FORT NORTH® City of Fort Worth
Change Order Request
Project Name E.Northside Dr.&Cold Springs Rd Roundabout City Sec# 55380
Client Project#(s) 101584
Project Description The project provides for the construction of a multi-lane roundabout at E.Northside Drive and Cold Springs Road intersection.
Contracto Reyes Group,Ltd. Change Order# 3 Date
City Project Mgr.I Shweta Rao City Inspector Habte Taezaz
Enter Department(s)to the Right and Contract Time
Contract Day Type Totals (CD)
Original Contract Amount $2,247,084.50 $2,247,084.50 260
Extras to Date 156
Credits to Date
Pending Change Orders(in M&C Process)
Contract Cost to Date $2,247,084.50 $2,247,084.50 416
Go to ADD&DEL Tabs to Enter CO Backup 34
Revised Contract Amount $2,247,084.50 $2,247,084.50450
Original Funds Available for Change Orders $0.00
Remaining Funds Available for this CO $0.00
Additional Funding(if necessary)
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 0.00%
MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $2,808,855.63
JUSTIFICATION(REASONS)FOR CHANGE ORDER
IN ACCORDANCE WITH THIS CONSTRUCTION CHANGE ORDER,THE CONTRACTOR SHALL:
Construction Time:
The contract was originally executed for 180 working days and change order 1 was executed to change it to calendar days.The construction start was delayed by 90
days due to revision and approval of Traffic Control Plan.These days were also added to the contract with Change Order 1 to update the notice to proceed date.This did
not include delay during construction.
Change order 2 added 60 days to construction duration due to delay in procurement of concrete and other site materials and also shortage of staff due to COVID
pandemic.
The contractor was trying to establish vegetation and in spite of watering on daily basis,the vegetation was not established due to severely hot weather conditions.The
contractor also experienced delays in receiving the materials for landscaping from the vendors.Even with the challenges experienced by the contractor on this project,
they opened the intersection for operation on June 3rd,which is within the originally allotted time duration for the project. This Change Order proposes to add 34 days to
the contract due to the above-mentioned vegetation supply-side circumstances and the unusually hot weather's impact on establishing vegetation..The landscaping
completed on June 14 and the TPW inspectors had a pre-final walk to prepare punch list on July 6.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in
full(both time and money)for all costs arising out of,or incidental to,the above Change Order. The Project/Program Manager signing below
acknowledges that he/she is the person responsible for the monitoring and administration of this contract,including ensuring all performance and
reporting requirements.
Contractor s Company Name Contractor(Name) Contract Signature Date
Reyes Group Ltd Marcos G Reyes MamosaR&ws Oct 28,2022
- ei Oc[ St1iC
Inspector/Inspection Supervisor Date Project and Contract Compliance Manager Date
Lo-(
Oct 28,2022 : Oct 28,2022
Program Manager Date Senior Capital Project Officer Date
.W&J2L _ Oct 29,2022 ..�� Oct 29,2022
Assistant Director(Dept) Date Director,Contracting Department(Dept) Date
Oct 31,2022rw Oct 31,2022
Assistant City Attorney Date Assistant City Manager Date
-WA Nov 2,2022 �-�+ Nov 2,2022
Council Action(if required)
M&C Number M&C Date Approved
ATTEST: pd�449�
,#yatta.0 rzy"u pAF°F OR r�aa
Jannette Goodall,City Secretary p��►O°° °Oo�.AddFFII, L RECORD
_� o
00o °Zd
8
*o a*�� CITY SECRETARY
d °
°00000000
dab.EXA`-�oAp
nan��a FT. WORTH, TX
FORT WORTH City of Fort worth
-1 v---- Change Order Additions
Project Name E.Northside Dr.&Cold Springs Rd Roundabout City Sec# 55380
Client Project# 101584
Contractor Reyes Group,Ltd. PM Shweta Rao InspectoF Habte Ta..
Change Order Submittal# O3 Date O
ADDITIONS
ITEM DESCRIPTION DEPT Qty Unit UnitCost Total
Sub Total Additions 0.00
Change Order Additions Page 2 of 5
F�>a�TH City of Fort worth
Change Order Deletions
Project Name E.Northside Dr.6 Cold Springs Rd Roundabout City Sec# 55380
Client Project# 101584
Contracto Reyes Group,Ltd. PM Shweta Rao Inspecto Habte Taezaz
Change Order Submittal# O3 Date O
DELETIONS
Unit ni s I otal
Sub TotalDeletions
Change Order Deletions Page 3 of 5
MISBE for this Change Order
M/SBE Sub Type of Service Amount for this CO
Total $0.00
Previous Change Orders
CO# DATE AMOUNT
1 11/3/2021 $0.00
2 4/18/2022 $0.00
Total $0.00
FORT WORTH.
Routing and Transmittal Slip
Transportation & Public Works
Department
DOCUMENT TITLE: Northside Dr at Cold Springs Roundabout
Project- Change Order 3
M&C: CPN: 101584 CSO: 55380 DOC#: 1
Date: 10/26/2022
To: Name Department Initials Date Out
1. Marcos Reyes, Contractor Reyes Gp Oct 28, 2022
2. Habte Taezaz, Inspector TPW Oct 28, 2022
3. Ariel Duarte, Sr. Inspector TPW o Oct 28, 2022
4. Shweta Rao, PM TPW S Oct 28, 2022
5. Lissette Acevedo, PgM TPW Oct 29, 2022
6. Lissette Acevedo, Interim Sr. CPO TPW Oct 29, 2022
7 Martin Phillips, Interim AD TPW Oct 31, 2022
8 Lauren Prieur, Interim Director TPW � Oct 31, 2022
9 Doug Black, Legal Legal ,�, Nov 2, 2022
10. William Johnson, ACM CMO ;. Nov 2, 2022
11. Janette Goodall, CSO CSO ,SG Nov 3, 2022
CC: Program Manager, Sr. CPO,TPW BSPAP Recon Team,TPW Records Room, TPW Contracts
DOCUMENTS FOR CITY MANAGER'S SIGNATURE: All documents received from any and all
City Departments requesting City Manager's signature for approval MUST BE ROUTED TO THE
APPROPRIATE ACM for approval first. Once the ACM has signed the routing slip, David will review
and take the next steps.
NEEDS TO BE NOTARIZED: ❑YES ®No
RUSH: ❑YES ®No SAME DAY: ❑YES ❑No NEXT DAY: ❑YES ❑No
ROUTING TO CSO: ®YES ❑No
Action Required: ❑ Attach Signature, Initial and Notary Tabs
❑ As Requested
❑ For Your Information
® Signature/Routing and or Recording
❑ Comment
❑ File