Loading...
HomeMy WebLinkAboutContract 56782-PM1F�RT����'H PI�()JEC 1 MANUAL FQR THE C�1�5TRUCTIQN �F 1VIEACHAM C'UMIVIEI�C:E C:ENTEI� IPI�C Record 1Vo.21-�](�26 Citv Prvject Nv. I03�U� FID �o. 30114-4�fl�431-1Q3��2-E07GS5 CSC Na. 56782-PM1 Mattie Parkcr Da�i� Caoke Mayc�r City Mana�er Ct�ri�t�pher P. Harcler, P,E. Director, Water IJepartment W ill ia�n Johnsan Directnr, Tran�pnrtatinn and Puhlic WnrkS L7epartment Prepared far The City nf Fnrt V4�orth TranSportat�on and Pu�lic Works Department December 2021 ��� ■■■ HALFF ��� 3803 Parkwood Blvd„ STE $QD Frisco, TX '15U34-$640 TBFE Firm l�io. F-312 �FFICIAL REC�RD CITY SECRETARY FT. W�RTH, TX .���� DF j'� [��� � �..�-� ..-�-� ��1r �* . *� %* * RDBERT E. G455ETT jf q :. 1 a7349 - . - - f����J1�F�n�G,'EN5� ��� l L-4 �—?.OrLI 00 00 00 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Page 1 of 5 CITY OF FORT WORTH Meacham Commerce Center STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN-103202 Revised March 20, 2020 SECTION 00 00 10 TABLE OF CONTENTS DEVELOPER AWARDED PROJECTS Division 00 - General Conditions Last Revised 00 11 13 Invitation to Bidders 03/20/2020 00 21 13 Instructions to Bidders 03/20/2020 00 41 00 Bid Form 04/02/2014 00 42 43 Proposal Form Unit Price 05/22/2019 00 43 13 Bid Bond 04/02/2014 00 45 11 Bidders Prequalification’s 04/02/2014 00 45 12 Prequalification Statement 09/01/2015 00 45 13 Bidder Prequalification Application 03/09/2020 00 45 26 Contractor Compliance with Workers' Compensation Law 04/02/2014 00 45 40 Minority Business Enterprise Goal 08/21/2018 00 52 43 Agreement 06/16/2016 00 61 25 Certificate of Insurance 07/01/2011 00 62 13 Performance Bond 01/31/2012 00 62 14 Payment Bond 01/31/2012 00 62 19 Maintenance Bond 01/31/2012 00 72 00 General Conditions 11/15/2017 00 73 00 Supplementary Conditions 07/01/2011 00 73 10 Standard City Conditions of the Construction Contract for Developer Awarded Projects 01/10/2013 Division 01 - General Requirements Last Revised 01 11 00 Summary of Work 12/20/2012 01 25 00 Substitution Procedures 08/30/2013 01 31 19 Preconstruction Meeting 08/30/2013 01 31 20 Project Meetings 07/01/2011 01 32 16 Construction Progress Schedule 07/01/2011 01 32 33 Preconstruction Video 08/30/2013 01 33 00 Submittals 08/30/2013 01 35 13 Special Project Procedures 08/30/2013 01 45 23 Testing and Inspection Services 03/20/2020 01 50 00 Temporary Facilities and Controls 07/01/2011 01 55 26 Street Use Permit and Modifications to Traffic Control 07/01/2011 01 57 13 Storm Water Pollution Prevention Plan 07/01/2011 01 58 13 Temporary Project Signage 04/07/2014 01 60 00 Product Requirements 03/20/2020 01 66 00 Product Storage and Handling Requirements 04/07/2014 01 70 00 Mobilization and Remobilization 04/07/2014 01 71 23 Construction Staking and Survey 04/07/2014 01 74 23 Cleaning 04/07/2014 01 77 19 Closeout Requirements 04/07/2014 01 78 23 Operation and Maintenance Data 04/07/2014 01 78 39 Project Record Documents 04/07/2014 00 00 00 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Page 2 of 5 CITY OF FORT WORTH Meacham Commerce Center STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN-103202 Revised March 20, 2020 Technical Specifications listed below are included for this Project by reference and can be viewed/downloaded from the City’s website at: http://fortworthtexas.gov/tpw/contractors/ or https://apps.fortworthtexas.gov/ProjectResources/ Division 02 - Existing Conditions Last Revised 02 41 13 Selective Site Demolition 12/20/2012 02 41 14 Utility Removal/Abandonment 12/20/2012 02 41 15 Paving Removal 02/02/2016 Division 03 - Concrete 03 30 00 Cast In Place Concrete 12/20/2012 03 34 13 Controlled Low Strength Material (CLSM) 12/20/2012 03 34 16 Concrete Base Material for Trench Repair 12/20/2012 03 80 00 Modifications to Existing Concrete Structure 12/20/2012 Division 26 - Electrical 26 05 00 Common Work Results for Electrical 11/22/2013 26 05 10 Demolition for Electrical Systems 12/20/2012 26 05 33 Raceways and Boxes for Electrical Systems 12/20/2012 26 05 43 Underground Ducts and Raceways for Electrical Systems 07/01/2011 26 05 50 Communications Multi Duct Conduit 02/26/2016 Division 31 - Earthwork 31 10 00 Site Clearing 12/20/2012 31 23 16 Unclassified Excavation 01/28/2013 31 23 23 Borrow 01/28/2013 31 24 00 Embankments 01/28/2013 31 25 00 Erosion and Sediment Control 12/20/2012 31 36 00 Gabions 12/20/2012 31 37 00 Riprap 12/20/2012 Division 32 - Exterior Improvements 32 01 17 Permanent Asphalt Paving Repair 12/20/2012 32 01 18 Temporary Asphalt Paving Repair 12/20/2012 32 01 29 Concrete Paving Repair 12/20/2012 32 11 23 Flexible Base Courses 12/20/2012 32 11 29 Lime Treated Base Courses 12/20/2012 32 11 33 Cement Treated Base Courses 12/20/2012 32 11 37 Liquid Treated Soil Stabilizer 08/21/2015 32 12 16 Asphalt Paving 12/20/2012 32 12 73 Asphalt Paving Crack Sealants 12/20/2012 32 13 13 Concrete Paving 12/20/2012 32 13 20 Concrete Sidewalks, Driveways and Barrier Free Ramps 06/05/2018 32 13 73 Concrete Paving Joint Sealants 12/20/2012 32 14 16 Brick Unit Paving 12/20/2012 32 16 13 Concrete Curb and Gutters and Valley Gutters 10/05/2016 00 00 00 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Page 3 of 5 CITY OF FORT WORTH Meacham Commerce Center STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN-103202 Revised March 20, 2020 32 17 23 Pavement Markings 11/22/2013 32 17 25 Curb Address Painting 11/04/2013 32 31 13 Chain Fences and Gates 12/20/2012 32 31 26 Wire Fences and Gates 12/20/2012 32 31 29 Wood Fences and Gates 12/20/2012 32 32 13 Cast in Place Concrete Retaining Walls 06/05/2018 32 91 19 Topsoil Placement and Finishing of Parkways 12/20/2012 32 92 13 Hydro-Mulching, Seeding, and Sodding 12/20/2012 32 93 43 Trees and Shrubs 12/20/2012 Division 33 - Utilities 33 01 30 Sewer and Manhole Testing 12/20/2012 33 01 31 Closed Circuit Television (CCTV) Inspection 03/03/2016 33 03 10 Bypass Pumping of Existing Sewer Systems 12/20/2012 33 04 10 Joint Bonding and Electrical Isolation 12/20/2012 33 04 11 Corrosion Control Test Stations 12/20/2012 33 04 12 Magnesium Anode Cathodic Protection System 12/20/2012 33 04 30 Temporary Water Services 07/01/2011 33 04 40 Cleaning and Acceptance Testing of Water Mains 02/06/2013 33 04 50 Cleaning of Sewer Mains 12/20/2012 33 05 10 Utility Trench Excavation, Embedment, and Backfill 12/12/2016 33 05 12 Water Line Lowering 12/20/2012 33 05 13 Frame, Cover and Grade Rings Cast Iron 01/22/2016 33 05 13.10 Frame, Cover and Grade Rings Composite 01/22/2016 33 05 14 Adjusting Manholes, Inlets, Valve Boxes, and Other Structures to Grade 12/20/2012 33 05 16 Concrete Water Vaults 12/20/2012 33 05 17 Concrete Collars 12/20/2012 33 05 20 Auger Boring 12/20/2012 33 05 21 Tunnel Liner Plate 12/20/2012 33 05 22 Steel Casing Pipe 12/20/2012 33 05 23 Hand Tunneling 12/20/2012 33 05 24 Installation of Carrier Pipe in Casing or Tunnel Liner Plate 06/19/2013 33 05 26 Utility Markers/Locators 12/20/2012 33 05 30 Location of Existing Utilities 12/20/2012 33 11 05 Bolts, Nuts, and Gaskets 12/20/2012 33 11 10 Ductile Iron Pipe 12/20/2012 33 11 11 Ductile Iron Fittings 12/20/2012 33 11 12 Polyvinyl Chloride (PVC) Pressure Pipe 11/16/2018 33 11 13 Concrete Pressure Pipe, Bar Wrapped, Steel Cylinder Type 12/20/2012 33 11 14 Buried Steel Pipe and Fittings 12/20/2012 33 12 10 Water Services 1-inch to 2-inch 02/14/2017 33 12 11 Large Water Meters 12/20/2012 33 12 20 Resilient Seated Gate Valve 12/20/2012 33 12 21 AWWA Rubber Seated Butterfly Valves 12/20/2012 33 12 25 Connection to Existing Water Mains 02/06/2013 33 12 30 Combination Air Valve Assemblies for Potable Water Systems 12/20/2012 33 12 40 Fire Hydrants 01/03/2014 33 12 50 Water Sample Stations 12/20/2012 00 00 00 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Page 4 of 5 CITY OF FORT WORTH Meacham Commerce Center STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN-103202 Revised March 20, 2020 33 12 60 Standard Blow off Valve Assembly 06/19/2013 33 31 12 Cured in Place Pipe (CIPP) 12/20/2012 33 31 13 Fiberglass Reinforced Pipe for Gravity Sanitary Sewers 12/20/2012 33 31 15 High Density Polyethylene (HDPE) Pipe for Sanitary Sewer 12/20/2012 33 31 20 Polyvinyl Chloride (PVC) Gravity Sanitary Sewer Pipe 06/19/2013 33 31 21 Polyvinyl Chloride (PVC) Closed Profile Gravity Sanitary Sewer Pipe 12/20/2012 33 31 22 Sanitary Sewer Slip Lining 12/20/2012 33 31 23 Sanitary Sewer Pipe Enlargement 12/20/2012 33 31 50 Sanitary Sewer Service Connections and Service Line 04/26/2013 33 31 70 Combination Air Valve for Sanitary Sewer Force Mains 12/20/2012 33 39 10 Cast-in-Place Concrete Manholes 12/20/2012 33 39 20 Precast Concrete Manholes 12/20/2012 33 39 30 Fiberglass Manholes 12/20/2012 33 39 40 Wastewater Access Chamber (WAC) 12/20/2012 33 39 60 Epoxy Liners for Sanitary Sewer Structures 12/20/2012 33 41 10 Reinforced Concrete Storm Sewer Pipe/Culverts 07/01/2011 33 41 11 High Density Polyethylene (HDPE) Pipe for Storm Drain 12/20/2012 33 41 12 Reinforced Polyethlene (SRPE) Pipe 11/13/2015 33 46 00 Subdrainage 12/20/2012 33 46 01 Slotted Storm Drains 07/01/2011 33 46 02 Trench Drains 07/01/2011 33 49 10 Cast in Place Manholes and Junction Boxes 12/20/2012 33 49 20 Curb and Drop Inlets 12/20/2012 33 49 40 Storm Drainage Headwalls and Wingwalls 07/01/2011 Division 34 - Transportation 34 41 10 Traffic Signals 10/12/2015 34 41 10.01 Attachment A Controller Cabinet 12/18/2015 34 41 10.02 Attachment B Controller Specification 02/2012 34 41 10.03 Attachment C Software Specification 01/2012 34 41 11 Temporary Traffic Signals 11/22/2013 34 41 13 Removing Traffic Signals 12/20/2012 34 41 15 Rectangular Rapid Flashing Beacon 11/22/2013 34 41 16 Pedestrian Hybrid Signal 11/22/2013 34 41 20 Roadway Illumination Assemblies 12/20/2012 34 41 20.01 Arterial LED Roadway Luminaires 06/15/2015 34 41 20.02 Freeway LED Roadway Luminaires 06/15/2015 34 41 20.03 Residential LED Roadway Luminaires 06/15/2015 34 41 30 Aluminum Signs 11/12/2013 34 41 50 Single Mode Fiber Optic Cable 02/26/2016 34 71 13 Traffic Control 11/22/2013 00 00 00 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Page 5 of 5 CITY OF FORT WORTH Meacham Commerce Center STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN-103202 Revised March 20, 2020 Appendix GC 4.01 Availability of Lands GC 4.02 Subsurface and Physical Conditions GC 4.04 Underground Facilities GC 4.06 Hazardous Environmental Condition at Site GC 6.06.D Minority and Women Owned Business Enterprise Compliance GC 6.07 Wage Rates GC 6.09 Permits and Utilities GC 6.24 Nondiscrimination GR-01 60 00 Product Requirements END OF SECTION 00 42 43 DAP - BID PROPOSAL Page 1 of 1 1 3305.0109 Trench Safety 33 05 10 LF 303 $1.00 $303.00 2 3312.2204 2" Private Water Service 33 12 10 LF 134 $58.00 $7,772.00 3 3311.0261 8" PVC Water Pipe 33 11 12 LF 97 $49.00 $4,753.00 4 3311.0461 12" PVC Water Pipe 33 11 12 LF 72 $92.00 $6,624.00 5 3312.0117 Connection to Existing 4"-12" Water Main 33 12 25 EA 2 $1,000.00 $2,000.00 6 3312.3003 8" Gate Valve 33 12 20 EA 2 $1,400.00 $2,800.00 7 3312.3004 10" Gate Valve 33 12 20 EA 1 $1,800.00 $1,800.00 8 3312.3005 12" Gate Valve 33 12 20 EA 2 $2,300.00 $4,600.00 9 3311.0001 Ductile Iron Water Fittings w/ Restraint 33 11 11 TON 1 $1,400.00 $1,400.00 10 9999.0004 Automatic Flusher 99 99 04 EA 1 $4,200.00 $4,200.00 11 3305.0109 Trench Safety 33 05 10 LF 1414.5 $1.00 $1,414.50 12 3301.0002 Post-CCTV Inspection 33 01 31 LF 1414.5 $2.00 $2,829.00 13 3301.0101 Manhole Vacuum Testing 33 01 30 EA 5 $100.00 $500.00 14 3305.3001 6" Sewer Carrier Pipe 33 05 24 LF 45.5 $30.00 $1,365.00 15 3305.3002 8" Sewer Carrier Pipe 33 05 24 LF 1369 $36.00 $49,284.00 16 3339.0001 Epoxy Manhole Liner 33 39 60 VF 66 $450.00 $29,700.00 17 3339.1001 4' Manhole 33 39 10 EA 5 $9,000.00 $45,000.00 18 9999.0006 Connect to Existing Manhole 99 99 06 EA 1 $1,600.00 $1,600.00 This Bid is submitted by the entity named below: BIDDER:BY: Rumsey Construction 4329 Reeder Dr Carrolton, TX 75010 TITLE: DATE: 90 END OF SECTION TOTAL UNIT IV: PAVING IMPROVEMENTS UNIT VI: TRAFFIC SIGNAL IMPROVEMENTS $167,944.50Total Construction Bid UNIT VI: TRAFFIC SIGNAL IMPROVEMENTS UNIT IV: PAVING IMPROVEMENTS UNIT V: STREET LIGHTING IMPROVEMENTS $131,692.50 TOTAL UNIT V: STREET LIGHTING IMPROVEMENTS $36,252.00 UNIT II: SANITARY SEWER IMPROVEMENTS UNIT III: DRAINAGE IMPROVEMENTS Bid Summary UNIT I: WATER IMPROVEMENTS VP of Preconstruction Corey Caughron Contractor agrees to complete WORK for FINAL ACCEPTANCE within working days after the date when the CONTRACT commences to run as provided in the General Conditions. Description TOTAL UNIT I: WATER IMPROVEMENTS $36,252.00 Bid Quantity UNIT III: DRAINAGE IMPROVEMENTS UNIT II: SANITARY SEWER IMPROVEMENTS TOTAL UNIT VI: TRAFFIC SIGNAL IMPROVEMENTS Specification Section No. Unit of Measure UNIT I: WATER IMPROVEMENTS UNIT V: STREET LIGHTING IMPROVEMENTS Bidlist Item No. SECTION 00 42 43 Developer Awarded Projects - PROPOSAL FORM UNIT PRICE BID TBA UNIT IV: PAVING IMPROVEMENTS Unit Price Bid Value Project Item Information Bidder's Proposal TOTAL UNIT II: SANITARY SEWER IMPROVEMENTS $131,692.50 TOTAL UNIT III: DRAINAGE IMPROVEMENTS CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS Form Version May 22, 2019 00 42 43_Bid Proposal_DAP 081121 12/07/21 00 45 12 DAP PREQUALIFICATION STATEMENT Page 1 of 1 CITY OF FORT WORTH Meacham Commerce Center STANDARD CONSTRUCTION PREQUALIFICATION STATEMENT – DEVELOPER AWARDED PROJECTS CPN-103202 Form Version September 1, 2015 SECTION 00 45 12 DAP – PREQUALIFICATION STATEMENT Each Bidder is required to complete the information below by identifying the prequalified contractors and/or subcontractors whom they intend to utilize for the major work type(s) listed. In the “Major Work Type” box provide the complete major work type and actual description as provided by the Water Department for water and sewer and TPW for paving. Major Work Type Contractor/Subcontractor Company Name Prequalification Expiration Date Water/Sewer: All sizes in diameter. Rumsey Construction 04/30/2022 The undersigned hereby certifies that the contractors and/or subcontractors described in the table above are currently prequalified for the work types listed. BIDDER: Rumsey Construction BY: Corey Caughron 4329 Reeder Dr Carrolton, TX 75010 _________________________________________ (Signature) TITLE: VP of Pre-Construction DATE: END OF SECTION 12/07/21 DO 45 ?5 - I CONTRACTOR COMPLIANCE WiTH WOKKER'S CQMPENSATiON LAW Page 1 of 1 2 3 4 5 b 7 S 9 10 11 12 13 14 15 lb 17 18 19 20 Z1 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 SECTION 00 45 26 CONTRACTOR COMPLIANCE W1TH WORKER'S COMPENSATION LAW Pursuant to Texas Labor Code Section 406.09fi(a), as amcnded, Contractor certifies that it provides worker's corr�pensation insurance coverage for all of its employees erz�ployed on City Project No. I03202. Contractor further certifics khat, pursuant to Texas Labor Code, SecCion 406.096(b), as amended, it will provide ta City its subcontractor's certificaies of coin�liance with wprker°s compensation coverage. CONTRACTOR: Rumsey Construction . Company �329 Reeder Dr Address Carrolltoz�, TX 75010 City/State/Zip THE STATE OF TEXAS COUNTY OFTARRANT § § By: Corey Cau�hran (P .eP �nt� _. H �I Signature: ` Title: VP of Preconstruction (Please Frint) SEFORE ME, the nders� ❑ed authority, on this day personally appeared �] /'O n , known to me to be the person whose r�ame is subscribed to e fore o� g instrument and acknowledged to me that he/she executed the same as the act and deed of m n ` for the purposes and consicEeration therein expressed and in the capacity therein stated. GIVEN [�NDER MY HAND AND SEAL OF OF�ICE this day of �P�-P�,r-.�.rr- , 20� �.�``R`r` `P"�., NA N CY W E 5T , ota....._a,�. �x. ;��Notary Pul�lic, 5tate of T�xas y`�':�'�� Camm. Expires 05-17-2024 �v�'.•...fi. �. �`l�rilit+��� Noiery lb 1994783 � Notary Public in and r the State of Texas END OF SECTION CITY OF PORT W'ORTH STANI]Al2D C�NSTRUCTiON SPECiFICATION DOCUIvl�lt'TS Revised Aprii 2, 2O14 Mecich¢nz Commerce Center CPN-103202 0452�3-i Developer Awarded Project Agreement Page 1 af 4 SECTIUN aa 52 43 2 3 4 5 6 7 AGI�EEMENT THIS AGREElI'IENT, authariaed an 1217l2D21 is made by and between the De�elaper, (Meacltartt MC I, L�C}, authoriaed to da business in Texas ("De�elaper"} , and Idumsey Construction, authariaed ta da l�usiness in Texas, acting by and through its duly authoriaed representative, {"Contractor"). $ De�eloper and Contractor, in consideration af the inutual cowenants hereinafter set forth, agree as 9 follows: 10 �rticle 1. WORK 11 12 13 14 15 16 17 18 19 2U 21 Cantractor shall camplete all Work as speeified or indicated in the Cantract �ocuments far the Praject identified herein. Article 2. PR�,]ECT The project for which the Work ui�der the Contract Dacuinents may be the whole or only a part is generally described as follows: Meacham Cnrizrrzerce Center CPN-103202 Article 3. COlYTRACT TI1�iE 3.1 Time is af the essenee. All time liinits for Milestones, if any, aiid Final Acceptaiice as stated in the Contract Documents are of the essence to this Contract. 22 3.2 Final Acceptance. 23 The Wvrk will lae cvmplete for Final Acceptance within 90 working days after the date 24 when the Cantract Time coinmences to run as pro�ided in Paragraph 12.44 of the Standard 25 City Coiiditians of the Constructian Cantract far �eveloper Awarded Projects. 26 3.3 Liquidated damages 27 28 29 30 31 32 33 34 35 36 37 Cantractvr recvgniaes that time is of the essence of this Agreeineirt and that De�eloper will suffer financial loss if the Work is not completed within the times specified in Paragraph 3.2 above, plus any extension thereaf allowed in accardance with Article ]4 of the 5taiidard City Canditions af the Canstructian Contract far Develaper Awarded Prajects. The Contractor also recogiiiaes the delays, expense and difiiculties iii�ol�ed iii prawing in a legal proceeding the actual loss suffered by the develaper if the Wark is not completed an tiine. Accordingly, instead of requiring aiiy such proof , Cantractor agrees that as liquidated dainages for delay (l�ut not as a penalty}, Cantractar shall pay De�eloper Five Hundred �oddars and Zero Cer�ts ($500.Oai for each day that expires after the time specified in Para�raph 3.2 for Final Acceptance until the City issues the Final L,etter of Acceptance. CTTY OF F�RT WORTH Meachum Commerre Center STAIYDARD CONSTRUCTIflN SPECIFICATIdN DOCUMENTS — DEVELOPER AWARDED FRfl.lECTS CPN-I03202 Revised Iune 1G, 2Ulb 00 52 43 - 2 Developer Awarded Project Agreement Page 2 of 4 CITY OF FORT WORTH Meacham Commerce Center STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN-103202 Revised June 16, 2016 Article 4. CONTRACT PRICE 38 Developer agrees to pay Contractor for performance of the Work in accordance with the Contract 39 Documents an amount in current funds of One hundred sixty seven thousand, nine hundred and 40 forty-four dollars and fifty cents ($167,944.50). 41 Article 5. CONTRACT DOCUMENTS 42 5.1 CONTENTS: 43 A. The Contract Documents which comprise the entire agreement between Developer and 44 Contractor concerning the Work consist of the following: 45 1. This Agreement. 46 2. Attachments to this Agreement: 47 a. Bid Form (As provided by Developer) 48 1) Proposal Form (DAP Version) 49 2) Prequalification Statement 50 3) State and Federal documents (project specific) 51 b. Insurance ACORD Form(s) 52 c. Payment Bond (DAP Version) 53 d. Performance Bond (DAP Version) 54 e. Maintenance Bond (DAP Version) 55 f. Power of Attorney for the Bonds 56 g. Worker’s Compensation Affidavit 57 h. MBE and/or SBE Commitment Form (If required) 58 3. Standard City General Conditions of the Construction Contract for Developer 59 Awarded Projects. 60 4. Supplementary Conditions. 61 5. Specifications specifically made a part of the Contract Documents by attachment 62 or, if not attached, as incorporated by reference and described in the Table of 63 Contents of the Project’s Contract Documents. 64 6. Drawings. 65 7. Addenda. 66 8. Documentation submitted by Contractor prior to Notice of Award. 67 9. The following which may be delivered or issued after the Effective Date of the 68 Agreement and, if issued, become an incorporated part of the Contract Documents: 69 a. Notice to Proceed. 70 b. Field Orders. 71 c. Change Orders. 72 d. Letter of Final Acceptance. 73 74 75 00 52 43 - 3 Developer Awarded Project Agreement Page 3 of 4 CITY OF FORT WORTH Meacham Commerce Center STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN-103202 Revised June 16, 2016 Article 6. INDEMNIFICATION 76 6.1 Contractor covenants and agrees to indemnify, hold harmless and defend, at its own 77 expense, the city, its officers, servants and employees, from and against any and all 78 claims arising out of, or alleged to arise out of, the work and services to be performed 79 by the contractor, its officers, agents, employees, subcontractors, licenses or invitees 80 under this contract. This indemnification provision is specifically intended to operate 81 and be effective even if it is alleged or proven that all or some of the damages being 82 sought were caused, in whole or in part, by any act, omission or negligence of the city. 83 This indemnity provision is intended to include, without limitation, indemnity for 84 costs, expenses and legal fees incurred by the city in defending against such claims and 85 causes of actions. 86 87 6.2 Contractor covenants and agrees to indemnify and hold harmless, at its own expense, 88 the city, its officers, servants and employees, from and against any and all loss, damage 89 or destruction of property of the city, arising out of, or alleged to arise out of, the work 90 and services to be performed by the contractor, its officers, agents, employees, 91 subcontractors, licensees or invitees under this contract. This indemnification 92 provision is specifically intended to operate and be effective even if it is alleged or 93 proven that all or some of the damages being sought were caused, in whole or in part, 94 by any act, omission or negligence of the city. 95 96 Article 7. MISCELLANEOUS 97 7.1 Terms. 98 Terms used in this Agreement are defined in Article 1 of the Standard City Conditions of 99 the Construction Contract for Developer Awarded Projects. 100 7.2 Assignment of Contract. 101 This Agreement, including all of the Contract Documents may not be assigned by the 102 Contractor without the advanced express written consent of the Developer. 103 7.3 Successors and Assigns. 104 Developer and Contractor each binds itself, its partners, successors, assigns and legal 105 representatives to the other party hereto, in respect to all covenants, agreements and 106 obligations contained in the Contract Documents. 107 7.4 Severability. 108 Any provision or part of the Contract Documents held to be unconstitutional, void or 109 unenforceable by a court of competent jurisdiction shall be deemed stricken, and all 110 remaining provisions shall continue to be valid and binding upon DEVELOPER and 111 CONTRACTOR. 112 7.5 Governing Law and Venue. 113 This Agreement, including all of the Contract Documents is performable in the State of 114 Texas. Venue shall be Tarrant County, Texas, or the United States District Court for the 115 Northern District of Texas, Fort Worth Division. 116 I1052�i-�{ T]e v el ���x r A war�ie�l Pru jcc t A� rec n wu � Fc�w �1 cJ 4 ��7 118 7.6 Autharity to Sigr�. 11� 12 t] 121 122 123 124 125 12 C, Contra�tor shall attach evidence of authority to Sigzt Agreemerlt, if nther than duly authori�ed si�natory af the Contractor. 1N WITNESS WHERE�F, I]e�elaper and C�nt�actor ha�e executed this A�reement in rnul�iple counterparts. This Agrccment is effecti�e as of the last datc si�n�d by thc Pa~tics {"Effectiv� �ate"). 1�Tea�ham MC l, LLC, a[ exas limited liability cornpany Contra�tnr� I]�Weln�er� By: LSG LAN�, LLC, a Texas limitcd liabilit} company, its Manager B � . �-� - - gr_aturc} � � Corey Caughron (Pi�inte•� Name) Title: 4'P af Precc�nstructic�n ('ompany 1Vame: Kumsey L'anstruction Addres>: 432'� Rccdcr Dr. By, o�-..-� 1r� � � (Signature} Daniel P. McCanna�k (Printed Namej Title: Sale Member C�7mpany name: Meacham MC l, LLC A�dress: 13L]3 C:amnbell Road CitylStatelZip: CdrrDlt�n, TX 75U1� CitylStateJ�ip: Houston, TK ?7Q55 Date : 121712D21 L7;3te: 1217/2021 CITY OF F�RT WpRTH +l7cuchntr� Corir�ire�re Cerrrcr STANDARD CD�ISTRtiCTIUN SPECIFICAT;�N D�CUNIENTS — DEVEL�FER ,�W,ARDED PROdECTS CPN-l032�2 R1:V11L'(� .TUfll' 1G, 2D16 QOfi2 ]3-1 PERFORMAI�CL:1301VD P;i„c 1 oF 2 1 2 3 4 5 6 7 S 9 1� il 12 1 "i �� 15 1 fi 17 18 19 20 21 22 Txr sT�� or T�xAs C�UNTY QF TARRANT SECTIDI1i (!0 62 13 8ond No. 5d-240166 Pf�I�PC]R1+IA�I€:E I3C3ND � § KNUW ALI, RY THk:SF PRESF,NTS: � That we, Rumsey C:onstruction; known as °`Principal" hcrein and United Fir� & Casualty Company , a Colps�rate sur�ty(Sui'etiCS, if nnore than one) duly autho�i�ed tv da business in the St�te c�f' T��as, knr�wn as "Surcty" hcreirt {ti�,'I1Ci�lC1' pIlC or rn��re}, are hcld and i'irmly hound unto thc I?�vcloper, Ahru Realty, Inc., authoria�d to do fa+�siness in 'I'exas ("Develop�r") azici tti� City af' Fc�rl V4'carth, a T�.x�ti rnu�iic:ip�il c��rpnraticm ("City"), in thG pcna] tiurn of', U�ii 1fr•rrtcl�'��d 5ix � 5'et+r.•►t Tltr1«s•�trr�l. ,�lrrie N[utd►•ed Attd f n+'h�-Foi��' Dnflri�a A��d f�i�>> Cc��rr.s (,$IG7,9�4.5�], law#'ul tnoney c�f tt�� [;riitcd Stat.cs, tU be paid ir� ]���rl Wnrth, Tari-anl C�unty, '1'cxas for �h� puyment of which sum u°ell and truly to be made jnintly untcf the I]cvclop�r and the City as duai c�bli�ecs, we. hind ourselves, our heirs, execulors, administratc7rs, successnrs and assigns, jr�intly and scv�rally, firmiy hy thc5c pr�ti�nl5. Wf;FR�:AS, I]cvcloper and City have entered into an Agreement fcar the canstruction of Corrun�uzity f'acilitics in �hc Ciiy of Foxt W'c�rth by and through a C:ornii�ut�ity I�acilities Agreernent, C:f �A Nun�ber 21-Q[)8fi; and WF�F.RFAS, the Pr�ncipal h�s entered into a certain writtcn coritrac:t wiltr thc �cwcle�per a�varded �e �th ���, of De�ernher a?�}21 , which Contraci is hereby reFerred to and m�de a 23 part herec�f f�t�r �11 purpnse5 u5 if fully Set forkh herein, to fumish all matenals, equi�ment labor 24 and athcr accessvrics defincd by ]a���; in the prosecutiori nf' thc Wvrk, inc�uding any Change 25 Drders, a5 prn�ided fnr in Said Conl.ract dcsi�nated as h�eachatn Corn�r�erce Cenler. 26 N�W, THERFFORF,, the cc�ndition of k.his obligatian is such that it ttic said Principal 27 5ha11 faithfulI;� �erfnrnl it ohligatinn5 iitlder the Contract and sh�ll in all respccts duly aric� 2$ faithfully perfarrri Ltie ��Vc3rk, incltidin� Chan€e C7rders, under t.he C'ontract, accardin� ta thc plans, 29 specifications, and contract documents ihcrcin rcf'crr�d lo, and ati well �iuring any perind of �a 31 vxtcn5ion pf the Contracl tha� rnay be granted on the �art of the De�eloper andfor City, #�en this vbligation sha�l be and became null and vnid, ❑therwise ta remain in fu11 force and efFect. C iTY Ol" [�Olt'C ��'i lR7 H Meu�:lturr� Cununerr e{;e��rr� 5'1'�1yIJAR]] C'I"I'Y ['[INI�lT10N5 — AEVELOPER AWA1�nCn PRpIECTS CPN-f03202 Rcti iticd lanuary :i i, 2[}12 nnr,z�:,-z E�r:�tHo�n��nvt�r: �r��ry I'a�e 2 n I 2 1'IIn�'IllL+'U I+ UR�I'HER, that i£ any legal aiticfn }�e filed on this Bond, venue sk�all lie in 2 Tarrant Cc�unty, Texas csr the United SLates iJiStrict {-:nurt fnr the Nnrthern District of'f'exas, Fort 3 Wo��th Di�isivn. 4 This band is made ant! exec�itcd in complianc� wit.�i t.hc �r�visions of Chapter 2253 af the 5 Texas Gn�crniti�nt C'ndc, a5 ani�ndcd, anci all li�ihililies on t.his bond shalE he determined in 6 accordance with the prnvisic�ns of said statue. 7 IN WITVL+',SS WH�;R�[}F, th� Principal and the Surety have ,S1GIVF;TI anci S�:A1,T?I7 8 Lhis iti5tiuni�nt hy �iuly authori�c�i a�cntti ar�cl nffi�crs �m It�is tfie gth day of 4 in jY 12 13 14 1s i� 1� �s 19 20 2Z 22 23 24 25 2fi 27 2g 29 3Q 31 32 33 34 35 3� 37 38 39 4U 41 42 43 44 45 4fi Decemher � 2[} 29 ATTEST: fYrin�i}�al} SccrcEary Wil=�esti as tc� Frincipal .r -�����. �� _ .. . _ . �_ -• a L9�. Witness as t� SE�reiy �utNc�i�nL: Rum=ey Const�ucti�n, fnC, Bi': � n: C� Cau,�,l�rc�n, Vl' uF Preconstruction tiiamz �tnd Tit1e AddreSs; 432�1 F�eeder I]r [:an-olltan TX 75{]1{) SURETY: Vni[ed Fire & sually Company F3Y: .. ._ _ 5i�nature A�lys❑� �ean-1Nest,A!lorn�j-ln-laCt I�Tame and Titic Address: '12�OD Park Central Drive, #14d0 �allas, TX 7525� I'elephone IVumher� z14•221-8306 �Note: lf signed by an nf���r rrf the 5urety ['c�mpany, tt3�r� rnust. h� rm fi]c a ccrt.if'icd cxtract. f'rnm t�e hy-law5 shor�•ing lhal this person has authnrity tn sign such nhligatinn. If 5urety's ph}�sical address is different frnrrf its mailing addre55, he�i� mus! bt; pr�vided. The date of the hond sha�l not he �7rinr tn thc datc tfic C'«Titr��t i5 �warded. CII'Y f)F F�RT W(7RTH M�urhr�rn (:ommerce Cenfer S' l�h V I),1 R 1) C I'1'Y � ONDITiClNS — dEVELOPER AWARDEf] PR C].TFCTS C'PIti -1032(1? He��isc:i Jeir.u�ry 3l , 2� 12 {l� 62 l4 1 PAYM�:nT AC3fi❑ Y<<gc 1 aF2 1 2 3 4 5 6 7 'I'H�: S'1'�'�'E QF '1'FKAS CUi.)1�ITY UF TARRr#NT SF.CTION {1[f 62 14 Bond Nfl. 54-2401fi6 PAY1•1EIVT F3aNll $ § K!tiQl'V ALL BY THFSF PRF.51:1�1'I'5: § 8 That �ve, Rumsey Cc�nstructican, known as "I'riiicipal" herein, and 4 lJnited Fire & Casualty Company , a �orporate surety ( or 10 sureties if rnare lhan one), duly aulhoriccd to do business in the Slule af Texas, knnwri s� 11 "Surety" herein {whether one or n�n�e), are held and firmly baund unto the De�eloper, A6ra 12 Realty, I�e., autharized to do busin�ss vn Texas "{Developer"), and the City of Fort Worth, a 13 Texas muniClpal cc3rporation {"Cii.y"}, in the pcn+tl tiizrrt c�f t)r�c lltr�tdrrrl 5i��r��-S'�>>�rr T hnirsancf, 14 Niirc H�.rirdrrrd .4rac1 Fr�rr�+-rr�i.rr- L]allars Arrd f'r€�t3r Ceirls f�167,9��..50}_ �a�vltil money of the 15 Unitcd 5tates, tn he �aid in Fort Wnrt.h, '[�arrant Cnunty, Cexas, fnr thc payrntmt vf �vhi�h s�m lfi well and kre�ly he rnade jninlly unto the I]cv�lopc:r and the City as dual obligees, we hind 17 ourscl�cs, c�ur heirs, executors, administratar5, Sixccessors and assigns, jaintly and se�erally, 1R firmly ny the�e prc5cnt5: ]9 WNFRTAS, De�e�nper and City have entered into an Agreement fvr the canstrt�ction of 20 c�mmuriity fucilitics in th� City nf Fart Worth, by and thirough a Carrtmunity Facilities 21 !�grecment, CFA �Iumber 21-0{}H[i; and 22 WH�;I�N:AS� Principal has entercd into a cGr[ain writt.cn C'.ontract with ❑cveloper, 23 awarded the 7�' da of ae�mber 2�} 21 y , which C:c�ntract is herehy� 24 refcrrcd to and made a part heres�i' far all purpvses as if' f'u1Iy set fc�rth hercin, ta furnish a11 25 materials, equipment, lahor and other a�cessories as defined by law, in the prasecution of the 25 Work as provided for in sdid Contract and desi�nate[i as �'1�leachum Cammer'ce Certter. 27 N�4'V, TH�:RI:I�'QRI:, THE CONDITION Of�� '1'HiS �F3[.IGATIDlti iti such that if 28 Principal shall pay all monies owing to any {and all) pa}'�ninl' hand hcnef'iciary (as defined in 29 Chaptcr 2253 ca[' khe Texas Governrn�nt Cade, as arnended) in the prosecutinn of the Work under 30 khe Cotltract, then this abIigatinn shall bc and hGcnm� nu21 and �oid; c�thcrwisc tca r�main in 1'uli 31 force azid cff'ec�. C:I'I'Y OF'rOR-I Wt3RI'Ii .blf�nchum C:r�ininrrc� ('r'nler 5TI1NL7ARll Ci1"Y Cbiti1)1-I'lUNS L]f:VfiLIJI'Lsft AWAHIII:I] F'KC]J}i[_:f5 C'PN-fl1.32�2 Aevised ,Ianuary 31, 24 i 2 nn rz i� z FAYM�!!'I' RUNi] I'a ge 2 aF 2 ] 2 3 This bond is mad� and executed in cotnp�iance with the pra�+isions nf Cha�xter 2253 nf the Texas Got�ern�nent Cnde, :3s a�nended, and all liabilities on this harid st�all hc dct�rmin,ed in accord,snce with the prnvisir�ris �f said statut�. A IN WITNESS WH�REQF, tii� Principal and Sti�rcty ha�+e each SIC�vLll and SEALED S this inslruiri�r►t hy duly auth[�rized agents and officerti on this the.9th day uf 6 7 aecember r 2�} 21 PRII�ICIPAI.: Rumsey Construction, Inc. F31': Si�na a Carcy Ca�i�*hrc�n, VP oF I'��s�w�struction I�'ame and Title ATTEST; (�'rin�ipal) Se�cretary Witne .. as t� Principal ATTEST: N!A {Surety} Sacretary Address: 432{� Heeder I]r Ca��rolltnn, TX 75(]1(] Si:RE�.1�Y� United Fire 8. Casuaity Gompany B Y: �� Si�nature Allyson �ean est, Attorney-In-fact Name �na Title '�`�-� Acicire�5: 12�0� Park Central Dri�a, #1440 C7al�as, Tx 75251 (�'}]� �. Witne.ss as to 5t� ty 8 9 �a 11 12 13 14 Telephane Nurnher: ��4-221-83Dfl l�e�te; Ii' si�n�d by an ❑i'f'icer of rthc Surcl.y, �herc mtzst l�c ❑n file a ccrtificd cxtra[:t frnm the bylaws showing that tl3is pers�n tia5 autht�rity to sign such �ahligativn. If Surety's physical ac]�ire55 is cii['f�rcnt f'rc�m its mailin� adciretiti, hoth mu5t be providcci, The date of the bond shall nnt }�e prior w lhe ddte ttic Cantract is awarded, END �F SE[;TIU1' C'ITY []H' I-Qlt l' 4VL71211-f AAeQc{anm C�mmerce Cezaler STi°.1�TDARi) C TT Y CQNDITIQIVS—Ilf:VHf.C]NI.k A11'r112[)t:l) PHQIECTS CPN-103202 Revisul laoiurry 3l, 2012 QO G2 19 - 1 MAINTENARC'H' �C]n'❑ f'�i€E� ] oT3 1 2 3 4 5 G 7 'I'HE STA'I�� o� �rLx�s S�:CTION [Hl �2 19 MAI\TBVAI�C:E B{)N� Bond Mo. Sd-2db988 S � l0 11 12 13 14 1� 16 1� 1s CUUNTY UF TARRANT § § KNUVV :�I.I. I3Y' TFIF.�F. PRFSF.NTS: § 'Chat we Rurnsey Construetion, known as "Principal" herein and Unit�d Fire & Gasualty Company ,� corporatc sUrety (surcties, if� rricfre than vne) duly aulhnriaed to do busine55 in Lhe Stute of Texas, known as "�urety" hereii� (vvhether ane or more}, are held and firml}° bound unta the De�el�per, �lbra lieulty, l�c., autho�ized to do husiness in Tcxas ("T]e�°elnper"} and ihe Ciky of rnrl Vvor[h, a Tex�.s municipal c��rpoCatlOn ("City"), in t.h�e sum of Urrc• Hr.ritd►'erf .5�r,r�}�-,}'K�re+� lJzp�r.srt��d, IVirte 1-l�ir�cl�•ec! Arrcl 1`�t1�-r��-l�o��r I3r�!lrr�•.rAi�r! F'r�,i�� Ccxart,+� I.�1�7.���..3�} lawful �noney oF the United 5�ates, to be paid in Fort WoLtti, Tarrarit C:�uiit.�, T�x�ss, for payiri�iit eaf' wt�i�li suiii w�ell and tiuly be mad� jaiiitly unta tl�e Developer dn�i khe City as duat obligee5 and thcir succG4sors, we hinci ourselves, nur heirs, executors, ad�7iinistratc�r5, successors aild assigns, jointly and scvcrally, firrn]y by thcse presents. 19 L'VHEHEA4, Dcvclup�r a�ici Cily havc c:ntcrGc� intcl an A�r�eni�;nt f's�i- th� ���ri5trucLic�n c�f' 20 cvmmi�nity facilities in thc City nF l�ort Worth by and thrc�ugh a C".c�mmunity �acilitics 2� Agreement, CFA �iuinf�er 2 t-{�{}g�y dn� 22 WH�:�t.�:1LS, the I'rin�ipal has entered into a certain written contract with the L7e�elaper 23 a��rardc,d thc �th day nf d����b�r ,�[) �� , whicli Cc�ntracl is 24 hereby referred ro anci a rliade part hereof f�r akl purp��5�s as if fully 5et #'�rth h�reiu, tu ti2rnish all 25 malcrials, equipment Iabor an�i other accessories �s ciefincd I�y ldw, in [he prosec;utian oF thc 26 Wark, including any 1�'nrk resulting f'rom a duly authnri�ed C:hang� C7rdcr [cnllc�tively ��rein, 27 thr� "W�rk") as pro�ided i'c�r ii� said Cc�nlract and [�esignated as Mcraclaam C'omrrzerce Center; and 28 29 WHFRT:A�, Prin�ipal hind4 it.�clF to use such materials and tn so canstruct the 1�'ark in 3(] accordance with the plxr��, speci�caEi�ns and C'nnlraci L��ocum�nt� that the. Work is and wi�l 31 rernain free frorn defects in zriaterials or workrri�r►ship fe�r and during thG perioc� c�f twa (2} years 32 after the date of Final Acce�txnce of the'Vt'ork hy t.he C'ity ("Maintenance Period"); and 33 CI"i'Y OF r{)lZ'I' W{)RTI� M�aChRir� Cornrnrrr.e c'r�nrer STAItifJART] CIT'Y C'C]NE�11'iC1NS I3!'VF:I.C3PF:1� A�VAf2111-:]) E'Hi}.Il-:f' I S L-1':V-fFi:f202 Revivcd Ianud��y 31 , 20 ]2 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 I fi 17 18 19 2U 21 22 23 {]i} G2 l9 - 2 NIAf\'fR\AnCF: B�ND Page 2 of 3 V4'HI+`.IL�:AS, Principal bittds its�;lf� to rcpuir or r�consiruc[ the Work �n whnle ��r in par[ upc�n recei�ing natice from the De�elc�per andlcjr Ciry nf t.he need tl�ereof at any time within khe Maintenance Period. N[)4V THEREF'[]RE, the conditicjn of this nhligation is such that if Principal shall remedy any defective Work, for which timely notice was pr��ided by I3evelpper ar C:ity, tp a completion satisfactory to the City, lhen this ohligation shalI becvrne null and �aid; c}therwise to rcmain in fuli forGc and effeGt. PRDi'ID�ll, IiDWI:V�It, if I'rincipal sfiall fail sc� t� r��air �r r�cs��istruct ariy timely iic�ticec� dcfeclivc Work, it is agrccd �h�t the De�eloper vr City rnay cause any an�k all such defective Work tt� be repaii�d andlr�r re�nnstructed w°ith ail a5tinciatccf ccasls thereof beirig barne by th� Frincigal and ihe 5urety under this Vlaintenance B�}nd; and PRdV�ll�;ll I'L�I�'I'I�EN, that if' any legal a�tic]n be f'iled on this Bond, venue shall lie in Tarrant County, "I'ex�r �n- t.hc L;riit�ci SiateS [)itil.rict (.'our[ for thc Nc�r�he�� DiSirict. of 'Fexas, l�orl Warth Division; and YItOV 11}k;I] FUR'TH�:I�, tt�at this obligation sha1l b� eontinuous iri riaturc and suecessi�°c r�c;ovcrie5 rriay hc had her�t�ri far sticccstiivc; hrcaches. CITY �F FORT �1'ORTF { SThIti TJ�� RTl (' I'T Y C'.D.\'Lil'I'10 ti 5— T)H V H'i.QPN'Id Av4`AIZL]�:I] 3'R C]J�CTS Reviseci Ianioaiy 31 , 20I2 ,'49'eur:rr:ins C.'u�nmcrcc C'cMler L'Pl�,' 1D32p1 nn csa � � - 3 n�nt��rF:vntir'H ��tVD P,sg�, 3 of 3 1 IN WI7'NFSS WHF.RFDF, the Prirlcipal arid the 5urety ha�e aaeh SIGNELI and S�ALED �his 2 instrwnent hy duly authnri�.ed agents ant� officers c�t� this the �fh day at 3 Oevernper , 20 21 5 6 7 8 9 1Q li 12 13 14 15 I$ ]? 18 ]9 2[i 21 22 23 24 25 2& 27 2R 29 3@ 31 32 33 34 3S 3fi ATT�ST: [Principal� 5ecret�iry � �. WiIC�CsS a5 tr) Pi'11tC1pa] ATTF;ST: n�rA f5uc 5ecretary � Wime.es as to . uret 37 *NOte: 3$ 39 4U 41 42 PFtI1�iCIYAL: Rumsey Canstructian, Inc. BY: � � Cnrev Cauef�ro�5, VP c�f Preconstruc�soi7 Namc and `I'ille flddress: 4329 Reeder L]r Currolltc�n. TX 7�QZ() SLiRETYc UniRed F�re & Casually Cvmpany BY: - 5i�riature Wlyson Dean-Wes! A�Eorney-in-facl IVame �ind Ti�lc Address i���0 Park Central Drive, #1d40 pallas. T}C 75251 TelephuneNumbcr: Zt4-221-a3ao If si�ned by an officer oi the 5urety L:onipar3y, there must be on file a certified extract fram the by-laws shawing t}iat this persorf has tiL1Lf}CJl-]ty t[7 si�ri such c�hligaticm. If Surety's physicai address is different frnrn its mai]ing address, both must be provided. The date nf' tt�e b��n�i shall not he prior ln the date ihe Contract is awarded. C1TY QN NURT WQH`I'} E Meacharn Com�erce Cen�er STA� DA R b � 1'1'Y Ct)h UITIONS — I}�VE:LCSP�R AWARDE� PR C}7F'C'TS CPN-1 f732QZ x��vis��d 7aouary Jl, 201Z uf� �h5u�,'�tiC,� lJ1i]'I'l�.i) ]'[IZf' 1l CASUAi,'1'Y CC3T�41'AI�Y, CI:I�lllt RAF'Ii]�, lA lni�uiries: SurM�• llcp�rtment �J1ti[E];i.}PIRI'cL'•Ilti[�[::A91tiiI.Yt.'(.)MPi1�Y.�'�.:135'Ii;i�. i.}E i1H5e�ondAvcSE. I�il��'kit('iA1..!'�'I[:It[f'IiVtiili�•'�1ti[.'�.t'[1t�1]'e1�Y,i2c]{.'KI.Iiv,LA [�L'I�FIi•i��i�3ids_I,l 52�I11 t!:!2 ['[I !}:11 ['t}I'Y [3[' I't31�'I'it Csl� A"I'](iRt� E:Y (ni i�ii��il �in l.�Ir �El ]l��mc c]lfic. ��i i.'�an�,ratiy - 5�e ['ri lirc,i�i[n�) I;14f]1�' Af..I. �'I'.i.t5f3N5 iSY '] Fi I.wf. PI�F:51 i�i : ti, .7xa1 L.1>>il�:l i irz k i'.i:.�ir..1y C'��rnpriAiy, :i cnrlxar:�lic�n [ii�lti oi-rranir�d anil L`\:tillll� lifiiiLl' ll7i la��'s ❑7� [lu: ti�a�� ❑f Io�,�•a: l.:n�[�d 1'irc & in;lcnuu�y Coii���aiiy, s1 cc�r;x�raEi�m clul�� or;,��uiir��l �jud cxi,�u��? iu�dcr u�e lakvs af the S�ate ol 1'ekas; ,u1� Ftn�uicia� 1'acil'ic lz�s,_u:u�.c Cnin��uu�•, n c��r�x�r.ili[m dul�. cir�anii�d ��nd �xistinr; un�lu- ll�c l�tiv� aCth� 5ln�i ci1' C.'.ihfnr�iia [hari�� c[�llcctivcly c.ill;:� die [_cf��i�3i�iairw}, a�icl h�ivai� liiiir i'uii�oi:ai� ��i�ciy��art�iti ui L'ccl.0 lta�f:�l�, tilat� o� ie�v,�. �lo�� ii�al:r, cuii.liLuic uctcl cq��wii:l ALLY50N DEAN-4'lEST, EVA G_ LIhi�+tER, EftRILY R1IKE5i{A, JOHN R. 4'JARD, THOPAAS DL7;JGLRS MOORE, i�6VICA VEA�EY, EACH INDIVI:7lJ1LLY [hci�' lrtic �niJ I:�Nlul A��.}:�i�y(.j-in-l�a�i ��i[]f E�:��aer aiiJ .iu�horlly la�r.lsv �c���fc�'['��� l❑ tii�„n, ti�a[ �i�c( �x��ul� ii� <<5 U�l�,�ll�:i!] l:i���l�il I+c�inls, un�tertnkingti illlfj OLtl.� �l>lig�izor�' l:]titlllf]1CI]�5 1)f S]R11Ifll' lliltlll'L ]J1��L'l:�t:CI 1I11j:lC} �1:1�lr. nl�li�a�io�y �h�tt cx�c�si $� ao, ooa, o00 . oa t1l](1 lC7 17117L� itlC �L�iil1kllllG.ti ��7�.1'L'�lj' '[YS IIIII]' �311ij l� C�i4 ti,ttl� C7ifClll fl5 Il�.illi:�l llltilf'il!]3Cl7l.ti �Vl'-['[' .tilf?S1C.[� I7}' I�1C ��llly nuthnr:��d nl�ticcrs cif' thc {�f]it1i7F1311ti,ti a�id all ol'th� acts vl' �ai�i.At�a�7ie��, ni�rs�<<ui� �c, ttic. autliority }icrchv �iveu �.�:e[ l�s�i�ehy r�ti�c�l �lll:l C0131ifIl1CCI. Tl�� Auiki�Yi�y l��t�by �raio[�d lti rUI1�l:1L1[]li� a�.d sha;i i'e:ilau� 111 tLIIV �OICC .uui �rr�t �����si ���tike� ��y l.�t�il��c! Fire & Casualty Campany, Ulllte[i Ftl�e & T�acl�jimily Cain4�z3u_,, u�i�l l iiE�iucial I'ritiJ���: luiin':u:�� [;oiuGki��y. liu� 1'es«u al rlllnrney s, rnadc 111CI ��tCLEI�C� j]LI;.Sllil[If t!] and i�V iiU�I:[][�lt' [l� t�;i', �ul<<i�kin� f�yl::n �luly �jtln� [{'d nr] M�y {5, 2O13, hy the I�ns,r:lc nl IJirectcm uf iJnifcci F�u�r & Cai��r,ili�' Carnp�in�, i i�i[��E i i�c & Iucicnutit� Carn��a�i;:, ,uul I ir.<<n�ial I',irilir i��.,��i�inr� i:urri}�atty. '•; l e tl r l c �[-!iu � r[p Rn n d c il il iI I� ll[ LP PF.I Ii 151 FY � .'iL'L��['ll �i :`k}�K'llll]}I4:31. l]I A�ilf:lll"t-E1L-I'Al� ���lt T':�tiilil'�Il� S7! :IIL�' ��[L'G ��]'titil411:11:� [71 ili1V [7�114:1' lL':IICl tl� ��ll' ��Gll]I3iillltiS j�i1V� ljUll} �flj3ti �U �Ill:l'r� el�1j}l]Ill� 11�1 hV'17��G11 '��FiILBTCti:kII(l:l1i?NV•11!- �B�I I[1 ;�i'.; 217 �1k7}3.}�f il. €�1L` ��(lifl�l:l!11EC ][1 �.11C F�\C['.:1�10r� nf S�nL:ir+: nl�iii;�.ir�ii� c, �uii�:lc, t�,>>r�eil.lkii���, :nir. ,ilhtr nhl'.C:1�[115� 111C�]'�I113l;fltt i��11�L' fl:l'lAf�. `i7lC 5i!;I1q4L�Y411iA1h'p�•`f1�CI R-:IIIUII,{CSI 13CiC:��:� H�ld Ijlti {.i+l]701a1: �cJ��fCi4}' lir.�;;ixc�lhy .'acsur•ilc S�,;r,ie �,rn��r: n� JLl4nllc� [7i ��7Cci�1 EvGl��CYnf'�uo�nccurc��iificat:uu ni aid+a� ainl�u�i�cr{ lic-��+y; :t���h eis�na[u,L Aud ccnl. u�liiu :a .i:iYl. hc���g, .�dn�+icc h�� i:�c Cc�r:���•.»e; a: i,�a nrig:s�aE ;i�nai:,re�. nf ;ts�'�i lt'.1CL'Y :117ii rl�e nrs�ii}al :u<d of .hc (;un�p:�ii��, �a'.�c ynlid a:�d 6iiuli�i� upun tha Ccnu�a�iic� �� i�ii �lic ,a�i:r 1'nnc anu �i-fce, a. iiioui:; inanually �CI'ixad. tiiwlz �t.lc}::�cs�-�:;-fa�l, sul,jeci �c� ihc lin�u:iiinnti,c� ��: �Dr175 m 1h�.ir rc;�cctit c cc:Tt[icat..: r1�a.�3hnci�y slt.�li ha��c :isll lwu�cr t;, hu3r] :'.ic �'nni�+ani�. hy ;}y�i- ai��t:i`.�rc �c�cl c�ct:�.tir=r, nr"n,iy::�c3� inaln�ittenfc ;��tid',n at[n�li tha ceal liu: Cumpanic5 flicrcin, �']ie Pitisi[lc:�. �n a�iy Vi�e P[c.i.luil, .he Rnar.< <:i T7i:r�:lc�r� cr. auy :��iz�:r nfi7�cr ni'Ihc Cnu:,r�:�:r. m:�y a.:ur; iiuio _u.�uk� t��l j�[nk�ci urc; uutinni.. prcriuu:ly�ivcninan� �ttnrncy-in-fa�t_ n+lYlltlyll�p 11L75�nHNrryr� ,�y�nunlr,,,, ,``��`i[��Y'�r��t � `��� Hswuinr���lf �4`�,.�� i�lSuAv"si a i ��'p�: fi ` � . 'y �r,�`FP:`�ir.^.:, �? CIf�fi7�lA1]' �� =9 �/1HIY11:A�1:,��`^' "�A ��t�s ` ' '�-- .��v r2 p � _ � .._..� �: �- �.� ; _ '�' " % v � - �JE4 - � � sr.}i. � 5}�� •� ='%��..r+� ,,r:,. � �rY� a1r,� '�q, �~ 3,'`'�.C.xCP,�.•'ra'� ''�' *niiu'a'��y /N�� fIIR i 15K1�j1,' `'� r� N� � N��u���� ���",� 5r;�tc aiIorva, C:ounry efl.uui. ss: I �til I I;,l f�lfth'. c� ['R�! �,'ll'�'1 c:[3ti11'�1N'Y z��� i E:_3 r�i��E: � rr�r�r-.�9N1'fV C`CIhtPANY I�1V:'1[ti�'IAI: l'�1C.f1�fC l�t5i. R:1,tiC'l,C'f?MF'Afil�' I�y: ��,,.,.1_�+�.�-�._. — -_ Vi�c 1'rctiid.��iri p� 22�d day of July, 2d�1, before r�e personally came Oenr�9s J_ Riehrnann [u s:Lc �::i�iu�i, wltu L•�iat� by �u� duly s�vot�f. <li�lils:p:i.s� �iit,: sa4; �iatl�� :.tiicl., iu Ceii�u' �t,i4siik,, �t��lc ol� ]c��tia: �hal hc iti ,� L'icc= f'r�.icl��i[ nJ'll��iic;l l�i�e �{`titiii�lh C'nir���[itiy, �i Vi�c P:eSid�;ii c�� C%1311C:[I I"f3-C � Iu�lct:t�i�ty Co:-ii��:�ny, .Zzid a L'icc }'ic�i�icii: {1J� I'ill�ili.Si3i I'acilic 11LGLli'�Il]CC C.OI]lj]illl�� tlte rnr�orat:cros dcc;.iit�cd ii� fli=.<l l�,'I11C�1 .YL`Cl'iCL t}�c s�E�nvc 1E151YE1:11[Y?l� thF�� u.: kii<±�,a, clic act�l ❑f' s�iicl resi7�c�r��io�is: [la�t [I�c Se:i1 :sfiixa! �ca th:: .ni[i isis�nirnc�i' i5 �ucii cnr�h}ratc sc:il; [Y��ti il. �t��i� scs ��l�li�rd i�urtivau� �n 'rlllk�l,llll4 S?14C71 :.1�� lLL fia}inl cti! Il:n'clt'.1".� [7� ti:li(I �nl��:�l'.�l]nli5 �tiic] �lr�t lE� sit��:cll:is niit�li thcrc:lo �mrs�auiY co I�kc .�uil�ar�t�, and acl.no��'Ic4��c, snmc In l�� �h;: aci �tiu! d:�d ni',i��d ce�pnrr�[€t!ns. �aui t PaH� lldaddnll � � loK•a NoL�ria: Soal � Cnmmisslon number 713274 �,�tai� Pul�lic O�� My Cominisaion Expires 1U12oI2•�22 ,LIV coniini5�ion ���]�irc;: I�l.r?C�12U�? I, i�7aty A. ��itvch, l��tii;t:uit 5�cr����r} ai�i3rii���1 I'�re & C�sualt,. C�[tip���' i3111L :�5ti1*'.e1711 S��l�l�lll ()I 1�1111L'[� �'ll� c�[ Il]ciUlllll'.V C[l1Ilj)ally, �ltli� ILytiltilkllll �ccxctt�av or 1't�taAZcitil Pt��il�ii ir�sL�ranre �'n3n��t3�xr, cics Iti�r�h�� c:crtil._1 lluit j Iti�tic ci�rnp�'��cl ifi� li�r��ni���, cc���� ❑i tit� I'rn�•�r ni'.Alluni�y �jiid til�l:cls�vit, tuici lhc cop}' af tlic Sutiii�nn of tl�e hy�la�ts �acl rc�:ni�u€ou, of 5�31[� i'C11]7[]C�iIL]llti aa �cl Ici7E1 in :.aic{ Pnu•���r ni.luc+rr��y, t� �tl� �1�4 C)[tl(.iI€�:11_5 C]Ii i� 11_.i: i'� I'� Il.: I1C1n�lt: UF�I']t;l= 4?i� 511i[] L'C]IZNC)1t:'1'I'I[.}I�S, an,] tli�� ilic samc �•c corr�ct t�un�cri�n. tl�cr�af, �:nd ❑f �tie �ti•hole oi� [Izc �aiil nriemals, c��l(: i]1s71 LIlL' ti�11({ ]'v�.ti tr uP rlttoiuey lius Fien F�c�u re� ak�ti au� is nuFv ui li�il forc� �ui�l �{�l�r�t. iii t�w�iinu�iiti� �+•lirr��f J ha e liarcwito �uh�cril]c�l m� i��itn� .�ud a'Fix��l [h� cor��ural+' �tai r�l tl�e �:iiJ L'urlwr<ttions i:�is � day af �� C�.��f-z .?0 21 ��+ti��c� ��ri�?��4� +� �P l � � 4 � Y =: LL1a1'[]H�iFI'. X � �_- r, ; -.-- �� 51-�L1 = �� �r r� `� ••i r.,� �I till•11'SIF�N r�lq,lnil4�i� �3����iiU�� �?17 �atinuirrra . �,�� �N ,a,.i . ���pyltiH:ayrr��� .'�4�G Sf�%ya'% �a`� r� �,y i T�r RPCqi-,✓t''. rP , _ ¢ � r..�^�_ _.� Clll[IY11i.1'il. '� e ' �L ;� � �U'' � � ;� .� :�. �v���� �. �; -.-- :_ . �.. �,�� r� - SF..11 " . :�_ 'y a .. ti� : a' . � `CrFdR���' � r 4 �H.r� isx�ti : � hrrl�11�74411��,it �'� I�irlrl��1151�i�1». 1�1 l�'I1'1\1:�5 wl'fiL.iZ�_C]r�, t��� C{]ME'_4h1k.5 lta�e eaclicaused lltesc j'�re4�ius ta E�� cig�i..d l�y ii.� vi�: kJ1�:1ISIL'IIL fS1iL� !I� �ni�lot;�ti ��al t[s ET� li�rctrr affix��j t�tie ��nd d3y Of Ju ] y, 2D21 ��' `�" �,�,�1�, �� �-��� �iti+lSi�tl;i til'{'!-t1�111�, ���':11� G. l �f�[�.l U�. �'I�i�� � u SURETY IMP�RTANT NQTICE '1'❑ ClBTAT1IT INI�QHMA'I'101� DR 11'I:hK]° A COMYI�A[1V'C: �n�ted Fire & Cas�aRy Company �,'nrted Fire & lndemr+ity Compar+y ,=rnar�ccyf P.s�ifrr. Jn�ur�nce Cc�mp3�'�! You may cali Uniied Fire Gz��up's loll free telephone number for infarmatian or ta make a�nmplaint at: 8 Dfl-3 43 -913 {) You may also writeto L:nited Fire Group at: [;nitcd l�ire Group Atti1: �tirety L)eparlment P.C1. Bt�x 7:��0'� Ced�r Rapids, lA 524�7-39U9 -c�r strcct address- i]nited Fir� Group Atkn: Surety Uepartrrient 1 18 �ec�>nd A�enue SF Cedar Ra�ids, IA 52401 You rnay cantact ihe Texas I7epurtment of� Insurance to c�htain infnrmalinn nn compani�s, coyera�es; rights ar camplaints at: 8UU-25Z-3439 You may write the Texas 1]cpartment nf I�tisurance at_ C�nnsuiner Prc�te�tion (111-1A) P.O, k3ox 149�91 AuStin, TX 75714-�)9{)9l Nax: {512) 44U-]OD7 Wcb; ��ww.tdi.texas.gov Emaii; C:onsu:zierPrvtectian�r¢7tdi.tcxas.�a� Premium or Claim I)ispules: 5hould you ha�e a dispute ct�ncernin� yt�ur prernium ar about a claim, yoia should �onta�t L]nited Fure Grnup first. If thc disputc is not resni�ed, yc}u may cnntact the Texas ❑�partment af'Insurance. A'1"1'ACH 1'HIS N[�'I'IC� 'I'❑ Y�tiR BU�ID. This noti�c is i'or information onlv and does not 6ecome a part nr a cc�nditinn ��f the attached dnc�iment and �5 �iven tc� cnm�ly �•�th �ectic�n 2253.Q21, Gavcrnm�ntal Cad�, and Sectiran 53-2D2, Froperty Code. HQMEOFFiCE: 1185ecand Avenue SE � Pfl Box T3909 � Geda• �ao:ds Iow252407-3809 � P; 8�0•332-7977 � F: 319-286-252Q � www.�fai�s.com CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 STANDARD CITY CONDITIONS OF THE CONSTRUCTION CONTRACT FOR DEVELOPER AWARDED PROJECTS Meacham Commerce Center CPN-103202 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 STANDARD CITY CONDITIONS OF THE CONSTRUCTION CONTRACT FOR DEVELOPER AWARDED PROJECTS TABLE OF CONTENTS Page Article 1 – Definitions and Terminology .......................................................................................................... 1  1.01 Defined Terms ............................................................................................................................... 1  1.02 Terminology .................................................................................................................................. 5  Article 2 – Preliminary Matters ......................................................................................................................... 6  2.01 Before Starting Construction ........................................................................................................ 6  2.02 Preconstruction Conference .......................................................................................................... 6  2.03 Public Meeting .............................................................................................................................. 6  Article 3 – Contract Documents and Amending ............................................................................................... 6  3.01 Reference Standards ..................................................................................................................... 6  3.02 Amending and Supplementing Contract Documents .................................................................. 6  Article 4 – Bonds and Insurance ....................................................................................................................... 7  4.01 Licensed Sureties and Insurers ..................................................................................................... 7  4.02 Performance, Payment, and Maintenance Bonds ........................................................................ 7  4.03 Certificates of Insurance ............................................................................................................... 7  4.04 Contractor’s Insurance .................................................................................................................. 9  4.05 Acceptance of Bonds and Insurance; Option to Replace ........................................................... 12  Article 5 – Contractor’s Responsibilities ........................................................................................................ 12  5.01 Supervision and Superintendent ................................................................................................. 12  5.02 Labor; Working Hours ................................................................................................................ 13  5.03 Services, Materials, and Equipment ........................................................................................... 13  5.04 Project Schedule .......................................................................................................................... 14  5.05 Substitutes and “Or-Equals” ....................................................................................................... 14  5.06 Pre-Qualification of Bidders (Prime Contractors and Subcontractors) ..................................... 16  5.07 Concerning Subcontractors, Suppliers, and Others ................................................................... 16  5.08 Wage Rates.................................................................................................................................. 18  5.09 Patent Fees and Royalties ........................................................................................................... 19  5.10 Laws and Regulations ................................................................................................................. 19  5.11 Use of Site and Other Areas ....................................................................................................... 19  5.12 Record Documents ...................................................................................................................... 20  5.13 Safety and Protection .................................................................................................................. 21  5.14 Safety Representative ................................................................................................................. 21  5.15 Hazard Communication Programs ............................................................................................. 22  5.16 Submittals .................................................................................................................................... 22  5.17 Contractor’s General Warranty and Guarantee .......................................................................... 23  Meacham Commerce Center CPN-103202 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 5.18 Indemnification ........................................................................................................................... 24  5.19 Delegation of Professional Design Services .............................................................................. 24  5.20 Right to Audit: ............................................................................................................................ 25  5.21 Nondiscrimination....................................................................................................................... 25  Article 6 – Other Work at the Site ................................................................................................................... 26  6.01 Related Work at Site ................................................................................................................... 26  Article 7 – City’s Responsibilities................................................................................................................... 26  7.01 Inspections, Tests, and Approvals .............................................................................................. 26  7.02 Limitations on City’s Responsibilities ....................................................................................... 26  7.03 Compliance with Safety Program ............................................................................................... 27  Article 8 – City’s Observation Status During Construction ........................................................................... 27  8.01 City’s Project Representative ..................................................................................................... 27  8.02 Authorized Variations in Work .................................................................................................. 27  8.03 Rejecting Defective Work .......................................................................................................... 27  8.04 Determinations for Work Performed .......................................................................................... 28  Article 9 – Changes in the Work ..................................................................................................................... 28  9.01 Authorized Changes in the Work ............................................................................................... 28  9.02 Notification to Surety .................................................................................................................. 28  Article 10 – Change of Contract Price; Change of Contract Time ................................................................ 28  10.01 Change of Contract Price ............................................................................................................ 28  10.02 Change of Contract Time............................................................................................................ 28  10.03 Delays .......................................................................................................................................... 28  Article 11 – Tests and Inspections; Correction, Removal or Acceptance of Defective Work ...................... 29  11.01 Notice of Defects ........................................................................................................................ 29  11.02 Access to Work ........................................................................................................................... 29  11.03 Tests and Inspections .................................................................................................................. 29  11.04 Uncovering Work ....................................................................................................................... 30  11.05 City May Stop the Work ............................................................................................................. 30  11.06 Correction or Removal of Defective Work ................................................................................ 30  11.07 Correction Period ........................................................................................................................ 30  11.08 City May Correct Defective Work ............................................................................................. 31  Article 12 – Completion .................................................................................................................................. 32  12.01 Contractor’s Warranty of Title ................................................................................................... 32  12.02 Partial Utilization ........................................................................................................................ 32  12.03 Final Inspection ........................................................................................................................... 32  12.04 Final Acceptance ......................................................................................................................... 33  Article 13 – Suspension of Work .................................................................................................................... 33  13.01 City May Suspend Work ............................................................................................................ 33  Article 14 – Miscellaneous .............................................................................................................................. 34  14.01 Giving Notice .............................................................................................................................. 34  Meacham Commerce Center CPN-103202 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 14.02 Computation of Times ................................................................................................................ 34  14.03 Cumulative Remedies ................................................................................................................. 34  14.04 Survival of Obligations ............................................................................................................... 35  14.05 Headings ...................................................................................................................................... 35  Meacham Commerce Center CPN-103202 00 73 10- 1 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 1 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 ARTICLE 1 – DEFINITIONS AND TERMINOLOGY 1.01 Defined Terms A. Wherever used in these General Conditions or in other Contract Documents, the terms listed below have the meanings indicated which are applicable to both the singular and plural thereof, and words denoting gender shall include the masculine, feminine and neuter. Said terms are generally capitalized or written in italics, but not always. When used in a context consistent with the definition of a listed-defined term, the term shall have a meaning as defined below whether capitalized or italicized or otherwise. In addition to terms specifically defined, terms with initial capital letters in the Contract Documents include references to identified articles and paragraphs, and the titles of other documents or forms. 1. Agreement - The written instrument which is evidence of the agreement between Developer and Contractor covering the Work 2. Asbestos—Any material that contains more than one percent asbestos and is friable or is releasing asbestos fibers into the air above current action levels established by the United States Occupational Safety and Health Administration. 3. Business Day – A business day is defined as a day that the City conducts normal business, generally Monday through Friday, except for federal or state holidays observed by the City. 4. Buzzsaw – City’s on-line, electronic document management and collaboration system. 5. Calendar Day – A day consisting of 24 hours measured from midnight to the next midnight. 6. City— The City of Fort Worth, Texas, a Texas home-rule municipal corporation, acting by, its governing body through its City Manager, his designee, or agents authorized pursuant to its duly authorized charter on his behalf. 7. Community Facilities Agreement (CFA) -–A Contract between the Developer and the City for the Construction of one or more following public facilities within the City public right-of- way or easement: Water, Sanitary Sewer, Street, Storm Drain, Street Light, and Street Signs. A CFA may include private facilities within the right-of-way dedicated as private right-of- way or easement on a recorded plat. 8. Contract—The entire and integrated written document incorporating the Contract Documents between the Developer, Contractor, and/or City concerning the Work. The Contract supersedes prior negotiations, representations, or agreements, whether written or oral. 9. Contract Documents—Those items that make up the contract and which must include the Agreement, and it’s attachments such as standard construction specifications, standard City Conditions, other general conditions of the Developer, including: a. An Agreement Meacham Commerce Center CPN-103202 00 73 10- 2 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 2 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 b. Attachments to the Agreement i. Bid Form ii. Vendor Compliance with State Law Non-Resident Bidder iii. Prequalification Statement c. Current Prevailing Wage Rates Table (if required by City) d. Insurance Accord Form e. Payment Bond f. Performance Bond g. Maintenance Bond h. Power of Attorney for Bonds i. Workers Compensation Affidavit j. MWBE Commitment Form( If required by City) k. General Conditions l. Supplementary Conditions m. The Standard City Conditions n. Specifications specifically made part of the Contract Documents by attachment, if not attached, as incorporated by reference and described in the Table of Contents of the Project’s Contract Documents o. Drawings p. Documentation submitted by contractor prior to Notice of Award. q. The following which may be delivered or issued after the effective date if the Agreement and, if issued become an incorporated part of the Contract Documents i. Notice to Proceed ii. Field Orders iii. Change Orders iv. Letters of Final Acceptance r. Approved Submittals, other Contractor submittals, and the reports and drawings of subsurface and physical conditions are not Contract Documents. 10. Contractor—The individual or entity with whom Developer has entered into the Agreement. 11. Day or day – A day, unless otherwise defined, shall mean a Calendar Day. 12. Developer – An individual or entity that desires to make certain improvements within the City of Fort Worth 13. Drawings—That part of the Contract Documents prepared or approved by Engineer which graphically shows the scope, extent, and character of the Work to be performed by Contractor. Submittals are not Drawings as so defined. 14. Engineer—The licensed professional engineer or engineering firm registered in the State of Texas performing professional services for the Developer. 15. Final Acceptance – The written notice given by the City to the Developer and/or Contractor that the Work specified in the Contract Documents has been completed to the satisfaction of the City. Meacham Commerce Center CPN-103202 00 73 10- 3 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 3 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 16. Final Inspection – Inspection carried out by the City to verify that the Contractor has completed the Work, and each and every part or appurtenance thereof, fully, entirely, and in conformance with the Contract Documents. 17. General Requirements—A part of the Contract Documents between the Developer and a Contractor. 18. Laws and Regulations—Any and all applicable laws, rules, regulations, ordinances, codes, and orders of any and all governmental bodies, agencies, authorities, and courts having jurisdiction. 19. Liens—Charges, security interests, or encumbrances upon Project funds, real property, or personal property. 20. Milestone—A principal event specified in the Contract Documents relating to an intermediate Contract Time prior to Final Acceptance of the Work. 21. Non-Participating Change Order—A document, which is prepared for and reviewed by the City, which is signed by Contractor, and Developer, and authorizes an addition, deletion, or revision in the Work or an adjustment in the Contract Price or the Contract Time, issued on or after the Effective Date of the Agreement. 22. Participating Change Order—A document, which is prepared for and approved by the City, which is signed by Contractor, Developer, and City and authorizes an addition, deletion, or revision in the Work or an adjustment in the Contract Price or the Contract Time, issued on or after the Effective Date of the Agreement. 23. Plans – See definition of Drawings. 24. Project Schedule—A schedule, prepared and maintained by Contractor, in accordance with the General Requirements, describing the sequence and duration of the activities comprising the Contractor’s plan to accomplish the Work within the Contract Time. 25. Project—The Work to be performed under the Contract Documents. 26. Project Representative—The authorized representative of the City who will be assigned to the Site. 27. Public Meeting – An announced meeting conducted by the Developer to facilitate public participation and to assist the public in gaining an informed view of the Project. 28. Regular Working Hours – Hours beginning at 7:00 a.m. and ending at 6:00 p.m., Monday thru Friday (excluding legal holidays). 29. Samples—Physical examples of materials, equipment, or workmanship that are representative of some portion of the Work and which establish the standards by which such portion of the Work will be judged. Meacham Commerce Center CPN-103202 00 73 10- 4 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 4 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 30. Schedule of Submittals—A schedule, prepared and maintained by Contractor, of required submittals and the time requirements to support scheduled performance of related construction activities. 31. Site—Lands or areas indicated in the Contract Documents as being furnished by City or Developer upon which the Work is to be performed, including rights-of-way, permits, and easements for access thereto, and such other lands furnished by City or Developer which are designated for the use of Contractor. 32. Specifications—That part of the Contract Documents consisting of written requirements for materials, equipment, systems, standards and workmanship as applied to the Work, and certain administrative requirements and procedural matters applicable thereto. Specifications may be specifically made a part of the Contract Documents by attachment or, if not attached, may be incorporated by reference as indicated in the Table of Contents (Division 00 00 00) of each Project. 33. Standard City Conditions – That part of the Contract Documents setting forth requirements of the City. 34. Subcontractor—An individual or entity having a direct contract with Contractor or with any other Subcontractor for the performance of a part of the Work at the Site. 35. Submittals—All drawings, diagrams, illustrations, schedules, and other data or information which are specifically prepared or assembled by or for Contractor and submitted by Contractor to illustrate some portion of the Work. 36. Superintendent – The representative of the Contractor who is available at all times and able to receive instructions from the City and/or Developer and to act for the Contractor. 37. Supplementary Conditions—That part of the Contract Documents which amends or supplements the General Conditions. 38. Supplier—A manufacturer, fabricator, supplier, distributor, materialman, or vendor having a direct contract with Contractor or with any Subcontractor to furnish materials or equipment to be incorporated in the Work by Contractor or Subcontractor. 39. Underground Facilities—All underground pipelines, conduits, ducts, cables, wires, manholes, vaults, tanks, tunnels, or other such facilities or attachments, and any encasements containing such facilities, including but not limited to, those that convey electricity, gases, steam, liquid petroleum products, telephone or other communications, cable television, water, wastewater, storm water, other liquids or chemicals, or traffic or other control systems. 40. Weekend Working Hours – Hours beginning at 9:00 a.m. and ending at 5:00 p.m., Saturday, Sunday or legal holiday, as approved in advance by the City. Meacham Commerce Center CPN-103202 00 73 10- 5 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 5 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 41. Work—The entire construction or the various separately identifiable parts thereof required to be provided under the Contract Documents. Work includes and is the result of performing or providing all labor, services, and documentation necessary to produce such construction including any Participating Change Order, Non-Participating Change Order, or Field Order, and furnishing, installing, and incorporating all materials and equipment into such construction, all as required by the Contract Documents. 42. Working Day – A working day is defined as a day, not including Saturdays, Sundays, or legal holidays authorized by the City for contract purposes, in which weather or other conditions not under the control of the Contractor will permit the performance of the principal unit of work underway for a continuous period of not less than 7 hours between 7 a.m. and 6 p.m. 1.02 Terminology A. The words and terms discussed in Paragraph 1.02.B through D are not defined but, when used in the Bidding Requirements or Contract Documents, have the indicated meaning. B. Defective: 1. The word “defective,” when modifying the word “Work,” refers to Work that is unsatisfactory, faulty, or deficient in that it: a. does not conform to the Contract Documents; or b. does not meet the requirements of any applicable inspection, reference standard, test, or approval referred to in the Contract Documents; or c. has been damaged prior to City’s written acceptance. C. Furnish, Install, Perform, Provide: 1. The word “Furnish” or the word “Install” or the word “Perform” or the word “Provide” or the word “Supply,” or any combination or similar directive or usage thereof, shall mean furnishing and incorporating in the Work including all necessary labor, materials, equipment, and everything necessary to perform the Work indicated, unless specifically limited in the context used. D. Unless stated otherwise in the Contract Documents, words or phrases that have a well-known technical or construction industry or trade meaning are used in the Contract Documents in accordance with such recognized meaning. Meacham Commerce Center CPN-103202 00 73 10- 6 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 6 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 ARTICLE 2 – PRELIMINARY MATTERS 2.01 Before Starting Construction Baseline Schedules: Submit to City in accordance with the Contract Documents, and prior to starting the Work. New schedules will be submitted to City when Participating Change Orders or Non- Participating Change Orders occur. 2.02 Preconstruction Conference Before any Work at the Site is started, the Contractor shall attend a Preconstruction Conference as specified in the Contract Documents. 2.03 Public Meeting Contractor may not mobilize any equipment, materials or resources to the Site prior to Contractor attending the Public Meeting as scheduled by the City. ARTICLE 3 – CONTRACT DOCUMENTS AND AMENDING 3.01 Reference Standards A. Standards, Specifications, Codes, Laws, and Regulations 1. Reference to standards, specifications, manuals, or codes of any technical society, organization, or association, or to Laws or Regulations, whether such reference be specific or by implication, shall mean the standard, specification, manual, code, or Laws or Regulations in effect at the time of opening of Bids (or on the Effective Date of the Agreement if there were no Bids), except as may be otherwise specifically stated in the Contract Documents. 2. No provision or instruction shall be effective to assign to City, or any of its officers, directors, members, partners, employees, agents, consultants, or subcontractors, any duty or authority to supervise or direct the performance of the Work or any duty or authority to undertake responsibility inconsistent with the provisions of the Contract Documents. 3.02 Amending and Supplementing Contract Documents A. The Contract Documents may be amended to provide for additions, deletions, and revisions in the Work or to modify the terms and conditions thereof by a Participating Change Order or a Non-Participating Change Order. B. The requirements of the Contract Documents may be supplemented, and minor variations and deviations in the Work not involving a change in Contract Price or Contract Time, may be authorized, by one or more of the following ways: 1. A Field Order; Meacham Commerce Center CPN-103202 00 73 10- 7 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 7 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 1. City’s or Engineer’s review of a Submittal (subject to the provisions of Paragraph 5.16.C); or 2. City’s written interpretation or clarification. ARTICLE 4 – BONDS AND INSURANCE 4.01 Licensed Sureties and Insurers All bonds and insurance required by the Contract Documents to be purchased and maintained by Contractor shall be obtained from surety or insurance companies that are duly licensed or authorized in the State of Texas to issue bonds or insurance policies for the limits and coverage so required. Such surety and insurance companies shall also meet such additional requirements and qualifications as may be provided Section 4.04. 4.02 Performance, Payment, and Maintenance Bonds A. Contractor shall furnish performance and payment bonds in the name of Developer and City, in accordance with Texas Government Code Chapter 2253 or successor statute, each in an amount equal to the Contract Price as security for the faithful performance and payment of all of Contractor’s obligations under the Contract Documents. B. Contractor shall furnish maintenance bonds in the name of Developer and City in an amount equal to the Contract Price as security to protect the City against any defects in any portion of the Work described in the Contract Documents. Maintenance bonds shall remain in effect for two (2) years after the date of Final Acceptance by the City. C. All bonds shall be in the form prescribed by the Contract Documents except as provided otherwise by Laws or Regulations, and shall be executed by such sureties as are named in the list of “Companies Holding Certificates of Authority as Acceptable Sureties on Federal Bonds and as Acceptable Reinsuring Companies” as published in Circular 570 (amended) by the Financial Management Service, Surety Bond Branch, U.S. Department of the Treasury. All bonds signed by an agent or attorney-in-fact must be accompanied by a sealed and dated power of attorney which shall show that it is effective on the date the agent or attorney-in-fact signed each bond. D. If the surety on any bond furnished by Contractor is declared bankrupt or becomes insolvent or its right to do business is terminated in the State of Texas or it ceases to meet the requirements of Paragraph 4.02.C, Contractor shall promptly notify City and shall, within 30 days after the event giving rise to such notification, provide another bond and surety, both of which shall comply with the requirements of Paragraphs 4.01 and 4.02.C. 4.03 Certificates of Insurance Contractor shall deliver to Developer and City, with copies to each additional insured and loss payee identified in these Standard City Conditions certificates of insurance (and other evidence of insurance requested by City or any other additional insured) which Contractor is required to purchase and maintain. Meacham Commerce Center CPN-103202 00 73 10- 8 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 8 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 1. The certificate of insurance shall document the City, an as “Additional Insured” on all liability policies. 2. The Contractor’s general liability insurance shall include a, “per project” or “per location”, endorsement, which shall be identified in the certificate of insurance provided to the City. 3. The certificate shall be signed by an agent authorized to bind coverage on behalf of the insured, be complete in its entirety, and show complete insurance carrier names as listed in the current A.M. Best Property & Casualty Guide 4. The insurers for all policies must be licensed and/or approved to do business in the State of Texas. Except for workers’ compensation, all insurers must have a minimum rating of A-: VII in the current A. M. Best Key Rating Guide or have reasonably equivalent financial strength and solvency to the satisfaction of Risk Management. If the rating is below that required, written approval of City is required. 5. All applicable policies shall include a Waiver of Subrogation (Rights of Recovery) in favor of the City. In addition, the Contractor agrees to waive all rights of subrogation against the Engineer (if applicable), and each additional insured identified in these Standard City Conditions. Failure of the City to demand such certificates or other evidence of full compliance with the insurance requirements or failure of the City to identify a deficiency from evidence that is provided shall not be construed as a waiver of Contractor’s obligation to maintain such lines of insurance coverage. 6. If insurance policies are not written for specified coverage limits, an Umbrella or Excess Liability insurance for any differences is required. Excess Liability shall follow form of the primary coverage. 7. Unless otherwise stated, all required insurance shall be written on the “occurrence basis”. If coverage is underwritten on a claims-made basis, the retroactive date shall be coincident with or prior to the date of the effective date of the agreement and the certificate of insurance shall state that the coverage is claims-made and the retroactive date. The insurance coverage shall be maintained for the duration of the Contract and for three (3) years following Final Acceptance provided under the Contract Documents or for the warranty period, whichever is longer. An annual certificate of insurance submitted to the City shall evidence such insurance coverage. 8. Policies shall have no exclusions by endorsements, which, neither nullify or amend, the required lines of coverage, nor decrease the limits of said coverage unless such endorsements are approved in writing by the City. In the event a Contract has been bid or executed and the exclusions are determined to be unacceptable or the City desires additional insurance coverage, and the City desires the contractor/engineer to obtain such coverage, the contract price shall be adjusted by the cost of the premium for such additional coverage plus 10%. 9. Any self-insured retention (SIR), in excess of $25,000.00, affecting required insurance coverage shall be approved by the City in regards to asset value and stockholders' equity. In Meacham Commerce Center CPN-103202 00 73 10- 9 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 9 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 lieu of traditional insurance, alternative coverage maintained through insurance pools or risk retention groups, must also be approved by City. 10. Any deductible in excess of $5,000.00, for any policy that does not provide coverage on a first-dollar basis, must be acceptable to and approved by the City. 11. City, at its sole discretion, reserves the right to review the insurance requirements and to make reasonable adjustments to insurance coverage’s and their limits when deemed necessary and prudent by the City based upon changes in statutory law, court decision or the claims history of the industry as well as of the contracting party to the City. The City shall be required to provide prior notice of 90 days, and the insurance adjustments shall be incorporated into the Work by Change Order. 12. City shall be entitled, upon written request and without expense, to receive copies of policies and endorsements thereto and may make any reasonable requests for deletion or revision or modifications of particular policy terms, conditions, limitations, or exclusions necessary to conform the policy and endorsements to the requirements of the Contract. Deletions, revisions, or modifications shall not be required where policy provisions are established by law or regulations binding upon either party or the underwriter on any such policies. 13. City shall not be responsible for the direct payment of insurance premium costs for Contractor’s insurance. 4.04 Contractor’s Insurance A. Workers Compensation and Employers’ Liability. Contractor shall purchase and maintain such insurance coverage with limits consistent with statutory benefits outlined in the Texas Workers’ Compensation Act (Texas Labor Code, Ch. 406, as amended), and minimum limits for Employers’ Liability as is appropriate for the Work being performed and as will provide protection from claims set forth below which may arise out of or result from Contractor’s performance of the Work and Contractor’s other obligations under the Contract Documents, whether it is to be performed by Contractor, any Subcontractor or Supplier, or by anyone directly or indirectly employed by any of them to perform any of the Work, or by anyone for whose acts any of them may be liable: 1. claims under workers’ compensation, disability benefits, and other similar employee benefit acts; 2. claims for damages because of bodily injury, occupational sickness or disease, or death of Contractor’s employees. 3. The limits of liability for the insurance shall provide the following coverages for not less than the following amounts or greater where required by Laws and Regulations a. Statutory limits b. Employer's liability Meacham Commerce Center CPN-103202 00 73 10- 10 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 10 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 1) $100,000 each accident/occurrence 2) $100,000 Disease - each employee 3) $500,000 Disease - policy limit B. Commercial General Liability. Coverage shall include but not be limited to covering liability (bodily injury or property damage) arising from: premises/operations, independent contractors, products/completed operations, personal injury, and liability under an insured contract. Insurance shall be provided on an occurrence basis, and as comprehensive as the current Insurance Services Office (ISO) policy. This insurance shall apply as primary insurance with respect to any other insurance or self-insurance programs afforded to the City. The Commercial General Liability policy, shall have no exclusions by endorsements that would alter of nullify premises/operations, products/completed operations, contractual, personal injury, or advertising injury, which are normally contained with the policy, unless the City approves such exclusions in writing. 1. For construction projects that present a substantial completed operation exposure, the City may require the contractor to maintain completed operations coverage for a minimum of no less than three (3) years following the completion of the project 2. Contractor's Liability Insurance under this Section which shall be on a per project basis covering the Contractor with minimum limits of: a. $1,000,000 each occurrence b. $2,000,000 aggregate limit 3. The policy must have an endorsement (Amendment – Aggregate Limits of Insurance) making the General Aggregate Limits apply separately to each job site. 4. The Commercial General Liability Insurance policies shall provide “X”, “C”, and “U” coverage’s. Verification of such coverage must be shown in the Remarks Article of the Certificate of Insurance. C. Automobile Liability. A commercial business auto policy shall provide coverage on “any auto”, defined as autos owned, hired and non-owned and provide indemnity for claims for damages because bodily injury or death of any person and or property damage arising out of the work, maintenance or use of any motor vehicle by the Contractor, any Subcontractor or Supplier, or by anyone directly or indirectly employed by any of them to perform any of the Work, or by anyone for whose acts any of them may be liable. 1. Automobile Liability, Contractor’s Liability Insurance under this Section, which shall be in an amount not less than the following amounts: a. Automobile Liability - a commercial business policy shall provide coverage on "Any Auto", defined as autos owned, hired and non-owned. Meacham Commerce Center CPN-103202 00 73 10- 11 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 11 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 1) $1,000,000 each accident on a combined single limit basis. Split limits are acceptable if limits are at least: 2) $250,000 Bodily Injury per person 3) $500,000 Bodily Injury per accident / 4) $100,000 Property Damage D. Railroad Protective Liability. If any of the work or any warranty work is within the limits of railroad right-of-way, the Contractor shall comply with the following requirements: 1. The Contractor’s construction activities will require its employees, agents, subcontractors, equipment, and material deliveries to cross railroad properties and tracks owned and operated by: ____________________________________________________________ Write the name of the railroad company. (If none, then write none) 2. The Contractor shall conduct its operations on railroad properties in such a manner as not to interfere with, hinder, or obstruct the railroad company in any manner whatsoever in the use or operation of its/their trains or other property. Such operations on railroad properties may require that Contractor to execute a “Right of Entry Agreement” with the particular railroad company or companies involved, and to this end the Contractor should satisfy itself as to the requirements of each railroad company and be prepared to execute the right-of-entry (if any) required by a railroad company. The requirements specified herein likewise relate to the Contractor’s use of private and/or construction access roads crossing said railroad company’s properties. 3. The Contractual Liability coverage required by Paragraph 5.04D of the General Conditions shall provide coverage for not less than the following amounts, issued by companies satisfactory to the City and to the Railroad Company for a term that continues for so long as the Contractor’s operations and work cross, occupy, or touch railroad property: a. General Aggregate: _____________________________________ Enter limits provided by Railroad Company (If none, write none) b. Each Occurrence: : _____________________________________ Enter limits provided by Railroad Company (If none, write none) 4. With respect to the above outlined insurance requirements, the following shall govern: a. Where a single railroad company is involved, the Contractor shall provide one insurance policy in the name of the railroad company. However, if more than one grade separation or at-grade crossing is affected by the Project at entirely separate locations on the line or lines of the same railroad company, separate coverage may be required, each in the amount stated above. b. Where more than one railroad company is operating on the same right-of-way or where several railroad companies are involved and operated on their own separate rights-of- Meacham Commerce Center CPN-103202 None None None 00 73 10- 12 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 12 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 way, the Contractor may be required to provide separate insurance policies in the name of each railroad company. c. If, in addition to a grade separation or an at-grade crossing, other work or activity is proposed on a railroad company’s right-of-way at a location entirely separate from the grade separation or at-grade crossing, insurance coverage for this work must be included in the policy covering the grade separation. d. If no grade separation is involved but other work is proposed on a railroad company’s right-of-way, all such other work may be covered in a single policy for that railroad, even though the work may be at two or more separate locations. 5. No work or activities on a railroad company’s property to be performed by the Contractor shall be commenced until the Contractor has furnished the City with an original policy or policies of the insurance for each railroad company named, as required above. All such insurance must be approved by the City and each affected Railroad Company prior to the Contractor’s beginning work. 6. The insurance specified above must be carried until all Work to be performed on the railroad right-of-way has been completed and the grade crossing, if any, is no longer used by the Contractor. In addition, insurance must be carried during all maintenance and/or repair work performed in the railroad right-of-way. Such insurance must name the railroad company as the insured, together with any tenant or lessee of the railroad company operating over tracks involved in the Project. E. Notification of Policy Cancellation: Contractor shall immediately notify City upon cancellation or other loss of insurance coverage. Contractor shall stop work until replacement insurance has been procured. There shall be no time credit for days not worked pursuant to this section. 4.05 Acceptance of Bonds and Insurance; Option to Replace If City has any objection to the coverage afforded by or other provisions of the bonds or insurance required to be purchased and maintained by the Contractor in accordance with Article 5 on the basis of non-conformance with the Contract Documents, the Developer and City shall so notify the Contractor in writing within 10 Business Days after receipt of the certificates (or other evidence requested). Contractor shall provide to the City such additional information in respect of insurance provided as the Developer or City may reasonably request. If Contractor does not purchase or maintain all of the bonds and insurance required by the Contract Documents, the Developer or City shall notify the Contractor in writing of such failure prior to the start of the Work, or of such failure to maintain prior to any change in the required coverage. ARTICLE 5 – CONTRACTOR’S RESPONSIBILITIES 5.01 Supervision and Superintendent A. Contractor shall supervise, inspect, and direct the Work competently and efficiently, devoting such attention thereto and applying such skills and expertise as may be necessary to perform the Meacham Commerce Center CPN-103202 00 73 10- 13 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 13 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 Work in accordance with the Contract Documents. Contractor shall be solely responsible for the means, methods, techniques, sequences, and procedures of construction. B. At all times during the progress of the Work, Contractor shall assign a competent, English- speaking, Superintendent who shall not be replaced without written notice to City. The Superintendent will be Contractor’s representative at the Site and shall have authority to act on behalf of Contractor. All communication given to or received from the Superintendent shall be binding on Contractor. C. Contractor shall notify the City 24 hours prior to moving areas during the sequence of construction. 5.02 Labor; Working Hours A. Contractor shall provide competent, suitably qualified personnel to perform construction as required by the Contract Documents. Contractor shall at all times maintain good discipline and order at the Site. B. Except as otherwise required for the safety or protection of persons or the Work or property at the Site or adjacent thereto, and except as otherwise stated in the Contract Documents, all Work at the Site shall be performed during Regular Working Hours. Contractor will not permit the performance of Work beyond Regular Working Hours or for Weekend Working Hours without City’s written consent (which will not be unreasonably withheld). Written request (by letter or electronic communication) to perform Work: 1. for beyond Regular Working Hours request must be made by noon at least two (2) Business Days prior 2. for Weekend Working Hours request must be made by noon of the preceding Thursday 3. for legal holidays request must be made by noon two Business Days prior to the legal holiday. 5.03 Services, Materials, and Equipment A. Unless otherwise specified in the Contract Documents, Contractor shall provide and assume full responsibility for all services, materials, equipment, labor, transportation, construction equipment and machinery, tools, appliances, fuel, power, light, heat, telephone, water, sanitary facilities, temporary facilities, and all other facilities and incidentals necessary for the performance, Contractor required testing, start-up, and completion of the Work. B. All materials and equipment incorporated into the Work shall be as specified or, if not specified, shall be of good quality and new, except as otherwise provided in the Contract Documents. All special warranties and guarantees required by the Specifications shall expressly run to the benefit of City. If required by City, Contractor shall furnish satisfactory evidence (including reports of required tests) as to the source, kind, and quality of materials and equipment. Meacham Commerce Center CPN-103202 00 73 10- 14 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 14 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 C. All materials and equipment to be incorporated into the Work shall be stored, applied, installed, connected, erected, protected, used, cleaned, and conditioned in accordance with instructions of the applicable Supplier, except as otherwise may be provided in the Contract Documents. 5.04 Project Schedule A. Contractor shall adhere to the Project Schedule established in accordance with Paragraph 2.01 and the General Requirements as it may be adjusted from time to time as provided below. 1. Contractor shall submit to City for acceptance (to the extent indicated in Paragraph 2.01 and the General Requirements) proposed adjustments in the Project Schedule. 2. Proposed adjustments in the Project Schedule that will change the Contract Time shall be submitted in accordance with the requirements of Article 9. Adjustments in Contract Time for projects with City participation shall be made by participating change orders. 5.05 Substitutes and “Or-Equals” A. Whenever an item of material or equipment is specified or described in the Contract Documents by using the name of a proprietary item or the name of a particular Supplier, the specification or description is intended to establish the type, function, appearance, and quality required. Unless the specification or description contains or is followed by words reading that no like, equivalent, or “or-equal” item or no substitution is permitted, other items of material or equipment of other Suppliers may be submitted to City for review under the circumstances described below. 1. “Or-Equal” Items: If in City’s sole discretion an item of material or equipment proposed by Contractor is functionally equal to that named and sufficiently similar so that no change in related Work will be required, it may be considered by City as an “or-equal” item, in which case review and approval of the proposed item may, in City’s sole discretion, be accomplished without compliance with some or all of the requirements for approval of proposed substitute items. For the purposes of this Paragraph 5.05.A.1, a proposed item of material or equipment will be considered functionally equal to an item so named if: a. City determines that: 1) it is at least equal in materials of construction, quality, durability, appearance, strength, and design characteristics; 2) it will reliably perform at least equally well the function and achieve the results imposed by the design concept of the completed Project as a functioning whole; and 3) it has a proven record of performance and availability of responsive service; and b. Contractor certifies that, if approved and incorporated into the Work: 1) there will be no increase in cost to the City or increase in Contract Time; and Meacham Commerce Center CPN-103202 00 73 10- 15 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 15 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 2) it will conform substantially to the detailed requirements of the item named in the Contract Documents. 2. Substitute Items: a. If in City’s sole discretion an item of material or equipment proposed by Contractor does not qualify as an “or-equal” item under Paragraph 5.05.A.1, it may be submitted as a proposed substitute item. b. Contractor shall submit sufficient information as provided below to allow City to determine if the item of material or equipment proposed is essentially equivalent to that named and an acceptable substitute therefor. Requests for review of proposed substitute items of material or equipment will not be accepted by City from anyone other than Contractor. c. Contractor shall make written application to City for review of a proposed substitute item of material or equipment that Contractor seeks to furnish or use. The application shall comply with Section 01 25 00 and: 1) shall certify that the proposed substitute item will: i. perform adequately the functions and achieve the results called for by the general design; ii. be similar in substance to that specified; iii. be suited to the same use as that specified; and 2) will state: i. the extent, if any, to which the use of the proposed substitute item will prejudice Contractor’s achievement of final completion on time; ii. whether use of the proposed substitute item in the Work will require a change in any of the Contract Documents (or in the provisions of any other direct contract with City for other work on the Project) to adapt the design to the proposed substitute item; iii. whether incorporation or use of the proposed substitute item in connection with the Work is subject to payment of any license fee or royalty; and 3) will identify: i. all variations of the proposed substitute item from that specified; ii. available engineering, sales, maintenance, repair, and replacement services; and Meacham Commerce Center CPN-103202 00 73 10- 16 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 16 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 4) shall contain an itemized estimate of all costs or credits that will result directly or indirectly from use of such substitute item, including costs of redesign and Damage Claims of other contractors affected by any resulting change. B. Substitute Construction Methods or Procedures: If a specific means, method, technique, sequence, or procedure of construction is expressly required by the Contract Documents, Contractor may furnish or utilize a substitute means, method, technique, sequence, or procedure of construction approved by City. Contractor shall submit sufficient information to allow City, in City’s sole discretion, to determine that the substitute proposed is equivalent to that expressly called for by the Contract Documents. Contractor shall make written application to City for review in the same manner as those provided in Paragraph 5.05.A.2. C. City’s Evaluation: City will be allowed a reasonable time within which to evaluate each proposal or submittal made pursuant to Paragraphs 5.05.A and 5.05.B. City may require Contractor to furnish additional data about the proposed substitute. City will be the sole judge of acceptability. No “or-equal” or substitute will be ordered, installed or utilized until City’s review is complete, which will be evidenced by a Change Order in the case of a substitute and an accepted Submittal for an “or-equal.” City will advise Contractor in writing of its determination. D. Special Guarantee: City may require Contractor to furnish at Contractor’s expense a special performance guarantee, warranty, or other surety with respect to any substitute. Contractor shall indemnify and hold harmless City and anyone directly or indirectly employed by them from and against any and all claims, damages, losses and expenses (including attorneys fees) arising out of the use of substituted materials or equipment. E. City’s Cost Reimbursement: City will record City’s costs in evaluating a substitute proposed or submitted by Contractor pursuant to Paragraphs 5.05.A.2 and 5.05.B. Whether or not City approves a substitute so proposed or submitted by Contractor, Contractor may be required to reimburse City for evaluating each such proposed substitute. Contractor may also be required to reimburse City for the charges for making changes in the Contract Documents. F. Contractor’s Expense: Contractor shall provide all data in support of any proposed substitute or “or-equal” at Contractor’s expense. G. Substitute Reimbursement: Costs (savings or charges) attributable to acceptance of a substitute shall be incorporated to the Contract by Participating Change Order. 5.06 Pre-Qualification of Bidders (Prime Contractors and Subcontractors) A. The Contractor and any subcontractors are required to be prequalified for the work types requiring pre-qualification 5.07 Concerning Subcontractors, Suppliers, and Others A. Minority and Women Owned Business Enterprise Compliance: Meacham Commerce Center CPN-103202 Oa 73 1D-17 Standard Crfy Canditions af The Construction Contract For Developer Awarded Projects Page 17 of 35 ❑ Required for this Conha�t. {Check this box if there is any City Parrici�rion) � Not Requu�ed far t}us Coutract. It is City golicy to enstue the full and equitaUle garticigatiou by Miuoi7ty and Wonten Business Enterprises (NI�BE) in the pro�tu�ement ❑f goods artd services an a cantrachial basis. If t}�e Conhact I]a�iunents provide far a MWBE goal, Cantractor is requued to coingly with the inteut of the City's MWSE �rdinance {as antended} Uy the followin�: 1. Conhactar shall, upon request by City, gravide coinplete and ac�urate infonuatiou re�arding actual wark perforuied by a MWBE on the Contract and paylnent therefor. 2. Conhactor will not inake additions, deletions, or suUstihitions of accepted MWBE withaut written consent af the City_ Any unjustified change or deletion shall be a uiaterial breach of Conhact and inay rest�lt in delaai�ient im accardance ��ith the pracediues autlined i� the Ordii�ance. 3. Contxactor shall, upon request Uy City, allaw an audit andlar exaiuivation of any books, recards, or �les in t}�e passession af t}�e Cantractor t�iat will substantiate the achial work perfoi�ned by an MWSE. Material uusrepresentatiau of any natw�e will Ue grouuds for tei�vnation of t}�e Contract_ Any such inisrepresentatian inay Ue gxounds for disqualification of Contractor ta Uid on fiihue conh�acts with the City for a pei7od of not less t�ian three years_ S. Conhaetor shall Ue fi�11y responsiUle to City for all aets and ouussions ❑f t}�e Suhconhactors, Suppliers, and ot}�er iudividuals or entities perfoi��iug or fiu-uishin� any of the Work ji�st as Conhactar is responsible for Contractor's own acts and omissions. Nothiug iv the Contra�t Docuineuts: 1. sltall create far the benefit of any suGh Subeonha�tor, Supplier, or other i�dividual ar entity any �ont�ach�l relationship betwee� City and any such Subcouti�actor, Supplier ❑r other individual or entity; nor 2. shall create any aUligatian on the part ❑f City to pay or to see ta the payment of any moneys due any such Subcontractor, Supglier, ar other individual or entity excegt as uiay otheivvise Ue reqtured by Laws and Aegulations. C. Conhaetor shall be solely responsible for sc�iedi�lin� and caarriivating the Work of SuUcontractors, Suppliers, and othe�� indi�iduals or entities peiforuun� or fiu�ishing any of t}�e Work under a au�ect or inciu�ect canha�t with Cantractor. D. All Suhcanhactors, Suppliers, and such ot�ier individuals ar entities peifaruun� or fiu�ishing any of the Wark shall coiiuuunicate with City t}uough Cantr�actor. E. A11 Work geifoi�ied for Coutractar Uy a Subcontractor or Sugplier will Ue ptu�suant to an appropriate a��eeinent between Canhactor and the Subco�tractar or Supplier which specifically biuds t�ie SuUcontractar or Supplier ta t}�e agplicaUle terins and �onc�itions of these Cantract CITY dF FORT WORTH STANDAR� CTTY CONDTITONS — DEVELaPER AR7AR�EI3 PRQ7ECTS Meacham Couunerce Center Res2sed ]anuTry 16, 2613 CPN-103202 Oa 73 1D-18 Standard Crfy Canditions af The Construction Contract For Developer Awarded Projects Page 18 of 35 Docuineuts, Conri�actor shall grovide City contract nurnUers and reference niunbers to t}�e SuUcantractors andlor Suppliers. 5.a8 � c�ge Rates ❑ Required for this Contract. � Not Aequu�ed for t}us Co�tract. A. D�r�� to p��> P�evaalang ��age 1Zafes. T1ie Conha�tor shall �omply with all reqtureiueuts of Chapter 225$, Texas Government Code (as arneuded}_ ivcludutg the paylnent of not less than t�ie rates detei7uived by the City Cou.ncil of t}�e City of Fort Worth to be the prevailing wage rates in accardance with Chapter 2258. Suc}� prevailuY� wa�e rates are included in t}�ese Contract Docuineuts. S. Pefral�° for T�ioTatiofr. A Contra�tar ar any Subconh�actar w}�o does not pay the pre�ailin� wage s}�all, ugon deinaud tnade Uy the City, pay to the City $b0 for each worker eiuployed for eaeh calendar day or part af tlte d�y that the worker is paid less t�ian the prevailivg wage rates stipt�lated in these conha�t dociunents. Tlus penalty shall Ue retained lay the City to ❑ffset its adininishative costs, pursuartt to Texas Governrnent Cade 2258.023. C. Conaplairrts of i�iolations afrd Ca�° Deter•rnitrafaor� af Good Cause. �n receipt of ivforinatian, inchiduig a coinglaint Uy a worker, �on�emiug an alleged violation of 225$.023, T'exas Governuient Cflde, by a Canri�actar or Sub�ouri�actor, the City shall uiake an initial dete�ninatian, before the 31st day after the date t}�e City receives tlie information, as to whether goad cause exists to Uelieve that the violation oc�uired. The City s}�all notify in wi7ting t}�e Conhactor or SuU�anri�actor and any affected worker af its uutial deteruunation_ iJpon t}�e City's deteiYnivation that there is good cause to believe the Conri�actor ar SuUcantractor �ias violated Chapter 2258, t�ie City shall retain the fiill amounts claimed Uy t}�e �launant or claiuiants as t�ie difference Uetween wages paid aud wa�es due u.nder the pre�ailing wage rates, suc�i amounts heiug subhacted fram successive progxess payinents pending a i�inal detei��ination of the vialation. D. Arbrtratzofr Re.qararer� af Violatran Nnt ResolverT. An issiue relatiug to an alleged violatiau of Section 2258_023, Texas Go�enunent Cade, ivcluding a penalty awed ta the City ar an affected worker, shall be subinitted to bindin� arUitration in accordance with the Texas General Arbitration Act {Article 224 et seq., Revised Statutes} if the Contractor or SuUcontractor and any affected worker does not resolve the issue by agX�eezuent before t}�e 15th day after the date the City makes its initial detei�vnation ptusuaut to Para�rap�i C abave. If the gersons required to arbihate under t}us section do not a�ree on an arbitrator Uefore the l lt}� day after t}�e date that arbihation is requu�ed, a district coiu�t shall appoiut an arUit�ator on the petition of any ❑f the persans. The City is not a party ui the arUitratian. The decisian and award af the arUihatar is fival and Uindin� an all parties and uiay Ue e�far�ed iu any caiu-t of �ompetent jurisdictiou. E. Records to �e. Maintanred. The Contractor and ea�h Sul�contractor shall, for a geriod of tliree (3) years followiug the date of ac�eptance ❑f the wflrk, uiaiutaiu re�ards t�iat show (i) the name and CITY dF FORT WORTH STANDAR� CTTY CONDTITONS — DEVELaPER AR7AR�EI3 PRQ7ECTS Meacham Couunerce Center Res2sed ]anuTry 16, 2613 CPN-103202 00 73 10- 19 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 19 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 occupation of each worker employed by the Contractor in the construction of the Work provided for in this Contract; and (ii) the actual per diem wages paid to each worker. The records shall be open at all reasonable hours for inspection by the City. The provisions of Paragraph 6.23, Right to Audit, shall pertain to this inspection. F. Progress Payments. With each progress payment or payroll period, whichever is less, the Contractor shall submit an affidavit stating that the Contractor has complied with the requirements of Chapter 2258, Texas Government Code. G. Posting of Wage Rates. The Contractor shall post prevailing wage rates in a conspicuous place at all times. H. Subcontractor Compliance. The Contractor shall include in its subcontracts and/or shall otherwise require all of its Subcontractors to comply with Paragraphs A through G above. 5.09 Patent Fees and Royalties A. To the fullest extent permitted by Laws and Regulations, Contractor shall indemnify and hold harmless City, from and against all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) arising out of or relating to any infringement of patent rights or copyrights incident to the use in the performance of the Work or resulting from the incorporation in the Work of any invention, design, process, product, or device not specified in the Contract Documents. 5.10 Laws and Regulations A. Contractor shall give all notices required by and shall comply with all Laws and Regulations applicable to the performance of the Work. Except where otherwise expressly required by applicable Laws and Regulations, the City shall not be responsible for monitoring Contractor’s compliance with any Laws or Regulations. B. If Contractor performs any Work knowing or having reason to know that it is contrary to Laws or Regulations, Contractor shall bear all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) arising out of or relating to such Work. However, it shall not be Contractor’s responsibility to make certain that the Specifications and Drawings are in accordance with Laws and Regulations, but this shall not relieve Contractor of Contractor’s obligations under Paragraph 3.01. 5.11 Use of Site and Other Areas A. Limitation on Use of Site and Other Areas: 1. Contractor shall confine construction equipment, the storage of materials and equipment, and the operations of workers to the Site and other areas permitted by Laws and Regulations, and shall not unreasonably encumber the Site and other areas with construction equipment or Meacham Commerce Center CPN-103202 00 73 10- 20 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 20 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 other materials or equipment. Contractor shall assume full responsibility for any damage to any such land or area, or to the owner or occupant thereof, or of any adjacent land or areas resulting from the performance of the Work. 2. At any time when, in the judgment of the City, the Contractor has obstructed or closed or is carrying on operations in a portion of a street, right-of-way, or easement greater than is necessary for proper execution of the Work, the City may require the Contractor to finish the section on which operations are in progress before work is commenced on any additional area of the Site. 3. Should any Damage Claim be made by any such owner or occupant because of the performance of the Work, Contractor shall promptly attempt to resolve the Damage Claim. 4. Pursuant to Paragraph 5.18, Contractor shall indemnify and hold harmless City, from and against all claims, costs, losses, and damages arising out of or relating to any claim or action, legal or equitable, brought by any such owner or occupant against City. B. Removal of Debris During Performance of the Work: During the progress of the Work Contractor shall keep the Site and other areas free from accumulations of waste materials, rubbish, and other debris. Removal and disposal of such waste materials, rubbish, and other debris shall conform to applicable Laws and Regulations. C. Site Maintenance Cleaning: 24 hours after written notice is given to the Contractor that the clean-up on the job site is proceeding in a manner unsatisfactory to the City or Developer, if the Contractor fails to correct the unsatisfactory procedure, the City may take such direct action as the City deems appropriate to correct the clean-up deficiencies cited to the Contractor in the written notice (by letter or electronic communication), and shall be entitled to recover its cost in doing so. The City may withhold Final Acceptance until clean-up is complete and cost are recovered. D. Final Site Cleaning: Prior to Final Acceptance of the Work Contractor shall clean the Site and the Work and make it ready for utilization by City or adjacent property owner. At the completion of the Work Contractor shall remove from the Site all tools, appliances, construction equipment and machinery, and surplus materials and shall restore to original condition or better all property disturbed by the Work. E. Loading Structures: Contractor shall not load nor permit any part of any structure to be loaded in any manner that will endanger the structure, nor shall Contractor subject any part of the Work or adjacent property to stresses or pressures that will endanger it. 5.12 Record Documents A. Contractor shall maintain in a safe place at the Site or in a place designated by the Contractor and approved by the City, one (1) record copy of all Drawings, Specifications, Addenda, Change Orders, Field Orders, and written interpretations and clarifications in good order and annotated to show changes made during construction. These record documents together with all approved Meacham Commerce Center CPN-103202 00 73 10- 21 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 21 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 Samples and a counterpart of all accepted Submittals will be available to City for reference. Upon completion of the Work, these record documents, any operation and maintenance manuals, and Submittals will be delivered to City prior to Final Inspection. Contractor shall include accurate locations for buried and imbedded items. 5.13 Safety and Protection A. Contractor shall be solely responsible for initiating, maintaining and supervising all safety precautions and programs in connection with the Work. Such responsibility does not relieve Subcontractors of their responsibility for the safety of persons or property in the performance of their work, nor for compliance with applicable safety Laws and Regulations. Contractor shall take all necessary precautions for the safety of, and shall provide the necessary protection to prevent damage, injury or loss to: 1. all persons on the Site or who may be affected by the Work; 2. all the Work and materials and equipment to be incorporated therein, whether in storage on or off the Site; and 3. other property at the Site or adjacent thereto, including trees, shrubs, lawns, walks, pavements, roadways, structures, utilities, and Underground Facilities not designated for removal, relocation, or replacement in the course of construction. B. Contractor shall comply with all applicable Laws and Regulations relating to the safety of persons or property, or to the protection of persons or property from damage, injury, or loss; and shall erect and maintain all necessary safeguards for such safety and protection. Contractor shall notify owners of adjacent property and of Underground Facilities and other utility owners when prosecution of the Work may affect them, and shall cooperate with them in the protection, removal, relocation, and replacement of their property. C. Contractor shall comply with the applicable requirements of City’s safety programs, if any. D. Contractor shall inform City of the specific requirements of Contractor’s safety program, if any, with which City’s employees and representatives must comply while at the Site. E. All damage, injury, or loss to any property referred to in Paragraph 5.13.A.2 or 5.13.A.3 caused, directly or indirectly, in whole or in part, by Contractor, any Subcontractor, Supplier, or any other individual or entity directly or indirectly employed by any of them to perform any of the Work, or anyone for whose acts any of them may be liable, shall be remedied by Contractor. F. Contractor’s duties and responsibilities for safety and for protection of the Work shall continue until such time as all the Work is completed and City has accepted the Work. 5.14 Safety Representative Contractor shall inform City in writing of Contractor’s designated safety representative at the Site. Meacham Commerce Center CPN-103202 00 73 10- 22 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 22 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 5.15 Hazard Communication Programs Contractor shall be responsible for coordinating any exchange of material safety data sheets or other hazard communication information required to be made available to or exchanged between or among employers in accordance with Laws or Regulations. 5.16 Submittals A. Contractor shall submit required Submittals to City for review and acceptance. Each submittal will be identified as required by City. 1. Submit number of copies specified in the General Requirements. 2. Data shown on the Submittals will be complete with respect to quantities, dimensions, specified performance and design criteria, materials, and similar data to show City the services, materials, and equipment Contractor proposes to provide and to enable City to review the information for the limited purposes required by Paragraph 5.16.C. 3. Submittals submitted as herein provided by Contractor and reviewed by City for conformance with the design concept shall be executed in conformity with the Contract Documents unless otherwise required by City. 4. When Submittals are submitted for the purpose of showing the installation in greater detail, their review shall not excuse Contractor from requirements shown on the Drawings and Specifications. 5. For-Information-Only submittals upon which the City is not expected to conduct review or take responsive action may be so identified in the Contract Documents. 6. Submit required number of Samples specified in the Specifications. 7. Clearly identify each Sample as to material, Supplier, pertinent data such as catalog numbers, the use for which intended and other data as City may require to enable City to review the submittal for the limited purposes required by Paragraph 5.16.C. B. Where a Submittal is required by the Contract Documents or the Schedule of Submittals, any related Work performed prior to City’s review and acceptance of the pertinent submittal will be at the sole expense and responsibility of Contractor. C. City’s Review: 1. City will provide timely review of required Submittals in accordance with the Schedule of Submittals acceptable to City. City’s review and acceptance will be only to determine if the items covered by the submittals will, after installation or incorporation in the Work, conform to the information given in the Contract Documents and be compatible with the design concept of the completed Project as a functioning whole as indicated by the Contract Documents. Meacham Commerce Center CPN-103202 00 73 10- 23 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 23 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 2. City’s review and acceptance will not extend to means, methods, techniques, sequences, or procedures of construction (except where a particular means, method, technique, sequence, or procedure of construction is specifically and expressly called for by the Contract Documents) or to safety precautions or programs incident thereto. The review and acceptance of a separate item as such will not indicate approval of the assembly in which the item functions. 3. City’s review and acceptance shall not relieve Contractor from responsibility for any variation from the requirements of the Contract Documents unless Contractor has complied with the requirements of Section 01 33 00 and City has given written acceptance of each such variation by specific written notation thereof incorporated in or accompanying the Submittal. City’s review and acceptance shall not relieve Contractor from responsibility for complying with the requirements of the Contract Documents. 5.17 Contractor’s General Warranty and Guarantee A. Contractor warrants and guarantees to City that all Work will be in accordance with the Contract Documents and will not be defective. City and its officers, directors, members, partners, employees, agents, consultants, and subcontractors shall be entitled to rely on representation of Contractor’s warranty and guarantee. B. Contractor’s warranty and guarantee hereunder excludes defects or damage caused by: 1. abuse, modification, or improper maintenance or operation by persons other than Contractor, Subcontractors, Suppliers, or any other individual or entity for whom Contractor is responsible; or 2. normal wear and tear under normal usage. C. Contractor’s obligation to perform and complete the Work in accordance with the Contract Documents shall be absolute. None of the following will constitute an acceptance of Work that is not in accordance with the Contract Documents or a release of Contractor’s obligation to perform the Work in accordance with the Contract Documents: 1. observations by City; 2. recommendation or payment by City or Developer of any progress or final payment; 3. the issuance of a certificate of Final Acceptance by City or any payment related thereto by City; 4. use or occupancy of the Work or any part thereof by City; 5. any review and acceptance of a Submittal by City; 6. any inspection, test, or approval by others; or Meacham Commerce Center CPN-103202 00 73 10- 24 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 24 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 7. any correction of defective Work by City. D. The Contractor shall remedy any defects or damages in the Work and pay for any damage to other work or property resulting therefrom which shall appear within a period of two (2) years from the date of Final Acceptance of the Work unless a longer period is specified and shall furnish a good and sufficient maintenance bond, complying with the requirements of Article 4.02.B. The City will give notice of observed defects with reasonable promptness. 5.18 Indemnification A. Contractor covenants and agrees to indemnify, hold harmless and defend, at its own expense, the City, its officers, servants and employees, from and against any and all claims arising out of, or alleged to arise out of, the work and services to be performed by the Contractor, its officers, agents, employees, subcontractors, licenses or invitees under this Contract. THIS INDEMNIFICATION PROVISION IS SPECIFICALLY INTENDED TO OPERATE AND BE EFFECTIVE EVEN IF IT IS ALLEGED OR PROVEN THAT ALL OR SOME OF THE DAMAGES BEING SOUGHT WERE CAUSED, IN WHOLE OR IN PART, BY ANY ACT, OMISSION OR NEGLIGENCE OF THE CITY. This indemnity provision is intended to include, without limitation, indemnity for costs, expenses and legal fees incurred by the City in defending against such claims and causes of actions. B. Contractor covenants and agrees to indemnify and hold harmless, at its own expense, the City, its officers, servants and employees, from and against any and all loss, damage or destruction of property of the City, arising out of, or alleged to arise out of, the work and services to be performed by the Contractor, its officers, agents, employees, subcontractors, licensees or invitees under this Contract. THIS INDEMNIFICATION PROVISION IS SPECIFICALLY INTENDED TO OPERATE AND BE EFFECTIVE EVEN IF IT IS ALLEGED OR PROVEN THAT ALL OR SOME OF THE DAMAGES BEING SOUGHT WERE CAUSED, IN WHOLE OR IN PART, BY ANY ACT, OMISSION OR NEGLIGENCE OF THE CITY. 5.19 Delegation of Professional Design Services A. Contractor will not be required to provide professional design services unless such services are specifically required by the Contract Documents for a portion of the Work or unless such services are required to carry out Contractor’s responsibilities for construction means, methods, techniques, sequences and procedures. B. If professional design services or certifications by a design professional related to systems, materials or equipment are specifically required of Contractor by the Contract Documents, City will specify all performance and design criteria that such services must satisfy. Contractor shall cause such services or certifications to be provided by a properly licensed professional, whose signature and seal shall appear on all drawings, calculations, specifications, certifications, and Submittals prepared by such professional. Submittals related to the Work designed or certified by such professional, if prepared by others, shall bear such professional’s written approval when submitted to City. Meacham Commerce Center CPN-103202 00 73 10- 25 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 25 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 C. City shall be entitled to rely upon the adequacy, accuracy and completeness of the services, certifications or approvals performed by such design professionals, provided City has specified to Contractor performance and design criteria that such services must satisfy. D. Pursuant to this Paragraph 5.19, City’s review and acceptance of design calculations and design drawings will be only for the limited purpose of checking for conformance with performance and design criteria given and the design concept expressed in the Contract Documents. City’s review and acceptance of Submittals (except design calculations and design drawings) will be only for the purpose stated in Paragraph 5.16.C. 5.20 Right to Audit: A. The City reserves the right to audit all projects utilizing City funds B. The Contractor agrees that the City shall, until the expiration of three (3) years after final payment under this Contract, have access to and the right to examine and photocopy any directly pertinent books, documents, papers, and records of the Contractor involving transactions relating to this Contract. Contractor agrees that the City shall have access during Regular Working Hours to all necessary Contractor facilities and shall be provided adequate and appropriate work space in order to conduct audits in compliance with the provisions of this Paragraph. The City shall give Contractor reasonable advance notice of intended audits. C. Contractor further agrees to include in all its subcontracts hereunder a provision to the effect that the subcontractor agrees that the City shall, until the expiration of three (3) years after final payment under this Contract, have access to and the right to examine and photocopy any directly pertinent books, documents, papers, and records of such Subcontractor, involving transactions to the subcontract, and further, that City shall have access during Regular Working Hours to all Subcontractor facilities, and shall be provided adequate and appropriate work space in order to conduct audits in compliance with the provisions of this Paragraph. The City shall give Subcontractor reasonable advance notice of intended audits. D. Contractor and Subcontractor agree to photocopy such documents as may be requested by the City. The City agrees to reimburse Contractor for the cost of the copies as follows at the rate published in the Texas Administrative Code in effect as of the time copying is performed. 5.21 Nondiscrimination A. The City is responsible for operating Public Transportation Programs and implementing transit- related projects, which are funded in part with Federal financial assistance awarded by the U.S. Department of Transportation and the Federal Transit Administration (FTA), without discriminating against any person in the United States on the basis of race, color, or national origin. B. Title VI, Civil Rights Act of 1964 as amended: Contractor shall comply with the requirements of the Act and the Regulations as further defined in the Supplementary Conditions for any project receiving Federal assistance. Meacham Commerce Center CPN-103202 00 73 10- 26 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 26 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 ARTICLE 6 – OTHER WORK AT THE SITE 6.01 Related Work at Site A. City may perform other work related to the Project at the Site with City’s employees, or other City contractors, or through other direct contracts therefor, or have other work performed by utility owners. If such other work is not noted in the Contract Documents, then written notice thereof will be given to Contractor prior to starting any such other work; and B. Contractor shall afford each other contractor who is a party to such a direct contract, each utility owner, and City, if City is performing other work with City’s employees or other City contractors, proper and safe access to the Site, provide a reasonable opportunity for the introduction and storage of materials and equipment and the execution of such other work, and properly coordinate the Work with theirs. Contractor shall do all cutting, fitting, and patching of the Work that may be required to properly connect or otherwise make its several parts come together and properly integrate with such other work. Contractor shall not endanger any work of others by cutting, excavating, or otherwise altering such work; provided, however, that Contractor may cut or alter others' work with the written consent of City and the others whose work will be affected. C. If the proper execution or results of any part of Contractor’s Work depends upon work performed by others under this Article 7, Contractor shall inspect such other work and promptly report to City in writing any delays, defects, or deficiencies in such other work that render it unavailable or unsuitable for the proper execution and results of Contractor’s Work. Contractor’s failure to so report will constitute an acceptance of such other work as fit and proper for integration with Contractor’s Work except for latent defects in the work provided by others. ARTICLE 7 – CITY’S RESPONSIBILITIES 7.01 Inspections, Tests, and Approvals City’s responsibility with respect to certain inspections, tests, and approvals is set forth in Paragraph 11.03. 7.02 Limitations on City’s Responsibilities A. The City shall not supervise, direct, or have control or authority over, nor be responsible for, Contractor’s means, methods, techniques, sequences, or procedures of construction, or the safety precautions and programs incident thereto, or for any failure of Contractor to comply with Laws and Regulations applicable to the performance of the Work. City will not be responsible for Contractor’s failure to perform the Work in accordance with the Contract Documents. B. City will notify the Contractor of applicable safety plans pursuant to Paragraph 5.13. Meacham Commerce Center CPN-103202 00 73 10- 27 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 27 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 7.03 Compliance with Safety Program While at the Site, City’s employees and representatives shall comply with the specific applicable requirements of Contractor’s safety programs of which City has been informed pursuant to Paragraph 5.13. ARTICLE 8 – CITY’S OBSERVATION STATUS DURING CONSTRUCTION 8.01 City’s Project Representative City will provide one or more Project Representative(s) during the construction period. The duties and responsibilities and the limitations of authority of City’s representative during construction are set forth in the Contract Documents. A. City’s Project Representative will make visits to the Site at intervals appropriate to the various stages of construction as City deems necessary in order to observe the progress that has been made and the quality of the various aspects of Contractor’s executed Work. Based on information obtained during such visits and observations, City’s Project Representative will determine, in general, if the Work is proceeding in accordance with the Contract Documents. City’s Project Representative will not be required to make exhaustive or continuous inspections on the Site to check the quality or quantity of the Work. City’s Project Representative’s efforts will be directed toward providing City a greater degree of confidence that the completed Work will conform generally to the Contract Documents. B. City’s Project Representative’s visits and observations are subject to all the limitations on authority and responsibility in the Contract Documents. 8.02 Authorized Variations in Work City’s Project Representative may authorize minor variations in the Work from the requirements of the Contract Documents which do not involve an adjustment in the Contract Price or the Contract Time and are compatible with the design concept of the completed Project as a functioning whole as indicated by the Contract Documents. These may be accomplished by a Field Order and will be binding on City Developer, and also on Contractor, who shall perform the Work involved promptly. 8.03 Rejecting Defective Work City will have authority to reject Work which City’s Project Representative believes to be defective, or will not produce a completed Project that conforms to the Contract Documents or that will prejudice the integrity of the design concept of the completed Project as a functioning whole as indicated by the Contract Documents. City will have authority to conduct special inspection or testing of the Work as provided in Article 11, whether or not the Work is fabricated, installed, or completed. Meacham Commerce Center CPN-103202 00 73 10- 28 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 28 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 8.04 Determinations for Work Performed Contractor will determine the actual quantities and classifications of Work performed. City’s Project Representative will review with Contractor the preliminary determinations on such matters before rendering a written recommendation. City’s written decision will be final (except as modified to reflect changed factual conditions or more accurate data). ARTICLE 9 – CHANGES IN THE WORK 9.01 Authorized Changes in the Work A. Without invalidating the Contract and without notice to any surety, City may, at any time or from time to time, order Extra Work. Upon notice of such Extra Work, Contractor shall promptly proceed with the Work involved which will be performed under the applicable conditions of the Contract Documents (except as otherwise specifically provided). Extra Work shall be memorialized by a Participating Change Order which may or may not precede an order of Extra work. B. For minor changes of Work not requiring changes to Contract Time or Contract Price on a project with City participation, a Field Order may be issued by the City. 9.02 Notification to Surety If the provisions of any bond require notice to be given to a surety of any change affecting the general scope of the Work or the provisions of the Contract Documents (including, but not limited to, Contract Price or Contract Time), the giving of any such notice will be Contractor’s responsibility. The amount of each applicable bond will be adjusted by the Contractor to reflect the effect of any such change. ARTICLE 10 – CHANGE OF CONTRACT PRICE; CHANGE OF CONTRACT TIME 10.01 Change of Contract Price A. The Contract Price may only be changed by a Participating Change Order for projects with City participation. 10.02 Change of Contract Time A. The Contract Time may only be changed by a Participating Change Order for projects with City participation. 10.03 Delays A. If Contractor is delayed, City shall not be liable to Contractor for any claims, costs, losses, or damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) sustained by Contractor on or in connection with any other project or anticipated project. Meacham Commerce Center CPN-103202 00 73 10- 29 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 29 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 ARTICLE 11 – TESTS AND INSPECTIONS; CORRECTION, REMOVAL OR ACCEPTANCE OF DEFECTIVE WORK 11.01 Notice of Defects Notice of all defective Work of which City has actual knowledge will be given to Contractor. Defective Work may be rejected, corrected, or accepted as provided in this Article 13. 11.02 Access to Work City, independent testing laboratories, and governmental agencies with jurisdictional interests will have access to the Site and the Work at reasonable times for their observation, inspection, and testing. Contractor shall provide them proper and safe conditions for such access and advise them of Contractor’s safety procedures and programs so that they may comply therewith as applicable. 11.03 Tests and Inspections A. Contractor shall give City timely notice of readiness of the Work for all required inspections, tests, or approvals and shall cooperate with inspection and testing personnel to facilitate required inspections or tests. B. If Contract Documents, Laws or Regulations of any public body having jurisdiction require any of the Work (or part thereof) to be inspected, tested, or approved, Contractor shall assume full responsibility for arranging and obtaining such independent inspections, tests, retests or approvals, pay all costs in connection therewith, and furnish City the required certificates of inspection or approval; excepting, however, those fees specifically identified in the Supplementary Conditions or any Texas Department of Licensure and Regulation (TDLR) inspections, which shall be paid as described in the Supplementary Conditions. C. Contractor shall be responsible for arranging and obtaining and shall pay all costs in connection with any inspections, tests, re-tests, or approvals required for City’s acceptance of materials or equipment to be incorporated in the Work; or acceptance of materials, mix designs, or equipment submitted for approval prior to Contractor’s purchase thereof for incorporation in the Work. Such inspections, tests, re-tests, or approvals shall be performed by organizations approved by City. D. City may arrange for the services of an independent testing laboratory (“Testing Lab”) to perform any inspections or tests (“Testing”) for any part of the Work, as determined solely by City. 1. City will coordinate such Testing to the extent possible, with Contractor; 2. Should any Testing under this Section 11.03 D result in a “fail”, “did not pass” or other similar negative result, the Contractor shall be responsible for paying for any and all retests. Contractor’s cancellation without cause of City initiated Testing shall be deemed a negative result and require a retest. Meacham Commerce Center CPN-103202 00 73 10- 30 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 30 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 3. Any amounts owed for any retest under this Section 11.03 D shall be paid directly to the Testing Lab by Contractor. City will forward all invoices for retests to Developer/Contractor. 4. If Contractor fails to pay the Testing Lab, City will not issue a letter of Final Acceptance until the Testing Lab is Paid E. If any Work (or the work of others) that is to be inspected, tested, or approved is covered by Contractor without written concurrence of City, Contractor shall, if requested by City, uncover such Work for observation. 11.04 Uncovering Work A. If any Work is covered contrary to the Contract Documents or specific instructions by the City, it must, if requested by City, be uncovered for City’s observation and replaced at Contractor’s expense. 11.05 City May Stop the Work If the Work is defective, or Contractor fails to supply sufficient skilled workers or suitable materials or equipment, or fails to perform the Work in such a way that the completed Work will conform to the Contract Documents, City may order Contractor to stop the Work, or any portion thereof, until the cause for such order has been eliminated; however, this right of City to stop the Work shall not give rise to any duty on the part of City to exercise this right for the benefit of Contractor, any Subcontractor, any Supplier, any other individual or entity, or any surety for, or employee or agent of any of them. 11.06 Correction or Removal of Defective Work A. Promptly after receipt of written notice, Contractor shall correct all defective Work pursuant to an acceptable schedule, whether or not fabricated, installed, or completed, or, if the Work has been rejected by City, remove it from the Project and replace it with Work that is not defective. Contractor shall pay all claims, costs, additional testing, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) arising out of or relating to such correction or removal (including but not limited to all costs of repair or replacement of work of others). Failure to require the removal of any defective Work shall not constitute acceptance of such Work. B. When correcting defective Work under the terms of this Paragraph 11.06 or Paragraph 11.07, Contractor shall take no action that would void or otherwise impair City’s special warranty and guarantee, if any, on said Work. 11.07 Correction Period A. If within two (2) years after the date of Final Acceptance (or such longer period of time as may be prescribed by the terms of any applicable special guarantee required by the Contract Meacham Commerce Center CPN-103202 00 73 10- 31 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 31 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 Documents), any Work is found to be defective, or if the repair of any damages to the land or areas made available for Contractor’s use by City or permitted by Laws and Regulations as contemplated in Paragraph 5.10.A is found to be defective, Contractor shall promptly, without cost to City and in accordance with City’s written instructions: 1. repair such defective land or areas; or 2. correct such defective Work; or 3. if the defective Work has been rejected by City, remove it from the Project and replace it with Work that is not defective, and 4. satisfactorily correct or repair or remove and replace any damage to other Work, to the work of others or other land or areas resulting therefrom. B. If Contractor does not promptly comply with the terms of City’s written instructions, or in an emergency where delay would cause serious risk of loss or damage, City may have the defective Work corrected or repaired or may have the rejected Work removed and replaced. All claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or other dispute resolution costs) arising out of or relating to such correction or repair or such removal and replacement (including but not limited to all costs of repair or replacement of work of others) will be paid by Contractor. C. Where defective Work (and damage to other Work resulting therefrom) has been corrected or removed and replaced under this Paragraph 11.07, the correction period hereunder with respect to such Work may be required to be extended for an additional period of one year after the end of the initial correction period. City shall provide 30 days written notice to Contractor and Developer should such additional warranty coverage be required. Contractor’s obligations under this Paragraph 11.07 are in addition to any other obligation or warranty. The provisions of this Paragraph 11.07 shall not be construed as a substitute for, or a waiver of, the provisions of any applicable statute of limitation or repose. 11.08 City May Correct Defective Work A. If Contractor fails within a reasonable time after written notice from City to correct defective Work, or to remove and replace rejected Work as required by City in accordance with Paragraph 11.06.A, or if Contractor fails to perform the Work in accordance with the Contract Documents, or if Contractor fails to comply with any other provision of the Contract Documents, City may, after seven (7) days written notice to Contractor and the Developer, correct, or remedy any such deficiency. B. In exercising the rights and remedies under this Paragraph 11.09, City shall proceed expeditiously. In connection with such corrective or remedial action, City may exclude Contractor from all or part of the Site, take possession of all or part of the Work and suspend Contractor’s services related thereto, and incorporate in the Work all materials and equipment incorporated in the Work, stored at the Site or for which City has paid Contractor but which are Meacham Commerce Center CPN-103202 00 73 10- 32 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 32 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 stored elsewhere. Contractor shall allow City, City’s representatives, agents, consultants, employees, and City’s other contractors, access to the Site to enable City to exercise the rights and remedies under this Paragraph. C. All claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or other dispute resolution costs) incurred or sustained by City in exercising the rights and remedies under this Paragraph 13.09 will be charged against Contractor, and a Change Order will be issued incorporating the necessary revisions in the Contract Documents with respect to the Work; and City shall be entitled to an appropriate decrease in the Contract Price. D. Contractor shall not be allowed an extension of the Contract Time because of any delay in the performance of the Work attributable to the exercise of City’s rights and remedies under this Paragraph 11.09. ARTICLE 12 – COMPLETION 12.01 Contractor’s Warranty of Title Contractor warrants and guarantees that title to all Work, materials, and equipment covered by any Application for Payment will pass to City no later than the time of Final Acceptance and shall be free and clear of all Liens. 12.02 Partial Utilization A. Prior to Final Acceptance of all the Work, City may use or occupy any substantially completed part of the Work which has specifically been identified in the Contract Documents, or which City, determines constitutes a separately functioning and usable part of the Work that can be used by City for its intended purpose without significant interference with Contractor’s performance of the remainder of the Work. City at any time may notify Contractor in writing to permit City to use or occupy any such part of the Work which City determines to be ready for its intended use, subject to the following conditions: 1. Contractor at any time may notify City in writing that Contractor considers any such part of the Work ready for its intended use. 2. Within a reasonable time after notification as enumerated in Paragraph 14.05.A.1, City and Contractor shall make an inspection of that part of the Work to determine its status of completion. If City does not consider that part of the Work to be substantially complete, City will notify Contractor in writing giving the reasons therefor. 3. Partial Utilization will not constitute Final Acceptance by City. 12.03 Final Inspection A. Upon written notice from Contractor that the entire Work is complete in accordance with the Contract Documents: Meacham Commerce Center CPN-103202 00 73 10- 33 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 33 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 1. within 10 days, City will schedule a Final Inspection with Contractor. 2. City will notify Contractor in writing of all particulars in which this inspection reveals that the Work is incomplete or defective. Contractor shall immediately take such measures as are necessary to complete such Work or remedy such deficiencies. 12.04 Final Acceptance A. Upon completion by Contractor to City’s satisfaction, of any additional Work identified in the Final Inspection, City will issue to Contractor a letter of Final Acceptance upon the satisfaction of the following: 1. All documentation called for in the Contract Documents, including but not limited to the evidence of insurance required by Paragraph 5.03; 2. consent of the surety, if any, to Final Acceptance; 3. a list of all pending or released Damage Claims against City that Contractor believes are unsettled; and 4. affidavits of payments and complete and legally effective releases or waivers (satisfactory to City) of all Lien rights arising out of or Liens filed in connection with the Work. 5. after all Damage Claims have been resolved: a. directly by the Contractor or; b. Contractor provides evidence that the Damage Claim has been reported to Contractor’s insurance provider for resolution. 6. Issuing Final Acceptance by the City shall not relieve the Contractor of any guarantees or other requirements of the Contract Documents which specifically continue thereafter. ARTICLE 13 – SUSPENSION OF WORK 13.01 City May Suspend Work A. At any time and without cause, City may suspend the Work or any portion thereof by written notice to Contractor and which may fix the date on which Work will be resumed. Contractor shall resume the Work on the date so fixed. During temporary suspension of the Work covered by these Contract Documents, for any reason, the City will stop contract time on City participation projects. B. Should the Contractor not be able to complete a portion of the Project due to causes beyond the control of and without the fault or negligence of the Contractor, and should it be determined by mutual consent of the Contractor and City that a solution to allow construction to proceed is not Meacham Commerce Center CPN-103202 00 73 10- 34 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 34 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 available within a reasonable period of time, Contractor may request an extension in Contract Time, directly attributable to any such suspension. C. If it should become necessary to suspend the Work for an indefinite period, the Contractor shall store all materials in such a manner that they will not obstruct or impede the public unnecessarily nor become damaged in any way, and he shall take every precaution to prevent damage or deterioration of the work performed; he shall provide suitable drainage about the work, and erect temporary structures where necessary. ARTICLE 14 – MISCELLANEOUS 14.01 Giving Notice A. Whenever any provision of the Contract Documents requires the giving of written notice, it will be deemed to have been validly given if: 1. delivered in person to the individual or to a member of the firm or to an officer of the corporation for whom it is intended; or 2. delivered at or sent by registered or certified mail, postage prepaid, to the last business address known to the giver of the notice. B. Business address changes must be promptly made in writing to the other party. C. Whenever the Contract Documents specifies giving notice by electronic means such electronic notice shall be deemed sufficient upon confirmation of receipt by the receiving party. 14.02 Computation of Times When any period of time is referred to in the Contract Documents by days, it will be computed to exclude the first and include the last day of such period. If the last day of any such period falls on a Saturday or Sunday or on a day made a legal holiday the next Working Day shall become the last day of the period. 14.03 Cumulative Remedies The duties and obligations imposed by these General Conditions and the rights and remedies available hereunder to the parties hereto are in addition to, and are not to be construed in any way as a limitation of, any rights and remedies available to any or all of them which are otherwise imposed or available by Laws or Regulations, by special warranty or guarantee, or by other provisions of the Contract Documents. The provisions of this Paragraph will be as effective as if repeated specifically in the Contract Documents in connection with each particular duty, obligation, right, and remedy to which they apply. Meacham Commerce Center CPN-103202 00 73 10- 35 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 35 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 14.04 Survival of Obligations All representations, indemnifications, warranties, and guarantees made in, required by, or given in accordance with the Contract Documents, as well as all continuing obligations indicated in the Contract Documents, will survive final payment, completion, and acceptance of the Work or termination or completion of the Contract or termination of the services of Contractor. 14.05 Headings Article and paragraph headings are inserted for convenience only and do not constitute parts of these General Conditions. Meacham Commerce Center CPN-103202 01 11 00 - 1 DAP SUMMARY OF WORK Page 1 of 3 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – Developer Awarded Projects Revised December 20, 2012 Meacham Commerce Center CPN-103202 SECTION 01 11 00 SUMMARY OF WORK PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Summary of Work to be performed in accordance with the Contract Documents B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the Contract 2. Division 1 - General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS A. Work Covered by Contract Documents 1. Work is to include furnishing all labor, materials, and equipment, and performing all Work necessary for this construction project as detailed in the Drawings and Specifications. B. Subsidiary Work 1. Any and all Work specifically governed by documentary requirements for the project, such as conditions imposed by the Drawings or Contract Documents in which no specific item for bid has been provided for in the Proposal and the item is not a typical unit bid item included on the standard bid item list, then the item shall be considered as a subsidiary item of Work, the cost of which shall be included in the price bid in the Proposal for various bid items. C. Use of Premises 1. Coordinate uses of premises under direction of the City. 2. Assume full responsibility for protection and safekeeping of materials and equipment stored on the Site. 3. Use and occupy only portions of the public streets and alleys, or other public places or other rights-of-way as provided for in the ordinances of the City, as shown in the Contract Documents, or as may be specifically authorized in writing by the City. a. A reasonable amount of tools, materials, and equipment for construction purposes may be stored in such space, but no more than is necessary to avoid delay in the construction operations. 01 11 00 - 2 DAP SUMMARY OF WORK Page 2 of 3 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – Developer Awarded Projects Revised December 20, 2012 Meacham Commerce Center CPN-103202 b. Excavated and waste materials shall be stored in such a way as not to interfere with the use of spaces that may be designated to be left free and unobstructed and so as not to inconvenience occupants of adjacent property. c. If the street is occupied by railroad tracks, the Work shall be carried on in such manner as not to interfere with the operation of the railroad. 1) All Work shall be in accordance with railroad requirements set forth in Division 0 as well as the railroad permit. D. Work within Easements 1. Do not enter upon private property for any purpose without having previously obtained permission from the owner of such property. 2. Do not store equipment or material on private property unless and until the specified approval of the property owner has been secured in writing by the Contractor and a copy furnished to the City. 3. Unless specifically provided otherwise, clear all rights-of-way or easements of obstructions which must be removed to make possible proper prosecution of the Work as a part of the project construction operations. 4. Preserve and use every precaution to prevent damage to, all trees, shrubbery, plants, lawns, fences, culverts, curbing, and all other types of structures or improvements, to all water, sewer, and gas lines, to all conduits, overhead pole lines, or appurtenances thereof, including the construction of temporary fences and to all other public or private property adjacent to the Work. 5. Notify the proper representatives of the owners or occupants of the public or private lands of interest in lands which might be affected by the Work. a. Such notice shall be made at least 48 hours in advance of the beginning of the Work. b. Notices shall be applicable to both public and private utility companies and any corporation, company, individual, or other, either as owners or occupants, whose land or interest in land might be affected by the Work. c. Be responsible for all damage or injury to property of any character resulting from any act, omission, neglect, or misconduct in the manner or method or execution of the Work, or at any time due to defective work, material, or equipment. 6. Fence a. Restore all fences encountered and removed during construction of the Project to the original or a better than original condition. b. Erect temporary fencing in place of the fencing removed whenever the Work is not in progress and when the site is vacated overnight, and/or at all times to provide site security. c. The cost for all fence work within easements, including removal, temporary closures and replacement, shall be subsidiary to the various items bid in the project proposal, unless a bid item is specifically provided in the proposal. 01 11 00 - 3 DAP SUMMARY OF WORK Page 3 of 3 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – Developer Awarded Projects Revised December 20, 2012 Meacham Commerce Center CPN-103202 1.5 SUBMITTALS [NOT USED] 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE [NOT USED] 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 01 25 00 - 1 DAP SUBSTITUTION PROCEDURES Page 1 of 4 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised August 30, 2013 Meacham Commerce Center CPN-103202 SECTION 01 25 00 SUBSTITUTION PROCEDURES PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. The procedure for requesting the approval of substitution of a product that is not equivalent to a product which is specified by descriptive or performance criteria or defined by reference to 1 or more of the following: a. Name of manufacturer b. Name of vendor c. Trade name d. Catalog number 2. Substitutions are not "or-equals". B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS A. Request for Substitution - General 1. Within 30 days after award of Contract (unless noted otherwise), the City will consider formal requests from Contractor for substitution of products in place of those specified. 2. Certain types of equipment and kinds of material are described in Specifications by means of references to names of manufacturers and vendors, trade names, or catalog numbers. a. When this method of specifying is used, it is not intended to exclude from consideration other products bearing other manufacturer's or vendor's names, trade names, or catalog numbers, provided said products are "or-equals," as determined by City. 3. Other types of equipment and kinds of material may be acceptable substitutions under the following conditions: a. Or-equals are unavailable due to strike, discontinued production of products meeting specified requirements, or other factors beyond control of Contractor; or, 01 25 00 - 2 DAP SUBSTITUTION PROCEDURES Page 2 of 4 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised August 30, 2013 Meacham Commerce Center CPN-103202 b. Contractor proposes a cost and/or time reduction incentive to the City. 1.5 SUBMITTALS A. See Request for Substitution Form (attached) B. Procedure for Requesting Substitution 1. Substitution shall be considered only: a. After award of Contract b. Under the conditions stated herein 2. Submit 3 copies of each written request for substitution, including: a. Documentation 1) Complete data substantiating compliance of proposed substitution with Contract Documents 2) Data relating to changes in construction schedule, when a reduction is proposed 3) Data relating to changes in cost b. For products 1) Product identification a) Manufacturer's name b) Telephone number and representative contact name c) Specification Section or Drawing reference of originally specified product, including discrete name or tag number assigned to original product in the Contract Documents 2) Manufacturer's literature clearly marked to show compliance of proposed product with Contract Documents 3) Itemized comparison of original and proposed product addressing product characteristics including, but not necessarily limited to: a) Size b) Composition or materials of construction c) Weight d) Electrical or mechanical requirements 4) Product experience a) Location of past projects utilizing product b) Name and telephone number of persons associated with referenced projects knowledgeable concerning proposed product c) Available field data and reports associated with proposed product 5) Samples a) Provide at request of City. b) Samples become the property of the City. c. For construction methods: 1) Detailed description of proposed method 2) Illustration drawings C. Approval or Rejection 1. Written approval or rejection of substitution given by the City 2. City reserves the right to require proposed product to comply with color and pattern of specified product if necessary to secure design intent. 3. In the event the substitution is approved, if a reduction in cost or time results, it will be documented by Change Order. 01 25 00 - 3 DAP SUBSTITUTION PROCEDURES Page 3 of 4 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised August 30, 2013 Meacham Commerce Center CPN-103202 4. Substitution will be rejected if: a. Submittal is not through the Contractor with his stamp of approval b. Request is not made in accordance with this Specification Section c. In the Developer’s opinion, acceptance will require substantial revision of the original design d. In the City’s or Developer’s opinion, substitution will not perform adequately the function consistent with the design intent 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE A. In making request for substitution or in using an approved product, the Contractor represents that the Contractor: 1. Has investigated proposed product, and has determined that it is adequate or superior in all respects to that specified, and that it will perform function for which it is intended 2. Will provide same guarantee for substitute item as for product specified 3. Will coordinate installation of accepted substitution into Work, to include building modifications if necessary, making such changes as may be required for Work to be complete in all respects 4. Waives all claims for additional costs related to substitution which subsequently arise 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 01 25 00 - 4 DAP SUBSTITUTION PROCEDURES Page 4 of 4 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised August 30, 2013 Meacham Commerce Center CPN-103202 EXHIBIT A REQUEST FOR SUBSTITUTION FORM: TO: PROJECT: DATE: We hereby submit for your consideration the following product instead of the specified item for the above project: SECTION PARAGRAPH SPECIFIED ITEM Proposed Substitution: Reason for Substitution: Include complete information on changes to Drawings and/or Specifications which proposed substitution will require for its proper installation. Fill in Blanks Below: A. Will the undersigned contractor pay for changes to the building design, including engineering and detailing costs caused by the requested substitution? B. What effect does substitution have on other trades? C. Differences between proposed substitution and specified item? D. Differences in product cost or product delivery time? E. Manufacturer's guarantees of the proposed and specified items are: Equal Better (explain on attachment) The undersigned states that the function, appearance and quality are equivalent or superior to the specified item. Submitted By: For Use by City Signature Recommended Recommended as noted Firm Not recommended Received late Address By Date Date Remarks Telephone For Use by City: Approved Rejected City Date 01 31 19 - 1 DAP PRECONSTRUCTION MEETING Page 1 of 3 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised August 30, 2013 Meacham Commerce Center CPN-103202 SECTION 01 31 19 PRECONSTRUCTION MEETING PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Provisions for the preconstruction meeting to be held prior to the start of Work to clarify construction contract administration procedures B. Deviations from this City of Fort Worth Standard Specification 1. No construction schedule required unless requested by the City. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS A. Coordination 1. Attend preconstruction meeting. 2. Representatives of Contractor, subcontractors and suppliers attending meetings shall be qualified and authorized to act on behalf of the entity each represents. 3. Meeting administered by City may be tape recorded. a. If recorded, tapes will be used to prepare minutes and retained by City for future reference. B. Preconstruction Meeting 1. A preconstruction meeting will be held within 14 days after the delivery of the distribution package to the City. a. The meeting will be scheduled and administered by the City. 2. The Project Representative will preside at the meeting, prepare the notes of the meeting and distribute copies of same to all participants who so request by fully completing the attendance form to be circulated at the beginning of the meeting. 3. Attendance shall include: a. Developer and Consultant b. Contractor's project manager c. Contractor's superintendent d. Any subcontractor or supplier representatives whom the Contractor may desire to invite or the City may request 01 31 19 - 2 DAP PRECONSTRUCTION MEETING Page 2 of 3 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised August 30, 2013 Meacham Commerce Center CPN-103202 e. Other City representatives f. Others as appropriate 4. Preliminary Agenda may include: a. Introduction of Project Personnel b. General Description of Project c. Status of right-of-way, utility clearances, easements or other pertinent permits d. Contractor’s work plan and schedule e. Contract Time f. Notice to Proceed g. Construction Staking h. Progress Payments i. Extra Work and Change Order Procedures j. Field Orders k. Disposal Site Letter for Waste Material l. Insurance Renewals m. Payroll Certification n. Material Certifications and Quality Control Testing o. Public Safety and Convenience p. Documentation of Pre-Construction Conditions q. Weekend Work Notification r. Legal Holidays s. Trench Safety Plans t. Confined Space Entry Standards u. Coordination with the City’s representative for operations of existing water systems v. Storm Water Pollution Prevention Plan w. Coordination with other Contractors x. Early Warning System y. Contractor Evaluation z. Special Conditions applicable to the project aa. Damages Claims bb. Submittal Procedures cc. Substitution Procedures dd. Correspondence Routing ee. Record Drawings ff. Temporary construction facilities gg. MBE/SBE procedures hh. Final Acceptance ii. Final Payment jj. Questions or Comments 01 31 19 - 3 DAP PRECONSTRUCTION MEETING Page 3 of 3 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised August 30, 2013 Meacham Commerce Center CPN-103202 1.5 SUBMITTALS [NOT USED] 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE [NOT USED] 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 01 31 20 - 1 DAP PROJECT MEETINGS Page 1 of 3 CITY OF FORT WORTH Meacham Commerce Center STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN-103202 Revised July 1, 2011 SECTION 01 31 20 1 PROJECT MEETINGS 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Provisions for project meetings throughout the construction period to enable orderly 6 review of the progress of the Work and to provide for systematic discussion of 7 potential problems 8 B. Deviations this City of Fort Worth Standard Specification 9 1. None. 10 C. Related Specification Sections include, but are not necessarily limited to: 11 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 12 2. Division 1 – General Requirements 13 1.2 PRICE AND PAYMENT PROCEDURES 14 A. Measurement and Payment 15 1. Work associated with this Item is considered subsidiary to the various items bid. 16 No separate payment will be allowed for this Item. 17 1.3 REFERENCES [NOT USED] 18 1.4 ADMINISTRATIVE REQUIREMENTS 19 A. Coordination 20 1. Schedule, attend and administer as specified, periodic progress meetings, and 21 specially called meetings throughout progress of the Work. 22 2. Representatives of Contractor, subcontractors and suppliers attending meetings 23 shall be qualified and authorized to act on behalf of the entity each represents. 24 3. Meetings administered by City may be tape recorded. 25 a. If recorded, tapes will be used to prepare minutes and retained by City for 26 future reference. 27 4. Meetings, in addition to those specified in this Section, may be held when requested 28 by the City, Engineer or Contractor. 29 B. Pre-Construction Neighborhood Meeting 30 1. After the execution of the Agreement, but before construction is allowed to begin, 31 attend 1 Public Meeting with affected residents to: 32 a. Present projected schedule, including construction start date 33 b. Answer any construction related questions 34 2. Meeting Location 35 a. Location of meeting to be determined by the City. 36 3. Attendees 37 a. Contractor 38 01 31 20 - 2 DAP PROJECT MEETINGS Page 2 of 3 CITY OF FORT WORTH Meacham Commerce Center STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN-103202 Revised July 1, 2011 b. Project Representative 1 c. Other City representatives 2 4. Meeting Schedule 3 a. In general, the neighborhood meeting will occur within the 2 weeks following 4 the pre-construction conference. 5 b. In no case will construction be allowed to begin until this meeting is held. 6 C. Progress Meetings 7 1. Formal project coordination meetings will be held periodically. Meetings will be 8 scheduled and administered by Project Representative. 9 2. Additional progress meetings to discuss specific topics will be conducted on an as-10 needed basis. Such additional meetings shall include, but not be limited to: 11 a. Coordinating shutdowns 12 b. Installation of piping and equipment 13 c. Coordination between other construction projects 14 d. Resolution of construction issues 15 e. Equipment approval 16 3. The Project Representative will preside at progress meetings, prepare the notes of 17 the meeting and distribute copies of the same to all participants who so request by 18 fully completing the attendance form to be circulated at the beginning of each 19 meeting. 20 4. Attendance shall include: 21 a. Contractor's project manager 22 b. Contractor's superintendent 23 c. Any subcontractor or supplier representatives whom the Contractor may desire 24 to invite or the City may request 25 d. Engineer's representatives 26 e. City’s representatives 27 f. Others, as requested by the Project Representative 28 5. Preliminary Agenda may include: 29 a. Review of Work progress since previous meeting 30 b. Field observations, problems, conflicts 31 c. Items which impede construction schedule 32 d. Review of off-site fabrication, delivery schedules 33 e. Review of construction interfacing and sequencing requirements with other 34 construction contracts 35 f. Corrective measures and procedures to regain projected schedule 36 g. Revisions to construction schedule 37 h. Progress, schedule, during succeeding Work period 38 i. Coordination of schedules 39 j. Review submittal schedules 40 k. Maintenance of quality standards 41 l. Pending changes and substitutions 42 m. Review proposed changes for: 43 1) Effect on construction schedule and on completion date 44 2) Effect on other contracts of the Project 45 n. Review Record Documents 46 o. Review monthly pay request 47 p. Review status of Requests for Information 48 01 31 20 - 3 DAP PROJECT MEETINGS Page 3 of 3 CITY OF FORT WORTH Meacham Commerce Center STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN-103202 Revised July 1, 2011 6. Meeting Schedule 1 a. Progress meetings will be held periodically as determined by the Project 2 Representative. 3 1) Additional meetings may be held at the request of the: 4 a) City 5 b) Engineer 6 c) Contractor 7 7. Meeting Location 8 a. The City will establish a meeting location. 9 1) To the extent practicable, meetings will be held at the Site. 10 1.5 SUBMITTALS [NOT USED] 11 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 12 1.7 CLOSEOUT SUBMITTALS [NOT USED] 13 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 14 1.9 QUALITY ASSURANCE [NOT USED] 15 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 16 1.11 FIELD [SITE] CONDITIONS [NOT USED] 17 1.12 WARRANTY [NOT USED] 18 PART 2 - PRODUCTS [NOT USED] 19 PART 3 - EXECUTION [NOT USED] 20 END OF SECTION 21 22 Revision Log DATE NAME SUMMARY OF CHANGE 23 01 32 16 - 1 DAP CONSTRUCTION PROGRESS SCHEDULE Page 1 of 5 CITY OF FORT WORTH Meacham Commerce Center STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN-103202 Revised July 1, 2011 SECTION 01 32 16 1 CONSTRUCTION PROGRESS SCHEDULE 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. General requirements for the preparation, submittal, updating, status reporting and 6 management of the Construction Progress Schedule 7 2. Specific requirements are presented in the City of Fort Worth Schedule Guidance 8 Document 9 B. Deviations from this City of Fort Worth Standard Specification 10 1. None. 11 C. Related Specification Sections include, but are not necessarily limited to: 12 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 13 2. Division 1 – General Requirements 14 1.2 PRICE AND PAYMENT PROCEDURES 15 A. Measurement and Payment 16 1. Work associated with this Item is considered subsidiary to the various items bid. 17 No separate payment will be allowed for this Item. 18 1.3 REFERENCES 19 A. Definitions 20 1. Schedule Tiers 21 a. Tier 1 - No schedule submittal required by contract. Small, brief duration 22 projects 23 b. Tier 2 - No schedule submittal required by contract, but will require some 24 milestone dates. Small, brief duration projects 25 c. Tier 3 - Schedule submittal required by contract as described in the 26 Specification and herein. Majority of City projects, including all bond program 27 projects 28 d. Tier 4 - Schedule submittal required by contract as described in the 29 Specification and herein. Large and/or complex projects with long durations 30 1) Examples: large water pump station project and associated pipeline with 31 interconnection to another governmental entity 32 e. Tier 5 - Schedule submittal required by contract as described in the 33 Specification and herein. Large and/or very complex projects with long 34 durations, high public visibility 35 1) Examples might include a water or wastewater treatment plant 36 2. Baseline Schedule - Initial schedule submitted before work begins that will serve 37 as the baseline for measuring progress and departures from the schedule. 38 3. Progress Schedule - Monthly submittal of a progress schedule documenting 39 progress on the project and any changes anticipated. 40 01 32 16 - 2 DAP CONSTRUCTION PROGRESS SCHEDULE Page 2 of 5 CITY OF FORT WORTH Meacham Commerce Center STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN-103202 Revised July 1, 2011 4. Schedule Narrative - Concise narrative of the schedule including schedule 1 changes, expected delays, key schedule issues, critical path items, etc 2 B. Reference Standards 3 1. City of Fort Worth Schedule Guidance Document 4 1.4 ADMINISTRATIVE REQUIREMENTS 5 A. Baseline Schedule 6 1. General 7 a. Prepare a cost-loaded baseline Schedule using approved software and the 8 Critical Path Method (CPM) as required in the City of Fort Worth Schedule 9 Guidance Document. 10 b. Review the draft cost-loaded baseline Schedule with the City to demonstrate 11 understanding of the work to be performed and known issues and constraints 12 related to the schedule. 13 c. Designate an authorized representative (Project Scheduler) responsible for 14 developing and updating the schedule and preparing reports. 15 B. Progress Schedule 16 1. Update the progress Schedule monthly as required in the City of Fort Worth 17 Schedule Guidance Document. 18 2. Prepare the Schedule Narrative to accompany the monthly progress Schedule. 19 3. Change Orders 20 a. Incorporate approved change orders, resulting in a change of contract time, in 21 the baseline Schedule in accordance with City of Fort Worth Schedule 22 Guidance Document. 23 C. Responsibility for Schedule Compliance 24 1. Whenever it becomes apparent from the current progress Schedule and CPM Status 25 Report that delays to the critical path have resulted and the Contract completion 26 date will not be met, or when so directed by the City, make some or all of the 27 following actions at no additional cost to the City 28 a. Submit a Recovery Plan to the City for approval revised baseline Schedule 29 outlining: 30 1) A written statement of the steps intended to take to remove or arrest the 31 delay to the critical path in the approved schedule 32 2) Increase construction manpower in such quantities and crafts as will 33 substantially eliminate the backlog of work and return current Schedule to 34 meet projected baseline completion dates 35 3) Increase the number of working hours per shift, shifts per day, working 36 days per week, the amount of construction equipment, or any combination 37 of the foregoing, sufficiently to substantially eliminate the backlog of work 38 4) Reschedule activities to achieve maximum practical concurrency of 39 accomplishment of activities, and comply with the revised schedule 40 2. If no written statement of the steps intended to take is submitted when so requested 41 by the City, the City may direct the Contractor to increase the level of effort in 42 manpower (trades), equipment and work schedule (overtime, weekend and holiday 43 work, etc.) to be employed by the Contractor in order to remove or arrest the delay 44 to the critical path in the approved schedule. 45 a. No additional cost for such work will be considered. 46 01 32 16 - 3 DAP CONSTRUCTION PROGRESS SCHEDULE Page 3 of 5 CITY OF FORT WORTH Meacham Commerce Center STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN-103202 Revised July 1, 2011 D. The Contract completion time will be adjusted only for causes specified in this 1 Contract. 2 a. Requests for an extension of any Contract completion date must be 3 supplemented with the following: 4 1) Furnish justification and supporting evidence as the City may deem 5 necessary to determine whether the requested extension of time is entitled 6 under the provisions of this Contract. 7 a) The City will, after receipt of such justification and supporting 8 evidence, make findings of fact and will advise the Contractor, in 9 writing thereof. 10 2) If the City finds that the requested extension of time is entitled, the City's 11 determination as to the total number of days allowed for the extensions 12 shall be based upon the approved total baseline schedule and on all data 13 relevant to the extension. 14 a) Such data shall be included in the next updating of the Progress 15 schedule. 16 b) Actual delays in activities which, according to the Baseline schedule, 17 do not affect any Contract completion date shown by the critical path in 18 the network will not be the basis for a change therein. 19 2. Submit each request for change in Contract completion date to the City within 30 20 days after the beginning of the delay for which a time extension is requested but 21 before the date of final payment under this Contract. 22 a. No time extension will be granted for requests which are not submitted within 23 the foregoing time limit. 24 b. From time to time, it may be necessary for the Contract schedule or completion 25 time to be adjusted by the City to reflect the effects of job conditions, weather, 26 technical difficulties, strikes, unavoidable delays on the part of the City or its 27 representatives, and other unforeseeable conditions which may indicate 28 schedule adjustments or completion time extensions. 29 1) Under such conditions, the City will direct the Contractor to reschedule the 30 work or Contract completion time to reflect the changed conditions and the 31 Contractor shall revise his schedule accordingly. 32 a) No additional compensation will be made to the Contractor for such 33 schedule changes except for unavoidable overall contract time 34 extensions beyond the actual completion of unaffected work, in which 35 case the Contractor shall take all possible action to minimize any time 36 extension and any additional cost to the City. 37 b) Available float time in the Baseline schedule may be used by the City 38 as well as by the Contractor. 39 3. Float or slack time is defined as the amount of time between the earliest start date 40 and the latest start date or between the earliest finish date and the latest finish date 41 of a chain of activities on the Baseline Schedule. 42 a. Float or slack time is not for the exclusive use or benefit of either the 43 Contractor or the City. 44 b. Proceed with work according to early start dates, and the City shall have the 45 right to reserve and apportion float time according to the needs of the project. 46 01 32 16 - 4 DAP CONSTRUCTION PROGRESS SCHEDULE Page 4 of 5 CITY OF FORT WORTH Meacham Commerce Center STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN-103202 Revised July 1, 2011 c. Acknowledge and agree that actual delays, affecting paths of activities 1 containing float time, will not have any effect upon contract completion times, 2 providing that the actual delay does not exceed the float time associated with 3 those activities. 4 E. Coordinating Schedule with Other Contract Schedules 5 1. Where work is to be performed under this Contract concurrently with or contingent 6 upon work performed on the same facilities or area under other contracts, the 7 Baseline Schedule shall be coordinated with the schedules of the other contracts. 8 a. Obtain the schedules of the other appropriate contracts from the City for the 9 preparation and updating of Baseline schedule and make the required changes 10 in his schedule when indicated by changes in corresponding schedules. 11 2. In case of interference between the operations of different contractors, the City will 12 determine the work priority of each contractor and the sequence of work necessary 13 to expedite the completion of the entire Project. 14 a. In such cases, the decision of the City shall be accepted as final. 15 b. The temporary delay of any work due to such circumstances shall not be 16 considered as justification for claims for additional compensation. 17 1.5 SUBMITTALS 18 A. Baseline Schedule 19 1. Submit Schedule in native file format and pdf format as required in the City of Fort 20 Worth Schedule Guidance Document. 21 a. Native file format includes: 22 1) Primavera (P6 or Primavera Contractor) 23 2. Submit draft baseline Schedule to City prior to the pre-construction meeting and 24 bring in hard copy to the meeting for review and discussion. 25 B. Progress Schedule 26 1. Submit progress Schedule in native file format and pdf format as required in the 27 City of Fort Worth Schedule Guidance Document. 28 2. Submit progress Schedule monthly no later than the last day of the month. 29 C. Schedule Narrative 30 1. Submit the schedule narrative in pdf format as required in the City of Fort Worth 31 Schedule Guidance Document. 32 2. Submit schedule narrative monthly no later than the last day of the month. 33 D. Submittal Process 34 1. The City administers and manages schedules through Buzzsaw. 35 2. Contractor shall submit documents as required in the City of Fort Worth Schedule 36 Guidance Document. 37 3. Once the project has been completed and Final Acceptance has been issued by the 38 City, no further progress schedules are required. 39 01 32 16 - 5 DAP CONSTRUCTION PROGRESS SCHEDULE Page 5 of 5 CITY OF FORT WORTH Meacham Commerce Center STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN-103202 Revised July 1, 2011 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1 1.7 CLOSEOUT SUBMITTALS [NOT USED] 2 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 3 1.9 QUALITY ASSURANCE 4 A. The person preparing and revising the construction Progress Schedule shall be 5 experienced in the preparation of schedules of similar complexity. 6 B. Schedule and supporting documents addressed in this Specification shall be prepared, 7 updated and revised to accurately reflect the performance of the construction. 8 C. Contractor is responsible for the quality of all submittals in this section meeting the 9 standard of care for the construction industry for similar projects. 10 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 11 1.11 FIELD [SITE] CONDITIONS [NOT USED] 12 1.12 WARRANTY [NOT USED] 13 PART 2 - PRODUCTS [NOT USED] 14 PART 3 - EXECUTION [NOT USED] 15 END OF SECTION 16 17 Revision Log DATE NAME SUMMARY OF CHANGE 18 01 32 33 - 1 DAP PRECONSTRUCTION VIDEO Page 1 of 2 CITY OF FORT WORTH Meacham Commerce Center STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN-103202 Revised August 30, 2013 SECTION 01 32 33 1 PRECONSTRUCTION VIDEO 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Administrative and procedural requirements for: 6 a. Preconstruction Videos 7 B. Deviations from this City of Fort Worth Standard Specification 8 1. Though not mandatory, it is highly recommended on infill developer projects. 9 C. Related Specification Sections include, but are not necessarily limited to: 10 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 11 2. Division 1 – General Requirements 12 1.2 PRICE AND PAYMENT PROCEDURES 13 A. Measurement and Payment 14 1. Work associated with this Item is considered subsidiary to the various items bid. 15 No separate payment will be allowed for this Item. 16 1.3 REFERENCES [NOT USED] 17 1.4 ADMINISTRATIVE REQUIREMENTS 18 A. Preconstruction Video 19 1. Produce a preconstruction video of the site/alignment, including all areas in the 20 vicinity of and to be affected by construction. 21 a. Provide digital copy of video upon request by the City. 22 2. Retain a copy of the preconstruction video until the end of the maintenance surety 23 period. 24 1.5 SUBMITTALS [NOT USED] 25 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 26 1.7 CLOSEOUT SUBMITTALS [NOT USED] 27 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 28 1.9 QUALITY ASSURANCE [NOT USED] 29 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 30 1.11 FIELD [SITE] CONDITIONS [NOT USED] 31 1.12 WARRANTY [NOT USED] 32 PART 2 - PRODUCTS [NOT USED] 33 01 32 33 - 2 DAP PRECONSTRUCTION VIDEO Page 2 of 2 CITY OF FORT WORTH Meacham Commerce Center STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN-103202 Revised August 30, 2013 PART 3 - EXECUTION [NOT USED] 1 END OF SECTION 2 3 Revision Log DATE NAME SUMMARY OF CHANGE 4 01 33 00 - 1 DAP SUBMITTALS Page 1 of 8 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised August 30, 2013 Meacham Commerce Center CPN-103202 SECTION 01 33 00 DAP SUBMITTALS PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. General methods and requirements of submissions applicable to the following Work-related submittals: a. Shop Drawings b. Product Data (including Standard Product List submittals) c. Samples d. Mock Ups B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS A. Coordination 1. Notify the City in writing, at the time of submittal, of any deviations in the submittals from the requirements of the Contract Documents. 2. Coordination of Submittal Times a. Prepare, prioritize and transmit each submittal sufficiently in advance of performing the related Work or other applicable activities, or within the time specified in the individual Work Sections, of the Specifications. b. Contractor is responsible such that the installation will not be delayed by processing times including, but not limited to: a) Disapproval and resubmittal (if required) b) Coordination with other submittals c) Testing d) Purchasing e) Fabrication f) Delivery g) Similar sequenced activities c. No extension of time will be authorized because of the Contractor's failure to transmit submittals sufficiently in advance of the Work. 01 33 00 - 2 DAP SUBMITTALS Page 2 of 8 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised August 30, 2013 Meacham Commerce Center CPN-103202 d. Make submittals promptly in accordance with approved schedule, and in such sequence as to cause no delay in the Work or in the work of any other contractor. B. Submittal Numbering 1. When submitting shop drawings or samples, utilize a 9-character submittal cross- reference identification numbering system in the following manner: a. Use the first 6 digits of the applicable Specification Section Number. b. For the next 2 digits number use numbers 01-99 to sequentially number each initial separate item or drawing submitted under each specific Section number. c. Last use a letter, A-Z, indicating the resubmission of the same drawing (i.e. A=2nd submission, B=3rd submission, C=4th submission, etc.). A typical submittal number would be as follows: 03 30 00-08-B 1) 03 30 00 is the Specification Section for Concrete 2) 08 is the eighth initial submittal under this Specification Section 3) B is the third submission (second resubmission) of that particular shop drawing C. Contractor Certification 1. Review shop drawings, product data and samples, including those by subcontractors, prior to submission to determine and verify the following: a. Field measurements b. Field construction criteria c. Catalog numbers and similar data d. Conformance with the Contract Documents 2. Provide each shop drawing, sample and product data submitted by the Contractor with a Certification Statement affixed including: a. The Contractor's Company name b. Signature of submittal reviewer c. Certification Statement 1) “By this submittal, I hereby represent that I have determined and verified field measurements, field construction criteria, materials, dimensions, catalog numbers and similar data and I have checked and coordinated each item with other applicable approved shop drawings." D. Submittal Format 1. Fold shop drawings larger than 8 ½ inches x 11 inches to 8 ½ inches x 11inches. 2. Bind shop drawings and product data sheets together. 3. Order a. Cover Sheet 1) Description of Packet 2) Contractor Certification b. List of items / Table of Contents c. Product Data /Shop Drawings/Samples /Calculations E. Submittal Content 1. The date of submission and the dates of any previous submissions 01 33 00 - 3 DAP SUBMITTALS Page 3 of 8 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised August 30, 2013 Meacham Commerce Center CPN-103202 2. The Project title and number 3. Contractor identification 4. The names of: a. Contractor b. Supplier c. Manufacturer 5. Identification of the product, with the Specification Section number, page and paragraph(s) 6. Field dimensions, clearly identified as such 7. Relation to adjacent or critical features of the Work or materials 8. Applicable standards, such as ASTM or Federal Specification numbers 9. Identification by highlighting of deviations from Contract Documents 10. Identification by highlighting of revisions on resubmittals 11. An 8-inch x 3-inch blank space for Contractor and City stamps F. Shop Drawings 1. As specified in individual Work Sections includes, but is not necessarily limited to: a. Custom-prepared data such as fabrication and erection/installation (working) drawings b. Scheduled information c. Setting diagrams d. Actual shopwork manufacturing instructions e. Custom templates f. Special wiring diagrams g. Coordination drawings h. Individual system or equipment inspection and test reports including: 1) Performance curves and certifications i. As applicable to the Work 2. Details a. Relation of the various parts to the main members and lines of the structure b. Where correct fabrication of the Work depends upon field measurements 1) Provide such measurements and note on the drawings prior to submitting for approval. G. Product Data 1. For submittals of product data for products included on the City’s Standard Product List, clearly identify each item selected for use on the Project. 2. For submittals of product data for products not included on the City’s Standard Product List, submittal data may include, but is not necessarily limited to: a. Standard prepared data for manufactured products (sometimes referred to as catalog data) 1) Such as the manufacturer's product specification and installation instructions 2) Availability of colors and patterns 3) Manufacturer's printed statements of compliances and applicability 4) Roughing-in diagrams and templates 5) Catalog cuts 6) Product photographs 01 33 00 - 4 DAP SUBMITTALS Page 4 of 8 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised August 30, 2013 Meacham Commerce Center CPN-103202 7) Standard wiring diagrams 8) Printed performance curves and operational-range diagrams 9) Production or quality control inspection and test reports and certifications 10) Mill reports 11) Product operating and maintenance instructions and recommended spare-parts listing and printed product warranties 12) As applicable to the Work H. Samples 1. As specified in individual Sections, include, but are not necessarily limited to: a. Physical examples of the Work such as: 1) Sections of manufactured or fabricated Work 2) Small cuts or containers of materials 3) Complete units of repetitively used products color/texture/pattern swatches and range sets 4) Specimens for coordination of visual effect 5) Graphic symbols and units of Work to be used by the City for independent inspection and testing, as applicable to the Work I. Do not start Work requiring a shop drawing, sample or product data nor any material to be fabricated or installed prior to the approval or qualified approval of such item. 1. Fabrication performed, materials purchased or on-site construction accomplished which does not conform to approved shop drawings and data is at the Contractor's risk. 2. The City will not be liable for any expense or delay due to corrections or remedies required to accomplish conformity. 3. Complete project Work, materials, fabrication, and installations in conformance with approved shop drawings, applicable samples, and product data. J. Submittal Distribution 1. Electronic Distribution a. Confirm development of Project directory for electronic submittals to be uploaded to City’s Buzzsaw site, or another external FTP site approved by the City. b. Shop Drawings 1) Upload submittal to designated project directory and notify appropriate City representatives via email of submittal posting. 2) Hard Copies a) 3 copies for all submittals b) If Contractor requires more than 1 hard copy of Shop Drawings returned, Contractor shall submit more than the number of copies listed above. c. Product Data 1) Upload submittal to designated project directory and notify appropriate City representatives via email of submittal posting. 2) Hard Copies a) 3 copies for all submittals d. Samples 1) Distributed to the Project Representative 2. Hard Copy Distribution (if required in lieu of electronic distribution) 01 33 00 - 5 DAP SUBMITTALS Page 5 of 8 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised August 30, 2013 Meacham Commerce Center CPN-103202 a. Shop Drawings 1) Distributed to the City 2) Copies a) 8 copies for mechanical submittals b) 7 copies for all other submittals c) If Contractor requires more than 3 copies of Shop Drawings returned, Contractor shall submit more than the number of copies listed above. b. Product Data 1) Distributed to the City 2) Copies a) 4 copies c. Samples 1) Distributed to the Project Representative 2) Copies a) Submit the number stated in the respective Specification Sections. 3. Distribute reproductions of approved shop drawings and copies of approved product data and samples, where required, to the job site file and elsewhere as directed by the City. a. Provide number of copies as directed by the City but not exceeding the number previously specified. K. Submittal Review 1. The review of shop drawings, data and samples will be for general conformance with the design concept and Contract Documents. This is not to be construed as: a. Permitting any departure from the Contract requirements b. Relieving the Contractor of responsibility for any errors, including details, dimensions, and materials c. Approving departures from details furnished by the City, except as otherwise provided herein 2. The review and approval of shop drawings, samples or product data by the City does not relieve the Contractor from his/her responsibility with regard to the fulfillment of the terms of the Contract. a. All risks of error and omission are assumed by the Contractor, and the City will have no responsibility therefore. 3. The Contractor remains responsible for details and accuracy, for coordinating the Work with all other associated work and trades, for selecting fabrication processes, for techniques of assembly and for performing Work in a safe manner. 4. If the shop drawings, data or samples as submitted describe variations and show a departure from the Contract requirements which City finds to be in the interest of the City and to be so minor as not to involve a change in Contract Price or time for performance, the City may return the reviewed drawings without noting an exception. 5. Submittals will be returned to the Contractor under 1 of the following codes: a. Code 1 1) "NO EXCEPTIONS TAKEN" is assigned when there are no notations or comments on the submittal. a) When returned under this code the Contractor may release the equipment and/or material for manufacture. b. Code 2 01 33 00 - 6 DAP SUBMITTALS Page 6 of 8 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised August 30, 2013 Meacham Commerce Center CPN-103202 1) "EXCEPTIONS NOTED". This code is assigned when a confirmation of the notations and comments IS NOT required by the Contractor. a) The Contractor may release the equipment or material for manufacture; however, all notations and comments must be incorporated into the final product. c. Code 3 1) "EXCEPTIONS NOTED/RESUBMIT". This combination of codes is assigned when notations and comments are extensive enough to require a resubmittal of the package. a) The Contractor may release the equipment or material for manufacture; however, all notations and comments must be incorporated into the final product. b) This resubmittal is to address all comments, omissions and non-conforming items that were noted. c) Resubmittal is to be received by the City within 15 Calendar Days of the date of the City's transmittal requiring the resubmittal. d. Code 4 1) "NOT APPROVED" is assigned when the submittal does not meet the intent of the Contract Documents. a) The Contractor must resubmit the entire package revised to bring the submittal into conformance. b) It may be necessary to resubmit using a different manufacturer/vendor to meet the Contract Documents. 6. Resubmittals a. Handled in the same manner as first submittals 1) Corrections other than requested by the City 2) Marked with revision triangle or other similar method a) At Contractor’s risk if not marked b. Submittals for each item will be reviewed no more than twice at the City’s expense. 1) All subsequent reviews will be performed at times convenient to the City and at the Contractor's expense, based on the City's or City Representative’s then prevailing rates. 2) Provide Contractor reimbursement to the City within 30 Calendar Days for all such fees invoiced by the City. c. The need for more than 1 resubmission or any other delay in obtaining City's review of submittals, will not entitle the Contractor to an extension of Contract Time. 7. Partial Submittals a. City reserves the right to not review submittals deemed partial, at the City’s discretion. b. Submittals deemed by the City to be not complete will be returned to the Contractor, and will be considered "Not Approved" until resubmitted. c. The City may at its option provide a list or mark the submittal directing the Contractor to the areas that are incomplete. 8. If the Contractor considers any correction indicated on the shop drawings to constitute a change to the Contract Documents, then written notice must be provided thereof to the Developer at least 7 Calendar Days prior to release for manufacture. 01 33 00 - 7 DAP SUBMITTALS Page 7 of 8 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised August 30, 2013 Meacham Commerce Center CPN-103202 9. When the shop drawings have been completed to the satisfaction of the City, the Contractor may carry out the construction in accordance therewith and no further changes therein except upon written instructions from the City. 10. Each submittal, appropriately coded, will be returned within 30 Calendar Days following receipt of submittal by the City. L. Mock ups 1. Mock Up units as specified in individual Sections, include, but are not necessarily limited to, complete units of the standard of acceptance for that type of Work to be used on the Project. Remove at the completion of the Work or when directed. M. Qualifications 1. If specifically required in other Sections of these Specifications, submit a P.E. Certification for each item required. N. Request for Information (RFI) 1. Contractor Request for additional information a. Clarification or interpretation of the contract documents b. When the Contractor believes there is a conflict between Contract Documents c. When the Contractor believes there is a conflict between the Drawings and Specifications 1) Identify the conflict and request clarification 2. Sufficient information shall be attached to permit a written response without further information. 1.5 SUBMITTALS [NOT USED] 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE [NOT USED] 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] 01 33 00 - 8 DAP SUBMITTALS Page 8 of 8 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised August 30, 2013 Meacham Commerce Center CPN-103202 PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 12/20/2012 D. Johnson 1.4.K.8. Working Days modified to Calendar Days 01 35 13 - 1 DAP SPECIAL PROJECT PROCEDURES Page 1 of 7 CITY OF FORT WORTH Meacham Commerce Center STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN-103202 Revised August, 30, 2013 SECTION 01 35 13 1 SPECIAL PROJECT PROCEDURES 2 [Text in Blue is for information or guidance. Remove all blue text in the final project document.] 3 PART 1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. The procedures for special project circumstances that includes, but is not limited to: 7 a. Coordination with the Texas Department of Transportation 8 b. Work near High Voltage Lines 9 c. Confined Space Entry Program 10 d. Air Pollution Watch Days 11 e. Use of Explosives, Drop Weight, Etc. 12 f. Water Department Notification 13 g. Public Notification Prior to Beginning Construction 14 h. Coordination with United States Army Corps of Engineers 15 i. Coordination within Railroad permits areas 16 j. Dust Control 17 k. Employee Parking 18 l. {Coordination with North Central Texas Council of Governments Clean 19 Construction Specification [remove if not required]} 20 B. Deviations from this City of Fort Worth Standard Specification 21 1. None. 22 C. Related Specification Sections include, but are not necessarily limited to: 23 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 24 2. Division 1 – General Requirements 25 3. Section 33 12 25 – Connection to Existing Water Mains 26 27 1.2 REFERENCES 28 A. Reference Standards 29 1. Reference standards cited in this Specification refer to the current reference 30 standard published at the time of the latest revision date logged at the end of this 31 Specification, unless a date is specifically cited. 32 2. Health and Safety Code, Title 9. Safety, Subtitle A. Public Safety, Chapter 752. 33 High Voltage Overhead Lines. 34 3. North Central Texas Council of Governments (NCTCOG) – Clean Construction 35 Specification 36 1.3 ADMINISTRATIVE REQUIREMENTS 37 A. Coordination with the Texas Department of Transportation 38 1. When work in the right-of-way which is under the jurisdiction of the Texas 39 Department of Transportation (TxDOT): 40 01 35 13 - 2 DAP SPECIAL PROJECT PROCEDURES Page 2 of 7 CITY OF FORT WORTH Meacham Commerce Center STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN-103202 Revised August, 30, 2013 a. Notify the Texas Department of Transportation prior to commencing any work 1 therein in accordance with the provisions of the permit 2 b. All work performed in the TxDOT right-of-way shall be performed in 3 compliance with and subject to approval from the Texas Department of 4 Transportation 5 B. Work near High Voltage Lines 6 1. Regulatory Requirements 7 a. All Work near High Voltage Lines (more than 600 volts measured between 8 conductors or between a conductor and the ground) shall be in accordance with 9 Health and Safety Code, Title 9, Subtitle A, Chapter 752. 10 2. Warning sign 11 a. Provide sign of sufficient size meeting all OSHA requirements. 12 3. Equipment operating within 10 feet of high voltage lines will require the following 13 safety features 14 a. Insulating cage-type of guard about the boom or arm 15 b. Insulator links on the lift hook connections for back hoes or dippers 16 c. Equipment must meet the safety requirements as set forth by OSHA and the 17 safety requirements of the owner of the high voltage lines 18 4. Work within 6 feet of high voltage electric lines 19 a. Notification shall be given to: 20 1) The power company (example: ONCOR) 21 a) Maintain an accurate log of all such calls to power company and record 22 action taken in each case. 23 b. Coordination with power company 24 1) After notification coordinate with the power company to: 25 a) Erect temporary mechanical barriers, de-energize the lines, or raise or 26 lower the lines 27 c. No personnel may work within 6 feet of a high voltage line before the above 28 requirements have been met. 29 C. Confined Space Entry Program 30 1. Provide and follow approved Confined Space Entry Program in accordance with 31 OSHA requirements. 32 2. Confined Spaces include: 33 a. Manholes 34 b. All other confined spaces in accordance with OSHA’s Permit Required for 35 Confined Spaces 36 D. Use of Explosives, Drop Weight, Etc. 37 1. When Contract Documents permit on the project the following will apply: 38 a. Public Notification 39 1) Submit notice to City and proof of adequate insurance coverage, 24 hours 40 prior to commencing. 41 2) Minimum 24 hour public notification in accordance with Section 01 31 13 42 E. Water Department Coordination 43 01 35 13 - 3 DAP SPECIAL PROJECT PROCEDURES Page 3 of 7 CITY OF FORT WORTH Meacham Commerce Center STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN-103202 Revised August, 30, 2013 1. During the construction of this project, it will be necessary to deactivate, for a 1 period of time, existing lines. The Contractor shall be required to coordinate with 2 the Water Department to determine the best times for deactivating and activating 3 those lines. 4 2. Coordinate any event that will require connecting to or the operation of an existing 5 City water line system with the City’s representative. 6 a. Coordination shall be in accordance with Section 33 12 25. 7 b. If needed, obtain a hydrant water meter from the Water Department for use 8 during the life of named project. 9 c. In the event that a water valve on an existing live system be turned off and on 10 to accommodate the construction of the project is required, coordinate this 11 activity through the appropriate City representative. 12 1) Do not operate water line valves of existing water system. 13 a) Failure to comply will render the Contractor in violation of Texas Penal 14 Code Title 7, Chapter 28.03 (Criminal Mischief) and the Contractor 15 will be prosecuted to the full extent of the law. 16 b) In addition, the Contractor will assume all liabilities and 17 responsibilities as a result of these actions. 18 F. Public Notification Prior to Beginning Construction 19 1. Prior to beginning construction on any block in the project, on a block by block 20 basis, prepare and deliver a notice or flyer of the pending construction to the front 21 door of each residence or business that will be impacted by construction. The notice 22 shall be prepared as follows: 23 a. Post notice or flyer 7 days prior to beginning any construction activity on each 24 block in the project area. 25 1) Prepare flyer on the Contractor’s letterhead and include the following 26 information: 27 a) Name of Project 28 b) City Project No (CPN) 29 c) Scope of Project (i.e. type of construction activity) 30 d) Actual construction duration within the block 31 e) Name of the contractor’s foreman and phone number 32 f) Name of the City’s inspector and phone number 33 g) City’s after-hours phone number 34 2) A sample of the ‘pre-construction notification’ flyer is attached as Exhibit 35 A. 36 3) Submit schedule showing the construction start and finish time for each 37 block of the project to the inspector. 38 4) Deliver flyer to the City Inspector for review prior to distribution. 39 b. No construction will be allowed to begin on any block until the flyer is 40 delivered to all residents of the block. 41 G. Public Notification of Temporary Water Service Interruption during Construction 42 1. In the event it becomes necessary to temporarily shut down water service to 43 residents or businesses during construction, prepare and deliver a notice or flyer of 44 the pending interruption to the front door of each affected resident. 45 2. Prepared notice as follows: 46 a. The notification or flyer shall be posted 24 hours prior to the temporary 47 interruption. 48 01 35 13 - 4 DAP SPECIAL PROJECT PROCEDURES Page 4 of 7 CITY OF FORT WORTH Meacham Commerce Center STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN-103202 Revised August, 30, 2013 b. Prepare flyer on the contractor’s letterhead and include the following 1 information: 2 1) Name of the project 3 2) City Project Number 4 3) Date of the interruption of service 5 4) Period the interruption will take place 6 5) Name of the contractor’s foreman and phone number 7 6) Name of the City’s inspector and phone number 8 c. A sample of the temporary water service interruption notification is attached as 9 Exhibit B. 10 d. Deliver a copy of the temporary interruption notification to the City inspector 11 for review prior to being distributed. 12 e. No interruption of water service can occur until the flyer has been delivered to 13 all affected residents and businesses. 14 f. Electronic versions of the sample flyers can be obtained from the Project 15 Construction Inspector. 16 H. Coordination with United States Army Corps of Engineers (USACE) 17 1. At locations in the Project where construction activities occur in areas where 18 USACE permits are required, meet all requirements set forth in each designated 19 permit. 20 I. Coordination within Railroad Permit Areas 21 1. At locations in the project where construction activities occur in areas where 22 railroad permits are required, meet all requirements set forth in each designated 23 railroad permit. This includes, but is not limited to, provisions for: 24 a. Flagmen 25 b. Inspectors 26 c. Safety training 27 d. Additional insurance 28 e. Insurance certificates 29 f. Other employees required to protect the right-of-way and property of the 30 Railroad Company from damage arising out of and/or from the construction of 31 the project. Proper utility clearance procedures shall be used in accordance 32 with the permit guidelines. 33 2. Obtain any supplemental information needed to comply with the railroad’s 34 requirements. 35 J. Dust Control 36 1. Use acceptable measures to control dust at the Site. 37 a. If water is used to control dust, capture and properly dispose of waste water. 38 b. If wet saw cutting is performed, capture and properly dispose of slurry. 39 K. Employee Parking 40 1. Provide parking for employees at locations approved by the City. 41 L. {Coordination with North Central Texas Council of Governments (NCTCOG) Clean 42 Construction Specification [if required for the project] 43 1. Comply with equipment, operational, reporting and enforcement requirements set 44 forth in NCTCOG’s Clean Construction Specification.} 45 01 35 13 - 5 DAP SPECIAL PROJECT PROCEDURES Page 5 of 7 CITY OF FORT WORTH Meacham Commerce Center STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN-103202 Revised August, 30, 2013 1.4 SUBMITTALS [NOT USED] 1 1.5 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 2 1.6 CLOSEOUT SUBMITTALS [NOT USED] 3 1.7 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 4 1.8 QUALITY ASSURANCE [NOT USED] 5 1.9 DELIVERY, STORAGE, AND HANDLING [NOT USED] 6 1.10 FIELD [SITE] CONDITIONS [NOT USED] 7 1.11 WARRANTY [NOT USED] 8 PART 2 - PRODUCTS [NOT USED] 9 PART 3 - EXECUTION [NOT USED] 10 END OF SECTION 11 12 Revision Log DATE NAME SUMMARY OF CHANGE 8/31/2012 D. Johnson 1.3.B – Added requirement of compliance with Health and Safety Code, Title 9. Safety, Subtitle A. Public Safety, Chapter 752. High Voltage Overhead Lines. 13 01 35 13 - 6 DAP SPECIAL PROJECT PROCEDURES Page 6 of 7 CITY OF FORT WORTH Meacham Commerce Center STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN-103202 Revised August, 30, 2013 EXHIBIT A 1 (To be printed on Contractor’s Letterhead) 2 3 4 5 Date: 6 7 CPN No.: 8 Project Name: 9 Mapsco Location: 10 Limits of Construction: 11 12 13 14 15 16 THIS IS TO INFORM YOU THAT UNDER A CONTRACT WITH THE CITY OF FORT 17 WORTH, OUR COMPANY WILL WORK ON UTILITY LINES ON OR AROUND YOUR 18 PROPERTY. 19 20 CONSTRUCTION WILL BEGIN APPROXIMATELY SEVEN DAYS FROM THE DATE 21 OF THIS NOTICE. 22 23 IF YOU HAVE QUESTIONS ABOUT ACCESS, SECURITY, SAFETY OR ANY OTHER 24 ISSUE, PLEASE CALL: 25 26 27 Mr. <CONTRACTOR’S SUPERINTENDENT> AT <TELEPHONE NO.> 28 29 OR 30 31 Mr. <CITY INSPECTOR> AT < TELEPHONE NO.> 32 33 AFTER 4:30 PM OR ON WEEKENDS, PLEASE CALL (817) 392 8306 34 35 PLEASE KEEP THIS FLYER HANDY WHEN YOU CALL 36 37 01 35 13 - 7 DAP SPECIAL PROJECT PROCEDURES Page 7 of 7 CITY OF FORT WORTH Meacham Commerce Center STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN-103202 Revised August, 30, 2013 EXHIBIT B 1 2 3 4 01 35 13 - 1 DAP SPECIAL PROJECT PROCEDURES Page 1 of 7 CITY OF FORT WORTH Meacham Commerce Center STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN-103202 Revised August, 30, 2013 SECTION 01 35 13 1 SPECIAL PROJECT PROCEDURES 2 [Text in Blue is for information or guidance. Remove all blue text in the final project document.] 3 PART 1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. The procedures for special project circumstances that includes, but is not limited to: 7 a. Coordination with the Texas Department of Transportation 8 b. Work near High Voltage Lines 9 c. Confined Space Entry Program 10 d. Air Pollution Watch Days 11 e. Use of Explosives, Drop Weight, Etc. 12 f. Water Department Notification 13 g. Public Notification Prior to Beginning Construction 14 h. Coordination with United States Army Corps of Engineers 15 i. Coordination within Railroad permits areas 16 j. Dust Control 17 k. Employee Parking 18 l. {Coordination with North Central Texas Council of Governments Clean 19 Construction Specification [remove if not required]} 20 B. Deviations from this City of Fort Worth Standard Specification 21 1. None. 22 C. Related Specification Sections include, but are not necessarily limited to: 23 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 24 2. Division 1 – General Requirements 25 3. Section 33 12 25 – Connection to Existing Water Mains 26 27 1.2 REFERENCES 28 A. Reference Standards 29 1. Reference standards cited in this Specification refer to the current reference 30 standard published at the time of the latest revision date logged at the end of this 31 Specification, unless a date is specifically cited. 32 2. Health and Safety Code, Title 9. Safety, Subtitle A. Public Safety, Chapter 752. 33 High Voltage Overhead Lines. 34 3. North Central Texas Council of Governments (NCTCOG) – Clean Construction 35 Specification 36 1.3 ADMINISTRATIVE REQUIREMENTS 37 A. Coordination with the Texas Department of Transportation 38 1. When work in the right-of-way which is under the jurisdiction of the Texas 39 Department of Transportation (TxDOT): 40 01 35 13 - 2 DAP SPECIAL PROJECT PROCEDURES Page 2 of 7 CITY OF FORT WORTH Meacham Commerce Center STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN-103202 Revised August, 30, 2013 a. Notify the Texas Department of Transportation prior to commencing any work 1 therein in accordance with the provisions of the permit 2 b. All work performed in the TxDOT right-of-way shall be performed in 3 compliance with and subject to approval from the Texas Department of 4 Transportation 5 B. Work near High Voltage Lines 6 1. Regulatory Requirements 7 a. All Work near High Voltage Lines (more than 600 volts measured between 8 conductors or between a conductor and the ground) shall be in accordance with 9 Health and Safety Code, Title 9, Subtitle A, Chapter 752. 10 2. Warning sign 11 a. Provide sign of sufficient size meeting all OSHA requirements. 12 3. Equipment operating within 10 feet of high voltage lines will require the following 13 safety features 14 a. Insulating cage-type of guard about the boom or arm 15 b. Insulator links on the lift hook connections for back hoes or dippers 16 c. Equipment must meet the safety requirements as set forth by OSHA and the 17 safety requirements of the owner of the high voltage lines 18 4. Work within 6 feet of high voltage electric lines 19 a. Notification shall be given to: 20 1) The power company (example: ONCOR) 21 a) Maintain an accurate log of all such calls to power company and record 22 action taken in each case. 23 b. Coordination with power company 24 1) After notification coordinate with the power company to: 25 a) Erect temporary mechanical barriers, de-energize the lines, or raise or 26 lower the lines 27 c. No personnel may work within 6 feet of a high voltage line before the above 28 requirements have been met. 29 C. Confined Space Entry Program 30 1. Provide and follow approved Confined Space Entry Program in accordance with 31 OSHA requirements. 32 2. Confined Spaces include: 33 a. Manholes 34 b. All other confined spaces in accordance with OSHA’s Permit Required for 35 Confined Spaces 36 D. Use of Explosives, Drop Weight, Etc. 37 1. When Contract Documents permit on the project the following will apply: 38 a. Public Notification 39 1) Submit notice to City and proof of adequate insurance coverage, 24 hours 40 prior to commencing. 41 2) Minimum 24 hour public notification in accordance with Section 01 31 13 42 E. Water Department Coordination 43 01 35 13 - 3 DAP SPECIAL PROJECT PROCEDURES Page 3 of 7 CITY OF FORT WORTH Meacham Commerce Center STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN-103202 Revised August, 30, 2013 1. During the construction of this project, it will be necessary to deactivate, for a 1 period of time, existing lines. The Contractor shall be required to coordinate with 2 the Water Department to determine the best times for deactivating and activating 3 those lines. 4 2. Coordinate any event that will require connecting to or the operation of an existing 5 City water line system with the City’s representative. 6 a. Coordination shall be in accordance with Section 33 12 25. 7 b. If needed, obtain a hydrant water meter from the Water Department for use 8 during the life of named project. 9 c. In the event that a water valve on an existing live system be turned off and on 10 to accommodate the construction of the project is required, coordinate this 11 activity through the appropriate City representative. 12 1) Do not operate water line valves of existing water system. 13 a) Failure to comply will render the Contractor in violation of Texas Penal 14 Code Title 7, Chapter 28.03 (Criminal Mischief) and the Contractor 15 will be prosecuted to the full extent of the law. 16 b) In addition, the Contractor will assume all liabilities and 17 responsibilities as a result of these actions. 18 F. Public Notification Prior to Beginning Construction 19 1. Prior to beginning construction on any block in the project, on a block by block 20 basis, prepare and deliver a notice or flyer of the pending construction to the front 21 door of each residence or business that will be impacted by construction. The notice 22 shall be prepared as follows: 23 a. Post notice or flyer 7 days prior to beginning any construction activity on each 24 block in the project area. 25 1) Prepare flyer on the Contractor’s letterhead and include the following 26 information: 27 a) Name of Project 28 b) City Project No (CPN) 29 c) Scope of Project (i.e. type of construction activity) 30 d) Actual construction duration within the block 31 e) Name of the contractor’s foreman and phone number 32 f) Name of the City’s inspector and phone number 33 g) City’s after-hours phone number 34 2) A sample of the ‘pre-construction notification’ flyer is attached as Exhibit 35 A. 36 3) Submit schedule showing the construction start and finish time for each 37 block of the project to the inspector. 38 4) Deliver flyer to the City Inspector for review prior to distribution. 39 b. No construction will be allowed to begin on any block until the flyer is 40 delivered to all residents of the block. 41 G. Public Notification of Temporary Water Service Interruption during Construction 42 1. In the event it becomes necessary to temporarily shut down water service to 43 residents or businesses during construction, prepare and deliver a notice or flyer of 44 the pending interruption to the front door of each affected resident. 45 2. Prepared notice as follows: 46 a. The notification or flyer shall be posted 24 hours prior to the temporary 47 interruption. 48 01 35 13 - 4 DAP SPECIAL PROJECT PROCEDURES Page 4 of 7 CITY OF FORT WORTH Meacham Commerce Center STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN-103202 Revised August, 30, 2013 b. Prepare flyer on the contractor’s letterhead and include the following 1 information: 2 1) Name of the project 3 2) City Project Number 4 3) Date of the interruption of service 5 4) Period the interruption will take place 6 5) Name of the contractor’s foreman and phone number 7 6) Name of the City’s inspector and phone number 8 c. A sample of the temporary water service interruption notification is attached as 9 Exhibit B. 10 d. Deliver a copy of the temporary interruption notification to the City inspector 11 for review prior to being distributed. 12 e. No interruption of water service can occur until the flyer has been delivered to 13 all affected residents and businesses. 14 f. Electronic versions of the sample flyers can be obtained from the Project 15 Construction Inspector. 16 H. Coordination with United States Army Corps of Engineers (USACE) 17 1. At locations in the Project where construction activities occur in areas where 18 USACE permits are required, meet all requirements set forth in each designated 19 permit. 20 I. Coordination within Railroad Permit Areas 21 1. At locations in the project where construction activities occur in areas where 22 railroad permits are required, meet all requirements set forth in each designated 23 railroad permit. This includes, but is not limited to, provisions for: 24 a. Flagmen 25 b. Inspectors 26 c. Safety training 27 d. Additional insurance 28 e. Insurance certificates 29 f. Other employees required to protect the right-of-way and property of the 30 Railroad Company from damage arising out of and/or from the construction of 31 the project. Proper utility clearance procedures shall be used in accordance 32 with the permit guidelines. 33 2. Obtain any supplemental information needed to comply with the railroad’s 34 requirements. 35 J. Dust Control 36 1. Use acceptable measures to control dust at the Site. 37 a. If water is used to control dust, capture and properly dispose of waste water. 38 b. If wet saw cutting is performed, capture and properly dispose of slurry. 39 K. Employee Parking 40 1. Provide parking for employees at locations approved by the City. 41 L. {Coordination with North Central Texas Council of Governments (NCTCOG) Clean 42 Construction Specification [if required for the project] 43 1. Comply with equipment, operational, reporting and enforcement requirements set 44 forth in NCTCOG’s Clean Construction Specification.} 45 01 35 13 - 5 DAP SPECIAL PROJECT PROCEDURES Page 5 of 7 CITY OF FORT WORTH Meacham Commerce Center STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN-103202 Revised August, 30, 2013 1.4 SUBMITTALS [NOT USED] 1 1.5 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 2 1.6 CLOSEOUT SUBMITTALS [NOT USED] 3 1.7 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 4 1.8 QUALITY ASSURANCE [NOT USED] 5 1.9 DELIVERY, STORAGE, AND HANDLING [NOT USED] 6 1.10 FIELD [SITE] CONDITIONS [NOT USED] 7 1.11 WARRANTY [NOT USED] 8 PART 2 - PRODUCTS [NOT USED] 9 PART 3 - EXECUTION [NOT USED] 10 END OF SECTION 11 12 Revision Log DATE NAME SUMMARY OF CHANGE 8/31/2012 D. Johnson 1.3.B – Added requirement of compliance with Health and Safety Code, Title 9. Safety, Subtitle A. Public Safety, Chapter 752. High Voltage Overhead Lines. 13 01 35 13 - 6 DAP SPECIAL PROJECT PROCEDURES Page 6 of 7 CITY OF FORT WORTH Meacham Commerce Center STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN-103202 Revised August, 30, 2013 EXHIBIT A 1 (To be printed on Contractor’s Letterhead) 2 3 4 5 Date: 6 7 CPN No.: 8 Project Name: 9 Mapsco Location: 10 Limits of Construction: 11 12 13 14 15 16 THIS IS TO INFORM YOU THAT UNDER A CONTRACT WITH THE CITY OF FORT 17 WORTH, OUR COMPANY WILL WORK ON UTILITY LINES ON OR AROUND YOUR 18 PROPERTY. 19 20 CONSTRUCTION WILL BEGIN APPROXIMATELY SEVEN DAYS FROM THE DATE 21 OF THIS NOTICE. 22 23 IF YOU HAVE QUESTIONS ABOUT ACCESS, SECURITY, SAFETY OR ANY OTHER 24 ISSUE, PLEASE CALL: 25 26 27 Mr. <CONTRACTOR’S SUPERINTENDENT> AT <TELEPHONE NO.> 28 29 OR 30 31 Mr. <CITY INSPECTOR> AT < TELEPHONE NO.> 32 33 AFTER 4:30 PM OR ON WEEKENDS, PLEASE CALL (817) 392 8306 34 35 PLEASE KEEP THIS FLYER HANDY WHEN YOU CALL 36 37 01 35 13 - 7 DAP SPECIAL PROJECT PROCEDURES Page 7 of 7 CITY OF FORT WORTH Meacham Commerce Center STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN-103202 Revised August, 30, 2013 EXHIBIT B 1 2 3 4 01 45 23 DAP TESTING AND INSPECTION SERVICES Page 1 of 2 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised March 20, 2020 Meacham Commerce Center CPN-103202 SECTION 01 45 23 TESTING AND INSPECTION SERVICES PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Testing and inspection services procedures and coordination B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various Items bid. No separate payment will be allowed for this Item. a. Contractor is responsible for performing, coordinating, and payment of all Quality Control testing. b. City is responsible for performing and payment for first set of Quality Assurance testing. 1) If the first Quality Assurance test performed by the City fails, the Contractor is responsible for payment of subsequent Quality Assurance testing until a passing test occurs. a) Final acceptance will not be issued by City until all required payments for testing by Contractor have been paid in full. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS A. Testing 1. Complete testing in accordance with the Contract Documents. 2. Coordination a. When testing is required to be performed by the City, notify City, sufficiently in advance, when testing is needed. b. When testing is required to be completed by the Contractor, notify City, sufficiently in advance, that testing will be performed. 3. Distribution of Testing Reports a. Electronic Distribution 1) Confirm development of Project directory for electronic submittals to be uploaded to the City’s document management system, or another form of distribution approved by the City. 01 45 23 DAP TESTING AND INSPECTION SERVICES Page 2 of 2 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised March 20, 2020 Meacham Commerce Center CPN-103202 2) Upload test reports to designated project directory and notify appropriate City representatives via email of submittal posting. 3) Hard Copies a) 1 copy for all submittals submitted to the Project Representative b. Hard Copy Distribution (if required in lieu of electronic distribution) 1) Tests performed by City a) Distribute 1 hard copy to the Contractor 2) Tests performed by the Contractor a) Distribute 3 hard copies to City’s Project Representative 4. Provide City’s Project Representative with trip tickets for each delivered load of Concrete or Lime material including the following information: a. Name of pit b. Date of delivery c. Material delivered B. Inspection 1. Inspection or lack of inspection does not relieve the Contractor from obligation to perform work in accordance with the Contract Documents. 1.5 SUBMITTALS [NOT USED] 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE [NOT USED] 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 03/20/2020 D.V. Magaña Removed reference to Buzzsaw and noted that electronic submittals be uploaded through the City’s document management system. 01 50 00 - 1 DAP TEMPORARY FACILITIES AND CONTROLS Page 1 of 4 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised JULY 1, 2011 Meacham Commerce Center CPN-103202 SECTION 01 50 00 TEMPORARY FACILITIES AND CONTROLS PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Provide temporary facilities and controls needed for the Work including, but not necessarily limited to: a. Temporary utilities b. Sanitary facilities c. Storage Sheds and Buildings d. Dust control e. Temporary fencing of the construction site B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various Items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS A. Temporary Utilities 1. Obtaining Temporary Service a. Make arrangements with utility service companies for temporary services. b. Abide by rules and regulations of utility service companies or authorities having jurisdiction. c. Be responsible for utility service costs until Work is approved for Final Acceptance. 1) Included are fuel, power, light, heat and other utility services necessary for execution, completion, testing and initial operation of Work. 2. Water a. Contractor to provide water required for and in connection with Work to be performed and for specified tests of piping, equipment, devices or other use as required for the completion of the Work. b. Provide and maintain adequate supply of potable water for domestic consumption by Contractor personnel and City’s Project Representatives. c. Coordination 1) Contact City 1 week before water for construction is desired 01 50 00 - 2 DAP TEMPORARY FACILITIES AND CONTROLS Page 2 of 4 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised JULY 1, 2011 Meacham Commerce Center CPN-103202 d. Contractor Payment for Construction Water 1) Obtain construction water meter from City for payment as billed by City’s established rates. 3. Electricity and Lighting a. Provide and pay for electric powered service as required for Work, including testing of Work. 1) Provide power for lighting, operation of equipment, or other use. b. Electric power service includes temporary power service or generator to maintain operations during scheduled shutdown. 4. Telephone a. Provide emergency telephone service at Site for use by Contractor personnel and others performing work or furnishing services at Site. 5. Temporary Heat and Ventilation a. Provide temporary heat as necessary for protection or completion of Work. b. Provide temporary heat and ventilation to assure safe working conditions. B. Sanitary Facilities 1. Provide and maintain sanitary facilities for persons on Site. a. Comply with regulations of State and local departments of health. 2. Enforce use of sanitary facilities by construction personnel at job site. a. Enclose and anchor sanitary facilities. b. No discharge will be allowed from these facilities. c. Collect and store sewage and waste so as not to cause nuisance or health problem. d. Haul sewage and waste off-site at no less than weekly intervals and properly dispose in accordance with applicable regulation. 3. Locate facilities near Work Site and keep clean and maintained throughout Project. 4. Remove facilities at completion of Project C. Storage Sheds and Buildings 1. Provide adequately ventilated, watertight, weatherproof storage facilities with floor above ground level for materials and equipment susceptible to weather damage. 2. Storage of materials not susceptible to weather damage may be on blocks off ground. 3. Store materials in a neat and orderly manner. a. Place materials and equipment to permit easy access for identification, inspection and inventory. 4. Equip building with lockable doors and lighting, and provide electrical service for equipment space heaters and heating or ventilation as necessary to provide storage environments acceptable to specified manufacturers. 5. Fill and grade site for temporary structures to provide drainage away from temporary and existing buildings. 6. Remove building from site prior to Final Acceptance. D. Temporary Fencing 1. Provide and maintain for the duration or construction when required in contract documents E. Dust Control 01 50 00 - 3 DAP TEMPORARY FACILITIES AND CONTROLS Page 3 of 4 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised JULY 1, 2011 Meacham Commerce Center CPN-103202 1. Contractor is responsible for maintaining dust control through the duration of the project. a. Contractor remains on-call at all times b. Must respond in a timely manner F. Temporary Protection of Construction 1. Contractor or subcontractors are responsible for protecting Work from damage due to weather. 1.5 SUBMITTALS [NOT USED] 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE [NOT USED] 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION [NOT USED] 3.1 INSTALLERS [NOT USED] 3.2 EXAMINATION [NOT USED] 3.3 PREPARATION [NOT USED] 3.4 INSTALLATION A. Temporary Facilities 1. Maintain all temporary facilities for duration of construction activities as needed. 3.5 [REPAIR] / [RESTORATION] 3.6 RE-INSTALLATION 3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED] 3.8 SYSTEM STARTUP [NOT USED] 3.9 ADJUSTING [NOT USED] 3.10 CLEANING [NOT USED] 3.11 CLOSEOUT ACTIVITIES A. Temporary Facilities 01 50 00 - 4 DAP TEMPORARY FACILITIES AND CONTROLS Page 4 of 4 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised JULY 1, 2011 Meacham Commerce Center CPN-103202 1. Remove all temporary facilities and restore area after completion of the Work, to a condition equal to or better than prior to start of Work. 3.12 PROTECTION [NOT USED] 3.13 MAINTENANCE [NOT USED] 3.14 ATTACHMENTS [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 01 55 26 - 1 DAP STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL Page 1 of 3 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised July 1, 2011 Meacham Commerce Center CPN-103202 SECTION 01 55 26 STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Administrative procedures for: a. Street Use Permit b. Modification of approved traffic control c. Removal of Street Signs B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 3. Section 34 71 13 – Traffic Control 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various Items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES A. Reference Standards 1. Reference standards cited in this specification refer to the current reference standard published at the time of the latest revision date logged at the end of this specification, unless a date is specifically cited. 2. Texas Manual on Uniform Traffic Control Devices (TMUTCD). 1.4 ADMINISTRATIVE REQUIREMENTS A. Traffic Control 1. General a. When traffic control plans are included in the Drawings, provide Traffic Control in accordance with Drawings and Section 34 71 13. b. When traffic control plans are not included in the Drawings, prepare traffic control plans in accordance with Section 34 71 13 and submit to City for review. 1) Allow minimum 10 working days for review of proposed Traffic Control. B. Street Use Permit 1. Prior to installation of Traffic Control, a City Street Use Permit is required. a. To obtain Street Use Permit, submit Traffic Control Plans to City Transportation and Public Works Department. 01 55 26 - 2 DAP STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL Page 2 of 3 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised July 1, 2011 Meacham Commerce Center CPN-103202 1) Allow a minimum of 5 working days for permit review. 2) Contractor’s responsibility to coordinate review of Traffic Control plans for Street Use Permit, such that construction is not delayed. C. Modification to Approved Traffic Control 1. Prior to installation traffic control: a. Submit revised traffic control plans to City Department Transportation and Public Works Department. 1) Revise Traffic Control plans in accordance with Section 34 71 13. 2) Allow minimum 5 working days for review of revised Traffic Control. 3) It is the Contractor’s responsibility to coordinate review of Traffic Control plans for Street Use Permit, such that construction is not delayed. D. Removal of Street Sign 1. If it is determined that a street sign must be removed for construction, then contact City Transportation and Public Works Department, Signs and Markings Division to remove the sign. E. Temporary Signage 1. In the case of regulatory signs, replace permanent sign with temporary sign meeting requirements of the latest edition of the Texas Manual on Uniform Traffic Control Devices (MUTCD). 2. Install temporary sign before the removal of permanent sign. 3. When construction is complete, to the extent that the permanent sign can be reinstalled, contact the City Transportation and Public Works Department, Signs and Markings Division, to reinstall the permanent sign. F. Traffic Control Standards 1. Traffic Control Standards can be found on the City’s Buzzsaw website. 1.5 SUBMITTALS [NOT USED] 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE [NOT USED] 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION [NOT USED] END OF SECTION 01 55 26 - 3 DAP STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL Page 3 of 3 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised July 1, 2011 Meacham Commerce Center CPN-103202 Revision Log DATE NAME SUMMARY OF CHANGE 01 57 13 - 1 DAP STORM WATER POLLUTION PREVENTION Page 1 of 3 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised July 1, 2011 Meacham Commerce Center CPN-103202 SECTION 01 57 13 STORM WATER POLLUTION PREVENTION PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Procedures for Storm Water Pollution Prevention Plans B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 3. Section 31 25 00 – Erosion and Sediment Control 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Construction Activities resulting in less than 1 acre of disturbance a. Work associated with this Item is considered subsidiary to the various Items bid. No separate payment will be allowed for this Item. 2. Construction Activities resulting in greater than 1 acre of disturbance a. Measurement and Payment shall be in accordance with Section 31 25 00. 1.3 REFERENCES A. Abbreviations and Acronyms 1. Notice of Intent: NOI 2. Notice of Termination: NOT 3. Storm Water Pollution Prevention Plan: SWPPP 4. Texas Commission on Environmental Quality: TCEQ 5. Notice of Change: NOC A. Reference Standards 1. Reference standards cited in this Specification refer to the current reference standard published at the time of the latest revision date logged at the end of this Specification, unless a date is specifically cited. 2. Integrated Storm Management (iSWM) Technical Manual for Construction Controls 1.4 ADMINISTRATIVE REQUIREMENTS A. General 1. Contractor is responsible for resolution and payment of any fines issued associated with compliance to Stormwater Pollution Prevention Plan. 01 57 13 - 2 DAP STORM WATER POLLUTION PREVENTION Page 2 of 3 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised July 1, 2011 Meacham Commerce Center CPN-103202 B. Construction Activities resulting in: 1. Less than 1 acre of disturbance a. Provide erosion and sediment control in accordance with Section 31 25 00 and Drawings. 2. 1 to less than 5 acres of disturbance a. Texas Pollutant Discharge Elimination System (TPDES) General Construction Permit is required b. Complete SWPPP in accordance with TCEQ requirements 1) TCEQ Small Construction Site Notice Required under general permit TXR150000 a) Sign and post at job site b) Prior to Preconstruction Meeting, send 1 copy to City Department of Transportation and Public Works, Environmental Division, (817) 392- 6088. 2) Provide erosion and sediment control in accordance with: a) Section 31 25 00 b) The Drawings c) TXR150000 General Permit d) SWPPP e) TCEQ requirements 3. 5 acres or more of Disturbance a. Texas Pollutant Discharge Elimination System (TPDES) General Construction Permit is required b. Complete SWPPP in accordance with TCEQ requirements 1) Prepare a TCEQ NOI form and submit to TCEQ along with required fee a) Sign and post at job site b) Send copy to City Department of Transportation and Public Works, Environmental Division, (817) 392-6088. 2) TCEQ Notice of Change required if making changes or updates to NOI 3) Provide erosion and sediment control in accordance with: a) Section 31 25 00 b) The Drawings c) TXR150000 General Permit d) SWPPP e) TCEQ requirements 4) Once the project has been completed and all the closeout requirements of TCEQ have been met a TCEQ Notice of Termination can be submitted. a) Send copy to City Department of Transportation and Public Works, Environmental Division, (817) 392-6088. 1.5 SUBMITTALS A. SWPPP 1. Submit in accordance with Section 01 33 00, except as stated herein. a. Prior to the Preconstruction Meeting, submit a draft copy of SWPPP to the City as follows: 1) 1 copy to the City Project Manager a) City Project Manager will forward to the City Department of Transportation and Public Works, Environmental Division for review 01 57 13 - 3 DAP STORM WATER POLLUTION PREVENTION Page 3 of 3 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised July 1, 2011 Meacham Commerce Center CPN-103202 B. Modified SWPPP 1. If the SWPPP is revised during construction, resubmit modified SWPPP to the City in accordance with Section 01 33 00. 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE [NOT USED] 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 01 58 13 - 1 DAP TEMPORARY PROJECT SIGNAGE Page 1 of 3 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised April 7, 2014 Meacham Commerce Center CPN-103202 SECTION 01 58 13 TEMPORARY PROJECT SIGNAGE PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Temporary Project Signage Requirements B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various Items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 1.5 SUBMITTALS [NOT USED] 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE [NOT USED] 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS 2.1 OWNER-FURNISHED [OR] OWNER-SUPPLIEDPRODUCTS [NOT USED] 2.2 EQUIPMENT, PRODUCT TYPES, AND MATERIALS A. Design Criteria 1. Provide free standing Project Designation Sign in accordance with City’s Standard Details for project signs. 01 58 13 - 2 DAP TEMPORARY PROJECT SIGNAGE Page 2 of 3 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised April 7, 2014 Meacham Commerce Center CPN-103202 B. Materials 1. Sign a. Constructed of ¾-inch fir plywood, grade A-C (exterior) or better 2.3 ACCESSORIES [NOT USED] 2.4 SOURCE QUALITY CONTROL [NOT USED] PART 3 - EXECUTION 3.1 INSTALLERS [NOT USED] 3.2 EXAMINATION [NOT USED] 3.3 PREPARATION [NOT USED] 3.4 INSTALLATION A. General 1. Provide vertical installation at extents of project. 2. Relocate sign as needed, upon request of the City. B. Mounting options a. Skids b. Posts c. Barricade 3.5 REPAIR / RESTORATION [NOT USED] 3.6 RE-INSTALLATION [NOT USED] 3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED] 3.8 SYSTEM STARTUP [NOT USED] 3.9 ADJUSTING [NOT USED] 3.10 CLEANING [NOT USED] 3.11 CLOSEOUT ACTIVITIES [NOT USED] 3.12 PROTECTION [NOT USED] 3.13 MAINTENANCE A. General 1. Maintenance will include painting and repairs as needed or directed by the City. 3.14 ATTACHMENTS [NOT USED] END OF SECTION 01 58 13 - 3 DAP TEMPORARY PROJECT SIGNAGE Page 3 of 3 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised April 7, 2014 Meacham Commerce Center CPN-103202 Revision Log DATE NAME SUMMARY OF CHANGE 4/7/2014 M. Domenech Revised for DAP application 01 60 00 DAP PRODUCT REQUIREMENTS Page 1 of 2 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised March 20, 2020 Meacham Commerce Center CPN-103202 SECTION 01 60 00 PRODUCT REQUIREMENTS PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. References for Product Requirements and City Standard Products List B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 1.2 PRICE AND PAYMENT PROCEDURES [NOT USED] 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS A list of City approved products for use is available through the City’s website at: https://apps.fortworthtexas.gov/ProjectResources/ and following the directory path: 02 - Construction Documents\Standard Products List A. Only products specifically included on City’s Standard Product List in these Contract Documents shall be allowed for use on the Project. 1. Any subsequently approved products will only be allowed for use upon specific approval by the City. B. Any specific product requirements in the Contract Documents supersede similar products included on the City’s Standard Product List. 1. The City reserves the right to not allow products to be used for certain projects even though the product is listed on the City’s Standard Product List. C. Although a specific product is included on City’s Standard Product List, not all products from that manufacturer are approved for use, including but not limited to, that manufacturer’s standard product. D. See Section 01 33 00 for submittal requirements of Product Data included on City’s Standard Product List. 1.5 SUBMITTALS [NOT USED] 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE [NOT USED] 01 60 00 DAP PRODUCT REQUIREMENTS Page 2 of 2 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised March 20, 2020 Meacham Commerce Center CPN-103202 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 10/12/12 D. Johnson Modified Location of City’s Standard Product List 4/7/2014 M.Domenech Revised for DAP application 03/20/2020 D.V. Magaña Removed reference to Buzzsaw and noted that the City approved products list is accessible through the City’s website. 01 66 00 - 1 DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS Page 1 of 4 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised April 7, 2014 Meacham Commerce Center CPN-103202 SECTION 01 66 00 PRODUCT STORAGE AND HANDLING REQUIREMENTS PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Scheduling of product delivery 2. Packaging of products for delivery 3. Protection of products against damage from: a. Handling b. Exposure to elements or harsh environments B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various Items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 1.5 SUBMITTALS [NOT USED] 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE [NOT USED] 1.10 DELIVERY AND HANDLING A. Delivery Requirements 1. Schedule delivery of products or equipment as required to allow timely installation and to avoid prolonged storage. 2. Provide appropriate personnel and equipment to receive deliveries. 3. Delivery trucks will not be permitted to wait extended periods of time on the Site for personnel or equipment to receive the delivery. 01 66 00 - 2 DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS Page 2 of 4 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised April 7, 2014 Meacham Commerce Center CPN-103202 4. Deliver products or equipment in manufacturer's original unbroken cartons or other containers designed and constructed to protect the contents from physical or environmental damage. 5. Clearly and fully mark and identify as to manufacturer, item and installation location. 6. Provide manufacturer's instructions for storage and handling. B. Handling Requirements 1. Handle products or equipment in accordance with these Contract Documents and manufacturer’s recommendations and instructions. C. Storage Requirements 1. Store materials in accordance with manufacturer’s recommendations and requirements of these Specifications. 2. Make necessary provisions for safe storage of materials and equipment. a. Place loose soil materials and materials to be incorporated into Work to prevent damage to any part of Work or existing facilities and to maintain free access at all times to all parts of Work and to utility service company installations in vicinity of Work. 3. Keep materials and equipment neatly and compactly stored in locations that will cause minimum inconvenience to other contractors, public travel, adjoining owners, tenants and occupants. a. Arrange storage to provide easy access for inspection. 4. Restrict storage to areas available on construction site for storage of material and equipment as shown on Drawings, or approved by City’s Project Representative. 5. Provide off-site storage and protection when on-site storage is not adequate. a. Provide addresses of and access to off-site storage locations for inspection by City’s Project Representative. 6. Do not use lawns, grass plots or other private property for storage purposes without written permission of owner or other person in possession or control of premises. 7. Store in manufacturers’ unopened containers. 8. Neatly, safely and compactly stack materials delivered and stored along line of Work to avoid inconvenience and damage to property owners and general public and maintain at least 3 feet from fire hydrant. 9. Keep public and private driveways and street crossings open. 10. Repair or replace damaged lawns, sidewalks, streets or other improvements to satisfaction of City’s Project Representative. a. Total length which materials may be distributed along route of construction at one time is 1,000 linear feet, unless otherwise approved in writing by City’s Project Representative. 01 66 00 - 3 DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS Page 3 of 4 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised April 7, 2014 Meacham Commerce Center CPN-103202 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION 3.1 INSTALLERS [NOT USED] 3.2 EXAMINATION [NOT USED] 3.3 PREPARATION [NOT USED] 3.4 ERECTION [NOT USED] 3.5 REPAIR / RESTORATION [NOT USED] 3.6 RE-INSTALLATION [NOT USED] 3.7 FIELD [OR] SITE QUALITY CONTROL A. Tests and Inspections 1. Inspect all products or equipment delivered to the site prior to unloading. B. Non-Conforming Work 1. Reject all products or equipment that are damaged, used or in any other way unsatisfactory for use on the project. 3.8 SYSTEM STARTUP [NOT USED] 3.9 ADJUSTING [NOT USED] 3.10 CLEANING [NOT USED] 3.11 CLOSEOUT ACTIVITIES [NOT USED] 3.12 PROTECTION A. Protect all products or equipment in accordance with manufacturer's written directions. B. Store products or equipment in location to avoid physical damage to items while in storage. C. Protect equipment from exposure to elements and keep thoroughly dry if required by the manufacturer. 3.13 MAINTENANCE [NOT USED] 3.14 ATTACHMENTS [NOT USED] END OF SECTION 01 66 00 - 4 DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS Page 4 of 4 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised April 7, 2014 Meacham Commerce Center CPN-103202 Revision Log DATE NAME SUMMARY OF CHANGE 4/7/2014 M.Domenech Revised for DAP application 01 70 00 - 1 DAP MOBILIZATION AND REMOBILIZATION Page 1 of 4 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised April 7, 2014 Meacham Commerce Center CPN-103202 SECTION 01 70 00 MOBILIZATION AND REMOBILIZATION PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Mobilization and Demobilization a. Mobilization 1) Transportation of Contractor’s personnel, equipment, and operating supplies to the Site 2) Establishment of necessary general facilities for the Contractor’s operation at the Site 3) Premiums paid for performance and payment bonds 4) Transportation of Contractor’s personnel, equipment, and operating supplies to another location within the designated Site 5) Relocation of necessary general facilities for the Contractor’s operation from 1 location to another location on the Site. b. Demobilization 1) Transportation of Contractor’s personnel, equipment, and operating supplies away from the Site including disassembly 2) Site Clean-up 3) Removal of all buildings and/or other facilities assembled at the Site for this Contract c. Mobilization and Demobilization do not include activities for specific items of work that are for which payment is provided elsewhere in the contract. 2. Remobilization a. Remobilization for Suspension of Work specifically required in the Contract Documents or as required by City includes: 1) Demobilization a) Transportation of Contractor’s personnel, equipment, and operating supplies from the Site including disassembly or temporarily securing equipment, supplies, and other facilities as designated by the Contract Documents necessary to suspend the Work. b) Site Clean-up as designated in the Contract Documents 2) Remobilization a) Transportation of Contractor’s personnel, equipment, and operating supplies to the Site necessary to resume the Work. b) Establishment of necessary general facilities for the Contractor’s operation at the Site necessary to resume the Work. 3) No Payments will be made for: a) Mobilization and Demobilization from one location to another on the Site in the normal progress of performing the Work. b) Stand-by or idle time c) Lost profits 3. Mobilizations and Demobilization for Miscellaneous Projects a. Mobilization and Demobilization 01 70 00 - 2 DAP MOBILIZATION AND REMOBILIZATION Page 2 of 4 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised April 7, 2014 Meacham Commerce Center CPN-103202 1) Mobilization shall consist of the activities and cost on a Work Order basis necessary for: a) Transportation of Contractor’s personnel, equipment, and operating supplies to the Site for the issued Work Order. b) Establishment of necessary general facilities for the Contractor’s operation at the Site for the issued Work Order 2) Demobilization shall consist of the activities and cost necessary for: a) Transportation of Contractor’s personnel, equipment, and operating supplies from the Site including disassembly for each issued Work Order b) Site Clean-up for each issued Work Order c) Removal of all buildings or other facilities assembled at the Site for each Work Oder b. Mobilization and Demobilization do not include activities for specific items of work for which payment is provided elsewhere in the contract. 4. Emergency Mobilizations and Demobilization for Miscellaneous Projects a. A Mobilization for Miscellaneous Projects when directed by the City and the mobilization occurs within 24 hours of the issuance of the Work Order. B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Mobilization and Demobilization a. Measure 1) This Item is considered subsidiary to the various Items bid. b. Payment 1) The work performed and materials furnished in accordance with this Item are subsidiary to the various Items bid and no other compensation will be allowed. 2. Remobilization for suspension of Work as specifically required in the Contract Documents a. Measurement 1) Measurement for this Item shall be per each remobilization performed. b. Payment 1) The work performed and materials furnished in accordance with this Item and measured as provided under “Measurement” will be paid for at the unit price per each “Specified Remobilization” in accordance with Contract Documents. c. The price shall include: 1) Demobilization as described in Section 1.1.A.2.a.1) 2) Remobilization as described in Section 1.1.A.2.a.2) d. No payments will be made for standby, idle time, or lost profits associated this Item. 01 70 00 - 3 DAP MOBILIZATION AND REMOBILIZATION Page 3 of 4 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised April 7, 2014 Meacham Commerce Center CPN-103202 3. Remobilization for suspension of Work as required by City a. Measurement and Payment 1) This shall be submitted as a Contract Claim in accordance with Article 10 of Section 00 72 00. 2) No payments will be made for standby, idle time, or lost profits associated with this Item. 4. Mobilizations and Demobilizations for Miscellaneous Projects a. Measurement 1) Measurement for this Item shall be for each Mobilization and Demobilization required by the Contract Documents b. Payment 1) The Work performed and materials furnished in accordance with this Item and measured as provided under “Measurement” will be paid for at the unit price per each “Work Order Mobilization” in accordance with Contract Documents. Demobilization shall be considered subsidiary to mobilization and shall not be paid for separately. c. The price shall include: 1) Mobilization as described in Section 1.1.A.3.a.1) 2) Demobilization as described in Section 1.1.A.3.a.2) d. No payments will be made for standby, idle time, or lost profits associated this Item. 5. Emergency Mobilizations and Demobilizations for Miscellaneous Projects a. Measurement 1) Measurement for this Item shall be for each Mobilization and Demobilization required by the Contract Documents b. Payment 1) The Work performed and materials furnished in accordance with this Item and measured as provided under “Measurement” will be paid for at the unit price per each “Work Order Emergency Mobilization” in accordance with Contract Documents. Demobilization shall be considered subsidiary to mobilization and shall not be paid for separately. c. The price shall include 1) Mobilization as described in Section 1.1.A.4.a) 2) Demobilization as described in Section 1.1.A.3.a.2) d. No payments will be made for standby, idle time, or lost profits associated this Item. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 1.5 SUBMITTALS [NOT USED] 1.6 INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE [NOT USED] 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 01 70 00 - 4 DAP MOBILIZATION AND REMOBILIZATION Page 4 of 4 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised April 7, 2014 Meacham Commerce Center CPN-103202 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 4/7/2014 M.Domenech Revised for DAP application 01 71 23 - 1 DAP CONSTRUCTION STAKING AND SURVEY Page 1 of 4 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised April 7, 2014 Meacham Commerce Center CPN-103202 SECTION 01 71 23 CONSTRUCTION STAKING AND SURVEY PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Requirements for construction staking and construction survey B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Construction Staking a. Measurement 1) This Item is considered subsidiary to the various Items bid. b. Payment 1) The work performed and the materials furnished in accordance with this Item are subsidiary to the various Items bid and no other compensation will be allowed. 2. Construction Survey a. Measurement 1) This Item is considered subsidiary to the various Items bid. b. Payment 1) The work performed and the materials furnished in accordance with this Item are subsidiary to the various Items bid and no other compensation will be allowed. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 1.5 SUBMITTALS A. Submittals, if required, shall be in accordance with Section 01 33 00. B. All submittals shall be approved by the City prior to delivery. 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS A. Certificates 1. Provide certificate certifying that elevations and locations of improvements are in conformance or non-conformance with requirements of the Contract Documents. a. Certificate must be sealed by a registered professional land surveyor in the State of Texas. 01 71 23 - 2 DAP CONSTRUCTION STAKING AND SURVEY Page 2 of 4 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised April 7, 2014 Meacham Commerce Center CPN-103202 B. Field Quality Control Submittals 1. Documentation verifying accuracy of field engineering work. 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE A. Construction Staking 1. Construction staking will be performed by the City. 2. Coordination a. Contact City’s Project Representative at least 2 weeks in advance for scheduling of Construction Staking. b. It is the Contractor’s responsibility to coordinate staking such that construction activities are not delayed or negatively impacted. 3. General a. Contractor is responsible for preserving and maintaining stakes furnished by City. b. If in the opinion of the City, a sufficient number of stakes or markings have been lost, destroyed or disturbed, by Contractor’s neglect, such that the contracted Work cannot take place, then the Contractor will be required to pay the City for new staking with a 25 percent markup. The cost for staking will be deducted from the payment due to the Contractor for the Project. B. Construction Survey 1. Construction Survey will be performed by the City. 2. Coordination a. Contractor to verify that control data established in the design survey remains intact. b. Coordinate with the City prior to field investigation to determine which horizontal and vertical control data will be required for construction survey. c. It is the Contractor’s responsibility to coordinate Construction Survey such that construction activities are not delayed or negatively impacted. d. Notify City if any control data needs to be restored or replaced due to damage caused during construction operations. 1) City shall perform replacements and/or restorations. 3. General a. Construction survey will be performed in order to maintain complete and accurate logs of control and survey work as it progresses for Project Records. b. The Contractor will need to ensure coordination is maintained with the City to perform construction survey to obtain construction features, including but not limited to the following: 1) All Utility Lines a) Rim and flowline elevations and coordinates for each manhole or junction structure 2) Water Lines a) Top of pipe elevations and coordinates for waterlines at the following locations: (1) Every 250 linear feet 01 71 23 - 3 DAP CONSTRUCTION STAKING AND SURVEY Page 3 of 4 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised April 7, 2014 Meacham Commerce Center CPN-103202 (2) Horizontal and vertical points of inflection, curvature, etc. (All Fittings) (3) Cathodic protection test stations (4) Sampling stations (5) Meter boxes/vaults (All sizes) (6) Fire lines (7) Fire hydrants (8) Gate valves (9) Plugs, stubouts, dead-end lines (10) Air Release valves (Manhole rim and vent pipe) (11) Blow off valves (Manhole rim and valve lid) (12) Pressure plane valves (13) Cleaning wyes (14) Casing pipe (each end) b) Storm Sewer (1) Top of pipe elevations and coordinates at the following locations: (a) Every 250 linear feet (b) Horizontal and vertical points of inflection, curvature, etc. c) Sanitary Sewer (1) Top of pipe elevations and coordinates for sanitary sewer lines at the following locations: (a) Every 250 linear feet (b) Horizontal and vertical points of inflection, curvature, etc. (c) Cleanouts c. Construction survey will be performed in order to maintain complete and accurate logs of control and survey work associated with meeting or exceeding the line and grade required by these Specifications. d. The Contractor will need to ensure coordination is maintained with the City to perform construction survey and to verify control data, including but not limited to the following: 1) Established benchmarks and control points provided for the Contractor’s use are accurate 2) Benchmarks were used to furnish and maintain all reference lines and grades for tunneling 3) Lines and grades were used to establish the location of the pipe 4) Submit to the City copies of field notes used to establish all lines and grades and allow the City to check guidance system setup prior to beginning each tunneling drive. 5) Provide access for the City to verify the guidance system and the line and grade of the carrier pipe on a daily basis. 6) The Contractor remains fully responsible for the accuracy of the work and the correction of it, as required. 7) Monitor line and grade continuously during construction. 8) Record deviation with respect to design line and grade once at each pipe joint and submit daily records to City. 9) If the installation does not meet the specified tolerances, immediately notify the City and correct the installation in accordance with the Contract Documents. 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 01 71 23 - 4 DAP CONSTRUCTION STAKING AND SURVEY Page 4 of 4 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised April 7, 2014 Meacham Commerce Center CPN-103202 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION 3.1 INSTALLERS [NOT USED] 3.2 EXAMINATION [NOT USED] 3.3 PREPARATION [NOT USED] 3.4 APPLICATION 3.5 REPAIR / RESTORATION [NOT USED] 3.6 RE-INSTALLATION [NOT USED] 3.7 FIELD [OR] SITE QUALITY CONTROL A. It is the Contractor’s responsibility to maintain all stakes and control data placed by the City in accordance with this Specification. B. Do not change or relocate stakes or control data without approval from the City. 3.8 SYSTEM STARTUP [NOT USED] 3.9 ADJUSTING [NOT USED] 3.10 CLEANING [NOT USED] 3.11 CLOSEOUT ACTIVITIES [NOT USED] 3.12 PROTECTION [NOT USED] 3.13 MAINTENANCE [NOT USED] 3.14 ATTACHMENTS [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 4/7/2014 M.Domenech Revised for DAP application 01 74 23 - 1 DAP CLEANING Page 1 of 4 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised April 7, 2014 Meacham Commerce Center CPN-103202 SECTION 01 74 23 CLEANING PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Intermediate and final cleaning for Work not including special cleaning of closed systems specified elsewhere B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 3. Section 32 92 13 – Hydro-Mulching, Seeding and Sodding 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various Items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS A. Scheduling 1. Schedule cleaning operations so that dust and other contaminants disturbed by cleaning process will not fall on newly painted surfaces. 2. Schedule final cleaning upon completion of Work and immediately prior to final inspection. 1.5 SUBMITTALS [NOT USED] 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE [NOT USED] 1.10 STORAGE, AND HANDLING A. Storage and Handling Requirements 1. Store cleaning products and cleaning wastes in containers specifically designed for those materials. 01 74 23 - 2 DAP CLEANING Page 2 of 4 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised April 7, 2014 Meacham Commerce Center CPN-103202 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS 2.1 OWNER-FURNISHED [OR] OWNER-SUPPLIEDPRODUCTS [NOT USED] 2.2 MATERIALS A. Cleaning Agents 1. Compatible with surface being cleaned 2. New and uncontaminated 3. For manufactured surfaces a. Material recommended by manufacturer 2.3 ACCESSORIES [NOT USED] 2.4 SOURCE QUALITY CONTROL [NOT USED] PART 3 - EXECUTION 3.1 INSTALLERS [NOT USED] 3.2 EXAMINATION [NOT USED] 3.3 PREPARATION [NOT USED] 3.4 APPLICATION [NOT USED] 3.5 REPAIR / RESTORATION [NOT USED] 3.6 RE-INSTALLATION [NOT USED] 3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED] 3.8 SYSTEM STARTUP [NOT USED] 3.9 ADJUSTING [NOT USED] 3.10 CLEANING A. General 1. Prevent accumulation of wastes that create hazardous conditions. 2. Conduct cleaning and disposal operations to comply with laws and safety orders of governing authorities. 3. Do not dispose of volatile wastes such as mineral spirits, oil or paint thinner in storm or sanitary drains or sewers. 4. Dispose of degradable debris at an approved solid waste disposal site. 5. Dispose of nondegradable debris at an approved solid waste disposal site or in an alternate manner approved by City and regulatory agencies. 01 74 23 - 3 DAP CLEANING Page 3 of 4 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised April 7, 2014 Meacham Commerce Center CPN-103202 6. Handle materials in a controlled manner with as few handlings as possible. 7. Thoroughly clean, sweep, wash and polish all Work and equipment associated with this project. 8. Remove all signs of temporary construction and activities incidental to construction of required permanent Work. 9. If project is not cleaned to the satisfaction of the City, the City reserves the right to have the cleaning completed at the expense of the Contractor. 10. Do not burn on-site. B. Intermediate Cleaning during Construction 1. Keep Work areas clean so as not to hinder health, safety or convenience of personnel in existing facility operations. 2. At maximum weekly intervals, dispose of waste materials, debris and rubbish. 3. Confine construction debris daily in strategically located container(s): a. Cover to prevent blowing by wind b. Store debris away from construction or operational activities c. Haul from site at a minimum of once per week 4. Vacuum clean interior areas when ready to receive finish painting. a. Continue vacuum cleaning on an as-needed basis, until Final Acceptance. 5. Prior to storm events, thoroughly clean site of all loose or unsecured items, which may become airborne or transported by flowing water during the storm. C. Exterior (Site or Right of Way) Final Cleaning 1. Remove trash and debris containers from site. a. Re-seed areas disturbed by location of trash and debris containers in accordance with Section 32 92 13. 2. Sweep roadway to remove all rocks, pieces of asphalt, concrete or any other object that may hinder or disrupt the flow of traffic along the roadway. 3. Clean any interior areas including, but not limited to, vaults, manholes, structures, junction boxes and inlets. 4. If no longer required for maintenance of erosion facilities, and upon approval by City, remove erosion control from site. 5. Clean signs, lights, signals, etc. 3.11 CLOSEOUT ACTIVITIES [NOT USED] 3.12 PROTECTION [NOT USED] 3.13 MAINTENANCE [NOT USED] 3.14 ATTACHMENTS [NOT USED] 01 74 23 - 4 DAP CLEANING Page 4 of 4 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised April 7, 2014 Meacham Commerce Center CPN-103202 END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 4/7/2014 M.Domenech Revised for DAP application 01 77 19 - 1 DAP CLOSEOUT REQUIREMENTS Page 1 of 3 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised April 7, 2014 Meacham Commerce Center CPN-103202 SECTION 01 77 19 CLOSEOUT REQUIREMENTS PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. The procedure for closing out a contract B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various Items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS A. Guarantees, Bonds and Affidavits 1. No application for final payment will be accepted until all guarantees, bonds, certificates, licenses and affidavits required for Work or equipment as specified are satisfactorily filed with the City. B. Release of Liens or Claims 1. No application for final payment will be accepted until satisfactory evidence of release of liens has been submitted to the City. 1.5 SUBMITTALS A. Submit all required documentation to City’s Project Representative. 01 77 19 - 2 DAP CLOSEOUT REQUIREMENTS Page 2 of 3 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised April 7, 2014 Meacham Commerce Center CPN-103202 1.6 INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION 3.1 INSTALLERS [NOT USED] 3.2 EXAMINATION [NOT USED] 3.3 PREPARATION [NOT USED] 3.4 CLOSEOUT PROCEDURE A. Prior to requesting Final Inspection, submit: 1. Project Record Documents in accordance with Section 01 78 39 2. Operation and Maintenance Data, if required, in accordance with Section 01 78 23 B. Prior to requesting Final Inspection, perform final cleaning in accordance with Section 01 74 23. C. Final Inspection 1. After final cleaning, provide notice to the City Project Representative that the Work is completed. a. The City will make an initial Final Inspection with the Contractor present. b. Upon completion of this inspection, the City will notify the Contractor, in writing within 10 business days, of any particulars in which this inspection reveals that the Work is defective or incomplete. 2. Upon receiving written notice from the City, immediately undertake the Work required to remedy deficiencies and complete the Work to the satisfaction of the City. 3. Upon completion of Work associated with the items listed in the City's written notice, inform the City, that the required Work has been completed. Upon receipt of this notice, the City, in the presence of the Contractor, will make a subsequent Final Inspection of the project. 4. Provide all special accessories required to place each item of equipment in full operation. These special accessory items include, but are not limited to: a. Specified spare parts b. Adequate oil and grease as required for the first lubrication of the equipment c. Initial fill up of all chemical tanks and fuel tanks d. Light bulbs e. Fuses f. Vault keys g. Handwheels h. Other expendable items as required for initial start-up and operation of all equipment D. Notice of Project Completion 01 77 19 - 3 DAP CLOSEOUT REQUIREMENTS Page 3 of 3 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised April 7, 2014 Meacham Commerce Center CPN-103202 1. Once the City Project Representative finds the Work subsequent to Final Inspection to be satisfactory, the City will issue a Notice of Project Completion (Green Sheet). E. Supporting Documentation 1. Coordinate with the City Project Representative to complete the following additional forms: a. Final Payment Request b. Statement of Contract Time c. Affidavit of Payment and Release of Liens d. Consent of Surety to Final Payment e. Pipe Report (if required) f. Contractor’s Evaluation of City g. Performance Evaluation of Contractor F. Letter of Final Acceptance 1. Upon review and acceptance of Notice of Project Completion and Supporting Documentation, in accordance with General Conditions, City will issue Letter of Final Acceptance and release the Final Payment Request for payment. 3.5 REPAIR / RESTORATION [NOT USED] 3.6 RE-INSTALLATION [NOT USED] 3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED] 3.8 SYSTEM STARTUP [NOT USED] 3.9 ADJUSTING [NOT USED] 3.10 CLEANING [NOT USED] 3.11 CLOSEOUT ACTIVITIES [NOT USED] 3.12 PROTECTION [NOT USED] 3.13 MAINTENANCE [NOT USED] 3.14 ATTACHMENTS [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 4/7/2014 M.Domenech Revised for DAP application 01 78 23 - 1 DAP OPERATION AND MAINTENANCE DATA Page 1 of 5 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised April 7, 2014 Meacham Commerce Center CPN-103202 SECTION 01 78 23 OPERATION AND MAINTENANCE DATA PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Product data and related information appropriate for City's maintenance and operation of products furnished under Contract 2. Such products may include, but are not limited to: a. Traffic Controllers b. Irrigation Controllers (to be operated by the City) c. Butterfly Valves B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various Items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS A. Schedule 1. Submit manuals in final form to the City within 30 calendar days of product shipment to the project site. 1.5 SUBMITTALS A. Submittals shall be in accordance with Section 01 33 00. All submittals shall be approved by the City prior to delivery. 1.6 INFORMATIONAL SUBMITTALS A. Submittal Form 1. Prepare data in form of an instructional manual for use by City personnel. 2. Format a. Size: 8 ½ inches x 11 inches b. Paper 1) 40 pound minimum, white, for typed pages 2) Holes reinforced with plastic, cloth or metal c. Text: Manufacturer’s printed data, or neatly typewritten 01 78 23 - 2 DAP OPERATION AND MAINTENANCE DATA Page 2 of 5 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised April 7, 2014 Meacham Commerce Center CPN-103202 d. Drawings 1) Provide reinforced punched binder tab, bind in with text 2) Reduce larger drawings and fold to size of text pages. e. Provide fly-leaf for each separate product, or each piece of operating equipment. 1) Provide typed description of product, and major component parts of equipment. 2) Provide indexed tabs. f. Cover 1) Identify each volume with typed or printed title "OPERATING AND MAINTENANCE INSTRUCTIONS". 2) List: a) Title of Project b) Identity of separate structure as applicable c) Identity of general subject matter covered in the manual 3. Binders a. Commercial quality 3-ring binders with durable and cleanable plastic covers b. When multiple binders are used, correlate the data into related consistent groupings. 4. If available, provide an electronic form of the O&M Manual. B. Manual Content 1. Neatly typewritten table of contents for each volume, arranged in systematic order a. Contractor, name of responsible principal, address and telephone number b. A list of each product required to be included, indexed to content of the volume c. List, with each product: 1) The name, address and telephone number of the subcontractor or installer 2) A list of each product required to be included, indexed to content of the volume 3) Identify area of responsibility of each 4) Local source of supply for parts and replacement d. Identify each product by product name and other identifying symbols as set forth in Contract Documents. 2. Product Data a. Include only those sheets which are pertinent to the specific product. b. Annotate each sheet to: 1) Clearly identify specific product or part installed 2) Clearly identify data applicable to installation 3) Delete references to inapplicable information 3. Drawings a. Supplement product data with drawings as necessary to clearly illustrate: 1) Relations of component parts of equipment and systems 2) Control and flow diagrams b. Coordinate drawings with information in Project Record Documents to assure correct illustration of completed installation. c. Do not use Project Record Drawings as maintenance drawings. 4. Written text, as required to supplement product data for the particular installation: a. Organize in consistent format under separate headings for different procedures. b. Provide logical sequence of instructions of each procedure. 01 78 23 - 3 DAP OPERATION AND MAINTENANCE DATA Page 3 of 5 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised April 7, 2014 Meacham Commerce Center CPN-103202 5. Copy of each warranty, bond and service contract issued a. Provide information sheet for City personnel giving: 1) Proper procedures in event of failure 2) Instances which might affect validity of warranties or bonds C. Manual for Materials and Finishes 1. Submit 5 copies of complete manual in final form. 2. Content, for architectural products, applied materials and finishes: a. Manufacturer's data, giving full information on products 1) Catalog number, size, composition 2) Color and texture designations 3) Information required for reordering special manufactured products b. Instructions for care and maintenance 1) Manufacturer's recommendation for types of cleaning agents and methods 2) Cautions against cleaning agents and methods which are detrimental to product 3) Recommended schedule for cleaning and maintenance 3. Content, for moisture protection and weather exposure products: a. Manufacturer's data, giving full information on products 1) Applicable standards 2) Chemical composition 3) Details of installation b. Instructions for inspection, maintenance and repair D. Manual for Equipment and Systems 1. Submit 5 copies of complete manual in final form. 2. Content, for each unit of equipment and system, as appropriate: a. Description of unit and component parts 1) Function, normal operating characteristics and limiting conditions 2) Performance curves, engineering data and tests 3) Complete nomenclature and commercial number of replaceable parts b. Operating procedures 1) Start-up, break-in, routine and normal operating instructions 2) Regulation, control, stopping, shut-down and emergency instructions 3) Summer and winter operating instructions 4) Special operating instructions c. Maintenance procedures 1) Routine operations 2) Guide to "trouble shooting" 3) Disassembly, repair and reassembly 4) Alignment, adjusting and checking d. Servicing and lubrication schedule 1) List of lubricants required e. Manufacturer's printed operating and maintenance instructions f. Description of sequence of operation by control manufacturer 1) Predicted life of parts subject to wear 2) Items recommended to be stocked as spare parts g. As installed control diagrams by controls manufacturer h. Each contractor's coordination drawings 1) As installed color coded piping diagrams 01 78 23 - 4 DAP OPERATION AND MAINTENANCE DATA Page 4 of 5 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised April 7, 2014 Meacham Commerce Center CPN-103202 i. Charts of valve tag numbers, with location and function of each valve j. List of original manufacturer's spare parts, manufacturer's current prices, and recommended quantities to be maintained in storage k. Other data as required under pertinent Sections of Specifications 3. Content, for each electric and electronic system, as appropriate: a. Description of system and component parts 1) Function, normal operating characteristics, and limiting conditions 2) Performance curves, engineering data and tests 3) Complete nomenclature and commercial number of replaceable parts b. Circuit directories of panelboards 1) Electrical service 2) Controls 3) Communications c. As installed color coded wiring diagrams d. Operating procedures 1) Routine and normal operating instructions 2) Sequences required 3) Special operating instructions e. Maintenance procedures 1) Routine operations 2) Guide to "trouble shooting" 3) Disassembly, repair and reassembly 4) Adjustment and checking f. Manufacturer's printed operating and maintenance instructions g. List of original manufacturer's spare parts, manufacturer's current prices, and recommended quantities to be maintained in storage h. Other data as required under pertinent Sections of Specifications 4. Prepare and include additional data when the need for such data becomes apparent during instruction of City's personnel. 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE A. Provide operation and maintenance data by personnel with the following criteria: 1. Trained and experienced in maintenance and operation of described products 2. Skilled as technical writer to the extent required to communicate essential data 3. Skilled as draftsman competent to prepare required drawings 01 78 23 - 5 DAP OPERATION AND MAINTENANCE DATA Page 5 of 5 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised April 7, 2014 Meacham Commerce Center CPN-103202 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 8/31/2012 D. Johnson 1.5.A.1 – title of section removed 4/7/2014 M.Domenech Revised for DAP Application 01 78 39 - 1 DAP PROJECT RECORD DOCUMENTS Page 1 of 4 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised April 7, 2014 Meacham Commerce Center CPN-103202 SECTION 01 78 39 PROJECT RECORD DOCUMENTS PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Work associated with the documenting the project and recording changes to project documents, including: a. Record Drawings b. Water Meter Service Reports c. Sanitary Sewer Service Reports d. Large Water Meter Reports B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various Items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 1.5 SUBMITTALS A. Prior to submitting a request for Final Inspection, deliver Project Record Documents to City’s Project Representative. 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE A. Accuracy of Records 1. Thoroughly coordinate changes within the Record Documents, making adequate and proper entries on each page of Specifications and each sheet of Drawings and other Documents where such entry is required to show the change properly. 2. Accuracy of records shall be such that future search for items shown in the Contract Documents may rely reasonably on information obtained from the approved Project Record Documents. 01 78 39 - 2 DAP PROJECT RECORD DOCUMENTS Page 2 of 4 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised April 7, 2014 Meacham Commerce Center CPN-103202 3. To facilitate accuracy of records, make entries within 24 hours after receipt of information that the change has occurred. 4. Provide factual information regarding all aspects of the Work, both concealed and visible, to enable future modification of the Work to proceed without lengthy and expensive site measurement, investigation and examination. 1.10 STORAGE AND HANDLING A. Storage and Handling Requirements 1. Maintain the job set of Record Documents completely protected from deterioration and from loss and damage until completion of the Work and transfer of all recorded data to the final Project Record Documents. 2. In the event of loss of recorded data, use means necessary to again secure the data to the City's approval. a. In such case, provide replacements to the standards originally required by the Contract Documents. 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS 2.1 OWNER-FURNISHED [OR] OWNER-SUPPLIED PRODUCTS [NOT USED] 2.2 RECORD DOCUMENTS A. Job set 1. Promptly following receipt of the Notice to Proceed, secure from the City, at no charge to the Contractor, 1 complete set of all Documents comprising the Contract. B. Final Record Documents 1. At a time nearing the completion of the Work and prior to Final Inspection, provide the City 1 complete set of all Final Record Drawings in the Contract. 2.3 ACCESSORIES [NOT USED] 2.4 SOURCE QUALITY CONTROL [NOT USED] PART 3 - EXECUTION 3.1 INSTALLERS [NOT USED] 3.2 EXAMINATION [NOT USED] 3.3 PREPARATION [NOT USED] 3.4 MAINTENANCE DOCUMENTS A. Maintenance of Job Set 1. Immediately upon receipt of the job set, identify each of the Documents with the title, "RECORD DOCUMENTS - JOB SET". 01 78 39 - 3 DAP PROJECT RECORD DOCUMENTS Page 3 of 4 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised April 7, 2014 Meacham Commerce Center CPN-103202 2. Preservation a. Considering the Contract completion time, the probable number of occasions upon which the job set must be taken out for new entries and for examination, and the conditions under which these activities will be performed, devise a suitable method for protecting the job set. b. Do not use the job set for any purpose except entry of new data and for review by the City, until start of transfer of data to final Project Record Documents. c. Maintain the job set at the site of work. 3. Coordination with Construction Survey a. At a minimum clearly mark any deviations from Contract Documents associated with installation of the infrastructure. 4. Making entries on Drawings a. Record any deviations from Contract Documents. b. Use an erasable colored pencil (not ink or indelible pencil), clearly describe the change by graphic line and note as required. c. Date all entries. d. Call attention to the entry by a "cloud" drawn around the area or areas affected. e. In the event of overlapping changes, use different colors for the overlapping changes. 5. Conversion of schematic layouts a. In some cases on the Drawings, arrangements of conduits, circuits, piping, ducts, and similar items, are shown schematically and are not intended to portray precise physical layout. 1) Final physical arrangement is determined by the Contractor, subject to the City's approval. 2) However, design of future modifications of the facility may require accurate information as to the final physical layout of items which are shown only schematically on the Drawings. b. Show on the job set of Record Drawings, by dimension accurate to within 1 inch, the centerline of each run of items. 1) Final physical arrangement is determined by the Contractor, subject to the City's approval. 2) Show, by symbol or note, the vertical location of the Item ("under slab", "in ceiling plenum", "exposed", and the like). 3) Make all identification sufficiently descriptive that it may be related reliably to the Specifications. c. The City may waive the requirements for conversion of schematic layouts where, in the City's judgment, conversion serves no useful purpose. However, do not rely upon waivers being issued except as specifically issued in writing by the City. B. Final Project Record Documents 1. Transfer of data to Drawings a. Carefully transfer change data shown on the job set of Record Drawings to the corresponding final documents, coordinating the changes as required. b. Clearly indicate at each affected detail and other Drawing a full description of changes made during construction, and the actual location of items. c. Call attention to each entry by drawing a "cloud" around the area or areas affected. 01 78 39 - 4 DAP PROJECT RECORD DOCUMENTS Page 4 of 4 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised April 7, 2014 Meacham Commerce Center CPN-103202 d. Make changes neatly, consistently and with the proper media to assure longevity and clear reproduction. 2. Transfer of data to other Documents a. If the Documents, other than Drawings, have been kept clean during progress of the Work, and if entries thereon have been orderly to the approval of the City, the job set of those Documents, other than Drawings, will be accepted as final Record Documents. b. If any such Document is not so approved by the City, secure a new copy of that Document from the City at the City's usual charge for reproduction and handling, and carefully transfer the change data to the new copy to the approval of the City. 3.5 REPAIR / RESTORATION [NOT USED] 3.6 RE-INSTALLATION [NOT USED] 3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED] 3.8 SYSTEM STARTUP [NOT USED] 3.9 ADJUSTING [NOT USED] 3.10 CLEANING [NOT USED] 3.11 CLOSEOUT ACTIVITIES [NOT USED] 3.12 PROTECTION [NOT USED] 3.13 MAINTENANCE [NOT USED] 3.14 ATTACHMENTS [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 4/7/2014 M.Domenech Revised for DAP Application