HomeMy WebLinkAboutContract 56732-PM1PROJECT MANUAL
FOR
THE CONSTRUCTION OF
WATER AND SEWER
IMPROVEMENT TO SERVE
SOUTHLAND TERRACE ADDITION
LOT 3, BLOCK 4-R
IPRC Record No. IPRC21-0111
City Project No. 103651
FID No. 30114-0200431-103651-E07685
File No.
X File No. X-27080
Mattie Parker David Cooke
Mayor City Manager
Christopher P. Harder, P.E.
Director, Water Department
Prepared for
The City of Fort Worth
AUGUST 2021
HAMILTON DUFFY, P.C.
8241 MID-CITIES BLVD., STE. 100
NORTH RICHLAND HILLS, TX 76182
CSC No. 56732-PM1
00 00 00
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Page 1 of 8
CITY OF FORT WORTH SOUTHLAND TERRACE ADDITION LOT 3, BLOCK 4-R
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS PROJECT NO. 103651
Revised March 20, 2020
SECTION 00 00 10
TABLE OF CONTENTS
DEVELOPER AWARDED PROJECTS
Division 00 - General Conditions Last Revised
00 42 43 Proposal Form Unit Price 05/22/2019
00 45 12 Prequalification Statement 09/01/2015
00 45 13 Bidder Prequalification Application 03/09/2020
00 45 26 Contractor Compliance with Workers' Compensation Law 04/02/2014
00 52 43 Agreement 06/16/2016
00 61 25 Certificate of Insurance 07/01/2011
00 62 13 Performance Bond 01/31/2012
00 62 14 Payment Bond 01/31/2012
00 62 19 Maintenance Bond 01/31/2012
00 73 10 Standard City Conditions of the Construction Contract for Developer
Awarded Projects 01/10/2013
Division 01 - General Requirements Last Revised
01 11 00 Summary of Work 12/20/2012
01 25 00 Substitution Procedures 08/30/2013
01 31 19 Preconstruction Meeting 08/30/2013
01 31 20 Project Meetings 07/01/2011
01 32 33 Preconstruction Video 08/30/2013
01 33 00 Submittals 08/30/2013
01 35 13 Special Project Procedures 08/30/2013
01 45 23 Testing and Inspection Services 03/20/2020
01 50 00 Temporary Facilities and Controls 07/01/2011
01 55 26 Street Use Permit and Modifications to Traffic Control 07/01/2011
01 57 13 Storm Water Pollution Prevention Plan 07/01/2011
01 60 00 Product Requirements 03/20/2020
01 66 00 Product Storage and Handling Requirements 04/07/2014
01 70 00 Mobilization and Remobilization 04/07/2014
01 71 23 Construction Staking 04/07/2014
01 74 23 Cleaning 04/07/2014
01 77 19 Closeout Requirements 04/07/2014
01 78 23 Operation and Maintenance Data 04/07/2014
01 78 39 Project Record Documents 04/07/2014
00 00 00
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Page 2 of 8
CITY OF FORT WORTH SOUTHLAND TERRACE ADDITION LOT 3, BLOCK 4-R
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS PROJECT NO. 103651
Revised March 20, 2020
Technical Specifications which have been modified by the Engineer specifically for this
Project; hard copies are included in the Project’s Contract Documents
Division 02 - Existing Conditions
Date
Modified
02 41 13 Selective Site Demolition NONE
02 41 14 Utility Removal/Abandonment NONE
02 41 15 Paving Removal NONE
Division 03 - Concrete
03 30 00 Cast-In-Place Concrete NONE
03 34 13 Controlled Low Strength Material (CLSM) NONE
03 34 16 Concrete Base Material for Trench Repair NONE
03 80 00 Modifications to Existing Concrete Structures NONE
Division 26 - Electrical
26 05 00 Common Work Results for Electrical NONE
26 05 10 Demolition for Electrical Systems NONE
26 05 33 Raceways and Boxes for Electrical Systems NONE
26 05 43 Underground Ducts and Raceways for Electrical Systems NONE
Division 31 - Earthwork
31 10 00 Site Clearing NONE
31 23 16 Unclassified Excavation NONE
31 23 23 Borrow NONE
31 24 00 Embankments NONE
31 25 00 Erosion and Sediment Control NONE
31 36 00 Gabions NONE
31 37 00 Riprap NONE
Division 32 - Exterior Improvements
32 01 17 Permanent Asphalt Paving Repair NONE
32 01 18 Temporary Asphalt Paving Repair NONE
32 01 29 Concrete Paving Repair NONE
32 11 23 Flexible Base Courses NONE
32 11 29 Lime Treated Base Courses NONE
32 11 33 Cement Treated Base Courses NONE
32 11 37 Liquid Treated Soil Stabilizer NONE
32 12 16 Asphalt Paving NONE
32 12 73 Asphalt Paving Crack Sealants NONE
32 13 13 Concrete Paving NONE
32 13 20 Concrete Sidewalks, Driveways and Barrier Free Ramps NONE
32 13 73 Concrete Paving Joint Sealants NONE
32 14 16 Brick Unit Paving NONE
32 16 13 Concrete Curb and Gutters and Valley Gutters NONE
32 17 23 Pavement Markings NONE
32 17 25 Curb Address Painting NONE
32 31 13 Chain Fences and Gates NONE
00 00 00
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Page 3 of 8
CITY OF FORT WORTH SOUTHLAND TERRACE ADDITION LOT 3, BLOCK 4-R
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS PROJECT NO. 103651
Revised March 20, 2020
32 31 26 Wire Fences and Gates NONE
32 31 29 Wood Fences and Gates NONE
32 32 13 Cast-in-Place Concrete Retaining Walls NONE
32 91 19 Topsoil Placement and Finishing of Parkways NONE
32 92 13 Hydro-Mulching, Seeding, and Sodding NONE
32 93 43 Trees and Shrubs NONE
Division 33 - Utilities
33 01 30 Sewer and Manhole Testing NONE
33 01 31 Closed Circuit Television (CCTV) Inspection NONE
33 03 10 Bypass Pumping of Existing Sewer Systems NONE
33 04 10 Joint Bonding and Electrical Isolation NONE
33 04 11 Corrosion Control Test Stations NONE
33 04 12 Magnesium Anode Cathodic Protection System NONE
33 04 30 Temporary Water Services NONE
33 04 40 Cleaning and Acceptance Testing of Water Mains NONE
33 04 50 Cleaning of Sewer Mains NONE
33 05 10 Utility Trench Excavation, Embedment, and Backfill NONE
33 05 12 Water Line Lowering NONE
33 05 13 Frame, Cover and Grade Rings - Cast Iron NONE
33 05 13.10 Frame, Cover and Grade Rings - Composite NONE
33 05 14 Adjusting Manholes, Inlets, Valve Boxes, and Other Structures to
Grade NONE
33 05 16 Concrete Water Vaults NONE
33 05 17 Concrete Collars NONE
33 05 20 Auger Boring NONE
33 05 21 Tunnel Liner Plate NONE
33 05 22 Steel Casing Pipe NONE
33 05 23 Hand Tunneling NONE
33 05 24 Installation of Carrier Pipe in Casing or Tunnel Liner Plate NONE
33 05 26 Utility Markers/Locators NONE
33 05 30 Location of Existing Utilities NONE
33 11 05 Bolts, Nuts, and Gaskets NONE
33 11 10 Ductile Iron Pipe NONE
33 11 11 Ductile Iron Fittings NONE
33 11 12 Polyvinyl Chloride (PVC) Pressure Pipe NONE
33 11 13 Concrete Pressure Pipe, Bar-Wrapped, Steel Cylinder Type NONE
33 11 14 Buried Steel Pipe and Fittings NONE
33 11 15 Pre-Stressed Concrete Cylinder Pipe NONE
33 12 10 Water Services 1-inch to 2-inch NONE
33 12 11 Large Water Meters NONE
33 12 20 Resilient Seated Gate Valve NONE
33 12 21 AWWA Rubber-Seated Butterfly Valves NONE
33 12 25 Connection to Existing Water Mains NONE
33 12 30 Combination Air Valve Assemblies for Potable Water Systems NONE
33 12 40 Fire Hydrants NONE
33 12 50 Water Sample Stations NONE
33 12 60 Standard Blow-off Valve Assembly NONE
33 31 12 Cured in Place Pipe (CIPP) NONE
00 00 00
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Page 4 of 8
CITY OF FORT WORTH SOUTHLAND TERRACE ADDITION LOT 3, BLOCK 4-R
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS PROJECT NO. 103651
Revised March 20, 2020
33 31 13 Fiberglass Reinforced Pipe for Gravity Sanitary Sewers NONE
33 31 15 High Density Polyethylene (HDPE) Pipe for Sanitary Sewer NONE
33 31 20 Polyvinyl Chloride (PVC) Gravity Sanitary Sewer Pipe NONE
33 31 21 Polyvinyl Chloride (PVC) Closed Profile Gravity Sanitary Sewer
Pipe
NONE
33 31 22 Sanitary Sewer Slip Lining NONE
33 31 23 Sanitary Sewer Pipe Enlargement NONE
33 31 50 Sanitary Sewer Service Connections and Service Line NONE
33 31 70 Combination Air Valve for Sanitary Sewer Force Mains NONE
33 39 10 Cast-in-Place Concrete Manholes NONE
33 39 20 Precast Concrete Manholes NONE
33 39 30 Fiberglass Manholes NONE
33 39 40 Wastewater Access Chamber (WAC) NONE
33 39 60 Epoxy Liners for Sanitary Sewer Structures NONE
33 41 10 Reinforced Concrete Storm Sewer Pipe/Culverts NONE
33 41 11 High Density Polyethylene (HDPE) Pipe for Storm Drain NONE
33 41 12 Reinforced Polyethlene (SRPE) Pipe NONE
33 46 00 Subdrainage NONE
33 46 01 Slotted Storm Drains NONE
33 46 02 Trench Drains NONE
33 49 10 Cast-in-Place Manholes and Junction Boxes NONE
33 49 20 Curb and Drop Inlets NONE
33 49 40 Storm Drainage Headwalls and Wingwalls NONE
Division 34 - Transportation
34 41 10 Traffic Signals NONE
34 41 10.01 Attachment A – Controller Cabinet NONE
34 41 10.02 Attachment B – Controller Specification NONE
34 41 10.03 Attachment C – Software Specification NONE
34 41 11 Temporary Traffic Signals NONE
34 41 13 Removing Traffic Signals NONE
34 41 15 Rectangular Rapid Flashing Beacon NONE
34 41 16 Pedestrian Hybrid Signal NONE
34 41 20 Roadway Illumination Assemblies NONE
34 41 20.01 Arterial LED Roadway Luminaires NONE
34 41 20.02 Freeway LED Roadway Luminaires NONE
34 41 20.03 Residential LED Roadway Luminaires NONE
34 41 30 Aluminum Signs NONE
34 71 13 Traffic Control NONE
00 00 00
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Page 5 of 8
CITY OF FORT WORTH SOUTHLAND TERRACE ADDITION LOT 3, BLOCK 4-R
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS PROJECT NO. 103651
Revised March 20, 2020
Technical Specifications listed below are included for this Project by reference and can be
viewed/downloaded from the City’s website at:
http://fortworthtexas.gov/tpw/contractors/
or
https://apps.fortworthtexas.gov/ProjectResources/
Division 02 - Existing Conditions Last Revised
02 41 13 Selective Site Demolition 12/20/2012
02 41 14 Utility Removal/Abandonment 12/20/2012
02 41 15 Paving Removal 02/02/2016
Division 03 Concrete
03 30 00 Cast In Place Concrete 12/20/2012
03 34 13 Controlled Low Strength Material (CLSM) 12/20/2012
03 34 16 Concrete Base Material for Trench Repair 12/20/2012
03 80 00 Modifications to Existing Concrete Structures 12/20/2012
Division 26 Electrical
26 05 00 Common Work Results for Electrical 11/22/2013
26 05 10 Demolition for Electrical Systems 12/20/2012
26 05 33 Raceways and Boxes for Electrical Systems 12/20/2012
26 05 43 Underground Ducts and Raceways for Electrical Systems 07/01/2011
26 05 50 Communications Multi Duct Conduit
02/26/2016
Division 31 - Earthwork
31 10 00 Site Clearing 12/20/2012
31 23 16 Unclassified Excavation 01/28/2013
31 23 23 Borrow 01/28/2013
31 24 00 Embankments 01/28/2013
31 25 00 Erosion and Sediment Control 12/20/2012
31 36 00 Gabions 12/20/2012
31 37 00 Riprap 12/20/2012
Division 32 - Exterior Improvements
32 01 17 Permanent Asphalt Paving Repair 12/20/2012
32 01 18 Temporary Asphalt Paving Repair 12/20/2012
32 01 29 Concrete Paving Repair 12/20/2012
32 11 23 Flexible Base Courses 12/20/2012
32 11 29 Lime Treated Base Courses 12/20/2012
32 11 33 Cement Treated Base Courses 12/20/2012
32 11 37 Liquid Treated Soil Stabilizer 08/21/2015
32 12 16 Asphalt Paving 12/20/2012
32 12 73 Asphalt Paving Crack Sealants 12/20/2012
32 13 13 Concrete Paving 12/20/2012
32 13 20 Concrete Sidewalks, Driveways and Barrier Free Ramps 06/05/2018
32 13 73 Concrete Paving Joint Sealants 12/20/2012
32 14 16 Brick Unit Paving 12/20/2012
00 00 00
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Page 6 of 8
CITY OF FORT WORTH SOUTHLAND TERRACE ADDITION LOT 3, BLOCK 4-R
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS PROJECT NO. 103651
Revised March 20, 2020
32 16 13 Concrete Curb and Gutters and Valley Gutters 10/05/2016
32 17 23 Pavement Markings 11/22/2013
32 17 25 Curb Address Painting 11/04/2013
32 31 13 Chain Fences and Gates 12/20/2012
32 31 26 Wire Fences and Gates 12/20/2012
32 31 29 Wood Fences and Gates 12/20/2012
32 32 13 Cast in Place Concrete Retaining Walls
06/05/2018
32 91 19 Topsoil Placement and Finishing of Parkways 12/20/2012
32 92 13 Hydro Mulching, Seeding, and Sodding
12/20/2012
32 93 43 Trees and Shrubs 12/20/2012
Division 33 - Utilities
33 01 30 Sewer and Manhole Testing 12/20/2012
33 01 31 Closed Circuit Television (CCTV) Inspection 03/03/2016
33 03 10 Bypass Pumping of Existing Sewer Systems 12/20/2012
33 04 10 Joint Bonding and Electrical Isolation 12/20/2012
33 04 11 Corrosion Control Test Stations 12/20/2012
33 04 12 Magnesium Anode Cathodic Protection System 12/20/2012
33 04 30 Temporary Water Services 07/01/2011
33 04 40 Cleaning and Acceptance Testing of Water Mains 02/06/2013
33 04 50 Cleaning of Sewer Mains 12/20/2012
33 05 10 Utility Trench Excavation, Embedment, and Backfill 12/12/2016
33 05 12 Water Line Lowering 12/20/2012
33 05 13 Frame, Cover and Grade Rings Cast Iron 01/22/2016
33 05 13.10 Frame, Cover and Grade Rings Composite 01/22/2016
33 05 14 Adjusting Manholes, Inlets, Valve Boxes, and Other Structures to
Grade 12/20/2012
33 05 16 Concrete Water Vaults 12/20/2012
33 05 17 Concrete Collars 12/20/2012
33 05 20 Auger Boring 12/20/2012
33 05 21 Tunnel Liner Plate 12/20/2012
33 05 22 Steel Casing Pipe 12/20/2012
33 05 23 Hand Tunneling 12/20/2012
33 05 24 Installation of Carrier Pipe in Casing or Tunnel Liner Plate 06/19/2013
33 05 26 Utility Markers/Locators 12/20/2012
33 05 30 Location of Existing Utilities 12/20/2012
33 11 05 Bolts, Nuts, and Gaskets 12/20/2012
33 11 10 Ductile Iron Pipe 12/20/2012
33 11 11 Ductile Iron Fittings 12/20/2012
33 11 12 Polyvinyl Chloride (PVC) Pressure Pipe 11/16/2018
33 11 13 Concrete Pressure Pipe, Bar Wrapped, Steel Cylinder Type 12/20/2012
33 11 14 Buried Steel Pipe and Fittings 12/20/2012
33 12 10 Water Services 1-inch to 2-inch 02/14/2017
33 12 11 Large Water Meters 12/20/2012
33 12 20 Resilient Seated Gate Valve 12/20/2012
33 12 21 AWWA Rubber Seated Butterfly Valves 12/20/2012
33 12 25 Connection to Existing Water Mains 02/06/2013
33 12 30 Combination Air Valve Assemblies for Potable Water Systems 12/20/2012
33 12 40 Fire Hydrants 01/03/2014
00 00 00
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Page 7 of 8
CITY OF FORT WORTH SOUTHLAND TERRACE ADDITION LOT 3, BLOCK 4-R
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS PROJECT NO. 103651
Revised March 20, 2020
33 12 50 Water Sample Stations 12/20/2012
33 12 60 Standard Blow off Valve Assembly
06/19/2013
33 31 12 Cured in Place Pipe (CIPP) 12/20/2012
33 31 13 Fiberglass Reinforced Pipe for Gravity Sanitary Sewers 12/20/2012
33 31 15 High Density Polyethylene (HDPE) Pipe for Sanitary Sewer 12/20/2012
33 31 20 Polyvinyl Chloride (PVC) Gravity Sanitary Sewer Pipe 06/19/2013
33 31 21 Polyvinyl Chloride (PVC) Closed Profile Gravity Sanitary Sewer
Pipe 12/20/2012
33 31 22 Sanitary Sewer Slip Lining 12/20/2012
33 31 23 Sanitary Sewer Pipe Enlargement 12/20/2012
33 31 50 Sanitary Sewer Service Connections and Service Line 04/26/2013
33 31 70 Combination Air Valve for Sanitary Sewer Force Mains 12/20/2012
33 39 10 Cast in Place Concrete Manholes 12/20/2012
33 39 20 Precast Concrete Manholes 12/20/2012
33 39 30 Fiberglass Manholes 12/20/2012
33 39 40 Wastewater Access Chamber (WAC) 12/20/2012
33 39 60 Epoxy Liners for Sanitary Sewer Structures 12/20/2012
33 41 10 Reinforced Concrete Storm Sewer Pipe/Culverts 07/01/2011
33 41 11 High Density Polyethylene (HDPE) Pipe for Storm Drain 12/20/2012
33 41 12 Reinforced Polyethlene (SRPE) Pipe 11/13/2015
33 46 00 Subdrainage 12/20/2012
33 46 01 Slotted Storm Drains 07/01/2011
33 46 02 Trench Drains 07/01/2011
33 49 10 Cast in Place Manholes and Junction Boxes
12/20/2012
33 49 20 Curb and Drop Inlets 12/20/2012
33 49 40 Storm Drainage Headwalls and Wingwalls 07/01/2011
Division 34 - Transportation
34 41 10 Traffic Signals 10/12/2015
34 41 10.01 Attachment A Controller Cabinet 12/18/2015
34 41 10.02 Attachment B Controller Specification 02/2012
34 41 10.03 Attachment C Software Specification 01/2012
34 41 11 Temporary Traffic Signals 11/22/2013
34 41 13 Removing Traffic Signals 12/20/2012
34 41 15 Rectangular Rapid Flashing Beacon 11/22/2013
34 41 16 Pedestrian Hybrid Signal 11/22/2013
34 41 20 Roadway Illumination Assemblies 12/20/2012
34 41 20.01 Arterial LED Roadway Luminaires 06/15/2015
34 41 20.02 Freeway LED Roadway Luminaires 06/15/2015
34 41 20.03 Residential LED Roadway Luminaires 06/15/2015
34 41 30 Aluminum Signs 11/12/2013
34 41 50 Single Mode Fiber Optic Cable
02/26/2016
34 71 13 Traffic Control 11/22/2013
00 00 00
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Page 8 of 8
CITY OF FORT WORTH SOUTHLAND TERRACE ADDITION LOT 3, BLOCK 4-R
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS PROJECT NO. 103651
Revised March 20, 2020
Appendix
GC-4.02 Subsurface and Physical Conditions
GC-4.04 Underground Facilities
GC-6.09 Permits and Utilities
GR-01 60 00 Product Requirements
END OF SECTION
00 42 43
DAP - BID PROPOSAL
Page 1 of 7
1 3312.0117 Connection to Existing 4"-12" Water Main 33 12 25 EA 1 $800.00 $800.00
2 3311.0261 8" PVC Water Pipe 33 11 12 LF 468 $52.00 $24,336.00
3 3311.0161 6" PVC Water Pipe 33 11 12 LF 8 $36.00 $288.00
4 3312.3003 8" Gate Valve 33 12 20 EA 5 $2,575.00 $12,875.00
5 3312.2203 2" Water Service 33 12 10 EA 1 $2,800.00 $2,800.00
6 3312.2003 1" Water Service 33 12 10 EA 1 $2,400.00 $2,400.00
7 3311.0001 Ductile Iron Water Fittings w/ Restraint 33 11 11 TON 1 $2,500.00 $2,500.00
8 3312.0001 Fire Hydrant 33 12 40 EA 1 $4,100.00 $4,100.00
9 3305.0109 Trench Safety 33 05 10 LF 480 $2.50 $1,200.00
10 3471.0001 Traffic Control 34 71 13 MO 1 $2,000.00 $2,000.00
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
Bidlist Item
No
UNIT I: WATER IMPROVEMENTS
SECTION 00 42 43
Developer Awarded Projects - PROPOSAL FORM
Bidder's Proposal
Description
TOTAL UNIT I: WATER IMPROVEMENTS $53,299.00
Bid
Quantity Unit Price Bid Value
Project Item Information
UNIT PRICE BID Bidder's Application
Specification
Section No
Unit of
Measure
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS
Form Version May 22, 2019 ResourcesP_30 - New Development Resources_Specs and Contract Documents_00 42 43_Bid Proposal_DAP
00 42 43
DAP - BID PROPOSAL
Page 2 of 7
Bidlist Item
No
SECTION 00 42 43
Developer Awarded Projects - PROPOSAL FORM
Bidder's Proposal
Description Bid
Quantity Unit Price Bid Value
Project Item Information
UNIT PRICE BID Bidder's Application
Specification
Section No
Unit of
Measure
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
UNIT II: SANITARY SEWER IMPROVEMENTS
TOTAL UNIT II: SANITARY SEWER IMPROVEMENTS
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS
Form Version May 22, 2019 ResourcesP_30 - New Development Resources_Specs and Contract Documents_00 42 43_Bid Proposal_DAP
00 42 43
DAP - BID PROPOSAL
Page 3 of 7
Bidlist Item
No
SECTION 00 42 43
Developer Awarded Projects - PROPOSAL FORM
Bidder's Proposal
Description Bid
Quantity Unit Price Bid Value
Project Item Information
UNIT PRICE BID Bidder's Application
Specification
Section No
Unit of
Measure
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
UNIT III: DRAINAGE IMPROVEMENTS
TOTAL UNIT III: DRAINAGE IMPROVEMENTS
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS
Form Version May 22, 2019 ResourcesP_30 - New Development Resources_Specs and Contract Documents_00 42 43_Bid Proposal_DAP
00 42 43
DAP - BID PROPOSAL
Page 4 of 7
Bidlist Item
No
SECTION 00 42 43
Developer Awarded Projects - PROPOSAL FORM
Bidder's Proposal
Description Bid
Quantity Unit Price Bid Value
Project Item Information
UNIT PRICE BID Bidder's Application
Specification
Section No
Unit of
Measure
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
UNIT IV: PAVING IMPROVEMENTS
TOTAL UNIT IV: PAVING IMPROVEMENTS
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS
Form Version May 22, 2019 ResourcesP_30 - New Development Resources_Specs and Contract Documents_00 42 43_Bid Proposal_DAP
00 42 43
DAP - BID PROPOSAL
Page 5 of 7
Bidlist Item
No
SECTION 00 42 43
Developer Awarded Projects - PROPOSAL FORM
Bidder's Proposal
Description Bid
Quantity Unit Price Bid Value
Project Item Information
UNIT PRICE BID Bidder's Application
Specification
Section No
Unit of
Measure
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
UNIT V: STREET LIGHTING IMPROVEMENTS
TOTAL UNIT V: STREET LIGHTING IMPROVEMENTS
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS
Form Version May 22, 2019 ResourcesP_30 - New Development Resources_Specs and Contract Documents_00 42 43_Bid Proposal_DAP
00 42 43
DAP - BID PROPOSAL
Page 6 of 7
Bidlist Item
No
SECTION 00 42 43
Developer Awarded Projects - PROPOSAL FORM
Bidder's Proposal
Description Bid
Quantity Unit Price Bid Value
Project Item Information
UNIT PRICE BID Bidder's Application
Specification
Section No
Unit of
Measure
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
TOTAL UNIT VI: TRAFFIC SIGNAL IMPROVEMENTS
UNIT VI: TRAFFIC SIGNAL IMPROVEMENTS
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS
Form Version May 22, 2019 ResourcesP_30 - New Development Resources_Specs and Contract Documents_00 42 43_Bid Proposal_DAP
G64:di
fiAP - 810 PRi1p(1SAI.
Pagc i �f 7
�._ s��r�r�N aa a2 aa --- --_-- _
�aVoloper Awarded Prpjects - PROPOSAt FORIVI
UNIT PR1GE BlD
Pm�c�s lirm infi�rniation
h6i isam
Nn
l�exn�iirm
B�dder`s Appltcation
$iddetc �rOpc�cal
sp«:irKatinn urut or sd
LJmt Price Bid VaEuG
Seciion No Mca�urc f)urntny
Sid Summary
UNIT I: WAT�R IMPfiOVElNENTS
UNIT fl; SAN{7ARY SEWER iMPiiOVENlENTS
UiVIT 11l: QRA4NAGE iNiPRQVE1N�iJ7S
UNIT IV: PAVITJG IMPF2DV�MEIJTS
L1NIT V: STREET L{GHTING INfPRQVEMEN75
UNlT V!: FRAFFiC SIGMP� IMPRpVENt�NTS
To�txl Comeruction
7'his Bkd Is au6mitled 6y tLe rntfty n�ned beiow;
flIDUEfi:
CO]'�ii'RF:iF: & STk;E1,57iiU['TLIRFS. Lf.0
7�9 WYCIik C'i".
su�.esn:r, rx �6xa
Cootnetar agrrrti ta compleer WURI{ far F!.'VAL ACCEPTAM10E wilEiin
COhTRACT� commrncrs [o ruo �: pror[drd ln 1he Genrral Conditloua�
SY:
TITL,£: � ,'j �''
°"'�: q 1 a� a�� r
15 world� days aftrr thr dstr wheu tLe
Ei p pF 5£Ct'[Pti
C tTY 11F FitRT 1L'I1RTii
57 A V E�.i k 6 C[ltiSTit l:C� tC]y SPFC'IF IC�AT I[}*� Cx]C7'x[Eh7S - hE�'ELU3'LR .� W:ARDF p pRly1E[TS
Fwm Vmrm \i.y. „ 2019 ResowcraP_H1- Nrw qerdn�mer! Reyc.eercrs_.�a aed Cwtrr.�t Do�womu_9Ri' d.] B�d ►mpw�_DAP
��
ix� s� i:
s�nr rkt.[lUnt.IFlc'nl t[�N STA'Cl��ll y S
Pa�;c 1 a f !
SECTIQN 00 4S � 2
DAP — !'REQUALIFICATIQN STATEM�NT
Eacti Bidder is required to �omplctc tltie information bc�law �iy idcntifyin�; the �requalifi�d cantr�ctors
andlor subcvt�tractors whom tiiey intend ta utiii�e tar the r�yajar work type(s) listed, in tt�4"Ly.�iar Work
Ty�7e" hna� rovidc the c�n1 lete ma'or wark e and actuAl descri tion s m�ided U tlte Water
Departiltent f�r �vater and se�ver anci TPW for �avine•
Major Work Type
Wastew�ter M�i��s ($" nnly) far
Ne��� De�clnpn��nt using Upen
C�t 1�lettiads
Water Mai�is tK" only} Far New
�e��elopment usin}; Open Cut
Methods
ContractarlSuhcoi�trnctQr CompAny Nam�
�ancrrtc �C Stccl S[ructures, i.LC
Concretc & Stccl Stru�tures, [.I.0
Pr�qualificalinn
Ex iratioii ❑ntL
kar� V2az2
i o�a i�zazz
T'h� undcrsi��neci hereby certities that the contractors �ndlor subcontractors dcs�ribed in tl�e tablc aba�c
Are curret�tly prequalified fqr ihe work types iistcd,
BIDDER:
Concretc � Sicel Structures, LLC
704 Wy�he �Ct.
Burieson, TX 75a28
HY:
[Si�naEurc)
TITI.�:: � rL51[��ry�
oA�r�: �� ��'� i��' � 1
E�va o� sEcTrarr
Glir OF FQRT W�RiH
STANDRRO C�NS7RLICilON PRfql1AUFICAiIflN STAIEMEN7 - I7fVELaPER AWAROEO PROlECi5
�ocumenSs QQi512_Prpqualifitativn5tatement
20t5 DAP �
Form Version Septem6er 1, 2�15
RrsourcesP 30 - New 6evetopment Resourccs Spres snd Con[rac[
_ "-�wa�uC ir H.
00 45 26 - I
CC}N?RACTUR C�MPi.IAiYCI: W[�'}4 WdR�fER'S C'dN[PI:NSAT[QN LAW
T'agc I ❑f }
SECTIQN 4U 45 Z6
CONTRACTOR C�M��.IANCE WITH WQ�KER'S COMPF.NSATI(7N �AW
Pursuani ta Texas i.abor Cadc Section 4D6.09fi{a}, as amended, Contractor certifes that it
prnvides worker's compensation insurance caverage for ajl af its cmplayees empfayed on City
Pr�ject No. 14365 �. Cantractor further certifies that, �ursuant to Texas Labor �nde, Section
406.Qg6{b}, as amendcd, it wiFl prn�ide t� L'ity its subcontractvr's certi�cates of comptian�e with
��nrker's campensatian co�erage.
ca�vT�cTaR:
,
Q.. � � By: �
Campany {Pleasc Print)
� Si ature:�
� �,�.---�—
Adclress
� ( �s � T;t��: i�l � �`
iry StatelZip [ tf:ase Print)
THE STA`fE OF TEXAS
COUNTY Q�' TARit.ANT
_ ��
'� ' a
�� .
`�/ •
�.
BEFORE ME, the undersigned authority, an this day persvnalIy ap�eared
, kr�ow-n to me to be the �erson whose name is
subscribed to the foregoin� instrument, an� ackn�wEedged to me that helshe executed the same as
tt�e a�t and deed af f�r the purposes and
cansideration therein expressed and in the �apacity therein stated.
GI EN UND�R,`MY HAND AN❑ SEAL dF OFFICE this day of
�U[- � , �4 �
R
Notary blic in and for th tate of Texas
ENII �F 6ECTI�N
CfTY �F FORT W03iT�[ 54L'THLAND TERR.4CE AOD1T€V?� LdT 3. BWCK �i-R
STANI}ARD C��tSTRL�CTID:` SPEC�'ICATiOh L7DCLIM�!�'i5 C'!Ti"PRDJEC'TI�fJ. ff:3hsf
Re�Fsed .�prsi �. ?a1-1
J
OQ5243-1
L]c�eloper Awarded Project Agreen�ent
Pagc 1 of 4
SECTIUN DU 5� 43
AGRE�MENT
THCS AGREEMENT, autharized on Dece_mber 5, 2021 is made by and between the
Developer, T. HICKS GP, iNC., authorized ta do business in Texas {"�e�eloper"}, and
C�NCRFTE_& STEEL STRUCTURES, LLC , a�thvrized to do business in
Texas, a�ting by and through its duly authorized representati�e, t"Contractor"}.
Dc�eloper and �ontractor, in consideration of the mut��.al co�enants hereinafrer set forth, agree as
fo��ows:
Articie 1, WqRK
Contractor shall complete all Work as speci�ed or indicated in the Cor�tract Documents fvr the
�raject identified herein.
Articie 2. PRO��CT
The project for which the Wark under the Contxact Docutnents may be the whole ar only a part is
generally described as follows:
S�UTHLAND TERRACE ADDITI�N, �.QT 3 BLOCK 4-R
CITY PRD7ECT N�. 143f�5I
Article 3. C�NTRACT TiME
3.1 Tizsze is of the essen�e.
All time lirnits for Milestox�es, if any, and Final Acceptance as stated in the �ontract
Docuznents are of thc cssen�c to this Contract.
3.2 Final Acceptance.
The Work will be complete for Finai Acceptance wiihin 45 warkir�g days after the date
when the Cantract Titne commences to run as pro��ded in Paragraph 12.�4 of the Staz�dard
City Conditior�s of the Constru�tion CQntra�t far De�eloper Awarded �'ro}ects.
3.3 Liyuidated dama�es
Cantractor recogni�es ihat time is pf the essence of tliis Agree�nent and that De��loper
will suffer financiat loss if the Wark is not completed wiil�in the tiznes speci�ied in
Paragraph 3.2 abo�e, plus any extensian thereof allowed in accardance with Arti�ie 1g of
thc 5iandard City Conditions af the Canstr�ction Contract for Dc�eIaper Awarded
Projeccs. The Contractor aiso re�ogniaes the delays, expense and difficufties inWol�ed in
pro�ing in a iegal proceeding the actual lnss suffered by the De�eloper if the Work is nat
cotnp�eted an time. Accardingly, instead af requi��ing any such proof , Contractor agrees
that as liq�idated damages 1Far delay (but not as a penalty}, Cantra�tor shall pay
De�eloper �'IVE H[]NflRED T.]ollars ($500.00} far each day that expires after the time
specsfied in Paragraph 3.2 for Final Acceptaz�ce until the Cit}+ issues the Final Letter of
AcCeptance.
C1TY dF F�HT WORTH SOIITHLANIJ 7'FRHRCE�IDflfTIO?�; LOT 3, BLOCK 4-R
STANL]ARi] CC?N5'I RUC I'1C}N SPECiI-"ICA�'IC}IV C]C]CI;�fElVTS — T]�.VELQPF.€t AWARfJED PR�fECTS CITYf'ROJEC7"NQ, IU3GSI
Rcvised Sune 16,261fi
flU5243-2
I7e�eioper Awarded Praject Agreement
1'age 2 of 4
Article 4. CONTRACT PRICE
Developer agrees ta pay Contractor for performance af the Wark in accordance with the Contract
Dacuments an amvunt in current funds of Fifty—Three Thousanc� Two H�ndred Ninety-Ni�e
Dollars and D01144 Doliars {$53 234.D0 )�
Article 5. CONTRACT D�CllMENTS
5.1 �DNTENT�;
A. The Cantract Documents whick� comprise the entire agreernent between De�eic�per and
Contractor concerning the Work consist of the follvwing;
l. This Agreennent.
2. Atta�hments ta this Agreement:
a. Sid Farm [As pra�ided by De�eloper)
1) Propasal FQrm (DAP Version}
2) Prequalification Statement
3} State and Federa� docurnents {praject specrfic)
b. Insurance AC�RT1 Form(s)
c. Payment Bond (DAP Version}
d. Performance Bond (�AP Version}
e. Mainienance B�nd tDAP Version)
f. Pawer af ATtorney for the B�nds
g. Worker's Cartxpensarion Affida�i#
h. MBE andlor SBE Coznmitment Form (If required}
3. Standarcl Gity General Conditions af the Constru�tion Contract far Ueveloper
Awarded Projects,
4. 5upplemeniary Conditions.
5. Speci��atians spec�fical]y rnade a part of the Contrac# �ocurr�er�ts by attachment
or, if not a#ta�h�d, as incorporated by referer�ce and described in the Table of
Cantents af the Praject's CQntra�t Documents.
b. Drawings.
7. Addenda.
8. Dacumentation sul�mitted t�y Contractor prior tv �iotice of Award.
9. The followtng which may t�e deli�ered or issued after the Effecti ve Date ❑f the
Agreement and, if issued, beGome an incorporated par� of t}�e Contract Documerits:
a. Natice to Pro�eed.
b. Field �rders.
c. Change Orders.
d. Letter of Final Acceptance.
CIFY QF FQkT WORTH SC7UTHLANIJ 7ERR�tCF.dI]DITlOh; LCJT3, &L�CK4-R
STAN�ARI] CC]NSFRLICTIOTI 5�'ECIF3CA'I'IUI4 DQCliNfENTS— L7EV�LOPER AWARI3ED PRplF.:CTS CITYPRDJECTNp, IU355]
Rc�•iscd 7une i G, 2U16
oosz43-3
De�cloper Awarded Projee� Agreement
i'age 3 ai4
Article C.INDEMNiFICATIDN
5.1 Contractar �v�enants and agrees to indemnify, hold harmless and defend, at 'tts own
cxpense, ihe c'tty, its o[ficers, ser�ants and emptnyees, fram and agsinst any and all
cla�ms arising out of, nr alleged to arise nut o% t�e work and sei-viees to be gerformed
by the eontractor, its o�cers, agents, employees, s�bcantractors, licenses or in►°'ttees
u�der this cantract. This. indemni�cation �ru��sio� is SUecif�callV intended tn uUerate
and be_effecti�e e�en if it is alleged ar pro�en that all or sa�ne af the damages heing
sou�ht were caused, in whole Qr in part. bv ar�v act, omissinn or ne�li�ence of the citY.
This indemnity provision is intended to incIudc, withnut limitatian, indemnity for
costs, expenses a�d Iegal fees ineurrec� by the city in de%nding agairtst such claims and
causes af actions.
6.2 Contractor ca�enants and agrees to indemnify and hatd harmless, at its own expense,
the city, its vfficers, serr+ants and employees, fror� and a�ainst a�y and ali luss, damage
nr destruetian Qf prvperty of the city, arising out af, or alleged to arise out of, the work
and ser��ees to be perfarmed by the contractor, its offieers, agents, ernployees,
suk►cantractors, licensees or in�itees e��der this contract. This i�de�nnifcat'rnn
rp�ision is speci _fically intended ta oqerate a�nd �e effecti�e e�en if 'rt„ is alie�ed or
rp OV�r� that all or_some vf the damages, heing sau�ht were caused, in whole or 'rn part,
b an act omission or ne li enee of the ci .
Article 7. MZSCELLANEaUS
7.1 Tcrms.
Tea-ms used in this Agreemez�t arc de�ned in Arti��e I of the Standard City Canditions of
the Construction Contract for Developer Awarded Projects.
7.2 Ass#gnment of Contract.
This llgreement, inc�uding all af the Cantract Documents may not 6e assigncd by the
C:ontractor wiEhout the ad�anced express written consent vf the De�elaper.
7.3 5u��essars and Assigns.
De�eIQper and Contcactor each binds itself, its partners, su�cessors, assigns and legal
repres�ntatives to the other party hereto, in respect to all co�enar�ts, agreements and
obligations cotitained in the Cantract Dacuments.
7.4 Severability.
Any pro�ision nr part ❑f ttze Contract Documents heid to be unconstitutionai, void or
unenfarcea.lale by a court of competent jurisdi�tion shalI be deeined stricken, and all
remaining pro�isions shall cantinue to l�e �alid and hinc�ing upon DEVELQPFR and
CdNTRACTDR,
7.5 Go�erning Law and Ver�ue.
This Agreernent, including all af the Contract Documents is perforn�able zn the State of
Texas. Venue shalt be Tarrant County, Texas, ar the Uni#ed States District Caurt far the
Northern District af Texas, Fort Warth Di�ision,
CITY pF FORT WpRTFI SOUTHL.4A�I3 TFRR�3CEADUITIpA�; LpT 3, SLOCI� d-R
STA]VDARD C{}h�5'I'RUCTIUN SP�CIFICATI014 DpCi�MEIVI'S — DEViLQPER AWAR�][-:17 PRaJECTS CYTYPR�JECTNp, IU3GSI
Re�ised 7une 16, 2f}] 6
��_:- - �
nosxa3-a
a��eloper Awnrdcd Projcet Agrcemen�
Faga 4 af 4
'T,G Authority tv Sign.
Cai�t�-actar sha11 att�ch evidence of aut�yority ta sign Agreement, if other than duly
a�itharizcd si�i�ntory tif the Cantractor,
IN WfTN�SS WH�REaF, Developer ai�d CQntractar l7ave executed #h'ss Agreement in multi�ie
�auntcrpnrls.
This ��reeil�ent is cffecti�e as af fh� ias[ datc sig�i�d i�y tf�e Parfies ("Effective Date"}.
C�nt ctnr: , Developer:
�Cl �'_ �' �.�-'�.�'�. �� �..�T��-�ul'�5 �i'• L�i c � c,
� � .�_ : _ , ��� , �
5ignature) �5ignatuxe} �
. �
/. � 1 .
{Printed NamC)
T�t��; t" � e 1f:1
Comp�tny I�iaine:
Address: �j� Q E
�" t c. � G P� G
l~vm L G �
(Pri�ltcc3 Nan1�}
�r��; d�.n`F-
+oii Cf^�^=� �� k ��C.ar�Any name:
A.ddress: C�Qsf- 5�,nti� �Q_ �y L�L
���� L L �r � r ��.��t .
,. � � S o
Ci�atel�ip: --- — —
J� � �
Date
CitylStatel�ip: - - - �
izl�lzozi
�DRte T r - - -- ..._..�.�.
CIT'f Qi FOR7lVDR'I"H S(J[If7I1..4ND T6Hk�ICE:tOAITI�h; LQT 3, &LUCI: 4-R
5TAi�fURR(] C'CJ3�STRUC,"Ti�N SPFCiFICATIC]N OOCUMGNiS - L]�VELaPER AWAfLaED PHOSEC"I'S C!T}'PkC7JEC'TA'0. 10365!
kavuecl It�nr l6, ?[} t 6
SiA� 7s � :sa,+.-:.'d+'
Bond No. 4450791
006213-]
PESiFflRhfAhC� BC}�fq
Pagc I of 3
s�crro�t oo �z �3
P�RFORIVIA3VCE �ONn
THE 5'TATE �F' TEXAS �
§ KNQ1�V ALL BY THES� PItESENTS:
COIJNTY QF TAItRA.NT §
T11at we, Concrete & Steel Structures, LLC , knoWn as
"PrinGipa�" herein and SureTec Ins�rance Company , a coi�Of'dte
surety{sureties, i�'more ihan ane} duly autharized to do business in the State of Tex�s, k�aozvn as
"Surety" hcrcin (whether one or rr�ore}, are held and firmly bound unto thc Develnper, `d'. H1CKS
GP, INC., authorized to do business in Texas ("De�cloper') and the City of F�rt Wortb, a Texas
rn�unicipal corporatian ("City"), in the gei�al sum of,
Fifty-Three Thousand Two Hundred Ninety-Nine �ollars and OOJ100 �Q��ar� �� 53,299.00-------------------------- �
�
lawfvI mancy of the United States, to be paid in �ert W orti�, TarranE Coun[y, Tcxas %r the
payrr►ent of whick� sum well and txuly to be �nade jointly untn the Devclo}�er and the Ciry as dual
obligecs, wc bind otirselyes, our Iteirs, executors, administr��tc�rs, suceessars and assigns, jointly
and severally, frmly by these presents.
WH�REAS, Developer and City ha�e eniered into an Agrecrrient Far thc construction of
carnmut�ity faeilities in t3te City of Fort Warth by and through a Comrt�un�ty Facilities
A�reemcnE, C�'A Number ;anci
WHEREAS, the Principa] has c�stered into a ccrtain writtcn cvntract with ihe Dcveioper awarded
the � day of..��e�. , 20 Z� , which Contracl is herel�y re€err�d tu and madc a
part hereof for all purposes as if fully set forth herein, ta furnisit all materials, equipment labor
and oti�er accessories de�ned by [aw, in khe prasecution of the Wark, tncluditt� a�y Change
Orders, as provided for in said Contract designated as SOi:�'HLAND i�IiRAC� ADDITION,
LOi 3, BLOCK 4-R.
NOW, THEREF�RE, the eondition ofthis ohligatior� is such tlsat ii'thc said Frincipal
shall faithfully perform it obli�atio��s �uider the Cantract a�d shall in all respccts du[y and
faithfully perform tE�e Work, includ�nb Change Orders, undar the Contract, �ccording to the plans,
specifications, and con�act documcnts therein referred tc�, and as we1Y during any period of
extension of tlie Contract that may 6e granted on thc part of the DcvcIoper antllor City, then this
obligation shall �e and becamc nul� and �oid, otherwise to remain in full Forcc anci effect.
Cf1�Y OF FpR'I' VVC3RTEf SQUTNLIlA'D 1 ERlt•iCF.' �1 DDI770A` LOT 3, BLQCR 4-!t
SiANDAF�L7 CCrY COIDIT10�1S — Dh'1'T:I.Ui�fiEt AIVARDE� PR�1F:C`!'S CliYFRDJEC7'NO. i036S!
Revised January 3 l, 2012
Band I�o. 4450791
oa sz i3 - �
rr:�Fa�.��.�c� nou�
�,e� z of s
PROVIDED FURTHCR, t�at if any legal acfion 6e fi[ed on this Baad, venue shall Iic in
Tarrant Counfy, Texas or thc Unitec� 5tates District Court for thc Northem District ofTexas, I'ori
Warth Division.
This bond is rnadc and cxecvtad in compliancc with the pravisions of Chapter 2253 af the
Texas Gowcrnmcnt Codc, as amcnded, and all liabi�ities on this bond shall be determined in
accordance with the pravisiflns af said statue.
IN W1TNE5S WH�R�UF, t3�e Prinetpal and Ehe Surety have SIGN�� and SEALED
this instr�trr2er�t by duly autf�orizcd ag�nts and offaccrs an this t�te �e �' day of
.2c:4'.w�(�►� , 2� 2�,.
A'fTEST:
�� .�����
(Prineipnl} Secretary
���n G �n m ez�� _
Witn�ss as to PrincipaI
PRINCIPA L:
Concrete & Steef Structures, LLC
BY: � �� �d�Y
Signaturc
p< < �� -
Narne and Tit3e
Address: 947 E Renfrost
Burleson, TX 76028
SURETY:
SureTec Insurance Company
BY:
5i�ttature �
Elena Sells, Attomey-In-Fact
I�famc �nd i'itle � �
�
W3Enes5 35 to Surety 5te� W. Lewis
Address: zJ.D3 CityWest Blvd., Suite 130�
Houstan, TX 77042
Telephone �lum6er: (713} 812-OBoo �
*Note: lf si�;ned by an of#iccr of the Surety Company, there rnusl bc on filc a certif€ed extr�cE
from the by-laws showing that this �erson has authority to sign slich obligation. lf
Surety's physica3 address is different frosn its mailing adc3ress, bath �nust be pro�ided.
CITY 6t' FUR7' W�OK7'H S4Lr'7'FII..�NlJ T�F.�RXACEAJJDITIONL07'3. BLUCK4-R
SFANUARU CITY CO�IDIT10N3 - L}fiVEIAPER AWARDF.Q ['RU71iC7'S CITYPRUJ�C7'N� lf13651
Revised Juauery 3l, �012
Bond No.4450791
oosz�3-3
i'E€tFOli��itA1�CE B04D
Paec 3 of 3
T'�e date af thc bond st3ail not hc priorto the date thc Cdntract is ativardcd.
C[7�5' OF FORT WQRTH 5U(r7lff.rf�'VD 7'�'RRACf: ADDITIONiOT 3, BLOCK d-H
S'CANaAftD CI'i'Y CO�DTT14.+15 - L3EV�LL?PI:R A�ARD£D PRQ,IECJ'S CITYPROJECTeVCJ. 103651
Rcvisec� January 31, 20E2
Bond No. 4450791
006214-1
PAYMENT IIOND
Page 1 0£2
SECTION 4i! b2 14
i'AYMENT B�ND
THE STATE OF TEXAS �
§ KNOW ALL BY THESE PRESENTS:
COUNTY QF TARCtANT §
That we, Concrete & Steel 5tructures, LLc ,�lpwn a5
"Pi'inClpaX" �7erei�, c't�1d SureTec Insurance
a
corporate surety ( or sureties if more tF�an ane), duly autharized ta do business iu tk�e Statc o�
Texas, lcnown as "Surety" herein (whether ane or more}, are held and firmly bouxld unto ti�c
De�elaper, T. HICKS GP, II�IC., authorized ta do bus[ness in Texas "(Dcveloper"), and t�e City
of Fort Worth, a Texas municipal corporation ("City"), in the pena! sum
p� Fifty-�hree Thnusand Twn Hundred Ninety-Nine �ollars and OQ/100 j]p1�aT5 {� 53,299.00--------------------------
�
fawful money of the United Staies, to be paid in Fort Worth, �'arrant County, Texas, for the
payment nf which sum weil and truly be made jointly unto the Develaper a.r►d the City as dual
p�ilgeCS, we bind ourselves, our �teirs, executars, administrators, successors and assi�s, jointly
an�i severaliy, frmiy by ihese presents:
WHEREAS, Develo�cr and City have entered into an Agree�nent for the canstruction of
eommunity facilztics in t3�e City of Fort Warth, 6y and thcaugh a Community �acilitfes
A�reement, CFA Num�er ;and
WHEREAS, Principal has entered i�fa a certain written Corzt�act wi#h I?eveloper,
awarded the �day of �� c� •►1. b e� �, 20 Z( , which Cantract is hereby
referred to and made a part hereof for all purpases as if fulty set forth herein, to fus�ish all
T11AtCCk�ISy equipment, �abor and ather accessaries as defined by law, in thc prvsecution of the
Work as provided far in said Cantrack and desagnated as SOUTHLAND TEAR4CE ADDITION,
LOT' 3, BLOCK 4-R.
NO'W> THERE�'�RE, THE CQNDITION OF THfS OBLIGATION I5 such fhat i€
Principal shall pay aII manies owing to any (and all} payment bond beneficiary (as defined in
ChapEer 2253 of thc Tcxas Gavernrnent Code, as amended) in the prosecutian of the Work under
the Contract, then this obligation shal[ be and bec:ome nv[1 and void; otherwise to remain in fnil
force and effect.
C1TY OF FOitT WORTH SOUTHL�1 ND TERR.3CE ADDITION, LOT 3, BLOCK 4-R
STANdAIZD C1TY CDND I7'ifl�15 — DS VELC?PLR AWART3E(3 P[20JECTS C1TY PROJECT N0. I�3651
Re�ised Jenaary 31, 2012
Bond No. 4450791
0062 i4-2
PAYl41ENT BQNf]
Page 2 of 2
This bond is macie and cxccutcd in comptiance with thc provisians ofChaptcr Z2�3 of tl�c
Tcxas Government Ca�c, as amcnded, and all liabilities on ihis bond shaIl be determined in
accordance with tite pravisions of said statute.
IN WITNESS WHEREUF, the Prirtcipal and Surety have each SIGNED and SEALED
this instrument by duly autI�orized agcnis and af�ccrs an this thc �r � day of
� G�{��+v , 20 ZI .
FRINCIPAi,:
Concrete & Steel 5tructures, lLC
ATTEST:
.� �.�n l�.�r�r� .
(Prineipal) Se�retary
J -l� 4 � YY1P -zr�
Witness as to Principal
BY: �
Signa re
�i(� r l l��-�Z.�/ � kin�
Namc and Titfc
/�dC�iC55: 947 E Renfrost
Burlesan, TX 75028
STJR�TY:
SureTec Insurance Campany
ATTEST: �Y: _��,
5i�nature
N/A
{Surety} Secreta�y
Witness as ta Surety �te�en W. Lawis
�
Elena Selfs, Attarney-ln-Fact
I�amc and Title
A[id�eSS; z103 CityWest Blvd,, Suite 1300
Houston, TX 77042
Telephone Number: (713j 812-0800
Note: lf signed by an pEficer of tEic Surety, thcre must be an �le a certi�ed extracc frc�m the
bytaws showing th�t Ehis persan has authori#y to sign such obligation. If Surery's physical
adcfress is different from its maifing �ddress, �oth rnust be pravided.
Thc date of the bond shall not 6e prior ta thc datc [hc Cont�-act is awarded.
Et�`D OF SECTIa�i
CfTY OF FORT V4'OlZ7'H SOt1TfIL-I.YD PERRiCF, e�DDITIQ.�Y, i�T 3. BLQCfi 4-R
S'fAItiDA12D C17Y CUNDI'I'I(yY$ - f)i:VEil.41'I:R A1VAi2I)[:U PRQ.fE:CI'S CITYPRQJ6CTNp, IQ3bS1
Reviscd Januasy 31, 2�I2
Bondf�o.4450791
006219-1
MAINTL•IVAItfCL' 1301VD
Page 1 af 3
SECT1aN �Q 62 19
MAINTENANCE BOND
THE STA'�'E 4F TEXAS §
§ K1�IOW ALL BY THES� PRESE�TS:
COUNTY ��' TARRANT §
T�lst we Cancrete & 5tee! 5tructures, LLC , known as
"Principal" herein and SureTec Insurance Company , a corporate surety
(sureties, if more than one) duly autharized to da business in the State of `Fexas, known as
"Surety" l�erein (whether ane ar more), are held a.nd firmly baund unto the Developer, T. i�ICI�S
GP, IiVC., authorized ta do business in Texas ("Develaper") and tlze City of Fo�t Worth, a Texas
municipal corporation ("�ll�T"}, lri t�70 SUITl Of Fifty-Three Thousand Twv Hundred Ninety-Nine Do[lars and 00/1D0
Dollars ($ s3,299.00_______________________..__ �, ta�,ful rnoney ofth� CJnited States, to be paid in Fart
Worth, Tarrant County, Texas, for payment of whi�h sum well and truly be made jaintly unto t�c
Deveioper arzc� E3�e City as dual obligees and their successors, we bind aurselves, our heirs,
exe�utors, adEninistrators, successors and assigns, jointly and scverally, f rmly by t�ese presents.
WHEREAS, Developer and Cify �ave entered into as� Agreement for the construction of
coznmunity facilities in the City of Fart �Jorth by and thra�gh a Community Facilities
A�recment, CFA Numbcr ;and
WHER,�A�, the Principal has entered into a certain written contract 4vith the Developer
awarded the �i � day of ��w� Ea � v�_ ._, 2Q 2(, which Contract is
hereby referred to and a made part hereof for all purppses as if fe�ly �et forth herein, io furuish all
materiais, equipment labar and ather accessnries as de�r�ed by law, in the prosecation of the
Work, including any Wark resulting frorza a duly authorized Change Order (�allectively �erein,
EF�e "Work"j as pro�idcd far in said Contract and designated as SOUTHLAND TERRAC�
ADDFTION, LOT 3, SLOCK 4-K; and
WHEREAS, Principal binds itsclf to use such materials and to sa cnnstruct the Work in
accordance with the plans, specifications and Contract Documents tF�at the Work is and will
remai� free from dcfccts in ma#erials vr �varkmanship for and during shc pez�od of two (2) ycars
after the date of Finai Acceptar�ce of tbe Work by the City ("Maintenance Period"); and
CI'I'Y QF FflFtT WO�t'I'H SOU7'HLAND TERRACE AlJD1TlQN, LOT 3, BLpCK 4-R
5Tt1�,�ARD GI'I'Y GaNpITLfl1�S — DEVELQPER AWARDGl7 PROJEGT5 CITYPRLUL�CTND. 103G51
Revised January 31, x412
Band No. 44�0791
oo6z i�-?
MAI.'+f7"F,AfAi�C[: BONt3
Pagc 2 a1' 3
WHEREAS, Principal binds itse�f to repair ar rccanstruct thc Work in �vhole or in part
upon receiving notice fram the DeL�eloper and/ar City of thc nccd tt�ereaf at any tinrie �+ithin the
Maintenance Period_
NOW THERERORE, thc condition af this obligation is sucl� that if 1'rincipal shall
remcdy a�y defective Work, for which timely nnticc wns pravided by De�eloper ar City, to a
compiction satisfactory to chc City, then tt3is obligatian shall become nul] and void; o#hcrwisc to
remain in fufl farce and effect.
PROVIDED, HOWEVER, if Principal shall fail so Ea re�air ar reconstrucE any timely
noticed dc%ctive Work, it is agre�d shat the QeveEaper or City �nay causc any and all such
defective Work to bc regair�d and/or reconstrucEcd with �11 associarcc� costs thcrcofbeing borne
by the Principal and the Sur�ty under ttus MainEcnanc� Bond, and
PROVIDED FURTH�R, that if any Ic�al aciion bc Cled on this Bond, venue shal! lic in
Tarrant Cot�nty, Texas or th,e Unitcd Statcs District Court for t13c Nflrtf�ern Dislri�t of Texas, Fort
Worth Division; and
PROVl�ED FURTHER, itzat this obEigatiqz� shall be conkinuous in naiure and
s�ccessive rccoveries rnay be had hereon for successi�c brcaches.
CITY �F FORT �VORTH SOU7"HLAA`!} TEIilLiC� dI]DITION. GOT 3, BLQCA 4-R
S'1�A�vDAitL1 CiTY CQNDII'[p4S — DF.VELdpEK AWARD�� I'R(1JlsC CS CITYPRQIEGT NO. Il)d55!
Revi�ccl JanuarY 3 i, 2012
Bond No. 4450791
ao6z i�-3
MA1N7'F'NANCL f30ND
Pagc 3 of 3
IN WiTNESS WHEREOF, the Principal and the Surety have cac� SIGNED and S�AL.ED this
instrument by dufy authorir.ed agents and afficcrs on this the �� day of
c¢.Kb$v� , 2�.�.
PRIiVCIE'AL:
Cancrete & Steel 5tructures, LLC
ATTEST:
{Principal) Secretnry
�-� a �, Y� e�zo�.
Witness as tn Principal
ATTEST:
as €v Surety S��en W. Lewis
BY: ` � `"" ��
ignature
� �r�� � ��� o�n�r
iV�me and Title
Afitlr�sS: g47 E Renfrast
Burleson, TX 76�28
5CIRETY:
SureTec lnsurance Company
SY: � _
Si�nature
EIena Sells, Attorney-fn-FacY
P�i�me and TiEle �
Address: 2103 CityWest alvd., Suite 130U
Houston, TX 77042
Teiep}tone d�iumber: (�13) 812-6800
'�Note: if si�ned bj+ an affcer o#'the Surety Company, tharc mt�st be on �le a certifizd extract
from thc by-laws showing that this person ]�as autf►ority to sign such abligatian. Jt'
Surety's �hysfcal address is diffcrent from its rnailin� adcEress, hath rnust bc pro�idcd.
The date of the bond sh�ii not be prior tn thc date the Contract is aw�rdcc3.
CI"f'Y 0� FOR7 LVC}R'rH SOL'77/!_�1 �D T�'RR.1 CF.' f1 DDITlD,Y, LOT j, SLOCti �f-R
S'iANDARfaCITYGaNDIT10�I5 D€VELUPIRAWARULDpRQ1f:C1'S CfTYF1i0J6GTNC1.11J3651
Rcvised lanuary 3 ! , Z01 �
�
SureTec Insurance Company
IMPORTANT NOTICE
Statufory Complaint NoticelFiling of Claims
7o abtain information or make a complaint: You may ca�l the Surety's toll free telephone number for information or io make
a camplaint or file a claim at: 1-866-732-0099. You may also write to the Surety at:
SureTec lnsurance Company
9737 Great Hills Trail, Suite 320
Austin, TX 78759
You may contact the Texas Department of Insurance to obfain infarmation on companies, coverage, rights or complaints
at 1-800-252- 3439. You may write the Texas Departrr�ent of Insurance at:
PO Box 1491 D4
Austin, TX 78714-9104
Fax#: 512-490-1007
Web: http:llwww.tdi.texas.qov
Email: ConsumerProtection@tdi.iexas.go�
-•',
PREMIUM OR CLAIMS DISPUTES: Should yau have a dispute concerning your premium or about a claim, you should
contact the Surety f�rst. ff the dispute is not reso[�ed, you may contact Eh� Texas Departmeni of Insurance.
Texas k2ider 8/2019
POA#: `�2��8��
SureTec Insurance Company
LIMITED POWER OF ATTORNEY
Krrow AII Men by Tltese Presents, That SC3RE7'EC 2NSURANCE COMPANY (the "Company"), a corporation du�y organized and
existing under tE�e laws o£ the State of Texas, and having its principa[ office in Houston, Harris County, Texas, does by these presents
make, constitute and appoint
Kathy Sells, Lanny Land, Ste�en W. Lewis, E�ena 5ells, Jennifer Upton, Paul Fredette
its true and lawful Attorneyan-fact, with full power and authority hereby conferred in its name, place and stead, to execute, acknowledge
and deliver any and at[ bands, recognizances, under�akings or other instruments ar contracts of suretyship to include waivers to the
conditions af contraets anc! consents of surety for, pro�iding the bond penalty does not exceed
Ten Million and 001100 Dollars ($1D,DOO,OD0.00)
and to bind the Company thereby as fully and to the same extent as if such bond were signed by the President, sealed with the corporate
seal of the Company and du]y attested by its Secretary, hereby ratify�ng and canfrming all that the said Attorney-in-Fact may do in the
premises. Said appaintment is made under and by authority of the following resolations of the Board af DirecTors af the SureTec
Insurance Campany:
Be it Resolved, that the President, aay Vice-President, any Assistant Vice-Psesident, any Secretary or any Assistant Secretary shal( be and is
hereby vested with full power and authority to appnint any one or more suitahle persons as Attorney(s)-in-Fact to represent and aci for and on
behalf af the Compaay subject to the fallowing provisions:
.4ttorney-in-Fcrct may be given full power and a�thority for and in the name of and of behalf of the Company, to execute, acknowledge and
deliver, any and aEl bonds, recognizances, contracts, agreements or indemnity and other conditionaI or obligatory undertakings and any and al[
no#ices xnd dac�sments cance[ing or terminating the Company's liability thereunder, and any such instaiments sa executed by any such
. Attomey-in-Fact sha11 be binding �pon the Cor�pany as if signed by the President and sealed and e�ected by the Corporate SecreTary.
Be it Resolved, thaY the signaEure of any authorized ofFicer and seal of the Company heretofore or hereafter affixed to any power of attorney or
any certificate relating thereto by facsimile, and any power of attorney or certificate bearing facsimile signature or facsiraile seal shall be valid
and binding upon the Company wath respect to any bond or undertxlcing to which iT is attached. (,�dopted ad a meeting held on �0'h of �1priF,
1999.)
In Witness Whereof, SURETEC TNSURANCE COMPANY has caused these presents to be signed by its President, ancf its eorporate seai
to be hereto affixed this 3�d day of Mav A.D. zozl .
State of Texas ss:
County of Hazris
,���u°°�������. SURETEC IIYSURANCE COMPAf\'Y
�;��r.�v�;
�;�.: �-.. ...,,:�:.
��,� � � �:�£ �Y�
y�,,� �•;�= Michael C. Keimig, President
�� ,( ; � �ce
.... ..•'.• &`F
. J
"�we � m,u,�r
On tE€is 3rd day of Mev l�.D. zoz� before me personally came Michae� C. Keimig, to me known, who, being hy me duly sworn, d�d depose and say,
that he resides in C-Iouston, Texas, that he is President of SUIZETEC INSURANCE COMPANY, tl�e company described in and which executed the ahove
instrument; that he icnows the seal of said Company; that the sea[ af�xed to said instrument is such corporate seal; thai it was so affixed by order of the
$oard of Directors of said Company; ar�d that he signed his name thereto by like order.
.�: �"° } �ANYA SNEED
Or •}��ti,*
k��* �r�i���l��
{,/OfTNtI. � ���
�~ °; �,� �r ro ��i��
Tanya Sneed, Not y Public
My commission exp es Marcla 30, 2023
I, M. Srent Beaty, Assistant Secretary of SURETEC INSUR�II+lCE COMPANY, d� hereby certify that the ahave and foregoing is a true and correct copy
of a Power af Attorney, executed by said Company, which is stil[ in full force and effect; and furthermore, the resolutions of the Board vf Directors, set
out in the Power of Attorney are in full #'orce and effect.
Given under my hand and the sea! of said Cocnpany at Houston, Texas tiiis �a � day of � ��a 2�z-( , A.D.
�
M. Brent Beaty, Assist�n� Se�Fetary �
Any instrument issued in ezcess oP the penalty statecE above is tofally �aid and without ar�y validity. 4224�00
For verifcation of the authority af this power you may call {713] 812-OB00 any business day between 8:30 am and �:liif �m G57.
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
STANDARD CITY CONDITIONS
OF THE CONSTRUCTION CONTRACT
FOR DEVELOPER AWARDED PROJECTS
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
STANDARD CITY CONDITIONS OF THE
CONSTRUCTION CONTRACT
FOR DEVELOPER AWARDED PROJECTS
TABLE OF CONTENTS
Page
Article 1 – Definitions and Terminology .......................................................................................................... 1
1.01 Defined Terms ............................................................................................................................... 1
1.02 Terminology .................................................................................................................................. 5
Article 2 – Preliminary Matters ......................................................................................................................... 6
2.01 Before Starting Construction ........................................................................................................ 6
2.02 Preconstruction Conference .......................................................................................................... 6
2.03 Public Meeting .............................................................................................................................. 6
Article 3 – Contract Documents and Amending ............................................................................................... 6
3.01 Reference Standards ..................................................................................................................... 6
3.02 Amending and Supplementing Contract Documents .................................................................. 6
Article 4 – Bonds and Insurance ....................................................................................................................... 7
4.01 Licensed Sureties and Insurers ..................................................................................................... 7
4.02 Performance, Payment, and Maintenance Bonds ........................................................................ 7
4.03 Certificates of Insurance ............................................................................................................... 7
4.04 Contractor’s Insurance .................................................................................................................. 9
4.05 Acceptance of Bonds and Insurance; Option to Replace ........................................................... 12
Article 5 – Contractor’s Responsibilities ........................................................................................................ 12
5.01 Supervision and Superintendent ................................................................................................. 12
5.02 Labor; Working Hours ................................................................................................................ 13
5.03 Services, Materials, and Equipment ........................................................................................... 13
5.04 Project Schedule .......................................................................................................................... 14
5.05 Substitutes and “Or-Equals” ....................................................................................................... 14
5.06 Pre-Qualification of Bidders (Prime Contractors and Subcontractors) ..................................... 16
5.07 Concerning Subcontractors, Suppliers, and Others ................................................................... 16
5.08 Wage Rates.................................................................................................................................. 18
5.09 Patent Fees and Royalties ........................................................................................................... 19
5.10 Laws and Regulations ................................................................................................................. 19
5.11 Use of Site and Other Areas ....................................................................................................... 19
5.12 Record Documents ...................................................................................................................... 20
5.13 Safety and Protection .................................................................................................................. 21
5.14 Safety Representative ................................................................................................................. 21
5.15 Hazard Communication Programs ............................................................................................. 22
5.16 Submittals .................................................................................................................................... 22
5.17 Contractor’s General Warranty and Guarantee .......................................................................... 23
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
5.18 Indemnification ........................................................................................................................... 24
5.19 Delegation of Professional Design Services .............................................................................. 24
5.20 Right to Audit: ............................................................................................................................ 25
5.21 Nondiscrimination....................................................................................................................... 25
Article 6 – Other Work at the Site ................................................................................................................... 26
6.01 Related Work at Site ................................................................................................................... 26
Article 7 – City’s Responsibilities................................................................................................................... 26
7.01 Inspections, Tests, and Approvals .............................................................................................. 26
7.02 Limitations on City’s Responsibilities ....................................................................................... 26
7.03 Compliance with Safety Program ............................................................................................... 27
Article 8 – City’s Observation Status During Construction ........................................................................... 27
8.01 City’s Project Representative ..................................................................................................... 27
8.02 Authorized Variations in Work .................................................................................................. 27
8.03 Rejecting Defective Work .......................................................................................................... 27
8.04 Determinations for Work Performed .......................................................................................... 28
Article 9 – Changes in the Work ..................................................................................................................... 28
9.01 Authorized Changes in the Work ............................................................................................... 28
9.02 Notification to Surety .................................................................................................................. 28
Article 10 – Change of Contract Price; Change of Contract Time ................................................................ 28
10.01 Change of Contract Price ............................................................................................................ 28
10.02 Change of Contract Time............................................................................................................ 28
10.03 Delays .......................................................................................................................................... 28
Article 11 – Tests and Inspections; Correction, Removal or Acceptance of Defective Work ...................... 29
11.01 Notice of Defects ........................................................................................................................ 29
11.02 Access to Work ........................................................................................................................... 29
11.03 Tests and Inspections .................................................................................................................. 29
11.04 Uncovering Work ....................................................................................................................... 30
11.05 City May Stop the Work ............................................................................................................. 30
11.06 Correction or Removal of Defective Work ................................................................................ 30
11.07 Correction Period ........................................................................................................................ 30
11.08 City May Correct Defective Work ............................................................................................. 31
Article 12 – Completion .................................................................................................................................. 32
12.01 Contractor’s Warranty of Title ................................................................................................... 32
12.02 Partial Utilization ........................................................................................................................ 32
12.03 Final Inspection ........................................................................................................................... 32
12.04 Final Acceptance ......................................................................................................................... 33
Article 13 – Suspension of Work .................................................................................................................... 33
13.01 City May Suspend Work ............................................................................................................ 33
Article 14 – Miscellaneous .............................................................................................................................. 34
14.01 Giving Notice .............................................................................................................................. 34
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
14.02 Computation of Times ................................................................................................................ 34
14.03 Cumulative Remedies ................................................................................................................. 34
14.04 Survival of Obligations ............................................................................................................... 35
14.05 Headings ...................................................................................................................................... 35
00 73 10- 1
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 1 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
ARTICLE 1 – DEFINITIONS AND TERMINOLOGY
1.01 Defined Terms
A. Wherever used in these General Conditions or in other Contract Documents, the terms listed
below have the meanings indicated which are applicable to both the singular and plural thereof,
and words denoting gender shall include the masculine, feminine and neuter. Said terms are
generally capitalized or written in italics, but not always. When used in a context consistent with
the definition of a listed-defined term, the term shall have a meaning as defined below whether
capitalized or italicized or otherwise. In addition to terms specifically defined, terms with initial
capital letters in the Contract Documents include references to identified articles and paragraphs,
and the titles of other documents or forms.
1. Agreement - The written instrument which is evidence of the agreement between Developer
and Contractor covering the Work
2. Asbestos—Any material that contains more than one percent asbestos and is friable or is
releasing asbestos fibers into the air above current action levels established by the United
States Occupational Safety and Health Administration.
3. Business Day – A business day is defined as a day that the City conducts normal business,
generally Monday through Friday, except for federal or state holidays observed by the City.
4. Buzzsaw – City’s on-line, electronic document management and collaboration system.
5. Calendar Day – A day consisting of 24 hours measured from midnight to the next midnight.
6. City— The City of Fort Worth, Texas, a Texas home-rule municipal corporation, acting by,
its governing body through its City Manager, his designee, or agents authorized pursuant to
its duly authorized charter on his behalf.
7. Community Facilities Agreement (CFA) -–A Contract between the Developer and the City
for the Construction of one or more following public facilities within the City public right-of-
way or easement: Water, Sanitary Sewer, Street, Storm Drain, Street Light, and Street Signs.
A CFA may include private facilities within the right-of-way dedicated as private right-of-
way or easement on a recorded plat.
8. Contract—The entire and integrated written document incorporating the Contract
Documents between the Developer, Contractor, and/or City concerning the Work. The
Contract supersedes prior negotiations, representations, or agreements, whether written or
oral.
9. Contract Documents—Those items that make up the contract and which must include the
Agreement, and it’s attachments such as standard construction specifications, standard City
Conditions, other general conditions of the Developer, including:
a. An Agreement
00 73 10- 2
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 2 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
b. Attachments to the Agreement
i. Bid Form
ii. Vendor Compliance with State Law Non-Resident Bidder
iii. Prequalification Statement
c. Current Prevailing Wage Rates Table (if required by City)
d. Insurance Accord Form
e. Payment Bond
f. Performance Bond
g. Maintenance Bond
h. Power of Attorney for Bonds
i. Workers Compensation Affidavit
j. MWBE Commitment Form( If required by City)
k. General Conditions
l. Supplementary Conditions
m. The Standard City Conditions
n. Specifications specifically made part of the Contract Documents by attachment, if
not attached, as incorporated by reference and described in the Table of Contents of
the Project’s Contract Documents
o. Drawings
p. Documentation submitted by contractor prior to Notice of Award.
q. The following which may be delivered or issued after the effective date if the
Agreement and, if issued become an incorporated part of the Contract Documents
i. Notice to Proceed
ii. Field Orders
iii. Change Orders
iv. Letters of Final Acceptance
r. Approved Submittals, other Contractor submittals, and the reports and drawings of
subsurface and physical conditions are not Contract Documents.
10. Contractor—The individual or entity with whom Developer has entered into the Agreement.
11. Day or day – A day, unless otherwise defined, shall mean a Calendar Day.
12. Developer – An individual or entity that desires to make certain improvements within the
City of Fort Worth
13. Drawings—That part of the Contract Documents prepared or approved by Engineer which
graphically shows the scope, extent, and character of the Work to be performed by
Contractor. Submittals are not Drawings as so defined.
14. Engineer—The licensed professional engineer or engineering firm registered in the State of
Texas performing professional services for the Developer.
15. Final Acceptance – The written notice given by the City to the Developer and/or Contractor
that the Work specified in the Contract Documents has been completed to the satisfaction of
the City.
00 73 10- 3
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 3 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
16. Final Inspection – Inspection carried out by the City to verify that the Contractor has
completed the Work, and each and every part or appurtenance thereof, fully, entirely, and in
conformance with the Contract Documents.
17. General Requirements—A part of the Contract Documents between the Developer and a
Contractor.
18. Laws and Regulations—Any and all applicable laws, rules, regulations, ordinances, codes,
and orders of any and all governmental bodies, agencies, authorities, and courts having
jurisdiction.
19. Liens—Charges, security interests, or encumbrances upon Project funds, real property, or
personal property.
20. Milestone—A principal event specified in the Contract Documents relating to an
intermediate Contract Time prior to Final Acceptance of the Work.
21. Non-Participating Change Order—A document, which is prepared for and reviewed by the
City, which is signed by Contractor, and Developer, and authorizes an addition, deletion, or
revision in the Work or an adjustment in the Contract Price or the Contract Time, issued on
or after the Effective Date of the Agreement.
22. Participating Change Order—A document, which is prepared for and approved by the City,
which is signed by Contractor, Developer, and City and authorizes an addition, deletion, or
revision in the Work or an adjustment in the Contract Price or the Contract Time, issued on
or after the Effective Date of the Agreement.
23. Plans – See definition of Drawings.
24. Project Schedule—A schedule, prepared and maintained by Contractor, in accordance with
the General Requirements, describing the sequence and duration of the activities comprising
the Contractor’s plan to accomplish the Work within the Contract Time.
25. Project—The Work to be performed under the Contract Documents.
26. Project Representative—The authorized representative of the City who will be assigned to
the Site.
27. Public Meeting – An announced meeting conducted by the Developer to facilitate public
participation and to assist the public in gaining an informed view of the Project.
28. Regular Working Hours – Hours beginning at 7:00 a.m. and ending at 6:00 p.m., Monday
thru Friday (excluding legal holidays).
29. Samples—Physical examples of materials, equipment, or workmanship that are
representative of some portion of the Work and which establish the standards by which such
portion of the Work will be judged.
00 73 10- 4
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 4 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
30. Schedule of Submittals—A schedule, prepared and maintained by Contractor, of required
submittals and the time requirements to support scheduled performance of related
construction activities.
31. Site—Lands or areas indicated in the Contract Documents as being furnished by City or
Developer upon which the Work is to be performed, including rights-of-way, permits, and
easements for access thereto, and such other lands furnished by City or Developer which are
designated for the use of Contractor.
32. Specifications—That part of the Contract Documents consisting of written requirements for
materials, equipment, systems, standards and workmanship as applied to the Work, and
certain administrative requirements and procedural matters applicable thereto.
Specifications may be specifically made a part of the Contract Documents by attachment or,
if not attached, may be incorporated by reference as indicated in the Table of Contents
(Division 00 00 00) of each Project.
33. Standard City Conditions – That part of the Contract Documents setting forth requirements
of the City.
34. Subcontractor—An individual or entity having a direct contract with Contractor or with any
other Subcontractor for the performance of a part of the Work at the Site.
35. Submittals—All drawings, diagrams, illustrations, schedules, and other data or information
which are specifically prepared or assembled by or for Contractor and submitted by
Contractor to illustrate some portion of the Work.
36. Superintendent – The representative of the Contractor who is available at all times and able
to receive instructions from the City and/or Developer and to act for the Contractor.
37. Supplementary Conditions—That part of the Contract Documents which amends or
supplements the General Conditions.
38. Supplier—A manufacturer, fabricator, supplier, distributor, materialman, or vendor having
a direct contract with Contractor or with any Subcontractor to furnish materials or
equipment to be incorporated in the Work by Contractor or Subcontractor.
39. Underground Facilities—All underground pipelines, conduits, ducts, cables, wires,
manholes, vaults, tanks, tunnels, or other such facilities or attachments, and any
encasements containing such facilities, including but not limited to, those that convey
electricity, gases, steam, liquid petroleum products, telephone or other communications,
cable television, water, wastewater, storm water, other liquids or chemicals, or traffic or
other control systems.
40. Weekend Working Hours – Hours beginning at 9:00 a.m. and ending at 5:00 p.m., Saturday,
Sunday or legal holiday, as approved in advance by the City.
00 73 10- 5
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 5 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
41. Work—The entire construction or the various separately identifiable parts thereof required
to be provided under the Contract Documents. Work includes and is the result of performing
or providing all labor, services, and documentation necessary to produce such construction
including any Participating Change Order, Non-Participating Change Order, or Field
Order, and furnishing, installing, and incorporating all materials and equipment into such
construction, all as required by the Contract Documents.
42. Working Day – A working day is defined as a day, not including Saturdays, Sundays, or
legal holidays authorized by the City for contract purposes, in which weather or other
conditions not under the control of the Contractor will permit the performance of the
principal unit of work underway for a continuous period of not less than 7 hours between 7
a.m. and 6 p.m.
1.02 Terminology
A. The words and terms discussed in Paragraph 1.02.B through D are not defined but, when used in
the Bidding Requirements or Contract Documents, have the indicated meaning.
B. Defective:
1. The word “defective,” when modifying the word “Work,” refers to Work that is
unsatisfactory, faulty, or deficient in that it:
a. does not conform to the Contract Documents; or
b. does not meet the requirements of any applicable inspection, reference standard, test, or
approval referred to in the Contract Documents; or
c. has been damaged prior to City’s written acceptance.
C. Furnish, Install, Perform, Provide:
1. The word “Furnish” or the word “Install” or the word “Perform” or the word “Provide” or
the word “Supply,” or any combination or similar directive or usage thereof, shall mean
furnishing and incorporating in the Work including all necessary labor, materials, equipment,
and everything necessary to perform the Work indicated, unless specifically limited in the
context used.
D. Unless stated otherwise in the Contract Documents, words or phrases that have a well-known
technical or construction industry or trade meaning are used in the Contract Documents in
accordance with such recognized meaning.
00 73 10- 6
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 6 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
ARTICLE 2 – PRELIMINARY MATTERS
2.01 Before Starting Construction
Baseline Schedules: Submit to City in accordance with the Contract Documents, and prior to starting
the Work. New schedules will be submitted to City when Participating Change Orders or Non-
Participating Change Orders occur.
2.02 Preconstruction Conference
Before any Work at the Site is started, the Contractor shall attend a Preconstruction Conference as
specified in the Contract Documents.
2.03 Public Meeting
Contractor may not mobilize any equipment, materials or resources to the Site prior to Contractor
attending the Public Meeting as scheduled by the City.
ARTICLE 3 – CONTRACT DOCUMENTS AND AMENDING
3.01 Reference Standards
A. Standards, Specifications, Codes, Laws, and Regulations
1. Reference to standards, specifications, manuals, or codes of any technical society,
organization, or association, or to Laws or Regulations, whether such reference be specific or
by implication, shall mean the standard, specification, manual, code, or Laws or Regulations
in effect at the time of opening of Bids (or on the Effective Date of the Agreement if there
were no Bids), except as may be otherwise specifically stated in the Contract Documents.
2. No provision or instruction shall be effective to assign to City, or any of its officers,
directors, members, partners, employees, agents, consultants, or subcontractors, any duty or
authority to supervise or direct the performance of the Work or any duty or authority to
undertake responsibility inconsistent with the provisions of the Contract Documents.
3.02 Amending and Supplementing Contract Documents
A. The Contract Documents may be amended to provide for additions, deletions, and revisions in
the Work or to modify the terms and conditions thereof by a Participating Change Order or a
Non-Participating Change Order.
B. The requirements of the Contract Documents may be supplemented, and minor variations and
deviations in the Work not involving a change in Contract Price or Contract Time, may be
authorized, by one or more of the following ways:
1. A Field Order;
00 73 10- 7
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 7 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
1. City’s or Engineer’s review of a Submittal (subject to the provisions of Paragraph 5.16.C); or
2. City’s written interpretation or clarification.
ARTICLE 4 – BONDS AND INSURANCE
4.01 Licensed Sureties and Insurers
All bonds and insurance required by the Contract Documents to be purchased and maintained by
Contractor shall be obtained from surety or insurance companies that are duly licensed or authorized
in the State of Texas to issue bonds or insurance policies for the limits and coverage so required.
Such surety and insurance companies shall also meet such additional requirements and qualifications
as may be provided Section 4.04.
4.02 Performance, Payment, and Maintenance Bonds
A. Contractor shall furnish performance and payment bonds in the name of Developer and City, in
accordance with Texas Government Code Chapter 2253 or successor statute, each in an amount
equal to the Contract Price as security for the faithful performance and payment of all of
Contractor’s obligations under the Contract Documents.
B. Contractor shall furnish maintenance bonds in the name of Developer and City in an amount
equal to the Contract Price as security to protect the City against any defects in any portion of the
Work described in the Contract Documents. Maintenance bonds shall remain in effect for two
(2) years after the date of Final Acceptance by the City.
C. All bonds shall be in the form prescribed by the Contract Documents except as provided
otherwise by Laws or Regulations, and shall be executed by such sureties as are named in the list
of “Companies Holding Certificates of Authority as Acceptable Sureties on Federal Bonds and
as Acceptable Reinsuring Companies” as published in Circular 570 (amended) by the Financial
Management Service, Surety Bond Branch, U.S. Department of the Treasury. All bonds signed
by an agent or attorney-in-fact must be accompanied by a sealed and dated power of attorney
which shall show that it is effective on the date the agent or attorney-in-fact signed each bond.
D. If the surety on any bond furnished by Contractor is declared bankrupt or becomes insolvent or
its right to do business is terminated in the State of Texas or it ceases to meet the requirements of
Paragraph 4.02.C, Contractor shall promptly notify City and shall, within 30 days after the event
giving rise to such notification, provide another bond and surety, both of which shall comply
with the requirements of Paragraphs 4.01 and 4.02.C.
4.03 Certificates of Insurance
Contractor shall deliver to Developer and City, with copies to each additional insured and loss payee
identified in these Standard City Conditions certificates of insurance (and other evidence of
insurance requested by City or any other additional insured) which Contractor is required to
purchase and maintain.
00 73 10- 8
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 8 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
1. The certificate of insurance shall document the City, an as “Additional Insured” on all
liability policies.
2. The Contractor’s general liability insurance shall include a, “per project” or “per location”,
endorsement, which shall be identified in the certificate of insurance provided to the City.
3. The certificate shall be signed by an agent authorized to bind coverage on behalf of the
insured, be complete in its entirety, and show complete insurance carrier names as listed in
the current A.M. Best Property & Casualty Guide
4. The insurers for all policies must be licensed and/or approved to do business in the State of
Texas. Except for workers’ compensation, all insurers must have a minimum rating of A-:
VII in the current A. M. Best Key Rating Guide or have reasonably equivalent financial
strength and solvency to the satisfaction of Risk Management. If the rating is below that
required, written approval of City is required.
5. All applicable policies shall include a Waiver of Subrogation (Rights of Recovery) in favor
of the City. In addition, the Contractor agrees to waive all rights of subrogation against the
Engineer (if applicable), and each additional insured identified in these Standard City
Conditions. Failure of the City to demand such certificates or other evidence of full
compliance with the insurance requirements or failure of the City to identify a deficiency
from evidence that is provided shall not be construed as a waiver of Contractor’s obligation
to maintain such lines of insurance coverage.
6. If insurance policies are not written for specified coverage limits, an Umbrella or Excess
Liability insurance for any differences is required. Excess Liability shall follow form of the
primary coverage.
7. Unless otherwise stated, all required insurance shall be written on the “occurrence basis”. If
coverage is underwritten on a claims-made basis, the retroactive date shall be coincident with
or prior to the date of the effective date of the agreement and the certificate of insurance shall
state that the coverage is claims-made and the retroactive date. The insurance coverage shall
be maintained for the duration of the Contract and for three (3) years following Final
Acceptance provided under the Contract Documents or for the warranty period, whichever is
longer. An annual certificate of insurance submitted to the City shall evidence such
insurance coverage.
8. Policies shall have no exclusions by endorsements, which, neither nullify or amend, the
required lines of coverage, nor decrease the limits of said coverage unless such endorsements
are approved in writing by the City. In the event a Contract has been bid or executed and the
exclusions are determined to be unacceptable or the City desires additional insurance
coverage, and the City desires the contractor/engineer to obtain such coverage, the contract
price shall be adjusted by the cost of the premium for such additional coverage plus 10%.
9. Any self-insured retention (SIR), in excess of $25,000.00, affecting required insurance
coverage shall be approved by the City in regards to asset value and stockholders' equity. In
00 73 10- 9
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 9 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
lieu of traditional insurance, alternative coverage maintained through insurance pools or risk
retention groups, must also be approved by City.
10. Any deductible in excess of $5,000.00, for any policy that does not provide coverage on a
first-dollar basis, must be acceptable to and approved by the City.
11. City, at its sole discretion, reserves the right to review the insurance requirements and to
make reasonable adjustments to insurance coverage’s and their limits when deemed
necessary and prudent by the City based upon changes in statutory law, court decision or the
claims history of the industry as well as of the contracting party to the City. The City shall
be required to provide prior notice of 90 days, and the insurance adjustments shall be
incorporated into the Work by Change Order.
12. City shall be entitled, upon written request and without expense, to receive copies of policies
and endorsements thereto and may make any reasonable requests for deletion or revision or
modifications of particular policy terms, conditions, limitations, or exclusions necessary to
conform the policy and endorsements to the requirements of the Contract. Deletions,
revisions, or modifications shall not be required where policy provisions are established by
law or regulations binding upon either party or the underwriter on any such policies.
13. City shall not be responsible for the direct payment of insurance premium costs for
Contractor’s insurance.
4.04 Contractor’s Insurance
A. Workers Compensation and Employers’ Liability. Contractor shall purchase and maintain such
insurance coverage with limits consistent with statutory benefits outlined in the Texas Workers’
Compensation Act (Texas Labor Code, Ch. 406, as amended), and minimum limits for
Employers’ Liability as is appropriate for the Work being performed and as will provide
protection from claims set forth below which may arise out of or result from Contractor’s
performance of the Work and Contractor’s other obligations under the Contract Documents,
whether it is to be performed by Contractor, any Subcontractor or Supplier, or by anyone directly
or indirectly employed by any of them to perform any of the Work, or by anyone for whose acts
any of them may be liable:
1. claims under workers’ compensation, disability benefits, and other similar employee benefit
acts;
2. claims for damages because of bodily injury, occupational sickness or disease, or death of
Contractor’s employees.
3. The limits of liability for the insurance shall provide the following coverages for not less
than the following amounts or greater where required by Laws and Regulations
a. Statutory limits
b. Employer's liability
00 73 10- 10
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 10 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
1) $100,000 each accident/occurrence
2) $100,000 Disease - each employee
3) $500,000 Disease - policy limit
B. Commercial General Liability. Coverage shall include but not be limited to covering liability
(bodily injury or property damage) arising from: premises/operations, independent contractors,
products/completed operations, personal injury, and liability under an insured contract. Insurance
shall be provided on an occurrence basis, and as comprehensive as the current Insurance
Services Office (ISO) policy. This insurance shall apply as primary insurance with respect to
any other insurance or self-insurance programs afforded to the City. The Commercial General
Liability policy, shall have no exclusions by endorsements that would alter of nullify
premises/operations, products/completed operations, contractual, personal injury, or advertising
injury, which are normally contained with the policy, unless the City approves such exclusions
in writing.
1. For construction projects that present a substantial completed operation exposure, the City
may require the contractor to maintain completed operations coverage for a minimum of no
less than three (3) years following the completion of the project
2. Contractor's Liability Insurance under this Section which shall be on a per project basis
covering the Contractor with minimum limits of:
a. $1,000,000 each occurrence
b. $2,000,000 aggregate limit
3. The policy must have an endorsement (Amendment – Aggregate Limits of Insurance)
making the General Aggregate Limits apply separately to each job site.
4. The Commercial General Liability Insurance policies shall provide “X”, “C”, and “U”
coverage’s. Verification of such coverage must be shown in the Remarks Article of the
Certificate of Insurance.
C. Automobile Liability. A commercial business auto policy shall provide coverage on “any auto”,
defined as autos owned, hired and non-owned and provide indemnity for claims for damages
because bodily injury or death of any person and or property damage arising out of the work,
maintenance or use of any motor vehicle by the Contractor, any Subcontractor or Supplier, or by
anyone directly or indirectly employed by any of them to perform any of the Work, or by anyone
for whose acts any of them may be liable.
1. Automobile Liability, Contractor’s Liability Insurance under this Section, which shall be in
an amount not less than the following amounts:
a. Automobile Liability - a commercial business policy shall provide coverage on "Any
Auto", defined as autos owned, hired and non-owned.
00 73 10- 11
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 11 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
1) $1,000,000 each accident on a combined single limit basis. Split limits are
acceptable if limits are at least:
2) $250,000 Bodily Injury per person
3) $500,000 Bodily Injury per accident /
4) $100,000 Property Damage
D. Railroad Protective Liability. If any of the work or any warranty work is within the limits of
railroad right-of-way, the Contractor shall comply with the following requirements:
1. The Contractor’s construction activities will require its employees, agents, subcontractors,
equipment, and material deliveries to cross railroad properties and tracks owned and
operated by: ____________________________________________________________
Write the name of the railroad company. (If none, then write none)
2. The Contractor shall conduct its operations on railroad properties in such a manner as not to
interfere with, hinder, or obstruct the railroad company in any manner whatsoever in the use
or operation of its/their trains or other property. Such operations on railroad properties may
require that Contractor to execute a “Right of Entry Agreement” with the particular railroad
company or companies involved, and to this end the Contractor should satisfy itself as to the
requirements of each railroad company and be prepared to execute the right-of-entry (if any)
required by a railroad company. The requirements specified herein likewise relate to the
Contractor’s use of private and/or construction access roads crossing said railroad company’s
properties.
3. The Contractual Liability coverage required by Paragraph 5.04D of the General Conditions
shall provide coverage for not less than the following amounts, issued by companies
satisfactory to the City and to the Railroad Company for a term that continues for so long as
the Contractor’s operations and work cross, occupy, or touch railroad property:
a. General Aggregate: _____________________________________
Enter limits provided by Railroad Company (If none, write none)
b. Each Occurrence: : _____________________________________
Enter limits provided by Railroad Company (If none, write none)
4. With respect to the above outlined insurance requirements, the following shall govern:
a. Where a single railroad company is involved, the Contractor shall provide one insurance
policy in the name of the railroad company. However, if more than one grade separation
or at-grade crossing is affected by the Project at entirely separate locations on the line or
lines of the same railroad company, separate coverage may be required, each in the
amount stated above.
b. Where more than one railroad company is operating on the same right-of-way or where
several railroad companies are involved and operated on their own separate rights-of-
00 73 10- 12
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 12 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
way, the Contractor may be required to provide separate insurance policies in the name
of each railroad company.
c. If, in addition to a grade separation or an at-grade crossing, other work or activity is
proposed on a railroad company’s right-of-way at a location entirely separate from the
grade separation or at-grade crossing, insurance coverage for this work must be included
in the policy covering the grade separation.
d. If no grade separation is involved but other work is proposed on a railroad company’s
right-of-way, all such other work may be covered in a single policy for that railroad, even
though the work may be at two or more separate locations.
5. No work or activities on a railroad company’s property to be performed by the Contractor
shall be commenced until the Contractor has furnished the City with an original policy or
policies of the insurance for each railroad company named, as required above. All such
insurance must be approved by the City and each affected Railroad Company prior to the
Contractor’s beginning work.
6. The insurance specified above must be carried until all Work to be performed on the railroad
right-of-way has been completed and the grade crossing, if any, is no longer used by the
Contractor. In addition, insurance must be carried during all maintenance and/or repair work
performed in the railroad right-of-way. Such insurance must name the railroad company as
the insured, together with any tenant or lessee of the railroad company operating over tracks
involved in the Project.
E. Notification of Policy Cancellation: Contractor shall immediately notify City upon cancellation
or other loss of insurance coverage. Contractor shall stop work until replacement insurance has
been procured. There shall be no time credit for days not worked pursuant to this section.
4.05 Acceptance of Bonds and Insurance; Option to Replace
If City has any objection to the coverage afforded by or other provisions of the bonds or insurance
required to be purchased and maintained by the Contractor in accordance with Article 5 on the basis
of non-conformance with the Contract Documents, the Developer and City shall so notify the
Contractor in writing within 10 Business Days after receipt of the certificates (or other evidence
requested). Contractor shall provide to the City such additional information in respect of insurance
provided as the Developer or City may reasonably request. If Contractor does not purchase or
maintain all of the bonds and insurance required by the Contract Documents, the Developer or City
shall notify the Contractor in writing of such failure prior to the start of the Work, or of such failure
to maintain prior to any change in the required coverage.
ARTICLE 5 – CONTRACTOR’S RESPONSIBILITIES
5.01 Supervision and Superintendent
A. Contractor shall supervise, inspect, and direct the Work competently and efficiently, devoting
such attention thereto and applying such skills and expertise as may be necessary to perform the
00 73 10- 13
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 13 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
Work in accordance with the Contract Documents. Contractor shall be solely responsible for the
means, methods, techniques, sequences, and procedures of construction.
B. At all times during the progress of the Work, Contractor shall assign a competent, English-
speaking, Superintendent who shall not be replaced without written notice to City. The
Superintendent will be Contractor’s representative at the Site and shall have authority to act on
behalf of Contractor. All communication given to or received from the Superintendent shall be
binding on Contractor.
C. Contractor shall notify the City 24 hours prior to moving areas during the sequence of
construction.
5.02 Labor; Working Hours
A. Contractor shall provide competent, suitably qualified personnel to perform construction as
required by the Contract Documents. Contractor shall at all times maintain good discipline and
order at the Site.
B. Except as otherwise required for the safety or protection of persons or the Work or property at
the Site or adjacent thereto, and except as otherwise stated in the Contract Documents, all Work
at the Site shall be performed during Regular Working Hours. Contractor will not permit the
performance of Work beyond Regular Working Hours or for Weekend Working Hours without
City’s written consent (which will not be unreasonably withheld). Written request (by letter or
electronic communication) to perform Work:
1. for beyond Regular Working Hours request must be made by noon at least two (2) Business
Days prior
2. for Weekend Working Hours request must be made by noon of the preceding Thursday
3. for legal holidays request must be made by noon two Business Days prior to the legal
holiday.
5.03 Services, Materials, and Equipment
A. Unless otherwise specified in the Contract Documents, Contractor shall provide and assume full
responsibility for all services, materials, equipment, labor, transportation, construction
equipment and machinery, tools, appliances, fuel, power, light, heat, telephone, water, sanitary
facilities, temporary facilities, and all other facilities and incidentals necessary for the
performance, Contractor required testing, start-up, and completion of the Work.
B. All materials and equipment incorporated into the Work shall be as specified or, if not specified,
shall be of good quality and new, except as otherwise provided in the Contract Documents. All
special warranties and guarantees required by the Specifications shall expressly run to the benefit
of City. If required by City, Contractor shall furnish satisfactory evidence (including reports of
required tests) as to the source, kind, and quality of materials and equipment.
00 73 10- 14
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 14 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
C. All materials and equipment to be incorporated into the Work shall be stored, applied, installed,
connected, erected, protected, used, cleaned, and conditioned in accordance with instructions of
the applicable Supplier, except as otherwise may be provided in the Contract Documents.
5.04 Project Schedule
A. Contractor shall adhere to the Project Schedule established in accordance with Paragraph 2.01
and the General Requirements as it may be adjusted from time to time as provided below.
1. Contractor shall submit to City for acceptance (to the extent indicated in Paragraph 2.01 and
the General Requirements) proposed adjustments in the Project Schedule.
2. Proposed adjustments in the Project Schedule that will change the Contract Time shall be
submitted in accordance with the requirements of Article 9. Adjustments in Contract Time
for projects with City participation shall be made by participating change orders.
5.05 Substitutes and “Or-Equals”
A. Whenever an item of material or equipment is specified or described in the Contract Documents
by using the name of a proprietary item or the name of a particular Supplier, the specification or
description is intended to establish the type, function, appearance, and quality required. Unless
the specification or description contains or is followed by words reading that no like, equivalent,
or “or-equal” item or no substitution is permitted, other items of material or equipment of other
Suppliers may be submitted to City for review under the circumstances described below.
1. “Or-Equal” Items: If in City’s sole discretion an item of material or equipment proposed by
Contractor is functionally equal to that named and sufficiently similar so that no change in
related Work will be required, it may be considered by City as an “or-equal” item, in which
case review and approval of the proposed item may, in City’s sole discretion, be
accomplished without compliance with some or all of the requirements for approval of
proposed substitute items. For the purposes of this Paragraph 5.05.A.1, a proposed item of
material or equipment will be considered functionally equal to an item so named if:
a. City determines that:
1) it is at least equal in materials of construction, quality, durability, appearance,
strength, and design characteristics;
2) it will reliably perform at least equally well the function and achieve the results
imposed by the design concept of the completed Project as a functioning whole; and
3) it has a proven record of performance and availability of responsive service; and
b. Contractor certifies that, if approved and incorporated into the Work:
1) there will be no increase in cost to the City or increase in Contract Time; and
00 73 10- 15
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 15 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
2) it will conform substantially to the detailed requirements of the item named in the
Contract Documents.
2. Substitute Items:
a. If in City’s sole discretion an item of material or equipment proposed by Contractor does
not qualify as an “or-equal” item under Paragraph 5.05.A.1, it may be submitted as a
proposed substitute item.
b. Contractor shall submit sufficient information as provided below to allow City to
determine if the item of material or equipment proposed is essentially equivalent to that
named and an acceptable substitute therefor. Requests for review of proposed substitute
items of material or equipment will not be accepted by City from anyone other than
Contractor.
c. Contractor shall make written application to City for review of a proposed substitute item
of material or equipment that Contractor seeks to furnish or use. The application shall
comply with Section 01 25 00 and:
1) shall certify that the proposed substitute item will:
i. perform adequately the functions and achieve the results called for by the general
design;
ii. be similar in substance to that specified;
iii. be suited to the same use as that specified; and
2) will state:
i. the extent, if any, to which the use of the proposed substitute item will prejudice
Contractor’s achievement of final completion on time;
ii. whether use of the proposed substitute item in the Work will require a change in
any of the Contract Documents (or in the provisions of any other direct contract
with City for other work on the Project) to adapt the design to the proposed
substitute item;
iii. whether incorporation or use of the proposed substitute item in connection with
the Work is subject to payment of any license fee or royalty; and
3) will identify:
i. all variations of the proposed substitute item from that specified;
ii. available engineering, sales, maintenance, repair, and replacement services; and
00 73 10- 16
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 16 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
4) shall contain an itemized estimate of all costs or credits that will result directly or
indirectly from use of such substitute item, including costs of redesign and Damage
Claims of other contractors affected by any resulting change.
B. Substitute Construction Methods or Procedures: If a specific means, method, technique,
sequence, or procedure of construction is expressly required by the Contract Documents,
Contractor may furnish or utilize a substitute means, method, technique, sequence, or procedure
of construction approved by City. Contractor shall submit sufficient information to allow City, in
City’s sole discretion, to determine that the substitute proposed is equivalent to that expressly
called for by the Contract Documents. Contractor shall make written application to City for
review in the same manner as those provided in Paragraph 5.05.A.2.
C. City’s Evaluation: City will be allowed a reasonable time within which to evaluate each
proposal or submittal made pursuant to Paragraphs 5.05.A and 5.05.B. City may require
Contractor to furnish additional data about the proposed substitute. City will be the sole judge of
acceptability. No “or-equal” or substitute will be ordered, installed or utilized until City’s review
is complete, which will be evidenced by a Change Order in the case of a substitute and an
accepted Submittal for an “or-equal.” City will advise Contractor in writing of its determination.
D. Special Guarantee: City may require Contractor to furnish at Contractor’s expense a special
performance guarantee, warranty, or other surety with respect to any substitute. Contractor shall
indemnify and hold harmless City and anyone directly or indirectly employed by them from and
against any and all claims, damages, losses and expenses (including attorneys fees) arising out
of the use of substituted materials or equipment.
E. City’s Cost Reimbursement: City will record City’s costs in evaluating a substitute proposed or
submitted by Contractor pursuant to Paragraphs 5.05.A.2 and 5.05.B. Whether or not City
approves a substitute so proposed or submitted by Contractor, Contractor may be required to
reimburse City for evaluating each such proposed substitute. Contractor may also be required to
reimburse City for the charges for making changes in the Contract Documents.
F. Contractor’s Expense: Contractor shall provide all data in support of any proposed substitute or
“or-equal” at Contractor’s expense.
G. Substitute Reimbursement: Costs (savings or charges) attributable to acceptance of a substitute
shall be incorporated to the Contract by Participating Change Order.
5.06 Pre-Qualification of Bidders (Prime Contractors and Subcontractors)
A. The Contractor and any subcontractors are required to be prequalified for the work types
requiring pre-qualification
5.07 Concerning Subcontractors, Suppliers, and Others
A. Minority and Women Owned Business Enterprise Compliance:
00 73 10- 17
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 17 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
Required for this Contract.
(Check this box if there is any City Participation)
Not Required for this Contract.
It is City policy to ensure the full and equitable participation by Minority and Women Business
Enterprises (MWBE) in the procurement of goods and services on a contractual basis. If the
Contract Documents provide for a MWBE goal, Contractor is required to comply with the intent
of the City’s MWBE Ordinance (as amended) by the following:
1. Contractor shall, upon request by City, provide complete and accurate information regarding
actual work performed by a MWBE on the Contract and payment therefor.
2. Contractor will not make additions, deletions, or substitutions of accepted MWBE without
written consent of the City. Any unjustified change or deletion shall be a material breach of
Contract and may result in debarment in accordance with the procedures outlined in the
Ordinance.
3. Contractor shall, upon request by City, allow an audit and/or examination of any books,
records, or files in the possession of the Contractor that will substantiate the actual work
performed by an MWBE. Material misrepresentation of any nature will be grounds for
termination of the Contract. Any such misrepresentation may be grounds for disqualification
of Contractor to bid on future contracts with the City for a period of not less than three years.
B. Contractor shall be fully responsible to City for all acts and omissions of the Subcontractors,
Suppliers, and other individuals or entities performing or furnishing any of the Work just as
Contractor is responsible for Contractor’s own acts and omissions. Nothing in the Contract
Documents:
1. shall create for the benefit of any such Subcontractor, Supplier, or other individual or entity
any contractual relationship between City and any such Subcontractor, Supplier or other
individual or entity; nor
2. shall create any obligation on the part of City to pay or to see to the payment of any moneys
due any such Subcontractor, Supplier, or other individual or entity except as may otherwise
be required by Laws and Regulations.
C. Contractor shall be solely responsible for scheduling and coordinating the Work of
Subcontractors, Suppliers, and other individuals or entities performing or furnishing any of the
Work under a direct or indirect contract with Contractor.
D. All Subcontractors, Suppliers, and such other individuals or entities performing or furnishing
any of the Work shall communicate with City through Contractor.
E. All Work performed for Contractor by a Subcontractor or Supplier will be pursuant to an
appropriate agreement between Contractor and the Subcontractor or Supplier which specifically
binds the Subcontractor or Supplier to the applicable terms and conditions of these Contract
00 73 10- 18
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 18 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
Documents, Contractor shall provide City contract numbers and reference numbers to the
Subcontractors and/or Suppliers.
5.08 Wage Rates
Required for this Contract.
Not Required for this Contract.
A. Duty to pay Prevailing Wage Rates. The Contractor shall comply with all requirements of
Chapter 2258, Texas Government Code (as amended), including the payment of not less than the
rates determined by the City Council of the City of Fort Worth to be the prevailing wage rates in
accordance with Chapter 2258. Such prevailing wage rates are included in these Contract
Documents.
B. Penalty for Violation. A Contractor or any Subcontractor who does not pay the prevailing wage
shall, upon demand made by the City, pay to the City $60 for each worker employed for each
calendar day or part of the day that the worker is paid less than the prevailing wage rates
stipulated in these contract documents. This penalty shall be retained by the City to offset its
administrative costs, pursuant to Texas Government Code 2258.023.
C. Complaints of Violations and City Determination of Good Cause. On receipt of information,
including a complaint by a worker, concerning an alleged violation of 2258.023, Texas
Government Code, by a Contractor or Subcontractor, the City shall make an initial
determination, before the 31st day after the date the City receives the information, as to whether
good cause exists to believe that the violation occurred. The City shall notify in writing the
Contractor or Subcontractor and any affected worker of its initial determination. Upon the
City’s determination that there is good cause to believe the Contractor or Subcontractor has
violated Chapter 2258, the City shall retain the full amounts claimed by the claimant or
claimants as the difference between wages paid and wages due under the prevailing wage rates,
such amounts being subtracted from successive progress payments pending a final determination
of the violation.
D. Arbitration Required if Violation Not Resolved. An issue relating to an alleged violation of
Section 2258.023, Texas Government Code, including a penalty owed to the City or an affected
worker, shall be submitted to binding arbitration in accordance with the Texas General
Arbitration Act (Article 224 et seq., Revised Statutes) if the Contractor or Subcontractor and any
affected worker does not resolve the issue by agreement before the 15th day after the date the
City makes its initial determination pursuant to Paragraph C above. If the persons required to
arbitrate under this section do not agree on an arbitrator before the 11th day after the date that
arbitration is required, a district court shall appoint an arbitrator on the petition of any of the
persons. The City is not a party in the arbitration. The decision and award of the arbitrator is
final and binding on all parties and may be enforced in any court of competent jurisdiction.
E. Records to be Maintained. The Contractor and each Subcontractor shall, for a period of three (3)
years following the date of acceptance of the work, maintain records that show (i) the name and
00 73 10- 19
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 19 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
occupation of each worker employed by the Contractor in the construction of the Work provided
for in this Contract; and (ii) the actual per diem wages paid to each worker. The records shall be
open at all reasonable hours for inspection by the City. The provisions of Paragraph 6.23, Right
to Audit, shall pertain to this inspection.
F. Progress Payments. With each progress payment or payroll period, whichever is less, the
Contractor shall submit an affidavit stating that the Contractor has complied with the
requirements of Chapter 2258, Texas Government Code.
G. Posting of Wage Rates. The Contractor shall post prevailing wage rates in a conspicuous place at
all times.
H. Subcontractor Compliance. The Contractor shall include in its subcontracts and/or shall
otherwise require all of its Subcontractors to comply with Paragraphs A through G above.
5.09 Patent Fees and Royalties
A. To the fullest extent permitted by Laws and Regulations, Contractor shall indemnify and hold
harmless City, from and against all claims, costs, losses, and damages (including but not limited
to all fees and charges of engineers, architects, attorneys, and other professionals and all court
or arbitration or other dispute resolution costs) arising out of or relating to any infringement of
patent rights or copyrights incident to the use in the performance of the Work or resulting from
the incorporation in the Work of any invention, design, process, product, or device not specified
in the Contract Documents.
5.10 Laws and Regulations
A. Contractor shall give all notices required by and shall comply with all Laws and Regulations
applicable to the performance of the Work. Except where otherwise expressly required by
applicable Laws and Regulations, the City shall not be responsible for monitoring Contractor’s
compliance with any Laws or Regulations.
B. If Contractor performs any Work knowing or having reason to know that it is contrary to Laws
or Regulations, Contractor shall bear all claims, costs, losses, and damages (including but not
limited to all fees and charges of engineers, architects, attorneys, and other professionals and all
court or arbitration or other dispute resolution costs) arising out of or relating to such Work.
However, it shall not be Contractor’s responsibility to make certain that the Specifications and
Drawings are in accordance with Laws and Regulations, but this shall not relieve Contractor of
Contractor’s obligations under Paragraph 3.01.
5.11 Use of Site and Other Areas
A. Limitation on Use of Site and Other Areas:
1. Contractor shall confine construction equipment, the storage of materials and equipment, and
the operations of workers to the Site and other areas permitted by Laws and Regulations, and
shall not unreasonably encumber the Site and other areas with construction equipment or
00 73 10- 20
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 20 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
other materials or equipment. Contractor shall assume full responsibility for any damage to
any such land or area, or to the owner or occupant thereof, or of any adjacent land or areas
resulting from the performance of the Work.
2. At any time when, in the judgment of the City, the Contractor has obstructed or closed or is
carrying on operations in a portion of a street, right-of-way, or easement greater than is
necessary for proper execution of the Work, the City may require the Contractor to finish the
section on which operations are in progress before work is commenced on any additional
area of the Site.
3. Should any Damage Claim be made by any such owner or occupant because of the
performance of the Work, Contractor shall promptly attempt to resolve the Damage Claim.
4. Pursuant to Paragraph 5.18, Contractor shall indemnify and hold harmless City, from and
against all claims, costs, losses, and damages arising out of or relating to any claim or
action, legal or equitable, brought by any such owner or occupant against City.
B. Removal of Debris During Performance of the Work: During the progress of the Work
Contractor shall keep the Site and other areas free from accumulations of waste materials,
rubbish, and other debris. Removal and disposal of such waste materials, rubbish, and other
debris shall conform to applicable Laws and Regulations.
C. Site Maintenance Cleaning: 24 hours after written notice is given to the Contractor that the
clean-up on the job site is proceeding in a manner unsatisfactory to the City or Developer, if the
Contractor fails to correct the unsatisfactory procedure, the City may take such direct action as
the City deems appropriate to correct the clean-up deficiencies cited to the Contractor in the
written notice (by letter or electronic communication), and shall be entitled to recover its cost in
doing so. The City may withhold Final Acceptance until clean-up is complete and cost are
recovered.
D. Final Site Cleaning: Prior to Final Acceptance of the Work Contractor shall clean the Site and
the Work and make it ready for utilization by City or adjacent property owner. At the completion
of the Work Contractor shall remove from the Site all tools, appliances, construction equipment
and machinery, and surplus materials and shall restore to original condition or better all property
disturbed by the Work.
E. Loading Structures: Contractor shall not load nor permit any part of any structure to be loaded
in any manner that will endanger the structure, nor shall Contractor subject any part of the Work
or adjacent property to stresses or pressures that will endanger it.
5.12 Record Documents
A. Contractor shall maintain in a safe place at the Site or in a place designated by the Contractor
and approved by the City, one (1) record copy of all Drawings, Specifications, Addenda, Change
Orders, Field Orders, and written interpretations and clarifications in good order and annotated
to show changes made during construction. These record documents together with all approved
00 73 10- 21
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 21 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
Samples and a counterpart of all accepted Submittals will be available to City for reference.
Upon completion of the Work, these record documents, any operation and maintenance manuals,
and Submittals will be delivered to City prior to Final Inspection. Contractor shall include
accurate locations for buried and imbedded items.
5.13 Safety and Protection
A. Contractor shall be solely responsible for initiating, maintaining and supervising all safety
precautions and programs in connection with the Work. Such responsibility does not relieve
Subcontractors of their responsibility for the safety of persons or property in the performance of
their work, nor for compliance with applicable safety Laws and Regulations. Contractor shall
take all necessary precautions for the safety of, and shall provide the necessary protection to
prevent damage, injury or loss to:
1. all persons on the Site or who may be affected by the Work;
2. all the Work and materials and equipment to be incorporated therein, whether in storage on
or off the Site; and
3. other property at the Site or adjacent thereto, including trees, shrubs, lawns, walks,
pavements, roadways, structures, utilities, and Underground Facilities not designated for
removal, relocation, or replacement in the course of construction.
B. Contractor shall comply with all applicable Laws and Regulations relating to the safety of
persons or property, or to the protection of persons or property from damage, injury, or loss; and
shall erect and maintain all necessary safeguards for such safety and protection. Contractor shall
notify owners of adjacent property and of Underground Facilities and other utility owners when
prosecution of the Work may affect them, and shall cooperate with them in the protection,
removal, relocation, and replacement of their property.
C. Contractor shall comply with the applicable requirements of City’s safety programs, if any.
D. Contractor shall inform City of the specific requirements of Contractor’s safety program, if any,
with which City’s employees and representatives must comply while at the Site.
E. All damage, injury, or loss to any property referred to in Paragraph 5.13.A.2 or 5.13.A.3 caused,
directly or indirectly, in whole or in part, by Contractor, any Subcontractor, Supplier, or any
other individual or entity directly or indirectly employed by any of them to perform any of the
Work, or anyone for whose acts any of them may be liable, shall be remedied by Contractor.
F. Contractor’s duties and responsibilities for safety and for protection of the Work shall continue
until such time as all the Work is completed and City has accepted the Work.
5.14 Safety Representative
Contractor shall inform City in writing of Contractor’s designated safety representative at the Site.
00 73 10- 22
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 22 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
5.15 Hazard Communication Programs
Contractor shall be responsible for coordinating any exchange of material safety data sheets or other
hazard communication information required to be made available to or exchanged between or
among employers in accordance with Laws or Regulations.
5.16 Submittals
A. Contractor shall submit required Submittals to City for review and acceptance. Each submittal
will be identified as required by City.
1. Submit number of copies specified in the General Requirements.
2. Data shown on the Submittals will be complete with respect to quantities, dimensions,
specified performance and design criteria, materials, and similar data to show City the
services, materials, and equipment Contractor proposes to provide and to enable City to
review the information for the limited purposes required by Paragraph 5.16.C.
3. Submittals submitted as herein provided by Contractor and reviewed by City for
conformance with the design concept shall be executed in conformity with the Contract
Documents unless otherwise required by City.
4. When Submittals are submitted for the purpose of showing the installation in greater detail,
their review shall not excuse Contractor from requirements shown on the Drawings and
Specifications.
5. For-Information-Only submittals upon which the City is not expected to conduct review or
take responsive action may be so identified in the Contract Documents.
6. Submit required number of Samples specified in the Specifications.
7. Clearly identify each Sample as to material, Supplier, pertinent data such as catalog numbers,
the use for which intended and other data as City may require to enable City to review the
submittal for the limited purposes required by Paragraph 5.16.C.
B. Where a Submittal is required by the Contract Documents or the Schedule of Submittals, any
related Work performed prior to City’s review and acceptance of the pertinent submittal will be
at the sole expense and responsibility of Contractor.
C. City’s Review:
1. City will provide timely review of required Submittals in accordance with the Schedule of
Submittals acceptable to City. City’s review and acceptance will be only to determine if the
items covered by the submittals will, after installation or incorporation in the Work, conform
to the information given in the Contract Documents and be compatible with the design
concept of the completed Project as a functioning whole as indicated by the Contract
Documents.
00 73 10- 23
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 23 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
2. City’s review and acceptance will not extend to means, methods, techniques, sequences, or
procedures of construction (except where a particular means, method, technique, sequence,
or procedure of construction is specifically and expressly called for by the Contract
Documents) or to safety precautions or programs incident thereto. The review and
acceptance of a separate item as such will not indicate approval of the assembly in which the
item functions.
3. City’s review and acceptance shall not relieve Contractor from responsibility for any
variation from the requirements of the Contract Documents unless Contractor has complied
with the requirements of Section 01 33 00 and City has given written acceptance of each
such variation by specific written notation thereof incorporated in or accompanying the
Submittal. City’s review and acceptance shall not relieve Contractor from responsibility for
complying with the requirements of the Contract Documents.
5.17 Contractor’s General Warranty and Guarantee
A. Contractor warrants and guarantees to City that all Work will be in accordance with the Contract
Documents and will not be defective. City and its officers, directors, members, partners,
employees, agents, consultants, and subcontractors shall be entitled to rely on representation of
Contractor’s warranty and guarantee.
B. Contractor’s warranty and guarantee hereunder excludes defects or damage caused by:
1. abuse, modification, or improper maintenance or operation by persons other than Contractor,
Subcontractors, Suppliers, or any other individual or entity for whom Contractor is
responsible; or
2. normal wear and tear under normal usage.
C. Contractor’s obligation to perform and complete the Work in accordance with the Contract
Documents shall be absolute. None of the following will constitute an acceptance of Work that is
not in accordance with the Contract Documents or a release of Contractor’s obligation to
perform the Work in accordance with the Contract Documents:
1. observations by City;
2. recommendation or payment by City or Developer of any progress or final payment;
3. the issuance of a certificate of Final Acceptance by City or any payment related thereto by
City;
4. use or occupancy of the Work or any part thereof by City;
5. any review and acceptance of a Submittal by City;
6. any inspection, test, or approval by others; or
00 73 10- 24
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 24 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
7. any correction of defective Work by City.
D. The Contractor shall remedy any defects or damages in the Work and pay for any damage to
other work or property resulting therefrom which shall appear within a period of two (2) years
from the date of Final Acceptance of the Work unless a longer period is specified and shall
furnish a good and sufficient maintenance bond, complying with the requirements of Article
4.02.B. The City will give notice of observed defects with reasonable promptness.
5.18 Indemnification
A. Contractor covenants and agrees to indemnify, hold harmless and defend, at its own expense, the
City, its officers, servants and employees, from and against any and all claims arising out of, or
alleged to arise out of, the work and services to be performed by the Contractor, its officers,
agents, employees, subcontractors, licenses or invitees under this Contract. THIS
INDEMNIFICATION PROVISION IS SPECIFICALLY INTENDED TO OPERATE
AND BE EFFECTIVE EVEN IF IT IS ALLEGED OR PROVEN THAT ALL OR SOME
OF THE DAMAGES BEING SOUGHT WERE CAUSED, IN WHOLE OR IN PART, BY
ANY ACT, OMISSION OR NEGLIGENCE OF THE CITY. This indemnity provision is
intended to include, without limitation, indemnity for costs, expenses and legal fees incurred by
the City in defending against such claims and causes of actions.
B. Contractor covenants and agrees to indemnify and hold harmless, at its own expense, the City, its
officers, servants and employees, from and against any and all loss, damage or destruction of
property of the City, arising out of, or alleged to arise out of, the work and services to be
performed by the Contractor, its officers, agents, employees, subcontractors, licensees or invitees
under this Contract. THIS INDEMNIFICATION PROVISION IS SPECIFICALLY
INTENDED TO OPERATE AND BE EFFECTIVE EVEN IF IT IS ALLEGED OR
PROVEN THAT ALL OR SOME OF THE DAMAGES BEING SOUGHT WERE
CAUSED, IN WHOLE OR IN PART, BY ANY ACT, OMISSION OR NEGLIGENCE OF
THE CITY.
5.19 Delegation of Professional Design Services
A. Contractor will not be required to provide professional design services unless such services are
specifically required by the Contract Documents for a portion of the Work or unless such
services are required to carry out Contractor’s responsibilities for construction means, methods,
techniques, sequences and procedures.
B. If professional design services or certifications by a design professional related to systems,
materials or equipment are specifically required of Contractor by the Contract Documents, City
will specify all performance and design criteria that such services must satisfy. Contractor shall
cause such services or certifications to be provided by a properly licensed professional, whose
signature and seal shall appear on all drawings, calculations, specifications, certifications, and
Submittals prepared by such professional. Submittals related to the Work designed or certified
by such professional, if prepared by others, shall bear such professional’s written approval when
submitted to City.
00 73 10- 25
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 25 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
C. City shall be entitled to rely upon the adequacy, accuracy and completeness of the services,
certifications or approvals performed by such design professionals, provided City has specified
to Contractor performance and design criteria that such services must satisfy.
D. Pursuant to this Paragraph 5.19, City’s review and acceptance of design calculations and design
drawings will be only for the limited purpose of checking for conformance with performance
and design criteria given and the design concept expressed in the Contract Documents. City’s
review and acceptance of Submittals (except design calculations and design drawings) will be
only for the purpose stated in Paragraph 5.16.C.
5.20 Right to Audit:
A. The City reserves the right to audit all projects utilizing City funds
B. The Contractor agrees that the City shall, until the expiration of three (3) years after final
payment under this Contract, have access to and the right to examine and photocopy any directly
pertinent books, documents, papers, and records of the Contractor involving transactions relating
to this Contract. Contractor agrees that the City shall have access during Regular Working Hours
to all necessary Contractor facilities and shall be provided adequate and appropriate work space
in order to conduct audits in compliance with the provisions of this Paragraph. The City shall
give Contractor reasonable advance notice of intended audits.
C. Contractor further agrees to include in all its subcontracts hereunder a provision to the effect that
the subcontractor agrees that the City shall, until the expiration of three (3) years after final
payment under this Contract, have access to and the right to examine and photocopy any directly
pertinent books, documents, papers, and records of such Subcontractor, involving transactions to
the subcontract, and further, that City shall have access during Regular Working Hours to all
Subcontractor facilities, and shall be provided adequate and appropriate work space in order to
conduct audits in compliance with the provisions of this Paragraph. The City shall give
Subcontractor reasonable advance notice of intended audits.
D. Contractor and Subcontractor agree to photocopy such documents as may be requested by the
City. The City agrees to reimburse Contractor for the cost of the copies as follows at the rate
published in the Texas Administrative Code in effect as of the time copying is performed.
5.21 Nondiscrimination
A. The City is responsible for operating Public Transportation Programs and implementing transit-
related projects, which are funded in part with Federal financial assistance awarded by the U.S.
Department of Transportation and the Federal Transit Administration (FTA), without
discriminating against any person in the United States on the basis of race, color, or national
origin.
B. Title VI, Civil Rights Act of 1964 as amended: Contractor shall comply with the requirements of
the Act and the Regulations as further defined in the Supplementary Conditions for any project
receiving Federal assistance.
00 73 10- 26
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 26 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
ARTICLE 6 – OTHER WORK AT THE SITE
6.01 Related Work at Site
A. City may perform other work related to the Project at the Site with City’s employees, or other
City contractors, or through other direct contracts therefor, or have other work performed by
utility owners. If such other work is not noted in the Contract Documents, then written notice
thereof will be given to Contractor prior to starting any such other work; and
B. Contractor shall afford each other contractor who is a party to such a direct contract, each utility
owner, and City, if City is performing other work with City’s employees or other City
contractors, proper and safe access to the Site, provide a reasonable opportunity for the
introduction and storage of materials and equipment and the execution of such other work, and
properly coordinate the Work with theirs. Contractor shall do all cutting, fitting, and patching of
the Work that may be required to properly connect or otherwise make its several parts come
together and properly integrate with such other work. Contractor shall not endanger any work of
others by cutting, excavating, or otherwise altering such work; provided, however, that
Contractor may cut or alter others' work with the written consent of City and the others whose
work will be affected.
C. If the proper execution or results of any part of Contractor’s Work depends upon work
performed by others under this Article 7, Contractor shall inspect such other work and promptly
report to City in writing any delays, defects, or deficiencies in such other work that render it
unavailable or unsuitable for the proper execution and results of Contractor’s Work. Contractor’s
failure to so report will constitute an acceptance of such other work as fit and proper for
integration with Contractor’s Work except for latent defects in the work provided by others.
ARTICLE 7 – CITY’S RESPONSIBILITIES
7.01 Inspections, Tests, and Approvals
City’s responsibility with respect to certain inspections, tests, and approvals is set forth in Paragraph
11.03.
7.02 Limitations on City’s Responsibilities
A. The City shall not supervise, direct, or have control or authority over, nor be responsible for,
Contractor’s means, methods, techniques, sequences, or procedures of construction, or the safety
precautions and programs incident thereto, or for any failure of Contractor to comply with Laws
and Regulations applicable to the performance of the Work. City will not be responsible for
Contractor’s failure to perform the Work in accordance with the Contract Documents.
B. City will notify the Contractor of applicable safety plans pursuant to Paragraph 5.13.
00 73 10- 27
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 27 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
7.03 Compliance with Safety Program
While at the Site, City’s employees and representatives shall comply with the specific applicable
requirements of Contractor’s safety programs of which City has been informed pursuant to
Paragraph 5.13.
ARTICLE 8 – CITY’S OBSERVATION STATUS DURING CONSTRUCTION
8.01 City’s Project Representative
City will provide one or more Project Representative(s) during the construction period. The duties
and responsibilities and the limitations of authority of City’s representative during construction are
set forth in the Contract Documents.
A. City’s Project Representative will make visits to the Site at intervals appropriate to the various
stages of construction as City deems necessary in order to observe the progress that has been
made and the quality of the various aspects of Contractor’s executed Work. Based on
information obtained during such visits and observations, City’s Project Representative will
determine, in general, if the Work is proceeding in accordance with the Contract Documents.
City’s Project Representative will not be required to make exhaustive or continuous inspections
on the Site to check the quality or quantity of the Work. City’s Project Representative’s efforts
will be directed toward providing City a greater degree of confidence that the completed Work
will conform generally to the Contract Documents.
B. City’s Project Representative’s visits and observations are subject to all the limitations on
authority and responsibility in the Contract Documents.
8.02 Authorized Variations in Work
City’s Project Representative may authorize minor variations in the Work from the requirements of
the Contract Documents which do not involve an adjustment in the Contract Price or the Contract
Time and are compatible with the design concept of the completed Project as a functioning whole as
indicated by the Contract Documents. These may be accomplished by a Field Order and will be
binding on City Developer, and also on Contractor, who shall perform the Work involved promptly.
8.03 Rejecting Defective Work
City will have authority to reject Work which City’s Project Representative believes to be defective,
or will not produce a completed Project that conforms to the Contract Documents or that will
prejudice the integrity of the design concept of the completed Project as a functioning whole as
indicated by the Contract Documents. City will have authority to conduct special inspection or
testing of the Work as provided in Article 11, whether or not the Work is fabricated, installed, or
completed.
00 73 10- 28
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 28 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
8.04 Determinations for Work Performed
Contractor will determine the actual quantities and classifications of Work performed. City’s Project
Representative will review with Contractor the preliminary determinations on such matters before
rendering a written recommendation. City’s written decision will be final (except as modified to
reflect changed factual conditions or more accurate data).
ARTICLE 9 – CHANGES IN THE WORK
9.01 Authorized Changes in the Work
A. Without invalidating the Contract and without notice to any surety, City may, at any time or
from time to time, order Extra Work. Upon notice of such Extra Work, Contractor shall
promptly proceed with the Work involved which will be performed under the applicable
conditions of the Contract Documents (except as otherwise specifically provided). Extra Work
shall be memorialized by a Participating Change Order which may or may not precede an order
of Extra work.
B. For minor changes of Work not requiring changes to Contract Time or Contract Price on a
project with City participation, a Field Order may be issued by the City.
9.02 Notification to Surety
If the provisions of any bond require notice to be given to a surety of any change affecting the
general scope of the Work or the provisions of the Contract Documents (including, but not limited
to, Contract Price or Contract Time), the giving of any such notice will be Contractor’s
responsibility. The amount of each applicable bond will be adjusted by the Contractor to reflect the
effect of any such change.
ARTICLE 10 – CHANGE OF CONTRACT PRICE; CHANGE OF CONTRACT TIME
10.01 Change of Contract Price
A. The Contract Price may only be changed by a Participating Change Order for projects with City
participation.
10.02 Change of Contract Time
A. The Contract Time may only be changed by a Participating Change Order for projects with City
participation.
10.03 Delays
A. If Contractor is delayed, City shall not be liable to Contractor for any claims, costs, losses, or
damages (including but not limited to all fees and charges of engineers, architects, attorneys, and
other professionals and all court or arbitration or other dispute resolution costs) sustained by
Contractor on or in connection with any other project or anticipated project.
00 73 10- 29
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 29 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
ARTICLE 11 – TESTS AND INSPECTIONS; CORRECTION, REMOVAL OR ACCEPTANCE OF
DEFECTIVE WORK
11.01 Notice of Defects
Notice of all defective Work of which City has actual knowledge will be given to Contractor.
Defective Work may be rejected, corrected, or accepted as provided in this Article 13.
11.02 Access to Work
City, independent testing laboratories, and governmental agencies with jurisdictional interests will
have access to the Site and the Work at reasonable times for their observation, inspection, and
testing. Contractor shall provide them proper and safe conditions for such access and advise them of
Contractor’s safety procedures and programs so that they may comply therewith as applicable.
11.03 Tests and Inspections
A. Contractor shall give City timely notice of readiness of the Work for all required inspections,
tests, or approvals and shall cooperate with inspection and testing personnel to facilitate required
inspections or tests.
B. If Contract Documents, Laws or Regulations of any public body having jurisdiction require any
of the Work (or part thereof) to be inspected, tested, or approved, Contractor shall assume full
responsibility for arranging and obtaining such independent inspections, tests, retests or
approvals, pay all costs in connection therewith, and furnish City the required certificates of
inspection or approval; excepting, however, those fees specifically identified in the
Supplementary Conditions or any Texas Department of Licensure and Regulation (TDLR)
inspections, which shall be paid as described in the Supplementary Conditions.
C. Contractor shall be responsible for arranging and obtaining and shall pay all costs in connection
with any inspections, tests, re-tests, or approvals required for City’s acceptance of materials or
equipment to be incorporated in the Work; or acceptance of materials, mix designs, or equipment
submitted for approval prior to Contractor’s purchase thereof for incorporation in the Work.
Such inspections, tests, re-tests, or approvals shall be performed by organizations approved by
City.
D. City may arrange for the services of an independent testing laboratory (“Testing Lab”) to
perform any inspections or tests (“Testing”) for any part of the Work, as determined solely by
City.
1. City will coordinate such Testing to the extent possible, with Contractor;
2. Should any Testing under this Section 11.03 D result in a “fail”, “did not pass” or other
similar negative result, the Contractor shall be responsible for paying for any and all retests.
Contractor’s cancellation without cause of City initiated Testing shall be deemed a negative
result and require a retest.
00 73 10- 30
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 30 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
3. Any amounts owed for any retest under this Section 11.03 D shall be paid directly to the
Testing Lab by Contractor. City will forward all invoices for retests to
Developer/Contractor.
4. If Contractor fails to pay the Testing Lab, City will not issue a letter of Final Acceptance
until the Testing Lab is Paid
E. If any Work (or the work of others) that is to be inspected, tested, or approved is covered by
Contractor without written concurrence of City, Contractor shall, if requested by City, uncover
such Work for observation.
11.04 Uncovering Work
A. If any Work is covered contrary to the Contract Documents or specific instructions by the City, it
must, if requested by City, be uncovered for City’s observation and replaced at Contractor’s
expense.
11.05 City May Stop the Work
If the Work is defective, or Contractor fails to supply sufficient skilled workers or suitable materials
or equipment, or fails to perform the Work in such a way that the completed Work will conform to
the Contract Documents, City may order Contractor to stop the Work, or any portion thereof, until
the cause for such order has been eliminated; however, this right of City to stop the Work shall not
give rise to any duty on the part of City to exercise this right for the benefit of Contractor, any
Subcontractor, any Supplier, any other individual or entity, or any surety for, or employee or agent
of any of them.
11.06 Correction or Removal of Defective Work
A. Promptly after receipt of written notice, Contractor shall correct all defective Work pursuant to
an acceptable schedule, whether or not fabricated, installed, or completed, or, if the Work has
been rejected by City, remove it from the Project and replace it with Work that is not defective.
Contractor shall pay all claims, costs, additional testing, losses, and damages (including but not
limited to all fees and charges of engineers, architects, attorneys, and other professionals and all
court or arbitration or other dispute resolution costs) arising out of or relating to such correction
or removal (including but not limited to all costs of repair or replacement of work of others).
Failure to require the removal of any defective Work shall not constitute acceptance of such
Work.
B. When correcting defective Work under the terms of this Paragraph 11.06 or Paragraph 11.07,
Contractor shall take no action that would void or otherwise impair City’s special warranty and
guarantee, if any, on said Work.
11.07 Correction Period
A. If within two (2) years after the date of Final Acceptance (or such longer period of time as may
be prescribed by the terms of any applicable special guarantee required by the Contract
00 73 10- 31
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 31 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
Documents), any Work is found to be defective, or if the repair of any damages to the land or
areas made available for Contractor’s use by City or permitted by Laws and Regulations as
contemplated in Paragraph 5.10.A is found to be defective, Contractor shall promptly, without
cost to City and in accordance with City’s written instructions:
1. repair such defective land or areas; or
2. correct such defective Work; or
3. if the defective Work has been rejected by City, remove it from the Project and replace it
with Work that is not defective, and
4. satisfactorily correct or repair or remove and replace any damage to other Work, to the work
of others or other land or areas resulting therefrom.
B. If Contractor does not promptly comply with the terms of City’s written instructions, or in an
emergency where delay would cause serious risk of loss or damage, City may have the defective
Work corrected or repaired or may have the rejected Work removed and replaced. All claims,
costs, losses, and damages (including but not limited to all fees and charges of engineers,
architects, attorneys, and other professionals and all court or other dispute resolution costs)
arising out of or relating to such correction or repair or such removal and replacement (including
but not limited to all costs of repair or replacement of work of others) will be paid by Contractor.
C. Where defective Work (and damage to other Work resulting therefrom) has been corrected or
removed and replaced under this Paragraph 11.07, the correction period hereunder with respect
to such Work may be required to be extended for an additional period of one year after the end
of the initial correction period. City shall provide 30 days written notice to Contractor and
Developer should such additional warranty coverage be required. Contractor’s obligations under
this Paragraph 11.07 are in addition to any other obligation or warranty. The provisions of this
Paragraph 11.07 shall not be construed as a substitute for, or a waiver of, the provisions of any
applicable statute of limitation or repose.
11.08 City May Correct Defective Work
A. If Contractor fails within a reasonable time after written notice from City to correct defective
Work, or to remove and replace rejected Work as required by City in accordance with Paragraph
11.06.A, or if Contractor fails to perform the Work in accordance with the Contract Documents,
or if Contractor fails to comply with any other provision of the Contract Documents, City may,
after seven (7) days written notice to Contractor and the Developer, correct, or remedy any such
deficiency.
B. In exercising the rights and remedies under this Paragraph 11.09, City shall proceed
expeditiously. In connection with such corrective or remedial action, City may exclude
Contractor from all or part of the Site, take possession of all or part of the Work and suspend
Contractor’s services related thereto, and incorporate in the Work all materials and equipment
incorporated in the Work, stored at the Site or for which City has paid Contractor but which are
00 73 10- 32
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 32 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
stored elsewhere. Contractor shall allow City, City’s representatives, agents, consultants,
employees, and City’s other contractors, access to the Site to enable City to exercise the rights
and remedies under this Paragraph.
C. All claims, costs, losses, and damages (including but not limited to all fees and charges of
engineers, architects, attorneys, and other professionals and all court or other dispute resolution
costs) incurred or sustained by City in exercising the rights and remedies under this Paragraph
13.09 will be charged against Contractor, and a Change Order will be issued incorporating the
necessary revisions in the Contract Documents with respect to the Work; and City shall be
entitled to an appropriate decrease in the Contract Price.
D. Contractor shall not be allowed an extension of the Contract Time because of any delay in the
performance of the Work attributable to the exercise of City’s rights and remedies under this
Paragraph 11.09.
ARTICLE 12 – COMPLETION
12.01 Contractor’s Warranty of Title
Contractor warrants and guarantees that title to all Work, materials, and equipment covered by any
Application for Payment will pass to City no later than the time of Final Acceptance and shall be
free and clear of all Liens.
12.02 Partial Utilization
A. Prior to Final Acceptance of all the Work, City may use or occupy any substantially completed
part of the Work which has specifically been identified in the Contract Documents, or which
City, determines constitutes a separately functioning and usable part of the Work that can be
used by City for its intended purpose without significant interference with Contractor’s
performance of the remainder of the Work. City at any time may notify Contractor in writing to
permit City to use or occupy any such part of the Work which City determines to be ready for its
intended use, subject to the following conditions:
1. Contractor at any time may notify City in writing that Contractor considers any such part of
the Work ready for its intended use.
2. Within a reasonable time after notification as enumerated in Paragraph 14.05.A.1, City and
Contractor shall make an inspection of that part of the Work to determine its status of
completion. If City does not consider that part of the Work to be substantially complete, City
will notify Contractor in writing giving the reasons therefor.
3. Partial Utilization will not constitute Final Acceptance by City.
12.03 Final Inspection
A. Upon written notice from Contractor that the entire Work is complete in accordance with the
Contract Documents:
00 73 10- 33
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 33 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
1. within 10 days, City will schedule a Final Inspection with Contractor.
2. City will notify Contractor in writing of all particulars in which this inspection reveals that
the Work is incomplete or defective. Contractor shall immediately take such measures as are
necessary to complete such Work or remedy such deficiencies.
12.04 Final Acceptance
A. Upon completion by Contractor to City’s satisfaction, of any additional Work identified in the
Final Inspection, City will issue to Contractor a letter of Final Acceptance upon the satisfaction
of the following:
1. All documentation called for in the Contract Documents, including but not limited to the
evidence of insurance required by Paragraph 5.03;
2. consent of the surety, if any, to Final Acceptance;
3. a list of all pending or released Damage Claims against City that Contractor believes are
unsettled; and
4. affidavits of payments and complete and legally effective releases or waivers (satisfactory to
City) of all Lien rights arising out of or Liens filed in connection with the Work.
5. after all Damage Claims have been resolved:
a. directly by the Contractor or;
b. Contractor provides evidence that the Damage Claim has been reported to Contractor’s
insurance provider for resolution.
6. Issuing Final Acceptance by the City shall not relieve the Contractor of any guarantees or
other requirements of the Contract Documents which specifically continue thereafter.
ARTICLE 13 – SUSPENSION OF WORK
13.01 City May Suspend Work
A. At any time and without cause, City may suspend the Work or any portion thereof by written
notice to Contractor and which may fix the date on which Work will be resumed. Contractor
shall resume the Work on the date so fixed. During temporary suspension of the Work covered
by these Contract Documents, for any reason, the City will stop contract time on City
participation projects.
B. Should the Contractor not be able to complete a portion of the Project due to causes beyond the
control of and without the fault or negligence of the Contractor, and should it be determined by
mutual consent of the Contractor and City that a solution to allow construction to proceed is not
00 73 10- 34
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 34 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
available within a reasonable period of time, Contractor may request an extension in Contract
Time, directly attributable to any such suspension.
C. If it should become necessary to suspend the Work for an indefinite period, the Contractor shall
store all materials in such a manner that they will not obstruct or impede the public unnecessarily
nor become damaged in any way, and he shall take every precaution to prevent damage or
deterioration of the work performed; he shall provide suitable drainage about the work, and erect
temporary structures where necessary.
ARTICLE 14 – MISCELLANEOUS
14.01 Giving Notice
A. Whenever any provision of the Contract Documents requires the giving of written notice, it will
be deemed to have been validly given if:
1. delivered in person to the individual or to a member of the firm or to an officer of the
corporation for whom it is intended; or
2. delivered at or sent by registered or certified mail, postage prepaid, to the last business
address known to the giver of the notice.
B. Business address changes must be promptly made in writing to the other party.
C. Whenever the Contract Documents specifies giving notice by electronic means such electronic
notice shall be deemed sufficient upon confirmation of receipt by the receiving party.
14.02 Computation of Times
When any period of time is referred to in the Contract Documents by days, it will be computed to
exclude the first and include the last day of such period. If the last day of any such period falls on a
Saturday or Sunday or on a day made a legal holiday the next Working Day shall become the last
day of the period.
14.03 Cumulative Remedies
The duties and obligations imposed by these General Conditions and the rights and remedies
available hereunder to the parties hereto are in addition to, and are not to be construed in any way as
a limitation of, any rights and remedies available to any or all of them which are otherwise imposed
or available by Laws or Regulations, by special warranty or guarantee, or by other provisions of the
Contract Documents. The provisions of this Paragraph will be as effective as if repeated specifically
in the Contract Documents in connection with each particular duty, obligation, right, and remedy to
which they apply.
00 73 10- 35
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 35 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
14.04 Survival of Obligations
All representations, indemnifications, warranties, and guarantees made in, required by, or given in
accordance with the Contract Documents, as well as all continuing obligations indicated in the
Contract Documents, will survive final payment, completion, and acceptance of the Work or
termination or completion of the Contract or termination of the services of Contractor.
14.05 Headings
Article and paragraph headings are inserted for convenience only and do not constitute parts of these
General Conditions.
01 11 00 - 1
DAP SUMMARY OF WORK
Page 1 of 3
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – Developer Awarded Projects [Insert Project Number]
Revised December 20, 2012
SECTION 01 11 00
SUMMARY OF WORK
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Summary of Work to be performed in accordance with the Contract Documents
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the Contract
2. Division 1 - General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. Work Covered by Contract Documents
1. Work is to include furnishing all labor, materials, and equipment, and performing
all Work necessary for this construction project as detailed in the Drawings and
Specifications.
B. Subsidiary Work
1. Any and all Work specifically governed by documentary requirements for the
project, such as conditions imposed by the Drawings or Contract Documents in
which no specific item for bid has been provided for in the Proposal and the item is
not a typical unit bid item included on the standard bid item list, then the item shall
be considered as a subsidiary item of Work, the cost of which shall be included in
the price bid in the Proposal for various bid items.
C. Use of Premises
1. Coordinate uses of premises under direction of the City.
2. Assume full responsibility for protection and safekeeping of materials and
equipment stored on the Site.
3. Use and occupy only portions of the public streets and alleys, or other public places
or other rights-of-way as provided for in the ordinances of the City, as shown in the
Contract Documents, or as may be specifically authorized in writing by the City.
a. A reasonable amount of tools, materials, and equipment for construction
purposes may be stored in such space, but no more than is necessary to avoid
delay in the construction operations.
01 11 00 - 2
DAP SUMMARY OF WORK
Page 2 of 3
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – Developer Awarded Projects [Insert Project Number]
Revised December 20, 2012
b. Excavated and waste materials shall be stored in such a way as not to interfere
with the use of spaces that may be designated to be left free and unobstructed
and so as not to inconvenience occupants of adjacent property.
c. If the street is occupied by railroad tracks, the Work shall be carried on in such
manner as not to interfere with the operation of the railroad.
1) All Work shall be in accordance with railroad requirements set forth in
Division 0 as well as the railroad permit.
D. Work within Easements
1. Do not enter upon private property for any purpose without having previously
obtained permission from the owner of such property.
2. Do not store equipment or material on private property unless and until the
specified approval of the property owner has been secured in writing by the
Contractor and a copy furnished to the City.
3. Unless specifically provided otherwise, clear all rights-of-way or easements of
obstructions which must be removed to make possible proper prosecution of the
Work as a part of the project construction operations.
4. Preserve and use every precaution to prevent damage to, all trees, shrubbery, plants,
lawns, fences, culverts, curbing, and all other types of structures or improvements,
to all water, sewer, and gas lines, to all conduits, overhead pole lines, or
appurtenances thereof, including the construction of temporary fences and to all
other public or private property adjacent to the Work.
5. Notify the proper representatives of the owners or occupants of the public or private
lands of interest in lands which might be affected by the Work.
a. Such notice shall be made at least 48 hours in advance of the beginning of the
Work.
b. Notices shall be applicable to both public and private utility companies and any
corporation, company, individual, or other, either as owners or occupants,
whose land or interest in land might be affected by the Work.
c. Be responsible for all damage or injury to property of any character resulting
from any act, omission, neglect, or misconduct in the manner or method or
execution of the Work, or at any time due to defective work, material, or
equipment.
6. Fence
a. Restore all fences encountered and removed during construction of the Project
to the original or a better than original condition.
b. Erect temporary fencing in place of the fencing removed whenever the Work is
not in progress and when the site is vacated overnight, and/or at all times to
provide site security.
c. The cost for all fence work within easements, including removal, temporary
closures and replacement, shall be subsidiary to the various items bid in the
project proposal, unless a bid item is specifically provided in the proposal.
01 11 00 - 3
DAP SUMMARY OF WORK
Page 3 of 3
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – Developer Awarded Projects [Insert Project Number]
Revised December 20, 2012
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
01 25 00 - 1
DAP SUBSTITUTION PROCEDURES
Page 1 of 4
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised August 30, 2013
SECTION 01 25 00
SUBSTITUTION PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. The procedure for requesting the approval of substitution of a product that is not
equivalent to a product which is specified by descriptive or performance criteria or
defined by reference to 1 or more of the following:
a. Name of manufacturer
b. Name of vendor
c. Trade name
d. Catalog number
2. Substitutions are not "or-equals".
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various items bid. No
separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. Request for Substitution - General
1. Within 30 days after award of Contract (unless noted otherwise), the City will
consider formal requests from Contractor for substitution of products in place of
those specified.
2. Certain types of equipment and kinds of material are described in Specifications by
means of references to names of manufacturers and vendors, trade names, or catalog
numbers.
a. When this method of specifying is used, it is not intended to exclude from
consideration other products bearing other manufacturer's or vendor's names,
trade names, or catalog numbers, provided said products are "or-equals," as
determined by City.
3. Other types of equipment and kinds of material may be acceptable substitutions
under the following conditions:
a. Or-equals are unavailable due to strike, discontinued production of products
meeting specified requirements, or other factors beyond control of Contractor;
or,
01 25 00 - 2
DAP SUBSTITUTION PROCEDURES
Page 2 of 4
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised August 30, 2013
b. Contractor proposes a cost and/or time reduction incentive to the City.
1.5 SUBMITTALS
A. See Request for Substitution Form (attached)
B. Procedure for Requesting Substitution
1. Substitution shall be considered only:
a. After award of Contract
b. Under the conditions stated herein
2. Submit 3 copies of each written request for substitution, including:
a. Documentation
1) Complete data substantiating compliance of proposed substitution with
Contract Documents
2) Data relating to changes in construction schedule, when a reduction is
proposed
3) Data relating to changes in cost
b. For products
1) Product identification
a) Manufacturer's name
b) Telephone number and representative contact name
c) Specification Section or Drawing reference of originally specified
product, including discrete name or tag number assigned to original
product in the Contract Documents
2) Manufacturer's literature clearly marked to show compliance of proposed
product with Contract Documents
3) Itemized comparison of original and proposed product addressing product
characteristics including, but not necessarily limited to:
a) Size
b) Composition or materials of construction
c) Weight
d) Electrical or mechanical requirements
4) Product experience
a) Location of past projects utilizing product
b) Name and telephone number of persons associated with referenced
projects knowledgeable concerning proposed product
c) Available field data and reports associated with proposed product
5) Samples
a) Provide at request of City.
b) Samples become the property of the City.
c. For construction methods:
1) Detailed description of proposed method
2) Illustration drawings
C. Approval or Rejection
1. Written approval or rejection of substitution given by the City
2. City reserves the right to require proposed product to comply with color and pattern
of specified product if necessary to secure design intent.
3. In the event the substitution is approved, if a reduction in cost or time results, it will
be documented by Change Order.
01 25 00 - 3
DAP SUBSTITUTION PROCEDURES
Page 3 of 4
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised August 30, 2013
4. Substitution will be rejected if:
a. Submittal is not through the Contractor with his stamp of approval
b. Request is not made in accordance with this Specification Section
c. In the Developer’s opinion, acceptance will require substantial revision of the
original design
d. In the City’s or Developer’s opinion, substitution will not perform adequately
the function consistent with the design intent
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE
A. In making request for substitution or in using an approved product, the Contractor
represents that the Contractor:
1. Has investigated proposed product, and has determined that it is adequate or
superior in all respects to that specified, and that it will perform function for which it
is intended
2. Will provide same guarantee for substitute item as for product specified
3. Will coordinate installation of accepted substitution into Work, to include building
modifications if necessary, making such changes as may be required for Work to be
complete in all respects
4. Waives all claims for additional costs related to substitution which subsequently
arise
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
01 25 00 - 4
DAP SUBSTITUTION PROCEDURES
Page 4 of 4
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised August 30, 2013
EXHIBIT A
REQUEST FOR SUBSTITUTION FORM:
TO:
PROJECT: DATE:
We hereby submit for your consideration the following product instead of the specified item for
the above project:
SECTION PARAGRAPH SPECIFIED ITEM
Proposed Substitution:
Reason for Substitution:
Include complete information on changes to Drawings and/or Specifications which proposed
substitution will require for its proper installation.
Fill in Blanks Below:
A. Will the undersigned contractor pay for changes to the building design, including engineering
and detailing costs caused by the requested substitution?
B. What effect does substitution have on other trades?
C. Differences between proposed substitution and specified item?
D. Differences in product cost or product delivery time?
E. Manufacturer's guarantees of the proposed and specified items are:
Equal Better (explain on attachment)
The undersigned states that the function, appearance and quality are equivalent or superior to the
specified item.
Submitted By: For Use by City
Signature Recommended Recommended
as noted
Firm Not recommended Received late
Address By
Date
Date Remarks
Telephone
For Use by City:
Approved Rejected
City Date
01 31 19 - 1
DAP PRECONSTRUCTION MEETING
Page 1 of 3
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised August 30, 2013
SECTION 01 31 19
PRECONSTRUCTION MEETING
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Provisions for the preconstruction meeting to be held prior to the start of Work to
clarify construction contract administration procedures
B. Deviations from this City of Fort Worth Standard Specification
1. No construction schedule required unless requested by the City.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. Coordination
1. Attend preconstruction meeting.
2. Representatives of Contractor, subcontractors and suppliers attending meetings
shall be qualified and authorized to act on behalf of the entity each represents.
3. Meeting administered by City may be tape recorded.
a. If recorded, tapes will be used to prepare minutes and retained by City for
future reference.
B. Preconstruction Meeting
1. A preconstruction meeting will be held within 14 days after the delivery of the
distribution package to the City.
a. The meeting will be scheduled and administered by the City.
2. The Project Representative will preside at the meeting, prepare the notes of the
meeting and distribute copies of same to all participants who so request by fully
completing the attendance form to be circulated at the beginning of the meeting.
3. Attendance shall include:
a. Developer and Consultant
b. Contractor's project manager
c. Contractor's superintendent
d. Any subcontractor or supplier representatives whom the Contractor may desire
to invite or the City may request
01 31 19 - 2
DAP PRECONSTRUCTION MEETING
Page 2 of 3
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised August 30, 2013
e. Other City representatives
f. Others as appropriate
4. Preliminary Agenda may include:
a. Introduction of Project Personnel
b. General Description of Project
c. Status of right-of-way, utility clearances, easements or other pertinent permits
d. Contractor’s work plan and schedule
e. Contract Time
f. Notice to Proceed
g. Construction Staking
h. Progress Payments
i. Extra Work and Change Order Procedures
j. Field Orders
k. Disposal Site Letter for Waste Material
l. Insurance Renewals
m. Payroll Certification
n. Material Certifications and Quality Control Testing
o. Public Safety and Convenience
p. Documentation of Pre-Construction Conditions
q. Weekend Work Notification
r. Legal Holidays
s. Trench Safety Plans
t. Confined Space Entry Standards
u. Coordination with the City’s representative for operations of existing water
systems
v. Storm Water Pollution Prevention Plan
w. Coordination with other Contractors
x. Early Warning System
y. Contractor Evaluation
z. Special Conditions applicable to the project
aa. Damages Claims
bb. Submittal Procedures
cc. Substitution Procedures
dd. Correspondence Routing
ee. Record Drawings
ff. Temporary construction facilities
gg. MBE/SBE procedures
hh. Final Acceptance
ii. Final Payment
jj. Questions or Comments
01 31 19 - 3
DAP PRECONSTRUCTION MEETING
Page 3 of 3
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised August 30, 2013
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
01 32 33 - 1
DAP PRECONSTRUCTION VIDEO
Page 1 of 2
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised August 30, 2013
SECTION 01 32 33
PRECONSTRUCTION VIDEO
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Administrative and procedural requirements for:
a. Preconstruction Videos
B. Deviations from this City of Fort Worth Standard Specification
1. Though not mandatory, it is highly recommended on infill developer projects.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. Preconstruction Video
1. Produce a preconstruction video of the site/alignment, including all areas in the
vicinity of and to be affected by construction.
a. Provide digital copy of video upon request by the City.
2. Retain a copy of the preconstruction video until the end of the maintenance surety
period.
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
01 32 33 - 2
DAP PRECONSTRUCTION VIDEO
Page 2 of 2
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised August 30, 2013
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
01 33 00 - 1
DAP SUBMITTALS
Page 1 of 8
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised August 30, 2013
SECTION 01 33 00
DAP SUBMITTALS
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. General methods and requirements of submissions applicable to the following
Work-related submittals:
a. Shop Drawings
b. Product Data (including Standard Product List submittals)
c. Samples
d. Mock Ups
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. Coordination
1. Notify the City in writing, at the time of submittal, of any deviations in the
submittals from the requirements of the Contract Documents.
2. Coordination of Submittal Times
a. Prepare, prioritize and transmit each submittal sufficiently in advance of
performing the related Work or other applicable activities, or within the time
specified in the individual Work Sections, of the Specifications.
b. Contractor is responsible such that the installation will not be delayed by
processing times including, but not limited to:
a) Disapproval and resubmittal (if required)
b) Coordination with other submittals
c) Testing
d) Purchasing
e) Fabrication
f) Delivery
g) Similar sequenced activities
c. No extension of time will be authorized because of the Contractor's failure to
transmit submittals sufficiently in advance of the Work.
01 33 00 - 2
DAP SUBMITTALS
Page 2 of 8
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised August 30, 2013
d. Make submittals promptly in accordance with approved schedule, and in such
sequence as to cause no delay in the Work or in the work of any other
contractor.
B. Submittal Numbering
1. When submitting shop drawings or samples, utilize a 9-character submittal cross-
reference identification numbering system in the following manner:
a. Use the first 6 digits of the applicable Specification Section Number.
b. For the next 2 digits number use numbers 01-99 to sequentially number each
initial separate item or drawing submitted under each specific Section number.
c. Last use a letter, A-Z, indicating the resubmission of the same drawing (i.e.
A=2nd submission, B=3rd submission, C=4th submission, etc.). A typical
submittal number would be as follows:
03 30 00-08-B
1) 03 30 00 is the Specification Section for Concrete
2) 08 is the eighth initial submittal under this Specification Section
3) B is the third submission (second resubmission) of that particular shop
drawing
C. Contractor Certification
1. Review shop drawings, product data and samples, including those by
subcontractors, prior to submission to determine and verify the following:
a. Field measurements
b. Field construction criteria
c. Catalog numbers and similar data
d. Conformance with the Contract Documents
2. Provide each shop drawing, sample and product data submitted by the Contractor
with a Certification Statement affixed including:
a. The Contractor's Company name
b. Signature of submittal reviewer
c. Certification Statement
1) “By this submittal, I hereby represent that I have determined and verified
field measurements, field construction criteria, materials, dimensions,
catalog numbers and similar data and I have checked and coordinated each
item with other applicable approved shop drawings."
D. Submittal Format
1. Fold shop drawings larger than 8 ½ inches x 11 inches to 8 ½ inches x 11inches.
2. Bind shop drawings and product data sheets together.
3. Order
a. Cover Sheet
1) Description of Packet
2) Contractor Certification
b. List of items / Table of Contents
c. Product Data /Shop Drawings/Samples /Calculations
E. Submittal Content
1. The date of submission and the dates of any previous submissions
01 33 00 - 3
DAP SUBMITTALS
Page 3 of 8
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised August 30, 2013
2. The Project title and number
3. Contractor identification
4. The names of:
a. Contractor
b. Supplier
c. Manufacturer
5. Identification of the product, with the Specification Section number, page and
paragraph(s)
6. Field dimensions, clearly identified as such
7. Relation to adjacent or critical features of the Work or materials
8. Applicable standards, such as ASTM or Federal Specification numbers
9. Identification by highlighting of deviations from Contract Documents
10. Identification by highlighting of revisions on resubmittals
11. An 8-inch x 3-inch blank space for Contractor and City stamps
F. Shop Drawings
1. As specified in individual Work Sections includes, but is not necessarily limited to:
a. Custom-prepared data such as fabrication and erection/installation (working)
drawings
b. Scheduled information
c. Setting diagrams
d. Actual shopwork manufacturing instructions
e. Custom templates
f. Special wiring diagrams
g. Coordination drawings
h. Individual system or equipment inspection and test reports including:
1) Performance curves and certifications
i. As applicable to the Work
2. Details
a. Relation of the various parts to the main members and lines of the structure
b. Where correct fabrication of the Work depends upon field measurements
1) Provide such measurements and note on the drawings prior to submitting
for approval.
G. Product Data
1. For submittals of product data for products included on the City’s Standard Product
List, clearly identify each item selected for use on the Project.
2. For submittals of product data for products not included on the City’s Standard
Product List, submittal data may include, but is not necessarily limited to:
a. Standard prepared data for manufactured products (sometimes referred to as
catalog data)
1) Such as the manufacturer's product specification and installation
instructions
2) Availability of colors and patterns
3) Manufacturer's printed statements of compliances and applicability
4) Roughing-in diagrams and templates
5) Catalog cuts
6) Product photographs
01 33 00 - 4
DAP SUBMITTALS
Page 4 of 8
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised August 30, 2013
7) Standard wiring diagrams
8) Printed performance curves and operational-range diagrams
9) Production or quality control inspection and test reports and certifications
10) Mill reports
11) Product operating and maintenance instructions and recommended
spare-parts listing and printed product warranties
12) As applicable to the Work
H. Samples
1. As specified in individual Sections, include, but are not necessarily limited to:
a. Physical examples of the Work such as:
1) Sections of manufactured or fabricated Work
2) Small cuts or containers of materials
3) Complete units of repetitively used products color/texture/pattern swatches
and range sets
4) Specimens for coordination of visual effect
5) Graphic symbols and units of Work to be used by the City for independent
inspection and testing, as applicable to the Work
I. Do not start Work requiring a shop drawing, sample or product data nor any material to
be fabricated or installed prior to the approval or qualified approval of such item.
1. Fabrication performed, materials purchased or on-site construction accomplished
which does not conform to approved shop drawings and data is at the Contractor's
risk.
2. The City will not be liable for any expense or delay due to corrections or remedies
required to accomplish conformity.
3. Complete project Work, materials, fabrication, and installations in conformance
with approved shop drawings, applicable samples, and product data.
J. Submittal Distribution
1. Electronic Distribution
a. Confirm development of Project directory for electronic submittals to be
uploaded to City’s Buzzsaw site, or another external FTP site approved by the
City.
b. Shop Drawings
1) Upload submittal to designated project directory and notify appropriate
City representatives via email of submittal posting.
2) Hard Copies
a) 3 copies for all submittals
b) If Contractor requires more than 1 hard copy of Shop Drawings
returned, Contractor shall submit more than the number of copies listed
above.
c. Product Data
1) Upload submittal to designated project directory and notify appropriate
City representatives via email of submittal posting.
2) Hard Copies
a) 3 copies for all submittals
d. Samples
1) Distributed to the Project Representative
2. Hard Copy Distribution (if required in lieu of electronic distribution)
01 33 00 - 5
DAP SUBMITTALS
Page 5 of 8
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised August 30, 2013
a. Shop Drawings
1) Distributed to the City
2) Copies
a) 8 copies for mechanical submittals
b) 7 copies for all other submittals
c) If Contractor requires more than 3 copies of Shop Drawings returned,
Contractor shall submit more than the number of copies listed above.
b. Product Data
1) Distributed to the City
2) Copies
a) 4 copies
c. Samples
1) Distributed to the Project Representative
2) Copies
a) Submit the number stated in the respective Specification Sections.
3. Distribute reproductions of approved shop drawings and copies of approved
product data and samples, where required, to the job site file and elsewhere as
directed by the City.
a. Provide number of copies as directed by the City but not exceeding the number
previously specified.
K. Submittal Review
1. The review of shop drawings, data and samples will be for general conformance
with the design concept and Contract Documents. This is not to be construed as:
a. Permitting any departure from the Contract requirements
b. Relieving the Contractor of responsibility for any errors, including details,
dimensions, and materials
c. Approving departures from details furnished by the City, except as otherwise
provided herein
2. The review and approval of shop drawings, samples or product data by the City
does not relieve the Contractor from his/her responsibility with regard to the
fulfillment of the terms of the Contract.
a. All risks of error and omission are assumed by the Contractor, and the City will
have no responsibility therefore.
3. The Contractor remains responsible for details and accuracy, for coordinating the
Work with all other associated work and trades, for selecting fabrication processes,
for techniques of assembly and for performing Work in a safe manner.
4. If the shop drawings, data or samples as submitted describe variations and show a
departure from the Contract requirements which City finds to be in the interest of
the City and to be so minor as not to involve a change in Contract Price or time for
performance, the City may return the reviewed drawings without noting an
exception.
5. Submittals will be returned to the Contractor under 1 of the following codes:
a. Code 1
1) "NO EXCEPTIONS TAKEN" is assigned when there are no notations or
comments on the submittal.
a) When returned under this code the Contractor may release the
equipment and/or material for manufacture.
b. Code 2
01 33 00 - 6
DAP SUBMITTALS
Page 6 of 8
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised August 30, 2013
1) "EXCEPTIONS NOTED". This code is assigned when a confirmation of
the notations and comments IS NOT required by the Contractor.
a) The Contractor may release the equipment or material for manufacture;
however, all notations and comments must be incorporated into the
final product.
c. Code 3
1) "EXCEPTIONS NOTED/RESUBMIT". This combination of codes is
assigned when notations and comments are extensive enough to require a
resubmittal of the package.
a) The Contractor may release the equipment or material for manufacture;
however, all notations and comments must be incorporated into the
final product.
b) This resubmittal is to address all comments, omissions and
non-conforming items that were noted.
c) Resubmittal is to be received by the City within 15 Calendar Days of
the date of the City's transmittal requiring the resubmittal.
d. Code 4
1) "NOT APPROVED" is assigned when the submittal does not meet the
intent of the Contract Documents.
a) The Contractor must resubmit the entire package revised to bring the
submittal into conformance.
b) It may be necessary to resubmit using a different manufacturer/vendor
to meet the Contract Documents.
6. Resubmittals
a. Handled in the same manner as first submittals
1) Corrections other than requested by the City
2) Marked with revision triangle or other similar method
a) At Contractor’s risk if not marked
b. Submittals for each item will be reviewed no more than twice at the City’s
expense.
1) All subsequent reviews will be performed at times convenient to the City
and at the Contractor's expense, based on the City's or City
Representative’s then prevailing rates.
2) Provide Contractor reimbursement to the City within 30 Calendar Days for
all such fees invoiced by the City.
c. The need for more than 1 resubmission or any other delay in obtaining City's
review of submittals, will not entitle the Contractor to an extension of Contract
Time.
7. Partial Submittals
a. City reserves the right to not review submittals deemed partial, at the City’s
discretion.
b. Submittals deemed by the City to be not complete will be returned to the
Contractor, and will be considered "Not Approved" until resubmitted.
c. The City may at its option provide a list or mark the submittal directing the
Contractor to the areas that are incomplete.
8. If the Contractor considers any correction indicated on the shop drawings to
constitute a change to the Contract Documents, then written notice must be
provided thereof to the Developer at least 7 Calendar Days prior to release for
manufacture.
01 33 00 - 7
DAP SUBMITTALS
Page 7 of 8
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised August 30, 2013
9. When the shop drawings have been completed to the satisfaction of the City, the
Contractor may carry out the construction in accordance therewith and no further
changes therein except upon written instructions from the City.
10. Each submittal, appropriately coded, will be returned within 30 Calendar Days
following receipt of submittal by the City.
L. Mock ups
1. Mock Up units as specified in individual Sections, include, but are not necessarily
limited to, complete units of the standard of acceptance for that type of Work to be
used on the Project. Remove at the completion of the Work or when directed.
M. Qualifications
1. If specifically required in other Sections of these Specifications, submit a P.E.
Certification for each item required.
N. Request for Information (RFI)
1. Contractor Request for additional information
a. Clarification or interpretation of the contract documents
b. When the Contractor believes there is a conflict between Contract Documents
c. When the Contractor believes there is a conflict between the Drawings and
Specifications
1) Identify the conflict and request clarification
2. Sufficient information shall be attached to permit a written response without further
information.
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
01 33 00 - 8
DAP SUBMITTALS
Page 8 of 8
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised August 30, 2013
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
12/20/2012 D. Johnson 1.4.K.8. Working Days modified to Calendar Days
01 45 23
DAP TESTING AND INSPECTION SERVICES
Page 1 of 2
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised March 20, 2020
SECTION 01 45 23
TESTING AND INSPECTION SERVICES
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Testing and inspection services procedures and coordination
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various Items bid.
No separate payment will be allowed for this Item.
a. Contractor is responsible for performing, coordinating, and payment of all
Quality Control testing.
b. City is responsible for performing and payment for first set of Quality
Assurance testing.
1) If the first Quality Assurance test performed by the City fails, the
Contractor is responsible for payment of subsequent Quality Assurance
testing until a passing test occurs.
a) Final acceptance will not be issued by City until all required payments
for testing by Contractor have been paid in full.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. Testing
1. Complete testing in accordance with the Contract Documents.
2. Coordination
a. When testing is required to be performed by the City, notify City, sufficiently
in advance, when testing is needed.
b. When testing is required to be completed by the Contractor, notify City,
sufficiently in advance, that testing will be performed.
3. Distribution of Testing Reports
a. Electronic Distribution
1) Confirm development of Project directory for electronic submittals to be
uploaded to the City’s document management system, or another form of
distribution approved by the City.
01 45 23
DAP TESTING AND INSPECTION SERVICES
Page 2 of 2
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised March 20, 2020
2) Upload test reports to designated project directory and notify appropriate
City representatives via email of submittal posting.
3) Hard Copies
a) 1 copy for all submittals submitted to the Project Representative
b. Hard Copy Distribution (if required in lieu of electronic distribution)
1) Tests performed by City
a) Distribute 1 hard copy to the Contractor
2) Tests performed by the Contractor
a) Distribute 3 hard copies to City’s Project Representative
4. Provide City’s Project Representative with trip tickets for each delivered load of
Concrete or Lime material including the following information:
a. Name of pit
b. Date of delivery
c. Material delivered
B. Inspection
1. Inspection or lack of inspection does not relieve the Contractor from obligation to
perform work in accordance with the Contract Documents.
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
03/20/2020 D.V. Magaña Removed reference to Buzzsaw and noted that electronic submittals be uploaded
through the City’s document management system.
01 55 26 - 1
DAP STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL
Page 1 of 3
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised July 1, 2011
SECTION 01 55 26
STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Administrative procedures for:
a. Street Use Permit
b. Modification of approved traffic control
c. Removal of Street Signs
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
3. Section 34 71 13 – Traffic Control
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various Items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES
A. Reference Standards
1. Reference standards cited in this specification refer to the current reference standard
published at the time of the latest revision date logged at the end of this
specification, unless a date is specifically cited.
2. Texas Manual on Uniform Traffic Control Devices (TMUTCD).
1.4 ADMINISTRATIVE REQUIREMENTS
A. Traffic Control
1. General
a. When traffic control plans are included in the Drawings, provide Traffic
Control in accordance with Drawings and Section 34 71 13.
b. When traffic control plans are not included in the Drawings, prepare traffic
control plans in accordance with Section 34 71 13 and submit to City for
review.
1) Allow minimum 10 working days for review of proposed Traffic Control.
B. Street Use Permit
1. Prior to installation of Traffic Control, a City Street Use Permit is required.
a. To obtain Street Use Permit, submit Traffic Control Plans to City
Transportation and Public Works Department.
01 55 26 - 2
DAP STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL
Page 2 of 3
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised July 1, 2011
1) Allow a minimum of 5 working days for permit review.
2) Contractor’s responsibility to coordinate review of Traffic Control plans for
Street Use Permit, such that construction is not delayed.
C. Modification to Approved Traffic Control
1. Prior to installation traffic control:
a. Submit revised traffic control plans to City Department Transportation and
Public Works Department.
1) Revise Traffic Control plans in accordance with Section 34 71 13.
2) Allow minimum 5 working days for review of revised Traffic Control.
3) It is the Contractor’s responsibility to coordinate review of Traffic Control
plans for Street Use Permit, such that construction is not delayed.
D. Removal of Street Sign
1. If it is determined that a street sign must be removed for construction, then contact
City Transportation and Public Works Department, Signs and Markings Division to
remove the sign.
E. Temporary Signage
1. In the case of regulatory signs, replace permanent sign with temporary sign meeting
requirements of the latest edition of the Texas Manual on Uniform Traffic Control
Devices (MUTCD).
2. Install temporary sign before the removal of permanent sign.
3. When construction is complete, to the extent that the permanent sign can be
reinstalled, contact the City Transportation and Public Works Department, Signs
and Markings Division, to reinstall the permanent sign.
F. Traffic Control Standards
1. Traffic Control Standards can be found on the City’s Buzzsaw website.
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
END OF SECTION
01 55 26 - 3
DAP STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL
Page 3 of 3
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised July 1, 2011
Revision Log
DATE NAME SUMMARY OF CHANGE
01 57 13 - 1
DAP STORM WATER POLLUTION PREVENTION
Page 1 of 3
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised July 1, 2011
SECTION 01 57 13
STORM WATER POLLUTION PREVENTION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Procedures for Storm Water Pollution Prevention Plans
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the
Contract
2. Division 1 – General Requirements
3. Section 31 25 00 – Erosion and Sediment Control
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Construction Activities resulting in less than 1 acre of disturbance
a. Work associated with this Item is considered subsidiary to the various Items
bid. No separate payment will be allowed for this Item.
2. Construction Activities resulting in greater than 1 acre of disturbance
a. Measurement and Payment shall be in accordance with Section 31 25 00.
1.3 REFERENCES
A. Abbreviations and Acronyms
1. Notice of Intent: NOI
2. Notice of Termination: NOT
3. Storm Water Pollution Prevention Plan: SWPPP
4. Texas Commission on Environmental Quality: TCEQ
5. Notice of Change: NOC
A. Reference Standards
1. Reference standards cited in this Specification refer to the current reference
standard published at the time of the latest revision date logged at the end of this
Specification, unless a date is specifically cited.
2. Integrated Storm Management (iSWM) Technical Manual for Construction
Controls
1.4 ADMINISTRATIVE REQUIREMENTS
A. General
1. Contractor is responsible for resolution and payment of any fines issued associated
with compliance to Stormwater Pollution Prevention Plan.
01 57 13 - 2
DAP STORM WATER POLLUTION PREVENTION
Page 2 of 3
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised July 1, 2011
B. Construction Activities resulting in:
1. Less than 1 acre of disturbance
a. Provide erosion and sediment control in accordance with Section 31 25 00 and
Drawings.
2. 1 to less than 5 acres of disturbance
a. Texas Pollutant Discharge Elimination System (TPDES) General Construction
Permit is required
b. Complete SWPPP in accordance with TCEQ requirements
1) TCEQ Small Construction Site Notice Required under general permit
TXR150000
a) Sign and post at job site
b) Prior to Preconstruction Meeting, send 1 copy to City Department of
Transportation and Public Works, Environmental Division, (817) 392-
6088.
2) Provide erosion and sediment control in accordance with:
a) Section 31 25 00
b) The Drawings
c) TXR150000 General Permit
d) SWPPP
e) TCEQ requirements
3. 5 acres or more of Disturbance
a. Texas Pollutant Discharge Elimination System (TPDES) General Construction
Permit is required
b. Complete SWPPP in accordance with TCEQ requirements
1) Prepare a TCEQ NOI form and submit to TCEQ along with required fee
a) Sign and post at job site
b) Send copy to City Department of Transportation and Public Works,
Environmental Division, (817) 392-6088.
2) TCEQ Notice of Change required if making changes or updates to NOI
3) Provide erosion and sediment control in accordance with:
a) Section 31 25 00
b) The Drawings
c) TXR150000 General Permit
d) SWPPP
e) TCEQ requirements
4) Once the project has been completed and all the closeout requirements of
TCEQ have been met a TCEQ Notice of Termination can be submitted.
a) Send copy to City Department of Transportation and Public Works,
Environmental Division, (817) 392-6088.
1.5 SUBMITTALS
A. SWPPP
1. Submit in accordance with Section 01 33 00, except as stated herein.
a. Prior to the Preconstruction Meeting, submit a draft copy of SWPPP to the City
as follows:
1) 1 copy to the City Project Manager
a) City Project Manager will forward to the City Department of
Transportation and Public Works, Environmental Division for review
01 57 13 - 3
DAP STORM WATER POLLUTION PREVENTION
Page 3 of 3
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised July 1, 2011
B. Modified SWPPP
1. If the SWPPP is revised during construction, resubmit modified SWPPP to the City
in accordance with Section 01 33 00.
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
01 60 00
DAP PRODUCT REQUIREMENTS
Page 1 of 2
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised March 20, 2020
SECTION 01 60 00
PRODUCT REQUIREMENTS
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. References for Product Requirements and City Standard Products List
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
1.2 PRICE AND PAYMENT PROCEDURES [NOT USED]
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A list of City approved products for use is available through the City’s website at:
https://apps.fortworthtexas.gov/ProjectResources/ and following the directory
path: 02 - Construction Documents\Standard Products List
A. Only products specifically included on City’s Standard Product List in these Contract
Documents shall be allowed for use on the Project.
1. Any subsequently approved products will only be allowed for use upon specific
approval by the City.
B. Any specific product requirements in the Contract Documents supersede similar
products included on the City’s Standard Product List.
1. The City reserves the right to not allow products to be used for certain projects even
though the product is listed on the City’s Standard Product List.
C. Although a specific product is included on City’s Standard Product List, not all
products from that manufacturer are approved for use, including but not limited to, that
manufacturer’s standard product.
D. See Section 01 33 00 for submittal requirements of Product Data included on City’s
Standard Product List.
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
01 60 00
DAP PRODUCT REQUIREMENTS
Page 2 of 2
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised March 20, 2020
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
10/12/12 D. Johnson Modified Location of City’s Standard Product List
4/7/2014 M.Domenech Revised for DAP application
03/20/2020 D.V. Magaña Removed reference to Buzzsaw and noted that the City approved products list is
accessible through the City’s website.
01 66 00 - 1
DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS
Page 1 of 4
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised April 7, 2014
SECTION 01 66 00
PRODUCT STORAGE AND HANDLING REQUIREMENTS
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Scheduling of product delivery
2. Packaging of products for delivery
3. Protection of products against damage from:
a. Handling
b. Exposure to elements or harsh environments
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various Items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED]
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY AND HANDLING
A. Delivery Requirements
1. Schedule delivery of products or equipment as required to allow timely installation
and to avoid prolonged storage.
2. Provide appropriate personnel and equipment to receive deliveries.
3. Delivery trucks will not be permitted to wait extended periods of time on the Site
for personnel or equipment to receive the delivery.
01 66 00 - 2
DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS
Page 2 of 4
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised April 7, 2014
4. Deliver products or equipment in manufacturer's original unbroken cartons or other
containers designed and constructed to protect the contents from physical or
environmental damage.
5. Clearly and fully mark and identify as to manufacturer, item and installation
location.
6. Provide manufacturer's instructions for storage and handling.
B. Handling Requirements
1. Handle products or equipment in accordance with these Contract Documents and
manufacturer’s recommendations and instructions.
C. Storage Requirements
1. Store materials in accordance with manufacturer’s recommendations and
requirements of these Specifications.
2. Make necessary provisions for safe storage of materials and equipment.
a. Place loose soil materials and materials to be incorporated into Work to prevent
damage to any part of Work or existing facilities and to maintain free access at
all times to all parts of Work and to utility service company installations in
vicinity of Work.
3. Keep materials and equipment neatly and compactly stored in locations that will
cause minimum inconvenience to other contractors, public travel, adjoining owners,
tenants and occupants.
a. Arrange storage to provide easy access for inspection.
4. Restrict storage to areas available on construction site for storage of material and
equipment as shown on Drawings, or approved by City’s Project Representative.
5. Provide off-site storage and protection when on-site storage is not adequate.
a. Provide addresses of and access to off-site storage locations for inspection by
City’s Project Representative.
6. Do not use lawns, grass plots or other private property for storage purposes without
written permission of owner or other person in possession or control of premises.
7. Store in manufacturers’ unopened containers.
8. Neatly, safely and compactly stack materials delivered and stored along line of
Work to avoid inconvenience and damage to property owners and general public
and maintain at least 3 feet from fire hydrant.
9. Keep public and private driveways and street crossings open.
10. Repair or replace damaged lawns, sidewalks, streets or other improvements to
satisfaction of City’s Project Representative.
a. Total length which materials may be distributed along route of construction at
one time is 1,000 linear feet, unless otherwise approved in writing by City’s
Project Representative.
01 66 00 - 3
DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS
Page 3 of 4
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised April 7, 2014
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION
3.1 INSTALLERS [NOT USED]
3.2 EXAMINATION [NOT USED]
3.3 PREPARATION [NOT USED]
3.4 ERECTION [NOT USED]
3.5 REPAIR / RESTORATION [NOT USED]
3.6 RE-INSTALLATION [NOT USED]
3.7 FIELD [OR] SITE QUALITY CONTROL
A. Tests and Inspections
1. Inspect all products or equipment delivered to the site prior to unloading.
B. Non-Conforming Work
1. Reject all products or equipment that are damaged, used or in any other way
unsatisfactory for use on the project.
3.8 SYSTEM STARTUP [NOT USED]
3.9 ADJUSTING [NOT USED]
3.10 CLEANING [NOT USED]
3.11 CLOSEOUT ACTIVITIES [NOT USED]
3.12 PROTECTION
A. Protect all products or equipment in accordance with manufacturer's written directions.
B. Store products or equipment in location to avoid physical damage to items while in
storage.
C. Protect equipment from exposure to elements and keep thoroughly dry if required by
the manufacturer.
3.13 MAINTENANCE [NOT USED]
3.14 ATTACHMENTS [NOT USED]
END OF SECTION
01 66 00 - 4
DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS
Page 4 of 4
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised April 7, 2014
Revision Log
DATE NAME SUMMARY OF CHANGE
4/7/2014 M.Domenech Revised for DAP application
01 70 00 - 1
DAP MOBILIZATION AND REMOBILIZATION
Page 1 of 4
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised April 7, 2014
SECTION 01 70 00
MOBILIZATION AND REMOBILIZATION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Mobilization and Demobilization
a. Mobilization
1) Transportation of Contractor’s personnel, equipment, and operating supplies
to the Site
2) Establishment of necessary general facilities for the Contractor’s operation
at the Site
3) Premiums paid for performance and payment bonds
4) Transportation of Contractor’s personnel, equipment, and operating supplies
to another location within the designated Site
5) Relocation of necessary general facilities for the Contractor’s operation
from 1 location to another location on the Site.
b. Demobilization
1) Transportation of Contractor’s personnel, equipment, and operating supplies
away from the Site including disassembly
2) Site Clean-up
3) Removal of all buildings and/or other facilities assembled at the Site for this
Contract
c. Mobilization and Demobilization do not include activities for specific items of
work that are for which payment is provided elsewhere in the contract.
2. Remobilization
a. Remobilization for Suspension of Work specifically required in the Contract
Documents or as required by City includes:
1) Demobilization
a) Transportation of Contractor’s personnel, equipment, and operating
supplies from the Site including disassembly or temporarily securing
equipment, supplies, and other facilities as designated by the Contract
Documents necessary to suspend the Work.
b) Site Clean-up as designated in the Contract Documents
2) Remobilization
a) Transportation of Contractor’s personnel, equipment, and operating
supplies to the Site necessary to resume the Work.
b) Establishment of necessary general facilities for the Contractor’s
operation at the Site necessary to resume the Work.
3) No Payments will be made for:
a) Mobilization and Demobilization from one location to another on the
Site in the normal progress of performing the Work.
b) Stand-by or idle time
c) Lost profits
3. Mobilizations and Demobilization for Miscellaneous Projects
a. Mobilization and Demobilization
01 70 00 - 2
DAP MOBILIZATION AND REMOBILIZATION
Page 2 of 4
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised April 7, 2014
1) Mobilization shall consist of the activities and cost on a Work Order basis
necessary for:
a) Transportation of Contractor’s personnel, equipment, and operating
supplies to the Site for the issued Work Order.
b) Establishment of necessary general facilities for the Contractor’s
operation at the Site for the issued Work Order
2) Demobilization shall consist of the activities and cost necessary for:
a) Transportation of Contractor’s personnel, equipment, and operating
supplies from the Site including disassembly for each issued Work
Order
b) Site Clean-up for each issued Work Order
c) Removal of all buildings or other facilities assembled at the Site for
each Work Oder
b. Mobilization and Demobilization do not include activities for specific items of
work for which payment is provided elsewhere in the contract.
4. Emergency Mobilizations and Demobilization for Miscellaneous Projects
a. A Mobilization for Miscellaneous Projects when directed by the City and the
mobilization occurs within 24 hours of the issuance of the Work Order.
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Mobilization and Demobilization
a. Measure
1) This Item is considered subsidiary to the various Items bid.
b. Payment
1) The work performed and materials furnished in accordance with this Item
are subsidiary to the various Items bid and no other compensation will be
allowed.
2. Remobilization for suspension of Work as specifically required in the Contract
Documents
a. Measurement
1) Measurement for this Item shall be per each remobilization performed.
b. Payment
1) The work performed and materials furnished in accordance with this Item
and measured as provided under “Measurement” will be paid for at the unit
price per each “Specified Remobilization” in accordance with Contract
Documents.
c. The price shall include:
1) Demobilization as described in Section 1.1.A.2.a.1)
2) Remobilization as described in Section 1.1.A.2.a.2)
d. No payments will be made for standby, idle time, or lost profits associated this
Item.
01 70 00 - 3
DAP MOBILIZATION AND REMOBILIZATION
Page 3 of 4
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised April 7, 2014
3. Remobilization for suspension of Work as required by City
a. Measurement and Payment
1) This shall be submitted as a Contract Claim in accordance with Article 10
of Section 00 72 00.
2) No payments will be made for standby, idle time, or lost profits associated
with this Item.
4. Mobilizations and Demobilizations for Miscellaneous Projects
a. Measurement
1) Measurement for this Item shall be for each Mobilization and
Demobilization required by the Contract Documents
b. Payment
1) The Work performed and materials furnished in accordance with this Item
and measured as provided under “Measurement” will be paid for at the unit
price per each “Work Order Mobilization” in accordance with Contract
Documents. Demobilization shall be considered subsidiary to mobilization
and shall not be paid for separately.
c. The price shall include:
1) Mobilization as described in Section 1.1.A.3.a.1)
2) Demobilization as described in Section 1.1.A.3.a.2)
d. No payments will be made for standby, idle time, or lost profits associated this
Item.
5. Emergency Mobilizations and Demobilizations for Miscellaneous Projects
a. Measurement
1) Measurement for this Item shall be for each Mobilization and
Demobilization required by the Contract Documents
b. Payment
1) The Work performed and materials furnished in accordance with this Item
and measured as provided under “Measurement” will be paid for at the unit
price per each “Work Order Emergency Mobilization” in accordance with
Contract Documents. Demobilization shall be considered subsidiary to
mobilization and shall not be paid for separately.
c. The price shall include
1) Mobilization as described in Section 1.1.A.4.a)
2) Demobilization as described in Section 1.1.A.3.a.2)
d. No payments will be made for standby, idle time, or lost profits associated this
Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED]
1.5 SUBMITTALS [NOT USED]
1.6 INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
01 70 00 - 4
DAP MOBILIZATION AND REMOBILIZATION
Page 4 of 4
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised April 7, 2014
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
4/7/2014 M.Domenech Revised for DAP application
01 71 23 - 1
DAP CONSTRUCTION STAKING AND SURVEY
Page 1 of 4
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised April 7, 2014
SECTION 01 71 23
CONSTRUCTION STAKING AND SURVEY
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Requirements for construction staking and construction survey
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Construction Staking
a. Measurement
1) This Item is considered subsidiary to the various Items bid.
b. Payment
1) The work performed and the materials furnished in accordance with this
Item are subsidiary to the various Items bid and no other compensation will
be allowed.
2. Construction Survey
a. Measurement
1) This Item is considered subsidiary to the various Items bid.
b. Payment
1) The work performed and the materials furnished in accordance with this
Item are subsidiary to the various Items bid and no other compensation will
be allowed.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED]
1.5 SUBMITTALS
A. Submittals, if required, shall be in accordance with Section 01 33 00.
B. All submittals shall be approved by the City prior to delivery.
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS
A. Certificates
1. Provide certificate certifying that elevations and locations of improvements are in
conformance or non-conformance with requirements of the Contract Documents.
a. Certificate must be sealed by a registered professional land surveyor in the
State of Texas.
01 71 23 - 2
DAP CONSTRUCTION STAKING AND SURVEY
Page 2 of 4
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised April 7, 2014
B. Field Quality Control Submittals
1. Documentation verifying accuracy of field engineering work.
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE
A. Construction Staking
1. Construction staking will be performed by the City.
2. Coordination
a. Contact City’s Project Representative at least 2 weeks in advance for
scheduling of Construction Staking.
b. It is the Contractor’s responsibility to coordinate staking such that construction
activities are not delayed or negatively impacted.
3. General
a. Contractor is responsible for preserving and maintaining stakes furnished by
City.
b. If in the opinion of the City, a sufficient number of stakes or markings have
been lost, destroyed or disturbed, by Contractor’s neglect, such that the
contracted Work cannot take place, then the Contractor will be required to pay
the City for new staking with a 25 percent markup. The cost for staking will be
deducted from the payment due to the Contractor for the Project.
B. Construction Survey
1. Construction Survey will be performed by the City.
2. Coordination
a. Contractor to verify that control data established in the design survey remains
intact.
b. Coordinate with the City prior to field investigation to determine which
horizontal and vertical control data will be required for construction survey.
c. It is the Contractor’s responsibility to coordinate Construction Survey such that
construction activities are not delayed or negatively impacted.
d. Notify City if any control data needs to be restored or replaced due to damage
caused during construction operations.
1) City shall perform replacements and/or restorations.
3. General
a. Construction survey will be performed in order to maintain complete and
accurate logs of control and survey work as it progresses for Project Records.
b. The Contractor will need to ensure coordination is maintained with the City to
perform construction survey to obtain construction features, including but not
limited to the following:
1) All Utility Lines
a) Rim and flowline elevations and coordinates for each manhole or
junction structure
2) Water Lines
a) Top of pipe elevations and coordinates for waterlines at the following
locations:
(1) Every 250 linear feet
01 71 23 - 3
DAP CONSTRUCTION STAKING AND SURVEY
Page 3 of 4
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised April 7, 2014
(2) Horizontal and vertical points of inflection, curvature, etc. (All
Fittings)
(3) Cathodic protection test stations
(4) Sampling stations
(5) Meter boxes/vaults (All sizes)
(6) Fire lines
(7) Fire hydrants
(8) Gate valves
(9) Plugs, stubouts, dead-end lines
(10) Air Release valves (Manhole rim and vent pipe)
(11) Blow off valves (Manhole rim and valve lid)
(12) Pressure plane valves
(13) Cleaning wyes
(14) Casing pipe (each end)
b) Storm Sewer
(1) Top of pipe elevations and coordinates at the following locations:
(a) Every 250 linear feet
(b) Horizontal and vertical points of inflection, curvature, etc.
c) Sanitary Sewer
(1) Top of pipe elevations and coordinates for sanitary sewer lines at
the following locations:
(a) Every 250 linear feet
(b) Horizontal and vertical points of inflection, curvature, etc.
(c) Cleanouts
c. Construction survey will be performed in order to maintain complete and
accurate logs of control and survey work associated with meeting or exceeding
the line and grade required by these Specifications.
d. The Contractor will need to ensure coordination is maintained with the City to
perform construction survey and to verify control data, including but not
limited to the following:
1) Established benchmarks and control points provided for the Contractor’s
use are accurate
2) Benchmarks were used to furnish and maintain all reference lines and
grades for tunneling
3) Lines and grades were used to establish the location of the pipe
4) Submit to the City copies of field notes used to establish all lines and
grades and allow the City to check guidance system setup prior to
beginning each tunneling drive.
5) Provide access for the City to verify the guidance system and the line and
grade of the carrier pipe on a daily basis.
6) The Contractor remains fully responsible for the accuracy of the work and
the correction of it, as required.
7) Monitor line and grade continuously during construction.
8) Record deviation with respect to design line and grade once at each pipe
joint and submit daily records to City.
9) If the installation does not meet the specified tolerances, immediately notify
the City and correct the installation in accordance with the Contract
Documents.
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
01 71 23 - 4
DAP CONSTRUCTION STAKING AND SURVEY
Page 4 of 4
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised April 7, 2014
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION
3.1 INSTALLERS [NOT USED]
3.2 EXAMINATION [NOT USED]
3.3 PREPARATION [NOT USED]
3.4 APPLICATION
3.5 REPAIR / RESTORATION [NOT USED]
3.6 RE-INSTALLATION [NOT USED]
3.7 FIELD [OR] SITE QUALITY CONTROL
A. It is the Contractor’s responsibility to maintain all stakes and control data placed by the
City in accordance with this Specification.
B. Do not change or relocate stakes or control data without approval from the City.
3.8 SYSTEM STARTUP [NOT USED]
3.9 ADJUSTING [NOT USED]
3.10 CLEANING [NOT USED]
3.11 CLOSEOUT ACTIVITIES [NOT USED]
3.12 PROTECTION [NOT USED]
3.13 MAINTENANCE [NOT USED]
3.14 ATTACHMENTS [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
4/7/2014 M.Domenech Revised for DAP application
01 74 23 - 1
DAP CLEANING
Page 1 of 4
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised April 7, 2014
SECTION 01 74 23
CLEANING
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Intermediate and final cleaning for Work not including special cleaning of closed
systems specified elsewhere
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
3. Section 32 92 13 – Hydro-Mulching, Seeding and Sodding
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various Items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. Scheduling
1. Schedule cleaning operations so that dust and other contaminants disturbed by
cleaning process will not fall on newly painted surfaces.
2. Schedule final cleaning upon completion of Work and immediately prior to final
inspection.
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 STORAGE, AND HANDLING
A. Storage and Handling Requirements
1. Store cleaning products and cleaning wastes in containers specifically designed for
those materials.
01 74 23 - 2
DAP CLEANING
Page 2 of 4
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised April 7, 2014
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS
2.1 OWNER-FURNISHED [OR] OWNER-SUPPLIEDPRODUCTS [NOT USED]
2.2 MATERIALS
A. Cleaning Agents
1. Compatible with surface being cleaned
2. New and uncontaminated
3. For manufactured surfaces
a. Material recommended by manufacturer
2.3 ACCESSORIES [NOT USED]
2.4 SOURCE QUALITY CONTROL [NOT USED]
PART 3 - EXECUTION
3.1 INSTALLERS [NOT USED]
3.2 EXAMINATION [NOT USED]
3.3 PREPARATION [NOT USED]
3.4 APPLICATION [NOT USED]
3.5 REPAIR / RESTORATION [NOT USED]
3.6 RE-INSTALLATION [NOT USED]
3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED]
3.8 SYSTEM STARTUP [NOT USED]
3.9 ADJUSTING [NOT USED]
3.10 CLEANING
A. General
1. Prevent accumulation of wastes that create hazardous conditions.
2. Conduct cleaning and disposal operations to comply with laws and safety orders of
governing authorities.
3. Do not dispose of volatile wastes such as mineral spirits, oil or paint thinner in
storm or sanitary drains or sewers.
4. Dispose of degradable debris at an approved solid waste disposal site.
5. Dispose of nondegradable debris at an approved solid waste disposal site or in an
alternate manner approved by City and regulatory agencies.
01 74 23 - 3
DAP CLEANING
Page 3 of 4
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised April 7, 2014
6. Handle materials in a controlled manner with as few handlings as possible.
7. Thoroughly clean, sweep, wash and polish all Work and equipment associated with
this project.
8. Remove all signs of temporary construction and activities incidental to construction
of required permanent Work.
9. If project is not cleaned to the satisfaction of the City, the City reserves the right to
have the cleaning completed at the expense of the Contractor.
10. Do not burn on-site.
B. Intermediate Cleaning during Construction
1. Keep Work areas clean so as not to hinder health, safety or convenience of
personnel in existing facility operations.
2. At maximum weekly intervals, dispose of waste materials, debris and rubbish.
3. Confine construction debris daily in strategically located container(s):
a. Cover to prevent blowing by wind
b. Store debris away from construction or operational activities
c. Haul from site at a minimum of once per week
4. Vacuum clean interior areas when ready to receive finish painting.
a. Continue vacuum cleaning on an as-needed basis, until Final Acceptance.
5. Prior to storm events, thoroughly clean site of all loose or unsecured items, which
may become airborne or transported by flowing water during the storm.
C. Exterior (Site or Right of Way) Final Cleaning
1. Remove trash and debris containers from site.
a. Re-seed areas disturbed by location of trash and debris containers in accordance
with Section 32 92 13.
2. Sweep roadway to remove all rocks, pieces of asphalt, concrete or any other object
that may hinder or disrupt the flow of traffic along the roadway.
3. Clean any interior areas including, but not limited to, vaults, manholes, structures,
junction boxes and inlets.
4. If no longer required for maintenance of erosion facilities, and upon approval by
City, remove erosion control from site.
5. Clean signs, lights, signals, etc.
3.11 CLOSEOUT ACTIVITIES [NOT USED]
3.12 PROTECTION [NOT USED]
3.13 MAINTENANCE [NOT USED]
3.14 ATTACHMENTS [NOT USED]
01 74 23 - 4
DAP CLEANING
Page 4 of 4
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised April 7, 2014
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
4/7/2014 M.Domenech Revised for DAP application
01 77 19 - 1
DAP CLOSEOUT REQUIREMENTS
Page 1 of 3
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised April 7, 2014
SECTION 01 77 19
CLOSEOUT REQUIREMENTS
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. The procedure for closing out a contract
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various Items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. Guarantees, Bonds and Affidavits
1. No application for final payment will be accepted until all guarantees, bonds,
certificates, licenses and affidavits required for Work or equipment as specified are
satisfactorily filed with the City.
B. Release of Liens or Claims
1. No application for final payment will be accepted until satisfactory evidence of
release of liens has been submitted to the City.
1.5 SUBMITTALS
A. Submit all required documentation to City’s Project Representative.
01 77 19 - 2
DAP CLOSEOUT REQUIREMENTS
Page 2 of 3
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised April 7, 2014
1.6 INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION
3.1 INSTALLERS [NOT USED]
3.2 EXAMINATION [NOT USED]
3.3 PREPARATION [NOT USED]
3.4 CLOSEOUT PROCEDURE
A. Prior to requesting Final Inspection, submit:
1. Project Record Documents in accordance with Section 01 78 39
2. Operation and Maintenance Data, if required, in accordance with Section 01 78 23
B. Prior to requesting Final Inspection, perform final cleaning in accordance with Section
01 74 23.
C. Final Inspection
1. After final cleaning, provide notice to the City Project Representative that the Work
is completed.
a. The City will make an initial Final Inspection with the Contractor present.
b. Upon completion of this inspection, the City will notify the Contractor, in
writing within 10 business days, of any particulars in which this inspection
reveals that the Work is defective or incomplete.
2. Upon receiving written notice from the City, immediately undertake the Work
required to remedy deficiencies and complete the Work to the satisfaction of the
City.
3. Upon completion of Work associated with the items listed in the City's written
notice, inform the City, that the required Work has been completed. Upon receipt
of this notice, the City, in the presence of the Contractor, will make a subsequent
Final Inspection of the project.
4. Provide all special accessories required to place each item of equipment in full
operation. These special accessory items include, but are not limited to:
a. Specified spare parts
b. Adequate oil and grease as required for the first lubrication of the equipment
c. Initial fill up of all chemical tanks and fuel tanks
d. Light bulbs
e. Fuses
f. Vault keys
g. Handwheels
h. Other expendable items as required for initial start-up and operation of all
equipment
D. Notice of Project Completion
01 77 19 - 3
DAP CLOSEOUT REQUIREMENTS
Page 3 of 3
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised April 7, 2014
1. Once the City Project Representative finds the Work subsequent to Final Inspection
to be satisfactory, the City will issue a Notice of Project Completion (Green Sheet).
E. Supporting Documentation
1. Coordinate with the City Project Representative to complete the following
additional forms:
a. Final Payment Request
b. Statement of Contract Time
c. Affidavit of Payment and Release of Liens
d. Consent of Surety to Final Payment
e. Pipe Report (if required)
f. Contractor’s Evaluation of City
g. Performance Evaluation of Contractor
F. Letter of Final Acceptance
1. Upon review and acceptance of Notice of Project Completion and Supporting
Documentation, in accordance with General Conditions, City will issue Letter of
Final Acceptance and release the Final Payment Request for payment.
3.5 REPAIR / RESTORATION [NOT USED]
3.6 RE-INSTALLATION [NOT USED]
3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED]
3.8 SYSTEM STARTUP [NOT USED]
3.9 ADJUSTING [NOT USED]
3.10 CLEANING [NOT USED]
3.11 CLOSEOUT ACTIVITIES [NOT USED]
3.12 PROTECTION [NOT USED]
3.13 MAINTENANCE [NOT USED]
3.14 ATTACHMENTS [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
4/7/2014 M.Domenech Revised for DAP application
01 78 23 - 1
DAP OPERATION AND MAINTENANCE DATA
Page 1 of 5
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised April 7, 2014
SECTION 01 78 23
OPERATION AND MAINTENANCE DATA
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Product data and related information appropriate for City's maintenance and
operation of products furnished under Contract
2. Such products may include, but are not limited to:
a. Traffic Controllers
b. Irrigation Controllers (to be operated by the City)
c. Butterfly Valves
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various Items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. Schedule
1. Submit manuals in final form to the City within 30 calendar days of product
shipment to the project site.
1.5 SUBMITTALS
A. Submittals shall be in accordance with Section 01 33 00. All submittals shall be
approved by the City prior to delivery.
1.6 INFORMATIONAL SUBMITTALS
A. Submittal Form
1. Prepare data in form of an instructional manual for use by City personnel.
2. Format
a. Size: 8 ½ inches x 11 inches
b. Paper
1) 40 pound minimum, white, for typed pages
2) Holes reinforced with plastic, cloth or metal
c. Text: Manufacturer’s printed data, or neatly typewritten
01 78 23 - 2
DAP OPERATION AND MAINTENANCE DATA
Page 2 of 5
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised April 7, 2014
d. Drawings
1) Provide reinforced punched binder tab, bind in with text
2) Reduce larger drawings and fold to size of text pages.
e. Provide fly-leaf for each separate product, or each piece of operating
equipment.
1) Provide typed description of product, and major component parts of
equipment.
2) Provide indexed tabs.
f. Cover
1) Identify each volume with typed or printed title "OPERATING AND
MAINTENANCE INSTRUCTIONS".
2) List:
a) Title of Project
b) Identity of separate structure as applicable
c) Identity of general subject matter covered in the manual
3. Binders
a. Commercial quality 3-ring binders with durable and cleanable plastic covers
b. When multiple binders are used, correlate the data into related consistent
groupings.
4. If available, provide an electronic form of the O&M Manual.
B. Manual Content
1. Neatly typewritten table of contents for each volume, arranged in systematic order
a. Contractor, name of responsible principal, address and telephone number
b. A list of each product required to be included, indexed to content of the volume
c. List, with each product:
1) The name, address and telephone number of the subcontractor or installer
2) A list of each product required to be included, indexed to content of the
volume
3) Identify area of responsibility of each
4) Local source of supply for parts and replacement
d. Identify each product by product name and other identifying symbols as set
forth in Contract Documents.
2. Product Data
a. Include only those sheets which are pertinent to the specific product.
b. Annotate each sheet to:
1) Clearly identify specific product or part installed
2) Clearly identify data applicable to installation
3) Delete references to inapplicable information
3. Drawings
a. Supplement product data with drawings as necessary to clearly illustrate:
1) Relations of component parts of equipment and systems
2) Control and flow diagrams
b. Coordinate drawings with information in Project Record Documents to assure
correct illustration of completed installation.
c. Do not use Project Record Drawings as maintenance drawings.
4. Written text, as required to supplement product data for the particular installation:
a. Organize in consistent format under separate headings for different procedures.
b. Provide logical sequence of instructions of each procedure.
01 78 23 - 3
DAP OPERATION AND MAINTENANCE DATA
Page 3 of 5
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised April 7, 2014
5. Copy of each warranty, bond and service contract issued
a. Provide information sheet for City personnel giving:
1) Proper procedures in event of failure
2) Instances which might affect validity of warranties or bonds
C. Manual for Materials and Finishes
1. Submit 5 copies of complete manual in final form.
2. Content, for architectural products, applied materials and finishes:
a. Manufacturer's data, giving full information on products
1) Catalog number, size, composition
2) Color and texture designations
3) Information required for reordering special manufactured products
b. Instructions for care and maintenance
1) Manufacturer's recommendation for types of cleaning agents and methods
2) Cautions against cleaning agents and methods which are detrimental to
product
3) Recommended schedule for cleaning and maintenance
3. Content, for moisture protection and weather exposure products:
a. Manufacturer's data, giving full information on products
1) Applicable standards
2) Chemical composition
3) Details of installation
b. Instructions for inspection, maintenance and repair
D. Manual for Equipment and Systems
1. Submit 5 copies of complete manual in final form.
2. Content, for each unit of equipment and system, as appropriate:
a. Description of unit and component parts
1) Function, normal operating characteristics and limiting conditions
2) Performance curves, engineering data and tests
3) Complete nomenclature and commercial number of replaceable parts
b. Operating procedures
1) Start-up, break-in, routine and normal operating instructions
2) Regulation, control, stopping, shut-down and emergency instructions
3) Summer and winter operating instructions
4) Special operating instructions
c. Maintenance procedures
1) Routine operations
2) Guide to "trouble shooting"
3) Disassembly, repair and reassembly
4) Alignment, adjusting and checking
d. Servicing and lubrication schedule
1) List of lubricants required
e. Manufacturer's printed operating and maintenance instructions
f. Description of sequence of operation by control manufacturer
1) Predicted life of parts subject to wear
2) Items recommended to be stocked as spare parts
g. As installed control diagrams by controls manufacturer
h. Each contractor's coordination drawings
1) As installed color coded piping diagrams
01 78 23 - 4
DAP OPERATION AND MAINTENANCE DATA
Page 4 of 5
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised April 7, 2014
i. Charts of valve tag numbers, with location and function of each valve
j. List of original manufacturer's spare parts, manufacturer's current prices, and
recommended quantities to be maintained in storage
k. Other data as required under pertinent Sections of Specifications
3. Content, for each electric and electronic system, as appropriate:
a. Description of system and component parts
1) Function, normal operating characteristics, and limiting conditions
2) Performance curves, engineering data and tests
3) Complete nomenclature and commercial number of replaceable parts
b. Circuit directories of panelboards
1) Electrical service
2) Controls
3) Communications
c. As installed color coded wiring diagrams
d. Operating procedures
1) Routine and normal operating instructions
2) Sequences required
3) Special operating instructions
e. Maintenance procedures
1) Routine operations
2) Guide to "trouble shooting"
3) Disassembly, repair and reassembly
4) Adjustment and checking
f. Manufacturer's printed operating and maintenance instructions
g. List of original manufacturer's spare parts, manufacturer's current prices, and
recommended quantities to be maintained in storage
h. Other data as required under pertinent Sections of Specifications
4. Prepare and include additional data when the need for such data becomes apparent
during instruction of City's personnel.
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE
A. Provide operation and maintenance data by personnel with the following criteria:
1. Trained and experienced in maintenance and operation of described products
2. Skilled as technical writer to the extent required to communicate essential data
3. Skilled as draftsman competent to prepare required drawings
01 78 23 - 5
DAP OPERATION AND MAINTENANCE DATA
Page 5 of 5
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised April 7, 2014
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
8/31/2012 D. Johnson 1.5.A.1 – title of section removed
4/7/2014 M.Domenech Revised for DAP Application
01 78 39 - 1
DAP PROJECT RECORD DOCUMENTS
Page 1 of 4
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised April 7, 2014
SECTION 01 78 39
PROJECT RECORD DOCUMENTS
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Work associated with the documenting the project and recording changes to project
documents, including:
a. Record Drawings
b. Water Meter Service Reports
c. Sanitary Sewer Service Reports
d. Large Water Meter Reports
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various Items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED]
1.5 SUBMITTALS
A. Prior to submitting a request for Final Inspection, deliver Project Record Documents to
City’s Project Representative.
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE
A. Accuracy of Records
1. Thoroughly coordinate changes within the Record Documents, making adequate
and proper entries on each page of Specifications and each sheet of Drawings and
other Documents where such entry is required to show the change properly.
2. Accuracy of records shall be such that future search for items shown in the Contract
Documents may rely reasonably on information obtained from the approved Project
Record Documents.
01 78 39 - 2
DAP PROJECT RECORD DOCUMENTS
Page 2 of 4
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised April 7, 2014
3. To facilitate accuracy of records, make entries within 24 hours after receipt of
information that the change has occurred.
4. Provide factual information regarding all aspects of the Work, both concealed and
visible, to enable future modification of the Work to proceed without lengthy and
expensive site measurement, investigation and examination.
1.10 STORAGE AND HANDLING
A. Storage and Handling Requirements
1. Maintain the job set of Record Documents completely protected from deterioration
and from loss and damage until completion of the Work and transfer of all recorded
data to the final Project Record Documents.
2. In the event of loss of recorded data, use means necessary to again secure the data
to the City's approval.
a. In such case, provide replacements to the standards originally required by the
Contract Documents.
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS
2.1 OWNER-FURNISHED [OR] OWNER-SUPPLIED PRODUCTS [NOT USED]
2.2 RECORD DOCUMENTS
A. Job set
1. Promptly following receipt of the Notice to Proceed, secure from the City, at no
charge to the Contractor, 1 complete set of all Documents comprising the Contract.
B. Final Record Documents
1. At a time nearing the completion of the Work and prior to Final Inspection, provide
the City 1 complete set of all Final Record Drawings in the Contract.
2.3 ACCESSORIES [NOT USED]
2.4 SOURCE QUALITY CONTROL [NOT USED]
PART 3 - EXECUTION
3.1 INSTALLERS [NOT USED]
3.2 EXAMINATION [NOT USED]
3.3 PREPARATION [NOT USED]
3.4 MAINTENANCE DOCUMENTS
A. Maintenance of Job Set
1. Immediately upon receipt of the job set, identify each of the Documents with the
title, "RECORD DOCUMENTS - JOB SET".
01 78 39 - 3
DAP PROJECT RECORD DOCUMENTS
Page 3 of 4
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised April 7, 2014
2. Preservation
a. Considering the Contract completion time, the probable number of occasions
upon which the job set must be taken out for new entries and for examination,
and the conditions under which these activities will be performed, devise a
suitable method for protecting the job set.
b. Do not use the job set for any purpose except entry of new data and for review
by the City, until start of transfer of data to final Project Record Documents.
c. Maintain the job set at the site of work.
3. Coordination with Construction Survey
a. At a minimum clearly mark any deviations from Contract Documents
associated with installation of the infrastructure.
4. Making entries on Drawings
a. Record any deviations from Contract Documents.
b. Use an erasable colored pencil (not ink or indelible pencil), clearly describe the
change by graphic line and note as required.
c. Date all entries.
d. Call attention to the entry by a "cloud" drawn around the area or areas affected.
e. In the event of overlapping changes, use different colors for the overlapping
changes.
5. Conversion of schematic layouts
a. In some cases on the Drawings, arrangements of conduits, circuits, piping,
ducts, and similar items, are shown schematically and are not intended to
portray precise physical layout.
1) Final physical arrangement is determined by the Contractor, subject to the
City's approval.
2) However, design of future modifications of the facility may require
accurate information as to the final physical layout of items which are
shown only schematically on the Drawings.
b. Show on the job set of Record Drawings, by dimension accurate to within 1
inch, the centerline of each run of items.
1) Final physical arrangement is determined by the Contractor, subject to the
City's approval.
2) Show, by symbol or note, the vertical location of the Item ("under slab", "in
ceiling plenum", "exposed", and the like).
3) Make all identification sufficiently descriptive that it may be related
reliably to the Specifications.
c. The City may waive the requirements for conversion of schematic layouts
where, in the City's judgment, conversion serves no useful purpose. However,
do not rely upon waivers being issued except as specifically issued in writing
by the City.
B. Final Project Record Documents
1. Transfer of data to Drawings
a. Carefully transfer change data shown on the job set of Record Drawings to the
corresponding final documents, coordinating the changes as required.
b. Clearly indicate at each affected detail and other Drawing a full description of
changes made during construction, and the actual location of items.
c. Call attention to each entry by drawing a "cloud" around the area or areas
affected.
01 78 39 - 4
DAP PROJECT RECORD DOCUMENTS
Page 4 of 4
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised April 7, 2014
d. Make changes neatly, consistently and with the proper media to assure
longevity and clear reproduction.
2. Transfer of data to other Documents
a. If the Documents, other than Drawings, have been kept clean during progress of
the Work, and if entries thereon have been orderly to the approval of the City,
the job set of those Documents, other than Drawings, will be accepted as final
Record Documents.
b. If any such Document is not so approved by the City, secure a new copy of that
Document from the City at the City's usual charge for reproduction and
handling, and carefully transfer the change data to the new copy to the approval
of the City.
3.5 REPAIR / RESTORATION [NOT USED]
3.6 RE-INSTALLATION [NOT USED]
3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED]
3.8 SYSTEM STARTUP [NOT USED]
3.9 ADJUSTING [NOT USED]
3.10 CLEANING [NOT USED]
3.11 CLOSEOUT ACTIVITIES [NOT USED]
3.12 PROTECTION [NOT USED]
3.13 MAINTENANCE [NOT USED]
3.14 ATTACHMENTS [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
4/7/2014 M.Domenech Revised for DAP Application
CITY OF FORT WORTH SOUTHLAND TERRACE ADDITION LOT 3, BLOCK 4-R
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS PROJECT NO. 103651
Revised July 1, 2011
APPENDIX
GC-4.02 Subsurface and Physical Conditions
GC-4.04 Underground Facilities
GC-6.09 Permits and Utilities
GR-01 60 00 Product Requirements
CITY OF FORT WORTH SOUTHLAND TERRACE ADDITION LOT 3, BLOCK 4-R
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS PROJECT NO. 103651
Revised July 1, 2011
GC-4.02 Subsurface and Physical Conditions
THIS PAGE LEFT INTENTIONALLY BLANK
CITY OF FORT WORTH SOUTHLAND TERRACE ADDITION LOT 3, BLOCK 4-R
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS PROJECT NO. 103651
Revised July 1, 2011
GC-4.04 Underground Facilities
THIS PAGE LEFT INTENTIONALLY BLANK
CITY OF FORT WORTH SOUTHLAND TERRACE ADDITION LOT 3, BLOCK 4-R
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS PROJECT NO. 103651
Revised July 1, 2011
GC-4.02 Subsurface and Physical Conditions
THIS PAGE LEFT INTENTIONALLY BLANK
CITY OF FORT WORTH SOUTHLAND TERRACE ADDITION LOT 3, BLOCK 4-R
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS PROJECT NO. 103651
Revised July 1, 2011
GC-4.04 Underground Facilities
THIS PAGE LEFT INTENTIONALLY BLANK
CITY OF FORT WORTH SOUTHLAND TERRACE ADDITION LOT 3, BLOCK 4-R
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS PROJECT NO. 103651
Revised July 1, 2011
GC-6.09 Permits and Utilities
THIS PAGE LEFT INTENTIONALLY BLANK
CITY OF FORT WORTH SOUTHLAND TERRACE ADDITION LOT 3, BLOCK 4-R
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS PROJECT NO. 103651
Revised July 1, 2011
GR-01 60 00 Product Requirements
THIS PAGE LEFT INTENTIONALLY BLANK
CITY OF FORT WORTH
WATER DEPARTMENT
STANDARD PRODUCT LIST
Updated: April 09, 2021
The Fort Worth Water Department’s Standard Products List has been developed to
minimize the submittal review of products which meet the Fort Worth Water
Department’s Standard Specifications during utility construction projects. When
Technical Specifications for specific products, are included as part of the
Construction Contract Documents, the requirements of the Technical Specification
will override the Fort Worth Water Department’s Standard Specifications and the
Fort Worth Water Department’s Standard Products List and approval of the
specific products will be based on the requirements of the Technical Specification
whether or not the specific product meets the Fort Worth Water Department’s
Standard Specifications or is on the Fort Worth Water Department’s Standard
Products List.
Table of Content
(Click on items to go directly to the page)
Items Page
A.Water & Sewer
1. Manholes & Bases/Components ........................................................... 1
2.Manholes & Bases/Fiberglass ............................................................... 2
3.Manholes & Bases/Frames & Covers/Rectangular ............................... 3
4.Manholes & Bases/Frames & Covers/Round ....................................... 4
5.Manholes & Bases/Frames & Covers/Water Tight & Pressure Tight .. 5
6.Manholes & Bases/Precast Concrete .................................................... 6
7.Manholes & Bases/Rehab Systems/Cementitious ................................ 7
8.Manholes & Bases/Rehab Systems/NonCementitious ......................... 8
9.Manhole Insert (Field Operations Use Only) ........................................ 9
10. Pipe Casing Spacer ............................................................................... 10
11. Pipes/Ductile Iron ................................................................................. 11
12. Utility Line Marker ............................................................................... 12
B.Sewer
13. Coatings/Epoxy ..................................................................................... 13
14. Coatings/Polyurethane .......................................................................... 14
15. Combination Air Valves ....................................................................... 15
16. Pipes/Concrete ...................................................................................... 16
17. Pipe Enlargement System (Method} ..............................................
1$. Pipes.lFiUerglass Reinforced Pipe ..................................................
19. PipesIHDPE ...................................................................................
2Q. PipeslPiiC (Pressi�re Sewer} ..........................................................
21. PipesIPVC* ....................................................................................
22. PipeslRehabICIPP ..........................................................................
23. PipeslItehablFald & Fai�i .............................................................
24. Pipe��Qpen Pro�le Large Diaineter ...............................................
17
18
19
2U
21
22
23
24
C. VLrater
25. Appw�tenances ....................................................................................... 2S
25. Balts, Nuts, and Gasl�ets ....................................................................... 26
27. Cainbination Au� Release Valve ........................................................... 27
28. Diy Barrel Fu�e Hyrit�ants ...................................................................... 28
29. Meters ................................................................................................... 29
30. PipeslP�iC (Pressi�re Water) ................................................................. 3U
31. Pipe5.lValves & Fittiv�slI]uctile I�on Fittings ....................................... 31
32. PipeslValves & Fittiv�slResilient Seated Gate Val�e .......................... 32
33. Pipe5.1�'alves & Fittiv�slRi2bber Seated Butterfly Val�e ...................... 33
34. Palyethylene En�asentent ..................................................................... 34
35. Sainplivg Stations ................................................................................. 35
3fi. Autornati� Flus}�er ................................................................................. 36
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeWater & Sewer - Manholes & Bases/Components 33-39-10 (Rev 2/3/16)07/23/97 33 05 13 Urethane Hydrophilic WaterstopAsahi Kogyo K KAdeka Ultra-Seal P-201ASTM D2240/D412/D79204/26/00 33 05 13 Offset Joint for 4' Diam MHHanson Concrete ProductsDrawing No 35-0048-00104/26/00 33 05 13 Profile Gasket for 4' Diam MHPress-Seal Gasket Corp250-4G GasketASTM C-443/C-361SS MH1/26/99 33 05 13 HDPE Manhole Adjustment RingsLadtech, IncHDPE Adjustment RingNon-traffic area5/13/05 33 05 13 Manhole External WrapCanusa - CPSWrapidSeal Manhole Encapsulation SystemCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.* From Original Standard Products ListClick to Return to the Table of Content1Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water & Sewer - Manholes & Bases/Fiberglass 33-39-13 (1/8/13)1/26/99 33 39 13 Fiberglass ManholeFluid Containment, IncFlowtiteASTM 3753Non-traffic area08/30/06 33 39 13 Fiberglass ManholeL F ManufacturingNon-traffic area* From Original Standard Products ListClick to Return to the Table of Content2Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water & Sewer - Manholes & Bases/Frames & Covers/Rectangular 33-05-13 (Rev 2/3/16)*33 05 13 Manhole Frames and CoversWestern Iron Works, Bass & Hays Foundry100124"x40" WD* From Original Standard Products ListClick to Return to the Table of Content3Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water & Sewer - Manholes & Bases/Frames & Covers/Standard (Round) 33-05-13 (Rev 2/3/16)*33 05 13 Manhole Frames and CoversWestern Iron Works, Bass & Hays Foundry3002424" Dia*33 05 13 Manhole Frames and CoversMcKinley Iron Works IncA 24 AM24" Dia08/24/18 33 05 13 Manhole Frames and CoversNeenah FoundryR-1272ASTM A48 & AASHTO M30624" Dia08/24/18 33 05 13 Manhole Frames and CoversNeenah FoundryR- 165-LM (Hinged)ASTM A48 & AASHTO M30624" Dia08/24/18 33 05 13 Manhole Frames and CoversNeenah FoundryNF 1274ASTM A48 & AASHTO M30630" Dia08/24/18 33 05 13 Manhole Frames and CoversNeenah FoundryR-1743-LM (Hinged)ASTM A48 & AASHTO M30630" dia33 05 13 Manhole Frames and CoversSigma CorporationMH-144N33 05 13 Manhole Frames and CoversSigma CorporationMH-143N33 05 13 Manhole Frames and CoversPont-A-MoussonGTS-STD24" dia33 05 13 Manhole Frames and CoversNeenah Casting24" dia10/31/06 33 05 13 Manhole Frames and Covers (Hinged)PowersealHinged Ductile Iron Manhole ASTM A53624" Dia7/25/03 33 05 13 Manhole Frames and CoversSaint-Gobain Pipelines (Pamrex/rexus)RE32-R8FS30" Dia01/31/06 33 05 13 30" Dia MH Ring and CoverEast Jordan Iron WorksV1432-2 and V1483 DesignsAASHTO M306-0430" Dia11/02/10 33 05 13 30" Dia MH Ring and CoverSigma CorporationMH1651FWN & MH1650230" Dia07/19/11 33 05 13 30" Dia MH Ring and CoverStar Pipe ProductsMH32FTWSS-DC 30" Dia08/10/11 33 05 13 30" Dia MH Ring and CoverAccucast220700 Heavy Duty with Gasket Ring30" Dia10/14/13 33 05 13 30" Dia MH Ring and Cover (Hinged & Lockable)East Jordan Iron Works 30" ERGO XL Assembly with Cam Lock/MPIC/T-Gasket ASSHTO M105 & ASTM A53630" Dia06/01/17 34 05 13 30" Dia MH Ring and Cover (Hinged & Lockable) CISIP Industries2280 (32")ASTM A 4830" Dia09/16/19 33 05 13 10 30" Dia MH Ring and Cover Composite Access Products, L PCAP-ONE-30-FTW, Composite, w/ Lock w/o Hing30" Dia* From Original Standard Products ListClick to Return to the Table of Content4Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water & Sewer - Manholes & Bases/Frames & Covers/Water Tight & Pressure Tight 33-05-13 (Rev 2/3/16)*33 05 13 Manhole Frames and CoversPont-A-MoussonPamtight24" Dia*33 05 13 Manhole Frames and CoversNeenah Casting24" Dia*33 05 13 Manhole Frames and CoversWestern Iron Works,Bass & Hays Foundry300-24P24" Dia*33 05 13 Manhole Frames and CoversMcKinley Iron Works IncWPA24AM24" Dia03/08/00 33 05 13 Manhole Frames and CoversAccucastRC-2100ASTM A 4824" Dia04/20/01 33 05 13 Manhole Frames and Covers(SIP)Serampore Industries Private Ltd300-24-23 75 Ring and CoverASTM A 4824" Dia* From Original Standard Products ListClick to Return to the Table of Content5Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water & Sewer - Manholes & Bases/Precast Concrete (Rev 1/8/13)*33 39 10 Manhole, Precast ConcreteHydro Conduit CorpSPL Item #49ASTM C 47848"*33 39 10 Manhole, Precast ConcreteWall Concrete Pipe Co IncASTM C-44348"09/23/96 33 39 10 Manhole, Precast ConcreteConcrete Product Inc48" I D Manhole w/ 32" ConeASTM C 47848" w/32" cone05/08/18 33 39 10 Manhole, Precast ConcreteThe Turner Company48", 60" I D Manhole w/ 32" ConeASTM C 47848", 60"10/27/06 33 39 10 Manhole, Precast ConcreteOldcastle Precast Inc48" I D Manhole w/ 24" ConeASTM C 47848" Diam w 24" Ring06/09/10 33 39 10 Manhole, Precast (Reinforce Polymer)ConcreteUS Composite PipeReinforced Polymer Concrete ASTM C-7648" to 72"09/06/19 33 39 20 Manhole, Precast ConcreteForterra Pipe and Precast60" & 72" I D Manhole w/32" ConeASTM C-7660" & 72"* From Original Standard Products ListClick to Return to the Table of Content6Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water & Sewer - Manholes & Bases/Rehab Systems/Cementitious*E1-14 Manhole Rehab SystemsQuadex04/23/01E1-14 Manhole Rehab SystemsStandard Cement Materials, IncReliner MSPE1-14 Manhole Rehab SystemsAP/M Permaform4/20/01E1-14 Manhole Rehab SystemStrong CompanyStrong Seal MS2A Rehab System5/12/03E1-14 Manhole Rehab System (Liner)Poly-triplex TechnologiesMH repair product to stop infiltrationASTM D581308/30/06General Concrete RepairFlexKrete TechnologiesVinyl Polyester Repair ProductMisc Use* From Original Standard Products ListClick to Return to the Table of Content7Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water & Sewer - Manholes & Bases/Rehab Systems/NonCementitious05/20/96E1-14 Manhole Rehab SystemsSprayroq, Spray Wall Polyurethane CoatingASTM D639/D790*E1-14 Manhole Rehab SystemsSun Coast12/14/01Coating for Corrosion protection(Exterior)ERTECHSeries 20230 and 2100 (Asphatic Emulsion)For Exterior Coating of Concrete Structures Only01/31/06Coatings for Corrosion ProtectionChestertonArc 791, S1HB, S1, S2Acid Resistance TestSewer Applications8/28/2006Coatings for Corrosion ProtectionWarren EnvironmentalS-301 and M-301Sewer Applications08/30/06Coatings for Corrosion ProtectionCitadelSLS-30 Solids EpoxySewer Applications03/19/1833 05 16, 33 39 10, 33 39 20 Coating for Corrosion protection(Exterior)Sherwin WilliamsRR&C Dampproofing Non-Fibered Spray Grade (Asphatic Emulsion)For Exterior Coating of Concrete Structures Only* From Original Standard Products ListClick to Return to the Table of Content8Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water & Sewer - Manhole Inserts - Field Operations Use Only (Rev 2/3/16)*33 05 13 Manhole InsertKnutson EnterprisesMade to Order - PlasticASTM D 1248For 24" dia*33 05 13 Manhole InsertSouth Western PackagingMade to Order - PlasticASTM D 1248For 24" dia*33 05 13 Manhole InsertNoflow-InflowMade to Order - PlasticASTM D 1248For 24" dia09/23/96 33 05 13 Manhole InsertSouthwestern Packing & Seals, IncLifeSaver - Stainless SteelFor 24" dia09/23/96 33 05 13 Manhole InsertSouthwestern Packing & Seals, IncTetherLok - Stainless SteelFor 24" dia* From Original Standard Products ListClick to Return to the Table of Content9Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water & Sewer - Pipe Casing Spacers 33-05-24 (07/01/13)11/04/02Steel Band Casing SpacersAdvanced Products and Systems, IncCarbon Steel Spacers, Model SI02/02/93Stainless Steel Casing SpacerAdvanced Products and Systems, IncStainless Steel Spacer, Model SSI04/22/87Casing SpacersCascade Waterworks ManufacturingCasing Spacers09/14/10Stainless Steel Casing SpacerPipeline Seal and InsulatorStainless Steel Casing SpacerUp to 48"09/14/10Coated Steel Casin SpacersPipeline Seal and InsulatorCoated Steel Casin SpacersUp to 48" 05/10/11Stainless Steel Casing SpacerPowerseal4810 PowerchockUp to 48"03/19/18Casing SpacersBWMSS-12 Casing Spacer(Stainless Steel)03/19/18Casing SpacersBWMFB-12 Casing Spacer (Coated Carbon Steel) for Non_pressure Pipe and Grouted Casing* From Original Standard Products ListClick to Return to the Table of Content10Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water & Sewer - Pipes/Ductile Iron 33-11-10(1/8/13)*33 11 10 Ductile Iron PipeGriffin Pipe Products, CoSuper Bell-Tite Ductile Iron Pressure Pipe, AWWA C150, C1513" thru 24"08/24/18 33 11 10 Ductile Iron PipeAmerican Ductile Iron Pipe CoAmerican Fastite Pipe (Bell Spigot)AWWA C150, C1514" thru 30"08/24/18 33 11 10 Ductile Iron PipeAmerican Ductile Iron Pipe CoAmerican Flex Ring (Restrained Joint)AWWA C150, C1514" thru 30"*33 11 10 Ductile Iron PipeU S Pipe and Foundry CoAWWA C150, C151*33 11 10 Ductile Iron PipeMcWane Cast Iron Pipe CoAWWA C150, C151* From Original Standard Products ListClick to Return to the Table of Content11Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water & Sewer - Utility Line Marker (08/24/2018)* From Original Standard Products ListClick to Return to the Table of Content12Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Sewer - Coatings/Epoxy 33-39-60 (01/08/13)02/25/02Epoxy Lining SystemSauereisen, IncSewerGard 210RSLA County #210-1 3312/14/01Epoxy Lining SystemErtech Technical CoatingsErtech 2030 and 2100 Series04/14/05Interior Ductile Iron Pipe CoatingInduronProtecto 401ASTM B-117Ductile Iron Pipe Only01/31/06Coatings for Corrosion ProtectionChestertonArc 791, S1HB, S1, S2Acid Resistance TestSewer Applications8/28/2006Coatings for Corrosion ProtectionWarren EnvironmentalS-301 and M-301Sewer Applications* From Original Standard Products ListClick to Return to the Table of Content13Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Sewer - Coatings/Polyurethane* From Original Standard Products ListClick to Return to the Table of Content14Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Sewer - Combination Air Valves 05/25/18 33-31-70 Air Release ValveA R I USA, IncD025LTP02(Composite Body)2"* From Original Standard Products ListClick to Return to the Table of Content15Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Sewer - Pipes/Concrete*E1-04 Conc Pipe, ReinforcedWall Concrete Pipe Co IncASTM C 76*E1-04 Conc Pipe, ReinforcedHydro Conduit CorporationClass III T&G, SPL Item #77ASTM C 76*E1-04 Conc Pipe, ReinforcedHanson Concrete ProductsSPL Item #95 Manhole, #98 PipeASTM C 76*E1-04 Conc Pipe, ReinforcedConcrete Pipe & Products Co IncASTM C 76* From Original Standard Products ListClick to Return to the Table of Content16Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Sewer - Pipe Enlargment System (Method)33-31-23 (01/18/13)PIM SystemPIM CorporationPolyethylenePIM Corp , Piscata Way, N J Approved PreviouslyMcConnell SystemsMcLat ConstructionPolyethyleneHouston, TexasApproved PreviouslyTRS SystemsTrenchless Replacement SystemPolyethyleneCalgary, CanadaApproved Previously* From Original Standard Products ListClick to Return to the Table of Content17Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Sewer - Pipe/Fiberglass Reinforced Pipe 33-31-13(1/8/13)7/21/97 33 31 13 Cent Cast Fiberglass (FRP)Hobas Pipe USA, IncHobas Pipe (Non-Pressure)ASTM D3262/D375403/22/10 33 31 13 Fiberglass Pipe (FRP)AmeronBondstrand RPMP PipeASTM D3262/D375404/09/21Glass-Fiber Reinforced Polymer Pipe (FRP)Thompson Pipe GroupThompson Pipe (Flowtite)ASTM D3262/D37544/14/05Polymer Modified Concrete PipeAmitech USAMeyer Polycrete PipeASTM C33, A276, F4778" to 102", Class V06/09/10E1-9 Reinforced Polymer Concrete PipeUS Composite PipeReinforced Polymer Concrete PipeASTM C-76* From Original Standard Products ListClick to Return to the Table of Content18Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Sewer - Pipes/HDPE 33-31-23(1/8/13)*High-density polyethylene pipePhillips Driscopipe, IncOpticore Ductile Polyethylene PipeASTM D 12488"*High-density polyethylene pipePlexco IncASTM D 12488"*High-density polyethylene pipePolly Pipe, IncASTM D 12488"High-density polyethylene pipeCSR Hydro Conduit/Pipeline SystemsMcConnell Pipe EnlargementASTM D 1248* From Original Standard Products ListClick to Return to the Table of Content19Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Sewer - Pipes/PVC (Pressure Sewer) 33-11-12 (4/1/13)12/02/11 33-11-12 DR-14 PVC Pressure PipePipelife JetstreamPVC Pressure PipeAWWA C9004" thru 12"10/22/14 33-11-12 DR-14 PVC Pressure PipeRoyal Building ProductsRoyal Seal PVC Pressure PipeAWWA C9004" thru 12"* From Original Standard Products ListClick to Return to the Table of Content20Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Sewer - Pipes/PVC* 33-31-20 (7/1/13)*33-31-20 PVC Sewer PipeJ-M Manufacturing Co , Inc (JM Eagle)SDR-26ASTM D 30344" - 15"12/23/97* 33-31-20 PVC Sewer PipeDiamond Plastics CorporationSDR-26ASTM D 30344" thru 15"*33-31-20 PVC Sewer PipeLamson Vylon PipeASTM F 7894" thru 15"01/18/18 33-31-20 PVC Sewer PipeVinyltech PVC PipeGravity SewerASTM D30344" thru 15"11/11/98 33-31-20 PVC Sewer PipeDiamond Plastics Corporation "S" Gravity Sewer PipeASTM F 67918" to 27"*33-31-20 PVC Sewer PipeJ-M Manufacturing Co, Inc (JM Eagle)SDR 26/35 PS 115/46ASTM F 67918" - 28"09/11/12 33-31-20 PVC Sewer PipePipelife Jet StreamSDR-26 and SDR-35ASTM F-67918"05/06/0533-31-20PVC Solid Wall PipeDiamond Plastics CorporationSDR 26/35 PS 115/46ASTM F-67918" to 48"04/27/0633-31-20PVC Sewer Fittings HarcoSDR-26 and SDR-35 Gasket Fittings ASTM D-3034, D-1784, etc4" - 15"*33-31-20PVC Sewer FittingsPlastic Trends, In cGasketed PVC Sewer Main FittingsASTM D 30343/19/2018 33 31 20 PVC Sewer PipePipelife Jet StreamSDR 35ASTM F67918"- 24"3/19/2018 33 31 20 PVC Sewer PipePipelife Jet StreamSDR 26ASTM D30344"- 15"3/29/2019 33 31 20Gasketed Fittings (PVC)GPK Products, IncSDR 26ASTM D3034/F-6794"- 15"10/21/2020 33 31 20 PVC Sewer PipeNAPCOSDR 26ASTM D30344" - 15"10/22/2020 33 31 20 PVC Sewer PipeSanderson Pipe CorpSDR 26ASTM D30344"- 15"10/21/2020 33 31 20 PVC Sewer PipeNAPCOSDR 26/35 PS 115/46ASTM F-67918"- 36"* From Original Standard Products ListClick to Return to the Table of Content21Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Sewer - Pipes/Rehab/CIPP 33-31-12 (01/18/13)*Cured in Place PipeInsituform Texark, IncASTM F 121605/03/99Cured in Place PipeNational Envirotech GroupNational Liner, (SPL) Item #27ASTM F-1216/D-581305/29/96Cured in Place PipeReynolds Inc/Inliner Technolgy (Inliner USA)Inliner TechnologyASTM F 1216* From Original Standard Products ListClick to Return to the Table of Content22Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Sewer - Pipes/Rehab/Fold & Form*Fold and Form PipeCullum Pipe Systems, Inc11/03/98Fold and Form PipeInsituform Technologies, IncInsituform "NuPIpe"ASTM F-1504Fold and Form PipeAmerican Pipe & Plastics, IncDemo Purpose Only12/04/00Fold and Form PipeUltralinerUltraliner PVC Alloy PipelinerASTM F-1504, 1871, 186706/09/03Fold and Form PipeMiller Pipeline CorpEX MethodASTM F-1504, F-1947Up to 18" diameter* From Original Standard Products ListClick to Return to the Table of Content23Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Sewer - Pipes/Open Profile Large Diameter09/26/91 E100-2 PVC Sewer Pipe, RibbedLamson Vylon PipeCarlon Vylon H C Closed Profile Pipe,ASTM F 67918" to 48"09/26/91 E100-2 PVC Sewer Pipe, RibbedExtrusion Technologies, IncUltra-Rib Open Profile Sewer PipeASTM F 67918" to 48"E100-2 PVC Sewer Pipe, RibbedUponor ETI Company11/10/10 (E100-2) Polypropylene (PP) Sewer Pipe, Double WallAdvanced Drainage Systems (ADS) SaniTite HP Double Wall (Corrugated)ASTM F 273624"-30"11/10/10 (E100-2) Polypropylene (PP) Sewer Pipe, Triple WallAdvanced Drainage Systems (ADS)SaniTite HP Triple Wall PipeASTM F 276430" to 60"05/16/11Steel Reinforced Polyethylene PipeConTech Construction ProductsDurmaxxASTM F 256224" to 72"* From Original Standard Products ListClick to Return to the Table of Content24Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water - Appurtenances 33-12-10 (07/01/13)01/18/18 33-12-10 Double Strap SaddleRomac202NS Nylon CoatedAWWA C8001"-2" SVC, up to 24" Pipe08/28/02Double Strap SaddleSmith Blair #317 Nylon Coated Double Strap Saddle07/23/12 33-12-10 Double Strap Service SaddleMueller CompanyDR2S Double (SS) Strap DI SaddleAWWA C8001"-2" SVC, up to 24" Pipe10/27/87Curb Stops-Ball Meter ValvesMcDonald6100M,6100MT & 610MT 3/4" and 1"10/27/87Curb Stops-Ball Meter ValvesMcDonald4603B, 4604B, 6100M, 6100TM and 6101M 1½" and 2"5/25/2018 33-12-10 Curb Stops-Ball Meter ValvesFord Meter Box Co , IncFB600-7NL, FB1600-7-NL, FV23-777-W-NL, L22-77NLAWWA C8002"5/25/2018 33-12-10 Curb Stops-Ball Meter ValvesFord Meter Box Co , IncFB600-6-NL, FB1600-6-NL, FV23-666-W-NL, L22-66NLAWWA C8001-1/2"5/25/2018 33-12-10 Curb Stops-Ball Meter ValvesFord Meter Box Co , IncFB600-4-NL, FB1600-4-NL, B11-444-WR-NL, B22444-WR-NL, L28-44NLAWWA C8001"5/25/2018 33-12-10 Curb Stops-Ball Meter ValvesMueller Co , LtdB-25000N, B-24277N-3, B-20200N-3, H-15000N, , H-1552N, H142276NAWWA C800, ANSF 61, ANSI/NSF 3722"5/25/2018 33-12-10 Curb Stops-Ball Meter ValvesMueller Co , LtdB-25000N, B-20200N-3, B-24277N-3,H-15000N, H-14276N, H-15525NAWWA C800, ANSF 61, ANSI/NSF 3721-1/2"5/25/2018 33-12-10 Curb Stops-Ball Meter ValvesMueller Co , LtdB-25000N, B-20200N-3,H-15000N, H-15530NAWWA C800, ANSF 61, ANSI/NSF 3721"01/26/00Coated Tapping Saddle with Double SS StrapsJCM Industries, Inc#406 Double Band SS Saddle1"-2" Taps on up to 12" 0/5/21/12 33-12-25 Tapping Sleeve (Coated Steel)JCM Industries, Inc412 Tapping Sleeve ESSAWWA C-223Up to 30" w/12" Out05/10/11Tapping Sleeve (Stainless Steel)Powerseal3490AS (Flange) & 3490MJ4"-8" and 16"02/29/12 33-12-25 Tapping Sleeve (Coated Steel)RomacFTS 420AWWA C-223U p to 42" w/24" Out02/29/12 33-12-25 Tapping Sleeve (Stainless Steel)RomacSST Stainless SteelAWWA C-223Up to 24" w/12" Out02/29/12 33-12-25 Tapping Sleeve (Stainless Steel)RomacSST III Stainless SteelAWWA C-223Up to 30" w/12" Out05/10/11Joint Repair ClampPowerseal3232 Bell Joint Repair Clamp4" to 30"Plastic Meter Box w/Composite LidDFW Plastics IncDFW37C-12-1EPAF FTWPlastic Meter Box w/Composite LidDFW Plastics IncDFW39C-12-1EPAF FTW08/30/06Plastic Meter Box w/Composite LidDFW Plastics IncDFW65C-14-1EPAF FTWClass "A"Concrete Meter BoxBass & HaysCMB37-B12 1118 LID-9Concrete Meter BoxBass & HaysCMB-18-Dual 1416 LID-9Concrete Meter BoxBass & HaysCMB65-B65 1527 LID-9* From Original Standard Products ListClick to Return to the Table of Content25Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water - Bolts, Nuts, and Gaskets 33-11-05 (01/08/13)* From Original Standard Products ListClick to Return to the Table of Content26Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water - Combination Air Release 33-31-70 (01/08/13)*E1-11 Combination Air Release ValveGA Industries, IncEmpire Air and Vacuum Valve, Model 935 ASTM A 126 Class B, ASTM A 240 - float, ASTM A 307 - Cover Bolts1" & 2"*E1-11 Combination Air Release ValveMultiplex Manufacturing CoCrispin Air and Vacuum Valves, Model No 1/2", 1" & 2"*E1-11 Combination Air Release ValveValve and Primer CorpAPCO #143C, #145C and #147C1", 2" & 3"* From Original Standard Products ListClick to Return to the Table of Content27Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water - Dry Barrel Fire Hydrants 33-12-40 (01/15/14)10/01/87 E-1-12 Dry Barrel Fire HydrantAmerican-Darling ValveDrawing Nos 90-18608, 94-18560AWWA C-50203/31/88 E-1-12 Dry Barrel Fire HydrantAmerican Darling ValveShop Drawing No 94-18791 AWWA C-50209/30/87 E-1-12 Dry Barrel Fire HydrantClow CorporationShop Drawing No D-19895AWWA C-50201/12/93 E-1-12 Dry Barrel Fire HydrantAmerican AVK CompanyModel 2700AWWA C-50208/24/88 E-1-12 Dry Barrel Fire HydrantClow CorporationDrawings D20435, D20436, B20506AWWA C-502E-1-12 Dry Barrel Fire HydrantITT Kennedy ValveShop Drawing No D-80783FWAWWA C-50209/24/87 E-1-12 Dry Barrel Fire HydrantM&H Valve CompanyShop Drawing No 13476AWWA C-50210/14/87 E-1-12 Dry Barrel Fire HydrantMueller CompanyShop Drawings No 6461 A-423 CenturionAWWA C-50201/15/88E1-12 Dry Barrel Fire HydrantMueller CompanyShop Drawing FH-12A-423 Super Centurion 200AWWA C-50210/09/87 E-1-12 Dry Barrel Fire HydrantU S Pipe & FoundryShop Drawing No 960250AWWA C-50209/16/87 E-1-12 Dry Barrel Fire HydrantWaterous CompanyShop Drawing No SK740803AWWA C-50208/12/16 33-12-40 Dry Barrel Fire HydrantEJ (East Jordan Iron Works)WaterMaster 5CD250* From Original Standard Products ListClick to Return to the Table of Content28Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water - Meters02/05/93 E101-5 Detector Check MeterAmes CompanyModel 1000 Detector Check ValveAWWA C5504" - 10"08/05/04Magnetic Drive Vertical TurbineHerseyMagnetic Drive VerticalAWWA C701, Class 13/4" - 6"* From Original Standard Products ListClick to Return to the Table of Content29Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water - Pipes/PVC (Pressure Water) 33-31-70 (01/08/13)01/18/18 33-11-12 PVC Pressure PipeVinyltech PVC PipeDR14AWWA C900, AWWA C605, ASTM D17844"-12"3/19/2018 33 11 12 PVC Pressure PipePipelife Jet StreamDR14AWWA C9004"-12"3/19/2018 33 11 12 PVC Pressure PipePipelife Jet StreamDR18AWWA C90016"-24"5/25/2018 33 11 12 PVC Pressure PipeDiamond Plastics CorporationDR 14AWWA C9004"-12"5/25/2018 33 11 12 PVC Pressure PipeDiamond Plastics CorporationDR 18AWWA C90016"-24"12/6/2018 33 11 12 PVC Pressure PipeJ-M Manufacturing Co , Inc d/b/a JM EagleDR 14AWWA C900-16UL 1285ANSI/NSF 61FM 16124"-28"12/6/2018 33 11 12 PVC Pressure PipeJ-M Manufacturing Co , Inc d/b/a JM EagleDR 18AWWA C900-16UL 1285ANSI/NSF 61FM 161216"-24"9/6/2019 33 11 12 PVC Pressure PipeUnderground Solutions IncDR14 Fusible PVCAWWA C9004" - 8"9/6/2019 33 11 12 PVC Pressure PipeNAPCODR18AWWA C90016" - 24"9/6/2019 33 11 12 PVC Pressure PipeNAPCODR14AWWA C9004"- 12"9/6/2019 33 11 12 PVC Pressure PipeSanderson Pipe CorpDR14AWWA C9004"- 12"* From Original Standard Products ListClick to Return to the Table of Content30Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water - Pipes/Valves & Fittings/Ductile Iron Fittings 33-11-11 (01/08/13)07/23/92E1-07 Ductile Iron FittingsStar Pipe Products, IncMechanical Joint FittingsAWWA C153 & C110*E1-07 Ductile Iron FittingsGriffin Pipe Products, CoMechanical Joint FittingsAWWA C 110*E1-07 Ductile Iron FittingsMcWane/Tyler Pipe/ Union Utilities DivisionMechanical Joint Fittings, SSB Class 350AWWA C 153, C 110, C 11108/11/98E1-07 Ductile Iron FittingsSigma, CoMechanical Joint Fittings, SSB Class 351AWWA C 153, C 110, C 11202/26/14E1-07 MJ FittingsAccucastClass 350 C-153 MJ FittingsAWWA C1534"-12"05/14/98E1-07 Ductile Iron Joint RestraintsFord Meter Box Co /Uni-FlangeUni-Flange Series 1400 AWWA C111/C1534" to 36"05/14/98E1-24 PVC Joint RestraintsFord Meter Box Co /Uni-FlangeUni-Flange Series 1500 Circle-LockAWWA C111/C1534" to 24" 11/09/04E1-07 Ductile Iron Joint RestraintsOne Bolt, IncOne Bolt Restrained Joint FittingAWWA C111/C116/C1534" to 12"02/29/12 33-11-11 Ductile Iron Pipe Mechanical Joint RestraintEBAA Iron, IncMegalug Series 1100 (for DI Pipe)AWWA C111/C116/C1534" to 42"02/29/12 33-11-11 PVC Pipe Mechanical Joint RestraintEBAA Iron, IncMegalug Series 2000 (for PVC Pipe)AWWA C111/C116/C1534" to 24"08/05/04E1-07 Mechanical Joint Retainer Glands(PVC)Sigma, CoSigma One-Lok SLC4 - SLC10AWWA C111/C1534" to 10"03/06/19 33-11-11 Mechanical Joint Retainer Glands(PVC)Sigma, CoSigma One-Lok SLCS4 - SLCS12AWWA C111/C1534" to 12"08/05/04E1-07 Mechanical Joint Retainer Glands(PVC)Sigma, CoSigma One-Lok SLCEAWWA C111/C15312" to 24"08/10/98E1-07 MJ Fittings(DIP)Sigma, CoSigma One-Lok SLDEAWWA C1534" - 24"10/12/10E1-24 Interior Restrained Joint SystemS & B Techncial ProductsBulldog System ( Diamond Lok 21 & JM Eagle ASTM F-16244" to 12"08/16/06E1-07 Mechanical Joint FittingsSIP Industries(Serampore)Mechanical Joint FittingsAWWA C1534" to 24"11/07/16 33-11-11 Mechanical Joint Retainer GlandsStar Pipe Products, IncPVC Stargrip Series 4000ASTM A536 AWWA C11111/07/16 33-11-11 Mechanical Joint Retainer GlandsStar Pipe Products, IncDIP Stargrip Series 3000ASTM A536 AWWA C11103/19/18 33-11-11 Mechanical Joint Retainer GlandsSIP Industries(Serampore)EZ Grip Joint Restraint (EZD) Black For DIPASTM A536 AWWA C1113"-48"03/19/18 33-11-11 Mechanical Joint Retainer GlandsSIP Industries(Serampore)EZ Grip Joint Restraint (EZD) Red for C900 DR14 PVC PipeASTM A536 AWWA C1114"-12"03/19/18 33-11-11 Mechanical Joint Retainer GlandsSIP Industries(Serampore)EZ Grip Joint Restraint (EZD) Red for C900 DR18 PVC PipeASTM A536 AWWA C11116"-24"* From Original Standard Products ListClick to Return to the Table of Content31Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water - Pipes/Valves & Fittings/Resilient Seated Gate Valve* 33-12-20 (05/13/15)Resilient Wedged Gate Valve w/no GearsAmerican Flow ControlSeries 2500 Drawing # 94-2024716"12/13/02Resilient Wedge Gate ValveAmerican Flow ControlSeries 2530 and Series 2536AWWA C51530" and 36"08/31/99Resilient Wedge Gate ValveAmerican Flow ControlSeries 2520 & 2524 (SD 94-20255)AWWA C51520" and 24"05/18/99Resilient Wedge Gate ValveAmerican Flow ControlSeries 2516 (SD 94-20247)AWWA C51516"10/24/00E1-26 Resilient Wedge Gate ValveAmerican Flow ControlSeries 2500 (Ductile Iron)AWWA C5154" to 12"08/05/04Resilient Wedge Gate ValveAmerican Flow Control42" and 48" AFC 2500AWWA C51542" and 48"05/23/91E1-26 Resilient Wedge Gate ValveAmerican AVK CompanyAmerican AVK Resilient Seaded GVAWWA C5094" to 12"01/24/02E1-26 Resilient Wedge Gate ValveAmerican AVK Company20" and smaller*E1-26 Resilient Seated Gate ValveKennedy4" - 12"*E1-26 Resilient Seated Gate ValveM&H4" - 12"*E1-26 Resilient Seated Gate ValveMueller Co4" - 12"11/08/99Resilient Wedge Gate Valve Mueller CoSeries A2361 (SD 6647)AWWA C51516"01/23/03Resilient Wedge Gate ValveMueller CoSeries A2360 for 18"-24" (SD 6709)AWWA C51524" and smaller05/13/05Resilient Wedge Gate ValveMueller CoMueller 30" & 36", C-515AWWA C51530" and 36"01/31/06Resilient Wedge Gate ValveMueller CoMueller 42" & 48", C-515AWWA C51542" and 48"01/28/88E1-26 Resilient Wedge Gate ValveClow Valve CoAWWA C5094" - 12"10/04/94Resilient Wedge Gate ValveClow Valve Co16" RS GV (SD D-20995)AWWA C51516"11/08/99E1-26 Resilient Wedge Gate ValveClow Valve CoClow RW Valve (SD D-21652)AWWA C51524" and smaller11/29/04Resilient Wedge Gate Valve Clow Valve CoClow 30" & 36" C-515AWWA C51530" and 36" (Note 3)11/30/12Resilient Wedge Gate ValveClow Valve CoClow Valve Model 2638AWWA C51524" to 48" (Note 3)05/08/91E1-26 Resilient Seated Gate ValveStockham Valves & FittingsAWWA C 509, ANSI 420 - stem, ASTM A 276 Type 304 - Bolts & nuts4" - 12"*E1-26 Resilient Seated Gate ValveU S Pipe and Foundry CoMetroseal 250, requirements SPL #743" to 16"10/26/16 33-12-20 Resilient Seated Gate ValveEJ (East Jordan Iron Works)EJ FlowMaster Gate Valve & Boxes08/24/18Matco Gate Valve Matco-Norca225 MRAWWA/ANSI C115/An21 154" to 16"* From Original Standard Products ListClick to Return to the Table of Content32Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water - Pipes/Valves & Fittings/Rubber Seated Butterfly Valve 33-12-21 (07/10/14)*E1-30 Rubber Seated Butterfly ValveHenry Pratt CoAWWA C-50424"*E1-30 Rubber Seated Butterfly ValveMueller CoAWWA C-50424"and smaller1/11/99E1-30 Rubber Seated Butterfly ValveDezurik Valves CoAWWA C-50424" and larger06/12/03E1-30 Valmatic American Butterfly ValveValmatic Valve and Manufacturing Corp Valmatic American Butterfly ValveAWWA C-504Up to 84" diameter04/06/07E1-30 Rubber Seated Butterfly ValveM&H ValveM&H Style 4500 & 1450 AWWA C-50424" to 48"03/19/18 33 12 21 Rubber Seated Butterfly ValveG A Industries (Golden Anderson)AWWA C504 Butterfly ValveAWWA C-50430"-54"* From Original Standard Products ListClick to Return to the Table of Content33Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water - Polyethylene Encasement 33-11-10 (01/08/13)05/12/05E1-13 Polyethylene EncasmentFlexsol PackagingFulton Enterprises AWWA C1058 mil LLD05/12/05E1-13 Polyethylene EncasmentMountain States Plastics (MSP) and AEP IndStandard HardwareAWWA C1058 mil LLD05/12/05E1-13 Polyethylene EncasmentAEP IndustriesBullstrong by Cowtown Bolt & GasketAWWA C1058 mil LLD09/06/19 33-11-11 Polyethylene EncasmentNorthtown Products Inc PE Encasement for DIPAWWA C1058 mil LLD* From Original Standard Products ListClick to Return to the Table of Content34Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water - Sampling Station3/12/96Water Sampling StationWater PlusB20 Water Sampling Station* From Original Standard Products ListClick to Return to the Table of Content35Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water - Automatic Flusher10/21/20Automated Flushing SystemMueller HydroguardHG6-A-IN-2-BRN-LPRR(Portable) HG2-A-IN--2-PVC-018-LPLG(Permanent)04/09/21Automated Flushing SystemKupferle Foundry CompanyEclipse #9800wc04/09/21Automated Flushing SystemKupferle Foundry CompanyEclipse #9700 (Portable)* From Original Standard Products ListClick to Return to the Table of Content36Updated:04/09/2021
Approval Spec No.Classsification Manufacturer Model No.National Spec Size
Storm Sewer - Manholes & Bases/Frames & Covers/Standard (Round) 33-05-13 (Rev 03/19/2021)
9/28/2018 33 05 13 Manhole Frames and Covers AccuCast (Govind Steel Company, LTD)MHRC #220605 ASTM A48 AASHTO M306 **24" Dia
9/28/2018 33 05 13 Manhole Cover Neenah Foundry NF-1274-T91 ASTM A48 AASHTO M306 32" Dia
9/28/2018 33 05 13 Manhole Frames and Covers Neenah Foundry NF-1743-LM (Hinged)ASTM A48 AASHTO M306 32" Dia
9/28/2018 33 05 13 Manhole Frame Neenah Foundry NF-1930-30 ASTM A48 AASHTO M306 32 25" Dia
9/28/2018 33 05 13 Manhole Frames and Covers Neenah Foundry R-1743-HV ASTM A48 AASHTO M306 32" Dia
4/3/2019 33 05 13 Manhole Frames and Covers SIP Industries ++2279ST ASTM A48 AASHTO M306 **24" Dia
4/3/2019 33 05 13 Manhole Frames and Covers SIP Industries ++2280ST ASTM A48 AASHTO M306 32" Dia
10/8/2020 33 05 13 Manhole Frames and Covers EJ ( Formally East Jordan Iron Works)EJ1033 Z2/A ASTM A536 AASHTO M306 32 25" Dia
CITY OF FORT WORTH
TRANSPORTATION & PUBLIC WORKS DEPARTMENT
STORMWATER MANAGEMENT DIVISION
STANDARD PRODUCT LIST
**Note: All new development and new installation mahnole lids shall meet the minimum 30-inch opening requirement as specified in City Specification 33 05 13. Any smaller opening sizes will only be allowed for existing manholes that require replacement
frames and covers.
Updated: 03/19/2021
* From Original Standard Products List
Approval Spec No.Classsification Manufacturer Model No.National Spec Size
Storm Sewer - Inlet & Structures 33-05-13 (Rev 03/19/2021)
10/08/20 33 49 20 Curb Inlets Forterrra FRT-10x3-405-PRECAST ASTM C913 10' X 3'
10/08/20 33 49 20 Curb Inlets Forterrra FRT-10x3-406-PRECAST ASTM C913 10' X 3'
10/08/20 33 49 20 Curb Inlets Forterrra FRT-10x4 5-407-PRECAST ASTM C913 10' X 4 5'
10/08/20 33 49 20 Curb Inlets Forterrra FRT-10x4 5-420-PRECAST ASTM C913 10' X 4 5'
10/08/20 33 39 20 Manhole Forterrra FRT-4X4-409-PRECAST-TOP ASTM C913 4' X 4'
10/08/20 33 39 20 Manhole Forterrra FRT-4X4-409-PRECAST-BASE ASTM C913 4' X 4'
10/08/20 33 39 20 Manhole Forterrra FRT-5X5-410-PRECAST-TOP ASTM C913 5' X 5'
10/08/20 33 39 20 Manhole Forterrra FRT-5X5-410-PRECAST-BASE ASTM C913 5' X 5'
10/08/20 33 39 20 Manhole Forterrra FRT-6X6-411-PRECAST-TOP ASTM C913 6' X 6'
10/08/20 33 39 20 Manhole Forterrra FRT-6X6-411-PRECAST-BASE ASTM C913 6' X 6'
3/19/2021 33 49 20 Curb Inlets Thompson Pipe Group TPG-10X3-405-PRECAST INLET ASTM 615 10' X 3'
3/19/2021 33 49 20 Curb Inlets Thompson Pipe Group TPG-15X3-405-PRECAST INLET ASTM 615 15' x 3'
3/19/2021 33 49 20 Curb Inlets Thompson Pipe Group TPG-20X3-405-PRECAST INLET ASTM 615 20' x 3'
3/19/2021 33 39 20 Manhole Thompson Pipe Group TPG-4X4-409-PRECAST TOP ASTM 615 4' X 4'
3/19/2021 33 39 20 Manhole Thompson Pipe Group TPG-4X4-409-PRECAST BASE ASTM 615 4' X 4'
3/19/2021 33 39 20 Manhole Thompson Pipe Group TPG-4X4-412-PRECAST 4-FT RISER ASTM 615 4' X 4'
3/19/2021 33 39 20 Manhole Thompson Pipe Group TPG-5X5-410-PRECAST TOP ASTM 615 5' X 5'
3/19/2021 33 39 20 Manhole Thompson Pipe Group TPG-5X5-410-PRECAST BASE ASTM 615 5' X 5'
3/19/2021 33 39 20 Manhole Thompson Pipe Group TPG-5X5-412-PRECAST 5-FT RISER ASTM 615 5' X 5'
3/19/2021 33 39 20 Manhole Thompson Pipe Group TPG-6X6-411-PRECAST TOP ASTM 615 6' X 6'
3/19/2021 33 39 20 Manhole Thompson Pipe Group TPG-6X6-411-PRECAST BASE ASTM 615 6' X 6'
3/19/2021 33 39 20 Manhole Thompson Pipe Group TPG-6X6-412-PRECAST 6-FT RISER ASTM 615 6' X 6'
3/19/2021 33 39 20 Manhole Thompson Pipe Group TPG-7X7-411-PRECAST TOP ASTM 615 7' X 7'
3/19/2021 33 39 20 Manhole Thompson Pipe Group TPG-7X7-411-PRECAST BASE ASTM 615 7' X 7'
3/19/2021 33 39 20 Manhole Thompson Pipe Group TPG-7X7-412-PRECAST 4-FT RISER ASTM 615 7' X 7'
3/19/2021 33 39 20 Manhole Thompson Pipe Group TPG-8X8-411-PRECAST TOP ASTM 615 8' X 8'
3/19/2021 33 39 20 Manhole Thompson Pipe Group TPG-8X8-411-PRECAST BASE ASTM 615 8' X 8'
3/19/2021 33 39 20 Manhole Thompson Pipe Group TPG-8X8-412-PRECAST 5-FT RISER ASTM 615 8' X 8'
3/19/2021 33 49 20 Drop Inlet Thompson Pipe Group TPG-4X4-408-PRECAST INLET ASTM 615 4' X 4'
3/19/2021 33 49 20 Drop Inlet Thompson Pipe Group TPG-5X5-408-PRECAST INLET ASTM 615 5' X 5'
3/19/2021 33 49 20 Drop Inlet Thompson Pipe Group TPG-6X6-408-PRECAST INLET ASTM 615 6' X 6'
CITY OF FORT WORTH
TRANSPORTATION & PUBLIC WORKS DEPARTMENT
STORMWATER MANAGEMENT DIVISION
STANDARD PRODUCT LIST
Updated: 03/19/21
* From Original Standard Products List
Approval Spec No. ClasssificationManufacturerModel No.National Spec SizeStorm Sewer - Pipes 33-05-13 (Rev 03/19/21)4/9/2021 33 41 13 Storm Drain Pipes Advanced Drainage Systems, Inc. (ADS) ADS HP Storm Polypropylene (PP) Pipe ASTM F2881 & AASHTO M33012" - 60" CITY OF FORT WORTHTRANSPORTATION & PUBLIC WORKS DEPARTMENT STORMWATER MANAGEMENT DIVISION STANDARD PRODUCT LISTUpdated: 04/14/21