HomeMy WebLinkAboutOrdinance 25870-11-2022 Ordinance No.25870-11-2022
AN ORDINANCE INCREASING ESTIMATED RECEIPTS AND
APPROPRIATIONS IN THE WATER AND SEWER CAPITAL PROJECTS FUND
IN THE AMOUNT OF$5,048,832.00,TRANSFERRED FROM AVAILABLE FUNDS
IN THE WATER AND SEWER FUND, FOR THE PURPOSE OF FUNDING THE
2022 BOND YEAR I CONTRACT 3 PROJECT; PROVIDING FOR A
SEVERABILITY CLAUSE; MAKING THIS ORDINANCE CUMULATIVE OF
PRIOR ORDINANCES; REPEALING ALL ORDINANCES IN CONFLICT
HEREWITH;AND PROVIDING AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH,
TEXAS:
SECTION 1.
That in addition to those amounts allocated to the various City departments for Fiscal Year 2023 in the Budget
of the City Manager, there shall also be increased estimated receipts and appropriations in the Water and
Sewer Capital Projects Fund in the amount of$5,048,832.00, transferred from available funds in the Water
and Sewer Fund,for the purpose of funding the 2022 Bond Year 1, Contract 3 Project.
SECTION 2.
That should any portion, section or part of a section of this ordinance be declared invalid, inoperative or void
for any reason by a court of competent jurisdiction,such decision,opinion or judgment shall in no way impair
the remaining portions,sections,or parts of sections of this ordinance,which said remaining provisions shall
be and remain in full force and effect.
SECTION 3.
That this ordinance shall be cumulative of Ordinance 25773-09-2022 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance are in
direct conflict with such other ordinances and appropriations,in which instance said conflicting provisions of
said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
APPROVED AS TO FORM AND LEGALITY: CITY SECRETARY
DQlack(Dec 1,202215:16 CST) 4affiette S.Goodall(Dec 1,2022 15: ST)
Douglas W.Black Jannette S. Goodall
Assistant City Attorney City Secretary
ADOPTED AND EFFECTIVE:November 29,2022
MAYORAL & COUNCIL COMMUNICATION MAP
2022 BOND NEIGHBORHOOD STREETS
CPN102976 - YEAR 1 CONTRACT 3
AVE N AVE N AVE N AVE H
AVE N AVE N
J W
W toU O
cc
ILI
MILLET U MILLET MILLET all F
MILLET p
MILLET y
C
C
p w UC
0 Q J
ADA ADA ADA �` > ZO C
O
LU RAMEY RAMEY RAMEY
IL m y
W U RAMEY
W
� LU J LORIN
LITTLEJOHN LITTLEJOHN LITTLEJOHN
3 °> Z J
O f
4 w ITTLEJOHN LITTLEJOHN
LITTLEJOHN LITTLEJOHN LITTLEJOHN
W
W
J W C
W O
CRENSHAW
U CRENSHAW CRENSHAW Li UI CRENSHAW
a C
W W
O
Q
FITZHUGH = W FITZHUGH
l7 = FITZHUGH
J C °y
W m y W
61 W W
y LW G O STRONG
Q W C
STRONG U 0Q LL N
FORBES FORBES FORBES FORBES
FORBES
W THANNISCH Q W
= W
J
Jx Z N BURTON
m O W BURTON
6 �
BURTON U
TARRANT BERRY BERRY BERRY BERRY
g�apY
MAP ID STREET FROM TO
1 Burton Ave Rufus St Donalee St
2 Donalee St Miller Ave E Berry St
PAVEMENT PROJECTS 3 Rufus St Forbes St E Berry St
W 4 Vogt St Ramey Ave Crenshaw Ave
■� MAJOR STREETS i 5 Vogt St Millet Ave Ramey Ave
CITY STREETS y 6 Crenshaw St Wallace St Donalee St
7 Wallace St Crenshaw Ave 158ft North of Crenshaw St
i RAILROAD TRACKS g Alley between Wallace St and Vogt St Millet Ave Ramey Ave
CITY PARKS 9 Easement between Wallace St and Vogt St Crenshaw Ave 158 ft North of Crenshaw St
0 0.05 0.1 10 Easement between Vogt St and Donalee St Littlejohn Ave Crenshaw Ave
Miles 11 Alley between Donalee St and Vogt St IMillet Ave Ramey Ave
City of Fort Worth, Texas
Mayor and Council Communication
DATE: 11/29/22 M&C FILE NUMBER: M&C 22-0972
LOG NAME: 202022 BOND YEAR 1 CONTRACT 3-MCCLENDON
SUBJECT
(CD 8)Authorize Execution of a Contract with McClendon Construction Company, Inc., in the Amount of$7,776,825.07,for Combined Street
Paving Improvements, Stormwater Improvements,Water and Sanitary Sewer Main Replacements for 2022 Bond Year 1 -Contract 3 project,
Adopt Appropriation Ordinances to Effect a Portion of Water's Contribution to Fiscal Years 2023-2027 Capital Improvement Program and Amend
the Fiscal Years 2023-2027 Capital Improvement Program(2022 Bond Program)
RECOMMENDATION:
It is recommended that the City Council:
1. Authorize execution of a contract with McClendon Construction Company, Inc., in the amount of$7,776,825.07,for combined street paving
improvements, Stormwater improvements,and water and sanitary sewer main replacements for the 2022 Bond Year 1 -Contract 3 project
(City Project Number 102976);
2. Adopt the attached appropriation ordinance increasing receipts and appropriations in the Water and Sewer Capital Projects Fund in the
amount of$5,048,832.00 transferred from available funds within the Water and Sewer Fund,for the purpose of funding the 2022 Bond Year 1
Contract 3 project(City Project Number 102976)to effect a portion of Water's Contribution to the Fiscal Years 2023-2027 Capital
Improvement Program;
3. Adopt the attached appropriation ordinance adjusting appropriations in the 2022 Bond Program Fund by increasing appropriations in the
2022 Bond Year 1 -Contract 3 project(City Project Number 102976)in an amount of$3,974,302.00 and decreasing appropriations in the
Street Improvement-Deteriorating Streets programmable project(City Project Number P130019)by the same amount;and
4. Amend the TPW's Contribution to Fiscal Years 2023-2027 Capital Improvement Program.
DISCUSSION:
This Mayor and Council Communication (M&C)is to authorize a construction contract for Year 1 Neighborhood Streets Improvements project
associated with the 2022 Bond Program. For 2022 Bond Year 1-Contract 3 project,this includes water,sanitary sewer,storm drain and
street paving improvements on approximately 2.46 lane miles,on the following streets:
Street From ! To Scope
Burton Avenue ;Rufus Donalee Street Water/Sewer/Paving
Street
Donalee Street Millet E Berry Street Water/Sewer/Paving;
Avenue
Rufus Street Forbes E Berry Street Water/Sewer/Paving
Street
Vogt Street Ramey Crenshaw Water/Sewer/Paving';
Avenue Avenue ,
Millet ...............
Vogt Street RameyAvenue Water
g Avenue
Wallace ......__—--....'...J
Crenshaw Street Donalee Street Water/Sewer
Street
Crenshaw 158 feet North
Wallace Street Avenue of Crenshaw Sewer
Avenue
Alley between Millet
Wallace Street and Avenue ;Ramey Avenue Sewer
Vogt Street
Alley Between Millet
Donalee Street and Avenue Ramey Avenue Sewer
Vogt Street
Easement between Crenshaw
Wallace Street and Avenue 158 feet North Sewer
Vogt Street
Easement between
`Little Johrr Crenshaw j
Vogt Street and Avenue Avenue Sewer
Donalee Street
*Due to close proximity to the 2022 Bond Year 1 Contract 3 project streets above,the Water Department has requested for water main extensions
on Vogt St from Millet Avenue to Ramey Avenue and on Crenshaw Street in order to loop the water system and provide increased efficiency.
Asphalt paving rehabilitation will be conducted on both roadways subsequent to water main installation.
The project was advertised for bid on September 22,2022 and September 29,2022 in the Fort Worth Star-Telegram.On October 20,2022,the
following bids were received:
Base Bid Alternate A
Bidder (Concrete (Asphalt Time of
paving) paving)
Completion!
McClendon 400
Construction $7,776,825.07 $7,806,397.57 Calendar
Co.,lnc. Days
Stabile&Winn,-in'cli $8,338,101.50 $7,605,615.501
Jackson $10,580,060.00 $9,910,272.50i
Construction, Ltd. I
In an attempt to secure alternate bids,staff advertised the project with Base Bid as concrete bid to reconstruct existing streets included in the Bond
with concrete travel lanes,and Alternative A as Rehabilitation of existing roadway with new asphalt and replacement of damaged curb and gutter.
Staff recommends award of the contract for Base Bid (concrete option).Concrete paving typically has a twenty year life span while asphalt paving
has a ten years span. In addition,the maintenance cost of concrete pavement is less than asphalt pavement.
The Transportation&Public Works Department's share on this contract is$3,401,049.50.The paving funds for this project are included in the
2022 Bond Program.The Water Department's share on this contract is$4,375,775.57 and will be available in the Water&Sewer Capital Projects
Fund for the project(City Project No. 102976). In addition to the contract amount,$857,467.43(Water:$291,082.50, Sewer:$163,184.93, Paving:
$403,200.00)is required for project management,material testing and inspection and$388,841.50(Water:$139,496.00, Sewer:$79,293.00,
Paving:$170,052.50)is provided for project contingencies.
This project will have no impact on the Transportation&Public Works'or on the Water Departments'operating budgets when completed.The
sanitary sewer component of this project is part of the Water Department's Sanitary Sewer Overflow Initiative Program.Approximately 5,324 linear
feet of cast iron water pipe will be removed and replaced as part of this project.
The action in this M&C will amend TPWs contribution to the Fiscal Years 2023-2027 Capital Improvement Program as follows:
Capital! Revised f
Project FY2023 CIP Budget Change
Fund I FY2023
Name Name Appropriations Increase/Decrease; g
gud et
2022
Bond .Street Imprv-
Program Deteriorating!I $77,115,444.00 $(3,974,302.00),$73,141,142.00
-Fund Sts-PB0019
34027
It is the practice of the Water Department to appropriate its CIP plan throughout the fiscal year,instead of within the annual budget ordinance,as
projects commence,additional funding needs are identified,and to comply with bond covenants.The actions in the M&C will appropriate funds in
support of the Water's portion of the City of Fort Worth's Fiscal Years 2023-2027 Capital Improvement Program,as follows:
2022 Bond Year 1 Contract 3-MCCLENDON
Capital E Revised
Project FY2023 CIP Budget Change �
Fund Authority Name Name Appropriations Increase/Decrease FY2023
� Budget j
W&S 102976-
2022
Capital BonProjects- Yeardl- This M&C $5,048,832.00 $5,048,832.00
Fund
56002 Contract I
3
2022 102976-Bond j
2022
Program- Bond This M&CI $3,974,302.00 $3,974,302.001
Year 1-Fund
I
34027 i Contract
Funding is budgeted in the Transfer to Water/Sewer account of the Water and Sewer operating budget for the purpose of funding the 2022 Bond
Year 1 -Contract 3 project within the Water&Sewer Capital Projects Fund.
Appropriations for the water,sanitary sewer and paving improvements for 2022 Bond Year 1 -Contract 3 project by Fund will consist of the
following:
Existing Additional
Fund Appropriations Appropriations Project Total*
2022d and Program $0.00 $3,974,302.00 $3,974,302.00
W&S Capital
Projects-Fund $356,070.00 $5,048,832.00$5,404,902.00
56002
2007 Critical Capital
Projects Fund $313,220.00 $0.00 $313,220.00
39001
Project Total $669,290.00 $9,023,134.001$9,692,424.00
*Numbers rounded for presentation purposes.
Business Equity:McClendon Construction Co.,Inc.is in compliance with the City's Business Equity Ordinance by committing to 12%Business
Equity participation on this project.The City's Business Equity goal on this project is 11%.
This project is included in the 2022 Bond Program.The City's Extendable Commercial Paper(ECP)(M&C 22-0607;Ordianance 25675-08-2022)
provides liquidity to support the appropriation.Available resources will be used to actually make any interim progress payments until debt is
issued.Once debt associated with a project is sold,debt proceeds will reimburse the interim financing source in accordance with the statement
expressing official Intent to Reimburse that was adopted as part of the ordinance canvassing the bond election(Ordinance 25515-05-2022).
This project is located in COUNCIL DISTRICT 8.
FISCAL INFORMATION/CERTIFICATION:
The Director of Finance certifies that funds are available in the current operating budget of the Water&Sewer Fund and upon the approval of the
above recommendations and adoption of the attached appropriation ordinances,funds will be available in the current capital budgets,as
appropriated,in the W&S Capital Projects Fund,and 2022 Bond Program Funds for the 2022 Bond Yr 1 -Contract 3 project to support the
approval of the above recommendations and execution of the construction contract.Prior to any expenditure being incurred,the Transportation&
Public Works and Water Departments have the responsibility of verifying the availability of funds.
Submitted for City Manager's Office b . William Johnson 5806
Originating Business Unit Head: Lauren Prieur 6035
Additional Information Contact: Monty Hall 8662