HomeMy WebLinkAboutContract 56522-PM1F��RT ��RTH �S�' No_ 56522-P1VI1
PR�JE["T M�NLT�L
F�R
THE C �1VS TRLTC TI�N �F
CREEKSIDE ESTATES PHASE 3
City- Praject Na. 1DDS25
Water Pi•oject �Ta. S96Q1-06DD430-10U825-00158D
Sauitai�y- Se��er Pz•aject �io. 596Q7-07DD434-1UU$25-0013$D
?�-24171
S'V-24b4
IPRC Na. IPRC16-2423
Betsy Price Da�id C'ooke
NI3�DT Clfy M7I13��T
Chris Har�der
Director, Water Depat�trnent
Williaui Joluison
Director, Transportation and Pul�lic Warks Depai-tment
PrePared far
The C'ity of Fort �'�orth
February 2�22
� DUNAwAy
DL�NAZ�i��.Y ASSOCI�.TES. L.P. ������"_'����
�� ;•, :.:�
550 Sailey Avenue, Suite 400 �.-;i-:::..:••. `� f.,,s���
�
Ft. ��i�orth, TX'.6107 ,s • ;=' �
�' � . �. .� �;', �
❑ffice: 817-335-1121 1 Fax: 817-424-1370 ¢' ' ---------- =
TX REG. F-111� ��C; ��f;E i•-• -��]J�'AF:O JR���
.... ..�..�..�.......... ..r .
"' �
«i�i��.diu�a�.�-a��-assac.crn�� �s � r7-'����5`��° 21�122
DA Praject# 2a10078.D30
OFFICIAL REC4RD
CITY SECRETARY
FT. WDRTH, TX
00 00 10- 1
TABLE OF CONTENTS FOR DEVELOPER AWARDED PROJECTS
Page 1 of 4
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
SECTION 00 00 10 1
TABLE OF CONTENTS 2
DEVELOPER AWARDED PROJECTS 3
4
Division 00 - General Conditions 5
00 42 43 Proposal Form Unit Price 6
00 43 13 Bid Bond 7
00 45 11 Bidders Prequalification’s 8
00 45 12 Prequalification Statement 9
00 45 26 Contractor Compliance with Workers' Compensation Law 10
00 52 43 Agreement 11
00 61 25 Certificate of Insurance 12
00 62 13 Performance Bond 13
00 62 14 Payment Bond 14
00 62 19 Maintenance Bond 15
00 73 10 Standard City Conditions of the Construction Contract for Developer Awarded 16
Projects 17
18
Division 01 - General Requirements 19
01 11 00 Summary of Work 20
01 25 00 Substitution Procedures 21
01 31 19 Preconstruction Meeting 22
01 31 20 Project Meetings 23
01 32 16 Construction Progress Schedule 24
01 32 33 Preconstruction Video 25
01 33 00 Submittals 26
01 35 13 Special Project Procedures 27
01 45 23 Testing and Inspection Services 28
01 50 00 Temporary Facilities and Controls 29
01 55 26 Street Use Permit and Modifications to Traffic Control 30
01 57 13 Storm Water Pollution Prevention Plan 31
01 58 13 Temporary Project Signage 32
01 60 00 Product Requirements 33
01 66 00 Product Storage and Handling Requirements 34
01 70 00 Mobilization and Remobilization 35
01 71 23 Construction Staking 36
01 74 23 Cleaning 37
01 77 19 Closeout Requirements 38
01 78 23 Operation and Maintenance Data 39
01 78 39 Project Record Documents 40
41
Technical Specifications which have been modified by the Engineer specifically for this 42
Project; hard copies are included in the Project’s Contract Documents 43
44
None 45
100825
00 00 10- 2
TABLE OF CONTENTS FOR DEVELOPER AWARDED PROJECTS
Page 2 of 4
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
Technical Specifications listed below are included for this Project by reference and can be 1
viewed/downloaded from the City’s Buzzsaw site at: 2
3
htps://projectpoint.buzzsaw.com/client/fortworthgov/Resources/02%20-4
%20Construction%20Documents/Specifications 5
6
Division 02 - Existing Conditions 7
02 41 13 Selective Site Demolition 8
02 41 14 Utility Removal/Abandonment 9
02 41 15 Paving Removal 10
11
Division 03 - Concrete03 30 00 Cast-In-Place Concrete 12
03 34 13 Controlled Low Strength Material (CLSM) 13
03 34 16 Concrete Base Material for Trench Repair 14
03 80 00 Modifications to Existing Concrete Structures 15
16
Division 26 - Electrical 17
26 05 00 Common Work Results for Electrical 18
26 05 10 Demolition for Electrical Systems 19
26 05 33 Raceway and Boxes for Electrical Systems 20
26 05 43 Underground Ducts and Raceways for Electrical Systems 21
22
Division 31 - Earthwork 23
31 10 00 Site Clearing 24
31 23 16 Unclassified Excavation 25
31 23 23 Borrow 26
31 24 00 Embankments 27
31 25 00 Erosion and Sediment Control 28
31 36 00 Gabions 29
31 37 00 Riprap 30
31
Division 32 - Exterior Improvements 32
32 01 17 Permanent Asphalt Paving Repair 33
32 01 18 Temporary Asphalt Paving Repair 34
32 01 29 Concrete Paving Repair 35
32 11 23 Flexible Base Courses 36
32 11 29 Lime Treated Base Courses 37
32 11 33 Cement Treated Base Courses 38
32 12 16 Asphalt Paving 39
32 12 73 Asphalt Paving Crack Sealants 40
32 13 13 Concrete Paving 41
32 13 20 Concrete Sidewalks, Driveways and Barrier Free Ramps 42
32 13 73 Concrete Paving Joint Sealants 43
32 14 16 Brick Unit Paving 44
32 16 13 Concrete Curb and Gutters and Valley Gutters 45
32 17 23 Pavement Markings 46
32 31 13 Chain Link Fences and Gates 47
32 31 26 Wire Fences and Gates 48
32 31 29 Wood Fences and Gates 49
32 32 13 Cast in Place Concrete Retaining Walls 50
100825
00 00 10- 3
TABLE OF CONTENTS FOR DEVELOPER AWARDED PROJECTS
Page 3 of 4
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
32 91 19 Topsoil Placement and Finishing of Parkways 1
32 92 13 Hydro-Mulching, Seeding, and Sodding 2
32 93 43 Trees and Shrubs 3
4
Division 33 - Utilities 5
33 01 30 Sewer and Manhole Testing 6
33 01 31 Closed Circuit Television (CCTV) Inspection 7
33 03 10 Bypass Pumping of Existing Sewer Systems 8
33 04 10 Joint Bonding and Electrical Isolation 9
33 04 11 Corrosion Control Test Stations 10
33 04 12 Magnesium Anode Cathodic Protection System 11
33 04 30 Temporary Water Services 12
33 04 40 Cleaning and Acceptance Testing of Water Mains 13
33 05 10 Utility Trench Excavation, Embedment, and Backfill 14
33 05 12 Water Line Lowering 15
33 05 13 Frame, Cover and Grade Rings 16
33 05 14 Adjusting Manholes, Inlets, Valve Boxes, and Other Structures to Grade 17
33 05 16 Concrete Water Vaults 18
33 05 17 Concrete Collars 19
33 05 20 Auger Boring 20
33 05 21 Tunnel Liner Plate 21
33 05 22 Steel Casing Pipe 22
33 05 23 Hand Tunneling 23
33 05 24 Installation of Carrier Pipe in Casing or Tunnel Liner Plate 24
33 05 26 Utility Markers/Locators 25
33 05 30 Exploratory Excavation for Existing Utilities 26
33 11 10 Ductile Iron Pipe 27
33 11 11 Ductile Iron Fittings 28
33 11 12 Polyvinyl Chloride (PVC) Pressure Pipe 29
33 11 13 Concrete Pressure Pipe, Bar Wrapped, Steel Cylinder Type 30
33 11 14 Buried Steel Pipe and Fittings 31
33 11 15 Pre stressed Concrete Cylinder Pipe 32
33 12 10 Water Services 1-inch to 2-inch 33
33 12 11 Large Water Meters 34
33 12 20 Resilient Seated Gate Valve 35
33 12 21 AWWA Rubber Seated Butterfly Valves 36
33 12 25 Connection to Existing Water Mains 37
33 12 30 Combination Air Valve Assemblies for Potable Water Systems 38
33 12 40 Dry-Barrel Fire Hydrants 39
33 12 50 Water Sample Stations 40
33 12 60 Blow off Valves 41
33 31 12 Cured in Place Pipe (CIPP) 42
33 31 13 Fiberglass Reinforced Pipe for Gravity Sanitary Sewers 43
33 31 15 HDPE Pipe For Sanitary Sewers (Gravity and Force Mains) 44
33 31 20 Polyvinyl Chloride (PVC) Gravity Sanitary Sewer Pipe 45
33 31 21 Polyvinyl Chloride (PVC) Closed Profile Gravity Sanitary Sewer Pipe 46
33 31 22 Sanitary Sewer Slip Lining 47
33 31 23 Sanitary Sewer Pipe Enlargement 48
33 31 50 Sanitary Sewer Service Connections and Service Line 49
33 31 70 Combination Air Valve for Sanitary Sewer Force Mains 50
100825
00 00 10- 4
TABLE OF CONTENTS FOR DEVELOPER AWARDED PROJECTS
Page 4 of 4
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
33 39 10 Cast-in-Place Concrete Manholes 1
33 39 20 Precast Concrete Manholes 2
33 39 30 Fiberglass Manholes 3
33 39 40 Wastewater Access Chamber (WAC) 4
33 39 60 Epoxy Liners for Sanitary Sewer Structures 5
33 41 10 Reinforced Concrete Storm Sewer Pipe/Culverts 6
33 41 11 HDPE Storm Sewer Pipe 7
33 46 00 Sub drainage 8
33 46 01 Slotted Storm Drains 9
33 46 02 Trench Drains 10
33 49 10 Cast-in-Place Manholes and Junction Boxes 11
33 49 20 Curb and Drop Inlets 12
33 49 40 Storm Drainage Headwalls and Wingwalls 13
14
Division 34 – Transportation34 41 10 Traffic Signals 15
34 41 13 Removing Traffic Signals 16
34 41 20 Roadway Illumination Assemblies 17
34 41 30 Aluminum Signs 18
34 71 13 Traffic Control 19
20
Appendix 21
GC-4.01 Availability of Lands 22
GC-4.02 Subsurface and Physical Conditions 23
GC-4.04 Underground Facilities 24
GC-4.06 Hazardous Environmental Condition at Site 25
GC-6.06.D Minority and Women Owned Business Enterprise Compliance 26
GC-6.07 Wage Rates 27
GC-6.09 Permits and Utilities 28
GC-6.24 Nondiscrimination 29
GR-01 60 00 Product Requirements 30
31
END OF SECTION 32
100825
4� 42 43
CREEI(51�E PHASE $ PUBLIC IMPROVEMENFS
Quawr�rr►�rqrRrx
Page ! of 2
ProJect Item ItNarmaHon 8idders Proposal
61d115t Itern NQ, Description Specifica[ion Seclion M1fa. llnits Bid Qty. Llnit Prite 6id Value
WATEREMPRDVEMENTS
1 3311.9007 �ucTilelranWaterFittingswlRestfaint 331111 TON �_�2 g 5509.00. �116fifl,99
2 3311.0241 6" Water Pipe 33 71 10, 33 � i 12 LF 2385 $ 3$.0� $90 63d,00
3 33� 2.3�03 8" Gate Vafve 33 12 20 EA 4 5 1 25d_DD 55 O��.GO
A 3372.40J7 Fire H drant 33 72 4� EA 3 4 200.00 5�2.644.40
5 3312.2203 1" IA+ater Serviae 33 72 10 EA &2 S 95b,40 $77,940.00
B 33C5.01a9 Trench 5aiety 33 05 1Q LF 2385 S 1.a❑ 82 385.0�
7 83i 2.oi 17 Connaccion to Existinp 4"-12' Water bABin 33 12 25 �� g$ �,OU4.04 $4 OOO,CQ
T�TAL H T• WATER PR�V M Od 778.0
EWER P
8 3331.3241 4" Sewer Service 33 31 50 EA �Z 750.4Q $6�.5�0,0❑
8 3339.1Q01 -0' Manhole 33 3310, 33 3S2D EA g$ d 540.a6 $40.506.00
10 3331.4715 d" 5ewer Pipe 33 31 12, 33 31 20 LF 99q $ 42.00 529.148.00
11 3331.A716 6" Sewef Pipe, CSS 6acicfill 33 1 S �0, 33 31 �2, 33 31 2o LF 20 � 52.00 $1 44q.0❑
i2 9331.-0201 id' SewerPipe 33 11 70, 33 31 �2, 33 31 20 LF i388 5 50.Ofl $a9,aoa.co
13 3331.d202 1a" 5ewerPipe, C55 Backfll 33 11 1�, 33 31 12, 33 39 29 LF 40 � BO.Ua 32 40a.a0
14 3339,1oQ� 4' Extra aep[h Manhole 33 3s 10, 33 39 2D VF 14 y 185.00 52 590.OD
15 3305,0709T�enchSafaty 33051D LF 2pg2 $ 200 $d,16d,60
16 3301.flCa2 Post-GGTW Inspe: tion 33 07 37 LF 2682 $ d.00 58 328. Q�
17 3301,4101 Manhafe Vaaum Testing 33 01 34 EA 9$ 150.D0 �t.35o,n�
T TAL N T I: EWER IMPR Z20 d20.
PQV N
1$ 32'11.4501 6" Lirn� Treatment 32 1 i 28 SY 8452 � 3, 5Q $29 582.d�
�� 32'73.41fl2 G"ConcPvmt 321313 SY 7899 $ 39.U� 530$�fi1.0U
24 3271.04fla Hydrated Lime 32 11 29 TN 142 5 190.40 $28.960.00
2i 32�3,a3534" Conc Sidewalk 32 13 2p SF 1415 S 3.75 $5,3q6,25
22 3273.�5018arrieYFfa8Ra111p,TypeR-1 321320 E4 6 s y.sao.oa $s,oao.00
23 3213.0504 Barrier Free Ramp, Type hA-2 32 73 20 EA 1 5 1 400.00 1 ag0.oa
24 3213.0502 6arrier Free Ramp, Type Ll-� 32 i3 20 EA 2 5 1�OO,bb S3 aQO.Gd
25 3213.0508 BatrierFr�f Ramp, Type P-1 32 13 2� EA 2 5 1,300.00 $2,6a0.0�
T T PROYEME T �5
OD d2 43lE3id i�rnp��ti�l_]3AP Crcckside PFiase 3.xls
4A 4Z 43
CREEI(Sf�E RHASE 3 PUBLIC fMPRDVEMENTS
❑URNTI TY 141ATF�1X
Page 2 Uf 2
Pray�ct Item Infwmation Bidders Proposal
Bidlist Itern No. �escription Specification Sedion Na. Lfn3ts Bdd Qly. Llnit Prica Bid Value
WtAINAGE IMPROVEMENT5
25 3349, 5001 10' Curb Inlet 33 48 2U EI1 8 y 3 40D.QD $2p 400.0❑
27 33q1.a201 21" RCP, Classlll 3341 1a LF 23 S 65.p� 51495.00
28 3341.fl205 24" RCP, Class III 33 41 1a LF 51 3 7fl.Q0 3 57a.00
29 3341.0303 30" RGP, CIdS5 Ill 33 41 40 LF 68 S $5.00 5 780.00
30 3359.�001 d' Storm Junction Bax 02 41 14 �+ 7 5 5,pOd,DO S5,OO�.Oo
31 33�5.0112 Cancrete Colfar 33 QS 17 EA 3 s i,oaQ.00 $3,U00.00
32 33o5.0iD8 Trench Safaty 33 Q510 LF 142 5 z.00 $2B4.UD
TAL �R ENT 529 UO
A
33 3471.avoT Tranc Gontr❑I 34 71 �3 M❑ s a.00a.aa $6.OU0,00
34 3d$1.d00d3 FurnishJlnstall r71um Sign Graund Moun{ City Sfd. 34 4� 3fl EA �$ $56.Op $4,250.0'J
TdTAL 51GNAGE ItIN
STREET LIGHTiN
35 3441.3Qa2 Rcfwy IpumAssmbFy TY 17 3a a1 24 EA g$ 2.800.0� 525200.OQ
36 aa-a1,3201 LEO Liphtir�y Fuctura 34 41 24 EA 9�y 850.00 5 85�.QQ
37 3441.7?33 Rdvry Illum Found�tion TY 11 34 41 20 FA B E 7,200.06 $74,800.60
38 28C5.3C7 i 3" C�N�T PVC SCH SO [7} 2fi 05 33 LF gp3 $ �5.00 $S8,5fi3.�0
39 26C5.3C71 Z" CflN�T PVC SCH BD {T} 27 O5 33 LF 572 $ 19.�6 $i�.BEB.�❑
TREET HT 71681
Canfractor _< < t- I [ U' � ��
/; _ �� - . ..
�r"ac� �-t; 1 f [ j� --- '4 �-
��� s�2o�2
CWrtraCto��IgreeSto �omplabe WORI( for FINAL ACGEPTAHCE wHhin
C�FfTRACT oommences Ec run aa provided in tha [#ene►al Condltivns.
�SUB TO7Q�
FQTA� C8#STRUCTION CO3T
i20 working days a�terthe ciata when ihB
�931,984.25
5931,984.15
NDTES:
EXCLUSIQNS:
- �aspection Fees
- ]mpact, Tap or Caniiectiviz Fees
- �ngineering �untroi
- M�ter Fecs andfoT D��osits
- Re-ve�;etatioi�
- Cnnstructirnl Matcrial Testing
- G�ntcch Tcsting
- Adjustm�nt Of�Exi�ti�ig Ut�litEes
- Locate �f Pri.uatc Utilitics
- I3oes noi include wzre o�- �umps
�Q d2 43_E3id Proposal_UAY_Creekside Pliasc 3.xls
Qfl d5 12
DAP PitEQLALIFICATIUN SSATEA�NF
page 1 of 1
SECTi�I�T Oil 45 12
�AP -- PREQiJALIFlCATION S'1'A'[']�NlI;N'I'
l�ac� Bidder is required to complete the information betaw by identifying the prequalifiad contractars
andlor subcantractors w�hom they intend to utiFiic for the maj[�r �vork type{s) ]istea. Jn �'ie"M�ior Work
e" box rowide the carn lcte ma"or wor� �� e and actu a�ided b4• the Wa
D arbment fvr water and sewer and TPW f '�
Majnr Wnrk Type Contractorl5ubcontractor Company Prec�ualifi�ation �
l�ac�� Ex iration I]ate
VLtA"1��K DISTRIB u"1�141v, C�NATSER C�NSTRUCTI�N TX LP 1 �I3112022
DF.VFI_CIPMLNT, 12-I1�'CH
DIAMETER �t SMALLER.
CCTV, 12-INCH ANI] SMALLER
SEW�R C�LLECTIDN 5Y5TEM,
�E�ELOPMENT, 8-INCHES &
SMAI.I.FR
C�NCRETE PAVING CONATSER CQNSTRUCTIOIV TX LP 11312U23
C�NS'T'R i1C'I'IONIRECON STRUCTIC]N
15,flU0 5Y AN� GREATER�
R�ADWAY & PED�STRIAN CONATSER CQNSTRiJCTIpN TX L� 11?12024
LIGHTTI�7G
The undersigned hereby certi�es ihat the enntractnrs ancllvr subcontractors described in the table a6ove
ar� �urrently prequalified for the worlc types listed.
RIDIlFR:
Cvnatser Construction 7'K, L.P.
5327 Wichita 5treet
F�rt VL�arth, �I'7C 7G � 19
�Y: Brrr�r�- t-�u99: n s
'5ignaturc}
TITLE: {�'�SI G� �C�-�
1]A"�'�.:
E11TD OF SECTIOriI
C}TY DF FCRT WQRTH CREEKSIGE ESTATES FHASE 3
SiANaRRo CONS7Rl1CfION PRERVkLIFICJRION STATfMENF— D�V ELOPER 0.WARG�D PROJEGTS City Pmje�t Nv.
For m Ve rsi on Septe m be r 1, ZQ15 1 QDSZS
4(1452fi-!
CdNTRACTQR f{]MPI.[ANCE WITfI V4'C1RKl�.R'5 COMPENSATiQ1V I.AW
Page i of i
1 S�;C7'�dN �q 45 26
2 CdNTRACTdR COMPI�IArJ{�E 4VITH WQR�ER'S C(]2vIPENSATIVN LAW
4 Pursuan# to Texas Labvx Cade SectiQn 406.0�36[a), as amended, Cnntractnr certi�es that it
5 provides worker's campensativn insurance co�erage far all af its employecs cmployed on City
6 Prnjcct No. ] d0424. C:onfxactor furthcr ceriifies that, pursuant to Texas Lat�or Code, Section
? �d6.496(b}, as arnended, it will provide to City its subcontra�tar's ce�titicates vf cflrnpliance with
8 worker's carnpensation caverage.
lf�
��
ZZ
13
14
15
I6
17
18
19
24
2I
22
�a
24
25
2fi
27
28
29
34
31
32
33
3�
35
3fi
C�NTRACTOR:
� t-h�a�, `�C . t{�y: $� N Ut� i r7s
Company (Please Prt t
t
� � ��►�,1, � f_Q �t � _ Signature: ��! ��
Address
�Q�'" llV��'}�l � �� , �i � � t � Title: R� S I G� �h {'
CitylStatel�ip (Please 1'rint)
THE 5T1lTE Q� TEXAS § •''"'r'"'
ti,�PRYAUBri' LfMlQSEY 5 GR1EH
�°;���,;Notary Pubaic, 5ta'.e of Taxas
C�L.TNTY QF TARRANT ":,Y � ...• � ; �a��• �xpir�s p8-06-2az3
§ '4i °i,��`�'i'` Notary !� 13032378-2
w
FURE the undersi cd authority, n�ypersona�Iy appeared
, known to rne ta be the person whose name is
subscrihed to th e i en and seknowlcdged ta me that hefshe executed the s�xne as
thc aci and deed nf fox the purposes and
Cnnsideratian therein pressed and in the capa�ity therein statead.
1•N i.7 -R MY HAND A SEAL �F �FFICN this
� 2{3�
�-�f
ry 1'ublic i
Eh'D U� 5EC
day €�f
for fhe 5tate af'I'exas
C ITY pF FpRT WpRTIi CREEIC$fIJE E'�'TrI T�SYHrfS� .3
S l ANBAiu7 C[]15TRUCTTON 3PECIFICATIQN DDGUMENTS — DEVEL(?PEk AWAR£lF.l7 YI�QiEC7'S Ciay Praject Na. I00815
uca5z�3—i
Ykrvslop� Awarded Project Ap-ecmcnt
Page 1 of 4
i ��c�rro�v vv �2 a3
2 A.GREEMENT.
3 TFQS AGREEi1�II:N'1', anthorized on ��f ���2 as made by and behveen the Daveloper,
q Moritz Interest, Ltd. , authari•r.ed to dn business in Texas ("I]e�e�oper"} , atid
5 Canatser Construction TX, L.P. _ _, authorized to dn
b business in Tixas, acting hy and Thraugh its dul}� authoriZed representati�+e, ("Cnntractor').
7 De�e�apcz and Cvntractvr, in cnnsideratinn of the mutual covenants tiereinafter set forth, a�ree as
8 follows:
9 Arricic 1. WURI�
i� Contra�tor sha11 compleEe all Wark as specified or indicated in the Cantract Iyocwneitts far the
11 Proje�t identified herein.
12 Article 2. PROJI+:CT
13
14
I5
1G
17
]8
19
20
The proje�t fQr wt�ic}i the VI'ork under the Contract Documents may bc th� whole or oaly a gart is
generally deseribcd as fo�lows:
CR��dGS'IAE ES'3'ATES PHflSE 3
Froiert Nn. �00825
Article 3. CUIVTRACT TIME
3.1 Timc is of the essence,
All rirne Iimits fnr 1Vlilestvnes, if any, and E�inal Acceptarice as stated in r.he Contrztct
Documents are of the essencc to this Coniract.
22 3.2 Fin�1 Acceptance.
22 Ti�e Work will be camplete fnr Final Acceptancc within ��0 �nnrking days after the date
23 when the Contraci '1'irne commences to run as provided in �aragraph ] 2.04 of the 5tandard
24 C:ity Conditivns of the Construsrion Cvn�act fcar I]e�e�uper Awarded Prvjects.
�5 3.3 Liquidated darnages
26
27
28
29
34
31
32
33
34
35
Contractor recognizes that time is af the essen�c of t]�is Agrccment and that Develo�er
will suffer financial loss if' the Work is not completed within the times specitied in
Paragraph 3_2 abo�e, plus any extensic�n thorcof allowed in accordanoc with Article ] d of
the Sta.ndard City Conditions af the �onstruccion (:antract far �eveloper Awarded
Projects. The Contractnr also recagnizes t�e delays, expcnse and difficulties invnZvcd in
pm�ing in a legal pro�eeding thc actual lvss suffered hy the T)eveloper if the Work is nat
�arnpleted on rime. Accnrdingly, instead af requiriug any su�h proaf ,{+vn�aotor agrees
that as liquiciated damages for deZay (but nQt as a penalry), Cvn[ractar shall pay
Deveinper �F_Rp �Qllar� {�P.� for each day that expires after the timc speci�ed in
Naragraph 3.2 £or Final Ac�eptance unCil the City issues the Fina� I.etter of Ac�eptance.
CI"ly Uh h-(]R'I' WORTII C'RF.F.ICSII]I:' F'ST�STES FN�iSE3
s�i.a�nAunCONSTR�CT1oIv5PL•CiFICAT[Q1�oocUM&NT5-DEVELOP�RAwARDE�pROJECTS CITYPROJNCJ.IQU8�5
Revised June l4, 2016
uosza3-2
DCVCIOpE[ AWBfdlG PfOJOCI A�CCIllCpL
Page 2 cf 4
36 �rtitle 4, CONTRACT PRICE
3T i]eve3oper a�rees tp p�}� ��naractor far perfvrmance of the Wprk in acc�rdanc� wiih ihe Contraa#
38 Dacumcnts an am�unt in �urrent funds of Ninehundrad�irty-0notnousantlnlnen•dn��e�eiyhlydour �]l�w� � jTl•e�rtt'frve eents
34 t� $93'f,984.�5 �.
40 Article 5. C�NTRACT DUCiTMENTS
41 S,i CQNTENTS�
42 A. The Contract Documents which compnse the entire agreement hetween De�eIoper ar�d
43 Cantractor concerning the L�ark consist of the follawing:
44 1. 'I'his Agreemcnt.
45
46
47
48
49
5t7
31
5�
53
54
SS
56
57
S8
59
�D
6�
62
b3
64
bS
6G
b7
68
69
�o
7I
72
73
4
5
6.
7.
8,
9.
�. Attachments w this Agrcc�ment:
a. Sid Farm (As pro�iided hy 17eveinper}
]} Prapasal Fnrm (I7AP Version)
2) }'requalification 5tatement
3} 5tate and Federal docurnents (project s�recifecf
b, Insurance ACORI] Farm(s}
c. Payrnent Bond (DAP Versian}
d. Performance Sond (Uf1P Version)
c. Maintenance Bond (DAP Version}
f. ?c�wer e�f Attorney for the Bvnds
g. Workcr's Compcnsation Af'fida�it
h, MF3E andlnr 5BF Cczmmitment Fnrm (lf rcquucd}
3. 5tandard City Gen�ral Conditions of t�e Cvnstructinn Contract for Developer
Awarde� Prvjects.
Supplernentary Conditions.
5pecificatians speci�icatly made a part of the Contract Doeuu�ents �}� attachme�t
or, if nnt attached, as incorpgrater� hy refczcnce and des�rihed in the Tahle of
Contents of the Prafect'S Contract Documents.
i]rawings.
Addenda.
Docurnent�tiDrl submitted by Con�actor ptior ta irTDriC� nf �w8rd.
The followiag which may be deli�ered or issued af�er the Effecti�e Date of tt�e
Agreement and, if issued, �ecome an in�nr�sarated part of the Cantract I]ocurruents:
x. Notice to Proceed.
b, Field �rders.
c. Change Urdcrs.
d, iJetter nf Final Acceptan�e,
CITY OF FDRT WflRTH CREEICSI27E E57:4TESPiiRS6.3
SPANDARDCONSTRUCT[QNSPECIFICATIOND[]CUl✓SF1TS—DEVELpPF,RAWA1tUEDPROIEC7'S C1TYP�tO.1NO.1dd825
Re�'iscd June ll�, 2S] I 5
OU5243•3
I%CYCIf1j)LL•C iLW Bfdl:� �I[]jL'CI A�Pf�'11'1C�C
F'agc 3 oF4
74 Article (. INDEMN�'ICATIDN
75
76
77
78
79
8U
S1
82
83
84
$5
8(
87
88
89
94
41
92
43
91l
1.2 C�ntraetar eo�enanis aud agrees ta inaemnify, hald harrnlcss and defend, at its vwn
exgense, the city, its vfficers, servants and employees, from and a�ainst any and ail
c�aims arising out of, or alleged ta anse out of, the work and semces ta be
per%rmed hy the con#ractor, its off'icers, agents, emplopees, suL�nntraetors, licenses
ar in�itees under thi�s cantra�t. 'r�is i�demnifcativn nra►�siaA is sneciticalt►�
intended tv u erate a�td i�c cffecli�e even if it �s alie ■ed flr roven that ail or sorne af
nc�_dama�yes bein� so�yht w�rc caased, en whale or in part, b� anr aci. omission or
nc�lieence of the c�tr. This indernnity pravir+ion is intended fa include, without
Limitutian, indemnity iar cvsts, egpenses and Ze�aI fees incurred by the city in
defending against such claims and causes af aetians,
6.2 Contractar co�enants and a�rees to itidemnify and hol� harmless, at its vwn eapense,
t�e ci#y, its officers, ser�ants and emplayee�, frvm and against any and all lu�s, damage
or destruetian of prnperty vf the city, ariyi�g nut of, ar �sllcged to arise out of, the wvrk
a�d serwices to be performed hy the cantractar, its vfficers, agents, employees�
subcoatracYar�, licensees or invitees under this contract. This indemai�cation
pro�ision is snecificallti intended ta aueraEc anc! b� effecti�e e�en if it is aue�ed nr
�roven that aR_ae svmc a! the da�a�es bein� suu�ht werc caused, in whale or in �ar�,
b� an�� act� o�issian ar ne_li=ence af the citti•.
45 Ai-�ele 7.111ISCELLAl�E�LS
9�5 7.1 '�'erms.
93 Terms used in this Agreement are definad in Am�le 1❑f !he Standard Ciry Conditiaus of
98 the Cnnstruction Contract ior Developer �lwarded Projeets.
99 ?,2 Assigtuneot of Contraet.
lQ� This Agraement, includin� ali af the Cnntract I)ncuments may not he assigncd by the
I01 Contractvr without the advan�ed express written cvnsent of thc De�cloper,
1�2 7.3
103
1Q4
105
Succesaors and Assigns.
Dev�loper arid Contraetnr each binds itself, its �aartness, success[►rs, assigns and ]egat
repr�esentati�es iv the other party hereto, in respect to all covenants, agreements and
ohligatians cnntained in the Contract Docsurlents-
�06 ?.4 5everahility.
107 Any prnrrisivn or part of the C,ontract Docurnents held to be unconsritutianal, �oid 8r
]�S unenforccahlc hy a cuurt of campetent jurisdiction sha1l be deemed �tricken, and a�t
]09 remaining prnvisic�ns sha1Z cantinue tn hc valid and binding upon DEVELO�EA and
110 CQIV'i'RACTDR.
111 7.S Cro�eming Law and Venue.
1 G2 This Agreement, including all of th� Contract Dacuments is performahle in the State of
lll3 7'exas, Venue sha31 bc Tarrant Counry, Texas, ar the Llnii�d States District Craurt for t�e
1�4 Northern T]istrictof'1'exas,Fart WorthDivisioii.
C1TY U�FaRT WORTI-I CREEJCSlDE65TdTESPHAS$3
STANS]ARDCDN57TLti�T[Q;15p7>�IFiCA'Ci<7�lIx]['lfivrh.N'T5 DEVL•1.QpERAWARDFPPR4JECT$ Clf'YPRQT1Y0.10�8T3
xcviserJ ]unc 15, 2016
00 52 43 - 4
D¢vClpper Awardcd Ymjcct Agrrenstnt
�' agc 4 of 4
1is
Z 1 C 7. t Autharity to 5ign.
117
118
119
i2o
121
122
!23
124
Canu-aotvr sha11 ttttach evidence ❑f autharity ta si� Agreerc�ent, if other than duly
autharized si�,►natory of the Contractos.
IN WITNFSS WHERF.(7N, I]e�eloper and Contracwr ha�c executed this Agreement in mu�tiple
cUunierpatts.
This Agreement is vffecti�c as of th� last d�te signed by the Parties {"Effective Date").
Contractor: �e�eloper:
-� G�1 VP McCart-Risin er L. P.
R � f
� � ,���'� _
(.�i �1atu[�) •' {'Si gnature)
#��_ �L_ r.■ ■_
w
�
City15[atel2ip: . 1�'k� ��
�I�sr�� 1�t lq
Date
Title: �en � Titl�: Mana�er
Campany Naruc: �� �'�' Cvmpany name:
Address: [.#�����i�� �C�) Address: 2111 N CDI1111S, SUIt 3�3
-�a+7 101 i CY��tQ .�' .
Z25
VIIR�iam V1l. 5nider
[Frinted Nama}
�itiyl5r�te�zip: Arlingtan, TX 76D11
�ate
f�Ts��2
CITY aF FO RT W{JATH CRF.F.'KSI17F FS'TATh:S PHASF. 3
STr��DARll CON57 x[fCTIqN SPECiF1CATlON DOC[Jh�IVT3— DEVELOPER nWARD"ED PI20IEC7'S CJTYPRa.I N�. 740825
Hcviscxl Iune 7 6, 20l 6
046125-1
CER'fIFICATE dF INSURANCL•
Pa�C 1 of 1
1
�
3
4
S
6
7
8
9
IO
ll
12
13
14
15
I6
Z7
18
19
20
Z1
2�
s��T�o�v oo sz as
•CERTIFI�ATF DF INSUR�.NC�
a. END dF SECTION
�i r�r or NORT wox�x
STANi7ARi] CpIVSTRUCTIQV SYECIF1CATiQN L]pL`�]MCN 1'$
Rcvised July 1. 2q 11
CREF'sKS1DE F.ST 1TF.5 PHASE 3
City Prnject No.
J0�87S
�ond �'o. a2427��
3
�
�
�
5
G
S E'CTIO:�I !][� b� 13
f'�RPORMA:V�'E F30?�4€]
i;Ilf,�i�-3
I'1:Rf i]Ft�1:4�L'�i BCY.tifIJ
Psu� 1 ut',
THE S�'ATE OF TE�{AS �
� I{�4V� Al.L $Y THES� PR�SENTS;
CDUNTY {7F T.�RRA�T �
7 Tlzai � e_ Conatser Construction TX, I..F. . I:no�vn as
S "�'ritiCi�&I" Iterei�t datd Berkle� tnsurance Cain��ant ___ _, a �Drf7[3r�tfL
9 sur�t��[suretles, it'i�iore ihart one) diifw authari�ed t[� da €�usi�z�;s ;i� the St�f�e Df �fe�as. �:tiat<<u as
i�
!1
13
i;
1 �#
I5
i6
17
`'���rcc}" I}�r�ir� [�ti�hether os�e ar 3nar�}. are he�d and finrF}� hna�nd tintn the De.reloper,
f:►iCC.�R'i'-RISIhGER, L.P.}, a�athori�gd to [�a hc�si��ess i�o `F��cas (`���welnper"'} an�i the Cit�� af
F[�R 1�'a�ti�. a Te.r-as r��ur�iri�rtl �nr�nratinn {••�it�"';. ir� the penal sum ot: �dine Hundred'I'hirty One `fhausand,
:Vine Hundred Ei�hh Faur and 25��00------------------,. f]a!lar� (� 931.984.25 }.
lawii�t mo�ie}� o#'the .i��3it� 5tates. it� b� paid in Foi-t Wnrri�. "i'arra,it Cairni�. �Tetas fbr the
paym�nx ni' ir�lii�ii sui� wel� and trtil3' tc� be i�iade joint{�- �nta the �evel�per and the C.il� as dual
obli�ees. ►�e �i���f o��rse)�es_ ��r }zeirs. e�eci�rors, aditli��istr��ors. ��iccessars �»d �ssia�ls, jnintf�
at�d sev�rull�°. iirinly �}• tlzese p�sents.
! 8 1�'[�EREA�;, De��elaper �E�d Cit. Ita��e ent�rec.l ;nta an A�ree�nent �ar t�e cnnstructiQn c�t�
f9 �[}El1II1L1[lli� fscilities iEt t€�e City' af' For[ ��'orth %�• a�lci ihr�u�*h a Comrnil���t�� 3�aciiitieS
30 �I�;reement. CFA �itinber CFA2D-002t:and
3i 4�HEREAS. #he �'rincipal h�s enter�d intp a cc�tain tl�ritt�n ��ntraet ���itll �Pie []ev�Ici�er at�°arded
_'? the 1$fh da� c,t Janua►1' .'D�� .�ti�f�i�l� Co��trxct is herebr• ref�rred ta and made a
�� part herenf'f'or ali purpc�ses �s i#' fi��l�� se� Iorth he�'eiFz. ia f�u•ni4h all materiaPs, �qviprnent la}�or
2� and ai�ter ac�esscari�5 s�rl�ned by taw. in il�e prc�se[:utican crf fhe Wt�rk. iric Eudir�� �lri�� C�I�nge
'� Qrd�rs, as pravided for in said Contract desi�nated a.s CNEEi{SID� Z;STATE.S PHA�SE 3.
�'G N01i�, THERC�DRE, the condifi�n aithi5 oi�li�ati�z� is suc�r that if ti�� sai� �'rinci�ai
'7 s�al1 #'aithtul lt� perfarin at a�sliga.ti�ns r�nder the Ca�ttract and shall i�� aiI respects d��lt� �nd
28 taithfuf�v per#bn� t��e l�Jark. inclu�in� Chan�e Or�ers. und�r t��� C�sntra�t. accorciin� tp il�e plans.
?9 s�s��i#icati[�ns_ ar�d coniract da�u��ents therein referr�d w, aiid as ��•eIi during af��� periud nt
ZU e�'t�nsinn of�the Cn�itract t�at �ra�• [ae �ra�ited an the part nf the U��eln�s�r andl�r Cit}•. tHen this
3f ni��i�a�ion sl7all be and becvn3E n�li and voi�, �il�e3-���ise to reE�iaii� i:� f�i{1 force and e�iiGi.
t��-�� caE� [ ��t r���tsu rE � �'►rt't:,�.ur.�F �ta�i, ti I'ff,1S'F i
�'! .� � I7 n K i7 C 31 Y L' S?ti SJ I'f 1 S 7T14 w[]1,i1 l;t .C7i'L• R i1 W: LKl74s U H!i[.7t� f�t'1:�3 (."11'Y !'lil1J '11J. IIN►k_' 1
H��iScrI.lsnu3n 3i.?i�!�
[K}h� IZ.:
I'1.RI f �Itt'ir1�i{'1: f3(]tf?
1�;�� ? �,k'=
! PROVii`lED FURTH�R, tli�it i� �r�� ]e�ai action he filed an ihi5 I3nnd, r�enue sls�li lie irt
� Tclf'1'aTli COUi}il'. T�13S [31' IISE' I�Ri��� �L�CL'S D15tr3Ct Court tor the �forthern I�istri�t of "I'exas. Fort
+ Worth I3ivisian.
�
�
b
7
�
i�
��
1!
i?
�;
ia
j5
!6
I7
1$
t9
?U
7j
23
�;
�,�
?4
7�j
��
,$
�g
;0
�I
;� �
a.�
34
35
3f►
37
7g
39
��
=� 1
��
#3
�4
�i
�G
•�7
I'his bni�d is m<ide and eaecat�d in �o��pliartce �.•itit the �rou�sinns c�I'C'Ita�ier 2�53 nf'the
'Itx�iS Gc�r�m�neiit Cude. as arr�eijded, and 2�11 liahiliti�s on this E�vnsi shaa) he detennined ��i
acc�ardan�r �4�ith the pra�-isians at'said sr�t�ie.
3�L' W1T�'ESS R'Mx�R�UF; tl�� Pri�cipaf �ndtiie Suret� fla,ve S1GN�D at�d S�,AL�D
this ins�r�uncrtt �,�� duly autE,ari�ed a�enfis and a#�icers oi� tfiis tli� _ 98th ___da� ot
Jarruary . �{� 22 ,
�Ri'�Cf �'�1 L:
Conatser Construction T'�, L.P.
s��: ,��% •
5iena«�r��
s�7`['ES'f-
�
{Priil�i}�a!] 5ecr - .
IIrock Hu��ins, Presidcrlt
;�atne �ild Title
f�ddress. 5327 V4�icFiita St.
Ft. Wrn'tY�. TX 7b I 19
�C�t�.�� �.��-��
11'itn�ss asto Frincip��
�
• ifrlc5s RS tp �ur�t}�
5l� R F"T�':
Berklev Insurance Cbrn��am
$1': ��-�s.� �.�
5 � �n atisre
Rob�i l�furales, A�t:�me} -in-faat
� a��e and -f itl e
,�ddress: 5eD5 L�7 Preeway, 5uite 1500
--�Ua11as��X_�.��4�
`I"e�ephnne �umhcr: 21419$4-OUOQ
*Nate: lfsi�F��d b�� �n t�ificrr af#he Suret�� �arnpan�, tf�cre rr��st b� t�n file a cerfiticr� extra�i
lrom ti7e �.�-]�r�s s1�o�i�in� that this ��n�r� hAs a�rtlinrit� tU si�n suclr obli�ation, 1�'
Suret�'s p%ti�siczl ttddress is a;#i'erent tro�n iis xnai�in�: ac�dress, hcath musi bc provided.
�1�h2 d�tte Uf tl�e bQnd sl�af[ not 6e prinr ta the datG the Cpntra�t is ati� arded,
Ci'i'S` t YF' }'i}R'1' k(}H"1�} E C l2F.F.R',5f1)7: F:4: t 7fr,�' f'!I.l.ti�:"?
ti{;�?�17�A}L[ ] C'f i l' C i}1 l)i'1 !t 1'.titi — t]I: VL I.(11't:It ,ti1W�llt�il� l] 1�Itc i.i1-C'! 4 ['1? y` I��t!].f 1'r�. � �r�y.Y' S
Rr�is�xl Junu�n� +f.'rl3?
Band Vo. 0242724
IH3�i? i�- 1
I':11''�'!f ;�T 13L3\ 1.5
{'se� ] ��P,
1
�
�
3
4
�
G
7
8
9
�a
lE
lM
1?
1-1
1�
IG
ll
i'I�IE :STATE �F TEXAS
CULlNTY �R T�IRHA�"17'
SECTiC]Tti �D b� l �
�AYM�N7 BC)'VL)
�
� [{�(3W ALL BI' THFSE PR�SF�'�1'S:
�
t i��tt �ve. _ C�natser C;nnstructian TY, L.P. , Iu��L�.� as
..Arirrcipal" liet'ei�i, and Beri�ley Insurance Compariy a
cvrpvr�tt sure[t' � or s�Ereties i1' ,�lar� than aitea. de�i�� a�zthQrized ta d� h«siness in the State u1'
Teras. k�awn �s "S��ret��.. �erein ��til��thcr one or �nare�. are hefd a�td frrm�� haun� ur,Eo the
D�ve�vper. (iL'ICCAR"T-NiSi?�i[�C.H, L.P.}_ at�tEiarized ta do bt�siness ir� 'I'e�as "(D��elaper`}.
dnc� th� CEtE oi� F'ort ��orth. a T�xxs ani�nicipal corpoe�fio�� (..Cif�,]. in tl�� penal sti�rn
�ine Hundre� "1'hiri� Uno Thousand.
o� ltiine Hundred �i��hi� Fnur and 251IUC1-------------------- Dall�irs ($ 93 i,984.25 �,
law�'ul mone�• c�t' t�ie United States, tv tre paid in f�qri Vi'orth. Tatrant Cotrntw. T�xas, for tl�e
�aa�meiat o!' ��hich sum a��ll �nd trul�� he inade jpintl► uy�tc� tl3z �e�elnper and the Cit}• as dual
abli�e�s, 44t bi��d aurseltiLs, our k�eirs, ererutnrs, adn�inistrs�tnrs. s«c�essnrs and assi�i3s..jnintf�.
and se�•era I I ti�, t�r�n Ey �y [>> rse �resen ls:
I8 1�VHEFi�AS, D��e�op�rar►d Cit}' liave e��tere.•d i��to �tt A�,reement far�lle constr�ictian of
I� co�nn�unit�� faeiiit3c:s i�i tl3� C�t�� of �nrt 1�'n�th. b�� ar�d throu�l� a Cast�i�iunit� Fac�I.�ties
?[i A�reement. CFA Iv�imb�r CFA2U-0(}Z�:ai�d
'1 WHFREAS. �'rirtci�al has eni�red irito � certai�� �a�ritten Cantr�ct ;t�il� Deve[op�r.
;? a«arded tl�e 18fh da.- s�#� _ January .�(] 22 . whirh Contract is Eiereb��
23 t�Ferre�l tt) and ���ad�: a part lirreaf for all piirp�5es as if tu11� sct fppth hcrein. to f'urnish alJ
"� matcria��. eqt�i�rner�#. ��hcrr and c,t�er access�►r�es as det�ned b�� �au. in the pr��ec�rtiqn at' tli�
�".� Warl► as pmvided fc�r in sai� Contract and ciesigriared a5 CREE![SID�'EST,� T,E'S P�I�ISE3,
2G i�IUW, TH�REF4$F, THE C�NDITiQ�f O�� T"HIS DE3i.1GA�I4N i� surh tl�at i!'
}7 RriE3cipay shall pa}r aEl iriUrii25 ot��ii1� t0 ai1y� �3,t1(� 8ll) pati�ment �a[�� i7�rl�1lC13lry {as definec� in
?8 Cliapter ??53 nflhz `Ie:�aS G[��rernittent Gode. �s atner�dedj in t}te pr��scGutian qf�khe War[i tai�del'
39 the C€ii�tra�t. then ihis obii�ation sl�a1� be and be�om� mdl and tiaid: nthenris� t{� rernai�� �3i �tGll
a0 f'nrce snd efi�ct.
��«� rs� r��Rr���c3��r}3 �"'R�'!i'A;»�ar,r:.��:a��:5r�iiru��
ti'1,1 ti i7.�1R�) t'1 ['�" C U11N�'l[?'+i ti- I7F.�`t.i.[}P�:R r'li�'ARi]T:I) PRtiJI�:C i"ti r ir F��fK.v.t�ta. ln+��3
Hz�iisc�l .i�n�an 3 [. =d}12
fkih� 13_ �
Iyo�1��1L^V f E3t1��)
1'a•+< < iiP �
] �"hi� �nd is i��ade e�3�cl excc��ted in camp]ianre �+itii tl� prcr�isipr�s afClta�t�r �?5� crfth�
? �fr�as Gn�erni�zcnt Cad�:. as afnended. ��d ali liahii:ci�s on t13is boizd sl�a�! be deterEnined in
3 8�C41'��i11cC we lt� T}lE �}1'oVi51QT15 ni SaiC� Statutc.
� i:� WITN�SS V�VHF�REOF, the Prii��i�al an�t 5urety� l�a�•e eac1� SIG�;`�❑ and SL;Ai..CD
� tFiis insirum�r�t b� c�u�� a�iti�nri�et� a�ents and ot�f[cers an tiiis tl�e 98th da�• ai'
G Janraary . ?U 22 .
7
PRI�ClP,-�f�:
C�natser Constructivn `1 X, L,F,
�
{Pr,3icipal� Secr�
�►TTF.ST:
�� �
Wetness as to Principal
R
ati�.
� i�:natur� �
Brock I--Iu�=_�ins_ Yresidcnt ___
\ar��� and Title
Addt-ess: Sa�71�Tv'ichlta 5i,
�.�adh�T���G.11�
5C:'REIi':
Berk�ey_Insurancc Corn�n}.
�TT �:ST:
� L
(5ur�ty) Secretary
���
ness �s tn S�Ertyty-
�
9
i4
1k
I2
l3
1 �l
B�':�fi�i,c�_� ��p-�,��c.�
� i �3] i3E LI FC
R�hhi 4loraies. Attorne� -in-fact
'1�fli� aflc� 3'irle - _......_
r�c3dress: 5Q05 Y�BJ Freewa4•. Suite ] 50i7
Dallas.�'1� 75244 .
'Eeiephor�e'�u�n6er: Z14.�989-�ODO
'�ote: fFsi�r�ed b� an ntTieer at�tl�e Suret�. there mu5t bG an tile a scrtified extract f'r�im the L�����rrs
sfzcztit in� th�t this parson }sas authoritti� rc5 si�n such obligation. lf Surei}''s �l�ysica# address is dit}crcnY t'r�n
jis mai�i3i�; ad�ress. both must be prn��ided.
Thc date �aFtl�c band Shall «nt b� prior tu the datc the Cui�tract is a4�arded.
Eh'D �F SF:CTI[]�I
C�I31'[]� f'{]it"I lt[}K�lI {7{��,'�,jlUI.�I.;il;f7f:,SI'l1_i.5fi3
ti!,'1�1):II�I7t'! 11' C'C1�1?I�f[{]� +-- f7F.VFi.C]ViiRAl7�ARD�ii] {�R[]il'•:d'iti C'17'}'f']�t.�! 1'C)_ 1�+11.Y?S
iLty �u�l .lunuan i I. 3fJ 1.�,
Band No.fl2427?4
!
h
_,
3
i
�
7
R
9
! t]
�r
S�CTIU� 4!U G2 19
n���r�r��t����� �a�n
cxs h � i �a - s
41r1[ti'I'1:ti;�;�ECf: i3i,��1.]
f'uge I uf'!
THF. �Tr�TE UF TFXAS �
§ KN(l�� AL� BY TH�S� PRF,4F�iTSc
cov�Tv oF r��z€�,��T �
��hat �t e Cnnatser Constructivn'['�C, L,P. , kna►�n as
"�ri�ir:i�aE" l�creiii �nd �3crkle� Insuranee Cnmpan�� _ _ , � caTpot'at� sutety'
(;�7reri�5. �I���iUi'e Chan one} c�q1�� authnri7c[i to d�7 htt5ltl�ss 1n tlle STate of Te�f;S, knr�tvn �
"Surert°" l�erei�� � �� hetherone orrnor�y. are i�eld and fin��iF bdund untn th� �e��lap�r,
[?1'�CC�ItT-RISI?4G�R. L.P.}, auchorized to da husiness in �'e�as {��Qe��e€nper"'j and tl�� C;ity rit
1� Fnrt 17dnrtli_ �-i���a� �n��nici�a! �urpnratinn {,.Cit��•}. in the sttm
Nine ��undred Thirty Q�,e 1'}lausand,
!3 b�_l�iinP_Hi?ud ri F��h(3, Fn�fr �ncl ��' ------------ Ut]ll�t'S {� 931�9$4.25 j.
i� lati l`ul 3��n7�e�� nf�the Llnite[� Stal�s. ta be paic� in �ort Vl�orth. Tarrant Cvur�t�F. 'Te4�s, For pa►rnent
i5 of uhich stim «ell and tru�y b� ma�e jointls i�s3t�� the IJe��eloperar�d lhe �i#� as dual ot�li�ees and
fG
�7
lR
I4
a�
�i
��
their su�cessnrs. �=e bii�d ourselyes. aur i�eirs, execui[�rs. adi��i�iistrat�3r�, succcssors and assi�ns.
�oirn�.� and se��rall;�. firi�ly b► these presents.
4VHER�'AS, C]eveloper ��nd Cit� 1����e enrerec� into ayt A�;�ement tor tlte col�strtt�l�on c�f
�c��r�muniit� fa�€lities ir� tlte Cit}� af Fort Wortl� b�• and ihi-�u�� � Con�rnunit�' Faeiiit�t`�;
�+gree��tent, CF'A lwiimber �Z(�[10�l:and
V►°HFR�'AS, the PririLipal l�as en#ered ii�tQ a c�rtain taritir�[ iQniract �j�itff the £7r�etoper
?3 ��'ard�d t}ie_ 'J8th_ cfa�- nf� Januar �. �d 22 . ti,�hiclj C«r�;ra�t i5
'_'�1 I�er�i�y referrec� to and � �7�ac�e part hereaftar all purposes as it'fullr' set f�rth here�n. to turnish �11
?S matzriads, equipment latror anc� vther accessaries as detinad 6+� 1�W, i�i t#i�: prvseCution n�'thc
�6 Wnrl;, ineluding any Vdar#c resultin� from a du1�� authari�ed Clian�e ()rdzr (�al I�ct�� e�t• ��erei��.
_'7 �l�e "�ar�"1 as prn�ided For in said Cnntract and desi�na#ed as CR�`E1f5IDE ESTATE�i PHA.S"L'
�g
�q
3❑
;'
_�
3?
33
:3.�.
3: ar�d
Vb'FIFREAS. Aroncipal bir,ds i#seifto use s�i�h inateriaRs and ia sa con�tru�t tiie Vv"qrk iat
accc�rdance ��ith the plai�s. speci#icati4ns and Contract D�cumz�ts that tt�r 4i'ark is and �+�-iii
remain f'ree f'rta�n defects in materiais or Korkntia��ship tor and during the �erind c�f t►ro �Z) ��exrs
after the date of Ftnal Acce�tance oft��e l�Fark by 2he Cit�� (:.1�4air,tenancc P�riod"j; and
�'f71' t}f I{7Et�l l�'CYKf'1[ ['H1:Fh;�7f.JF F.S'?' I'l1:.5" f'lf t.17: 3
S'!"htil7;�ki7 Cil'!' C'�)�l]lT'I(�3�E5 —f}F:V1:Li}I�3��t���b'AREIE:L] PR[11FiL"f5 ��i� rlrr��.�r�. ;r���,t�;
R�ti i5�ci fdni3:�r► 31. ��ll? .
r3c� h� ��- �
ki�l] ti'1'1,4A tiCli 13i]?t!3
E'���.: 2 uF' 3
� VL'HEREAS. Prineipal 6inds itseff ta re�ir ar reconstruc# the `Jl�ark in �� h�le nr irt part
'� uprsn �•���Er�ing notice frv�n tlie de�e�c�per ancllor Ci[�� ot thN r�eed tliereot'at ar�p tir7ie �� ithir� tli�:
� ti4�int�n��ssce ��r's�d.
�
5 I�[Di� THER�FORE. ihe c�ttdiYion ❑f #hiS qh! i�atinn i� s«clt that i#' �rin�ipa� s}3afl
f► rc3t��d� an;� d�fectE�e V4�ork. tor ��•lti�� tiinel, notic� was prn�ided b} De����oper�rCic�. sa a
� c�rr�p�arion satistactvr}� to the Cir4•. rherr rhis abl;gat�n�� sl�ali become nufl und ►•oid; od3envise ta
� ren�sin in t'uil fnrc� �4id �fiect.
9
iD �RUVIDEll, HQWEt'ER, i f P�in��pal slsa�l fail so ta repair or re�onstr�rct any timelv
11 jinticed c�efectiv� l�'or�, it is a�reed i13�i th� �eveloper �r �i#y ma�• ca�ise �ny a�td atl such
i? defective �'V'cyrk tn h� repai��d t�ndlpr reconstruetid ►t�ith a)1 assaci�ted casts tHerec�#'beiF�� bvrne
1+ h3 the Rrirtcipal and tl�e Sur�tr• a�nder this Maintenan�e Bond; and
t �#
li PRaVIllFD �iJRT��IER, chat �i'�n1� l:.��a! c�Gticjn be �i�ecf on this Bon�, �-e��ueshall lie itt
I G '1'arrant Ct�Wztt��. "C��as car#he l���il�� �tates �3isEric.�E Cuurt for the ;�'�ar[heni I3ist�•ict ��f Texas, I"arl
}7 Worth Diuision_a�id
18
l9 PRQViI]El7 �'L'RTH�R, that tliis c�hli�tion 5��fi be cc�ntiituc�us in nacure a�tii
ZU sucee�sive recor,°eries mai be I�ad Et�re�n f�r surce�si�e �reac[zes.
21
Cl'l'Y'()F!{F13� il-�]�fE[ f'RI:F_'R'.S'lr�f:L•:S'i.t7fi�S?'11:1.�'E:3
S�'A?�!f):iR17{'II5'Cf74f)1�']{}�5--[]k:l�l:.L(7P�1�e111'1Hli! f]YfZCiJf:C'i4 C"ITY NItCJJ 111. !�'1J.4'3
IZ.414Cd 1a11ua!} 31 _ ?il f �
4[ih? !�1_?
L1.A I ti i'I=�;1 tiCt: I3�?�iC7
1'agr 3 nt'3
0
�
;
�
�
6
7
8
9
i0
II
13
i3
I�
i�
I fi
I7
!$
I �l
�U
�}
71
?3
��
�r�
�fi
�7
�8
� ��
:�o
��
3'�
�4
i5
aG
�7
:$
39
��
�11
�?
I�I 1�'�T:�E�54 V4�H�REO�`, tlte f'ri3��ipal anc� tlti� SEirety fia� e earfi 5i�GA'�U a�xd SE�1i..ED lhis
in;tr�rn�nt �w d��ll aut���i-i�ed a��.tits a�d o!f icers Q3i t��is the 9$th c����� �yt
Jar�uary , �� 2�
�1TT�Si:
���e,,�, ��
(Prinei�al) Secretary�a
_,.��.L�E� }�,��-�C�...
1�4'itn�ssasto Princi�al
,�'1-C'I:ST:
F ��
(�ureFy Set:ret'drrP .� _
�
� l ��55 aS L� �urei�
PRitiC'1P,iL:
Conatticr Canstruction ] X, L.P.
ti
E3Y.
Si�nature
Srnck Hu gins�l'residenl
lam� and f-itl�
:�ddress: 5327 Wichita 5t.
��:or1.h,�:�..7�_ .. . .
S!i RETY:
F3erktey lnsurance C:�jmpa�y
01' �vC.r_.
Sier�ature �
l�ob�i Mnrales, .�Litatnc; -irl-fact
_�. :�a���e and -['i[iz
����•�ss: SU05 LS7 Freewa,. 5uite 1540
Dailas. `T'� 75244
i elepiic�ne �u���ber; 2 i 4.�y 89-DO�a
"'tinEe: 1 t si��ied b� an atticez° nt'rhe 5�rec�° C'nmpam _ fl�ere �nust he nn ttl� a C�rCi}ied f:�tract tron� �hz
�7�'-Iil�4'4 SFIOti� 1I7� Llltii 1I735 �JCfSqil has at:thnrity r�� .a��rt su�h nbli�,ati�n. dt� S�irri��'s ph}sica!
�ddress is difte:ent fra�n i[s mailin� addr�ss. bnih nitist be provi�ed,
The dateof ih� br�iul sl�ali nqt be �rior;q the d�tr the finntr�t is a�rardcd.
t'II-7 t)�� 1�{?�tJ il[llt"IiI
S" E;! EV i7�t ii15 C]'f 1' i" �.1ti !?f'I fi 1ti 7—[)i.= V L•'Ll1Pl _k q1A A R I]�:1) E'ILl Jl €`i '! 4
Etc'� �t,tid J�nuarti• ��_'iH?
f'►tF_r•.d'.�r7]L F'�; . r'r �_` f•if, i,�Yi =
('[7i f'13CJ.1171. l�Jf].S'"�
PC?�VF.R O£ _'LT I'a[t.1'�Y
13[�:HKLEY I�ISi:FtA�C'�' Cpl�iP�11�Y
4VlLl�tl�ft;TON. I)H1.AWARE
��o. SI-728Dj-el
Ni7T.ICE: The warning found elsewhere in this Power a i' �ittorney affects th� �alidity thereof. Please review carefuIly.
KNOV� ALL 1VI}':Tv �3Y TFI�SE PRESL�'NTS, that $FiZKL�.Y I�iStTfL:1�IC:F�. t:Dh�PAVY (tlte "Company'°}, a corporaEiun duly
argani�ed and existing undzr t,he lau°s of the 5tntc of'Delaware, havin� ifs princi�al nff ce in Cireenu�ich, CT, has madc, constituted
and appninted, �xnd does hy tf�ese prescnts make, �onstitute and appUint: RtCardn ,I. I��}:nu; �on F Corne�l; .5'opltinie Ilurttet;
Ro6di llfornles; lielly rd. �Y'esthrouk; Tinn :YIC'EW[Lil� Jasle�su A. Sarrr�rlers; or TQnie !'eFr�rnek Uf Aa� Ri.�k .Service.s Sauflewest,
In� af Drella.c, ?:� its true and lawful Attorr�ey-in-��act, to 3i�n iis izame as Sui'ety orily ��s delincatcd helnw and to exeeute, seal,
acicrtowIedge ant! deliver any and ai1 bonds and undcrtakinas, with the exceptian of � Tnancial Guaranty ]nsurai��e, providin� that
no single Ubli�;ation shall cxc;eed Fifty 11'fillinn and O�I�UU l;.S. �ollars (i].S.�SQ,UUU,UUO.[lU}, to thc same extent as if suCh bnnds
had heen duly executed �nd acknaw�edged by the regularly elected off ccrs of the Cnrnpany at its prit�cipa] ❑f�f"rcc in their aw•n
proper persons.
`l his Power o(' Attorney shall be �Unstrued and en�orced in accvrdance with, and �overned by, lhi laws of the St3te of []ela►��arc,
titrithout �i�in� effect to the principles of canfli�is ��f laws Eherenf'. i'his PawGr c�f Attorney is gl•anted pursuar�t to the followin�
resol�iLiUns urhich sverz d�ly �tnd ��alidly adnptcd at � meeiing of the Soard nFilirectors of thc Cnmp�ny hela on Jant�ary 25, 241 Q;
1��SQLVED, that, with respcct fo the 5urety husiness �vritlen hy Rerki.ey 5urety, thc C;hairman oi the F3nard, C�hief
Execiiti�e �ff'i�er, PresidenE or any W'i�e Prisident nf thz C;ompariy, in �onjunc�inn with the 5ecrctary �r xny Assistant
Secx•etuy ar� herehy auihori�ed to execute pawcrs nf attorncy authnri7ing and qualifying ihe attUrneJ�-in-f�ct named therein
to execute 6onds, undcrtakings, recagnic��ri�;,s, or othcr suretyship obli�atinns �n behalf of the Cc�mpany, and to anix the
corporafc seal of the Cninpany to p��r�•ers nf attornew executed �ursuant hereta; xrtd saiti nf�F[cer5 rnay rernotie any suGh.
attorney-in-fact af�d re�oke any po��er of' attnrney previously �;rantcd; and furtFier
RE50Lw'ED, that suc.h J�n«er of'attorncy linlits the aets of thuse namcd thcrein to the b�nds, undcrtakings, recognizances,
Or other suretyship obligatinns spccitically �arned thercin, and they ha�e na authority to binc! the Campany except in lhe
mariner and ro nc� extent �herein stated; and furthcr
Ix�Si]LVED; tli�t such pu��cr of attnrney revol�es all previauS ppwers issued an hehalf of the attorney-in-f�ct named; and
fiarther
RESOI.�rFD, that the signaturc of any authnri�ed of�i��r and the ;eal of tne ��.�mpany may be affuxed by facsirnile to any
pawer of attarne,� ❑r certificatian thereof autlzoriaing the executian aild de]i��ery of any bond, undertaking, reoognizance, ar
nihcr suretyship ohligaiinn o'Fthe Company�; attd sl�ch si�nalure and s2al whcn sn used shall hs�c the same force and zt[�ect as
thnugh manuZlly afiixcd. The C:oLnpany rnay carninue tn use for t�ie purposes herein sfatcc! #he facsimile signaLurc ❑f� any
person c�r p�rsons whn shall ha�c b�::n such officer or of�icer; oC�hc Cnmpany, not�vithstandingthe faet that they rr�ay have
ceased to iae such at tlic tirnc ����ien suGh inserun�cnts s�al] be issued.
IAi WITNESS WFIEREOF, �a Cannpaxcy kas cansed theso presents to.3� si�c� and attestut �y i�s appropuriat� a$`ice�s and ats
Cdtpfltate SCal71GIGL�Eli4 ��iCd i�7s 2nd d�}f 4f June —l2Q�� .
�*�sutza�,v� Attest � $er�cI v Tas�uar�ce �Dmpatc�y
e
�4 `�c�r`" �3 'i � f r �
�. 5°��::��. ; � y BY !. �.,, . �.
m. .� ! L e de�m�t J �j. �
s��s . -
�r.avm��' F.�tecut�ve Vicc Preside�lt & SecrGtary � s e'residcaf
,. � �
aTATE U�' CQNNEC�CiIT )
} ss:
Ci]"E]NTY OF FAJRFi�LL� }
5wom ta hefara rrie, a Notary P��lic ia the 5tate nf C�nne�c�rt, f3�is 2nd day ❑f JUne , 2Q2o ,�ry Ira 5. I.tderman
and Je�z�y M. �a�� �x�o art sworu to me tn be fhe Executive Vice Presiden ��3 5ccas�ary, and T=•• Seninr [tice Presidec►i,
respact�velyj O�B�'�CIG� TIISLIIiIIIGG G'dD]�SdA�'• �`�T RY�A �FG�� /'.%�-�����-
#r►' ca� ii �� � �- b'taz�yPub�ic, 5tate o�F Cora�ecti�t
CERTIF�CAxE
I, thc undersi�d, Assastanf 5ecretaiy of 31G:u� Fty itr'S�R,�NCE C�1�P.AN�, D� HERE�Y CERTiFY tha� ihc foregoing is a
fru�, co;xcct and cnmglctc copy of the ari�nal P�wer of A#torneY, that said P4wCz Df AT�4�Fl�y tlas nof beGn z'e�aket3 pr i�esCiz�d
a�.a :::�N .r aitt�ibritys ri� t�e Arl4m�y�i.n-Fact �e# fprt� tbra-cm, who executed th� bon�3 a� undrx�aking ta which t�is Power af
; `����che� is i� full force and e$eei as of fisis clai:e.
� �
'� ixt�; �,., r�� my h�.nd and seax nf �e Cc�mpany, this day of
x .
� �N::�I, � Y - -
m �
.��
°£in��� V�m�cn# P. Fartc
1MP�RTANT NQTE�E
To abtain informa#ion ❑r make a cflmplaint;
Y�u r�tay ca�i 8er�t�ey Surety Grae�p, LLC and i#s a�fi�iat�s by
#el�phane fvr infarmatian or ta make a carnplaint:
BERKLEY �Ui�ETY �RDU�P, LiC
Please se�d ali n�tfC�S p� Ciai�xl Dh this hond to:
B�rkley Surety Gr�up� LL�
[8��) 7�8-35�4
412 �Vlaunt i[em�l� Av�nue, 5uite 31f�N
�Q1'3"ISt�W11, N,� ��9�7�
Attn. Sur�ty Clairns ❑�partme�t
Yvu rnay cvntact the T�xas Departrnent of insu�r�r�ce iv vbtain
in�armatinh on compani�s, coverages, rights or camp)�ints at:
'� -S#��-25�-3439
You may write the Texas Departmer+t Qf Insuranc�:
P. D, Bvx 9�4�91 a4
Austin, TX 78T��-9�[44
Fax: (5?�� 475-7�7'�
Vli�b: htt :Ilwww.#di.state,tx.�as
E-mail: �on�urnerPro#ecti4n tdi.s#ate.tx.us
PREM�U�N OR CL�1{�VI QiSPIJTES:
Should you have a dis�ute �oncer�in� your premium or about a c#�im
yau �hould �anta�t yaur ag�r�t �r Berki�y Surety Group, LLC first. 1�
#he dispute is nvt resal�ed, yvu may cantact t�� Texas pepartment of
fnsuran�e.
ATTA�H �`#��S NQ�ICE T4 Y[3UR 9�E�p:
This na�ic� is �or �nfarmat�vn on�y �rrd does nof became a part or
conditi�r� af the a#tached dvcum�nt and is given t� c�rrrply ►nr�th Texas
[egai and �re�uta#nry r�quiremen��.
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
STANDARD CITY CONDITIONS
OF THE CONSTRUCTION CONTRACT
FOR DEVELOPER AWARDED PROJECTS
CREEKSIDE ESTATES PHASE
CITY PROJECT NO.
B2010078.030
100825
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
STANDARD CITY CONDITIONS OF THE
CONSTRUCTION CONTRACT
FOR DEVELOPER AWARDED PROJECTS
TABLE OF CONTENTS
Page
Article 1 – Definitions and Terminology .......................................................................................................... 1
1.01 Defined Terms ............................................................................................................................... 1
1.02 Terminology .................................................................................................................................. 5
Article 2 – Preliminary Matters ......................................................................................................................... 6
2.01 Before Starting Construction ........................................................................................................ 6
2.02 Preconstruction Conference .......................................................................................................... 6
2.03 Public Meeting .............................................................................................................................. 6
Article 3 – Contract Documents and Amending ............................................................................................... 6
3.01 Reference Standards ..................................................................................................................... 6
3.02 Amending and Supplementing Contract Documents .................................................................. 6
Article 4 – Bonds and Insurance ....................................................................................................................... 7
4.01 Licensed Sureties and Insurers ..................................................................................................... 7
4.02 Performance, Payment, and Maintenance Bonds ........................................................................ 7
4.03 Certificates of Insurance ............................................................................................................... 7
4.04 Contractor’s Insurance .................................................................................................................. 9
4.05 Acceptance of Bonds and Insurance; Option to Replace ........................................................... 12
Article 5 – Contractor’s Responsibilities ........................................................................................................ 12
5.01 Supervision and Superintendent ................................................................................................. 12
5.02 Labor; Working Hours ................................................................................................................ 13
5.03 Services, Materials, and Equipment ........................................................................................... 13
5.04 Project Schedule .......................................................................................................................... 14
5.05 Substitutes and “Or-Equals” ....................................................................................................... 14
5.06 Pre-Qualification of Bidders (Prime Contractors and Subcontractors) ..................................... 16
5.07 Concerning Subcontractors, Suppliers, and Others ................................................................... 16
5.08 Wage Rates.................................................................................................................................. 18
5.09 Patent Fees and Royalties ........................................................................................................... 19
5.10 Laws and Regulations ................................................................................................................. 19
5.11 Use of Site and Other Areas ....................................................................................................... 19
5.12 Record Documents ...................................................................................................................... 20
5.13 Safety and Protection .................................................................................................................. 21
5.14 Safety Representative ................................................................................................................. 21
5.15 Hazard Communication Programs ............................................................................................. 22
5.16 Submittals .................................................................................................................................... 22
5.17 Contractor’s General Warranty and Guarantee .......................................................................... 23
CREEKSIDE ESTATES PHASE 3
CITY PROJECT NO.
B2010078.030
100825
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
5.18 Indemnification ........................................................................................................................... 24
5.19 Delegation of Professional Design Services .............................................................................. 24
5.20 Right to Audit: ............................................................................................................................ 25
5.21 Nondiscrimination....................................................................................................................... 25
Article 6 – Other Work at the Site ................................................................................................................... 26
6.01 Related Work at Site ................................................................................................................... 26
Article 7 – City’s Responsibilities................................................................................................................... 26
7.01 Inspections, Tests, and Approvals .............................................................................................. 26
7.02 Limitations on City’s Responsibilities ....................................................................................... 26
7.03 Compliance with Safety Program ............................................................................................... 27
Article 8 – City’s Observation Status During Construction ........................................................................... 27
8.01 City’s Project Representative ..................................................................................................... 27
8.02 Authorized Variations in Work .................................................................................................. 27
8.03 Rejecting Defective Work .......................................................................................................... 27
8.04 Determinations for Work Performed .......................................................................................... 28
Article 9 – Changes in the Work ..................................................................................................................... 28
9.01 Authorized Changes in the Work ............................................................................................... 28
9.02 Notification to Surety .................................................................................................................. 28
Article 10 – Change of Contract Price; Change of Contract Time ................................................................ 28
10.01 Change of Contract Price ............................................................................................................ 28
10.02 Change of Contract Time............................................................................................................ 28
10.03 Delays .......................................................................................................................................... 28
Article 11 – Tests and Inspections; Correction, Removal or Acceptance of Defective Work ...................... 29
11.01 Notice of Defects ........................................................................................................................ 29
11.02 Access to Work ........................................................................................................................... 29
11.03 Tests and Inspections .................................................................................................................. 29
11.04 Uncovering Work ....................................................................................................................... 30
11.05 City May Stop the Work ............................................................................................................. 30
11.06 Correction or Removal of Defective Work ................................................................................ 30
11.07 Correction Period ........................................................................................................................ 30
11.08 City May Correct Defective Work ............................................................................................. 31
Article 12 – Completion .................................................................................................................................. 32
12.01 Contractor’s Warranty of Title ................................................................................................... 32
12.02 Partial Utilization ........................................................................................................................ 32
12.03 Final Inspection ........................................................................................................................... 32
12.04 Final Acceptance ......................................................................................................................... 33
Article 13 – Suspension of Work .................................................................................................................... 33
13.01 City May Suspend Work ............................................................................................................ 33
Article 14 – Miscellaneous .............................................................................................................................. 34
14.01 Giving Notice .............................................................................................................................. 34
CREEKSIDE ESTATES PHASE 3
CITY PROJECT NO.
B2010078.030
100825
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
14.02 Computation of Times ................................................................................................................ 34
14.03 Cumulative Remedies ................................................................................................................. 34
14.04 Survival of Obligations ............................................................................................................... 35
14.05 Headings ...................................................................................................................................... 35
CREEKSIDE ESTATES PHASE 3
CITY PROJECT NO.
B2010078.030
100825
00 73 10- 1
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 1 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
ARTICLE 1 – DEFINITIONS AND TERMINOLOGY
1.01 Defined Terms
A. Wherever used in these General Conditions or in other Contract Documents, the terms listed
below have the meanings indicated which are applicable to both the singular and plural thereof,
and words denoting gender shall include the masculine, feminine and neuter. Said terms are
generally capitalized or written in italics, but not always. When used in a context consistent with
the definition of a listed-defined term, the term shall have a meaning as defined below whether
capitalized or italicized or otherwise. In addition to terms specifically defined, terms with initial
capital letters in the Contract Documents include references to identified articles and paragraphs,
and the titles of other documents or forms.
1. Agreement - The written instrument which is evidence of the agreement between Developer
and Contractor covering the Work
2. Asbestos—Any material that contains more than one percent asbestos and is friable or is
releasing asbestos fibers into the air above current action levels established by the United
States Occupational Safety and Health Administration.
3. Business Day – A business day is defined as a day that the City conducts normal business,
generally Monday through Friday, except for federal or state holidays observed by the City.
4. Buzzsaw – City’s on-line, electronic document management and collaboration system.
5. Calendar Day – A day consisting of 24 hours measured from midnight to the next midnight.
6. City— The City of Fort Worth, Texas, a Texas home-rule municipal corporation, acting by,
its governing body through its City Manager, his designee, or agents authorized pursuant to
its duly authorized charter on his behalf.
7. Community Facilities Agreement (CFA) -–A Contract between the Developer and the City
for the Construction of one or more following public facilities within the City public right-of-
way or easement: Water, Sanitary Sewer, Street, Storm Drain, Street Light, and Street Signs.
A CFA may include private facilities within the right-of-way dedicated as private right-of-
way or easement on a recorded plat.
8. Contract—The entire and integrated written document incorporating the Contract
Documents between the Developer, Contractor, and/or City concerning the Work. The
Contract supersedes prior negotiations, representations, or agreements, whether written or
oral.
9. Contract Documents—Those items that make up the contract and which must include the
Agreement, and it’s attachments such as standard construction specifications, standard City
Conditions, other general conditions of the Developer, including:
a. An Agreement
CREEKSIDE ESTATES PHASE 3
CITY PROJECT NO.
B2010078.030
100825
00 73 10- 2
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 2 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
b. Attachments to the Agreement
i. Bid Form
ii. Vendor Compliance with State Law Non-Resident Bidder
iii. Prequalification Statement
c. Current Prevailing Wage Rates Table (if required by City)
d. Insurance Accord Form
e. Payment Bond
f. Performance Bond
g. Maintenance Bond
h. Power of Attorney for Bonds
i. Workers Compensation Affidavit
j. MWBE Commitment Form( If required by City)
k. General Conditions
l. Supplementary Conditions
m. The Standard City Conditions
n. Specifications specifically made part of the Contract Documents by attachment, if
not attached, as incorporated by reference and described in the Table of Contents of
the Project’s Contract Documents
o. Drawings
p. Documentation submitted by contractor prior to Notice of Award.
q. The following which may be delivered or issued after the effective date if the
Agreement and, if issued become an incorporated part of the Contract Documents
i. Notice to Proceed
ii. Field Orders
iii. Change Orders
iv. Letters of Final Acceptance
r. Approved Submittals, other Contractor submittals, and the reports and drawings of
subsurface and physical conditions are not Contract Documents.
10. Contractor—The individual or entity with whom Developer has entered into the Agreement.
11. Day or day – A day, unless otherwise defined, shall mean a Calendar Day.
12. Developer – An individual or entity that desires to make certain improvements within the
City of Fort Worth
13. Drawings—That part of the Contract Documents prepared or approved by Engineer which
graphically shows the scope, extent, and character of the Work to be performed by
Contractor. Submittals are not Drawings as so defined.
14. Engineer—The licensed professional engineer or engineering firm registered in the State of
Texas performing professional services for the Developer.
15. Final Acceptance – The written notice given by the City to the Developer and/or Contractor
that the Work specified in the Contract Documents has been completed to the satisfaction of
the City.
CREEKSIDE ESTATES PHASE 3
CITY PROJECT NO.
B2010078.030
100825
00 73 10- 3
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 3 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
16. Final Inspection – Inspection carried out by the City to verify that the Contractor has
completed the Work, and each and every part or appurtenance thereof, fully, entirely, and in
conformance with the Contract Documents.
17. General Requirements—A part of the Contract Documents between the Developer and a
Contractor.
18. Laws and Regulations—Any and all applicable laws, rules, regulations, ordinances, codes,
and orders of any and all governmental bodies, agencies, authorities, and courts having
jurisdiction.
19. Liens—Charges, security interests, or encumbrances upon Project funds, real property, or
personal property.
20. Milestone—A principal event specified in the Contract Documents relating to an
intermediate Contract Time prior to Final Acceptance of the Work.
21. Non-Participating Change Order—A document, which is prepared for and reviewed by the
City, which is signed by Contractor, and Developer, and authorizes an addition, deletion, or
revision in the Work or an adjustment in the Contract Price or the Contract Time, issued on
or after the Effective Date of the Agreement.
22. Participating Change Order—A document, which is prepared for and approved by the City,
which is signed by Contractor, Developer, and City and authorizes an addition, deletion, or
revision in the Work or an adjustment in the Contract Price or the Contract Time, issued on
or after the Effective Date of the Agreement.
23. Plans – See definition of Drawings.
24. Project Schedule—A schedule, prepared and maintained by Contractor, in accordance with
the General Requirements, describing the sequence and duration of the activities comprising
the Contractor’s plan to accomplish the Work within the Contract Time.
25. Project—The Work to be performed under the Contract Documents.
26. Project Representative—The authorized representative of the City who will be assigned to
the Site.
27. Public Meeting – An announced meeting conducted by the Developer to facilitate public
participation and to assist the public in gaining an informed view of the Project.
28. Regular Working Hours – Hours beginning at 7:00 a.m. and ending at 6:00 p.m., Monday
thru Friday (excluding legal holidays).
29. Samples—Physical examples of materials, equipment, or workmanship that are
representative of some portion of the Work and which establish the standards by which such
portion of the Work will be judged.
CREEKSIDE ESTATES PHASE 3
CITY PROJECT NO.
B2010078.030
100825
00 73 10- 4
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 4 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
30. Schedule of Submittals—A schedule, prepared and maintained by Contractor, of required
submittals and the time requirements to support scheduled performance of related
construction activities.
31. Site—Lands or areas indicated in the Contract Documents as being furnished by City or
Developer upon which the Work is to be performed, including rights-of-way, permits, and
easements for access thereto, and such other lands furnished by City or Developer which are
designated for the use of Contractor.
32. Specifications—That part of the Contract Documents consisting of written requirements for
materials, equipment, systems, standards and workmanship as applied to the Work, and
certain administrative requirements and procedural matters applicable thereto.
Specifications may be specifically made a part of the Contract Documents by attachment or,
if not attached, may be incorporated by reference as indicated in the Table of Contents
(Division 00 00 00) of each Project.
33. Standard City Conditions – That part of the Contract Documents setting forth requirements
of the City.
34. Subcontractor—An individual or entity having a direct contract with Contractor or with any
other Subcontractor for the performance of a part of the Work at the Site.
35. Submittals—All drawings, diagrams, illustrations, schedules, and other data or information
which are specifically prepared or assembled by or for Contractor and submitted by
Contractor to illustrate some portion of the Work.
36. Superintendent – The representative of the Contractor who is available at all times and able
to receive instructions from the City and/or Developer and to act for the Contractor.
37. Supplementary Conditions—That part of the Contract Documents which amends or
supplements the General Conditions.
38. Supplier—A manufacturer, fabricator, supplier, distributor, materialman, or vendor having
a direct contract with Contractor or with any Subcontractor to furnish materials or
equipment to be incorporated in the Work by Contractor or Subcontractor.
39. Underground Facilities—All underground pipelines, conduits, ducts, cables, wires,
manholes, vaults, tanks, tunnels, or other such facilities or attachments, and any
encasements containing such facilities, including but not limited to, those that convey
electricity, gases, steam, liquid petroleum products, telephone or other communications,
cable television, water, wastewater, storm water, other liquids or chemicals, or traffic or
other control systems.
40. Weekend Working Hours – Hours beginning at 9:00 a.m. and ending at 5:00 p.m., Saturday,
Sunday or legal holiday, as approved in advance by the City.
CREEKSIDE ESTATES PHASE 3
CITY PROJECT NO.
B2010078.030
100825
00 73 10- 5
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 5 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
41. Work—The entire construction or the various separately identifiable parts thereof required
to be provided under the Contract Documents. Work includes and is the result of performing
or providing all labor, services, and documentation necessary to produce such construction
including any Participating Change Order, Non-Participating Change Order, or Field
Order, and furnishing, installing, and incorporating all materials and equipment into such
construction, all as required by the Contract Documents.
42. Working Day – A working day is defined as a day, not including Saturdays, Sundays, or
legal holidays authorized by the City for contract purposes, in which weather or other
conditions not under the control of the Contractor will permit the performance of the
principal unit of work underway for a continuous period of not less than 7 hours between 7
a.m. and 6 p.m.
1.02 Terminology
A. The words and terms discussed in Paragraph 1.02.B through D are not defined but, when used in
the Bidding Requirements or Contract Documents, have the indicated meaning.
B. Defective:
1. The word “defective,” when modifying the word “Work,” refers to Work that is
unsatisfactory, faulty, or deficient in that it:
a. does not conform to the Contract Documents; or
b. does not meet the requirements of any applicable inspection, reference standard, test, or
approval referred to in the Contract Documents; or
c. has been damaged prior to City’s written acceptance.
C. Furnish, Install, Perform, Provide:
1. The word “Furnish” or the word “Install” or the word “Perform” or the word “Provide” or
the word “Supply,” or any combination or similar directive or usage thereof, shall mean
furnishing and incorporating in the Work including all necessary labor, materials, equipment,
and everything necessary to perform the Work indicated, unless specifically limited in the
context used.
D. Unless stated otherwise in the Contract Documents, words or phrases that have a well-known
technical or construction industry or trade meaning are used in the Contract Documents in
accordance with such recognized meaning.
CREEKSIDE ESTATES PHASE 3
CITY PROJECT NO.
B2010078.030
100825
00 73 10- 6
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 6 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
ARTICLE 2 – PRELIMINARY MATTERS
2.01 Before Starting Construction
Baseline Schedules: Submit to City in accordance with the Contract Documents, and prior to starting
the Work. New schedules will be submitted to City when Participating Change Orders or Non-
Participating Change Orders occur.
2.02 Preconstruction Conference
Before any Work at the Site is started, the Contractor shall attend a Preconstruction Conference as
specified in the Contract Documents.
2.03 Public Meeting
Contractor may not mobilize any equipment, materials or resources to the Site prior to Contractor
attending the Public Meeting as scheduled by the City.
ARTICLE 3 – CONTRACT DOCUMENTS AND AMENDING
3.01 Reference Standards
A. Standards, Specifications, Codes, Laws, and Regulations
1. Reference to standards, specifications, manuals, or codes of any technical society,
organization, or association, or to Laws or Regulations, whether such reference be specific or
by implication, shall mean the standard, specification, manual, code, or Laws or Regulations
in effect at the time of opening of Bids (or on the Effective Date of the Agreement if there
were no Bids), except as may be otherwise specifically stated in the Contract Documents.
2. No provision or instruction shall be effective to assign to City, or any of its officers,
directors, members, partners, employees, agents, consultants, or subcontractors, any duty or
authority to supervise or direct the performance of the Work or any duty or authority to
undertake responsibility inconsistent with the provisions of the Contract Documents.
3.02 Amending and Supplementing Contract Documents
A. The Contract Documents may be amended to provide for additions, deletions, and revisions in
the Work or to modify the terms and conditions thereof by a Participating Change Order or a
Non-Participating Change Order.
B. The requirements of the Contract Documents may be supplemented, and minor variations and
deviations in the Work not involving a change in Contract Price or Contract Time, may be
authorized, by one or more of the following ways:
1. A Field Order;
CREEKSIDE ESTATES PHASE 3
CITY PROJECT NO.
B2010078.030
100825
00 73 10- 7
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 7 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
1. City’s or Engineer’s review of a Submittal (subject to the provisions of Paragraph 5.16.C); or
2. City’s written interpretation or clarification.
ARTICLE 4 – BONDS AND INSURANCE
4.01 Licensed Sureties and Insurers
All bonds and insurance required by the Contract Documents to be purchased and maintained by
Contractor shall be obtained from surety or insurance companies that are duly licensed or authorized
in the State of Texas to issue bonds or insurance policies for the limits and coverage so required.
Such surety and insurance companies shall also meet such additional requirements and qualifications
as may be provided Section 4.04.
4.02 Performance, Payment, and Maintenance Bonds
A. Contractor shall furnish performance and payment bonds in the name of Developer and City, in
accordance with Texas Government Code Chapter 2253 or successor statute, each in an amount
equal to the Contract Price as security for the faithful performance and payment of all of
Contractor’s obligations under the Contract Documents.
B. Contractor shall furnish maintenance bonds in the name of Developer and City in an amount
equal to the Contract Price as security to protect the City against any defects in any portion of the
Work described in the Contract Documents. Maintenance bonds shall remain in effect for two
(2) years after the date of Final Acceptance by the City.
C. All bonds shall be in the form prescribed by the Contract Documents except as provided
otherwise by Laws or Regulations, and shall be executed by such sureties as are named in the list
of “Companies Holding Certificates of Authority as Acceptable Sureties on Federal Bonds and
as Acceptable Reinsuring Companies” as published in Circular 570 (amended) by the Financial
Management Service, Surety Bond Branch, U.S. Department of the Treasury. All bonds signed
by an agent or attorney-in-fact must be accompanied by a sealed and dated power of attorney
which shall show that it is effective on the date the agent or attorney-in-fact signed each bond.
D. If the surety on any bond furnished by Contractor is declared bankrupt or becomes insolvent or
its right to do business is terminated in the State of Texas or it ceases to meet the requirements of
Paragraph 4.02.C, Contractor shall promptly notify City and shall, within 30 days after the event
giving rise to such notification, provide another bond and surety, both of which shall comply
with the requirements of Paragraphs 4.01 and 4.02.C.
4.03 Certificates of Insurance
Contractor shall deliver to Developer and City, with copies to each additional insured and loss payee
identified in these Standard City Conditions certificates of insurance (and other evidence of
insurance requested by City or any other additional insured) which Contractor is required to
purchase and maintain.
CREEKSIDE ESTATES PHASE 3
CITY PROJECT NO.
B2010078.030
100825
00 73 10- 8
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 8 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
1. The certificate of insurance shall document the City, an as “Additional Insured” on all
liability policies.
2. The Contractor’s general liability insurance shall include a, “per project” or “per location”,
endorsement, which shall be identified in the certificate of insurance provided to the City.
3. The certificate shall be signed by an agent authorized to bind coverage on behalf of the
insured, be complete in its entirety, and show complete insurance carrier names as listed in
the current A.M. Best Property & Casualty Guide
4. The insurers for all policies must be licensed and/or approved to do business in the State of
Texas. Except for workers’ compensation, all insurers must have a minimum rating of A-:
VII in the current A. M. Best Key Rating Guide or have reasonably equivalent financial
strength and solvency to the satisfaction of Risk Management. If the rating is below that
required, written approval of City is required.
5. All applicable policies shall include a Waiver of Subrogation (Rights of Recovery) in favor
of the City. In addition, the Contractor agrees to waive all rights of subrogation against the
Engineer (if applicable), and each additional insured identified in these Standard City
Conditions. Failure of the City to demand such certificates or other evidence of full
compliance with the insurance requirements or failure of the City to identify a deficiency
from evidence that is provided shall not be construed as a waiver of Contractor’s obligation
to maintain such lines of insurance coverage.
6. If insurance policies are not written for specified coverage limits, an Umbrella or Excess
Liability insurance for any differences is required. Excess Liability shall follow form of the
primary coverage.
7. Unless otherwise stated, all required insurance shall be written on the “occurrence basis”. If
coverage is underwritten on a claims-made basis, the retroactive date shall be coincident with
or prior to the date of the effective date of the agreement and the certificate of insurance shall
state that the coverage is claims-made and the retroactive date. The insurance coverage shall
be maintained for the duration of the Contract and for three (3) years following Final
Acceptance provided under the Contract Documents or for the warranty period, whichever is
longer. An annual certificate of insurance submitted to the City shall evidence such
insurance coverage.
8. Policies shall have no exclusions by endorsements, which, neither nullify or amend, the
required lines of coverage, nor decrease the limits of said coverage unless such endorsements
are approved in writing by the City. In the event a Contract has been bid or executed and the
exclusions are determined to be unacceptable or the City desires additional insurance
coverage, and the City desires the contractor/engineer to obtain such coverage, the contract
price shall be adjusted by the cost of the premium for such additional coverage plus 10%.
9. Any self-insured retention (SIR), in excess of $25,000.00, affecting required insurance
coverage shall be approved by the City in regards to asset value and stockholders' equity. In
CREEKSIDE ESTATES PHASE 3
CITY PROJECT NO.
B2010078.030
100825
00 73 10- 9
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 9 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
lieu of traditional insurance, alternative coverage maintained through insurance pools or risk
retention groups, must also be approved by City.
10. Any deductible in excess of $5,000.00, for any policy that does not provide coverage on a
first-dollar basis, must be acceptable to and approved by the City.
11. City, at its sole discretion, reserves the right to review the insurance requirements and to
make reasonable adjustments to insurance coverage’s and their limits when deemed
necessary and prudent by the City based upon changes in statutory law, court decision or the
claims history of the industry as well as of the contracting party to the City. The City shall
be required to provide prior notice of 90 days, and the insurance adjustments shall be
incorporated into the Work by Change Order.
12. City shall be entitled, upon written request and without expense, to receive copies of policies
and endorsements thereto and may make any reasonable requests for deletion or revision or
modifications of particular policy terms, conditions, limitations, or exclusions necessary to
conform the policy and endorsements to the requirements of the Contract. Deletions,
revisions, or modifications shall not be required where policy provisions are established by
law or regulations binding upon either party or the underwriter on any such policies.
13. City shall not be responsible for the direct payment of insurance premium costs for
Contractor’s insurance.
4.04 Contractor’s Insurance
A. Workers Compensation and Employers’ Liability. Contractor shall purchase and maintain such
insurance coverage with limits consistent with statutory benefits outlined in the Texas Workers’
Compensation Act (Texas Labor Code, Ch. 406, as amended), and minimum limits for
Employers’ Liability as is appropriate for the Work being performed and as will provide
protection from claims set forth below which may arise out of or result from Contractor’s
performance of the Work and Contractor’s other obligations under the Contract Documents,
whether it is to be performed by Contractor, any Subcontractor or Supplier, or by anyone directly
or indirectly employed by any of them to perform any of the Work, or by anyone for whose acts
any of them may be liable:
1. claims under workers’ compensation, disability benefits, and other similar employee benefit
acts;
2. claims for damages because of bodily injury, occupational sickness or disease, or death of
Contractor’s employees.
3. The limits of liability for the insurance shall provide the following coverages for not less
than the following amounts or greater where required by Laws and Regulations
a. Statutory limits
b. Employer's liability CREEKSIDE ESTATES PHASE 3
CITY PROJECT NO.
B2010078.030
100825
00 73 10- 10
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 10 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
1) $100,000 each accident/occurrence
2) $100,000 Disease - each employee
3) $500,000 Disease - policy limit
B. Commercial General Liability. Coverage shall include but not be limited to covering liability
(bodily injury or property damage) arising from: premises/operations, independent contractors,
products/completed operations, personal injury, and liability under an insured contract. Insurance
shall be provided on an occurrence basis, and as comprehensive as the current Insurance
Services Office (ISO) policy. This insurance shall apply as primary insurance with respect to
any other insurance or self-insurance programs afforded to the City. The Commercial General
Liability policy, shall have no exclusions by endorsements that would alter of nullify
premises/operations, products/completed operations, contractual, personal injury, or advertising
injury, which are normally contained with the policy, unless the City approves such exclusions
in writing.
1. For construction projects that present a substantial completed operation exposure, the City
may require the contractor to maintain completed operations coverage for a minimum of no
less than three (3) years following the completion of the project
2. Contractor's Liability Insurance under this Section which shall be on a per project basis
covering the Contractor with minimum limits of:
a. $1,000,000 each occurrence
b. $2,000,000 aggregate limit
3. The policy must have an endorsement (Amendment – Aggregate Limits of Insurance)
making the General Aggregate Limits apply separately to each job site.
4. The Commercial General Liability Insurance policies shall provide “X”, “C”, and “U”
coverage’s. Verification of such coverage must be shown in the Remarks Article of the
Certificate of Insurance.
C. Automobile Liability. A commercial business auto policy shall provide coverage on “any auto”,
defined as autos owned, hired and non-owned and provide indemnity for claims for damages
because bodily injury or death of any person and or property damage arising out of the work,
maintenance or use of any motor vehicle by the Contractor, any Subcontractor or Supplier, or by
anyone directly or indirectly employed by any of them to perform any of the Work, or by anyone
for whose acts any of them may be liable.
1. Automobile Liability, Contractor’s Liability Insurance under this Section, which shall be in
an amount not less than the following amounts:
a. Automobile Liability - a commercial business policy shall provide coverage on "Any
Auto", defined as autos owned, hired and non-owned.
CREEKSIDE ESTATES PHASE 3
CITY PROJECT NO.
B2010078.030
100825
00 73 10- 11
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 11 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
1) $1,000,000 each accident on a combined single limit basis. Split limits are
acceptable if limits are at least:
2) $250,000 Bodily Injury per person
3) $500,000 Bodily Injury per accident /
4) $100,000 Property Damage
D. Railroad Protective Liability. If any of the work or any warranty work is within the limits of
railroad right-of-way, the Contractor shall comply with the following requirements:
1. The Contractor’s construction activities will require its employees, agents, subcontractors,
equipment, and material deliveries to cross railroad properties and tracks owned and
operated by: ____________________________________________________________
Write the name of the railroad company. (If none, then write none)
2. The Contractor shall conduct its operations on railroad properties in such a manner as not to
interfere with, hinder, or obstruct the railroad company in any manner whatsoever in the use
or operation of its/their trains or other property. Such operations on railroad properties may
require that Contractor to execute a “Right of Entry Agreement” with the particular railroad
company or companies involved, and to this end the Contractor should satisfy itself as to the
requirements of each railroad company and be prepared to execute the right-of-entry (if any)
required by a railroad company. The requirements specified herein likewise relate to the
Contractor’s use of private and/or construction access roads crossing said railroad company’s
properties.
3. The Contractual Liability coverage required by Paragraph 5.04D of the General Conditions
shall provide coverage for not less than the following amounts, issued by companies
satisfactory to the City and to the Railroad Company for a term that continues for so long as
the Contractor’s operations and work cross, occupy, or touch railroad property:
a. General Aggregate: _____________________________________
Enter limits provided by Railroad Company (If none, write none)
b. Each Occurrence: : _____________________________________
Enter limits provided by Railroad Company (If none, write none)
4. With respect to the above outlined insurance requirements, the following shall govern:
a. Where a single railroad company is involved, the Contractor shall provide one insurance
policy in the name of the railroad company. However, if more than one grade separation
or at-grade crossing is affected by the Project at entirely separate locations on the line or
lines of the same railroad company, separate coverage may be required, each in the
amount stated above.
b. Where more than one railroad company is operating on the same right-of-way or where
several railroad companies are involved and operated on their own separate rights-of-
CREEKSIDE ESTATES PHASE 3
CITY PROJECT NO.
B2010078.030
100825
00 73 10- 12
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 12 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
way, the Contractor may be required to provide separate insurance policies in the name
of each railroad company.
c. If, in addition to a grade separation or an at-grade crossing, other work or activity is
proposed on a railroad company’s right-of-way at a location entirely separate from the
grade separation or at-grade crossing, insurance coverage for this work must be included
in the policy covering the grade separation.
d. If no grade separation is involved but other work is proposed on a railroad company’s
right-of-way, all such other work may be covered in a single policy for that railroad, even
though the work may be at two or more separate locations.
5. No work or activities on a railroad company’s property to be performed by the Contractor
shall be commenced until the Contractor has furnished the City with an original policy or
policies of the insurance for each railroad company named, as required above. All such
insurance must be approved by the City and each affected Railroad Company prior to the
Contractor’s beginning work.
6. The insurance specified above must be carried until all Work to be performed on the railroad
right-of-way has been completed and the grade crossing, if any, is no longer used by the
Contractor. In addition, insurance must be carried during all maintenance and/or repair work
performed in the railroad right-of-way. Such insurance must name the railroad company as
the insured, together with any tenant or lessee of the railroad company operating over tracks
involved in the Project.
E. Notification of Policy Cancellation: Contractor shall immediately notify City upon cancellation
or other loss of insurance coverage. Contractor shall stop work until replacement insurance has
been procured. There shall be no time credit for days not worked pursuant to this section.
4.05 Acceptance of Bonds and Insurance; Option to Replace
If City has any objection to the coverage afforded by or other provisions of the bonds or insurance
required to be purchased and maintained by the Contractor in accordance with Article 5 on the basis
of non-conformance with the Contract Documents, the Developer and City shall so notify the
Contractor in writing within 10 Business Days after receipt of the certificates (or other evidence
requested). Contractor shall provide to the City such additional information in respect of insurance
provided as the Developer or City may reasonably request. If Contractor does not purchase or
maintain all of the bonds and insurance required by the Contract Documents, the Developer or City
shall notify the Contractor in writing of such failure prior to the start of the Work, or of such failure
to maintain prior to any change in the required coverage.
ARTICLE 5 – CONTRACTOR’S RESPONSIBILITIES
5.01 Supervision and Superintendent
A. Contractor shall supervise, inspect, and direct the Work competently and efficiently, devoting
such attention thereto and applying such skills and expertise as may be necessary to perform the
CREEKSIDE ESTATES PHASE 3
CITY PROJECT NO.
B2010078.030
100825
00 73 10- 13
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 13 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
Work in accordance with the Contract Documents. Contractor shall be solely responsible for the
means, methods, techniques, sequences, and procedures of construction.
B. At all times during the progress of the Work, Contractor shall assign a competent, English-
speaking, Superintendent who shall not be replaced without written notice to City. The
Superintendent will be Contractor’s representative at the Site and shall have authority to act on
behalf of Contractor. All communication given to or received from the Superintendent shall be
binding on Contractor.
C. Contractor shall notify the City 24 hours prior to moving areas during the sequence of
construction.
5.02 Labor; Working Hours
A. Contractor shall provide competent, suitably qualified personnel to perform construction as
required by the Contract Documents. Contractor shall at all times maintain good discipline and
order at the Site.
B. Except as otherwise required for the safety or protection of persons or the Work or property at
the Site or adjacent thereto, and except as otherwise stated in the Contract Documents, all Work
at the Site shall be performed during Regular Working Hours. Contractor will not permit the
performance of Work beyond Regular Working Hours or for Weekend Working Hours without
City’s written consent (which will not be unreasonably withheld). Written request (by letter or
electronic communication) to perform Work:
1. for beyond Regular Working Hours request must be made by noon at least two (2) Business
Days prior
2. for Weekend Working Hours request must be made by noon of the preceding Thursday
3. for legal holidays request must be made by noon two Business Days prior to the legal
holiday.
5.03 Services, Materials, and Equipment
A. Unless otherwise specified in the Contract Documents, Contractor shall provide and assume full
responsibility for all services, materials, equipment, labor, transportation, construction
equipment and machinery, tools, appliances, fuel, power, light, heat, telephone, water, sanitary
facilities, temporary facilities, and all other facilities and incidentals necessary for the
performance, Contractor required testing, start-up, and completion of the Work.
B. All materials and equipment incorporated into the Work shall be as specified or, if not specified,
shall be of good quality and new, except as otherwise provided in the Contract Documents. All
special warranties and guarantees required by the Specifications shall expressly run to the benefit
of City. If required by City, Contractor shall furnish satisfactory evidence (including reports of
required tests) as to the source, kind, and quality of materials and equipment.
CREEKSIDE ESTATES PHASE 3
CITY PROJECT NO.
B2010078.030
100825
00 73 10- 14
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 14 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
C. All materials and equipment to be incorporated into the Work shall be stored, applied, installed,
connected, erected, protected, used, cleaned, and conditioned in accordance with instructions of
the applicable Supplier, except as otherwise may be provided in the Contract Documents.
5.04 Project Schedule
A. Contractor shall adhere to the Project Schedule established in accordance with Paragraph 2.01
and the General Requirements as it may be adjusted from time to time as provided below.
1. Contractor shall submit to City for acceptance (to the extent indicated in Paragraph 2.01 and
the General Requirements) proposed adjustments in the Project Schedule.
2. Proposed adjustments in the Project Schedule that will change the Contract Time shall be
submitted in accordance with the requirements of Article 9. Adjustments in Contract Time
for projects with City participation shall be made by participating change orders.
5.05 Substitutes and “Or-Equals”
A. Whenever an item of material or equipment is specified or described in the Contract Documents
by using the name of a proprietary item or the name of a particular Supplier, the specification or
description is intended to establish the type, function, appearance, and quality required. Unless
the specification or description contains or is followed by words reading that no like, equivalent,
or “or-equal” item or no substitution is permitted, other items of material or equipment of other
Suppliers may be submitted to City for review under the circumstances described below.
1. “Or-Equal” Items: If in City’s sole discretion an item of material or equipment proposed by
Contractor is functionally equal to that named and sufficiently similar so that no change in
related Work will be required, it may be considered by City as an “or-equal” item, in which
case review and approval of the proposed item may, in City’s sole discretion, be
accomplished without compliance with some or all of the requirements for approval of
proposed substitute items. For the purposes of this Paragraph 5.05.A.1, a proposed item of
material or equipment will be considered functionally equal to an item so named if:
a. City determines that:
1) it is at least equal in materials of construction, quality, durability, appearance,
strength, and design characteristics;
2) it will reliably perform at least equally well the function and achieve the results
imposed by the design concept of the completed Project as a functioning whole; and
3) it has a proven record of performance and availability of responsive service; and
b. Contractor certifies that, if approved and incorporated into the Work:
1) there will be no increase in cost to the City or increase in Contract Time; and
CREEKSIDE ESTATES PHASE 3
CITY PROJECT NO.
B2010078.030
100825
00 73 10- 15
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 15 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
2) it will conform substantially to the detailed requirements of the item named in the
Contract Documents.
2. Substitute Items:
a. If in City’s sole discretion an item of material or equipment proposed by Contractor does
not qualify as an “or-equal” item under Paragraph 5.05.A.1, it may be submitted as a
proposed substitute item.
b. Contractor shall submit sufficient information as provided below to allow City to
determine if the item of material or equipment proposed is essentially equivalent to that
named and an acceptable substitute therefor. Requests for review of proposed substitute
items of material or equipment will not be accepted by City from anyone other than
Contractor.
c. Contractor shall make written application to City for review of a proposed substitute item
of material or equipment that Contractor seeks to furnish or use. The application shall
comply with Section 01 25 00 and:
1) shall certify that the proposed substitute item will:
i. perform adequately the functions and achieve the results called for by the general
design;
ii. be similar in substance to that specified;
iii. be suited to the same use as that specified; and
2) will state:
i. the extent, if any, to which the use of the proposed substitute item will prejudice
Contractor’s achievement of final completion on time;
ii. whether use of the proposed substitute item in the Work will require a change in
any of the Contract Documents (or in the provisions of any other direct contract
with City for other work on the Project) to adapt the design to the proposed
substitute item;
iii. whether incorporation or use of the proposed substitute item in connection with
the Work is subject to payment of any license fee or royalty; and
3) will identify:
i. all variations of the proposed substitute item from that specified;
ii. available engineering, sales, maintenance, repair, and replacement services; and
CREEKSIDE ESTATES PHASE 3
CITY PROJECT NO.
B2010078.030
100825
00 73 10- 16
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 16 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
4) shall contain an itemized estimate of all costs or credits that will result directly or
indirectly from use of such substitute item, including costs of redesign and Damage
Claims of other contractors affected by any resulting change.
B. Substitute Construction Methods or Procedures: If a specific means, method, technique,
sequence, or procedure of construction is expressly required by the Contract Documents,
Contractor may furnish or utilize a substitute means, method, technique, sequence, or procedure
of construction approved by City. Contractor shall submit sufficient information to allow City, in
City’s sole discretion, to determine that the substitute proposed is equivalent to that expressly
called for by the Contract Documents. Contractor shall make written application to City for
review in the same manner as those provided in Paragraph 5.05.A.2.
C. City’s Evaluation: City will be allowed a reasonable time within which to evaluate each
proposal or submittal made pursuant to Paragraphs 5.05.A and 5.05.B. City may require
Contractor to furnish additional data about the proposed substitute. City will be the sole judge of
acceptability. No “or-equal” or substitute will be ordered, installed or utilized until City’s review
is complete, which will be evidenced by a Change Order in the case of a substitute and an
accepted Submittal for an “or-equal.” City will advise Contractor in writing of its determination.
D. Special Guarantee: City may require Contractor to furnish at Contractor’s expense a special
performance guarantee, warranty, or other surety with respect to any substitute. Contractor shall
indemnify and hold harmless City and anyone directly or indirectly employed by them from and
against any and all claims, damages, losses and expenses (including attorneys fees) arising out
of the use of substituted materials or equipment.
E. City’s Cost Reimbursement: City will record City’s costs in evaluating a substitute proposed or
submitted by Contractor pursuant to Paragraphs 5.05.A.2 and 5.05.B. Whether or not City
approves a substitute so proposed or submitted by Contractor, Contractor may be required to
reimburse City for evaluating each such proposed substitute. Contractor may also be required to
reimburse City for the charges for making changes in the Contract Documents.
F. Contractor’s Expense: Contractor shall provide all data in support of any proposed substitute or
“or-equal” at Contractor’s expense.
G. Substitute Reimbursement: Costs (savings or charges) attributable to acceptance of a substitute
shall be incorporated to the Contract by Participating Change Order.
5.06 Pre-Qualification of Bidders (Prime Contractors and Subcontractors)
A. The Contractor and any subcontractors are required to be prequalified for the work types
requiring pre-qualification
5.07 Concerning Subcontractors, Suppliers, and Others
A. Minority and Women Owned Business Enterprise Compliance:
CREEKSIDE ESTATES PHASE 3
CITY PROJECT NO.
B2010078.030
100825
00 73 10- 17
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 17 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
Required for this Contract.
(Check this box if there is any City Participation)
Not Required for this Contract.
It is City policy to ensure the full and equitable participation by Minority and Women Business
Enterprises (MWBE) in the procurement of goods and services on a contractual basis. If the
Contract Documents provide for a MWBE goal, Contractor is required to comply with the intent
of the City’s MWBE Ordinance (as amended) by the following:
1. Contractor shall, upon request by City, provide complete and accurate information regarding
actual work performed by a MWBE on the Contract and payment therefor.
2. Contractor will not make additions, deletions, or substitutions of accepted MWBE without
written consent of the City. Any unjustified change or deletion shall be a material breach of
Contract and may result in debarment in accordance with the procedures outlined in the
Ordinance.
3. Contractor shall, upon request by City, allow an audit and/or examination of any books,
records, or files in the possession of the Contractor that will substantiate the actual work
performed by an MWBE. Material misrepresentation of any nature will be grounds for
termination of the Contract. Any such misrepresentation may be grounds for disqualification
of Contractor to bid on future contracts with the City for a period of not less than three years.
B. Contractor shall be fully responsible to City for all acts and omissions of the Subcontractors,
Suppliers, and other individuals or entities performing or furnishing any of the Work just as
Contractor is responsible for Contractor’s own acts and omissions. Nothing in the Contract
Documents:
1. shall create for the benefit of any such Subcontractor, Supplier, or other individual or entity
any contractual relationship between City and any such Subcontractor, Supplier or other
individual or entity; nor
2. shall create any obligation on the part of City to pay or to see to the payment of any moneys
due any such Subcontractor, Supplier, or other individual or entity except as may otherwise
be required by Laws and Regulations.
C. Contractor shall be solely responsible for scheduling and coordinating the Work of
Subcontractors, Suppliers, and other individuals or entities performing or furnishing any of the
Work under a direct or indirect contract with Contractor.
D. All Subcontractors, Suppliers, and such other individuals or entities performing or furnishing
any of the Work shall communicate with City through Contractor.
E. All Work performed for Contractor by a Subcontractor or Supplier will be pursuant to an
appropriate agreement between Contractor and the Subcontractor or Supplier which specifically
binds the Subcontractor or Supplier to the applicable terms and conditions of these Contract
CREEKSIDE ESTATES PHASE 3
CITY PROJECT NO.
B2010078.030
100825
00 73 10- 18
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 18 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
Documents, Contractor shall provide City contract numbers and reference numbers to the
Subcontractors and/or Suppliers.
5.08 Wage Rates
Required for this Contract.
Not Required for this Contract.
A. Duty to pay Prevailing Wage Rates. The Contractor shall comply with all requirements of
Chapter 2258, Texas Government Code (as amended), including the payment of not less than the
rates determined by the City Council of the City of Fort Worth to be the prevailing wage rates in
accordance with Chapter 2258. Such prevailing wage rates are included in these Contract
Documents.
B. Penalty for Violation. A Contractor or any Subcontractor who does not pay the prevailing wage
shall, upon demand made by the City, pay to the City $60 for each worker employed for each
calendar day or part of the day that the worker is paid less than the prevailing wage rates
stipulated in these contract documents. This penalty shall be retained by the City to offset its
administrative costs, pursuant to Texas Government Code 2258.023.
C. Complaints of Violations and City Determination of Good Cause. On receipt of information,
including a complaint by a worker, concerning an alleged violation of 2258.023, Texas
Government Code, by a Contractor or Subcontractor, the City shall make an initial
determination, before the 31st day after the date the City receives the information, as to whether
good cause exists to believe that the violation occurred. The City shall notify in writing the
Contractor or Subcontractor and any affected worker of its initial determination. Upon the
City’s determination that there is good cause to believe the Contractor or Subcontractor has
violated Chapter 2258, the City shall retain the full amounts claimed by the claimant or
claimants as the difference between wages paid and wages due under the prevailing wage rates,
such amounts being subtracted from successive progress payments pending a final determination
of the violation.
D. Arbitration Required if Violation Not Resolved. An issue relating to an alleged violation of
Section 2258.023, Texas Government Code, including a penalty owed to the City or an affected
worker, shall be submitted to binding arbitration in accordance with the Texas General
Arbitration Act (Article 224 et seq., Revised Statutes) if the Contractor or Subcontractor and any
affected worker does not resolve the issue by agreement before the 15th day after the date the
City makes its initial determination pursuant to Paragraph C above. If the persons required to
arbitrate under this section do not agree on an arbitrator before the 11th day after the date that
arbitration is required, a district court shall appoint an arbitrator on the petition of any of the
persons. The City is not a party in the arbitration. The decision and award of the arbitrator is
final and binding on all parties and may be enforced in any court of competent jurisdiction.
E. Records to be Maintained. The Contractor and each Subcontractor shall, for a period of three (3)
years following the date of acceptance of the work, maintain records that show (i) the name and
CREEKSIDE ESTATES PHASE 3
CITY PROJECT NO.
B2010078.030
100825
00 73 10- 19
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 19 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
occupation of each worker employed by the Contractor in the construction of the Work provided
for in this Contract; and (ii) the actual per diem wages paid to each worker. The records shall be
open at all reasonable hours for inspection by the City. The provisions of Paragraph 6.23, Right
to Audit, shall pertain to this inspection.
F. Progress Payments. With each progress payment or payroll period, whichever is less, the
Contractor shall submit an affidavit stating that the Contractor has complied with the
requirements of Chapter 2258, Texas Government Code.
G. Posting of Wage Rates. The Contractor shall post prevailing wage rates in a conspicuous place at
all times.
H. Subcontractor Compliance. The Contractor shall include in its subcontracts and/or shall
otherwise require all of its Subcontractors to comply with Paragraphs A through G above.
5.09 Patent Fees and Royalties
A. To the fullest extent permitted by Laws and Regulations, Contractor shall indemnify and hold
harmless City, from and against all claims, costs, losses, and damages (including but not limited
to all fees and charges of engineers, architects, attorneys, and other professionals and all court
or arbitration or other dispute resolution costs) arising out of or relating to any infringement of
patent rights or copyrights incident to the use in the performance of the Work or resulting from
the incorporation in the Work of any invention, design, process, product, or device not specified
in the Contract Documents.
5.10 Laws and Regulations
A. Contractor shall give all notices required by and shall comply with all Laws and Regulations
applicable to the performance of the Work. Except where otherwise expressly required by
applicable Laws and Regulations, the City shall not be responsible for monitoring Contractor’s
compliance with any Laws or Regulations.
B. If Contractor performs any Work knowing or having reason to know that it is contrary to Laws
or Regulations, Contractor shall bear all claims, costs, losses, and damages (including but not
limited to all fees and charges of engineers, architects, attorneys, and other professionals and all
court or arbitration or other dispute resolution costs) arising out of or relating to such Work.
However, it shall not be Contractor’s responsibility to make certain that the Specifications and
Drawings are in accordance with Laws and Regulations, but this shall not relieve Contractor of
Contractor’s obligations under Paragraph 3.01.
5.11 Use of Site and Other Areas
A. Limitation on Use of Site and Other Areas:
1. Contractor shall confine construction equipment, the storage of materials and equipment, and
the operations of workers to the Site and other areas permitted by Laws and Regulations, and
shall not unreasonably encumber the Site and other areas with construction equipment or
CREEKSIDE ESTATES PHASE 3
CITY PROJECT NO.
B2010078.030
100825
00 73 10- 20
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 20 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
other materials or equipment. Contractor shall assume full responsibility for any damage to
any such land or area, or to the owner or occupant thereof, or of any adjacent land or areas
resulting from the performance of the Work.
2. At any time when, in the judgment of the City, the Contractor has obstructed or closed or is
carrying on operations in a portion of a street, right-of-way, or easement greater than is
necessary for proper execution of the Work, the City may require the Contractor to finish the
section on which operations are in progress before work is commenced on any additional
area of the Site.
3. Should any Damage Claim be made by any such owner or occupant because of the
performance of the Work, Contractor shall promptly attempt to resolve the Damage Claim.
4. Pursuant to Paragraph 5.18, Contractor shall indemnify and hold harmless City, from and
against all claims, costs, losses, and damages arising out of or relating to any claim or
action, legal or equitable, brought by any such owner or occupant against City.
B. Removal of Debris During Performance of the Work: During the progress of the Work
Contractor shall keep the Site and other areas free from accumulations of waste materials,
rubbish, and other debris. Removal and disposal of such waste materials, rubbish, and other
debris shall conform to applicable Laws and Regulations.
C. Site Maintenance Cleaning: 24 hours after written notice is given to the Contractor that the
clean-up on the job site is proceeding in a manner unsatisfactory to the City or Developer, if the
Contractor fails to correct the unsatisfactory procedure, the City may take such direct action as
the City deems appropriate to correct the clean-up deficiencies cited to the Contractor in the
written notice (by letter or electronic communication), and shall be entitled to recover its cost in
doing so. The City may withhold Final Acceptance until clean-up is complete and cost are
recovered.
D. Final Site Cleaning: Prior to Final Acceptance of the Work Contractor shall clean the Site and
the Work and make it ready for utilization by City or adjacent property owner. At the completion
of the Work Contractor shall remove from the Site all tools, appliances, construction equipment
and machinery, and surplus materials and shall restore to original condition or better all property
disturbed by the Work.
E. Loading Structures: Contractor shall not load nor permit any part of any structure to be loaded
in any manner that will endanger the structure, nor shall Contractor subject any part of the Work
or adjacent property to stresses or pressures that will endanger it.
5.12 Record Documents
A. Contractor shall maintain in a safe place at the Site or in a place designated by the Contractor
and approved by the City, one (1) record copy of all Drawings, Specifications, Addenda, Change
Orders, Field Orders, and written interpretations and clarifications in good order and annotated
to show changes made during construction. These record documents together with all approved
CREEKSIDE ESTATES PHASE 3
CITY PROJECT NO.
B2010078.030
100825
00 73 10- 21
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 21 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
Samples and a counterpart of all accepted Submittals will be available to City for reference.
Upon completion of the Work, these record documents, any operation and maintenance manuals,
and Submittals will be delivered to City prior to Final Inspection. Contractor shall include
accurate locations for buried and imbedded items.
5.13 Safety and Protection
A. Contractor shall be solely responsible for initiating, maintaining and supervising all safety
precautions and programs in connection with the Work. Such responsibility does not relieve
Subcontractors of their responsibility for the safety of persons or property in the performance of
their work, nor for compliance with applicable safety Laws and Regulations. Contractor shall
take all necessary precautions for the safety of, and shall provide the necessary protection to
prevent damage, injury or loss to:
1. all persons on the Site or who may be affected by the Work;
2. all the Work and materials and equipment to be incorporated therein, whether in storage on
or off the Site; and
3. other property at the Site or adjacent thereto, including trees, shrubs, lawns, walks,
pavements, roadways, structures, utilities, and Underground Facilities not designated for
removal, relocation, or replacement in the course of construction.
B. Contractor shall comply with all applicable Laws and Regulations relating to the safety of
persons or property, or to the protection of persons or property from damage, injury, or loss; and
shall erect and maintain all necessary safeguards for such safety and protection. Contractor shall
notify owners of adjacent property and of Underground Facilities and other utility owners when
prosecution of the Work may affect them, and shall cooperate with them in the protection,
removal, relocation, and replacement of their property.
C. Contractor shall comply with the applicable requirements of City’s safety programs, if any.
D. Contractor shall inform City of the specific requirements of Contractor’s safety program, if any,
with which City’s employees and representatives must comply while at the Site.
E. All damage, injury, or loss to any property referred to in Paragraph 5.13.A.2 or 5.13.A.3 caused,
directly or indirectly, in whole or in part, by Contractor, any Subcontractor, Supplier, or any
other individual or entity directly or indirectly employed by any of them to perform any of the
Work, or anyone for whose acts any of them may be liable, shall be remedied by Contractor.
F. Contractor’s duties and responsibilities for safety and for protection of the Work shall continue
until such time as all the Work is completed and City has accepted the Work.
5.14 Safety Representative
Contractor shall inform City in writing of Contractor’s designated safety representative at the Site.
CREEKSIDE ESTATES PHASE 3
CITY PROJECT NO.
B2010078.030
100825
00 73 10- 22
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 22 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
5.15 Hazard Communication Programs
Contractor shall be responsible for coordinating any exchange of material safety data sheets or other
hazard communication information required to be made available to or exchanged between or
among employers in accordance with Laws or Regulations.
5.16 Submittals
A. Contractor shall submit required Submittals to City for review and acceptance. Each submittal
will be identified as required by City.
1. Submit number of copies specified in the General Requirements.
2. Data shown on the Submittals will be complete with respect to quantities, dimensions,
specified performance and design criteria, materials, and similar data to show City the
services, materials, and equipment Contractor proposes to provide and to enable City to
review the information for the limited purposes required by Paragraph 5.16.C.
3. Submittals submitted as herein provided by Contractor and reviewed by City for
conformance with the design concept shall be executed in conformity with the Contract
Documents unless otherwise required by City.
4. When Submittals are submitted for the purpose of showing the installation in greater detail,
their review shall not excuse Contractor from requirements shown on the Drawings and
Specifications.
5. For-Information-Only submittals upon which the City is not expected to conduct review or
take responsive action may be so identified in the Contract Documents.
6. Submit required number of Samples specified in the Specifications.
7. Clearly identify each Sample as to material, Supplier, pertinent data such as catalog numbers,
the use for which intended and other data as City may require to enable City to review the
submittal for the limited purposes required by Paragraph 5.16.C.
B. Where a Submittal is required by the Contract Documents or the Schedule of Submittals, any
related Work performed prior to City’s review and acceptance of the pertinent submittal will be
at the sole expense and responsibility of Contractor.
C. City’s Review:
1. City will provide timely review of required Submittals in accordance with the Schedule of
Submittals acceptable to City. City’s review and acceptance will be only to determine if the
items covered by the submittals will, after installation or incorporation in the Work, conform
to the information given in the Contract Documents and be compatible with the design
concept of the completed Project as a functioning whole as indicated by the Contract
Documents.
CREEKSIDE ESTATES PHASE 3
CITY PROJECT NO.
B2010078.030
100825
00 73 10- 23
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 23 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
2. City’s review and acceptance will not extend to means, methods, techniques, sequences, or
procedures of construction (except where a particular means, method, technique, sequence,
or procedure of construction is specifically and expressly called for by the Contract
Documents) or to safety precautions or programs incident thereto. The review and
acceptance of a separate item as such will not indicate approval of the assembly in which the
item functions.
3. City’s review and acceptance shall not relieve Contractor from responsibility for any
variation from the requirements of the Contract Documents unless Contractor has complied
with the requirements of Section 01 33 00 and City has given written acceptance of each
such variation by specific written notation thereof incorporated in or accompanying the
Submittal. City’s review and acceptance shall not relieve Contractor from responsibility for
complying with the requirements of the Contract Documents.
5.17 Contractor’s General Warranty and Guarantee
A. Contractor warrants and guarantees to City that all Work will be in accordance with the Contract
Documents and will not be defective. City and its officers, directors, members, partners,
employees, agents, consultants, and subcontractors shall be entitled to rely on representation of
Contractor’s warranty and guarantee.
B. Contractor’s warranty and guarantee hereunder excludes defects or damage caused by:
1. abuse, modification, or improper maintenance or operation by persons other than Contractor,
Subcontractors, Suppliers, or any other individual or entity for whom Contractor is
responsible; or
2. normal wear and tear under normal usage.
C. Contractor’s obligation to perform and complete the Work in accordance with the Contract
Documents shall be absolute. None of the following will constitute an acceptance of Work that is
not in accordance with the Contract Documents or a release of Contractor’s obligation to
perform the Work in accordance with the Contract Documents:
1. observations by City;
2. recommendation or payment by City or Developer of any progress or final payment;
3. the issuance of a certificate of Final Acceptance by City or any payment related thereto by
City;
4. use or occupancy of the Work or any part thereof by City;
5. any review and acceptance of a Submittal by City;
6. any inspection, test, or approval by others; or
CREEKSIDE ESTATES PHASE 3
CITY PROJECT NO.
B2010078.030
100825
00 73 10- 24
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 24 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
7. any correction of defective Work by City.
D. The Contractor shall remedy any defects or damages in the Work and pay for any damage to
other work or property resulting therefrom which shall appear within a period of two (2) years
from the date of Final Acceptance of the Work unless a longer period is specified and shall
furnish a good and sufficient maintenance bond, complying with the requirements of Article
4.02.B. The City will give notice of observed defects with reasonable promptness.
5.18 Indemnification
A. Contractor covenants and agrees to indemnify, hold harmless and defend, at its own expense, the
City, its officers, servants and employees, from and against any and all claims arising out of, or
alleged to arise out of, the work and services to be performed by the Contractor, its officers,
agents, employees, subcontractors, licenses or invitees under this Contract. THIS
INDEMNIFICATION PROVISION IS SPECIFICALLY INTENDED TO OPERATE
AND BE EFFECTIVE EVEN IF IT IS ALLEGED OR PROVEN THAT ALL OR SOME
OF THE DAMAGES BEING SOUGHT WERE CAUSED, IN WHOLE OR IN PART, BY
ANY ACT, OMISSION OR NEGLIGENCE OF THE CITY. This indemnity provision is
intended to include, without limitation, indemnity for costs, expenses and legal fees incurred by
the City in defending against such claims and causes of actions.
B. Contractor covenants and agrees to indemnify and hold harmless, at its own expense, the City, its
officers, servants and employees, from and against any and all loss, damage or destruction of
property of the City, arising out of, or alleged to arise out of, the work and services to be
performed by the Contractor, its officers, agents, employees, subcontractors, licensees or invitees
under this Contract. THIS INDEMNIFICATION PROVISION IS SPECIFICALLY
INTENDED TO OPERATE AND BE EFFECTIVE EVEN IF IT IS ALLEGED OR
PROVEN THAT ALL OR SOME OF THE DAMAGES BEING SOUGHT WERE
CAUSED, IN WHOLE OR IN PART, BY ANY ACT, OMISSION OR NEGLIGENCE OF
THE CITY.
5.19 Delegation of Professional Design Services
A. Contractor will not be required to provide professional design services unless such services are
specifically required by the Contract Documents for a portion of the Work or unless such
services are required to carry out Contractor’s responsibilities for construction means, methods,
techniques, sequences and procedures.
B. If professional design services or certifications by a design professional related to systems,
materials or equipment are specifically required of Contractor by the Contract Documents, City
will specify all performance and design criteria that such services must satisfy. Contractor shall
cause such services or certifications to be provided by a properly licensed professional, whose
signature and seal shall appear on all drawings, calculations, specifications, certifications, and
Submittals prepared by such professional. Submittals related to the Work designed or certified
by such professional, if prepared by others, shall bear such professional’s written approval when
submitted to City.
CREEKSIDE ESTATES PHASE 3
CITY PROJECT NO.
B2010078.030
100825
00 73 10- 25
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 25 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
C. City shall be entitled to rely upon the adequacy, accuracy and completeness of the services,
certifications or approvals performed by such design professionals, provided City has specified
to Contractor performance and design criteria that such services must satisfy.
D. Pursuant to this Paragraph 5.19, City’s review and acceptance of design calculations and design
drawings will be only for the limited purpose of checking for conformance with performance
and design criteria given and the design concept expressed in the Contract Documents. City’s
review and acceptance of Submittals (except design calculations and design drawings) will be
only for the purpose stated in Paragraph 5.16.C.
5.20 Right to Audit:
A. The City reserves the right to audit all projects utilizing City funds
B. The Contractor agrees that the City shall, until the expiration of three (3) years after final
payment under this Contract, have access to and the right to examine and photocopy any directly
pertinent books, documents, papers, and records of the Contractor involving transactions relating
to this Contract. Contractor agrees that the City shall have access during Regular Working Hours
to all necessary Contractor facilities and shall be provided adequate and appropriate work space
in order to conduct audits in compliance with the provisions of this Paragraph. The City shall
give Contractor reasonable advance notice of intended audits.
C. Contractor further agrees to include in all its subcontracts hereunder a provision to the effect that
the subcontractor agrees that the City shall, until the expiration of three (3) years after final
payment under this Contract, have access to and the right to examine and photocopy any directly
pertinent books, documents, papers, and records of such Subcontractor, involving transactions to
the subcontract, and further, that City shall have access during Regular Working Hours to all
Subcontractor facilities, and shall be provided adequate and appropriate work space in order to
conduct audits in compliance with the provisions of this Paragraph. The City shall give
Subcontractor reasonable advance notice of intended audits.
D. Contractor and Subcontractor agree to photocopy such documents as may be requested by the
City. The City agrees to reimburse Contractor for the cost of the copies as follows at the rate
published in the Texas Administrative Code in effect as of the time copying is performed.
5.21 Nondiscrimination
A. The City is responsible for operating Public Transportation Programs and implementing transit-
related projects, which are funded in part with Federal financial assistance awarded by the U.S.
Department of Transportation and the Federal Transit Administration (FTA), without
discriminating against any person in the United States on the basis of race, color, or national
origin.
B. Title VI, Civil Rights Act of 1964 as amended: Contractor shall comply with the requirements of
the Act and the Regulations as further defined in the Supplementary Conditions for any project
receiving Federal assistance.
CREEKSIDE ESTATES PHASE 3
CITY PROJECT NO.
B2010078.030
100825
00 73 10- 26
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 26 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
ARTICLE 6 – OTHER WORK AT THE SITE
6.01 Related Work at Site
A. City may perform other work related to the Project at the Site with City’s employees, or other
City contractors, or through other direct contracts therefor, or have other work performed by
utility owners. If such other work is not noted in the Contract Documents, then written notice
thereof will be given to Contractor prior to starting any such other work; and
B. Contractor shall afford each other contractor who is a party to such a direct contract, each utility
owner, and City, if City is performing other work with City’s employees or other City
contractors, proper and safe access to the Site, provide a reasonable opportunity for the
introduction and storage of materials and equipment and the execution of such other work, and
properly coordinate the Work with theirs. Contractor shall do all cutting, fitting, and patching of
the Work that may be required to properly connect or otherwise make its several parts come
together and properly integrate with such other work. Contractor shall not endanger any work of
others by cutting, excavating, or otherwise altering such work; provided, however, that
Contractor may cut or alter others' work with the written consent of City and the others whose
work will be affected.
C. If the proper execution or results of any part of Contractor’s Work depends upon work
performed by others under this Article 7, Contractor shall inspect such other work and promptly
report to City in writing any delays, defects, or deficiencies in such other work that render it
unavailable or unsuitable for the proper execution and results of Contractor’s Work. Contractor’s
failure to so report will constitute an acceptance of such other work as fit and proper for
integration with Contractor’s Work except for latent defects in the work provided by others.
ARTICLE 7 – CITY’S RESPONSIBILITIES
7.01 Inspections, Tests, and Approvals
City’s responsibility with respect to certain inspections, tests, and approvals is set forth in Paragraph
11.03.
7.02 Limitations on City’s Responsibilities
A. The City shall not supervise, direct, or have control or authority over, nor be responsible for,
Contractor’s means, methods, techniques, sequences, or procedures of construction, or the safety
precautions and programs incident thereto, or for any failure of Contractor to comply with Laws
and Regulations applicable to the performance of the Work. City will not be responsible for
Contractor’s failure to perform the Work in accordance with the Contract Documents.
B. City will notify the Contractor of applicable safety plans pursuant to Paragraph 5.13.
CREEKSIDE ESTATES PHASE 3
CITY PROJECT NO.
B2010078.030
100825
00 73 10- 27
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 27 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
7.03 Compliance with Safety Program
While at the Site, City’s employees and representatives shall comply with the specific applicable
requirements of Contractor’s safety programs of which City has been informed pursuant to
Paragraph 5.13.
ARTICLE 8 – CITY’S OBSERVATION STATUS DURING CONSTRUCTION
8.01 City’s Project Representative
City will provide one or more Project Representative(s) during the construction period. The duties
and responsibilities and the limitations of authority of City’s representative during construction are
set forth in the Contract Documents.
A. City’s Project Representative will make visits to the Site at intervals appropriate to the various
stages of construction as City deems necessary in order to observe the progress that has been
made and the quality of the various aspects of Contractor’s executed Work. Based on
information obtained during such visits and observations, City’s Project Representative will
determine, in general, if the Work is proceeding in accordance with the Contract Documents.
City’s Project Representative will not be required to make exhaustive or continuous inspections
on the Site to check the quality or quantity of the Work. City’s Project Representative’s efforts
will be directed toward providing City a greater degree of confidence that the completed Work
will conform generally to the Contract Documents.
B. City’s Project Representative’s visits and observations are subject to all the limitations on
authority and responsibility in the Contract Documents.
8.02 Authorized Variations in Work
City’s Project Representative may authorize minor variations in the Work from the requirements of
the Contract Documents which do not involve an adjustment in the Contract Price or the Contract
Time and are compatible with the design concept of the completed Project as a functioning whole as
indicated by the Contract Documents. These may be accomplished by a Field Order and will be
binding on City Developer, and also on Contractor, who shall perform the Work involved promptly.
8.03 Rejecting Defective Work
City will have authority to reject Work which City’s Project Representative believes to be defective,
or will not produce a completed Project that conforms to the Contract Documents or that will
prejudice the integrity of the design concept of the completed Project as a functioning whole as
indicated by the Contract Documents. City will have authority to conduct special inspection or
testing of the Work as provided in Article 11, whether or not the Work is fabricated, installed, or
completed.
CREEKSIDE ESTATES PHASE 3
CITY PROJECT NO.
B2010078.030
100825
00 73 10- 28
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 28 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
8.04 Determinations for Work Performed
Contractor will determine the actual quantities and classifications of Work performed. City’s Project
Representative will review with Contractor the preliminary determinations on such matters before
rendering a written recommendation. City’s written decision will be final (except as modified to
reflect changed factual conditions or more accurate data).
ARTICLE 9 – CHANGES IN THE WORK
9.01 Authorized Changes in the Work
A. Without invalidating the Contract and without notice to any surety, City may, at any time or
from time to time, order Extra Work. Upon notice of such Extra Work, Contractor shall
promptly proceed with the Work involved which will be performed under the applicable
conditions of the Contract Documents (except as otherwise specifically provided). Extra Work
shall be memorialized by a Participating Change Order which may or may not precede an order
of Extra work.
B. For minor changes of Work not requiring changes to Contract Time or Contract Price on a
project with City participation, a Field Order may be issued by the City.
9.02 Notification to Surety
If the provisions of any bond require notice to be given to a surety of any change affecting the
general scope of the Work or the provisions of the Contract Documents (including, but not limited
to, Contract Price or Contract Time), the giving of any such notice will be Contractor’s
responsibility. The amount of each applicable bond will be adjusted by the Contractor to reflect the
effect of any such change.
ARTICLE 10 – CHANGE OF CONTRACT PRICE; CHANGE OF CONTRACT TIME
10.01 Change of Contract Price
A. The Contract Price may only be changed by a Participating Change Order for projects with City
participation.
10.02 Change of Contract Time
A. The Contract Time may only be changed by a Participating Change Order for projects with City
participation.
10.03 Delays
A. If Contractor is delayed, City shall not be liable to Contractor for any claims, costs, losses, or
damages (including but not limited to all fees and charges of engineers, architects, attorneys, and
other professionals and all court or arbitration or other dispute resolution costs) sustained by
Contractor on or in connection with any other project or anticipated project.
CREEKSIDE ESTATES PHASE 3
CITY PROJECT NO.
B2010078.030
100825
00 73 10- 29
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 29 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
ARTICLE 11 – TESTS AND INSPECTIONS; CORRECTION, REMOVAL OR ACCEPTANCE OF
DEFECTIVE WORK
11.01 Notice of Defects
Notice of all defective Work of which City has actual knowledge will be given to Contractor.
Defective Work may be rejected, corrected, or accepted as provided in this Article 13.
11.02 Access to Work
City, independent testing laboratories, and governmental agencies with jurisdictional interests will
have access to the Site and the Work at reasonable times for their observation, inspection, and
testing. Contractor shall provide them proper and safe conditions for such access and advise them of
Contractor’s safety procedures and programs so that they may comply therewith as applicable.
11.03 Tests and Inspections
A. Contractor shall give City timely notice of readiness of the Work for all required inspections,
tests, or approvals and shall cooperate with inspection and testing personnel to facilitate required
inspections or tests.
B. If Contract Documents, Laws or Regulations of any public body having jurisdiction require any
of the Work (or part thereof) to be inspected, tested, or approved, Contractor shall assume full
responsibility for arranging and obtaining such independent inspections, tests, retests or
approvals, pay all costs in connection therewith, and furnish City the required certificates of
inspection or approval; excepting, however, those fees specifically identified in the
Supplementary Conditions or any Texas Department of Licensure and Regulation (TDLR)
inspections, which shall be paid as described in the Supplementary Conditions.
C. Contractor shall be responsible for arranging and obtaining and shall pay all costs in connection
with any inspections, tests, re-tests, or approvals required for City’s acceptance of materials or
equipment to be incorporated in the Work; or acceptance of materials, mix designs, or equipment
submitted for approval prior to Contractor’s purchase thereof for incorporation in the Work.
Such inspections, tests, re-tests, or approvals shall be performed by organizations approved by
City.
D. City may arrange for the services of an independent testing laboratory (“Testing Lab”) to
perform any inspections or tests (“Testing”) for any part of the Work, as determined solely by
City.
1. City will coordinate such Testing to the extent possible, with Contractor;
2. Should any Testing under this Section 11.03 D result in a “fail”, “did not pass” or other
similar negative result, the Contractor shall be responsible for paying for any and all retests.
Contractor’s cancellation without cause of City initiated Testing shall be deemed a negative
result and require a retest.
CREEKSIDE ESTATES PHASE 3
CITY PROJECT NO.
B2010078.030
100825
00 73 10- 30
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 30 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
3. Any amounts owed for any retest under this Section 11.03 D shall be paid directly to the
Testing Lab by Contractor. City will forward all invoices for retests to
Developer/Contractor.
4. If Contractor fails to pay the Testing Lab, City will not issue a letter of Final Acceptance
until the Testing Lab is Paid
E. If any Work (or the work of others) that is to be inspected, tested, or approved is covered by
Contractor without written concurrence of City, Contractor shall, if requested by City, uncover
such Work for observation.
11.04 Uncovering Work
A. If any Work is covered contrary to the Contract Documents or specific instructions by the City, it
must, if requested by City, be uncovered for City’s observation and replaced at Contractor’s
expense.
11.05 City May Stop the Work
If the Work is defective, or Contractor fails to supply sufficient skilled workers or suitable materials
or equipment, or fails to perform the Work in such a way that the completed Work will conform to
the Contract Documents, City may order Contractor to stop the Work, or any portion thereof, until
the cause for such order has been eliminated; however, this right of City to stop the Work shall not
give rise to any duty on the part of City to exercise this right for the benefit of Contractor, any
Subcontractor, any Supplier, any other individual or entity, or any surety for, or employee or agent
of any of them.
11.06 Correction or Removal of Defective Work
A. Promptly after receipt of written notice, Contractor shall correct all defective Work pursuant to
an acceptable schedule, whether or not fabricated, installed, or completed, or, if the Work has
been rejected by City, remove it from the Project and replace it with Work that is not defective.
Contractor shall pay all claims, costs, additional testing, losses, and damages (including but not
limited to all fees and charges of engineers, architects, attorneys, and other professionals and all
court or arbitration or other dispute resolution costs) arising out of or relating to such correction
or removal (including but not limited to all costs of repair or replacement of work of others).
Failure to require the removal of any defective Work shall not constitute acceptance of such
Work.
B. When correcting defective Work under the terms of this Paragraph 11.06 or Paragraph 11.07,
Contractor shall take no action that would void or otherwise impair City’s special warranty and
guarantee, if any, on said Work.
11.07 Correction Period
A. If within two (2) years after the date of Final Acceptance (or such longer period of time as may
be prescribed by the terms of any applicable special guarantee required by the Contract
CREEKSIDE ESTATES PHASE 3
CITY PROJECT NO.
B2010078.030
100825
00 73 10- 31
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 31 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
Documents), any Work is found to be defective, or if the repair of any damages to the land or
areas made available for Contractor’s use by City or permitted by Laws and Regulations as
contemplated in Paragraph 5.10.A is found to be defective, Contractor shall promptly, without
cost to City and in accordance with City’s written instructions:
1. repair such defective land or areas; or
2. correct such defective Work; or
3. if the defective Work has been rejected by City, remove it from the Project and replace it
with Work that is not defective, and
4. satisfactorily correct or repair or remove and replace any damage to other Work, to the work
of others or other land or areas resulting therefrom.
B. If Contractor does not promptly comply with the terms of City’s written instructions, or in an
emergency where delay would cause serious risk of loss or damage, City may have the defective
Work corrected or repaired or may have the rejected Work removed and replaced. All claims,
costs, losses, and damages (including but not limited to all fees and charges of engineers,
architects, attorneys, and other professionals and all court or other dispute resolution costs)
arising out of or relating to such correction or repair or such removal and replacement (including
but not limited to all costs of repair or replacement of work of others) will be paid by Contractor.
C. Where defective Work (and damage to other Work resulting therefrom) has been corrected or
removed and replaced under this Paragraph 11.07, the correction period hereunder with respect
to such Work may be required to be extended for an additional period of one year after the end
of the initial correction period. City shall provide 30 days written notice to Contractor and
Developer should such additional warranty coverage be required. Contractor’s obligations under
this Paragraph 11.07 are in addition to any other obligation or warranty. The provisions of this
Paragraph 11.07 shall not be construed as a substitute for, or a waiver of, the provisions of any
applicable statute of limitation or repose.
11.08 City May Correct Defective Work
A. If Contractor fails within a reasonable time after written notice from City to correct defective
Work, or to remove and replace rejected Work as required by City in accordance with Paragraph
11.06.A, or if Contractor fails to perform the Work in accordance with the Contract Documents,
or if Contractor fails to comply with any other provision of the Contract Documents, City may,
after seven (7) days written notice to Contractor and the Developer, correct, or remedy any such
deficiency.
B. In exercising the rights and remedies under this Paragraph 11.09, City shall proceed
expeditiously. In connection with such corrective or remedial action, City may exclude
Contractor from all or part of the Site, take possession of all or part of the Work and suspend
Contractor’s services related thereto, and incorporate in the Work all materials and equipment
incorporated in the Work, stored at the Site or for which City has paid Contractor but which are
CREEKSIDE ESTATES PHASE 3
CITY PROJECT NO.
B2010078.030
100825
00 73 10- 32
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 32 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
stored elsewhere. Contractor shall allow City, City’s representatives, agents, consultants,
employees, and City’s other contractors, access to the Site to enable City to exercise the rights
and remedies under this Paragraph.
C. All claims, costs, losses, and damages (including but not limited to all fees and charges of
engineers, architects, attorneys, and other professionals and all court or other dispute resolution
costs) incurred or sustained by City in exercising the rights and remedies under this Paragraph
13.09 will be charged against Contractor, and a Change Order will be issued incorporating the
necessary revisions in the Contract Documents with respect to the Work; and City shall be
entitled to an appropriate decrease in the Contract Price.
D. Contractor shall not be allowed an extension of the Contract Time because of any delay in the
performance of the Work attributable to the exercise of City’s rights and remedies under this
Paragraph 11.09.
ARTICLE 12 – COMPLETION
12.01 Contractor’s Warranty of Title
Contractor warrants and guarantees that title to all Work, materials, and equipment covered by any
Application for Payment will pass to City no later than the time of Final Acceptance and shall be
free and clear of all Liens.
12.02 Partial Utilization
A. Prior to Final Acceptance of all the Work, City may use or occupy any substantially completed
part of the Work which has specifically been identified in the Contract Documents, or which
City, determines constitutes a separately functioning and usable part of the Work that can be
used by City for its intended purpose without significant interference with Contractor’s
performance of the remainder of the Work. City at any time may notify Contractor in writing to
permit City to use or occupy any such part of the Work which City determines to be ready for its
intended use, subject to the following conditions:
1. Contractor at any time may notify City in writing that Contractor considers any such part of
the Work ready for its intended use.
2. Within a reasonable time after notification as enumerated in Paragraph 14.05.A.1, City and
Contractor shall make an inspection of that part of the Work to determine its status of
completion. If City does not consider that part of the Work to be substantially complete, City
will notify Contractor in writing giving the reasons therefor.
3. Partial Utilization will not constitute Final Acceptance by City.
12.03 Final Inspection
A. Upon written notice from Contractor that the entire Work is complete in accordance with the
Contract Documents:
CREEKSIDE ESTATES PHASE 3
CITY PROJECT NO.
B2010078.030
100825
00 73 10- 33
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 33 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
1. within 10 days, City will schedule a Final Inspection with Contractor.
2. City will notify Contractor in writing of all particulars in which this inspection reveals that
the Work is incomplete or defective. Contractor shall immediately take such measures as are
necessary to complete such Work or remedy such deficiencies.
12.04 Final Acceptance
A. Upon completion by Contractor to City’s satisfaction, of any additional Work identified in the
Final Inspection, City will issue to Contractor a letter of Final Acceptance upon the satisfaction
of the following:
1. All documentation called for in the Contract Documents, including but not limited to the
evidence of insurance required by Paragraph 5.03;
2. consent of the surety, if any, to Final Acceptance;
3. a list of all pending or released Damage Claims against City that Contractor believes are
unsettled; and
4. affidavits of payments and complete and legally effective releases or waivers (satisfactory to
City) of all Lien rights arising out of or Liens filed in connection with the Work.
5. after all Damage Claims have been resolved:
a. directly by the Contractor or;
b. Contractor provides evidence that the Damage Claim has been reported to Contractor’s
insurance provider for resolution.
6. Issuing Final Acceptance by the City shall not relieve the Contractor of any guarantees or
other requirements of the Contract Documents which specifically continue thereafter.
ARTICLE 13 – SUSPENSION OF WORK
13.01 City May Suspend Work
A. At any time and without cause, City may suspend the Work or any portion thereof by written
notice to Contractor and which may fix the date on which Work will be resumed. Contractor
shall resume the Work on the date so fixed. During temporary suspension of the Work covered
by these Contract Documents, for any reason, the City will stop contract time on City
participation projects.
B. Should the Contractor not be able to complete a portion of the Project due to causes beyond the
control of and without the fault or negligence of the Contractor, and should it be determined by
mutual consent of the Contractor and City that a solution to allow construction to proceed is not
CREEKSIDE ESTATES PHASE 3
CITY PROJECT NO.
B2010078.030
100825
00 73 10- 34
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 34 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
available within a reasonable period of time, Contractor may request an extension in Contract
Time, directly attributable to any such suspension.
C. If it should become necessary to suspend the Work for an indefinite period, the Contractor shall
store all materials in such a manner that they will not obstruct or impede the public unnecessarily
nor become damaged in any way, and he shall take every precaution to prevent damage or
deterioration of the work performed; he shall provide suitable drainage about the work, and erect
temporary structures where necessary.
ARTICLE 14 – MISCELLANEOUS
14.01 Giving Notice
A. Whenever any provision of the Contract Documents requires the giving of written notice, it will
be deemed to have been validly given if:
1. delivered in person to the individual or to a member of the firm or to an officer of the
corporation for whom it is intended; or
2. delivered at or sent by registered or certified mail, postage prepaid, to the last business
address known to the giver of the notice.
B. Business address changes must be promptly made in writing to the other party.
C. Whenever the Contract Documents specifies giving notice by electronic means such electronic
notice shall be deemed sufficient upon confirmation of receipt by the receiving party.
14.02 Computation of Times
When any period of time is referred to in the Contract Documents by days, it will be computed to
exclude the first and include the last day of such period. If the last day of any such period falls on a
Saturday or Sunday or on a day made a legal holiday the next Working Day shall become the last
day of the period.
14.03 Cumulative Remedies
The duties and obligations imposed by these General Conditions and the rights and remedies
available hereunder to the parties hereto are in addition to, and are not to be construed in any way as
a limitation of, any rights and remedies available to any or all of them which are otherwise imposed
or available by Laws or Regulations, by special warranty or guarantee, or by other provisions of the
Contract Documents. The provisions of this Paragraph will be as effective as if repeated specifically
in the Contract Documents in connection with each particular duty, obligation, right, and remedy to
which they apply.
CREEKSIDE ESTATES PHASE 3
CITY PROJECT NO.
B2010078.030
100825
00 73 10- 35
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 35 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
14.04 Survival of Obligations
All representations, indemnifications, warranties, and guarantees made in, required by, or given in
accordance with the Contract Documents, as well as all continuing obligations indicated in the
Contract Documents, will survive final payment, completion, and acceptance of the Work or
termination or completion of the Contract or termination of the services of Contractor.
14.05 Headings
Article and paragraph headings are inserted for convenience only and do not constitute parts of these
General Conditions.
CREEKSIDE ESTATES PHASE 3
CITY PROJECT NO.
B2010078.030
100825
01 11 00 - 1
DAP SUMMARY OF WORK
Page 1 of 3
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
SECTION 01 11 00 1
SUMMARY OF WORK 2
PART 1 - GENERAL 3
1.1 SUMMARY 4
A. Section Includes: 5
1. Summary of Work to be performed in accordance with the Contract Documents 6
B. Deviations from this City of Fort Worth Standard Specification 7
1. None. 8
C. Related Specification Sections include, but are not necessarily limited to: 9
1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the Contract 10
2. Division 1 - General Requirements 11
1.2 PRICE AND PAYMENT PROCEDURES 12
A. Measurement and Payment 13
1. Work associated with this Item is considered subsidiary to the various items bid. 14
No separate payment will be allowed for this Item. 15
1.3 REFERENCES [NOT USED] 16
1.4 ADMINISTRATIVE REQUIREMENTS 17
A. Work Covered by Contract Documents 18
1. Work is to include furnishing all labor, materials, and equipment, and performing 19
all Work necessary for this construction project as detailed in the Drawings and 20
Specifications. 21
B. Subsidiary Work 22
1. Any and all Work specifically governed by documentary requirements for the 23
project, such as conditions imposed by the Drawings or Contract Documents in 24
which no specific item for bid has been provided for in the Proposal and the item is 25
not a typical unit bid item included on the standard bid item list, then the item shall 26
be considered as a subsidiary item of Work, the cost of which shall be included in 27
the price bid in the Proposal for various bid items. 28
C. Use of Premises 29
1. Coordinate uses of premises under direction of the City. 30
2. Assume full responsibility for protection and safekeeping of materials and 31
equipment stored on the Site. 32
3. Use and occupy only portions of the public streets and alleys, or other public places 33
or other rights-of-way as provided for in the ordinances of the City, as shown in the 34
Contract Documents, or as may be specifically authorized in writing by the City. 35
a. A reasonable amount of tools, materials, and equipment for construction 36
purposes may be stored in such space, but no more than is necessary to avoid 37
delay in the construction operations. 38
100825
01 11 00 - 2
DAP SUMMARY OF WORK
Page 2 of 3
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
b. Excavated and waste materials shall be stored in such a way as not to interfere 1
with the use of spaces that may be designated to be left free and unobstructed 2
and so as not to inconvenience occupants of adjacent property. 3
c. If the street is occupied by railroad tracks, the Work shall be carried on in such 4
manner as not to interfere with the operation of the railroad. 5
1) All Work shall be in accordance with railroad requirements set forth in 6
Division 0 as well as the railroad permit. 7
D. Work within Easements 8
1. Do not enter upon private property for any purpose without having previously 9
obtained permission from the owner of such property. 10
2. Do not store equipment or material on private property unless and until the 11
specified approval of the property owner has been secured in writing by the 12
Contractor and a copy furnished to the City. 13
3. Unless specifically provided otherwise, clear all rights-of-way or easements of 14
obstructions which must be removed to make possible proper prosecution of the 15
Work as a part of the project construction operations. 16
4. Preserve and use every precaution to prevent damage to, all trees, shrubbery, plants, 17
lawns, fences, culverts, curbing, and all other types of structures or improvements, 18
to all water, sewer, and gas lines, to all conduits, overhead pole lines, or 19
appurtenances thereof, including the construction of temporary fences and to all 20
other public or private property adjacent to the Work. 21
5. Notify the proper representatives of the owners or occupants of the public or private 22
lands of interest in lands which might be affected by the Work. 23
a. Such notice shall be made at least 48 hours in advance of the beginning of the 24
Work. 25
b. Notices shall be applicable to both public and private utility companies and any 26
corporation, company, individual, or other, either as owners or occupants, 27
whose land or interest in land might be affected by the Work. 28
c. Be responsible for all damage or injury to property of any character resulting 29
from any act, omission, neglect, or misconduct in the manner or method or 30
execution of the Work, or at any time due to defective work, material, or 31
equipment. 32
6. Fence 33
a. Restore all fences encountered and removed during construction of the Project 34
to the original or a better than original condition. 35
b. Erect temporary fencing in place of the fencing removed whenever the Work is 36
not in progress and when the site is vacated overnight, and/or at all times to 37
provide site security. 38
c. The cost for all fence work within easements, including removal, temporary 39
closures and replacement, shall be subsidiary to the various items bid in the 40
project proposal, unless a bid item is specifically provided in the proposal. 41
100825
01 11 00 - 3
DAP SUMMARY OF WORK
Page 3 of 3
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
1.5 SUBMITTALS [NOT USED] 1
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 2
1.7 CLOSEOUT SUBMITTALS [NOT USED] 3
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 4
1.9 QUALITY ASSURANCE [NOT USED] 5
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 6
1.11 FIELD [SITE] CONDITIONS [NOT USED] 7
1.12 WARRANTY [NOT USED] 8
PART 2 - PRODUCTS [NOT USED] 9
PART 3 - EXECUTION [NOT USED] 10
END OF SECTION 11
12
Revision Log
DATE NAME SUMMARY OF CHANGE
13
100825
01 25 00 - 1
DAP SUBSTITUTION PROCEDURES
Page 1 of 5
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
Revised August 30, 2013
SECTION 01 25 00 1
SUBSTITUTION PROCEDURES 2
PART 1 - GENERAL 3
1.1 SUMMARY 4
A. Section Includes: 5
1. The procedure for requesting the approval of substitution of a product that is not 6
equivalent to a product which is specified by descriptive or performance criteria or 7
defined by reference to 1 or more of the following: 8
a. Name of manufacturer 9
b. Name of vendor 10
c. Trade name 11
d. Catalog number 12
2. Substitutions are not "or-equals". 13
B. Deviations from this City of Fort Worth Standard Specification 14
1. None. 15
C. Related Specification Sections include, but are not necessarily limited to: 16
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 17
2. Division 1 – General Requirements 18
1.2 PRICE AND PAYMENT PROCEDURES 19
A. Measurement and Payment 20
1. Work associated with this Item is considered subsidiary to the various items bid. No 21
separate payment will be allowed for this Item. 22
1.3 REFERENCES [NOT USED] 23
1.4 ADMINISTRATIVE REQUIREMENTS 24
A. Request for Substitution - General 25
1. Within 30 days after award of Contract (unless noted otherwise), the City will 26
consider formal requests from Contractor for substitution of products in place of 27
those specified. 28
2. Certain types of equipment and kinds of material are described in Specifications by 29
means of references to names of manufacturers and vendors, trade names, or catalog 30
numbers. 31
a. When this method of specifying is used, it is not intended to exclude from 32
consideration other products bearing other manufacturer's or vendor's names, 33
trade names, or catalog numbers, provided said products are "or-equals," as 34
determined by City. 35
3. Other types of equipment and kinds of material may be acceptable substitutions 36
under the following conditions: 37
100825
01 25 00 - 2
DAP SUBSTITUTION PROCEDURES
Page 2 of 5
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
Revised August 30, 2013
a. Or-equals are unavailable due to strike, discontinued production of products 1
meeting specified requirements, or other factors beyond control of Contractor; 2
or, 3
b. Contractor proposes a cost and/or time reduction incentive to the City. 4
1.5 SUBMITTALS 5
A. See Request for Substitution Form (attached) 6
B. Procedure for Requesting Substitution 7
1. Substitution shall be considered only: 8
a. After award of Contract 9
b. Under the conditions stated herein 10
2. Submit 3 copies of each written request for substitution, including: 11
a. Documentation 12
1) Complete data substantiating compliance of proposed substitution with 13
Contract Documents 14
2) Data relating to changes in construction schedule, when a reduction is 15
proposed 16
3) Data relating to changes in cost 17
b. For products 18
1) Product identification 19
a) Manufacturer's name 20
b) Telephone number and representative contact name 21
c) Specification Section or Drawing reference of originally specified 22
product, including discrete name or tag number assigned to original 23
product in the Contract Documents 24
2) Manufacturer's literature clearly marked to show compliance of proposed 25
product with Contract Documents 26
3) Itemized comparison of original and proposed product addressing product 27
characteristics including, but not necessarily limited to: 28
a) Size 29
b) Composition or materials of construction 30
c) Weight 31
d) Electrical or mechanical requirements 32
4) Product experience 33
a) Location of past projects utilizing product 34
b) Name and telephone number of persons associated with referenced 35
projects knowledgeable concerning proposed product 36
c) Available field data and reports associated with proposed product 37
5) Samples 38
a) Provide at request of City. 39
b) Samples become the property of the City. 40
c. For construction methods: 41
1) Detailed description of proposed method 42
2) Illustration drawings 43
C. Approval or Rejection 44
1. Written approval or rejection of substitution given by the City 45
100825
01 25 00 - 3
DAP SUBSTITUTION PROCEDURES
Page 3 of 5
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
Revised August 30, 2013
2. City reserves the right to require proposed product to comply with color and pattern 1
of specified product if necessary to secure design intent. 2
3. In the event the substitution is approved, if a reduction in cost or time results, it will 3
be documented by Change Order. 4
4. Substitution will be rejected if: 5
a. Submittal is not through the Contractor with his stamp of approval 6
b. Request is not made in accordance with this Specification Section 7
c. In the Developer’s opinion, acceptance will require substantial revision of the 8
original design 9
d. In the City’s or Developer’s opinion, substitution will not perform adequately 10
the function consistent with the design intent 11
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 12
1.7 CLOSEOUT SUBMITTALS [NOT USED] 13
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 14
1.9 QUALITY ASSURANCE 15
A. In making request for substitution or in using an approved product, the Contractor 16
represents that the Contractor: 17
1. Has investigated proposed product, and has determined that it is adequate or 18
superior in all respects to that specified, and that it will perform function for which it 19
is intended 20
2. Will provide same guarantee for substitute item as for product specified 21
3. Will coordinate installation of accepted substitution into Work, to include building 22
modifications if necessary, making such changes as may be required for Work to be 23
complete in all respects 24
4. Waives all claims for additional costs related to substitution which subsequently 25
arise 26
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 27
1.11 FIELD [SITE] CONDITIONS [NOT USED] 28
1.12 WARRANTY [NOT USED] 29
PART 2 - PRODUCTS [NOT USED] 30
PART 3 - EXECUTION [NOT USED] 31
END OF SECTION 32
33
Revision Log
DATE NAME SUMMARY OF CHANGE
100825
01 25 00 - 4
DAP SUBSTITUTION PROCEDURES
Page 4 of 5
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
Revised August 30, 2013
1
100825
01 25 00 - 5
DAP SUBSTITUTION PROCEDURES
Page 5 of 5
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
Revised August 30, 2013
EXHIBIT A 1
REQUEST FOR SUBSTITUTION FORM: 2
3
TO: 4
PROJECT: DATE: 5
We hereby submit for your consideration the following product instead of the specified item for 6
the above project: 7
SECTION PARAGRAPH SPECIFIED ITEM 8
9
10
Proposed Substitution: 11
Reason for Substitution: 12
Include complete information on changes to Drawings and/or Specifications which proposed 13
substitution will require for its proper installation. 14
15
Fill in Blanks Below: 16
A. Will the undersigned contractor pay for changes to the building design, including engineering 17
and detailing costs caused by the requested substitution? 18
19
20
B. What effect does substitution have on other trades? 21
22
23
C. Differences between proposed substitution and specified item? 24
25
26
D. Differences in product cost or product delivery time? 27
28
29
E. Manufacturer's guarantees of the proposed and specified items are: 30
31
Equal Better (explain on attachment) 32
The undersigned states that the function, appearance and quality are equivalent or superior to the 33
specified item. 34
Submitted By: For Use by City 35
36
Signature Recommended Recommended 37
as noted 38
39
Firm Not recommended Received late 40
Address By 41
Date 42
Date Remarks 43
Telephone 44
45
For Use by City: 46
47
Approved Rejected 48
City Date 49
100825
01 31 19 - 1
DAP PRECONSTRUCTION MEETING
Page 1 of 3
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
SECTION 01 31 19 1
PRECONSTRUCTION MEETING 2
PART 1 - GENERAL 3
1.1 SUMMARY 4
A. Section Includes: 5
1. Provisions for the preconstruction meeting to be held prior to the start of Work to 6
clarify construction contract administration procedures 7
B. Deviations from this City of Fort Worth Standard Specification 8
1. No construction schedule required unless requested by the City. 9
C. Related Specification Sections include, but are not necessarily limited to: 10
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 11
2. Division 1 – General Requirements 12
1.2 PRICE AND PAYMENT PROCEDURES 13
A. Measurement and Payment 14
1. Work associated with this Item is considered subsidiary to the various items bid. 15
No separate payment will be allowed for this Item. 16
1.3 REFERENCES [NOT USED] 17
1.4 ADMINISTRATIVE REQUIREMENTS 18
A. Coordination 19
1. Attend preconstruction meeting. 20
2. Representatives of Contractor, subcontractors and suppliers attending meetings 21
shall be qualified and authorized to act on behalf of the entity each represents. 22
3. Meeting administered by City may be tape recorded. 23
a. If recorded, tapes will be used to prepare minutes and retained by City for 24
future reference. 25
B. Preconstruction Meeting 26
1. A preconstruction meeting will be held within 14 days after the delivery of the 27
distribution package to the City. 28
a. The meeting will be scheduled and administered by the City. 29
2. The Project Representative will preside at the meeting, prepare the notes of the 30
meeting and distribute copies of same to all participants who so request by fully 31
completing the attendance form to be circulated at the beginning of the meeting. 32
3. Attendance shall include: 33
a. Developer and Consultant 34
b. Contractor's project manager 35
c. Contractor's superintendent 36
d. Any subcontractor or supplier representatives whom the Contractor may desire 37
to invite or the City may request 38
100825
01 31 19 - 2
DAP PRECONSTRUCTION MEETING
Page 2 of 3
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
e. Other City representatives 1
f. Others as appropriate 2
4. Preliminary Agenda may include: 3
a. Introduction of Project Personnel 4
b. General Description of Project 5
c. Status of right-of-way, utility clearances, easements or other pertinent permits 6
d. Contractor’s work plan and schedule 7
e. Contract Time 8
f. Notice to Proceed 9
g. Construction Staking 10
h. Progress Payments 11
i. Extra Work and Change Order Procedures 12
j. Field Orders 13
k. Disposal Site Letter for Waste Material 14
l. Insurance Renewals 15
m. Payroll Certification 16
n. Material Certifications and Quality Control Testing 17
o. Public Safety and Convenience 18
p. Documentation of Pre-Construction Conditions 19
q. Weekend Work Notification 20
r. Legal Holidays 21
s. Trench Safety Plans 22
t. Confined Space Entry Standards 23
u. Coordination with the City’s representative for operations of existing water 24
systems 25
v. Storm Water Pollution Prevention Plan 26
w. Coordination with other Contractors 27
x. Early Warning System 28
y. Contractor Evaluation 29
z. Special Conditions applicable to the project 30
aa. Damages Claims 31
bb. Submittal Procedures 32
cc. Substitution Procedures 33
dd. Correspondence Routing 34
ee. Record Drawings 35
ff. Temporary construction facilities 36
gg. MBE/SBE procedures 37
hh. Final Acceptance 38
ii. Final Payment 39
jj. Questions or Comments 40
100825
01 31 19 - 3
DAP PRECONSTRUCTION MEETING
Page 3 of 3
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
1.5 SUBMITTALS [NOT USED] 1
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 2
1.7 CLOSEOUT SUBMITTALS [NOT USED] 3
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 4
1.9 QUALITY ASSURANCE [NOT USED] 5
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 6
1.11 FIELD [SITE] CONDITIONS [NOT USED] 7
1.12 WARRANTY [NOT USED] 8
PART 2 - PRODUCTS [NOT USED] 9
PART 3 - EXECUTION [NOT USED] 10
END OF SECTION 11
12
Revision Log
DATE NAME SUMMARY OF CHANGE
13
100825
01 31 20 - 1
DAP PROJECT MEETINGS
Page 1 of 3
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
Revised July 1, 2011
SECTION 01 31 20 1
PROJECT MEETINGS 2
3
PART 1 - GENERAL 4
1.1 SUMMARY 5
A. Section Includes: 6
1. Provisions for project meetings throughout the construction period to enable orderly 7
review of the progress of the Work and to provide for systematic discussion of 8
potential problems 9
B. Deviations this City of Fort Worth Standard Specification 10
1. None. 11
C. Related Specification Sections include, but are not necessarily limited to: 12
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 13
2. Division 1 – General Requirements 14
1.2 PRICE AND PAYMENT PROCEDURES 15
A. Measurement and Payment 16
1. Work associated with this Item is considered subsidiary to the various items bid. 17
No separate payment will be allowed for this Item. 18
1.3 REFERENCES [NOT USED] 19
1.4 ADMINISTRATIVE REQUIREMENTS 20
A. Coordination 21
1. Schedule, attend and administer as specified, periodic progress meetings, and 22
specially called meetings throughout progress of the Work. 23
2. Representatives of Contractor, subcontractors and suppliers attending meetings 24
shall be qualified and authorized to act on behalf of the entity each represents. 25
3. Meetings administered by City may be tape recorded. 26
a. If recorded, tapes will be used to prepare minutes and retained by City for 27
future reference. 28
4. Meetings, in addition to those specified in this Section, may be held when requested 29
by the City, Engineer or Contractor. 30
B. Pre-Construction Neighborhood Meeting 31
1. After the execution of the Agreement, but before construction is allowed to begin, 32
attend 1 Public Meeting with affected residents to: 33
a. Present projected schedule, including construction start date 34
b. Answer any construction related questions 35
2. Meeting Location 36
100825
01 31 20 - 2
DAP PROJECT MEETINGS
Page 2 of 3
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
Revised July 1, 2011
a. Location of meeting to be determined by the City. 1
3. Attendees 2
a. Contractor 3
b. Project Representative 4
c. Other City representatives 5
4. Meeting Schedule 6
a. In general, the neighborhood meeting will occur within the 2 weeks following 7
the pre-construction conference. 8
b. In no case will construction be allowed to begin until this meeting is held. 9
C. Progress Meetings 10
1. Formal project coordination meetings will be held periodically. Meetings will be 11
scheduled and administered by Project Representative. 12
2. Additional progress meetings to discuss specific topics will be conducted on an as-13
needed basis. Such additional meetings shall include, but not be limited to: 14
a. Coordinating shutdowns 15
b. Installation of piping and equipment 16
c. Coordination between other construction projects 17
d. Resolution of construction issues 18
e. Equipment approval 19
3. The Project Representative will preside at progress meetings, prepare the notes of 20
the meeting and distribute copies of the same to all participants who so request by 21
fully completing the attendance form to be circulated at the beginning of each 22
meeting. 23
4. Attendance shall include: 24
a. Contractor's project manager 25
b. Contractor's superintendent 26
c. Any subcontractor or supplier representatives whom the Contractor may desire 27
to invite or the City may request 28
d. Engineer's representatives 29
e. City’s representatives 30
f. Others, as requested by the Project Representative 31
5. Preliminary Agenda may include: 32
a. Review of Work progress since previous meeting 33
b. Field observations, problems, conflicts 34
c. Items which impede construction schedule 35
d. Review of off-site fabrication, delivery schedules 36
e. Review of construction interfacing and sequencing requirements with other 37
construction contracts 38
f. Corrective measures and procedures to regain projected schedule 39
g. Revisions to construction schedule 40
h. Progress, schedule, during succeeding Work period 41
i. Coordination of schedules 42
j. Review submittal schedules 43
k. Maintenance of quality standards 44
l. Pending changes and substitutions 45
m. Review proposed changes for: 46
100825
01 31 20 - 3
DAP PROJECT MEETINGS
Page 3 of 3
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
Revised July 1, 2011
1) Effect on construction schedule and on completion date 1
2) Effect on other contracts of the Project 2
n. Review Record Documents 3
o. Review monthly pay request 4
p. Review status of Requests for Information 5
6. Meeting Schedule 6
a. Progress meetings will be held periodically as determined by the Project 7
Representative. 8
1) Additional meetings may be held at the request of the: 9
a) City 10
b) Engineer 11
c) Contractor 12
7. Meeting Location 13
a. The City will establish a meeting location. 14
1) To the extent practicable, meetings will be held at the Site. 15
1.5 SUBMITTALS [NOT USED] 16
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 17
1.7 CLOSEOUT SUBMITTALS [NOT USED] 18
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 19
1.9 QUALITY ASSURANCE [NOT USED] 20
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 21
1.11 FIELD [SITE] CONDITIONS [NOT USED] 22
1.12 WARRANTY [NOT USED] 23
PART 2 - PRODUCTS [NOT USED] 24
PART 3 - EXECUTION [NOT USED] 25
END OF SECTION 26
27
Revision Log
DATE NAME SUMMARY OF CHANGE
28
100825
01 32 16 - 1
DAP CONSTRUCTION PROGRESS SCHEDULE
Page 1 of 5
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
Revised July 1, 2011
SECTION 01 32 16 1
CONSTRUCTION PROGRESS SCHEDULE 2
PART 1 - GENERAL 3
1.1 SUMMARY 4
A. Section Includes: 5
1. General requirements for the preparation, submittal, updating, status reporting and 6
management of the Construction Progress Schedule 7
2. Specific requirements are presented in the City of Fort Worth Schedule Guidance 8
Document 9
B. Deviations from this City of Fort Worth Standard Specification 10
1. None. 11
C. Related Specification Sections include, but are not necessarily limited to: 12
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 13
2. Division 1 – General Requirements 14
1.2 PRICE AND PAYMENT PROCEDURES 15
A. Measurement and Payment 16
1. Work associated with this Item is considered subsidiary to the various items bid. 17
No separate payment will be allowed for this Item. 18
1.3 REFERENCES 19
A. Definitions 20
1. Schedule Tiers 21
a. Tier 1 - No schedule submittal required by contract. Small, brief duration 22
projects 23
b. Tier 2 - No schedule submittal required by contract, but will require some 24
milestone dates. Small, brief duration projects 25
c. Tier 3 - Schedule submittal required by contract as described in the 26
Specification and herein. Majority of City projects, including all bond program 27
projects 28
d. Tier 4 - Schedule submittal required by contract as described in the 29
Specification and herein. Large and/or complex projects with long durations 30
1) Examples: large water pump station project and associated pipeline with 31
interconnection to another governmental entity 32
e. Tier 5 - Schedule submittal required by contract as described in the 33
Specification and herein. Large and/or very complex projects with long 34
durations, high public visibility 35
1) Examples might include a water or wastewater treatment plant 36
2. Baseline Schedule - Initial schedule submitted before work begins that will serve 37
as the baseline for measuring progress and departures from the schedule. 38
100825
01 32 16 - 2
DAP CONSTRUCTION PROGRESS SCHEDULE
Page 2 of 5
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
Revised July 1, 2011
3. Progress Schedule - Monthly submittal of a progress schedule documenting 1
progress on the project and any changes anticipated. 2
4. Schedule Narrative - Concise narrative of the schedule including schedule 3
changes, expected delays, key schedule issues, critical path items, etc 4
B. Reference Standards 5
1. City of Fort Worth Schedule Guidance Document 6
1.4 ADMINISTRATIVE REQUIREMENTS 7
A. Baseline Schedule 8
1. General 9
a. Prepare a cost-loaded baseline Schedule using approved software and the 10
Critical Path Method (CPM) as required in the City of Fort Worth Schedule 11
Guidance Document. 12
b. Review the draft cost-loaded baseline Schedule with the City to demonstrate 13
understanding of the work to be performed and known issues and constraints 14
related to the schedule. 15
c. Designate an authorized representative (Project Scheduler) responsible for 16
developing and updating the schedule and preparing reports. 17
B. Progress Schedule 18
1. Update the progress Schedule monthly as required in the City of Fort Worth 19
Schedule Guidance Document. 20
2. Prepare the Schedule Narrative to accompany the monthly progress Schedule. 21
3. Change Orders 22
a. Incorporate approved change orders, resulting in a change of contract time, in 23
the baseline Schedule in accordance with City of Fort Worth Schedule 24
Guidance Document. 25
C. Responsibility for Schedule Compliance 26
1. Whenever it becomes apparent from the current progress Schedule and CPM Status 27
Report that delays to the critical path have resulted and the Contract completion 28
date will not be met, or when so directed by the City, make some or all of the 29
following actions at no additional cost to the City 30
a. Submit a Recovery Plan to the City for approval revised baseline Schedule 31
outlining: 32
1) A written statement of the steps intended to take to remove or arrest the 33
delay to the critical path in the approved schedule 34
2) Increase construction manpower in such quantities and crafts as will 35
substantially eliminate the backlog of work and return current Schedule to 36
meet projected baseline completion dates 37
3) Increase the number of working hours per shift, shifts per day, working 38
days per week, the amount of construction equipment, or any combination 39
of the foregoing, sufficiently to substantially eliminate the backlog of work 40
4) Reschedule activities to achieve maximum practical concurrency of 41
accomplishment of activities, and comply with the revised schedule 42
100825
01 32 16 - 3
DAP CONSTRUCTION PROGRESS SCHEDULE
Page 3 of 5
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
Revised July 1, 2011
2. If no written statement of the steps intended to take is submitted when so requested 1
by the City, the City may direct the Contractor to increase the level of effort in 2
manpower (trades), equipment and work schedule (overtime, weekend and holiday 3
work, etc.) to be employed by the Contractor in order to remove or arrest the delay 4
to the critical path in the approved schedule. 5
a. No additional cost for such work will be considered. 6
D. The Contract completion time will be adjusted only for causes specified in this 7
Contract. 8
a. Requests for an extension of any Contract completion date must be 9
supplemented with the following: 10
1) Furnish justification and supporting evidence as the City may deem 11
necessary to determine whether the requested extension of time is entitled 12
under the provisions of this Contract. 13
a) The City will, after receipt of such justification and supporting 14
evidence, make findings of fact and will advise the Contractor, in 15
writing thereof. 16
2) If the City finds that the requested extension of time is entitled, the City's 17
determination as to the total number of days allowed for the extensions 18
shall be based upon the approved total baseline schedule and on all data 19
relevant to the extension. 20
a) Such data shall be included in the next updating of the Progress 21
schedule. 22
b) Actual delays in activities which, according to the Baseline schedule, 23
do not affect any Contract completion date shown by the critical path in 24
the network will not be the basis for a change therein. 25
2. Submit each request for change in Contract completion date to the City within 30 26
days after the beginning of the delay for which a time extension is requested but 27
before the date of final payment under this Contract. 28
a. No time extension will be granted for requests which are not submitted within 29
the foregoing time limit. 30
b. From time to time, it may be necessary for the Contract schedule or completion 31
time to be adjusted by the City to reflect the effects of job conditions, weather, 32
technical difficulties, strikes, unavoidable delays on the part of the City or its 33
representatives, and other unforeseeable conditions which may indicate 34
schedule adjustments or completion time extensions. 35
1) Under such conditions, the City will direct the Contractor to reschedule the 36
work or Contract completion time to reflect the changed conditions and the 37
Contractor shall revise his schedule accordingly. 38
a) No additional compensation will be made to the Contractor for such 39
schedule changes except for unavoidable overall contract time 40
extensions beyond the actual completion of unaffected work, in which 41
case the Contractor shall take all possible action to minimize any time 42
extension and any additional cost to the City. 43
b) Available float time in the Baseline schedule may be used by the City 44
as well as by the Contractor. 45
100825
01 32 16 - 4
DAP CONSTRUCTION PROGRESS SCHEDULE
Page 4 of 5
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
Revised July 1, 2011
3. Float or slack time is defined as the amount of time between the earliest start date 1
and the latest start date or between the earliest finish date and the latest finish date 2
of a chain of activities on the Baseline Schedule. 3
a. Float or slack time is not for the exclusive use or benefit of either the 4
Contractor or the City. 5
b. Proceed with work according to early start dates, and the City shall have the 6
right to reserve and apportion float time according to the needs of the project. 7
c. Acknowledge and agree that actual delays, affecting paths of activities 8
containing float time, will not have any effect upon contract completion times, 9
providing that the actual delay does not exceed the float time associated with 10
those activities. 11
E. Coordinating Schedule with Other Contract Schedules 12
1. Where work is to be performed under this Contract concurrently with or contingent 13
upon work performed on the same facilities or area under other contracts, the 14
Baseline Schedule shall be coordinated with the schedules of the other contracts. 15
a. Obtain the schedules of the other appropriate contracts from the City for the 16
preparation and updating of Baseline schedule and make the required changes 17
in his schedule when indicated by changes in corresponding schedules. 18
2. In case of interference between the operations of different contractors, the City will 19
determine the work priority of each contractor and the sequence of work necessary 20
to expedite the completion of the entire Project. 21
a. In such cases, the decision of the City shall be accepted as final. 22
b. The temporary delay of any work due to such circumstances shall not be 23
considered as justification for claims for additional compensation. 24
1.5 SUBMITTALS 25
A. Baseline Schedule 26
1. Submit Schedule in native file format and pdf format as required in the City of Fort 27
Worth Schedule Guidance Document. 28
a. Native file format includes: 29
1) Primavera (P6 or Primavera Contractor) 30
2. Submit draft baseline Schedule to City prior to the pre-construction meeting and 31
bring in hard copy to the meeting for review and discussion. 32
B. Progress Schedule 33
1. Submit progress Schedule in native file format and pdf format as required in the 34
City of Fort Worth Schedule Guidance Document. 35
2. Submit progress Schedule monthly no later than the last day of the month. 36
C. Schedule Narrative 37
1. Submit the schedule narrative in pdf format as required in the City of Fort Worth 38
Schedule Guidance Document. 39
2. Submit schedule narrative monthly no later than the last day of the month. 40
D. Submittal Process 41
1. The City administers and manages schedules through Buzzsaw. 42
100825
01 32 16 - 5
DAP CONSTRUCTION PROGRESS SCHEDULE
Page 5 of 5
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
Revised July 1, 2011
2. Contractor shall submit documents as required in the City of Fort Worth Schedule 1
Guidance Document. 2
3. Once the project has been completed and Final Acceptance has been issued by the 3
City, no further progress schedules are required. 4
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 5
1.7 CLOSEOUT SUBMITTALS [NOT USED] 6
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 7
1.9 QUALITY ASSURANCE 8
A. The person preparing and revising the construction Progress Schedule shall be 9
experienced in the preparation of schedules of similar complexity. 10
B. Schedule and supporting documents addressed in this Specification shall be prepared, 11
updated and revised to accurately reflect the performance of the construction. 12
C. Contractor is responsible for the quality of all submittals in this section meeting the 13
standard of care for the construction industry for similar projects. 14
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 15
1.11 FIELD [SITE] CONDITIONS [NOT USED] 16
1.12 WARRANTY [NOT USED] 17
PART 2 - PRODUCTS [NOT USED] 18
PART 3 - EXECUTION [NOT USED] 19
END OF SECTION 20
21
Revision Log
DATE NAME SUMMARY OF CHANGE
22
100825
01 33 00 - 1
DAP SUBMITTALS
Page 1 of 8
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
SECTION 01 33 00 1
DAP SUBMITTALS 2
PART 1 - GENERAL 3
1.1 SUMMARY 4
A. Section Includes: 5
1. General methods and requirements of submissions applicable to the following 6
Work-related submittals: 7
a. Shop Drawings 8
b. Product Data (including Standard Product List submittals) 9
c. Samples 10
d. Mock Ups 11
B. Deviations from this City of Fort Worth Standard Specification 12
1. None. 13
C. Related Specification Sections include, but are not necessarily limited to: 14
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 15
2. Division 1 – General Requirements 16
1.2 PRICE AND PAYMENT PROCEDURES 17
A. Measurement and Payment 18
1. Work associated with this Item is considered subsidiary to the various items bid. 19
No separate payment will be allowed for this Item. 20
1.3 REFERENCES [NOT USED] 21
1.4 ADMINISTRATIVE REQUIREMENTS 22
A. Coordination 23
1. Notify the City in writing, at the time of submittal, of any deviations in the 24
submittals from the requirements of the Contract Documents. 25
2. Coordination of Submittal Times 26
a. Prepare, prioritize and transmit each submittal sufficiently in advance of 27
performing the related Work or other applicable activities, or within the time 28
specified in the individual Work Sections, of the Specifications. 29
b. Contractor is responsible such that the installation will not be delayed by 30
processing times including, but not limited to: 31
a) Disapproval and resubmittal (if required) 32
b) Coordination with other submittals 33
c) Testing 34
d) Purchasing 35
e) Fabrication 36
f) Delivery 37
g) Similar sequenced activities 38
c. No extension of time will be authorized because of the Contractor's failure to 39
transmit submittals sufficiently in advance of the Work. 40
100825
01 33 00 - 2
DAP SUBMITTALS
Page 2 of 8
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
d. Make submittals promptly in accordance with approved schedule, and in such 1
sequence as to cause no delay in the Work or in the work of any other 2
contractor. 3
B. Submittal Numbering 4
1. When submitting shop drawings or samples, utilize a 9-character submittal cross-5
reference identification numbering system in the following manner: 6
a. Use the first 6 digits of the applicable Specification Section Number. 7
b. For the next 2 digit number use numbers 01-99 to sequentially number each 8
initial separate item or drawing submitted under each specific Section number. 9
c. Last use a letter, A-Z, indicating the resubmission of the same drawing (i.e. 10
A=2nd submission, B=3rd submission, C=4th submission, etc.). A typical 11
submittal number would be as follows: 12
13
03 30 00-08-B 14
15
1) 03 30 00 is the Specification Section for Concrete 16
2) 08 is the eighth initial submittal under this Specification Section 17
3) B is the third submission (second resubmission) of that particular shop 18
drawing 19
C. Contractor Certification 20
1. Review shop drawings, product data and samples, including those by 21
subcontractors, prior to submission to determine and verify the following: 22
a. Field measurements 23
b. Field construction criteria 24
c. Catalog numbers and similar data 25
d. Conformance with the Contract Documents 26
2. Provide each shop drawing, sample and product data submitted by the Contractor 27
with a Certification Statement affixed including: 28
a. The Contractor's Company name 29
b. Signature of submittal reviewer 30
c. Certification Statement 31
1) “By this submittal, I hereby represent that I have determined and verified 32
field measurements, field construction criteria, materials, dimensions, 33
catalog numbers and similar data and I have checked and coordinated each 34
item with other applicable approved shop drawings." 35
D. Submittal Format 36
1. Fold shop drawings larger than 8 ½ inches x 11 inches to 8 ½ inches x 11inches. 37
2. Bind shop drawings and product data sheets together. 38
3. Order 39
a. Cover Sheet 40
1) Description of Packet 41
2) Contractor Certification 42
b. List of items / Table of Contents 43
c. Product Data /Shop Drawings/Samples /Calculations 44
E. Submittal Content 45
1. The date of submission and the dates of any previous submissions 46
100825
01 33 00 - 3
DAP SUBMITTALS
Page 3 of 8
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
2. The Project title and number 1
3. Contractor identification 2
4. The names of: 3
a. Contractor 4
b. Supplier 5
c. Manufacturer 6
5. Identification of the product, with the Specification Section number, page and 7
paragraph(s) 8
6. Field dimensions, clearly identified as such 9
7. Relation to adjacent or critical features of the Work or materials 10
8. Applicable standards, such as ASTM or Federal Specification numbers 11
9. Identification by highlighting of deviations from Contract Documents 12
10. Identification by highlighting of revisions on resubmittals 13
11. An 8-inch x 3-inch blank space for Contractor and City stamps 14
F. Shop Drawings 15
1. As specified in individual Work Sections includes, but is not necessarily limited to: 16
a. Custom-prepared data such as fabrication and erection/installation (working) 17
drawings 18
b. Scheduled information 19
c. Setting diagrams 20
d. Actual shopwork manufacturing instructions 21
e. Custom templates 22
f. Special wiring diagrams 23
g. Coordination drawings 24
h. Individual system or equipment inspection and test reports including: 25
1) Performance curves and certifications 26
i. As applicable to the Work 27
2. Details 28
a. Relation of the various parts to the main members and lines of the structure 29
b. Where correct fabrication of the Work depends upon field measurements 30
1) Provide such measurements and note on the drawings prior to submitting 31
for approval. 32
G. Product Data 33
1. For submittals of product data for products included on the City’s Standard Product 34
List, clearly identify each item selected for use on the Project. 35
2. For submittals of product data for products not included on the City’s Standard 36
Product List, submittal data may include, but is not necessarily limited to: 37
a. Standard prepared data for manufactured products (sometimes referred to as 38
catalog data) 39
1) Such as the manufacturer's product specification and installation 40
instructions 41
2) Availability of colors and patterns 42
3) Manufacturer's printed statements of compliances and applicability 43
4) Roughing-in diagrams and templates 44
5) Catalog cuts 45
6) Product photographs 46
100825
01 33 00 - 4
DAP SUBMITTALS
Page 4 of 8
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
7) Standard wiring diagrams 1
8) Printed performance curves and operational-range diagrams 2
9) Production or quality control inspection and test reports and certifications 3
10) Mill reports 4
11) Product operating and maintenance instructions and recommended 5
spare-parts listing and printed product warranties 6
12) As applicable to the Work 7
H. Samples 8
1. As specified in individual Sections, include, but are not necessarily limited to: 9
a. Physical examples of the Work such as: 10
1) Sections of manufactured or fabricated Work 11
2) Small cuts or containers of materials 12
3) Complete units of repetitively used products color/texture/pattern swatches 13
and range sets 14
4) Specimens for coordination of visual effect 15
5) Graphic symbols and units of Work to be used by the City for independent 16
inspection and testing, as applicable to the Work 17
I. Do not start Work requiring a shop drawing, sample or product data nor any material to 18
be fabricated or installed prior to the approval or qualified approval of such item. 19
1. Fabrication performed, materials purchased or on-site construction accomplished 20
which does not conform to approved shop drawings and data is at the Contractor's 21
risk. 22
2. The City will not be liable for any expense or delay due to corrections or remedies 23
required to accomplish conformity. 24
3. Complete project Work, materials, fabrication, and installations in conformance 25
with approved shop drawings, applicable samples, and product data. 26
J. Submittal Distribution 27
1. Electronic Distribution 28
a. Confirm development of Project directory for electronic submittals to be 29
uploaded to City’s Buzzsaw site, or another external FTP site approved by the 30
City. 31
b. Shop Drawings 32
1) Upload submittal to designated project directory and notify appropriate 33
City representatives via email of submittal posting. 34
2) Hard Copies 35
a) 3 copies for all submittals 36
b) If Contractor requires more than 1 hard copy of Shop Drawings 37
returned, Contractor shall submit more than the number of copies listed 38
above. 39
c. Product Data 40
1) Upload submittal to designated project directory and notify appropriate 41
City representatives via email of submittal posting. 42
2) Hard Copies 43
a) 3 copies for all submittals 44
d. Samples 45
1) Distributed to the Project Representative 46
2. Hard Copy Distribution (if required in lieu of electronic distribution) 47
100825
01 33 00 - 5
DAP SUBMITTALS
Page 5 of 8
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
a. Shop Drawings 1
1) Distributed to the City 2
2) Copies 3
a) 8 copies for mechanical submittals 4
b) 7 copies for all other submittals 5
c) If Contractor requires more than 3 copies of Shop Drawings returned, 6
Contractor shall submit more than the number of copies listed above. 7
b. Product Data 8
1) Distributed to the City 9
2) Copies 10
a) 4 copies 11
c. Samples 12
1) Distributed to the Project Representative 13
2) Copies 14
a) Submit the number stated in the respective Specification Sections. 15
3. Distribute reproductions of approved shop drawings and copies of approved 16
product data and samples, where required, to the job site file and elsewhere as 17
directed by the City. 18
a. Provide number of copies as directed by the City but not exceeding the number 19
previously specified. 20
K. Submittal Review 21
1. The review of shop drawings, data and samples will be for general conformance 22
with the design concept and Contract Documents. This is not to be construed as: 23
a. Permitting any departure from the Contract requirements 24
b. Relieving the Contractor of responsibility for any errors, including details, 25
dimensions, and materials 26
c. Approving departures from details furnished by the City, except as otherwise 27
provided herein 28
2. The review and approval of shop drawings, samples or product data by the City 29
does not relieve the Contractor from his/her responsibility with regard to the 30
fulfillment of the terms of the Contract. 31
a. All risks of error and omission are assumed by the Contractor, and the City will 32
have no responsibility therefore. 33
3. The Contractor remains responsible for details and accuracy, for coordinating the 34
Work with all other associated work and trades, for selecting fabrication processes, 35
for techniques of assembly and for performing Work in a safe manner. 36
4. If the shop drawings, data or samples as submitted describe variations and show a 37
departure from the Contract requirements which City finds to be in the interest of 38
the City and to be so minor as not to involve a change in Contract Price or time for 39
performance, the City may return the reviewed drawings without noting an 40
exception. 41
5. Submittals will be returned to the Contractor under 1 of the following codes: 42
a. Code 1 43
1) "NO EXCEPTIONS TAKEN" is assigned when there are no notations or 44
comments on the submittal. 45
a) When returned under this code the Contractor may release the 46
equipment and/or material for manufacture. 47
b. Code 2 48
100825
01 33 00 - 6
DAP SUBMITTALS
Page 6 of 8
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
1) "EXCEPTIONS NOTED". This code is assigned when a confirmation of 1
the notations and comments IS NOT required by the Contractor. 2
a) The Contractor may release the equipment or material for manufacture; 3
however, all notations and comments must be incorporated into the 4
final product. 5
c. Code 3 6
1) "EXCEPTIONS NOTED/RESUBMIT". This combination of codes is 7
assigned when notations and comments are extensive enough to require a 8
resubmittal of the package. 9
a) The Contractor may release the equipment or material for manufacture; 10
however, all notations and comments must be incorporated into the 11
final product. 12
b) This resubmittal is to address all comments, omissions and 13
non-conforming items that were noted. 14
c) Resubmittal is to be received by the City within 15 Calendar Days of 15
the date of the City's transmittal requiring the resubmittal. 16
d. Code 4 17
1) "NOT APPROVED" is assigned when the submittal does not meet the 18
intent of the Contract Documents. 19
a) The Contractor must resubmit the entire package revised to bring the 20
submittal into conformance. 21
b) It may be necessary to resubmit using a different manufacturer/vendor 22
to meet the Contract Documents. 23
6. Resubmittals 24
a. Handled in the same manner as first submittals 25
1) Corrections other than requested by the City 26
2) Marked with revision triangle or other similar method 27
a) At Contractor’s risk if not marked 28
b. Submittals for each item will be reviewed no more than twice at the City’s 29
expense. 30
1) All subsequent reviews will be performed at times convenient to the City 31
and at the Contractor's expense, based on the City's or City 32
Representative’s then prevailing rates. 33
2) Provide Contractor reimbursement to the City within 30 Calendar Days for 34
all such fees invoiced by the City. 35
c. The need for more than 1 resubmission or any other delay in obtaining City's 36
review of submittals, will not entitle the Contractor to an extension of Contract 37
Time. 38
7. Partial Submittals 39
a. City reserves the right to not review submittals deemed partial, at the City’s 40
discretion. 41
b. Submittals deemed by the City to be not complete will be returned to the 42
Contractor, and will be considered "Not Approved" until resubmitted. 43
c. The City may at its option provide a list or mark the submittal directing the 44
Contractor to the areas that are incomplete. 45
8. If the Contractor considers any correction indicated on the shop drawings to 46
constitute a change to the Contract Documents, then written notice must be 47
provided thereof to the Developer at least 7 Calendar Days prior to release for 48
manufacture. 49
100825
01 33 00 - 7
DAP SUBMITTALS
Page 7 of 8
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
9. When the shop drawings have been completed to the satisfaction of the City, the 1
Contractor may carry out the construction in accordance therewith and no further 2
changes therein except upon written instructions from the City. 3
10. Each submittal, appropriately coded, will be returned within 30 Calendar Days 4
following receipt of submittal by the City. 5
L. Mock ups 6
1. Mock Up units as specified in individual Sections, include, but are not necessarily 7
limited to, complete units of the standard of acceptance for that type of Work to be 8
used on the Project. Remove at the completion of the Work or when directed. 9
M. Qualifications 10
1. If specifically required in other Sections of these Specifications, submit a P.E. 11
Certification for each item required. 12
N. Request for Information (RFI) 13
1. Contractor Request for additional information 14
a. Clarification or interpretation of the contract documents 15
b. When the Contractor believes there is a conflict between Contract Documents 16
c. When the Contractor believes there is a conflict between the Drawings and 17
Specifications 18
1) Identify the conflict and request clarification 19
2. Sufficient information shall be attached to permit a written response without further 20
information. 21
22
23
24
25
1.5 SUBMITTALS [NOT USED] 26
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 27
1.7 CLOSEOUT SUBMITTALS [NOT USED] 28
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 29
1.9 QUALITY ASSURANCE [NOT USED] 30
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 31
1.11 FIELD [SITE] CONDITIONS [NOT USED] 32
1.12 WARRANTY [NOT USED] 33
100825
01 33 00 - 8
DAP SUBMITTALS
Page 8 of 8
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
PART 2 - PRODUCTS [NOT USED] 1
PART 3 - EXECUTION [NOT USED] 2
END OF SECTION 3
4
Revision Log
DATE NAME SUMMARY OF CHANGE
12/20/2012 D. Johnson 1.4.K.8. Working Days modified to Calendar Days
5
100825
01 45 23 - 1
DAP TESTING AND INSPECTION SERVICES
Page 1 of 2
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised August 30, 2013
SECTION 01 45 23
TESTING AND INSPECTION SERVICES
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Testing and inspection services procedures and coordination
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various Items bid.
No separate payment will be allowed for this Item.
a. Contractor is responsible for performing, coordinating, and payment of all
Quality Control testing.
b. City is responsible for performing and payment for first set of Quality
Assurance testing.
1) If the first Quality Assurance test performed by the City fails, the
Contractor is responsible for payment of subsequent Quality Assurance
testing until a passing test occurs.
a) Final acceptance will not be issued by City until all required payments
for testing by Contractor have been paid in full.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. Testing
1. Complete testing in accordance with the Contract Documents.
2. Coordination
a. When testing is required to be performed by the City, notify City, sufficiently
in advance, when testing is needed.
b. When testing is required to be completed by the Contractor, notify City,
sufficiently in advance, that testing will be performed.
3. Distribution of Testing Reports
a. Electronic Distribution
1) Confirm development of Project directory for electronic submittals to be
uploaded to City’s Buzzsaw site, or another form of distribution approved
by the City.
01 45 23 - 2
DAP TESTING AND INSPECTION SERVICES
Page 2 of 2
CITY OF FORT WORTH [Insert Project Name]
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS [Insert Project Number]
Revised August 30, 2013
2) Upload test reports to designated project directory and notify appropriate
City representatives via email of submittal posting.
3) Hard Copies
a) 1 copy for all submittals submitted to the Project Representative
b. Hard Copy Distribution (if required in lieu of electronic distribution)
1) Tests performed by City
a) Distribute 1 hard copy to the Contractor
2) Tests performed by the Contractor
a) Distribute 3 hard copies to City’s Project Representative
4. Provide City’s Project Representative with trip tickets for each delivered load of
Concrete or Lime material including the following information:
a. Name of pit
b. Date of delivery
c. Material delivered
B. Inspection
1. Inspection or lack of inspection does not relieve the Contractor from obligation to
perform work in accordance with the Contract Documents.
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
01 45 23 - 1
DAP TESTING AND INSPECTION SERVICES
Page 1 of 2
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
SECTION 01 45 23 1
TESTING AND INSPECTION SERVICES 2
PART 1 - GENERAL 3
1.1 SUMMARY 4
A. Section Includes: 5
1. Testing and inspection services procedures and coordination 6
B. Deviations from this City of Fort Worth Standard Specification 7
1. None. 8
C. Related Specification Sections include, but are not necessarily limited to: 9
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 10
2. Division 1 – General Requirements 11
1.2 PRICE AND PAYMENT PROCEDURES 12
A. Measurement and Payment 13
1. Work associated with this Item is considered subsidiary to the various Items bid. 14
No separate payment will be allowed for this Item. 15
a. Contractor is responsible for performing, coordinating, and payment of all 16
Quality Control testing. 17
b. City is responsible for performing and payment for first set of Quality 18
Assurance testing. 19
1) If the first Quality Assurance test performed by the City fails, the 20
Contractor is responsible for payment of subsequent Quality Assurance 21
testing until a passing test occurs. 22
a) Final acceptance will not be issued by City until all required payments 23
for testing by Contractor have been paid in full. 24
1.3 REFERENCES [NOT USED] 25
1.4 ADMINISTRATIVE REQUIREMENTS 26
A. Testing 27
1. Complete testing in accordance with the Contract Documents. 28
2. Coordination 29
a. When testing is required to be performed by the City, notify City, sufficiently 30
in advance, when testing is needed. 31
b. When testing is required to be completed by the Contractor, notify City, 32
sufficiently in advance, that testing will be performed. 33
3. Distribution of Testing Reports 34
a. Electronic Distribution 35
1) Confirm development of Project directory for electronic submittals to be 36
uploaded to City’s Buzzsaw site, or another form of distribution approved 37
by the City. 38
100825
01 45 23 - 2
DAP TESTING AND INSPECTION SERVICES
Page 2 of 2
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
2) Upload test reports to designated project directory and notify appropriate 1
City representatives via email of submittal posting. 2
3) Hard Copies 3
a) 1 copy for all submittals submitted to the Project Representative 4
b. Hard Copy Distribution (if required in lieu of electronic distribution) 5
1) Tests performed by City 6
a) Distribute 1 hard copy to the Contractor 7
2) Tests performed by the Contractor 8
a) Distribute 3 hard copies to City’s Project Representative 9
4. Provide City’s Project Representative with trip tickets for each delivered load of 10
Concrete or Lime material including the following information: 11
a. Name of pit 12
b. Date of delivery 13
c. Material delivered 14
B. Inspection 15
1. Inspection or lack of inspection does not relieve the Contractor from obligation to 16
perform work in accordance with the Contract Documents. 17
1.5 SUBMITTALS [NOT USED] 18
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 19
1.7 CLOSEOUT SUBMITTALS [NOT USED] 20
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 21
1.9 QUALITY ASSURANCE [NOT USED] 22
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 23
1.11 FIELD [SITE] CONDITIONS [NOT USED] 24
1.12 WARRANTY [NOT USED] 25
PART 2 - PRODUCTS [NOT USED] 26
PART 3 - EXECUTION [NOT USED] 27
END OF SECTION 28
29
Revision Log
DATE NAME SUMMARY OF CHANGE
30
100825
01 50 00 - 1
DAP TEMPORARY FACILITIES AND CONTROLS
Page 1 of 4
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
SECTION 01 50 00 1
TEMPORARY FACILITIES AND CONTROLS 2
PART 1 - GENERAL 3
1.1 SUMMARY 4
A. Section Includes: 5
1. Provide temporary facilities and controls needed for the Work including, but not 6
necessarily limited to: 7
a. Temporary utilities 8
b. Sanitary facilities 9
c. Storage Sheds and Buildings 10
d. Dust control 11
e. Temporary fencing of the construction site 12
B. Deviations from this City of Fort Worth Standard Specification 13
1. None. 14
C. Related Specification Sections include, but are not necessarily limited to: 15
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 16
2. Division 1 – General Requirements 17
1.2 PRICE AND PAYMENT PROCEDURES 18
A. Measurement and Payment 19
1. Work associated with this Item is considered subsidiary to the various Items bid. 20
No separate payment will be allowed for this Item. 21
1.3 REFERENCES [NOT USED] 22
1.4 ADMINISTRATIVE REQUIREMENTS 23
A. Temporary Utilities 24
1. Obtaining Temporary Service 25
a. Make arrangements with utility service companies for temporary services. 26
b. Abide by rules and regulations of utility service companies or authorities 27
having jurisdiction. 28
c. Be responsible for utility service costs until Work is approved for Final 29
Acceptance. 30
1) Included are fuel, power, light, heat and other utility services necessary for 31
execution, completion, testing and initial operation of Work. 32
2. Water 33
a. Contractor to provide water required for and in connection with Work to be 34
performed and for specified tests of piping, equipment, devices or other use as 35
required for the completion of the Work. 36
b. Provide and maintain adequate supply of potable water for domestic 37
consumption by Contractor personnel and City’s Project Representatives. 38
c. Coordination 39
100825
01 50 00 - 2
DAP TEMPORARY FACILITIES AND CONTROLS
Page 2 of 4
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
1) Contact City 1 week before water for construction is desired 1
d. Contractor Payment for Construction Water 2
1) Obtain construction water meter from City for payment as billed by City’s 3
established rates. 4
3. Electricity and Lighting 5
a. Provide and pay for electric powered service as required for Work, including 6
testing of Work. 7
1) Provide power for lighting, operation of equipment, or other use. 8
b. Electric power service includes temporary power service or generator to 9
maintain operations during scheduled shutdown. 10
4. Telephone 11
a. Provide emergency telephone service at Site for use by Contractor personnel 12
and others performing work or furnishing services at Site. 13
5. Temporary Heat and Ventilation 14
a. Provide temporary heat as necessary for protection or completion of Work. 15
b. Provide temporary heat and ventilation to assure safe working conditions. 16
B. Sanitary Facilities 17
1. Provide and maintain sanitary facilities for persons on Site. 18
a. Comply with regulations of State and local departments of health. 19
2. Enforce use of sanitary facilities by construction personnel at job site. 20
a. Enclose and anchor sanitary facilities. 21
b. No discharge will be allowed from these facilities. 22
c. Collect and store sewage and waste so as not to cause nuisance or health 23
problem. 24
d. Haul sewage and waste off-site at no less than weekly intervals and properly 25
dispose in accordance with applicable regulation. 26
3. Locate facilities near Work Site and keep clean and maintained throughout Project. 27
4. Remove facilities at completion of Project 28
C. Storage Sheds and Buildings 29
1. Provide adequately ventilated, watertight, weatherproof storage facilities with floor 30
above ground level for materials and equipment susceptible to weather damage. 31
2. Storage of materials not susceptible to weather damage may be on blocks off 32
ground. 33
3. Store materials in a neat and orderly manner. 34
a. Place materials and equipment to permit easy access for identification, 35
inspection and inventory. 36
4. Equip building with lockable doors and lighting, and provide electrical service for 37
equipment space heaters and heating or ventilation as necessary to provide storage 38
environments acceptable to specified manufacturers. 39
5. Fill and grade site for temporary structures to provide drainage away from 40
temporary and existing buildings. 41
6. Remove building from site prior to Final Acceptance. 42
D. Temporary Fencing 43
1. Provide and maintain for the duration or construction when required in contract 44
documents 45
100825
01 50 00 - 3
DAP TEMPORARY FACILITIES AND CONTROLS
Page 3 of 4
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
E. Dust Control 1
1. Contractor is responsible for maintaining dust control through the duration of the 2
project. 3
a. Contractor remains on-call at all times 4
b. Must respond in a timely manner 5
F. Temporary Protection of Construction 6
1. Contractor or subcontractors are responsible for protecting Work from damage due 7
to weather. 8
1.5 SUBMITTALS [NOT USED] 9
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 10
1.7 CLOSEOUT SUBMITTALS [NOT USED] 11
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 12
1.9 QUALITY ASSURANCE [NOT USED] 13
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 14
1.11 FIELD [SITE] CONDITIONS [NOT USED] 15
1.12 WARRANTY [NOT USED] 16
PART 2 - PRODUCTS [NOT USED] 17
PART 3 - EXECUTION [NOT USED] 18
3.1 INSTALLERS [NOT USED] 19
3.2 EXAMINATION [NOT USED] 20
3.3 PREPARATION [NOT USED] 21
3.4 INSTALLATION 22
A. Temporary Facilities 23
1. Maintain all temporary facilities for duration of construction activities as needed. 24
100825
01 50 00 - 4
DAP TEMPORARY FACILITIES AND CONTROLS
Page 4 of 4
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
3.5 [REPAIR] / [RESTORATION] 1
3.6 RE-INSTALLATION 2
3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED] 3
3.8 SYSTEM STARTUP [NOT USED] 4
3.9 ADJUSTING [NOT USED] 5
3.10 CLEANING [NOT USED] 6
3.11 CLOSEOUT ACTIVITIES 7
A. Temporary Facilities 8
1. Remove all temporary facilities and restore area after completion of the Work, to a 9
condition equal to or better than prior to start of Work. 10
3.12 PROTECTION [NOT USED] 11
3.13 MAINTENANCE [NOT USED] 12
3.14 ATTACHMENTS [NOT USED] 13
END OF SECTION 14
15
Revision Log
DATE NAME SUMMARY OF CHANGE
16
100825
01 55 26 - 1
DAP STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL
Page 1 of 3
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
SECTION 01 55 26 1
STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL 2
PART 1 - GENERAL 3
1.1 SUMMARY 4
A. Section Includes: 5
1. Administrative procedures for: 6
a. Street Use Permit 7
b. Modification of approved traffic control 8
c. Removal of Street Signs 9
B. Deviations from this City of Fort Worth Standard Specification 10
1. None. 11
C. Related Specification Sections include, but are not necessarily limited to: 12
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 13
2. Division 1 – General Requirements 14
3. Section 34 71 13 – Traffic Control 15
1.2 PRICE AND PAYMENT PROCEDURES 16
A. Measurement and Payment 17
1. Work associated with this Item is considered subsidiary to the various Items bid. 18
No separate payment will be allowed for this Item. 19
1.3 REFERENCES 20
A. Reference Standards 21
1. Reference standards cited in this specification refer to the current reference standard 22
published at the time of the latest revision date logged at the end of this 23
specification, unless a date is specifically cited. 24
2. Texas Manual on Uniform Traffic Control Devices (TMUTCD). 25
1.4 ADMINISTRATIVE REQUIREMENTS 26
A. Traffic Control 27
1. General 28
a. When traffic control plans are included in the Drawings, provide Traffic 29
Control in accordance with Drawings and Section 34 71 13. 30
b. When traffic control plans are not included in the Drawings, prepare traffic 31
control plans in accordance with Section 34 71 13 and submit to City for 32
review. 33
1) Allow minimum 10 working days for review of proposed Traffic Control. 34
B. Street Use Permit 35
1. Prior to installation of Traffic Control, a City Street Use Permit is required. 36
a. To obtain Street Use Permit, submit Traffic Control Plans to City 37
Transportation and Public Works Department. 38
100825
01 55 26 - 2
DAP STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL
Page 2 of 3
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
1) Allow a minimum of 5 working days for permit review. 1
2) Contractor’s responsibility to coordinate review of Traffic Control plans for 2
Street Use Permit, such that construction is not delayed. 3
C. Modification to Approved Traffic Control 4
1. Prior to installation traffic control: 5
a. Submit revised traffic control plans to City Department Transportation and 6
Public Works Department. 7
1) Revise Traffic Control plans in accordance with Section 34 71 13. 8
2) Allow minimum 5 working days for review of revised Traffic Control. 9
3) It is the Contractor’s responsibility to coordinate review of Traffic Control 10
plans for Street Use Permit, such that construction is not delayed. 11
D. Removal of Street Sign 12
1. If it is determined that a street sign must be removed for construction, then contact 13
City Transportation and Public Works Department, Signs and Markings Division to 14
remove the sign. 15
E. Temporary Signage 16
1. In the case of regulatory signs, replace permanent sign with temporary sign meeting 17
requirements of the latest edition of the Texas Manual on Uniform Traffic Control 18
Devices (MUTCD). 19
2. Install temporary sign before the removal of permanent sign. 20
3. When construction is complete, to the extent that the permanent sign can be 21
reinstalled, contact the City Transportation and Public Works Department, Signs 22
and Markings Division, to reinstall the permanent sign. 23
F. Traffic Control Standards 24
1. Traffic Control Standards can be found on the City’s Buzzsaw website. 25
1.5 SUBMITTALS [NOT USED] 26
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 27
1.7 CLOSEOUT SUBMITTALS [NOT USED] 28
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 29
1.9 QUALITY ASSURANCE [NOT USED] 30
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 31
1.11 FIELD [SITE] CONDITIONS [NOT USED] 32
1.12 WARRANTY [NOT USED] 33
PART 2 - PRODUCTS [NOT USED] 34
PART 3 - EXECUTION [NOT USED] 35
END OF SECTION 36
100825
01 55 26 - 3
DAP STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL
Page 3 of 3
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
1
Revision Log
DATE NAME SUMMARY OF CHANGE
2
100825
01 57 13 - 1
DAP STORM WATER POLLUTION PREVENTION
Page 1 of 3
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
SECTION 01 57 13 1
STORM WATER POLLUTION PREVENTION 2
PART 1 - GENERAL 3
1.1 SUMMARY 4
A. Section Includes: 5
1. Procedures for Storm Water Pollution Prevention Plans 6
B. Deviations from this City of Fort Worth Standard Specification 7
1. None. 8
C. Related Specification Sections include, but are not necessarily limited to: 9
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the 10
Contract 11
2. Division 1 – General Requirements 12
3. Section 31 25 00 – Erosion and Sediment Control 13
1.2 PRICE AND PAYMENT PROCEDURES 14
A. Measurement and Payment 15
1. Construction Activities resulting in less than 1 acre of disturbance 16
a. Work associated with this Item is considered subsidiary to the various Items 17
bid. No separate payment will be allowed for this Item. 18
2. Construction Activities resulting in greater than 1 acre of disturbance 19
a. Measurement and Payment shall be in accordance with Section 31 25 00. 20
1.3 REFERENCES 21
A. Abbreviations and Acronyms 22
1. Notice of Intent: NOI 23
2. Notice of Termination: NOT 24
3. Storm Water Pollution Prevention Plan: SWPPP 25
4. Texas Commission on Environmental Quality: TCEQ 26
5. Notice of Change: NOC 27
A. Reference Standards 28
1. Reference standards cited in this Specification refer to the current reference 29
standard published at the time of the latest revision date logged at the end of this 30
Specification, unless a date is specifically cited. 31
2. Integrated Storm Management (iSWM) Technical Manual for Construction 32
Controls 33
1.4 ADMINISTRATIVE REQUIREMENTS 34
A. General 35
1. Contractor is responsible for resolution and payment of any fines issued associated 36
with compliance to Stormwater Pollution Prevention Plan. 37
100825
01 57 13 - 2
DAP STORM WATER POLLUTION PREVENTION
Page 2 of 3
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
B. Construction Activities resulting in: 1
1. Less than 1 acre of disturbance 2
a. Provide erosion and sediment control in accordance with Section 31 25 00 and 3
Drawings. 4
2. 1 to less than 5 acres of disturbance 5
a. Texas Pollutant Discharge Elimination System (TPDES) General Construction 6
Permit is required 7
b. Complete SWPPP in accordance with TCEQ requirements 8
1) TCEQ Small Construction Site Notice Required under general permit 9
TXR150000 10
a) Sign and post at job site 11
b) Prior to Preconstruction Meeting, send 1 copy to City Department of 12
Transportation and Public Works, Environmental Division, (817) 392-13
6088. 14
2) Provide erosion and sediment control in accordance with: 15
a) Section 31 25 00 16
b) The Drawings 17
c) TXR150000 General Permit 18
d) SWPPP 19
e) TCEQ requirements 20
3. 5 acres or more of Disturbance 21
a. Texas Pollutant Discharge Elimination System (TPDES) General Construction 22
Permit is required 23
b. Complete SWPPP in accordance with TCEQ requirements 24
1) Prepare a TCEQ NOI form and submit to TCEQ along with required fee 25
a) Sign and post at job site 26
b) Send copy to City Department of Transportation and Public Works, 27
Environmental Division, (817) 392-6088. 28
2) TCEQ Notice of Change required if making changes or updates to NOI 29
3) Provide erosion and sediment control in accordance with: 30
a) Section 31 25 00 31
b) The Drawings 32
c) TXR150000 General Permit 33
d) SWPPP 34
e) TCEQ requirements 35
4) Once the project has been completed and all the closeout requirements of 36
TCEQ have been met a TCEQ Notice of Termination can be submitted. 37
a) Send copy to City Department of Transportation and Public Works, 38
Environmental Division, (817) 392-6088. 39
1.5 SUBMITTALS 40
A. SWPPP 41
1. Submit in accordance with Section 01 33 00, except as stated herein. 42
a. Prior to the Preconstruction Meeting, submit a draft copy of SWPPP to the City 43
as follows: 44
1) 1 copy to the City Project Manager 45
a) City Project Manager will forward to the City Department of 46
Transportation and Public Works, Environmental Division for review 47
100825
01 57 13 - 3
DAP STORM WATER POLLUTION PREVENTION
Page 3 of 3
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
B. Modified SWPPP 1
1. If the SWPPP is revised during construction, resubmit modified SWPPP to the City 2
in accordance with Section 01 33 00. 3
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 4
1.7 CLOSEOUT SUBMITTALS [NOT USED] 5
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 6
1.9 QUALITY ASSURANCE [NOT USED] 7
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 8
1.11 FIELD [SITE] CONDITIONS [NOT USED] 9
1.12 WARRANTY [NOT USED] 10
PART 2 - PRODUCTS [NOT USED] 11
PART 3 - EXECUTION [NOT USED] 12
END OF SECTION 13
14
Revision Log
DATE NAME SUMMARY OF CHANGE
15
100825
01 58 13 - 1
DAP TEMPORARY PROJECT SIGNAGE
Page 1 of 4
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
Revised April 7, 2014
SECTION 01 58 13 1
TEMPORARY PROJECT SIGNAGE 2
PART 1 - GENERAL 3
1.1 SUMMARY 4
A. Section Includes: 5
1. Temporary Project Signage Requirements 6
B. Deviations from this City of Fort Worth Standard Specification 7
1. None. 8
C. Related Specification Sections include, but are not necessarily limited to: 9
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 10
2. Division 1 – General Requirements 11
1.2 PRICE AND PAYMENT PROCEDURES 12
A. Measurement and Payment 13
1. Work associated with this Item is considered subsidiary to the various Items bid. 14
No separate payment will be allowed for this Item. 15
1.3 REFERENCES [NOT USED] 16
1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 17
1.5 SUBMITTALS [NOT USED] 18
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 19
1.7 CLOSEOUT SUBMITTALS [NOT USED] 20
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 21
1.9 QUALITY ASSURANCE [NOT USED] 22
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 23
1.11 FIELD [SITE] CONDITIONS [NOT USED] 24
1.12 WARRANTY [NOT USED] 25
PART 2 - PRODUCTS 26
2.1 OWNER-FURNISHED [OR] OWNER-SUPPLIEDPRODUCTS [NOT USED] 27
2.2 EQUIPMENT, PRODUCT TYPES, AND MATERIALS 28
A. Design Criteria 29
100825
01 58 13 - 2
DAP TEMPORARY PROJECT SIGNAGE
Page 2 of 4
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
Revised April 7, 2014
1. Provide free standing Project Designation Sign in accordance with City’s Standard 1
Details for project signs. 2
B. Materials 3
1. Sign 4
a. Constructed of ¾-inch fir plywood, grade A-C (exterior) or better 5
2.3 ACCESSORIES [NOT USED] 6
2.4 SOURCE QUALITY CONTROL [NOT USED] 7
PART 3 - EXECUTION 8
3.1 INSTALLERS [NOT USED] 9
3.2 EXAMINATION [NOT USED] 10
3.3 PREPARATION [NOT USED] 11
3.4 INSTALLATION 12
A. General 13
1. Provide vertical installation at extents of project. 14
2. Relocate sign as needed, upon request of the City. 15
B. Mounting options 16
a. Skids 17
b. Posts 18
c. Barricade 19
3.5 REPAIR / RESTORATION [NOT USED] 20
3.6 RE-INSTALLATION [NOT USED] 21
3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED] 22
3.8 SYSTEM STARTUP [NOT USED] 23
3.9 ADJUSTING [NOT USED] 24
3.10 CLEANING [NOT USED] 25
3.11 CLOSEOUT ACTIVITIES [NOT USED] 26
3.12 PROTECTION [NOT USED] 27
3.13 MAINTENANCE 28
A. General 29
1. Maintenance will include painting and repairs as needed or directed by the City. 30
100825
01 58 13 - 3
DAP TEMPORARY PROJECT SIGNAGE
Page 3 of 4
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
Revised April 7, 2014
3.14 ATTACHMENTS [NOT USED] 1
END OF SECTION 2
3
100825
01 58 13 - 4
DAP TEMPORARY PROJECT SIGNAGE
Page 4 of 4
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
Revised April 7, 2014
1
Revision Log
DATE NAME SUMMARY OF CHANGE
4/7/2014 M. Domenech Revised for DAP application
2
3
100825
01 60 00 - 1
DAP PRODUCT REQUIREMENTS
Page 1 of 2
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
SECTION 01 60 00 1
PRODUCT REQUIREMENTS 2
PART 1 - GENERAL 3
1.1 SUMMARY 4
A. Section Includes: 5
1. References for Product Requirements and City Standard Products List 6
B. Deviations from this City of Fort Worth Standard Specification 7
1. None. 8
C. Related Specification Sections include, but are not necessarily limited to: 9
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 10
2. Division 1 – General Requirements 11
1.2 PRICE AND PAYMENT PROCEDURES [NOT USED] 12
1.3 REFERENCES [NOT USED] 13
1.4 ADMINISTRATIVE REQUIREMENTS 14
A. A list of City approved products for use is located on Buzzsaw as follows: 15
1. Resources\02 - Construction Documents\Standard Products List 16
B. Only products specifically included on City’s Standard Product List in these Contract 17
Documents shall be allowed for use on the Project. 18
1. Any subsequently approved products will only be allowed for use upon specific 19
approval by the City. 20
C. Any specific product requirements in the Contract Documents supersede similar 21
products included on the City’s Standard Product List. 22
1. The City reserves the right to not allow products to be used for certain projects even 23
though the product is listed on the City’s Standard Product List. 24
D. Although a specific product is included on City’s Standard Product List, not all 25
products from that manufacturer are approved for use, including but not limited to, that 26
manufacturer’s standard product. 27
E. See Section 01 33 00 for submittal requirements of Product Data included on City’s 28
Standard Product List. 29
1.5 SUBMITTALS [NOT USED] 30
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 31
1.7 CLOSEOUT SUBMITTALS [NOT USED] 32
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 33
1.9 QUALITY ASSURANCE [NOT USED] 34
100825
01 60 00 - 2
DAP PRODUCT REQUIREMENTS
Page 2 of 2
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1
1.11 FIELD [SITE] CONDITIONS [NOT USED] 2
1.12 WARRANTY [NOT USED] 3
PART 2 - PRODUCTS [NOT USED] 4
PART 3 - EXECUTION [NOT USED] 5
END OF SECTION 6
7
Revision Log
DATE NAME SUMMARY OF CHANGE
10/12/12 D. Johnson Modified Location of City’s Standard Product List
4/7/2014 M.Domenech Revised for DAP application
8
100825
01 66 00 - 1
DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS
Page 1 of 4
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
SECTION 01 66 00 1
PRODUCT STORAGE AND HANDLING REQUIREMENTS 2
PART 1 - GENERAL 3
1.1 SUMMARY 4
A. Section Includes: 5
1. Scheduling of product delivery 6
2. Packaging of products for delivery 7
3. Protection of products against damage from: 8
a. Handling 9
b. Exposure to elements or harsh environments 10
B. Deviations from this City of Fort Worth Standard Specification 11
1. None. 12
C. Related Specification Sections include, but are not necessarily limited to: 13
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 14
2. Division 1 – General Requirements 15
1.2 PRICE AND PAYMENT PROCEDURES 16
A. Measurement and Payment 17
1. Work associated with this Item is considered subsidiary to the various Items bid. 18
No separate payment will be allowed for this Item. 19
1.3 REFERENCES [NOT USED] 20
1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 21
1.5 SUBMITTALS [NOT USED] 22
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 23
1.7 CLOSEOUT SUBMITTALS [NOT USED] 24
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 25
1.9 QUALITY ASSURANCE [NOT USED] 26
1.10 DELIVERY AND HANDLING 27
A. Delivery Requirements 28
1. Schedule delivery of products or equipment as required to allow timely installation 29
and to avoid prolonged storage. 30
2. Provide appropriate personnel and equipment to receive deliveries. 31
3. Delivery trucks will not be permitted to wait extended periods of time on the Site 32
for personnel or equipment to receive the delivery. 33
100825
01 66 00 - 2
DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS
Page 2 of 4
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
4. Deliver products or equipment in manufacturer's original unbroken cartons or other 1
containers designed and constructed to protect the contents from physical or 2
environmental damage. 3
5. Clearly and fully mark and identify as to manufacturer, item and installation 4
location. 5
6. Provide manufacturer's instructions for storage and handling. 6
B. Handling Requirements 7
1. Handle products or equipment in accordance with these Contract Documents and 8
manufacturer’s recommendations and instructions. 9
C. Storage Requirements 10
1. Store materials in accordance with manufacturer’s recommendations and 11
requirements of these Specifications. 12
2. Make necessary provisions for safe storage of materials and equipment. 13
a. Place loose soil materials and materials to be incorporated into Work to prevent 14
damage to any part of Work or existing facilities and to maintain free access at 15
all times to all parts of Work and to utility service company installations in 16
vicinity of Work. 17
3. Keep materials and equipment neatly and compactly stored in locations that will 18
cause minimum inconvenience to other contractors, public travel, adjoining owners, 19
tenants and occupants. 20
a. Arrange storage to provide easy access for inspection. 21
4. Restrict storage to areas available on construction site for storage of material and 22
equipment as shown on Drawings, or approved by City’s Project Representative. 23
5. Provide off-site storage and protection when on-site storage is not adequate. 24
a. Provide addresses of and access to off-site storage locations for inspection by 25
City’s Project Representative. 26
6. Do not use lawns, grass plots or other private property for storage purposes without 27
written permission of owner or other person in possession or control of premises. 28
7. Store in manufacturers’ unopened containers. 29
8. Neatly, safely and compactly stack materials delivered and stored along line of 30
Work to avoid inconvenience and damage to property owners and general public 31
and maintain at least 3 feet from fire hydrant. 32
9. Keep public and private driveways and street crossings open. 33
10. Repair or replace damaged lawns, sidewalks, streets or other improvements to 34
satisfaction of City’s Project Representative. 35
a. Total length which materials may be distributed along route of construction at 36
one time is 1,000 linear feet, unless otherwise approved in writing by City’s 37
Project Representative. 38
100825
01 66 00 - 3
DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS
Page 3 of 4
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
1.11 FIELD [SITE] CONDITIONS [NOT USED] 1
1.12 WARRANTY [NOT USED] 2
PART 2 - PRODUCTS [NOT USED] 3
PART 3 - EXECUTION 4
3.1 INSTALLERS [NOT USED] 5
3.2 EXAMINATION [NOT USED] 6
3.3 PREPARATION [NOT USED] 7
3.4 ERECTION [NOT USED] 8
3.5 REPAIR / RESTORATION [NOT USED] 9
3.6 RE-INSTALLATION [NOT USED] 10
3.7 FIELD [OR] SITE QUALITY CONTROL 11
A. Tests and Inspections 12
1. Inspect all products or equipment delivered to the site prior to unloading. 13
B. Non-Conforming Work 14
1. Reject all products or equipment that are damaged, used or in any other way 15
unsatisfactory for use on the project. 16
3.8 SYSTEM STARTUP [NOT USED] 17
3.9 ADJUSTING [NOT USED] 18
3.10 CLEANING [NOT USED] 19
3.11 CLOSEOUT ACTIVITIES [NOT USED] 20
3.12 PROTECTION 21
A. Protect all products or equipment in accordance with manufacturer's written directions. 22
B. Store products or equipment in location to avoid physical damage to items while in 23
storage. 24
C. Protect equipment from exposure to elements and keep thoroughly dry if required by 25
the manufacturer. 26
3.13 MAINTENANCE [NOT USED] 27
3.14 ATTACHMENTS [NOT USED] 28
END OF SECTION 29
30
100825
01 66 00 - 4
DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS
Page 4 of 4
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
Revision Log
DATE NAME SUMMARY OF CHANGE
4/7/2014 M.Domenech Revised for DAP application
1
100825
01 74 23 - 1
DAP CLEANING
Page 1 of 4
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
SECTION 01 74 23 1
CLEANING 2
PART 1 - GENERAL 3
1.1 SUMMARY 4
A. Section Includes: 5
1. Intermediate and final cleaning for Work not including special cleaning of closed 6
systems specified elsewhere 7
B. Deviations from this City of Fort Worth Standard Specification 8
1. None. 9
C. Related Specification Sections include, but are not necessarily limited to: 10
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 11
2. Division 1 – General Requirements 12
3. Section 32 92 13 – Hydro-Mulching, Seeding and Sodding 13
1.2 PRICE AND PAYMENT PROCEDURES 14
A. Measurement and Payment 15
1. Work associated with this Item is considered subsidiary to the various Items bid. 16
No separate payment will be allowed for this Item. 17
1.3 REFERENCES [NOT USED] 18
1.4 ADMINISTRATIVE REQUIREMENTS 19
A. Scheduling 20
1. Schedule cleaning operations so that dust and other contaminants disturbed by 21
cleaning process will not fall on newly painted surfaces. 22
2. Schedule final cleaning upon completion of Work and immediately prior to final 23
inspection. 24
1.5 SUBMITTALS [NOT USED] 25
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 26
1.7 CLOSEOUT SUBMITTALS [NOT USED] 27
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 28
1.9 QUALITY ASSURANCE [NOT USED] 29
1.10 STORAGE, AND HANDLING 30
A. Storage and Handling Requirements 31
1. Store cleaning products and cleaning wastes in containers specifically designed for 32
those materials. 33
100825
01 74 23 - 2
DAP CLEANING
Page 2 of 4
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
1.11 FIELD [SITE] CONDITIONS [NOT USED] 1
1.12 WARRANTY [NOT USED] 2
PART 2 - PRODUCTS 3
2.1 OWNER-FURNISHED [OR] OWNER-SUPPLIEDPRODUCTS [NOT USED] 4
2.2 MATERIALS 5
A. Cleaning Agents 6
1. Compatible with surface being cleaned 7
2. New and uncontaminated 8
3. For manufactured surfaces 9
a. Material recommended by manufacturer 10
2.3 ACCESSORIES [NOT USED] 11
2.4 SOURCE QUALITY CONTROL [NOT USED] 12
PART 3 - EXECUTION 13
3.1 INSTALLERS [NOT USED] 14
3.2 EXAMINATION [NOT USED] 15
3.3 PREPARATION [NOT USED] 16
3.4 APPLICATION [NOT USED] 17
3.5 REPAIR / RESTORATION [NOT USED] 18
3.6 RE-INSTALLATION [NOT USED] 19
3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED] 20
3.8 SYSTEM STARTUP [NOT USED] 21
3.9 ADJUSTING [NOT USED] 22
3.10 CLEANING 23
A. General 24
1. Prevent accumulation of wastes that create hazardous conditions. 25
2. Conduct cleaning and disposal operations to comply with laws and safety orders of 26
governing authorities. 27
3. Do not dispose of volatile wastes such as mineral spirits, oil or paint thinner in 28
storm or sanitary drains or sewers. 29
4. Dispose of degradable debris at an approved solid waste disposal site. 30
5. Dispose of nondegradable debris at an approved solid waste disposal site or in an 31
alternate manner approved by City and regulatory agencies. 32
100825
01 74 23 - 3
DAP CLEANING
Page 3 of 4
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
6. Handle materials in a controlled manner with as few handlings as possible. 1
7. Thoroughly clean, sweep, wash and polish all Work and equipment associated with 2
this project. 3
8. Remove all signs of temporary construction and activities incidental to construction 4
of required permanent Work. 5
9. If project is not cleaned to the satisfaction of the City, the City reserves the right to 6
have the cleaning completed at the expense of the Contractor. 7
10. Do not burn on-site. 8
B. Intermediate Cleaning during Construction 9
1. Keep Work areas clean so as not to hinder health, safety or convenience of 10
personnel in existing facility operations. 11
2. At maximum weekly intervals, dispose of waste materials, debris and rubbish. 12
3. Confine construction debris daily in strategically located container(s): 13
a. Cover to prevent blowing by wind 14
b. Store debris away from construction or operational activities 15
c. Haul from site at a minimum of once per week 16
4. Vacuum clean interior areas when ready to receive finish painting. 17
a. Continue vacuum cleaning on an as-needed basis, until Final Acceptance. 18
5. Prior to storm events, thoroughly clean site of all loose or unsecured items, which 19
may become airborne or transported by flowing water during the storm. 20
C. Exterior (Site or Right of Way) Final Cleaning 21
1. Remove trash and debris containers from site. 22
a. Re-seed areas disturbed by location of trash and debris containers in accordance 23
with Section 32 92 13. 24
2. Sweep roadway to remove all rocks, pieces of asphalt, concrete or any other object 25
that may hinder or disrupt the flow of traffic along the roadway. 26
3. Clean any interior areas including, but not limited to, vaults, manholes, structures, 27
junction boxes and inlets. 28
4. If no longer required for maintenance of erosion facilities, and upon approval by 29
City, remove erosion control from site. 30
5. Clean signs, lights, signals, etc. 31
3.11 CLOSEOUT ACTIVITIES [NOT USED] 32
3.12 PROTECTION [NOT USED] 33
3.13 MAINTENANCE [NOT USED] 34
3.14 ATTACHMENTS [NOT USED] 35
36
37
38
39
40
100825
01 74 23 - 4
DAP CLEANING
Page 4 of 4
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
END OF SECTION 1
2
Revision Log
DATE NAME SUMMARY OF CHANGE
4/7/2014 M.Domenech Revised for DAP application
3
100825
01 77 19 - 1
DAP CLOSEOUT REQUIREMENTS
Page 1 of 3
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
SECTION 01 77 19 1
CLOSEOUT REQUIREMENTS 2
PART 1 - GENERAL 3
1.1 SUMMARY 4
A. Section Includes: 5
1. The procedure for closing out a contract 6
B. Deviations from this City of Fort Worth Standard Specification 7
1. None. 8
C. Related Specification Sections include, but are not necessarily limited to: 9
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 10
2. Division 1 – General Requirements 11
1.2 PRICE AND PAYMENT PROCEDURES 12
A. Measurement and Payment 13
1. Work associated with this Item is considered subsidiary to the various Items bid. 14
No separate payment will be allowed for this Item. 15
1.3 REFERENCES [NOT USED] 16
1.4 ADMINISTRATIVE REQUIREMENTS 17
A. Guarantees, Bonds and Affidavits 18
1. No application for final payment will be accepted until all guarantees, bonds, 19
certificates, licenses and affidavits required for Work or equipment as specified are 20
satisfactorily filed with the City. 21
B. Release of Liens or Claims 22
1. No application for final payment will be accepted until satisfactory evidence of 23
release of liens has been submitted to the City. 24
1.5 SUBMITTALS 25
A. Submit all required documentation to City’s Project Representative. 26
100825
01 77 19 - 2
DAP CLOSEOUT REQUIREMENTS
Page 2 of 3
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
1.6 INFORMATIONAL SUBMITTALS [NOT USED] 1
1.7 CLOSEOUT SUBMITTALS [NOT USED] 2
PART 2 - PRODUCTS [NOT USED] 3
PART 3 - EXECUTION 4
3.1 INSTALLERS [NOT USED] 5
3.2 EXAMINATION [NOT USED] 6
3.3 PREPARATION [NOT USED] 7
3.4 CLOSEOUT PROCEDURE 8
A. Prior to requesting Final Inspection, submit: 9
1. Project Record Documents in accordance with Section 01 78 39 10
2. Operation and Maintenance Data, if required, in accordance with Section 01 78 23 11
B. Prior to requesting Final Inspection, perform final cleaning in accordance with Section 12
01 74 23. 13
C. Final Inspection 14
1. After final cleaning, provide notice to the City Project Representative that the Work 15
is completed. 16
a. The City will make an initial Final Inspection with the Contractor present. 17
b. Upon completion of this inspection, the City will notify the Contractor, in 18
writing within 10 business days, of any particulars in which this inspection 19
reveals that the Work is defective or incomplete. 20
2. Upon receiving written notice from the City, immediately undertake the Work 21
required to remedy deficiencies and complete the Work to the satisfaction of the 22
City. 23
3. Upon completion of Work associated with the items listed in the City's written 24
notice, inform the City, that the required Work has been completed. Upon receipt 25
of this notice, the City, in the presence of the Contractor, will make a subsequent 26
Final Inspection of the project. 27
4. Provide all special accessories required to place each item of equipment in full 28
operation. These special accessory items include, but are not limited to: 29
a. Specified spare parts 30
b. Adequate oil and grease as required for the first lubrication of the equipment 31
c. Initial fill up of all chemical tanks and fuel tanks 32
d. Light bulbs 33
e. Fuses 34
f. Vault keys 35
g. Handwheels 36
h. Other expendable items as required for initial start-up and operation of all 37
equipment 38
D. Notice of Project Completion 39
100825
01 77 19 - 3
DAP CLOSEOUT REQUIREMENTS
Page 3 of 3
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
1. Once the City Project Representative finds the Work subsequent to Final Inspection 1
to be satisfactory, the City will issue a Notice of Project Completion (Green Sheet). 2
E. Supporting Documentation 3
1. Coordinate with the City Project Representative to complete the following 4
additional forms: 5
a. Final Payment Request 6
b. Statement of Contract Time 7
c. Affidavit of Payment and Release of Liens 8
d. Consent of Surety to Final Payment 9
e. Pipe Report (if required) 10
f. Contractor’s Evaluation of City 11
g. Performance Evaluation of Contractor 12
F. Letter of Final Acceptance 13
1. Upon review and acceptance of Notice of Project Completion and Supporting 14
Documentation, in accordance with General Conditions, City will issue Letter of 15
Final Acceptance and release the Final Payment Request for payment. 16
3.5 REPAIR / RESTORATION [NOT USED] 17
3.6 RE-INSTALLATION [NOT USED] 18
3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED] 19
3.8 SYSTEM STARTUP [NOT USED] 20
3.9 ADJUSTING [NOT USED] 21
3.10 CLEANING [NOT USED] 22
3.11 CLOSEOUT ACTIVITIES [NOT USED] 23
3.12 PROTECTION [NOT USED] 24
3.13 MAINTENANCE [NOT USED] 25
3.14 ATTACHMENTS [NOT USED] 26
END OF SECTION 27
28
Revision Log
DATE NAME SUMMARY OF CHANGE
4/7/2014 M.Domenech Revised for DAP application
29
100825
01 78 23 - 1
DAP OPERATION AND MAINTENANCE DATA
Page 1 of 5
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
SECTION 01 78 23 1
OPERATION AND MAINTENANCE DATA 2
PART 1 - GENERAL 3
1.1 SUMMARY 4
A. Section Includes: 5
1. Product data and related information appropriate for City's maintenance and 6
operation of products furnished under Contract 7
2. Such products may include, but are not limited to: 8
a. Traffic Controllers 9
b. Irrigation Controllers (to be operated by the City) 10
c. Butterfly Valves 11
B. Deviations from this City of Fort Worth Standard Specification 12
1. None. 13
C. Related Specification Sections include, but are not necessarily limited to: 14
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 15
2. Division 1 – General Requirements 16
1.2 PRICE AND PAYMENT PROCEDURES 17
A. Measurement and Payment 18
1. Work associated with this Item is considered subsidiary to the various Items bid. 19
No separate payment will be allowed for this Item. 20
1.3 REFERENCES [NOT USED] 21
1.4 ADMINISTRATIVE REQUIREMENTS 22
A. Schedule 23
1. Submit manuals in final form to the City within 30 calendar days of product 24
shipment to the project site. 25
1.5 SUBMITTALS 26
A. Submittals shall be in accordance with Section 01 33 00. All submittals shall be 27
approved by the City prior to delivery. 28
1.6 INFORMATIONAL SUBMITTALS 29
A. Submittal Form 30
1. Prepare data in form of an instructional manual for use by City personnel. 31
2. Format 32
a. Size: 8 ½ inches x 11 inches 33
b. Paper 34
1) 40 pound minimum, white, for typed pages 35
2) Holes reinforced with plastic, cloth or metal 36
c. Text: Manufacturer’s printed data, or neatly typewritten 37
100825
01 78 23 - 2
DAP OPERATION AND MAINTENANCE DATA
Page 2 of 5
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
d. Drawings 1
1) Provide reinforced punched binder tab, bind in with text 2
2) Reduce larger drawings and fold to size of text pages. 3
e. Provide fly-leaf for each separate product, or each piece of operating 4
equipment. 5
1) Provide typed description of product, and major component parts of 6
equipment. 7
2) Provide indexed tabs. 8
f. Cover 9
1) Identify each volume with typed or printed title "OPERATING AND 10
MAINTENANCE INSTRUCTIONS". 11
2) List: 12
a) Title of Project 13
b) Identity of separate structure as applicable 14
c) Identity of general subject matter covered in the manual 15
3. Binders 16
a. Commercial quality 3-ring binders with durable and cleanable plastic covers 17
b. When multiple binders are used, correlate the data into related consistent 18
groupings. 19
4. If available, provide an electronic form of the O&M Manual. 20
B. Manual Content 21
1. Neatly typewritten table of contents for each volume, arranged in systematic order 22
a. Contractor, name of responsible principal, address and telephone number 23
b. A list of each product required to be included, indexed to content of the volume 24
c. List, with each product: 25
1) The name, address and telephone number of the subcontractor or installer 26
2) A list of each product required to be included, indexed to content of the 27
volume 28
3) Identify area of responsibility of each 29
4) Local source of supply for parts and replacement 30
d. Identify each product by product name and other identifying symbols as set 31
forth in Contract Documents. 32
2. Product Data 33
a. Include only those sheets which are pertinent to the specific product. 34
b. Annotate each sheet to: 35
1) Clearly identify specific product or part installed 36
2) Clearly identify data applicable to installation 37
3) Delete references to inapplicable information 38
3. Drawings 39
a. Supplement product data with drawings as necessary to clearly illustrate: 40
1) Relations of component parts of equipment and systems 41
2) Control and flow diagrams 42
b. Coordinate drawings with information in Project Record Documents to assure 43
correct illustration of completed installation. 44
c. Do not use Project Record Drawings as maintenance drawings. 45
4. Written text, as required to supplement product data for the particular installation: 46
a. Organize in consistent format under separate headings for different procedures. 47
b. Provide logical sequence of instructions of each procedure. 48
100825
01 78 23 - 3
DAP OPERATION AND MAINTENANCE DATA
Page 3 of 5
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
5. Copy of each warranty, bond and service contract issued 1
a. Provide information sheet for City personnel giving: 2
1) Proper procedures in event of failure 3
2) Instances which might affect validity of warranties or bonds 4
C. Manual for Materials and Finishes 5
1. Submit 5 copies of complete manual in final form. 6
2. Content, for architectural products, applied materials and finishes: 7
a. Manufacturer's data, giving full information on products 8
1) Catalog number, size, composition 9
2) Color and texture designations 10
3) Information required for reordering special manufactured products 11
b. Instructions for care and maintenance 12
1) Manufacturer's recommendation for types of cleaning agents and methods 13
2) Cautions against cleaning agents and methods which are detrimental to 14
product 15
3) Recommended schedule for cleaning and maintenance 16
3. Content, for moisture protection and weather exposure products: 17
a. Manufacturer's data, giving full information on products 18
1) Applicable standards 19
2) Chemical composition 20
3) Details of installation 21
b. Instructions for inspection, maintenance and repair 22
D. Manual for Equipment and Systems 23
1. Submit 5 copies of complete manual in final form. 24
2. Content, for each unit of equipment and system, as appropriate: 25
a. Description of unit and component parts 26
1) Function, normal operating characteristics and limiting conditions 27
2) Performance curves, engineering data and tests 28
3) Complete nomenclature and commercial number of replaceable parts 29
b. Operating procedures 30
1) Start-up, break-in, routine and normal operating instructions 31
2) Regulation, control, stopping, shut-down and emergency instructions 32
3) Summer and winter operating instructions 33
4) Special operating instructions 34
c. Maintenance procedures 35
1) Routine operations 36
2) Guide to "trouble shooting" 37
3) Disassembly, repair and reassembly 38
4) Alignment, adjusting and checking 39
d. Servicing and lubrication schedule 40
1) List of lubricants required 41
e. Manufacturer's printed operating and maintenance instructions 42
f. Description of sequence of operation by control manufacturer 43
1) Predicted life of parts subject to wear 44
2) Items recommended to be stocked as spare parts 45
g. As installed control diagrams by controls manufacturer 46
h. Each contractor's coordination drawings 47
1) As installed color coded piping diagrams 48
100825
01 78 23 - 4
DAP OPERATION AND MAINTENANCE DATA
Page 4 of 5
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
i. Charts of valve tag numbers, with location and function of each valve 1
j. List of original manufacturer's spare parts, manufacturer's current prices, and 2
recommended quantities to be maintained in storage 3
k. Other data as required under pertinent Sections of Specifications 4
3. Content, for each electric and electronic system, as appropriate: 5
a. Description of system and component parts 6
1) Function, normal operating characteristics, and limiting conditions 7
2) Performance curves, engineering data and tests 8
3) Complete nomenclature and commercial number of replaceable parts 9
b. Circuit directories of panelboards 10
1) Electrical service 11
2) Controls 12
3) Communications 13
c. As installed color coded wiring diagrams 14
d. Operating procedures 15
1) Routine and normal operating instructions 16
2) Sequences required 17
3) Special operating instructions 18
e. Maintenance procedures 19
1) Routine operations 20
2) Guide to "trouble shooting" 21
3) Disassembly, repair and reassembly 22
4) Adjustment and checking 23
f. Manufacturer's printed operating and maintenance instructions 24
g. List of original manufacturer's spare parts, manufacturer's current prices, and 25
recommended quantities to be maintained in storage 26
h. Other data as required under pertinent Sections of Specifications 27
4. Prepare and include additional data when the need for such data becomes apparent 28
during instruction of City's personnel. 29
1.7 CLOSEOUT SUBMITTALS [NOT USED] 30
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 31
1.9 QUALITY ASSURANCE 32
A. Provide operation and maintenance data by personnel with the following criteria: 33
1. Trained and experienced in maintenance and operation of described products 34
2. Skilled as technical writer to the extent required to communicate essential data 35
3. Skilled as draftsman competent to prepare required drawings 36
100825
01 78 23 - 5
DAP OPERATION AND MAINTENANCE DATA
Page 5 of 5
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1
1.11 FIELD [SITE] CONDITIONS [NOT USED] 2
1.12 WARRANTY [NOT USED] 3
PART 2 - PRODUCTS [NOT USED] 4
PART 3 - EXECUTION [NOT USED] 5
END OF SECTION 6
7
Revision Log
DATE NAME SUMMARY OF CHANGE
8/31/2012 D. Johnson 1.5.A.1 – title of section removed
4/7/2014 M.Domenech Revised for DAP Application
8
100825
01 78 39 - 1
DAP PROJECT RECORD DOCUMENTS
Page 1 of 5
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
SECTION 01 78 39 1
PROJECT RECORD DOCUMENTS 2
PART 1 - GENERAL 3
1.1 SUMMARY 4
A. Section Includes: 5
1. Work associated with the documenting the project and recording changes to project 6
documents, including: 7
a. Record Drawings 8
b. Water Meter Service Reports 9
c. Sanitary Sewer Service Reports 10
d. Large Water Meter Reports 11
B. Deviations from this City of Fort Worth Standard Specification 12
1. None. 13
C. Related Specification Sections include, but are not necessarily limited to: 14
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 15
2. Division 1 – General Requirements 16
1.2 PRICE AND PAYMENT PROCEDURES 17
A. Measurement and Payment 18
1. Work associated with this Item is considered subsidiary to the various Items bid. 19
No separate payment will be allowed for this Item. 20
1.3 REFERENCES [NOT USED] 21
1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 22
1.5 SUBMITTALS 23
A. Prior to submitting a request for Final Inspection, deliver Project Record Documents to 24
City’s Project Representative. 25
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 26
1.7 CLOSEOUT SUBMITTALS [NOT USED] 27
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 28
1.9 QUALITY ASSURANCE 29
A. Accuracy of Records 30
1. Thoroughly coordinate changes within the Record Documents, making adequate 31
and proper entries on each page of Specifications and each sheet of Drawings and 32
other Documents where such entry is required to show the change properly. 33
100825
01 78 39 - 2
DAP PROJECT RECORD DOCUMENTS
Page 2 of 5
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
2. Accuracy of records shall be such that future search for items shown in the Contract 1
Documents may rely reasonably on information obtained from the approved Project 2
Record Documents. 3
3. To facilitate accuracy of records, make entries within 24 hours after receipt of 4
information that the change has occurred. 5
4. Provide factual information regarding all aspects of the Work, both concealed and 6
visible, to enable future modification of the Work to proceed without lengthy and 7
expensive site measurement, investigation and examination. 8
1.10 STORAGE AND HANDLING 9
A. Storage and Handling Requirements 10
1. Maintain the job set of Record Documents completely protected from deterioration 11
and from loss and damage until completion of the Work and transfer of all recorded 12
data to the final Project Record Documents. 13
2. In the event of loss of recorded data, use means necessary to again secure the data 14
to the City's approval. 15
a. In such case, provide replacements to the standards originally required by the 16
Contract Documents. 17
1.11 FIELD [SITE] CONDITIONS [NOT USED] 18
1.12 WARRANTY [NOT USED] 19
PART 2 - PRODUCTS 20
2.1 OWNER-FURNISHED [OR] OWNER-SUPPLIED PRODUCTS [NOT USED] 21
2.2 RECORD DOCUMENTS 22
A. Job set 23
1. Promptly following receipt of the Notice to Proceed, secure from the City, at no 24
charge to the Contractor, 1 complete set of all Documents comprising the Contract. 25
B. Final Record Documents 26
1. At a time nearing the completion of the Work and prior to Final Inspection, provide 27
the City 1 complete set of all Final Record Drawings in the Contract. 28
100825
01 78 39 - 3
DAP PROJECT RECORD DOCUMENTS
Page 3 of 5
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
2.3 ACCESSORIES [NOT USED] 1
2.4 SOURCE QUALITY CONTROL [NOT USED] 2
PART 3 - EXECUTION 3
3.1 INSTALLERS [NOT USED] 4
3.2 EXAMINATION [NOT USED] 5
3.3 PREPARATION [NOT USED] 6
3.4 MAINTENANCE DOCUMENTS 7
A. Maintenance of Job Set 8
1. Immediately upon receipt of the job set, identify each of the Documents with the 9
title, "RECORD DOCUMENTS - JOB SET". 10
2. Preservation 11
a. Considering the Contract completion time, the probable number of occasions 12
upon which the job set must be taken out for new entries and for examination, 13
and the conditions under which these activities will be performed, devise a 14
suitable method for protecting the job set. 15
b. Do not use the job set for any purpose except entry of new data and for review 16
by the City, until start of transfer of data to final Project Record Documents. 17
c. Maintain the job set at the site of work. 18
3. Coordination with Construction Survey 19
a. At a minimum clearly mark any deviations from Contract Documents 20
associated with installation of the infrastructure. 21
4. Making entries on Drawings 22
a. Record any deviations from Contract Documents. 23
b. Use an erasable colored pencil (not ink or indelible pencil), clearly describe the 24
change by graphic line and note as required. 25
c. Date all entries. 26
d. Call attention to the entry by a "cloud" drawn around the area or areas affected. 27
e. In the event of overlapping changes, use different colors for the overlapping 28
changes. 29
5. Conversion of schematic layouts 30
a. In some cases on the Drawings, arrangements of conduits, circuits, piping, 31
ducts, and similar items, are shown schematically and are not intended to 32
portray precise physical layout. 33
1) Final physical arrangement is determined by the Contractor, subject to the 34
City's approval. 35
2) However, design of future modifications of the facility may require 36
accurate information as to the final physical layout of items which are 37
shown only schematically on the Drawings. 38
b. Show on the job set of Record Drawings, by dimension accurate to within 1 39
inch, the centerline of each run of items. 40
1) Final physical arrangement is determined by the Contractor, subject to the 41
City's approval. 42
100825
01 78 39 - 4
DAP PROJECT RECORD DOCUMENTS
Page 4 of 5
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
2) Show, by symbol or note, the vertical location of the Item ("under slab", "in 1
ceiling plenum", "exposed", and the like). 2
3) Make all identification sufficiently descriptive that it may be related 3
reliably to the Specifications. 4
c. The City may waive the requirements for conversion of schematic layouts 5
where, in the City's judgment, conversion serves no useful purpose. However, 6
do not rely upon waivers being issued except as specifically issued in writing 7
by the City. 8
B. Final Project Record Documents 9
1. Transfer of data to Drawings 10
a. Carefully transfer change data shown on the job set of Record Drawings to the 11
corresponding final documents, coordinating the changes as required. 12
b. Clearly indicate at each affected detail and other Drawing a full description of 13
changes made during construction, and the actual location of items. 14
c. Call attention to each entry by drawing a "cloud" around the area or areas 15
affected. 16
d. Make changes neatly, consistently and with the proper media to assure 17
longevity and clear reproduction. 18
2. Transfer of data to other Documents 19
a. If the Documents, other than Drawings, have been kept clean during progress of 20
the Work, and if entries thereon have been orderly to the approval of the City, 21
the job set of those Documents, other than Drawings, will be accepted as final 22
Record Documents. 23
b. If any such Document is not so approved by the City, secure a new copy of that 24
Document from the City at the City's usual charge for reproduction and 25
handling, and carefully transfer the change data to the new copy to the approval 26
of the City. 27
3.5 REPAIR / RESTORATION [NOT USED] 28
3.6 RE-INSTALLATION [NOT USED] 29
3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED] 30
3.8 SYSTEM STARTUP [NOT USED] 31
3.9 ADJUSTING [NOT USED] 32
3.10 CLEANING [NOT USED] 33
3.11 CLOSEOUT ACTIVITIES [NOT USED] 34
3.12 PROTECTION [NOT USED] 35
3.13 MAINTENANCE [NOT USED] 36
3.14 ATTACHMENTS [NOT USED] 37
END OF SECTION 38
39
100825
01 78 39 - 5
DAP PROJECT RECORD DOCUMENTS
Page 5 of 5
CITY OF FORT WORTH Creekside Estates Phase 3
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No.
B2010078.030
Revision Log
DATE NAME SUMMARY OF CHANGE
4/7/2014 M.Domenech Revised for DAP Application
1
100825