HomeMy WebLinkAboutContract 56788-PM1PROJECT MANUAL
FOR
THE CONSTRUCTION OF
WATER AND SEWER IMPROVEMENTS
TO SERVE
THE LIBRARY
IPRC Record No. IPRC20-0012
City Project No. 102561
X File No. 26388
FID No. 30114-0200431-102561-E07685
File No. K-2739
Mattie Parker David Cooke
Mayor City Manager
Christopher P. Harder, P.E.
Director, Water Department
Prepared for
The City of Fort Worth
November 2021
Prepared by:
Texas Registered Engineering Firm F-928
801 Cherry Street, Suite 1300, Unit 11
Fort Worth, TX 76102
817.339.2269
Kimley-Horn No. 064145035
CSC No. 56788-PM1
00 00 00
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Page 1 of 6
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102561
Revised March 20, 2020
SECTION 00 00 10
TABLE OF CONTENTS
DEVELOPER AWARDED PROJECTS
Division 00 - General Conditions Last Revised
00 11 13 Invitation to Bidders 03/20/2020
00 21 13 Instructions to Bidders 03/20/2020
00 41 00 Bid Form 04/02/2014
00 42 43 Proposal Form Unit Price 05/22/2019
00 43 13 Bid Bond 04/02/2014
00 45 11 Bidders Prequalification’s 04/02/2014
00 45 12 Prequalification Statement 09/01/2015
00 45 13 Bidder Prequalification Application 03/09/2020
00 45 26 Contractor Compliance with Workers' Compensation Law 04/02/2014
00 45 40 Minority Business Enterprise Goal 08/21/2018
00 52 43 Agreement 06/16/2016
00 61 25 Certificate of Insurance 07/01/2011
00 62 13 Performance Bond 01/31/2012
00 62 14 Payment Bond 01/31/2012
00 62 19 Maintenance Bond 01/31/2012
00 72 00 General Conditions 11/15/2017
00 73 00 Supplementary Conditions 03/09/2020
00 73 10 Standard City Conditions of the Construction Contract for Developer
Awarded Projects 01/10/2013
Division 01 - General Requirements Last Revised
01 11 00 Summary of Work 12/20/2012
01 25 00 Substitution Procedures 08/30/2013
01 31 19 Preconstruction Meeting 08/30/2013
01 31 20 Project Meetings 07/01/2011
01 32 33 Preconstruction Video 08/30/2013
01 33 00 Submittals 08/30/2013
01 35 13 Special Project Procedures 08/30/2013
01 45 23 Testing and Inspection Services 03/20/2020
01 50 00 Temporary Facilities and Controls 07/01/2011
01 55 26 Street Use Permit and Modifications to Traffic Control 07/01/2011
01 57 13 Storm Water Pollution Prevention Plan 07/01/2011
01 60 00 Product Requirements 03/20/2020
01 66 00 Product Storage and Handling Requirements 04/07/2014
01 70 00 Mobilization and Remobilization 04/07/2014
01 71 23 Construction Staking (Mod) 04/07/2014
01 74 23 Cleaning 04/07/2014
01 77 19 Closeout Requirements 04/07/2014
01 78 23 Operation and Maintenance Data 04/07/2014
01 78 39 Project Record Documents 04/07/2014
00 00 00
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Page 2 of 6
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102561
Revised March 20, 2020
Technical Specifications which have been modified by the Engineer specifically for this
Project; hard copies are included in the Project’s Contract Documents
Division 02 - Existing Conditions
None
Division 03 - Concrete
None
Division 26 – Electrical
None
Division 31 - Earthwork
None
Division 32 - Exterior Improvements
None
Division 33 – Utilities
None
Division 34 – Transportation
None
Technical Specifications listed below are included for this Project by reference and can be
viewed/downloaded from the City’s website at:
http://fortworthtexas.gov/tpw/contractors/
or
https://apps.fortworthtexas.gov/ProjectResources/
Division 02 - Existing Conditions Last Revised
02 41 13 Selective Site Demolition 12/20/2012
02 41 14 Utility Removal/Abandonment 12/20/2012
02 41 15 Paving Removal 02/02/2016
Division 03 - Concrete
03 30 00 Cast-In-Place Concrete 12/20/2012
03 34 13 Controlled Low Strength Material (CLSM) 12/20/2012
03 34 16 Concrete Base Material for Trench Repair 12/20/2012
03 80 00 Modifications to Existing Concrete Structures 12/20/2012
Division 26 - Electrical
26 05 00 Common Work Results for Electrical 11/22/2013
26 05 10 Demolition for Electrical Systems 12/20/2012
26 05 33 Raceways and Boxes for Electrical Systems 12/20/2012
26 05 43 Underground Ducts and Raceways for Electrical Systems 07/01/2011
26 05 50 Communications Multi-Duct Conduit 02/26/2016
00 00 00
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Page 3 of 6
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102561
Revised March 20, 2020
Division 31 - Earthwork
31 10 00 Site Clearing 12/20/2012
31 23 16 Unclassified Excavation 01/28/2013
31 23 23 Borrow 01/28/2013
31 24 00 Embankments 01/28/2013
31 25 00 Erosion and Sediment Control 12/20/2012
31 36 00 Gabions 12/20/2012
31 37 00 Riprap 12/20/2012
Division 32 - Exterior Improvements
32 01 17 Permanent Asphalt Paving Repair 12/20/2012
32 01 18 Temporary Asphalt Paving Repair 12/20/2012
32 01 29 Concrete Paving Repair 12/20/2012
32 11 23 Flexible Base Courses 12/20/2012
32 11 29 Lime Treated Base Courses 12/20/2012
32 11 33 Cement Treated Base Courses 12/20/2012
32 11 37 Liquid Treated Soil Stabilizer 08/21/2015
32 12 16 Asphalt Paving 12/20/2012
32 12 73 Asphalt Paving Crack Sealants 12/20/2012
32 13 13 Concrete Paving 12/20/2012
32 13 20 Concrete Sidewalks, Driveways and Barrier Free Ramps 06/05/2018
32 13 73 Concrete Paving Joint Sealants 12/20/2012
32 14 16 Brick Unit Paving 12/20/2012
32 16 13 Concrete Curb and Gutters and Valley Gutters 10/05/2016
32 17 23 Pavement Markings 11/22/2013
32 17 25 Curb Address Painting 11/04/2013
32 31 13 Chain Fences and Gates 12/20/2012
32 31 26 Wire Fences and Gates 12/20/2012
32 31 29 Wood Fences and Gates 12/20/2012
32 32 13 Cast-in-Place Concrete Retaining Walls 06/05/2018
32 91 19 Topsoil Placement and Finishing of Parkways 12/20/2012
32 92 13 Hydro-Mulching, Seeding, and Sodding 12/20/2012
32 93 43 Trees and Shrubs 12/20/2012
Division 33 - Utilities
33 01 30 Sewer and Manhole Testing 12/20/2012
33 01 31 Closed Circuit Television (CCTV) Inspection 03/03/2016
33 03 10 Bypass Pumping of Existing Sewer Systems 12/20/2012
33 04 10 Joint Bonding and Electrical Isolation 12/20/2012
33 04 11 Corrosion Control Test Stations 12/20/2012
33 04 12 Magnesium Anode Cathodic Protection System 12/20/2012
33 04 30 Temporary Water Services 07/01/2011
33 04 40 Cleaning and Acceptance Testing of Water Mains 02/06/2013
33 04 50 Cleaning of Sewer Mains 12/20/2012
33 05 10 Utility Trench Excavation, Embedment, and Backfill 12/12/2016
33 05 12 Water Line Lowering 12/20/2012
33 05 13 Frame, Cover and Grade Rings – Cast Iron 01/22/2016
33 05 13.10 Frame, Cover and Grade Rings – Composite 01/22/2016
00 00 00
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Page 4 of 6
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102561
Revised March 20, 2020
33 05 14 Adjusting Manholes, Inlets, Valve Boxes, and Other Structures to
Grade 12/20/2012
33 05 16 Concrete Water Vaults 12/20/2012
33 05 17 Concrete Collars 12/20/2012
33 05 20 Auger Boring 12/20/2012
33 05 21 Tunnel Liner Plate 12/20/2012
33 05 22 Steel Casing Pipe 12/20/2012
33 05 23 Hand Tunneling 12/20/2012
33 05 24 Installation of Carrier Pipe in Casing or Tunnel Liner Plate 06/19/2013
33 05 26 Utility Markers/Locators 12/20/2012
33 05 30 Location of Existing Utilities 12/20/2012
33 11 05 Bolts, Nuts, and Gaskets 12/20/2012
33 11 10 Ductile Iron Pipe 12/20/2012
33 11 11 Ductile Iron Fittings 12/20/2012
33 11 12 Polyvinyl Chloride (PVC) Pressure Pipe 11/16/2018
33 11 13 Concrete Pressure Pipe, Bar-Wrapped, Steel Cylinder Type 12/20/2012
33 11 14 Buried Steel Pipe and Fittings 12/20/2012
33 12 10 Water Services 1-inch to 2-inch 02/14/2017
33 12 11 Large Water Meters 12/20/2012
33 12 20 Resilient Seated Gate Valve 12/20/2012
33 12 21 AWWA Rubber-Seated Butterfly Valves 12/20/2012
33 12 25 Connection to Existing Water Mains 02/06/2013
33 12 30 Combination Air Valve Assemblies for Potable Water Systems 12/20/2012
33 12 40 Fire Hydrants 01/03/2014
33 12 50 Water Sample Stations 12/20/2012
33 12 60 Standard Blow-off Valve Assembly 06/19/2013
33 31 12 Cured in Place Pipe (CIPP) 12/20/2012
33 31 13 Fiberglass Reinforced Pipe for Gravity Sanitary Sewers 12/20/2012
33 31 15 High Density Polyethylene (HDPE) Pipe for Sanitary Sewer 12/20/2012
33 31 20 Polyvinyl Chloride (PVC) Gravity Sanitary Sewer Pipe 06/19/2013
33 31 21 Polyvinyl Chloride (PVC) Closed Profile Gravity Sanitary Sewer
Pipe 12/20/2012
33 31 22 Sanitary Sewer Slip Lining 12/20/2012
33 31 23 Sanitary Sewer Pipe Enlargement 12/20/2012
33 31 50 Sanitary Sewer Service Connections and Service Line 04/26/2013
33 31 70 Combination Air Valve for Sanitary Sewer Force Mains 12/20/2012
33 39 10 Cast-in-Place Concrete Manholes 12/20/2012
33 39 20 Precast Concrete Manholes 12/20/2012
33 39 30 Fiberglass Manholes 12/20/2012
33 39 40 Wastewater Access Chamber (WAC) 12/20/2012
33 39 60 Epoxy Liners for Sanitary Sewer Structures 12/20/2012
33 41 10 Reinforced Concrete Storm Sewer Pipe/Culverts 07/01/2011
33 41 11 High Density Polyethylene (HDPE) Pipe for Storm Drain 12/20/2012
33 41 12 Reinforced Polyethlene (SRPE) Pipe 11/13/2015
33 46 00 Subdrainage 12/20/2012
33 46 01 Slotted Storm Drains 07/01/2011
33 46 02 Trench Drains 07/01/2011
33 49 10 Cast-in-Place Manholes and Junction Boxes 12/20/2012
33 49 20 Curb and Drop Inlets 12/20/2012
00 00 00
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Page 5 of 6
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102561
Revised March 20, 2020
33 49 40 Storm Drainage Headwalls and Wingwalls 07/01/2011
Division 34 - Transportation
34 41 10 Traffic Signals 10/12/2015
34 41 10.01 Attachment A – Controller Cabinet 12/18/2015
34 41 10.02 Attachment B – Controller Specification 02/2012
34 41 10.03 Attachment C – Software Specification 01/2012
34 41 11 Temporary Traffic Signals 11/22/2013
34 41 13 Removing Traffic Signals 12/20/2012
34 41 15 Rectangular Rapid Flashing Beacon 11/22/2013
34 41 16 Pedestrian Hybrid Signal 11/22/2013
34 41 20 Roadway Illumination Assemblies 12/20/2012
34 41 20.01 Arterial LED Roadway Luminaires 06/15/2015
34 41 20.02 Freeway LED Roadway Luminaires 06/15/2015
34 41 20.03 Residential LED Roadway Luminaires 06/15/2015
34 41 30 Aluminum Signs 11/12/2013
34 41 50 Single-Mode Fiber Optic Cable 02/26/2016
34 71 13 Traffic Control 11/22/2013
00 00 00
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Page 6 of 6
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102561
Revised March 20, 2020
Appendix
GC-4.01 Availability of Lands
GC-4.02 Subsurface and Physical Conditions
GC-4.04 Underground Facilities
GC-4.06 Hazardous Environmental Condition at Site
GC-6.06.D Minority and Women Owned Business Enterprise Compliance
GC-6.07 Wage Rates
GC-6.09 Permits and Utilities
GC-6.24 Nondiscrimination
GR-01 60 00 Product Requirements
END OF SECTION
1 0241.1012 Remove 6" Water Line 02 41 14 LF 299 $15.00 $4,485
2 0241.1118 4"-12" Pressure Plug 02 41 14 EA 1 $650.00 $650
3 3201.0112 5' Wide Asphalt Pvmt Repair, Residential 32 01 17 LF 420 $100.00 $42,000
4 3212.0201 2" Asphalt Pvmt Type C 32 12 16 SY 467 $65.00 $30,355
5 3304.0101 Temporary Water Services 33 04 30 LS 1 $3,000.00 $3,000
6 3305.0103 Exploratory Excavation of Existing Utilities 33 05 30 EA 1 $1,000.00 $1,000
7 3305.0109 Trench Safety 33 05 10 LF 452 $2.00 $904
8 3311.0161 6" PVC Water Pipe 33 11 12 LF 7 $100.00 $700
9 3311.0001 Ductile Iron Water Fittings w/ Restraint 33 11 11 TON 0.5 $10,000.00 $5,000
10 3311.0261 8" PVC Water Pipe 33 11 12 LF 452 $92.00 $41,584
11 3312.0001 Fire Hydrant 33 12 40 EA 1 $3,750.00 $3,750
12 3312.0117 Connection to Existing 4"-12" Water Main 33 12 25 EA 1 $2,000.00 $2,000
13 3312.2203 2" Water Service 33 12 10 EA 2 $3,000.00 $6,000
14 3312.3002 6" Gate Valve 33 12 20 EA 1 $1,650.00 $1,650
15 3312.3003 8" Gate Valve 33 12 20 EA 1 $2,250.00 $2,250
16 3471.0001 Traffic Control 34 71 13 MO 1 $2,500.00 $2,500
17 9999.0001 Kupferle #9700 Automatic Flushing Device 00 00 00 EA 1 $6,500.00 $6,500
1 3110.0102 6"-12" Tree Removal 31 10 00 EA 2 $850.00 $1,700
2 3110.0103 12"-18" Tree Removal 31 10 00 EA 1 $1,250.00 $1,250
3 3137.0104 Medium Stone Riprap, dry 31 37 00 SY 33 $85.00 $2,805
4 3301.0002 Post-CCTV Inspection 33 01 31 LF 272 $2.00 $544
5 3305.0109 Trench Safety 33 05 10 LF 272 $2.00 $544
6 3305.0113 Trench Water Stops 33 05 15 EA 3 $750.00 $2,250
7 3331.4115 8" Sewer Pipe 33 11 10, 33 31 12, 33 31 20 LF 272 $60.00 $16,320
8 3339.0001 Epoxy Manhole Liner 33 39 60 VF 23 $400.00 $9,200
9 3339.1001 4' Manhole 33 39 10, 33 39 20 EA 4 $5,500.00 $22,000
$154,328
$56,613
$210,941
END OF SECTION
Contractor Name
Signature
Date
CONTRACT commences to run as provided in the General Conditions.
HARD CONSTRUCTION COSTS:
UNIT I: WATER IMPROVEMENTS
UNIT II: SANITARY SEWER IMPROVEMENTS
Contractor agrees to complete WORK for FINAL ACCEPTANCE within working days after the date when the
BID TOTAL:
$56,613TOTAL UNIT II: SANITARY SEWER IMPROVEMENTS
UNIT PRICE BID Bidder's Application
Specification Section No.Unit of
Measure
Bidlist Item
No.
Bidder's Proposal
Description Bid Quantity Unit Price Bid Value
Project Item Information
UNIT I: WATER IMPROVEMENTS
SECTION 00 42 43
Developer Awarded Projects - PROPOSAL FORM
TOTAL UNIT I: WATER IMPROVEMENTS
UNIT II: SANITARY SEWER IMPROVEMENTS
$154,328
25
Andy Nord - Owner / GM of Dagger Contracting
9/22/21
00 45 12
DAP PREQUALIFICATION STATEMENT
Page 1 of 1
CITY OF FORT WORTH
STANDARD CONSTRUCTION PREQUALIFICATION STATEMENT – DEVELOPER AWARDED PROJECTS 00 45 12_Prequalification Statement 2015_DAP.docx
Form Version September 1, 2015
SECTION 00 45 12
DAP – PREQUALIFICATION STATEMENT
Each Bidder is required to complete the information below by identifying the prequalified contractors
and/or subcontractors whom they intend to utilize for the major work type(s) listed. In the “Major Work
Type” box provide the complete major work type and actual description as provided by the Water
Department for water and sewer and TPW for paving.
Major Work Type Contractor/Subcontractor Company Name Prequalification
Expiration Date
Water Distribution,
Development, 8-inch diameter
and smaller
Dagger Contracting LLC 1/31/2023
Sewer Collection System,
Development, 8-inches and
smaller
Dagger Contracting LLC 1/31/2023
<List Work Type Here or Blank> <Company Name Here or Blank> <Date Here or
Blank>
<List Work Type Here or Blank> <Company Name Here or Blank> <Date Here or
Blank>
The undersigned hereby certifies that the contractors and/or subcontractors described in the table above
are currently prequalified for the work types listed.
BIDDER:
BY:
_________________________________________
(Signature)
TITLE:
DATE:
END OF SECTION
Dagger Contracting, LLC
PO Box 1040
Roanoke, TX 76262
Andrew Nord
Owner / GM
2/16/22
00 52 43 - 1
Developer Awarded Project Agreement
Page 1 of 4
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102561
Revised June 16, 2016
SECTION 00 52 43 1
AGREEMENT 2
THIS AGREEMENT, authorized on ______________is made by and between the Developer, 3
ASFW Apartments, L.P., authorized to do business in Texas (“Developer”) , and 4
______________________________________________________________, authorized to do 5
business in Texas, acting by and through its duly authorized representative, (“Contractor”). 6
Developer and Contractor, in consideration of the mutual covenants hereinafter set forth, agree as 7
follows: 8
Article 1. WORK 9
Contractor shall complete all Work as specified or indicated in the Contract Documents for the 10
Project identified herein. 11
Article 2. PROJECT 12
The project for which the Work under the Contract Documents may be the whole or only a part is 13
generally described as follows: 14
Water and Sewer to Serve The Library 15
102561 16
Article 3. CONTRACT TIME 17
3.1 Time is of the essence. 18
All time limits for Milestones, if any, and Final Acceptance as stated in the Contract 19
Documents are of the essence to this Contract. 20
3.2 Final Acceptance. 21
The Work will be complete for Final Acceptance within 25 working days after the date 22
when the Contract Time commences to run as provided in Paragraph 12.04 of the Standard 23
City Conditions of the Construction Contract for Developer Awarded Projects. 24
3.3 Liquidated damages 25
Contractor recognizes that time is of the essence of this Agreement and that Developer 26
will suffer financial loss if the Work is not completed within the times specified in 27
Paragraph 3.2 above, plus any extension thereof allowed in accordance with Article 10 of 28
the Standard City Conditions of the Construction Contract for Developer Awarded 29
Projects. The Contractor also recognizes the delays, expense and difficulties involved in 30
proving in a legal proceeding the actual loss suffered by the Developer if the Work is not 31
completed on time. Accordingly, instead of requiring any such proof , Contractor agrees 32
that as liquidated damages for delay (but not as a penalty), Contractor shall pay 33
Developer One Thousand Two Hundred Fifty Dollars and Zero Cents, ($1,250.00) for 34
each day that expires after the time specified in Paragraph 3.2 for Final Acceptance until 35
the City issues the Final Letter of Acceptance. 36
Dagger Contracting, LLC
2/17/2022
00 52 43 - 2
Developer Awarded Project Agreement
Page 2 of 4
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102561
Revised June 16, 2016
Article 4. CONTRACT PRICE 37
Developer agrees to pay Contractor for performance of the Work in accordance with the Contract 38
Documents an amount in current funds of __________________________________Dollars 39
($___________________). 40
Article 5. CONTRACT DOCUMENTS 41
5.1 CONTENTS: 42
A. The Contract Documents which comprise the entire agreement between Developer and 43
Contractor concerning the Work consist of the following: 44
1. This Agreement. 45
2. Attachments to this Agreement: 46
a. Bid Form (As provided by Developer) 47
1) Proposal Form (DAP Version) 48
2) Prequalification Statement 49
3) State and Federal documents (project specific) 50
b. Insurance ACORD Form(s) 51
c. Payment Bond (DAP Version) 52
d. Performance Bond (DAP Version) 53
e. Maintenance Bond (DAP Version) 54
f. Power of Attorney for the Bonds 55
g. Worker’s Compensation Affidavit 56
h. MBE and/or SBE Commitment Form (If required) 57
3. Standard City General Conditions of the Construction Contract for Developer 58
Awarded Projects. 59
4. Supplementary Conditions. 60
5. Specifications specifically made a part of the Contract Documents by attachment 61
or, if not attached, as incorporated by reference and described in the Table of 62
Contents of the Project’s Contract Documents. 63
6. Drawings. 64
7. Addenda. 65
8. Documentation submitted by Contractor prior to Notice of Award. 66
9. The following which may be delivered or issued after the Effective Date of the 67
Agreement and, if issued, become an incorporated part of the Contract Documents: 68
a. Notice to Proceed. 69
b. Field Orders. 70
c. Change Orders. 71
d. Letter of Final Acceptance. 72
73
74
229,916.00
Two Hundred Twenty Nine Thousand,
Nine Hundred Sixteen Dollars($210,941.00 ).
Two Hundred Ten Thousand, Nine Hundred Forty-One Dollars
00 52 43 - 3
Developer Awarded Project Agreement
Page 3 of 4
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102561
Revised June 16, 2016
Article 6. INDEMNIFICATION 75
6.1 Contractor covenants and agrees to indemnify, hold harmless and defend, at its own 76
expense, the city, its officers, servants and employees, from and against any and all 77
claims arising out of, or alleged to arise out of, the work and services to be performed 78
by the contractor, its officers, agents, employees, subcontractors, licenses or invitees 79
under this contract. This indemnification provision is specifically intended to operate 80
and be effective even if it is alleged or proven that all or some of the damages being 81
sought were caused, in whole or in part, by any act, omission or negligence of the city. 82
This indemnity provision is intended to include, without limitation, indemnity for 83
costs, expenses and legal fees incurred by the city in defending against such claims and 84
causes of actions. 85
86
6.2 Contractor covenants and agrees to indemnify and hold harmless, at its own expense, 87
the city, its officers, servants and employees, from and against any and all loss, damage 88
or destruction of property of the city, arising out of, or alleged to arise out of, the work 89
and services to be performed by the contractor, its officers, agents, employees, 90
subcontractors, licensees or invitees under this contract. This indemnification 91
provision is specifically intended to operate and be effective even if it is alleged or 92
proven that all or some of the damages being sought were caused, in whole or in part, 93
by any act, omission or negligence of the city. 94
95
Article 7. MISCELLANEOUS 96
7.1 Terms. 97
Terms used in this Agreement are defined in Article 1 of the Standard City Conditions of 98
the Construction Contract for Developer Awarded Projects. 99
7.2 Assignment of Contract. 100
This Agreement, including all of the Contract Documents may not be assigned by the 101
Contractor without the advanced express written consent of the Developer. 102
7.3 Successors and Assigns. 103
Developer and Contractor each binds itself, its partners, successors, assigns and legal 104
representatives to the other party hereto, in respect to all covenants, agreements and 105
obligations contained in the Contract Documents. 106
7.4 Severability. 107
Any provision or part of the Contract Documents held to be unconstitutional, void or 108
unenforceable by a court of competent jurisdiction shall be deemed stricken, and all 109
remaining provisions shall continue to be valid and binding upon DEVELOPER and 110
CONTRACTOR. 111
7.5 Governing Law and Venue. 112
This Agreement, including all of the Contract Documents is performable in the State of 113
Texas. Venue shall be Tarrant County, Texas, or the United States District Court for the 114
Northern District of Texas, Fort Worth Division. 115
2/17/20222/17/2022
Bond No. NTX 3797
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
SECTION 00 62 13
PERFORMANCE BOND
006213-I
PERFORMANCE BOND
Page 1 of 3
THE STATE OF TEXAS §
§ KNOW ALL BY THESE PRESENTS:
COUNTY OF TARRANT §
That we, Dagger Contracting LLC known as
"Principal" herein and Merchants National BondinQ Inc , a corporate
surety(sureties, if more than one) duly authorized to do business in the State of Texas, known as
"Surety" herein (whether one or more), are held and firmly bound unto the Developer, ASFW
Apartments, L.P., authorized to do business in Texas ("Developer") and the City of Fort Worth, a
Texas municipal corporation ("City"), in the penal sum of,
Two Hundred Twenty-Nine Thousand Nine Hundred Sixteen and 00/100DOI I8['S ($ ZZ9,916.00 ),
lawful money of the United States, to be paid in Fort Worth, Tarrant County, Texas for the
payment of which sum well and tnily to be made jointly unto the Developer and the City as dual
obligees, we bind ourselves, our heirs, executors, administrators, successors and assigns, jointly
and severally, firmly by these presents.
18 WHEREAS, Developer and City have entered into an Agreement for the construction of
19 community facilities in the City of Fort Worth by and through a Community Facilities
20 Agreement, CFA Number CFA20-0029;and
21 WHEREAS, the Principal has entered into a certain written contract with the Developer awarded
22 the I� day of hcaa.+.� , 20� which Contract is hereby refened to and made a
23 part hereof for all purposes as if fully set forth herein, to furnish all materials, equipment labor
24 and other accessories defined by law, in the prosecution of the Work, including any Change
25 Orders, as provided for in said Contract designated as Water and Se►ver to Serve The Library.
26 NOW, THEREFORE, the condition ofthis obligation is such that ifthe said Principal
27 shall faithfully perform it obligations under the Contract and shall in all respects duly and
28 faithfully perform the Work, including Change Orders, under the Contract, according to the plans,
29 specifications, and contract documents therein referred to, and as well during any period of
30 extension of the Contract that may be granted on the part of the Developer and/or City, then this
31 obligation shall be and become null and void, otherwise to remain in full force and effect.
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised January 31, 2012
Water und Sewer to Serve The /,rbrary
101.i6/
This document was created by an apptication that isn't licensed to use novaPDF.
Purchase a license to generate PDF files without this notice.
006213-2
PERFORMANCE BOND
Page 2 of 3
10
Il
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
1 PROVIDED FURTHER, dtat ifany legal action be filed on this Bond, venue shali lie in
2 Tairant County, Texas or the United States District Court for the Northern District of Texas, Fort
3 Worth Division.
4 T'his bond is made and executed in compliance with the provisions of Chapter 2253 of the
5 Texas Government Code, as amended, and all liabilities on this bond shall be determined in
6 accordance with the provisions of said statue.
7 IN WITNESS WHEREOF, the Principal and the Surety have SIGNED and SEALED
8 this instrument by duly authorized agents and officers on this the /�'-" day of
9 te�sn...,.a.,� .20�.
����1��
� -
�.
W itn ss as to Princi al
'►.%!�1 T �f.��
Witness as to urety, Sophie Hunter
PRINCIPAL:
Dae
BY:
Signature
7t�w No/� - Qi�lN6� /(�l�'1
Name and Title '-
Address: 660 N Carroll Ave, Ste 130
Southlake, TX 76092
SURETY:
Merchants National Bondin� Inc
BY: ` _lJil — _J "__� Jyi.
Signaiure ` =„ �-.�
_ _� f -� -
Mikaela Peppers Attornev-In-Fact - ^ , ^ J ' _
'� �
Name and Title - ,� � -
� ='�� � '
'i -. '� ^ ;
Address: 6700 Westown Parkway �, r �- _
West Des Moines, IA 50266 -___
Telephone Number. 800-678-8171
*Note: If signed by an officer of the Surety Company, there must be on file a certified extract
from the by-laws showing that this person has authority to sign such obligation. If
Surety's physical address is different from its mailing address, both must be provided.
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised January 31, 2012
Wurer and tiewer to Serve '!'he l,ihrury
10156!
This document was created by an application that isn't licensed to use novaPDF.
Purchase a license to generate PDF files without this notice.
006213-3
PERFORMANCE BOND
Page 3 of 3
T'he date of the bond shall not be prior to the date the Contract is awarded.
CITY OF FORT WORTH Wu�er and Sewer �o Serve %he Lrhrrrry
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS 10256/
Revised January 31, 2012
This document was created by an application that isn't licensed to use npvaPDF.
Purchase a license to generate PDF files without this notice.
Bond No. NTX 3797
006214-]
PAYMENTBOND
Page 1 of2
1
2
3
4
5
6
THE STATE OF TEXAS
COUNTY OF TARRANT
SECTION 00 62 l4
PAYMENT BOND
§
§ KNOW ALL BY THESE PRESENTS:
§
7 That we, Dagger Contracting, LLC , known as
8 "Principal" herein, and Merchants National Bonding Inc , a
9 corporate surety ( or sureties if more than one), duly authorized to do business in the State of
10 Texas, known as"Surety" herein (whether one or more), are held and firmly bound unto the
i l Developer, ASFW Apartments, L.P., authorized to do business in Texas "(Developer"), and the
12 City of Fort Worth, a Texas municipal corporation ("City"), in the penal sum
13 OfTwo Hundred Twenry-Nine Thousand Nine Hundred Sixteen and 00/100DOII3I'S �$ 229,916.00 ),
14 lawful money of the United States, to be paid in Fort Worth, Tazrant County, Texas, for the
15 payment of which sum well and truly be made jointly unto the Developer and the City as dual
16 obligees, we bind ourselves, our heirs, executors, administrators, successors and assigns, jointly
17 and severally, firmly by these presents:
18 WHEREAS, Developer and City have entered into an Agreement for the construction of
19 community facilities in the City of Fort Worth, by and through a Community Facilities
20 Agreement, CFA Number CFA20-0029;and
21 WHEREAS, Principal has entered into a certain written Contract with Developer,
22 awarded the �� day of 1=��,At�.,, , 20 22 , which Contract is hereby
23 referred to and made a part hereof for all purposes as if fully set forth herein, to furnish all
24 materials, equipment, labor and other accessories as defined by law, in the prosecution of the
25 Work as provided for in said Contract and designated as Water and Sewer to Serve The Library.
26 NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION is such that if
27 Principal shall pay all monies owing to any (and all) payment bond beneficiary (as defined in
28 Chapter 2253 of the Texas Government Code, as amended) in the prosecution of the Work under
29 the Contract, then this obligation shall be and become null and void; otherwise to remain in full
30 force and effect.
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVII.OPER AWARDED PROJECTS
Revised January 31, 2012
Water und Sewer to Serve The Lihrary
l0256/
This document was created by an application that isn't licensed to use novaPDF.
Purchase a license to generate PDF files without this notice.
006214-2
PAYMENT BOND
Page 2 of 2
2
3
4
�
8
9
10
11
12
13
14
This bond is made and executed in compliance with the provisions of Chapter 2253 of the
Texas Government Code, as amended, and all Gabilities on this bond shall be determined in
accordance with the provisions of said statute.
IN WITNESS WHEREOF, the Principal and Surety have each SIGNED and SEALED
5 this instrument by duly authorized agents and officers on this the l� day of
h'aaR..aaw , 20 1.Z .
7
ATTEST:
nci ) Secretary
Wimes as to Principal
ATTEST:
(Surety) Secretary
�� '��1.�1rL� L
Witness as to Surety; Sophie Hunter
PRINCIPAL:
Da er Contractin LLC
BY: �
Signature
��R�, �l � ' OW,�/�
Name and Title
Address: 660 N Carroll Ave, Ste 130
Southlake, TX 76092
SURETY:
Merchants National Bonding Inc.
�. � , � ��!�
/ /
Mikaela Peppers, Attorney-In-Fact
Name and Title
Address: 6700 Westown Parkwav
Southlake,TX 76092
Telephone Number: 800-678-8171
� __ � i
_ ^� • � J �`. �
� �
- � �� � �
_ _:; - � _
: -
��� v +;
Note: If signed by an officer of the Surety, there must be on file a certified extract from the
bylaws showing that this person has authority to sign such obligation. If Surety's physical
address is different from its mailing address, both must be provided.
The date of the bond shall not be prior to the date the Contract is awazded.
END OF SECTION
CITY OF FORT WORTH
STANDARD CITY CONDITIONS- DEVELOPER AWARDED PROJECTS
Revised January 31, 2012
Wa�erund SewerL� Serve lhe Lrbrary
inzsdt
This document was created by an application that isn't licensed to use novaPDF.
Purchase a license to generate PDF files without this notice.
Bond No. NTX 3797
2
3
4
5
6
7
8
9
10
11
12
�T'.
20
SECTION 00 62 19
MAINTENANCE BOND
00 62 19 - 1
MAINTENANCE BOND
Page 1 of3
THE STATE OF TEXAS §
§ KNOW ALL BY THESE PRESENTS:
COUNTY OF TARRANT §
That we Dag�er Contracting, LLC , known as
"Principal" herein and Merchants National Bonding Inc. , a corporate surety
(sureties, if more than one) duly authorized to do business in the State of Texas, known as
"Surety" herein (whether one or more), are held and firmly bound unto the Developer, ASFW
Aparnnents, L. P., authorized to do business in Texas ("Developer") and the City of Fort Worth, a
Texas municipal corporation ("City"), in the sum
13 OfTwo Hundred Twenty-Nine Thousand Nine Hundred Sixteen and 00/10(flOI18TS �$ 229,916.00 ),
14 lawful money of the United States, to be paid in Fort Worth, Tarrant County, Texas, for payment
15 of which sum well and truly be made jointly unto the Developer and the City as dual obligees and
16 their successors, we bind ourselves, our heirs, executors, administrators, successors and assigr�s,
17 jointly and severally, firmly by these presents.
18
WHEREAS, Developer and City have entered into an Agreement for the construction of
community facilities in the City of Fort Worth by and through a Community Facilities
21 Agreement, CFA Number CFA20-0029;and
22 WHEREAS, the Principal has entered into a certain written contract with the Developer
23 awarded the I� day of r�s�a;+.y 20 ZZ , which Contract is
24
25
26
27
28
29
30
31
32
33
34
hereby referred to and a made part hereof for all purposes as if fully set forth herein, to furnish all
materials, equipment labor and other accessories as defined by law, in the prosecution of the
Work, including any Work resulting from a duly authorized Change Order (collectively herein,
the "Work") as provided for in said Contract and designated as Water and Sewer to Serve The
Library;and
WHEREAS, Principal binds itself to use such materials and to so construct the Work in
accordance with the plans, specifications and Contract Documents that the Work is and will
remain free from defects in materials or workmanship for and during the period of two (2) years
after the date of Final Acceptance of the Work by the City ("Maintenance Period"); and
CTI'Y OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDEp PROJECTS
Revised January 31, 2012
Water und Sewer lo Serve The l.ihrary
l0156/
This document was created by an application that isn't licensed to use novaPDF.
Purchase a license to generate PDF files without this notice.
006219-2
MAINTENANCE BOND
Page 2 of 3
�
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
WHEREAS, Principal binds itself to repair or reconstruct the Work in whole or in part
upon receiving norice from the Developer and/or City of the need thereof at any time within the
Maintenance Period.
NOW THEREFORE, the condition of this obligation is such that if Principal shall
remedy any defective Work, for which timely notice was provided by Developer or City, to a
completion satisfactory to the City, then this obligation shall become nuli and void; otherwise to
remain in full force and effect.
PROVIDED, HOWEVER, if Principal shall fail so to repair or reconstruct any timely
noticed defective Work, it is agreed that the Developer or City may cause any and all such
defective Work to be repaired and/or reconstructed with all associated costs thereof being borne
by the Principal and the Surety under this Maintenance Bond; and
PROVIDED FURTHER, that ifany legal action be filed on this Bond, venue shall lie in
Tarrant County, Texas or the United States District Court for the Northern District of Texas, Fort
Worth Division; and
PROVIDED FURTHER, that this obligation shall be continuous in nature and
successive recoveries may be had hereon for successive breaches.
CITY OF FORT WORTH
STANDARD CITY CONDITIONS - DEVELOPER AWARDED PROJECTS
Revised lanuary 31, 2012
Water and Sewer to Serve The I,ibrary
102561
This document was created by an application that isn't licensed to use novaPDF.
Purchase a license to generate PDF files without this notice.
006219-3
MAINTENANCE BOND
Page 3 of 3
5
6
7
8
9
10
I1
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
1 IN WITNESS WHEREOF, the Principal and the Surety have each SIGNED and SEALED this
2 instrument by duly authorized agents and officers on this the I� day of
3 r�;�.��iw . 20 �- .
r---
ATTES :
( �pal cretary .
W ifiess as to Principal
ATTEST:
(Surety) Secretary
'�u�Z
Witness as to Sure , Sophie Hunter
PRINCIPAL:
Da er Contractin LLC
BY:
ignature
��VAiEW /VpQQ ^ d/4/fr?L-/Nl �
- l�iame and Title
Address: _ 660 N Carroll Ave. Ste 130
Southlake. TX 76092
SURETY:
Merchants National Bonding Inc.
BY: Signatu/�Z� ��� � J �- _
�
` ` � � �
Mikaela Penpers, Attornev-In-Fact - � v � '�" - -
= ., �.:�
Name and Title ;� -'�i `�✓ , '
, � -:
Address: 6700 Westown Parkwav �' " - �
Southlake, TX 76092 _ -." �_
Telephone Number. 800-678-8171
*Note: If signed by an officer of the Surety Company, there must be on file a certified extract
from the by-laws showing that this person has authority to sign such obligation. If
Surety's physical address is different from its mailing address, both must be provided.
The date of the bond shall not be prior to the date the Contract is awarded.
CCCY OF FORT WOR"CH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised January 31, 2012
Wulerund tiewerto Serve %'hr I,rhrury
I0256!
This document was created by an application that isn't licensed to use novaPDF
Purchase a license to generate PDF files without this notice.
MERCHANT`5�
BONDING COMPANY-u
POWER OF ATTORNEY
Know All Persons By These Presents, that MERCHANTS BONDING COMPANY (MUTUAL) and MERCHANTS NATIONAL BONDING, INC.,
both being corporations of the State of lowa (herein collectively calied the "Companies") do hereby make, constitute and appoint, individuaily,
Don E Comell; Josh Saunders; Kelly A Westbrook; Mikaela Peppers; Ricardo J Reyna; Robbi Morales; Sophinie Hunter; Tina McEwan; Tonie
Petranek
their true and lawful Attomey(s)-in-Fact, to sign its name as surety(ies) and to execute, seal and acknowledge any and all bonds, undertakings,
contracts and other written instruments in the nature thereof, on behalf of the Companies in their business of guaranteeing the fidelity
of persons, guaranteeing the pertormance of contracts and executing or guaranteeing bonds and undertakings required or permitted in any
actions or proceedings allowed by law.
This Power-of-Attomey is granted and is signed and sealed by facsimile under and by authority of the following By-Laws adopted by the Board
of Directors of Merchants Bonding Company (Mutual) on April 23, 2U11 and amended August 14, 2015 and adopted by the Board of Directors
of Merchants National Bonding, Inc., on October 16, 2015.
"The President, Secretary, Treasurer, or any Assistant Treasurer or any Assistant Secretary or any Vice President shall have power and authority
to appoint Attorneys-in-Fact, and to authorize them to execute on behalf of the Company, and attach the seal of the Company thereto, bonds and
undertakings, recognizances, contracts of indemnity and other writings obiigatory in the nature thereof."
"The signature of any authorized officer and the seal of the Company may be affixed by facsimile or electronic transmission to arry Power of Attomey
or Certification thereof authorizing the execution and delivery of any bond, undertaking, recognizance, or other sureryship obligations of the
Company, and such signature and seal when so used shall have the same force and effect as though manualy fixed."
In connection with obligations in favor of the Florida Department of Transportation ony, it is agreed that the power and aut hority hereby given to the
Attorney-in-Fact inGudes any and all consents for the release of retained percentages and/or final estimates on engineering and construction
contracts required by the State of Florida Department of Transportation. It is fully understood that consenGng to the State ofFlorida Department
of Transportation making payment of the final estimate to the Contractor and/or its assignee, shall not relieve this surety company of any of
its obligations under its bond.
In connection with obligations in favor of the KentuGry Department of Highways onty, it is agreed that the power and authority hereby given
to the Attomey-in-Fact cannot be modified or revoked unless prior written personal notice of such intent has been given to the Commissioner-
Department of Highways of the Commonwealth of Kentucky at least thirty (30) days prior to the modification or revocation.
In Witness Whereof, the Companies ha �e caused this instrument to be signed and sealed this 30th day of March , 2p21 .
'��.. .,,�� � � . . . . . � �
�. Z 10 Nq ,, � .
'y . P,....... , l . • p\N... �O,�j •
'p�p�Rq'�G : ' O�•'APOq •'09�. �RCHANTSBONDINGCOMPANY�MUTUAL)
:Z:2G �'�•:ZO; � y: V� '4� ;y�; MERCHANT NATIONAL BONDING, INC.
v� 2003 v`�; : a�' t 933 ��.c � By
. s�- • ti. ��
,:d�•. � � ; . vd. .�o.
�...�.,. � .,:;�'�. .�.��V � �� � `�.• President
STATE OF IOWA �''•'•••••••••' ' • ••••••
COUNTY OF DALLAS ss.
On this 30th day of March 2021 , before me appeared Larry Taylor, to me personally known, who being by me duly swom
did say that he is President of MERCHANTS BONDING COMPANY (MUTUAL) and MERCHANTS NATIONAL BONDING, INC.; and that the
seals affixed to the foregoing instniment are the Corporate Seals of the Companies; and that the said instrument was signed and sealed in behalf
of the Companies by authority of their respective Boards of Directors.
,�P��A� S POLLY MASON .
o � Commission Number 750576 � ��p.ti.�
Z°°°°'� My Commission Expires ��-
• ��rP . January 07, 2023
Notary Public
(Expiration of notary's commission
does not irrvaadate this instrument)
I, William Warner, Jr., Secretary of MERCHANTS BONDING COMPANY (MUTUAL) arxl MERCHANTS NATIONAL BONDING, INC., do hereby
certify that the above and foregoing is a Vue and correct copy of the POWER-0E-ATTORNEY executed by said Companies, which is still in full
force and effect and has not been amended or revoked.
In Witness Whereof, I have hereunto set my hand and affaed the seal of the Companies on this day of
'���..........,� �.•---•.� ,
��.�Pt 10 Nq � � . .• • O�NG Cp�lj••.
� ' • � � �. A •
,y:•oRPoq� .o . .�o,.oRPOA�.qy: �
:a •c, '4�'�;•.Z. � •G �•..c• . �� - _ ///�
=Q;,Z -o- C:�: �:_ -o- �� : i� i%s' �1,�•,,K,G„�
;v� 2003 :`,�; � y 1933 ���c; Sec►etary _ _ _ _
d' ' � Jy• ��:' __
'•..�'••... . ;'��o' •. .�k,•'�1��� �;'a: _ ` -
•����•.. �....�'�� � • • ... . • • _ - = � _`
POA 0018 (1/20) .
�,' __�__ -
MERCHANTS
BONDING COMPANYTM
MERCHANTS BONDING COMPANY (MUTUAL) • MERCHANTS nATIONAL BONDING, INC.
P.O. 60X 1449$ • DE5 MOINES. IOWA 5030G-3498 •(800) G78-8171 •(SI>) 24:i-3854 FAX
IMPORTANT NOTICE
Have a complaint or need help?
if you have a problem with a claim or your premium, call your insurance company first. If you can't work out the
issue, the Texas Department of Insurance may be able to help.
Even if you file a complaint with the Texas Department of Insurance, you should also file a complaint or appeal
through your insurance company. If you don't, you may lose your right to appeal.
Merchants Bonding Company (Mutual)
To get information or file a comptaint with your insurance company:
Call: Compliance Officer at 800-678-8171
To I I-f ree : 1-800-678-8171
Email: regulatory@merchantsbonding.com
Mail: P.O. Box 14498, Des Moines, IA 50306-3498
To get insurance information you may also contact your agent:
Call:
Mail:
The Texas Department of Insurance
To get help with an insurance question or file a complaint with the state:
Call with a question: 1-800-252-3439
File a complaint: www.tdi.texas.gov
Email: ConsumerProtection@tdi.texas.gov
Mail: MC 111-1A, P.O. Box 149091, Austin, TX 78714-9091
SUP 0032 TX (11/19)
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
STANDARD CITY CONDITIONS
OF THE CONSTRUCTION CONTRACT
FOR DEVELOPER AWARDED PROJECTS
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
STANDARD CITY CONDITIONS OF THE
CONSTRUCTION CONTRACT
FOR DEVELOPER AWARDED PROJECTS
TABLE OF CONTENTS
Page
Article 1 – Definitions and Terminology .......................................................................................................... 1
1.01 Defined Terms ............................................................................................................................... 1
1.02 Terminology .................................................................................................................................. 5
Article 2 – Preliminary Matters ......................................................................................................................... 6
2.01 Before Starting Construction ........................................................................................................ 6
2.02 Preconstruction Conference .......................................................................................................... 6
2.03 Public Meeting .............................................................................................................................. 6
Article 3 – Contract Documents and Amending ............................................................................................... 6
3.01 Reference Standards ..................................................................................................................... 6
3.02 Amending and Supplementing Contract Documents .................................................................. 6
Article 4 – Bonds and Insurance ....................................................................................................................... 7
4.01 Licensed Sureties and Insurers ..................................................................................................... 7
4.02 Performance, Payment, and Maintenance Bonds ........................................................................ 7
4.03 Certificates of Insurance ............................................................................................................... 7
4.04 Contractor’s Insurance .................................................................................................................. 9
4.05 Acceptance of Bonds and Insurance; Option to Replace ........................................................... 12
Article 5 – Contractor’s Responsibilities ........................................................................................................ 12
5.01 Supervision and Superintendent ................................................................................................. 12
5.02 Labor; Working Hours ................................................................................................................ 13
5.03 Services, Materials, and Equipment ........................................................................................... 13
5.04 Project Schedule .......................................................................................................................... 14
5.05 Substitutes and “Or-Equals” ....................................................................................................... 14
5.06 Pre-Qualification of Bidders (Prime Contractors and Subcontractors) ..................................... 16
5.07 Concerning Subcontractors, Suppliers, and Others ................................................................... 16
5.08 Wage Rates.................................................................................................................................. 18
5.09 Patent Fees and Royalties ........................................................................................................... 19
5.10 Laws and Regulations ................................................................................................................. 19
5.11 Use of Site and Other Areas ....................................................................................................... 19
5.12 Record Documents ...................................................................................................................... 20
5.13 Safety and Protection .................................................................................................................. 21
5.14 Safety Representative ................................................................................................................. 21
5.15 Hazard Communication Programs ............................................................................................. 22
5.16 Submittals .................................................................................................................................... 22
5.17 Contractor’s General Warranty and Guarantee .......................................................................... 23
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
5.18 Indemnification ........................................................................................................................... 24
5.19 Delegation of Professional Design Services .............................................................................. 24
5.20 Right to Audit: ............................................................................................................................ 25
5.21 Nondiscrimination....................................................................................................................... 25
Article 6 – Other Work at the Site ................................................................................................................... 26
6.01 Related Work at Site ................................................................................................................... 26
Article 7 – City’s Responsibilities................................................................................................................... 26
7.01 Inspections, Tests, and Approvals .............................................................................................. 26
7.02 Limitations on City’s Responsibilities ....................................................................................... 26
7.03 Compliance with Safety Program ............................................................................................... 27
Article 8 – City’s Observation Status During Construction ........................................................................... 27
8.01 City’s Project Representative ..................................................................................................... 27
8.02 Authorized Variations in Work .................................................................................................. 27
8.03 Rejecting Defective Work .......................................................................................................... 27
8.04 Determinations for Work Performed .......................................................................................... 28
Article 9 – Changes in the Work ..................................................................................................................... 28
9.01 Authorized Changes in the Work ............................................................................................... 28
9.02 Notification to Surety .................................................................................................................. 28
Article 10 – Change of Contract Price; Change of Contract Time ................................................................ 28
10.01 Change of Contract Price ............................................................................................................ 28
10.02 Change of Contract Time............................................................................................................ 28
10.03 Delays .......................................................................................................................................... 28
Article 11 – Tests and Inspections; Correction, Removal or Acceptance of Defective Work ...................... 29
11.01 Notice of Defects ........................................................................................................................ 29
11.02 Access to Work ........................................................................................................................... 29
11.03 Tests and Inspections .................................................................................................................. 29
11.04 Uncovering Work ....................................................................................................................... 30
11.05 City May Stop the Work ............................................................................................................. 30
11.06 Correction or Removal of Defective Work ................................................................................ 30
11.07 Correction Period ........................................................................................................................ 30
11.08 City May Correct Defective Work ............................................................................................. 31
Article 12 – Completion .................................................................................................................................. 32
12.01 Contractor’s Warranty of Title ................................................................................................... 32
12.02 Partial Utilization ........................................................................................................................ 32
12.03 Final Inspection ........................................................................................................................... 32
12.04 Final Acceptance ......................................................................................................................... 33
Article 13 – Suspension of Work .................................................................................................................... 33
13.01 City May Suspend Work ............................................................................................................ 33
Article 14 – Miscellaneous .............................................................................................................................. 34
14.01 Giving Notice .............................................................................................................................. 34
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
14.02 Computation of Times ................................................................................................................ 34
14.03 Cumulative Remedies ................................................................................................................. 34
14.04 Survival of Obligations ............................................................................................................... 35
14.05 Headings ...................................................................................................................................... 35
00 73 10- 1
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 1 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
ARTICLE 1 – DEFINITIONS AND TERMINOLOGY
1.01 Defined Terms
A. Wherever used in these General Conditions or in other Contract Documents, the terms listed
below have the meanings indicated which are applicable to both the singular and plural thereof,
and words denoting gender shall include the masculine, feminine and neuter. Said terms are
generally capitalized or written in italics, but not always. When used in a context consistent with
the definition of a listed-defined term, the term shall have a meaning as defined below whether
capitalized or italicized or otherwise. In addition to terms specifically defined, terms with initial
capital letters in the Contract Documents include references to identified articles and paragraphs,
and the titles of other documents or forms.
1. Agreement - The written instrument which is evidence of the agreement between Developer
and Contractor covering the Work
2. Asbestos—Any material that contains more than one percent asbestos and is friable or is
releasing asbestos fibers into the air above current action levels established by the United
States Occupational Safety and Health Administration.
3. Business Day – A business day is defined as a day that the City conducts normal business,
generally Monday through Friday, except for federal or state holidays observed by the City.
4. Buzzsaw – City’s on-line, electronic document management and collaboration system.
5. Calendar Day – A day consisting of 24 hours measured from midnight to the next midnight.
6. City— The City of Fort Worth, Texas, a Texas home-rule municipal corporation, acting by,
its governing body through its City Manager, his designee, or agents authorized pursuant to
its duly authorized charter on his behalf.
7. Community Facilities Agreement (CFA) -–A Contract between the Developer and the City
for the Construction of one or more following public facilities within the City public right-of-
way or easement: Water, Sanitary Sewer, Street, Storm Drain, Street Light, and Street Signs.
A CFA may include private facilities within the right-of-way dedicated as private right-of-
way or easement on a recorded plat.
8. Contract—The entire and integrated written document incorporating the Contract
Documents between the Developer, Contractor, and/or City concerning the Work. The
Contract supersedes prior negotiations, representations, or agreements, whether written or
oral.
9. Contract Documents—Those items that make up the contract and which must include the
Agreement, and it’s attachments such as standard construction specifications, standard City
Conditions, other general conditions of the Developer, including:
a. An Agreement
00 73 10- 2
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 2 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
b. Attachments to the Agreement
i. Bid Form
ii. Vendor Compliance with State Law Non-Resident Bidder
iii. Prequalification Statement
c. Current Prevailing Wage Rates Table (if required by City)
d. Insurance Accord Form
e. Payment Bond
f. Performance Bond
g. Maintenance Bond
h. Power of Attorney for Bonds
i. Workers Compensation Affidavit
j. MWBE Commitment Form( If required by City)
k. General Conditions
l. Supplementary Conditions
m. The Standard City Conditions
n. Specifications specifically made part of the Contract Documents by attachment, if
not attached, as incorporated by reference and described in the Table of Contents of
the Project’s Contract Documents
o. Drawings
p. Documentation submitted by contractor prior to Notice of Award.
q. The following which may be delivered or issued after the effective date if the
Agreement and, if issued become an incorporated part of the Contract Documents
i. Notice to Proceed
ii. Field Orders
iii. Change Orders
iv. Letters of Final Acceptance
r. Approved Submittals, other Contractor submittals, and the reports and drawings of
subsurface and physical conditions are not Contract Documents.
10. Contractor—The individual or entity with whom Developer has entered into the Agreement.
11. Day or day – A day, unless otherwise defined, shall mean a Calendar Day.
12. Developer – An individual or entity that desires to make certain improvements within the
City of Fort Worth
13. Drawings—That part of the Contract Documents prepared or approved by Engineer which
graphically shows the scope, extent, and character of the Work to be performed by
Contractor. Submittals are not Drawings as so defined.
14. Engineer—The licensed professional engineer or engineering firm registered in the State of
Texas performing professional services for the Developer.
15. Final Acceptance – The written notice given by the City to the Developer and/or Contractor
that the Work specified in the Contract Documents has been completed to the satisfaction of
the City.
00 73 10- 3
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 3 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
16. Final Inspection – Inspection carried out by the City to verify that the Contractor has
completed the Work, and each and every part or appurtenance thereof, fully, entirely, and in
conformance with the Contract Documents.
17. General Requirements—A part of the Contract Documents between the Developer and a
Contractor.
18. Laws and Regulations—Any and all applicable laws, rules, regulations, ordinances, codes,
and orders of any and all governmental bodies, agencies, authorities, and courts having
jurisdiction.
19. Liens—Charges, security interests, or encumbrances upon Project funds, real property, or
personal property.
20. Milestone—A principal event specified in the Contract Documents relating to an
intermediate Contract Time prior to Final Acceptance of the Work.
21. Non-Participating Change Order—A document, which is prepared for and reviewed by the
City, which is signed by Contractor, and Developer, and authorizes an addition, deletion, or
revision in the Work or an adjustment in the Contract Price or the Contract Time, issued on
or after the Effective Date of the Agreement.
22. Participating Change Order—A document, which is prepared for and approved by the City,
which is signed by Contractor, Developer, and City and authorizes an addition, deletion, or
revision in the Work or an adjustment in the Contract Price or the Contract Time, issued on
or after the Effective Date of the Agreement.
23. Plans – See definition of Drawings.
24. Project Schedule—A schedule, prepared and maintained by Contractor, in accordance with
the General Requirements, describing the sequence and duration of the activities comprising
the Contractor’s plan to accomplish the Work within the Contract Time.
25. Project—The Work to be performed under the Contract Documents.
26. Project Representative—The authorized representative of the City who will be assigned to
the Site.
27. Public Meeting – An announced meeting conducted by the Developer to facilitate public
participation and to assist the public in gaining an informed view of the Project.
28. Regular Working Hours – Hours beginning at 7:00 a.m. and ending at 6:00 p.m., Monday
thru Friday (excluding legal holidays).
29. Samples—Physical examples of materials, equipment, or workmanship that are
representative of some portion of the Work and which establish the standards by which such
portion of the Work will be judged.
00 73 10- 4
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 4 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
30. Schedule of Submittals—A schedule, prepared and maintained by Contractor, of required
submittals and the time requirements to support scheduled performance of related
construction activities.
31. Site—Lands or areas indicated in the Contract Documents as being furnished by City or
Developer upon which the Work is to be performed, including rights-of-way, permits, and
easements for access thereto, and such other lands furnished by City or Developer which are
designated for the use of Contractor.
32. Specifications—That part of the Contract Documents consisting of written requirements for
materials, equipment, systems, standards and workmanship as applied to the Work, and
certain administrative requirements and procedural matters applicable thereto.
Specifications may be specifically made a part of the Contract Documents by attachment or,
if not attached, may be incorporated by reference as indicated in the Table of Contents
(Division 00 00 00) of each Project.
33. Standard City Conditions – That part of the Contract Documents setting forth requirements
of the City.
34. Subcontractor—An individual or entity having a direct contract with Contractor or with any
other Subcontractor for the performance of a part of the Work at the Site.
35. Submittals—All drawings, diagrams, illustrations, schedules, and other data or information
which are specifically prepared or assembled by or for Contractor and submitted by
Contractor to illustrate some portion of the Work.
36. Superintendent – The representative of the Contractor who is available at all times and able
to receive instructions from the City and/or Developer and to act for the Contractor.
37. Supplementary Conditions—That part of the Contract Documents which amends or
supplements the General Conditions.
38. Supplier—A manufacturer, fabricator, supplier, distributor, materialman, or vendor having
a direct contract with Contractor or with any Subcontractor to furnish materials or
equipment to be incorporated in the Work by Contractor or Subcontractor.
39. Underground Facilities—All underground pipelines, conduits, ducts, cables, wires,
manholes, vaults, tanks, tunnels, or other such facilities or attachments, and any
encasements containing such facilities, including but not limited to, those that convey
electricity, gases, steam, liquid petroleum products, telephone or other communications,
cable television, water, wastewater, storm water, other liquids or chemicals, or traffic or
other control systems.
40. Weekend Working Hours – Hours beginning at 9:00 a.m. and ending at 5:00 p.m., Saturday,
Sunday or legal holiday, as approved in advance by the City.
00 73 10- 5
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 5 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
41. Work—The entire construction or the various separately identifiable parts thereof required
to be provided under the Contract Documents. Work includes and is the result of performing
or providing all labor, services, and documentation necessary to produce such construction
including any Participating Change Order, Non-Participating Change Order, or Field
Order, and furnishing, installing, and incorporating all materials and equipment into such
construction, all as required by the Contract Documents.
42. Working Day – A working day is defined as a day, not including Saturdays, Sundays, or
legal holidays authorized by the City for contract purposes, in which weather or other
conditions not under the control of the Contractor will permit the performance of the
principal unit of work underway for a continuous period of not less than 7 hours between 7
a.m. and 6 p.m.
1.02 Terminology
A. The words and terms discussed in Paragraph 1.02.B through D are not defined but, when used in
the Bidding Requirements or Contract Documents, have the indicated meaning.
B. Defective:
1. The word “defective,” when modifying the word “Work,” refers to Work that is
unsatisfactory, faulty, or deficient in that it:
a. does not conform to the Contract Documents; or
b. does not meet the requirements of any applicable inspection, reference standard, test, or
approval referred to in the Contract Documents; or
c. has been damaged prior to City’s written acceptance.
C. Furnish, Install, Perform, Provide:
1. The word “Furnish” or the word “Install” or the word “Perform” or the word “Provide” or
the word “Supply,” or any combination or similar directive or usage thereof, shall mean
furnishing and incorporating in the Work including all necessary labor, materials, equipment,
and everything necessary to perform the Work indicated, unless specifically limited in the
context used.
D. Unless stated otherwise in the Contract Documents, words or phrases that have a well-known
technical or construction industry or trade meaning are used in the Contract Documents in
accordance with such recognized meaning.
00 73 10- 6
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 6 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
ARTICLE 2 – PRELIMINARY MATTERS
2.01 Before Starting Construction
Baseline Schedules: Submit to City in accordance with the Contract Documents, and prior to starting
the Work. New schedules will be submitted to City when Participating Change Orders or Non-
Participating Change Orders occur.
2.02 Preconstruction Conference
Before any Work at the Site is started, the Contractor shall attend a Preconstruction Conference as
specified in the Contract Documents.
2.03 Public Meeting
Contractor may not mobilize any equipment, materials or resources to the Site prior to Contractor
attending the Public Meeting as scheduled by the City.
ARTICLE 3 – CONTRACT DOCUMENTS AND AMENDING
3.01 Reference Standards
A. Standards, Specifications, Codes, Laws, and Regulations
1. Reference to standards, specifications, manuals, or codes of any technical society,
organization, or association, or to Laws or Regulations, whether such reference be specific or
by implication, shall mean the standard, specification, manual, code, or Laws or Regulations
in effect at the time of opening of Bids (or on the Effective Date of the Agreement if there
were no Bids), except as may be otherwise specifically stated in the Contract Documents.
2. No provision or instruction shall be effective to assign to City, or any of its officers,
directors, members, partners, employees, agents, consultants, or subcontractors, any duty or
authority to supervise or direct the performance of the Work or any duty or authority to
undertake responsibility inconsistent with the provisions of the Contract Documents.
3.02 Amending and Supplementing Contract Documents
A. The Contract Documents may be amended to provide for additions, deletions, and revisions in
the Work or to modify the terms and conditions thereof by a Participating Change Order or a
Non-Participating Change Order.
B. The requirements of the Contract Documents may be supplemented, and minor variations and
deviations in the Work not involving a change in Contract Price or Contract Time, may be
authorized, by one or more of the following ways:
1. A Field Order;
00 73 10- 7
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 7 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
1. City’s or Engineer’s review of a Submittal (subject to the provisions of Paragraph 5.16.C); or
2. City’s written interpretation or clarification.
ARTICLE 4 – BONDS AND INSURANCE
4.01 Licensed Sureties and Insurers
All bonds and insurance required by the Contract Documents to be purchased and maintained by
Contractor shall be obtained from surety or insurance companies that are duly licensed or authorized
in the State of Texas to issue bonds or insurance policies for the limits and coverage so required.
Such surety and insurance companies shall also meet such additional requirements and qualifications
as may be provided Section 4.04.
4.02 Performance, Payment, and Maintenance Bonds
A. Contractor shall furnish performance and payment bonds in the name of Developer and City, in
accordance with Texas Government Code Chapter 2253 or successor statute, each in an amount
equal to the Contract Price as security for the faithful performance and payment of all of
Contractor’s obligations under the Contract Documents.
B. Contractor shall furnish maintenance bonds in the name of Developer and City in an amount
equal to the Contract Price as security to protect the City against any defects in any portion of the
Work described in the Contract Documents. Maintenance bonds shall remain in effect for two
(2) years after the date of Final Acceptance by the City.
C. All bonds shall be in the form prescribed by the Contract Documents except as provided
otherwise by Laws or Regulations, and shall be executed by such sureties as are named in the list
of “Companies Holding Certificates of Authority as Acceptable Sureties on Federal Bonds and
as Acceptable Reinsuring Companies” as published in Circular 570 (amended) by the Financial
Management Service, Surety Bond Branch, U.S. Department of the Treasury. All bonds signed
by an agent or attorney-in-fact must be accompanied by a sealed and dated power of attorney
which shall show that it is effective on the date the agent or attorney-in-fact signed each bond.
D. If the surety on any bond furnished by Contractor is declared bankrupt or becomes insolvent or
its right to do business is terminated in the State of Texas or it ceases to meet the requirements of
Paragraph 4.02.C, Contractor shall promptly notify City and shall, within 30 days after the event
giving rise to such notification, provide another bond and surety, both of which shall comply
with the requirements of Paragraphs 4.01 and 4.02.C.
4.03 Certificates of Insurance
Contractor shall deliver to Developer and City, with copies to each additional insured and loss payee
identified in these Standard City Conditions certificates of insurance (and other evidence of
insurance requested by City or any other additional insured) which Contractor is required to
purchase and maintain.
00 73 10- 8
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 8 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
1. The certificate of insurance shall document the City, an as “Additional Insured” on all
liability policies.
2. The Contractor’s general liability insurance shall include a, “per project” or “per location”,
endorsement, which shall be identified in the certificate of insurance provided to the City.
3. The certificate shall be signed by an agent authorized to bind coverage on behalf of the
insured, be complete in its entirety, and show complete insurance carrier names as listed in
the current A.M. Best Property & Casualty Guide
4. The insurers for all policies must be licensed and/or approved to do business in the State of
Texas. Except for workers’ compensation, all insurers must have a minimum rating of A-:
VII in the current A. M. Best Key Rating Guide or have reasonably equivalent financial
strength and solvency to the satisfaction of Risk Management. If the rating is below that
required, written approval of City is required.
5. All applicable policies shall include a Waiver of Subrogation (Rights of Recovery) in favor
of the City. In addition, the Contractor agrees to waive all rights of subrogation against the
Engineer (if applicable), and each additional insured identified in these Standard City
Conditions. Failure of the City to demand such certificates or other evidence of full
compliance with the insurance requirements or failure of the City to identify a deficiency
from evidence that is provided shall not be construed as a waiver of Contractor’s obligation
to maintain such lines of insurance coverage.
6. If insurance policies are not written for specified coverage limits, an Umbrella or Excess
Liability insurance for any differences is required. Excess Liability shall follow form of the
primary coverage.
7. Unless otherwise stated, all required insurance shall be written on the “occurrence basis”. If
coverage is underwritten on a claims-made basis, the retroactive date shall be coincident with
or prior to the date of the effective date of the agreement and the certificate of insurance shall
state that the coverage is claims-made and the retroactive date. The insurance coverage shall
be maintained for the duration of the Contract and for three (3) years following Final
Acceptance provided under the Contract Documents or for the warranty period, whichever is
longer. An annual certificate of insurance submitted to the City shall evidence such
insurance coverage.
8. Policies shall have no exclusions by endorsements, which, neither nullify or amend, the
required lines of coverage, nor decrease the limits of said coverage unless such endorsements
are approved in writing by the City. In the event a Contract has been bid or executed and the
exclusions are determined to be unacceptable or the City desires additional insurance
coverage, and the City desires the contractor/engineer to obtain such coverage, the contract
price shall be adjusted by the cost of the premium for such additional coverage plus 10%.
9. Any self-insured retention (SIR), in excess of $25,000.00, affecting required insurance
coverage shall be approved by the City in regards to asset value and stockholders' equity. In
00 73 10- 9
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 9 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
lieu of traditional insurance, alternative coverage maintained through insurance pools or risk
retention groups, must also be approved by City.
10. Any deductible in excess of $5,000.00, for any policy that does not provide coverage on a
first-dollar basis, must be acceptable to and approved by the City.
11. City, at its sole discretion, reserves the right to review the insurance requirements and to
make reasonable adjustments to insurance coverage’s and their limits when deemed
necessary and prudent by the City based upon changes in statutory law, court decision or the
claims history of the industry as well as of the contracting party to the City. The City shall
be required to provide prior notice of 90 days, and the insurance adjustments shall be
incorporated into the Work by Change Order.
12. City shall be entitled, upon written request and without expense, to receive copies of policies
and endorsements thereto and may make any reasonable requests for deletion or revision or
modifications of particular policy terms, conditions, limitations, or exclusions necessary to
conform the policy and endorsements to the requirements of the Contract. Deletions,
revisions, or modifications shall not be required where policy provisions are established by
law or regulations binding upon either party or the underwriter on any such policies.
13. City shall not be responsible for the direct payment of insurance premium costs for
Contractor’s insurance.
4.04 Contractor’s Insurance
A. Workers Compensation and Employers’ Liability. Contractor shall purchase and maintain such
insurance coverage with limits consistent with statutory benefits outlined in the Texas Workers’
Compensation Act (Texas Labor Code, Ch. 406, as amended), and minimum limits for
Employers’ Liability as is appropriate for the Work being performed and as will provide
protection from claims set forth below which may arise out of or result from Contractor’s
performance of the Work and Contractor’s other obligations under the Contract Documents,
whether it is to be performed by Contractor, any Subcontractor or Supplier, or by anyone directly
or indirectly employed by any of them to perform any of the Work, or by anyone for whose acts
any of them may be liable:
1. claims under workers’ compensation, disability benefits, and other similar employee benefit
acts;
2. claims for damages because of bodily injury, occupational sickness or disease, or death of
Contractor’s employees.
3. The limits of liability for the insurance shall provide the following coverages for not less
than the following amounts or greater where required by Laws and Regulations
a. Statutory limits
b. Employer's liability
00 73 10- 10
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 10 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
1) $100,000 each accident/occurrence
2) $100,000 Disease - each employee
3) $500,000 Disease - policy limit
B. Commercial General Liability. Coverage shall include but not be limited to covering liability
(bodily injury or property damage) arising from: premises/operations, independent contractors,
products/completed operations, personal injury, and liability under an insured contract. Insurance
shall be provided on an occurrence basis, and as comprehensive as the current Insurance
Services Office (ISO) policy. This insurance shall apply as primary insurance with respect to
any other insurance or self-insurance programs afforded to the City. The Commercial General
Liability policy, shall have no exclusions by endorsements that would alter of nullify
premises/operations, products/completed operations, contractual, personal injury, or advertising
injury, which are normally contained with the policy, unless the City approves such exclusions
in writing.
1. For construction projects that present a substantial completed operation exposure, the City
may require the contractor to maintain completed operations coverage for a minimum of no
less than three (3) years following the completion of the project
2. Contractor's Liability Insurance under this Section which shall be on a per project basis
covering the Contractor with minimum limits of:
a. $1,000,000 each occurrence
b. $2,000,000 aggregate limit
3. The policy must have an endorsement (Amendment – Aggregate Limits of Insurance)
making the General Aggregate Limits apply separately to each job site.
4. The Commercial General Liability Insurance policies shall provide “X”, “C”, and “U”
coverage’s. Verification of such coverage must be shown in the Remarks Article of the
Certificate of Insurance.
C. Automobile Liability. A commercial business auto policy shall provide coverage on “any auto”,
defined as autos owned, hired and non-owned and provide indemnity for claims for damages
because bodily injury or death of any person and or property damage arising out of the work,
maintenance or use of any motor vehicle by the Contractor, any Subcontractor or Supplier, or by
anyone directly or indirectly employed by any of them to perform any of the Work, or by anyone
for whose acts any of them may be liable.
1. Automobile Liability, Contractor’s Liability Insurance under this Section, which shall be in
an amount not less than the following amounts:
a. Automobile Liability - a commercial business policy shall provide coverage on "Any
Auto", defined as autos owned, hired and non-owned.
00 73 10- 11
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 11 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
1) $1,000,000 each accident on a combined single limit basis. Split limits are
acceptable if limits are at least:
2) $250,000 Bodily Injury per person
3) $500,000 Bodily Injury per accident /
4) $100,000 Property Damage
D. Railroad Protective Liability. If any of the work or any warranty work is within the limits of
railroad right-of-way, the Contractor shall comply with the following requirements:
1. The Contractor’s construction activities will require its employees, agents, subcontractors,
equipment, and material deliveries to cross railroad properties and tracks owned and
operated by: ____________________________________________________________
Write the name of the railroad company. (If none, then write none)
2. The Contractor shall conduct its operations on railroad properties in such a manner as not to
interfere with, hinder, or obstruct the railroad company in any manner whatsoever in the use
or operation of its/their trains or other property. Such operations on railroad properties may
require that Contractor to execute a “Right of Entry Agreement” with the particular railroad
company or companies involved, and to this end the Contractor should satisfy itself as to the
requirements of each railroad company and be prepared to execute the right-of-entry (if any)
required by a railroad company. The requirements specified herein likewise relate to the
Contractor’s use of private and/or construction access roads crossing said railroad company’s
properties.
3. The Contractual Liability coverage required by Paragraph 5.04D of the General Conditions
shall provide coverage for not less than the following amounts, issued by companies
satisfactory to the City and to the Railroad Company for a term that continues for so long as
the Contractor’s operations and work cross, occupy, or touch railroad property:
a. General Aggregate: _____________________________________
Enter limits provided by Railroad Company (If none, write none)
b. Each Occurrence: : _____________________________________
Enter limits provided by Railroad Company (If none, write none)
4. With respect to the above outlined insurance requirements, the following shall govern:
a. Where a single railroad company is involved, the Contractor shall provide one insurance
policy in the name of the railroad company. However, if more than one grade separation
or at-grade crossing is affected by the Project at entirely separate locations on the line or
lines of the same railroad company, separate coverage may be required, each in the
amount stated above.
b. Where more than one railroad company is operating on the same right-of-way or where
several railroad companies are involved and operated on their own separate rights-of-
None
None
None
00 73 10- 12
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 12 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
way, the Contractor may be required to provide separate insurance policies in the name
of each railroad company.
c. If, in addition to a grade separation or an at-grade crossing, other work or activity is
proposed on a railroad company’s right-of-way at a location entirely separate from the
grade separation or at-grade crossing, insurance coverage for this work must be included
in the policy covering the grade separation.
d. If no grade separation is involved but other work is proposed on a railroad company’s
right-of-way, all such other work may be covered in a single policy for that railroad, even
though the work may be at two or more separate locations.
5. No work or activities on a railroad company’s property to be performed by the Contractor
shall be commenced until the Contractor has furnished the City with an original policy or
policies of the insurance for each railroad company named, as required above. All such
insurance must be approved by the City and each affected Railroad Company prior to the
Contractor’s beginning work.
6. The insurance specified above must be carried until all Work to be performed on the railroad
right-of-way has been completed and the grade crossing, if any, is no longer used by the
Contractor. In addition, insurance must be carried during all maintenance and/or repair work
performed in the railroad right-of-way. Such insurance must name the railroad company as
the insured, together with any tenant or lessee of the railroad company operating over tracks
involved in the Project.
E. Notification of Policy Cancellation: Contractor shall immediately notify City upon cancellation
or other loss of insurance coverage. Contractor shall stop work until replacement insurance has
been procured. There shall be no time credit for days not worked pursuant to this section.
4.05 Acceptance of Bonds and Insurance; Option to Replace
If City has any objection to the coverage afforded by or other provisions of the bonds or insurance
required to be purchased and maintained by the Contractor in accordance with Article 5 on the basis
of non-conformance with the Contract Documents, the Developer and City shall so notify the
Contractor in writing within 10 Business Days after receipt of the certificates (or other evidence
requested). Contractor shall provide to the City such additional information in respect of insurance
provided as the Developer or City may reasonably request. If Contractor does not purchase or
maintain all of the bonds and insurance required by the Contract Documents, the Developer or City
shall notify the Contractor in writing of such failure prior to the start of the Work, or of such failure
to maintain prior to any change in the required coverage.
ARTICLE 5 – CONTRACTOR’S RESPONSIBILITIES
5.01 Supervision and Superintendent
A. Contractor shall supervise, inspect, and direct the Work competently and efficiently, devoting
such attention thereto and applying such skills and expertise as may be necessary to perform the
00 73 10- 13
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 13 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
Work in accordance with the Contract Documents. Contractor shall be solely responsible for the
means, methods, techniques, sequences, and procedures of construction.
B. At all times during the progress of the Work, Contractor shall assign a competent, English-
speaking, Superintendent who shall not be replaced without written notice to City. The
Superintendent will be Contractor’s representative at the Site and shall have authority to act on
behalf of Contractor. All communication given to or received from the Superintendent shall be
binding on Contractor.
C. Contractor shall notify the City 24 hours prior to moving areas during the sequence of
construction.
5.02 Labor; Working Hours
A. Contractor shall provide competent, suitably qualified personnel to perform construction as
required by the Contract Documents. Contractor shall at all times maintain good discipline and
order at the Site.
B. Except as otherwise required for the safety or protection of persons or the Work or property at
the Site or adjacent thereto, and except as otherwise stated in the Contract Documents, all Work
at the Site shall be performed during Regular Working Hours. Contractor will not permit the
performance of Work beyond Regular Working Hours or for Weekend Working Hours without
City’s written consent (which will not be unreasonably withheld). Written request (by letter or
electronic communication) to perform Work:
1. for beyond Regular Working Hours request must be made by noon at least two (2) Business
Days prior
2. for Weekend Working Hours request must be made by noon of the preceding Thursday
3. for legal holidays request must be made by noon two Business Days prior to the legal
holiday.
5.03 Services, Materials, and Equipment
A. Unless otherwise specified in the Contract Documents, Contractor shall provide and assume full
responsibility for all services, materials, equipment, labor, transportation, construction
equipment and machinery, tools, appliances, fuel, power, light, heat, telephone, water, sanitary
facilities, temporary facilities, and all other facilities and incidentals necessary for the
performance, Contractor required testing, start-up, and completion of the Work.
B. All materials and equipment incorporated into the Work shall be as specified or, if not specified,
shall be of good quality and new, except as otherwise provided in the Contract Documents. All
special warranties and guarantees required by the Specifications shall expressly run to the benefit
of City. If required by City, Contractor shall furnish satisfactory evidence (including reports of
required tests) as to the source, kind, and quality of materials and equipment.
00 73 10- 14
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 14 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
C. All materials and equipment to be incorporated into the Work shall be stored, applied, installed,
connected, erected, protected, used, cleaned, and conditioned in accordance with instructions of
the applicable Supplier, except as otherwise may be provided in the Contract Documents.
5.04 Project Schedule
A. Contractor shall adhere to the Project Schedule established in accordance with Paragraph 2.01
and the General Requirements as it may be adjusted from time to time as provided below.
1. Contractor shall submit to City for acceptance (to the extent indicated in Paragraph 2.01 and
the General Requirements) proposed adjustments in the Project Schedule.
2. Proposed adjustments in the Project Schedule that will change the Contract Time shall be
submitted in accordance with the requirements of Article 9. Adjustments in Contract Time
for projects with City participation shall be made by participating change orders.
5.05 Substitutes and “Or-Equals”
A. Whenever an item of material or equipment is specified or described in the Contract Documents
by using the name of a proprietary item or the name of a particular Supplier, the specification or
description is intended to establish the type, function, appearance, and quality required. Unless
the specification or description contains or is followed by words reading that no like, equivalent,
or “or-equal” item or no substitution is permitted, other items of material or equipment of other
Suppliers may be submitted to City for review under the circumstances described below.
1. “Or-Equal” Items: If in City’s sole discretion an item of material or equipment proposed by
Contractor is functionally equal to that named and sufficiently similar so that no change in
related Work will be required, it may be considered by City as an “or-equal” item, in which
case review and approval of the proposed item may, in City’s sole discretion, be
accomplished without compliance with some or all of the requirements for approval of
proposed substitute items. For the purposes of this Paragraph 5.05.A.1, a proposed item of
material or equipment will be considered functionally equal to an item so named if:
a. City determines that:
1) it is at least equal in materials of construction, quality, durability, appearance,
strength, and design characteristics;
2) it will reliably perform at least equally well the function and achieve the results
imposed by the design concept of the completed Project as a functioning whole; and
3) it has a proven record of performance and availability of responsive service; and
b. Contractor certifies that, if approved and incorporated into the Work:
1) there will be no increase in cost to the City or increase in Contract Time; and
00 73 10- 15
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 15 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
2) it will conform substantially to the detailed requirements of the item named in the
Contract Documents.
2. Substitute Items:
a. If in City’s sole discretion an item of material or equipment proposed by Contractor does
not qualify as an “or-equal” item under Paragraph 5.05.A.1, it may be submitted as a
proposed substitute item.
b. Contractor shall submit sufficient information as provided below to allow City to
determine if the item of material or equipment proposed is essentially equivalent to that
named and an acceptable substitute therefor. Requests for review of proposed substitute
items of material or equipment will not be accepted by City from anyone other than
Contractor.
c. Contractor shall make written application to City for review of a proposed substitute item
of material or equipment that Contractor seeks to furnish or use. The application shall
comply with Section 01 25 00 and:
1) shall certify that the proposed substitute item will:
i. perform adequately the functions and achieve the results called for by the general
design;
ii. be similar in substance to that specified;
iii. be suited to the same use as that specified; and
2) will state:
i. the extent, if any, to which the use of the proposed substitute item will prejudice
Contractor’s achievement of final completion on time;
ii. whether use of the proposed substitute item in the Work will require a change in
any of the Contract Documents (or in the provisions of any other direct contract
with City for other work on the Project) to adapt the design to the proposed
substitute item;
iii. whether incorporation or use of the proposed substitute item in connection with
the Work is subject to payment of any license fee or royalty; and
3) will identify:
i. all variations of the proposed substitute item from that specified;
ii. available engineering, sales, maintenance, repair, and replacement services; and
00 73 10- 16
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 16 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
4) shall contain an itemized estimate of all costs or credits that will result directly or
indirectly from use of such substitute item, including costs of redesign and Damage
Claims of other contractors affected by any resulting change.
B. Substitute Construction Methods or Procedures: If a specific means, method, technique,
sequence, or procedure of construction is expressly required by the Contract Documents,
Contractor may furnish or utilize a substitute means, method, technique, sequence, or procedure
of construction approved by City. Contractor shall submit sufficient information to allow City, in
City’s sole discretion, to determine that the substitute proposed is equivalent to that expressly
called for by the Contract Documents. Contractor shall make written application to City for
review in the same manner as those provided in Paragraph 5.05.A.2.
C. City’s Evaluation: City will be allowed a reasonable time within which to evaluate each
proposal or submittal made pursuant to Paragraphs 5.05.A and 5.05.B. City may require
Contractor to furnish additional data about the proposed substitute. City will be the sole judge of
acceptability. No “or-equal” or substitute will be ordered, installed or utilized until City’s review
is complete, which will be evidenced by a Change Order in the case of a substitute and an
accepted Submittal for an “or-equal.” City will advise Contractor in writing of its determination.
D. Special Guarantee: City may require Contractor to furnish at Contractor’s expense a special
performance guarantee, warranty, or other surety with respect to any substitute. Contractor shall
indemnify and hold harmless City and anyone directly or indirectly employed by them from and
against any and all claims, damages, losses and expenses (including attorneys fees) arising out
of the use of substituted materials or equipment.
E. City’s Cost Reimbursement: City will record City’s costs in evaluating a substitute proposed or
submitted by Contractor pursuant to Paragraphs 5.05.A.2 and 5.05.B. Whether or not City
approves a substitute so proposed or submitted by Contractor, Contractor may be required to
reimburse City for evaluating each such proposed substitute. Contractor may also be required to
reimburse City for the charges for making changes in the Contract Documents.
F. Contractor’s Expense: Contractor shall provide all data in support of any proposed substitute or
“or-equal” at Contractor’s expense.
G. Substitute Reimbursement: Costs (savings or charges) attributable to acceptance of a substitute
shall be incorporated to the Contract by Participating Change Order.
5.06 Pre-Qualification of Bidders (Prime Contractors and Subcontractors)
A. The Contractor and any subcontractors are required to be prequalified for the work types
requiring pre-qualification
5.07 Concerning Subcontractors, Suppliers, and Others
A. Minority and Women Owned Business Enterprise Compliance:
00 73 10- 17
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 17 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
Required for this Contract.
(Check this box if there is any City Participation)
Not Required for this Contract.
It is City policy to ensure the full and equitable participation by Minority and Women Business
Enterprises (MWBE) in the procurement of goods and services on a contractual basis. If the
Contract Documents provide for a MWBE goal, Contractor is required to comply with the intent
of the City’s MWBE Ordinance (as amended) by the following:
1. Contractor shall, upon request by City, provide complete and accurate information regarding
actual work performed by a MWBE on the Contract and payment therefor.
2. Contractor will not make additions, deletions, or substitutions of accepted MWBE without
written consent of the City. Any unjustified change or deletion shall be a material breach of
Contract and may result in debarment in accordance with the procedures outlined in the
Ordinance.
3. Contractor shall, upon request by City, allow an audit and/or examination of any books,
records, or files in the possession of the Contractor that will substantiate the actual work
performed by an MWBE. Material misrepresentation of any nature will be grounds for
termination of the Contract. Any such misrepresentation may be grounds for disqualification
of Contractor to bid on future contracts with the City for a period of not less than three years.
B. Contractor shall be fully responsible to City for all acts and omissions of the Subcontractors,
Suppliers, and other individuals or entities performing or furnishing any of the Work just as
Contractor is responsible for Contractor’s own acts and omissions. Nothing in the Contract
Documents:
1. shall create for the benefit of any such Subcontractor, Supplier, or other individual or entity
any contractual relationship between City and any such Subcontractor, Supplier or other
individual or entity; nor
2. shall create any obligation on the part of City to pay or to see to the payment of any moneys
due any such Subcontractor, Supplier, or other individual or entity except as may otherwise
be required by Laws and Regulations.
C. Contractor shall be solely responsible for scheduling and coordinating the Work of
Subcontractors, Suppliers, and other individuals or entities performing or furnishing any of the
Work under a direct or indirect contract with Contractor.
D. All Subcontractors, Suppliers, and such other individuals or entities performing or furnishing
any of the Work shall communicate with City through Contractor.
E. All Work performed for Contractor by a Subcontractor or Supplier will be pursuant to an
appropriate agreement between Contractor and the Subcontractor or Supplier which specifically
binds the Subcontractor or Supplier to the applicable terms and conditions of these Contract
00 73 10- 18
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 18 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
Documents, Contractor shall provide City contract numbers and reference numbers to the
Subcontractors and/or Suppliers.
5.08 Wage Rates
Required for this Contract.
Not Required for this Contract.
A. Duty to pay Prevailing Wage Rates. The Contractor shall comply with all requirements of
Chapter 2258, Texas Government Code (as amended), including the payment of not less than the
rates determined by the City Council of the City of Fort Worth to be the prevailing wage rates in
accordance with Chapter 2258. Such prevailing wage rates are included in these Contract
Documents.
B. Penalty for Violation. A Contractor or any Subcontractor who does not pay the prevailing wage
shall, upon demand made by the City, pay to the City $60 for each worker employed for each
calendar day or part of the day that the worker is paid less than the prevailing wage rates
stipulated in these contract documents. This penalty shall be retained by the City to offset its
administrative costs, pursuant to Texas Government Code 2258.023.
C. Complaints of Violations and City Determination of Good Cause. On receipt of information,
including a complaint by a worker, concerning an alleged violation of 2258.023, Texas
Government Code, by a Contractor or Subcontractor, the City shall make an initial
determination, before the 31st day after the date the City receives the information, as to whether
good cause exists to believe that the violation occurred. The City shall notify in writing the
Contractor or Subcontractor and any affected worker of its initial determination. Upon the
City’s determination that there is good cause to believe the Contractor or Subcontractor has
violated Chapter 2258, the City shall retain the full amounts claimed by the claimant or
claimants as the difference between wages paid and wages due under the prevailing wage rates,
such amounts being subtracted from successive progress payments pending a final determination
of the violation.
D. Arbitration Required if Violation Not Resolved. An issue relating to an alleged violation of
Section 2258.023, Texas Government Code, including a penalty owed to the City or an affected
worker, shall be submitted to binding arbitration in accordance with the Texas General
Arbitration Act (Article 224 et seq., Revised Statutes) if the Contractor or Subcontractor and any
affected worker does not resolve the issue by agreement before the 15th day after the date the
City makes its initial determination pursuant to Paragraph C above. If the persons required to
arbitrate under this section do not agree on an arbitrator before the 11th day after the date that
arbitration is required, a district court shall appoint an arbitrator on the petition of any of the
persons. The City is not a party in the arbitration. The decision and award of the arbitrator is
final and binding on all parties and may be enforced in any court of competent jurisdiction.
E. Records to be Maintained. The Contractor and each Subcontractor shall, for a period of three (3)
years following the date of acceptance of the work, maintain records that show (i) the name and
00 73 10- 19
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 19 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
occupation of each worker employed by the Contractor in the construction of the Work provided
for in this Contract; and (ii) the actual per diem wages paid to each worker. The records shall be
open at all reasonable hours for inspection by the City. The provisions of Paragraph 6.23, Right
to Audit, shall pertain to this inspection.
F. Progress Payments. With each progress payment or payroll period, whichever is less, the
Contractor shall submit an affidavit stating that the Contractor has complied with the
requirements of Chapter 2258, Texas Government Code.
G. Posting of Wage Rates. The Contractor shall post prevailing wage rates in a conspicuous place at
all times.
H. Subcontractor Compliance. The Contractor shall include in its subcontracts and/or shall
otherwise require all of its Subcontractors to comply with Paragraphs A through G above.
5.09 Patent Fees and Royalties
A. To the fullest extent permitted by Laws and Regulations, Contractor shall indemnify and hold
harmless City, from and against all claims, costs, losses, and damages (including but not limited
to all fees and charges of engineers, architects, attorneys, and other professionals and all court
or arbitration or other dispute resolution costs) arising out of or relating to any infringement of
patent rights or copyrights incident to the use in the performance of the Work or resulting from
the incorporation in the Work of any invention, design, process, product, or device not specified
in the Contract Documents.
5.10 Laws and Regulations
A. Contractor shall give all notices required by and shall comply with all Laws and Regulations
applicable to the performance of the Work. Except where otherwise expressly required by
applicable Laws and Regulations, the City shall not be responsible for monitoring Contractor’s
compliance with any Laws or Regulations.
B. If Contractor performs any Work knowing or having reason to know that it is contrary to Laws
or Regulations, Contractor shall bear all claims, costs, losses, and damages (including but not
limited to all fees and charges of engineers, architects, attorneys, and other professionals and all
court or arbitration or other dispute resolution costs) arising out of or relating to such Work.
However, it shall not be Contractor’s responsibility to make certain that the Specifications and
Drawings are in accordance with Laws and Regulations, but this shall not relieve Contractor of
Contractor’s obligations under Paragraph 3.01.
5.11 Use of Site and Other Areas
A. Limitation on Use of Site and Other Areas:
1. Contractor shall confine construction equipment, the storage of materials and equipment, and
the operations of workers to the Site and other areas permitted by Laws and Regulations, and
shall not unreasonably encumber the Site and other areas with construction equipment or
00 73 10- 20
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 20 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
other materials or equipment. Contractor shall assume full responsibility for any damage to
any such land or area, or to the owner or occupant thereof, or of any adjacent land or areas
resulting from the performance of the Work.
2. At any time when, in the judgment of the City, the Contractor has obstructed or closed or is
carrying on operations in a portion of a street, right-of-way, or easement greater than is
necessary for proper execution of the Work, the City may require the Contractor to finish the
section on which operations are in progress before work is commenced on any additional
area of the Site.
3. Should any Damage Claim be made by any such owner or occupant because of the
performance of the Work, Contractor shall promptly attempt to resolve the Damage Claim.
4. Pursuant to Paragraph 5.18, Contractor shall indemnify and hold harmless City, from and
against all claims, costs, losses, and damages arising out of or relating to any claim or
action, legal or equitable, brought by any such owner or occupant against City.
B. Removal of Debris During Performance of the Work: During the progress of the Work
Contractor shall keep the Site and other areas free from accumulations of waste materials,
rubbish, and other debris. Removal and disposal of such waste materials, rubbish, and other
debris shall conform to applicable Laws and Regulations.
C. Site Maintenance Cleaning: 24 hours after written notice is given to the Contractor that the
clean-up on the job site is proceeding in a manner unsatisfactory to the City or Developer, if the
Contractor fails to correct the unsatisfactory procedure, the City may take such direct action as
the City deems appropriate to correct the clean-up deficiencies cited to the Contractor in the
written notice (by letter or electronic communication), and shall be entitled to recover its cost in
doing so. The City may withhold Final Acceptance until clean-up is complete and cost are
recovered.
D. Final Site Cleaning: Prior to Final Acceptance of the Work Contractor shall clean the Site and
the Work and make it ready for utilization by City or adjacent property owner. At the completion
of the Work Contractor shall remove from the Site all tools, appliances, construction equipment
and machinery, and surplus materials and shall restore to original condition or better all property
disturbed by the Work.
E. Loading Structures: Contractor shall not load nor permit any part of any structure to be loaded
in any manner that will endanger the structure, nor shall Contractor subject any part of the Work
or adjacent property to stresses or pressures that will endanger it.
5.12 Record Documents
A. Contractor shall maintain in a safe place at the Site or in a place designated by the Contractor
and approved by the City, one (1) record copy of all Drawings, Specifications, Addenda, Change
Orders, Field Orders, and written interpretations and clarifications in good order and annotated
to show changes made during construction. These record documents together with all approved
00 73 10- 21
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 21 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
Samples and a counterpart of all accepted Submittals will be available to City for reference.
Upon completion of the Work, these record documents, any operation and maintenance manuals,
and Submittals will be delivered to City prior to Final Inspection. Contractor shall include
accurate locations for buried and imbedded items.
5.13 Safety and Protection
A. Contractor shall be solely responsible for initiating, maintaining and supervising all safety
precautions and programs in connection with the Work. Such responsibility does not relieve
Subcontractors of their responsibility for the safety of persons or property in the performance of
their work, nor for compliance with applicable safety Laws and Regulations. Contractor shall
take all necessary precautions for the safety of, and shall provide the necessary protection to
prevent damage, injury or loss to:
1. all persons on the Site or who may be affected by the Work;
2. all the Work and materials and equipment to be incorporated therein, whether in storage on
or off the Site; and
3. other property at the Site or adjacent thereto, including trees, shrubs, lawns, walks,
pavements, roadways, structures, utilities, and Underground Facilities not designated for
removal, relocation, or replacement in the course of construction.
B. Contractor shall comply with all applicable Laws and Regulations relating to the safety of
persons or property, or to the protection of persons or property from damage, injury, or loss; and
shall erect and maintain all necessary safeguards for such safety and protection. Contractor shall
notify owners of adjacent property and of Underground Facilities and other utility owners when
prosecution of the Work may affect them, and shall cooperate with them in the protection,
removal, relocation, and replacement of their property.
C. Contractor shall comply with the applicable requirements of City’s safety programs, if any.
D. Contractor shall inform City of the specific requirements of Contractor’s safety program, if any,
with which City’s employees and representatives must comply while at the Site.
E. All damage, injury, or loss to any property referred to in Paragraph 5.13.A.2 or 5.13.A.3 caused,
directly or indirectly, in whole or in part, by Contractor, any Subcontractor, Supplier, or any
other individual or entity directly or indirectly employed by any of them to perform any of the
Work, or anyone for whose acts any of them may be liable, shall be remedied by Contractor.
F. Contractor’s duties and responsibilities for safety and for protection of the Work shall continue
until such time as all the Work is completed and City has accepted the Work.
5.14 Safety Representative
Contractor shall inform City in writing of Contractor’s designated safety representative at the Site.
00 73 10- 22
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 22 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
5.15 Hazard Communication Programs
Contractor shall be responsible for coordinating any exchange of material safety data sheets or other
hazard communication information required to be made available to or exchanged between or
among employers in accordance with Laws or Regulations.
5.16 Submittals
A. Contractor shall submit required Submittals to City for review and acceptance. Each submittal
will be identified as required by City.
1. Submit number of copies specified in the General Requirements.
2. Data shown on the Submittals will be complete with respect to quantities, dimensions,
specified performance and design criteria, materials, and similar data to show City the
services, materials, and equipment Contractor proposes to provide and to enable City to
review the information for the limited purposes required by Paragraph 5.16.C.
3. Submittals submitted as herein provided by Contractor and reviewed by City for
conformance with the design concept shall be executed in conformity with the Contract
Documents unless otherwise required by City.
4. When Submittals are submitted for the purpose of showing the installation in greater detail,
their review shall not excuse Contractor from requirements shown on the Drawings and
Specifications.
5. For-Information-Only submittals upon which the City is not expected to conduct review or
take responsive action may be so identified in the Contract Documents.
6. Submit required number of Samples specified in the Specifications.
7. Clearly identify each Sample as to material, Supplier, pertinent data such as catalog numbers,
the use for which intended and other data as City may require to enable City to review the
submittal for the limited purposes required by Paragraph 5.16.C.
B. Where a Submittal is required by the Contract Documents or the Schedule of Submittals, any
related Work performed prior to City’s review and acceptance of the pertinent submittal will be
at the sole expense and responsibility of Contractor.
C. City’s Review:
1. City will provide timely review of required Submittals in accordance with the Schedule of
Submittals acceptable to City. City’s review and acceptance will be only to determine if the
items covered by the submittals will, after installation or incorporation in the Work, conform
to the information given in the Contract Documents and be compatible with the design
concept of the completed Project as a functioning whole as indicated by the Contract
Documents.
00 73 10- 23
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 23 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
2. City’s review and acceptance will not extend to means, methods, techniques, sequences, or
procedures of construction (except where a particular means, method, technique, sequence,
or procedure of construction is specifically and expressly called for by the Contract
Documents) or to safety precautions or programs incident thereto. The review and
acceptance of a separate item as such will not indicate approval of the assembly in which the
item functions.
3. City’s review and acceptance shall not relieve Contractor from responsibility for any
variation from the requirements of the Contract Documents unless Contractor has complied
with the requirements of Section 01 33 00 and City has given written acceptance of each
such variation by specific written notation thereof incorporated in or accompanying the
Submittal. City’s review and acceptance shall not relieve Contractor from responsibility for
complying with the requirements of the Contract Documents.
5.17 Contractor’s General Warranty and Guarantee
A. Contractor warrants and guarantees to City that all Work will be in accordance with the Contract
Documents and will not be defective. City and its officers, directors, members, partners,
employees, agents, consultants, and subcontractors shall be entitled to rely on representation of
Contractor’s warranty and guarantee.
B. Contractor’s warranty and guarantee hereunder excludes defects or damage caused by:
1. abuse, modification, or improper maintenance or operation by persons other than Contractor,
Subcontractors, Suppliers, or any other individual or entity for whom Contractor is
responsible; or
2. normal wear and tear under normal usage.
C. Contractor’s obligation to perform and complete the Work in accordance with the Contract
Documents shall be absolute. None of the following will constitute an acceptance of Work that is
not in accordance with the Contract Documents or a release of Contractor’s obligation to
perform the Work in accordance with the Contract Documents:
1. observations by City;
2. recommendation or payment by City or Developer of any progress or final payment;
3. the issuance of a certificate of Final Acceptance by City or any payment related thereto by
City;
4. use or occupancy of the Work or any part thereof by City;
5. any review and acceptance of a Submittal by City;
6. any inspection, test, or approval by others; or
00 73 10- 24
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 24 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
7. any correction of defective Work by City.
D. The Contractor shall remedy any defects or damages in the Work and pay for any damage to
other work or property resulting therefrom which shall appear within a period of two (2) years
from the date of Final Acceptance of the Work unless a longer period is specified and shall
furnish a good and sufficient maintenance bond, complying with the requirements of Article
4.02.B. The City will give notice of observed defects with reasonable promptness.
5.18 Indemnification
A. Contractor covenants and agrees to indemnify, hold harmless and defend, at its own expense, the
City, its officers, servants and employees, from and against any and all claims arising out of, or
alleged to arise out of, the work and services to be performed by the Contractor, its officers,
agents, employees, subcontractors, licenses or invitees under this Contract. THIS
INDEMNIFICATION PROVISION IS SPECIFICALLY INTENDED TO OPERATE
AND BE EFFECTIVE EVEN IF IT IS ALLEGED OR PROVEN THAT ALL OR SOME
OF THE DAMAGES BEING SOUGHT WERE CAUSED, IN WHOLE OR IN PART, BY
ANY ACT, OMISSION OR NEGLIGENCE OF THE CITY. This indemnity provision is
intended to include, without limitation, indemnity for costs, expenses and legal fees incurred by
the City in defending against such claims and causes of actions.
B. Contractor covenants and agrees to indemnify and hold harmless, at its own expense, the City, its
officers, servants and employees, from and against any and all loss, damage or destruction of
property of the City, arising out of, or alleged to arise out of, the work and services to be
performed by the Contractor, its officers, agents, employees, subcontractors, licensees or invitees
under this Contract. THIS INDEMNIFICATION PROVISION IS SPECIFICALLY
INTENDED TO OPERATE AND BE EFFECTIVE EVEN IF IT IS ALLEGED OR
PROVEN THAT ALL OR SOME OF THE DAMAGES BEING SOUGHT WERE
CAUSED, IN WHOLE OR IN PART, BY ANY ACT, OMISSION OR NEGLIGENCE OF
THE CITY.
5.19 Delegation of Professional Design Services
A. Contractor will not be required to provide professional design services unless such services are
specifically required by the Contract Documents for a portion of the Work or unless such
services are required to carry out Contractor’s responsibilities for construction means, methods,
techniques, sequences and procedures.
B. If professional design services or certifications by a design professional related to systems,
materials or equipment are specifically required of Contractor by the Contract Documents, City
will specify all performance and design criteria that such services must satisfy. Contractor shall
cause such services or certifications to be provided by a properly licensed professional, whose
signature and seal shall appear on all drawings, calculations, specifications, certifications, and
Submittals prepared by such professional. Submittals related to the Work designed or certified
by such professional, if prepared by others, shall bear such professional’s written approval when
submitted to City.
00 73 10- 25
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 25 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
C. City shall be entitled to rely upon the adequacy, accuracy and completeness of the services,
certifications or approvals performed by such design professionals, provided City has specified
to Contractor performance and design criteria that such services must satisfy.
D. Pursuant to this Paragraph 5.19, City’s review and acceptance of design calculations and design
drawings will be only for the limited purpose of checking for conformance with performance
and design criteria given and the design concept expressed in the Contract Documents. City’s
review and acceptance of Submittals (except design calculations and design drawings) will be
only for the purpose stated in Paragraph 5.16.C.
5.20 Right to Audit:
A. The City reserves the right to audit all projects utilizing City funds
B. The Contractor agrees that the City shall, until the expiration of three (3) years after final
payment under this Contract, have access to and the right to examine and photocopy any directly
pertinent books, documents, papers, and records of the Contractor involving transactions relating
to this Contract. Contractor agrees that the City shall have access during Regular Working Hours
to all necessary Contractor facilities and shall be provided adequate and appropriate work space
in order to conduct audits in compliance with the provisions of this Paragraph. The City shall
give Contractor reasonable advance notice of intended audits.
C. Contractor further agrees to include in all its subcontracts hereunder a provision to the effect that
the subcontractor agrees that the City shall, until the expiration of three (3) years after final
payment under this Contract, have access to and the right to examine and photocopy any directly
pertinent books, documents, papers, and records of such Subcontractor, involving transactions to
the subcontract, and further, that City shall have access during Regular Working Hours to all
Subcontractor facilities, and shall be provided adequate and appropriate work space in order to
conduct audits in compliance with the provisions of this Paragraph. The City shall give
Subcontractor reasonable advance notice of intended audits.
D. Contractor and Subcontractor agree to photocopy such documents as may be requested by the
City. The City agrees to reimburse Contractor for the cost of the copies as follows at the rate
published in the Texas Administrative Code in effect as of the time copying is performed.
5.21 Nondiscrimination
A. The City is responsible for operating Public Transportation Programs and implementing transit-
related projects, which are funded in part with Federal financial assistance awarded by the U.S.
Department of Transportation and the Federal Transit Administration (FTA), without
discriminating against any person in the United States on the basis of race, color, or national
origin.
B. Title VI, Civil Rights Act of 1964 as amended: Contractor shall comply with the requirements of
the Act and the Regulations as further defined in the Supplementary Conditions for any project
receiving Federal assistance.
00 73 10- 26
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 26 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
ARTICLE 6 – OTHER WORK AT THE SITE
6.01 Related Work at Site
A. City may perform other work related to the Project at the Site with City’s employees, or other
City contractors, or through other direct contracts therefor, or have other work performed by
utility owners. If such other work is not noted in the Contract Documents, then written notice
thereof will be given to Contractor prior to starting any such other work; and
B. Contractor shall afford each other contractor who is a party to such a direct contract, each utility
owner, and City, if City is performing other work with City’s employees or other City
contractors, proper and safe access to the Site, provide a reasonable opportunity for the
introduction and storage of materials and equipment and the execution of such other work, and
properly coordinate the Work with theirs. Contractor shall do all cutting, fitting, and patching of
the Work that may be required to properly connect or otherwise make its several parts come
together and properly integrate with such other work. Contractor shall not endanger any work of
others by cutting, excavating, or otherwise altering such work; provided, however, that
Contractor may cut or alter others' work with the written consent of City and the others whose
work will be affected.
C. If the proper execution or results of any part of Contractor’s Work depends upon work
performed by others under this Article 7, Contractor shall inspect such other work and promptly
report to City in writing any delays, defects, or deficiencies in such other work that render it
unavailable or unsuitable for the proper execution and results of Contractor’s Work. Contractor’s
failure to so report will constitute an acceptance of such other work as fit and proper for
integration with Contractor’s Work except for latent defects in the work provided by others.
ARTICLE 7 – CITY’S RESPONSIBILITIES
7.01 Inspections, Tests, and Approvals
City’s responsibility with respect to certain inspections, tests, and approvals is set forth in Paragraph
11.03.
7.02 Limitations on City’s Responsibilities
A. The City shall not supervise, direct, or have control or authority over, nor be responsible for,
Contractor’s means, methods, techniques, sequences, or procedures of construction, or the safety
precautions and programs incident thereto, or for any failure of Contractor to comply with Laws
and Regulations applicable to the performance of the Work. City will not be responsible for
Contractor’s failure to perform the Work in accordance with the Contract Documents.
B. City will notify the Contractor of applicable safety plans pursuant to Paragraph 5.13.
00 73 10- 27
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 27 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
7.03 Compliance with Safety Program
While at the Site, City’s employees and representatives shall comply with the specific applicable
requirements of Contractor’s safety programs of which City has been informed pursuant to
Paragraph 5.13.
ARTICLE 8 – CITY’S OBSERVATION STATUS DURING CONSTRUCTION
8.01 City’s Project Representative
City will provide one or more Project Representative(s) during the construction period. The duties
and responsibilities and the limitations of authority of City’s representative during construction are
set forth in the Contract Documents.
A. City’s Project Representative will make visits to the Site at intervals appropriate to the various
stages of construction as City deems necessary in order to observe the progress that has been
made and the quality of the various aspects of Contractor’s executed Work. Based on
information obtained during such visits and observations, City’s Project Representative will
determine, in general, if the Work is proceeding in accordance with the Contract Documents.
City’s Project Representative will not be required to make exhaustive or continuous inspections
on the Site to check the quality or quantity of the Work. City’s Project Representative’s efforts
will be directed toward providing City a greater degree of confidence that the completed Work
will conform generally to the Contract Documents.
B. City’s Project Representative’s visits and observations are subject to all the limitations on
authority and responsibility in the Contract Documents.
8.02 Authorized Variations in Work
City’s Project Representative may authorize minor variations in the Work from the requirements of
the Contract Documents which do not involve an adjustment in the Contract Price or the Contract
Time and are compatible with the design concept of the completed Project as a functioning whole as
indicated by the Contract Documents. These may be accomplished by a Field Order and will be
binding on City Developer, and also on Contractor, who shall perform the Work involved promptly.
8.03 Rejecting Defective Work
City will have authority to reject Work which City’s Project Representative believes to be defective,
or will not produce a completed Project that conforms to the Contract Documents or that will
prejudice the integrity of the design concept of the completed Project as a functioning whole as
indicated by the Contract Documents. City will have authority to conduct special inspection or
testing of the Work as provided in Article 11, whether or not the Work is fabricated, installed, or
completed.
00 73 10- 28
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 28 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
8.04 Determinations for Work Performed
Contractor will determine the actual quantities and classifications of Work performed. City’s Project
Representative will review with Contractor the preliminary determinations on such matters before
rendering a written recommendation. City’s written decision will be final (except as modified to
reflect changed factual conditions or more accurate data).
ARTICLE 9 – CHANGES IN THE WORK
9.01 Authorized Changes in the Work
A. Without invalidating the Contract and without notice to any surety, City may, at any time or
from time to time, order Extra Work. Upon notice of such Extra Work, Contractor shall
promptly proceed with the Work involved which will be performed under the applicable
conditions of the Contract Documents (except as otherwise specifically provided). Extra Work
shall be memorialized by a Participating Change Order which may or may not precede an order
of Extra work.
B. For minor changes of Work not requiring changes to Contract Time or Contract Price on a
project with City participation, a Field Order may be issued by the City.
9.02 Notification to Surety
If the provisions of any bond require notice to be given to a surety of any change affecting the
general scope of the Work or the provisions of the Contract Documents (including, but not limited
to, Contract Price or Contract Time), the giving of any such notice will be Contractor’s
responsibility. The amount of each applicable bond will be adjusted by the Contractor to reflect the
effect of any such change.
ARTICLE 10 – CHANGE OF CONTRACT PRICE; CHANGE OF CONTRACT TIME
10.01 Change of Contract Price
A. The Contract Price may only be changed by a Participating Change Order for projects with City
participation.
10.02 Change of Contract Time
A. The Contract Time may only be changed by a Participating Change Order for projects with City
participation.
10.03 Delays
A. If Contractor is delayed, City shall not be liable to Contractor for any claims, costs, losses, or
damages (including but not limited to all fees and charges of engineers, architects, attorneys, and
other professionals and all court or arbitration or other dispute resolution costs) sustained by
Contractor on or in connection with any other project or anticipated project.
00 73 10- 29
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 29 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
ARTICLE 11 – TESTS AND INSPECTIONS; CORRECTION, REMOVAL OR ACCEPTANCE OF
DEFECTIVE WORK
11.01 Notice of Defects
Notice of all defective Work of which City has actual knowledge will be given to Contractor.
Defective Work may be rejected, corrected, or accepted as provided in this Article 13.
11.02 Access to Work
City, independent testing laboratories, and governmental agencies with jurisdictional interests will
have access to the Site and the Work at reasonable times for their observation, inspection, and
testing. Contractor shall provide them proper and safe conditions for such access and advise them of
Contractor’s safety procedures and programs so that they may comply therewith as applicable.
11.03 Tests and Inspections
A. Contractor shall give City timely notice of readiness of the Work for all required inspections,
tests, or approvals and shall cooperate with inspection and testing personnel to facilitate required
inspections or tests.
B. If Contract Documents, Laws or Regulations of any public body having jurisdiction require any
of the Work (or part thereof) to be inspected, tested, or approved, Contractor shall assume full
responsibility for arranging and obtaining such independent inspections, tests, retests or
approvals, pay all costs in connection therewith, and furnish City the required certificates of
inspection or approval; excepting, however, those fees specifically identified in the
Supplementary Conditions or any Texas Department of Licensure and Regulation (TDLR)
inspections, which shall be paid as described in the Supplementary Conditions.
C. Contractor shall be responsible for arranging and obtaining and shall pay all costs in connection
with any inspections, tests, re-tests, or approvals required for City’s acceptance of materials or
equipment to be incorporated in the Work; or acceptance of materials, mix designs, or equipment
submitted for approval prior to Contractor’s purchase thereof for incorporation in the Work.
Such inspections, tests, re-tests, or approvals shall be performed by organizations approved by
City.
D. City may arrange for the services of an independent testing laboratory (“Testing Lab”) to
perform any inspections or tests (“Testing”) for any part of the Work, as determined solely by
City.
1. City will coordinate such Testing to the extent possible, with Contractor;
2. Should any Testing under this Section 11.03 D result in a “fail”, “did not pass” or other
similar negative result, the Contractor shall be responsible for paying for any and all retests.
Contractor’s cancellation without cause of City initiated Testing shall be deemed a negative
result and require a retest.
00 73 10- 30
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 30 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
3. Any amounts owed for any retest under this Section 11.03 D shall be paid directly to the
Testing Lab by Contractor. City will forward all invoices for retests to
Developer/Contractor.
4. If Contractor fails to pay the Testing Lab, City will not issue a letter of Final Acceptance
until the Testing Lab is Paid
E. If any Work (or the work of others) that is to be inspected, tested, or approved is covered by
Contractor without written concurrence of City, Contractor shall, if requested by City, uncover
such Work for observation.
11.04 Uncovering Work
A. If any Work is covered contrary to the Contract Documents or specific instructions by the City, it
must, if requested by City, be uncovered for City’s observation and replaced at Contractor’s
expense.
11.05 City May Stop the Work
If the Work is defective, or Contractor fails to supply sufficient skilled workers or suitable materials
or equipment, or fails to perform the Work in such a way that the completed Work will conform to
the Contract Documents, City may order Contractor to stop the Work, or any portion thereof, until
the cause for such order has been eliminated; however, this right of City to stop the Work shall not
give rise to any duty on the part of City to exercise this right for the benefit of Contractor, any
Subcontractor, any Supplier, any other individual or entity, or any surety for, or employee or agent
of any of them.
11.06 Correction or Removal of Defective Work
A. Promptly after receipt of written notice, Contractor shall correct all defective Work pursuant to
an acceptable schedule, whether or not fabricated, installed, or completed, or, if the Work has
been rejected by City, remove it from the Project and replace it with Work that is not defective.
Contractor shall pay all claims, costs, additional testing, losses, and damages (including but not
limited to all fees and charges of engineers, architects, attorneys, and other professionals and all
court or arbitration or other dispute resolution costs) arising out of or relating to such correction
or removal (including but not limited to all costs of repair or replacement of work of others).
Failure to require the removal of any defective Work shall not constitute acceptance of such
Work.
B. When correcting defective Work under the terms of this Paragraph 11.06 or Paragraph 11.07,
Contractor shall take no action that would void or otherwise impair City’s special warranty and
guarantee, if any, on said Work.
11.07 Correction Period
A. If within two (2) years after the date of Final Acceptance (or such longer period of time as may
be prescribed by the terms of any applicable special guarantee required by the Contract
00 73 10- 31
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 31 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
Documents), any Work is found to be defective, or if the repair of any damages to the land or
areas made available for Contractor’s use by City or permitted by Laws and Regulations as
contemplated in Paragraph 5.10.A is found to be defective, Contractor shall promptly, without
cost to City and in accordance with City’s written instructions:
1. repair such defective land or areas; or
2. correct such defective Work; or
3. if the defective Work has been rejected by City, remove it from the Project and replace it
with Work that is not defective, and
4. satisfactorily correct or repair or remove and replace any damage to other Work, to the work
of others or other land or areas resulting therefrom.
B. If Contractor does not promptly comply with the terms of City’s written instructions, or in an
emergency where delay would cause serious risk of loss or damage, City may have the defective
Work corrected or repaired or may have the rejected Work removed and replaced. All claims,
costs, losses, and damages (including but not limited to all fees and charges of engineers,
architects, attorneys, and other professionals and all court or other dispute resolution costs)
arising out of or relating to such correction or repair or such removal and replacement (including
but not limited to all costs of repair or replacement of work of others) will be paid by Contractor.
C. Where defective Work (and damage to other Work resulting therefrom) has been corrected or
removed and replaced under this Paragraph 11.07, the correction period hereunder with respect
to such Work may be required to be extended for an additional period of one year after the end
of the initial correction period. City shall provide 30 days written notice to Contractor and
Developer should such additional warranty coverage be required. Contractor’s obligations under
this Paragraph 11.07 are in addition to any other obligation or warranty. The provisions of this
Paragraph 11.07 shall not be construed as a substitute for, or a waiver of, the provisions of any
applicable statute of limitation or repose.
11.08 City May Correct Defective Work
A. If Contractor fails within a reasonable time after written notice from City to correct defective
Work, or to remove and replace rejected Work as required by City in accordance with Paragraph
11.06.A, or if Contractor fails to perform the Work in accordance with the Contract Documents,
or if Contractor fails to comply with any other provision of the Contract Documents, City may,
after seven (7) days written notice to Contractor and the Developer, correct, or remedy any such
deficiency.
B. In exercising the rights and remedies under this Paragraph 11.09, City shall proceed
expeditiously. In connection with such corrective or remedial action, City may exclude
Contractor from all or part of the Site, take possession of all or part of the Work and suspend
Contractor’s services related thereto, and incorporate in the Work all materials and equipment
incorporated in the Work, stored at the Site or for which City has paid Contractor but which are
00 73 10- 32
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 32 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
stored elsewhere. Contractor shall allow City, City’s representatives, agents, consultants,
employees, and City’s other contractors, access to the Site to enable City to exercise the rights
and remedies under this Paragraph.
C. All claims, costs, losses, and damages (including but not limited to all fees and charges of
engineers, architects, attorneys, and other professionals and all court or other dispute resolution
costs) incurred or sustained by City in exercising the rights and remedies under this Paragraph
13.09 will be charged against Contractor, and a Change Order will be issued incorporating the
necessary revisions in the Contract Documents with respect to the Work; and City shall be
entitled to an appropriate decrease in the Contract Price.
D. Contractor shall not be allowed an extension of the Contract Time because of any delay in the
performance of the Work attributable to the exercise of City’s rights and remedies under this
Paragraph 11.09.
ARTICLE 12 – COMPLETION
12.01 Contractor’s Warranty of Title
Contractor warrants and guarantees that title to all Work, materials, and equipment covered by any
Application for Payment will pass to City no later than the time of Final Acceptance and shall be
free and clear of all Liens.
12.02 Partial Utilization
A. Prior to Final Acceptance of all the Work, City may use or occupy any substantially completed
part of the Work which has specifically been identified in the Contract Documents, or which
City, determines constitutes a separately functioning and usable part of the Work that can be
used by City for its intended purpose without significant interference with Contractor’s
performance of the remainder of the Work. City at any time may notify Contractor in writing to
permit City to use or occupy any such part of the Work which City determines to be ready for its
intended use, subject to the following conditions:
1. Contractor at any time may notify City in writing that Contractor considers any such part of
the Work ready for its intended use.
2. Within a reasonable time after notification as enumerated in Paragraph 14.05.A.1, City and
Contractor shall make an inspection of that part of the Work to determine its status of
completion. If City does not consider that part of the Work to be substantially complete, City
will notify Contractor in writing giving the reasons therefor.
3. Partial Utilization will not constitute Final Acceptance by City.
12.03 Final Inspection
A. Upon written notice from Contractor that the entire Work is complete in accordance with the
Contract Documents:
00 73 10- 33
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 33 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
1. within 10 days, City will schedule a Final Inspection with Contractor.
2. City will notify Contractor in writing of all particulars in which this inspection reveals that
the Work is incomplete or defective. Contractor shall immediately take such measures as are
necessary to complete such Work or remedy such deficiencies.
12.04 Final Acceptance
A. Upon completion by Contractor to City’s satisfaction, of any additional Work identified in the
Final Inspection, City will issue to Contractor a letter of Final Acceptance upon the satisfaction
of the following:
1. All documentation called for in the Contract Documents, including but not limited to the
evidence of insurance required by Paragraph 5.03;
2. consent of the surety, if any, to Final Acceptance;
3. a list of all pending or released Damage Claims against City that Contractor believes are
unsettled; and
4. affidavits of payments and complete and legally effective releases or waivers (satisfactory to
City) of all Lien rights arising out of or Liens filed in connection with the Work.
5. after all Damage Claims have been resolved:
a. directly by the Contractor or;
b. Contractor provides evidence that the Damage Claim has been reported to Contractor’s
insurance provider for resolution.
6. Issuing Final Acceptance by the City shall not relieve the Contractor of any guarantees or
other requirements of the Contract Documents which specifically continue thereafter.
ARTICLE 13 – SUSPENSION OF WORK
13.01 City May Suspend Work
A. At any time and without cause, City may suspend the Work or any portion thereof by written
notice to Contractor and which may fix the date on which Work will be resumed. Contractor
shall resume the Work on the date so fixed. During temporary suspension of the Work covered
by these Contract Documents, for any reason, the City will stop contract time on City
participation projects.
B. Should the Contractor not be able to complete a portion of the Project due to causes beyond the
control of and without the fault or negligence of the Contractor, and should it be determined by
mutual consent of the Contractor and City that a solution to allow construction to proceed is not
00 73 10- 34
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 34 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
available within a reasonable period of time, Contractor may request an extension in Contract
Time, directly attributable to any such suspension.
C. If it should become necessary to suspend the Work for an indefinite period, the Contractor shall
store all materials in such a manner that they will not obstruct or impede the public unnecessarily
nor become damaged in any way, and he shall take every precaution to prevent damage or
deterioration of the work performed; he shall provide suitable drainage about the work, and erect
temporary structures where necessary.
ARTICLE 14 – MISCELLANEOUS
14.01 Giving Notice
A. Whenever any provision of the Contract Documents requires the giving of written notice, it will
be deemed to have been validly given if:
1. delivered in person to the individual or to a member of the firm or to an officer of the
corporation for whom it is intended; or
2. delivered at or sent by registered or certified mail, postage prepaid, to the last business
address known to the giver of the notice.
B. Business address changes must be promptly made in writing to the other party.
C. Whenever the Contract Documents specifies giving notice by electronic means such electronic
notice shall be deemed sufficient upon confirmation of receipt by the receiving party.
14.02 Computation of Times
When any period of time is referred to in the Contract Documents by days, it will be computed to
exclude the first and include the last day of such period. If the last day of any such period falls on a
Saturday or Sunday or on a day made a legal holiday the next Working Day shall become the last
day of the period.
14.03 Cumulative Remedies
The duties and obligations imposed by these General Conditions and the rights and remedies
available hereunder to the parties hereto are in addition to, and are not to be construed in any way as
a limitation of, any rights and remedies available to any or all of them which are otherwise imposed
or available by Laws or Regulations, by special warranty or guarantee, or by other provisions of the
Contract Documents. The provisions of this Paragraph will be as effective as if repeated specifically
in the Contract Documents in connection with each particular duty, obligation, right, and remedy to
which they apply.
00 73 10- 35
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 35 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
14.04 Survival of Obligations
All representations, indemnifications, warranties, and guarantees made in, required by, or given in
accordance with the Contract Documents, as well as all continuing obligations indicated in the
Contract Documents, will survive final payment, completion, and acceptance of the Work or
termination or completion of the Contract or termination of the services of Contractor.
14.05 Headings
Article and paragraph headings are inserted for convenience only and do not constitute parts of these
General Conditions.
01 11 00 - 1
DAP SUMMARY OF WORK
Page 1 of 3
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – Developer Awarded Projects 102561
Revised December 20, 2012
1 SECTION 01 11 00
2 SUMMARY OF WORK
3 PART 1 - GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. Summary of Work to be performed in accordance with the Contract Documents
7 B. Deviations from this City of Fort Worth Standard Specification
8 1. None.
9 C. Related Specification Sections include, but are not necessarily limited to:
10 1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the Contract
11 2. Division 1 - General Requirements
12 1.2 PRICE AND PAYMENT PROCEDURES
13 A. Measurement and Payment
14 1. Work associated with this Item is considered subsidiary to the various items bid.
15 No separate payment will be allowed for this Item.
16 1.3 REFERENCES [NOT USED]
17 1.4 ADMINISTRATIVE REQUIREMENTS
18 A. Work Covered by Contract Documents
19 1. Work is to include furnishing all labor, materials, and equipment, and performing
20 all Work necessary for this construction project as detailed in the Drawings and
21 Specifications.
22 B. Subsidiary Work
23 1. Any and all Work specifically governed by documentary requirements for the
24 project, such as conditions imposed by the Drawings or Contract Documents in
25 which no specific item for bid has been provided for in the Proposal and the item is
26 not a typical unit bid item included on the standard bid item list, then the item shall
27 be considered as a subsidiary item of Work, the cost of which shall be included in
28 the price bid in the Proposal for various bid items.
29 C. Use of Premises
30 1. Coordinate uses of premises under direction of the City.
31 2. Assume full responsibility for protection and safekeeping of materials and
32 equipment stored on the Site.
33 3. Use and occupy only portions of the public streets and alleys, or other public places
34 or other rights-of-way as provided for in the ordinances of the City, as shown in the
35 Contract Documents, or as may be specifically authorized in writing by the City.
36 a. A reasonable amount of tools, materials, and equipment for construction
37 purposes may be stored in such space, but no more than is necessary to avoid
38 delay in the construction operations.
01 11 00 - 2
DAP SUMMARY OF WORK
Page 2 of 3
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – Developer Awarded Projects 102561
Revised December 20, 2012
1 b. Excavated and waste materials shall be stored in such a way as not to interfere
2 with the use of spaces that may be designated to be left free and unobstructed
3 and so as not to inconvenience occupants of adjacent property.
4 c. If the street is occupied by railroad tracks, the Work shall be carried on in such
5 manner as not to interfere with the operation of the railroad.
6 1) All Work shall be in accordance with railroad requirements set forth in
7 Division 0 as well as the railroad permit.
8 D. Work within Easements
9 1. Do not enter upon private property for any purpose without having previously
10 obtained permission from the owner of such property.
11 2. Do not store equipment or material on private property unless and until the
12 specified approval of the property owner has been secured in writing by the
13 Contractor and a copy furnished to the City.
14 3. Unless specifically provided otherwise, clear all rights-of-way or easements of
15 obstructions which must be removed to make possible proper prosecution of the
16 Work as a part of the project construction operations.
17 4. Preserve and use every precaution to prevent damage to, all trees, shrubbery, plants,
18 lawns, fences, culverts, curbing, and all other types of structures or improvements,
19 to all water, sewer, and gas lines, to all conduits, overhead pole lines, or
20 appurtenances thereof, including the construction of temporary fences and to all
21 other public or private property adjacent to the Work.
22 5. Notify the proper representatives of the owners or occupants of the public or private
23 lands of interest in lands which might be affected by the Work.
24 a. Such notice shall be made at least 48 hours in advance of the beginning of the
25 Work.
26 b. Notices shall be applicable to both public and private utility companies and any
27 corporation, company, individual, or other, either as owners or occupants,
28 whose land or interest in land might be affected by the Work.
29 c. Be responsible for all damage or injury to property of any character resulting
30 from any act, omission, neglect, or misconduct in the manner or method or
31 execution of the Work, or at any time due to defective work, material, or
32 equipment.
33 6. Fence
34 a. Restore all fences encountered and removed during construction of the Project
35 to the original or a better than original condition.
36 b. Erect temporary fencing in place of the fencing removed whenever the Work is
37 not in progress and when the site is vacated overnight, and/or at all times to
38 provide site security.
39 c. The cost for all fence work within easements, including removal, temporary
40 closures and replacement, shall be subsidiary to the various items bid in the
41 project proposal, unless a bid item is specifically provided in the proposal.
01 11 00 - 3
DAP SUMMARY OF WORK
Page 3 of 3
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – Developer Awarded Projects 102561
Revised December 20, 2012
1 1.5 SUBMITTALS [NOT USED]
2 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
3 1.7 CLOSEOUT SUBMITTALS [NOT USED]
4 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
5 1.9 QUALITY ASSURANCE [NOT USED]
6 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
7 1.11 FIELD [SITE] CONDITIONS [NOT USED]
8 1.12 WARRANTY [NOT USED]
9 PART 2 - PRODUCTS [NOT USED]
10 PART 3 - EXECUTION [NOT USED]
11 END OF SECTION
12
Revision Log
DATE NAME SUMMARY OF CHANGE
13
01 25 00 - 1
DAP SUBSTITUTION PROCEDURES
Page 1 of 4
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102561
Revised August 30, 2013
1 SECTION 01 25 00
2 SUBSTITUTION PROCEDURES
3 PART 1 - GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. The procedure for requesting the approval of substitution of a product that is not
7 equivalent to a product which is specified by descriptive or performance criteria or
8 defined by reference to 1 or more of the following:
9 a. Name of manufacturer
10 b. Name of vendor
11 c. Trade name
12 d. Catalog number
13 2. Substitutions are not "or-equals".
14 B. Deviations from this City of Fort Worth Standard Specification
15 1. None.
16 C. Related Specification Sections include, but are not necessarily limited to:
17 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
18 2. Division 1 – General Requirements
19 1.2 PRICE AND PAYMENT PROCEDURES
20 A. Measurement and Payment
21 1. Work associated with this Item is considered subsidiary to the various items bid. No
22 separate payment will be allowed for this Item.
23 1.3 REFERENCES [NOT USED]
24 1.4 ADMINISTRATIVE REQUIREMENTS
25 A. Request for Substitution - General
26 1. Within 30 days after award of Contract (unless noted otherwise), the City will
27 consider formal requests from Contractor for substitution of products in place of
28 those specified.
29 2. Certain types of equipment and kinds of material are described in Specifications by
30 means of references to names of manufacturers and vendors, trade names, or catalog
31 numbers.
32 a. When this method of specifying is used, it is not intended to exclude from
33 consideration other products bearing other manufacturer's or vendor's names,
34 trade names, or catalog numbers, provided said products are "or-equals," as
35 determined by City.
36 3. Other types of equipment and kinds of material may be acceptable substitutions
37 under the following conditions:
38 a. Or-equals are unavailable due to strike, discontinued production of products
39 meeting specified requirements, or other factors beyond control of Contractor;
40 or,
01 25 00 - 2
DAP SUBSTITUTION PROCEDURES
Page 2 of 4
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102561
Revised August 30, 2013
1 b. Contractor proposes a cost and/or time reduction incentive to the City.
2 1.5 SUBMITTALS
3 A. See Request for Substitution Form (attached)
4 B. Procedure for Requesting Substitution
5 1. Substitution shall be considered only:
6 a. After award of Contract
7 b. Under the conditions stated herein
8 2. Submit 3 copies of each written request for substitution, including:
9 a. Documentation
10 1) Complete data substantiating compliance of proposed substitution with
11 Contract Documents
12 2) Data relating to changes in construction schedule, when a reduction is
13 proposed
14 3) Data relating to changes in cost
15 b. For products
16 1) Product identification
17 a) Manufacturer's name
18 b) Telephone number and representative contact name
19 c) Specification Section or Drawing reference of originally specified
20 product, including discrete name or tag number assigned to original
21 product in the Contract Documents
22 2) Manufacturer's literature clearly marked to show compliance of proposed
23 product with Contract Documents
24 3) Itemized comparison of original and proposed product addressing product
25 characteristics including, but not necessarily limited to:
26 a) Size
27 b) Composition or materials of construction
28 c) Weight
29 d) Electrical or mechanical requirements
30 4) Product experience
31 a) Location of past projects utilizing product
32 b) Name and telephone number of persons associated with referenced
33 projects knowledgeable concerning proposed product
34 c) Available field data and reports associated with proposed product
35 5) Samples
36 a) Provide at request of City.
37 b) Samples become the property of the City.
38 c. For construction methods:
39 1) Detailed description of proposed method
40 2) Illustration drawings
41 C. Approval or Rejection
42 1. Written approval or rejection of substitution given by the City
43 2. City reserves the right to require proposed product to comply with color and pattern
44 of specified product if necessary to secure design intent.
45 3. In the event the substitution is approved, if a reduction in cost or time results, it will
46 be documented by Change Order.
01 25 00 - 3
DAP SUBSTITUTION PROCEDURES
Page 3 of 4
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102561
Revised August 30, 2013
1 4. Substitution will be rejected if:
2 a. Submittal is not through the Contractor with his stamp of approval
3 b. Request is not made in accordance with this Specification Section
4 c. In the Developer’s opinion, acceptance will require substantial revision of the
5 original design
6 d. In the City’s or Developer’s opinion, substitution will not perform adequately
7 the function consistent with the design intent
8 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
9 1.7 CLOSEOUT SUBMITTALS [NOT USED]
10 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
11 1.9 QUALITY ASSURANCE
12 A. In making request for substitution or in using an approved product, the Contractor
13 represents that the Contractor:
14 1. Has investigated proposed product, and has determined that it is adequate or
15 superior in all respects to that specified, and that it will perform function for which it
16 is intended
17 2. Will provide same guarantee for substitute item as for product specified
18 3. Will coordinate installation of accepted substitution into Work, to include building
19 modifications if necessary, making such changes as may be required for Work to be
20 complete in all respects
21 4. Waives all claims for additional costs related to substitution which subsequently
22 arise
23 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
24 1.11 FIELD [SITE] CONDITIONS [NOT USED]
25 1.12 WARRANTY [NOT USED]
26 PART 2 - PRODUCTS [NOT USED]
27 PART 3 - EXECUTION [NOT USED]
28 END OF SECTION
29
Revision Log
DATE NAME SUMMARY OF CHANGE
01 25 00 - 4
DAP SUBSTITUTION PROCEDURES
Page 4 of 4
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102561
Revised August 30, 2013
1 EXHIBIT A
2 REQUEST FOR SUBSTITUTION FORM:
3
4 TO:
5 PROJECT: DATE:
6 We hereby submit for your consideration the following product instead of the specified item for
7 the above project:
8 SECTION PARAGRAPH SPECIFIED
9 ITEM
10
11
12 Proposed Substitution:
13 Reason for Substitution:
14 Include complete information on changes to Drawings and/or Specifications which proposed
15 substitution will require for its proper installation.
16
17 Fill in Blanks Below:
18 A. Will the undersigned contractor pay for changes to the building design, including engineering
19 and detailing costs caused by the requested substitution?
20
21
22 B. What effect does substitution have on other trades?
23
24
25 C. Differences between proposed substitution and specified item?
26
27
28 D. Differences in product cost or product delivery time?
29
30
31 E. Manufacturer's guarantees of the proposed and specified items are:
32
33 Equal Better (explain on attachment)
34 The undersigned states that the function, appearance and quality are equivalent or superior to the
35 specified item.
36 Submitted By: For Use by City
37
38 Signature Recommended Recommended
39 as noted
40
41 Firm Not recommended Received late
42 Address By
43 Date
44 Date Remarks
45 Telephone
46
47 For Use by City:
48
49 Approved Rejected
50 City Date
01 31 19 - 1
DAP PRECONSTRUCTION MEETING
Page 1 of 3
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102561
Revised August 30, 2013
1 SECTION 01 31 19
2 PRECONSTRUCTION MEETING
3 PART 1 - GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. Provisions for the preconstruction meeting to be held prior to the start of Work to
7 clarify construction contract administration procedures
8 B. Deviations from this City of Fort Worth Standard Specification
9 1. No construction schedule required unless requested by the City.
10 C. Related Specification Sections include, but are not necessarily limited to:
11 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
12 2. Division 1 – General Requirements
13 1.2 PRICE AND PAYMENT PROCEDURES
14 A. Measurement and Payment
15 1. Work associated with this Item is considered subsidiary to the various items bid.
16 No separate payment will be allowed for this Item.
17 1.3 REFERENCES [NOT USED]
18 1.4 ADMINISTRATIVE REQUIREMENTS
19 A. Coordination
20 1. Attend preconstruction meeting.
21 2. Representatives of Contractor, subcontractors and suppliers attending meetings
22 shall be qualified and authorized to act on behalf of the entity each represents.
23 3. Meeting administered by City may be tape recorded.
24 a. If recorded, tapes will be used to prepare minutes and retained by City for
25 future reference.
26 B. Preconstruction Meeting
27 1. A preconstruction meeting will be held within 14 days after the delivery of the
28 distribution package to the City.
29 a. The meeting will be scheduled and administered by the City.
30 2. The Project Representative will preside at the meeting, prepare the notes of the
31 meeting and distribute copies of same to all participants who so request by fully
32 completing the attendance form to be circulated at the beginning of the meeting.
33 3. Attendance shall include:
34 a. Developer and Consultant
35 b. Contractor's project manager
36 c. Contractor's superintendent
37 d. Any subcontractor or supplier representatives whom the Contractor may desire
38 to invite or the City may request
01 31 19 - 2
DAP PRECONSTRUCTION MEETING
Page 2 of 3
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102561
Revised August 30, 2013
1 e. Other City representatives
2 f. Others as appropriate
3 4. Preliminary Agenda may include:
4 a. Introduction of Project Personnel
5 b. General Description of Project
6 c. Status of right-of-way, utility clearances, easements or other pertinent permits
7 d. Contractor’s work plan and schedule
8 e. Contract Time
9 f. Notice to Proceed
10 g. Construction Staking
11 h. Progress Payments
12 i. Extra Work and Change Order Procedures
13 j. Field Orders
14 k. Disposal Site Letter for Waste Material
15 l. Insurance Renewals
16 m. Payroll Certification
17 n. Material Certifications and Quality Control Testing
18 o. Public Safety and Convenience
19 p. Documentation of Pre-Construction Conditions
20 q. Weekend Work Notification
21 r. Legal Holidays
22 s. Trench Safety Plans
23 t. Confined Space Entry Standards
24 u. Coordination with the City’s representative for operations of existing water
25 systems
26 v. Storm Water Pollution Prevention Plan
27 w. Coordination with other Contractors
28 x. Early Warning System
29 y. Contractor Evaluation
30 z. Special Conditions applicable to the project
31 aa. Damages Claims
32 bb. Submittal Procedures
33 cc. Substitution Procedures
34 dd. Correspondence Routing
35 ee. Record Drawings
36 ff. Temporary construction facilities
37 gg. MBE/SBE procedures
38 hh. Final Acceptance
39 ii. Final Payment
40 jj. Questions or Comments
01 31 19 - 3
DAP PRECONSTRUCTION MEETING
Page 3 of 3
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102561
Revised August 30, 2013
1 1.5 SUBMITTALS [NOT USED]
2 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
3 1.7 CLOSEOUT SUBMITTALS [NOT USED]
4 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
5 1.9 QUALITY ASSURANCE [NOT USED]
6 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
7 1.11 FIELD [SITE] CONDITIONS [NOT USED]
8 1.12 WARRANTY [NOT USED]
9 PART 2 - PRODUCTS [NOT USED]
10 PART 3 - EXECUTION [NOT USED]
11 END OF SECTION
12
Revision Log
DATE NAME SUMMARY OF CHANGE
13
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102561
Revised August 30, 2013
01 32 33 - 1
DAP PRECONSTRUCTION VIDEO
Page 1 of 2
SECTION 01 32 33
PRECONSTRUCTION VIDEO
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Administrative and procedural requirements for:
a. Preconstruction Videos
B. Deviations from this City of Fort Worth Standard Specification
1. Though not mandatory, it is highly recommended on infill developer projects.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. Preconstruction Video
1. Produce a preconstruction video of the site/alignment, including all areas in the vicinity
of and to be affected by construction.
a. Provide digital copy of video upon request by the City.
2. Retain a copy of the preconstruction video until the end of the maintenance surety
period.
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102561
Revised August 30, 2013
01 32 33 - 2
DAP PRECONSTRUCTION VIDEO
Page 2 of 2
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
01 33 00 - 1
DAP SUBMITTALS
Page 1 of 8
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102561
Revised August 30, 2013
1 SECTION 01 33 00
2 DAP SUBMITTALS
3 PART 1 - GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. General methods and requirements of submissions applicable to the following
7 Work-related submittals:
8 a. Shop Drawings
9 b. Product Data (including Standard Product List submittals)
10 c. Samples
11 d. Mock Ups
12 B. Deviations from this City of Fort Worth Standard Specification
13 1. None.
14 C. Related Specification Sections include, but are not necessarily limited to:
15 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
16 2. Division 1 – General Requirements
17 1.2 PRICE AND PAYMENT PROCEDURES
18 A. Measurement and Payment
19 1. Work associated with this Item is considered subsidiary to the various items bid.
20 No separate payment will be allowed for this Item.
21 1.3 REFERENCES [NOT USED]
22 1.4 ADMINISTRATIVE REQUIREMENTS
23 A. Coordination
24 1. Notify the City in writing, at the time of submittal, of any deviations in the
25 submittals from the requirements of the Contract Documents.
26 2. Coordination of Submittal Times
27 a. Prepare, prioritize and transmit each submittal sufficiently in advance of
28 performing the related Work or other applicable activities, or within the time
29 specified in the individual Work Sections, of the Specifications.
30 b. Contractor is responsible such that the installation will not be delayed by
31 processing times including, but not limited to:
32 a) Disapproval and resubmittal (if required)
33 b) Coordination with other submittals
34 c) Testing
35 d) Purchasing
36 e) Fabrication
37 f) Delivery
38 g) Similar sequenced activities
39 c. No extension of time will be authorized because of the Contractor's failure to
40 transmit submittals sufficiently in advance of the Work.
01 33 00 - 2
DAP SUBMITTALS
Page 2 of 8
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102561
Revised August 30, 2013
1 d. Make submittals promptly in accordance with approved schedule, and in such
2 sequence as to cause no delay in the Work or in the work of any other
3 contractor.
4 B. Submittal Numbering
5 1. When submitting shop drawings or samples, utilize a 9-character submittal cross-
6 reference identification numbering system in the following manner:
7 a. Use the first 6 digits of the applicable Specification Section Number.
8 b. For the next 2 digits number use numbers 01-99 to sequentially number each
9 initial separate item or drawing submitted under each specific Section number.
10 c. Last use a letter, A-Z, indicating the resubmission of the same drawing (i.e.
11 A=2nd submission, B=3rd submission, C=4th submission, etc.). A typical
12 submittal number would be as follows:
13
14 03 30 00-08-B
15
16 1) 03 30 00 is the Specification Section for Concrete
17 2) 08 is the eighth initial submittal under this Specification Section
18 3) B is the third submission (second resubmission) of that particular shop
19 drawing
20 C. Contractor Certification
21 1. Review shop drawings, product data and samples, including those by
22 subcontractors, prior to submission to determine and verify the following:
23 a. Field measurements
24 b. Field construction criteria
25 c. Catalog numbers and similar data
26 d. Conformance with the Contract Documents
27 2. Provide each shop drawing, sample and product data submitted by the Contractor
28 with a Certification Statement affixed including:
29 a. The Contractor's Company name
30 b. Signature of submittal reviewer
31 c. Certification Statement
32 1) “By this submittal, I hereby represent that I have determined and verified
33 field measurements, field construction criteria, materials, dimensions,
34 catalog numbers and similar data and I have checked and coordinated each
35 item with other applicable approved shop drawings."
36 D. Submittal Format
37 1. Fold shop drawings larger than 8 ½ inches x 11 inches to 8 ½ inches x 11inches.
38 2. Bind shop drawings and product data sheets together.
39 3. Order
40 a. Cover Sheet
41 1) Description of Packet
42 2) Contractor Certification
43 b. List of items / Table of Contents
44 c. Product Data /Shop Drawings/Samples /Calculations
45 E. Submittal Content
46 1. The date of submission and the dates of any previous submissions
01 33 00 - 3
DAP SUBMITTALS
Page 3 of 8
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102561
Revised August 30, 2013
1 2. The Project title and number
2 3. Contractor identification
3 4. The names of:
4 a. Contractor
5 b. Supplier
6 c. Manufacturer
7 5. Identification of the product, with the Specification Section number, page and
8 paragraph(s)
9 6. Field dimensions, clearly identified as such
10 7. Relation to adjacent or critical features of the Work or materials
11 8. Applicable standards, such as ASTM or Federal Specification numbers
12 9. Identification by highlighting of deviations from Contract Documents
13 10. Identification by highlighting of revisions on resubmittals
14 11. An 8-inch x 3-inch blank space for Contractor and City stamps
15 F. Shop Drawings
16 1. As specified in individual Work Sections includes, but is not necessarily limited to:
17 a. Custom-prepared data such as fabrication and erection/installation (working)
18 drawings
19 b. Scheduled information
20 c. Setting diagrams
21 d. Actual shopwork manufacturing instructions
22 e. Custom templates
23 f. Special wiring diagrams
24 g. Coordination drawings
25 h. Individual system or equipment inspection and test reports including:
26 1) Performance curves and certifications
27 i. As applicable to the Work
28 2. Details
29 a. Relation of the various parts to the main members and lines of the structure
30 b. Where correct fabrication of the Work depends upon field measurements
31 1) Provide such measurements and note on the drawings prior to submitting
32 for approval.
33 G. Product Data
34 1. For submittals of product data for products included on the City’s Standard Product
35 List, clearly identify each item selected for use on the Project.
36 2. For submittals of product data for products not included on the City’s Standard
37 Product List, submittal data may include, but is not necessarily limited to:
38 a. Standard prepared data for manufactured products (sometimes referred to as
39 catalog data)
40 1) Such as the manufacturer's product specification and installation
41 instructions
42 2) Availability of colors and patterns
43 3) Manufacturer's printed statements of compliances and applicability
44 4) Roughing-in diagrams and templates
45 5) Catalog cuts
46 6) Product photographs
01 33 00 - 4
DAP SUBMITTALS
Page 4 of 8
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102561
Revised August 30, 2013
1 7) Standard wiring diagrams
2 8) Printed performance curves and operational-range diagrams
3 9) Production or quality control inspection and test reports and certifications
4 10) Mill reports
5 11) Product operating and maintenance instructions and recommended
6 spare-parts listing and printed product warranties
7 12) As applicable to the Work
8 H. Samples
9 1. As specified in individual Sections, include, but are not necessarily limited to:
10 a. Physical examples of the Work such as:
11 1) Sections of manufactured or fabricated Work
12 2) Small cuts or containers of materials
13 3) Complete units of repetitively used products color/texture/pattern swatches
14 and range sets
15 4) Specimens for coordination of visual effect
16 5) Graphic symbols and units of Work to be used by the City for independent
17 inspection and testing, as applicable to the Work
18 I. Do not start Work requiring a shop drawing, sample or product data nor any material to
19 be fabricated or installed prior to the approval or qualified approval of such item.
20 1. Fabrication performed, materials purchased or on-site construction accomplished
21 which does not conform to approved shop drawings and data is at the Contractor's
22 risk.
23 2. The City will not be liable for any expense or delay due to corrections or remedies
24 required to accomplish conformity.
25 3. Complete project Work, materials, fabrication, and installations in conformance
26 with approved shop drawings, applicable samples, and product data.
27 J. Submittal Distribution
28 1. Electronic Distribution
29 a. Confirm development of Project directory for electronic submittals to be
30 uploaded to City’s Buzzsaw site, or another external FTP site approved by the
31 City.
32 b. Shop Drawings
33 1) Upload submittal to designated project directory and notify appropriate
34 City representatives via email of submittal posting.
35 2) Hard Copies
36 a) 3 copies for all submittals
37 b) If Contractor requires more than 1 hard copy of Shop Drawings
38 returned, Contractor shall submit more than the number of copies listed
39 above.
40 c. Product Data
41 1) Upload submittal to designated project directory and notify appropriate
42 City representatives via email of submittal posting.
43 2) Hard Copies
44 a) 3 copies for all submittals
45 d. Samples
46 1) Distributed to the Project Representative
47 2. Hard Copy Distribution (if required in lieu of electronic distribution)
01 33 00 - 5
DAP SUBMITTALS
Page 5 of 8
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102561
Revised August 30, 2013
1 a. Shop Drawings
2 1) Distributed to the City
3 2) Copies
4 a) 8 copies for mechanical submittals
5 b) 7 copies for all other submittals
6 c) If Contractor requires more than 3 copies of Shop Drawings returned,
7 Contractor shall submit more than the number of copies listed above.
8 b. Product Data
9 1) Distributed to the City
10 2) Copies
11 a) 4 copies
12 c. Samples
13 1) Distributed to the Project Representative
14 2) Copies
15 a) Submit the number stated in the respective Specification Sections.
16 3. Distribute reproductions of approved shop drawings and copies of approved
17 product data and samples, where required, to the job site file and elsewhere as
18 directed by the City.
19 a. Provide number of copies as directed by the City but not exceeding the number
20 previously specified.
21 K. Submittal Review
22 1. The review of shop drawings, data and samples will be for general conformance
23 with the design concept and Contract Documents. This is not to be construed as:
24 a. Permitting any departure from the Contract requirements
25 b. Relieving the Contractor of responsibility for any errors, including details,
26 dimensions, and materials
27 c. Approving departures from details furnished by the City, except as otherwise
28 provided herein
29 2. The review and approval of shop drawings, samples or product data by the City
30 does not relieve the Contractor from his/her responsibility with regard to the
31 fulfillment of the terms of the Contract.
32 a. All risks of error and omission are assumed by the Contractor, and the City will
33 have no responsibility therefore.
34 3. The Contractor remains responsible for details and accuracy, for coordinating the
35 Work with all other associated work and trades, for selecting fabrication processes,
36 for techniques of assembly and for performing Work in a safe manner.
37 4. If the shop drawings, data or samples as submitted describe variations and show a
38 departure from the Contract requirements which City finds to be in the interest of
39 the City and to be so minor as not to involve a change in Contract Price or time for
40 performance, the City may return the reviewed drawings without noting an
41 exception.
42 5. Submittals will be returned to the Contractor under 1 of the following codes:
43 a. Code 1
44 1) "NO EXCEPTIONS TAKEN" is assigned when there are no notations or
45 comments on the submittal.
46 a) When returned under this code the Contractor may release the
47 equipment and/or material for manufacture.
48 b. Code 2
01 33 00 - 6
DAP SUBMITTALS
Page 6 of 8
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102561
Revised August 30, 2013
1 1) "EXCEPTIONS NOTED". This code is assigned when a confirmation of
2 the notations and comments IS NOT required by the Contractor.
3 a) The Contractor may release the equipment or material for manufacture;
4 however, all notations and comments must be incorporated into the
5 final product.
6 c. Code 3
7 1) "EXCEPTIONS NOTED/RESUBMIT". This combination of codes is
8 assigned when notations and comments are extensive enough to require a
9 resubmittal of the package.
10 a) The Contractor may release the equipment or material for manufacture;
11 however, all notations and comments must be incorporated into the
12 final product.
13 b) This resubmittal is to address all comments, omissions and
14 non-conforming items that were noted.
15 c) Resubmittal is to be received by the City within 15 Calendar Days of
16 the date of the City's transmittal requiring the resubmittal.
17 d. Code 4
18 1) "NOT APPROVED" is assigned when the submittal does not meet the
19 intent of the Contract Documents.
20 a) The Contractor must resubmit the entire package revised to bring the
21 submittal into conformance.
22 b) It may be necessary to resubmit using a different manufacturer/vendor
23 to meet the Contract Documents.
24 6. Resubmittals
25 a. Handled in the same manner as first submittals
26 1) Corrections other than requested by the City
27 2) Marked with revision triangle or other similar method
28 a) At Contractor’s risk if not marked
29 b. Submittals for each item will be reviewed no more than twice at the City’s
30 expense.
31 1) All subsequent reviews will be performed at times convenient to the City
32 and at the Contractor's expense, based on the City's or City
33 Representative’s then prevailing rates.
34 2) Provide Contractor reimbursement to the City within 30 Calendar Days for
35 all such fees invoiced by the City.
36 c. The need for more than 1 resubmission or any other delay in obtaining City's
37 review of submittals, will not entitle the Contractor to an extension of Contract
38 Time.
39 7. Partial Submittals
40 a. City reserves the right to not review submittals deemed partial, at the City’s
41 discretion.
42 b. Submittals deemed by the City to be not complete will be returned to the
43 Contractor, and will be considered "Not Approved" until resubmitted.
44 c. The City may at its option provide a list or mark the submittal directing the
45 Contractor to the areas that are incomplete.
46 8. If the Contractor considers any correction indicated on the shop drawings to
47 constitute a change to the Contract Documents, then written notice must be
48 provided thereof to the Developer at least 7 Calendar Days prior to release for
49 manufacture.
01 33 00 - 7
DAP SUBMITTALS
Page 7 of 8
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102561
Revised August 30, 2013
1 9. When the shop drawings have been completed to the satisfaction of the City, the
2 Contractor may carry out the construction in accordance therewith and no further
3 changes therein except upon written instructions from the City.
4 10. Each submittal, appropriately coded, will be returned within 30 Calendar Days
5 following receipt of submittal by the City.
6 L. Mock ups
7 1. Mock Up units as specified in individual Sections, include, but are not necessarily
8 limited to, complete units of the standard of acceptance for that type of Work to be
9 used on the Project. Remove at the completion of the Work or when directed.
10 M. Qualifications
11 1. If specifically required in other Sections of these Specifications, submit a P.E.
12 Certification for each item required.
13 N. Request for Information (RFI)
14 1. Contractor Request for additional information
15 a. Clarification or interpretation of the contract documents
16 b. When the Contractor believes there is a conflict between Contract Documents
17 c. When the Contractor believes there is a conflict between the Drawings and
18 Specifications
19 1) Identify the conflict and request clarification
20 2. Sufficient information shall be attached to permit a written response without further
21 information.
22
23
24
25
26 1.5 SUBMITTALS [NOT USED]
27 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
28 1.7 CLOSEOUT SUBMITTALS [NOT USED]
29 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
30 1.9 QUALITY ASSURANCE [NOT USED]
31 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
32 1.11 FIELD [SITE] CONDITIONS [NOT USED]
33 1.12 WARRANTY [NOT USED]
01 33 00 - 8
DAP SUBMITTALS
Page 8 of 8
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102561
Revised August 30, 2013
1 PART 2 - PRODUCTS [NOT USED]
2 PART 3 - EXECUTION [NOT USED]
3 END OF SECTION
4
Revision Log
DATE NAME SUMMARY OF CHANGE
5
01 45 23
DAP TESTING AND INSPECTION SERVICES
Page 1 of 3
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102561
Revised March 20, 2020
SECTION 01 45 23
TESTING AND INSPECTION SERVICES
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Testing and inspection services procedures and coordination
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the
Contract
2. Division 1 – General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various Items
bid. No separate payment will be allowed for this Item.
a. Contractor is responsible for performing, coordinating, and payment of
all Quality Control testing.
b. City is responsible for performing and payment for first set of Quality
Assurance testing.
1) If the first Quality Assurance test performed by the City fails, the
Contractor is responsible for payment of subsequent Quality
Assurance testing until a passing test occurs.
a) Final acceptance will not be issued by City until all required
payments for testing by Contractor have been paid in full.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. Testing
1. Complete testing in accordance with the Contract Documents.
2. Coordination
a. When testing is required to be performed by the City, notify City,
sufficiently in advance, when testing is needed.
b. When testing is required to be completed by the Contractor, notify City,
sufficiently in advance, that testing will be performed.
3. Distribution of Testing Reports
a. Electronic Distribution
01 45 23
DAP TESTING AND INSPECTION SERVICES
Page 2 of 3
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102561
Revised March 20, 2020
1) Confirm development of Project directory for electronic submittals
to be uploaded to the City’s document management system, or
another form of distribution approved by the City.
2) Upload test reports to designated project directory and notify
appropriate City representatives via email of submittal posting.
3) Hard Copies
a) 1 copy for all submittals submitted to the Project
Representative
b. Hard Copy Distribution (if required in lieu of electronic distribution)
1) Tests performed by City
a) Distribute 1 hard copy to the Contractor
2) Tests performed by the Contractor
a) Distribute 3 hard copies to City’s Project Representative
4. Provide City’s Project Representative with trip tickets for each delivered
load of Concrete or Lime material including the following information:
a. Name of pit
b. Date of delivery
c. Material delivered
B. Inspection
1. Inspection or lack of inspection does not relieve the Contractor from
obligation to perform work in accordance with the Contract Documents.
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
01 45 23
DAP TESTING AND INSPECTION SERVICES
Page 3 of 3
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102561
Revised March 20, 2020
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
03/20/2020 D.V. Magaña Removed reference to Buzzsaw and noted that electronic submittals be uploaded
through the City’s document management system.
01 55 26 - 1
DAP STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL
Page 1 of 3
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102561
Revised July 1, 2011
1 SECTION 01 55 26
2 STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL
3 PART 1 - GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. Administrative procedures for:
7 a. Street Use Permit
8 b. Modification of approved traffic control
9 c. Removal of Street Signs
10 B. Deviations from this City of Fort Worth Standard Specification
11 1. None.
12 C. Related Specification Sections include, but are not necessarily limited to:
13 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
14 2. Division 1 – General Requirements
15 3. Section 34 71 13 – Traffic Control
16 1.2 PRICE AND PAYMENT PROCEDURES
17 A. Measurement and Payment
18 1. Work associated with this Item is considered subsidiary to the various Items bid.
19 No separate payment will be allowed for this Item.
20 1.3 REFERENCES
21 A. Reference Standards
22 1. Reference standards cited in this specification refer to the current reference standard
23 published at the time of the latest revision date logged at the end of this
24 specification, unless a date is specifically cited.
25 2. Texas Manual on Uniform Traffic Control Devices (TMUTCD).
26 1.4 ADMINISTRATIVE REQUIREMENTS
27 A. Traffic Control
28 1. General
29 a. When traffic control plans are included in the Drawings, provide Traffic
30 Control in accordance with Drawings and Section 34 71 13.
31 b. When traffic control plans are not included in the Drawings, prepare traffic
32 control plans in accordance with Section 34 71 13 and submit to City for
33 review.
34 1) Allow minimum 10 working days for review of proposed Traffic Control.
35 B. Street Use Permit
36 1. Prior to installation of Traffic Control, a City Street Use Permit is required.
37 a. To obtain Street Use Permit, submit Traffic Control Plans to City
38 Transportation and Public Works Department.
01 55 26 - 2
DAP STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL
Page 2 of 3
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102561
Revised July 1, 2011
1 1) Allow a minimum of 5 working days for permit review.
2 2) Contractor’s responsibility to coordinate review of Traffic Control plans for
3 Street Use Permit, such that construction is not delayed.
4 C. Modification to Approved Traffic Control
5 1. Prior to installation traffic control:
6 a. Submit revised traffic control plans to City Department Transportation and
7 Public Works Department.
8 1) Revise Traffic Control plans in accordance with Section 34 71 13.
9 2) Allow minimum 5 working days for review of revised Traffic Control.
10 3) It is the Contractor’s responsibility to coordinate review of Traffic Control
11 plans for Street Use Permit, such that construction is not delayed.
12 D. Removal of Street Sign
13 1. If it is determined that a street sign must be removed for construction, then contact
14 City Transportation and Public Works Department, Signs and Markings Division to
15 remove the sign.
16 E. Temporary Signage
17 1. In the case of regulatory signs, replace permanent sign with temporary sign meeting
18 requirements of the latest edition of the Texas Manual on Uniform Traffic Control
19 Devices (MUTCD).
20 2. Install temporary sign before the removal of permanent sign.
21 3. When construction is complete, to the extent that the permanent sign can be
22 reinstalled, contact the City Transportation and Public Works Department, Signs
23 and Markings Division, to reinstall the permanent sign.
24 F. Traffic Control Standards
25 1. Traffic Control Standards can be found on the City’s Buzzsaw website.
26 1.5 SUBMITTALS [NOT USED]
27 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
28 1.7 CLOSEOUT SUBMITTALS [NOT USED]
29 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
30 1.9 QUALITY ASSURANCE [NOT USED]
31 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
32 1.11 FIELD [SITE] CONDITIONS [NOT USED]
33 1.12 WARRANTY [NOT USED]
34 PART 2 - PRODUCTS [NOT USED]
35 PART 3 - EXECUTION [NOT USED]
36 END OF SECTION
01 55 26 - 3
DAP STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL
Page 3 of 3
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102561
Revised July 1, 2011
1
Revision Log
DATE NAME SUMMARY OF CHANGE
2
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102561
Revised March 20, 2020
01 60 00
DAP PRODUCT REQUIREMENTS
Page 1 of 2
SECTION 01 60 00
PRODUCT REQUIREMENTS
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. References for Product Requirements and City Standard Products List
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
1.2 PRICE AND PAYMENT PROCEDURES [NOT USED]
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A list of City approved products for use is available through the City’s website at:
https://apps.fortworthtexas.gov/ProjectResources/ and following the directory
path: 02 - Construction Documents\Standard Products List
A. Only products specifically included on City’s Standard Product List in these Contract
Documents shall be allowed for use on the Project.
1. Any subsequently approved products will only be allowed for use upon specific
approval by the City.
B. Any specific product requirements in the Contract Documents supersede similar
products included on the City’s Standard Product List.
1. The City reserves the right to not allow products to be used for certain projects even
though the product is listed on the City’s Standard Product List.
C. Although a specific product is included on City’s Standard Product List, not all products
from that manufacturer are approved for use, including but not limited to, that
manufacturer’s standard product.
D. See Section 01 33 00 for submittal requirements of Product Data included on City’s
Standard Product List.
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102561
Revised March 20, 2020
10 60 00
DAP PRODUCT REQUIREMENTS
Page 2 of 2
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
10/12/12 D. Johnson Modified Location of City’s Standard Product List
4/7/2014 M.Domenech Revised for DAP application
03/20/2020 D.V. Magaña Removed reference to Buzzsaw and noted that the City approved products list is
accessible through the City’s website.
01 66 00 - 1
DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS
Page 1 of 4
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102561
Revised April 7, 2014
1 SECTION 01 66 00
2 PRODUCT STORAGE AND HANDLING REQUIREMENTS
3 PART 1 - GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. Scheduling of product delivery
7 2. Packaging of products for delivery
8 3. Protection of products against damage from:
9 a. Handling
10 b. Exposure to elements or harsh environments
11 B. Deviations from this City of Fort Worth Standard Specification
12 1. None.
13 C. Related Specification Sections include, but are not necessarily limited to:
14 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
15 2. Division 1 – General Requirements
16 1.2 PRICE AND PAYMENT PROCEDURES
17 A. Measurement and Payment
18 1. Work associated with this Item is considered subsidiary to the various Items bid.
19 No separate payment will be allowed for this Item.
20 1.3 REFERENCES [NOT USED]
21 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED]
22 1.5 SUBMITTALS [NOT USED]
23 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
24 1.7 CLOSEOUT SUBMITTALS [NOT USED]
25 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
26 1.9 QUALITY ASSURANCE [NOT USED]
27 1.10 DELIVERY AND HANDLING
28 A. Delivery Requirements
29 1. Schedule delivery of products or equipment as required to allow timely installation
30 and to avoid prolonged storage.
31 2. Provide appropriate personnel and equipment to receive deliveries.
32 3. Delivery trucks will not be permitted to wait extended periods of time on the Site
33 for personnel or equipment to receive the delivery.
01 66 00 - 2
DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS
Page 2 of 4
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102561
Revised April 7, 2014
1 4. Deliver products or equipment in manufacturer's original unbroken cartons or other
2 containers designed and constructed to protect the contents from physical or
3 environmental damage.
4 5. Clearly and fully mark and identify as to manufacturer, item and installation
5 location.
6 6. Provide manufacturer's instructions for storage and handling.
7 B. Handling Requirements
8 1. Handle products or equipment in accordance with these Contract Documents and
9 manufacturer’s recommendations and instructions.
10 C. Storage Requirements
11 1. Store materials in accordance with manufacturer’s recommendations and
12 requirements of these Specifications.
13 2. Make necessary provisions for safe storage of materials and equipment.
14 a. Place loose soil materials and materials to be incorporated into Work to prevent
15 damage to any part of Work or existing facilities and to maintain free access at
16 all times to all parts of Work and to utility service company installations in
17 vicinity of Work.
18 3. Keep materials and equipment neatly and compactly stored in locations that will
19 cause minimum inconvenience to other contractors, public travel, adjoining owners,
20 tenants and occupants.
21 a. Arrange storage to provide easy access for inspection.
22 4. Restrict storage to areas available on construction site for storage of material and
23 equipment as shown on Drawings, or approved by City’s Project Representative.
24 5. Provide off-site storage and protection when on-site storage is not adequate.
25 a. Provide addresses of and access to off-site storage locations for inspection by
26 City’s Project Representative.
27 6. Do not use lawns, grass plots or other private property for storage purposes without
28 written permission of owner or other person in possession or control of premises.
29 7. Store in manufacturers’ unopened containers.
30 8. Neatly, safely and compactly stack materials delivered and stored along line of
31 Work to avoid inconvenience and damage to property owners and general public
32 and maintain at least 3 feet from fire hydrant.
33 9. Keep public and private driveways and street crossings open.
34 10. Repair or replace damaged lawns, sidewalks, streets or other improvements to
35 satisfaction of City’s Project Representative.
36 a. Total length which materials may be distributed along route of construction at
37 one time is 1,000 linear feet, unless otherwise approved in writing by City’s
38 Project Representative.
01 66 00 - 3
DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS
Page 3 of 4
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102561
Revised April 7, 2014
1 1.11 FIELD [SITE] CONDITIONS [NOT USED]
2 1.12 WARRANTY [NOT USED]
3 PART 2 - PRODUCTS [NOT USED]
4 PART 3 - EXECUTION
5 3.1 INSTALLERS [NOT USED]
6 3.2 EXAMINATION [NOT USED]
7 3.3 PREPARATION [NOT USED]
8 3.4 ERECTION [NOT USED]
9 3.5 REPAIR / RESTORATION [NOT USED]
10 3.6 RE-INSTALLATION [NOT USED]
11 3.7 FIELD [OR] SITE QUALITY CONTROL
12 A. Tests and Inspections
13 1. Inspect all products or equipment delivered to the site prior to unloading.
14 B. Non-Conforming Work
15 1. Reject all products or equipment that are damaged, used or in any other way
16 unsatisfactory for use on the project.
17 3.8 SYSTEM STARTUP [NOT USED]
18 3.9 ADJUSTING [NOT USED]
19 3.10 CLEANING [NOT USED]
20 3.11 CLOSEOUT ACTIVITIES [NOT USED]
21 3.12 PROTECTION
22 A. Protect all products or equipment in accordance with manufacturer's written directions.
23 B. Store products or equipment in location to avoid physical damage to items while in
24 storage.
25 C. Protect equipment from exposure to elements and keep thoroughly dry if required by
26 the manufacturer.
27 3.13 MAINTENANCE [NOT USED]
28 3.14 ATTACHMENTS [NOT USED]
29 END OF SECTION
30
01 66 00 - 4
DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS
Page 4 of 4
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102561
Revised April 7, 2014
Revision Log
DATE NAME SUMMARY OF CHANGE
1
01 70 00 - 1
DAP MOBILIZATION AND REMOBILIZATION
Page 1 of 4
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102561
Revised April 7, 2014
SECTION 01 70 00 1
MOBILIZATION AND REMOBILIZATION 2
PART 1 - GENERAL 3
1.1 SUMMARY 4
A. Section Includes: 5
1. Mobilization and Demobilization 6
a. Mobilization 7
1) Transportation of Contractor’s personnel, equipment, and operating supplies 8
to the Site 9
2) Establishment of necessary general facilities for the Contractor’s operation 10
at the Site 11
3) Premiums paid for performance and payment bonds 12
4) Transportation of Contractor’s personnel, equipment, and operating supplies 13
to another location within the designated Site 14
5) Relocation of necessary general facilities for the Contractor’s operation 15
from 1 location to another location on the Site. 16
b. Demobilization 17
1) Transportation of Contractor’s personnel, equipment, and operating supplies 18
away from the Site including disassembly 19
2) Site Clean-up 20
3) Removal of all buildings and/or other facilities assembled at the Site for this 21
Contract 22
c. Mobilization and Demobilization do not include activities for specific items of 23
work that are for which payment is provided elsewhere in the contract. 24
2. Remobilization 25
a. Remobilization for Suspension of Work specifically required in the Contract 26
Documents or as required by City includes: 27
1) Demobilization 28
a) Transportation of Contractor’s personnel, equipment, and operating 29
supplies from the Site including disassembly or temporarily securing 30
equipment, supplies, and other facilities as designated by the Contract 31
Documents necessary to suspend the Work. 32
b) Site Clean-up as designated in the Contract Documents 33
2) Remobilization 34
a) Transportation of Contractor’s personnel, equipment, and operating 35
supplies to the Site necessary to resume the Work. 36
b) Establishment of necessary general facilities for the Contractor’s 37
operation at the Site necessary to resume the Work. 38
3) No Payments will be made for: 39
a) Mobilization and Demobilization from one location to another on the 40
Site in the normal progress of performing the Work. 41
b) Stand-by or idle time 42
c) Lost profits 43
3. Mobilizations and Demobilization for Miscellaneous Projects 44
a. Mobilization and Demobilization 45
01 70 00 - 2
DAP MOBILIZATION AND REMOBILIZATION
Page 2 of 4
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102561
Revised April 7, 2014
1) Mobilization shall consist of the activities and cost on a Work Order basis 1
necessary for: 2
a) Transportation of Contractor’s personnel, equipment, and operating 3
supplies to the Site for the issued Work Order. 4
b) Establishment of necessary general facilities for the Contractor’s 5
operation at the Site for the issued Work Order 6
2) Demobilization shall consist of the activities and cost necessary for: 7
a) Transportation of Contractor’s personnel, equipment, and operating 8
supplies from the Site including disassembly for each issued Work 9
Order 10
b) Site Clean-up for each issued Work Order 11
c) Removal of all buildings or other facilities assembled at the Site for 12
each Work Oder 13
b. Mobilization and Demobilization do not include activities for specific items of 14
work for which payment is provided elsewhere in the contract. 15
4. Emergency Mobilizations and Demobilization for Miscellaneous Projects 16
a. A Mobilization for Miscellaneous Projects when directed by the City and the 17
mobilization occurs within 24 hours of the issuance of the Work Order. 18
B. Deviations from this City of Fort Worth Standard Specification 19
1. None. 20
C. Related Specification Sections include, but are not necessarily limited to: 21
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 22
2. Division 1 – General Requirements 23
1.2 PRICE AND PAYMENT PROCEDURES 24
A. Measurement and Payment 25
1. Mobilization and Demobilization 26
a. Measure 27
1) This Item is considered subsidiary to the various Items bid. 28
b. Payment 29
1) The work performed and materials furnished in accordance with this Item 30
are subsidiary to the various Items bid and no other compensation will be 31
allowed. 32
2. Remobilization for suspension of Work as specifically required in the Contract 33
Documents 34
a. Measurement 35
1) Measurement for this Item shall be per each remobilization performed. 36
b. Payment 37
1) The work performed and materials furnished in accordance with this Item 38
and measured as provided under “Measurement” will be paid for at the unit 39
price per each “Specified Remobilization” in accordance with Contract 40
Documents. 41
c. The price shall include: 42
1) Demobilization as described in Section 1.1.A.2.a.1) 43
2) Remobilization as described in Section 1.1.A.2.a.2) 44
d. No payments will be made for standby, idle time, or lost profits associated this 45
Item. 46
01 70 00 - 3
DAP MOBILIZATION AND REMOBILIZATION
Page 3 of 4
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102561
Revised April 7, 2014
3. Remobilization for suspension of Work as required by City 1
a. Measurement and Payment 2
1) This shall be submitted as a Contract Claim in accordance with Article 10 3
of Section 00 72 00. 4
2) No payments will be made for standby, idle time, or lost profits associated 5
with this Item. 6
4. Mobilizations and Demobilizations for Miscellaneous Projects 7
a. Measurement 8
1) Measurement for this Item shall be for each Mobilization and 9
Demobilization required by the Contract Documents 10
b. Payment 11
1) The Work performed and materials furnished in accordance with this Item 12
and measured as provided under “Measurement” will be paid for at the unit 13
price per each “Work Order Mobilization” in accordance with Contract 14
Documents. Demobilization shall be considered subsidiary to mobilization 15
and shall not be paid for separately. 16
c. The price shall include: 17
1) Mobilization as described in Section 1.1.A.3.a.1) 18
2) Demobilization as described in Section 1.1.A.3.a.2) 19
d. No payments will be made for standby, idle time, or lost profits associated this 20
Item. 21
5. Emergency Mobilizations and Demobilizations for Miscellaneous Projects 22
a. Measurement 23
1) Measurement for this Item shall be for each Mobilization and 24
Demobilization required by the Contract Documents 25
b. Payment 26
1) The Work performed and materials furnished in accordance with this Item 27
and measured as provided under “Measurement” will be paid for at the unit 28
price per each “Work Order Emergency Mobilization” in accordance with 29
Contract Documents. Demobilization shall be considered subsidiary to 30
mobilization and shall not be paid for separately. 31
c. The price shall include 32
1) Mobilization as described in Section 1.1.A.4.a) 33
2) Demobilization as described in Section 1.1.A.3.a.2) 34
d. No payments will be made for standby, idle time, or lost profits associated this 35
Item. 36
1.3 REFERENCES [NOT USED] 37
1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 38
1.5 SUBMITTALS [NOT USED] 39
1.6 INFORMATIONAL SUBMITTALS [NOT USED] 40
1.7 CLOSEOUT SUBMITTALS [NOT USED] 41
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 42
1.9 QUALITY ASSURANCE [NOT USED] 43
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 44
01 70 00 - 4
DAP MOBILIZATION AND REMOBILIZATION
Page 4 of 4
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102561
Revised April 7, 2014
1.11 FIELD [SITE] CONDITIONS [NOT USED] 1
1.12 WARRANTY [NOT USED] 2
PART 2 - PRODUCTS [NOT USED] 3
PART 3 - EXECUTION [NOT USED] 4
END OF SECTION 5
6
Revision Log
DATE NAME SUMMARY OF CHANGE
7
01 71 23 - 1
CONSTRUCTION STAKING AND SURVEY
Page 1 of 8
CITY OF FORT WORTH Carter Park East Phase III & IV
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102808
Revised February 14, 2018
1 SECTION 01 71 23
2 CONSTRUCTION STAKING AND SURVEY
3 PART 1 - GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. Requirements for construction staking and construction survey
7 B. Deviations from this City of Fort Worth Standard Specification
8 1. See Changes (Highlighted in Yellow).
9 C. Related Specification Sections include, but are not necessarily limited to:
10 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
11 2. Division 1 – General Requirements
12 1.2 PRICE AND PAYMENT PROCEDURES
13 A. Measurement and Payment
14 1. Construction Staking
15 a. Measurement
16 1) This Item is considered subsidiary to the various Items bid.
17 b. Payment
18 1) The work performed and the materials furnished in accordance with this
19 Item are subsidiary to the various Items bid and no other compensation will
20 be allowed.
21 2. Construction Survey
22 a. Measurement
23 1) This Item is considered subsidiary to the various Items bid.
24 b. Payment
25 1) The work performed and the materials furnished in accordance with this
26 Item are subsidiary to the various Items bid and no other compensation will be
27 allowed.
28 3. As-Built Survey
29 a. Measurement
30 1) This Item is considered subsidiary to the various Items bid.
31 b. Payment
32 1) The work performed and the materials furnished in accordance with this
33 Item are subsidiary to the various Items bid and no other compensation will be
34 allowed.
35
36
37
38
39
40
Water and Sewer to Serve The Library
102561
01 71 23 - 2
CONSTRUCTION STAKING AND SURVEY
Page 2 of 8
CITY OF FORT WORTH Carter Park East Phase III & IV
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102808
Revised February 14, 2018
1 1.3 REFERENCES
2 A. Definitions
3 1. Construction Survey - The survey measurements made prior to or while
4 construction is in progress to control elevation, horizontal position, dimensions and
5 configuration of structures/improvements included in the Project Drawings.
6 2. As-built Survey –The measurements made after the construction of the
7 improvement features are complete to provide position coordinates for the features
8 of a project.
9 3. Construction Staking – The placement of stakes and markings to provide offsets
10 and elevations to cut and fill in order to locate on the ground the designed
11 structures/improvements included in the Project Drawings. Construction staking
12 shall include staking easements and/or right of way if indicated on the plans.
13 4. Survey “Field Checks” – Measurements made after construction staking is
14 completed and before construction work begins to ensure that structures marked on
15 the ground are accurately located per Project Drawings.
16 B. Technical References
17 1. City of Fort Worth – Construction Staking Standards (available on City’s Buzzsaw
18 website) – 01 71 23.16.01_ Attachment A_Survey Staking Standards
19 2. City of Fort Worth - Standard Survey Data Collector Library (fxl) files (available
20 on City’s Buzzsaw website).
21 3. Texas Department of Transportation (TxDOT) Survey Manual, latest revision
22 4. Texas Society of Professional Land Surveyors (TSPS), Manual of Practice for Land
23 Surveying in the State of Texas, Category 5
24
25 1.4 ADMINISTRATIVE REQUIREMENTS
26 A. The Contractor’s selection of a surveyor must comply with Texas Government
27 Code 2254 (qualifications based selection) for this project.
28 1.5 SUBMITTALS
29 A. Submittals, if required, shall be in accordance with Section 01 33 00.
30 B. All submittals shall be received and reviewed by the City prior to delivery of work.
31 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS
32 A. Field Quality Control Submittals
33 1. Documentation verifying accuracy of field engineering work, including coordinate
34 conversions if plans do not indicate grid or ground coordinates.
35 2. Submit “Cut-Sheets” conforming to the standard template provided by the City
36 (refer to 01 71 23.16.01 – Attachment A – Survey Staking Standards).
37
38 1.7 CLOSEOUT SUBMITTALS
39 B. As-built Redline Drawing Submittal
Water and Sewer to Serve The Library
102561
01 71 23 - 3
CONSTRUCTION STAKING AND SURVEY
Page 3 of 8
CITY OF FORT WORTH Carter Park East Phase III & IV
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102808
Revised February 14, 2018
1 1. Submit As-Built Survey Redline Drawings documenting the locations/elevations of
2 constructed improvements signed and sealed by Registered Professional Land
3 Surveyor (RPLS) responsible for the work (refer to 01 71 23.16.01 – Attachment A
4 – Survey Staking Standards) .
5 2. Contractor shall submit the proposed as-built and completed redline drawing
6 submittal one (1) week prior to scheduling the project final inspection for City
7 review and comment. Revisions, if necessary, shall be made to the as-built redline
8 drawings and resubmitted to the City prior to scheduling the construction final
9 inspection.
10 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
11 1.9 QUALITY ASSURANCE
12 A. Construction Staking
13 1. Construction staking will be performed by the Contractor.
14 2. Coordination
15 a. Contact City and Developer’s Project Representative at least one week in
16 advance notifying the City of when Construction Staking is scheduled.
17 b. It is the Contractor’s responsibility to coordinate staking such that
18 construction activities are not delayed or negatively impacted.
19 3. General
20 a. Contractor is responsible for preserving and maintaining stakes. If City
21 surveyors or Developer’s Project Representative are required to re-stake for
22 any reason, the Contractor will be responsible for costs to perform staking. If
23 in the opinion of the City, a sufficient number of stakes or markings have been
24 lost, destroyed disturbed or omitted that the contracted Work cannot take place
25 then the Contractor will be required to stake or re-stake the deficient areas.
26 B. Construction Survey
27 1. Construction Survey will be performed by the Contractor.
28 2. Coordination
29 a. Contractor to verify that horizontal and vertical control data established in the
30 design survey and required for construction survey is available and in place.
31 3. General
32 a. Construction survey will be performed in order to construct the work shown
33 on the Construction Drawings and specified in the Contract Documents.
34 b. For construction methods other than open cut, the Contractor shall perform
35 construction survey and verify control data including, but not limited to, the
36 following:
37 1) Verification that established benchmarks and control are accurate.
38 2) Use of Benchmarks to furnish and maintain all reference lines and grades
39 for tunneling.
40 3) Use of line and grades to establish the location of the pipe.
41 4) Submit to the City copies of field notes used to establish all lines and
42 grades, if requested, and allow the City to check guidance system setup prior
43 to beginning each tunneling drive.
44 5) Provide access for the City, if requested, to verify the guidance system and
45 the line and grade of the carrier pipe.
Water and Sewer to Serve The Library
102561
01 71 23 - 4
CONSTRUCTION STAKING AND SURVEY
Page 4 of 8
CITY OF FORT WORTH Carter Park East Phase III & IV
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102808
Revised February 14, 2018
1 6) The Contractor remains fully responsible for the accuracy of the work and
2 correction of it, as required.
3 7) Monitor line and grade continuously during construction.
4 8) Record deviation with respect to design line and grade once at each pipe
5 joint and submit daily records to the City.
6 9) If the installation does not meet the specified tolerances (as outlined in
7 Sections 33 05 23 and/or 33 05 24), immediately notify the City and correct
8 the installation in accordance with the Contract Documents.
9 C. As-Built Survey
10 1. Required As-Built Survey will be performed by the Contractor.
11 2. Coordination
12 a. Contractor is to coordinate with City to confirm which features require as-
13 built surveying.
14 b. It is the Contractor’s responsibility to coordinate the as-built survey and
15 required measurements for items that are to be buried such that construction
16 activities are not delayed or negatively impacted.
17 c. For sewer mains and water mains 12” and under in diameter, it is acceptable
18 to physically measure depth and mark the location during the progress of
19 construction and take as-built survey after the facility has been buried. The
20 Contractor is responsible for the quality control needed to ensure accuracy.
21 3. General
22 a. The Contractor shall provide as-built survey including the elevation and
23 location (and provide written documentation to the City) of construction
24 features during the progress of the construction including the following:
25 1) Water Lines
26 a) Top of pipe elevations and coordinates for waterlines at the following
27 locations:
28 (1) Minimum every 250 linear feet, including
29 (2) Horizontal and vertical points of inflection, curvature,
30 etc.
31 (3) Fire line tee
32 (4) Plugs, stub-outs, dead-end lines
33 (5) Casing pipe (each end) and all buried fittings
34 2) Sanitary Sewer
35 a) Top of pipe elevations and coordinates for force mains and siphon
36 sanitary sewer lines (non-gravity facilities) at the following locations:
37 (1) Minimum every 250 linear feet and any buried fittings
38 (2) Horizontal and vertical points of inflection, curvature,
39 etc.
40 3) Stormwater – Not Applicable
41 b. The Contractor shall provide as-built survey including the elevation and
42 location (and provide written documentation to the City) of construction
43 features after the construction is completed including the following:
44 1) Manholes
45 a) Rim and flowline elevations and coordinates for each manhole
46 2) Water Lines
47 a) Cathodic protection test stations
48 b) Sampling stations
49 c) Meter boxes/vaults (All sizes)
Water and Sewer to Serve The Library
102561
01 71 23 - 5
CONSTRUCTION STAKING AND SURVEY
Page 5 of 8
CITY OF FORT WORTH Carter Park East Phase III & IV
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102808
Revised February 14, 2018
1 d) Fire hydrants
2 e) Valves (gate, butterfly, etc.)
3 f) Air Release valves (Manhole rim and vent pipe)
4 g) Blow off valves (Manhole rim and valve lid)
5 h) Pressure plane valves
6 i) Underground Vaults
7 (1) Rim and flowline elevations and coordinates for each
8 Underground Vault.
9 3) Sanitary Sewer
10 a) Cleanouts
11 (1) Rim and flowline elevations and coordinates for each
12 b) Manholes and Junction Structures
13 (1) Rim and flowline elevations and coordinates for each
14 manhole and junction structure.
15 4) Stormwater – Not Applicable
16 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
17 1.11 FIELD [SITE] CONDITIONS [NOT USED]
18 1.12 WARRANTY
19 PART 2 - PRODUCTS
20 A. A construction survey will produce, but will not be limited to:
21 1. Recovery of relevant control points, points of curvature and points of intersection.
22 2. Establish temporary horizontal and vertical control elevations (benchmarks)
23 sufficiently permanent and located in a manner to be used throughout construction.
24 3. The location of planned facilities, easements and improvements.
25 a. Establishing final line and grade stakes for piers, floors, grade beams, parking
26 areas, utilities, streets, highways, tunnels, and other construction.
27 b. A record of revisions or corrections noted in an orderly manner for reference.
28 c. A drawing, when required by the client, indicating the horizontal and vertical
29 location of facilities, easements and improvements, as built.
30 4. Cut sheets shall be provided to the City inspector and Survey Superintendent for all
31 construction staking projects. These cut sheets shall be on the standard city template
32 which can be obtained from the Survey Superintendent (817-392-7925).
33 5. Digital survey files in the following formats shall be acceptable:
34 a. AutoCAD (.dwg)
35 b. ESRI Shapefile (.shp)
36 c. CSV file (.csv), formatted with X and Y coordinates in separate columns (use
37 standard templates, if available)
38 6. Survey files shall include vertical and horizontal data tied to original project
39 control and benchmarks, and shall include feature descriptions
40 PART 3 - EXECUTION
41 3.1 INSTALLERS
Water and Sewer to Serve The Library
102561
01 71 23 - 6
CONSTRUCTION STAKING AND SURVEY
Page 6 of 8
CITY OF FORT WORTH Carter Park East Phase III & IV
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102808
Revised February 14, 2018
1 A. Tolerances:
2 1. The staked location of any improvement or facility should be as accurate as
3 practical and necessary. The degree of precision required is dependent on many
4 factors all of which must remain judgmental. The tolerances listed hereafter are
5 based on generalities and, under certain circumstances, shall yield to specific
6 requirements. The surveyor shall assess any situation by review of the overall plans
7 and through consultation with responsible parties as to the need for specific
8 tolerances.
9 a. Earthwork: Grades for earthwork or rough cut should not exceed 0.1 ft. vertical
10 tolerance. Horizontal alignment for earthwork and rough cut should not exceed
11 1.0 ft. tolerance.
12 b. Horizontal alignment on a structure shall be within .0.1ft tolerance.
13 c. Paving or concrete for streets, curbs, gutters, parking areas, drives, alleys and
14 walkways shall be located within the confines of the site boundaries and,
15 occasionally, along a boundary or any other restrictive line. Away from any
16 restrictive line, these facilities should be staked with an accuracy producing no
17 more than 0.05ft. tolerance from their specified locations.
18 d. Underground and overhead utilities, such as sewers, gas, water, telephone and
19 electric lines, shall be located horizontally within their prescribed areas or
20 easements. Within assigned areas, these utilities should be staked with an
21 accuracy producing no more than 0.1 ft tolerance from a specified location.
22 e. The accuracy required for the vertical location of utilities varies widely. Many
23 underground utilities require only a minimum cover and a tolerance of 0.1 ft.
24 should be maintained. Underground and overhead utilities on planned profile,
25 but not depending on gravity flow for performance, should not exceed 0.1 ft.
26 tolerance.
27 B. Surveying instruments shall be kept in close adjustment according to manufacturer’s
28 specifications or in compliance to standards. The City reserves the right to request a
29 calibration report at any time and recommends regular maintenance schedule be
30 performed by a certified technician every 6 months.
31 1. Field measurements of angles and distances shall be done in such fashion as to
32 satisfy the closures and tolerances expressed in Part 3.1.A.
33 2. Vertical locations shall be established from a pre-established benchmark and
34 checked by closing to a different bench mark on the same datum.
35 3. Construction survey field work shall correspond to the client’s plans. Irregularities
36 or conflicts found shall be reported promptly to the City.
37 4. Revisions, corrections and other pertinent data shall be logged for future reference.
38
39 3.2 EXAMINATION [NOT USED]
40 3.3 PREPARATION [NOT USED]
41 3.4 APPLICATION
42 3.5 REPAIR / RESTORATION
43 A. If the Contractor’s work damages or destroys one or more of the control
44 monuments/points set by the City or Developer’s Project Representative, the monuments
45 shall be adequately referenced for expedient restoration.
Water and Sewer to Serve The Library
102561
01 71 23 - 7
CONSTRUCTION STAKING AND SURVEY
Page 7 of 8
CITY OF FORT WORTH Carter Park East Phase III & IV
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102808
Revised February 14, 2018
1 1. Notify City or Developer’s Project Representative if any control data needs to be
2 restored or replaced due to damage caused during construction operations.
3 a. Contractor shall perform replacements and/or restorations.
4 b. The City or Developer’s Project Representative may require at any time a
5 survey “Field Check” of any monument or benchmarks that are set be verified
6 by the City surveyors or Developer’s Project Representative before further
7 associated work can move forward.
8 3.6 RE-INSTALLATION [NOT USED]
9 3.7 FIELD [OR] SITE QUALITY CONTROL
10 A. It is the Contractor’s responsibility to maintain all stakes and control data placed by the
11 City or Developer’s Project Representative in accordance with this Specification. This
12 includes easements and right of way, if noted on the plans.
13 B. Do not change or relocate stakes or control data without approval from the City.
14 3.8 SYSTEM STARTUP
15 A. Survey Checks
16 1. The City reserves the right to perform a Survey Check at any time deemed
17 necessary.
18 2. Checks by City personnel or 3rd party contracted surveyor are not intended to
19 relieve the contractor of his/her responsibility for accuracy.
20
21 3.9 ADJUSTING [NOT USED]
22 3.10 CLEANING [NOT USED]
23 3.11 CLOSEOUT ACTIVITIES [NOT USED]
24 3.12 PROTECTION [NOT USED]
25 3.13 MAINTENANCE [NOT USED]
26 3.14 ATTACHMENTS [NOT USED]
27 END OF SECTION
28
Revision Log
DATE NAME SUMMARY OF CHANGE
8/31/2012 D. Johnson
8/31/2017 M. Owen
Added instruction and modified measurement & payment under 1.2; added
definitions and references under 1.3; modified 1.6; added 1.7 closeout submittal
requirements; modified 1.9 Quality Assurance; added PART 2 – PRODUCTS ;
Added 3.1 Installers; added 3.5 Repair/Restoration; and added 3.8 System Startup.
2/14/2018 M Owen
Removed “blue text”; revised measurement and payment sections for Construction
Staking and As-Built Survey; added reference to selection compliance with TGC
2254; revised action and Closeout submittal requirements; added acceptable depth
Water and Sewer to Serve The Library
102561
01 71 23 - 8
CONSTRUCTION STAKING AND SURVEY
Page 8 of 8
CITY OF FORT WORTH Carter Park East Phase III & IV
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102808
Revised February 14, 2018
measurement criteria; revised list of items requiring as-built survey “during” and
“after” construction; and revised acceptable digital survey file format
1
Water and Sewer to Serve The Library
102561
01 74 23 - 1
DAP CLEANING
Page 1 of 4
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102561
Revised April 7, 2014
1 SECTION 01 74 23
2 CLEANING
3 PART 1 - GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. Intermediate and final cleaning for Work not including special cleaning of closed
7 systems specified elsewhere
8 B. Deviations from this City of Fort Worth Standard Specification
9 1. None.
10 C. Related Specification Sections include, but are not necessarily limited to:
11 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
12 2. Division 1 – General Requirements
13 3. Section 32 92 13 – Hydro-Mulching, Seeding and Sodding
14 1.2 PRICE AND PAYMENT PROCEDURES
15 A. Measurement and Payment
16 1. Work associated with this Item is considered subsidiary to the various Items bid.
17 No separate payment will be allowed for this Item.
18 1.3 REFERENCES [NOT USED]
19 1.4 ADMINISTRATIVE REQUIREMENTS
20 A. Scheduling
21 1. Schedule cleaning operations so that dust and other contaminants disturbed by
22 cleaning process will not fall on newly painted surfaces.
23 2. Schedule final cleaning upon completion of Work and immediately prior to final
24 inspection.
25 1.5 SUBMITTALS [NOT USED]
26 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
27 1.7 CLOSEOUT SUBMITTALS [NOT USED]
28 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
29 1.9 QUALITY ASSURANCE [NOT USED]
30 1.10 STORAGE, AND HANDLING
31 A. Storage and Handling Requirements
32 1. Store cleaning products and cleaning wastes in containers specifically designed for
33 those materials.
01 74 23 - 2
DAP CLEANING
Page 2 of 4
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102561
Revised April 7, 2014
1 1.11 FIELD [SITE] CONDITIONS [NOT USED]
2 1.12 WARRANTY [NOT USED]
3 PART 2 - PRODUCTS
4 2.1 OWNER-FURNISHED [OR] OWNER-SUPPLIEDPRODUCTS [NOT USED]
5 2.2 MATERIALS
6 A. Cleaning Agents
7 1. Compatible with surface being cleaned
8 2. New and uncontaminated
9 3. For manufactured surfaces
10 a. Material recommended by manufacturer
11 2.3 ACCESSORIES [NOT USED]
12 2.4 SOURCE QUALITY CONTROL [NOT USED]
13 PART 3 - EXECUTION
14 3.1 INSTALLERS [NOT USED]
15 3.2 EXAMINATION [NOT USED]
16 3.3 PREPARATION [NOT USED]
17 3.4 APPLICATION [NOT USED]
18 3.5 REPAIR / RESTORATION [NOT USED]
19 3.6 RE-INSTALLATION [NOT USED]
20 3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED]
21 3.8 SYSTEM STARTUP [NOT USED]
22 3.9 ADJUSTING [NOT USED]
23 3.10 CLEANING
24 A. General
25 1. Prevent accumulation of wastes that create hazardous conditions.
26 2. Conduct cleaning and disposal operations to comply with laws and safety orders of
27 governing authorities.
28 3. Do not dispose of volatile wastes such as mineral spirits, oil or paint thinner in
29 storm or sanitary drains or sewers.
30 4. Dispose of degradable debris at an approved solid waste disposal site.
31 5. Dispose of nondegradable debris at an approved solid waste disposal site or in an
32 alternate manner approved by City and regulatory agencies.
01 74 23 - 3
DAP CLEANING
Page 3 of 4
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102561
Revised April 7, 2014
1 6. Handle materials in a controlled manner with as few handlings as possible.
2 7. Thoroughly clean, sweep, wash and polish all Work and equipment associated with
3 this project.
4 8. Remove all signs of temporary construction and activities incidental to construction
5 of required permanent Work.
6 9. If project is not cleaned to the satisfaction of the City, the City reserves the right to
7 have the cleaning completed at the expense of the Contractor.
8 10. Do not burn on-site.
9 B. Intermediate Cleaning during Construction
10 1. Keep Work areas clean so as not to hinder health, safety or convenience of
11 personnel in existing facility operations.
12 2. At maximum weekly intervals, dispose of waste materials, debris and rubbish.
13 3. Confine construction debris daily in strategically located container(s):
14 a. Cover to prevent blowing by wind
15 b. Store debris away from construction or operational activities
16 c. Haul from site at a minimum of once per week
17 4. Vacuum clean interior areas when ready to receive finish painting.
18 a. Continue vacuum cleaning on an as-needed basis, until Final Acceptance.
19 5. Prior to storm events, thoroughly clean site of all loose or unsecured items, which
20 may become airborne or transported by flowing water during the storm.
21 C. Exterior (Site or Right of Way) Final Cleaning
22 1. Remove trash and debris containers from site.
23 a. Re-seed areas disturbed by location of trash and debris containers in accordance
24 with Section 32 92 13.
25 2. Sweep roadway to remove all rocks, pieces of asphalt, concrete or any other object
26 that may hinder or disrupt the flow of traffic along the roadway.
27 3. Clean any interior areas including, but not limited to, vaults, manholes, structures,
28 junction boxes and inlets.
29 4. If no longer required for maintenance of erosion facilities, and upon approval by
30 City, remove erosion control from site.
31 5. Clean signs, lights, signals, etc.
32 3.11 CLOSEOUT ACTIVITIES [NOT USED]
33 3.12 PROTECTION [NOT USED]
34 3.13 MAINTENANCE [NOT USED]
35 3.14 ATTACHMENTS [NOT USED]
36
37
38
39
40
01 74 23 - 4
DAP CLEANING
Page 4 of 4
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102561
Revised April 7, 2014
1 END OF SECTION
2
Revision Log
DATE NAME SUMMARY OF CHANGE
4/7/2014 M.Domenech Revised for DAP application
3
01 77 19 - 1
DAP CLOSEOUT REQUIREMENTS
Page 1 of 3
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102561
Revised April 7, 2014
1 SECTION 01 77 19
2 CLOSEOUT REQUIREMENTS
3 PART 1 - GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. The procedure for closing out a contract
7 B. Deviations from this City of Fort Worth Standard Specification
8 1. None.
9 C. Related Specification Sections include, but are not necessarily limited to:
10 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
11 2. Division 1 – General Requirements
12 1.2 PRICE AND PAYMENT PROCEDURES
13 A. Measurement and Payment
14 1. Work associated with this Item is considered subsidiary to the various Items bid.
15 No separate payment will be allowed for this Item.
16 1.3 REFERENCES [NOT USED]
17 1.4 ADMINISTRATIVE REQUIREMENTS
18 A. Guarantees, Bonds and Affidavits
19 1. No application for final payment will be accepted until all guarantees, bonds,
20 certificates, licenses and affidavits required for Work or equipment as specified are
21 satisfactorily filed with the City.
22 B. Release of Liens or Claims
23 1. No application for final payment will be accepted until satisfactory evidence of
24 release of liens has been submitted to the City.
25 1.5 SUBMITTALS
26 A. Submit all required documentation to City’s Project Representative.
01 77 19 - 2
DAP CLOSEOUT REQUIREMENTS
Page 2 of 3
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102561
Revised April 7, 2014
1 1.6 INFORMATIONAL SUBMITTALS [NOT USED]
2 1.7 CLOSEOUT SUBMITTALS [NOT USED]
3 PART 2 - PRODUCTS [NOT USED]
4 PART 3 - EXECUTION
5 3.1 INSTALLERS [NOT USED]
6 3.2 EXAMINATION [NOT USED]
7 3.3 PREPARATION [NOT USED]
8 3.4 CLOSEOUT PROCEDURE
9 A. Prior to requesting Final Inspection, submit:
10 1. Project Record Documents in accordance with Section 01 78 39
11 2. Operation and Maintenance Data, if required, in accordance with Section 01 78 23
12 B. Prior to requesting Final Inspection, perform final cleaning in accordance with Section
13 01 74 23.
14 C. Final Inspection
15 1. After final cleaning, provide notice to the City Project Representative that the Work
16 is completed.
17 a. The City will make an initial Final Inspection with the Contractor present.
18 b. Upon completion of this inspection, the City will notify the Contractor, in
19 writing within 10 business days, of any particulars in which this inspection
20 reveals that the Work is defective or incomplete.
21 2. Upon receiving written notice from the City, immediately undertake the Work
22 required to remedy deficiencies and complete the Work to the satisfaction of the
23 City.
24 3. Upon completion of Work associated with the items listed in the City's written
25 notice, inform the City, that the required Work has been completed. Upon receipt
26 of this notice, the City, in the presence of the Contractor, will make a subsequent
27 Final Inspection of the project.
28 4. Provide all special accessories required to place each item of equipment in full
29 operation. These special accessory items include, but are not limited to:
30 a. Specified spare parts
31 b. Adequate oil and grease as required for the first lubrication of the equipment
32 c. Initial fill up of all chemical tanks and fuel tanks
33 d. Light bulbs
34 e. Fuses
35 f. Vault keys
36 g. Handwheels
37 h. Other expendable items as required for initial start-up and operation of all
38 equipment
39 D. Notice of Project Completion
01 77 19 - 3
DAP CLOSEOUT REQUIREMENTS
Page 3 of 3
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102561
Revised April 7, 2014
1 1. Once the City Project Representative finds the Work subsequent to Final Inspection
2 to be satisfactory, the City will issue a Notice of Project Completion (Green Sheet).
3 E. Supporting Documentation
4 1. Coordinate with the City Project Representative to complete the following
5 additional forms:
6 a. Final Payment Request
7 b. Statement of Contract Time
8 c. Affidavit of Payment and Release of Liens
9 d. Consent of Surety to Final Payment
10 e. Pipe Report (if required)
11 f. Contractor’s Evaluation of City
12 g. Performance Evaluation of Contractor
13 F. Letter of Final Acceptance
14 1. Upon review and acceptance of Notice of Project Completion and Supporting
15 Documentation, in accordance with General Conditions, City will issue Letter of
16 Final Acceptance and release the Final Payment Request for payment.
17 3.5 REPAIR / RESTORATION [NOT USED]
18 3.6 RE-INSTALLATION [NOT USED]
19 3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED]
20 3.8 SYSTEM STARTUP [NOT USED]
21 3.9 ADJUSTING [NOT USED]
22 3.10 CLEANING [NOT USED]
23 3.11 CLOSEOUT ACTIVITIES [NOT USED]
24 3.12 PROTECTION [NOT USED]
25 3.13 MAINTENANCE [NOT USED]
26 3.14 ATTACHMENTS [NOT USED]
27 END OF SECTION
28
Revision Log
DATE NAME SUMMARY OF CHANGE
4/7/2014 M.Domenech Revised for DAP application
29
01 78 23 - 1
DAP OPERATION AND MAINTENANCE DATA
Page 1 of 5
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102561
Revised April 7, 2014
1 SECTION 01 78 23
2 OPERATION AND MAINTENANCE DATA
3 PART 1 - GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. Product data and related information appropriate for City's maintenance and
7 operation of products furnished under Contract
8 2. Such products may include, but are not limited to:
9 a. Traffic Controllers
10 b. Irrigation Controllers (to be operated by the City)
11 c. Butterfly Valves
12 B. Deviations from this City of Fort Worth Standard Specification
13 1. None.
14 C. Related Specification Sections include, but are not necessarily limited to:
15 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
16 2. Division 1 – General Requirements
17 1.2 PRICE AND PAYMENT PROCEDURES
18 A. Measurement and Payment
19 1. Work associated with this Item is considered subsidiary to the various Items bid.
20 No separate payment will be allowed for this Item.
21 1.3 REFERENCES [NOT USED]
22 1.4 ADMINISTRATIVE REQUIREMENTS
23 A. Schedule
24 1. Submit manuals in final form to the City within 30 calendar days of product
25 shipment to the project site.
26 1.5 SUBMITTALS
27 A. Submittals shall be in accordance with Section 01 33 00. All submittals shall be
28 approved by the City prior to delivery.
29 1.6 INFORMATIONAL SUBMITTALS
30 A. Submittal Form
31 1. Prepare data in form of an instructional manual for use by City personnel.
32 2. Format
33 a. Size: 8 ½ inches x 11 inches
34 b. Paper
35 1) 40 pound minimum, white, for typed pages
36 2) Holes reinforced with plastic, cloth or metal
37 c. Text: Manufacturer’s printed data, or neatly typewritten
01 78 23 - 2
DAP OPERATION AND MAINTENANCE DATA
Page 2 of 5
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102561
Revised April 7, 2014
1 d. Drawings
2 1) Provide reinforced punched binder tab, bind in with text
3 2) Reduce larger drawings and fold to size of text pages.
4 e. Provide fly-leaf for each separate product, or each piece of operating
5 equipment.
6 1) Provide typed description of product, and major component parts of
7 equipment.
8 2) Provide indexed tabs.
9 f. Cover
10 1) Identify each volume with typed or printed title "OPERATING AND
11 MAINTENANCE INSTRUCTIONS".
12 2) List:
13 a) Title of Project
14 b) Identity of separate structure as applicable
15 c) Identity of general subject matter covered in the manual
16 3. Binders
17 a. Commercial quality 3-ring binders with durable and cleanable plastic covers
18 b. When multiple binders are used, correlate the data into related consistent
19 groupings.
20 4. If available, provide an electronic form of the O&M Manual.
21 B. Manual Content
22 1. Neatly typewritten table of contents for each volume, arranged in systematic order
23 a. Contractor, name of responsible principal, address and telephone number
24 b. A list of each product required to be included, indexed to content of the volume
25 c. List, with each product:
26 1) The name, address and telephone number of the subcontractor or installer
27 2) A list of each product required to be included, indexed to content of the
28 volume
29 3) Identify area of responsibility of each
30 4) Local source of supply for parts and replacement
31 d. Identify each product by product name and other identifying symbols as set
32 forth in Contract Documents.
33 2. Product Data
34 a. Include only those sheets which are pertinent to the specific product.
35 b. Annotate each sheet to:
36 1) Clearly identify specific product or part installed
37 2) Clearly identify data applicable to installation
38 3) Delete references to inapplicable information
39 3. Drawings
40 a. Supplement product data with drawings as necessary to clearly illustrate:
41 1) Relations of component parts of equipment and systems
42 2) Control and flow diagrams
43 b. Coordinate drawings with information in Project Record Documents to assure
44 correct illustration of completed installation.
45 c. Do not use Project Record Drawings as maintenance drawings.
46 4. Written text, as required to supplement product data for the particular installation:
47 a. Organize in consistent format under separate headings for different procedures.
48 b. Provide logical sequence of instructions of each procedure.
01 78 23 - 3
DAP OPERATION AND MAINTENANCE DATA
Page 3 of 5
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102561
Revised April 7, 2014
1 5. Copy of each warranty, bond and service contract issued
2 a. Provide information sheet for City personnel giving:
3 1) Proper procedures in event of failure
4 2) Instances which might affect validity of warranties or bonds
5 C. Manual for Materials and Finishes
6 1. Submit 5 copies of complete manual in final form.
7 2. Content, for architectural products, applied materials and finishes:
8 a. Manufacturer's data, giving full information on products
9 1) Catalog number, size, composition
10 2) Color and texture designations
11 3) Information required for reordering special manufactured products
12 b. Instructions for care and maintenance
13 1) Manufacturer's recommendation for types of cleaning agents and methods
14 2) Cautions against cleaning agents and methods which are detrimental to
15 product
16 3) Recommended schedule for cleaning and maintenance
17 3. Content, for moisture protection and weather exposure products:
18 a. Manufacturer's data, giving full information on products
19 1) Applicable standards
20 2) Chemical composition
21 3) Details of installation
22 b. Instructions for inspection, maintenance and repair
23 D. Manual for Equipment and Systems
24 1. Submit 5 copies of complete manual in final form.
25 2. Content, for each unit of equipment and system, as appropriate:
26 a. Description of unit and component parts
27 1) Function, normal operating characteristics and limiting conditions
28 2) Performance curves, engineering data and tests
29 3) Complete nomenclature and commercial number of replaceable parts
30 b. Operating procedures
31 1) Start-up, break-in, routine and normal operating instructions
32 2) Regulation, control, stopping, shut-down and emergency instructions
33 3) Summer and winter operating instructions
34 4) Special operating instructions
35 c. Maintenance procedures
36 1) Routine operations
37 2) Guide to "trouble shooting"
38 3) Disassembly, repair and reassembly
39 4) Alignment, adjusting and checking
40 d. Servicing and lubrication schedule
41 1) List of lubricants required
42 e. Manufacturer's printed operating and maintenance instructions
43 f. Description of sequence of operation by control manufacturer
44 1) Predicted life of parts subject to wear
45 2) Items recommended to be stocked as spare parts
46 g. As installed control diagrams by controls manufacturer
47 h. Each contractor's coordination drawings
48 1) As installed color coded piping diagrams
01 78 23 - 4
DAP OPERATION AND MAINTENANCE DATA
Page 4 of 5
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102561
Revised April 7, 2014
1 i. Charts of valve tag numbers, with location and function of each valve
2 j. List of original manufacturer's spare parts, manufacturer's current prices, and
3 recommended quantities to be maintained in storage
4 k. Other data as required under pertinent Sections of Specifications
5 3. Content, for each electric and electronic system, as appropriate:
6 a. Description of system and component parts
7 1) Function, normal operating characteristics, and limiting conditions
8 2) Performance curves, engineering data and tests
9 3) Complete nomenclature and commercial number of replaceable parts
10 b. Circuit directories of panelboards
11 1) Electrical service
12 2) Controls
13 3) Communications
14 c. As installed color coded wiring diagrams
15 d. Operating procedures
16 1) Routine and normal operating instructions
17 2) Sequences required
18 3) Special operating instructions
19 e. Maintenance procedures
20 1) Routine operations
21 2) Guide to "trouble shooting"
22 3) Disassembly, repair and reassembly
23 4) Adjustment and checking
24 f. Manufacturer's printed operating and maintenance instructions
25 g. List of original manufacturer's spare parts, manufacturer's current prices, and
26 recommended quantities to be maintained in storage
27 h. Other data as required under pertinent Sections of Specifications
28 4. Prepare and include additional data when the need for such data becomes apparent
29 during instruction of City's personnel.
30 1.7 CLOSEOUT SUBMITTALS [NOT USED]
31 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
32 1.9 QUALITY ASSURANCE
33 A. Provide operation and maintenance data by personnel with the following criteria:
34 1. Trained and experienced in maintenance and operation of described products
35 2. Skilled as technical writer to the extent required to communicate essential data
36 3. Skilled as draftsman competent to prepare required drawings
01 78 23 - 5
DAP OPERATION AND MAINTENANCE DATA
Page 5 of 5
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102561
Revised April 7, 2014
1 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
2 1.11 FIELD [SITE] CONDITIONS [NOT USED]
3 1.12 WARRANTY [NOT USED]
4 PART 2 - PRODUCTS [NOT USED]
5 PART 3 - EXECUTION [NOT USED]
6 END OF SECTION
7
Revision Log
DATE NAME SUMMARY OF CHANGE
8/31/2012 D. Johnson 1.5.A.1 – title of section removed
4/7/2014 M.Domenech Revised for DAP Application
8
01 78 39 - 1
DAP PROJECT RECORD DOCUMENTS
Page 1 of 4
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102561
Revised April 7, 2014
1 SECTION 01 78 39
2 PROJECT RECORD DOCUMENTS
3 PART 1 - GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. Work associated with the documenting the project and recording changes to project
7 documents, including:
8 a. Record Drawings
9 b. Water Meter Service Reports
10 c. Sanitary Sewer Service Reports
11 d. Large Water Meter Reports
12 B. Deviations from this City of Fort Worth Standard Specification
13 1. None.
14 C. Related Specification Sections include, but are not necessarily limited to:
15 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
16 2. Division 1 – General Requirements
17 1.2 PRICE AND PAYMENT PROCEDURES
18 A. Measurement and Payment
19 1. Work associated with this Item is considered subsidiary to the various Items bid.
20 No separate payment will be allowed for this Item.
21 1.3 REFERENCES [NOT USED]
22 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED]
23 1.5 SUBMITTALS
24 A. Prior to submitting a request for Final Inspection, deliver Project Record Documents to
25 City’s Project Representative.
26 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
27 1.7 CLOSEOUT SUBMITTALS [NOT USED]
28 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
29 1.9 QUALITY ASSURANCE
30 A. Accuracy of Records
31 1. Thoroughly coordinate changes within the Record Documents, making adequate
32 and proper entries on each page of Specifications and each sheet of Drawings and
33 other Documents where such entry is required to show the change properly.
34 2. Accuracy of records shall be such that future search for items shown in the Contract
35 Documents may rely reasonably on information obtained from the approved Project
36 Record Documents.
01 78 39 - 2
DAP PROJECT RECORD DOCUMENTS
Page 2 of 4
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102561
Revised April 7, 2014
1 3. To facilitate accuracy of records, make entries within 24 hours after receipt of
2 information that the change has occurred.
3 4. Provide factual information regarding all aspects of the Work, both concealed and
4 visible, to enable future modification of the Work to proceed without lengthy and
5 expensive site measurement, investigation and examination.
6 1.10 STORAGE AND HANDLING
7 A. Storage and Handling Requirements
8 1. Maintain the job set of Record Documents completely protected from deterioration
9 and from loss and damage until completion of the Work and transfer of all recorded
10 data to the final Project Record Documents.
11 2. In the event of loss of recorded data, use means necessary to again secure the data
12 to the City's approval.
13 a. In such case, provide replacements to the standards originally required by the
14 Contract Documents.
15 1.11 FIELD [SITE] CONDITIONS [NOT USED]
16 1.12 WARRANTY [NOT USED]
17 PART 2 - PRODUCTS
18 2.1 OWNER-FURNISHED [OR] OWNER-SUPPLIED PRODUCTS [NOT USED]
19 2.2 RECORD DOCUMENTS
20 A. Job set
21 1. Promptly following receipt of the Notice to Proceed, secure from the City, at no
22 charge to the Contractor, 1 complete set of all Documents comprising the Contract.
23 B. Final Record Documents
24 1. At a time nearing the completion of the Work and prior to Final Inspection, provide
25 the City 1 complete set of all Final Record Drawings in the Contract.
26 2.3 ACCESSORIES [NOT USED]
27 2.4 SOURCE QUALITY CONTROL [NOT USED]
28 PART 3 - EXECUTION
29 3.1 INSTALLERS [NOT USED]
30 3.2 EXAMINATION [NOT USED]
31 3.3 PREPARATION [NOT USED]
32 3.4 MAINTENANCE DOCUMENTS
33 A. Maintenance of Job Set
34 1. Immediately upon receipt of the job set, identify each of the Documents with the
35 title, "RECORD DOCUMENTS - JOB SET".
01 78 39 - 3
DAP PROJECT RECORD DOCUMENTS
Page 3 of 4
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102561
Revised April 7, 2014
1 2. Preservation
2 a. Considering the Contract completion time, the probable number of occasions
3 upon which the job set must be taken out for new entries and for examination,
4 and the conditions under which these activities will be performed, devise a
5 suitable method for protecting the job set.
6 b. Do not use the job set for any purpose except entry of new data and for review
7 by the City, until start of transfer of data to final Project Record Documents.
8 c. Maintain the job set at the site of work.
9 3. Coordination with Construction Survey
10 a. At a minimum clearly mark any deviations from Contract Documents
11 associated with installation of the infrastructure.
12 4. Making entries on Drawings
13 a. Record any deviations from Contract Documents.
14 b. Use an erasable colored pencil (not ink or indelible pencil), clearly describe the
15 change by graphic line and note as required.
16 c. Date all entries.
17 d. Call attention to the entry by a "cloud" drawn around the area or areas affected.
18 e. In the event of overlapping changes, use different colors for the overlapping
19 changes.
20 5. Conversion of schematic layouts
21 a. In some cases on the Drawings, arrangements of conduits, circuits, piping,
22 ducts, and similar items, are shown schematically and are not intended to
23 portray precise physical layout.
24 1) Final physical arrangement is determined by the Contractor, subject to the
25 City's approval.
26 2) However, design of future modifications of the facility may require
27 accurate information as to the final physical layout of items which are
28 shown only schematically on the Drawings.
29 b. Show on the job set of Record Drawings, by dimension accurate to within 1
30 inch, the centerline of each run of items.
31 1) Final physical arrangement is determined by the Contractor, subject to the
32 City's approval.
33 2) Show, by symbol or note, the vertical location of the Item ("under slab", "in
34 ceiling plenum", "exposed", and the like).
35 3) Make all identification sufficiently descriptive that it may be related
36 reliably to the Specifications.
37 c. The City may waive the requirements for conversion of schematic layouts
38 where, in the City's judgment, conversion serves no useful purpose. However,
39 do not rely upon waivers being issued except as specifically issued in writing
40 by the City.
41 B. Final Project Record Documents
42 1. Transfer of data to Drawings
43 a. Carefully transfer change data shown on the job set of Record Drawings to the
44 corresponding final documents, coordinating the changes as required.
45 b. Clearly indicate at each affected detail and other Drawing a full description of
46 changes made during construction, and the actual location of items.
47 c. Call attention to each entry by drawing a "cloud" around the area or areas
48 affected.
01 78 39 - 4
DAP PROJECT RECORD DOCUMENTS
Page 4 of 4
CITY OF FORT WORTH Water and Sewer to Serve The Library
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102561
Revised April 7, 2014
1 d. Make changes neatly, consistently and with the proper media to assure
2 longevity and clear reproduction.
3 2. Transfer of data to other Documents
4 a. If the Documents, other than Drawings, have been kept clean during progress of
5 the Work, and if entries thereon have been orderly to the approval of the City,
6 the job set of those Documents, other than Drawings, will be accepted as final
7 Record Documents.
8 b. If any such Document is not so approved by the City, secure a new copy of that
9 Document from the City at the City's usual charge for reproduction and
10 handling, and carefully transfer the change data to the new copy to the approval
11 of the City.
12 3.5 REPAIR / RESTORATION [NOT USED]
13 3.6 RE-INSTALLATION [NOT USED]
14 3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED]
15 3.8 SYSTEM STARTUP [NOT USED]
16 3.9 ADJUSTING [NOT USED]
17 3.10 CLEANING [NOT USED]
18 3.11 CLOSEOUT ACTIVITIES [NOT USED]
19 3.12 PROTECTION [NOT USED]
20 3.13 MAINTENANCE [NOT USED]
21 3.14 ATTACHMENTS [NOT USED]
22 END OF SECTION
23
Revision Log
DATE NAME SUMMARY OF CHANGE
4/7/2014 M.Domenech Revised for DAP Application
24
CITY OF FORT WORTH Carter Park East Phase III & IV
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS CPN 102808
Revised July 1, 2011
APPENDIX
GC-4.01 Availability of Lands
GC-4.02 Subsurface and Physical Conditions
GC-6.06.D Minority and Women Owned Business Enterprise Compliance
GC-6.07 Wage Rates
GC-6.09 Permits and Utilities
GR-01 60 00 Product Requirements
This document was created by an application that isn’t licensed to use novaPDF.
Purchase a license to generate PDF files without this notice.
CITY OF FORT WORTH Carter Park East Phase III & IV
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS CPN 102808
Revised July 1, 2011
GR-01 60 00 Product Requirements
THIS PAGE LEFT INTENTIONALLY BLANK
This document was created by an application that isn’t licensed to use novaPDF.
Purchase a license to generate PDF files without this notice.
CITY OF FORT WORTH
WATER DEPARTMENT
STANDARD PRODUCT LIST
Updated: April 09, 2021
The Fort Worth Water Department’s Standard Products List has been developed to
minimize the submittal review of products which meet the Fort Worth Water
Department’s Standard Specifications during utility construction projects. When
Technical Specifications for specific products, are included as part of the
Construction Contract Documents, the requirements of the Technical Specification
will override the Fort Worth Water Department’s Standard Specifications and the
Fort Worth Water Department’s Standard Products List and approval of the
specific products will be based on the requirements of the Technical Specification
whether or not the specific product meets the Fort Worth Water Department’s
Standard Specifications or is on the Fort Worth Water Department’s Standard
Products List.
Table of Content
(Click on items to go directly to the page)
Items Page
A.Water & Sewer
1. Manholes & Bases/Components ........................................................... 1
2.Manholes & Bases/Fiberglass ............................................................... 2
3.Manholes & Bases/Frames & Covers/Rectangular ............................... 3
4.Manholes & Bases/Frames & Covers/Round ....................................... 4
5.Manholes & Bases/Frames & Covers/Water Tight & Pressure Tight .. 5
6.Manholes & Bases/Precast Concrete .................................................... 6
7.Manholes & Bases/Rehab Systems/Cementitious ................................ 7
8.Manholes & Bases/Rehab Systems/NonCementitious ......................... 8
9.Manhole Insert (Field Operations Use Only) ........................................ 9
10. Pipe Casing Spacer ............................................................................... 10
11. Pipes/Ductile Iron ................................................................................. 11
12. Utility Line Marker ............................................................................... 12
B.Sewer
13. Coatings/Epoxy ..................................................................................... 13
14. Coatings/Polyurethane .......................................................................... 14
15. Combination Air Valves ....................................................................... 15
16. Pipes/Concrete ...................................................................................... 16
17. Pipe Enlargement System (Method) ..................................................... 17
18. Pipes/Fiberglass Reinforced Pipe ......................................................... 18
19. Pipes/HDPE .......................................................................................... 19
20. Pipes/PVC (Pressure Sewer) ................................................................. 20
21. Pipes/PVC* ........................................................................................... 21
22. Pipes/Rehab/CIPP ................................................................................. 22
23. Pipes/Rehab/Fold & Form .................................................................... 23
24. Pipes/Open Profile Large Diameter ...................................................... 24
C.Water
25. Appurtenances ....................................................................................... 25
26. Bolts, Nuts, and Gaskets ....................................................................... 26
27. Combination Air Release Valve ........................................................... 27
28. Dry Barrel Fire Hydrants ...................................................................... 28
29. Meters ................................................................................................... 29
30. Pipes/PVC (Pressure Water) ................................................................. 30
31. Pipes/Valves & Fittings/Ductile Iron Fittings ....................................... 31
32. Pipes/Valves & Fittings/Resilient Seated Gate Valve .......................... 32
33. Pipes/Valves & Fittings/Rubber Seated Butterfly Valve ...................... 33
34. Polyethylene Encasement ..................................................................... 34
35. Sampling Stations ................................................................................. 35
36. Automatic Flusher ................................................................................. 36
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeWater & Sewer - Manholes & Bases/Components 33-39-10 (Rev 2/3/16)07/23/97 33 05 13 Urethane Hydrophilic WaterstopAsahi Kogyo K.K.Adeka Ultra-Seal P-201ASTM D2240/D412/D79204/26/00 33 05 13 Offset Joint for 4' Diam. MHHanson Concrete ProductsDrawing No. 35-0048-00104/26/00 33 05 13 Profile Gasket for 4' Diam. MH.Press-Seal Gasket Corp.250-4G GasketASTM C-443/C-361SS MH1/26/99 33 05 13 HDPE Manhole Adjustment RingsLadtech, IncHDPE Adjustment RingNon-traffic area5/13/05 33 05 13 Manhole External WrapCanusa - CPSWrapidSeal Manhole Encapsulation SystemCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.* From Original Standard Products ListClick to Return to the Table of Content1Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water & Sewer - Manholes & Bases/Fiberglass 33-39-13 (1/8/13)1/26/99 33 39 13 Fiberglass ManholeFluid Containment, Inc.FlowtiteASTM 3753Non-traffic area08/30/06 33 39 13 Fiberglass ManholeL.F. ManufacturingNon-traffic area* From Original Standard Products ListClick to Return to the Table of Content2Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water & Sewer - Manholes & Bases/Frames & Covers/Rectangular 33-05-13 (Rev 2/3/16)*33 05 13 Manhole Frames and CoversWestern Iron Works, Bass & Hays Foundry100124"x40" WD* From Original Standard Products ListClick to Return to the Table of Content3Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water & Sewer - Manholes & Bases/Frames & Covers/Standard (Round) 33-05-13 (Rev 2/3/16)*33 05 13 Manhole Frames and CoversWestern Iron Works, Bass & Hays Foundry3002424" Dia.*33 05 13 Manhole Frames and CoversMcKinley Iron Works Inc.A 24 AM24" Dia.08/24/18 33 05 13 Manhole Frames and CoversNeenah FoundryR-1272ASTM A48 & AASHTO M30624" Dia.08/24/18 33 05 13 Manhole Frames and CoversNeenah FoundryR- 165-LM (Hinged)ASTM A48 & AASHTO M30624" Dia.08/24/18 33 05 13 Manhole Frames and CoversNeenah FoundryNF 1274ASTM A48 & AASHTO M30630" Dia.08/24/18 33 05 13 Manhole Frames and CoversNeenah FoundryR-1743-LM (Hinged)ASTM A48 & AASHTO M30630" dia.33 05 13 Manhole Frames and CoversSigma CorporationMH-144N33 05 13 Manhole Frames and CoversSigma CorporationMH-143N33 05 13 Manhole Frames and CoversPont-A-MoussonGTS-STD24" dia.33 05 13 Manhole Frames and CoversNeenah Casting24" dia.10/31/06 33 05 13 Manhole Frames and Covers (Hinged)PowersealHinged Ductile Iron Manhole ASTM A53624" Dia.7/25/03 33 05 13 Manhole Frames and CoversSaint-Gobain Pipelines (Pamrex/rexus)RE32-R8FS30" Dia.01/31/06 33 05 13 30" Dia. MH Ring and CoverEast Jordan Iron WorksV1432-2 and V1483 DesignsAASHTO M306-0430" Dia.11/02/10 33 05 13 30" Dia. MH Ring and CoverSigma CorporationMH1651FWN & MH1650230" Dia07/19/11 33 05 13 30" Dia. MH Ring and CoverStar Pipe ProductsMH32FTWSS-DC 30" Dia08/10/11 33 05 13 30" Dia. MH Ring and CoverAccucast220700 Heavy Duty with Gasket Ring30" Dia10/14/13 33 05 13 30" Dia. MH Ring and Cover (Hinged & Lockable)East Jordan Iron Works 30" ERGO XL Assembly with Cam Lock/MPIC/T-Gasket ASSHTO M105 & ASTM A53630" Dia06/01/17 34 05 13 30" Dia. MH Ring and Cover (Hinged & Lockable) CISIP Industries2280 (32")ASTM A 4830" Dia.09/16/19 33 05 13.10 30" Dia. MH Ring and Cover Composite Access Products, L.P.CAP-ONE-30-FTW, Composite, w/ Lock w/o Hing30" Dia.* From Original Standard Products ListClick to Return to the Table of Content4Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water & Sewer - Manholes & Bases/Frames & Covers/Water Tight & Pressure Tight 33-05-13 (Rev 2/3/16)*33 05 13 Manhole Frames and CoversPont-A-MoussonPamtight24" Dia.*33 05 13 Manhole Frames and CoversNeenah Casting24" Dia.*33 05 13 Manhole Frames and CoversWestern Iron Works,Bass & Hays Foundry300-24P24" Dia.*33 05 13 Manhole Frames and CoversMcKinley Iron Works Inc.WPA24AM24" Dia.03/08/00 33 05 13 Manhole Frames and CoversAccucastRC-2100ASTM A 4824" Dia.04/20/01 33 05 13 Manhole Frames and Covers(SIP)Serampore Industries Private Ltd.300-24-23.75 Ring and CoverASTM A 4824" Dia.* From Original Standard Products ListClick to Return to the Table of Content5Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water & Sewer - Manholes & Bases/Precast Concrete (Rev 1/8/13)*33 39 10 Manhole, Precast ConcreteHydro Conduit CorpSPL Item #49ASTM C 47848"*33 39 10 Manhole, Precast ConcreteWall Concrete Pipe Co. Inc.ASTM C-44348"09/23/96 33 39 10 Manhole, Precast ConcreteConcrete Product Inc.48" I.D. Manhole w/ 32" ConeASTM C 47848" w/32" cone05/08/18 33 39 10 Manhole, Precast ConcreteThe Turner Company48", 60" I.D. Manhole w/ 32" ConeASTM C 47848", 60"10/27/06 33 39 10 Manhole, Precast ConcreteOldcastle Precast Inc.48" I.D. Manhole w/ 24" ConeASTM C 47848" Diam w 24" Ring06/09/10 33 39 10 Manhole, Precast (Reinforce Polymer)ConcreteUS Composite PipeReinforced Polymer Concrete ASTM C-7648" to 72"09/06/19 33 39 20 Manhole, Precast ConcreteForterra Pipe and Precast60" & 72" I.D. Manhole w/32" ConeASTM C-7660" & 72"* From Original Standard Products ListClick to Return to the Table of Content6Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water & Sewer - Manholes & Bases/Rehab Systems/Cementitious*E1-14 Manhole Rehab SystemsQuadex04/23/01E1-14 Manhole Rehab SystemsStandard Cement Materials, Inc.Reliner MSPE1-14 Manhole Rehab SystemsAP/M Permaform4/20/01E1-14 Manhole Rehab SystemStrong CompanyStrong Seal MS2A Rehab System5/12/03E1-14 Manhole Rehab System (Liner)Poly-triplex TechnologiesMH repair product to stop infiltrationASTM D581308/30/06General Concrete RepairFlexKrete TechnologiesVinyl Polyester Repair ProductMisc. Use* From Original Standard Products ListClick to Return to the Table of Content7Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water & Sewer - Manholes & Bases/Rehab Systems/NonCementitious05/20/96E1-14 Manhole Rehab SystemsSprayroq, Spray Wall Polyurethane CoatingASTM D639/D790*E1-14 Manhole Rehab SystemsSun Coast12/14/01Coating for Corrosion protection(Exterior)ERTECHSeries 20230 and 2100 (Asphatic Emulsion)For Exterior Coating of Concrete Structures Only01/31/06Coatings for Corrosion ProtectionChestertonArc 791, S1HB, S1, S2Acid Resistance TestSewer Applications8/28/2006Coatings for Corrosion ProtectionWarren EnvironmentalS-301 and M-301Sewer Applications08/30/06Coatings for Corrosion ProtectionCitadelSLS-30 Solids EpoxySewer Applications03/19/1833 05 16, 33 39 10, 33 39 20 Coating for Corrosion protection(Exterior)Sherwin WilliamsRR&C Dampproofing Non-Fibered Spray Grade (Asphatic Emulsion)For Exterior Coating of Concrete Structures Only* From Original Standard Products ListClick to Return to the Table of Content8Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water & Sewer - Manhole Inserts - Field Operations Use Only (Rev 2/3/16)*33 05 13 Manhole InsertKnutson EnterprisesMade to Order - PlasticASTM D 1248For 24" dia.*33 05 13 Manhole InsertSouth Western PackagingMade to Order - PlasticASTM D 1248For 24" dia.*33 05 13 Manhole InsertNoflow-InflowMade to Order - PlasticASTM D 1248For 24" dia.09/23/96 33 05 13 Manhole InsertSouthwestern Packing & Seals, Inc.LifeSaver - Stainless SteelFor 24" dia.09/23/96 33 05 13 Manhole InsertSouthwestern Packing & Seals, Inc.TetherLok - Stainless SteelFor 24" dia* From Original Standard Products ListClick to Return to the Table of Content9Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water & Sewer - Pipe Casing Spacers 33-05-24 (07/01/13)11/04/02Steel Band Casing SpacersAdvanced Products and Systems, Inc.Carbon Steel Spacers, Model SI02/02/93Stainless Steel Casing SpacerAdvanced Products and Systems, Inc.Stainless Steel Spacer, Model SSI04/22/87Casing SpacersCascade Waterworks ManufacturingCasing Spacers09/14/10Stainless Steel Casing SpacerPipeline Seal and InsulatorStainless Steel Casing SpacerUp to 48"09/14/10Coated Steel Casin SpacersPipeline Seal and InsulatorCoated Steel Casin SpacersUp to 48" 05/10/11Stainless Steel Casing SpacerPowerseal4810 PowerchockUp to 48"03/19/18Casing SpacersBWMSS-12 Casing Spacer(Stainless Steel)03/19/18Casing SpacersBWMFB-12 Casing Spacer (Coated Carbon Steel) for Non_pressure Pipe and Grouted Casing* From Original Standard Products ListClick to Return to the Table of Content10Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water & Sewer - Pipes/Ductile Iron 33-11-10(1/8/13)*33 11 10 Ductile Iron PipeGriffin Pipe Products, Co.Super Bell-Tite Ductile Iron Pressure Pipe, AWWA C150, C1513" thru 24"08/24/18 33 11 10 Ductile Iron PipeAmerican Ductile Iron Pipe Co.American Fastite Pipe (Bell Spigot)AWWA C150, C1514" thru 30"08/24/18 33 11 10 Ductile Iron PipeAmerican Ductile Iron Pipe Co.American Flex Ring (Restrained Joint)AWWA C150, C1514" thru 30"*33 11 10 Ductile Iron PipeU.S. Pipe and Foundry Co.AWWA C150, C151*33 11 10 Ductile Iron PipeMcWane Cast Iron Pipe Co.AWWA C150, C151* From Original Standard Products ListClick to Return to the Table of Content11Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water & Sewer - Utility Line Marker (08/24/2018)* From Original Standard Products ListClick to Return to the Table of Content12Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Sewer - Coatings/Epoxy 33-39-60 (01/08/13)02/25/02Epoxy Lining SystemSauereisen, IncSewerGard 210RSLA County #210-1.3312/14/01Epoxy Lining SystemErtech Technical CoatingsErtech 2030 and 2100 Series04/14/05Interior Ductile Iron Pipe CoatingInduronProtecto 401ASTM B-117Ductile Iron Pipe Only01/31/06Coatings for Corrosion ProtectionChestertonArc 791, S1HB, S1, S2Acid Resistance TestSewer Applications8/28/2006Coatings for Corrosion ProtectionWarren EnvironmentalS-301 and M-301Sewer Applications* From Original Standard Products ListClick to Return to the Table of Content13Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Sewer - Coatings/Polyurethane* From Original Standard Products ListClick to Return to the Table of Content14Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Sewer - Combination Air Valves 05/25/18 33-31-70 Air Release ValveA.R.I. USA, Inc.D025LTP02(Composite Body)2"* From Original Standard Products ListClick to Return to the Table of Content15Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Sewer - Pipes/Concrete*E1-04 Conc. Pipe, ReinforcedWall Concrete Pipe Co. Inc.ASTM C 76*E1-04 Conc. Pipe, ReinforcedHydro Conduit CorporationClass III T&G, SPL Item #77ASTM C 76*E1-04 Conc. Pipe, ReinforcedHanson Concrete ProductsSPL Item #95-Manhole, #98- PipeASTM C 76*E1-04 Conc. Pipe, ReinforcedConcrete Pipe & Products Co. Inc.ASTM C 76* From Original Standard Products ListClick to Return to the Table of Content16Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Sewer - Pipe Enlargment System (Method)33-31-23 (01/18/13)PIM SystemPIM CorporationPolyethylenePIM Corp., Piscata Way, N.J. Approved PreviouslyMcConnell SystemsMcLat ConstructionPolyethyleneHouston, TexasApproved PreviouslyTRS SystemsTrenchless Replacement SystemPolyethyleneCalgary, CanadaApproved Previously* From Original Standard Products ListClick to Return to the Table of Content17Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Sewer - Pipe/Fiberglass Reinforced Pipe 33-31-13(1/8/13)7/21/97 33 31 13 Cent. Cast Fiberglass (FRP)Hobas Pipe USA, Inc.Hobas Pipe (Non-Pressure)ASTM D3262/D375403/22/10 33 31 13 Fiberglass Pipe (FRP)AmeronBondstrand RPMP PipeASTM D3262/D375404/09/21Glass-Fiber Reinforced Polymer Pipe (FRP)Thompson Pipe GroupThompson Pipe (Flowtite)ASTM D3262/D37544/14/05Polymer Modified Concrete PipeAmitech USAMeyer Polycrete PipeASTM C33, A276, F4778" to 102", Class V06/09/10E1-9 Reinforced Polymer Concrete PipeUS Composite PipeReinforced Polymer Concrete PipeASTM C-76* From Original Standard Products ListClick to Return to the Table of Content18Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Sewer - Pipes/HDPE 33-31-23(1/8/13)*High-density polyethylene pipePhillips Driscopipe, Inc.Opticore Ductile Polyethylene PipeASTM D 12488"*High-density polyethylene pipePlexco Inc.ASTM D 12488"*High-density polyethylene pipePolly Pipe, Inc.ASTM D 12488"High-density polyethylene pipeCSR Hydro Conduit/Pipeline SystemsMcConnell Pipe EnlargementASTM D 1248* From Original Standard Products ListClick to Return to the Table of Content19Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Sewer - Pipes/PVC (Pressure Sewer) 33-11-12 (4/1/13)12/02/11 33-11-12 DR-14 PVC Pressure PipePipelife JetstreamPVC Pressure PipeAWWA C9004" thru 12"10/22/14 33-11-12 DR-14 PVC Pressure PipeRoyal Building ProductsRoyal Seal PVC Pressure PipeAWWA C9004" thru 12"* From Original Standard Products ListClick to Return to the Table of Content20Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Sewer - Pipes/PVC* 33-31-20 (7/1/13)*33-31-20 PVC Sewer PipeJ-M Manufacturing Co., Inc. (JM Eagle)SDR-26ASTM D 30344" - 15"12/23/97* 33-31-20 PVC Sewer PipeDiamond Plastics CorporationSDR-26ASTM D 30344" thru 15"*33-31-20 PVC Sewer PipeLamson Vylon PipeASTM F 7894" thru 15"01/18/18 33-31-20 PVC Sewer PipeVinyltech PVC PipeGravity SewerASTM D30344" thru 15"11/11/98 33-31-20 PVC Sewer PipeDiamond Plastics Corporation "S" Gravity Sewer PipeASTM F 67918" to 27"*33-31-20 PVC Sewer PipeJ-M Manufacturing Co, Inc. (JM Eagle)SDR 26/35 PS 115/46ASTM F 67918" - 28"09/11/12 33-31-20 PVC Sewer PipePipelife Jet StreamSDR-26 and SDR-35ASTM F-67918"05/06/0533-31-20PVC Solid Wall PipeDiamond Plastics CorporationSDR 26/35 PS 115/46ASTM F-67918" to 48"04/27/0633-31-20PVC Sewer Fittings HarcoSDR-26 and SDR-35 Gasket Fittings ASTM D-3034, D-1784, etc4" - 15"*33-31-20PVC Sewer FittingsPlastic Trends, In.cGasketed PVC Sewer Main FittingsASTM D 30343/19/2018 33 31 20 PVC Sewer PipePipelife Jet StreamSDR 35ASTM F67918"- 24"3/19/2018 33 31 20 PVC Sewer PipePipelife Jet StreamSDR 26ASTM D30344"- 15"3/29/2019 33 31 20Gasketed Fittings (PVC)GPK Products, Inc.SDR 26ASTM D3034/F-6794"- 15"10/21/2020 33 31 20 PVC Sewer PipeNAPCOSDR 26ASTM D30344" - 15"10/22/2020 33 31 20 PVC Sewer PipeSanderson Pipe Corp.SDR 26ASTM D30344"- 15"10/21/2020 33 31 20 PVC Sewer PipeNAPCOSDR 26/35 PS 115/46ASTM F-67918"- 36"* From Original Standard Products ListClick to Return to the Table of Content21Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Sewer - Pipes/Rehab/CIPP 33-31-12 (01/18/13)*Cured in Place PipeInsituform Texark, IncASTM F 121605/03/99Cured in Place PipeNational Envirotech GroupNational Liner, (SPL) Item #27ASTM F-1216/D-581305/29/96Cured in Place PipeReynolds Inc/Inliner Technolgy (Inliner USA)Inliner TechnologyASTM F 1216* From Original Standard Products ListClick to Return to the Table of Content22Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Sewer - Pipes/Rehab/Fold & Form*Fold and Form PipeCullum Pipe Systems, Inc.11/03/98Fold and Form PipeInsituform Technologies, Inc.Insituform "NuPIpe"ASTM F-1504Fold and Form PipeAmerican Pipe & Plastics, Inc.Demo. Purpose Only12/04/00Fold and Form PipeUltralinerUltraliner PVC Alloy PipelinerASTM F-1504, 1871, 186706/09/03Fold and Form PipeMiller Pipeline Corp.EX MethodASTM F-1504, F-1947Up to 18" diameter* From Original Standard Products ListClick to Return to the Table of Content23Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Sewer - Pipes/Open Profile Large Diameter09/26/91 E100-2 PVC Sewer Pipe, RibbedLamson Vylon PipeCarlon Vylon H.C. Closed Profile Pipe,ASTM F 67918" to 48"09/26/91 E100-2 PVC Sewer Pipe, RibbedExtrusion Technologies, Inc.Ultra-Rib Open Profile Sewer PipeASTM F 67918" to 48"E100-2 PVC Sewer Pipe, RibbedUponor ETI Company11/10/10 (E100-2) Polypropylene (PP) Sewer Pipe, Double WallAdvanced Drainage Systems (ADS) SaniTite HP Double Wall (Corrugated)ASTM F 273624"-30"11/10/10 (E100-2) Polypropylene (PP) Sewer Pipe, Triple WallAdvanced Drainage Systems (ADS)SaniTite HP Triple Wall PipeASTM F 276430" to 60"05/16/11Steel Reinforced Polyethylene PipeConTech Construction ProductsDurmaxxASTM F 256224" to 72"* From Original Standard Products ListClick to Return to the Table of Content24Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water - Appurtenances 33-12-10 (07/01/13)01/18/18 33-12-10 Double Strap SaddleRomac202NS Nylon CoatedAWWA C8001"-2" SVC, up to 24" Pipe08/28/02Double Strap SaddleSmith Blair #317 Nylon Coated Double Strap Saddle07/23/12 33-12-10 Double Strap Service SaddleMueller CompanyDR2S Double (SS) Strap DI SaddleAWWA C8001"-2" SVC, up to 24" Pipe10/27/87Curb Stops-Ball Meter ValvesMcDonald6100M,6100MT & 610MT 3/4" and 1"10/27/87Curb Stops-Ball Meter ValvesMcDonald4603B, 4604B, 6100M, 6100TM and 6101M 1½" and 2"5/25/2018 33-12-10 Curb Stops-Ball Meter ValvesFord Meter Box Co., Inc.FB600-7NL, FB1600-7-NL, FV23-777-W-NL, L22-77NLAWWA C8002"5/25/2018 33-12-10 Curb Stops-Ball Meter ValvesFord Meter Box Co., Inc.FB600-6-NL, FB1600-6-NL, FV23-666-W-NL, L22-66NLAWWA C8001-1/2"5/25/2018 33-12-10 Curb Stops-Ball Meter ValvesFord Meter Box Co., Inc.FB600-4-NL, FB1600-4-NL, B11-444-WR-NL, B22444-WR-NL, L28-44NLAWWA C8001"5/25/2018 33-12-10 Curb Stops-Ball Meter ValvesMueller Co., Ltd.B-25000N, B-24277N-3, B-20200N-3, H-15000N, , H-1552N, H142276NAWWA C800, ANSF 61, ANSI/NSF 3722"5/25/2018 33-12-10 Curb Stops-Ball Meter ValvesMueller Co., Ltd.B-25000N, B-20200N-3, B-24277N-3,H-15000N, H-14276N, H-15525NAWWA C800, ANSF 61, ANSI/NSF 3721-1/2"5/25/2018 33-12-10 Curb Stops-Ball Meter ValvesMueller Co., Ltd.B-25000N, B-20200N-3,H-15000N, H-15530NAWWA C800, ANSF 61, ANSI/NSF 3721"01/26/00Coated Tapping Saddle with Double SS StrapsJCM Industries, Inc.#406 Double Band SS Saddle1"-2" Taps on up to 12" 0/5/21/12 33-12-25 Tapping Sleeve (Coated Steel)JCM Industries, Inc.412 Tapping Sleeve ESSAWWA C-223Up to 30" w/12" Out05/10/11Tapping Sleeve (Stainless Steel)Powerseal3490AS (Flange) & 3490MJ4"-8" and 16"02/29/12 33-12-25 Tapping Sleeve (Coated Steel)RomacFTS 420AWWA C-223U p to 42" w/24" Out02/29/12 33-12-25 Tapping Sleeve (Stainless Steel)RomacSST Stainless SteelAWWA C-223Up to 24" w/12" Out02/29/12 33-12-25 Tapping Sleeve (Stainless Steel)RomacSST III Stainless SteelAWWA C-223Up to 30" w/12" Out05/10/11Joint Repair ClampPowerseal3232 Bell Joint Repair Clamp4" to 30"Plastic Meter Box w/Composite LidDFW Plastics Inc.DFW37C-12-1EPAF FTWPlastic Meter Box w/Composite LidDFW Plastics Inc.DFW39C-12-1EPAF FTW08/30/06Plastic Meter Box w/Composite LidDFW Plastics Inc.DFW65C-14-1EPAF FTWClass "A"Concrete Meter BoxBass & HaysCMB37-B12 1118 LID-9Concrete Meter BoxBass & HaysCMB-18-Dual 1416 LID-9Concrete Meter BoxBass & HaysCMB65-B65 1527 LID-9* From Original Standard Products ListClick to Return to the Table of Content25Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water - Bolts, Nuts, and Gaskets 33-11-05 (01/08/13)* From Original Standard Products ListClick to Return to the Table of Content26Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water - Combination Air Release 33-31-70 (01/08/13)*E1-11 Combination Air Release ValveGA Industries, Inc.Empire Air and Vacuum Valve, Model 935 ASTM A 126 Class B, ASTM A 240 - float, ASTM A 307 - Cover Bolts1" & 2"*E1-11 Combination Air Release ValveMultiplex Manufacturing Co.Crispin Air and Vacuum Valves, Model No. 1/2", 1" & 2"*E1-11 Combination Air Release ValveValve and Primer Corp.APCO #143C, #145C and #147C1", 2" & 3"* From Original Standard Products ListClick to Return to the Table of Content27Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water - Dry Barrel Fire Hydrants 33-12-40 (01/15/14)10/01/87 E-1-12 Dry Barrel Fire HydrantAmerican-Darling ValveDrawing Nos. 90-18608, 94-18560AWWA C-50203/31/88 E-1-12 Dry Barrel Fire HydrantAmerican Darling ValveShop Drawing No. 94-18791 AWWA C-50209/30/87 E-1-12 Dry Barrel Fire HydrantClow CorporationShop Drawing No. D-19895AWWA C-50201/12/93 E-1-12 Dry Barrel Fire HydrantAmerican AVK CompanyModel 2700AWWA C-50208/24/88 E-1-12 Dry Barrel Fire HydrantClow CorporationDrawings D20435, D20436, B20506AWWA C-502E-1-12 Dry Barrel Fire HydrantITT Kennedy ValveShop Drawing No. D-80783FWAWWA C-50209/24/87 E-1-12 Dry Barrel Fire HydrantM&H Valve CompanyShop Drawing No. 13476AWWA C-50210/14/87 E-1-12 Dry Barrel Fire HydrantMueller CompanyShop Drawings No. 6461 A-423 CenturionAWWA C-50201/15/88E1-12 Dry Barrel Fire HydrantMueller CompanyShop Drawing FH-12A-423 Super Centurion 200AWWA C-50210/09/87 E-1-12 Dry Barrel Fire HydrantU.S. Pipe & FoundryShop Drawing No. 960250AWWA C-50209/16/87 E-1-12 Dry Barrel Fire HydrantWaterous CompanyShop Drawing No. SK740803AWWA C-50208/12/16 33-12-40 Dry Barrel Fire HydrantEJ (East Jordan Iron Works)WaterMaster 5CD250* From Original Standard Products ListClick to Return to the Table of Content28Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water - Meters02/05/93 E101-5 Detector Check MeterAmes CompanyModel 1000 Detector Check ValveAWWA C5504" - 10"08/05/04Magnetic Drive Vertical TurbineHerseyMagnetic Drive VerticalAWWA C701, Class 13/4" - 6"* From Original Standard Products ListClick to Return to the Table of Content29Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water - Pipes/PVC (Pressure Water) 33-31-70 (01/08/13)01/18/18 33-11-12 PVC Pressure PipeVinyltech PVC PipeDR14AWWA C900, AWWA C605, ASTM D17844"-12"3/19/2018 33 11 12 PVC Pressure PipePipelife Jet StreamDR14AWWA C9004"-12"3/19/2018 33 11 12 PVC Pressure PipePipelife Jet StreamDR18AWWA C90016"-24"5/25/2018 33 11 12 PVC Pressure PipeDiamond Plastics CorporationDR 14AWWA C9004"-12"5/25/2018 33 11 12 PVC Pressure PipeDiamond Plastics CorporationDR 18AWWA C90016"-24"12/6/2018 33 11 12 PVC Pressure PipeJ-M Manufacturing Co., Inc d/b/a JM EagleDR 14AWWA C900-16UL 1285ANSI/NSF 61FM 16124"-28"12/6/2018 33 11 12 PVC Pressure PipeJ-M Manufacturing Co., Inc d/b/a JM EagleDR 18AWWA C900-16UL 1285ANSI/NSF 61FM 161216"-24"9/6/2019 33 11 12 PVC Pressure PipeUnderground Solutions Inc.DR14 Fusible PVCAWWA C9004" - 8"9/6/2019 33 11 12 PVC Pressure PipeNAPCODR18AWWA C90016" - 24"9/6/2019 33 11 12 PVC Pressure PipeNAPCODR14AWWA C9004"- 12"9/6/2019 33 11 12 PVC Pressure PipeSanderson Pipe Corp.DR14AWWA C9004"- 12"* From Original Standard Products ListClick to Return to the Table of Content30Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water - Pipes/Valves & Fittings/Ductile Iron Fittings 33-11-11 (01/08/13)07/23/92E1-07 Ductile Iron FittingsStar Pipe Products, Inc.Mechanical Joint FittingsAWWA C153 & C110*E1-07 Ductile Iron FittingsGriffin Pipe Products, Co.Mechanical Joint FittingsAWWA C 110*E1-07 Ductile Iron FittingsMcWane/Tyler Pipe/ Union Utilities DivisionMechanical Joint Fittings, SSB Class 350AWWA C 153, C 110, C 11108/11/98E1-07 Ductile Iron FittingsSigma, Co.Mechanical Joint Fittings, SSB Class 351AWWA C 153, C 110, C 11202/26/14E1-07 MJ FittingsAccucastClass 350 C-153 MJ FittingsAWWA C1534"-12"05/14/98E1-07 Ductile Iron Joint RestraintsFord Meter Box Co./Uni-FlangeUni-Flange Series 1400 AWWA C111/C1534" to 36"05/14/98E1-24 PVC Joint RestraintsFord Meter Box Co./Uni-FlangeUni-Flange Series 1500 Circle-LockAWWA C111/C1534" to 24" 11/09/04E1-07 Ductile Iron Joint RestraintsOne Bolt, Inc.One Bolt Restrained Joint FittingAWWA C111/C116/C1534" to 12"02/29/12 33-11-11 Ductile Iron Pipe Mechanical Joint RestraintEBAA Iron, Inc.Megalug Series 1100 (for DI Pipe)AWWA C111/C116/C1534" to 42"02/29/12 33-11-11 PVC Pipe Mechanical Joint RestraintEBAA Iron, Inc.Megalug Series 2000 (for PVC Pipe)AWWA C111/C116/C1534" to 24"08/05/04E1-07 Mechanical Joint Retainer Glands(PVC)Sigma, Co.Sigma One-Lok SLC4 - SLC10AWWA C111/C1534" to 10"03/06/19 33-11-11 Mechanical Joint Retainer Glands(PVC)Sigma, Co.Sigma One-Lok SLCS4 - SLCS12AWWA C111/C1534" to 12"08/05/04E1-07 Mechanical Joint Retainer Glands(PVC)Sigma, Co.Sigma One-Lok SLCEAWWA C111/C15312" to 24"08/10/98E1-07 MJ Fittings(DIP)Sigma, Co.Sigma One-Lok SLDEAWWA C1534" - 24"10/12/10E1-24 Interior Restrained Joint SystemS & B Techncial ProductsBulldog System ( Diamond Lok 21 & JM Eagle ASTM F-16244" to 12"08/16/06E1-07 Mechanical Joint FittingsSIP Industries(Serampore)Mechanical Joint FittingsAWWA C1534" to 24"11/07/16 33-11-11 Mechanical Joint Retainer GlandsStar Pipe Products, Inc.PVC Stargrip Series 4000ASTM A536 AWWA C11111/07/16 33-11-11 Mechanical Joint Retainer GlandsStar Pipe Products, Inc.DIP Stargrip Series 3000ASTM A536 AWWA C11103/19/18 33-11-11 Mechanical Joint Retainer GlandsSIP Industries(Serampore)EZ Grip Joint Restraint (EZD) Black For DIPASTM A536 AWWA C1113"-48"03/19/18 33-11-11 Mechanical Joint Retainer GlandsSIP Industries(Serampore)EZ Grip Joint Restraint (EZD) Red for C900 DR14 PVC PipeASTM A536 AWWA C1114"-12"03/19/18 33-11-11 Mechanical Joint Retainer GlandsSIP Industries(Serampore)EZ Grip Joint Restraint (EZD) Red for C900 DR18 PVC PipeASTM A536 AWWA C11116"-24"* From Original Standard Products ListClick to Return to the Table of Content31Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water - Pipes/Valves & Fittings/Resilient Seated Gate Valve* 33-12-20 (05/13/15)Resilient Wedged Gate Valve w/no GearsAmerican Flow ControlSeries 2500 Drawing # 94-2024716"12/13/02Resilient Wedge Gate ValveAmerican Flow ControlSeries 2530 and Series 2536AWWA C51530" and 36"08/31/99Resilient Wedge Gate ValveAmerican Flow ControlSeries 2520 & 2524 (SD 94-20255)AWWA C51520" and 24"05/18/99Resilient Wedge Gate ValveAmerican Flow ControlSeries 2516 (SD 94-20247)AWWA C51516"10/24/00E1-26 Resilient Wedge Gate ValveAmerican Flow ControlSeries 2500 (Ductile Iron)AWWA C5154" to 12"08/05/04Resilient Wedge Gate ValveAmerican Flow Control42" and 48" AFC 2500AWWA C51542" and 48"05/23/91E1-26 Resilient Wedge Gate ValveAmerican AVK CompanyAmerican AVK Resilient Seaded GVAWWA C5094" to 12"01/24/02E1-26 Resilient Wedge Gate ValveAmerican AVK Company20" and smaller*E1-26 Resilient Seated Gate ValveKennedy4" - 12"*E1-26 Resilient Seated Gate ValveM&H4" - 12"*E1-26 Resilient Seated Gate ValveMueller Co.4" - 12"11/08/99Resilient Wedge Gate Valve Mueller Co.Series A2361 (SD 6647)AWWA C51516"01/23/03Resilient Wedge Gate ValveMueller Co.Series A2360 for 18"-24" (SD 6709)AWWA C51524" and smaller05/13/05Resilient Wedge Gate ValveMueller Co.Mueller 30" & 36", C-515AWWA C51530" and 36"01/31/06Resilient Wedge Gate ValveMueller Co.Mueller 42" & 48", C-515AWWA C51542" and 48"01/28/88E1-26 Resilient Wedge Gate ValveClow Valve Co.AWWA C5094" - 12"10/04/94Resilient Wedge Gate ValveClow Valve Co.16" RS GV (SD D-20995)AWWA C51516"11/08/99E1-26 Resilient Wedge Gate ValveClow Valve Co.Clow RW Valve (SD D-21652)AWWA C51524" and smaller11/29/04Resilient Wedge Gate Valve Clow Valve Co.Clow 30" & 36" C-515AWWA C51530" and 36" (Note 3)11/30/12Resilient Wedge Gate ValveClow Valve Co.Clow Valve Model 2638AWWA C51524" to 48" (Note 3)05/08/91E1-26 Resilient Seated Gate ValveStockham Valves & FittingsAWWA C 509, ANSI 420 - stem, ASTM A 276 Type 304 - Bolts & nuts4" - 12"*E1-26 Resilient Seated Gate ValveU.S. Pipe and Foundry Co.Metroseal 250, requirements SPL #743" to 16"10/26/16 33-12-20 Resilient Seated Gate ValveEJ (East Jordan Iron Works)EJ FlowMaster Gate Valve & Boxes08/24/18Matco Gate Valve Matco-Norca225 MRAWWA/ANSI C115/An21.154" to 16"* From Original Standard Products ListClick to Return to the Table of Content32Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water - Pipes/Valves & Fittings/Rubber Seated Butterfly Valve 33-12-21 (07/10/14)*E1-30 Rubber Seated Butterfly ValveHenry Pratt Co.AWWA C-50424"*E1-30 Rubber Seated Butterfly ValveMueller Co.AWWA C-50424"and smaller1/11/99E1-30 Rubber Seated Butterfly ValveDezurik Valves Co.AWWA C-50424" and larger06/12/03E1-30 Valmatic American Butterfly ValveValmatic Valve and Manufacturing Corp. Valmatic American Butterfly Valve.AWWA C-504Up to 84" diameter04/06/07E1-30 Rubber Seated Butterfly ValveM&H ValveM&H Style 4500 & 1450 AWWA C-50424" to 48"03/19/18 33 12 21 Rubber Seated Butterfly ValveG. A. Industries (Golden Anderson)AWWA C504 Butterfly ValveAWWA C-50430"-54"* From Original Standard Products ListClick to Return to the Table of Content33Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water - Polyethylene Encasement 33-11-10 (01/08/13)05/12/05E1-13 Polyethylene EncasmentFlexsol PackagingFulton Enterprises AWWA C1058 mil LLD05/12/05E1-13 Polyethylene EncasmentMountain States Plastics (MSP) and AEP Ind.Standard HardwareAWWA C1058 mil LLD05/12/05E1-13 Polyethylene EncasmentAEP IndustriesBullstrong by Cowtown Bolt & GasketAWWA C1058 mil LLD09/06/19 33-11-11 Polyethylene EncasmentNorthtown Products Inc. PE Encasement for DIPAWWA C1058 mil LLD* From Original Standard Products ListClick to Return to the Table of Content34Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water - Sampling Station3/12/96Water Sampling StationWater PlusB20 Water Sampling Station* From Original Standard Products ListClick to Return to the Table of Content35Updated:04/09/2021
Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Water - Automatic Flusher10/21/20Automated Flushing SystemMueller HydroguardHG6-A-IN-2-BRN-LPRR(Portable) HG2-A-IN--2-PVC-018-LPLG(Permanent)04/09/21Automated Flushing SystemKupferle Foundry CompanyEclipse #9800wc04/09/21Automated Flushing SystemKupferle Foundry CompanyEclipse #9700 (Portable)* From Original Standard Products ListClick to Return to the Table of Content36Updated:04/09/2021