HomeMy WebLinkAboutContract 57226-PM1PROJECT MANUAL
FOR
THE CONSTRUCTION OF
PUBLIC WATER & PAVING IMPROVEMENTS
TO SERVE
ALLIANCE CENTER NORTH - 8
IPRC Record No. IPRC21-0138
City Project No. 103761
FID No: 30114-0200431-103761-E07685
Mattie Parker David Cooke
Mayor City Manager
Christopher P. Harder, P.E.
Director, Water Department
William Johnson
Director, Transportation and Public Works Department
Prepared for
The City of Fort Worth
November 2021
PREPARED BY
PELOTON LAND SOLUTIONS
9800 HILLWOOD PARKWAY, SUITE 250
FORT WORTH, TEXAS 76177
817-562-3350
TBPE Firm No. 12207
CSC No. 57226-PM1
00 00 00
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Page 1 of 5
CITY OF FORT WORTH Public Water Improvements to serve Alliance Center North - 8
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No. 103761
Revised March 20, 2020
SECTION 00 00 10
TABLE OF CONTENTS
DEVELOPER AWARDED PROJECTS
Division 00 - General Conditions Last Revised
00 11 13 Invitation to Bidders 03/20/2020
00 21 13 Instructions to Bidders 03/20/2020
00 41 00 Bid Form 04/02/2014
00 42 43 Proposal Form Unit Price 05/22/2019
00 43 13 Bid Bond 04/02/2014
00 45 11 Bidders Prequalification’s 04/02/2014
00 45 12 Prequalification Statement 09/01/2015
00 45 13 Bidder Prequalification Application 03/09/2020
00 45 26 Contractor Compliance with Workers' Compensation Law 04/02/2014
00 45 40 Minority Business Enterprise Goal 08/21/2018
00 52 43 Agreement 06/16/2016
00 61 25 Certificate of Insurance 07/01/2011
00 62 13 Performance Bond 01/31/2012
00 62 14 Payment Bond 01/31/2012
00 62 19 Maintenance Bond 01/31/2012
00 72 00 General Conditions 11/15/2017
00 73 00 Supplementary Conditions 07/01/2011
00 73 10 Standard City Conditions of the Construction Contract for Developer
Awarded Projects 01/10/2013
Division 01 -General Requirements Last Revised
01 11 00 Summary of Work 12/20/2012
01 25 00 Substitution Procedures 08/30/2013
01 31 19 Preconstruction Meeting 08/30/2013
01 31 20 Project Meetings 07/01/2011
01 32 33 Preconstruction Video 08/30/2013
01 33 00 Submittals 08/30/2013
01 35 13 Special Project Procedures 08/30/2013
01 45 23 Testing and Inspection Services 03/20/2020
01 50 00 Temporary Facilities and Controls 07/01/2011
01 55 26 Street Use Permit and Modifications to Traffic Control 07/01/2011
01 57 13 Storm Water Pollution Prevention Plan 07/01/2011
01 60 00 Product Requirements 03/20/2020
01 66 00 Product Storage and Handling Requirements 04/07/2014
01 70 00 Mobilization and Remobilization 04/07/2014
01 71 23 Construction Staking 04/07/2014
01 74 23 Cleaning 04/07/2014
01 77 19 Closeout Requirements 04/07/2014
01 78 23 Operation and Maintenance Data 04/07/2014
01 78 39 Project Record Documents 04/07/2014
00 00 00
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Page 2 of 5
CITY OF FORT WORTH Public Water Improvements to serve Alliance Center North - 8
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No. 103761
Revised March 20, 2020
Technical Specifications which have been modified by the Engineer specifically for this
Project; hard copies are included in the Project’s Contract Documents
NONE
Technical Specifications listed below are included for this Project by reference and can be
viewed/downloaded from the City’s website at:
http://fortworthtexas.gov/tpw/contractors/
Division 02 - Existing Conditions Last Revised
02 41 13 Selective Site Demolition 12/20/2012
02 41 14 Utility Removal/Abandonment 12/20/2012
02 41 15 Paving Removal 02/02/2016
Division 03 - Concrete
03 30 00 Cast-In-Place Concrete 12/20/2012
03 34 13 Controlled Low Strength Material (CLSM)12/20/2012
03 34 16 Concrete Base Material for Trench Repair 12/20/2012
03 80 00 Modifications to Existing Concrete Structures 12/20/2012
Division 26 - Electrical
26 05 00 Common Work Results for Electrical 11/22/2013
26 05 10 Demolition for Electrical Systems 12/20/2012
26 05 33 Raceways and Boxes for Electrical Systems 12/20/2012
26 05 43 Underground Ducts and Raceways for Electrical Systems 07/01/2011
26 05 50 Communications Multi-Duct Conduit 02/26/2016
Division 31 - Earthwork
31 10 00 Site Clearing 12/20/2012
31 23 16 Unclassified Excavation 01/28/2013
31 23 23 Borrow 01/28/2013
31 24 00 Embankments 01/28/2013
31 25 00 Erosion and Sediment Control 12/20/2012
31 36 00 Gabions 12/20/2012
31 37 00 Riprap 12/20/2012
Division 32 - Exterior Improvements
32 01 17 Permanent Asphalt Paving Repair 12/20/2012
32 01 18 Temporary Asphalt Paving Repair 12/20/2012
32 01 29 Concrete Paving Repair 12/20/2012
32 11 23 Flexible Base Courses 12/20/2012
32 11 29 Lime Treated Base Courses 12/20/2012
32 11 33 Cement Treated Base Courses 12/20/2012
32 11 37 Liquid Treated Soil Stabilizer 08/21/2015
32 12 16 Asphalt Paving 12/20/2012
32 12 73 Asphalt Paving Crack Sealants 12/20/2012
32 13 13 Concrete Paving 12/20/2012
00 00 00
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Page 3 of 5
CITY OF FORT WORTH Public Water Improvements to serve Alliance Center North - 8
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No. 103761
Revised March 20, 2020
32 13 20 Concrete Sidewalks, Driveways and Barrier Free Ramps 06/05/2018
32 13 73 Concrete Paving Joint Sealants 12/20/2012
32 14 16 Brick Unit Paving 12/20/2012
32 16 13 Concrete Curb and Gutters and Valley Gutters 10/05/2016
32 17 23 Pavement Markings 11/22/2013
32 17 25 Curb Address Painting 11/04/2013
32 31 13 Chain Fences and Gates 12/20/2012
32 31 26 Wire Fences and Gates 12/20/2012
32 31 29 Wood Fences and Gates 12/20/2012
32 32 13 Cast-in-Place Concrete Retaining Walls 06/05/2018
32 91 19 Topsoil Placement and Finishing of Parkways 12/20/2012
32 92 13 Hydro-Mulching, Seeding, and Sodding 12/20/2012
32 93 43 Trees and Shrubs 12/20/2012
Division 33 - Utilities
33 01 30 Sewer and Manhole Testing 12/20/2012
33 01 31 Closed Circuit Television (CCTV) Inspection 03/03/2016
33 03 10 Bypass Pumping of Existing Sewer Systems 12/20/2012
33 04 10 Joint Bonding and Electrical Isolation 12/20/2012
33 04 11 Corrosion Control Test Stations 12/20/2012
33 04 12 Magnesium Anode Cathodic Protection System 12/20/2012
33 04 30 Temporary Water Services 07/01/2011
33 04 40 Cleaning and Acceptance Testing of Water Mains 02/06/2013
33 04 50 Cleaning of Sewer Mains 12/20/2012
33 05 10 Utility Trench Excavation, Embedment, and Backfill 12/12/2016
33 05 12 Water Line Lowering 12/20/2012
33 05 13 Frame, Cover and Grade Rings –Cast Iron 01/22/2016
33 05 13.10 Frame, Cover and Grade Rings –Composite 01/22/2016
33 05 14 Adjusting Manholes, Inlets, Valve Boxes, and Other Structures to
Grade 12/20/2012
33 05 16 Concrete Water Vaults 12/20/2012
33 05 17 Concrete Collars 12/20/2012
33 05 20 Auger Boring 12/20/2012
33 05 21 Tunnel Liner Plate 12/20/2012
33 05 22 Steel Casing Pipe 12/20/2012
33 05 23 Hand Tunneling 12/20/2012
33 05 24 Installation of Carrier Pipe in Casing or Tunnel Liner Plate 06/19/2013
33 05 26 Utility Markers/Locators 12/20/2012
33 05 30 Location of Existing Utilities 12/20/2012
33 11 05 Bolts, Nuts, and Gaskets 12/20/2012
33 11 10 Ductile Iron Pipe 12/20/2012
33 11 11 Ductile Iron Fittings 12/20/2012
33 11 12 Polyvinyl Chloride (PVC) Pressure Pipe 11/16/2018
33 11 13 Concrete Pressure Pipe, Bar-Wrapped, Steel Cylinder Type 12/20/2012
33 11 14 Buried Steel Pipe and Fittings 12/20/2012
33 12 10 Water Services 1-inch to 2-inch 02/14/2017
33 12 11 Large Water Meters 12/20/2012
33 12 20 Resilient Seated Gate Valve 12/20/2012
33 12 21 AWWA Rubber-Seated Butterfly Valves 12/20/2012
00 00 00
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Page 4 of 5
CITY OF FORT WORTH Public Water Improvements to serve Alliance Center North - 8
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No. 103761
Revised March 20, 2020
33 12 25 Connection to Existing Water Mains 02/06/2013
33 12 30 Combination Air Valve Assemblies for Potable Water Systems 12/20/2012
33 12 40 Fire Hydrants 01/03/2014
33 12 50 Water Sample Stations 12/20/2012
33 12 60 Standard Blow-off Valve Assembly 06/19/2013
33 31 12 Cured in Place Pipe (CIPP)12/20/2012
33 31 13 Fiberglass Reinforced Pipe for Gravity Sanitary Sewers 12/20/2012
33 31 15 High Density Polyethylene (HDPE) Pipe for Sanitary Sewer 12/20/2012
33 31 20 Polyvinyl Chloride (PVC) Gravity Sanitary Sewer Pipe 06/19/2013
33 31 21 Polyvinyl Chloride (PVC) Closed Profile Gravity Sanitary Sewer
Pipe 12/20/2012
33 31 22 Sanitary Sewer Slip Lining 12/20/2012
33 31 23 Sanitary Sewer Pipe Enlargement 12/20/2012
33 31 50 Sanitary Sewer Service Connections and Service Line 04/26/2013
33 31 70 Combination Air Valve for Sanitary Sewer Force Mains 12/20/2012
33 39 10 Cast-in-Place Concrete Manholes 12/20/2012
33 39 20 Precast Concrete Manholes 12/20/2012
33 39 30 Fiberglass Manholes 12/20/2012
33 39 40 Wastewater Access Chamber (WAC)12/20/2012
33 39 60 Epoxy Liners for Sanitary Sewer Structures 12/20/2012
33 41 10 Reinforced Concrete Storm Sewer Pipe/Culverts 07/01/2011
33 41 11 High Density Polyethylene (HDPE) Pipe for Storm Drain 12/20/2012
33 41 12 Reinforced Polyethlene (SRPE) Pipe 11/13/2015
33 46 00 Subdrainage 12/20/2012
33 46 01 Slotted Storm Drains 07/01/2011
33 46 02 Trench Drains 07/01/2011
33 49 10 Cast-in-Place Manholes and Junction Boxes 12/20/2012
33 49 20 Curb and Drop Inlets 12/20/2012
33 49 40 Storm Drainage Headwalls and Wingwalls 07/01/2011
Division 34 -Transportation
34 41 10 Traffic Signals 10/12/2015
34 41 10.01 Attachment A –Controller Cabinet 12/18/2015
34 41 10.02 Attachment B –Controller Specification 02/2012
34 41 10.03 Attachment C –Software Specification 01/2012
34 41 11 Temporary Traffic Signals 11/22/2013
34 41 13 Removing Traffic Signals 12/20/2012
34 41 15 Rectangular Rapid Flashing Beacon 11/22/2013
34 41 16 Pedestrian Hybrid Signal 11/22/2013
34 41 20 Roadway Illumination Assemblies 12/20/2012
34 41 20.01 Arterial LED Roadway Luminaires 06/15/2015
34 41 20.02 Freeway LED Roadway Luminaires 06/15/2015
34 41 20.03 Residential LED Roadway Luminaires 06/15/2015
34 41 30 Aluminum Signs 11/12/2013
34 41 50 Single-Mode Fiber Optic Cable 02/26/2016
34 71 13 Traffic Control 11/22/2013
00 00 00
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Page 5 of 5
CITY OF FORT WORTH Public Water Improvements to serve Alliance Center North - 8
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project No. 103761
Revised March 20, 2020
Appendix
GC-4.01 Availability of Lands
GC-4.02 Subsurface and Physical Conditions
GC-4.04 Underground Facilities
GC-4.06 Hazardous Environmental Condition at Site
GC-6.06.D Minority and Women Owned Business Enterprise Compliance
GC-6.07 Wage Rates
GC-6.09 Permits and Utilities
GC-6.24 Nondiscrimination
GR-01 60 00 Product Requirements
END OF SECTION
00 42 43
�AP - BID PAOPOSAL
Page 1 of 1
SECTION 00 42 43
Developer Awarded Projects - PROPOSAL FORM
UNIT PRICE BID
Bidder's Application
ALLIANCE CENTER NORTH 8- PUBLIC WATER & PAVING IMPROVEMENTS
Project Item Information Bidder's Proposal
Bidlist Item Specification Unit of
No. Descripfion Section No. Measure Bid Quanrity Unit Price Bid Value
UNIT I: WATER IMPROVEMENTS
1 3125.0101 SWPPP > 1 acre 31 25 00 LS 1 $2,000.00 $2.000.00
2 3311.0001 Ductile Iron Water Fittings w/ Restraint 33 11 11 TON 0.84 $12,000.00 $10,080.00
3 3312.2203 2" Water Service 33 12 10 EA 3 $3,500.00 $10,500.00
4 3312.3005 12" Gate Valve 33 12 20 EA 2.00 33,800.00 $7 600.00
5 9999.0001 Concrete Blocking, Type B 00 00 00 CY 0.60 $500.00 $300.00
TOTAL UNIT I: WATER IMPROVEMENTS $30,480.00
B;d
UNIT II: PAVING IMPROVEMENTS
T6is Bid is submitted by the entity, named below:
Total Construction
$30,480.00
� �� $109.284.00
BIDDER: BY: BROCK HUGGINS
CONATSER CONSTRUCTION TX, L.P.
5327 WICH(TA STREET
FORT WORTH, TX 761I9 TITLE: PRESIDEi. I'
DATE:
Contractor agrees to complete WORK far FINAL ACCEPTANCE within 30 workin� days after the date when the
CONTRACT commences to run as provided in the General Conditioos.
E!VD OF SECTION
CITY'OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATTON DOCUMENTS - DEVELOPERAWARDED PROJECTS
Fmm Vereion May 22, 2019 00 42 43_WSS_Bid Proposnl_DAP_ACN8
0o as t?
DAP PREQUALIFICATION STATEMENT
P.ige ] of 1
SECTION 00 45 12
DAP — PREQUALIFICATION STATEMENT
Each Bidder is required to complete the information below by identifying the prequalified cont�•actors
and/or subcontractors whoni they intend to utilize for the major work type(s) listed. In the "Major Work
Type" box provide the com�lete major work type and actual description as provided by the Water
Departme��t for water and sewer and TPW for paving.
Major Work Type Contractor/Subcontractor Company Name Prequalification
EXpiration Date
Water �listribution, Developroent, , � ,,� ,
l6 inches and smaller. �����fi`�'� ����5���''��� � � �—� l��/ �� / a�
Concrete Con/Reco�� <l 5,000 SY ���-�-����-- �i��„��,��.-�-�,�,� �( � Lp � � 3 � � .�
Tl�e undersigned hereby certifies that the contractors and/or subcontractors described in the table above
are currently prequalified for tl�e work types listed.
BIDDER:
By:
C�'�'1C�fiSt;x_�.�>S�1Yl. �C-�-1�� ( x, ��� i�Y �t�C1�-� l" ���1C4 �a i IiS
Company (Please Print)
Signature: �
�����1 N! � (�'� � t� ��.
Address
Title:
t�...'�'r �UC>�'�1'�,TX�ir_�l I� N��SiGle�'l1"
City/State/Zip (Please Print)
Date: c�ctn(,dGC'Y���ZZ
END OF SECTION
CITY OF FORT WORTH
STANDARD CONSTRUCTION PREQUALIFlCATION STATEMENT — DEVELOPER AWARDED PROJECTS Wtr & Pav Imprvmnts to serve Alliance Center North - 8
Form Version September 1, 2015 Clty P�OjeCt NO. 103761
00 45 26 - 1
CONTRACTOR COMPLIANCE WITH WORKER'S COMPENSATION LAW
Page 1 of 2
1
2
SECTION 00 45 26
CONTRACTOR COMPLIANCE WITH WORKER'S COMPENSATION LAW
3 Pursuant to Texas Labor Code Section 406.096(a), as amended, Contractor certifies that it
4 provides worker's compensation insurance coverage for all of its employees employed on City
5 Project No. 103761 Contractor further certifies that, pursuant to Texas Labor Code, Section
6 406.096(b), as amended, it will provide to City its subcontractor's certificates of compliance with
7 worker's compensation coverage.
�
9 CONTRACTOR:
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
C��'lC'iT�f'X' Cs�'1 �fiYt _a C_�l �_TX , L{� BY : t-� Y�C�k=- �-4� Ca 1115
Company (Please Print)
�
��"l Vti i��`l� t Ci S�• Signature:
Address
�t;�V�i �1"C�Vi�'1 T% �ilG�� l�j Title: 1�r�� IC�`�i�'�lfi
City/State/Zip (Please Print)
THE STATE OF TEXAS
COUNTY OF TARRANT
§
§
BEFORE ME, the undersigned authority, on this day personally appeared
�C (,Y,�. �,�,�('�� rl� , known to me to be the person whose name is
subscribed to the foregoing instrument, and acknowledged to me that he/she executed the
same as the act and deed of ���� 1-�— for the purposes and
consideration therein expressed and in the capacity therein stated.
GIVEN UNDER MY HAND AND SEAL OF OFFICE this �I� _day of
�anur��`� , zo22
,w �_ ,�,6 KAMRA HOERIG
i��y, �� Notary Public, Statc of Texas
s�,T/�,�P Comm.Expires08/IS/2023
.9TF �� ��} Notary ID 13213162-8
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised April 2, 2014
C/�/V
Notary Public in and for e State of Texas
Wtr & Pav Imprvmnts to serve Alliarice Center North - 8
City Project No. 103761
0
004526-2
CONTRACTOR COMPLIANCE WITH WORKER'S COMPENSATION lAW
Page 2 of 2
1
2
3
J
�
�
�
�
�
�
�
J
�
�
�
END OF SECTION
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised April 2, 2014
Wtr & Pav Imprvmnts to serve Alliance Center North - 8
City Project No. 103761
:
005243-1
Developer Awarded Project Agreement
Page 1 of 6
1
�
SECTION 00 52 43
AGREEMENT
3 THIS AGREEMENT, authorized on ��1�2Lis made by and between the Developer,
4 Hillwood Alliance Services, LLC, a Texas limited liability Company, authorized to do business in
5 Texas ("Developer"), and ��4'����C'►'-GC�'1,511'UC. (��1�7 1 i` , �-1-� , authorized to
6 do business in Texas, acting by and through its duly authorized representative, ("Contractor").
7 Developer and Contractor, in consideration of the mutual covenants hereinafter set forth, agree
8 as follows:
9 Article 1. WORK
10 Contractor shall complete all Work as specified or indicated in the Contract Documents for the
11 Project identified herein.
12 Article 2. PROJECT
13 The project for which the Work under the Contract Documents may be the whole or only a part
14 is generally described as follows:
15 Public Water & Pavin p Improvements to serve Alliance Center North - 8.
16 CPN:103761
17 Article 3. CONTRACT TIME
18 3.1 Time is of the essence.
19 All time limits for Milestones, if any, and Final Acceptance as stated in the Contract
20 Documents are of the essence to this Contract.
21 3.2 Final Acceptance.
22 The Work will be complete for Final Acceptance within {._��3._.� working days after the date
23 when the Contract Time commences to run as provided in Paragraph 12.04 of the
24 Standard City Conditions of the Construction Contract for Developer Awarded Projects.
25 3.3 Liquidated damages
26 Contractor recognizes that time is of the essence of this Agreement and that Developer
27 will suffer financial loss if the Work is not completed within the times specified in
28 Paragraph 3.2 above, plus any extension thereof allowed in accordance with Article 10
29 of the Standard City Conditions of the Construction Contract for Developer Awarded
30 Projects. The Contractor also recognizes the delays, expense and difficulties involved in
CITY OF FORT WORTH Wtr & Pav Imprvmnts to serve Alliance Center North - 8
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PRO.IECTS City Project No. 103761
Revised June 16.2016
�
005243-2
Developer Awarded Project Agreement
Page 2 of 6
31 proving in a legal proceeding the actual loss suffered by the Developer if the Work is not
32 completed on time. Accordingly, instead of requiring any such proof, Contractor agrees
33 that as liquidated damages for delay (but not as a penalty), Contractor shall pay
34 Developer
35 Dollars ($ ) for each day that expires after the time
36 specified in Paragraph 3.2 for Final Acceptance until the City issues the Final Letter of
37 Acceptance.
38 Article 4. CONTRACT PRICE
39 Developer agrees to pay Contractor for performance of the Work in accordance with the
40 Contract Documents an amount in current funds of
41 Dollars($ I�'�,���'•� ).
42 Article 5. CONTRACT DOCUMENTS
43 5.1 CONTENTS:
44 A. The Contract Documents which comprise the entire agreement between Developer
45 and Contractor concerning the Work consist of the following:
46 1. This Agreement.
47 2. Attachments to this Agreement:
48 a. Bid Form (As provided by Developer)
49 1) Proposal Form (DAP Version)
50 2) Prequalification Statement
51 3) State and Federal documents (projectspecificJ
52 b. Insurance ACORD Form(s)
53 c. Payment Bond (DAP Version)
54 d. Performance Bond (DAP Version)
55 e. Maintenance Bond (DAP Version)
56 f. Power of Attorney for the Bonds
57 g. Worker's Compensation Affidavit
58 h. MBE and/or SBE Commitment Form (If required)
59 3. Standard City General Conditions of the Construction Contract for Developer
60 Awarded Projects.
CITY OF PORT w'ORTH Wtr & Pav Imprvmnts to serve Alliance Center North - 8
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DLVELOPER AWARDED PRO.IECTS City Project No. 103761
Revised .lune 16, 2016
J
005243-3
Developer Awarded Project Agreement
Page 3 of 6
61 4. Supplementary Conditions.
62 5. Specifications specifically made a part of the Contract Documents by attachment
63 or, if not attached, as incorporated by reference and described in the Table of
64 Contents of the Project's Contract Documents.
65 6. Drawings.
66 7. Addenda.
67 8. Documentation submitted by Contractor prior to Notice of Award.
68 9. The following which may be delivered or issued after the Effective Date of the
69 Agreement and, if issued, become an incorporated part of the Contract
70 Documents:
71 a. Notice to Proceed.
72 b. Field Orders.
73 c. Change Orders.
74 d. Letter of Final Acceptance.
75
76
�
�
�
J
J
CITY OP FORT w'ORTH Wtr & Pav Imprvmnts to serve Alliance Center North - 8
S"I'ANDARD CONS'1'RUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PRO.IECTS City Project No. 103761
Revised .lune 16.2016
_J
005243-4
Developer Awarded Project Agreement
Page 4 of 6
77 Article 6. INDEMNIFICATION
78 6.1 Contractor covenants and agrees to indemnify, hold harmless and defend, at its own
79 expense, the city, its officers, servants and employees, from and against any and all
80 claims arising out of, or alleged to arise out of, the work and services to be perFormed by
81 the contractor, its officers, agents, employees, subcontractors, licenses or invitees under
82 this contract. This indemnification provision is specifically intended to operate and be
83 effective even if it is alle�ed or proven that all or some of the dama�es bein� sou�ht
84 were caused, in whole or in part, bv any act, omission or negli�ence of the city. This
85 indemnity provision is intended to include, without limitation, indemnity for costs,
86 expenses and legal fees incurred by the city in defending against such claims and causes
87 of actions.
::
89 6.2 Contractor covenants and agrees to indemnify and hold harmless, at its own expense,
90 the city, its officers, servants and employees, from and against any and all loss, damage
91 or destruction of property of the city, arising out of, or alleged to arise out of, the work
92 and services to be performed by the contractor, its officers, agents, employees,
93 subcontractors, licensees or invitees under this contract. This indemnification provision
94 is specifically intended to operate and be effective even if it is alle�ed or proven that all
95 or some of the dama�es bein� sou�ht were caused, in whole or in part, bv anv act,
96 omission or ne�ligence of the city.
97
98 Article 7. MISCELLANEOUS
99 7.1 Terms.
100 Terms used in this Agreement are defined in Article 1 of the Standard City Conditions of
101 the Construction Contract for Developer Awarded Projects.
102 7.2 Assignment of Contract.
103 This Agreement, including all of the Contract Documents may not be assigned by the
104 Contractor without the advanced express written consent of the Developer.
105 7.3 Successors and Assigns.
106 Developer and Contractor each binds itself, its partners, successors, assigns and legal
107 representatives to the other party hereto, in respect to all covenants, agreements and
108 obligations contained in the Contract Documents.
CITY OP FORT WORTH Wtr & Pav Imprvmnts to serve Alliance Center Norih - 8
STANDARD CONSTRUCTION SPECIFICA7'ION DOCUMENTS — DEV�LOPER AWARDED PRO.IECTS City Projed No. 103761
Revised June ] 6. 2016
�
005243-5
Developer Awarded Project Agreernent
Page 5 of 6
109 7.4 Severability.
110 Any provision or part of the Contract Documents held to be unconstitutional, void or
111 unenforceable by a court of competent jurisdiction shall be deemed stricken, ar�d all
112 remaining provisions shall continue to be valid and binding upon DEVELOPER and
113 CONTRACTOR.
114 7.5 Governing Law and Venue.
115 This Agreement, including all of the Contract Documents is performable in the State of
116 Texas. Venue shall be Tarrant County, Texas, or the United States District Court for the
117 Northern District of Texas, Fort Worth Division.
118
119
120
121
122
123
124
125
126
127
128
129
130
131
132
133
134
135
136
7.6 Authority to Sign.
Contractor shall attach evidence of authority to sign Agreement, if other than duly
authorized signatory of the Contractor.
IN WITNESS WHEREOF, Developer and Contractor have executed this Agreement in multiple
counterparts.
This Agreement is effective as of the last date signed by the Parties ("Effective Date").
CI"I Y OF FORT WORTH Wtr & Pav Imprvmnts to serve Alliance Center North - 8
STANDARDCONSTRUCTIONSPECIFICATIONDOCUMLNTS—DEVELOPERAWARDEDPRO.IL-CTS CityProjectNo.103761
Revised June 16, 2016
�
Od5243-G
aevelop�r Awarded Pro�ect kgreement
Page 6 of 6
Contractor:
Developer:
�_, . L -
• �
'�t.: ar� T��C.�,�_.C�;.��t� �;:.-4�-L-4� �t�'�r....���� ��: , �_ ',.�.iC10 . � �4��'�j . ���G.:C-��' _
By: � � y:
--, — --
(5i ure} "�� naturej
137
--- ' i -�: i C, = :_ i'�L�1� 1� , � � �;
�
(Printed �lame)
Title: ._,
Yi��_' ;� C��:x" l � -----
Company Name: ��`����'�"
r, �
C_ ���.�� T l'"r. �# C.�" i tiy�7` l� X, i_ }='
Add ress:
__ `�� vU ; C;�'1, t<.� .�r . _.._
Ci��/State/Zip
��`.��1 _�'i�C 1 � i`_ � . i� �' � p� i �� �
�nu�?.�i�.��.�-
Date
• `�t..S`�-� � � � _ _ _ -- --
tt1
(Printe me)
Title:
_____... ._._..� -- - ---
-r__- - - --
Companyname: � �� Lc�t7vr.�..�C1�eAY1Cp'j�..fl1tiC„�'j, �-.�C
AAddress--- �� / � `� � �2�t`K+w � �c.s�S~�
_..! � �'1 ,.f [n.'at�
�
__ �-� G✓���,,- -��.� 7�'f? -
City/State/Zip:
-- --�e.,� cn___ a,, r��i`'1 �'' � Z 0 Z Z `
Date
Cl�il' OF fOR�i V.'t)R�I�1 I Wv &�av tmprvmnts to;erve Alliance Center North - 8
S'iANDARDf'(�NSTRiIi'�Ck1�vSNt�:(�IFICAI�It)NI)OCt`P4PN'I'S DfVELUI'FRA��'ARDi�ff)PRr).tl�l'TS CiryPro/e�tNo.IG37fi7
Reeiscd hinc Ie.201t,
Bond No. 0242726
OO G2 23 1
PER�ORMANCE BOND
Page 1 of 3
1
2
3
4
5
fi
7
SECTION 00 5213
PERFORMANCE BOND
3HE SiATE OF TEXAS §
§ KNOiN ALL 8Y THESE PRE5EfdT5:
COUNTY OF TAiiRANT §
That w2, Conatser Construction TX, L.P. known 8S
-- ----�
8 "Principal" herein and Berkley Insurance Company a Corporate
9 surety(sureties, if more than ane} duly authorized to do business in the State of Texas, known as
20 "Surety" herein (whether c�ne ar morej, are held and firmly bound unto the Deve�oper, Hillwaad
11 Aliiance Services„ ILC,:, authorized to do business in Texas ("Oeveloper") attd the City of Fort
12 Warth, a 7exas muniCipa) corporation �"Cit�'}, in the penal sum of, One Hundred Thirty Nine Thousand,
13 Seven Hundred Sixty Four and No/100- ------------------ Dollars ($ 139,764.00 },
14 lawful money nf the United States, to be paid +n Fort Worth, Tarrant County, Texas for the
15 payment of which sum weil and truly to be made jointly unto the Deveioper and the City as dual
16 ohliges, we �ind ourselves, our heirs, executars, adminis#rators, succes5ors and assigns, jointly
I7 and severally, firmly by these presents.
18 WHEREAS, Developar and City have enterQd into an Agreement for the construction of
I9 tommunity facilities in the City af Fort Worth by and through a Community Facilities Agreement,
2o CFA Number Gf!4_.21- ��.6b_, and
21 WHER�A5, the Principal has entered inta a certain written contract witt► the Cleveloper awarded
22 the day of Jfi1t�N.lGfy 2.� z0___,Z whicl� �ontract is hereby referred to and made a
23 parc hereof for all purpases as if fully set forth herein, ta furnish all materials, equipment labor
24 and other accessories defineti by law, in the prosecution of the Work, including any Change
25
26
Orders, as provided for in said �ontraci designated as Public Water Impro�ements to serve
Alliance Center North — 8.
27 NOW, THEREFORE, the condition of this obligation is such that if the said Principal shall
28 faithfuJly perform it ob4igatians underthe Contract artd 5ha11 in a[I respetts duly and faithfully
Z9 perfarrxi �he Work, including Change Orders, under the Cantract, according to the plans,
CITY O F FORT WORTH Wtr & Pav lmprvmrtts fo sern Allianct Center North - 8
STANDARD Ct7Y CONOtT10k5- DEVEIOPER AWAR�ED PROJECTSCity tiryProject No. I03761
Kevised lanuary 31, 2012
�
1
006213-2
PERFORMANCE BOND
Page 2 of 3
1 specifications, and contract docurnents therein referred to, and aswell during any period of
2 extension af the Cantract that may be granted an the part of the aeveloper and/or City, then
3 this o�ligation shall be and become nufl and void, Qtherwise to remain in full force and effect.
4 PROVIDEp FURTNER, that if any legal action be fled on this Bond, venue 5ha11 lie in
.� Tarrant Ca�nty, Texas or the United States District Court for the Northern District of Texas, Fort
6 Worth Divisian.
7 This bond is made and executed in compliance with the provisions of Chapter 2253 of
8 the Texas Government Code, as amended, and all liabilities on this bond shall lae determined in
9 accardance with the provisions of said statue.
10 IN WiiNE55 WHEREOF, #he Printipal and the Surety have SIGNFb and SEALED this
11 instrument by duly authorized agents and otFicers on this the day ofi�
12 2��'� 20 �2 .
PRf NC�PAL:
Conatser Construction TX, L.P.
_ _
AITEST: `����v7�'v!� � _
gY: �
Si�n�ture
/�G��?�N `
� Brock Huggins, Presiderrt
(Principal} Secretary Name and Title
Addres5: 5327 Wichita St.
Fort Worth, TX 761 19
_ Itvc.�-�.ie.� I��:-� �
Witness as to Princi�al
CITY OF FO R� WORTN Wtr � Pav fmpnmrnts to sern A11Jvnce Lenter Marth - 8
SiANQARDCITY CONDI710NS—CEVELOPER AWAR�ED PROJECTSCIry City Pro)eCE No. i03761
Revised lanuary 31, 2012
�
W6223-3
PERFOR�qRNCF 64Nb
Page 3 ot 3
SURETY�
Berkley Insurance Company
ATTEST: $Y" �_,,.���%- _J'LI���,
Signature
_ ���.1r���`.._
(5uretyj Secretary
_ _/lr:��
Witness as to Sur2ty
Robbi Morales, Attorney-in-fact
Name and Title
AddYess: 5005 LBJ Fr•eeway, Suite 1500
Dallas, TX 75244
Telephone Nurnber 214/989-0000
0
1
�
3
4
5
6
7
8
�
'"Note: If signed by an officer of the Surety Company, there must be an file a certified extract
from the by-laws showing that this person has authority to sign such abligatior�. If
Suret�s physicai address is different frnm its mai4ing address, bot� must be provided.
The date of the bond shail not i�e praar to the date the Contract is awarded.
CITY OF FORT WdpTH Wfr & Po� lmprvmnt5 to SefVe plilO�rCp Center Morth - 8
STAkDAR�CITY COND!TtONS - DEVEIOPER AWARDED PROJECfSCrry �iry Arojett No. 14376I
Revised l�nuary 31. 2Q:2
Bond No. 0242726
oc bz ia - �
?AYUIEM BOND
Pagelof3
1
a
3
4
5
6
7
$
9
1tl
11
lz
13
SECTfO�I 00 6Z 34
PAYMENT 80ND
7HE STATE OF TEXAS
COUNTY Of TARRANi
That we,
§
§
§
KNOW ALL BY THESE PRESfNTS:
Conatser Constructioil TX, L.P.
known as
"Principal" herein, and Berkley Insurance Co�npany a
corparete surety ( ar su�e�s�s a� �t-�C�r� �h�t� t�t'r�?, ttu+y �uth�riz�� t0 do buSirtESS irt the State of
iexas, known as "Surety" h�rein {whether one or morej, are held and firmly bound unto the
Deve{�per, (Hillwoad AIlianee Services, LLG), authariz�d to da business in Texas "(Develope�"�,
ant� the City �f Fort Worth, a i��r�.� r;�;;r„`;:��I cc�rporatian ("�iiy:`) in the ��na1 sum
One Hundred Thirty Nine Thousand,
of Seven Hundred Sixty Four and No/100--------------------- ppllars {$ 139,764.00 7,
14 lawful money of the United States, to be paid in Fort Worth, Tarrant Cou�ty, 7exas, for the
15 paymen# 4f which sum well and truly be rnade jointly unto the Developer and the City as dual
16 obliges, we bind oursetves, our heirs, executors, adrninistrators, successors an� assigns, jointly
17 and severaliy, firmly by these presents:
18 WNEREAS, Developer and City have entered into an agreement for the construction of
19 �omrnunity facilities in the City of Fort Worth, 6y and through a Community Facilities
2Q A�reernent, CFA Number Cf/� �,�-616b and
21 WHEREAS, Principol has entered inta a tertain written Contract with Develaper,
22 awarded the day ot �'c�nuarY Z�It�h zo� which Contract is hereby
i3 referred to and made � part hereof for all purposes as if fuliy set forth herein, tca ft�rnish a11
Z4 materials, equipment, fabor and other accessories as defined by law, in the prosecutian af the
25 Work as provided for in said Contract and designated as P,�,�I�c Water & Pavin�,� Im�lrovements to
26 serve AIl+ance Cer�ter �rth -8.
�7 NOW, THEREFCiRE, THE CONDITION (JF THlS OBLICRTION is such that if Princi�al shali
2B pay aEi monies owing to any (and ailj payrr�ent bor�d beneficiar}+ (as defined in Chapter 2253 of
29 the Texas Government Cade, as amended) in t�e prosecution of the Work under the Contract,
CITY OF F�R7 WOR'fH
STANDARD C!'Y CDNOfTIONS - DEVELOPER AWARDED �R01ECT5
� RevfsedJanuary 31 2�i2
Wt� & Pau Jmprvmat; to serve APl�ance tenter Narth - 8
City Projeci No 203761
_J
006214-Z
PAYMENf BQNp
Page 2 af 3
2 then this obligation shall be and become nutl and void; otherwise, to remain in fu11 for�e and
z effect.
3 This bond is made and executed in compiiance with the provisions of Cha�rter 2253 of
4 the Texas Gavemment Code, as amend�d, and all liabilities on this bond shatl be determ►ned in
5 accordar�ce with #he pravisions of said statute.
fi IN WITNE55 WHEREOF, the Principal and Surety have each 5iGNED and SEAl.Et7 this
7 instrument by duly authorized agents and officers on this the day of
$ J�huury Z�1 �I� , zo 22 .
ATTEST:
i�����"''' `
�
(Principal) Secretary
���, � -��. .
Witness as ta Principal
CITv pF FOR7 WORTH
STANDARp CITY CONdlTIONS — DEVELOPER AWARDED PRO)ECTS
RevlsedJanuary 31. 2012
PRINCIPA�.
Conatser Construction TX, L.P.
����'�/ ,
BY� � __
5ignature
Brock I�uggins, President
Name and Title
AddreSS: 53?7 Wichita St.
Foet Wortll, TX 76119
SURETY:
Berkley Insurance Company
Wtr & Ppv lmprvmnts to serve Alliance Cen fer Morth -�
City Proje[t No. 103761
�
606214-3
PAYMENT 6pND
Page 3 of 3
arrFsr �Y� �a-c� 1� ��.-�..�
Sign�ture
� ���.-.—
(5urety� Secretary
Robbi Morales, Attorney-in-fact
Name and Title
Addres5: 5005 LBJ Freeway, Suite 1500
Dallas, TX 75244
.. _ /'6-� ��
tness as to Surety
Tetephone Number: 214,�989-0000
1
2 Note: #f signed by an officer uf the Surety, there must be on fEle a terti�ed extract from the
3 bylaurs showing that this person has au#horlty to sign su�h obHgation, Ii Surety`s physlcai
4 address is different from its mailing address, both must be provided.
5
6 The date of the bond shal! not be prior to the date the Contract is awarded.
7
8
EAfD OF SECTIQN
c+zv oF r-aar waflrH
STANDARp CITY CONDTti0N5 — pEVEIOPER AWAROEO PROlECTS
Revised lanuary 31. 2Q12
Wtr & Pov lmprvmnGc to serve A!!lpnce Center North � 8
City P�aject No. 1Q3T62
_)
Bond No. 0242726
006219�1
MAIIYTENANLE BpND
Page 1 of a
1
Z
3
4
5
6
7
8
9
10
11
22
13
24
15
16
17
18
SECTION 00 6219
MAiNTENANCE BOIVO
THE SiATE OF TF�(Ag §
§ KNOW ALL BY THESE FRESFNTS:
CDUNTY OF TARRANT §
That we Conatser Construction TX, L.P.
_ __._. , known as
"P►'inCipal" herein and Berl<ley Insurance Company
a corporate surety
(sureties, if more than one) duly authorized to do business in the 5#ate of Texas, knawn as
`"5urety" herein (whether one or morej, are held and firmly bound unto the peveloper, Hillwpod
Alliance Services, �LC, authorized to do busi ness in Texas {"Develaper"}, and the City af Fort
Wort�, a Texas munitip�I tor orati n{"City"), in the surn
One Hundred Thirty Nu�e Tl�ousan�,
�f Seveu Hundred Sixty Four and No/100----------- pollars ($ 139,764.00
_ �,
lawful maney o€the United States, to be paid in Fort Warth, Tarrant [ounty, i"exas, far payment
of whict� sum well and truly be made jointly unto the Developer and the City as dual obliges and
their suceessors, we dind ourselves, our heirs, exetutars, administrators, sutcessors and assigns,
joinily and severally, firmly by these presents.
�9 WNEREAS, Developer and City have entered into an Agreement for the construction of
ZO community fatilities in the City of Fort Warth by and through a�ommunity Facilities Agreement,
Z1 CFA Zi-0��; and
ZZ WHEREAS, the Principal has entered into a certain written contract with the Develaper
23 awarded the day ot-����_ Z�i�h
- --__..,�.�_�.__ 20� which ContraCx is
24 hereby referred to and a made part herevf for all purposes as if fully 5et forth herein, to furnish
25 at1 materials, equipment lab4r and other accessaries as defined by law, in the pr�asecution of the
26 Work, includi�g any Work resulting from a duly authorized Cftange Order (collectively herein,
27 the "Work") as provided far in sa id Contract anc! designated as Public Water & Pav(r�e
�S �±r�.Yer�,�n�, to_serve Alliance Center No,r��_, 8. and
29
cm ox FoaT waRrrr
STANDARO CITY C�NDiTI�NS— DEVELOPcR AWARpED PRp;ECT$ �� �' POV �mprvmnts �o SA,ryp p1J�erl�e Center North •$
Revised lanuary 31, 2011 Chy Project No. 103761
ooEzlg-z
MAINTENANCE BOMD
Page 2 of 4
1 Wi1EREAS, Principal binds itseif to use such materials and to so car�struct the Work in
2 accordance with the plans, specifications and Contratt Documents that the Wark is and will
3 remain free from defects in materials or wnrkmanship for and during the period of two (2j years
4 aftPr the date of Final A�eeptance of the Work by the City ("Maintenance Period"j; and
5
b WHEREAS, Principal binds itseEf to repaEr or reconstruct the Work in whofe or in part upon
7 receiving notice from the Deveioper and/or City ofthe need thereof at any time within rhe
8 Maintenance Period.
�
10 fVOW TfiEREFORE, the tonditian of this obligation is such that if Principal shall remedy
21 any cfefective Work, for whitl� timely notice was provided by Qeveloper or City, to a compfetion
12 satisfactory to the City, then thi5 obiigation shali become null and vaitl; othervuise, to remain in
13 full force and effect.
14
15 PROVIDED, HOWEVER, if PriRcipa( shall fail so to repair or recanstruct any timely
16 noticed defective Work, it is agreed that the Develaper or City may cause any and all sueh
17 defective Work to be repaired and/or reconstructed with all associated costs thereof being
18 borne by the Principal and tt�e 5urety under this Maintenance Bond; and
19
2a PROVIDED FiiRTHfR, that if any legal action be filed on this Bond, venue s�a�l lie in
21 Tarrant �aunty, Texas or the Uni#ed States District Court for Ehe Northern District of Texas, Fort
22 Warth Division; anc!
23
Z4 PROVfDEC] FURTHER, that this obiigatian shall be cantinuous in nature and successive
�5 recoveries may be had hereon far successive breathes
26
CIT( OF FORT WQRTIi Wtr � Pov Imprvm�t, to serve q1liance Center Abrth - 8
5TANDARD pTY CdNDIT10N5— DEVELOPER AWAR'JED PROJEC?5 City P�oject No.7d37&1
Revisedlan�ary31, 2i712
�
0062i9-3
MAINTENANCE BOh'Q
Page 3 of 4
d
I �
1 IN WI�NESS WHEREO�, the Principal and the Surety have each SIGNED and SEALED this
2 instrument tay duly authorized agents and officers on this the ___, day of
3 �+n 2�}�, 24 2Z ,
4
5
PRINCIPAL,
Conatser Constructioi� TX, L.P.
AFTEST: ���`��V�'1`� ,
BY: _.
�
Signature
/�4���i�vv�"!� `
V V
(Pri�cipalj Secretary
Brock Huggius, President
Name and Title
Address 5337 Wichita St.
Fort Worth, TX 76119
�.�k�Z�
' _ �� -4`��
Witness as to P�incipal
SURE7Y•
Bei�idey Insurance Company
ATTEST. BY: ��-Z�.�. �-.�--��� .
Signature
CITY 4F FpRT WORTH
STANpAR� CITY CONDiTI0N5 — DfVELOPEA AWARbFp PROJECTS
RevisedJanuary 31, 1012
Wtt & Aw tmprvmnts ta s�rve Alllance Crntei North • 8
City Project No. i03762
006219-4
MAINTENANCE BOND
Page 4 of 4
(Surety) Secretary
Name and Title
Address:
Witness as to Surety
Telephone Number:
1
2 *Note: If signed by an officer of the Surety Company, there must be on file a certified extract
3 from the by-laws showing that this person has authority to sign such obligation. If
4 Surety's physical address is different from its mailing address, both must be provided.
�
6 The date of the bond shall not be prior to the date the Contract is awarded.
7
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS City Project No. 103761
Revised January 31, 2012
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CITY CONDITIONS DEVELOPER AWARDED PROJECTS City Project No. 103761
STANDARD CITY CONDITIONS
OF THE CONSTRUCTION CONTRACT
FOR DEVELOPER AWARDED PROJECTS
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CITY CONDITIONS DEVELOPER AWARDED PROJECTS City Project No. 103761
STANDARD CITY CONDITIONS OF THE
CONSTRUCTION CONTRACT
FOR DEVELOPER AWARDED PROJECTS
TABLE OF CONTENTS
Page
Article 1 Definitions and Terminology .......................................................................................................... 1
1.01 Defined Terms ............................................................................................................................... 1
1.02 Terminology .................................................................................................................................. 5
Article 2 Preliminary Matters ......................................................................................................................... 6
2.01 Before Starting Construction ........................................................................................................ 6
2.02 Preconstruction Conference .......................................................................................................... 6
2.03 Public Meeting .............................................................................................................................. 6
Article 3 Contract Documents and Amending ............................................................................................... 6
3.01 Reference Standards ..................................................................................................................... 6
3.02 Amending and Supplementing Contract Documents .................................................................. 6
Article 4 Bonds and Insurance ....................................................................................................................... 7
4.01 Licensed Sureties and Insurers ..................................................................................................... 7
4.02 Performance, Payment, and Maintenance Bonds ........................................................................ 7
4.03 Certificates of Insurance ............................................................................................................... 7
4.04 Contract s Insurance .................................................................................................................. 9
4.05 Acceptance of Bonds and Insurance; Option to Replace ........................................................... 12
Article 5 Responsibilities ........................................................................................................ 12
5.01 Supervision and Superintendent ................................................................................................. 12
5.02 Labor; Working Hours ................................................................................................................ 13
5.03 Services, Materials, and Equipment ........................................................................................... 13
5.04 Project Schedule .......................................................................................................................... 14
5.05 Substitutes and Or-Equa ....................................................................................................... 14
5.06 Pre-Qualification of Bidders (Prime Contractors and Subcontractors) ..................................... 16
5.07 Concerning Subcontractors, Suppliers, and Others ................................................................... 16
5.08 Wage Rates.................................................................................................................................. 18
5.09 Patent Fees and Royalties ........................................................................................................... 19
5.10 Laws and Regulations ................................................................................................................. 19
5.11 Use of Site and Other Areas ....................................................................................................... 19
5.12 Record Documents ...................................................................................................................... 20
5.13 Safety and Protection .................................................................................................................. 21
5.14 Safety Representative ................................................................................................................. 21
5.15 Hazard Communication Programs ............................................................................................. 22
5.16 Submittals .................................................................................................................................... 22
5.17 Contract s General Warranty and Guarantee .......................................................................... 23
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CITY CONDITIONS DEVELOPER AWARDED PROJECTS City Project No. 103761
5.18 Indemnification ........................................................................................................................... 24
5.19 Delegation of Professional Design Services .............................................................................. 24
5.20 Right to Audit: ............................................................................................................................ 25
5.21 Nondiscrimination....................................................................................................................... 25
Article 6 Other Work at the Site ................................................................................................................... 26
6.01 Related Work at Site ................................................................................................................... 26
Article 7 s Responsibilities................................................................................................................... 26
7.01 Inspections, Tests, and Approvals .............................................................................................. 26
7.02 Limitations on Responsibilities ....................................................................................... 26
7.03 Compliance with Safety Program ............................................................................................... 27
Article 8 tus During Construction ........................................................................... 27
8.01 Project Representative ..................................................................................................... 27
8.02 Authorized Variations in Work .................................................................................................. 27
8.03 Rejecting Defective Work .......................................................................................................... 27
8.04 Determinations for Work Performed .......................................................................................... 28
Article 9 Changes in the Work ..................................................................................................................... 28
9.01 Authorized Changes in the Work ............................................................................................... 28
9.02 Notification to Surety .................................................................................................................. 28
Article 10 Change of Contract Price; Change of Contract Time ................................................................ 28
10.01 Change of Contract Price ............................................................................................................ 28
10.02 Change of Contract Time............................................................................................................ 28
10.03 Delays .......................................................................................................................................... 28
Article 11 Tests and Inspections; Correction, Removal or Acceptance of Defective Work ...................... 29
11.01 Notice of Defects ........................................................................................................................ 29
11.02 Access to Work ........................................................................................................................... 29
11.03 Tests and Inspections .................................................................................................................. 29
11.04 Uncovering Work ....................................................................................................................... 30
11.05 City May Stop the Work ............................................................................................................. 30
11.06 Correction or Removal of Defective Work ................................................................................ 30
11.07 Correction Period ........................................................................................................................ 30
11.08 City May Correct Defective Work ............................................................................................. 31
Article 12 Completion .................................................................................................................................. 32
12.01 Contract Warranty of Title ................................................................................................... 32
12.02 Partial Utilization ........................................................................................................................ 32
12.03 Final Inspection ........................................................................................................................... 32
12.04 Final Acceptance ......................................................................................................................... 33
Article 13 Suspension of Work .................................................................................................................... 33
13.01 City May Suspend Work ............................................................................................................ 33
Article 14 Miscellaneous .............................................................................................................................. 34
14.01 Giving Notice .............................................................................................................................. 34
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CITY CONDITIONS DEVELOPER AWARDED PROJECTS City Project No. 103761
14.02 Computation of Times ................................................................................................................ 34
14.03 Cumulative Remedies ................................................................................................................. 34
14.04 Survival of Obligations ............................................................................................................... 35
14.05 Headings ...................................................................................................................................... 35
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CITY CONDITIONS DEVELOPER AWARDED PROJECTS City Project No. 103761
00 73 10- 1
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 1 of 35
ARTICLE 1 DEFINITIONS AND TERMINOLOGY
1.01 Defined Terms
A. Wherever used in these General Conditions or in other Contract Documents, the terms listed
below have the meanings indicated which are applicable to both the singular and plural thereof,
and words denoting gender shall include the masculine, feminine and neuter. Said terms are
generally capitalized or written in italics, but not always. When used in a context consistent with
the definition of a listed-defined term, the term shall have a meaning as defined below whether
capitalized or italicized or otherwise. In addition to terms specifically defined, terms with initial
capital letters in the Contract Documents include references to identified articles and paragraphs,
and the titles of other documents or forms.
1.Agreement -The written instrument which is evidence of the agreement between Developer
and Contractor covering the Work
2.Asbestos Any material that contains more than one percent asbestos and is friable or is
releasing asbestos fibers into the air above current action levels established by the United
States Occupational Safety and Health Administration.
3.Business Day A business day is defined as a day that the City conducts normal business,
generally Monday through Friday, except for federal or state holidays observed by the City.
4.Buzzsaw on-line, electronic document management and collaboration system.
5.Calendar Day A day consisting of 24 hours measured from midnight to the next midnight.
6.City The City of Fort Worth, Texas, a Texas home-rule municipal corporation, acting by,
its governing body through its City Manager, his designee, or agents authorized pursuant to
its duly authorized charter on his behalf.
7.Community Facilities Agreement (CFA) -A Contract between the Developer and the City
for the Construction of one or more following public facilities within the City public right-of-
way or easement: Water, Sanitary Sewer, Street, Storm Drain, Street Light, and Street Signs.
A CFA may include private facilities within the right-of-way dedicated as private right-of-
way or easement on a recorded plat.
8.Contract The entire and integrated written document incorporating the Contract
Documents between the Developer,Contractor,and/or City concerning the Work.The
Contract supersedes prior negotiations, representations, or agreements, whether written or
oral.
9.Contract Documents Those items that make up the contract and which must include the
Agreement, and attachments such as standard construction specifications, standard City
Conditions, other general conditions of the Developer, including:
a. An Agreement
00 73 10- 2
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 2 of 35
b. Attachments to the Agreement
i.Bid Form
ii.Vendor Compliance with State Law Non-Resident Bidder
iii.Prequalification Statement
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CITY CONDITIONS DEVELOPER AWARDED PROJECTS City Project No. 103761
c. Current Prevailing Wage Rates Table (if required by City)
d.Insurance Accord Form
e.Payment Bond
f.Performance Bond
g. Maintenance Bond
h.Power of Attorney for Bonds
i. Workers Compensation Affidavit
j. MWBE Commitment Form( If required by City)
k. General Conditions
l.Supplementary Conditions
m. The Standard City Conditions
n.Specifications specifically made part of the Contract Documents by attachment, if
not attached, as incorporated by reference and described in the Table of Contents of
ments
o. Drawings
p. Documentation submitted by contractor prior to Notice of Award.
q. The following which may be delivered or issued after the effective date if the
Agreement and, if issued become an incorporated part of the Contract Documents
i. Notice to Proceed
ii.Field Orders
iii. Change Orders
iv. Letters of Final Acceptance
r. Approved Submittals, other Contractor submittals, and the reports and drawings of
subsurface and physical conditions are not Contract Documents.
10.Contractor The individual or entity with whom Developer has entered into the Agreement.
11.Day or day A day, unless otherwise defined, shall mean a Calendar Day.
12.Developer An individual or entity that desires to make certain improvements within the
City of Fort Worth
13.Drawings That part of the Contract Documents prepared or approved by Engineer which
graphically shows the scope,extent,and character of the Work to be performed by
Contractor. Submittals are not Drawings as so defined.
14.Engineer The licensed professional engineer or engineering firm registered in the State of
Texas performing professional services for the Developer.
15.Final Acceptance The written notice given by the City to the Developer and/or Contractor
that the Work specified in the Contract Documents has been completed to the satisfaction of
the City.
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CITY CONDITIONS DEVELOPER AWARDED PROJECTS City Project No. 103761
00 73 10- 3
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 3 of 35
16.Final Inspection Inspection carried out by the City to verify that the Contractor has
completed the Work, and each and every part or appurtenance thereof, fully, entirely, and in
conformance with the Contract Documents.
17.General Requirements A part of the Contract Documents between the Developer and a
Contractor.
18.Laws and Regulations Any and all applicable laws, rules, regulations, ordinances, codes,
and orders of any and all governmental bodies, agencies, authorities, and courts having
jurisdiction.
19.Liens Charges, security interests, or encumbrances upon Project funds, real property, or
personal property.
20.Milestone A principal event specified in the Contract Documents relating to an
intermediate Contract Time prior to Final Acceptance of the Work.
21.Non-Participating Change Order A document, which is prepared for and reviewed by the
City, which is signed by Contractor, and Developer, and authorizes an addition, deletion, or
revision in the Work or an adjustment in the Contract Price or the Contract Time, issued on
or after the Effective Date of the Agreement.
22.Participating Change Order A document, which is prepared for and approved by the City,
which is signed by Contractor, Developer, and City and authorizes an addition, deletion, or
revision in the Work or an adjustment in the Contract Price or the Contract Time, issued on
or after the Effective Date of the Agreement.
23.Plans See definition of Drawings.
24.Project Schedule A schedule, prepared and maintained by Contractor, in accordance with
the General Requirements, describing the sequence and duration of the activities comprising
the plan to accomplish the Work within the Contract Time.
25.Project The Work to be performed under the Contract Documents.
26.Project Representative The authorized representative of the City who will be assigned to
the Site.
27.Public Meeting An announced meeting conducted by the Developer to facilitate public
participation and to assist the public in gaining an informed view of the Project.
28.Regular Working Hours Hours beginning at 7:00 a.m. and ending at 6:00 p.m., Monday
thru Friday (excluding legal holidays).
29.Samples Physical examples of materials,equipment,or workmanship that are
representative of some portion of the Work and which establish the standards by which such
portion of the Work will be judged.
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CITY CONDITIONS DEVELOPER AWARDED PROJECTS City Project No. 103761
00 73 10- 4
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 4 of 35
30.Schedule of Submittals A schedule, prepared and maintained by Contractor, of required
submittals and the time requirements to support scheduled performance of related
construction activities.
31.Site Lands or areas indicated in the Contract Documents as being furnished by City or
Developer upon which the Work is to be performed, including rights-of-way, permits, and
easements for access thereto, and such other lands furnished by City or Developer which are
designated for the use of Contractor.
32.Specifications That part of the Contract Documents consisting of written requirements for
materials, equipment, systems, standards and workmanship as applied to the Work, and
certain administrative requirements and procedural matters applicable thereto.
Specifications may be specifically made a part of the Contract Documents by attachment or,
if not attached, may be incorporated by reference as indicated in the Table of Contents
(Division 00 00 00) of each Project.
33.Standard City Conditions That part of the Contract Documents setting forth requirements
of the City.
34.Subcontractor An individual or entity having a direct contract with Contractor or with any
other Subcontractor for the performance of a part of the Work at the Site.
35.Submittals All drawings, diagrams, illustrations, schedules, and other data or information
which are specifically prepared or assembled by or for Contractor and submitted by
Contractor to illustrate some portion of the Work.
36.Superintendent The representative of the Contractor who is available at all times and able
to receive instructions from the City and/or Developer and to act for the Contractor.
37.Supplementary Conditions That part of the Contract Documents which amends or
supplements the General Conditions.
38.Supplier A manufacturer, fabricator, supplier, distributor, materialman, or vendor having
a direct contract with Contractor or with any Subcontractor to furnish materials or
equipment to be incorporated in the Work by Contractor or Subcontractor.
39.Underground Facilities All underground pipelines,conduits,ducts,cables,wires,
manholes,vaults,tanks,tunnels,or other such facilities or attachments,and any
encasements containing such facilities,including but not limited to,those that convey
electricity, gases, steam, liquid petroleum products, telephone or other communications,
cable television, water, wastewater, storm water, other liquids or chemicals, or traffic or
other control systems.
40.Weekend Working Hours Hours beginning at 9:00 a.m. and ending at 5:00 p.m., Saturday,
Sunday or legal holiday, as approved in advance by the City.
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CITY CONDITIONS DEVELOPER AWARDED PROJECTS City Project No. 103761
00 73 10- 5
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 5 of 35
41.Work The entire construction or the various separately identifiable parts thereof required
to be provided under the Contract Documents. Work includes and is the result of performing
or providing all labor, services, and documentation necessary to produce such construction
including any Participating Change Order,Non-Participating Change Order,or Field
Order, and furnishing, installing, and incorporating all materials and equipment into such
construction, all as required by the Contract Documents.
42.Working Day A working day is defined as a day, not including Saturdays, Sundays, or
legal holidays authorized by the City for contract purposes, in which weather or other
conditions not under the control of the Contractor will permit the performance of the
principal unit of work underway for a continuous period of not less than 7 hours between 7
a.m. and 6 p.m.
1.02 Terminology
A. The words and terms discussed in Paragraph 1.02.B through D are not defined but, when used in
the Bidding Requirements or Contract Documents, have the indicated meaning.
B.Defective:
1. The word when modifying the word refers to Work that is
unsatisfactory, faulty, or deficient in that it:
a. does not conform to the Contract Documents; or
b. does not meet the requirements of any applicable inspection, reference standard, test, or
approval referred to in the Contract Documents; or
c. has been damaged prior to written acceptance.
C.Furnish, Install, Perform, Provide:
1. The word Furnis or the word I or the word rform or the word or
the word or any combination or similar directive or usage thereof, shall mean
furnishing and incorporating in the Work including all necessary labor, materials, equipment,
and everything necessary to perform the Work indicated, unless specifically limited in the
context used.
D. Unless stated otherwise in the Contract Documents, words or phrases that have a well-known
technical or construction industry or trade meaning are used in the Contract Documents in
accordance with such recognized meaning.
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CITY CONDITIONS DEVELOPER AWARDED PROJECTS City Project No. 103761
00 73 10- 6
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 6 of 35
ARTICLE 2 PRELIMINARY MATTERS
2.01 Before Starting Construction
Baseline Schedules:Submit to City in accordance with the Contract Documents, and prior to starting
the Work. New schedules will be submitted to City when Participating Change Orders or Non-
Participating Change Orders occur.
2.02 Preconstruction Conference
Before any Work at the Site is started, the Contractor shall attend a Preconstruction Conference as
specified in the Contract Documents.
2.03 Public Meeting
Contractor may not mobilize any equipment, materials or resources to the Site prior to Contractor
attending the Public Meeting as scheduled by the City.
ARTICLE 3 CONTRACT DOCUMENTS AND AMENDING
3.01 Reference Standards
A. Standards, Specifications, Codes, Laws, and Regulations
1. Reference to standards, specifications, manuals, or codes of any technical society,
organization, or association, or to Laws or Regulations, whether such reference be specific or
by implication, shall mean the standard, specification, manual, code, or Laws or Regulations
in effect at the time of opening of Bids (or on the Effective Date of the Agreement if there
were no Bids), except as may be otherwise specifically stated in the Contract Documents.
2. No provision or instruction shall be effective to assign to City, or any of its officers,
directors, members, partners, employees, agents, consultants, or subcontractors, any duty or
authority to supervise or direct the performance of the Work or any duty or authority to
undertake responsibility inconsistent with the provisions of the Contract Documents.
3.02 Amending and Supplementing Contract Documents
A. The Contract Documents may be amended to provide for additions, deletions, and revisions in
the Work or to modify the terms and conditions thereof by a Participating Change Order or a
Non-Participating Change Order.
B. The requirements of the Contract Documents may be supplemented, and minor variations and
deviations in the Work not involving a change in Contract Price or Contract Time, may be
authorized, by one or more of the following ways:
1. A Field Order;
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CITY CONDITIONS DEVELOPER AWARDED PROJECTS City Project No. 103761
00 73 10- 7
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 7 of 35
1. or review of a Submittal (subject to the provisions of Paragraph 5.16.C); or
2. written interpretation or clarification.
ARTICLE 4 BONDS AND INSURANCE
4.01 Licensed Sureties and Insurers
All bonds and insurance required by the Contract Documents to be purchased and maintained by
Contractor shall be obtained from surety or insurance companies that are duly licensed or authorized
in the State of Texas to issue bonds or insurance policies for the limits and coverage so required.
Such surety and insurance companies shall also meet such additional requirements and qualifications
as may be provided Section 4.04.
4.02 Performance, Payment, and Maintenance Bonds
A. Contractor shall furnish performance and payment bonds in the name of Developer and City, in
accordance with Texas Government Code Chapter 2253 or successor statute, each in an amount
equal to the Contract Price as security for the faithful performance and payment of all of
Contract s obligations under the Contract Documents.
B. Contractor shall furnish maintenance bonds in the name of Developer and City in an amount
equal to the Contract Price as security to protect the City against any defects in any portion of the
Work described in the Contract Documents. Maintenance bonds shall remain in effect for two
(2) years after the date of Final Acceptance by the City.
C. All bonds shall be in the form prescribed by the Contract Documents except as provided
otherwise by Laws or Regulations, and shall be executed by such sureties as are named in the list
of Holding Certificates of Authority as Acceptable Sureties on Federal Bonds and
as Acceptable Reinsuring Companies as published in Circular 570 (amended) by the Financial
Management Service, Surety Bond Branch, U.S. Department of the Treasury. All bonds signed
by an agent or attorney-in-fact must be accompanied by a sealed and dated power of attorney
which shall show that it is effective on the date the agent or attorney-in-fact signed each bond.
D. If the surety on any bond furnished by Contractor is declared bankrupt or becomes insolvent or
its right to do business is terminated in the State of Texas or it ceases to meet the requirements of
Paragraph 4.02.C, Contractor shall promptly notify City and shall, within 30 days after the event
giving rise to such notification, provide another bond and surety, both of which shall comply
with the requirements of Paragraphs 4.01 and 4.02.C.
4.03 Certificates of Insurance
Contractor shall deliver to Developer and City, with copies to each additional insured and loss payee
identified in these Standard City Conditions certificates of insurance (and other evidence of
insurance requested by City or any other additional insured) which Contractor is required to
purchase and maintain.
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CITY CONDITIONS DEVELOPER AWARDED PROJECTS City Project No. 103761
00 73 10- 8
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 8 of 35
1. The certificate of insurance shall document the City, an as nal on all
liability policies.
2. The general liability insurance shall include a,
endorsement, which shall be identified in the certificate of insurance provided to the City.
3. The certificate shall be signed by an agent authorized to bind coverage on behalf of the
insured, be complete in its entirety, and show complete insurance carrier names as listed in
the current A.M. Best Property & Casualty Guide
4. The insurers for all policies must be licensed and/or approved to do business in the State of
Texas. Except for compensation, all insurers must have a minimum rating of A-:
VII in the current A. M. Best Key Rating Guide or have reasonably equivalent financial
strength and solvency to the satisfaction of Risk Management. If the rating is below that
required, written approval of City is required.
5. All applicable policies shall include a Waiver of Subrogation (Rights of Recovery) in favor
of the City. In addition, the Contractor agrees to waive all rights of subrogation against the
Engineer (if applicable), and each additional insured identified in these Standard City
Conditions. Failure of the City to demand such certificates or other evidence of full
compliance with the insurance requirements or failure of the City to identify a deficiency
from evidence that is provided shall not be construed as a waiver of Cont obligation
to maintain such lines of insurance coverage.
6. If insurance policies are not written for specified coverage limits, an Umbrella or Excess
Liability insurance for any differences is required. Excess Liability shall follow form of the
primary coverage.
7. Unless otherwise stated, all required insurance shall be written on the currence If
coverage is underwritten on a claims-made basis, the retroactive date shall be coincident with
or prior to the date of the effective date of the agreement and the certificate of insurance shall
state that the coverage is claims-made and the retroactive date. The insurance coverage shall
be maintained for the duration of the Contract and for three (3) years following Final
Acceptance provided under the Contract Documents or for the warranty period, whichever is
longer. An annual certificate of insurance submitted to the City shall evidence such
insurance coverage.
8. Policies shall have no exclusions by endorsements, which, neither nullify or amend, the
required lines of coverage, nor decrease the limits of said coverage unless such endorsements
are approved in writing by the City. In the event a Contract has been bid or executed and the
exclusions are determined to be unacceptable or the City desires additional insurance
coverage, and the City desires the contractor/engineer to obtain such coverage, the contract
price shall be adjusted by the cost of the premium for such additional coverage plus 10%.
9. Any self-insured retention (SIR), in excess of $25,000.00, affecting required insurance
coverage shall be approved by the City in regards to asset value and stockholders' equity. In
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CITY CONDITIONS DEVELOPER AWARDED PROJECTS City Project No. 103761
00 73 10- 9
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 9 of 35
lieu of traditional insurance, alternative coverage maintained through insurance pools or risk
retention groups, must also be approved by City.
10.Any deductible in excess of $5,000.00, for any policy that does not provide coverage on a
first-dollar basis, must be acceptable to and approved by the City.
11.City, at its sole discretion, reserves the right to review the insurance requirements and to
make reasonable adjustments to insurance and their limits when deemed
necessary and prudent by the City based upon changes in statutory law, court decision or the
claims history of the industry as well as of the contracting party to the City. The City shall
be required to provide prior notice of 90 days, and the insurance adjustments shall be
incorporated into the Work by Change Order.
12.City shall be entitled, upon written request and without expense, to receive copies of policies
and endorsements thereto and may make any reasonable requests for deletion or revision or
modifications of particular policy terms, conditions, limitations, or exclusions necessary to
conform the policy and endorsements to the requirements of the Contract. Deletions,
revisions, or modifications shall not be required where policy provisions are established by
law or regulations binding upon either party or the underwriter on any such policies.
13.City shall not be responsible for the direct payment of insurance premium costs for
Contract s insurance.
4.04 Contr s Insurance
A.Workers Compensation and Employ Liability.Contractor shall purchase and maintain such
insurance coverage with limits consistent with statutory benefits outlined in the Texas Wo
Compensation Act (Texas Labor Code, Ch. 406, as amended), and minimum limits for
Liability as is appropriate for the Work being performed and as will provide
protection from claims set forth below which may arise out of or result from
performance of the Work and Contr other obligations under the Contract Documents,
whether it is to be performed by Contractor, any Subcontractor or Supplier, or by anyone directly
or indirectly employed by any of them to perform any of the Work, or by anyone for whose acts
any of them may be liable:
1. claims ation, disability benefits, and other similar employee benefit
acts;
2. claims for damages because of bodily injury, occupational sickness or disease, or death of
Contract s employees.
3. The limits of liability for the insurance shall provide the following coverages for not less
than the following amounts or greater where required by Laws and Regulations
a. Statutory limits
b. Employer's liability
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CITY CONDITIONS DEVELOPER AWARDED PROJECTS City Project No. 103761
00 73 10- 10
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 10 of 35
1) $100,000 each accident/occurrence
2) $100,000 Disease - each employee
3) $500,000 Disease - policy limit
B. Commercial General Liability. Coverage shall include but not be limited to covering liability
(bodily injury or property damage) arising from: premises/operations, independent contractors,
products/completed operations, personal injury, and liability under an insured contract. Insurance
shall be provided on an occurrence basis, and as comprehensive as the current Insurance
Services Office (ISO) policy. This insurance shall apply as primary insurance with respect to
any other insurance or self-insurance programs afforded to the City. The Commercial General
Liability policy, shall have no exclusions by endorsements that would alter of nullify
premises/operations, products/completed operations, contractual, personal injury, or advertising
injury, which are normally contained with the policy, unless the City approves such exclusions
in writing.
1. For construction projects that present a substantial completed operation exposure, the City
may require the contractor to maintain completed operations coverage for a minimum of no
less than three (3) years following the completion of the project
2. Contractor's Liability Insurance under this Section which shall be on a per project basis
covering the Contractor with minimum limits of:
a. $1,000,000 each occurrence
b. $2,000,000 aggregate limit
3. The policy must have an endorsement (Amendment Aggregate Limits of Insurance)
making the General Aggregate Limits apply separately to each job site.
4. The Commercial General Liability Insurance policies shall provide and
s. Verification of such coverage must be shown in the Remarks Article of the
Certificate of Insurance.
C.Automobile Liability.A commercial business auto policy shall provide coverage on any aut
defined as autos owned, hired and non-owned and provide indemnity for claims for damages
because bodily injury or death of any person and or property damage arising out of the work,
maintenance or use of any motor vehicle by the Contractor, any Subcontractor or Supplier, or by
anyone directly or indirectly employed by any of them to perform any of the Work, or by anyone
for whose acts any of them may be liable.
1. Automobile Liability, Liability Insurance under this Section, which shall be in
an amount not less than the following amounts:
a.Automobile Liability - a commercial business policy shall provide coverage on "Any
Auto", defined as autos owned, hired and non-owned.
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CITY CONDITIONS DEVELOPER AWARDED PROJECTS City Project No. 103761
00 73 10- 11
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 11 of 35
1)$1,000,000 each accident on a combined single limit basis. Split limits are
acceptable if limits are at least:
2) $250,000 Bodily Injury per person
3) $500,000 Bodily Injury per accident /
4) $100,000 Property Damage
D.Railroad Protective Liability.If any of the work or any warranty work is within the limits of
railroad right-of-way, the Contractor shall comply with the following requirements:
1. The Contrac s construction activities will require its employees, agents, subcontractors,
equipment, and material deliveries to cross railroad properties and tracks owned and
operated by: _____none______________________________________________________
Write the name of the railroad company. (If none, then write none)
2. The Contractor shall conduct its operations on railroad properties in such a manner as not to
interfere with, hinder, or obstruct the railroad company in any manner whatsoever in the use
or operation of its/their trains or other property. Such operations on railroad properties may
require that Contractor to execute a of Entry Agreement ith the particular railroad
company or companies involved, and to this end the Contractor should satisfy itself as to the
requirements of each railroad company and be prepared to execute the right-of-entry (if any)
required by a railroad company. The requirements specified herein likewise relate to the
Contractor s use of private and/or construction access roads crossing said railroad compan
properties.
3. The Contractual Liability coverage required by Paragraph 5.04D of the General Conditions
shall provide coverage for not less than the following amounts, issued by companies
satisfactory to the City and to the Railroad Company for a term that continues for so long as
the Contractor operations and work cross, occupy, or touch railroad property:
a. General Aggregate: __________none___________________________
Enter limits provided by Railroad Company (If none, write none)
b. Each Occurrence: : ____________none_________________________
Enter limits provided by Railroad Company (If none, write none)
4. With respect to the above outlined insurance requirements, the following shall govern:
a. Where a single railroad company is involved, the Contractor shall provide one insurance
policy in the name of the railroad company. However, if more than one grade separation
or at-grade crossing is affected by the Project at entirely separate locations on the line or
lines of the same railroad company, separate coverage may be required, each in the
amount stated above.
b. Where more than one railroad company is operating on the same right-of-way or where
several railroad companies are involved and operated on their own separate rights-of-
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CITY CONDITIONS DEVELOPER AWARDED PROJECTS City Project No. 103761
00 73 10- 12
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 12 of 35
way, the Contractor may be required to provide separate insurance policies in the name
of each railroad company.
c. If, in addition to a grade separation or an at-grade crossing, other work or activity is
proposed on a railroad right-of-way at a location entirely separate from the
grade separation or at-grade crossing, insurance coverage for this work must be included
in the policy covering the grade separation.
d. If no grade separation is involved but other work is proposed on a railroad company s
right-of-way, all such other work may be covered in a single policy for that railroad, even
though the work may be at two or more separate locations.
5. No work or activities on a railroad property to be performed by the Contractor
shall be commenced until the Contractor has furnished the City with an original policy or
policies of the insurance for each railroad company named, as required above. All such
insurance must be approved by the City and each affected Railroad Company prior to the
Contract s beginning work.
6. The insurance specified above must be carried until all Work to be performed on the railroad
right-of-way has been completed and the grade crossing, if any, is no longer used by the
Contractor. In addition, insurance must be carried during all maintenance and/or repair work
performed in the railroad right-of-way. Such insurance must name the railroad company as
the insured, together with any tenant or lessee of the railroad company operating over tracks
involved in the Project.
E.Notification of Policy Cancellation:Contractor shall immediately notify City upon cancellation
or other loss of insurance coverage. Contractor shall stop work until replacement insurance has
been procured. There shall be no time credit for days not worked pursuant to this section.
4.05 Acceptance of Bonds and Insurance; Option to Replace
If City has any objection to the coverage afforded by or other provisions of the bonds or insurance
required to be purchased and maintained by the Contractor in accordance with Article 5 on the basis
of non-conformance with the Contract Documents, the Developer and City shall so notify the
Contractor in writing within 10 Business Days after receipt of the certificates (or other evidence
requested). Contractor shall provide to the City such additional information in respect of insurance
provided as the Developer or City may reasonably request. If Contractor does not purchase or
maintain all of the bonds and insurance required by the Contract Documents, the Developer or City
shall notify the Contractor in writing of such failure prior to the start of the Work, or of such failure
to maintain prior to any change in the required coverage.
ARTICLE 5 CONTRACTO S RESPONSIBILITIES
5.01 Supervision and Superintendent
A. Contractor shall supervise, inspect, and direct the Work competently and efficiently, devoting
such attention thereto and applying such skills and expertise as may be necessary to perform the
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CITY CONDITIONS DEVELOPER AWARDED PROJECTS City Project No. 103761
00 73 10- 13
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 13 of 35
Work in accordance with the Contract Documents. Contractor shall be solely responsible for the
means, methods, techniques, sequences, and procedures of construction.
B. At all times during the progress of the Work, Contractor shall assign a competent, English-
speaking, Superintendent who shall not be replaced without written notice to City. The
Superintendent will be s representative at the Site and shall have authority to act on
behalf of Contractor. All communication given to or received from the Superintendent shall be
binding on Contractor.
C. Contractor shall notify the City 24 hours prior to moving areas during the sequence of
construction.
5.02 Labor; Working Hours
A. Contractor shall provide competent, suitably qualified personnel to perform construction as
required by the Contract Documents. Contractor shall at all times maintain good discipline and
order at the Site.
B. Except as otherwise required for the safety or protection of persons or the Work or property at
the Site or adjacent thereto, and except as otherwise stated in the Contract Documents, all Work
at the Site shall be performed during Regular Working Hours. Contractor will not permit the
performance of Work beyond Regular Working Hours or for Weekend Working Hours without
written consent (which will not be unreasonably withheld). Written request (by letter or
electronic communication) to perform Work:
1. for beyond Regular Working Hours request must be made by noon at least two (2) Business
Days prior
2. for Weekend Working Hours request must be made by noon of the preceding Thursday
3. for legal holidays request must be made by noon two Business Days prior to the legal
holiday.
5.03 Services, Materials, and Equipment
A. Unless otherwise specified in the Contract Documents, Contractor shall provide and assume full
responsibility for all services, materials, equipment, labor, transportation, construction
equipment and machinery, tools, appliances, fuel, power, light, heat, telephone, water, sanitary
facilities, temporary facilities, and all other facilities and incidentals necessary for the
performance, Contractor required testing, start-up, and completion of the Work.
B. All materials and equipment incorporated into the Work shall be as specified or, if not specified,
shall be of good quality and new, except as otherwise provided in the Contract Documents. All
special warranties and guarantees required by the Specifications shall expressly run to the benefit
of City. If required by City, Contractor shall furnish satisfactory evidence (including reports of
required tests) as to the source, kind, and quality of materials and equipment.
00 73 10- 14
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 14 of 35
C. All materials and equipment to be incorporated into the Work shall be stored, applied, installed,
connected, erected, protected, used, cleaned, and conditioned in accordance with instructions of
the applicable Supplier, except as otherwise may be provided in the Contract Documents.
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CITY CONDITIONS DEVELOPER AWARDED PROJECTS City Project No. 103761
5.04 Project Schedule
A. Contractor shall adhere to the Project Schedule established in accordance with Paragraph 2.01
and the General Requirements as it may be adjusted from time to time as provided below.
1. Contractor shall submit to City for acceptance (to the extent indicated in Paragraph 2.01 and
the General Requirements) proposed adjustments in the Project Schedule.
2. Proposed adjustments in the Project Schedule that will change the Contract Time shall be
submitted in accordance with the requirements of Article 9. Adjustments in Contract Time
for projects with City participation shall be made by participating change orders.
5.05 Substitutes and -
A. Whenever an item of material or equipment is specified or described in the Contract Documents
by using the name of a proprietary item or the name of a particular Supplier, the specification or
description is intended to establish the type, function, appearance, and quality required. Unless
the specification or description contains or is followed by words reading that no like, equivalent,
-m or no substitution is permitted, other items of material or equipment of other
Suppliers may be submitted to City for review under the circumstances described below.
1.- Items:etion an item of material or equipment proposed by
Contractor is functionally equal to that named and sufficiently similar so that no change in
related Work will be required, it may be consid -m, in which
case review and approval of the proposed item may, in s sole discretion, be
accomplished without compliance with some or all of the requirements for approval of
proposed substitute items. For the purposes of this Paragraph 5.05.A.1, a proposed item of
material or equipment will be considered functionally equal to an item so named if:
a. City determines that:
1) it is at least equal in materials of construction, quality, durability, appearance,
strength, and design characteristics;
2) it will reliably perform at least equally well the function and achieve the results
imposed by the design concept of the completed Project as a functioning whole; and
3) it has a proven record of performance and availability of responsive service; and
b. Contractor certifies that, if approved and incorporated into the Work:
1) there will be no increase in cost to the City or increase in Contract Time; and
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CITY CONDITIONS DEVELOPER AWARDED PROJECTS City Project No. 103761
00 73 10- 15
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 15 of 35
2) it will conform substantially to the detailed requirements of the item named in the
Contract Documents.
2.Substitute Items:
a. If in City s sole discretion an item of material or equipment proposed by Contractor does
not qualify as an - item under Paragraph 5.05.A.1, it may be submitted as a
proposed substitute item.
b. Contractor shall submit sufficient information as provided below to allow City to
determine if the item of material or equipment proposed is essentially equivalent to that
named and an acceptable substitute therefor. Requests for review of proposed substitute
items of material or equipment will not be accepted by City from anyone other than
Contractor.
c. Contractor shall make written application to City for review of a proposed substitute item
of material or equipment that Contractor seeks to furnish or use. The application shall
comply with Section 01 25 00 and:
1) shall certify that the proposed substitute item will:
i. perform adequately the functions and achieve the results called for by the general
design;
ii. be similar in substance to that specified;
iii.be suited to the same use as that specified; and
2) will state:
i. the extent, if any, to which the use of the proposed substitute item will prejudice
Contract s achievement of final completion on time;
ii. whether use of the proposed substitute item in the Work will require a change in
any of the Contract Documents (or in the provisions of any other direct contract
with City for other work on the Project) to adapt the design to the proposed
substitute item;
iii.whether incorporation or use of the proposed substitute item in connection with
the Work is subject to payment of any license fee or royalty; and
3) will identify:
i. all variations of the proposed substitute item from that specified;
ii. available engineering, sales, maintenance, repair, and replacement services; and
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CITY CONDITIONS DEVELOPER AWARDED PROJECTS City Project No. 103761
00 73 10- 16
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 16 of 35
4) shall contain an itemized estimate of all costs or credits that will result directly or
indirectly from use of such substitute item, including costs of redesign and Damage
Claims of other contractors affected by any resulting change.
B.Substitute Construction Methods or Procedures: If a specific means, method, technique,
sequence, or procedure of construction is expressly required by the Contract Documents,
Contractor may furnish or utilize a substitute means, method, technique, sequence, or procedure
of construction approved by City. Contractor shall submit sufficient information to allow City, in
sole discretion, to determine that the substitute proposed is equivalent to that expressly
called for by the Contract Documents. Contractor shall make written application to City for
review in the same manner as those provided in Paragraph 5.05.A.2.
C. Evaluation:City will be allowed a reasonable time within which to evaluate each
proposal or submittal made pursuant to Paragraphs 5.05.A and 5.05.B. City may require
Contractor to furnish additional data about the proposed substitute. City will be the sole judge of
acceptability. No - or substi
is complete, which will be evidenced by a Change Order in the case of a substitute and an
accepted Subm - City will advise Contractor in writing of its determination.
D.Special Guarantee:City may require Contractor to furnish at Contract expense a special
performance guarantee, warranty, or other surety with respect to any substitute.Contractor shall
indemnify and hold harmless City and anyone directly or indirectly employed by them from and
against any and all claims, damages, losses and expenses (including attorneys fees) arising out
of the use of substituted materials or equipment.
E. Cost Reimbursement: City will record Cit costs in evaluating a substitute proposed or
submitted by Contractor pursuant to Paragraphs 5.05.A.2 and 5.05.B. Whether or not City
approves a substitute so proposed or submitted by Contractor, Contractor may be required to
reimburse City for evaluating each such proposed substitute. Contractor may also be required to
reimburse City for the charges for making changes in the Contract Documents.
F.Contr s Expense: Contractor shall provide all data in support of any proposed substitute or
- at Contractor s expense.
G.Substitute Reimbursement: Costs (savings or charges) attributable to acceptance of a substitute
shall be incorporated to the Contract by Participating Change Order.
5.06 Pre-Qualification of Bidders (Prime Contractors and Subcontractors)
A. The Contractor and any subcontractors are required to be prequalified for the work types
requiring pre-qualification
5.07 Concerning Subcontractors, Suppliers, and Others
A.Minority and Women Owned Business Enterprise Compliance:
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CITY CONDITIONS DEVELOPER AWARDED PROJECTS City Project No. 103761
00 73 10- 17
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 17 of 35
Required for this Contract.
(Check this box if there is any City Participation)
Not Required for this Contract.
It is City policy to ensure the full and equitable participation by Minority and Women Business
Enterprises (MWBE) in the procurement of goods and services on a contractual basis. If the
Contract Documents provide for a MWBE goal, Contractor is required to comply with the intent
of the s MWBE Ordinance (as amended) by the following:
1. Contractor shall, upon request by City, provide complete and accurate information regarding
actual work performed by a MWBE on the Contract and payment therefor.
2. Contractor will not make additions, deletions, or substitutions of accepted MWBE without
written consent of the City. Any unjustified change or deletion shall be a material breach of
Contract and may result in debarment in accordance with the procedures outlined in the
Ordinance.
3. Contractor shall, upon request by City, allow an audit and/or examination of any books,
records, or files in the possession of the Contractor that will substantiate the actual work
performed by an MWBE. Material misrepresentation of any nature will be grounds for
termination of the Contract. Any such misrepresentation may be grounds for disqualification
of Contractor to bid on future contracts with the City for a period of not less than three years.
B. Contractor shall be fully responsible to City for all acts and omissions of the Subcontractors,
Suppliers, and other individuals or entities performing or furnishing any of the Work just as
Contractor is responsible for own acts and omissions. Nothing in the Contract
Documents:
1. shall create for the benefit of any such Subcontractor, Supplier, or other individual or entity
any contractual relationship between City and any such Subcontractor, Supplier or other
individual or entity; nor
2. shall create any obligation on the part of City to pay or to see to the payment of any moneys
due any such Subcontractor, Supplier, or other individual or entity except as may otherwise
be required by Laws and Regulations.
C. Contractor shall be solely responsible for scheduling and coordinating the Work of
Subcontractors, Suppliers, and other individuals or entities performing or furnishing any of the
Work under a direct or indirect contract with Contractor.
D. All Subcontractors, Suppliers, and such other individuals or entities performing or furnishing
any of the Work shall communicate with City through Contractor.
E. All Work performed for Contractor by a Subcontractor or Supplier will be pursuant to an
appropriate agreement between Contractor and the Subcontractor or Supplier which specifically
binds the Subcontractor or Supplier to the applicable terms and conditions of these Contract
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CITY CONDITIONS DEVELOPER AWARDED PROJECTS City Project No. 103761
00 73 10- 18
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 18 of 35
Documents, Contractor shall provide City contract numbers and reference numbers to the
Subcontractors and/or Suppliers.
5.08 Wage Rates
Required for this Contract.
Not Required for this Contract.
A.Duty to pay Prevailing Wage Rates. The Contractor shall comply with all requirements of
Chapter 2258, Texas Government Code (as amended), including the payment of not less than the
rates determined by the City Council of the City of Fort Worth to be the prevailing wage rates in
accordance with Chapter 2258. Such prevailing wage rates are included in these Contract
Documents.
B.Penalty for Violation. A Contractor or any Subcontractor who does not pay the prevailing wage
shall, upon demand made by the City, pay to the City $60 for each worker employed for each
calendar day or part of the day that the worker is paid less than the prevailing wage rates
stipulated in these contract documents. This penalty shall be retained by the City to offset its
administrative costs, pursuant to Texas Government Code 2258.023.
C.Complaints of Violations and City Determination of Good Cause. On receipt of information,
including a complaint by a worker, concerning an alleged violation of 2258.023, Texas
Government Code, by a Contractor or Subcontractor, the City shall make an initial
determination, before the 31st day after the date the City receives the information, as to whether
good cause exists to believe that the violation occurred. The City shall notify in writing the
Contractor or Subcontractor and any affected worker of its initial determination. Upon the
determination that there is good cause to believe the Contractor or Subcontractor has
violated Chapter 2258, the City shall retain the full amounts claimed by the claimant or
claimants as the difference between wages paid and wages due under the prevailing wage rates,
such amounts being subtracted from successive progress payments pending a final determination
of the violation.
D.Arbitration Required if Violation Not Resolved. An issue relating to an alleged violation of
Section 2258.023, Texas Government Code, including a penalty owed to the City or an affected
worker, shall be submitted to binding arbitration in accordance with the Texas General
Arbitration Act (Article 224 et seq., Revised Statutes) if the Contractor or Subcontractor and any
affected worker does not resolve the issue by agreement before the 15th day after the date the
City makes its initial determination pursuant to Paragraph C above. If the persons required to
arbitrate under this section do not agree on an arbitrator before the 11th day after the date that
arbitration is required, a district court shall appoint an arbitrator on the petition of any of the
persons. The City is not a party in the arbitration. The decision and award of the arbitrator is
final and binding on all parties and may be enforced in any court of competent jurisdiction.
E.Records to be Maintained. The Contractor and each Subcontractor shall, for a period of three (3)
years following the date of acceptance of the work, maintain records that show (i) the name and
x
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CITY CONDITIONS DEVELOPER AWARDED PROJECTS City Project No. 103761
00 73 10- 19
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 19 of 35
occupation of each worker employed by the Contractor in the construction of the Work provided
for in this Contract; and (ii) the actual per diem wages paid to each worker. The records shall be
open at all reasonable hours for inspection by the City. The provisions of Paragraph 6.23, Right
to Audit, shall pertain to this inspection.
F.Progress Payments. With each progress payment or payroll period, whichever is less, the
Contractor shall submit an affidavit stating that the Contractor has complied with the
requirements of Chapter 2258, Texas Government Code.
G.Posting of Wage Rates. The Contractor shall post prevailing wage rates in a conspicuous place at
all times.
H.Subcontractor Compliance. The Contractor shall include in its subcontracts and/or shall
otherwise require all of its Subcontractors to comply with Paragraphs A through G above.
5.09 Patent Fees and Royalties
A.To the fullest extent permitted by Laws and Regulations, Contractor shall indemnify and hold
harmless City, from and against all claims, costs, losses, and damages (including but not limited
to all fees and charges of engineers, architects, attorneys, and other professionals and all court
or arbitration or other dispute resolution costs) arising out of or relating to any infringement of
patent rights or copyrights incident to the use in the performance of the Work or resulting from
the incorporation in the Work of any invention, design, process, product, or device not specified
in the Contract Documents.
5.10 Laws and Regulations
A. Contractor shall give all notices required by and shall comply with all Laws and Regulations
applicable to the performance of the Work. Except where otherwise expressly required by
applicable Laws and Regulations, the City shall not be responsible for monitoring Contractor
compliance with any Laws or Regulations.
B. If Contractor performs any Work knowing or having reason to know that it is contrary to Laws
or Regulations, Contractor shall bear all claims, costs, losses, and damages (including but not
limited to all fees and charges of engineers, architects, attorneys, and other professionals and all
court or arbitration or other dispute resolution costs) arising out of or relating to such Work.
However, it shall not be Contract s responsibility to make certain that the Specifications and
Drawings are in accordance with Laws and Regulations, but this shall not relieve Contractor of
Contract s obligations under Paragraph 3.01.
5.11 Use of Site and Other Areas
A.Limitation on Use of Site and Other Areas:
1. Contractor shall confine construction equipment, the storage of materials and equipment, and
the operations of workers to the Site and other areas permitted by Laws and Regulations, and
shall not unreasonably encumber the Site and other areas with construction equipment or
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CITY CONDITIONS DEVELOPER AWARDED PROJECTS City Project No. 103761
00 73 10- 20
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 20 of 35
other materials or equipment. Contractor shall assume full responsibility for any damage to
any such land or area, or to the owner or occupant thereof, or of any adjacent land or areas
resulting from the performance of the Work.
2. At any time when, in the judgment of the City, the Contractor has obstructed or closed or is
carrying on operations in a portion of a street, right-of-way, or easement greater than is
necessary for proper execution of the Work, the City may require the Contractor to finish the
section on which operations are in progress before work is commenced on any additional
area of the Site.
3. Should any Damage Claim be made by any such owner or occupant because of the
performance of the Work, Contractor shall promptly attempt to resolve the Damage Claim.
4.Pursuant to Paragraph 5.18, Contractor shall indemnify and hold harmless City, from and
against all claims, costs, losses, and damages arising out of or relating to any claim or
action, legal or equitable, brought by any such owner or occupant against City.
B.Removal of Debris During Performance of the Work: During the progress of the Work
Contractor shall keep the Site and other areas free from accumulations of waste materials,
rubbish, and other debris. Removal and disposal of such waste materials, rubbish, and other
debris shall conform to applicable Laws and Regulations.
C.Site Maintenance Cleaning: 24 hours after written notice is given to the Contractor that the
clean-up on the job site is proceeding in a manner unsatisfactory to the City or Developer, if the
Contractor fails to correct the unsatisfactory procedure, the City may take such direct action as
the City deems appropriate to correct the clean-up deficiencies cited to the Contractor in the
written notice (by letter or electronic communication), and shall be entitled to recover its cost in
doing so. The City may withhold Final Acceptance until clean-up is complete and cost are
recovered.
D.Final Site Cleaning:Prior to Final Acceptance of the Work Contractor shall clean the Site and
the Work and make it ready for utilization by City or adjacent property owner. At the completion
of the Work Contractor shall remove from the Site all tools, appliances, construction equipment
and machinery, and surplus materials and shall restore to original condition or better all property
disturbed by the Work.
E.Loading Structures:Contractor shall not load nor permit any part of any structure to be loaded
in any manner that will endanger the structure, nor shall Contractor subject any part of the Work
or adjacent property to stresses or pressures that will endanger it.
5.12 Record Documents
A. Contractor shall maintain in a safe place at the Site or in a place designated by the Contractor
and approved by the City, one (1) record copy of all Drawings, Specifications, Addenda, Change
Orders, Field Orders, and written interpretations and clarifications in good order and annotated
to show changes made during construction. These record documents together with all approved
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CITY CONDITIONS DEVELOPER AWARDED PROJECTS City Project No. 103761
00 73 10- 21
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 21 of 35
Samples and a counterpart of all accepted Submittals will be available to City for reference.
Upon completion of the Work, these record documents, any operation and maintenance manuals,
and Submittals will be delivered to City prior to Final Inspection. Contractor shall include
accurate locations for buried and imbedded items.
5.13 Safety and Protection
A. Contractor shall be solely responsible for initiating, maintaining and supervising all safety
precautions and programs in connection with the Work. Such responsibility does not relieve
Subcontractors of their responsibility for the safety of persons or property in the performance of
their work, nor for compliance with applicable safety Laws and Regulations. Contractor shall
take all necessary precautions for the safety of, and shall provide the necessary protection to
prevent damage, injury or loss to:
1. all persons on the Site or who may be affected by the Work;
2. all the Work and materials and equipment to be incorporated therein, whether in storage on
or off the Site; and
3. other property at the Site or adjacent thereto, including trees, shrubs, lawns, walks,
pavements, roadways, structures, utilities, and Underground Facilities not designated for
removal, relocation, or replacement in the course of construction.
B. Contractor shall comply with all applicable Laws and Regulations relating to the safety of
persons or property, or to the protection of persons or property from damage, injury, or loss; and
shall erect and maintain all necessary safeguards for such safety and protection. Contractor shall
notify owners of adjacent property and of Underground Facilities and other utility owners when
prosecution of the Work may affect them, and shall cooperate with them in the protection,
removal, relocation, and replacement of their property.
C. Contractor shall comply with the applicable requirements of City safety programs, if any.
D. Contractor shall inform City of the specific requirements of Contract s safety program, if any,
with which employees and representatives must comply while at the Site.
E. All damage, injury, or loss to any property referred to in Paragraph 5.13.A.2 or 5.13.A.3 caused,
directly or indirectly, in whole or in part, by Contractor, any Subcontractor, Supplier, or any
other individual or entity directly or indirectly employed by any of them to perform any of the
Work, or anyone for whose acts any of them may be liable, shall be remedied by Contractor.
F. Contract duties and responsibilities for safety and for protection of the Work shall continue
until such time as all the Work is completed and City has accepted the Work.
5.14 Safety Representative
Contractor shall inform City in writing of Contract designated safety representative at the Site.
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CITY CONDITIONS DEVELOPER AWARDED PROJECTS City Project No. 103761
00 73 10- 22
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 22 of 35
5.15 Hazard Communication Programs
Contractor shall be responsible for coordinating any exchange of material safety data sheets or other
hazard communication information required to be made available to or exchanged between or
among employers in accordance with Laws or Regulations.
5.16 Submittals
A. Contractor shall submit required Submittals to City for review and acceptance. Each submittal
will be identified as required by City.
1. Submit number of copies specified in the General Requirements.
2. Data shown on the Submittals will be complete with respect to quantities, dimensions,
specified performance and design criteria, materials, and similar data to show City the
services, materials, and equipment Contractor proposes to provide and to enable City to
review the information for the limited purposes required by Paragraph 5.16.C.
3. Submittals submitted as herein provided by Contractor and reviewed by City for
conformance with the design concept shall be executed in conformity with the Contract
Documents unless otherwise required by City.
4. When Submittals are submitted for the purpose of showing the installation in greater detail,
their review shall not excuse Contractor from requirements shown on the Drawings and
Specifications.
5. For-Information-Only submittals upon which the City is not expected to conduct review or
take responsive action may be so identified in the Contract Documents.
6. Submit required number of Samples specified in the Specifications.
7. Clearly identify each Sample as to material, Supplier, pertinent data such as catalog numbers,
the use for which intended and other data as City may require to enable City to review the
submittal for the limited purposes required by Paragraph 5.16.C.
B. Where a Submittal is required by the Contract Documents or the Schedule of Submittals, any
related Work perf f the pertinent submittal will be
at the sole expense and responsibility of Contractor.
C. Review:
1. City will provide timely review of required Submittals in accordance with the Schedule of
Submittals acceptable to City. review and acceptance will be only to determine if the
items covered by the submittals will, after installation or incorporation in the Work, conform
to the information given in the Contract Documents and be compatible with the design
concept of the completed Project as a functioning whole as indicated by the Contract
Documents.
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CITY CONDITIONS DEVELOPER AWARDED PROJECTS City Project No. 103761
00 73 10- 23
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 23 of 35
2.tance will not extend to means, methods, techniques, sequences, or
procedures of construction (except where a particular means, method, technique, sequence,
or procedure of construction is specifically and expressly called for by the Contract
Documents) or to safety precautions or programs incident thereto. The review and
acceptance of a separate item as such will not indicate approval of the assembly in which the
item functions.
3. review and acceptance shall not relieve Contractor from responsibility for any
variation from the requirements of the Contract Documents unless Contractor has complied
with the requirements of Section 01 33 00 and City has given written acceptance of each
such variation by specific written notation thereof incorporated in or accompanying the
Submittal. review and acceptance shall not relieve Contractor from responsibility for
complying with the requirements of the Contract Documents.
5.17 Contr s General Warranty and Guarantee
A. Contractor warrants and guarantees to City that all Work will be in accordance with the Contract
Documents and will not be defective. City and its officers, directors, members, partners,
employees, agents, consultants, and subcontractors shall be entitled to rely on representation of
Contract s warranty and guarantee.
B. Contract s warranty and guarantee hereunder excludes defects or damage caused by:
1. abuse, modification, or improper maintenance or operation by persons other than Contractor,
Subcontractors, Suppliers, or any other individual or entity for whom Contractor is
responsible; or
2. normal wear and tear under normal usage.
C. Contract s obligation to perform and complete the Work in accordance with the Contract
Documents shall be absolute. None of the following will constitute an acceptance of Work that is
not in accordance with the Contract Documents or a release of Cont obligation to
perform the Work in accordance with the Contract Documents:
1. observations by City;
2. recommendation or payment by City or Developer of any progress or final payment;
3. the issuance of a certificate of Final Acceptance by City or any payment related thereto by
City;
4. use or occupancy of the Work or any part thereof by City;
5. any review and acceptance of a Submittal by City;
6. any inspection, test, or approval by others; or
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CITY CONDITIONS DEVELOPER AWARDED PROJECTS City Project No. 103761
00 73 10- 24
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 24 of 35
7. any correction of defective Work by City.
D. The Contractor shall remedy any defects or damages in the Work and pay for any damage to
other work or property resulting therefrom which shall appear within a period of two (2) years
from the date of Final Acceptance of the Work unless a longer period is specified and shall
furnish a good and sufficient maintenance bond, complying with the requirements of Article
4.02.B. The City will give notice of observed defects with reasonable promptness.
5.18 Indemnification
A. Contractor covenants and agrees to indemnify, hold harmless and defend, at its own expense, the
City, its officers, servants and employees, from and against any and all claims arising out of, or
alleged to arise out of, the work and services to be performed by the Contractor, its officers,
agents, employees, subcontractors, licenses or invitees under this Contract.THIS
INDEMNIFICATION PROVISION IS SPECIFICALLY INTENDED TO OPERATE
AND BE EFFECTIVE EVEN IF IT IS ALLEGED OR PROVEN THAT ALL OR SOME
OF THE DAMAGES BEING SOUGHT WERE CAUSED, IN WHOLE OR IN PART, BY
ANY ACT, OMISSION OR NEGLIGENCE OF THE CITY. This indemnity provision is
intended to include, without limitation, indemnity for costs, expenses and legal fees incurred by
the City in defending against such claims and causes of actions.
B. Contractor covenants and agrees to indemnify and hold harmless, at its own expense, the City, its
officers, servants and employees, from and against any and all loss, damage or destruction of
property of the City, arising out of, or alleged to arise out of, the work and services to be
performed by the Contractor, its officers, agents, employees, subcontractors, licensees or invitees
under this Contract.THIS INDEMNIFICATION PROVISION IS SPECIFICALLY
INTENDED TO OPERATE AND BE EFFECTIVE EVEN IF IT IS ALLEGED OR
PROVEN THAT ALL OR SOME OF THE DAMAGES BEING SOUGHT WERE
CAUSED, IN WHOLE OR IN PART, BY ANY ACT, OMISSION OR NEGLIGENCE OF
THE CITY.
5.19 Delegation of Professional Design Services
A. Contractor will not be required to provide professional design services unless such services are
specifically required by the Contract Documents for a portion of the Work or unless such
services are required to carry out responsibilities for construction means, methods,
techniques, sequences and procedures.
B. If professional design services or certifications by a design professional related to systems,
materials or equipment are specifically required of Contractor by the Contract Documents, City
will specify all performance and design criteria that such services must satisfy. Contractor shall
cause such services or certifications to be provided by a properly licensed professional, whose
signature and seal shall appear on all drawings, calculations, specifications, certifications, and
Submittals prepared by such professional. Submittals related to the Work designed or certified
by such professional, if prepared by others, shall bear such prof written approval when
submitted to City.
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CITY CONDITIONS DEVELOPER AWARDED PROJECTS City Project No. 103761
00 73 10- 25
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 25 of 35
C. City shall be entitled to rely upon the adequacy, accuracy and completeness of the services,
certifications or approvals performed by such design professionals, provided City has specified
to Contractor performance and design criteria that such services must satisfy.
D. Pursuant to this Paragraph 5.19, City s review and acceptance of design calculations and design
drawings will be only for the limited purpose of checking for conformance with performance
and design criteria given and the design concept expressed in the Contract Documents. City
review and acceptance of Submittals (except design calculations and design drawings) will be
only for the purpose stated in Paragraph 5.16.C.
5.20 Right to Audit:
A. The City reserves the right to audit all projects utilizing City funds
B. The Contractor agrees that the City shall, until the expiration of three (3) years after final
payment under this Contract, have access to and the right to examine and photocopy any directly
pertinent books, documents, papers, and records of the Contractor involving transactions relating
to this Contract. Contractor agrees that the City shall have access during Regular Working Hours
to all necessary Contractor facilities and shall be provided adequate and appropriate work space
in order to conduct audits in compliance with the provisions of this Paragraph. The City shall
give Contractor reasonable advance notice of intended audits.
C. Contractor further agrees to include in all its subcontracts hereunder a provision to the effect that
the subcontractor agrees that the City shall, until the expiration of three (3) years after final
payment under this Contract, have access to and the right to examine and photocopy any directly
pertinent books, documents, papers, and records of such Subcontractor, involving transactions to
the subcontract, and further, that City shall have access during Regular Working Hours to all
Subcontractor facilities, and shall be provided adequate and appropriate work space in order to
conduct audits in compliance with the provisions of this Paragraph. The City shall give
Subcontractor reasonable advance notice of intended audits.
D. Contractor and Subcontractor agree to photocopy such documents as may be requested by the
City. The City agrees to reimburse Contractor for the cost of the copies as follows at the rate
published in the Texas Administrative Code in effect as of the time copying is performed.
5.21 Nondiscrimination
A. The City is responsible for operating Public Transportation Programs and implementing transit-
related projects, which are funded in part with Federal financial assistance awarded by the U.S.
Department of Transportation and the Federal Transit Administration (FTA), without
discriminating against any person in the United States on the basis of race, color, or national
origin.
B.Title VI, Civil Rights Act of 1964 as amended: Contractor shall comply with the requirements of
the Act and the Regulations as further defined in the Supplementary Conditions for any project
receiving Federal assistance.
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CITY CONDITIONS DEVELOPER AWARDED PROJECTS City Project No. 103761
00 73 10- 26
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 26 of 35
ARTICLE 6 OTHER WORK AT THE SITE
6.01 Related Work at Site
A. City may perform other work related to the Project at the Site with City s employees, or other
City contractors, or through other direct contracts therefor, or have other work performed by
utility owners. If such other work is not noted in the Contract Documents, then written notice
thereof will be given to Contractor prior to starting any such other work; and
B. Contractor shall afford each other contractor who is a party to such a direct contract, each utility
owner, and City, if City is performing other work with employees or other City
contractors, proper and safe access to the Site, provide a reasonable opportunity for the
introduction and storage of materials and equipment and the execution of such other work, and
properly coordinate the Work with theirs. Contractor shall do all cutting, fitting, and patching of
the Work that may be required to properly connect or otherwise make its several parts come
together and properly integrate with such other work. Contractor shall not endanger any work of
others by cutting, excavating, or otherwise altering such work; provided, however, that
Contractor may cut or alter others' work with the written consent of City and the others whose
work will be affected.
C. If the proper execution or results of any part of Contract Work depends upon work
performed by others under this Article 7, Contractor shall inspect such other work and promptly
report to City in writing any delays, defects, or deficiencies in such other work that render it
unavailable or unsuitable for the proper execution a Wo
failure to so report will constitute an acceptance of such other work as fit and proper for
integration with Contract Work except for latent defects in the work provided by others.
ARTICLE 7 CITY S RESPONSIBILITIES
7.01 Inspections, Tests, and Approvals
responsibility with respect to certain inspections, tests, and approvals is set forth in Paragraph
11.03.
7.02 Limitations on Responsibilities
A. The City shall not supervise, direct, or have control or authority over, nor be responsible for,
Contract s means, methods, techniques, sequences, or procedures of construction, or the safety
precautions and programs incident thereto, or for any failure of Contractor to comply with Laws
and Regulations applicable to the performance of the Work. City will not be responsible for
Contract failure to perform the Work in accordance with the Contract Documents.
B. City will notify the Contractor of applicable safety plans pursuant to Paragraph 5.13.
00 73 10- 27
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 27 of 35
7.03 Compliance with Safety Program
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CITY CONDITIONS DEVELOPER AWARDED PROJECTS City Project No. 103761
While at the Site, Cit s employees and representatives shall comply with the specific applicable
requirements of Contra safety programs of which City has been informed pursuant to
Paragraph 5.13.
ARTICLE 8 CITY S OBSERVATION STATUS DURING CONSTRUCTION
8.01
City will provide one or more Project Representative(s) during the construction period. The duties
and responsibilities and the limitations of authority of representative during construction are
set forth in the Contract Documents.
A. Project Representative will make visits to the Site at intervals appropriate to the various
stages of construction as City deems necessary in order to observe the progress that has been
made and the quality of the various aspects of executed Work. Based on
information obtained during such visits and observations, Project Representative will
determine, in general, if the Work is proceeding in accordance with the Contract Documents.
Project Representative will not be required to make exhaustive or continuous inspections
on the Site to check the quality or quantity of the Work. P forts
will be directed toward providing City a greater degree of confidence that the completed Work
will conform generally to the Contract Documents.
B. Project Repre visits and observations are subject to all the limitations on
authority and responsibility in the Contract Documents.
8.02 Authorized Variations in Work
Project Representative may authorize minor variations in the Work from the requirements of
the Contract Documents which do not involve an adjustment in the Contract Price or the Contract
Time and are compatible with the design concept of the completed Project as a functioning whole as
indicated by the Contract Documents. These may be accomplished by a Field Order and will be
binding on City Developer, and also on Contractor, who shall perform the Work involved promptly.
8.03 Rejecting Defective Work
City will have authority to reject Work which Project Representative believes to be defective,
or will not produce a completed Project that conforms to the Contract Documents or that will
prejudice the integrity of the design concept of the completed Project as a functioning whole as
indicated by the Contract Documents. City will have authority to conduct special inspection or
testing of the Work as provided in Article 11, whether or not the Work is fabricated, installed, or
completed.
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CITY CONDITIONS DEVELOPER AWARDED PROJECTS City Project No. 103761
00 73 10- 28
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 28 of 35
8.04 Determinations for Work Performed
Contractor will determine the actual quantities and classifications of Work pe
Representative will review with Contractor the preliminary determinations on such matters before
rendering a written recommendation. written decision will be final (except as modified to
reflect changed factual conditions or more accurate data).
ARTICLE 9 CHANGES IN THE WORK
9.01 Authorized Changes in the Work
A. Without invalidating the Contract and without notice to any surety, City may, at any time or
from time to time, order Extra Work. Upon notice of such Extra Work, Contractor shall
promptly proceed with the Work involved which will be performed under the applicable
conditions of the Contract Documents (except as otherwise specifically provided). Extra Work
shall be memorialized by a Participating Change Order which may or may not precede an order
of Extra work.
B. For minor changes of Work not requiring changes to Contract Time or Contract Price on a
project with City participation, a Field Order may be issued by the City.
9.02 Notification to Surety
If the provisions of any bond require notice to be given to a surety of any change affecting the
general scope of the Work or the provisions of the Contract Documents (including, but not limited
to, Contract Price or Contract Time), the giving of any such notice will be s
responsibility. The amount of each applicable bond will be adjusted by the Contractor to reflect the
effect of any such change.
ARTICLE 10 CHANGE OF CONTRACT PRICE; CHANGE OF CONTRACT TIME
10.01 Change of Contract Price
A. The Contract Price may only be changed by a Participating Change Order for projects with City
participation.
10.02 Change of Contract Time
A. The Contract Time may only be changed by a Participating Change Order for projects with City
participation.
10.03 Delays
A. If Contractor is delayed, City shall not be liable to Contractor for any claims, costs, losses, or
damages (including but not limited to all fees and charges of engineers, architects, attorneys, and
other professionals and all court or arbitration or other dispute resolution costs) sustained by
Contractor on or in connection with any other project or anticipated project.
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CITY CONDITIONS DEVELOPER AWARDED PROJECTS City Project No. 103761
00 73 10- 29
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 29 of 35
ARTICLE 11 TESTS AND INSPECTIONS; CORRECTION, REMOVAL OR ACCEPTANCE OF
DEFECTIVE WORK
11.01 Notice of Defects
Notice of all defective Work of which City has actual knowledge will be given to Contractor.
Defective Work may be rejected, corrected, or accepted as provided in this Article 13.
11.02 Access to Work
City, independent testing laboratories, and governmental agencies with jurisdictional interests will
have access to the Site and the Work at reasonable times for their observation, inspection, and
testing. Contractor shall provide them proper and safe conditions for such access and advise them of
Contract s safety procedures and programs so that they may comply therewith as applicable.
11.03 Tests and Inspections
A. Contractor shall give City timely notice of readiness of the Work for all required inspections,
tests, or approvals and shall cooperate with inspection and testing personnel to facilitate required
inspections or tests.
B. If Contract Documents, Laws or Regulations of any public body having jurisdiction require any
of the Work (or part thereof) to be inspected, tested, or approved, Contractor shall assume full
responsibility for arranging and obtaining such independent inspections, tests, retests or
approvals, pay all costs in connection therewith, and furnish City the required certificates of
inspection or approval; excepting, however, those fees specifically identified in the
Supplementary Conditions or any Texas Department of Licensure and Regulation (TDLR)
inspections, which shall be paid as described in the Supplementary Conditions.
C. Contractor shall be responsible for arranging and obtaining and shall pay all costs in connection
with any inspections, tests, re-tests, or approvals required for acceptance of materials or
equipment to be incorporated in the Work; or acceptance of materials, mix designs, or equipment
submitted for approval prior to purchase thereof for incorporation in the Work.
Such inspections, tests, re-tests, or approvals shall be performed by organizations approved by
City.
D. City may arrange for the services of an independent testing laboratory to
perform any inspections or tests e for any part of the Work, as determined solely by
City.
1. City will coordinate such Testing to the extent possible, with Contractor;
2. Should any Testing under this Section 11.03 D result in a f d not pass or other
similar negative result, the Contractor shall be responsible for paying for any and all retests.
f City initiated Testing shall be deemed a negative
result and require a retest.
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CITY CONDITIONS DEVELOPER AWARDED PROJECTS City Project No. 103761
00 73 10- 30
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 30 of 35
3. Any amounts owed for any retest under this Section 11.03 D shall be paid directly to the
Testing Lab by Contractor. City will forward all invoices for retests to
Developer/Contractor.
4. If Contractor fails to pay the Testing Lab, City will not issue a letter of Final Acceptance
until the Testing Lab is Paid
E. If any Work (or the work of others) that is to be inspected, tested, or approved is covered by
Contractor without written concurrence of City, Contractor shall, if requested by City, uncover
such Work for observation.
11.04 Uncovering Work
A. If any Work is covered contrary to the Contract Documents or specific instructions by the City, it
must, if requested by City, be uncovered for Ci observation and replaced at s
expense.
11.05 City May Stop the Work
If the Work is defective, or Contractor fails to supply sufficient skilled workers or suitable materials
or equipment, or fails to perform the Work in such a way that the completed Work will conform to
the Contract Documents, City may order Contractor to stop the Work, or any portion thereof, until
the cause for such order has been eliminated; however, this right of City to stop the Work shall not
give rise to any duty on the part of City to exercise this right for the benefit of Contractor, any
Subcontractor, any Supplier, any other individual or entity, or any surety for, or employee or agent
of any of them.
11.06 Correction or Removal of Defective Work
A. Promptly after receipt of written notice, Contractor shall correct all defective Work pursuant to
an acceptable schedule, whether or not fabricated, installed, or completed, or, if the Work has
been rejected by City, remove it from the Project and replace it with Work that is not defective.
Contractor shall pay all claims, costs, additional testing, losses, and damages (including but not
limited to all fees and charges of engineers, architects, attorneys, and other professionals and all
court or arbitration or other dispute resolution costs) arising out of or relating to such correction
or removal (including but not limited to all costs of repair or replacement of work of others).
Failure to require the removal of any defective Work shall not constitute acceptance of such
Work.
B. When correcting defective Work under the terms of this Paragraph 11.06 or Paragraph 11.07,
Contractor shall take no action that would void o
guarantee, if any, on said Work.
11.07 Correction Period
A. If within two (2) years after the date of Final Acceptance (or such longer period of time as may
be prescribed by the terms of any applicable special guarantee required by the Contract
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CITY CONDITIONS DEVELOPER AWARDED PROJECTS City Project No. 103761
00 73 10- 31
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 31 of 35
Documents), any Work is found to be defective, or if the repair of any damages to the land or
areas made available for Contractor s use by City or permitted by Laws and Regulations as
contemplated in Paragraph 5.10.A is found to be defective, Contractor shall promptly, without
cost to City and in accordance w
1. repair such defective land or areas; or
2. correct such defective Work; or
3. if the defective Work has been rejected by City, remove it from the Project and replace it
with Work that is not defective, and
4. satisfactorily correct or repair or remove and replace any damage to other Work, to the work
of others or other land or areas resulting therefrom.
B. If Contractor does not promptly comply with the terms of written instructions, or in an
emergency where delay would cause serious risk of loss or damage, City may have the defective
Work corrected or repaired or may have the rejected Work removed and replaced. All claims,
costs, losses, and damages (including but not limited to all fees and charges of engineers,
architects, attorneys, and other professionals and all court or other dispute resolution costs)
arising out of or relating to such correction or repair or such removal and replacement (including
but not limited to all costs of repair or replacement of work of others) will be paid by Contractor.
C. Where defective Work (and damage to other Work resulting therefrom) has been corrected or
removed and replaced under this Paragraph 11.07, the correction period hereunder with respect
to such Work may be required to be extended for an additional period of one year after the end
of the initial correction period. City shall provide 30 days written notice to Contractor and
Developer should such additional warranty coverage be required. Contract obligations under
this Paragraph 11.07 are in addition to any other obligation or warranty. The provisions of this
Paragraph 11.07 shall not be construed as a substitute for, or a waiver of, the provisions of any
applicable statute of limitation or repose.
11.08 City May Correct Defective Work
A. If Contractor fails within a reasonable time after written notice from City to correct defective
Work, or to remove and replace rejected Work as required by City in accordance with Paragraph
11.06.A, or if Contractor fails to perform the Work in accordance with the Contract Documents,
or if Contractor fails to comply with any other provision of the Contract Documents, City may,
after seven (7) days written notice to Contractor and the Developer, correct, or remedy any such
deficiency.
B. In exercising the rights and remedies under this Paragraph 11.09, City shall proceed
expeditiously. In connection with such corrective or remedial action, City may exclude
Contractor from all or part of the Site, take possession of all or part of the Work and suspend
Contract services related thereto, and incorporate in the Work all materials and equipment
incorporated in the Work, stored at the Site or for which City has paid Contractor but which are
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CITY CONDITIONS DEVELOPER AWARDED PROJECTS City Project No. 103761
00 73 10- 32
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 32 of 35
stored elsewhere. Contractor shall allow City, representatives, agents, consultants,
employees, and other contractors, access to the Site to enable City to exercise the rights
and remedies under this Paragraph.
C. All claims, costs, losses, and damages (including but not limited to all fees and charges of
engineers, architects, attorneys, and other professionals and all court or other dispute resolution
costs) incurred or sustained by City in exercising the rights and remedies under this Paragraph
13.09 will be charged against Contractor, and a Change Order will be issued incorporating the
necessary revisions in the Contract Documents with respect to the Work; and City shall be
entitled to an appropriate decrease in the Contract Price.
D. Contractor shall not be allowed an extension of the Contract Time because of any delay in the
performance of the Work attributable to the exercise of rights and remedies under this
Paragraph 11.09.
ARTICLE 12 COMPLETION
12.01 Warranty of Title
Contractor warrants and guarantees that title to all Work, materials, and equipment covered by any
Application for Payment will pass to City no later than the time of Final Acceptance and shall be
free and clear of all Liens.
12.02 Partial Utilization
A. Prior to Final Acceptance of all the Work, City may use or occupy any substantially completed
part of the Work which has specifically been identified in the Contract Documents, or which
City, determines constitutes a separately functioning and usable part of the Work that can be
used by City for its intended purpose without significant interference with
performance of the remainder of the Work. City at any time may notify Contractor in writing to
permit City to use or occupy any such part of the Work which City determines to be ready for its
intended use, subject to the following conditions:
1. Contractor at any time may notify City in writing that Contractor considers any such part of
the Work ready for its intended use.
2. Within a reasonable time after notification as enumerated in Paragraph 14.05.A.1, City and
Contractor shall make an inspection of that part of the Work to determine its status of
completion. If City does not consider that part of the Work to be substantially complete, City
will notify Contractor in writing giving the reasons therefor.
3. Partial Utilization will not constitute Final Acceptance by City.
12.03 Final Inspection
A. Upon written notice from Contractor that the entire Work is complete in accordance with the
Contract Documents:
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CITY CONDITIONS DEVELOPER AWARDED PROJECTS City Project No. 103761
00 73 10- 33
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 33 of 35
1. within 10 days, City will schedule a Final Inspection with Contractor.
2. City will notify Contractor in writing of all particulars in which this inspection reveals that
the Work is incomplete or defective. Contractor shall immediately take such measures as are
necessary to complete such Work or remedy such deficiencies.
12.04 Final Acceptance
A. Upon completion by Contractor to satisfaction, of any additional Work identified in the
Final Inspection, City will issue to Contractor a letter of Final Acceptance upon the satisfaction
of the following:
1. All documentation called for in the Contract Documents, including but not limited to the
evidence of insurance required by Paragraph 5.03;
2. consent of the surety, if any, to Final Acceptance;
3. a list of all pending or released Damage Claims against City that Contractor believes are
unsettled; and
4. affidavits of payments and complete and legally effective releases or waivers (satisfactory to
City) of all Lien rights arising out of or Liens filed in connection with the Work.
5.after all Damage Claims have been resolved:
a. directly by the Contractor or;
b. Contractor provides evidence that the Damage Claim has been reported to Contractor s
insurance provider for resolution.
6. Issuing Final Acceptance by the City shall not relieve the Contractor of any guarantees or
other requirements of the Contract Documents which specifically continue thereafter.
ARTICLE 13 SUSPENSION OF WORK
13.01 City May Suspend Work
A. At any time and without cause, City may suspend the Work or any portion thereof by written
notice to Contractor and which may fix the date on which Work will be resumed. Contractor
shall resume the Work on the date so fixed. During temporary suspension of the Work covered
by these Contract Documents, for any reason, the City will stop contract time on City
participation projects.
B. Should the Contractor not be able to complete a portion of the Project due to causes beyond the
control of and without the fault or negligence of the Contractor, and should it be determined by
mutual consent of the Contractor and City that a solution to allow construction to proceed is not
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CITY CONDITIONS DEVELOPER AWARDED PROJECTS City Project No. 103761
00 73 10- 34
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 34 of 35
available within a reasonable period of time, Contractor may request an extension in Contract
Time, directly attributable to any such suspension.
C. If it should become necessary to suspend the Work for an indefinite period, the Contractor shall
store all materials in such a manner that they will not obstruct or impede the public unnecessarily
nor become damaged in any way, and he shall take every precaution to prevent damage or
deterioration of the work performed; he shall provide suitable drainage about the work, and erect
temporary structures where necessary.
ARTICLE 14 MISCELLANEOUS
14.01 Giving Notice
A. Whenever any provision of the Contract Documents requires the giving of written notice, it will
be deemed to have been validly given if:
1. delivered in person to the individual or to a member of the firm or to an officer of the
corporation for whom it is intended; or
2. delivered at or sent by registered or certified mail, postage prepaid, to the last business
address known to the giver of the notice.
B. Business address changes must be promptly made in writing to the other party.
C. Whenever the Contract Documents specifies giving notice by electronic means such electronic
notice shall be deemed sufficient upon confirmation of receipt by the receiving party.
14.02 Computation of Times
When any period of time is referred to in the Contract Documents by days, it will be computed to
exclude the first and include the last day of such period. If the last day of any such period falls on a
Saturday or Sunday or on a day made a legal holiday the next Working Day shall become the last
day of the period.
14.03 Cumulative Remedies
The duties and obligations imposed by these General Conditions and the rights and remedies
available hereunder to the parties hereto are in addition to, and are not to be construed in any way as
a limitation of, any rights and remedies available to any or all of them which are otherwise imposed
or available by Laws or Regulations, by special warranty or guarantee, or by other provisions of the
Contract Documents. The provisions of this Paragraph will be as effective as if repeated specifically
in the Contract Documents in connection with each particular duty, obligation, right, and remedy to
which they apply.
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CITY CONDITIONS DEVELOPER AWARDED PROJECTS City Project No. 103761
00 73 10- 35
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 35 of 35
14.04 Survival of Obligations
All representations, indemnifications, warranties, and guarantees made in, required by, or given in
accordance with the Contract Documents, as well as all continuing obligations indicated in the
Contract Documents, will survive final payment, completion, and acceptance of the Work or
termination or completion of the Contract or termination of the services of Contractor.
14.05 Headings
Article and paragraph headings are inserted for convenience only and do not constitute parts of these
General Conditions.
01 11 00 - 1
DAP SUMMARY OF WORK
Page 1 of 3
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Developer Awarded Projects City Project No. 103761
Revised December 20, 2012
SECTION 01 11 001
SUMMARY OF WORK2
PART 1 -GENERAL3
1.1 SUMMARY4
A.Section Includes:5
1.Summary of Work to be performed in accordance with the Contract Documents6
B.Deviations from this City of Fort Worth Standard Specification7
1. None.8
C.Related Specification Sections include, but are not necessarily limited to:9
1.Division 0 - Bidding Requirements, Contract Forms, and Conditions of the Contract10
2.Division 1 - General Requirements11
1.2 PRICE AND PAYMENT PROCEDURES12
A.Measurement and Payment13
1.Work associated with this Item is considered subsidiary to the various items bid.14
No separate payment will be allowed for this Item.15
1.3 REFERENCES [NOT USED]16
1.4 ADMINISTRATIVE REQUIREMENTS17
A.Work Covered by Contract Documents18
1.Work is to include furnishing all labor, materials, and equipment, and performing19
all Work necessary for this construction project as detailed in the Drawings and20
Specifications.21
B.Subsidiary Work22
1.Any and all Work specifically governed by documentary requirements for the23
project, such as conditions imposed by the Drawings or Contract Documents in24
which no specific item for bid has been provided for in the Proposal and the item is25
not a typical unit bid item included on the standard bid item list, then the item shall26
be considered as a subsidiary item of Work, the cost of which shall be included in27
the price bid in the Proposal for various bid items.28
C.Use of Premises29
1.Coordinate uses of premises under direction of the City.30
2.Assume full responsibility for protection and safekeeping of materials and31
equipment stored on the Site.32
3.Use and occupy only portions of the public streets and alleys, or other public places33
or other rights-of-way as provided for in the ordinances of the City, as shown in the34
Contract Documents, or as may be specifically authorized in writing by the City.35
a.A reasonable amount of tools, materials, and equipment for construction36
purposes may be stored in such space, but no more than is necessary to avoid37
delay in the construction operations.38
01 11 00 - 2
DAP SUMMARY OF WORK
Page 2 of 3
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Developer Awarded Projects City Project No. 103761
Revised December 20, 2012
b.Excavated and waste materials shall be stored in such a way as not to interfere1
with the use of spaces that may be designated to be left free and unobstructed2
and so as not to inconvenience occupants of adjacent property.3
c.If the street is occupied by railroad tracks, the Work shall be carried on in such4
manner as not to interfere with the operation of the railroad.5
1)All Work shall be in accordance with railroad requirements set forth in6
Division 0 as well as the railroad permit.7
D.Work within Easements8
1.Do not enter upon private property for any purpose without having previously9
obtained permission from the owner of such property.10
2.Do not store equipment or material on private property unless and until the11
specified approval of the property owner has been secured in writing by the12
Contractor and a copy furnished to the City.13
3.Unless specifically provided otherwise, clear all rights-of-way or easements of14
obstructions which must be removed to make possible proper prosecution of the15
Work as a part of the project construction operations.16
4.Preserve and use every precaution to prevent damage to, all trees, shrubbery, plants,17
lawns, fences, culverts, curbing, and all other types of structures or improvements,18
to all water, sewer, and gas lines, to all conduits, overhead pole lines, or19
appurtenances thereof, including the construction of temporary fences and to all20
other public or private property adjacent to the Work.21
5.Notify the proper representatives of the owners or occupants of the public or private22
lands of interest in lands which might be affected by the Work.23
a.Such notice shall be made at least 48 hours in advance of the beginning of the24
Work.25
b.Notices shall be applicable to both public and private utility companies and any26
corporation, company, individual, or other, either as owners or occupants,27
whose land or interest in land might be affected by the Work.28
c.Be responsible for all damage or injury to property of any character resulting29
from any act, omission, neglect, or misconduct in the manner or method or30
execution of the Work, or at any time due to defective work, material, or31
equipment.32
6.Fence33
a.Restore all fences encountered and removed during construction of the Project34
to the original or a better than original condition.35
b.Erect temporary fencing in place of the fencing removed whenever the Work is36
not in progress and when the site is vacated overnight, and/or at all times to37
provide site security.38
c.The cost for all fence work within easements, including removal, temporary39
closures and replacement, shall be subsidiary to the various items bid in the40
project proposal, unless a bid item is specifically provided in the proposal.41
01 11 00 - 3
DAP SUMMARY OF WORK
Page 3 of 3
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Developer Awarded Projects City Project No. 103761
Revised December 20, 2012
1.5 SUBMITTALS [NOT USED]1
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]2
1.7 CLOSEOUT SUBMITTALS [NOT USED]3
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]4
1.9 QUALITY ASSURANCE [NOT USED]5
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]6
1.11 FIELD [SITE] CONDITIONS [NOT USED]7
1.12 WARRANTY [NOT USED]8
PART 2 -PRODUCTS [NOT USED]9
PART 3 -EXECUTION [NOT USED]10
END OF SECTION11
12
Revision Log
DATE NAME SUMMARY OF CHANGE
13
01 25 00 - 1
DAP SUBSTITUTION PROCEDURES
Page 1 of 4
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS DEVELOPER AWARDED PROJECTS City Project No. 103761
Revised August 30, 2013
SECTION 01 25 001
SUBSTITUTION PROCEDURES2
PART 1 -GENERAL3
1.1 SUMMARY4
A.Section Includes:5
1.The procedure for requesting the approval of substitution of a product that is not6
equivalent to a product which is specified by descriptive or performance criteria or7
defined by reference to 1 or more of the following:8
a.Name of manufacturer9
b.Name of vendor10
c.Trade name11
d.Catalog number12
2.Substitutions are not "or-equals".13
B.Deviations from this City of Fort Worth Standard Specification14
1.None.15
C.Related Specification Sections include, but are not necessarily limited to:16
1.Division 0 Bidding Requirements, Contract Forms and Conditions of the Contract17
2.Division 1 General Requirements18
1.2 PRICE AND PAYMENT PROCEDURES19
A.Measurement and Payment20
1.Work associated with this Item is considered subsidiary to the various items bid. No21
separate payment will be allowed for this Item.22
1.3 REFERENCES [NOT USED]23
1.4 ADMINISTRATIVE REQUIREMENTS24
A.Request for Substitution - General25
1.Within 30 days after award of Contract (unless noted otherwise), the City will26
consider formal requests from Contractor for substitution of products in place of27
those specified.28
2.Certain types of equipment and kinds of material are described in Specifications by29
means of references to names of manufacturers and vendors, trade names, or catalog30
numbers.31
a.When this method of specifying is used, it is not intended to exclude from32
consideration other products bearing other manufacturer's or vendor's names,33
trade names, or catalog numbers, provided said products are "or-equals," as34
determined by City.35
3.Other types of equipment and kinds of material may be acceptable substitutions36
under the following conditions:37
a.Or-equals are unavailable due to strike, discontinued production of products38
meeting specified requirements, or other factors beyond control of Contractor;39
or,40
01 25 00 - 2
DAP SUBSTITUTION PROCEDURES
Page 2 of 4
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS DEVELOPER AWARDED PROJECTS City Project No. 103761
Revised August 30, 2013
b.Contractor proposes a cost and/or time reduction incentive to the City.1
1.5 SUBMITTALS2
A.See Request for Substitution Form (attached)3
B.Procedure for Requesting Substitution4
1.Substitution shall be considered only:5
a.After award of Contract6
b.Under the conditions stated herein7
2.Submit 3 copies of each written request for substitution, including:8
a.Documentation9
1)Complete data substantiating compliance of proposed substitution with10
Contract Documents11
2)Data relating to changes in construction schedule, when a reduction is12
proposed13
3)Data relating to changes in cost14
b.For products15
1)Product identification16
a)Manufacturer's name17
b)Telephone number and representative contact name18
c)Specification Section or Drawing reference of originally specified19
product, including discrete name or tag number assigned to original20
product in the Contract Documents21
2)Manufacturer's literature clearly marked to show compliance of proposed22
product with Contract Documents23
3)Itemized comparison of original and proposed product addressing product24
characteristics including, but not necessarily limited to:25
a)Size26
b)Composition or materials of construction27
c)Weight28
d)Electrical or mechanical requirements29
4)Product experience30
a)Location of past projects utilizing product31
b)Name and telephone number of persons associated with referenced32
projects knowledgeable concerning proposed product33
c)Available field data and reports associated with proposed product34
5)Samples35
a)Provide at request of City.36
b)Samples become the property of the City.37
c.For construction methods:38
1)Detailed description of proposed method39
2)Illustration drawings40
C.Approval or Rejection41
1.Written approval or rejection of substitution given by the City42
2.City reserves the right to require proposed product to comply with color and pattern43
of specified product if necessary to secure design intent.44
3.In the event the substitution is approved, if a reduction in cost or time results, it will45
be documented by Change Order.46
01 25 00 - 3
DAP SUBSTITUTION PROCEDURES
Page 3 of 4
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS DEVELOPER AWARDED PROJECTS City Project No. 103761
Revised August 30, 2013
4.Substitution will be rejected if:1
a.Submittal is not through the Contractor with his stamp of approval2
b.Request is not made in accordance with this Specification Section3
c.In the Developer opinion, acceptance will require substantial revision of the4
original design5
d.In the opinion, substitution will not perform adequately6
the function consistent with the design intent7
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]8
1.7 CLOSEOUT SUBMITTALS [NOT USED]9
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]10
1.9 QUALITY ASSURANCE11
A.In making request for substitution or in using an approved product, the Contractor12
represents that the Contractor:13
1.Has investigated proposed product, and has determined that it is adequate or14
superior in all respects to that specified, and that it will perform function for which it15
is intended16
2.Will provide same guarantee for substitute item as for product specified17
3.Will coordinate installation of accepted substitution into Work, to include building18
modifications if necessary, making such changes as may be required for Work to be19
complete in all respects20
4.Waives all claims for additional costs related to substitution which subsequently21
arise22
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]23
1.11 FIELD [SITE] CONDITIONS [NOT USED]24
1.12 WARRANTY [NOT USED]25
PART 2 -PRODUCTS [NOT USED]26
PART 3 -EXECUTION [NOT USED]27
END OF SECTION28
29
Revision Log
DATE NAME SUMMARY OF CHANGE
30
01 25 00 - 4
DAP SUBSTITUTION PROCEDURES
Page 4 of 4
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS DEVELOPER AWARDED PROJECTS City Project No. 103761
Revised August 30, 2013
EXHIBIT A1
REQUEST FOR SUBSTITUTION FORM:2
3
TO:4
PROJECT: DATE:5
We hereby submit for your consideration the following product instead of the specified item for6
the above project:7
SECTION PARAGRAPH SPECIFIED ITEM8
9
10
Proposed Substitution:11
Reason for Substitution:12
Include complete information on changes to Drawings and/or Specifications which proposed13
substitution will require for its proper installation.14
15
Fill in Blanks Below:16
A. Will the undersigned contractor pay for changes to the building design, including engineering17
and detailing costs caused by the requested substitution?18
19
20
B. What effect does substitution have on other trades?21
22
23
C. Differences between proposed substitution and specified item?24
25
26
D. Differences in product cost or product delivery time?27
28
29
E. Manufacturer's guarantees of the proposed and specified items are:30
31
Equal Better (explain on attachment)32
The undersigned states that the function, appearance and quality are equivalent or superior to the33
specified item.34
Submitted By:For Use by City35
36
Signature Recommended Recommended37
as noted38
39
Firm Not recommended Received late40
Address By41
Date42
Date Remarks43
Telephone44
45
For Use by City:46
47
Approved Rejected48
City Date49
01 31 19 - 1
DAP Preconstruction Meeting
Page 1 of 3
CITY OF FORT WORTH Public
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS DEVELOPER AWARDED PROJECTS City Project No. 103761
Revised April 7, 2014
SECTION 01 31 191
PRECONSTRUCTION MEETING2
PART 1 - GENERAL3
1.1 SUMMARY4
A. Section Includes:5
1. Provisions for the preconstruction meeting to be held prior to the start of Work to6
clarify construction contract administration procedures7
B. Deviations from this City of Fort Worth Standard Specification8
1. No construction schedule required unless requested by the City.9
C. Related Specification Sections include, but are not necessarily limited to:10
1. Division 0 Bidding Requirements, Contract Forms and Conditions of the Contract11
2. Division 1 General Requirements12
1.2 PRICE AND PAYMENT PROCEDURES13
A. Measurement and Payment14
1. Work associated with this Item is considered subsidiary to the various items bid. No15
separate payment will be allowed for this Item.16
1.3 REFERENCES [NOT USED]17
1.4 ADMINISTRATIVE REQUIREMENTS18
A. Coordination19
1. Attend preconstruction meeting.20
2. Representatives of Contractor, subcontractors and suppliers attending meetings shall be21
qualified and authorized to act on behalf of the entity each represents.22
3. Meeting administered by City may be tape recorded.23
a. If recorded, tapes will be used to prepare minutes and retained by City for future24
reference.25
B. Preconstruction Meeting26
1. A preconstruction meeting will be held within 14 days after the delivery of the27
distribution package to the City.28
The meeting will be scheduled and administered by the City.29
1.The Project Representative will preside at the meeting, prepare the notes of the30
meeting and distribute copies of same to all participants who so request by fully31
completing the attendance form to be circulated at the beginning of the meeting.32
2.Attendance shall include:33
a.Developer and Consultant34
b.Contractor's project manager35
c.Contractor's superintendent36
d.Any subcontractor or supplier representatives whom the Contractor may desire37
to invite or the City may request38
39
01 31 19 - 2
DAP Preconstruction Meeting
Page 2 of 3
CITY OF FORT WORTH Public
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS DEVELOPER AWARDED PROJECTS City Project No. 103761
Revised April 7, 2014
e.Other City representatives1
f.Others as appropriate2
3.Preliminary Agenda may include:3
a.Introduction of Project Personnel4
b.General Description of Project5
c.Status of right-of-way, utility clearances, easements or other pertinent permits6
d.7
e.Contract Time8
f.Notice to Proceed9
g.Construction Staking10
h.Progress Payments11
i.Extra Work and Change Order Procedures12
j.Field Orders13
k.Disposal Site Letter for Waste Material14
l.Insurance Renewals15
m.Payroll Certification16
n.Material Certifications and Quality Control Testing17
o.Public Safety and Convenience18
p.Documentation of Pre-Construction Conditions19
q.Weekend Work Notification20
r.Legal Holidays21
s.Trench Safety Plans22
t.Confined Space Entry Standards23
u.24
systems25
v.Storm Water Pollution Prevention Plan26
w.Coordination with other Contractors27
x.Early Warning System28
y.Contractor Evaluation29
z.Special Conditions applicable to the project30
aa.Damages Claims31
bb.Submittal Procedures32
cc.Substitution Procedures33
dd.Correspondence Routing34
ee.Record Drawings35
ff.Temporary construction facilities36
gg.MBE/SBE procedures37
hh.Final Acceptance38
ii. Final Payment39
jj.Questions or Comments40
01 31 19 - 3
DAP Preconstruction Meeting
Page 3 of 3
CITY OF FORT WORTH Public
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS DEVELOPER AWARDED PROJECTS City Project No. 103761
Revised April 7, 2014
1.5 SUBMITTALS [NOT USED]1
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]2
1.7 CLOSEOUT SUBMITTALS [NOT USED]3
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]4
1.9 QUALITY ASSURANCE [NOT USED]5
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]6
1.11 FIELD [SITE] CONDITIONS [NOT USED]7
1.12 WARRANTY [NOT USED]8
PART 2 - PRODUCTS [NOT USED]9
PART 3 - EXECUTION [NOT USED]10
END OF SECTION11
12
Revision Log
DATE NAME SUMMARY OF CHANGE
13
14
8
76
8
76
01 33 00- 1
DAP Submittals
Page 1 of 8
City Project No.
SECTION 01 33 001
DAP SUBMITTALS2
PART 1 - GENERAL3
1.1 SUMMARY4
A. Section Includes:5
1. General methods and requirements of submissions applicable to the following6
Work-related submittals:7
a. Shop Drawings8
b. Product Data (including Standard Product List submittals)9
c. Samples10
d. Mock Ups11
B. Deviations from this City of Fort Worth Standard Specification12
1. None.13
C. Related Specification Sections include, but are not necessarily limited to:14
1. Division 0 Bidding Requirements, Contract Forms and Conditions of the Contract15
2. Division 1 General Requirements16
1.2 PRICE AND PAYMENT PROCEDURES17
A. Measurement and Payment18
1. Work associated with this Item is considered subsidiary to the various items bid.19
No separate payment will be allowed for this Item.20
1.3 REFERENCES [NOT USED]21
1.4 ADMINISTRATIVE REQUIREMENTS22
A. Coordination23
1. Notify the City in writing, at the time of submittal, of any deviations in the24
submittals from the requirements of the Contract Documents.25
2. Coordination of Submittal Times26
a. Prepare, prioritize and transmit each submittal sufficiently in advance of27
performing the related Work or other applicable activities, or within the time28
specified in the individual Work Sections, of the Specifications.29
b. Contractor is responsible such that the installation will not be delayed by30
processing times including, but not limited to:31
a) Disapproval and resubmittal (if required)32
b) Coordination with other submittals33
c) Testing34
d) Purchasing35
e) Fabrication36
f) Delivery37
Similar sequenced activities38
c.No extension of time will be authorized because of the Contractor's failure to39
transmit submittals sufficiently in advance of the Work.40
01 33 00- 2
DAP Submittals
Page 2 of 8
City Project No.
d.Make submittals promptly in accordance with approved schedule, and in1
such sequence as to cause no delay in the Work or in the work of any other2
contractor.3
A.Submittal Numbering4
1.When submitting shop drawings or samples, utilize a 9-character submittal5
cross-reference identification numbering system in the following manner:6
a.Use the first 6 digits of the applicable Specification Section Number.7
b.For the next 2 digits number use numbers 01-99 to sequentially number8
each initial separate item or drawing submitted under each specific Section9
number.10
c.Last use a letter, A-Z, indicating the resubmission of the same drawing (i.e.11
A=2nd submission, B=3rd submission, C=4th submission, etc.). A typical12
submittal number would be as follows:13
14
03 30 00-08-B15
16
1)03 30 00 is the Specification Section for Concrete17
2)08 is the eighth initial submittal under this Specification Section18
3)B is the third submission (second resubmission) of that particular shop19
drawing20
B.Contractor Certification21
1.Review shop drawings, product data and samples, including those by22
subcontractors, prior to submission to determine and verify the following:23
a.Field measurements24
b.Field construction criteria25
c.Catalog numbers and similar data26
d.Conformance with the Contract Documents27
2.Provide each shop drawing, sample and product data submitted by the28
Contractor with a Certification Statement affixed including:29
a.The Contractor's Company name30
b.Signature of submittal reviewer31
c.Certification Statement32
1)ermined and33
verified field measurements, field construction criteria, materials,34
dimensions, catalog numbers and similar data and I have checked and35
coordinated each item with other applicable approved shop drawings."36
C.Submittal Format37
1.Fold shop drawings larger than 8 ½ inches x 11 inches to 8 ½ inches x 11inches.38
2.Bind shop drawings and product data sheets together.39
3.Order40
a.Cover Sheet41
1)Description of Packet42
2)Contractor Certification43
b.List of items / Table of Contents44
c.Product Data /Shop Drawings/Samples /Calculations45
01 33 00- 3
DAP Submittals
Page 3 of 8
City Project No.
D.Submittal Content1
1.The date of submission and the dates of any previous submissions2
2.The Project title and number3
3.Contractor identification4
4.The names of:5
a.Contractor6
b.Supplier7
c.Manufacturer8
5.Identification of the product, with the Specification Section number, page and9
paragraph(s)10
6.Field dimensions, clearly identified as such11
7.Relation to adjacent or critical features of the Work or materials12
8.Applicable standards, such as ASTM or Federal Specification numbers13
9.Identification by highlighting of deviations from Contract Documents14
10.Identification by highlighting of revisions on resubmittals15
11.An 8-inch x 3-inch blank space for Contractor and City stamps16
E.Shop Drawings17
1.As specified in individual Work Sections includes, but is not necessarily limited18
to:19
a.Custom-prepared data such as fabrication and erection/installation20
(working) drawings21
b.Scheduled information22
c.Setting diagrams23
d.Actual shopwork manufacturing instructions24
e.Custom templates25
f.Special wiring diagrams26
g.Coordination drawings27
h.Individual system or equipment inspection and test reports including:28
1) Performance curves and certifications29
i. As applicable to the Work30
2. Details31
a. Relation of the various parts to the main members and lines of the structure32
b. Where correct fabrication of the Work depends upon field measurements33
Provide such measurements and note on the drawings prior to submitting for34
approval.35
F.Product Data36
1.Standard Product37
List, clearly identify each item selected for use on the Project.38
2.For submittals of product data for products not39
Product List, submittal data may include, but is not necessarily limited to:40
a.Standard prepared data for manufactured products (sometimes referred to as41
catalog data)42
01 33 00- 4
DAP Submittals
Page 4 of 8
City Project No.
1)Such as the manufacturer's product specification and installation1
instructions2
2)Availability of colors and patterns3
3)Manufacturer's printed statements of compliances and applicability4
4)Roughing-in diagrams and templates5
5)Catalog cuts6
6)Product photographs7
7)Standard wiring diagrams8
8) Printed performance curves and operational-range diagrams9
9) Production or quality control inspection and test reports and certifications10
10) Mill reports11
11) Product operating and maintenance instructions and recommended12
spare-parts listing and printed product warranties13
12) As applicable to the Work14
H. Samples15
1. As specified in individual Sections, include, but are not necessarily limited to:16
a. Physical examples of the Work such as:17
1) Sections of manufactured or fabricated Work18
2) Small cuts or containers of materials19
3) Complete units of repetitively used products color/texture/pattern swatches20
and range sets21
4) Specimens for coordination of visual effect22
5) Graphic symbols and units of Work to be used by the City for independent23
inspection and testing, as applicable to the Work24
I. Do not start Work requiring a shop drawing, sample or product data nor any material to25
be fabricated or installed prior to the approval or qualified approval of such item.26
1. Fabrication performed, materials purchased or on-site construction accomplished27
which does not conform to approved shop drawings and data is at the Contractor's28
risk.29
2. The City will not be liable for any expense or delay due to corrections or remedies30
required to accomplish conformity.31
3. Complete project Work, materials, fabrication, and installations in conformance32
with approved shop drawings, applicable samples, and product data.33
J. Submittal Distribution34
1. Electronic Distribution35
a. Confirm development of Project directory for electronic submittals to be36
37
City.38
b. Shop Drawings39
1) Upload submittal to designated project directory and notify appropriate40
City representatives via email of submittal posting.41
2) Hard Copies42
a) 3 copies for all submittals43
b) If Contractor requires more than 1 hard copy of Shop Drawings44
returned, Contractor shall submit more than the number of copies listed45
above.46
c. Product Data47
01 33 00- 5
DAP Submittals
Page 5 of 8
City Project No.
1) Upload submittal to designated project directory and notify appropriate1
City representatives via email of submittal posting.2
2) Hard Copies3
a) 3 copies for all submittals4
d. Samples5
1) Distributed to the Project Representative6
2. Hard Copy Distribution (if required in lieu of electronic distribution)7
8
9
a.Shop Drawings10
1)Distributed to the City11
2)Copies12
a.8 copies for mechanical submittals13
b.7 copies for all other submittals14
c.If Contractor requires more than 3 copies of Shop Drawings15
returned, Contractor shall submit more than the number of copies16
listed above.17
b.Product Data18
1)Distributed to the City19
2)Copies20
a)4 copies21
c.Samples22
1)Distributed to the Project Representative23
2)Copies24
a)Submit the number stated in the respective Specification Sections.25
3.Distribute reproductions of approved shop drawings and copies of approved26
product data and samples, where required, to the job site file and elsewhere as27
directed by the City.28
a.Provide number of copies as directed by the City but not exceeding the29
number previously specified.30
K. Submittal Review31
1. The review of shop drawings, data and samples will be for general conformance32
with the design concept and Contract Documents. This is not to be construed as:33
a. Permitting any departure from the Contract requirements34
b. Relieving the Contractor of responsibility for any errors, including details,35
dimensions, and materials36
c. Approving departures from details furnished by the City, except as otherwise37
provided herein38
2. The review and approval of shop drawings, samples or product data by the City39
does not relieve the Contractor from his/her responsibility with regard to the40
fulfillment of the terms of the Contract.41
a. All risks of error and omission are assumed by the Contractor, and the City will42
have no responsibility therefore.43
3. The Contractor remains responsible for details and accuracy, for coordinating the44
Work with all other associated work and trades, for selecting fabrication processes,45
for techniques of assembly and for performing Work in a safe manner.46
01 33 00- 6
DAP Submittals
Page 6 of 8
City Project No.
4. If the shop drawings, data or samples as submitted describe variations and show a1
departure from the Contract requirements which City finds to be in the interest of2
the City and to be so minor as not to involve a change in Contract Price or time for3
performance, the City may return the reviewed drawings without noting an4
exception.5
5. Submittals will be returned to the Contractor under 1 of the following codes:6
a. Code 17
1) "NO EXCEPTIONS TAKEN" is assigned when there are no notations or8
comments on the submittal.9
a. When returned under this code the Contractor may release the10
equipment and/or material for manufacture.11
b. Code 212
1) "EXCEPTIONS NOTED". This code is assigned when a confirmation of13
the notations and comments IS NOT required by the Contractor.14
a. The Contractor may release the equipment or material for manufacture;15
however, all notations and comments must be incorporated into the16
final product.17
c. Code 318
1) "EXCEPTIONS NOTED/RESUBMIT". This combination of codes is19
assigned when notations and comments are extensive enough to require a20
resubmittal of the package.21
a) The Contractor may release the equipment or material for manufacture;22
however, all notations and comments must be incorporated into the23
final product.24
b) This resubmittal is to address all comments, omissions and25
non-conforming items that were noted.26
c) Resubmittal is to be received by the City within 15 Calendar Days of27
the date of the City's transmittal requiring the resubmittal.28
d. Code 429
1) "NOT APPROVED" is assigned when the submittal does not meet the30
intent of the Contract Documents.31
a) The Contractor must resubmit the entire package revised to bring the32
submittal into conformance.33
b) It may be necessary to resubmit using a different manufacturer/vendor34
to meet the Contract Documents.35
6. Resubmittals36
a. Handled in the same manner as first submittals37
1) Corrections other than requested by the City38
2) Marked with revision triangle or other similar method39
a)40
b.41
expense.42
1) All subsequent reviews will be performed at times convenient to the City43
and at the Contractor's expense, based on the City's or City44
rates.45
2) Provide Contractor reimbursement to the City within 30 Calendar Days for46
all such fees invoiced by the City.47
01 33 00- 7
DAP Submittals
Page 7 of 8
City Project No.
c. The need for more than 1 resubmission or any other delay in obtaining City's1
review of submittals, will not entitle the Contractor to an extension of Contract2
Time.3
7. Partial Submittals4
a. City reserves the right to not5
discretion.6
b. Submittals deemed by the City to be not complete will be returned to the7
Contractor, and will be considered "Not Approved" until resubmitted.8
c. The City may at its option provide a list or mark the submittal directing the9
Contractor to the areas that are incomplete.10
8. If the Contractor considers any correction indicated on the shop drawings to11
constitute a change to the Contract Documents, then written notice must be12
provided thereof to the Developer at least 7 Calendar Days prior to release for13
manufacture.14
9. When the shop drawings have been completed to the satisfaction of the City, the15
Contractor may carry out the construction in accordance therewith and no further16
changes therein except upon written instructions from the City.17
10. Each submittal, appropriately coded, will be returned within 30 Calendar Days18
following receipt of submittal by the City.19
L. Mock ups20
1. Mock Up units as specified in individual Sections, include, but are not necessarily21
limited to, complete units of the standard of acceptance for that type of Work to be22
used on the Project. Remove at the completion of the Work or when directed.23
M. Qualifications24
If specifically required in other Sections of these Specifications, submit a P.E.25
Certification for each item required.26
N. Request for Information (RFI)27
1. Contractor Request for additional information28
a. Clarification or interpretation of the contract documents29
b. When the Contractor believes there is a conflict between Contract Documents30
c. When the Contractor believes there is a conflict between the Drawings and31
Specifications32
1) Identify the conflict and request clarification33
2. Sufficient information shall be attached to permit a written response without further34
information.35
36
37
38
39
1.5 SUBMITTALS [NOT USED]40
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]41
1.7 CLOSEOUT SUBMITTALS [NOT USED]42
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]43
01 33 00- 8
DAP Submittals
Page 8 of 8
City Project No.
1.9 QUALITY ASSURANCE [NOT USED]1
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]2
1.11 FIELD [SITE] CONDITIONS [NOT USED]3
1.12 WARRANTY [NOT USED]4
5
6
7
8
PART 2 PRODUCTS [NOT USED]9
PART 3 - EXECUTION [NOT USED]10
END OF SECTION11
12
Revision Log
DATE NAME SUMMARY OF CHANGE
12/20/2012 D. Johnson 1.4.K.8. Working Days modified to Calendar Days
13
01 35 13 - 1
DAP SPECIAL PROJECT PROCEDURES
Page 1 of 7
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS DEVELOPER AWARDED PROJECTS City Project No. 103761
Revised August, 30, 2013
SECTION 01 35 131
SPECIAL PROJECT PROCEDURES2
PART 1 -GENERAL3
1.1 SUMMARY4
A.Section Includes:5
1.The procedures for special project circumstances that includes, but is not limited to:6
a.Coordination with the Texas Department of Transportation7
b.Work near High Voltage Lines8
c.Confined Space Entry Program9
d.Air Pollution Watch Days10
e.Use of Explosives, Drop Weight, Etc.11
f.Water Department Notification12
g.Public Notification Prior to Beginning Construction13
h.Coordination with United States Army Corps of Engineers14
i.Coordination within Railroad permits areas15
j.Dust Control16
k.Employee Parking17
B.Deviations from this City of Fort Worth Standard Specification18
1.None.19
C.Related Specification Sections include, but are not necessarily limited to:20
1.Division 0 Bidding Requirements, Contract Forms and Conditions of the Contract21
2.Division 1 General Requirements22
3.Section 33 12 25 Connection to Existing Water Mains23
24
1.2 REFERENCES25
A.Reference Standards26
1.Reference standards cited in this Specification refer to the current reference27
standard published at the time of the latest revision date logged at the end of this28
Specification, unless a date is specifically cited.29
2.Health and Safety Code, Title 9. Safety, Subtitle A. Public Safety, Chapter 752.30
High Voltage Overhead Lines.31
3.North Central Texas Council of Governments (NCTCOG) Clean Construction32
Specification33
1.3 ADMINISTRATIVE REQUIREMENTS34
A.Coordination with the Texas Department of Transportation35
1.When work in the right-of-way which is under the jurisdiction of the Texas36
Department of Transportation (TxDOT):37
a.Notify the Texas Department of Transportation prior to commencing any work38
therein in accordance with the provisions of the permit39
01 35 13 - 2
DAP SPECIAL PROJECT PROCEDURES
Page 2 of 7
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS DEVELOPER AWARDED PROJECTS City Project No. 103761
Revised August, 30, 2013
b.All work performed in the TxDOT right-of-way shall be performed in1
compliance with and subject to approval from the Texas Department of2
Transportation3
B.Work near High Voltage Lines4
1.Regulatory Requirements5
a.All Work near High Voltage Lines (more than 600 volts measured between6
conductors or between a conductor and the ground) shall be in accordance with7
Health and Safety Code, Title 9, Subtitle A, Chapter 752.8
2.Warning sign9
a.Provide sign of sufficient size meeting all OSHA requirements.10
3.Equipment operating within 10 feet of high voltage lines will require the following11
safety features12
a.Insulating cage-type of guard about the boom or arm13
b.Insulator links on the lift hook connections for back hoes or dippers14
c.Equipment must meet the safety requirements as set forth by OSHA and the15
safety requirements of the owner of the high voltage lines16
4.Work within 6 feet of high voltage electric lines17
a.Notification shall be given to:18
1)The power company (example: ONCOR)19
a)Maintain an accurate log of all such calls to Power Company and20
record action taken in each case.21
b.Coordination with Power Company22
1)After notification coordinate with the power company to:23
a)Erect temporary mechanical barriers, de-energize the lines, or raise or24
lower the lines25
c.No personnel may work within 6 feet of a high voltage line before the above26
requirements have been met.27
C.Confined Space Entry Program28
1.Provide and follow approved Confined Space Entry Program in accordance with29
OSHA requirements.30
2.Confined Spaces include:31
a.Manholes32
b.for33
Confined Spaces34
D.Use of Explosives, Drop Weight, Etc.35
1.When Contract Documents permit on the project the following will apply:36
a.Public Notification37
1)Submit notice to City and proof of adequate insurance coverage, 24 hours38
prior to commencing.39
2)Minimum 24 hour public notification in accordance with Section 01 31 1340
E.Water Department Coordination41
1.During the construction of this project, it will be necessary to deactivate, for a42
period of time, existing lines. The Contractor shall be required to coordinate with43
the Water Department to determine the best times for deactivating and activating44
those lines.45
01 35 13 - 3
DAP SPECIAL PROJECT PROCEDURES
Page 3 of 7
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS DEVELOPER AWARDED PROJECTS City Project No. 103761
Revised August, 30, 2013
2.Coordinate any event that will require connecting to or the operation of an existing1
2
a.Coordination shall be in accordance with Section 33 12 25.3
b.If needed, obtain a hydrant water meter from the Water Department for use4
during the life of named project.5
c.In the event that a water valve on an existing live system be turned off and on6
to accommodate the construction of the project is required, coordinate this7
activity through the appropriate City representative.8
1)Do not operate water line valves of existing water system.9
a)Failure to comply will render the Contractor in violation of Texas Penal10
Code Title 7, Chapter 28.03 (Criminal Mischief) and the Contractor11
will be prosecuted to the full extent of the law.12
b)In addition, the Contractor will assume all liabilities and13
responsibilities as a result of these actions.14
F.Public Notification Prior to Beginning Construction15
1.Prior to beginning construction on any block in the project, on a block by block16
basis, prepare and deliver a notice or flyer of the pending construction to the front17
door of each residence or business that will be impacted by construction. The notice18
shall be prepared as follows:19
a.Post notice or flyer 7 days prior to beginning any construction activity on each20
block in the project area.21
1)Prepare flyer on the C include the following22
information:23
a)Name of Project24
b)City Project No (CPN)25
c)Scope of Project (i.e. type of construction activity)26
d)Actual construction duration within the block27
e)Name of phone number28
f)Name phone number29
g)C -hours phone number30
2)-construction notif as Exhibit31
A.32
3)Submit schedule showing the construction start and finish time for each33
block of the project to the inspector.34
4)Deliver flyer to the City Inspector for review prior to distribution.35
b.No construction will be allowed to begin on any block until the flyer is36
delivered to all residents of the block.37
G.Public Notification of Temporary Water Service Interruption during Construction38
1.In the event it becomes necessary to temporarily shut down water service to39
residents or businesses during construction, prepare and deliver a notice or flyer of40
the pending interruption to the front door of each affected resident.41
2.Prepared notice as follows:42
a.The notification or flyer shall be posted 24 hours prior to the temporary43
interruption.44
b.Prepare45
information:46
1)Name of the project47
2)City Project Number48
01 35 13 - 4
DAP SPECIAL PROJECT PROCEDURES
Page 4 of 7
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS DEVELOPER AWARDED PROJECTS City Project No. 103761
Revised August, 30, 2013
3)Date of the interruption of service1
4)Period the interruption will take place2
5)Name of phone number3
6)Name of the Cit4
c.A sample of the temporary water service interruption notification is attached as5
Exhibit B.6
d.Deliver a copy of the temporary interruption notification to the City inspector7
for review prior to being distributed.8
e.No interruption of water service can occur until the flyer has been delivered to9
all affected residents and businesses.10
f.Electronic versions of the sample flyers can be obtained from the Project11
Construction Inspector.12
H.Coordination with United States Army Corps of Engineers (USACE)13
1.At locations in the Project where construction activities occur in areas where14
USACE permits are required, meet all requirements set forth in each designated15
permit.16
I.Coordination within Railroad Permit Areas17
1.At locations in the project where construction activities occur in areas where18
railroad permits are required, meet all requirements set forth in each designated19
railroad permit. This includes, but is not limited to, provisions for:20
a.Flagmen21
b.Inspectors22
c.Safety training23
d.Additional insurance24
e.Insurance certificates25
f.Other employees required to protect the right-of-way and property of the26
Railroad Company from damage arising out of and/or from the construction of27
the project. Proper utility clearance procedures shall be used in accordance28
with the permit guidelines.29
2.Obtain30
requirements.31
J.Dust Control32
1.Use acceptable measures to control dust at the Site.33
a.If water is used to control dust, capture and properly dispose of waste water.34
b.If wet saw cutting is performed, capture and properly dispose of slurry.35
K.Employee Parking36
1.Provide parking for employees at locations approved by the City.37
01 35 13 - 5
DAP SPECIAL PROJECT PROCEDURES
Page 5 of 7
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS DEVELOPER AWARDED PROJECTS City Project No. 103761
Revised August, 30, 2013
1.4 SUBMITTALS [NOT USED]1
1.5 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]2
1.6 CLOSEOUT SUBMITTALS [NOT USED]3
1.7 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]4
1.8 QUALITY ASSURANCE [NOT USED]5
1.9 DELIVERY, STORAGE, AND HANDLING [NOT USED]6
1.10 FIELD [SITE] CONDITIONS [NOT USED]7
1.11 WARRANTY [NOT USED]8
PART 2 -PRODUCTS [NOT USED]9
PART 3 -EXECUTION [NOT USED]10
END OF SECTION11
12
Revision Log
DATE NAME SUMMARY OF CHANGE
8/31/2012 D. Johnson
1.3.B Added requirement of compliance with Health and Safety Code, Title 9.
Safety, Subtitle A. Public Safety, Chapter 752. High Voltage Overhead Lines.
13
01 35 13 - 6
DAP SPECIAL PROJECT PROCEDURES
Page 6 of 7
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS DEVELOPER AWARDED PROJECTS City Project No. 103761
Revised August, 30, 2013
EXHIBIT A1
Letterhead)2
3
4
5
Date:6
7
CPN No.:8
Project Name:9
Mapsco Location:10
Limits of Construction:11
12
13
14
15
16
THIS IS TO INFORM YOU THAT UNDER A CONTRACT WITH THE CITY OF FORT17
WORTH, OUR COMPANY WILL WORK ON UTILITY LINES ON OR AROUND YOUR18
PROPERTY.19
20
CONSTRUCTION WILL BEGIN APPROXIMATELY SEVEN DAYS FROM THE DATE21
OF THIS NOTICE.22
23
IF YOU HAVE QUESTIONS ABOUT ACCESS, SECURITY, SAFETY OR ANY OTHER24
ISSUE, PLEASE CALL:25
26
27
Mr. <> AT <TELEPHONE NO.>28
29
OR30
31
Mr. <CITY INSPECTOR> AT <TELEPHONE NO.>32
33
AFTER 4:30 PM OR ON WEEKENDS, PLEASE CALL (817) 392 830634
35
PLEASE KEEP THIS FLYER HANDY WHEN YOU CALL36
37
01 35 13 - 7
DAP SPECIAL PROJECT PROCEDURES
Page 7 of 7
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS DEVELOPER AWARDED PROJECTS City Project No. 103761
Revised August, 30, 2013
EXHIBIT B1
2
3
4
01 45 23 - 1
DAP Testing and Inspection Services
Page 1 of 2
Public Wtr Improvements to serve Alliance Center North - 8
City Project No. 103761
SECTION 01 45 231
TESTING AND INSPECTION SERVICES2
PART 1 - GENERAL3
1.1 SUMMARY4
A. Section Includes:5
1. Testing and inspection services procedures and coordination6
B. Deviations from this City of Fort Worth Standard Specification7
1. None.8
C. Related Specification Sections include, but are not necessarily limited to:9
1. Division 0 Bidding Requirements, Contract Forms and Conditions of the Contract10
2. Division 1 General Requirements11
1.2 PRICE AND PAYMENT PROCEDURES12
A. Measurement and Payment13
1. Work associated with this Item is considered subsidiary to the various Items bid.14
No separate payment will be allowed for this Item.15
a. Contractor is responsible for performing, coordinating, and payment of all16
Quality Control testing.17
b. City is responsible for performing and payment for first set of Quality18
Assurance testing.19
1) If the first Quality Assurance test performed by the City fails, the20
Contractor is responsible for payment of subsequent Quality Assurance21
testing until a passing test occurs.22
a) Final acceptance will not be issued by City until all required payments23
for testing by Contractor have been paid in full.24
1.3 REFERENCES [NOT USED]25
1.4 ADMINISTRATIVE REQUIREMENTS26
A. Testing27
1. Complete testing in accordance with the Contract Documents.28
2. Coordination29
a. When testing is required to be performed by the City, notify City, sufficiently30
in advance, when testing is needed.31
b. When testing is required to be completed by the Contractor, notify City,32
sufficiently in advance, that testing will be performed.33
3. Distribution of Testing Reports34
a. Electronic Distribution35
1) Confirm development of Project directory for electronic submittals to be36
37
by the City.38
39
40
01 45 23 - 2
DAP Testing and Inspection Services
Page 2 of 2
Public Wtr Improvements to serve Alliance Center North - 8
City Project No. 103761
1)Upload test reports to designated project directory and notify appropriate1
City representatives via email of submittal posting.2
2)Hard Copies3
a)1 copy for all submittals submitted to the Project Representative4
b. Hard Copy Distribution (if required in lieu of electronic distribution)5
1)Tests performed by City6
a)Distribute 1 hard copy to the Contractor7
2)Tests performed by the Contractor8
a)9
4. P10
load of Concrete or Lime material including the following information:11
a. Name of pit12
b. Date of delivery13
c. Material delivered14
B. Inspection15
1. Inspection or lack of inspection does not relieve the Contractor from obligation to16
perform work in accordance with the Contract Documents.17
1.5 SUBMITTALS [NOT USED]18
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]19
1.7 CLOSEOUT SUBMITTALS [NOT USED]20
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]21
1.9 QUALITY ASSURANCE [NOT USED]22
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]23
1.11 FIELD [SITE] CONDITIONS [NOT USED]24
1.12 WARRANTY [NOT USED]25
PART 2 - PRODUCTS [NOT USED]26
PART 3 - EXECUTION [NOT USED]27
END OF SECTION28
29
Revision Log
DATE NAME SUMMARY OF CHANGE
30
01 50 00- 1
DAP Temporary Facilities and Controls
Page 1 of 4
Wtr Improvements to serve Alliance Center North 8
City Project No. 103761
SECTION 01 50 001
TEMPORARY FACILITIES AND CONTROLS2
PART 1 - GENERAL3
1.1 SUMMARY4
A. Section Includes:5
1. Provide temporary facilities and controls needed for the Work including, but not6
necessarily limited to:7
a. Temporary utilities8
b. Sanitary facilities9
c. Storage Sheds and Buildings10
d. Dust control11
e. Temporary fencing of the construction site12
B. Deviations from this City of Fort Worth Standard Specification13
1. None.14
C. Related Specification Sections include, but are not necessarily limited to:15
1. Division 0 Bidding Requirements, Contract Forms and Conditions of the Contract16
2. Division 1 General Requirements17
1.2 PRICE AND PAYMENT PROCEDURES18
A. Measurement and Payment19
1. Work associated with this Item is considered subsidiary to the various Items bid.20
No separate payment will be allowed for this Item.21
1.3 REFERENCES [NOT USED]22
1.4 ADMINISTRATIVE REQUIREMENTS23
A. Temporary Utilities24
1. Obtaining Temporary Service25
a. Make arrangements with utility service companies for temporary services.26
b. Abide by rules and regulations of utility service companies or authorities27
having jurisdiction.28
c. Be responsible for utility service costs until Work is approved for Final29
Acceptance.30
1) Included are fuel, power, light, heat and other utility services necessary for31
execution, completion, testing and initial operation of Work.32
2. Water33
a. Contractor to provide water required for and in connection with Work to be34
performed and for specified tests of piping, equipment, devices or other use as35
required for the completion of the Work.36
b. Provide and maintain adequate supply of potable water for domestic37
consumption by Contractor pe38
c. Coordination39
1) Contact City 1 week before water for construction is desired40
41
01 50 00- 2
DAP Temporary Facilities and Controls
Page 2 of 4
Wtr Improvements to serve Alliance Center North 8
City Project No. 103761
d. Contractor Payment for Construction Water1
1)2
established rates.3
3. Electricity and Lighting4
a. Provide and pay for electric powered service as required for Work, including5
testing of Work.6
Provide power for lighting, operation of equipment, or other use.7
b. Electric power service includes temporary power service or generator to8
maintain operations during scheduled shutdown.9
4. Telephone10
a. Provide emergency telephone service at Site for use by Contractor personnel11
and others performing work or furnishing services at Site.12
5. Temporary Heat and Ventilation13
a. Provide temporary heat as necessary for protection or completion of Work.14
b. Provide temporary heat and ventilation to assure safe working conditions.15
B. Sanitary Facilities16
1. Provide and maintain sanitary facilities for persons on Site.17
a. Comply with regulations of State and local departments of health.18
2. Enforce use of sanitary facilities by construction personnel at job site.19
a. Enclose and anchor sanitary facilities.20
b. No discharge will be allowed from these facilities.21
c. Collect and store sewage and waste so as not to cause nuisance or health22
problem.23
d. Haul sewage and waste off-site at no less than weekly intervals and properly24
dispose in accordance with applicable regulation.25
3. Locate facilities near Work Site and keep clean and maintained throughout Project.26
4. Remove facilities at completion of Project27
C. Storage Sheds and Buildings28
1. Provide adequately ventilated, watertight, weatherproof storage facilities with floor29
above ground level for materials and equipment susceptible to weather damage.30
2. Storage of materials not susceptible to weather damage may be on blocks off31
ground.32
3. Store materials in a neat and orderly manner.33
a. Place materials and equipment to permit easy access for identification,34
inspection and inventory.35
4. Equip building with lockable doors and lighting, and provide electrical service for36
equipment space heaters and heating or ventilation as necessary to provide storage37
environments acceptable to specified manufacturers.38
5. Fill and grade site for temporary structures to provide drainage away from39
temporary and existing buildings.40
6. Remove building from site prior to Final Acceptance.41
D. Temporary Fencing42
1. Provide and maintain for the duration or construction when required in contract43
documents44
01 50 00- 3
DAP Temporary Facilities and Controls
Page 3 of 4
Wtr Improvements to serve Alliance Center North 8
City Project No. 103761
E. Dust Control1
1. Contractor is responsible for maintaining dust control through the duration of the2
project.3
a. Contractor remains on-call at all times4
b. Must respond in a timely manner5
F. Temporary Protection of Construction6
1. Contractor or subcontractors are responsible for protecting Work from damage due7
to weather.8
1.5 SUBMITTALS [NOT USED]9
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]10
1.7 CLOSEOUT SUBMITTALS [NOT USED]11
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]12
1.9 QUALITY ASSURANCE [NOT USED]13
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]14
1.11 FIELD [SITE] CONDITIONS [NOT USED]15
1.12 WARRANTY [NOT USED]16
PART 2 - PRODUCTS [NOT USED]17
PART 3 - EXECUTION [NOT USED]18
3.1 INSTALLERS [NOT USED]19
3.2 EXAMINATION [NOT USED]20
3.3 PREPARATION [NOT USED]21
3.4 INSTALLATION22
A. Temporary Facilities23
1. Maintain all temporary facilities for duration of construction activities as needed.24
3.5 [REPAIR] / [RESTORATION]25
3.6 RE-INSTALLATION26
3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED]27
3.8 SYSTEM STARTUP [NOT USED]28
3.9 ADJUSTING [NOT USED]29
3.10 CLEANING [NOT USED]30
3.11 CLOSEOUT ACTIVITIES31
A. Temporary Facilities32
33
34
35
01 50 00- 4
DAP Temporary Facilities and Controls
Page 4 of 4
Wtr Improvements to serve Alliance Center North 8
City Project No. 103761
1.Remove all temporary facilities and restore area after completion of the Work,1
to a condition equal to or better than prior to start of Work.2
3.12 PROTECTION [NOT USED]3
3.13 MAINTENANCE [NOT USED]4
3.14 ATTACHMENTS [NOT USED]5
END OF SECTION6
7
Revision Log
DATE NAME SUMMARY OF CHANGE
8
01 55 26- 1
DAP Street Use Permit and Modifications to Traffic Control
Page 1 of 3
Public Wtr Improvements to serve Alliance Center North - 8
City Project No. 103761
SECTION 01 55 261
STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL2
PART 1 - GENERAL3
1.1 SUMMARY4
A. Section Includes:5
1. Administrative procedures for:6
a. Street Use Permit7
b. Modification of approved traffic control8
c. Removal of Street Signs9
B. Deviations from this City of Fort Worth Standard Specification10
1. None.11
C. Related Specification Sections include, but are not necessarily limited to:12
1. Division 0 Bidding Requirements, Contract Forms and Conditions of the Contract13
2. Division 1 General Requirements14
3. Section 34 71 13 Traffic Control15
1.2 PRICE AND PAYMENT PROCEDURES16
A. Measurement and Payment17
1. Work associated with this Item is considered subsidiary to the various Items bid.18
No separate payment will be allowed for this Item.19
1.3 REFERENCES20
A. Reference Standards21
1. Reference standards cited in this specification refer to the current reference standard22
published at the time of the latest revision date logged at the end of this23
specification, unless a date is specifically cited.24
2. Texas Manual on Uniform Traffic Control Devices (TMUTCD).25
1.4 ADMINISTRATIVE REQUIREMENTS26
A. Traffic Control27
1. General28
a. When traffic control plans are included in the Drawings, provide Traffic29
Control in accordance with Drawings and Section 34 71 13.30
b. When traffic control plans are not included in the Drawings, prepare traffic31
control plans in accordance with Section 34 71 13 and submit to City for32
review.33
1) Allow minimum 10 working days for review of proposed Traffic Control.34
B. Street Use Permit35
1. Prior to installation of Traffic Control, a City Street Use Permit is required.36
a. To obtain Street Use Permit, submit Traffic Control Plans to City37
Transportation and Public Works Department.38
39
01 55 26- 2
DAP Street Use Permit and Modifications to Traffic Control
Page 2 of 3
Public Wtr Improvements to serve Alliance Center North - 8
City Project No. 103761
1
2
1)Allow a minimum of 5 working days for permit review.3
2)4
Street Use Permit, such that construction is not delayed.5
C. Modification to Approved Traffic Control6
1. Prior to installation traffic control:7
a. Submit revised traffic control plans to City Department Transportation and8
Public Works Department.9
1) Revise Traffic Control plans in accordance with Section 34 71 13.10
2) Allow minimum 5 working days for review of revised Traffic Control.11
3) It is the C12
plans for Street Use Permit, such that construction is not delayed.13
D. Removal of Street Sign14
1. If it is determined that a street sign must be removed for construction, then contact15
City Transportation and Public Works Department, Signs and Markings Division to16
remove the sign.17
E. Temporary Signage18
1. In the case of regulatory signs, replace permanent sign with temporary sign meeting19
requirements of the latest edition of the Texas Manual on Uniform Traffic Control20
Devices (MUTCD).21
2. Install temporary sign before the removal of permanent sign.22
3. When construction is complete, to the extent that the permanent sign can be23
reinstalled, contact the City Transportation and Public Works Department, Signs24
and Markings Division, to reinstall the permanent sign.25
F. Traffic Control Standards26
1.27
1.5 SUBMITTALS [NOT USED]28
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]29
1.7 CLOSEOUT SUBMITTALS [NOT USED]30
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]31
1.9 QUALITY ASSURANCE [NOT USED]32
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]33
1.11 FIELD [SITE] CONDITIONS [NOT USED]34
1.12 WARRANTY [NOT USED]35
PART 2 - PRODUCTS [NOT USED]36
PART 3 - EXECUTION [NOT USED]37
END OF SECTION38
01 55 26- 3
DAP Street Use Permit and Modifications to Traffic Control
Page 3 of 3
Public Wtr Improvements to serve Alliance Center North - 8
City Project No. 103761
1
Revision Log
DATE NAME SUMMARY OF CHANGE
2
01 57 13 - 1
DAP STORM WATER POLLUTION PREVENTION
Page 1 of 3
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS DEVELOPER AWARDED PROJECTS City Project No. 103761
Revised July 1, 2011
SECTION 01 57 131
STORM WATER POLLUTION PREVENTION2
PART 1 -GENERAL3
1.1 SUMMARY4
A.Section Includes:5
1.Procedures for Storm Water Pollution Prevention Plans6
B.Deviations from this City of Fort Worth Standard Specification7
1.None.8
C.Related Specification Sections include, but are not necessarily limited to:9
1.Division 0 Bidding Requirements, Contract Forms and Conditions of the10
Contract11
2.Division 1 General Requirements12
3.Section 31 25 00 Erosion and Sediment Control13
1.2 PRICE AND PAYMENT PROCEDURES14
A.Measurement and Payment15
1.Construction Activities resulting in less than 1 acre of disturbance16
a.Work associated with this Item is considered subsidiary to the various Items17
bid. No separate payment will be allowed for this Item.18
2.Construction Activities resulting in greater than 1 acre of disturbance19
a.Measurement and Payment shall be in accordance with Section 31 25 00.20
1.3 REFERENCES21
A.Abbreviations and Acronyms22
1.Notice of Intent: NOI23
2.Notice of Termination: NOT24
3.Storm Water Pollution Prevention Plan: SWPPP25
4.Texas Commission on Environmental Quality: TCEQ26
5.Notice of Change: NOC27
A.Reference Standards28
1.Reference standards cited in this Specification refer to the current reference29
standard published at the time of the latest revision date logged at the end of this30
Specification, unless a date is specifically cited.31
2.Integrated Storm Management (iSWM) Technical Manual for Construction32
Controls33
1.4 ADMINISTRATIVE REQUIREMENTS34
A.General35
1.Contractor is responsible for resolution and payment of any fines issued associated36
with compliance to Stormwater Pollution Prevention Plan.37
01 57 13 - 2
DAP STORM WATER POLLUTION PREVENTION
Page 2 of 3
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS DEVELOPER AWARDED PROJECTS City Project No. 103761
Revised July 1, 2011
B.Construction Activities resulting in:1
1.Less than 1 acre of disturbance2
a.Provide erosion and sediment control in accordance with Section 31 25 00 and3
Drawings.4
2.1 to less than 5 acres of disturbance5
a.Texas Pollutant Discharge Elimination System (TPDES) General Construction6
Permit is required7
b.Complete SWPPP in accordance with TCEQ requirements8
1)TCEQ Small Construction Site Notice Required under general permit9
TXR15000010
a)Sign and post at job site11
b)Prior to Preconstruction Meeting, send 1 copy to City Department of12
Transportation and Public Works, Environmental Division, (817) 392-13
6088.14
2)Provide erosion and sediment control in accordance with:15
a)Section 31 25 0016
b)The Drawings17
c)TXR150000 General Permit18
d)SWPPP19
e)TCEQ requirements20
3.5 acres or more of Disturbance21
a.Texas Pollutant Discharge Elimination System (TPDES) General Construction22
Permit is required23
b.Complete SWPPP in accordance with TCEQ requirements24
1)Prepare a TCEQ NOI form and submit to TCEQ along with required fee25
a)Sign and post at job site26
b)Send copy to City Department of Transportation and Public Works,27
Environmental Division, (817) 392-6088.28
2)TCEQ Notice of Change required if making changes or updates to NOI29
3)Provide erosion and sediment control in accordance with:30
a)Section 31 25 0031
b)The Drawings32
c)TXR150000 General Permit33
d)SWPPP34
e)TCEQ requirements35
4)Once the project has been completed and all the closeout requirements of36
TCEQ have been met a TCEQ Notice of Termination can be submitted.37
a)Send copy to City Department of Transportation and Public Works,38
Environmental Division, (817) 392-6088.39
1.5 SUBMITTALS40
A.SWPPP41
1.Submit in accordance with Section 01 33 00, except as stated herein.42
a.Prior to the Preconstruction Meeting, submit a draft copy of SWPPP to the City43
as follows:44
1)1 copy to the City Project Manager45
a)City Project Manager will forward to the City Department of46
Transportation and Public Works, Environmental Division for review47
01 57 13 - 3
DAP STORM WATER POLLUTION PREVENTION
Page 3 of 3
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS DEVELOPER AWARDED PROJECTS City Project No. 103761
Revised July 1, 2011
B.Modified SWPPP1
1.If the SWPPP is revised during construction, resubmit modified SWPPP to the City2
in accordance with Section 01 33 00.3
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]4
1.7 CLOSEOUT SUBMITTALS [NOT USED]5
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]6
1.9 QUALITY ASSURANCE [NOT USED]7
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]8
1.11 FIELD [SITE] CONDITIONS [NOT USED]9
1.12 WARRANTY [NOT USED]10
PART 2 -PRODUCTS [NOT USED]11
PART 3 -EXECUTION [NOT USED]12
END OF SECTION13
14
Revision Log
DATE NAME SUMMARY OF CHANGE
15
oi 60 00
PRODUCT REQUIREMENTS
Page 1 of 2
SECTION O1 60 00
PRODUCT REQUIREMENTS
PART1- GENERAL
1.1 SUMMARY
A. Section Includes:
1. References for Product Requirements and City Standard Products List
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Speciiication Sections include, but are not necessarily limited to:
1. Division 0— Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1— General Requirements
1.2 PRICE AND PAYMENT PROCEDURES [NOT USED]
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. A list of City approved products for use is available through the City's website at:
https://apps.fortworthtexas.gov/ProjectResources/ and following the directory path;
02 - Construction Documents/Standard Products List
B. Only products specifically included on City's Standard Product List in these Contract
Documents shall be allowed for use on the Project.
1. Any subsequently approved products will only be allowed for use upon specific
approval by the City.
C. Any specific product requirements in the Contract Documents supersede similar
products included on the City's Standard Product List.
1. The City reserves the right to not allow products to be used for certain projects even
though the product is listed on the City's Standard Product List.
D. Although a specific product is included on City's Standard Product List, not all
products from that manufacturer are approved for use, including but not limited to, that
manufacturer's standard product.
E. See Section O1 33 00 for submittal requirements of Product Data included on City's
Standard Product List.
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No. 103761
Revised March 9, 2020
oi 60 00
PRODUCT REQUIREMENTS
Page 2 of 2
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
10/12/12 D. Johnson Modified Location of Ciry's Standard Product List
3/9/2020 D.V. Magana Removed reference to Buzzsaw and noted that the City approved products list is
accessible through the City's website.
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CONSTRUCTION SPECIFICATION DOCUMENT City Project No. 103761
Revised March 9, 2020
01 66 00- 1
DAP PROJECT RECORD DOCUMENTS
Page 1 of 4
Public Wtr Improvements to serve Alliance Center North - 8
City Project No. 103761
SECTION 01 66 001
PRODUCT STORAGE AND HANDLING REQUIREMENTS2
PART 1 - GENERAL3
1.1 SUMMARY4
A. Section Includes:5
1. Scheduling of product delivery6
2. Packaging of products for delivery7
3. Protection of products against damage from:8
a. Handling9
b. Exposure to elements or harsh environments10
B. Deviations from this City of Fort Worth Standard Specification11
1. None.12
C. Related Specification Sections include, but are not necessarily limited to:13
1. Division 0 Bidding Requirements, Contract Forms and Conditions of the Contract14
2. Division 1 General Requirements15
1.2 PRICE AND PAYMENT PROCEDURES16
A. Measurement and Payment17
1. Work associated with this Item is considered subsidiary to the various Items bid.18
No separate payment will be allowed for this Item.19
1.3 REFERENCES [NOT USED]20
1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED]21
1.5 SUBMITTALS [NOT USED]22
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]23
1.7 CLOSEOUT SUBMITTALS [NOT USED]24
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]25
1.9 QUALITY ASSURANCE [NOT USED]26
1.10 DELIVERY AND HANDLING27
A. Delivery Requirements28
1. Schedule delivery of products or equipment as required to allow timely installation29
and to avoid prolonged storage.30
2. Provide appropriate personnel and equipment to receive deliveries.31
3. Delivery trucks will not be permitted to wait extended periods of time on the Site32
for personnel or equipment to receive the delivery.33
34
35
36
01 66 00- 2
DAP PROJECT RECORD DOCUMENTS
Page 2 of 4
Public Wtr Improvements to serve Alliance Center North - 8
City Project No. 103761
4. Deliver products or equipment in manufacturer's original unbroken cartons or other1
containers designed and constructed to protect the contents from physical or2
environmental damage.3
5. Clearly and fully mark and identify as to manufacturer, item and installation4
location.5
6. Provide manufacturer's instructions for storage and handling.6
B. Handling Requirements7
1. Handle products or equipment in accordance with these Contract Documents and8
ns and instructions.9
C. Storage Requirements10
1.11
requirements of these Specifications.12
2. Make necessary provisions for safe storage of materials and equipment.13
a. Place loose soil materials and materials to be incorporated into Work to prevent14
damage to any part of Work or existing facilities and to maintain free access at15
all times to all parts of Work and to utility service company installations in16
vicinity of Work.17
3. Keep materials and equipment neatly and compactly stored in locations that will18
cause minimum inconvenience to other contractors, public travel, adjoining owners,19
tenants and occupants.20
a. Arrange storage to provide easy access for inspection.21
4. Restrict storage to areas available on construction site for storage of material and22
23
5. Provide off-site storage and protection when on-site storage is not adequate.24
a. Provide addresses of and access to off-site storage locations for inspection by25
26
6. Do not use lawns, grass plots or other private property for storage purposes without27
written permission of owner or other person in possession or control of premises.28
7.29
8. Neatly, safely and compactly stack materials delivered and stored along line of30
Work to avoid inconvenience and damage to property owners and general public31
and maintain at least 3 feet from fire hydrant.32
9. Keep public and private driveways and street crossings open.33
10. Repair or replace damaged lawns, sidewalks, streets or other improvements to34
35
a. Total length which materials may be distributed along route of construction at36
37
Project Representative.38
01 66 00- 3
DAP PROJECT RECORD DOCUMENTS
Page 3 of 4
Public Wtr Improvements to serve Alliance Center North - 8
City Project No. 103761
1.11 FIELD [SITE] CONDITIONS [NOT USED]1
1.12 WARRANTY [NOT USED]2
PART 2 - PRODUCTS [NOT USED]3
PART 3 - EXECUTION4
3.1 INSTALLERS [NOT USED]5
3.2 EXAMINATION [NOT USED]6
3.3 PREPARATION [NOT USED]7
3.4 ERECTION [NOT USED]8
3.5 REPAIR / RESTORATION [NOT USED]9
3.6 RE-INSTALLATION [NOT USED]10
3.7 FIELD [OR] SITE QUALITY CONTROL11
A. Tests and Inspections12
1. Inspect all products or equipment delivered to the site prior to unloading.13
B. Non-Conforming Work14
1. Reject all products or equipment that are damaged, used or in any other way15
unsatisfactory for use on the project.16
3.8 SYSTEM STARTUP [NOT USED]17
3.9 ADJUSTING [NOT USED]18
3.10 CLEANING [NOT USED]19
3.11 CLOSEOUT ACTIVITIES [NOT USED]20
3.12 PROTECTION21
A. Protect all products or equipment in accordance with manufacturer's written directions.22
B. Store products or equipment in location to avoid physical damage to items while in23
storage.24
C. Protect equipment from exposure to elements and keep thoroughly dry if required by25
the manufacturer.26
3.13 MAINTENANCE [NOT USED]27
3.14 ATTACHMENTS [NOT USED]28
END OF SECTION29
30
31
32
01 66 00- 4
DAP PROJECT RECORD DOCUMENTS
Page 4 of 4
Public Wtr Improvements to serve Alliance Center North - 8
City Project No. 103761
1
Revision Log
DATE NAME SUMMARY OF CHANGE
4/7/2014 M.Domenech Revised for DAP application
2
01 70 00 - 1
MOBILIZATION AND REMOBILIZATION
Page 1 of 6
CITY OF FORT WORTH Public Water Improvements to serve Alliance Center North - 8
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No. 103761
Revised November 22, 2016
SECTION 01 70 001
MOBILIZATION AND REMOBILIZATION2
[Text in Blue is for information or guidance. Remove all blue text in the final project document.]3
PART 1 -GENERAL4
1.1 SUMMARY5
A.Section Includes:6
1.Mobilization and Demobilization7
a.Mobilization8
1)9
to the Site10
2)11
at the Site12
3)Premiums paid for performance and payment bonds13
4)14
to another location within the designated Site15
5)Relocation16
from 1 location to another location on the Site.17
b.Demobilization18
1)19
away from the Site including disassembly20
2)Site Clean-up21
3)Removal of all buildings and/or other facilities assembled at the Site for this22
Contract23
c.Mobilization and Demobilization do not include activities for specific items of24
work that are for which payment is provided elsewhere in the contract.25
2.Remobilization26
a.Remobilization for Suspension of Work specifically required in the Contract27
Documents or as required by City includes:28
1)Demobilization29
a)30
supplies from the Site including disassembly or temporarily securing31
equipment, supplies, and other facilities as designated by the Contract32
Documents necessary to suspend the Work.33
b)Site Clean-up as designated in the Contract Documents34
2)Remobilization35
a)36
supplies to the Site necessary to resume the Work.37
b)Establishm38
operation at the Site necessary to resume the Work.39
3)No Payments will be made for:40
a)Mobilization and Demobilization from one location to another on the41
Site in the normal progress of performing the Work.42
b)Stand-by or idle time43
c)Lost profits44
01 70 00 - 2
MOBILIZATION AND REMOBILIZATION
Page 2 of 6
CITY OF FORT WORTH Public Water Improvements to serve Alliance Center North - 8
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No. 103761
Revised November 22, 2016
3.Mobilizations and Demobilization for Miscellaneous Projects1
a.Mobilization and Demobilization2
1)Mobilization shall consist of the activities and cost on a Work Order basis3
necessary for:4
a)onnel, equipment, and operating5
supplies to the Site for the issued Work Order.6
b)7
operation at the Site for the issued Work Order8
2)Demobilization shall consist of the activities and cost necessary for:9
a)10
supplies from the Site including disassembly for each issued Work11
Order12
b)Site Clean-up for each issued Work Order13
c)Removal of all buildings or other facilities assembled at the Site for14
each Work Oder15
b.Mobilization and Demobilization do not include activities for specific items of16
work for which payment is provided elsewhere in the contract.17
4.Emergency Mobilizations and Demobilization for Miscellaneous Projects18
a.A Mobilization for Miscellaneous Projects when directed by the City and the19
mobilization occurs within 24 hours of the issuance of the Work Order.20
B.Deviations from this City of Fort Worth Standard Specification21
1.None.22
C.Related Specification Sections include, but are not necessarily limited to:23
1.Division 0 Bidding Requirements, Contract Forms and Conditions of the Contract24
2.Division 1 General Requirements25
1.2 PRICE AND PAYMENT PROCEDURES26
A.Measurement and Payment [Consult City Department/Division for direction on if27
Mobilization pay item to be included or the item should be subsidiary. Include the28
appropriate Section 1.2 A. 1.]29
1.Mobilization and Demobilization [If subsidiary]30
a.Measure31
1)This Item is considered subsidiary to the various Items bid.32
b.Payment33
1)The work performed and materials furnished in accordance with this Item34
are subsidiary to the various Items bid and no other compensation will be35
allowed.36
[OR]37
1.Mobilization and Demobilization [If bid item included for Mobilization38
Consultant to provide a maximum % of adjusted contract amount based on the39
anticipated mobilization costs to limit the amount bid for this item]40
a.Measure41
1)This Item will be measured by the lump sum or each as the work42
progresses. Mobilization is calculated on the base bid only and will not be43
paid for separately on any additive alternate items added to the Contract.44
2)Demobilization shall be considered subsidiary to the various bid items.45
b.Payment46
01 70 00 - 3
MOBILIZATION AND REMOBILIZATION
Page 3 of 6
CITY OF FORT WORTH Public Water Improvements to serve Alliance Center North - 8
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No. 103761
Revised November 22, 2016
1)For this Item, the adjusted Contract amount will be calculated as the total1
Contract amount less the lump sum for mobilization. Mobilization shall be2
made in partial payments as follows:3
a) When 1% of the adjusted Contract amount for construction Items is4
earned, 50% of the mobilization lump sum bid or [Insert ½ the maximum5
allowed] % of the total Contract amount, whichever is less, will be paid.6
b) When 5% of the adjusted Contract amount for construction Items is7
earned, 75% of the mobilization lump sum bid or [Insert the maximum8
allowed]% of the total Contract amount, whichever is less, will be paid.9
Previous payments under the Item will be deducted from this amount.10
c) When 10% of the adjusted Contract amount for construction Items is11
earned, 100% of the mobilization lump sum bid or [Insert the maximum12
allowed]% of the total Contract amount, whichever is less, will be paid.13
Previous payments under the Item will be deducted from this amount.14
d)[Insert15
maximum allowed]% of total contract shall be considered unbalanced16
and a cause for consideration of rejection.17
e) The Lump Sum bid18
include any cost or sum for mobilization items associated with19
water/sewer items. Those costs shall be included in the various20
water/sewer bid Items. Otherwise the bid Items shall be considered21
unbalanced and a cause for consideration of rejection.22
f) The Lump Sum bid23
any cost or sum for mobilization items associated with drainage items.24
Drainag25
Sum bid Item. Otherwise the bid Items shall be considered unbalanced26
and a cause for consideration of rejection.27
g) The Lump Sum bid28
include any cost or sum for mobilization items associated with paving29
item30
Lump Sum bid Item. Otherwise the bid Items shall be considered31
unbalanced and a cause for consideration of rejection.32
2)The work performed and materials furnished for demobilization in33
accordance with this Item are subsidiary to the various Items bid and no other34
compensation will be allowed.35
[OR]36
1.Mobilization and Demobilization [If are used37
due to different funding (ex. Water and Sewer and Paving and/or Drainage)38
Provide detail of each bid item - Consultant to provide detail for each bid item39
(typically Water/Sewer will be subsidiary and Paving/Drainage will be LS, with40
possibly separate bid items for Paving and Drainage due to funding).]41
a.Measure42
1)This item for Water/Sewer improvements is considered subsidiary to the43
various Items bid.44
2) Paving Drainage, and/or Mobilization45
will be measured by the lump sum or each as the work46
progresses. Mobilization is calculated on the base bid only and will not be47
paid for separately on any additive alternate items added to the Contract.48
3)Demobilization shall be considered subsidiary to the various bid items.49
b.Payment50
01 70 00 - 4
MOBILIZATION AND REMOBILIZATION
Page 4 of 6
CITY OF FORT WORTH Public Water Improvements to serve Alliance Center North - 8
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No. 103761
Revised November 22, 2016
1)The work performed and materials furnished in accordance with this Item1
for Water/Sewer improvements are subsidiary to the various Items bid and no2
other compensation will be allowed.3
2) Paving4
, the adjusted Contract amount will be calculated as the5
total Contract amount for paving, drainage or paving/drainage improvements6
less the lump sum for mobilization. Mobilization shall be made in partial7
payments as follows:8
a) When 1% of the adjusted Contract amount for construction Items is9
earned, 50% of the mobilization lump sum bid or [Insert ½ the maximum10
allowed] % of the total paving, drainage, or paving/drainage Contract11
amount, whichever is less, will be paid.12
b) When 5% of the adjusted Contract amount for construction Items is13
earned, 75% of the mobilization lump sum bid or [Insert the maximum14
allowed]% of the total paving, drainage, or paving/drainage Contract15
amount, whichever is less, will be paid. Previous payments under the Item16
will be deducted from this amount.17
c) When 10% of the adjusted Contract amount for construction Items is18
earned, 100% of the mobilization lump sum bid or [Insert the maximum19
allowed]% of the total paving, drainage, or paving/drainage Contract20
amount, whichever is less, will be paid. Previous payments under the Item21
will be deducted from this amount.22
d)[Insert23
maximum allowed]% of total paving, drainage or paving/drainage24
contract shall be considered unbalanced and a cause for consideration25
of rejection.26
3)The work performed and materials furnished for demobilization in27
accordance with this Item are subsidiary to the various Items bid and no other28
compensation will be allowed.29
2.Remobilization for suspension of Work as specifically required in the Contract30
Documents31
a.Measurement32
1)Measurement for this Item shall be per each remobilization performed.33
b.Payment34
1)The work performed and materials furnished in accordance with this Item35
will be paid for at the unit36
37
Documents.38
c.The price shall include:39
1)Demobilization as described in Section 1.1.A.2.a.1)40
2)Remobilization as described in Section 1.1.A.2.a.2)41
d.No payments will be made for standby, idle time, or lost profits associated this42
Item.43
3.Remobilization for suspension of Work as required by City44
a.Measurement and Payment45
1)This shall be submitted as a Contract Claim in accordance with Article 1046
of Section 00 72 00.47
2)No payments will be made for standby, idle time, or lost profits associated48
with this Item.49
01 70 00 - 5
MOBILIZATION AND REMOBILIZATION
Page 5 of 6
CITY OF FORT WORTH Public Water Improvements to serve Alliance Center North - 8
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No. 103761
Revised November 22, 2016
4.Mobilizations and Demobilizations for Miscellaneous Projects1
a.Measurement2
1)Measurement for this Item shall be for each Mobilization and3
Demobilization required by the Contract Documents4
b.Payment5
1)The Work performed and materials furnished in accordance with this Item6
will be paid for at the unit7
Work Order Mobilization8
Documents. Demobilization shall be considered subsidiary to mobilization9
and shall not be paid for separately.10
c.The price shall include:11
1)Mobilization as described in Section 1.1.A.3.a.1)12
2)Demobilization as described in Section 1.1.A.3.a.2)13
d.No payments will be made for standby, idle time, or lost profits associated this14
Item.15
5.Emergency Mobilizations and Demobilizations for Miscellaneous Projects16
a.Measurement17
1)Measurement for this Item shall be for each Mobilization and18
Demobilization required by the Contract Documents19
b.Payment20
1)The Work performed and materials furnished in accordance with this Item21
will be paid for at the unit22
price per each Work Order Emergency Mobilization23
Contract Documents. Demobilization shall be considered subsidiary to24
mobilization and shall not be paid for separately.25
c.The price shall include26
1)Mobilization as described in Section 1.1.A.4.a)27
2)Demobilization as described in Section 1.1.A.3.a.2)28
d.No payments will be made for standby, idle time, or lost profits associated this29
Item.30
1.3 REFERENCES [NOT USED]31
1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED]32
1.5 SUBMITTALS [NOT USED]33
1.6 INFORMATIONAL SUBMITTALS [NOT USED]34
1.7 CLOSEOUT SUBMITTALS [NOT USED]35
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]36
1.9 QUALITY ASSURANCE [NOT USED]37
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]38
1.11 FIELD [SITE] CONDITIONS [NOT USED]39
1.12 WARRANTY [NOT USED]40
01 70 00 - 6
MOBILIZATION AND REMOBILIZATION
Page 6 of 6
CITY OF FORT WORTH Public Water Improvements to serve Alliance Center North - 8
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No. 103761
Revised November 22, 2016
PART 2 -PRODUCTS [NOT USED]1
PART 3 -EXECUTION [NOT USED]2
END OF SECTION3
4
Revision Log
DATE NAME SUMMARY OF CHANGE
11/22/16 Michael Owen 1.2 Price and Payment Procedures - Revised specification, including blue text, to
make specification flexible for either subsidiary or paid bid item for Mobilization.
5
01 71 23 - 1
CONSTRUCTION STAKING AND SURVEY
Page 1 of 8
CITY OF FORT WORTH Public Water Improvements to serve Alliance Center North - 8
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS DEVELOPER AWARDED PROJECTS City Project No. 103761
Revised February 14, 2018
SECTION 01 71 231
CONSTRUCTION STAKING AND SURVEY2
PART 1 -GENERAL3
1.1 SUMMARY4
A.Section Includes:5
1. Requirements for construction staking and construction survey6
B.Deviations from this City of Fort Worth Standard Specification7
1. See Changes (Highlighted in Yellow).8
C.Related Specification Sections include, but are not necessarily limited to:9
1.Division 0 Bidding Requirements, Contract Forms and Conditions of the Contract10
2.Division 1 General Requirements11
1.2 PRICE AND PAYMENT PROCEDURES12
A.Measurement and Payment13
1.Construction Staking14
a.Measurement15
1)This Item is considered subsidiary to the various Items bid.16
b.Payment17
1)The work performed and the materials furnished in accordance with this18
Item are subsidiary to the various Items bid and no other compensation will19
be allowed.20
2.Construction Survey21
a.Measurement22
1)This Item is considered subsidiary to the various Items bid.23
b.Payment24
1)The work performed and the materials furnished in accordance with this25
Item are subsidiary to the various Items bid and no other compensation will be26
allowed.27
3.As-Built Survey28
a.Measurement29
1)This Item is considered subsidiary to the various Items bid.30
b.Payment31
1)The work performed and the materials furnished in accordance with this32
Item are subsidiary to the various Items bid and no other compensation will be33
allowed.34
35
36
37
38
39
40
01 71 23 - 2
CONSTRUCTION STAKING AND SURVEY
Page 2 of 8
CITY OF FORT WORTH Public Water Improvements to serve Alliance Center North - 8
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS DEVELOPER AWARDED PROJECTS City Project No. 103761
Revised February 14, 2018
1.3 REFERENCES1
A.Definitions2
1.Construction Survey - The survey measurements made prior to or while3
construction is in progress to control elevation, horizontal position, dimensions and4
configuration of structures/improvements included in the Project Drawings.5
2.As-built Survey The measurements made after the construction of the6
improvement features are complete to provide position coordinates for the features7
of a project.8
3.Construction Staking The placement of stakes and markings to provide offsets9
and elevations to cut and fill in order to locate on the ground the designed10
structures/improvements included in the Project Drawings. Construction staking11
shall include staking easements and/or right of way if indicated on the plans.12
4. Measurements made after construction staking is13
completed and before construction work begins to ensure that structures marked on14
the ground are accurately located per Project Drawings.15
B.Technical References16
1.City of Fort Worth17
website) 01 71 23.16.01_ Attachment A_Survey Staking Standards18
2.City of Fort Worth - Standard Survey Data Collector Library (fxl) files (available19
w website).20
3.Texas Department of Transportation (TxDOT) Survey Manual, latest revision21
4.Texas Society of Professional Land Surveyors (TSPS), Manual of Practice for Land22
Surveying in the State of Texas, Category 523
24
1.4 ADMINISTRATIVE REQUIREMENTS25
A.s selection of a surveyor must comply with Texas Government26
Code 2254 (qualifications based selection) for this project.27
1.5 SUBMITTALS28
A.Submittals, if required, shall be in accordance with Section 01 33 00.29
B.All submittals shall be received and reviewed by the City prior to delivery of work.30
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS31
A.Field Quality Control Submittals32
1. Documentation verifying accuracy of field engineering work, including coordinate33
conversions if plans do not indicate grid or ground coordinates.34
2.-35
(refer to 01 71 23.16.01 Attachment A Survey Staking Standards).36
37
1.7 CLOSEOUT SUBMITTALS38
B. As-built Redline Drawing Submittal39
01 71 23 - 3
CONSTRUCTION STAKING AND SURVEY
Page 3 of 8
CITY OF FORT WORTH Public Water Improvements to serve Alliance Center North - 8
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS DEVELOPER AWARDED PROJECTS City Project No. 103761
Revised February 14, 2018
1.Submit As-Built Survey Redline Drawings documenting the locations/elevations of1
constructed improvements signed and sealed by Registered Professional Land2
Surveyor (RPLS) responsible for the work (refer to 01 71 23.16.01 Attachment A3
Survey Staking Standards) .4
2.Contractor shall submit the proposed as-built and completed redline drawing5
submittal one (1) week prior to scheduling the project final inspection for City6
review and comment. Revisions, if necessary, shall be made to the as-built redline7
drawings and resubmitted to the City prior to scheduling the construction final8
inspection.9
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]10
1.9 QUALITY ASSURANCE11
A.Construction Staking12
1.Construction staking will be performed by the Contractor.13
2.Coordination14
a.Contact Project Representative at least one week in15
advance notifying the City of when Construction Staking is scheduled.16
b.17
construction activities are not delayed or negatively impacted.18
3.General19
a.Contractor is responsible for preserving and maintaining stakes. If City20
are required to re-stake for21
any reason, the Contractor will be responsible for costs to perform staking. If22
in the opinion of the City, a sufficient number of stakes or markings have been23
lost, destroyed disturbed or omitted that the contracted Work cannot take place24
then the Contractor will be required to stake or re-stake the deficient areas.25
B.Construction Survey26
1.Construction Survey will be performed by the Contractor.27
2.Coordination28
a.Contractor to verify that horizontal and vertical control data established in the29
design survey and required for construction survey is available and in place.30
3.General31
a.Construction survey will be performed in order to construct the work shown32
on the Construction Drawings and specified in the Contract Documents.33
b.For construction methods other than open cut, the Contractor shall perform34
construction survey and verify control data including, but not limited to, the35
following:36
1)Verification that established benchmarks and control are accurate.37
2)Use of Benchmarks to furnish and maintain all reference lines and grades38
for tunneling.39
3)Use of line and grades to establish the location of the pipe.40
4)Submit to the City copies of field notes used to establish all lines and41
grades, if requested, and allow the City to check guidance system setup prior42
to beginning each tunneling drive.43
5)Provide access for the City, if requested, to verify the guidance system and44
the line and grade of the carrier pipe.45
01 71 23 - 4
CONSTRUCTION STAKING AND SURVEY
Page 4 of 8
CITY OF FORT WORTH Public Water Improvements to serve Alliance Center North - 8
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS DEVELOPER AWARDED PROJECTS City Project No. 103761
Revised February 14, 2018
6)The Contractor remains fully responsible for the accuracy of the work and1
correction of it, as required.2
7)Monitor line and grade continuously during construction.3
8)Record deviation with respect to design line and grade once at each pipe4
joint and submit daily records to the City.5
9)If the installation does not meet the specified tolerances (as outlined in6
Sections 33 05 23 and/or 33 05 24), immediately notify the City and correct7
the installation in accordance with the Contract Documents.8
C. As-Built Survey9
1.Required As-Built Survey will be performed by the Contractor.10
2.Coordination11
a.Contractor is to coordinate with City to confirm which features require as-12
built surveying.13
b.It is the Contractor as-built survey and14
required measurements for items that are to be buried such that construction15
activities are not delayed or negatively impacted.16
c.and under in diameter, it is acceptable17
to physically measure depth and mark the location during the progress of18
construction and take as-built survey after the facility has been buried. The19
Contractor is responsible for the quality control needed to ensure accuracy.20
3.General21
a.The Contractor shall provide as-built survey including the elevation and22
location (and provide written documentation to the City) of construction23
features during the progress of the construction including the following:24
1)Water Lines25
a)Top of pipe elevations and coordinates for waterlines at the following26
locations:27
(1)Minimum every 250 linear feet, including28
(2)Horizontal and vertical points of inflection, curvature,29
etc.30
(3)Fire line tee31
(4)Plugs, stub-outs, dead-end lines32
(5)Casing pipe (each end) and all buried fittings33
2)Sanitary Sewer34
a)Top of pipe elevations and coordinates for force mains and siphon35
sanitary sewer lines (non-gravity facilities) at the following locations:36
(1)Minimum every 250 linear feet and any buried fittings37
(2)Horizontal and vertical points of inflection, curvature,38
etc.39
3)Stormwater Not Applicable40
b.The Contractor shall provide as-built survey including the elevation and41
location (and provide written documentation to the City) of construction42
features after the construction is completed including the following:43
1)Manholes44
a)Rim and flowline elevations and coordinates for each manhole45
2)Water Lines46
a)Cathodic protection test stations47
b)Sampling stations48
c)Meter boxes/vaults (All sizes)49
01 71 23 - 5
CONSTRUCTION STAKING AND SURVEY
Page 5 of 8
CITY OF FORT WORTH Public Water Improvements to serve Alliance Center North - 8
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS DEVELOPER AWARDED PROJECTS City Project No. 103761
Revised February 14, 2018
d)Fire hydrants1
e)Valves (gate, butterfly, etc.)2
f)Air Release valves (Manhole rim and vent pipe)3
g)Blow off valves (Manhole rim and valve lid)4
h)Pressure plane valves5
i)Underground Vaults6
(1)Rim and flowline elevations and coordinates for each7
Underground Vault.8
3)Sanitary Sewer9
a)Cleanouts10
(1)Rim and flowline elevations and coordinates for each11
b)Manholes and Junction Structures12
(1)Rim and flowline elevations and coordinates for each13
manhole and junction structure.14
4)Stormwater Not Applicable15
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]16
1.11 FIELD [SITE] CONDITIONS [NOT USED]17
1.12 WARRANTY18
PART 2 -PRODUCTS19
A.A construction survey will produce, but will not be limited to:20
1.Recovery of relevant control points, points of curvature and points of intersection.21
2.Establish temporary horizontal and vertical control elevations (benchmarks)22
sufficiently permanent and located in a manner to be used throughout construction.23
3.The location of planned facilities, easements and improvements.24
a.Establishing final line and grade stakes for piers, floors, grade beams, parking25
areas, utilities, streets, highways, tunnels, and other construction.26
b.A record of revisions or corrections noted in an orderly manner for reference.27
c.A drawing, when required by the client, indicating the horizontal and vertical28
location of facilities, easements and improvements, as built.29
4.Cut sheets shall be provided to the City inspector and Survey Superintendent for all30
construction staking projects. These cut sheets shall be on the standard city template31
which can be obtained from the Survey Superintendent (817-392-7925).32
5.Digital survey files in the following formats shall be acceptable:33
a. AutoCAD (.dwg)34
b.ESRI Shapefile (.shp)35
c.CSV file (.csv), formatted with X and Y coordinates in separate columns (use36
standard templates, if available)37
6. Survey files shall include vertical and horizontal data tied to original project38
control and benchmarks, and shall include feature descriptions39
PART 3 -EXECUTION40
3.1 INSTALLERS41
01 71 23 - 6
CONSTRUCTION STAKING AND SURVEY
Page 6 of 8
CITY OF FORT WORTH Public Water Improvements to serve Alliance Center North - 8
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS DEVELOPER AWARDED PROJECTS City Project No. 103761
Revised February 14, 2018
A.Tolerances:1
1.The staked location of any improvement or facility should be as accurate as2
practical and necessary. The degree of precision required is dependent on many3
factors all of which must remain judgmental. The tolerances listed hereafter are4
based on generalities and, under certain circumstances, shall yield to specific5
requirements. The surveyor shall assess any situation by review of the overall plans6
and through consultation with responsible parties as to the need for specific7
tolerances.8
a.Earthwork: Grades for earthwork or rough cut should not exceed 0.1 ft. vertical9
tolerance. Horizontal alignment for earthwork and rough cut should not exceed10
1.0 ft. tolerance.11
b.Horizontal alignment on a structure shall be within .0.1ft tolerance.12
c.Paving or concrete for streets, curbs, gutters, parking areas, drives, alleys and13
walkways shall be located within the confines of the site boundaries and,14
occasionally, along a boundary or any other restrictive line. Away from any15
restrictive line, these facilities should be staked with an accuracy producing no16
more than 0.05ft. tolerance from their specified locations.17
d.Underground and overhead utilities, such as sewers, gas, water, telephone and18
electric lines, shall be located horizontally within their prescribed areas or19
easements. Within assigned areas, these utilities should be staked with an20
accuracy producing no more than 0.1 ft tolerance from a specified location.21
e.The accuracy required for the vertical location of utilities varies widely. Many22
underground utilities require only a minimum cover and a tolerance of 0.1 ft.23
should be maintained. Underground and overhead utilities on planned profile,24
but not depending on gravity flow for performance, should not exceed 0.1 ft.25
tolerance.26
B.Surveying instruments shall be kept in close adjustment according t27
specifications or in compliance to standards. The City reserves the right to request a28
calibration report at any time and recommends regular maintenance schedule be29
performed by a certified technician every 6 months.30
1.Field measurements of angles and distances shall be done in such fashion as to31
satisfy the closures and tolerances expressed in Part 3.1.A.32
2.Vertical locations shall be established from a pre-established benchmark and33
checked by closing to a different bench mark on the same datum.34
3.35
or conflicts found shall be reported promptly to the City.36
4.Revisions, corrections and other pertinent data shall be logged for future reference.37
38
3.2 EXAMINATION [NOT USED]39
3.3 PREPARATION [NOT USED]40
3.4 APPLICATION41
3.5 REPAIR / RESTORATION42
A.43
monuments/points set by the City , the monuments44
shall be adequately referenced for expedient restoration.45
01 71 23 - 7
CONSTRUCTION STAKING AND SURVEY
Page 7 of 8
CITY OF FORT WORTH Public Water Improvements to serve Alliance Center North - 8
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS DEVELOPER AWARDED PROJECTS City Project No. 103761
Revised February 14, 2018
1.Notify City if any control data needs to be1
restored or replaced due to damage caused during construction operations.2
a.Contractor shall perform replacements and/or restorations.3
b.The City or Develo may require at any time a4
5
by the City before further6
associated work can move forward.7
3.6 RE-INSTALLATION [NOT USED]8
3.7 FIELD [OR] SITE QUALITY CONTROL9
A.10
City in accordance with this Specification. This11
includes easements and right of way, if noted on the plans.12
B.Do not change or relocate stakes or control data without approval from the City.13
3.8 SYSTEM STARTUP14
A.Survey Checks15
1.The City reserves the right to perform a Survey Check at any time deemed16
necessary.17
2.Checks by City personnel or 3rd party contracted surveyor are not intended to18
relieve the contractor of his/her responsibility for accuracy.19
20
3.9 ADJUSTING [NOT USED]21
3.10 CLEANING [NOT USED]22
3.11 CLOSEOUT ACTIVITIES [NOT USED]23
3.12 PROTECTION [NOT USED]24
3.13 MAINTENANCE [NOT USED]25
3.14 ATTACHMENTS [NOT USED]26
END OF SECTION27
28
Revision Log
DATE NAME SUMMARY OF CHANGE
8/31/2012 D. Johnson
8/31/2017 M. Owen
Added instruction and modified measurement & payment under 1.2; added
definitions and references under 1.3; modified 1.6; added 1.7 closeout submittal
requirements; modified 1.9 Quality Assurance; added PART 2 PRODUCTS ;
Added 3.1 Installers; added 3.5 Repair/Restoration; and added 3.8 System Startup.
2/14/2018 M Owen Staking and As-Built Survey; added reference to selection compliance with TGC
2254; revised action and Closeout submittal requirements; added acceptable depth
01 71 23 - 8
CONSTRUCTION STAKING AND SURVEY
Page 8 of 8
CITY OF FORT WORTH Public Water Improvements to serve Alliance Center North - 8
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS DEVELOPER AWARDED PROJECTS City Project No. 103761
Revised February 14, 2018
measurement criteria; revised list of items requiring as-
; and revised acceptable digital survey file format
1
01 74 23 - 1
DAP CLEANING
Page 1 of 4
Public Wtr Improvements to serve Alliance Center North -8
City Project No. 103761
SECTION 01 74 231
CLEANING2
PART 1 - GENERAL3
1.1 SUMMARY4
A. Section Includes:5
1. Intermediate and final cleaning for Work not including special cleaning of closed6
systems specified elsewhere7
B. Deviations from this City of Fort Worth Standard Specification8
1. None.9
C. Related Specification Sections include, but are not necessarily limited to:10
1. Division 0 Bidding Requirements, Contract Forms and Conditions of the Contract11
2. Division 1 General Requirements12
3. Section 32 92 13 Hydro-Mulching, Seeding and Sodding13
1.2 PRICE AND PAYMENT PROCEDURES14
A. Measurement and Payment15
1. Work associated with this Item is considered subsidiary to the various Items bid.16
No separate payment will be allowed for this Item.17
1.3 REFERENCES [NOT USED]18
1.4 ADMINISTRATIVE REQUIREMENTS19
A. Scheduling20
1. Schedule cleaning operations so that dust and other contaminants disturbed by21
cleaning process will not fall on newly painted surfaces.22
2. Schedule final cleaning upon completion of Work and immediately prior to final23
inspection.24
1.5 SUBMITTALS [NOT USED]25
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]26
1.7 CLOSEOUT SUBMITTALS [NOT USED]27
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]28
1.9 QUALITY ASSURANCE [NOT USED]29
1.10 STORAGE, AND HANDLING30
A. Storage and Handling Requirements31
1. Store cleaning products and cleaning wastes in containers specifically designed for32
those materials.33
01 74 23 - 2
DAP CLEANING
Page 2 of 4
Public Wtr Improvements to serve Alliance Center North -8
City Project No. 103761
1.11 FIELD [SITE] CONDITIONS [NOT USED]1
1.12 WARRANTY [NOT USED]2
PART 2 - PRODUCTS3
2.1 OWNER-FURNISHED [OR] OWNER-SUPPLIEDPRODUCTS [NOT USED]4
2.2 MATERIALS5
A. Cleaning Agents6
1. Compatible with surface being cleaned7
2. New and uncontaminated8
3. For manufactured surfaces9
a. Material recommended by manufacturer10
2.3 ACCESSORIES [NOT USED]11
2.4 SOURCE QUALITY CONTROL [NOT USED]12
PART 3 - EXECUTION13
3.1 INSTALLERS [NOT USED]14
3.2 EXAMINATION [NOT USED]15
3.3 PREPARATION [NOT USED]16
3.4 APPLICATION [NOT USED]17
3.5 REPAIR / RESTORATION [NOT USED]18
3.6 RE-INSTALLATION [NOT USED]19
3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED]20
3.8 SYSTEM STARTUP [NOT USED]21
3.9 ADJUSTING [NOT USED]22
3.10 CLEANING23
A. General24
1. Prevent accumulation of wastes that create hazardous conditions.25
2. Conduct cleaning and disposal operations to comply with laws and safety orders of26
governing authorities.27
3. Do not dispose of volatile wastes such as mineral spirits, oil or paint thinner in28
storm or sanitary drains or sewers.29
4. Dispose of degradable debris at an approved solid waste disposal site.30
5. Dispose of nondegradable debris at an approved solid waste disposal site or in an31
alternate manner approved by City and regulatory agencies.32
33
34
35
36
01 74 23 - 3
DAP CLEANING
Page 3 of 4
Public Wtr Improvements to serve Alliance Center North -8
City Project No. 103761
6. Handle materials in a controlled manner with as few handlings as possible.1
7. Thoroughly clean, sweep, wash and polish all Work and equipment associated with2
this project.3
8. Remove all signs of temporary construction and activities incidental to construction4
of required permanent Work.5
9. If project is not cleaned to the satisfaction of the City, the City reserves the right to6
have the cleaning completed at the expense of the Contractor.7
10. Do not burn on-site.8
B. Intermediate Cleaning during Construction9
1. Keep Work areas clean so as not to hinder health, safety or convenience of10
personnel in existing facility operations.11
2. At maximum weekly intervals, dispose of waste materials, debris and rubbish.12
3. Confine construction debris daily in strategically located container(s):13
a. Cover to prevent blowing by wind14
b. Store debris away from construction or operational activities15
c. Haul from site at a minimum of once per week16
4. Vacuum clean interior areas when ready to receive finish painting.17
a. Continue vacuum cleaning on an as-needed basis, until Final Acceptance.18
5. Prior to storm events, thoroughly clean site of all loose or unsecured items, which19
may become airborne or transported by flowing water during the storm.20
C. Exterior (Site or Right of Way) Final Cleaning21
1. Remove trash and debris containers from site.22
a. Re-seed areas disturbed by location of trash and debris containers in accordance23
with Section 32 92 13.24
2. Sweep roadway to remove all rocks, pieces of asphalt, concrete or any other object25
that may hinder or disrupt the flow of traffic along the roadway.26
3. Clean any interior areas including, but not limited to, vaults, manholes, structures,27
junction boxes and inlets.28
4. If no longer required for maintenance of erosion facilities, and upon approval by29
City, remove erosion control from site.30
Clean signs, lights, signals, etc.31
3.11 CLOSEOUT ACTIVITIES [NOT USED]32
3.12 PROTECTION [NOT USED]33
3.13 MAINTENANCE [NOT USED]34
3.14 ATTACHMENTS [NOT USED]35
36
37
38
39
40
01 74 23 - 4
DAP CLEANING
Page 4 of 4
Public Wtr Improvements to serve Alliance Center North -8
City Project No. 103761
END OF SECTION1
2
Revision Log
DATE NAME SUMMARY OF CHANGE
4/7/2014 M.Domenech Revised for DAP application
3
01 77 19 - 1
DAP CLOSEOUT REQUIREMENTS
Page 1 of 3
Public Wtr Improvements to serve Alliance Center North - 8
City Project No. 103761
SECTION 01 77 191
CLOSEOUT REQUIREMENTS2
PART 1 - GENERAL3
1.1 SUMMARY4
A. Section Includes:5
1. The procedure for closing out a contract6
B. Deviations from this City of Fort Worth Standard Specification7
1. None.8
C. Related Specification Sections include, but are not necessarily limited to:9
1. Division 0 Bidding Requirements, Contract Forms and Conditions of the Contract10
1. Division 1 General Requirements11
1.2 PRICE AND PAYMENT PROCEDURES12
A. Measurement and Payment13
1. Work associated with this Item is considered subsidiary to the various Items bid.14
No separate payment will be allowed for this Item.15
1.3 REFERENCES [NOT USED]16
1.4 ADMINISTRATIVE REQUIREMENTS17
A. Guarantees, Bonds and Affidavits18
1. No application for final payment will be accepted until all guarantees, bonds,19
certificates, licenses and affidavits required for Work or equipment as specified are20
satisfactorily filed with the City.21
B. Release of Liens or Claims22
1. No application for final payment will be accepted until satisfactory evidence of23
release of liens has been submitted to the City.24
1.5 SUBMITTALS25
A.26
01 77 19 - 2
DAP CLOSEOUT REQUIREMENTS
Page 2 of 3
Public Wtr Improvements to serve Alliance Center North - 8
City Project No. 103761
1.6 INFORMATIONAL SUBMITTALS [NOT USED]1
1.7 CLOSEOUT SUBMITTALS [NOT USED]2
PAT 2 - PRODUCTS [NOT USED]3
PART 3 - EXECUTION4
3.1 INSTALLERS [NOT USED]5
3.2 EXAMINATION [NOT USED]6
3.3 PREPARATION [NOT USED]7
3.4 CLOSEOUT PROCEDURE8
A. Prior to requesting Final Inspection, submit:9
1. Project Record Documents in accordance with Section 01 78 3910
2. Operation and Maintenance Data, if required, in accordance with Section 01 78 2311
B. Prior to requesting Final Inspection, perform final cleaning in accordance with Section12
01 74 23.13
C. Final Inspection14
1. After final cleaning, provide notice to the City Project Representative that the Work15
is completed.16
a. The City will make an initial Final Inspection with the Contractor present.17
b. Upon completion of this inspection, the City will notify the Contractor, in18
writing within 10 business days, of any particulars in which this inspection19
reveals that the Work is defective or incomplete.20
2. Upon receiving written notice from the City, immediately undertake the Work21
required to remedy deficiencies and complete the Work to the satisfaction of the22
City.23
3. Upon completion of Work associated with the items listed in the City's written24
notice, inform the City, that the required Work has been completed. Upon receipt25
of this notice, the City, in the presence of the Contractor, will make a subsequent26
Final Inspection of the project.27
4. Provide all special accessories required to place each item of equipment in full28
operation. These special accessory items include, but are not limited to:29
a. Specified spare parts30
b. Adequate oil and grease as required for the first lubrication of the equipment31
c. Initial fill up of all chemical tanks and fuel tanks32
d. Light bulbs33
e. Fuses34
f. Vault keys35
g. Handwheels36
h. Other expendable items as required for initial start-up and operation of all37
equipment38
D. Notice of Project Completion39
40
01 77 19 - 3
DAP CLOSEOUT REQUIREMENTS
Page 3 of 3
Public Wtr Improvements to serve Alliance Center North - 8
City Project No. 103761
1. Once the City Project Representative finds the Work subsequent to Final Inspection1
to be satisfactory, the City will issue a Notice of Project Completion (Green Sheet).2
E. Supporting Documentation3
1. Coordinate with the City Project Representative to complete the following4
additional forms:5
a. Final Payment Request6
b. Statement of Contract Time7
c. Affidavit of Payment and Release of Liens8
d. Consent of Surety to Final Payment9
e. Pipe Report (if required)10
f.11
g. Performance Evaluation of Contractor12
F. Letter of Final Acceptance13
1. Upon review and acceptance of Notice of Project Completion and Supporting14
Documentation, in accordance with General Conditions, City will issue Letter of15
Final Acceptance and release the Final Payment Request for payment.16
3.5 REPAIR / RESTORATION [NOT USED]17
3.6 RE-INSTALLATION [NOT USED]18
3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED]19
3.8 SYSTEM STARTUP [NOT USED]20
3.9 ADJUSTING [NOT USED]21
3.10 CLEANING [NOT USED]22
3.11 CLOSEOUT ACTIVITIES [NOT USED]23
3.12 PROTECTION [NOT USED]24
3.13 MAINTENANCE [NOT USED]25
3.14 ATTACHMENTS [NOT USED]26
END OF SECTION27
28
Revision Log
DATE NAME SUMMARY OF CHANGE
4/7/2014 M.Domenech Revised for DAP application
29
01 78 23 - 1
Operation and Maintenance Data
Page 1 of 5
Public Wtr Improvements to serve Alliance Center North - 8
City Project No. 103761
SECTION 01 78 231
OPERATION AND MAINTENANCE DATA2
PART 1 - GENERAL3
1.1 SUMMARY4
A. Section Includes:5
1. Product data and related information appropriate for City's maintenance and6
operation of products furnished under Contract7
2. Such products may include, but are not limited to:8
a. Traffic Controllers9
b. Irrigation Controllers (to be operated by the City)10
c. Butterfly Valves11
B. Deviations from this City of Fort Worth Standard Specification12
1. None.13
C. Related Specification Sections include, but are not necessarily limited to:14
1. Division 0 Bidding Requirements, Contract Forms and Conditions of the Contract15
2. Division 1 General Requirements16
1.2 PRICE AND PAYMENT PROCEDURES17
A. Measurement and Payment18
1. Work associated with this Item is considered subsidiary to the various Items bid.19
No separate payment will be allowed for this Item.20
1.3 REFERENCES [NOT USED]21
1.4 ADMINISTRATIVE REQUIREMENTS22
A. Schedule23
1. Submit manuals in final form to the City within 30 calendar days of product24
shipment to the project site.25
1.5 SUBMITTALS26
A. Submittals shall be in accordance with Section 01 33 00. All submittals shall be27
approved by the City prior to delivery.28
1.6 INFORMATIONAL SUBMITTALS29
A. Submittal Form30
1. Prepare data in form of an instructional manual for use by City personnel.31
2. Format32
a. Size: 8 ½ inches x 11 inches33
b. Paper34
1) 40 pound minimum, white, for typed pages35
2) Holes reinforced with plastic, cloth or metal36
c.37
38
39
01 78 23 - 2
Operation and Maintenance Data
Page 2 of 5
Public Wtr Improvements to serve Alliance Center North - 8
City Project No. 103761
d. Drawings1
1) Provide reinforced punched binder tab, bind in with text2
2) Reduce larger drawings and fold to size of text pages.3
e. Provide fly-leaf for each separate product, or each piece of operating4
equipment.5
1) Provide typed description of product, and major component parts of6
equipment.7
2) Provide indexed tabs.8
f. Cover9
1) Identify each volume with typed or printed title "OPERATING AND10
MAINTENANCE INSTRUCTIONS".11
2) List:12
a) Title of Project13
b) Identity of separate structure as applicable14
c) Identity of general subject matter covered in the manual15
3. Binders16
a. Commercial quality 3-ring binders with durable and cleanable plastic covers17
b. When multiple binders are used, correlate the data into related consistent18
groupings.19
4. If available, provide an electronic form of the O&M Manual.20
B. Manual Content21
1. Neatly typewritten table of contents for each volume, arranged in systematic order22
a. Contractor, name of responsible principal, address and telephone number23
b. A list of each product required to be included, indexed to content of the volume24
c. List, with each product:25
1) The name, address and telephone number of the subcontractor or installer26
2) A list of each product required to be included, indexed to content of the27
volume28
3) Identify area of responsibility of each29
4) Local source of supply for parts and replacement30
d. Identify each product by product name and other identifying symbols as set31
forth in Contract Documents.32
2. Product Data33
a. Include only those sheets which are pertinent to the specific product.34
b. Annotate each sheet to:35
1) Clearly identify specific product or part installed36
2) Clearly identify data applicable to installation37
3) Delete references to inapplicable information38
3. Drawings39
a. Supplement product data with drawings as necessary to clearly illustrate:40
1) Relations of component parts of equipment and systems41
2) Control and flow diagrams42
b. Coordinate drawings with information in Project Record Documents to assure43
correct illustration of completed installation.44
c. Do not use Project Record Drawings as maintenance drawings.45
4. Written text, as required to supplement product data for the particular installation:46
a. Organize in consistent format under separate headings for different procedures.47
b. Provide logical sequence of instructions of each procedure.48
01 78 23 - 3
Operation and Maintenance Data
Page 3 of 5
Public Wtr Improvements to serve Alliance Center North - 8
City Project No. 103761
5. Copy of each warranty, bond and service contract issued1
a. Provide information sheet for City personnel giving:2
1) Proper procedures in event of failure3
2) Instances which might affect validity of warranties or bonds4
C. Manual for Materials and Finishes5
1. Submit 5 copies of complete manual in final form.6
2. Content, for architectural products, applied materials and finishes:7
a. Manufacturer's data, giving full information on products8
1) Catalog number, size, composition9
2) Color and texture designations10
3) Information required for reordering special manufactured products11
b. Instructions for care and maintenance12
1) Manufacturer's recommendation for types of cleaning agents and methods13
2) Cautions against cleaning agents and methods which are detrimental to14
product15
3) Recommended schedule for cleaning and maintenance16
3. Content, for moisture protection and weather exposure products:17
a. Manufacturer's data, giving full information on products18
1) Applicable standards19
2) Chemical composition20
3) Details of installation21
b. Instructions for inspection, maintenance and repair22
D. Manual for Equipment and Systems23
1. Submit 5 copies of complete manual in final form.24
2. Content, for each unit of equipment and system, as appropriate:25
a. Description of unit and component parts26
1) Function, normal operating characteristics and limiting conditions27
2) Performance curves, engineering data and tests28
3) Complete nomenclature and commercial number of replaceable parts29
b. Operating procedures30
1) Start-up, break-in, routine and normal operating instructions31
2) Regulation, control, stopping, shut-down and emergency instructions32
3) Summer and winter operating instructions33
4) Special operating instructions34
c. Maintenance procedures35
1) Routine operations36
2) Guide to "trouble shooting"37
3) Disassembly, repair and reassembly38
4) Alignment, adjusting and checking39
d. Servicing and lubrication schedule40
1) List of lubricants required41
e. Manufacturer's printed operating and maintenance instructions42
f. Description of sequence of operation by control manufacturer43
1) Predicted life of parts subject to wear44
2) Items recommended to be stocked as spare parts45
g. As installed control diagrams by controls manufacturer46
h. Each contractor's coordination drawings47
1) As installed color coded piping diagrams48
01 78 23 - 4
Operation and Maintenance Data
Page 4 of 5
Public Wtr Improvements to serve Alliance Center North - 8
City Project No. 103761
i. Charts of valve tag numbers, with location and function of each valve1
j. List of original manufacturer's spare parts, manufacturer's current prices, and2
recommended quantities to be maintained in storage3
k. Other data as required under pertinent Sections of Specifications4
3. Content, for each electric and electronic system, as appropriate:5
a. Description of system and component parts6
1) Function, normal operating characteristics, and limiting conditions7
2) Performance curves, engineering data and tests8
3) Complete nomenclature and commercial number of replaceable parts9
b. Circuit directories of panelboards10
1) Electrical service11
2) Controls12
3) Communications13
c. As installed color coded wiring diagrams14
d. Operating procedures15
1) Routine and normal operating instructions16
2) Sequences required17
3) Special operating instructions18
e. Maintenance procedures19
1) Routine operations20
2) Guide to "trouble shooting"21
3) Disassembly, repair and reassembly22
4) Adjustment and checking23
f. Manufacturer's printed operating and maintenance instructions24
g. List of original manufacturer's spare parts, manufacturer's current prices, and25
recommended quantities to be maintained in storage26
h. Other data as required under pertinent Sections of Specifications27
4. Prepare and include additional data when the need for such data becomes apparent28
during instruction of City's personnel.29
1.7 CLOSEOUT SUBMITTALS [NOT USED]30
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]31
1.9 QUALITY ASSURANCE32
A. Provide operation and maintenance data by personnel with the following criteria:33
1. Trained and experienced in maintenance and operation of described products34
2. Skilled as technical writer to the extent required to communicate essential data35
3. Skilled as draftsman competent to prepare required drawings36
37
01 78 23 - 5
Operation and Maintenance Data
Page 5 of 5
Public Wtr Improvements to serve Alliance Center North - 8
City Project No. 103761
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]1
1.11 FIELD [SITE] CONDITIONS [NOT USED]2
1.12 WARRANTY [NOT USED]3
PART 2 - PRODUCTS [NOT USED]4
PART 3 - EXECUTION [NOT USED]5
END OF SECTION6
7
Revision Log
DATE NAME SUMMARY OF CHANGE
8/31/2012 D. Johnson 1.5.A.1 title of section removed
4/7/2014 M.Domenech Revised for DAP Application
8
01 78 39 - 1
DAP PROJECT RECORD DOCUMENTS
Page 1 of 4
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS DEVELOPER AWARDED PROJECTS City Project No. 103761
Revised April 7, 2014
SECTION 01 78 391
PROJECT RECORD DOCUMENTS2
PART 1 -GENERAL3
1.1 SUMMARY4
A.Section Includes:5
1.Work associated with the documenting the project and recording changes to project6
documents, including:7
a.Record Drawings8
b.Water Meter Service Reports9
c.Sanitary Sewer Service Reports10
d.Large Water Meter Reports11
B.Deviations from this City of Fort Worth Standard Specification12
1.None.13
C.Related Specification Sections include, but are not necessarily limited to:14
1.Division 0 Bidding Requirements, Contract Forms and Conditions of the Contract15
2.Division 1 General Requirements16
1.2 PRICE AND PAYMENT PROCEDURES17
A.Measurement and Payment18
1.Work associated with this Item is considered subsidiary to the various Items bid.19
No separate payment will be allowed for this Item.20
1.3 REFERENCES [NOT USED]21
1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED]22
1.5 SUBMITTALS23
A.Prior to submitting a request for Final Inspection, deliver Project Record Documents to24
.25
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]26
1.7 CLOSEOUT SUBMITTALS [NOT USED]27
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]28
1.9 QUALITY ASSURANCE29
A.Accuracy of Records30
1.Thoroughly coordinate changes within the Record Documents, making adequate31
and proper entries on each page of Specifications and each sheet of Drawings and32
other Documents where such entry is required to show the change properly.33
2.Accuracy of records shall be such that future search for items shown in the Contract34
Documents may rely reasonably on information obtained from the approved Project35
Record Documents.36
01 78 39 - 2
DAP PROJECT RECORD DOCUMENTS
Page 2 of 4
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS DEVELOPER AWARDED PROJECTS City Project No. 103761
Revised April 7, 2014
3.To facilitate accuracy of records, make entries within 24 hours after receipt of1
information that the change has occurred.2
4.Provide factual information regarding all aspects of the Work, both concealed and3
visible, to enable future modification of the Work to proceed without lengthy and4
expensive site measurement, investigation and examination.5
1.10 STORAGE AND HANDLING6
A.Storage and Handling Requirements7
1.Maintain the job set of Record Documents completely protected from deterioration8
and from loss and damage until completion of the Work and transfer of all recorded9
data to the final Project Record Documents.10
2.In the event of loss of recorded data, use means necessary to again secure the data11
to the City's approval.12
a.In such case, provide replacements to the standards originally required by the13
Contract Documents.14
1.11 FIELD [SITE] CONDITIONS [NOT USED]15
1.12 WARRANTY [NOT USED]16
PART 2 -PRODUCTS17
2.1 OWNER-FURNISHED [OR] OWNER-SUPPLIED PRODUCTS [NOT USED]18
2.2 RECORD DOCUMENTS19
A.Job set20
1.Promptly following receipt of the Notice to Proceed, secure from the City, at no21
charge to the Contractor, 1 complete set of all Documents comprising the Contract.22
B.Final Record Documents23
1.At a time nearing the completion of the Work and prior to Final Inspection, provide24
the City 1 complete set of all Final Record Drawings in the Contract.25
2.3 ACCESSORIES [NOT USED]26
2.4 SOURCE QUALITY CONTROL [NOT USED]27
PART 3 -EXECUTION28
3.1 INSTALLERS [NOT USED]29
3.2 EXAMINATION [NOT USED]30
3.3 PREPARATION [NOT USED]31
3.4 MAINTENANCE DOCUMENTS32
A.Maintenance of Job Set33
1.Immediately upon receipt of the job set, identify each of the Documents with the34
title, "RECORD DOCUMENTS - JOB SET".35
01 78 39 - 3
DAP PROJECT RECORD DOCUMENTS
Page 3 of 4
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS DEVELOPER AWARDED PROJECTS City Project No. 103761
Revised April 7, 2014
2.Preservation1
a.Considering the Contract completion time, the probable number of occasions2
upon which the job set must be taken out for new entries and for examination,3
and the conditions under which these activities will be performed, devise a4
suitable method for protecting the job set.5
b.Do not use the job set for any purpose except entry of new data and for review6
by the City, until start of transfer of data to final Project Record Documents.7
c.Maintain the job set at the site of work.8
3.Coordination with Construction Survey9
a.At a minimum clearly mark any deviations from Contract Documents10
associated with installation of the infrastructure.11
4.Making entries on Drawings12
a.Record any deviations from Contract Documents.13
b.Use an erasable colored pencil (not ink or indelible pencil), clearly describe the14
change by graphic line and note as required.15
c.Date all entries.16
d.Call attention to the entry by a "cloud" drawn around the area or areas affected.17
e.In the event of overlapping changes, use different colors for the overlapping18
changes.19
5.Conversion of schematic layouts20
a.In some cases on the Drawings, arrangements of conduits, circuits, piping,21
ducts, and similar items, are shown schematically and are not intended to22
portray precise physical layout.23
1)Final physical arrangement is determined by the Contractor, subject to the24
City's approval.25
2)However, design of future modifications of the facility may require26
accurate information as to the final physical layout of items which are27
shown only schematically on the Drawings.28
b.Show on the job set of Record Drawings, by dimension accurate to within 129
inch, the centerline of each run of items.30
1)Final physical arrangement is determined by the Contractor, subject to the31
City's approval.32
2)Show, by symbol or note, the vertical location of the Item ("under slab", "in33
ceiling plenum", "exposed", and the like).34
3)Make all identification sufficiently descriptive that it may be related35
reliably to the Specifications.36
c.The City may waive the requirements for conversion of schematic layouts37
where, in the City's judgment, conversion serves no useful purpose. However,38
do not rely upon waivers being issued except as specifically issued in writing39
by the City.40
B.Final Project Record Documents41
1.Transfer of data to Drawings42
a.Carefully transfer change data shown on the job set of Record Drawings to the43
corresponding final documents, coordinating the changes as required.44
b.Clearly indicate at each affected detail and other Drawing a full description of45
changes made during construction, and the actual location of items.46
c.Call attention to each entry by drawing a "cloud" around the area or areas47
affected.48
01 78 39 - 4
DAP PROJECT RECORD DOCUMENTS
Page 4 of 4
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS DEVELOPER AWARDED PROJECTS City Project No. 103761
Revised April 7, 2014
d.Make changes neatly, consistently and with the proper media to assure1
longevity and clear reproduction.2
2.Transfer of data to other Documents3
a.If the Documents, other than Drawings, have been kept clean during progress of4
the Work, and if entries thereon have been orderly to the approval of the City,5
the job set of those Documents, other than Drawings, will be accepted as final6
Record Documents.7
b.If any such Document is not so approved by the City, secure a new copy of that8
Document from the City at the City's usual charge for reproduction and9
handling, and carefully transfer the change data to the new copy to the approval10
of the City.11
3.5 REPAIR / RESTORATION [NOT USED]12
3.6 RE-INSTALLATION [NOT USED]13
3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED]14
3.8 SYSTEM STARTUP [NOT USED]15
3.9 ADJUSTING [NOT USED]16
3.10 CLEANING [NOT USED]17
3.11 CLOSEOUT ACTIVITIES [NOT USED]18
3.12 PROTECTION [NOT USED]19
3.13 MAINTENANCE [NOT USED]20
3.14 ATTACHMENTS [NOT USED]21
END OF SECTION22
23
Revision Log
DATE NAME SUMMARY OF CHANGE
4/7/2014 M.Domenech Revised for DAP Application
24
02 41 13 - 1
SELECTIVE SITE DEMOLITION
Page 1 of 5
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No. 103761
Revised December 20, 2012
SECTION 02 41 131
SELECTIVE SITE DEMOLITION2
PART 1 -GENERAL3
1.1 SUMMARY4
A.Section Includes:5
1.Removing sidewalks and steps6
2.Removing ADA ramps and landings7
3.Removing driveways8
4.Removing fences9
5.Removing guardrail10
6.Removing retaining walls (less than 4 feet tall)11
7.Removing mailboxes12
8.Removing rip rap13
9.Removing miscellaneous concrete structures including porches and foundations14
10.Disposal of removed materials15
B.Deviations this from City of Fort Worth Standard Specification16
1.None.17
C.Related Specification Sections include, but are not necessarily limited to:18
1.Division 0 Bidding Requirements, Contract Forms, and Conditions of the19
Contract20
2.Division 1 General Requirements21
3.Section 31 23 23 Borrow22
1.2 PRICE AND PAYMENT PROCEDURES23
A.Measurement and Payment24
1.Measurement25
a.Remove Sidewalk: Measure by square foot.26
b.Remove Steps: measure by the square foot as seen in the plan view only.27
c.Remove ADA Ramp: measure by each.28
d.Remove Driveway: measure by the square foot by type.29
e.Remove Fence: measure by the linear foot.30
f.Remove Guardrail: measure by the linear foot along the face of the rail in place31
including metal beam guard fence transitions and single guard rail terminal32
sections from the center of end posts.33
g.Remove Retaining Wall (less than 4 feet tall): measure by the linear foot34
h.Remove Mailbox: measure by each.35
i.Remove Rip Rap: measure by the square foot.36
j.Remove Miscellaneous Concrete Structure: measure by the lump sum.37
2.Payment38
02 41 13 - 2
SELECTIVE SITE DEMOLITION
Page 2 of 5
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No. 103761
Revised December 20, 2012
a.Remove Sidewalk: full compensation for saw cutting, removal, hauling,1
disposal, tools, equipment, labor and incidentals needed to execute work.2
Sidewalk adjacent to or attached to retaining wall (including sidewalk that acts3
as a wall footing) shall be paid as sidewalk removal. For utility projects, this4
Item shall be considered subsidiary to the trench and no other compensation5
will be allowed.6
b.Remove Steps: full compensation for saw cutting, removal, hauling, disposal,7
tools, equipment, labor and incidentals needed to execute work. For utility8
projects, this Item shall be considered subsidiary to the trench and no other9
compensation will be allowed.10
c.Remove ADA Ramp and landing: full compensation for saw cutting, removal,11
hauling, disposal, tools, equipment, labor and incidentals needed to execute12
work. Work includes ramp landing removal. For utility projects, this Item shall13
be considered subsidiary to the trench and no other compensation will be14
allowed.15
d.Remove Driveway: full compensation for saw cutting, removal, hauling,16
disposal, tools, equipment, labor and incidentals needed to remove improved17
driveway by type. For utility projects, this Item shall be considered subsidiary18
to the trench and no other compensation will be allowed.19
e.Remove Fence: full compensation for removal, hauling, disposal, tools,20
equipment, labor and incidentals needed to remove fence. For utility projects,21
this Item shall be considered subsidiary to the trench and no other22
compensation will be allowed.23
f.Remove Guardrail: full compensation for removing materials, loading, hauling,24
unloading, and storing or disposal; furnishing backfill material; backfilling the25
postholes; and equipment, labor, tools, and incidentals. For utility projects, this26
Item shall be considered subsidiary to the trench and no other compensation27
will be allowed.28
g.Remove Retaining Wall (less than 4 feet tall): full compensation for saw29
cutting, removal, hauling, disposal, tools, equipment, labor and incidentals30
needed to execute work. Sidewalk adjacent to or attached to retaining wall31
(including sidewalk that acts as a wall footing) shall be paid as sidewalk32
removal. For utility projects, this Item shall be considered subsidiary to the33
trench and no other compensation will be allowed.34
h.Remove Mailbox: full compensation for removal, hauling, disposal, tools,35
equipment, labor and incidentals needed to execute work. For utility projects,36
this Item shall be considered subsidiary to the trench and no other37
compensation will be allowed.38
i.Remove Rip Rap: full compensation for saw cutting, removal, hauling,39
disposal, tools, equipment, labor and incidentals needed to execute work. For40
utility projects, this Item shall be considered subsidiary to the trench and no41
other compensation will be allowed.42
j.Remove Miscellaneous Concrete Structure: full compensation for saw cutting,43
removal, hauling, disposal, tools, equipment, labor and incidentals needed to44
execute work. For utility projects, this Item shall be considered subsidiary to45
the trench and no other compensation will be allowed.46
1.3 REFERENCES47
A.Definitions48
02 41 13 - 3
SELECTIVE SITE DEMOLITION
Page 3 of 5
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No. 103761
Revised December 20, 2012
1.Improved Driveway: Driveway constructed of concrete, asphalt paving or brick unit1
pavers.2
1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED]3
1.5 SUBMITTALS [NOT USED]4
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]5
1.7 CLOSEOUT SUBMITTALS [NOT USED]6
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]7
1.9 QUALITY ASSURANCE [NOT USED]8
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]9
1.11 FIELD [SITE] CONDITIONS [NOT USED]10
1.12 WARRANTY [NOT USED]11
PART 2 -PRODUCTS12
2.1 OWNER-FURNISHED PRODUCTS [NOT USED]13
2.2 MATERIALS14
A.Fill Material: See Section 31 23 23.15
2.3 ACCESSORIES [NOT USED]16
2.4 SOURCE QUALITY CONTROL [NOT USED]17
PART 3 -EXECUTION18
3.1 INSTALLERS [NOT USED]19
3.2 EXAMINATION [NOT USED]20
3.3 PREPARATION [NOT USED]21
3.4 REMOVAL22
A.Remove Sidewalk23
1.Remove sidewalk to nearest existing dummy, expansion or construction joint.24
2.Sawcut when removing to nearest joint is not practical. See 3.4.K.25
B.Remove Steps26
1.Remove step to nearest existing dummy, expansion or construction joint.27
2.Sawcut when removing to nearest joint is not practical. See 3.4.K.28
C.Remove ADA Ramp29
1.Sawcut existing curb and gutter and pavement prior to wheel chair ramp removal.30
See 3.4.K.31
2.Remove ramp to nearest existing dummy, expansion or construction joint on32
existing sidewalk.33
D.Remove Driveway34
02 41 13 - 4
SELECTIVE SITE DEMOLITION
Page 4 of 5
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No. 103761
Revised December 20, 2012
1.Sawcut existing drive, curb and gutter and pavement prior to drive removal. See1
3.4.K.2
2.Remove drive to nearest existing dummy, expansion or construction joint.3
3.Sawcut when removing to nearest joint is not practical. See 3.4.K.4
4.Remove adjacent sidewalk to nearest existing dummy, expansion or construction5
joint on existing sidewalk.6
E.Remove Fence7
1.Remove all fence components above and below ground and backfill with acceptable8
fill material.9
2.Use caution in removing and salvaging fence materials.10
3.Salvaged materials may be used to reconstruct fence as approved by City or as11
shown on Drawings.12
4.Contractor responsible for keeping animals (livestock, pets, etc.) within the fenced13
areas during construction operation and while removing fences.14
F.Remove Guardrail15
1.Remove rail elements in original lengths.16
2.Remove fittings from the posts and the metal rail and then pull the posts.17
3.Do not mar or damage salvageable materials during removal.18
4.Completely remove posts and any concrete surrounding the posts.19
5.Furnish backfill material and backfill the hole with material equal in composition20
and density to the surrounding soil unless otherwise directed.21
6.Cut off or bend down eyebolts anchored to the dead man to an elevation at least 1-22
foot below the new subgrade elevation and leave in place along with the dead man.23
G.Remove Retaining Wall (less than 4 feet tall)24
1.Remove wall to nearest existing joint.25
2.Sawcut when removing to nearest joint is not practical. See 3.4.K.26
3.Removal includes all components of the retaining wall including footings.27
4.Sidewalk adjacent to or attached to retaining wall: See 3.4.A28
H.Remove Mailbox29
1.Salvage existing materials for reuse. Mailbox materials may need to be used for30
reconstruction.31
I.Remove Rip Rap32
1.Remove rip rap to nearest existing dummy, expansion or construction joint.33
2.Sawcut when removing to nearest joint is not practical. See 3.4.K.34
J.Remove Miscellaneous Concrete Structure35
1.Remove portions of miscellaneous concrete structures including foundations and36
slabs that do not interfere with proposed construction to 2 feet below the finished37
ground line.38
2.Cut reinforcement close to the portion of the concrete to remain in place.39
3.Break or perforate the bottom of structures to remain to prevent the entrapment of40
water.41
02 41 13 - 5
SELECTIVE SITE DEMOLITION
Page 5 of 5
CITY OF FORT WORTH Public Wtr Improvements to serve Alliance Center North - 8
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS City Project No. 103761
Revised December 20, 2012
K.Sawcut1
1.Sawing Equipment2
a.Power-driven3
b.Manufactured for the purpose of sawing pavement4
c.In good operating condition5
d.Shall not spall or fracture the pavement to the removal area6
2.Sawcut perpendicular to the surface completely through existing pavement.7
3.5 REPAIR [NOT USED]8
3.6 RE-INSTALLATION [NOT USED]9
3.7 SITE QUALITY CONTROL [NOT USED]10
3.8 SYSTEM STARTUP [NOT USED]11
3.9 ADJUSTING [NOT USED]12
3.10 CLEANING [NOT USED]13
3.11 CLOSEOUT ACTIVITIES [NOT USED]14
3.12 PROTECTION [NOT USED]15
3.13 MAINTENANCE [NOT USED]16
3.14 ATTACHMENTS [NOT USED]17
END OF SECTION18
19
Revision Log
DATE NAME SUMMARY OF CHANGE
12/20/2012 D. Johnson 1.2.A.2. Modified Payment - Items will be subsidiary to trench on utility projects
20
* From Original5tandard Products List
CITY OF FORT WORTH
FORT WORTH�� WATER DEPARTMENT
STANDARD PRODUCT LIST
Updated: 11/OS/2021
FORT WORTHO
CITY OF FORT WORTH
WATER DEPARTMENT
STANDARD PRODUCT LIST
Updated: 11/OS/2021
Note: All water or sewer i e lar er than 15 inch diameter shall be a roved for use b the Water De artment on a ro'ect s ecific basis. S ecial beddin ma be re uired for some i es.
• � � � �• i i i �• i i �•
Water & Sewer - Manhole Inserts - Field Ooerafions Use Onlv fRev 2/3/161
33 OS 13 Manhole Insert Knutson Enler nses Made to Order- Plastic ASTM D 1248 For 24" dia.
33 OS 13 Manhole Insert South Westerz� Packe in Made to Order - Plastic ASTM D 1248 For 24" dia.
33 OS 13 Manhole Insert Noflow-Inilow Made to Order - Plastic ASTM D 1248 For 24" dia.
09/23/96 33 OS 13 Manhole Insert Southwestern Packin & Seals Inc. LifeSaver - Stainless Steel For 24" dia.
09/23/96 33 OS 13 Manhulc Insert Southwestern Packin & Seals Inc. TelherLok - Sleinless Steel For 24" dia
Water & Sewer - Pioe Casin¢ Soacers 33-OS-24 (07/Ol/131
i iroaioz s«��i a��a cas��� s�a�� na����a e��a�ati ��a sytii�ms, m�. ca�n�� si�i s����, M�a��i si
02/02/93 Stainlctiti Slccl Catiin� Spaccr A�vancc� Pru�uati an� Sytilcros, Inc Stainlctiti Slccl Spaccr, Mu�cl SSI
04/22/87 Casing Spaccrs Casca�c Walcnvurkti Manufaclurine Catiin� Spaccn
09/14/10 Stainless Sleel Casine Spacer Pipeline Seal and Insulalor Stainless Sleel Casing Spacer Up l0 48"
09/14/10 Coated Sleel Casin Spacers Pipeline Seal and Insulalor Coatul Sleel Casin Spacers Up l0 48"
OS/10/I I Stainless Sleel Casine Spacer Powe�seal 4810 Powerchock Up to 48"
03/19/IA CasingSpace�s BWM SS-12CasingSpacer(SlainlessSteel)
03/19/18 Casing Spacers BWM Ff3-12 Casing Spacer (Coated Carbon Steel)
for Nonyruwre Pipe and Grouted Casing
Water & Sewer - Pioes/Ductile Iron 33-11-1Ofl/8/131
* 33 I 1 10 Ductle Iron Pipe (inRn P�pe Produas, Co. Super Bell-T�le Dudile Iron Pressure P�pe, p�yµ�p CI50, C I51 3" Ihru 24"
0824/I R 33 11 10 Duclilc Iron Pi e American Ductile Iron Pi e Co. American Feslile Pi e(Bell S i ol) AW WA C750, C751 4" Iluu 30"
08/24/18 33 1 I 10 Ductile Iron Pipe Amecican Ductile Iron Pipe Co. Amecican Flex Ring (Rutcained Join�) AW WA C I50, CI51 4" thcu 30"
* 33 I I 10 Ductile Iron Pipe U.S. Pipe and Foundry Co. AW WA CI50, C I51
* 33 I I 10 Ductile Iron Pipe McWene Cesl Iron Pipe Co. AW WA CI50, C I51
Water & Sewer - Utilit Line Marker 08/24/2018
Sewer - Coatin s/E ox 33-39-60 Ol/O8/13
02/25/U2 E oxv Linin Svstem Sauereisen.lnc SewerGard 21URS LA Count '�21U-133
12/14/01 E oxv Linin Svstem Ertech Technical Coatin Eetech 2U3U and 210U Series
04/14/05 Interior D�ctile Iron Pi e Coatin Induron Proteclo 401 ASTM B-I 17 D�ctile Iron Pi e Onl
01/31/06 Coatin s foc Cocrosion Protection Chesterton Aro 791. S I HB S I. S2 Acid Resistance Test Sewer A lications
ft/28/2006 Coatin s for Corrosion Protection Warren Environmental 5-301 and M-301 Sewer A lications
Sewer - CoaGn s/Pol urethane
Sewer - Combination Air Valves
05/25/IN 3331-70 Air Release Valve A.R.I. 1;5A, lnc. D0251_I'P02 Com osite Rod 2"
Sewer - Pi es/Concrete
' EI-04 Conc.Pi e.Reinforced WaIlConcre�ePi eCo.lne. AST.vi C76
EI-04 Conc. Pi e. Reinforced H d�n Conduit Cor oration Claaa 111 T&G, SPL Item'�77 ASTM C 76
EI-04 Conc. Pi e. Reinfo�ced Hanson Concrete Prod�cts ASTM C 76
EI-04 Conc. Pi e. Reinfoeced Concrete Pi e& Prod�cts Co. Ine. ASTM C 76
Sewer - Pi e Enlar ment S stem Method 33-31-23 Ol/18/13
PIM S stem PIM Cor oration Pol eth lene PIM Cor .. Piscata Wa , NJ. A roved Previousl
MeConnell S srems McLat Construction Pol eth lece Houston, Texas A roved Previousl
TRS S stems Trenchless Re lacement S srem Pol eth lene Cal ar , Canada A roved Previousl
Sewer - Pi e/Ftiber lass Reinforced Pi e 3331-13 1/8/13
7/21/97 33 31 13 Cent Cast Fiber lass (hRP Hobas Pi e USA. Inc. Hobas Pi e(Von-P�ess��e ASTM 173262/D3754
03/22/10 33 31 13 Fiber lass Pi e FRP Ameron Bondst�and RPMP Pi e ASTM D3262/D3754
04/09/21 Glass-Fiber Reinforoed Pol mee Pi e FRP Thom son Pi e Grou Thom son Pi e Flowtite ASTM D32621D3754
4/14/05 Pol mer Modifed Conccete Pi e Amitech USA Me ec Pol ccete Pi e AS'CM C33, A276. F477 8" to 102". Class V
06/09/10 E I-9 Reinfoeced Pol er Concrete Pi e US Com osite Pi e Reinforced Pol er Concre�e Pi e ASTM G76
Sewer - Pi es/HDPE 33-31-23 1/8/13
Hi h-densit alveth lene i Philli s D�isco i e, Ine. O tico�e Ductile Pol 'eth lene Pi e ASTM D 1248 8"
Hi h-densit olveth lene i Plexco Inc. ASTM D 1248 8"
Hi h-densit olveth lene i Poll Pi e, Ine. ASTM D 1248 8"
Hi h-densi� � al e�h �lece i CSR H dro Cond�ait/fti el'ine S �ems McConnell Pi e F:nlar�emenl AS"fM IJ 124N
Sewer - Pi es/PVC Pressure Sewer 33-11-12 4/1/13
17J07JI1 33-II-12 DR-14PVCPruwrePipe Pipelile7etstreain PVCPressurePipe AWWAC9U0 4"th��l2"
10/27JI4 33-I I-12 DR-14 PVC Pruwre Pipe Royal Ruilding Products Royal Seal PVC Pressu�e Pipe AW WA C900 4" th�� 12"
* From Original5tandard Products List
* From Original5tandard Products List
CITY OF FORT WORTH
FORT WORTH�� WATER DEPARTMENT
STANDARD PRODUCT LIST
Updated: 11/OS/2021
Water - Pioes/PVC [Pressure Water133-31-70 (Ol/08/13)
AW WA C900, AW WA C605,
01/18/18 33-II-12 PVCPressurePi e Vin ItechPVCPi e DRI4 ASTMDI784 4"-12"
3/19/2018 331112 PVCPressurePi e Pi elifeJetSlream DRI4 AWWAC900 4"-12"
3/19/2018 331112 PVCPressurePi e Pi elifeJetSlream DRIS AWWAC900 16"-24"
5/25/2018 33 I I 12 PVC Pressure Pi e Diamond Plastics Cor oalion DR 14 AW WA C900 4"-12"
5/25/2018 33 I I 12 PVC Pressure Pi e Diamond Plastics Cor oalion DR 18 AW WA C900 16"-24"
AW WA C900.16
12/6/2018 33 I I 12 PVC Pressure Pipe 1-M Manufaeturing Co., Inc d/b/a 1M Fsgle DR 14 UL 1285 4„ z8„
ANSI/NSF 61
FM 1612
AW WA C900-16
12/6l2018 33 I I 12 PVC Pressure Pipe J-M Manufact�cing Co., Inc d/b/a JM Eagle DR 18 UL 1285 16"-24"
ANSIMSF C>I
FM IC>I2
9/6/2019 331112 PVCPcuwrePipe UndecgcoundSolutionslnc. DRI4FusiblePVC AWWAC900 4"-8"
9/6/2019 331112 PVCPcusucePipe NAPCO DRI8 AWWAC900 16"-2A"
9/6/2019 33 I I 12 PVC Pressure Pipe NAPCO DR14 AWWA C900 4"- 12"
9/6/2019 331112 PVCPrusurePipe SandersonPipeCorp. IJR14 AWWAC900 4"-12"
Water - Pioes/Valves & Fittinas/DucHle Iron Fittinas 33-11-ll [Ol/08/13)
0723/92 GI-07 Duclilc Iron �iltings Star Pipc Producls, Inc. Mcchanical loinl Cittingti AW WA C153 & CI10
CI-07 DuctilclronCittin s Gril7inPi cProducl�,Cu. McchunicelloinlCillin�n AWWACIIO
EI-07 Ductle Iron Cittin s MeWaneJTvler Pi e/ Union Ulililies Division Mechanical Juinl Piuings, SSII Class 350 p�yy�p C 153, C I 10, C I I I
OS/71/98 EI-07 Ductle Iron Fillin s Si ma, Co. Mechanical Joinl Fiuings, 55B Class 351 p�yµ�p C 153, C I 10, C I 12
02/26/14 EI-07 M7 Fittin s Accucast Class 350 C-753 M7 Fittmgs p�yµ�p CI53 4"-12"
OS/14/98 EI-07 Ductile Iron Joml Reslramis Ford Meler Box Co.Nni-Flan e Uni-Flange Series 1400 p�yµ�p CI I I/C 153 4" to 36"
OS/14/98 EI-24 PVC Joinl Reslrainls Ford Meler Box Co.Nni-Flan e Uni-Flange Series I500 Circle-Lock p�yµ�p CI I I/C753 4" to 24"
71/09/04 EI-07 Ductile Iron Joml ReslramLs One Boll, Inc. One Bolt Resvained loint Fitling pµryyp C I I I/CI 16/C 153 4" to 12"
02/29/12 33-I1-I1 Ductile Iron Pi e Mechanical 1oin1 Reslreinl EBAA Iroq Inc. Megalug Series 1100 (for DI Pipe) pµryyp C I I UCI 16/C 153 4" to 42"
02/29/12 33-I1-I1 PVC Pi e Mechanical loint Resvainl EBAA Iron, Ine. Megalug Series 2000 (for PVC Pipe) pµryyp C I I I/CI 16/C 153 4" to 24"
OS/OS/04 EI-07 Mechanical Joml Relainer Glands PVC Si ma, Co. Sigma One-Lok SLC4 - SLCIO p�yµ�p CI I I/CI53 4" to 10"
03/06/19 33-I1-17 Mechanical Joinl Releiner Glands PVC Si ma, Co. Sigma One-Lok SLCS4 -SLCS12 p�yµ�p CI I I/C153 4" to 12"
OS/OS/04 EI-07 Muhanical Joml Relainer Glands PVC Si ma, Co. Sigma One-Lok SLCE p�yµ�p CI I I/C 153 12" to 24"
OS/10/98 EI-07 M7 Fitlin s(DIP Si ma, Co. Sigma One-Lok SLDE p�yµ�p CI53 4" -24"
10/12/10 EI-24 Inlerior Reslrained Joinl S slem S& B Techncial Produas Bulldog Syslem ( Diamond Lok 21 & 1M pSTM F-1624 4" to 12"
OS/16/06 EI-07 Mechanical Joinl Fiuin s SIP Induslries Seram or Mechanical Joinl Fillings p�yµ�p CI53 4" to 24"
11/07/16 33-I I-I1 Mechanical Joinl Releiner Glands Star Pi e Products, Ince PVC Stargrip Series 4000 pSTM A536 AWWA C111
11/07/16 33-I 1-I I Mechanical Joinl Releiner Glands Star Pi e Products, Inc. DIP Slargrip Series 3000 pSTM A536 AW WA C 111
03/19/IS 33-I I-I I Muhanical Joinl Relainer (ilands SIP Induslries Seram or EZ (irip Joinl Reslrainl (EZD) Black For DIP pSTM A536 AWWA C111 3"-48"
03/19/18 33-I I-I I Mechanical Joint Retainer Glands SIP Ind�stries(Se�ampore) EZGrip loint Resvaint (EZD) Red forC900 pSTM A536 AW WA C111 4"-12"
DRI4 PVC Pipe
03/19/18 33-I I-I I Mechanical Joint Retainer Glands SIP Ind�stries(Serampore) EZGiip 7oint Resvaint (EZD) Red forC900 pSTM A536 AWWA C111 16"-24"
DRIB PVC Pipe
* From Original5tandard Products List
CITY OF FORT WORTH
FORT WORTH�� WATER DEPARTMENT
STANDARD PRODUCT LIST
Updated: 11/OS/2021
* From Original5tandard Products List
CITY OF FORT WORTH
FORT WORTH�� WATER DEPARTMENT
STANDARD PRODUCT LIST
Updated: 11/OS/2021