City Of Fort Worth
Change Order Request
Facility and
project Park Maintenance Facility Phase 2 City Sec No. 53607
Description:
Funding(FID)34018 0800450 5740010101010 004480 999918020111 City Proj.No. 101010
No.(s)
Contractor:I Muckleroy&Falls Construction Company Change Order#F-3 J Date: 1112812022
City Project Mgr.I Ronnie Clements City Inspector: JDonIsaacs
Phone Number:(817)392-8014 Phone Number: (817)392-8498
Contract Time
(CD)
Original Contract Amount ---- $9,099,973.00 365
Extras to Date ---- $69,924.00 45
Credits to Date ------ $0.00 0
Pending Change Orders(in M&C Process) ---- $0.00 0
Contract Cost to Date ---- $9,169,897.00 0
Amount of Proposed Change Order ----- $9,869.00 0
Revised Contract Amount $9,179,766.00 410
Original Funds Available for Change Orders--- $0.00
Remaining Funds Available for this CO ---- $0.00
Additional Funding(if necessary) $0.00
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 0.876%
MAXALLOWABLECONTRACTAMOUNT(ORIGINAL CONTRACT COST+25%) $11,374,966.25
JUSTIFICATION(REASONS)FOR CHANGE ORDER
The purpose of Change Order#3 is to install low clearance racks on the overhead doors that were obstructed by the required PEMB
structure.Change Orders No.1,2,&3 increases the original contract($9,099,973.00)by$79,973.00 for a revised contract amount of
$9.179,766.00.A 0.876 percent increase to the original contract price.
It is understood and agreed that the acceptance of this Change Order by the contractor consitutes an accord and satisfaction and represents
payment in full(both time and money)for all costs arising out of,or incindental to the above Change Order.
Nov 28,2022
Muckleroy&Falls Dustin Vardaman -—.0 �n
Contractor's Company Name Contractor Name Contractor Signature Date
Da Nov 28,2022 Nov 29,2022
PMD Inspector Date Architecural Services Manager Date
Z?-ta2 Nov 28,2022 Dec 2,2022
PMD Superintendent Date Director Property Management Department Date
e-MCA—tl Nov 28,2022 sr Dec 7,2022
PMD Project Manager Date Assistant City Attorney Date
buyta� Nov 29,2022 Dec 72022
Dana fti hde(O-1,- :SOCS1 f
Project Architect Date Assistant City Manager Date
OFFICIAL RECORD
M&C Number N/A M&C Date Approved N/A
CITY SECRETARY
Contract Compliance Manager: FT.WORTH,TX
By signing I acknowledge that I am the person responsible ►�/yy�� �• 64'3t J
for the monitoring and administration of this contract,including Brian R.Glass,AIA
ensuring all performance and reporting requirements. Assistant Director,Property Managemei
Change Order Request
LIM I Detailed(with Breakdown of PCOs),Grouped by Each
MUCKLEROY LEROY FALLS Number
CoFW Park Maintenance Facility-Phase II Project# 19636 HM&MF Ltd.,d/b/a MUCKLEROY&FALLS
5189 James Ave.Fort Worth TX,76115 Tel: Fax:
Change • • 037 D. 1112312022
To: James Diestel From: Dustin Vardeman
City of Fort Worth HM&MF Ltd.,d/b/a MUCKLEROY&FALLS
401 W 13th St 3200 Riverfront Dr
Fort Worth,TX 76102 Suite 200
Fort Worth,TX 76107
Description Category Status
Low Clearance Overhead Door Tracks
Reference Required By Days Req Amt Req
11/30/2022 0 9,869
Notes
PCO No Date Reference Amt Prop Days Req Category Reason
Description Notes
PCO 37 11/23/2022 9,869 0
Low Clearance Overhead Door Tracks This PCO is to install low clearance tracks on overhead doors
obstructed by required PEMB structure.This is to provide a tighter seal
at the heads of the overhead doors.
This PCO is issued to incorporate the revisions as specifically detailed
on the attached cost summary and supporting documents.If additional
costs become apparent at a later date,or additional information
regarding this scope of work become available,we reserve the right to
price any additional cost and/or schedule impacts as they become
known.
Item No Item Description Amt Prop Reference
001 Owner Contingency-Low Clearance Overhead Door -3,808
Tracks
002 Texas Overhead Door-Low Clearance Overhead 13,677
Door Tracks
Approved By:
Signature
Name Date
Prolog Converge Printed on: 11/23/2022 MuckleroyFallsProlog Page 1
COMMERCIAL
lSERVICE0 MANAGER HOUS DIVISION
ell Sanders, 17 - TEXAS® Dale Overbay,83126- 5
dsandersO-txohd.com OVERHEAD DOOR doverbav(&txohd.com
SECURITY SALES COMMERCIAL&RFSIDF vTinL ESTIMATOR
Jesse Collier,817-295-0216 Don DeKing,800-715-8781
jcollier txohd.com CORPORATE OFFICE ddekinq(@txohd.com
ERIC FLETCHER
ESTIMATOR 122 NW Hillery Street,Burleson,TX 76028 ESTIMATOR
Mark Bateman,817-295-0216 817-295-0216/efletcher(ftcohd.com Linsey Golden,817-295-0216
mbateman(@__txohd.com Igolden(@__txohd.com
PROPOSAL
DATE: November 17, 2022
TO: Dustin Vardeman
Mark Pagel
Muckleroy&Falls
DVardeman(&muckleroyfalls.com
MPagel@muckleroyfalls.com
PROJECT: FORT WORTH PARD PHASE II
Change Below Doors to Double Low Headroom In lieu of Originally Installed Tracking System(Parts as mfg. by Clopay
Building Products)
(3)8'x 12'Sectional Doors
(1) 12'x 12'Sectional Doors
TOTAL $9,877.00
Tax Excluded
Change One Door to Double Low Headroom ahead of the remaining doors to get final approval from GC and Owner
TOTAL $3,800.00
Tax Excluded
***ELECTRICAL WIRE OR WIRING LOW OR HIGH VOLTAGE BY OTHERS***
Important Note:Specialty Product Requires from the Manufacturer a 309,66 Down Payment on Material Portion Only
This quotation is based on current pricing from our suppliers and includes surcharges levied by the steel industry.Surcharges
are subject to change and final pricing will be determined at the time the order is released for fabrication
YOUR CONTACT FOR THIS PROJECT IS: ERIC FLETCHER, 817-295-0216
EMAIL: efletcher@txohd.com
........................................................................................................................................
OVERHEAD SECTIONAL AND ROLLING DOORS - HIGH SPEED ROLLING DOORS
FULL LINE OF DOCK EQUIPMENT - INDUSTRIAL HANGAR, BI-FOLD,AND BLAST DOORS
Please visit our website: www.txohd.com
LG