Change Order Request
Project Name:I Water&Sanitary Sewer Replacement on Home Street City Sec No.: 1 57279
Project No.(s):l 103123 1 DOE No. N/A CityProj.No.:l 103123
Project Description: Replacing Water&Sanitary Sewer Lines on Home St.,Carver Dr.,Diaz Ave.,and alleyways.
Contractor: William J.Schultz,Inc.dba Circle C Construction,Co. Change Order# Date: 11129I2022
City Project Mgr.1 Pratima Poudyal City Inspector: I Cody Horton
Phone Number: 817-392-6149 Phone Number: 817475-6903
Dept. Unit I Water Unit II Sewer Totals Contract Time
Calendar days)_
Original Contract Amount $2,905,104.25 $1,519,011.95 $4,424,116.20 550
Extras to Date 1 $0.00 $0.00 $0.00 25
Credits to Date
Pending Change Orders(in M&C Process)
Contract Cost to Date $2,905,104.25 $1,519,011.95 $4,424,116.20 575
Amount of Proposed Change Order 40.50 $0.00 40.50 0
Revised Contract Amount $2,905,103.75 $1,519,011.95 $4,424,115.70 575
Original Funds Available for Change Orders $145,255.00 $75,951.00 $221,206.00
Remaining Funds Available for this CO r $145,255.00 $75,951.00 1 $221,206.00
Additional Funding(if necessary)
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 0.00%
MAXALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $5,530,145.25
JUSTIFICATION(REASONS)FOR CHANGE ORDER
Change Order No.2 provides compensation for the following:
•Installation of bored private service in order to relocate water meter away from driveway and avoid cutting the driveway and sidewalk,
•4 inch temporary water jumper lines in order to avoide service disruptions to customers.
•Asphalt transition over 4 inch temporary jumper for protection at streets crossings.
•Additional traffic control for protection of the jumper lines.
•Cost for demobilization and remobilization for election.
OFFICIAL RECORD
CITY SECRETARY
FT.WORTH,TX
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in
full(both time and money)for all costs arising out of,or incidental to,the above Change Order.
Contractor's Company Name Contractor Name Contractor Signature Date
wfulam a.schnitz,Inc.dba Circle c construction,co. Teri Skelly ]' /,Z•2—-Z.-:J
Inspector., Date Pro ect Manager Date
e 12/5/2022 e 12/06/2022
Director Wate a t) Date Construction Supervisor(T Dept) Date
�' Dec 6,2022 12/06/22
M1rRa"' Nerl6ec6,10]306506n
Assistant City Attorney Date F�aBumhdoff
istant CityManager Date
pawl
m yi a 6rzr,x 6n Dec 8,2022 B 2 :16C5 Dec s,2022
Council Action If Required)
M&C Number N/A M&C Date Approved
F_o__R-r W"R-FYI City of Fort Worth
1W-- J Change Order Additions
Project Name Water&Sanitary Sewer Replacement on Home Street City Sec No.: 57279
Project No.(s): 103123 — � DOE No.E= City Proj.No.: 103123
Project Replacing Water&Sanitary Sewer Lines on Home St.,Carver Dr.,Diaz Ave.,and alleyways.
Description
Contractor William J.Schultz,Inc.dba Circle C Construction,Co. Change Order: Date: 11129/2022
City Project Mgr. �T Pratima Poudyal City Inspector FCodyHorton
ADDITIONS
DEPT Q Unit Unit Cost Total
61 Bored Private Service Unit I Water 40.00 LF $188.00 $7,520.00
62 Temporary 4"Fire Hydrant Jumper Unit I Water 1350.00 LF $28.00 $37,800.00
63 Asphalt Transition Over 4"Pipe Unit I Water 8.00 EA $1,250.00 $10,000.00
64 Traffic Control Unit I Water 3.00 MO $2,250.00 $6,750.00
65 Demobilize and Remobilization for Election Unit I Water 1.00 LS $4,000.00 $4,000.00
Unit I Water $66,070.00
Unit II Sewer
Page 1 of 3 Additions Sub Total $66,070.00
FORT WO R-r A City of Fort Worth
—+ - Change Order Deletions
Project Name Water&Sanitary Sewer Replacement on Horne Street City Sec No.: 57279
Project No.(s): 103123 DOE No. N/A City Proj.No.: 1 103123
Project Description Replacing Water&Sanitary Sewer Lines on Horne St.,Carver Dr.,Diaz Ave.,and alleyways.
Contractor William J.Schultz,Inc.dba Circle C Construction,Co. Change Order: 111 Date 11/29/2022
City Project Mgr. Pratima Poudyal City Inspector: Cody Horton
DELETIONS
ITEM DESCRIPTION DEPT Qty Unit Unit Coat Total
60 Water Construction Allowance Unit I Water 0.4404700 LS $150,000.00 $66,070.50
Unit I Water $66,070.50
Unit II Sewer
Page 2 of 3 Deletions Sub Total $66,070.50
INIWBE Breakdown for this Change Order
MWBE Sub Type of Service Amount for this CO
Total $0.00
Previous Change Orders
CO# DATE AMOUNT
Total $0.00
Page 3 of 3
.Contract Compliance Manager
By signing I acknowledge that I am the person responsible
for the monitoring and administration of this contract,including
ensuring all performance and reporting requirements.
'l
Signature
Pratima Poudyal,P.E.
Name of Employee
Project Manager
Title
p4pAUg4
ATTEST: PaoF FORr��od
04eTi� C57
ette S.Goodall(Dec 9,202216: ST) aaab nEXP`�ooap
Jannette Goodall
City Secretary
OFFICIAL RECORD
CITY SECRETARY
FT.WORTH,TX
11/29/2022
CPN 103123- Horne Street Water&Sanitary Sewer Rehabilitation
Change Request 2 Notes
Staff has reviewed the change order price and considers it to be fair and reasonable.