CITY OF FORT WORTH CONTRACT NOo G• I Zfi�'C�,�
CHANGE ORDER REQUEST
CHANGE ORDER NO. DATE D.O.E. NO. PROJECT NO. City Project 01839
� September 06, 2012 N�A P258 541200 701300183980
PROJECT DESCR[PTION: Village Creek WRF Secondary Clanfier 1— 9 Weir Replacement CITY SECRETARY CONTRACT NO.
43128
ORIGINAL CONTRACT AMOUNT ........................................ $ 339,600.00
EXTRAS TO DATE ............................................ $ 0.00
CREDITS TO DATE ........................................... $ 0.00
CONTRACTCOST TO DATE .......................................................................................................................................................$ 389.600.00
AMOLINT OF PROPOSED CHANGE ORDER .................................................................................................................•--••-----...$ 48.430.61
REVISED CONTRACT AMOiJNT ...................................••---........................................................................................................$ 438.030.61
ORIGINAL FUNDS AVAII.ABLE FOR CHANGE ORDERS .........................................................................................................$ 19.430.00
ADDITIONAL FUNDING (IF NECESSARY) --•• ............................................................................................................................$ 28.950.61
REMAINING FUNDS AVAILABLE FOR CHANGE ORDER ........................................................................................................$ 0.00
IN ACCORDANCE WITH THIS CHANGE ORDER, THE CONTRACTOR SHALL: modify/change the contract as shown below to provide a complete,
functional, and operational plant. These changes are as listed below. Further descriptions and Cost Breakdowns are attached.
CMR001 WEIR ADJLTSTMENTS ------------------------------------------------------------------- ------------- ------------------------------ $40,747.42
The Contractor shall adjust the weir elevations in Final Clarifiers 2, 3, 4, 5, and 7 to accommodate the weir sweep brush assembly and scum
bridges in these clarifiers. The specified weir elevations created conflicts with the brush assemblies and the scum bridges in these clarifiers.
The Contractor provided a cost of $40,747.42 for this work and requested no additional contract time.
CMR-002 ADJiJSTMENTS TO SCiJM BEACH ELEVATIONS ------------------------------------------------------------------------------$7,683.19
The Contractor shall adjust the scum beach elevations in Final Clarifiers 5 and 6 to accommodate the adjusted weir elevations in these
clarifiers. The adjusted weir elevations required a higher elevation for the scum beach to operate properly in these two clarifiers. The
Contractor provided a cost of $7,683.19 for this work and requested no additional contract time.
OFFICIAL RECOR�
f��'. RIVNOR�'H,1'X
The Completion date for e con rac is October 19, 2012.
���u� •��
.:; '�,�'��� � ��' �`
--------TOTAL COST FOR Ct�u�,��Q'RDE1�I0°��
�1
b-- a.�r�,�% �
�, . �� p�eo��. ,;_
� � �� � J�
� o v
� � o �;
� '��,
� ,� /. � ¢��- o �.� �
$48,430.61
- % � r _ _ _ _ — __.-., �u� �� '�'
It is understood and a�Teed [hat the acceptance of this Change Order by the contractor constitutes an accorit�"and satisfaction and represents payment in fu �,'Q�a�Sd money) for all cos[s
arising out of, or incidental to. the Change Order.
MEMORANDUM
DA�: SEP�MSER 06, 2012
To: A� RoBu�sorr, P.E., CaMr DxEssER & McKEE, Irrc.
FROM: MADELENE RAFALKO, P.E., FORT WORTH WATER DEPARTMENT
SUBJECT: VILLAGE CREEK WRF WEIR REPLACEMENT FINAL CLARIFIERS 1- 9
Cz� PRorECTNo. 01839
CMR-001: WE�x AD.TUS�NTS
This office has reviewed your correspondence dated August 14, 2012 regarding the proposed
contract modification (CMR-001) to adjust the specified elevation of Final Clarifiers 2, 3, 4, 5
and 7. The specified weir elevation conflicts with the weir sweep brush assemblies and the scum
beach bridge walkway.
The Water Department agrees with your recommendation that the contractor's cost of
$40,747.42 should be accepted, as the cost is fair and reasonable. The Contractor has not
requested additional time to complete this work. This o�ce will recommend to the City Council
(and/or the City Manager's Office) the approval and acceptance of this cost in the form of a
change order.
Madelene Rafalko, P.E.
Fort Worth Water Department
W:\Groups\Engineering\im-afalko�AA Madelene\CDM General Eng Support\Secondaiy Clarifier Rehab\conshuction\changes\CMROO l.doc
� •
100 Throckmorton Street, Suite 600
Fort Worth, Texas 76102
tel: 817 332-8727
fax: 817 820-0450
August iq., zoia
Ms. Madelene Rafalko
Fort Worth Water Department
Subject: City Secretary Contract No. 43ia8 (M&C Ga547a, March o6, aoia)
City of Fort Worth Village Creelc Water Reclamation Facility
Secondary Weir i-g Replacement
City Project No. oi839
Contractor's Modification Request — Weir Adjustments
Dear Madelene:
Transmitted herewith please find a copy of Archer Westerri s contract modification request
(CMR) to adjust clarifier 2, 3, 4, 5, and 7 weirs to accommodate the brush assembly and scum
beach conflicts. The pricing includes additional labor and material cost for making the weir
adjustrnents. The cost associated with this work is $40,747.42. No change to Contract Time
has been requested.
CDM Smith has reviewed this price proposal and is of the opinion that it is a fair and
equitable price. CDM Smith recommends the City accept this cost and issue a Change Order
in the amount of $40,747.42. Please advise if the Water Department desires this CMR be
incorporated in a Change Order.
Very truly yours,
�o��
Amy Robinson, PE
Senior Project Manager
Camp Dresser & McI<ee Inc.
TBPE Firm No. 3�43
cc I<ent Rilcer, CDM
PW File o515-g33243-�5�o6.qo
Rafalko, CMR-ClarifierWeirAdjustments.doc
CMR
VILLAGE CREEK WWTP
SECONDARY AREA & FILTER REHAB AND MODS
OWNER: CITY OF FORT WORTH TEXAS WORK DESCRIPTION:
Raise Scum Beach at Clarifiers 5& 6
ENGINEER: CDMSmith
page 1
COM'RACTOR: ARCHER WESTERN CONTRACTORS, LTD
212'I AVENUE J, SUITE #103
� AR�INGTON, TEXAS 76006