HomeMy WebLinkAboutContract 58394-PM1CSC No. 58394-PM1 FORT WORTH PROJECT MANUAL FOR THE CONSTRUCTION OF WATER, SANITARY SEWER, PAVING, STREET LIGHTS AND DRAINAGE IMPROVEMENTS FOR RANCH AT DUCK CREEK PHASE 2 Mattie Parker Mayor City Project No. 103754 IPRC21-0126 FID# 30114-0200431-103754-E07685 W- 2808 X-27125 David Cooke City Manager Christopher P. Harder, P.E. Director, Water Department Lauren L. Prieur, P.E. Interim Director, Transportation and Public Works Department Prepared for The City of Fort Worth November, 2022 MArnEw J. BAAC E f •,. 99368 :V 1tci).Ep '4vS GMcivil Engineering &Surveying 2559 SW Grapevine Pkwy. Grapevine, Texas 76051 817.329.4373 OFFICIAL RECORD CITY SECRETARY FT. WORTH, TX SECTION 00 00 00 TABLE OF CONTENTS Division 00 - General Conditions Last Revised 00 05 10 Mayor and Council Communication 07/01/2011 00 05 15 Addenda 07/01/2011 00 11 13 Invitation to Bidders 07/19/2021 00 21 13 Instructions to Bidders 11/02/2021 00 35 13 Conflict of Interest Statement 02/24/2020 00 41 00 Bid Form 09/30/2021 00 42 43 Proposal Form Unit Price 01/20/2012 00 43 13 Bid Bond 09/11/2017 00 43 37 Vendor Compliance to State Law Nonresident Bidder 06/27/2011 00 45 11 Bidders Prequalifications 08/13/2011 00 45 12 Prequalification Statement 09/30/2021 00 45 13 Prequalification Application 08/13/2021 00 45 26 Contractor Compliance with Workers' Compensation Law 07/01/2011 00 45 40 Business Equity Goal 10/27/2021 00 52 43 Agreement 11/23/2021 00 61 13 Performance Bond 07/01/2011 00 61 14 Payment Bond 07/01/2011 00 61 19 Maintenance Bond 07/01/2011 00 61 25 Certificate of Insurance 07/01/2011 00 72 00 General Conditions 08/23/2020 00 73 00 Supplementary Conditions 03/09/2020 Division 01 - General Requirements Last Revised 01 11 00 Summary of Work 12/20/2012 01 25 00 Substitution Procedures 07/01/2011 01 31 19 Preconstruction Meeting 08/17/2012 01 31 20 Project Meetings 07/01/2011 01 32 16 Construction Schedule 08/13/2011 01 32 33 Preconstruction Video 07/01/2011 01 33 00 Submittals 12/20/2012 01 35 13 Special Project Procedures 12/20/2012 01 45 23 Testing and Inspection Services 03/09/2020 01 50 00 Temporary Facilities and Controls 07/01/2011 01 55 26 Street Use Permit and Modifications to Traffic Control 03/22/2021 01 57 13 Storm Water Pollution Prevention Plan 07/01/2011 01 58 13 Temporary Project Signage 07/01/2011 01 60 00 Product Requirements 03/09/2020 01 66 00 Product Storage and Handling Requirements 07/01/2011 01 70 00 Mobilization and Remobilization 11/22/2016 01 71 23 Construction Staking and Survey 02/14/2018 01 74 23 Cleaning 07/01/2011 01 77 19 Closeout Requirements 03/22/2021 01 78 23 Operation and Maintenance Data 12/20/2012 01 78 39 Project Record Documents 07/01/2011 00 00 00 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Page 1 of 8 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS CPN #103754 Revised December 9, 2021 Technical Specifications which have been modified by the Engineer specifically for this Project; hard copies are included in the Project’s Contract Documents NONE Technical Specifications listed below are included for this Project by reference and can be viewed/downloaded from the City’s website at: 00 00 00 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Page 2 of 8 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS CPN #103754 Revised December 9, 2021 http://fortworthtexas.gov/tpw/contractors/ or https://apps.fortworthtexas.gov/ProjectResources/ [Only list the Standard Specifications the Engineer has determined are appropriate for this specific project and strike through the Specifications not applicable to the project.] Division 02 - Existing Conditions Last Revised 02 41 13 Selective Site Demolition 12/20/2012 02 41 14 Utility Removal/Abandonment 12/20/2012 02 41 15 Paving Removal 02/02/2016 Division 03 - Concrete 03 30 00 Cast-In-Place Concrete 12/20/2012 03 34 13 Controlled Low Strength Material (CLSM) 12/20/2012 03 34 16 Concrete Base Material for Trench Repair 12/20/2012 03 80 00 Modifications to Existing Concrete Structures 12/20/2012 Division 26 - Electrical 26 05 00 Common Work Results for Electrical 11/22/2013 26 05 10 Demolition for Electrical Systems 12/20/2012 26 05 33 Raceways and Boxes for Electrical Systems 12/20/2012 26 05 43 Underground Ducts and Raceways for Electrical Systems 07/01/2011 26 05 50 Communications Multi-Duct Conduit 02/26/2016 Division 31 - Earthwork 31 00 00 Site Clearing 03/22/2021 31 23 16 Unclassified Excavation 01/28/2013 31 23 23 Borrow 01/28/2013 31 24 00 Embankments 01/28/2013 31 25 00 Erosion and Sediment Control 04/29/2021 31 36 00 Gabions 12/20/2012 31 37 00 Riprap 12/20/2012 Division 32 - Exterior Improvements 32 01 17 Permanent Asphalt Paving Repair 12/20/2012 32 01 18 Temporary Asphalt Paving Repair 12/20/2012 32 01 29 Concrete Paving Repair 12/20/2012 32 11 23 Flexible Base Courses 12/20/2012 32 11 29 Lime Treated Base Courses 12/20/2012 32 11 33 Cement Treated Base Courses 12/20/2012 32 11 37 Liquid Treated Soil Stabilizer 08/21/2015 32 12 16 Asphalt Paving 12/20/2012 32 12 73 Asphalt Paving Crack Sealants 12/20/2012 32 13 13 Concrete Paving 03/19/2021 32 13 20 Concrete Sidewalks, Driveways and Barrier Free Ramps 12/09/2021 32 13 73 Concrete Paving Joint Sealants 12/20/2012 32 14 16 Brick Unit Paving 12/20/2012 00 00 00 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Page 3 of 8 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS CPN #103754 Revised December 9, 2021 32 16 13 Concrete Curb and Gutters and Valley Gutters 12/09/2021 32 17 23 Pavement Markings 11/22/2013 32 17 25 Curb Address Painting 11/04/2013 32 31 13 Chain Fences and Gates 12/20/2012 32 31 26 Wire Fences and Gates 12/20/2012 32 31 29 Wood Fences and Gates 12/20/2012 32 32 13 Cast-in-Place Concrete Retaining Walls 06/05/2018 32 91 19 Topsoil Placement and Finishing of Parkways 12/20/2012 32 92 13 Sodding 05/13/2021 32 92 14 Non-Native Seeding 05/13/2021 32 93 43 Trees and Shrubs 12/20/2012 Division 33 - Utilities 33 01 30 Sewer and Manhole Testing 9/07/2018 33 01 31 Closed Circuit Television (CCTV) Inspection 04/29/2021 33 03 10 Bypass Pumping of Existing Sewer Systems 12/20/2012 33 04 10 Joint Bonding and Electrical Isolation 12/20/2012 33 04 11 Corrosion Control Test Stations 12/20/2012 33 04 12 Magnesium Anode Cathodic Protection System 12/20/2012 33 04 30 Temporary Water Services 07/01/2011 33 04 40 Cleaning and Acceptance Testing of Water Mains 02/06/2013 33 04 50 Cleaning of Sewer Mains 12/20/2012 33 05 10 Utility Trench Excavation, Embedment, and Backfill 04/02/2021 33 05 12 Water Line Lowering 12/20/2012 33 05 13 Frame, Cover and Grade Rings 12/09/2021 33 05 14 Adjusting Manholes, Inlets, Valve Boxes, and Other Structures to Grade 09/20/2017 33 05 16 Concrete Water Vaults 12/20/2012 33 05 17 Concrete Collars 12/20/2012 33 05 20 Auger Boring 12/20/2012 33 05 21 Tunnel Liner Plate 12/20/2012 33 05 22 Steel Casing Pipe 12/20/2012 33 05 23 Hand Tunneling 12/20/2012 33 05 24 Installation of Carrier Pipe in Casing or Tunnel Liner Plate 06/19/2013 33 05 26 Utility Markers/Locators 12/20/2012 33 05 30 Location of Existing Utilities 12/20/2012 33 11 05 Bolts, Nuts, and Gaskets 12/20/2012 33 11 10 Ductile Iron Pipe 12/20/2012 33 11 11 Ductile Iron Fittings 09/20/2017 33 11 12 Polyvinyl Chloride (PVC) Pressure Pipe 11/16/2018 33 11 13 Concrete Pressure Pipe, Bar-Wrapped, Steel Cylinder Type 12/20/2012 33 11 14 Buried Steel Pipe and Fittings 12/20/2012 33 12 10 Water Services 1-inch to 2-inch 02/14/2017 33 12 11 Large Water Meters 12/20/2012 33 12 20 Resilient Seated Gate Valve 05/06/2015 33 12 21 AWWA Rubber-Seated Butterfly Valves 04/23/2019 33 12 25 Connection to Existing Water Mains 02/06/2013 33 12 30 Combination Air Valve Assemblies for Potable Water Systems 12/20/2012 00 00 00 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Page 4 of 8 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS CPN #103754 Revised December 9, 2021 33 12 40 Fire Hydrants 01/03/2014 33 12 50 Water Sample Stations 12/20/2012 33 12 60 Standard Blow-off Valve Assembly 06/19/2013 33 31 12 Cured in Place Pipe (CIPP) 12/20/2012 33 31 13 Fiberglass Reinforced Pipe for Gravity Sanitary Sewers 12/20/2012 33 31 15 High Density Polyethylene (HDPE) Pipe for Sanitary Sewer 04/23/2019 33 31 20 Polyvinyl Chloride (PVC) Gravity Sanitary Sewer Pipe 06/19/2013 33 31 21 Polyvinyl Chloride (PVC) Closed Profile Gravity Sanitary Sewer Pipe 12/20/2012 33 31 22 Sanitary Sewer Slip Lining 12/20/2012 33 31 23 Sanitary Sewer Pipe Enlargement 12/20/2012 33 31 50 Sanitary Sewer Service Connections and Service Line 04/26/2013 33 31 70 Combination Air Valve for Sanitary Sewer Force Mains 12/20/2012 33 39 10 Cast-in-Place Concrete Manholes 12/20/2012 33 39 20 Precast Concrete Manholes 12/20/2012 33 39 30 Fiberglass Manholes 12/20/2012 33 39 40 Wastewater Access Chamber (WAC) 12/20/2012 33 39 60 Liners for Sanitary Sewer Structures 04/29/2021 33 41 10 Reinforced Concrete Storm Sewer Pipe/Culverts 07/01/2011 33 41 11 High Density Polyethylene (HDPE) Pipe for Storm Drain 12/20/2012 33 41 12 Reinforced Polyethylene (SRPE) Pipe 11/13/2015 33 41 13 Polypropylene Pipe for Storm Drain 4/02/2021 33 46 00 Subdrainage 12/20/2012 33 46 01 Slotted Storm Drains 07/01/2011 33 46 02 Trench Drains 07/01/2011 33 49 10 Cast-in-Place Manholes and Junction Boxes 12/20/2012 33 49 20 Curb and Drop Inlets 12/20/2012 33 49 40 Storm Drainage Headwalls and Wingwalls 07/01/2011 Division 34 - Transportation 34 41 10 Traffic Signals 10/12/2015 34 41 10.01 Attachment A – Controller Cabinet 12/18/2015 34 41 10.02 Attachment B – Controller Specification 02/2012 34 41 10.03 Attachment C – Software Specification 01/2012 34 41 11 Temporary Traffic Signals 11/22/2013 34 41 13 Removing Traffic Signals 12/20/2012 34 41 15 Rectangular Rapid Flashing Beacon 11/22/2013 34 41 16 Pedestrian Hybrid Signal 11/22/2013 34 41 20 Roadway Illumination Assemblies 12/20/2012 34 41 20.01 Arterial LED Roadway Luminaires 06/15/2015 34 41 20.02 Freeway LED Roadway Luminaires 06/15/2015 34 41 20.03 Residential LED Roadway Luminaires 06/15/2015 34 41 30 Aluminum Signs 11/12/2013 34 41 50 Single-Mode Fiber Optic Cable 02/26/2016 34 71 13 Traffic Control 03/22/2021 00 00 00 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Page 5 of 8 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS CPN #103754 Revised December 9, 2021 Appendix GC-4.01 Availability of Lands GC-4.02 Subsurface and Physical Conditions GC-4.04 Underground Facilities GC-4.06 Hazardous Environmental Condition at Site GC-6.06.D Minority and Women Owned Business Enterprise Compliance GC-6.07 Wage Rates GC-6.09 Permits and Utilities GC-6.24 Nondiscrimination GR-01 60 00 Product Requirements END OF SECTION DIVISION 00 GENERAL CONDITIONS UTILITIES PAVING r UNIT PRICE BID Bidlist I Item SECTION 00 42 43 Developer Awarded Projects - PROPOSAL FORM Ranch at Duck Creek, Phase 2, City Project #103754 Project Item Information Description Specification I Unit of Section No. Measure Bid OuantiPi Unit Price I Bid Value Water Facilities 1 0241.1118 4"-12" Pressure Plup 02 41 14 EA 2 $1.000.00 $2 000.00 2 3305.0109 Trench Safe-v 33 05 10 LF 8.684 $1.00 $8,684.00 3 3311.0001 Ductile Iron Water Fittin.is w/ Restraint 33 11 11 TON 1.9 $6.500.00 $12,350.00 4 3311.0241 8" PVC Water Pipe 33 11 10, LF 7,769 $48.00 $372,912.00 33 11 12 5 3311.0241 8" PVC Water Pipe, CSS Back -fill 331110, LF 300 $58.00 $17,400.00 6 3311.0541 16" Water Pipe 11 13' LF 595 $156.00 $92,820.00 33 11 12 7 3311.0541 16" Water Pipe, CSS Backfill 3311 10, LF 20 $176.00 $3,520.00 33 11 12 8 3312.0001 Std. Fire Hydrant Assembly wl 6" Gate Valve & Valve Box 33 12 40 EA 7 $4.800.00 $33,600.00 9 3312.0106 Connection to Existing 16" W.L. 33 12 25 EA 1 $2,500.00 $2.500.00 10 3312.2003 1" Domestic Water Services 33 1210 EA 194 $1.100.00 $213,400.00 11 3312.3003 8" Gate Valve & Valve Box 33 12 20 EA 32 $1,450.00 $46,400.00 12 3312.3006 16" Gate Valve w/ Vault 33 12 20 EA 1 S22.500.00 $22.500.00 Water Subtotal $828,086.00 Sanitary Sewer Facilities 13 3301.0602 Post -CCTV Inspection 33 01 31 LF 7 475 $4.00 $29.900.00 14 3301.0101 Vacuum Test Manholes 33 01 30 EA 36 $150.00 $5.400.00 15 3305.0109 Trench Safety 33 05 10 LF 7 475 $2.00 514 950.00 16 3305.0113 Trench Water Stops 33 05 15 EA 19 $500.00 $9.500.00 17 3331.3101 SDR-26 4" Sewer Services 33 31 50 EA 194 $850.00 $164,900.00 3311 10, 18 3331.4115 8" SDR-26 PVC Sewer Pipe 33 31 12, LF 6,758 $52.00 $351,416.00 33 31 20 19 3331.4116 8" PVC Sanitary Sewer Pipe w/ CSS Backfill 33 11 10, LF 547 $62.00 $33,914.00 33 11 12 33 11 10, 20 3331.4208 12" Sewer Pipe 33 31 12, LF 170 $82.00 $13,940.00 21 3339.1001 4' Std. Dia. Manhole 33 3 1 EA 36 $4,500.00 $162,000.00 _ 33 39 20 22 3339.1003 4' Extra Depth Manhole 33 39 10, VF 97 $215.00 $20,855.00 33 39 20 tanitary Sewer Subtotal $806,775.00 Storm Drain Facilities 23 3137.0102 Lar-,e Stone Ri.prap, dry 31 37 00 SY 22 s125.00 $2 750.00 24 3137.0104 Medium Stone Iiprap, dry 31 37 00 SY 234 $115.00 $26 910.00 25 3305.0112 Concrete Collar 33 05 17 EA 6 $1 000.00 $6 000.00 26 3305.0109 Trench Safety 33 05 10 LF 4 358 $1.00 $4,358.00 27 3349.5001 10' Curb Inlet 33 49 20 EA 20 $4 200.00 $84.000.00 28 3349.5002 15' Curb Inlet 34 49 20 EA 2 $5.200.00 $10.400.00 29 3349.7001 4' Drop Inlet 33 49 20 EA 2 $6.000.00 $12.000.00 30 3349.7002 5' Drop Inlet 35 49 20 EA 2 27.500.00 $15,000.00 31 3341.0201 21" RCP, Class III 33 41 10 LF 416 $75.00 $31,200.00 32 3341.0205 24" RCP, Class III 33 41 10 LF 78 385.00 $6,630.00 33 3341.0208 27" RCP, Class III 33 41 10 LF 217 $90.00 $19,530.00 34 3341.0309 36" RCP, Class III 33 41 10 LF 287 $130.00 $37.310.00 35 3341.0402 42" RCP, Class III 33 41 10 LF 1 439 $165.00 $237,435.00 36 3341.0409 48" RCP, Class III 33 41 10 LF 483 $185.00 $89,355.00 37 3349.0001 4' Storm Junction Box 33 49 10 EA 5 $6.000.00 $30 000.00 38 3349.0002 5' Storm Junction Box 33 49 10 EA 6 $7,000.00 $42,000.00 39 3349.0003 6' Storm Junction Box 33 49 10 EA 1 38.500.00 $8,500.00 40 3349.0102 4' Manhole Riser 33 49 10 EA 2 $5.000.00 $10,000.00, 41 3349.4111 42" SET, 1 pipe 33 49 40 EA 1 $6 500.00 $6.500.00 42 9999.0001 42" RCP End & PIuD 00 00 00 EA 1 '31.000.00 $1.000.00 43 3341.1103 4' x 4' RCB 33 41 10 LF 323 $260.00 $83.980.00 44 3341.1402 7' x 4' RCB 33 41 10 LF 248 $475.00 $117,800.00 45 9999.0002 8' x 3' RCB 00 00 00 LF 377 $495.00 $186,615.00 46 3341.1501 (7} 8' x 4' RCB 33 41 10 LF 490 $550.00 $269,500.00 47 9999.0003 8' x 3' Sloped -End Headwall 00 00 00 EA _ 1 $12 500.00 $12,500.00 48 9999.0004 (7,1 8' x 4' Headwall w/ Straight Wingwalls 00 00 00 EA 1 $72 500.00 $72 500.00 49 9999.0005 i 1 8' x 4' Headwall w/ Flared Wingwalls 00 00 00 EA 1 $77 500.00 $77,500.00 50 9999.0006 Pedestrian Rail 00 00 00 LF 159 $240.00 $38 160.00 torm Drain Subtotal $1,539,433.00 Water/Sanitary Sewer/Storm Drain Facilities Subtotal $3,174,294.00! CITY OF FORT WORTH STANDARD CONSTRUCTION BID PROPOSAL -DEVELOPER AWARDED PROJECTS Forth Revised January 29, 2020 Ranch el Duck Creek Phdse 2 City P jcct#103754 00 42 43Bid Proposal 11/04/2022 11/04/2022 10/31/23 XXXXXX 00 45 26 - 1 CONTRACTOR COMPLIANCE WITH WORKER'S COMPENSATION LAW Page 1 of 1 SECTION 00 45 26 CONTRACTOR COMPLIANCE WITH WORKER'S COMPENSATION LAW Pursuant to Texas Labor Code Section 406.096(a), as amended, Contractor certifies that it provides worker's compensation insurance coverage for all of its employees employed on City Project No. 103754 . Contractor further certifies that, pursuant to Texas Labor Code, Section 406.096(b), as amended, it will provide to City its subcontractor's certificates of compliance with worker's compensation coverage. CONTRACTOR: Conatser Construction TX. L.P. Company 5327 Wichita Street Address Ft. Worth. TX 76119 City/State/Zip THE STATE OF TEXAS COUNTY OF TARRANT By: Signature: Title: Brock Hunks President BEFORE ME, the undersigned authority, on this day personally appeared fyrDG dug! lS , known to me to be the person whose name is subscribed to the foregoing instrument, an acknowledged to me that he/she executed the same as the act and deed of P S I .and for the purposes and consideration therein expressed and in the capacity therein stated. "" GIVEN UNDER MY HAND AND SEAL OF OFFICE this (0 day of C obo-- , 2022. KATHRINE ROSE NOTARY PUBLIC ID# 133467933 State of Texas Comm. Exp. 11-30-2025 K Notary Public in and for the State of Texas END OF SECTION CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised April 2, 2014 Ranch at Duck Creek Phase 2 CPN 103754 11/04/2022 005243-2 Developer Awarded Project Agreement Page 2 of 4 Article 4. CONTRACT PRICE Developer agrees to pay Contractor for performance of the Work in accordance with the Contract Documents an amount in current funds of Four Million Six Hundred Sixtv Nine Thousand Eight Hundred Fiftv 4 00/100 Dollars (S4.669.850.00) . Article 5. CONTRACT DOCUMENTS 5.1 CONTENTS: A. The Contract Documents which comprise the entire agreement between Developer and Contractor concerning the Work consist of the following: 1. This Agreement. 2. Attachments to this Agreement: a. Bid Form (As provided by Developer) 1) Proposal Form (DAP Version) 2) Prequalification Statement 3) State and Federal documents (project specific) b. Insurance ACORD Form(s) c. Payment Bond (DAP Version) d. Performance Bond (DAP Version) e. Maintenance Bond (DAP Version) f. Power of Attorney for the Bonds g. Worker's Compensation Affidavit h. MBE and/or SBE Commitment Form (If required) 3. Standard City General Conditions of the Construction Contract for Developer Awarded Projects. 4. Supplementary Conditions. 5. Specifications specifically made a part of the Contract Documents by attachment or, if not attached, as incorporated by reference and described in the Table of Contents of the Project's Contract Documents. 6. Drawings. 7. Addenda. 8. Documentation submitted by Contractor prior to Notice of Award. 9. The following which may be delivered or issued after the Effective Date of the Agreement and, if issued, become an incorporated part of the Contract Documents: a. Notice to Proceed. b. Field Orders. c. Change Orders. d. Letter of Final Acceptance. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS —DAP Revised June 16, 2016 Ranch at Duck Creek Phase 2 CPN 103754 00 52 43 - 3 Developer Awarded Project Agreement Page 3 of 4 Article 6. INDEMNIFICATION 6.1 Contractor covenants and agrees to indemnify, hold harmless and defend, at its own expense, the city, its officers, servants and employees, from and against any and all claims arising out of, or alleged to arise out of, the work and services to be performed by the contractor, its officers, agents, employees, subcontractors, licenses or invitees under this contract. This indemnification provision is snecificallv intended to operate and be effective even if it is alleged or nroven that all or some of the damages being sou ht were caused. in whole or in Hart. by anv act. omission or negligence of the city. This indemnity provision is intended to include, without limitation, indemnity for costs, expenses and legal fees incurred by the city in defending against such claims and causes of actions. 6.2 Contractor covenants and agrees to indemnify and hold harmless, at its own expense, the city, its officers, servants and employees, from and against any and all loss, damage or destruction of property of the city, arising out of, or alleged to arise out of, the work and services to be performed by the contractor, its officers, agents, employees, subcontractors, licensees or invitees under this contract. This indemnification provision is specifically intended to operate and be effective even if it is alleged or proven that all or some of the damages beine soueht were caused. in whole or in Dart. by anv act. omission or negligence of the city. Article 7. MISCELLANEOUS 7.1 Terms. Terms used in this Agreement are defined in Article 1 of the Standard City Conditions of the Construction Contract for Developer Awarded Projects. 7.2 Assignment of Contract. This Agreement, including all of the Contract Documents may not be assigned by the Contractor without the advanced express written consent of the Developer. 7.3 Successors and Assigns. Developer and Contractor each binds itself, its partners, successors, assigns and legal representatives to the other party hereto, in respect to all covenants, agreements and obligations contained in the Contract Documents. 7.4 Severability. Any provision or part of the Contract Documents held to be unconstitutional, void or unenforceable by a court of competent jurisdiction shall be deemed stricken, and all remaining provisions shall continue to be valid and binding upon DEVELOPER and CONTRACTOR. 7.5 Governing Law and Venue. This Agreement, including all of the Contract Documents is performable in the State of Texas. Venue shall be Tarrant County, Texas, or the United States District Court for the Northern District of Texas, Fort Worth Division. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS —DAP Revised June 16, 2016 Ranch at Duck Creek Phase 2 CPN 103754 11/04/2022 11/04/2022 4th November 4th November 4th November 4th November 4th November 0062It)-2 MAINTI:`ANC1: Cit)NI) Page 2of3 WHEREAS. Principal binds itself to repair or reconstruct the Work in whole or in part upon receiving notice from the Developer and/or City of the need thereof at any time within the Maintenance Period. NOW THEREFORE. the condition of this obligation is such that if Principal shall remedy any defective Work. for which timely notice was provided by Developer or City, to a completion satisfactory to the City. then this obligation shall become null and void; otherwise to remain in full force and effect. PROVIDED, HOWEVER, if Principal shall fail so to repair or reconstruct any timely noticed defective Work. it is agreed that the Developer or City may cause an) and all such detective Work to be repaired and/or reconstructed with all associated costs thereof being borne by the Principal and the Surety under this Maintenance Bond: and PROVIDED FURTHER. that if any legal action be filed on this Bond. venue shall lie in Tarrant County. Texas or the United States District Court for the Northern District of Texas, Fort Worth Division: and PROVIDED FURTHER, that this obligation shall be continuous in nature and successive recoveries may be had hereon for successive breaches. MY Y OF t c )RT WORTI-I STANDARD cm( CONDI PIONS - I)tivIiLOPI:R AWARDED PRC)JEcTs Revised January 31. 2012 Ranch at Duck Creek Phase 2 CPN 103754 4th November 4th November 2022 IMPORTANT NOTICE To obtain information or make a complaint: You may call Berkley Surety Group, LLC and its affiliates by telephone for information or to make a complaint: BERKLEY SURETY GROUP, LLC Please send all notices of claim on this bond to: Berkley Surety Group, LLC (866) 768-3534 412 Mount Kemble Avenue, Suite 310N Morristown, NJ 07960 Attn: Surety Claims Department You may contact the Texas Department of Insurance to obtain information on companies, coverages, rights or complaints at: 1-800-252-3439 You may write the Texas Department of Insurance: P. O. Box 149104 Austin, TX 78714-9104 Fax: (512) 475-1771 Web: http:llwww.tdi.state.tx.us E-mail: ConsumerProtection(a.tdi.state.tx.us PREMIUM OR CLAIM DISPUTES: Should you have a dispute concerning your premium or about a claim you should contact your agent or Berkley Surety Group, LLC first. If the dispute is not resolved, you may contact the Texas Department of Insurance. ATTACH THIS NOTICE TO YOUR BOND: This notice is for information only and does not become a part or condition of the attached document and is given to comply with Texas legal and regulatory requirements. LIGHTING UNIT PRICE BID Bidlist Item SECTION 00 42 43 Developer Awarded Projects - PROPOSAL FORM Ranch at Duck Creek, Phase 2, City Project #103754 Project Item Information Description Specification (Unit of Section No. Measure Street Lighting Facilities 1 2605.3011 2" CONDT PVC SCH 40 (T) 2 3441.1408 NO 6 Insulated Elec Condr 3 3441.1633 Type 33B Arm 4 3441.3201 LED Lighting Fixture (R-2) 5 3441.3201 LED Lighting Fixture (R-4) 6 3441.3301 Rdwy Illum Foundation TY 1,2, and 4 7 3441.3341 Rdwy Illum TY 11 Pole Street Lighting Subtotal Bid Quantity Unit Price IUC Bid Value 26 05 33 LF 4,080 $15.39 $62,791.20 34 41 10 LF 12,240 $2.26 $27,662.40 34 41 20 EA 36 $254.00 $9,144.00 34 41 20 EA 35 $331.00 $11,585.00 34 41 20 EA 1 $331.00 $331.00 35 41 20 EA 36 $1,442.00 $51,912.00 34 41 20 EA 36 $2,067.00 $74,412.00 $237,837.60 Bid Summary Street Lighting Facilities Subtotal Total Bid Performance/Payment and 2-year Maintenance Bonds Grand Total This bid is submitted by the entity listed below: Company: Independent Utility By: Richard Wolf Construction, Inc. Signature Street Address: 5109 Sun Valley Drive Title: President J City, State, Zip Code: Ft. Worth, TX 76119 Date: 8/25/2022 Phone: 817-478-4444 $237,837.60 $237,837.60 $0.00 $237,837.60 Contractor agrees to complete WORK for FINAL ACCEPTANCE within 40 working days after the date when the CONTRACT commences to run as provided in the General Conditions. END OF SECTION CITY OF FORT WORTH STANDARD CONSTRUCTION BID PROPOSAL -DEVELOPER AWARDED PROJECTS Form Revised January 29, 2020 Ranch at Duck Creek, Phase 2 City Project # 103754 00 42 4 3_Bid Proposal 00 45 12 DAP PR.EQUALIFICATION STATEMENT Page 1 of 1 SECTION 00 45 12 DAP — PREQUALIFICATION STATEMENT Each Bidder is required to complete the information below by identifying the prequalified contractors and/or subcontractors whom they intend to utilize for the major work type(s) listed. In the "Maior Work Type" box provide the complete major work type and actual description as provided by the Water Department for water and sewer and TPW for paving. Roadway and Pedestrian Lighting Contractor/Subcontractor Company Name Prequalification Expiration Date Independent Utility Construction, Inc. 03-01-2023 The undersigned hereby certifies that the contractors and/or subcontractors described in the table above are currently prequalified for the work types listed. BIDDER: Independent Utility Construction, Inc. BY• Ri4hard Wolfe 5109 Sun Valley Drive Ft. Worth, TX 76119 ture) TITLE: President DATE: 8/25/2022 END OF SECTION CITY OF FORT WORTH STANDARD CONSTRUCTION PREQUALIFICATION STATEMENT — DEVELOPER AWARDED PROJECTS Form Version September 1, 2015 Ranch at Duck Creek Phase 2 CPN 103754 00 45 26 - 1 CONTRACTOR COMPLIANCE WITH WORKERS COMPENSATION LAW Page 1 of 1 SECTION 00 45 26 CONTRACTOR COMPLIANCE WITH WORKER'S COMPENSATION LAW Pursuant to Texas Labor Code Section 406.096(a), as amended, Contractor certifies that it provides worker's compensation insurance coverage for all of its employees employed on City Project No. 103754 . Contractor further certifies that, pursuant to Texas Labor Code, Section 406.096(b), as amended, it will provide to City its subcontractor's certificates of compliance with worker's compensation coverage. CONTRACTOR: Independent Utility Construction, Inc. By: Company 5109 Sun Valley Drive Signature: Address Ft. Worth, TX 76119 Title: City/State/Zip THE STATE OF TEXAS COUNTY OF TARRANT § Richard Wolfe President BEFORE ME, the undersigned authority, on this day personally appeared Richard Wolfe , known to me to be the person whose name is subscribed to the foregoing instrument, and acknowledged to me that he/she executed the same as the act and deed of Independent Utility Construction, Inc. for the purposes and consideration therein expressed and in the capacity therein stated. G EN UNDER MY HAND AND SEAL OF OFFICE this \� day of , 2022. ttT4tCHRISTINA GARCIA .•=Notary Public, State of Texas tkp•'_. r . Comm. Expires 12-20-2024 1'1.4'1 .1-0 Notary ID 130940785 Llt1IJ' )F SECTION CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised April 2, 2014 ary Public in and for the State of Texas Ranch at Duck Creek Phase 2 CPN 103754 11/04/2022 00 52 43 - 2 Developer Awarded Project Agreement Page 2 of 4 Article 4. CONTRACT PRICE Developer agrees to pay Contractor for performance of the Work in accordance with the Contract Documents an amount in current funds of Two Hundred Thirty Seven Thousand Eight Hundred Thirty Seven & 60/100 Dollars ($237,837.60) Article 5. CONTRACT DOCUMENTS 5.1 CONTENTS: A. The Contract Documents which comprise the entire agreement between Developer and Contractor concerning the Work consist of the following: 1. This Agreement. 2. Attachments to this Agreement: a. Bid Form (As provided by Developer) 1) Proposal Form (DAP Version) 2) Prequalification Statement 3) State and Federal documents (project specific) b. Insurance ACORD Form(s) c. Payment Bond (DAP Version) d. Performance Bond (DAP Version) e. Maintenance Bond (DAP Version) f. Power of Attorney for the Bonds g. Worker's Compensation Affidavit h. MBE and/or SBE Commitment Form (If required) 3. Standard City General Conditions of the Construction Contract for Developer Awarded Projects. 4. Supplementary Conditions. 5. Specifications specifically made a part of the Contract Documents by attachment or, if not attached, as incorporated by reference and described in the Table of Contents of the Project's Contract Documents. 6. Drawings. 7. Addenda. 8. Documentation submitted by Contractor prior to Notice of Award. 9. The following which may be delivered or issued after the Effective Date of the Agreement and, if issued, become an incorporated part of the Contract Documents: a. Notice to Proceed. b. Field Orders. c. Change Orders. d. Letter of Final Acceptance. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS —DAP Revised June 16, 2016 Ranch at Duck Creek Phase 2 CPN 103754 005243-3 Developer Awarded Project Agreement Page 3 of 4 Article 6. INDEMNIFICATION 6.1 Contractor covenants and agrees to indemnify, hold harmless and defend, at its own expense, the city, its officers, servants and employees, from and against any and all claims arising out of, or alleged to arise out of, the work and services to be performed by the contractor, its officers, agents, employees, subcontractors, licenses or invitees under this contract. This indemnification provision is specifically intended to operate and be effective even if it is alleged or proven that all or some of the damages being sought were caused, in whole or in part, by anv act, omission or negligence of the city. This indemnity provision is intended to include, without limitation, indemnity for costs, expenses and legal fees incurred by the city in defending against such claims and causes of actions. 6.2 Contractor covenants and agrees to indemnify and hold harmless, at its own expense, the city, its officers, servants and employees, from and against any and all loss, damage or destruction of property of the city, arising out of, or alleged to arise out of, the work and services to be performed by the contractor, its officers, agents, employees, subcontractors, licensees or invitees under this contract. This indemnification provision is specifically intended to operate and be effective even if it is alleged or, proven that all or some of the damages being sought were caused, in whole or in part, by anv act, omission or negligence of the city. Article 7. MISCELLANEOUS 7.1 Terms. Terms used in this Agreement are defined in Article 1 of the Standard City Conditions of the Construction Contract for Developer Awarded Projects. 7.2 Assignment of Contract. This Agreement, including all of the Contract Documents may not be assigned by the Contractor without the advanced express written consent of the Developer. 7.3 Successors and Assigns. Developer and Contractor each binds itself, its partners, successors, assigns and legal representatives to the other party hereto, in respect to all covenants, agreements and obligations contained in the Contract Documents. 7.4 Severability. Any provision or part of the Contract Documents held to be unconstitutional, void or unenforceable by a court of competent jurisdiction shall be deemed stricken, and all remaining provisions shall continue to be valid and binding upon DEVELOPER and CONTRACTOR. 7.5 Governing Law and Venue. This Agreement, including all of the Contract Documents is performable in the State of Texas. Venue shall be Tarrant County, Texas, or the United States District Court for the Northern District of Texas, Fort Worth Division. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS —DAP Revised June 16, 2016 Ranch at Duck Creek Phase 2 CPN 103754 11/04/2022 4th November 22 4th November 22 4th November 22 4th November 22 4th November 22 0062 19-2 MAINTENANCE BOND Page 2 01'3 Bond No. 204149J WHEREAS, Principal hinds itself to repair or reconstruct the Work in whole or in part 2 upon receiving notice from the Developer and/or City of the need thereof at any time within the 3 Maintenance Period. 4 5 NOW THEREFORE, the condition of this obligation is such that if Principal shall 6 remedy any defective Work, for which timely notice was provided by Developer or City, to a 7 completion satisfactory to the City, then this obligation shall become null and void; otherwise to 8 remain in full force and effect. 9 10 PROVIDED, HOWEVER, if Principal shall fail so to repair or reconstruct any timely 11 noticed defective Work, it is agreed that the Developer or City may cause any and all such 12 defective Work to be repaired and/or reconstructed with all associated costs thereof being borne 13 by the Principal and the Surety under this Maintenance Bond; and 14 15 PROVIDED FURTHER, that if any legal action be filed on this Bond, venue shall lie in 16 Tarrant County, Texas or the United States District Court for the Northern District of Texas, Fort 17 Worth Division; and 18 19 PROVIDED FURTHER, that this obligation shall be continuous in nature and 20 successive recoveries may be had hereon for successive breaches. 21 22 23 CITY OF FORT WORTH STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS Revised January 31; 2012 Ranch at Duck Creek Phase 2 City Project No. 103754 4th November 22 IMPORTANT NOTICE To obtain information or make a complaint: You may call Westfield Insurance Company's and/or Ohio Farmers Insurance Company's toll -free telephone number for information or to make a complaint at: 1-800-368-3597 You may also write to Westfield insurance Company and/or Ohio Farmers Insurance Company at: 555 Republic Drive, Suite 450 Plano, Texas 75074-8848 You may contact the Texas Department of Insurance to obtain information on companies, coverages, rights or complaints at: 1-800-252-3439 You may write the Texas Department of Insurance: P. O. Box 149104 Austin, TX 78714-9104 Fax: (512) 475-1771 Web: http://www.tdi.state.tx.us E-mail: ConsumerProtection(c�tdi.state.tx.us PREMIUM OR CLAIM DISPUTES: Should you have a dispute concerning your premium or about a claim you should contact the agent or Westfield Insurance Company and/or Ohio Farmers Insurance Comapny first. If the dispute is not resolved, you may contact the Texas Department of Insurance. ATTACH THIS NOTICE TO YOUR POLICY: This notice is for information only and does not become a part or condition of the attached document. AVISO IMPORTANTE Para obtener informacion o para someter una queja: Usted puede Ilamar al numero de telefono gratis de Westfield Insurance Company's / Ohio Farmers Insurance Company's para informacion o para someter una queja al: 1-800-368-3597 Usted tambien puede escribir a Westfield Insurance Company / Ohio Farmers Insurance Company: 555 Republic Drive, Suite 450 Plano, Texas 75074-8848 Puede comunicarse con el Departamento de Seguros de Texas para obtener informacion acerca de companias, coberturas, derechos o quejas al: 1-800-252-3439 Puede escribir al Departamento de Seguros de Texas: P. O. Box 149104 Austin, TX 78714-9104 Fax: (512) 475-1771 Web: http://www.tdi.state.tx.us E-mail: ConsumerProtection(a�tdi.state.tx.us DISPUTAS SOBRE PRIMAS 0 RECLAMOS: Si tiene una disputa concerniente a su prima o a un reclamo, debe comunicarse con el agente o Westfield Insurance Company / Ohio Farmers Insurance Company primero. Si no se resuelve la disputa, puede entonces comunicarse con el departamento (TDI). UNA ESTE AVISO A SU POLIZA: Este aviso es solo para proposito de informacion y no se convierte en parte o condicion del documento adjunto. 4thNovember 2022 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 STANDARD CITY CONDITIONS OF THE CONSTRUCTION CONTRACT FOR DEVELOPER AWARDED PROJECTS CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 STANDARD CITY CONDITIONS OF THE CONSTRUCTION CONTRACT FOR DEVELOPER AWARDED PROJECTS TABLE OF CONTENTS Page Article 1 – Definitions and Terminology .......................................................................................................... 1  1.01 Defined Terms ............................................................................................................................... 1  1.02 Terminology .................................................................................................................................. 5  Article 2 – Preliminary Matters ......................................................................................................................... 6  2.01 Before Starting Construction ........................................................................................................ 6  2.02 Preconstruction Conference .......................................................................................................... 6  2.03 Public Meeting .............................................................................................................................. 6  Article 3 – Contract Documents and Amending ............................................................................................... 6  3.01 Reference Standards ..................................................................................................................... 6  3.02 Amending and Supplementing Contract Documents .................................................................. 6  Article 4 – Bonds and Insurance ....................................................................................................................... 7  4.01 Licensed Sureties and Insurers ..................................................................................................... 7  4.02 Performance, Payment, and Maintenance Bonds ........................................................................ 7  4.03 Certificates of Insurance ............................................................................................................... 7  4.04 Contractor’s Insurance .................................................................................................................. 9  4.05 Acceptance of Bonds and Insurance; Option to Replace ........................................................... 12  Article 5 – Contractor’s Responsibilities ........................................................................................................ 12  5.01 Supervision and Superintendent ................................................................................................. 12  5.02 Labor; Working Hours ................................................................................................................ 13  5.03 Services, Materials, and Equipment ........................................................................................... 13  5.04 Project Schedule .......................................................................................................................... 14  5.05 Substitutes and “Or-Equals” ....................................................................................................... 14  5.06 Pre-Qualification of Bidders (Prime Contractors and Subcontractors) ..................................... 16  5.07 Concerning Subcontractors, Suppliers, and Others ................................................................... 16  5.08 Wage Rates.................................................................................................................................. 18  5.09 Patent Fees and Royalties ........................................................................................................... 19  5.10 Laws and Regulations ................................................................................................................. 19  5.11 Use of Site and Other Areas ....................................................................................................... 19  5.12 Record Documents ...................................................................................................................... 20  5.13 Safety and Protection .................................................................................................................. 21  5.14 Safety Representative ................................................................................................................. 21  5.15 Hazard Communication Programs ............................................................................................. 22  5.16 Submittals .................................................................................................................................... 22  5.17 Contractor’s General Warranty and Guarantee .......................................................................... 23  CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 5.18 Indemnification ........................................................................................................................... 24  5.19 Delegation of Professional Design Services .............................................................................. 24  5.20 Right to Audit: ............................................................................................................................ 25  5.21 Nondiscrimination....................................................................................................................... 25  Article 6 – Other Work at the Site ................................................................................................................... 26  6.01 Related Work at Site ................................................................................................................... 26  Article 7 – City’s Responsibilities................................................................................................................... 26  7.01 Inspections, Tests, and Approvals .............................................................................................. 26  7.02 Limitations on City’s Responsibilities ....................................................................................... 26  7.03 Compliance with Safety Program ............................................................................................... 27  Article 8 – City’s Observation Status During Construction ........................................................................... 27  8.01 City’s Project Representative ..................................................................................................... 27  8.02 Authorized Variations in Work .................................................................................................. 27  8.03 Rejecting Defective Work .......................................................................................................... 27  8.04 Determinations for Work Performed .......................................................................................... 28  Article 9 – Changes in the Work ..................................................................................................................... 28  9.01 Authorized Changes in the Work ............................................................................................... 28  9.02 Notification to Surety .................................................................................................................. 28  Article 10 – Change of Contract Price; Change of Contract Time ................................................................ 28  10.01 Change of Contract Price ............................................................................................................ 28  10.02 Change of Contract Time............................................................................................................ 28  10.03 Delays .......................................................................................................................................... 28  Article 11 – Tests and Inspections; Correction, Removal or Acceptance of Defective Work ...................... 29  11.01 Notice of Defects ........................................................................................................................ 29  11.02 Access to Work ........................................................................................................................... 29  11.03 Tests and Inspections .................................................................................................................. 29  11.04 Uncovering Work ....................................................................................................................... 30  11.05 City May Stop the Work ............................................................................................................. 30  11.06 Correction or Removal of Defective Work ................................................................................ 30  11.07 Correction Period ........................................................................................................................ 30  11.08 City May Correct Defective Work ............................................................................................. 31  Article 12 – Completion .................................................................................................................................. 32  12.01 Contractor’s Warranty of Title ................................................................................................... 32  12.02 Partial Utilization ........................................................................................................................ 32  12.03 Final Inspection ........................................................................................................................... 32  12.04 Final Acceptance ......................................................................................................................... 33  Article 13 – Suspension of Work .................................................................................................................... 33  13.01 City May Suspend Work ............................................................................................................ 33  Article 14 – Miscellaneous .............................................................................................................................. 34  14.01 Giving Notice .............................................................................................................................. 34  CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 14.02 Computation of Times ................................................................................................................ 34  14.03 Cumulative Remedies ................................................................................................................. 34  14.04 Survival of Obligations ............................................................................................................... 35  14.05 Headings ...................................................................................................................................... 35  00 73 10- 1 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 1 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 ARTICLE 1 – DEFINITIONS AND TERMINOLOGY 1.01 Defined Terms A. Wherever used in these General Conditions or in other Contract Documents, the terms listed below have the meanings indicated which are applicable to both the singular and plural thereof, and words denoting gender shall include the masculine, feminine and neuter. Said terms are generally capitalized or written in italics, but not always. When used in a context consistent with the definition of a listed-defined term, the term shall have a meaning as defined below whether capitalized or italicized or otherwise. In addition to terms specifically defined, terms with initial capital letters in the Contract Documents include references to identified articles and paragraphs, and the titles of other documents or forms. 1. Agreement - The written instrument which is evidence of the agreement between Developer and Contractor covering the Work 2. Asbestos—Any material that contains more than one percent asbestos and is friable or is releasing asbestos fibers into the air above current action levels established by the United States Occupational Safety and Health Administration. 3. Business Day – A business day is defined as a day that the City conducts normal business, generally Monday through Friday, except for federal or state holidays observed by the City. 4. Buzzsaw – City’s on-line, electronic document management and collaboration system. 5. Calendar Day – A day consisting of 24 hours measured from midnight to the next midnight. 6. City— The City of Fort Worth, Texas, a Texas home-rule municipal corporation, acting by, its governing body through its City Manager, his designee, or agents authorized pursuant to its duly authorized charter on his behalf. 7. Community Facilities Agreement (CFA) -–A Contract between the Developer and the City for the Construction of one or more following public facilities within the City public right-of- way or easement: Water, Sanitary Sewer, Street, Storm Drain, Street Light, and Street Signs. A CFA may include private facilities within the right-of-way dedicated as private right-of- way or easement on a recorded plat. 8. Contract—The entire and integrated written document incorporating the Contract Documents between the Developer, Contractor, and/or City concerning the Work. The Contract supersedes prior negotiations, representations, or agreements, whether written or oral. 9. Contract Documents—Those items that make up the contract and which must include the Agreement, and it’s attachments such as standard construction specifications, standard City Conditions, other general conditions of the Developer, including: a. An Agreement 00 73 10- 2 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 2 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 b. Attachments to the Agreement i. Bid Form ii. Vendor Compliance with State Law Non-Resident Bidder iii. Prequalification Statement c. Current Prevailing Wage Rates Table (if required by City) d. Insurance Accord Form e. Payment Bond f. Performance Bond g. Maintenance Bond h. Power of Attorney for Bonds i. Workers Compensation Affidavit j. MWBE Commitment Form( If required by City) k. General Conditions l. Supplementary Conditions m. The Standard City Conditions n. Specifications specifically made part of the Contract Documents by attachment, if not attached, as incorporated by reference and described in the Table of Contents of the Project’s Contract Documents o. Drawings p. Documentation submitted by contractor prior to Notice of Award. q. The following which may be delivered or issued after the effective date if the Agreement and, if issued become an incorporated part of the Contract Documents i. Notice to Proceed ii. Field Orders iii. Change Orders iv. Letters of Final Acceptance r. Approved Submittals, other Contractor submittals, and the reports and drawings of subsurface and physical conditions are not Contract Documents. 10. Contractor—The individual or entity with whom Developer has entered into the Agreement. 11. Day or day – A day, unless otherwise defined, shall mean a Calendar Day. 12. Developer – An individual or entity that desires to make certain improvements within the City of Fort Worth 13. Drawings—That part of the Contract Documents prepared or approved by Engineer which graphically shows the scope, extent, and character of the Work to be performed by Contractor. Submittals are not Drawings as so defined. 14. Engineer—The licensed professional engineer or engineering firm registered in the State of Texas performing professional services for the Developer. 15. Final Acceptance – The written notice given by the City to the Developer and/or Contractor that the Work specified in the Contract Documents has been completed to the satisfaction of the City. 00 73 10- 3 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 3 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 16. Final Inspection – Inspection carried out by the City to verify that the Contractor has completed the Work, and each and every part or appurtenance thereof, fully, entirely, and in conformance with the Contract Documents. 17. General Requirements—A part of the Contract Documents between the Developer and a Contractor. 18. Laws and Regulations—Any and all applicable laws, rules, regulations, ordinances, codes, and orders of any and all governmental bodies, agencies, authorities, and courts having jurisdiction. 19. Liens—Charges, security interests, or encumbrances upon Project funds, real property, or personal property. 20. Milestone—A principal event specified in the Contract Documents relating to an intermediate Contract Time prior to Final Acceptance of the Work. 21. Non-Participating Change Order—A document, which is prepared for and reviewed by the City, which is signed by Contractor, and Developer, and authorizes an addition, deletion, or revision in the Work or an adjustment in the Contract Price or the Contract Time, issued on or after the Effective Date of the Agreement. 22. Participating Change Order—A document, which is prepared for and approved by the City, which is signed by Contractor, Developer, and City and authorizes an addition, deletion, or revision in the Work or an adjustment in the Contract Price or the Contract Time, issued on or after the Effective Date of the Agreement. 23. Plans – See definition of Drawings. 24. Project Schedule—A schedule, prepared and maintained by Contractor, in accordance with the General Requirements, describing the sequence and duration of the activities comprising the Contractor’s plan to accomplish the Work within the Contract Time. 25. Project—The Work to be performed under the Contract Documents. 26. Project Representative—The authorized representative of the City who will be assigned to the Site. 27. Public Meeting – An announced meeting conducted by the Developer to facilitate public participation and to assist the public in gaining an informed view of the Project. 28. Regular Working Hours – Hours beginning at 7:00 a.m. and ending at 6:00 p.m., Monday thru Friday (excluding legal holidays). 29. Samples—Physical examples of materials, equipment, or workmanship that are representative of some portion of the Work and which establish the standards by which such portion of the Work will be judged. 00 73 10- 4 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 4 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 30. Schedule of Submittals—A schedule, prepared and maintained by Contractor, of required submittals and the time requirements to support scheduled performance of related construction activities. 31. Site—Lands or areas indicated in the Contract Documents as being furnished by City or Developer upon which the Work is to be performed, including rights-of-way, permits, and easements for access thereto, and such other lands furnished by City or Developer which are designated for the use of Contractor. 32. Specifications—That part of the Contract Documents consisting of written requirements for materials, equipment, systems, standards and workmanship as applied to the Work, and certain administrative requirements and procedural matters applicable thereto. Specifications may be specifically made a part of the Contract Documents by attachment or, if not attached, may be incorporated by reference as indicated in the Table of Contents (Division 00 00 00) of each Project. 33. Standard City Conditions – That part of the Contract Documents setting forth requirements of the City. 34. Subcontractor—An individual or entity having a direct contract with Contractor or with any other Subcontractor for the performance of a part of the Work at the Site. 35. Submittals—All drawings, diagrams, illustrations, schedules, and other data or information which are specifically prepared or assembled by or for Contractor and submitted by Contractor to illustrate some portion of the Work. 36. Superintendent – The representative of the Contractor who is available at all times and able to receive instructions from the City and/or Developer and to act for the Contractor. 37. Supplementary Conditions—That part of the Contract Documents which amends or supplements the General Conditions. 38. Supplier—A manufacturer, fabricator, supplier, distributor, materialman, or vendor having a direct contract with Contractor or with any Subcontractor to furnish materials or equipment to be incorporated in the Work by Contractor or Subcontractor. 39. Underground Facilities—All underground pipelines, conduits, ducts, cables, wires, manholes, vaults, tanks, tunnels, or other such facilities or attachments, and any encasements containing such facilities, including but not limited to, those that convey electricity, gases, steam, liquid petroleum products, telephone or other communications, cable television, water, wastewater, storm water, other liquids or chemicals, or traffic or other control systems. 40. Weekend Working Hours – Hours beginning at 9:00 a.m. and ending at 5:00 p.m., Saturday, Sunday or legal holiday, as approved in advance by the City. 00 73 10- 5 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 5 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 41. Work—The entire construction or the various separately identifiable parts thereof required to be provided under the Contract Documents. Work includes and is the result of performing or providing all labor, services, and documentation necessary to produce such construction including any Participating Change Order, Non-Participating Change Order, or Field Order, and furnishing, installing, and incorporating all materials and equipment into such construction, all as required by the Contract Documents. 42. Working Day – A working day is defined as a day, not including Saturdays, Sundays, or legal holidays authorized by the City for contract purposes, in which weather or other conditions not under the control of the Contractor will permit the performance of the principal unit of work underway for a continuous period of not less than 7 hours between 7 a.m. and 6 p.m. 1.02 Terminology A. The words and terms discussed in Paragraph 1.02.B through D are not defined but, when used in the Bidding Requirements or Contract Documents, have the indicated meaning. B. Defective: 1. The word “defective,” when modifying the word “Work,” refers to Work that is unsatisfactory, faulty, or deficient in that it: a. does not conform to the Contract Documents; or b. does not meet the requirements of any applicable inspection, reference standard, test, or approval referred to in the Contract Documents; or c. has been damaged prior to City’s written acceptance. C. Furnish, Install, Perform, Provide: 1. The word “Furnish” or the word “Install” or the word “Perform” or the word “Provide” or the word “Supply,” or any combination or similar directive or usage thereof, shall mean furnishing and incorporating in the Work including all necessary labor, materials, equipment, and everything necessary to perform the Work indicated, unless specifically limited in the context used. D. Unless stated otherwise in the Contract Documents, words or phrases that have a well-known technical or construction industry or trade meaning are used in the Contract Documents in accordance with such recognized meaning. 00 73 10- 6 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 6 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 ARTICLE 2 – PRELIMINARY MATTERS 2.01 Before Starting Construction Baseline Schedules: Submit to City in accordance with the Contract Documents, and prior to starting the Work. New schedules will be submitted to City when Participating Change Orders or Non- Participating Change Orders occur. 2.02 Preconstruction Conference Before any Work at the Site is started, the Contractor shall attend a Preconstruction Conference as specified in the Contract Documents. 2.03 Public Meeting Contractor may not mobilize any equipment, materials or resources to the Site prior to Contractor attending the Public Meeting as scheduled by the City. ARTICLE 3 – CONTRACT DOCUMENTS AND AMENDING 3.01 Reference Standards A. Standards, Specifications, Codes, Laws, and Regulations 1. Reference to standards, specifications, manuals, or codes of any technical society, organization, or association, or to Laws or Regulations, whether such reference be specific or by implication, shall mean the standard, specification, manual, code, or Laws or Regulations in effect at the time of opening of Bids (or on the Effective Date of the Agreement if there were no Bids), except as may be otherwise specifically stated in the Contract Documents. 2. No provision or instruction shall be effective to assign to City, or any of its officers, directors, members, partners, employees, agents, consultants, or subcontractors, any duty or authority to supervise or direct the performance of the Work or any duty or authority to undertake responsibility inconsistent with the provisions of the Contract Documents. 3.02 Amending and Supplementing Contract Documents A. The Contract Documents may be amended to provide for additions, deletions, and revisions in the Work or to modify the terms and conditions thereof by a Participating Change Order or a Non-Participating Change Order. B. The requirements of the Contract Documents may be supplemented, and minor variations and deviations in the Work not involving a change in Contract Price or Contract Time, may be authorized, by one or more of the following ways: 1. A Field Order; 00 73 10- 7 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 7 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 1. City’s or Engineer’s review of a Submittal (subject to the provisions of Paragraph 5.16.C); or 2. City’s written interpretation or clarification. ARTICLE 4 – BONDS AND INSURANCE 4.01 Licensed Sureties and Insurers All bonds and insurance required by the Contract Documents to be purchased and maintained by Contractor shall be obtained from surety or insurance companies that are duly licensed or authorized in the State of Texas to issue bonds or insurance policies for the limits and coverage so required. Such surety and insurance companies shall also meet such additional requirements and qualifications as may be provided Section 4.04. 4.02 Performance, Payment, and Maintenance Bonds A. Contractor shall furnish performance and payment bonds in the name of Developer and City, in accordance with Texas Government Code Chapter 2253 or successor statute, each in an amount equal to the Contract Price as security for the faithful performance and payment of all of Contractor’s obligations under the Contract Documents. B. Contractor shall furnish maintenance bonds in the name of Developer and City in an amount equal to the Contract Price as security to protect the City against any defects in any portion of the Work described in the Contract Documents. Maintenance bonds shall remain in effect for two (2) years after the date of Final Acceptance by the City. C. All bonds shall be in the form prescribed by the Contract Documents except as provided otherwise by Laws or Regulations, and shall be executed by such sureties as are named in the list of “Companies Holding Certificates of Authority as Acceptable Sureties on Federal Bonds and as Acceptable Reinsuring Companies” as published in Circular 570 (amended) by the Financial Management Service, Surety Bond Branch, U.S. Department of the Treasury. All bonds signed by an agent or attorney-in-fact must be accompanied by a sealed and dated power of attorney which shall show that it is effective on the date the agent or attorney-in-fact signed each bond. D. If the surety on any bond furnished by Contractor is declared bankrupt or becomes insolvent or its right to do business is terminated in the State of Texas or it ceases to meet the requirements of Paragraph 4.02.C, Contractor shall promptly notify City and shall, within 30 days after the event giving rise to such notification, provide another bond and surety, both of which shall comply with the requirements of Paragraphs 4.01 and 4.02.C. 4.03 Certificates of Insurance Contractor shall deliver to Developer and City, with copies to each additional insured and loss payee identified in these Standard City Conditions certificates of insurance (and other evidence of insurance requested by City or any other additional insured) which Contractor is required to purchase and maintain. 00 73 10- 8 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 8 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 1. The certificate of insurance shall document the City, an as “Additional Insured” on all liability policies. 2. The Contractor’s general liability insurance shall include a, “per project” or “per location”, endorsement, which shall be identified in the certificate of insurance provided to the City. 3. The certificate shall be signed by an agent authorized to bind coverage on behalf of the insured, be complete in its entirety, and show complete insurance carrier names as listed in the current A.M. Best Property & Casualty Guide 4. The insurers for all policies must be licensed and/or approved to do business in the State of Texas. Except for workers’ compensation, all insurers must have a minimum rating of A-: VII in the current A. M. Best Key Rating Guide or have reasonably equivalent financial strength and solvency to the satisfaction of Risk Management. If the rating is below that required, written approval of City is required. 5. All applicable policies shall include a Waiver of Subrogation (Rights of Recovery) in favor of the City. In addition, the Contractor agrees to waive all rights of subrogation against the Engineer (if applicable), and each additional insured identified in these Standard City Conditions. Failure of the City to demand such certificates or other evidence of full compliance with the insurance requirements or failure of the City to identify a deficiency from evidence that is provided shall not be construed as a waiver of Contractor’s obligation to maintain such lines of insurance coverage. 6. If insurance policies are not written for specified coverage limits, an Umbrella or Excess Liability insurance for any differences is required. Excess Liability shall follow form of the primary coverage. 7. Unless otherwise stated, all required insurance shall be written on the “occurrence basis”. If coverage is underwritten on a claims-made basis, the retroactive date shall be coincident with or prior to the date of the effective date of the agreement and the certificate of insurance shall state that the coverage is claims-made and the retroactive date. The insurance coverage shall be maintained for the duration of the Contract and for three (3) years following Final Acceptance provided under the Contract Documents or for the warranty period, whichever is longer. An annual certificate of insurance submitted to the City shall evidence such insurance coverage. 8. Policies shall have no exclusions by endorsements, which, neither nullify or amend, the required lines of coverage, nor decrease the limits of said coverage unless such endorsements are approved in writing by the City. In the event a Contract has been bid or executed and the exclusions are determined to be unacceptable or the City desires additional insurance coverage, and the City desires the contractor/engineer to obtain such coverage, the contract price shall be adjusted by the cost of the premium for such additional coverage plus 10%. 9. Any self-insured retention (SIR), in excess of $25,000.00, affecting required insurance coverage shall be approved by the City in regards to asset value and stockholders' equity. In 00 73 10- 9 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 9 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 lieu of traditional insurance, alternative coverage maintained through insurance pools or risk retention groups, must also be approved by City. 10. Any deductible in excess of $5,000.00, for any policy that does not provide coverage on a first-dollar basis, must be acceptable to and approved by the City. 11. City, at its sole discretion, reserves the right to review the insurance requirements and to make reasonable adjustments to insurance coverage’s and their limits when deemed necessary and prudent by the City based upon changes in statutory law, court decision or the claims history of the industry as well as of the contracting party to the City. The City shall be required to provide prior notice of 90 days, and the insurance adjustments shall be incorporated into the Work by Change Order. 12. City shall be entitled, upon written request and without expense, to receive copies of policies and endorsements thereto and may make any reasonable requests for deletion or revision or modifications of particular policy terms, conditions, limitations, or exclusions necessary to conform the policy and endorsements to the requirements of the Contract. Deletions, revisions, or modifications shall not be required where policy provisions are established by law or regulations binding upon either party or the underwriter on any such policies. 13. City shall not be responsible for the direct payment of insurance premium costs for Contractor’s insurance. 4.04 Contractor’s Insurance A. Workers Compensation and Employers’ Liability. Contractor shall purchase and maintain such insurance coverage with limits consistent with statutory benefits outlined in the Texas Workers’ Compensation Act (Texas Labor Code, Ch. 406, as amended), and minimum limits for Employers’ Liability as is appropriate for the Work being performed and as will provide protection from claims set forth below which may arise out of or result from Contractor’s performance of the Work and Contractor’s other obligations under the Contract Documents, whether it is to be performed by Contractor, any Subcontractor or Supplier, or by anyone directly or indirectly employed by any of them to perform any of the Work, or by anyone for whose acts any of them may be liable: 1. claims under workers’ compensation, disability benefits, and other similar employee benefit acts; 2. claims for damages because of bodily injury, occupational sickness or disease, or death of Contractor’s employees. 3. The limits of liability for the insurance shall provide the following coverages for not less than the following amounts or greater where required by Laws and Regulations a. Statutory limits b. Employer's liability 00 73 10- 10 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 10 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 1) $100,000 each accident/occurrence 2) $100,000 Disease - each employee 3) $500,000 Disease - policy limit B. Commercial General Liability. Coverage shall include but not be limited to covering liability (bodily injury or property damage) arising from: premises/operations, independent contractors, products/completed operations, personal injury, and liability under an insured contract. Insurance shall be provided on an occurrence basis, and as comprehensive as the current Insurance Services Office (ISO) policy. This insurance shall apply as primary insurance with respect to any other insurance or self-insurance programs afforded to the City. The Commercial General Liability policy, shall have no exclusions by endorsements that would alter of nullify premises/operations, products/completed operations, contractual, personal injury, or advertising injury, which are normally contained with the policy, unless the City approves such exclusions in writing. 1. For construction projects that present a substantial completed operation exposure, the City may require the contractor to maintain completed operations coverage for a minimum of no less than three (3) years following the completion of the project 2. Contractor's Liability Insurance under this Section which shall be on a per project basis covering the Contractor with minimum limits of: a. $1,000,000 each occurrence b. $2,000,000 aggregate limit 3. The policy must have an endorsement (Amendment – Aggregate Limits of Insurance) making the General Aggregate Limits apply separately to each job site. 4. The Commercial General Liability Insurance policies shall provide “X”, “C”, and “U” coverage’s. Verification of such coverage must be shown in the Remarks Article of the Certificate of Insurance. C. Automobile Liability. A commercial business auto policy shall provide coverage on “any auto”, defined as autos owned, hired and non-owned and provide indemnity for claims for damages because bodily injury or death of any person and or property damage arising out of the work, maintenance or use of any motor vehicle by the Contractor, any Subcontractor or Supplier, or by anyone directly or indirectly employed by any of them to perform any of the Work, or by anyone for whose acts any of them may be liable. 1. Automobile Liability, Contractor’s Liability Insurance under this Section, which shall be in an amount not less than the following amounts: a. Automobile Liability - a commercial business policy shall provide coverage on "Any Auto", defined as autos owned, hired and non-owned. 00 73 10- 11 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 11 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 1) $1,000,000 each accident on a combined single limit basis. Split limits are acceptable if limits are at least: 2) $250,000 Bodily Injury per person 3) $500,000 Bodily Injury per accident / 4) $100,000 Property Damage D. Railroad Protective Liability. If any of the work or any warranty work is within the limits of railroad right-of-way, the Contractor shall comply with the following requirements: 1. The Contractor’s construction activities will require its employees, agents, subcontractors, equipment, and material deliveries to cross railroad properties and tracks owned and operated by: ____________________________________________________________ Write the name of the railroad company. (If none, then write none) 2. The Contractor shall conduct its operations on railroad properties in such a manner as not to interfere with, hinder, or obstruct the railroad company in any manner whatsoever in the use or operation of its/their trains or other property. Such operations on railroad properties may require that Contractor to execute a “Right of Entry Agreement” with the particular railroad company or companies involved, and to this end the Contractor should satisfy itself as to the requirements of each railroad company and be prepared to execute the right-of-entry (if any) required by a railroad company. The requirements specified herein likewise relate to the Contractor’s use of private and/or construction access roads crossing said railroad company’s properties. 3. The Contractual Liability coverage required by Paragraph 5.04D of the General Conditions shall provide coverage for not less than the following amounts, issued by companies satisfactory to the City and to the Railroad Company for a term that continues for so long as the Contractor’s operations and work cross, occupy, or touch railroad property: a. General Aggregate: _____________________________________ Enter limits provided by Railroad Company (If none, write none) b. Each Occurrence: : _____________________________________ Enter limits provided by Railroad Company (If none, write none) 4. With respect to the above outlined insurance requirements, the following shall govern: a. Where a single railroad company is involved, the Contractor shall provide one insurance policy in the name of the railroad company. However, if more than one grade separation or at-grade crossing is affected by the Project at entirely separate locations on the line or lines of the same railroad company, separate coverage may be required, each in the amount stated above. b. Where more than one railroad company is operating on the same right-of-way or where several railroad companies are involved and operated on their own separate rights-of- 00 73 10- 12 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 12 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 way, the Contractor may be required to provide separate insurance policies in the name of each railroad company. c. If, in addition to a grade separation or an at-grade crossing, other work or activity is proposed on a railroad company’s right-of-way at a location entirely separate from the grade separation or at-grade crossing, insurance coverage for this work must be included in the policy covering the grade separation. d. If no grade separation is involved but other work is proposed on a railroad company’s right-of-way, all such other work may be covered in a single policy for that railroad, even though the work may be at two or more separate locations. 5. No work or activities on a railroad company’s property to be performed by the Contractor shall be commenced until the Contractor has furnished the City with an original policy or policies of the insurance for each railroad company named, as required above. All such insurance must be approved by the City and each affected Railroad Company prior to the Contractor’s beginning work. 6. The insurance specified above must be carried until all Work to be performed on the railroad right-of-way has been completed and the grade crossing, if any, is no longer used by the Contractor. In addition, insurance must be carried during all maintenance and/or repair work performed in the railroad right-of-way. Such insurance must name the railroad company as the insured, together with any tenant or lessee of the railroad company operating over tracks involved in the Project. E. Notification of Policy Cancellation: Contractor shall immediately notify City upon cancellation or other loss of insurance coverage. Contractor shall stop work until replacement insurance has been procured. There shall be no time credit for days not worked pursuant to this section. 4.05 Acceptance of Bonds and Insurance; Option to Replace If City has any objection to the coverage afforded by or other provisions of the bonds or insurance required to be purchased and maintained by the Contractor in accordance with Article 5 on the basis of non-conformance with the Contract Documents, the Developer and City shall so notify the Contractor in writing within 10 Business Days after receipt of the certificates (or other evidence requested). Contractor shall provide to the City such additional information in respect of insurance provided as the Developer or City may reasonably request. If Contractor does not purchase or maintain all of the bonds and insurance required by the Contract Documents, the Developer or City shall notify the Contractor in writing of such failure prior to the start of the Work, or of such failure to maintain prior to any change in the required coverage. ARTICLE 5 – CONTRACTOR’S RESPONSIBILITIES 5.01 Supervision and Superintendent A. Contractor shall supervise, inspect, and direct the Work competently and efficiently, devoting such attention thereto and applying such skills and expertise as may be necessary to perform the 00 73 10- 13 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 13 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 Work in accordance with the Contract Documents. Contractor shall be solely responsible for the means, methods, techniques, sequences, and procedures of construction. B. At all times during the progress of the Work, Contractor shall assign a competent, English- speaking, Superintendent who shall not be replaced without written notice to City. The Superintendent will be Contractor’s representative at the Site and shall have authority to act on behalf of Contractor. All communication given to or received from the Superintendent shall be binding on Contractor. C. Contractor shall notify the City 24 hours prior to moving areas during the sequence of construction. 5.02 Labor; Working Hours A. Contractor shall provide competent, suitably qualified personnel to perform construction as required by the Contract Documents. Contractor shall at all times maintain good discipline and order at the Site. B. Except as otherwise required for the safety or protection of persons or the Work or property at the Site or adjacent thereto, and except as otherwise stated in the Contract Documents, all Work at the Site shall be performed during Regular Working Hours. Contractor will not permit the performance of Work beyond Regular Working Hours or for Weekend Working Hours without City’s written consent (which will not be unreasonably withheld). Written request (by letter or electronic communication) to perform Work: 1. for beyond Regular Working Hours request must be made by noon at least two (2) Business Days prior 2. for Weekend Working Hours request must be made by noon of the preceding Thursday 3. for legal holidays request must be made by noon two Business Days prior to the legal holiday. 5.03 Services, Materials, and Equipment A. Unless otherwise specified in the Contract Documents, Contractor shall provide and assume full responsibility for all services, materials, equipment, labor, transportation, construction equipment and machinery, tools, appliances, fuel, power, light, heat, telephone, water, sanitary facilities, temporary facilities, and all other facilities and incidentals necessary for the performance, Contractor required testing, start-up, and completion of the Work. B. All materials and equipment incorporated into the Work shall be as specified or, if not specified, shall be of good quality and new, except as otherwise provided in the Contract Documents. All special warranties and guarantees required by the Specifications shall expressly run to the benefit of City. If required by City, Contractor shall furnish satisfactory evidence (including reports of required tests) as to the source, kind, and quality of materials and equipment. 00 73 10- 14 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 14 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 C. All materials and equipment to be incorporated into the Work shall be stored, applied, installed, connected, erected, protected, used, cleaned, and conditioned in accordance with instructions of the applicable Supplier, except as otherwise may be provided in the Contract Documents. 5.04 Project Schedule A. Contractor shall adhere to the Project Schedule established in accordance with Paragraph 2.01 and the General Requirements as it may be adjusted from time to time as provided below. 1. Contractor shall submit to City for acceptance (to the extent indicated in Paragraph 2.01 and the General Requirements) proposed adjustments in the Project Schedule. 2. Proposed adjustments in the Project Schedule that will change the Contract Time shall be submitted in accordance with the requirements of Article 9. Adjustments in Contract Time for projects with City participation shall be made by participating change orders. 5.05 Substitutes and “Or-Equals” A. Whenever an item of material or equipment is specified or described in the Contract Documents by using the name of a proprietary item or the name of a particular Supplier, the specification or description is intended to establish the type, function, appearance, and quality required. Unless the specification or description contains or is followed by words reading that no like, equivalent, or “or-equal” item or no substitution is permitted, other items of material or equipment of other Suppliers may be submitted to City for review under the circumstances described below. 1. “Or-Equal” Items: If in City’s sole discretion an item of material or equipment proposed by Contractor is functionally equal to that named and sufficiently similar so that no change in related Work will be required, it may be considered by City as an “or-equal” item, in which case review and approval of the proposed item may, in City’s sole discretion, be accomplished without compliance with some or all of the requirements for approval of proposed substitute items. For the purposes of this Paragraph 5.05.A.1, a proposed item of material or equipment will be considered functionally equal to an item so named if: a. City determines that: 1) it is at least equal in materials of construction, quality, durability, appearance, strength, and design characteristics; 2) it will reliably perform at least equally well the function and achieve the results imposed by the design concept of the completed Project as a functioning whole; and 3) it has a proven record of performance and availability of responsive service; and b. Contractor certifies that, if approved and incorporated into the Work: 1) there will be no increase in cost to the City or increase in Contract Time; and 00 73 10- 15 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 15 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 2) it will conform substantially to the detailed requirements of the item named in the Contract Documents. 2. Substitute Items: a. If in City’s sole discretion an item of material or equipment proposed by Contractor does not qualify as an “or-equal” item under Paragraph 5.05.A.1, it may be submitted as a proposed substitute item. b. Contractor shall submit sufficient information as provided below to allow City to determine if the item of material or equipment proposed is essentially equivalent to that named and an acceptable substitute therefor. Requests for review of proposed substitute items of material or equipment will not be accepted by City from anyone other than Contractor. c. Contractor shall make written application to City for review of a proposed substitute item of material or equipment that Contractor seeks to furnish or use. The application shall comply with Section 01 25 00 and: 1) shall certify that the proposed substitute item will: i. perform adequately the functions and achieve the results called for by the general design; ii. be similar in substance to that specified; iii. be suited to the same use as that specified; and 2) will state: i. the extent, if any, to which the use of the proposed substitute item will prejudice Contractor’s achievement of final completion on time; ii. whether use of the proposed substitute item in the Work will require a change in any of the Contract Documents (or in the provisions of any other direct contract with City for other work on the Project) to adapt the design to the proposed substitute item; iii. whether incorporation or use of the proposed substitute item in connection with the Work is subject to payment of any license fee or royalty; and 3) will identify: i. all variations of the proposed substitute item from that specified; ii. available engineering, sales, maintenance, repair, and replacement services; and 00 73 10- 16 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 16 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 4) shall contain an itemized estimate of all costs or credits that will result directly or indirectly from use of such substitute item, including costs of redesign and Damage Claims of other contractors affected by any resulting change. B. Substitute Construction Methods or Procedures: If a specific means, method, technique, sequence, or procedure of construction is expressly required by the Contract Documents, Contractor may furnish or utilize a substitute means, method, technique, sequence, or procedure of construction approved by City. Contractor shall submit sufficient information to allow City, in City’s sole discretion, to determine that the substitute proposed is equivalent to that expressly called for by the Contract Documents. Contractor shall make written application to City for review in the same manner as those provided in Paragraph 5.05.A.2. C. City’s Evaluation: City will be allowed a reasonable time within which to evaluate each proposal or submittal made pursuant to Paragraphs 5.05.A and 5.05.B. City may require Contractor to furnish additional data about the proposed substitute. City will be the sole judge of acceptability. No “or-equal” or substitute will be ordered, installed or utilized until City’s review is complete, which will be evidenced by a Change Order in the case of a substitute and an accepted Submittal for an “or-equal.” City will advise Contractor in writing of its determination. D. Special Guarantee: City may require Contractor to furnish at Contractor’s expense a special performance guarantee, warranty, or other surety with respect to any substitute. Contractor shall indemnify and hold harmless City and anyone directly or indirectly employed by them from and against any and all claims, damages, losses and expenses (including attorneys fees) arising out of the use of substituted materials or equipment. E. City’s Cost Reimbursement: City will record City’s costs in evaluating a substitute proposed or submitted by Contractor pursuant to Paragraphs 5.05.A.2 and 5.05.B. Whether or not City approves a substitute so proposed or submitted by Contractor, Contractor may be required to reimburse City for evaluating each such proposed substitute. Contractor may also be required to reimburse City for the charges for making changes in the Contract Documents. F. Contractor’s Expense: Contractor shall provide all data in support of any proposed substitute or “or-equal” at Contractor’s expense. G. Substitute Reimbursement: Costs (savings or charges) attributable to acceptance of a substitute shall be incorporated to the Contract by Participating Change Order. 5.06 Pre-Qualification of Bidders (Prime Contractors and Subcontractors) A. The Contractor and any subcontractors are required to be prequalified for the work types requiring pre-qualification 5.07 Concerning Subcontractors, Suppliers, and Others A. Minority and Women Owned Business Enterprise Compliance: 00 73 10- 17 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 17 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 Required for this Contract. (Check this box if there is any City Participation) Not Required for this Contract. It is City policy to ensure the full and equitable participation by Minority and Women Business Enterprises (MWBE) in the procurement of goods and services on a contractual basis. If the Contract Documents provide for a MWBE goal, Contractor is required to comply with the intent of the City’s MWBE Ordinance (as amended) by the following: 1. Contractor shall, upon request by City, provide complete and accurate information regarding actual work performed by a MWBE on the Contract and payment therefor. 2. Contractor will not make additions, deletions, or substitutions of accepted MWBE without written consent of the City. Any unjustified change or deletion shall be a material breach of Contract and may result in debarment in accordance with the procedures outlined in the Ordinance. 3. Contractor shall, upon request by City, allow an audit and/or examination of any books, records, or files in the possession of the Contractor that will substantiate the actual work performed by an MWBE. Material misrepresentation of any nature will be grounds for termination of the Contract. Any such misrepresentation may be grounds for disqualification of Contractor to bid on future contracts with the City for a period of not less than three years. B. Contractor shall be fully responsible to City for all acts and omissions of the Subcontractors, Suppliers, and other individuals or entities performing or furnishing any of the Work just as Contractor is responsible for Contractor’s own acts and omissions. Nothing in the Contract Documents: 1. shall create for the benefit of any such Subcontractor, Supplier, or other individual or entity any contractual relationship between City and any such Subcontractor, Supplier or other individual or entity; nor 2. shall create any obligation on the part of City to pay or to see to the payment of any moneys due any such Subcontractor, Supplier, or other individual or entity except as may otherwise be required by Laws and Regulations. C. Contractor shall be solely responsible for scheduling and coordinating the Work of Subcontractors, Suppliers, and other individuals or entities performing or furnishing any of the Work under a direct or indirect contract with Contractor. D. All Subcontractors, Suppliers, and such other individuals or entities performing or furnishing any of the Work shall communicate with City through Contractor. E. All Work performed for Contractor by a Subcontractor or Supplier will be pursuant to an appropriate agreement between Contractor and the Subcontractor or Supplier which specifically binds the Subcontractor or Supplier to the applicable terms and conditions of these Contract 00 73 10- 18 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 18 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 Documents, Contractor shall provide City contract numbers and reference numbers to the Subcontractors and/or Suppliers. 5.08 Wage Rates Required for this Contract. Not Required for this Contract. A. Duty to pay Prevailing Wage Rates. The Contractor shall comply with all requirements of Chapter 2258, Texas Government Code (as amended), including the payment of not less than the rates determined by the City Council of the City of Fort Worth to be the prevailing wage rates in accordance with Chapter 2258. Such prevailing wage rates are included in these Contract Documents. B. Penalty for Violation. A Contractor or any Subcontractor who does not pay the prevailing wage shall, upon demand made by the City, pay to the City $60 for each worker employed for each calendar day or part of the day that the worker is paid less than the prevailing wage rates stipulated in these contract documents. This penalty shall be retained by the City to offset its administrative costs, pursuant to Texas Government Code 2258.023. C. Complaints of Violations and City Determination of Good Cause. On receipt of information, including a complaint by a worker, concerning an alleged violation of 2258.023, Texas Government Code, by a Contractor or Subcontractor, the City shall make an initial determination, before the 31st day after the date the City receives the information, as to whether good cause exists to believe that the violation occurred. The City shall notify in writing the Contractor or Subcontractor and any affected worker of its initial determination. Upon the City’s determination that there is good cause to believe the Contractor or Subcontractor has violated Chapter 2258, the City shall retain the full amounts claimed by the claimant or claimants as the difference between wages paid and wages due under the prevailing wage rates, such amounts being subtracted from successive progress payments pending a final determination of the violation. D. Arbitration Required if Violation Not Resolved. An issue relating to an alleged violation of Section 2258.023, Texas Government Code, including a penalty owed to the City or an affected worker, shall be submitted to binding arbitration in accordance with the Texas General Arbitration Act (Article 224 et seq., Revised Statutes) if the Contractor or Subcontractor and any affected worker does not resolve the issue by agreement before the 15th day after the date the City makes its initial determination pursuant to Paragraph C above. If the persons required to arbitrate under this section do not agree on an arbitrator before the 11th day after the date that arbitration is required, a district court shall appoint an arbitrator on the petition of any of the persons. The City is not a party in the arbitration. The decision and award of the arbitrator is final and binding on all parties and may be enforced in any court of competent jurisdiction. E. Records to be Maintained. The Contractor and each Subcontractor shall, for a period of three (3) years following the date of acceptance of the work, maintain records that show (i) the name and 00 73 10- 19 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 19 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 occupation of each worker employed by the Contractor in the construction of the Work provided for in this Contract; and (ii) the actual per diem wages paid to each worker. The records shall be open at all reasonable hours for inspection by the City. The provisions of Paragraph 6.23, Right to Audit, shall pertain to this inspection. F. Progress Payments. With each progress payment or payroll period, whichever is less, the Contractor shall submit an affidavit stating that the Contractor has complied with the requirements of Chapter 2258, Texas Government Code. G. Posting of Wage Rates. The Contractor shall post prevailing wage rates in a conspicuous place at all times. H. Subcontractor Compliance. The Contractor shall include in its subcontracts and/or shall otherwise require all of its Subcontractors to comply with Paragraphs A through G above. 5.09 Patent Fees and Royalties A. To the fullest extent permitted by Laws and Regulations, Contractor shall indemnify and hold harmless City, from and against all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) arising out of or relating to any infringement of patent rights or copyrights incident to the use in the performance of the Work or resulting from the incorporation in the Work of any invention, design, process, product, or device not specified in the Contract Documents. 5.10 Laws and Regulations A. Contractor shall give all notices required by and shall comply with all Laws and Regulations applicable to the performance of the Work. Except where otherwise expressly required by applicable Laws and Regulations, the City shall not be responsible for monitoring Contractor’s compliance with any Laws or Regulations. B. If Contractor performs any Work knowing or having reason to know that it is contrary to Laws or Regulations, Contractor shall bear all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) arising out of or relating to such Work. However, it shall not be Contractor’s responsibility to make certain that the Specifications and Drawings are in accordance with Laws and Regulations, but this shall not relieve Contractor of Contractor’s obligations under Paragraph 3.01. 5.11 Use of Site and Other Areas A. Limitation on Use of Site and Other Areas: 1. Contractor shall confine construction equipment, the storage of materials and equipment, and the operations of workers to the Site and other areas permitted by Laws and Regulations, and shall not unreasonably encumber the Site and other areas with construction equipment or 00 73 10- 20 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 20 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 other materials or equipment. Contractor shall assume full responsibility for any damage to any such land or area, or to the owner or occupant thereof, or of any adjacent land or areas resulting from the performance of the Work. 2. At any time when, in the judgment of the City, the Contractor has obstructed or closed or is carrying on operations in a portion of a street, right-of-way, or easement greater than is necessary for proper execution of the Work, the City may require the Contractor to finish the section on which operations are in progress before work is commenced on any additional area of the Site. 3. Should any Damage Claim be made by any such owner or occupant because of the performance of the Work, Contractor shall promptly attempt to resolve the Damage Claim. 4. Pursuant to Paragraph 5.18, Contractor shall indemnify and hold harmless City, from and against all claims, costs, losses, and damages arising out of or relating to any claim or action, legal or equitable, brought by any such owner or occupant against City. B. Removal of Debris During Performance of the Work: During the progress of the Work Contractor shall keep the Site and other areas free from accumulations of waste materials, rubbish, and other debris. Removal and disposal of such waste materials, rubbish, and other debris shall conform to applicable Laws and Regulations. C. Site Maintenance Cleaning: 24 hours after written notice is given to the Contractor that the clean-up on the job site is proceeding in a manner unsatisfactory to the City or Developer, if the Contractor fails to correct the unsatisfactory procedure, the City may take such direct action as the City deems appropriate to correct the clean-up deficiencies cited to the Contractor in the written notice (by letter or electronic communication), and shall be entitled to recover its cost in doing so. The City may withhold Final Acceptance until clean-up is complete and cost are recovered. D. Final Site Cleaning: Prior to Final Acceptance of the Work Contractor shall clean the Site and the Work and make it ready for utilization by City or adjacent property owner. At the completion of the Work Contractor shall remove from the Site all tools, appliances, construction equipment and machinery, and surplus materials and shall restore to original condition or better all property disturbed by the Work. E. Loading Structures: Contractor shall not load nor permit any part of any structure to be loaded in any manner that will endanger the structure, nor shall Contractor subject any part of the Work or adjacent property to stresses or pressures that will endanger it. 5.12 Record Documents A. Contractor shall maintain in a safe place at the Site or in a place designated by the Contractor and approved by the City, one (1) record copy of all Drawings, Specifications, Addenda, Change Orders, Field Orders, and written interpretations and clarifications in good order and annotated to show changes made during construction. These record documents together with all approved 00 73 10- 21 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 21 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 Samples and a counterpart of all accepted Submittals will be available to City for reference. Upon completion of the Work, these record documents, any operation and maintenance manuals, and Submittals will be delivered to City prior to Final Inspection. Contractor shall include accurate locations for buried and imbedded items. 5.13 Safety and Protection A. Contractor shall be solely responsible for initiating, maintaining and supervising all safety precautions and programs in connection with the Work. Such responsibility does not relieve Subcontractors of their responsibility for the safety of persons or property in the performance of their work, nor for compliance with applicable safety Laws and Regulations. Contractor shall take all necessary precautions for the safety of, and shall provide the necessary protection to prevent damage, injury or loss to: 1. all persons on the Site or who may be affected by the Work; 2. all the Work and materials and equipment to be incorporated therein, whether in storage on or off the Site; and 3. other property at the Site or adjacent thereto, including trees, shrubs, lawns, walks, pavements, roadways, structures, utilities, and Underground Facilities not designated for removal, relocation, or replacement in the course of construction. B. Contractor shall comply with all applicable Laws and Regulations relating to the safety of persons or property, or to the protection of persons or property from damage, injury, or loss; and shall erect and maintain all necessary safeguards for such safety and protection. Contractor shall notify owners of adjacent property and of Underground Facilities and other utility owners when prosecution of the Work may affect them, and shall cooperate with them in the protection, removal, relocation, and replacement of their property. C. Contractor shall comply with the applicable requirements of City’s safety programs, if any. D. Contractor shall inform City of the specific requirements of Contractor’s safety program, if any, with which City’s employees and representatives must comply while at the Site. E. All damage, injury, or loss to any property referred to in Paragraph 5.13.A.2 or 5.13.A.3 caused, directly or indirectly, in whole or in part, by Contractor, any Subcontractor, Supplier, or any other individual or entity directly or indirectly employed by any of them to perform any of the Work, or anyone for whose acts any of them may be liable, shall be remedied by Contractor. F. Contractor’s duties and responsibilities for safety and for protection of the Work shall continue until such time as all the Work is completed and City has accepted the Work. 5.14 Safety Representative Contractor shall inform City in writing of Contractor’s designated safety representative at the Site. 00 73 10- 22 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 22 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 5.15 Hazard Communication Programs Contractor shall be responsible for coordinating any exchange of material safety data sheets or other hazard communication information required to be made available to or exchanged between or among employers in accordance with Laws or Regulations. 5.16 Submittals A. Contractor shall submit required Submittals to City for review and acceptance. Each submittal will be identified as required by City. 1. Submit number of copies specified in the General Requirements. 2. Data shown on the Submittals will be complete with respect to quantities, dimensions, specified performance and design criteria, materials, and similar data to show City the services, materials, and equipment Contractor proposes to provide and to enable City to review the information for the limited purposes required by Paragraph 5.16.C. 3. Submittals submitted as herein provided by Contractor and reviewed by City for conformance with the design concept shall be executed in conformity with the Contract Documents unless otherwise required by City. 4. When Submittals are submitted for the purpose of showing the installation in greater detail, their review shall not excuse Contractor from requirements shown on the Drawings and Specifications. 5. For-Information-Only submittals upon which the City is not expected to conduct review or take responsive action may be so identified in the Contract Documents. 6. Submit required number of Samples specified in the Specifications. 7. Clearly identify each Sample as to material, Supplier, pertinent data such as catalog numbers, the use for which intended and other data as City may require to enable City to review the submittal for the limited purposes required by Paragraph 5.16.C. B. Where a Submittal is required by the Contract Documents or the Schedule of Submittals, any related Work performed prior to City’s review and acceptance of the pertinent submittal will be at the sole expense and responsibility of Contractor. C. City’s Review: 1. City will provide timely review of required Submittals in accordance with the Schedule of Submittals acceptable to City. City’s review and acceptance will be only to determine if the items covered by the submittals will, after installation or incorporation in the Work, conform to the information given in the Contract Documents and be compatible with the design concept of the completed Project as a functioning whole as indicated by the Contract Documents. 00 73 10- 23 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 23 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 2. City’s review and acceptance will not extend to means, methods, techniques, sequences, or procedures of construction (except where a particular means, method, technique, sequence, or procedure of construction is specifically and expressly called for by the Contract Documents) or to safety precautions or programs incident thereto. The review and acceptance of a separate item as such will not indicate approval of the assembly in which the item functions. 3. City’s review and acceptance shall not relieve Contractor from responsibility for any variation from the requirements of the Contract Documents unless Contractor has complied with the requirements of Section 01 33 00 and City has given written acceptance of each such variation by specific written notation thereof incorporated in or accompanying the Submittal. City’s review and acceptance shall not relieve Contractor from responsibility for complying with the requirements of the Contract Documents. 5.17 Contractor’s General Warranty and Guarantee A. Contractor warrants and guarantees to City that all Work will be in accordance with the Contract Documents and will not be defective. City and its officers, directors, members, partners, employees, agents, consultants, and subcontractors shall be entitled to rely on representation of Contractor’s warranty and guarantee. B. Contractor’s warranty and guarantee hereunder excludes defects or damage caused by: 1. abuse, modification, or improper maintenance or operation by persons other than Contractor, Subcontractors, Suppliers, or any other individual or entity for whom Contractor is responsible; or 2. normal wear and tear under normal usage. C. Contractor’s obligation to perform and complete the Work in accordance with the Contract Documents shall be absolute. None of the following will constitute an acceptance of Work that is not in accordance with the Contract Documents or a release of Contractor’s obligation to perform the Work in accordance with the Contract Documents: 1. observations by City; 2. recommendation or payment by City or Developer of any progress or final payment; 3. the issuance of a certificate of Final Acceptance by City or any payment related thereto by City; 4. use or occupancy of the Work or any part thereof by City; 5. any review and acceptance of a Submittal by City; 6. any inspection, test, or approval by others; or 00 73 10- 24 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 24 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 7. any correction of defective Work by City. D. The Contractor shall remedy any defects or damages in the Work and pay for any damage to other work or property resulting therefrom which shall appear within a period of two (2) years from the date of Final Acceptance of the Work unless a longer period is specified and shall furnish a good and sufficient maintenance bond, complying with the requirements of Article 4.02.B. The City will give notice of observed defects with reasonable promptness. 5.18 Indemnification A. Contractor covenants and agrees to indemnify, hold harmless and defend, at its own expense, the City, its officers, servants and employees, from and against any and all claims arising out of, or alleged to arise out of, the work and services to be performed by the Contractor, its officers, agents, employees, subcontractors, licenses or invitees under this Contract. THIS INDEMNIFICATION PROVISION IS SPECIFICALLY INTENDED TO OPERATE AND BE EFFECTIVE EVEN IF IT IS ALLEGED OR PROVEN THAT ALL OR SOME OF THE DAMAGES BEING SOUGHT WERE CAUSED, IN WHOLE OR IN PART, BY ANY ACT, OMISSION OR NEGLIGENCE OF THE CITY. This indemnity provision is intended to include, without limitation, indemnity for costs, expenses and legal fees incurred by the City in defending against such claims and causes of actions. B. Contractor covenants and agrees to indemnify and hold harmless, at its own expense, the City, its officers, servants and employees, from and against any and all loss, damage or destruction of property of the City, arising out of, or alleged to arise out of, the work and services to be performed by the Contractor, its officers, agents, employees, subcontractors, licensees or invitees under this Contract. THIS INDEMNIFICATION PROVISION IS SPECIFICALLY INTENDED TO OPERATE AND BE EFFECTIVE EVEN IF IT IS ALLEGED OR PROVEN THAT ALL OR SOME OF THE DAMAGES BEING SOUGHT WERE CAUSED, IN WHOLE OR IN PART, BY ANY ACT, OMISSION OR NEGLIGENCE OF THE CITY. 5.19 Delegation of Professional Design Services A. Contractor will not be required to provide professional design services unless such services are specifically required by the Contract Documents for a portion of the Work or unless such services are required to carry out Contractor’s responsibilities for construction means, methods, techniques, sequences and procedures. B. If professional design services or certifications by a design professional related to systems, materials or equipment are specifically required of Contractor by the Contract Documents, City will specify all performance and design criteria that such services must satisfy. Contractor shall cause such services or certifications to be provided by a properly licensed professional, whose signature and seal shall appear on all drawings, calculations, specifications, certifications, and Submittals prepared by such professional. Submittals related to the Work designed or certified by such professional, if prepared by others, shall bear such professional’s written approval when submitted to City. 00 73 10- 25 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 25 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 C. City shall be entitled to rely upon the adequacy, accuracy and completeness of the services, certifications or approvals performed by such design professionals, provided City has specified to Contractor performance and design criteria that such services must satisfy. D. Pursuant to this Paragraph 5.19, City’s review and acceptance of design calculations and design drawings will be only for the limited purpose of checking for conformance with performance and design criteria given and the design concept expressed in the Contract Documents. City’s review and acceptance of Submittals (except design calculations and design drawings) will be only for the purpose stated in Paragraph 5.16.C. 5.20 Right to Audit: A. The City reserves the right to audit all projects utilizing City funds B. The Contractor agrees that the City shall, until the expiration of three (3) years after final payment under this Contract, have access to and the right to examine and photocopy any directly pertinent books, documents, papers, and records of the Contractor involving transactions relating to this Contract. Contractor agrees that the City shall have access during Regular Working Hours to all necessary Contractor facilities and shall be provided adequate and appropriate work space in order to conduct audits in compliance with the provisions of this Paragraph. The City shall give Contractor reasonable advance notice of intended audits. C. Contractor further agrees to include in all its subcontracts hereunder a provision to the effect that the subcontractor agrees that the City shall, until the expiration of three (3) years after final payment under this Contract, have access to and the right to examine and photocopy any directly pertinent books, documents, papers, and records of such Subcontractor, involving transactions to the subcontract, and further, that City shall have access during Regular Working Hours to all Subcontractor facilities, and shall be provided adequate and appropriate work space in order to conduct audits in compliance with the provisions of this Paragraph. The City shall give Subcontractor reasonable advance notice of intended audits. D. Contractor and Subcontractor agree to photocopy such documents as may be requested by the City. The City agrees to reimburse Contractor for the cost of the copies as follows at the rate published in the Texas Administrative Code in effect as of the time copying is performed. 5.21 Nondiscrimination A. The City is responsible for operating Public Transportation Programs and implementing transit- related projects, which are funded in part with Federal financial assistance awarded by the U.S. Department of Transportation and the Federal Transit Administration (FTA), without discriminating against any person in the United States on the basis of race, color, or national origin. B. Title VI, Civil Rights Act of 1964 as amended: Contractor shall comply with the requirements of the Act and the Regulations as further defined in the Supplementary Conditions for any project receiving Federal assistance. 00 73 10- 26 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 26 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 ARTICLE 6 – OTHER WORK AT THE SITE 6.01 Related Work at Site A. City may perform other work related to the Project at the Site with City’s employees, or other City contractors, or through other direct contracts therefor, or have other work performed by utility owners. If such other work is not noted in the Contract Documents, then written notice thereof will be given to Contractor prior to starting any such other work; and B. Contractor shall afford each other contractor who is a party to such a direct contract, each utility owner, and City, if City is performing other work with City’s employees or other City contractors, proper and safe access to the Site, provide a reasonable opportunity for the introduction and storage of materials and equipment and the execution of such other work, and properly coordinate the Work with theirs. Contractor shall do all cutting, fitting, and patching of the Work that may be required to properly connect or otherwise make its several parts come together and properly integrate with such other work. Contractor shall not endanger any work of others by cutting, excavating, or otherwise altering such work; provided, however, that Contractor may cut or alter others' work with the written consent of City and the others whose work will be affected. C. If the proper execution or results of any part of Contractor’s Work depends upon work performed by others under this Article 7, Contractor shall inspect such other work and promptly report to City in writing any delays, defects, or deficiencies in such other work that render it unavailable or unsuitable for the proper execution and results of Contractor’s Work. Contractor’s failure to so report will constitute an acceptance of such other work as fit and proper for integration with Contractor’s Work except for latent defects in the work provided by others. ARTICLE 7 – CITY’S RESPONSIBILITIES 7.01 Inspections, Tests, and Approvals City’s responsibility with respect to certain inspections, tests, and approvals is set forth in Paragraph 11.03. 7.02 Limitations on City’s Responsibilities A. The City shall not supervise, direct, or have control or authority over, nor be responsible for, Contractor’s means, methods, techniques, sequences, or procedures of construction, or the safety precautions and programs incident thereto, or for any failure of Contractor to comply with Laws and Regulations applicable to the performance of the Work. City will not be responsible for Contractor’s failure to perform the Work in accordance with the Contract Documents. B. City will notify the Contractor of applicable safety plans pursuant to Paragraph 5.13. 00 73 10- 27 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 27 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 7.03 Compliance with Safety Program While at the Site, City’s employees and representatives shall comply with the specific applicable requirements of Contractor’s safety programs of which City has been informed pursuant to Paragraph 5.13. ARTICLE 8 – CITY’S OBSERVATION STATUS DURING CONSTRUCTION 8.01 City’s Project Representative City will provide one or more Project Representative(s) during the construction period. The duties and responsibilities and the limitations of authority of City’s representative during construction are set forth in the Contract Documents. A. City’s Project Representative will make visits to the Site at intervals appropriate to the various stages of construction as City deems necessary in order to observe the progress that has been made and the quality of the various aspects of Contractor’s executed Work. Based on information obtained during such visits and observations, City’s Project Representative will determine, in general, if the Work is proceeding in accordance with the Contract Documents. City’s Project Representative will not be required to make exhaustive or continuous inspections on the Site to check the quality or quantity of the Work. City’s Project Representative’s efforts will be directed toward providing City a greater degree of confidence that the completed Work will conform generally to the Contract Documents. B. City’s Project Representative’s visits and observations are subject to all the limitations on authority and responsibility in the Contract Documents. 8.02 Authorized Variations in Work City’s Project Representative may authorize minor variations in the Work from the requirements of the Contract Documents which do not involve an adjustment in the Contract Price or the Contract Time and are compatible with the design concept of the completed Project as a functioning whole as indicated by the Contract Documents. These may be accomplished by a Field Order and will be binding on City Developer, and also on Contractor, who shall perform the Work involved promptly. 8.03 Rejecting Defective Work City will have authority to reject Work which City’s Project Representative believes to be defective, or will not produce a completed Project that conforms to the Contract Documents or that will prejudice the integrity of the design concept of the completed Project as a functioning whole as indicated by the Contract Documents. City will have authority to conduct special inspection or testing of the Work as provided in Article 11, whether or not the Work is fabricated, installed, or completed. 00 73 10- 28 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 28 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 8.04 Determinations for Work Performed Contractor will determine the actual quantities and classifications of Work performed. City’s Project Representative will review with Contractor the preliminary determinations on such matters before rendering a written recommendation. City’s written decision will be final (except as modified to reflect changed factual conditions or more accurate data). ARTICLE 9 – CHANGES IN THE WORK 9.01 Authorized Changes in the Work A. Without invalidating the Contract and without notice to any surety, City may, at any time or from time to time, order Extra Work. Upon notice of such Extra Work, Contractor shall promptly proceed with the Work involved which will be performed under the applicable conditions of the Contract Documents (except as otherwise specifically provided). Extra Work shall be memorialized by a Participating Change Order which may or may not precede an order of Extra work. B. For minor changes of Work not requiring changes to Contract Time or Contract Price on a project with City participation, a Field Order may be issued by the City. 9.02 Notification to Surety If the provisions of any bond require notice to be given to a surety of any change affecting the general scope of the Work or the provisions of the Contract Documents (including, but not limited to, Contract Price or Contract Time), the giving of any such notice will be Contractor’s responsibility. The amount of each applicable bond will be adjusted by the Contractor to reflect the effect of any such change. ARTICLE 10 – CHANGE OF CONTRACT PRICE; CHANGE OF CONTRACT TIME 10.01 Change of Contract Price A. The Contract Price may only be changed by a Participating Change Order for projects with City participation. 10.02 Change of Contract Time A. The Contract Time may only be changed by a Participating Change Order for projects with City participation. 10.03 Delays A. If Contractor is delayed, City shall not be liable to Contractor for any claims, costs, losses, or damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) sustained by Contractor on or in connection with any other project or anticipated project. 00 73 10- 29 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 29 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 ARTICLE 11 – TESTS AND INSPECTIONS; CORRECTION, REMOVAL OR ACCEPTANCE OF DEFECTIVE WORK 11.01 Notice of Defects Notice of all defective Work of which City has actual knowledge will be given to Contractor. Defective Work may be rejected, corrected, or accepted as provided in this Article 13. 11.02 Access to Work City, independent testing laboratories, and governmental agencies with jurisdictional interests will have access to the Site and the Work at reasonable times for their observation, inspection, and testing. Contractor shall provide them proper and safe conditions for such access and advise them of Contractor’s safety procedures and programs so that they may comply therewith as applicable. 11.03 Tests and Inspections A. Contractor shall give City timely notice of readiness of the Work for all required inspections, tests, or approvals and shall cooperate with inspection and testing personnel to facilitate required inspections or tests. B. If Contract Documents, Laws or Regulations of any public body having jurisdiction require any of the Work (or part thereof) to be inspected, tested, or approved, Contractor shall assume full responsibility for arranging and obtaining such independent inspections, tests, retests or approvals, pay all costs in connection therewith, and furnish City the required certificates of inspection or approval; excepting, however, those fees specifically identified in the Supplementary Conditions or any Texas Department of Licensure and Regulation (TDLR) inspections, which shall be paid as described in the Supplementary Conditions. C. Contractor shall be responsible for arranging and obtaining and shall pay all costs in connection with any inspections, tests, re-tests, or approvals required for City’s acceptance of materials or equipment to be incorporated in the Work; or acceptance of materials, mix designs, or equipment submitted for approval prior to Contractor’s purchase thereof for incorporation in the Work. Such inspections, tests, re-tests, or approvals shall be performed by organizations approved by City. D. City may arrange for the services of an independent testing laboratory (“Testing Lab”) to perform any inspections or tests (“Testing”) for any part of the Work, as determined solely by City. 1. City will coordinate such Testing to the extent possible, with Contractor; 2. Should any Testing under this Section 11.03 D result in a “fail”, “did not pass” or other similar negative result, the Contractor shall be responsible for paying for any and all retests. Contractor’s cancellation without cause of City initiated Testing shall be deemed a negative result and require a retest. 00 73 10- 30 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 30 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 3. Any amounts owed for any retest under this Section 11.03 D shall be paid directly to the Testing Lab by Contractor. City will forward all invoices for retests to Developer/Contractor. 4. If Contractor fails to pay the Testing Lab, City will not issue a letter of Final Acceptance until the Testing Lab is Paid E. If any Work (or the work of others) that is to be inspected, tested, or approved is covered by Contractor without written concurrence of City, Contractor shall, if requested by City, uncover such Work for observation. 11.04 Uncovering Work A. If any Work is covered contrary to the Contract Documents or specific instructions by the City, it must, if requested by City, be uncovered for City’s observation and replaced at Contractor’s expense. 11.05 City May Stop the Work If the Work is defective, or Contractor fails to supply sufficient skilled workers or suitable materials or equipment, or fails to perform the Work in such a way that the completed Work will conform to the Contract Documents, City may order Contractor to stop the Work, or any portion thereof, until the cause for such order has been eliminated; however, this right of City to stop the Work shall not give rise to any duty on the part of City to exercise this right for the benefit of Contractor, any Subcontractor, any Supplier, any other individual or entity, or any surety for, or employee or agent of any of them. 11.06 Correction or Removal of Defective Work A. Promptly after receipt of written notice, Contractor shall correct all defective Work pursuant to an acceptable schedule, whether or not fabricated, installed, or completed, or, if the Work has been rejected by City, remove it from the Project and replace it with Work that is not defective. Contractor shall pay all claims, costs, additional testing, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) arising out of or relating to such correction or removal (including but not limited to all costs of repair or replacement of work of others). Failure to require the removal of any defective Work shall not constitute acceptance of such Work. B. When correcting defective Work under the terms of this Paragraph 11.06 or Paragraph 11.07, Contractor shall take no action that would void or otherwise impair City’s special warranty and guarantee, if any, on said Work. 11.07 Correction Period A. If within two (2) years after the date of Final Acceptance (or such longer period of time as may be prescribed by the terms of any applicable special guarantee required by the Contract 00 73 10- 31 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 31 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 Documents), any Work is found to be defective, or if the repair of any damages to the land or areas made available for Contractor’s use by City or permitted by Laws and Regulations as contemplated in Paragraph 5.10.A is found to be defective, Contractor shall promptly, without cost to City and in accordance with City’s written instructions: 1. repair such defective land or areas; or 2. correct such defective Work; or 3. if the defective Work has been rejected by City, remove it from the Project and replace it with Work that is not defective, and 4. satisfactorily correct or repair or remove and replace any damage to other Work, to the work of others or other land or areas resulting therefrom. B. If Contractor does not promptly comply with the terms of City’s written instructions, or in an emergency where delay would cause serious risk of loss or damage, City may have the defective Work corrected or repaired or may have the rejected Work removed and replaced. All claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or other dispute resolution costs) arising out of or relating to such correction or repair or such removal and replacement (including but not limited to all costs of repair or replacement of work of others) will be paid by Contractor. C. Where defective Work (and damage to other Work resulting therefrom) has been corrected or removed and replaced under this Paragraph 11.07, the correction period hereunder with respect to such Work may be required to be extended for an additional period of one year after the end of the initial correction period. City shall provide 30 days written notice to Contractor and Developer should such additional warranty coverage be required. Contractor’s obligations under this Paragraph 11.07 are in addition to any other obligation or warranty. The provisions of this Paragraph 11.07 shall not be construed as a substitute for, or a waiver of, the provisions of any applicable statute of limitation or repose. 11.08 City May Correct Defective Work A. If Contractor fails within a reasonable time after written notice from City to correct defective Work, or to remove and replace rejected Work as required by City in accordance with Paragraph 11.06.A, or if Contractor fails to perform the Work in accordance with the Contract Documents, or if Contractor fails to comply with any other provision of the Contract Documents, City may, after seven (7) days written notice to Contractor and the Developer, correct, or remedy any such deficiency. B. In exercising the rights and remedies under this Paragraph 11.09, City shall proceed expeditiously. In connection with such corrective or remedial action, City may exclude Contractor from all or part of the Site, take possession of all or part of the Work and suspend Contractor’s services related thereto, and incorporate in the Work all materials and equipment incorporated in the Work, stored at the Site or for which City has paid Contractor but which are 00 73 10- 32 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 32 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 stored elsewhere. Contractor shall allow City, City’s representatives, agents, consultants, employees, and City’s other contractors, access to the Site to enable City to exercise the rights and remedies under this Paragraph. C. All claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or other dispute resolution costs) incurred or sustained by City in exercising the rights and remedies under this Paragraph 13.09 will be charged against Contractor, and a Change Order will be issued incorporating the necessary revisions in the Contract Documents with respect to the Work; and City shall be entitled to an appropriate decrease in the Contract Price. D. Contractor shall not be allowed an extension of the Contract Time because of any delay in the performance of the Work attributable to the exercise of City’s rights and remedies under this Paragraph 11.09. ARTICLE 12 – COMPLETION 12.01 Contractor’s Warranty of Title Contractor warrants and guarantees that title to all Work, materials, and equipment covered by any Application for Payment will pass to City no later than the time of Final Acceptance and shall be free and clear of all Liens. 12.02 Partial Utilization A. Prior to Final Acceptance of all the Work, City may use or occupy any substantially completed part of the Work which has specifically been identified in the Contract Documents, or which City, determines constitutes a separately functioning and usable part of the Work that can be used by City for its intended purpose without significant interference with Contractor’s performance of the remainder of the Work. City at any time may notify Contractor in writing to permit City to use or occupy any such part of the Work which City determines to be ready for its intended use, subject to the following conditions: 1. Contractor at any time may notify City in writing that Contractor considers any such part of the Work ready for its intended use. 2. Within a reasonable time after notification as enumerated in Paragraph 14.05.A.1, City and Contractor shall make an inspection of that part of the Work to determine its status of completion. If City does not consider that part of the Work to be substantially complete, City will notify Contractor in writing giving the reasons therefor. 3. Partial Utilization will not constitute Final Acceptance by City. 12.03 Final Inspection A. Upon written notice from Contractor that the entire Work is complete in accordance with the Contract Documents: 00 73 10- 33 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 33 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 1. within 10 days, City will schedule a Final Inspection with Contractor. 2. City will notify Contractor in writing of all particulars in which this inspection reveals that the Work is incomplete or defective. Contractor shall immediately take such measures as are necessary to complete such Work or remedy such deficiencies. 12.04 Final Acceptance A. Upon completion by Contractor to City’s satisfaction, of any additional Work identified in the Final Inspection, City will issue to Contractor a letter of Final Acceptance upon the satisfaction of the following: 1. All documentation called for in the Contract Documents, including but not limited to the evidence of insurance required by Paragraph 5.03; 2. consent of the surety, if any, to Final Acceptance; 3. a list of all pending or released Damage Claims against City that Contractor believes are unsettled; and 4. affidavits of payments and complete and legally effective releases or waivers (satisfactory to City) of all Lien rights arising out of or Liens filed in connection with the Work. 5. after all Damage Claims have been resolved: a. directly by the Contractor or; b. Contractor provides evidence that the Damage Claim has been reported to Contractor’s insurance provider for resolution. 6. Issuing Final Acceptance by the City shall not relieve the Contractor of any guarantees or other requirements of the Contract Documents which specifically continue thereafter. ARTICLE 13 – SUSPENSION OF WORK 13.01 City May Suspend Work A. At any time and without cause, City may suspend the Work or any portion thereof by written notice to Contractor and which may fix the date on which Work will be resumed. Contractor shall resume the Work on the date so fixed. During temporary suspension of the Work covered by these Contract Documents, for any reason, the City will stop contract time on City participation projects. B. Should the Contractor not be able to complete a portion of the Project due to causes beyond the control of and without the fault or negligence of the Contractor, and should it be determined by mutual consent of the Contractor and City that a solution to allow construction to proceed is not 00 73 10- 34 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 34 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 available within a reasonable period of time, Contractor may request an extension in Contract Time, directly attributable to any such suspension. C. If it should become necessary to suspend the Work for an indefinite period, the Contractor shall store all materials in such a manner that they will not obstruct or impede the public unnecessarily nor become damaged in any way, and he shall take every precaution to prevent damage or deterioration of the work performed; he shall provide suitable drainage about the work, and erect temporary structures where necessary. ARTICLE 14 – MISCELLANEOUS 14.01 Giving Notice A. Whenever any provision of the Contract Documents requires the giving of written notice, it will be deemed to have been validly given if: 1. delivered in person to the individual or to a member of the firm or to an officer of the corporation for whom it is intended; or 2. delivered at or sent by registered or certified mail, postage prepaid, to the last business address known to the giver of the notice. B. Business address changes must be promptly made in writing to the other party. C. Whenever the Contract Documents specifies giving notice by electronic means such electronic notice shall be deemed sufficient upon confirmation of receipt by the receiving party. 14.02 Computation of Times When any period of time is referred to in the Contract Documents by days, it will be computed to exclude the first and include the last day of such period. If the last day of any such period falls on a Saturday or Sunday or on a day made a legal holiday the next Working Day shall become the last day of the period. 14.03 Cumulative Remedies The duties and obligations imposed by these General Conditions and the rights and remedies available hereunder to the parties hereto are in addition to, and are not to be construed in any way as a limitation of, any rights and remedies available to any or all of them which are otherwise imposed or available by Laws or Regulations, by special warranty or guarantee, or by other provisions of the Contract Documents. The provisions of this Paragraph will be as effective as if repeated specifically in the Contract Documents in connection with each particular duty, obligation, right, and remedy to which they apply. 00 73 10- 35 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 35 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 14.04 Survival of Obligations All representations, indemnifications, warranties, and guarantees made in, required by, or given in accordance with the Contract Documents, as well as all continuing obligations indicated in the Contract Documents, will survive final payment, completion, and acceptance of the Work or termination or completion of the Contract or termination of the services of Contractor. 14.05 Headings Article and paragraph headings are inserted for convenience only and do not constitute parts of these General Conditions. DIVISION 01 GENERAL REQUIREMENTS 01 11 00 - 1 DAP SUMMARY OF WORK Page 1 of 3 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – Developer Awarded Projects City Project #103754 Revised December 20, 2012 SECTION 01 11 00 SUMMARY OF WORK PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Summary of Work to be performed in accordance with the Contract Documents B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the Contract 2. Division 1 - General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS A. Work Covered by Contract Documents 1. Work is to include furnishing all labor, materials, and equipment, and performing all Work necessary for this construction project as detailed in the Drawings and Specifications. B. Subsidiary Work 1. Any and all Work specifically governed by documentary requirements for the project, such as conditions imposed by the Drawings or Contract Documents in which no specific item for bid has been provided for in the Proposal and the item is not a typical unit bid item included on the standard bid item list, then the item shall be considered as a subsidiary item of Work, the cost of which shall be included in the price bid in the Proposal for various bid items. C. Use of Premises 1. Coordinate uses of premises under direction of the City. 2. Assume full responsibility for protection and safekeeping of materials and equipment stored on the Site. 3. Use and occupy only portions of the public streets and alleys, or other public places or other rights-of-way as provided for in the ordinances of the City, as shown in the Contract Documents, or as may be specifically authorized in writing by the City. a. A reasonable amount of tools, materials, and equipment for construction purposes may be stored in such space, but no more than is necessary to avoid delay in the construction operations. 01 11 00 - 2 DAP SUMMARY OF WORK Page 2 of 3 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – Developer Awarded Projects City Project #103754 Revised December 20, 2012 b. Excavated and waste materials shall be stored in such a way as not to interfere with the use of spaces that may be designated to be left free and unobstructed and so as not to inconvenience occupants of adjacent property. c. If the street is occupied by railroad tracks, the Work shall be carried on in such manner as not to interfere with the operation of the railroad. 1) All Work shall be in accordance with railroad requirements set forth in Division 0 as well as the railroad permit. D. Work within Easements 1. Do not enter upon private property for any purpose without having previously obtained permission from the owner of such property. 2. Do not store equipment or material on private property unless and until the specified approval of the property owner has been secured in writing by the Contractor and a copy furnished to the City. 3. Unless specifically provided otherwise, clear all rights-of-way or easements of obstructions which must be removed to make possible proper prosecution of the Work as a part of the project construction operations. 4. Preserve and use every precaution to prevent damage to, all trees, shrubbery, plants, lawns, fences, culverts, curbing, and all other types of structures or improvements, to all water, sewer, and gas lines, to all conduits, overhead pole lines, or appurtenances thereof, including the construction of temporary fences and to all other public or private property adjacent to the Work. 5. Notify the proper representatives of the owners or occupants of the public or private lands of interest in lands which might be affected by the Work. a. Such notice shall be made at least 48 hours in advance of the beginning of the Work. b. Notices shall be applicable to both public and private utility companies and any corporation, company, individual, or other, either as owners or occupants, whose land or interest in land might be affected by the Work. c. Be responsible for all damage or injury to property of any character resulting from any act, omission, neglect, or misconduct in the manner or method or execution of the Work, or at any time due to defective work, material, or equipment. 6. Fence a. Restore all fences encountered and removed during construction of the Project to the original or a better than original condition. b. Erect temporary fencing in place of the fencing removed whenever the Work is not in progress and when the site is vacated overnight, and/or at all times to provide site security. c. The cost for all fence work within easements, including removal, temporary closures and replacement, shall be subsidiary to the various items bid in the project proposal, unless a bid item is specifically provided in the proposal. 01 11 00 - 3 DAP SUMMARY OF WORK Page 3 of 3 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – Developer Awarded Projects City Project #103754 Revised December 20, 2012 1.5 SUBMITTALS [NOT USED] 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE [NOT USED] 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 01 25 00 - 1 DAP SUBSTITUTION PROCEDURES Page 1 of 4 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised August 30, 2013 SECTION 01 25 00 SUBSTITUTION PROCEDURES PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. The procedure for requesting the approval of substitution of a product that is not equivalent to a product which is specified by descriptive or performance criteria or defined by reference to 1 or more of the following: a. Name of manufacturer b. Name of vendor c. Trade name d. Catalog number 2. Substitutions are not "or-equals". B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS A. Request for Substitution - General 1. Within 30 days after award of Contract (unless noted otherwise), the City will consider formal requests from Contractor for substitution of products in place of those specified. 2. Certain types of equipment and kinds of material are described in Specifications by means of references to names of manufacturers and vendors, trade names, or catalog numbers. a. When this method of specifying is used, it is not intended to exclude from consideration other products bearing other manufacturer's or vendor's names, trade names, or catalog numbers, provided said products are "or-equals," as determined by City. 3. Other types of equipment and kinds of material may be acceptable substitutions under the following conditions: a. Or-equals are unavailable due to strike, discontinued production of products meeting specified requirements, or other factors beyond control of Contractor; or, 01 25 00 - 2 DAP SUBSTITUTION PROCEDURES Page 2 of 4 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised August 30, 2013 b. Contractor proposes a cost and/or time reduction incentive to the City. 1.5 SUBMITTALS A. See Request for Substitution Form (attached) B. Procedure for Requesting Substitution 1. Substitution shall be considered only: a. After award of Contract b. Under the conditions stated herein 2. Submit 3 copies of each written request for substitution, including: a. Documentation 1) Complete data substantiating compliance of proposed substitution with Contract Documents 2) Data relating to changes in construction schedule, when a reduction is proposed 3) Data relating to changes in cost b. For products 1) Product identification a) Manufacturer's name b) Telephone number and representative contact name c) Specification Section or Drawing reference of originally specified product, including discrete name or tag number assigned to original product in the Contract Documents 2) Manufacturer's literature clearly marked to show compliance of proposed product with Contract Documents 3) Itemized comparison of original and proposed product addressing product characteristics including, but not necessarily limited to: a) Size b) Composition or materials of construction c) Weight d) Electrical or mechanical requirements 4) Product experience a) Location of past projects utilizing product b) Name and telephone number of persons associated with referenced projects knowledgeable concerning proposed product c) Available field data and reports associated with proposed product 5) Samples a) Provide at request of City. b) Samples become the property of the City. c. For construction methods: 1) Detailed description of proposed method 2) Illustration drawings C. Approval or Rejection 1. Written approval or rejection of substitution given by the City 2. City reserves the right to require proposed product to comply with color and pattern of specified product if necessary to secure design intent. 3. In the event the substitution is approved, if a reduction in cost or time results, it will be documented by Change Order. 01 25 00 - 3 DAP SUBSTITUTION PROCEDURES Page 3 of 4 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised August 30, 2013 4. Substitution will be rejected if: a. Submittal is not through the Contractor with his stamp of approval b. Request is not made in accordance with this Specification Section c. In the Developer’s opinion, acceptance will require substantial revision of the original design d. In the City’s or Developer’s opinion, substitution will not perform adequately the function consistent with the design intent 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE A. In making request for substitution or in using an approved product, the Contractor represents that the Contractor: 1. Has investigated proposed product, and has determined that it is adequate or superior in all respects to that specified, and that it will perform function for which it is intended 2. Will provide same guarantee for substitute item as for product specified 3. Will coordinate installation of accepted substitution into Work, to include building modifications if necessary, making such changes as may be required for Work to be complete in all respects 4. Waives all claims for additional costs related to substitution which subsequently arise 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 01 25 00 - 4 DAP SUBSTITUTION PROCEDURES Page 4 of 4 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised August 30, 2013 EXHIBIT A REQUEST FOR SUBSTITUTION FORM: TO: PROJECT: DATE: We hereby submit for your consideration the following product instead of the specified item for the above project: SECTION PARAGRAPH SPECIFIED ITEM Proposed Substitution: Reason for Substitution: Include complete information on changes to Drawings and/or Specifications which proposed substitution will require for its proper installation. Fill in Blanks Below: A. Will the undersigned contractor pay for changes to the building design, including engineering and detailing costs caused by the requested substitution? B. What effect does substitution have on other trades? C. Differences between proposed substitution and specified item? D. Differences in product cost or product delivery time? E. Manufacturer's guarantees of the proposed and specified items are: Equal Better (explain on attachment) The undersigned states that the function, appearance and quality are equivalent or superior to the specified item. Submitted By: For Use by City Signature Recommended Recommended as noted Firm Not recommended Received late Address By Date Date Remarks Telephone For Use by City: Approved Rejected City Date 01 31 19 - 1 DAP PRECONSTRUCTION MEETING Page 1 of 3 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised August 30, 2013 SECTION 01 31 19 PRECONSTRUCTION MEETING PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Provisions for the preconstruction meeting to be held prior to the start of Work to clarify construction contract administration procedures B. Deviations from this City of Fort Worth Standard Specification 1. No construction schedule required unless requested by the City. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS A. Coordination 1. Attend preconstruction meeting. 2. Representatives of Contractor, subcontractors and suppliers attending meetings shall be qualified and authorized to act on behalf of the entity each represents. 3. Meeting administered by City may be tape recorded. a. If recorded, tapes will be used to prepare minutes and retained by City for future reference. B. Preconstruction Meeting 1. A preconstruction meeting will be held within 14 days after the delivery of the distribution package to the City. a. The meeting will be scheduled and administered by the City. 2. The Project Representative will preside at the meeting, prepare the notes of the meeting and distribute copies of same to all participants who so request by fully completing the attendance form to be circulated at the beginning of the meeting. 3. Attendance shall include: a. Developer and Consultant b. Contractor's project manager c. Contractor's superintendent d. Any subcontractor or supplier representatives whom the Contractor may desire to invite or the City may request 01 31 19 - 2 DAP PRECONSTRUCTION MEETING Page 2 of 3 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised August 30, 2013 e. Other City representatives f. Others as appropriate 4. Preliminary Agenda may include: a. Introduction of Project Personnel b. General Description of Project c. Status of right-of-way, utility clearances, easements or other pertinent permits d. Contractor’s work plan and schedule e. Contract Time f. Notice to Proceed g. Construction Staking h. Progress Payments i. Extra Work and Change Order Procedures j. Field Orders k. Disposal Site Letter for Waste Material l. Insurance Renewals m. Payroll Certification n. Material Certifications and Quality Control Testing o. Public Safety and Convenience p. Documentation of Pre-Construction Conditions q. Weekend Work Notification r. Legal Holidays s. Trench Safety Plans t. Confined Space Entry Standards u. Coordination with the City’s representative for operations of existing water systems v. Storm Water Pollution Prevention Plan w. Coordination with other Contractors x. Early Warning System y. Contractor Evaluation z. Special Conditions applicable to the project aa. Damages Claims bb. Submittal Procedures cc. Substitution Procedures dd. Correspondence Routing ee. Record Drawings ff. Temporary construction facilities gg. MBE/SBE procedures hh. Final Acceptance ii. Final Payment jj. Questions or Comments 01 31 19 - 3 DAP PRECONSTRUCTION MEETING Page 3 of 3 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised August 30, 2013 1.5 SUBMITTALS [NOT USED] 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE [NOT USED] 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 01 32 33 - 1 DAP PRECONSTRUCTION VIDEO Page 1 of 2 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised August 30, 2013 SECTION 01 32 33 PRECONSTRUCTION VIDEO PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Administrative and procedural requirements for: a. Preconstruction Videos B. Deviations from this City of Fort Worth Standard Specification 1. Though not mandatory, it is highly recommended on infill developer projects. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS A. Preconstruction Video 1. Produce a preconstruction video of the site/alignment, including all areas in the vicinity of and to be affected by construction. a. Provide digital copy of video upon request by the City. 2. Retain a copy of the preconstruction video until the end of the maintenance surety period. 1.5 SUBMITTALS [NOT USED] 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE [NOT USED] 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS [NOT USED] 01 32 33 - 2 DAP PRECONSTRUCTION VIDEO Page 2 of 2 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised August 30, 2013 PART 3 - EXECUTION [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 01 33 00 - 1 DAP SUBMITTALS Page 1 of 8 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised August 30, 2013 SECTION 01 33 00 DAP SUBMITTALS PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. General methods and requirements of submissions applicable to the following Work-related submittals: a. Shop Drawings b. Product Data (including Standard Product List submittals) c. Samples d. Mock Ups B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS A. Coordination 1. Notify the City in writing, at the time of submittal, of any deviations in the submittals from the requirements of the Contract Documents. 2. Coordination of Submittal Times a. Prepare, prioritize and transmit each submittal sufficiently in advance of performing the related Work or other applicable activities, or within the time specified in the individual Work Sections, of the Specifications. b. Contractor is responsible such that the installation will not be delayed by processing times including, but not limited to: a) Disapproval and resubmittal (if required) b) Coordination with other submittals c) Testing d) Purchasing e) Fabrication f) Delivery g) Similar sequenced activities c. No extension of time will be authorized because of the Contractor's failure to transmit submittals sufficiently in advance of the Work. 01 33 00 - 2 DAP SUBMITTALS Page 2 of 8 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised August 30, 2013 d. Make submittals promptly in accordance with approved schedule, and in such sequence as to cause no delay in the Work or in the work of any other contractor. B. Submittal Numbering 1. When submitting shop drawings or samples, utilize a 9-character submittal cross- reference identification numbering system in the following manner: a. Use the first 6 digits of the applicable Specification Section Number. b. For the next 2 digits number use numbers 01-99 to sequentially number each initial separate item or drawing submitted under each specific Section number. c. Last use a letter, A-Z, indicating the resubmission of the same drawing (i.e. A=2nd submission, B=3rd submission, C=4th submission, etc.). A typical submittal number would be as follows: 03 30 00-08-B 1) 03 30 00 is the Specification Section for Concrete 2) 08 is the eighth initial submittal under this Specification Section 3) B is the third submission (second resubmission) of that particular shop drawing C. Contractor Certification 1. Review shop drawings, product data and samples, including those by subcontractors, prior to submission to determine and verify the following: a. Field measurements b. Field construction criteria c. Catalog numbers and similar data d. Conformance with the Contract Documents 2. Provide each shop drawing, sample and product data submitted by the Contractor with a Certification Statement affixed including: a. The Contractor's Company name b. Signature of submittal reviewer c. Certification Statement 1) “By this submittal, I hereby represent that I have determined and verified field measurements, field construction criteria, materials, dimensions, catalog numbers and similar data and I have checked and coordinated each item with other applicable approved shop drawings." D. Submittal Format 1. Fold shop drawings larger than 8 ½ inches x 11 inches to 8 ½ inches x 11inches. 2. Bind shop drawings and product data sheets together. 3. Order a. Cover Sheet 1) Description of Packet 2) Contractor Certification b. List of items / Table of Contents c. Product Data /Shop Drawings/Samples /Calculations E. Submittal Content 1. The date of submission and the dates of any previous submissions 01 33 00 - 3 DAP SUBMITTALS Page 3 of 8 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised August 30, 2013 2. The Project title and number 3. Contractor identification 4. The names of: a. Contractor b. Supplier c. Manufacturer 5. Identification of the product, with the Specification Section number, page and paragraph(s) 6. Field dimensions, clearly identified as such 7. Relation to adjacent or critical features of the Work or materials 8. Applicable standards, such as ASTM or Federal Specification numbers 9. Identification by highlighting of deviations from Contract Documents 10. Identification by highlighting of revisions on resubmittals 11. An 8-inch x 3-inch blank space for Contractor and City stamps F. Shop Drawings 1. As specified in individual Work Sections includes, but is not necessarily limited to: a. Custom-prepared data such as fabrication and erection/installation (working) drawings b. Scheduled information c. Setting diagrams d. Actual shopwork manufacturing instructions e. Custom templates f. Special wiring diagrams g. Coordination drawings h. Individual system or equipment inspection and test reports including: 1) Performance curves and certifications i. As applicable to the Work 2. Details a. Relation of the various parts to the main members and lines of the structure b. Where correct fabrication of the Work depends upon field measurements 1) Provide such measurements and note on the drawings prior to submitting for approval. G. Product Data 1. For submittals of product data for products included on the City’s Standard Product List, clearly identify each item selected for use on the Project. 2. For submittals of product data for products not included on the City’s Standard Product List, submittal data may include, but is not necessarily limited to: a. Standard prepared data for manufactured products (sometimes referred to as catalog data) 1) Such as the manufacturer's product specification and installation instructions 2) Availability of colors and patterns 3) Manufacturer's printed statements of compliances and applicability 4) Roughing-in diagrams and templates 5) Catalog cuts 6) Product photographs 01 33 00 - 4 DAP SUBMITTALS Page 4 of 8 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised August 30, 2013 7) Standard wiring diagrams 8) Printed performance curves and operational-range diagrams 9) Production or quality control inspection and test reports and certifications 10) Mill reports 11) Product operating and maintenance instructions and recommended spare-parts listing and printed product warranties 12) As applicable to the Work H. Samples 1. As specified in individual Sections, include, but are not necessarily limited to: a. Physical examples of the Work such as: 1) Sections of manufactured or fabricated Work 2) Small cuts or containers of materials 3) Complete units of repetitively used products color/texture/pattern swatches and range sets 4) Specimens for coordination of visual effect 5) Graphic symbols and units of Work to be used by the City for independent inspection and testing, as applicable to the Work I. Do not start Work requiring a shop drawing, sample or product data nor any material to be fabricated or installed prior to the approval or qualified approval of such item. 1. Fabrication performed, materials purchased or on-site construction accomplished which does not conform to approved shop drawings and data is at the Contractor's risk. 2. The City will not be liable for any expense or delay due to corrections or remedies required to accomplish conformity. 3. Complete project Work, materials, fabrication, and installations in conformance with approved shop drawings, applicable samples, and product data. J. Submittal Distribution 1. Electronic Distribution a. Confirm development of Project directory for electronic submittals to be uploaded to City’s Buzzsaw site, or another external FTP site approved by the City. b. Shop Drawings 1) Upload submittal to designated project directory and notify appropriate City representatives via email of submittal posting. 2) Hard Copies a) 3 copies for all submittals b) If Contractor requires more than 1 hard copy of Shop Drawings returned, Contractor shall submit more than the number of copies listed above. c. Product Data 1) Upload submittal to designated project directory and notify appropriate City representatives via email of submittal posting. 2) Hard Copies a) 3 copies for all submittals d. Samples 1) Distributed to the Project Representative 2. Hard Copy Distribution (if required in lieu of electronic distribution) 01 33 00 - 5 DAP SUBMITTALS Page 5 of 8 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised August 30, 2013 a. Shop Drawings 1) Distributed to the City 2) Copies a) 8 copies for mechanical submittals b) 7 copies for all other submittals c) If Contractor requires more than 3 copies of Shop Drawings returned, Contractor shall submit more than the number of copies listed above. b. Product Data 1) Distributed to the City 2) Copies a) 4 copies c. Samples 1) Distributed to the Project Representative 2) Copies a) Submit the number stated in the respective Specification Sections. 3. Distribute reproductions of approved shop drawings and copies of approved product data and samples, where required, to the job site file and elsewhere as directed by the City. a. Provide number of copies as directed by the City but not exceeding the number previously specified. K. Submittal Review 1. The review of shop drawings, data and samples will be for general conformance with the design concept and Contract Documents. This is not to be construed as: a. Permitting any departure from the Contract requirements b. Relieving the Contractor of responsibility for any errors, including details, dimensions, and materials c. Approving departures from details furnished by the City, except as otherwise provided herein 2. The review and approval of shop drawings, samples or product data by the City does not relieve the Contractor from his/her responsibility with regard to the fulfillment of the terms of the Contract. a. All risks of error and omission are assumed by the Contractor, and the City will have no responsibility therefore. 3. The Contractor remains responsible for details and accuracy, for coordinating the Work with all other associated work and trades, for selecting fabrication processes, for techniques of assembly and for performing Work in a safe manner. 4. If the shop drawings, data or samples as submitted describe variations and show a departure from the Contract requirements which City finds to be in the interest of the City and to be so minor as not to involve a change in Contract Price or time for performance, the City may return the reviewed drawings without noting an exception. 5. Submittals will be returned to the Contractor under 1 of the following codes: a. Code 1 1) "NO EXCEPTIONS TAKEN" is assigned when there are no notations or comments on the submittal. a) When returned under this code the Contractor may release the equipment and/or material for manufacture. b. Code 2 01 33 00 - 6 DAP SUBMITTALS Page 6 of 8 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised August 30, 2013 1) "EXCEPTIONS NOTED". This code is assigned when a confirmation of the notations and comments IS NOT required by the Contractor. a) The Contractor may release the equipment or material for manufacture; however, all notations and comments must be incorporated into the final product. c. Code 3 1) "EXCEPTIONS NOTED/RESUBMIT". This combination of codes is assigned when notations and comments are extensive enough to require a resubmittal of the package. a) The Contractor may release the equipment or material for manufacture; however, all notations and comments must be incorporated into the final product. b) This resubmittal is to address all comments, omissions and non-conforming items that were noted. c) Resubmittal is to be received by the City within 15 Calendar Days of the date of the City's transmittal requiring the resubmittal. d. Code 4 1) "NOT APPROVED" is assigned when the submittal does not meet the intent of the Contract Documents. a) The Contractor must resubmit the entire package revised to bring the submittal into conformance. b) It may be necessary to resubmit using a different manufacturer/vendor to meet the Contract Documents. 6. Resubmittals a. Handled in the same manner as first submittals 1) Corrections other than requested by the City 2) Marked with revision triangle or other similar method a) At Contractor’s risk if not marked b. Submittals for each item will be reviewed no more than twice at the City’s expense. 1) All subsequent reviews will be performed at times convenient to the City and at the Contractor's expense, based on the City's or City Representative’s then prevailing rates. 2) Provide Contractor reimbursement to the City within 30 Calendar Days for all such fees invoiced by the City. c. The need for more than 1 resubmission or any other delay in obtaining City's review of submittals, will not entitle the Contractor to an extension of Contract Time. 7. Partial Submittals a. City reserves the right to not review submittals deemed partial, at the City’s discretion. b. Submittals deemed by the City to be not complete will be returned to the Contractor, and will be considered "Not Approved" until resubmitted. c. The City may at its option provide a list or mark the submittal directing the Contractor to the areas that are incomplete. 8. If the Contractor considers any correction indicated on the shop drawings to constitute a change to the Contract Documents, then written notice must be provided thereof to the Developer at least 7 Calendar Days prior to release for manufacture. 01 33 00 - 7 DAP SUBMITTALS Page 7 of 8 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised August 30, 2013 9. When the shop drawings have been completed to the satisfaction of the City, the Contractor may carry out the construction in accordance therewith and no further changes therein except upon written instructions from the City. 10. Each submittal, appropriately coded, will be returned within 30 Calendar Days following receipt of submittal by the City. L. Mock ups 1. Mock Up units as specified in individual Sections, include, but are not necessarily limited to, complete units of the standard of acceptance for that type of Work to be used on the Project. Remove at the completion of the Work or when directed. M. Qualifications 1. If specifically required in other Sections of these Specifications, submit a P.E. Certification for each item required. N. Request for Information (RFI) 1. Contractor Request for additional information a. Clarification or interpretation of the contract documents b. When the Contractor believes there is a conflict between Contract Documents c. When the Contractor believes there is a conflict between the Drawings and Specifications 1) Identify the conflict and request clarification 2. Sufficient information shall be attached to permit a written response without further information. 1.5 SUBMITTALS [NOT USED] 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE [NOT USED] 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] 01 33 00 - 8 DAP SUBMITTALS Page 8 of 8 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised August 30, 2013 PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 12/20/2012 D. Johnson 1.4.K.8. Working Days modified to Calendar Days 01 35 13 - 1 DAP SPECIAL PROJECT PROCEDURES Page 1 of 7 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised August, 30, 2013 SECTION 01 35 13 SPECIAL PROJECT PROCEDURES PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. The procedures for special project circumstances that includes, but is not limited to: a. Coordination with the Texas Department of Transportation b. Work near High Voltage Lines c. Confined Space Entry Program d. Air Pollution Watch Days e. Use of Explosives, Drop Weight, Etc. f. Water Department Notification g. Public Notification Prior to Beginning Construction h. Coordination with United States Army Corps of Engineers i. Coordination within Railroad permits areas j. Dust Control k. Employee Parking B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 3. Section 33 12 25 – Connection to Existing Water Mains 1.2 REFERENCES A. Reference Standards 1. Reference standards cited in this Specification refer to the current reference standard published at the time of the latest revision date logged at the end of this Specification, unless a date is specifically cited. 2. Health and Safety Code, Title 9. Safety, Subtitle A. Public Safety, Chapter 752. High Voltage Overhead Lines. 3. North Central Texas Council of Governments (NCTCOG) – Clean Construction Specification 1.3 ADMINISTRATIVE REQUIREMENTS A. Coordination with the Texas Department of Transportation 1. When work in the right-of-way which is under the jurisdiction of the Texas Department of Transportation (TxDOT): a. Notify the Texas Department of Transportation prior to commencing any work therein in accordance with the provisions of the permit 01 35 13 - 2 DAP SPECIAL PROJECT PROCEDURES Page 2 of 7 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised August, 30, 2013 b. All work performed in the TxDOT right-of-way shall be performed in compliance with and subject to approval from the Texas Department of Transportation B. Work near High Voltage Lines 1. Regulatory Requirements a. All Work near High Voltage Lines (more than 600 volts measured between conductors or between a conductor and the ground) shall be in accordance with Health and Safety Code, Title 9, Subtitle A, Chapter 752. 2. Warning sign a. Provide sign of sufficient size meeting all OSHA requirements. 3. Equipment operating within 10 feet of high voltage lines will require the following safety features a. Insulating cage-type of guard about the boom or arm b. Insulator links on the lift hook connections for back hoes or dippers c. Equipment must meet the safety requirements as set forth by OSHA and the safety requirements of the owner of the high voltage lines 4. Work within 6 feet of high voltage electric lines a. Notification shall be given to: 1) The power company (example: ONCOR) a) Maintain an accurate log of all such calls to power company and record action taken in each case. b. Coordination with power company 1) After notification coordinate with the power company to: a) Erect temporary mechanical barriers, de-energize the lines, or raise or lower the lines c. No personnel may work within 6 feet of a high voltage line before the above requirements have been met. C. Confined Space Entry Program 1. Provide and follow approved Confined Space Entry Program in accordance with OSHA requirements. 2. Confined Spaces include: a. Manholes b. All other confined spaces in accordance with OSHA’s Permit Required for Confined Spaces D. Use of Explosives, Drop Weight, Etc. 1. When Contract Documents permit on the project the following will apply: a. Public Notification 1) Submit notice to City and proof of adequate insurance coverage, 24 hours prior to commencing. 2) Minimum 24 hour public notification in accordance with Section 01 31 13 E. Water Department Coordination 1. During the construction of this project, it will be necessary to deactivate, for a period of time, existing lines. The Contractor shall be required to coordinate with the Water Department to determine the best times for deactivating and activating those lines. 01 35 13 - 3 DAP SPECIAL PROJECT PROCEDURES Page 3 of 7 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised August, 30, 2013 2. Coordinate any event that will require connecting to or the operation of an existing City water line system with the City’s representative. a. Coordination shall be in accordance with Section 33 12 25. b. If needed, obtain a hydrant water meter from the Water Department for use during the life of named project. c. In the event that a water valve on an existing live system be turned off and on to accommodate the construction of the project is required, coordinate this activity through the appropriate City representative. 1) Do not operate water line valves of existing water system. a) Failure to comply will render the Contractor in violation of Texas Penal Code Title 7, Chapter 28.03 (Criminal Mischief) and the Contractor will be prosecuted to the full extent of the law. b) In addition, the Contractor will assume all liabilities and responsibilities as a result of these actions. F. Public Notification Prior to Beginning Construction 1. Prior to beginning construction on any block in the project, on a block by block basis, prepare and deliver a notice or flyer of the pending construction to the front door of each residence or business that will be impacted by construction. The notice shall be prepared as follows: a. Post notice or flyer 7 days prior to beginning any construction activity on each block in the project area. 1) Prepare flyer on the Contractor’s letterhead and include the following information: a) Name of Project b) City Project No (CPN) c) Scope of Project (i.e. type of construction activity) d) Actual construction duration within the block e) Name of the contractor’s foreman and phone number f) Name of the City’s inspector and phone number g) City’s after-hours phone number 2) A sample of the ‘pre-construction notification’ flyer is attached as Exhibit A. 3) Submit schedule showing the construction start and finish time for each block of the project to the inspector. 4) Deliver flyer to the City Inspector for review prior to distribution. b. No construction will be allowed to begin on any block until the flyer is delivered to all residents of the block. G. Public Notification of Temporary Water Service Interruption during Construction 1. In the event it becomes necessary to temporarily shut down water service to residents or businesses during construction, prepare and deliver a notice or flyer of the pending interruption to the front door of each affected resident. 2. Prepared notice as follows: a. The notification or flyer shall be posted 24 hours prior to the temporary interruption. b. Prepare flyer on the contractor’s letterhead and include the following information: 1) Name of the project 2) City Project Number 01 35 13 - 4 DAP SPECIAL PROJECT PROCEDURES Page 4 of 7 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised August, 30, 2013 3) Date of the interruption of service 4) Period the interruption will take place 5) Name of the contractor’s foreman and phone number 6) Name of the City’s inspector and phone number c. A sample of the temporary water service interruption notification is attached as Exhibit B. d. Deliver a copy of the temporary interruption notification to the City inspector for review prior to being distributed. e. No interruption of water service can occur until the flyer has been delivered to all affected residents and businesses. f. Electronic versions of the sample flyers can be obtained from the Project Construction Inspector. H. Coordination with United States Army Corps of Engineers (USACE) 1. At locations in the Project where construction activities occur in areas where USACE permits are required, meet all requirements set forth in each designated permit. I. Coordination within Railroad Permit Areas 1. At locations in the project where construction activities occur in areas where railroad permits are required, meet all requirements set forth in each designated railroad permit. This includes, but is not limited to, provisions for: a. Flagmen b. Inspectors c. Safety training d. Additional insurance e. Insurance certificates f. Other employees required to protect the right-of-way and property of the Railroad Company from damage arising out of and/or from the construction of the project. Proper utility clearance procedures shall be used in accordance with the permit guidelines. 2. Obtain any supplemental information needed to comply with the railroad’s requirements. J. Dust Control 1. Use acceptable measures to control dust at the Site. a. If water is used to control dust, capture and properly dispose of waste water. b. If wet saw cutting is performed, capture and properly dispose of slurry. K. Employee Parking 1. Provide parking for employees at locations approved by the City. 01 35 13 - 5 DAP SPECIAL PROJECT PROCEDURES Page 5 of 7 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised August, 30, 2013 1.4 SUBMITTALS [NOT USED] 1.5 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1.6 CLOSEOUT SUBMITTALS [NOT USED] 1.7 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.8 QUALITY ASSURANCE [NOT USED] 1.9 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1.10 FIELD [SITE] CONDITIONS [NOT USED] 1.11 WARRANTY [NOT USED] PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 8/31/2012 D. Johnson 1.3.B – Added requirement of compliance with Health and Safety Code, Title 9. Safety, Subtitle A. Public Safety, Chapter 752. High Voltage Overhead Lines. 01 35 13 - 6 DAP SPECIAL PROJECT PROCEDURES Page 6 of 7 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised August, 30, 2013 EXHIBIT A (To be printed on Contractor’s Letterhead) Date: CPN No.: Project Name: Mapsco Location: Limits of Construction: THIS IS TO INFORM YOU THAT UNDER A CONTRACT WITH THE CITY OF FORT WORTH, OUR COMPANY WILL WORK ON UTILITY LINES ON OR AROUND YOUR PROPERTY. CONSTRUCTION WILL BEGIN APPROXIMATELY SEVEN DAYS FROM THE DATE OF THIS NOTICE. IF YOU HAVE QUESTIONS ABOUT ACCESS, SECURITY, SAFETY OR ANY OTHER ISSUE, PLEASE CALL: Mr. <CONTRACTOR’S SUPERINTENDENT> AT <TELEPHONE NO.> OR Mr. <CITY INSPECTOR> AT < TELEPHONE NO.> AFTER 4:30 PM OR ON WEEKENDS, PLEASE CALL (817) 392 8306 PLEASE KEEP THIS FLYER HANDY WHEN YOU CALL 01 35 13 - 7 DAP SPECIAL PROJECT PROCEDURES Page 7 of 7 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised August, 30, 2013 EXHIBIT B 01 45 23 DAP TESTING AND INSPECTION SERVICES Page 1 of 2 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Ranch at Duck Creek Phase 2 City Project #103754Revised March 20, 2020 SECTION 01 45 23 TESTING AND INSPECTION SERVICES PART 1 - GENERAL 1.1 SUMMARY A.Section Includes: 1. Testing and inspection services procedures and coordination B.Deviations from this City of Fort Worth Standard Specification 1. None. C.Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A.Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various Items bid. No separate payment will be allowed for this Item. a.Contractor is responsible for performing, coordinating, and payment of all Quality Control testing. b. City is responsible for performing and payment for first set of Quality Assurance testing. 1) If the first Quality Assurance test performed by the City fails, the Contractor is responsible for payment of subsequent Quality Assurance testing until a passing test occurs. a)Final acceptance will not be issued by City until all required payments for testing by Contractor have been paid in full. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS A.Testing 1. Complete testing in accordance with the Contract Documents. 2. Coordination a.When testing is required to be performed by the City, notify City, sufficiently in advance, when testing is needed. b. When testing is required to be completed by the Contractor, notify City, sufficiently in advance, that testing will be performed. 3. Distribution of Testing Reports a.Electronic Distribution 1) Confirm development of Project directory for electronic submittals to be uploaded to the City’s document management system, or another form of distribution approved by the City. 01 45 23 DAP TESTING AND INSPECTION SERVICES Page 2 of 2 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Ranch at Duck Creek Phase 2 City Project #103754 Revised March 20, 2020 2) Upload test reports to designated project directory and notify appropriate City representatives via email of submittal posting. 3) Hard Copies a)1 copy for all submittals submitted to the Project Representative b. Hard Copy Distribution (if required in lieu of electronic distribution) 1) Tests performed by City a)Distribute 1 hard copy to the Contractor 2) Tests performed by the Contractor a)Distribute 3 hard copies to City’s Project Representative 4.Provide City’s Project Representative with trip tickets for each delivered load of Concrete or Lime material including the following information: a.Name of pit b. Date of delivery c.Material delivered B.Inspection 1. Inspection or lack of inspection does not relieve the Contractor from obligation to perform work in accordance with the Contract Documents. 1.5 SUBMITTALS [NOT USED] 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE [NOT USED] 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 03/20/2020 D.V. Magaña Removed reference to Buzzsaw and noted that electronic submittals be uploaded through the City’s document management system. 01 50 00 - 1 DAP TEMPORARY FACILITIES AND CONTROLS Page 1 of 4 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised JULY 1, 2011 SECTION 01 50 00 TEMPORARY FACILITIES AND CONTROLS PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Provide temporary facilities and controls needed for the Work including, but not necessarily limited to: a. Temporary utilities b. Sanitary facilities c. Storage Sheds and Buildings d. Dust control e. Temporary fencing of the construction site B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various Items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS A. Temporary Utilities 1. Obtaining Temporary Service a. Make arrangements with utility service companies for temporary services. b. Abide by rules and regulations of utility service companies or authorities having jurisdiction. c. Be responsible for utility service costs until Work is approved for Final Acceptance. 1) Included are fuel, power, light, heat and other utility services necessary for execution, completion, testing and initial operation of Work. 2. Water a. Contractor to provide water required for and in connection with Work to be performed and for specified tests of piping, equipment, devices or other use as required for the completion of the Work. b. Provide and maintain adequate supply of potable water for domestic consumption by Contractor personnel and City’s Project Representatives. c. Coordination 1) Contact City 1 week before water for construction is desired 01 50 00 - 2 DAP TEMPORARY FACILITIES AND CONTROLS Page 2 of 4 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised JULY 1, 2011 d. Contractor Payment for Construction Water 1) Obtain construction water meter from City for payment as billed by City’s established rates. 3. Electricity and Lighting a. Provide and pay for electric powered service as required for Work, including testing of Work. 1) Provide power for lighting, operation of equipment, or other use. b. Electric power service includes temporary power service or generator to maintain operations during scheduled shutdown. 4. Telephone a. Provide emergency telephone service at Site for use by Contractor personnel and others performing work or furnishing services at Site. 5. Temporary Heat and Ventilation a. Provide temporary heat as necessary for protection or completion of Work. b. Provide temporary heat and ventilation to assure safe working conditions. B. Sanitary Facilities 1. Provide and maintain sanitary facilities for persons on Site. a. Comply with regulations of State and local departments of health. 2. Enforce use of sanitary facilities by construction personnel at job site. a. Enclose and anchor sanitary facilities. b. No discharge will be allowed from these facilities. c. Collect and store sewage and waste so as not to cause nuisance or health problem. d. Haul sewage and waste off-site at no less than weekly intervals and properly dispose in accordance with applicable regulation. 3. Locate facilities near Work Site and keep clean and maintained throughout Project. 4. Remove facilities at completion of Project C. Storage Sheds and Buildings 1. Provide adequately ventilated, watertight, weatherproof storage facilities with floor above ground level for materials and equipment susceptible to weather damage. 2. Storage of materials not susceptible to weather damage may be on blocks off ground. 3. Store materials in a neat and orderly manner. a. Place materials and equipment to permit easy access for identification, inspection and inventory. 4. Equip building with lockable doors and lighting, and provide electrical service for equipment space heaters and heating or ventilation as necessary to provide storage environments acceptable to specified manufacturers. 5. Fill and grade site for temporary structures to provide drainage away from temporary and existing buildings. 6. Remove building from site prior to Final Acceptance. D. Temporary Fencing 1. Provide and maintain for the duration or construction when required in contract documents E. Dust Control 01 50 00 - 3 DAP TEMPORARY FACILITIES AND CONTROLS Page 3 of 4 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised JULY 1, 2011 1. Contractor is responsible for maintaining dust control through the duration of the project. a. Contractor remains on-call at all times b. Must respond in a timely manner F. Temporary Protection of Construction 1. Contractor or subcontractors are responsible for protecting Work from damage due to weather. 1.5 SUBMITTALS [NOT USED] 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE [NOT USED] 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION [NOT USED] 3.1 INSTALLERS [NOT USED] 3.2 EXAMINATION [NOT USED] 3.3 PREPARATION [NOT USED] 3.4 INSTALLATION A. Temporary Facilities 1. Maintain all temporary facilities for duration of construction activities as needed. 3.5 [REPAIR] / [RESTORATION] 3.6 RE-INSTALLATION 3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED] 3.8 SYSTEM STARTUP [NOT USED] 3.9 ADJUSTING [NOT USED] 3.10 CLEANING [NOT USED] 3.11 CLOSEOUT ACTIVITIES A. Temporary Facilities 01 50 00 - 4 DAP TEMPORARY FACILITIES AND CONTROLS Page 4 of 4 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised JULY 1, 2011 1. Remove all temporary facilities and restore area after completion of the Work, to a condition equal to or better than prior to start of Work. 3.12 PROTECTION [NOT USED] 3.13 MAINTENANCE [NOT USED] 3.14 ATTACHMENTS [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 01 55 26 - 1 DAP STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL Page 1 of 3 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised July 1, 2011 SECTION 01 55 26 STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Administrative procedures for: a. Street Use Permit b. Modification of approved traffic control c. Removal of Street Signs B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 3. Section 34 71 13 – Traffic Control 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various Items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES A. Reference Standards 1. Reference standards cited in this specification refer to the current reference standard published at the time of the latest revision date logged at the end of this specification, unless a date is specifically cited. 2. Texas Manual on Uniform Traffic Control Devices (TMUTCD). 1.4 ADMINISTRATIVE REQUIREMENTS A. Traffic Control 1. General a. When traffic control plans are included in the Drawings, provide Traffic Control in accordance with Drawings and Section 34 71 13. b. When traffic control plans are not included in the Drawings, prepare traffic control plans in accordance with Section 34 71 13 and submit to City for review. 1) Allow minimum 10 working days for review of proposed Traffic Control. B. Street Use Permit 1. Prior to installation of Traffic Control, a City Street Use Permit is required. a. To obtain Street Use Permit, submit Traffic Control Plans to City Transportation and Public Works Department. 01 55 26 - 2 DAP STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL Page 2 of 3 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised July 1, 2011 1) Allow a minimum of 5 working days for permit review. 2) Contractor’s responsibility to coordinate review of Traffic Control plans for Street Use Permit, such that construction is not delayed. C. Modification to Approved Traffic Control 1. Prior to installation traffic control: a. Submit revised traffic control plans to City Department Transportation and Public Works Department. 1) Revise Traffic Control plans in accordance with Section 34 71 13. 2) Allow minimum 5 working days for review of revised Traffic Control. 3) It is the Contractor’s responsibility to coordinate review of Traffic Control plans for Street Use Permit, such that construction is not delayed. D. Removal of Street Sign 1. If it is determined that a street sign must be removed for construction, then contact City Transportation and Public Works Department, Signs and Markings Division to remove the sign. E. Temporary Signage 1. In the case of regulatory signs, replace permanent sign with temporary sign meeting requirements of the latest edition of the Texas Manual on Uniform Traffic Control Devices (MUTCD). 2. Install temporary sign before the removal of permanent sign. 3. When construction is complete, to the extent that the permanent sign can be reinstalled, contact the City Transportation and Public Works Department, Signs and Markings Division, to reinstall the permanent sign. F. Traffic Control Standards 1. Traffic Control Standards can be found on the City’s Buzzsaw website. 1.5 SUBMITTALS [NOT USED] 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE [NOT USED] 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION [NOT USED] END OF SECTION 01 55 26 - 3 DAP STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL Page 3 of 3 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised July 1, 2011 Revision Log DATE NAME SUMMARY OF CHANGE 01 57 13 - 1 DAP STORM WATER POLLUTION PREVENTION Page 1 of 3 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised July 1, 2011 SECTION 01 57 13 STORM WATER POLLUTION PREVENTION PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Procedures for Storm Water Pollution Prevention Plans B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 3. Section 31 25 00 – Erosion and Sediment Control 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Construction Activities resulting in less than 1 acre of disturbance a. Work associated with this Item is considered subsidiary to the various Items bid. No separate payment will be allowed for this Item. 2. Construction Activities resulting in greater than 1 acre of disturbance a. Measurement and Payment shall be in accordance with Section 31 25 00. 1.3 REFERENCES A. Abbreviations and Acronyms 1. Notice of Intent: NOI 2. Notice of Termination: NOT 3. Storm Water Pollution Prevention Plan: SWPPP 4. Texas Commission on Environmental Quality: TCEQ 5. Notice of Change: NOC A. Reference Standards 1. Reference standards cited in this Specification refer to the current reference standard published at the time of the latest revision date logged at the end of this Specification, unless a date is specifically cited. 2. Integrated Storm Management (iSWM) Technical Manual for Construction Controls 1.4 ADMINISTRATIVE REQUIREMENTS A. General 1. Contractor is responsible for resolution and payment of any fines issued associated with compliance to Stormwater Pollution Prevention Plan. 01 57 13 - 2 DAP STORM WATER POLLUTION PREVENTION Page 2 of 3 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised July 1, 2011 B. Construction Activities resulting in: 1. Less than 1 acre of disturbance a. Provide erosion and sediment control in accordance with Section 31 25 00 and Drawings. 2. 1 to less than 5 acres of disturbance a. Texas Pollutant Discharge Elimination System (TPDES) General Construction Permit is required b. Complete SWPPP in accordance with TCEQ requirements 1) TCEQ Small Construction Site Notice Required under general permit TXR150000 a) Sign and post at job site b) Prior to Preconstruction Meeting, send 1 copy to City Department of Transportation and Public Works, Environmental Division, (817) 392- 6088. 2) Provide erosion and sediment control in accordance with: a) Section 31 25 00 b) The Drawings c) TXR150000 General Permit d) SWPPP e) TCEQ requirements 3. 5 acres or more of Disturbance a. Texas Pollutant Discharge Elimination System (TPDES) General Construction Permit is required b. Complete SWPPP in accordance with TCEQ requirements 1) Prepare a TCEQ NOI form and submit to TCEQ along with required fee a) Sign and post at job site b) Send copy to City Department of Transportation and Public Works, Environmental Division, (817) 392-6088. 2) TCEQ Notice of Change required if making changes or updates to NOI 3) Provide erosion and sediment control in accordance with: a) Section 31 25 00 b) The Drawings c) TXR150000 General Permit d) SWPPP e) TCEQ requirements 4) Once the project has been completed and all the closeout requirements of TCEQ have been met a TCEQ Notice of Termination can be submitted. a) Send copy to City Department of Transportation and Public Works, Environmental Division, (817) 392-6088. 1.5 SUBMITTALS A. SWPPP 1. Submit in accordance with Section 01 33 00, except as stated herein. a. Prior to the Preconstruction Meeting, submit a draft copy of SWPPP to the City as follows: 1) 1 copy to the City Project Manager a) City Project Manager will forward to the City Department of Transportation and Public Works, Environmental Division for review 01 57 13 - 3 DAP STORM WATER POLLUTION PREVENTION Page 3 of 3 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised July 1, 2011 B. Modified SWPPP 1. If the SWPPP is revised during construction, resubmit modified SWPPP to the City in accordance with Section 01 33 00. 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE [NOT USED] 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 01 60 00 DAP PRODUCT REQUIREMENTS Page 1 of 2 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Ranch at Duck Creek Phase 2 City Project #103754 Revised March 20, 2020 SECTION 01 60 00 PRODUCT REQUIREMENTS PART 1 - GENERAL 1.1 SUMMARY A.Section Includes: 1. References for Product Requirements and City Standard Products List B.Deviations from this City of Fort Worth Standard Specification 1. None. C.Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 1.2 PRICE AND PAYMENT PROCEDURES [NOT USED] 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS A list of City approved products for use is available through the City’s website at: https://apps.fortworthtexas.gov/ProjectResources/ and following the directory path: 02 - Construction Documents\Standard Products List A.Only products specifically included on City’s Standard Product List in these Contract Documents shall be allowed for use on the Project. 1. Any subsequently approved products will only be allowed for use upon specific approval by the City. B.Any specific product requirements in the Contract Documents supersede similar products included on the City’s Standard Product List. 1. The City reserves the right to not allow products to be used for certain projects even though the product is listed on the City’s Standard Product List. C.Although a specific product is included on City’s Standard Product List, not all products from that manufacturer are approved for use, including but not limited to, that manufacturer’s standard product. D.See Section 01 33 00 for submittal requirements of Product Data included on City’s Standard Product List. 1.5 SUBMITTALS [NOT USED] 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE [NOT USED] 01 60 00 DAP PRODUCT REQUIREMENTS Page 2 of 2 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Ranch at Duck Creek Phase 2 City Project #103754 Revised March 20, 2020 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 10/12/12 D. Johnson Modified Location of City’s Standard Product List 4/7/2014 M.Domenech Revised for DAP application 03/20/2020 D.V. Magaña Removed reference to Buzzsaw and noted that the City approved products list is accessible through the City’s website. 01 66 00 - 1 DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS Page 1 of 4 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised April 7, 2014 SECTION 01 66 00 PRODUCT STORAGE AND HANDLING REQUIREMENTS PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Scheduling of product delivery 2. Packaging of products for delivery 3. Protection of products against damage from: a. Handling b. Exposure to elements or harsh environments B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various Items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 1.5 SUBMITTALS [NOT USED] 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE [NOT USED] 1.10 DELIVERY AND HANDLING A. Delivery Requirements 1. Schedule delivery of products or equipment as required to allow timely installation and to avoid prolonged storage. 2. Provide appropriate personnel and equipment to receive deliveries. 3. Delivery trucks will not be permitted to wait extended periods of time on the Site for personnel or equipment to receive the delivery. 01 66 00 - 2 DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS Page 2 of 4 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised April 7, 2014 4. Deliver products or equipment in manufacturer's original unbroken cartons or other containers designed and constructed to protect the contents from physical or environmental damage. 5. Clearly and fully mark and identify as to manufacturer, item and installation location. 6. Provide manufacturer's instructions for storage and handling. B. Handling Requirements 1. Handle products or equipment in accordance with these Contract Documents and manufacturer’s recommendations and instructions. C. Storage Requirements 1. Store materials in accordance with manufacturer’s recommendations and requirements of these Specifications. 2. Make necessary provisions for safe storage of materials and equipment. a. Place loose soil materials and materials to be incorporated into Work to prevent damage to any part of Work or existing facilities and to maintain free access at all times to all parts of Work and to utility service company installations in vicinity of Work. 3. Keep materials and equipment neatly and compactly stored in locations that will cause minimum inconvenience to other contractors, public travel, adjoining owners, tenants and occupants. a. Arrange storage to provide easy access for inspection. 4. Restrict storage to areas available on construction site for storage of material and equipment as shown on Drawings, or approved by City’s Project Representative. 5. Provide off-site storage and protection when on-site storage is not adequate. a. Provide addresses of and access to off-site storage locations for inspection by City’s Project Representative. 6. Do not use lawns, grass plots or other private property for storage purposes without written permission of owner or other person in possession or control of premises. 7. Store in manufacturers’ unopened containers. 8. Neatly, safely and compactly stack materials delivered and stored along line of Work to avoid inconvenience and damage to property owners and general public and maintain at least 3 feet from fire hydrant. 9. Keep public and private driveways and street crossings open. 10. Repair or replace damaged lawns, sidewalks, streets or other improvements to satisfaction of City’s Project Representative. a. Total length which materials may be distributed along route of construction at one time is 1,000 linear feet, unless otherwise approved in writing by City’s Project Representative. 01 66 00 - 3 DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS Page 3 of 4 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised April 7, 2014 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION 3.1 INSTALLERS [NOT USED] 3.2 EXAMINATION [NOT USED] 3.3 PREPARATION [NOT USED] 3.4 ERECTION [NOT USED] 3.5 REPAIR / RESTORATION [NOT USED] 3.6 RE-INSTALLATION [NOT USED] 3.7 FIELD [OR] SITE QUALITY CONTROL A. Tests and Inspections 1. Inspect all products or equipment delivered to the site prior to unloading. B. Non-Conforming Work 1. Reject all products or equipment that are damaged, used or in any other way unsatisfactory for use on the project. 3.8 SYSTEM STARTUP [NOT USED] 3.9 ADJUSTING [NOT USED] 3.10 CLEANING [NOT USED] 3.11 CLOSEOUT ACTIVITIES [NOT USED] 3.12 PROTECTION A. Protect all products or equipment in accordance with manufacturer's written directions. B. Store products or equipment in location to avoid physical damage to items while in storage. C. Protect equipment from exposure to elements and keep thoroughly dry if required by the manufacturer. 3.13 MAINTENANCE [NOT USED] 3.14 ATTACHMENTS [NOT USED] END OF SECTION 01 66 00 - 4 DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS Page 4 of 4 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised April 7, 2014 Revision Log DATE NAME SUMMARY OF CHANGE 4/7/2014 M.Domenech Revised for DAP application 01 70 00 - 1 DAP MOBILIZATION AND REMOBILIZATION Page 1 of 4 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised April 7, 2014 SECTION 01 70 00 MOBILIZATION AND REMOBILIZATION PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Mobilization and Demobilization a. Mobilization 1) Transportation of Contractor’s personnel, equipment, and operating supplies to the Site 2) Establishment of necessary general facilities for the Contractor’s operation at the Site 3) Premiums paid for performance and payment bonds 4) Transportation of Contractor’s personnel, equipment, and operating supplies to another location within the designated Site 5) Relocation of necessary general facilities for the Contractor’s operation from 1 location to another location on the Site. b. Demobilization 1) Transportation of Contractor’s personnel, equipment, and operating supplies away from the Site including disassembly 2) Site Clean-up 3) Removal of all buildings and/or other facilities assembled at the Site for this Contract c. Mobilization and Demobilization do not include activities for specific items of work that are for which payment is provided elsewhere in the contract. 2. Remobilization a. Remobilization for Suspension of Work specifically required in the Contract Documents or as required by City includes: 1) Demobilization a) Transportation of Contractor’s personnel, equipment, and operating supplies from the Site including disassembly or temporarily securing equipment, supplies, and other facilities as designated by the Contract Documents necessary to suspend the Work. b) Site Clean-up as designated in the Contract Documents 2) Remobilization a) Transportation of Contractor’s personnel, equipment, and operating supplies to the Site necessary to resume the Work. b) Establishment of necessary general facilities for the Contractor’s operation at the Site necessary to resume the Work. 3) No Payments will be made for: a) Mobilization and Demobilization from one location to another on the Site in the normal progress of performing the Work. b) Stand-by or idle time c) Lost profits 3. Mobilizations and Demobilization for Miscellaneous Projects a. Mobilization and Demobilization 01 70 00 - 2 DAP MOBILIZATION AND REMOBILIZATION Page 2 of 4 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised April 7, 2014 1) Mobilization shall consist of the activities and cost on a Work Order basis necessary for: a) Transportation of Contractor’s personnel, equipment, and operating supplies to the Site for the issued Work Order. b) Establishment of necessary general facilities for the Contractor’s operation at the Site for the issued Work Order 2) Demobilization shall consist of the activities and cost necessary for: a) Transportation of Contractor’s personnel, equipment, and operating supplies from the Site including disassembly for each issued Work Order b) Site Clean-up for each issued Work Order c) Removal of all buildings or other facilities assembled at the Site for each Work Oder b. Mobilization and Demobilization do not include activities for specific items of work for which payment is provided elsewhere in the contract. 4. Emergency Mobilizations and Demobilization for Miscellaneous Projects a. A Mobilization for Miscellaneous Projects when directed by the City and the mobilization occurs within 24 hours of the issuance of the Work Order. B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Mobilization and Demobilization a. Measure 1) This Item is considered subsidiary to the various Items bid. b. Payment 1) The work performed and materials furnished in accordance with this Item are subsidiary to the various Items bid and no other compensation will be allowed. 2. Remobilization for suspension of Work as specifically required in the Contract Documents a. Measurement 1) Measurement for this Item shall be per each remobilization performed. b. Payment 1) The work performed and materials furnished in accordance with this Item and measured as provided under “Measurement” will be paid for at the unit price per each “Specified Remobilization” in accordance with Contract Documents. c. The price shall include: 1) Demobilization as described in Section 1.1.A.2.a.1) 2) Remobilization as described in Section 1.1.A.2.a.2) d. No payments will be made for standby, idle time, or lost profits associated this Item. 01 70 00 - 3 DAP MOBILIZATION AND REMOBILIZATION Page 3 of 4 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised April 7, 2014 3. Remobilization for suspension of Work as required by City a. Measurement and Payment 1) This shall be submitted as a Contract Claim in accordance with Article 10 of Section 00 72 00. 2) No payments will be made for standby, idle time, or lost profits associated with this Item. 4. Mobilizations and Demobilizations for Miscellaneous Projects a. Measurement 1) Measurement for this Item shall be for each Mobilization and Demobilization required by the Contract Documents b. Payment 1) The Work performed and materials furnished in accordance with this Item and measured as provided under “Measurement” will be paid for at the unit price per each “Work Order Mobilization” in accordance with Contract Documents. Demobilization shall be considered subsidiary to mobilization and shall not be paid for separately. c. The price shall include: 1) Mobilization as described in Section 1.1.A.3.a.1) 2) Demobilization as described in Section 1.1.A.3.a.2) d. No payments will be made for standby, idle time, or lost profits associated this Item. 5. Emergency Mobilizations and Demobilizations for Miscellaneous Projects a. Measurement 1) Measurement for this Item shall be for each Mobilization and Demobilization required by the Contract Documents b. Payment 1) The Work performed and materials furnished in accordance with this Item and measured as provided under “Measurement” will be paid for at the unit price per each “Work Order Emergency Mobilization” in accordance with Contract Documents. Demobilization shall be considered subsidiary to mobilization and shall not be paid for separately. c. The price shall include 1) Mobilization as described in Section 1.1.A.4.a) 2) Demobilization as described in Section 1.1.A.3.a.2) d. No payments will be made for standby, idle time, or lost profits associated this Item. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 1.5 SUBMITTALS [NOT USED] 1.6 INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE [NOT USED] 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 01 70 00 - 4 DAP MOBILIZATION AND REMOBILIZATION Page 4 of 4 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised April 7, 2014 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 4/7/2014 M.Domenech Revised for DAP application 01 71 23 - 1 CONSTRUCTION STAKING AND SURVEY Page 1 of 8 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised February 14, 2018 SECTION 01 71 23 CONSTRUCTION STAKING AND SURVEY PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Requirements for construction staking and construction survey B. Deviations from this City of Fort Worth Standard Specification 1. See Changes (Highlighted in Yellow). C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Construction Staking a. Measurement 1) This Item is considered subsidiary to the various Items bid. b. Payment 1) The work performed and the materials furnished in accordance with this Item are subsidiary to the various Items bid and no other compensation will be allowed. 2. Construction Survey a. Measurement 1) This Item is considered subsidiary to the various Items bid. b. Payment 1) The work performed and the materials furnished in accordance with this Item are subsidiary to the various Items bid and no other compensation will be allowed. 3. As-Built Survey a. Measurement 1) This Item is considered subsidiary to the various Items bid. b. Payment 1) The work performed and the materials furnished in accordance with this Item are subsidiary to the various Items bid and no other compensation will be allowed. 01 71 23 - 2 CONSTRUCTION STAKING AND SURVEY Page 2 of 8 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised February 14, 2018 1.3 REFERENCES A. Definitions 1. Construction Survey - The survey measurements made prior to or while construction is in progress to control elevation, horizontal position, dimensions and configuration of structures/improvements included in the Project Drawings. 2. As-built Survey –The measurements made after the construction of the improvement features are complete to provide position coordinates for the features of a project. 3. Construction Staking – The placement of stakes and markings to provide offsets and elevations to cut and fill in order to locate on the ground the designed structures/improvements included in the Project Drawings. Construction staking shall include staking easements and/or right of way if indicated on the plans. 4. Survey “Field Checks” – Measurements made after construction staking is completed and before construction work begins to ensure that structures marked on the ground are accurately located per Project Drawings. B. Technical References 1. City of Fort Worth – Construction Staking Standards (available on City’s Buzzsaw website) – 01 71 23.16.01_ Attachment A_Survey Staking Standards 2. City of Fort Worth - Standard Survey Data Collector Library (fxl) files (available on City’s Buzzsaw website). 3. Texas Department of Transportation (TxDOT) Survey Manual, latest revision 4. Texas Society of Professional Land Surveyors (TSPS), Manual of Practice for Land Surveying in the State of Texas, Category 5 1.4 ADMINISTRATIVE REQUIREMENTS A. The Contractor’s selection of a surveyor must comply with Texas Government Code 2254 (qualifications based selection) for this project. 1.5 SUBMITTALS A. Submittals, if required, shall be in accordance with Section 01 33 00. B. All submittals shall be received and reviewed by the City prior to delivery of work. 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS A. Field Quality Control Submittals 1. Documentation verifying accuracy of field engineering work, including coordinate conversions if plans do not indicate grid or ground coordinates. 2. Submit “Cut-Sheets” conforming to the standard template provided by the City (refer to 01 71 23.16.01 – Attachment A – Survey Staking Standards). 1.7 CLOSEOUT SUBMITTALS B. As-built Redline Drawing Submittal 01 71 23 - 3 CONSTRUCTION STAKING AND SURVEY Page 3 of 8 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised February 14, 2018 1. Submit As-Built Survey Redline Drawings documenting the locations/elevations of constructed improvements signed and sealed by Registered Professional Land Surveyor (RPLS) responsible for the work (refer to 01 71 23.16.01 – Attachment A – Survey Staking Standards) . 2. Contractor shall submit the proposed as-built and completed redline drawing submittal one (1) week prior to scheduling the project final inspection for City review and comment. Revisions, if necessary, shall be made to the as-built redline drawings and resubmitted to the City prior to scheduling the construction final inspection. 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE A. Construction Staking 1. Construction staking will be performed by the Contractor. 2. Coordination a. Contact City and Developer’s Project Representative at least one week in advance notifying the City of when Construction Staking is scheduled. b. It is the Contractor’s responsibility to coordinate staking such that construction activities are not delayed or negatively impacted. 3. General a. Contractor is responsible for preserving and maintaining stakes. If City surveyors or Developer’s Project Representative are required to re-stake for any reason, the Contractor will be responsible for costs to perform staking. If in the opinion of the City, a sufficient number of stakes or markings have been lost, destroyed disturbed or omitted that the contracted Work cannot take place then the Contractor will be required to stake or re-stake the deficient areas. B. Construction Survey 1. Construction Survey will be performed by the Contractor. 2. Coordination a. Contractor to verify that horizontal and vertical control data established in the design survey and required for construction survey is available and in place. 3. General a. Construction survey will be performed in order to construct the work shown on the Construction Drawings and specified in the Contract Documents. b. For construction methods other than open cut, the Contractor shall perform construction survey and verify control data including, but not limited to, the following: 1) Verification that established benchmarks and control are accurate. 2) Use of Benchmarks to furnish and maintain all reference lines and grades for tunneling. 3) Use of line and grades to establish the location of the pipe. 4) Submit to the City copies of field notes used to establish all lines and grades, if requested, and allow the City to check guidance system setup prior to beginning each tunneling drive. 5) Provide access for the City, if requested, to verify the guidance system and the line and grade of the carrier pipe. 01 71 23 - 4 CONSTRUCTION STAKING AND SURVEY Page 4 of 8 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised February 14, 2018 6) The Contractor remains fully responsible for the accuracy of the work and correction of it, as required. 7) Monitor line and grade continuously during construction. 8) Record deviation with respect to design line and grade once at each pipe joint and submit daily records to the City. 9) If the installation does not meet the specified tolerances (as outlined in Sections 33 05 23 and/or 33 05 24), immediately notify the City and correct the installation in accordance with the Contract Documents. C. As-Built Survey 1. Required As-Built Survey will be performed by the Contractor. 2. Coordination a. Contractor is to coordinate with City to confirm which features require as- built surveying. b. It is the Contractor’s responsibility to coordinate the as-built survey and required measurements for items that are to be buried such that construction activities are not delayed or negatively impacted. c. For sewer mains and water mains 12” and under in diameter, it is acceptable to physically measure depth and mark the location during the progress of construction and take as-built survey after the facility has been buried. The Contractor is responsible for the quality control needed to ensure accuracy. 3. General a. The Contractor shall provide as-built survey including the elevation and location (and provide written documentation to the City) of construction features during the progress of the construction including the following: 1) Water Lines a) Top of pipe elevations and coordinates for waterlines at the following locations: (1) Minimum every 250 linear feet, including (2) Horizontal and vertical points of inflection, curvature, etc. (3) Fire line tee (4) Plugs, stub-outs, dead-end lines (5) Casing pipe (each end) and all buried fittings 2) Sanitary Sewer a) Top of pipe elevations and coordinates for force mains and siphon sanitary sewer lines (non-gravity facilities) at the following locations: (1) Minimum every 250 linear feet and any buried fittings (2) Horizontal and vertical points of inflection, curvature, etc. 3) Stormwater – Not Applicable b. The Contractor shall provide as-built survey including the elevation and location (and provide written documentation to the City) of construction features after the construction is completed including the following: 1) Manholes a) Rim and flowline elevations and coordinates for each manhole 2) Water Lines a) Cathodic protection test stations b) Sampling stations c) Meter boxes/vaults (All sizes) 01 71 23 - 5 CONSTRUCTION STAKING AND SURVEY Page 5 of 8 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised February 14, 2018 d) Fire hydrants e) Valves (gate, butterfly, etc.) f) Air Release valves (Manhole rim and vent pipe) g) Blow off valves (Manhole rim and valve lid) h) Pressure plane valves i) Underground Vaults (1) Rim and flowline elevations and coordinates for each Underground Vault. 3) Sanitary Sewer a) Cleanouts (1) Rim and flowline elevations and coordinates for each b) Manholes and Junction Structures (1) Rim and flowline elevations and coordinates for each manhole and junction structure. 4) Stormwater – Not Applicable 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY PART 2 - PRODUCTS A. A construction survey will produce, but will not be limited to: 1. Recovery of relevant control points, points of curvature and points of intersection. 2. Establish temporary horizontal and vertical control elevations (benchmarks) sufficiently permanent and located in a manner to be used throughout construction. 3. The location of planned facilities, easements and improvements. a. Establishing final line and grade stakes for piers, floors, grade beams, parking areas, utilities, streets, highways, tunnels, and other construction. b. A record of revisions or corrections noted in an orderly manner for reference. c. A drawing, when required by the client, indicating the horizontal and vertical location of facilities, easements and improvements, as built. 4. Cut sheets shall be provided to the City inspector and Survey Superintendent for all construction staking projects. These cut sheets shall be on the standard city template which can be obtained from the Survey Superintendent (817-392-7925). 5. Digital survey files in the following formats shall be acceptable: a. AutoCAD (.dwg) b. ESRI Shapefile (.shp) c. CSV file (.csv), formatted with X and Y coordinates in separate columns (use standard templates, if available) 6. Survey files shall include vertical and horizontal data tied to original project control and benchmarks, and shall include feature descriptions PART 3 - EXECUTION 3.1 INSTALLERS 01 71 23 - 6 CONSTRUCTION STAKING AND SURVEY Page 6 of 8 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised February 14, 2018 A. Tolerances: 1. The staked location of any improvement or facility should be as accurate as practical and necessary. The degree of precision required is dependent on many factors all of which must remain judgmental. The tolerances listed hereafter are based on generalities and, under certain circumstances, shall yield to specific requirements. The surveyor shall assess any situation by review of the overall plans and through consultation with responsible parties as to the need for specific tolerances. a. Earthwork: Grades for earthwork or rough cut should not exceed 0.1 ft. vertical tolerance. Horizontal alignment for earthwork and rough cut should not exceed 1.0 ft. tolerance. b. Horizontal alignment on a structure shall be within .0.1ft tolerance. c. Paving or concrete for streets, curbs, gutters, parking areas, drives, alleys and walkways shall be located within the confines of the site boundaries and, occasionally, along a boundary or any other restrictive line. Away from any restrictive line, these facilities should be staked with an accuracy producing no more than 0.05ft. tolerance from their specified locations. d. Underground and overhead utilities, such as sewers, gas, water, telephone and electric lines, shall be located horizontally within their prescribed areas or easements. Within assigned areas, these utilities should be staked with an accuracy producing no more than 0.1 ft tolerance from a specified location. e. The accuracy required for the vertical location of utilities varies widely. Many underground utilities require only a minimum cover and a tolerance of 0.1 ft. should be maintained. Underground and overhead utilities on planned profile, but not depending on gravity flow for performance, should not exceed 0.1 ft. tolerance. B. Surveying instruments shall be kept in close adjustment according to manufacturer’s specifications or in compliance to standards. The City reserves the right to request a calibration report at any time and recommends regular maintenance schedule be performed by a certified technician every 6 months. 1. Field measurements of angles and distances shall be done in such fashion as to satisfy the closures and tolerances expressed in Part 3.1.A. 2. Vertical locations shall be established from a pre-established benchmark and checked by closing to a different bench mark on the same datum. 3. Construction survey field work shall correspond to the client’s plans. Irregularities or conflicts found shall be reported promptly to the City. 4. Revisions, corrections and other pertinent data shall be logged for future reference. 3.2 EXAMINATION [NOT USED] 3.3 PREPARATION [NOT USED] 3.4 APPLICATION 3.5 REPAIR / RESTORATION A. If the Contractor’s work damages or destroys one or more of the control monuments/points set by the City or Developer’s Project Representative, the monuments shall be adequately referenced for expedient restoration. 01 71 23 - 7 CONSTRUCTION STAKING AND SURVEY Page 7 of 8 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised February 14, 2018 1. Notify City or Developer’s Project Representative if any control data needs to be restored or replaced due to damage caused during construction operations. a. Contractor shall perform replacements and/or restorations. b. The City or Developer’s Project Representative may require at any time a survey “Field Check” of any monument or benchmarks that are set be verified by the City surveyors or Developer’s Project Representative before further associated work can move forward. 3.6 RE-INSTALLATION [NOT USED] 3.7 FIELD [OR] SITE QUALITY CONTROL A. It is the Contractor’s responsibility to maintain all stakes and control data placed by the City or Developer’s Project Representative in accordance with this Specification. This includes easements and right of way, if noted on the plans. B. Do not change or relocate stakes or control data without approval from the City. 3.8 SYSTEM STARTUP A. Survey Checks 1. The City reserves the right to perform a Survey Check at any time deemed necessary. 2. Checks by City personnel or 3rd party contracted surveyor are not intended to relieve the contractor of his/her responsibility for accuracy. 3.9 ADJUSTING [NOT USED] 3.10 CLEANING [NOT USED] 3.11 CLOSEOUT ACTIVITIES [NOT USED] 3.12 PROTECTION [NOT USED] 3.13 MAINTENANCE [NOT USED] 3.14 ATTACHMENTS [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 8/31/2012 D. Johnson 8/31/2017 M. Owen Added instruction and modified measurement & payment under 1.2; added definitions and references under 1.3; modified 1.6; added 1.7 closeout submittal requirements; modified 1.9 Quality Assurance; added PART 2 – PRODUCTS ; Added 3.1 Installers; added 3.5 Repair/Restoration; and added 3.8 System Startup. 2/14/2018 M Owen Removed “blue text”; revised measurement and payment sections for Construction Staking and As-Built Survey; added reference to selection compliance with TGC 2254; revised action and Closeout submittal requirements; added acceptable depth 01 71 23 - 8 CONSTRUCTION STAKING AND SURVEY Page 8 of 8 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised February 14, 2018 measurement criteria; revised list of items requiring as-built survey “during” and “after” construction; and revised acceptable digital survey file format 01 74 23 - 1 DAP CLEANING Page 1 of 4 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised April 7, 2014 SECTION 01 74 23 CLEANING PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Intermediate and final cleaning for Work not including special cleaning of closed systems specified elsewhere B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 3. Section 32 92 13 – Hydro-Mulching, Seeding and Sodding 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various Items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS A. Scheduling 1. Schedule cleaning operations so that dust and other contaminants disturbed by cleaning process will not fall on newly painted surfaces. 2. Schedule final cleaning upon completion of Work and immediately prior to final inspection. 1.5 SUBMITTALS [NOT USED] 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE [NOT USED] 1.10 STORAGE, AND HANDLING A. Storage and Handling Requirements 1. Store cleaning products and cleaning wastes in containers specifically designed for those materials. 01 74 23 - 2 DAP CLEANING Page 2 of 4 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised April 7, 2014 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS 2.1 OWNER-FURNISHED [OR] OWNER-SUPPLIEDPRODUCTS [NOT USED] 2.2 MATERIALS A. Cleaning Agents 1. Compatible with surface being cleaned 2. New and uncontaminated 3. For manufactured surfaces a. Material recommended by manufacturer 2.3 ACCESSORIES [NOT USED] 2.4 SOURCE QUALITY CONTROL [NOT USED] PART 3 - EXECUTION 3.1 INSTALLERS [NOT USED] 3.2 EXAMINATION [NOT USED] 3.3 PREPARATION [NOT USED] 3.4 APPLICATION [NOT USED] 3.5 REPAIR / RESTORATION [NOT USED] 3.6 RE-INSTALLATION [NOT USED] 3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED] 3.8 SYSTEM STARTUP [NOT USED] 3.9 ADJUSTING [NOT USED] 3.10 CLEANING A. General 1. Prevent accumulation of wastes that create hazardous conditions. 2. Conduct cleaning and disposal operations to comply with laws and safety orders of governing authorities. 3. Do not dispose of volatile wastes such as mineral spirits, oil or paint thinner in storm or sanitary drains or sewers. 4. Dispose of degradable debris at an approved solid waste disposal site. 5. Dispose of nondegradable debris at an approved solid waste disposal site or in an alternate manner approved by City and regulatory agencies. 01 74 23 - 3 DAP CLEANING Page 3 of 4 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised April 7, 2014 6. Handle materials in a controlled manner with as few handlings as possible. 7. Thoroughly clean, sweep, wash and polish all Work and equipment associated with this project. 8. Remove all signs of temporary construction and activities incidental to construction of required permanent Work. 9. If project is not cleaned to the satisfaction of the City, the City reserves the right to have the cleaning completed at the expense of the Contractor. 10. Do not burn on-site. B. Intermediate Cleaning during Construction 1. Keep Work areas clean so as not to hinder health, safety or convenience of personnel in existing facility operations. 2. At maximum weekly intervals, dispose of waste materials, debris and rubbish. 3. Confine construction debris daily in strategically located container(s): a. Cover to prevent blowing by wind b. Store debris away from construction or operational activities c. Haul from site at a minimum of once per week 4. Vacuum clean interior areas when ready to receive finish painting. a. Continue vacuum cleaning on an as-needed basis, until Final Acceptance. 5. Prior to storm events, thoroughly clean site of all loose or unsecured items, which may become airborne or transported by flowing water during the storm. C. Exterior (Site or Right of Way) Final Cleaning 1. Remove trash and debris containers from site. a. Re-seed areas disturbed by location of trash and debris containers in accordance with Section 32 92 13. 2. Sweep roadway to remove all rocks, pieces of asphalt, concrete or any other object that may hinder or disrupt the flow of traffic along the roadway. 3. Clean any interior areas including, but not limited to, vaults, manholes, structures, junction boxes and inlets. 4. If no longer required for maintenance of erosion facilities, and upon approval by City, remove erosion control from site. 5. Clean signs, lights, signals, etc. 3.11 CLOSEOUT ACTIVITIES [NOT USED] 3.12 PROTECTION [NOT USED] 3.13 MAINTENANCE [NOT USED] 3.14 ATTACHMENTS [NOT USED] 01 74 23 - 4 DAP CLEANING Page 4 of 4 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised April 7, 2014 END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 4/7/2014 M.Domenech Revised for DAP application 01 77 19 - 1 DAP CLOSEOUT REQUIREMENTS Page 1 of 3 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised April 7, 2014 SECTION 01 77 19 CLOSEOUT REQUIREMENTS PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. The procedure for closing out a contract B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various Items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS A. Guarantees, Bonds and Affidavits 1. No application for final payment will be accepted until all guarantees, bonds, certificates, licenses and affidavits required for Work or equipment as specified are satisfactorily filed with the City. B. Release of Liens or Claims 1. No application for final payment will be accepted until satisfactory evidence of release of liens has been submitted to the City. 1.5 SUBMITTALS A. Submit all required documentation to City’s Project Representative. 01 77 19 - 2 DAP CLOSEOUT REQUIREMENTS Page 2 of 3 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised April 7, 2014 1.6 INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION 3.1 INSTALLERS [NOT USED] 3.2 EXAMINATION [NOT USED] 3.3 PREPARATION [NOT USED] 3.4 CLOSEOUT PROCEDURE A. Prior to requesting Final Inspection, submit: 1. Project Record Documents in accordance with Section 01 78 39 2. Operation and Maintenance Data, if required, in accordance with Section 01 78 23 B. Prior to requesting Final Inspection, perform final cleaning in accordance with Section 01 74 23. C. Final Inspection 1. After final cleaning, provide notice to the City Project Representative that the Work is completed. a. The City will make an initial Final Inspection with the Contractor present. b. Upon completion of this inspection, the City will notify the Contractor, in writing within 10 business days, of any particulars in which this inspection reveals that the Work is defective or incomplete. 2. Upon receiving written notice from the City, immediately undertake the Work required to remedy deficiencies and complete the Work to the satisfaction of the City. 3. Upon completion of Work associated with the items listed in the City's written notice, inform the City, that the required Work has been completed. Upon receipt of this notice, the City, in the presence of the Contractor, will make a subsequent Final Inspection of the project. 4. Provide all special accessories required to place each item of equipment in full operation. These special accessory items include, but are not limited to: a. Specified spare parts b. Adequate oil and grease as required for the first lubrication of the equipment c. Initial fill up of all chemical tanks and fuel tanks d. Light bulbs e. Fuses f. Vault keys g. Handwheels h. Other expendable items as required for initial start-up and operation of all equipment D. Notice of Project Completion 01 77 19 - 3 DAP CLOSEOUT REQUIREMENTS Page 3 of 3 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised April 7, 2014 1. Once the City Project Representative finds the Work subsequent to Final Inspection to be satisfactory, the City will issue a Notice of Project Completion (Green Sheet). E. Supporting Documentation 1. Coordinate with the City Project Representative to complete the following additional forms: a. Final Payment Request b. Statement of Contract Time c. Affidavit of Payment and Release of Liens d. Consent of Surety to Final Payment e. Pipe Report (if required) f. Contractor’s Evaluation of City g. Performance Evaluation of Contractor F. Letter of Final Acceptance 1. Upon review and acceptance of Notice of Project Completion and Supporting Documentation, in accordance with General Conditions, City will issue Letter of Final Acceptance and release the Final Payment Request for payment. 3.5 REPAIR / RESTORATION [NOT USED] 3.6 RE-INSTALLATION [NOT USED] 3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED] 3.8 SYSTEM STARTUP [NOT USED] 3.9 ADJUSTING [NOT USED] 3.10 CLEANING [NOT USED] 3.11 CLOSEOUT ACTIVITIES [NOT USED] 3.12 PROTECTION [NOT USED] 3.13 MAINTENANCE [NOT USED] 3.14 ATTACHMENTS [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 4/7/2014 M.Domenech Revised for DAP application 01 78 23 - 1 DAP OPERATION AND MAINTENANCE DATA Page 1 of 5 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised April 7, 2014 SECTION 01 78 23 OPERATION AND MAINTENANCE DATA PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Product data and related information appropriate for City's maintenance and operation of products furnished under Contract 2. Such products may include, but are not limited to: a. Traffic Controllers b. Irrigation Controllers (to be operated by the City) c. Butterfly Valves B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various Items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS A. Schedule 1. Submit manuals in final form to the City within 30 calendar days of product shipment to the project site. 1.5 SUBMITTALS A. Submittals shall be in accordance with Section 01 33 00. All submittals shall be approved by the City prior to delivery. 1.6 INFORMATIONAL SUBMITTALS A. Submittal Form 1. Prepare data in form of an instructional manual for use by City personnel. 2. Format a. Size: 8 ½ inches x 11 inches b. Paper 1) 40 pound minimum, white, for typed pages 2) Holes reinforced with plastic, cloth or metal c. Text: Manufacturer’s printed data, or neatly typewritten 01 78 23 - 2 DAP OPERATION AND MAINTENANCE DATA Page 2 of 5 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised April 7, 2014 d. Drawings 1) Provide reinforced punched binder tab, bind in with text 2) Reduce larger drawings and fold to size of text pages. e. Provide fly-leaf for each separate product, or each piece of operating equipment. 1) Provide typed description of product, and major component parts of equipment. 2) Provide indexed tabs. f. Cover 1) Identify each volume with typed or printed title "OPERATING AND MAINTENANCE INSTRUCTIONS". 2) List: a) Title of Project b) Identity of separate structure as applicable c) Identity of general subject matter covered in the manual 3. Binders a. Commercial quality 3-ring binders with durable and cleanable plastic covers b. When multiple binders are used, correlate the data into related consistent groupings. 4. If available, provide an electronic form of the O&M Manual. B. Manual Content 1. Neatly typewritten table of contents for each volume, arranged in systematic order a. Contractor, name of responsible principal, address and telephone number b. A list of each product required to be included, indexed to content of the volume c. List, with each product: 1) The name, address and telephone number of the subcontractor or installer 2) A list of each product required to be included, indexed to content of the volume 3) Identify area of responsibility of each 4) Local source of supply for parts and replacement d. Identify each product by product name and other identifying symbols as set forth in Contract Documents. 2. Product Data a. Include only those sheets which are pertinent to the specific product. b. Annotate each sheet to: 1) Clearly identify specific product or part installed 2) Clearly identify data applicable to installation 3) Delete references to inapplicable information 3. Drawings a. Supplement product data with drawings as necessary to clearly illustrate: 1) Relations of component parts of equipment and systems 2) Control and flow diagrams b. Coordinate drawings with information in Project Record Documents to assure correct illustration of completed installation. c. Do not use Project Record Drawings as maintenance drawings. 4. Written text, as required to supplement product data for the particular installation: a. Organize in consistent format under separate headings for different procedures. b. Provide logical sequence of instructions of each procedure. 01 78 23 - 3 DAP OPERATION AND MAINTENANCE DATA Page 3 of 5 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised April 7, 2014 5. Copy of each warranty, bond and service contract issued a. Provide information sheet for City personnel giving: 1) Proper procedures in event of failure 2) Instances which might affect validity of warranties or bonds C. Manual for Materials and Finishes 1. Submit 5 copies of complete manual in final form. 2. Content, for architectural products, applied materials and finishes: a. Manufacturer's data, giving full information on products 1) Catalog number, size, composition 2) Color and texture designations 3) Information required for reordering special manufactured products b. Instructions for care and maintenance 1) Manufacturer's recommendation for types of cleaning agents and methods 2) Cautions against cleaning agents and methods which are detrimental to product 3) Recommended schedule for cleaning and maintenance 3. Content, for moisture protection and weather exposure products: a. Manufacturer's data, giving full information on products 1) Applicable standards 2) Chemical composition 3) Details of installation b. Instructions for inspection, maintenance and repair D. Manual for Equipment and Systems 1. Submit 5 copies of complete manual in final form. 2. Content, for each unit of equipment and system, as appropriate: a. Description of unit and component parts 1) Function, normal operating characteristics and limiting conditions 2) Performance curves, engineering data and tests 3) Complete nomenclature and commercial number of replaceable parts b. Operating procedures 1) Start-up, break-in, routine and normal operating instructions 2) Regulation, control, stopping, shut-down and emergency instructions 3) Summer and winter operating instructions 4) Special operating instructions c. Maintenance procedures 1) Routine operations 2) Guide to "trouble shooting" 3) Disassembly, repair and reassembly 4) Alignment, adjusting and checking d. Servicing and lubrication schedule 1) List of lubricants required e. Manufacturer's printed operating and maintenance instructions f. Description of sequence of operation by control manufacturer 1) Predicted life of parts subject to wear 2) Items recommended to be stocked as spare parts g. As installed control diagrams by controls manufacturer h. Each contractor's coordination drawings 1) As installed color coded piping diagrams 01 78 23 - 4 DAP OPERATION AND MAINTENANCE DATA Page 4 of 5 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised April 7, 2014 i. Charts of valve tag numbers, with location and function of each valve j. List of original manufacturer's spare parts, manufacturer's current prices, and recommended quantities to be maintained in storage k. Other data as required under pertinent Sections of Specifications 3. Content, for each electric and electronic system, as appropriate: a. Description of system and component parts 1) Function, normal operating characteristics, and limiting conditions 2) Performance curves, engineering data and tests 3) Complete nomenclature and commercial number of replaceable parts b. Circuit directories of panelboards 1) Electrical service 2) Controls 3) Communications c. As installed color coded wiring diagrams d. Operating procedures 1) Routine and normal operating instructions 2) Sequences required 3) Special operating instructions e. Maintenance procedures 1) Routine operations 2) Guide to "trouble shooting" 3) Disassembly, repair and reassembly 4) Adjustment and checking f. Manufacturer's printed operating and maintenance instructions g. List of original manufacturer's spare parts, manufacturer's current prices, and recommended quantities to be maintained in storage h. Other data as required under pertinent Sections of Specifications 4. Prepare and include additional data when the need for such data becomes apparent during instruction of City's personnel. 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE A. Provide operation and maintenance data by personnel with the following criteria: 1. Trained and experienced in maintenance and operation of described products 2. Skilled as technical writer to the extent required to communicate essential data 3. Skilled as draftsman competent to prepare required drawings 01 78 23 - 5 DAP OPERATION AND MAINTENANCE DATA Page 5 of 5 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised April 7, 2014 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 8/31/2012 D. Johnson 1.5.A.1 – title of section removed 4/7/2014 M.Domenech Revised for DAP Application 01 78 39 - 1 DAP PROJECT RECORD DOCUMENTS Page 1 of 4 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised April 7, 2014 SECTION 01 78 39 PROJECT RECORD DOCUMENTS PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Work associated with the documenting the project and recording changes to project documents, including: a. Record Drawings b. Water Meter Service Reports c. Sanitary Sewer Service Reports d. Large Water Meter Reports B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various Items bid. No separate payment will be allowed for this Item. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 1.5 SUBMITTALS A. Prior to submitting a request for Final Inspection, deliver Project Record Documents to City’s Project Representative. 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE A. Accuracy of Records 1. Thoroughly coordinate changes within the Record Documents, making adequate and proper entries on each page of Specifications and each sheet of Drawings and other Documents where such entry is required to show the change properly. 2. Accuracy of records shall be such that future search for items shown in the Contract Documents may rely reasonably on information obtained from the approved Project Record Documents. 01 78 39 - 2 DAP PROJECT RECORD DOCUMENTS Page 2 of 4 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised April 7, 2014 3. To facilitate accuracy of records, make entries within 24 hours after receipt of information that the change has occurred. 4. Provide factual information regarding all aspects of the Work, both concealed and visible, to enable future modification of the Work to proceed without lengthy and expensive site measurement, investigation and examination. 1.10 STORAGE AND HANDLING A. Storage and Handling Requirements 1. Maintain the job set of Record Documents completely protected from deterioration and from loss and damage until completion of the Work and transfer of all recorded data to the final Project Record Documents. 2. In the event of loss of recorded data, use means necessary to again secure the data to the City's approval. a. In such case, provide replacements to the standards originally required by the Contract Documents. 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS 2.1 OWNER-FURNISHED [OR] OWNER-SUPPLIED PRODUCTS [NOT USED] 2.2 RECORD DOCUMENTS A. Job set 1. Promptly following receipt of the Notice to Proceed, secure from the City, at no charge to the Contractor, 1 complete set of all Documents comprising the Contract. B. Final Record Documents 1. At a time nearing the completion of the Work and prior to Final Inspection, provide the City 1 complete set of all Final Record Drawings in the Contract. 2.3 ACCESSORIES [NOT USED] 2.4 SOURCE QUALITY CONTROL [NOT USED] PART 3 - EXECUTION 3.1 INSTALLERS [NOT USED] 3.2 EXAMINATION [NOT USED] 3.3 PREPARATION [NOT USED] 3.4 MAINTENANCE DOCUMENTS A. Maintenance of Job Set 1. Immediately upon receipt of the job set, identify each of the Documents with the title, "RECORD DOCUMENTS - JOB SET". 01 78 39 - 3 DAP PROJECT RECORD DOCUMENTS Page 3 of 4 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised April 7, 2014 2. Preservation a. Considering the Contract completion time, the probable number of occasions upon which the job set must be taken out for new entries and for examination, and the conditions under which these activities will be performed, devise a suitable method for protecting the job set. b. Do not use the job set for any purpose except entry of new data and for review by the City, until start of transfer of data to final Project Record Documents. c. Maintain the job set at the site of work. 3. Coordination with Construction Survey a. At a minimum clearly mark any deviations from Contract Documents associated with installation of the infrastructure. 4. Making entries on Drawings a. Record any deviations from Contract Documents. b. Use an erasable colored pencil (not ink or indelible pencil), clearly describe the change by graphic line and note as required. c. Date all entries. d. Call attention to the entry by a "cloud" drawn around the area or areas affected. e. In the event of overlapping changes, use different colors for the overlapping changes. 5. Conversion of schematic layouts a. In some cases on the Drawings, arrangements of conduits, circuits, piping, ducts, and similar items, are shown schematically and are not intended to portray precise physical layout. 1) Final physical arrangement is determined by the Contractor, subject to the City's approval. 2) However, design of future modifications of the facility may require accurate information as to the final physical layout of items which are shown only schematically on the Drawings. b. Show on the job set of Record Drawings, by dimension accurate to within 1 inch, the centerline of each run of items. 1) Final physical arrangement is determined by the Contractor, subject to the City's approval. 2) Show, by symbol or note, the vertical location of the Item ("under slab", "in ceiling plenum", "exposed", and the like). 3) Make all identification sufficiently descriptive that it may be related reliably to the Specifications. c. The City may waive the requirements for conversion of schematic layouts where, in the City's judgment, conversion serves no useful purpose. However, do not rely upon waivers being issued except as specifically issued in writing by the City. B. Final Project Record Documents 1. Transfer of data to Drawings a. Carefully transfer change data shown on the job set of Record Drawings to the corresponding final documents, coordinating the changes as required. b. Clearly indicate at each affected detail and other Drawing a full description of changes made during construction, and the actual location of items. c. Call attention to each entry by drawing a "cloud" around the area or areas affected. 01 78 39 - 4 DAP PROJECT RECORD DOCUMENTS Page 4 of 4 CITY OF FORT WORTH Ranch at Duck Creek Phase 2 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #103754 Revised April 7, 2014 d. Make changes neatly, consistently and with the proper media to assure longevity and clear reproduction. 2. Transfer of data to other Documents a. If the Documents, other than Drawings, have been kept clean during progress of the Work, and if entries thereon have been orderly to the approval of the City, the job set of those Documents, other than Drawings, will be accepted as final Record Documents. b. If any such Document is not so approved by the City, secure a new copy of that Document from the City at the City's usual charge for reproduction and handling, and carefully transfer the change data to the new copy to the approval of the City. 3.5 REPAIR / RESTORATION [NOT USED] 3.6 RE-INSTALLATION [NOT USED] 3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED] 3.8 SYSTEM STARTUP [NOT USED] 3.9 ADJUSTING [NOT USED] 3.10 CLEANING [NOT USED] 3.11 CLOSEOUT ACTIVITIES [NOT USED] 3.12 PROTECTION [NOT USED] 3.13 MAINTENANCE [NOT USED] 3.14 ATTACHMENTS [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 4/7/2014 M.Domenech Revised for DAP Application GEOTECHNICAL REPORT GEOTECHNICAL EXPLORATION RANCH AT DUCK CREEK – PHASE 2 Off Wj Boaz Road Fort Worth, Texas ALPHA Report No. W212004 September 1, 2021 Prepared for: STARLIGHT HOMES TEXAS, LLC 1800 Valley View Lane, Suite 100 Farmers Branch, Texas 75234 Attention: Mr. Scot Albert Prepared By: Geotechnical Construction Materials Environmental TBPE Firm No. 813 5058 Brush Creek Road Fort Worth, Texas 76119 Tel: 817-496-5600 Fax: 817-496-5608 www.alphatesting.com Dallas • Fort Worth • Houston • San Antonio September 1, 2021 Starlight Homes Texas, LLC 1800 Valley View Lane, Suite 100 Farmers Branch, Texas 75234 Attention: Mr. Scot Albert Re: Geotechnical Exploration Ranch at Duck Creek – Phase 2 Off Wj Boaz Road Fort Worth, Texas ALPHA Report No. W212004 Attached is the report of the geotechnical exploration performed for the project referenced above. This study was authorized by Mr. Scot Albert using the Starlight Homes Work Agreement on July 01, 2021 and performed in accordance with ALPHA Proposal No. 85000-rev1 dated July 01, 2021. This report contains results of field explorations and laboratory testing and an engineering interpretation of these with respect to available project characteristics. The results and analyses were used to develop recommendations to aid design and construction of residential foundations. ALPHA TESTING, INC. appreciates the opportunity to be of service on this project. If we can be of further assistance, such as providing materials testing services during construction, please contact our office. Sincerely, ALPHA TESTING, INC. September 1, 2021 Kimberly Fyffe Brian J. Hoyt, P.E. Geotechnical Project Manager Geotechnical Department Manager BJH/KLF/nl Copies: (1-PDF) Client TABLE OF CONTENTS ALPHA REPORT NO. W212004 PURPOSE AND SCOPE .................................................................................................... 1 PROJECT CHARACTERISTICS ...................................................................................... 1 FIELD EXPLORATION .................................................................................................... 2 LABORATORY TESTS .................................................................................................... 2 GENERAL SUBSURFACE CONDITIONS ...................................................................... 2 DESIGN RECOMMENDATIONS .................................................................................... 3 6.1 Backfilled Pond ....................................................................................................... 3 6.2 Slab-on-Grade Foundations .................................................................................... 4 6.2.1 Subgrade Improvement Using Moisture Conditioning in Zone II .............. 5 6.3 Post-Tensioning Institute, Design of Post-Tensioned Slab-on-Grade .................... 6 6.4 Drainage and Other Considerations ........................................................................ 6 GENERAL CONSTRUCTION PROCEDURES AND GUIDELINES ............................. 7 7.1 Site Preparation and Grading .................................................................................. 8 7.2 Foundation Excavations .......................................................................................... 9 7.3 Fill Compaction ...................................................................................................... 9 7.4 Utilities .................................................................................................................. 10 7.5 Groundwater ......................................................................................................... 10 LIMITATIONS ................................................................................................................. 11 APPENDIX A-1 Methods of Field Exploration Boring Location Plan – Figure 1 B-1 Methods of Laboratory Testing Logs of Borings Key to Soil Symbols and Classifications ALPHA Report No. W212004 1 PURPOSE AND SCOPE The purpose of this geotechnical exploration is for ALPHA TESTING, INC. (“ALPHA”) to evaluate for Starlight Homes Texas, LLC (Client) some of the physical and engineering properties of subsurface materials at selected locations on the subject site with respect to formulation of geotechnical design parameters for the subject construction. The field exploration was accomplished by securing subsurface samples from widely spaced test borings performed across the project site. Engineering analyses were performed from results of the field exploration and laboratory tests performed on representative samples. In addition, results of a Geotechnical Exploration performed at the site (ALPHA Report No. W193011 dated January 15, 2020) were reviewed as part of this current study. Also included are general comments pertaining to reasonably anticipated construction problems and recommendations concerning earthwork and quality control testing during construction. This information can be used to evaluate subsurface conditions and to aid in ascertaining construction meets project specifications. Recommendations provided in this report were developed from information obtained in test borings depicting subsurface conditions only at the specific boring locations and at the particular time designated on the logs. Subsurface conditions at other locations may differ from those observed at the boring locations, and subsurface conditions at boring locations may vary at different times of the year. The scope of work may not fully define the variability of subsurface materials and conditions that are present on the site. The nature and extent of variations between borings may not become evident until construction. If significant variations then appear evident, our office should be contacted to re-evaluate our recommendations after performing on-site observations and possibly other tests PROJECT CHARACTERISTICS It is proposed to develop a residential subdivision (Ranch at Duck Creek) on a tract of land located on the north side of Wj Boaz Road, about 1,900 west of North Old Decatur Road in Fort Worth, Texas. A site plan illustrating the subject site is provided as Figure 1, the Boring Location Plan, in the Appendix. At the time the field exploration was performed, the site consisted of a tract of land with some scattered trees. An abandoned gas pad is located in the northwest corner of the site at Boring 7. Historical aerial images available from Google Earth® indicate a pond was backfilled north of Boring 7. No other information regarding previous development of the site was provides to us. Grading plans prepared by Goodwin and Marshall, Inc. (Job No. 10874, Sheets 31, 32 and 33 dated March 2021) indicate the site slopes down towards the east about 25 ft (approximate elevation 795 ft to 770 ft). These grading plans also indicate cuts of up to 6 ft and fills of up to 5 ft will be required to achieve final grade in the building pad areas. ALPHA Report No. W212004 2 FIELD EXPLORATION Subsurface conditions on the site were explored by drilling a total of 31 test borings to a depth of 20 ft. The borings were drilled in general accordance with ASTM Standard D 420 using standard rotary drilling equipment. The approximate location of each test boring is shown on the Boring Location Plan, Figure 1, enclosed in the Appendix. Details of drilling and sampling operations are briefly summarized in Methods of Field Exploration, Section A-1 of the Appendix. Subsurface types encountered during the field exploration are presented on the Log of Boring sheets (boring logs) included in the Appendix. The boring logs contain our Field Technician's and Engineer's interpretation of conditions believed to exist between actual samples retrieved. Therefore, the boring logs contain both factual and interpretive information. Lines delineating subsurface strata on the boring logs are approximate and the actual transition between strata may be gradual. LABORATORY TESTS Selected samples of the subsurface materials were tested in the laboratory to evaluate their engineering properties as a basis in providing recommendations for residential foundation design and earthwork construction. A brief description of testing procedures used in the laboratory can be found in Methods of Laboratory Testing, Section B-1 of the Appendix. Individual test results are presented on the Log of Boring sheets in the Appendix. GENERAL SUBSURFACE CONDITIONS Based on geological maps available from the Bureau of Economic Geology, published by The University of Texas at Austin, the project site lies within the undivided Fort Worth Limestone and Duck Creek formation. This undivided formation generally consists of alternating layers of limestone and marl (limey shale). Residual overburden soils associated with these undivided formations generally consist of clay soils characterized by moderate to high shrink-swell potential. Subsurface conditions encountered in most of the borings generally consisted of clay and shaly clay to depths of about 5 ft to 19 ft below the ground surface underlain by limestone extending to the 20 ft termination depth of the borings. Subsurface conditions encountered in Borings 1, 2, 3, 4, 5, 7, 10 and 13 generally consisted of clay, shaly clay and/or shale extending to the 20 ft termination depth. Layers of limestone about 1 ft to 13 ft thick were encountered between the clay and shaly clay layers in Borings 1, 2, 4, 5, 7, 10 and 13 at depths of about 3 ft to 8 ft below the ground surface. Most of the materials encountered in the borings are considered relatively impermeable and are anticipated to have a relatively slow response to water movement. Therefore, several days of observation would be required to evaluate actual groundwater levels within the depths explored. Also, the groundwater level at the subject site is anticipated to fluctuate seasonally depending on the amount of rainfall, prevailing weather conditions, and subsurface drainage characteristics. ALPHA Report No. W212004 3 Free groundwater was not encountered in the borings. However, it is common to encounter seasonal groundwater from natural fractures within the clayey matrix, at the soil/rock (limestone) interface or from fractures in the rock (limestone), particularly during or after periods of precipitation. If more detailed groundwater information is required, monitoring wells or piezometers can be installed. Further details concerning subsurface materials and conditions encountered can be obtained from the boring logs provided in the Appendix. DESIGN RECOMMENDATIONS The following design recommendations were developed on the basis of the previously described Project Characteristics (Section 2.0) and General Subsurface Conditions (Section 5.0). Should the project criteria change, our office should conduct a review to determine if modifications to the recommendations are required. Further, it is recommended our office be provided with a copy of the final building plans and specifications for review prior to construction. The following design recommendations were evaluated based on final grades as indicated on the referenced grading plans and discussed in Section 2.0. Cutting and filling on the site other than depicted on the referenced grading plans can alter the recommended foundation design parameters. Therefore, it is recommended our office be provided with final grading plans prior to construction to verify appropriate design parameters are utilized for final foundation design. 6.1 Backfilled Pond As discussed in Section 2.0, a pond was backfilled north of Boring 7. It is not known if this fill was placed under engineering supervision with compaction records. If compaction records for this fill cannot be obtained, the existing fill should be considered as uncontrolled fill. Uncontrolled fill is generally not considered suitable for support of slab foundations due to the risk of under- compacted zones resulting in failures of weak soil and/or indeterminate levels of settlement. Any existing uncontrolled fill should be removed from the building pad areas and replaced with engineered fill as recommended in Section 6.2 where moisture conditioned soils are required or Section 7.3 where general fill is required. The excavated materials may be suitable for reuse as engineered fill provided they are free of organics, boulders, rubble, and other debris. The lateral extent, depth and nature of the existing fill are not known. Test pits could be performed prior to construction to verify the presence, lateral extent, depth, and nature of the existing fill materials. ALPHA would be pleased to provide this service if desired. The depth of existing fill in the pond is not known. Even if fill is properly compacted as recommended in Section 7.3, fills in excess of about 10 ft are still subject to settlements over time of up to about 1 to 2 percent of the total fill thickness. This should be considered when backfilling ponds in areas where foundations are planned. ALPHA Report No. W212004 4 6.2 Slab-on-Grade Foundations Slab-on-grade foundations should be designed with exterior and interior grade beams adequate to provide sufficient rigidity to the foundation system. A net allowable bearing pressure of 1.5 kips per sq ft should be used for all grade beams bearing on undisturbed cuts in native soils, on general fill placed as recommended in Section 7.3, on moisture improved soil placed as recommended in Section 6.2.1 or on limestone. Grade beams should bear a minimum depth of 12 inches below final grade and should have a minimum width of 10 inches considering the recommended bearing capacity. To reduce cracking as normal movements occur in foundation soils, all grade beams and slab foundations should be adequately reinforced with steel (conventional reinforcing steel and/or post- tensioned reinforcement). It is common to experience some minor cosmetic distress to structures with slab-on-grade foundation systems due to normal ground movements. A properly designed and constructed moisture barrier should be placed between the slabs and subgrade soils to retard moisture migration through the slabs. Conditions encountered in the test borings, the planned cut/fill within the building pads and results of the laboratory tests reveal variations in highly expansive clay thickness and expansive properties across the site. Such variations in clay thickness and expansive properties will directly affect design parameters used for slab-on-grade foundations. Therefore, lots with apparently common average clay thickness, similar expansive clay properties and similar corresponding estimated potential movements have been grouped into Zones I and II and delineated on the Boring Location Plan, Figure 1. Subgrade improvement in the respective Zones (see Figure 1) should be performed using the information summarized in Table A. TABLE A Estimates of Potential Seasonal Movements and Required Subgrade Improvement ZONE ESTIMATED POTENTIAL MOVEMENT, INCHES IMPROVEMENT REQUIRED TO REDUCE MOVEMENTS TO 4½ INCHES I Up to 4½ No Improvement Required II Up to about 6½ 4 ft of Moisture Conditioning Potential seasonal movements were estimated using results from absorption swell tests, in general accordance with methods outlined by the Texas Department of Transportation (TxDOT) Test Method Tex-124-E and engineering judgment and experience. Estimated movements were calculated assuming the moisture content of the in-situ soil within the normal zone of seasonal moisture content change varies between a "dry" condition and a "wet" condition as defined by Tex-124-E. Also, it was assumed a 1 psi surcharge load from the floor slab acts on the subgrade soils. Movements exceeding our estimates could occur if positive drainage of surface water is not maintained or if soils are subject to an outside water source, such as leakage fro m a utility line or subsurface moisture migration from off-site locations. ALPHA Report No. W212004 5 Potential seasonal movements were estimated assuming fill material used to raise the grade will consist of onsite or similar material with a plasticity index of 50 or less. If the plasticity index of material used to raise the grade is higher than 50, potential movements could be higher than our estimates. Potential movements estimated for slab foundations in Zone II (see Figure 1 for delineation of Zones) are considered outside normal design tolerances. Movement of slab foundations in Zone II could be reduced to not more than 4½ inches if the upper 4 ft of soil below final grade, as summarized in Table A, are moisture conditioned and then covered with an impermeable plastic barrier (polyethylene sheeting). Moisture conditioning recommendations are provided in Section 6.2.1. In choosing moisture conditioning as a method of slab movement reduction, the Client is accepting some post construction movement of slabs (about 4½ inches). Therefore, the Client understands and acknowledges that in the geographical region covered by this report, a potential movement of 4½ inches is considered a reasonable compromise between foundation design and construction cost and the amount of allowable movement of the foundation. Please note, improvement of the existing soils using moisture conditioning with plastic sheeting is intended only for the designated building pad areas plus 5 ft beyond the building pad limits, and not the entire residential lot. Accordingly, planned residences must be exclusively constructed within 1 ft of the existing ground surface. The purpose of the plastic sheeting is to maintain the moisture of the underlying soils relatively the same from the time the plastic sheeting is placed through the time the foundation is placed. This plastic sheeting is not intended as a moisture barrier component for the actual foundation. Any such requirements should be addressed by the designer of the foundation, and should be followed by the builder. Prior to building on the improved designated building pad area, a surveyor should verify the lateral extent of the plastic sheeting and to confirm that no portion of the new residences will extend beyond the limits of the designated building pad. If any part of the slab footprint extends beyond the designated building pad, ALPHA should be contacted for additional design recommendations. 6.2.1 Subgrade Improvement Using Moisture Conditioning in Zone II Estimated potential movements of slab foundations in Zone II could be reduced to about 4½ inches by moisture-conditioning the uppermost 4 ft of soil below final grade as recommended in Table A. Limestone could be encountered within the recommended depth of moisture conditioning, particularly near zone boundaries. It is not required to over-excavate limestone to install moisture conditioned soils. Test pits should be performed to verify the nature of limestone prior to terminating moisture conditioning at depths shallower than recommended. ALPHA should be retained to observe the test pits.. Moisture-conditioning consists of over-excavating (where necessary) and/or filling with on-site soil that is compacted at a “target” moisture content at least 5 percentage points above the material’s optimum moisture content as determined by the standard Proctor method (ASTM D 698). The moisture-conditioned soil should be compacted to a dry density between 93 and 98 percent of standard Proctor maximum dry density. Moisture- conditioning with on-site soil should extend throughout the entire building pad area and at ALPHA Report No. W212004 6 least 5 ft beyond the perimeter of the designated building pad (as indicated on the referenced project grading plans). Following completion of moisture-conditioning and placement of the plastic sheeting, estimated movements in Zone II should not exceed about 4½ inches. The purpose of moisture-conditioning is to reduce the free swell of the moisture- conditioned soils to 1 percent or less. Additional laboratory tests (i.e., standard Proctors, absorption swell tests, etc.) should be conducted during construction to verify that the “target” moisture content for moisture-conditioning (estimated at 5 percentage points above the material’s optimum moisture content as defined by ASTM D 698) is sufficient to reduce the free swell potential of the processed soil to 1 percent or less. Moisture conditioning should be observed and tested on a full time basis by a representative of ALPHA to verify the moisture conditioned clays are placed with the proper lift thickness, moisture content, and density. 6.3 Post-Tensioning Institute, Design of Post-Tensioned Slab-on-Grade Table B contains information for design of the post-tensioned, slab-on-grade foundations. Design parameters were evaluated based on the conditions encountered in the borings and using information and correlations published by PTI Third Edition and VOLFLO 1.5 computer program provided by Geostructural Tool Kit, Inc. (GTI). TABLE B PTI Design Parameters Potential Seasonal Movement = 4½ inches In Zone I and after subgrade improvement in Zone II as recommended in Section 6.2 Edge Lift Center Lift Edge Moisture Distance (em), ft 4.0 8.0 Differential Soil Movement (ym), inches 2.3 (swell) 1.6 (Shrink) 6.4 Drainage and Other Considerations Adequate drainage should be provided to reduce seasonal variations in the moisture content of foundation soils. All pavement and sidewalks within 5 ft of the residences should be sloped away from the structures to prevent ponding of water around the foundations. Final grades within 5 ft of the structures should be adjusted to slope away from the structures at a minimum slope of 2 percent. Maintaining positive surface drainage throughout the life of the structures is essential. In areas with pavement or sidewalks adjacent to the new residences, a positive seal must be maintained between the structure and the pavement or sidewalk to minimize seepage of water into the underlying supporting soils. Post-construction movement of pavement and flatwork is common. Normal maintenance should include inspection of all joints in paving and sidewalks, etc. as well as resealing where necessary. ALPHA Report No. W212004 7 Several factors relate to civil and architectural design and/or maintenance, which can significantly affect future movements of the foundation and floor slab systems: • Preferably, a complete system of gutters and downspouts should carry runoff water a minimum of 5 ft from the completed structures. • Large trees and shrubs should not be allowed closer to the foundation than a horizontal distance equal to roughly one-half of their mature height due to their significant moisture demand upon maturing. • Moisture conditions should be maintained “constant” around the edge of the slab. Ponding of water in planters, in unpaved areas, and around joints in paving and sidewalks can cause slab movements beyond those predicted in this report. • Planter box structures placed adjacent to building should be provided with a means to assure concentrations of water are not available to the subsoil stratigraphy. • Architectural design of the floor slabs should avoid additional features such as wing walls as extensions of the slab. • The root systems from existing trees at this site will have dried and desiccated the surrounding clay soils, resulting in soil with near-maximum swell potential. Clay soils surrounding tree root mats in areas to be covered with grade slabs (including but not limited to foundations, driveways, patios and sidewalks) should be removed to a minimum depth of 1 ft below the root ball and compacted in-place with moisture and density control as described in Section 7.3. Trench backfill for utilities should be properly placed and compacted as outlined in Section 7.4 and in accordance with requirements of local City standards. Since granular bedding backfill is used for most utility lines, the backfilled trench should not become a conduit and allow access for surface or subsurface water to travel toward the new structures. Concrete cut-off collars or clay plugs should be provided where utility lines cross building lines to prevent water from traveling in the trench backfill and entering beneath the structure. GENERAL CONSTRUCTION PROCEDURES AND GUIDELINES Variations in subsurface conditions could be encountered during construction. To permit correlation between test boring data and actual subsurface conditions encountered during construction, it is recommended a registered Professional Engineering firm be retained to observe construction procedures and materials. Some construction problems, particularly degree or magnitude, cannot be reasonably anticipated until the course of construction. The recommendations offered in the following paragraphs are intended not to limit or preclude other conceivable solutions, but rather to provide our observations based on our experience and understanding of the project characteristics and subsurface conditions encountered in the borings. ALPHA Report No. W212004 8 7.1 Site Preparation and Grading Limestone was encountered within 4 ft of the ground surface in several borings and could be encountered during general excavation and grading at this site. From our experience, this limestone can be hard and difficult to excavate. Rock excavation methods (including, but not limited to rock teeth, rippers, jack hammers, or sawcutting) may be required to remove the limestone. Crushing equipment may be required to process this limestone if it is desired to use this material as compacted fill on the site. The contractor selected should have experience with excavation in hard limestone. All areas supporting slab foundations, flatwork or areas to receive new fill should be properly prepared. • After completion of the necessary stripping, clearing, and excavating and prior to placing any required fill, the exposed subgrade should be carefully evaluated by probing and testing. Any undesirable material (organic material, wet, soft, or loose soil) still in place should be removed. • The exposed subgrade should be further evaluated by proof-rolling with a heavy pneumatic tired roller, loaded dump truck or similar equipment weighing approximately 10 tons to check for pockets of soft or loose material hidden beneath a thin crust of possibly better soil. • Proof-rolling procedures should be observed routinely by a Professional Engineer or his designated representative. Any undesirable material (organic material, wet, soft, or loose soil) exposed from the proof roll should be removed and replaced with well-compacted material as outlined in Section 7.3. • Prior to placement of any fill, the exposed subgrade should then be scarified to a minimum depth of 6 inches and recompacted as outlined in Section 7.3. If fill is to be placed on existing slopes (natural or constructed) steeper than six horizontal to one vertical (6:1), the fill materials should be benched into the existing slopes in such a manner as to provide a minimum bench width of five (5) ft. This should provide a good contact between the existing soils and new fill materials, reduce potential sliding planes, and allow relatively horizontal lift placements. Even if fill is properly compacted as recommended in Section 7.3, fills in excess of about 10 ft are still subject to settlements over time of up to about 1 to 2 percent of the total fill thickness. This should be considered when planning or placing deep fills. Slope stability analysis of embankments (natural or constructed) and global stability analysis for retaining walls was not within the scope of this study. The contractor is responsible for designing any excavation slopes, temporary sheeting or shoring. Design of these structures should include any imposed surface surcharges. Construction site safety is the sole responsibility of the contractor, who shall also be solely responsible for the means, methods and sequencing of construction operations. The contractor should also be aware that ALPHA Report No. W212004 9 slope height, slope inclination or excavation depths (including utility trench excavations) should in no case exceed those specified in local, state and/or federal safety regulations, such as OSHA Health and Safety Standard for Excavations, 29 CFR Part 1926, or successor regulations. Stockpiles should be place well away from the edge of the excavation and their heights should be controlled so they do not surcharge the sides of the excavation. Surface drainage shou ld be carefully controlled to prevent flow of water over the slopes and/or into the excavations. Construction slopes should be closely observed for signs of mass movement, including tension cracks near the crest or bulging at the toe. If potential stability problems are observed, a geotechnical engineer should be contacted immediately. Shoring, bracing or underpinning required for the project (if any) should be designed by a professional engineer registered in the State of Texas. Due to the nature of the clay soils found near the surface at the borings, traffic of heavy equipment (including heavy compaction equipment) may create pumping and general deterioration of shallow soils. Therefore, some construction difficulties should be anticipated during periods when these soils are saturated. 7.2 Foundation Excavations All foundation excavations should be monitored to verify foundations bear on suitable material. The bearing stratum exposed in the base of all foundation excavations should be protected against any detrimental change in conditions. Surface runoff water should be drained away from excavations and not allowed to collect. All concrete for foundations should be placed as soon as practical after the excavation is made. Prolonged exposure of the bearing surface to air or water will result in changes in strength and compressibility of the bearing stratum. Therefore, if delays occur, excavations should be slightly deepened and cleaned, in order to provide a fresh bearing surface. 7.3 Fill Compaction The following are recommendations pertaining to general fill compaction. Moisture conditioned soil should conform to the recommendations provided in Section 6.2. Clay soils with a plasticity index equal to or greater than 25 should be compacted to a dry density between 93 and 98 percent of standard Proctor maximum dry density (ASTM D 698). The compacted moisture content of the clays during placement should be within the range of 2 to 6 percentage points above optimum. Clay soils with a plasticity index less than 25 should be compacted to a dry density of at least 95 percent of standard Proctor maximum dry density (ASTM D 698) and within the range of 1 percentage point below to 3 percentage points above the material's optimum moisture content. Clayey materials used as fill should be processed and the largest particle or clod should be less than 6 inches prior to compaction. ALPHA Report No. W212004 10 Processed limestone used as fill should be compacted to at least 95 percent of standard Proctor maximum dry density. The compacted moisture content of the processed limestone is not considered crucial to proper performance. However, if the material's moisture content during placement is within 3 percentage points of optimum, the compactive effort required to achieve the minimum compaction criteria may be minimized. Individual rock pieces larger than 6 inches in dimension should not be used as fill. However, if rock fill is utilized within 3 ft below the bottom of floor slabs, the maximum allowable size of individual rock pieces should be reduced to 3 inches. Processed limestone used as fill should incorporate sufficient fines to prevent the presence of voids around larger diameter rock pieces. A gradation of at least 40 percent passing a standard No. 4 sieve is recommended. Where mass fills are deeper than 10 ft, the fill/backfill below 10 ft should be compacted to at least 100 percent of standard Proctor maximum dry density (ASTM D-698) and within 2 percentage points of the material's optimum moisture content. The portion of the fill/backfill shallower than 10 ft should be compacted as outlined herein. Compaction should be accomplished by placing fill in about 8-inch thick loose lifts and compacting each lift to at least the specified minimum dry density. Field density and moisture content tests should be performed on each lift. 7.4 Utilities Where utility lines are deeper than 10 ft, the fill/backfill below 10 ft should be compacted to at least 100 percent of standard Proctor maximum dry density (ASTM D 698) and within –2 to +2 percentage points of the material's optimum moisture content. The portion of the fill/backfill shallower than 10 ft should be compacted as previously outlined. Density tests should be performed on each lift (maximum 12-inch thick) and should be performed as the trench is being backfilled. Even if fill is properly compacted, fills in excess of about 10 ft are still subject to settlements over time of up to about 1 to 2 percent of the total fill thickness. This should be considered when designing pavement over utility lines and/or other areas with deep fill. If utility trenches or other excavations extend to or beyond a depth of 5 ft below construction grade, the contractor or others shall be required to develop an excavation safety plan to protect personnel entering the excavation or excavation vicinity. The collection of specific geotechnical data and the development of such a plan, which could include designs for sloping and benching or various types of temporary shoring, is beyond the scope of this study. Any such designs and safety plans shall be developed in accordance with current OSHA guidelines and other applicable industry standards. 7.5 Groundwater Groundwater was not encountered in the borings. However, from our experience, shallow groundwater seepage could be encountered from the subsurface stratigraphy in excavations for pavement, utilities and other general excavations at this site. The risk of seepage increases with depth of excavation and during or after periods of precipitation. Standard sump pits and pumping may be adequate to control seepage on a local basis. ALPHA Report No. W212004 11 In any areas where cuts are made, attention should be given to possible seasonal water seepage that could occur through natural cracks and fissures in the newly exposed stratigraphy. Also, the risk of seepage is increased where limestone is exposed in excavations and slopes or is near final grade. In these areas subsurface drains may be required to intercept seasonal groundwater seepage. The need for these or other dewatering devices should be carefully addressed during construction. Our office could be contacted to visually observe final grades to evaluate the need for such drains. LIMITATIONS Professional services provided in this geotechnical exploration were performed, findings obtained, and recommendations prepared in accordance with generally accepted geotechnical engineering principles and practices. The scope of services provided herein does not include an environmental assessment of the site or investigation for the presence or absence of hazardous materials in the soil, surface water or groundwater. ALPHA, upon written request, can be retained to provide these services. ALPHA is not responsible for conclusions, opinions or recommendations made by others based on this data. Information contained in this report is intended for the exclusive use of the Client (and their designated design representatives), and is related solely to design of the specific structures outlined in Section 2.0. No party other than the Client (and their designated design representatives) shall use or rely upon this report in any manner whatsoever unless such party shall have obtained ALPHA’s written acceptance of such intended use. Any such third party using this report after obtaining ALPHA’s written acceptance shall be bound by the limitations and limitations of liability contained herein, including ALPHA’s liability being limited to the fee paid to it for this report. Recommendations presented in this report should not be used for design of any other structures except those specifically described in this report. In all areas of this report in which ALPHA may provide additional services if requested to do so in writing, it is presumed that such requests have not been made if not evidenced by a written document accepted by ALPHA. Further, subsurface conditions can change with passage of time. Recommendations contained herein are not considered applicable for an extended period of time after the completion date of this report. It is recommended our office be contacted for a review of the contents of this report for construction commencing more than one (1) year after completion of this report. Non - compliance with any of these requirements by the Client or anyone else shall release ALPHA from any liability resulting from the use of, or reliance upon, this report. Recommendations provided in this report are based on our understanding of information provided by the Client about characteristics of the project. If the Client notes any deviation from the facts about project characteristics, our office should be contacted immediately since this may materially alter the recommendations. Further, ALPHA is not responsible for damages resulting from workmanship of designers or contractors. It is recommended the Owner retain qualified personnel, such as a Geotechnical Engineering firm, to verify construction is performed in accordance with plans and specifications. APPENDIX ALPHA Report No. W212004 A-1 METHODS OF FIELD EXPLORATION Using standard rotary drilling equipment, a total of 31 test borings were performed for this geotechnical exploration. The approximate locations of the borings are shown on the Boring Location Plan, Figure 1. The test boring locations were staked using a handheld GPS unit or by pacing/taping and estimating right angles from landmarks which could be identified in the field and as shown on the site plan provided during this study. The locations of test borings shown on the Boring Location Plan are considered accurate only to the degree implied by the methods used to define them. Relatively undisturbed samples of the cohesive subsurface materials were obtained by hydraulically pressing 3-inch O.D. thin-wall sampling tubes into the underlying soils at selected depths (ASTM D 1587). These samples were removed from the sampling tubes in the field and evaluated visually. One representative portion of each sample was sealed in a plastic bag for use in future visual evaluation and possible testing in the laboratory. A modified version of the Texas Cone Penetration (TCP) test was completed in the field to determine the apparent in-place strength characteristics of the rock type materials. A 3-inch diameter steel cone driven by a 170-pound hammer dropped 24 inches is the basis for TxDOT strength correlations. In this case, ALPHA TESTING, INC. has modified the procedure by using a 140-pound hammer dropping 30-inches for completion of the field test. Depending on the resistance (strength) of the materials, either the number of blows of the hammer required to provide 12 inches of penetration, or the inches of penetration of the cone due to 100 blows of the hammer are recorded on the field log and are shown on the Log of Boring sheets as “TX Cone” (reference TxDOT Test Method TEX 132-E, as modified). Logs of the borings are included in the Appendix. The logs show visual descriptions of subsurface strata encountered using the Unified Soil Classification System. Sampling information, pertinent field data, and field observations are also included. Samples not consumed by testing will be retained in our laboratory for at least 14 days and then discarded unless the Client requests otherwise. BORING LOCATION PLAN GEOTECHNICAL EXPLORATION RANCH AT DUCK CREEK - PHASE 2 OFF WJ BOAZ ROAD FORT WORTH, TEXAS ALPHA PROJECT NO. W212004 FIGURE 1 B-21 B-23 B-22 B-24 B-25 B-26 B-27 B-28B-11 B-13 B-12 B-14 B-15 B-16 B-17 B-18 B-19 B-20 B-1 B-3 B-2 B-4 B-5 B-6 B-7 B-8 B-9 B-10 B-17 B-12 B-44 B-50 B-46 B-1 B-33B-22 B-43 B-38 B-27B-7 B-28 B-51 B-29 B-30 B-31 I I I I I I I I I I I IIIII I I I I I I I I I I I I II II II II II II II IIII II II II II II II II IIII II II II II II II II II IIIIII II II II II II II II II II II IIII II II II II B-21 B-23 B-22 B-24 B-25 B-26 B-27 B-28B-11 B-13 B-12 B-14 B-15 B-16 B-17 B-18 B-19 B-20 B-1 B-3 B-2 B-4 B-5 B-6 B-7 B-8 B-9 B-10 B-17 B-12 B-44 B-50 B-46 B-1 B-33B-22 B-43 B-38 B-27B-7 B-28 B-51 B-29 B-30 B-31 I I I I I I I I I I I IIIII I I I I I I I I I I I I II II II II II II II IIII II II II II II II II IIII II II II II II II II II IIIIII II II II II II II II II II II IIII II II II II APPROXIMATE BORING LOCATION ZONE II I ZONE I II APPROXIMATE ADJACENT BORING LOCATION (W193011) N ALPHA Report No. W212004 B-1 METHODS OF LABORATORY TESTING Representative samples were evaluated and classified by a qualified member of the Geotechnical Division and the boring logs were edited as necessary. To aid in classifying the subsurface materials and to determine the general engineering characteristics, natural moisture content tests (ASTM D 2216), Atterberg-limit tests (ASTM D 4318) and dry unit weight determinations were performed on selected samples. In addition, unconfined compressive strength tests (ASTM D 2166) and pocket-penetrometer tests were conducted on selected soil samples to evaluate the soil shear strength. Results of these laboratory tests are provided on the Log of Boring sheets. In addition to the Atterberg-limit tests, the expansive properties of the clayey soils were further analyzed by absorption swell tests in general accordance with ASTM D 4546. The swell test is performed by placing a selected sample in a consolidation machine and applying either the approximate current or expected overburden pressure and then allowing the sample to absorb water. When the sample exhibits very little tendency for further expansion, the height increase is recorded and the percent free swell and total moisture gain calculated. Results of these laboratory tests are provided on the Log of Boring sheets. Client: Project: Start Date:End Date: Drilling Method: BORING NO.: PROJECT NO.: Location: Surface Elevation: West: North: Hammer Drop (lbs / in): De p t h , f e e t Gr a p h i c L o g MATERIAL DESCRIPTION Sa m p l e T y p e Re c o v e r y % RQ D TX C o n e o r S t d . Pe n . ( b l o w s / f t , i n ) Po c k e t Pe n e t r o m e t e r ( t s f ) Un c o n f i n e d C o m p . St r e n g t h ( t s f ) % P a s s i n g No . 2 0 0 S i e v e Un i t D r y W e i g h t (p c f ) Wa t e r C o n t e n t , % Li q u i d L i m i t Pl a s t i c L i m i t Pl a s t i c i t y I n d e x Sw e l l , % GROUND WATER OBSERVATIONS On Rods (ft): After Drilling (ft): After Hours (ft): Starlight Homes Texas, LLC W. Boaz Road Project 12/12/2019 12/12/2019 CONTINUOUS FLIGHT AUGER 1 W193011 Fort Worth, Texas 140 / 30 18 18 5058 Brush Creek Rd. Fort Worth,Texas 76119 Phone:817-496-5600 Fax:817-496-5608 www.alphatesting.com 5 10 15 20 Dark Brown CLAY 2.0 Light Brown CLAY 6.0 Tan CLAY 18.0 Tan LIMESTONE with clay seam and layers 20.0 TEST BORING TERMINATED AT 20 FT 2.25 30 2.75 23 65 22 43 0.4 2.75 22 3.75 19 3.5 17 3.5 15 100/1.25" Sheet 1 of 1 Client: Project: Start Date:End Date: Drilling Method: BORING NO.: PROJECT NO.: Location: Surface Elevation: West: North: Hammer Drop (lbs / in): De p t h , f e e t Gr a p h i c L o g MATERIAL DESCRIPTION Sa m p l e T y p e Re c o v e r y % RQ D TX C o n e o r S t d . Pe n . ( b l o w s / f t , i n ) Po c k e t Pe n e t r o m e t e r ( t s f ) Un c o n f i n e d C o m p . St r e n g t h ( t s f ) % P a s s i n g No . 2 0 0 S i e v e Un i t D r y W e i g h t (p c f ) Wa t e r C o n t e n t , % Li q u i d L i m i t Pl a s t i c L i m i t Pl a s t i c i t y I n d e x Sw e l l , % GROUND WATER OBSERVATIONS On Rods (ft): After Drilling (ft): After Hours (ft): Starlight Homes Texas, LLC W. Boaz Road Project 12/12/2019 12/12/2019 CONTINUOUS FLIGHT AUGER 7 W193011 Fort Worth, Texas 140 / 30 NONE DRY 5058 Brush Creek Rd. Fort Worth,Texas 76119 Phone:817-496-5600 Fax:817-496-5608 www.alphatesting.com 5 10 15 20 Dark Brown CLAY 4.0 Tan CLAY 19.0 Tan LIMESTONE with clay seam and layers 20.0 TEST BORING TERMINATED AT 20 FT 2.25 32 2.75 29 4.5+11 4.5+13 3.25 20 57 22 35 0.0 4.5+12 100/1.25" Sheet 1 of 1 Client: Project: Start Date:End Date: Drilling Method: BORING NO.: PROJECT NO.: Location: Surface Elevation: West: North: Hammer Drop (lbs / in): De p t h , f e e t Gr a p h i c L o g MATERIAL DESCRIPTION Sa m p l e T y p e Re c o v e r y % RQ D TX C o n e o r S t d . Pe n . ( b l o w s / f t , i n ) Po c k e t Pe n e t r o m e t e r ( t s f ) Un c o n f i n e d C o m p . St r e n g t h ( t s f ) % P a s s i n g No . 2 0 0 S i e v e Un i t D r y W e i g h t (p c f ) Wa t e r C o n t e n t , % Li q u i d L i m i t Pl a s t i c L i m i t Pl a s t i c i t y I n d e x Sw e l l , % GROUND WATER OBSERVATIONS On Rods (ft): After Drilling (ft): After Hours (ft): Starlight Homes Texas, LLC W. Boaz Road Project 12/12/2019 12/12/2019 CONTINUOUS FLIGHT AUGER 12 W193011 Fort Worth, Texas 140 / 30 17 7 5058 Brush Creek Rd. Fort Worth,Texas 76119 Phone:817-496-5600 Fax:817-496-5608 www.alphatesting.com 5 10 15 20 Dark Brown CLAY 4.0 Tan CLAY 15.0 Tan LIMESTONE with clay seam and layers 17.0 Gray LIMESTONE with shale seams 20.0 TEST BORING TERMINATED AT 20 FT 2.5 34 2.25 28 71 24 47 4.0 162.1 113 3.5 16 4.5 18 4.0 23 100/0.75" Sheet 1 of 1 Client: Project: Start Date:End Date: Drilling Method: BORING NO.: PROJECT NO.: Location: Surface Elevation: West: North: Hammer Drop (lbs / in): De p t h , f e e t Gr a p h i c L o g MATERIAL DESCRIPTION Sa m p l e T y p e Re c o v e r y % RQ D TX C o n e o r S t d . Pe n . ( b l o w s / f t , i n ) Po c k e t Pe n e t r o m e t e r ( t s f ) Un c o n f i n e d C o m p . St r e n g t h ( t s f ) % P a s s i n g No . 2 0 0 S i e v e Un i t D r y W e i g h t (p c f ) Wa t e r C o n t e n t , % Li q u i d L i m i t Pl a s t i c L i m i t Pl a s t i c i t y I n d e x Sw e l l , % GROUND WATER OBSERVATIONS On Rods (ft): After Drilling (ft): After Hours (ft): Starlight Homes Texas, LLC W. Boaz Road Project 12/11/2019 12/11/2019 CONTINUOUS FLIGHT AUGER 17 W193011 Fort Worth, Texas 140 / 30 NONE DRY 5058 Brush Creek Rd. Fort Worth,Texas 76119 Phone:817-496-5600 Fax:817-496-5608 www.alphatesting.com 5 10 15 20 Dark Brown CLAY 2.0 Brown CLAY 4.0 Tan CLAY with calcareous deposits 13.0 Tan SHALY CLAY 15.0 Tan LIMESTONE with clay seam and layers 18.0 Gray LIMESTONE with shale seams 20.0 TEST BORING TERMINATED AT 20 FT 2.0 35 2.5 261.3 98 4.5+13 4.5+17 4.5+15 45 20 25 0.5 4.0 17 42 18 24 100/0.75" Sheet 1 of 1 Client: Project: Start Date:End Date: Drilling Method: BORING NO.: PROJECT NO.: Location: Surface Elevation: West: North: Hammer Drop (lbs / in): De p t h , f e e t Gr a p h i c L o g MATERIAL DESCRIPTION Sa m p l e T y p e Re c o v e r y % RQ D TX C o n e o r S t d . Pe n . ( b l o w s / f t , i n ) Po c k e t Pe n e t r o m e t e r ( t s f ) Un c o n f i n e d C o m p . St r e n g t h ( t s f ) % P a s s i n g No . 2 0 0 S i e v e Un i t D r y W e i g h t (p c f ) Wa t e r C o n t e n t , % Li q u i d L i m i t Pl a s t i c L i m i t Pl a s t i c i t y I n d e x Sw e l l , % GROUND WATER OBSERVATIONS On Rods (ft): After Drilling (ft): After Hours (ft): Starlight Homes Texas, LLC W. Boaz Road Project 12/11/2019 12/11/2019 CONTINUOUS FLIGHT AUGER 22 W193011 Fort Worth, Texas 140 / 30 NONE DRY 5058 Brush Creek Rd. Fort Worth,Texas 76119 Phone:817-496-5600 Fax:817-496-5608 www.alphatesting.com 5 10 15 20 Dark Brown CLAY 6.0 Tan LIMESTONE with clay seam and layers 16.0 Gray LIMESTONE with shale seams 20.0 TEST BORING TERMINATED AT 20 FT 1.5 31 1.5 36 4.0 24 88 28 60 1.3 14 14 9 100/4" 100/0.25" 100/1.25" Sheet 1 of 1 Client: Project: Start Date:End Date: Drilling Method: BORING NO.: PROJECT NO.: Location: Surface Elevation: West: North: Hammer Drop (lbs / in): De p t h , f e e t Gr a p h i c L o g MATERIAL DESCRIPTION Sa m p l e T y p e Re c o v e r y % RQ D TX C o n e o r S t d . Pe n . ( b l o w s / f t , i n ) Po c k e t Pe n e t r o m e t e r ( t s f ) Un c o n f i n e d C o m p . St r e n g t h ( t s f ) % P a s s i n g No . 2 0 0 S i e v e Un i t D r y W e i g h t (p c f ) Wa t e r C o n t e n t , % Li q u i d L i m i t Pl a s t i c L i m i t Pl a s t i c i t y I n d e x Sw e l l , % GROUND WATER OBSERVATIONS On Rods (ft): After Drilling (ft): After Hours (ft): Starlight Homes Texas, LLC W. Boaz Road Project 12/11/2019 12/11/2019 CONTINUOUS FLIGHT AUGER 27 W193011 Fort Worth, Texas 140 / 30 NONE DRY 5058 Brush Creek Rd. Fort Worth,Texas 76119 Phone:817-496-5600 Fax:817-496-5608 www.alphatesting.com 5 10 15 20 Dark Brown CLAY 4.0 Brown CLAY with limestone fragments 5.0 Tan LIMESTONE with clay seam and layers 16.0 Gray LIMESTONE with shale seams 20.0 TEST BORING TERMINATED AT 20 FT 2.0 34 2.75 26 4.5+20 54 20 34 0.3 100/3.5" 100/0.5" 100/0.75" Sheet 1 of 1 Client: Project: Start Date:End Date: Drilling Method: BORING NO.: PROJECT NO.: Location: Surface Elevation: West: North: Hammer Drop (lbs / in): De p t h , f e e t Gr a p h i c L o g MATERIAL DESCRIPTION Sa m p l e T y p e Re c o v e r y % RQ D TX C o n e o r S t d . Pe n . ( b l o w s / f t , i n ) Po c k e t Pe n e t r o m e t e r ( t s f ) Un c o n f i n e d C o m p . St r e n g t h ( t s f ) % P a s s i n g No . 2 0 0 S i e v e Un i t D r y W e i g h t (p c f ) Wa t e r C o n t e n t , % Li q u i d L i m i t Pl a s t i c L i m i t Pl a s t i c i t y I n d e x Sw e l l , % GROUND WATER OBSERVATIONS On Rods (ft): After Drilling (ft): After Hours (ft): Starlight Homes Texas, LLC W. Boaz Road Project 12/11/2019 12/11/2019 CONTINUOUS FLIGHT AUGER 28 W193011 Fort Worth, Texas 140 / 30 9 11 5058 Brush Creek Rd. Fort Worth,Texas 76119 Phone:817-496-5600 Fax:817-496-5608 www.alphatesting.com 5 10 15 20 Dark Brown CLAY 6.0 Tan LIMESTONE with clay seam and layers 13.0 Gray LIMESTONE with shale seams 20.0 TEST BORING TERMINATED AT 20 FT 2.0 34 1.5 33 78 28 50 0.0 2.5 30 100/1.5" 100/1.25" 100/0.25" Sheet 1 of 1 Client: Project: Start Date:End Date: Drilling Method: BORING NO.: PROJECT NO.: Location: Surface Elevation: West: North: Hammer Drop (lbs / in): De p t h , f e e t Gr a p h i c L o g MATERIAL DESCRIPTION Sa m p l e T y p e Re c o v e r y % RQ D TX C o n e o r S t d . Pe n . ( b l o w s / f t , i n ) Po c k e t Pe n e t r o m e t e r ( t s f ) Un c o n f i n e d C o m p . St r e n g t h ( t s f ) % P a s s i n g No . 2 0 0 S i e v e Un i t D r y W e i g h t (p c f ) Wa t e r C o n t e n t , % Li q u i d L i m i t Pl a s t i c L i m i t Pl a s t i c i t y I n d e x Sw e l l , % GROUND WATER OBSERVATIONS On Rods (ft): After Drilling (ft): After Hours (ft): Starlight Homes Texas, LLC W. Boaz Road Project 12/11/2019 12/11/2019 CONTINUOUS FLIGHT AUGER 33 W193011 Fort Worth, Texas 140 / 30 12 DRY 5058 Brush Creek Rd. Fort Worth,Texas 76119 Phone:817-496-5600 Fax:817-496-5608 www.alphatesting.com 5 10 15 20 Dark Brown CLAY 2.0 Brown CLAY 6.0 - with limestone fragments Tan LIMESTONE with clay seam and layers 13.0 Gray LIMESTONE with shale seams 20.0 TEST BORING TERMINATED AT 20 FT 2.0 29 4.5 22 77 27 50 0.1 4.5+17 100/1.25" 100/2" 100/0.75" Sheet 1 of 1 Client: Project: Start Date:End Date: Drilling Method: BORING NO.: PROJECT NO.: Location: Surface Elevation: West: North: Hammer Drop (lbs / in): De p t h , f e e t Gr a p h i c L o g MATERIAL DESCRIPTION Sa m p l e T y p e Re c o v e r y % RQ D TX C o n e o r S t d . Pe n . ( b l o w s / f t , i n ) Po c k e t Pe n e t r o m e t e r ( t s f ) Un c o n f i n e d C o m p . St r e n g t h ( t s f ) % P a s s i n g No . 2 0 0 S i e v e Un i t D r y W e i g h t (p c f ) Wa t e r C o n t e n t , % Li q u i d L i m i t Pl a s t i c L i m i t Pl a s t i c i t y I n d e x Sw e l l , % GROUND WATER OBSERVATIONS On Rods (ft): After Drilling (ft): After Hours (ft): Starlight Homes Texas, LLC W. Boaz Road Project 12/11/2019 12/11/2019 CONTINUOUS FLIGHT AUGER 38 W193011 Fort Worth, Texas 140 / 30 NONE DRY 5058 Brush Creek Rd. Fort Worth,Texas 76119 Phone:817-496-5600 Fax:817-496-5608 www.alphatesting.com 5 10 15 20 Dark Brown CLAY 6.0 - with limestone fragments Tan LIMESTONE with clay seam and layers 14.0 Gray LIMESTONE with shale seams 20.0 TEST BORING TERMINATED AT 20 FT 1.75 31 73 26 47 2.25 31 4.5+20 100/2.75" 100/1.75" 100/0.25" Sheet 1 of 1 Client: Project: Start Date:End Date: Drilling Method: BORING NO.: PROJECT NO.: Location: Surface Elevation: West: North: Hammer Drop (lbs / in): De p t h , f e e t Gr a p h i c L o g MATERIAL DESCRIPTION Sa m p l e T y p e Re c o v e r y % RQ D TX C o n e o r S t d . Pe n . ( b l o w s / f t , i n ) Po c k e t Pe n e t r o m e t e r ( t s f ) Un c o n f i n e d C o m p . St r e n g t h ( t s f ) % P a s s i n g No . 2 0 0 S i e v e Un i t D r y W e i g h t (p c f ) Wa t e r C o n t e n t , % Li q u i d L i m i t Pl a s t i c L i m i t Pl a s t i c i t y I n d e x Sw e l l , % GROUND WATER OBSERVATIONS On Rods (ft): After Drilling (ft): After Hours (ft): Starlight Homes Texas, LLC W. Boaz Road Project 12/9/2019 12/9/2019 CONTINUOUS FLIGHT AUGER 43 W193011 Fort Worth, Texas 140 / 30 NONE DRY 5058 Brush Creek Rd. Fort Worth,Texas 76119 Phone:817-496-5600 Fax:817-496-5608 www.alphatesting.com 5 10 15 20 Brown CLAY 4.0 Tan CLAY with limestone fragments 5.0 Tan LIMESTONE with clay seam and layers 17.0 Gray LIMESTONE with shale seams 20.0 TEST BORING TERMINATED AT 20 FT 2.5 31 3.5 28 4.5+15 38 17 21100/2" 100/0.25" 100/1.25" 100/1" Sheet 1 of 1 Client: Project: Start Date:End Date: Drilling Method: BORING NO.: PROJECT NO.: Location: Surface Elevation: West: North: Hammer Drop (lbs / in): De p t h , f e e t Gr a p h i c L o g MATERIAL DESCRIPTION Sa m p l e T y p e Re c o v e r y % RQ D TX C o n e o r S t d . Pe n . ( b l o w s / f t , i n ) Po c k e t Pe n e t r o m e t e r ( t s f ) Un c o n f i n e d C o m p . St r e n g t h ( t s f ) % P a s s i n g No . 2 0 0 S i e v e Un i t D r y W e i g h t (p c f ) Wa t e r C o n t e n t , % Li q u i d L i m i t Pl a s t i c L i m i t Pl a s t i c i t y I n d e x Sw e l l , % GROUND WATER OBSERVATIONS On Rods (ft): After Drilling (ft): After Hours (ft): Starlight Homes Texas, LLC W. Boaz Road Project 12/11/2019 12/11/2019 CONTINUOUS FLIGHT AUGER 44 W193011 Fort Worth, Texas 140 / 30 NONE DRY 5058 Brush Creek Rd. Fort Worth,Texas 76119 Phone:817-496-5600 Fax:817-496-5608 www.alphatesting.com 5 10 15 20 Dark Brown CLAY 6.0 - with limestone fragments from 2 ft to 6 ft Tan LIMESTONE with clay seam and layers 14.0 Gray LIMESTONE with shale seams 20.0 TEST BORING TERMINATED AT 20 FT 2.5 32 2.5 31 4.5+24 84 25 59 1.6 17 100/2" 100/1.75" 100/0.5" Sheet 1 of 1 Client: Project: Start Date:End Date: Drilling Method: BORING NO.: PROJECT NO.: Location: Surface Elevation: West: North: Hammer Drop (lbs / in): De p t h , f e e t Gr a p h i c L o g MATERIAL DESCRIPTION Sa m p l e T y p e Re c o v e r y % RQ D TX C o n e o r S t d . Pe n . ( b l o w s / f t , i n ) Po c k e t Pe n e t r o m e t e r ( t s f ) Un c o n f i n e d C o m p . St r e n g t h ( t s f ) % P a s s i n g No . 2 0 0 S i e v e Un i t D r y W e i g h t (p c f ) Wa t e r C o n t e n t , % Li q u i d L i m i t Pl a s t i c L i m i t Pl a s t i c i t y I n d e x Sw e l l , % GROUND WATER OBSERVATIONS On Rods (ft): After Drilling (ft): After Hours (ft): Starlight Homes Texas, LLC W. Boaz Road Project 12/9/2019 12/9/2019 CONTINUOUS FLIGHT AUGER 46 W193011 Fort Worth, Texas 140 / 30 NONE DRY 5058 Brush Creek Rd. Fort Worth,Texas 76119 Phone:817-496-5600 Fax:817-496-5608 www.alphatesting.com 5 10 15 20 Brown CLAY 4.0 Tan CLAY with limestone fragments 5.0 Tan LIMESTONE with clay seam and layers 17.0 Gray LIMESTONE with shale seams 20.0 TEST BORING TERMINATED AT 20 FT 2.5 32 3.0 26 67 22 45 0.5 4.5+13 100/0.25" 100/1.25" 100/6" 100/0.75" Sheet 1 of 1 Client: Project: Start Date:End Date: Drilling Method: BORING NO.: PROJECT NO.: Location: Surface Elevation: West: North: Hammer Drop (lbs / in): De p t h , f e e t Gr a p h i c L o g MATERIAL DESCRIPTION Sa m p l e T y p e Re c o v e r y % RQ D TX C o n e o r S t d . Pe n . ( b l o w s / f t , i n ) Po c k e t Pe n e t r o m e t e r ( t s f ) Un c o n f i n e d C o m p . St r e n g t h ( t s f ) % P a s s i n g No . 2 0 0 S i e v e Un i t D r y W e i g h t (p c f ) Wa t e r C o n t e n t , % Li q u i d L i m i t Pl a s t i c L i m i t Pl a s t i c i t y I n d e x Sw e l l , % GROUND WATER OBSERVATIONS On Rods (ft): After Drilling (ft): After Hours (ft): Starlight Homes Texas, LLC W. Boaz Road Project 12/9/2019 12/9/2019 CONTINUOUS FLIGHT AUGER 50 W193011 Fort Worth, Texas 140 / 30 NONE DRY 5058 Brush Creek Rd. Fort Worth,Texas 76119 Phone:817-496-5600 Fax:817-496-5608 www.alphatesting.com 5 10 15 20 Brown CLAY with limestone fragments 4.0 Tan CLAY with limestone fragments 6.0 Tan LIMESTONE with clay seam and layers 17.0 Gray LIMESTONE with shale seams 20.0 TEST BORING TERMINATED AT 20 FT 2.25 31 3.25 271.7 96 4.5 17 54 18 36 4.9 7 7 10 7 100/1.5" 100/5" 100/1" Sheet 1 of 1 Client: Project: Start Date:End Date: Drilling Method: BORING NO.: PROJECT NO.: Location: Surface Elevation: West: North: Hammer Drop (lbs / in): De p t h , f e e t Gr a p h i c L o g MATERIAL DESCRIPTION Sa m p l e T y p e Re c o v e r y % RQ D TX C o n e o r S t d . Pe n . ( b l o w s / f t , i n ) Po c k e t Pe n e t r o m e t e r ( t s f ) Un c o n f i n e d C o m p . St r e n g t h ( t s f ) % P a s s i n g No . 2 0 0 S i e v e Un i t D r y W e i g h t (p c f ) Wa t e r C o n t e n t , % Li q u i d L i m i t Pl a s t i c L i m i t Pl a s t i c i t y I n d e x Sw e l l , % GROUND WATER OBSERVATIONS On Rods (ft): After Drilling (ft): After Hours (ft): Starlight Homes Texas, LLC W. Boaz Road Project 12/9/2019 12/9/2019 CONTINUOUS FLIGHT AUGER 51 W193011 Fort Worth, Texas 140 / 30 NONE DRY 5058 Brush Creek Rd. Fort Worth,Texas 76119 Phone:817-496-5600 Fax:817-496-5608 www.alphatesting.com 5 10 15 20 Dark Brown CLAY 5.0 - with limestone fragments from 2 ft to 5 ft Tan LIMESTONE with clay seam and layers 14.0 Gray LIMESTONE with shale seams 20.0 TEST BORING TERMINATED AT 20 FT 2.25 29 72 26 46 2.75 28 4.5+21 6 8 17 10 100/0.5" 100/2.25" 100/3.5" 100/1.5" Sheet 1 of 1 Client: Project: Start Date:End Date: Drilling Method: BORING NO.: PROJECT NO.: Location: Surface Elevation: West: North: Hammer Drop (lbs / in): De p t h , f e e t Gr a p h i c L o g MATERIAL DESCRIPTION Sa m p l e T y p e Re c o v e r y % RQ D TX C o n e o r S t d . Pe n . ( b l o w s / f t , i n ) Po c k e t Pe n e t r o m e t e r ( t s f ) Un c o n f i n e d C o m p . St r e n g t h ( t s f ) % P a s s i n g No . 2 0 0 S i e v e Un i t D r y W e i g h t (p c f ) Wa t e r C o n t e n t , % Li q u i d L i m i t Pl a s t i c L i m i t Pl a s t i c i t y I n d e x Sw e l l , % GROUND WATER OBSERVATIONS On Rods (ft): After Drilling (ft): After Hours (ft): Starlight Homes Texas, LLC Ranch at Duck Creek - Phase 2 8/4/2021 8/4/2021 CONTINUOUS FLIGHT AUGER 1 W212004 Fort Worth, Texas 170 / 24 NONE DRY 5058 Brush Creek Rd. Fort Worth,Texas 76119 Phone:817-496-5600 Fax:817-496-5608 www.alphatesting.com 5 10 15 20 25 30 35 40 45 50 Dark Brown CLAY with limestone fragments 2.0 Brown and Tan CLAY with limestone fragments and calcareous deposits 5.0 Tan LIMESTONE with clay seams and layers 13.0 Tan CLAY 16.0 Gray SHALE 20.0 TEST BORING TERMINATED AT 20 FT 1.5 28 74 23 51 0.7 4.5+11 41 19 22 4.25 17 4.5+21 4.5+18 100/1.0" 100/0.50" Sheet 1 of 1 Client: Project: Start Date:End Date: Drilling Method: BORING NO.: PROJECT NO.: Location: Surface Elevation: West: North: Hammer Drop (lbs / in): De p t h , f e e t Gr a p h i c L o g MATERIAL DESCRIPTION Sa m p l e T y p e Re c o v e r y % RQ D TX C o n e o r S t d . Pe n . ( b l o w s / f t , i n ) Po c k e t Pe n e t r o m e t e r ( t s f ) Un c o n f i n e d C o m p . St r e n g t h ( t s f ) % P a s s i n g No . 2 0 0 S i e v e Un i t D r y W e i g h t (p c f ) Wa t e r C o n t e n t , % Li q u i d L i m i t Pl a s t i c L i m i t Pl a s t i c i t y I n d e x Sw e l l , % GROUND WATER OBSERVATIONS On Rods (ft): After Drilling (ft): After Hours (ft): Starlight Homes Texas, LLC Ranch at Duck Creek - Phase 2 8/4/2021 8/4/2021 CONTINUOUS FLIGHT AUGER 2 W212004 Fort Worth, Texas 170 / 24 NONE DRY 5058 Brush Creek Rd. Fort Worth,Texas 76119 Phone:817-496-5600 Fax:817-496-5608 www.alphatesting.com 5 10 15 20 25 30 35 40 45 50 Dark Brown CLAY 2.0 Tan LIMESTONE with clay seams and layers 12.0 Tan and Gray CLAY 18.0 Gray SHALE 20.0 TEST BORING TERMINATED AT 20 FT 2.0 32 13 2.75 23 63 19 44 0.4 4.5+13 33 100/7.25" 31 Sheet 1 of 1 Client: Project: Start Date:End Date: Drilling Method: BORING NO.: PROJECT NO.: Location: Surface Elevation: West: North: Hammer Drop (lbs / in): De p t h , f e e t Gr a p h i c L o g MATERIAL DESCRIPTION Sa m p l e T y p e Re c o v e r y % RQ D TX C o n e o r S t d . Pe n . ( b l o w s / f t , i n ) Po c k e t Pe n e t r o m e t e r ( t s f ) Un c o n f i n e d C o m p . St r e n g t h ( t s f ) % P a s s i n g No . 2 0 0 S i e v e Un i t D r y W e i g h t (p c f ) Wa t e r C o n t e n t , % Li q u i d L i m i t Pl a s t i c L i m i t Pl a s t i c i t y I n d e x Sw e l l , % GROUND WATER OBSERVATIONS On Rods (ft): After Drilling (ft): After Hours (ft): Starlight Homes Texas, LLC Ranch at Duck Creek - Phase 2 8/4/2021 8/4/2021 CONTINUOUS FLIGHT AUGER 3 W212004 Fort Worth, Texas 170 / 24 NONE DRY 5058 Brush Creek Rd. Fort Worth,Texas 76119 Phone:817-496-5600 Fax:817-496-5608 www.alphatesting.com 5 10 15 20 25 30 35 40 45 50 Dark Brown CLAY with limestone fragments 2.0 Brown CLAY with limestone fragments and calcareous deposits 6.0 Tan CLAY with limestone fragments and calcareous deposits 13.0 Tan and Gray CLAY 20.0 TEST BORING TERMINATED AT 20 FT 2.0 30 4.5+18 4.5+16 4.5+13 34 16 18 0.3 4.5 15 4.0 29 4.5+22 69 25 44 Sheet 1 of 1 Client: Project: Start Date:End Date: Drilling Method: BORING NO.: PROJECT NO.: Location: Surface Elevation: West: North: Hammer Drop (lbs / in): De p t h , f e e t Gr a p h i c L o g MATERIAL DESCRIPTION Sa m p l e T y p e Re c o v e r y % RQ D TX C o n e o r S t d . Pe n . ( b l o w s / f t , i n ) Po c k e t Pe n e t r o m e t e r ( t s f ) Un c o n f i n e d C o m p . St r e n g t h ( t s f ) % P a s s i n g No . 2 0 0 S i e v e Un i t D r y W e i g h t (p c f ) Wa t e r C o n t e n t , % Li q u i d L i m i t Pl a s t i c L i m i t Pl a s t i c i t y I n d e x Sw e l l , % GROUND WATER OBSERVATIONS On Rods (ft): After Drilling (ft): After Hours (ft): Starlight Homes Texas, LLC Ranch at Duck Creek - Phase 2 8/4/2021 8/4/2021 CONTINUOUS FLIGHT AUGER 4 W212004 Fort Worth, Texas 170 / 24 NONE DRY 5058 Brush Creek Rd. Fort Worth,Texas 76119 Phone:817-496-5600 Fax:817-496-5608 www.alphatesting.com 5 10 15 20 25 30 35 40 45 50 Dark Brown CLAY with limestone fragments 2.0 Brown CLAY with limestone fragments 4.0 Tan CLAY with calcareous deposits 5.0 Tan LIMESTONE with clay seams and layers 18.0 Tan and Gray CLAY 20.0 TEST BORING TERMINATED AT 20 FT 3.5 284.4 96 4.5+6 52 19 33 4.5+15 16 4.5+20 100/2.0" 68 100/5.25" Sheet 1 of 1 Client: Project: Start Date:End Date: Drilling Method: BORING NO.: PROJECT NO.: Location: Surface Elevation: West: North: Hammer Drop (lbs / in): De p t h , f e e t Gr a p h i c L o g MATERIAL DESCRIPTION Sa m p l e T y p e Re c o v e r y % RQ D TX C o n e o r S t d . Pe n . ( b l o w s / f t , i n ) Po c k e t Pe n e t r o m e t e r ( t s f ) Un c o n f i n e d C o m p . St r e n g t h ( t s f ) % P a s s i n g No . 2 0 0 S i e v e Un i t D r y W e i g h t (p c f ) Wa t e r C o n t e n t , % Li q u i d L i m i t Pl a s t i c L i m i t Pl a s t i c i t y I n d e x Sw e l l , % GROUND WATER OBSERVATIONS On Rods (ft): After Drilling (ft): After Hours (ft): Starlight Homes Texas, LLC Ranch at Duck Creek - Phase 2 8/4/2021 8/4/2021 CONTINUOUS FLIGHT AUGER 5 W212004 Fort Worth, Texas 170 / 24 NONE DRY 5058 Brush Creek Rd. Fort Worth,Texas 76119 Phone:817-496-5600 Fax:817-496-5608 www.alphatesting.com 5 10 15 20 25 30 35 40 45 50 Dark Brown CLAY 2.0 Tan LIMESTONE 3.0 Brown CLAY with limestone fragments and calcareous deposits 4.0 Tan CLAY with limestone fragments and calcareous deposits 6.0 Tan LIMESTONE with clay seams and layers 12.0 Tan and Gray CLAY with limestone fragments 19.0 Gray SHALE 20.0 TEST BORING TERMINATED AT 20 FT 4.5 32 83 26 57 4.3 4.5+12 4.5+15 4.5+18 43 100/2.0" 41 Sheet 1 of 1 Client: Project: Start Date:End Date: Drilling Method: BORING NO.: PROJECT NO.: Location: Surface Elevation: West: North: Hammer Drop (lbs / in): De p t h , f e e t Gr a p h i c L o g MATERIAL DESCRIPTION Sa m p l e T y p e Re c o v e r y % RQ D TX C o n e o r S t d . Pe n . ( b l o w s / f t , i n ) Po c k e t Pe n e t r o m e t e r ( t s f ) Un c o n f i n e d C o m p . St r e n g t h ( t s f ) % P a s s i n g No . 2 0 0 S i e v e Un i t D r y W e i g h t (p c f ) Wa t e r C o n t e n t , % Li q u i d L i m i t Pl a s t i c L i m i t Pl a s t i c i t y I n d e x Sw e l l , % GROUND WATER OBSERVATIONS On Rods (ft): After Drilling (ft): After Hours (ft): Starlight Homes Texas, LLC Ranch at Duck Creek - Phase 2 8/4/2021 8/4/2021 CONTINUOUS FLIGHT AUGER 6 W212004 Fort Worth, Texas 170 / 24 NONE DRY 5058 Brush Creek Rd. Fort Worth,Texas 76119 Phone:817-496-5600 Fax:817-496-5608 www.alphatesting.com 5 10 15 20 25 30 35 40 45 50 Dark Brown CLAY 4.0 Brown CLAY with limestone fragments 6.0 Light Brown CLAY with calcareous deposits and limestone fragments 8.0 Tan CLAY with calcareous deposits 13.0 Tan and Gray CLAY with limestone fragments 17.0 Tan LIMESTONE with clay seams and layers 20.0 TEST BORING TERMINATED AT 20 FT 2.5 30 4.5 26 3.0 23 3.0 23 61 20 41 0.4 2.5 14 2.5 27 100/0.50" Sheet 1 of 1 Client: Project: Start Date:End Date: Drilling Method: BORING NO.: PROJECT NO.: Location: Surface Elevation: West: North: Hammer Drop (lbs / in): De p t h , f e e t Gr a p h i c L o g MATERIAL DESCRIPTION Sa m p l e T y p e Re c o v e r y % RQ D TX C o n e o r S t d . Pe n . ( b l o w s / f t , i n ) Po c k e t Pe n e t r o m e t e r ( t s f ) Un c o n f i n e d C o m p . St r e n g t h ( t s f ) % P a s s i n g No . 2 0 0 S i e v e Un i t D r y W e i g h t (p c f ) Wa t e r C o n t e n t , % Li q u i d L i m i t Pl a s t i c L i m i t Pl a s t i c i t y I n d e x Sw e l l , % GROUND WATER OBSERVATIONS On Rods (ft): After Drilling (ft): After Hours (ft): Starlight Homes Texas, LLC Ranch at Duck Creek - Phase 2 8/3/2021 8/3/2021 CONTINUOUS FLIGHT AUGER 7 W212004 Fort Worth, Texas 170 / 24 NONE DRY 5058 Brush Creek Rd. Fort Worth,Texas 76119 Phone:817-496-5600 Fax:817-496-5608 www.alphatesting.com 5 10 15 20 25 30 35 40 45 50 Brown CLAY 2.0 Reddish Brown CLAY with limestone fragments and calcareous deposits 4.0 Tan CLAY 8.0 - with limestone layer at 5' to 6' Tan LIMESTONE with clay seams and layers 13.0 Tan and Gray CLAY 20.0 - with calcareous deposits and limestone fragments at 18' to 20 ' TEST BORING TERMINATED AT 20 FT 4.5 25 4.5+10 54 21 33 2.0 15 4.5+21 4.5+19 100/6.50" 50/5.0" Sheet 1 of 1 Client: Project: Start Date:End Date: Drilling Method: BORING NO.: PROJECT NO.: Location: Surface Elevation: West: North: Hammer Drop (lbs / in): De p t h , f e e t Gr a p h i c L o g MATERIAL DESCRIPTION Sa m p l e T y p e Re c o v e r y % RQ D TX C o n e o r S t d . Pe n . ( b l o w s / f t , i n ) Po c k e t Pe n e t r o m e t e r ( t s f ) Un c o n f i n e d C o m p . St r e n g t h ( t s f ) % P a s s i n g No . 2 0 0 S i e v e Un i t D r y W e i g h t (p c f ) Wa t e r C o n t e n t , % Li q u i d L i m i t Pl a s t i c L i m i t Pl a s t i c i t y I n d e x Sw e l l , % GROUND WATER OBSERVATIONS On Rods (ft): After Drilling (ft): After Hours (ft): Starlight Homes Texas, LLC Ranch at Duck Creek - Phase 2 8/4/2021 8/4/2021 CONTINUOUS FLIGHT AUGER 8 W212004 Fort Worth, Texas 170 / 24 NONE DRY 5058 Brush Creek Rd. Fort Worth,Texas 76119 Phone:817-496-5600 Fax:817-496-5608 www.alphatesting.com 5 10 15 20 25 30 35 40 45 50 Brown CLAY with limestone fragments and calcareous deposits 2.0 Light Brown CLAY with rocks, limestone fragments and calcareous deposits 6.0 Tan LIMESTONE with clay seams and layers 13.0 Tan and Gray CLAY with limestone fragments 18.0 Tan LIMESTONE with clay seams and layers 20.0 TEST BORING TERMINATED AT 20 FT 2.0 28 71 23 48 0.7 4.5+13 4.5+13 4.0 25 100/0.75" 57 100/0.75" Sheet 1 of 1 Client: Project: Start Date:End Date: Drilling Method: BORING NO.: PROJECT NO.: Location: Surface Elevation: West: North: Hammer Drop (lbs / in): De p t h , f e e t Gr a p h i c L o g MATERIAL DESCRIPTION Sa m p l e T y p e Re c o v e r y % RQ D TX C o n e o r S t d . Pe n . ( b l o w s / f t , i n ) Po c k e t Pe n e t r o m e t e r ( t s f ) Un c o n f i n e d C o m p . St r e n g t h ( t s f ) % P a s s i n g No . 2 0 0 S i e v e Un i t D r y W e i g h t (p c f ) Wa t e r C o n t e n t , % Li q u i d L i m i t Pl a s t i c L i m i t Pl a s t i c i t y I n d e x Sw e l l , % GROUND WATER OBSERVATIONS On Rods (ft): After Drilling (ft): After Hours (ft): Starlight Homes Texas, LLC Ranch at Duck Creek - Phase 2 8/4/2021 8/4/2021 CONTINUOUS FLIGHT AUGER 9 W212004 Fort Worth, Texas 170 / 24 NONE DRY 5058 Brush Creek Rd. Fort Worth,Texas 76119 Phone:817-496-5600 Fax:817-496-5608 www.alphatesting.com 5 10 15 20 25 30 35 40 45 50 Dark Brown CLAY 2.0 Dark Brown and Brown CLAY with rocks and limestone fragments 4.0 Tan CLAY with limestone fragments and calcareous deposits 8.0 Tan and Gray CLAY 16.0 Tan LIMESTONE with clay seams and layers 20.0 TEST BORING TERMINATED AT 20 FT 3.0 30 4.5+21 71 23 48 4.5+12 36 16 20 0.1 4.5+15 4.5+18 4.5+16 8100/0.75" Sheet 1 of 1 Client: Project: Start Date:End Date: Drilling Method: BORING NO.: PROJECT NO.: Location: Surface Elevation: West: North: Hammer Drop (lbs / in): De p t h , f e e t Gr a p h i c L o g MATERIAL DESCRIPTION Sa m p l e T y p e Re c o v e r y % RQ D TX C o n e o r S t d . Pe n . ( b l o w s / f t , i n ) Po c k e t Pe n e t r o m e t e r ( t s f ) Un c o n f i n e d C o m p . St r e n g t h ( t s f ) % P a s s i n g No . 2 0 0 S i e v e Un i t D r y W e i g h t (p c f ) Wa t e r C o n t e n t , % Li q u i d L i m i t Pl a s t i c L i m i t Pl a s t i c i t y I n d e x Sw e l l , % GROUND WATER OBSERVATIONS On Rods (ft): After Drilling (ft): After Hours (ft): Starlight Homes Texas, LLC Ranch at Duck Creek - Phase 2 8/3/2021 8/3/2021 CONTINUOUS FLIGHT AUGER 10 W212004 Fort Worth, Texas 170 / 24 NONE DRY 5058 Brush Creek Rd. Fort Worth,Texas 76119 Phone:817-496-5600 Fax:817-496-5608 www.alphatesting.com 5 10 15 20 25 30 35 40 45 50 Brown CLAY with limestone fragments 2.0 Light Brown CLAY with limestone fragments and calcareous deposits 4.0 Tan CLAY with calcareous deposits 5.0 Tan LIMESTONE with clay seams and layers 13.0 Tan and Gray CLAY with limestone fragments 20.0 TEST BORING TERMINATED AT 20 FT 3.5 28 4.5+13 51 20 31 4.5+18 4.5+23 4.5+16 50 17 33 50/3.0" 100/4.50" Sheet 1 of 1 Client: Project: Start Date:End Date: Drilling Method: BORING NO.: PROJECT NO.: Location: Surface Elevation: West: North: Hammer Drop (lbs / in): De p t h , f e e t Gr a p h i c L o g MATERIAL DESCRIPTION Sa m p l e T y p e Re c o v e r y % RQ D TX C o n e o r S t d . Pe n . ( b l o w s / f t , i n ) Po c k e t Pe n e t r o m e t e r ( t s f ) Un c o n f i n e d C o m p . St r e n g t h ( t s f ) % P a s s i n g No . 2 0 0 S i e v e Un i t D r y W e i g h t (p c f ) Wa t e r C o n t e n t , % Li q u i d L i m i t Pl a s t i c L i m i t Pl a s t i c i t y I n d e x Sw e l l , % GROUND WATER OBSERVATIONS On Rods (ft): After Drilling (ft): After Hours (ft): Starlight Homes Texas, LLC Ranch at Duck Creek - Phase 2 8/4/2021 8/4/2021 CONTINUOUS FLIGHT AUGER 11 W212004 Fort Worth, Texas 170 / 24 NONE DRY 5058 Brush Creek Rd. Fort Worth,Texas 76119 Phone:817-496-5600 Fax:817-496-5608 www.alphatesting.com 5 10 15 20 25 30 35 40 45 50 Brown CLAY with limestone fragments and calcareous deposits 2.0 Light Brown CLAY with limestone fragments and calcareous deposits 4.0 Tan CLAY with calcareous deposits 5.0 Tan LIMESTONE with clay seams and layers 8.0 Tan CLAY with limestone fragments 15.0 Tan LIMESTONE with clay seams and layers 20.0 TEST BORING TERMINATED AT 20 FT 3.0 25 4.5+12 4.5+15 3.0 22 65 20 45 0.7 4.5+23 15 100/4.75" 100/0.75" Sheet 1 of 1 Client: Project: Start Date:End Date: Drilling Method: BORING NO.: PROJECT NO.: Location: Surface Elevation: West: North: Hammer Drop (lbs / in): De p t h , f e e t Gr a p h i c L o g MATERIAL DESCRIPTION Sa m p l e T y p e Re c o v e r y % RQ D TX C o n e o r S t d . Pe n . ( b l o w s / f t , i n ) Po c k e t Pe n e t r o m e t e r ( t s f ) Un c o n f i n e d C o m p . St r e n g t h ( t s f ) % P a s s i n g No . 2 0 0 S i e v e Un i t D r y W e i g h t (p c f ) Wa t e r C o n t e n t , % Li q u i d L i m i t Pl a s t i c L i m i t Pl a s t i c i t y I n d e x Sw e l l , % GROUND WATER OBSERVATIONS On Rods (ft): After Drilling (ft): After Hours (ft): Starlight Homes Texas, LLC Ranch at Duck Creek - Phase 2 8/4/2021 8/4/2021 CONTINUOUS FLIGHT AUGER 12 W212004 Fort Worth, Texas 170 / 24 NONE DRY 5058 Brush Creek Rd. Fort Worth,Texas 76119 Phone:817-496-5600 Fax:817-496-5608 www.alphatesting.com 5 10 15 20 25 30 35 40 45 50 Dark Brown CLAY with limestone fragments 6.0 Brown CLAY with limestone fragments and calcareous deposits 8.0 Tan CLAY with calcareous deposits and limestone fragments 14.0 Tan LIMESTONE with clay seams and layers 18.0 Gray LIMESTONE with shale seams 20.0 TEST BORING TERMINATED AT 20 FT 2.5 30 4.5+24 4.25 20 80 24 56 0.4 4.0 17 48 15 33 0.3 3.0 16 4.5+22 100/0.25" 100/0.75" Sheet 1 of 1 Client: Project: Start Date:End Date: Drilling Method: BORING NO.: PROJECT NO.: Location: Surface Elevation: West: North: Hammer Drop (lbs / in): De p t h , f e e t Gr a p h i c L o g MATERIAL DESCRIPTION Sa m p l e T y p e Re c o v e r y % RQ D TX C o n e o r S t d . Pe n . ( b l o w s / f t , i n ) Po c k e t Pe n e t r o m e t e r ( t s f ) Un c o n f i n e d C o m p . St r e n g t h ( t s f ) % P a s s i n g No . 2 0 0 S i e v e Un i t D r y W e i g h t (p c f ) Wa t e r C o n t e n t , % Li q u i d L i m i t Pl a s t i c L i m i t Pl a s t i c i t y I n d e x Sw e l l , % GROUND WATER OBSERVATIONS On Rods (ft): After Drilling (ft): After Hours (ft): Starlight Homes Texas, LLC Ranch at Duck Creek - Phase 2 8/3/2021 8/3/2021 CONTINUOUS FLIGHT AUGER 13 W212004 Fort Worth, Texas 170 / 24 NONE DRY 5058 Brush Creek Rd. Fort Worth,Texas 76119 Phone:817-496-5600 Fax:817-496-5608 www.alphatesting.com 5 10 15 20 25 30 35 40 45 50 Dark Brown CLAY 2.0 Brown CLAY with calcareous deposits and limestone fragments 4.0 Tan CLAY with limestone fragments 5.0 Tan LIMESTONE with clay seams and layers 18.0 Tan and Gray SHALY CLAY 20.0 TEST BORING TERMINATED AT 20 FT 3.0 31 4.5+19 4.5+12 4.5+22 58 22 36 100/2.50" 100/1" 100/2.75" Sheet 1 of 1 Client: Project: Start Date:End Date: Drilling Method: BORING NO.: PROJECT NO.: Location: Surface Elevation: West: North: Hammer Drop (lbs / in): De p t h , f e e t Gr a p h i c L o g MATERIAL DESCRIPTION Sa m p l e T y p e Re c o v e r y % RQ D TX C o n e o r S t d . Pe n . ( b l o w s / f t , i n ) Po c k e t Pe n e t r o m e t e r ( t s f ) Un c o n f i n e d C o m p . St r e n g t h ( t s f ) % P a s s i n g No . 2 0 0 S i e v e Un i t D r y W e i g h t (p c f ) Wa t e r C o n t e n t , % Li q u i d L i m i t Pl a s t i c L i m i t Pl a s t i c i t y I n d e x Sw e l l , % GROUND WATER OBSERVATIONS On Rods (ft): After Drilling (ft): After Hours (ft): Starlight Homes Texas, LLC Ranch at Duck Creek - Phase 2 8/3/2021 8/3/2021 CONTINUOUS FLIGHT AUGER 14 W212004 Fort Worth, Texas 170 / 24 NONE DRY 5058 Brush Creek Rd. Fort Worth,Texas 76119 Phone:817-496-5600 Fax:817-496-5608 www.alphatesting.com 5 10 15 20 25 30 35 40 45 50 Dark Brown CLAY with limestone fragments 2.0 Brown CLAY with limestone fragments 4.0 Tan CLAY with calcareous deposits 13.0 Tan LIMESTONE with clay seams and layers 20.0 TEST BORING TERMINATED AT 20 FT 2.5 30 4.5+17 4.5+12 2.0 19 27 13 14 0.0 19 85 100/0.5" Sheet 1 of 1 Client: Project: Start Date:End Date: Drilling Method: BORING NO.: PROJECT NO.: Location: Surface Elevation: West: North: Hammer Drop (lbs / in): De p t h , f e e t Gr a p h i c L o g MATERIAL DESCRIPTION Sa m p l e T y p e Re c o v e r y % RQ D TX C o n e o r S t d . Pe n . ( b l o w s / f t , i n ) Po c k e t Pe n e t r o m e t e r ( t s f ) Un c o n f i n e d C o m p . St r e n g t h ( t s f ) % P a s s i n g No . 2 0 0 S i e v e Un i t D r y W e i g h t (p c f ) Wa t e r C o n t e n t , % Li q u i d L i m i t Pl a s t i c L i m i t Pl a s t i c i t y I n d e x Sw e l l , % GROUND WATER OBSERVATIONS On Rods (ft): After Drilling (ft): After Hours (ft): Starlight Homes Texas, LLC Ranch at Duck Creek - Phase 2 8/3/2021 8/3/2021 CONTINUOUS FLIGHT AUGER 15 W212004 Fort Worth, Texas 170 / 24 NONE DRY 5058 Brush Creek Rd. Fort Worth,Texas 76119 Phone:817-496-5600 Fax:817-496-5608 www.alphatesting.com 5 10 15 20 25 30 35 40 45 50 Dark Brown CLAY with limestone fragments 4.0 Brown CLAY with calcareous deposits and limestone fragments 6.0 Tan CLAY with calcareous deposits 12.0 Tan LIMESTONE with clay seams and layers 16.0 Gray LIMESTONE with shale seams 20.0 TEST BORING TERMINATED AT 20 FT 3.0 29 82 26 56 0.9 4.5+21 3.5 17 4.5+14 38 15 23 0.7 4.5+18 100/0.50" 100/0.75" Sheet 1 of 1 Client: Project: Start Date:End Date: Drilling Method: BORING NO.: PROJECT NO.: Location: Surface Elevation: West: North: Hammer Drop (lbs / in): De p t h , f e e t Gr a p h i c L o g MATERIAL DESCRIPTION Sa m p l e T y p e Re c o v e r y % RQ D TX C o n e o r S t d . Pe n . ( b l o w s / f t , i n ) Po c k e t Pe n e t r o m e t e r ( t s f ) Un c o n f i n e d C o m p . St r e n g t h ( t s f ) % P a s s i n g No . 2 0 0 S i e v e Un i t D r y W e i g h t (p c f ) Wa t e r C o n t e n t , % Li q u i d L i m i t Pl a s t i c L i m i t Pl a s t i c i t y I n d e x Sw e l l , % GROUND WATER OBSERVATIONS On Rods (ft): After Drilling (ft): After Hours (ft): Starlight Homes Texas, LLC Ranch at Duck Creek - Phase 2 7/30/2021 7/30/2021 CONTINUOUS FLIGHT AUGER 16 W212004 Fort Worth, Texas 170 / 24 NONE DRY 5058 Brush Creek Rd. Fort Worth,Texas 76119 Phone:817-496-5600 Fax:817-496-5608 www.alphatesting.com 5 10 15 20 25 30 35 40 45 50 Brown CLAY with limestone fragments and calcareous deposits 4.0 Tan CLAY with calcareous deposits 18.0 Tan LIMESTONE with clay seams and layers 20.0 TEST BORING TERMINATED AT 20 FT 4.5+20 4.5+20 4.5+14 3.0 16 4.5+20 4.5+16 49 17 32 100/0.25" Sheet 1 of 1 Client: Project: Start Date:End Date: Drilling Method: BORING NO.: PROJECT NO.: Location: Surface Elevation: West: North: Hammer Drop (lbs / in): De p t h , f e e t Gr a p h i c L o g MATERIAL DESCRIPTION Sa m p l e T y p e Re c o v e r y % RQ D TX C o n e o r S t d . Pe n . ( b l o w s / f t , i n ) Po c k e t Pe n e t r o m e t e r ( t s f ) Un c o n f i n e d C o m p . St r e n g t h ( t s f ) % P a s s i n g No . 2 0 0 S i e v e Un i t D r y W e i g h t (p c f ) Wa t e r C o n t e n t , % Li q u i d L i m i t Pl a s t i c L i m i t Pl a s t i c i t y I n d e x Sw e l l , % GROUND WATER OBSERVATIONS On Rods (ft): After Drilling (ft): After Hours (ft): Starlight Homes Texas, LLC Ranch at Duck Creek - Phase 2 7/30/2021 7/30/2021 CONTINUOUS FLIGHT AUGER 17 W212004 Fort Worth, Texas 170 / 24 NONE DRY 5058 Brush Creek Rd. Fort Worth,Texas 76119 Phone:817-496-5600 Fax:817-496-5608 www.alphatesting.com 5 10 15 20 25 30 35 40 45 50 Dark Brown CLAY 2.0 Brown CLAY with limestone fragments and calcareous deposits 4.0 Tan CLAY with calcareous deposits 13.0 Tan and Gray SHALY CLAY 16.0 Tan LIMESTONE with clay seams and layers 20.0 TEST BORING TERMINATED AT 20 FT 4.5+23 4.5+19 73 25 48 4.5+14 4.0 16 3.0 21 4.5+19 100/0.75" Sheet 1 of 1 Client: Project: Start Date:End Date: Drilling Method: BORING NO.: PROJECT NO.: Location: Surface Elevation: West: North: Hammer Drop (lbs / in): De p t h , f e e t Gr a p h i c L o g MATERIAL DESCRIPTION Sa m p l e T y p e Re c o v e r y % RQ D TX C o n e o r S t d . Pe n . ( b l o w s / f t , i n ) Po c k e t Pe n e t r o m e t e r ( t s f ) Un c o n f i n e d C o m p . St r e n g t h ( t s f ) % P a s s i n g No . 2 0 0 S i e v e Un i t D r y W e i g h t (p c f ) Wa t e r C o n t e n t , % Li q u i d L i m i t Pl a s t i c L i m i t Pl a s t i c i t y I n d e x Sw e l l , % GROUND WATER OBSERVATIONS On Rods (ft): After Drilling (ft): After Hours (ft): Starlight Homes Texas, LLC Ranch at Duck Creek - Phase 2 8/3/2021 8/3/2021 CONTINUOUS FLIGHT AUGER 18 W212004 Fort Worth, Texas 170 / 24 NONE DRY 5058 Brush Creek Rd. Fort Worth,Texas 76119 Phone:817-496-5600 Fax:817-496-5608 www.alphatesting.com 5 10 15 20 25 30 35 40 45 50 Dark Brown CLAY with limestone fragments 4.0 Brown CLAY with calcareous deposits 6.0 Tan CLAY 10.0 - with calcareous deposits at 6' to 8' Tan LIMESTONE with clay seams and layers 16.0 Gray LIMESTONE with shale seams 20.0 TEST BORING TERMINATED AT 20 FT 2.0 342.2 86 77 27 50 0.1 4.5+21 73 24 49 4.5+14 4.5+15 4.5+13 100/0.75" 100/0.75" Sheet 1 of 1 Client: Project: Start Date:End Date: Drilling Method: BORING NO.: PROJECT NO.: Location: Surface Elevation: West: North: Hammer Drop (lbs / in): De p t h , f e e t Gr a p h i c L o g MATERIAL DESCRIPTION Sa m p l e T y p e Re c o v e r y % RQ D TX C o n e o r S t d . Pe n . ( b l o w s / f t , i n ) Po c k e t Pe n e t r o m e t e r ( t s f ) Un c o n f i n e d C o m p . St r e n g t h ( t s f ) % P a s s i n g No . 2 0 0 S i e v e Un i t D r y W e i g h t (p c f ) Wa t e r C o n t e n t , % Li q u i d L i m i t Pl a s t i c L i m i t Pl a s t i c i t y I n d e x Sw e l l , % GROUND WATER OBSERVATIONS On Rods (ft): After Drilling (ft): After Hours (ft): Starlight Homes Texas, LLC Ranch at Duck Creek - Phase 2 7/29/2021 7/29/2021 CONTINUOUS FLIGHT AUGER 19 W212004 Fort Worth, Texas 170 / 24 NONE DRY 5058 Brush Creek Rd. Fort Worth,Texas 76119 Phone:817-496-5600 Fax:817-496-5608 www.alphatesting.com 5 10 15 20 25 30 35 40 45 50 Dark Brown CLAY 2.0 Brown CLAY with limestone fragments 4.0 Tan CLAY with limestone fragments 13.0 - with calcareous deposits at 6' to 8' Tan and Gray CLAY 19.0 Tan LIMESTONE with clay seams and layers 20.0 TEST BORING TERMINATED AT 20 FT 4.0 23 69 22 47 4.5+16 4.5+12 40 15 25 0.4 3.25 20 4.5+14 4.5+10 4.5+21 100/1.0" Sheet 1 of 1 Client: Project: Start Date:End Date: Drilling Method: BORING NO.: PROJECT NO.: Location: Surface Elevation: West: North: Hammer Drop (lbs / in): De p t h , f e e t Gr a p h i c L o g MATERIAL DESCRIPTION Sa m p l e T y p e Re c o v e r y % RQ D TX C o n e o r S t d . Pe n . ( b l o w s / f t , i n ) Po c k e t Pe n e t r o m e t e r ( t s f ) Un c o n f i n e d C o m p . St r e n g t h ( t s f ) % P a s s i n g No . 2 0 0 S i e v e Un i t D r y W e i g h t (p c f ) Wa t e r C o n t e n t , % Li q u i d L i m i t Pl a s t i c L i m i t Pl a s t i c i t y I n d e x Sw e l l , % GROUND WATER OBSERVATIONS On Rods (ft): After Drilling (ft): After Hours (ft): Starlight Homes Texas, LLC Ranch at Duck Creek - Phase 2 7/30/2021 7/30/2021 CONTINUOUS FLIGHT AUGER 20 W212004 Fort Worth, Texas 170 / 24 NONE DRY 5058 Brush Creek Rd. Fort Worth,Texas 76119 Phone:817-496-5600 Fax:817-496-5608 www.alphatesting.com 5 10 15 20 25 30 35 40 45 50 Brown CLAY with limestone fragments and calcareous deposits 2.0 Light Brown CLAY with limestone fragments and calcareous deposits 4.0 Tan CLAY with calcareous deposits 13.0 Tan and Gray CLAY 14.0 Tan LIMESTONE with clay seams and layers 19.0 Gray LIMESTONE with shale seams 20.0 TEST BORING TERMINATED AT 20 FT 4.5+21 4.5+18 4.5 14 4.5 14 3.5 16 4.0 23 70 23 47 100/0.50" 100/0.75" Sheet 1 of 1 Client: Project: Start Date:End Date: Drilling Method: BORING NO.: PROJECT NO.: Location: Surface Elevation: West: North: Hammer Drop (lbs / in): De p t h , f e e t Gr a p h i c L o g MATERIAL DESCRIPTION Sa m p l e T y p e Re c o v e r y % RQ D TX C o n e o r S t d . Pe n . ( b l o w s / f t , i n ) Po c k e t Pe n e t r o m e t e r ( t s f ) Un c o n f i n e d C o m p . St r e n g t h ( t s f ) % P a s s i n g No . 2 0 0 S i e v e Un i t D r y W e i g h t (p c f ) Wa t e r C o n t e n t , % Li q u i d L i m i t Pl a s t i c L i m i t Pl a s t i c i t y I n d e x Sw e l l , % GROUND WATER OBSERVATIONS On Rods (ft): After Drilling (ft): After Hours (ft): Starlight Homes Texas, LLC Ranch at Duck Creek - Phase 2 8/3/2021 8/3/2021 CONTINUOUS FLIGHT AUGER 21 W212004 Fort Worth, Texas 170 / 24 NONE DRY 5058 Brush Creek Rd. Fort Worth,Texas 76119 Phone:817-496-5600 Fax:817-496-5608 www.alphatesting.com 5 10 15 20 25 30 35 40 45 50 Brown CLAY with limestone fragments 2.0 Light Brown CLAY with limestone fragments and calacareous deposits 6.0 Tan CLAY with calcareous deposits 7.0 Tan LIMESTONE with clay seams and layers 16.0 Gray LIMESTONE with shale seams 20.0 TEST BORING TERMINATED AT 20 FT 3.5 29 4.5+21 4.5+15 43 17 26 1.1 4.5+14 22 100/6.75" 100/0.50" 100/0.75" 100/0.75" Sheet 1 of 1 Client: Project: Start Date:End Date: Drilling Method: BORING NO.: PROJECT NO.: Location: Surface Elevation: West: North: Hammer Drop (lbs / in): De p t h , f e e t Gr a p h i c L o g MATERIAL DESCRIPTION Sa m p l e T y p e Re c o v e r y % RQ D TX C o n e o r S t d . Pe n . ( b l o w s / f t , i n ) Po c k e t Pe n e t r o m e t e r ( t s f ) Un c o n f i n e d C o m p . St r e n g t h ( t s f ) % P a s s i n g No . 2 0 0 S i e v e Un i t D r y W e i g h t (p c f ) Wa t e r C o n t e n t , % Li q u i d L i m i t Pl a s t i c L i m i t Pl a s t i c i t y I n d e x Sw e l l , % GROUND WATER OBSERVATIONS On Rods (ft): After Drilling (ft): After Hours (ft): Starlight Homes Texas, LLC Ranch at Duck Creek - Phase 2 8/3/2021 8/3/2021 CONTINUOUS FLIGHT AUGER 22 W212004 Fort Worth, Texas 170 / 24 NONE DRY 5058 Brush Creek Rd. Fort Worth,Texas 76119 Phone:817-496-5600 Fax:817-496-5608 www.alphatesting.com 5 10 15 20 25 30 35 40 45 50 Brown CLAY with limestone fragments 6.0 Tan LIMESTONE with clay seams and layers 12.0 Gray LIMESTONE with shale seams 20.0 TEST BORING TERMINATED AT 20 FT 2.5 29 75 24 51 0.0 4.5 23 2.0 32 82 25 57 50/4.5" 100/0.50" 100/2.75" 100/0.75" Sheet 1 of 1 Client: Project: Start Date:End Date: Drilling Method: BORING NO.: PROJECT NO.: Location: Surface Elevation: West: North: Hammer Drop (lbs / in): De p t h , f e e t Gr a p h i c L o g MATERIAL DESCRIPTION Sa m p l e T y p e Re c o v e r y % RQ D TX C o n e o r S t d . Pe n . ( b l o w s / f t , i n ) Po c k e t Pe n e t r o m e t e r ( t s f ) Un c o n f i n e d C o m p . St r e n g t h ( t s f ) % P a s s i n g No . 2 0 0 S i e v e Un i t D r y W e i g h t (p c f ) Wa t e r C o n t e n t , % Li q u i d L i m i t Pl a s t i c L i m i t Pl a s t i c i t y I n d e x Sw e l l , % GROUND WATER OBSERVATIONS On Rods (ft): After Drilling (ft): After Hours (ft): Starlight Homes Texas, LLC Ranch at Duck Creek - Phase 2 7/29/2021 7/29/2021 CONTINUOUS FLIGHT AUGER 23 W212004 Fort Worth, Texas 170 / 24 NONE DRY 5058 Brush Creek Rd. Fort Worth,Texas 76119 Phone:817-496-5600 Fax:817-496-5608 www.alphatesting.com 5 10 15 20 25 30 35 40 45 50 Dark Brown CLAY 2.0 Brown CLAY with limestone fragments 6.0 - with calcareous deposits at 4' to 6' Tan CLAY with limestone fragments 8.0 Tan and Gray SHALY CLAY 15.0 - with calcareous deposits at 8' to 10' Tan LIMESTONE with clay seams and layers 20.0 TEST BORING TERMINATED AT 20 FT 4.5+19 4.5+13 31 15 16 0.0 4.5+13 4.5+17 3.75 23 4.5+17 45 18 27 9100/0.75" Sheet 1 of 1 Client: Project: Start Date:End Date: Drilling Method: BORING NO.: PROJECT NO.: Location: Surface Elevation: West: North: Hammer Drop (lbs / in): De p t h , f e e t Gr a p h i c L o g MATERIAL DESCRIPTION Sa m p l e T y p e Re c o v e r y % RQ D TX C o n e o r S t d . Pe n . ( b l o w s / f t , i n ) Po c k e t Pe n e t r o m e t e r ( t s f ) Un c o n f i n e d C o m p . St r e n g t h ( t s f ) % P a s s i n g No . 2 0 0 S i e v e Un i t D r y W e i g h t (p c f ) Wa t e r C o n t e n t , % Li q u i d L i m i t Pl a s t i c L i m i t Pl a s t i c i t y I n d e x Sw e l l , % GROUND WATER OBSERVATIONS On Rods (ft): After Drilling (ft): After Hours (ft): Starlight Homes Texas, LLC Ranch at Duck Creek - Phase 2 7/30/2021 7/30/2021 CONTINUOUS FLIGHT AUGER 24 W212004 Fort Worth, Texas 170 / 24 NONE DRY 5058 Brush Creek Rd. Fort Worth,Texas 76119 Phone:817-496-5600 Fax:817-496-5608 www.alphatesting.com 5 10 15 20 25 30 35 40 45 50 Dark Brown CLAY 2.0 Brown CLAY with limestone fragments 4.0 Tan CLAY with limestone fragments and calcareous deposits 13.0 Tan LIMESTONE with clay seams and layers 20.0 TEST BORING TERMINATED AT 20 FT 4.5+23 4.5+20 4.5+14 3.0 19 33 16 17 4.5+14 100/0.25" 100/0.75" Sheet 1 of 1 Client: Project: Start Date:End Date: Drilling Method: BORING NO.: PROJECT NO.: Location: Surface Elevation: West: North: Hammer Drop (lbs / in): De p t h , f e e t Gr a p h i c L o g MATERIAL DESCRIPTION Sa m p l e T y p e Re c o v e r y % RQ D TX C o n e o r S t d . Pe n . ( b l o w s / f t , i n ) Po c k e t Pe n e t r o m e t e r ( t s f ) Un c o n f i n e d C o m p . St r e n g t h ( t s f ) % P a s s i n g No . 2 0 0 S i e v e Un i t D r y W e i g h t (p c f ) Wa t e r C o n t e n t , % Li q u i d L i m i t Pl a s t i c L i m i t Pl a s t i c i t y I n d e x Sw e l l , % GROUND WATER OBSERVATIONS On Rods (ft): After Drilling (ft): After Hours (ft): Starlight Homes Texas, LLC Ranch at Duck Creek - Phase 2 8/3/2021 8/30/2021 CONTINUOUS FLIGHT AUGER 25 W212004 Fort Worth, Texas 170 / 24 NONE DRY 5058 Brush Creek Rd. Fort Worth,Texas 76119 Phone:817-496-5600 Fax:817-496-5608 www.alphatesting.com 5 10 15 20 25 30 35 40 45 50 Dark Brown CLAY 4.0 Tan CLAY with limestone fragments and calcareous deposits 8.0 Tan LIMESTONE with clay seams and layers 16.0 Gray LIMESTONE with shale seams 20.0 TEST BORING TERMINATED AT 20 FT 3.0 33 79 26 53 0.7 4.5+23 4.5+13 4.5+11 100/1.50" 100/0.25" 100/0.50" 100/0.75" Sheet 1 of 1 Client: Project: Start Date:End Date: Drilling Method: BORING NO.: PROJECT NO.: Location: Surface Elevation: West: North: Hammer Drop (lbs / in): De p t h , f e e t Gr a p h i c L o g MATERIAL DESCRIPTION Sa m p l e T y p e Re c o v e r y % RQ D TX C o n e o r S t d . Pe n . ( b l o w s / f t , i n ) Po c k e t Pe n e t r o m e t e r ( t s f ) Un c o n f i n e d C o m p . St r e n g t h ( t s f ) % P a s s i n g No . 2 0 0 S i e v e Un i t D r y W e i g h t (p c f ) Wa t e r C o n t e n t , % Li q u i d L i m i t Pl a s t i c L i m i t Pl a s t i c i t y I n d e x Sw e l l , % GROUND WATER OBSERVATIONS On Rods (ft): After Drilling (ft): After Hours (ft): Starlight Homes Texas, LLC Ranch at Duck Creek - Phase 2 8/3/2021 8/30/2021 CONTINUOUS FLIGHT AUGER 26 W212004 Fort Worth, Texas 170 / 24 NONE DRY 5058 Brush Creek Rd. Fort Worth,Texas 76119 Phone:817-496-5600 Fax:817-496-5608 www.alphatesting.com 5 10 15 20 25 30 35 40 45 50 Dark Brown CLAY with limestone fragments 2.0 Brown CLAY with limestone fragments and calcareous deposits 4.0 Light Brown CLAY with calcareous deposits and limestone fragments 5.0 Tan LIMESTONE with clay seams and layers 15.0 Gray LIMESTONE with shale seams 20.0 TEST BORING TERMINATED AT 20 FT 3.5 29 4.5+21 2.5 20 46 17 29 0.5 100/0.50" 100/0.75" 100/1.75" 100/0.75" Sheet 1 of 1 Client: Project: Start Date:End Date: Drilling Method: BORING NO.: PROJECT NO.: Location: Surface Elevation: West: North: Hammer Drop (lbs / in): De p t h , f e e t Gr a p h i c L o g MATERIAL DESCRIPTION Sa m p l e T y p e Re c o v e r y % RQ D TX C o n e o r S t d . Pe n . ( b l o w s / f t , i n ) Po c k e t Pe n e t r o m e t e r ( t s f ) Un c o n f i n e d C o m p . St r e n g t h ( t s f ) % P a s s i n g No . 2 0 0 S i e v e Un i t D r y W e i g h t (p c f ) Wa t e r C o n t e n t , % Li q u i d L i m i t Pl a s t i c L i m i t Pl a s t i c i t y I n d e x Sw e l l , % GROUND WATER OBSERVATIONS On Rods (ft): After Drilling (ft): After Hours (ft): Starlight Homes Texas, LLC Ranch at Duck Creek - Phase 2 7/29/2021 7/29/2021 CONTINUOUS FLIGHT AUGER 27 W212004 Fort Worth, Texas 170 / 24 NONE DRY 5058 Brush Creek Rd. Fort Worth,Texas 76119 Phone:817-496-5600 Fax:817-496-5608 www.alphatesting.com 5 10 15 20 25 30 35 40 45 50 Dark Brown CLAY 2.0 Brown CLAY 4.0 Tan CLAY with calcareous deposits 14.0 Tan LIMESTONE with clay seams and layers 20.0 TEST BORING TERMINATED AT 20 FT 4.5+21 4.5+17 62 20 42 2.4 3.5 13 4.0 13 3.5 20 32 17 15 15 7 100/0.75" 100/0.50" Sheet 1 of 1 Client: Project: Start Date:End Date: Drilling Method: BORING NO.: PROJECT NO.: Location: Surface Elevation: West: North: Hammer Drop (lbs / in): De p t h , f e e t Gr a p h i c L o g MATERIAL DESCRIPTION Sa m p l e T y p e Re c o v e r y % RQ D TX C o n e o r S t d . Pe n . ( b l o w s / f t , i n ) Po c k e t Pe n e t r o m e t e r ( t s f ) Un c o n f i n e d C o m p . St r e n g t h ( t s f ) % P a s s i n g No . 2 0 0 S i e v e Un i t D r y W e i g h t (p c f ) Wa t e r C o n t e n t , % Li q u i d L i m i t Pl a s t i c L i m i t Pl a s t i c i t y I n d e x Sw e l l , % GROUND WATER OBSERVATIONS On Rods (ft): After Drilling (ft): After Hours (ft): Starlight Homes Texas, LLC Ranch at Duck Creek - Phase 2 7/30/2021 7/30/2021 CONTINUOUS FLIGHT AUGER 28 W212004 Fort Worth, Texas 170 / 24 NONE DRY 5058 Brush Creek Rd. Fort Worth,Texas 76119 Phone:817-496-5600 Fax:817-496-5608 www.alphatesting.com 5 10 15 20 25 30 35 40 45 50 Brown CLAY with calcareous deposits and limestone fragments 4.0 Light Brown CLAY with calcareous deposits 6.0 Tan CLAY with calcareous deposits 10.0 Tan LIMESTONE with clay seams and layers 17.0 Gray LIMESTONE with shale seams 20.0 TEST BORING TERMINATED AT 20 FT 4.5+19 4.5+17 4.5+14 4.5+12 33 15 18 0.1 15 100/0.75" 100/0.75" Sheet 1 of 1 Client: Project: Start Date:End Date: Drilling Method: BORING NO.: PROJECT NO.: Location: Surface Elevation: West: North: Hammer Drop (lbs / in): De p t h , f e e t Gr a p h i c L o g MATERIAL DESCRIPTION Sa m p l e T y p e Re c o v e r y % RQ D TX C o n e o r S t d . Pe n . ( b l o w s / f t , i n ) Po c k e t Pe n e t r o m e t e r ( t s f ) Un c o n f i n e d C o m p . St r e n g t h ( t s f ) % P a s s i n g No . 2 0 0 S i e v e Un i t D r y W e i g h t (p c f ) Wa t e r C o n t e n t , % Li q u i d L i m i t Pl a s t i c L i m i t Pl a s t i c i t y I n d e x Sw e l l , % GROUND WATER OBSERVATIONS On Rods (ft): After Drilling (ft): After Hours (ft): Starlight Homes Texas, LLC Ranch at Duck Creek - Phase 2 7/28/2021 7/28/2021 CONTINUOUS FLIGHT AUGER 29 W212004 Fort Worth, Texas 170 / 24 NONE DRY 5058 Brush Creek Rd. Fort Worth,Texas 76119 Phone:817-496-5600 Fax:817-496-5608 www.alphatesting.com 5 10 15 20 25 30 35 40 45 50 Dark Brown CLAY with limestone fragments 2.0 Brown and Tan CLAY with rocks and limestone fragments 4.0 Tan CLAY with limestone fragments and calcareous deposits 6.0 Brown CLAY with limestone fragments 10.0 Tan and Gray SHALY CLAY 15.0 Tan LIMESTONE with clay seams and layers 20.0 TEST BORING TERMINATED AT 20 FT 4.5+22 68 23 45 6.5 4.5+5 4.5+11 7 38 17 21 8 2.5 25 6100/0.75" Sheet 1 of 1 Client: Project: Start Date:End Date: Drilling Method: BORING NO.: PROJECT NO.: Location: Surface Elevation: West: North: Hammer Drop (lbs / in): De p t h , f e e t Gr a p h i c L o g MATERIAL DESCRIPTION Sa m p l e T y p e Re c o v e r y % RQ D TX C o n e o r S t d . Pe n . ( b l o w s / f t , i n ) Po c k e t Pe n e t r o m e t e r ( t s f ) Un c o n f i n e d C o m p . St r e n g t h ( t s f ) % P a s s i n g No . 2 0 0 S i e v e Un i t D r y W e i g h t (p c f ) Wa t e r C o n t e n t , % Li q u i d L i m i t Pl a s t i c L i m i t Pl a s t i c i t y I n d e x Sw e l l , % GROUND WATER OBSERVATIONS On Rods (ft): After Drilling (ft): After Hours (ft): Starlight Homes Texas, LLC Ranch at Duck Creek - Phase 2 7/30/2021 7/30/2021 CONTINUOUS FLIGHT AUGER 30 W212004 Fort Worth, Texas 170 / 24 NONE DRY 5058 Brush Creek Rd. Fort Worth,Texas 76119 Phone:817-496-5600 Fax:817-496-5608 www.alphatesting.com 5 10 15 20 25 30 35 40 45 50 Brown CLAY with limestone fragments and calcareous deposits 4.0 Tan CLAY with calcareous deposits 10.0 Tan LIMESTONE with clay seams and layers 16.0 Gray LIMESTONE with shale seams 20.0 TEST BORING TERMINATED AT 20 FT 4.5+21 4.5+21 76 25 51 4.5+21 4.5+15 4.5+15 100/0.75" 100/0.75" Sheet 1 of 1 Client: Project: Start Date:End Date: Drilling Method: BORING NO.: PROJECT NO.: Location: Surface Elevation: West: North: Hammer Drop (lbs / in): De p t h , f e e t Gr a p h i c L o g MATERIAL DESCRIPTION Sa m p l e T y p e Re c o v e r y % RQ D TX C o n e o r S t d . Pe n . ( b l o w s / f t , i n ) Po c k e t Pe n e t r o m e t e r ( t s f ) Un c o n f i n e d C o m p . St r e n g t h ( t s f ) % P a s s i n g No . 2 0 0 S i e v e Un i t D r y W e i g h t (p c f ) Wa t e r C o n t e n t , % Li q u i d L i m i t Pl a s t i c L i m i t Pl a s t i c i t y I n d e x Sw e l l , % GROUND WATER OBSERVATIONS On Rods (ft): After Drilling (ft): After Hours (ft): Starlight Homes Texas, LLC Ranch at Duck Creek - Phase 2 7/30/2021 7/30/2021 CONTINUOUS FLIGHT AUGER 31 W212004 Fort Worth, Texas 170 / 24 NONE DRY 5058 Brush Creek Rd. Fort Worth,Texas 76119 Phone:817-496-5600 Fax:817-496-5608 www.alphatesting.com 5 10 15 20 25 30 35 40 45 50 Dark Brown CLAY with limestone fragments 4.0 Brown CLAY with limestone fragments 5.0 Tan LIMESTONE with clay seams and layers 16.0 Gray LIMESTONE with shale seams 20.0 TEST BORING TERMINATED AT 20 FT 4.5+23 4.5+23 77 24 53 4.4 4.5+17 4.5+21 100/1.50" 100/0.50" 100/0.75" Sheet 1 of 1 TEXAS CONE PENETRATION FILL LIMESTONE (MH), Elastic SILT SANDSTONE (GP), Poorly Graded GRAVEL LOW MEDIUM HIGH VERY HIGH 4 TO 15 16 TO 25 26 TO 35 OVER 35 SAMPLING SYMBOLS (OL), ORGANIC SILT (OH), ORGANIC CLAY 8.0" OR LARGER 3.0" TO 8.0" 0.75" TO 3.0" 5.0 mm TO 3.0" 2.0 mm TO 5.0 mm 0.4 mm TO 5.0 mm 0.07 mm TO 0.4 mm 0.002 mm TO 0.07 mm LESS THAN 0.002 mm SOIL & ROCK SYMBOLS KEY TO SOIL SYMBOLS AND CLASSIFICATIONS (CH), High Plasticity CLAY VERY LOOSE LOOSE MEDIUM DENSE VERY DENSE RELATIVE DENSITY OF COHESIONLESS SOILS (blows/ft) 0 TO 4 5 TO 10 11 TO 30 31 TO 50 OVER 50 SHELBY TUBE (3" OD except where noted otherwise) SPLIT SPOON (2" OD except where noted otherwise) AUGER SAMPLE ROCK CORE (2" ID except where noted otherwise) PARTICLE SIZE IDENTIFICATION (DIAMETER) (CL), Low Plasticity CLAY (SP), Poorly Graded SAND (GW), Well Graded GRAVEL (GC), CLAYEY GRAVEL (GM), SILTY GRAVEL BOULDERS COBBLES COARSE GRAVEL FINE GRAVEL COURSE SAND MEDIUM SAND FINE SAND SILT CLAY TRACE LITTLE SOME AND 1 TO 10 11 TO 20 21 TO 35 36 TO 50 RELATIVE PROPORTIONS (%) VERY SOFT SOFT FIRM STIFF VERY STIFF HARD LESS THAN 0.25 0.25 TO 0.50 0.50 TO 1.00 1.00 TO 2.00 2.00 TO 4.00 OVER 4.00 SHEAR STRENGTH OF COHESIVE SOILS (tsf) RELATIVE DEGREE OF PLASTICITY (PI)SHALE / MARL (SC), CLAYEY SAND (SW), Well Graded SAND (SM), SILTY SAND (ML), SILT Approval Spec No. Classsification Manufacturer Model No. National Spec Size Water & Sewer - Manholes & Bases/Components 33-39-10 (Rev 2/3/16) 07/23/97 33 05 13 Urethane Hydrophilic Waterstop Asahi Kogyo K.K. Adeka Ultra-Seal P-201 ASTM D2240/D412/D792 04/26/00 33 05 13 Offset Joint for 4' Diam. MH Hanson Concrete Products Drawing No. 35-0048-001 04/26/00 33 05 13 Profile Gasket for 4' Diam. MH. Press-Seal Gasket Corp. 250-4G Gasket ASTM C-443/C-361 SS MH 1/26/99 33 05 13 HDPE Manhole Adjustment Rings Ladtech, Inc HDPE Adjustment Ring Traffic and Non-traffic area 5/13/05 33 05 13 Manhole External Wrap Canusa - CPS WrapidSeal Manhole Encapsulation System Water & Sewer - Manholes & Bases/Fiberglass 33-39-13 (1/8/13) 1/26/99 33 39 13 Fiberglass Manhole Fluid Containment, Inc. Flowtite ASTM 3753 Non-traffic area 08/30/06 33 39 13 Fiberglass Manhole L.F. Manufacturing Non-traffic area Water & Sewer - Manholes & Bases/Frames & Covers/Rectangular 33-05-13 (Rev 2/3/16) * 33 05 13 Manhole Frames and Covers Western Iron Works, Bass & Hays Foundry 1001 24"x40" WD Water & Sewer - Manholes & Bases/Frames & Covers/Standard (Round) 33-05-13 (Rev 2/3/16) * 33 05 13 Manhole Frames and Covers Western Iron Works, Bass & Hays Foundry 30024 24" Dia. * 33 05 13 Manhole Frames and Covers McKinley Iron Works Inc. A 24 AM 24" Dia. 08/24/18 33 05 13 Manhole Frames and Covers Neenah Foundry R-1272 ASTM A48 & AASHTO M306 24" Dia. 08/24/18 33 05 13 Manhole Frames and Covers Neenah Foundry R- 165-LM (Hinged) ASTM A48 & AASHTO M306 24" Dia. 08/24/18 33 05 13 Manhole Frames and Covers Neenah Foundry NF 1274 ASTM A48 & AASHTO M306 30" Dia. 08/24/18 33 05 13 Manhole Frames and Covers Neenah Foundry R-1743-LM (Hinged) ASTM A48 & AASHTO M306 30" dia. 33 05 13 Manhole Frames and Covers Sigma Corporation MH-144N 33 05 13 Manhole Frames and Covers Sigma Corporation MH-143N 33 05 13 Manhole Frames and Covers Pont-A-Mousson GTS-STD 24" dia. 33 05 13 Manhole Frames and Covers Neenah Casting 24" dia. 10/31/06 33 05 13 Manhole Frames and Covers (Hinged) Powerseal Hinged Ductile Iron Manhole ASTM A536 24" Dia. 7/25/03 33 05 13 Manhole Frames and Covers Saint-Gobain Pipelines (Pamrex/rexus) RE32-R8FS 30" Dia. 01/31/06 33 05 13 30" Dia. MH Ring and Cover East Jordan Iron Works V1432-2 and V1483 Designs AASHTO M306-04 30" Dia. 11/02/10 33 05 13 30" Dia. MH Ring and Cover Sigma Corporation MH1651FWN & MH16502 30" Dia 07/19/11 33 05 13 30" Dia. MH Ring and Cover Star Pipe Products MH32FTWSS-DC 30" Dia 08/10/11 33 05 13 30" Dia. MH Ring and Cover Accucast 220700 Heavy Duty with Gasket Ring 30" Dia 10/14/13 33 05 13 30" Dia. MH Ring and Cover (Hinged & Lockable) East Jordan Iron Works 30" ERGO XL Assembly with Cam Lock/MPIC/T-Gasket ASSHTO M105 & ASTM A536 30" Dia 06/01/17 34 05 13 30" Dia. MH Ring and Cover (Hinged & Lockable) CI SIP Industries 2280 (32") ASTM A 48 30" Dia. 09/16/19 33 05 13 30" Dia. MH Ring and Cover Composite Access Products, L.P. CAP-ONE-30-FTW, Composite, w/ Lock w/o Hing 30" Dia. 10/07/21 34 05 13 30" Dia. MH Ring and Cover Trumbull Manufacturing 32"(30") Frame and Cover 30" Dia. Water & Sewer - Manholes & Bases/Frames & Covers/Water Tight & Pressure Tight 33-05-13 (Rev 2/3/16) * 33 05 13 Manhole Frames and Covers Pont-A-Mousson Pamtight 24" Dia. * 33 05 13 Manhole Frames and Covers Neenah Casting 24" Dia. * 33 05 13 Manhole Frames and Covers Western Iron Works,Bass & Hays Foundry 300-24P 24" Dia. * 33 05 13 Manhole Frames and Covers McKinley Iron Works Inc. WPA24AM 24" Dia. 03/08/00 33 05 13 Manhole Frames and Covers Accucast RC-2100 ASTM A 48 24" Dia. 04/20/01 33 05 13 Manhole Frames and Covers (SIP)Serampore Industries Private Ltd. 300-24-23.75 Ring and Cover ASTM A 48 24" Dia. Water & Sewer - Manholes & Bases/Precast Concrete (Rev 1/8/13) * 33 39 10 Manhole, Precast Concrete Hydro Conduit Corp SPL Item #49 ASTM C 478 48" * 33 39 10 Manhole, Precast Concrete Wall Concrete Pipe Co. Inc. ASTM C-443 48" 09/23/96 33 39 10 Manhole, Precast Concrete Concrete Product Inc. 48" I.D. Manhole w/ 32" Cone ASTM C 478 48" w/32" cone 05/08/18 33 39 10 Manhole, Precast Concrete The Turner Company 48", 60" I.D. Manhole w/ 32" Cone ASTM C 478 48", 60" 10/27/06 33 39 10 Manhole, Precast Concrete Oldcastle Precast Inc.48" I.D. Manhole w/ 24" Cone ASTM C 478 48" Diam w 24" Ring 06/09/10 33 39 10 Manhole, Precast (Reinforced Polymer)Concrete US Composite Pipe Reinforced Polymer Concrete ASTM C-76 48" to 72" 09/06/19 33 39 20 Manhole, Precast Concrete Forterra Pipe and Precast 60" & 72" I.D. Manhole w/32" Cone ASTM C-76 60" & 72" 10/07/21 32 39 20 Manhole, Precast Concrete Forterra Pipe and Precast 48" I.D. Manhole w/32" Cone ASTM C-77 48" 10/07/21 33 39 20 Manhole, Precast (Reinforced Polymer) Concrete Armorock 48" & 60" I.D. Manhole w/32" Cone 48" & 60" 10/07/21 33 39 20 Manhole, Precast (Hybrid) Polymer & PVC Predl Systems 48" & 60" I.D. Manhole w/32" Cone 48" & 60" Non Traffic Areas Water & Sewer - Manholes & Bases/Rehab Systems/Cementitious * E1-14 Manhole Rehab Systems Quadex 04/23/01 E1-14 Manhole Rehab Systems Standard Cement Materials, Inc. Reliner MSP E1-14 Manhole Rehab Systems AP/M Permaform 4/20/01 E1-14 Manhole Rehab System Strong Company Strong Seal MS2A Rehab System 5/12/03 E1-14 Manhole Rehab System (Liner) Poly-triplex Technologies MH repair product to stop infiltration ASTM D5813 08/30/06 General Concrete Repair FlexKrete Technologies Vinyl Polyester Repair Product Misc. Use Water & Sewer - Manholes & Bases/Rehab Systems/NonCementitious 05/20/96 E1-14 Manhole Rehab Systems Sprayroq, Spray Wall Polyurethane Coating ASTM D639/D790 * E1-14 Manhole Rehab Systems Sun Coast 12/14/01 Coating for Corrosion protection(Exterior) ERTECH Series 20230 and 2100 (Asphatic Emulsion) For Exterior Coating of Concrete Structures Only 01/31/06 Coatings for Corrosion Protection Chesterton Arc 791, S1HB, S1, S2 Acid Resistance Test Sewer Applications 8/28/2006 Coatings for Corrosion Protection Warren Environmental S-301 and M-301 Sewer Applications 08/30/06 Coatings for Corrosion Protection Citadel SLS-30 Solids Epoxy Sewer Applications 03/19/18 33 05 16, 33 39 10, 33 39 20 Coating for Corrosion protection(Exterior) Sherwin Williams RR&C Dampproofing Non-Fibered Spray Grade (Asphatic Emulsion) For Exterior Coating of Concrete Structures Only CITY OF FORT WORTH WATER DEPARTMENT STANDARD PRODUCT LIST Note: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes. Updated: 03/29/2022 * From Original Standard Products List 1 Approval Spec No. Classsification Manufacturer Model No. National Spec Size CITY OF FORT WORTH WATER DEPARTMENT STANDARD PRODUCT LIST Note: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes. Updated: 03/29/2022 Water & Sewer - Manhole Inserts - Field Operations Use Only (Rev 2/3/16) * 33 05 13 Manhole Insert Knutson Enterprises Made to Order - Plastic ASTM D 1248 For 24" dia. * 33 05 13 Manhole Insert South Western Packaging Made to Order - Plastic ASTM D 1248 For 24" dia. * 33 05 13 Manhole Insert Noflow-Inflow Made to Order - Plastic ASTM D 1248 For 24" dia. 09/23/96 33 05 13 Manhole Insert Southwestern Packing & Seals, Inc. LifeSaver - Stainless Steel For 24" dia. 09/23/96 33 05 13 Manhole Insert Southwestern Packing & Seals, Inc. TetherLok - Stainless Steel For 24" dia Water & Sewer - Pipe Casing Spacers 33-05-24 (07/01/13) 11/04/02 Steel Band Casing Spacers Advanced Products and Systems, Inc. Carbon Steel Spacers, Model SI 02/02/93 Stainless Steel Casing Spacer Advanced Products and Systems, Inc. Stainless Steel Spacer, Model SSI 04/22/87 Casing Spacers Cascade Waterworks Manufacturing Casing Spacers 09/14/10 Stainless Steel Casing Spacer Pipeline Seal and Insulator Stainless Steel Casing Spacer Up to 48" 09/14/10 Coated Steel Casin Spacers Pipeline Seal and Insulator Coated Steel Casin Spacers Up to 48" 05/10/11 Stainless Steel Casing Spacer Powerseal 4810 Powerchock Up to 48" 03/19/18 Casing Spacers BWM SS-12 Casing Spacer(Stainless Steel) 03/19/18 Casing Spacers BWM FB-12 Casing Spacer (Coated Carbon Steel) for Non_pressure Pipe and Grouted Casing 03/29/22 33 05 13 Casing Spacers CCI Pipeline Systems CSC12, CSS12 Water & Sewer - Pipes/Ductile Iron 33-11-10(1/8/13) * 33 11 10 Ductile Iron Pipe Griffin Pipe Products, Co. Super Bell-Tite Ductile Iron Pressure Pipe, AWWA C150, C151 3" thru 24" 08/24/18 33 11 10 Ductile Iron Pipe American Ductile Iron Pipe Co.American Fastite Pipe (Bell Spigot) AWWA C150, C151 4" thru 30" 08/24/18 33 11 10 Ductile Iron Pipe American Ductile Iron Pipe Co.American Flex Ring (Restrained Joint) AWWA C150, C151 4" thru 30" * 33 11 10 Ductile Iron Pipe U.S. Pipe and Foundry Co. AWWA C150, C151 * 33 11 10 Ductile Iron Pipe McWane Cast Iron Pipe Co. AWWA C150, C151 Water & Sewer - Utility Line Marker (08/24/2018) Sewer - Coatings/Epoxy 33-39-60 (01/08/13) 02/25/02 Epoxy Lining System Sauereisen, Inc SewerGard 210RS LA County #210-1.33 12/14/01 Epoxy Lining System Ertech Technical Coatings Ertech 2030 and 2100 Series 04/14/05 Interior Ductile Iron Pipe Coating Induron Protecto 401 ASTM B-117 Ductile Iron Pipe Only 01/31/06 Coatings for Corrosion Protection Chesterton Arc 791, S1HB, S1, S2 Acid Resistance Test Sewer Applications 8/28/2006 Coatings for Corrosion Protection Warren Environmental S-301 and M-301 Sewer Applications Sewer - Coatings/Polyurethane Sewer - Combination Air Valves 05/25/18 33-31-70 Air Release Valve A.R.I. USA, Inc. D025LTP02(Composite Body) 2" Sewer - Pipes/Concrete * E1-04 Conc. Pipe, Reinforced Wall Concrete Pipe Co. Inc. ASTM C 76 * E1-04 Conc. Pipe, Reinforced Hydro Conduit Corporation Class III T&G, SPL Item #77 ASTM C 76 * E1-04 Conc. Pipe, Reinforced Hanson Concrete Products SPL Item #95-Manhole, #98- Pipe ASTM C 76 * E1-04 Conc. Pipe, Reinforced Concrete Pipe & Products Co. Inc. ASTM C 76 Sewer - Pipe Enlargment System (Method)33-31-23 (01/18/13) PIM System PIM Corporation Polyethylene PIM Corp., Piscata Way, N.J. Approved Previously McConnell Systems McLat Construction Polyethylene Houston, Texas Approved Previously TRS Systems Trenchless Replacement System Polyethylene Calgary, Canada Approved Previously Sewer - Pipe/Fiberglass Reinforced Pipe 33-31-13(1/8/13) 7/21/97 33 31 13 Cent. Cast Fiberglass (FRP) Hobas Pipe USA, Inc.Hobas Pipe (Non-Pressure) ASTM D3262/D3754 03/22/10 33 31 13 Fiberglass Pipe (FRP) Ameron Bondstrand RPMP Pipe ASTM D3262/D3754 04/09/21 Glass-Fiber Reinforced Polymer Pipe (FRP) Thompson Pipe Group Thompson Pipe (Flowtite) ASTM D3262/D3754 4/14/05 Polymer Modified Concrete Pipe Amitech USA Meyer Polycrete Pipe ASTM C33, A276, F477 8" to 102", Class V 06/09/10 E1-9 Reinforced Polymer Concrete Pipe US Composite Pipe Reinforced Polymer Concrete Pipe ASTM C-76 Sewer - Pipes/HDPE 33-31-23(1/8/13) * High-density polyethylene pipe Phillips Driscopipe, Inc. Opticore Ductile Polyethylene Pipe ASTM D 1248 8" * High-density polyethylene pipe Plexco Inc. ASTM D 1248 8" * High-density polyethylene pipe Polly Pipe, Inc. ASTM D 1248 8" High-density polyethylene pipe CSR Hydro Conduit/Pipeline Systems McConnell Pipe Enlargement ASTM D 1248 Sewer - Pipes/PVC (Pressure Sewer) 33-11-12 (4/1/13) 12/02/11 33-11-12 DR-14 PVC Pressure Pipe Pipelife Jetstream PVC Pressure Pipe AWWA C900 4" thru 12" 10/22/14 33-11-12 DR-14 PVC Pressure Pipe Royal Building Products Royal Seal PVC Pressure Pipe AWWA C900 4" thru 12" * From Original Standard Products List 2 Approval Spec No. Classsification Manufacturer Model No. National Spec Size CITY OF FORT WORTH WATER DEPARTMENT STANDARD PRODUCT LIST Note: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes. Updated: 03/29/2022 Sewer - Pipes/PVC* 33-31-20 (7/1/13) * 33-31-20 PVC Sewer Pipe J-M Manufacturing Co., Inc. (JM Eagle) SDR-26 ASTM D 3034 4" - 15" 12/23/97* 33-31-20 PVC Sewer Pipe Diamond Plastics Corporation SDR-26 ASTM D 3034 4" thru 15" * 33-31-20 PVC Sewer Pipe Lamson Vylon Pipe ASTM F 789 4" thru 15" 01/18/18 33-31-20 PVC Sewer Pipe Vinyltech PVC Pipe Gravity Sewer ASTM D3034 4" thru 15" 11/11/98 33-31-20 PVC Sewer Pipe Diamond Plastics Corporation "S" Gravity Sewer Pipe ASTM F 679 18" to 27" * 33-31-20 PVC Sewer Pipe J-M Manufacturing Co, Inc. (JM Eagle) SDR 26/35 PS 115/46 ASTM F 679 18" - 28" 09/11/12 33-31-20 PVC Sewer Pipe Pipelife Jet Stream SDR-26 and SDR-35 ASTM F-679 18" 05/06/05 33-31-20 PVC Solid Wall Pipe Diamond Plastics Corporation SDR 26/35 PS 115/46 ASTM F-679 18" to 48" 04/27/06 33-31-20 PVC Sewer Fittings Harco SDR-26 and SDR-35 Gasket Fittings ASTM D-3034, D-1784, etc 4" - 15" *33-31-20 PVC Sewer Fittings Plastic Trends, Inc.(Westlake)Gasketed PVC Sewer Main Fittings ASTM D 3034 3/19/2018 33 31 20 PVC Sewer Pipe Pipelife Jet Stream SDR 35 ASTM F679 18"- 24" 3/19/2018 33 31 20 PVC Sewer Pipe Pipelife Jet Stream SDR 26 ASTM D3034 4"- 15" 3/29/2019 33 31 20 Gasketed Fittings (PVC)GPK Products, Inc. SDR 26 ASTM D3034/F-679 4"- 15" 10/21/2020 33 31 20 PVC Sewer Pipe NAPCO(Westlake) SDR 26 ASTM D3034 4" - 15" 10/22/2020 33 31 20 PVC Sewer Pipe Sanderson Pipe Corp. SDR 26 ASTM D3034 4"- 15" 10/21/2020 33 31 20 PVC Sewer Pipe NAPCO(Westlake) SDR 26/35 PS 115/46 ASTM F-679 18"- 36" Sewer - Pipes/Rehab/CIPP 33-31-12 (01/18/13) * Cured in Place Pipe Insituform Texark, Inc ASTM F 1216 05/03/99 Cured in Place Pipe National Envirotech Group National Liner, (SPL) Item #27 ASTM F-1216/D-5813 05/29/96 Cured in Place Pipe Reynolds Inc/Inliner Technolgy (Inliner USA) Inliner Technology ASTM F 1216 Sewer - Pipes/Rehab/Fold & Form * Fold and Form Pipe Cullum Pipe Systems, Inc. 11/03/98 Fold and Form Pipe Insituform Technologies, Inc. Insituform "NuPIpe" ASTM F-1504 Fold and Form Pipe American Pipe & Plastics, Inc.Demo. Purpose Only 12/04/00 Fold and Form Pipe Ultraliner Ultraliner PVC Alloy Pipeliner ASTM F-1504, 1871, 1867 06/09/03 Fold and Form Pipe Miller Pipeline Corp. EX Method ASTM F-1504, F-1947 Up to 18" diameter Sewer - Pipes/Open Profile Large Diameter 09/26/91 E100-2 PVC Sewer Pipe, Ribbed Lamson Vylon Pipe Carlon Vylon H.C. Closed Profile Pipe, ASTM F 679 18" to 48" 09/26/91 E100-2 PVC Sewer Pipe, Ribbed Extrusion Technologies, Inc. Ultra-Rib Open Profile Sewer Pipe ASTM F 679 18" to 48" E100-2 PVC Sewer Pipe, Ribbed Uponor ETI Company 11/10/10 (E100-2) Polypropylene (PP) Sewer Pipe, Double Wall Advanced Drainage Systems (ADS) SaniTite HP Double Wall (Corrugated)ASTM F 2736 24"-30" 11/10/10 (E100-2) Polypropylene (PP) Sewer Pipe, Triple Wall Advanced Drainage Systems (ADS) SaniTite HP Triple Wall Pipe ASTM F 2764 30" to 60" 05/16/11 Steel Reinforced Polyethylene Pipe ConTech Construction Products Durmaxx ASTM F 2562 24" to 72" Water - Appurtenances 33-12-10 (07/01/13) 01/18/18 33-12-10 Double Strap Saddle Romac 202NS Nylon Coated AWWA C800 1"-2" SVC, up to 24" Pipe 08/28/02 Double Strap Saddle Smith Blair #317 Nylon Coated Double Strap Saddle 07/23/12 33-12-10 Double Strap Service Saddle Mueller Company DR2S Double (SS) Strap DI Saddle AWWA C800 1"-2" SVC, up to 24" Pipe 10/27/87 Curb Stops-Ball Meter Valves McDonald 6100M,6100MT & 610MT 3/4" and 1" 10/27/87 Curb Stops-Ball Meter Valves McDonald 4603B, 4604B, 6100M, 6100TM and 6101M 1½" and 2" 5/25/2018 33-12-10 Curb Stops-Ball Meter Valves Ford Meter Box Co., Inc. FB600-7NL, FB1600-7-NL, FV23-777-W-NL, L22-77NL AWWA C800 2" 5/25/2018 33-12-10 Curb Stops-Ball Meter Valves Ford Meter Box Co., Inc. FB600-6-NL, FB1600-6-NL, FV23-666-W- NL, L22-66NL AWWA C800 1-1/2" 5/25/2018 33-12-10 Curb Stops-Ball Meter Valves Ford Meter Box Co., Inc. FB600-4-NL, FB1600-4-NL, B11-444-WR- NL, B22444-WR-NL, L28-44NL AWWA C800 1" 5/25/2018 33-12-10 Curb Stops-Ball Meter Valves Mueller Co., Ltd. B-25000N, B-24277N-3, B-20200N-3, H- 15000N, , H-1552N, H142276N AWWA C800, ANSF 61, ANSI/NSF 372 2" 5/25/2018 33-12-10 Curb Stops-Ball Meter Valves Mueller Co., Ltd. B-25000N, B-20200N-3, B-24277N-3,H- 15000N, H-14276N, H-15525N AWWA C800, ANSF 61, ANSI/NSF 372 1-1/2" 5/25/2018 33-12-10 Curb Stops-Ball Meter Valves Mueller Co., Ltd. B-25000N, B-20200N-3,H-15000N, H- 15530N AWWA C800, ANSF 61, ANSI/NSF 372 1" 01/26/00 Coated Tapping Saddle with Double SS Straps JCM Industries, Inc. #406 Double Band SS Saddle 1"-2" Taps on up to 12" 0/5/21/12 33-12-25 Tapping Sleeve (Coated Steel) JCM Industries, Inc. 412 Tapping Sleeve ESS AWWA C-223 Up to 30" w/12" Out 03/29/22 33-12-25 Tapping Sleeve (Coated or Stainless Steel) JCM Industries, Inc. 415 Tapping Sleeve AWWA C-223 Concrete Pipe Only 05/10/11 Tapping Sleeve (Stainless Steel) Powerseal 3490AS (Flange) & 3490MJ 4"-8" and 16" 02/29/12 33-12-25 Tapping Sleeve (Coated Steel) Romac FTS 420 AWWA C-223 U p to 42" w/24" Out 02/29/12 33-12-25 Tapping Sleeve (Stainless Steel) Romac SST Stainless Steel AWWA C-223 Up to 24" w/12" Out 02/29/12 33-12-25 Tapping Sleeve (Stainless Steel) Romac SST III Stainless Steel AWWA C-223 Up to 30" w/12" Out 05/10/11 Joint Repair Clamp Powerseal 3232 Bell Joint Repair Clamp 4" to 30" Plastic Meter Box w/Composite Lid DFW Plastics Inc. DFW37C-12-1EPAF FTW Plastic Meter Box w/Composite Lid DFW Plastics Inc. DFW39C-12-1EPAF FTW 08/30/06 Plastic Meter Box w/Composite Lid DFW Plastics Inc. DFW65C-14-1EPAF FTW Class "A" Concrete Meter Box Bass & Hays CMB37-B12 1118 LID-9 Concrete Meter Box Bass & Hays CMB-18-Dual 1416 LID-9 Concrete Meter Box Bass & Hays CMB65-B65 1527 LID-9 Water - Bolts, Nuts, and Gaskets 33-11-05 (01/08/13) * From Original Standard Products List 3 Approval Spec No. Classsification Manufacturer Model No. National Spec Size CITY OF FORT WORTH WATER DEPARTMENT STANDARD PRODUCT LIST Note: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes. Updated: 03/29/2022 Water - Combination Air Release 33-31-70 (01/08/13) * E1-11 Combination Air Release Valve GA Industries, Inc. Empire Air and Vacuum Valve, Model 935 ASTM A 126 Class B, ASTM A 240 - float, ASTM A 307 - Cover Bolts 1" & 2" * E1-11 Combination Air Release Valve Multiplex Manufacturing Co. Crispin Air and Vacuum Valves, Model No. 1/2", 1" & 2" * E1-11 Combination Air Release Valve Valve and Primer Corp. APCO #143C, #145C and #147C 1", 2" & 3" Water - Dry Barrel Fire Hydrants 33-12-40 (01/15/14) 10/01/87 E-1-12 Dry Barrel Fire Hydrant American-Darling Valve Drawing Nos. 90-18608, 94-18560 AWWA C-502 03/31/88 E-1-12 Dry Barrel Fire Hydrant American Darling Valve Shop Drawing No. 94-18791 AWWA C-502 09/30/87 E-1-12 Dry Barrel Fire Hydrant Clow Corporation Shop Drawing No. D-19895 AWWA C-502 01/12/93 E-1-12 Dry Barrel Fire Hydrant American AVK Company Model 2700 AWWA C-502 08/24/88 E-1-12 Dry Barrel Fire Hydrant Clow Corporation Drawings D20435, D20436, B20506 AWWA C-502 E-1-12 Dry Barrel Fire Hydrant ITT Kennedy Valve Shop Drawing No. D-80783FW AWWA C-502 09/24/87 E-1-12 Dry Barrel Fire Hydrant M&H Valve Company Shop Drawing No. 13476 AWWA C-502 10/14/87 E-1-12 Dry Barrel Fire Hydrant Mueller Company Shop Drawings No. 6461 A-423 Centurion AWWA C-502 01/15/88 E1-12 Dry Barrel Fire Hydrant Mueller Company Shop Drawing FH-12 A-423 Super Centurion 200 AWWA C-502 10/09/87 E-1-12 Dry Barrel Fire Hydrant U.S. Pipe & Foundry Shop Drawing No. 960250 AWWA C-502 09/16/87 E-1-12 Dry Barrel Fire Hydrant Waterous Company Shop Drawing No. SK740803 AWWA C-502 08/12/16 33-12-40 Dry Barrel Fire Hydrant EJ (East Jordan Iron Works) WaterMaster 5CD250 Water - Meters 02/05/93 E101-5 Detector Check Meter Ames Company Model 1000 Detector Check Valve AWWA C550 4" - 10" 08/05/04 Magnetic Drive Vertical Turbine Hersey Magnetic Drive Vertical AWWA C701, Class 1 3/4" - 6" Water - Pipes/PVC (Pressure Water) 33-31-70 (01/08/13) 01/18/18 33-11-12 PVC Pressure Pipe Vinyltech PVC Pipe DR14 AWWA C900, AWWA C605, ASTM D1784 4"-12" 3/19/2018 33 11 12 PVC Pressure Pipe Pipelife Jet Stream DR14 AWWA C900 4"-12" 3/19/2018 33 11 12 PVC Pressure Pipe Pipelife Jet Stream DR18 AWWA C900 16"-24" 5/25/2018 33 11 12 PVC Pressure Pipe Diamond Plastics Corporation DR 14 AWWA C900 4"-12" 5/25/2018 33 11 12 PVC Pressure Pipe Diamond Plastics Corporation DR 18 AWWA C900 16"-24" 12/6/2018 33 11 12 PVC Pressure Pipe J-M Manufacturing Co., Inc d/b/a JM Eagle DR 14 AWWA C900-16 UL 1285 ANSI/NSF 61 FM 1612 4"-28" 12/6/2018 33 11 12 PVC Pressure Pipe J-M Manufacturing Co., Inc d/b/a JM Eagle DR 18 AWWA C900-16 UL 1285 ANSI/NSF 61 FM 1612 16"-24" 9/6/2019 33 11 12 PVC Pressure Pipe Underground Solutions Inc. DR14 Fusible PVC AWWA C900 4" - 8" 9/6/2019 33 11 12 PVC Pressure Pipe NAPCO(Westlake) DR18 AWWA C900 16" - 24" 9/6/2019 33 11 12 PVC Pressure Pipe NAPCO(Westlake) DR14 AWWA C900 4"- 12" 9/6/2019 33 11 12 PVC Pressure Pipe Sanderson Pipe Corp. DR14 AWWA C900 4"- 12" Water - Pipes/Valves & Fittings/Ductile Iron Fittings 33-11-11 (01/08/13) 07/23/92 E1-07 Ductile Iron Fittings Star Pipe Products, Inc. Mechanical Joint Fittings AWWA C153 & C110 * E1-07 Ductile Iron Fittings Griffin Pipe Products, Co. Mechanical Joint Fittings AWWA C 110 * E1-07 Ductile Iron Fittings McWane/Tyler Pipe/ Union Utilities Division Mechanical Joint Fittings, SSB Class 350 AWWA C 153, C 110, C 111 08/11/98 E1-07 Ductile Iron Fittings Sigma, Co. Mechanical Joint Fittings, SSB Class 351 AWWA C 153, C 110, C 112 02/26/14 E1-07 MJ Fittings Accucast Class 350 C-153 MJ Fittings AWWA C153 4"-12" 05/14/98 E1-07 Ductile Iron Joint Restraints Ford Meter Box Co./Uni-Flange Uni-Flange Series 1400 AWWA C111/C153 4" to 36" 05/14/98 E1-24 PVC Joint Restraints Ford Meter Box Co./Uni-Flange Uni-Flange Series 1500 Circle-Lock AWWA C111/C153 4" to 24" 11/09/04 E1-07 Ductile Iron Joint Restraints One Bolt, Inc. One Bolt Restrained Joint Fitting AWWA C111/C116/C153 4" to 12" 02/29/12 33-11-11 Ductile Iron Pipe Mechanical Joint Restraint EBAA Iron, Inc.Megalug Series 1100 (for DI Pipe)AWWA C111/C116/C153 4" to 42" 02/29/12 33-11-11 PVC Pipe Mechanical Joint Restraint EBAA Iron, Inc.Megalug Series 2000 (for PVC Pipe)AWWA C111/C116/C153 4" to 24" 08/05/04 E1-07 Mechanical Joint Retainer Glands(PVC) Sigma, Co. Sigma One-Lok SLC4 - SLC10 AWWA C111/C153 4" to 10" 03/06/19 33-11-11 Mechanical Joint Retainer Glands(PVC) Sigma, Co. Sigma One-Lok SLCS4 - SLCS12 AWWA C111/C153 4" to 12" 08/05/04 E1-07 Mechanical Joint Retainer Glands(PVC) Sigma, Co. Sigma One-Lok SLCE AWWA C111/C153 12" to 24" 08/10/98 E1-07 MJ Fittings(DIP) Sigma, Co. Sigma One-Lok SLDE AWWA C153 4" - 24" 10/12/10 E1-24 Interior Restrained Joint System S & B Techncial Products Bulldog System ( Diamond Lok 21 & JM ASTM F-1624 4" to 12" 08/16/06 E1-07 Mechanical Joint Fittings SIP Industries(Serampore) Mechanical Joint Fittings AWWA C153 4" to 24" 11/07/16 33-11-11 Mechanical Joint Retainer Glands Star Pipe Products, Inc.PVC Stargrip Series 4000 ASTM A536 AWWA C111 11/07/16 33-11-11 Mechanical Joint Retainer Glands Star Pipe Products, Inc.DIP Stargrip Series 3000 ASTM A536 AWWA C111 03/19/18 33-11-11 Mechanical Joint Retainer Glands SIP Industries(Serampore)EZ Grip Joint Restraint (EZD) Black For DIP ASTM A536 AWWA C111 3"-48" 03/19/18 33-11-11 Mechanical Joint Retainer Glands SIP Industries(Serampore)EZ Grip Joint Restraint (EZD) Red for C900 DR14 PVC Pipe ASTM A536 AWWA C111 4"-12" 03/19/18 33-11-11 Mechanical Joint Retainer Glands SIP Industries(Serampore)EZ Grip Joint Restraint (EZD) Red for C900 DR18 PVC Pipe ASTM A536 AWWA C111 16"-24" * From Original Standard Products List 4 Approval Spec No. Classsification Manufacturer Model No. National Spec Size CITY OF FORT WORTH WATER DEPARTMENT STANDARD PRODUCT LIST Note: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes. Updated: 03/29/2022 Water - Pipes/Valves & Fittings/Resilient Seated Gate Valve* 33-12-20 (05/13/15) Resilient Wedged Gate Valve w/no Gears American Flow Control Series 2500 Drawing # 94-20247 16" 12/13/02 Resilient Wedge Gate Valve American Flow Control Series 2530 and Series 2536 AWWA C515 30" and 36" 08/31/99 Resilient Wedge Gate Valve American Flow Control Series 2520 & 2524 (SD 94-20255) AWWA C515 20" and 24" 05/18/99 Resilient Wedge Gate Valve American Flow Control Series 2516 (SD 94-20247) AWWA C515 16" 10/24/00 E1-26 Resilient Wedge Gate Valve American Flow Control Series 2500 (Ductile Iron)AWWA C515 4" to 12" 08/05/04 Resilient Wedge Gate Valve American Flow Control 42" and 48" AFC 2500 AWWA C515 42" and 48" 05/23/91 E1-26 Resilient Wedge Gate Valve American AVK Company American AVK Resilient Seaded GV AWWA C509 4" to 12" 01/24/02 E1-26 Resilient Wedge Gate Valve American AVK Company 20" and smaller * E1-26 Resilient Seated Gate Valve Kennedy 4" - 12" * E1-26 Resilient Seated Gate Valve M&H 4" - 12" * E1-26 Resilient Seated Gate Valve Mueller Co.4" - 12" 11/08/99 Resilient Wedge Gate Valve Mueller Co. Series A2361 (SD 6647) AWWA C515 16" 01/23/03 Resilient Wedge Gate Valve Mueller Co. Series A2360 for 18"-24" (SD 6709) AWWA C515 24" and smaller 05/13/05 Resilient Wedge Gate Valve Mueller Co. Mueller 30" & 36", C-515 AWWA C515 30" and 36" 01/31/06 Resilient Wedge Gate Valve Mueller Co. Mueller 42" & 48", C-515 AWWA C515 42" and 48" 01/28/88 E1-26 Resilient Wedge Gate Valve Clow Valve Co. AWWA C509 4" - 12" 10/04/94 Resilient Wedge Gate Valve Clow Valve Co. 16" RS GV (SD D-20995) AWWA C515 16" 11/08/99 E1-26 Resilient Wedge Gate Valve Clow Valve Co. Clow RW Valve (SD D-21652) AWWA C515 24" and smaller 11/29/04 Resilient Wedge Gate Valve Clow Valve Co. Clow 30" & 36" C-515 AWWA C515 30" and 36" (Note 3) 11/30/12 Resilient Wedge Gate Valve Clow Valve Co. Clow Valve Model 2638 AWWA C515 24" to 48" (Note 3) 05/08/91 E1-26 Resilient Seated Gate Valve Stockham Valves & Fittings AWWA C 509, ANSI 420 - stem, ASTM A 276 Type 304 - Bolts & nuts 4" - 12" * E1-26 Resilient Seated Gate Valve U.S. Pipe and Foundry Co.Metroseal 250, requirements SPL #74 3" to 16" 10/26/16 33-12-20 Resilient Seated Gate Valve EJ (East Jordan Iron Works)EJ FlowMaster Gate Valve & Boxes 08/24/18 Matco Gate Valve Matco-Norca 225 MR AWWA/ANSI C115/An21.15 4" to 16" Water - Pipes/Valves & Fittings/Rubber Seated Butterfly Valve 33-12-21 (07/10/14) * E1-30 Rubber Seated Butterfly Valve Henry Pratt Co. AWWA C-504 24" * E1-30 Rubber Seated Butterfly Valve Mueller Co. AWWA C-504 24"and smaller 1/11/99 E1-30 Rubber Seated Butterfly Valve Dezurik Valves Co. AWWA C-504 24" and larger 06/12/03 E1-30 Valmatic American Butterfly Valve Valmatic Valve and Manufacturing Corp. Valmatic American Butterfly Valve. AWWA C-504 Up to 84" diameter 04/06/07 E1-30 Rubber Seated Butterfly Valve M&H Valve M&H Style 4500 & 1450 AWWA C-504 24" to 48" 03/19/18 33 12 21 Rubber Seated Butterfly Valve G. A. Industries (Golden Anderson) AWWA C504 Butterfly Valve AWWA C-504 30"-54" Water - Polyethylene Encasement 33-11-10 (01/08/13) 05/12/05 E1-13 Polyethylene Encasment Flexsol Packaging Fulton Enterprises AWWA C105 8 mil LLD 05/12/05 E1-13 Polyethylene Encasment Mountain States Plastics (MSP) and AEP Ind. Standard Hardware AWWA C105 8 mil LLD 05/12/05 E1-13 Polyethylene Encasment AEP Industries Bullstrong by Cowtown Bolt & Gasket AWWA C105 8 mil LLD 09/06/19 33-11-11 Polyethylene Encasment Northtown Products Inc. PE Encasement for DIP AWWA C105 8 mil LLD Water - Sampling Station 3/12/96 Water Sampling Station Water Plus B20 Water Sampling Station Water - Automatic Flusher 10/21/20 Automated Flushing System Mueller Hydroguard HG6-A-IN-2-BRN-LPRR(Portable) HG2-A-IN--2-PVC-018-LPLG(Permanent) 04/09/21 Automated Flushing System Kupferle Foundry Company Eclipse #9800wc 04/09/21 Automated Flushing System Kupferle Foundry Company Eclipse #9700 (Portable) * From Original Standard Products List 5 FORT WORTH. CITY OF FORT WORTH TRANSPORTATION/PUBLIC WORKS DEPARTMENT STANDARD PRODUCTS LIST AS OF 12/01/2022 Approval Spec No. Classification Manufacturer \lodcl \o. National Spec Concrete 9/9/2022 03 30 00 Mix Design American Concrete Company 9/9/2022 03 30 00 Mix Design American Concrete Company 9/9/2022 03 30 00 Mix Design American Concrete Company 9/9/2022 03 30 00 Mix Design American Concrete Company 9/9/2022 03 30 00 Mix Design Argos 9/9/2022 03 30 00 Mix Design Argos 9/9/2022 03 30 00 Mix Design Argos 9/9/2022 03 30 00 Mix Design Argos 9/9/2022 03 30 00 Mix Design Argos 9/9/2022 03 30 00 Mix Design Argos 9/9/2022 03 30 00 Mix Design Argos 9/9/2022 03 30 00 Mix Design Argos 9/9/2022 03 30 00 Mix Design Argos 9/9/2022 03 30 00 Mix Design Argos 9/9/2022 03 30 00 Mix Design Argos 9/9/2022 03 30 00 Mix Design Argos 9/9/2022 03 30 00 Mix Design Argos 9/9/2022 03 30 00 Mix Design Argos 9/9/2022 03 30 00 Mix Design Argos 9/9/2022 03 30 00 Mix Design Argos 9/9/2022 03 30 00 Mix Design Argos 9/9/2022 03 30 00 Mix Design Argos 9/9/2022 03 30 00 Mix Design Argos 9/9/2022 03 30 00 Mix Design Big D Concrete 9/9/2022 03 30 00 Mix Design Big D Concrete 9/9/2022 03 30 00 Mix Design Big Town Concrete 9/9/2022 03 30 00 Mix Design Big Town Concrete 9/9/2022 03 30 00 Mix Design Burnco Texas 9/9/2022 03 30 00 Mix Design Burnco Texas 9/9/2022 03 30 00 Mix Design Burnco Texas 9/9/2022 03 30 00 Mix Design Burnco Texas 9/9/2022 03 30 00 Mix Design Burnco Texas 9/9/2022 03 30 00 Mix Design Burnco Texas 9/9/2022 03 30 00 Mix Design Burnco Texas 9/9/2022 03 30 00 Mix Design Burnco Texas 9/9/2022 03 30 00 Mix Design Burnco Texas 9/9/2022 03 30 00 Mix Design Burnco Texas 9/9/2022 03 30 00 Mix Design Carder Concrete 9/9/2022 03 30 00 Mix Design Carder Concrete 9/9/2022 03 30 00 Mix Design Carder Concrete 9/9/2022 03 30 00 Mix Design Carder Concrete 9/9/2022 03 30 00 Mix Design Carder Concrete 9/9/2022 03 30 00 Mix Design Carder Concrete 9/9/2022 03 30 00 Mix Design Carder Concrete 9/9/2022 03 30 00 Mix Design Carder Concrete 9/9/2022 03 30 00 Mix Design Charley's Concrete 9/9/2022 03 30 00 Mix Design Charley's Concrete 9/9/2022 03 30 00 Mix Design Charley's Concrete 9/9/2022 03 30 00 Mix Design Charley's Concrete 9/9/2022 03 30 00 Mix Design Charley's Concrete 9/9/2022 03 30 00 Mix Design Charley's Concrete 9/9/2022 03 30 00 Mix Design Charley's Concrete 9/9/2022 03 30 00 Mix Design Charley's Concrete 9/9/2022 03 30 00 Mix Design Charley's Concrete 9/9/2022 03 30 00 Mix Design Charley's Concrete 9/9/2022 03 30 00 Mix Design Charley's Concrete 9/9/2022 03 30 00 Mix Design Charley's Concrete 9/9/2022 03 30 00 Mix Design Chisholm Trail Redi Mix 9/9/2022 03 30 00 Mix Design City Concrete Company 30CAF029 3000 psi Concrete for Sidewalks & ADA Ramps 01JAF382 1000 psi Concrete Base Material for Trench Repair 40CNF065 4000 psi Concrete for Manholes & Utility Structures 45CAF076 4500 psi Concrete for Hand Placed Paving D10000001737 4500 psi Concrete for Hand Placed Paving D10000001791 4500 psi Concrete for Hand Placed Paving D10000001793 4500 psi Concrete for Hand Placed Paving D10000001103 4500 psi Concrete for Hand Placed Paving D10000002107 4500 psi Concrete for Hand Placed Paving D10000001273 4500 psi Concrete for Hand Placed Paving D10000001617 3600 psi Concrete for Machine Placed Paving D10000008381 4500 psi Concrete for HES Paving D10000009857 50 psi Flowable Fill - CLSM D10000001055 3000 psi Concrete for Inlets, Junction Boxes, Manholes, Channel Liners, Sidewalks, Driveways, Curb & Gutter D1000001043S 3000 psi Concrete for Sidewalks, Curbs D1000001565S 3000 psi Concrete for Curbs, Curb & Gutters, Sidewalks, Driveways, ADA Ramps D1000001615 3600 psi Concrete for Inlets, Boxes, Encasement, Blocking D10000001061 3600 psi Concrete for Inlets, Boxes, Encasement, Blocking D10000001083S 4000 psi Concrete for Valve Pads, Inlets, Structures, Headwalls, Thrust Blocking D10000001083 4000 psi Concrete for Valve Pads, Inlets, Structures, Headwalls, Thrust Blocking D10000001685 4000 psi Concrete for Valve Pads D10000005751 750 Psi Concrete Base for Trench Repair D10000001681 4000 psi Concrete for Headwalls, Retaining Walls, Box Culverts, Valley Gutters 7SKGRT 3000 psi Concrete for Grouting 14500AE 4500 psi Concrete for High Early Strength Paving 452065-1 4500 psi hand placed paving 450065-1 4500 psi hand placed paving 45U500BG 4500 psi Concrete Mix for Hand Placed Paving, Storm Structures 40U553BG 4000 psi Concrete Mix for Machine Placed Paving 55U120AG 4000 psi Concrete Mix for High Early Strength Paving 30U100AG 3000 psi Concrete Mix for Pipe Collars, Inlets, Thrust Blocks, Sidewalks, ADA Ramps 30U101AG 3000 psi Concrete Mix for Flatwork 30U500BG 3000 psi Concrete Mix for Blocking, Driveways, Curb & Gutters, Sidewalks, ADA Ramps 40U500BG 4000 psi Concrete Mix for Storm Drain Structures, Driveways, Screen Walls 36U500BG 3600 psi Concrete Mix for Lighting and Traffic Signal Foundations 08Y450BA 800 psi Concrete Mix for Base for Trench Repair 01Y690BF 100 psi Concrete Mix for Flowable Fill FWCC602021 4500 psi concrete for Hand Placed Paving FWCC552091 3600 psi for Machine Placed Paving FWCC602091 3600 psi for Machine Placed Paving FWCC359101 Flowable Fill - CLSM FWFF237501 Flowable Fill - CLSM FWCC602001 4000 psi Concrete for Storm Drain Structures, Manholes, Headwalls, Retaining Walls, Valley Gutters, Drive Approaches, Lighting & Traffic Signal Foundations FWCC502021 3500 psi concrete for Sidewalks, Driveways, Ramps, Curb & Gutter FWCC502001 3000 psi for Sidewalks, Driveways, Ramps, Curb & Gutter, Flatwork 4142 3600 psi Concrete for Curb Inlets, Junction Boxes 4518 4000 psi Concrete for Headwalls, Wingwalls 5167 3600 psi Concrete Mix for Machine Placed Paving 4609 4500 psi Concrete Mix for Hand Placed Paving, Manholes 6103 4500 psi Concrete Mix for Hand Placed Paving, Manholes 4502 3000 psi Concrete Mix for Sidewalks 3759 3000 psi Concrete Mix for Sidewalks 1502 150 psi Concrete for Flowable Fill-CLSM 1518 150 Psi Concrete for Flowable Fill-CLSM 5642 4000 psi Concrete for Storm Drain Structures 6595 5000 psi Concrete Mix for High Early Strength Paving 6589 4500 psi Concrete Mix for High Early Strength Paving C13020AE 3000 psi Concrete for Driveways, Curb & Gutter 11-350-FF 50-150 psi Concrete for Flowable Fill-CLSM FORT WORTH. CITY OF FORT WORTH TRANSPORTATION/PUBLIC WORKS DEPARTMENT STANDARD PRODUCTS LIST AS OF 12/01/2022 Approval Spec No. Classification Manufacturer \lodcl \o. National Spec Concrete (Cot tined) 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 11/16/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 34 13 Mix Design 9/9/2022 03 34 13 Mix Design 9/9/2022 03 34 13 Mix Design 9/9/2022 03 34 13 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 11/14/2022 32 13 13 Mix Design 9/9/2022 33 13 13 Mix Design 9/9/2022 34 13 13 Mix Design 9/9/2022 35 13 13 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design City Concrete Company City Concrete Company City Concrete Company City Concrete Company City Concrete Company City Concrete Company City Concrete Company City Concrete Company City Concrete Company Cow Town Redi Mix Cow Town Redi Mix Cow Town Redi Mix Cow Town Redi Mix Cow Town Redi Mix Cow Town Redi Mix Cow Town Redi Mix Cow Town Redi Mix Cow Town Redi Mix Cow Town Redi Mix Cow Town Redi Mix Cow Town Redi Mix Cow Town Redi Mix Cow Town Redi Mix Cow Town Redi Mix Cow Town Redi Mix Cow Town Redi Mix Cow Town Redi Mix Cow Town Redi Mix Cow Town Redi Mix Cow Town Redi Mix Cow Town Redi Mix Cow Town Redi Mix Cow Town Redi Mix Cow Town Redi Mix Cow Town Redi Mix Cow Town Redi Mix Cow Town Redi Mix Cow Town Redi Mix Cow Town Redi Mix Cow Town Redi Mix Cow Town Redi Mix Cow Town Redi Mix Cow Town Redi Mix Cow Town Redi Mix Cow Town Redi Mix Cow Town Redi Mix GCH Concrete Services GCH Concrete Services GCH Concrete Services Ingram Concrete & Aggregates Ingram Concrete & Aggregates Ingram Concrete & Aggregates Ingram Concrete & Aggregates Ingram Concrete & Aggregates Ingram Concrete & Aggregates Ingram Concrete & Aggregates Ingram Concrete & Aggregates Ingram Concrete & Aggregates Holcim - SOR, Inc. Holcim - SOR, Inc. Holcim - SOR, Inc. 30HA25II 3000 psi Concrete for Rip -Rap 30HA20II 3000 psi Concrete Mix for Blocking, Sidewalks, Flatwork, Pads 45NG2511 3600 psi Concrete Mix for Drilled Shafts 50QG2511 3600 psi Slurry Displaced Drilled Shaft 45NA20I14500 psi Concrete Mix for Hand Placed Paving 36LA2011 3600 psi Concrete Mix for Machine Placed Paving 36JA001J 3600 psi Concrete Mix for Machine Placed Paving 40LA2011 4000 psi Concrete Mix for Storm Drain Structures CLNG25II 3600 psi concrete for Drilled Shaft 250 3000 psi Concrete Mix for Sidewalks, Driveways, ADA Ramps 350 3000 psi Concrete Mix for Sidewalks, Driveways, ADA Ramps 9 70 psi Flowable Fill - CLSM 9-S-2 70 psi Flowable Fill - CLSM 220-8 50 psi Concrete Mix for Flowable Fill - CLSM 320-8 50 psi Concrete Mix for Flowable Fill - CLSM 230-8 750 psi Concrete Base Material for Trench Repair 330-S8 750 psi Concrete Base Material for Trench Repair 353 3000 psi Concrete Mix for Sidewalks, ADA Ramps, Driveways, Curb & Gutter, Safety End Treatments, Non-TxDOT Retaining Walls 253-W 3000 psi Concrete Mix Sidewalks, ADA Ramps, Driveways, Curb & Gutter, Safety End Treatments, Non-TxDOT Retaining Walls 260 4000 psi Concrete Mix for Bridge Slabs, Box Culverts, Headwalls, Lighting and Traffic Signal Foundations 260-1 3600 psi Concrete Mix for Headwalls 260-2 3600 psi Concrete Mix for Box Culverts, Headwalls, Lighting and Traffic Signal Foundations 360 4000 psi Concrete Mix for Bridge Slabs, Box Culverts, Headwalls, Lighting & Traffic Signal Foundations 360-1 3600 psi Concrete Mix for Box Culverts, Headwalls, Wingwalls 264-N 4500 psi Concrete Mix for Hand Placed Paving 366 4500 psi Concrete Mix for Hand Placed Paving 265 4500 psi Concrete Mix for Hand Placed Paving 365 4500 psi Concrete Mix for Hand Placed Paving 370-NC 4500 psi Concrete for HES Paving 370-1NC 5000 psi Concrete for HES Paving 375-NC 5000 psi Concrete for HES Paving 267 4200 psi Concrete Mix for Manholes and Drainage Structures 270 5000 psi Concrete Mix for Cast -in -Place Box Culverts 370 5000 psi Concrete Mix for Cast -in -Place Box Culverts 255-2 3000 psi Concrete Mix for Inlets, Thrust Blocking, Concrete Encasement 257 3600 psi Concrete mix for Valley Gutters 357-M 3600 psi Concrete Mix for Machine Placed Paving 257-M 3600 psi Concrete Mix for Machine Placed Paving 260-M 4000 psi Concrete Mix for Machine Placed Paving 360-M 4000 psi Concrete Mix for Machine Placed Paving 255-LP 3000 psi Concrete Mix for Curb & Gutter 355-LP 3000 psi Concrete Mix for Curb & Gutter 255 3500 psi Concrete Mix for Flatwork, Inlets, Thrust Blocking Concrete Encasement 355 3000 psi Concrete Mix for Inlets, Thrust Blocking, Concrete Encasement 365-STX 4000 psi Concrete for Bridge slabs, top slabs of direct traffic culverts, approach slabs 357 3600 psi Concrete Mix for Valley Gutters GCH4000 4000 psi Concrete for for Sidewalks, Ramps, Headwalls, Inlets, and Storm Drain Structures GCHVS 4000 psi Concrete for Machine Placed Paving GCH4500 4500 psi Concrete Hand Placed Paving C47PV5E5 3000 psi Concrete for Sidewalks, ADA Ramps 2MWR-70J23504 3000 psi Concrete for Sidewalks, ADA Ramps 2MWR-147QW5D5 3000 psi Concrete Mix for Sidewalks, ADA Ramps 2MWR-056PS5D5 4000 psi Concrete Machine Placed Paving 2MWR-161UV5DM 4500 psi Concrete for Hand Placed Paving 2MWR-10MQS50N 4500 psi Concrete for Hand Placed Paving 161 PSSEM 4500 psi Concrete for Hand Placed Paving C47PV5E5 3000 psi Concrete Mix for Sidewalks, ADA Ramps 161 PSSEM 4500 psi Concrete Mix for Hand Placed Paving 5177 3000 psi Concrete Mix for Sidewalks 1261 3000 psi Concrete Mix for Sidewalks 1551 3000 psi Concrete Mix for Blocking FORT WORTH. CITY OF FORT WORTH TRANSPORTATION/PUBLIC WORKS DEPARTMENT STANDARD PRODUCTS LIST AS OF 12/01/2022 Approval Spec No. Classification Manufacturer Model So. National Spec Concrete(Con'inued) 9/9/2022 4 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 04 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 12/5/2022 4 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 34 13 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 11/2/2022 32 13 13 Mix Design 11/2/2022 32 13 13 Mix Design 11/2/2022 32 13 13 Mix Design 11/15/2022 33 13 13 Mix Design 11/15/2022 34 13 13 Mix Design 11/2/2022 32 13 13 Mix Design 11/2/2022 32 13 13 Mix Design 11/2/2022 32 13 13 Mix Design 11/2/2022 32 13 13 Mix Design 11/2/2022 32 13 13 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 34 13 Mix Design Holcim - SOR, Inc. Holcim - SOR, Inc. Holcim - SOR, Inc. Holcim - SOR, Inc. Holcim - SOR, Inc. Holcim - SOR, Inc. Holcim - SOR, Inc. Holcim - SOR, Inc. Holcim - SOR, Inc. Martin Marietta Martin Marietta Martin Marietta Martin Marietta Martin Marietta Martin Marietta Martin Marietta Martin Marietta Martin Marietta Martin Marietta Martin Marietta Martin Marietta Martin Marietta Martin Marietta Martin Marietta Martin Marietta Martin Marietta Martin Marietta Martin Marietta Martin Marietta Martin Marietta Martin Marietta Martin Marietta Martin Marietta Martin Marietta Martin Marietta Martin Marietta Martin Marietta Martin Marietta Martin Marietta Martin Marietta Martin Marietta Martin Marietta Martin Marietta Martin Marietta Martin Marietta Martin Marietta Martin Marietta Martin Marietta Martin Marietta Martin Marietta Martin Marietta Martin Marietta NCS Redi Mix NCS Redi Mix NBR Ready Mix NBR Ready Mix Redi-Mix Redi-Mix Redi-Mix 2125 4500 psi Concrete for HES Paving 1701 4000 psi Concrete Mix for Storm Drain Structures, Sanitary Sewer Manholes 5409 4000 psi Concrete Mix for Sidewalks, Inlets 5507 4500 psi Concrete Mix for Hand Placed Paving 5017 200 psi Concrete for Base Material for Trench Repair 9600 3600 psi Concrete for Drill Shafts 1851 4500 psi Concrete for Storm Drain Structures, Hand Placed Paving 1822 3600 psi Concrete for Drilled Shafts 1859 4000 psi Concrete for Drilled Shafts R2131014 3000 psi Concrete for Sidewalks & Ramps R2132214 3,000 psi Concrete for Sidewalks & Ramps D9490SC 3,000 psi Concrete for Sidewalks & Ramps R2131214 3,000 psi Concrete for Sidewalks & Ramps R2131314 3,000 psi Concrete for Sidewalks & Ramps R2136014 3,000 psi Concrete for Sidewalks & Ramps R2136214 3,000 psi Concrete for Sidewalks & Ramps R2141224 4,000 psi Concrete for Sidewalks & Ramps R2141024 4,000 psi Concrete for Sidewalks & Ramps R2136224 3,600 psi Concrete for Curb Inlets R2141233 3,600 psi Concrete for Storm Structures, Inlets, Blocking & Encasement FLOW25A 50 psi Concrete for Flowable Fill/CLSM R2142233 3,600 psi Concrete for Manholes, Inlets & Headwalls R2146333 3,600 psi Concrete for Manholes, Inlets & Headwalls, Concrete Encasement R21412304,000 psi Concrete for Manholes, Inlets & Headwalls, Valve Pads R2146035 4,000 psi Concrete for Manholes, Inlets & Headwalls, Valve Pads R2146335 4,500 psi Concrete for Hand Placed Paving, Inlets, Storm Drain Structures R2146034 4,500 psi Concrete for Manholes, Inlets & Headwalls, Hand Placed Paving R214123 4,000 psi Concrete for Inlets, Manholes, Headwalls R2141231 4,000 psi Concrete for Inlets, Sidewalks R2161070 6,000 (3,000 @ 24-hrs.) psi Concrete for HES Paving D9492SFC 4,000 psi Concrete for Machine Placed Paving R2146233 4,500 psi Concrete for Hand Placed Paving R2146238 4,500 psi Concrete for Hand Placed Paving, Inlets, Storm Drain Structures R2146336 4,500 psi Concrete for Hand Placed Paving R2146235 4,500 psi Concrete for Hand Placed Paving Q2141N27 4,000 psi Concrete for Machine Placed paving Q2141K30 4,000 psi Concrete for Machine Placed Paving R2146N36 4,500 psi Concrete for Hand Placed Paving R2146K36 4,500 psi Concrete for Hand Placed Paving R2146P36 4,500 psi Concrete for Hand Placed Paving R2146K36 4,500 psi Concrete for Hand Placed Paving R2146N35 4,000 psi Concrete for Inlets, Manholes, Headwalls R2146K34 4,000 psi Concrete for Inlets, Manholes, Headwalls R2141N24 4,000 psi Concrete for Sidewalks and Ramps R2141K24 4,000 psi Concrete for Sidewalks and Ramps R2146038 4,500 psi Concrete for Inlets, Storm Drain Structures R2146036 4,500 psi Concrete for Hand Placed Paving, Inlets R2146042 4,500 psi Concrete for Hand Placed Paving R2146242 4,500 psi Concrete for Hand Placed Paving R2146236 4,500 psi Concrete for Hand Placed Paving D9493SC 4,500 psi Concrete for Hand Placed Paving R2147241 4,500 psi Concrete for Hand Placed Paving NCS5020A 3000 psi Concrete Mix for Curb & Gutter, Driveways, Sidewalks NCS6020AHP 4500 psi Concrete Mix for Valley Gutters, Hand Placed Paving TX C-YY 3000 psi Concrete Mix for Curb Inlets TX C-NY 3000 psi Concrete Mix for Curb Inlets DCA2E554 3000 psi Concrete Mix for Rip Rap VOJ11524 3000 psi Concrete Mix for Curb & Gutter FOC10021 215 psi Flowable Fill - CLSM FORT WORTH. CITY OF FORT WORTH TRANSPORTATION/PUBLIC WORKS DEPARTMENT STANDARD PRODUCTS LIST AS OF 12/01/2022 Approval Spec No. Classification Manufacturer Model No. National Spec Concrete(Con'inued) 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/29/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/29/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 34 13 Mix Design 9/9/2022 03 34 13 Mix Design 9/9/2022 03 34 13 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 11/2/2022 03 30 00 Mix Design 12/5/2022 03 30 00 Mix Design 12/5/2022 03 30 00 Mix Design 12/5/2022 03 30 00 Mix Design 9/9/2022 03 34 13 Mix Design 9/9/2022 03 34 13 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 10/10/2022 03 30 00 Mix Design 10/10/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 34 13 Mix Design 9/9/2022 03 34 13 Mix Design 9/9/2022 03 30 00 Mix Design 10/10/2022 03 30 00 Mix Design 10/10/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design 9/9/2022 03 30 00 Mix Design Redi-Mix Redi-Mix Redi-Mix Redi-Mix Redi-Mix Redi-Mix Redi-Mix Redi-Mix Redi-Mix Redi-Mix Redi-Mix Redi-Mix Redi-Mix Redi-Mix Redi-Mix Redi-Mix Redi-Mix Redi-Mix Redi-Mix Redi-Mix Redi-Mix Redi-Mix Redi-Mix Redi-Mix Redi-Mix Redi-Mix Redi-Mix SRM Concrete SRM Concrete SRM Concrete SRM Concrete SRM Concrete SRM Concrete SRM Concrete SRM Concrete SRM Concrete SRM Concrete SRM Concrete Tarrant Concrete Tarrant Concrete Tarrant Concrete Tarrant Concrete Tarrant Concrete Tarrant Concrete Tarrant Concrete Tarrant Concrete Tarrant Concrete Tarrant Concrete Tarrant Concrete Tarrant Concrete Tarrant Concrete Tarrant Concrete Tarrant Concrete Titan Ready Mix Titan Ready Mix True Grit Redi Mix True Grit Redi Mix True Grit Redi Mix True Grit Redi Mix True Grit Redi Mix True Grit Redi Mix 10J11524 3000 psi Concrete Mix for Driveways, Sidewalks, ADA Ramps 10J11504 3000 psi Concrete Mix for Sidewalks 10L11504 3,600 psi Concrete Mix for Sidewalks, Curb & Gutter 10L11524 3600 psi Concrete Mix Manholes, Inlets, Junction Boxes, Headwalls 1RJ11524 3500 psi Concrete Mix for Thrust Blocks, Valve Pads 10L21524 4000 psi Concrete Mix for Manholes 15611524 4000 psi Concrete Mix for Cast -in -Place Storm Drain Structures 10L115E4 3600 psi Concrete Mix for Bridge substructures DCC2G5E2 3600 psi Concrete Mix for Drilled Shafts DCUIG5E2 3600 psi Underwater Drilled Shafts 156115D4 4000 psi Bridge Slabs F35238VN 100 psi Flowable Fill - CLSM FOD138VM 100 psi Flowable Fill - CLSM 10J11554 3000 psi Concrete Mix for Rip -Rap POG138K9 1000 psi Concrete Mix for Trench Repair Base Material 10K11524 3600 psi Concrete Mix for Encasement 10N11507 4500 psi (2600 psi @ 24 hrs.) Concrete Mix for HES Paving 10N11504 5000 psi (3600 psi @ 2 days) Concrete Mix for HES Paving 50K11524 3600 psi Concrete Mix for Machine Placed Paving 10M115D4 4500 psi Concrete Mix for Hand Placed Paving, Storm Drain Structures 10M11524 4500 psi Concrete Mix for Hand Placed Paving 10M11504 4500 psi Concrete Mix for Hand Placed Paving 145CD5P4 4500 psi Concrete Mix for Hand Placed Paving, Storm Drain Structures 145P25P4 4500 psi Concrete for Storm Drain Structures 10K115C4 3500 psi Concrete for Thrust Blocks, Valve Pads 156115C4 4000 psi Concrete for CIP Storm Drain Structures 10L115C4 3600 psi Concrete for Manhole, Inlet, Junction Box, Headwall 30000 3,000 psi Concrete for Sidewalks and Ramps, Curb & Gutter 40050 4,000 psi Concrete for Headwalls 35023 3,600 psi Concrete for Machine Placed Paving 40068 3,600 psi Concrete for Machine Placed Paving 45000 4,500 psi Concrete for Hand Placed Paving 45300 4,500 psi Concrete for Hand Placed Paving 40326 4,500 (3,00 @ 3-days) psi Concrete for HES Paving 35000 3600 psi Concrete for Sewer Manholes 35300 3600 psi Concrete for Swere Manholes 35022 3,600 psi Concrete for Junction Box 30050 3,000 psi Concrete for Sidewalks, Inlets, Junction Boxes, Thrust Blocks FW6020AHP 4500 psi Concrete Mix for Hand Placed Paving FW60AHP 4500 psi Concrete Mix for Hand Placed Paving TCFW6020AHP 4500 psi Concrete Mix for Hand Placed Paving FW7520AMR 4500 (3000 psi @ 3-days) psi Concrete HES Paving FW6520AMR 4500 (3000 psi @ 3-days) psi HES Paving FW5520AMP 3600 psi Concrete for Machine Placed Paving FW5320A 3000 psi Concrete Mix for Blocking FWFF150CLSM 50-150 psi Flowable Fill - CLSM FWFF275 50-150 psi Flowable Fill - CLSM FW6020A2 4000 psi Concrete Mix for Storm Drain Structures TCFW6025A2 4000 psi Concrete for Manholes TCFW5020A 3000 psi Concrete for Sidewalks FW5025A 3000 psi Concrete Mix for Curb & Gutter, Driveways, Sidewalks, ADA Ramps CP5020A 3000 psi Concrete Mix for Curb and Gutter FW5525A2 3600 psi Concrete Mix for Sidewalks, Drive Approaches, ADA Ramp 3020AE 3000 psi Concrete for Sidewalks TRC4520 4500 psi Concrete for Hand Placed Paving 0250.230 3000 psi Concrete Mix for Flatwork, Curb & Gutter, Driveways, Sidewalks, ADA Ramps 270.230 5000 psi Concrete for Hand Placed Paving 0250.2301 3000 psi Concret Mix for Curb & Gutter, Driveways, Sidewalks, ADA Ramps 0260.2302 4000 psi Concrete Mix for Machine Placed Paving 0255.2301 3600 psi Concrete Mix for Machine Placed Paving 0260.2301 4500 psi Concrete Mix for Hand Placed Paving FORT WORTH. CITY OF FORT WORTH TRANSPORTATION/PUBLIC WORKS DEPARTMENT STANDARD PRODUCTS LIST AS OF 12/01/2022 Approval Spec No. Classification 9/9/2022 9/9/2022 9/9/2022 9/9/2022 9/9/2022 9/9/2022 9/9/2022 9/9/2022 9/9/2022 9/9/2022 9/9/2022 11/26/2022 12/5/2022 9/9/2022 9/9/2022 9/9/2022 9/9/2022 9/9/2022 9/9/2022 9/9/2022 9/9/2022 9/9/2022 9/9/2022 9/9/2022 Concrete(Continued) 03 30 00 IMix Design 03 30 00 I Mix Design Asphalt Pavia ; 32 12 16 Mix Design 32 12 16 Mix Design 32 12 16 Mix Design 32 12 16 Mix Design 32 12 16 Mix Design 32 12 16 Mix Design 32 12 16 Mix Design 32 12 16 Mix Design 32 12 16 Mix Design 32 12 16 Mix Design 33 12 16 Mix Design 32 12 16 Mix Design 32 12 16 Mix Design 32 12 16 Mix Design 32 12 16 Mix Design 32 12 16 Mix Design 32 12 16 Mix Design 32 12 16 Mix Design 32 12 16 Mix Design 32 12 16 Mix Design Detectable Warning Surface 32 13 20 DWS - Pavers 32 13 20 DWS - Pavers 9/9/2022 32 13 20 DWS - Composite 9/9/2022 32 13 20 DWS - Composite 9/9/2022 9/9/2022 9/9/2022 9/9/2022 9/9/2022 9/9/2022 9/9/2022 9/9/2022 9/9/2022 Silicone Joint Sealant 32 13 73 32 13 73 32 13 73 32 13 73 Joint Sealant Joint Sealant Joint Sealant Joint Sealant Utility Trench Embedment Sand 33 05 10 Embedment Sand 33 05 10 Embedment Sand 33 05 10 Embedment Sand 33 05 10 Embedment Sand 33 05 10 Embedment Sand Manufacturer True Grit Redi Mix Wise Redi Mix Austin Asphalt Austin Asphalt Austin Asphalt Austin Asphalt Austin Asphalt Reynolds Asphalt Reynolds Asphalt Reynolds Asphalt Sunmount Paving Sunmount Paving Sunmount Paving Sunmount Paving TXBIT TXBIT TXBIT TXBIT TXBIT TXBIT TXBIT TXBIT Model No. 0265.2301 4500 psi Concrete Mix for Valley Gutters, Hand Placed Paving 3678 3600 psi Concrete Mix for Lighting and Traffic Signal Foundations FT5D137965 PG64-22 Type D Fine Surface DA5D135965 PG64-22 Type D Fine Surface FT5B117965 PG64-22 Type B Fine Base FT1B139965 PG64-22 Type B Fine Base FT1B117.2 PG64-22 Type B Fine Base 1901D PG64-22 Type D Fine Surface 1112B PG64-22 Type B Fine Base 1612B PG64-22 Type B Fine Base 341DV6422 PG64-22 Type D Fine Surface 340DV6422 PG64-22 Type D Fine Surface 3076BV6422 PG62-22 Type B Fine Base 341-BRAP6422ERG PG64-22 Type B Fine Base 37-211305-20 PG64-22 Type B Fine Base 44-211305-17 PG64-22 Type B Fine Base 211305 (1757) PG64-22 Type B Fine Base 222475 (1857) PG64-22 Type D Fine Surface 29-222475-19 PG64-22 Type D Fine Surface 1-222475-20 PG64-22 Type D Fine Surface 64-224125-18 PG70-22 Type D Fine Surface 12-222475-19 PG64-22 Type D Fine Surface Pine Hall Brick (Winston Salem, NC) Tactile Pavers Western Brick Co. (Houston, TX) Detectable Warning Pavers Engineered Plastics, Inc. (Williamsville, NY) Armor Tile ADA Solutions (Wilmington, MA) Heritage Brick CIP Composite Paver Dow Tremco Pecora Crafco Silver Creek Materials Crouch Materials F and L Dirt Movers F and L Dirt Movers Tin Top Martin Marietta 890SL - Cold Applied, Single Component, Silicone Joint Sealant 900SL - Cold Applied, Single Component, Silicone Joint Sealant 300SL - Cold Applied, Single Component, Silicone Joint Sealant RoadSaver Silicone - Cold Applied, Single Component, Silicone Joint Sealant Utility Embedment Sand Utility Embedment Sand Utility Embedment Sand Utility Embedment Sand Utility Embedment Sand National Spec ASTM D5893 ASTM D5893 ASTM D5893 ASTM D5893 ASTM C33 ASTM C33 ASTM C33 ASTM C33 ASTM C33 FORT WORTH. CITY OF FORT WORTH TRANSPORTATION/PUBLIC WORKS DEPARTMENT STANDARD PRODUCTS LIST AS OF 12/01/2022 Approval Spec No. Classification Manufacturer Model No. National Spec Frame, Cover and Grade Rinds - Cast Iron** for Stormwater Structures 9/9/2022 9/9/2022 9/9/2022 9/9/2022 9/9/2022 9/9/2022 9/9/2022 9/9/2022 9/9/2022 9/9/2022 9/9/2022 9/9/2022 9/9/2022 33 05 13 33 05 13 33 05 13 33 05 13 33 05 13 33 05 13 33 05 13 33 05 13 33 05 13 33 05 13 33 05 13 33 05 13 33 05 13 9/9/2022 33 05 13 **Note: All new development Manhole Frames and Covers Manhole Frames and Covers Manhole Frames and Covers Manhole Frames and Covers Manhole Frames and Covers Manhole Frames and Covers Manhole Frames and Covers Manhole Cover Manhole Frames and Covers Manhole Frame Manhole Frames and Covers Manhole Frames and Covers Manhole Frames and Covers Manhole Frames and Covers and new installation manhole lids Neena Foundry Neena Foundry SIP Industries EJCO Neena Foundry Neena Foundry AccuCast (Govind Steel Company, Ltd.) Neena Foundry Neena Foundry Neena Foundry Neena Foundry SIP Industries SIP Industries 32" Diameter Liftmate Water Manhole Gasketed Frame and Cover w/Longhorn Logo, Model No. NF-1743LT66 32" Diameter Liftmate Sanitary Sewer Manhole Frame and Cover w/Longhom Logo, Model No. NF-1743LT69 32" Diameter Fort Worth Sanitary Sewer Manhole Frame and Cover, Item No. NF-2280 Ergo XL Assembly 32" Diameter Sanitary Sewer Manhole Frame and Cover, Model No. 00148021L010 32" Diameter Liftmate Storm Sewer Junction Box and Manhole Frame and Cover w/Longhom Logo, Model No. NF-1743LTXX 24" Diameter Liftmate Storm Sewer Inlet Manhole Frame and Cover w/Longhom Logo, Model No. NF-1650LT61 24" Diameter MHRC #220605 * * 32" Diameter NF-1274-T91 32" Diameter NF-1743-LM (Hinged) 32.25" Diameter NF-1930-30 32" Diameter NF-1743-HV 24" Diameter 2279ST** 32" Diameter 2280ST EJCO 32.25" Diameter EJ1033 X2/A sha t meet the minimum 30" opening requirement as specified in City Specification 33 0513. Any smaller opening sizes will only be allowed for existing manholes that require replacement frames and covers. Reinforced Concrete Storm Drain Pipe/Culverts 9/9/2022 33 41 10 Precast Box Culverts Forterra 9/9/2022 33 41 10 Concrete Pipe Wyes and Bends Forterra 9/9/2022 33 49 10 Precast Box Culverts Rinker Materials 9/9/2022 33 49 10 Concrete Pipe Rinker Materials 9/9/2022 33 41 10 Concrete Pipe Forterra Polypropylene Storm Drain Pipe 9/9/2022 133 41 13 (Polypropylene Pipe (Advanced Drainage Systems, Inc. Storm Drain Manholes and Junction Boxes 9/9/2022 33 49 10 Stacked Manhole Oldcastle 9/9/2022 33 49 10 Junction Box Oldcastle 9/9/2022 33 49 10 Junction Box Oldcastle 9/9/2022 33 49 10 Junction Box Oldcastle 9/9/2022 33 49 10 Junction Box Oldcastle 9/9/2022 33 49 10 Junction Box Oldcastle 9/9/2022 33 49 10 Junction Box Oldcastle 9/9/2022 33 49 10 Junction Box Cowtown Redi Mix 9/9/2022 33 49 10 Manhole Rinker Materials 9/9/2022 33 49 10 Manhole Connector Trelleborg Engineered Systems 9/9/2022 33 49 10 Junction Box Forterra 9/9/2022 33 49 10 Junction Box Forterra 9/9/2022 33 49 10 Junction Box Forterra 9/9/2022 33 49 10 Junction Box Forterra 9/9/2022 33 49 10 Junction Box Forterra 9/9/2022 33 49 10 Junction Box Thompson Pipe Group 9/9/2022 33 49 10 Junction Box Thompson Pipe Group 9/9/2022 33 49 10 Junction Box Thompson Pipe Group 9/9/2022 33 49 10 Junction Box Thompson Pipe Group 9/9/2022 33 49 10 Junction Box Thompson Pipe Group 9/9/2022 33 49 10 Junction Box Thompson Pipe Group 9/9/2022 33 49 10 Junction Box Thompson Pipe Group 9/9/2022 33 49 10 Junction Box Thompson Pipe Group 9/9/2022 33 49 10 Junction Box Thompson Pipe Group 9/9/2022 33 49 10 Junction Box Thompson Pipe Group 9/9/2022 33 49 10 Junction Box Thompson Pipe Group 9/9/2022 33 49 10 Junction Box Thompson Pipe Group 9/9/2022 33 49 10 Junction Box Thompson Pipe Group 9/9/2022 33 49 10 Junction Box Thompson Pipe Group 9/9/2022 33 49 10 Junction Box Thompson Pipe Group Precast Box Culverts RCP Wye and Bends Rinker Materials Reinforced Concrete Box Culvert ASTM C789, C850 Rinker Materials Reinforced Concrete Pipe Tongue and Groove Joint Pipe ASTM C76, C655 Reinforced Concrete Pipe - Tongue and Groove +D48 HP Polypropylene Storm Drain Pipe Precast 4' x 4' Stacked Manhole Precast 5' x 8' Storm Junction Box Precast 4' x 4' Storm Junction Box Precast 5' x 5' Storm Junction Box Precast 6' x 6' Storm Junction Box Precast 8' x 8' Storm Junction Box Base Precast 5' x 8' Storm Junction Box Base No. 260-2 6 Sack 3600 psi Concrete for Concrete Collars Rinker Materials Reinforced 48" Diameter Spread Footing Manhole Kor-N-Seal 106/406 Series Pipe to Manhole Connector 4' x 4' FRT-4x4-409-PRECAST-BASE 5' x 5' FRT-5x5-409-PRECAST-TOP 5' x 5' FRT-5x5-409-PRECAST-BASE 6' x 6' FRT-6x6-409-PRECAST-TOP 6' x 6' FRT-6x6-409-PRECAST-BASE 4 'x 4' TPG-4x4-409-PRECAST TOP 4 'x 4' TPG-4x4-409-PRECAST BASE 4 'x 4' TPG-4x4-412-PRECAST 4-FT RISER 5 'x 5' TPG-5x5-410-PRECAST TOP 5 'x 5' TPG-5x5-410-PRECAST BASE 5 'x 5' TPG-5x5-412-PRECAST 5-FT RISER 6'x 6' TPG-6x6-411-PRECAST TOP 6'x 6' TPG-6x6-411-PRECAST BASE 6 'x 6' TPG-6x6-412-PRECAST 6-FT RISER 7'x 7' TPG-7x7-411-PRECAST TOP 7 'x 7' TPG-7x7-411-PRECAST BASE 7 'x 7' TPG-7x7-412-PRECAST 4-FT RISER 8'x 8' TPG-8x8-411-PRECAST TOP 8'x 8' TPG-8x8-411-PRECAST BASE 8 'x 8' TPG-8x8-412-PRECAST 5-FT RISER ASTM A48 AASHTO M306 ASTM A48 AASHTO M306 ASTM A48 AASHTO M306 ASTM A48 AASHTO M306 ASTM A48 AASHTO M306 ASTM A48 AASHTO M306 ASTM A48 AASHTO M306 ASTM A48 AASHTO M306 ASTM C789, C850 ASTM C76, C655 ASTM C478 ASTM C478 ASTM C478 ASTM C478 ASTM C478 ASTM C478 ASTM C478 ACI 318-14 ASTM C433 ASTM C923 ASTM C913 ASTM C913 ASTM C913 ASTM C913 ASTM C913 ASTM C615 ASTM C615 ASTM C615 ASTM C615 ASTM C615 ASTM C615 ASTM C615 ASTM C615 ASTM C615 ASTM C615 ASTM C615 ASTM C615 ASTM C615 ASTM C615 ASTM C615 FORT WORTH. CITY OF FORT WORTH TRANSPORTATION/PUBLIC WORKS DEPARTMENT STANDARD PRODUCTS LIST AS OF 12/01/2022 Approval Spec No. Classification Manufacturer Model So. National Spec Storm Drain Curb and Drop Inlets 9/9/2022 33 49 20 9/9/2022 33 49 20 9/9/2022 33 49 20 9/9/2022 33 49 20 9/9/2022 33 49 20 9/9/2022 33 49 20 9/9/2022 33 49 20 9/9/2022 33 49 20 9/9/2022 33 49 20 9/9/2022 33 49 20 9/9/2022 33 49 20 Curb Inlets Curb Inlets Curb Inlets Curb Inlets Junction Box Curb Inlet Curb Inlet Curb Inlet Drop Inlet Drop Inlet Drop Inlet Forterra Forterra Forterra Forterra Forterra Thompson Pipe Group Thompson Pipe Group Thompson Pipe Group Thompson Pipe Group Thompson Pipe Group Thompson Pipe Group 10' x 3' FRT-10x3-405-PRECAST 10' x 3' FRT-10x3-406-PRECAST 10' x 4.5' FRT-10x4-407-PRECAST 10' x 4.5' FRT-10x4-420-PRECAST 4' x 4' FRT-4x4-409-PRECAST-TOP 10' x 3' TPG-10x3-405-PRECAST INLET 15' x 3' TPG-15x3-405-PRECAST INLET 20' x 3' TPG-20X3-405-PRECAST INLET 4' x 4' TPG-4X4-408-PRECAST INLET 5' x 5' TPG-5X5-408-PRECAST INLET 6' x 6' TPG-6X6-408-PRECAST INLET ASTM C913 ASTM C913 ASTM C913 ASTM C913 ASTM C913 ASTM C615 ASTM C615 ASTM C615 ASTM C615 ASTM C615 ASTM C615