HomeMy WebLinkAboutContract 54223-FP1NN Coded 01.11.23
Vendor Name: Bar Constructors
VendorID# 0000034012
Invoice No. 54223-FP1
Invoice Date 01.10.23
FW060-10477 - $44,296.60
Release retainage - $200,644.86
FID 56019-2060000-100995-RETAIN
Total Invoice - $244,941.46
FORTWORTH
-IF
WATER DEPARTMENT
ENGINEERING AND FISCAL SERVICES
NOTICE OF PROJECT COMPLETION
CSC No. 54223-FP1
56019-100995
CS 54223
Regarding contract 54223 for Lake Arlington Lift Station as required by the Water Department as approved by City
Council on 6/23/20 through M&C 20-0460 the Director of the Water Department, upon the recommendation of the Sr.
Capital Projects Officer, Capital Projects Delivery, Water Department, has accepted the project as complete.
Original Contract Prices:
Amount of Approved Change Orders:
Revised Contract Amount:
Total Cost Work Completed:
Less Deductions:
Liquidated Damages:
Other Deductions(see comments):
Total Deduction Amount:
Total Cost Work Completed:
Less Previous Payments:
Final Payment Due
$10,077,693.00
($797.52) Ns
4 $10,076,895.48
$10,076,539.37
0 Days @ $630.00/ Day
$0.00
$10,076,539.37
$9,831,597.91
$244,941.46
�� S o L G 4 10 2 9
Recommended for Acceptance Date
Assistant Director, Water Department
Christopher Hardo'(Jan 12, 2023 08:18 CST)
Accepted _ Date
Director, Water Department
Dam &%Ldloz-
Dana Burghdoff (Ja 12, 2023 0 :36 CST)
City Manager Date
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
Project Name: Lake Arlington Lift Station
DOE. Ns:
Comments:
City Project Numbers 100995
Contract Name Lake Arlington Lift Station
Contract Limits Council District 5
Project Type Alternate Bid A-2
Project Funding
Project Manager UNKNOWN
Inspectors Johnson / Gray
Contractor BAR CONSTRUCTORS INC
P0BOX 10
LANCASTER, TX 75146
56019-100995
CS 54223
DOE Number 0223
Estimate Number 27
Payment Number 27
For Period Ending 12/28/2022
City Secretary Contract Number 54223
Contract Date
6/23/2020
Contract Time
719 CD
Days Charged to Date
713 CD
Contract is .000000
Complete
CITY OF FORT WORTH
SUMMARY OF CHARGES
Line Fund Account Center Amount Gross Retainage Net
Funded
------------
Total Cost of Work Completed $10,076,539.37
Less 0 % Retained
$0.00
Net Earned
$10,076,539.37
Earned This Period $244,941.46
Retainage This Period $0.00
Less Liquidated Damages
0 Days @ $0.00 / Day
$0.00
LessPavement Deficiency
$0.00
Less Penalty
$0.00
Less Previous Payment
$9,831,597.91
Plus Material on Hand Less 15%
$0.00
Balance Due This Payment
$244,941.46
Wednesday, January 4, 2023 Pal-e 6 of 6
FORT WORTH
CITY OF FORT WORTH
FINAL PAYMENT REQUEST
Contract Name
Lake Arlington Lift Station
Contract Limits
Council District 5
Project Type
Lift Station
City Project Numbers 100995
DOE Number
0223
Estimate Number 27 Payment Number 27
City Secretary Contract Number 54223
Contract Date 6/23/2020
Project Manager UNKNOWN
Contractor BAR CONSTRUCTORS INC
P0BOX 10
For Period Ending 12/29/2022
CD
LANCASTER , TX 75146
Inspectors Johnson / Gray
Contract Time 719D
Days Charged to Date 713
Contract is 100.00 Complete
Wednesday, January 4, 2023 Page 1 of 6
City Project Numbers 100995
Contract Name
Lake Arlington Lift Station
Contract Limits
Council District 5
Project Type
Lift Station
Project Funding
Unit I Lift Station
Item Description of Items
No.
---------------
32a 9999.0016a SEL 735 Power Quality Met
32b 9999.0016b SEL 751 Arch Flash Relay
32c 9999.0016c Rosemount InteiliSAW The
33 9999.0017 Instrumentation, SCADA**,
33a 9999.0017a Magelis HMDT732 Operato
33b 9999.0017b MDS Orbit 900 Ethernet R
33c 9999.0017c Modicon M340 PLC without
34 9999.0018 Cable bus, cable tray, cab
35 9999.0019 750kVA Generator
36 9999.0020 Power System Studies, Star
37 9999.0021 Miscellaneous Electrical
1 9999.0001 78" Fiberglass Sewer Pipe
2 3331.4505 42" DIP Sewer Pipe and Fi
3 3331.4405 30" DIP Sewer Pipe and Fi
4 3331.4311 24" Fiberglass Sewer Pipe (CO#4)
5 3312.3011 42" Gate Valve
6 3312.3009 30" Gate Valve
7 9999.0002 30" Swing Check Valve
8 9999.0003 78" Sluice Gate
9 3331.6106 Sewer Air Release Valve A
10 3339.1101 5' Diameter Sewer Manhole (CO#4)
11 3339.1111 5' Tee Base Manhole
12 3339.1102 5' Drop Manhole
13 9999.0004 Odor Control System
14 3305.0109 Trench Safety
15 0171.0101 Construction Staking
16 0171.0102 As -Built Survey
17 3310.0101 All Lift Station Site Work
18 9999.0005 Excavation and Backfill (A
19 9999.0006 Drilled Shafts*
20 3231.0113 Chain Link Fence
DOE Number
0223
Estimate Number
27
Payment Number
27
For Period Ending
12/29/2022
Estimated Unit Unit Cost
Estimated
Completed Completed
Quanity
Total
Quanity Total
-----------------------
1 LS
$6,000.00
$6,000.00
1
$6,000.00
1 LS
$9,600.00
$9,600.00
1
$9,600.00
1 LS
$18,000.00
$18,000.00
1
$18,000.00
0.946 LS
$256,000.00
$242,176.00
0.94632
$242,257.92
1 LS
$6,800.00
$6,800.00
1
$6,800.00
1 LS
$3,000.00
$3,000.00
1
$3,000.00
1 LS
$8,100.00
$8,100.00
1
$8,100.00
1 LS
$654,000.00
$654,000.00
1
$654,000.00
1 LS
$454,300.00
$454,300.00
1
$454,300.00
1 LS
$136,800.00
$136,800.00
1
$136,800.00
0.05589 LS
$245,000.00
$13,693.05
0.05589
$13,693.05
210 LF
$1,016.00
$213,360.00
210
$213,360.00
200 LF
$1,042.00
$208,400.00
200
$208,400.00
235 LF
$987.00
$231,945.00
235
$231,945.00
550.89 LF
$174.00
$95,854.86
550.89
$95,854.86
2 EA
$86,200.00
$172,400.00
2
$172,400.00
3 EA
$32,300.00
$96,900.00
3
$96,900.00
3 EA
$46,400.00
$139,200.00
3
$139,200.00
1 EA
$23,400.00
$23,400.00
1
$23,400.00
5 EA
$8,070.00
$40,350.00
5
$40,350.00
2.88 EA
$24,100.00
$69,408.00
2.876
$69,311.60
2 EA
$35,100.00
$70,200.00
2
$70,200.00
1 EA
$20,100.00
$20,100.00
1
$20,100.00
1 EA
$196,800.00
$196,800.00
1
$196,800.00
910 LF
$10.00
$9,100.00
910
$9,100.00
1 LS
$3,500.00
$3,500.00
1
$3,500.00
1 LS
$1,500.00
$1,500.00
1
$1,500.00
1 LS
$77,500.00
$77,500.00
1
$77,500.00
1 LS
564,000.00
.,564,000.00
1
1,564,000.00
400 VF
$96.00
$38,400.00
400
$38,400.00
1440 LF
$45.00
$64,800.00
1432.07
$64,443.15
Wednesday, January 4, 2023 Page 2 of 6
City Project Numbers 100995
Contract Name Lake Arlington Lift Station
Contract Limits Council District 5
Project Type Lift Station
Project Funding
DOE Number
0223
Estimate Number
27
Payment Number
27
For Period Ending
12/29/2022
21
3213.0102 7" Reinforced Concrete P
7851 SY
$71.00
$557,421.00
7851
$557,421.00
22
3213.0401 6" Concrete Driveway
255 SF
$8.00
$2,040.00
255
$2,040.00
23
9999.0007 Reinforced Concrete (All S
1 LS
,822,400.00
822,400.00
1
,1,822,400.00
24
9999.0008 Masonry Screen Wall at Gen
1 LS
$63,500.00
$63,500.00
1
$63,500.00
25
9999.0009 Metal Fabrications (All It
1 LS
$109,700.00
$109,700.00
1
$109,700.00
26
9999.0010 Electrical Building, inclu
1 LS
$232,200.00
$232,200.00
1
$232,200.00
27
9999.0011 Lift Station Mechanical Va
1 LS
$250,000.00
$250,000.00
1
$250,000.00
28
9999.0012 Wet Well hiterior Concrete
1 LS
$209,000.00
$209,000.00
1
$209,000.00
29
9999.0022 All Painting
1 LS
$46,270.00
$46,270.00
1
$46,270.00
30
9999.0013 Lift Station Heating and V
1 LS
$144,000.00
$144,000.00
1
$144,000.00
31
9999.0014 Variable Frequency Drive
0 EA
$189,800.00
$0.00
32
9999.0015 Switchgear**, Panelboards,
0 LS
$277,000.00
$0.00
38
vcariable Frequency Dr. (500hp VFDs) CO#1, CO#4
2.96887 EA
$184,705.00
$548,365.13
2.96887
$548,365.13
39
Switchgear,p[anelboards, Transformers 2400 amp
1 LS
$256,617.00
$256,617.00
1
$256,617.00
CO# 1
40
Misc. Electrical(reduce wire, equipments) CO#1
1 LS
$216,021.95
$216,021.95
1
$216,021.95
41
Add. Project Expense Pending Delivery Motors COl
1 EA
$31,122.06
$31,122.06
1
$31,122.06
43
20' Pole Antenna & Appurtenances (CO#2)
1 EA
$1,763.13
$1,763.13
1
$1,763.13
44
Temporary power Supply (CO#3)
1 LS
$21,866.54
$21,866.54
1
$21,866.54
45
24' Swing Gate (CO#3)
3 EA
$4,290.00
$12,870.00
3
$12,870.00
46
--------------------------------------
Electrical Building Pre -cast Panel (CO#4)
1 LS
$6,600.00
$6,600.00
1
$6,600.00
Sub-Total of Previous Unit
$9,421,343.72
$9,420,972.39
Unit II Water
Item
Description of Items
Estimated Unit
Unit Cost
Estimated
Completed
Completed
No.
Quanity
Total
Quanity
Total
---------------------------------------
1
3311.0261 8" PVC Water Pipe with Se
680 LF
$52.00
$35,360.00
680
$35,360.00
2
3312.0001 Fire Hydrant Assembly
1 EA
$6,500.00
$6,500.00
1
$6,500.00
3
3311.0001 Ductile Iron Water Fittin
0.25 TN
$4,000.00
$1,000.00
0.25
$1,000.00
4
3312.0117 Connection to Existing 4"
1 EA
$8,600.00
$8,600.00
1
$8,600.00
5
3201.0616 Concrete Pavement Repair (CO#1)
81.9656 SY
$135.00
$11,065.36
81.9656
$11,065.36
6
3312.2003 1" Water Service Assembly (C0#1)
0 EA
$6,500.00
$0.00
0
$0.00
7
3305.0109 Trench Safety
680 LF
$1.00
$680.00
680
$680.00
8
0171.0101 Construction Staking
1 LS
$550.00
$550.00
1
$550.00
9
0171.0102 As -built Survey
1 LS
$550.00
$550.00
1
$550.00
Wednesday, January 4, 2023 Page 3 of 6
City Project Number
Contract Name
Contract Limits
Project Type
Project Funding
100995
Lake Arlington Lift Station
Council District 5
Water
DOE Number
0223
Estimate Number
27
Payment Number
27
For Period Ending
12/28/2022
42 1" Water Service w/ Meter and box CO#1 1 EA $8,259.62 $8,259.62 1 $8,259.62
Sub -Total of Previous Unit $72,564.98 $72,564.98
Unit III Alternate Bid A-2
Item Description of Items Estimated Unit Unit Cost Estimated Completed Completed
No. Quanity Total Quanity Total
---------------------------------------
I KSB Pumps with Wire to Water 3 EA $194,334.00 $583,002.00 3 $583,002.00
--------------------------------------
Sub-Total of Previous Unit $583,002.00 $583,002.00
--------------------------------------
Wednesday, January 4, 2023 Page 4 of 6
City Project Numbers 100995
Contract Name Lake Arlington Lift Station
Contract Limits Council District 5
Project Type Alternate Bid A-2
Project Funding
Contract Information Summary
Original Contract Amount
Change Orders
Change Order Number I
Change Order Number I
Change Order Number 2
Change Order Number 3
Change Order Number 4
Co
ntr for
Date/— �^ 2
In pection Supervisor
Date (j 3
Pro ect Man ge
N / A Date
Asst. Director/TPW
Qhnstopher Hzrd !Jan 12. 2023 08 18 CST) Date
Director! Contracting Department
DOE Number
0223
Estimate Number
27
Payment Number
27
For Period Ending
12/282022
$10,077,693,00
($19,830.94)
($0.02)
($11,978.95)
$34,736.54
($3,724.15)
Total Contract Price $10,076,910.70
Total Cost of Work Completed $10,076,539.37
Less 0 % Retained $0.00
Net Earned $10,076,539.37
Earned This Period $244,941.46
Retainage This Period $0.00
Less Liquidated Damages
Days @ / Day
$0.00
LessPavement Deficiency
$0.00
Less Penalty
$0.00
Less Previous Payment
$9,831,597.9I
Plus Material on Hand Less 15%
$0.00
Balance Due This Payment
$244,941.46
Wednesday, January 4, 2023 Page 5 of 6
FORTWORTH rev 03/05/07
WATER ENGINEERING & FISCAL SERVICES
FINAL STATEMENT OF CONTRACT TIME
FINAL STATEMENT NO.:27
NAME OF PROJECT: Lake Arlington Lift Station
PROJECT NO.: 100995
CONTRACTOR: BAR Constructors, Inc.
CITY PROJECT 54223
PERIOD FROM:09/01/20 TO: 12/01/22
FINAL INSPECTION DATE: 12/1/2022
WORK ORDER EFFECTIVE:9/l/2020
CONTRACT TIME: 719 O WD QQ CD
DAY OF DAYS RE ASON FOR DAYS DAY OF DAYS REASON FOR DAYS
CHARGED CHARGED
MONTH CREDITED
DURING
MONTH CREDITED
DURING
1.
16.
2.
17.
3.
18.
4•
19.
5.
20.
6.
21.
7.
22.
8.
23.
9.
24.
10.
25.
11.
26.
12.
27.
13.
28.
14.
29.
15.
30.
31.
SAT, SUN,
RAIN, TOO WET,
UTILITIES
DAYS
TOTAL
& HOLIDAYS
& TOO COLD
RELOCATIONS
OTHERS*
CHARGED
DAYS
THIS
PERIOD
0
0
PREVIOUS
PERIOD
713
713
TOTALS
TO DATE
713
713
IKEMAKA 13:
i
— 5 — 3 12/30/2022
CdNTRACTOR DATE INSPECTOR DATE
Capital Projects Delivery, Water Department
The City of Fort Worth • 200 Texas Street • Fort Wordi, TX 76012-6311
(817) 392 - 4477 - Fax: (817) 392 - 8460
FORTWORTH
Capital Projects Delivery, Water Department
CONTRACTOR'S EVALUATION OF CITY
REV: 02/22/07
I) PROJECT INFORMATION Date: 29-Dec-22
None of Contractor
Project Name
BAR Constructors, Inc.
Lake Arlington Lift Statation
IYater Engineering Inspector
Project Manager
Natan Gray
Pratima Poudyal
DOE Number
Project Difficulty
Type ojComact
Q Simple Q Routine Q Complex
❑ Water 0 Waste Water ❑ Storm Drainage ❑ Pavement
Initial Contract Amormt
final Contract Amount
$10,077,693.00
$10,076, 895.48
II) PERFORMANCE EVALUATION
0 - Inadequate I - Deficient 2 - Standard 3 - Good 4 - Excellent
ELEMENT
RATING
(0 - 4)
ELEMENT
RATING
(0 - 4)
INSPECTION EVALUATION
PLANS & SPECIFICATIONS
1 Availability of Inspector
I Accuracy of Plans to Existing Conditions
2 Knowledge of Inspector
2 Clarity & Sufficiency of Details
3 Accuracy of Measured Quantities
3 Applicability of Specifications
4 Display Of Professionalism
14 Accuracy of Plan Quantities
5 Citizen Complaint Resolution
PROJECT MANAGER EVALUATION
6 Performance - Setting up Valve Crews, Labs
1 Knowledge And/Or Problem Resolution
ADMINISTRATION
2 Availability of Project Manager
1 Change Order Processing Time
3 Communication
2 Ti nliness of Contractor Payments
4 Resolution of Utility Conflicts
3 Bid Opening to Pre -Con Meeting Timefiame
III) COMMENTS & SIGNATURES
COMMENTS
Signature Contractor
Signature Inspector
Signature Inspector's Supervisor
INSPECTOR'S COMMENTS
Capital Projects Delivery, lf/ater Department
The City of Fort Worth • 1000 Throckmorton Strcet • Fort Worth, TX 76012-6311
(817) 392 - 4477 • Fax. (817) 392 - 8460
FoRTWORTHREV: 02/20/07
Capital Projects Delivery, Water Department
PERFORMANCE EVALUATION OF CONTRACTOR
I) CONTRACTOR & PROJECT DATA
Naune ojContractor
Project Name
BAR Constructors, Inc.
Lake Arlington Lift Station
Plater Engineering Inspector
DOE Number
Nathan Gray
N/A
IYafer Engineering Inspector
Projectdlanager
❑ Water EJ Waste Water ❑ Storm Drainage ❑ Pavement
Pratima Poudyal
Initial Contrac! Amonml
Project Difficulty
$10,077,693.00
Q Simple p Routine Q Complex
Final Contract Anioun!
Date
$10,076,895.48
II) PERFORMANCE EVALUATION
10 - Inadeauate 1 - Deficient 2 - Standard 3 - Gnnd 4 - Fsceltew
ELEMENT
WEIGHT(
APPLICABLE (Y / N)
RATING (0 - 4)
MAX SCORE
SCORE
1 Submission of Documents
2
Y
3
8
6
2 Public Notifications
5
Y
4
20
20
3 Plans on Site
5
Y
4
20
20
4 Field Super -vision
15
Y
4
60
60
5 Work Performed
15
Y
1 4
1 60
60
6 Finished Product
15
Y
4
60
60
7 Job Site Safety
15
Y
4
60
60
8 Traffic Control Maintenance
15
Y
4
60
60
9 Daily Clean Up
5
Y
4
20
20
10 Citizen's Complaint Resolution
5
Y
4
20
20
11 Property Restoration
5
Y 1
4
20 1
20
12 After Hours Response
5
Y
4
20
20
13 Project Completion
5
Y
3
20
15
TOTAL ELEMENT SCORE (A) 441
BONUS POINTS (25 Maximum) (B)
TOTAL SCORE (TS) 441
III) CONTRACTOR'S RATING
Maximum Score (MS) = 443 or sum of applicable element score maximums which = 443
Rating ( [TS / MS] * 100%) 441 1 448 = 98%
Performnnee Category Excellent
<20% = Inadequate 20% to <40% = Deficient 40% to <60% = Standard 60% to <80% = Good >_80% = Excellent
Inspcctor's Comments (INCLUDING EXPLANATION OF BONUS POINTS AWARDED)
Signature Inspector Signature Contractor (/t
Signature Inspector's Supervisor
CONTRACTOR'S COMMENTS
Capital Projects Delivery, Water Department
The City of Fort %north • 1060 Throckmorton Street • Fort Worth, TX 76012-6311
(817) 392 - 4477 • Fax: (817) 392 - 8460
FORTWORTH
WATER ENGINEERING & FISCAL SERVICES
PIPE REPORT FOR:
PROJECT NAME:
Lake Arlington Lift
Station
PROJECT NUMBER:
100995
DOE NUMBER:
N/A
WATER
PIPE LAID
SIZE
TYPE OF PIPE
LF
WATER
8-Inch
PVC
680
FIRE HYDRANTS: 1
VALVES (16" OR LARGER)
PIPE ABANDONED
SIZE
TYPE OF PIPE
LF
DENSITIES:
3
NEW SERVICES:
1
Copper
50
SEWER
PIPE LAID
SIZE
TYPE OF PIPE
LF
SEWER
78-Inch
Fiberglass
210
SEWER
42-Inch
Ductile Iron Pipe
200
SEWER
30-Inch
Ductile Iron Pipe
235
SEWER
24-Inch
Fiberglass
550.89
PIPE ABANDONED
SIZE
TYPE OF PIPE
LF
DENSITIES:
6
NEW SERVICES:
WATER ENGINEERING & FISCAL SERVICES
The City of Fort Worth • 1000 Throckmorton Street • Fort Worth, TX 76012-6311
(817) 392 - 4477 • Fax: (817) 392 - 8460
Owner
CONSENT OF
Architect
SURETY COMPANY
Contractor
TO FINAL. PAYMENT
Surety
AIA DOC'UMi.NTG7o7
Other
PROJECT: Lake Arlington LittStation: City Project No. 100995.
(name, address) Bond # 46BCSII8396
TO: 0vilco
City of Fort Worth
1000 Throckmorton Street
Fort Worth, TX 76102
CONTRACTOR:
BAR Constructors Inc
P. O. Box 10
Lancaster, TX 75146
ARCHITECT'S PROJECT' CIO:
CONTRACT FOR: Construction
C'ON'['lt.a<'T n.a• E-. 6/23/2020
In accordance with the provisions of the Contract between the Uxeiter and the Contractor as indicated above, the
Hartford Fire Insurance Company
3000 Internet Drive, Suite 600
Frisco, Texas 75034-1991 SUIRETY C0A1P.V Y
on bond of (here insert name and addresa ni ontraetor)
BAR Constructors Inc
P. O. Box 10
Lancaster, Texas 75146
.CONTRACTOR,
hereby approves of the final payment to the Contractor, acid agrees that final payment to the Contractor shall not
relieve the Surety Company of any of its obligations to (here ittscri name and nddresa ni o weer)
City of Fort Worth
1000 Throckmorton Street ,ONVNER,
Fort Worth, Texas 76102
as set forth in the said Surety Company's bond.
In W.7FNLSS WHEREOF.
the Surety Company has hereunto set its hand this
27th day of October 2022
Surety ' to airy
HartUdER1 ee Insurance mp• y
Sicmai :rc c+t Authoriicd Rcpresentaute ( " T
AIta.,t. Dawn Davis - Attorney -In -Fact. ;
NOTF:'Iltis form is to be ust.d as a companion document to AIA DOCUMENT Ci7tK>, CON I-KAC TOR'S APYtllAVIT OF'PAYMf-NTOF '
DEB IS AND ('1 AIMS, Current edition
AIA DOCUMPNT 0707-CONSUN1.OF SURETY COMPANY TO FINAL PAYMf;;'T PRII. I0711 LI>ITit7A•AIA.tt:'_ _ -ONE
PALL :
K:] 970� r]IF. AMPR[C'AN INS'Cf[lTF OF ARCHITL•C'I'S. 1735 NEW YORK..AVF.. WK.1l'ASI II1tGTON. LK. 20000-,
Direct Inquiries/Claims to:
THE HARTFORD
POWER OF ATTORNEY BONnectic
One Hartford Plaza
Hartford, Connecticut 06155
Sond.Claims(&thehartford.com
call: 888-266-3488 or fax: 860-757-5835
KNOW ALL PERSONS BY THESE PRESENTS THAT: Agency Name: MARSH & MCLENNAN AGENCY LLC
Agency Code: 4 6- 4 614 9 6
0 Hartford Fire Insurance Company, a corporation duly organized under the Paws ofrhe State of Connecticut
Hartford Casualty Insurance Company, a corporation duty organized under the laws of the State of Indiana
Hartford Accident and Indemnity Company, it corporation duly organized under the laws of the State of Connecticut
Hartford Underwriters Insurance Company, a corporation duly organized tinder the laws of the State of Connecticut
Twin City Fire Insurance Company, a corporation duly organized under the laws of the State of Indiana
Hartford Insurance Company of Illinois, a corporation duly organized under the laws of the State of Illinois
Hartford Insurance Company of the Midwest, a corporation duly organized under the laws of the State of Indiana
Hartford Insurance Company of the Southeast, a corporation duly organized under the laws of the State of Florida
having their home office in Hartford. Connecticut, (hereinafter collectively referred to as the "Companies") do hereby make, constitute and appoint
up to the amount of Unlimited :
Edward R. Bowles, Dawn Davis, Walter J. DeLaRosa, DONNIE DOAN, Kristi Meek, Kae
Perdue, Christen Tyner o-f DALLAS, Texas
their true and lawful Attorney(s)-in-Fact, each in their separate capacity if more than one is named above, to sign its name as surety(ies) only as
delineated above by ®, and to execute, seal and acknowledge any and all bonds, undertakings, contracts and other written instruments in the
nature thereof, on behalf of the Companies in their business of guaranteeing the fidelity of persons, guaranteeing the performance of contracts and
executing or guaranteeing bonds and undertakings required or permitted in any actions or proceedings allowed by law.
In Witness Whereof, and as authorized by a Resolution of the Board of Directors of the Companies on May 23, 2016 the Companies
have caused these presents to be signed by its Assistant Vice President and its corporate seals to be hereto affixed, duly attested by its Assistant
Secretary. Further, pursuant to Resolution of the Board of Directors of the Companies, the Companies hereby unambiguously affirm that they are
and will be bound by any mechanically applied signatures applied to this Power of Attorney.
4 SYl •f flat t` '00-
�/O�>�
! o �r e'r •, •,. 1 n 8 : ' : a, _ — s ac°I0:"` +o • = _ - • ^; ,*�°O°"" 'i
E O2 .......... «e Aaux► o-,Z879f`� Z97e
' 'a'. �.. 9
• `?:,,- 'oewrto '�ry . ice" f � 1• ''+. �.• ,y m
_ -."�unM�wr'` •��+ant+• �~'���
V66* 0�2��
Shelby Wiggins, Assistant Secretary
STATE OF FLORIDA
SS. Lake Mary
COUNTY OF SEMINOLE
On this 20th day of May. 2021. before me personally came Joelle LaPierre• to me known, who being by mo duly sworn, did doposo and say: that
(s)he resides in Seminole County, State of Florida; that (s)he is the Assistant Vice President of the Companies, the corporations described in and which
executed the above instrument; that (s)he knows the seals of the said corporations; that the seals affixed to the said instrument are such corporate seals;
that they were so affixed by authority of the Boards of Directors of said corporations and that (s)he signed his/her name thereto by like authority.
c c, o-.
I, the undersigned, Assistant Vice President of the Companies, DO HEREBY CERTIFY that the above and toregoing Is a true and correct
copy of the Power of Attorney executed by said Companies, which is still in full force effective as of October 27. 2022
Signed and sealed in Lake Mary. Florida.
v
Joelle L. LaPierre, Assistant Vice President
4� ''••, � re,.,e.re�:' 0a 7 ~ _ _rl r, r�e+c2•;� - `_3 u+ °""40
/ibibEl►
i
fir. l �Yr{i !Q
Keith D. Dozois, Assistant Vice President
State of: Texas
County of: Dallas
CONTRACTOR'S AFFIDAVIT OF
FINAL PAYMENT AND RELEASE
BEFORE ME, the undersigned authority, on this day personally appeared Marlene
Arrambide ("Affiant"), who, after being by me duly sworn and says BAR Constructors,
Inc. (the "Contractor"), which said Contractor was awarded the contract dated the 23rd day
of June 2020, for the construction of Lake Arlington Lift Station, Project No. 100995 (the
"Work"), for a total consideration of Ten Million Seventy Six Thousand Five Hundred
Thirty Nine Dollars and thirty Seven cents (10.076 539.37) to be paid to the said Contractor
(the "Contract"), and that the Affiant has full power of authority to make this affidavit.
That the City of Fort Worth (the "Owner") has approved the final estimate on said
Work, and that the said Contractor has fully satisfied and paid any and all claims that may
be covered by Chapter 53 of the Texas Property Code, and Article 5160 of the Revised
Civil Statutes of the State of Texas, or any other applicable statutes of charter provisions,
and that all just bills for labor and materials have been paid and discharged by said
Contractor insofar as they pertain to the Work in question.
That in addition to any funds which may have been previously paid by the Owner,
the Contractor hereby accepts the amount of Ten Million Seventy Six Thousand Five
Hundred Thirty Nine Dollars and thirty Seven cents (10 076 539.37) as FULL AND
FINAL PAYMENT under the aforementioned Contract, and hereby waives and releases
any right Affiant and/or the Contractor may have to pursue claims of any nature against
the Owner arising out of or in any manner connected with the performance of the Work
and/or the Contract, including but not limited to claims of third parties that supplied
material and/or labor for the Work for or through the Contractor ("Subcontractors"), as
well as claims for delay, additional compensation or for recovery of liquidated damages
which may have been withheld by the Owner. The Contractor shall defend, hold harmless,
and indemnify the Owner from any such claims of such Subcontractors. The Contractor
further releases the Owner from any claim or liability arising from any act or neglect of the
Owner related to or connected with the contract. This affidavit is given pursuant to the
final payment provisions of the Contract, and shall not be deemed to alter or modify the
terms and provisions of said Contract.
By
Secretary/Treasurer
Title
SUBSCRIBED AND SWORN TO BEFORE ME, this 1 Oth day of January 2023
Notary
��}pYAUp� SHERYL FLOYD CATHEY
Y SMbY PUBLIC
FTEXAs My commission expires: ( - l4-; y
OFT%MY COMM. EXP. 06/14124
NOTAgY ID 637376-5
CSC No. 54223-CO4
FO RX WO RT H City of Fort Worth
Change Order Request
ProjectName.-I Lake Arlington Lift Station City Sec No.: 1 54223 —�
Project No.(s):l 56019107004301001480 NTP N/A CIV Proj. No.: 100995
Project Description:1 Construction of a new Sanitary Sewer Lift Station for the Lake Arlington Force Main Project
Contractorl Bar Constructors Inc. Changs.Omer# r.-747-1 Date: 912612022
CItYP(()JerAM9Tj Pralima Poud al City Inspector. Nathan Gray
Phone Number. 817-392-6149 Phone Number. 817-392-4961
Dept. i Unit 1 Lift Station I Unit It Water ! Altemate A-2
Totals Contract Time
Original Contract Amount
22,126.00
$72,565.00
$583,002.00
'=$10077_ 03i00 °
'
487
Extras to Date
_
4�136."�4 "=
4$31,809.91
$0.00
$0.00
7 $ =:
232
Credits to Date
$0.00
_3 .5
Pending Change Orders (in M$C Process)
_--
ContractCast to Dale
s 4�5<0s2:13;3.�
z2 s �a0
$0f13 aaz ao.
080�6'1190
ZU .., . �_ ..
Amount of Prmosed Chanoe Order
72d d5 �
. ;° n,e _ .
_. a- n7
0- :� T d., a :.
Original funds Avaliable for Change Orders
Remaining Funds Available for this CO
Addilional Funding (if necessary)
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT
MAX ALLOWABLE CONTRA CT AMOUNT (ORIGINAL CONTRACT COST 4 25%)
Change Order No. 4 provides compensation for a sample pre -cast building panel for the electrical building before a final selection was made.
The change order also provides credits for remaining work for the 24" sanitary sewer line tie -In which Is being delayed until construction of
the force main. The credit Includes installation of remaining pipe, by-pass pumping, core hole into existing manhole, manhole coating and
weir wall Installation. Additional credit is also provided for remaining Commissioning Activities: pump performance testing, discharge
transmitter calibration, flow meter calibration, check valve adjustment, odor control testing, and level instrument calibration.
It Is understood and agreed that the acceptance of this Chanqe Order by the contractor constitutes an accord and
In full (both time and money) for all casts arising out of, or incidental to, the above Change Order.
9/2712022
-5, j Sep 28, 2022
Sep 29, 2022
M&C Number 1—NiA
MSC Date Approved
FO RT VV4 RT H City of Fort Worth
Change Order Additions
Project Name I Lake Arlington Lift Station City Sec No.: 54223
Project No.(s): 1 56019107004301001480 DOE No. N/A City Proj. No.: 100995
Project
Description
Construction of a new Sanitary Sewer Lift Station for the Lake Arlington Force Main Project
Contractor Bar Constructors Inc. Change Order:® Date: 9/26/2022
City Project Mgr. Pratima Poudyal City Inspector Nathan Gray
ADDITIONS
Fo RT Wo RT H City of Fort Worth
Change Order Deletions
Project Name F Lake Arlington Lift Station City Sec No.: 54223
Project No.(s): 1 56019107004301001480 DOE No. = City Proj, No.: 104995
Project Description
Construction of a new Sanitary Sewer Lift Station for the Lake Arlington Force Main Project
Contractor I Bar Constructors Inc. Change Order: ® Date 9/26/2022
City Project Mgr. I Pratima Poudyal City Inspector: Nathan Gray
DELETIONS
Page 2 of 3
MMBE Breakdown for this Chance Order
TotalR.
. . . ...... 4'e
.1* It N-S
Previous Change Orders
N -TUI
Total
it
Page 3 of 3
,Contract Compliance Manager
By signing I acknowledge that I am the person responsible
for the monitoring and administration of this contract, including
ensuring all performance and reporting requirements,
C
Signature
Pratima Poudyal, P.E.
Name of Employee
Project Manager
Title
ATTEST:
,7AWMet$ S GwWa
nvan. i Good>I1 lup �.=0�216:s; CJtI
Jannette Goodall
City Secretary
09/26/2022
CPN 100995
Lake Arlington Lift Station
Change Request 4 Notes
Staff has reviewed the change order price and considers it to be fair and reasonable.
FORT WORTH
December 29, 2022
Bar Constructors, Inc.
805 Katy Street
Lancaster, TX 75146
Re: Acceptance Letter
Project Name: Lake Arlington Lift Station
Project Type: Sewer
Project Ns: 100995
D.O.E. Ns: N/A
Contract Ns: 54223 Dated: 6/23/2020
Gentleman:
On December 01, 2022 a final inspection was made on the subject project. There were no punch list items
identified at the time. The final inspection indicates that the work meets the City of Fort Worth specifications and
is therefore accepted by the City. The warranty period will start on December 01, 2022, which is the date of final
inspection and will extend for (2) years in accordance with the Contract Documents.
If you have any questions concerning this letter of acceptance, please feel free to contact me at (817) 392-6054
Yours Truly,
Tony Sholola, P.E., Assistant Director Water Department
Q
cc: Chris Harder, P.E., Director, Water Department
Laura Wilson, P.E., Deputy Director, Water Department
Captain Michael Skains, Fire Department
Cesar Zavala, Field Operations Superintendent, Water Department
Luke Coffman, Field Operations Superintendent, Waste Water Department
Pratima Poudyal, P. E., Project Manager, Water Department Capital Delivery
Olivia Kerss, P. E., Freese and Nichols, Inc., Consultant
Bar Constructors, Inc., Contractor
David Johnson, Inspection Supervisor, Water Department Capital Delivery
Nathan Gray, Inspector, Water Department Capital Delivery
File
WATER DEPARTMENT
ENGINEERING AND FISCAL SERVICES
THE CITY OF FORT WORTH * 1000 THRocKMORTON STREET * FORT WORTH, TEXAS 76102
817-392-8240 * FAx 817-392-8195
t� Printed on recycled paper