HomeMy WebLinkAboutContract 57461-CO1CSC No. 57461-COI
FORT WORTH, City of Fort Worth
Change Order Request
Project Name 8th Ave Safety and Circulation Improvements Project City Sec # F57461
Client Project #(s)
This is a Pedestrian Safety and traffic Circulation improvements project
Contractor Fain Group, Inc. Change Order # 1 Date 2/7/2023
City Project Mgr. I Jose A Orozco City Inspector Byron McDonald
Dept.
Original Contract Amount
Extras to Date
Credits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Date
Paving - Unit I
Irrigation- Unit II
Totals
Contract Time
CD
$1,015,549.01
$32,992.06
$1,048,541.07
150
$1,015,549.01
$32,992.06
$1,048,541.07
150
Amount of Proposed Change Order
$23,741.74
$0.00
$0.00
$23,741.74
167
Revised Contract Amount $1,039,290.75 $32,992.06
Original Funds Available for Change Orders $50,777.45 $1,649.60
Remaining Funds Available for this CO $50,777.45 $1,649.60
Additional Funding (if necessary)
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST + 25%)
$1,072,282.81
317
$52,427.05
$52,427.05
2.26%
$1,310,676.34
�1111. JUSTIFICATION (REASONS) FOR CHANGE ORDER s
IN ACCORDANCE WITH THIS CHANGE ORDER, THE CONTRACTOR SHALL: Furnish all labor and material as per the proposed Change Order. This Change
Order will cover the increase in asphalt material cost and remobilization due to postponing the new pavement improvements at 8th Ave and Cooper until the new
Cook Children's Medical Center Contractor removed the lane closure on 8th Ave on 12/19/2022. Fain provided the City with documentation from asphalt
subcontractor pricing at the time of bidding and the new price due to the delays in the project. This change order will also add additional 150 days due to this delay.
It will also add 10 additional days for utility conflict with the gas, and 7 days for inclement weather, which also triggered changing the light street foundation. The
change order will also include the new bid items needed to remove the existing traffic signal cabinet located at 8th and Terrell Ave to transfer service to the newly
installed traffic poles. The City of Fort Worth has compared the unit prices which are being proposed by the contractor to other similar items and accepts the unit
costs. The difference in pricing can be justified by the current market pricing, which fluctuates on a monthly basis due to price escalation and inflation. The City
finds that the prices that the contractor is proposing are fair and reasonable. The average pricing was compiled from similar items from the 2022 Traffic Signal and
Street Lighting Improvements Unit Price Construction Contract bid tabs.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents
payment in full (both time and money) for all costs arising out of, or incidental to, the above Change Order. The Project/Program Manager signing
below acknowledges that he/she is the person responsible for the monitoring and administration of this contract, including ensuring all performance
and reporting requirements.
Contractor's Company Nam
Fain Group, Inc. Larry Frazier
ate
Feb 8, 2023
Inspector/Inspection Supervisor
Date
Project and Contract Compliance Manager
Date
awa
Feb 8, 2023
Feb 9, 2023
Program Manager
Date
Senior Capital Project Officer
Date
Feb 9, 2023
z--- mow,
Feb 9, 2023
Assistant Director (Dept)
Date
nt (Dept)
Date
Feb 9, 2023
—A--�-
Feb 9, 2023
Assistant City Attorney
Date
JAssistant CityManager
Date
Feb 13, 2023
Feb 10, 2023
Council Action (if require
o88son>w�
;tee
ATTEST:"t
Jannette Goodall, City Secretary
M&C Number I N/A M&C Date Approved N/A
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
FORT WORTH City of Fort Worth
Change Order Additions
Project Name 8th Ave Safety and Circulation Improvements Project City Sec # 57461
Client Project #
Contractor Fain Group, Inc. PM Jose A Orozco Inspector Byron McDonald
Change Order Submittal # 0 Date 2I712023
ADDITIONS
ITEM
DESCRIPTION
DEPT
ty
Unit
Unit Cost
Total
0302 2"Asphalt Base Type D
777i—ng-7717-7770-000000
3212.0401 HMAC Transition
avmg - nit
5.
TN
385.00
, 5.
3212.0503 6" Asphalt Base Type B
awng - mt
SY
50.60
3212.0600 HMAC Pavement Level Up
avmg - nit
5.
TN
385.00
, 5.
106
0 70.0101 Remobilization
avmg - n
EA
2,600.00
107
9999.021 Remove Existing Cables From Traffic Signal Cabinet & Reterminate
avmg - nit
LS
1,725.00
,7 5.
108
3441.1507 Remove Ground Box
Paving - Unit 1
2.00000000
EA
$402.50
109
3441.1709 Ped Pole (10-14) Spread Footing Foundation
awng - Unit I
EA
2,452.40
5 .
110
3441.1749 Remove Signal Controller Cabinet Assembly
awng - n
EA
2,025.00
111
3441.2011 Remove signal cabinet foundation
avmg - nit
LS
2,000.00
1 2
9999.0018 Miscellaneous adjustments Irrigation
awng - mt
LS
1,725.00
113
9999.0019 Flags over RRFB's
awng - nit
EA
88.44
5
114
9999.0020 Additional Cost for modified TY 7 Foundation
avmg - mt
EA
750.00
Paving - Unit 1
120,657.04
Irrigation- Unit II
$0.00
$0.00
Sub Total Additions
20,657.04
Change Order Additions Page 2 of 4
FOR?� City of Fort Worth
Change Order Deletions
Project Name 8th Ave Safety and Circulation Improvements Project City Sec # 57461
Client Project #
Contractor Fain Group, Inc. PM Jose A Orozco Inspector Byron McDonald
Change Order Submittal # Date 2I7I2023
DELETION5
�IL31'1�
' •'
�'Li��s:�f��'L���'m�.rx�i��
3212.0302
.11 11111 I I I`
�$:iR'Y.YAI11
�P212.0401
HIMAC Transition'.
�
11111111®
��[SYhb7
•
�
11111111�
I 1
' I 1
Paving - Unit 1
I
Irrigation- Unit 11
1 11
11
Sub Total Deletions
�� �7��.�y$��0
iYYYYY
Change Order Deletions Page 3 of 4
Previous Change Orders
CO # DATE AMOUNT
Total $0.00
FORT WORTH
Routing and Transmittal Slip
Transportation & Public Works
Department
DOCUMENT TITLE: 8t" Ave Safety and Circulation Improvements
M&C
CPN 102842 CSO # 57461 DOC#
DATE: 2/7/2023
TO:
INITIALS
DATE OUT
1.
Ilianisse Figueroa Aponte
- Review
FA
Feb 97 2023
2�
Larry Frazier
Ifrazier(c�faingp.com
_signaturer�
Feb 8, 2023
3.
Byron McDonald
- signature
1,5M
Feb 8 2023
,
4.
Gary Deyon
- signature
0�
Feb 9, 2023
5.
Jose Orozco
- signature
I�
JAO
Feb 9 2023
,
6.
Mary Hanna
- signature
INS
Feb 9, 2023
7.
Leon Wilson
- signature
I Z- a,/
Feb 9 2023
8.
Michael Owen
- signature
I—
Feb 9, 2023
9.
Lauren Prieur
- signature
I�
I Feb 9, 2023
10.
William Johnson
- signature
IW�
Feb 10, 2023
11.
Doug Black
- signature
Ids
Feb 13, 2023
12.
Jannette Goodall
- signature
I4a--
Feb 14, 2023
13.
TPW Contracts
I
DOCUMENTS FOR CITY MANAGER'S SIGNATURE: All documents received from any and all City
Departments requesting City Manager's signature for approval MUST BE ROUTED TO THE
APPROPRIATE ACM for approval first. Once the ACM has signed the routing slip, David will review
and take the next steps.
NEEDS TO BE NOTARIZED: ❑ Yes ® No
RUSH: ❑ Yes ® No SAME DAY: ❑ Yes ❑ No NEXT DAY: ❑ Yes ❑ No
ROUTING TO CSO: ® Yes ❑ No
Action Required:
❑ As Requested
❑ For Your Information
® Signature/Routing and or Recording
❑ Comment
❑ File
❑ Attach Signature, Initial and Notary Tabs
Return To: Please calITPW Contracts at ext. 7233 for pick up when completed. Thank you.