HomeMy WebLinkAboutResolution 5691-02-2023 A Resolution
NO. 5691-02-2023
STATEMENT EXPRESSING
OFFICIAL INTENT TO REIMBURSE
EXPENDITURES WITH PROCEEDS OF FUTURE DEBT FOR THE WALNUT
CREEK SANITARY SEWER EXTENSION
WHEREAS, the City of Fort Worth, Texas (the "City") is a home-rule municipality
and political subdivision of the State of Texas; and
WHEREAS, the City expects to pay expenditures in connection with the design,
planning, acquisition and construction for the Walnut Creek Sanitary Sewer Extension
Project (the "Project") prior to the issuance of obligations by the City in connection with
the financing of the Project from available funds; and
WHEREAS, the City finds, considers, and declares that the reimbursement of the
City for the payment of such expenditures will be appropriate and consistent with the
lawful objectives of the City and, as such, chooses to declare its intention, in accordance
with the provisions of Section 1.150-2 of the Treasury Regulations, to reimburse itself for
such payments at such time as it issues obligations to finance the Project;
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF FORT WORTH, TEXAS, THAT:
Section 1. The City reasonably expects debt, as one or more series of obligations,
may be issued or incurred by the City with an aggregate maximum principal amount not to
exceed $13,400,000.00 for the purpose of paying the aggregate costs of the Project.
Section 2. All costs to be reimbursed pursuant hereto will be capital expenditures.
No obligations will be issued by the City in furtherance of this Statement after a date
which is later than 18 months after the later of (1) the date the expenditures are paid or
(2) the date on which the property, with respect to which such expenditures were made, is
placed in service.
Section 3. The foregoing notwithstanding, no obligation will be issued pursuant to
this Statement more than three years after the date any expenditure which is to be
reimbursed is paid.
Adopted this 14"' day of February 2023.
ATTEST: ,1,'
(
F0000*_�O-P.
&�
0o~� z
°
By: ° Aa�'
��
*Jannette S. Goodall City Secretary °
°O°°°°°° d
,o
a�nEXa soap'
MAYOR AND COUNCIL COMMUNICATION MAP
60WCREEKSSEP1 -SJLOUIS
zY
•� °+� R I, ^ l(��a"��M", � � t�l`�- ':
j,�` .. ; I' _ � �°; is �,. ' ,,.....!•- .M`...,.._.._.,,.�' F i° '--�}�,r a f�.1 - �
SILVER SADDLERD
_ - -
cco
f
CORP04,....RAT�IONPKWY
EB'EXIBLu
``
Lul
ul
y 0� C9O _
Q' A� i r"Z
�
IWESTR GERD
5r7 w' ov `
oo V
UNION PACIFIC RR
_
Kvv
Lu
y a- P
�y CO INAD eROL�ILIN'T G H LL¢SDR qA�/�r - p;�,1DE
` C
R�pGEID y0O REGENTROW
TR�AI RIB D ED TRAIL a �r
���. E cKSLEYD
GI ",�
GOL'FVIEWWAYti
KWY
'JERRY:DUNNP NRpy �
RPNG
FoRTWORTH8,.,,D
3'�a r
City of Fort Worth,Texas
Mayor and Council Communication
DATE: 02/14/23 M&C FILE NUMBER: M&C 23-0129
LOG NAME: 60WCREEKSSEPI-SJLOUIS
SUBJECT
(CD 3/Future CD 3)Authorize Execution of a Contract with S.J. Louis Construction of Texas,Ltd.in the Amount of$10,424,212.97 for Phase 1 of
the Walnut Creek Sanitary Sewer Extension,Adopt Resolution Expressing Official Intent to Reimburse Expenditures with Proceeds of Future Debt,
and Adopt Appropriation Ordinance to Effect a Portion of Water's Contribution to the Fiscal Years 2023-2027 Capital Improvement Program
RECOMMENDATION:
It is recommended that the City Council:
1. Authorize execution of a contract with S.J. Louis Construction of Texas, Ltd. in the amount of$10,424,212.97 for phase 1 of the Walnut Creek
Sanitary Sewer Extension project;
2. Adopt the attached resolution expressing official intent to reimburse expenditures with proceeds from future debt for phase 1 of the Walnut
Creek Sanitary Sewer Extension project;and
3. Adopt the attached appropriation ordinance adjusting appropriations in the W&S Commercial Paper Fund by increasing appropriations in
the Walnut Creek Sanitary Sewer Extension project(City Project No.103414)in the amount of$11,169,635.00 and decreasing
appropriations in the W&S Commercial Paper Fund project(City Project No. UCMLPR)by the same amount to effect a portion of Water's
Contribution to the Fiscal Years 2023-2027 Capital Improvement Program.
DISCUSSION:
This Mayor and Council Communication(M&C)is to authorize a construction contract with S.J. Louis Construction of Texas, Ltd, and appropriate
funding for phase 1 of the Walnut Creek Sanitary Sewer Extension,from Chapin School Road to Markum Ranch Road.
The project was advertised for bid on October 27, 2022 and November 3, 2022 in the Fort Worth Star-Telegram. On December 1, 2022 the
following bids were received:
Bidder Bid Amount Calendar Days
S.J.Louis Construction of Texas, $10684 360 Calendar
Ltd. , ,818.00 Days j
McKee Utility Constructors, Inc. $13,951,068.00
In addition to the contract cost, $484,817.00 is required for project management and inspection and$260,605.00 is provided for project
contingency.
This project will have no impact on the Water Department's operating budget when complete.
It is the practice of the Water Department to appropriate its CIP plan throughout the fiscal year, instead of within the annual budget ordinance,as
projects commence,additional funding needs are identified,and to comply with bond covenants.The actions in the M&C will amend the City of
Fort Worth's Fiscal Year 2023-2027 Capital Improvement Program as follows:
60WCREEKSSEPI-SJLOUIS
Capital Revised
Project FY2023 CIP Budget Change
Fund Authority FY2023
Name Name Appropriations (Increase/Decrease) 9
Bud et
103414-1
56021 - Walnut
W&S Creek $0.00Lis M&C' $11,169,635.00 $11,169,635.00
Commercial Sanitary
Paper Sewer
Extension �
Funding is currently available in the W&S Commercial Paper project within the W&S Commercial Paper Fund for the purpose of funding the
Walnut Creek Sanitary Sewer Extension.
Funding for the Walnut Creek Sanitary Sewer Extension project is depicted below:
Existing ( Additional
FUND L ( Project Total*
Appropriations Appropriations;
i
W&S Rev Bonds j
Series 2022- $2,154,511.00! $0.00 $2,154,511.00'
Fund 56020
7=
W&S Commercial IL $0.001 $11,169,635.00;$11,169,635.00
Paper Fund 56021
Project Total $2,154,511.00 $11,169,635.00 $13,324,146.00
I i �
*Numbers rounded for presentation purposes.
This project is anticipated to be included in a future revenue bond issue for the Water& Sewer Fund.Available cash within the Water and Sewer
portfolio and the City's portfolio along with the appropriation authority authorized under the Callable Commercial Paper Program(CP)will be used
to provide interim financing for this project until debt is issued. Once debt associated with this project is sold, bond proceeds will be used to
reimburse the Water and Sewer portfolio and the City's portfolio in accordance with the attached reimbursement resolution. Under federal law,
debt must be issued within approximately three years in order for these expenses to be reimbursable.Adoption of the attached resolution does not
obligate the City to sell bonds, but preserves the ability of the City to reimburse itself from tax-exempt bond proceeds.
Business Equity- S.J. Louis Construction of Texas, Ltd. is in compliance with City's Business Equity Ordinance by committing to 17
percent Business Equity participation on this project.The City's Business Equity goal on this project is 17 percent.
The project is located in COUNCIL DISTRICT 3/FUTURE COUNCIL DISTRICT 3.
FISCAL INFORMATION I CERTIFICATION:
The Director of Finance certifies that funds are currently available in the W&S Commercial Paper UCMLPR project within the W&S Commercial
Paper Fund and upon approval of the above recommendations and adoption of the attached appropriation ordinance,funds will be available in the
W&S Commercial Paper Fund for the Walnut Creek SS Extension project to support the execution of the construction contract. Prior to an
expenditure being incurred,the Water Department has the responsibility of verifying the availability of funds.
Submitted for City Manager's Office by: Dana Burghdoff 8018
Originating Business Unit Head: Chris Harder 5020
Additional Information Contact: Preeti KC 5467
Expedited