HomeMy WebLinkAboutContract 57657-A1Date Received: Mar 1, 2023
Time Received: 3:13 p.m. (2/28/23)
City Secretary
Contract No.: 57657-A1
FIRST AMENDMENT TO CITY SECRETARY CONTRACT NUMBER 57657
A COMMUNITY FACILITIES AGREEMENT BETWEEN
THE CITY OF FORT WORTH AND ORCHARD FARMS VENTURES, LLC
This FIRST AMENDMENT TO CITY SECRETARY CONTRACT NUMBER 57657
("First Amendment") is made and entered into by and between the City of Fort Worth ("City"),
a home -rule municipal corporation of the state of Texas, and Orchard Farms Ventures, LLC
("Developer"), a Florida limited liability company.
WHEREAS, the City and Developer entered into a Community Facilities Agreement for
the construction of public infrastructure Improvements for a Project known as Orchard Village
Phase IA, City Project Number 101759, City Secretary Contract No. 57657 ("CFA"); and
WHEREAS, prior to proceeding to construction pursuant to the CFA Developer has hired
a new contractor to construct the Improvements; and
WHEREAS, City and Developer desire to amend the CFA to reflect the new contractor,
the revisions to the project cost and estimated fees for the project, and the increase in the financial
guarantee;
NOW THEREFORE, City and Developer, acting herein by and through their duly
authorized representatives, enter into the following agreement, which amends City Secretary No.
57657:
Section 36 of the CFA is amended in its entirety to be and read as set forth in Exhibit A of this
First Amendment.
2.
The Cost Estimates in the CFA are amended in their entirety to be and read as set forth in
Exhibit B of this First Amendment.
3.
Section 5 of the CFA is amended to add the following sentence after the first paragraph:
In connection with hiring a new contractor to construct the Improvements and the
associated increase in cost for the Improvements, Developer has provided the City with a bond
rider to increase the development bond provided for the CFA to $4,209,316.00.
City of Fort Worth, Texas
First Amendment to City Secretary Contract No. 57657
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
4.
Section 14 of the CFA is amended to add the following sentence after the first paragraph:
In connection with hiring a new contractor to construct the Improvements and the
associated increase in construction inspection service fees, Developer has paid to the City an
additional $10,750.00 in construction inspection service fees.
5.
a. All other provisions of City Secretary Contract No. 57657 which are not expressly
amended herein, shall remain in full force and effect.
b. All terms in this First Amendment that are capitalized, but not defined, shall have the
meanings ascribed to those terms in City Secretary Contract No. 57657.
[SIGNATURES ON FOLLOWING PAGE]
City of Fort Worth, Texas
First Amendment to City Secretary Contract No. 57657
IN TESTIMONY WHEREOF, the City and Developer have executed this First
Amendment to be effective on the date signed by the City's Assistant City Manager.
CITY OF FORT WORTH
��q �I�GILIG�Oi�
Dana Burghdoff (Fe 27, 202 1 :53 CST)
Dana Burghdoff
Assistant City Manager
Date: Feb 27, 2023
Recommended by:
Dwayne Hollars (Feb 27, 202314:24 CST)
Dwayne Hollars
Contract Compliance Specialist
Development Services
Approved as to Form & Legality:
4r2, -
Richard A. McCracken (Feb 27, 2023 14:27 CST)
Richard A. McCracken
Sr. Assistant City Attorney
M&C No. N/A
Form 1295: N/A
2
ATTEST:
%00 V DOS T�
?� 000000ao a
n� AiXA?z�o,
Jannette S. Goodall
City Secretary
DEVELOPER
Orchard Farms Ventures, LLC
J Boyce (Feb 27, 29 15:19 EST)
James Boyce
Authorized Signatory
Date: Feb 27, 2023
Contract Compliance Manager:
By signing, I acknowledge that I am the
person responsible for the monitoring and
administration of this contract, including all
performance and reporting requirements.
M,,&\
Rebecca Diane Owen (Feb 27, 2023 14:25 CST)
Name: Rebecca Diane Owen
Title: Development Manager
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
City of Fort Worth, Texas
First Amendment to City Secretary Contract No. 57657
EXHIBIT A
36.
Cost Summary Sheet
Project Name: Orchard Village Phase IA
CFA No.: CFA18-0147 City Project No.: 101759 IPRC No.: IPRC18-0045
Items
A. Water and Sewer Construction
1. Water Construction
2. Sewer Construction
Water and Sewer Construction Total
B. TPW Construction
1. Street
2. Storm Drain
3. Street Lights Installed by Developer
4. Signals
TPW Construction Cost Total
Total Construction Cost (excluding the fees)
Estimated Construction Fees:
C. Construction Inspection Service Fee
D. Administrative Material Testing Service Fee
E. Water Testing Lab Fee
Total Estimated Construction Fees:
Financial (4uarantPP (7ntinnc chnncP nnP
Developer's Cost
$ 841,309.00
$ 737,784.00
$ 1,579,093.00
$ 1,864,038.00
$ 567,050.00
$ 199,135.00
$ 2,630,223.00
$ 4,209,316.00
$68,750.00
$21, 315.00
$1, 290.00
$ 91,355.00
Choice
dmnunt Mark nnPI
Bond = 100%
$ 4,209,316.00
Completion Agreement = 100% / Holds Plat
$ 4,209,316.00
X
Cash Escrow Water/Sanitary Sewer= 125%
$ 1,973,866.25
Cash Escrow Paving/Storm Drain = 125%
$ 3,287,778.75
Letter of Credit = 125%
$ 5,261,645.00
City of Fort Worth, Texas
First Amendment to City Secretary Contract No. 57657
EXHIBIT B
SECTION 00 42 43
Developer Awarded Projects - PROPOSAL FORM
Orchard Village Phase IA
City Project 101759
UNIT PRICE BID
Bidder's Application
Project Item Inf'onnation
Bidders Proposal
Bidlist
Item No.
Description
Specification Section No.
I
Unit of I Bid
I Measure Quarn
Unit Pnce
Bid Value
UNIT k WATER IMPROVEMENTS
1
3311.0261 W PVC Water Pipe
3311 10 3311 12
LF
1 4,736
1 $54.001
$255,744.00
2
33123003 8" Gate Valve & Valve Box
33 12 20
EA
1 23
$1,500.00'
$34,500.00
3
3311.0341 10" PVC Water Pipe
33 11 10 3311 12
LF
1.955
$68.001
$132,940.00
4
33123004 10" Gate Valve & Valve Box
33 12 20
EA
5
$2,200.00
$11 000.00
5
3312.0001 Std. Fire Hydrant Assembly wl 5' Gate Valve & Valve F
33 12 40
EA
8
$48.00
$354.00
6
3311.0001 Ductile Iron Water Fittings wJ Restraint
3311 11
TON
1.4
$15.000.00
$21.000.05
7
3305.0109 Trench Safety
33 05 10
LF
6 691
$1.00
$6,691.00
8
13312.2003 1" Domestic Water Services
33 12 10
EA
225
$1,150.00
$258.750.00
9
33122003 1" Irrigation Water Services
33 12 10
EA
1
$1.500.00
$1 500.00
10
3312.4113 16"x 1 (Y'Tappina Sleeve & Valve
33 12 25
EA
1
$9 500.00
$9 500.00
11
3305.0003 8" Waterline Lowering
33 05 12
1 EA
5
$3.500.00
$17.500.00
12
%99.0001 16' Ebsbn Waterline Lowering33
05 12
EA
1
$55,300.00
$55,300.00
13
3312 3006 16" Gate Valve w/ Vault
33 1220
1 EA
1 1
$36 500.00
$36.500 00
TOTAL UNIT I: WATER
IMPROVEMENTS
$941,309,00
tIN1T II: SANITARY 5EWER
IMPROVEMENTS
14
3331.4115 8" SDR-26 PVC Sewer Pipe
33 11 10, 33 31 12,
33 31 20
LF
5,660
$62.00
$350,920.00
15
3331.3101 SDR-26 4" Sewer Services
33 31 50
EA
225
$850.00
$191,250.00
16
3339.1001 4' Std. Dia. Manhoe
33 39 10 33 39 20
EA
25
$4,500.00
$112,500.00
17
3339.1003 Extra Depth for 4' Dia. Manhole
33 39 10 33 39 20
LF
38
$225.00
$8,550.00
18
3331.4116 8" PVC Sanitary Sewer Pipe w! CSS Backfill
JS
3120
LF
418
$72.00
$30,096.00
19
3305.0109 Trench Safety
33 05 10
LF
6.078
$2.00
$12,156.00
20
3301.0002 Post -CCTV Inspection
33 01 31
LF
6 078
$4.00
$24,312.00
21
9999.0002 Connect to 8" Sewer in Phase 2
00 00 00
EA
2
$7,500.00
$3,000.00
22
3301.0101 Vacuum Test Manholes
3301 30
EA 1
25
$200.00
$5,000.00
TOTAL UNIT
I: SANITARY SEWER
IMPROVEMENTS
$737 784.00
UNIT IN: STORM DRAIN
MPROVEMENTS
23
3349.5001 10' Curb Inlet
33 49 20
1 EA
14
$3.800.001
$53,200.00
24
3349.5002 16 Curb Inlet
334920
EA
2
$000.00
$9,600.00
25
3349.5003 29 Curb Inlet
334920
EA
3
$5.800.001
$17,400.00
26
3341.0201 21" Class III R.C.P.
3341 10
1 LF
550
$72.00
$39,600.00
27
3341.0205 24" Class III R.C.P.
3341 10
LF
997
$82.00
$81.754.00
28
3341.0302 30" Class III R.C.P.
3341 10
LF
308
$110.00
$33,880.00
29
3341.0402 42" Class III R.C.P.
333 10
LF
248
$160.00
$39,680.00
30
9999.0003 5' x 2' Box Culvert
33 41 10
LF
1 289
1 $330.00
$95 370.00
31
3341.1302 6' x 3' Box Culvert
3341 10
LF
1 131
$420.00
$55,020.00
32
3349.4104 21" Class III R.C.P. Sbped End Headwall
334940
EA
1
$3,000.00
$3,000.00
33
3349.4204 Double 21" Class III R.C.P. Sloped End Headwall
334940
EA
2
$5,500.00
$11,000.00
34
9999.0004 5'x2'Soped End Headwall
36 49 40
EA
1
$5,000.00
$5 000.00
35
9999.0005 6' x 3' Sbped End Headwall
364940
EA
2
$7,500.00
$15,000.00
36
3349.0001 4 x 4' Sbryn Junction Box
334910
EA
5
$5 500.00
$27 500.00
37
19999.0006 6 x 4' Storm Junction Box
34 49 10
EA
1
$7,500.00
$7,500.00
38
9999.0007 7 x 4' Storm Junction Bolt
34 49 10
EA
2
$8,500.00
$17,000.00
39
3305.0109 Trench Wet
330510
LF
2,523
$2.00
$5,046.00
40
3305.0112 Concrete Collar
330517
EA
3
$1.000.00
$3,000.00
41
3137.0104 Medium Stone Ri ra . d
31 3700
SY
380
$125.00
$47 500.00
TOTAL
UNIT III: STORM DRAIN IMPROVEMENTS
SW7,050.00
City of Fort Worth, Texas
First Amendment to City Secretary Contract No. 57657
SECTION 00 42 43
Developer Awarded Projects - PROPOSAL FORM
Orchard Village Phase 1A
City Projccf 101759
UNIT PRICE BID
Bidder's Application
Project Item Infommtion
Bidder's Proposal
Bidlist
Description Specification Section No.
Unit of
Bid
I
Unit Price
Bid Value
Item No.
Measure
Quantity
UNIT IV: PAVING IMPROVEMENTS
42
3213-0101 6" Concrete Pavement (Residential
32 13 13
SY
22 619
$48.00
$1,085,712.00
43
3213.0101 6" Concrete Pavement (Alley)
32 13 13
SY
5.95E
$52.00
$309.712.00
44
3211.0501 6" Lime Treated Su rade (Residential)
32 11 29
SY
30 546
$4.00
$122,184.00
45
3211.0400 Hydrated Lime 36 lbs./S.Y. Residential
32 11 29
TON
550.0
$245,00
$134,750.00
46
3213.0501 R-1 Ramp
32 1320
EA
17
$2,200.00
$37,400.00
47
3213.0506 P-1 Ramp
32 1320
EA
50
$2,000.00
$100,000 00
48
13213.0302 5' Concrete Sidewalk
32 12 20
LF
1 1,676
$20.00
$33,520.00
49
9999.0008 End of Road Barricade
00 00 00
EA
4
$800.00
$3,200.00
50
9999.0009 Concrete Header
00 00 00
LF
116
$25,00
$2,900.00
51
9999.0010 Sav,cut & Dispose of Concrete Curb & Gutter
00 00 00
LF
69
$30.00
$2,070.00
52
9999.00010 St Sign w/Stop Sin
00 00 DO
EA
17
$850.00
$14,450.00
53
9999.0011 St Marker Blade
00 00 00
EA
34
$250.00
$8.500.00
54
3291.0100 Topsoil
32 91 19
CY
78
$28.00
$2,184.00
55
3292.0100 Block Sod Placement
32 92 13
SY 1
932
$8.00
$7 456.00
TOTAL UNIT IV: PAVING
IMPROVEMENTS
$1,864,038.D0
Bid Summary
UNIT I: WATER IMPROVEMENTS $841.309.00
UNIT 11: SANITARY SEWER IMPROVEMENTS $737,784.00
UNIT III: STORM DRAIN IMPROVEMENTS $567,050.00
UNIT IV: PAVING IMPROVEMENTS $1 864 038.00
This bid is submitted by the entity listed below
Conatser Construction TX, L.P. By: Brock Huggins
5327 Wichita Street t
Ft. Worth, TX 76119
817-534-1743 SignAKrW
Title: President
Date: 12/30/2022
Contractor agrees to complete WORK fur FINAL ACCEPTANCE wltbin 220 working days after the date when the
CONTRACT commences to run as provided in the General Conditions.
END ON' SECTION
City of Fort Worth, Texas
First Amendment to City Secretary Contract No. 57657
SECTION 00 42 43
Developer Awarded Projects - PROPOSAL FORM
Orchard Village Phase to
City Projecl ID1754
UNIT PRICE BID
Bidder's Application
Project Item Information
Bidders Proposal
Bidlisl
Description
Specification Section No.
Unit of
Bid
Unit Price
Bid Value
Item No,
Measure
Quantity
UN V: STREET LIGHTING IMPROVEMENTS
55
3441.3201 LED Lighting Fixture
34 41 20
EA
27
$750.00
$20,250.00
56
2605.3011 2" Conduit PVC SCH 40 T
26 05 33
LF
2 165
$14.00
$30,310.00
57
3441.1408 No. 6 Insulated Elec Condr
34 4112
LF
6,495
$5.00
$32,475.00
58
3441.3301 Rd Illumination Foundation T 1
34 41 2O
EA
27
$1,200.00
$32,400.00
59
3441.3341 Rdwy Illumuminabon Pole Type 11
3441 10
1 EA
1 27
$3 100.00
$83,700.00
TOTAL UNIT
V: STREET LIGHTING
IMPROVEMENTS
$199.135.00
This bid is submitted by the entity listed below:
Conatser Construction TX, L.P By: Brock Huggins
5327 Wichita Street
Ft Worth, TX 76119
817-534-1743 r Sig
Title: President
Date: 12/30/2022
Contractor agrees to complete WORK for FINAL ACCEPTANCE within 30 working days after the date when the
CONTRACT commences to run as provided in the General Conditions.
END OF SECTION