HomeMy WebLinkAboutContract 59061PROJECT MANUAL
FOR
THE CONSTRUCTION OF
Mattie Parker
Mayor
2022 Water Service Leak
Repair Contract
City Project No. 104552
Christopher Harder, P .E.
Water Director
Prepared for
The City of Fort Worth
Water Department
2022
• •• •• • • • •
··············· ... ENCE HAMILTO ...•........... ,.
• 90528 ~-
··~!P.ENS~~· •• .,J
····•~f§.✓
N~;.!.~
1~( i( ( Jt/J _-:L
.
David Cooke
City Manager
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
CITY OF FORT WORTH, TEXAS
WATER DEPARTMENT
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No. 104552
CHRISTOPHER HARDER, P.E.
DIRECTOR
WATER DEPARTMENT
2022
APPROVED b 5Aoll 12 /2-t /zoz2._
TONY seod u, P.E., ASSISTANT DIRECTOR, WATER DEPARTMENT
~~ ~-,;i.,f )., I J.e )-'l..
RE DMMENDED DATE 1
FORT WORTH ®
City of Fort Worth
Standard Construction Specification
Documents
Adopted September 2011
00 00 00
STAN DARD CONSTRUCTI ON SPECIFICATION DOCUMENTS
SECTION 00 00 00
TABLE OF CONTENTS
Division 00 -General Conditions
00 05 10 Mayor and Coun ci l Communication
00 05 15 Addenda
00 11 13 Invitation to Bidders
00 21 13 Instructions to Bidders
00 35 13 Conflict oflnterest Statement
00 41 00 Bid Form
00 42 43 Proposal Form Unit Price
00 43 13 Bid Bond
00 43 37 Vendor Compliance to State Law Nonresident Bidder
00 45 11 Bidders Prequalifications
00 45 12 Prequalification Statement
00 45 13 Prequalification Application
00 45 26 Contractor Compli ance with Workers' Compensation Law
00 45 40 Business Equity Goal
00 52 43 Agreement
00 61 13 Performance Bond
00 61 14 Payment Bond
00 61 19 Maintenance Bond
00 61 25 Certificate of Insurance
00 72 00 General Conditions
00 73 00 Supplementary Conditions
ff . . 01 G IVISIOn -enera IR t eqmremen s
01 11 00 Summary of Work
01 25 00 Substitution Procedures
01 31 19 Preconstruction Meeting
01 31 20 Project Meetings
013216 Construction Schedule
01 32 33 Preconstruction Video
01 33 00 Submittals
01 35 13 Special Project Procedures
01 45 23 Testing and Inspection Services
01 50 00 Temporary Facilities and Controls
01 55 26 Street Use Permit and Modifications to Traffic Control
015713 Storm Water Pollution Prevention Plan
01 58 13 Temporary Project Signage
01 60 00 Product Requirements
01 66 00 Product Storage and Hand lin g Requirements
01 70 00 Mobilization and Remobilization
01 71 23 Construction Staking and Survey
017423 Cleaning
017719 Closeout Requirements
01 78 23 Operation and Maintenance Data
01 78 39 Project Record Documents
CITY OF FORT WORTH
STANDARD CON STRUC TION SP EC IFI CATION DO CUMENTS
Revi sed September 9, 2022
Page I of4
Last Revised
07/01 /2011
07/01 /2011
07/19/2021
11/02/2 021
02 /24/2020
09/30/2021
01 /20 /2012
09 /11/2017
06/27 /2011
08 /13 /2011
09/30 /2021
08 /13 /2021
07/01/2011
10 /27/2021
11 /23 /2021
07/01 /2011
07 /01 /2011
07 /01 /2011
07 /01 /20 11
08 /23/2021
03 /09 /2020
as ev1se L tR . d
12 /20/2012
07/01 /2011
08 /17 /2012
07/01 /2011
08/13 /2021
07/01/2011
12 /20/2012
03 /11/2022
03 /09 /2020
07/01 /2011
03 /22 /202 1
07/01 /2011
07 /01 /201 1
03 /09/2020
07 /01 /2011
11/22/2016
02/14/2018
07/01/2011
03 /22/2021
12/20/2012
07 /01/2011
2022 WATER SERVI CE LEAK
REPAIR CONTRACT
City Project No . 104552
00 00 00
STA N DARD CON STRUC TI ON SP EC IFIC ATION DOCUMENTS
Page 2 of 4
Technical Specifications which have been modified by the Engineer specifically for this
Project; hard copies are included in the Project's Contract Documents
Division 02 -Existin Conditions
02 41 14 Utilit Removal/Abandonment
Division 03 -Concrete
None
Division 26 -Electrical
None
Division 31 -Earthwork
None
iv1s1on -D . . 32 E xtenor mprovemen s I t
32 01 17 Permanent Asphalt Paving Repair
32 01 29 Concrete Paving Repair
32 17 23 Pavement Markings
32 91 19 Topsoil Placement and Finishing of Parkways
32 92 13 Hydro-Mulching, Seeding, and Sodding
Division 33 -Utilities
33 12 10 Water Services 1-inch to 2-i nch
33 12 25 Connection to Existin Water Mains
Division 34 -Trans ortation
34 71 13 Traffic Co ntro l
Date
Modified
Technical Specifications listed below are included for this Project by reference and can be
viewed/downloaded from the City's website at:
http://fortworthtexas.gov/tpw/contractors/
or
https://apps.fortworthtexas.gov/ProjectResources/
[Only li st the Standard Specifications the Engineer has determined are appropriate for this specific project
and strike through the Specifications not applicable to the project.}
Division 02 -Existin Conditions
02 41 15 Pavin Removal
Division 03 -Concrete
03 34 13 Contro ll ed Low Stren h Material CLSM
03 34 16 Concrete Base Material for Trench Re air
Division 26 -Electrical
None
C ITY O F FORT WORTH
STANDARD CONSTRUCTION SPEC IFI CATION DOCUMENTS
Re v ised Se ptembe r 9, 2022
Last Revised
02 /02/2016
12/20 /2012
12 /20/2012
2022 WATER SERVI CE LEAK
REP AIR C O NTRACT
C ity Project No. I 0455 2
00 00 00
STANDARD CONSTRUCTI ON SPECIFI CATION DOCUMENTS
Page 3 of 4
Division 31 -Earthwork
None
1v 1sion 32 -Exterior mprovements D' . I
32 12 16 Asphalt Paving 12/20/2012
32 12 73 Asphalt Paving Crack Sealants 12 /20 /2012
32 13 13 Concrete Paving 12 /20 /2012
32 13 20 Concrete Sidewalks, Driveways and Barrier Free Ramps 06 /05 /2018
32 16 13 Concrete Curb and Gutters and Valley Gutters 10 /05 /2016
Division 33 -Utilities
33 04 40 Cleaning and Acceptance Testing of Water Mains 02/06 /2013
33 05 10 Utility Trench Excavation, Embedment, and Backfill 12/1 2/2016
33 05 30 Location of Existing Utilities 12/20 /2012
33 11 05 Bolts, Nuts, and Gaskets · 12/20/2012
331110 Ductile Iron Pipe 12 /20/2012
33 11 11 Ductile Iron Fittings 12/20/2012
33 11 12 Polyvinyl Chloride (PVC) Press ure Pioe 11 /1 6/2018
Division 34 -Transportation
None
Appendix
GC-6.06.D
GC-6.07
Minority and Women Owned Business E nterprise Compliance
Wage Rates
END OF SECTION
CITY OF FORT WORTH
ST AND ARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revi sed September 9, 2022
2022 WATER SERVICE LEAK
RE PAIR CONTRACT
City Project No. I 04552
City of Fort Worth, Texas
Mayor and Council Communication
DATE: 02/14/23 M&C FILE NUMBER: M&C 23-0117
LOG NAME: 602022WATER SL REPAIR CONTRACT -TEJASC
SUBJECT
(ALL) Authorize Execution of a Contract with Tejas Commercial Construction , LLC, in the Amount of $750 ,000.00 for the 2022 Water Service Leak
Repair Contract with Three Optional Renewals , and Adopt Appropriation Ordinance to Effect a Portion of Water's Contribution to the Fiscal Years
2023-2027 Capital Improvements Program
RECOMMENDATION:
It is recommended that the City Council:
1. Authorize execution of a contract with Tejas Commercial Construction , LLC , in the amount of $750 ,000.00 for 2022 Water Service Leak
Repair Contract which includes three optional renewals ; and
2 . Adopt the attached appropriation ordinance increasing estimated rece ipts and appropriations in the Water and Sewer Capital Projects Fund
in the amount of $900 ,000.00, transferred from available funds within the Water and Sewer Fund , for the purpose of funding the 2022 Water
Service Leak Repair Contract project (City Project No . 104552) to effect a portion of Water's contribution to the Fiscal Years 2023-2027
Capital Improvement Program .
DISCUSSION:
The purpose of this Mayor and Council Communication (M&C) is to authorize execution of a contract with Tejas Commercial Construction, LLC , in
the amount of $750 ,000.00, for 2022 Water Service Leak Repair Contract, with three optional renewals.
The work to be performed under th is contract consists of repairing water services lines as leaks in the distribution system are discovered so as to
minimize system water loss and respond quickly to customer requests. The contract will augment Water Field Operations efforts in timely repairs of
service line leaks that are discovered or reported within the water distribution system .
The bid documents included a stipulation that the total quantities listed may not reflect actual quantities and that the amount budgeted for the
projects is $750 ,000.00. Final payments will be made based on actual measured quantities . The bid documents also included a stipulation giving
the City the option to renew this contract three times under the same terms , conditions and unit prices subject to appropriated funding.
The project was advertised for bid on December 22, 2022 & December 29 , 2022 in the Fort Worth Star-Telegram and on January 26 , 2023 , the
following bid was received:
LLC
Staff has reviewed the proposal unit prices and considers them to be fair and reasonable.
In addition to the contract amount, $150 ,000 .00 is required for project management, land acquisition, material testing and inspection.
It is the practice of the Water Department to appropriate its Capital Improvement Program (CIP) plan throughout the fiscal year, instead of within
the annual budget ordinance , as projects commence , additional funding needs are identified , and to comply with bond covenants . The actions in
the M&C will appropriate funds in support of the Water's portion of the City of Fort Worth 's Fiscal Years 2023-2027 Capital Improvement Program ,
as follows :
602022WATER SL REPAIR CONTRACT -TEJAS
Capital Budget Revised
Fund Project FY2023 CIP Authority Change FY2023
Name Name Appropriations (Increase/ Budget Decrease)
56002 -104552-
W&S 2022
Capital Water $0 .00 This M&C $900 ,000.00 $900,000.00 SL Projects Repair Fund Contrac
Funding is budgeted in the Transfer to Water/Sewer account of the Water Capital Project Department's Water & Sewer Fund for the purpose of
funding the 2022 Water SL Repair Contra ct project within the Water & Sewer Capital Proje cts Fund .
Appropriations for 2022 Water Service Line Repair Contract as depicted below.
FUND
Capital
Projects -
Fund
56002
$0.00
$0.00
I Appropri ·
$900 ,000 .00 $900 ,000 .00
$900,000.00 ,000.00
This project will have no impact on the Water Department's operating budget when completed .
Business Equity: Tejas Commercial Construction , LLC . is in compliance with the City's Business Equity Ordinance by committing to 79
percent Bus iness Equity participation on this project. The City's Business Equity goal on this project is 10 percent. Additionally, Tejas Commercial
Construction , LLC . is a certified Business Equity Firm .
This project is located in ALL COUNCIL DISTRICTS .
FISCAL INFORMATION/ CERTIFICATION:
The Director of Finance certifies that funds are currently available in the Water & Sewer Fund and upon approval of the above recommendations
and adoption of the attached appropriation ordinance, funds will be available in the W&S Capital Projects Fund for the 2022 Water SL Repair
Contract project to support the approval of the above recommendations and execution of the contract. Prior to any expenditures being incurred , the
Water Department has the responsibility of verifying the availability of funds .
Submitted for City Manager's Office by: Dana Burghdoff 8018
Originating Business Unit Head : Chris Harder 5020
Additional Information Contact: J. Chris Underwood 2629
Expedited
•
602022 WATER SL REPAIR CONTRACT -TEJASC FID Table
IReZ#y ~nd loe-pt #
__ __ _ __ _ _ _ _ ___ FIDs (Budget)__
!Account t roject ID IActivity [!~:;et 1CF 2 [Program i----Amount ----r--------Purpose -------l Xfer ---
1&2 56002 0600430 4956001 104552 2023 $900,000 .00
1&2 56002 0600430 104552 2023 $900 ,000 .00
,----i--_T ___ ---IAZc~u;;,lp'°ject 10~7',!rng,am I Amo;;;;,~., : Rec# Fund Dept #
'
1&2 56001 0609020 5956001 $900,000.00
1&2 56002 0600430 4956001 104552 001780 9999 ($900,000 .00)
1 Rec# 1F~nd -
1
Dept #
-FIDs (REVENUE or EXPENSE -No KK or GL Entries Needed) -
1
Account r roject IDr ctivity --,~~:;~,-Amount ----1------Purpose ---r r
1&2 56002 0600430 4956001 104552 9999 ($900,000.00)
1&2 56002 0600430 5110101 104552 001740 9999 $1,250.00
1&2 56002 0600430 5330500 104552 001740 9999 $1,250.00
1&2 56002 0600430 5710010 104552 001740 9999 $1,250.00
1&2 56002 0600430 5740010 104552 001740 9999 $1 ,250 .00
1&2 56002 0600430 5110101 104552 001780 9999 $65,000.00
1&2 56002 0600430 5540101 104552 001480 9999 $5,000.00
1 56002 0600430 5740010 104552 001780 9999 $750,000.00
1&2 56002 0600430 5310350 104552 001784 9999 $5,000.00
1&2 56002 0600430 5330500 104552 001784 9999 $10,000.00
1&2 56002 0600430 5110101 104552 001785 9999 $60,000.00
56002 2060000 104552 RETAIN
2
3
4
5
6
7
8
9
JO
11
12
13
14
15
16
17
18
19
20
21
22
23
00 05 10 -I
MAYOR AND COUNCIL COMMUNICATION (M&C)
SECTION 00 05 10
MAYOR AND COUNCIL COMMUNICATION (M&C)
END OF SECTION
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIF!CATION DOCUMENTS
Revised July I , 2011
Page I of I
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No. I 04552
00 05 15 -I
CITY OF FORT WORTH
WATER DEPARTMENT
ENGINEERING SERVICES DIVISION
RELEASE DATE: January 5, 2023
ADDENDUM NO. 1
2022 WATER SERVICE LEAK
REPAIR CONTRACT
CITY PROJECT NO. 104552
BID RECEIPT DATE: January 19, 2023
INFORMATION TO BIDDERS:
Page I of I
The Specifications and Contract Documents for the above mentioned project are revised and amended as follows:
1. In the TABLE OF CONTENTS; DIVISION 01 -General Requirements specification
01 31 20 Project Meetings is listed as part of the Contract Specifications.
The TABLE OF CONTENTS shall be REVISED deletin,g the 01 31 20 Project Meeting
Specification as the unique nature of this miscellaneous contract will not require regular project
meetings.
Please acknowledge receipt of the Addendum in the bid proposal and on the outside of the sealed envelope.
RECEIPT ACKNOWLEDGED:
CHRIS HARDER, P.E.
DIRECTOR., WATER DEP RTMENT
By:_--1---'--'--t--__ -«--. ~h=t>_.__U+-----
on . holola, P.E.
Assistant Director,
Water Department Capital Delivery
CITY OF PORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No. 104552
CITY OF FORT WORTH
WATER DEPARTMEN T
ENGIN EERING SERVICES DIVISION
ADDENDUM NO. 2
2022 WATER SERVICE LEAK
RERAIR CONTRACT
CITY PROJECT NO. 104552
RELEASE DATE: January 19, 2023
BID RECEIPT DATE: January 19 , 2023
REVISED BID RECEIPT DATE: January 26, 2023
INFORMATION TO BIDDERS:
00 05 15 • 1
Pnge I of J-
The Specifications and Contract Documents for the above mention ed project are revised and amended as follow s:
1. In the INVITATION TO BIDDERS; the first paragraph specifies that sealed bids ''will be received
by the City of Fort W 01th Purchasing Office until 1:30 P ;M. CST, Thursday Ja:nuary 19, 2023 and
bids will be opened publicly and read aloud at 2:00 P .M . CST in the Council Chambers."
.The INVITATION TO BIDDERS shall be REVISED in that sealed bids "will be received by the
City of Fort Wo1th Purchasing Office until 1:30 P.M. CST, Thursday January 26, 2023 and bids
will be opened publi cly and read aloud at 2:00 P.M. CST in the Council Chambers."
Please acknowledge receipt of the Addendum in the bid proposal and on th e outside of the sealed envelope .
RECEIPT ACKNOWLEDGED :
CHRIS HARDER, P .E.
DIRECTOR, WATERDEPARTMENT
By :_-O_A _____ _,___~~--
Tony holo la, P .E.
Assistant Dh-ector,
Water Department Capital Delivery
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No. 104552
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
SECTION 00 05 15
ADDENDA
END OF SECTION
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Rev ised Jul y I , 2011
00 05 15 -I
ADDENDA
Page I of I
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No. I 04552
00 11 13
rNVITATION TO BIDDERS
SECTION 00 1113
INVITATION TO BIDDERS
RECEIPT OF BIDS
Page I of2
Sealed bids for the construction of2022 WATER SERVICE LEAK REPAIR CONTRACT,
City Project No. 104552 ("Project") will be received by the City of Fort Worth Purchasing
Office until 1 :30 P.M. CST, Thursday , January 19, 2023 as further described below:
City of Fort Worth
Purchasing Division
200 Texas Street
Fort Worth, Texas 76102
Bids will be accepted by: US Mail, Courier, FedEx or hand delivery at the address above ;
Bids will be opened publicly and read aloud at 2:00 PM CST in the City Council Chambers.
GENERAL DESCRIPTION OF WORK
The major work will consist of the (approximate) following:
Repair of 1-inch through 2-inch Water Service Leaks
TIME PERIOD AND RENEWALS
The time period of this Agreement will be for one calendar year or the expiration of the funding ,
whichever occurs last. The City reserves the right to renew the contract for up to three (3)
additional one calendar year time periods or up to three (3) additional expenditures of
$750,000.00 under the same terms, conditions and unit prices. The City shall provide at least
sixty (60) days' notice to the Contractor of the City's intent to renew.
PREQUALIFICA TION
Certain improvements included in this project must be performed by a contractor or designated
subcontractor who is pre-qualified by the City at the time of bid opening. The procedures for
qualification and pre-qualification are outlined in the Section 3 of 00 21 13 -INSTRUCTIONS
TO BIDDERS .
DOCUMENT EXAMINATION AND PROCUREMENTS
The Bidding and Contract Documents may be examined or obtained on-line by visiting the City
of Fort Worth 's Purchasing Division website at http://www.fortwo rtht exas.gov/purchas in g/ and
clicking on the link to the advertised project folders on the City's electronic document
management and collaboration system site. The Contract Documents may be downloaded,
viewed, and printed by interested contractors and/or suppliers.
Bid Document Package
https ://docs . b360 . autodesk . com/sha res/dbcd9a65 -c22e-4 95a-b5 78 -4260f 4b216f2
Addenda Folder
https ://docs.b360 .autodesk.com/sha res/3b79a38e-f539-4b46-a5ce-49a386d0fcb8
C ITY OF FORT WORTH
ST AND ARD CONSTRUCTION SPEC IFI CATION DOCUMENT
Re vised 7/19/202 1
2022 WATER SERVICE LEAK
REPAIR CONTRACT
C ity Project No. I 04552
Copies of the Bidding and Contract Documents may be obtained from
J. Chris Underwood
Water Department, Design Services
927 Taylor Street
Fort Worth, Texas 76102
The cost of Bidding and Contract Documents is: No Cost
EXPRESSION OF INTEREST
00 11 13
fNVITATION TO BIDDERS
Page 2 of2
To ensure potential bidders are kept up to date of any new information pertinent to this project, all
interested parties are requested to email Expressions oflnterest in this procurement to the City
Project Manager and the Design Engineer. The email should include the company 's name,
contact person and that individual 's email address and phone number. All Addenda will be
distributed directly to those who have expressed an interest in the procurement and will also be
posted in the City of Fort Worth's purchasing website at http://fortworthtexas.gov/purchasing/
PREBID CONFERENCE
A prebid conference will not be held as discussed in Section 00 21 13 -INSTRUCTIONS TO
BIDDERS.
Since a prebid conference is not being held, prospective bidders can e-mail questions or
comments in accordance with Section 6 of the Instructions to Bidders referenced above to the
project manager(s) at the e-mail addresses listed below. Emailed questions will suffice as
"questions in writing." If necessary, Addenda will be issued pursuant to the Instructions to
Bidders.
CITY'S RIGHT TO ACCEPT OR REJECT BIDS
City reserves the right to waive irregularities and to accept or reject any or all bids .
AWARD
City will award a contract to the Bidder presenting the lowest price, qualifications and
competencies considered.
INQUIRIES
All inquiries relative to this procurement should be addressed to the following:
Attn: J. Chris Underwood, City of Fort Worth
Email: john.underwood@ fortworthtexas.gov
Phone: (817) 392-2629
AND/OR
Attn: Lawrence Hamilton, P.E., City of Fort Worth
Email: lawrence.hamilton@ fortworthtexas .gov
Phone: (817) 392-2626
ADVERTISEMENT DATES
December 22, 2022
December 29, 2022
END OF SECTION
CITY OF FORT WORTH
STANDARD C ONSTRUC TION SPEC IFI CA TION DO CUMENT
Revi sed 7/19/2021
2022 WATER SERVICE LEAK
REPAIR CONTRACT
C ity Project No . 10455 2
Defined Terms
SECTION 00 21 13
INSTRUCTIONS TO BIDDERS
00 2 1 13
INSTRUCTIONS TO BIDDE RS
Page I of IO
LI.Capitalized terms used in these INSTRUCTIONS TO BIDDE RS are defined in Section
00 72 00 -GENERAL CONDITIONS.
1.2. Certain additional terms used in these INSTRUCTIONS TO BIDDERS have the
meanings indicated below which are applicable to both the singular and plural thereof.
1.2.1. Bidder: Any person, firm, partnership, company , association, or corporation acting
directly through a duly authorized representative, submitting a bid for performing
the work contemplated under the Contract Documents.
1.2.2. Nonresident Bidder: Any person, firm , partnership, company, association, or
corporation acting directly through a duly authorized representative, submitting a
bid for performing the work contemplated under the Contract Documents whose
principal place of business is not in the State of Texas.
1.2.3. Successful Bidder: The lowest responsible and responsive Bidder to whom City
(on the basis of City's evaluation as hereinafter provided) makes an award .
2. Copies of Bidding Documents
2.1. Neither City nor Engineer shall assume any respon s ibility for errors or misinterpretations
resulting from the Bidders use of incomplete sets of Bidding Documents .
2.2. City and Engineer in making copies of Bidding Documents available do so only for the
purpose of obtaining Bids for the Work and do not authorize or confer a license or grant
for any other use.
3. Prequalification of Bidders (Prime Contractors and Subcontractors)
3.1. Bidders or their designated subcontractors are required to be prequalified for the work
types requiring prequalification as per Sections 00 45 11 BIDDERS
PREQUALIFICATIONS and 00 45 12 PREQUALIFICATION STATEMENT. Firms
seeking pre-qualification, must submit the documentation identified in Section 00 45 11
on Section 00 45 13 PREQUALIFICA TION APPLICATION at least seven (7)
calendar days prior to Bid opening for review and, if qualified, acceptance. The
subcontractors listed by a Bidder on 00 45 12 mu st be prequalified for the appropriate
work types. Subcontractors must follow the same timelines as Bidders for obtaining
prequalification review. Bidders or Subcontractors who are not prequalified at the time
bids are opened and reviewed may cause the bid to be rejected.
Prequalification requirement work types and documentation are available by accessing all
required files through the City's website at:
https ://apps.fortworthtexas.gov/ProjectResources/
CITY OF FORT WORTH
STANDARD CONSTRUCTION SP EC IFICATION DOCUMENT
Revised/Updated November 2, 2021
2022 WATERSERVICELEAK
REPAIR CONTRACT
City Projec t No . I 04552
00 2 1 13
INSTRU CTIONS TO BIDDERS
Page 2 of IO
3 .1.1 . Water and Sanitary Sewer -Requirements document located at:
https://apps.fortworthtexas.gov/ProjectResources/ResourcesP/02%20-
%20Construction%20Documents/Contractor%20Pregualification/Water%20and%2
0Sanitary%20Sewer%20Contractor%20Pregualification%20Program/WSS%20pre
gual%20reguirements.pdf
3.2 . Each Bidder, unless currently prequalified , must submit to City at least seven (7)
calendar days prior to Bid opening, the documentation identified in Section 00 45 11,
BIDDERS PREQUALIFICA TIONS.
3.2 . I. Submission of and/or questions related to prequalification should be addressed to
the City contact as provided in Paragraph 6.1.
3.3. The City reserves the right to require any pre-qualified contractor who is the apparent low
bidder for a project to submit such additional information as the City , in its sole
discretion may require , including but not limited to manpower and equipment records,
information about key personnel to be assigned to the project, and construction schedule
to assist the City in evaluating and assessing the ability of the apparent low bidder to
deliver a quality product and successfully complete projects for the amount bid within
the stipulated time frame. Based upon the City's assessment of the submitted
information , a recommendation regarding the award ofa contract will be made to the
City Council. Failure to submit the additional information, ifrequested, may be grounds
for rejecting the apparent low bidder as non-responsive. Affected contractors will be
notified in writing of a recommendation to the City Council.
3.4. ln addition to prequalification, additional requirements for qualification may be required
within various sections of the Contract Documents .
4. Examination of Bidding and Contract Documents, Other Related Data, and Site
4 .1. Before submitting a Bid , each Bidder:
4.1.1. Sha! I examine and carefully study the Contract Documents and other related data
identified in the Bidding Documents (including "technical data" referred to in
Paragraph 4.2. below). No information given by City or any representative of the
City other than that contained in the Contract Documents and officially
promulgated addenda thereto , shall be binding upon the City.
4.1.2. Should visit the site to become familiar with and satisfy Bidder as to the general,
local and site conditions that may affect cost, progress, performance or furnishing
of the Work.
4.1.3. Shall consider federal, state and local Laws and Regulations that may affect cost,
progress, performance or furnishing of the Work.
4.1.4. Not Used
CITY OF FORT WORTH
STANDARD CONSTRU CTION SP EC IFI CATION DOC UMEN T
Re vised/Updated N ovember 2, 2021
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Proje ct No . 10455 2
00 21 13
INSTRU CTION S TO BIDDERS
Page 3 of 10
4.1.5. Shall study all: (i) reports of exp lo rations and tests of subsurface conditions at or
contiguous to the Site and all drawings of physical conditions relating to existing
surface or subsurface structures at the Site (except Underground Facilities) that
have been identified in the Contract Documents as containing reliable "technical
data" and (ii) reports and drawings of Hazardous E nvironmental Conditions, if any ,
at the Site that have been identified in the Contract Documents as containing
re li able "technical data."
4.1.6. Is advised that the Contract Documents on file with the City shall constitute all of
the information which the City will furnish . All additional information and data
which the City will supply after promulgation of the formal Contract Documents
shall be issued in the form of written addenda and shall become part of the Contract
Documents just as though such addenda were actually written into the original
Contract Documents. No information given by the City other than that contained in
the Contract Documents and officially promulgated addenda thereto , shall be
binding upon the City.
4.1.7. Should perform independent research , investigations, tests , borings, and such other
means as may be necessary to gain a complete knowledge of the conditions which
will be encountered during the construction of the project. For projects with
restricted access, upon request, City may provide each Bidder access to the site to
conduct such examinations, investigations, explorations, tests and studies as each
Bidder deems necessary for submission of a Bid. Bidder must fill all holes and
clean up and restore the s it e to it s former conditions upon completion of such
explorations , investigations, tests and studies .
4 .1.8. Shall determine the difficulties of the Work and all attending circumstances
affecting the cost of doing the Work, time required for its completion, and obtain all
information required to make a proposal. Bidders shall rely exclusively and sole ly
upon their own estimates, investigation, research, tests , explorations, and other data
which are necessary for full and complete information upon which the proposal is
to be based. It is understood that the submission of a proposal or bid is prima-facie
evidence that the Bidder has made the investigations, examinations and tests herein
required.
4.1.9. Shall promptly notify City of all conflicts, errors, ambiguities or discrepancies in or
between the Contract Documents and such other related documents. The Contractor
shall not take advantage of any gross error or omission in the Contract Documents,
and the City shall be permitted to make such corrections or interpretations as may
be deemed necessary for fulfillment of the intent of the Contract Documents.
4 .2. Reference is made to Section 00 73 00 -Supplementary Conditions for identification of:
4 .2.1 . those reports of explorations and tests of subsurface conditions at or contiguous to
the site which have been utilized by City in preparation of the Contract Documents.
The logs of Soil Borings, if any, on the plans are for general information only.
Neither the City nor the Engineer guarantee that the data shown is representative of
conditions which actually exist.
C ITY OF FORT WORTH
STANDARD C ONS TRUCTION SPEC IFICAT ION DOCU MEN T
Revi sed/U pd ated N ov ember 2, 202 1
2022 WAT ER SE RVI CE LEAK
REPAIR CONTRACT
Ci ty P roje ct No I 04 55 2
00 2 1 13
INSTRU CTIONS TO BIDDERS
Pa ge 4 of 10
4.2.2. those drawings of physical conditions in or relating to existing surface and
subsurface structures (except Underground Facilities) which are at or conti g uous to
the site that have been utili ze d by City in preparation of the Contract Documents.
4.2.3. copies of such report s and drawin gs will be made available by City to any Bidder
on request. Those reports and drawings may not be part of the Contract
Documents, but the "technical data" contained therein upon which Bidder is entitled
to rely as provided in Paragraph 4 .02. of the General Conditions has been identified
and established in Paragraph SC 4.02 of the Supplementary Conditions. Bidder is
responsible for any interpretation or conclusion drawn from any "technical data" or
any other data, interpretations, opinions or information.
4.2.4. Standard insurance requirements, coverages and limits.
4.3 . The submission of a Bid will constitute an incontrovertible representation by Bidder: (i)
that Bidder has complied with every requirement of this Paragraph 4 , (ii) that without
exception the Bid is premised upon performing and furnishing the Work required by the
Contract Documents and applying the specific means , methods, techniques, sequences or
procedures of construction (if any) that may be shown or indicated or expressly required
by the Contract Documents, (iii) that Bidder has given City written notice of all
conflicts, errors, ambiguities and discrepancies in the Contract Documents and the
written re solutions thereof by City are acceptable to Bidder, and when said conflicts ,
etc., have not been resolved through the interpretations by City as de sc ribed in
Paragraph 6., and (iv) that the Contract Documents are generally sufficient to indicate
and convey understanding of all terms and conditions for performing and furnishing the
Work.
4.4. The provisions of this Paragraph 4 , inclusive, do not apply to Asbestos, Polychlorinated
biphenyls (PCBs), Petroleum, Hazardous Waste or Radioactive Material covered by
Paragraph 4.06. of the General Conditions, unless specifically identified in the Contract
Documents .
5. Availability of Lands for Work, Etc.
5.1. The lands upon which the Work is to be performed, rights-of-way and easements for
access thereto and other lands designated for use by Contractor in performing the Work
are identified in the Contract Documents. All additional lands and access thereto
required for temporary construction facilities , construction equipment or storage of
materials and equipment to be incorporated in the Work are to be obtained and paid for
by Contractor. Easements for permanent structures or permanent changes in existing
facilities are to be obtained and paid for by City unless otherwise provided in the
Contract Documents.
5.2. Outstanding right-of-way , easements , and/or permits to be acquired by the City are listed
in Paragraph SC 4 .01 of the Supplementary Conditions. In the event the necessary right-
of-way , easements , and/or permits are not obtained , the City reserves the right to cancel
the award of contract at any time before the Bidder begins any construction work on the
project.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SP EC IFI CATIO N DOCUMENT
Revi se d/Upd ate d Novembe r 2, 202 1
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Proje ct No . I 04552
00 2 1 13
fNSTR UC TION S TO BIDDE RS
Page 5 of 10
5.3. The Bidder shall be prepared to commence construction without all executed right-of-
way, easements, and/or permits, and shall submit a schedule to the City of how
construction will proceed in the other areas of the project that do not require permits
and/or easements.
6. Interpretations and Addenda
6.1. All questions about the meaning or intent of the Bidding Documents are to be directed to
City in writing on or before 2 p.m ., the Monday prior to the Bid opening. Questions
received after this day may not be responded to. Interpretations or clarifications
considered necessary by City in response to such questions will be issued by Addenda
delivered to all parties recorded by City as having received the Bidding Documents.
Only questions answered by formal written Addenda will be binding. Oral and other
interpretations or clarifications will be without legal effect.
Address questions to:
City of Fort Worth
200 Texas Street
Fort Worth, TX 76102
Attn: J. Chris Underwood
Fax: (817) 392-2527
Emai 1: john. underwood@ fortworthtexas.gov
Phone : (817)392-2629
6.2. Addenda may also be issued to modify the Bidding Documents as deemed advisable by
City.
6.3. Addenda or clarifications may be posted via the City's electronic document management
and collaboration system at.
Bid Document Package
https ://docs . b360 . autodes k. com/s ha res/d bed 9a6 5-c22e-495a-b5 7 8-4260f 4b216f2
Addenda Folder
https://docs .b360 .autodesk .com/shares/3b79a38e-f539-4b46-a5ce-49a386d0fcb8
6.4. A prebid conference may be held at the time and place indicated in the Advertisement or
INVITATION TO BIDDERS. Representatives of City will be present to discuss the
Project. Bidders are encouraged to attend and participate in the conference. City will
transmit to all prospective Bidders of record such Addenda as City considers necessary
in response to questions arising at the conference . Oral statements may not be relied
upon and will not be binding or legally effective.
7. Bid Security
7.1. Each Bid must be accompanied by a Bid Bond made payable to City in an amount of five
(5) percent of Bidder's maximum Bid price, on the form attached or equivalent issued
by a surety meeting the requirements of Paragraph 5.01 of the General Conditions.
CITY OF FORT WORTH
ST AND ARD C ONSTRUCTION SPEC IFI CATION DOCUMEN T
Revised/Updated November 2, 2021
2 022 WATER SERVI CE LEAK
REPAIR CONTRACT
City Project No. I 04 552
00 2 1 13
INSTRUCTIONS TO BIDDERS
Page 6 of 10
7.2 . The Bid Bonds provided by a Bidder will be retained until the conditions of the Notice of
Award have been satisfied. If the Successful Bidder fails to execute and return the
Contract Documents within 14 days after the Notice of Award conveying same, City
may consider Bidder to be in default, rescind the Notice of Award and act on the Bid
Bond. Such action s hall be City's exclusive remedy in the event Bidder is deemed to
have defaulted .
8. Contract Times
The number of days within which, or the dates by which, Milestones are to be achieved in
accordance with the General Requirements and the Work is to be completed and ready for
Final Acceptance is set forth in the Agreement or incorporated therein by reference to the
attached Bid Form.
9. Liquidated Damages
Provisions for liquidated damages are set forth in the Agreement.
10. Substitute and "Or-Equal" Items
The Contract, if awarded, will be on the basis of materials and equipment described in the
Bidding Documents without consideration of possible substitute or "or-equal" items.
Whenever it is indicated or specified in the Bidding Documents that a "substitute" or "or-
equal" item of material or equipment may be furnished or used by Contractor if acceptable to
City, application for such acceptance will not be considered by City until after the Effective
Date of the Agreement. The procedure for submission of any such application by Contractor
and consideration by City is set forth in Paragraphs 6.05A., 6.05B. and 6.05C. of the General
Conditions and is supplemented in Section 01 25 00 of the General Requirements .
11. Subcontractors, Suppliers and Others
11. I. In accordance with the City's Business Equity Ordinance No.25165-10-2021 the City
has goals for the participation of minority business and/or women business
enterprises in City contracts $100,000 or greater. See Section 00 45 40 for the
M/WBE Project Goals and additional requirements. Failure to comply shall render
the Bidder as non-responsive.
Business Equity Ordinance No.25165-10-2021 , as amended (replacing Ordinance
No. 24534-11-2020), codified at:
https ://codelibrary.amlegal .com/codes/ftworth/latest/ftworth tx/0-0 -0-22593
11.2. No Contractor shall be required to employ any Subcontractor, Supplier, other person
or organization against whom Contractor or City has reasonable objection.
12. Bid Form
12.1. The Bid Form is included with the Bidding Documents; additional copies may be
obtained from the City.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENT
Revised/Updated November 2, 202 1
2022 WATERSERVJCELEAK
REPAIR CONTRACT
City Project No. 104552
00 2 1 13
INSTRUCTIONS TO BIDDERS
Page 7 of 10
12.2 . All blanks on the Bid Form must be completed and the Bid Form signed in ink.
Erasures or alterations shall be initialed in ink by the person signing the Bid Form. A
Bid price shall be indicated for each Bid item , alternative, and unit price item listed
therein. In the case of optional alternatives , the words "No Bid," "No Change," or
"Not Applicable" may be entered. Bidder shall state the prices for which the Bidder
proposes to do the work contemplated or furni sh materials required . All entries shall
be legible.
12.3 . Bids by corporations shall be exec uted in the corporate name by the president or a
vice-president or other corporate officer accompanied by evidence of authority to
sign. The corporate seal shall be affixed. The corporate address and state of
incorporation shall be shown below the signature.
12.4 . Bids by partnerships shall be executed in the partnership name and signed by a
partner, whose title must appear under the signature accompanied by evidence of
authority to sign. The official address of the partnership shall be shown below the
signature.
12.5. Bids by limited liability companies shall be executed in the name of the firm by a
member and accompanied by evidence of authority to sign. The state of formation of
the firm and the official address of the firm shall be shown.
12.6 . Bids by individuals shall show the Bidder's name and official address.
12.7. Bids by joint ventures shall be executed by each joint venture in the manner indicated
on the Bid Form. The official address of the joint venture shall be shown.
12.8. All names shall be typed or printed in ink below the signature.
12 .9. The Bid shall contain an acknowledgement ofreceipt of all Addenda, the numbers of
which shall be filled in on the Bid Form.
12 .10. Postal and e-mail addresses and telephone number for communications regarding the
Bid s hall be shown.
12 .11 . Evidence of authority to conduct business as a Nonresident Bidder in the state of
Texas shall be provided in accordance with Section 00 43 37 -Vendor Compliance
to State Law Non Resident Bidder.
13. Submission of Bids
Bids shall be submitted on the prescribed Bid Form, provided with the Bidding Documents,
at the time and place indicated in the Advertisement or INVITATION TO BIDDERS ,
addressed to Purchasing Manager of the City, and shall be enclosed in an opaque sealed
envelope , marked with the City Project Number, Project title, the name and address of
Bidder, and accompanied by the Bid security and other required documents. If the Bid is sent
through the mail or other delivery system, the sealed envelope shall be enclosed in a separate
envelope with the notation "BID ENCLOSED" on the face of it.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPEC IFICATION DOCUME NT
Revi sed/Updated November 2 , 202 1
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No. I 04552
14. Withdrawal of Bids
00 2 1 13
INSTRUCTIONS TO BIDDERS
Page 8 of IO
14.1. Bids addressed to the Purchasing Manager and filed with the Purchasing Office may
be withdrawn prior to the time set for bid opening. A request for withdrawal must be
made in writing and delivered to the Purchasin g Office to receive a time stamp prior
to the opening of Bids. A timely withdrawn bid will be returned to the Bidder or, if
the request is within one hour of bid opening, will not be read aloud and will
thereafter be returned unopened.
14.2. In the event any Bid for which a withdrawal request has been timely filed has been
inadvertently opened , said Bid and any record thereof will subsequently be marked
"Withdrawn" and will be given no further consideration for the award of contract.
15. Opening of Bids
Bids will be opened and read aloud publicly. An abstract of the amounts of the base Bids and
major alternates (if any) will be made available to Bidders after the opening of Bids.
16. Bids to Remain Subject to Acceptance
All Bids will remain subject to acceptance for a minimum of 90 days or the time period
specified for Notice of Award and execution and delivery of a complete Agreement by
Successful Bidder. City may, at City's sole discretion , release any Bid and nullify the Bid
security prior to that date.
17. Evaluation of Bids and Award of Contract
17.1. City reserves the right to reject any or all Bids, including without limitation the rights
to reject any or all nonconforming, nonresponsive, unbalanced or conditional Bids
and to reject the Bid of any Bidder if City believes that it would not be in the best
interest of the Project to make an award to that Bidder. City reserves the right to
waive informalities not involving price, contract time or changes in the Work and
award a contract to such Bidder. Discrepancies between the multiplication of units of
Work and unit prices will be resolved in favor of the unit prices. Discrepancies
between the indicated sum of any column of figures and the correct sum thereof will
be resolved in favor of the correct sum. Discrepancies between words and figures
will be resolved in favor of the words.
17.1.1. Any or all bids will be rejected if City has reason to believe that collusion exists
among the Bidders, Bidder is an interested party to any litigation against City,
City or Bidder may have a claim against the other or be engaged in litigation,
Bidder is in arrears on any existing contract or has defaulted on a previous
contract, Bidder has performed a prior contract in an unsatisfactory manner, or
Bidder has uncompleted work which in the judgment of the City will prevent or
hinder the prompt completion of additional work if awarded.
C ITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENT
Revi sed/Upd ated November 2, 202 1
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No. I 04552
00 2 1 13
INSTRUCTIO NS TO BIDDERS
Page 9 of I O
17.2 . In addition to Bidder's relevant prequalification requirements, City may consider the
qualifications and experience of Subcontractors, Suppliers, a nd other persons and
organizations proposed for those portions of the Work where the identity of such
Subcontractors, Suppliers, and other persons and organi zations must be submitted as
provided in the Contract Documents or upon the request of the City. City also may
consider the operating costs, maintenance requirements, performance data and
guarantees of major items of materials and equipment proposed for incorporation in
the Work when such data is required to be s ubmitted prior to the Notice of Award.
17.3. City may conduct such investigations as City deems necessary to assist in the
evaluation of any Bid and to establish the responsibility, qualifications, and financial
ability of Bidders, proposed Subcontractors, Suppliers and other persons and
organizations to perform and furnish the Work in accordance with the Contract
Documents to City's satisfaction within the prescribed time .
17.4. Contractor shall perform with his own organization, work of a value not less than
35% of the value embraced on the Contract, unle ss otherwise approved by the City.
17.5 . If the Contract is to be awarded, it will be awarded to lowest responsible and
respon s ive Bidder whose evaluation by City indicates that the award will be in the
best interests of the City.
17.6. Pursuant to Texas Government Code Chapter 2252.001, the City will not award
contract to a Nonresident Bidder unless the Nonresident Bidder's bid is lower than
the lowest bid submitted by a responsible Texas Bidder by the same amount that a
Texas resident bidder would be required to underbid a Nonresident Bidder to obtain a
comparable contract in the state in which the nonresident 's principal place of
business is located.
17.7. A contract is not awarded until formal City Council authorization. If the Contract is
to be awarded , City will award the Contract within 90 days after the day of the Bid
opening unless extended in writing. No other act of City or others will constitute
acceptance of a Bid. Upon the contract award, a Notice of Award will be issued by
the City.
17. 7 .1. The contractor is required to fill out and sign the Certificate of Interested
Parties Form 1295 and the form must be submitted to the Project Manager
before the contract will be presented to the City Council. The form can be
obtained at https ://www.ethics.state.tx.us/data/forms/1295/1295.pdf
17.8. Failure or refusal to comply with the requirements may result in rejection of Bid.
18. Signing of Agreement
18.1. When City issues a Notice of Award to the Successful Bidder, it will be accompanied
by the required number of unsigned counterparts of the Project Manual. Within 14
days thereafter, Contractor shall sign and deliver the required number of counterparts
of the Project Manual to City with the required Bonds, Certificates oflnsurance, and
all other required documentation.
CITY OF FORT WORTH
STANDARD CONSTRUCT ION SPECIFICATION DOCUMENT
Revised/Updated November 2 , 2021
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No. 104552
00 21 13
INSTRUCTIONS TO BIDDERS
Page 10 of 10
18.2. City sha ll thereafter deliver one fully s igned counterpart to Contractor.
END OF SECTION
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENT
Revised/Updated November 2, 2021
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No. 104552
SECTION 00 35 13
CONFLICT OF INTEREST STATEMENT
0 0 35 13
CONFLICT O F INTEREST STATEMENT
Pa ge 1 of 1
Each bidder , offeror or respondent to a City of Fort Worth procurement is required to complete a
Conflict of Interest Questionnaire or certify that one is current and on file with the City Secretary's
Office pursuant to state law.
If a member of the Fort Worth City Council , any one or more of the City Manager or Assistant
City Managers , or an agent of the City who exercise discretion in the planning, recommending ,
selecting or contracting with a bidder, offeror or respondent is affiliated with your company , then
a Local Government Officer Conflicts Disclosure Statement (CIS) may be required .
You are urged to consult with counsel regarding the applicability of these forms and Local
Government Code Chapter 176 to your company .
The referenced forms may be downloaded from the links provided below.
Form CIQ (Conflict of Interest Questionnaire) (state .tx .us)
https ://www.ethics.state .tx .us/data/forms/conflicUCIS.pdf
□
□
□
□
BIDDER:
CIQ Form does not apply
CIQ Form is on file with City Secretary
CIQ Form is being provided to the City Secretary
CIS Form does not apply
CIS Form is on File with City Secretary
CIS Form is being provided to the City Secretary
By : Charles D . Allen
Signature : a ~/ <tM4
END OF SECTION
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised February 24 , 2020
Title : Vice President
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No . 104552
CONFLICT OF INTEREST QUESTIONNAIRE FORM CIQ
For vendor or other person doing business with local governmental entity
This questionnaire reflects changes made to the law by H.B . 1491, 80th Leg ., Regular Session .
This questionnaire is being filed in accordance with Chapter 176, Local Government Code
by a person who has a business relationship as defined by Section 176 .001 (1-a) with a local
governmental entity and the person meets requirements under Section 176.006(a).
OFFICE USE ONLY
Date Re ceived
By law this questionnaire must be filed with the records administrator of the local governmental
entity not later than the 7th business day after the date the person becomes aware of facts
that require the statement to be filed. See Section 176.006, Local Government Code.
A person commits an offense if the person knowingly violates Section 176.006 , Local
Government Code. An offense under this section is a Class C misdemeanor.
l.!J Name of person who has a business relationship with local governmental entity.
l3..I □ Check this box if you are filing an update to a previously filed questionnaire.
(The law requires that you file an updated completed questionnaire with the appropriate filing authority not
later than the 7th business day after the date the orig in ally filed questionnaire becomes incomplete or inaccurate .)
l!J Name of local government officer with whom filer has employment or business relationship.
~
Name of Officer
This section (item 3 including subparts A , 8 , C & D) must be completed for each officer with whom the filer has an
employment or other business relationsh ip as defined by Section 176 .001(1-a), Local Government Code . Attach additional
pages to this Form CIQ as necessary.
A. Is the local government officer named in th is section receiving or likely to receive taxable income, other than investment
income , from the filer of the questionnaire?
Dves □No
8 . Is the filer of the questionnaire receiving or likely to receive taxable income , other than investment income , from or at the
direction of the local government officer named in th is section AND the taxable income is not received from the local
governmental entity?
Oves □No
C . Is the filer of this questionnaire employed by a corporation or other business entity with respect to wh ich the local
government officer serves as an officer or director, or holds an ownership of 1 O percent or more?
Oves □No
D . Describe each employment or business relationship with the local government officer named in this section .
Signature of person doing business with the governmental entity Date
Adopted 06/29/2007
LOCAL GOVERNMENT OFFICER FORM CIS
CONFLICTS DISCLOSURE STATEMENT
(Instructions for completing and filing this fonn are provided on the next page.)
This questionnaire reflects changes made to the law by H.B . 1491, 80th Leg ., Regular Session. OFFICE USE ONLY
This is the notice to the appropriate local governmental entity that the following local
government officer has become aware of facts that require the officer to file this statement Date Received
in accordance with Chapter 176, Local Government Code.
l2..J Name of Local Government Officer
~ Office Held
l:J Name of person described by Sections 176.002(a) and 176.003(a), Local Government Code
!J Description of the nature and extent of employment or other business relationship with person named in item 3
~ List gifts accepted by the local government officer and any family member, excluding gifts described by Section
176.003(a-1), if aggregate value of the gifts accepted from person named in item 3 exceed $250 during the 12-month
period described by Section 176.003(a)(2)(B)
Date Gift Accepted Descr i ption of Gift
Date Gift Accepted Description of Gift
Date Gift Accepted Descript ion of Gift
(attach additional forms as necessary)
~ AFFIDAVIT
I swear under penalty of perjury that the above statement is true and corre ct. I acknowledge
that the disclosure applies to a family member (as defined by Section 176 .001 (2 ), Local
Government Code) of this lo cal government offi cer. I also acknowledge that this statement
covers the 12-month period described by Section 176 .003 (a), Local Government Code .
Signature of Lo cal Government Officer
AFFI X NOTARY S T AMP / SEAL ABOV E
Sworn to and subscribed before me, by the sa id , th is the day
of ,20 , to certify wh ich , witness my hand and seal of office.
Signature of officer adm inistering oath Printed name of officer administering oath Title of officer administering oath
Adopted 06/29/2007
LOCAL GOVERNMENT OFFICER
CONFLICTS DISCLOSURE STATEMENT
Section 176.003 of the Local Government Code requires certain local government officers to file this form . A
"local government officer" is defined as a member of the governing body of a local governmental entity ; a
director, superintendent , administrator, president, or other person designated as the executive officer of the
local governmental entity; or an employee of a local governmental entity with respect to whom the local
governmental entity has , in accordance with Section 176 .005, extended the requirements of Sections 176.003
and 176.004. This form is required to be filed with the records administrator of the local governmental entity
not later than 5 p .m. on the seventh business day after the date on which the officer becomes aware of the
facts that require the filing of this statement.
A local government officer commits an offense if the officer knowingly violates Section 176 .003, Local
Government Code . An offense under this section is a Class C misdemeanor.
Please refer to chapter 176 of the Local Government Code for detailed information regarding the requirement
to file this form .
INSTRUCTIONS FOR COMPLETING THIS FORM
The following numbers correspond to the numbered boxes on the other side .
1. Name of Local Government Officer. Enter the name of the local government officer filing this statement.
2. Office Held. Enter the name of the office held by the local government officer filing this statement.
3. Name of person described by Sections 176.002(a) and 176.003(a), Local Government Code. Enter
the name of the person described by Section 176 .002, Local Government Code with whom the officer has an
employment or other business relationship as described by Section 176.003(a), Local Government Code .
4. Description of the nature and extent of employment or business relationship with person named
in item 3. Describe the nature and extent of the employment or other business relationship with the person
in item 3 as described by Section 176.003(a), Local Government Code .
5. List gifts accepted, excluding gifts described by Section 176.003(a-1), if aggregate value of the
gifts accepted from person named in item 3 exceed $250. List gifts accepted during the 12-month period
(described by Section 176.003(a), Local Government Code) by the local government officer or family member
of the officer, excluding gifts described by Section 176 .003(a-1 ), from the person named in item 3 that in the
aggregate exceed $250 in value .
6. Affidavit. Signature of local government officer.
Adopted 06 /29/2007
SECTION 00 41 00
BID FORM
00 41 00
BID FORM
Page 1 of 3
TO : The Purchasing Manager
c/o : The Purchasing Division
200 Texas Street
City of Fort Worth , Texas 76102
FOR : 2022 WATER SERVICE LEAK REPAIR CONTRACT
City Project No .: 104552
Units/Sections: Water Improvements
1. Enter Into Agreement
The undersigned Bidder proposes and agrees , if this Bid is accepted , to enter into an Agreement with City in the form
included in the Bidding Documents to perform and furnish all Work as specified or indicated in the Contract Documents
for the Bid Price and within the Contract Time indicated in this Bid and in accordance with the other terms and conditions
of the Contract Documents.
2. BIDDER Acknowledgements and Certification
2 .1. In submitting this Bid , Bidder accepts all of the terms and conditions of the INVITATION TO BIDDERS and
INSTRUCTIONS TO BIDDERS , including without limitation those dealing with the disposition of Bid Bond .
2 .2. Bidder is aware of all costs to provide the required insurance, will do so pending contract award, and will
provide a valid insurance certificate meeting all requirements within 14 days of notification of award .
2.3. Bidder certifies that this Bid is genuine and not made in the interest of or on behalf of any undisclosed
individual or entity and is not submitted in conformity with any collusive agreement or rules of any group,
association , organization, or corporation .
2.4 . Bidder has not directly or indirectly induced or solicited any other Bidder to submit a false or sham Bid.
2 .5. Bidder has not solicited or induced any individual or entity to refrain from bidding.
2 .6 . Bidde r has not engaged in corrupt, fraudulent , collusive , or coercive practices in competing for the Contract.
For the purposes of this Paragraph :
CITY OF FORT WORTH
a. "corrupt practice" means the offering, giving, receiving , or soliciting of any thing of value likely to
influence the action of a public official in the bidding process .
b. "fraudulent practice" means an intentional misrepresentation of facts made (a) to influence the
bidding process to the detriment of City (b) to establish Bid prices at artificial non-competitive
levels, or (c) to deprive City of the benefits of free and open competition.
c. "collusive practice" means a scheme or arrangement between two or more Bidders , with or without
the knowledge of City , a purpose of which is to establish Bid prices at artificial , non-competitive
levels .
d. "coercive practice" means harming or threatening to harm , directly or indirectly , persons or their
property to influence their participation in the bidding process or affect the execution of the
Contract.
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Form Revised 9/30/2021
2022 WATER SERVICE LEAK
REPAIR CONTRACT
C ity Project No . 104 552
3. Prequalification
00 4 1 00
BID FOR M
Pag e 2 of 3
The Bidder acknowledges that the following work types must be performed only by prequalified contractors and
subcontractors :
a . Water Improvements -1-inch to 2-inch Water Service Leak Repairs
b .
C.
d .
4. Time of Completion
4 .1. The Work will be complete for Final Acceptance within 365 days after the date when the
the Contract Time commences to run as provided in Paragraph 2 .03 of the General Conditions .
4 .2 . Bidder accepts the provisions of the Agreement as to liquidated damages in the event of failure to complete
the Work {and /or achievement of Milestones} within the times specified in the Agreement.
5. Attached to this Bid
The following documents are attached to and made a part of this Bid :
a . This Bid Form , Section 00 41 00
b . Required Bid Bond , Section 00 43 13 issued by a surety meeting the requirements of Paragraph
5 .01 of the General Conditions.
c . Proposal Form , Section 00 42 43
d . Vendor Compliance to State Law Non Resident Bidder, Section 00 43 37
e . MWBE Forms (optional at time of bid)
f. Prequalification Statement , Section 00 45 12
g . Confl ict of Interest Affidavit , Section 00 35 13
*If necessary , CIQ or CIS fo rms are to be provided directly to City Secretary
h . Any addit ional documents that may be required by Section 12 of the Instructions to Bidders
6. Total Bid Amount
6.1 . Bidder will complete the Work in accordance with the Contract Documents for the following bid amount. In the
space provided below, please enter the total bid amount for th is project. Only this figure will be read publicly
by the City at the bid opening .
C ITY OF FO RT W O RTH
STAN DA RD CON STRUCTIO N SPECIFI CAT ION DOC UME NTS
Form Revi sed 9/30/2 021
2022 W ATE R SER VICE LEA K
REPAIR CO NTRACT
City Proj ect No . 10455 2
00 41 00
BID FORM
Pag e 3 of 3
6 .2 . It is understood and agreed by the Bidder in signing this proposal that the total bid amount entered below is
subject to verification and/or modification by multiplying the unit bid prices for each pay item by the respective
estimated quantities shown in this proposal and then totaling all of the extended amounts .
6 .3. Total Bid Amount
Total Bid
7. Bid Submittal
This Bid is submitted on January 26th , 2023
Respectfully submitted,
By:{>//~
(Signature)
Charles D. Allen
(Printed Name)
Title : Vice President
Company: Tejas Commercial Construction , LLC
Address : P.O . Box 10395
River Oaks, TX 76114
State of Incorporation : Texas
Email : callen@tejasconstruction .net
Phone: 817-901-8499
END OF SECTION
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Form Revised 9/30/2021
$1,679 ,950 .00
by the entity named below.
Receipt is acknowledged of the Initial following Addenda:
Addendum No. 1:
Addendum No . 2 :
Addendum No . 3 :
Addendum No. 4 :
Corporate Seal :
bJ
l~6.J
202 2 WATER SERVICE LEAK
REPAIR CONTRACT
Ci ty Project No . 104552
UNIT PRICE BID
SECTION 00 42 43
PROPOSA L FORM
Bidder's Application
00 42 43
B ID PROPOSAL
Page 1 of7
Project It em Informa ti on Bidd er's Prop osa l
Bid Li st Item Specification Bid Quan ti ty I Pay It em No. Sec ti on No.
1 3312 .2003 33 12 10 15
2 3312.2003 33 12 10 15
3 3312.2003 33 12 10 5
4 3312 .2003 33 12 10 15
5 3312.2003 33 12 10 15
6 3312 .2003 33 12 10 5
7 3312 .2003 33 12 10 15
8 3312 .2003 33 12 10 5
9 3312.2003 331210 20
10 3312 .2103 33 12 10 5
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFIC ATION DOCUMENTS
Form Revised 9/3012021
Unit of l
Meas ureme nt Descr ipti on
WATER IMPROVEMENTS
EA 1-inch Water Service ,
O' -10' Length , No Paving
Five Thousand Dollars
No Cents
EA 1-inch Water Service,
0' -10' Length, Asphalt Paving
Fifl'i Three Hundred Dollars
No Cents
EA 1-inch Water Service,
0' -10' Length , Concrete Paving
Fifi}'. Six Hund re d Dollars
No Cents
EA 1-inch Water Service ,
10 .1' -25' Length , No Paving
Si x Thousand Dollars
No Cents
EA 1-inch Water Service,
10.1' -25' Length , Asphalt Paving
Sixt'i Four Hundred Doliars
No Cents
EA 1-inch Water Service ,
10 .1' -25' Length , Concrete Paving
Sixt'i Seven Hundred Dollars
No Cents
EA 1-inch Water Service ,
25 .1 -40' Length , Asphalt Paving
Sevent'i Six Hundred Dollars
No Cents
EA 1-inch Water Service,
25 .1' -40' Length , Concrete Paving
Sevent'i Eight Hundred Dollars
No Cents
LF 1-inch Water Service ,
Additional Length over 40 '
One Hundred Ninet'i Five Dollars
No Cents
EA 1.5-inch Water Serv ice ,
0' -1 0' Length, No Paving
Six Thousand Dollars
No Cents
Unit Price
$5 ,000 .00
$5 ,300 .00
$5 ,600 .00
$6 ,000 .00
$6,400 .00
$6 ,700 .00
$7 ,600 .00
$7 ,800 .00
$195 .00
$6 ,000.00
Bid Va lue
$75,000.00
$79 ,500.00
$28,000.00
$90,000.00
$96,000.00
$33,500.00
$114 ,000.00
$39,000.00
$3 ,900.00
$30,000.00
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No. 104552
UNIT PRICE BID
S ECTION 00 42 43
PRO POS AL FORM
Bidder's App li cation
00 42 43
BID PROPOSAL
Page 2 of 7
Projec t Item ln fon natio n Bidd er's Proposa l
Bid Li st It em Speci fic ati on Bi d Quantity Pay It em No . Sect ion No.
11 33 12 .2103 33 12 10 5
12 3312 .2103 33 12 10 2
13 3312.2 103 33 12 10 5
14 3312 .21 03 33 12 10 5
15 3312.2103 33 12 10 2
16 3312 .2103 33 12 10 5
17 3312 .21 03 33 12 10 2
18 3312 .2103 33 12 10 10
19 33 12 .22 03 33 12 10 5
20 3312.2203 33 12 10 5
CITY OF FORT WORTH
STANDARD CONSTRU CTION SPECI F ICATION DOCUM ENTS
Form R evised 9/30/202 1
Unit of
Meas uremen t
EA
EA
EA
EA
EA
EA
EA
LF
EA
EA
Descripti on
1.5-inch Water Service ,
O' -1 O' Length , Asphalt Paving
Sixty Seven Hund red Dolla rs
No Cents
1.5-inch Water Service,
O' -1 O' Leng th , Con crete Paving
Seven Thousand Dollars
No Cents
1.5-inch Water Service ,
10 .1' -25' Le ngth, No Paving
Seventy Five Hundred Dollars
No Cents
1.5-inch Water Service ,
10.1' -25' Length , Aspha lt Paving
Se venty Nine Hundred Do ll ars
NO Cents
1.5-i nch Water Service,
10 .1 ' -25' Le ngth , Concrete Paving
Eiqhty Two Hundred Dollars
No Cents
1.5-inch Water Se rv ice ,
25 .1 -40' Le ngth , Aspha lt Paving
Ninety Fi ve Hundred Dollars
No Ce nts
1.5-inch Wate r Service ,
25 .1' -40' Le ng th , Concrete Paving
Nine ty Seve n Hun dred Do ll ars
No Cents
1.5-i nch Wate r Serv ice ,
Ad di tiona l Len gth over 40 '
Two Hund red Fo rty Five Do ll ars
No Cents
2-in ch Water Service ,
O' -10' Length , No Paving
Sixty Se ven Hundred Do ll ars
No Cents
2-inch W ater Service ,
O' -1 O' Length , A sphalt Pa v ing
Se venty Two Hund red Dollars
No Cents
Un it Pri ce
$6 ,700 .00
$7,000 .00
$7 ,500 .00
$7 ,900 .00
$8,200 .00
$9 ,500 .00
$9 ,700 .00
$245.00
$6 ,700 .00
$7 ,2 00 .00
Bid Va lue
$33,500.00
$14,00 0.00
$37,500.00
$39,500.00
$16,4 00.00
$47,500.00
$19,4 00.00
$2,4 50.00
$33,500.00
$36,0 00.00
2022 WATER SER VICE LEAK
REPAI R CONTRACT
City Project No. 104552
UNIT PRICE BID
SECTION 00 42 43
PRO POSAL FORM
Bidder's Application
00 42 43
BID PROPOSAL
Page 3 of 7
Proje ct Item In format ion Bidd er's Proposal
Bi d List Item Speci fi ca ti on Bid Quantity Pay Item No. Sect ion No.
21 3312 .2203 33 12 10 2
22 3312 .2203 33 12 10 5
23 3312 .2203 33 12 10 5
24 3312 .2203 33 12 10 2
25 3312 .2203 33 12 10 5
26 3312.2203 33 12 10 2
27 33 12 .2203 33 12 10 10
28 9999 .00 01 33 12 10 15
29 9999 .0002 33 12 10 15
30 9999 .0003 33 12 10 5
CITY OF FORT WORTH
STAN DAR D CONSTRUCTION SPECIFICATI ON DOCUM ENTS
Form Rev ised 9/30/2021
Unit of
Meas urement
EA
EA
EA
EA
EA
EA
LF
EA
EA
EA
Desc ri ption
2-inch Water Service ,
O' -10' Length , Con crete Paving
Seventy Five Hundred Do ll ars
No Cents
2-inch W ater Service ,
10.1' -25' Le ngth, No Paving
Seventy Nine Hu ndred Do ll ars
No Cents
2-inch Water Service ,
10.1' -25' Length , Asphalt Paving
Eighty One Hund red Do ll ars
No Cents
2-inch Water Service,
10 .1' -25' Length , Con c rete Paving
Eighty Eight Hundred Dollars
No Cents
2-inch Water Service ,
25 .1 -40' Length , Aspha lt Paving
Ni nety Five Hundred Do ll ars
No Cents
2-inch Water Service ,
25 .1' -40' Length , Concrete Pav ing
Ninety Nine H undred Dollars
No Cents
2-inch Water Service ,
Additional Le ngt h over 40'
Two Hundred Sixty Do ll ars
No Cen ts
1-inch Water Se rv ice Repair, in Lieu of
Replacement , No Paving
Forty Five Hundred Do ll ars
No Cents
1-in ch W ater Se rv ice Repair, in Lieu of
Repl aceme nt , Asphalt Pa ving
Forty Eig ht Hundred Dollars
No Cents
1-inch Wate r Service Repair , in Lieu of
Replace men t , Concrete Paving
Fifty One Hund red Dol la rs
No Ce nts
Unit Price
$7 ,500 .00
$7 ,900 .00
$8 ,100.00
$8 ,800 .00
$9,500 .00
$9 ,900 .00
$260 .00
$4 ,500 .00
$4 ,800.00
$5 ,100 .00
Bid Value
$15,000.00
$39 ,500.00
$4 0,500.00
$17,60 0.00
$47,500.00
$1 9,8 00 .00
$2,600.00
$67,5 00.00
$72,000.00
$25,5 00.00
2022 WATER SERVICE LEAK
REPAI R CONTRAC T
City Project No. 104552
UNIT PRICE BID
SECTION 00 42 43
PROPOSAL FORM
Bidder's Application
00 42 43
BID PROPOSAL
Page4of7
Project It em lnfo1mation Bidder's Proposa l
Pay Item Bid Li st Item Specification Bid Quantity No . Sec ti on No.
31 9999 .0004 33 12 10 5
32 9999 .0005 33 12 10 5
33 9999 .0006 33 12 10 2
34 9999.0007 33 12 10 5
35 9999 .0008 33 12 10 5
36 9999 .0009 33 12 10 2
37 3311 .0161 33 11 12 100
38 3311.0151 33 11 10 100
39 3311 .0261 33 11 12 100
40 3311.0251 33 11 10 100
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Form Revised 9/30/2021
Unit of
Measurement
EA
EA
EA
EA
EA
EA
LF
LF
LF
LF
Description
1.5-inch Water Servi ce Repair , in Lieu of
Replacement, No Pav ing
Six Thousand Dollars
No Cents
1.5-inch Water Service Repair , in Lieu of
Replacement , Asphalt Paving
Sixty Three Hundred Dollars
No Cents
1.5-inch Water Service Repair, in Lieu of
Replacement, Concrete Paving
Sixty Five Hundred Dollars
No Cents
2-inch Water Service Repa ir, in Li eu of
Replacement , No Paving
Sixty Seven Hund re d Dollars
No Cents
2-inch Water Service Repair, in Lieu of
Replacement , Asphalt Paving
Seven Thousand Dollars
No Cents
2-inch Water Service Repair, in Li eu of
Replacement , Concrete Paving
Seventy Two Hundred Dollars
No Cents
6-inch PVC Water Pipe
~
Eighty Five l.l11J;Id,ii:g, Dollars
No Cents
6-inch DIP Water
ti"
Ninety Eight I m,,e~ee-Dollars
No Cents
8-inch PVC Water Pipe
One Hundred Ten Dollars
No Cents
8-inch DIP Water
One Hundred Twenty Five Dollars
No Cents
Un it Price
$6 ,000 .00
$6 ,300 .00
$6 ,500.00
$6 ,700.00
$7,000 .00
$7 ,200.00
$85 .00
$98.00
$110.00
$125.00
Bid Valu e
$30,000.00
$31,500.00
$13,000.00
$33,500.00
$35,000.00
$14,400.00
$8,500.00
$9,800.00
$11,000.00
$12,500.00
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No. 104552
UNIT PRICE B ID
SECTION 00 42 43
PROPOSAL FO RM
Bidder's App li cation
00 42 43
BID PROPOSAL
Page S of 7
Proj ec t Item In fo nn atio n Bidd er's Propo sal
Bid List Item Speci fi ca ti on Bid Quantity Pay Item No . Sec ti on No.
41 3311 .0361 33 11 12 100
42 3311 .0351 33 11 10 100
43 3311 .0461 33 11 12 100
44 331 1.0451 33 1 1 10 100
45 9999 .0010 33 12 10 10
46 9999 .00 11 33 12 10 100
47 3312 .2004 33 12 10 100
48 33 12 .2 104 33 12 10 20
4 9 3312 .2204 33 12 10 20
50 9999 .0012 5
CITY OF FORT WORTH
STANDARD CONSTR UCTI ON SPECIFICAT ION DOCUMENTS
Form Revised 9/30/2021
Unit of
Meas urement
LF
LF
LF
LF
EA
LF
L F
LF
LF
EA
Description
10-i nch PVC Water Pip e
On e Hundred Twenty Dolla rs
No Ce nts
10-inch D IP Water
One Hundred Th irty Five Dol lars
No C e nts
12-inch PVC Water Pipe
One Hundred Forty Doll ars
No Cents
12-in ch D IP Water
On e Hundred Fifty Five Do llars
No Cents
Multiple Service Branch Set-up
(Branch , Curb Stop & "C " Bo x)
One T ho usa nd Fifty Dollars
No Cents
3/4-inch Private Wate r Service ,
Relocatio n
Sixty Dollars
No Cents
1-i nch Private W ater Service ,
Relocation
Se venty Do ll ars
No Cen ts
1.5-i nch Private Water Servi ce ,
Re location
Ei ghty Fi ve Dollars
No Cents
2-inch Private Water Servi ce ,
Re location
One Hundred Dollars
No Cents
3/4" -2" Water Service "Kill",
Remove Tap & Plug at Main
Sixteen Hun d red Fifty Dollars
No Cents
Uni t Price
$120 .00
$135 .00
$140 .00
$155 .00
$1,050 .00
$60 .00
$7 0 .00
$85 .00
$100.0 0
$1,650 .00
Bid Valu e
$12,00 0.00
$13,500.00
$14 ,000.00
$15,500.00
$1 0,500.00
$6 ,000.00
$7,000.00
$1,700.00
$2,000.00
$8,250.00
2022 WATER SERVICE LEAK
R EPAIR CONTRAC T
City Project No. 104552
UNIT PRICE BID
SECTION 00 42 43
PROPO SAL FORM
Bidder's Application
00 42 43
BID PROPOSA L
Page 6 of 7
Proj ect ltem Infomtati on Bid der's Proposa l
Pay Item Bid List Item Specifi cati on Bid Q uantity No. Section No.
51 3305.0203 33 05 10 10
52 3201 .0112 32 01 17 300
53 3201.0132 32 01 17 150
54 3201 .0614 32 01 29 150
55 3201.0616 32 01 29 75
56 3201 .0302 32 01 17 250
57 3216.0101 32 16 13 50
58 3213.0301 32 13 20 75
59 3213 .0401 32 13 20 75
60 3471.0003 34 71 13 30
CITY OF FORT WORTH
STANDARD CONSTRUC TION SPECIFICATION DOCUMENTS
Form Revis ed 9/30/2021
Uni t of
Mea surement
CY
LF
LF
SY
SY
SY
LF
SF
SF
EA
Descr ipti on
Imported Embedme nt / Backfill CLSM
Two Hundred Thirty Dollars
No Cents
5-foot Wide Asphalt Pavement
Repair, Residential
Ninety Five Dol lars
No Cents
5-foot Wide Asphalt Pavement
Repair, Industrial
On e Hundred Five Dollars
No Cents
Concrete Pavement Repair,
Residential
On e Hundred Fifty Dollars
No Cents
Concrete Pavement Repair,
Arterial/ Industrial
One Hundred Sixty Dollars
No Cents
3-inch Extra Width Asphalt
Pavement Repa ir
Seventy Five Dollars
No Cents
6-inch Concrete Curb and Gutter,
Replacement
Eighty Dollars
No Cents
4-inch Con crete Sidewalk,
Replacement
Eighteen Dollars
No Cents
6-inch Concrete Driveway ,
Replacement
Twenty Dollars
No Cents
Traffic Control , Residential
Eight Hundred Dollars
No Cents
Uni t Pri ce
$230 .00
$95.00
$105 .00
$150 .00
$160 .00
$75 .00
$80 .00
$18 .00
$20.00
$800 .00
Bid Va lue
$2 ,300.00
$28,500.00
$15,750.00
$22,500.00
$12,000.00
$18,750.00
$4 ,000.00
$1,350.00
$1 ,500.00
$24,000.00
2022 WATE R SERVICE LEAK
REPAIR CONTRACT
City Project No . 104552
UNIT PRICE BID
SECTION 00 42 43
PROPOSAL FORM
Bidder's Application
00 42 43
BID PROPOSAL
Page 7 of 7
Project It em lnfonnation Bidder's Proposal
Pay Item Bid List Item Specification Bid Quantity No. Section No .
6 1 3471 .0003 34 7 1 13 10
62 3471 .0003 34 71 13 10
63 9999 .0013 50
END OF SECTIO N
CITY OF FORT WORTH
STANDARD CONSTRUCTI ON SPECI FI CATION DOCUMENTS
Form Revised 9/30 /2 021
Unit of
Measurement
EA
EA
EA
De sc ription Unit Price Bid Value
Traffic Control , Arterial/ Industrial
Eighteen Hundred Fiftll Dollars
No Cents $1,8 50 .00 $18,500.00
Traffic Control , Major Arterial/
Industrial
Two Thousand Dollars
No Cents $2,000.00 $20,000.00
Street Use Permit
On e Hundred Dollars
No Cents $100.00 $5,000.00
Total Bid $1,679,950.00 --------'----'---
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No . 104552
BID BOND
KNOW ALL MEN BY THESE PRESENTS: That We , Tejas Commercial Construction , LLC
As Principal, and the Travelers Casualty and Surety Company of America, a corporation
organized and existing under the laws of the state of Connecticut, and authorized to do
business in the State of Texas as Surety are h e ld and firmly bound unto the
City of Fort Worth
_______________________________ as Obligee,
In the amount of Five Percent of Greatest Amount Bid (5% GAB) DOLLARS,
Lawful money of the United States of America, to the payment of which sum of money well and
truly to be made, the said Principal and Surety bind themselves, their and each of their heirs ,
executors , administrators, successors and assigns, jointly and severally, by these presents.
THE CONDITIONS OF THIS OBLIGATION IS SUCH, that, if the Obligee shall make any
award to the principal for:
Fort Worth -Water Service Leak Repair Contract
Project No . 104552
According to the terms of the proposal or bid made by the Principal therefor, and the Principal
shall duly make and enter into a contract with the Obligee in accordance with the terms of said
proposal or bid and award and shall give bond for the faithful performance thereof, with The
Travelers Casualty and Surety Company of America as Surety or with other Surety or
Sureties approved by the Obligee; or if the Principal shall, in case of failure so to do, pay to
the Obligee the damages which the Obligee may suffer by reason of such failure not
exceeding the penalty of this bond , then this obligation shall be null and void; otherwise it
shall be and remain in full force and effect.
BY ~ ~. ·· . (Seal)
Lloyd Ra;;;;; ~orney-ln-Fact
~ TRAVELERS J
Travelers Casualty and Surety Company of America
Travelers Casualty and Surety Company
St. Paul Fire and Marine Insurance Company
POWER OF ATTORNEY
KNOW ALL MEN BY THESE PRESENTS : That Travelers Casualty and Surety Company of America , Travelers Casualty and Surety Company, and
St. Paul Fire and Marine Insurance Company are corporations duly organized under the laws of the State of Connecticut (herein
collectively called the "Companies"), and that the Companies do hereby make, constitute and appoint Lloyd Ray Pitts Jr of
DALLAS , Texas , their true and lawfu l Attorney(s)-in-Fact to sign , execute , seal and
acknowledge any and all bonds, recognizances, conditional undertakings and other writings obligatory in the nature thereof on behalf of
the Companies in their business of guaranteeing the fidelity of persons, guaranteeing the performance of contracts and executing or
guaranteeing bonds and undertakings required or permitted in any actions or proceedings allowed by la w.
IN WITNESS WHEREOF , the Companies have caused this instrum ent to be signed , and their corporate seals to be hereto affixed, this 21st day of April ,
2021.
State of Connecticut
City of Hartford SS .
On this the 21st day of April , 2021 , before me personally appeared Robert L. Raney, who acknowledged himself to be the Senior
Vice President of each of the Companies , and that he , as such , being authorized so to do , executed the foregoing instrument for the
purposes therein contained by signing on behalf of said Companies by himself as a duly authorized officer.
IN WITNESS WHEREOF , I hereunto set my hand and official seal.
My Commission expires the 30th day of June , 2026
Anna P. Nowik, Notary Public
This Power of Attorney is granted under and by the authority of the following resolutions adopted by the Boards of Directors of each of
the Companies, which reso lutions are now in full force and effect, reading as follows:
RESOLVED, that the Chairman, the President , any Vice Chairman, any Executive Vice President , any Senior Vice President , any Vice
President , any Second Vice President , the Treasurer , any Assistant Treasurer, the Corporate Secretary or any Assistant Secretary may appoint
Attorneys-in-Fact and Agents to act for and on behalf of the Company and may give such appointee such authority as his or her certificate of authority
may prescribe to sign with the Company's name and seal with the Company's seal bonds , recognizances, contracts of indemnity , and other writings
obligatory in the nature of a bond , recognizance , or conditional undertaking, and any of said officers or the Board of Directors at any time may
remove any such appointee and revoke the power given him or her; and it is
FURTHER RESOLVED, that the Chairma n, the President, any Vice Chairman , any Executive Vice President , any Senior Vice President or
any Vice President may delegate all or any part of the foregoing authority to one or more officers or employees of this Company , provided
that each such delegation is in writing and a copy thereof is filed in the office of t he Secretary ; and it is
FURTHER RESOLVED, that any bond , recogn izance , contract of indemnity , or writing obligatory in the nature of a bond, recognizance,
or conditional undertaking shall be valid and binding upon the Compa ny when (a) signed by the President, any Vice Chairman , any Executive
Vice President , any Senior Vice President or any Vice President , any Second Vice President , the Treasurer, any Assistant Treasurer, the
Corporate Secretary or any Assistant Secretary and duly attested and sealed with the Company's seal by a Secretary or Assistant Secretary ;
or (b) duly executed (u nder seal, if required) by one or more Attorneys-in-Fact and Agents pursuant to the power prescribed in his or her
certificate or their certificates of authority or by one or more Company officers pursuant to a written delegation of authority; and it is
FURTHER RESOLVED, that the signature of each of the following officers: President , any Executive Vice President , any Senior Vice President ,
any Vice President , any Assistant Vice President, any Secretary , any Assistant Secretary, and the seal of the Company may be affixed by facsimile to
any Power of Attorney or to any certificate relating thereto appointing Resident Vice Presidents , Resident Assistant Secretaries or Attorneys-in-
Fact for purposes only of executing and attesting bonds and undertakings and other writings obligatory in the nature thereof, and any such Power of
Attorney or certificate bearing such facsimile signature or facsimile seal shall be val id and binding upon the Company and any such power so executed
and certified by such fa csimi le signature and facsimile seal shall be valid and binding on the Company in the future with respect to any bond or
understanding to which it is attached .
I, Kevin E. Hughes , the undersigned, Assistant Secretary of each of the Companies , do hereby certify that the above and foregoing is a
true and correct copy of the Power of Attorney executed by said Companies, which remains in full force and effect.
Dated this 26th day of January , 2023
t Kevin E. Hughes.Assitantsecretary
To verify the authenticity of this Power of Attorney, please call us at 1-800-421-3880.
Please refer ta the above-named Attorney(s)-in-Fact and the details of the bond to which this Power of Attorney is attached.
SECTION 00 43 37
00 43 37
VENDOR COMP LI ANCE TO STATE LAW
Page 1 of 1
VENDOR COMPLIANCE TO STATE LAW NON RESIDENT BIDDER
Texas Government Code Chapter 2252 was adopted for the award of contracts to nonresident bidders . This law
provides that, in order to be awarded a contract as low bidder , nonresident bidders (out-of-state contractors
whose corporate offices or principal place of business are outside the State of Texas) bid projects for
construction , improvements, supplies or services in Texas at an amount lower than the lowest Texas resident
bidder by the same amount that a Texas resident bidder would be required to underbid a nonresident bidder in
order to obtain a comparable contract in the State which the nonresident's principal place of business is located .
The appropriate blanks in Section A must be filled out by all nonresident bidders in order for your bid to meet
specifications . The failure of nonresident bidders to do so will automatically disqualify that bidder. Resident
bidders must check the box in Section B.
A. Nonresident bidders in the State of , our principal place of business ,
are required to be percent lower than resident bidders by State Law . A copy of the
statute is attached .
Nonresident bidders in the State of , our principal place of business ,
are not required to underbid resident bidders.
B. The principal place of business of our company or our parent company or majority owner is
in the State of Texas . 0
BIDDER:
END OF SECTION
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised 9/30/2021
By: Charles D. Allen
[:hJ_(~
(Signature)
Title: Vice President
Date: 1/26/2023
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No . 104552
00 45 11 -I
BIDDERS PREQ UALIFIC ATIO NS
Page I of 3
1 SECTION 00 45 11
2 BIDDERS PREQUALIFICA TIONS
3
4 1. Summary. A Bidder or their desi gnated subco ntractors are required to be prequalified or
5 have applied for prequalification by the City for the work types requiring prequalification
6 prior to submi tting bids. To be considered for award of contract the Bidder must submit
7 Section 00 45 12 , PREQUALIFICATION STATEMENT for the work type(s) listed with
8 their Bid. Any contractor or subcontractor who is not prequalified for the work type(s) listed
9 must submit Section 00 45 13, PREQUALIFICA TION APPLICATION in accordance with
1 O the requirements below. The information must be submitted seven (7) days prior to the
11 date of the opening of bids. Subcontractors must fo ll ow the same timelines as contractors
12 for obtaining prequalification review. Bidders or Subcontractors who are not prequalified at
13 the tim e bids are opened and reviewed may cause the bid to be rejected.
14
15
16 The prequalification process wi ll establish a bid limit based on a technical evaluation and
17 financial analysis of the contractor. For examp le, a contractor wishing to submit bids on
18 projects to be opened on the 7th of Apri l must file the information by the 31st day of March
19 in order to eligible to work on these projects. In order to facilitate the approval of a Bidder's
20 Prequalification Application, the following must accompany the submission.
21 a. A complete set of audited or reviewed financial statements .
22 (1) Classified Balance Sheet
23 (2) Income Statement
24 (3) Statement of Cash F lows
25 (4) Statement of Retained Earnings
26 (5) Notes to the Financ ia l Statements, if any
27 b. A certified copy of the firm's organizational documents (Corporate Charter, Articles
28 oflncorporation, Articles of Organization, Certificate of Formation , LLC
29 Regulations, and Certificate of Limited Partnership Agreement).
30 c. A completed Bidder Prequalification App li cation.
31 (1) The firm 's Texas Taxpayer Identification Number as issued by the Texas
32 Comptro ll er of Public Accounts . To obtain a Texas Taxpayer Identification
33 number vis it the Texas Comptroller of Public Accounts online at the
34 following web address www.window.state.tx.us/taxpermit/ and fill out the
35 application to apply for your Texas tax ID .
36 (2) The firm's e-mai l address and fax number.
37 (3) The firm's DUNS number as issued by Dun & Bradstreet. This number
38 is used by the City for required reporting on Federal Aid projects. The DUNS
39 number may be obtained at www.dnb.com.
40 d. Resumes reflecting the construction experience of the principles of the firm for firms
41 submitting their initial prequalification. These resumes should include the size and
42 scope of the work performed.
43 e. Other information as requested by the City.
44
45 2. Prequalification Requirements
46 a. Finan cial Statements. Financial statement submission must be provided in
47 accordance with the following:
48 (1) The City requires that the original Financial Statement or a certifi ed copy
49 be submitted for consideration .
CITY OF FORT WORTH
STANDARD CO NSTRUCTION SPEC IFICATION DOC UME NTS
Re vised Au g ust 13, 202 1
2022 WATER SERVI CE LEAK
REPAIR CO NTRACT
City Project No. I 04552
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
3.
00 45 11 -2
BIDDERS P REQU ALIFJ CATIONS
Page 2 of3
(2 ) To be satisfactory , the financial statem e nts mu st be audited or reviewed
by an ind ependent, certified public accounting firm registered and in
g ood standing in any state . Current Texas statues also require that
accounting firms performing audits or reviews on business entities within
the State of Texas be properly licensed or registered with the Texas State
Board of Public Accountancy.
(3) The accounting firm should state in the audit report or review whether
the contractor is an individual , corporation, or limited liability company .
(4) Financial Statements must be presented in U.S . dollars at the current rate
of exchange of the Balance Sheet date.
(5) The City will not recognize any certified public accountant as
independent who is not, in fact , independent.
(6) The accountant 's opinion on the financial statements of the contracting
company should state that the audit or review has been conducted in
accordance with auditing standards generally accepted in the United
States of America. This must be stated in the accounting firm 's opinion.
It should: (I) express an unqualified opinion , or (2) express a qualified
opinion on the statements taken as a whole .
(7) The City re serves the right to require a new statement at any time .
(8) The financial statement must be prepared as of the last day of any month ,
not more than one year old and must be on file with the City 16 month s
thereafter, in accordance with Paragraph 1.
(9) The City will determine a contractor's bidding capacity for the purposes
of awarding contracts . Bidding capacity is determined by multiplying the
positive net working capital (working capital = current assets -current
liabilities) by a factor of 10 . Only those statements reflecting a positive
net working capital position will be cons idered satisfactory for
prequalification purposes.
(10) In the case that a bidding date falls within the time a new financial
statement is being prepared, the previous statement shall be updated with
proper verification .
b. Bidder Prequalification Application. A Bidder Prequalification Application must be
submitted along with audited or reviewed financial statements by firms wishing to be
eligible to bid on all classes of construction and maintenance projects. Incomplete
Applications will be rejected.
(I) In those schedules where there is nothing to report , the notation of
"None" or "NI A" should be inserted.
(2) A minimum of five (5) references of related work must be provided.
(3) Submission of an equipment schedule which indicates equipment under
the control of the Contractor and which is related to the type of work for
which the Contactor is seeking prequalification. The schedule must
include the manufacturer, model and general common description of
each piece of equipment. Abbreviations or means of describing
equipment other than provided above will not be accepted .
Eligibility for Award of Contract
a. The City shall be the sole judge as to a contractor's prequalification.
b. The City may reject, suspend, or modify any prequalification for failure by the
contractor to demonstrate acceptable financial ability or performance .
c. The City will issue a letter as to the status of the prequalification approval.
CITY OF FORT WORTH 2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No. I 04552
STANDARD CON STRUCTION SPEC IFI CATION DOCUMENT S
Rev ise d August 13, 202 1
I -
2
3
4
5
6
7
8
9
00 45 11 -3
BIDDERS PREQUALIFICATIONS
Page 3 of3
d. If a contractor has a valid prequalification letter, the contractor will be eligible to
perform the prequalified work types until the expiration date stated in the letter .
END OF SECTION
CITY OF FORT WORTH
STANDARD CONSTRUCTIO N SPECIFICATION DOCUMENTS
Revised August 13 , 2021
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No . I 04552
SECTION 00 45 12
PREQUALI FICATION STATEMENT
00 45 12
BID FO RM
Page 1 of 1
Each Bidder for a City procurement is required to complete the information below by identifying the prequalified
contractors and/or subcontractors whom they intend to utilize for the major work type(s) listed.
Major Work Type Contractor/Subcontractor Company Name Prequalification
Expiration Date
Water Improvements -1-inch
to 2-inch Water Service Leak
Repairs
0
Tejas Commercial Construction
The undersigned hereby certifies that the contractors and/or subcontractors described in the table above are
currently prequalified for the work types listed.
BIDDER:
Tejas Commercial Construction, LLC
P.O . Box 10395
0
River Oaks , TX 76114
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised 9/30/2021
END OF SECTION
By: Charles D. Allen
(Signature)
Title : Vice President
Date: 1/t-, / Z,oz.;r
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No . 104552
Date of Balance Sheet
SECTION 00 45 13
PREQUALIFICA TION APPLICATION
Mark only one:
Individual
Name under which you wish to qualify
Limited Partnership
General Partnership
Corporation
Limited Liability Company
Post Office Box City State Zip Code
Street Address (required) City State Zip Code
Telephone Fax Email
Texas Taxpayer Identification No.
I
Federal Employers Identification No .
DUNS No . (if applicable)
Email/mai l this questionnaire a long with financial statements to the appropriate group be low. A separate
submittal is required for water/sewer, paving, and lighting:
Work Category -Water Dept-Water/sewe r Work Category -TPW Paving Work Category -TPW Ped/Rdwy Lighting
john.kasavich@FortWorthTexas.gov TPW _prequal ifi cation@ fortworthtexas.gov c lint.h oover@fortworthtexas.gov
Fort Worth Water Department Engineering a nd City of Fort Worth Transportation and Public City offort Worth TPW Transportation
Fiscal Services Di v ision 200 Texas St. Fort Works Dept. 3741 SW Loop 820, Fort Worth , Management Attn: Clint Hoover, P.E. 500 1
Worth, TX 76 102 TX 76133 Attn : A li c ia Garcia James Ave. Fort Worth , TX 76115
*Financial Statements must be mailed. Mark the envelope: "Bidder Prequalification Application"
004513-2
BIDDER PREQUALIFICA TION APPLICATION
Page 2 of8
BUSINESS CLASSIFICATION
T he fo llowing shou ld b e completed in order that we may properly classify your firm:
(Check the block(s) which are app li cab le -Block 3 is to be left blank if Block 1 and/or Block 2 is
checked)
D Has fewe r than 100 empl oyees
and /or D Has less than $6,000 ,00 0 .00 in annual gross receipts
OR D Does not meet the criteria for being des ignated a small business as provided in Section
2006 .001 of the Texas Government Code.
The c lass ific ation of your firm as a small or large business is not a fac tor in determining eli g ibility to
become preq ualified.
Select major work categories for which you wo uld like to b e prequalified (City ma y deem you are not
qualified for selected category or may approve y ou at a lesser size/length and maximum size may
not be li ste d specifically under a major work category):
MAJOR WORK CATEGORIES
Water Department
A ugur Boring -24-inch di amet er casi ng and less
A ug ur Boring -Greater than 24-inch diameter casing and greate r
Tunn eling -36-Inches -60 -inches, and 350 LF or less
Tunnelin g -36-Inches -60 -in ches, and greater than 350 LF
Tunnelin g-66 " and greater, 350 LF and greater
Tunneling -66 " and greater, 350 LF or Less
Cathodic Protection
Water Distribution, D eve lopment, 8-inch diam eter and smaller
Water Distribution , Urban and Renewal , 8-inch diam et er and smaller
Water Distribution, Development, 12-i nch diameter and smaller
Water Distribution, Urban and Renewal , 12-inch diam eter and small er
Water Transmission, D evelopment, 24-inches and small er
Water Transmission, Urban/Renewal, 24-inches and smaller
Water Transmission , D eve lopment, 42-inches and small er
Water Transmission, Urban/Renewal, 42-inches and smaller
Water Transmission, D eve lopment, All Sizes
Water Transmission, Urban/Renewal, All Sizes
Sewer Bypass Pumping, 18-inches and smaller
Sewer By pass Pumping, 18-inches -36-inches
Sewer Bypass Pumping 42-inches and larger
CCTV, 8-inches and smaller
CCTV, 12-inche s and smaller
CCTV, 18-inches and small er
CCTV, 24-inches and smalle r
C ITY OF FORT WORTH
STANDARD CONSTRUCTION S PECIFICATIO N DOCUMENTS
Rev ised August 13, 202 1
2022 WATER SERVICE LEAK
REPAIR CONTRACT
C ity Project No. I 04552
00 45 13 -3
BIDDER PREQUA L!FI CA TION APPLI CATION
Page 3 of 8
MAJOR WORK CATEGORIES, CONTINUED
CCTV, 42-inches and smaller
CCTV, 48-inches and smaller
Sewer CIPP, 12 -inches and smaller
Sewer CIPP, 24-inches and smaller
Sewer CIPP, 42-inches and smaller
Sewer CIPP, All Sizes
Sewer Collection System, Development, 8-inches and smaller
Sewer Collection System, Urban/Renewal, 8-inches and smaller
Sewer Collection System, Development, 12-inches and smaller
Sewer Collection System, Urban/Renewal, 12-inches and smaller
Sewer Interceptors, Development, 24-inches and smaller
Sewer Interceptors , Urban/Renewal , 24-inches and smaller
Sewer Interceptors, Development, 42-inches and smaller
Sewer Interceptors , Urban/Renewal, 42-inches and smaller
Sewer Interceptors, Development, 48-inches and smaller
Sewer Interceptors , Urban/Renewal, 48-inches and smaller
Sewer Pipe Enlargement 12-inches and smaller
Sewer Pipe Enlargement 24-inches and smaller
Sewer Pipe Enlargement, All Sizes
Sewer Cleaning , 24-inches and smaller
Sewer Cleaning, 42 -inches and smaller
Sewer Cleaning, All Sizes
Sewer Cleaning, 8-inches and smaller
Sewer Cleaning, 12-inches and smaller
Sewer Siphons 12-inches or less
Sewer Siphons 24-inches or less
Sewer Siphons 42-inches or less
Sewer Siphons All Sizes
Transportation Public Works
Asphalt Paving Construction/Reconstruction (LESS THAN 15,000 square yards)
Asphalt Paving Construction/Reconstruction (15,000 square yards and GREATER)
Asphalt Paving Heavy Maintenance (UNDER $1,000,000)
Asphalt Paving Heavy Maintenance ($1,000,000 and OVER)
Concrete Paving Construction/Reconstruction (LESS THAN 15 ,000 square yards)*
Concrete Paving Construction/Reconstruction (15,000 square yards and GREATER)*
Roadway and Pedestrian Lighting
NOTE *There is not a prequalification requirement for installation of concrete sidewalk, curb &
gutter, driveways, and panel replacement, only on concrete street I ROW paving
CITY OF FORT WORTH
STANDARD CONSTRU CTION SPECIFICATION DOCU ME NTS
Revised August 13 , 2021
2022 WATER SERVICE LEAK
REPAJR CONTRACT
City Project No . I 04 552
1. List equipment yo u do not own but whic h is available by renting
00 45 13 -4
BIDDER PREQUALIFICA TION APPLICATION
Page 4 of8
D ESCRIPTION OF EQUIPMENT NAME AND D ETAIL ED ADDRESS OF OWNER
2. How many years has your organization be en in busines s as a general contractor under your present
nam e? -------------------------------------
List previous bu s in ess nam es : ____________________________ _
3. How many years of experience in __________ construction work has your organization
had:
(a) As a General Co ntr ac tor: ______ (b) As a Sub-Contractor: _____ _
4. *What projects has your organi zation completed in Texas and elsewhere?
CLASS LOCATION NAME AND D ETAILED
CONTRACT OF DATE CITY-COUNTY-ADDRESS OF OFFICIAL T O
AMOUNT WORK COMPLETED STATE WHOM YOU REFER
*If requalifying only show work performed s ince last statement.
5.Have you ever failed to complete any work awarded to you? ________________ _
If so, where and why? ______________________________ _
6.Has any officer or owner of y our organization ever been an officer of another organi zation that failed to
complete a contract? _______________________________ _
If so, state the name of the individual , other organization and reason . _____________ _
7 .Has any officer or owner of your organization ever failed to complete a contract executed in hi s/her
name ? ____________________________________ _
If so, state the name of the individual , name of owner and reason . _______________ _
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICA TION DO CUMENTS
Revi sed Aug ust 13, 202 1
2022 WATER SERVICE LEAK
REP AIR CONTRACT
C ity Project No. I 04552
00 45 13 -5
BIDDER PREQUALIFI C ATION APPLICATION
Page 5 of8
8 . In what other lines of business are you financially interested ? _______________ _
9. Have you ever perfonned any work for the City? ___________________ _
If so , when and to whom do you refer? ________________________ _
10. State names and detailed addresses of all producers from whom you have purchased principal
materials during the last three years.
NAME OF FIRM OR COMP ANY DETAILED ADDRESS
11 . Give the names of any affiliates or relatives currently debarred by the City. Indicate your relationship
to this person or firm . _______________________________ _
12. What is the construction experience of the principal individuals in your organization?
PRESENT MAGNITUDE
POSITION OR YEARS OF AND TYPE OF IN WHAT
NAME OFFICE EXPERIENCE WORK CAPACITY
13. If any owner, officer, director, or stockholder ofyour firm is an employee of the City, or shares the
same household with a City employee, please list the name of the City employee and the relationship . In
addition, list any City employee who is the spouse , child , or parent of an owner, officer, stockholder, or
director who does not live in the same household but who receives care and assistance from that person as
a direct result of a documented medical condition. This includes foster children or those related by
adoption or marriage. _______________________________ _
C ITY OF FORT WORTH
STANDARD CONSTRUCTION SP EC IFI C ATION DOCUMENTS
Re vised Au g ust I 3, 202 1
2022 WATER S ERVI CE LEAK
REPAIR CONTRACT
C ity Proj ect No . I 04 55 2
CORPORATION BLOCK
If a corporation:
D ate of Incorp orati on
Ch arter/F il e N o .
President
Vi ce Pres id ents
Secretary
T reas ure r
LIMITED LIABILITY COMPANY BLOCK
If a corporation:
State of In corp oration
D at e of organ ization
F il e N o.
Office rs or M anage rs (w ith titl es , if any)
00 45 13 - 6
BIDDER PREQUA LI FI C AT fON APPLI CA T ION
Page 6 of8
PARTNER SHIP BLOCK
If a partn ership:
State of Organizati on
D ate of organ ization
I s partners hip general, limited , or registered lim ite d
li a bili ty partn e rship ?
F il e No. (if L imited
P artn ersh ip)
Ge neral P artners/Officers
Limi te d P artners (if a ppli cabl e)
In d iv id ua ls authori zed to s ign for P artne rshi p
Except for limited partners, the individuals listed in the blocks above are presumed to have full
signature authority for your firm unless otherwise advi sed. Should you wish to grant signature
authority for additional individuals, please attach a certified copy of the corporate resolution,
corporate minutes, partnership agreement, power of attorney or other legal documentation which
grants this authority.
C ITY OF FORT WO RTH
STANDARD CONSTRUCT ION SP EC IFI CATION DOCUMENTS
Revi sed A ug ust 13, 202 1
2022 W ATER SERV ICE LEAK
RE PAI R CONTRACT
C ity Proj ect No. I 04552
14. Equipment
00 45 13 - 7
BIDD ER PREQUA LIFI CATION APPLI CATION
Page 7 of8
$ ______ _
TOTAL
Similar types of equipment may be lumped together. If your firm has more than 30 types of equipment,
you may show these 30 types and show the remainder as "various". The City, by allowing you to show
only 30 types of equipment, reserves the right to request a complete, detailed li st of all your equipment.
The equipment list is a representation of equipment under the control of the firm and which is related to
the type of work for which the firm is seeking qualification . In the description include, the manufacturer,
model , and general common description of each.
ITEM QUANTITY ITEM DESCRIPTION
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
Various-
CITY OF FORT WORTH
ST ANDA RD C ON STRUCTION SP ECIFJ CA TION DO CUMENTS
Revi sed Au gust 13 , 20 21
TOTAL
BALANCE SHEET
VALUE
2022 W ATE R S ERVI CE LEAK
REPAIR CONTRACT
City Proj ect No. 104552
00 45 13 -8
BIDD ER PREQUALIFICA TION APPLICAT IO N
Page 8 of8
BIDDER PREQUALIFICATION AFFIDAVIT
STATE OF
COUNTY OF
The undersigned hereby declares that the foregoing is a true statement of the financial condition of the
entity herein first named, as of the date herein first given; that this statement is for the express purpose of
inducing the party to whom it is submitted to award the submitter a contract; and that the accountant who
prepared the balance sheet accompanying this report as well as any depository , vendor or any other
agency herein named is hereby author ized to supply each party with any information, while this statement
is in force, necessary to verify said statement.
be ing dul y sworn, deposes and says that
h e/s he is the ________________ of ___________ _, the entity
described in and which executed the foregoing statement that he/s he is fa miliar with the books of the said
entity showing its financial condition; that the foregoing financial statement taken from the books of the
said entity as of the date thereof and that the answers to the que stion s of the foregoing Bidder
Prequalification Application are correct and true as of the date of this affidavit.
Firm Name:
Signature:
Sworn to before me thi s
_____ day of ________ ~ ____ _
Notary Public
Notary Public must not be an officer, director, or stockholder or relative thereof.
CITY OF FORT WORTH
ST AND ARD CONSTRUCT ION SPECIFICATION DOCUMENTS
Re vised August 13, 202 1
2022 WATER SERVICE LEAK
REPA JR CONTRAC T
City Project No. I 04552
1
2
3
00 45 26 -I
CONTRACTOR COMPLIANCE WITH WORKER'S COMPENSA TJON LAW
Page I of I
SECTION 00 45 26
CONTRACTOR COMPLIANCE WITH WORKER'S COMPENSATION LAW
4 Pursuant to Texas Labor Code Section 406.096(a), as amended, Contractor certifies that it
5 provides worker's compensation insurance coverage for all of its employees employed on City
6 Project No. 104552 . Contractor further certifies that, pursuant to Texas Labor Code, Section
7 406.096(b), as amended, it will provide to City its subcontractor's certificates of compliance with
8 worker's compensation coverage.
9
10 CONTRACTOR:
Tejas Commercial Construction, LLC By: Charles D. Allen
Company (Please Print)
11
12
13
14
15 P.O. Box 10395 Signature: &✓t/? ~
16 Address
17
18
19
20
21
22
23
24
25
River Oaks, TX 76114
City/State/Zip
THE STATE OF TEXAS
COUNTY OFT ARRANT
§
§
Title: Vice President
(Please Print)
BEFORE ME, the undersigned authority, on this day personally appeared 26
27
28
29
30
31
32
33
34
Charles D. Allen known to me to be the person whose name is
subscribed to the foregoing instrument, and acknowledged to me that he/she executed the same as
the act and deed of Vice President for the purposes and
consideration therein expressed and in the capacity therein stated.
GIVEN UNDER MY HAND AND SEAL OF OFFICE this l 4 J-,,ft
6 ... b,1..14,<'3-= , 20.23
35 ~~~~~~~~~~
36 ,,,111111,, LETICIA ANN ROJO
"\."r--?-Y Pu/~,,
37 {f:"::.:.X:{~ Notary Public, State of Texas
~~--.~.:~~Comm .Expires 11-12-2023
38 '-:-;,7,··oF°',l-:-Notary ID 124 702839
1111\
39
40
END OF SECTION
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revi sed July I , 2011
day of
2022 WATER SE RVICE L EAK
REPAIR CONTRACT
City Project No. 104552
2
3 APPLICATION OF POLICY
SECTION 00 45 40
Busines s E quity Goal
00 45 40 - I
Bus iness Equ ity Goal
Page I of2
4 If th e tota l dollar value of the contract is $100,000 or more, th e n a Busi ness E quity g oal is a pplicabl e .
5 A Business Equity Firm refers to certified Minority-, and/or Women-, owned Business Enterprises
6 (M/WBEs).
7
8 POLICY STATEMENT
9 It is the policy of the City of Fort Worth to ensure th e full and e quitable participation of Bu s in e s s E quity
l O F irm s when applicabl e, in the procurem ent of all g oods and s e rv ices. All require m ents and regulations
11 stated in the City's Bus ines s E quity O r din a nc e No.25165-I 0-2 0 2 1, (re pl acing Ordinance No . 24534-11-
12 2020 (codified at: https ://codelibrary.amlegal.com/codes/ftworth/latest/ftworth tx/0-0-0-22593 ) apply to
13 this bid.
14
15 BUSINESS EQUITY PROJECT GOAL
16 The City's Bus iness E quity goal on this project is 10 % of the total bid value of the contract (Base bid
17 appli es to Parks and Co mmunity Serv ices).
18
19 METHODS TO COMPLY WITH THE GOAL
20 On City contracts whe re a Busin ess E quity Goal is applied, offe rors a re re quired to comply w ith th e City 's
2 1 Bus ine s s E quity Ordinanc e by mee tin g or e x ceeding the above state d goal or otherwise comply w ith the
22 ordinance throu g h one of the follow in g methods: 1. Commercially useful services performed by a
23 Business Equity prime contractor, 2. Business Equity subcontracting participation, 3. Combination
24 of Business Equity prime services and Business Equity subcontracting participation, 4. Business
2 5 Equity Joint Venture/Mentor-Protege participation, 5. Good Faith Effort documentation, or 6.
26 Prime contractor Waiver documentation.
27
2 8 SUBMITTAL OF REQUIRED DOCUMENTATION
29 Applicable documents (listed below) mus t be received by the Purchas in g Divi s ion , OR the offeror shall
30 EMAIL the Bus ine ss E quity d o cumentation to the as sign ed C ity of Fort Worth Project M anager or
3 1 Department Des ignee. Documents are to be received no later than 2:00 p.m., on the third City
3 2 business day after the bid opening date, exclusive of the bid opening date.
33
34 The Offeror mu st s ubmit one or more o f th e followin g docume nt s :
35 I. Utilization Form and Letter(s) oflntent, if th e g oal is m e t or e x ce ede d;
36 2. Good Faith Effort Form and Utilization Form, including s upporting documentation, if
37 participation is less than st ated g o a l, or no Business E quity p a rti c ipation is accompli shed ;
38 3. Prime Contractor Waiver Form, including supporting documentation, if the Offeror will perform
39 all subcontracting/supplier opportunities; or
40 4. Joint Venture/Mentor-Protege Form, if g o a l is met or exceede d with a Joint Venture or Mentor-
41 Proteg e participation.
42
43 These forms can be found at:
44 Business E quity Utiliz ation Form an d Letter of Intent
45 https://apps.fortworthtexas.gov/ProjectResources/ResourcesP/60 -MWBE/Business Equity Utilization
46 Form DVIN 2022 220324.pdf
47
48 Letter of Inte nt
CITY OF FORT W ORTH
ST AN D ARD CONSTRUCTION SPECIF ICATION D OCUMENTS
Rev ised October 27 , 202 1
2022 WATER SERVI CE LEAK
RE PAI R CONTRACT
City project No. I 04552
00 45 40 - 2
B us in es s Eq ui ty Goa l
Page 2 of 2
2
3
https://apps.fortworthtexas.gov/ProjectResources/ResourcesP/60 -MWB E/Letter oflntent DVIN
2021.pdf
4 Business Equity Good Faith E ffort F orm
5 https://apps .fortworthtexas.gov/ProjectResources/ResourcesP/60 -MWBE/Good Faith Effort
6 Form DV1N 2022.pdf
7
8 Business Equity Prime Contractor Waiver F orm
9 https://apps.fortworthtexas.gov/ProjectResources/ResourcesP/60 -MWBE/MWBE Prime Contractor
10 Waiver-220313.pdf
11
12 Business Equity Joint Venture Form
13 https://apps .fortworthtexas .gov/ProjectResources/ResourcesP/60 -MWBE/MWBE Joint
14 Venture 220225 .pdf
15
16
17 FAJLURE TO ACHIEVE THE GOAL OR OTHERWISE COMPLY WITH THE ORDINANCE WILL
18 RESULT IN THE BIDDER/OFFEROR BEING DECLARED NON-RESPONSIVE AND THE BID
19 REJECTED.
20
21
22 FAILURE TO SUBMIT THE REQUIRED BUSJNESS EOUTY DOCUMENTATION OR OTHERWISE
23 COMPLY WITH THE ORDINANCE WILL RESULT IN THE BID BEING DECLARED NON-
24 RESPONSIVE, THE BID REJECTED AND MAY SUBJECT THE BIDDER/OFFEROR TO SANCTIONS
25 AS DESCRIBED JN SEC. 20-373 OF THE ORDINANCE.
26
27 For Questions, Please Contact The Business Equity Division of the Department of Diversity and
28 Inclusion at (817) 392-2674.
29 END OF SECTION
30
CIT Y O F FO RT WORTH
STAN DARD CON STRUC TION SPEC IFI CAT ION DOCUMEN TS
Rev ised Oc tober 27, 202 1
2022 WATER SERV ICE LEA K
RE PAIR CONTRACT
City project No . I 04552
SECTION 00 52 43
AGREEMENT
00 52 4 3 - I
Agree me nt
Page I of 6
THIS AGREEMENT, authorized on '1-/t+/1.,r:>"l/3 , is made by and between the City of Fort
Worth , a Texas home rule municipality, acting by and through its duly authorized City Manager,
("City"), and ::(eJAS C.OM"-'.~~L. Co~1'RutnON , lLL '
authorized to do business in Texas , acting by and through its duly authori zed representative,
("Contractor"). City and Contractor may jointly be referred to as Parties .
City and Contractor, in consideration of the mutual covenants hereinafter set forth, agree as follows:
Article 1. WORK
Contractor shall complete all Work as specified or indicated in the Contract Documents for the
Project identified herein.
Article 2. PROJECT
The project for which the Work under the Contract Documents may be the whole or only a part is
generally described as follows :
2022 WATER SERVICE LEAK REPAIR CONTRACT
City Project No. 104552
Article 3. CONTRACT PRICE
City agrees to pay Contractor for performance of the Work in accordance with the Contract
Documents an amount, in current funds , of Seven Hundred -Fifty Thousand and 00/100
Dollars ($750,000.00). Contract price may be adjusted by change orders duly authorized by the
Parties .
Article 4. CONTRACT TIME
4 .1 Final Acceptance.
The Work shall be complete for Final Acceptance within 365 days after the date when the
Contract Time commences to run, as provided in Paragraph 2.02 of the General Conditions ,
plus any extension thereof allowed in accordance with Article 12 of the General Conditions.
4.2 Liquidated Damages
Contractor recognizes that time is of th e essence for completion of Milestones, if any , and
to achieve Final Acceptance of the Work and City and the public will suffer from loss of
use if the Work is not completed within the time(s) specified in Paragraph 4.1 above. The
Contractor also recognizes the delays , expense and difficulties involved in proving in a
legal proceeding, the actual loss suffered by the City if the Work is not completed on time.
Accordingly , instead of requiring any such proof, Contractor agrees that as liquidated
damages for delay (but not as a penalty), Contractor shall pay City Three Hundred -
Fifteen and 00/100 Dollars ($315.00) for each day that expires after the time specified in
Paragraph 4.1 for Final Acceptance until the City issues the Final Letter of Acceptance.
C ITY OF FORT WORTH
STANDARD CONS TRUCTION SPEC IFI C ATIO N DOCUMENTS
R ev ised 8/22/2022
2 022 WATER SERVI CE LEA K
RE PAIR C ONTRACT
C ity Proj ect N o . I 04 552
Article 5. CONTRACT DOCUMENTS
5 .1 CONTENTS :
00 52 43 -2
Agreement
Page2of6
A.The Contract Documents which comprise the entire agree ment b etween City and
Contractor concerning the Work consist of the fo ll owing:
1. T hi s Agreement.
2 . Attachments to this Agreement:
a. Bid Form
1) Proposal Form
2) Vendor Comp li ance t o State Law Non-Resid e nt Bidder
3) Prequalification Statement
4) State and Federal documents (project specific)
b . Current Prevailing Wage Rate Tabl e
c. In surance ACORD Form(s)
d . Payment Bond
e. Performance Bond
f. Maintenance Bond
g . Power of Attorney for the Bonds
h. Worker 's Compensation Affidavit
1. MB E and/or SBE Utilization Form
3. General Conditions.
4 . Supp leme nt ary Conditions.
5. Specification s specifically made a part of th e Contract Documents by attachment or,
if not attached , as in corp orated by reference and de scribed in the Tab le of Contents
of the Project 's Co ntract Documents .
6. Drawi ngs.
7. A dd end a .
8. Documentation subm itted by Co ntractor prior to Notice of Award.
9. T he fo ll owi ng wh ich may be delivered or iss ued after the Effective Date of the
Agreement and , if issued , become an in corporated part of the Contract Documents:
a. Notice to Proceed.
b. F ie ld Orders.
c. Change Orders.
d. Letter of Final Acceptance.
Article 6. INDEMNIFICATION
6.1 Contractor covenants and agrees to indemnify, hold harmless and defend, at its own
expense, the city, its officers, servants and employees, from and against any and all
claims arising out of, or alleged to arise out of, the work and services to be performed
by the contractor, its officers, agents, employees , subcontractors, licenses or invitees
under this contract. This indemnification provision is specifically intended to operate
and be effective even if it is alleged or proven that all or some of the damages being
sought were caused, in whole or in part, by any act, omission or negligence of the city.
This indemnity provision is intended to include, without limitation, indemnity for costs,
expenses and legal fees incurred by the city in defending against such claims and causes
of actions.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIF ICATION DOCUMENTS
Revi se d 8/22 /2022
2022 WATER S ER VI CE LEA K
RE PAIR CONTRACT
C ity Project No . I 04552
00 52 43 - 3
Agre em ent
Page 3 of6
6.2 Contractor covenants and agrees to indemnify and hold harmless, at its own expense,
the city, its officers, servants and employees, from and against any and all loss, damage
or destruction of property of the city, arising out of, or alleged to arise out of, the work
and services to be performed by the contractor, its officers, agents, emp lo yees,
subcontractors, licensees or invitees under this contract. This indemnification provision
is specifically intended to operate and be effective even if it is alleged or proven that all
or some of the damages being sought were caused, in whole or in part, by any act,
omission or negligence of the city.
Article 7. MISCELLANEOUS
7.1 Terms .
Terms used in this Agreement which are defined in Article I of the General Conditions will
have the meaning s indicated in the General Conditions.
7 .2 Assignment of Contract.
This Agreement, including all of the Contract Documents may not be assigned by the
Contractor without the advanced express written consent of the City.
7.3 Successors and Ass igns .
City and Contractor each binds itself, its partners , successors, assigns and legal
representatives to the other party hereto, in respect to all covenants, ag reements and
obligations contained in the Contract Documents.
7.4 Severability/Non-Waiver of Claims.
Any provision or part of the Contract Documents held to be unconstitutional , void or
unenforceable by a court of competent jurisdiction shall be deemed stricken, and all
remaining provisions shall continue to be valid and binding upon City and Contractor.
The failure of City or Contractor to insi st upon the performance of any term or provision of
this Agreement or to exercise any right granted herein shall not constitute a waiver of City's
or Contractor's res pective right to ins ist upon appropriate performance or to assert any s uch
right on any future occasion.
7.5 Governing Law and Venue.
This Agreement, including all of the Contract Documents is performable in the State of
Texas. Venue shall be Tarrant County, Texas, or the United States District Court for the
Northern District of Texas, Fort Worth Division.
7 .6 Authority to Sign .
Contractor shall attach evidence of authority to sign Agreement if signed by someone other
than the duly authorized signatory of the Contractor.
7. 7 Non-appropriation of Funds .
In the event no funds or insufficient funds are appropriated by City in any fiscal period for
any payments due hereunder, City will notify Vendor of such occurrence and this Agreement
shall terminate on the last day of the fiscal period for which appropriations were received
without penalty or expense to City of any kind whatsoever, except a s to the portions o f the
payments herein agreed upon for which funds have been appropriated .
C ITY OF FORT WORTH
STANDARD CO NS TRUC TI ON SPECIFI CATION DOCUMEN TS
Rev ised 8/22 /2022
2022 WATE R SERVI CE LEAK
RE PAIR CO NT RACT
C ity Proj ect No . 10455 2
7.8 Prohibition On Contracts With Companies Boycotting Israel.
00 52 43 - 4
Agreement
Page 4 of6
Contractor, unless a sole proprietor, acknowledges that in accordance with Chapter 2271 of
the Texas Government Code, if Contractor has 10 or more full time-employees and the
contract value is $100 ,000 or more, the City is prohibited from entering into a contract with
a company for goods or services unless the contract contains a written verification from the
company that it: (1) does not boycott Israel; and (2) will not boycott Israel during the term of
the contract. The terms "boycott Israel" and "company" shall have the meanings ascribed to
those terms in Section 808.001 of the Texas Government Code. By signing this contract,
Contractor certifies that Contractor's signature provides written verification to the
City that if Chapter 2271, Texas Government Code applies, Contractor: (1) does not
boycott Israel; and (2) will not boycott Israel during the term of the contract.
7.9 Prohibition on Boycotting Energy Companies.
Contractor acknowledges that in accordance with Chapter 2274 of the Texas Government
Code-(as added by Acts 2021, 87th Leg., R.S., S.B. 13, § 2), the City is prohibited from
entering into a contract for goods or services that has a value of $100,000 or more , which
will be paid wholly or partly from public funds of the City, with a company (with 10 or more
full-time employees) unless the contract contains a written verification from the company
that it: (1) does not boycott energy companies; and (2) will not boycott energy companies
during the term of the contract. The terms "boycott energy company" and "company " have
the meaning ascribed to those terms by Chapter 2274 of the Texas Government Code (as
added by Acts 2021, 87th Leg., R.S., S.B. 13, § 2). To the extent that Chapter 2274 of the
Government Code is applicable to this Agreement, by signing this Agreement,
Contractor certifies that Contractor's signature provides written verification to the
City that Contractor: (1) does not boycott energy companies; and (2) will not boycott
energy companies during the term of this Agreement.
7.10 Prohibition on Discrimination Against Firearm and Ammunition Industries.
Contractor acknowledges that except as otherwise provided by Chapter 2274 of the Texas
Government Code (as added by Acts 2021, 87th Leg., R.S., S.B. 19, § 1), the City is
prohibited from entering into a contract for goods or services that has a value of $100 ,000 or
more which will be paid wholly or partly from public funds of the City, with a company (with
10 or more full-time employees) unless the contract contains a written verification from the
company that it: (1) does not have a practice, policy , guidance, or directive that discriminates
against a firearm entity or firearm trade association; and (2) will not discriminate during the
term of the contract against a firearm entity or firearm trade association. The terms
"discriminate ," "firearm entity" and "firearm trade association" have the meaning ascribed
to those terms by Chapter 2274 of the Texas Government Code (as added by Acts 2021 , 87th
Leg., R.S ., S.B. 19, § 1). To the extent that Chapter 2274 of the Government Code is
applicable to this Agreement, by signing this Agreement, Contractor certifies that
Contractor's signature provides written verification to the City that Contractor: (1)
does not have a practice, policy, guidance, or directive that discriminates against a
firearm entity or firearm trade association; and (2) will not discriminate against a
firearm entity or firearm trade association during the term of this Agreement.
C ITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DO CUMENTS
Revised 8/22/2022
2022 WATER SERVICE LEAK
REP AIR CONTRACT
C ity Project No . I 04552
7.11 Immigration Nationality Act.
00 52 43 - 5
Agreement
Page 5 of6
Contractor shall verify the identity and employment eligibility of its employees who perform
work under this Agreement, in cluding completing the E mployment E ligibility Verification
Form (1-9). Upon request by City , Contractor shall prov ide City with copies of all I-9 forms
and supporting e li g ibility documentation for each employee who pe rform s work under this
Agreement. Contractor shall adhere to all Federal and State laws as well as establish
appropriate procedures and controls so that no services will be performed by any Contractor
emp lo yee who is not legally eligible to perform such services. CONTRACTOR SHALL
INDEMNIFY CITY AND HOLD CITY HARMLESS FROM ANY PENALTIES,
LIABILITIES, OR LOSSES DUE TO VIOLATIONS OF THIS PARAGRAPH BY
CONTRACTOR, CONTRACTOR'S EMPLOYEES, SUBCONTRACTORS,
AGENTS, OR LICENSEES. City, upon written notice to Contractor, shall have the ri ght
to immediately terminate this Agreement for violations of this provision by Contractor.
7.12 No Third-Party Beneficiaries .
This Agreement g ive s no rights or benefits to anyone other than the City and the Contractor
and there are no third-party beneficiaries .
7 .13 No Cause of Action Against E n g ineer.
Contractor, its subcontractors and equipment and materials supp li ers on the PROJECT or their
sureties, shall maintain no direct action against the E ngineer, its officers, employees, and
subcontractors, for any c laim arising out of, in connection with, or resulting from the engineering
services perfonned. Only the City will be the beneficiary of any undertaking by the Engineer.
The presence or duties of the E ng ineer's pers onnel at a construction site, whether as on-site
representatives or otherwise, do not make the Engineer or its personnel in any way
responsible for those duties th a t belong to the City and/or the City's construction contractors
or other entities , and do not relieve the construction contractors or any other entity of their
obligations, duties , and responsibilities , including, but not limited to , all construction
methods , means , techniques , sequences, and proc e dures necessary for coordinating and
completing all portions of the construction work in accordance with the Contract Documents
and any health or safety precautions required by such construction work. The Engineer and
its personnel have no authority to exercise any control over any con struction contractor or
other entity or their employees in connection with their work or any health or safety
precautions.
C ITY OF FORT WORTH
ST AND ARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised 8/22 /2022
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No . I 04552
l [
I
11
11
11
00 52 43 -6
Agreement
Page 6 of6
IN WITNESS WHEREOF, City and Contractor have each executed this Agreement to be effective
as of the date subscribed by the City's designated Assistant City Manager ("Effective Date").
Contractor:
By:
d/ t' C/f'..--
Signature
(Printed Name)
Title
Address
~ :'(J <( OA-10) :=i)( 7/ll\ Ii
City/State/Zip
Date
CITY OF FORT WORTH
City ofFort Worth
By:
Dana Burghdoff
Assistant City Manager
Date
Attest:
Mar 6, 2023
Contract Compliance Manager:
By signing, I acknowledge that I am the person
responsible for the monitoring and
administration of this contract, including
ensuring all performance and reporting
requirements.
J. is Underwood
Senior Engineering Tech
Approved as to Form and Legality:
,vw,
081Kk {Marl,N.!31S:46CST)
Douglas W. Black
Sr. Assistant City Attorney
APPROVAL RECOMMENDED:
ct?dsfooher Harder
ChristopherHirder(Feb13,202307:07 CST)
Chris Harder, P.E.
Director,
Water Department
:?,.0 · SERVICE LEAK
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised 8/22/2022
OFFICIAL Rt _..__. .. ,.,,,,_.vA[R CONTRACT
CITY SECRETAR · • roject No . 104552
FT. WORTH, TX
00 61 13 -1
PERFORMANCE BOND
Page 1 of2
Bond Number: 10 7724005
SECTION 00 6113
PERFORMANCE BOND 2
3
4
5
6
THE STATE OF TEXAS
COUNTY OFT ARRANT
§
§
§
KNOW ALL BY THESE PRESENTS:
7
8 That we, __ T_ej~a_s_C_o_m_m_er_c_i_al_C_o_n_s_tr_u_c_t _io_n~,_L_L_C _______ , known as
9 "Principal " herein and Travelers Casualty and Surety Co mpany of America, a corporate
10 s urety(sureties, if more than one) duly authorized to do business in the State of Texas, known as
11 "Surety" herein (whether one or more), are held and firmly bound unto the City of Fort Worth, a
12 municipal corporation created pursuant to the laws of Texas, known as "City" herein, in the penal
13 sum of, Seven Hundred -Fifty Thousand & 00/100 Dollars($ 750,000.00), lawful money of
14 the United States, to be paid in Fort Worth, Tarrant County, Texas for the payment of which surn
15 well and truly to be made , we bind ourselves, our heirs , executors, administrators, successors and
16 assigns, jointly and severally, firmly by these presents.
17 WHEREAS, the Principal has entered into a certain written contract with the City
18 awarded the ~ day of ~'( , 2013, which Contract is hereby referred to and
19 made a part hereof for all purposes as if fully set forth herein , to furnish all materials, equipment
20 labor and other accessories defined by law, in the prosecution of the Work, including any Change
21 Orders, as provided for in said Contract designated as 2022 Water Service Leak Repair
22 Contract; City Project No. 104552
23 NOW, THEREFORE, the condition of this obligation is such that if the said Principal
24 shall faithfully perform it obligations under the Contract and shall in all respects duly and
25 faithfully perform the Work, including Change Orders, under the Contract, according to the plans,
26 specifications, and contract documents therein referred to , and as well during any period of
27 extension of the Contract that may be granted on the part of the City, then this obligation shall be
28 and become null and void, otherwise to remain in full force and effect.
29 PROVIDED FURTHER, that if any legal action be filed on this Bond, venue shall lie in
30 Tarrant County, Texas or the United States District Court for the Northern District of Texas, Fort
31 Worth Div ision .
CITY OF FO RT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July I , 201 1
WATER SERVICE LEAK
REPAIR CONTRACT
City Project No. 104552
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
0061 13-2
PERFORMANCE BOND
Page 2 of2
This bond is made and executed in compliance with the provisions of Chapter 2253 of the
Texas Government Code, as amended, and all liabilities on this bond shall be determined in
accordance with the provisions of said statue.
IN WITNESS WHEREOF, the Principal and the Surety have SIGNED and SEALED
this instrument by duly authorized agents and officers on this the \ .\-day of __ _
~bi(l'f . 20~.
Address: P.O. Box 10395 -----------River Oaks, TX 76114
Witness as to Principal
SURETY :
Travelers Casualty and Surety Com ~= BY:~:::.(...--.;....,,,,--
~-....c:.:::'-.i-~'---II'-'..._..-.. __ ~-~~-
*Note:
Signa re _ ~.
Lloyd Ray Pitts Tr -Attorney-~-.Fact
Name and Title ,,.. __
Address: One Tower Square
Hartford, CT 06183
. -
Telephone Number: (800) 328-2189
If signed by an officer of the Surety Company, there must be on file a certified extract
from the by-laws showing that this person has authority to sign such obligation. If
Surety's physical address is different from its mailing address, both must be provided.
The date of the bond shall not be prior to the date the Contract is awarded.
ClTY OF FORT WORTH WATER SERVICE LEAK
REPAIR CONTRACT
City Project No . I 04552
ST AND ARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1, 2011
SECTION 00 6114
PAYMENT BOND
006114-1
PAYMENT BOND
Page I of2
Bond N umb er: 107724005
2
3
4
5
6
THE STATE OF TEXAS
COUNTY OF TARRANT
§
§
§
KNOW ALL BY THESE PRESENTS:
7
8 That we , Tejas Commercial Construction, LLC , known as
9 "Principal " herein , and Travelers Casualty and Surety Company of America , a
10 corporate surety (sureties), duly authorized to do business in the State of Texas, known as
11 "Surety" herein (whether one or more), are held and firmly bound unto the City of Fort Worth, a
12 municipal corporation created pursuant to the laws of the State of Texas, known as "City" herein,
13 in the penal sum of Seven Hundred -Fifty Thousand & 00/100 Dollars ($750,000.00). lawful
14 money of the United States, to be paid in Fort Worth, Tarrant County, Texas, for the payment of
15 which sum well and truly be made , we bind ourselves , our heirs, executors, administrators,
16 successors and assigns , jointly and severally , firmly by these presents:
17 WHEREAS, Principal has entered into a certain written Contract with City, awarded the
18 ....l!__day of yt6,tµA~'( , 20..1:'2__, which Contract is hereby referred to and
19 made a part hereof for all purposes as if fully set forth herein, to furnish all materials, equipment,
20 labor and other accessories as defined by law, in the prosecution of the Work as provided for in
21 said Contract and designated as 2022 Water Service Leak Repair Contract; City Project No.
22 104552
23 NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION is such that if
24 Principal shall pay all monies owing to any (and all) payment bond beneficiary (as defined in
25 Chapter 2253 of the Texas Government Code , as amended) in the prosecution of the Work under
26 the Contract, then this obligation shall be and become null and void; otherwise to remain in full
27 force and effect.
28 This bond is made and executed in compliance with the provisions of Chapter 2253 of the
29 Texas Government Code, as amended , and all liabilities on this bond shall be determined in
30 accordance with the provisions of said statute.
31
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July I, 2011
WAT ER SERVIC E LEAK
REPAIR CONTRACT
City Project No. 104552
2
3
4
5
6
7
8
9
10
11
12
006114-2
PAYMENT BOND
Page 2 of2
IN WITNESS WHEREOF, the Principal and Surety have each SIGNED and SEALED
this instrument by duly authorized agents and officers on this the ,+ day of
_fa2a___.__............__u, ...... A ..... B.: .... :-f--, 20 _122_.
ATTEST:
Witness as to Principal
ATTEST:
~(Jd/4
(Surety) Secretary Melissa Pitts,
Bond Secretary
Jorda
SURETY:
Travelers Casualty and Surety
Company of America
BY: Sign~1:--~:-
Lloyd Ray Pitts Jr -Attorney-fo-Fqct
Name and Title '
Address: One Tower Square
Hartford, CT 06183
Telephone Number: (800) 328-2189
Note: If signed by an officer of the Surety, there must be on file a certified extract from the
bylaws showing that this person has authority to sign such obligation. If Surety's physical
address is different from its mailing address, both must be provided.
The date of the bond shall not be prior to the date the Contract is awarded.
END OF SECTION
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATlON DOCUMENTS
Re vis ed July I , 2011
WATER SERVICE LEAK
REPAJR CONTRACT
City Project No . 104552
~ TRAVELERS J
Travelers Casualty and Surety Company of America
Travelers Casualty and Surety Company
St. Paul Fire and Marine Insurance Company
POWER OF ATTORNEY
KNOW ALL MEN BY THESE PRESENTS : That Travelers Casualty and Surety Company of America , Travelers Casualty and Surety Company , and
St. Paul Fire and Marine Insurance Company are corporations duly organized under the laws of the State of Connecticut (herein
collective ly called the "Companies"), and that the Companies do hereby make , constitute and appoint Lloyd Ray Pitts Jr of
DALLAS , Texas , their true and lawfu l Attorney(s)-in -Fact to sign , execute , seal and
acknowledge any and all bonds , recognizances , conditional undertakings and other writings obligatory in the nature thereof on behalf of
the Companies in their business of guaranteeing the fidelity of persons , guaranteeing the performance of contracts and executing or
guaranteeing bonds and undertakings required or permitted in any actions or proceedings allowed by law .
IN WITNESS WHEREOF , the Compan ies have caused this instrument to be signed , and their corporate seals to be hereto affixed , this 21st day of April ,
2021 .
State of Connecticut
City of Hartford ss .
On this the 21st day of April , 2021 , before me personally appeared Robert L. Raney , who acknowledged himself to be the Senior
Vice President of each of the Companies , and that he , as such , being authorized so to do , executed the foregoing instrument for the
purposes therein contained by signing on behalf of said Companies by himself as a duly authorized officer .
IN WITNESS WHEREOF , I hereunto set my hand and official seal.
My Commission expires the 30th day of June , 2026
Anna P. Nowik , Notary Public
This Power of Attorney is granted under and by the authority of the following resolutions adopted by the Boards of Directors of each of
the Companies , which resolutions are now in full force and effect , reading as follows :
RESOLVED , that the Chairman , the President , any Vice Chairman , any Executive Vice President , any Senior Vice President , any Vice
President , any Second Vice President , the Treasurer , any Assistant Treasurer, the Corporate Secretary or any Ass istant Secretary may appoint
Attorneys-in-Fact and Agents to act for and on behalf of the Company and may give such appointee such authority as his or her certificate of authority
may prescribe to sign with the Company's name and seal with the Company's seal bonds , recognizances , contracts of indemnity , and other writings
obligatory in the nature of a bond , recognizance , or conditional undertaking , and any of said officers or the Board of Directors at any time may
remove any such appointee and revoke the power given him or her ; and it is
FURTHER RESOLVED , that the Chairman , th e President , any Vice Chairman , any Executive Vice President , any Senior Vice President or
any Vice President may delegate all or any part of the foregoing authority to one or more officers or employees of this Company , provided
that each such delegation is in writing and a copy thereof is filed in the office of the Secretary ; and it is
FURTHER RESOLVED, that any bond , recognizance , contract of indemnity , or writing obligatory in the nature of a bond , recognizance ,
or conditional uli1dertaking shall be valid and binding upon the Company when (a) signed by the President , any Vice Chairman , any Executive
Vice President , any Senior Vice President or any Vice President , any Second Vice President , the Treasurer, any Assistant Treasurer , the
Corporate Secretary or any Assistant Secretary and duly attested and sealed with the Company's seal by a Secretary or Assistant Secretary ;
or (b) duly executed (under seal, if required) by one or more Attorneys-in-Fact and Agents pursuant to the power prescribed in his or her
cert ificate or their certificates of authority or by one or more Company officers pursuant to a written delegation of authority ; and it is
FURTHER RESOLVED, that the signature of each of the following officers : President , any Executive Vice President , any Senior Vice President ,
any Vice President , any Assistant Vice President , any Secretary , any Assistant Secretary , and the seal of the Company may be affixed by facsimile to
any Power of Attorney or to any certificate relating thereto appointing Resident Vice Presidents , Resident Assistant Secretaries or Attorneys-in-
F act for purposes only of executing and attesting bonds and undertakings and other writi ngs obligatory in the nature thereof, and any such Power of
Attorney or certificate bearing such facsimile signature or facsimile seal shall be valid and binding upon the Company and any such power so executed
and certified by such facsimile signature and facsimile seal shall be valid and binding on the Company in the future with respect to any bond or
understanding to which it is attached.
I, Kevin E. Hughes , the undersigned , Assistant Secretary of each of the Companies , do hereby certify that the above and foregoing is a
true and co rrect copy of the Power of Attorney executed by said Companies , which rema ins in full force and effect.
Dated th is day of
---_,,--_ To verify the authenticity of this Power of Attorney, please call us at 1-800-421-3880.
Please refer to the above-named Attorney(s}-in-Fact and the details of the bond to which this Power of Attorney is attached.
IMPORTANT NOTICE
To obta in information or make a complaint:
You may call Travelers Casualty and Surety Company of America and its affiliates' toll-
free telephone number for information or to make a complaint at:
1-800-328-2189
You may contact the Texas Department of Insurance to obtain information on
companies , coverages , rights or complaints at:
1-800-252-3439
You may write the Texas Department of Insurance :
P. 0. Box 149104
Austin, TX 78714-9104
Fax : (512) 475-177 1
Web : http ://www .tdi.state.tx .us
E-mail : ConsumerProtection@tdi.state.tx .us
PREMIUM OR CLAIM DISPUTES:
Shou ld you have a dispute concerning your premium or about a cla im you should
contact your Agent or Travelers first. If the d ispute is not resolved , you may contact the
Texas Department of Insurance.
ATTACH THIS NOTICE TO YOUR BOND:
This notice is for information only and does not become a part or condition of the
attached document and is given to comply with Texas lega l and regulatory requirements .
(PN -042-B) Ed. 10 .18 .07
2
3
4 THE STATE OF TEXAS
SECTION 00 6119
MAINTENANCE BOND
006119-1
MAINTENANCE BOND
Page 1 of3
Bond Number: 107724005
5
§
§
§
KNOW ALL BY THESE PRESENTS:
6 COUNTY OF TARRANT
7
8 That we __ T_e~ja_s_C_o_m_m_e_r _ci_a_l_C_o_n_s_t_ru_c_t_io_n_, L_L_C ________ , known as
9 "Principal" herein and Travelers Casualty and Surety Company of America , a corporate surety
10 (sureties, if more than one) duly authorized to do business in the State of Texas, known as
11 "Surety" herein (whether one or more), are held and firmly bound unto the City of Fort Worth, a
12 municipal corporation created pursuant to the laws of the State of Texas, known as "City" herein,
13 in the sum of Seven Hundred-Fifty Thousand & 00/100 Dollars ($750,000.00), lawful money
14 of the United States, to be paid in Fort Worth, Tarrant County, Texas, for payment of which sum
15 well and truly be made unto the City and its successors, we bind ourselves, our heirs, executors,
16 administrators, successors and assigns, jointly and severally, firmly by these presents.
17
18 WHEREAS, the Principal has entered into a certain written contract with the City awarded
19 theJ.!_ day of rf,f>WA~'( , 201..}, which Contract is hereby
20 referred to and a made part hereof for all purposes as if fully set forth herein, to furnish all
21 materials, equipment labor and other accessories as defined by law, in the prosecution of the
22 Work, including any Work resulting from a duly authorized Change Order (collectively herein,
23 the "Work") as provided for in said contract and designated as 2022 Water Service Leak Repair
24 Contract; City Project No. 104552 ; and
25
26 WHEREAS, Principal binds itself to use such materials and to so construct the Work in
27 accordance with the plans, specifications and Contract Documents that the Work is and will
28 remain free from defects in materials or workmanship for and during the period of two (2) years
29 after the date of Final Acceptance of the Work by the City ("Maintenance Period"); and
30
31 WHEREAS, Principal binds itself to repair or reconstruct the Work in whole or in part
32 upon receiving notice from the City of the need therefor at any time within the Maintenance
33 Period.
34
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOC UMENTS
Revised Ju ly 1,2011
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No. 104552
0061 19-2
MAINTENANC E BOND
Page 2 of3
NOW THEREFORE, the condition of this obligation is such that if Principal shall
2 remedy any defective Work, for which timely notice was provided by City, to a completion
3 satisfactory to the City , then this obligation shall become null and void; otherwise to remain in
4 full force and effect.
5
6 PROVIDED, HOWEVER, if Principal shall fail so to repair or reconstruct any timely
7 noticed defective Work, it is agreed that the City may cause any and all such defective Work to
8 be repaired and/or reconstructed with all associated costs thereof being borne by the Principal and
9 the Surety under this Maintenance bond; and
10
11 PROVIDED FURTHER, that if any legal action be filed on this Bond , venue shall lie in
12 Tarrant County, Texas or the United States District Court for the Northern District of Texas, Fort
13 Worth Division; and
14
15 PROVIDED FURTHER, that this obligation shall be continuous in nature and
16 successive recoveries may be had hereon for successive breaches.
17
18
19
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revi se d July I , 2011
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No . 104552
006119-3
MAINTENANCE BOND
Page 3 of3
IN WITNESS WHEREOF, the Principal and the Surety have each SIGNED and SEALED this
2 instrument by duly authorized agents and officers on this the \4,-day of _____ _
3
4
5
6
7
8
9
10
11 ATTEST:
:~ (Prin~~c~
15
16
17
18
19
Address: P.O. Box 10395
River Oaks, TX 76114
20 Witness as to Principal
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
*Note:
SURETY:
Travelers Casualty and Surety
Com ~-
BY: -
Signa re ..:_
Lloyd Ray Pitts Jr -Attorney-Iii-Fact
Name and Title -_
Address: One Tower Square
Hartford, CT 06183
Telephone Number: (800) 328-2189
If signed by an officer of the Surety Company, there must be on file a certified extract
from the by-laws showing that this person has authority to sign such obligation. If
Surety's physical address is different from its mailing address, both must be provided.
The date of the bond shall not be prior to the date the Contract is awarded.
CITY OF FORT WORTH 2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project o. 104552
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July 1,2011
..... TRAVELERS J
Travelers Casualty and Surety Company of America
Travelers Casualty and Surety Company
St. Paul Fire and Marine Insurance Company
POWER OF ATTORN EY
KNOW ALL MEN BY TH ESE PR ESEN TS : That Travelers Casualty and Surety Company of America , Travelers Casualty and Surety Company , and
St. Paul Fire and Marine Insurance Company are corporations duly organized under the laws of the State of Conn ecticut (herein
collectively call ed the "Companies "), and that the Companies do hereby make , constitute and appoint Ll oyd Ray Pitts Jr of
DALLAS , Texas , the ir true and lawful Attorney(s)-in -Fact to sign , execute , seal and
acknowledge any and all bonds , recognizances , conditiona l undertakings and other writings obligatory in the nature the reof on behalf of
the Companies in their business of guaranteeing the fidelity of pe rso ns, guarantee ing the performance of contracts and executing or
guaranteeing bonds and undertakings required or permitted in any actions or pro ceedings allowed by law .
IN WITNESS WHEREOF , the Companies have caused this instrument to be signed , and their corporate sea ls to be hereto affixed , th is 21st day of April,
20 21.
State of Connecticut
City of Hartford ss .-· -'
On this the 21st day of April, 2021 , before me personally appeared Rob ert L. Ran ey, who acknowledged himself to be the Senior
Vice President of each of the Companie s , and that he , as such , be ing authorized so to do , executed the foregoing instrument for the
purposes therein contained by signing on behalf of said Companies by himself as a duly authorized officer .
IN WITNESS WHEREOF , I hereunto set my hand and officia l seal.
My Commission expires the 30th day of June , 2026
Anna P. Nowik , Notary Public
This Power of Attorney is granted under and by the authority of the following resolutions adopted by the Boards of Directors of each of
the Companies , which resolutions are now in full force and effect , reading as follows :
RESO LVED , that the Chairman , the President , any Vice Chairman , any Executive Vice President , any Senior Vice President , any Vice
Pres ident , any Second Vice President , the Treasurer , any Assistant Treasurer, the Corporate Secretary or any Assistant Secretary may appoint
Attorneys-in-Fact and Agents to act for and on behalf of the Company and may give such appo intee such authority as his or her certificate of authority
may prescribe to sign with the Co mpany's name and seal with the Company 's seal bonds , recognizances , contracts of indemnity , and other writings
obl igatory in the nature of a bond , recognizance , or conditional undertak ing , and any of said officers or the Board of Directors at any time may
remove any such appointee and revoke the power given him or her : and it is
FURT HER RESOLVED , that the Chairman , the Pres ident , any Vice Chairman , any Executive Vice President , any Sen ior Vice President or
any Vice President may delegate all or any part of the foregoing authority to one or more officers or employees of this Company , provided
that each such delegation is in writing and a copy thereof is filed in the office of the Secretary : and it is
FURTHER RESOLVED , that any bond , recogniza nce , contract of in dem nity, or writing ob ligato ry in the natu re of a bo nd , recognizance ,
or conditional undertaking shall be valid and binding upon t he Co mp any when (a ) signed by the President , any Vice Chai rman, any Executive
Vice President , any Senior Vice President or any Vice Preside nt , any Second Vice President , the Treasurer , any Assistant Treasurer , the
Corporate Secretary or any Assistant Secretary and duly attested and sea led with the Company's seal by a Secretary or Assistant Se cretary ;
or (b) duly executed (under seal , if required ) by one or more Attorneys-in-Fact and Agents pursuant to the power prescribed in his or her
certificate or the ir cert ificates of authority or by one or more Company officers pursuant to a written delegation of authority ; and it is
FURTHER RESOLV ED , that the signature of each of the following officers : President , any Executive Vice President , any Sen ior Vice Pres ident ,
any Vice President , any Assistant Vice President , any Secretary , any Assistant Secretary , and the seal of the Company may be affixed by facsimile to
any Power of Attorney or to any certificate re lating thereto appointing Resident Vice Presidents , Res ident Assistant Secretaries or Attorneys-in -
F act for purposes only of executing and attesting bo nds and undertakings and other writings obligatory in the nature thereof, and any such Power of
Attorney or certificate bearing such facsim ile signature or facsimi le sea l shall be val id and binding upon the Company and any such power so executed
and certified by such facsimile signature and fa csimi le seal shall be va lid and binding on the Company in the futu re wit h respect to any bo nd or
understanding to which it is attached .
I, Kevin E. Hughes , the undersigned , Assistant Secretary of each of the Companies , do hereby certify that the above and foregoing is a
true and correct copy of the Power of Attorney executed by said Companies , which rema ins in full force and effect.
Dated th is day of
~---To verify the authenticity of this Power of Attorney, please call us at 1-800-4 21-3880.
Please refer tq'the above-named Attorney(s)-in-Fact and the details of the bond to which this Power of Attorney is attached.
IMPORTANT NOTICE
To obtain information or make a complaint:
You may ca ll Travelers Casualty and Surety Company of America and its affiliates' toll-
free telephone number for information or to make a compla int at:
1-800-328-2189
You may contact the Texas Department of Insurance to obtain information on
companies , coverages, rights or complaints at:
1-800-252-3439
You may write the Texas Department of Insurance:
P. 0. Box 149104
Austin , TX 78714-9104
Fax : (512) 475-177 1
Web: http ://www.tdi.state .tx.us
E-mail : ConsumerProtection@tdi .state . tx. us
PREMIUM OR CLAIM DISPUTES:
Shou ld you have a dispute concern ing your premium or about a c la im you should
contact your Agent or Trave lers first. If the d ispute is not resolved, you may contact the
Texas Department of Insurance .
ATTACH THIS NOTICE TO YOUR BOND:
This notice is for info r mation only and does not become a part or condition of the
attached document and is g iven to comply with Texas lega l and regu latory requirements.
(PN -042-B) Ed . 10 .18.07
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
2 1
22
23
SECTION 00 61 25
CERTIFI CATE OF INSURANCE
END OF SECTION
C ITY OF FORT WORTH
STANDARD CONSTRUCTION SPECI FICATION DOCUMENTS
Revised J uly 1, 20 11
006125-1
CERT IFICATE OF INSURANCE
Page I of I
2022 WATER SERVI CE LEAK
RE PAIR CONTRACT
C ity Project No. I 04552
CITY OF FORT WORTH
STANDARD GENERAL CONDITIONS
OF THE CONSTRUCTION CONTRACT
ST AND ARD CONSTRUCTION SPECIF ICA TIO N DOCUMENTS
Revi sion: 8/23/2021
STANDARD GENERAL CONDITIONS OF THE
CONSTRUCTION CONTRACT
TABLE OF CONTENTS
Page
A rti c le 1 -D e finiti ons a nd Termin ology .......................................................................................................... 1
1.01 D efin e d Te rms ............................................................................................................................... 1
1.02 T ermin ology .................................................................................................................................. 6
A rticle 2-Pre limin a ry Matte r s ......................................................................................................................... 7
2 .01 Copi es of Doc u1n e nt s .................................................................................................................... 7
2 .02 Comme nce me nt of C ontract T im e; N otice to Proceed ................................................................ 7
2 . 03 Starting the Wo rk .......................................................................................................................... 8
2 .04 B efore Sta rtin g Construction ........................................................................................................ 8
2.05 Preconstru cti on Confe r e nc e .......................................................................................................... 8
2 .06 Public Meetin g .............................................................................................................................. 8
2.07 Initia l Acceptanc e of Sc he dul es .................................................................................................... 8
A rticle 3 -Contrac t D oc um e nts: Inte nt , Ame ndin g, R e use ............................................................................ 8
3.01 Intent. ............................................................................................................................................. 8
3 .02 R efer e nce Sta ndards ...................................................................................................................... 9
3 .0 3 R eporting and R esolving Discrep a nc ies ....................................................................................... 9
3 .04 A me ndin g a nd Supple menting Contrac tD oc um ents ................................................................. 10
3 .05 Reus e of Doc um e nt s ................................................................................................................... 10
3 .06 E le ctronic D ata ............................................................................................................................ 11
A rti c le 4 -A vaila bilit y of Lands; Subsurfac e a nd Phys ica l Co nditions ; H azardo us E nvir onm e nta l
Conditions; R efe re nce Points ........................................................................................................... 11
4 .01 Availa bility of L and s .................................................................................................................. 11
4.02 Subs urfac e and Phys ical Conditions .......................................................................................... 12
4 .03 Diffe rin g Subsurfa ce or Phys ical Conditions ............................................................................. 12
4.04 U ndergro und F aciliti es ............................................................................................................... 13
4 .05 R e fere nce P oint s ......................................................................................................................... 14
4.06 Haza rdo us Environmental Condition a t S ite .............................................................................. 14
Article 5 -B ond s and Ins uranc e ..................................................................................................................... 16
5.01 Lic e nse d Sur eti es and Insurers ................................................................................................... 16
5.02 P erforma nc e,Payme nt , and Mainte nanc e B onds ....................................................................... 16
5.03 Certificates of Insura nce ............................................................................................................. 16
5.04 Contractor 's Ins uranc e ................................................................................................................ 18
5.05 A c c epta nc e of Bonds and Ins urance; Option to R eplace ........................................................... 19
Article 6 -Contractor 's R esponsibilities ........................................................................................................ 19
6.01 Sup e rv ision a nd Sup e rintendence ............................................................................................... 19
CITY OF FORT WORTH
STANDARD CONSTRUCT ION SPECIF ICA TIO N DOCUMENTS
Revision: 8123/.l021
6.02 Labor; Working Hours ................................................................................................................ 20
6.03 Serv ices, Materials , and Equipm e nt ........................................................................................... 20
6.04 Project Schedule .......................................................................................................................... 21
6.0 5 Substitutes and "Or-Equals " ....................................................................................................... 21
6.0 6 Concerning Subcontractors , Suppliers , and Others .................................................................... 24
6.07 Wage Rate s .................................................................................................................................. 25
6.08 Patent Fees and Royalties ........................................................................................................... 26
6.09 Permits and Utilit ies .................................................................................................................... 27
6.10 Laws and Regulation s ................................................................................................................. 27
6.11 Taxes ........................................................................................................................................... 28
6.12 Use of Site and Other Areas ....................................................................................................... 28
6.13 Record Documents ...................................................................................................................... 29
6.14 Safety and Protection .................................................................................................................. 29
6.15 Safety Repre se ntative .................................................................................................................. 30
6.1 6 Hazard Communic ation Programs ............................................................................................. 30
6.17 Emergencie s and/or Rectification ............................................................................................... 30
6.18 Submittals .................................................................................................................................... 31
6.19 Continuing th e Work ................................................................................................................... 32
6.2 0 Contractor's Genera l Warranty and Guarantee .......................................................................... 32
6.21 Indernnillcation ......................................................................................................................... 33
6.22 Delegation of Professiona l D es ign Serv ices .............................................................................. 34
6.23 Right to Audit .............................................................................................................................. 34
6.24 Nondiscrimination ....................................................................................................................... 35
Artic le 7 -Other Work at th e Site ................................................................................................................... 35
7.01 Related Work at Site ................................................................................................................... 35
7.02 Coordination ................................................................................................................................ 36
Artic le 8 -City 's Re sponsi bilities ................................................................................................................... 36
8.01 Communications to Contractor ................................................................................................... 36
8.02 Furnish Data ................................................................................................................................ 36
8.03 Pay When Due ............................................................................................................................ 36
8.04 Lands and Ease ments ; Reports and Tests ................................................................................... 36
8.05 Change Orders ............................................................................................................................. 36
8.06 Inspections , Tests , and Approvals .............................................................................................. 36
8.07 Limitations on City's Re sponsibilities ....................................................................................... 37
8.08 Undisclosed Hazardous E nvironmental Condition .................................................................... 37
8.09 Compliance with Safety Program ............................................................................................... 37
Article 9 -City 's Observation Status During Construction ........................................................................... 37
9.01 City 's Project Manager ............................................................................................................ 37
9.02 Visits to Site ................................................................................................................................ 37
9.03 A uthorized Variations in Work .................................................................................................. 38
9.04 Rejecting Defective Work .......................................................................................................... 38
9.0 5 Determinations for Work Performed .......................................................................................... 38
9.06 Decisions on Re quirements of Contract Documents and Acceptability of Work ..................... 38
C ITY OF FORT WORTH
STANDARDC0NSTRUCTI0N SPECIFICATION DO CUMENTS
Revis ion: &'231.m l
Artic le 10 -Changes in the Work; C laims; Extra Work ................................................................................ 38
10.0 1 A uthorized Changes in the Work ............................................................................................... 38
10 .02 Una uthorized C hanges in the Work ........................................................................................... 39
10.03 Exec ut ion of Change Orders ....................................................................................................... 39
10.04 Extra Work .................................................................................................................................. 39
10.05 Notificat ion to Surety .................................................................................................................. 39
10.06 Contract C laims Process ............................................................................................................. 40
Art ic le 11 -Cost of the Work; Allowances ; Unit Price Work; P !ans Quantity Meas urement.. ................... .41
11.01 Cost of the Work ......................................................................................................................... 41
11.02 A llowances .................................................................................................................................. 43
11.03 Unit Price Work .......................................................................................................................... 44
11.04 P lans Q ua ntity Measurement. ..................................................................................................... 45
Article 12 -Change of Contract Price; Cha nge of Contract Time ................................................................. 46
12.0 1 Cha nge of Co ntract Price ............................................................................................................ 46
12.02 Change of Contract T im e ............................................................................................................ 47
12.03 De lays .......................................................................................................................................... 47
Artic le 13 -Tests and Inspections ; Correction, Remova l or Acceptance of Defective Work ...................... 48
13.0 1 Notice of Defects ........................................................................................................................ 48
13.02 Access to Work ........................................................................................................................... 48
13.03 Tests and Inspections .................................................................................................................. 48
13.04 U ncoverin g Work ........................................................................................................................ 49
13.05 City May Stop t he Work ............................................................................................................. 49
13 . 06 Correction or Re mova l of Defective Work ................................................................................ 50
13.07 Correction Period ........................................................................................................................ 50
13.08 Acceptance ofDefective Work. .................................................................................................. 51
13.09 City May Correct Defective Work ............................................................................................. 5 1
Artic le 14 -Payme nts to Contractor a nd Completion .................................................................................... 52
14 .0 1 Sche dule ofValu es ...................................................................................................................... 52
14 .02 Progress Payme nts ...................................................................................................................... 52
14.03 Co ntractor 's Wa rr anty of Tit le ................................................................................................... 54
14 .04 Partia l Util izatio n ........................................................................................................................ 55
14 .05 F in a l Inspectio n ........................................................................................................................... 55
14 .06 Fina l Acceptance ......................................................................................................................... 55
14.07 Fina l Payment. ............................................................................................................................. 56
14 .08 Final Comp letion De layed and Partia l Retainage Re lease ........................................................ 56
14 .09 Waive r of C laims ........................................................................................................................ 57
Article I S -Suspe ns ion of Work a nd Te rmin ation ........................................................................................ 57
15.01 City M ay Suspend Work ............................................................................................................. 57
15.02 City May Terminate for Cause ................................................................................................... 58
15 .03 City May Terminate For Convenie nce ....................................................................................... 60
Artie le 16 -Dis p ute Resolu tion ...................................................................................................................... 6 1
16 .01 Methods and Procedures ............................................................................................................. 6 1
CITY OF FORT WORTH
ST AND ARD CONSTRUCT IO N SPECIF ICA TIO N DO CUMENTS
Revi sion : &/23/2021
Artic le 17 -Miscellaneous .............................................................................................................................. 62
17.01 Giving Notice .............................................................................................................................. 62
17.02 Computation ofTimes ................................................................................................................ 62
17.03 Cumulative Remedies ................................................................................................................. 62
17.04 Surv iva l ofO bligations ............................................................................................................... 63
17. 05 Headings ...................................................................................................................................... 63
CITY OF FORT WORTH
STANDARDC0NSTRUCTI0N SPECIFICATION DOCUMENTS
Revision: &23/2021
ARTICLE 1-DEFINITIONS AND TERMINOLOGY
1.01 Defined Terms
00 72 00-1
GENERAL COND ITI ONS
Page I of63
A. Wherever used in these General Conditions or in other Contract Documents , the terms listed below
have the meanings indicated which are applicable to both the singular and plural thereof, and
words denoting gender shall include the masculine , feminine and neuter. Said terms are generally
capitalized or written in italics, but not always. When used in a context consistent with the
definition of a listed-defined term, the term s hall have a meaning as defined below whether
capitalized or italicized or otherwise. In addition to terms specifically defined, terms with initial
capital letters in the Contract Documents include references to id e ntified articles and paragraphs ,
and the titles of other documents or forms.
I. Addenda-Written or graphic instruments issued prior to the opening of Bids which clarify ,
correct, or change the Bidding Requirements or the proposed Contract Documents.
2. Agreement-The written instrument which is evidence of the agreement between City and
Contractor covering the Work.
3. Application for Payment-The form acceptable to City which is to be used by Contractor
during the course of the Work in requesting progress or final payments and which is to be
accompanied by such supporting documentation as is required by the Contract Documents.
4. Asbestos-Any material that contains more than one percent asbestos and is friable or is
releasing asbestos fibers into the air above current action levels established by the United States
Occupational Safety and Health Administration.
5. Award -Authorization by the City Council for the City to enter into an Agreement.
6 . Bid-The offer or proposal of a Bidder s ubmitted on the prescribed form setting forth the
prices for the Work to be performed .
7. Bidde r-T he individual or entity who submits a Bid directly to City.
8. Bidding Documents-The Bidding Requirements and the proposed Contract Documents
(including all Addenda).
9. Bidding Require me nts-The advertisement or Invitation to Bid , Instructions to Bidders , Bid
security of acceptable form, if any, and the Bid Form with any supplements.
10. Busine ss Day -A business day is defined as a day that the City conducts normal business ,
generally Monday through Frid ay, except for federal or state holidays observed by the City .
11. Ca lendar Day -A day consisting of 24 hours measured from midnight to the next midnight.
CITY OF FORT WORTH
STANDARD CONSTRUCT 10 N SPEC IF ICA TIO N DOCUMENTS
Revision : &23/202 1
00 72 00-1
GENERAL CO NDITI ONS
Page 2 of 63
12. Change Order-A document, which is prepared and approved by the City, which is signed
by Contractor and City and authorizes an addition, deletion, or revision in the Work or an
adjustment in the Contract Price or the Contract Time , issued on or after the Effective Date
of the Agreement.
13 . City-The City of Fort Worth, Texas , a home-rule municipal corporation, authorized and
chartered under the Texas State Statutes , acting by its governing body through its City
Manager, his designee , or agents authorized under his behalf, each of which is required by
Charter to perform specific duties with responsibility for final enforcement of the contracts
involving the City of Fort Worth is by Charter vested in the City Manager and is the entity
with whom Contractor has entered into the Agreement and for whom the Work is to be
performed.
14. City Attorn ey -The officially appointed City Attorney of the City of Fort Worth, Texas , or
his duly authorized representative .
15. City Council -The duly elected and qualified governmg body of the City of Fort Worth ,
Texas .
16. City Manager -The officially appointed and authorized City Manager of the City of Fort
Worth, Texas, or his duly authorized representative.
17. Contract Claim-A demand or assertion by City or Contractor seeking an adjustment of
Contract Price or Contract Time, or both , or other relief with respect to the terms of the
Contract. A demand for money or services by a third party is not a Contract Claim.
18. Contract-The entire and integrated written document between the City and Contractor
concerning the Work. The Contract contains the Agreement and all Contract Documents and
supersedes prior negotiations , representations , or agreements , whether written or oral.
19. Contract Docume nts-Those items so designated in the Agreement. All items listed in the
Agreement are Contract Documents. Approved Submittals, other Contractor submittals , and
the reports and drawings of subsurface and physical conditions are not Contract Documents .
20 . Contract Price-The moneys payable by City to Contractor for completion of the Work in
accordance with the Contract Documents as stated in the Agreement (subject to the provisions
of Paragraph 11.03 in the case of Unit Price Work).
21. Contract Time -The number of days or the dates stated in the Agreement to: (i) achieve
Milestones, if any and (ii) complete the Work so that it is ready for Final Acceptance .
22. Contractor-The individual or entity with whom City has entered into the Agreement.
23. Cost of the Work-See Paragraph I 1.01 of these General Conditions for defmition.
CITY OF FORT WORTH
STANDARD CONSTR UC TIO N SPEC IFICA TIO N DOCUMENTS
Re visi on : &23/202 1
00 7200 -1
GENERAL CO NDITIO NS
P age 3 of 6 3
24. Damage Claims -A demand for money or services arising from the Project or Site from a
third party, City or Contractor exclusive of a Contract Claim.
25. Day or day -A day, unless otherwise def med , shall mean a Calendar Day.
26. Director of Aviation -The officially appointed Director of the Aviation Department of the
City of Fort Worth , Texas, or his duly appointed representative , assistant, or agents.
27. Director of Parks and Community Servic es -The officially appointed Director of the Parks
and Community Services Department of the City of Fort Worth , Texas, or his duly appointed
representative, assistant, or agents.
28. Director of Planning and Development -The officially appointed Director of the Planning
and Development Department of the City of Fort Worth , Texas , or his duly appointed
representative, assistant, or agents.
29. Director of Transportation Public Work s -The officially appointed Director of the
Transportation Public Works Department of the City of Fort Worth, Texas , or his duly
appointed representative, assistant, or agents .
30. Director of Water Department -The officially appointed Director of the Water Department
of the City of Fort Worth, Texas, or his duly appointed representative , assistant, or agents.
31. Drawings-That part of the Contract Documents prepared or approved by Engineer which
graphically shows the scope, extent, and character of the Work to be performed by Contractor.
Submittals are not Drawings as so defined.
32. Effective Date of the Agreement-The date indicated in the Agreement on which it becomes
effective , but if no such date is indicated , it means the date on which the Agreement is signed
and delivered by the last of the two parties to sign and deliver.
33. Engineer-The licensed professional engineer or engineering firm registered in the State of
Texas performing professional services for the City.
34. Extra Work -Additional work made necessary by changes or alterations of the Contract
Documents or of quantities or for other reasons for which no prices are provided in the Contract
Documents. Extra work shall be part of the Work.
35. Field Order -A written order issued by City which requires changes in the Work but which
does not involve a change in the Contract Price, Contract Time , or the intent of the Engineer.
Field Orders are paid from Field Order Allowances incorporated into the Contract by funded
work type at the time of award.
36. Final Acceptance -The written notice given by the City to the Contractor that the Work
specified in the Contract Documents has been completed to the satisfaction of the City.
CITYOF FORT WORTH
STANDARD CONSTR UCT IO N SPEC IF ICA TIO N DO CUMENTS
Revi sion : &'23/2021
00 72 00-1
GENERAL COND IT IONS
Page 4 of 63
37. Fina l Inspection -Inspection carried out by the City to verify that the Contractor has
completed the Work, and each and every part or appurtenance thereof, fully , entirely , and in
conformance with the Contract Documents.
38. General Requirements-Sections of Division I of the Contract Documents .
39. Ha z ardous Environmental Condition-The presence at the Site of Asbestos, PCBs,
Petroleum, Hazardous Waste , Radioactive Material, or other materials in s uch quantities or
circumstances that may present a substantial dange r to persons or property exposed thereto.
40. Hazardous Waste -Hazardous waste is defmed as any solid waste listed as hazardous or
possesses one or more hazardous characteristics as defmed in the federal waste regulations,
as amended from time to time .
41. Laws and Regulations-Any and all applicable laws , rules , regulations , ordinances , codes ,
and orders of any and all gove rnmental bodies , agencies, authorities , and courts ha ving
jurisdiction.
42. Liens-Charges , security intere sts, or encumbrances up on Project funds , real property, or
persona l property.
43. Maj or Item -An Item of work included in the Contract Documents that has a total cost equal
to or greater than 5% of the original Contract Price or $25,000 whichever is less.
44. Milestone -A principal event specified in the Contract Documents relating to an intermediate
Contract Time prior to Final Acceptance of the Work.
45. Notice of Award-The written notice by City to the Successful Bidder stating that upon
timely compliance by the Successful Bidder with the conditions precedent listed therein , City
will s ign and deliver the Agreement.
46 . Notice to Proceed-A written notice given by City to Contractor fixing the date on which the
Contract Time will commence to run and on which Contractor shall start to perform the Work
specified in Contract Documents .
47. PCBs-Polychlorinated biphenyls.
48. Petroleum-Petroleum, including crude oil or any fraction thereof which is liquid at standard
conditions of temperature and pressure (60 degrees Fahrenheit and 14.7 pounds per square
inch absolute), such as oil, petroleum, fuel oil, oil sludge, oil refuse, gasoline, kerosene, and
oil mixed with other non-Hazardous Waste and crude oils.
49 . Plans -See definition of Drawings.
CITYOF FORT WORTH
STANDARD C0NSTRUCTION SPECIFICATION DOCUMENTS
Revision : &,23.,2021
007200-1
GENERAL CONDITIONS
Page 5 of 63
50. Project Schedule-A schedule, prepared and maintained by Contractor, in accordance with
the General Requirements , describing the sequence and duration of the activities compnsmg
the Contractor's plan to accomplish the Work within the Contract Time.
51. Project-The Work to be performed under the Contract Documents .
52. Proj ect Manager-The authorized representative of the City who will be assigned to the
Site.
53. Public Meeting -An announced meeting conducted by the City to facilitate public
participation and to assist the public in gaining an informed view of the Project.
54 . Radioactive Material-Source, special nuclear, or byproduct material as defmed by the
Atomic Energy Act of 1954 (42 USC Section 2011 et seq.) as amended from time to time .
55 . Regu lar Working Hours -Hours beginnin g at 7 :00 a.m. and ending at 6:00 p.m., Monday
thru Friday (excluding legal holidays).
56. Samples-Physical examples of materials , equipment, or workmanship that are
representative of some portion of the Work a nd whjch establish the standards by which such
portion of the Work will be judged.
57. Schedule of Submittals-A schedule, prepared and maintained by Contractor, of required
submittals and the time requirements to support scheduled performance of related construction
activities.
58. Schedule of Values-A schedule , prepare d and maintained by Contractor, allocating portions
of the Contract Price to various portions of the Work and used as the basis for reviewing
Contractor's Applications for Payment.
59. Site-Lands or areas indicated in the Contract Documents as being furnjghed by City upon
which the Work is to be performed, including rights-of-way , permrts , and easements for access
thereto, and such other lands furnished by City which are designated for the use of Contractor.
60. Specifications-That part of the Contract Documents consisting of written requirements for
materials , equipment, systems, standards and workmanship as applied to the Work, and certain
administrative requirements and procedural matters applicable thereto. Specifications may be
specifically made a part of the Contract Documents by attachment or , if not attached, may be
incorporated by reference as indicated in the Table of Contents (Division 00 00 00) of each
Project.
61. Subcontractor-An individual or entity having a direct contract with Contractor or with any
other Subcontractor for the performance of a part of the Work at the Site .
CITY OF FORT WORTH
ST ANDARDCONSTRUCT!O N SPEC I FI CA T!ON DOCUMENTS
Re vision : &1231..m l
00 72 00 -I
GENERAL CONDITIONS
Page 6 of 63
62. Submittals-All drawings , diagrams, illustrations , schedules, and other data or inform at ion
which are specifically prepared or assembled by or for Contractor and submitted by Contractor
to illu strate some portion of the Work.
63. Substantial Co mpletion -The stage in the progress of the Project when the Work is
s ufficiently complete in accordance with the Contract Doc um e nts for Final Insp ection .
64. Successful Bidder-The Bidder submitting the lowest and mo st responsive Bid to whom City
makes an Award.
65. Superintendent -The representative of the Contractor who is available at all tim es and able
to receive instructions from the City and to act for the Contractor.
66. Supplementary Co ndition s-That part of the Contract Documents which amends or
supp lements these General Conditions.
67 . Supplier-A manufacturer, fabricator, supplier, distributor , materialrnan , or vendor having a
direct contract with Contractor or with any Subcontractor to furnish materials or equipment
to be incorporated in the Work by Contractor or Subcontractor.
68. Underground Facilities-All underground pipe line s, conduits, ducts, cables , wires,
manholes , vaults, tanks , tunnels , or other such facilities or attachments, and any encasements
containing such facilities , including but not limited to, those that convey e lectricity, gases,
steam, liquid petrole um products , telephone or other communications , cable television ,
water, wastewater, storm water, other liquid s or chemicals , or traffic or other control systems.
69 Unit Pric e Work -See Paragraph 11.03 of thes e General Conditions for definition .
70. Weekend Working Hours -Hours beginning at 9:00 a.m. and ending at 5:00 p.m., Saturday,
Sunday or legal holiday , as approved in advance by the City.
71. Work -The entire construction or the various separately identifiable parts thereofrequired to
be provided under the Contract Documents. Work includes and is the result of performing or
providing all labor , services, and documentation neces sary to produce s uch construction
including any Change Order or Field Order, and furnishing, in stalling , and incorporating all
materials and equipment into such construction, all as required by the Contract Documents.
72 . Working Day -A working da y is defined as a day , not including Saturdays , Sundays, or legal
holidays authorized by the City for contract purposes , in which weather or other conditions
not under the control of the Contractor will permit the performance of the principal unit of
work underway for a continuous period of not less than 7 hours between 7 a.m. and 6 p.m.
1.02 Terminology
A. The words and terms discussed in Paragraph 1.02.B through E are not def med but, whe n used in
the Bidding Requirements or Contract Documents , have the indicated meaning.
B. Intent of Certain Terms or Adj ectives:
CITY OF FORT WORTH
ST AND ARD CONST RUCTION SPEC!F !CA TIO N DOCUMENTS
Revi sion : &23/2021
007200 -1
GENERAL CO NDITI ONS
P age 7 of 63
1. The Contract Docwnents include the terms "as allowed ," "as approved ," "as ordered," "as
directed" or terms of like effect or import to authorize an exercise of judgment by City. In
addition , the adjectiv e s "reasonable ," "suitable ," "acceptable ," "proper," "satisfactory," or
adjectives of like effect or import are used to describe an action or determination of City as to
the Work. It is intended that such exercise of profes s ional judgment, action , or determination
will be solely to evaluate , in genera~ the Work for compliance with the information in the
Contract Docwnents and with th e design concept of the Project as a functioning whole as
shown or indicated in the Contract Docume nt s (unless there is a specific statement indicating
otherwise).
C. D ef e ctive:
1. The word "defective ," when modifying the word "Work," refers to Work that is
unsatisfactory, faulty , or deficient in that it :
a . do e s not conform to the Contract Docwne nts; or
b. does not meet the requirements of any applicable inspection, reference standard , test, or
approva l referred to in the Contract Documents; or
c. has been damaged prior to City 's written acceptance.
D. Furnis h , In stall, Peiform, Provide :
1. The word ''Furnish" or the word "Install" or the word ''Perform" or the word ''Provide " or
the word "Supply," or any combination or similar directive or usage thereof, shall mean
furnishing and incorporating in the Work including all neces sary labor, materials , equipment,
and everything necessary to perform the Work indicated, unless specifically limited in the
context used.
E . Unless stated otherwise in the Contract Documents , words or phrases that have a well-known
technical or construction industry or trade meaning are us ed in the Contract Documents in
accordance with such recognized meaning.
ARTICLE 2 -PRELIMINARY MATTERS
2.01 Copies of Documents
City shall furnish to Contractor one (1) original executed copy and one (1) electronic copy of the
Contract Docwnents, and four (4) additional copies of the Drawings. Additional copies will be
furnished upon request at the cost of reproduction.
2.02 Commence ment of Contract Time; Notic e to Proceed
The Contract Time will commence to run on the day indicated in the Notice to Proceed. A Notice to
Proceed may be given no earlie r than 14 days after the E ffective Date of the Agreement, unless agreed
to by both parties in writing.
CITY OF FORT WORTH
ST ANDARDC 0NS TR UCT I0N SPEC IFICATION DOCUMENTS
Revi sion: 8/23/202 1
2.03 Starting th e Work
00 72 00 -1
GENERAL CON DITI ONS
Page 8 of 63
Contractor shall start to perform the Work on the date when the Contract Time commences to run.
No Work shall be done at the Site prior to the date on which the Contract Time commences to run .
2.04 Before Starting Construction
Baseline Schedules: Submit in accordance with the Contract Documents , and prior to starting the
Work.
2 .05 Preconstruction Corifere nc e
Before any Work at the Site is started, the Contractor shall attend a Preconstruction Conference as
specified in the Contract Documents.
2.06 Public Meeting
Contractor may not mobilize any equipment, materials or resources to the Site prior to Contractor
attending the Public Meeting as scheduled by the City.
2 .07 Initial Acceptance of Sche dule s
No progress payment shall be made to Contractor until acceptable schedules are submitted to City in
accordance with the Schedule Specification as provided in the Contract Documents.
ARTICLE 3 -CONTRACT DOCUMENTS: INTENT, AMENDING, REUSE
3.01 Intent
A . The Contract Documents are complementary ; what is required by one is as binding as if required
by all.
B. It is the intent of the Contract Documents to describe a functionally complete project ( or part
thereof) to be constructed in accordance with the Contract Documents. Any labor, documentation ,
services , materials , or equipment that reasonably may be inferred from the Contract Documents
or from prevailing custom or trade usage as being required to produce the indicated result will be
provided whether or not specifically called for , at no additional cost to City.
C . Clarifications and interpretations of the Contract Documents shall be issued by City.
D . The Specifications may vary in form, format and style. Some Specification sections may be written
in varying degrees of streamlined or declarative style and some sections may be relatively
narrative by comparison. Omission of such words and phrases as "the Contractor shall," "in
conformity with," "as shown," or "as specified" are intentional in streamlined sections.
Omitted words and phrases shall be supplied by inference. Similar types of provisions may appear
in various parts of a section or articles within a part depending on the format of the
CITY OF FORT WORTH
STANDARD C0NSTR UC TI 0N SPEC IFICA TIO N DOCUMENT S
Revi sion: &'23/202 1
00 72 00 -1
GENERAL CO NDITIONS
Page 9 of 63
section. The Contractor shall not take advantage of any variation of form , format or style m
making Contract Claims.
E. The cross referencing of specification sections under the subparagraph heading ''Related
Sections include but are not necessarily limited to :" and elsewhere within each Specification
section is provided as an aid and convenience to the Contractor. The Contractor shall not rely on
the cross referencing provided and shall be responsible to coordinate the entire Work under the
Contract Documents and provide a complete Project whether or not the cross referencing is
provided in each section or whether or not the cross referencing is complete.
3 .02 Reference Standards
A. Standards , Specifications, Codes , Laws , and Regulations
1. Reference to standards , specifications , manuals , or codes of any technical society, organization,
or association, or to Laws or Regulations, whether such reference be specific or by implication ,
shall mean the standard, specification, manual, code , or Laws or Regulations in effect at the
time of opening of Bids (or on the Effective Date of the Agreement if there were no Bids),
except as may be otherwise specifically stated in the Contract Documents.
2. No provision of any such standard, specification, manual, or code, or any instruction of a
Supplier, shall be effective to change the duties or responsibilities of City, Contractor, or any
of their subcontractors, consultants , agents , or employees , from those set forth in the Contract
Documents . No such provision or instruction shall be effective to assign to City , or any of its
officers , directors, members , partners , employees, agents , consultants , or subcontractors , any
duty or authority to supervise or direct the performance of the Work or any duty or authority
to undertake responsibility inconsistent with the provisions of the Contract Documents .
3.03 Reporting and Resolving Discrepancies
A. Reporting Discrepancies :
l. Contractor 's Review of Contract Documents Before Starting Work: Before undertaking each
part of the Work, Contractor shall carefully study and compare the Contract Documents and
check and verify pertinent figures therein against all applicable field measurements and
conditions . Contractor shall promptly report in writing to City any conflict, error, ambiguity ,
or discrepancy which Contractor discovers , or has actual knowledge of, and shall obtain a
written interpretation or clarification from City before proceeding with any Work affected
thereby .
2. Contra ctor 's Review of Contract Docume nts During Performance of Work: If, during the
performance of the Work, Contractor discovers any conflict, error, ambiguity , or discrepancy
within the Contract Documents, or between the Contract Documents and (a) any applicable
Law or Regulation , (b) any standard, specification, manual, or code , or (c) any instruction of
any Supplier, then Contractor shall promptly report it to City in writing. Contractor shall not
proceed w ith the Work affected thereby (except in an emergency as required by Paragraph
CITY OF FORT WORTH
ST ANDARD CONSTR UC TI O SPEC IFICA TI ON DOCUMENT S
Revi sion: &23/202 1
00 72 00 -1
GENERAL CONDITIONS
Page 10of63
6.17.A) until an amendment or supplement to the Contract Documents has been issued by
one of the methods indicated in Paragraph 3.04.
3. Contractor shall not be liable to City for failure to report any conflict, error, ambiguity, or
discrepancy in the Contract Documents unless Contractor had actual knowledge thereof.
B. Resolving Discrepancies:
1. Except as may be otherwise specifically stated in the Contract Documents , the provisions of
the Contract Documents shall take precedence in resolving any conflict, error, ambiguity, or
discrepancy between the provisions of the Contract Documents and the provisions of any
standard, specification, manual, or the instruction of any Supplier (whether or not specifically
incorporated by reference in the Contract Documents).
2. In case of discrepancies , figured dimensions shall govern over scaled dimens ions , Plans shall
govern over Specifications, Supplementary Conditions shall govern over General Conditions
and Specifications, and quantities shown on the Plans shall govern over those shown in the
proposal.
3 .04 Amending and Supplementing Contract Documents
A. The Contract Documents may be amended to provide for additions, deletions , and revisions m
the Work or to modify the terms and conditions thereof by a Change Order.
B. The requirements of the Contract Documents may be supplemented, and minor variations and
deviations in the Work not involving a change in Contract Price or Contract Time , may be
authorized, by one or more of the following ways:
1. A Field Order;
2 . City's review of a Submittal (subject to the provisions of Paragraph 6.18.C); or
3 . City's written interpretation or clarification.
3.05 Reuse of Documents
A . Contractor and any Subcontractor or Supplier shall not:
1. have or acquire any title to or ownership rights in any of the Drawings, Specifications, or
other documents ( or copies of any thereof) prepared by or bearing the seal of Engineer,
including electronic media editions; or
2. reuse any such Drawings , Specifications, other documents , or copies thereof on extensions of
the Project or any other project without written consent of City and specific written verification
or adaptation by Engineer.
CITY OF FORT WORTH
ST ANDARDCONS TR UCTION SPECIF ICATION DOCUMENTS
Revision : &/23/2021
00 72 00 -1
GENERAL CO NDITIONS
Page 11 of63
B. The prohibitions of this Paragr aph 3.05 will s urvive final payment, or t e rmination of the
Contract. Nothing herein shall preclude Contractor from retaining copies of the Contract
Documents for record purpose s.
3.06 Ele ctronic Data
A. Unless otherwise stated in the Supplementary Conditions , the data furnished by City or Engineer
to Contractor, or by Contractor to City or E ngineer , that may be relied upon are limited to the
printed copies included in the Contract Documents (also known as hard copies) and other
Specifications referenced and located on the City 's on-line e lectronic document management and
collaboration system site. Files in electronic media format of text, data, graphics, or other types
are furnished only for the convenjence of the re ceiving party. Any conclusion or information
obtained or derived from such electronic files will be atthe user's sole risk. If there is a discrepancy
between the electronic ftles and the hard copies , the hard copies govern.
B. When transferring documents in electronic media format, the transferring party makes no
representations as to long term compatibility , usability , or readability of documents resulting from
the us e of software application packages, operating systems, or computer hardware differing from
those used by the data 's creator.
ARTICLE 4 -AVAILABILITY OF LANDS; SUBSURFACE AND PHYSICAL CONDITIONS;
HAZARDOUS ENVIRONMENTAL CONDITIONS; REFERENCE POINTS
4.01 A vailability of Lands
A. City shall furnish the Site. City shall notify Contractor of any encumbrances or restrictions not of
general application but specifically related to use of the Site with which Contractor must comply
in performing the Work. City will obtain in a timely manner and pay for easements for permanent
structures or permanent changes in existing facilities .
1. The City has obtained or anticipate s acquisition of and/or access to right-of-way , and/or
easements. Any outstanding right-of-way and/or easements are anticipated to be acquired in
accordance with the schedule set forth in the Supplementary Conditions . The Project Schedule
submitted by the Contractor in accordance with the Contract Documents must consider any
outstanding right-of-way , and/or easements .
2. The City has or anticipates removing and/or relocating utilities , and obstructions to the Site.
Any outstanding removal or relocation of utilities or obstructions is anticipated in accordance
with the schedule set forth in the Supplementary Conditions. The Project Schedule submitted
by the Contractor in accordance with the Contract Documents must consider any outstanding
utilities or obstructions to be removed, adjusted , and/or relocated by others .
B . Upon reasonable written request, City shall furnish Contractor with a current statement of record
legal title and legal description of the lands upon which the Work is to be performed.
C ITY OF FORT WORTH
ST AND ARD CONSTRUCTION SPECIF ICATION DOCUMENTS
Rev ision: ~I
00 72 00 -1
GENERAL COND ITI ON S
Page 12 of63
C. Contractor shall provide for all additional lands and access thereto that may be required for
construction facilities or storage of materials and equipment.
4.02 Subsurfac e and Physical Condition s
A. Reports and Drawings : The Supplementary Conditions identify:
1. those reports known to City of explorations and tests of subsurface conditions at or
contiguous to the Site ; and
2. those drawings known to City of physical conditions relating to existing surface or
subsurface structure s at the Site (except Underground Facilities).
B. Limited Reliance by Contractor on Technical Data Authorize d: Contractor may rely upon the
accuracy of the "technical data" contained in such reports and drawings , but such reports and
drawings are not Contract Documents. Such ''technical data" is identified in the Supplementary
Conditions. Contractor may not make any Contract Claim against City, or any of their officers ,
directors , members , partners , employees , agents , consultants, or subcontractors with respect to:
1. the completeness of such reports and drawings for Contractor's purposes , including , but not
limited to , any aspects of the means , methods , techniques , sequences , and procedures of
construction to be employed by Contractor, and safety precautions and programs incident
thereto; or
2. other data , interpretations , opinions, and information contained in such reports or shown or
indicated in such drawings ; or
3. any Contractor interpretation of or conclusion drawn from any ''technical data" or any such
other data , interpretations , opinions, or information.
4 .03 DifferingSubswface or Phy s ical Conditions
A . Notice : If Contractor believes that any subsurface or physical condition that is uncovered or
revealed either:
1. is of such a nature as to establish that any ''technical data" on which Contractor is entitled to
rely as provided in Paragraph 4 .02 is materially inaccurate ; or
2. is of such a nature as to require a change in the Contract Documents ; or
3. differs materially from that shown or indicated in the Contract Documents; or
4 . is of an unusual nature, and differs materially from conditions ordinarily encountered and
generally recognized as inherent in work of the character provided for in the Contract
Documents;
C ITY OF FORT WORTH
ST AND ARD CONSTR UCTI ON SPEC IF !CA TIO N DOC UMENTS
Rev ision : &2:3/.m l
00 72 00-1
GENERAL CONDI TIONS
Page 13of63
then Contractor shall, promptly after becoming aware thereof and before further disturbing the
subsurface or phy s ical conditions or performing any Work in connection therewith (except in an
emergency as required by Paragraph 6.17.A), notify City in writing about such condition.
B. Possible Pric e and Time Adjustments
Contractor shall not be entitled to any adjustment in the Contract Price or Contract Time if:
1. Contractor knew of the existence of such conditions at the time Contractor made a fina 1
commitment to City with respect to Contract Price and Contract Time by the submiss ion of a
Bid or becoming bound under a negotiated contract; or
2 . the existence of such condit ion could reasonably have been discovered or revealed as a result
of the examination of the Contract Documents or the Site; or
3. Contractor failed to give the written notice as required by Paragraph 4.03.A.
4 .04 Underground Facilities
A . Shown or Indicated: The information and data shown or indicated in the Contract Documents
with respectto existing Underground Facilities at or contiguous to the Site is based on information
and data furnished to City or E ngineer by the owners of s uch Underground Facilities ,
including City , or by others. Unless it is otherwise expressly provided in the Supplementary
Conditions :
1. City and Engineer shall not be responsib le for the accuracy or completeness of any such
information or data provided by others; and
2 . the cost of all of the following will be included in the Contract Price , and Contractor shall
have full responsibility for:
a. reviewing and checking all such information and data;
b. locating all Underground Facilities shown or indicated in the Contract Documents ;
c. coordination and adjustment of the Work with the owners of such Underground
Facilities , including City , during construction; and
d. the safety and protection of all s uch Underground Facilities and repairing any damage
thereto resulting from the Work.
B. Not Shown or Indicated:
1. If an Underground Facility which conflicts with the Work is uncovered or revealed at or
contiguous to the Site which was not shown or indicated, or not shown or indicated with
reasonable accuracy in the Contract Documents , Contractor shall, promptly after becoming
aware thereof and before further disturbing conditions affected thereby or performing any
CITYOF FORT WORTH
STANDARDCONSTRUCTION SPECIFICATIO DOCUMENTS
Rev ision : &23/202 1
00 72 00-1
GENERAL CO NDITION S
Page 14 of 63
Work in connection therewith ( except in an emergency as required by Paragraph 6.17.A),
identify the owner of such Underground Facility and give notice to that owner and to City .
City will review the discovered Underground F acility and determine the extent, if any, to
which a change may be required in the Contract Documents to reflect and document the
consequences of the existence or location of th e Underground Facility. Contractor shall be
responsible for the safety and protection of such discovered Underground F acility .
2. If City concludes that a change in the Contract Documents is required, a Change Order may
be issued to reflect and document such consequences.
3 . Verification of existing utilities , structures , and service lines shall include notification of all
utility companies a minimum of 48 hours in advance of construction including exploratory
excavation if necessary.
4 .05 Reference Points
A. City shall provide engineering surveys to establish reference points for construction, which in
City 's judgment are necessary to enable Contractor to proceed with the Work. City will provide
construction stakes or other customary method of marking to establish line and grades for roadway
and utility construction, centerlines and benchmarks for bridgework. Contractor shall protect and
preserve the established reference points and property monuments, and shall make no changes or
relocations . Contractor shall report to City whenever any reference point or property monument is
lost or destroyed or requires relocation because of necessary changes in grades or locations. The
City shall be responsible for the replacement or relocation of reference points or property
monuments not carelessly or willfully destroyed by the Contractor. The Contractor shall notify
City in advance and with sufficient time to avoid delays .
B. Whenever, in the opinion of the City, any reference point or monument has been carelessly or
willfully destroyed, disturbed , or removed by the Contractor or any of his employees, the full cost
for replacing such points plus 25% will be charged against the Contractor, and the full amount will
be deducted from payment due the Contractor.
4.06 Hazardous Environmental Condition at Site
A. Reports and Drawings: The Supplementary Conditions identify those reports and drawings known
to City relating to Hazardous Environmental Conditions that have been identified at the Site .
B. Limited Reliance by Contractor on Technical Data Authorized: Contractor may rely upon the
accuracy of the "technical data" contained in such reports and drawings, but such reports and
drawings are not Contract Documents. Such ''technical data" is identified in the Supplementary
Conditions. Contractor may not make any Contract Claim against City, or any of their officers,
directors, members , partners , employees , agents, consultants, or subcontractors with respect to:
1. the completeness of such reports and drawings for Contractor's purposes, including , but not
limited to , any aspects of the means , methods, techniques , sequences and procedures of
C ITY OF FO RT WORTH
STANDARD C0NS TR UCT IO N SPEC IFICA TIO N DOC UM ENTS
Revi sion : &'23.002 1
00 72 00-1
GENERAL COND ITI ONS
Page 15 of63
construction to be employed by Contractor and safety precautions and programs incident
thereto; or
2 . other data , interpretations , opinions and information contained in such reports or s hown or
indicated in such drawings; or
3. any Contractor interpretation of or conclusion drawn from any "technical data" or any such
other data , interpretations , opinions or information.
C . Contractor shall not be responsible for any Hazardous Environmental Condition uncovered or
revealed at the Site which was not shown or indicated in Drawings or Specifications or identified
in the Contract Documents to be within the scope of the Work. Contractor shall be responsible for
a Hazardous E nvironmental Condition created with any materials brought to the Site by
Contractor, Subcontractors , Suppliers, or anyone else for whom Contractor is responsible .
D . If Contractor encounters a Hazardous E nvironmental Condition or if Contractor or anyone for
whom Contractor is responsible creates a Hazardous Environme ntal Condition, Contractor shall
immediately: (i) secure or otherwise isolate such condition; (ii) stop all Work in connection with
such condition and in any area affected thereby (except in an emergency as required by Paragrapl
6.17.A); and (iii) notify City (and promptly thereafter confirm suc h notice in writing). City may
consider the necessity to retain a qualifie d expert to evaluate such condition or take corrective
action, if any.
E . Contractor shall not be required to resume Work in connection with such condition or in any
affected area until after City has obtained any required permits related thereto and delivered written
notice to Contractor: (i) specifying that such condition and any affected area is or has been
rendered suitable for the resumption of Work; or (ii) specify in g any spec ial conditions under which
such Work ma y be resumed.
F . If after receipt of such written notice Contractor doe s not agree to resume s uch Work based on a
reasonable belief it is unsafe , or does not agree to resume such Work under such special conditions,
then City may order the portion of the Work that is in the area affected by such condition to be
deleted from the Work. City may have such deleted portion of the Work performed by City's own
forces or others.
G. To the fullest extent permitted by Laws and Regulations, Contractor shall indemnify and hold
harmless City , from and against all claims, costs, losses, and damages (including but not limited
to all fees and charges of engineers, architects, attorneys, and other professionals and all court
or arbitration or other dispute resolution costs) arising out of or relating to a Hazardous
Environmental Co ndition created by Contractor or by anyoneforwhom Co ntractor is responsible.
Nothing in this Paragraph 4 . 06.G s hall obligate Contractor to indemnify any individual or entity
from and against the consequences of that individual 's or entity's own negligence.
H. The provisions of Paragraphs 4.02, 4.03 , and 4.04 do not apply to a Hazardous Environmental
Condition uncovered or revealed at the Site.
CITY OF FORT WORTH
ST ANDARDCONSTRUCTION SPECIFICATION DOCUMENTS
Revision : &123/X)21
ARTICLE 5 -BONDS AND INSURANCE
5.01 Licensed Sureties and Insurers
00 72 00 -I
GENERAL CO NDITI ON S
Pag e 16of63
All bonds and insurance required by the Contract Documents to be purchased and maintained by
Contractor shall be obtained from surety or in s urance companies that are duly licensed or authorized
in the State of Texas to issue bonds or insurance policies for the limits and coverages so required.
Such surety and insurance companies shall also meet such additional requirements and qualifications
as may be provided in the Supplementary Conditions.
5.02 Pe rformance, Payme nt, and Maintenance Bonds
A . Contractor shall furnish performance and payment bonds, in accordance with Texas Government
Code Chapter 2253 or successor statute, each in an amount equal to the Contract Price as
security for the faithful performance and payment of all of Contractor 's obligations under the
Contract Documents .
B. Contractor shall furnish maintenance bonds in an amount equal to the Contract Price as security
to protect the City against any defects in any portion of the Work described in the Contract
Documents . Maintenance bonds shall remain in effect for two (2) years after the date of Fina l
Acceptance by the City .
C. All bonds shall be in the form prescribed by the Contract Documents except as provided otherwise
by Laws or Regulations , and shall be executed by such sureties as are named in the list of
"Companies Holding Certificates of Authority as Acceptable Sureties on Federal Bonds and as
Acceptable Reinsuring Companies" as published in Circular 570 (amended) by the Financial
Management Service , Surety Bond Branch, U .S. Department of the Treasury. All bonds signed by
an agent or attorney-in-fact must be accompanied by a sealed and dated power of attorney which
shall show that it is effective on the date the agent or attorney-in-fact signed each bond.
D. If the surety on any bond furnished by Contractor is declared bankrupt or becomes insolvent or its
right to do business is terminated in the State of Texas or it ceases to meet the requirements of
Paragraph 5.02.C , Contractor shall promptly notify City and shall, within 30 days after the event
giving rise to such notification, provide another bond and surety, both of which shall comply with
the requirements of Paragraphs 5.01 and 5 .02.C .
5.03 Certificates of Insurance
Contractor shall deliver to City , with copies to each additional insured and loss payee identified in the
Supplementary Conditions, certificates of insurance ( other evidence of insurance requested by City or
any other additional insured) in at least the minimum amount as specified in the Supplementary
Conditions which Contractor is required to purchase and maintain.
1. The certificate of insurance shall document the City, and all identified entities named in the
Supplementary Conditions as "Additional Insured" on all liability policies.
CIT Y OF FO RT WORTH
ST AND ARD CONSTR UC TI ON SPEC IF ICA TIO N DOC UMENTS
Revi sion : &'23/202 1
00 72 00-1
GENERAL CONDIT IONS
Page 17 of 63
2. The Contractor 's general liability insurance shall include a, "per project" or "per location",
endorsement, which shall be identified in the certificate of insurance provided to the City.
3. The certificate shall be signed by an agent authorized to bind coverage on behalf of the insured ,
be complete in its entirety, and show complete insurance carrier names as listed in the current
A.M. Best Property & Casualty Guide
4. The insurers for all policies must be licensed and/or approved to do business in the State of
Texas. Except for workers' compensation, all insurers must have a minimum rating of A-:
VII in the current A . M. Best Key Rating Guide or have reasonably equivalent financial
strength and so lv ency to the satisfaction of Risk Management. If the rating is below that
required , written approval of City is required.
5. All applicable policies shall include a Waiver of Subrogation (Rights of Recovery) in favor
of the City. In addition, the Contractor agrees to waive all ri ghts of subrogation against the
E ngineer (if applicable), and each additional insured identified in the Supplementary
Conditions
6. Failure of the City to demand such certificates or other evidence of full compliance with the
in s urance requirements or failure of the City to identify a deficiency from evidence that is
provided shall not be construed as a waiver of Contractor's obligation to maintain such lines
of insurance coverage.
7. If insurance policie s are not written for specified coverage limits , an Umbrella or Excess
Liability insurance for any differences is required . Excess Liability shall follow form of the
primary coverage.
8. Unless otherwise stated, all required insurance shall be written on the "occurrence basis". If
coverage is underwritten on a claims-made basis , the retroactive date shall be coincident with
or prior to the date of the effective date of the agreement and the certificate of insurance shall
state that the coverage is claims-made and the retroactive date. The in s urance coverage shall
be maintained for the duration of the Contract and for three (3) years following Final
Acceptance provided under the Contract Documents or for the warranty period, whichever is
longer. An annual certificate of insurance submitted to the City shall evidence such
in s urance coverage.
9. Policies shall have no exclusions by endorsements, which, neither nullify or amend, the
required lines of coverage, nor decrease the limits of said coverage unless such endorsements
are approved in writing by the City . In the event a Contract has been bid or executed and the
exclusions are determined to be unacceptable or the City desires additional insurance coverage,
and the City desires the contractor/engineer to obtain such coverage, the contract price shall
be adjusted by the cost of the premium for such additional coverage plus 10%.
10. Any self-insured retention (SIR), in excess of $25,000.00, affecting required insurance
coverage shall be approved by the City in regards to asset value and stockholders' equity. In
CITY OF FORT WORTH
ST AND ARD CONSTRUCTION SPECIF !CA TIO DOCUMENTS
Revi sio n: &23/2021
00 72 00-I
GENERAL CONDITIONS
Page 18 of 63
lieu of traditional insurance, alternative coverage maintained through insurance pools or risk
retention groups, must also be approved by City.
11. Any deductible in excess of $5,000.00, for any policy that does not provide coverage on a
fast-dollar basis , mu st be acceptable to and approved by the City.
12. City, at its sole discretion , reserves the right to review the insurance requirements and to
make reasonable adjustments to insurance coverage 's and their limits when deemed necessary
and prudent by the City based upon changes in statutory law , court decision or the claims
history of the industry as well as of the contracting party to the City. The City shall be required
to provide prior notice of 90 days , and the insurance adjustments shall be incorporated into the
Work by Change Order.
13. City shall be entitled, upon written request and without expense, to receive copies of policies
and endorsements thereto and may make any reasonable requests for deletion or revision or
modifications of particular policy terms, conditions, limitations, or exclusions necessary to
conform the policy and endorsements to the requirements of the Contract. Deletions, revisions ,
or modifications shall not be required where policy provisions are established by law or
regulations binding upon either party or the underwriter on any such policies.
14. City shall not be responsible for the direct payment of insurance premium costs for
Contractor's insurance.
5 .04 Con tractor's Insuranc e
A . Workers Compensation and Employers' Liability. Contractor shall purchase and maintain such
insurance coverage with limits consistent with statutory benefits outlined in the Texas Workers'
Compensation Act (Texas Labor Code, Ch. 406 , as amended), and minimum limits for Employers'
Liability as is appropriate for the Work being performed and as will provide protection from claims
set forth below which may arise out of or result from Contractor's performance of the Work and
Contractor's other obligations under the Contract Documents, whether it is to be performed by
Contractor, any Subcontractor or Supplier, or by anyone directly or indirectly employe d by any of
them to perform any of the Work, or by anyone for whose acts any of them may be liable:
1. claims under workers' compensation, disability benefits , and other similar employee benefit
acts;
2. claims for damages because of bodily injury , occupational sickness or disease , or death of
Contractor's employees.
B . Commercial General Liability. Coverage shall include but not be limited to covering liability
(bodily injury or property damage) arising from: premises /operations, independent contractors ,
products /c ompleted operations, personal injury , and liability under an insured contract. Insurance
shall be provided on an occurrence basis, and as comprehensive as the current Insurance Services
Office (ISO) polic y. This insurance shall apply as primary insurance with respect to any other
CITY OF FORT WORTH
STANDARD C0NST RUCTI 0 N SPECIFICATION DOCUMENTS
Revi sion: &'23/2021
00 72 00-I
GENERAL CO NDITIONS
Page 19of 63
insurance or self-insurance programs afforded to the City. The Commercial General Liability
policy, shall have no exclusions by endorsements that would alter of nullify premises/operations,
products/completed operations , contractual, personal injury , or advertising injury , which are
normally contained with the policy , unless the City approves such exclusions in writing .
For construction projects that present a substantial completed operation exposure, the City may
require the contractor to maintain completed operations coverage for a minimum of no less than
three (3) years following the completion of the project (if identified in the Supplementary
Conditions).
C . Automobile Liability. A commercial business auto policy shall provide coverage on "any auto",
defmed as autos owned , hired and non-owned and provide indemnity for claims for damages
because bodily injury or death of any person and or property damage arising out of the work ,
maintenance or use of any motor vehicle by the Contractor, any Subcontractor or Supplier , or by
anyone directly or indirectly employed by any of them to perform any of the Work, or by anyone
for whose acts any of them may be liable .
D. Railroad Protective Liability. If any of the work or any warranty work is within the limits of
railroad right-of-way , the Contractor shall comply with the requirements identified in the
Supplementary Conditions .
E . Notification of Policy Cancellation: Contractor shall immediately notify City upon cancellation
or other loss of insurance coverage . Contractor shall stop work until replacement insurance has
been procured. There shall be no time credit for days not worked pursuant to this section.
5.05 Acceptance of Bonds and Insuranc e; Option to Replace
If City has any objection to the coverage afforded by or other provisions of the bonds or insurance
required to be purchased and maintained by the Contractor in accordance with Article 5 on the basis
of non-conformance with the Contract Documents , the City shall so notify the Contractor in writing
within 10 Business Days after receipt of the certificates ( or other evidence requested). Contractor shall
provide to the City such additional information in respect of insurance provided as the City may
reasonably request. If Contractor does not purchase or maintain all of the bonds and insurance required
by the Contract Documents, the City shall notify the Contractor in writing of such failure prior to the
start of the Work, or of such failure to maintain prior to any change in the required coverage.
ARTICLE 6 -CONTRACTOR'S RESPONSIBILITIES
6.01 Supervision and Superintendence
A. Contractor shall supervise, inspect, and direct the Work competently and efficiently, devoting
such attention thereto and applying such skills and expertise as may be necessary to perform the
Work in accordance with the Contract Documents. Contractor shall be solely responsible for the
means , methods , techniques, sequences , and procedures of construction .
CITY OF F ORT WORTH
STANDARD CONSTRUC TI ON SPECIF I CA TIO DOCUMENTS
Revision : &'23/202 1
007200 -1
GENERAL CON DITI ONS
Page 20 of 63
B. At all times during the progress of the Work, Contractor shall assign a competent, English-
speaking, Superintendent who shall not be replaced without written notice to City. The
Superintendent will be Contractor 's representative at the Site and shall have authority to act on
behalf of Contractor. All communication given to or received from the Superintendent shall be
binding on Contractor.
C. Contractor shall notify the City 24 hours prior to moving areas during the sequence of construction.
6.02 Labor; Working Hours
A. Contractor shall provide competent, suitably qualified personnel to perform construction as
required by the Contract Documents. Contractor shall at all times maintain good discipline and
order at the Site.
B. Except as otherwise required for the safety or protection of persons or the Work or property at
the Site or adjacent thereto, and except as otherwise stated in the Contract Documents, all Work
at the Site shall be performed during Regular Working Hours. Contractor will not permit the
performance of Work beyond Regular Working Hours or for Weekend Working Hours without
City 's written consent (which will not be unreasonably withheld). Written request (by letter or
electronic communication) to perform Work:
1. for beyond Regular Working Hours request must be made by noon at least two (2) Business
Days prior
2. for Weekend Working Hours request must be made by noon of the preceding Thursday
3. for legal holidays request must be made by noon two Business Days prior to the legal
holiday.
6.03 Services, Materials, and Equipment
A. Unless otherwise specified in the Contract Documents, Contractor shall provide and assume full
responsibility for all services, materials , equipment, labor, transportation, construction equipment
and machinery, tools, appliances , fuel, power, light, heat, telephone, water, sanitary facilities,
temporary facilities , and all other facilities and incidentals necessary for the performance,
Contractor required testing, start-up, and completion of the Work.
B. All materials and equipment incorporated into the Work shall be as specified or, if not specified,
shall be of good quality and new, except as otherwise provided in the Contract Documents. All
special warranties and guarantees required by the Specifications shall expressly run to the benefit
of City . If required by City, Contractor shall furnish satisfactory evidence (including reports of
required tests) as to the source , kind, and quality of materials and equipment.
CITY OF FORT WORTH
STANDARD C0NS TR UC TI0 SPEC IFI CAT IO N DOCUMENTS
Revision : &23/202 1
00 72 00-1
GENERAL CONDITIONS
Page 2 1 of63
C. All materials and equipment to be incorporate d into the Work shall be stored, applied, installed ,
connected, erected, protected, use d , cleaned, and conditioned in accordance with instructions of
the applicable Supplier, except as otherwise may be provided in the Contract Docume nts.
D . All items of standard equipment to be incorporated into the Work shall be the latest model at the
time of bid , unless otherwise specified.
6.04 ProjectSchedule
A. Contractor s hall adhere to the Project Schedule established in accordance with Paragraph 2.07
and the General Requirements as it may be adju sted from time to time as provided be low.
I . Contractor shall submit to City for acceptance (to the extent indicated in Paragraph 2.07 and
the General Requirements) propos e d adju stments in the Project Schedule that will not result
in changing the Contract Time. Such adjustments will comply with any provisions of the
Ge ne ral Requirements applicable thereto.
2. Contractor shall submit to City a monthly Project Schedule with a monthly progress payment
for the duration of the Contract in accordance with the schedule sp ec ification 01 32 16.
3. Proposed adjustments in the Project Schedule that will change the Contract Time shall be
s ubmitted in accordance with the requirements of Article 12. Adjustments in Contract Time
may only be made by a Change Order.
6 .05 Substitutes and "Or-Equals "
A. Whenever an item of material or equipment is specified or described in the Contract Documents
by us ing the name of a proprietary item or the name of a particular Supplier, the specification or
description is intended to establish the type , function, appearance , and quality required . Unless the
specification or de s cription contains or is followed by words reading that no like , equivalent, or
"or-equal" item or no substitution is pe rmitt e d , other items of material or equipment of other
Suppliers may be submitted to City for review under the circumstances described below.
1. "O r-Equal " Ite ms: If in City's sole discretion an item of material or equipment proposed by
Contractor is functionally equal to that named and sufficiently similar so that no change in
related Work will be required , it may be considered by City as an "or-equal" item, in which
case review and approval of the proposed item may, in City's sole discretion, be accomplished
without compliance with some or all of the requirements for approval of propose d substitute
items. For the purposes of this Paragraph 6 .05.A. l, a proposed item of material or equipment
will be considered functionally equal to an item so named if:
a. the City determines that:
CITY OF FORT WORTH
1) it is at least equal in materials of construction, quality , durability , appearance,
strength, and design characteristic s;
STANDARDC0NSTRUCTI0N SPECIFICATION DOCUMENTS
Revi sion &23/202 1
007200-1
GENERAL COND ITIONS
Page 22of63
2) it will reliably perform at least equa lly well the function and achieve the results
imposed by the design concept of the completed Project as a functioning whole; and
3) it has a proven record of performance and availability of responsive service ; and
b. Contractor certifies that, if approved and incorporate d into the Work:
1) there will be no incre ase in cost to the City or increase in Contract Time; and
2) it will conform substantially to the detailed requirements of the item named in the
Contract Documents.
2. Substitute Items :
a . If in City's sole discretion an item of material or equipment proposed by Contractor does
not qualify as an "or-e qual" item under Paragraph 6 .05 .A. l , it may be submitted as a
proposed substitute item.
b . Contractor shall submit sufficient information as provided below to allow City to determine
if the item of material or equipment proposed is essentially equivalent to that named and
an acceptable substitute therefor. Requests for review of proposed substitute items of
material or equipment will not be accepted by City from anyone othe r than Contractor.
c. Contractor shall make written application to City for review of a proposed substitute item
of material or equipment that Contractor seeks to furnish or use. The application shall
comply with Section 01 25 00 and :
CITYOF FORT WORTH
1) shall certify that the proposed substitute item will:
a) perform adequately the functions and achieve the re s ults called for by the general
design ;
b) be similar in substance to that specified;
c) be suited to the same use as that specified; and
2) will state:
a) the extent, if any, to which the use of the proposed substitute item will prejudice
Contractor's achievement of final completion on time ;
b) whether use of the proposed substitute item in the Work will require a change in
any of the Contract Documents (or in the provisions of any other direct contract
with City for other work on the Project) to adapt the design to the propose d
substitute item;
ST AND ARD CONST RUCTION SPECIF ICA TIO N DOCUMENTS
Revision : &1231;m.I
00 72 00-1
GENERAL CON □ IT IONS
Page 23 of 63
c) whether incorporation or use of the proposed substitute item in connection with
the Work is subject to payment of any license fee or royalty; and
3) will identify:
a) all variations of the proposed substitute item from that specified;
b) available engineering, sales , maintenance , repair, and replacement services; and
4) shall contain an itemized estimate of all costs or credits that will result directly or
indirectly from use of such substitute item , including costs of redesign and Damage
Claims of other contractors affected by any resulting change.
B. Substitute ConstructionMethods or Procedures: If a specific means , method , technique , sequence,
or procedure of construction is expressly required by the Contract Documents , Contractor may
furnish or utilize a substitute means , method , technique, sequence, or procedure of construction
approved by City. Contractor shall submit sufficient information to allow City , in City's sole
discretion, to determine that the substitute proposed is equivalent to that expressly called for by
the Contract Documents. Contractor shall make written application to City for review in the same
manner as those provided in Paragraph 6 .05.A.2 .
C. City 's Evaluation: City will be allowed a reasonable time within which to evaluate each
proposal or submittal made pursuant to Paragraphs 6.05.A and 6.05.B. City may require Contractor
to furnish additional data about the proposed substitute. City will be the so le judge of acceptability.
No "or-equal" or substitute will be ordered, installed or utilized until City's review is complete,
which will be evidenced by a Change Order in the case of a substitute and an accepted Submittal
for an "or-equal." City will advise Contractor in writing of its determination.
D. Special Guarantee: City may require Contractor to furnish at Contractor's expense a special
performance guarantee, warranty, or other surety with respect to any substitute. Contractor shall
indemnify and hold harmless City and anyone directly or indirectly emp loyed by them from and
against any and all claims, damages , lo sses and expenses (including attorneys fees) arising out of
the use of substituted materials or equipment.
E . City 's Cost Reimbursement: City will record City's costs in evaluating a substitute proposed or
submitted by Contractor pursuant to Paragraphs 6 .05.A.2 and 6.05.B. Whether or not City
approves a substitute so proposed or submitted by Contractor, Contractor may be required to
reimburse City for evaluating each such proposed substitute. Contractor may also be required to
reimburse City for the charges for making changes in the Contract Documents ( or in the provisions
of any other direct contract with City) resulting from the acceptance of each proposed substitute.
F. Contractor's Expense: Contractor shall provide all data in support of any proposed substitute or
"or-equal" at Contractor's expense.
CITYOF FORT WORTH
STANDARD CONS TR UCTION SPECIF ICA TIO DOCUMENTS
Revision : &!23/2021
00 72 00 -1
GENERAL CON DITI ONS
Page 24 of 63
G. City Substitute Reimbursement: Costs (savings or charges) attributable to acceptance of a substitute
sha ll be incorporated to the Contract by Change Order.
H. Tim e Extensions: No additional time will be granted for substitutions.
6.06 Concerning Subcontractors , Suppliers , and Others
A. Contractor shall perform with his own organization, work of a value not less than 35% of the
value embraced on the Contract, unless otherwise approved by the City .
B. Contractor shall not employ any Subcontractor, Supplier, or other individual or entity, whether
initially or as a replacement, against whom City may have reasonable objection. Contractor shall
not be required to employ any Subcontractor, Supplier, or other individual or entity to furnish or
perform any of the Work against whom Contractor has reasonable objection ( excluding those
acceptable to City as indicated in Paragraph 6.06.C).
C . The City may from time to time require the use of certain Subcontractors , Suppliers, or other
individuals or entities on the project, and will provide such requirements in the Supplementary
Conditions.
D. Minority Busine s s Enterpris e Compliance: It is City policy to ensure the full and equitable
participation by Minority Business Enterprises (MB E ) in the procurement of goods and services
on a contractual basis . If the Contract Documents provide for a MBE goa l, Contractor is required
to comply with the intent of the City 's MBE Ordinance (as amended) by the following:
1. Contractor shall, upon request by City, provide complete and accurate information regarding
actual work performed by a MBE on the Contract and payment therefor.
2. Contractor will not make additions, deletions , or substitutions of accepted MBE without
writte n consent of the City . Any unjustified change or deletion shall be a material breach of
Contract and may result in debarment in accordance with the procedures outlined in the
Ordinance .
3. Contractor shall, upon request by City, allow an audit and/or examination of any books, records,
or files in the possession of the Contractor that will substantiate the actual work performed by
an MBE. Material misrepresentation of any nature will be grounds for termination of the
Contract in accordance with Paragraph 15.02 .A . Any such misrepresentation may be grounds
for disqualification of Contractor to bid on future contracts with the City for a period of
not less than three years .
E . Contractor shall be fully responsible to City for all acts and omissions of the Subcontractors ,
Suppliers, and other individuals or entities performing or furnishing any of the Work just as
Contractor is responsible for Contractor's own acts and omissions . Nothing in the Contract
Documents:
CITY OF FORT WORTH
ST AND ARD CONST RUCTION SPEC IFICA TI ON DOC UM EN TS
Rev ision : &'23/Xl2 I
00 72 00 -1
GENERAL CO NDITIONS
P age 2 5 of 63
1. shall create for the benefit of any such Subcontractor, Supplier, or other individual or entity
any contractual relationship between City and any such Subcontractor, Supplier or other
individual or entity ; nor
2. shall create any obligation on the part of City to pay or to see to the payment of any moneys
due any such Subcontractor, Supp lier, or other individual or entity except as may otherwise be
required by Laws and Regulations .
F. Contractor shall be so le ly responsible for scheduling and coordinating the Work of Subcontractors ,
Suppliers , and other individuals or entities performing or furnishing any of the Work under a direct
or indirect contract w ith Contractor.
G. All Subcontractors, Suppliers, and such other individuals or entities performing or furnishing any
of the Work sha ll communicate with City through Contractor.
H. All Work performed for Contractor by a Subcontractor or Supplier will be pursuant to an
appropriate agreement between Contractor and the Subcontractor or Supp lier which specifica ll y
binds the Subcontractor or Supplier to the applicable terms and conditions of the Contract
Documents for the benefit of City .
6.07 Wage Rates
A. Duty to pay Prevailing Wage Rates. The Contractor shall comply with all requirements of
Chapter 2258, Texas Government Code (as amended), including the payment of not less than the
rates determined by the City Council of the City of Fort Worth to be the prevailing wage rates in
accordance with Chapter 2258. Such prevailing wage rates are included in these Contract
Documents.
B. Penalty for Violation. A Contractor or any Subcontractor who does not pay the prevailing wage
shall, upon demand made by the City, pay to the City $60 for each worker employed for each
calendar day or part of the day that the worker is paid less than the prevailing wage rates stipulated
in these contract documents. This penalty shall be retained by the City to offset its administrat iv e
costs , pursuant to Texas Government Code 2258.023.
C . Complaints of Violations and City Determination of Good Cause. On receipt of information,
including a complaint by a worker, concerning an alleged violation of 2258 .023, Texas
Government Code , by a Contractor or Subcontractor, the City shall make an initial
determination , before the 31st day after the date the City receives the information, as to whether
good cause exists to believe that the vio lation occurred. The City shall notify in writing the
Contractor or Subcontractor and any affected worker of its initial determination . Upon the City 's
determination that there is good cause to believe the Contractor or Subcontractor has violated
Chapter 2258, the City shall retain the full amounts claimed by the claimant or claimants as the
difference between wages paid and wages due under the prevailing wage rates , such amounts being
subtracted from successive progres s payments pending a fmal determination of the vio lation .
C ITY OF FORT WORTH
STANDARD CONST RUCTION SPEC IFICATION DOCUMENTS
Revi sion : 8/23/2021
00 7200 -1
GENERAL CONDITIONS
P age 26 of 6 3
D. Arbitration Required if Violation Not Resolved. An issue relating to an alleged violation of Section
2258.023, Texas Government Code, including a penalty owed to the City or an affected worker,
shall be submitted to binding arbitration in accordance with the Texas General Arbitration Act
(Article 224 et seq., Revised Statutes) if the Contractor or Subcontractor and any affected worker
does not resolve the issue by agreement before the 15th day after the date the City makes its initial
determination pursuant to Paragraph C above. If the persons required to arbitrate under this
section do not agree on an arbitrator before the 11th day after the date that arbitration is required,
a district court shall appoint an arbitrator on the petition of any of the persons. The City is not a
party in the arbitration. The decision and award of the arbitrator is final and binding on all parties
and may be enforced in any court of competent jurisdiction.
E. Records to be Maintained. The Contractor and each Subcontractor shall, for a period of three (3)
years following the date of acceptance of the work, maintain records that show (i) the name and
occupation of each worker employed by the Contractor in the construction of the Work provided
for in this Contract; and (ii) the actual per diem wages paid to each worker. The records shall be
open at all reasonable hours for inspection by the City. The provisions of Paragraph 6 .23 , Right
to Audit , shall pertain to this inspection .
F. Progress Payments. With each progress payment or payroll period , whichever is less, the
Contractor shall submit an affidavit stating that the Contractor has complied with the requirements
of Chapter 2258, Texas Government Code.
G. Posting of Wage Rates . The Contractor shall post prevailing wage rates in a conspicuous place at
all times.
H . Subcontractor Compliance. The Contractor shall include in its subcontracts and/or shall
otherwise require all of its Subcontractors to comply with Paragraphs A through G above .
6.08 Patent Fees and Royalties
A. Contractor shall pay all license fees and royalties and assume all costs incident to the use in the
performance of the Work or the incorporation in the Work of any invention , design , process,
product, or device which is the subject of patent rights or copyrights held by others. If a particular
invention, design , process , product, or device is specified in the Contract Documents for use in the
performance of the Work and if, to the actual knowledge of City, its use is subject to patent rights
or copyrights calling for the payment of any license fee or royalty to others, the existence of such
rights shall be disclosed by City in the Contract Documents. Failure of the City to disclose such
information does not relieve the Contractor from its obligations to pay for the use of said fees or
royalties to others.
B. To the fullest extent permitted by Laws and Regulations, Contractor shall indemnify and hold
harmless City,from and against all claims, costs, losses, and damages (including but not limited
to all fees and charges of engineers, architects, attorneys, and other professionals and all court
or arbitration or other dispute resolution costs) arising out of or relating to any infringement of
patent rights or copyrights incident to the use in the performance of the Work or resultingfrom
CITY OF FORT WORTH
ST AND ARD CONS T RUC TIO N SPECIF !CA TIO N DOC UMENTS
Revision: &23/202 1
00 72 00-1
GENERAL COND ITI ONS
Page 27 of 63
the incorporation in the Work of any invention , design, process, product, or device not specified
in th e Contract Do cumen ts.
6.09 Permits and Utilities
A. Contractor obtained permits and licenses. Contractor shall obtain and pay for all construction
permits and licen ses except tho se provided for in the Supplementary Conditions or Contract
Documents. City shall as s ist Contractor, when necessary, in obtaining such permits and licenses.
Contractor shall pay all governmental charge s and inspection fees necessary for the prosecution of
the Work which are applicable at the time of opening of Bids , or , if there are no Bids , on the
E ffective Date of the Agreement, except for permits provided by the City as specified in 6.09.B.
City shall pay all charges of utility owners for connections for providing permanent service to the
Work.
B. C ity obtained p ermits and lice nses. City will obtain and pay for all permits and licenses as provided
for in the Supplementary Conditions or Contract Documents. It will be the Contractor's
re sponsibility to carry out the provisions of the permit. If the Contractor initiates cha nge s to the
Contract and the City approves the changes, the Contractor is re spons ibl e for obtaining clearances
and coordinating with the appropriate regulatory agency. The City will not reimburse the
Contractor for any cost associated with these requirements of any City acquired permit. The
following are permits the City will obtain if required :
1. Texas Department of Transportation Permits
2. U.S. Army Corps of Engineers Permits
3 . Texas Commission on Environmental Quality Permits
4 . Railroad Company Permits
C. Outsta nding p ermits and licens es. The City anticipates acquisition of and/or access to p~rmits
and licenses. Any outstanding permits and licenses are anticipated to be acquired in accordance
with the schedule set forth in the Supplementary Conditions. The Project Schedule submitted by
the Contractor in accordance with the Contract Documents must consider any outstanding permits
and licenses.
6.10 Laws and R egulations
A. Contractor shall give all notices required by and shall comply with all Laws and R e gulations
applicable to the performance of the Work. Except where otherwise expressly required by
applicable Laws and Regulations, the City shall not be responsible for monitoring Contractor's
compliance with any Laws or Regulations.
B. If Contractor performs any Work knowing or having reason to know that it is contrary to Laws or
Regulations, Contractor shall bear all claims , costs , losses , and damages (including but not limited
to all fees and charges of engineers , architects , attorneys , and other professionals and a ll
CITY OF FORT WORTH
ST ANDARDCONSTRUC TIO N SPECIF ICA TIO N DOCUMENTS
Revi sion : &'23/202 1
00 72 00 -1
GENERAL CO NDITIONS
Page 28 of 63
court or arbitration or other dispute resolution costs) arising out of or relating to such Work.
However, it shall not be Contractor's responsibility to make certain that the Specifications and
Drawings are in accordance with Laws and Regulations, but this shall not relieve Contractor of
Contractor's obligations under Paragraph 3.02.
C. Changes in Laws or Regulations not known at the time of opening of Bids having an effect on
the cost or time of performance of the Work may be the subject of an adjustment in Contract Price
or Contract Time.
6 .11 Taxes
A. On a contract awarded by the City, an organization which qualifies for exemption pursuant to
Texas Tax Code , Subchapter H, Sections 151.301-335 (as amended), the Contractor may purchase,
rent or lease all materials , supplies and equipment used or consumed in the performance of this
contract by issuing to his supplier an exemption certificate in lieu of the tax, said exemption
certificate to comply with State Comptroller's Ruling .007. Any such exemption certificate issued
to the Contractor in lieu of the tax shall be subject to and shall comply with the provision of State
Comptroller 's Ruling .011 , and any other applicable rulings pertaining to the Texas Tax Code ,
Subchapter H .
B . Texas Tax permits and information may be obtained from:
1. Comptroller of Public Accounts
Sales Tax Division
Capitol Station
Austin, TX 78711; or
2 . http://www. window. state. tx. us/taxinfo/taxf orms/93-forms . html
6.12 Use of Site and Other Areas
A . Limitation on Use of Site and Other Areas:
1. Contractor shall confine construction equipment, the storage of materials and equipment, and
the operations of workers to the Site and other areas permitted by Laws and Regulations, and
shall not unreasonably encumber the Site and other areas with construction equipment or other
materials or equipment. Contractor shall assume full responsibility for any damage to any such
land or area, or to the owner or occupant thereof, or of any adjacent land or areas resulting
from the performance of the Work.
2. At any time when, in the judgment of the City, the Contractor has obstructed or closed or is
carrying on operations in a portion of a street, right-of-way, or easement greater than is
necessary for proper execution of the Work, the City may require the Contractor to finish the
section on which operations are in progress before work is commenced on any additiona l
area of the Site.
CITY OF FORT WORTH
ST AND ARD CONS TR UC TIO N SPEC IF ICA TIO N DOC UMEN T S
Revi sion : 8/23/202 1
00 72 00-1
GENERAL COND ITI ONS
Page 29 of 63
3. Shou ld any Damage Claim be made by any such owner or occupant because of the performance
of the Work, Contractor shall promptly attempt t o resolve the Damage C laim.
4. Pursuant to Paragraph 6. 2 1, Contractor s hall indemnify and hold harmless City, from and
aga in st all claims, costs, losses, and damages arising out of or relating to any claim or action,
legal or eq uitable, brought by any such owner or occupant against City.
B . Remova l of Debris During Performance of the Work: During the progre ss of the Work
Contractor sha ll keep the Site and other areas free from accwnulations of waste materials , rubbish ,
and other debris . Removal and disposal of such waste mate rials , rubbish, and other de bris shall
conform to applicable Laws and Regulations.
C. Site Maintenance Cleaning : 24 hours after written notice is given to the Contractor that the
clean-up on the job site is proceeding in a manner unsatisfactory to the City, if the Contractor fails
to correct the unsatisfactory procedure , the City may take s uch direct action as the City deems
appropriate to correct the clean-up deficiencies cited to the Contractor in the written notice
(by letter or electronic communication), and the costs of s uch direct action , plus 25 % of such
costs , shall be deducted from the monies due or to become due to the Contractor.
D. Final Site Cleaning: Prior to Final Acceptance of the Work Contractor shall clean the Site and
the Work and make it ready for utilizatio n by City or adjacent prope rty owner. At the completion
of the Work Contractor sha ll remove from the Site all tools, appliances , construction equipment
and machinery, and surplus materials a nd shall restore to original condition or better all property
disturbe d by the Work.
E. Loading Structures : Contractor shall not load nor p ermit any part of any structure to be loaded
in any manner that will endanger the structure , nor shall Contractor subject any part of the Work
or adjacent property to stresses or press ures that will endanger it.
6.13 Reco rd Docume nts
A . Contractor shall maintain in a safe place at the Site or in a place designated by the Contractor and
approved by the City, one (1) record copy of all Drawings, Specifications , Addenda, Change
Orde rs , Field Orders, and written interpretations and clarifications in good order and annotated to
show changes made during construction. T hese record docwnents together with all approved
Samples and a counterpart of all accepted Submittals will be available to City for reference. Upon
completion of the Work, these record documents , any operation and maintenance manuals , and
Submittals will be delivered to City prior to F inal Inspection. Contractor shall include accurate
lo cations for buried and imbedded items.
6.14 Safety and Protectio n
A. Contractor shall be so le ly responsible for initiating , maintallllllg and supervISmg all safety
precautions a nd programs in connection with the Work. Such responsibility does not relieve
Subcontractors of their re sponsibility for the safety of persons or property in the performance of
their work, nor for compliance with app lic able safety Laws and Regulations. Contractor shall
CITY OF FORT WORTH
ST AND ARD CONSTRUCTION SPECIF ICA TIO DOCUMENTS
Revision: ~I
00 72 00-1
GENERAL CON DITI ONS
P age 30 of 63
take all necessary precautions for the safety of, and s hall prov id e the necessary protection to
prevent damage, injury or loss to:
1. all persons on the Site or who may be affected by the Work;
2. all the Work and materials and equipment to be incorporated therein , whether in storage on
or off the Site; and
3. other property at the Site or adjacent thereto, including trees , shrubs , lawns, walks ,
pavements , roadways , structures , utilities , and Underground Facilities not designated for
removal, relocation , or replacement in the course of construction.
B. Contractor shall comply with all applicable Laws and Regulations relating to the safety of
persons or property, or to the protection of persons or property from damage , injur y, or loss; and
shall erect and maintain all necessary safeguards for such safety and protection. Contractor shall
notify owners of adjacent property and of Underground Facilities and other utility owners when
prosecution of the Work may affect them, and shall cooperate with them in the protection ,
removal, relocation , and replacement of their property.
C. Contractor shall comply with the applicable requirements of City 's safety programs , if any.
D. Contractor shall inform City of the specific requirements of Contractor 's safety program, if any ,
with which City 's employees and representatives must comply while at the Site.
E. All damage , injury, or loss to any property referred to in Paragraph 6.14 .A.2 or 6.14.A.3 caused,
directly or indirectly, in whole or in part, by Contractor, any Subcontractor, Supplier, or any other
individua 1 or entity directly or indirectly employed by any of them to perform any of the Work ,
or anyone for whose acts any of them may be liable , shall be remedied by Contractor.
F. Contractor 's duties and responsibilities for safety and for protection of the Work shall continue
until such time as all the Work is completed and City has accepted th~ Work.
6.15 Safety Repre se ntative
Contractor shall inform City in writing of Contractor's designated safety representative at the Site.
6.16 Ha zard Co mmunication Programs
Contractor shall be responsible for coordinating any exchange of material safety data sheets or other
hazard communication information required to be made available to or exchanged between or among
employers in accordance with Laws or Regulations.
6.17 Emergencies and/or Rectification
A. In emergencies affecting the safety or protection of persons or the Work or property at the Site or
adjacent thereto, Contractor is obligated to act to prevent threatened damage, injury , or los s .
Contractor shall give City prompt written notice if Contractor believes that any significant
C IT Y OF FORT WORTH
ST ANDARDCONSTRUCTION SPEC I FICATION DOCUMENTS
Revi sio n: &23al2 1
00 72 00-1
GENERAL COND ITI ONS
Page 3 1 of 63
changes in the Work or variations from the Contract Documents have been caused thereby or are
required as a result thereof. If City determines that a change in the Contract Docwnents is required
because of the action taken by Contractor in response to s uch an emergency, a Change Order may
be issued.
B . Should the Contractor fail to respond to a request from the City to rectify any discrepancies ,
omissions, or correction neces sary to conform with the requirements of the Contract Documents ,
the City shall give the Contractor written notice that such work or changes are to be performed.
The written notice shall direct attention to the discrepant condition and request the Contractor to
take remedial action to correct the condition . In the event the Contractor doe s not take positive
steps to fulfill this written request, or does not show just cause for not taking the proper action,
within 24 hours , the City may take such remedial action with City forces or by contract. The City
shall deduct an amount equal to the entire costs for such remedial action, plus 25%, from any
funds due or become due the Contractor on the Project.
6.18 Submittals
A. Contractor shall submit re quired Submittals to City for review and acceptance in accordance
with the accepted Schedule of Submittals (as required by Paragraph 2.07). Each submittal will be
identified as City may require.
1. Submit number of copies specified in the General Requirements.
2. Data shown on the Submittals will be complete with respectto quantities , dimension s, specified
performance and design criteria, materials, and similar data to show City the services,
materials , and equipment Contractor proposes to provide and to enable City to review the
information for the limited purpo ses required by Paragraph 6.18.C.
3. Submittals submitted as herein provided by Contractor and reviewed by City for
conformanc~ with the design concept shall be executed in conformity with the Contract
Documents unless otherwise required by City.
4. When Submittals are submitted for the purpose of showing the installation in greater detail ,
their review shall not excuse Contractor from requirements shown on the Drawings and
Specifications.
5. For-Information-Only submittals upon which the City is not expected to conduct review or
take responsive action may be so identified in the Contract Documents.
6 . Submit required nwnber of Samples specified in the Specifications.
7 . Clearly identify each Sample as to material, Supplier, pertinent data such as catalog numbers,
the use for which intended and other data as City may require to enable City to review the
submittal for the limited purposes required by Paragraph 6.18.C.
CITY OF FO RT WORTH
STANDARD C0NSTRUC TI0 N SPECIFICATION DOCUMENTS
Revision : &'23/2021
00 72 00-1
GENERAL CO NDITIONS
P age 32 of 63
B. Where a Submittal is required by the Contract Documents or the Schedule of Submittals , any
related Work performed prior to City's review and acceptance of the pertinent submittal will be
at the sole expense and responsibility of Contractor.
C . City 's Review:
1. City will provide timely review of required Submittals in accordance with the Schedule of
Submittals acceptable to City. City 's review and acceptance will be only to determine if the
items covered by the submittals will , after installation or incorporation in the Work, conform
to the information given in the Contract Documents and be compatible with the de s ign concept
of the completed Project as a functioning whole as indicated by the Contract Documents.
2. City's review and acceptance will not extend to means , methods , techniques, sequences, or
procedures of construction ( except where a particular means, method, technique , sequence ,
or procedure of construction is specifically and expressly called for by the Contract
Documents) or to safety precautions or programs incident thereto. The review and acceptance
of a separate item as such will not indicate approval of the assembly in which the item
functions .
3. City 's review and acceptance shall not relieve Contractor from responsibility for any
variation from the requirements of the Contract Docwnents unless Contractor has complied
with the requirements of Section 0 1 33 00 and City has given written acceptance of each
such variation by specific written notation thereof incorporated in or accompanying the
Submittal. City's review and acceptance shall not relieve Contractor from responsibility for
complying with the requirements of the Contract Documents.
6 .19 Continuing the Work
Exce pt as otherwise provided , Contractor shall carry on the Work and adhere to the Project Schedule
during all disputes or disagreements with City. No Work shall be delayed or postponed pending
resolution of any disputes or disagreements , except as City and Contractor may otherwise agree in
writing.
6.20 Co ntractor 's General Warranty and Guarantee
A. Contractor warrants and guarantees to City that all Work will be in accordance with the Contract
Documents and will not be defective . City and its officers, directors , members , partners ,
employees, agents, consultants, and subcontractors shall be entitled to rely on representation of
Contractor's warranty and guarantee .
B. Contractor's warranty and guarantee hereunder excludes defects or damage caused by :
1. abuse, modification, or improper maintenance or operation by persons other than Contractor,
Subcontractors, Suppliers, or any other individual or entity for whom Contractor is
responsible ; or
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIF ICA TIO N DO CUMENTS
Revision : &1231:ml
2 . norma l wear and tear under norma l us age.
00 72 0 0 -1
GENERAL COND ITI ON S
Page 33 of 63
C. Contractor 's ob ligation to perform a nd comp lete the Work in accorda nce w ith the Contrac t
D oc um e nts sha ll be a bso lute. None of the fo llow ing w ill const it ute a n accepta nce of Work tha t is
not in accordance w ith t he Contract D ocume nts or a re lease of Contractor 's obligat ion to perform
the Wo rk in accorda nce w ith th e Contract D oc um ents :
1. obse rvations by City;
2. recomm e nd ation or payme nt by City of a ny progress or fin a l payme nt ;
3. the iss ua nce of a certificate of F in a l Acce ptance by City or a ny p ayme nt re lated the ret o by
City;
4. use or occ upancy of the W ork or a ny pa rt th e reof by City;
5. a ny rev iew a nd accepta nce of a Submitta l by City;
6. a ny inspec ti on, tes t, or approva l by othe r s; or
7 . a ny corr ec ti on of defective W ork by City .
D . The Contrac tor sha ll re m edy a ny defects or da mages in the Wo rk a nd p ay fo r a ny da mage to
other wor k or property res ultin g the refrom whj c h s ha ll appear w ithin a period of two (2) year s
fro m the date of F in a l Accepta nce of th e Work unl ess a longer p e riod is spec ifie d a nd s ha ll furnis h
a goo d a nd s ufficie nt ma inte na nce bond, comp ly in g w ith th e re qu ireme nts of Article
5.02.B . T he C ity w ill give notice of o bse rve d defect s w ith reasona ble p romptness .
6.2 1 I ndemnification
A. Contractor covenants and agrees to indemnify, hold harml es s and defend, at its own
expe nse , the City, its officers , se rvants and e mplo ye es , from and again s t an y and all clai~
ari s ing out of, or alleged to arise out of, the work and s ervices to be pe rformed by the
Contractor, it s officers , agents, e mplo yees , s ubcontractors , licen ses or in v itees under this
Contract. THIS INDEMNTFTCATTQN PRQVTSTQN IS SPECIFICALLY INTENDED IQ
OPERATE AND BE EFFECTIVE EYEN IF IT IS ALLEGED QB PBQYEN THAT ALL
QB SOME QF THE DAMAGES BEING SQJJGHT WEBE CAUSED, IN WHQLE QB IN
PART, BY ANY ACT, OMISSION QB NEGLIGENCE QF THE CITY. This indemnity
pro v is ion is intended to include, without limitation, indemnity for co s ts ,e x pen s e s and legal
fee s incurred by th e City in defendin g again s t such claim s and causes of actions .
B. Contractor covenants and agrees to indemnify and hold harml e ss , at its own e x pen se, the City,
its officers, servants and employees, from and against an y and all los s, damage or destruction
of property of the City, ari s ing out of, or alleged to ari s e out of, the work and services to be
performed by the Contractor, its officers , ag e nts, employees , subcontractors , licensees or
in v ite e s und e r this Contract. THIS TNDEMNTFTCATTQN PRQVTSTQN TS
CITY OF FORT WOR TH
STANDARD C0NSTRUC TI0 N SPECIF ICAT ION DOCUMENTS
Revi sion: &'23/202 1
007200 -1
GENERAL COND ITI ONS
P age 34 of 63
SPECIFICALLY INTENDED TQ OPERATE AND BE EFFECTIVE EVEN IF TT JS
ALLEGED QR PROVEN THAT ALL QR SOME QF THE DAMAGES BEING SOUGHT
WERE CAUSED, TN WHOLE QR TN PART, BY ANY ACT, QMTSSJQN QR
NEGLIGENCE QF THE CITY,
6.22 D e legation of Profe ssional D e sign Services
A. Contractor will not be required to provide professional design services unless such services are
specifically required by the Contract Doc urnents for a portion of the Work or unless such services
are required to carryout Contractor's responsibilities for construction means , methods , techniques ,
sequences and procedures.
B. If professional design service s or certifications by a design professional related to systems,
materials or equipment are specifically required of Contractor by the Contract Documents , City
will specify all performance and design criteria that such services must satisfy . Contractor shall
cause such services or certifications to be provided by a properly licensed professional, who s e
signature and seal shall appear on all drawings , calculations , specifications , certifications , and
Submittals prepared by such professional. Submittals related to the Work designed or certified by
such professional, if prepared by others , shall bear such professional's written approval when
submitted to City.
C. City shall be entitled to rely upon the adequacy, accuracy and completeness of the services ,
certifications or approvals performed by such design professionals , provided City has specified
to Contractor performance and design criteria that such services must satisfy.
D. Pursuant to this Paragraph 6.22, City 's review and acceptance of design calcu lations and design
drawings will be only for the limited purpose of checking for conformance with performance and
design criteria given and the design concept expressed in the Contract Documents. City 's review
and acceptance of Submittals (except design calculations and design drawings) will be only for
the purpose stated in Paragraph 6 .18. C .
6.23 Right to Audit
A. The Contractor agrees that the City shall, until the expiration of three (3) years after final
payment under this Contract, have access to and the right to examine and photocopy any directly
pertinent books , documents , papers , and records of the Contractor involving transactions relating
to this Contract. Contractor agrees that the City shall have access during Regular Working Hours
to all necessary Contractor facilities and shall be provided adequate and appropriate work space
in order to conduct audits in compliance with the provisions of this Paragraph. The City shall
give Contractor reasonable advance notice of intended audits .
B. Contractor further agrees to include in all its subcontracts hereunder a provision to the effect that
the subcontractor agrees that the City shall, until the expiration of three (3) years after final
payment under this Contract, have access to and the right to examine and photocopy any directly
pertinent books , documents, papers , and records of such Subcontractor, involving transactions to
the subcontract, and further , that City shall have access during Regular Working Hours to all
C ITY OF FORT WORTH
ST AND ARD CONS TRUC TI ON SPEC IFICA TIO DOCUMENT S
Rev ision: &23/202 1
00 72 00-1
GENERAL CO NDITIONS
P age 35 of 6 3
Subcontractor facilities, and shall be provided adequate and appropriate work space in order to
conduct audits in compliance with the provisions of this Paragraph. The City shall give
Subcontractor reasonable advance notice of intended audits.
C. Contractor and Subcontractor agree to photocopy such documents as may be requested by the City.
The City agrees to reimburse Contractor for the cost of the copies as follows at the rate published
in the Texas Administrative Code in effect as of the time copying is performed.
6.24 Nondiscrimination
A . The City is responsible for operating Public Transportation Programs and implementing transit-
related projects , which are funded in part with Federal fmancial assistance awarded by the U.S.
Department of Transportation and the Federal Transit Administration (FTA), without
discriminating against any person in the United States on the basis of race,color, or national origin.
B. Title VI, Civil Rights Act of 1964 as amended: Contractor shall comply with the requirements of
the Act and the Regulations as further defined in the Supplementary Conditions for any project
receiving Federal assistance.
ARTICLE 7 -OTHER WORK AT THE SITE
7.01 Related Work at Site
A. City may perform other work related to the Project at the Site with City 's employees, or other
City contractors, or through other direct contracts therefor, or have other work performed by utility
owners. If such other work is not noted in the Contract Documents , then written notice thereof
will be given to Contractor prior to starting any such other work; and
B. Contractor shall afford each other contractor who is a party to such a direct contract, each utility
owner, and City , if City is performing other work with City's employees or other City contractors,
proper and safe access to the Site , provide a reasonable opportunity for the introduction and storage
of materials and equipment and the execution of such other work, and properly coordinate the
Work with theirs. Contractor shall do all cutting, fitting, and patching of the Work that may be
required to properly connect or otherwise make its several parts come together and properly
integrate with such other work. Contractor shall not endanger any work of others by cutting ,
excavating, or otherwise altering such work; provided, however, that Contractor may cut or alter
others' work with the written consent of City and the others whose work will be affected.
C . If the proper execution or results of any part of Contractor's Work depends upon work performed
by others under this Article 7, Contractor shall inspect such other work and promptly report to
City in writing any delays, defects, or deficiencies in such other work that render it unavailable
or unsuitable for the proper execution and results of Contractor's Work. Contractor's failure to so
report will constitute an acceptance of such other work as fit and proper for integration with
Contractor 's Work except for latent defects in the work provided by others.
CITY OF FORT WORTH
STANDARD CONSTR UC TIO N SPEC IF !CATION DOC UME NTS
Revi sion : &'2.3/Xl21
7.02 Coo rdin ation
00 72 00 -1
GENERAL COND IT IONS
Page 36 of 63
A. If City intends to contract with others for the performance of other work on the Project at th e
Site, the following will be set forth in Supplementary Conditions:
1. the individua I or entity who will have authority and re spons ibility for coordination of the
activities among the various contractors will be id entifie d;
2. the specific matters to be covered by such authority and re spons ibility will be itemized ; and
3. the exte nt of such authority and respons ibilities will be provide d.
B. Unless otherwise provided in the Supplementary Conditions, City s hall have authority for such
coordination.
ARTICLE 8 -CITY'S RESPONSIBILITIES
8.01 Communication s to Contractor
Except as otherwise provided in the Supplementary Conditions , City shall issue all communications
to Contractor.
8.02 Furnish Data
City shall timely furnish the data required under the Contract Documents .
8.03 Pay When Du e
City shall make payments to Contractor in accordance with Article 14.
8.04 Lands and Easements; Reports and Tests
City 's dutie s with respect to providing lands and easements and providing engineering surveys to
establish reference points are set forth in Paragraphs 4.01 and 4.05. Paragraph 4 .02 refers to City's
identifying and making available to Contractor copie s of reports of explorations and tests of subsurface
conditions and drawings of physical conditions relating to existing surface or subsurface structures at
or contiguous to the Site that have been utilized by City in preparing the Contract Documents.
8.05 Change Orders
City shall execute Change Orders in accordance with Paragraph 10.03.
8.06 In spections, Tests, and Approvals
City's responsibility with respect to certain inspections , tests , and approvals is set forth in Paragraph
13.03.
C!TYOF FORT WORTH
STANDARD C0NSTR UCTI0 N SPEC IFI CA TIO N DOC UMENTS
Revi sion: &23/202 1
8.07 Limitations on City 's Responsibilitie s
00 72 00 -1
GENERAL CO NDITI ONS
Page 37 of 63
A. The City shall not supervise, direct, or have control or authority over, nor be responsible for,
Contractor's means , methods , techniques , sequences , or procedures of construction, or the safety
precautions and programs incident thereto, or for any failure of Contractor to comply with Laws
and Regulations applicable to the performance of the Work. City will not be responsible for
Contractor's failure to perform the Work in accordance with the Contract Documents.
B . City will notify the Contractor of applicable safety plans pursuant to Paragraph 6.14.
8.08 Undisclosed Hazardous Environmental Condition
City's responsibility with respect to an undisclosed Hazardous Environmental Condition is set forth
in Paragraph 4.06 .
8.09 Complianc e with Safety Program
While at the Site , City 's employees and representatives shall comply with the specific applicable
requirements of Contractor's safety programs of which City has been informed pursuant to
Paragraph 6.14.
ARTICLE 9 -CITY'S OBSERVATION STATUS DURING CONSTRUCTION
9.01 C ity 's Project Manager
City will provide one or more Project Manager(s) during the construction period. The duties and
responsibilities and the limitations of authority of City's Project Manager during construction are set
forth in the Contract Documents. The City 's Project Manager for this Contract is identified in the
Supplementary Conditions.
9.02 Visits to Site
A . City 's Project Manager will make visits to the Site at intervals appropriate to the various stages
of construction as City deems necessary in order to observe the progress that has been made and
the quality of the various aspects of Contractor's executed Work. Based on information
obtained during such visits and observations, City 's Project Manager will determine , in general, if
the Work is proceeding in accordance with the Contract Documents. City 's Project Manager will
not be required to make exhaustive or continuous inspections on the Site to check the quality or
quantity of the Work. City 's Project Manager's efforts will be directed toward providing City a
greater degree of confidence that the completed Work will conform generally to the Contract
Documents.
B. City 's Project Manager's visits and observations are subject to all the limitations on authority and
responsibility in the Contract Documents including those set forth in Paragraph
8.07.
CITY OF FORT WORTH
ST AND ARD C0NSTRUC TI 0N SPEC IFICAT I0 DOCUMENT S
Re vision: &'23/202 1
9.03 Authorized Variations in Work
00 7200 -1
GENERAL CO NDITI ONS
P age 38 of 63
City 's Project Manager may authorize minor vanat1ons in the Work from the requirements of the
Contract Documents which do not involve an adjustment in the Contract Price or the Contract Time
and are compatible with the design concept of the completed Project as a functioning whole as
indicated by the Contract Documents. These may be accomplished by a Field Order and will be
binding on City and also on Contractor, who shall perform the Work involved promptly .
9.04 Rejecting Defective Work
City will have authority to reject Work which City's Project Manager believes to be defective , or will
not produce a completed Project that conforms to the Contract Documents or that will prejudice the
integrity of the design concept of the completed Project as a functioning whole as indicated by the
Contract Documents. City will have authority to conduct special inspection or testing of the Work as
provided in Article 13, whether or not the Work is fabricated, installed , or completed.
9.05 Determinations for Work Performed
Contractor will determine the actual quantities and classifications of Work performed. City's Project
Manager will review with Contractor the preliminary determinations on such matters before rendering
a written recommendation. City's written decision will be fmal ( except as modified to reflect changed
factual conditions or more accurate data).
9.06 Decisions on Requirements of Contract Documents and Acceptability of Work
A. City will be the initial interpreter of the requirements of the Contract Documents and judge of the
acceptability of the Work thereunder.
B. City will render a written decision on any issue referred.
C . City's written decision on the issue referred will be final and binding on the Contractor, subject
to the provisions of Paragraph 10.06 .
ARTICLE 10 -CHANGES IN THE WORK; CLAIMS; EXTRA WORK
10.01 Authorized Changes in the Work
A . Without invalidating the Contract and without notice to any surety, City may, at any time or from
time to time, order Extra Work. Upon notice of such Extra Work, Contractor shall promptly
proceed with the Work involved which will be performed under the applicable conditions of the
Contract Documents (except as otherwise specifically provided). Extra Work shall be
memorialized by a Change Order which may or may not precede an order of Extra work.
B . For minor changes of Work not requiring changes to Contract Time or Contract Price, a Field
Order may be issued by the City .
CITY OF FORT WORTH
STANDARD C0NSTR UCTI0 N SPEC IF ICA TIO N D OC UMEN TS
Revis ion: &23/Xl2 1
10 .02 Unauthorized Changes in the Work
00 72 00-I
GENERAL CONDITIONS
Page 39 of 63
Contractor s hall not be entitled to an increase in the Contract Price or an extension of the Contract
Time with respect to any work performed that is not required by the Contract Documents as amended,
modified, or supplemented as provided in Paragraph 3.04, except in the case of an emergency as
provided in Paragraph 6.17.
10.03 Execution of Change Orders
A. City and Contractor shall execute appropriate Change Orders covering:
1. changes in the Work which are: (i) ordered by City pursuant to Paragraph 10.01.A, (ii) required
because of acceptance of defective Work under Paragraph 13 .08 or City's correction of
defective Work under Paragraph 13.09, or (iii) agreed to by the parties ;
2. changes in the Contract Price or Contract Time which are agreed to by the parties , including
any undisputed sum or amount of time for Work actually performed.
10.04 Ex tra Work
A. Should a difference arise as to what does or does not constitute Extra Work, or as to the payment
thereof, and the City insists upon its performance, the Contractor shall proceed with the work after
making written request for written orders and shall keep accurate account of the actual reasonable
cost thereof. Contract Claims regarding Extra Work shall be made pursuant to Paragraph 10.06.
B. The Contractor shall furnish the City such installation records of all deviations from the original
Contract Documents as may be necessary to enable the City to prepare for permanent record a
corrected set of plans showing the actual installation.
C. The compensation agreed upon for Extra Work whether or not initiated by a Change Order shall
be a full , complete and final payment for all costs Contractor incurs as a result or relating to the
change or Extra Work, whether said costs are known, unknown, foreseen or unforeseen at that
time , including without limitation , any costs for delay , extended overhead, ripple or impact cost,
or any other effect on changed or unchanged work as a result of the change or Extra Work.
10 .05 Notification to Surety
If the provisions of any bond require notice to be given to a surety of any change affecting the general
scope of the Work or the provisions of the Contract Documents (including , but not limited to,
Contract Price or Contract Time), the giving of any such notice will be Contractor's responsibility.
The amount of each applicable bond will be adjusted by the Contractor to reflect the effect of any
such change .
C ITY OF F ORT WORTH
STANDARDCONSTRUC TIO N SPECIF I CATION DOCUMENTS
Revision : &'23/2021
10.06 Co ntract Claims Process
007200 -1
GENERAL CONDITIONS
Page 40 of 63
A . City 's Decision Requ ir ed: All Contract Claims, except those waived pursuant to Paragraph
14.09, shall be referred to the City for decision. A decision by City shall be required as a condition
precedent to any exercise by Contractor of any rights or reme dies he may otherwise have under
the Contract Documents or by Laws and Regulations in respect of such Contract Claims .
B. Notice:
1. Written notice stating the genera l nature of each Contract Claim shall be delivered by the
Contractor to City no later than 15 days after the start of the event giving rise thereto. The
responsibility to substantiate a Contract Claim s hall rest with the party making the Contract
Claim .
2. Notice of the amount or extent of the Contract C laim, with supporting data shall be delivered
to the City on or before 45 days from the start of the event giving rise thereto (unless the City
allows additional time for Contractor to submit additional or more accurate data in support of
such Contract Claim).
3. A Contract Claim for an adjustment in Contract Price shall be prepared in accordance with
the provisions of Paragraph 12 .01.
4. A Contract Claim for an adjustment in Contract Time shall be prepared in accordance w ith
the provisions of Paragraph 12.02.
5 . Each Contract Claim shall be accompanied by Contractor's written statement that the
adjustment claimed is the entire adjustment to which the Contractor believes it is entitled as a
result of said event.
6 . The City shall submit any response to the Contractor within 30 days after receipt of the
claimant's last submittal ( unless Contract allows additional time).
C. City's Action: City will review each Contract Claim and, within 30 days after receipt of the last
submitta l of the Contractor, if any, take one of the following actions in writing:
l. deny the Contract Claim in whole or in part;
2. approve the Contract Claim; or
3. notify the Contractor that the City is unable to resolve the Contract C laim if, in the City's
sole discretion, it would be inappropriate for the City to do so. For purposes of further
resolution of the Contract Claim, such notice shall be deemed a denial.
CITY OF FORT WORTH
ST AND ARD CONST RU CTIO SPECIF ICA TIO N DO CUMENTS
Revi sion: &'2312D21
00 72 00 -1
GENERAL CON DITION S
Page 4 1 of63
D. City 's written action under Paragraph 10 .06.C will be final and binding , unless City or
Contractor invoke the dispute resolution procedure set forth in Article 16 within 30 days of such
action or denial.
E. No Contract Claim for an adjustment in Contract Price or Contract Time will be valid if not
submitted in accordance with this Paragraph 10.06.
ARTICLE 11-COST OF THE WORK; ALLOWANCES; UNIT PRICE WORK; PLANS
QUANTITY MEASUREMENT
11.01 Cost of the Work
A . Costs Included: The term Cost of the Work means the sum of all costs, except those excluded in
Paragraph 11.01.B , necessarily incurred and paid by Contractor in the proper performance of the
Work. When the value of any Work covered by a Change Order, the costs to be reimbursed to
Contractor will be only those additional or incremental costs required because of the change in the
Work. Such costs shall not include any of the costs itemized in Paragraph 11.01.B , and shall
include but not be limited to the following items:
1. Payroll costs for employees in the direct employ of Contractor in the performance of the
Work under schedules of job classifications agreed upon by City and Contractor. Such
employees shall include, without limitation , superintendents , for e men, and other personnel
employed full time on the Work. Payroll costs for employees not employed full time on the
Work shall be apportioned on the basis of their time spent on the Work. Payroll costs shall
include;
a. salaries with a 55% markup, or
b. salaries and wages plus the cost of fringe be nefits, which s hall include social security
contributions , unemployment, excise, and payroll taxes , workers ' compensation, health
and retirement benefits , bonuses , sick leave, vacation and holiday pay applicable thereto.
The expenses of performing Work outside of Regular Working Hours, Weekend
Working Hours , or legal holidays , shall be included in the above to the extent authorized
by City.
2 . Cost of all materials and equipment furnished and incorporated in the Work, including costs
of transportation and storage thereof, and Suppliers ' field services required in connection
therewith.
3 . Rentals of all construction equipment and machinery, and the parts thereof whether rented
from Contractor or others in accordance with rental agreements approved by City, and the
costs of transportation , loading , unloading , assembly , dismantling , and removal thereof. All
such costs shall be in accordance with the terms of said rental agreements . The rental of any
such equipment, machinery, or parts shall cease when the use thereof is no longe r necessruy
for the Work.
CITY OF FORT WORTH
STA NDARDC0NSTR UCTI 0N SPECIF ICATI0 DOCUMENTS
Rev ision: &'23!202 1
00 7200-1
GENERAL COND IT IONS
Page 42 of 63
4. Payments made by Contractor to Subcontractors for Work performed by Sub contractors. If
required by City, Contractor sha ll o btain competitive bids from s ub contractors acceptable to
City and Contractor and sha ll deliver such bid s to City , who will then determin e, which bids,
if any, will be acceptable . If a ny subcontract provides that the Subcontractor is to be paid on
the basis of Cost of the Work plus a fee, the Subcontractor's Cost of the Work and fee sha ll
be determined in the same manner as Contractor's Cost of the Work and fee as provided m
this Paragraph 11.01.
5. Costs of spec ia l consultants (including but not limit ed to engineers, architects, testing
laboratorie s, surveyors , attorneys , and accountants) employed for serv ices specifically related
to the Work.
6. Supp lementa l costs including the fo llowing:
a . T he proportion of necessary transportation, travel, and subsistence expenses of
Contractor 's employees incurred in discharge of dutie s connected with the Work.
b. Cost, including transportation and mainte na nc e, of a ll materials , supplies , equipment,
machinery, applia nce s, office, and temporary facilities at the Site , and ha nd tools not
owned by the workers , which are consumed in the performance of the Work, and cost, less
market va lu e, of s uch items used but not consumed w hi ch remain the property of
Contractor.
c . Sa les, consumer, use , and other similar taxes related to the Work, and for which
Contractor is liable not covered under Paragraph 6.11 , as imposed by Laws and
Regulations.
d. Deposits lost for causes other than neglige nce of Contractor, any Subcontractor, or
anyone directly or indirectly emp loyed by any of them or for whose acts any of them ma y
be liable , and royalty payments and fees for permits and licenses.
e. Losses and damages (and related expenses) caused by damage to the Work, not
compensated by insurance or otherwise , sustained by Contractor in connection with the
performance of the Work, provided s uch losses a nd damages have res ulted from causes
other than the negligence of Contractor, any Subcontractor, or anyone directly or indirectly
employed by any of them or for whose acts any of them may be liable. Such losses sha ll
include sett lements made with the written consent and approva l of City. No such losse s,
damages , and expenses sha ll be included in the Cost of the Work for the purpose of
determining Contractor 's fee.
f. The costofutilities , fuel , and sanitary facilities atthe Site.
g. Minor expenses s uch as telegrams , long distance telephone calls, telephone and
communication services at the Site , express and courier services, and s imilar petty cash
items in connection with the Work.
CIT Y OF FORT WORTH
ST AND ARD CONST RUC TIO N SPECIF !CATION DOCUMENTS
Revisio n: &'.23/2021
00 72 00-1
GENERAL CONDITIONS
P age 43 of 63
h. The costs of premiums for all bonds and insurance Contractor is required by the Contract
Documents to purchase and maintain.
B. Costs Excluded: The term Cost of the Work shall not include any of the following items:
1. Payroll costs and other compensation of Contractor's officers, executives, principals (of
partnerships and sole proprietor s hips), ge neral managers, safety managers, e ngineers ,
architects, estimators, attorneys , auditors, accountants, purchasing and contracting agents,
expediters, timekeepers , clerks, and other personnel employed by Contractor, whether at the
Site or in Contractor's principal or branch office for general administration of the Work and
not specifically included in the agreed upon schedule of job classifications referred to in
Paragraph 11.01.A. l or specifically covered by Paragraph l 1.01.A.4, all of which are to be
considered administrative costs covered by the Contractor's fee.
2. Expe nses of Contractor's principal and branch offices other than Contractor's office at the
Site.
3. Any part of Contractor's capital expenses, including interest on Contractor's capita I
employed for the Work and charges against Contractor for delinquent payments.
4. Costs due to the negligence of Contractor, any Subcontractor, or anyone directly or indirectly
employed by any of them or for whose acts any of them may be liable , including but not
limited to , the correction of defective Work, disposal of materials or equipment wrongly
supplied, and making good any damage to property .
5. Other overhead or general expense costs of any kind.
C. Co ntractor 's Fee: When all the Work is performed on the basis of cost-plus, Contractor's fee
shall be determined as set forth in the Agreement. When the value of any Work covered by a
Change Order for an adjustment in Contract Price is determined on the basis of Cost of the
Work, Contractor's fee shall be determined as set forth in Paragraph 12.01 .C .
D . Documentation: Whenever the Cost of the Work for any purpose is to be determined pursuant to
Paragraphs 11.01.A and 11.01.B, Contractor will establish and maintain records thereof in
accordance with generally accepted accounting practices and submit in a form acceptable to City
an itemized cost breakdown together w ith supporting data.
11.02 Allowances
A. Specified A llowanc e: It is understood that Contractor has included in the Contract Price all
allowances so named in the Contract Documents and shall cause the Work so covered to be
performed for such sums and by such persons or entities as may be acceptab le to City.
B . Pre-bid Allowances:
1. Contractor agrees that:
CITY OF FORT WORTH
ST AND ARD CONSTRU CTIO SPECIF I CA TIO N DO CUMENTS
Revi sion : &'23/202 1
007200-1
GENERAL CON DITI ONS
P age 44 of 63
a. the pre-bid allowances include the cost to Contractor of materials and equipment required
by the allowances to be delivered at the Site , and all applicable taxes ; and
b. Contractor's costs for unloading and handling on the Site , labor , installation , overhead,
profit, and other expenses contemplated for the pre-bid allowances have been included in
the allowances, and no demand for additional payment on account of any of the
foregoing will be valid .
C. Contingency Allowance : Contractor agrees that a contingency allowance, if any, is for the sole use
of City.
D . Prior to final payment, an appropriate Change Order will be issued to reflect actual amounts due
Contractor on account of Work covered by allowances, and the Contract Price shall be
correspondingly adjusted .
11.03 Unit Price Work
A . Where the Contract Documents provide that all or part of the Work is to be Unit Price Work,
initially the Contract Price will be deemed to include for all Unit Price Work an amount equal to
the sum of the unit price for each separately identified item of Unit Price Work times the estimated
quantity of each item as indicated in the Agreement.
B. The estimated quantities of items of Unit Price Work are not guaranteed and are solely for the
purpose of comparison of Bids and determining an initial Contract Price. Determinations of the
actual quantities and classifications of Unit Price Work performed by Contractor will be made by
City subject to the provisions of Paragraph 9.05.
C. Each unit price will be deemed to include an amount considered by Contractor to be adequate to
cover Contractor's overhead and profit for each separately identified item . Work described in the
Contract Documents , or reasonably inferred as required for a functionally complete installation ,
but not identified in the listing of unit price items shall be considered incidental to unit price work
listed and the cost of incidental work included as part of the unit price .
D . City may make an adjustment in the Contract Price in accordance with Paragraph 12.01 if:
1. the quantity of any item of Unit Price Work performed by Contractor differs materially and
significantly from the estimated quantity of such item indicated in the Agreement; and
2. there is no corresponding adjustment with respect to any other item of Work.
E. In creased or Decreased Quantities: The City reserves the right to order Extra Work m
accordance with Paragraph 10.01.
1. If the changes in quantities or the alterations do not significantly change the character of
work under the Contract Documents, the altered work will be paid for at the Contract unit
pnce.
CITY OF FORT WORTH
ST AND ARD CONST RU CTIO SPECIF !CAT IO N DOC UMENTS
Revi sio n: &12312D21
00 72 00 -1
GENERAL CD NDITION S
Pag e 45 of 63
2. If the changes in quantities or alterations significantly change the character of work, the
Contract will be amended by a Change Order.
3. If no unit prices exist, this will be considered Extra Work and the Contract will be amended
by a Change Order in accordance with Article 12 .
4. A significant change in the character of work occurs when:
a. the character of work for any Item as altered differs materially in kind or nature from that
in the Contract or
b. a Major Item of work varies by more than 25% from the original Contract quantity.
5. When the quantity of work to be done under any Major Item of the Contract is more than
125% of the original quantity stated in the Contract, then either party to the Contract may
request an adjustment to the unit price on the portion of the work that is above 125%.
6. When the quantity of work to be done under any Major Item of the Contract is less than 75%
of the original quantity stated in the Contract, then either party to the Contract may request
an adju stment to the unit price.
11.04 Plans Quantity M easure ment
A. Plans quantities may or may not represent the exact quantity of work performed or material moved ,
handled, or placed during the execution of the Contract. The estimated bid quantities are
designated as final payment quantitie s, unless revised by the governing Section or this Article.
B. If the quantity measured as outlined under ''Price and Payment Procedures" varies by more than
25% (or as stipulated under ''Price and Payment Procedures" for specific Items) from the total
estimated quantity for an individual Item originally shown in the Contract Documents , an
adjustment may be made to the quantity of authorized work done for payment purposes. The party
to the Contract requesting the adjustment will provide field measurements and calculations
showing the fmal quantity for which payment will be made. Payment for revised quantity will be
made at the unit price bid for that Item, except as provided for in Article 10 .
C . When quantities are revised by a change in design approved by the City, by Change Order, or to
correct an error, or to correct an error on the plans, the plans quantity will be increased or decreased
by the amount involved in the change , and the 25% variance will apply to the new plans quantity.
D. If the total Contract quantity multiplied by the unit price bid for an individual Item is less than
$250 and the Item is not originally a plans quantity Item, then the Item may be paid as a plans
quantity Item if the City and Contractor agree in writing to fix the fmal quantity as a plans quantity .
C IT Y OF FORT WORTH
ST AND ARD CONST RU CTI ON SPECIF ICA TI O N DOCUMENTS
Revisio n: &123.,'Xl2 1
00 7200-1
GENERAL CONDIT IONS
Page 46 of 63
E. For callout work or non-site specific Contracts, the plans quantity measurement requirements are
not applicable.
ARTICLE 12 -CHANGE OF CONTRACT PRICE; CHANGE OF CONTRACT TIME
12.01 Cha nge of Contract Price
A. The Contract Price may only be changed by a Change Order.
B . The value of any Work covered by a Change Order will be determined as follows:
1. where the Work involved is covered by unit prices contained in the Contract Documents , by
application of such unit prices to the quantities of the items involved (subject to the provisions
of Paragraph 11.03); or
2. where the Work involved is not covered by unit prices contained in the Contract Documents ,
by a mutually agreed lump s um or unit price (which may include an allowance for overhead
and profit not necessarily in accordance with Paragraph 12 .01.C .2), and shall include the cost
of any secondary impacts that are foreseeable at the time of pricing the cost of Extra Work;
or
3 . where the Work involved is not covered by unit prices contained in the Contract Documents
and agreement to a lump sum or unit price is not reached und er Paragraph 12 .01.B.2, on the
basis of the Cost of the Work (determined as provided in Paragraph 11.01) plus a Contractor's
fee for overhead and profit (determined as provided in Paragraph 12.01.C).
C. Contractor's Fee: The Contractor's additional fee for overhead and profit shall be determined as
fo llows:
1. a mutually acceptable fixed fee; or
2. if a fixed fee is not agreed upon , then a fee based on the following percentage s of the various
portions of the Cost of the Work:
a . for costs incurred under Paragraphs 11.01.A. l, 11.01.A.2. and 11.01.A .3, the
Contractor 's additional fee shall be 15 percent except for:
1) rental fees for Contractor's own equipment using standard rental rates;
2) bonds and insurance ;
b. for costs incurred under Paragraph 11.01.A.4 and 11.01.A .5, the Contractor's fee shall be
five percent (5%);
CITYOF FORT WORTH
I) where one or more tiers of subcontracts are on the basis of Cost of the Work plus a
fee and no fixed fee is agreed upon, the intent of Paragraphs 12.01.C .2.a and
12.01.C.2.b is that the Subcontractor who actually performs the Work, at whatever
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revision: &'23/2021
00 72 00 -1
GENERAL CO NDITI ONS
Page 47 of63
tier, will be paid a fee of 15 percent of the costs incurred by such Subcontractor under
Paragraphs 11.01.A. l and 11.01.A.2 and that any higher tier Subcontractor and
Contractor will each be paid a fee of five percent (5 %) of the amount paid to the next
lower tier Subcontractor, however in no case shall the cumulative total of fees paid be
in excess of 25 %;
c. no fee shall be payable on the basis of costs itemized under Paragraphs 11 .01 .A .6, and
11.01.B;
d. the amount of credit to be allowed by Contractor to City for any change which results in
a net decrease in cost will be the amount of the actual net decrease in cost plus a deduction
in Contractor's fee by an amount equal to five percent (5%) of such net decrease.
12.02 Change of Contract Time
A. The Contract Time may only be changed by a Change Order.
B. No extension of the Contract Time will be allowed for Extra Work or for claimed delay unless the
E xtra Work contemplated or claimed delay is shown to be on the critical path of the Project
Schedule or Contractor can show by Critical Path Method analysis how the Extra Work or claimed
delay adversely affects the critical path.
12.03 Delays
A . Where Contractor is reasonably delayed in the performance or completion of any part of the
Work within the Contract Time due to delay beyond the control of Contractor, the Contract Time
may be extended in an amount equal to the time lost due to such delay if a Contract Claim is made
therefor. Delays beyond the control of Contractor shall include , but not be limited to , acts or
neglect by City, acts or neglect of utility owners or other contractors performing other work as
contemplated by Article 7, fires , floods , epidemics , abnormal weather conditions , or acts of God.
Such an adjustment shall be Contractor 's sole and exclusive remedy for the delays described in
this Paragraph.
B. If Contractor is delayed, City shall not be liable to Contractor for any claims , costs , losses, or
damages (including but not limited to all fees and charges of engineers , architects , attorneys , and
other professionals and all court or arbitration or other dispute resolution costs) sustained by
Contractor on or in connection with any other project or anticipated project.
C . Contractor shall not be entitled to an adjustment in Contract Price or Contract Time for delays
within the control of Contractor. Delays attributable to and within the control of a Subcontractor
or Supplier shall be deemed to be delays within the control of Contractor.
D. The Contractor shall receive no compensation for delays or hindrances to the Work, except when
direct and unavo idable extra cost to the Contractor is caused by the failure of the City to provide
information or material, if any, which is to be furnished by the City .
C ITY OF FOR T WORTH
STANDARD C0NS T RUCT IO SPEC I FI CATION D OCUMENTS
Revision: &!23/202 1
00 72 00 - I
GENERAL CO NDITI ON S
Page 48 of 63
ARTICLE 13 -TESTS AND INSPECTIONS; CORRECTION, REMOVAL OR ACCEPTANCE OF
DEFECTIVE WORK
13.01 Notice of Defects
Notice of all defective Work of which City has actual knowledge will be given to Contractor.
Defective Work may be rejected, corrected, or accepted as provided in this Article 13.
13.02 A cce ss to Work
City, independent testing laboratories , and governmental agencies with jurisdictional interests will
have access to the Site and the Work at reasonable tim es for their observation , inspection, and testing.
Contractor shall provide them proper and safe conditions for such access and advise them of
Contractor's safety procedures and programs so that th ey may comply therewith as applicable.
13 .0 3 Tests and In sp ection s
A . Contractor shall give City timely notice of readiness of the Work for all required inspections ,
tests , or approvals and shall cooperate with inspection and testing personnel to facilitate required
inspections or tests .
B. If Contract Docwnents , Laws or Regulations of any public body having jurisdiction require any
of the Work ( or part thereof) to be inspected, tested, or approved , Contractor shall assume full
responsibility for arranging and obtaining such independent inspections , te s ts , retests or approvals ,
pay all costs in connection therewith, and furnish City the required certificates of inspection or
approval; excepting, however, those fees specifically identified in the Supplementary Conditions
or any Texas Department of Licensure and Regulation (TDLR) inspections , which shall be paid as
described in the Supplementary Conditions.
C . Contractor shall be responsible for arranging and obtaining and shall pay all costs in connection
with any inspections, tests , re-tests , or approvals re quired for City's acceptance of materials or
equipment to be incorporated in the Work; or acceptance of materials, mix designs, or equipment
submitted for approval prior to Contractor 's purchase thereof for incorporation in the Work.
Such inspections , tests , re-tests , or approva ls shall be performed by organizations acceptable to
City.
D. City may arrange for the services of an independent testing laboratory ("Testing Lab") to
perform any inspections or tests ("Testing") for any part of the Work, as determined solely by
City.
1. City will coordinate such Testing to the extent possible , with Contractor ;
2 . Should any Testing under this Section 13 .03 D result in a "fail ", "did not pass" or other
similar negative result , the Contractor shall be responsible for paying for any and all retests.
Contractor's cancellation without cause of City initiated Testing shall be deemed a negative
result and require a retest.
C ITY OF FORT WORT H
ST ANDARD CONSTRUCTION SPEC IF ICA TI O N DOCUMENTS
Revis ion: &123/2J2 1
00 72 00-1
GE NERAL COND ITIONS
Page 49 of 63
3. Any amounts owed for any retest under this Section 13.03 D s hall be paid direc t ly to the
Testing Lab by Contractor. City w ill forward all inv oices for retests to Contractor.
4. If Contractor fails to pay th e Testing Lab, City will not issue F inal Payment until the Testing
Lab is pa id .
E . If any Work ( or the work of others) that is to be in specte d, tested, or approved is covered by
Contractor without written concurrence of City, Contractor shall, if requested by City , uncover
s uch Work for observation.
F. Uncovering Work as provided in Paragraph 13.03 .E s hall be at Contractor's expense.
G. Contractor shall have the right to make a Contract Claim regarding any rete st or invoice issued
under Section 13.03 D.
13.04 Uncove ring Work
A. If any Work is covered contrary to the Contract Doc uments or specific instructions by the City, it
must, if re quested by City, be uncovered for City's observation and replaced at Contractor's
expense .
B. If City considers it necessary or advisable that covered Work be observed by City or inspected or
tested by others, Contractor, at City's reque st , s hall uncover , expose, or otherwise make available
for observation, inspection, or testing as City ma y require , that portion of the Work in que stion ,
furnishing all necessary labor , materia~ and equipment.
1. If it is found that the uncovered Work is defective , Contractor shall pay all claims, costs,
lo sses, and damages (including but not limited to all fees and charges of engineers, architects,
attorneys , and other professiona ls and all court or other dispute re so lution costs) arising out of
or relating to such uncovering, exposure, observation, in spection, and testing, and of
satisfactory replacement or reconstruction (including but not limited to all costs of repair or
replacement of work of others); or City shall be entitled to accept defective Work in accordance
with Paragraph 13.08 in which case Contractor shall still be re s ponsible for all costs associated
with exposing, observing, and testing the defective Work.
2. If the uncove red Work is not found to be defective , Contractor shall be allowed an increa se
in the Contract Price or an extension of the Contract Time, or both, directly attributable to such
uncovering, exposure, observation, in spection, te sting , replacement, and reconstruction .
13.05 C ity May Stop the Work
If the Work is defective , or Contractor fails to supply sufficient skilled workers or suitab le materials
or equipment, or fails to perform the Work in such a way that the completed Work will conform to
the Contract Documents , City may order Contractor to stop the Work, or any portion thereof, until the
cause for such order ha s been eliminated; however, this right of City to stop the Work shall not give
ris e to any duty on the part of City to exercise this ri ght for the benefit of Contractor, any
CITY OF FORT WORTH
ST ANDARDCONSTRUCTION SPECIFICAT ION DOCUMENTS
Revi sion: &'23/202 1
00 7200-1
GENERAL CON DITI ONS
Page 50 of 63
Subcontractor, any Supplier, any other individual or entity , or any surety for , or employee or agent of
any of them.
13 .06 Co rrec tion or Re moval of D efe ctiv e Work
A. Promptly after receipt of written notice , Contractor s hall correct all defective Work pursuant to
an acceptable schedule, whether or not fabricated , in sta lled , or completed, or, if the Work ha s been
rejected by City, remove it from the Project and replace it w ith Work that is not defective.
Contractor sha ll pay all claims , costs , additional testing, losses, and damages (including but not
limited to all fees and charges of engineers, architects , attorneys, and other profess ionals and all
court or arbitration or other dispute resolution costs) arising out of or re lating to such correction
or removal (including but not limited to all costs of repair or replacement of work of others).
Failure to require the removal of a ny defective Work shall not constitute acceptance of s uch Work.
B . When correcting defective Work under the terms of this Paragraph 13.06 or Paragraph 13.07,
Contractor shall take no action that wou ld void or otherwise impair City's special warranty and
guarantee, if any , on said Work.
13 .07 Co rrection Period
A. If within two (2) years after the date of Final Acceptance (or s uch longer period of time as may be
prescribed by the te rms of any applicab le specia l guarantee required by the Contract Documents),
any Work is found to be defective , or if the repair of any damages to the land or areas made
available for Contractor 's use by City or permitted by Laws and Regulations as contemplated in
Paragraph 6.10.A is found to be defective , Contractor shall promptly, without cost to City and in
accordance with City's written in structions:
1. repair s uch defective land or areas; or
2. correct s uch defective Work; or
3 . if the defective Work has bee n rejected by City , remove it from the Project and replace it
with Work that is not defective , and
4. satisfactorily correct or repair or remove and replace any damage to other Work, to the work
of others or other land or areas resulting therefrom.
B. If Contractor does not promptly comply with the terms of City's written instructions , or in an
emergency where delay would cause serious risk of loss or damage , City may have the defective
Work corrected or repaired or may have the rejected Work removed and replaced. All claims ,
costs, lo sses, and damages (including but not limited to all fees and charges of engineers,
architects , attorneys, and other professionals and all court or other dispute reso luti on costs) arising
out of or relating to such correction or repair or such removal and replacement (including but not
limited to all costs of repair or replacement of work of others) will be paid by Contractor.
CITY OF FORT WORTH
STANDARDC0NSTRUCTI0N SPECIFICATION DOCUMENTS
Revis ion: &!23/202 1
00 72 00-1
GENERAL COND ITI ONS
Page 5 1 of63
C. In special circumstances where a particular item of equipment is placed in continuous service
before Final Acceptance of all the Work, the correction period for that it e m may start to run from
an earlier date if so provided in the Contract Docume nts.
D. Where defective Work (and damage to other Work resulting therefrom) has been corrected or
removed and replaced under this Paragraph 13 .07 , the correction period hereunder with respect
to such Work may be required to be extended for an additional period of one year after the end of
the initial correction period. City shall provide 30 days written notice to Contractor should such
additional warranty coverage be required. Contractor may dispute this requirement by filing a
Contract Claim, pursuant to Paragraph 10.06.
E. Contractor's obligations under this Paragraph 13.07 are in addition to any other obligation or
warranty. The provisions of this Paragraph 13.07 shall not be construed as a substitute for , or a
waiver of, the provisions of any applicable statute of limitation or repose .
13.08 Acceptance of Defective Work
If, instead of requiring correction or removal and replacement of defective Work, City prefers to
accept it , City may do so. Contractor shall pay all claims , costs, lo sses, and damages (including but
not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all
court or other dispute resolution costs) attributable to City's evaluation of and determination to accep:
s uch defective Work and for the diminished value of the Work to the extent not otherwise paid by
Contractor. If any such acceptance occurs prior to Final Acceptance, a Change Order will be issued
incorporating the necessary revisions in the Contract Documents with respect to the Work, and City
s hall be entitled to an appropriate decrease in the Contract Price , reflecting the diminished value of
Work so accepted.
13.09 City May Correc t Defec tive Work
A. If Contractor fails within a reasonable time after written notice from City to correct defective
Work, or to remove and replace rejected Work as r e quired by City in accordance with Paragraph
13.06.A, or if Contractor fails to perform the Work in accordance with the Contract Documents ,
or if Contractor fails to comply with any other provision of the Contract Documents , City may,
after seven (7) days written notice to Contractor, correct, or remedy any such deficiency.
B. In exercising the rights and remedies under this Paragraph 13.09, City shall proceed
expeditiously. In connection with such corrective or remedial action, City may exclude Contractor
from all or part of the Site , take possession of all or part of the Work and suspend Contractor's
services related thereto, and incorporate in the Work all materials and equipment incorporated in
the Work, stored at the Site or for which City has paid Contractor but which are stored elsewhere.
Contractor shall allow City, City's representatives , agents , consultants , employees, and City's
other contractors, access to the Site to enable City to exercise the rights and remedies under this
Paragraph.
C. All claims , costs , losses , and damages (including but not limited to all fees and charges of
engineers, architects, attorneys , and other professionals and all court or other dispute resolution
CITYOF FORT WORTH
ST AND ARD CONS TR U CT!O N SPECIF !CA TIO DOCUMENTS
Revision: &'23/202 1
00 72 00 -I
GENERAL CO NDITIONS
Page 52 of 63
costs) incurred or sustained by City in exercising the rights and remedies under this Paragraph
13.09 will be charged against Contractor, and a Change Order will be issued incorporating the
necessary revisions in the Contract Documents with respect to the Work; and City shall be entitled
to an appropriate decrease in the Contract Price.
D. Contractor shall not be allowed an extension of the Contract Time because of any delay in the
performance of the Work attributable to the exercise of City's ri ghts and remedies under this
Paragraph 13.09.
ARTICLE 14 -PAYMENTS TO CONTRACTOR AND COMPLETION
14 .01 ScheduleofValues
The Schedule of Values for lump sum contracts established as provided in Paragraph 2.07 will serve
as the basis for progress payments and will be incorporated into a form of Application for Payment
acceptable to City . Progress payments on account of Unit Price Work will be based on the number of
units completed.
14.02 Progress Payments
A. Applicationsfor Payments:
1. Contractor is responsible for providing all information as required to become a vendor of the
City.
2. At least 20 days before the date established in the General Requirements for each progress
payment, Contractor shall submit to City for review an Application for Payment filled out and
signed by Contractor covering the Work completed as of the date of the Application and
accompanied by such s upporting documentation as is required by the Contract Documents.
3. If payment is requested on the basis of materials and equipment not incorporated in the Work
but delivered and suitably stored at the Site or at another location agreed to in writing, the
Application for Payment shall also be accompanied by a bill of sale, invoice , or other
documentation warranting that City has received the materials and equipment free and clear of
all Liens and evidence that the materials and equipment are covered by appropriate insurance
or other arrangements to protect City's interest therein, all of which must be satisfactory to
City.
4. Beginning with the second Application for Payment, each Application shall include an affidavit
of Contractor stating that previous progress payments received on account of the Work have
been applied on account to discharge Contractor's legitimate obligations associated with prior
Applications for Payment.
5. The amount of retainage with respect to progress payments will be as described in
subsection C. unless otherwise stipulated in the Contract Documents.
CITY OF F ORT WORTH
STANDARD CONSTRUC TIO N SPEC IFIC A TIO N DOCUMENTS
Revis ion : &!23/2021
B. Revie w of Applications :
00 72 00 -1
GENERAL CO NDIT IONS
Page 53 of 63
1. City will, after receipt of each Application for Payment, either indicate in wntmg a
recommendation of payment or return the Application to Contractor indicating reasons for
refusing payment. In the latter case , Contractor may make the necessary corrections and
resubmit the Application.
2. City 's processing of any payment requested in an Application for Payment will be based on
City's observations of the executed Work, and on City's review of the Application for Payment
and the accompanying data and sc hed ul es , that to the best of City's knowledge:
a . the Work has progressed to the point indicated ;
b. the quality of the Work is generally in accordance with the Contract Documents (subject
to an eva lu ation of the Work as a functioning whole prior to or upon Fina l Acceptance, tre
resu lt s of any subsequent tests called for in the Contract Documents , a final determination
of quantities and c lassifications for Work performed under Paragraph 9.05, and a ny other
qualifications stated in the recommendation).
3 . Processing any such payment will not thereby be deemed to have represented that:
a . inspections made to check the quality or the quantity of the Work as it has been performed
have been exhaustive , extended to every aspect of the Work in progress , or involved
detailed inspections of the Work beyond the responsibilities specifically assigned to City
in the Contract Documents; or
b. there may not be other matters or issues between the parties that might entitle Contractor
to be paid additionally by City or entitle City to withhold payment to Contractor; or
c . Contractor has complied with Laws and Regulations applicable to Contractor's performance
of the Work.
4. City may refuse to process the whole or any part of any payment because of subsequently
discovered evidence or the results of s ub sequent inspections or tests, and revise or revoke
any s uch payment previously made, to such extent as may be necessary to protect City from
loss because:
a. the Work is defective or completed Work has been damaged by the Contractor or
subcontractors requiring correction or replacement;
b. discrepancies in quantities contained in previous appli cations for payment;
c. the Contract Price has been reduced by Change Orders ;
d. City ha s been required to correct defective Work or comp lete Work in accordance with
Paragraph 13 .09; or
CITY OF FORT WORTH
ST AND ARD CONST RUC TI ON SPEC IF !CATION DOCUMENTS
Revisio n: &l23/202 1
00 72 00-I
GENERAL CONDIT IONS
e. City has actual knowledge of the occurrence of any of the events enumerated in
Paragraph 15 .02.A.
C. Retainage:
Page 54 of 63
1. For contracts less than $400,000 at the time of execution, retainage shall be t e n percent
(10%).
2. For contracts greater than $400 ,000 at the tim e of execution, retainage shall be five percent
(5%).
D. Liquidated Damages. For each calendar day that any work shall remain uncompleted after the
time specified in the Contract Documents , the sum pe r da y specified in the Agreement will be
assessed against the monies due the Contractor, not as a penalty, but as damages suffered by the
City.
E. Payme nt: Contractor will be paid pursuant to the requirements of this Article 14 and payment
will become due in accordance with the Contract D oc uments.
F. Reduction in Pa y me nt:
1. City may refuse to make payment of the amount requested because:
a. Liens have been filed in connection with the Work, except where Contractor has delivered
a specific bond satisfactory to City to sec ure the satisfaction and discharge of such Liens;
b. there are other item s entitling City to a set-off against the amount recommended ; or
c. City has actual knowledge of the occurrence of any of the events enumerated in
Paragraphs 14.02.B.4.a through 14.02.B.4.e or Paragraph 15 .02 .A.
2. If City refuses to make payment of the amount requested, City will give Contractor written
notice stating the reasons for such action and pay Contractor any amount remaining after
deduction of the amount so withheld. City shall pay Contractor the amount so withheld, or any
adjustment thereto agreed to by City and Contractor, when Contractor remedies the reasons
for such action.
14 .03 Contractor '.s Warranty of Title
Contractor warrants and guarantees that title to all Work, materials , and equipment covered by any
Application for Payment, whether incorporated in the Project or not , will pass to City no later than the
time of payment free and clear of all Liens.
C ITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DO CUMENTS
Revision: &/23/202 1
14.04 Partial Utilization
00 72 00-1
GENERAL CONDITIONS
Page 55 of 63
A . Prior to Final Acceptance of all the Work, City may use or occupy any part of the Work which
has specifically been identified in the Contract Documents , or which City determines constitutes
a separately functioning and usable part of the Work that can be used for its intended purpose
without significant interference with Contractor's performance of the remainder of the Work. City
at any time may notify Contractor in writing to permit City to use or occupy any such part of the
Work which City determines to be ready for its intended use , subject to the foUowing conditions:
1. Contractor at any time may notify City in writing that Contractor considers any such part of
the Work ready for its intended use.
2. Within a reasonable time after notification as enumerated in Paragraph 14.05.A. l, City and
Contractor shall make an inspection of that part of the Work to determine its status of
completion. If City does not consider that part of the Work to be substantiaUy complete , City
will notify Contractor in writing giving the reasons therefor.
3. Partial Utilization will not constitute F inal Acceptance by City .
14.05 Final Insp e ction
A. Upon written notice from Contractor that the entire Work JS Substantially Complete m
accordance with the Contract Documents:
1. Within 10 days , City will schedule a Final Inspection with Contractor.
2. City will notify Contractor in writing of aU particulars in which this inspection reveals that
the Work is incomplete or defective ("Punch List Items"). Contractor shaU immediately take
such measures as are necessary to complete such Work or remedy such deficiencies.
B. No time charge will be made against the Contractor between said date of notification to the City
of Substantial Completion and the date of Final Inspection .
1. Should the City determine that the Work is not ready for Final Inspection, City will notify the
Contractor in writing of the reasons and Contract Time will resume.
2. Should the City concur that Substantial Completion has been achieved with the exception of
any Punch List Items, Contract Time will resume for the duration it takes for Contractor to
achieve Final Acceptance .
14.06 Fina/Acceptance
Upon completion by Contractor to City's satisfaction, of any additional Work identified in the Final
Inspection, City will issue to Contractor a letter of Final Acceptance .
CITY OF FORT WORTH
ST AND ARD CONST RUCTI ON SPECIF ICA TIO N DOCUMENT S
Revi sion : &'23/202 1
14.07 Final Payment
A. Applicationfor Payment:
00 72 00-I
GENERAL CO NDITIONS
Page 56 of 63
1. Upon Final Acceptance, and in the opinion of City, Contractor may make an application for
final payment following the procedure for progress payme nts in accordance with the
Contract Documents.
2. The final Application for Payment shall be accompanied (except as previous ly delivered) by:
a. all docume ntation called for in the Contract Documents , including but not limited to the
evidence of insurance required by Paragraph 5.03;
b. consent of the surety, if any, to final payment;
c . a list of all pending or released Damage Claims against City that Contractor beli eves are
unsettled ; and
d . affidavits of payments and complete and legally effective releases or waivers
(satisfactory to City) of all Lien rig hts arising out of or Liens ftled in connection with the
Work.
B. Payment Becomes Due:
1. After City's acceptance of the Application for Payment and accompanying documentation ,
requested by Contractor, les s previous payments made and any sum City is entitled ,
including but not limited to liquidated damages , will become due and payable.
2. After all Damage Claims have been resolved:
a. directly by the Contractor or;
b. Contractor provide s evidence that the Damage Claim has been reported to Contractor's
in s urance provider for resolution .
3. The making of the fmal payment by the City shall not relieve the Contractor of any
guarantee s or other requirements of the Contract Documents which specifically continue
thereafter.
14.08 Final Completion D e layed and Partial Retainage Release
A. If fmal completion of the Work is significantly delayed, and if City so confmns , City may, upon
receipt of Contractor 's fmal Application for Payment, and without terminating the Contract, make
payment of the balance due for that portion of the Work fully completed and accepted. If the
remaining balance to be held by City for Work not fully completed or corrected is les s than the
retainage stipulated in Paragraph 14.02.C, and if bonds have been furnished as required in
Paragraph 5.02, the written consent of the surety to the payment of the balance due for that
C ITYOF FORT WORTH
ST ANDARDCONSTRUCTION SPEC IFI CATION DO CUM ENTS
Revi sion : ~I
00 72 00-1
GENERAL COND ITI ONS
Page 57 of 63
portion of the Work fully completed and accepted s hall be submitted by Contractor to City with
the Application for such payment. Such payment s hall be made under the terms and conditions
governing final payment, except that it sha ll not constitute a waiver of Contract Claims.
B. Partial Retainage Release. For a Contract that provides for a separate vegetative establishment
and maintenance , and test and performance periods following the completion of all other
construction in the Contract Documents for all Work locations , th e City may release a portion of
the amount retaine d provided that all other work is completed as determined by the City. Before
the release , all submittals and final quantities must be completed and accepted for all other work.
An amount sufficient to ensure Contract compliance will be reta ined.
14.09 Waiver of Claims
The acceptance offmal payment will constitute a release of the City from all claims or liabilities
under the Contract for anything done or furnished or relating to the work under the Contract
Documents or any act or neglect of City related to or connected with the Contract.
ARTICLE 15-SUSPENSION OF WORK AND TERMINATION
15.01 CityMaySuspendWork
A. At any time and without cause, City may suspend the Work or any portion thereof by written
notice to Contractor and which may fix. the date on which Work will be resumed . Contractor sha ll
resume the Work on the date so fIXed. During temporary suspension of the Work covered by these
Contract Documents, for any reason, the City will make no extra payment for stand-by time of
construction equipment and/or construction crews.
B. Should the Contractor not be able to complete a portion of the Project due to causes beyond the
control of and without the fault or negligenc e of the Contractor, and should it be determined by
mutual consent of the Contractor and City that a solution to allow construction to proceed is not
available within a reasonable period of tim e, Contractor may request an extension in Contract
Time, directly attributable to any such suspension .
C. If it should become necessary to suspend the Work for an indefmite period, the Contractor shall
store all materials in such a manner that they will not obstruct or impede the public unnecessarily
nor become damaged in any way, and he shall take every precaution to prevent damage or
deterioration of the work performed; he shall provide suitab le drainage about the work, and erect
temporary structures where necessary.
D. Contractor may be reimbursed for the cost of movin g his equipment off the job and r eturning the
necessary equipment to the job when it is determined by the City that construction may be
resumed. Such reimbursement shall be based on actual cost to the Contractor of moving the
equipment and no profit will be allowed. Reimbursement may not be allowed if the equipment is
moved to another construction project for the City.
CITYOF FORT WORTH
STANDARDCONSTR UC TIO N SPEC IFICATIO N DOCUMENTS
Revi sio n: &'23/202 1
15.02 City May Terminate for Cause
00 7200-1
GENERAL CON DITI ONS
Page 58 of 63
A. The occurrence ofany one or more of the followin g events by way of example , but not of limitation,
may justify termination for cause:
1. Contractor's persistent failure to perform the Work in accordance with the Contract Documents
(including, but not limited to, failure to supply sufficient skilled workers or suitable materials
or equipment, failure to adhere to the Project Schedule established under Paragraph 2 .07 as
adjusted from time to time pursuant to Paragraph 6.04, or failure to adhere to the City's
Business Diversity Enterprise Ordinance #20020-12-201 lestablished under Paragraj:TI
6.06.D);
2. Contractor's disregard of Laws or Regulations of any public body having jurisdiction;
3. Contractor's repeated disregard of the authority of City; or
4. Contractor's violation in any substantial way of any provisions of the Contract Documents;
or
5. Contractor's failure to promptly make good any defect in materials or workmanship, or
defects of any nature , the correction of which has been directed in writing by the City; or
6. Substantia l indication that the Contractor has made an unauthorized assignment of the
Contract or any funds due therefrom for the benefit of any creditor or for any other purpose;
or
7. Substantial evidence that the Contractor has become insolvent or bankrupt, or otherwise
fmancially unable to carry on the Work satisfactorily; or
8. Contractor commences legal action in a collit of competent jurisdiction against the City .
B. If one or more of the events identified in Paragraph 15.02A. occur, City will provide written notice
to Contractor and Surety to arrange a conference w ith Contractor and Surety to address
Contractor's failure to perform the Work. Conference shall be held not later than 15 days , after
receipt of notice.
1. If the City, the Contractor, and the Surety do not agree to allow the Contractor to proceed to
perform the construction Contract, the City may, to the extent permitted by Laws and
Regulations, declare a Contractor default and formally terminate the Contractor's right to
complete the Contract. Contractor default shall not be declared earlier than 20 days after the
Contractor and Surety have received notice of conference to address Contractor's failure to
perform the Work.
2. If Contractor's services are terminated, Surety shall be obligated to take over and perform the
Work. If Surety does not commence performance thereof within 15 consecutive calendar days
after date of an additional written notice demanding Surety's performance of its
CITY OF FORT WOR TH
ST ANDARD CONSTRUC TIO N SPEC IFI CA TIO N DOC UM EN TS
Revi si on &Q.3/202 1
00 72 00-1
GENERAL CONDITIONS
Pag e 59 of 63
obligations , then City , without process or action at law , may take over any portion of the
Work and complete it as described below_
a. If City completes the Work, City may exclude Contractor and Surety from the site and
take possession of the Work, and all materials and equipment incorporated into the Work
stored at the Site or for which City has paid Contractor or Surety but which are stored
elsewhere , and finish the Work as City may deem expedient.
3. Whether City or Surety completes the Work, Contractor shall not be entitled to receive any
further payment until the Work is finished. If the unpaid balance of the Contract Price exceeds
all claims , costs , losses and damages sustained by City arising out of or resulting from
completing the Work, such excess will be paid to Contractor. If such claims , costs , losses and
damages exceed such unpaid balance , Contractor shall pay the difference to City. Such claims,
costs, losses and damages incurred by City will be incorporated in a Change Order, provided
that when exercising any rights or remedies under this Paragraph, City shall not be required to
obtain the lowest price for the Work performed.
4. Neither City, nor any of its respective consultants , agents , officers, directors or employees
shall be in any way liable or accountable to Contractor or Surety for the method by which the
completion of the said Work, or any portion thereof, may be accomplished or for the price paid
therefor.
5. City, notwithstanding the method used in completing the Contract, shall not forfeit the right
to recover damages from Contractor or Surety for Contractor's failure to timely complete the
entire Contract. Contractor shall not be entitled to any claim on account of the method used
by City in completing the Contract.
6. Maintenance of the Work shall continue to be Contractor's and Surety's responsibilities as
provided for in the bond requirem~nts of the Contract Documents or any special guarantees
provided for under the Contract Documents or any other obligations otherwise prescribed by
law.
C. Notwithstanding Paragraphs 15.02.B, Contractor's services will not be terminated if Contractor
begins within seven days of receipt of notice of intent to terminate to correct its failure to perform
and proceeds diligently to cure such failure within no more than 30 days of receipt of said notice.
D. Where Contractor's services have been so terminated by City, the termination will not affect any
rights or remedies of City against Contractor then existing or which may thereafter accrue . Any
retention or payment of moneys due Contractor by City will not release Contractor from liability.
E. If and to the extent that Contractor has provided a performance bond under the provisions of
Paragraph 5.02 , the termination procedures of that bond shall not supersede the provisions of this
Article.
CITY OF FORT WORTH
STANDARD CONSTR UCTIO N SPEC IFI CA TIO DOC UM ENTS
Revision : &12.31])21
00 72 00 -1
GENERAL CONDITION S
Page 60 of 63
15.03 City May Terminate For Convenience
A. City may, without cause and without prejudice to any other right or remedy of City, terminate the
Contract. Any termination shall be effected by mailing a notice of the termination to the Contractor
specifying the extent to which performance of Work under the contract is terminated, and the date
upon which such termination becomes effective. Receipt of the notice shall be deemed
conclusively presumed and established when the letter is placed in the United States Postal Service
Mail by the City. Further, it shall be deemed conclusively presumed and established that such
termination is made with just cause as therein stated; and no proof in any claim, demand or suit
shall be required of the City regarding such discretionary action.
B. After receipt of a notice of termination , and except as otherwise directed by the City, the
Contractor shall:
1. Stop work under the Contract on the date and to the extent specified in the notice of termination;
2. place no further orders or subcontracts for materials , services or facilities except as may be
necessary for completion of such portion of the Work under the Contract as is not terminated ;
3. terminate all orders and subcontracts to the extent that they relate to the performance of the
Work terminated by notice of termination;
4. transfer title to the City and deliver in the manner, at the times , and to the extent, if any ,
directed by the City:
a . the fabricated or unfabricated parts, Work in progress, completed Work, supplies and
other material produced as a part of, or acquired in connection with the performance of,
the Work terminated by the notice of the termination ; and
b. the completed, or partially completed plans , drawings , information and other property
which , if the Contract had been completed , would have been required to be furnished to
the City.
5. complete performance of such Work as shall not have been terminated by the notice of
termination; and
6. take such action as may be necessary, or as the City may direct, for the protection and
preservation of the property related to its contract which is in the possession of the
Contractor and in which the owner has or may acquire the rest.
C. At a time not later than 30 days after the termination date specified in the notice of termination ,
the Contractor may submit to the City a list, certified as to quantity and quality , of any or all items
of termination inventory not previously disposed of, exclusive of items the disposition of which
has been directed or authorized by City.
CITY OF FOR T WORTH
ST AND ARD CONSTR UCT 10 SPEC I F !CA TIO N DOCUMENTS
Revi sion: 8/23/2D2 1
00 72 00-1
GENERAL CO NDITIONS
Page 6 1 of 63
D. Not later than 15 days thereafter, the City shall accept title to such items provided, that the list
submitted shall be subject to verification by the City upon removal of the items or, if the items are
stored, within 45 days from the date of submission of the list, and any necessary adjustments to
correct the list as submitted, shall be made prior to fmal settlement.
E. Not later than 60 days after the notice of termination, the Contractor shall submit his termination
claim to the City in the form and with the certification prescribed by the City. Unless an extension
is made in writing within such 60 day period by the Contractor, and granted by the City , any and
all such claims shall be conclusively deemed waived.
F. In such case, Contractor shall be paid for (without duplication of any items):
1. completed and acceptable Work executed in accordance with the Contract Documents prior
to the effective date of termination, including fair and reasonable swns for overhead and profit on
such Work;
2. expenses sustained prior to the effective date of termination in performing services and
furnishing labor , materials, or equipment as required by the Contract Documents in connection
with uncompleted Work, plus fair and reasonable sums for overhead and profit on such expenses;
and
3. reasonable expenses directly attributable to termination .
G. In the event of the failure of the Contractor and City to agree upon the whole amount to be paid
to the Contractor by reason of the termination of the Work, the City shall determine, on the basis
of information available to it, the amount, if any, due to the Contractor by reason of the termination
and shall pay to the Contractor the amounts determined. Contractor shall not be paid on account
of loss of anticipated profits or revenue or other economic loss arising out of or resulting from
such termination.
ARTICLE 16-DISPUTE RESOLUTION
16.01 Methods and Procedures
A. Either City or Contractor may request mediation of any Contract Claim submitted for a decision
under Paragraph 10 .06 before such decision becomes fmal and binding. The request for mediation
shall be submitted to the other party to the Contract. Timely submission of the request shall stay
the effect of Paragraph 10.06.E.
B. City and Contractor shall participate in the mediation process in good faith. The process shall be
commenced within 60 days of filing of the request.
C. If the Contract Claim is not resolved by mediation, City's action under Paragraph 10 .06.C or a
denial pursuant to Paragraphs 10.06.C.3 or 10 .06.D shall become fmal and binding 30 days after
termination of the mediation unless, within that time period, City or Contractor:
CITY OF FORT WORTH
ST AND ARD CO NSTR UC TIO N SPEC IFICA TIO N DOC UM ENT S
Revision : &/23/2021
00 72 00 -1
GENERAL COND ITIONS
Page 62 of63
l. elects in wntmg to invoke any other dispute re so lution process provided for m the
Supplementary Conditions; or
2. agrees with the other party to submit the Contract Claim to another dispute resolution
process; or
3 . gives written notice to the other party of the intent to submit th e Contract Claim to a court of
competent jurisdiction .
ARTICLE 17 -MISCELLANEOUS
17.01 Giving Notice
A. Whenever any provision of the Contract Documents require s the giving of written notice , it will
be dee med to have been validly given if:
I. delivered in person to the individual or to a me mber of the firm or to an officer of the
corporation for whom it is intended; or
2. delivered at or sent by registered or certified mail, postage prepaid, to the last business
address known to the giver of the notice .
B. Business address changes must be promptly made in writing to the other party.
C. Whenever the Contract Documents specifies giving notic e by electronic means such electronic
notice shall be deemed sufficient upon confrrmation of receipt by the receiving party.
17.02 Co mputation a/Times
When any period of time is referred to in the Contract Documents by days , it will be computed to
exclude the first and include the last day of such period . If the last day of any such period falls on a
Saturday or Sunday or on a day made a legal holiday the next Working Day shall become the last day
of the period.
17 .03 Cumulative Re medies
The duties and obligations imposed by these General Condition s and the rights and remedies available
hereunder to the parties hereto are in addition to , and are not to be construed in any way as a limitation
of, any rights and remedies available to any or all of them which are otherwise impo se d or available
by Laws or Regulations , by special warranty or guarantee, or by other provisions of the Contract
Documents. The provisions of this Paragraph will be as effective as if repeated specifically in the
Contract Documents in connection with each particular duty , obligation, right , and remedy to which
they apply .
CITY OF FORT WORTH
STANDARDC0NSTRUCTI0N SPECIFICATION DOCUMENTS
Revi sion: &'23/2021
17.04 S urvival of Obligations
00 72 00-1
GENERAL CONDIT IONS
Page 63 of 63
A ll representations, indemnifications, warranties , a nd guarantees made in , required by, or given in
accordance with the Contract D oc uments , as well as all continuing obligations indicated in the
Contract Documents, w ill survive final p ayment, completion, and acceptance of the Work or
termination or completion of the Contract or termination of the services of Contractor.
17.05 Headings
Article and paragraph headings are inserte d for convenience only and do not constitute parts of these
Genera l Conditions.
CITY OF FORT WORTH
STANDARDC0NSTRUCT I0N SPEC IFICATION DOCUMENTS
Revi sion: &'23/202 1
Supplementary Conditions
SECTION 00 73 00
SUPPLEMENTARY CONDITIONS
TO
GENERAL CONDITIONS
00 73 00
SUPPLEMENTARY CO N DITION S
Page I of5
These Supplementary Conditions modify and supplement Section 00 72 00 -General Conditions, and other
provisions of the Contract Documents as indicated below. All provisions of the General Conditions that are
modified or supplemented remain in full force and effect as so modified or supplemented. All provisions
of the General Conditions which are not so modified or supplemented remain in full force and effect.
Defined Terms
The terms used in these Supplementary Conditions which are defined in the General Conditions have the
meaning assigned to them in the General Conditions, unless specifically noted herein.
Modifications and Supplements
The following are instructions that modify or supplement specific paragraphs in the General Conditions and
other Contract Documents .
SC-3.03B.2, "Resolving Discrepancies"
Plans govern over Specifications .
SC-4.0lA
E asement limits shown on the Drawing are approximate and were provided to establish a basis for bidding.
Upon receiving the final easements descriptions , Contractor shall compare them to the lines shown on the
Contract Drawings .
SC-4.0lA.1., "Availability of Lands"
The following is a list of known outstanding right-of-way , and/or easements to be acquired , if any as of
December 9, 2022
Outstanding Right-Of-Way, and/or Easements to Be Acquired
PARCEL OWNER
NUMBER
None
TARGET DATE
OF POSSESSION
The Contractor understands and agrees that the dates listed above are estimates only, are not guaranteed ,
and do not bind the City.
If Contractor considers the final easements provided to differ materially from the representations on the
Contract Drawings , Contractor shall within five (5) Business Days and before proceeding with the Work ,
notify City in writing associated with the differing easement line locations.
CITY OF FORT WORTH
ST ANDA RD CO NSTRUCTION SPECIFI C ATION DOCUMENTS
Revised March 9, 2020
202 2 WATER SERVI CE L EAK
REPAIR CONTRACT
C ity Proj ect no. I 04552
SC-4.0lA.2, "Availability of Land s"
Utilities or ob struction s to be removed , adju sted, and /or reloca ted
00 73 0 0
SU PPL EMEN TARY CON DITION S
Page 2 of 5
T he fo ll ow in g is li st of ut il ities and /or obstructio ns th at have not bee n re moved , adju sted, a nd/o r re located
as of December 20, 2022
EXPECTE D
OWNER
None
UTILITY AND LOC A TIO T ARGET D A TE OF
AD JUSTMENT
T he Contractor und erstand s and agrees th at the dates li sted a bove are estim ates o nl y, are not gu a ranteed ,
and do not bind th e C ity.
S C-4.02A., "Subsurface and Physical Condition s"
T he fo ll owin g ar e re po rt s of expl orati ons and tests of sub surface co nditi o ns at t he s ite of th e Work :
None
T h e fo ll owin g are draw in gs of ph ys ic al co nditi o ns in or re lati ng to existin g surface and sub sur face
stru ctures (exce pt U nd ergro und Fac iliti es) w hi ch are at o r co ntig uo us to th e s it e of th e Wo rk:
None
S C-4.06A., "Hazardou s E nvironmental Conditions at Site"
T he fo ll ow in g are re po rt s and draw in gs of ex istin g haza rd o us env iro nm ental co nditi o n s kn own to th e C ity:
None
SC -5.03A., "Certificates of In surance"
T he entiti es li sted be low are "additi ona l in sure d s as th e ir interes t may a p pear" in c ludin g th e ir res pecti ve
offi ce rs, directo rs, age nts and employees.
(1 ) C ity
(2) Co nsult ant: None
(3) Oth er: None
SC-5.04A., "Contractor's In surance"
Th e limits of li a bili ty for th e in sura nc e requi red by Parag ra ph G C-5.04 sha ll provide th e foll owi ng
coverages fo r not less th an the fo ll owin g amo unts or greater where re quired by laws and regul ati o ns:
5.04A. Wo rk ers' Co mp ensati o n, und er P aragraph GC -5.04 A .
Statutory limits
E mpl oyer's li a bility
$100 ,000 each acc id ent/occ urrence
$100 ,000 Disease -eac h employee
$500 ,000 Di sease -poli cy limit
CITY OF FORT WORTH
ST AND ARD CON STRUC TION SPEC IF ICATIO N DO CUMENTS
Revi sed March 9, 2020
2022 WATER SER VI CE LEAK
REPAIR CONTRACT
C ity Project no . I 045 52
SC-5.04B., "Contractor's Insurance"
00 73 00
SUPPL EMEN TAR Y CON DITI ONS
Page 3 of 5
5.04B. Commercial General Liability, under Paragraph GC-5 .04B . Contractor's Liability Insurance
under Paragraph GC-5.04B., which shall be on a per project basis covering the Contractor with
minimum limits of:
$1,000 ,000 each occurrence
$2 ,000,000 aggregate limit
The policy must have an endorsement (Amendment -Aggregate Limits oflnsurance) making the
General Aggregate Limits apply separately to each job site .
The Commercial General Liability In surance policies shall provide "X", "C", and "U" coverage's.
Verification of such coverage must be shown in the Remarks Article of the Certificate of Insurance.
SC 5.04C., "Contractor's Insurance"
5.04C. Automobile Liability , under Paragraph GC-5 .04C . Contractor 's Liability Insurance under
Paragraph GC-5.04C., which shall be in an amount not less than the following amounts :
(I) Automobile Liability -a commercial business policy shall provide coverage on "Any Auto ",
defined as autos owned, hired and non-owned.
$1 ,000 ,000 each accident on a combined single limit basis. Split limits are acceptable if limits are at
least:
$250 ,000
$500 ,000
$100 ,000
Bodily Injury per person /
Bodily Injury per accident /
Property Damage
SC-5.04D., "Contractor's Insurance"
The Contractor's construction activities will require its employees, agents , subcontractors, equipment, and
material deliveries to cross railroad properties and tracks None
The Contractor shall conduct its operation s on railroad properties in such a manner as not to interfere with ,
hinder, or obstruct the railroad company in any manner whatsoever in the use or operation of its /their trains
or other property. Such operations on railroad properties may require that Contractor to execute a "Right of
Entry Agreement" with the particular railroad company or companies involved , and to this end the
Contractor should satisfy itself as to the requirements of each railroad company and be prepared to execute
the right-of-entry (if any) required by a railroad company. The requirements specified herein likewise relate
to the Contractor's use of private and/or construction access roads crossing said railroad company's
properties.
The Contractual Liability coverage required by Paragraph 5.04D of the General Conditions shall provide
coverage for not less than the following amounts , issued by companies satisfactory to the City and to the
Railroad Company for a term that continues for so long as the Contractor's operations and work cross ,
occupy, or touch railroad property:
(1) General Aggregate:
(2) Each Occurrence:
__ Required for this Contract
CITY OF FORT WORTH
STANDARD CO NSTRUCTIO N SP EC IFICATION DO CUMENTS
Re v ised March 9, 2020
$Confirm Limits with Railroad
$Confirm Limits with Railroad
_x_ Not required for this Contract
2022 WATER SERVI CE LEAK
REPAIR CO NTRACT
C ity Proj ect no. I 04 552
00 73 00
SUPPL EMENTARY CONDITION S
Page 4 of 5
With respect to the above outlined insurance requirements, the following sha ll govern:
1. Where a s in g le rai lroad company is involved , the Contractor shall provide one insurance policy in
the name of the rai lroad company . However, if more than one grade separation or at-grade
crossing is affected by the Project at entirel y separate locations on the lin e or lin es of the same
rai lro ad company, separate coverage may be required , each in the amount stated above.
2. Where more than one rai lroad company is operating on the same right-of-way or where several
railroad companies are involved and operated on their own separate rights-of-way, the Contractor
may be required to provide separate insurance policies in the name of each railroad company.
3. If, in addition to a grade separation or an at-grade crossing, other work or activity is proposed on a
railroad company 's right-of-way at a location entirely separate from the grade separation or at-
grade crossing, insurance coverage for this work must be included in the policy covering the grade
separation .
4 . If no grade separation is involved but other work is proposed on a railroad company 's ri ght-of-
way , all such other work may be covered in a s in gle policy for that railroad, even though the work
may be at two or more separate locations.
No work or activities on a railroad company's property to be performed by the Contractor sha ll be
commenced until the Contractor h as furnished the City with an original policy or policies of the insurance
for each railroad company named , as required above . All such insurance must be approved by the City and
each affected Railroad Company prior to the Contractor's beginning work.
The insurance specified above must be carried until a ll Work to be performed o n the railroad right-of-way
has been completed and the grade crossing, if any, is no longer used by the Contractor. In addition,
insurance must be carried during all maintenance and/or repair work performed in the railroad right-of-way .
Such insurance must name the rai lroad company as the insured, together with any tenant or lessee of the
railroad company operating over tracks in volved in the Project.
SC-6.04., "Project Schedule"
Project schedu le shall be tier 1 for the project.
SC-6.07., "Wage Rates "
The following is the prevailing wage rate table(s) applicable to this project and is provided in the
Appendixes:
GC-6.07 2013 Prevailing Wage Rates (Heavy & highway Construction Projects)
A copy of the table is also available by accessing the City 's website at:
https://apps.fortworthtexas.gov/ProjectResources/
You can access the file by following the directory path:
02-Construction Documents/Specifications/Div00 -General Conditions
SC-6.09., "Permits and Utilities"
SC-6.09A., "Contractor obtained permits and licen ses"
The following are known permits and/or li censes required by the Contract to be acquired by the Contractor:
None
CITY OF FORT WORTH
STANDARD CO NSTRUCTIO N SPEC IFI CATION DOCUMENT S
Revi sed March 9, 2020
2022 WATER SERVICE LEAK
REPAIR CONTRACT
C ity Proj ect no . I 04552
SC-6.09B. "City obtained permits and licenses"
00 73 00
SUPPLEMENTARY CONDITIONS
Page5of5
The following are known permits and/or li censes required by the Contract to be acquired by the City: None
SC-6.09C. "Outstanding permits and licenses "
T he following is a li st of known outstan din g permits and/or li censes to be acq uired, if any as of December
20,2022
Outstanding Permits and/or Licenses to Be Acquired
OWNER PERMIT OR LICENSE AND LOCATION
None
SC-7.02., "Coordination"
TARGE T DATE
OF POSSESSION
T he individuals or e ntiti es listed below h ave contracts with the City for the performance of other work at
the Site:
Vendor Scope of Work Coordination Authority
None
SC-8.01, "Communications to Contractor"
None
SC-9.01., "City's Project Manager"
The City 's Project Manager for this Co ntract is J. C hri s Underwood, or his /her successor pursuant to
written notification from the Director of Water Department.
SC-13.03C., "Tests and Inspections"
None
SC-16.0IC.1, "Methods and Procedures"
None
END OF SECTION
Revis ion Log
DATE NAME SUMMARY OF CHANGE
1/22/2016 F. Griffin SC-9 .01 ., "City 's Project Representative " wording changed to City 's Project
Manager.
3/9/2020 D.V. Magana SC-6 .07 , Updated the link such that files can be accessed via the City 's
website.
C ITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIF ICATION DOCUMENTS
Revised March 9, 2020
2022 WATER SERVICE L EA K
REPAIR CONTRACT
City Proj ect no. I 045 52
SECTION 01 11 00
2 SUMMARY OF WORK
3 PARTl-GENERAL
4 1.1 SUMMARY
5 A. Section Includ es:
01 11 00 -I
SUMMARY OF WORK
Page I of6
6 1. Summ ary of Work to be performed in accordance with the Contract D ocuments
7 B. Deviations fro m this Ci ty of Fort Worth Standard Specifi catio n
8 1. Bid Quantities-Bid quantities of the various items in the proposal are for
9 comparison only and may not reflect the actual quantities. There is no limit to
10 which a bid item can be increased or decreased.
11 Contractor shall not be entitled to renegotiation of unit prices regardless of the
12 final measured quantities. To the extent that General Conditions (00-72-00)
13 Article 11 conflicts with this provision, this provision controls. No claim will be
14 considered for lost or anticipated profits based upon differences in estimated
15 quantities versus actual quantities.
16 Total quantities given in the bid proposal may not reflect actual quantities;
17 however, they are given for the purpose of bidding and awarding the contract.
18 A contract in the amount of $750,000.00 shall be awarded with final payment
19 based on actual measured quantities and the unit price in this proposa l.
20 Moreover, there is to be no limit on the variation between the estimated
21 quantities shown and the actual quantities performed.
22 It is understood and agreed that the scope of work contemplated in this
23 contract is that which is designated by the City but will in no case exceed
24 $750,000.00
25 2. Non-Exclusive Contract-This contract is non-exclusive. During the term of
26 this contract or any renewal hereof, the City reserves the right to advertise
27 and award another contract for like or similar work. If a second contract is
28 awarded, the City further reserves the right to issue work orders under either
29 contract as it deems in its best interest, without recourse.
30 3. Scope of Work-The work covered by these Specifications consists of the
31 replacement or repair of existing 1-inch, 1.5-inch and 2-inch water services
32 that are leaking. Included in this work will be all necessary appurtenances
33 required for a complete water service leak repair or replacement and surface
34 restoration as itemized in the appropriate water service bid item and specified
35 in "Water Services 1-inch to 2-inch" (33-12-10).
36 The process for repairing or replacing the leaking water services will be as
37 follows:
38 a) The City of Fort Worth Water Field Operations Valve Crew will shut
39 down the water main prior to replacement.
40 b) The service line will be excavated and exposed at the water main to
41 assess the service line leak. City of Fort Worth Water Department
42 Staff will determine whether service line can be repaired or if full
43 replacement is necessary.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised De ce mber 20 , 2012
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No. I 04552
I
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
2 1
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
4.
01 11 00-2
SUMMARY OF WORK
Pa ge 2 of 6
c) In the event, at City of Fort Worth Water Department Staff
discretion, the leaking service lines can be repaired at the tap saddle
connection, corporation and/or any other fitting, the work will be paid
for at the price for each of the appropriate bid item for SERVICE
REPAIR, IN LIEU OF REPLACEMENT.
d) In the event, at City of Fort Worth Water Department Staff
discretion, the leaking service lines need full replacement, the existing
service line will be removed from main to meter including the removal
of the existing corporation at the main.
e) The appropriate tap saddle will be installed over the existing hole left
by the removal of the existing corporation. If the existing water main
is compromised by the removal of the corporation and as directed by
the engineer, a portion of the water main may be replaced, as
necessary. This portion will be paid for at the price per foot of the
appropriate bid item for water pipe (PVC or DIP). There will be no
additional payment as specified in these documents for "Connection
to Existing Water Mains" (33-12-25).
f) After the service line has been replaced, the City of Fort Worth Field
Operations Valve Crew will re-open the valves to load the water main.
The service line shall be flushed a minimum of thirty (30) minutes
before reconnecting to meter.
g) The water main and service shall be operational prior to the end of
the day and/or moving off of jobsite.
The Engineer shall determine and designate to the Contractor the location of
the service installation by a Work Order together with a sketch and/or map
for each such service installation, giving the appropriate bid item required for
installation and providing the amount of time to complete the work. The
Engineer will notify the Contractor that a Work Order is ready and fax
and/or e-mail the Contractor a copy of the Work Order notification. The
Contractor is to provide his fax number and e-mail address to the Engineer at
the pre-construction conference. Single or several Work Orders may be issued
at one time. The Contractor shall initiate work on an installation within seven
(7) working days of the date the Work Order is sent to the Contractor, and
continue work on the Work Order until it has been completed, not including
paving.
Contractor's Responsibility-Contractor covenants and agrees to fully
perform or cause to be performed, with good faith and due diligence, and in
accordance with standards common to the industry and herein set forth in
these Contract Documents which is hereby incorporated and made a part of
this contract. The City may designate water services to be installed by
furnishing to the contractor a marked drawing, or street addresses contained
in a written order or by marking in the field by painted stake or other means,
or by any or all combinations of said methods of designation. The contractor
agrees that no work will be performed without written authorization from the
individual designated in writing by the Director of the Water Department.
CITY OF FORT WORTH 2022 WATER SERVIC E LEAK
REPAIR CONTRACT
City Project No . I 04552
STANDARD CONSTRUCTION SPECIF ICATION DOCUMENTS
Revised December 20 , 2012
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
2 1
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
4 3
44
45
46
47
0 1 I I 00-3
SUMMARY OF WORK
Page 3 of6
5. Contract Time-It is contemplated that Work Orders will be issued to the
Contractor for work to be performed under this Contract for not to exceed
three hundred sixty-five (365) calendar days following the date of the Contract
nor to exceed the limit of the award amount, whichever should occur first. The
Contractor shall be required to complete any work covered by a Work Order
issued prior to that date of termination but will not be required to accept any
Work Order for execution dated after that date of termination. If the cost of
the work performed under this Contract is less than the limit of the contract
award at the end of the three hundred sixty-five (365) calendar day period, at
the City's option and the Contractor's concurrence, the Contract Time may
be extended to the limit of the contract award amount.
A calendar day is any day of the week or month, Sundays or legal holidays as
defined in General Conditions (00-72-00) Article 1.
6. Option to Renew-The time period of this Agreement will be for one calendar
year or the expiration of the funding, whichever occurs last. The City reserves
the right to renew the contract for up to three (3) additional time periods
under the same terms, conditions and unit prices. The City shall provide at
least sixty (60) days' notice to the Contractor of the City's intent to renew.
7. Required Crew Personnel & Equipment-The Contractor shall furnish and
supply sufficient equipment and personnel to complete the Work Order in the
amount of time provided for in the Work Order. Should the Contractor fail to
start any Work Order within the time specified, he shall add the necessary
work crews and equipment to prosecute the work to complete the Work Order
or Work Orders in the time provided.
8. Liquidated Damages-The Contractor shall pay liquidated damages of two
hundred ten dollars ($315.00) per day per Work Order, for Failure to begin a
Work Order within the seven (7) working days of the date the Work Order is
faxed and/or e-mailed to the Contractor. Failure to complete the work within
the stipulated construction time on the Work Order will require the
Contractor to pay liquidated damages in the amount stipulated in these
contract documents.
9. Payment-Because of the unique nature of this contract, General Conditions
(00-72-00) Article 14 shall not apply and shall be superseded by the following:
Whenever the improvements prescribed by an individual Work Order have
been completed, the contractor shall notify the engineer. The engineer or other
appropriate official of the owner will, within a reasonable time, perform the
inspections. If such inspection reveals that the improvements are in an
acceptable condition and have been completed in accordance with the terms of
the Contract Documents and all approved modifications thereof, the engineer
will recommend acceptance of the work under that particular Work Order
and recommend payment therefore.
If the engineer finds that the work has not been completed as required, he
shall so advise the contractor in writing, furnishing him an itemized list of all
known items which have not been completed or which are not in acceptable
condition. When the contractor has corrected all such items, he shall again
notify the engineer that the improvements are ready for inspection, and the
engineer shall proceed as outlined above.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised December 20 , 2012
2022 WATER SERVICE LEAK
REPAIR CONTRACT
C ity Project No. I 04552
0 1 11 00-4
SUMMARY OF WORK
Page 4 of6
Whenever the improvements prescribed by the individual Work Order have
2 been completed and all the requirements of the Contract Documents have
3 been fulfilled on the part of the contractor, an estimate showing the value of
4 the work will be prepared by the engineer as the necessary measurements,
5 computations and checks can be made.
6 The amount of the estimate will be paid to the contractor after acceptance by
7 the Water Department Director, provided the contractor has furnished to the
8 owner satisfactory evidence of payment as follows: Prior to submission of the
9 estimate for payment, the contractor shall execute an affidavit, as furnished by
10 the City, certifying that all persons, firms, associations, corporations or other
11 organizations furnishing labor and/or materials under that Work Order have
12 been paid in full, that the wage scale established by the City Council in the
13 City of Fort Worth has been paid, and that there are no claims pending for
14 personal injury and/or property damages.
15 The acceptance by the contractor of the individual payment as aforesaid shall
16 operate as and shall release the owner from all claims or liabilities under the
17 Contract for anything done or furnished or relating to the work under that
18 Work Order or any act or neglect of said City relating to or connected with
19 the Contract.
20 The making of the payment by the owner shall not relieve the contractor of
21 any guarantees or other requirements of the Contract Documents which
22 specifically continue thereafter.
23 C. Related Specification Sections include, but are not necessarily limited to:
24 1. Division O -Bidding Requirements , Contract Forms , and Conditions of the Contract
25 2. Division 1 -General Requirements
26 1.2 PRICE AND PAYMENT PROCEDURES
27 A . Measurement and Payment
28 1. Work associated with this Item is considered subsidiary to the various items bid .
29 No separate payment will be allowed for this Item.
30 1.3 REFERENCES [NOT USED]
31 1.4 ADMINISTRATIVE REQUIREMENTS
32 A. Work Covered by Contract Documents
33 1. Work is to include furnishing all labor, materials, and equipment, and performing
34 all Work necessary for this construction project as detailed in the Drawings and
35 Specifications.
36 8 . Subsidiary Work
37 1. Any and all Work specifically governed by documentary requirements for the
38 project, such as conditions imposed by the Drawings or Contract Documents in
39 which no specific item for bid has been provided for in the Proposal and the item is
40 not a typical unit bid item included on the standard bid item list, then the item shall
41 be considered as a subsidiary item of Work, the cost of which shall be included in
42 the price bid in the Proposal for various bid items.
43 C . Use of Premises
C ITY OF FORT WORTH
STANDARD CO NSTRUC TlON SP EC IFI CATION DOCUMENT S
Revi sed Decem ber 20, 20 12
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No. I 04552
1. Coordinate u ses of premises under direction of the City.
01 11 00-5
SUMMARY OF WORK
Page5of6
2 2. Assume full responsibility for protection and safekeepin g of materials and
3 equipment stored on the Site.
4 3. Use and occupy only portions of the public streets and alleys, or other public places
5 or other rights-of-way as provided for in the ordinances of the City, as shown in the
6 Contract Documents, or as may be specifically authorized in writing by the City.
7 a. A reasonable amount of tools , materials, and equipment for construction
8 purposes may be stored in such space, but no more than is nece ssary to avoid
9 de lay in the construction operations.
10 b. Excavated and waste materials shall be stored in such a way as not to interfere
11 with the u se of spaces that may be designated to be left free and unobstructed
12 and so as not to inconvenience occupants of adjacent property.
13 c. If the street is occupied by railroad tracks , the Work shall be carried on in such
14 manner as not to interfere with the operation of the railroad.
15 1) All Work shall be in accordance with railroad requirements set forth in
16 Division Oas well as the railroad permit.
17 D . Work within E asements
18 1. Do not enter upon private property for any purpose without having previou s ly
19 obtained pennission from the owner of such property.
20 2. Do not store equipment or material on private property unless and until the
21 specified approval of the property owner has been secured in writing by the
22 Contractor and a copy furnished to the City.
23 3. Unless specificall y provided otherwise, clear a ll right s-of-way or easements of
24 obstructions which must be removed to make poss ible proper prosecution of the
25 Work as a part of the project construction operations .
26 4. Preserve and use every precaution to prev ent damage to , all trees, shrubbery , plants ,
27 lawns, fences, cu lverts, curbing, and a ll other types of structures or improvements,
28 to a ll water, sewer, and gas lin es, to a ll conduits , overhead pole lines, or
29 appurtenances thereof, in cluding the construction of temporary fences and to all
30 other public or private property adjacent to the Work.
3 l 5. Notify the proper repre sentatives of the owners or occupants of the public or private
32 land s of interest in land s which might be affected by the Work.
33 a. Such notice shall be made at least 48 hours in advance of the beginning of the
34 Work.
35 b. Notices sha ll be applicable to both public and private utility companies and any
36 corporation, company, individual , or other, either as owners or occupants ,
37 whose land or interest in land might be affected by the Work.
38 c. Be responsible for a ll damage or injury to property of any character resulting
39 from any act, omission , neglect, or misconduct in the manner or method or
40 execution of the Work, or at any time du e to defective work, material , or
41 equipment.
42 6. Fence
43 a. Restore all fences encountered and removed durin g construction of the Project
44 to the original or a better than original condition.
45 b. E rect temporary fencing in place of the fencing removed whenever the Work is
46 not in progress and w hen the site is vacated overnight, and/or at all times to
47 provide s it e security.
CITY OF FORT WORTH
STANDARD CONS TRUCTION SPECIFICATION DOCUMENTS
Revi sed December 20 , 20 I 2
2022 WATER SERVICE LEAK
REPAIR CONTRACT
C ity P roj ec t No. 104552
0 1 11 00-6
SUMMARY OF WORK
Page 6 of6
c. T he cost for a ll fence wo rk w ithin easements, in c ludin g re moval, t e mp orary
2 c los ures and re pl acement, sha ll be s ub s idiary t o th e variou s ite ms bid in th e
3 proj ect pro posal, unl ess a bi d ite m is s pec ifica ll y pro v id e d in the proposal.
4 1.5 SUBMITT AL S [NOT US ED]
5 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
6 1.7 CLOSEOUT SUBMITTALS [NOT USED]
7 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
8 1.9 QUALITY ASSURANCE [NOT USED]
9 1.10 DELIVERY , STORAGE, AND HANDLING [NOT USED]
10 1.11 FIELD [SITE] CONDITIONS [NOT USED]
11 1.12 WARRANTY [NOT USED]
12 PART 2 -PRODUCTS [NOT USED]
13 PART 3 -EXECUTION [NOT US ED]
14 END OF SECTION
15
16
Revis io n L og
D ATE NAME
CITY OF FORT WORTH
STANDARD CONSTRUCT ION SPEC IFICATION DOCUMENTS
Revised Decembe r 20, 20 12
SUMMARY OF CHANGE
2022 WATER SERVICE LEAK
REPA IR CONTRACT
City Projec t No. 104552
SECTION 0125 00
2 SUBSTITUTION PROCE DURES
3 PARTl-GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
0 12500-1
SUBS TITUTION PROCEDURES
Page I of4
6 1 . The procedure for requesting the approval of substitution of a product th at is not
7 equivalent to a product which is specified by descriptive or performance criteria or
8 defined by reference to 1 or more of the following:
9 a . Name of manufacturer
10 b. Name of vendor
11 c. Trade name
12 d . Catalog number
13 2. Substitutions are not "or-equals".
14 B. Deviations from this City of Fort Worth Standard Specification
15 1. None.
16 C . Related Specification Sections include, but are not necessarily limited to :
17 1. Division O -Bidding Requirements, Contract Forms and Conditions of the Contract
18 2. Division 1 -General Requirements
19 1.2 PRICE AND PAYMENT PROCEDURES
20 A. Meas urement and Payment
21 1. Work associated with this Item is considered subsidiary to the various item s bid .
22 No separate payment will be allowed for this Item .
23 1.3 REFERENCES [NOT USED]
24 1.4 ADMINISTRATIVE REQUIREMENTS
25 A . Request for Substitution -General
26 1. Within 30 days after award of Contract ( unless noted otherwise), the City wi II
27 consider formal requests from Contractor for substitution of products in place of
28 those specified.
29 2. Certain types of equipment and kinds of mater ial are described in Specifications by
30 means of references to names of manufacturers and vendors, trade names, or
31 catalog numbers.
32 a . When this method of specifying is used , it is not intended to exclude from
33 consideration other products bearing other manufacturer's or vendor's names ,
34 trade names , or catalog numbers, provided said products are "or-equals," as
35 determined by City .
36 3. Other types of equipment and kinds of material may be acceptable substitutions
37 under the following conditions:
38 a. Or-equals are unavailable due to strike, discontinued production of products
39 meeting specified requirements, or other factors beyond control of Contractor;
40 or,
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFI CATION DOCUMENTS
R ev ised July I , 20 11
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Proj ect No. I 04552
0 I 25 00 -2
SUB STITUTION PRO C ED UR ES
Page 2 of 4
b. Contractor proposes a cost and/or time reduction inc e ntive to the City.
2 1.5 SUBMITT ALS
3 A . See Request for Substitution Form (attached)
4 B . Procedure for R e questing Substitution
5 1. Substitution shall be considered only :
6 a . After award of Contract
7 b. Under the conditions stated herein
8 2. Submit 3 copies of each written request for substitution, including:
9 a . Documentation
10 1) Complete data substantiating compliance of proposed substitution with
11 Contract Documents
12 2) Data relating to changes in construction schedule, when a reduction is
13 proposed
14 3) Data relating to chang es in cost
15 b. For products
16 1) Product identification
17 a) Manufacturer's name
18 b) Telephone number and representative contact name
19 c) Specification Section or Drawing reference of originally specified
20 product, including discrete name or tag number assigned to original
21 product in the Contract Documents
22 2) Manufacturer's literature clearly marked to show compliance of proposed
23 product with Contra ct Documents
24 3) Itemized comparison of original and proposed product addressing product
25 characteristics including, but not necessarily limited to:
26 a) Size
27 b) Composition or materials of construction
28 c) Weight
29 d) E lectrical or mechanical requirements
30 4) Product experience
31 a) Location of past projects utilizing product
32 b) Name and telephone number of persons associated with referenced
33 projects knowledgeable concerning proposed product
34 c) Available field data and reports associated with proposed product
35 5) Samples
36 a) Provide at request of City.
37 b) Samples become the property of the City.
38 c . For construction methods:
39 1) Detailed description of proposed method
40 2) Illustration drawings
41 C. Approval or Rejection
42 I . Written approval or rejection of substitution given by the City
43 2. City reserves the right to require proposed product to comp ly with color and pattern
44 of specified product if necessary to secure design intent.
45 3 . In the event the substitution is approved , the resulting cost and/or time reduction
46 will be documented by Change Order in accordance with the General Conditions.
C ITY O F F ORT WO RTH
STANDARD C ON STRUC TION S PEC IFICATI ON DOCUMENTS
Revi sed Jul y I , 20 11
2022 WATER SE RVI CE LEAK
REPAIR CO NTRACT
C ity Proj ec t N o . I 04552
4 . No additional contract time will b e given for substitution.
2 5 . Substitution w ill be rejected if:
0 1 25 00 -3
SUBSTITUT ION PROCEDURES
Page 3 of4
3 a. Submittal is not through the Contractor w ith his stamp of a pprova l
4 b . Request is not made in accordance w ith this Spec ificat ion Section
5 c. In the City's opinion, acceptance wi ll require substantia l revision of the original
6 design
7 d. In the City's opinion, subst itution wi ll not perform adeq u ate ly the funct ion
8 cons iste nt w ith the design intent
9 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS (NOT USED]
10 1.7 CLOSEOUT SUBMITTALS [NOT USED]
11 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
12 1.9 QUALITY ASSURANCE
13 A. In making request for substitutio n or in using an approved product, the Contractor
14 represents that the Contractor:
15 1. Has investigated proposed product, and h as determined th at it is adequ ate or
16 superior in a ll respects to that specified , and t hat it w ill perform function fo r which
17 it is intended
18 2. Will provide same guarantee for substitute item as for product s pecified
19 3. Will coordinate installatio n of accepted s ub stitution into Work, to inc lud e building
20 modifications if necessary, m aking s uc h changes as may be required for Work to be
2 1 comp lete in all respects
22 4. Waives a ll c laims for additional costs related to substituti on whic h subseq uently
23 arise
24 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
25 1.11 FIELD [SITE] CONDITIONS [NOT USED]
26 1.12 WARRANTY [NOT USED]
27 PART 2 -PRODUCTS [NOT USED]
28 PART 3-EXECUTION [NOT USED]
29 END OF SECTION
30
3 1
Revision Log
DATE NAME
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised Jul y I , 20 I I
SUMMARY OF CHANGE
2022 WATER SER VI CE LEAK
REPAIR CONTRACT
City Project No. 104552
1
2
3
4
5
6
7
8
9
10
EXHIBIT A
REQUEST FOR SUBSTITUTION FORM:
0 1 2500-4
SUBSTITUT ION PROCEDURES
Page 4 of4
TO: ___________________________________ _
PROJECT: _______________ DATE : __________ _
We hereby s ubmit for your co ns ideration the fo llow in g product in stead of the s pecified item for
th e above project:
SECTION PARAGRAPH SPECIFIED ITEM
11 Proposed Substitution: ______________________________ _
12 Reas on for Substitution: _____________________________ _
13 Include comp lete information on changes to Drawings and/or Specifications which propose d
14 s ub stitution will require for it s proper in stall at ion .
15
16 Fill in Blanks B e low :
17 A. Will the undersign e d contractor pay for changes to the building desi g n, including engineering
18 and detailin g costs caused by the requested substitution?
19
20
21 B . What effect does substitution have on other trad es?
22
23
24 C . Diffe rence s between propose d substitution and specified item ?
25
26
27 D. Diffe rences in product cost or product de liv ery time?
28
29
30 E. Manufacturer's guarantees of the propose d and specified items are:
31
32 ___ E qual ___ B etter (explain on attachment)
33 The unders ig ned states th at the function , a ppearance and quality are equivalent or superior to the
34 specified item.
35 Submitted By: For Use by C ity
36
37
38
39
40
41
42
43
44
45
Signature ____________ _
as noted
Firm ______________ _
Address ____________ _
Date ______________ _
Te lephone ____________ _
46 For Use by City:
47
48
49
___ Approved
City ____________ _
C ITY OF FORT WORTH
STANDARD CONSTRUCTION SPEC IFICATION DOCUMENTS
Rev ise d Jul y I , 20 11
Recommende d Recommended
Not recomm e nded __ Received late
By ______________ _
Date _________________ _
Remarks _______________ _
___ Rejected
Date _________________ _
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No. I 04552
SECTION 01 3119
2 PRECONSTRUCTION MEETING
3 PARTl-GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
01 3 1 19-1
PRECON STRUCTION MEETING
Pag e 1 of3
6 I . Provisions for the preconstruction meeting to be held prior to the start of Work to
7 clarify construction contract administration procedures
8 B. Deviations from this City of Fort Worth Standard Specification
9 I. None.
10 C. Related Specification Sections include, but are not necessarily limited to:
11 I. Division O -Bidding Requirements , Contract Forms and Conditions of the Contract
12 2. Division I -General Requirements
13 1.2 PRICE AND PAYMENT PROCEDURES
14 A. Measurement and Payment
15 I. Work associated with this Item is considered subsidiary to the various items bid .
16 No separate payment will be allowed for this Item.
17 1.3 REFERENCES [NOT USED]
18 1.4 ADMINISTRATIVE REQUIREMENTS
19 A. Coordination
20 I. Attend preconstruction meeting.
21 2. Representatives of Contractor, subcontractors and suppliers attending meetings
22 shall be qualified and authorized to act on behalfofthe entity each represents .
23 3. Meeting administered by City may be tape recorded.
24 a. If recorded, tapes will be used to prepare minutes and retained by City for
25 future reference.
26 B. Preconstruction Meeting
27 I. A preconstruction meeting wi l 1 be held within 14 days after the execution of the
28 Agreement and before Work is started.
29 a . The meeting will be scheduled and administered by the City.
30 2. The Project Representative will preside at the meeting, prepare the notes of the
31 meeting and distribute copies of same to all participants who so request by fully
32 completing the attendance form to be circulated at the beginning of the meeting.
33 3. Attendance shall include:
34 a. Project Representative
35 b. Contractor's project manager
36 c. Contractor's superintendent
37 d. Any subcontractor or supplier representatives whom the Contractor may desire
38 to invite or the City may request
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPEC!FICATIO N DOCUMENTS
Revised August 17, 20 12
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No. 104 552
I
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
• 29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
e. Other City representatives
f. Others as appropriate
4. Construct ion Schedule
OJ 31 19-2
PRECONSTRUCTION MEETING
Page 2 of3
a. Prepare baseline construction schedu le in accordance with Section O 1 32 16 and
provide at Preconstruction Meeting .
b. City will notify Contractor of any schedu le changes upon Notice of
Preconstruction Meeting.
5. Preliminary Agenda may include :
a. Introduction of Project Personnel
b. General Description of Project
c. Status of right-of-way, utility clearances, easements or other pertinent permits
d. Contractor's work plan and schedule
e. Contract Time
f. Notice to Proceed
g . Construction Staking
h . Progress Payments
1. Extra Work and Change Order Procedures
j. Fie ld Orders
k. Disposal Site Letter for Waste Material
1. Insurance Renewals
m . Payroll Certification
n . Material Certifications and Quality Control Testing
o. Public Safety and Convenience
p. Documentation of Pre-Construction Conditions
q. Weekend Work Notification
r. Legal Holidays
s . Trench Safety Plans
t. Confined Space Entry Standards
u. Coordination with the City's representative for operations of existing water
systems
v. Storm Water Pollution Prevention Plan
w. Coordination with other Contractors
x. Early Warning System
y. Contractor Evaluation
z. Special Conditions applicable to the project
aa. Damages Claims
bb. Submittal Procedures
cc. Substitution Procedures
dd . Correspondence Routing
ee. Record Drawings
ff. Temporary construction facilities
gg. M/WBE or MBE/SBE procedures
hh . Final Acceptance
ii. Final Payment
jj. Questions or Comments
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFlCATION DO CUMEN TS
Revised Augu st 17, 2012
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No. I 04552
1.5 SUBMITT ALS [NOT USED]
0 1 3 1 19 -3
PRECONSTRUCTION MEETING
Page 3 of3
2 1.6 ACTION SUBMITTALS/INFORMATIONAL SU BMITTALS [NOT USED]
3 1.7 CLOSEOUT SUBMITTALS [NOT USED]
4 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
5 1.9 QUALITY ASSURANCE [NOT USED]
6 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
7 1.11 FIELD [SITE] CONDITIONS [NOT USED]
8 1.12 WARRANTY [NOT USED]
9 PART 2 -PRODUCTS [NOT USED]
10 PART 3 -EXECUTION [NOT USED]
11 END OF SECTION
12
13
Revisi o n Log
DATE NAME
C ITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIF ICATION DOCUMENTS
Revi sed August 17, 20 12
SUMMARY OF CHANGE
2022 WATER SERVJCE LEAK
REPAIR CONTRA CT
C ity Project No. I 04552
0 1 32 16 - I
CONST RU C TION PROGRESS SCHEDULE
Page I of 10
SECTION 01 32 16
2 CONSTRUCTION SCHEDULE
3 PARTl-GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. General requirements for the preparation, submittal , updating, status reporting and
7 management of the Construction Progress Schedule
8 2 . Specific requirements are pres ente d in the City of Fort Worth Schedule Guidance
9 Document
10 B . Deviations from this City of Fort Worth Standard Specification
11 1. None.
12 C. Related Specification Sections include , but are not necessarily limited to:
13 1. Divi sio n O -Bidding Requirements, Contract Forms and Conditions of the Contract
14 2. Division I -General Requirements
15 D. Purpose
16 The City ofFort Worth (City) is committed to delivering quality, cost-effective
17 infrastructure to its citizens in a timely manner. A key tool to achieve this purpose is a
18 properly structured schedule with accurate updates. This supports effective monitoring
19 of progress and is input to critical decision making by the project manager throughout
20 the life of the project. Data from the updated project schedule is utilize d in status
21 reporting to various levels of the City organization and the citizenry.
22
23 This Document complements the City's Standard Agreement to guide the construction
24 contractor (Contractor) in preparing and submitting acceptable schedules for use by the
25 City in project delivery. The expectation is the performance of the work follows the
26 accepted sc hedule and adhere to the contractual timeline .
27
28 The Contractor will designate a qualified representative (Project Scheduler) responsible
29 for developing and updating the schedule and preparing status reporting as required by
30 the City.
31 1.2 PRICE AND PAYMENT PROCEDURES
32 A. Measurement and Payment
33 1. Work associated with this Item is considered subsidiary to the various items bid.
34 No se parate payment will be allowed for this Item .
35 2. Non-compliance with this specification is grounds for City to withhold payment of
36 the Contractor's invoices until Contractor achieves said compliance .
37 1.3 REFERENCES
38 A. Project Schedules
CITY OF FORT WORTH
STANDARD CONSTRUCT IO N SP EC IFICATION DOCUMENTS
Revised Au g ust 13 , 2021
2022 WATER SERVICE LEAK
REP AIR CONTRACT
City Project No. I 04552
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
B.
0 1 32 16 -2
C O NS T RUCTION PROG RESS SCHEDULE
Page 2 of 10
Each project is represented by City 's master project schedule that encompasses the
entire scope of activities envisioned by the City to properly deliver the work. When the
City contracts with a Contractor to perform construction of the Work, the Contractor
will develop and maintain a schedule for their scope of work in ali g nment with the
City 's standard schedule requirements as defined herein. The data and information of
each such schedule will be leveraged and become integral in the master project
schedule as deemed appropriate by the City 's Project Control Specialist and approved
by the City's Project Manager.
1. Master Project Schedule
The master project schedule is a holistic representation of the scheduled activitie s
and milestones for the total project and be Critical Path Method (CPM) based. The
City's Project Manager is accountable for oversight of the development and
maintaining a master project schedule for each project. When the City contracts for
the design and/or construction of the project, the master project schedule will
incorporate elements of the Design and Construction schedules as deemed
appropriate by the City 's Project Control Specialist. The assigned City Project
Control Specialist creates and maintains the master project schedule in P6 (City's
scheduling software).
2. Construction Schedule
The Contractor is responsible for developing and maintaining a schedule for the
scope of the Contractor's contractual requirements . The Contractor will issue an
initial schedule for review and acceptance by the City's Project Control Specialist
and the City 's Project Manager as a baseline schedule for Contractor's scope of
work. Contractor will issue current, accurate updates of their schedule (Progress
Schedule) to the City at the end of each month throughout the life of their work .
Schedule Tiers
The City has a portfolio of projects that vary widely in size, complexity and content
requiring different scheduling to effectively deliver each project. The City uses a
"tiered" approach to align the proper schedule with the criteria for each project. The
City's Project Manager determines the appropriate schedule tier for each project, and
includes that designation and the associated requirements in the Contractor 's scope of
work. The following is a summary of the ''tiers".
1. Tier 1: Small Size and Short Duration Project (design not required)
The City develops and maintains a Master Project Schedule for the project. No
schedule submittal is required from Contractor. City's Project Control Specialist
acquires any necessary schedule status data or information through discussions with
the respective party on an as-needed basis.
2. Tier 2: Small Size and Short to Medium Duration Project
The City develops and maintains a Master Project Schedule for the project. The
Contractor identifies "start" and "finish " milestone dates on key elements of their
work as agreed with the City's Project Manager at the kickoff of their work effort.
The Contractor issues to the City, updates to the "start" and "finish " dates for such
milestones at the end of each month throughout the life of their work on the project.
3. Tier 3: Medium and Large Size and/or Complex Projects Regardless of Duration
CITY OF FORT WORTH 2022 WATER SERVICE LEAK
REP AIR CONTRACT
City Proj ect No. I 045 52
STANDARD CON STRUC TION SPECIFI CATION DOCUMENTS
Rev ised August 13 , 2021
0132 16-3
CONSTRUCT JO N PROGRESS SCHEDULE
Page 3 of 10
The City develops and maintains a Master Project Schedule for the project. The
2 Contractor develops a Baseline Schedule and maintains the schedule of their
3 respective scope of work on the project at a level of detail (generally Level 3) and in
4 alignment with the WBS structure in Section 1.4.Has agreed by the Project
5 Manager. The Contractor issues to the City, updates of their respective schedule
6 (Progress Schedule) at the end of each month throughout the life of their work on the
7 project.
8 C. Schedule Types
9 Project delivery for the City utilizes two types of schedules as noted below. The City
IO develops and mainta in s a Master Project Schedule as a "baseline" schedu le and iss ue
11 monthly updates to the City Project Manager (end of each month) as a "pro g re ss"
12 schedule. The Contractor prepares and submits each schedule type to fulfill their
13 contractual requirements.
14
15 1. Baseline Schedule
16 The Contractor d eve lop s and submits to the City, an initial schedule for their scope
17 of work in alignment with this specification . Once reviewed and accepted by the
18 City, it becomes the "Baseline" schedule and is the basis against which all progress
19 is measured . The baseline schedule wi ll be updated when there is a change or
20 addition to the scope of work impacting the duration of the work, and only after
21 receipt of a duly authorized change order is s ued by the City. In the event progress is
22 significantly behind schedule, the City's Project Manager may authorize an update
23 to the baseline schedule to facilitate a more practical evaluation of progress. An
24 example of a Baseline Schedule is provided in Specification 01 32 16.1
25 Construction Project Schedule Baseline Example.
26
27 2. Progress Schedule
28 The Contractor updates their schedule at the end of each month to represent the
29 progress achieved in the work which includes any impact from authorized changes
30 in the work. The updated schedule must accurately reflect the current status of the
31 work at that point in time and is referred to as the "Progress Schedule". The City's
32 Project Manager and Project Control Specialist reviews and accepts each progress
33 schedule. In the event a progress schedule is deemed not acceptab le, the
34 unacceptable is s ues are identified by the City within 5 working days and the
35 Contractor must provide an acceptable progress schedule within 5 working days
36 after receipt of non-acceptance notification . An example of a Progress Schedule is
37 provided in Specification 01 32 16.2 Construction Project Schedu le Progress
38 Example.
39 D. City Standard Schedule requirements
40 The following is an overview of the methodology for developing and maintaining a
41 schedule for delivery of a project.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICA TTO N DOCUl'vlENTS
Revised August 13, 202 1
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No. l04552
2
3
4
5
6
7
8
9
JO
11
0 1 32 16 -4
CONSTRUCTION PROGRE SS SCHED UL E
Pa ge 4 of IO
1. Schedule Framework -The schedule will be based on the defined scope of work
and follow the (Critical Path Methodology) CPM method. The Contractor's
schedule will align with the requirements of this specification and will be cost
loaded to reflect their plan for execution. Compliance with cost loading can be
provided with traditional cost loading of line items OR a projected cost per
month for the project when the initial sc hedule is submitted, updated on a
quarterly basis is significant change is anticipated. Overall schedule duration
will align with the contractual requirements for the respective scope of work and be
reflected in City 's Master Project Schedule . The Project Number and Name of the
Project is required on each schedule and must match the City's project data.
12 E. Schedule File Name
13 All schedules submitted to the City for a project will have a file name that begins with
14 the City's project number followed by the name of the project followed by baseline (if
15 a baseline schedule) or the year and month (if a progress schedule), as shown below.
16
17
18
19
20
21
22
23
24
25
26
27
28
• Baseline Schedule Fi le Name
Format:
Example:
City Project Number_Project Name_Baseline
101376_North Montgomery Street HMAC_Basel ine
• Progress Schedule File Name
Format: City Project Number _Project Name_ YYYY-MM
Example: 101376_North Montgomery Street HMAC_2018_01
• Project Schedule Progress Narrative File Name
Format: City Project Number _Project Name _PN _ YYYY-MM
Example: 101376_North Montgomery Street HMAC_PN_2018_01
29 F. Schedule Templates
30 The Contractor will utilize the relevant sections from the City's templates provided in
31 the City's document management system as the basis for creating their respective
32 project schedule . Specificall y, the Contractor's schedu le will align with the layout of
33 the Construction section. The templates are identified by type of project as noted
34 below.
35 • Arterials
36 • Aviation
37 • Neighborhood Streets
38 • Sidewalks (later)
39 • Quiet Zones (later)
40 • Street Lights (later)
41 • Intersection Improvements (later)
42 • Parks
43
44
45
46
47
• Storm water
• Street Maintenance
• Traffic
• Water
48 G . Schedu le Calendar
CITY OF FORT WORTH
STANDARD CONSTRUCTION SP EC IFI CATIO N DO CUMENTS
Revi sed Au g ust 13, 2021
20 22 WATER SERVIC E LEAK
REP AIR CONTRA CT
City Project No . I 04 552
0 1 32 16 -5
CONST RUC TION PRO GRESS SC HED ULE
Page 5 of 10
The City 's standard calendar for schedule development purpo ses is based on a 5-day
2 workweek and accounts for the City 's eig ht standard holidays (New Years, Martin
3 Luther King, Memorial , Independence, Labor, T hanksgiving, day after Thanksgiving,
4 Christmas). The Contractor wi 11 establish a schedule calendar as part of the schedule
5 development process and provide to the Project Control Spec ialist as p art of the bas is
6 for their schedule . Variations between the City 's calendar and the Contractor 's
7 calendar must be re solved prior to the City 's acce ptance of th e ir Baseline project
8 schedule.
9
JO H. WBS & Milestone Standards for Schedule Development
11 The scope of work to be accomplished by the Contractor is represented in th e schedule
12 in the form of a Work Breakdown Structure (WBS). The WBS is the basis for the
13 development of the schedule activities and shall be imbedded and depicted in the
14 schedule.
15
16 The followin g is a summary of the standard s to be followed in pre parin g and
17 maintaining a schedule for project delivery.
18
19 1. Contractor is required to utilize the City 's WBS structure and respective
20 project type template for "Construction" as shown in Section 1.4.H below.
21 Additional activities may be added to Levels 1 - 4 to accommodate the need s
22 of the organization executing the work. Specifically the Contractor wi 11 add
23 activities under WBS XXXXXX .80.83 "Construction Execution " that
24 delineates the activities associated with the variou s components of the work .
25
26 2 . Contractor is re quired to adhere to the City's Standard Milestones as shown
27 in Section 1.4.l below. Contractor will include additional milestones
28 repre senting intermediate deliverables as required to accurately reflect their
29 scope of work.
30
31 I. Schedule Activiti e s
32 Activities are the discrete elements of work that make up the schedule. They will be
33 organized under the umbrella of the WBS. Activity de scriptions should adequately
34 describe the activity, and in some cases the extent of the activity. All activities are
35 logically ti e d with a predecessor and a successor. The only exception to this rule is for
36 "proj ect start" and "project finish " milestones.
37
38
39
40
41
42
43
The activity duration is based on the physical amount of work to be performed for the
stated activity, with a maximum duration of 20 working days OR a continuous activity
in one location. If the work for any one activity exceeds 20 days , break that activity
down incrementall y to achieve this duration constraint. Any e xception to this requires
review and acceptance by the City 's Project Control Specialist.
44 J. Change Orders
45 When a Change Order is issued by the City , the impact is incorporated into the
46 previously accepted baseline schedule as an update, to clearly show impact to the
47 project timeline . The Contractor submits this updated baseline schedule to the City for
CITY OF FORT WO RTH
ST AN DARD CONSTR UC TI ON SPEC IFI CA TIO N DOCUMEN TS
Re vised Au gust 13 , 202 1
2022 WATER SE RVI CE LEAK
RE PAIR CONTRACT
City Proj ec t No . 104552
01 32 16 -6
C ONS TRUC TION PROG R ESS SCHEDULE
l
2
3
4
5
6
7
8
9
JO
Page 6 of IO
review and acceptance as described in Section 1.5 below. Updated baseline schedules
adhere to the following :
I. Time extensions associated with approved contract modifications are limited to the
actual amount oftime the project activities are anticipated to be delayed, unless
otherwise approved by the Prog ram Manager.
2. The re-baselined schedule is submitted by the Contractor within ten workdays after
the date of receipt of the approved Change Order.
11 3. The changes in logic or durations approved by the City are used to analyze the impact
12 of the change and is included in the Change Order. The coding for a new activity(s)
13 added to the schedule for the Change Order includes the Change Order number in the
14 Activ ity ID. Use as many activities as needed to accurately show the work of the
15 Change Order. Revisions to the baseline schedule are not effective until accepted by
16 the City .
17 K. City's Work Breakdown Structure
18
19
20
21
22
23
24
25
26
27
28
WBS Code WBS Name
XXXXXX Project Name
XXXXXX.30 Design
XXXXX:X.30 .10
XXXXXX.30.20
XXXXXX.30.30
XXXXXX.30.40
XXXXXX.30.50
XXXXXX.30.60
XXXXXX .30 .60.10
Design Contractor Agreement
Conceptual Design (30%)
Preliminary Design (60%)
Final Design
Environmental
Permits
Permits -Identification
29 XXXXXX.30.60.20 Permits -Review/Approve
30 XXXXXX.40 ROW & Easements
31 XXXXXX.40 .10 ROW Negotiations
32 XXXXXX.40.20 Condemnation
33 XXXXXX.70 Utility Relocation
34 XXXXXX.70.10 Utility Relocation Co-ordination
35 XXXXXX.80 Construction
36 XXXXXX .80.81 Bid and Award
37 XXXXXX.80.83 Construction Execution
38 XXXXX:X.80.85 Inspection
39 XXXXX:X.80.86 Landscaping
40 XXXXXX.90 Closeout
41 XXXXX:X.90.10 Construction Contract Close-out
42 XXXXXX.90.40 Design Contract Closure
43 L. City 's Standard Milestones
44 The following milestone activities (i .e., important events on a project that mark critical
45 points in time) are of particular interest to the City and must be reflected in the project
46 schedu le for all phases of work.
47
CITY OF FORT WORTH
STANDARD C ON STRUCTION SP EC IFI C ATION DOCUMENTS
Revi sed Aug ust 13 , 2021
2022 WATER SERVICE LEAK
REP AIR CONTRACT
City Proje ct No. I 04552
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
2 1
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
01 32 I 6 - 7
CONSTRUCT ION PROGRESS SCHEDULE
Activity ID Activity Name
Design
3020
3040
3100
Award Design Agreement
I ss ue Notice to Proceed -Design E ng ineer
Design Kick-off Meeting
Page 7 of 10
3120 Submit Conceptual Plans to Utilities, ROW, Traffic, Parks, Storm Water,
3150
3160
3170
3220
3250
3310
Water & Sewer
Peer Review Meeting/Design Review meeting (technical)
Conduct Design Public Meeting #1 (required)
Conceptual Design Complete
Submit Preliminary Plans and Specifications to Utilities, ROW, Traffic,
Parks, Storm Water, Water & Sewer
Conduct Design Public Meeting #2 (required)
3260 Preliminary Design Complete
Submit Final Design to Utilities, ROW, Traffic, Parks, Storm Water,
Water & Sewer
3330 Conduct Des ign Public Meeting #3 (if required)
3360 Final Design Complete
ROW & Easements
4000 Right of Way Start
4230 Right of Way Complete
Utility Relocation
7000 Utilities Start
7120 Utilities Cleared/Complete
Construction
Bid and Award
8110 Start Advertisement
8150 Conduct Bid Opening
8240 Award Construction Contract
Construction Execution
8330 Conduct Construction Public Meeting #4 Pre-Construction
8350 Construction Start
8370 Substantial Completion
8540 Construction Completion
9130 Notice of Completion/Green Sheet
9150 Construction Contract Closed
9420 Design Contract Closed
39 1.4 SUBMITT ALS
40 A. Schedule Submittal & Review
41 The City's Project Manager is responsible for reviews and acceptance of the Contractor's
42 schedule. The City's Project Control Specialist is responsible for ensuring alignment of
43 the Contractor's baseline and progress sched ules with the Master Project Schedule as
44 support to the City 's Project Manager. The City reviews and accepts or rejects the
45 schedule within ten workdays of Contractor's submittal.
46
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised August 13 , 2021
2022 WATER SERVICE LEAK
REPAJR CONTRACT
City Project No. I 04552
I
2
3
4
5
6
7
8
9
10
I I
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
1. Schedule Format
0 13216-8
CONSTRUCT ION PRO GRESS SCHEDULE
Page 8 of 10
The Contractor will s ubmit each sc hed ule in two electronic forms , one in native file
format (.xer, .xml, .mpx) and the second in apd/fonnat, in the City's document
management system in the location dedicated for this purpose and identified by the
Project Manager. In the event the Contractor does not use Primavera P6 or MS
Project for scheduling purposes , the schedule information must be s ubmitted in .xis or
.xlsx format in compliance with the samp le layout (See Specification 01 32 16.1
Construction Project Schedule Baseline Example), including activity predecessors,
successors and total float.
2. Initial & Baseline Schedule
The Contractor will develop their schedule for their scope of work a nd submit their
initial schedule in electronic form (in the file formats noted above), in the City's
document management system in the location dedicated for this purpose at least 5
working days prior to Pre Construction Meeting.
The City's Project Manager and Project Control Specialist review this initial schedule
to determine alignment with the City's Master Project Schedule, including format &
WBS struct ure . Following the City's review, feedback is provid ed to the Contractor
for their use in finalizing their initi a l schedule and issuing (within jive workdays) their
Baseline Schedule for final review and acceptance by the City.
3. Progress Schedule
The Contractor will update and is s ue their project schedule (Progress Schedule) by the
last day of each month throughout the life of their work on the project. The Progress
Schedule is submitted in electronic form as noted above, in the City's document
management system in the location d ed icated for this purpose.
The City 's Project Control team reviews each Progress Schedule for data and
information that support the assessment of the update to the schedule. In the event
data or information is missing or incomplete, the Project Controls Specialist
communicates directly with the Contractor's scheduler for providing same. The
Contractor re-submits the corrected Progress Schedule within 5 workdays , following
the submittal process noted above. The City's Project Manager and Project Control
Specialist review the Contractor's prog res s schedule for acceptance and to monitor
performance and progress.
The following list of items are required to ensure proper status information is
contained in the Progress Schedule.
• Baseline Start date
• Baseline Finish Date
• % Complete
• Float
• Activity Logic (dependencies)
• Critical Path
• Activities added or deleted
• Expected Base line Finish date
• Variance to the Baseline Finish Date
CITY OF FORT WORTH
STANDARD CONSTRUCT IO N SPECIFICA TION DO CUMEN TS
Revised August I 3,202 I
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No . I 04552
0 1 32 16 -9
CO NSTRUCTIO N PROGRE SS SCHEDULE
Page 9 of 10
l B. Monthly Construction Status Report
2 The Contractor submits a written status report (referred to as a progress narrative) at the
3 monthly progress meeting (if monthly meetings are held) or at the end of each month to
4 accompany the Progress Schedule submittal , using the standard format provided in
5 Specification 01 32 16.3 Construction Project Schedule Progress Narrative. The content
6 of the Construction Project Schedule Progress Narrative should be concise and complete
7 to include only changes, delays , and anticipated problems.
8
9 C. Submittal Process
10
II
12
13
14
• Schedules and Monthly Construction Status Reports are submitted in in the City's
document management system in the location dedicated for this purpose.
• Once the project has been completed and Final Acceptance has been issued by the
City, no further progress schedules or construction status reports are required from
the Contractor.
15 1.
16 1.5 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
17 1.6 CLOSEOUT SUBMITT ALS [NOT USED]
18 1.7 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
19 1.8 QUALITY ASSURANCE
20 A. The person preparing and revising the construction Progress Schedule shall be
21 experienced in the preparation of schedules of sim i I ar complexity.
22 B. Schedule and supporting documents addressed in this Specification shall be prepared,
23 updated and revised to accurately reflect the performance of the construction.
24 C. Contractor is responsible for the quality of all submittals in this section meeting the
25 standard of care for the construction industry for similar projects.
26 1.9 DELIVERY, STORAGE, AND HANDLING [NOT USED]
27 1.10 FIELD [SITE] CONDITIONS [NOT USED]
28 1.11 WARRANTY [NOT USED]
29 1.12 ATTACHMENTS
30 Spec 013216.1 Construction Project Schedule Baseline Example
31 Spec 01 32 16.2 Construction Project Schedule Progress Example
32 Spec O 1 32 16.3 Construction Project Schedule Progress Narrative
33
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFI CATIO N DOCUMENTS
Revi sed August 13 , 2021
2022 WATER SERVI CE LEAK
REPAIR CONTRACT
City Project No . 104552
2 PART 2 -PRODUCTS [NOT USED]
3 PART 3 -EXECUTION [NOT USED]
4 END OF SECTION
5
Revision Log
0 1 32 16 -I O
CONSTRUC TION PROGRESS SCHEDULE
Page IO of IO
•
DATE NAME SUMMARY OF CHANGE
6
8/13 /2021 Michael Owen Revi sed to update specification requirements and e liminate duplicate schedule
specifications.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPEClFICA TION DO CUMEN TS
Revi se d August 13, 202 1
2022 WATER SERVICE LEAK
REP AIR CONTRACT
City Project No. I 04552
1 SECTION 01 32 33
2 PREC ON STR UCTIO N V IDE O
3 PARTl-GENERAL
4 1.1 SUMMARY
5 A. S ecti o n In c lud es:
6 1. A dmini strati ve and procedural require m en ts fo r :
7 a . Preco nstructi on Videos
8 B . D ev iati ons from thi s City of F ort Wo rth St a nd ard Spec ific ation
0 1 3233-1
PRECONSTRUC TION VID EO
Page I of2
9 1. Pre-construction Videos-Given the brief nature of the Work Orders in this
10 contract, pre-construction videos will only be required as reques ted by the
11 inspector or directed by the Engineer.
12 C . R e late d S pecificatio n S ecti ons in c lud e, bu t are not necessaril y limi te d to :
13 1. D iv is ion O -Bi d ding R e quire me nts , Co nt ract Form s and Condi ti o ns of t he Contract
14 2 . Di v is io n 1 -General R equire me nts
I 5 1.2 PRICE AND PAYMENT PROCEDURES
16 A . M eas urem e nt a nd Paym ent
17 1. W o rk assoc iate d w ith thi s Item is co ns id e re d s ub sidiary to the v a ri o us ite m s bid.
18 N o se parate pay m ent will be a ll owed fo r thi s Item.
19 1.3 REFERENCES [NOT USED]
20 1.4 ADMINISTRATIVE REQUIREMENTS
2 1 A. Preco nstructio n Vid eo
22 1. Pro du ce a preco nstructi on v id eo of th e s ite/a lignment, inc lu di ng a ll areas in the
23 v ic ini ty of a nd to be affect ed by c on stru cti o n .
24 a. Prov id e di g it a l copy o f vid eo up on re quest by th e C ity.
25 2. R eta in a co py of th e precon st ruction v id eo until the end of th e m a inte nance s ur ety
26 pe ri od .
27 1.5 SUBMITT ALS [NOT USED]
28 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT US ED]
29 1. 7 CLOSEOUT SUBMITT ALS [NOT USED]
3 0 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
3 1 1.9 QUALITY ASSURANCE [NOT USED]
32 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
33 1.11 FIELD [SITE] CONDITIONS [NOT USED]
34 1.12 WARRANTY [NOT USED]
CITY OF FORT WORTH
STANDARD CONSTRU CT ION SPEC IFICATION DO CUMENTS
Revi sed Ju ly I, 20 I I
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No . I 04552
PART 2 -PRODUCTS [N OT US ED]
2 PART 3 -EXECUTION [NOT US ED]
3 END OF SECTION
4
Revi s ion Log
0 1 3233-2
PRECONSTRUCTION VIDEO
Page 2 of2
D ATE NAME SUMMARY OF CHANGE
5
CITY OF FORT WORTH
STAND ARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised J uly I , 2011
2022 WATER SERVI CE LEAK
REPAIR CONTRACT
C ity Projec t No. I 04552
SECTION 01 33 00
2 SUB MITT ALS
3 PARTl-GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
0 1 33 00 .- I
S UBMITIALS
Page I of 8
6 1. General methods and requirements of submissions applicable to the following
7 Work-related submittals:
8 a. Shop Drawings
9 b. Product Data (including Standard Product List submittals)
10 c . Samples
11 d. Mock Ups
12 B. Deviations from this City of Fort Worth Standard Specification
13 1. None.
14 C. Related Specification Sections include, but are not necessarily limited to:
15 1. Division O -Bidding Requirements, Contract Forms and Conditions of the Contract
16 2. Division 1 -General Requirements
17 1.2 PRICE AND PAYMENT PROCEDURES
18 A. Measurement and Payment
19 1. Work associated with this Item is considered subsidiary to the various items bid.
20 No separate payment will be allowed for this Item.
21 1.3 REFERENCES [NOT USED]
22 1.4 ADMINISTRATIVE REQUIREMENTS
23 A. Coordination
24 1. Notify the City in writing, at the time of submittal, of any deviations in the
25 submittals from the requirements of the Contract Documents.
26 2 . Coordination of Submittal Times
27 a . Prepare, prioritize and transmit each submittal sufficiently in advance of
28 performing the related Work or other applicable activities, or within the time
29 specified in the individual Work Sections, of the Specifications.
30 b. Contractor is responsible such that the installation will not be delayed by
31 processing times including, but not limited to:
32 a) Disapproval and resubmittal (if required)
33 b) Coordination with other submittals
34 c) Testing
35 d) Purchasing
36 e) Fabrication
37 f) Delivery
38 g) Similar sequenced activities
39 c. No extension of time will be authorized because of the Contractor's failure to
40 transmit submittals sufficiently in advance of the Work.
CITY OF FORT WORTH
STANDARD CONSTRUCTIO N SPECIFICATION DOC UMENTS
Revi sed December 20, 2012
202 2 WATER SERVI CE LEA K
REPAIR CONTRACT
Ci ty Project No. I 0455 2
01 3300-2
SUBMJITALS
Page 2 of8
d . Make submittals promptly in accordance with approved schedule, and in such
2 sequence as to cause no delay in the Work or in the work of any other
3 contractor.
4 B . Submittal Numbering
5 1. When submitting shop drawings or samples , utili z e a 9-character submittal cross-
6 reference identification numbering system in the following manner:
7 a . Use the fir st 6 digits of the applicable Specification Section Number.
8 b . For the next 2 digits number use numbers 01-99 to sequentially number each
9 initial separate item or drawing submitted under each specific Section number.
10 c. Last use a letter, A-Z, indicating the resubmission of the same drawing (i .e .
11 A =2nd submission, B =3rd submission, C=4th submission, etc .). A typical
12 submittal number would be as follows:
13
14 03 30 00-08-B
15
16 1) 03 30 00 is the Specification Section for Concrete
17 2) 08 is the eighth initial submittal under this Specification Section
18 3) B is the third submission (second resubmission) of that particular shop
19 drawing
20 C. Contractor Certification
21 I. Review shop drawings, product data and samples, including those by
22 subcontractors, prior to submission to determine and verify the following:
23 a. Field measurements
24 b . Field construction criteria
25 c. Catalog numbers and similar data
26 d . Conformance with the Contract Documents
27 2. Provide each shop drawing, sample and product data submitted by the Contractor
28 with a Certification Statement affixed including:
29 a. The Contractor's Company name
30 b. Signature of submittal reviewer
31 c. Certification Statement
32 I) "By this submittal , I hereby represent that I have determined and verified
33 field measurements , field construction criteria, materials, dimensions,
34 catalog numbers and similar data and I have checked and coordinated each
35 item with other applicable approved shop drawings."
36 D . Submittal Format
37 1. Fold shop drawings larger than 8 ½ inches x 11 inches to 8 ½ inches x l linches .
38 2 . Bind shop drawings and product data sheets together.
39 3. Order
40 a. Cover Sheet
41 I) Description of Packet
42 2) Contractor Certification
43 b. List of items / Table of Contents
44 c. Product Data /Shop Drawings/Samples /Calculations
45 E. Submittal Content
46 1. The date of submission and the dates of any previous submissions
CITY OF FORT WORTH
STANDARD C ON STRUCTION SPECIFJ CATION DOCUMENTS
Re v ised Decembe r 20, 20 12
2022 WATER SERVICE LEAK
REPAIR C ONTRACT
C ity Proj ect No . I 0455 2
013300-3
SUBMJTIALS
Page 3 of8
2. The Project title and number
2 3 . Contractor identification
3 4 . The names of:
4 a. Contractor
5 b. Supplier
6 c. Manufacturer
7 5. Identification of the product, with the Specification Section number, page and
8 paragraph(s)
9 6. Field dimensions , clearly identified as such
10 7 . Relation to adjacent or critical features of the Work or materials
11 8. Applicable standards, such as ASTM or Federal Specification numbers
12 9. Identification by highlighting of deviations from Contract Documents
13 10. Identification by highlighting ofrevisions on resubmittals
14 11. An 8-inch x 3-inch blank space for Contractor and City stamps
15 F. Shop Drawings
16 1. As specified in individual Work Sections includes , but is not neces sari ly limited to:
17 a. Custom-prepared data such as fabrication and erection/installation (working)
18 drawings
19 b. Scheduled information
20 c. Setting diagrams
21 d. Actual shopwork manufacturing instructions
22 e. Custom templates
23 f. Special wiring diagrams
24 g. Coordination drawings
25 h. Individual system or equipment inspection and test reports including :
26 1) Performance curves and certifications
27 i. As applicable to the Work
28 2. Details
29 a. Relation of the various parts to the main members and lines of the structure
30 b. Where correct fabrication of the Work depends upon field measurements
31 1) Provide such measurements and note on the drawings prior to submitting
32 for approval.
33 G. Product Data
34 1. For submittals of product data for products included on the City's Standard Product
35 List, clearly identify each item selected for use on the Project.
36 2. For submittals of product data for products not included on the City's Standard
37 Product List, submittal data may include, but is not necessarily limited to:
38 a. Standard prepared data for manufactured products (sometimes referred to as
39 catalog data)
40 1) Such as the manufacturer's product specification and installation
41 instructions
42 2) Availability of colors and patterns
43 3) Manufacturer's printed statements of compliances and applicability
44 4) Roughing-in diagrams and templates
45 5) Catalog cuts
46 6) Product photographs
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised December 20 , 20 12
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No. I 04552
7) Standard wiring diagrams
2 8) Printed pe rformance curves and operational-range diag ram s
0 I 33 00 - 4
SUBMIITALS
Page 4 of8
3 9) Production or quality co ntrol in s pection and te st reports and certifications
4 10) Mill reports
5 11) Product operating and maintenance in structions a nd recommended
6 s pare-parts li stin g and printed product warranties
7 12) As applicable to the Work
8 H. Samples
9 1. As s pecified in individual Sections, include, but are not n ecessaril y limited to:
10 a. Physical examples of the Work such as:
11 1) Sections of manufactured or fabricated Work
12 2) Small cuts or containers of materials
13 3) Complete units of repetitively used products co lor/texture/pattern swatches
14 and range sets
15 4) Specimens for coordination of visual effect
16 5) Graphic sy mbol s and units of Work to be used by the City for independent
17 inspection and testin g, as applicable to the Work
18 I. Do not s tart Work requiring a shop drawing, sample or produ c t data nor any material to
19 be fabricated or insta lled prior to th e approval or qualified approval of such item .
20 1. Fabrication performed, material s purchased or on-s ite constr uction accomplished
21 wh ich does not conform to approved shop drawings and data is at the Contractor's
22 risk.
23 2. The C ity will not be li able for any expense or delay due to corrections or remedies
24 required to accompl ish conform ity.
25
26
3. Complete project Work, material s, fabrication , and inst all ations in conformance
with approved s hop drawings, appl icable samples , and product data.
27 J. Submittal Dist ribution
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
1. E lectronic Di stribution
a. Confirm development of Project directory for e lectronic submittals to be
uploaded to City's Buzzsaw site, or another external FTP s ite approved by the
C ity.
b. Shop Drawings
1) Upload submittal to desi gnated project directory and notify appropriate
City representatives v ia email of subm ittal posting.
2) Hard Copies
a) 3 copies for all s ubmittals
b) If Contractor requires more than 1 hard copy of Shop Drawings
returned, Contractor s h a ll submit more than the number of copies li sted
above.
c. Product Data
l ) Upload submittal to designated project directory and notify appropriate
C ity representatives via email of submittal posting .
2) Hard Copies
a) 3 copies for all submittals
d . Samples
I) Distributed to the Project R e prese ntative
2. Hard Copy Distribution (if required in lieu of electronic distribution)
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICA T!ON DOCUMENTS
Revised December 20 , 20 12
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Proj ect No. I 04552
a. Shop Drawings
2 1) Distributed to the City
3 2) Copies
4 a) 8 copies for mechanical submittals
5 b) 7 copies for all other submittals
0 1 3300-5
SUBMJTTALS
Page 5 of8
6 c) If Contractor requires more than 3 copies of Shop Drawings returned,
7 Contractor shall submit more than the nwnber of copies listed above.
8 b. Product Data
9 1) Distributed to the City
10 2) Copies
11 a) 4 copies
12 c. Samples
13 1) Distributed to the Project Representative
14 2) Copies
15 a) Submit the number stated in the respective Specification Sections.
16 3. Distribute reproductions of approved shop drawings and copies of approved
17 product data and samples , where required, to the job site file and elsewhere as
18 directed by the City.
19 a. Provide number of copies as directed by the City but not exceeding the number
20 previously specified.
21 K. Submittal Review
22 1. The review of shop drawings , data and samples will be for general conformance
23 with the design concept and Contract Documents. This is not to be construed as:
24 a. Permitting any departure from the Contract requirements
25 b. Relieving the Contractor ofresponsibility for any errors, including details ,
26 dimensions, and materials
27 c. Approving departures from details furnished by the City, except as otherwise
28 provided herein
29 2. The review and approval of shop drawings, samples or product data by the City
30 does not relieve the Contractor from his/her responsibility with regard to the
31 fulfillment of the terms of the Contract.
32 a. All risks of error and omission are assumed by the Contractor, and the City will
33 have no responsibility therefore.
34 3. The Contractor remains responsible for details and accuracy , for coordinating the
35 Work with all other associated work and trades , for selecting fabrication proce sses,
36 for techniques of assembly and for performing Work in a safe manner.
37 4 . If the shop drawings , data or samples as submitted describ e variations and show a
38 departure from the Contract requirements which City finds to be in the interest of
39 the City and to be so minor as not to involve a change in Contract Price or time for
40 performance, the City may return the reviewed drawings without noting an
41 exception .
42 5. Submittals will be returned to the Contractor under 1 of the following codes:
43 a . Code 1
44 1) "NO EXCEPTIONS TAKEN" is assigned when there are no notations or
45 comments on the submittal.
46 a) When returned under this code the Contractor may release the
47 equipment and/or material for manufacture.
48 b. Code 2
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised Decemb er 20 , 2012
2022 WATER SERVICE LEAK
REPAIR CONTRACT
C ity Project No. 104 552
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
0133 00 -6
SUBMTITALS
Page 6 of8
1) "EXCEPTIONS NOTED". This code is assigned when a confirmation of
the notations and comments IS NOT required by the Contractor.
a) The Contractor may release the equipment or material for manufacture;
however, all notations and comments must be incorporated into the
final product.
c . Code 3
1) "EXCEPTIONS NOTED/RESUBMIT". This combination of codes is
assigned when notations and comments are extensive enough to requ ire a
resubmittal of the package.
a) The Contractor may re lease the equipment or material for manufacture ;
however, all notations and comments must be incorporated into the
final product.
b) This resubmittal is to address all comments, omissions and
non-conforming items that were noted .
c) Resubmittal is to be received by the City within 15 Calendar Days of
the date of the City's transmittal requiring the resubmittal.
d. Code 4
1) "NOT APPROVED" is assigned when the submittal does not meet the
intent of the Contract Documents.
a) The Contractor must resubmit the entire package revised to bring the
submittal into conformance .
b) It may be necessary to resubmit using a different manufacturer/vendor
to meet the Contract Documents.
6. Resubmittals
a. Hand led in the same manner as first submittals
1) Corrections other than requested by the City
2) Marked with revision triangle or other similar method
a) At Contractor's risk if not marked
b. Submittals for each item will be reviewed no more than twice at the City 's
expense.
1) All subsequent reviews wi ll be performed at time s convenient to the City
and at the Contractor's expense, based on the City's or City
Representative's then prevailing rates.
2) Provide Contractor reimbursement to the City within 30 Calendar Days for
all such fees invoiced by the City .
c. The need for more than 1 resubmiss ion or any other delay in obtaining City's
review of submittals, w ill not entitle the Contractor to an extension of Contract
Time.
7. Partial Submittals
a. City reserves the right to not review submittals deemed partial, at the City 's
discretion.
b. Submittals deemed by the City to be not comp lete will be returned to the
Contractor, and will be considered "Not Approved" until resubmitted.
c. The City may at its option provide a li st or mark the submittal directing the
Contractor to the areas that are incomplete.
8. If the Contractor considers any correction indicated on the shop drawings to
constitute a change to the Contract Documents , then written notice must be
provided thereof to the City at least 7 Calendar Days prior to release for
manufacture.
CITY OF FORT WORTH
STANDARD CON STRU CTION SPECIFT CA TTO N DO CUMENT S
Revi sed De cemb er 20, 20 12
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No. 104552
0 1 3300-7
SUBMITIALS
Page 7 of8
9. When the shop drawings have been completed to the satisfaction of the C ity , the
2 Contractor may carry out th e co nstruction in accordance therewith and no further
3 ch anges therein except upon written in stru ctions from the C ity.
4 10 . Each s ubmittal , appropriately coded, will be returned w ithin 30 Cale nd ar Days
5 fo llo w in g receipt of s ubmitta l by th e City .
6 L. Mock up s
7 1. Mock Up units as specified in individual Sections, in clude, but are not necessarily
8 limited to, complete units of the stand ard of acceptance for that type of Work to be
9 used on the Project. Remove at the completion of the Work or w hen directed .
10 M. Qualifications
11 1. If specifica lly required in other Sections of these Specifications, submit a P.E.
12 Certification for each item required.
13 N. Request for Inform ation (RPI)
14 1. Contractor Request for a dditiona l info rm ation
15 a . C lar ificat ion or interpretatio n of the contract documents
16 b. When the Contractor b e li eves there is a conflict between Contract Documents
17 c. When the Contractor believes there is a conflict between th e Drawings and
18 Spec ifications
19 1) Id e nti fy the conflict and request clarification
20 2. Use the Request for Inform atio n (RPI) form provided by the C ity .
21 3. Numbering of RPI
22 a. Prefix with "RPI" followed by series number, "-xxx", beginning with "O 1" and
23 incre as ing sequentially with each ad ditional transmittal.
24 4. Sufficient information sha ll be attached to p erm it a written res pon se without further
25 inform ation .
26 5. The City w ill log each request and w ill review the request.
27 a. Ifreview of the proj ect information request indicates that a change to the
28 Contract Documents is required, th e City wi ll issue a F ie ld Order or C hange
29 Order, as appro priate.
30 1.5 SUBMITTALS [NOT USED]
3 1 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
32 1.7 CLOSEOUT SUBMITTALS [NOT USED]
33 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
34 1.9 QUALITY ASSURANCE [NOT USED)
35 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
36 1.11 FIELD [SITE] CONDITIONS [NOT USED]
37 1.12 WARRANTY [NOT USED]
C ITY OF FORT WORTH
STANDARD CONSTRUCTION SPEC IFICATION DOCUMENTS
Revised December 20, 20 12
2022 WATER SERVICE LEAK
REPAIR CONTRACT
C ity Project No. I 04552
PART 2 -PRODU CTS [NOT USED]
2 PART 3 -EXE CUTIO N [N OT USED]
3 END OF SEC TION
4
Revis ion Log
DATE NAME SUMMARY OF CHANGE
01 33 00 -8
SUBMIITALS
Page8of8
12/20 /20 12 D. Jo hnson 1.4.K.8. Wo rking Days modified to Calendar Days
5
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised December 20 , 20 12
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No. 104552
01 35 13 -I
SPEC IAL PROJ ECT PROCEDURES
Page I of8
SECTION 01 35 13
2 SPECIAL PROJECT PROCEDURES
3 PARTl-GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. The pro cedures for special project circumstances that includes, but is not limited to :
7 a . Coordination with the Texas Department of Transportation
8 b. Work near High Voltage Lines
9 c. Confined Space Entry Program
10 d. Use of Explosives , Drop Weight, E tc.
11 e. Water Department Notification
12 f. Public Notification Prior to Beginning Construction
13 g. Coordination with United States Army Corps of Engineers
14 h. Coordination within Railroad permits areas
15 1. Dust Control
16 j . Employee Parking
17 B . Deviations from thi s City of Fort Worth Standard Specification
18 1. None.
19 C. Related Specification Sections include, but are not necessarily limited to :
20 1. Divi s ion O -Bidding Requirements, Contract Forms and Conditions of the Contract
21 2. Division 1 -General Requirements
22 3. Section 33 12 25 -Connection to Existing Water Mains
23 1.2 PRICE AND PAYMENT PROCEDURES
24 A. Measurement and Payment
25 1. Coord in ation within Railroad permit areas
26 a. Meas urement
27 1) Measurement for this Item will be by lump sum .
28 b . Payment
29 1) The work performed and material s furnished in accordance with this Item
30 will be paid for at the lump sum price bid for Railroad Coordination.
31 c. The price bid shall include:
32 1) Mobilization
33 2) Inspection
34 3) Safety training
35 4) Additional Insurance
36 5) Insurance Certificates
37 6) Other requirements assoc iated with general coordination with Railroad,
38 including additional employees required to protect the right-of-way and
39 property of the Railroad from damage arising out of and/or from the
40 construction of the Project.
41 2. Railroad F lag men
42 a. Measurement
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFI CATIO N DOCUMENTS
Revised March I I, 2022
2022 WATER SERVICE LEAK
RE PAIR CONTRACT
C ity Project No. 104552
0 I 35 13 -2
SPEC IAL PROJECT PROCEDURES
Page2of8
1) Measurement for thi s Item will be per working day .
b. Payment 2
3
4
5
6
7
8
9
1) The work perform ed and materials furnished in accordance with this Item
will be paid for each working day th at Railroad Flagmen are pre sent at the
Site.
c. The price bid shall include :
1) Coordination for scheduling flagmen
2) Flagmen
3) Other requirements associated with Railroad
3. All other items 10
11
12
a. Work associated with the se Items is considered subsidiary to the various Items
bid. No separate payment will be allowed for this Item.
13 1.3 REFERENCES
14 A. Reference Standards
15 1. Reference standards cited in this Specification refer to the current reference
16 standard published at the time of the latest revision date logged at the end of this
17 Specification, unless a date is specifically cited.
18 2. Health and Safety Code, Title 9. Safety, Subtitle A. Public Safety, Chapter 752.
19 Hi g h Voltage Overhead Lines.
20 1.4 ADMINISTRATIVE REQUIREMENTS
21 A. Coordination with the Texas Department of Transportation
22 1. When work in the right-of-way which is under the jurisdiction of the Texas
23 Department of Transportation (TxDOT):
24 a. Notify the Texas Department of Transportation prior to commencing any work
25 therein in accordance with the provisions of the permit
26 b . All work performed in the TxDOT right-of-way shall be performed in
27 compliance with and subject to approval from the Texas Department of
28 Transportation
29 B. Work near High Voltage Lines
30 1. Regulatory Requirements
31 a. All Work near High Voltage Lines (more than 600 volts measured between
32 conductors or between a conductor and the ground) shall be in accordance with
33 Health and Safety Code, Title 9, Subtitle A, Chapter 752.
34 2. Warning sign
35 a. Provide sign of sufficient size meeting all OSHA requirements.
36 3 . E quipment operating within 10 feet of high voltage lines will require the following
37 safety features
38 a . Insulating cage-type of guard about the boom or arm
39 b. Insulator links on the lift hook connections for back hoes or dippers
40 c. Equipment must meet the safety requirements as set forth by OSHA and the
41 safety requirements of the owner of the high voltage lines
42 4. Work within 6 feet of high voltage electric lines
43 a. Notification shall be given to:
44 1) The power company (example: ONCOR)
CITY OF FORT WORTH
ST AND ARD CONSTRUCTIO N SPECJFICA TION DOCUMENTS
Revised March I I, 2022
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City P roj ect No. I 04552
0 1 351 3 -3
SPEC IAL PROJ ECT PROCEDURE S
Page 3 of 8
a) Maintain an accurate log of all such calls to power company and record
2 action taken in each case.
3 b. Coordination with power company
4 1) After notification coordinate with the power company to:
5 a) Erect temporary mechanical barriers, de-energize the lines , or raise or
6 lower the lines
7 c. No personnel may work within 6 feet of a high voltage line before the above
8 requirements have been met.
9 C. Confined Space Entry Program
10 1. Provide and follow approved Confined Space Entry Program in accordance with
11 OSHA requirements.
12 2. Confined Spaces include:
13 a. Manholes
14 b. All other confined spaces in accordance with OSHA 's Permit Required for
15 Confined Spaces
16 D. Use ofExplosives, Drop Weight, Etc.
17 1. When Contract Documents permit on the project the following will apply:
18 a. Public Notification
19 1) Submit notice to City and proof of adequate insurance coverage, 24 hours
20 prior to commencing.
21 2) Minimum 24 hour public notification in accordance with Section 01 31 13
22 E. Water Department Coordination
23 1. During the construction of this project, it will be necessary to deactivate, for a
24 period of time, existing lines. The Contractor shall be required to coordinate with
25 the Water Department to determine the best times for deactivating and activating
26 those lines.
27 2. Coordinate any event that will require connecting to or the operation of an existing
28 City water line system with the City's representative.
29 a. Coordination shall be in accordance with Section 33 12 25.
30 b. If needed, obtain a hydrant water meter from the Water Department for use
31 during the life of named project.
32 c. In the event that a water valve on an existing live system be turned off and on
33 to accommodate the construction of the project is required, coordinate this
34 activity through the appropriate City representative.
35 1) Do not operate water line valves of existing water system.
36 a) Failure to comply will render the Contractor in violation of Texas Penal
37 Code Title 7, Chapter 28.03 (Criminal Mischief) and the Contractor will
38 be prosecuted to the full extent of the law.
39 b) In addition, the Contractor will assume all liabilities and
40 responsibilities as a result of these actions.
41 F. Public Notification Prior to Beginning Construction
42 1. Prior to beginning construction on any block in the project, on a block by block
43 basis, prepare and deliver a notice or flyer of the pending construction to the front
44 door of each residence or business that will be impacted by construction. The notice
45 shall be prepared as follows:
46 a. Post notice or flyer and City of Fort Worth Door Hangers, 7 days prior to
47 beginning any construction activity on each block in the project area.
CITY OF FORT WORTH
ST AND ARD CONSTRUCTION SPECJFICA TION DOCUMENTS
Revi sed March 11 , 2022
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No. I 04552
0135 13-4
S PEC IA L PROJ ECT PROC EDURES
Page 4 of 8
1) Prepare flyer on the Contractor 's letterhead and include the fo llo wing
2 information:
3 a) Name of Project
4 b) City Project No (CPN)
5 c) Scope of Project (i.e. type of construction activity)
6 d) Actual construction duration within the block
7 e) Name of the contractor's foreman and phone number
8 f) Name of the City 's inspector and phone number
9 g) City's after-hours phone number
10 2) A sample of the 'pre-construction notification' flyer is attached as Exhibit
11 A.
12 3) City of Fort Worth Door Hangers wi ll be provided to the Contractor for
13 distribution with their notice.
14 4) Submit schedule showing the construction start and finish time for each
15 block of the project to the inspector.
16 5) Deliver flyer to the City Inspector for review prior to distribution.
17 b. No construction will be allowed to begin on any block until the flyer and door
18 hangers are delivered to all residents of the block.
19 G. Public Notification of Temporary Water Service Interruption durin g Construction
20 1. In the event it becomes necessary to temporarily shut down water service to
21 residents or businesses during construction, prepare and deliver a notice or flyer of
22 the pending interruption to the front door of each affected resident.
23 2. Prepared notice as follows:
24 a. The notification or flyer shall be posted 24 hours prior to the temporary
25 interruption.
26 b. Prepare flyer on the contractor 's letterhead and include the following
27 information:
28 1) Name of the project
29 2) City Project Number
30 3) Date of the interruption of service
31 4) Period the interruption wi ll take place
32 5) Name of the contractor's foreman and phone number
33 6) Name of the C ity 's inspector and phone number
34 c. A sample of the temporary water service interruption notification is attached as
35 Exhibit B.
36 d . Deliver a copy of the temporary interruption notification to the City inspector
37 for review prior to being distributed.
38 e . No interruption of water service can occur until the flyer has been delivered to
39 all affected residents and businesses.
40 f. Electronic versions of the sample flyers can be obtained from the Project
41 Construction Inspector.
42 H. Coordination w ith United States Army Corps of Engineers (USA CE)
43 1. At locations in the Project where construction activities occur in areas where
44 USA CE permits are required, meet all requirements set forth in each designated
45 permit.
46 I. Coordination within Railroad Permit Areas
CITY O F FORT WORTH
ST AND ARD C ONSTRUCTION S PEC IFI CA T!ON DOC UMEN T S
Revi sed March I I , 2022
2022 WATER SERVI CE LEAK
REPAIR CONTRACT
City Project No . I 0455 2
013513-5
SPEC IAL PROJECT PROCEDURES
Page5of8
1. At locations in the project where construction activities occur in areas where
2 railroad permits are required, meet all requirements set forth in each designated
3 railroad permit. This includes, but is not limited to , provisions for:
4 a. Flagmen
5 b. Inspectors
6 c. Safety training
7 d. Additional in surance
8 e. Insurance certificates
9 f. Other employees required to protect the right-of-way and property of the
10 Railroad Company from damage arising out of and/or from the construction of
11 the project. Proper utility clearance procedures shall be used in accordance with
12 the permit guidelines.
13 2. Obtain any supplemental information needed to comply with the railroad's
14 requirements.
15 3. Railroad Flagmen
16 a. Submit receipts to City for verification of working days that railroad flagmen
17 were present on Site.
18 J. Dust Control
19 1. Use acceptable measures to control dust at the Site.
20 a. If water is used to control dust, capture and properly dispose of waste water.
21 b. If wet saw cutting is performed, capture and properl y dispose of slurry.
22 K. E mployee Parking
23 1. Provide parking for employees at locations approved by the City.
24 1.5 SUBMITT ALS [NOT USED]
25 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
26 1. 7 CLOSEOUT SUBMITT ALS [NOT USED]
27 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
28 1.9 QUALITY ASSURANCE [NOT USED]
29 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
30 1.11 FIELD [SITE] CONDITIONS [NOT USED]
31 1.12 WARRANTY [NOT USED]
32 PART 2 -PRODUCTS [NOT USED]
33 PART 3 -EXECUTION [NOT USED]
34 END OF SECTION
35
Revision Log
CITY OF FORT WORTH
ST AND ARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised March I I, 2022
2022 WATERSERVICELEAK
REPAIR CONTRACT
C ity Project No. 104 552
DATE NAME
8/3 1/20 12 D. Johnson
3/11/2022 MOwen
CITY OF FORT WORTH
0 1351 3-6
SPEC IA L PROJECT PRO CEDURES
Page 6 of 8
SUMMARY OF CHA GE
1.4 .B -Added requirement of comp liance with Health and Safety Code, Title 9.
Safety, Subtit le A. Public Safety, Chapter 752. High Voltage Overhead Lines.
1.4 .E -Added Contractor responsibility for obtainin g a TCEQ Air Permit
Remove refere nce s to Air Pollution watch Days and NCTCOG C lean construction
Specification req uirements. Clarify need for Door Hangers und er in addition to
contracto r notification of public.
STANDARD CONSTRUCTION SPECIF ICATIO N DOCUMENTS
Revised March I I, 2022
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No. I 04552
0 1 351 3-7
SPEC IAL PROJECT PROCEDURES
1
2
3
4
5
6 Date :
7
8 CPN No .:
9 Project Name:
10 Mapsco Location :
11 Li mi ts of Const ru ct ion:
12
13
14
15
16
Page 7 of8
EXHIBIT A
(To be printed on Con t racto r's Lett erh ead )
17 THIS IS TO INFORM YOU THAT UNDER A CONTRACT WITH THE CITY OF FORT
18 WORTH , OUR COMPANY WILL WORK ON UTILITY LINES ON OR AROUND YOUR
19 PROPERTY.
20
2 1 CONSTRUCTION WILL BEGIN APPROXIMATELY SEVEN DAYS FROM THE DATE
22 OF THIS NOTICE.
23
24 IF YOU HAVE QUESTIONS ABOUT ACCESS, SECURITY, SA F ETY OR ANY OTHER
25 ISSUE , PLEASE CALL:
26
27
2 8 Mr. <CONTRACTOR'S SUPERINTENDENT> AT <TELEPHONE NO.>
29
30 OR
3 I
32 Mr. <CITY INSPECTOR> AT < TELEPHONE NO .>
33
3 4 AFTER 4:30 PM OR ON WEEKENDS , PLEASE CALL (817) 392 8306
35
36 PL EASE KEEP THIS FL YER HANDY WH EN YOU CALL
37
CITY OF FO RT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMEN TS
Revised March I I, 2022
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No. I 04552
2
3
4
0 1 3513-8
SPECIAL PROJ ECT PROCE DURES
-------
E XHIBITB
DOit NO. XlUCX
Projec:1 Name:
NOTICE OF TEMPORARY WATER SERVICE
INTERRUPTION
DUE TO UTILITY IMPROVEMENTS IN YOUR NEIGHBORHOOD, YOUR
WATER SERVICE WILL BE INTERRUPTED ON _________ _
BETWEEN THE HOURS OF ________ AND ______ _
IF YOU HAVE QUESTIONS ABOUT TIDS SHUT-OUT, PLEASE CALL:
Page 8 of8
MR. --:---:---=-----:-=-:-=-:c--:,,c==:-c---~=-=-AT ____________ _
(CONTRACTORS S_UPERINTENDENT) (TELEPHONE NUMBER)
OR
MR. ______________ AT ____________ _
(CITY INSPECTOR) (TELEPHONE NUMBER)
THIS INCONVENIENCE WILL BE AS SHORT AS POSSIBLE.
THANK YOU,
_____________ ....,CONTRACTOR
CITY O F FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revi sed March 11 , 2022
2022 WATERSERVlCE LEAK
RE PAIR CONTRACT
C ity Project No. I 04552
01 45 23
TES TfN G AND INSPECT ION SERVICE S
PART 1-GENERAL
1.1 SUMMARY
A. Section Includes:
SECTION 01 45 23
TESTING AND INSPECTION SERVICES
1. Testing and inspection services procedures and coordination
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include , but are not necessarily limited to:
Page I of2
1. Division O -Bidding Requirements , Contract Forms and Conditions of the Contract
2. Divi sion 1 -General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various Items bid.
No separate payment will be allowed for this Item.
a. Contractor is responsible for performing, coordinating, and payment of all
Quality Control testing.
b. City is responsible for performing and payment for fir st set of Quality
Assurance testin g .
1) If the first Quality Assurance test performed by the City fails, the
Contractor is responsible for payment of subsequent Quality Assurance
testing until a passing test occurs.
a) Final acceptance will not be issued by City until all required payments
for testing by Contractor have been paid in full.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. Testing
1. Complete testing in accordance with the Contract Documents.
2. Coordination
a . When testing is required to be performed by the City, notify City, sufficiently
in advance, when testing is needed.
b. When testing is required to be completed by the Contractor, notify City,
sufficiently in advance, that testing will be performed.
3. Distribution of Testing Reports
a. Electronic Distribution
1) Confirm development of Project directory for electronic submittals to be
uploaded to the City's document management system, or another external
FTP site approved by the City.
CITY OF FO RT WORTH
STANDARD CONSTRUCTION SP EC IFI CATION DOCUMENTS
Revi sed March 9, 2020
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Proj ec t No . I 04552
OJ 45 23
TESTING AND INSPECTION SERVI CES
Page 2 of 2
2) Upload test reports to designated project directory and notify appropriate
City representatives via email of submittal posting.
3) Hard Copies
a) 1 copy for all submittals submitted to the Project Representative
b. Hard Copy Distribution (if required in lieu of electronic distribution)
1) Tests performed by City
a) Distribute l hard copy to the Contractor
2) Tests performed by the Contractor
a) Distribute 3 hard copies to City 's Project Representative
4. Provide C ity 's Project Representative with trip tickets for each delivered lo ad of
Concrete or Lime material including the following informati on:
a. Name of pit
b. Date of delivery
c. Material delivered
B. Inspection
1. Inspection or lack of in spection does not relieve the Contractor from obligation to
perform work in accordance with the Co ntract Documents.
1.5 SUBMITT ALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 -PRODUCTS [NOT USED]
PART 3-EXECUTION [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHA GE
3/9/2020 D. V. Magana Removed reference to Buzzsaw and noted that e lectronic submittals be uploaded
through the City's document management system.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SP ECIFICATION DOCUMENTS
Revi sed March 9, 20 20
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No. 104552
0 1 50 00 - I
TEMPORARY FACILITIES AND CONTROLS
Page I of4
1 SECTION 01 50 00
2 TEMPORARY FACILITIES AND CONTROLS
3 PARTl-GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. Provide temporary facilitie s and controls needed for th e Work including, but not
7 necessarily limited to:
8 a. Temporary utilities
9 b. Sanitary facilities
10 c. Storage Sheds and Buildings
11 d. Dust control
12 e. Temporary fencing of the construction site
13 B. Deviations from this City of Fort Worth Standard Specification
14 1. None.
15 C. Related Specification Sections include, but are not necessarily limited to :
16 1. Division O -Bidding Requirements, Contract Forms and Conditions of the Contract
17 2. Division 1 -General Requirements
18 1.2 PRICE AND PAYMENT PROCEDURES
19 A. Measurement and Payment
20 1. Work associated with this Item is considered subsidiary to the various Items bid.
21 No separate payment wi ll be allowed for this Item.
22 1.3 REFERENCES [NOT USED]
23 1.4 ADMINISTRATIVE REQUIREMENTS
24 A. Temporary Utilities
25 1. Obtaining Temporary Service
26 a. Make arrangements with utility service companies for temporary services.
27 b . Abide by rules and regulations of utility service companies or authorities
28 having jurisdiction.
29 c. Be responsible for utility service costs until Work is approved for Final
30 Acceptance .
31 1) Included are fuel , power, light, heat and other utility services nece ssary for
32 exe cution, completion , testing and initial operation of Work.
33 2. Water
34 a. Contractor to provide water required for and in connection with Work to be
35 performed and for specified tests of piping, equipment, devices or other use as
36 required for the completion of the Work.
37 b. Provide and maintain adequate supply of potable water for domestic
38 consumption by Contractor personnel and City's Project Representatives.
39 c. Coordination
40 1) Contact City 1 week before water for construction is desired
CITY OF FORT WORTH
STANDARD CONSTRU CTION SPECIFICATION DOCUMENTS
Revised Jul y 1, 20 1 1
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No. I 04552
01 5000-2
TEMPORARY FACILITIES AND CONTROLS
Page 2 of 4
d . Contractor P ay ment for Co nstruction Water
2 1) Obtain construction water meter from City for payment as billed by City's
3 established rates.
4 3. E lectricity and Lighting
5 a. Provide and pay for electric powered service as required for Work, including
6 tes ting of Work.
7 1) Provide power for li g hting, operation of equipment, or other use.
8 b. Electric power service includes temporary power service or generator to
9 maintain operations durin g scheduled shutdown.
10 4 . Telephone
11 a. Provide emergency telephone service at Site for use by Contractor pe rsonnel
12 and others performing work or furnishin g services at Site.
13 5. Temporary Heat and Ventilation
14 a. Provide temporary heat as necessary for protection or completion of Work.
15 b. Provide temporary heat and ventilation to ass ure safe working conditions.
16 B . Sanitary Facilities
17 1. Provide and maintain sanitary faci lities for persons on Site.
18 a. Comply with regulations of State and local departments of health .
19 2 . E nforce use of sanitary facilities by construction personnel at job site.
20 a. E nclose and anchor sanitary facilities .
21 b. No discharge will be allowed from these facilities.
22 c . Collect and store sewage and waste so as not to cause nuisance or health
23 problem .
24 d . Haul sewage and waste off-site at no le ss than weekly intervals and properly
25 di s pose in accordance with applicable regul ation.
26 3 . Locate facilities near Work Site and keep clean and maintained throughout Project.
27 4 . Remove facilities at completion of Project
28 C. Storage Sheds and Buildings
29 1. Provide adequately ventilated , watertight, weatherproof storage facilitie s with floor
30 above ground level for materials and equipment susceptible to weather damage .
31 2. Storage of materials not susceptible to weather damage may be on blocks off
32 ground.
33 3 . Store material s in a neat and orderly manner.
34 a. Place materials and equipment to permit easy access for identification,
35 inspection and inventory.
36 4. Equip building with lockable doors and lighting , and provide electrical service for
37 equipment space heaters and heating or ventilation as necessary to provide storage
38 environments acceptable to specified manufacturers.
39 5. Fill and grade site for temporary structures to provide drainage away from
40 temporary and existing buildings.
41 6. Remove building from site prior to Final Acceptance .
42 D. Temporary Fencing
43 1. Provide and maintain for the duration or construction when required in contract
44 documents
45 E. Dust Control
CITY OF FORT WORTH
STANDARD CONSTRUCTIO N S PEC IFICATION DOCUMENTS
Rev ised Jul y I, 20 I I
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No. 104 552
0 1 50 00 - 3
TEMPORARY FAC ILITI ES AN D CONTROLS
Page 3 of4
1. Contractor is responsible for maintaining dust control through the du ration of the
2 project.
3 a. Contractor remains on-call at a ll times
4 b . Must respond in a timely manner
5 F. Temporary Protection of Construction
6 1. Contractor or s ub co ntractors are respo ns ibl e fo r protecting Work from damage due
7 to weather.
8 1.5 SUBMITT ALS [NOT USED]
9 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
10 1.7 CLOSEOUT SUBMITTALS [NOT USED]
11 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
12 1.9 QUALITY ASSURANCE [NOT USED]
13 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
14 1.11 FIELD [SITE] CONDITIONS [NOT USED]
15 1.12 WARRANTY [NOT USED]
16 PART 2 -PRODUCTS [NOT USED]
17 PART 3 -EXECUTION [NOT USED]
18 3.1 INSTALLERS [NOT USED]
19 3.2 EXAMINATION [NOT USED]
20 3.3 PREPARATION [NOT USED]
2 1 3.4 INSTALLATION
22 A. Temporary Fac iliti es
23 1. Maintain all temporary facilities for duration of construction activities as n ee ded.
24 3.5 [REPAIR] / [RESTORATION]
25 3.6 RE-INSTALLATION
26 3.7 FIELD [oR] SITE QUALITY CONTROL [NOT USED]
27 3.8 SYSTEM STARTUP [NOT USED]
28 3.9 ADJUSTING [NOT USED]
29 3.10 CLEANING [NOT USED]
30 3.11 CLOSEOUT ACTIVITIES
31 A. Temporary Fac iliti es
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECI FICATION DOCUMENTS
Revi sed Jul y I, 20 II
2022 WATER SERVI CE LEAK
REPAIR CONTRACT
City Project No . I 04552
01 50 00 -4
TEMPORARY FACILITIES AND CONTROLS
Page 4 of4
1. Remove all temporary facilities and restore area after completion of the Work, to a
2 condition equal to or better than prior to start of Work.
3 3.12 PROTECTION [NOT USED]
4 3.13 MAINTENANCE [NOT USED]
5 3.14 ATTACHMENTS [NOT USED]
6 END OF SECTION
7
8
Revision Log
DATE NAME
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July I , 20 I I
SUMMARY OF CHANGE
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No. I 04552
01 55 26 -I
STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL
Page I of 3
l SECTION 01 55 26
2 STREET USE P E RMIT AND MODIFICATIONS TO TRAFFIC CONTROL
3 PARTl-GENERAL
4 1.1 SUMMARY
5 A. Section Inc lu des:
6 1. Administrative procedures for:
7 a. Street Use Permit
8 b . Modification of approved traffic control
9 c. Removal of Street Signs
10 B. Deviations from this City ofFortWorth Standard Specification
11 1. 1.2PRICEANDPAYMENTPROCEDURES-
12 Given the nature of this contract Street Use Permits will be paid for at the pre-bid price
of $100.00 each on an as needed basis. Additionally, Traffic Control Plans will be
categorized as Residential, Arterial/ Industrial and Major Arterial/ Industrial due to
the varying degrees of Traffic Control required in these different road types.
13 C. Related Specification Sections include , but are not necessarily limit ed to:
14 1. Division 0 -Bidding Requirements , Contract Forms and Conditions of the Contract
15 2. Division 1 -General Requirements
16 3. Section 34 71 13 -Traffic Contro l
17 1.2 PRICE AND PAYMENT PROCEDURES
18 A. Measurement and Payment
19 I. Work associated with this Item is considered subsidiary to the various Items bid.
20 No separate payment will be allowed for thi s Item.
2 1 1.3 REFERENCES
22 A . Reference Standards
23 1. Reference standards cited in this specification refer to the current reference standard
24 published at the time of the latest revision date logged at the end ofthis
25 specification, unless a date is specifical ly cited.
26 2. Texas Manual on Uniform Traffic Contro l Devices (TMUTCD).
27 1.4 ADMINISTRATIVE REQUIREMENTS
28 A. Traffic Control
29 1. General
30 a. Contractor shall minimize lane clo s ure s and impact to vehicular/pedestrian
31 traffic.
32 b . When traffic control plans are included in the Drawings, provide Traffic
33 Contro l in accordance with Drawings and Section 34 71 13 .
34 c. When traffic control plans are not included in the Drawings, prepare traffic
35 control plans in accordance with Section 34 71 13 and submit to City for
36 review .
37 I) Allow minimum 10 working days for review of propose d Traffic Control.
CITY OF FORT WORTH
ST AND ARD CONSTRUCT ION SPECIFICATION DOCUMENTS
Revised March 22, 202 1
2022 WATER SERVICE LEAK
REPAIR CONTRACT
C ity Proj ect No. 104552
0 1 5526-2
STREET USE PE RMIT AND MODIFICATIONS TO TRAFFIC CONTROL
Page 2 of 3
1 2) A traffic control "Ty pical " published by City of Fort Worth, the Texas
2 Manual Unified Traffic Control Devices (TMUTCD) or Texas Department
3 of Transportation (TxDOT) can be used as an alternative to preparing
4 project/site specific traffic control plan if the typical is applicable to the
5 specific project/site.
6 B. Street Use Permit
7 1. Prior to install ation of Traffic Control, a City Street Use Permit is required .
8 a . To obtain Street Use Permit, submit Traffic Control Plans to City
9 Transportation and Public Works Department.
IO 1) Allow a minimum of 5 working days for permit review.
I I 2) It is the Contractor's responsibility to coordinate review of Traffic Control
12 plans for Street Use Permit, such that construction is not delayed.
13 C. Modification to Approved Traffic Control
14 1. Prior to installation traffic control :
15 a . Submit revised traffic control plans to City Department Transportation and
16 Public Works Department.
17 1) Revise Traffic Control plans in accordance with Section 34 7 I 13.
18 2) A ll ow minimum 5 working day s for review of revised Traffic Control.
19 3) It is the Contractor's responsibility to coordinate review of Traffic Control
20 plans for Street Use Permit, such that construction is not delayed.
21 D. Removal of Street Sign
22 1. If it is determined that a street s ign mus t be re moved for construction, then contact
23 C ity Transportation and Public Works D e partment, Signs and Markings Division to
~ re~w~s~.
25 E . Temporary Signage
26 1. In the case of re g ulatory signs, replace permanent sign with temporary sign meeting
27 requirements of the latest edition of th e Texas Manual on Uniform Traffic Control
28 Devices (MUTCD).
29 2. lns tal 1 temporary s ign before the removal of permanent s ign.
30 3. When construction is complete, to the extent that the permanent sign can be
31 reinstalled, contact the City Transportation and Public Works Department, Signs
32 and Markings Division, to reinstall the permanent sign.
33 F. Traffic Control Standards
34 I. Traffic Control Standards can be found on the City's website .
35 1.5 SUBMITTALS [NOTUSED]
36 A. Submit all required documentation to City's Project Representative.
CITY OF FORT WORTH
ST AND ARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revi se d M arch 22, 2021
2022 WATER SERVICE LEAK
REP AIR CONTRACT
City Proj ect No. 104552
0 1 5526 -3
STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL
Page 3 of3
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
2 1.7 CLOSEOUT SUBMITTALS [NOT USED]
3 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
4 1.9 QUALITY ASSURANCE [NOT USED]
5 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
6 1.11 FIELD [SITE] CONDITIONS [NOT USED]
7 1.12 WARRANTY [NOT USED]
8 PART 2 -PRODUCTS [NOT USED]
9 PART 3 -EXECUTION [NOT USED]
10 END OF SECTION
11
Revision Log
DATE NAME SUMMARY OF CHANGE
1.4 A. Added language to emph asize minimizing of lan e closures and impact to
12
traffic.
3 /22/202 1 MOwen
1.4 A. l. c. Added language to a ll ow for use of published traffic control "Typicals" if
app licable to specific project/site.
1.4 F. I) Removed reference to Buzzsaw
1.5 Added langu age re: su bmitta l of permit
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised March 22 , 2021
2022 WATER SERVlCE LEAK
REP AIR CONTRACT
City Proj ect No . 104552
01 57 I 3 -I
STORM WATER POLLUTION PREVENTION
Page I of3
SECTION 01 57 13
2 STORM WATER POLLUTION PREVENTION
3 PARTl-GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. Procedures for Storm Water Pollution Prevention Plans
7 B. Deviations from this City of Fort Worth Standard Specification
8 1. None.
9 C. Related Specification Sections include, but are not necessarily limited to:
10 I. Division O -Bidding Requirements, Contract Forms and Conditions of the
11 Contract
12 2. Division 1 -General Requirements
13 3. Section 31 25 00 -Erosion and Sediment Control
14 1.2 PRICE AND PAYMENT PROCEDURES
15 A. Measurement and Payment
16 1. Construction Activities resulting in less than I acre of disturbance
17 a . Work associated with this Item is considered subsidiary to the various Items
18 bid. No separate payment will be allowed for this Item .
19 2. Construction Activities resulting in greater than 1 acre of disturbance
20 a. Measurement and Payment shall be in accordance with Section 31 25 00.
21 1.3 REFERENCES
22 A. Abbreviations and Acronyms
23 1. Notice oflntent: NOi
24 2 . Notice of Termination: NOT
25 3. Storm Water Pollution Prevention Plan: SWPPP
26 4. Texas Commission on Environmental Quality: TCEQ
27 5. Notice of Change: NOC
28 A. Reference Standards
29 1. Reference standards cited in this Specification refer to the current reference
30 standard published at the time of the latest revision date logged at the end of this
3 1 Specification, unless a date is specifically cited.
32 2. Integrated Storm Management (iSWM) Technical Manual for Construction
33 Controls
34 1.4 ADMINISTRATIVE REQUIREMENTS
35 A. General
36 1. Contractor is responsible for resolution and payment of any fines issued associated
37 with compliance to Stormwater Pollution Prevention Plan.
CITY OF FORT WORTH
STANDARD C ONSTRUCTION SPECIFICATION DOCUMENTS
Re v ised July I , 20 II
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No. I 04552
B. Construction Activities re sulting in:
015713 -2
STORM WATER POLLUTION PREV ENTIO N
Page 2 of3
2 1. Less than 1 acre of disturban ce
3 a . Provide erosion and sediment control in accordance with Section 31 25 00 and
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
3 1
32
33
34
35
36
37
38
39
Drawings .
2. 1 to le ss than 5 ac res of di st urb ance
a . Texas Pollutant Dis charge Elimin at ion System (TPDES) General Construction
Permit is required
b. Complete SWPPP in accordance with TCEQ requirements
1) TCEQ Small Construction Site Notice Required under ge neral permit
TXR150000
a) Sign and post at job site
b) Prior to Preconstruction Meeting, send 1 copy to City Department of
Transportation and Public Works , Environmental Division , (817) 392-
6088.
2) Provide erosion and sediment control in accordance with:
a) Section 31 25 00
b) The Drawings
c) TXR150000 General Permit
d) SWPPP
e) TCEQ requirem e nts
3. 5 acres or more of Disturbance
a . Texas Pollutant Discharge E limination System (TPDE S) General Construction
Permit is required
b . Complete SWPPP in accordance with TCEQ requirements
1) Prepare a TCEQ NOI form and submit to TCEQ along with required fee
a) Sign and post at job s ite
b) Send copy to City Department of Transportation and Public Works,
E nvironmental Di v is ion , (817) 392-6088.
2) TCEQ Notice of Change required if making changes or updates to NOI
3) Provide erosion and se diment control in accordance with:
a) Section 31 25 00
b) The Drawings
c) TXR150000 General Permit
d) SWPPP
e) TCEQ requirements
4) Once the project has been completed and all the closeout requirements of
TCEQ have been met a TCEQ Notice of Termination can be s ubmitted .
a) Send copy to City Department of Transportation and Public Works ,
E nvironmental Division , (817) 392-6088.
40 1.5 SUBMITTALS
41 A. SWPPP
42 1. Submit in accordance with Section 01 33 00 , except as stated herein.
43 a. Prior to the Preconstruction Meeting, submit a draft copy of SWPPP to the City
44 as follows:
45 1) 1 copy to the City Project Manager
46 a) City Project Manager will forward to the City Department of
47 Transportation and Public Works , Environmental Division for review
CITY OF FORT WORTH
STANDARD CONSTRUCT IO N SPEClFICATIO N DOCUMENTS
Revi sed Jul y I, 20 11
2022 WATER SERVIC E LEAK
REPAIR CONTRACT
City Project No . I 04552
01 57 13 -3
STORM WATER POLLUTION PREVENTION
Page 3 of3
B . Modified SWPPP
2 I. lfthe SWPPP is revised during construction , res ubmit modified SWPPP to the City
3 in accordance with Section 01 33 00 .
4 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
5 1.7 CLOSEOUT SUBMITTALS [NOT USED]
6 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
7 1.9 QUALITY ASSURANCE [NOT USED]
8 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
9 1.11 FIELD [SITE] CONDITIONS [NOT USED]
10 1.12 WARRANTY [NOT USED]
11 PART 2 -PRODUCTS [NOT USED]
12 PART 3 -EXECUTION [NOT USED]
13 END OF SECTION
14
15
Revision Log
D ATE NAME
CITY OF FORT WORTH
STANDARD CONSTRUCT ION SPECIFICATION DOCUMENTS
Revised Jul y I , 20 I 1
SUMMARY OF CHANGE
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No. 104552
1 SECTION 0158 13
2 TEMPORARY PROJECT SIGNAGE
3 PARTl-GENERAL
4 1.1 SUMMARY
5 A. Section Includes :
6 l. Temporary Project Signage Requirements
01 58 13 - I
TE MPORARY PROJECT SIGNAGE
Page I of3
7 B. Deviations from this City of Fort Worth Standard Specification
8 1. None .
9 C. Related Specification Sections include, but are not necessarily limited to:
10 I. Division O -Bidding Requirements , Contract Forms and Conditions of the Contract
11 2. Division 1 -General Requirements
12 1.2 PRICE AND PAYMENT PROCEDURES
13 A. Measurem e nt and Payment
14 1. Work a ss ociated with this Item is considered subsidiary to the various Items bid.
15 No separate payment will be a ll owed for this Item.
16 1.3 REFERENCES [NOT USED]
17 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED]
18 1.5 SUBMITT ALS [NOT USED]
19 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
20 1.7 CLOSEOUT SUBMITTALS [NOT USED]
21 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
22 1.9 QUALITY ASSURANCE [NOT USED]
23 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
24 1.11 FIELD [SITE] CONDITIONS [NOT USED]
25 1.12 WARRANTY [NOT USED]
26 PART 2 -PRODUCTS
27 2.1 OWNER-FURNISHED [oR] OWNER-SUPPLIEDPRODUCTS [NOT USED]
28 2.2 EQUIPMENT, PRODUCT TYPES, AND MATERIALS
29 A. Design Criteria
30 1. Provide free standing Project Designation Sign in accordance with City's Standard
31 Details for project signs.
C ITY OF FORT WORTH
ST AND ARD CONSTRUCTIO N SPECIFICATION DOCUMENTS
Revised Jul y 1,20 1 1
2022 WATER SERVICE LEAK
REPAIR CONTRACT
C ity Project No. I 04552
B. Materials
2 1. S ign
0158 13-2
TEMPORARY PROJECT SIGNAGE
Page 2 of3
3 a. Constru cted of ¾-inch fir plywood, grade A -C (exterior) or better
4 2.3 ACCESSORIES [NOT USED]
5 2.4 SOURCE QUALITY CONTROL [NOT USED]
6 PART 3 -EXECUTION
7 3.1 INSTALLERS [NOT USED]
8 3.2 EXAM NATION [NOT USED]
9 3.3 PREPARATION [NOT USED]
10 3.4 INSTALLATION
11 A. General
12 1. Provide vertical in stallation at extents of proj ect.
13 2. Relocate s ign as needed , upon req ue st of the C ity .
14 B. Mounting options
15 a . Skids
16 b. Posts
17 c. Barri cad e
18 3.5 REPAIR/ RESTORATION [NOT USED]
19 3.6 RE-INSTALLATION [NOT USED]
20 3.7 FIELD [oR] SITE QUALITY CONTROL [NOT USED]
21 3.8 SYSTEM STARTUP [NOT USED]
22 3.9 ADJUSTING [NOT USED]
23 3.10 CLEANING [NOT USED]
24 3.11 CLOSEOUT ACTIVITIES [NOT USED]
25 3.12 PROTECTION [NOT USED]
26 3.13 MAINTENANCE
27 A. General
28 1. Maintenance will include painting and repairs as need ed or directed by the City .
29 3.14 ATTACHMENTS [NOT USED]
3 0 END OF SECTION
31
CITY OF FORT WORTH
ST AND ARD CONSTRUCTION SPECIFICAT ION DOCUMENTS
Revi sed July I , 2011
2022 WATER SERYJCE LEAK
REPAIR CONTRACT
C ity Project No. I 04552
2
015813-3
TEMPORARY PROJECT SIGNAGE
Page 3 of3
Rev is ion Log
D ATE NAME
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFI CATI ON DOCUMENTS
Revise d July I, 20 I I
SUMMARY OF CHANGE
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No . I 04552
0 1 6000
PRODUCT REQUIREMEN TS
PART 1 -GENERAL
1.1 SUMMARY
A. Section Includes:
SECTION 01 60 00
PRODUCT REQUIREMENTS
1. References for Product Requirements and City Standard Products List
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
Page I of2
1. Division O -Bidding Requirements , Contract Forms and Conditions of the Contract
2. Division 1 -General Requirements
1.2 PRICE AND PAYMENT PROCEDURES [NOT USED]
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. A list of City approved products for use is available through the City's website at:
https://apps.fortworthtexas.gov/ProjectResources/ and following the directory path ;
02 -Construction Documents/Standard Products List
B. Only products specifically included on City's Standard Product List in these Contract
Documents shall be allowed for use on the Project.
1. Any subsequently approved products will only be allowed for use upon specific
approval by the City.
C. Any specific product requirements in the Contract Documents supersede similar
products included on the City 's Standard Product List.
1. The City reserves the right to not al low products to be used for certain projects even
though the product is listed on the City 's Standard Product List.
D. Although a specific product is included on City 's Standard Product Li st , not all
products from that manufacturer are approved for use , including but not limited to, that
manufacturer's standard product.
E. See Section 01 33 00 for submittal requirements of Product Data included on City 's
Standard Product List.
1.5 SUBMITT ALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED)
C ITY OF FORT WORTH
STANDARD CON STRUCTION SPECIFICATION DOCUMEN TS
Re v ised March 9, 2020
2022 WATER SERVI CE LEAK
REPAIR CO N TRACT
Ci ty Proj ect N o . I 04552
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 -PRODUCTS [NOT USED]
PART 3-EXECUTION [NOT USED]
END OF SECTION
Revision Log
01 60 00
PRODUCT REQUIREMENTS
Page2 of 2
D ATE NAME SUMMARY OF CHANGE
10/12/12 D. Johnson Modified Location of C ity's Standard Product List
3/9/2020 D .V. Magana Removed reference to Buzzsaw and noted that the City appro ved products li st is
accessib le through the City 's website.
CITY OF FORT WORTH
STANDARD CONSTRUCT ION SPECIFICATION DOCUMENTS
Revised March 9, 2020
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No. I 04552
0 1 66 00 - I
PRODU C T STORAGE AND HANDLIN G RE Q UIREMEN TS
Page I of4
1 SECTION 01 66 00
2 PRODUCT STORAGE AND HANDLING REQUIREMENTS
3 PARTl-GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. Scheduling of product delivery
7 2. Packaging of products for delivery
8 3. Protection of products against damage from:
9 a . Handling
10 b. Exposure to elements or harsh environments
11 B. Deviations from this City of Fort Worth Standard Specification
12 1. None.
13 C. Related Specification Sections include, but are not necessarily limited to:
14 1. Division O -Bidding Requirements, Contract Forms and Conditions of the Contract
15 2. Division 1 -General Requirements
16 1.2 PRICE AND PAYMENT PROCEDURES
17 A. Measurement and Payment
18 1. Work associated with this Item is considered subsidiary to the various Items bid.
19 No separate payment will be allowed for this Item.
20 1.3 REFERENCES [NOT USED]
21 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED]
22 1.5 SUBMITT ALS [NOT USED]
23 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
24 1.7 CLOSEOUT SUBMITTALS [NOT USED]
25 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
26 1.9 QUALITY ASSURANCE [NOT USED]
27 1.10 DELIVERY AND HANDLING
28 A. Delivery Requirements
29 1. Schedule delivery of products or equipment as required to allow timely installation
30 and to avoid prolonged storage.
31 2. Provide appropriate personnel and equipment to receive deliveries.
32 3. Delivery trucks will not be permitted to wait extended periods of time on the Site
33 for personnel or equipment to receive the delivery.
C ITY OF FORT WORTH
STANDARD CON STRUC TION SPEClFICATION DOCUMENTS
R evi sed Jul y I , 20 11
2022 WATER SERVJCE LEAK
REPAIR CONTRACT
C ity Proj e ct N o . I 04552
01 66 00 -2
PROD UCT STORA GE AND HANDLING REQUIREMENTS
Pag e 2 of 4
4. Deliver products or equipment in manufacturer's original unbroken cartons or other
2 containers designed and constructed to protect the contents from physical or
3 environmental damage.
4 5. Clearly and fully mark and identify as to manufacturer, item and installation
5 location.
6 6. Provide manufacturer's instructions for storage and handling.
7 B. Handling Requirements
8 1. Handle products or equipment in accordance with these Contract Documents and
9 manufacturer's recommendations and instructions.
10 C. Storage Requirements
11 1. Store materials in accordance with manufacturer's recommendations and
12 requirements of these Specifications.
13 2. Make necessary provisions for safe storage of materials and equipment.
14 a. Place loose soil materials and materials to be incorporated into Work to prevent
15 damage to any part of Work or existing facilities and to maintain free access at
16 all times to all parts of Work and to utility service company installations in
17 vicinity of Work.
18 3. Keep materials and equipment neatly and compactly stored in locations that will
19 cause minimum inconvenience to other contractors, public travel, adjoining owners,
20 tenants and occupants.
21 a. Arrange storage to provide easy access for inspection.
22 4. Restrict storage to areas available on construction site for storage of material and
23 equipment as shown on Drawings, or approved by City's Project Representative .
24 5. Provide off-site storage and protection when on-site storage is not adequate.
25 a. Provide addresses of and access to off-s ite storage locations for inspection by
26 City's Project Representative.
27 6. Do not use lawns , grass plots or other private property for storage purposes without
28 written permission of owner or other person in possession or control of premises.
29 7. Store in manufacturers' unopened containers.
30 8. Neatly, safely and compactly stack materials delivered and stored along line of
31 Work to avoid inconvenience and damage to property owners and general public
32 and maintain at least 3 feet from fire hydrant.
33 9 . Keep public and private driveways and street crossings open.
34 10 . Repair or replace damaged lawns, sidewalks, streets or other improvements to
35 satisfaction of City's Project Representative.
36 a. Total length which materials may be distributed along route of construction at
37 one time is 1,000 linear feet , unless otherwise approved in writing by City's
38 Project Representative.
CITY O F FORT WORTH
STANDARD CON STRUCTION SP EC IFI CATION DO C UME NT S
Revi sed Jul y 1, 2011
2022 WATER SERVI CE LE AK
REPAIR CO NTRACT
City Project No. I 04552
01 66 00 -3
PRODUCT STORAGE AND HANDLING REQUIREMENTS
Page 3 of4
1.11 FIELD [SITE] CONDITIONS [NOT USED]
2 1.12 WARRANTY [NOT USED]
3 PART 2 -PRODUCTS [NOT USED]
4 PART 3 -EXECUTION
5 3.1 INSTALLERS [NOT USED]
6 3.2 EXAMINATION [NOT USED]
7 3.3 PREPARATION [NOT USED]
8 3.4 ERECTION [NOT USED]
9 3.5 REPAIR/ RESTORATION [NOT USED]
10 3.6 RE-INSTALLATION [NOT USED]
11 3.7 FIELD [oR] SITE QUALITY CONTROL
12 A. Tests and Inspections
13 1. Inspect all products or equipment delivered to the site prior to unloading .
14 B. Non-Conforming Work
15 1. Reject all products or equipment that are damaged , u sed or in any other way
16 unsatisfactory for use on the project.
17 3.8 SYSTEM STARTUP [NOT USED]
18 3.9 ADJUSTING [NOT USED]
19 3.10 CLEANING [NOT USED]
20 3.11 CLOSEOUT ACTIVITIES [NOT USED]
21 3.12 PROTECTION
22 A. Protect all products or equipment in accordance with manufacturer's written directions.
23 B. Store products or equipment in location to avoid physical damage to items while in
24 storage.
25 C. Protect equipment from exposure to elements and keep thoroughly dry if required by
26 the manufacturer.
27 3.13 MAINTENANCE [NOT USED]
28 3.14 ATTACHMENTS [NOT USED]
29 END OF SECTION
30
C ITY OF FO RT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised Jul y I , 20 I I
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Proj ect No. I 04552
0 1 66 00 -4
PRODUCT STORAGE AND HANDUNG REQUIREMENTS
Page 4 of4
Rev is io n Log
DATE NAME
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Rev ised Jul y I , 20 11
SUMMARY OF CHANGE
2022 WATER SERV ICE LEAK
REPAIR CONTRACT
City Proj ec t No. I 04552
0 1 70 00 - I
MOBILlZATION AN D REMOBfLIZATfON
SECTION 01 70 00
2 MOBILIZATION AND REMOBILIZATION
3 PARTl-GENERAL
4 1.1 SUMMARY
5 A. Section lncludes:
6 1. Mobilization and Demobilization
7 a. Mobilization
Page I of4
8 I) Transportation of Contractor's personnel, equipment, and operating supplies
9 to the Site
LO 2) Establishment of necessary general facilities for the Contractor's operation
l l at the Site
12 3) Premiums paid for performance and payment bonds
13 4) Transportation of Contractor's personnel, equipment, and operating supplies
14 to another location within the designated Site
15 5) Relocation of necessary general facilities for the Contractor's operation
16 from I location to another location on the Site.
17 b. Demobilization
18 1) Transportation of Contractor's personnel , equipment, and operating supplies
l 9 away from the Site including disassembly
20 2) Site Clean-up
21 3) Removal of all buildings and/or other facilities assembled at the Site for this
22 Contract
23 c. Mobilization and Demobilization do not include activities for specific items of
24 work that are for which payment is provided elsewhere in the contract.
25 2. Remobilization
26
27
28
29
30
3 1
32
33
34
35
36
37
3 8
39
40
41
42
43
44
45
a. Remobilization for Suspension of Work specifically required in the Contract
Documents or as required by City includes:
I) Demobilization
a) Transportation of Contractor's personnel , equipment, and operating
supplies from the Site including disassembly or temporarily securing
equipment, supplies, and other facilities as des ignated by the Contract
Documents necessary to suspend the Work.
b) Site Clean-up as designate d in the Contract Documents
2) Remobilization
a) Transportation of Contractor's personnel , equipment, and operating
supplies to the Site necessary to resume the Work.
b) Establishment of necessary general facilities for the Contractor's
operation at the Site necessary to resume the Work.
3) No Payments wi ll be made for:
a) Mobilization and Demobilization from one location to another on the
Site in the normal progress of performing the Work.
b) Stand-by or idle time
c) Lost profits
3. Mobilizations and Demobilization for Miscellaneous Projects
a. Mobilization and Demobilization
CITY OF FORT WORTH
ST AND ARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised December 20, 2012
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No. I 04552
01 70 00 -2
MOBILI ZATION AND REMOBI LI ZATION
Page 2 of 4
1) Mobilization shall cons ist of the activ iti es and cost on a Work Order basis
2 necessary for:
3 a) Transportation of Contractor's p ersonnel , equipment, and operating
4 suppli es to the S it e for th e iss ued Work Ord er.
5 b) Establi shm e nt of necessary ge neral facilities for the Contractor's
6 operation at th e Site for the iss ued Work Order
7 2) D e mobili zat ion s hall consist of the activities and cost necessary for:
8 a) T ran s portation of Contractor 's p ersonnel , e quipment, and operating
9 s upplies from th e Site including di sassembly for each iss ued Work
10 Ord e r
11 b) Site Clean-up for eac h is sued Work Order
12 c) Removal of all buildings or other fac ilities assembled at th e Site for
13 each Work Oder
14 b. Mobilization and Demobili zation do not include activiti es for specific items of
15 work for which pay ment is provided elsewhere in the contract.
16 4. Emergency Mobilizations and Demobilization for Miscellaneous Proj ects
17 a. A Mobilization for Mi scellaneo us Projects when directed by the City and the
18 mobili zation occurs within 24 hours of the iss uance of the Work Order.
19 B. Deviations from thi s City of Fort Worth Standard Specification
20 1. 1.2-A-4 Mobilization and Demobilization for Miscellaneous Projects -
21 1.2-A-5 Emergency Mobilization and Demobilization for Miscellaneous
22 Projects -Although this contract is considered a miscellaneous type contract,
23 all mobilizations and demobilizations will be considered subsidiary to the work
24 to be performed.
25 C. Re lated Specification Sections include, but are not necessarily limite d to:
26 1. Division O -Bidding Require ments, Contract Forms a nd Conditions of the Contract
27 2. Division 1 -General Requirements
2 8 1.2 PRICE AND PAYMENT PROCEDURES
29 A . Measurement and Payment
30 1. Mobilization and Demobilization
31 a. Measure
32 1) This Item is considered subsidiary to the various Item s bid.
33 b . Payment
34 1) The work performed and material s furnished in accordance with this Item
35 are subsidiary to the various Items bid and no other compensation will be
36 allowed.
37 2. Remobilization for suspension of Work as s pecificall y require d in the Contract
38 Documents
39 a. Measurement
40 1) Measurement for this Item shall be per each remobilization performed.
41 b . Payment
42 1) The work performed and materials furnished in accordance with this Item
43 and meas ured as provided under "Measurement" will be paid for at the unit
44 price per each "Specified Remobili zat ion " in accordance with Contract
45 Documents.
46 c. The price shall include:
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPEC l FICATION DO CUMENTS
Revi se d Dece mb er 20 , 2012
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No . I 04552
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
01 70 00 -3
MOBILI Z ATION AND REMOBILIZATIO N
Page 3 of 4
1) Demobilization as described in Section 1.1.A .2.a.l)
2) Remobilization as described in Section 1.1.A.2.a.2)
d. No payments will be made for standby, idle time, or lost profits associated this
Item.
3. Remobilization for suspension of Work as required by City
a. Measurement and Payment
1) This shall be submitted as a Contract Claim in accordance with Article 10
of Section 00 72 00.
2) No payments will be made for standby, idle time, or lost profits associated
with this Item.
4. Mobilizations and Demobilizations for Miscellaneous Projects
a. Measurement
1) Measurement for this Item shall be for each Mobilization and
Demobilization required by the Contract Documents
b. Payment
1) The Work performed and materials furnished in accordance with this Item
and measured as provided under "Measurement" will be paid for at the unit
price per each "Work Order Mobilization" in accordance with Contract
Documents. Demobilization shall be considered subsidiary to mobilization
and shall not be paid for separately.
c. The price shall include:
1) Mobilization as described in Section 1.1.A .3.a.1)
2) Demobilization as described in Section 1.1.A.3 .a.2)
d. No payments will be made for standby, idle time, or lost profits associated this
Item.
5. E mergency Mobilizations and Demobilizations for Miscellaneous Projects
a. Measurement
1) Measurement for this Item shall be for each Mobilization and
Demobilization re quired by the Contract Documents
b. Payment
1) The Work performed and materials furnished in accordance with this Item
and measured as provided under "Measurement" will be paid for at the unit
price per each "Work Order Emergency Mobilization" in accordance with
Contract Documents. Demobilization shall be considered subsidiary to
mobilization and shall not be paid for separately.
c. The price shall include
1) Mobilization as described in Section 1.1.A.4.a)
2) Demobilization as described in Section 1.1.A.3.a.2)
d . No payments will be made for standby, idle time, or lo st profits associated this
Item.
41 1.3 REFERENCES [NOT USED]
42 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED]
43 1.5 SUBMITT ALS [NOT USED]
44 1.6 INFORMATIONAL SUBMITTALS [NOT USED]
45 1.7 CLOSEOUT SUBMITTALS [NOT USED]
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFI CATION DOCUMENTS
Revised December 20, 20 I 2
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No. 104552
OJ 70 00 - 4
MOB ILLZATION AND REMOBILL ZATION
1.8 MAINTENANCE MATERIAL SUBMITT ALS [NOT USED]
2 1.9 QUALITY ASSURANCE [NOT USED]
3 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
4 1.11 FIELD [SITE] CONDITIONS [NOT USED]
5 1.12 WARRANTY [NOT USED]
6 PART 2-PRODUCTS [NOT USED]
7 PART 3-EXECUTION [NOT USED]
8 END OF SECTION
9
Revi s ion Log
DATE NAME
CITY OF FORT WORTH
STANDARD CONSTRUCTION SP ECIFICATION DO CUMENTS
Revi sed December 20 , 20 I 2
SUMMARY OF CHA GE
Pag e 4 of4
202 2 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No . I 04552
OJ 71 23 -I
CONSTRUC TfON STAKING AND SURVEY
Page I of8
PART 1 -GENERAL
1.1 SUMMARY
SECTION 0 1 71 23
CONSTRUCTION STAKING AND SURVEY
A. Section Includes:
1. Requirements for construction staking and construction s urvey
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division O -Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 -General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Construction Staking
a. Measurement
1) Measurement for this Item shall be by lump sum.
b. Payment
1) The work performed and the materials furnished in accordance with this
Item shall be paid for at the lump sum price bid for "Construction Staking".
2) Payment for "Construction Staking" shall be made in partial payments
prorated by work completed compared to total work included in the lump
sum item.
c. The price bid shall include, but not be limited to the following:
1) Verification ofcontrol data provided by City.
2) Placement, maintenance and replacement ofrequired stakes and markings
in the field .
3) Preparation and submittal of construction staking documentation in the
form of"cut sheets" using the City 's standard template.
2 . Construction Survey
a . Measurement
1) This Item is considered subsidiary to the various Items bid.
b. Payment
1) The work performed and the materials furnished in accordance with this
Item are subsidiary to the various Items bid and no other compensation will be
allowed.
3. As-Bui lt Survey
a. Measurement
1) Measurement for this Item shall be by lump sum .
b . Payment
1) The work performed and the materials furnished in accordance with this
Item shall be paid for at the lump sum price bid for "As-Bui lt Survey ".
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIF ICATION DOCUMENTS
Revised Febr uary 14, 2018
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No . 104552
0171 23-2
CONSTRU CTION STAKING AND SURVEY
Page 2 of 8
2) Payment for "Construction Staking" shall be made in partial payments
prorated by work completed compared to total work included in the lump sum
item.
c. The price bid shall include, but not be limited to the fo llowin g::
1) Fie ld measurements and survey shots to identify location of completed
faci liti es.
2) Documentation and submittal of as-built survey data onto contractor redline
plans and digital survey files.
1.3 REFERENCES
A. Definjtions
1. Construction Survey -The surv ey measurements made prior to or while
construction is in progress to control elevation, horizontal position, dimensions and
configuration of structures/improvements included in the Project Drawings.
2. As-built Survey -The measurements made after the construction of the
improvem ent features are complete to provide position coordinates for the features
of a project.
3. Construction Staking -The placement of stakes and markings to provide offsets
and elevations to cut and fill in order to locate on the ground the designed
structures/improvements included in the Project Drawings . Construction staking
shall include staking easements and/or right of way if indicated on the plans.
4. Survey "Field Checks" -Measurements made after construction staking is
completed and before construction work begins to ensure that structures marked on
the ground are accurately loc ated per Project Drawings.
B. Technical References
1. City of Fort Worth-Construction Staking Standards (available on City's Buzzsaw
website)-01 71 23.16.01 _ Attachment A_Survey Staking Standards
2. City ofFort Worth -Standard Survey Data Collector Library (fxl) files (available
on City's Buzzsaw website).
3. Texas Department of Transportation (TxDOT) Survey Manual, latest revi sion
4. Texas Society of Professional Land Surveyors (TSPS), Manual of Practice for Land
Surveying in the State of Texas, Category 5
1.4 ADMINISTRATIVE REQUIREMENTS
A. The Contractor's selection of a surveyor must comply with Texas Government
Code 2254 (qualifications based selection) for this project.
1.5 SUBMITT ALS
A. Submittals, ifrequired, shall be in accordance with Section 01 33 00.
B. All submittals shall be received and reviewed by the City prior to delivery of work.
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS
A. Field Quality Control Submittals
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATIO N DO CUM ENTS
Revise d February 14, 2018
2022 WATER SERVIC E LEAK
REPAIR CONTRACT
City Project No . I 04552
017 1 23-3
CONSTRUCTION STAKJNG AND SURVEY
Page 3 of8
1. Documentation verifying accuracy of field eng ineering work, includin g coordinate
conversions if plans do not indicate grid or gro und coordinates.
2. Submit "Cut-Sheets " conforming to the standard templ ate provided by th e City
(refer to 0 1 71 23.16.01 -Attachment A -Survey Staking Standards).
1.7 CLOSEOUT SUBMITTALS
B . A s-built Redline Drawing Submittal
1. Submit As-Built Survey Redline Drawings documenting the locations/elevations of
constructed improvements s igned and sealed by Regi stered Profes s ional Land
Surveyor (RPLS) re s pons ible for th e work (refer to 01 71 23.16.01 -Attachment A
-Survey Staking Standards).
2. Contractor shall submit the proposed as-built and completed red line drawing
submittal one (1) week prior to schedu ling the project final inspection for City
review and comment. Revi s ions, if necessary , shall be made to the as-built redline
drawings and resubmitted to the City prior to schedulin g the construction final
in spection .
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE
A. Construction Staking
1. Construction staking will be performed by the Contractor.
2. Coordination
a. Contact City's Project Representative at least one week in advance notifyin g
the City of when Construction Staking is scheduled.
b. It is the Contractor's re sponsibility to coordinate staking such that
construction activities are not delayed or negatively impacted .
3. General
a. Contractor is re s pon s ible for preserving and maintaining stakes. If City
surveyors are required to re-stake for any reason , the Contractor will be
responsible for costs to perform staking. Ifin the opinion of the City, a
sufficient number of stakes or markings have been lost, destroyed disturbed or
omitted that the contracted Work cannot take place then the Contractor will be
required to stake or re-stake the deficient areas.
B. Construction Survey
1. Construction Survey will be performed by the Contractor.
2. Coordination
a. Contractor to verify that horizontal and vertical control data established in the
desi g n survey and required for construction survey is available and in place.
3. General
a. Construction survey will be performed in order to construct the work shown
on the Construction Drawings and specified in the Contract Documents.
b . For construction methods other than open cut, the Contractor shall perform
construction survey and verify control d ata including, but not limited to , the
following:
1) Verification that established benchmarks and control are accurate.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised February 14, 2018
2022 WATER SER VICE LEAK
REP AIR CONTRACT
C ity Project No . l 04 552
01 71 23 -4
CONSTRUCTION STAKING AND SURVEY
Page 4 of 8
2) Use of Benchmarks to furnish and maintain all reference lines and grades
for tunneling.
3) Use ofline and grades to establish the location of the pipe.
4) Submit to the City copies of field notesused to establish all lines and
grades, ifrequested, and allow the City to check guidance system setup prior
to beginning each tunneling drive .
5) Provide access for the City, ifrequested, to verify the guidance system and
the lin e and grade of the carrier pipe.
6) The Contractor remains fully responsible for the accuracy of the work and
correction of it, as required.
7) Monitor line and grade continuously during construction.
8) Record deviation with respect to design line and grade once at each pipe
joint and submit dail y records to the City.
9) If the installation does not meet the specified tolerances (as outlined in
Sections 33 05 23 and /or 33 05 24), immediately notify the City and correct
the in stall ation in accordance with the Contract Documents.
C. As-Built Survey
1. Required As-Built Survey will be performed by the Contractor.
2. Coordination
a. Contractor is to coordinate with City to confirm which features require as-
built surveying.
b. It is the Contractor's responsibility to coordinate the as-bui lt s urvey and
required measurements for items that are to be buried such that construction
activities are not delayed or negatively impacted.
c. For sewer mains and water mains 12 " and under in diameter, it is acceptable
to physically measure depth and mark the location during the progress of
construction and take as-built survey after the facility has been buried. The
Contractor is responsible for the quality control needed to ensure accuracy.
3. General
a. The Contractor shall provide as-built survey including the elevation and
location (and provide written documentation to the City) of construction
features during the progress of the construction including the following:
1) Water Lines
a) Top of pipe elevations and coordinates for waterlines at the following
locations:
(1) Minimum every 250 linear feet, including
(2) Horizontal and vertical points of inflection, curvature,
etc.
(3) Fire line tee
(4) Plugs, stub-outs, dead-end line s
(5) Casing pipe (each end) and all buried fittings
2) Sanitary Sewer
a) Top of pipe elevations and coordinates for force mains and siphon
sanitary sewer line s (non-gravity facilities) at the following locations:
(1) Minimum every 250 linear feet and any buried fittings
(2) Horizontal and vertical points of inflection, curvature,
etc.
3) Stormwater -Not Applicable
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIF ICATIO N DOCUMENTS
Revised February 14 , 2018
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No . I 04552
0 1 71 23 -5
CONSTRUCTION STAKJNG AND SURVEY
Page 5 of8
b. The Contractor shall provide as-built survey including the elevation and
location (and provide written documentation to the City) of con struction
features after the construction is completed including the following:
I) Manholes
a) Rim and flowline elevations and coordinates for each manhol e
2) Water Lines
a) Cathodic protection test stations
b) Sampling stations
c) Meter boxes/vaults (All sizes)
d) Fire hydrants
e) Valves (gate, butterfly, etc.)
f) Air Release valves (Manhole rim and vent pipe)
g) Blow off valves (Manhole rim and valve lid)
h) Pressure plane valves
i) Underground Vaults
(1) Rim and flow line elevations and coordinates for each
Underground Vault.
3) Sanitary Sewer
a) Cleanouts
(1) Rim and flowline elevations and coordinates for each
b) Manholes and Junction Structures
(1) Rim and flowline elevations and coordinates for each
manhole and junction structure.
4) Stormwater -Not Applicable
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY
PART 2 -PRODUCTS
A. A construction survey will produce, but will not be limited to:
1. Recovery of relevant control points, points of curvature and points of intersection.
2. Establish temporary horizontal and vertical control elevations (benchmarks)
sufficiently permanent and located in a manner to be used throughout construction .
3. The location of planned facilities, easements and improvements.
a. Establishing final line and grade stakes for piers, floors, grade beams, parking
areas, utilities , streets , highways, tunnels, and other construction.
b. A record of revisions or corrections noted in an orderly manner for reference.
c. A drawing, when required by the client, indicating the horizontal and vertical
location of facilities , easements and improvements, as built.
4 . Cut sheets shall be provided to the City inspector and Survey Superintendent for all
construction staking projects . These cut sheets shall be on the standard city template
which can be obta ined from the Survey Superintendent (817-392-7925).
5 . Digital survey files in the following formats shall be acceptable:
a. AutoCAD (.dwg)
b. ESRI Shapefile (.shp)
CITY OF FORT WORTH
STANDARD CONSTRUCTIO N SP EC IFICATION DOCUMENTS
Revised February 14, 2018
2022 WATER SERVICE LEAK
REPAIR CONTRACT
C ity Proj ect No. 104552
0 1 71 23 -6
CONSTRUCTION STAKING AND SURVEY
Page 6 of8
c. CSV file (.csv), formatted with X and Y coordinates in separate columns (use
standard templates, if available)
6. Survey files shall includ e vertical and hori zontal data tied to original project
control and benchmarks , and shall include feat ure descriptions
PART 3 -EXECUTION
3.1 INST ALLERS
A. Tolerances:
1. The staked location of any improvement or facility should be as accurate as
practical and necessary. The deg ree of preci s ion required is dependent on many
factors all of which must remain judgmental. The tolerances listed hereaft er are
based on generalities and , und er certain circumstances, shall yield to specific
requirements. The surveyor s ha ll assess any s ituation by review of the overall plan s
and through consultation with responsible part ie s as to the need for specific
tolerances.
a. Earthwork: Grades for earthwork or rough cut should not exceed 0.1 ft. vertical
tolerance. Horizontal alignment for earthwork and rough cut should not exceed
1.0 ft. tolerance .
b. Horizontal alignment on a structure shall be within .0. lft tolerance.
c. Paving or concrete for streets, curbs, g utters, parking areas, drive s, alleys and
walkways shall be located within the confin es of th e s ite boundaries and ,
occasionally, along a boundary or any other restrictive line . Away from any
restrictive line, these facilities should be staked with an accuracy producing no
more than 0.05ft. tolerance from their specified location s.
d. Underground and overhead ut ilities, s uch as sewers, gas, water, telephone and
electric lines , shall be located horizontally within their prescribed areas or
easements. Within assigned areas, the se utilities should be staked with an
accuracy producing no more than 0 .1 ft tolerance from a specified location .
e. The accuracy required for the vertical loc ation of utilitie s varies widely. Many
underground utilities require only a minimum cover and a toleran ce of 0.1 ft.
should be maintained. U nderground and overhead utilitie s on planned profile,
but not depending on gravity flow for performance, should not exceed 0 .1 ft.
tolerance.
B.Surveying instruments shall be kept in close adjustment according to manufacturer's
specifications or in compliance to standards. The City reserves the right to reque st a
calibration report at any time and recommends regular maintenance schedule be
performed by a certified technician every 6 months.
1. Field measurements of angles and distances shall be done in such fashion as to
satisfy the closures and tolerances expressed in Part 3.1.A .
2. Vertical locations shall be established from a pre-established benchmark and
checked by closing to a different bench mark on the same datum.
3. Construction survey field work shall correspond to the client's plans. Irregularities
or conflicts found shall be reported promptly to the City.
4. Revisions , corrections and other pertinent data shall be lo gged for future reference.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised February 14 , 2018
2022 WATERSERVlCE LEAK
REPAIR CONTRACT
C ity Project No . I 04552
3.2 EXAMINATION [NOT USED]
3.3 PREPARATION [NOT USED]
3.4 APPLICATION
3.5 REPAIR/ RESTORATION
01 71 23 -7
CONSTRUCTION STAKING AND SURVEY
Page 7 of8
A.If the Contractor's work damages or destroys one or more of the control
monuments/points set by the City, the monuments shall be adequately referenced for
expedient restoration.
1. Notify City if any control data needs to be restored or replaced due to damage
caused during construction operations.
a. Contractor shall perform replacements and/or restorations .
b. The City may require at any time a survey "Field Check" of any monument
or benchmarks that are set be verified by the City surveyors before further
associated work can move forward.
3.6 RE-INSTALLATION [NOT USED]
3.7 FIELD [oR] SITE QUALITY CONTROL
A.It is the Contractor's responsibility to maintain all stakes and control data placed by the
City in accordance with this Specification. This includes easements and right of way, if
noted on the plans .
B. Do not change or relocate stakes or control data without approval from the City.
3.8 SYSTEM STARTUP
A. Survey Checks
1. The City reserves the right to perform a Survey Check at any time deemed
neces sary.
2. Checks by City personnel or 3rd party contracted surveyor are not intended to
relieve the contractor of his/her responsibility for accuracy.
3.9 ADJUSTING [NOT USED)
3.10 CLEANING [NOT USED]
3.11 CLOSEOUT ACTIVITIES [NOT USED]
3.12 PROTECTION [NOT USED]
3.13 MAINTENANCE [NOT USED]
3.14 ATTACHMENTS [NOT USED]
END OF SECTION
Revision Log
C ITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised February 14, 2018
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No. I 04552
DATE NAME
8/3 1/20 12 D. John son
8/3 1/20 17 M. Owen
2/14/2018 MOwen
C ITY OF FORT WORTH
0 1 71 23 - 8
CONSTRUCTIO N STAKING AND SURVEY
Page 8 of8
SUMMARY OF CHANGE
Added in struction and modified measurement & pay me nt und e r 1.2; added
definitions and references under 1.3; modified 1.6; added 1.7 closeout submittal
requirements ; modified 1.9 Quality Ass uran ce ; added PART 2 -PRODUCTS;
Added 3.1 In sta ll e rs; added 3.5 Repair/Restoration ; and ad ded 3.8 System Startup.
Re mo ved "blu e text"; rev ised measurement and payment section s for Construction
Stakin g and As-B uil t Survey; added refe rence to se lection compl iance with TGC
22 54 ; revi sed ac tion and C loseout su bmittal req uire me nts; add ed acceptab le depth
meas ureme nt criter ia; re v ised li st of items req uirin g as -bu ilt survey "during" and
"after" construction ; an d rev ised acceptable digital survey file format
STANDARD CONS TRUCTION SPECIFICATION DOCUMENTS
Rev ised February 14 , 2018
2022 WATER SERVICE LEAK
REPAIR CONTRACT
C ity Proj ect No. I 04552
1 SECTION 01 74 23
2 CLEANING
3 PARTl-GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
01 74 23 -I
CLEANING
Page I of4
6 1. Intermediate and final cleaning for Work not including special cleaning of closed
7 systems specified elsewhere
8 B. Deviations from this City of Fort Worth Standard Specification
9 1. None.
10 C. Related Specification Sections include, but are not necessarily limited to:
11 1. Division O -Bidding Requirements, Contract Forms and Conditions of the Contract
12 2. Division l -General Requirements
13 3. Section 32 92 13 -Hydro-Mulching, Seeding and Sodding
14 1.2 PRICE AND PAYMENT PROCEDURES
15 A. Meas urement and Payment
16 1. Work associated with this Item is considered subsidiary to the various Items bid.
17 No separate payment will be allowed for this Item.
18 1.3 REFERENCES [NOT USED]
19 1.4 ADMINISTRATIVE REQUIREMENTS
20 A. Scheduling
2 1 1. Schedule cleaning operations so that dust and other contaminants disturbed by
22 cleaning process will not fall on newly pa inted surfaces.
23 2. Schedule final cleaning upon completion of Work and immediately prior to final
24 inspection .
25 1.5 SUBMITTALS [NOT USED]
26 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
27 1.7 CLOSEOUT SUBMITTALS [NOT USED]
28 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
29 1.9 QUALITY ASSURANCE [NOT USED]
30 1.10 STORAGE, AND HANDLING
31 A . Storage and Handling Requirements
32 1. Store cleaning products and cleaning wastes in containers specifically designed for
33 those materials .
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July I , 20 11
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No. 104 552
1.11 FIELD [SITE] CONDITIONS [NOT USED]
2 1.12 WARRANTY [NOT USED]
3 PART2-PRODUCTS
01 74 23 -2
CLEANfNG
Page 2 of4
4 2.1 OWNER-FURNISHED [oR) OWNER-SUPPLIEDPRODUCTS [NOT USED]
5 2.2 MATERIALS
6 A . Cleaning Agents
7 I. Compatible with surface being cleaned
8 2. New and uncontaminated
9 3. For manufactured surfaces
1 0 a. Material recommended by manufacturer
11 2.3 ACCESSORIES [NOT USED]
12 2.4 SOURCE QUALITY CONTROL [NOT USED]
13 PART 3-EXECUTION
14 3.1 INSTALLERS [NOT USED]
15 3.2 EXAMINATION [NOT USED]
16 3.3 PREPARATION [NOT USED]
17 3.4 APPLICATION [NOT USED]
18 3.5 REPAIR/ RESTORATION [NOT USED]
19 3.6 RE-INSTALLATION [NOT USED]
20 3.7 FIELD [oR] SITE QUALITY CONTROL [NOT USED]
21 3.8 SYSTEM STARTUP [NOT USED]
22 3.9 ADJUSTING [NOT USED]
23 3.10 CLEANING
24 A. General
25 I. Prevent accumulation of wastes that create hazardous conditions.
26 2. Conduct cleaning and disposal operations to comply with laws and safety orders of
27 governing authorities.
28 3. Do not dispose of volatile wastes such as mineral spirits, oil or paint thinner in
29 storm or sanitary drains or sewers.
30 4. Dispose of degradable debris at an approved solid waste disposal site.
31 5. Dispose of nondegradable debris at an approved solid waste disposal site or in an
32 alternate manner approved by City a nd regulatory agencies.
CITY OF FORT WORTH
STANDARD CONSTRUC TIO N SPECIFICATION DO CUMEN TS
Re vised Jul y I, 20 I I
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No. I 04552
1 6 . Handle materials in a controlled manner with as few handlings as possible.
0 1 74 23 - 3
CLEANING
Page 3 of 4
2 7. Thoroug hly clean, sweep, wash and polish all Work and equipment associated with
3 this project.
4 8. Remove all signs of temporary construction and activities incidental to construction
5 ofrequired permanent Work.
6 9 . If project is not cleaned to the satisfaction of the City, the City reserves the right to
7 have the cleaning completed at the expense of the Contractor.
8 10 . Do not burn on-site.
9 B. Intermediate Cleaning during Construction
IO 1. Keep Work areas clean so as not to hinder health, safety or convenience of
11 personnel in existing facility operations.
12 2. At maximum weekly intervals, dispose of waste materials, debris and rubbish.
13 3. Confine construction debris daily in strategically located container(s):
14 a. Cover to prevent blowing by wind
15 b. Store debris away from construction or operational activities
16 c. Haul from site at a minimum of once per week
17 4. Vacuum clean interior areas when ready to receive finish painting.
18 a. Continue vacuum cleaning on an as-needed basis , until Final Acceptance.
19 5. Prior to storm events, thoroughly clean site of all loose or unsecured items, which
20 may become airborne or transported by flowing water during the storm.
21 C. Interior Final Cleaning
22 1. Remove grease, mastic, adhesives, dust, dirt, stains, fingerprints , labels and other
23 foreign materials from sight-exposed surfaces.
24 2. Wipe all lighting fixture reflectors , lenses, lamps and trim s clean.
25 3. Wash and shine glazing and mirrors .
26 4 . Polish glossy surfaces to a clear shine.
27 5. Ventilating systems
28 a. Clean permanent filters and replace disposable filters if units were operated
29 during construction.
30 b. Clean ducts , blowers and coils if units were operated without filters during
31 construction.
32 6. Replace all burned out lamps.
33 7. Broom clean process area floors.
34 8. Mop office and control room floors .
35 D. Exterior (Site or Right of Way) Final Cleaning
36 1. Remove trash and debris containers from site.
37 a. Re-seed areas disturbed by location of trash and debris containers in accordance
38 with Section 32 92 13.
39 2. Sweep roadway to remove all rocks, pieces of asphalt, concrete or any other object
40 that may hinder or disrupt the flow of traffic along the roadway.
41 3. Clean any interior areas including, but not limited to, vaults, manholes , structures ,
42 junction boxes and inlets .
CITY OF FORT WORTH
STANDARD CON STRUCTION SPEC IFICATION DOCUMENTS
Revi sed July I , 20 I I
2022 WATER SERVI CE LEAK
REPAIR CONTRACT
City Proj e ct No . I 04552
01 74 23 -4
CLEANING
Page 4 of 4
4 . Ifno longer required for maintenance of eros ion facilities, and upon a pproval by
2 City, remove eros ion control from s ite.
3 5. Clean s ign s, li g ht s, signals , etc.
4 3.11 CLOSEOUT ACTIVITIES [NOT USED]
5 3.12 PROTECTION [NOT USED]
6 3.13 MAINTENANCE [NOT USED]
7 3.14 ATTACHMENTS [NOT USED]
8 END OF SECTION
9
IO
Revision Log
DATE NAME
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPEC lFI CAT!ON DOCUMENTS
Revi se d Jul y I, 20 I I
SUMMARY OF CHANGE
2022 WATER SE RVI CE LEAK
RE PAIR CONTRACT
City Proj ec t No. I 04552
SECTION 01 77 19
2 CLOSEOUT REQUIREMENTS
3 PARTl-GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. The procedure for clo sing out a contract
7 B. Deviations from thi s City of Fort Worth Standard Specification
8 1. None.
01 7719 -1
CLOSEOUT REQUIREMENTS
Page 1 of 3
9 C. Related Specification Sections include, but are not necessarily limited to:
10 1. Division 0 -B iddin g Requirements , Contract Forms and Con ditions of the Contract
11 2. Divi sion 1 -General Requirements
12 1.2 PRICE AND PAYMENT PROCEDURES
13 A. Measurement and Payment
14 1. Work associated with this Item is considered sub s idi ary to the various Item s bid .
15 No se parate payment will be allowed for this It em.
16 1.3 REFERENCES [NOT USED]
17 1.4 ADMINISTRATIVE REQUIREMENTS
18 A. Guarantees, Bonds and Affidavits
19 1. No application for final payment will be accepted until all guarantees, bonds ,
20 certificates, licenses and affidavits required for Work or equipment as specified are
21 satisfactorily filed with the City.
22 B. Release of Liens or Claims
23 1. No application for final payment will be accepted until satisfactory evidence of
24 release ofliens has been submitted to the City.
25 1.5 SUBMITTALS
26 A. Submit all required documentation to City's Project Representative.
27
28 1.6 INFORMATIONAL SUBMITT ALS [NOT USED]
29
30 1.7 CLOSEOUT SUBMITTALS [NOT USED]
31 PART 2 -PRODUCTS [NOT USED]
32
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPEC[FICATION DOCUMENTS
Revised March 22, 202 1
2022 WATER SERVICE LEAK
REP AIR CONTRACT
City Project No. 104552
PART 3 -EXECUTION
2 3.1 INST ALLERS [NOT USED]
3 3.2 EXAMINATION [NOT USED]
4 3.3 PREPARATION [NOT USED]
5 3.4 CLOSEOUT PROCEDURE
6 A. Prior to requesting Final Inspection, submit:
01 771 9-2
C LO SEOUT REQUIREMENTS
Page 2 of 3
7 1. Project Record Documents in accordance with Section 01 78 39
8 2. Operation and Maintenance Data, if required, in accordance with Section 017823
9 B. Prior to requesting Final Inspection, perform final cleaning in accordance with Section
10 01 74 23.
11 C. Final Inspection
12 1. After final cleaning, provide notice to the City Project Representative that the Work
13 is completed.
14 a. The City will make an initial Final Inspection with the Contractor present.
15 b. Upon completion of this inspection, the City will notify the Contractor, in
16 writing within 10 business days, of any particulars in which this inspection
17 reveals that the Work is defective or incomplete.
18 2. Upon receiving written notice from the City, immediately undertake the Work
19 required to remedy deficiencies and complete the Work to the satisfaction of the
20 City.
21 3. The Right-of-way shall be cleared of all construction materials, barricades, and
22 temporary signage.
23 4. Upon completion of Work associated with the items listed in the City's written
24 notice , inform the City that the required Work has been completed. Upon receipt of
25 this notice, the City, in the presence of the Contractor, will make a subsequent Final
26 Inspection of the project.
27 5. Provide all special accessories required to place each item of equipment in full
28 operation. These special accessory items include, but are not limited to:
29 a. Specified spare parts
30 b. Adequate oil and grease as required for the first lubrication of the equipment
31 c. Initial fill up of all chemical tanks and fuel tanks
32 d. Light bulbs
33 e. Fuses
34 f. Vault keys
35 g. Handwheels
36 h. Other expendable items as required for initial start-up and operation of all
37 equipment
38 D. Notice of Project Completion
39 1. Once the City Project Representative finds the Work subsequent to Final Inspection
40 to be satisfactory, the City will issue a Notice of Project Completion (Green Sheet).
41 E. Supporting Documentation
CITY OF FORT WORTH
ST AND ARD CONSTRUCTION SP ECrFI C A T JON DOC UMEN TS
Re v ised March 22 , 2021
2022 WATER SERVICE LEAK
REP AIR CONTRACT
City Project No. 104552
0177 19-3
C LOS EOU T REQUIREMENTS
Page 3 of3
1. Coordinate with the City Project Representative to complete the following
2 additional forms:
3 a. Final Payment Request
4 b. Statement of Contract Time
5 c. Affidavit of Payment and Release of Liens
6 d. Consent of Surety to Final Payment
7 e. Pipe Report (if required)
8 f. Contractor's Evaluation of City
9 g. Performance Evaluation of Contractor
10 F. Letter of Final Acceptance
11 1. Upon review and acceptance of Notice of Project Completion and Supporting
12 Documentation, in accordance with General Conditions, City will issue Letter of
13 Final Acceptance and release the Final Payment Reque st for payment.
14 3.5 REPAIR/RESTORATION [NOT USED]
15 3.6 RE-INSTALLATION [NOT USED]
16 3.7 FIELD [oR] SITE QUALITY CONTROL [NOT USED]
17 3.8 SYSTEM STARTUP [NOT USED]
18 3.9 ADJUSTING [NOT USED]
19 3.10 CLEANING [NOT USED]
20 3.11 CLOSEOUT ACTIVITIES [NOT USED]
21 3.12 PROTECTION [NOT USED]
22 3.13 MAINTENANCE [NOT USED]
23 3.14 ATTACHMENTS [NOT USED]
24 END OF SECTION
25
Revision Log
DATE NAME SUMMARY OF CHANGE
3 /22/2021 MOwen 3.4 C. Added lang uage to clarify and emphasize requirement to "Clearin g ROW''
26
CITY OF FORT WORTH
ST AND ARD CONSTRUCTION SPEClFICA TION DOCUMENTS
Rev ised March 22, 2021
2022 WATER SERVICE LEAK
REP AIR CONTRACT
City Project No. I 04552
0 1 78 23 -I
OPERATION AND MAINTENANCE DATA
Page I of5
SECTION 01 78 23
2 OPERATION AND MAINTENANCE DAT A
3 PARTl-GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. Product data and related information appropriate for City's maintenance and
7 operation of products furnished under Contract
8 2. Such products may include, but are not limited to:
9 a. Traffic Controllers
10 b. Irrigation Controllers (to be operated by the City)
11 c. Butterfly Valves
12 B . Deviations from this City of Fort Worth Standard Specification
13 1. None.
14 C. Related Specification Sections include, but are not necessarily limited to :
15 1. Divi s ion O -Bidding Requirements , Contract Forms and Conditions of the Contract
16 2. Division 1 -General Requirements
17 1.2 PRICE AND PAYMENT PROCEDURES
18 A. Measurement and Payment
19 1. Work associated with this Item is considered subsidiary to the various Items b id.
20 No separate payment will be allowed for this Item.
21 1.3 REFERENCES [NOT USED]
22 1.4 ADMINISTRATIVE REQUIREMENTS
23 A. Schedule
24 1. Submit manuals in final form to the City within 30 calendar days of product
25 shipment to the project site.
26 1.5 SUBMITT ALS
27 A. Submittals shall be in accordance with Section 01 33 00. All submittals shall be
28 approved by the City prior to delivery.
29 1.6 INFORMATIONAL SUBMITTALS
30 A . Submittal Fonn
31 1. Prepare data in form of an instructional manual for use by City personnel.
32 2. Fonnat
33 a. Size: 8 ½ inches x 11 inches
34 b. Paper
35 1) 40 pound minimum, white, for typed pages
36 2) Holes reinforced with plastic, cloth or metal
37 c. Text: Manufacturer's printed data, or neatly typewritten
C ITY OF FORT WORTH
STANDARD CONSTRUCTIO N SPECIFICATION DOCUMENTS
Revised December 20 , 20 12
2022 WATER SERVICE LEAK
REPAIR CONTRACT
C ity Proj ect No. 104 552
0 1 78 23 - 2
OPERATIO N AND MA[NT EN ANCE DATA
Page 2 of 5
d . Drawings
1) Provide reinforced punched binder tab , bind in with text
2) Reduce larger drawings and fold to size of text pages.
2
3
4
5
6
7
8
9
e . Provide fly-leaf for each separate product, or each piece of operating
equipment.
1) Provide typed description of product, and major component parts of
equipment.
2) Provide indexed tabs.
f. Cover
10
11
I) Identify each volume with typed or printed title "OPE RA TING AND
MAINTENANCE INSTRUCTIONS".
12 2) List:
13 a) Title of Project
14 b) Identity of separate structure as applicable
15 c) Identity of general subject matter covered in the manual
16 3 . Binders
17 a . Commercial quality 3-ring binders with durable and cleanable plastic covers
18 b . When multiple binders are used , correl ate the data into related consistent
19 groupings.
20 4. If available, provide an electronic form of the O&M Manual.
21 B. Manual Content
22 I. Neatly typewritten table of contents for each volume, arranged in systematic order
23 a. Contractor, name of responsible principal , address and te lephone number
24 b. A list of each product required to be included , indexed to content of the volume
25 c. List, with each product:
26 1) The name, address and telephone number of the subcontractor or installer
27 2) A list of each product required to be included, indexed to content of the
28 vo lum e
29 3) Identify area ofresponsibility of each
30 4) Local source of supply for parts and replacement
3 1 d . Identify each product by product name and other identi fy ing symbol s as set
32 forth in Contract Documents .
33 2 . Product Data
34 a. Include only those sheets which are pertinent to the specific product.
35 b . Annotate each sheet to:
36 1) Clearly identify specific product or part installed
37 2) Clearly identify data app li cable to installation
38 3) Delete references to inapplicable information
39 3 . Drawings
40 a . Supplement product data with drawings a s necessary to clearly illustrate:
41 1) Relations of component parts of equipment and systems
42 2) Control and flow diagrams
43 b . Coordinate drawings with information in Project Record Documents to assure
44 correct illustration of completed in stallation.
45 c. Do not use Project Record Drawings as maintenance drawings.
46 4. Written text, as required to supp lement product data for the particular installation:
47 a . Organize in consistent format under separate headings for different procedures.
48 b . Provide logical sequence of instructions of each procedure.
C ITY O F FORT WORTH
STANDARD CO N STRUC TION SPEC IFI C ATIO N DOCUMENTS
Revi se d Dece m be r 20 , 20 12
2022 W ATER SER YT CE LEAK
REPAIR CONTRACT
C ity Project No. I 04552
0 1 7823 -3
OPERA TION AND MAINTENANCE DATA
Page 3 of 5
1 5. Copy of each warranty, bond and service contract issued
2 a . Provide information sheet for City personnel giving:
3 1) Proper procedures in event of failure
4 2) Instances which might affect validity of warranties or bonds
5 C. Manual for Materials and Finishes
6 1. Submit 5 copies of complete manual in final form.
7 2. Content, for architectural products , applied materials and finishes:
8 a. Manufacturer's data, giving full information on products
9 1) Catalog number, size, composition
10 2) Color and texture designations
11 3) Information required for reordering special manufactured products
12 b . Instructions for care and maintenance
13 1) Manufacturer's recommendation for types of cleaning agents and methods
14 2) Cautions against c leaning agents and methods which are detrimental to
15 product
16 3) Recommended schedule for cleaning and maintenance
17 3 . Content, for moisture protection and weather exposure products:
18 a. Manufacturer's data, giving full information on products
19 I) Applicable standards
20 2) Chemical composition
21 3) Details of installation
22 b. Instructions for inspection, maintenance and repair
23 D . Manual for Equipment and Systems
24 1. Submit 5 copies of complete manual in final fonn.
25 2. Content, for each unit of equipment and system, as appropriate:
26 a. Description of unit and component parts
27 1) Function, normal operating characteristics and limitin g conditions
28 2) Performance curves , engineering data and tests
29 3) Complete nomenclature and commercial number ofreplaceable parts
30 b. Operating procedures
31 1) Start-up, break-in, routine and normal operating instructions
32 2) Regulation, control, stopping, shut-down and emergency instructions
33 3) Summer and winter operating instructions
34 4) Special operating instructions
35 c. Maintenance procedures
36 I) Routine operations
37 2) Guide to "troub le shooting"
38 3) Disassembly, repair and reassembly
39 4) Alignment, adjusting and checking
40 d. Servicing and lubrication schedule
41 1) List oflubricants required
42 e. Manufacturer's printed operating and maintenance instructions
43 f. Description of sequence of operation by control manufacturer
44 I) Predicted life of parts subject to wear
45 2) Items recommended to be stocked as spare parts
46 g . As installed control diagrams by controls manufacturer
47 h. Each contractor's coordination drawings
48 1) As installed color coded piping diagrams
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised December 20 , 2012
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No. I 04552
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
01 78 23 -4
OPERATlON AND MAINTENANCE DATA
Page 4 of5
1. Charts of valve tag numbers, with location and function of each valve
J. List of original manufacturer's spare parts , manufacturer's current prices, and
recommend ed quantities to be ma intained in storage
k. Other data as required under pertinent Sections of Specifications
3. Content, for each electric and e lectronic syste m, as appropriate:
a. Description of system and component parts
1) Function, normal operating characteristics, and limiting conditions
2) Performance curves , engineering data and tests
3) Complete nomenclature and commercial number of replaceable parts
b . Circuit directories of panel boards
1) Electrical service
2) Controls
3) Communications
c. As installed color coded wiring diagrams
d . Operating procedures
1) Routine and normal operating instructions
2) Sequences required
3) Special operating instructions
e. Maintenance procedures
1) Routine operations
2) Guide to "trouble shooting"
3) Disasse mbly, repair and reassembly
4) Adjustment and checking
f. Manufacturer's printed operating and maintenance instructions
g. List of original manufacturer's spare parts, manufacturer's current prices, and
recommended quantities to be maintained in storage
h . Other data as required under pertinent Sections of Specifications
4. Prepare and include additional data when the need for such data becomes apparent
during instruction of City's personnel.
30 1.7 CLOSEOUT SUBMITTALS [NOT USED]
31 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
32 1.9 QUALITY ASSURANCE
33 A. Provide operation and maintenance data by personnel with the following criteria:
34 1. Trained and experienced in maintenance and operation of described products
35 2. Skilled as technical writer to the extent required to communicate essential data
36 3. Skilled as draftsman competent to prepare required drawings
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised Dece m be r 20 , 20 12
2022 WATER SERVICE LEAK
REP AIR CONTRACT
City Project No. I 04552
01 78 23 -5
OPERATION AND MAINTENANCE DATA
1 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
2 1.11 FIELD [SITE] CONDITIONS [NOT USED]
3 1.12 WARRANTY [NOT USED]
4 PART 2 -PRODUCTS [NOT USED]
5 PART 3 -EXECUTION [NOT USED]
6 END OF SECTION
7
8
Revision Log
DATE NAME
8/3 1/20 12 D. Johnson
CITY OF FORT WORTH
STANDARD CONSTRUCTIO N SPECIFICATION DOCUMENTS
Revised Dece mb er 20 , 20 12
SUMMARY OF CHANGE
1.5 .A. l -title of section removed
Page 5 of5
2022 WATER SERVI CE LEAK
REPAIR CONTRACT
City Project No . 104 552
SECTION 01 78 39
2 PROJECT RECORD DOCUMENTS
3 PARTl-GENERAL
4 1.1 SUMMARY
5 A . Section Includes :
0 1 7839 -1
PROJECT RE CORD DOCUMEN TS
Page I of4
6 1. Work associated with the documenting the project and recording changes to project
7 documents , including:
8 a . Record Drawings
9 b. Water Meter Service Reports
10 c . Sanitary Sewer Service Reports
11 d . Large Water Meter Reports
12 B. Deviations from this City of Fort Worth Standard Specification
13 1. None.
14 C. Related Specification Sections include, but are not necessarily limited to:
15 I . Division O -Bidding Requirements, Contract Forms and Conditions of the Contract
16 2 . Division I -General Requirements
17 1.2 PRICE AND PAYMENT PROCEDURES
18 A. Measurement and Payment
19 1. Work associated with this Item is considered subsidiary to the various Items bid .
20 No separate payment will be allowed for this Item.
21 1.3 REFERENCES [NOT USED]
22 1.4 ADMINISTRA TNE REQUIREMENTS [NOT USED]
23 1.5 SUBMITT ALS
24 A. Prior to submitting a request for Final Inspection, deliver Project Record Documents to
25 City 's Project Representative.
26 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
27 1.7 CLOSEOUT SUBMITTALS [NOT USED]
28 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
29 1.9 QUALITY ASSURANCE
30 A . Accuracy of Records
31 I. Thoroughly coordinate changes within the Record Documents, making adequate
32 and proper entries on each page of Specifications and each sheet of Drawings and
33 other Documents where such entry is required to show the change properly.
34 2. Accuracy of records shall be such that future search for items shown in the Contract
35 Documents may rely reasonably on information obtained from the approved Project
36 Record Documents.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATIO N DOCUMEN TS
Revi sed Jul y 1, 20 11
2021 WATERSERVI CE LEAK
REPAIR CONTRACT
City Project No. I 0455 2
0 I 78 39 - 2
PROJ ECT RE CORD DOCUMENTS
Page 2 of 4
3. To facilitate accuracy ofrecords, make entries within 24 hou rs after receipt of
2 info rmation that the change has occurred .
3 4. Provide factual information regardin g all aspects of the Work, both co ncealed and
4 vi s ibl e, to enable future modifi cation of the Work to proceed without lengthy and
5 expen siv e site measurement, inv es ti gation and examination.
6 1.10 STORAGE AND HANDLING
7 A. Storage and Handling Requirem ent s
8 1. M a intain th e job set of Record Documents complete ly protected from deterioration
9 and from loss and damage until completion of the Work and tran sfer of al I recorded
10 data to the final Project Record Documents.
11 2. In the eve nt of loss of recorded data, use means necessary to again secure the data
12 to the City's approval.
13 a. In such case, provide re placements to the standards originall y required by the
14 Contract Documents.
15 1.11 FIELD [SITE] CONDITIONS [NOT USED]
16 1.12 WARRANTY [NOT USED]
17 PART 2 -PRODUCTS
18 2.1 OWNER-FURNISHED [oR] OWNER-SUPPLIED PRODUCTS [NOT USED]
19 2.2 RECORD DOCUMENTS
20 A. Job set
2 1 1. Promptly following receipt of the Notice to Proceed, secure from the City, at no
22 charge to the Contractor, 1 complete set of all Documents comprising the Contract.
23 B. Final Record Documents
24 1. At a time nearing the completion of the Work and prior to Final Ins pection, provide
25 the City 1 complete set of all Final Record Drawings in the Contract.
26 2.3 ACCESSORIES [NOT USED]
27 2.4 SOURCE QUALITY CONTROL [NOT USED]
2 8 PART 3 -EXECUTION
29 3.1 INSTALLERS [NOT USED]
30 3.2 EXAMINATION [NOT USED]
31 3.3 PREPARATION [NOT USED]
32 3.4 MAINTENANCE DOCUMENTS
33 A. Maintenance of Job Set
34 1. Immediately upon receipt of the job set, identify each of the Documents with the
35 title , "RECORD DOCUMENTS -JOB SET".
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPEC IFI CATIO N DOCUMENTS
Revised Ju ly 1, 2011
202 1 WATER SERVICE LEA K
REPAIR CONTRACT
C ity Proj ect No. I 04552
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
B.
2. Preservation
0 I 78 39 -3
PROJECT REC ORD DO CUMENTS
Page 3 of4
a. Considering the Contract completion time, the probable number of occasions
upon which the job set must be taken out for new entries and for examination,
and the conditions under which these activities will be performed, devise a
suitable method for protecting the job set.
b. Do not use the job set for any purpose except entry of new data and for rev iew
by the City, until start of transfer of data to final Project Record Documents.
c. Maintain the job set at the site of work.
3. Coordination with Construction Survey
a. At a minimum, in accordance with the intervals set forth in Section 01 71 23 ,
clearly mark any deviations from Contract Documents associated with
installation of the infrastructure.
4. Making entries on Drawings
a. Record any deviations from Contract Documents .
b. Use an erasable colored pencil (not ink or indelible pencil), clearly describe the
change by graphic line and note as required.
c. Date all entries.
d. Call attention to the entry by a "cloud" drawn around the area or areas affected.
e. In the event of overlapping changes, use different colors for the overlapping
changes.
5. Conversion of schematic layouts
a. In some cases on the Drawings , arrangements of conduits, circuits, piping,
ducts, and similar items, are shown schematically and are not intended to
portray precise physical layout.
1) Final physical arrangement is determined by the Contractor, subject to the
City's approval.
2) However, design of future modifications of the facility may require
accurate information as to the final physical layout of items which are
shown only schematically on the Drawings .
b. Show on the job set of Record Drawings, by dimension accurate to within 1
inch, the centerline of each run of items.
I) Final physical arrangement is determined by the Contractor, subject to the
City's approval.
2) Show, by symbol or note, the vertical location of the Item ("under s lab", "in
ceiling plenum", "exposed", and the like).
3) Make all identification sufficiently descriptive that it may be related
reliably to the Specifications.
c. The City may waive the requirements for conversion of schematic layouts
where, in the City's judgment, conversion serves no useful purpose. However,
do not rely upon waivers being issued except as specifically issued in writing
by the City.
Final Project Record Documents
1. Transfer of data to Drawings
a . Carefully transfer change data shown on the job set of Record Drawings to the
corresponding final documents, coordinating the changes as required.
b . Clearly indicate at each affected detail and other Drawing a full description of
changes made during construction, and the actual location of items .
CITY OF FORT WORTH 2021 WATER SERVICE LEAK
REPAIR CONTRACT
C ity Project No. I 04552
ST AND ARD CONSTRUCTION SP EC IFI CATIO N DOCUMENTS
Revised Jul y I , 20 11
01 78 39 -4
PROJECT RECORD DOCUMENTS
Page 4 of4
c. Call attention t o each ent ry by drawin g a "cloud " around the area or areas
2 affected.
3 d. Make changes neatly, cons istently and with the proper medi a to ass ur e
4 lon gev ity and clear reproduction.
5 2. Transfer of data to other Docum ent s
6 a . If th e Documents, other than Drawings, have been kept clean durin g progress of
7 the Work, and if entries thereon have been orderly to the approval of the City,
8 the job set of thos e Docum ent s, other than Drawings, will be accepted as fin al
9 Record Documents.
10 b . If any s uch Docum ent is not so approved by the City, secure a new copy of th at
11 Document from the City at the City's usual charge for reproduction and
12 handling, and carefully tran sfe r the change data to the new copy to the approval
13 of th e City.
14 3.5 REPAIR/ RESTORATION [NOT USED]
15 3.6 RE-INSTALLATION [NOT USED]
16 3.7 FIELD [oR] SITE QUALITY CONTROL [NOT USED]
17 3.8 SYSTEM STARTUP [NOT USED]
18 3.9 ADJUSTING [NOT USED]
19 3.10 CLEANING [NOT USED]
20 3.11 CLOSEOUT ACTIVITIES [NOT USED]
2 1 3.12 PROTECTION [NOT USED]
22 3.13 MAINTENANCE [NOT USED]
23 3.14 ATTACHMENTS [NOT USED]
24 END OF SECTION
25
26
Revision Log
DATE NAME
CITY OF FORT WORTH
ST AND ARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revi sed Jul y 1, 20 11
SUMMARY OF CHANGE
202 1 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No. I 04552
0241 14 -1
UTILI TY REMOVAL/ABANDONMENT
Page I of 17
0SECTION 02 4114
2 UTILITY REMOVAL/ ABANDONMENT
3 PARTl-GENERAL
4 1.1 SUMMARY
5 A. Section Include s:
6 1. Direction for the removal , abandonment or salvaging of the following utilities :
7 a . Cathodic Protection Test Stations
8 b . Water Lines
9 c. Gate Valves
10 d. Water Valves
11 e. F ire Hydrants
12 f. Water Meters and Meter Box
13 g. Water Sampling Station
14 h. Concrete Water Vaults
I 5 i . Sanitary Sewer Lines
16 j. Sanitary Sewer Manholes
17 k. Sanitary Sewer Junction Boxes
18 I. Storm Sewer Lines
19 m. Storm Sewer Manhole Risers
20 n . Storm Sewer Junction Boxes
21 o. Storm Sewer Inlets
22 p. Box Culverts
23 q . Headwalls and Safety End Treatments
24 r. Trench Drains
25 B . Deviations from this City of F ort Worth Standard Specification
26 1. Removal of Existing Service Lines -The work for removal and disposal of the
27 existing water services to be replaced shall be considered subsidiary to the bid
28 price for the appropriate water service as specified in "Summary of Work" (01
29 11 00) and "Water Services 1-inch to 2-inch" (33 12 10).
30 C. Related Specification Sections include, but are not necessarily limited to :
31 1. Divi sion O -Bidding Requirements, Contract Forms and Conditions of the Contract
32 2. Division 1 -General Requirements
33 3. Section 03 34 13 -Controlled Low Strength Material (CLSM)
34 4. Section 33 05 10 -Utility Trench Excavation, Embedment and Backfill
35 5 . Section 33 05 24 -Installation of Carrier Pipe in Casing or Tunnel Liner Plate
36 6. Section 33 11 11 -Ductile Iron Fittings
37 7. Section 33 11 13 -Concrete Pressure Pipe, Bar-wrapped, Steel Cylinder Type
38 8. Section 33 11 14 -Buried Steel Pipe and Fittings
39 9. Section 33 12 25 -Co nnection to Existin g Water Mains
40 1.2 PRICE AND PAYMENT PROCEDURES
41 A. Utility Lines
CITY OF FORT WORTH
STANDARD CONSTRUCTION SP ECIFICATION DOCUMENTS
Revi sed December 20, 20 12
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No. I 04552
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
0241 14-2
UTILITY REMOVAL/ABANDONMENT
Page 2 of 17
1. Abandonment of Utility Line by Grouting
a. Measurement
1) Measurement for this Item shall be per cubic yard of existing utility line to
be grouted. Measure by tickets showing cubic yards of grout applied.
b. Payment
1) The work performed and materials furnished in accordance with this Item
and measured as provided under "Measurement" shall be paid for at the
unit price per cubic yard of "L ine Groutin g" for :
a) Various types of utility line
c. The price bid shall include :
1) Low density cellular grout or CLSM
2) Water
3) Pavement removal
4) Excavation
5) Hauling
6) Disposal of excess materials
7) Furnishing, placement and compaction of backfill
8) Clean-up
2. Utility Line Removal, Separate Trench
a . Measurement
1) Measurement for this Item shall be per linear foot of existing utility line to
be removed.
b . Payment
1) The work performed and materials furnished in accordance with this Item
and measured as provided under "Measurement" shall be paid for at the
unit price bid per linear foot of "Remove Line" for:
a) Various types of existing utility line
b) Various sizes
c. The price bid shall include:
1) Removal and disposal of existing utility pipe
2) Pavement removal
3) Excavation
4) Hauling
5) Disposal of excess materials
6) Furnishing, placement and compaction of backfill
7) Clean-up
3. Utility Line Removal, Same Trench
a. Measurement
1) This Item is considered subsidiary the proposed utility line being installed.
b. Payment
1) The work performed and materials furnished in accordance with this Item
are subsidiary to the installation of proposed utility pipe and shall be
subsidiary to the unit price bid per linear foot of pipe complete in place, and
no other compensation will be allowed.
4 . Manhole Abandonment
a . Measurement
1) Measurement for this Item will be per each manhole to be abandoned.
b. Payment
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised Decembe r 20, 20 I 2
2022 WATER SERVICE LEAK
REPAJR CONTRACT
City Project No. 104552
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
B.
0241 14 -3
UT ILITY REMOVAL/ ABANDONMENT
Page 3 of 17
1) The work performed and m aterials furni shed in accordance with this Item
and meas ured as provided under "Meas ure ment" shall be paid for at the
unit price bid p er each "Abandon M anhole" for:
a) Various diameters
b) Various types
c. The price bid shall include :
1) Removal and disposal of manhole cone
2) Removal , salvage and delivery of fram e and cover to City, if applicable
3) Cutting and plugging of existing sewer lin es
4) Concrete
5) Acceptable material for backfilling manhole void
6) Pavement removal
7) Excavation
8) Hauling
9) Disposal of excess materials
I 0) Furnishing, placement and compaction of backfill
11) Surface re storation
12) Clean-up
5 . Cathodic Test Station Abandonment
a. Measurement
I) Measurement for this Item will be per each cathodic test station to be
abandoned.
b . Payment
I) The work performed and materials furnished in accordance with this Item
and measured as provided under "Meas urement" shall be paid for at the
unit price bid per each "Abandon Cathodic Test Station".
c. The price bid shall include:
1) Abandon cathodic test station
2) CLSM
3) Pavement removal
4) Excavation
5) Hauling
6) Disposal of excess materials
7) Furnishing, placement and compaction of backfill
8) Clean-up
Water Lines and Appurtenances
I. Installation of a Water Line Pressure Plug
a. Measurement
1) Measurement for this Item shall be per each pressure plug to be installed .
b . Payment
I) The work performed and materials furnished in accordance with this Item
and measured as provided under "Meas urement" shall be paid for at the
unit price bid for each "Pressure Plug" installed for :
a) Various sizes
c. The price bid shall include :
1) Furnishing and installing pressure plug
2) Pavement removal
3) Excavation
4) Hauling
CITY OF FORT WORTH 2022 WATER SERVI CE LEAK
REPAIR CONTRACT
City Project No. 104552
ST AND ARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised De cember 20 , 2012
I
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
024114-4
UT! LITY REMOVAL/ ABANDONMENT
Page 4 of 17
5) Disposal of excess material
6) Gaskets
7) Bolts and Nuts
8) Furnishing, placement and compaction of embedment
9) Furnishing, placement and compaction of backfill
10) Disinfection
11) Testing
12) Clean-up
2. Abandonment of Water Line by Cut and installation of Abandonment Plug
a. Measurement
1) Measurement for this Item shall be per each cut and abandonment plug
installed.
b. Payment
1) The work performed and materials furnished in accordance with this Item
and measured as provided under "Measurement" shall be paid for at the
unit price bid for each "Water Abandonment Plug" installed for:
a) Various sizes
c. The price bid shall include:
1) Furnishing and installing abandonment plug
2) Pavement removal
3) Excavation
4) Hauling
5) CLSM
6) Disposal of excess material
7) Furnishing, placement and compaction of backfill
8) Clean-up
3 . Water Valve Removal
a. Measurement
1) Measurement for this Item will be per each water valve to be removed.
b. Payment
1) The work performed and materials furnished in accordance with this Item
and measured as provided under "Measurement" shall be paid for at the
unit price bid per each "Remove Water Valve" for:
a) Various sizes
c. The price bid shall include:
I) Removal and disposal of valv e
2) CLSM
3) Pavement removal
4) Excavation
5) Hauling
6) Disposal of excess materials
7) Furnishing, placement and compaction of backfill
8) Clean-up
4. Water Valve Removal and Salvage
a. Measurement
1) Measurement for this Item will be per each water valve to be removed and
salvaged.
b. Payment
CITY OF FORT WORTH
STANDARD CON STRUCTION SPECIFIC ATION DO C UMENTS
Revi sed December 20 , 20 12
2022 WATER SERVICE LE AK
REPAIR CONTRACT
City Project No. 104552
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
024114-5
UTILITY REMOVAL/ ABANDONMENT
Page 5 of 17
1) The work performed and materials furnished in accordance with this Item
and measured as provided under "Measurement" shall be paid for at the
unit price bid per each "·Salvage Water Valve" for:
a) Various sizes
c . The price bid shall include:
1) Removal and Salvage of valve
2) CLSM
3) Delivery to City
4) Pavement removal
5) Excavation
6) Hauling
7) Disposal of excess materials
8) Furnishing, placement and compaction of backfill
9) Clean-up
5. Water Valve Abandonment
a. Measurem ent
1) Measurement for this Item will be per each water valve to be abandoned.
b. Payment
1) The work performed and materials furnished in accordance with this Item
and measured as provided under "Measurement" shall be paid for at the
unit price bid per each "Abandon Water Valve" for:
a) Various Sizes
c. The price bid shall include:
1) Abandonment of valve
2) CLSM
3) Pavement removal
4) Excavation
5) Hauling
6) Disposal of excess materials
7) Furnishing, placement and compaction of backfill
8) Clean-u p
6 . Fire Hydrant Removal and Salvage
a. Measurement
1) Measurement for this Item will be per each fire hydrant to be removed.
b. Payment
1) The work performed and materials furnished in accordance with this Item
and measured as provided under "Measurement" shall be paid for at the
unit price bid per each "Salvage Fire Hydrant".
c. The price bid shall include:
1) Removal and salvage of fire hydrant
2) Delivery to City
3) Pavement removal
4) Excavation
5) Hauling
6) Disposal of excess materials
7) Furnishing, placement and compaction of backfill
8) Clean-up
7. Water Meter Removal and Salvage
a. Measurement
CITY OF FORT WORTH
ST AND ARD CONSTRUCTION SPECIFICATION DOCU MENTS
Revi sed December 20 , 2012
2022 WATER SERVICE LEAK
REPAfR CONTRACT
City Project No. 104552
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
02 4 1 14-6
UT ILITY REMOVAL/ ABA NDO NME NT
Page 6 of 17
1) Measurement for this Item will be per each water meter to be removed and
salvaged.
b . Payment
1) The work performed and materials furnished in accordance with this Item
and measured as provided under "Measurement" shall be paid for at the
unit price bid per each "Salvage Water Meter" for:
a) Various sizes
2) If a "Water Meter Service Relocate" is performed in accordance with
Section 33 12 10, removal and salvage or disposal of the existing (2-inch or
smaller) water meter shall be subsidiary to the cost of the "Water Meter
Service Relocate ", no other compensation will be allowed.
c . The price bid shall include:
1) Removal and salvage of water meter
2) Delivery to City
3) Pavement removal
4) E xcavation
5) Haulin g
6) Disposal of excess materials
7) Furnishing, placement and compaction of backfill
8) Clean-up
8. Water Sampling Station Removal and Salvage
a. Measurement
1) Measurement for this Item will be per each water sampling station to be
removed.
b. Payment
1) The work performed and materials furnished in accordance with this Item
and measured as provided under "Measurement" shall be paid for at the
unit price bid per each "Salvage Water Sampling Station".
c. The price bid shall include:
1) Removal and salvage of water sampling station
2) Delivery to City
3) Pavement removal
4) Excavation
5) Hauling
6) Disposal of excess materials
7) Furnishing, placement and compaction of backfill
8) Clean-up
9. Concrete Water Vault Removal
a. Measurement
1) Measurement for this Item will be per each concrete water vault to be
removed.
b. Payment
1) The work performed and materials furnished in accordance with this Item
and measured as provided under "Measurement" shall be paid for at the
unit price bid per each "Remove Concrete Water Vault".
c . The price bid shall include:
1) Removal and disposal of concrete water vault
2) Removal , salvage and delivery of frame and cover to City, if applicable
3) Removal , salvage and delivery of any valves to City, if applicable
CITY OF FORT WORTH
STANDARD CONSTRUC TIO N SPEC IFI CATIO N DOCU MENTS
Revi sed D ecember 20, 20 12
2022 WATER SERVICE LEAK
REPAIR CONTRACT
C ity Project No. 104552
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
C.
024 1 14 -7
UTILITY RE MO VAL/ABAND ONMENT
Page 7 of 17
4) Removal, salvage and delivery of any water meters to City, if applicable
5) Pavement removal
6) Excavation
7) Hauling
8) Disposal of excess materials
9) Furnishing, placement and compaction of backfill
10) Clean-up
Sanitary Sewer Lines and Appurtenances
1. Abandonment of Sanitary Sewer Line by Cut and installation of Abandonment Plug
a. Measurement
1) Measurement for this Item shall be per each cut and abandonment plug
installed .
b. Payment
1) The work performed and materials furnished in accordance with this Item
and measured as provided under "Measurement" shall be paid for at the
unit price bid for each "Sewer Abandonment Plug" for :
a) Various sizes
c. The price bid shall include:
I) Furnishing and installing abandonment plug
2) Pavement removal
3) Excavation
4) Hauling
5) CLSM
6) Disposal of excess material
7) Furnishing, placement and compaction of backfill
8) Clean-up
2. Sanitary Sewer Manhole Removal
a. Measurement
1) Measurement for this Item will be per each sanitary sewer manhole to be
removed.
b. Payment
1) The work performed and materials furnished in accordance with this Item
and measured as provided under "Measurement" shall be paid for at the
unit price bid per each "Remove Sewer Manhole" for:
a) Various diameters
c. The price bid shall include:
1) Removal and disposal of manhole
2) Removal, salvage and delivery of frame and cover to City , if applicable
3) Cutting and plugging of existing sewer lines
4) Pavement removal
5) Excavation
6) Hauling
7) Disposal of excess materials
8) Furnishing, placement and compaction of backfill
9) Clean-up
3. Sanitary Sewer Junction Structure Removal
a. Measurement
1) Measurement for this Item will be per each sanitary sewer junction
structure being removed.
C ITY OF FORT WORTH 2022 WATER SERVI CE LEAK
REPAIR CONTRACT
City Proj ect No. 104552
ST AND ARD CONSTRUCTION SPECIFI CATION DOC UMENTS
Revised Dece mber 20 , 20 12
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
D.
024 1 14-8
UTILITY RE MOVAL/AB AN DO NMEN T
Page 8 of 17
b. Payment
1) The work performed and mate rials furnished in accordance with this Item
and meas ured as provided under "Measurement" shall be paid for at the
lump sum bid per each "Remove Sewer Junction Box" location.
c . The price bid shall include :
1) Removal and disposal of junction box
2) Removal , salvage and delivery of frame and cover to City .
3) Pavement removal
4) E xcavation
5) Hauling
6) Disposal of excess materials
7) Furnishing, placement and compaction of backfill
8) Clean-up
Storm Sewer Lines and Appurtenances
1. Abandonment of Storm Sewer Line by Cut and installation of Abandonment Plug
a. Measurement
I) Measurement for this Item shall be per each cut and abandonment plug to
be installed.
b. Payment
1) The work performed and materials furnished in accordance with this Item
and measured as provided under "Measurement" shall be paid for at the
unit price bid for each "Storm Abandonment Plug" installed for:
a) Various sizes
c . The price bid shall include:
I) Furnishing and installing abandonment plug
2) Pavement removal
3) Excavation
4) Hauling
5) CLSM
6) Disposal of excess material
7) Furnishing, placement and compaction of backfill
8) Clean-up
2. Storm Sewer Manhole Removal
a. Measurement
I) Measurement for this Item wi II be per each storm sewer manhole to be
removed.
b. Payment
1) The work performed and materials furnished in accordance with this Item
and measured as provided under "Measurement" shall be paid for at the
unit price bid per each "Remove Manhole Riser" for:
a) Various sizes
c. The price bid shall include:
1) Removal and disposal of manhole
2) Removal, salvage and delivery of frame and cover to City, if applicable
3) Pavement removal
4) Excavation
5) Hauling
6) Disposal of excess materials
7) Furnishing, placement and compaction of backfill
C ITY OF FO RT WORTH 2022 W ATER SERVI CE LEAK
REPAIR CO NTRACT
C ity Proj ect No. I 04 552
STANDARD CON STRUCTION SPEC IFI CATION DOCUMENTS
Revi sed December 20, 20 12
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
8) Clean-up
3. Storm Sewer Junction Box Removal
a. Measurement
024114-9
UTILITY REMOVAL/ABANDONMENT
Page 9 of 17
1) Measurement for this Item will be per each storm sewer junction structure
to be remov ed .
b . Pay ment
l) The work performed and materials furnished in accordance with this Item
and measured as provided under "Measurement" shall be paid for at the
unit pric e bid per each "Remove Storm Junction Box" for:
a) Various sizes
c. The price bid shall include :
1) Removal and disposal of junction bo x
2) Removal , salvage and delivery of frame and cover to City, if applicable
3) Pavement removal
4) Excavation
5) Hauling
6) Disposal of excess materials
7) Furnishing, placement and compaction of backfill
8) C lean-up
4 . Storm Sewer Junction Structure Removal
a. Measurement
1) Measurement for this Item will be per each storm sewer junction structure
being removed.
b. Payment
1) The work performed and materials furnished in accordance with this Item
and measured as provided under "Meas ur ement" shall be paid for at the
lump sum bid per each "Remove Storm Junction Structure" location.
c. The price bid shall include:
1) Removal and disposal of junction structure
2) Removal , salvage and de livery of frame and cover to City, if applicable
3) Pavement removal
4) Excavation
5) Hauling
6) Disposal of excess material s
7) Furnishing, placement and compaction of backfill
8) Clean-up
5. Storm Sewer Inlet Removal
a. Measurement
1) Measurement for this Item will be per each storm sewer inlet to be
removed.
b . Pay ment
1) The work performed and material s furnished in accordance with this Item
and measured as provided under "Measurement" shall be paid for at the
unit price bid per each "Remove Storm Inlet" for:
a) Various types
b) Various s izes
c. The price bid shall include:
1) Removal and disposal of inlet
2) Pavement removal
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised December 20, 20 12
2022 WATER SERVJCE LEAK
REPAIR CONTRACT
City Project No. 104552
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
024 1 14 -10
UTILITY RE MO VAL/ ABANDONMENT
Page 10 of 17
3) Excavation
4) Hauling
5) Di spo sal of excess material s
6) Furnishin g , placement and compaction of backfill
7) Clean -up
6 . Storm Sewer Junction Bo x Removal
a. Measurement
1) Meas urement for this Item shall be per linear foot of existin g storm sewer
box to be removed.
b. Payment
1) The work performed and materials furnished in accordance with this Item
and measured as provided under "Measurement" shall be paid for at the
unit price bid per linear foot of "Remov e Storm Junction Box" for all si zes .
c . The price bid shall include:
1) Removal and disposal of Storm Sewer Box
2) Pavement removal
3) Excavation
4) Hauling
5) Disposal of excess materials
6) Furnishing, placement and compaction of backfill
7) Clean -up
7 . Headwall/SET Removal
a . Measurement
1) Measurement for this Item will be per each headwall or safety end
treatment (SET) to be removed.
b. Payment
1) The work performed and materials furnished in accordance with this Item
and measured as provided und er "Measurement" shall be paid for at the
unit price bid per each "Remove Headwall/SET".
c. The price bid shall include :
1) Removal and disposal of Headwall/SE T
2) Pavement removal
3) Excavation
4) Hauling
5) Disposal of excess materials
6) Furnishing, placement and compaction of backfill
7) Clean-up
8. Trench Drain Removal
a. Measurement
1) Measurement for this Item shall be per linear foot of storm sewer trench
drain to be removed .
b. Payment
1) The work performed and materials furnished in accordance with this Item
and measured as provided under "Measurement" shall be paid for at the
unit price bid per linear foot of "Remove Trench Drain" for:
a) Various sizes
c. The price bid shall include:
1) Removal and disposal of storm sewer line
2) Pavement removal
CITY OF FORT WORTH
STANDARD CO NS TRUCTIO N SPECIFICATION DOCUMENT S
Rev ised Dece mber 20 , 20 12
2022 WATER SERVI CE LEAK
REPAIR CONTRACT
C ity Proj ec t N o. I 04 552
1 3) Excavat ion
2 4) Hauling
3 5) Disposal of excess materials
02 41 14-11
UTI LITY REMOVAL/ABANDONMENT
Page 11 of 17
4 6) Furnishing, placement and compaction of backfi ll
5 7) Clean-up
6 1.3 REFERENCES [NOT USED]
7 1.4 ADMINISTRATIVE REQUIREMENTS
8 A . Coordination
9 1. Contact In s pector and the Water Department F ield Operation Storage Yard for
10 coordination of salvage material return.
11 1.5 SUBMITT ALS [NOT USED]
12 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
13 1. 7 CLOSEOUT SUBMITT ALS [NOT USED]
14 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
15 1.9 QUALITY ASSURANCE [NOT USED)
16 1.10 DELIVERY, STORAGE, AND HANDLING
17 A. Storage and Handling Requirement s
18 1. Protect and salvage all materials s uch that no damage occurs during delivery to the
19 City.
C ITY OF FORT WORTH
ST AND ARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised December 20, 2012
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No . I 04552
024 1 14 -1 2
UTILITY RE MOV AL/AB AN DONMEN T
Page 12 of 17
1 1.11 FIELD [SITE] CONDITIONS [NOT USED]
2 1.12 WARRANTY [NOT USED]
3 PART2-PRODUCTS
4 2.1 OWNER-FURNISHED [oR] OWNER-SUPPLIED PRODUCTS [NOT USED]
5 2.2 MATERIALS
6 2.3 ACCESSORIES [NOT USED]
7 2.4 SOURCE QUALITY CONTROL [NOT USED]
8 PART 3 -EXECUTION
9 3.1 INSTALLERS [NOT USED]
10 3.2 EXAMINATION [NOT USED]
11 3.3 PREPARATION [NOT USED]
12 3.4 REMOVAL, SALVAGE, AND ABANDONMENT
13 A . General
14 I. Manhole Abandonment
15 a . All manholes that are to be taken out of service are to be removed unless
16 specifically requested and/or approved by City.
17 b. Excavate and backfill in accordance with Section 33 05 10.
18 c. Remove and salvage manhole frame and cover as coordinated with City.
19 d. Deliver salvaged material to the City.
20 e . Cut and plug sewer lines to be abandoned.
21 f. Backfill manhole void in accordance with City Standard Detail s.
22 B . Water Lines and Appurtenances
23 1. Water Line Pressure Plugs
24 a. Ductile Iron Water Lines
25 1) Excavate, embed, and backfill in accordance with Section 33 05 10 .
26 2) Plug with an MJ Plug with mechanical restraint and blocking in accordance
27 with Section 33 11 11.
28 3) Perform Cut and Plug in accordance with Section 33 12 25.
29 b. PVC C900 and C905 Water Lines
30 1) Excavate, embed, and backfill in accordance with Section 33 05 10.
31 2) Plug with an MJ Plug with mechanical restraint and blocking in accordance
32 with Section 33 11 11.
33 3) Perform Cut and Plug in accordance with Section 33 12 25.
34 c. Concrete Pressure Pipe, Bar Wrapped, Steel Cylinder Type Water Lines
35 1) Excavate, embed, and backfill in accordance with Section 33 05 10
36 2) Plug using:
37 a) A fabricated plug restrained by welding or by a Snap Ring in
38 accordance with Section 33 11 13 ; or
CITY OF FORT WORTH
STANDARD CONS TRUCTIO N SPEC IFI CA TI ON DOCUMEN TS
Re vise d Decemb er 20, 20 I 2
2022 WATER SERY1 CE LEAK
REPAIR CONTRACT
City Proj ect No. 104552
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
2 1
22
23
24
25
26
27
28
29
30
3 1
32
33
34
35
36
37
3 8
39
40
41
42
4 3
44
45
46
47
48
024 11 4 -13
UTILITY REMOVAL/ABANDONMENT
Page 13 of 17
b) A blind flan ge in accordance with Section 33 11 13
3) P erform Cut and Plug in accordance with Section 33 12 25.
d. Buried Steel Water Lines
1) Excavate , embed, and backfill in acco rdan ce with Section 33 05 10 .
2) Plug usin g :
a) A fabricated p lu g re strain ed by welding in accordance with Section 33
1114;or
b) A blind flange in accordance w ith Section 33 11 14
3) P erform Cut and Plug in accordance with Section 33 12 25 .
2. Water Line Abandonment Plug
a. Excavate and backfill in accordance with Section 33 05 10.
b. Plug with CLSM in accordance with Section 03 34 13.
3 . Water Line Abandonment by Grouting
a . Excavate and backfill in accordance w ith Section 33 05 10 .
b . Dewater from existing lin e to be grouted.
c . Fill line with Low Density Ce llul ar Grout in accordance with Section 33 05 24
or CLSM in accordance with 03 34 13.
d. Dispose of any excess m aterial.
4. Water Line Removal
a. Excavate and backfill in accordance with Section 33 05 10 .
b . Cut existing line from the utility system prior to removal.
c. Cut any serv ices prior to removal.
d. Remove existing pip e lin e and properly di s pose as approved by City.
5. Water Valve Removal
a. Excavate and bac kfill in accordance with Section 33 05 10 .
b. Remove and dispose of valve bonnet, wedge and stem.
c. F ill valve body with CLSM in accordance with Section 03 34 13 .
6. Water Valve Removal and Salv age
a. Excavate and backfill in accordance w ith Section 33 05 10.
b . Remove valve bonnet, wedge and stem.
c. Deliver salvaged material to the Water Department Field Operation Storage
Yard .
d. Protect salvaged materials from damage.
e. Fill valve body with CLSM in accordance with Section 03 34 13 .
7. Water Valve Abandonment
a. Excavate and backfill in accordance with Section 33 05 10 .
b . Remove the top 2 feet of the valve stack and any valve extensions.
c. Fill the remainin g valve stack w ith CLSM in accordance with Section 03 34 13 .
8. Fire Hy drant Removal and Sa lvage
a . Excavate and backfill in accordance with Section 33 05 10 .
b. Remove Fire Hydrant.
c. Place abandonm ent plug on fire hydrant lead line.
d . Deliver salvaged fire hydrant to the Water Department Field Operation Storage
Yard.
e. Protect salv aged materials from damage.
9. Water Meter Removal and Salvage
a. Remove and salvage water meter.
b. Return salvaged meter to Project Repres entative.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised December 20, 2012
2022 WATER SERVI CE LEAK
REPA IR CONTRACT
City Project No. I 04552
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
C.
02 4 1 14-14
UTILITY RE MOV AL/ABAN DONMEN T
Page 14 of 17
c . City will provide replacement meter for installation.
d. Meter Box and Lid
1) Remove and salvag e cast iron meter box lid.
2) Remove and dispose of any non-cast iron meter box lid .
3) Return salvaged material to the Water Department Fie ld Operation Storage
Yard .
4) Remove and dispose of meter box.
10. Water Sample Station Removal and Salvage
a. Remove and salv age existing water sample station.
b. Deliver salvaged material to the Water Department Field Operation Storage
Yard.
11. Concrete Water Vault Removal
a. Excavate and backfill in accordance with Section 33 05 10.
b. Remove and salvage vault lid.
c . Remove and salvage valv es .
d. Remove and salv age meters.
e. Deliver salvaged material to the Water Department Field Operation Storage
Yard.
f. Remove and dispose of any piping or other appurtenances.
g. Demolish and remove entire concrete vault.
h. Dispose of all excess materials.
12. Cathodic Test Station Abandonment
a. Excavate and backfill in accordance with Section 33 05 10
b. Remove the top 2 feet of the cathodic test station stack and contents .
c. Fi ll any remaining voids with CLSM in accordance with Section 03 34 13.
Sanitary Sewer Lines and Appurtenances
1. Sanitary Sewer Line Abandonment Plug
a . Excavate and backfi ll in accordance with Section 33 05 10.
b. Remove and dispose of any sewage.
c. Plug with CLSM in accordance with Section 03 34 13.
2. Sanitary Sewer Line Abandonment by Grouting
a. Excavate and backfill in accordance with Section 33 05 10.
b. Dewater and dispose of any sewage from the existing line to be grouted.
c . Fill line w ith Low Density Ce llular Grout in accordance with Section 33 05 24
or CLSM in accordance with 03 34 13.
d. Dispose of any excess material.
3. Sanitary Sewer Line Removal
a. Excavate and backfill in accordance with Section 33 05 10.
b. Cut existing line from the utility system prior to removal.
c. C ut any services prior to removal.
d. Remove existing pipe line and properly dispose as approved by City.
4 . Sanitary Sewer Manholes Removal
a. All sanitary sewer manholes that are to be taken out of service are to be
removed unless specifically requested and/or approved by City.
b. Excavate and backfill in accordance with Section 33 05 10.
c. Remove and salvage manhole frame and cover.
d . Deliver salv aged material to the Water Department Field Operation Storage.
e. Demolish and remove entire concrete manhole.
CITY OF FORT WORTH 2022 WATER SERVI CE L EAK
REPAIR CONTRACT
C ity Proj ect No. I 04552
STANDARD CONSTRUCTION SPEC IFI CATI ON DO CUMENTS
Re vised Decembe r 20, 20 12
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
D.
024 1 14-1 5
UTILITY REMOVAL/ABA NDON ME NT
Page 15 of 17
f. Cut and plug sewer lines to be abandoned.
5. Sanitary Sewer Junction Structure Removal
a. Excavate and backfill in accordance with Section 33 05 10.
b . Remove and salvage manhole frame and cover.
c. Deliver salvaged material to the Water Department Field Operation Storage.
d. Demolish and remove entire concrete manhole.
e. Cut and plug sewer lines to be abandoned.
Storm Sewer Lines and Appurtenances
1. Storm Sewer Abandonment Plug
a. Excavate and backfill in accordance with Section 33 05 10 .
b. Dewater line.
c . Plug with CLSM in accordance with Section 03 34 13.
2. Storm Sewer Line Abandonment by Grouting
a . Excavate and backfill in accordance with Section 33 05 10.
b . Dewater the existing line to be grouted .
c. Fill line with Low Density Cellular Grout in accordance with Section 33 05 24
or CLSM in accordance with 03 34 13.
d . Dispose of any excess material.
3. Storm Sewer Line Removal
a. Excavate and backfill in accordance with Section 33 05 10 .
b. Remove existing pipe line and properly di spose as approved by City.
4. Storm Sewer Manhole Removal
a. All storm sewer manholes that are to be taken out of service are to be removed
unless specifically requested and/or approved by City.
b. Excavate and backfill in accordance with Section 33 05 10.
c. Demolish and remove entire concrete manhole .
d. Cut and plug storm sewer lines to be abandoned.
5. Storm Sewer Junction Box and/or Junction Structure Removal
a. Excavate and backfill in accordance with Section 33 05 10.
b. Demolish and remove entire concrete structure .
c. Cut and plug storm sewer lines to be abandoned .
6. Storm Sewer Inlet Removal
a. Excavate and backfill in accordance with Section 33 05 10.
b . Demolish and remove entire concrete inlet.
c . Cut and plug storm sewer lines to be abandoned .
7. Storm Sewer Box Removal
a. E xcavate and backfill in accordance with Section 33 05 10.
b . Cut existing line from the utility system prior to removal.
c. Cut any services prior to removal.
d. Remove existing pipe line and properly dispose a s approved by City.
8. Headwall/S E T Removal
a. Excavate and backfill in accordance with Section 33 05 10.
b. Demolish and remove entire concrete inlet.
c . Cut and plug storm sewer lines to be abandoned.
9. Storm Sewer Trench Drain Removal
a . E xcavate and backfill in accordance with Section 33 05 10.
b. Remove existing pipe line and dispose as approved by City.
CITY O F FORT WORTH 2022 WATER SERVI CE LEAK
REP AIR CO NTRACT
C ity Proj ec t No. I 04552
ST ANDARD CONSTRUCTIO N SP EC IFI C ATION DOCUMENTS
Rev ised Decembe r 20, 20 12
2
3
4
5
6
7
8
9
10
11
3.5 REPAIR/ RESTORATION [NOT USED]
3.6 RE-INSTALLATION [NOT USED]
3.7 FIELD [oR] SITE QUALITY CONTROL
3.8 SYSTEM STARTUP [NOT USED]
3.9 ADJUSTING [NOT USED]
3.10 CLEANING [NOT USED]
3.11 CLOSEOUT ACTIVITIES [NOT USED)
3.12 PROTECTION [NOT USED]
3.13 MAINTENANCE [NOT USED]
3.14 ATTACHMENTS [NOT USED]
CITY OF FORT WORTH
ST AND ARD CONSTRUCT ION SPECIFJCA TIO N DO CUMEN TS
Revi sed December 20 , 20 12
024 1 14-16
UT ILI TY REMOVAL/ ABANDO NMENT
Page 16 of 17
2022 WATER SERV ICE LEAK
REPAIR CONTRACT
C ity Project No. 104 552
2
DATE NAME
12/20/12 D . Johnson
CITY OF FORT WORTH
END OF SECTION
Revision Log
024114-17
UT! LITY REMOVAL/ ABANDONMENT
Pa ge 17 of 17
SUMMARY OF CHANGE
1.2.C.3.c. -Include Frame and Cover in Payment description
Throughout -added abandonment of storm and sewer manholes when requested
and/or approved by City
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised December 20, 20 12
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No. I 04552
32 0 1 17 -I
PERMA NENT ASPHALT PAVING RE PAIR
1 SECTION 32 0117
2 PERMANENT ASPHALT PAVING REPAIR
3 PARTl-GENERAL
4 1.1 SUMMARY
5 A . Section includes :
6
7
8
9
10
11
1. Flexible pav e ment repair to include, but not limited to:
a . Utility cuts (water, sanitary sewer, drainage, franchise utilities , etc.)
b. Warranty work
c. Repairs of damage caused by Contractor
d. Any permanen t asphalt pavement repair needed during the course of
construction
12 B. Deviations from this City of Fort Worth Standard Specification
Page I of5
13 1. Asphalt Pavement Repair, Water Services-The asphalt pavement repair work
14 covered by these Specifications is included in the unit bid price of the
15 appropriate water service to be installed or repaired. All asphalt paving repair
16 as specified under 1.2-A-2. "Asphalt Pavement Repair for Utility Service
17 Trench" up to 4-foot wide is considered s ubsidiary to the appropriate water
18 service bid item and specified in "Water Services 1-inch to 2-inch" (33-12-10).
19 When asphalt pavement repair in addition to the 4-foot wide trench repair is
20 required as directed by the City, the additional work will be paid for at the
21 square yard price bid for "3-inch Extra Width Asphalt Pavement Repair" as
22 specified under 1.2-A-4 below.
23 C. Related Specification Sections include, but are not necessar ily limited to:
24 1. Divi s ion 0 -Bidding Requirements, Contract Forms, and Conditions of the
25 Contract
26 2. Divi s ion 1 -General Requirements
27 3. Section 03 34 16 -Concrete Base Material for Trench Repair
28 4. Section 32 12 16 -Asphalt Paving
29 5. Section 32 13 13 -Concrete Paving
30 6. Section 33 05 10 -Utility Trench Excavation, Embedment and Backfill
31 1.2 PRICE AND PAYMENT PROCEDURES
32 A. Measurement and Payment
33 1. Asphalt Pavement Repair
34 a. Meas urement
35 1) Meas urement for this Item will be by the linear foot of Asphalt Pavement
36 Rep air base d on the defined width and roadway class ifi cation specified in the
37 Drawings.
38 b . Payment
39 1) The work performed and materials furnished in accordance with this Item
40 and measured as provided under "Measurement" wi ll be paid for at the un it
41 price bid price per linear foot of Asphalt Pavement Repair.
CITY OF FORT WORTH
ST AND ARD CONSTRUCTION SPECIFIC ATION DOCUMEN TS
Revi sed December 20 , 20 12
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No. I 04552
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
32 OJ 17 -2
PERMANENT ASPHALT PA YING REPAIR
Page 2 of5
c . The price bid shall include:
1) Preparing final surfaces
2) Furnishing, loadin g, unlo ading, storin g, haulin g and handlin g all material s
includin g freight and ro yalty
3) Traffic control for all testing
4) Asphalt, aggre gate , and additive
5) Materials and work n ee ded for corrective action
6) Trial batches
7) Tack coat
8) Removal and/or swee ping excess material
2. Asphalt Pavement Repair for Uti lity Service Trench
a. Measurement
1) Measurement for this Item will be by the linear foot of Asphalt Pavement
Repair centered on the propo se d sewer service lin e measured from the face of
curb to the limit of the Aspha lt Pavement Rep a ir for the main se wer line.
b. Payment
1) The work performed and materials furnished in accordance with thi s Item
and measured as provided under "Measurement" will be paid for at the unit
price bid price per linear foot of "Asphalt Pavement Repair, Service" installed
for:
a) Various types of utilities
c. The price bid shall include:
1) Preparing final surfaces
2) Furnishing, loading, unloading, storing, haulin g and handling all materials
including freight and royalty
3) Traffic control for all testing
4) Asphalt, aggregate, and additive
5) Materials and work needed for corrective action
6) Trial batches
7) Tack coat
8) Removal and/or sweeping excess material
3. Asphalt Pavement Repair Beyond Defined Width
a. Measurement
1) Measurement for this Item wi ll be by the square yard for asphalt pavement
repair beyond pay limits of the defined width of Asphalt Pavement Repair by
roadway classification specified in the Drawings .
b . Payment
1) The work performed and materials furnished in accordance with this Item
and measured as provided under "Measurement" will be paid for at the unit
price bid per square yard of Asphalt Pavement Repair Beyond Defined Width .
c. The price bid shall include :
1) Preparing final surfaces
2) Furnishing, lo ading, unloading, storing, hauling and handling all materials
including freight and royalty
3) Traffic control for all testing
4) Asphalt, aggregate , and additive
5) Materials and work needed for corrective action
6) Trial batches
7) Tack coat
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUME TS
Revised December 20, 2012
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No. I 04552
32 0 I 17 -3
PERMANENT ASPHALT PAVING REPA IR
Page3of5
1 8) Removal a nd/or sweeping excess material
2 4. Extra Width Asphalt Pavem ent Rep a ir
3 a. Measurement
4 1) Measurement for thi s Item will b e by the sq uare yard for surface repair
5 (does not in c lude b ase rep a ir) for :
6 a) Various thicknesses
7 b. Payment
8 1) The work performe d and material s furnished in accordance with this Item
9 and measured as provide d under "Meas ur ement" will be pa id for at the unit
Io price bid per square yard of Extra Width Asphalt Pavement Repair
11 c. The price bid shall include:
12 1) Preparing final surfaces
13 2) Furnishing, loading, unloading, storing, ha uling and handling all mater ial s
14 including freight and royalty
15 3) Traffic control for all testin g
16 4) Asphalt, aggregate, and additive
17 5) Materials and work needed for corrective action
18 6) Trial batches
19 7) Tack coat
20 8) Removal and/or sweeping excess material
21 1.3 REFERENCES
22 A. Definition s
23 1. H .M.A.C. -Hot Mi x Asphalt Concrete
24 1.4 ADMINISTRATIVE REQUIREMENTS
25 A. Permitting
26 1. Obtain Street Use Permit to make utility cuts in the street from the Transportation
27 and Public Works D e partment in conformance with current ordinances.
28 2 . The Transportation and Public Works Department will inspect the paving repair
29 after construction .
3 0 1.5 SUBMITT ALS [NOT USED]
31 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS
32 A. Asphalt Pavement Mi x Design : submit for approval: see Section 32 12 16.
33 1.7 CLOSEOUT SUBMITTALS [NOT USED]
34 1.8 MAINTENANCE MATERIAL SUBMITT ALS [NOT USED]
35 1.9 QUALITY ASSURANCE [NOT USED]
36 1.11 DELIVERY, STORAGE, AND HANDLING [NOT USED]
37 1.12 FIELD CONDITIONS
38 A. Place mixture when the roadway surface temperature is 45 degrees For higher and
39 risin g unless otherw ise approved.
CITY OF FORT WORTH
STANDARD CONSTRUCTIO N SPECIFI CATION DOCUMENTS
Revised December 20, 20 I 2
2022 WATER SERVI CE LEAK
REPAIR CONTRACT
City Project No. I 04552
32 0 1 17 -4
PERMANENT ASPHALT PA VJNG REPA IR
Page 4 of5
1.13 WARRANTY [NOT USED]
2 PART2-PRODUCTS
3 2.1 OWNER-FURNISHED [NOT USED]
4 2.2 MATERIALS
5 A. Backfill
6 1. See Section 33 05 10 .
7 B. Base Material
8 1. Concrete Base Material for Trench Repair: See Section 03 34 16.
9 2. Concrete Base: See Section 32 13 13.
10 C. Asphalt Paving: see Section 32 12 16 .
I 1 I. H.M.A .C. p a ving: T y pe D.
12 2.3 ACCESSORIES [NOT USED]
13 2.4 SOURCE QUALITY CONTROL (NOT USED]
14 PART 3-EXECUTION
15 3.1 INSTALLERS [NOT USED]
16 3.2 EXAMINATION [NOT USED]
17 3.3 PREPARATION
18 A. Surface Preparation
19 1. Mark pavement cut for repairs for approval by the City.
20 2. Contractor and City meet prior to saw cutting to confirm limits of repairs.
21 3.4 INSTALLATION
22 A. General
23 I . Equipment
24 a. Use machine intended for cutting pavement.
25 b. Milling machines may be used as long as straight edge is mainta in ed .
26 2. Repairs: In true and straight lines to dimens ions shown on the Drawings.
27 3. Utility Cuts
28 a. In a true and straight line on both sides of th e trench
29 b. Minimum of 12 inches outside the trench walls
30 c. If the existing fle x ible pavement is 2 feet or less between the lip of the existing
31 gutter and the e dge of the trench repair, remove th e existing paving to such
32 gutter.
33 4. Limit dust and res idues from sawing from entering the atmosphere or drainage
34 facilities.
35 B . R emoval
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised Decem be r 20 , 2012
2022 WATER SER VICE LEAK
REPAIR CONTRACT
City Proj ect No. 104552
32 0 I 17 -5
PERMANENT ASPHALT PAVING REPAJR
Pa ge 5 of5
1. Use care to preve nt fract ur in g existin g pave men t structure adj ace nt t o th e re pa ir
2 area.
3 C. Base
4 1. Install re pl ace me nt base m ateria l as sp ecifie d in D rawi ngs.
5 D . Aspha lt Paving
6 1. H.M.A.C pl ace m ent: in accord a nce w it h Section 32 12 16
7 2 . Type D s urface mix
8 3 . D epth : as s pecified in D raw in gs
9 4 . Pl ace s urface m ix in li fts n ot to exceed 3 in c hes .
10 5. Last or to p li ft sha ll not be less th a n 2 in ches t hi ck.
1 I 3.5 REPAIR/RE STORATION [NOT USE D]
12 3.6 RE-IN STALLATION [NOT USE D]
13 3.7 FIELD QUA LITY CO NTROL [NOT USED]
14 3.8 SYST EM STARTUP [NOT U SED]
15 3.9 ADJUSTING [NOT US ED]
16 3.10 CLEANIN G [NOT U SE D]
17 3.11 CLO SE OUT ACTIVITIE S [NOT USE D]
18 3.12 PROT ECTION [NOT US ED]
19 3.13 MAINTENANC E [NOT USED]
2 0 3.14 ATTACHMENT S [NOT USED]
21
22
23
END OF SECTIO N
Revis io n Log
DATE NAME SUMMARY OF CHANGE
1.2.A -Modified Items to be inc luded in price bid ; Added blu e text for clarification
24
12/20/20 12 D. Johnson of repair width on uti lity trench repair; Added a bid item fo r uti li ty serv ice trench
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMEN TS
Revised December 20, 2012
repair.
2022 WATER SERVI CE LEAK
REPAIR CONTRACT
City Project No. I 04552
32 0 1 29 -I
C O NCRETE PAVING R EPA IR
Page I of 4
SECTION 32 01 29
2 CONCRETE PA YING REPAIR
3 PARTl-GENERAL
4 1.1 SUMMARY
5 A. Section includes:
6 1. Concrete pavement repair to include, but not limited to:
7 a. Utility cuts (water, sanitary sewer, drainage, etc.)
8 b. Warranty work
9 c. Repairs of damage caused by Contractor
JO d . Any other concrete pavement repair needed during the course of construction
11 B . Deviations from this City of Fort Worth Standard Specification
12 1. Concrete Pavement Repair, Water Services-The concrete pavement repair
13 work covered by these Specifications is included in the unit bid price of the
14 appropriate water service to be installed or repaired. All concrete paving
15 repair up to 4-foot wide is considered subsidiary to the appropriate water
16 service bid item and specified in "Water Services 1-inch to 2-inch" (33-12-10).
17 When concrete pavement repair in addition to the 4-foot wide trench repair is
18 required as directed by the City, the additional work will be paid for at the
19 square yard price bid for "Concrete Pavement Repair" as specified below.
20 C. Related Specification Sections include, but are not necessarily limited to:
21 1. Division O -Bidding Requirements , Contract Forms, and Conditions of the Contract
22 2. Division 1 -General Requirements
23 3. Section 32 01 18 -Temporary Asphalt Paving Repair
24 4. Section 32 12 16 -Asphalt Paving
25 5. Section 32 13 13 -Concrete Paving
26 6. Section 33 05 10 -Utility Trench Excavation , Embedment and Backfill
27 1.2 PRICE AND PAYMENT PROCEDURES
28 A. Measurement and Payment
29 1. Concrete Pavement Repair
30 a. Measurement
31 1) Measurement for this Item shall be by the square yard of Concrete
32 Pavement Repair for various:
33 a) Street types
34 2) Limits of repair will be based on the time of service of the existing
35 pavement. The age of the pavement will need to be determined by the
36 Engineer through coordination with the City. For pavement ages:
37 a) 10 years or less : repair entire panel
38 b) Greater than 10 years: repair to limits per Drawings
39 b . Payment
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFI C ATIO N DOCUMENTS
Revi sed December 20 , 20 12
2022 WATER SERVI CE LEAK
REPAIR CON TRACT
C ity Project No. I 045 52
32 01 29 -2
CONCRETE PAYING REPAIR
Page2of4
1) The work performed and materials furnished in accordance with this Item
2 and m easured as provided und er "Measurement" shall be paid for at the
3 u nit price bid per square yard of Concrete Pavement Repair
4 c. The price bid shall include:
5 1) Shaping and fine grading the placement area
6 2) Furnis hin g and app lying all water required
7 3) Furnis hing, loading and unl oading, storing, hauling and ha ndlin g all
8 concrete
9 4) Furn is hin g, lo ading and unl oad ing, stor in g, h auli ng and handling all base
10 material
11 5) Mixing, pl ac in g, finishing and c urin g a ll concrete
12 6) F urni shin g and installing reinforcing stee l
13 7) F urni shing a ll m aterials and pl acing longitudin al , warping, expansion and
14 contraction joints, including a ll ste el dowels, dowel caps and lo ad
15 transmis s ion units required , wire and devices for placing, holdin g and
16 supporting the steel bar, lo ad transmission units, and joint filler in the
17 proper po sition; for coating stee l bars where required by the Drawings
18 8) Sealingjoints
I 9 9) Mono lithically p o ured curb
20 10) Cleanup
2 1 1.3 REFERENCES [NOT USED]
22 1.4 ADMINISTRATIVE REQUIREMENTS
23 A. Permitting
24 1. Obtain Street Use Permit to m ake utili ty cuts in the street from the Transportation
25 and Public Works Department in conformance with current ordinances.
26 2. Transportat ion and Publi c Works D epartment wi ll inspect paving repair after
27 construction.
28 1.5 SUBMITT ALS [NOT USED]
29 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS
30 A. Concrete Mix Design: su bmit for ap proval in accordance with Section 32 13 13.
3 1 1. 7 CLOSEOUT SUBMITT ALS [NOT USED]
32 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
33 1.9 QUALITY ASSURANCE [NOT USED]
34 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
35 1.11 FIELD CONDITIONS
36 A. Weather Conditions: Place concrete as specifi ed in Section 32 13 13 .
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUME TS
Revi sed December 20 , 2012
2022 WATER SERVICE LEAK
REP AlR CONTRACT
City Proj ect No . I 04552
1.12 WARRANTY [NOT USED]
2 PART2-PRODUCTS
3 2.1 OWNER-FURNISHED PRODUCTS [NOT USED]
4 2.2 MATERIALS
5 A. Embedment and Backfill: see Section 33 05 10.
6 B. Base material: Concrete base: see Section 32 13 13 .
7 C. Concrete: see Section 32 13 13.
8 1. Concrete paving: Class H or Class HES.
9 2. Replace concrete to the specified thickness .
10 2.3 ACCESSORIES [NOT USED]
11 2.4 SOURCE QUALITY CONTROL [NOT USED]
12 PART 3 -EXECUTION
13 3.1 INSTALLERS [NOT USED]
14 3.2 EXAMINATION [NOT USED]
15 3.3 PREPARATION
32 0 1 29 -3
CONCRETE PA VfNG REPAIR
Page 3 of4
16 A. Replace a continuous section if multiple repairs are closer than 10 feet apart from edge
17 of one repair to the edge of a second repair.
18 B. If the cut is to be covered, use steel plates of sufficient strength and thickness to support
19 traffic.
20 1. Construct a transition of hot-mix or cold-mix asphalt from the top of the steel plate
21 to the existing pavement to create a smooth riding surface.
22 a . Hot-mix or cold-mix asphalt: conform to the requirements of Section 32 12 16 .
23 C. Surface Preparation: mark pavement cut repairs for approval by the City.
24 3.4 INSTALLATION
25 A. Sawing
26 1. General
27 a. Saw cut perpendicular to the surface to full pavement depth.
28 b. Saw cut the edges of pavement and appurtenances damaged subsequent to
29 sawing to remove damaged areas.
30 c . Such saw cuts shall be parallel to the original saw cut and to neat straight lines .
31 2 . Sawing equipment
32 a. Power-driven
33 b. Manufactured for the purpose of sawing pavement
34 c. In good operating condition
35 d. Shall not spall or facture concrete adjacent to the repair area
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised December 20 , 2012
2022 WATER SERVI CE LEAK
REPAIR CONTRACT
City Project No. I 04552
32 0 I 2 9 -4
CONCRET E PAVING REPA IR
Page 4 of 4
1 3. Repa ir s: In tru e a nd straight lin es to dimensions s ho w n o n the D rawings
2 4. Utility Cuts
3 a. In a true and straight lin e on both s ides of the trench
4 b. Minimum of 12 inch es outside the trench wall s
5 5 . Preven t dust and residues from sawing from e nte rin g the atmosphere or drainage
6 facilities.
7 B . Removal
8 1. Use care in removing concrete to be re paired to prevent s palling or fracturing
9 concrete a djacent to the rep air a rea.
10 C . B ase: as specified in Drawings
11 D . Concrete Paving
12 1. Concrete place ment: in accordance with Section 32 13 13.
13 2. R einforce concrete replacement: as specified in Drawings
14 3.5 REPAIR/RESTORATION [NOT USED]
15 3.6 RE-INSTALLATION [NOT USED]
16 3.7 FIELD QUALITY CONTROL [NOT USED]
17 3.8 SYSTEM STARTUP [NOT USED]
18 3.9 ADJUSTING [NOT USED]
19 3.10 CLEANING [NOT USED]
20 3.11 CLOSEOUT ACTIVITIES [NOT USED]
21 3.12 PROTECTION [NOT USED]
22 3.13 MAINTENANCE [NOT USED]
23 3.14 ATTACHMENTS [NOT USED]
24 END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
1.2.A -Modified Items to be include d in price bid; Added blue text for c larifi cation
25
12/20/2012 D. Johnson of repa ir width on utility trench repair
2.2.C . l -C hanged to C lass P to C lass H
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOC UMENTS
Revi sed December 20 , 20 12
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No . I 04552
SECTION 32 17 23
2 PAVEMENT MARKINGS
3 PARTl-GENERAL
4 1.1 SUMMARY
5 A .Section Includes :
6 1. Pavement Markings
32 17 23 -I
PAVEMENT MARKINGS
Page I of 11
7 a. Thermoplastic, hot-applied, spray (HAS) pavement markings
8 b . Thermoplastic , hot-applied, extruded (HAE ) pavement markings
9 c. Preformed polymer tape
10 d . Preformed heat-activated thermoplastic tape
I l e . Preformed Contrast Markings
12 2. Rai sed markers
13 3 . Work zone markings
14 4. Removal of pavement markings and markers
15 B.Devi ation s from thi s City of Fort Worth Standard Specification
16 1. Pavement Markings -All pavement markings removal, repair and /or
replacement s hall be subsidiary to the appropriate pavement repair bid item
in these contract specification s.
17 C .Related Specification Sections include, but are not necessarily limited to:
I 8 1. Division 0 -Bidding Requirements, Contract Forms and Conditions of the Contract
19 2 . Division 1 -General Requirements
20 1.2 PRICE AND PAYMENT PROCEDURES
21 A.Meas urement and Payment
22 1. Pavement Markings
23 a. Measurement
24 1) Measurement for this Item shall be per linear foot of material placed.
25 b. Paym ent
26 1) The work performed and material s furnished in accordance w ith this Item
27 and measured as provided under "Measurement" shall be paid for at the unit
28 price bid per linear foot of "Pvmt Marking" installed for:
29 a) Various Widths
30 b) Variou s Type s
31 c) Various Materials
32 d) Various Colors
33 c. Th e price bid shall include:
34 1) Installation of Pavement Marking
35 2) Glass beads , when required
36 3) Surface preparation
37 4) Clean-up
38 5) Testing (when required)
39 2. Legends
40 a. Measurement
41 1) Measurement for this Item shall be per each Legend installed .
C ITY OF FORT WORTH
ST AND ARD C O NS TRUC TI ON SPEC IFI CATION DO CUMENTS
Rev ise d Jun e I 0, 2022
2022 WA TER SERVI CE LEAK
RE PA IR CO NTRACT
C ity P roject No . I 04552
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
b. Payment
32 17 23 -2
PAV EME NT MARKINGS
Page 2 of 11
1) The work performed and materials furnished in accordance with this Item
shall be paid for at the unit price bid per each "Legend" installed for:
a) Various type s
b) Various application s
c . The price bid shall include:
1) Installation of Pavement Marking
2) Glass beads, when required
3) Surface preparation
4) Clean-up
5) Testing
3. Preformed Thermoplastic -Contrast Markings
a. Measurement
I) Measurement for this Item shall be per linear foot of material placed or per
each for legend items
b. Payment
I) The work performed and materials furnished in accordance with this Item
shall be paid for at the unit price bid per linear foot or per each for legends for
"Preformed Thermop lastic -Contract Markings" installed for:
a) Various Widths
b) Various Types
c) Various Applications
c. The price bid shall include:
I) Installation of Contrast Markings , including solid black and solid white or
yellow material as preformed
2) Railroad Legend shall include X and RR legend markings and three 24"
stop bars
3) Surface preparation
4) Clean-up
5) Testing
4. Raised Markers
a. Measurement
I) Measurement for this Item shall be per each Raised Marker installed.
b. Payment
I) The work performed and materials furnished in accordance with this Item
shall be paid for at the unjt price bid per each "Raised Marker" installed for:
a) Various types
c. The price bid shall include:
I) Installation of Raised Markers
2) Surface preparation
3) Clean-up
4) Testing
5. Work Zone Tab Markers
a. Measurement
1) Measurement for this Item shall be per each Tab Marker installed.
b. Payment
I) The work performed and materials furnished in accordance with this Item
shall be paid for at the unit price bid per each "Tab Marker" installed for:
a) Various types
CITY OF FORT WORTH
ST ANDA RD CO NSTRU CTIO N SP ECIFI CATIO N DO CUMEN TS
Revi sed June I 0, 2022
2022 WATER SERVICE LEAK
REPAIR CO NTRA CT
City Project No . I 045 52
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
c. The price bid shall include:
1) Installation of Tab Work Zone Markers
6. Fire Lane Markings
a. Measurement
32 17 23 - 3
PAVEMENT MARKIN GS
Page 3 of 11
1) Measurement for this Item shall be per the linear foot.
b. Payment
1) The work performed and materials furnished in accordance with this Item
and measured as provided under "Measurement" shall be paid for at the unit
price bid per linear foot of "Fire Lane Marking" installed.
c. The price bid shall include:
1) Surface preparation
2) Clean-up
3) Testing
7. Pavement Marking Removal
a. Measurement
I) Measure for this Item shall be per linear foot.
b. Payment
I) The work performed and materials furnished in accordance with this Item
and measured as provided under "Measurement" shall be paid for at the unit
price bid per linear foot of "Remove Pvmt Marking" performed for:
a) Various widths
c. The price bid shall include:
I) Removal of Pavement Markings
2) Clean-up
8. Raised Marker Removal
a. Measurement
I) Measurement for this Item shall be per each Pavement Marker removed.
b. Payment
I) The work performed and materials furnished in accordance with this Item
shall be paid for at the unit price bid per each "Remove Raised Marker"
performed.
c. The price bid shall include:
I) Removal of each Marker
2) Disposal of removed materials
3) Clean-up
9. Legend Removal
a. Measurement
I) Measure for this Item shall be per each Legend removed.
b . Payment
I) The work performed and materials furnished in accordance with this Item
and measured as provided under "Measurement" shall be paid for at the unit
price bid per linear foot of "Remove Legend" performed for:
a) Various types
b) Various applications
c. The price bid shall include:
I) Removal of Pavement Markings
2) Clean-up
CITY OF FORT WORTH
STANDARD CONSTRUCTION SP EC IFI CATION DO CUMENTS
Revi sed June I 0, 2022
20 22 WAT ER SERVICE LEAK
REPAIR CONTRACT
Ci ty Proje ct No . I 04552
1.3 REFERENCES
2 A.Reference Standards
32 17 23 -4
PAVEMENT MARKJNGS
Page4 of 11
3 1. Reference standards cited in this Specification refer to the current reference
4 standard published at the time of the latest revision date lo gged at th e end of this
5 Spec ification , unless a date is specifically cited .
6 2. Texas Manual on Uniform Traffic Contro l Devices (MUTCD), 2011 Edition
7 a . Part 3 , Markings
8 3. American Association of State Highway and Transportation Officials (AASHTO)
9 a. Standard Spec ifi cation for Glass B eads Used in Pavement Markings, M 247-09
1 O 4. Federal Highway Adm ini stration (FHW A)
11 a. 23 CFR Part 655, FHW A Docket No. FHW A-2009-0 139
12 5. Texas Department of Transportation (TxDOT)
13 a. DMS-4200, Pavement Markers (Reflectorized)
14 b. DMS-4300 , Traffic Buttons
15 c. DMS-8220, Hot App li ed Thermoplastic
16 d. DMS-8 240, Permanent Prefabricated Pavement Markings
17 e. DMS-8241 , Removable Prefabricated Pavement Markings
18 f . DMS-8242, Temporary Flexible-Reflective Road Marker Tabs
19 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED]
20 1.5 SUBMITT ALS
21 A .Submittals shall be in accordance with Section 01 33 00.
22 B.All submittals shall be a ppro ved by the City prior to delivery and/or fabrication for
23 specials.
24 1.6 ACTION SUBMITTALS/INFORMA TIONAL SUBMITTALS [NOT USED]
25 1.7 CLOSEOUT SUBMITTALS [NOT USED]
26 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
27 1.9 QUALITY ASSURANCE [NOT USED]
28 1.10 DELIVERY, STORAGE, AND HANDLING
29 A.Storage and Handling Requirements
30 1. T he Contractor shall secure and maintain a location to store the material in
31 acco rd ance w ith Section O 1 50 00 .
32 1.11 FIELD [SITE] CONDITIONS [NOT USED]
33 1.12 WARRANTY [NOT USED]
34 PART 2-PRODUCTS
35 2.1 OWNER-SUPPLIED PRODUCTS
36 A.New Products
37 1. R efer to Drawings to determine if there are owner-supp li ed products for the Project.
CITY OF FORT WORTH
ST AND ARD CONSTRUC TIO N SP EC IFI CATIO N DOCUMENTS
Revi sed Jun e 10, 202 2
202 2 WATER SERV ICE LEAK
REPAIR CONTRA CT
City Project No. 104552
2.2 MATERIALS
2 A.Manufacturers
32 17 23 -5
PAVEMENT MARKJNGS
Page 5 of 11
3 1. Only the manufacturers as listed in the City's Standard Products List will be
4 considered as shown in Section O 1 60 00.
5 a . The manufacturer must comply with this Specification and related Sections .
6 2. Any product that is not listed on the Standard Products List is considered a
7 substitution and shall be submitted in accordance with Section 01 25 00.
8 B.Materials
9 1. Pavement Markings
10 a . Thermoplastic, hot applied, spray
11 1) Refer to Drawings and City Standard Detail Drawings for width of
12 longitudinal lines.
13 2) Product shall be especially compounded for traffic markings.
14 3) When placed on the roadway, the markings shall not be slippery when wet ,
15 lift from pavement under normal weather conditions nor exhibit a tacky
16 exposed surface .
17 4) Cold ductility of the material shall permit normal road surface expansion
18 and contraction without chipping or cracking.
19 5) The markings shall retain their original color, dimensions and placement
20 under normal traffic conditions at road surface temperatures of 158 degrees
21 Fahrenheit and below.
22 6) Markings shall have uniform cross-section, clean edges, square ends and no
23 evidence of tracking.
24 7) The density and quality of the material shall be uniform throughout the
25 markings.
26 8) The thickness shall be uniform throughout the length and width of the
27 markings.
28 9) The markings shall be 95 percent free of holes and voids, and free of
29 blisters for a minimum of 60 days after application.
30 10) The material shall not deteriorate by contact with sodium chloride, calcium
31 chloride or other chemicals used to prevent roadway ice or because of the oil
32 content of pavement markings or from oil droppings or other effects of traffic.
33 11) The material shall not prohibit adhesion of other thermoplastic markings if,
34 at some future time, new markings are placed over existing material.
35 a) New material shall bond itself to the old line in such a manner that no
36 splitting or separation takes place.
37 12) The markings placed on the roadway shall be completely retroreflective
38 both internally and externally with traffic beads and shall exhibit uniform
39 retro-directive reflectance.
40 13) Traffic beads
41 a) Manufactured from glass
42 b) Spherical in shape
43 c) Essentially free of sharp angular particles
44 d) Essentially free of particles showing cloudiness, surface scoring or
45 surface scratching
46 e) Water white in color
47 f) Applied at a uniform rate
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFI C ATION DOC UMENTS
R evi sed June I 0 , 2022
2022 WATER S E RVICE LEAK
REPAIR C ON TRACT
C ity Project N o . I 04552
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
32 17 23 -6
PAV EMENT MA RKIN GS
Page 6 o f 11
g) Meet or exceed Specifications shown in AASHTO Standard
Specification for Glass B eads Used in Pavement Markings , AASHTO
Des ignation: M 247-09.
b. Thermoplastic , hot applied , extruded
1) Product shall be especially compounded for traffic markings
2) When placed on the roadway, the markings shall not be slippery when wet,
lift from pavement under normal weather conditions nor exhibit a tacky
exposed surface .
3) Cold ductility of the material shall permit normal road surface expansion
and contraction without chipping or cracking.
4) The markings shall retain their original color, dimensions and placement
under normal traffic conditions at road surface temperatures of 158 degrees
Fahrenheit and below.
5) Markings shall have uniform cross-section, clean edges , square ends and no
evidence of tracking.
6) The density and quality of the material shall be uniform throughout the
markings.
7) The thickness shall be uniform throughout the length and width of the
markings.
8) The markings shall be 95 percent free of holes and voids , and free of
blisters for a minimum of 60 days after application.
9) The minimum thickness of the marking, as measured above the plane
formed by the pavement surface, shall not be less than 1/8 inch in the center
of the marking and 3/32 inch at a distance of ½ inch from the edge.
10) Maximum thickness shall be 3/16 inch .
11) The material shall not deteriorate by contact with sodium chloride , calcium
chloride or other chemicals used to prevent roadway ice or because of the oil
content of pavement markings or from oil droppings or other effects of traffic.
12) The material shall not prohibit adhesion of other thermoplastic markings if,
at some future time, new markings are placed over existing material. New
material shall bond itself to the old line in such a manner that no splitting or
separation takes place.
13) The markings placed on the roadway shall be completely retroreflective
both internally and externally with traffic beads and shall exhibit uniform
retro-directive reflectance.
14) Traffic beads
a) Manufactured from glass
b) Spherical in shape
c) Essentially free of sharp angular particles
d) Essentially free of particles showing cloudiness, surface scoring or
surface scratching
e) Water white in color
f) Applied at a uniform rate
g) Meet or exceed Specifications shown in AASHTO Standard
Specification for Glass Beads Used in Pavement Markings , AASHTO
Designation: M 247-09 .
c. Preformed Polymer Tape
1) Material shall meet or exceed the Specifications for SW ARCO Director 35 ,
3M High Performance Tape Series 3801 ES , or approved equal.
d. Preformed Heat-Activated Thermoplastic Tape
C ITY OF FORT WORTH
STANDARD CO NSTRUC TION S PEC IFIC AT ION DOCUME TS
Revised June I 0 , 2022
202 2 WATER SERVICE LEAK
REPAIR CONTRACT
C ity Project No . I 04 55 2
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
32 17 23 -7
PAVEMENT MARKINGS
Page 7 of 11
1) Material shall meet or exceed the Specifications for HOT Tape Brand 0 .125
mil preformed thermoplastic or approved equal.
2. Rais ed Markers
a . Markers shall meet the requirements of the Texas Manual on Unifonn Traffic
Control D ev ice s.
b. Non-reflective markers shall be Type Y (yellow body) and Type W (white body)
round ceramic markers and shall meet or exceed the TxDOT Specification
DMS-4300 .
c. The reflective markers shall be plastic , meet or exceed the TxDOT Specification
DMS-4200 for high-volume retroreflective raised markers and be avai lab le in
the follow in g type s:
1) Type 1-C, white body, 1 face reflects white
2) Type II-A-A, yellow body, 2 faces reflect amber
3) Type II-C-R, white body , 1 face reflects white, the oth er red
3 . Work Zone Markings
a. Tabs
1) Temporary flexible-reflective roadway marker tab s shall meet requirements
ofTxDOT DMS-8242 , "Temporary F lexibl e-Reflective Road Marker Tabs."
2) Removable markings shall not be used to s imul ate edge lines .
3) No segment of roadway open to traffic shall remain without permanent
pavement markings for a period greater than 14 calendar day s.
b. Raised Markers
1) All raised pavement markers shall meet the requirements ofDMS-4200.
c. Striping
1) Work Zone striping shall meet or exceed the TxDOT Specification DMS-
8200.
28 2.3 ACCESSORIES [NOT USED]
29 2.4 SOURCE QUALITY CONTROL
30 A.Performance
31 1. Minimum maintained retrorefl ec tivity levels for longitudinal markings shall meet
32 the requirements detailed in the table below for a minimum of 30 calendar day s.
Posted Speed (mph)
::;30 35-50 :::: 55
2-lane road s with centerline n/a 100 250 markings only (1)
All other roads (2) n/a 50 100
33 (1) Measured at standard 30-m geometry m units ofmcd/m2/lux.
34 (2) Exce ptions:
35 A . When rai se d re fl ecti ve p avement markings (RRPMs) sup pl eme nt or s ubstitute for a
36 long itudina l line, minimum pavement marking retroreflectivity leve ls are not a pplica bl e as
37 long as the RRPMs are maintained so th at at least 3 are visi bl e from any position along that
38 line during nighttime conditions.
39 B. When continuous roadway li ghting assures that the markings are v is ible, minimum
40 pave ment marking retrore fl ectiv ity leve ls are not applicable .
CITY OF FORT WORTH
ST AND ARD CONSTRUCTION SP ECIFICATION DOC UMENTS
Revi sed June I 0, 2022
2022 WATER SERV ICE LEAK
REPAIR CONTRACT
City Project No . I 04552
PART 3 -EXECUTION
2 3.1 EXAMINATION [NOT USED]
3 3.2 PREPARATION
4 A .Pavement Conditions
32 17 23 -8
PAVEMENT MARKINGS
Page 8 of 11
5 1. Roadway surfaces shall be free of dirt, grease, loose and/or flaking existing
6 markings and other forms of contamination.
7 2. New Portland cement concrete surfaces shall be cleaned sufficiently to remove the
8 curing membrane.
9 3. Pavement to which material is to be applied shall be completely dry.
10 4. Pavement shall be considered dry, if, on a sunny day after observation for 15
11 minutes, no condensation develops on the underside of a 1 square foot piece of
12 clear plastic that has been placed on the pavement and weighted on the edges .
13 5. Equipment and methods used for surface preparation shall not damage the
14 pavement or present a hazard to motorists or pedestrians.
15 3.3 INSTALLATION
16 A.General
17 1. The materials shal 1 be applied according to the manufacturer's recommendations.
18 2. Markings and markers shall be applied within temperature limits recommended by
19 the material manufacturer, and shall be appli ed on clean, dry pavement having a
20 surface temperature above 50 degrees Fahrenheit.
21 3 . Markings that are not properly applied due to faulty app li cation methods or being
22 placed in the wrong position or a lignment shall be removed and replaced by the
23 Contractor at the Contractor's expense. If the mistake is such that it would be
24 confusing or hazardous to motorists, it shall be remedied the same day of
25 notification. Notification will be made by phone and confirmed by fax. Other
26 mistakes shall be remedied within 5 days of written notification.
27 4 . When markings are applied on roadways open to traffic , care will be taken to
28 ensure that proper safety precautions are followed, including the use of signs,
29 cones, barricades, flaggers , etc.
30 5. Fresh ly applied markings shall be protected from traffic damage and disfigurem ent.
31 6. Temperature of the material must be equal to the temperature of the road surface
32 before allowing traffic to travel on it.
33 B.Pavement Markings
34 1. Thermoplastic, hot applied, spray
35 a. This method shal l be used to install and replace long lines -centerlines, lane
36 lin es, edge lin es, tum lanes, and dots.
37 b. Markings shall be applied at a 110-mil thickness .
38 c. Markings shall be app lied at a 90-mil thickness when placed over existing
39 markings.
40 d. A sealer shall be used if concrete or asphalt is older than three (3) years.
41 e. Typical setting time shall be between 4 minutes and 10 minutes depending upon
42 the roadway surface temperature and the humidity factor.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised June I 0 , 2022
2022 WATER SERVJCE LEAK
REPAJR CONTRACT
C ity Project No . I 04552
32 17 23 -9
PAVE MENT MARKINGS
Page 9 of 11
f. Retroreflective raised markers shall be used to supplement the centerlines, lane
2 lines, and turn lanes. Refer to City Standard Detail Drawings for placement.
3 g. Minimum retroreflectivity of markings shall meet or exceed values s hown in
4 subparagraph 2.4 .A. I of this Specification.
5 2. Thermoplastic, hot applied, extruded
6 a. This method shall be used to install and rep lace crosswalks and s top-lines.
7 b . Markings shall be applied at a 125-mil thickness.
8 c. Minimum retroreflectivity of markings shall meet or exceed values shown in
9 this Specification .
10 3. Preformed Polymer Tape
11 a. This method shall be used to install and replace crosswalks, stop-lines, and
12 le gends.
13 b. The appli ed marking shall adhere to the pavement surface with no slippage or
14 lifting and have square ends, straight lines and clean edges.
15 c . Minimum retroreflectivity of markings shall meet or exceed values shown in
16 this Specification .
17 4. Preformed Heat-Activated Thermoplastic Tape
18 a . This method shall be used to in stall and replace crosswalks, stop-lin es, and
19 legends.
20 b. The applied marking shall adhere to the pavement surface with no slippage or
21 lifting and have square ends , straight lines and clean edges.
22 c. Minimum retroreflectivity of markings shall meet or exceed values shown in
23 this Specification.
24 C.Raised Markers
25 1. All permanent raised pavement markers on Portland Cement roadways shal I be
26 installed with epoxy adhesive. Bituminous adhesive is not acceptable .
27 2 . All permanent raised pavement markers on new asphalt roadways may be installed
28 with epoxy or bituminous adhesive .
29 3. A chalk line , chain or equivalent shall be used during layout to ensure that
30 individual markers a re properly aligned. A ll markers shall be placed uniforml y
3 1 along the line to achieve a smooth continuous appearance .
32 D.Work Zone Markings
33 1. Work shall be performed with as little disruption to traffic as possible.
34 2. Install longitudinal markings on pavement surfaces before opening to traffic.
35 3 . Maintain lane alignment traffic control devices and operations until markings are
36 installed.
37 4. Install markings in proper alignment in accordance with the Texas MUTCD and as
38 shown on the Drawings.
39 5. Place standard longitudinal line s no sooner than 3 calendar days after the placement
40 of a surface treatment, unles s otherwise shown on the Drawings.
41 6. Place markings in proper a li gnment with the lo cation of the final pavement
42 markings.
43 7 . Do not use raised pavement markers for words, symbols, shapes, or diagonal or
44 transverse lines.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revi sed June I 0, 2022
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No. I 04552
2
3
4
5
6
7
32 17 23 -10
PAVEMEN T MARKIN GS
Page 10 of 11
8. All markings shall be visible from a distance of300 feet in daylight conditions and
from a distance ofat least 160 feet in nighttime conditions, illuminated by low-
beam automobile headlig ht.
9 . The daytime and nighttime reflected color of the markings must be distinctly white
or yellow .
10. The markings must exhibit uniform retroreflective characteristics.
11 . Epoxy adhesives shall not be used to work zone markings.
8 3.4 REMOVALS
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
1. Pavement Marking and Marker Removal
a. The industry's best practice shall be used to remove existing pavement markings
and markers.
b. If the roadway is being damaged during the marker removal, Work shall be
halted until consultation with the City .
c. Removals shall be done in such a matter that co lor and texture contrast of the
pavement surface will be held to a minimum.
d . Repair damage to asphaltic surfaces, such as spalling, shelling, etc., greater than
¼ inch in depth resulting from the removal of pavement markings and markers.
Driveway patch asphalt emulsion may be broom applied to reseal damage to
asphaltic surfaces .
e. Dispose of markers in accordance with federal, state, and local regulations.
f. Use any of the following methods unless otherwise shown on the Drawings.
1) Surface Treatment Method
a) Apply surface treatment at rates shown on the Drawings or as directed.
Place a surface treatment a minimum of2 feet wide to cover the existing
marking.
b) Place a surface treatment, thin overlay , or microsurfacing a minimum
of 1 lane in width in areas where directional changes of traffic are
involved or in other areas as directed by the City.
2) Burn Method
a) Use an approved burning method.
b) For thermoplastic pavement markings or prefabricated pavement
markings, heat may be applied to remove the bulk of the marking material
prior to blast cleaning.
c) When using heat, avoid spalling pavement surfaces.
d) Sweeping or light blast cleaning may be used to remove minor residue.
3) Blasting Method
a) Use a blasting method such as water blasting, abrasive blasting, water
abrasive blasting, shot blasting, slurry blasting, water-injected abrasive
blasting, or brush blasting as approved.
b) Remove pavement markings on concrete surfaces by a blasting method
only.
4) Mechanical Method
a) Use any mechanical method except grinding.
b) F lail milling is acceptable in the removal of markings on asphalt and
concrete surfaces.
2 . If a lo cation is to be paved over, no additional compensation will be allowed for
marking or marker removal.
CITY OF FORT WORTH
STANDARD CON STRUCTION SPEC IFI CATION DOCUMENTS
Revi sed June I 0, 2022
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No. I 04552
3.5 REPAIR I RESTORATION [NOT USED]
2 3.6 RE-INSTALLATION [NOT USED]
3 3.7 FIELD QUALITY CONTROL
32 17 23 -11
PAVEMENT MARKJNGS
Pa ge 11 of 11
4 A.All lines must have clean edges, square ends, and be uniform cross-section.
5 B . The density and quality of markings shall be uniform throughout their thickne ss.
6 C.The applied markings shall have no more than 5 percent, by area, of hol es or voids and
7 shall be free of bli sters.
8 3.8 SYSTEM STARTUP [NOT USED]
9 3.9 ADJUSTING [NOT USED]
10 3.10 CLEANING
11 A .Contractor shall clean up and remove all loose material resulting from construction
12 operations.
13 3.11 CLOSEOUT ACTIVITIES [NOT USED]
14 3.12 PROTECTION [NOT USED]
15 3.13 MAINTENANCE [NOT USED]
16 3.14 ATTACHMENTS [NOT USED]
17 END OF SECTION
18
Revi sion Log
DATE NAME SUMMARY OF CHANGE
19
11 /22 /13 S. Arnold R e moved paint type marking, upd ated refe re nces, added seale r language
6/10/22 MOwen 1.1 A and 1.2 A -R evised to address preformed "contra st" pave ment markings
CITY OF FORT WORTH
ST ANDA RD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised Ju ne I 0, 2022
2022 WATER SERVI CE LEAK
REP AIR CONTRACT
City Project No . I 04552
32 9 1 19 -I
T OPSOIL PLA CEMENT AND FI N ISHING O F PARK.WAYS
Page I of3
I SECTION 32 9119
2 TOPSOIL PLACEMENT AND FINISHING OF ROADWAY RIGHT-OF-WAYS
3 PARTl-GENERAL
4 1.1 SUMMARY
5 1. Section Includes:
6 1. Furnish and place topsoil to a minimum of 3-inch depth unless otherwise shown on
7 the Drawings within the Roadway Right-of ways (Roadway ROW includes
8 medians and parkways between the curb and property line.
9 2. Deviations from this City of Fort Worth Standard Specification
1. Topsoil Placement, Water Services -The topsoil placement work covered by these
Specifications is included in the unit bid price of the appropriate water service to be
installed or repaired. All topsoil placement as specified below is considered
subsidiary to the appropriate water service bid item and specified in "Water
Services 1-inch to 2-inch" (33-12-10).
JO 3. Related Specification Sections include but are not necessarily limited to
11 1. Division O -Bidding Requirements , Contract Forms, and Conditions of the Contract
12 2. Division I -General Requirements
13 1.2 PRICE AND PAYMENT PROCEDURES
14 1. Measurement and Payment
15 1. Measurement
16 a. Measurement for this Item shall be by cubic yard of Topsoil in place.
17 2. Payment
18 a. The work performed and materials furnished in accordance with this Item and
19 measured as provided under "Measurement" will be paid for at the unit price
20 bid per cubic yard ofin place/tamped Topsoil.
21 b. All excavation required by this Item in cut sections shall be measured in
22 accordance with provisions for the various excavation items involved with the
23 provision that excavation will be measured and paid for once, regardless of the
24 manipulations involved.
25 3. The price bid shall include:
26 a. Furnishing Topsoil
27 b. Loading
28 C. Hauling
29 d. Placing
30 1.3 REFERENCES [NOT USED]
31 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED]
32 1.5 ACTION SUBMITT ALS [NOT USED)
33 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
34 1.7 CLOSEOUT SUBMITTALS [NOT USED)
35 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOTUSED]
36 1.9 QUALITY ASSURANCE [NOT USED]
CITY OF FORT WORTH
STANDARD CONSTRUC TION SP EC IFI C ATION DOCU MENTS
Revi sed March I I , 2022
2022 WATER SERVIC E LEAK
REP AIR CONTRACT
City Project No . I 04522
32 9 1 19 -2
TOPSO IL PLACE MENT AND FINI SHTN G OF PARK WAYS
37 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
38 1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
2 PART2-PRODUCTS
3 2.1 OWNER-FURNISHED !OR] OWNER-SUPPLIEDPRODUCTS [NOT USED]
4 2.2 MATERIALS
5 1. Topsoil
6 1. Use easily cultivated, fertile topsoil that:
Page 2 of3
7 a. Is free from objectionable material including subsoil, weeds, clay lumps, non-
8 soil materials, roots, stumps or stones larger than 1.0 inches
9 b. Has a high resistance to erosion
10 c. ls able to support plant growth
11 2. Secure topsoil from approved sources.
12 3. Topsoil is subject to testing by the City. Contractor shall have soil delivery tickets
13 available upon request.
14 4. pH: 5.5 to 8.5.
15 5. Liquid Limit: 50 or less
16 6. Plasticity Index: 20 or less
17 7. Gradation: maximum of 10 percent passing No. 200 sieve
18 2 . Water: Clean and free of industrial wastes and other substanc es harmful to the growth
19 of vegetation
20 2.3 ACCESSORIES [NOT USED]
21 2.4 SOURCE QUALITY CONTROL [NOT USED]
22 PART 3 -EXECUTION
23 3.1 INSTALLERS [NOT USED]
24 3.2 PREPARATION [NOT USED]
25 3.4 INSTALLATION
26 1. Finishing of Roadway Right-of-Ways
27 1. Smoothly shape right-of-ways, shoulders, slopes, and ditches.
28 2. Cut right-of-ways to finish grade prior to the placing of any improvements in or
29 adjacent to the roadway.
30 3. In the event that unsuitable material for right-of-ways is encountered, extend the
31 depth of excavation in the right-of-ways to 6 inches and backfill with minimum of 3
32 inches of topsoil.
33 4 . Make standard right-of-ways grade perpendicular to and draining to the curb line.
34 a . Minimum: 1/4 inch per foot
35 b. Maximum: 4:1
36 c. City may approve variations from these requirements in special cases.
37 5. Whenever the adjacent property is lower than the design curb grade and runoff
38 drains away from the street, the right-of-ways grade must be set level with the top
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPEC IFI CATION DOCUMENTS
Re vise d March I I, 2022
2022 WATER SERVI CE LEAK
REPAIR CONTRA CT
City Proj ect No . I 04 522
32 91 I 9 -3
TOPSOIL PLACEMENT AND FINISHING OF PARKWAYS
Page 3 of3
39 of th e c u rb .
1 6. T he d es ign grade fro m th e ri ght -of-ways ext end s to the back of th e walk line .
2 7. F rom th at po int (behind the walk), th e grade m ay s lo pe up or down at m aximum
3 s lop e of 4:1.
4 2 . Pl acin g of T opso il
5 1. Spread the top so i I t o a uni fo rm lo ose cover at the thi ckness spec ifi ed .
6 2. Pl ac e a nd sha p e the to pso il as directed.
7 a . H and tamp or roll to pso il s ur fa c e (with han d ta mp er or lan dscaping ro ll er or
8 oth e r acce pted m ethod) a nd fini s h a minimum of 5 feet from a ll fl atwork .
9 b . E ns ure top soi l is free fro m obj ecti on a bl e materi a l including su bs oil , weeds,
10 cl ay lump s, no n-soi l m ate ri a ls, roots, stump s or sto nes large r th an 1.0 in ches
11 c . No addi tio n a l to psoil should b e a dded w ithin the criti cal ro ot zo ne of trees .
12 Tam p t he t o pso il w ith a li g ht roll e r o r othe r s ui tabl e equipm ent.
13 3.5 REP AIR/RESTORATION] [NOT USED]
14 3.6 RE-INSTALLATION [NOT USED]
15 3.7 FIELD QUALITY CONTROL [NOT USED]
16 3.8 SY STEM STARTUP [NOT USED]
17 3.9 ADJUSTING [NOT US ED]
18 3.10 CLEANING [NOT USED]
19 3.11 CLOSEOUT ACTIVITIES [NOT USED]
20 3.12 PROTECTION [NOT USED]
2 1 3.13 MAINTENANCE [NOT USED]
22 3.14 ATTACHMENTS [NOT USED]
23 END OF SECTION
24
Revi sion Log
DATE NAME SUMMARY OF CHANGE
25
3/11 /2022 MOwen Revised ti tl e of specificati on and provided clarificat ions in Sections I . I Summary,
2 .2 Materials, 3.4 Installation
CITY OF FORT WORTH
STANDARD CONSTRUCT ION SPECIFICATION DOCUMENTS
Re vised March I I , 2022
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No . I 04522
1
2
3
4 PARTl-GENERAL
5 1.1 SUMMARY
6 A. Section Includes:
SECTION 32 92 13
SODDING
32 92 13 -1
SODDING
Page 1 of 7
7 1. Furnishing and installing grass sod as shown on Drawings , or as directed .
8 B. Deviations from this City of Fort Worth Standard Specification
1. Hydro-mulching, Seeding and Sodding -The hydro-mulching, seeding and / or
sod placement work covered by these Specifications is included in the unit bid price
of the appropriate water service to be installed or repaired. All hydro-mulching,
seeding and /or sod placement as specified below is considered subsidiary to the
appropriate water service bid item and specified in "Water Services 1-inch to 2-
inch" (33-12-10).
9 C. Related Specification Sections include, but are not necessarily limited to:
10 1. Division O -Bidding Requirements, Contract Forms , and Conditions of the Contract
11 2. Division 1 -General Requirements
12 3. Section 31 10 00 -Site Clearing
13 4. Section 32 91 19 -Topsoil Placement and Finishing of Parkways
14 5. Section 32 84 23 -Irrigation
15 1.2 PRICE AND PAYMENT PROCEDURES
16 A. Measurement and Payment
17 1. Sod Placement
18 a. Measurement
19 1) Measurement for this Item shall be by the square yard of Sod complete in
20 place for uniform vegetative coverage.
21 b . Payment
22 1) The work performed and materials furnished in accordance with this Item
23 and measured as provided under "Measurement" will be paid for at the unit
24 price bid per square yard of Sod placed.
25 c. The price bid shall include:
26 1) Surface preparation, scarifying subgrade, cleaning, and fine grading as
27 described in section 3.3 Preparation
28 2) Furnishing and placing all sod (until established complete in place with no
29 gaps or overlaps)
30 3) Rolling and tamping
31 4) Watering (until established)
32 5) Fertilizer, if required by City to be determined by soil test
33 6) Disposal of surplus materials off site or as directed by City
34 7) Weed removal (until established)
35 8) Mowing of two cycles, beginning at thirty (30) days from installation or
36 when blade height is 4 " or greater, whichever comes first
37 9) Mowing cycles shall be spaced a minimum often (10) days apart (until
38 established)
CITY OF FORT WORTH
STANDARD CONSTRUC TION SP EC IFI CATIO N DO CUME NTS
Revi sed May 13, 2021
2022 WATER SERVI CE LEAK
REPAIR CONTRA CT
City Proj ect No 10455 2
32 92 13 -2
SODDING
Page 2 of7
39 d. Exceptions to c. include the following for areas to be turned over to adjacent
40 properties for maintenance:
l 1) Sod shall be watered until turned over to adjacent property owner for
2 maintenance
3 2) Fertilization will not be required
4 3) Mowing not required for projects in areas where maintenance will be
5 immediately turned over to adjacent property owners
6 2. Mowing
7 a. Measurement
8 1) Measurement for this Item shall be per each for the project, beyond the two
9 (2) mow cycles included in sodding price, as approved and directed by the
10 City
11 b. Payment
12 1) The work performed and material s furnished in accordance with this Item
13 and measured as provided under "Measurement" will be paid for at the unit
14 price bid per each.
15 1.3 REFERENCES [NOT USED]
16 1.4 ADMINISTRATIVEREQUIREMENTS [NOTUSED]
17 1.5 ACTION SUBMITTALS [NOT USED]
18 1.6 INFORMATIONAL SUBMITTALS
19 A. Certifications, Samples and Documentation
20 1. Certificates and/or labels and samples of sod, fertilizer, compost, soil amendments
21 and/or other materials, including a certificate from the vendor indicating sod is free
22 from weeds.
23 2. Delivery receipts and copies of invoices for materials used for this work shall be
24 subject to verification by the City
25 B. Exceptions
26 1. Certifications, samples and associated documentation will not be required for sod to
27 be turned over to adjacent property owner for maintenance
28 1.7 CLOSEOUT SUBMITTALS [NOT USED]
29 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
30 1.9 QUALITY ASSURANCE
31 A. Developer/contractor who plants material is responsible for the supervision of crew, the
32 site, and the maintenance of the material until the project is accepted by the City
33 1.10 DELIVERY, STORAGE, AND HANDLING
34 A. Sod
35 1. Protect from exposure to wind, sun and freezing.
36 2. Keep stacked sod moist, consistently throughout stack.
37 3. Sod upon delivery may be inspected by City
38 4. Harvesting and planting operations shall be coordinated with not more than seventy-
39 two (72) hours elapsing between harvesting and placement, rolling, tamping, and
40 watering of sod.
41 B. Fertilizer, as determined by soil testing report provided to Contractor, if specifically
C ITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIF ICA TIO DOCUMENTS
Revised May 13 , 2021
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No. I 04552
42 required by City for the project.
32 92 13 -3
SODDING
Page 3 of7
1. Provide unopened bags labeled with the manufacturer's guaranteed fertilizer
2 analysis.
3 2. Conform to Texas fertilizer law , Texas Agriculture Code Chapter 63.
4 3. Provide to City application rate for which fertilizer will be applied.
5 1.11 FIELD [SITE] CONDITIONS
6 A. Grading of site and installation of topsoil must be approved by City prior to application
7 of sod.
8 1.12 WARRANTY
9 A. Warranty Period: Until project acceptance or through required maintenance period ,
10 whjchever is longer duration of time.
11 B. Warrant sod against defects in product, installation and workmanship.
12 1. Exceptions include
13 a. When maintenance is transferred to the adjacent property owner during the
14 project or after project acceptance
15 b . Vandalism caused by persons other than contractor or subcontractors of thi s
16 project
17 c. Improper watering by persons other than contractor or subcontractors of this
18 project
19 d. Damage caused by vehicles or equipment other than contractor or
20 subcontractors of this project.
21 e. Sod that goes dormant after job acceptance
22 PART2 -PRODUCTS
23 2.1 OWNER-FURNISHED PRODUCTS [NOT USED]
24 2.2 MATERIALS AND EQUIPMENT
25 A. Materials
26 1. Sod
27 a. Sod Varieties (match exjsting ifapplicable)
28 1) "Cynodon dactylon TIF419" or "TIFWA Y " or "TIFTUF" (Bermudagrass
29 hybrid)
30 2) or an approved St. Augustine grass
31 3) or an approved Zoysia grass
32 b . Sod must contain stolons , leaf blades, rhizomes and roots as appropriate to
33 species.
34 c. Sod shall be alive , healthy and free of insects , disease , stones, undesirable
35 foreign materials and weeds and grasses deleterious to its growth or which might
36 affect its subsistence or hardiness when transplanted.
37 1) Johnsongrass not allowed
38 2) Nutgrass not allowed
39 3) Millet not allowed
40 d. Sod shall have been produced on growing bed s of clay or clay loam topsoil.
41 e. Sod must not be harvested or planted when its moisture condition is so
42 excessively wet or dry that its survival will be affected.
43 2. Mirumum sod thickness: 1/2-inch minimum
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised May 13 , 202 1
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No . I 04552
a. Maximum g ras s heig ht: 2-inches
b. Dimensions
1) Machine cut to uniform soil thickness .
32 92 13 -4
SODD ING
Page 4 of7
2
3
4
5
6
7
8
9
2) Sod is to be cut in strips 16-inches wide a nd 24-inches long or approved
equal.
3) Sod shall be of equal width and of a s iz e that permits the sod to be lifted,
ha ndled and rolled without breaking.
c . Broken or torn sod or sod with uneven ends shall be rejected.
10
I 1
12
13
d . Temporary Erosion Control or Over Seed of dormant s od-consist of the sowing
of cool season plant seed. Seed must be included between November 1 through
March 1 or a s directed by the City.
Common Name Botanical Name
Elbon Rye S ecale cer eale
Lbs .I Acre
broadcast
method
100-120
Lbs .I Acre
drilled seed
method
80-100
14
15
16
17
18
19
3. Fertilizer to be installed only as directed by City or as indicated in construction
documents
a. Determined by soil testin g report
b . Acceptable condition for distribution per manufacturer's instructions
c. Applied uniformly over sod area. Do not fertili z e in s ide the drip line of trees, or
Tree Protection Area.
4 . Topsoil: See Section 32 91 19. 20
21
22
5. Water: clean and free of industrial wastes or other s ubstances harmful to the
germination of seed or to the growth of the veg etation .
23 2.3 ACCESSORIES
24 A. SOD PINS
25 1. Metal
26 2 . Wood pegs
27 2.4 SOURCE QUALITY CONTROL [NOT USED]
28 PART 3 -EXECUTION
29 3.1 INST ALLERS [NOT USED]
30 3.2 EXAMINATION
31 A. City may examine site grading to ensure it conforms to approved drawings, prior to
32 installing sod.
33 1. City will notify Contractor if grading is to be inspected prior to sod installation .
34 2. If required for specific project, Contractor must coordinate inspection seventy-two
35 (72) hours prior to cutting of sod and delivery
36 B. Sod may be inspected by City upon delivery.
37 3.3 PREPARATION
38 A. Surface Preparation: clear surface of all material including the following and dispose of
39 off-site or as directed by City :
CITY OF FORT WORT H
ST ANDARD CONST RUC TlON SPEC lFI CATION DOCUME TS
Revised May 13 , 2021
2022 WATER SERVI CE LEAK
RE PAIR CONTRA CT
C ity Proj ec t No. I 04552
1. Stumps, stones, and other objects larger than I -inch .
2 2. Roots, brush , wire, stakes, etc .
3 3 . Any objects that may interfere with so dding or maintenance.
4 B . Scarify Subgrade
5 1. Scarify s ubgrade to a depth of 2-inches before depo s iting the required topsoi l.
32 92 13 -5
SODDING
Page 5 of7
6 2. Compacted or heavily ve getated areas may be till ed 3-inches deep with City approval
7 a. For tilled areas, u se a heavy -duty di sc or a chisel-type breaking plow, chisels
8 set not more than 10-inches apart.
9 b . Initial tillage shall be done in a crossing pattern for double coverage, then
10 followed by a disc harrow. Depth of ti ll age may be up to 3 -inches .
11 c. Areas sloped greater than 3: 1: run a tractor para! lei to s lope to provide less
12 seed/water run-off
13 3. Areas near trees: Do not till within dripline of tree. Do not disturb the Tree Protect ion
14 Area, or canopy dripline.
15 C. C leaning
16 1. Soil shal I be further prepared by the removal of debris , building materi a ls, rubbi sh ,
17 and rock I-inch and greater, and weeds.
18 2. Remove and dispose of debris off-site.
19 D . Fine Grading:
20 1. After scarifying or tilling and cleaning, all areas to be so dded shall have 3-inches of
21 tops oil placed, be leveled , fine graded by use of weighted spike and harrow, or float
22 drag, or hand grading to e liminate ruts, depression s, humps, and objectionable so il
23 clods . This s h a ll be the final soil preparation step to be completed prior to
24 in s pection b efo re sodding.
25 2. Areas near trees: Do not disturb the Tree Protection Area, or canopy dripline
26 3.4 INSTALLATION
27 A. General
28 1. Do not lay sod when ground is frozen .
29 2. Over-seeding with E lbon Rye shall be included from November 1 until March 1.
30 Refer to Section 32 92 14 "Seeding" for seed rates.
31 B. Installation
32 1. Plant sod specified after the area has been inspected and accepted by City for
33 planting
34 2 . Scarify 2-inches of s ubgrade and place a minimum of 3-inches of topsoil per Section
35 32 91 19 on areas to receive sod.
36 3. Sod to be laid parallel to the c ontours in areas as specified. Sod to be laid
37 perpendicular to slopes g reater than or equal to 4: 1.
38 4. Use care to retain native so il on the roots of the sod during the process of excavating,
39 hauling and planting.
40 5. Keep sod material moist from the time it is dug until planted . Dry sod shall be
41 rejected .
42 6. Fill in s lumped areas due to watering to keep sod moist.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SP ECIFI CATION DOCUMENTS
Revi sed May 13 , 202 1
2022 WATER SERVI CE LEAK
REPAIR CONTRACT
Ci ty Project No . I 04552
32 92 13 -6
SODDING
Page 6 of7
7. Pl ace sod so that the entire area de s ign ated for sodd in g is covered with no gaps or
2 overlapping material
3 8 . F ill voids left in the so lid sodd in g with add ition a l sod and tamp .
4 9. Stagger joints and seams .
5 10. Roll and tamp sod so that sod is in comp lete contact w ith top so il at a uniform slop e.
6 a. Use p edestrian mechanical process (no motorized vehicles / equipm ent).
7 b . Low spots, or settlem ent greater than 1-in ch, that may cause tripping hazard
8 sha ll be leve led
9 c. F ini shed grade of so d s hall be maximum 1-in ch below adj acent edges including
10 curbs, driv es, and walkways.
11 11. Peg sod with wooden pe gs (or wire staple) driven through the sod block to the firm
12 earth in areas that may s lide due to th e h e ight or s lop e of the surface or nature of the
13 so il.
14 C. Watering and Finishing
15 1. Water so d to a minimum depth of 4-inches imm ed iate ly after pl ace d and t amped and
16 rolled .
17 2. Generally, as recommended by the vendor
18 3. Water source shall be clean and free of industrial waste or other substances harmful
19 to the ge rmination of the seed or growth of the vegetatio n.
20 4. Water until 100 percent green an d establi shed as defined in 3.13 . Dormant sod mu st
2 1 be over-seeded as dire cted in 2.2 A.2.d.
22 3.5 REPAIR/RESTORATION [NOT USED]
23 3.6 RE-INSTALLATION [NOT USED]
24 3.7 FIELD QUALITY CONTROL [NOT USED]
25 3.8 SYSTEM STARTUP [NOT USED]
26 3.9 ADJUSTING [NOT USED]
27 3.10 CLEANING [NOT USED]
28 3.11 CLOSEOUT ACTIVITIES
29 3.12 PROTECTION [NOT USED]
30 3.13 MAINTENANCE
31 A. Sodding
32 1. Water and mow sod until completion and final acceptance of the Project or as
33 directed by the City.
34 2. Trim and ma intain along edges inc ludi ng curbs, dri ves, and walk ways w ith
35 max imum I-inch surface e levation change.
36 3. Sod shall be rooted to scarified soil with continuous surface coverage with no gap s or
37 overlapping edges.
38 4. Includes protection, replanting, and maintaining grades with no settlement over 1-
39 inch, and immedi ate repair of erosion damage unt il the project receives final
40 acceptance.
41 5. Sod shall not b e considered finally accepted unti 1 the sod has starte d to peg down
42 (roots growing into the so il ) and is free from dead blocks of sod.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Re vised May 13 , 2021
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No . I 04552
B. Acceptance
2 1. Sod shall be accepted once fully estab li shed.
32 92 I 3 - 7
SODDING
Page 7 of7
3 a . Sodded area must have 100 percent ground coverage and a blade height of3-
4 in ches w ith 2 mow cycles, minimum ten (10 ) days apart, performed by the
5 Contractor prior to consideration of acceptance by the City.
6 b . Grass shall be active ly growing and free of disease and pests.
7 c . Ground surface to be smooth and free of forei gn material and rock or clods 1-
8 inch diameter a nd greater.
9 C. Replanting
10 1. Replant areas with dead blocks of sod (50 percent of individual block or greater).
l l D. Rejection
12 1. City may reject sod area based on the fo ll owing items prior to final acceptance :
13 a. Weed populations
14 b. Poor installation including but not limited to gaps and /or overlapping sod
15 c. Disease and/or pests
16 d . Insufficient or over watering
17 e . Poor or improper maintenance
18 f. Soi l settlement in excess of I-inch.
19 3.14 ATTACHMENTS [NOT USED]
20 END OF SECTION
21
22
Revision Log
DATE NAME SUMMARY OF CHANGE
Remove d information and details regarding see d, native grasses and wildfl owe rs .
These item s are addressed in new s pecifi cation 32 92 14 and P arks s pecifi cati on fo r
native grasses/wildflowers. Item s p erta ining to fertilizer throug ho ut document
upd ated to include soil testin g. Remove and replace "bl ock sod" with "sod"
M ay 13, 2021 M Owen throughou t docum ent. Updated 1.2 p ay ment measw·ement. 3.3 Preparation updated to
re fle c t cuiTe nt indu stry tree care stand ards fo r root zo ne di s turb a nce. 3 .4 In stallati on
added descripti ons to clarify acceptable installation. 3.13 Maintenance added
desc rip tio ns to clarify acceptance and rej ecti on of sodd ed areas including growth ,
mow cycle and watering . Insert ed exceptions assoc iated with sod to be turned over to
adjacen t property m:vner.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revi sed May 13 , 202 1
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No . I 04552
SECTION 33 12 10
33 12 10-I
WATER SE RVICES I-INCH TO 2-INCH
Page I of 17
WATER SERVICES I-INCH TO 2-INCH
PART 1 -GENERAL
1.1 SUMMARY
A. Section Includ es:
1. Lead-free I-inch to 2-inch water service lin es from the water main to th e ri ght-of-
way, fittings and water meter boxes complete in place, as shown on the Drawin gs,
directed by the E ng ineer, and s pecified herein for:
a. New Water Service
b. New Water Service (Bored)
c. Water Meter Service Relocate
d . Private Water Service
B. D ev iations from this City of Fort Worth Standard Specification
1. Water Services -All water services for this contract have been categorized by
service size, service length and surface restoration. The water service bid items
in the proposal are for removing existing services, including corporation at
main, and strapping the appropriate tap saddle over the remaining hole in
mains of all sizes and pipe materials up to and including 12-inch in diameter.
The measurement for the services shall be from the tap of the main to the
existing meter, unless otherwise designated by the Engineer. The payment for
each service shall be for the service size, service length and surface restoration
of the appropriate bid item. The price bid shall include all items as specified
below, as well as, reconnection of the meter/ private service, the surface
restoration of street paving, top soil and grass as necessary to replace a
complete water service. The surface restoration exceptions, which will be paid
separately at the unit price bid, are 4-inch Concrete Sidewalk (32-13-20) and 6-
inch Concrete Driveway (32-13-20). The unit price bid for water services
includes the embedment and backfill as specified "Utility Trench Excavation,
Embedment and Backfill" (33-05-10), the exception will be for "Imported
Embedment / Backfill CLSM". The "Imported Embedment / Backfill CLSM"
bid item will be paid for at the cubic yard bid price when required and
directed by the Engineer.
2. Water Service Relocation -When necessary to relocate the meter/service (i.e.
out of driveways or splitting bullhead services), the service reconnection will
be paid separately at the unit price bid per linear foot of "Private Water
Service, Relocation".
C. Products In stalled but not Furnished Under this Section
I. Water meters for various s izes
D. Related Specification Sections include , but are not neces saril y limited to:
1. Division O -Bidding Requirements, Contract Fo rm s and Conditions of the Contract
2. Di v isio n I -General Requirements
3. Section 33 04 40 -Cleaning and Acceptance Testing of Water Main s
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revi sed February 14 , 2017
2022 WATER SERV ICE LEAK
REPAIR CONTRACT
City Project No . I 04552
331 2 10 -2
W ATERS ERVl C ES I-INCH TO 2 -I NC H
Page 2 of 17
4. Section 33 05 10 -Utility Trench E xcavation, E mbedment and Backfill
5. Section 33 12 25 -Connection to Existing Water Mains
1.2 PRICE AND PAYMENT PROCEDURES
A . Measurement and Payment
1. New Water Service
a. Measurement
1) Measurement for this Item shall be per each new "Water Service" complete
in place from the tap of the main to the installation of the meter box and
associated appurtenances where the service line is installed by open cut
construction.
b. Payment
1) The work performed and materials furnished in accordance with this Item
and measured as provided under "Measurement" will be paid for at the uni t
price bid per each "Water Service" installed for:
a) Various sizes
c. The price bid shall include:
1) Furnishing and installing New Service Line as specified by the Drawings
2) Submitting product data
3) Tapping saddle
4) Corporation stop
5) Curb stop
6) Fittings
7) Service line installed by open cut
8) Connection to meter
9) Meter Box and Lid
10) Pavement removal
11) Excavation
12) Hauling
13) Disposal of excess material
14) Surface Restoration associated with Meter Box installation and connection ,
excluding grass (seeding, sodding or hydro-mulch paid separately)
15) C lean -up
16) Disinfection
17) Testing
2. New Bored Water Service
a. Measurement
1) Measurement for this Item shall be per each new Water Service complete in
place from the tap of the main to the installation of the meter box and
associated appurtenances where the service line is installed by trenchless
method.
b. Payment
1) The work performed and materials furnished in accordance with this Item
and measured as provided under "Measurement" will be paid for at the unit
price bid per each "Bored Water Service" installed for:
a) Various sizes
c. The price bid shall include :
1) Submitting product data
2) Tapping saddle
CITY O F FORT WORTH
STANDARD CO N STRUC TION SPEC IFI CATION DO CUMENT S
Rev ised Fe bru ary 14 , 20 17
2022 WATER SERVICE LEA K
REPAIR C ON TRACT
C ity Proj ect N o . 104 552
3) Corporation stop
4) Curb stop
5) Fittings
6) Service line installed by trenchless method
7) Connection to meter
8) Meter Box and Lid
9) Pavement removal
10) Excavation
11) Hauling
12) Disposal of excess material
33 12 10 -3
WATE R S ERVI CES I-INC H TO 2-INC H
Page 3 of 17
13) Surface restoration associated with Meter Box installation and connection ,
excluding grass (seeding, sodding or hydro-mulch paid separately)
14) Clean-up
15) Disinfection
16) Testing
3 . Water Meter Service Reconnect
a. Measurement
1) Measurement for this Item shall be per each Water Meter Service
Reconnect complete in place from public service line connection to private
service line connection .
b. Payment
1) The work performed in conjunction with relocation of the meter, associated
private service line, fittings and meter box 5 feet or less in any direction
from centerline of existing meter location and the materials furnished in
accordance with this ltem will be paid for at the unit price bid per each
"Water Meter Service, Reconnection" installed for:
a) Various size of services
c . The price bid shall include :
1) Private service line
2) Fittings
3) Private connection to water meter
4) Connection to existing private service line
5) Cut and crimp of existing service
6) Removal and Disposal or Salvage of existing 2-inch or smaller water meter,
as directed by City
7) Pavement removal
8) Excavation
9) Hauling
10) Disposal of excess material
11) Surface restoration for area disturbed for installation of meter box,
excluding grass (seed ing, sodding or hydro-mulch paid separately)
12) Clean-up
13) Cleaning
14) Disinfection
15) Testing
4 . Private Water Service Relocation
a. Measurement
CITY OF FORT WORTH
STANDARD CONS TRUCTIO N SP EC IFI CATIO N DO CUMENT S
Revi se d February 14 , 2017
20 22 WATER SERVI CE LEAK
REPAIR CONTRACT
City Proj ec t No . I 04552
33 12 10-4
WATER SERV ICES I-INCH TO 2-JNCH
Page 4 of 17
1) Measurement for thi s Item s hall be per linear foot of Private Service
relocation complete in place from the meter box to a connection to the
existing serv ice line on private property .
b. Pay ment
1) The work performed in conjunction with Private Service Line installation
where th e meter and meter boxe s are moved more than 5 feet in any
direction from centerline of existin g meter location and materials furnished
in accordance with the Item and measured as provided under
"Measurement" will be paid for at the unit price bid per linear foot of
"Private Water Service" performed for:
a) Various service sizes
c. The price bid shall include:
1) Obtaining appropriate permit
2) Obtaining Ri g ht of Entry
3) Submitting product data
4) Private service line
5) Fittings
6) Backflow preventer, check valve, and isolation valve relocation , if
applicable
7) Connection to existing private service line
8) Pavement removal and replacement
9) Excavation
10) Hauling
11) Disposal of excess material
12) Surface restoration , excluding grass (seeding, sodding or hydro-mulch paid
separately)
13) Clean-up
14) Cleaning
15) Disinfection
16) Testing
1.3 REFERENCES
A. Definitions
I. New Service
a. Installation of new I-inch to 2-inch Water Service Line by open cut
construction from the water main to the right-of-way , including corporation
stop, curb stop, fittings and water meter boxes complete in place, as shown on
the Drawings.
2. New Service (Bored)
a. Installation of new I-inch to 2-inch Water Service Line by trenchles s
construction method from the water ma in to the ri ght-of-way, including
corporation stop, curb stop, fitting s and water meter boxes complete in place , as
shown on the Drawings.
3. Meter Service Reconnection
a. Relocation and reconnection of the private service line from an existing meter
to be abandoned and a new meter installed that lies within 5 feet of the existing
meter.
4. Private Service Relocation
CITY OF FO RT WORTH
STANDARD CONSTRUCT ION SPECIFICATION DOCUMENTS
Revised February 14, 2017
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No. I 04552
33 12 10-5
WA TER SERVI CE S 1-fNCH TO2-fN CH
Page 5 of I 7
a. Relocation and reconnection of private service line behind the water meter
where the existing meter to be abandoned and the new meter installed is greater
than 5 feet of the existing meter. A licensed plumber is required to relocate the
private service.
5 . Lead-free
a . Lead-free pipes and plumbing fittings and fixtures shall contain less than 0.25
percent lead in accordance with the reduction of Lead in Drinking Water Act
(P.L. 111-380).
B. Reference Standards
1. Reference standards cited in this Specification refer to the current reference
standard published at the time of the latest revision date logged at the end of this
Specification, unless a date is specifically cited.
2. ASTM International (ASTM):
a . A48, Standard Specification for Gray Iron Castings.
b. A536, Standard Specification for Ductile Iron Castings.
c. B88, Standard Specification for Seamless Copper Water Tube.
d. B98, Standard Specification for Copper-Silicon Alloy Rod, Bar and Shapes.
e. C 131, Standard Specification for Resistance to Degradation of Small-Size
Coarse Aggregate by Abrasion and Impact in the Los Angeles Machine .
f. C150 , Standard Specification for Portland Cement.
g. C330 , Standard Specification for Lightweight Aggregates for Structural
Concrete.
h. C857 (RL), Standard Practice for Minimum Structural Design Loading for
Underground Precast Concrete Utility Structures
1. D883, Standard Terminology Relating to Plastics.
j. D1693, Standard Test Method for Environmental Stress-Cracking of Ethylene
Plastics
3. American Water Works Association (A WW A):
a. C700 , Cold-Water Meters -Displacement Type, Bronze Main Case.
b. C800, Underground Service Line Valves and Fittings.
4. NSF International (NSF):
a . 61, Drinking Water System Components -Health Effects.
5. Reduction of Lead in Drinking Water Act
a. Public Law 111-380 (P.L. 111-380)
6. General Services Administration (GSA):
a. RR-F-621E, Frames, Covers, Gratings, Steps, Sump and Catch Basin, Manhole
1.4 ADMINISTRATIVE REQUIREMENTS
A. Scheduling
1. Provide advance notice for service interruptions and meet requirements of Division
0 and Division 1.
1.5 SUBMITTALS
A. Submittals shall be in accordance with Section 01 33 00 .
B. All submittals shall be approved by the City prior to delivery.
CITY OF FORT WORTH
STANDARD CONSTRUC TION SPEC IFI CATION DOCUMENTS
Re vised Febru ary 14 , 20 17
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No. I 04552
33 12 10-6
WA TE R SE RVI CES 1-fN CH TO 2-fN CH
Page 6 of 17
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS
A. Product Data, if applicable:
1. Tapping Saddl e
2. Corporation stop
3. Curb Stop
4. Service Line
5 . Meter Box
6. Meter Box Lid
B. Certificates and Test Reports
1. Prior to shipment of any Water Service components, the manufacturer shall submit
the following:
a. A Certificate of Adequacy of Design stating that the components to be
furnished comply with all regulatory requirements identified in this Section
including:
1) The Reduction of Lead in Drinking Water Act (P.L. 111-380)
2) AWWA C800
3) NSF 61
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE
A. Qualifications
1. Manufacturers
a. Water Services shall meet or exceed the latest revisions of A WW A C800, NSF
61, the Reduction of Lead in Drinking Water Act and shall meet or exceed the
requirements of this Specification.
1.10 DELIVERY, STORAGE, AND HANDLING
A. Storage and Handling Requirements
1. Protect all parts such that no damage or deterioration will occur during a prolonged
delay from the time of shipment until installation is completed and the units and
equipment are ready for operation.
2. Protect all equipment and parts against any damage during a prolonged period at the
site.
3. Prevent plastic and similar brittle items from being directly exposed to sunlight or
extremes in temperature.
4. Secure and maintain a location to store the material in accordance with Section 01
66 00.
CITY O F FORT WORTH
STANDARD CONSTRUCTION SP EC IFI CATION DO CUMEN T S
Rev ised February 14 , 20 17
2022 WATER SERVI CE LEAK
REPAIR CONTRACT
Ci ty Project No . 104552
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2-PRODUCTS
2.1 OWNER-FURNISHED PRODUCTS
A. Water meters for various sizes
2.2 EQUIPMENT, PRODUCT TYPES, AND MATERIALS
A. Manufacturers
33 12 10 -7
WATE R SERVI CE S !-INC H TO 2-IN CH
Page 7 of 17
1. Only the manufacturers as listed on the City 's Standard Products List will be
considered as shown in Section 01 60 00.
a. The manufacturer must comply with this Specification and related Sections.
2. Any product that is not listed on the Standard Products List is considered a
substitution and shall be submitted in accordance with Section 01 25 00 .
3. The Water Services and appurtenances shall be new and the product ofa
manufacturer regularly engaged in the manufacturing of Water Services and
appurtenances having similar service and size.
B . Description
1. Regulatory Requirements
a. All materials shall conform to the Reduction of Lead in Drinking Water
Act (P.L. 111-380). This Act defines "Lead-free" for pipes and other
appurtenances to be less than 0.25 percent lead.
b. Water Services shall meet or exceed the latest revisions of A WWA C800 and
shall meet or exceed the requirements of this Specification.
c. All Water Services components in contact with potable water shall conform to
the requirements ofNSF 61.
C. Materials/Design Criteria
1. Service Lines
a. Provide Type K Copper Tubing per ASTM B88.
b. Furnish in the annealed conditions , unless otherwi se specified in the Contract
Documents.
2. Service Couplings
a. Fitting Ends
1) Flared Copper Tubing with thread dimensions per A WW A C800
2) Provide coupling nuts with a machined bearing skirt of a length equal to the
tubing outer diameter (O.D.).
b. Provide with hexagonal wrench grip compatible with the coupling size.
c. Provide lead-free service couplings in accordance with the Reduction of Lead
in Drinking Water Act.
3. Corporation stops
a. Provide brass castings per A WW A C800 for:
1) Bodies
2) Plugs
3) D washers
CITY OF FORT WORTH
STANDARD CO NS TRUC TION SP EC IFI CATIO N DOCUMENTS
Revi sed Febru ary 14 , 20 17
2022 WATER SERVI CE LEAK
REPAIR CONTRACT
City Project No. 1045 52
4) Bottom nuts
b. Machining and Finishing of Surfaces
33 12 IO -8
WATER SERVI CES I-IN CH TO2-I NCH
Page 8 of I 7
1) Provide 1 ¾ inch per foot or 0.1458 inch per inch ± 0.007 inch per inch
taper of the seating surfaces for the key and body.
2) Reduce large end of the tapered surface of the key in diameter by chamfer
or turning for a distance that will bring the largest end of the seating surface
of the key into the largest diameter of the seating surface of the body.
3) Relieve taper seat in the body on the small end .
4) Extend small end of the key there-through to prevent the wearing of a
shoulder and facilitate proper seating of key.
5) Design key, key nut and washer such that if the key nut is tightened to
failure point, the stem end of the key shall not fracture.
6) Design nut and stem to withstand a turning force on the nut of at least 3
times the necessary effort to properly seat the key without failure in any
manner.
7) Port through corporation stop shall be full size to eliminate turbulence in
the flow way.
8) Design stop for rotation about the axis of the flow passageway inside the
following minimum circles in order to properly clear the tapping machine:
a) Two 7 /8-inch for I-inch corporation stops
b) Four 15/16-inch for 1 ½ -inch and 2-inch corporation stops
c. Provide lead-free corporation stops in accordance with the Reduction of Lead in
Drinking Water Act.
4 . Curb Stops
a. Provide brass castings per A WWA C800.
b. Valve plugs shall be:
1) Cylinder type
2) Plug type , or
3) Ball type
c. Incorporate full flow porting.
d. Provide for full 360 degree plug rotation clockwise or counter-clockwise.
e. Overall Length
1) 3-5 /16 inch± 1/8 inch for I-inch diameter
2) 4-1 /32 inch± 9.32 for I-inch diameter
f. Cylindrical Plug Type
1) Provide O-ring seal at top and bottom.
a) O-ring at top only is acceptable if bottom of curb stop body is closed.
2) Seals shall be Buna N.
3) 1 O-ring seal shall surround the outlet port of the curb stop and act to
effectively seal in the closed position.
4) The port in the plug shall provide a straight through , full size flow way, so
shaped as to eliminate turbulence.
5) All waterways shall be smooth and free of burrs or rough areas.
6) Design the curb stop to provide ease and accuracy of operation and positive
shut-off of water.
g. Tapered Plug Type
1) Provide O-ring seal at top and bottom.
2) The tapered plug and cylindrical recess in the valve body shall be machined
to match within approved manufacturing tolerances.
CITY O F FORT WORTH
STANDARD CONSTRUC TION SPECIFI CATI ON DO CUME TS
Rev ised February 14, 20 17
2022 WATER SERVI CE LEAK
REPAIR CONTRACT
City Project No . I 04552
331 2 10-9
WATER SERVI CE S I-I NCH TO 2-IN CH
Page 9 of 17
3) Inlet and outlet ports shall be sealed by O-rings or combination Teflon U-
shap ed seal rin gs backed with O-rings .
4) The port in the plug shall provide a straight through, full size flow way, so
shap ed as to e limin ate turbul e nce.
5) A 11 waterways shall be s mooth and free of burrs or rough areas.
6) Des ign the curb stop to provide ease and acc uracy of operation and po s itive
shut-off of water.
h. Ball Plug Type
1) Provide double O-ring seals on the stem.
2) The ball sha ll seal against rubber rings mounted in the valve body at th e
inlet and outlet ports.
3) The ball shall b e bronze with a s mooth Teflon coating.
4) The port in the plug sha ll provide a straight through, full size flow way, so
shap ed as to eliminate turbulence .
5) A ll waterways shall be smooth and free of burrs or rough areas.
1. Provi de lead-free curb stops in accordance with the Reduction of Lead in
Drinking Water Act.
5. Straight Adapters
a . Brass castings and thread s per A WW A C800
b. Provide lead-free straight a dapters in accordance w ith the Reduction of Lead in
Drinking W ater Act.
6. Three Part Copper Unions
a . Brass castings and threads per A WW A C80 0
b. Provide lead-free Three Part Copper Unions in accordance w ith the Reduction
of Lead in Drinking Water Act.
7. Straight Meter Couplings
a . Brass castings per A WW A C800
b. Threads per A WW A C700
c. Tailpiece with outside iron pipe thread
d. Chamfer corners on threaded end of meter nut.
e . Machine inside and outside oftailpiece.
f. Provide lead-free Straight Meter Couplings in accordance w ith the Reduction of
Lead in Drinking Water Act.
8. Branch Connections
a. Brass castings per A WW A C800
b . Inlet and outlet connections per A WW A C800
c. Provide lead-free branch connections in accordance with the Reduction of Lead
in Drinking Water Act.
9 . Service Saddles
a. Castings
1) Brass or Nylon coated ductile iron castings per A WW A C800
2) F ree of porosity with sharp edges removed
3) Saddle
a) Form to fit firmly against side of maxi mum diameter of water main
with approximately 180 degrees wrap around.
4) Outlet
a) Design outlet bo ss for no thread di stortion by bending moments.
b) Tapped for taper threaded corporation stop conforming to A WW A
C800.
C ITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised February 14 , 2017
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No . I 04552
33 12 10-10
WATER SERV ICES I-INCH TO 2-INCH
Page 10 of 17
b. Straps
1) Conform to ASTM B98.
2) Fo rm flat to fit uniformly against the wall of the water main.
3) Shall be double straps
4) Rod diameter not less than 5/8 inch flattened to 1 inch on one side .
5) Strap s shall be threaded 5/8 in ch (l l-NC-2A) for a di stance such that ½
inch remains after clamp is fully tightened on th e pip e .
6) Chamfer strap ends to protect the starting threads.
7) The threads shall be full and free from shear.
8) 4-inch and larger pipe shall be in accordance with Section 33 12 25.
c. Nuts
1) Bronze material
a) Same material as straps
2) Dimensions equal to or larger than heavy hexagon nuts
3) Tapped 5/8 in ch (l 1-NC-2B)
d. Gaskets
1) Neoprene rubber material
2) Cemented to sadd le and po s itioned to facilitate in stall ation
10. Brass Flanged Angle Valve
a. For 1 ½-inch and 2-in ch services
b. Brass castings per A WW A C800
c. Valve Body with integral outlet flange and inlet wrenching flat
d. Fit together key and body by turning key and reaming bod y
1) Key with O-ring seal seat at the upper end
2) Lap key and body seat are to conform to corporation stop requirements of
this Specification.
3) The outlet flange shall contain an O-ring seat or a uniform fl at drop-in
flange gasket surface .
4) Drop-in flange gasket surface shall contain gasket retainin g grooves milled
c ir cu lar about the axis of the flange .
5) The size of the outlet flange and the diameter and spacing of the bolt holes
shall conform to A WW A C700.
6) The flange on 2-inch angle valves shall be double drilled to permit
connection to 1 ½ -inch meters.
7) The inl et port of the valve shall be tapered to conform to A WW A C800
taper pipe thread.
8) The key cap shall include a wrenching tee marked with a rai se d or recessed
arrow to show whether the valve is open or closed.
9) Valve Assembly (main bod y, key, key cap)
CITY OF FORT WORTH
a) Brass materi a l per A WW A C800
b) O-ring seal on the top of the key between the key and body seat
c) Key cap shall complete the assembly by attaching to the key by mean s
of a strong bronze pin with phosphor bronze spring washer(s)
depressed between the key cap and the top of the valve main body .
d) Provide with padlock wings for locking the valve in the c lo sed position.
e) There shall be a uniform application of cold water valve grease
between the body and the key.
f) The valve shall be capable of being easil y op ened and stopping lu gs .
g) The waterway throu gh the valve shall be smooth and rounded for
minimum pressure loss , and shal l be free of burrs or fin s .
STANDARD CONSTRUCTION SPECIFICATION DO CUMENTS
Revi sed February 14 , 2017
2022 WATER SERVI CE LEAK
REPAIR CONTRACT
C ity Project No. I 04552
33 12 I O-11
WATE R SERVICES I-INCH TO 2-INCH
Pag e 11 of 17
h) The valve shall be strong, well designed , neat in appearance, water-
tight and entirely adequate for the intended purpose .
i) Provide with either a high quality rubber drop-in gasket or an O-ring
seal depending on the manufacturer's flange seal surface design choice.
e. Provide lead-free brass flanged angle valves in accordance with the Reduction
of Lead in Drinking Water Act.
11. Meter Boxes shat I:
a. Be constructed of:
1) Polymer, black polyethylene material as defined in ASTM D883.
a) Minimum wall thickness of 3/8-inch throughout with no blowing
agents or foaming plastics
b) Body shall be black throughout, blended at the time of manufacture,
and shall have a molded recycled emblem with a minimum of 35
percent Post Industrial/ Pre Consumer Recycled Content-verified with
a Leed Product Documentation.
c) Have a tensile strength greater than 1700 pounds per square inch (psi).
d) Smooth edges and corners and be free from sharp edges so the unit can
be handled safely without gloves.
e) Exter ior free from seams or parting lines .
f) Have crush resistant ribbing along the outside of the box.
g) Have a flange around the lid opening to help prevent settling and aide
in adjustment to grade.
h) Not to be installed in roadway -designed to withstand loading in non-
deliberate and incidental traffic only.
2) Concrete
a) Frame of No. 6 gauge wire welded closed
b) Type I or Type II Portland cement, in accordance with ASTM C 150 ,
portioned with lightweight aggregate, in accordance with ASTM C330
( 1) Percentage of wear not to exceed 40 per ASTM C 131
(2) Minimum 28 day compressive strength of 3 ,000 psi
b. Be able to withstand a minimum 15,000 pounds vertical load
c. Withstand a minimum 400 pounds sidewall load .
d. Have pipe holes measuring a minimum of2-1/2" x 3-1/4".
e. I-inch Standard Meter Box (Class A)
1) For use with services utilizing 5/8-inch x ¾-inch , ¾-inch or ]-inch meter
Single or Dual service meter.
2) Polymer
a) Size: working of not less than 10 inches x 16 inches, 12 inches high
3) Concrete
a) Size: working area not less than 10 -inches x 16-inches, 12 inches high
f . 2-inch Standard Meter Box (Class C)
1) For use with services utilizing 1-1 /2 -inch or 2-inch Single service meter.
2) Polymer
a) Size: working area not less than 14-inches x 28-inches , 12 inches high
3) Concrete
a) Size: working area not less than 15-inches x 26-1 /2-inches, 12 inches
high
g. Bullhead Standard Meter Box (Class B)
1) For use with services utilizing two 5/8-inch x ¾-inch or ¾-inch or I-inch
Single service meter .
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised February 14 , 2017
2022 WATER SERVI CE LE AK
REPAIR CONTRACT
City Project No. I 04552
33 12 10-12
WATER SERVICES I-IN CH TO 2-I NC H
Page 12 of 17
2) Polymer
a) S ize: working area not less than 15-inches x 18-inches, 12 inches high
3) Concrete
a) Size: working area not less than 15-inches x 18-inches, 12 inches high
12. Meter Box Lid
a. Meter Box Lids Shal l:
1) Be solid throughout with reinforcing ribs .
2) Have City of Fort Worth 'Molly ' logo molded into the lid.
3) Bear the Manufacturer's IS (name or logo) and Country of Origin.
4) Be designed both with and without AMI receptacles
5) Have a molded tread-plate
6) Seat securely and evenly in side the meter box and shall not overlap the top
edge of the meter box.
7) Have a molded pick bar for use by meter reading tool.
8) Have Automated Meter Infrastructure (AMI) snap locking slide mounts for
number of meters/endpoi nt s associated with meter box
9) Have an opening to accept the AMI end-poi nt. Opening shall accommodate
an endpoint with a 1-7 /8 in ches diameter.
10) Have recessed AMI end point area , to alleviate a trip hazard, centered over
AMI slide mount. Recess area should be 4-1/2 inches in diameter and 3/8"
deep.
11) Have built-in anti-flotation devices.
b. Cast Iron or Ductile Iron
1) Lids for Concrete Meter Boxes shall be constructed out of a cast iron and
meet RRF-621 specification.
2) Shall withstand a minimum vertical lo ad of 15,000 pounds
3) Coat castings w ith a bituminous emulsified asphalt unless otherwise
spec ifi ed in the Contract Documents, ground smooth, and cleaned with shot
blasting, to get a uniform quality free from strength defects and distortions.
4) Dimensions shall be within industry standards of ±1/16 inch per foot.
5) Shall have a plug in serted in to the AMI receptacle to avoid water entering
through opening until the AMI receptacle is used
6) Be a minimum of 1-3 /4 inches thick at reinforcing ribs.
7) Casting weights may vary ±5 percent from drawing weight per indu stry
standards .
c. Plastic(Composite)
1) The lid shall :
CITY OF FORT WORTH
a) Constructed of Engineered Plastic as defined in ASTM 0883
(1) Have a molded recycled emblem with a minimum of 50 percent
Post Consumer Recycled and 50 percent Post Industrial/ Pre
Consume r Recycled Content-verified with a Leed Product
Documentation.
(2) Be designed to fit a concrete box/cast iron box in retrofit
installations.
(3) Have a tensile strength greater than 1700 psi.
(4) Have a 'knock-out" plug to accept the AMI end-point. Knock-out
diameter shall be 1-7/8 inch diameter. A removable plug may be
substituted for the knock-out plug.
STANDARD CONS TRUCTIO N SP EC IFI CA TIO DOCUMEN TS
Re vi sed February 14 , 20 17
2022 WATER SERVIC E LEAK
REPAIR CONTRACT
City Project No . I 04 552
33 12 10 -13
WAT ER S ERVI CE S I-I N CH TO 2-I NCH
Page 13 of 17
(5) Be constructed out of a composite material blend for maximum
durability and corrosion resistance.
(6) Be black throughout with no blowing agents or foaming plastics
(7) Smooth edges and comers and be free from sharp edges so the unit
can be handled safely without gloves.
(8) Exterior free from seams or parting lines .
(9) Have a molded tread-pattern-tread dimensions shall be .188-inch x
.938-inch x .150-inch deep.
(10) Have "City of Fort Worth" molded into the lid.
(11) Have "Water Meter" molded into the lid-Font shall be standard
Fadal CNC font with ]-inch characters x .150-inch deep.
(12) Have a molded pick hole pocket-dimensions shall be 3-inch x
9/16-inch x Thru Hole with 3/16-inch 304 stainless steel rod.
(13) Have 2 pieces of ½-inch rebar located in lid pockets for
locatability as shown in Drawings.
(14) Have location capability using metal detector.
b) Domestic Manufacture Only-Made in USA molded on Lid .
c) Not to be installed in roadway or parking area
d) Be designed to withstand H-10 loading for non-deliberate and
incidental traffic only as .
e) Have ultraviolet protection.
2) 1-inch Standard Plastic Meter Box Lid (Class A)
a) For use with services utilizing 5/8-inch x ¾-inch, ¾-inch or I-inch
meter Single or Dual service meter.
b) Size: 11-7/8-inch x 17-7/8-inch, 1-1/2 inches high
c) For use with Class A Standard Meter Box.
d) Polymer lid shall seat evenly inside meter box and shall not overlap the
top edge of the meter box.
3) 2-inch Standard Plastic Meter Box Lid (Class C)
a) For use with services utilizing 1-1 /2-inch or 2-inch Single service
meter.
b) Size 27-inches x 15-1 /4-inches, 1-7 /8 inches high
c) For use with Class C Standard Meter Box.
d) Polymer lid shall seat evenly inside meter box and shall not overlap the
top edge of the meter box.
4) Bullhead Standard Plastic Meter Box Lid (Class B)
a) For use with services utilizing two 5/8-inch x ¾-inch or ¾-inch or ]-
inch Single service meter:
b) Size: 16-5/8-inch x 14-5/8-inch , 1-3 /4 inches high
c) For use with Class B Standard Meter Box.
d) Polymer lid shall seat evenly inside meter box and shall not overlap the
top edge of the meter box.
13. Horizontal Check Valve
a. Equip 1 ½-inch and 2-inch Water Services with a horizontal check valve, with
pipe plug, only if specified in the Drawings .
b. If an existing backflow preventer is present, the Contractor is to leave it, and is
not required to provide an additional horizontal check valve.
c . Provide lead-free horizontal check valves in accordance with the Reduction of
Lead in Drinking Water Act.
CITY OF FORT WORTH
ST AND ARD CONSTRUCTION SPECIFI CATION DO C UMENTS
Re vised February 14, 2017
2022 WATER SERVICE LEAK
REPAfR CONTRACT
Ci ty Project No . I 045 52
14. Service Marker
a . 3 inch wide, 5 mil blu e vinyl tape
2.3 ACCESSORIES [NOT USED]
2.4 SOURCE QUALITY CONTROL
A. Tests and Inspections
33 12 10 -14
WATER SER VI CES I-INC H TO 2-IN CH
Page 14 of 17
1. At the City 's option, the manufacturer shall be required to provide certification
records showing conformance of materials , design and testing to these
Specifications.
2. The test procedures shall conform to A WW A C800.
a . In the event that a chosen valve fails the City 's hydrostatic test, the cost of the
test shall be at the expense of the supplier.
b. Proof testing of the remainder of the valves shall be at the cost and
responsibility of the supplier.
c. These tests will be the basis of acceptance or rejection of the remainder of the
shipment by the City .
3. The City reserves the right to select products at random for testing. The failure of
materials to conform to the applicable Specification may result in the rejection of
the ent ir e shipment.
B. Marking
1. Service saddle castings shall be clearly marked by letters and numerals cast thereon
showing:
a. Manufacturer's name
b. Type
c. Size of Pipe
PART 3-EXECUTION
3.1 INSTALLERS
A. A licensed plumber is required for installations on the outlet side of the service meter.
3.2 EXAMINATION [NOT USED]
3.3 PREPARATION [NOT USED]
3.4 INSTALLATION
A. General
1. Install Water Services and appurtenances in accordance with A WW A C800.
2. Install Water Service Lines 5 feet north or east of center of lot frontage on lots 75
feet or wider, or where shown on Drawings.
3. Install Water Service Lines on lot center line on lots less than 75 feet wide, unless
otherwise shown on the Drawings.
4. install services at a minimum depth of 36 inches below final grade/proposed top of
curb, unless otherwise specified in the Contract Documents.
5. Perform leak tests in accordance with Section 33 04 40.
CITY OF FORT WORTH
STANDARD CONS TR UC TI ON SPEC IFI CATION DOCUMENTS
Rev ise d Febru ary 14 , 20 17
2022 WATER SERVIC E LEA K
REPAIR CONTRA CT
City Project No. 104 55 2
33 12 10 -1 5
WA T ER SERVI CES 1-TNCH TO2-INCH
Page 15 of 17
6. Replace existing ¾-inch Service Lines with I-inch new Service Line, tap , and
corporation.
7. Install replaced or relocated services with the service main tap and service line
being in line with the service meter, unless otherwise directed by the City .
8. E xcavate , embed and backfill trenches in accordance with Section 33 05 10 .
B . Handling
1. Haul and distribute Service Line s fittings at the project site and handle with care to
avoid damage.
a. Inspect each segment of Service Line and reject or repair any damaged pipe
prior to lowering into the trench .
b. Do not handle the pipe in such a way that will damage the pipe.
2. At the close of each operating day:
a. Keep the pipe clean and free of debri s, dirt, animals and trash -during and after
the laying operation.
b. E ffectively seal the open end of the pipe using a gasketed night cap .
C. Service Line Installation
1. Service T aps
a. Only ductile iron pipe may be directly tapped .
b . Install service taps and/or tap assemblies of th e sp ecified size as indicated on
the Drawings , or as specified by the Engineer.
c. Perform taps on a water sy stem that is either uncharged or under pressure.
d. Taps cons ist of:
1) For Concrete Pressure Pipe or Steel Pipe
a) Standard internal pipe threaded holes in the pipe walls
(1) Made during pipe fabrication
(2) Provide tapered threaded outlet with cc threads for up to 2-inch.
(3) Provide flange outlet with flange to thread insulator adaptor kits for
4-inch and larger taps.
2) Other pipe materials
a) Bronze service clamp with a sealed , threaded port through which the
pipe wall is drilled to complete a service port
e . Tap Assemblies
1) Consist of corporation stop with iron to copper connection attached to:
a) Copper tubing terminating as shown on the City 's Standard Detail
b) May be required adjacent to gate valves
c) Install as shown on the Drawings , or as directed by the Engineer.
d) When required , shall be included in the unit price bid for installing gate
valve .
2) Chlorination and testing purposes
a) No separate payment will be made for taps required for testing and
chlorination .
2 . Installation of Water Services
a. Install tap and Service Line in accordance with City Details.
b. Install meter box in accordance with City Details .
1) Adjustment of the Service Line to proper meter placement height shall be
considered as part of the Meter Box installation.
3. Trenching
CITY O F FORT WORTH
STANDARD CO NS TRUC TION SPEC IFT CATION DOCUMENTS
Re vised Fe bru ary 14 , 20 17
2022 WATER SERVI CE LEAK
RE PAIR CO NTRACT
City Project No. I 04552
33 12 IO-16
WATER SERVI CES 1-TN CH TO 2-I NC H
Page 16 of 17
a. Provide a trench width sufficiently wide to allow for 2 inches of granular
embedment on either s ide of the Service Line.
4 . Bored Service s
a. Services shall be bored utili z ing a pilot hole havin g a diameter ½ inch to ¾
inches larger than the Service L ine .
5. Arrangement
a. Arrange corporation stops, branches, curb stops, meter spuds , meter boxes and
other associate appurtenances as shown in the City D etail , and to the approval
of the Engineer.
6. Service Marker
a. When Meter Box is not installed immediately subsequent to service installation:
I) Mark Curb Stop with a strip of blue viny l tape fastened to the end of the
service and extending through the backfill approximately 6 inches above
ground at the Meter Box location.
b. Installation of service tap s only :
I) Attach service marker tape to the corporation stop or plug and extend
upward and normal to the main through the backfill at the adjacent trench
edge to at least 6 inches above ground to flag the tap location.
7. Corporation stops
a. Fully open corporation stop prior to backfill.
D. Removal of Existing Water Meters
1. Remove, tag and collect existing Water Service meter for pickup by the City for
reconditioning or replacement.
2. After installation of the Water Service in the proposed location and receipt ofa
meter from the City inspector, install the meter.
3. Reset the meter box as necessary to be flush with existing ground or as otherwi se
directed by the City.
4. All such work on the outlet side of the service meter shall be performed by a
licensed plumber.
3.5 REPAIR/ RESTORATION [NOT USED]
3.6 RE-INSTALLATION [NOT USED]
3.7 FIELD [oR] SITE QUALITY CONTROL
A. Field Tests and Inspections
1. Check each Water Service installation for leaks and full flow through the curb stop
at the time the main is tested in accordance with Section 33 04 40.
3.8 SYSTEM STARTUP [NOT USED]
3.9 ADJUSTING [NOT USED]
3.10 CLEANING [NOT USED]
3.11 CLOSEOUT ACTIVITIES [NOT USED]
3.12 PROTECTION [NOT USED]
3.13 MAINTENANCE [NOT USED]
CITY OF FORT WORTH
STANDARD CON STRUCTION SPEC IFI CATION DOCUMENTS
Re vised February 14, 20 17
2022 WATER SERVIC E L EA K
REPAIR CONTRA CT
City Project No. I 045 52
3312 10-17
WATER SERVICES !-INC H TO 2-INCH
Page 17 of 17
3.14 ATTACHMENTS [NOT USED]
END OF SECTION
Revi s ion Log
DATE NAME SUMMARY OF CHANGE
Added Blue Text for clarificatio n
1.2 A . -Revi sio n to ite ms inc lu ded in price bid
Specificati o n modified to be in accordance with th e Reduction of Lead in Dri nki ng
12/20/20 12 D. Johnson Wate r Act -A ll material s sha ll be lea d free in accordance with this Act.
1.2 .A.3 -Water Meter Service Relo cate was re nam ed Wate r Mete r Service
Reconnect
1.6 .B. -added certification submitta ls for comp li ance with regul atory requirements
A dd ed the phrase', in clud ing grass' to lines;
Part 1, l.2.A.1.c.14 , Part I , l.2 .A.2.c.13, Part 1, l.2.A.2.c.13 , Part I , l.2.A.3.c.11,
2/13/20 13 F. Griffin Partl, 1.2 .A.4.c.l l
Added th e phrase 'and re place ment ' to li ne Part I , 1.2.A.4.c.7
Revi se d lines w ith 'in cludin g grass' replacing with 'exc ludin g grass (seeding,
4/26/20 13 F . Griffin sod din g or hydromulching paid se parately)'
In clud ed in Part I , 1.2, A, I , c, 14 ; Part I , 1.2, A, 2, c, 13; Part I , 1.2 , A, 3, c, 11 ;
Part I , 1.2 , A, 4, 2, 11
6/19/20 13 D . John so n 1.2.A.4.c -Addi ti on of private water se rvice appurtenances relocation to bein g
in clu ded in th e lin ear foo t price of orivate water se rvice s
11/2 1/2016 W. Norwood Require meter box suitable for AMI meter. 2.2,C, 11 & 2.2,C, 12
11 /2 1/2016 W. Norwood Require service saddle with do ubl e straps. 2.2,C,9,b
2/14/17 W . Norwood 2.2, C, 9.a.3 Remove table "Fit Co ntour of pipe ... "
2/14/17 W . No rwood 3.4 , C, l .d.(2) Remove nylon s leeve inserts, re quire cc thread s .
CITY OF FORT WORTH
STANDARD CONS TRU CTION SPECIFICATION DOCUMENTS
Revised February 14, 20 17
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No . l 04552
33 12 25 -I
CONNECTION TO EX ISTING WATER MAINS
Page I of8
SECTION 33 12 25
2 CONNECTION TO EXISTING WATER MAINS
3 PARTl-GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 I. Connection to existing water mains to include, but not limited to:
7 a. Cutting in a tee for a branch connection
8 b. Extending from an existing water main
9 c. Installing a tapping sleeve and valve
10 B. Deviations from this City of Fort Worth Standard Specification
11 1. Measurement and Payment -Due to the unique nature of this contract and the
12 process as outlined in the specification "Summary of Work" (01-11-00) /
13 "Scope of Work" this item is considered subsidiary to the water service being
14 replaced. The work performed and materials furnished in accordance with this
15 item are subsidiary to the unit price per each water service complete in place
16 and minor pipe replacement, regardless of size and pipe material of the
17 existing main. No other compensation will be allowed.
18 C. Related Specification Sections include, but are not necessarily limited to:
19 1. Division O -Bidding Requirements, Contract Forms, and Conditions of the
20 Contract
21 2. Division 1 -General Requirements
22 3. Section 33 04 40 -Cleaning and Acceptance Testing of Water Mains
23 4. Section 33 05 10 -Utility Trench Excavation, Embedment and Backfill
24 5. Section 33 05 30 -Location of Existing Utilities
25 6. Section 33 11 05 -Bolts, Nuts, and Gaskets
26 7. Section 33 11 10 -Ductile Iron Pipe
27 1.2 PRICE AND PAYMENT PROCEDURES
28 A. Measurement and Payment
29 1. Connection to an existing unpressurized Fort Worth Water Distribution System
30 Main that does not require the City to take part of the water system out of service
31 a. Measurement
32 1) This Item is considered subsidiary to the water pipe being installed .
33 b. P ay ment
34 I) The work performed and the materials furnished in accordance with this
35 Item are subsidiary to the unit price bid per linear foot of water pipe
36 complete in place, and no other compensation will be allowed.
37 2. Connection to an existing pressurized Fort Worth Water Distribution System Main
38 that requires a shutdown of some part of the water system
39 a. Measurement
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DO CUMENTS
Revi se d February 6 , 2013
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No . I 04552
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
3.
33 12 25 -2
CONNECTION TO EX ISTING WATER MAINS
Page 2 of8
1) Measurement for this Item s ha ll be per each connection completed.
b . Payment
1) The work perform ed and the materials furnished in acco rdan ce with thi s
Item sha ll be paid for at the unit pri ce bid per eac h "Connection to Existin g
Water Main" in stall ed for:
a) Various s izes of exist in g water distribution main
c . The price bid shall in c lud e all as pects of making the co nn ection including, but
not limited to :
1) Preparing submitt a ls
2) Dewatering
3) Exploratory excavation (as needed)
4) Coordination and notification
5) R emobili zation
6) Temporary li ghting
7) Polyethylene encasement
8) Make-up pieces
9) Linings
10) Pavement remov al
11) Excavation
12) Hauling
13) Disposal of excess material
14) Clean-up
15) Cleaning
16) Disinfection
17) Testing
Connection to an ex isting press uri ze d Fort Worth Water Di st ribution System M a in
by Tapping Sleeve and Va lv e:
a. Measurement
1) Measurement for thi s Item shall be per each connection co mpleted.
b . Payment
1) The work performed and the materi als furnished in accordance with thi s
Item shall be paid for at th e unit price bid per each "Tapping Sleeve and
Valve" in stalled for:
a) Various sizes of connecting main
b) Various sizes of existing water distribution main
c. The price bid shall include all aspects of making the connection including, but
not limited to :
1) Preparing submittals
2) Dewatering
3) Exploratory excavation (as needed)
4) Coordination and notification
5) Tapping Sleeve and Tapping Valve
6) Remobilization
7) Temporary lighting
8) Polyethylene encasement
9) Make-up pieces
10) Linings
11) Pavement remov a l
12 ) Excavation
CITY OF FORT WORTH 2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No. I 04552
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revi sed Febru ary 6, 20 I 3
33 12 25 -3
CONNECTION TO EXISTING WATER MAINS
1
2
3
4
5
6
13) Hauling
14) Disposal of excess material
15) Clean-up
16) Cleaning
17) Disinfection
18) Testing
7 1.3 REFERENCES
8 A. Reference Standards
9 1. Reference standards cited in this Specification refer to the current reference
Page 3 of 8
10 standard published at the time of the latest revision date logged at the end of this
11 Specification, unless a date is specifically cited.
12 2. American Society ofMechanical Engineers (ASME):
13 a. B16.l, Gray Iron Pipe Flanges and Flanged Fittings Classes 25, 125 and 250)
14 3. ASTM International (ASTM):
15 a. A36, Standard Specification for Carbon Structural Steel.
16 b. A193, Standard Specification for Alloy-Steel and Stainless Steel Bolting for
I 7 High Temperature or High Pressure Service and Other Special Purpose
18 Applications
19 c. Al 94, Specification for Carbon and Alloy Steel Nuts for Bolts for High
20 Pressure or High Temperature Service, or Both
21 d. A242, Standard Specification for High-Strength Low-Alloy Structural Steel.
22 e. A283, Standard Specification for Low and Intermediate Tensile Strength
23 Carbon Steel Plates.
24 f. A285, Standard Specification for Pressure Ve sse l Plates, Carbon Steel, Low-
25 and Intermediate-Tensile Strength.
26 g. B 117 , Standard Practice for Operating Salt Spray (Fog) Apparatus.
27 h. D2000, Standard Classification System for Rubber Products in Automotive
28 Applications.
29 4. American Water Works Association (AWWA):
30 a. C200, Steel Water Pipe -6 IN and Larger.
31 b . C207, Steel Pipe Flanges for Waterworks Service -Sizes 4 IN through 144 IN.
32 c. C213, Fusion-Bonded Epoxy Coating for the Interior and Exterior of Steel
33 Water Pipelines .
34 d. C223, Fabricated Steel and Stainless Steel Tapping Sleeves.
35 5. American Water Works Association/American National Standards Institute
36 (AWWA/ANSI):
37 a. Cl 05 /A21.5, Polyethylene Encasement for Ductile-Iron Pipe Systems.
38 b . C 111/ A21.11, Rubber-Gasket Joints for Ductile-Iron Pressure Pipe and
39 Fittings.
40 c. Cl 15A21/15 , Flanged Ductile-Iron Pipe with Ductile Iron or Gray-Iron
41 Threaded Flanges.
42 6. NSF International (NSF):
43 a. 61, Drinking Water System Components -Health Effects .
44 7. Manufacturers Standardization Society of the Valve and Fitting Industry Inc .
45 (MSS):
46 a. SP-60, Connecting flange Joint Between Tapping Sleeves and Tapping Valves.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIF ICA Tl ON DOCUMENTS
Revised February 6, 20 I 3
2022 WATER SER V1 CE LEAK
REPAIR CONTRACT
City Project No. I 04 552
33 12 25 -4
CONNECTION TO EXlSTTNG WATER MAINS
Page 4 of8
1.4 ADMINISTRATIVE REQUIREMENTS
2 A. Pre-installation Meetings
3 1. Required for any connections to an existing, press urized 16-inch or larger City
4 water distribution system main that requires a shutdown of some part of the water
5 system
6 2. May also be required for connections that involve shutting water service off to
7 certain critical businesses
8 3. Schedule a pre-installation meeting a minimum of3 weeks prior to proposed time
9 for the work to occur.
10 4. The meeting shall include the Contractor, City Inspector and City Valve Crew.
11 5. Review work procedures as submitted and any adjustments made for current field
12 conditions.
13 6 . Verify that all valves and plugs to be used have adequate thrust restraint or
14 blocking.
15 7. Schedule a test shutdown with the City.
16 8. Schedule the date for the connection to the existing system.
17 B . Scheduling
18 1. Schedule work to make all connections to existing 16-inch and larger mains:
19 a. During the period from November through April, unless otherwise approved by
20 the City
21 b. During normal business hours from Monday through Friday, unless otherwise
22 approved by the City
23 2. Schedule City Valve Crew by 1 :00 P.M. a minimum of 1 business day prior to
24 planned disruption to the existing water system.
25 a. In the event that other water system activities do not allow the existing main to
26 be dewatered at the requested time, schedule work to allow the connection at an
27 alternate time acceptable to the City.
28 1) If water main cannot be taken out of service at the originally requested
29 time, coordination will be required with the City to discuss rescheduling
30 and compensation for mobilization.
31 2) No additional payment will be provided if the schedule was altered at the
32 Contractor's request.
33 1.5 SUBMITT ALS
34 A. Submittals shall be in accordance with Section 01 33 00.
35 B. All submittals shall be approved by the City prior to delivery and/or fabrication for
36 specials.
37 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS
38 A. Product Data, if applicable
39 1. Tapping Sleeve noting the pressure rating and coating system supplied including:
40 a. Dimensions, weights, material list, and detailed drawings
41 b. Maximum torque recommended by the manufacturer for the valve by size
42 B. Submittals
CITY OF FORT WORTH
STANDARD CONSTRUCT ION SPECIFICATION DOCUMENTS
Revised February 6, 2013
2022 WATER SERVICE LEAK
REPAlR CONTRAC T
City Project No. I 04552
33 12 25 -5
CONNEC TION TO EXISTING WATER MAINS
Page 5 of8
1. Provide a detailed sequence of work for 16-inch, or larger , connections if required
2 by City that includes :
3 a. Re s ults of exploratory excavation
4 b. Dewatering
5 c. Procedure for connecting to the existing water main
6 d. Time period for completing work from when the water is shut down to when
7 the main is back in service
8 e. Testin g and repressurization procedures
9 2. Welders that are assigned to work on connection to concrete cylinder or steel pip e
1 O mu st be certified and provide Welding Certificates, upon request, in accordance
11 with A WWA C2OO.
12 1.7 CLOSEOUT SUBMITTALS [NOT USED]
13 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
14 1.9 QUALITY ASSURANCE [NOT USED]
15 1.10 DELIVERY, STORAGE, AND HANDLING
16 A. Storage and Handling Requirements
17 1. Protect parts so that no damage or deterioration occurs during a prolonged delay
18 from the time of shipment until installation is completed.
19 2. Protect all equipment and parts against any damage during a prolon ged period at the
20 site.
21 3. Protect the finished surfaces of all exposed flanges u sin g wooden flanges , strongly
22 built and securely bolted thereto.
23 4. Protect finished iron or steel surfaces not painted to prevent rust and corros ion.
24 5. Prevent plast ic and similar brittle items from being exposed to direct sunlight and
25 extremes in temperature.
26 6. Secure and maintain a location to store the material in accordance with Section O 1
27 66 00.
28 1.11 FIELD [SITE] CONDITIONS [NOT USED]
29 1.12 WARRANTY
30 A. Manufacturer Warranty
31 1. Manufacture r 's warranty shall be in accordance with Divi s ion 1.
32 PART 2 -PRODUCTS
33 2.1 OWNER-FURNISHED [oR] OWNER-SUPPLIED PRODUCTS [NOT USED]
34 2.2 EQUIPMENT, PRODUCT TYPES AND MATERIALS
35 A. Manufacturers
36 1. Only the manufacturers as listed by the City 's Standard Products List will be
37 considered as shown in Section 01 60 00 .
38 a. The manufacturer must comply with this Specification and related Sections.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revi sed February 6, 20 I 3
2022 WATER SERVJCE LEAK
REPAIR CONTRACT
City Project No . I 04552
33 12 25 -6
CONNECTIO N TO EX ISTIN G WATE R MAIN S
Page 6 of8
2. Any product that is not listed on the Standard Products List is considered a
2 substitution and shall be s ubmitted in accordance with Section 01 25 00.
3 B. Description
4 1. Regulatory Requirements
5 a. Tapping Sleeves shall meet or exceed A WWA C223 and the requirements of
6 this Specification.
7 b . All valve components in contact with potable water shall conform to the
8 requirements ofNSF 61.
9 C. Tapping Sleeve Materials
10 I. Body
1 I a. Body: Carbon Steel per ASTM A283 Grade C, ASTM A285 Grade C, ASTM
12 A36 Steel or equal
13 b. Finish: fusion bonded epoxy coating to an average 12 mil thickness. Fusion
14 applied per A WWA C213.
15 c . All buried tapping sleeves shall be provided with polyethylene encasement in
16 accordance with A WW A /ANSI C105 /A21.5.
17 1) Polyethylene encasement shall be in accordance with Section 33 11 10.
18 2. Flange
19 a . Carbon Steel per ASTM A36 in accordance with AWWA C207 and ASME
20 B16.1 Class 125.
21 b. Recessed for tapping valve per MSS SP-60
22 3. Bolts and Nuts
23 a. Flanged Ends
24 1) Meet requirements of A WW A C 115 or A WW A C207 depending on pipe
25 material.
26 2) Provide bolts and nuts in accordance with Section 33 11 05.
27 4. Gaskets
28 a. Provide gaskets in accordance with Section 33 11 05.
29 5. Test Plug
30 a. ¾-inch NPT carbon steel with square head and fusion bonded epoxy coating
31 2.3 ACCESSORIES [NOT USED]
32 2.4 SOURCE QUALITY CONTROL [NOT USED]
33 PART 3 -EXECUTION
34 3.1 INST ALLERS [NOT USED]
35 3.2 EXAMINATION
36 A. Verification of Conditions
37 1. Verify by exploratory excavation, if needed, that existing water main is as depicted
38 in the Drawings and that the location is suitable for a connection to the existing
39 water main.
40 a. Excavate and backfill trench for the exploratory excavation in accordance with
41 33 05 10.
CITY OF FORT WORTH
ST AND ARD CO N STRUCTION SPEC IFl CA n o DOCUM E TS
Revi sed Fe bruary 6, 20 13
2022 WATER SERVIC E LEAK
REPAIR CONTRACT
C ity Projec t No . I 04 55 2
33 12 25 -7
CONNECTION TO EX ISTING WATE R MAINS
Page7of8
2
3
4
2. Verify that all equipment and materials are avail ab le on-site prior to the shutdown
of the existing main.
3. Pipe lines shall be completed , tested and authorized for connection to the exist in g
system in accordance with Section 33 04 40.
5 3.3 PREPARATION [NOT USED)
6 3.4 INSTALLATION
7 A. General
8 I. Upon disruption of the existing water main , continue work until the connection is
9 complete and the existing water main is bac k in service.
10 B. Procedure
11 I. Expose the proposed connection point in accordance with Section 33 05 10 .
12 2. Dewater the existing water line so the chlorin ated water is not unlawfully
13 discharged.
14 3. Maintain the water that may bleed by existing valves or plugs durin g installation
15 within the work area to a reasonable level.
16 a. Control the water in such a way that it doe s not interfere with the proper
17 in stallation of the connection or create a discharge of chlorinated water.
18 4-, If a ny discharge of chlorinated water occurs, di scharged water shall be de-
19 chlorinated in accordance with Section 33 04 40
20 5 . Cut and remove existing w ater main in order to make the connection.
21 6 . Verify that the existing pipe lin e is suitable for the propo se d connection.
22 7. Place trench foundation and bedding in accordance with 33 05 10.
23 8. In the event that a tapping s le eve and valve is used , the coupon from the existing
24 water main shall be submitted to the City.
25 9. Prevent embedment, backfill , soi l, water or other debris form entering the pipeline.
26 10. Estab li sh thrust restraint as provided for in the Drawings.
27 11. Clean and disinfect the pipeline associated with the connection in accordance with
28 Section 33 04 40.
29 12 . Place embedment to the top of the pipe zone.
30 13. Request that the City Valve Crew re-pressurize the pipeline .
31 14. Directionally flush the connection in accordance with Section 33 04 40.
32 15. Request that City Valve Crew open all remaining valves.
33 3.5 REPAIR/RESTORATION [NOT USED]
34 3.6 RE-INSTALLATION [NOT USED]
35 3.7 FIELD [oR] SITE QUALITY CONTROL [NOT USED]
36 3.8 SYSTEM STARTUP [NOT USED]
37 3.9 ADJUSTING [NOT USED]
38 3.10 CLEANING [NOT USED)
CITY OF FORT WORTH
STANDARD CONSTRUCTIO N SPECIF ICATIO N DOCUMENTS
Revi sed February 6, 20 13
2022 WATER SERVICE LEAK
REPAIR CONTRACT
C ity Project No . I 04552
3.11 CLOSEOUT ACTIVITIES [NOT USED)
2 3.12 PROTECTION [NOT USED]
3 3.13 MAINTENANCE [NOT USED]
4 3.14 ATTACHMENTS [NOT USED]
33 1225-8
CONNECTION TO EX !STfNG WATER MAINS
Page 8 of8
5 END OF SECTION
6
7
Revision Log
DATE NAME SUMMARY OF CHANGE
12/20/20 12 D. Johnson 2.2.C.3 and 4 -Added refe rence to Section 33 11 05 and removed bolt, nut and
gasket material specification
2/6/201 3 D . Townsend 3.4.B.4 Modified to refer to Section 33 04040
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIF!CA TION DOCUME TS
Revised February 6 , 2 0 I 3
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No . 104552
SECTION 34 7113
2 TRAFFIC CONTROL
3 PARTl-GENERAL
4 1.1 SUMMARY
5 A. Section Includes :
34 7 1 13 -1
TRAFF IC CONTROL
Page l of6
6 1. Install ation of Traffic Control D ev ice s and preparation of Traffic Control Plans
7 B. Deviations from thi s City of Fort Worth Standard Specification
8 1. Traffic Control -The contractor will be required to obtain a "Street Use Permit"
(01-55-26) prior to starting work. As part of the "Street Use Permit", a traffic control
plan is required. The contractor shall be responsible for providing traffic control
during the construction of each work order consistent with the provisions set forth in
the latest edition of the "Texas Manual on Uniform Traffic Control Devices"
(TMUTCD).
Unless otherwise included as part of the work order, the contractor shall submit a
traffic control plan (duly sealed, signed and dated by a Registered Professional
Engineer (P.E.) in the State of Texas), to the City Traffic Engineer at or before the
start of each work order. The P.E. preparing the traffic control plan may utilize
standard traffic reroute configurations posted as "Typicals" on the City's Buzzsaw
website. Although the work will not begin until the traffic control plan has been
reviewed and approved, the contractor's time will begin in accordance with the
timeframe mutually established on the issued work order and specified in "Summary
of Work" (01-11-00).
Work shall not be performed on certain streets/ locations during "peak traffic
periods" as determined by the City Traffic Engineer and in accordance with the
applicable provision of the "City of Fort Worth Traffic Control Handbook for
Construction and Maintenance Work Areas".
Given the unique nature of this contract Traffic Control has been categorized by
type of street I traffic density. The category that the Traffic Control fits in
(Residential, Arterial or Major Arterial) will be mutually established by the City's
Project Manager, Traffic Engineer and Contractor prior to the start of each work
order issued. Payment for Traffic Control shall cover the design, installation and
maintenance of the Traffic Control plan and devices required at the appropriate unit
price bid.
9 C. Related Specification Sections include , but are not necessaril y limited to:
10 1. Division 0 -Bidding Requirem ents , Contract Forms and Conditions of the Contract
11 2. Division 1 -General Require ments
12 1.2 PRICE AND PAYMENT PROCEDURES
13 A. Measurement and Payment
14 I. Installation of Traffic Control Devices
15 a. Measurement
16 1) Meas urement for Traffic Control Devices shall be per month for the Project
17 duration.
18 a) A month is defined as 30 calendar days.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revi se d March 22 , 202 1
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No. 104 552
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
I
2
3
4
5
6
7
8
9
10
11
12
13
14
b . Pay ment
34 7 1 13 -2
TRAFFIC CO NTRO L
Page 2 of 6
1) The work perform ed and materials furni shed in accordance with this Item
and meas ured as provided under "Meas ur ement " shall be paid for at the
unit price bid for "Traffic Control ".
c. The price bid shall include :
I) Traffic Control implementation
2) Installation
3) Maintenance
4) Adjustments
5) Replacements
6) Removal
7) Po lice assi stance during peak hours
2. Portable Message Signs
a. Measurement
I) Measurement for this Item shall be per week for the duration of use .
b. Payment
1) The work performed and materials furnished in accordance to this Item and
measured as provided under "Measurement" shall be paid for at the unit
price bid per week for "Portable Message Sign" rental.
c. The price bid shall inc lude:
I) Delivery of Portable Message Sign to Site
2) Message updating
3) Sign movement throughout construction
4) Return of the Portable Message Sign post-construction
3. Preparation of Traffic Control Plan Detai Is
a. Measurement
1) Measurement for this Item be per each Traffic Control Detai I prepared.
b. Payment
1) The work performed and materials furnished in accordance with this Item
shall be paid for at the unit price bid per each "Traffic Control Detail "
prepared.
c. The price bid shall include:
I) Preparing the Traffic Control Plan Details for closures of 24 hours or
longer
2) Adherence to City and Texas Manual on Uniform Traffic Control Devices
(TMUTCD)
3) Obtaining the signature and seal of a licensed Texas Professional Engineer
4) Incorporation of City comments
15 1.3 REFERENCES
16 A. Reference Standards
17 1. Reference standards cited in this Specification refer to the current reference
18 standard published at the time of the latest revision date logged at the end of this
I 9 Specification, unless a date is specifically cited .
20 2. Texas Manual on Uniform Traffic Control Devices (TMUTCD).
21 3. Item 502 , Barricades, Signs, and Traffic Handling of the Texas Department of
22 Transportation , Standard Specifications for Construction and Maintenance of
23 Highways, Streets, and Bridges.
24 1.4 ADMINISTRATIVE REQUIREMENTS
C ITY OF FORT WORTH
STANDARD CONS TRUC TIO SPEC IFI CATION DOCUMEN TS
Revi sed March 22 , 202 1
2022 WATER SERVICE LEAK
REPAIR CONTRACT
Ci ty Project No. 104552
34 71 I 3 -3
T RA FFI C CONTROL
Page 3 of6
25 A. General
26 1. Contractor shall minimize lane closures and impact to vehicular/pedestrian traffic.
27 B. Coordination
28 1. Contact Traffic Services Division (817-392-7738) a minimum of 48 hours prior to
29 implementing Traffic Control within 500 feet of a traffic signal.
30 C. Sequencing
31 1. Any deviations to the Traffic Control Plan included in the Drawings must be first
32 approved by the City and design Engineer before implementation.
33 1.5 SUBMITTALS
34 A. Provide the City with a current list of qualified flaggers before beginning flagging
35 activities. Use only flaggers on the qualified list.
36 B. Obtain a Street Use Permit from the TPW Department's Transportation Division . The
37 Traffic Control Plan (TCP) for the Project shall be as detailed on the Traffic Control
38 Plan Detail sheets of the Drawing set. A copy of this Traffic Control Plan shall be
39 submitted with the Street Use Permit.
40 C. Traffic Control Plans shall be signed and sealed by a licensed Texas Professional
41 Engineer.
l D . Contractor shall prepare Traffic Control Plans ifrequired by the Drawings or
2 Specifications. The Contractor will be responsible for having a licensed Texas
3 Professional Engineer sign and seal the Traffic Control Plan sheets .A traffic control
4 "Typical " published by City of Fort Worth, the Texas Manual Unified Traffic Control
5 Devices (TMUTCD) or Texas Department of Transportation (TxDOT) can be used as
6 an alternative to preparing project/site specific traffic control plan if the typical is
7 applicable to the specific project/site.
8 E. Lane closures 24 hours or longer shal I require a site-specific traffic control plan.
9 F . Contractor responsible for having a licensed Texas Professional Engineer sign and seal
10 changes to the Traffic Control Plan(s) developed by the Design Engineer.
11 1.6 ACTION SUBMITTALS/INFORMA TIONAL SUBMITTALS [NOT USED]
12 1.7 CLOSEOUT SUBMITTALS [NOT USED]
13 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
14 1.9 QUALITY ASSURANCE [NOT USED]
15 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
16 1.11 FIELD [SITE] CONDITIONS [NOT USED]
17 1.12 WARRANTY [NOT USED]
18 PART2 -PRODUCTS
19 2.1 OWNER-FURNISHED !OR] OWNER-SUPPLIED PRODUCTS [NOT USED]
20 2.2 ASSEMBLIES AND MA TE RIALS
21 A . Description
CITY OF FORT WORT H
STANDARD CONS TRUC TION SPEC IFI CATION DO CUMENTS
Re vise d March 22 , 2021
2022 WA TER SERVI CE LEAK
RE PAIR CO NTRA CT
City Proj ect No . I 04552
22 I. Regulatory Requirements
34 71 13 -4
TRAFFIC CONTROL
Page 4 of 6
23 a. Provide Traffic Control Devices that conform to details shown on th e
24 Drawin gs, the TMUTCD, and TxDOT's Compliant Work Zone Traffic Control
25 Device L ist (CWZTCDL).
26 2 . Mate ri a ls
27 a . Traffic Control D ev ices must meet all reflectivity re quirements included in the
28 TMUTCD a nd TxDOT Specifications -Item 502 at all times during
29 construction.
30 b . Electronic mes sage boards shall be provided in accordance with the TMUTCD.
2.3 ACCESSORIES [NOT USED]
2 2.4 SOURCE QUALITY CONTROL [NOT USED]
3 PART 3 -EXECUTION
4 3.1 EXAMINATION [NOT USED]
5 3.2 PREPARATION
6 A. Protection ofln-Place Conditions
7 I. Protect existing traffic signal equipment.
8 3.3 INSTALLATION
9 A. Follow the Traffic Control Plan (TCP) and install Traffic Control Devices as shown on
10 the Drawings and as directed .
l l B . Install Traffic Control Devices straight and plumb .
12 C. Do not make changes to the location of any device or implement any other changes to
13 the Traffic Control Plan without the approval of the Engineer.
14 I. Minor adjustments to meet field constructability and visibility are allowed.
15 D. Maintain Traffic Control Devices by taking corrective action as soon as possible.
16 I. Corrective action includes but is not limited to cleaning, replacing, straightenjng,
17 covering, or removing Devices .
18 2 . Maintain the Devices such that they are properly positioned, spaced, and legible,
19 and that retroreflective characteristics meet requirements during darkness and rain.
20 E . If the Inspector discovers that the Contractor has failed to comply with applicable federal
21 and state laws (by failing to furnish the necessary flagmen, warning devices , barricades,
22 1 ights, signs, or other precautionary measures for the protection of persons or property), the
23 Inspector may order such additional precautionary measures be taken to protect persons
24 and property.
25 F. Subject to the approval of the Inspector, portions ofthjs Project, wruch are not affected by
26 or in conflict with the proposed method of handlin g traffic orutility adjustments, can be
27 constructed during any phase.
28 G . Barricades and signs shall be placed in such a manner as to not interfere with the sight
29 distance of drivers entering the highway from driveways or side streets.
30 H. To facilitate shifting, barricades and signs used in lane closures or traffic staging may
31 be erected and mounted on portable supports.
32 1. The support design is subject to the approval of the Engineer.
CITY OF FORT WORTH
STANDARD CONSTRUCT IO SPECCF ICAT ION DOCUMENTS
Re vised March 22 , 202 1
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No. I 04552
34 71 13 -5
TRAFFIC CONTROL
Page 5 of6
33 I. Lane closures shall be in accordance with the approved Traffic Control Plans.
34 J. If at any time the existing traffic signals become inoperable as a result of construction
35 operations, the Contractor shall provide portabl e stop signs with 2 orange fl ags, as
36 approved by the E ngineer, to be used for Traffic Control.
1 K . Contractor shall make arrangements for police assistance to direct traffic if traffic signal
2 tum-ons, street light pole installation, or other construction will be done durin g peak traffic
3 times (AM: 7 am -9 am , PM: 4 pm -6 pm).
4 L. Flaggers
5 1. Provide a Contractor representative who has been certified as a flagging in structor
6 through courses offered by the Texas Engineering Extension Service, the American
7 Traffic Safety Services Association, the N at ional Safety Council, or other approved
8 organizations.
9 a. Provide the certificate indicating course completion when requested.
10 b . This representative is responsible for training and assuring that all flaggers are
11 qualified to perform flagging duties .
12 2. A qualified flagger must b e independently certified by 1 of the organizations li sted
13 above or trained by the Contractor's certified flaggin g in structor.
14 3. Flaggers must be courteous and able to effectively communicate with the public .
15 4. When directing traffic, flaggers must use standard attire, fl ags, signs, and signals
16 and follow the flagg ing procedures set forth in the TMUTCD.
17 5. Provide and maintain flaggers at such points and for such periods of time as m ay be
18 required to provide for the safety and convenience of public travel and Contractor's
19 personnel , and as shown on th e Drawings or as directed by the Engineer.
20 a. These flaggers shall be located at each end of the lane closure.
21 M. Remova l
22 1. Upon completion of Work, remove from the Site all barricades, signs, cones, li ghts
23 and other Traffic Control Devices used for work-zone traffic handling as soon as
24 practical in a timely manner, unless otherwise shown on the Drawings.
25 3.4 REPAIR/RESTORATION [NOT USED]
26 3.5 RE-INSTALLATION [NOT USED]
27 3.6 FIELD !OR] SITE QUALITY CONTROL [NOT USED]
28 3.7 SYSTEM STARTUP [NOT USED]
29 3.8 ADJUSTING [NOT USED]
30 3.9 CLEANING [NOT USED]
31 3.10 CLOSEOUT ACTIVITIES [NOT USED]
32 3.11 PROTECTION [NOT USED]
33 3.12 MAINTENANCE [NOT USED]
34 3.13 ATTACHMENTS [NOTUSED]
35 END OF SECTION
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIF ICATION DOCUMENTS
Revised March 22 , 2021
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No . I 04552
36
37
DATE NAME
11 /22/13 S . Arnold
3 /22/202 1 M Owen
CIT Y OF FORT WO RTH
Revi s ion Log
SUMMARY OF CHANGE
34 7 1 13 -6
TRAFFIC CONTROL
Page 6 of 6
A dded p o li c e ass ista n ce, re qu irement fo r w he n a s ite s p ecifi c TCP is re quired
1.4 A . A dde d la ng uage to e mphas ize minimizi n g of lan e cl osures a nd im pact to
traffic.
1.5 C larified submittal requirem ents
3 .3 M. C larifi e d re m oval re quirem e nts
ST AND ARD CONSTRUCTION SPECIF ICAT ION DOCUMENTS
Revised March 22 , 202 1
2022 WATER SERVI CE LEAK
REPAIR CONTRA CT
C ity Project No. 104552
APPENDIX
GC-4.01 Availability of Lands -None
GC-4.02 Subsurface and Physical Conditions -None
GC-4.04 Underground Facilit ies -None
GC-4.06 Hazardous Environmental Condition at Site -None
GC-6.06.D Minority and Women Owned Business Enterprise Compliance
Business Equity -Instructions to Bidders about the Business Equity Goal
Business Equity -Utilization Form
M/WBE -Prime Contractor Waiver Form
Business Equity -Good Faith Effort Form
M /WBE -Joint Venture E li gibi lity Form
GC-6.07 Wage Rates
2013 Prevailing Wage Rates (Heavy & Highway Construction Projects)
GC-6.09 Permits and Uti liti es -None
GC-6.24 Nondiscrimination -None
GR-01 60 00 Product Requirements -None
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revi sed Jul y I, 2011
2022 WATER SERVICE LEAK
REPAIR CONTRACT
Ci ty Project No . 104 552
GC-4.01 Availability of Lands
THIS PAGE LEFT INTENTIONALLY BLANK
CITY OF FORT WORTH
STANDARD CONSTRUCT ION SPECIFICAT ION DOCUMENTS
Revised July I , 20 I I
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No . I 04552
GC-4.02 Subsurface and Physical Conditions
THIS PAGE LEFT INTENTIONALLY BLANK
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised Jul y I, 2011
2022 WATER SERVICE LEAK
REPA IR CONTRACT
City Project No . 104552
GC-4.04 Underground Facilities
THIS PAGE LEFT INTENTIONALLY BLANK
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July I , 20 11
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No. I 04552
GC-4.06 Hazardous Environmental Condition at Site
THIS PAGE LEFT INTENTIONALLY BLANK
CITY OF FORT WORTH
ST AND ARD CONSTRUCTION SPECIFICATION DOCUMENTS
Rev ised Ju ly 1, 20 11
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No. 104552
GC-6.06.D Minority and Women Owned Business
Enterprise Compliance
Business Equity -Instructions to Bidders about the
Business Equity Goal
Business Equity -Utilization Form
M/WBE -Prime Contractor Waiver Form
Business Equity -Good Faith Effort Form
M/WBE -Joint Venture Eligibility Form
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFI CATIO N DOCUMENTS
Revised Jul y I , 2011
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No. I 04552
FORT WORTH @ City of Fort Worth
Business Equity Division ~
INSTRUCTIONS TO BIDDERS ABOUT THE BUSINESS EQUITY GOAL
Bid number: ______ Business Equity Goal: _____ %
It is the policy of the City of Fort Worth to ensure the full and equitable utilization of Business Equity
Firms when appropriate, in the procurement of all goods and services . When a Business Equity Goal
is established for a bid, it means that the City of Fort Worth believes that there are Business Equity
Firms available that can provide goods or services requested by the bid.
The Business Equity Goal for Bid number ____ is ___ %. This means that the City
believes that there are available Business Equity Firms that can provide goods or services required
by this bid and therefore, ___ % of the Bidder's awarded amount must be spent with a Business
Equity Firm. All requirements and regulations stated in the City's current Business Equity Ord inance
#25165-10-2021 apply to this bid. Definitions are at the end of this document.
Because a Business Equity Goal has been established for this bid, in order for your bid to be
considered, a Bidder must satisfy one {1} of the conditions below.
A. Commit to Meet or Exceed the Business Equity Goal
Hire Business Equity Firm(s) to provide goods or services and spend at least the goal amount
with the Business Equity Firm(s).
Step 1: Obtain a listing of Business Equity Firms by completing the "Request for Listing of
Certified Firms Form" located at the City of Fort Worth's Business Equity Division
website .
Step 2: Request bids from Business Equity Firms to provide goods or services at least 1 O
calendar days before bid opening.
Step 3: Submit the following two (2) forms:
a. Utilization Plan
b. Letter(s) of Intent
B. Prove a Good Faith Effort
Show attempt to hire Business Equity Firms to meet or exceed the goal, but was unsuccessful.
This can occur in two (2) ways:
1) Bidder proposes a smaller Goal
Step 1: Obtain a listing of Business Equity Firms by completing the "Request for Listing of
Certified Firms Form" located at the City of Fort Worth's Business Equity Division
website.
Step 2: Request bids from Business Equity Firms to provide goods or services at least 10
calendar days before bid opening.
Step 3: Submit the following three (3) forms:
a. Utilization Plan
b. Letter(s) of Intent
c. Good Faith Effort
2) Bidder proposes a 0% Goal
Step 1: Obtain a listing of Business Equity Firms by completing the "Request for Listing of
Certified Firms Form" located at the City of Fort Worth's Business Equity Division
website.
Step 2: Request bids from Business Equity Firms to provide goods or services at least 10
calendar days before bid opening . ·
Step 3: If unsuccessful, submit Good Faith Effort Form. Please see Ordinance §20 -370 (g)
page for requirements of an acceptable Good Faith Effort.
C. Prove that the Bidder Can Perform the Service and Provide all Materia ls on the Project
as the Prime Contractor
Bidder must show that the Bidder is providing all of the goods and services through their own
company and that there are no goods or services provided by a third party or an affiliate.
Bidder will not purchase any supplies or inventory from a third party.
Step 1: Must submit Prime Contract Waiver Form
D. C reate a Jo int Venture with a Business Equity Firm
At least one or both of the firms must be a Business Equity Firm
Step 1: Must submit Joint Venture Form
DEADLIN E T O SUBMI T REQ U IR ED DO CUM E NTS AND FO RMS
Bidders must submit sealed bids to be opened at the date, time, and place stated in the solicitation for
the public opening of bids. Faxed copies will not be accepted.
FREQUEN TLY ASKED QUES TI O NS
1. If I am Business Equity Firm, can I count my performance of the bid?
Answer. A Business Equity Prime Contractor can count its self-performance towards meeting the
Business Equity Goal for the assigned North American Industry Classification System (NAICS)
commodity codes on its Minority Business Enterprise (MBE) or Women Business Enterprise (WBE)
certification.
2. What if I am a Business Equity Firm, but I am unable to self perform all work or provide all of the
goods under the bid, can I count my performance under the Bid?
Answer. If the Business Equity Prime cannot self-perform all of the work, it will be accountable for
subcontracting with certified firms to meet the overall goal. Business Equity Firms that qualify under
the "Significant Business Presence" definition may count in the Program upon approval of DVIN-BE.
3. This bid does not have a set amount that the City will purchase from the Awarded Bidder, how do I
complete the form?
Answers:
a. For a low bid procurement, the lowest bidder shall submit a Utilization Plan no later than 2:00 PM
on the third business day after bids are opened detailing all Subcontractors the Contractor intends
to utilize in its performance of a Contract. Contractors that are Business Equity Firms may count
their self-performed services towards meeting a Business Equity Goal.
b. For a Best Value procurement, all bidders who wish to be considered for evaluation scoring shall
submit a Utilization Plan by 2:00 PM on the third business day after the bids are opened detailing
all Subcontractors the Contractor intends to utilize in its performance of a Contract. Contractors
that are Business Equity Firms may count their self-performed services towards meeting a
Business Equity Goal.
c. Non-compliance. If the lowest bidder for a low bid procurement or any bidder for a Best Value
procurement does not timely submit its Utilization Plan with the required documents, that bidder
will be deemed No n-Responsive. For a low bi d procurement, the City will notify the next lowest
bidder who shall then submit a Utilization Plan with required documents no later than 2:00 PM on
the third business day after the bidder receives notification. This process will be followed until a
bidder submitting the required documents is selected.
DEFINITIONS
Business Equity Firm means an Independent Firm that is a Certified minority-and/or women-owned
business enterprise (M/WBE) with a Significant Business Presence in the City's Marketplace.
Business Equity Goal means a calculation prepared by the DVIN-BE that includes all the following
factors: the detailed cost estimate of the work to be performed, or goods purchased ; the 6-county
Marketplace; the availability of Business Equity Firms and non -Business Equ ity Firms in the Marketplace
determined ona Contract-by-Contract basis; and the subcontracting/supplier opportunities of each
project.
Certified means those firms identified by the North American Industry Class ification System (NAICS)
that have been determined to be a bona fide MBE or WBE by the North Central Texas Regional
Certification Agency (NCTRCA), the Dallas/Fort Worth Minority Supplier Development Council (DFW
/MSDC), Women's Business Council-SW (WBCS), Texas Department of Transportation (TxDOT) or
another certifying agency that the DVIN-BE may deem appropriate and accepted by the City of Fort
Worth.
DVIN-BE means the City's Department of D iversity and Inclusion -Business Equity Division
Good Faith Effo rt s means the actions undertaken by a Contractor and approved by DVIN-BE as
described inthe Business Equity Ordinance §20-370 (g).
Joint Ventu re means a business entity formed by two or more independent Persons for the purpose of
pursuing a common objective, such as a prime contract. The result ing business entity has additional
re sources and capacity, enhancing its ability to compete for larger awards. A joint venture is generally
characterized by shared ownership, shared returns and risks , and shared governance. In a joint venture,
the prime managing partner holds 51 % or more interest in the business. Partner(s) hold less than 51 %
interest but in most cases, not less than 20%.
Marketplace means the geographic area as defined by the City's most current Disparity Study (i.e.,
Tarrant, Dallas, Denton, Johnson, Parker and Wise counties).
Re s pon si ve means that a Person is compliant with the requirements of the Business Equity Ordinance .
Sig ni fic ant Bus iness Presence means a Person (1) which has its principal place of business located
inside the Marketplace; (2) which has its principal place of business located outside the Marketplace but
has been verified to be in existence for a minimum of 24 months and from which at least 20% of the
business's workforce is based in the Marketplace; or (3) which has cumulative business receipts
greater than $1,000,000 for work done in the Marketplace since January 1, 2013 .
Utilization Plan means the list of Business Equity Firms that a Contractor commits will be utilized to
meet t h e B usiness Equity Goal for a specific project , the scopes of the work and the dollar values or the
percentages of the work to be performed.
VIOLATIONS AND SANCT IONS
1. Failure to comply with the City's Business Equity Ordinance will result in the bid being
considered "Non-Responsive ."
2 . Failure to submit the required Business Equity forms and documentation will result in the bid being
con sidered non-responsive and a "written warning" letter that may impact the Offeror's evaluation scoring
on future City bid opportunities for up to 12 months, refer to Ordinance §20-373 on V IOLATIONS AND
SANCTIONS for continued offenses or fa ilures to comply.
If you have any que stions , con ta ct Department of D ive rs ity & Inclusi o n, Business Equ ity Div is ion
Email : DVIN_BE@fortworthtexas.gov I Ph one : 817 -3 92 -2674
FORT WORT H ---.....----
PRIME/OFF EROR/OWNER
COMPANY NAME:
PROJECT NAME:
City of Fo rt W o rth
Business Equity Utilization Form
Di sadvanta g e d Bus i n ess Enterpris e Uti l ization F orm (Appl i cable if Federally-Funded)
ATTACHMENT 1A
Page 1 of 4
PROJECT NUMBER: BID DAT E: City's B usiness Equity Goal: Offeror's Business Equity (or DBE)
D (Ch eck if add re ss ing DBE Go al) % Com m itm en t : %
C~eck all applicable boxes t?_de~cribe □ Not Certified
Pnme/Offe ror/Owne r's Class 1f1cat1o n: □MBE □wBE □DBE D Hu·B OvosB O section3
Certifying Agency: □NCTRCA ODtFW MSDC □TX DOT D wBcs □Other:
Ethnicity: □African American □Hispanic O caucasian □Asian □ Native American Gender: □Male □Female D Non-Binary
Defi n iti ons: Business Equity Fi rm: Certified MBE Minority Business Enterprise or WBE Women Business Enterprise DBE : Disadvantaged Business Enterprise
HUB : Historicall y Under U tilized Business VOSB : Veteran O wned Small Business Section 3 : Certified Housing U rban Development Vendors
ALL BUSINESS EQUITY FIRMS MUST BE CERTIFIED BEFORE CONTRACT AWARD
Failure to complete this form , in its entirety, and received by the Purchasing Division no later than 2:00 p.m. on the th ird City business day after bid opening, exclusive of bid opening date,
will result in the bid-being considered non-responsive to bid specifications. Exception: CFA, ICA, and CDBG projects, documents will be submitted to the City Project Manager if publicly
bid or to the Developer if private ly bid.
The undersigned Prime/Offerer agrees to enter into a formal agreement with the Business Equity firm(s) listed in this utilization schedule, conditioned upon execution of a contract with the
City of Fort Worth (Exception: Developer projects). The intentional and/or knowing misrepresentation of facts is grounds for consideration of disqualification and will result in the bid being
considered non-responsive to bid specifications .
B·usiness Equity firms listed toward meeting the project goa l must be located in· the City's marketplace at the time of bid or the business has a Significant · Business Presence in the
Marketplace. The marketplace is the C ity of Fort Worth including portions of Denton, Parker. Wise, and all of Tarrant, Dallas, and Johnson counties.
Certified means those Busi ness Equity Firms, loca ted withi n the Ma rketplace, ·that have been determined to be a bona-fide minority or women busine·ss enterprise by the
North Central Texas Regional Certification Agency (NCTRCA), Dallas/Fort Worth Minority Supplier Development Council (D/FW MSDC) and Women's Business Council-Southwest
(WBCS).
If hauling services are utilized, the Prim e/Offerer will be given credit as long as the Business Equity firm listed owns and operates at least one fully licensed and operational truck to be
used on the contract. The Business Eq uity firms may lease trucks from a nother Business Equity firm , including Business Equity owner-operated, and receive full Business Equity
credit. The Business Equity firm may lease trucks from non-Business Equity firms, including owner-operated, but will only receive credit for the fees and commissions earned by the
Business Equity as outlined in the lease agreement.
Fede rally -funded Proje cts (ONLY), Counting DBE Parti ci pation : If materials or supplies are obtained from a DBE manufacturer, count 100 percent of the cost of the materials or
supplies towards the goal. If the materia ls or supplies are purchased from a DBE regular dealer, count 60 percent of the cost of the materials and supplies toward the DBE goal. When
materia ls or s upplies are pu rchased fro m a DBE neither a manufacturer nor a regular dealer, count the entire amount of fees or commissions charged for assistance in the
procurement of the materials and supplies or fees or transportation charges for the delivery of the materials or supplies delivered to the job site. In all cases, the Prime/Offerer is
res ponsible to identify the am ounts to be used toward th e committed D BE goal. Note : For DBE Goals, 60 % of t he servi ces c ount towards the goal.
Effective 01/01/2021
Updated 03/24/2022
FORT WORTH ------.-----Bus iness Equity Uti lization Form
ATTACHMENT 1A
Page 2 of 4
Please note that only certified Business Equity firms w ill be counted to meet the Business Equity goal. Prime/0fferors are required to identify ALL subcontractors/suppliers ,
regardle ss of status ; i.e ., Business Equity firms and non-Business Eq uity fi rms. Prime/0fferors must identify by tier level all subcontractors/suppliers. Tier : means the level of
subcon tracting be low the Prime/0fferor i.e . a direct payment from the Prime/0fferor to a subcontractor is considered 1st tier, a payment by a subcontractor to its supplier is cons idered
2nd tier. Business Equity firms are to be listed before non-Business Equity fi rms. The Prime/0fferor is responsib le to provide proof of payment of a ll tiered sub-contractors/suppliers
iden tified as a Business Equity fir m and counting those dollars towards meeting the contract committed goal.
Certified Business Equity Prime/0fferor Contractors counting their self-performance towards meeting the contract goal, must be certifi ed within those NAICS commodity codes with a
certifying agency acceptable by the City of Fort Worth . Certified Business Equity Prime/0fferor counting se lf-performing services towards the goal , the service(s) to be performed
shou ld be listed first on the Utilization form.
Check this boxOit certified Prime Contractor services will be counting towards t he Business Equity contracting goa l. Please list serv ices first below.
Please list certified Business Equity firm names as listed on their certification , inc luding DBA names .
NAMES AND ADDRESSES OF TYPE O F SERVIC ES/SUPPLIES Spe ci fy Tier
CON T RACTORS/SUPPLIERS PROVIDED (NAICS Required) Name 1st ner
Business Name: Type of Servi ce/Supplies :
Address:
Phone: NAICS Code : Email :
Contact Person : $AMOUNT:
Business Name: Type of Serv ic e/Suppli es:
Add ress:
Phone: NAICS Code :
Email :
Contact Person : $AMOUNT:
Business Name: Type of Service/Supplies :
Address :
Phone : NAICS Code :
Email :
Contact Person : $AMOUNT :
Certification Agency
Certifi ed By:
[}>tFWMS DC
□NCTRCA
[JrxooT D wscs
G ther:
Ce rtifi ed By:
□oFWMSDC
□NCTRCA
□TXD0T Owscs
O0ther:
Certified By:
□o FWMSDC
□NCTRCA
□TXD0T O wBcs
Oother:
Gend er an d Eth nicity:
OMale D Female D Non-B inary
□African American D Hispanic
O Asian
O caucasian O Native
American
OMale D Female D Non -Binary
D African American □Hispanic
OAsian
Ocaucasian □Native
American
OMale D Female D Non-Binary
D African American
O Asian
Ocaucasian
□Hispanic
□Native
American
Effective 0 1/01/202 1
Updated 03/24/2022
FORT WORTH ------....----
Business Equity Utilization Form
Please include multiple copies of this page if needed to list all contractors and suppliers.
NAMES AND ADDRESSES OF TYPE OF SERVICES/SUPPLIES Specify Tier Certification Agency CONTRACTORS/SUPPLIERS PROVIDED (NAICS Required) Name 1st Tie r
Business Name:
Type of Service/Supplies : Certified By :
Address: OotFWMSDC
O NC T RCA
Phone: NAICS Code : □TXD 0 T OwBcs Email:
Oother:
Contact Person: $AMOUNT :
Business Name: Type of Serv ice /Supplies: Certified By :
Address: □o FWMS D C
□NCTRCA
Phone: NAICS Code : [J-rxo oT O wBcs Email:
Oother:
Contact Person: $AMOUNT :
Business Name: Type of Service/Supplies : Certi fie d By :
Address: O oFwMsoc
□NCTRC A
Phone: NAICS Code : □TXD0T OwBcs Email:
Oother:
$AMOUNT: Contact Person:
Business Name: Type of Serv ice /Supp lies : Certified By :
Address : OoFwMsoc
ONCTRCA
Phone: NAICS Code : BTX DOT O wBcs Email:
Other:
$AMOUNT : Contact Person:
ATTACH MENT 1A
Page 3 of4
Gender and Ethnicity:
O Ma le D Fem al e D Non -Bina ry
□African American □Hispanic
OAsian
Ocaucasian ONalive
American
O Male O Female ONon-Binary
□African American □Hispanic
□Asian
Ocaucasian □Native
American
OMale OFemale D Non-Binary
□African American □Hispanic
O Asian
Ocaucasian ONative
American
O Male O Female 0 Non-Binary
□Africa n American □Hispanic
OAsian
O caucasian O Native
American
Effective 01/01/2021
Updated 03/2412022
FORT WORTH ---.•. Business Equity Utilization Form
Total Dollar Amount of Certified Prime/Offeror Services towards contract goal
Total Dollar Amount of Business Equity (or DBE if applicable) Subcontractors/Suppliers
Total Dollar Amount of Non-Business Equity Subcontractors/Suppl iers
TOTAL DOLLAR AMOUNT OF CERTIFIED PRIME/ALL SUBCONTRACTORS/SUPPLIERS
$
$
$
$
ATTACH MENT 1A
Page 4 of 4
The Prime/Offerer will not make additions , deletions, or substitutions to this certified list w ithout the prior approval of t he Business Equ ity Division
through the submittal of a Request for Approval of Change/Addition online. Any unjus t ified change or deleti on shall be a material breach of
cont ract and may result in debarmen t in accord with the procedures outl ined in the ordinance. The Prime/Offerer shall subm it a detailed explanation of
how the requested change/addition or deletion will affect the committed Bus iness Equity goal. If the detail exp lanat ion is no t subm itted , it will affect
the final compliance determination .
By affixing a signature to th is form , the Prime/Offeror further agrees to provide , directly to the City upon request, complete and accu rate information
regarding actual work performed by all subcontractors , including non-Business Equ ity fi rms . The Prime/Offerer also agrees to allow an audit and/or
exam ination of any books , records and files held by thei r company. The Prime/Offeror agrees to allow the transm ission of interviews w it h owners ,
principals , officers , employees and applicab le subcontractors/suppliers participating on the contract that w ill substant iate the actual work
performed by the Business Equ ity firms on this contract , by an authorized officer or employee of the City. A Prime/Offerer who intentionally and/o r
knowingly misrepresents material facts shall be Debarred for a period of time of not less than three (3) years .
Authorized Signature
Title
Company Name
Address
City/State/Zip Code
Department of Divers ity and Inclus ion -Busi ness Equity Divisio n
Email : DVIN_BEOffice@fortworthtexas.gov
Ph : 817-3 92 -2 674
Printed Signature
Contact Name and Title (if different)
Phone Number
Email Address
Date
Effective 01/01/2021
Upda ted 03/24/2022
FORT WORTH
~ City of Fort Worth
Business Equity (M/WBE) Specifications
Prime Contractor Waiver Form
ATTACHMENT 18
Page 1 of 1
OFFE ROR COMPAN Y NAM E : C heck app licable bl ock to descri be Prime
PROJECT NAM E : l j MNVBE l J NON-MWBE
BID DAT E
C ity's MBE Project Goal : I Offe ro r's MBE P roject Commitment: P RO JE CT NUMB E R
% %
If both answers to this form are YES , do not complete ATTACHMENT 1C (Good Faith Effort Form). All questions on
th is form m ust be comp leted and a de tailed explanation provided, if applicable . If the answer to either question is
NO , the n you must comp lete ATTACHMENT 1C. This form is only applicable if b.oth answers are yes .
Failure to complete th is form in its enti rety and be received by the Purchasing D iv ision no later than 2 :00
p.m ., on the second City business day afte r bid ope ning , exclus ive of the bid opening date, will result In
the bid being considered non-respons ive to b id specification s.
Will you perform this enti re contract without subcontractors? □ YES
If yes, please provide a detailed explanation that proves based on the size and scope of this □ NO project , this is your norma l business practice and provide an opera ti onal profile of your business .
Will you perform this entire contract without suppliers? □ YES
If yes, please provide a detailed explanation that proves based on the size and scope of this LJ project, this is your norma l business practice and provide an inventory profile of your business . NO
The Offerer further ag rees to provide, directly to the City upon reque st, complete and accurate information
regarding actual work performed by all subcontra ctors, includi ng certified M/WBE(s) on this co ntract, the payment
the reof and any proposed changes to the original M/WBE(s) arrangements submitted with this bid. The Offerer
also agrees to all ow an audit and/or exami natio n of any books , records and files held by their company that will
substantiate the actual work performed by the M/WBEs on th is contract , by an authorized officer or
em plo yee of the City. Any intenti onal and/o r knowing misrepresentation of facts will be grounds for
term in ating the contract or debarment from City work for a period of not less than three (3) years and for
in itiati ng act ion under Fede ra l, State or Local la ws concerning fa lse statements . Any failure to comply with th is
ord inance creates a materia l breach of contract and may result in a determination of an irresponsible Offeror
and barred fro m partici pati ng in City work fo r a period of t ime not less t han o ne (1) year.
Authorized Signatu re
Ti tle
Company Name
Address
City/State/Zi p
Business Equ ity Division
Email : DVIN _BEOffice@fortworthtexas .gov Phon e:
(817) 392 -2674
Printed Signature
Contact Name (if differe nt)
Phone Number Fa x Number
Email Address
Da te
Rev . 3 /13/2 022
FORT WORTH @
~
PRIME /OFFEROR
COMPANY NAME:
PROJECT NAME:
Business Equity Goal :
%
City of Fort Worth
Business Equity Division
Good Faith Effort Form
I Offeror's Business Equity Goal Commitment:
%
ATTACHMENT1C
Page 1 of 4
Check appli cabl e box to describe
Pri me/Offeror's Certification D Business Equity I DI Non_-Bu~iness
Finn Equity Firm
BID DATE
PROJECT NUMBER
If the Offeror did not meet or exceed the Business Equity Goal for this project, the Prime/Offeror must complete
this form.
If the Prime/Offeror's method of compliance with the Business Equity Goal is based
upon demonstration of a "Good Faith Effort", the Prime/Offeror will have the burden of
correctly and accurately preparing and submitting the documentation required by the
City. Compliance with each item, 1 thru 10 below, shall satisfy the Good Faith Effort
requirement absent proof of fraud, intentional and/or knowing misrepresentation of the facts
or intentional discrimination by the Prime/Offeror.
Failure to complete this form , in its entirety with supporting documentation, and received by the
Purchasing Division no later than 2:00 p.m. on the third City business day after bid opening , exclusive
of bid opening date, will result in the bid being considered non-responsive to bid specifications .
Exception: CFA , ICA, and CDBG projects, documents will be submitted to the City Project Manager if
publicly bid or to the Developer if privately bid.
1.) Please list each and every subcontracting and/or supplier opportunity for the completion of this
project, regardless of whether it is to be provided by a Business Equity firm or non-Business
Equity firm . (DO NOT LIST NAMES OF FIRMS). On all projects , the Prime/Offeror must list each
subcontracting and or supplier opportunity regardless of tier.
(Use additional sheets, if necessary)
List of Subcontracting Opportunities List of Supplier Opportunities
Effective 03 /15/2022
ATTACHMENT 1C
Page 2 of 4
2 .) Obtain a current (not more than two (2) months old from the bid open date) list of Business Equity
subcontractors and/or suppliers from the City's Business Equity Divis i on .
OYes
□ No
Date of Listing ______ _
3 .) Did you solicit bids from Business Equity firms , within the subcontracti ng and/or suppl ier areas
previously listed, at least ten calendar days prior to bid opening by telephone, exclusive of the day the
bids are opened?
D Yes (If yes, attach list to include name of Business Equ ity fi r m, pers on contacted, phone number and dat e and time of contact.)
□No
4.) Did you solicit bids from Business Equity firms , within the subcontracting and/or supplier areas
previously listed, at least ten calendar days prior to bid opening by fax , exclusive of the day the bids are
opened?
OYes (if yes, attach 11st to include name of Business Equ ity firm , fax number and d ate and time of contact. In addition, If the fax Is
returned as undel iverable, then that "undeliverable confirmation" received must be printed di rectly from the facsimile for
proper documentation. Failure to submit confirmation and/or "unde liverable confirmation" documentation may render the
GFE non -responsive.)
5.) Did you solicit bids from Business Equity firms, within the subcontracting and/or supplier areas
previously listed, at least ten calendar days prior to bid opening by email , exclusive of the day the bids are
opened? D Yes (If yes , attach email confirmation to include~ of Bus i ness Equity firm , date and time . in addition , if an
email Is returned as undeliverable, then that "undeliverable message" rece i pt must be printed directly from the
email system for proper documentation. Failure to submit confirmation and/or "undeliverable message"
documentation may render the GFE non-responsive .)
NOTE: The three methods Identified above are acceptable for soliciting bids, and each selected
method must be applied to the applicable contract. The Prime/Offeror must document that either at
least two attempts were made using two of the three methods or that at least one successful contact was
made using one of the three methods in order to deemed responsive to the Good Faith Effort requirement.
NOTE: The Prime/0fferor must contact the entire Business Equity list specific to each
subcontracting and supplier opportunity to be in compliance with questions 3 thru 5.
6.) Did you provide plans and specifications to potential Business Equity firms?
OYes
0 No
7.) Did you provide the information regarding the location of plans and specifications in order to assist
the Business Equity firms?
OYes
□No
Effective 03/15 /2022
ATTACHMENT 1C
Page 3 of 4
8.) Did you prepare a quotation for the Business Equity firms to bid on goods/services specific to their
skill set?
D Yes (If yes, attach all copies of quotations.)
□No
9.) Was the contact information on any of the listings not valid?
□ Y (If yes, attach the Information that was not valid in order for the Business Equity Division to address
es the corrections needed.)
□ No
10.) Submit documentation if Business Equity firms quotes were rejected. The documentation submitted
should be in the firms forms of an affidavit, include a detailed explanation of why the Business Equity firms
was rejected and any supporting documentation the Prime/Offeror wishes to be considered by the City. In the
event of a bona fide dispute concerning quotes, the Prime/Offeror will provide for confidential in-camera
access to an inspection of any relevant documentation by City personnel.
(Please use additional sheets, if necessary, and attach.)
Company Name Telephone Contact Person Scope of Work Reason for Rejection
ADDITIONAL INFORMATION:
Please provide additional information you feel will further explain your good and honest efforts to obtain
Business Equity firm participation on this project.
The Prime/Offerer further agrees to provide, directly to the City upon request,
complete and accurate information regarding actual work performed on this contract,
the payment thereof and any proposed changes to the original arrangements submitted
with this bid. The Prime/Offeror also agrees to allow an audit and/or examination of any
books, records and files held by their company that will substantiate the actual work
performed on this contract, by an authorized officer or employee of the City.
A Prime/Offeror who intentionally and/or knowingly misrepresents material facts shall be
Debarred for a period of time of not less than three (3} years.
Effective 03/15/2022
ATTACHMENT 1C
Page 4 of 4
The undersigned certifies that the information provided and the Business Equity firms
listed was/were contacted in good faith. It is understood that any Business Equity firms
listed in Attachment 1 C will be contacted and the reasons for not using them will be
verified by the City's Business Equity Division.
Authorized Signature
Title
Company Name
Address
City/State/Zip
Business Equity Division
Email : DVIN_BEOffice@fortworthtexas.gov
Phone : (817) 392-2674
Printed Signature
Contact Name and Title (if different)
Phone Number
Email Address
Date
Effective 03/15/2022
CITY OF F ORT W ORTH
M/WBE Join t Ve nture E ligibility F orm
A ll q11 estio11s 11111 st be answered; use "NIA " if 11ot applicable.
Joi nt Venture
Page 1 of 3
Na me of City proj ect:------:-:---:-----=-------,---,-----,------,---------------
A j oin t ve nture for m mu st be comp leted on ea ch project
RFP/Bid/Purchas ing Number: ___________ _
1. Joi nt ve ntur e info rmatio n:
Joint Venture Name:
Joint Venture Address :
(If applicable)
Telephone: Fa csimile : E-mail addre ss:
Cellular:
Identi fy the firms that comprise the joint venture:
Please attach extra sheets if additional space is required to provide detailed exp lanations of work lo be performed by each firm comprising the
joint venture
M/WBE fi rm I No n-M/WBE firm I
na m e: na me :
Bu si ness Addre ss: Bu siness Address:
City, State, Zip : City, State, Zip:
Telephon e Facsi mile E-mail Te leph one Facsim ile
Cellular Cellula r
Ce rtifi catio n Status: E-m ail addres s
Name of Certifyi ng Agency:
2 S cop e o wor per orm e f k ,v e om en ure : db th J . t V t
Des crib e th e scop e of w ork of th e M/W BE: Describ e the sco pe of wo rk of th e non-M/WBE:
Rev . 2/13/19
Joint Ve nture
Page 2 of 3
3. What is the percentage of M/WBE participation on this joint venture that you wi sh to b e counted toward
meeting the project goal?
4. Attach a copy of the joint venture ag re ement.
5. List components of ownership of joint venture: (Do 1101 co mple1e if !his i11for111alio11 is descl'ib ed i11 joi111 venture
~ aJ?ree111e11/
Profit and loss sharing :
Capital contrib utions, including
equipment:
Other appli cab le ownership interests:
6. Identify by name, race, sex and firm those individuals (with titl es) who are r esponsible for the day-to-day
management and decision making of the joint venture:
Fi na ncial deci sio ns
(to include Account Payable and Receivable):
Management d ecisions :
a. Estimating
---b . Marketin g and Sa les
---·--------
C. Hiri ng and Firing of management
personnel
----d. P urchasing of maj or e qu ipment
a nd /or suppl ies
Sup ervi si on of fie ld op eration s
The City 's Business Equity Divis ion will review your joint ventu re submission and will have final
approval of the M/WBE percentage applied toward the goal for the project listed on this form .
NOTE:
From and after the date of project award , if any of the participants , the individually defined scopes of work or
the dollar amounts/perce ntages change from the originally approved information , then the part icipants must
inform the City's Business Equity Division immed iately fo r approval. Any unjustified change or
deletion shall be a material breach of contract and may re sult in debarment in accord with the procedures
outlined in the City's Bus iness Equity Ordinance 25165-10-2021 .
Rev. 2/13/19
Joint Venture
Paae 3 of 3
AFFID AVIT
The undersigned affirms that the foregoing statements are trne and correct and include all material information
necessa1y to identify and explain the terms and operation of the joint venture . Furthermore, the undersigned shall
agree to provide to the joint venture the stated scope of work, decision-making responsibilities and payments
herein .
The City also reserves the right to request any addi tion a l infmmation deemed nece ssaty to dete1mine if the joint
venture is eligible. Failure to cooperate and/or provide requested information within the time specified is grounds
for te1mination of the eligibility process.
The undersigned agree to permit audits, interviews with owners and examination of the books, records and files
of the joint venture by any authorized representatives of the City of Fort Worth. Failure to comply with this
provision shall result in the termination of any contract, which may be awa rded under the provisions of this joint
venture's eligibility and may initiate action under Federal, State and/or Local l a ws/ordinances concerning false
statements or willful misrepresentation of facts.
Name ofMBE finn Name ofn on -MB E fin n
Printed Name of Own er Printed Na me of Own er
Signature of Own er Si gnature of Owner
Printed Name of Owner Pri nted Na me of Owner
Si gnature of Own er Signature of Own er
Title Title
Date Date
Notarization
State of __________________ County of ______________ _
On this _____________ day of _______ ~ 20 __ , before me appeared
_____________________ and ____________________ _
to me personally known and who, being duly sworn, did execute the foregoing affidavit and did state that they were
properly authorized to execute this affidavit and did so as their free act and deed.
Nota1y Public _______________________ _
Print Name
Nota1y Public _______________________ _
Signature
Commission Expires _______________________ _
Office of Business Diversity
Email: mwbeoffice@fo1two1thtexas.gov
Phone: (817) 392-2674 Rev . 2/13/19
GC-6.07 Wage Rates
2013 Prevailing Wage Rates
(Heavy & Highway Construction Projects)
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIF ICATION DOCUMENTS
Revised July I , 2011
2022 WATER SERVI CE LEAK
REPAIR CONTRACT
City Project No . I 04552
2013 PREVAILING WAGE RATES
(Heavy and Highway Construction Projects)
CLASSIF ICATION DESCRIPTION Wage Rate
Asphalt Distributor Operator $ 15 .32
Asphalt Paving Machine Operator $ 13.99
Asphalt Raker $ 12.69
Broom or Sweeper Operator $ 11.74
Concrete Finisher, Paving and Structures $ 14.12
Concrete Pavement Finish i ng Machine Operator $ 16 .05
Concrete Saw Operator $ 14.48
Crane Operator, Hydraulic 80 ton s or less $ 18.12
Crane Operator, Lattice Boom 80 Ton s or Less $ 17 .27
Crane Operator, Lattice Boom Over 80 Tons $ 20.52
Crawler Tractor Operator $ 14.07
Electrician $ 19.80
Excavator Operator, 50,000 pounds or less $ 17.19
Excavator Operator, Over 50,000 pounds $ 16 .99
Flagger $ 10.06
Form Builder/Setter, Structures $ 13 .84
Form Setter, Paving & Curb $ 13.16
Foundation Drill Operator, Crawler Mounted $ 17 .99
Foundation Drill Operator, Truck Mounted $ 21.07
Front End Loader Operator, 3 CY or Less $ 13.69
Front End Loader Operator, Over 3 CY $ 14.72
Laborer, Common $ 10.72
Laborer, Utility $ 12 .32
Loader/Backhoe Operator $ 15 .18
Mechanic $ 17 .68
Milling Machine Operator $ 14 .32
Motor Grader Operator, Fine Grade $ 17 .19
Motor Grader Opera t or, Rough $ 16.02
Off Road Hauler $ 12.25
Pavement Marking Machine Operator $ 13.63
Pipelayer $ 13.24
Reclaimer/Pulverizer Operator $ 11 .01
Reinforcing Steel Worker $ 16 .18
Roller Operator, Asphalt $ 13.08
Roller Operator, Other $ 11.51
Scraper Operator $ 12 .96
Servicer $ 14.58
Small Slipform Machine Operator $ 15.96
Spreader Box Operator $ 14 .73
Truck Driver Lowboy-Float $ 16.24
Truck Driver Transit-Mix $ 14 .14
Truck Driver, Single Axle $ 12 .31
Truck Driver, Single or Tandem Axle Dump Truck $ 12 .62
Truck Driver, Tandem Axle Tractor with Semi Trailer $ 12.86
Welder $ 14.84
Work Zone Barricade Servicer $ 11.68
The Davis-Bacon Act prevailing wage rates shown for Heavy and Highway construction projects were determined by
the United States Department of Labor and current as of September 2013 . The titles and descriptions for the
classifications listed are detailed in the AGC of Texas' Standard Job Classificat ions and Descriptions for Highway ,
Heavy, Utilities , and Industrial Construction in Texas .
Page 1 of 1
GC-6.09 Permits and Utilities
THIS PAGE LEFT INTENTIONALLY BLANK
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised Jul y I , 20 I I
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No . I 04552
GC-6.24 Nondiscrimination
THIS PAGE LEFT INTENTIONALLY BLANK
CITY OF FORT WORTH
ST AND ARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July I , 20 I I
2022 WATER SER V1 CE LEAK
REPAIR CONTRACT
City Project No. I 04552
GR-01 60 00 Product Requirements
THIS PAGE LEFT INTENTIONALLY BLANK
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised July I , 2011
2022 WATER SERVICE LEAK
REPAIR CONTRACT
City Project No . I 04552