HomeMy WebLinkAboutOrdinance 6244 ORDINANCE NO.
AN ORDINANCE APPROVING AND ADOPTING ESTIMATES OF THE COST OF IMPROVE-
MENTS AND OF AMOUNTS TO BE ASSESSED FOR IMPROVEMENTS ON A PORTION OF
BLACK TONE DRIVE _
AND PORTIONS OF SUNDRY OTHER STREETS, AVENUES AND PUBLIC PLACES IN THE
CITY OF FORT WORTH, TEXAS; FIXING TIME AND PLACE FOR HEARING TO THE
OWNERS OF ABUTTING PROPERTY AND TO ALL OTHERS INTERESTED; DIRECTING
THE CITY SECRETARY TO GIVE NOTICE OF SUCH HEARING; AND DIRECTING THE
CITY SECRETARY TO ENGROSS AND ENROLL THIS ORDINANCE BY COPYING THE
CAPTION OF SAME IN THE MINUTE BOOK OF THE CITY COUNCIL AND BY FILLING
THE COMPLETE ORDINANCE IN THE APPROPRIATE ORDINANCE RECORDS OF THE
CITY; AND PROVIDING AN EFFECTIVE DATE.
WHEREAS, the City Council of the City of Fort Worth, Texas, has heretofore ordered that each of the
hereinafter described portions of streets, avenues and public places in the City of Fort Worth, Texas, be im-
proved by raising, grading and filling same and by constructing thereon the following, to-wit:
UNIT l: Blackstone Drive From Churchill Road to Isbell Road,, known and
designated as Unit 1, Project No. 104-24000-198,
to be improved by constructing a six-inch thick
hot-mix asphaltic concrete pavement on a six-
inch thick cement stabilized subgrade, seven-
inch high concrete curb and eighteen-inch wide
concrete gutter, so that the finished roadway
will be thirty feet wide and by constructing
six-inch thick concrete driveways and four-foot
wide concrete sidewalks where specified.
UNIT 2: Tidwell Drive From Banks Street to Springer Street, known and
designated as Unit 2, Project No. 104-24000-195,
to be improved by constructing a six-inch thick
hot-mix asphaltic concrete pavement on a six-inch
thick cement stabilized subgrade, seven-inch high
concrete curb and eighteen-inch wide concrete
gutter, so that the finished roadway will be
thirty feet wide and by constructing six-inch
thick concrete driveways where specified.
UNIT 3: Quail Trail From Shenna Boulevard to Ohio Garden Road, known
and designated as Unit 3, Project No. 104-24000-198,
to be improved by constructing a six-inch thick
hot-mix asphaltic concrete pavement on a six-inch
thick cement stabilized subgrade, seven-inch high
concrete curb and eighteen-inch wide concrete
gutter, so that the finished roadway will be
thirty feet wide and by constructing six-inch
thick driveways where specified.
......................................................................................................
UNIT 4, Robinson Street From NW. 23rd Street to NW. 24th Street, known
and designated as Unit 4, Project No. 104-24000-198:
to be improved by constructing a six-inch thick
hot-mix asphaltic concrete pavement on a six-inch
thick lime stabilized subgrade, seven-inch high
concrete curb and eighteen-inch wide concrete
gutter, so that the finished roadway will be
thirty feet wide and by constructing six-inch
thick concrete driveways and four -foot wide
concrete sidewalk where specified.
UNIT 5,1 Robinson Street From NW. 24th Street to NW. 26th Street, known
and designated as Unit 5, Project No. 104-24000-198:
to be improved by constructing a six-inch thick
hot-mix asphaltic concrete pavement on a six-inch
thick lime stabilized subgrade, seven-inch high
concrete curb and eighteen-inch wide concrete
gutter, so that the finished roadway will be
thirty feet wide and by constructing six-inch
thick concrete driveways and four-foot wide
concrete sidewalk where specified.
UNIT 6, McCandless Street From NW. Loraine Street to NW. 32nd Street,
known and designated as Unit 6, Project No.
104-24000-198: to be improved by constructing
a six-inch thick hot-mix asphaltic concrete
pavement on a six-inch thick lime stabilized
subgrade, seven-inch high curb and eighteen-inch
concrete gutter, so that the finished roadway
will be thirty feet wide and by constructing six-
inch thick concrete driveways and four-foot wide
concrete sidewalks where specified.
UNIT 7, 29th Street From McCandless Street to Titus Street, known
and designated as Unit 7, Project No. 104-24000-198:
to be improved by constructing a six-inch thick
hot-mix asphaltic concrete pavement on a six-inch
thick cement stabilized subgrade, seven-inch high
concrete curb and eighteen-inch wide concrete
gutter, so that the finished roadway will be
thirty feet wide and by constructing six-inch
thick concrete driveways and four-foot wide
concrete sidewalk where specified.
UNIT 8, NW. Loraine Street From Titus Street to Sherman Street, known and
designated as Unit 8, Project No. 104-24000-198:
to be improved by constructing a six-inch thick
hot-mix asphaltic concrete pavement on a six-inch
thick cement stabilized subgrade, seven-inch high
concrete curb and eighteen inch wide concrete
gutter, so that the finished roadway will be
thirty feet wide and by constructing six-inch
thick concrete driveways where specified.
together with concrete curbs, gutters, driveways and incidentals to such improvements
on proper grade and line where same are not already so constructed, together with storm
sewers and drains and other necessary incidentals and appurtenances; all of said im-
provements to be constructed as and where shown on the Plans and in strict accordance
with the Plans and Specifications therefor; contract therefore has been made and
entered into with S.R.O. ASPHALT. INC. , ARLINGTON, TEXAS
and
WHEREAS, the City Council of the City of Fort Worth, Texas, has caused the Public
Works Director to prepare and file estimates of the cost of such improvements and
estimates of the amount per front foot proposed to be assessed against abutting property
and the owners thereof, and such estimates have been examined, NOW, THEREFORE,
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH, TEXAS, THAT:
I.
Such estimates be, and they are hereby adopted and approved.
II.
It is hereby found and determined that the cost of improvements on each portion of
streets, avenues, and public places hereinafter described , with the amount or amounts
per front foot proposed to be assessed for such improvements against abutting pro-
perty and the owners thereof, are as follows, to-wit:
UNIT 1: Blackstone Drive From Churchill Road to Isbell Road ,
known and designated as Unit 1,
Project No. 104-24000-198.
The estimated cost of improvements is 37-229.23 —; the estimated amount
per front foot to be assessed against abutting property and the owners thereof for
concrete curb and gutter is 2.44 the estimated amount per front foot to
be assessed against abutting property and the owners thereof for pavement is $ 5.65
the estimated amount per front foot to be assessed against abutting property and the
owners thereof for 4 foot wide concrete sidewalk is $ 2.67 ; the estimated
amount per square foot to be assessed against abutting property and the owners thereof for
six-inch thick concrete driveway is $ .30 per square foot; the total
estimated amount per front foot to be assessed against abutting property and the owners
thereof is $ 10, 76 plus the cost incurred for concrete driveway construction
where specified.
A hearing be given and held by and before the City Council of t'e City
of Fort o° th, Texas, to all owning or claiming any property abutting upon said
portions of highways, streets, avenues and public places , as well as to all,
owning or claiming any interest in any such property. Such hearing shall be
given and held on the __2,_ day of 19_,ZQ_._, at
in the Council Chamber in the City Hall in the City of Fort Worth, Texas , and
the City Secretary is hereby directed to give or cause to be given notice of the
time and place of such hearing and of other matters and facts in accordance with
the to and provisions of an Act passed at the First Called Session of the
Fortieth Legislature of the State of Texas , and known as Chapter 106 of the Acts
of said Session, now being known as Article 1105b of Vernon's Texas Civil Statutes
as amended by Acts 1967, 60th Legislature, Page 365, Chapter 176, Section 1,
emergency effective May 12, 1967. Such notice shall be by advertisement inserted
at least three (3) times in a newspaper published in the City of Fort Worth,
Texas , the first publication to be imnade at least, twenty-one (21) days before
the date of said hearing. Said notice shall comply with and be in accordance with
the terms and provisions of said Act as amendecl. Ilie City Secretary is further
directed to give or cause to be given personal notice of the time and place of
such hearing to all owning or claiming any property abutting on said portions of
highways, streets, avenues and public places , as well as to all owning or claiming
any interest in any such property. Such personal notice shall be in writing and
shall be given, or caused to be given by the City Secretary by depositing such
written notice in the United States Mail at least fourteen (14) days before the
date of the hearing, postage prepaid, in envelopes addressed to all persons
o%niing or claiming any interest in the respective properties abutting the high-
ways, streets , avenues and public places or portions thereof to be improved, as
the names of such persons are shown on the current rendered tax roLls of the City
of Fort Worth and at the; addresses so shown, or if the name of such respective
owners do not appear on such rendered tax rolls, then address to such owners as
their names are shown on the current unrendered tax rolls of the City of Fort Worth
at the addresses shown thereon. In those cases in which an owner of property
abutting a highway, street, avenue or public place or portion or portions there-
of which is to be improved is listed as %nknmen" on the then current City of
Fort Worth tax rolls, or the name of an owner is shown an the City of Fort Worth
tax rolls 'but no address for such owner is shown, no notice need ba mailed. In
those cases where the owner is shown to be an estate, the mailed notice may be
addressed to such estate. In this connection, the City Secretary shall prepare
and file or cause to be p •ejmred and filed with these proceedings a list of the
properties to be assessed, the names of those persons owning or claiming any
interest in said properties to whom the notice was mailed, together with the last
known addresses determined as aforesaid of the respective owners and those per-,,
sons owning or claiming any interest in said property.
. he City Secretary shall certify that each of the parties in said list whose
address is shown on the then current rendered or unrendered tax rolls of the City
of Fort Worth was mailed a copy of the notice of hearing and shall further certify
the date or dates on which said notice was mailed. A copy of each notice shall be
attached to such certificate. The certificate of the City Secretary will be con.,
clusive evidence of the facts therein recited,,
xzv.
This ordinance shall take effect and be in full force and effect from
and after the date of its passage.
PASSED AND APPROVED THIS DAY
APPROVED AS TO FORM AND LEGALITY:
ze7-"flo
City Attorney
UNIT 2: Tidwell Drive From Banks Street to Springer Street,
known and designated as Unit 2, Project
No. 104-24000-198.
The estimated cost of improvements is $ 8,474.68 ; the estimated amount
per front foot to be assessed against abutting property and the owners thereof for
concrete curb and gutter is $ 2.44 ; the estimated amount per front foot to be
assessed against abutting property and the owners thereof for pavement is $ 5_ 99 ;
the estimated amount per front foot to be assessed against abutting property and
the owners thereof for -0- wide concrete sidewalk is $ -0- ; the estimated
amount per square foot to be assessed against abutting property and the owners
thereof for 6-inch thick concrete driveway is $ .80 per square foot; the total
estimated amount per front foot to be assessed against abutting property and the
owners thereof is $-8.03 plus the cost incurred for concrete driveway con-
struction where specified.
UNIT 3: Quail Trail From Shenna Boulevard to Ohio Garden
Road, known and designated as Unit
3, Project No. 104-24000-198.
The estimated cost of improvements is $ 19047-4S ; the estimated amount
per front foot to be assessed against abutting property and the owners thereof for
concrete curb and gutter is $ 2_44 '; the estimated amount per front foot to be
assessed against abutting property and the owners thereof for pavement is $5_91
the estimated amount per front foot to be assessed against abutting property and
the owners thereof for -0- wide concrete sidewalk is $ -0- ; the estimated
amount per square foot to be assessed against abutting property and the owners
thereof for 6-inch thick concrete driveway is $ .80 per square foot; the total
estimated amount per front foot to be assessed against abutting property and the
owners thereof is $ 8.35 plus the cost incurred for concrete driveway con-
struction where specified.
UNIT 4: Robinson Street From NW. 23rd Street to NW. 24th Street,
known and designated as Unit 4, Project
No. 104-24000-198.
The estimated cost of improvements is $ g,894,60 ; the estimated amount
per front foot to be assessed against abutting property and the owners thereof for
concrete curb and gutter is $ 2,44 the estimated amount per front foot to be
assessed against abutting property and the owners thereof for pavement is $ 5.60
the estimated amount per front foot to be assessed against abutting property and
the owners thereof for 4 of wide concrete sidewalk is $ 2.67 ; the estimated
amount per square foot to be assessed against abutting property and the owners
thereof for 6-inch thick concrete driveway is $ 80 per square foot; the total
estimated amount per front foot to be assessed against abutting property and the
owners thereof is $ 10_ 71 , plus the cost incurred for concrete driveway con-
struction where specified.
UNIT 5: Robinson Street From NW. 24th Street to NW. 26th Street,
known and designated as Unit 5, Project No.
104-24000-198.
The estimated cost of improvements is $ 21.366.95 the estimated amount
per front foot to be assessed against abutting property and the owners thereof for
concrete curb and gutter is $-2.44 ; the estimated amount per front foot to be
assessed against abutting property and the owners thereof for pavement is $ 5.91
the estimated amount per front foot to be assessed against abutting property and
the owners thereof for 4 foot wide concrete sidewalk is $ 2.67 ; the estimated
amount per square foot to be assessed against abutting property and the owners
thereof for 6-inch thick concrete driveway is $ 80 per square foot; the total
estimated amount per front foot to be assessed against abutting property and the
owners thereof is $_11,02 plus the cost incurred for concrete driveway con-
struction where specified.
UNIT 6: McCandless Street From NW. Loraine Street to NW. 32nd Street,
known and designated as Unit 6, Project No.
104-24000-198.
The estimated cost of improvements is $_ 330519.75 the estimated amount
per front foot to be assessed against abutting property and the owners thereof for
concrete curb and gutter is $-2.44 ; the estimated amount per front foot to be
assessed against abutting property and the owners thereof for pavement is $ 5.64
the estimated amount per front foot to be assessed against abutting property and
the owners thereof for -0- wide concrete sidewalk is $ -0- ; the estimated
amount per square foot to be assessed against abutting property and the owners
thereof for 6-inch thick concrete driveway is $ .80 per square foot; the total
estimated amount per front foot to be assessed against abutting property and the
owners thereof is $-8.08 plus the cost incurred for concrete driveway con-
struction where specified.
UNIT 7: NW. 29th Street From McCandless Street to Titus Street,
known and Designated as Unit 7, Project
No. 104-24000-198.
The estimated cost of improvements is $ 15.047,45 the estimated amount
per front foot to be assessed against abutting property and the owners thereof for
concrete curb and gutter is $ 2.44 ; the estimated amount per front foot to be
assessed against abutting property and the owners thereof for pavement is $ 5,99
the estimated amount per front foot to be assessed against abutting property and
the owners thereof for -0- wide concrete sidewalk is $ -0- ; the estimated
amount per square foot to be assessed against abutting property and the owners
thereof for 6-inch thick concrete driveway is $ .80 per square foot; the total
estimated amount per front foot to be assessed against abutting property and the
owners thereof is $ 8,43 plus the cost incurred for concrete driveway con-
struction where specified.
UNIT 8: NW. Loraine Street From Titus Street to Sherman Street,
known and designated as Unit 8,
Project No. 104-24000-198
The estimated cost of improvements is $ _16,683.70 ; the estimated amount
per front foot to be assessed against abutting property and the owners thereof for
concrete curb and gutter is $ 2.44 the estimated amount per front foot to be
assessed against abutting property and the owners thereof for pavement is $ 5,80
the estimated amount per front foot to be assessed against abutting property and
the owners thereof for -0- wide concrete sidewalk is $ -0- ; the estimated
amount per square foot to be assessed against abutting property and the owners
thereof for 6-inch thick concrete driveway is $_ .80 per square foot; the total
estimated amount per front foot to be assessed against abutting property and the
owners thereof is $ 8.24 plus the cost incurred for concrete driveway con-
struction where specified.
The estimated cos of improvements is $ the estimated amount
L 1
per front foot to b assessed against abutting property and the owners thereof for
I
concrete curb and gut r is $ the estimated amount per front foot to be
j
assessed estimated
property and the owners thereof for pavement is $
the estimated amount per FTont foot to be assessed against abutting property and
the owners thereof for wide concrete sidewalk is $ ; the estimated
amount per square foot to be 'Assessed against abutting property and the owners
thereof for 6-inch thick concrete driveway is $_ per square foot; the total
estimated amount per front foot to,, be assessed against abutting property and the
owners thereof is $ plu S"""the cost incurred for concrete driveway con-
struction where specified.
The estimated cost of improvements is the estimated amount
per front foot to be assessed against abutting property and tie owners thereof for
concrete curb and gutter is $ the estimated amount""'kr front foot to be
assessed against abutting property and the owners thereof for pavement is $
the estimated amount per front foot to be assessed against abuttin'k, property and
the owners thereof for wide concrete sidewalk is he estimated
amount per square foot to be assessed against abutting property and th 6,,,owners
thereof for 6-inch thick concrete driveway is $ per square foot;"",t,he total
estimated amount per front foot to be assessed against abutting property atn d, the
owner's thereof is $ plus the cost incurred for concrete driveway 6qn-
struction where specified.
Q City of Fort Worth, Texas
Mayor and Council Communication,
DATE AUEREN E suu irrn Kard of Contract _ Assessment Mot
2;9/70 71663 1 I
Council action is requested on the ro ct described below.
projectUsIliktion,
Nature of Work: Assessment Paving at S Locations on the Northwest Side.
Roadway
Unit Street Limits Width R.041
1 Blackstone Drive Churchill Drive to Isbell Rod 30 feet 5 0 feet
I
2 Tidwell Drive Banks Street to Springer Street 38 feet 50 feet
3 Quail Trail Shenna Boulevard to Ohio
Garden ,cued 30 feet 50 feet
4 Robinson Street N.W. 23rd Street to N.W.
24th Street 30 fee's 60 feet
5 Robinson Street N.W. 24th Street to N.W.
26th Street 30 feet 60 feet
6 McCandless Street N04 Loraine Street to
W.W. 32nd Street 30 feet, 60 feint
7 N.W. 29th Street McCan4less Street to
Sherman Street, 30 feet 60 feet
8 N.W. Loraine Titus Street to Sherman Street 30 feet 60 feet
Paving an doses units was petitioned with the exception of Robinson Street
thich was initiated as the result of a poll card survey.
.
Suuluuuui cup _of I Bids
The following bids have been received-
Bidder ,u uunt Bid,
S.I .C . Asphalt, Inc. , Klington, Terns $146,310.75
Austin Gaud Company 1.54,830.80
Ernest Lod 1`701,319.25
Texas 8f tuulfthic Company a 172,491.25
General Construction Clump nyr , 18C ,999.54
Bids ceived; January 15, 19 70
Working Days Allowed: 145
J/'Na
DATE REFERENCE SUBJECT: Award of Contract Assessment PAGE
NUMBER Paving at 8 Locations on the Northwest 2 2
2/9/70 C-16,63 fide of —
Project Cost and Financin
Based on the low bid., approximately ately $68,621.84 will be assessed against
abutting property owners. The coat to the City-at-large will be approximately
$92,320, including engineering expense. A Bond fund °T"ransf r-frout Future Sales
of Unspecified Funds is proposed to provide for the City's portion of the cost
of the project. Future Sales financing is required because the 1969 bond sale
allocation for this purpose has been exhausted.
Recommendations
It is recoil -nded that:
1) The following bond Fund "Transfers be approved-;
Amopat From To Reason
$68,621.84 Unspecified 8 Locations on the Property Corners' portion
042-09724-901 Northwest Side of construction cost.
042-10424-198
$91,000.00 Unspecified 8 Locations on the City's portion of con-
104-24000-901 Northwest Side struction, engineering
(Future Sales) 104-24000-198-198 and miscellaneous costs.
Approximately $1,500 is available in the City cost account, which was estab-
lished for preliminary engineering costs.
) An ordinance be adopted:
a) Declaring the necessity for and ordering the improvements;
b) Making provisions for levying of assessments;
c) Directing the Public Works Director to prepare estimates of
costs and amounts to be assessed;
d) Awarding the contract to S.R.O. Asphalt, Inc. , Arlington,
Texas, in the amount of $146,310-75; and.,
e) Making appropriations to cover the indebtedness thereby
incurred for improvements as described above.
3) An ordinance be adopted;
a) Approving the estimates of cost and amounts to be assessed;
and.,
b) Setting March 9, 1971, as the date for the Benefit Tearing.
UD :
Attachments.
"A" Resume of Project
"B" - Location Maps
"C" - Engineers" Preliminary„ Rolls
SUBMITTED SY: DISPOSITI±D Y COUNCIL. PROCES BY
APPRO'VEO 3 OTHER (DESCRIBE)
V � CITY SECRETARY
e DATE
CITY MANAGER
w