HomeMy WebLinkAboutContract 57453-FP1FORT WORTII®
TRANSPORTATION AND PUBLIC WORKS
NOTICE OF PROJECT COMPLETION
-FP1
City Secretary No:_57453
Date Received: 3/30/2023
City Project Ne: 103456
Regarding contract 57453 Bridge Repair for Twenty Locations for as required by the TRANSPORTATION
AND PUBLIC WORKS DEPARTMENT as approved by City Council on 3/08/2022 through M&C 22-0150
the director of the
TRANSPORTATION AND PUBLIC WORKS DEPARTMENT upon the recommendation of the Assistant
Director of the Transportation & Public Works Department has accepted the project as complete.
Original Contract Prices: $679,646.60
Amount of Approved Change Orders: $32,544.0M 2
Revised Contract Amount: $712,190.60
Total Cost Work Completed: $712,037.73
Less Deductions:
Liquidated Damages: 0 Days @ $650.00/ Day
Pavement Deficiencies:
Total Deduction Amount: $0.00
Total Cost Work Completed: $712,037.73
Less Previous Payments: $676,435.84
FinalinIPayment Due $35,601.89
�'"';•44" Mar 30, 2023
Recommended for Acceptance Date
Asst. Director, TPW - Capital Delivery
Lauren Prieur (Mar 30, 2023 10:05 CDT)
Accepted
Director, TRANSPORTATION AND PUBLIC WORKS DEPARTMENT
Client Deartment
William
Mar 30, 2023
Date
Mar 30, 2023
Asst. City Manager Date
Comments:
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
C-620 Signature Page
To (Owner)
P. O.
Number.
Project: 103456
City Secretary Contract
Number:
Approved Change Orders
Number
1
2
3
4
5
6
7
8
TOTALS
NET CHANGE BY
CHANGE ORDERS
Contractor's Certification
Contractor's Application for Payment Invoice No.1
City of Fort Worth Invoicing Period (From - To): Invoice Date:
02/01/2023 - 02/28/2023
FW020-007730 From (Contractor):
Gibson & Associates Inc
Contractor's CFW Vendor No.:
0000009564
57453 CoName:ntract 2022 Bridge Rehabilitation Contract 2
Application For Payment
Change Order Summary
Additions
$10,219.00
$22,325.00
$32,544.00
$32,544.00
Deletions
The Contractor certifies with the submittal of this document and associated Payment Request Submittal
on the City of Fort Worth Buzzsaw system that to the best of their knowledge: (1) all previous progress
payments received from Owner on account of Work done under the Contract have been applied on
account to discharge Contractor's legitimate obligations incurred in connection with Work covered by
prior Applications for Payment (2) title of all Work, materials and equipment incorporated in said Work
or otherwise listed in or covered by this Application for Payment will pass to Owner at time of payment
free and clear of all Liens, security interests and encumbrances (except such as are covered by a Bond
acceptable to Owner indemnifying Owner against any such Liens, security interest or encumbrances);
and (3) all Work covered by this Application for Payment is in accordance with the Contract Documents
and is not defective.
Liquidated Damages $650.00 x day
,7o,ret Montaotktetti
Joseph Illontgomery (Mar'28, 202311:5 CDT)
9 & Final
3/7/2023
Remit to (If Not Automatic Deposit ):
1. ORIGINAL CONTRACT PRICE $ $679,646.60
2. Net change by Change Orders $ $32,544.00
3. Current Contract Price (Line 1 ± 2) $ $712,190.60
4. TOTAL COMPLETED AND STORED TO DATE
(Progress Estimate, Construction Allowance and Change Orders) $ $712,037.73
5. RETAINAGE:
a. X $712,037.73 Work Completed $
b. X Not Used $
c. Total Retainage (Line 5a + Line 5b) $
6. AMOUNT ELIGIBLE TO DATE (Line 4 - Line 5c) $ $712,037.73
7. LESS PREVIOUS PAYMENTS (Line 6 from prior Application) $ $676,435.84
8. AMOUNT DUE THIS APPLICATION $ $35,601.89
9. BALANCE TO FINISH, PLUS RETAINAGE
(Column G on Progress Estimate+ CA + COs + Line 5 above) $ $152.87
10. CONTRACT TIME:
Consent of Surety
Affidavit of Bills Paid
a. Days Awarded
b. Days Added by CO
c. Total Days
d.
e.
Days Charged
Days Remaining
This document has been modified from its original form as an EJCDC document and the user did not highlight the
modifications. You are encouraged to read the document carefully and consult Legal Counsel prior to its execution.
180
30
210
210
Progress Estimate
F"`I`°n"'"' 2022 Bridge Rehabilitation Contract 2
APPbc.una Peru,
02/01/2023 -02/28/2023
9N Item Na Dacromon
C,ry Sea.,
Cow. Num:
57453
ADDbe.uon Number.
AwlEatrun Date:
Contractor's Application
9 A Find
3/7/2023
Er mated Qunmiry blmm4 (P05500)
Toul ComDluud Bala. to Ewalt
SDecPicatmn Gm of Bid QuanUty Uml Pr¢v BN Value Wulted Value Prwmu.ly N.uSN Veuu Value T. Period Stumd (rim in C) and Smmdu Deu (F) (B•F)
SccuanNo Musters (Da E)
_ 1 REMOBILOATON EA 1.000000 SSOOAB ,500,0E _ 5500.00
2 REMOVE CONCRETE(PAV) _ 1044001 SY 151.100000 $110m 53]196.00 20342000000 SJ6,59].60 126,397A0 -__ 5]6,591m 134.5% 39399.50
J REMOVE CONCRETE (SIDEWALKS) 1044015 SY 273W000 3100m 52,]50.00 31A00000v0 - _ 50,150.00 5],150A0 53,150m 1149%-9410.00
4 REMOVE CONCRETE (APPROACH SLAB) 104.5027 SY 151.100000 8100m $
3],196m 15535000000 52T,99B.W 52)p99A0 52]A9Dm 1029% 3501.00
S - -- EXCAVATION (ROADWAY) 1106W1 CY 160A00000 553m 513250m 15].00W0000 512380.00 512A99A0512,595m _95.6% 5561.00
6 EMBANKMENT (FlNAL)(ORD COMP)(IY B) 1Ytl00] CY 25.OW000 513am SS TSOm 25.00000000 $3,750.00 $3,]SOAD _.... _.. _._____.-,SS.75Om 10G0%
] - -CONCRETE PAVEMENT (COHTREWF-CRCPJ(1j 360.6001 SY 152m0000 Si9Sm S44,MOm 20]A3000000 SS9A]9.40 555479A0 _. _... _ _... _ _... -.. - 559A79.40 1]]A% 315,1]9.40
6 _ CEMENT STABRPEDMCKFLL 4004005 _ CY 155,0000011 S1Nm S29,TOIm 15]A0000000 525,]W.00 525,TMm 515.]51m _9fA% 5910m
9 PLOWABLE BACKFILL 401-6001 CY 2003000 SSDOm S1AWm 425000000 f2.125.00 f2,125m 52,125A0 3133% $1,125.00
10CLC CONC (415C) __. _ -- 42060]4 CY S.000OOD f12A00m 560AOOm 435000W0 i$$300.W .$SSA00m $55A00.00 9JA%_ _ 54,200A0
11 APPROACH SLAB 4225015 CY 55.000000 St,t62m 3550tOm 70.ODWDWO 562740.OD 562,740m 552,]40m 137.]% St),Tw.Oo
12 ___CONCRETE STR REPAIR (VERTIGL5OVERHEAD) 429-500] SF 455.000000 StOSm 947,775m T952]0110000 $]0.999.15 S]OA9D.15 930A99.15 54.5% 515,]]5.05
13 CONCRETE SIR REPAIR (STANDARD) 43&6DD9 _ SF 43.000000 f50m 53,440m 15AB000000 _- S5,006.40 i5,006A0 SS,OOEAO 114.!% 52.566.40
14 RIPRAP (205005TE)(CLB) 4]3SOD6 CY 0.500000 S2,OODm f1ADDm 03000W00 51,000.00 51,OODm S1,000AO 100A%
15 RIPRAP (STONE PROTECTION) (121M 4]2d0]1 CY 6300000 yTUDm S6,2Mm 53000D000 56205A0 55,205m 38,2a5.00 100.0%
10 CLEAN AND SEAL EXISTING JOINTS 4]56D01 LF 470.000000 i]Dm 5/4,100• 470.00000000 314,100A0 $14,100A0 514,100.00 100.0%
17 CLEAN AND PAINT E%ISTG STRUCTURE 40010 LS _ 1.000000 $252 5.00 f2D 500,00 1,ODOl10WD S10,500:00 S20,S00A0-__--_-_ i20.5D0.00 100.0%_
16 MIL (NANOMIL)(TV A) 4504047 LF B1.000D00 5215m $16,060.00 15.70000000 515,050,00 f15,05000 516,050,00 100,0%
19 RAIL (TYPR11) 4504103 LF 305.000000 519030 _ f54303.00 215.70000W0 _ _ f41,090A5 $
41,09035 941,O90A5 ]OS% it],202.15
?D CLEAN EXISTING CULVERTS 4606002 00 5.000000 87,000m ie+000m 5.00000000 f3000.00 55,000m 55000.00 100.0%
21---REMOVE STR (RAIL) _ _ --__ 4966W9 LF 250.000000 _9OOM 211,600.00 i90.00000000 S110Wm 511,500m ._. _-- _.-$11,500A0 100.0%
22 CONCRETE SIDEWALKS (5) 5314002 5Y 00.000000 S10DA0 $15 000.00 5T.65000000 515355.00 t15,55540 - 515355A0 105.7% 3655m
23 _ MTL W-0EAM GO FEN (RM POST) 5400001 LF ]55m0000 f]3.15 f25,35220 524500000011 515,]67.15 $
]5,]51.15 535.36726 1352% 39,9MS5
24 _ _ MTL VABEAM GD FEN (IHRIE-0BEAM) 5406W6 EA - 6m0000 32A5430 f17,127.00 7.00000000 _ S19A61m 519A61m _ - _ 552,951.00 116.0% 33A5430
25 MIL W.9EAL1 GO FEN (7L2) _ 51p6WT G 1m0000 52,145m 52145m 1.000000W 52145m f2,145m 52,145A0 100DX
m OOwNSREAM ANCHOR TERMINALSEOTION _._... 5404K115 EA000000 i1.G.5UD0_ S4s950.00 J.00000000 S•.950.W 54,950m _.. 11ASOA5100.7%_
2T REMOVE METAL BEAM GUARD FENCE 54241001 LF NO.ODO.IO0 -
54.13 51715]0 605A0001.0 52496AS 52496.5T - .254.550...00
3 �95A5 140.TA ---Sia.Ts
26_-_ REMOVE METAL BEAM GUARD FENCE TRANS (11011 54SSW5 FA 2.000000---SMDm 3660.00 3.00000000 _51A20m 31 A20AD SI,ROAO 150.0% _-- 5410.00
29 _ GUARDRAIL END TREATMENT (INSTALL) _ 5M0001 EA 6.000000 N,T2530 _ f37.TB6.00 .--_ 6A000OWO A).196A0 _ $3),796m _ 33),]%.OD 100,0%
30 GUARDRAIL END TREATMENT (REMOVE) 5144W] FA 2400000 5355m 5770.OD 2.000OOOOp f110.00 $T70A0 5710m 1WA%
31 CRASH CUSHION ATTENUATOR BNSTALL)(RJ(I!)(ILt) 7524003_ _FA_ 1.000000 $33,OODJp X 9250.OD 200000000 SV,000.00 SSt 000A0 533A00m 100.0%
32 _ TREE REMOVAL ]521W5 FA 1.000000 5250m 5250.00 _ _ 2AD000000 5500.00 _ _ SsaoaD SSOOAO 200.0% 425040
33 REMOVEIREPLACE 51051P OST - _7706010 EA 1.000OW 5935m S935.0 _ 240000000 5935.00 59]5.00 5460.00 600.0%
30 _ REMOVERtEPLACE STEEL POST _ ]106010 EA 1.000OW SWSm _ S9]5.00 6.00000000 S],460.00 5),460.00 - 57480.00 500,0% 46,545.00
15 _ REMOVE/REPLACE BLOCKOUT T705019 EA_ 1.000000 S907,50 590).50 tA0000000 _ 5907.50 S90)30 SBO]SO t00A%
36 REPAIR (EXISTING METAL PED. RAIL) 778-60]] LF 7 5.00W00 S1JOm _ 513,650.00 T5930000000 S]J,T]5.00 2]],)]SAO 5]S,TJSAO 24].1% 33D,055m
J] CONCRETE CRACK REPAIR (ROUT AND SEAL) _ >50-0004 LF 190.000000 550.00 50,500.00 145.75000000 $]A3].50 5],]]T.50 _ $T,JJ130 _T2% 32,16330
34 _ REPULE NUTS, WASHERS 6OTHER HARDWARE _ _ 500D61 D5 EA 12.000000 520m ,95.00 2200000000 5440.00 N40.00 54AOA0 100A%
]9 CONSTRUCTION ALLOWANCE 000000 LS 1.000000 SSO,o00m 550,000.00 - _ 550.000.00
TWsdocummt has been modified Born to onoo4 farm as an EICOC document and Mc user dN not 119.819 the
mod,0emors You ma ene0ur.5ed TO read Nv downs. catalb1hand consult Legal Counsel pour to esnaavu0n
Progress Estimate
For (contract):
Application Period:
Item Number
Construction Allowance Usage
ADDITIONS
2022 Bridge Rehabilitation Contract 2
103456
A
Item
Description
4' White TYI THERMOPLASTIC
02/01/2023 - 02/28/2023
City Secretary
Contract Num:
57453
B D
Specification Unit of Quantity to Add Unit Pricc Addition Value Estimated Quantity
Installed
Section No. Measure
LF 160.00000000 $8.21 51313.60 160.00000000
Value
Application Number:
Application Date:
E
Previously Value This Materials 1' o.ntly
Installed Value Period Stored (not in C)
$I313.60 51313.60
2 4' Yellow TYl THERMOPLASTIC (DOUBLE YELLOW) LF 120.00000000 $822 $986.40 120.00000000
3 Minimum Trip Charge LS 1.00000000 $1.000.00 $1.000.00 1.00000000
$986.40 $986.40
$1.000.00 $1.000.00
C-620 Change Order
Contractor's Application
9 & Final
3/7/2023
F
Total Completed %
and Stored to Date (F)
(D+E) B
$1313.60 100.0%
Balance to Finish
(13-F)
$986.40 100.0%
$1.000.00 100.0%
This document has been modified from its original form as m EJCDC document and the user did not highlight the
modifications. You are encouraged to read the document carefully and consult Legal Counsel prior to its execution.
C-620 Change Order
Totals S3300.00 S3300.00 S3300.00 S3300.00 100.0% I
This document has been modified from its original form as an EJCDC document and the user did not highlight the
modifcotions. You are encouraged to read the document carefully and consult Legal Counsel prior to its execution.
Progress Estimate
'For (contract):
'Application Period:
103456 2022 Bridge Rehabilitation Contract 2
Construction Allowance Usage
CONSTRUCTION ALLOWANCE ITEMS TO BE REDUCED
02/01/2023 - 02/28/2023
Bid Item Number
A
Item
Description
Construction Allowance 1
Specification
Section No.
Unit of
Measure
Quantity to Delete
0.02627200
Unit Price
$50,000.06
B
Reduction Value
$1313.66
T
Construction Allowance 1
0.01972800
$50000.00
$986.40
Construction Allowance l
0.02000000
$50,000.00
$1,000.00
C
bt Used
D
Not Used
This document hos been modified from its original form os an EJCDC document and the user did not highlight the
modJcotions. You arc encouraged to mad the document carefully and consult Legal Counsel prior to its execution.
Not Used
Not Used
Application Number:
Application Date:
B
Not Used
C-620 Change Order
Contractor's Application
Not Used
F
9 & Final
3/7/2023
Not Used
Not Used
Totals
S3,300.001
This document has been modified from its original form as an EJCDC document and the use did not highlight the
modifications. You am encouraged to read the document carefully and consult Legal Counsel prior to its execution.
C-620 Change Order
Progress Estimate
For (contract):
Application Period:
Change Order Item
No.
29
Change Order Number
ADDITIONS
103456 2022 Bridge Rehabilitation Contract 2
Item
Description
GUARDRAIL END TREATMENT (INSTALL)
A
02/01/2023 -02/28/2023
Specification Unit of
Section No. Measure
1
City Secretary
Contract Num:
Addition
CO Quantity to Add Unit Price Change Order
Value
C-620 Change Order
Contractor's Application
57453 Application Number.
Application Date:
C D E F
Estimated Quantity
Installed
Value
Previously Value This Materials Presently and Stored to Date (F) (B -F)
Installed Value Period Stored (not in C) (D + E) B
9 & Final
3/7/2023
Total Completed % Balance to Finish
EA 2.00000000 54.724.50 $9.449.00 2.00000000 S9.449.00 $9.449.00 $9.449.00 100.0%
30 GUARDRAIL END TREATMENT (REMOVE) EA 2.00000000 S385.00 S770.00 2.00000000 S770.00 S770.00 5770.00 100.0%
This document has been modified from its original form as an EJCDC document and the user did not highlight the
modifications. You am encouraged to mad the document carefully and consult Legal Counsel prior to its execution
Totals
C-620 Change Order
S10,219.00 S10,219.00 S10.219.00 S10,219.00 100.0%
This document has been modified from its original form as an E]CDC document and the user did not highlight the
modifications. Von are encouraged to read the document carefully and consult Legal Counsel prior to its execution.
Progress Estimate Change Order Number
For (contract):
Application Period:
Change Order Item
No.
1
C-620 Change Order
Contractor's Application
DELETIONS
103456 2022 Bridge Rehabilitation Contract 2 Application Number.
9 & Final
02/01/2023 - 02/28/2023 Application Date: 3/7/2023
A B C D E F
Item Deletion
CO Quantity to
Description Speccation Unit of DeleteUnit Price Change Order Not Used Not Uscd Not Used Not Used Not Used Not Used Not Used Not Uscd
Section No. Measure Value
This document has been modified from its original fomt as an EJCDC document and the user did not highlight the
modifications. You am encouraged to read the document carefully and consult Legal Counsel prior to its execution.
Totals
C-620 Change Order
This document has been modified from its original form as an EJCDC document and the user did not highlight the
modifications. You am encouraged to mad the document carefully and consult Legal Counsel prior to its execution.
Progress Estimate Change Order Number I 2
ADDITIONS
For(nnntn1o) 103456 2022 Bridge Rehabilitation Contract 2 City Secretary 57453 Application Number:
Contract Nun:
Application Need: 02/01/2023 — 02/28/2023 Application Date:
A B C D E
Item
Chan Order Item Spcn cation Unit or CO Quantity Unit Price Addition Change Estimoted Quantity Previously Value This Materials Presently
Description Order Value Installed lmidled Value Period Stored (not in C)
No. Section No. Measure
15 RIPRAP(STONE PROTECTION/ (1215)
17 CLEAN AND PAINT EXISTING STRUCTURE
CY 2.50000000
S730.00 0i625.00 2.50000000 01.825.00 51.825.00
IS 1.00000000 520,500.00 S20.500.00 1.00000000 _ 520,50000 S20,500.00
Contractor's Application
9 & Final
3/7/2023
Total Completed
and Stored to Dote
(D+E)
S1 S25.00 100.0%
Balance to Finish
6-F)
520500.00 100.0%
Totolo 522.325.00 52232.500 522.32500 522.325.00 100.0%
This document has been modified from its original !form us an EJCDC document and the user did not highlight the
modifications. You are encouraged to read the document oarelLlly and consult Legal Counsel prior to its execution.
0-620 Change Order
Progress Estimate Change Order Number
DELETIONS
For (contt0ct) 103456 2022 Bridge Rehabilitation Contract 2
Application Period: 02/01/2023 - 02/28/2023
Change Oder Item
No.
Item
Description
Totals
2
Application Number.
Application Dole:
Contractor's Application
A D E F
Speelieatmn Una of
Section No. Measure
CO Quantity to
Delete
Unit Price
Deletion Change
Order Value
Not Uscd
9 & Final
3/7/2023
Not Uscd Not Used Not Uscd Not Uscd Not Uscd Not Used Not Used
This document has been modified from its original form as an EJCDC document and the user did not highlight the
modifications. You arc encouraged to read the document carctully and consult Legal Counsel prior to its execution.
C-620 Change Order
Progress Estimate Change Order Number I 3 Contractor's Application
ADDITIONS
em(camraeD: 103456 2022 Bridge Rehabilitation Contract 2 City Secretary 57453 Application Number 9 S Final
Convect Num:
Application Period: 02/01/2023 - 02/28/2023 Application note: 3/7/2023
A B C D E F
lam Balance to Finish
Addition Total Completed �° s'
Estimated Qmntiry Prniously Value This Materials Presently B-F)
c Chan order llem Specification Unit of CO Quantity to Add Unit Price Change Order Value and Stand to Dole (F)
g No. Description Section No. Measure Value Installed Installed Value Period Stored (not in C) (D*E) B
Totals
This document has been modified from its original form as on FJCDC document and the user did not highlight the
modifications. You are encouraged to rod the document orofully and consult Legal Counsel prior to its oncoulion.
C-620 Change Order
Progress Estimate Change Order Number I
DELETIONS
For (contract): 103456 2022 Bridge Rehabilitation Contract 2
Application Period: 02/01/2023 - 02/28/2023
A
Item
Change Order Item Spcciticauon Unit ol
Despli
No. enon Section No. Measure
3
CO Quantity to
Delete
Application Number.
Application Date:
Contractor's Application
9 & Final
3/7/2023
Deletion
Unit Bice Change Order Not Used Not Used Not Used Not Used Not Used Not Used Not Used Not Used
Value
Tonne
This document has been modified from its original form as an EICDC document and the user did not highlight the
modifications. You arc encouraged to read the document carefully and consult Legal Counsel prior to its execution.
C-620 Change Order
Progress Estimate Change Order Number
ADDITIONS
For (contract). 103456 2022 Bridge Rehabilitation Contract 2
Application Period: 02/01/2023 - 02/28/2023
Change Order Item
No.
Item
Description
Totals
A
4 I Contractor's Application
City Secretary
Contract Num:
B
57453
Addition Fstimvted Qmntiry
Specification Unit of CO Quantity to Add Unit Price Change Order Installed
Value
Section No. Measure Value
Application Number.
Application Date:
F
9 & Final
3/7/2023
Previously Value This Materials Presently Total Completed
Installed Value Period Stored (not in C) °1d StmedkDak (F)
(D+E) B
This document has been modified from its original form as an EJCDC document and the user did not highlight the
modifications. You are encouraged to read the doemnent carefully and consult Legal Counsel prior to its execution.
Balance to Finish
(B-F)
C-620 Change Order
Application Period:
Change Order item Description
No.
Progress Estimate Change Order Number
DELETIONS
For (contract) : 103456 2022 Bridge Rehabilitation Contract 2
D2/01/2023 - 02/28/2023
4
Application Number.
Application Date:
Contractor's Application
9 & Final
3/7/2023
A B C D E F
Item CO Quantity to Deletion
Spcciticahon Unit of DeleteUnit Price Change Order Not Used Not Used Not Used Not Used Not Used Not Used Not Used Not Used
Section No. Measure Value
Totals
This document has been modified from its original form as an EICDC document and the user did not highlight the
modifications. You are encouraged to read the document carefully and consult Legal Counsel prior to its execution.
C-620 Change Order
Progress Estimate Change Order Number I
ADDITIONS
For (contmeB 103456 2022 Bridge Rehabilitation Contract 2
Application Pedal: 02/01/2023 - 02/28/2023
Change Order Item
No.
Item
Description
Totals
A
5 1 Contractor's Application
City Secretary
Contract Num:
57453
C D
Addition
Specification Unit of CO Quantity to Add Unit Price Change Order Estimated Quantity
Value
Section No. Measure Value Installed
Application Number.
Application Date:
9 & Final
3/7/2023
Total Completed Ts
Previously Value This Materiels Presently
"d S""I" r"" (F)
Installed Value Period Stored (not in C)
Balance to Finish
(3-F)
This document has been modified from its original form as an EICDC document and the user did not highlight the
medificationc. You ate encouraged to read the document carefully and consult Legal Counsel prior to its execution.
C-620 Change Order
Progress Estimate Change Order Number
DELETIONS
For (contract): 103456 2022 Bridge Rehabilitation Contract 2
Application Poriod: 02/01/2023 - 02/28/2023
A
Item
Change °fact Item Specitication that or
Dcscription
No, Section No. Measure
5
CO Quantity to unit pd.
Dcictc
Application Number.
Application Date:
Contractor's Application
9 & Final
3/7/2023
Delebon
Change Order Not Used Not Used Not Uscd Not Used Not Used Not Used Not Used Not Used
Value
Totals
This document hos boon modified from its original form ooun EJCDC document and the user did not highlight the
modifications. You are cneouragal to mad the document carefully and consult Legal Counsel prior to its execution.
C-620 Change Order
Application Period:
Change Order Item
No.
Progress Estimate Change Order Number I 6
ADDITIONS
For (contract): 103456 2022Bridge Rehabilitation Contract 2 City Secretary 57453 Application Number:
Contract Num:
02/01/2023 - 02/28/2023 Application Date:
A B C D E
Item
Dos«iption
Totals
Specification Unit of
Section No. Measure
Contractor's Application
9 & Final
3/7/2023
Addition Total Completed %
Eslimotcd CO Quantityto Add Unit Prim Change Order (Zuan"'Y P oValue
Value This Materials Presently
Installed VoValueInstalledtaIIlled Value Period Stored (not in C) and Stored to Date (F)
Value N+E)
Balance to Finish
(B-F)
This document has been modified from its original form as an FJCDC document and the user did not highlight the
modifications. You arc encouraged to read the document carefully and consult Legal Counsel prior to its execution.
C-620 Change Order
Progress Estimate Change Order Number
DELETIONS
For (contract): 103456 2022 Bridge Rehabilitation Contract 2
Application Period: 02/01/2023 - 02/28/2023
Change Order Item
No.
A
Item
Description
Specification Unit or
Section No. Measure
6
CO Quantity to
Delete
Application Number.
Application Date:
B C D B
Contractor's Application
9 & Final
3/7/2023
Deletion
Unit Price Change Order Not Used Not Used Not Used Not Used Not Used Not Used Not Used Not Uxd
Value
Tarots
This document has been modified from its original form as an EJCDC document and the user did not highlight the
modifications. You me encouraged to read the document carefully and consult legal Counsel prior to its execution.
C-620 Change Order
Progress Estimate Change Order Number
ADDITIONS
For (contract): 103456 2022 Bridge Rehabilitation Contract 2
Application Penal: 02/01/2023 - 02/28/2023
Change Order Item
No_
Item
Description
Total
7 1 Contractor's Application
City Secretary
Contract Num:
A
57453
C D
Addition QuantityQ d ate
Specification Unit of CO Quantity to Add Unit Price Change Order Estimated
Section No. Measure Value
Application Number.
Application Date:
9 & Final
3/7/2023
Value
Previously Value This Materials Presently Total Completed
Installed
Stored to Date (F)lled Value Period Stored (not in C) (D+E) B
Balance to Finish
(B-F)
This document has been modified from its original form as an E)CDC document and the user did not highlight the
modifications. You are encouraged to read the document catching and consult Legal Counsel prior to its execution.
C-620 Change Order
Progress Estimate Change Order Number I 7 I Contractor's Application
DELETIONS
Fnr(contfBc): 103456 2022 Bridge Rehabilitation Contract 2 Application Number. 9 & Final
Application Period: 02/01/2023 — 02/28/2023 Application Dote: 3/7/2023
A B C D E
Item DeletionCO Quantity to
Change Order Dom Specification umt or Unit Price Change Order Not Used Not Used Not Used Not Used Not Used Not Used Not Used Not Used
No. DescriptionDeleteNo. Measure Delete Value
MINIS
This document has been modified from its original form as an EJCDC document and the user did not highlight the
modifications. You are encouraged to read the document carefully and consult Legal Counsel prior to its execution.
C-620 Change Order
Progress Estimate Change Order Number i 8 I Contractor's Application
ADDITIONS
For (connect): 103456 2022Bridge Rehabilitation Contract 2 City Secretary 57353 Application Number. 9&Final
Convect Num
Application Period: 02/01/2023 - 02/28/2023 Application Date: 3/7/2023
A B D E F
Item Balance to Finish
Addition Total Completed %
E+timalW quantity Previously Value This Materials Presently (B-F)
Change Order Item Description Specifimtion Unit of CO quantity to Add Unit Price Change Order Installed Value Installed Value Period Stored (not in C) and Stored to Date (F)
No- P Smtion No. Measure Value (D. E) B
Totals
This document has been modified from its original form as an FJCDC document and the user did not highlight the
modi6mtions. You are encouraged to read the document carefully and consult Legal Counsel prior to its execution.
C-620 Change Order
Application Period:
Change Odor Item
No.
Progress Estimate Change Order Number
DELETIONS
For (contract): 103456 2022 Bridge Rehabilitation Contract 2
02/01/2023 - 02/28/2023
Item
Description
A
Specification Unit of
Section No. Measure
8 1 Contractor's Application
CO Quantity to unit Price
Delete
Application Number.
Application Date:
B D B
Deletion
Change Order Not Used Not Used Not Used Not Used Not Used
Value
Totals
9 & Final
3/7/2023
Not Used Not Used
Not Used
This document has limn modified from its original f as an EJCDC document and the user did not highlight the
modifications. You arc encouraged to reed the document carefully and consult Legal Counsel prior to its execution.
C-620 Change Order
City Secretary Contract Num: 57453
Application Period:
City of Fort Worth Summary of Charges
2022 Bridge Rehabilitation Contract 2
02/01/2023 - 02/28/2023
Funding Identification (FID) Total Completed
IP.O.:
Application
Number:
FW020-007730
9 & Final
Project Number.
Application Date:
103456
3/7/2023
Amt Remaining Gross Retainage Net
Original Contract
30100-0200431-5740010-103456-E02680-9999 $679,493.73 $152.88
0
0
0
0
0
0
o
o
0
0
Change Order 1
30100-0200431-5740010-103456-E02680-9999
0
0
0
0
0
0
0
0
0
0
Change Order 2
30100-0200431-5740010-103456-E02680-9999
0
0
0
0
0
0
0
0
0
0
$10, 219.00
$22,325.00
City Secretary Contract Num: 57453
Application Period:
City of Fort Worth Summary of Charges
2022 Bridge Rehabilitation Contract 2 [P. O. :
02/01/2023 - 02/28/2023 Application
Number:
Funding Identification (FID) Total Completed
Change Order 3
30100-0200431-5740010-103456-E02680-9999
0
0
0
0
0
0
0
0
0
0
Change Order 4
30100-0200431-5740010-103456-E02680-9999
0
0
0
0
0
0
0
0
0
0
Change Order 5
30100-0200431-5740010-103456-E02680-9999
0
0
0
0
0
0
0
0
0
0
FW020-007730
9 & Final
Project Number.
Application Date:
103456
3/7/2023
Amt Remaining Gross Retainage Net
City Secretary Contract Num:
57453
Application Period:
City of Fort Worth Summary of Charges
FW020-007730
2022 Bridge Rehabilitation Contract 2
02/01/2023 - 02/28/2023
Funding Identification (FID) Total Completed
Change Order 6
30100-0200431-5740010-103456-E02680-9999
0
0
0
0
0
0
0
0
0
0
Chan_ a Order 7
30100-0200431-5740010-103456- 02680-9999
0
0
0
0
0
0
0
0
0
0
Change Order 8
30100-0200431-5740010-103456-E02680-9999
0
0
0
0
0
0
0
0
0
0
(P.O.:
Application
Number:
9 & Final
Amt Remaining Gross
Project Number:
Application Date:
Retainacle
103456
3/7/2023
Net
City Secretary Contract Num: I 57453
Application Period:
City of Fort Worth Summary of Charges
2022 Bridge Rehabilitation Contract 2
02/01/2023 - 02/28/2023
Funding Identification (FID) Total Completed
Totals
30100-0200431-5740010-103456-E02680-9999
0
0
0
0
0
0
0
0
0
0
(P. 0.:
Application
Number:
FW020-007730
9 & Final
Project Number:
Application Date:
103456
3/7/2023
Amt Remaining Gross Retainage Net
$712,037.73 $152.88
Grand Total I I $712,037.73 I I $152.88
$0.00 I I
($35,601.89)1 I $35,601.89
FORT WORTH
Routing and Transmittal Slip
Transportation and Public Works
Department
DOCUMENT TITLE: Change Order # 1 — 2022 Bridge Rehab Contract 2
M&C CPN: 103456
Date: 11/30/2022 FM
To:
1. Trey Meador (Contractor)
2. Robert Riley (Inspector)
3. lretomiwa Otuyelu (PM)
4. Omar Elbagalati (PgM)
5. Leon Wilson (Sr CPO)
6. Michael Owen (AD)
7. Lauren Prieur (Director)
8. Doug Black (ACA)
9. William Johnsom (ACM)
10. Jannette Goodall (CSO)
CSO # 57453
Department
Gibson & Associates Inc
trevm(@.aibsonassoc.net
TPW-Signature
TPW-Signature
TPW-Reviewer
TPW-Reviewer
TPW-Signature
TPW-Signature
LAW -Signature
CMO-Signature
CSO-Signature
DOC# C01
Initials Date Out
Dec 5, 2022
TM
RR. Dec 5, 2022
Dec 2, 2022
.t Dec 5, 2022
Ltd Dec 5, 2022
Dec 5, 2022
/1P Dec 5, 2022
dew Dec 7, 2022
61— Dec 9, 2022
Dec 9, 2022
DOCUMENTS FOR CITY MANAGER'S SIGNATURE: All documents received from any and all
City Departments requesting City Manager's signature for approval MUST BE ROUTED TO THE
APPROPRIATE ACM for approval first. Once the ACM has signed the routing slip, David will review
and take the next steps.
NEEDS TO BE NOTARIZED: ❑ Yes X No
RUSH: ❑ Yes X No SAME DAY: ❑ Yes X No NEXT DAY: ❑ Yes X No
ROUTING TO CSO: ❑ Yes ❑ No
Action Required:
❑ As Requested
o For Your Information
X Signature/Routing and or Recording
❑ Comment
o File
❑ Attach Signature, Initial and Notary Tabs
Return to: Please call lretomiwa Otuvelu at ext. 6747 for pick up when completed. Thank you.
CSC No. 57453-CO1
FORT WORTH.•. City of Fort Worth
Change Order Request
Project Name' 2022 Bridge Rehabilitation Contract 2
Client Project #(s)I 103456
Project Description)
Contractor' Gibson & Associates Inc.
City Project Mgr.' lretomiwa Otuyelu
Repair and maintenace of bridges at various locations in the city.
Change Order#I
1
City Inspector'
City Sec # 57453
Date' 11 /23/2022
Robert Riley
Contract Time
Dept. TPW Totals (CD)
Original Contract Amount $679,646.60 $679,646.60 180
Extras to Date
Credits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Date $679,646.60 $679,646.60 180
'Amount of Proposed Change Order $10,219.00 $10,219.00 30
Revised Contract Amount $689,865.60 $689,865.60 210
Original Funds Available for Change Orders $20,000.00 $20,000.00
Remaining Funds Available for this CO $20,000.00 $20,000.00
Additional Funding (if necessary)
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST + 25%)
JUSTIFICATION (REASONS) FOR CHANGE ORDER
This Change Order is to increase the number of days, and scope of work in Construction Contract 57453.
I$849,558.25
1.50%
Multiple RFI's were submitted by the contractor which resulted in modifications to the details provided for metal railings at two bridge locations. Contractor was unable to
proceed with fabrication until after receiving approved shop drawings. Time taken to provide answers to the RFIs, receive new shop drawings, and get them approved by the
engineer was approximately 42 days.
Fabricators are expected to deliver the metal rails by the end of the week ending on 11/25/2022.
PM also proposes to the replacement of two Guardrail End Treatment on E 1st St over West Fork Trinity River (#4) and Trinity Blvd WB over Railtran (#19) which were not
part of the original scope of work, but got damaged, by citizens, during construction.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in
full (both time and money) for all costs arising out of, or incidental to, the above Change Order. The Project/Program Manager signing below
acknowledges that he/she is the person responsible for the monitoring and administration of this contract, including ensuring all performance and
reporting requirements.
Contractor's Company Name
Gibson & Associates Inc
(Inspector/Inspection Supervisor
'Robert Riley,_,_
(Program Manager
(Assistant Director (Dept)
'Assistant City Attorney
Contractor (Name)
Trey Meador
Dec 5, 2022
.311
Dale (Director, Contracting Department (Dept)
Dec 5, 2022
( Date (Assistant City Manager
Dec 7, 2022
1 Contract Signature
T 1i ,4lendo -
Project and Contract Compliance Manager
Senior Capital Project Officer
Date
Dec 5, 2022
Dat
Dec 2, 2022
Dat
Dec 5, 2022
Date
Dec 5, 2022
Dat
Dec 9, 2022
Web0n`ctlMtbn(ifrequired) ' `
M&C Number
M&C Date Approved
ATTEST:
Jannette Goodall, City Secretary
FORT
Project Name 12022 Bridge Rehabilitation Contract 2
Client Project# I 103456
Contractor) Gibson & Associates Inc.
City of Fort Worth
Change Order Additions
PMI lretomiwa Otuyelu
Change Order Submittal #
ADDITIONS
HEM tM UESURIP I ION UtP I
29 GUARURAILEND IREAIMEN I INSIALL) IPW
30 GUARDRAIL END TREATMENT (REMOVE) TPW
1 I
City Sec # I 57453
Inspector) Robert Riley I
Date I 11/23/2022
Uty Unit undCost ' total
2.00000000 to 34,(24.59 59,449.1.111
2.00000000 EA $385.00 5170,00
TPW $10,219.0
Sub Total Additions $10,219.0
Change Order Additions Page 2 of 5
FORT WORTH City of Fort Worth
"s' Change Order Deletions
Project Name I 2022 Bridge Rehablitation Contract 2
Client Project # 1103456
Contractor' Gibson & Associates Inc.
PMI Iretomiwa Otuyelu I
Change Order Submittal #
DELETIONS
IILM DLSCRIPIION UEPI
Oty
1
I City Sec # 1 57453
Inspector) Robert Riley
Date
11/2312022
Unit Unit Cost total
T('W 50.0
Sub Total Deletions 50.0
Change Order Deletions Page 3 of 5
MISBE for this Change Order
MISBE Sub
Type of Service Amount for this CO I
co #
i
Total
Previous Change Orders
DATE I AMOUNT
Total
$0.00
FORT WORTH
Routing and Transmittal Slip
Transportation and Public Works
Department
DOCUMENT TITLE: Change Order # 2 — 2022 Bridge Rehabilitation Contract 2
M&C CPN: 103456
Date: 01/12/2023 AE
To.
1. Trey Meador (Contractor)
2. Kevin Jackson (Inspector)
3. Iretomiwa Otuyelu (PM)
4. Omar Elbagalati (PgM)
5. Leon Wilson (Sr CPO)
6. Michael Owen (AD)
7. Lauren Prieur (Interim Director)
8. Doug Black (ACA)
9. William Johnson (ACM)
10. Jannette Goodall (CSO)
CSO # 57453
Department
Gibson & Assoc. Inc
trevm(a�aibsonassoc. net
TPW-Signature
TPW-Signature
TPW-Signature
TPW-Reviewer
TPW-Signature
TPW-Signature
LAW -Signature
CMO-Signature
CSO-Signature
TN
TM
OE
I- (I)
7,11
ue�
DOC# CO2
Initials Date Out
Jan 30, 2023
Jan 26, 2023
Jan 27, 2023
Jan 30, 2023
Jan 30, 2023
Jan 30, 2023
Jan 30, 2023
Jan 30, 2023
Jan 31, 2023
Feb 1, 2023
DOCUMENTS FOR CITY MANAGER'S SIGNTURE: All documents received from any and all City
Departments requesting City Manager's signature for approval MUST BE ROUTED TO THE
APPROPRIATE ACM for approval first. Once the ACM has signed the routing slip, David will review
and take the next steps.
NEEDS TO BE NOTARIZED: ❑ Yes X No
RUSH: ❑ Yes X No SAME DAY: ❑ Yes X No NEXT DAY: ❑ Yes X No
ROUTING TO CSO: ❑ Yes ❑ No
Action Reauired:
❑ As Requested
❑ For Your Information
X Signature/Routing and or Recording
❑ Comment
❑ File
❑ Attach Signature, Initial and Notary Tabs
Return to: Please call Iretomiwa Otuvelu at ext. 6747 for pick up when completed. Thank you.
CSC No. 57453-0O2
Project Name' 2022 Bridge Rehabilitation Contract 2
Client Project #(s)I 103456
Project Description)
Contractor'
City Project Mgr.1
Gibson & Associates Inc.
Iretomiwa Otuyelu
Dept, TPW
Original Contract Amount
Extras to Date
Credits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Date
!Amount of Proposed Change Order
Revised Contract Amount
Original Funds Available for Change Orders
Remaining Funds Available for this CO
Additional Funding (if necessary)
$679,646.60
$10,219.00
$689,865.60
$22,325.00
$712,190.60
$20,000.00
$9,781.00
$12,544.00
City of Fort Worth
Change Order Request
Repair and maintenace of bridges at various locations in the city.
Change Order#I
2
City Inspector'
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST + 25%)
JUSTIFICATION (REASONS) FOR CHANGE ORDER
This Change Order is to increase the scope of work and contract amount in Construction Contract 57453.
City Sec # I 57453
Date 1/23/2023
Kevin Jackson
Totals
$679,646.60
$10,219.00
$689,865.60
$22,325.00
$712,190.60
$20,000.00
$9,781.00
$12,544.00
4.79%
$849,558.25
Contract Time
(CD)
180
30
210
210
PM approved to Clean and Paint Existing Structure (#17) of the WB Bridge on Trinity Blvd over Boyd Branch, as well as extra 2.5 CY of Riprap (Stone Protection) for the Bridge
at NW 30TH St over Marine Creek. These extra quantities were not estimated in the original contract but were determined to be necessary during construction.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full
(both time and money) for all costs arising out of, or incidental to, the above Change Order. The Project/Program Manager signing below acknowledges that
he/she is the person responsible for the monitoring and administration of this contract, including ensuring all performance and reporting requirements.
Contractor's Company Name Contractor (Name) Date
Gibson & Associates, Inc Trey Meador
I InspectorMspection Supervisor
(Program Manager
(Assistant Director (DeptIMIIIIIr
I-"4,.44-7"&—+—
'Assistant Cityaigia
I�-
ATTEST:
Jannette Goodall, City Secretary
Date
Jan 26, 2023
Jan 30, 2023
Date
Jan 30, 2023
Contract Signature
TeMeado7-
Project and Cont act Compliance Manager
Senior_Capital Project officer
Director, Contracting Department (Dept)
Assistant City Manager
Jan 30, 2023
Council Action (if required)
M&C Number
M&C Date Approved
Jan 30, 2023
Date
Jan 27, 2023
Jan 30, 20231
le
Jan 30, 20231
ID -
Jan 31, 2023
FORT WORTH
Project Name I 2022 Bridge Rehabilitation Contract 2
Client Project# I 103456
Contractor' Gibson & Associates Inc.
ITEM ' DESCRIPTION
15 NIPRAP(SIUNEPRO IECIIONI(12IN)
17 CLEAN AND PAIN] EXISIINUSIRULtIURE
City of Fort Worth
Change Order Additions
PMI Iretomiwa Otuyelu I
Change Order Submittal #
ADDITIONS
DEPT
IPW
IPW
2
City Sec # I 57453
Inspector' Kevin Jackson
Date I 1/23/2023
Qty Unit Unit Cost ' total
2.511110110011 CY $7311.0U $1,825.00
1.00000000 LS $20,500.00 $20,5110.00
TPW $22,325.00]
Sub Total Additions $22,325.001
Change Order Additions Page 2 of 4
Project Name I 2022 Bridge Rehabilitation Contract 2
Client Project # j 103456
Ccnlracto I Gibson & Associates Inc.
City of Fort Worth
Change Order Deletions
PM' IretomiwaOtuyelu I
Change Order Submittal #
DELETIONS
IFEM ' DESCRIPTION DEPT
2
j City Sec # j 57453
Inspector' Kevin Jackson I
Date
1/23/2023 I
Oty Unit ' Unit Cost ' Total
TPW SO.00
Sub Total Deletions $0.00
Change Order Deletions Page 3 of 4
M/SBE for this Change Order
M/SBE Sub
Type of Service Amount for this CO I
Total
Previous Change Orders
$0.00
co# DATE AMOUNT
Total
FORT WORTH
Routing and Transmittal Slip
Transportation and Public Works
Department
DOCUMENT TITLE: Construction Allowance 1 — 2022 Bridge Rehabilitation Contract 2
M&C 22-0150 CPN: 103456
Date: 10/25/2022 FM
To:
1. Trey Meador (Contractor)
2. Robert Riley (Inspector)
3. lretomiwa Otuyelu (PM)
4. Omar Elbagalati (PgM)
5. Martin Philips (Sr CPO)
6. Martin Phillips (AD)
7. Lauren Prieur (Director)
8. Doug Black (ACA)
9. William Johnson (ACM)
10. Jannette Goodall (CSO)
CSO # 57453
Department
Gibson and Associates
trevm(@.aibsonasoc.net
TPW-Signature
TPW-Signature
TPW-Reviewer
TPW-Reviewer
TPW-Signature
TPW-Signature
LAW -Signature
CMO-Signature
CSO-Signature
DOC# CA#1
YrrP
LLP
jSa
Date
10/28/22
10/31/22
10/31/22
10/31/22
10/31/22
10/31/22
10/31/22
11/04/22
11/04/22
11/07/22
DOCUMENTS FOR CITY MANAGER'S SIGNTURE: All documents received from any and all City
Departments requesting City Manager's signature for approval MUST BE ROUTED TO THE
APPROPRIATE ACM for approval first. Once the ACM has signed the routing slip, David will review
and take the next steps.
NEEDS TO BE NOTARIZED: ❑ Yes X No
RUSH: ❑ Yes X No SAME DAY: ❑ Yes V No NEXT DAY: ❑ Yes X No
ROUTING TO CSO: ❑ Yes ❑X No
Action Required:
❑ As Requested
o For Your Information
X Signature/Routing and or Recording
❑ Comment
o File
❑ Attach Signature, Initial and Notary Tabs
Return to: Please call lretomiwa Otuvelu at ext. 6747 for pick up when completed. Thank you.
CSC No. 57453-AR1
FOR TWORTH9 City of Fort Worth
Construction Allowance Request
Project Name' 2022 Bridge Rehabilitation Contract 2
Client Project #(s)l 103456
ProjectlBridge rehabilitation at various locations, city wide.
Description
ContractorlGibson and Associates Inc
City Project Mgr.l Iretomiwa Otuyelu
UNIT or DEPT I TPW
Original Contract Amount 1 $679,646.60
Extras to Date
Credits to Date
Current Contract Amount $679 646.60
(Amount of Proposed Allocation $3,300.00
Original Allowance Available to Allocation $ i0,000.00
Allowance Funds Previously Allocated
Revised Allowance Balance $46,700.00 $0.00 $0.00
l City Sec # l 57453
CA ri1 1 I Date' 10/18/2022
City Inspector) Robert Riley
UNIT 2 or Dept UNIT 3 or Dept UNIT 4 or Dept Totals
$0.00 $0.00
$679,646.60
$679,646.60
i 300.00
$td000.00
$0.00
$0.00 $46,700.00
$0.00
JUSTIFICATION (REASONS) FOR CONSTRUCTION ALLOWANCE
IN ACCORDANCE WITH THIS CONSTRUCTION ALLOWANCE REQUEST, THE CONTRACT SHALL: Furnish all labor and material as per
attached proposed Construction Allowance Request (with attachments): Replacement of existing pavement striping on the approach slab at the
Meacham Boulevard Bridge over BNSF Railroad.
During preliminary estimates, this line item was not thought to be needed and therefore not provided in the contract. However, after the work
was completed, staff determined that there would need to be pavement markings on the replaced concrete slabs, for proper traffic control.
The attached email shows that this is the most reasonable price we could achieve to mobilize a crew for the job.
It is understood and agreed that the acceptance of this Construction Allowance Request by the contractor constitutes an accord and
satisfaction and represents payment in full (both time and money) for all costs arising out of, or incidental to, the above Construction
Allowance Request. The Project/Program Manager signing below acknowledges that he/she is the person responsible for the monitoring and
administration of this contract, including ensuring all performance and reporting requirements.
Contractor's Company Name
Gibson & Associates Inc
Inspector/Inspection Supervisor
Program Manager
Assistant Director (Dept)
Assistant City Attorney
167,1
ATTEST:
r,n,.,ftes ,aednx
Jannette Goodall, City Secretary
Contractor (Name)
Trey Meador
MINIM
Date
10/31/22
Date
10/31/22
Date
10/31/22
Date
11/04/22
Contractor Signature
??: f hlerular
Project and Contract Compliance Manager
Senior Capital Project Officer
Ate. Pl.Gy�,
Director, Contracting Department (Dept)
Assistant City Manager
Date
10/28/22
Date
10/31/22
Date
10/31/22
Date
10/31/22
Date
11/04/22
Construction Allowance SUMMARY
Page 1 of 4
FORT
Project Name 12022 Bridge Rehabilitation Contract 2
Client Project # 1103456
Contractor Gibson and Associates Inc
City of Fort Worth
Construction Allowance Additions
PMI lretomiwa Otuyelu
Construction Allowance Submittal #
I I I
I City Sec # I 57453 I
Inspector' Robert Riley
Date 110/18/20221
ADDITIONS
ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total
1 4" White TY1 THERMOPLASTIC TPW 160.00000000 LF $8.21 $1,313.601
2 4" Yellow TY1 THERMOPLASTIC (DOUBLE YELLOW) TPW 120.00000000 LF $8.22 $986.401
3 Minimum Trip Charge TPW 1.00000000 LS $1,000.00 $1,000.001
TPW $3,300.00
UNIT 2 or Dept $0.00
UNIT 3 or Dept $0.00
UNIT 4 or Dept $0.00
Total Additions $3,300.00
Construction Allowance Additions
Page 2 of 4
FORT WORTH..
Project Name 1 2022 Bridge Rehabilitation Contract 2
Client Project # 1103456
Contractor' Gibson and Associates Inc
ITEM
City of Fort Worth
Construction Allowance Value
PMI Iretomiwa Otuyelu I
Construction Allowance Submittal #
1
I City Sec # I b/453
Inspector' Robert Riley
Date I 10/1612022 I
CONSTRUCTION ALLOWANCE VALUE BEING USED
DESCRIPTION Qty Unit Unit Cost Total
Construction Allowance Value
3 of 4
M/SBE for this Construction Allowance Request
M/SBE Sub
Type of Service Amount for this CAR
Total
Previous Construction Allowance Requests
$o.00 I
CAR # DATE
I
AMOUNT
1
Total
Construction Allowance MSBE Data
Page 4 of 4
From: Joe Montaomery
To: Otuvelu. Iretomiwa S
Cc: Cordova. Ron; Devon, Gary; Trey Meador; Mark Person; Taufa Tuoou; Riley. Robert D
Subject: FW: 2022 Bridge Rehabilitation Contract 2 CPN 103456- Meacham Blvd. Final Striping Proposal
Date: Wednesday, October 19, 2022 3:56:04 PM
Attachments: doc06287620221006142551.odf
CAUTION: This email originated from outside of the City of Fort Worth email system. Do not click any links or open
attachments unless you recognize the sender and know the content is safe.
Tommy,
We have reached out to multiple striping contractors and we received three quotes for this work.
The other two striping quotes we received are both $1,000 more than the quote we included with
our proposal.
The cost is high primarily due to mobilization costs for such a small amount of work. The striping sub
must pull crew and equipment from another project for less productive work. The price submitted
by American Striping is the minimum cost for which they are willing to perform the work and we
highly doubt a qualified striping contractor would perform this work for any less.
Please let us know how you would like to proceed or let us know if the City plans on performing this
work with its own forces.
Thank you,
Joe Montgomery
Project Coordinator
Office- (972) 557-1199
Cell- (214) 301-2474
Gibson & Associates, Inc.
11210 Ryliecrest Drive
Balch Springs, TX 75180
From: Joe Montgomery
Sent: Thursday, October 6, 2022 2:40 PM
To: Otuyelu, Iretomiwa S <Iretomiwa.Otuyelu@fortworthtexas.gov>
Cc: Cordova, Ron <Ronald.Cordova@fortworthtexas.gov>; Deyon, Gary
<Gary.Deyon@fortworthtexas.gov>; Trey Meador <treym@gibsonassoc.net>; Mark Person
<markp@gibsonassoc.net>; Taufa Tupou <taufat@gibsonassoc.net>; Riley, Robert D
<robert.riley@fortworthtexas.gov>
Subject: 2022 Bridge Rehabilitation Contract 2 CPN 103456- Meacham Blvd. Final Striping Proposal
Tommy,
Please see attached change order proposal as requested for replacement of existing striping at the
Meacham Blvd. bridge location. This will be limited to the area of the approach slabs and concrete
pavement we are currently working on. Please let us know if approved and we will proceed with
scheduling the work.
If you have any questions or need any additional information, please let me know.
Thank you,
Joe Montgomery
Project Coordinator
Office- (972) 557-1199
Cell- (214) 301-2474
Gibson & Associates, Inc.
11210 Ryliecrest Drive
Balch Springs, TX 75180
GIBSON & ASSOCIATES, INC.
Engineers and Contractors
11210 Ryliecrest
P.O. Box 800579
Balch Springs, Texas
75180-0579
972/557-1199
FAX 557-1552
October 6, 2022
Mr. Iretomiwa S. Otuyelu, E.I.T.
City of Fort Worth
Transportation and Public Works Department
City Hall, 2" d Floor
200 Texas Street
Fort Worth, TX 76102
RE: Project: 2022 Bridge Rehabilitation, Contract #2
Project No.: 103456
County: Tarrant
Dear Sir:
Below please find the pricing requested for replacement of the existing striping following
the approach slab and concrete pavement work at the Meacham Blvd. bridge location.
ADD Meacham Blvd. Final Striping
1 LS @ $3,000/LS x 10% markup
= $3,300.00
Please see attached quote from our striping subcontractor for reference. We would like to
request one additional day be added to the contract for this work.
If there are any questions regarding this matter, please call me.
Very truly yours,
GIBSON & ASSOCIATES, INC.
?p_ IYIAirjr-
Joe Montgomery
Project Coordinator
F
f--"
AMERICAN STRIPING
COMPANY
Billed To
GIBSON & ASSOCIATES
PO BOX 800579
11210 Rylie Crest
BALCI-I SPRINGS, TX 75180-0579
Specs
NONE SEEN
11551 Ravenview Road
Dallas, TX 75253
972-557-8565
estimating@americanstriping.net
Job Name
MEACI-IAM BLVD STRIPING
MEACIIAM BLVD
FORT WORTH, TX
Material Addenda/alts
TYI TI-IERMO
Description
BASED ON nil THERMOPLASTIC W/ FLAIL MILL GRINDING PREP
4" WHITE TY 1 THERMOPLASTIC
4" YELLOW TY1 TI-IERMOPLASTIC (DOUBLE YELLOW)
MINIMUM TRIP CHARGE
NONE
Proposal
Date Estimate #
10/6/2022
Terms
Net 30
EXCLUSIONS: 2 YEAR WARRANTY, ALL MAJOR TRAFFIC CONTROL, FLAGGERS, CRASH CUSHIONS, MMA,
3M TAPE, PREFAB TAPE, WATER BLASTING, SAND BLASTING, SODA BLASTING, SHOP BLAST PREP, PROFILE
& SHADOW PAVEMENT MARKINGS, RETROREFLECTIVE READINGS, MICROSURFACING, ALL SIGNS,
REMOVAL OF EXISTING PAVEMENT MARKINGS (NONE SHOWN), BONDS, PERMITS, TAX
CONDITIONS:
No Lced Materials. No Prior Cleaning, Exclude All Permits.
Insurance not to exceed sample/Evidence of Insurance.
Not responsible for damages to underground utilities.
Above Work Only. Additional work is for unit price.
No guarantee if Concrete less than 90 Days Old. No shop
drawings \vill be provided for striping layout.
DONNIE WILLIAMS - ESTIMATOR
Subtotal
Sales Tax (8.25%)
Total
8128
Rep
BW
Qty U/M
160 LF
120 LF
I LS
$3,000.00
$0.00
$3,000,00
Note: This proposal may be withdrawn by us if not accepted within 30 days. The above prices, specifications and conditions are satisfactory and are hereby
accepted. When signed, American Striping Company is authorized to proceed with the above work. This proposal becomes a part of any contract, existing
or proposed, will the person or company represented. Payment will be Net 30 days, or as outlined above.
Accepted By & Date:
FORT WORTH®
TRANSPORTATION AND PUBLIC WORKS
March 9, 2023
Gibson & Associates, Inc.
11210 Rylicrest Drive
Balch Springs, Texas 75180
RE: Acceptance Letter
Project Name: Bridge repair for Twenty Locations
Project Type: TPW bridge repairs
City Project No.: 103456
To Whom It May Concern:
On January 23, 2023 a final inspection was made on the subject project. There were no punch list items
identified at that time. The final inspection indicates that the work meets the City of Fort Worth
specifications and is therefore accepted by the City. The warranty period will start on March 9, 2023,
which is the date of the final inspection and will extend of two (2) years in accordance with the Contract
Documents.
If you have any questions concerning this letter of acceptance, please feel free to contact me at
Iretomiwa S. Otuyelu E.I.T. Graduate Engineer City of Fort Worth Transportation and Public Work
Department Tel: 817.392.6747 .
Sincerely,
Iretomiwa Otuyelu, Project Manager
Cc: Kevin Jackson, Inspector
Gary Deyon, Inspection Supervisor
Troy Gardner, Senior Inspector
Omar Elbagalati, Program Manager
CP&Y, Consultant
Gibson & Associates, Inc., Contractor
City of Fort Worth, Developer
File
E-Mail: TPW_Acceptance@fortworthtexas.gov
Rev. 08/20/19
CONSENT OF
SURETY COMPANY
TO FINAL PAYMENT
Conforms with the American Institute of
Architects, AIA Document G707
PROJECT:
(name, address)2022 Bridge Rehabilitation Contract 2
Fort Worth, TX
TO (Owner)
T
CITY OF FORT WORTH
1000 Throckmorton Street
Fort Worth TX 76102
CONTRACTOR: GIBSON & ASSOCIATES. INC.
OWNER ❑
ARCHITECT ❑
CONTRACTOR ❑
SURETY ❑
OTHER
Bond No K40427405
ARCHITECT'S PROJECT NO:
CONTRACT FOR:
2022 Bridge Rehabilitation Contract 2 - Project No. 103456
CONTRACT DATE: 3/8/2022
In accordance with the provisions of the Contract between the Owner and the Contractor as indicated above, the
there insert name and address of Surety Company)
FEDERAL INSURANCE COMPANY
202E Hall's Mill Road
Whitehouse Station NJ 08889
on bond of There insert name and address of Contractor)
GIBSON & ASSOCIATES. INC.
P.0 Box 800579
Balch Springs
TX 75180-0579
, SURETY COMPANY
, CONTRACTOR,
hereby approves of the final payment to the Contractor, and agrees that final payment to the Contractor shall not relieve
the Surety Company of any of its obligations to (here insert name and address of Owner)
CITY OF FORT WORTH
1000 Throckmorton Street
Fort Worth TX 76102
as set forth in the said Surety Company's bond.
IN WITNESS, WHEREOF,
the Surety Company has hereunto set its hand this
Attest:
(Seal): -4„ ---
27th day of March, 2023
FEDERAL INSURANCE COMPANY
Surety Company 7
.,
Signature of Authorized Representative
Robb) Morales
Title
, OWNER,
Attorney -in -Fact
NOTE; This form Is to be used as a companion document to AIA DOCUMENT G706, CONTRACTOR'S AFFIDAVIT OF PAYMENT OF DEBTS AND CLAIMS,
Current Edition
ONE PAGE
Each of the Chairman, the President and the Vice Presidents of the Company lshereby authorized to execute any Written Commitment for and on behalf of the Company, under the seal
of the Company or otherwise-
(2) Each duly appointed attorney -in -fact of the Company is hereby authorized to execute any Written Commitment far and on behalf of the Company, under the seal of the Company or otherwise,
to the extent that such action is authorized by the grant of powers provided for in such person's written appointment as such attorney -in -fact
Each of the Chairman. the Preskdent and the Vice Presidents of the Company is hereby authorized, for and on behalf of the Company, to appoint in writing any person the attorney -In -
fact of the Company with full power and autharityto execute, for and on behalf of the Company, under the seal of the Company or otherwise, such Written Commitments of the Company
as may he specified in such written appointment, which specification may he by general type ar class of Written Commitments or by specification of one ar more particular Written
Commitments,
(4) Each of the Chairman. the President and the Vice Presidents or the Company Is hereby authorised. for and on behalf of the Company, to delegate in writing to any other officer of the
Company the authority to execute, for and on behalf of the Company. under the Company's seal cr otherwtse, such Written Commitments of the Company as are specified in such written
delegation, which specification may be by general type or class of Written Commitments or by specification of one ar more particular Written Commitments.
(5] The signature of any officer or other person executing any Written Commitment nr appointment ar delegation pursuant to this Resolution, and the seal of the Company, may be affixed by
Facsimile on such Written Commitment or written appointment or delegation.
FURTHER RESOLVED, that the foregoing Resolution shall not be deemed to he an exclusive statement of the powers and authority of officers, employees and other persons to art for and on behalf nfthe
Company, and such Resolution shall not limit or otherwise affect the exercise of any such power or authority otherwise validly granted or vested,"
I, Dawn M. Chloros, Assistant Secretary of FEDERAL INSURANCE COMPANY, VIGILANT INSURANCE COMPANY, PACIFIC INDEMNITY COMPANY, WESTCHESTER FIRE INSURANCE
COMPANY and ACE AMERICAN INSURANCE COMPANY (the "Companies") do hereby certify that
(i) the foregoing Resolutions adopted by the Board of Directors of the Companies are true, correct and in full force and effect,
(ii] the foregoing Power of Attorney is true, correct and in full force and effect.
Given under my hand and seals of said Companies at Whitehouse Station, NI. this March 27, 2023
CHUBS
Power of Attorney
Federal Insurance Company I Vigilant Insurance Company I Pacific Indemnity Company
Westchester Fire Insurance Company I ACE American Insurance Company
Know All by These Presents, that FEDERAL INSURANCE COMPANY, an Indiana corporation, VIGILANT INSURANCE COMPANY, a New York corporation, PACIFIC INDEMNITY
COMPANY, a Wisconsin corporation, WESTCH ESTER FIRE INSURANCE COMPANY and ACE AMERICAN INSURANCE COMPANY corporations of the Commonwealth of Pennsylvania,
do each hereby constitute and appoint Don E. Cornell, Sophinie Hunter, Tina McEwan, Robbi Morales, Mikaela Peppers, Tonie Petranek, Ricardo J. Reyna,
Joshua Saunders and Kelly A. Westbrook of Dallas, Texas; Steven Dwain Brockinton of Little Rock, Arkansas ------- ----------
each as their true and lawful Attorney -in -Fact to execute under such designation in their names and to affix their corporate seals to and deliver for and on their behalf as surety therenn
or otherwise, bonds and undertakings and other writings obligatory in the nature thereof (other than bail bonds) given or executed in the course of business, and any instruments
amending or altering the same, and consents to the modification or alteration of any instrument referred to in said bonds or obligations.
In Witness Whereof, said FEDERAL INSURANCE COMPANY, VIGILANT INSURANCE COMPANY, PACIFIC INDEMNITY COMPANY, WESTCHESTER FIRE INSURANCE COMPANY
and ACE AMERICAN INSURANCE COMPANY have each executed and attested these presents and affixed their corporate seals on this 4ih day of February, 2022.
�JaLwm. ehilDA Z
I trv. n II t bit iti St t't,'I lry
STATE OF NEW JERSEY
County of Hunterdon
SS.
Stephen 11 I lanky .1 ice Prurient
On this 4ft day of February, 2022 before me, a Notary Public of New Jersey, personally came Dawn M. Chloros and Stephen M. Haney, to me known to be Assistant Secretary and Vice
President, respectively, of FEDERAL INSURANCE COMPANY, VIGILANT INSURANCE COMPANY, PACIFIC INDEMNITY COMPANY, WESTCHESTER FIRE INSURANCE COMPANY and ACE
AMERICAN INSURANCE COMPANY, the companies which executed the foregoing Power of Attorney, and the said Dawn M. Chloros and Stephen M. Haney, being by me duly sworn,
severally and each for herself and himself did depose and say that they are Assistant Secretary and Vice President, respectively, of FEDERAL INSURANCE COMPANY, VIGILANT
INSURANCE COMPANY, PACIFIC INDEMNITY COMPANY, WESTCHESTER FIRE INSURANCE COMPANY and ACE AMERICAN INSURANCE COMPANY and know the corporate seals
thereof, that the seals affixed to the foregoing Power of Attorney are such corporate seals and were thereto affixed by authority of said Companies; and that their signatures as such
officers were duly affixed and subscribed by like authority.
Notarial Sea]
KATHERINE J. ADELAAR
NOTARY PUBLIC OF NEW JERSEY
No, 2316085
Commisslen Expires July 10. 2024
Naary ti4tlle
CERTIFICATION
Resolutions adopted by the Boards of Directors of FEDERAL INSURANCE COMPANY, VIGILANT INSURANCE COMPANY, and PACIFIC INDEMNITY COMPANY on August 30, 20I6;
WESTCHESTER FIRE INSURANCE COMPANY on December 11. 2006; and ACE AMERICAN INSURANCE COMPANY on March 20,2009:
"RESOLVED, that the following authorizations relate to the execution, for and an behalf of the Company, of bonds, undertakings, recognizances, contracts and other written commitments of the Company
entered Into in the ordl nary course of business {each a "Written Commitment"):
(l)
(3)
•
lirv,n YI iId( in, .ltiwuantksTvtary
IN THE. EVENT YOU WISH TO VERIFY THE AUTHENTICITY OF THIS BOND OR NOTIFY US OF ANY OTHER MATTER, PLEASE CONTACT U5 AT:
Telephone 19091 903-3493 Fax f9091403. 3656 a -mail: suretv@chubb.com
Combined. FED-VIG-PI-WFIC-AAIC (rev. 11-19)
AFFIDAVIT
STATE OF TEXAS
COUNTY OF DALLAS
Before me, the undersigned authority, a notary public in the state
and county aforesaid, on this day personally appeared Alan C. Meador, III,
Vice President Of Gibson & Associates, Inc., known to me to be a credible
person, who being by me duly sworn, upon his oath deposed and said;
That all persons, firms, associations, corporations, or other
organizations furnishing labor and/or materials have been paid in full;
That the wage scale established by the City Council in the City of
Fort Worth has been paid in full;
That there are no claims pending for personal injury and/or
property damages;
On Contract described as;
2022 Bridge Rehabilitation Contract 2
BY / /
Alan C. Meador, III
Subscribed and sworn before me on this date 27th of March, 2023.
Notary Public
Dallas, Texas
PAM N DAVIS
:��tipPY PVe �i
?i•4 �� Notary Public, State of Texas
Trc Comm. Expires 03-30-2025
,,,„„so Notary ID 283117-2