HomeMy WebLinkAboutContract 58566-CO1CSC No. 58566-COI
FORT WORTH. City of Fort Worth
Change Order Request
Project Name 2023 Asphalt Resurfacing Contract 2 City Sec # 58566
Client Project #(s) 104178
Project Description Pulverization of existing street and 3" asphalt overlay at various locations.
Contractor Peachtree Construction Ltd Change Order # 1 Date 3/22/2023
City Project Mgr. I Tariqul Islam City Inspector Stephen Barnard
Dept.
Original Contract Amount
Extras to Date
Credits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Date
TPW
Totals
Contract Time
(CD)
$1,841,526.65
$1,841,526.65
210
$1,841,526.65
$1,841,526.65
210
Amount of Proposed Change Order
$16,395.90
$16,395.90
10
Revised Contract Amount $1,857,922.55
Original Funds Available for Change Orders $100,000.00
Remaining Funds Available for this CO $100,000.00
Additional Funding (if necessary)
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST+ 25%)
$1,857,922.55
220
$100,000.00
$100,000.00
0.89%
$2,301,908.31
JUSTIFICATION (REASONS) FOR CHANGE ORDE
This change order is to add $16,395.90 and 10 calendar days to contract # 58566 and with a revised contract amount of $1,857,922.55
During construction it was identified that Yuma Ave has concrete base in certain areas that need to be removed to complete pulverization process. Also, a 10 ft inlet top at Belle
PI is identified broken that needs replacement. These two items were not included in original contract and a quote was received from contractor for these additional works. The
quote for these items is verified with recent bids and found reasonable. Contractor's quotes are attached to this document as reference. To do this additional work 10 calendar
days are proposed to add to the contract. Adequate fund is available in this project to cover the change order cost.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full
(both time and money) for all costs arising out of, or incidental to, the above Change Order. The Project/Program Manager signing below acknowledges that
he/she is the person responsible for the monitoring and administration of this contract, including ensuring all performance and reporting requirements.
Contractor's Company Name
Contractor (Name)
Contract Signature
Peachtree Construciton Ltd
Brendan Taylor
171 ,k a„g,202313i30CDV
Mar 28, 2023
Inspector/Inspection Supervi
Date
Project and Contract Compliance Manager
Date
a�
Mar27,2023
C0.1
Mar 27,2023
Program Manager M
Date
Senior C ct Officer
Date
-rzx'�
Mar 28, 2023
- . �-
Mar 28, 2023
As 'stant Director (Dept)
Date
Mar 30, 2023
nt De t
„e ,,1p r1Mar30�0J08�OCOr
Date
Mar 30, 2023
Assistant City Attorney
D
Assistant City Manager
Date
Mar 30, 2023
llam on =o M 30 eCDn
Mar 30, 2023
Cou
M&C Number I N/A
ATTEST:
dg44pQ
Jannette Goodall, City Secretary
a0F FO°°RTaa
°
p,,�o 'p9�d
"1 0.10
0
Ovo g=0
Ppa * o° *�
o.°o
Qan� nEonSaaa
M&C Date Approved N/A
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
FORTWORTH City of Fort Worth
Change Order Additions
Project Name 2023 Asphalt Resurfacing Contract 2 City Sec # 58566
Client Project # 104178
Contractor Peachtree Construction Ltd PM Tariqul Islam Inspector Stephen Barnard
Change Order Submittal # 0 Date 3/22/2023
ADDITIONS
Remove concrete base
:rrrrrrrrr��� rr
� Replace 10 ft inlet top MEEK. ]
TPW r
FORTWORTH City of Fort Worth
Change Order Deletions
Project Name 2023 Asphalt Resurfacing Contract 2 City Sec # 58566
Client Project # 104178
Contractor Peachtree Construction Ltd PM Tariqul Islam inspectof Stephen Barnard
Change Order Submittal # =1 Date 3/22/2023
Change Order Deletions Page 3 of 4
Previous Change Orders
co # DATE AMOUNT
Total $0.00
Islam, Tariqul
From:
Brendan Taylor <btaylor@peachtreecon.com>
Sent:
Wednesday, March 8, 2023 2:20 PM
To:
Islam, Tariqul
Subject:
Change Order for Removal of Concrete
Attachments:
Backhoe 1 day.png; Breaker attachement 1 day.png; Concrete Saw 1 day.png; Munoz
Haul off quote.PNG; Remove 6-8IN Concrete paving.xlsx; Skidsteer 1 day.png; Remove
6-8IN Concrete Paving.docx
Follow Up Flag:
Follow up
Flag Status:
Completed
CAUTION: This email originated from outside of the City of Fort Worth email system. Do not click any links or open attachments
unless you recognize the sender and know the content is safe.
Ta ri q,
The price with our markup will be $31.95/ SY. JR West Approximates that there is 380 SY to remove. Attached is their
documentation for costs. Please let me know asap if the price is agreed to so that they can continue work on Yuma.
Thank You,
Brendan Taylor -Project Manager
Peachtree Construction, Ltd.
5801 Park Vista Circle
Keller, TX 76244
(817) 741-4658 Office
(817) 741-4648 Fax
(817) 915-7200 Cell
County:
JR WEST TEXAS CONCRETE
Change Order Derivation Worksheet
Tarrant
Project: 2023 Asphalt Project
Description of Work: Remove 6-8IN Concrete
Highway: Yuma Ave, Various
Date: 2/28/2023
Description
Unit
Quantity
Rate
Amount
LABOR
$400.00
labor 1
HR
20
$20.00
labor 2
HR
20
$20.00
$400.00
labor 3
HR
20
$20.00
$400.00
Operator
HR
20
$25.00
$500.00
Operator
HR
20
$25.00
$500.00
Foreman
HR
20
$30.00
$600.00
Superintedant
HR
5
$35.00
$175.00
HR
$0.00
$0.00
HR
$0.00
$0.00
HR
$0.00
$0.00
Base Labor =
$2,975.00
25% Labor Premium (O/T) =
$743.75
55% Labor Burden =
$1,636.25
EQUIPMENT
Skid Steer
DAY
2
$512.87
$1,025.74
Dump Truck
HR
16
$100.00
$1,600.00
Concrete saw
DAY
2
$417.39
$834.78
Backhoe
DAY
2
$699.99
$1,399.98
Breaker attachment
DAY
2
$269.77
$539.54
HR
$0.00
$0.00
HR
$0.00
$0.00
HR
$0.00
$0.00
HR
$0.00
$0.00
HR
$0.00
$0.00
HR
$0.00
$0.00
HR
$0.00
$0.00
HR
$0.00
$0.00
HR
$0.00
$0.00
HR
$0.00
$0.00
Base Equipment =
$5,400.04
15% Equipment Compensation =
$810.01
MATERIAL
CY
$0.00
LOAD
$0.00
LS
$0.00
TON
$0.00
LOAD
$0.00
Base Material =
$0.00
25% Material Compensation =
$0.00
Grand Total for Sheet =
$11,565.05
Total Estimated Quantity (SY) = 380.00
1 Cost Per SY = $30.43
From:
Brendan Taylor
To:
Islam. Tariaul
Subject:
Inlet Top Adjustment
Date:
Friday, March 10, 2023 9:29:23 AM
Attachments:
Inlet Adjusment.xlsx
CAUTION: This email originated from outside of the City of Fort Worth email system. Do not click any links or open
attachments unless you recognize the sender and know the content is safe.
Ta ri q,
Price to Adjust inlet top on Belle Place will be $4254.90 EA
Thank You,
Brendan Taylor -Project Manager
Peachtree Construction, Ltd.
5801 Park Vista Circle
Keller, TX 76244
(817) 741-4658 Office
(817) 741-4648 Fax
(817) 915-7200 Cell
County:
JR WEST TEXAS CONCRETE
Change Order Derivation Worksheet
Tarrant
Project: 2023 Asphalt Project
Description of Work: Inlet
Highway: Yuma Ave, Various
Date: 3/8/2023
Description
Unit
Quantity
Rate
Amount
LABOR
$240.00
labor 1
HR
12
$20.00
labor 2
HR
12
$20.00
$240.00
Operator
HR
3
$25.00
$75.00
Foreman
HR
12
$30.00
$360.00
Superintedant
HR
3
$35.00
$105.00
HR
$0.00
$0.00
HR
$0.00
$0.00
HR
$0.00
$0.00
HR
$0.00
$0.00
HR
$0.00
$0.00
Base Labor =
$1,020.00
25% Labor Premium (O/T) =
$255.00
55% Labor Burden =
$561.00
EQUIPMENT
Skid Steer
DAY
1
$512.87
$512.87
Breaker attachment
DAY
1
$269.77
$269.77
DAY
$0.00
$0.00
DAY
$0.00
$0.00
DAY
$0.00
$0.00
HR
$0.00
$0.00
HR
$0.00
$0.00
HR
$0.00
$0.00
HR
$0.00
$0.00
HR
$0.00
$0.00
HR
$0.00
$0.00
HR
$0.00
$0.00
HR
$0.00
$0.00
HR
$0.00
$0.00
HR
$0.00
$0.00
Base Equipment =
$782.64
15% Equipment Compensation =
$117.40
MATERIAL
Concrete (3 CY Minimum)
CY
3.00
$151.00
$453.00
Rebar
LS
1.00
$400.00
$400.00
Forms
LS
1.00
$200.00
$200.00
TON
$0.00
LOAD
$0.00
Base Material =
$1,053.00
25% Material Compensation =
$263.25
Grand Total for Sheet =
$4,052.29
Total Estimated Quantity (EA) = 1.00
1 Cost Per EA = $4,052.29
FORT WORTH.
Routing and Transmittal Slip
Transportation & Public Works
Department
DOCUMENT TITLE: 2023 Asphalt Resurfacing Contract 2
M&C: N/A CPN: 104178 CSO:
DOC#:
Date: 3-22-2023
To:
Name
Department
Initials
Date Out
1.
Valentina Riera
TPW - initial
Mar 27, 2023
2.
Brendan Taylor
Vendor - signature
Mar 28, 2023
3.
1 Stephen Barnard
TPW - signature
40E
Mar 27, 2023
4.
Tariqul Islam
TPW - signatures—
Mar 27, 2023
5.
Omar Elbagalati
TPW - signatures
Mar 28, 2023
6.
Leon Wilson
TPW - initial
Mar 28, 2023
7.
Michael Owen
TPW - signature
Mar 30, 2023
8.
Lauren Prieur
TPW - signature
LLP
Mar 30, 2023
9.
Doug Black
Legal - signature
011
D.10.
Mar 30, 2023
William Johnson
CMO - signature
W
M a r 30, 2023
11.
Jannette Goodall
CSO - signature
7,11
JSG
Mar 30, 2023
12.
TPW Contracts
TPW
DOCUMENTS FOR CITY MANAGER'S SIGNATURE: All documents received from any
and all City Departments requesting City Manager's signature for approval MUST BE ROUTED
TO THE APPROPRIATE ACM for approval first. Once the ACM has signed the routing slip,
David will review and take the next steps.
NEEDS TO BE NOTARIZED: ❑YES ®No
RUSH: ❑YES ®No SAME DAY: ❑YES ❑No NEXT DAY: ❑YES ❑No
ROUTING TO CSO: ®YES ❑No
Action Required:
❑ As Requested
❑ For Your Information
® Signature/Routing and or Recording
❑ Comment
❑ File
❑ Attach Signature, Initial and Notary Tabs
Return To: TPWContracts kFortWorthTexas.gov at ext. 7233 for pick up when completed.