NOTICE OF PROJECT COMPLETION
(Developer Projects)
The Transportation and Public Works Department upon the recommendation of the Project
Manager has accepted the following project as complete:
Project Name: Retreat at Fossil Creek Phase 1
City Project No.: 103050
Improvement Type(s): ❑ Paving ❑ Drainage X❑ Street Lights ❑ Traffic Signals
Original Contract Price:
$347,070.00
Amount of Approved Change Order(s):
Revised Contract Amount:
Total Cost of Work Complete:
$347,070.00
o Sancen (ADr 7. 202310:33 CDT
Contractor
Superintendent
Title
Conatser Construction TX., LP
Company Name
Project Inspector
Vctor V Toni m J;- T E
Project Manager
1�a,�,r.
Rebecca Diane Owen (Apr 7, 202311:07 CDT)
CFA Manager
X
Lauren Pri— (Apr 7, 202311:08 CDT)
TPW Director
Will am Johnson (Ao(7.202315,56 CDT)
Asst. City Manager
Apr 7, 2023
Date
Apr 7, 2023
Date
Apr 7, 2023
Date
Apr 7, 2023
Date
Apr 7, 2023
Date
Apr 7, 2023
Date
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
Page 1 of 2
Notice of Project Completion
Project Name: Retreat at Fossil Creek Phase 1
City Project No.: 103050
City's Attachments
Final Pay Estimate ❑x
Change Order(s): ❑ Yes ❑x N/A
Contractor's Attachments
Affidavit of Bills Paid
Consent of Surety
Statement of Contract Time
Contract Time 200 WD Days Charged: 322
Work Start Date: 9/15/2021 Work Complete Date: 4/3/2023
Completed number of Soil Lab Test: 1025
Completed number of Water Test: 30
Page 2of2
FoRTWoRTH
CITY OF FORT WORTH
FINAL PAYMENT REQUEST
Contract Name RETREAT AT FOSSIL CREEK PHASE I
Contract Limits
Project Type ST LIGHT
City Project Numbers 103050
DOE Number 3050
Estimate Number I Payment Number 1 For Period Ending
City Secretary Contract Number 56019
Contract Date 7/14/2021
Project Manager NA
Contractor CONATSER CONSTRUCTION TxLP
5327 WICHITA ST
FORT WORTH, TX 76119
Inspectors GLOVER / WALKER
Contract Time
Days Charged to Date
Contract is 100.00
4/3/2023
WD
20WD
322
Complete
Tuesday, April 4, 2023 Page 1 of 4
City Project Numbers 103050
Contract Name RETREAT AT FOSSIL CREEK PHASE I
Contract Limits
Project Type ST LIGHT
Project Funding
ST LIGHT
Item
Description of Items
Estimated Unit
No.
Quanity
1
2" CONDT PVC SCH 80
5158 LF
2
TYPE 11 STREET LIGHT FOUNDATION
60 LF
3
TYPE 11 STREET LIGHT POLE
60 LF
4
TYPE 33B STREET LIGHT ARM
60 LF
5
TYPE R2 STREET LIGHT
57 EA
6
----------------------
TYPE R4 STREET LIGHT
3 EA
Sub-Total of
Previous Unit
DOE Number 3050
Estimate Number 1
Payment Number 1
For Period Ending 4/3/2023
Unit Cost
Estimated
Completed
Completed
Total
Quanity
Total
$15.00
$77,370.00
5158
$77,370.00
$1,240.00
$74,400.00
60
$74,400.00
$2,240.00
$134,400.00
60
$134,400.00
$620.00
$37,200.00
60
$37,200.00
$400.00
$22,800.00
57
$22,800.00
$300.00
---------------
$900.00
3
$900.00
$347,070.00
$347,070.00
Tuesday, April 4, 2023 Page 2 of 4
City Project Numbers 103050
Contract Name RETREAT AT FOSSIL CREEK PHASE I
Contract Limits
Project Type ST LIGHT
Project Funding
Contract Information Summary
Original Contract Amount
Change Orders
Total Contract Price
DOE Number 3050
Estimate Number I
Payment Number 1
For Period Ending 4/3/2023
$347,070.00
$347,070.00
Total Cost of Work Completed $347,070.00
Less % Retained $0.00
Net Earned $347,070.00
Earned This Period $347,070.00
Retainage This Period $0.00
Less Liquidated Damages
Days @ / Day
LessPavement Deficiency
Less Penalty
Less Previous Payment
Plus Material on Hand Less 15%
Balance Due This Payment
$0.00
$0.00
$0.00
$0.00
$0.00
$347,070.00
Tuesday, April 4, 2023 Page 3 of 4
City Project Numbers 103050
Contract Name RETREAT AT FOSSIL CREEK PHASE I
Contract Limits
Project Type ST LIGHT
Project Funding
Project Manager NA
Inspectors GLOVER / WALKER
Contractor CONATSER CONSTRUCTION TxLP
5327 WICHITA ST
FORT WORTH, TX 76119
DOE Number 3050
Estimate Number 1
Payment Number 1
For Period Ending 4/3/2023
City Secretary Contract Number 56019
Contract Date
7/14/2021
Contract Time
200 WD
Days Charged to Date
322 WD
Contract is .000000
Complete
CITY OF FORT WORTH
SUMMARY OF CHARGES
Line Fund Account Center Amount Gross Retainage Net
Funded
Total Cost of Work Completed $347,070.00
Less % Retained $0.00
Net Earned $347,070.00
Earned This Period $347,070.00
Retainage This Period $0.00
Less Liquidated Damages
0 Days @ $0.00 / Day
$0.00
LessPavement Deficiency
$0.00
Less Penalty
$0.00
Less Previous Payment
$0.00
Plus Material on Hand Less 15%
$0.00
Balance Due This Payment
$347,070.00
Tuesday, April 4, 2023 Page 4 of 4
FORTWORTH.
''no,
TRANSPORTATION AND PUBLIC WORKS
April 3, 2023
CONATSER CONSTRUCTION ,TXJP
5327 WICHTIA STREET
FORT WORTH,TX. 76119
RE: Acceptance Letter
Project Name: RETREAT AT FOSSIL CREEK PHASE 1
Project Type: STREET LIGHTS
City Project No.: 103050
To Whom It May Concern:
On February 24, 2023 a final inspection was made on the subject project. There were punch list items
identified at that time. The punch list items were completed on April 3, 2023. The final inspection and
the corrected punch list items indicate that the work meets the City of Fort Worth specifications and is
therefore accepted by the City. The warranty period will start on April 3, 2023, which is the date of the
punch list completion and will extend of two (2) years in accordance with the Contract Documents.
If you have any questions concerning this letter of acceptance, please feel free to contact me at 817-
392-7830.
Sincerely,
Vlcta- V. 7oPN8Po ]Y. T U.
Victor Tornero, Project Manager
Cc: Eddie Walker, Inspector
Mike Glover, Inspection Supervisor
Daniel Roy, Senior Inspector
Victor Tornero, Program Manager
LJA ENGINEERING, Consultant
Conatser Construction,TX.LP., Contractor
Benchmark Acquisitions,LLC., Developer
File
E-Mail: TPW_Acceptance@fortworthtexas.gov
Rev. 8/20/19
STATI. OF TEXAS
P farc me. the undersigned autwrity. a Nfliary Public in the state and county afnremid,
on this day peTsDmIly appearcd Bra& Huggins, ]E sident of Conamer Management Grotip, Inc..,
gcncml partner of Csmomgr C'ona wtion M.-LE,, known to me to be a credible pcnr , who
Wing by me duly sworn. upon his oath deposed and said:
71ml all persons, rum% mmiatimms. corpamtions or other cgAaixatiam furnishing
labor aD&(r materials have heka pad in full*
Mal the wage "t estal3liAM by the City Council in the City of Fort Worth, hw
hcca paid in full; and
That iltiere arc no claims pending for personal injury am&ur property damages.
On Conirmt cie writx-d as:
RE-'REAT AT FOSSIL CREEK PH. i
57REI+T LI Jff IMPROVEMENTS
CPA PRI N, 21-D 7
CITY PROJECT M 103050
CITY OF FORT WORTH
STATE OF T EMAS
('0NA'r491'R CONSTRUCTION TX LF
Brook Hu0g
Subscribed and sworn to before me this 5"" day of lamuary. 2023.
_ s -
irw Pk�
• �+pRen C 1136atrl5
Notary Public in Tarrard C au*. Teau
CONSENT OF
SURETY COMPANY
TO FINAL PAYMENT
Conforms with the American Inatr[uie of
ArphftwoU. AIIA Document 0707
PROJECT:
Iname, add re5z�R@rental 117C4SIN C:%h4k I5h$5� 1
Fort 4YOrth. Tx
TO (Owner)
OWNER
❑
ARCHlITECT
CONTRACTOR
C
SURETY
❑
OTHER
IRETREA-i A7 FMIL GREETS, LTD AND THE CITY —1 AA0"1TKT-' RS ECT 1140: GFA Nc� 21 7
OF FORT MRTH CONTRACT FOAL
10410 tir04rrrvrF Lift Blvd SVme1 Llgwling :mpmvemernr for Relreal ai Fobiil Owerb - Phone 1
t2-90n TX 77DBS --J CONTPAOT GATE:
CONTRACTOR, CONATSIE R CONSTRUCTION TX L P
In smotdimee with thr proiristons of the Coniract between the Owner and t11e Contractor as indicated 6bvvo, ft
om Mrr+wt rr-y and WRIMMa4T S"V Cafflarnxl
EERKLEV INSURANCE COMPANY
47:55ttemb= Rwo
*r"'Imc,h Cfi W630 SURETY COMPANY
on borld Uf #w% ..=j rMnm vid a#n4 u+ Cmrrrctwl
CONATSIER CONSTROCTION TX, L P
5327 V knit# St
FM Worth TX 79111116-6M5 . CONTRACTOR,
herrby approves of the F1nid payment to the Cont I im and ogre" That final paym-tw to the Contrwtot shtrli hot ttlkV
the Surety Company of any of its obh&stions to uuri vnrn rurr,..�tl .aenar � �w*iNl
RETREAT AT FOSSIL CREEK, LTD AND THE CrT'r OP FORT WORTH
7¢410 MROerrMOte �-ihkt Rbd#
Hauam Tx 77DBS , OWNER,
sm se forth in the se.id Surcry Co npany's bond.
IN WJTNESS, WHEREOF,
the Surcty Company !ms hmanto sct its hand this
A
4Lrl day of January, 2023
B ERKLEY INSURANCE COMPANY
Surety Company
Signam r of Authorized Represcntativc
7itic
PMM TIN kft 16 GI 0* awl in s uEn—Pn d4 ;J-4111 to wig, O0CVh1FNr 47Q*_ C0&TNAr_T0+r'S AFFID^YiT OF PAYM$FR Of OEM AND CLAM41,
CUM* Edwam
OH! PAS!