HomeMy WebLinkAboutContract 57476-CO1CSC No. 57476-CO1
City of Fort Worth
Change Order Request
PfojeGtNarne:j Eagle Mountain Woslsldo Water Treatment Plants Weatherproof Enclosures City Sec No,: F 67476
ProlectNo.(s): 66020/06004301103336 DOE No, I N/A 7 CityP(oj,Ko-:j 103335
Project Descdption:j Weatherproof Enclosures at Eagle Mountain and Weslridge Water Treatment Plants
Contractor: CrescenlConslruclors,[no. ChangeOrderfl L_ Date; 1 3/27/2023
City Prolect Mgr. I Dena Johnson, PE Clly Inspeclor: I Nathan Gray
Phone Number. (817) 392-7808 Phone Number. (817) 392 4961
Dept,
Original Contract Amount
Extras to Date
Credits to Date
Pending Chenge Orders (in M&C Process)
Contract Cost to Date
Water
Sower
Totals
ContractTlme
Colander days)
$1,897,000.00
$7,897 000.00
400
$7,897,000.00
$7,897 000.00
400
Amount of Pronosed Channe Order
72,604.0D
72.604.00
090
Original Funds Available for Change Orders
Remaining Funds Avallable for this CO
Additional Funding (If necessary)
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT 0.02%.
MAXALLOWA6LECONTRACTAMOUNT (ORIGINAL CONTRACT COST+26Y) 9,871,250.00
JUSTIFICATION+(REASONS) FOR, CHANGE, ORDER,.,..,,
Change Order No.1 provides for the following that were at the Eagle Mountain Water Treatment Plant H Igh
Service Pump Station No.1:
Removal and relocation of existing conflicting concrete footing
core drilling and removal of the existing concrete encasement (over a plant 54-inch water main) that is in
conflict with the westgrade beam of the proposed enclosure
Staff concurs with the contractors request for 90 calendar days for the change order,
His understood and agreed thatihe acceptance of this Change Order by the contractor consgtutes an accord and satlsfactlon and represents payment
In fug (both time and money) for all costs adsingtoul of, or Incidental to, the above Change Order.
Contractor's Company Name
Contractor Name
nlra4 r qgvlure
Date
Crescent Constructors, Inc,
Todd+l* >; lO -
' J_
A /2q / 3
Inspector
Dale
Pro ectMana
Date
3/29/2023-�
3/29/23
Director(Water D l
Date
Con traction Wpeivisor(Water De
Date
gpHevtrav„I�r ! •J.
Mar 31,2023
'SenlorAssistant City Attorney
Dale
AssIslant Qy Manager
Date
9iC
Apr 3, 2023
r4 2
Council Action If Re titre
M&C Number NIA M&C Date Approved WA
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
Ff.)RT WORTH City of Fort Worth
Change Order Additions
Project Name I Eagle Mountain Westside Water Treatment Plants Weatherproof Enclosures City Sec No.: 57476
Project No.(s): 1 56020 / 0600430 / 103335 1 DOE No. N A City Proj. No.: 103335
Project Weatherproof Enclosures at Eagle Mountain and Westridge Water Treatment Plants
Description
FOP,— ' WORTH City of Fort Worth
Change Order Deletions
Project Name Eagle Mountain Westside Water Treatment Plants Weatherproof Enclosures City Sec No,: 57476
Project No,(s): 5602010600430 / 103335 1 DOE No, N/A City Proj, No,: 103335
Project Description
Weatherproof Enclosures at Eagle Mountain and Westridge Water Treatment Plants
Contractor Crescent Constructors, Inc, Change Order: F-1-1 Date 3/2712023
City Project Mgr. Dena Johnson, PE City Inspector: Nalhan Gray —�
DELETIONS
Page 3 of 4
MMBE Breakdown for this Change Order
MWBE Sub I Type of Service I Amount for this CO
Total I $0.00
Previous Change Orders
co # DATE AMOUNT
Total 1 $0.00
Page 4 of 4
CONTRACT MODIFICATION REQUEST: 1
PROJECT: Eagle Mountain & Westside Water Treatment Plant DATE:
Pump Station Weatherproof Enclosures
CS#57476
ATTENTION: Dena Johnson, PE
City of Fort Worth
Attention:
The following change in contract on this project is proposed:
A breakdown of cost SHALL he attached.
Work shall not commence until authorized by the OWNER.
Description of the Proposed Change & Clarifications
Remove and relocated duct bank in way of the concrete footing at Eagle Mountain HSPS # 1,
See RFI-015
TOTAL AMOUNT 1 $ 82,459
12/12/2022
E ,a a"
Todd C. Hoff
All work shall be in accordance with the terms, stipulations, and conditions of the Recommended for approval 311012023
original Contract Documents. If the work hereln provided for Is Approved by
Change Order, the time of completion will be:
Increased 13y 15 Calendar Days
Decreased
Unchanged CDM Smith
ACCEPTED
City of Fort Worth Date
❑ REJECTED
CHANGE ORDER SUMM
Front Sheet
Eagle Mountain & Westside Water Treatment Plant Pump Station Weatherproof Enclosures
CHANGE DESCRIPTION: Relocate duct bank at Eagle Mountain HSPS # 1
CONTRACTORS MODIFICATION REQUEST 11001 Job #: 1 2022-03
Description
Labor
Material
Equipment
Subcontract
Other
Total
DIRECT COSTS
0,150
3,027
4,590
47,202
63,969
LABOR BURDEN & FRINGES 55%
5,033
6,033
SMALL TOOLS 5% OF LABOR
732
732
SAFETY SUPPLIES 3% OF LABOR
275
275
SUBTOTALS
14,103
3 027
4,690
47,202
1,007
70,000
CONTRACTOR MARKUP
2,127
454
609
7,000
10,350
BONDS & INSURANCE 3%
2,100
TOTAL
02,459
CLARIFICATIONS:
1 Remove Duct Bank
2 Install relocated duct bank
3 Back011 new duct bank
4 Haul off debri from removed duclbank
CONTRACT MODIFICATION REQUEST: 4
PROJECT: Eagle Mountain & Westside Water Treatment Plant DATE:
Pump Station Weatherproof Enclosures
CS#57476
ATTENTION: Dena Johnson, PE
City of Fort Worth
Attention:
The following change in contract on this project is proposed:
A breakdown of cost SHALL be attached.
HMork shall not commence mail mahorized by the 01 ME .
Description of the Proposed Change & Clarifications
3/612023
Core Drill Demo concrete pipe encasement in the way of the west grade beam @ Eagle Mountain HSPS # 1.
See RFI-025
ENGINEER COMMENTS
1.The minimum core drilling diameter shall be 22", and contractor shall coordinate with the drilled shaft sub -contractor for the required temporary casing
diameter, If needed,
2,Installed drilled shafts shall not have any direct contact with the existing concrete material. Prior to the drilled shaft concrete installation, Constructor must
apply an approximately 1.5" thick, soil separalorCoint filler material between the existing concrete block and proposed drilled shaft circumferencefinlerface. A
vertical slippage must be provided to avoid load transfer between the two concrete members (existing and proposed).
3.Conlactor shall coordinate with the GPR company prior to the construction to confirm there are no utilities within the concrete areas being removed.
Progressive scanning, drilling, and selective demo/removal of the existing concrete in short segments may be required.
TOTAL AMOUNT $ 70,745
�. 700
All work shall be In accordance with the terms, stipulations, and conditions of the
original Contract Documents. If the work herein provided for Is Approved by
Change Order, the time of completion will be:
Increased
Decreased
Unchanged
ACCEPTED
By 75 Calendar Days
m
Todd C. Hoff
Recommended for approval with comments
311012023
CDM Smith
City of Fort Worth Date
❑ REJECTED
CHANGE ORDER SUMMARY
Front Sheet
Eagle Mountain & Westslde Water Treatment Plant Pu1np Station Weatherproof Enclosures
CHANGE DESCRIPTION: Core Drill Concrete Pipe Enasement Eagle Mountain HSPS it 1
CONTRACTORS MODIFICATION REQUEST t1004 Job It: 1 2022.03
Doscrlptlon
Labor
Material
Equipment
Subcontract
Other
Total
DIRECT COSTS
1,700
7,631
49,524
58,055
LABOR BURDEN & FRINGES 55%
035
935
SMALL TOOLS 0%OF LABOR
136
136
SAFETY SUPPLIES 3%OF LABOR
51
61
SUBTOTALS
2,636
7,631
49,524
107
59,977
CONTRACTOR MARKUP
395
1,145
7,429
8,969
BONDS & INSURANCE 3%
1,799
TOTAL
-
70,745
CLARIFICATIONS:
1
2
3
4
CONTRACT MODIFICATION REQUEST: 2
PROJECT: Eagle Mountain & Westside Water Treatment Plant DATE: 1 3/612023
Pump Station Weatherproof Enclosures
CS#57476
ATTENTION: Dena Johnson, PE C R IT
City of Fort Worth
Attention:
The following change in contrnct on this project is proposed:
A breakdown of cost SHALL he attached.
)York shall not connnence until authorized by the OWNER,
llescription otthe Proposed C;liange & C;laritications
Delete cable tray at Eagle Mountain HSPS # 1.
TOTAL AMOUNT $ 700 loll
Todd C. Hoff
All work shall be In accordance with the terms, stipulations, and conditions of the
original Contract Documents. If the work herein provided for Is Approved by
Change Order, the time of completion will be:
Increased By
Decreased
Unchanged
11 ACCEPTED
❑ REJECTED
Calendar Days
Recommended for approval 311012023
7/-W-
CDM Smith
I
i
City of Fort Worth Date
CHANGE ORDER SUMMARY
Front Sheet
Eagle Mountain & Westside Water Treatment Plant Pump Station Weatherproof Enclosures
CHANGE DESCRIPTION: Dlete Cable Tray at Eagle Mountain HSPS # 'I
CONTRACTORS MODIFICATION REQUEST fl002 Job m 2022.03
Description
Labor
Materlal
Equlpmant
Subcontract
Other
Total
DIRECT COSTS
7CO
700
LABOR BURDEN & FRINGES 66%
SMALL TOOLS S% OF LABOR
SAFETY SUPPLIES 3% OF LABOR
SUBTOTALS
700
700
CONTRACTOR MARKUP
BONDS & INSURANCE 3%
TOTAL
700
CLARIFICATIONS:
1
2
3
4
.Contract Compliance Manager
By signing I acknowledge that I am the person responsible
for the monitoring and administration of this contract, including
ensuring all performance and reporting requirements.
Dvia 7oksoji
Signature
Dena Johnson
Name of Employee
Project Manager
Title
ATTEST:
Jannette Goodall
City Secretary
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
03/30/2023
CPN103335
Eagle Mountain Westside Water Treatment Plants Weatherproof Enclosure
Change Request 1 Notes
Staff has reviewed the change order price and considers it to be fair and reasonable.