HomeMy WebLinkAboutContract 58528-CO1CSC No. 58528-COI
F"a-r WORTH City of Fort Worth
Change Order Request
Project Name: Sanitary Sewer Rehabilitation Contract 98 City Sec No.: 58528
Project No.(s): 56002-0600430-0700430-0200430-5740010 M&C: 22-0888 City Proj. No.: CO2719
Project Description: Water, sanitary sewer, and paving Improvements in the Northside Neighborhood.
Contractors) Woody Contractors
Change Order # 0
Date: 3/27/2023
City Project Mgr.1 Suzy Abbe
City Inspector: I Charles Hayes
Phone Number: 817-392-8209
Phone Number: 682-213-0240
Dept. Water
Sewer Paving
Totals Contract Time
(Calender days)
Original Contract Amount $3,043,559.00
$3,253,980.00 $957,884.25
$7,255,423.25 550
Extras to Date
Credits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Date
550
Amount of Proposed Change Order
$6,200.00
$7,053.00
$0.00
$13,253.00
Revised Contract Amount $6,200.00
$7,053.00 $0.00
$13,253.00
550
Original Funds Available for Change Orders $121,742.00
$130,159.00 $57,473.00
$309,374.00
Remaining Funds Available for this CO $121,742.00
$130,159.00 $57,473.00
$309,374.00
Additional Funding (if necessary)
0.18%
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL
CONTRACT COST + 25%)
$9,069,279.06
JUSTIFICATION (REASONS) FOR CHANGE ORDER
Change order No. 1 provides for the following:
• New 8" water gate valve at the corner of NE 21 st Street and Grove Street to allow for testing.
One additional exploratory excavation to locate a main and size an insert -a -valve for the 4-inch temporary water service.
• Pay item for gravel in alleys.
• Substitution of green C900, SDR 18 pipe for ductile iron pipe.
Substitution of 16" DIIP sewer pipe for 15" SDR 26 in shallow installation.
• Removal of manhole at STA 4+96.76 on L-638 and resulting adjustments in total linear feel of pipe, and extra depth manhole, and coating.
• Additional epoxy coating and/or hydraulic slide to meet City design policy.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment
in full (both time and money) for all costs arising out of, or incidental to, the above Change Order.
Contractor's Company Name
Contractor Name
Con
Date
Woody Contractors
Troy Woody
Inspector
Dale
Project Manp9qr
Date
3/30/23
3/31/2021
Director (Water Dept
Date
Construction Supervisor (TPW Dept)
Date
hw-&Ophe�
mar 31, 2023
Joe Rogers
3/31 /23
Senior Assistant City Attorney
Date
Assistant City Manager
Date
Mpg,,
JApr12,2023
1-72fl a ✓ -
pr 13, 2023
Council Action (If Required)
M&C Number N/A
M&C Date Approved
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
FORT WoRT" City of Fort Worth
Change Order Additions
Project Name Sanitary Sewer Rehabilitation Contract 98 City Sec No.: 58528
Project No.(s): 56002-0600430-0700430-0200430-5740010 DOE No. 22-088 City Proj. No.: CO2719
Project
Description
Water, sanitary sewer, and paving Improvements in the Northside Neighborhood,
Contractor Woody Contractors Change Order:= Date: 3/27/2623
City Project Mgr. Suzy Abbe City Inspector Charles Hayes
ADDITIONS
ITEM
DESCRIPTION
DEPT
Qty
Unit
Unit Cost
Total
26
8" Gate Valve
Water
1.00
EA
$2,600.00
$2,600.00
34
Temporary Water Service (4" Service)
Water
1.00
LS
$44,400.00
$44,400.00
49
Exploratory Excavation of Existing Utilities
Water
1.00
EA
$1,000.00
$1,000.00
1 B
16" DIP Sewer
Sewer
180.00
LF
$294.00
$52,920.00
17
4' Extra Depth Manhole
Sewer
1.00
VF
$220.00
$220.00
19
Epoxy Manhole Liner Warren Chesterton - 4' Sewer MH
Sewer
9.00
VF
$380.00
$3,420.00
29
8" C900 DR 18, Green PVC Acceptable Backfill
Sewer
477.00
LF
$200.00
$95,400.00
30
8" C900 DR 18, Green PVC CSS Backfill
Sewer
38.00
LF
$250.00
$9,500.00
31
8" C900 DR 18, Green PVC CLSM Backfill
Sewer
30.00
LF
$393.00
$11,790.00
32
8" C900 DR 18, Green PVC Carrier Pipe
Sewer
20.00
LF
$250.00
$5,000.00
34
Gravel Alley
Sewer
1,140.00
LF
$10.70
$12,198.00
Rage i of i
Water
$48,000.00
Sewer
$190,448.00
Paving
Additions Sub Total
$238,448.00
FORT ` "iz-Fm City of Fort Worth
Change Order Deletions
Project Name Sanitary Sewer Rehabilitation Contract 98 City Sec No.: 5II528
Project No.(s): 56002-0600430-0700430-0200430-5740010 DOE No. 22-08 City Proj. No.: CO2719
Project Description
Water, sanitary sewer, and paving Improvements in the Northside Neighborhood.
Contractor Woody Contractors Change Order: FTI Date 3/27/2023
City Project Mgr. Suzy Abbe City Inspector: Charles Hayes
DELETIONS
ITEM
DESCRIPTION
DEPT
Qty
Unit
Unit Cost
Total
34
Temporary Water Service (4" Service)
Water
1.00
LS
$41,800.00
$41,800.00
1 B
16" Sewer SDR 26 CSS Backfill
Sewer
180.00
LF
$233.00
$41,940.00
5A
8" DIP Sewer, Acceptable Backfill
Sewer
457.00
LF
$219.00
$100,083.00
6A1
8" DIP Sewer, CLSM Embedment, CSS Backfill
Sewer
38.00
LF
$269.00
$10,222.00
6A2
8" DIP Sewer Carrier Pipe
Sewer
20.00
LF
$269.00
$5,380.00
7A
8" DIP Sewer, CLSM Embedment, CLSM Backfill
Sewer
30.00
LF
$412.00
$12,360.00
8
8" PVC SDR-26 Sewer, Acceptable Backfill
Sewer
35,00
LF
$166.00
$5,810.00
13
4' Manhole
Sewer
1.00
EA
$7,600.00
$7,600.00
Pages 1 of 1
Water
$41,800.00
Sewer
$183,395.00
Paving
Deletions Sub Total
1$225,195.00
MMBE Breakdown for this Change Order
MWBE Sub I Type of Service I Amount for this CO
Total 1 $0.00
Previous Change Orders
Page 1 of 1
3/31/2023
Sanitary Sewer Rehabilitation Contract 98
CSC: 58528
CPN:CO2719
Change Order 1 Notes
Staff has reviewed the requested prices and considers them to be fair and reasonable.
.Contract Compliance Manager
By signing I acknowledge that I am the person responsible
for the monitoring and administration of this contract, including
ensuring all performance and reporting requirements.
Signature
Suzanne Abbe
Name of Employee
Senior Engineer, Capital Project Delivery
Title
Jannette Goodall
City Secretary
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX