NOTICE OF PROJECT COMPLETION
(Developer Projects)
The Transportation and Public Works Department upon the recommendation of the Project
Manager has accepted the following project as complete:
Project Name: Tradition Central Phase 2B
City Project No.: 103142
Improvement Type(s): x❑ Paving ❑x Drainage ❑ Street Lights ❑ Traffic Signals
Original Contract Price:
$1,196,750.00
Amount of Approved Change Order(s):
Revised Contract Amount:
Total Cost of Work Complete:
$1,196,750.00
57— P�—
Contractor
VP
Title
SAI Construction
Company Name
9 - Z_-
JasWi Brad ley(Apr 21, 202307:56 CDT)
Project Inspector
Project Manager
9L , An
Rebecca Diane Owen (Apr 21, 2023 08:55 CDT)
CFA Manager
ar. ..., P,.,;—
Lauren Prieur (Apr 21, 2023 09:13 CDT)
TPW Director
William Johnson (Ap 24 202312:23 CDT)
Asst. City Manager
Apr19,2023
Date
Apr21,2023
Date
Apr21,2023
Date
Apr21,2023
Date
Apr21,2023
Date
Apr24,2023
Date
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
Page 1 of 2
Notice of Project Completion
Project Name: Tradition Central Phase 2B
City Project No.: 103142
City's Attachments
Final Pay Estimate ❑x
Change Order(s): ❑ Yes ❑x N/A
Contractor's Attachments
Affidavit of Bills Paid
Consent of Surety
Statement of Contract Time
Contract Time 150 WD Days Charged: 295
Work Start Date: 12/6/2021 Work Complete Date: 3/30/2023
Completed number of Soil Lab Test: 408
Completed number of Water Test: 22
Page 2of2
FoRTWoRTH
CITY OF FORT WORTH
FINAL PAYMENT REQUEST
Contract Name TRADITIONS CENTRAL PHASE 213
Contract Limits
Project Type DRAINAGE/PAVING IMPROVEMENTS
City Project Numbers 103142
DOE Number 1420
Estimate Number 1 Payment Number 1 For Period Ending 4/13/2023
WD
City Secretary Contract Number Contract Time 12WD
Contract Date 12/6/2021 Days Charged to Date 295
Project Manager NA Contract is 100.00 Complete
Contractor SAI CONSTRUCTION
2105 WATERVIEW PARKWAY
RICHARDSON , TX 75080
Inspectors WATSON / BRADLEY
Thursday, April 13, 2023 Page 1 of 5
City Project Numbers 103142
Contract Name TRADITIONS CENTRAL PHASE 213
Contract Limits
Project Type DRAINAGE/PAVING IMPROVEMENTS
Project Funding
UNIT III DRAINAGE IMPROVEMENTS
Item
Description of Items
Estimated Unit
No.
Quanity
23
MEDIUM RIPRAP,DRY
372 SY
24
TRENCH SAFETY
1977 LF
25
CONCRETE COLLAR
2 EA
26
21" RCP. CLASS III
235 LF
27
24" RCP, CLASS III
837 LF
28
27" RCP, CLASS III
300 LF
29
30" RCP, CLASS III
374 LF
30
42" RCP, CLASS lII
231 LF
31
4' STORM JUNCTION BOX
2 EA
32
5" STORM JUNCTION BOX
3 EA
33
(7) 10'XY HEADWALL, BOX CULVERT
14 CY
34
10' CURB INLET
10 EA
35
CONNECT TO EX. 42" END & PLUG
I EA
366
(7) 10'X3' RCB
90 LF
37
CONSTRUCT DROP STRUCTURE
45 CY
38
CONCRETE APRON
127 SY
Sub -Total of Previous Unit
UNIT IV PAVING IMPROVEMENTS
DOE Number 1420
Estimate Number 1
Payment Number 1
For Period Ending 4/13/2023
Unit Cost
Estimated
Completed
Completed
Total
Quanity
Total
$150.00
$55,800.00
372
$55,800.00
$1.00
$1,977.00
1977
$1,977.00
$1,000.00
$2,000.00
2
$2,000.00
$55.00
$12,925.00
235
$12,925.00
$65.00
$54,405.00
837
$54,405.00
$73.00
$21,900.00
300
$21,900.00
$85.00
$31,790.00
374
$31,790.00
$156.00
$36,036.00
231
$36,036.00
$4,500.00
$9,000.00
2
$9,000.00
$5,500.00
$16,500.00
3
$16,500.00
$1,000.00
$14,000.00
14
$14,000.00
$3,400.00
$34,000.00
10
$34,000.00
$1,000.00
$1,000.00
1
$1,000.00
$4,200.00
$378,000.00
90
$378,000.00
$650.00
$29,250.00
45
$29,250.00
$120.00
$15,240.00
127
$15,240.00
$713,823.00
$713,823.00
Item
Description of Items
Estimated Unit
Unit Cost
Estimated
Completed
Completed
No.
Quanity
Total
Quanity
Total
39
HYDRATED LIME@30LBS./S.Y.(RESIDENTIAL)
172 TN
$180.00
$30,960.00
172
$30,960.00
40
6" LIME TREATED SUBGRADE(RESIDENTIAL)
11494 SY
$3.00
$34,482.00
11494
$34,482.00
41
6" CONCRETE PAVEMENT (RESIDENTIAL)
10752 SY
$36.25
$389,760.00
10752
$389,760.00
42
Y CONC SIDEWALK
980 SF
$4.75
$4,655.00
980
$4,655.00
43
P-1 RAMP
4 EA
$1,500.00
$6,000.00
4
$6,000.00
44
FURNISH/INSTALL ALUM SIGH GROUND
4 EA
$750.00
$3,000.00
4
$3,000.00
MOUNT CITY STD.
45
TRAFFIC CONTROL
1 EA
$1,500.00
$1,500.00
1
$1,500.00
46
INSTALL END OF ROAD BARRICADE
1 EA
$750.00
$750.00
1
$750.00
47
REMOVE END OF ROAD BARRICADE
3 EA
$250.00
$750.00
3
$750.00
Thursday, April 13, 2023 Page 2 of 5
City Project Numbers 103142
Contract Name TRADITIONS CENTRAL PHASE 213
Contract Limits
Project Type DRAINAGE/PAVING IMPROVEMENTS
Project Funding
DOE Number 1420
Estimate Number 1
Payment Number 1
For Period Ending 4/13/2023
48 CONCRETE HEADER 116 LF
$20.00
$2,320.00
116 $2,320.00
49 CONNCECT TO EXISTING PAVEMENT 3 EA
$1,250.00
$3,750.00
3 $3,750.00
50 RI-1 STOP SIGN 4 EA
$750.00
$3,000.00
4 $3,000.00
51 ST MARKER BLADE 8 EA
--------------------------------------
$250.00
$2,000.00
8 $2,000.00
Sub-Total of Previous Unit
$482,927.00
$482,927.00
Thursday, April 13, 2023 Page 3 of 5
City Project Numbers 103142
Contract Name TRADITIONS CENTRAL PHASE 213
Contract Limits
Project Type DRAINAGE/PAVING IMPROVEMENTS
Project Funding
Contract Information Summary
Original Contract Amount
Change Orders
DOE Number 1420
Estimate Number 1
Payment Number 1
For Period Ending 4/13/2023
$1,196,750.00
Total Contract Price $1,196,750.00
Total Cost of Work Completed $1,196,750.00
Less % Retained $0.00
Net Earned $1,196,750.00
Earned This Period $1,196,750.00
Retainage This Period $0.00
Less Liquidated Damages
Days @ / Day
LessPavement Deficiency
Less Penalty
Less Previous Payment
Plus Material on Hand Less 15%
Balance Due This Payment
$0.00
$0.00
$0.00
$0.00
$0.00
$1,196,750.00
Thursday, April 13, 2023 Page 4 of 5
City Project Numbers 103142
Contract Name TRADITIONS CENTRAL PHASE 2B
Contract Limits
Project Type DRAINAGE/PAVING IMPROVEMENTS
Project Funding
Project Manager NA
Inspectors WATSON / BRADLEY
Contractor SAI CONSTRUCTION
2105 WATERVIEW PARKWAY
RICHARDSON, TX 75080
DOE Number 1420
Estimate Number 1
Payment Number 1
For Period Ending 4/13/2023
City Secretary Contract Number
Contract Date
12/6/2021
Contract Time
125 WD
Days Charged to Date
295 WD
Contract is .000000
Complete
CITY OF FORT WORTH
SUMMARY OF CHARGES
Line Fund Account Center Amount Gross Retainage Net
Funded
Total Cost of Work Completed $1,196,750.00
Less % Retained $0.00
Net Earned $1,196,750.00
Earned This Period $1,196,750.00
Retainage This Period $0.00
Less Liquidated Damages
0 Days @ $0.00 / Day
$0.00
LessPavement Deficiency
$0.00
Less Penalty
$0.00
Less Previous Payment
$0.00
Plus Material on Hand Less 15%
$0.00
Balance Due This Payment
$1,196,750.00
Thursday, April 13, 2023 Page 5 of 5
FORTWORTH.
M,
TRANSPORTATION AND PUBLIC WORKS
April 13, 2023
SAI Construction
2105 Waterview Parkway
Richardson, TX 75080
RE: Acceptance Letter
Project Name: Tradition Central Phase 2B
Project Type: Developer Water, Sewer, Storm, Streets
City Project No.: 103142
To Whom It May Concern:
On March 30, 2023 a final inspection was made on the subject project. There were punch list items
identified at that time. The punch list items were completed on April 13, 2023. The final inspection and
the corrected punch list items indicate that the work meets the City of Fort Worth specifications and is
therefore accepted by the City. The warranty period will start on April 13, 2023, which is the date of the
punch list completion and will extend of two (2) years in accordance with the Contract Documents.
If you have any questions concerning this letter of acceptance, please feel free to contact me at 817-
392-2373.
Sincerely,
ya8_� it e P.0
Yogesh Patel, P.E., Project Manager
Cc: Jason Bradley, Inspector
Don Watson, Inspection Supervisor
Joseph Rogers, Senior Inspector
Victor Tornero, Program Manager
Goodwin & Marshall, Consultant
SAI Construction, Contractor
Hines Interest, LP, Developer