HomeMy WebLinkAboutContract 57392-FP1FORT WORTH.
-FP1
City Secretary
Contract No. 57392
Date Received 05/03/2023
AT
NOTICE OF PROJECT COMPLETION
(Developer Projects)
The Transportation and Public Works Department upon the recommendation of the Project
Manager has accepted the following project as complete:
Project Name: Project Attraction Alliance Gateway
City Project No.: 103904
Improvement Type(s): x❑ Paving
Original Contract Price:
Amount of Approved Change Order(s):
Revised Contract Amount:
Total Cost of Work Complete:
❑ Drainage ❑ Street Lights
$160,492.00
$160,492.00
A,r4wa-sue May 3, 2023
Arturo Sancen (May 3, 2023 07:46 CDT)
Contractor Date
Superintendent
Title
Jeremiah Patton
Company Name
Carlos Garcia (May 3, 202310:43 CDT)
Project Inspector
Sanft Ad kari,P.E.(May3,202311:55CDT)
Project Manager
:F tU'n
Rebecca Diane Owen (May 3, 202312:07 CDT)
CFA Manager
Lauren Prieur (May 3, 202313:42 CDT)
TPW Director
William Johnson (Mt 3,202313:42 CDT)
Asst. City Manager
May 3, 2023
Date
May 3, 2023
Date
May 3, 2023
Date
May 3, 2023
Date
May 3, 2023
Date
❑ Traffic Signals
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX Page 1 of 2
Notice of Project Completion
Project Name: Project Attraction Alliance Gateway
City Project No.: 103904
City's Attachments
Final Pay Estimate ❑x
Change Order(s): ❑ Yes ❑x N/A
Contractor's Attachments
Affidavit of Bills Paid
Consent of Surety
Statement of Contract Time
Contract Time 60 WD Days Charged: 55
Work Start Date: 1/5/2023 Work Complete Date 4/19/2023
Completed number of Soil Lab Test: 15
Completed number of Water Test: 6
Page 2of2
FoRTWoRTH
CITY OF FORT WORTH
FINAL PAYMENT REQUEST
Contract Name ALLIANCE GATEWAY - LOT 3, BLOCK 2
Contract Limits
Project Type PAVING IMPROVEMENTS
City Project Numbers 103904
DOE Number 3904
Estimate Number 1 Payment Number 1 For Period Ending 4/26/2023
WD
City Secretary Contract Number
Contract Date
Project Manager NA
Contractor CONATSER CONSTRUCTION TxLP
5327 WICHITA ST
FORT WORTH, TX 76119
Inspectors T. GARDNER / C. GARCIA
Contract Time 6WD
Days Charged to Date 55
Contract is 100.00 Complete
Friday, April 28, 2023 Page 1 of 4
City Project Numbers 103904
Contract Name ALLIANCE GATEWAY - LOT 3, BLOCK 2
Contract Limits
Project Type PAVING IMPROVEMENTS
Project Funding
UNIT 11: PAVING IMPROVEMENTS
Item
Description of Items
Estimated Unit
No.
Quanity
1
REMOVE CONC CURB & GUTTER
363 LF
2
UNCLASSIFIED EXCAVATION BY PLAN
1 LS
3
HYDRATED LIME
17 TN
4
8" LIME TREATMENT
602 SY
5
8" CONC PVMT
523 SY
6
4" CONC SIDEWALK
3692 SF
7
BARRIER FREE RAMP, TYPE P-1
2 EA
8
6" CONC CURB & GUTTER
130 LF
9
8" SLD PVMT MARKING HAS (W)
153 LF
10
REFL RAISED MARKER TY I-C
8 EA
11
UTILITY SERVICE SURFACE RESTORATION
352 SY
SODDING
12
REMOVE & REINSTALL SIGN PANEL & POST
1 EA
13
TRAFFIC CONTROL
1 MO
14
CONNECT TO EXIST PAVEMENT
363 LF
15
IRRIGATION SYSTEM ADJUSTMENTS
1 LS
16
IRRIGATION VALVE RELOCATION
6 EA
Sub -Total of Previous
Unit
DOE Number 3904
Estimate Number 1
Payment Number 1
For Period Ending 4/26/2023
Unit Cost
Estimated
Completed
Completed
Total
Quanity
Total
$40.00
$14,520.00
363
$14,520.00
$6,000.00
$6,000.00
1
$6,000.00
$225.00
$3,825.00
17
$3,825.00
$12.50
$7,525.00
602
$7,525.00
$120.00
$62,760.00
523
$62,760.00
$6.00
$22,152.00
3692
$22,152.00
$2,500.00
$5,000.00
2
$5,000.00
$60.00
$7,800.00
130
$7,800.00
$8.00
$1,224.00
153
$1,224.00
$20.00
$160.00
8
$160.00
$18.00
$6,336.00
352
$6,336.00
$1,000.00
$1,000.00
1
$1,000.00
$2,500.00
$2,500.00
1
$2,500.00
$30.00
$10,890.00
363
$10,890.00
$4,000.00
$4,000.00
1
$4,000.00
$800.00
$4,800.00
6
$4,800.00
$160,492.00
$160,492.00
Friday, April 28, 2023 Page 2 of 4
City Project Numbers 103904
Contract Name ALLIANCE GATEWAY - LOT 3, BLOCK 2
Contract Limits
Project Type PAVING IMPROVEMENTS
Project Funding
Contract Information Summary
Original Contract Amount
Change Orders
Total Contract Price
DOE Number 3904
Estimate Number 1
Payment Number 1
For Period Ending 4/26/2023
$160,492.00
$160,492.00
Total Cost of Work Completed $160,492.00
Less % Retained $0.00
Net Earned $160,492.00
Earned This Period $160,492.00
Retainage This Period $0.00
Less Liquidated Damages
Days @ / Day
LessPavement Deficiency
Less Penalty
Less Previous Payment
Plus Material on Hand Less 15%
Balance Due This Payment
$0.00
$0.00
$0.00
$0.00
$0.00
$160,492.00
Friday, April 28, 2023 Page 3 of 4
City Project Numbers 103904
Contract Name ALLIANCE GATEWAY - LOT 3, BLOCK 2
Contract Limits
Project Type PAVING IMPROVEMENTS
Project Funding
Project Manager NA
Inspectors T. GARDNER / C. GARCIA
Contractor CONATSER CONSTRUCTION TxLP
5327 WICHITA ST
FORT WORTH, TX 76119
DOE Number 3904
Estimate Number 1
Payment Number 1
For Period Ending 4/26/2023
City Secretary Contract Number
Contract Date
Contract Time 60 WD
Days Charged to Date 55 WD
Contract is .000000 Complete
CITY OF FORT WORTH
SUMMARY OF CHARGES
Line Fund Account Center Amount Gross Retainage Net
Funded
Total Cost of Work Completed $160,492.00
Less % Retained $0.00
Net Earned $160,492.00
Earned This Period $160,492.00
Retainage This Period $0.00
Less Liquidated Damages
0 Days @ $0.00 / Day
$0.00
LessPavement Deficiency
$0.00
Less Penalty
$0.00
Less Previous Payment
$0.00
Plus Material on Hand Less 15%
$0.00
Balance Due This Payment
$160,492.00
Friday, April 28, 2023 Page 4 of 4
FORTWORTH.
TRANSPORTATION AND PUBLIC WORKS
April 26, 2023
Conatser Construction TX, LP
5327 Wichita St.
Fort Worth, Texas 76119
RE: Acceptance Letter
Project Name: Project Attraction Alliance Gateway
Project Type: Water and Paving Improvements
City Project No.: 103904
To Whom It May Concern:
On April 26, 2023 a final inspection was made on the subject project. There were no punch list items
identified at that time. The final inspection indicates that the work meets the City of Fort Worth
specifications and is therefore accepted by the City. The warranty period will start on April 26, 2023,
which is the date of the final inspection and will extend of two (2) years in accordance with the Contract
Documents.
If you have any questions concerning this letter of acceptance, please feel free to contact me at
(817)392-8424.
Sincerely,
Sandi pAd Kkari, P.E.(May 3, 202311:55 CDT)
Sandip Adhikari, Project Manager
Cc: Carlos Garcia, Inspector
Gary Deyon, Inspection Supervisor
Edward D'avila, Senior Inspector
Victor Tornero, Program Manager
Peloton, Consultant
Conatser Construction, Contractor
MP Magnetics, Developer
File
E-Mail: TPW_Acceptance@fortworthtexas.gov
Rev. 08/20/19
AFFIDAVIT
STATE OF TEXAS
COUNTY OF TARRANT
Before me, the undersigned authority, a Notary Public in the state and county aforesaid,
on this day personally appeared Brock Huggins, President of Conatser Management Group, Inc.,
general partner of Conatser Construction TX� LP, known to me to be a credible person, who
being by me duly sworn, upon his oath deposed and said:
That all persons, firms, associations, corporations or other organizations furnishing
labor and/or materials have been paid in full;
That the wage scale established by the City Council in the City of Fort Worth, has
been paid in full; and
That there are no claims pending for personal injury and/or property damages;
On Contract described as:
PROJECT ATTRACTION
WATER & PAVING IMPROVEMENTS
CFA PRJ #: 22-0030
CITY PROJECT #: 103904
CITY OF FORT WORTH
STATE OF TEXAS
CONATSER CONSTRUCTION TX, LP
Brock Huggin
Subscribed and sworn to before me this 251h day of April, 2023.
KATHERINEROSE `� W
NOTARY PUBLIC Notary Public in Tarrant County, Texas
ID# 13U67933
,ygyr State at Texas
Comm. Exp.11-30.2025
e
CONSENT OF
SURETY COMPANY
TO FINAL PAYMENT
Conforms with the American Institute of
Architects, AIA Document G707
OWNER
❑
ARCHITECT
❑
CONTRACTOR
❑
SURETY
❑
OTHER
PROJECT:
(name, address)Project Attraction(Alliance Gtwy -Lot 3, Block 2)
Fort Worth, TX
TO {Owner)
MP MAGNETICS LLC AND THE CITY OF FORT
WORTH
6720 Via Austi Parkway, Suite 450
Las Vegas NV 89119
CONTRACTOR: CONATSER CONSTRUCTION TX, L P,
Bond No 0243970
ARCHITECT'S PROJECT NO: CF22-0030
CONTRACT FOR:
Public Water 8 Paving Improvements for Project Attraction (Alliance
Gateway - Lot 3, Block 2)
.J CONTRACT DATE:
In accordance with the provisions of the Contract between the Owner and the Contractor as indicated above, the
There insert name end address of Surety Companyl
BERKLEY INSURANCE COMPANY
475 Steamboat Road
Greenwich CT 06830 , SURETY COMPANY
on bond of {here insert name and address of Contractor)
CONATSER CONSTRUCTION TX, L.P.
5327 Wichita St.
Fort Worth TX 76119-6035
,CONTRACTOR,
hereby approves of the final payment to the Contractor, and agrees that final payment to the Contractor shall not relieve
the Surety Company of any of its obligations to (here insert name and address or Owner)
MP MAGNETICS LLC AND THE CITY OF FORT WORTH
6720 Via Austi Parkway, Suite 450
Las Vegas NV 89119
as set forth in the said Surety Company's bond.
IN WITNESS, WHEREOF,
the Surety Company has hereunto set its hand this
Attest; 'r
(Seat):
, OWNER,
20th day of April, 2023
BERKLEY INSURANCE COMPANY
Surety Company
Signature of Authorized Representative
Robbi Morales Attorney -in -Fact
Title
NOTE: This form is to be used as a companion document to AIA DOCUMENT G706. CONTRACTOR'S AFFIDAVIT OF PAYMENT OF DEBTS AND CLAIMS,
Current Edition
ONE PAGE