HomeMy WebLinkAboutContract 56291-CO1CSC No. 56291-COI
FORT WORTH City of Fort Worth
= Change Order Request
Project Name: Weslside Water Treatment Plant Plate Settler Expansion Project ( CitySec No,: 1 56291
Project No,(s):l 56003 0600430102052 1 DOE No, I N/A City Proj, No.: J 102052
Project Description:) Weslside Water Treatment Plant Plate Settler Expansion
Contraclorl Crescent Constructors, Inc. Change Order it 1
I Date: 4112/2023
City Project Mgr,1 Scoll Taylor PE Cily Inspector: Nathan Gray
Phone Number,) 817-392-7240 Phone Number: 8173924961
Dept, Water Sewer
Totals Contract Time
(Calendar days)
Original Contract Amount $3,697,000.00
$3,697,000.00 400
Extras to Dale
Credits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Date $3,697,000.00
$3,697,000.00 ` 400
JAmount of Proposed Change Order 382,345.00
382,345.00 -227
Revised Contract Amount $ ,079,346,00
$ ,079,346,00 . 627
Original Funds Available for Change Orders $50,000.00
$50,000.00
Remaining Funds Available for this CO $50,000.00
$50,000.00
Additional Funding (if necessary) $332,345.00
$332,345.00
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT
10,34%
MAXALLOWABLE CONTRACTAMOUNT (ORIGINAL CONTRACT COST+ 259/0)
$4,621,250,00
JUSTIFICATION (REASONS) FOR CHANGE ORDER
Change Order No. 1 provides for the installation of a beam to allow for future plate settler installation, programmable logic control (PLC) for the
central processing unit CPU for the membrane filtration system, and redundant Supervisory Control and
Data Acquisition (SCADA) PLC,
Staff recommends the addition of 227 calendar days for the change order.
"Notwithstanding anything else to the contrary, Crescent shall only be liable to the City of Fort Worth for claims arising out of Pall's work for damages
(liquid or consequential) to the same extent Pall Is liable to Crescent under the subcontract between Pali and Crescent" (See 3.04 & 11.06 below)
3.04 Damages for Delay to Contractor. Subcontractor shall not be liable for any damages for delay sustained by Contractor caused directly or
indirectly by Subcontractor; including, but not limited to, damages, liquidated or otherwise, for which Contractor Is liable to Owner.
11.06 Limitation of Liability. IN NO EVENT SHALL SUBCONTRACTOR BE LIABLE FOR ANY INCIDENTAL OR CONSEQUENTIAL DAMAGES OF ANY KIND,
WHETHER FOR BREACH OF ANY WARRANTY, FOR BREACH OR REPUDIATION OF ANY OTHER TERM OR CONDITION OF THIS CONTRACT, FOR NEGLIGENCE,
ON THE BASIS OF STRICT LIABILITY, OR OTHERWISE. The total liability of Subcontractor and its subsidiaries, affiliates, employees, directors, officers and
agents arising out of the performance or nonperformance hereunder or its obligations In connection with the design, manufacture, sale, delivery, and/or
use of materials, equipment or services shall in no circumstance exceed in the aggregate a sum equal to the amount actually paid to Subcontractor for
materials, equipment or services delivered hereunder.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment
in full (both time and money) for all costs arising out of, or incidental to, the above Change Order.
5/10/2023
S//i/25
��-4,14a. 4 4 T• 5 . May 11, 2023
Senior Assistant City, Attorney,
i May 12, 2023 bang BcualuJaFF May 15, 2023
l`Wtlnclli4I1on;(If:Requlred)' OFFICIAL RECORD
M&C Number 23 2238 M&C Dale Approved j T I'fP1M CITY SECRETARY
FT. WORTH, TX
FORT Wcowrm City of Fort Worth
Change Order Additions
Project Name Westside Water Treatment Plant Plate Seiner Expansion Project
City Sec No.:
56291
Project No.(s): 56003 0600430102052 DOE No,J N/A
City Proj. No.:
102052 j
Project Westside Water Treatment Plant Plate Settler Expansion
I
Description
7
Contractor Crescent Constructors, Inc, Change Order: 01
Dale:1 4/12/2023
City Project Mgr, I Scott Taylor PE City Inspector I Nathan Gray
ADDITIONS
I I tM UESCftll'PIUN DEPT Qty Unit
Unit Cost
Total '
8 Installation of Beam for Plate Settler Expansion 1.00 LS
$165,985.00
$155,985.00
9 Pail PLC CPU and Redundacy Upgrade 1.06 LS
$118,363.00
$118,363.00
10 Redundant SCADA PLC (PLC-FLT-A and PLC-FLT-B) 1.00 LS
$107,997.00
$107,997.00
Water 1$382,345.00
� Sewer
Page 2 of 4 !Additions Sub Total $382,345.00
I'ORT WORTH City of Fort Worth
Change Order Deletions
Project Name Weslside Water Treatment Plant Plate Settler Expansion Project City Sec No,: J 56291
Project No,(s): 56003 0600430102052 DOE No, I N/A City Pro], No.: 1 102052
Project Description I Weslside Water Treatment Plant Plate Settler Expansion
I �
Contractor I Crescent Constructors, Inc, Change Order: F-1-1 Dale I 4/12/2023
City Project Mgr. Scott Taylor PE City Inspector: I Nathan Gray
ITEM DESCRIPTION
DELETIONS
DEPT City 'Unit , Unit Cost
Page 3 of 4
'Water
Sewer
IDelelions Sub Total
Total
11
MIWBE Breakdown for this Change Order
MWBE Sub Type of Service Amount for this CO
Total $0.00
Previous Change Orders
co # DATE AMOUNT
Total $0.00
Page 4 of 4
Contract Compliance Manager
By signing I aciolowledge that I am the person responsible
for the monitoring and administration of this contract, including
ensuring all performance and reporting requirements.
Signature
Scott Taylor, P.E.
Name of Employee
Project Manager
Title
�d4vogn�
a FORA 4a
x ovoo..o 4($;
ATTEST: d v o .=a
Q op * 0
o00 000,
o �aIIa� AEXASaap�
Jannette Goodall
City Secretary
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
City of lrorrg, Worrgh) Texas
DATE: Tuesday, April 11, 2023 REFERENCE NO.: **M&C 23-0238
LOG NAME: 60WSWTPPSETCOI- CRESCENT
SUBJECT:
(CD 3 / Future CD 3) Authorize Execution of Change Order No. 1 in the Amount of $382,345.00 and the
Addition of 227 Calendar Days to a Contract with Crescent Constructors Inc. for the Westside Water
Treatment Plate Settlers Project for a Revised Contract Amount of $4,079,345.00 and Adopt Appropriation
Ordinances to Effect a Portion of Water's Contribution to the Fiscal Years 2023-2027 Capital Improvement
Program
RECOMMENDATION:
It is recommended that the City Council:
1. Authorize execution of Change Order No. 1 in the amount of $382,345.00 to City Secretary Contract
No. 56291 with Crescent Constructors Inc., for Westside Water Treatment Plant Plate Settlers
Expansion project for a revised contract amount of $4,079,345.00;
2. Adopt the attached appropriation ordinance increasing receipts and appropriations in the Water
Impact Fee Fund in the amount of $382,345.00 from available funds for the purpose of transferring
funds from the Water/Wastewater Wholesale Impact Fees and Water/Wastewater Retail Impact Fee
projects (City Project Nos. B20004 and 1320005) to the Westside Water Treatment Plant Plate
Settlers project; and
3. Adopt the attached appropriation ordinance increasing receipts and appropriations in the Water
Impact Fee Fund in the amount of $382,345.00 transferred from within the Water Impact Fee Fund
to the Westside Water Treatment Plant Plate Settlers project (City Project No. 102052) to effect a
portion of Water's Contributions to the Fiscal Years 2023-2027 Capital Improvement Program.
DISCUSSION:
On August 3, 2021, Mayor and Council Communication (M&C 21-0540) authorized a contract with
Crescent Constructors, Inc., (City Secretary Contract No. 56291), in the amount of $3,697,000.00 for the
Westside Water Treatment Plant Plate Settlers project.
Change Order No. 1 provides for the installation of a beam to allow for future plate settler installation,
programmable logic control (PLC) for the central processing unit CPU for the membrane filtration system,
and redundant Supervisory Control and Data Acquisition (SCADA) PLC.
It is the practice of the Water Department to appropriate its CIP plan throughout the fiscal year, instead of
within the annual budget ordinance, as projects commence, additional funding needs are identified, and to
comply with bond covenants. The actions in the M&C will amend the City of Fort Worth's Fiscal Year 2023-
2027 Capital Improvement Program as follows:
60WSWTPPSETC01- CRESCENT
Capital Project FY2023 Budget Revised
Fund Name CIP Appropriations Authority Change (Increase/Decrease) FY2023
Name Budget
56003 102052
Water $0.00 This M&C $382,345.00 $382,345.00
Westside
Impact
WTP
Fee -
Plate
Fund
Settlers
Funding for the Westside WTP Plate Settlers project is depicted below:
Fund Existing IJ Additional
Appropriations Appropriations Project Total*I
Water Impact
Fee— Fund $4,841,657.00 $382,345.00 $5,224,002.00
.56003
Project Total 1 $4,841,657.0-011 $382,345.001$5,224,002.001
*Numbers rounded for presentation purposes.
Funding is currently available in the W/WW Wholesale Impact Fees and the W/WW Retail Impact Fees
projects within the Water Impact Fee fund for the purpose of funding the Westside WTP Plate Settlers
project.
Staff has reviewed and verified the quantities for the additional work under this Change Order No. 1.
Additionally to complete this work, staff recommends that the contract time be extended by 227 calendar
days for delivery installation of the beam, the redundant PLC for the SCADA and PLC for CPU for the
membrane filtration system.
DVIN: A waiver of the goal for Business Equity subcontracting requirements was requested, and approved
by the DVIN, in accordance with the applicable Ordinance, because the purchase of goods or services is
from sources where subcontracting or supplier opportunities are negligible.
The project is located in COUNCIL DISTRICT 3/FUTURE COUNCIL DISTRICT 3.
FISCAL INFORMATION / CERTIFICATION:
The Director of Finance certifies that funds are currently available in the W/WW Wholesale Impact Fees
and W/WW Retail Impact Fees projects within the Water Impact Fee Fund and upon approval of the above
recommendations and adoption of the attached appropriation ordinances, funds will be available in the
Water Impact Fee Fund for the Westside WTP Plate Settlers project to support the approval of the above
recommendations and execution of the amendment to the agreement. Prior to an expenditure being
Incurred, the Water Department has the responsibility of verifying the availability of funds.
FUND IDENTIFIERS (FIDs):
TO
Fund
Department
Accoun
I
Project
Program
I
Activity
Budget
Reference #
mount
ID
ID I I
Year I
(Chartfield 2)
FROM
Fundl
I
Department
Account�
I
Project
ProgramlActivityl
I
Budget
Reference #
�P►mount
ID
II
ID
Year I
(Chartfield 2)
�
CERTIFICATIONS:
Submitted for City Manaaer's Office bv: Dana Burghdoff (8018)
Originating Department Head: Chris Harder (5020)
Additional Information Contact: Scott Taylor (7240)
ATTACHMENTS
1. 60WSWTPPSETCO1- CRESCENT 1295 Form.pdf (CMInternal)
2.60WSWTPPSETC01- CRESCENT FID Table (WCF 01.25.23).xlsx (CMInternal)
3. 60WSWTPPSETC01- CRESCENT funds availability.%f (CFw Internal)
4. 60WSWTPPSETCO I -CRESCENT MAP.r)df (Public)
5.60WSWTPPSETC01- CRESCENT SAM.ndf (CMInternal)
6. 60WSWTPPSETC01- CRESCENT Updated FID.xlsx (CMInternal)
7. 60WSWTPPSETC01- CRESCENT Waiver.pdf (CMInternal)
8. ORD.APP60WSWTPPSETC01- CRESCENT 56003_AO23(r2).docx (Public)
9. ORD.APP60WSWTPPSETCO1- CRESCENT 56003_ AO23(r3).docx (Public)
10. PBS CPN 102052.pdf (CFW Internal)
60WSWTPPSETCOI-CRESCENT FED T2ble
2
56003
0600430
B20004
2023
2
56003
0600430
4413024 B20005
2023
2
56003
0600430
B20005
2023
3
� 56003
0600430
4956003 102052 �
!�
I 2023
3
56003
0600430
102052 I
I 2023
$191,172.00 Water- Retail
$191,172.00
$382,345.00
$382,345.001
4 56003 0600430 5900016 B20004 B02000 9999 $191,173.00
4 56003 0600430 5900016 B20005 B02000 9999 $191,172.00
4 56003 0600430 4956003 102052 005430 9999 ($382,345.00)