Contract 57092-CO3
CSC No. 57092-CO3 FoR-i- Wolivi t t, City of Fort Worth Change Order Request Project Name Intersection Improvements at Bonds Ranch & FM 156 Client Project #(s)I 101009-2 City Sec # I 57092 Project Description Intersection improvements including widening Bond Ranch Rd to provide left turn lanes onto Farm to Market Road 156, improve raddi for northbound to eastbound traffic, minor storm drian improvemnets and a new traffic signal with pedestrain access. Contractorl Texas Materials Group, Inc. dba TexasBit I Change Order #I 3 I Date 5/30/2023 City Project Mgr.I Brendan McInnes, PE I City Inspectorl Habte Taezaz Dept. TPW Contract Time Totals (CD �00 Original Contract Amount $1,180,676.20 $1,180,676.20 Extras to Date $163,332.35 $163,332.35 Credits to Date $131,639.20 $131,639.20 Pending Change Orders (in M&C Process) $0.00 Contract Cost to Date $1,212,369.35 300 Amount of Proposed Change Order $2,566.31 50 Revised Contract Amount $1,214,935.66 350 Original Funds Available for Change Orders $0.00 $0.00 Remaining Funds Available for this CO 1 Additional Funding (if necessary) $2,566.31 CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT 2.90% MAX ALLOWABLE CONTRA CT AMOUNT (ORIGINAL CONTRACT COST+ 25%) $1,475,845.25 Construction began April 11, 2022 with an anticipated signal pole delivery in installation of September 6, 2022. Signal poles were approved for production on March 3, 2022 with an anticipated 6-month lead time. The new poles were required to be installed in order to remove the old poles and widen the roadway as detailed in the plans. Contractor completed available work on the project during the time that the poles were being fabricated. In late September notice was provided that there was a delay in a mast arm and delivery would be in early November (over 60 days later than anticipated in the schedule). This delay prevented removal of the existing pole and progression of the project completion. The mast arms were installed in November and the signal work completed, signal activated, and the old poles removed. The contractor then worked on finishing the widening, grading, and MBGF installation. Additional grading and base items are needed to match field conditions and additional pavement markings being added to the radius of the intersection to better delineate the pavement edges. Time - Additional contract time has been reviewed and the amount of days being granted is deemed reasonable for the work when reviewed in relation to the critical path of the work activities. It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full (both time and money) for all costs arising out of, or incidental to, the above Change Order. The Project/Program Manager signing below acknowledges that he/she is the person responsible for the monitoring and administration of this contract, including ensuring all performance and reporting requirements. ontractor's Com an TexasBit Adam Newsom Date Jun 5, 2023 Inspector/Inspection Supervisor Date Project and Contract Compliance Manager Date awA� Jun 4, 2023 B✓Pnd —1111, an INoInn-5 JUrl 5, 2023 Program Manager Date Senior Capital Project Officer Date Jun 5, 2023 Z1511i U. Jun 6, 2023 Assistant Director (Dept) Date Director, Contracting Department (Dept) Date �' ' �N �"�%trrr�► Jun 6, 2023 Jun 6, 2023 Assistant City Attorney Date Assistant City Manager Date I Jun 7, 2023� Jun 7, 2023 Council Action if required) M&C Number I I M&C Date Approved ATTEST: Jannette Goodall, City Secretary p000vvnp�� Pvo 0 PAP f ° Oan� T°n0000p54aa OFFICIAL RECORD CITY SECRETARY FT. WORTH, TX T: N �wide r�i City of Fort Worth Change Order Additions Project Name I Intersection Improvements at Bonds Ranch & FM 156 City Sec # 57092 Client Project # 1 101009-2 1 Contractorl Texas Materials Group, Inc. dba TexasBit I PM I Brendan McInnes, PE Inspectorl Habte Taezaz I Change Order Submittal # O3 Date 1 5/30/2023 1 ADDITIONS IIEM DEbUKIPIIUN DEPI Uty j unit 18 9999.0002 Ditch Grading I PW 10AOOWOOL I UY 20 3211.0113 8" Flexible Base, Type A, GR-1 TPW 141.0000000C I SY 23 3212.0503 6" Asphalt Base Type B TPW 13.000OOOOC I SY 82 9999.0022 REFL PAV MIRK TY II (W) 4" (SLID) TPW 250.0000000C I LF UnitUost total 1 $22.35 $223.50 1 $10.1U $1,424.101 $45.67 $59371� $1.3U $325.001 TFW $2,566.31 1 1 1 1 Sub Total Additions $2,566.31 1 Change Order Additions Page 2 of 4 I I tM T t� x;'r City of Fort Worth T Change Order Deletions Project Name 1 Intersection Improvements at Bonds Ranch & FM 156 City Sec # 1 57092 Client Project# 1 101009-2 1 Contractorl Texas Materials Group, Inc. dba TexasBit I PMI Brendan McInnes, PE I Inspectorl Habte Taezaz I Change Order Submittal # O3 Date 1 5/30/2023 1 DELETIONS ULbUNINI IUN ULI'I uty Unit Unit host total 1 I 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I TOW $o.00l I I I Sub Total Deletions Change Order Deletions Page 3 of 4 MISBE for this Change Order M/SBE Sub Type of Service Amount for this CO Total $0.00 Previous Change Orders CO # DATE I AMOUNT 4/28/2022 $24,220.00 8/16/2022 $7,473.15 Total I $31,693.15 PAVEMENT MARKING SUMMARY 5pecifiatian Bitl Item DescrlPtlon Total U., section No. Quantity REFL PAV MRK TY II (W) 4" (SLD) 1635 LF I REEL PAV MRK TY II (Y) 4" (SLD) 2185 LF I REELPAV MIRK TYII(W)8"(SLD) 550 LF I REEL PAV MRK TY II (W)12" (SLID) 320 LF IREFL PAV MRK TY II (Y) 8" (SLD) 85 LF TXDOT IREFL PAV MRK TY II (W) 24" (SLD) 93 EA REEL PAV MRK TY II(W)(ARROW) 5 EA IREFL PAV MRK TY 11(W)(DBL ARROW) 3 EA I,,TRRA�AFFFIC BUTTON NII6C 26 EA (REFL HARK TV l((if/{ IYyORD) 3 EA 150+00 TIE INTO EXISTNG STRIPING 1 " O PROP 5-STRAND J EX ROW BARBED WIRE FENCE XXXX XX r -XXX Je-� o - � 32 - �+00 32' 20 NDS RANCH RD BONDS RANCH TMP' POSTED SPEED: 45 MPH RD c/L JJ r ❑ L"s 340' Too' -- - x X� X x H x H x— x% xxxx——x xx- - E% EDGE OF r ASPHALT PVMT • • EX ROW • (30•X30•)W3-3 SIGN NO 1 0 0 F I v = Z f 151 _ (n K Z c O Do Lu J_ U H Q xx x- R3-B LK (36"X30') SIGN NO, 2 PROP 4" WHITE EDGE MATCHLINE FM 156 STA 211+00 STRIPING (5 LF) PROP SIGNAL POLE RESIGNAL SHEETS E% ROW Y II SIGN N0. 4% EX UTILITY SIGN R3-6 LK TO REMAIN PROP 4• WHITE EDGE X EX UTILITY SIGN (36"X30") B / STRIPING (5 LF) TO REMAIN NL PROP 5-STRAND d BARBED WIRE FENCE v/ EX UTILITY SIGN Zr N B 'X a Q X TO REMAIN r, X- X XX %%XXX- % � `III � tJ5' A �1 T PROP SIGN �. r II n C O % RE: SIGNAL�HEETS� iii a EX ROWJ /^ PROP 4" WHITE EDGE 0 GI � J� U STRIPING (35 LF) / LNF• `E% CITY OF HASLET Z _ SIGN TO REMAIN ° PROP 4" WHITE EDGE PROP EDGE OF STRIPING (20 LF) STRIPING (40TLF)DGE ASPHALT PVMT T K /,(II c O , BONDS RANCH ts6 C/L RD C/L 23' �. F BONDS RANCH RD m ZD �^ + _ POSTF,S SPEED: 45 MP 00 155+00 J 156+00 � 17+00 D K 58+00 C DEMO 4" WHITE 32 Call BI /) EDGE STRIPING N - U LS G �� (20 LF) Lr H m m EX UTILITY POLE — TO REMAIN I A — _ E% UTILITY SIGN T\ EX W PRO SIGNAL POLE / / PROP ROW TO REMAIN`PROP TCE �SIGNY O0 3� RE. SIGNAL SHEETS 3I R3_ X X %HX X X i 1]5 PROP 5-STRAND a %I / (36•) 0") I 7 ARBED WIRE FENCE / PROP 4' WHITE EDGE f MATCHLINE FM 156 STA 209+50 `PROP 4" WHITE EDGE PROP 4" WHITE EDGE) STRIPING (JS LF) STRIPING (JO LF) sTRIPINc (s LF) SIGN SUMMARY E [REC'RCATIoN BID ITEM NO. DESC. SIGN DIMENSIONS QUANTITY UNIT r, w EC71ON NO. a E 9999.0" TXDOTSign and SIGNALAHFAD W3_3 30'X30" TXWT 1 LA Support TY l0BWG(1) SA(P)LANE USE SIGN R3.8 LK 36"X3D" 3 EA = TOTAL 4 EA -8 3 O LO + W F U Z 0 Z O 00 W Z 0 U Q REVISIONS No. Q 11 IPTIory IATE 1 Q /1\ EDGE LINE STRIPING03/24/23 2 Q 3 Q a Q GRAPHIC SCALE IN FEET 0 10 20 NORTH I LEGEND ❑A 4" SLD PVMT MARKING HAS (W) © 4" SILO PVMT MARKING HAS (Y) S" SLID PVMT MARKING HAS (W) ❑D LANE LEGEND ARROW (W) ❑E LANE LEGEND DBL ARROW (W) ❑F LANE LEGEND (W) WORD (ONLY) © 24" SLID PVMT MARKING HAE (W) (STOP BAR) Q 12" SLD PVMT MARKING HAE (W) (CROSSWALK) ❑ S" SLD PVMT MARKING HAE (Y) ❑� 4" TY II -A -A (Y) ❑K 4" TY I-C (W) NOTES 1. ALL SIGNS SHALL BE PLACED IN ACCORDANCE WITH THE TEXAS MUTCD 2. ALL EXISTING SIGNS THAT ARE REMOVED SHALL BE RETURNED TO THE CITY 18/14/2020 1111lI y{fIllx • "I (cq•P 4YlN't•4/����= W Kimley*Horn 801 Phone (_)5335-Mll 1— (817)1335-5070 MPE a .—t n No F-928 CITY PROJECT #101009-2 AIAPSCO NO. TAR-020P, 7AR-0200, MR-02OU CITY OF FORT WORTH, TEXAS TRANSPORTATION AND PUBLIC WORKS CAPITAL DELIVERY DIVISION BONDS RANCH ROAD & FM 156 INTERSECTION IMPROVEMENTS PAVEMENT MARKING & SIGNING PLAN BEGAN TO STA 158+50 DESIGNED NWP SCALE: DATE- SHEET DRAWN KRR 1: 20 AUGUST 202O C9.01 CHECKED. OLE PAVEMENT MARKING SUMMARY SpecUlatlon I Total Bid Ihm Dauription Unit Section No. QTa ' , REEL PAV MRIC TY II (YT94' (SLD) 1057 LF EX ROW Ex TO TREMAIN IREFL PAV MRK TY II (Y)4" (SLD) 1164 LP - - -X�N x X X % x X X x X % IREFL PAV MRK TY II(W)8'(SLD) 1014 LF ❑ TXDOT IREFL PAV ARK TV II(W) 24'(SLD) 37 LF PROP 4" WHITE EDGE IREFL PAV ARK TY (W) (ARROW) 6 EA STRIPING(75 LF) ITRAFFIC BUTTON TY I-C 51 EA PROP SIG POLE ITRAFFIC BUTTON TYISA-A 14 EA RE slcNaL s Ts E% EDGE OF Q IREFL MRK TY II (YVJ(WORD) 8 EA — �pSPHALT nE INTO STRIPING, FM 156 C/L �y; - —� - - - - 32• �2. - - —+ - - - p r ~� 32• 32' 2 LL D r/ FM 156 K D W Z J 32' 32' � 32' 32' ' `PROP EDGE OF ASPHALT PVMT 100' 175' PROP 4" WHITE EDGE STRIPING (70 LF) X X X X 7—X X % X X X%% X X H—%— %X X H X x XX X X X X • E% UTUTY SIGN W3-3 TO REMAIN �R3-BB EX ROW (30'%30") i (48"%30') R3-eB PROP ROW (48"X30") 1 SIGN NO 7 SIGN NO 8 PROP 5-STRAND SIGN NO 9 BARBED WIRE FENCE SIGN NO 11 SIGN 0 12 SIGN N0. 10 R3-8B R3-8B 46"X30" W3-3 v ( ) (30"X30') -- __ - __ —1— — — — — — — I — — — E% ROW — — — — EX UTILITY SIGN — — — — — — — — TO REMAIN 7XFXEX xxx Ixx x x x Ix x x x x X x x x x x x X UnLITY SIGNTO REMAIN I - O ----- -- -- -- .�—x- X----%--- —%—X--H%---X 0 0 ns' � 100' nI P—PROP EDGE OF Q ASPHALT PVMT F to f 32' 3Y _+ nE INTO EXISTING STRIPIv R NG F FM III C/L `L° FM 156 F >-CK] D f © F LI.I ,,,, - - - - 214+00 215 32 Q B E%ISPNG STRIPING \o 0 `EX EDGE OF ASPHALT PVMT EX UTILITY SIGN REMAIN TO REMAIN X x H % X X -- 7 x X E% ROW SIGN SUMMARY BIDITEM NO. D.C. SIGN DIMENSIONS SPEECCTIIFICON NATIONO. QUANTITY UNIT SBOB.0000 TXDOTSLBn and S SIGNALAHFAD W3-3 -'X30" TXDOT 2 EA SupportTYlOBWG(1)SA(P)� LANE USE SIGN R3-8B Q.,X30' 4 EA TOTAL 6 EA REVISIONS No. Q D1� IpnoN DATE 1 Q /1\ EDGE LINE STRIPING03/24/23 a Q IF srE 0 iPSIC SCALE I�FEET-aD 10 20 40 o LEGEND ❑A 4" SLID PVMT MARKING HAS (W) © 4" SLD PVMT MARKING HAS (Y) © 8" SLD PVMT MARKING HAS (W) ❑D LANE LEGEND ARROW (W) ❑E LANE LEGEND DEL ARROW (W) ❑F LANE LEGEND (W) WORD (ONLY) © 24" SLD PVMT MARKING HAE (W) (STOP BAR) �H 12" SITE PVMT MARKING HAE (W) (CROSSWALK) ❑I 8" SLD PVMT MARKING HAE (Y) ❑� 4" TY II -A -A (Y) ❑K 4" TY I-C (W) NOTES. 1. ALL SIGNS SHALL BE PLACED IN ACCORDANCE WITH THE TEXAS MUTCD 2 ALL EXISTING SIGNS THAT ARE REMOVED SHALL BE RETURNED TO THE CITY. t1t 8/14/2020 �It/1 y{ATxAA Kimley>>> Horn 801 Phone DN )5335-8511t 1Fox5(817)1335-5070WoMPE a .—t n No F-928 LYTY PROJECT #10100V-2 AIAPSCO NO. TAR-020P, 7AR-0200, MR-02OU CITY OF FORT WORTH, TEXAS TRANSPORTATION AND PUBLIC WORKS CAPITAL DELIVERY DIVISION BONDS RANCH ROAD & FM 156 INTERSECTION IMPROVEMENTS PAVEMENT MARKING & SIGNING PLAN BEGAN TO STA 209+50 DESIGNED NWP SCALE' DATE- SHEET DRAWN KRR CHECKED. OLS 1: 20 AUGUST 2020 C9.03 > q). sR -�-- n 2 �o x N.Sg 00 d-00 �I3 qU cPN /O/DOI-a 3- 11- a3 gd. E F,41 s GZ ? �I 1-7 �, APi 3�D,75 n AP- /Vo3,33x3l.- 7T z D x sa �1L-J- ZQ.z5442.5�t12_7t; 4 _H3,Y�+'1�1,17+ 931,7r+ 3S� 2i= 3/d.fto �LI M- _I- - --$ = �J-.3i � l G,o 00 v 7y Ate= sa Ap-36d'�s�x �g r��- f p Goxba- 37ao x,zfyG- D 'r �-W, SS /N�,75'x s`l �� X AP 1 i 7 9 E f SANITARYVS— / / LINE (X-19962) PROP 2" MILL AND TYPE D ASPHALT OVERLAY -10" ss ia" ss�i°" ss �1o" ss o ss o s EX R 1 OW x �x — x — x-- x x �x w9+oo so+oo 1s+oo Ifs@+ob 1 BEGIN 2" MILL ADD-", 2" TYPE D OVERLAY 49+o0 c XX c 9 11 BONDS RANCH RD Es ( oDeeO) RE5 ( oDEED) uL u o MMsroN , x 73061 M.CYARC x T . z _RAND DR -1 3oe11 c c r well ^^ °RTCT DRTcr c wee eou°s RANCx RD ess E eaxos RAxcN Ro wwcx xo = + �Lws ` .'P— se EX ROW ST _ Z (� 00 159+00' 1 0 m o W= Z_ n ry s of J PROP = TCE BONDS RAN RD CA Q a� oue— EX ROW— ER 36" PCPP WATER / LINE (X-15206)JJJ BONDS RANCH RD I III ACRE " SUN z tx c c F. ry — 5lx stexo)sNlyDRTCT I �'D I I g PROP DRAINAGE EASEMENT a AREA - 1817 SF� III`\Ip EX ROW-�L\\Ii SIT \p EX TREE TO BE REMOVED (TYP) RE. REMOVAL SHEETS III I I I I� END 2j 'MILL' IANO 1. Q 4y�o I�'o ED T. o CF ftoc. oKI 10365 BIE M°UN° ROAD w k 8" CONO \ 13 JAY. EET / EX ROW-- END 2" MILL AND iy O 00 o oc e W Q ro EX R.w 156 CA 2" TYPE 0 OVERLAY. w 11112 F ACRES�Ro ARC AND 163+OOe EX 24" RCP su2.NNrvAlc Tx�CA xIP �) BST2 DR CT �E������ A2' E%ROW" MILL AND / D OVERLAY ii, 206+31 REVISIONS Ni0. o 1Ee1I1TIMry DA E o :o GRAPHIC SCALE IN FEET 0 20 40 80 NORTH IF S.EET Is nx1 . A 11 1 - a LEGEND HA^VL°AS LTOERAY MAX TE-IN SLOPE 4:1 1 5' G—UT �20' EXISTIf — — 2_MAX y GROUN 0' 2" TYPE D HMAC TYP. MILL & OVERLAY 2" TYPE D HMAC EX VARIABLE DEPTH PAVEMENT 6" TYPE B HMAC ON STABILIZED SUBGRADE 8" FLEXIBLE BASE, Ty A. GR-1 MILL & TYPE D HMAC OVERLAY DETAIL SCALE H1-10' V: 1 2' 18/t4/2020 IIff1 If � E'AAi Kimley>>> Horn R— (El )8335-RAT 1Fox8(817)1335-5070 TEPE e9a-b— N. F-928 LYTY PROJECT IF101009-2 —SCO NO. TAR-020P, TAR-0200, DIR-02OU CITY OF FORT WORTH, TEXAS TRANSPORTATION AND PUBLIC WORKS CAPITAL DELIVERY DIVISION BONDS RANCH ROAD & FM 156 INTERSECTION IMPROVEMENTS ASPHALT OVERLAY PLAN BONDS RANCH RD BEGIN TO END DESIGNED NWP SCALE DATE SHEET DRAWN KRR 1: 40 AUGUST 2020 C5.04 CHECKED. OLS P (,,25 x. i , Dg -�' 33,+,11 3r'-l",2 12-4.9,x L� (fPAM/a/d,?-2 3- 1) -,2 2 6gaw A CRH COMPANY March 141", 2023 Mr. Brendan McInnes, P.E. Project Manager Transportation and Public Works T: (979) 220-0385 E: brendan.mcinnes@fortworthtexas.gov CPN: 101009-2 Project Name: Intersection Improvements at Bonds Ranch Rd & FM 156 RE: Request for additional contract time Dear Mr. McInnes, 420 Decker Drive, Suite 200 Irving, TX 75062 Phone: (214) 741-3531 As you are aware, we have experienced delays due to unforeseen material procurement lead times and material shortages that have delayed our completion of this project. Our team has been working diligently to get this project wrapped up for city handoff. New Signal Poles and Powder Coating The new signals were stamped approved for production on March 3, 2022, and we were immediately notified that these items were on a six-month lead time for delivery. We included this delay in our initial schedule and showed an optimistic finish date of February 3, 2023. We were able to complete some work before the delivery of the new signal poles, but we were handcuffed for the better part of 60 days of our schedule because the old poles could not be removed until the new poles were installed. Our project delays are mostly visible in our May through August schedule, showing minimal construction progress during this time. We elected to move the widening phasing to the back end of that time period so that we could focus all of our manpower into continuous phasing, as opposed to starting and stopping in intervals to allow for material procurement. On September 28, 2022, we were notified by the 48' mast arm supplier that their delivery date was pushed back to November, which set us even further behind in activating the intersection and removing the old signal pole foundations. We were finally complete with all widening, guardrail, and storm extension work moving into December, which is typically a difficult month to pave due to HMAC temperature and precipitation constraints. As of today, we are waiting on final thermo striping to be completed and one street sign to be erected to substantially complete this project. As stated previously, we are working tirelessly to finish this job for the city. Copies of our Progress Schedule Summaries, Project Schedule Updates, and Inclement Weather Delay Tracker are included at the end of this submittal for reference if desired. We are requesting a contract time extension to March 24, 2023, to allow us ample time to complete the remaining items on this project and schedule a final inspection. 6gaw A CRH COMPANY 420 Decker Drive, Suite 200 Irving, TX 75062 Phone: (214) 741-3531 Please review this TIA and let me know if you have any questions or concerns or would like to discuss this further. Thank you for your attention to this matter. Sincerely, J`I'G�.Q/IZ V Y F�J,SO/IZ. Adam Newsom Construction Manager T (214) 912-4282 E adam.newsomCcDtexasbit.com STRUCTURAL AND STEEL PRODUCTS 3001 W Pafford. Ft. Worth TX 76110 August 22, 2022 Bean Electrical Re: City of Fort Worth Intersection Improvements Bonds Ranch & FM 156 Structural & Steel Products: TL21415 Bean Electrical: 5129 (Job 2665-22) To whom it may concern, The above mentioned project bid was awarded to Structural and Steel Products on February 25, 2022. Structural and Steel was made aware of submittal approval and powder coating approval on April 18, 2022. The traffic poles were released for production on the same day, and the poles were originally scheduled for delivery in early September. Union Metal has fallen behind on their original schedule and have once again pushed back delivery to mid -late November. Union Metal has given no explanation for these delays. We have been notified that the fabrication on the poles has begun. We will do everything we can to make sure Union Metal sticks to their current schedule. Our company has stressed the importance of having this project completed in November. We are sorry for the delays, and hope to have the poles delivered in November. Thank you, Whit Richardson Structural & Steel Products, Inc ZUAW A CRH COMPANY July 51h, 2022 Mr. Brendan McInnes, P.E. Project Manager Transportation and Public Works T: (979) 220-0385 E: brendan.mcinnes@fortworthtexas.gov CPN: 101009-2 Project Name: Intersection Improvements at Bonds Ranch Rd & FM 156 RE: Monthly Project Schedule Summary — June 2022 - Activity Log Changes Nothing new to report - Activities Added/Deleted Nothing new to report 420 Decker Drive, Suite 200 Irving, TX 75062 Phone: (214) 741-3531 - Variance in Expected Finish Date Possibility of earlier finish if we work around existing pole foundations and demo/spot repair at a later date - Changes/Delays/Anticipated Problems As of today, July 5th, we are still looking at new signal pole arrival of early September Sincerely, Texas Materials Group, Inc. Adam Newsom Project Manager June 2023 Progress Schedule ID Task Adrvily ID (Task Name (Duration (Start Fimsh I%Complete (Total Slack (Predecessors (Successors 8 Mode t all CPN 101009-2 Bonds Ranch Rd & FM 256 382299 528 days Mon Dec 6 Wed May 17 11% 0 days 2 �» Pre -Construction 271 days Mon Dec 6 Fri Sep 2 D% 257 days 3 82 Pre -Construction 1 day Mon Apr 11 Mon Apr 11 0% 287 days 6 SSS,9SS 4 -' Material Procurement Delay (Traffic Signal Poles) 145 days Mon Apr 11 Fri Sep 2 0% 7 days 28 5 a 8250 Mobilization 1 day Mon Apr 18 Mon Apr 18 10% 282 days 3SS 6 ` 8200 Award Construct,," Contract 0 days Mon Dec 6 Mon Dec 6 0% 89 days 10 3,7,855 7 8210 SW3P 0 days Mon Dec 6 Mon Dec 6 0% 377 days 6 8 8220 Site Walk Through 1 day Tue Dec 7 Tue Dec 7 0% 376 days 6SS 9 8230 Notice to Proceed / Pre -Construction Meeting 0 days Mon Apr 11 Mon Apr 11 0% 288 days 3SS 14 10 8240 Pre -Construction / Public Meeting 1 day Mon Dec 6 Mon Dec 6 0% 89 days 6 11 Construction Contract Execution 225 days Mon Apr 11 Fri Feb 3 25% 73 days 12 83 Construction 225 days Mon Apr 11 Fri Feb 3 25% 73 days 13 ` Phase 1- New Traffic Signal Installation & Storm Drain Improvement 127 days Mon Apr 11 Tue Oct 4 45% 161 days 14 Temporary traffic control setup �1 day Mon Apr 11 Mon Apr 11 100% 0 days 9 15 15 Locate existing utilities; notify of any conflicts 1 day Tue Apr 19 Tue Apr 19 100% O days 14 16,17 16 _ Construction staking 1 day Tue Apr 19 Wed Apr 20 100% 0 days 15 21 17 SW3P Install 1day Wed May Wed May 100% 0days 15 19,18 18 Site clearing /tree removal 3 days Thu May 5 Mon May 9 100% 0 days 17 19 19 —' Install conduit bores 10 days Wed Apr 20 Tue May 3 100% 0 days 18,17 20 20 J — Conduit turn ups @ pole base 6 days Mon May 9 Mon May 16 100% 0 days 19 21 21 Install traffic signal foundations 6 days Tue May 17 Tue May 24 100% 0 days 20,16 22SS 22 Traffic signal cabinet rough in 6 days Thu May 12 Thu May 19 100% 0 days 21SS 23 23 Traffic signal cabinet foundation pour 14 days Fri May 20 Wed Jun 8 100% 0 days 22 24,26 24 Construct upstream storm drain ext Al A2 A3 3 days Thu Jun 9 Mon Jun 13 0% 239 days 23 27,25 25 Construct downstream storm drain ext A3 2 days Tue Jun 14 Wed Jun 15 0% 240 days 24 26 Fence Removal 1 day Thu Jun 16 Thu Jun 16 0% 239 days 27,23 27 Fence installation 2 days Tue lun 14 Wed Jun 15 0% 239 days 24 26 28 Receive new traffic signal poles 1 day Tue Sep 6 Tue Sep 6 0% 4 days 29 29 Bee.ae,Install new traffic signal poles 5 days Wed Sep 7 Tue Sep 13 0% 4 days 28 30 30 �» Install traffic signal equipment I3 days Wed Sep 14 Fri Sep 16 0% 4 days 29 31 31 s. Pull traffic signal wire and terminate 8 days Mon Sep 19 Wed Sep 28 0% 4 days 30 32FF 32 a Red flash intersection 30 days Thu Aug 18 Wed Sep 28 0% 4 days 31FF 33 33 Activate intersection 1 day Thu Sep 29 Thu Sep 29 0% 4 days 32 34 34 Remove existing traffic signal 3 days Fri Sep 30 Tue Oct 4 0% 4 days 33 35 35 4 8500 Inspection 0 days Tue Oct 4 Tue Oct 4 0% 4 days 34 92,37 36 4 Phase 2 - Bonds Ranch Rd Full Closure & Detour 10 days Wed Oct 5 Tue Oct 1S 0% 4 days 37 Construction staking 1 day Wed Oct 5 Wed Oct 5 0% 4 days 35 3855 38 a Traffic control reorganization 1 day Wed Oct 5 Wed Oct 5 0% 4 days 37SS 3955,4055 39 a Traffic detoursetup 1day Wed Oct Wed Oct 0% 4days 38SS 4155 40 Locate existing utilities; notify of any conflicts 0 days Wed Oct 5 Wed Oct 5 0% 4 days 38SS 41 41 4 Existing pavement removal 2 days Wed Oct 5 Thu Oct 6 0% 4 days 39SS,40 42 42 Flex base 3 days Fri Oct 7 Tue Oct 11 0% 4 days 41 43FS+3 days 43 R. Type B HMAC 2 days Mon Oct 17 Tue O<t 18 0% 4 da42 ysF5+3 days 44 44 8500 Inspection 0 days Tue Oct 18 Tue Oct 18 0% 4 days43 92,46 45 Phase 3 - NW & NE Corners -Asphalt Widening 19 days Tue Oct 18 Mon Nov 14 D% 4 days 46 Locate existing utilities; notify of any conflicts 0 days Tue Oct 18 Tue Oct 18 0% 4 days44 47 47 Remove existing pavement along NW and NE corners 3 days Wed Oct 19 Fri Oct 21 0% 4 days 46 48 48 Construction staking 1 day Mon Oct 24 Mon Oct 24 0% 4 days 47 49 49 Flex base 3 days Tue Oct 25 Thu Oct 27 0% 4 days 48 51FS+3 days,50SS 50 Commercial utility adjustments 2 days Tue Oct 25 Wed Oct 26 0% 145 days 49SS 51 4 Type B HMAC widening along NW and NE corners 3 days Wed Nov 2 Fri Nov 4 0% 4 days49FS+3 days 52 52 t Ditch grading 3 days Mon Nov 7 Wed Nov 9 0% 4 days Sl 53 Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024 N D 1 F M A M 1 1 A i 5 I O I N I D 1 F M A M 1 1 A S O N D l F M I Bean Electrical I Been Elea 11.1 ♦ 4/11 Crossroads I Bean Elec-ical 1 Fort Wort i Surveying I Southw tst Environmental Inc g Site So utions Bean Electrical e Bean Electrical e Bean Electrical e Bean Electrical Be in Electrical g III utz Construction R utz Construction Ste Solutions T wasBlt Bean Electrical Bean Electrical Bean Electrical Bean Electrical Bean Electrical Bean Electrical Bean Electrical ♦ 10/4 I Fort Worth Surveying Crossroads Crossroads • 10/5 I Silt Solutions g Site Solutions I TexasBit ♦ 10/18 rl ♦ 10/18 1 Site Solutions I Fort Worth Surveying I Site Solutions TexasBit 1 TexasBit 1 TexasBit Task Summary �1 Inadrve Milestone O Duration -only Start -only C Extemal Milestone ♦ cnncal Split ....... Project 101009-2_eonds Ranch • • • • • • • • • • • • • • • • Pro d Summa � I ,nad,,e Summa l l Manual Summa Rollu Fmsh-on 7 Deadline + Pro Date: Tue Jul5 SpIR le ry ry ry p ly gress Milestone • Inactive Task Manual Task Manual Summary r -----1 Extemal Tasks Critical Manual Progress Page 1 ID 53 la (Mode A—ily ID ` ` 8500 ` ® ` ` ` ` ` ` 8500 ` ` R ` see. 8500 a 8500 85 a 8510 4 8520 8530 8540 see. 90 9100 9110 9120 9130 9140 9150 9160 101009-2_Bonds Ranch Tue Jul5 (Task Name ADA ramps & sidewalk Inspection Phase 4-SE Corner- Asphalt Widening Traffic control reorganization Locate existing utilities; notify of any conflicts Construction staking Remove existing pavement along SE corner Concrete barrier wall removal MBGF removal Flex base MBGF install Type B HMAC widening along SE corner Ditch grading ADA amp Inspection Phase 5-SW Corner- Asphalt Widening Temporary pavement markings Traffic control reorganization Locate existing utilities; notify of any conflicts Construction staking Remove existing pavement along SE corner Flex base Type B HMAC widening along SW corner ADA amp Pedestrian pole foundation pour Pedestrian pole installation Ditch grading Inspection Phase 6 - Full Mill & Overlay Traffic control reorganization Full 2" surface mill Type D HMAC overlay (NIGHT) Temporary pavement markings Permanent pavement markings Remove traffic control devices Sod Inspection Inspections Inspection Final Inspection Complete Punch List Tasks Final Walk Through for Completed Punch List Tasks Construction Final Completion Closeout Closeout As -Built Survey Contract Reconciliation Submittals (Project Closeout Documentation) Notice of Completion/Green Sheet Final Construction Contract lnovice Paid Construction Contract Closed Lessons Learned Task Summary SpLt ................. I' -Summary Milestone • I —we Task 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 T 78 79 80 81 82 83 84 85 86 87 813 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 Project Date: (Duration (Start (Finish I%Complete (Total Slack (Predecessors (Successors I Half 1, 2022 Half 2, 2022 IHalf 1, 2023 Half 2, 2023 Half 1, 2024 I I I 13 days Thu Nov 10 Mon Nov 14 1 0% 4 days 52 N 54 D 1 F M A M l l A S O N 0 , 1 F M A M 1 1 A S 0 N 0 1 F M g Texas it '.. 0 days Mon Nov 14 Mon Nov 14 0% 4 days 53 92,56 ♦ 11/14 19 days Mon Nov 21 Thu Dec 15 D% 0 days I —I '... 1 day Mon Nov 21 Mon Nov 21 0% 0 days 54 57SS I 0 days Mon Nov 21 Mon Nov 21 0% 0 days 56S5 58 ♦ 11/21 1 day Mon Nov 21 Mon Nov 21 0% 0 days 57 59 I Fort Worth Surveying 3 days Tue Nov 22 Thu Nov 24 0% 0 days 58 6055,62 I Site Solutions 3 days Tue Nov 22 Thu Nov 24 0% 120 days 59SS 61 I TexasBit 1 day Fri Nov 25 Fri Nov 25 0% 120 days 60 63 I TexasBit 2 days Fri Nov 25 Mon Nov 28 0% 0 days 59 64FS+3 days F Site Solutions 3 days Mon Nov 28 Wed Nov 30 0% 120 days 61 I Crossroads 2 days Fri Dec 2 Mon Dec 5 0% 0 days 62FS+3 days 65 TexasBit 5 days Tue Dec 6 Mon Dec 12 0% 0 days 64 66 B Site Solutions 3 days Tue Dec 13 Thu Dec 15 0% 0 days 65 67 1 TexasBit 0 days Thu Dec 15 Thu Dec 15 0% 0 days 66 92,69 ♦ 12/15 22 days Fri Dec 16 Mon Jan 16 0% 0 days r1 2 days Fri Dec 16 Mon Dec 19 0% 0 days 67 70 1 Crossroads 1 day Tue Dec 20 Tue Dec 20 0% 0 days 69 71SS I Crossroads 0 days Tue Dec 20 Tue Dec 20 0% 0 days 70SS 72 ♦ 12/20 1 day Tue Dec 20 Tue Dec 20 0% 0 days 71 73 1 Fort Worth Surveying 3 days Wed Dec 21 Fri Dec 23 0% 0 days 72 74 1 Site Solutions 3 days Mon Dec 26 Wed Dec 28 0% 0 days 73 75FS+3 days 1 Site Solutions 2 days Tue Jan 3 Wed Jan 4 0% 0 days 74FS+3 days 76 1 TexasBit 3 days Thu Jan 5 Mon Jan 9 0% 0 days 75 79,77 1 Klutz Construction 3 days Tue Jan 10 Thu Jan 12 0% 87 days 76 78 1 Bean Electrical 2 days Fri Jan 13 Mon Jan 16 0% 87 days 77 N Bean Electrical IS days Tue Jan 10 Mon Ian 16 0% 0 days 76 88,80 B Site Solutions days Mon Jan 16 Mon Jan 16 0% 3 days 79 92,82 ♦ 1/16 14 days Tue Jan 17 Fri Feb 3 D% 0 days I"I 1 day Tue Jan 17 Tue Jan 17 0% 73 days 80 83 1 Crossroads 1 day Wed Jan 18 Wed Jan 18 0% 73 days 82 84 Dustrol 1 day Thu Jan 19 Thu Jan 19 0% 73 days 83 85,86FS+7 days TexasBit 11 day Fri Jan 20 Fri Ian 20 0% 83 days 84 TexasBit 3 days Tue Jan 31 Thu Feb 2 0% 73 days 84FS+7 days 87 Crossroads 1 day Fri Feb 3 Fri Feb 3 0% 73 days 86 Crossroads 3 days Tue Jan 17 Thu Jan 19 0% 0 days 79 91 Greenscaping 0 days Thu Jan 19 Thu Ian 19 0% 0 days 9155 92 ♦ 1/19 41 days Thu Jan 19 Fri Mar 17 0% 0 days r1 0 days Thu Jan 19 Thu Jan 19 0% 0 days 88 89SS ♦ 1/19 10 days Fri Jan 20 Thu Feb 2 0% 0 days 89,80,67,54,44,35 93 TexasBit 30 days Fri Feb 3 Thu Mar 16 0% 0 days 92 94 BBBBB TexasBit 1 day Fri Mar 17 Fri Mar 17 0% 0 days 93 95 1 TexasBit 0 days Fri Mar 17 Fri Mar 17 0% 0 days 94 97 ♦ 3/17 43 days Fri Mar 17 Wed May 17 D% 0 days r-1 0 days Fri Mar 17 Fri Mar 17 0% 0 days 95 98,99 ♦ 3/17 5 days Mon Mar 20 Fri Mar 24 0% 0 days 97 100 1 Fort Worth Surveying 130 days Mon Mar 20 Fri Apr 28 0% 11 days 97 101 38 days Mon Mar 27 Wed May 17 0% 0 days 98 0 days Fri Apr 28 Fri Apr 28 0% 11 days 99 102 ♦ 4/28 1 day Mon May 1 Mon May 1 0% 11 days 101 103 0 days Mon May 1 Mon May 1 0% 11 days 102 104 ♦ S/1 1 day Tue May 2 Tue May 2 0% 11 days 103 I �1 In.d— W.A.- Duration -only Start -only C External Milesrone ♦ cnacal Split ....... .......... � I In—e Summary I I Manual Summary Rdlup Finish -only ] Deadline + Progress Manual Task Manual Summary r-1 EMemal Tasks cntical Manual Progress Page 2 July 2023 Progress Schedule B ha� A1dvM 10 hazk xame ourzuon sun f;n;sn ss eo p hmnl s;a<k vreaxersors su<essors aesource xames enu<al Amal sun Amal fmizn $ S Cpx 101009-28antls RancM1 Rtl8FM 356381299 628 Wp 2/6/21 /1,/23 31% Odap Yu 12/6/EI 2 $ �, preConnNn.an 272 dap 12/6/21 9/2/22 099 25]dap Na 12/6/21 3 10 s e2 1re-Cmsz1.1— lady w11n2 4/11/22 0% 287day6 sss,9ss No 4/11/22 Mammal P1.1.1eme.1D ley Rroff.< sgnal PmeO 14s d., 4/11/z2 9/2/22 0% ) y za Bean El--i N. NA s ]ia M. 8250 Mobilization lady 4/13/22 4/18/22 1. 282 days 355 Bean Ele —1 No 4/1.1n 4 8200 Award Constr—C-t—t 0days 12/6/21 12/6/21 0% 89 day ]0 3.Z0ss No NA s duo swap 0d.y, 12/6/u 12/6/21 0% 3n p — N. NA S S22o Sue Walk Through 1my 12/2/21 12p/21 0% 3]6 days 655 No NA a az3o nonce to Proceed/ pre<o.m.nm. Meenne 0days 4/11/22 4/1v22 0% 288 day ass 14 No NA a R. 8240 Pre C.nmum—/Pubbc Mee.ng laav 12/6/21 1z/6/22 0% 09 dap 6 No NA t ti co,etMmpn uno-an Faxul1- zas mvs 4/11/zz z/3/z3 z6% 73 day No 4112/22 p 83 mnnron.a. —day. 4/11/12 213/23 26% 73 p — N. 4/11/22 PNau 1-N. Traffla Slgwllnstellatl.n&Sturm Dram lmprov ..1127 days 4/11/22 10/4/22 47% 262 days N. 4111/22 4 ✓ 4 Tampoary traffk rontrol setup lday 4/11/22 4/11/2z l00% 0day9 15 Crossroads No 4/12/zz 5 ✓ 4 Locate ex. g blines, n.tdy ora.y c.nR.ms 1day 4/19/22 4/19/22 S00% 1days 14 1,17 Bean Ele 111 N. 4/19/22 6 ✓ S mnsnvnion staung lady 4A1n/ -4/zD/22 1. 0aay 15 1 Fanwonn 1—ymg No 4/19/ 17 ✓ p SW3p Install 1 ay 5/4/22 5/4/22 1W% 0 day 15 1%18 Southwest EnWronmenmllnc No 514122 e ✓ q sue clearing /tree removal 3days 5/5/22 5/9/22 100% 0dap ]) 1I1e5olut1o.z No 5/1/22 9 J R I-.11 conduit bores 30 day 4/2W/ l 5/3/22 100% Oday le,l] Bean El--1 No 4/20/2z z. ✓ a m.aua m .pa a p.le bane 6d.y, 5/9/22 5/16/22 100% o d.p dean Nean<,I N. 5/9/22 t ✓ S Innall traffksignalfoundatlonz 6dy 5112/22 5n4/22 100% 0d.W 20,16 Bean Elendcal No s/lln3 22 ✓ m, Tnarec signal tub —rough.. 6dap s/12/22 5/19/22 100% 0bW 21SS 23 Bean Ei—ical No 5/12/22 2.3 ✓ T—signal nab.., mood,... Dour 14 days 5/20/22 6/8/22 S00% 0dap 22 6 Bean Elemncal No 5120122 ti —t—tp tream norm dram exl Al az A3 3aays 6/9n2 6/13/22 0% —day 23 5 gmt: C.11-111on No NA s m.nro<te.w.aneamsmrm aro.. extA3 zd., 6/14/22 6/15/22 0% z p 24 kwe C..—I... — N. NA Fence Removal lacy 6/16/22 6/16/22 0% 2. day 27,23 511e 5alut1om No NA ✓ F4 Fence.mmllanon day, 6/14/22 6/15/22 100% 0day 24 26 T—,B.t No 6/14/zz zd �Sq Rem.ne.ewtre0i<a.g.al P.1- 1 d.y 9/6/22 9/6/22 0% 4d1p4 21 dean El 111 N. NA dS Innall new traffic 1,g 101., 1days 917/22 9/13/23 0% 4my 28 Bean E-ft.l No NA p Insta111-., .g equp ent 3days 9/14/22 9/16/22 0% 4 d.y, 29 31 Bean El--i No NA r , PW1— signal wbe and terminate eddy, 9/n/22 9/28/22 0% 4dap 30 F Bean Elettrical No NA R Retl ilazM1.nmrsen.on 30 day 8/18n2 9/28/22 0% 4my 31FF Bean EleRk.1 No NA �, A<mam mtereen..n 1 d.y 9/21/22 9/29/22 0% a d., 32 M.. Ei—... I — N. NA Remove ...sting traffic signal 3days 9/30/22 10/4/22 0% 4day 33 35 Bean Elettdcal No NA Odays 10/4/22 10/4/22 0% 4by, 34 92,37 No NA �, Pnase2-eantls Ran<M1 Rd FUIl tlasureeDemur SO dap 10/5/22 10/28/22 099 •days No NA —tr.mm�:—g lady 1o/s/2z 1o/s/22 0% 4aay 35 3ess Fon won. S.rveymg No NA Tnar6«.no-.1 g an.. 1 d.y 10/5/21 10/5/22 0% 4 y 37SS 39se,4oss cm:ar.ada N. NA r , Tlamc demur setup lady 10/5/22 1015/22 D% 4dap3855 411 clomoad, N. NA S Locate exrsimg unlR.ez, notdy of anY conmds 0days W/s/22 1o/s/2z 0% 4day 38SS 41 Bean Elenncal No rvA z d.y, M/5/21 10/6/22 0% 4 p 39SS,40 4z s.e N. NA Fka base 3aays 10/7/22 10/11/22 0% 4day 41 43FS.3 days sge solunonz No NA SType HMAC 2days 11/11/22 10/18/23 0% 4dap 42f5.3 days 44 T-0.1 No NA as0o Insce<.o. 0aay. 10/18/22 10/18/22 0% 4dap 43 92,46 No NA 4s t Pnaae 3-1- s NE comeN-A h.lt •ndenmg 19 day 10/1a/zz n/m/zz o% 4aays No NA 46 �, Inane a:. g bne., ..tdy or..Y-0.na 0d.y, 10/18/22 10/18/22 0% a d., 47 Texa.B., N. NA Remove existing Pavement al.ng NW and NE comers 3aays M/19/z2 10/21/22 D% 4day 46 4e See—tl— No NA 4 —tnuction smkng lady 10/24n2 10/z4/22 0% 4da 47 49 fort Wonn surveying No NA Fkx base 3 y SO/25/22 10/27/22 0% 4dap ae 11Fs13 p,o5551 Solutions No NA Wmme.lal uugn adornments zaays 1o/zs/zz 1012Wz2 0% 145 day 49s5 Texaselt No NA t �, ype HMAcwd—N alone NW and NE 3days 11/2/22 1114/22 0% 4 ay 49f5.3 days 52 Te.,aB., N. NA Dilh grading 3days 111/7/21 I11/9n2 0% 4dap 51 Te-I, No NA Dale 8/29n2 • +2/6 ♦ lz/6 Bean Demi<al Nq Bean E—H-1 NA Bean Elec[n<al NA NA ♦ 10/4 rf I Fon wan. wroeyl.9 NA NA roNroaae NA NA NA ♦ +0/s sl<. solutions NA E a ed 4 10/18 NA 4 10/18 NA g sNe SoluHonz ryq I nWonM1 Su y g NA g smmm.a NA NA TexaaBn _ S a z z 0 > > > > z z > z > > > > 0 > > > > > > > > z z > z 0 z z z z z z > > > > > > > > > > > z > z z z z 6gaw A CRH COMPANY September 2"d, 2022 Mr. Brendan McInnes, P.E. Project Manager Transportation and Public Works T: (979) 220-0385 E: brendan.mcinnes@fortworthtexas.gov CPN: 101009-2 Project Name: Intersection Improvements at Bonds Ranch Rd & FM 156 RE: Monthly Project Schedule Summary — August 2022 - Activity Log Changes Nothing new to report - Activities Added/Deleted Nothing new to report - Variance in Expected Finish Date Storm extension completion was delayed, finished 8/31 Flex base install begin around 9/19 Full closure dates please begin 9/19 Message boards to be put out 9/6 420 Decker Drive, Suite 200 Irving, TX 75062 Phone: (214) 741-3531 - Changes/Delays/Anticipated Problems New signal pole arrival of early September Cabinet assembly lead time is early October as of today Swiss hammer testing on signal foundation came back with promising results, we plan on coring the foundation next week for further testing Sincerely, Texas Materials Group, Inc. J`III-L v/Y2 1501M Adam Newsom Project Manager 1 E _ r E� m m$ x� e a ~� P N-■-■- s l i _ S [ ; a Al • p c ♦ I f _ I s_ s z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z z F e z z a>> a a z z a z a a a a g a a a a a a a a z z a z a z z z z z z a a 0 a>>> a a a a z a z z z z I � S a 3 0 3 S S = v .......... . ommomerr m ........... �M oo�000000000000�000000a00000�00000000�000mo�00000000 �E „-,m,,,-,,,,, I .» o .. .. o .. m .» .L 0 0 E - � _ 3 m u 9 s < m m m m m m m m P a a m m a a a Y Y Y Y Y Yip Y Y Y Y Y Y Y Y p_ Y Y Y Y Y Y if jr k Y jr jr Y L Y Y Y Y Y Y Y Y Y Y Y it it Y Y Y Y Y Y Y Y $c db q q _ � $ � m 9t S, 9 • 3 $ e $ 6 • ffi R r r r F � $ • � $ m � & A m � $ & 8 % TEXAS420 Decker Drive, Suite 200 Irving, TX 75062 Phone: (214) 741-3531 A CRH COMPANY Date: 3/14/2023 Notice to Proceed: 4/11/2022 Project Manager: Adam Newsom Substantial Completion: 2/7/2023 Estimated Final Completion: 3/24/2023 Project #: 381299 Job: 101009-2 Bonds Ranch Rd Intersection Improvements Delay Description Start Date End Date IDays Requested �] Precipitation Delay 11/4/2022 11/4/2022 1 Precipitation + Temperature Delay 11/14/2022 11/14/2022 1 Precipitation Delay 11/23/2022 11/26/2022 4 Preciptation Delay 12/8/2022 12/8/2022 1 Precipitation Delay 12/10/2022 12/10/2022 1 Precipitation Delay 12/13/2022 12/13/2022 1 Temperature Delay 12/19/2022 12/22/2022 4 Christmas Holiday 12/27/2022 12/29/2022 3 Precipitation Delay 1/24/2023 1/24/2023 1 Precipitation + Temperature Delay 1/30/2023 2/3/2023 5 Temperature Delay 2/8/2023 2/8/2023 1 Temperature Delay 2/10/2023 2/10/2023 1 Temperature Delay 2/17/2023 2/18/2023 2 Temperature Delay 2/24/2023 2/25/2023 2 Precipitation Delay 3/1/2023 3/3/2023 3 Precipitation Delay 3/9/2023 3/9/2023 1 32 FORT WORTH. Routing and Transmittal Slip Transportation & Public Works Department DOCUMENT TITLE: Construction Change Order No. 3 — Bonds Ranch at FM 156 M&C: 21-0786 CPN: 101009 Date: To: Name 1. Bus. Support Partner — Alexiz Ramirez 2. Adam Newsom — Contractor TexasBit 3. Habte Taezaz - Inspector 4. Brendan McInnes — Project Manger 5. Shweta Rao Contract Compliance Mngr 6. Chad Allen — Program Manager 7. Lissette Acevedo - Snr CPO 8. Michael Owen — Interim Asst. Director 9. Lauren Prieur — Director 10. Doug Black 11. William Johnson 12. Jannette Goodall 13. TPW Contracts CSO: 57092 DOC#: 1 Department Initials Date Out TPW-initialer Jun 2, 2023 Contractor - sign Jun 5, 2023 TPW - signature !i Jun 4, 2023 TPW-initial B� Jun 5, 2023 TPW - signature BLM•� Jun 5, 2023 TPW - signature Jun 5, 2023 TPW - signature o Jun 6, 2023 TPW - signatures Jun 6, 2023 TPW - signatures Jun 6, 2023 Legal - signatures Jun 7, 2023 LV CMO - signature W, Jun 7, 2023 CSO - signature. — Jun 8, 2023 TPW DOCUMENTS FOR CITY MANAGER'S SIGNATURE: All documents received from any and all City Departments requesting City Manager's signature for approval MUST BE ROUTED TO THE APPROPRIATE ACM for approval first. Once the ACM has signed the routing slip, David will review and take the next steps. NEEDS TO BE NOTARIZED: ❑YES ®No RUSH: []YES ®No SAME DAY: ❑YES ®No NEXT DAY: ❑YES ®No ROUTING TO CSO: ®YES ❑No Action Required: ❑ As Requested ❑ For Your Information ® Signature/Routing and or Recording ❑ Comment ❑ File ❑ Attach Signature, Initial and Notary Tabs Return To: TPWContracts(a)fortworthtexas.00v, for pick up when completed; list "Please call Brendan ext # 2617 for questions. Thank you. "