HomeMy WebLinkAboutContract 53181-CO5CSC No. 53181-005 FORT 'WORTm City of Fort Worth 1"oW Change Order Request ProjectName] Watercress Low Pressure Sewer Extension Project No.(s):I 56016-0700430-CO1783 1 DOE No. I N/A City Sec No,: l 53181 City Proj. No.: I 101002 Project Descriplion:l Extend low pressure sewer in Watercress Drive and connecting streets, Install grinder pumps at each home. Contractor.) William J. Schultz, Inc. dba Circle C Construction Co 1 Change Order # 5 1 CityProject Mgr.1 Walter Norwood CityInspector: 1 Shane Behn Phone Number:l 817-392-5026 I Phone Number:) (817)392-2190 Dept. Original Contract Amount Extras to Date Credits to Date Pending Change Orders (in M&C Process) Contract Cost to Date Amount of Proposed Change Order Revised Contract Amount Original Funds Available for Change Orders Remaining Funds Available for this CO Additional Funding (if necessary) Unit 1 Sewer Unit 2 Paving j Unit 3 Water $4,905,476.50 $510,107.60 $0.00 $93,596.60 $0.00 $59,400.00 $4,999,073.00 $510,107.50 $59,400,00 - 444,665.00 �0.00 444,565.00 1503,965.00 $ ,554,508,00 $510,107.50 $147,164.00 $25,505.00 $0.00 $53,567.50 $25,505.00 $0.00 CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT MAXALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST+ 2591o) JUSTIFICATION (REASONS) FOR CHANG5 ORDER Date: 1 6/6/2023 1 Totals Contract Time Calender days) $5,415,584.00 �310 $152,996.50 0350 $5,668,580.60 11l080 0.00 120 $5,5 8,580.50 1,200 $172,669.00 $79,072.50 2,83% $6,769,480.00 Change Order No. 5 will provide for water main extensions in order to provide water services to additional customers on Ella Young Drive, Sommerville Place Road and Jarvis Way. Water main extension will take place on Jacksboro Highway (Surfside Dr. to City limit), Sommerville Place Road (Ella Young Drive to Tyler Place) and Tyler Place (Sommerville Place Road to Ella Young Drive). The affected locations are currently provided water by Lakeside but must be converted to Fort Worth water per the terms of the Transfer Agreement with Lakeside. The cost for Change Order No. 5 is actually $444,565.00. However, Change Order No. 5 will also include the deletion of various Sanitary Sewer items that totals $444,565.00 resulting in a net amount of $0.00. Therefore no additional appropriations are needed to execute Change Order No. 5. Staff recommends the addition of 120 calendar days for the additional work. It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full (both time and money) for all costs arising out of, or incidental to, the above Change Order. Contractor's Company Name Contractor Name I _-.6ontractor Signature Date William J. Schultz, Inc. dba Circle C Construction Co Terri Skellv —7- L S IrApeclor +1 i'211a, s-Q,01X 64 "Ad Director (Water Dept) Chrostophe✓ Na�cJe� Senior Assistant City Attorney Date Prolect Manager Date Construction Supervisor (Water Dept) Jun 7, 2023 -- Date Assistant City Manager Jun 7, 2023 Council Action -(If Reoulred) Date ry �7 �7v� . Date Date Jun 7, 2023 M&C Number 1 23.0405 1 M&C Date Approved 1 5123/2023 1 I OFFICIAL RECORD CITY SECRETARY FT. WORTH, TX Fo RT Wo RT H City of Fort Worth Change Order Additions Project Name Watercress Low Pressure Sewer Extension City Sec No.: 1 53181 Project No.(s): 56016-0700430-CO1783 ! DOE No.1 N/A City Proj. No.: 1 101002 Project I Extend low pressure sewer in Watercress Drive and connecting streets. Install grinder pumps at each home. Description Contractor William J. Schultz, Inc. dba Circle C Construction Co Change Order: 5 Date:1 6/6/2023 City Project Mgr. Walter Norwood City Inspector I Shane Behn ADDITIONS IIF-M UESCRINIIUN DEPT Qty ,Unit 'Unit Cost Total 1 Thermal Expansion Tank Unit 3 Water 28 EA $550.00 $15,400.00 2 Pressure Reducing Valve Unit 3 Water 28 EA $725.00 $20,300.00 3 Install Meter/Provide and Install Meter Box Unit 3 Water 28 EA $525.00 $14,700.00 4 8" PVC Water Pipe by Open Cut Unit 3 Water 1,648.00 LF $125.00 $206,000.00 5 6" PVC Water Pipe by Open Cut Unit 3 Water 51.00 LF $95.00 $4,845.00 6 Ductile Iron Water Fittings w/ Restraint Unit 3 Water 1.00 TN $12,500.00 $12,500.00 7 Fire Hydrant Unit 3 Water 2.00 EA $6,500.00 $13,000.00 8 Connection to Existing 4"-12" Water Main Unit 3 Water 3.00 EA $6,500.00 $19,500.00 9 Connection to Existing 24" Water Main Unit 3 Water 1.00 EA $18,500.00 $18,500.00 10 1" Private Water Service Unit 3 Water 13.00 EA $100.00 $1,300,00 11 8" Gate Valve Unit 3 Water 2.00 EA $1,800.00 $3,600.00 12 Temporary Asphalt Paving Repair (with Asphalt and Flex Base) Unit 3 Water 1,800,00 LF $40.00 $72,000.00 13 Gravel for Driveways & Alleyways Unit 3 Water 144.00 SY $55.00 $7,920.00 14 Construction Staking Unit 3 Water 1.00 LS $7,500.00 $7,500.00 15 Construction Survey (GPS Red Line Survey) Unit 3 Water 1.00 LS $7,500.00 $7,500.00 16 Traffic Control Unit 3 Water 3.00 MO $4,500.00 $13,500.00 17 SWPPP >_ 1 acre Unit 3 Water 1.00 LS $6,500.00 $6,500.00 jUnit 1 Sewer jUnit 2 Paving iUnit 3 Water $444,565.00 Page 2 of 4 Additions Sub Total $444,565.00 FOPT WORTH City of Fort Worth -1' _ - Change Order Deletions Project Name Watercress Low Pressure Sewer Extension ! City Sec No.: Project No.(s): 56016-0700430-CO1783 DOE No. I N/A City Proj. No.: Project I Extend low pressure sewer in Watercress Drive and connecting streets. Install grinder pumps at each home. Description 53181 101002 Contractor I William J. Schultz, Inc. dba Circle C Construction Co I Change Order 5 Date I 6/6/2023 City Project Mgr, Walter Norwood City inspector: I Shane Behn DELETIONS ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total 30 5' Wide Asphalt Pvmt Repair 12" HMAC,10" Conc. Base Material) Unit 1 Sewer 3775.822727 LF $55.00 $207,670.25 Temporary 5-ft high Construction Fence, Metal Posts on Park Land Unit 1 Sewer 32 as directed by Owner. 39 2" Surface Milling Unit 1 Sewer 40 6" Concrete Driveway Unit 1 Sewer 66 1-1/4" HDPE (DR11) Discharge Line Unit 1 Sewer Page 3 of 4 10,552.00 LF $10.00 $105,520.00 6,650.00 SY $5.00 $33,250.00 658.35000 SF $25.00 $16,458.75 4,537.00 LF $18.00 $81,666.00 (Unit 1 Sewer $444,565.00 jUnit 2 Paving (Unit 3 Water IDeletions Sub Total $444,565.00 MIWBE Breakdown for this Change Order MWBE Sub Type of Service Amount for this CO Total $0.00 Previous Change Orders co# DATE AMOUNT Total $0.00 Page 4 of 4 City of Fort Worth, Texas Mayor and Council Communication DATE: Tuesday, May 23, 2023 LOG NAME: 60WCRESSLPSSIC05-CIRCLEC REFERENCE NO.: **M&C 23-0405 SUBJECT: (CD 7 / Future CD 7) Authorize Execution of Change Order No. 5 with a Net Total Amount of $0.00 After Deducts, and the Addition of 120 Calendar Days to a Contract with William J. Schultz, Inc. dba Circle C Construction Company for Watercress Low Pressure Sanitary Sewer Extension Project and to Effect a Portion of Water's Contribution to the Fiscal Years 2023-2027 Capital Improvement Program RECOMMENDATION: It is recommended that the City Council authorize execution of Change Order No. 5 with a net total amount of $0.00 after deducts and the addition of 120 calendar days to City Secretary Contract No. 53181 with William J. Schultz, Inc. dba Circle C Construction Company for Watercress Low Pressure Sanitary Sewer Extension project (City Project Number 101002). DISCUSSION: In January 2007, the City Council adopted the Lake Worth Capital Improvements Implementation Plan. The plan included a number of water and sewer projects designed to provide Fort Worth Water Department services to areas around Lake Worth previously served by septic systems. To date, projects have been completed to provide water/sewer service to the Landmark/Quebec and Woodvale areas and water service has been provided along Watercress Drive. On November 19, 2019, Mayor and Council Communication (M&C 19-0331), the City Council authorized a contract with William J. Schultz, Inc. dba Circle C Construction Company, (City Secretary Contract No. 53181) in the amount of $5,415,584.00 for the installation of a low pressure sanitary sewer system and individual grinder pumps on Watercress Drive, Peninsula Club Drive, Sunset Point, North Lake Drive, Island View Drive and Lupine Circle. The contract was subsequently revised by Change Order No. 1 with a net total of $0.00 authorized administratively on July 23, 2020 that provided for a 3 inch diameter Force Main with a thicker wall to satisfy cleanout velocity, Change Order No. 2 in the amount of $93,596.50 after deducts authorized administratively September 1, 2020, allowed for the relocation of a portion of Peninsula Drive and water main abandonment on Watercress Drive, Change Order No. 3 with a net total amount of $0.00 authorized administratively May 7, 2021 that provided for the installation of low pressure sewer service by directional drilling and Change Order No. 4 in the amount of $59,400.00 authorized September 13, 2022 (M&C 22-0720) that provided for the installation of 33 water service meter boxes to the existing water mains on Ella Young Drive, Sommerville Place Road and Jarvis Way. Change Order No. 5 will provide for water main extensions in order to provide water services to additional customers on Ella Young Drive, Sommerville Place Road and Jarvis Way. Water main extension will take place on Jacksboro Highway (Surfside Dr. to City limit), Sommerville Place Road (Ella Young Drive to Tyler Place) and Tyler Place (Sommerville Place Road to Ella Young Drive). The affected locations are currently provided water by Lakeside but must be converted to Fort Worth water per the terms of the Transfer Agreement with Lakeside. The cost for Change Order No. 5 is actually $444,565.00. However, Change Order No. 5 will also include the deletion of various Sanitary Sewer items that totals $444,565.00 resulting in a net amount of $0.00. Therefore no additional appropriations are needed to execute change order No. 5. Appropriations for Watercress Low Pressure Sanitary Sewer Extension project are as depicted below: Fund Existing Additional Project Total* Appropriations Appropriations General Capital Projects — Fund $610,600.00 $0.00 $610,600.00 30100 Lake Worth Gas $6,184,976.00 $0.00 $6,184,976.00 Lease Capital Project — Fund 33001 Project Total II $6,795,576.0011 *Numbers rounded for presentation purposes. II $0.0011$6,795,576.00 DVIN: A waiver of the goal for Business Equity subcontracting requirements was requested, and approved by the DVIN, in accordance with the applicable Ordinance, because the application of the provisions of this ordinance will impose an economic risk on the City or unduly delay acquisition of the goods or services. The contractor was able to successfully document good faith effort on the original contract and a 0\% MWBE goal assigned. Change Order number 5 will have a net change of $0 after deducts of an equivalent amount. Funding is budgeted and encumbered in the Wastewater Public Utility Department 0700430 and upon approval of this M&C, funds will be moved to the Water Public Utility Department 0600430 for the purpose of funding the Watercress LP SS Extension project all within the Lake Worth Gas Lease Cap Project Fund. This project is located in COUNCIL DISTRICT 7 and Future COUNCIL DISTRICT 7. FISCAL INFORMATION / CERTIFICATION: The Director of Finance certifies that funds are currently available in the Lake Worth Gas Lse Cap Project Fund for the Watercress LP SS Extension project. Prior to any expenditure being incurred, the Water Department has the responsibility to validate the availability of funds. FUND IDENTIFIERS (FIDs): TO Fund Department ccount Project Program) ctivity Budget Reference # mount ID IA I ID I I Year I (Chartfield 2) 1A FROM Fund Department ccount Project Program ctivity Budget Reference # mount ID IA I ID I I Year I (Chartfield 2) CERTIFICATIONS: Submitted for Citv Manager's Office bv: Dana Burghdoff (8018) Originating Department Head: Chris Harder (5020) Additional Information Contact: Walter Norwood (5026) ATTACHMENTS 1. 60WCRESSLPSS1CO5-CIRCLEC Form 1295.pdf (CFW Internal) 2.60WCRESSLPSS1C05-CIRCLEC MAP.pdf (Public) 3.60WCRESSLPSS1C05-CIRCLEC SAM.pdf (CFW Internal) 4. 60WCRESSLPSS1C05-CIRCLEC Waiver Form. pdf (CFW Internal) 5. 60WCRESSLPSSIC05-CIRCLEC FID Table (WCF draft 03.26.23).xlsx (CFW Internal) 6.60WCRESSLPSSIC05-CIRCLEC.docx (CFW Internal) 7. PBS CPN 100261.Ddf (CFW Internal) # (Fund (Dept# (Account ProjectlD Rec # I Fund I Dept # Account I Project ID Activity Rec # I Fund I Dept # lAccount ity FIDs Bud et Budget CF 2 Program Amount Year Budget CF 2 Program I Amount Year 7EXPE-I SE - No KK or GL Entries Needed udget iCF2 (Program Amount ear Purpose Purpose Purpose Xfer Xfer Xfer Contract Compliance Manager By signing 1 acknowledge that I am the person responsible for the monitoring and administration of this contract, including ensuring all performance and reporting requirements. Signature Walter Norwood Name of Employee Project Manager Title ATTEST: Jannette Goodall City Secretary OFFICIAL RECORD CITY SECRETARY FT. WORTH, TX