HomeMy WebLinkAboutOrdinance 26217-06-2023ORDINANCE NO.26217-06-2023
AN ORDINANCE ADJUSTING ESTIMATED RECEIPTS AND
APPROPRIATIONS IN THE STORMWATER CAPITAL PROJECTS FUND BY
INCREASING ESTIMATED RECEIPTS AND APPROPRIATIONS IN THE 2022
BOND YEAR 3-CONTRACT 17 PROJECT (CITY PROJECT NO. 104323) IN THE
AMOUNT OF $15,000.00 AND DECREASING ESTIMATED RECEIPTS AND
APPROPRIATIONS IN THE DRAINAGE IMPROVEMENTS PROGRAMMABLE
PROJECT (CITY PROJECT NO. P00043) BY THE SAME AMOUNT; PROVIDING
FOR A SEVERABILITY CLAUSE; MAKING THIS ORDINANCE CUMULATIVE
OF PRIOR ORDINANCES; REPEALING ALL ORDINANCES IN CONFLICT
HEREWITH; AND PROVIDING AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH,
TEXAS:
SECTION 1.
That in addition to those amounts allocated to the various City departments for Fiscal Year 2022-2023 in the
Budget of the City Manager, there shall also be adjusted estimated receipts and appropriations in the
Stormwater Capital Projects Fund by increasing estimated receipts and appropriations in the 2022 Bond Year
3-Contract 17 project (City Project No.104323) in the amount of $15,000.00 and decreasing estimated receipts
and appropriations in the Drainage Improvements Programmable Project (City Project No. P00043) by the
same amount.
SECTION 2.
That should any portion, section or part of a section of this ordinance be declared invalid, inoperative or void
for any reason by a court of competent jurisdiction, such decision, opinion or judgment shall in no way impair
the remaining portions, sections, or parts of sections of this ordinance, which said remaining provisions shall
be and remain in full force and effect.
SECTION 3.
That this ordinance shall be cumulative of Ordinance 25773-09-2022 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance are in
direct conflict with such other ordinances and appropriations, in which instance said conflicting provisions of
said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
APPROVED AS TO FORM AND LEGALITY:
Ate' l
Dffi ck(Jun 20,202319:12CDT)
Assistant City Attorney
ADOPTED AND EFFECTIVE: June 13, 2023
CITY SECRETARY
Jannette S. Goodall
City Secretary 000FP,aF°,
47 ° O°.vi°
�'01000 0
D* o °o-10
°O 0 �.LA
Y 000000°° 0
aII�' nos v�
Mayor & Council Map
2022 Bond, Year 3, Contract 17 1 CPN #104323
CD #5, #8/Future CD #8
FORT WORTH
City of Fort Worth, Texas
Mayor and Council Communication
DATE: 06113123 M&C FILE NUMBER: M&C 23-0465
LOG NAME: 2022 BOND YEAR 3-CONTRACT 17 - LIM
SUBJECT
(CD 5 and CD 8) Authorize Execution of an Engineering Agreement with Lim & Associates, Inc., in the Amount of $513,158.40 for Combined
Water, Sanitary Sewer, Stormwater, and Street Paving Improvements for 2022 Bond Year 3-Contract 17 Project, Adopt Appropriation Ordinances
to Effect a Portion of Water's Contribution to and Amend the Fiscal Years 2023-2027 Capital Improvement Program (2022 Bond Program)
RECOMMENDATION:
It is recommended that the City Council:
1. Authorize execution of an engineering agreement with Lim & Associates, Inc., the amount of $513,158.40 for combined water, sanitary
sewer, stormwater, and street paving improvements for 2022 Bond Year 3-Contract 17 project (City Project No. 104323);
2. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the Water and Sewer Capital Projects Fund
in the amount $439,768.00, transferred from available funds within the Water and Sewer Fund, for the purpose of funding the 2022 Bond Year
3-Contract 17 project (City Project No. 104323) to effect a portion of Water's Contribution to the Fiscal Years 2023-2027 Capital
Improvement Program;
3. Adopt the attached appropriation ordinance adjusting appropriations in the 2022 Bond Program Fund by increasing appropriations in the
2022 Bond Year 3-Contract 17 project (City Project No. 104323) in an amount of $401,810.00 and decreasing appropriations in the Street
Improvement -Deteriorating Streets programmable project (City Project No. P130019) by the same amount;
4. Adopt the attached appropriation ordinance adjusting estimated receipts and appropriations in the Stormwater Capital Projects fund by
increasing estimated receipts and appropriations in the 2022 Bond Year 3 - Contract 17 project (City Project No. 104323) in the amount of
$15,000.00 and decreasing estimated receipts and appropriations in the Drainage Improvements programmable project (City Project No.
P00043) by the same amount; and
5. Amend the Fiscal Years 2023-2027 Capital Improvement Program.
DISCUSSION:
This Mayor and Council Communication (M&C) is to authorize the preparation of plans and specifications for this Year 3 Neighborhood Streets
Improvements project associated with the 2022 Bond Program. For 2022 Bond Year 3-Contract 17 project, this includes water, sanitary sewer,
stormwater and street paving improvements on 3.19 lane miles, on the following streets:
Street
From J
To
i Scope
Vaughn
Wichita
Hardeman
Boulevard
Street
Street
Paving/Water/Sewer/Stormdrain
Martin Luther
Baylor
Vaughn
King
Paving
Street
Boulevard
Freeway
Bishop
Street
Martin Luther
Freeway King
Martin Luther
Leedtreet
Paving/Water/Sewer/Storm i
Drain
Bright
Street
King
Vaughn
Boulevard
Paving/Water/Sewer
Freeway
Rufus
rK,an Luther
way
Vau hn
9Street
Boulevard
Paving
Martin Luther
hn
E,ydney
t
King
Vau
Boulevard
Paving/Water
Freeway
Errah],IMartin
LutherVau
Freeway
hnetKing Boulevard
Water/Sewer
Reed
FKing
Street/Bishop,
Southeasterly
Water/Sewer
Street
feet
*
Intersection
Martin
Luther
Emerson
Bishop
Sewer
King
Street
Street
Freeway*
;
coman hellWichita
Street
(
Street
Vaughn
113oulevard
Water
Martin Luther
Emerson
Vaughn
Water
Street*
Freeway
Boulevard
* As part of this CIP project, the Water Department will replace cast iron water mains and/or deteriorated sanitary sewer mains as indicated.
In April 2020, the Transportation and Public Works Department (TPW), Capital Delivery Division, published a Request for Qualifications (RFQ) for
various engineering consulting services. Forty-six consultants responded to the RFQ for the Planning, Design and Construction Services for
Neighborhood Streets Projects area with Statements of Qualifications (SOQ). An evaluation team of City staff subject matter experts from the
Capital Delivery Division of TPW scored the SOQ's based on company experience, prior projects, workload, and team experience. A pool of
nineteen consultants were prequalified for Neighborhood Streets projects based upon these scores. In an effort to match consultants with projects
specific scope, TPW asked the consultants to submit a response to a Request for Additional Information (RFAI) highlighting their proposed design
schedule, sub -consultant availability, and project manager workload among other potential project elements. Respondents to the RFAI were
scored and based on this scoring, Lim & Associates, Inc. was selected as the most qualified consultant to perform design services for this project.
The Transportation & Public Works Department's share on this contract is $231,850.40 (Paving: $224,810.00; Stormwater: $7,040.40). The Water
Department's share on this contract is $281,308.00 (Water: $196,100.00; Sewer $85,208.00) and will be available in the Water & Sewer Capital
Projects Fund for the project (City Project No. 104323).
In addition to the contract amount, $343,419.60 (Water: $125,460.00, Sewer: $33,000.00, Paving: $177,000.00, Storm Water: $7,959.60) is
required for project management, utility coordination and material testing. This project will have no impact on the Transportation and Public Works'
annual operating budget nor on the Water Department's operating budget when completed.
Design is expected to start in August 2023 and be completed by September 2024. Construction should commence in March 2025.
The sanitary sewer component of this project is part of the Water Department's Sanitary Sewer Overflow Initiative Program.
The stormwater component of this project will rehabilitate portions of the existing storm drain system in Vaughn Boulevard and Bishop Street. This
effort will improve drainage in the area.
The action in this M&C will amend TPWs contribution to the Fiscal Years 2023-2027 Capital Improvement Program as follows:
Capital
Revised
Fund
Project
FY2023 CIP y
Budget Change
FY2023
Name
Name
Appropriations
Increase/Decrease'
Budget
2022
Bond
Street Imprv-
Program;
Deteriorating
Sts -
$35,409,202.00i
$(401,810.00)
$35,007,392.00'
-Fund !
PB0019
34027
It is the practice of the Water Department to appropriate its CIP plan throughout the fiscal year, instead of within the annual budget ordinance, as
projects commence, additional funding needs are identified, and to comply with bond covenants. The actions in the M&C will appropriate funds in
support of the Water's portion of the City of Fort Worth's Fiscal Years 2023-2027 Capital Improvement Program, as follows:
202022 Bond Year 3- Contract 17 - LIM
Revised
Capital Fund Name
Project Name
FY2023 CIP
Authority,
Budget Change
f
Appropriations
(Increase/Decrease)
Budget
W&S Capital Projects-
104323-2022 Bond
$0.00
This M&C
$439,768.00
$439,768.001
Fund 56002
Year 3-Contract 17
2022 Bond Program- I104323-2022
Fund 34027
Bond
Year 3-Contract 17
$0.00
This M&C
$401,810.00
$401,810.00
Storm Water Capital
104323-2022 Bond
I
Projects Fund 52002
Year 3-Contract 17
$0.00
This M&C
$15,000.00
$15,000.00
[
Funding is budgeted in the Transfer to Water/Sewer account of the Water and Sewer operating budget for the purpose of funding the 2022 Bond
Year 3 — Contract 17 project within the Water & Sewer Capital Projects Fund, in the Street Imprv-DeterioratingSts programmable project within the
2022 Bond Program Fund and the Drainage Improvement Projects programmable project within the Stormwater Capital Projects Fund for the
purpose of funding the 2022 Bond Year 3 — Contract 17 project.
Appropriations for the water, sanitary sewer, stormwater and paving improvements for 2022 Bond Year 3-Contract 17 project by Fund will consist
of the following:
Existing
Additional
Project
Fund
Appropriationsi
Appropriations,
Total"
2022 Bond Proram
g
$0.00
$401,810.00
$401,810.00
Fund 34027 �
W&S Capital
Projects -Fund 56002
$0.00
$439,768.00
$439,768.00
Storm Water Capital
i Projects Fund-52002
Project Total
$0.00
$0.061
$15,000.00
$856,578.00
$15,000.00
$856,578.00
*Numbers rounded for presentation purposes.
Business Equity Office: Lim & Associates, Inc. is in compliance with the City's Business Equity Ordinance by committing to 100 percent MWBE on
this project. The City's MWBE goal on this project is 8 percent. Additionally, Lim & Associates, Inc. is a certified MBE firm.
This project is included in the 2022 Bond Program. The City's Extendable Commercial Paper (ECP) (M&C 22-0607; Ordinance 25675-08-2022)
provides liquidity to support the appropriation. Available resources will be used to actually make any interim progress payments until debt is
issued. Once debt associated with a project is sold, debt proceeds will reimburse the interim financing source in accordance with the statement
expressing official Intent to Reimburse that was adopted as part of the ordinance canvassing the bond election (Ordinance 25515-05-2022).
This project is located in COUNCIL DISTRICT 5 and 8 and FUTURE COUNCIL DISTRICT 5 and 8.
FISCAL INFORMATION / CERTIFICATION:
The Director of Finance certifies that funds are currently available in the Street Improv-DeterioratingSts project within the 2022 Bond Program
Fund and in the Drainage Improvement Projects project within the Stormwater Capital Projects Fund and in the Water and Sewer Fund and upon
approval of the above recommendations and adoption of the attached appropriation ordinances, funds will be available in the Water and Sewer
Capital Projects, 2022 Bond Program, Stormwater Capital Projects Funds for the 2022 Bond Year 3-Contract 17 project to support the approval of
the above recommendations and execution of the construction contract. Prior to an expenditure being incurred, the Transportation & Public Works
and Water Departments have the responsibility of verifying the availability of funds.
Submitted for City Manager's Office-W. William Johnson 5806
Originating Business Unit Head: Lauren Prieur 6035
Additional Information Contact: Monty Hall 8662