HomeMy WebLinkAboutOrdinance 26224-06-2023ORDINANCE NO. 26224-06-2023
AN ORDINANCE INCREASING ESTIMATED RECEIPTS AND
APPROPRIATIONS IN THE WATER AND SEWER CAPITAL PROJECTS FUND
IN THE AMOUNT OF $277,960.00, TRANSFERRED FROM AVAILABLE FUNDS
IN THE WATER AND SEWER FUND, FOR THE PURPOSE OF FUNDING THE
EASTSIDE II 36-INCH PRESTRESSED CONCRETE CYLINDER PIPE WATER
MAIN CONDITION ASSESSMENT AND CRITICAL REPLACEMENT
IDENTIFICATION (CITY PROJECT NO. 103294); PROVIDING FOR A
SEVERABILITY CLAUSE; MAKING THIS ORDINANCE CUMULATIVE OF
PRIOR ORDINANCES; REPEALING ALL ORDINANCES IN CONFLICT
HEREWITH; AND PROVIDING AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH,
TEXAS:
SECTION 1.
That in addition to those amounts allocated to the various City departments for Fiscal Year 2022-2023 in the
Budget of the City Manager, there shall also be increased estimated receipts and appropriations in the Water
and Sewer Capital Projects Fund in the amount of $277,960.00, transferred from available funds in the Water
and Sewer Fund, for the purpose of funding the Eastside II 36-inch Prestressed Concrete Cylinder Pipe Water
Main Condition Assessment and Critical Replacement Identification (City Project No. 103294).
SECTION 2.
That should any portion, section or part of a section of this ordinance be declared invalid, inoperative or void
for any reason by a court of competent jurisdiction, such decision, opinion or judgment shall in no way impair
the remaining portions, sections, or parts of sections of this ordinance, which said remaining provisions shall
be and remain in full force and effect.
SECTION 3.
That this ordinance shall be cumulative of Ordinance 25773-09-2022 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance are in
direct conflict with such other ordinances and appropriations, in which instance said conflicting provisions of
said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
APPROVED AS TO FORM AND LEGALITY:
I
23 19:15 CDT)
Douglas W. Black
Senior Assistant City Attorney
ADOPTED AND EFFECTIVE: June 13, 2023
CITY SECRETARY
�A� b A'0'—�
Jannette S. Goodall
City Secretary
4.d40U���11
' A *0_0
0000000
�00a00
o
0oAl 00000001
Oof*A5 ��
MAYOR AND COUNCIL COMMUNICATION MAP
60ES1136WM&CRIA1-HDR
s. SAE#+iVA 7t;t TYNETRL
TRAMMEL DAVISRD
CREEDETIRL ui
a
* J
fa Mi W
co F-
.O Z
w
0 1 RAIDor
I _j VILLAGE CREEK - I
WASTEWATER
T TREATMENT PLANT WTPcul
I
a -
0
� .9 IV D �AF7 13LV
i z T WriiT 1 r
04-0 k FUi=RVILLERD MEADOtihl13ROOK13LVD
BRENTWOOD.S'TAIRRD
401
YOLANDAl7R
AIYLNr'r; t
O
ELL'1SRD RTkiliL.�[ ,� �� ti �
' co�f�rLN � •
JEWELLAVE ;
to I!1ry r
C ❑ HITNEYj_hI
S
RAIuST
" KELLDR +r
R0[J'TT'3T ol
r r -
CHURCHST.
- :et BIfTTERCi1PL1�
yl f�
V i i
FC}RTWORTK '� 5`� ■ PIPE SEGMENTS TO
BE REPLACED
City of Fort Worth, Texas
Mayor and Council Communication
DATE: 06/13/23 MSC FILE NUMBER: M&C 23-0491
LOG NAME: 60ESSII36WMA&CRIA1-HDR
SUBJECT
(CD 5) Authorize Execution of Amendment No. 1 in the Amount of $237,960.00 to an Engineering Agreement with HDR Engineering Inc., for Final
Design for Eastside II 36-inch Prestressed Concrete Cylinder Pipe Water Main Condition Assessment and Critical Replacement Identification
Project and Adopt Appropriation Ordinance to Effect a Portion of Water's Contribution to the Fiscal Years 2023-2027 Capital Improvement
Program
RECOMMENDATION:
It is recommended that the City Council:
1, Authorize execution of Amendment No. 1 in the amount of $237,960.00 to City Secretary Contract No. 58146 with HDR Engineering, Inc., for
final design of Eastside II 36-inch Prestressed Concrete Cylinder Pipe Water Main Condition Assessment and Critical Replacement
Identification Project, for a revised contract amount of $1,138,806.00; and
2. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the Water & Sewer Capital Projects Fund
in the amount of $277,960.00 transferred from available funds within the Water and Sewer Fund, for the Eastside II 36-inch Prestressed
Concrete Cylinder Pipe Water Main Condition Assessment and Critical Replacement Identification (City Project No. 103294) to effect a
portion of Water's contribution to Fiscal Years 2023-2027 Capital Improvement Program.
DISCUSSION:
On August, 9, 2022, Mayor & Council Communication (M&C) 22-0592 the City Council authorized an Engineering Agreement with HDR
Engineering Inc., in the amount of $900,846.00 for Eastside II 36-inch Prestressed Concrete Cylinder Pipe Water Main Condition Assessment and
Critical Replacement project. The project provided for condition assessment of approximately 19,000 feet of the Eastside If 36-inch water main
located on the south side of Interstate Highway (IH)-30 from the east side of IH-820 to the north right—of—way line of IH-30 at the Village
Creek/Green Oaks Boulevard intersection, with the goal of identifying possible future failure points and to provide recommendations for
replacements. The water main has experienced breaks over the past couple years.
The condition assessment has been completed and six pipe segments at different locations on the water main alignment have been identified as
structurally deficient and in need of replacement.
HDR Engineering, Inc., proposes to complete the additional engineering design services for a fee not to exceed $237,960.00. Staff considers this
fee to be fair and reasonable for the scope of services proposed.
In addition to the contract amount, $40,000.00 is required for project management.
It is the practice of the Water Department to appropriate its CIP plan throughout the fiscal year, instead of within the annual budget ordinance, as
projects commence, additional funding needs are identified, and to comply with bond covenants. The actions in the M&C will appropriate funds in
support of the Water's portion of the City of Fort Worth's Fiscal Years 2023-2027 Capital Improvement Program, as follows:
60ESS1136WMA&CR1A1-HDR
Capital
Fund
Project
FY2023 CIP
Authority
BudgetRevised
Change
FY2023
Name
Name
Appropriations
(increase/
Budget
g
Decrease)
Fund
103294-
56002 —
ESII 36"
Water &
PCCP
$0.00
This M&C
$277,960.00
$277,960.00
Sewer
WM &
Capital
Critical
Projects
REPL
Funding is budgeted in the Transfer to Water/Sewer account of the Water and Sewer operating budget for the purpose of funding the ESII 36"
PCCP WM & Critical REPLC within the Water & Sewer Capital Projects Fund.
Appropriations for the Eastside II 36-Inch PCCP Water Main Condition Assessment and Critical Replacement Identification Project are depicted
below:
FUND I
Existing Appropriations
Additional Appropriations
Project Total*
Fund
56002 -
Water &
Sewer
$1,046,396.00
$277,960.00
$1,324,356.00
Capital
Projects
!Project
otal
$1,046,396.00
$277,9ti0.00
�,:356.00
*Numbers rounded for presentation purposes.
This project will have no impact on the Water Department's operating budget when complete.
Business Equity: HDR Engineering, Inc. agrees to maintain its initial M/WBE commitment of 10 percent that it made on the original agreement
and extend and maintain that same M/WBE commitment of 10 percent to this first amendment. Therefore HDR Engineering, Inc. remains in
compliance with the City's MAMBE Ordinance and attests to its commitment by its signature on the Acceptance of Previous MMIBE Commitment
form executed by an authorized representative of its company.
This project is located in COUNCIL DISTRICT 5.
FISCAL INFORMATION / CERTIFICATION:
The Director of Finance certifies that funds are currently available in the Water & Sewer Fund, and upon approval of the above recommendations
and adoption of the attached appropriation ordinance, funds will be available in the W&S Capital Projects Fund for the ESII 36" PCCP WM &
Critical REPL project to support the approval of the above recommendations and execution of the engineering agreement. Prior to any expenditure
being incurred, the Water Department has the responsibility of verifying the availability of funds.
Submitted for City Manager's Office by: Dana Burghdoff 8018
Originating Business Unit Head: Chris Harder 5020
Additional Information Contact: Scott Taylor 7240