HomeMy WebLinkAboutContract 59347-A1CSC No. 59347-A1
TEXAS DEPARTMENT OF TRANSPORTATION
AIRPORT PROJECT PARTICIPATION AGREEMENT
(Federally Assisted Airport Development)
TxDOT Project No.: 2302SPINK
Commission Approval: April 27, 2023
NPE Funds Applied: FY 23
UEI: ENS6MKS1ZL18
ALN: 20.106
Amendment No. 01 to the Agreement
Part I - Identification of the Project
TO: City of Fort Worth, Texas
FROM: The State of Texas, acting through the Texas Department of Transportation
City of Fort Worth, Texas, hereinafter referred to as the "Sponsor," and the Texas
Department of Transportation, hereinafter referred to as the "State," have entered into an Airport
Project Participation Agreement TxDOT CSJ Number 2302SPINK, executed by the Sponsor on
April 4, 2023, and by the State on May 1, 2023, for the development of Fort Worth Spinks Airport,
hereinafter referred to as the "Airport".
The project is described as construction services to: construct hangar access taxilanes
northeast side of the airport at Fort Worth Spinks Airport.
It is in the mutual interest of the Sponsor and the State to increase the agreement by
$404,780 based on bids. $403,260 of the total project cost will be for additive alternate 1. This
will be funded at 75/25.
Part II - Offer of Financial Assistance, estimates total project costs to be $1,387,400; and
financial assistance is currently limited to $1,248,660 in federal funds and $138,740 in local
sponsor funds.
The following amendment to the Airport Project Participation Agreement shall become
effective upon execution of this Amendment by the Sponsor and the State.
The Airport Project Participation Agreement is amended as follows:
1. On Part II, Item No. 2 of the Agreement, change Amount A, estimated total construction
costs, and any further references in the Agreement to Amount A, to $1,792,180.
Page 1 of 3
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
2. On Part II, Item No. 2 of the Agreement, change Amount B, estimated construction costs
eligible for federal financial assistance, and any further references in the Agreement to Amount B,
to $1,792,180.
3. On Part II, Item 3 of the Agreement, change Amount C, the maximum obligation of the
United States payable under this offer, and any further references in the Agreement to Amount C,
to $1,552,473.
4. On Part II, Item 4 of the Agreement, change Amount D, Sponsor's share of the estimated
construction costs, and any further references in the Agreement to Amount D, to $239,707.
All other terms and conditions of the agreement are unchanged and remain in full force and
effect.
This Amendment to the Airport Project Participation Agreement between City of Fort
Worth, Texas, and the Texas Department of Transportation is mutually agreed to and accepted.
Citv of Fort Worth, Texas
Sponsor
Daum But�hdofF
Dana Burghdoff (i 8, 2023 17:15 CDT)
Sponsor Signature
Assistant City Manager
Sponsor Title
Jun 28, 2023
Page 2 of 3
Date
Execution by the State
Executed by and approved for the Texas Transportation Commission for the purpose and effect
of activating and/or carrying out the orders, established policies or work programs and grants
heretofore approved and authorized by the Texas Transportation Commission.
STATE OF TEXAS
TEXAS DEPARTMENT OF TRANSPORTATION
W"
BY: Dan Harmon
(Jun
129, 2023 06:22 CDT)
Date: Jun 29, 2023
Page 3 of 3
APPROVAL RECOMMENDED:
Roger Venables
Aviation Director
Contract Compliance Manager:
By signing, I acknowledge that I am the person
responsible for the monitoring and administration
of this contract, including ensuring all performance
and reporting requirements.
Erin Roden
Senior Contract Compliance Specialist
ATTEST: annn
a FpORr Wp,
od
�o
adap QEXP5o4
Jannette Goodall
City Secretary
Approved as to Form and Legality
Thomas Royce Hansen
Assistant City Attorney
M&C: 23-0552
Date: 6/27/2023
Form 1295: N/A
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
FORT WORTH
Routing and Transmittal Slip
Aviation
Department
DOCUMENT TITLE:
FWS East Side Hangar Taxilane Construction
Amendment 1
M&C
23-0552 CPN
104902 CSO # 59347
DOC#
DATE:
6/27/2023
INITIALS
DATE OUT
TO:
Jun 27, 2023
1.
Erin Roden
E
2.
Joe Hammond
Jun 27, 2023
3.
Roger Venables
`
Jun 27, 2023
4.
Royce HansenN
Jun 28, 2023
5.
Dana Burghdoff
L9B
Jun 28, 2023
Jun 29, 2023
6.
Jannette Goodall
DOCUMENTS FOR CITY MANAGER'S SIGNTURE: All documents received from any and all City
Departments requesting City Manager's signature for approval MUST BE ROUTED TO THE
APPROPRIATE ACM for approval first. Once the ACM has signed the routing slip, David will review
and take the next steps.
NEEDS TO BE NOTARIZED: ❑ Yes ❑x No
RUSH: X❑ Yes ❑ No SAME DAY: ❑ Yes ❑ No NEXT DAY: ❑ Yes ❑ No
ROUTING TO CSO: x❑ Yes ❑ No
Action Required:
❑ As Requested
❑ For Your Information
1 Signature/Routing and or Recording
❑ Comment
❑ File
❑ Attach Signature, Initial and Notary Tabs
Return to: Please call Tyler Dale at ext. 5416 for pick up when completed. Thank you.
Create New From This M&C
DATE: 6/27/2023 REFERENCE
NO..
CODE: C TYPE:
**M&C 23- 55FWS EAST SIDE HANGAR
0552 LOG NAME: ACCESS TAXILANE PROJECT
AMENDMENT 1
CONSENT PUBLIC NO
NO
SUBJECT: (CD 8) Authorize Execution of Amendment No. 1 to the Grant Agreement with Texas
Department of Transportation for the East Side Hangar Access Taxilane Project in an
Amount Up to $404,780.00 at Fort Worth Spinks Airport, Authorize a Transfer from the
Municipal Airport Capital Projects Fund in an Amount Up to $100,967.00 for the City's
Match Requirement and Adopt Appropriation Ordinance
RECOMMENDATION:
It is recommended City Council:
1. Authorize execution of Amendment No. 1 to the Grant Agreement with Texas Department of
Transportation for the East Side Hangar Access Taxilane project in an amount up
to $404,780.00 at Fort Worth Spinks Airport; and
2. Adopt the attached appropriation ordinance increasing estimated receipts and
appropriations in the Muni Airport Grants Federal Fund in an amount up to (1) $303,813.00
subject to receipt of the grant, and (2) $100,967.00 as a transfer from the Municipal Airport
Capital Projects Fund to satisfy the City's match requirement, totaling $404,780.00 for the
purpose of funding the East Side Hangar Access Taxilane project (City Project No.104902).
DISCUSSION:
On August 3, 2021, Mayor and Council Communication (M&C) 21-0536, City Council authorized the
application for and acceptance of a grant from the Federal Aviation Administration (FAA), passed
through the State of Texas, being represented by the Texas Department of Transportation, Aviation
Division (TxDOT), for development of taxilanes (Project) at Fort Worth Spinks Airport (Airport). This
M&C also adopted Resolution No. 5431-08-2021, which allowed for the execution of grant related
agreements for the Project.
On April 4, 2023, City Secretary Contract 59347 (Contract) was executed with TxDOT accepting grant
funds for the construction of the Project. On June 6, 2023, TxDOT informed the Aviation Department
that additional funding was necessary for construction and construction services of the Project, and
that execution of an amendment will be needed.
Amendment No. 1 (Amendment) will increase the construction total of the grant by $404,780.00,
bringing the grant total amount for construction and construction services of the Project from
$1,387,400.00 to $1,792,180.00. The City's match requirement and total share for the construction and
construction services of the Project will be $239,707.00. The original $138,740.00 for the City's match
requirement was at a 90/10 cost split, and the City's match requirement for the Amendment amount of
$100,967.00 is at a 75/25 cost split. The total construction costs of the Project are summarized below:
Fund Original Contract Amendment New Contract
Amount 1 Amount
TxDOT Grant $1,248,660.00 $303,813.00 $1,552,473.00
Funds
CFW Funds $138,740.00 $100,967.00 $239,707.00
Project Total $1,387,400.00 $404,780.00 $1,792,180.00
This Project will consist of constructing three taxilanes that will connect to Taxiway Mike on the
northeast side of the Airport (see attached map), and will allow for future development of hangars and
other infrastructure to help alleviate the issue of limited hangar space at the Airport. This Project was
advertised with the first two taxilanes as the Base Bid, and the third taxilane as Additive Alternate 1.
Both the Base Bid and Additive Alternate 1 will be awarded.
Funding is budgeted in the Municipal Airport Capital Proj Fund for the transfer into the Muni Airport
Grants Federal Fund for the purpose of funding the FWS 2302SPINK NE Side Hangar project, as
appropriated.
Fort Worth Spinks Airport is located in COUNCIL DISTRICT 8.
FISCAL INFORMATION/CERTIFICATION:
The Director of Finance certifies that upon approval of the above recommendations and adoption of
the attached appropriation ordinance, funds will be available in the current capital budget, as
appropriated, in the Muni Airport Grants Federal Fund. The Aviation Department (and Financial
Management Services) will be responsible for the collection and deposit of funds due to the City. Prior
to an expenditure being incurred, the Aviation Department has the responsibility to validate the
availability of funds. This is a reimbursement grant.
WC,
Fund
Department Account
Project
Program
Activity
Budget Reference # Amount
ID
ID
Year (Chartfield 2)
FROM
Fund
Department Account
Project
I
Program
Activity
Budget Reference # Amount
ID
ID
Year (Chartfield 2)
Submitted for Citv Manaqer's Office bv:
Oriqinatinq Department Head:
Additional Information Contact:
ATTACHMENTS
FID Table.XLSX (CFW Internal)
Funds Available.bq (CFW Internal)
Dana Burghdoff (8018)
Roger Venables (6334)
Tyler Dale (5416)