HomeMy WebLinkAboutContract 58735-CO1CSC No. 58735-COI
FORT WOR-riq City of Fort Worth
Change Order Request
Project Name:1 Water and Sanitary Sewer Main Extensions to Serve Buddharalanaram Community
ProjectNo.(s):1 56002.060043010700430.102994.001780 1 M&C: 1 22-0884
Project Description:) Water and Sewer Extensions to serve Buddharalanaram Community
City Sec No.: 58735
City Proj, No.: 102994
Contractor: I Woody Contractors, Inc. Change Order# I 1 I Date: 6/21/2023
CityProject Mgr.1 Brenda Oropeza CityInspector: I Paul Gieger
Phone Number: 817-392-8271 Phone Number: 817-223-2258
Dept.
Water
Sewer Paving
Original Contract Amount
$2,213,000.00
$1,986,690.00
Extras to Dale
Credits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Date
Amount of Proposed Change Order
40.72
$0.00
Revised Contract Amount
$2,212,999.28
$1,986,690.00
Original Funds Available for Change Orders
$110,650.00
$99,335.00
Remaining Funds Available for this CO
$110,650.00
$99,335.00
Additional Funding (if necessary)
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT
MAXALLOWABLE CONTRACTAMOUNT (ORIGINAL CONTRACT COST + 25%)
JUSTIFICATION (REASONS) FOR CHANGE ORDER
Totals Contract Time
(Calender days)
$4,199,690.00 310
•$0.72
$4,199,689.28
$209,985.00
$209,985.00
0.00%
$5,249,612.50
310
Change order No.1 will allow for:
• The replacement of existing speed cushions that were removed during water and sanitary sewer Installation
• The installation of tapping sleeve and valves at two street connections in lieu of two cut in sections in order to minimize water service
disruptions to residents in the vicinity.
• The purchase (from the contractor) and delivery of two gale valves and custom flanges (not used in the cut -in sections) to water Field
Operations yard. It is more economical to purchase the valves for use by Field Operations than to pay the restocking fee.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment
in full (both time and money) for all costs arising out of, or incidental to, the above Change Order.
j Contractor's Company Name
Contractor Name
Cojdractor S nature Date
Woody Contractors, Inc.
Troy Woody
Insilctor
•�-�i��.
Date
U( 3�
=ia§er Date
tp -21 '23
_
Director (Water Dept)
Date
ConVruclion pe� Date
T Jun 26, 2023
y�_ _ -;13 —.23
Assistant City Attorney
Date
Assistant City Manager Date
t
Jut 3, 2023
Dana S4�02f Jul 5, 2023
Council Action (If Required)
M&C Number NIA
M&C Date Approved j NIA
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
FORT WC3R'TH City of Fort Worth
Change Order Additions
Project Name Water and Sanitary Sewer Main Extensions to Serve Buddharatanaram Community I City Sec No.: 1 58735 1
Project No.(s): 56002-060043010700430-102994.001780 1 DOE No.1 22-08841 City Proj, No.: 1 102994 1,
Project I Water and Sewer Extensions to serve Buddharatanaram Community
Description
Contractor Woody Contractors, Inc. Change Order: Date:1 6/21/2023
City Project Mgr, 1 Brenda Oropeza I City Inspector 1 Paul Gieger
ADDITIONS
HEM EM
UESURIF I IUN
DEPT
QIX 'Unit 'Unit Cost
Total
51
21"A2" Tapping Sleeve & Valve
Water
2.00 EA $12,800.00
$25,600.00
52
Purchase 24" Gate Valve
Water
1.00 EA $29,750.00
$29,750.00
53
Purchase Custom Flange Pieces
Water
2.00 EA $17,870.00
$35,740.00
54
Speed Cushion
Water
5.00 EA $3,400.00
$17,000.00
45
Speed Cushion
Sewer
5.00 EA $3,400.00
$17,000.00
Water
$108,090.00
Sewer
$17,000.00
Paving
Page 2 of 4
Additions Sub Total
$125,090.00
FORT WC)RXM City of Fort Worth
Change Order Deletions
Project Name Water and Sanitary Sewer Main Extensions to Serve Buddharatanaram Community
Project No.(s): 56002-060043010700430-102994-001780 1 DOE No. 22 08
Project Description I Water and Sewer Extensions to serve Budd haratanaram Community
Contractor Woody Contractors, Inc.
City Project Mgr. Brenda Oropeza
ITEM DESCRIPTION
1 3311.0672 24" Steel AWWA C200 Water Pipe
42 Construction Sewer
City Sec No,: 58735
City Proj. No.: 102994
Change Order: � Date 6121/2023
City Inspector I Paul Gieger
DELETIONS
DEPT City Unit Unit Cost Total
Water 41.256 LF $2,620.00 $108.090.72
Sewer 0,17 LS $100,000.00 $17,000.00
Page 3 of 4
Water $108,090.72
Sewer $17,000.00
Paving
(Deletions Sub Total $125,090.72
MMBE Breakdown for this Change Order
Total
"I'mr
Previous Change Orders
iuw,
Total ON
Page 4 of 4
6/21/2023
Water and Sanitary Sewer Main Extensions to Serve Wat Buddharatanaram Community
CSC: 58735
CPN:102994
Change Order 1 Notes
Staff has reviewed the requested prices and considers them to be fair and reasonable.
Contract Compliance Manager
By signing I acknowledge that I am the person responsible
for the monitoring and administration of this contract, including
ensuring all performance and reporting requirements.
Signature
Brenda Oropeza
Name of Employee
Graduate Engineer
Title
ATTEST: �p
Jannette Goodall
City Secretary
pd4�oanu
a.00001. P
a° °g9Pd
-1d
Pv0 0
00
PPS * o°o *�
d� b
44 nE4p5ooa
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX