HomeMy WebLinkAboutContract 53393-FP1FORTWORTH,
TRANSPORTATION AND PUBLIC WORKS
NOTICE OF PROJECT COMPLETION
-FP1
City Secretary No: 53393
Date Received: 7/10/2023
City Project JV!?: 102098
Regarding contract 53393 HMAC Surface Overlay 2019-6for as required by the TRANSPORTATION AND
PUBLIC WORKS DEPARTMENT as approved by City Council on 12/17/2019 through M&C 19-0411 the director of
the TRANSPORTATION AND PUBLIC WORKS DEPARTMENT upon the recommendation of the Assistant
Director of the Transportation & Public Works Department has accepted the project as complete.
Original Contract Prices: $ 1,079,975.00
Amount of Approved Change Orders: $ 0.00 No
Revised Contract Amount: $
Total Cost Work Completed: $ 984,729.95
Less Deductions:
Liquidated Damages: 0 Days @ $ / Day
Pavement Deficiencies:
Total Deduction Amount: $ 0.00
Total Cost Work Completed: $ 984,729.95
Less Previous Payments: $ 935,493.46
Final Payment Due $ 49,236.49
Patricia L. wadsacK Jul 10, 2023
Patricia L. Wadsack (Jul 10, 202311:31 CDT)
Recommended for Acceptance Date
Asst. Director, TPW - Capital Delivery
"-12 J u 110, 2023
Lauren Prieur(Jul 10, 202311:33 CDT)
Accepted Date
Director, TRANSPORTATION AND PUBLIC WORKS DEPARTMENT
Jul 10, 2023
William Johnson (Ju 10, 202314:19 CDT)
Asst. City Manager Date
OFFICIAL RECORD
Comments: CITY SECRETARY
FT. WORTH, TX
C-620 Signature Page
Contractor's Application for Payment
To (Owner) City of Fort Worth Invoicing Period (From -To):
3/1/23 - 6/29/23
P. O. FW020-0000003282 From (Contractor):
Number: Peachtree Construction Ltd
Project: 102098 Contractor's CFW Vendor No.:
0000007231
City Secretary Contract 53393 contract HMAC Surface Overlay 2019-6
Number. Name:
Application For Payment
Change Order Summary
Approved Change Orders
Number Additions
1
2
3
4
5
6
7
8
TOTALS
NET CHANGE BY
CHANGE ORDERS
Contractor's Certification
Invoice No.
Invoice Date:
6/29/2023
Remit to ( If Not Automatic Deposit ):
17 Final
1. ORIGINAL CONTRACT PRICE.......................................................... S
Deletions 2. Net change by Change Orders................................................................. $
3. Current Contract Price (Line 1 t 2)........................................................ $
4. TOTAL COMPLETED AND STORED TO DATE
(Progress Estimate, Construction Allowance and Change Orders)....... $
5. RETAINAGE:
a. X $984,729.95 Work Completed.......... $
b. X Not Used $
c. Total Retainage (Line 5a + Line 5b) ............................... $
6. AMOUNT ELIGIBLE TO DATE (Line 4 - Line 5c)............................. $
7. LESS PREVIOUS PAYMENTS (Line 6 from prior Application)........ $
8. AMOUNT DUE THIS APPLICATION ................................................. $
9. BALANCE TO FINISH, PLUS RETAINAGE
(Column G on Progress Estimate+ CA + Cos + Line 5 above) .............. $
The Contractor certifies with the submittal of this document and associated Payment Request Submittal
on the City of Fort Worth Buzzsaw system that to the best of their knowledge: (1) all previous progress
payments received from Owner on account of Work done under the Contract have been applied on
account to discharge Contractor's legitimate obligations incurred in connection with Work covered by
prior Applications for Payment; (2) title of all Work, materials and equipment incorporated in said
Work or otherwise listed in or covered by this Application for Payment will pass to Owner at time of
payment free and clear of all Liens, security interests and encumbrances (except such as are covered by
a Bond acceptable to Owner indemnifying Owner against any such Liens, security interest or
encumbrances); and (3) all Work covered by this Application for Payment is in accordance with the
Contract Documents and is not defective.
B Taylor
B Taylor (Jul 7, 2023 08:20 CDT)
10. CONTRACT TIME:
Consent of Surety
Affidavit of Bills Paid
$1,079,975.00
$1,079,975.00
$984,729.95
$984,729.95
$935,493.46
$49,236.49
$95,245.05
a, Days Awarded 175
b, Days Added by CO 310
C. Total Days 485
d. Days Charged 485
e, Days Remaining
This document has been modified from its original form as an EJCDC document and the user did not highlight the
modifications. You are encouraged to read the document carefully and consult Legal Counsel prior to its execution.
G620 Unit Pnce RN.. Eed.e.
Progress Estimate
01tySt°m
53393
Contractor's Application
Comma Nmn.
HMAC Surface Overlay 2019-6
17 Final
npph°nti°n Pm;na:
3/1/23-6/29/23
Appli 6. Dmc
619/2023
A
B
C
D
E
F
G
h-
Toml C°mpincd �:
Bdmxto Finish
S i-N..
Hid Quontity
Unit Pncc
Bid Voloc
C ct, motcd Quvntity
Vnlm
Pmvioo.ly lmNlled V.I. VductTisPmod
Mmminl. Pnxnay
6tomd(notN C7
and $tmcdtc➢m° (F7
(B•F) Qwntity hmcltcd ]id.
Bidem Na
Danpaon
pi° Uvt
SacOm No.
ofMcuom
Wt°Ilcd
NtE) B
Pmiod
1
10135.0201 REMOBILIZATION
01 7000
EA
1
s5poA&
5500.00
$500.00
_
2
10241.1300 REMOVE CONC CURBBGUTTER
024115
LF
8000
$SM
546,000.00
_ 5499.76660000
330.183.35
E30,193.35
S30.193.35 86.6X
573.806.65
EE584370
6gawrSIDEWALK
ZS725
0000
---
��%
5
13213 41.0101 . LWCOVE
1 321320 1
1
SF
SF
7200
588W00
1330.900WW0
765�1337c
31444399
.70
7
CONCSIDEA'TBJ')ACK
1321320
18�
E7.75
3140275.00.
_ 18513.5500000
5743480.01
-5143480.01
514348001102.3%
33205.01
3213.0301 C C OF SIDEWALK
� i
i
8
f6 to )Cti�t'V/u.LEY
$2450
5900A0
_.. 713.77000000
0.62000000
E77 d8737
3301.00
317487.37
E3,01.00
Ei748737 178.4%
53010 40.4%
37_168737
$4.469.0
9 41.1400 REMOVE GUTTER
10�I3216.001 7" CONC VALLEY GUTTER
024115
1 321613 1
SV
SV
10
150
SSO.W
590_W
5700.00
513500.00
0.62000000
55.455.B0
35,455.00
_._
55455_0 40_6%
38,01120
11
12
10241,000 REMOVE ADA RAMP
3T13.0501 q�ljjjq�jjjJJJpyjjjJJf)(fpEfRyjfp'
Ej- NMP.
024113
1
EA
40
$165.00
$6,600.0
17A000000
800000000
$2,60500
52800000
___$2.805.00_
$2800.00
$Z$05,00 42.5%
52800000 40.0%
S3.MMO
00
m
13
3213.050 H/}I�jl TYPEMI
321320
1
EA
I 32.70.0
5765CR00_
-
3213. �fF ��(jjj��jj''32
tt5330.0
�15990.00
$41.250.00s_=.w
16
I9999.0000T U�ME V�ATE/5 X2'1
000
EA
2
I
S_660013,00000000
900
_
SM= 15mm
i7
10241:170 8"PAVEMENT QULVERIZA ON
024115
BY
11500
I $7.00
SB0,500.00
11101.35MOM
S77,709A5
577,709.45
_ $77.70.9.45 %S%
32,7055
18
3212.0023"ASPHALTP VEMENT.'[YPEO
321276
SV
11W0
I E15.d0
E1771000___
112d8.00a0000
5173,2'2967
__._ E173229.67
$17322987 W.e%
53070.33
19
3211.0600 CEMENT MODIFICATION. 'ZG Ibs/gv
3211 33
TN
150
I 5205.0
$3075000
_ _ 152.020000
$3116410
E3118d_10
_ _
53116410 707.3%
3414.10
20
0241.120 WOVE BRICK PAVEMENT
024115
SV
20
$47.8
S9.00
7.3300000
$251-_
6Z694.51_
5269451 6,7%
-4175451
21
7
BY
52200,
2D.00000000
2,20000
E220000
574516
100.0%
574519 10.E%
E4504.82
22
23
1-4
9999.
3110.01026-12'TREE REMOVAL
106
310
311000
SV
EA
120
00
4
I 3525
I E7,100,op
SS,I50.00
$4.0.00
141.94000000
3,00000000
E74519
33,30000
_
33300.0.0
53300 75.0%
E7,10.00
24�:3123.0101
UNCLASSIFIED EXCAVATION
312316
CV
50
I 527.50
$1.375.00 _
24.3300000
3669.00
_ E669.08
_
3669.0 48.7%
3705.93
25
3292.010 BLOCK SOD REPLACEMENT
329213
SV
110
I $1325
$14.575.00 __.
206.00000000
W5.60,10
_ _539,600.10
$35.600MO 2443%
531.025.10
26
13217.0305 STOP BARS PAVEMENT MARKINGS
321723
LF 1
10
1 36_w
b990.00 _
__ _ __. _
$990,0
3217.001 4" 8S,01111
331723
LF
110
I
gTNHEERMOOPLASTIC
37.�0
$165.00.
_--___-
5165.0
-2
3217.00024"SOL1U'1'H'ULLASTIC
( p$ ('�1& (�F
321723
LF
150
I 31.10
$70.00
�
3217.05012�4�yy0��SPFO�Il7(Wj$H,gII�lT�JH(E�Rf[MJOPLASTIC
ES
321723
LF
150
I SSg_0
$1,320.00
_ --
E3,70D.00
$3,_700,00 1233%
$1,3Z00
3700.00
3-0
31
321 T.1 CUR9 AbRA PAIMIFIG
13211,0122 FLEX BASE. TYPE A_ GR-2
321725
3211 23
EA
CY
60
50
.300
$00
I $58_00
5,00.
36400.00 _
74.0000000
9,11000000
53,700.00
11801.68
SIi0148
$801.88 18:2%
33yWSM
ADJUSTMENT
3305.0100 MIJJS��CTT77E{{ LLL�L
330514
LS
1
I
32
33
IAIFFNEEjOUS
.010 MISCELLA3bUS STRUCTURE ADJUSTMENT
330514
BY
50
E6000,0
372.00
$B.00.W
33.800.00
a,01nW00
__.. _33.0000.0DO
E1t5.50
$2,376.00
S115.50
_52.376.013
$115.50 1.9%
$Z376.00 88.0%
SS,804J10
51,224.00
WATER VALVE BOX ADJUSTMENT (WRH STEEL�fM.01
F.I.,
F.@011t
33OSt4
EA
5
E250.00
5720.0`
112 WATER VALVE BOX ADJUSTMENT CONCRETE
330514
EA
5
35
36
(��J'1i�� I- INCH STANDARD PLASTIC METER BOX
331210 1
EA 1
2
$280.00
510.0
SYJ2000 400.00
2700000000
_. 8DW 5,100aoo
S1J 0.00
S118200 4350.0%
-=.DO
37
BETE METER BOX1a2`'�
I.00
SS6000D
2.0000000
$S6a0
_$50.00_
55600 100.0%
3349t2.01071MIH�}OJLSTAFFOIJ,UgSTMaENT
6
I
36
EA
tt0o0
39
13305.0112 M I�}6/�J,E�A�O(JpUSL�TMRIT �@`
330517
EA
e
_seso.00
a5.loa.ao-
6.00aaoaoo
sc,eoo ao
E6,69o.ao
$5.6_ao.00 133.3%
-$1.700.00
40
330.0108 MISCELLANEOUS SYRU UOR ADJUSTMENT
ISSTOJjfQ,fjgSS51,(Ly4Fi
330514
EA
1
�•800.00
SZ_500.0
1_00000000
S3.B00.00
52.800.00
32.600_00. 100.0_%
3355010 MJ,I�S{CjEL
LAFIEOl1 $i1i11Ci UftEADJUSTMENT
330574
EA
1
41
d2�
�y1,[��4f j��,�T (�
6.01016"`PEi ATED S'l�9b IN PIPE
1 33460
LF
30
u52i.00
$660.0
8660.0
43
AM90000 REMOVE CONCT PVMT
0241 15
SV
20
I E16,00
$3200_00
_203._00000000
S_3.24500
$3448.00
53248.0 1015%
s46.00
44
9999.0096 PAVING CONSTRUCTION ALLOWANCE
EA
1
1 S_45A00.00
526.00000___0.94882300
E2%720.55.
$23.720.55
52 055 94.9%
31.279.45
Thu dm W1-bcmmodified fiom is migi.Afmmmm 13JCDC dmummt and the°.cr didnet highlight d,e
madilimlicna Yoe me mcourcged to mad the dmvnmt 4 [hIly and con+ult Lcgol to 1 pnm to id accution
c-Q0 UM N. ProBrms Es0tn°t°
Progress Estimate
city —w�
Cvnvnct Nmn.
HMAC Surface Overlay 2019-6
npp5m6nn Pvivd: 3/l/23 - 6/29/23
A
anm
Bid 11®Nv. Daviptim
, Tatab
I
Spmmtim Udtd'Mwmv Bid QmntltY Unit Price
Section N°.
I
53393
Contractor's Application
npp5m6m Nomlw
17 Final
Applicnti°n Dntc:
6292023
B
c
D
E
F C
Tvml Cvmpictvd °' Bnlmmty Finish
Bitl Vdvv
Astim"led Q"mary
Vdm Prmamly Lnmll°d Vdm
Mvm rnOY
Vduv7ldePm°d
nm (F) B-F7 Qm titylnw m.
and $(Dv
MNII�
Stvmd(nvtHC)
d(..1
E)
N+E7 B Pmiad
51.0".975.00
$904.729.951 $994.72995
$984.729.95 91.2% $95.246.05
Thie dvc—hn. hcm m° T,d Gvm in vdgimlIDmmm=DC dmmnmt and Nv— did not highlight thv
modilicntivm. Y. me me°urngcd Iv mdthe d.—.—Mly andcvm°It tcg"1 Cvm"vl prior tv its —6—
C-620 Change Order
Progress Estimate Construction Allowance Usage Contractor's Application
ADDITIONS
For(contmet):
102098 HMAC Surface Overlay 2019-6
City Secretary
53393
Application Number:
17 Final
Contract Ntmu
Application Period:
3/1/23 - 6/29/23
Appliention Date:
6/29/2023
A
B
C
D E F
Itan
Total Completed
% Balmcc to Finish
Specification Unit of Quantity to Add
Unit Price Addition Value
Estimated Quantity
Previously Value This Materials Presently
Value end Stored to Date
(F) (B - F)
Item Number
Ite
Description
Section No. Measure
(DIE) Value Period Stored (not C) (D+E)
B
9999.0096
Regarding Work Performed on Sth_Ave due to Water Main Break
IS 1.00000000
$11,883.69 $11,883.69
$11,983.69
Tomis SI1.883.69 S11,883.69
This document has been modified 6om its original form as an EJCDC document and the user did not highlight the
modifications. You are encouraged to rood the document carefully end consult Legal Couasel prior to its execution.
C-620 Change Order
Progress Estimate
For (centmcp: 102098 HMAC Surface Overlay 2019-6
Application Period:
A
Item
Bid Item Numbor Description
Construction Allowance
Construction Allowance Usage
CONSTRUCTION ALLOWANCE ITEMS TO BE REDUCED
3/1/23 - 6/29/23
B C D
Specification Unit of Quantity to Delete Unit Prim Reduction Value Not Used Not Used
Section No. Masmc
L8 1.00000000 �11 883.69 SI1,883.69
Application Number.
Application Dote:
E
Not Used Not Used Not Used
Contractor's Application
17 Final
6/29/2023
F
Not Used Not Used Not Used
Totals
S11.883.69
This dmument bens been modified from its original form as an EICDC document end the user did not highlight the
modiGations. You me encouraged to read the document artfully and consult Legal Counsel prior to its aceution.
CE20 Change Order
Progress Estimate
Chancre Order Number 1 1
Contractor's Application
ADDITIONS
Far(eontracp: 102098
HMAC S-fueeOverlay2019-6
city Secretary
Contract Num:
53393
Applieation Number.
17Fin81
Application Period:
3/1/23 - 6/29/23
Application Date:
6/29/2023
A
B
C
D E
F
Change Order Item
No,
Item
Specification Mail or CO Quantity to Add Unit Rice
Description SeMion No. Measure
Addition
Change Order
Value
Estimated Quantity
InslaBed
Previously Value This Materials Rnendy
Value
Installed Value Period Stared (not in C)
Total Completed / Balance to Finish
and Stored to Date (F) (D - F)
(D+E) H
Totals
This document has ls,� modified from its original Conn m on E1CDC document and the user did not highlight the
modifications. You are encouraged to rend the document carefully and consult Lego] Counsel prior to its esecution.
C£220 Change Order
Progress Estimate Change Order Number 1 1 1
DELETIONS
For (contract): 102098 11MAC Surface Overlay 2019-6
Applieotian Period: 3/1/23 - 6/29/23
A B I C
Iran CO Quantityto Dcictiou
Charge Order flan Dcscri lion Specification Unit of Delete Unit Price Charge Order Not Used
No. F Seution No. Measure Value
Totals I
Application Numb -
Application Dmc:
D E
Not Used Not Used Not Usal Not Us d
This document hus been modified from its original form us on EtCDC document end the user did not highlight the
modifications. You are encouraged to mod the document carefully end consult Legal Counsel prior to its —lion.
Contractor's Application
17 Final
6/29/2023
F
Not Used Not Used Not Used
C-620 Change Order
Proaress Estimate
Change Order Number 1 2
Contractor's Application
ADDITIONS
r°r (canvacp_ 102098
HYIAC Surface Overlay 2019-6
City Secretary
53393
Application Numlxc
17 Final
Contact Num:
Applieation Penod:
3/1/23 - 6/29/23
Application Dole:
6/29/2023
A
B
C
D E
F
Item
Baloney to Finish
Change Order Item
SpecificationLUnit of CO Quantity to Add Unit Price
Addition Chong.
Etimaled Quantity
Previously Value This Mnleriols P'r"""
Value
Total Completed
and Stored to Dnlc (F) "F>
No.
DC�puO° Section,n No..Mcasme
Order Value
Installed
Installed Value Period Stored (not in C)
(p+E) B
Totals
This docummt hm been modified from its original forms an oFJCDC document and the user did not highlight the
modifications. You one eneor aged to read the docuraant carefully and consult Legal Counsel prior to its execution.
C-620 Change Order
Progress Estimate Change Order Number 1 2
DELETIONS
For (contract): 102098 HMAC Surface Overlay 2019-6
Apolication Period: 3/1/23 - 6/29/23
Chong, Order It®
No.
Item
Description
A B C D
CO Quantity to D,lotion Change
Spc ioN n oUnit of lete Order V.I.
Unit Price Not Used Not Used Not Used Not Used
SaLion No.. Measure De
1
Totals
This document has born moditicd from its original form os m FJCDC document and the user did not highlight the
modifications. You ore rneomagcd to rend the document m fully and consult Legal Counsel prior to its -doo.
Contractor's Application
Application Numbcr: 17 Final
Apolirntion Date: 6/29/2023
E F
Not Uscd Not Used Not Used Not 11sed
C-620 Change Order
Progress Estimate Change Order Number 1 3
ADDITIONS
Contractor's Application
Far(contracq' 102098 HMAC Surface Overlay 2019-6 City Sarutry 53393 Application Numbr: 17 Final
Contract Num:
Application Prfad 311/23 - 6/29/23 Application Dote: 6/29/2023
Change Order Item
No.
A B C D E F
itern
Addition Total Completed
Estimated Quantity Previously Value This Materials P—dy and Stand to Date (F)
Spe fl.tian Unit of CO Quantity to Add Unit Price CImage Order Value
De.xiption Swtioa No. Mcasme Value ��`d hsmlled Value Period Stored not in C) (D+E) B
Tomis
This document has been modified from its original Iona as an EJCDC document and the us r did not highlight the
modifications. You mo enwumged to read the document oureNuy and consult Legal Counsel prior to its execution.
Balance to Finish
(B - F)
G820 Change Order
Progress Estimate
Change Order Number 1 3
Contractor's Application
DELETIONS
For (contract): 102098
11MAC Surface Overlay 2019.6
Application Number.
17 Final
Apptienfi. Period:
3/1/23 - 6/29/23
Application note:
6/29/2023
A
B
C
D E
F
Change U, , Item
Item CO Quantity to
Specitieation Unit of Unit Price
lleletion
Change Order
Nol Used
Not Used Not Used Not Used Not Used
Not Used Not Used Net Used
No.
Description Delete
Section No. Measure
Value
Totols
This document has been modified Gom its original form as an EICDC document and the user did not highlight the
modifications. You ore cnmumgod to read the document carefully and consult Legal Couesel prior to its esecution.
C-620 Change Order
Progress Estimate Change Order Number 1 4 Contractor's Application
ADDITIONS
For(comme0: 102098 HMAC Surface Overlay 2019-6 City Secretary 53393 Application Number: 17 Final
ContraclNum:
Application Period 3/1/23 — 6/29/23 Application Date: 6/29/2023
A B C D E F
It® Balance to Finish
Addition Tool Completed %
Estimmcd Quantity Value Previously Value This Mmeriols p`—tIy end Stared to Date
No. Description Section No. Mcesme Value (F) (B _ F)
Change Order Item Specification hvsWInsmll
Unit of CO Quantity to Add Unit Fri« Change Order led ed Vnluc Period Stored (not in C) (D+E) B
Tomis
This document hue been modified from its original form as on E1CDC document and the user did not highlight the
modifications. You we encouraged to tend the document carefully end consult Legal Counsel prior to its esecution.
C-620 Change Order
Progress Estimate
Change Order Number 1 4
DELETIONS
For (eentmet): 102098
nMAC Surface Overlay 2019-6
Application Number:
Application Period:
311/23 - 6/29123
Application Dnlc:
A
B C
D E
Change Order Item
Item
spccificutien Unit of CO Quantity to
Deletion
Unit Price Change Order Not Used
Not Used Not Used Not Used Not Used
No.
Description section No. Meosum Delete
Value
Totals
This document hos been modified from its original form as ratFJCDC document end the mer did not highlight the
mad flMtions. You ore encouraged to read the document carefully and consult Legal Counsel prior to its esecution.
Contractor's Application
17 Final
6/29/2023
F
Not Used Not Used Not Used
C•620 Change Order
Progress Estimate
Change Order Number 1 5
Contractor's Application
ADDITIONS
For (contract): 102098
HMAC Surface Overlay 2019-6
City Secretary
53393
Application Number.
17 Final
Contract Nam:
Appliention period:
3/1/23-6/29/23
Application Dmac
6/29/2023
A
B
C
D E
F
Item
Balance to Finish
Change Order Item
Specification Unit oC CO Quantity to Add
Addition
Unit Price Change Order
Estimated Quantity
previously Value This Materials presently
Value
Installed Value Period Stored in C)
Total Completed Y
(B _
and Stared to Date (F)
No.
D..cnpuon gentian No. Measmc
Value
Installed
(not
(D+E) B
Totals
This document has been modified Lam its original Corm a an EJCDC document and the user did not highlight the
modifications. You are encouraged to read the document carefully and consult Legal Counsel prior to its esecution.
C-620 Change Order
Progress Estimate Change Order Number 1 5
DELETIONS
For (contract): 102098 FIMAC Surface Overlay 2019-6
Application Period: - 3/1/23 - 6/29/23
item
Chong.Ordcr Item Description
No.
Totals
A B C D
llcletion
S c Lion No. Unit of CO Q—tDetetcty to Unit Price Clunk Order Not Used Not Used Not Used Not Used
Section No. M.a vre dote Voluc
This document has hem modified from its originW form as an FJCDC docomrnt and the user did not highlight the
modifications. You me mcoumged to read the dm mmn emefully and consult Legal Counsel prior to its execution.
Contractor's Application
Application Numbs. 17 Final
Application Dot. 6/29/2023
B r•
Not Used Not Used Not Uscd Not Used
C-620 Change Order
Progress Estimate Change Order Number 1 6 Contractor's Application
ADDITIONS
For (contract): 102098 HMAC Surface Overlay 2019-6 City Secretary 53393 Application Number: 17 Final
Contract None
Application Period VIM -6/29/23 Application Dntc 6/29/2023
n B C D E F
hem Balance to Finish
Addition Total Completed
Change Order Item Estimated Quantity Previously Value This Moored ( of in C) (B - F7
specification Non Unit of CO Quantity to Add Unit ]'rice Change Order Value and Stored to Date (F)
No. Description Section No. Measure Value InsW11M Installed Value Period Stored (not in C) (D-E) B
Totals
This document has been modified from frontcum its original Caas on E)CDC document and the user did not highlight the
modifications. You are, encouraged to read the document carefully and consult Legal Counsel prior to its a tioo.
C-620 Change Order
Progress Estimate Change Order Number 1 6
DELETIONS
For (matmet): 102098 HMAC Surface Overlay 2019-6
Application Period: VIM - 6/29/23
A H C
It— CO Qamtity to Deletion
Change Or Item Description Specification Unit of Delete Unit Prim Change Order Not Used
No. Section No. Measure Value
Totals
D
Not Used Not Used Not Used
This do arnent has been modified from its original Conn as an FJCDC doeumcnt and the user did not highlight the
modifications. You we enwumged to read the document carefully and consult Legal Counsel prior to its execution.
Contractor's Application
Application Numbee 17 Final
Application Date: 6/29/2023
E F
Not Used Not Used Not Used Not Used
C-620 Change Order
Progress Estimate
Change Order Number 1 7
Contractor's Application
ADDITIONS
Far(—trae)102098
HMAC Surface Overlay 2019-6
City See mry
53393
Applientian Number
17 Final
Cramer Num:
Appliention Period:
3/1/23 - 6/29/23
Application Date:
6/19/2023
A
B
C
D E
F
Item
Balance to Finish
Change Order Item
SpeciGwtion Unit of CO Quantity to Add
Addition
Unit Price Change Order
Estimated Quality
Previously Va This Mmred(presw0y
Value
Total Completed Y
and Stared to Date CF) (B-p)
No.
Description Section No. Meosme
Value
sta
Installed
stalled Value P¢iod Stared (not in C)
Period
(D+E) B
Totals
This document has been modified from its original form as an EICDC document and the user did not highlight the
madiLeations. You we encouraged to read the donanent eamfully and consult Legal Counsel prior to its execution.
C-620 Change Order
Progress Estimate
Change Order Number 1 7
Contractor's Application
DELETIONS
For (contract): 102098
$MAC Surface Overlay 2019-6
Application Number
17 Final
Aophmtion Period:
3/1/23 - 6/29/23
Anpfication Date:
6/29/2023
A
B C
D E
F
Itcm CO Quantity to
Deletion
Change Order Item
No.
Spoe fration Unit of
Description Section No. Mwsaro Ddde
Unit Prier Change Order Not Used
Value
Not Used Not Uscd Not Used Not Used
Not Used Not Used Not Used
Totals
This donanent has bean modified from its original Conn = an FJCDC document and the ma did not highlight the
modifications. You ma mmomged to rood the dacvtnom moofully and meadt Legal Counsel prior to its amotion.
C-620 Change Order
Progress Estimate
Change Order Number 1 8
Contractor's Application
ADDITIONS
For(omarmt): 102098
HMAC Surface Overlay 2019.6
City Secretary
53393
Application Number:
17 Final
Contract Num:
Appliention Period
3/1/23 — 6/2923
Application Datv..
6/29/2023
A
B
C
D E
F
Item
Balame to Finish
Change Ordcrltem
SpedUnit of CO Quantity to Add
Addition
Unit Price Change Order
Estimated quantity
Previously value This Materials Presently
Value
Total Completed
and Stored to D¢te (F) (B _ F)
No.
Non
Description SectionNo. Measure
Value
Installed
Installed Value Pcri¢d Stored (rat in C)
(D+E) B
Totals
This document has born modified from its original Cann as an E1CDC document and the user did not highlight the
modifications. You are eneoumged to read the document cmefully and consult Legal Counsel prior to its mention.
CE20 Change Order
Progress Estimate Change Order Number 1 8
DELETIONS
For (contruct): 102098 HMAC Surface Overlay 2019-6
Application Period: 3/1/23 - 6/29/23
A B C
Item CO
Changc Order Itern specification Umt of CO DelQuaete to Unit price Change Order Not Uscd
No.pti06 Section No. Meosrue Delete Value
Totals
Contractor's Application
Application Number. 17 Final
Application Dom: 6/29/2023
D E F
Not Used Net Used Not Used Not Uscd Not Used Net Used Not Used
This document has be. m.dificd from its original form as on E)CDC d.--t end the user did not highlight the
modifications. You arc encouraged to read the document carefully and consult Legal Counsel prior to its ewoutim
City of Fort Worth Summary of Charges
City Secretary Contract Num: 53393 HMAC Surface Overlay 2019-6 P. 0.: FW020-0000003282
Application Period: 3/1/23 - 6/29/23 Application 17 Final
Number:
Funding Identification (FID)
Original Contract
30100-0200431 *5740010-102098-006280-9999
0
0
0
0
0
0
0
0
0
0
Change Order 1
30100-0200431 *5740010-102098-006280-9999
0
0
0
0
0
0
0
0
0
0
Change Order 2
30100-0200431 *5740010-102098-006280-9999
0
0
0
0
0
0
0
0
0
0
Project Number: 102098
Application Date: 6/29/2023
Total Completed
Amt Remaining
Gross
Retainage I
i i
I
i
I
I
i I
$984,729.95
$95,245.05
$0.
$0.00
1_0
$0.00
0.0o
II1
Jam
s0 00
$Mo
$o0o
$0.00
S0.00
$0.00
$0.00
$0.00
30.00
$0.ao
$0 ao IIII
$0.00
30.00
$0.00
$O.00
$0.00
SOOo
$0.00
$000
I O.Oo
SO.00
$0.00
$0.00 I
I $o_oo I
3000 I I
so.ao I I
$0 00 I
1 $o.00
I So.00 I I
$o.00 I I
$0.00 I I
I $0 00
I 30.00 I I
$0 00
77
1 I
$0.00
50.00
$0.00
so.00
I $0.00 I
I 60.00 I
$0.00
I $0.00 i
I so 0o I I
$0.00 I
$0 00 I
I $0_00 I
I 30.00 I I
$0.00
s0.00 I
I $0.00 I
SO oo I I
$Mo I I
$0 00
I h0.0U I
I 50.00 I I
$0.00 I I
$O oo I
I $0 00 I
s0.00 I I
$0.00 I I
$0 00 I I
I $0.00 I
I SO.00 I I
$0.00 I I
so.00 I I
I $0.00 I
I so 0o I I
$0 00 I
$o 0o I I
I $0.00 I
I SO.00 I I
$0.00 I I
$0.00 I I
$o.00
I so 0o I I
$0.00 I I
3000 I I
I
I � I
I I
I
$0.00
So 00
$0 00
SO Oo
I $U.00 I
Sam I 1
$0.00 I I
$090 I I
I $0.00 I
so oo I I
so.ao I I
S&oo I I
I $0.001
So.001 I
$0.001 I
30.001 I
$0.00 I
3000 I I
$0.00 I I
$0 00 I I
I $0.00I
50.00I I
$0.00I I
$0.00I
I :10-00 1
I SO 00 I I
$0.00 I I
$0 00 I
$0.00I
I So.001 I
$0.00I (
50.001
$0.00
I 50.00 I 1
$0.00 I I
soon I I
I iGG.o0I
I So.00I I
$0.00I I
$0.00I i
I $0.00
I SO.00 I I
$0 00 I I
Woo I I
Net
$0.00
$0.00
$0.00
$0.00
$0.00
50.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00 1
$0.0o I
$o.00 I
$0.00
$0.00 I
$0.00
$o.00 I
$o.o0 1
$0.001
$o.o0 1
$0.001
$0-00
$0.00
Moo
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
City of Fort Worth Summary of Charges
City Secretary Contract Num: 53393 HMAC Surface Overlay 2019-6 P. 0.: FW020-0000003282
Application Period: 3/1/23 - 6/29/23 Application 17 Final
Number:
Funding Identification (FID)
Change Order 3
30100-0200431 *5740010-102098-006280-9999
0
0
0
0
0
0
0
0
0
0
Change Order 4
30100-0200431 *5740010-102098-006280-9999
0
0
0
0
0
0
0
0
0
0
Change Order 5
30100-0200431 *5740010-102098-006280-9999
0
0
0
0
0
0
0
0
0
0
Project Number:
Application Date:
Total Completed Amt Remaining 1 7-Gross I Retainage
I102098
6/29/2023
$0.001
50.001 I
$0.00 1
30.00 I
$0.00 1
30.001 I
$0.001 I
30.001 I
$0.00 I
S0.06I I
$0.00I I
30.00I I
$o 'Do I I
so 00 I I
$0.00 I I
$0 00 I I
$0.001 I
$0.00I I
$0.001 I
Sam
$o.o0 I I
3000 I I
$0 00 I I
$0 00 I I
I I $0.00 I I
S0.00 I I
$0.00
$0.00 I I
I I $0.00 I I
so 0o I I
$0.00 I
$0.00 I I
I I ro.00 I I
s0 00 I I
w.00
$0.00 I I
1 $0.00 I I
50.00 I
$0 00 1
$0 00 1 I
I `E6.001 I
S0.00I I
$0.001 1
$0.00 I
I I
I I I
sl
I
$0.00
S0.00
$0.00
50.00
$o.o0 I
S0 00 I I
$o-00 I I
$o.00 I
$0.00 1 I
Sa.00 1 I
$0.00 1 I
$0.00 1 I
I $0.00I I
30.00I
$0.00I I
$0.00I I
I $0.00 I I
so oc 1 I
$0.00
$0 00 I
I $o.00 I I
so 0o I I
$0.00 I I
To 00 I I
1 $0.001 1
S0.001 I
$0.001 I
$0.001
I $0.00 1 I
30.00 I I
$0.00 I 1
$0 00 I I
I $0.0o I I
s0.00 I I
$0.00 I I
$0.00 I I
I $0.00 I I
So.00 I I
$0.00 I I
$0 00 I I
1 $o.001 I
S0.001 I
$0.001
$0.001
I I I I
I I
I I
$0.00
S0.00 I
$0.00
$0.00
$0.001 I
S0.001
$0.001 1
$0.01)
I $0.00 I I
So.00 I I
$0.00 I
30 0c,
I $0.00 I
so 00 I I
Sam I I
H 00 I I
I $0.001 I
30.001 1
$0.001 1
60.001 1
I $o.00 I
30.00 I I
s0.00 I I
SOLO I I
I $0.00 1 I
So.00 1 I
$0.00 1 I
$0.00 1 I
I $0 00 I I
s0.00 I I
$0.00 I I
$0.00 I I
I $o.oc I I
S0.00 I I
$0.00 I I
$0.00 I I
I $0.00 I
s0 00 I I
$0 00 I I
$0 00 I I
$0.00 I
I I I
S0.00 I 1
I I
$0.00 I I
I I
$0 00 I I
I I
Net
$0.00 1
$o.00 I
$0.00 1
$0.00 1
$0.00 I
$0.00 1
$o.00 I
$0.00
$0.00
$0.00
$0.00 I
$o.00
$0.00 I
$o.00 I
$0.00 I
$0.00 I
$0.00 i
$0.00
$UAO
$0.00 1
$o.00 1
$o.001
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$o.oa
$0,00
$0.00
City of Fort Worth Summary of Charges
City Secretary Contract Num: 53393 HMAC Surface Overlay 2019-6 I P. O.: FW020-0000003282Project Number: 102098
Application Period: I 3/1/23 - 6/29123 Application I 17 Final Application Date: 6/29/2023
Number:
Funding Identification (FID) I I Total Completed Amt Remaining I I Gross I I Retainage I I Net
Change Order 6
1
n
130100-0200431*5740010-102098-006280-9999
I
$0.00
S0.00
$0.00
$0.00
$0.00
10
$o.oc I I
so.00 1 1
$0.00 1 1
$0 00 1 1
$0.0) I
10
$o.00 I I
SO.00 1 1
$0.00 1 1
$0.00 1 1
$0.00 I
10
! I $0.00 1 1
so.00 1 1
$0.00 1 1
$o.00 I I
so.00 I
10
I $0.00 1 1
so.00 1 1
$0.00 1 1
$0.00 1 1
$0.00 1
10
I I $0.00 1 1
S0.00 1 1
$&GO 1 1
$0 00 1 1
so.Oo 1
10
I i $0.00 1 1
SO.00 1 1
$0.00 1 1
so.00 I I
m.00 I
10
I I $0.00 1 1
so 00 1 1
�r0.00 I I
SO.00 I I
SO.00 1
10
I I so.00 I I
s0.00 I 1
$0.00 1 1
10,00 1 1
$0.00 I
10
1 1 $0.00 1 1
so 0o 1 1
$0.00 1 1
$coo 1 1
$0.00 I
10
1 1 i60.00 1 1
So.00 I 1
1i0.00 1 1
I
so.00 I I
I
$o.00 1
I
I
I
I l I
I
I
I
I
Change Order 7
I
130100-0200431 *5740010-102098-006280-9999
1
$0.00
SO.00
$0.00
so.00
$0.00
10
I I $0.00 1 1
Sam I I
so.00 I 1
$0.00 1 1
so.00
10
I $0.00 1 I
So.00 I I
$o.00 I 1
$0.60 1 1
so.00 I
10
I $0.00 1 1
saoo I I
$o.o0 1 1
$0.00 1 1
so.00
IO
I I $0.00 1 1
SO.00 1 1
$0.o0 1 1
$0 00 1 1
$0.00 I
IO
I $o no I I
SO o0 1 1
$0.00 1 1
$c 00 1 1
so.00 I
10
I I $o.00 I I
so.00 I I
$0.00 1 1
$o.Uo I 1
$0.00 1
10
I I $0.00 1 1
so oo 1 1
$0.00 1 1
$0 00 1 1
so.00
10
I I $o.00 I I
50.00 I I
$0.00 1 1
$aoo 1 1
$0.00 1
10
I I $0.00 1 1
So 0o 1 1
$0.00 1 1
$0 00 1 1
$o.00 1
10
I I $0.00 1 1
so.00 I I
so.00 I I
$O.Oo I I
$0.00
Change Order 8
130100-0200431 *5740010-102098-006280-9999
I
$0.00
so.00
so 00
$0. oo
`G0.00
10
I $0.00 1 1
so.00 1 1
$0.00 1 1
So oo 1 1
so.Oo I
1O
I $0.00 I 1
so oo I I
so.00 1 1
$0 00 I I
so.00 I
10
I I $o.oc 1 1
so 0o I I
$0.00 1 1
$0.00 1 1
$0.00
IO
I I $0.00 I 1
30.00 I 1
$0.00 1 1
som I I
$o.00 I
IO
I I $0.00 1 I
Sam 1 1
$0-00 1 1
Woo I I
$o.0o 1
10
1 $O.Oo I I
50.00 I 1
$0.00 1 1
$0.00 1 1
1:0.00 I
10
1 $0.00 1 1
s0 00 1 1
$0.00 1 1
$0.00 1 1
so -Go
10
1 $0.00 1 1
Sam 1 1
Moo 1 1
yo.00 I I
$0.0o 1
10
I 1 so.00 I I
So.00 1 1
$0-00 1 1
$0 00 1 1
$0.00 1
IO
I so.00 1 1
SO.00 I I
so.00
$o.00 I I
$C.oc I
City of Fort Worth Summary of Charges
City Secretary Contract Num: 53393
HMAC Surface Overlay 2019-6
P. O.:
FW020-0000003282
Project Number:
102098
Application Period:
3/1/23 - 6/29/23
Application
Number:
17 Final
Application Date:
6/29/2023
Funding Identification (FID)
Total Completed Amt Remaining
Gross
1 Retainage ;
I Net 1
L
I
Totals
30100-0200431*5740010-102098-006280-9999
$984,729.95 i
$95,245.05 1
$0.00
$0.00
$0.00
0
I �0I I
;-1I 1
$0.00I
I $0.00I
I $0.00I
0
I i JC I t
=; I
$0.00 I
I $o.00 I
$6.00 I
0
I I $0.0o I I
SUC I
$0.00 I
$0.00 I
I $o.00 I
0
I $6.001 I
So.001
$0.00
I S0.00
1 $0.001
0
I $o.00 I I
3000 I
$0.00 I
1 $0 00 I
$0.00 I
0
I $0.00 I I
S0 0o I I
$0.00 I
I $0.00
I $0.00 I
0
I $0.00 I
S0.00 I I
so.00 I
I $0 00 I
i $o.00 I
0
I $0.00 I
S0.00 I 1
$0.00 I
$c.0o I
1 $0.00
0
$0.00 I I
S0 00 I I
$0.00 I
S0 00 I
$0.00 I
0
$6.00 I I
S0.00 1 I
$C.00 I
'0 rj o(
.7,0.09 I
Grand Total
I $984,729.95 I 1
$95,245.05 I 1
$0.00 1
1 ($49,236.49)1
1 $49,236.49
FORT WORTH.
Routing and Transmittal Slip
Transportation & Public Works
Department
DOCUMENT TITLE: CO 1, HMAC Surface Overlay 2019-6
M&C: N/A CPN: 102098 CSO: 53393 DOC#:
Date: 6-15-2023
To: Name
Department
Initials
Date Out
1. Valentina Riera
TPW - initial
Iz-
J u n 15, 2023
2. Brendan Taylor
Vendor - signature
Bs
J u n 15, 2023
3. Brian McGill
TPW - signatures
J u n 15, 2023
4. Tariqul Islam
TPW - signature
T/
Jun 15, 2023
5. Omar Elbagalati
TPW - signatures
J u n 15, 2023
6. Mary Hanna
TPW - initialer
Jun 15, 2023
7. Michael Owen
TPW - signatures
Jun 16, 2023
8. Lauren Prieur
TPW - signature
Jun 16, 2023
9. Doug Black
Legal - signatures
Jun 20, 2023
10. William Johnson
CMO - signature
W
Jun 22, 2023
11. Jannette Goodall
CSO - signature
Jun 22, 2023
12. TPW Contracts
TPW
DOCUMENTS FOR CITY MANAGER'S SIGNATURE:
All documents
received from any
and all City Departments requesting City Manager's signature for approval MUST BE ROUTED
TO THE APPROPRIATE
ACM for approval first. Once the ACM has signed the routing slip,
David will review and take the next steps.
NEEDS TO BE NOTARIZED:
❑YES ®No
RUSH: ❑YES ®No
SAME DAY: ❑YES ❑No
NEXT DAY: ❑YES ❑No
ROUTING TO CSO: ®YES ❑No
Action Required:
❑ As Requested
❑ For Your Information
® Signature/Routing and or Recording
❑ Comment
❑ File
❑ Attach Signature, Initial and Notary Tabs
Return To: TPWContractsaFortWorthTexas.2ov at ext. 7233 for pick up when completed.
CSC No. 53393-COI
Fox_ T� x;
Project Namel HMAC Surface Overlay 2019-6
Client Project #(s)I 102098
Project Description)
Contractorl
City Project Mgr.l
Peachtree Construction Ltd
Tariqul Islam
Dept.
Original Contract Amount
Extras to Date
Credits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Date
lGo to ADD & DEL Tabs to Enter CO Backup
Revised Contract Amount
Original Funds Available for Change Orders
Remaining Funds Available for this CO
Additional Funding (if necessary)
City of Fort Worth
Change Order Request
City Sec # I 53393
Pulverization of existing street and 3 inch asphalt overlay at various locations
TPW
$1,079,975.00
Change Order #I 1 1 Date 6/12/2023
City Inspector Brian McGill
Contract Time
Totals (CD)
$1,079,975.00 175
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT 0.00%
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST+ 15%) $1,349,968.75
JUSTIFICATION (REASONS) FOR CHANGE ORDER
This change order is to add 310 additional days to the project contract time due to water line conflict, water main break, gas line conflict and rain delays. Here is breakdown of
delays: 1. Water main break on 5th Ave (97 days): Due to the shallow depth of the existing water line, the contractor broke it during construction and had to mobilize out of the
site until Water Department replaced it under a different contract. Atmos had to work on their gas line relocation work on this street at the same time. The work was stopped on
5th Ave from 06117/2020 until 10/10/2020. The total 97 days of delay deemed reasonable to be granted for the critical path of the work activities on this street. ,
2. Waterer main replacement on Lagonda Ave and Denver Ave (91 days): After construction started, the Contractor couldn't perform the 11" pavement pulverization due to the
water main being cast iron and too shallow and need to be replaced. The work was stopped from 11/11/2020 until 2/10/2021 for the water department to complete the water main
replacement. The total 91 days of delay deemed reasonable to be granted for the critical path of the work activities on this street. ,
3.The tying in of Lagonda Ave and Denver Ave (94 days): The tying in of Lagonda Ave and Denver Ave to NE 28th St required a mill and overlay at the intersection instead of
pulverization for the existing concrete base. The work was stopped from 3/11/2021 until 6/13/2021 to finalize an alternate work approach, receive a quote from the contractor, and
price negotiation. Construction allowance #2 was executed for this work on 06/02/2021. The total 94 days of delay deemed reasonable to be granted for the critical path of the
work for this purpose on this street. 4. Rain/Weather delays (28 days): Experienced more than average yearly rain days and couldn't do any work on the following days:
3/412020, 3/13/2020 — 3/16/2020, 3/18/2020 — 3/20/2020, 3/23/2020 — 3/27/2020, 3/31/2020, [March 2020 had 19 days with measurable rainfall and set an all-time record for
days with consecutive rainfall] 10/23/2020— 10/27/2020, 12/11/2020, 12/30/2020, 2/11/2021— 2/21/2021, 2/25/2021 [February 2021was the month of the historical winter evenu
snow storm in Texas]. 5. The inspector's log, email communications, and weather report pertaining to these delays have been documented. A memo to TPW Director regarding
this delay is attached with the change order.
it Is understood and agreed that the acceptance of tnls Lnange Urder by the contractor constitutes an accord and satlstaction and represents payment In tun
(both time and money) for all costs arising out of, or incidental to, the above Change Order. The Project/Program Manager signing below acknowledges that
he/she is the person responsible for the monitoring and administration of this contract, including ensuring all performance and reporting requirements.
IN Contractor's Com
Peachtree Construciton Ltd.
Contractor
Brendan Taylor
Contract
15, 2023
Inspector/Inspection Supervisor
F
Project and Contract Compliance Manager
Date
Jun 15, 2023
Jun 15, 2023
Program Manager
Date
Senior Capital Project Officer
Date
Jun 15, 2023
Jun 15, 2023
Assistant Director (Dept)
Date
Director, Contracting Department (Dept)
Date
' ��"'�^� �'����•+�►
J u n 16, 2023
J u n 16, 2023
Assistant City Attorney
Date
Assistant City Manager
Date
(
Jun 20, 2023
Jun 22, 2023
Council Actio
M&C Number I
ATTEST:
�_a "
Jannette Goodall, City Secretary
M&C Date Approved
FORT WORTH City of Fort Worth
�'*`--- Change Order Additions
Project Name I HMAC Surface Overlay 2019-6
Client Project # 1 102098
Contractorl Pulverization and asphalt overlay at various locations l
I I tM DESOHIP I ION
City Sec # 1 53393 1 ###
I
PMl Tariqul Islam Inspectorl Brian McGill l
Peachtree Construction Ltd F— Date 1 6/12/2023 1 4/1/2022
ADDITIONS
DtPI Oty Unit Umt(:ost total
I
I
I
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
TF W $0.001
I I
I I
I I
Sub Total Additions $0.001
Change Order Additions Page 2 of 4
FORTWORTH City of Fort Worth
Change Order Deletions
Project Name I HMAC Surface Overlay 2019-6
Client Project # I 102098
Contractorl rurvencauun anu iaspnmL Wendy ai vanuus ,��a.
ITEM DESCRIPTION
City Sec # 53393 ###
PMl Tariqul Islam I Inspeclorl Brian McGill
Peachtree Construction Ltd Date 1 6/12/2023 4/1/2022
DELETIONS
DEPT Oty Unit Unit Cost Total
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
TF W $0.001
I
I
I
Sub Total Deletions $0,001
Change Order Deletions Page 3 of 4
M/SBE for this Change Order
M/SBE Sub Tvpe of Service Amount for this CO
Total $0.00
Previous Change Orders
co # DATE I AMOUNT
Total I $0.00 1
FORT WORTH:..
Memorandum
Date June 12, 2023
To Lauren Prieur
Director, Transportation, and Public Works
From Tariqul Islam
Project Manager, Transportation, and Public Works
Subject HMAC Surface Overlay (City Project Number 102098)
Excessive delay in project completion
This project was advertised to bid on September 12, 2019, after coordination with Water
Department, and it was cleared by them to rehabilitate the asphalt pavement. Construction started
on March 02, 2020, with a total of 175 calendar days.
During construction, the Contractor had to stop working and mobilize out of the project until
several conflicts were resolved, as stated below:
1. 5th Ave: A section of 5th Ave was included in the project for pulverization and overlay. Due
to the shallow depth of the existing water line, the contractor broke it during construction
and had to mobilize out of the site until Water Department replaced it under a different
contract. Atmos had to work on their gas line relocation work on this street at the same
time. The work was stopped on 5th Ave from 06/17/2020 until 10/10/2020. The total 97 days
of delay deemed reasonable to be granted for the critical path of the work activities on this
street.
Update: A change order will be processed to add 97 days to the contract.
2. Lagonda Ave and Denver Ave: After construction started, the Contractor couldn't perform
the 11" pavement pulverization due to the water main being cast iron and too shallow and
need to be replaced. The work was stopped from 11/11/2020 until 2/10/2021 for the water
department to complete the water main replacement. The total 91 days of delay deemed
reasonable to be granted for the critical path of the work activities on this street.
Update: A change order will be processed to add 91 days to the contract.
3. Lagonda Ave and Denver Ave: The tying in of Lagonda Ave and Denver Ave to NE 28th St
required a mill and overlay at the intersection instead of pulverization for the existing
concrete base. The work was stopped from 3/11/2021 until 6/13/2021 to finalize an alternate
work approach, receive a quote from the contractor, and price negotiation. Construction
allowance #2 was executed for this work on 06/02/2021. The total 94 days of delay deemed
reasonable to be granted for the critical path of the work for this purpose on this street.
Update: A change order will be processed to add 94 days to the contract.
4. Rain/Weather Delays: Experienced more than average yearly rain days and couldn't do any
work on the following days: 3/4/2020, 3/13/2020 — 3/16/2020, 3/18/2020 — 3/20/2020,
3/23/2020 — 3/27/2020, 3/31/2020, [March 2020 had 19 days with measurable rainfall and
set an all-time record for days with consecutive rainfall] 10/23/2020 — 10/27/2020,
12/11/2020, 12/30/2020, 2/11/2021 — 2/21/2021, 2/25/2021 [February 2021was the month of
the historical winter event/snow storm in Texas].
TRANSPORTATION PUBLIC WORKS DEPARTMENT
CAPITAL DELIVERY DIVISION
THE CITY OF FORT WORTH * 200 TEXAS STREET * FoRT WORTH, TEXAS 76102
*Tel 817-392-8363* * Fax 817-392-8092*
HMAC Surface Overlay (CPN 102098)
Excessive delay in project completion
Page 2 of 2
Memorandum
Update: A change order will be processed to add 28 days to the contract.
The inspector's log, email communications, and weather report pertaining to these delays have been
documented.
This project was completed almost two years ago, but due to the type of contract being calendar
days, this necessitated the need to execute a change order for additional time after the project was
accepted. The project was managed by multiple PMs, some no longer with the City. Due to the staff
turnover and lack of proper documentation of the changes, the change order was not processed
timely. Measures are being taken to ensure that similar situations do not occur in the future. The
Project Manager will diligently adhere to City policy by promptly initiating change orders following
any project delays, and saving all the project documentation on BIM360 or any future document
management system.
Conclusion: A change order of 310 additional days of contract time will be routed for execution.
The final payment to the contractor and project reconciliation will be followed.
TRANSPORTATION PUBLIC WORKS DEPARTMENT
CAPITAL DELIVERY DIVISION
THE CITY OF FORT WORTH * 200 TEXAS STREET * FoRT WORTH, TEXAS 76102
*Tel 817-392-8363* * Fax 817-392-8092*
FORTWORTH.
M,
TRANSPORTATION AND PUBLIC WORKS
June 29, 2023
Peachtree construction
5801 Park Vista Circle
Keller, TX 76244
RE: Acceptance Letter
Project Name: HMAC Surface Overlay (2019-6)
Project Type: paving
City Project No.: 102098
To Whom It May Concern:
On September 22, 2021 a final inspection was made on the subject project. There were no punch list
items identified at that time. The final inspection indicates that the work meets the City of Fort Worth
specifications and is therefore accepted by the City. The warranty period will start on September 22,
2021, which is the date of the final inspection and will extend of two (2) years in accordance with the
Contract Documents.
If you have any questions concerning this letter of acceptance, please feel free to contact me at 817-
392-2486.
Sincerely,
kzr
Tariqul Islam (Jul 7, 2023 14:56 CDT)
Tariqul Islam, Project Manager
Cc: Brian McGill, Inspector
Gary Deyon, Inspection Supervisor
Gary Deyon, Senior Inspector
Mary Hannah, Program Manager
Cirt of Ft Worth, Consultant
Peachtree Construction, Contractor
City of Ft Worth, Developer
File
E-Mail: TPW_Acceptance@fortworthtexas.gov
Rev. 08/20/19
Bond: 106971478
CONSENT OF
SURETY COMPANY
TO FINAL PAYMENT
Conforms with theAmorlean Institute of
Architects, AIA Document G707
OWNER
M
ARCHITECT
F]
CONTRACTOR El
SURrTY
0
OTRER
El
PROJECT. HMAC Surface, Overlay 2019-6 City Proj No. 102098
TO (Owner)
City of Fort Worth
200 Texas St. ARCHITECT'S PROJECTNO,
Fort Worth, TX 76102 CONTRACT FOR: Construction
CONTRACT DATE: Dec 18, 2019
CONTRACTOR: Peachtree Construction, LTD
-TX1.6.244 -1 . ........ . ... . ... .
In accordance with the provisions of the Contract between the Owner and the Contractor as above, the_--
Travelers Casualty and Surety Company of America
9601 McAllister Freeway, Suite 9.00; -San Antonio, TX 78216 SURETY COMPANY,
on bond of
Peachtree Construction, LTD,
5801 Park Vista Cir, Keller, TX 76244
,CONTRACTOR,
hereby approves of the final payment to the Contractor, and agrees that final payment to the Contractor shall not relieve
the Surety Company of any of its obligations to
City of Fort Worth
200 Texas St., Fort Worth, TX 76102 OWNER,
as set forth in the: said Surety Company's bond,
IN WITNESS WHEREOF,
the Surety Qonipany has hereunto set its hand this 3rd day of July
2023
Su ty Company Tray qua ers Ca Do
erica
Witness: ig l, attro oflitherized 4Ro—tatmilsa i
Reyes, Sew tat
TeresaAyala
Name & Title
N.017'Nisfonn is to be used as 4 comjAniou Acournont to AIA D(RKIMENT (3700, CONTRACTOWS AFFfl)AVi;R6F—PAymF.NT
OV DMIS AND CLANS'.
CuffentEdition.
D0138 12/00 ONBPAGB
Travelers Casualty and Surety Company of America
Travelers Casualty and Surety Company
St. maul Fire and Marine Insurance Company
POWER OF ATTORNEY
KNOW ALL MEN BY THESE PRESENTS: That Travelers Casualty and Surety Company of America, Travelers Casualty and Surety Company, and
St, Paul Fire and Marine Insurance Company are corporations duly organized under the laws of the State of Connecticut (herein
collectively called the "Companies'), and that the Companies do hereby make, constitute and appoint Teresa Ayala of
FT WORTH , Texas , their true and lawful Attorney(s)-in-Fact to sign, execute, seal and
acknowledge any and all bonds, recognizances, conditional undertakings and other writings obligatory In the nature thereof on behalf of
the Companies in their business of guaranteeing the fidelity of persons, guaranteeing the performance of contracts and executing or
guaranteeing bonds and undertakings required or permitted in any actions or proceedings allowed by law.
IN WITNESS WHEREOF, the Companies have caused this Instrument to be signed, and their corporate seals to be hereto affixed, this 21st day of April,
2021.
Sol
State of Connecticut
City of Hartford as.
By:
ttobert L. Rane , entor Vice President
On this the 21st day of April, 2021, before me personally appeared Robert L. Raney, who acknowledged himself to be the Senior
Vice President of each of the Companies, and that he, as such, being authorized so to do, executed the foregoing instrument for the
purposes therein contained by signing on behalf of said Companies by himself as a duly authorized officer.
IN WITNESS WHEREOF, I hereunto set my hand and official seal,
My Commission expires the 301th day of June, 2026
tU?'IAAY Y
' c�`1° h nna P. Nowitc, Notary Public
This Power of Attorney is granted under and by the authority of the following resolutions adopted by the Boards of Directors of each of
the Companies, which resolutions are now in full force and effect, reading as follows:
RESOLVED, that the Chairman, the President, any Vice Chairman, any Executive Vice President, any Senior Vice President, any Vice
President, any Second Vice President, the Treasurer, any Assistant Treasurer, the Corporate Secretary or any Assistant Secretary may appoint
Attorneys -in -Fact and Agents to act for and on behalf of the Company and may give such appointee such authority as his or her certificate of authority
may prescribe to sign with the Company's name and seal with the Company's seal bonds, recognlzances, contracts of Indemnity, and other writings
obligatory in the nature of a bond, recognizance, or conditional undertaking, and any of said officers or the Board of Directors at any time may
remove any such appointee and revoke the power given him or her; and it is
FURTHER RESOLVED, that the Chairman, the President, any Vice Chairman, any Executive Vice President, any Senior Vice President or
any Vice President may delegate all or any part of the foregoing authority to one or more officers or employees of this Company, provided
that each such delegation Is in writing and a copy thereof Is filed In the office of the Secretary; and It Is
FURTHER RESOLVED, that any bond, recognizance, contract of Indemnity, or writing obligatory in the nature of a bond, recognizance,
or conditional undertaking shall be valid and binding upon the Company when (a) signed by the President, any Vice Chairman, any Executive
Vice President, any Senior Vice President or any Vice President, any Second Vice President, the Treasurer, any Assistant Treasurer, the
Corporate Secretary or any Assistant Secretary and duly attested and sealed with the Company's seal by a Secretary or Assistant Secretary;
or (b) duly executed (under seal, If required) by one or more Attorneys -in -Fact and Agents pursuant to the power prescribed In his or her
certif€cafe or their certificates of authority or by one or more Company officers pursuant to a written delegation of authority; and it Is
FURTHER RESOLVED, that the signature of each of the following officers: President, any Executive Vice President, any Senior Vice President,
any Vice President, any Assistant Vice President, any Secretary, any Assistant Secretary, and the seal of the Company may be affixed by facsimile to
any Power of Attorney or to any certificate relating thereto appointing Resident Vice Presidents, Resident Assistant Secretaries or Attorneys -in -
Fact for purposes only of executing and attesting bonds and undertakings and other writings obligatory in the nature thereof, and any such Power of
Attorney or certificate bearing such facsimile signature or facsimile seat shall be valid and binding upon the Company and any such power so executed
and certified by such facsimile signature and facsimile seal shall be valid and binding on the Company In the future with respect to any bond or
understanding to which it Is attached.
1, Kevin E. Hughes, the undersigned, Assistant Secreta_rryy,,, of each of the Companies, do hereby certify that the above and foregoing is a
true and correct copy of the Power of Attorney executeduby''s� .d faom riies, which remains in full force and effect.
Dated this 3rd day of JUiv 2023z.
3 µisrza,s� op
1::osta �g _
evin E. Hughes, Assl tank Secretary
To verify the authenticity o6hikPower ofAttorney, please callus at .1-800-4,2.1-.3880-
P/ease refer to the above -named Attorney(s)-in-Fact and the details ofthe bond to which thiq Power of Attorney is attached
AFFIDAVIT
STATE OF TEXAS
COUNTY OF Tarrant
Before me, the undersigned authority, a Notary Public in the state and county
aforesaid, on this day personally appeared Brendan Taylor (name), Proiect Manaaer
(title), of Peachtree Construction, Ltd., known to me to be a credible person, who being
by me duly sworn, upon his oath deposed and said;
That all persons, firms, associations, corporations, or other organizations
furnishing labor and/or materials have been paid in full;
That the wage scale established by City of Fort Worth has been paid; and
That there are no claims pending for personal injury and/or property damages;
On Contract described as;
HMAC Surface Overlay 2019-6
Subscribed and sworn before me on this , jObl-
day of 520 S
Notary PWlic in Tarrant County, Texas
P Y
"G Janet Lynn Reiter
•.
} My Commission Expires
9IF0 ID No. 130350G71