HomeMy WebLinkAboutContract 58704-CO1CSC No. 58704-COI
.�r
Project Name l 2023 Concrete Restoration Contract 2
Client Project #(s)I 104179
Project
City of Fort Worth
Change Order Request
City Sec # 1 58704
Description Repair and replacement of select concrete pavement panels on Meadowbrook Dr.
Contractorl Makou Inc. I Change Order #I 1 1 Datel
City Project Mgr.I Iretomiwa Otuyelu I City Inspectorl
6/29/2023
Travis Strang
Dept.
TPW
Contract Time
Totals (CD)
Original Contract Amount
$1,449,450.00
$1,449,450.00 180
Extras to Date
Credits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Date
$1,449,450.00
$1,449,450.00 180
Amount of Proposed Change Order
$184,750.00
$184,750.00
Revised Contract Amount
$1,634,200.00
$1,634,200.00 180
Original Funds Available for Change Orders
$200,000.00
$200,000.00
Remaining Funds Available for this CO
$200,000.00
$200,000.00
Additional Funding (if necessary)
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT
12.75%
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRA CT COST + 25%)
$1,811,812.50
Mir
JUSTIFICATION (REASONSLEOR CHANGE ORDER —.EEL
This Change Order is to increase the contract amount in Construction Contract 58704
During construction on Meadowbrook drive, it was discovered that the pavement thickness ranges from 8.5 inches to 11 inches, while the contract specifies 7 inches. Staff
negotiated an average of 10" with the contractor. Staff proposes to add 5300 SY of 10 inches concrete pavement (line item 29), and delete 4500 SY of 7 inches concrete
pavement (line item 4).
The concrete pavement transitions to asphalt pavement at varius sections on Meadowbrook Dr., the addition of HMAC Transition wil allow staff to repair asphalt pavement,
beyond the subsidiary 9 inches asphalt transition.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in
full (both time and money) for all costs arising out of, or incidental to, the above Change Order. The Project/Program Manager signing below
acknowledges that he/she is the person responsible for the monitoring and administration of this contract, including ensuring all performance and
reporting requirements.
ontractor's Compan Na Contractor(Nam Contract Signr
Makou Inc. Maqsood Khan ,--(Ju�,,,,�>.,
I Date
Jun 29, 2023
spection Supervisor
Date
Project and Contract Compliance Manager Er
Date
—st'
Jul 5, 2023
Jun 29, 2023
Program Manager
Date
Senior Capital Project Officer
Date
Jul 5, 2023
--7
Jul 6, 2023
Assistant Director Dept
Date
Director, Contracting Department Dept
Date
a ✓icia L. Wads ack
Jul 6, 2023
Jul 7, 2023
Assistant City Attorney
Date
Assistant City Manager
Date
1 I
Jul 7, 2023
iU-^
Jul 10, 2023
Council Action if required)
M&C Number I 23-0588 I M&C Date Approved I 6/27/2023
ATTEST:
Jannette Goodall, City Secretary pCAT°uL
a° � pa
Pam,
°aay4�z4sga
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
T: N �wide r�i City of Fort Worth
Change Order Additions
Project Name 1 2023 Concrete Restoration Contract 2 City Sec # I 58704
Client Project # I 104179 1
Contractorl Makou Inc. I PMI Iretomiwa Otuyelu Inspectorl Travis Strang I
Change Order Submittal # O1 Date 1 6/29/2023 1
ADDITIONS
I I tM UtSCKIP I IUN DEP 1
29 3213.0205 Remove and Replace 10" Cone Pvmt HES PW
30 3212.0401 HMAC Transition TPW
Uty Unit Unit Cost total I
5,300.00000000 SY $119.00 $630,700.001
30.00000000 TN $135.00 $4,050.001
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
TFW $634,750.001
1
I
1
Sub Total Additions $634,750.001
Change Order Additions Page 2 of 4
T t� V'�r;'r City of Fort Worth
T Change Order Deletions
Project Name 1 2023 Concrete Restoration Contract 2 City Sec # 1 58704
Client Project# 1 104179 1
Contractorl Makou Inc. I PMI Iretomiwa Otuyelu I Inspectorl Travis Strang I
Change Order Submittal # O1 Date 1 6/29/2023 1
DELETIONS
I I tM UtSUNIN I IUN JEH I
4 9999.uuuu Remove and Replace r" concrete Pavement hits I Nvv
uty unit unit cost lotal
4,5uu.uuuuuuuu 5y $1Uu.UU $4bU,000.l1Ul
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
TOW $450,000.00
I
Sub Total Deletions $450,000.00 1
Change Order Deletions Page 3 of 4
M/SBE for this Change Order
M/SBE Sub Type of Service Amount for this CO
Total $0.00
Previous Change Orders
CO # DATE I AMOUNT
Total I $0.00 1
City of Fort Worth, Texas
Mayor and Council Communication
DATE: 06/27/23 M&C FILE NUMBER: M&C 23-0588
LOG NAME: 202023 CONCRETE RESTORATION CONTRACT 2 CHANGE ORDER 1
SUBJECT
(CD 11) Authorize Execution of Change Order Number 1 in the Amount of $184,750.00 to a Construction Contract with Makou Inc. for the 2023
Concrete Restoration Contract 2 Project for a Revised Contract Amount of $1,634,200.00
RECOMMENDATION:
It is recommended that the City Council authorize the execution of Change Order Number 1 to a construction contract with Makou Inc. (City
Secretary Contract Number 58704) in the amount of $184,750.00 for the 2023 Concrete Restoration Contract 2 project at various locations on
Meadowbrook Drive for a revised contract amount of $1,634,200.00 (City Project No. 104179).
11 &10111*4101 kqF
On November 29, 2022, via Mayor & Council Communication (M&C) 22-0983, the City Council authorized execution of a contract with Makou Inc.,
in the amount of $1,449,450.00 for 2023 Concrete Restoration Contract 2 at various locations on Meadowbrook Drive.
Change Order Number 1 will provide for an additional 5300 square yards of 10 inch thickness concrete pavement to the contract and deletion
of 4500 square yards of 7 inch thickness concrete pavement from the contract. During construction on Meadowbrook Drive, it was discovered that
the pavement thickness ranges from 8.5 inches to 11 inches, while the contract specifies replacement to 7 inches of concrete. Staff negotiated an
average of 10 inches of concrete pavement with the contractor.
The concrete pavement transitions to asphalt pavement at various sections on Meadowbrook Drive. Staff recommends the addition of Hot Mix
Asphalt Concrete (HMAC) transitions which will allow staff to repair asphalt pavement beyond the subsidiary 9 inches of asphalt transition. Staff
has reviewed and verified the quantities for the additional work under this change order.
The following table summarizes previous contract action and change orders:
Construction Contract
Original Contract Amount (M&C 22-0983)
Change Order No. 1
Revised Contract Amount
Date Amount
11/29/2022 $1,449,450.00
This M&C $184,750.00
- $1,634,200.00
This change order will have no impact on the Transportation and Public Works Department's annual operating budget. Funding is budgeted the
Transportation and Public Works Department's General Capital Projects Fund for the purpose of funding the 2023 Concrete Restoration Contract
2 project, as appropriated.
M/WBE OFFICE — Makou Inc. agrees to maintain its initial M/WBE commitment of 100% that it made on the original contract and extend and
maintain that same M/WBE commitment of 100% to this first change order. Therefore Makou Inc. remains in compliance with the City's M/WBE
Ordinance and attests to its commitment by its signature on the Acceptance of Previous M/WBE Commitment form executed by an authorized
representative of its company.
FISCAL INFORMATION / CERTIFICATION:
The Director of Finance certifies that funds are available in the current capital budget, as previously appropriated, in the General Capital Projects
Fund for the 2023 Concrete Restoration 2 project to support the approval of the above recommendation and execution of the change order. Prior
to any expenditure being incurred, the Transportation & Public Works Department has the responsibility to validate the availability of funds.
Submitted for Citv Manaaer's Office bv: William Johnson 5806
Oriainatina Business Unit Head: Lauren Prieur 6035
Additional Information Contact: Monty Hall 8662
104179-CNCO-2023 Concrete Restoration
Contract 2
Interim Agreement Report 2023-07-13
Created: 2023-06-29
By: Andrea Munoz (Andrea. Munoz@fortworthtexas.gov)
Status: Out for Signature
Transaction ID: CBJCHBCAABAA7raokGrnOSOo8o-ag2zOtgUO8cPVB441
Agreement History
Agreement history is the list of the events that have impacted the status of the agreement prior to the final signature. A final audit report will
be generated when the agreement is complete.
"104179-CNCO-2023 Concrete Restoration Contract 2" History
Document created by Andrea Munoz (Andrea.Munoz@fortworthtexas.gov)
2023-06-29 - 6:22:11 PM GMT- IP address: 204.10.90.100
Document emailed to ann.estes@fortworthtexas.gov for filling
2023-06-29 - 6:39:57 PM GMT
Document emailed to makouinc@gmail.com for signature
2023-06-29 - 6:39:57 PM GMT
Document emailed to travis.strang@fortworthtexas.gov for signature
2023-06-29 - 6:39:58 PM GMT
Document emailed to Iretomiwa.Otuyelu@fortworthtexas.gov for signature
2023-06-29 - 6:39:58 PM GMT
Email viewed by makouinc@gmail.com
2023-06-29 - 6:40:02 PM GMT- IP address: 66.249.80.234
Email viewed by travis.strang@fortworthtexas.gov
2023-06-29 - 6:40:13 PM GMT- IP address: 166.205.54.26
Email viewed by Iretomiwa.Otuyelu@fortworthtexas.gov
2023-06-29 - 6:40:14 PM GMT- IP address: 138.229.172.23
Signer makouinc@gmail.com entered name at signing as maqsood khan
2023-06-29 - 6:41:37 PM GMT- IP address: 68.206.95.156
FORT WORTHS 1 Powered'y
Adobe
Acrobat Sign
Document e-signed by maqsood khan (makouinc@gmail.com)
Signature Date: 2023-06-29 - 6:41:39 PM GMT - Time Source: server- IP address: 68.206.95.156
Signer Iretomiwa.Otuyelu@fortworthtexas.gov entered name at signing as Iretomiwa Otuyelu
2023-06-29 - 6:42:44 PM GMT- IP address: 138.229.172.23
Document e-signed by Iretomiwa Otuyelu (Iretomiwa.Otuyelu@fortworthtexas.gov)
Signature Date: 2023-06-29 - 6:42:46 PM GMT - Time Source: server- IP address: 138.229.172.23
Email viewed by ann.estes@fortworthtexas.gov
2023-06-29 - 6:45:02 PM GMT- IP address: 204.10.90.100
Signer ann.estes@fortworthtexas.gov entered name at signing as Ann Estes
2023-06-29 - 6:47:58 PM GMT- IP address: 204.10.90.100
Form filled by Ann Estes (ann.estes@fortworthtexas.gov)
Form filling Date: 2023-06-29 - 6:48:00 PM GMT - Time Source: server- IP address: 204.10.90.100
Email viewed by travis.strang@fortworthtexas.gov
2023-07-05 - 1:54:53 PM GMT- IP address: 166.205.54.12
Signer travis.strang@fortworthtexas.gov entered name at signing as Travis Strang
2023-07-05 - 1:56:22 PM GMT- IP address: 107.77.196.55
Document e-signed by Travis Strang (travis.strang@fortworthtexas.gov)
Signature Date: 2023-07-05 - 1:56:24 PM GMT - Time Source: server- IP address: 107.77.196.55
Document emailed to omar.elbagalati@fortworthtexas.gov for signature
2023-07-05 - 1:56:26 PM GMT
Email viewed by omar.elbagalati@fortworthtexas.gov
2023-07-05 - 2:11:54 PM GMT- IP address: 172.59.233.117
Signer omar.elbagalati@fortworthtexas.gov entered name at signing as Omar Elbagalati
2023-07-05 - 2:22:09 PM GMT- IP address: 172.59.233.117
Document e-signed by Omar Elbagalati (omar.elbagalati@fortworthtexas.gov)
Signature Date: 2023-07-05 - 2:22:11 PM GMT - Time Source: server- IP address: 172.59.233.117
Document emailed to Mary.Hanna@fortworthtexas.gov for signature
2023-07-05 - 2:22:13 PM GMT
Email viewed by Mary.Hanna@fortworthtexas.gov
2023-07-06 - 4:20:55 PM GMT- IP address: 204.10.90.100
Signer Mary.Hanna@fortworthtexas.gov entered name at signing as Mary Hanna
2023-07-06 - 4:23:52 PM GMT- IP address: 204.10.90.100
FORT WORTHS 1 Powered'y
Adobe
Acrobat Sign
Document e-signed by Mary Hanna (Mary.Hanna@fortworthtexas.gov)
Signature Date: 2023-07-06 - 4:23:54 PM GMT - Time Source: server- IP address: 204.10.90.100
Document emailed to patricia.wadsack@fortworthtexas.gov for signature
2023-07-06 - 4:23:56 PM GMT
Email viewed by patricia.wadsack@fortworthtexas.gov
2023-07-06 - 9:53:01 PM GMT- IP address: 204.10.90.100
Signer patricia.wadsack@fortworthtexas.gov entered name at signing as Patricia L. Wadsack
2023-07-06 - 9:54:44 PM GMT- IP address: 204.10.90.100
Document e-signed by Patricia L. Wadsack (patricia.wadsack@fortworthtexas.gov)
Signature Date: 2023-07-06 - 9:54:46 PM GMT - Time Source: server- IP address: 204.10.90.100
Document emailed to Lauren.Prieur@fortworthtexas.gov for signature
2023-07-06 - 9:54:48 PM GMT
Email viewed by Lauren.Prieur@fortworthtexas.gov
2023-07-07 - 3:14:45 PM GMT- IP address: 108.209.194.42
Signer Lauren.Prieur@fortworthtexas.gov entered name at signing as Lauren Prieur
2023-07-07 - 3:15:14 PM GMT- IP address: 108.209.194.42
Document e-signed by Lauren Prieur (Lauren.Prieur@fortworthtexas.gov)
Signature Date: 2023-07-07 - 3:15:16 PM GMT - Time Source: server- IP address: 108.209.194.42
Document emailed to Priscilla.Ramirez@fortworthtexas.gov for approval
2023-07-07 - 3:15:18 PM GMT
Email viewed by Priscilla.Ramirez@fortworthtexas.gov
2023-07-07 - 3:29:29 PM GMT- IP address: 174.207.105.142
Signer Priscilla.Ramirez@fortworthtexas.gov entered name at signing as Priscilla Ramirez
2023-07-07 - 3:29:44 PM GMT- IP address: 174.207.105.142
Document approved by Priscilla Ramirez (Priscilla.Ramirez@fortworthtexas.gov)
Approval Date: 2023-07-07 - 3:29:46 PM GMT - Time Source: server- IP address: 174.207.105.142
Document emailed to Douglas.Black@fortworthtexas.gov for signature
2023-07-07 - 3:29:48 PM GMT
Email viewed by Douglas.Black@fortworthtexas.gov
2023-07-07 - 9:55:23 PM GMT- IP address: 204.10.90.100
Signer Douglas.Black@fortworthtexas.gov entered name at signing as DBlack
2023-07-07 - 9:56:20 PM GMT- IP address: 204.10.90.100
FORT WORTHS 1 Powered'y
Adobe
Acrobat Sign
Document e-signed by DBlack (Douglas.Black@fortworthtexas.gov)
Signature Date: 2023-07-07 - 9:56:22 PM GMT - Time Source: server- IP address: 204.10.90.100
Document emailed to William.Johnson@fortworthtexas.gov for signature
2023-07-07 - 9:56:23 PM GMT
Email viewed by William.Johnson@fortworthtexas.gov
2023-07-10 - 7:53:49 PM GMT- IP address: 204.10.90.100
Signer William.Johnson@fortworthtexas.gov entered name at signing as William Johnson
2023-07-10 - 7:54:12 PM GMT- IP address: 204.10.90.100
Document e-signed by William Johnson (William.Johnson@fortworthtexas.gov)
Signature Date: 2023-07-10 - 7:54:14 PM GMT - Time Source: server- IP address: 204.10.90.100
FORT WORTHS 1 Powered'y
Adobe
Acrobat Sign
FORTWORTH
Routing and Transmittal Slip
Transportation and Public Works
Department
DOCUMENT TITLE: 2023 CONCRETE RESTORATION CONTRACT 2
M&C; 23-0588 CPN; 104179 CSO # 58704 DOC# 1
Date:
To: Name Department Initials Date Out
1
Ann Estes
BSP
_�&-
Jun 29, 2023
2
Maqsood Khan
Vendor
Jun 29, 2023
3
Travis Strang
TPW
TI
Jul 5, 2023
4
Iretomiwa Otuyelu
TPW
1115
Jun 29, 2023
5
Omar Elbagalati
TPW
7 -
Jul 5, 2023
6
Mary Hanna
TPW
m�
Jul 6, 2023
6
Patricia Wadsack
TPW
P1_W
Jul 6, 2023
7
Lauren Prieur
TPW
Jul 7, 2023
7
Doug Black
Legal
dw`
Jul 7, 2023
8
William Johnson
CMO
w,
Jul 10, 2023
9
Janette Goodall
CSO
Jul 13, 2023
10
TPW Contracts
TPW
CC: Program Manager, Sr.
CPO, TPW BSAP Recon Team,
TPW Records Room, TPW Contracts
-Bus Sppt: Ann Estes;
-Prg Mgr: Omar Elbagalati;
-Sr. CPO:
Mary Hanna.
DOCUMENTS FOR CITY MANAGER'S SIGNTURE: All documents received from any and all City
Departments requesting City Manager's signature for approval MUST BE ROUTED TO THE
APPROPRIATE ACM for approval first. Once the ACM has signed the routing slip, David will review
and take the next steps.
NEEDS TO BE NOTARIZED: ❑ Yes XNo
RUSH : ❑ Yes X No SAME DAY: ❑ Yes X No NEXT DAY: ❑ Yes X No
ROUTING TO CSO: ❑ Yes ❑ No
Action Reauired:
❑ As Requested ❑ Attach Signature, Initial and Notary Tabs
❑ For Your Information
X Signature/Routing and or Recording
❑ Comment
❑ File
Return to: Please notify TPWContracts(afortworthtexas.gov for pickup when complete. Call ext. 7233 or
ext. 8363. Thank you!