FC3R-c WORTH City of Fort Worth
Change Order Request
Project Name: Clear Fork Force Main J Cily Sec No.: 1 58320
Project No.(s):l 560211070043011780 DOE No. I N/ A I City Proj. No.: 1 100996-2
Project Description- Approximately 14,330 linear feel of 36•inch sanitary sewer force main piping to convey wastewater from proposed Clear Fork Lift Station to
downstream discharge point.
Contractor: S.J. Louis Construction of Texas, Ltd Change Order # 1 Date: 1 6/2112023
City Project Mgr. Liam Conlon City Inspector: Carmen Drake
Phone Number: 817-392-6824 Phone Number: 682-432-5486
Dept. Sewer Totals Contract Time
(Calendar days)
Original Contract Amount $29,829,815.71 $29,829,815.71 400
Extras to Dale
Credits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Date $29,829,815.71 $29,829 815.71 400
Amount of Proposed Change Order $0.00 $0.6 020
Revised Contract Amount $29,829.815.71 $29,829,815.71 420;
Original Funds Available for Change Orders $298,298.00 $298,298.00
Remaining Funds Available for this CO $298,298.00 $298,298.00
Additional Funding (if necessary)
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT
MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST + 25116) $37,287,269.64
JUSTIFICATION (REASONS) FOR CHANGE ORDER
Change Order No. 1 provides for the following:
Revisions to various project vaults with dual 8-Inch combination air release valves and gate valves to accomodate
actual field conditions that were encountered during construction.
8-Inch water line lowering to avoid conflict with 8-Inch ARV piping.
Lowering of the force main beyond the design depth to accomodate the revised vault depth.
Staff concu rs with the contractors request for 20 additional calendar days on the change order.
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in
full (both time and money) for all costs arising out of, or incidental to, the above Change Order,
I Contractor's Company Name
Contractor Name
gnature
Date
ruction j S.J,Louis Constof Texas, Ltd I
Adam Lunsford
I Phtraclor
-WA�
7/Io1Z3
,f'nseector
Date
Project Manager
, Date
`61rector (W�r-0ept)
Date
Cohstruction,Supervisor (Water)
Date
I Laura R Wilson
Jul 13, 2023
�r--
6
Senior Assistant City Attorney
Dale
Assistant City Manager
Dale
I
Jut 19, 2023
Daila BcaWL�(O f
Jut 20, 2023
Council Action (If
Required)
M&C Number nla
M&C Date Approved nla
i
Fo R r WC-) R"r H City of Fort Worth
W ' Change Order Additions
Project Name Clear Fork Force Main E City Sec No.: 58320
Project No.(s): 56021 10700430 11780 DOE No.1 N/A City Proj. No.: 100996-2
Project Approximately 14,330 linear feel of 36-inch sanitary sewer force main piping to convey wastewater from proposed Clear `
Description Fork Lift Station to downstream discharge point. I
Contractor S.J. Louis Construction of Texas, Ltd I Change Order: [--T—] Date: 1 6/21/2023
City Project Mgr, j Liam Conlon l City Inspector I Carmen Drake
ADDITIONS
I I Em
DES',;Ri1PI ION
DEPT
Qt�( Unit
Unit Cost
Total
61
Post -CCTV Inspection
Sewer
876.00 LF
$3.00
$2,628.00
62
Modified 36" Gale Valve wl Vault @ STA 89+85
Sewer
1.00 LS
$14,000.00
$14,000.00
63
Modified Offset Dual 8" Sewer Air Release Valve & Vault @ STA 22+13
Sewer
1.00 LS
$150,000.00
$150,000.00
64
Modified Dual 8" Sewer Air Release Valve & Vault @ STA 57+95
Sewer
1.00 LS
$106,000.00
$106,000.00
65
Modified Offset Dual 8" Sewer Air Release Valve & Vault @ STA 86+81
Sewer
1.00 LS
$150,000.00
$150,000.00
66
Modified Dual 8" Sewer Air Release Valve & Vault @ STA 139+60
Sewer
1.00 LS
$106,000.00
$106,000.00
67
36" HDPE Force Main Extra Depth STA 18+16 to 18+88 and additional bend, Sewer
1.00 LS
$49,000.00
$49,000.00
68
36" HDPE Force Main Extra Depth STA 86+10 to 92+06
Sewer
1.00 LS
$48,000.00
$48,000.00
69
8" Waterline Lowering
Sewer
1.00 LS
$23,000.00
$23,000.00
Sewer $648,628.00
Page 2 of 4 Additions Sub Total I$648,628.00
FCi RT' W" RT H City of Fort Worth
MW I Change Order Deletions
Project Name Clear Fork Force Main City Sec No.: k MM
Project No.(s): 56021 1070043011780. DOE No. N/A City Proj. No.: 100996-2
Project Description I Approximately 14,330 linear feet of 36-inch sanitary sewer force main piping to convey wastewater from proposed
Clear Fork Lift Station to downstream discharge point,
Contractor I S.J. Louis Construction of Texas, Ltd Change Order: 1� Date l 6/21/20231
City Project Mgr. I Liam Conlon City Inspector: I Carmen Drake
ITEM DESCRIPTION
37 9999,0010 Dual 8" Sewer Air Release Valve & Vault
38 0241.2021 Remove 24" Sewer Line
39 3123.0101 Unclassified Excavation by Plan
40 3305.0202 Imported Embed men UBackfil1, CSS
60 9999.0018 Construction Allowance
DELETIONS
DEPT
Qty Unit
Unit Cost Total
Sewer
4.00 EA
$101,000.00 $404,000.00
Sewer
381.00 LF
$64.00 $24,384.00
Sewer
1,092.00 CY
$35.00 $38,220.00
Sewer
1,092.00 CY
$110.00 $120,120.00
Sewer
0.30952 LS
$200,000.00 $61,904.00
Page 3 of 4
Sewer $648,628.00
(Deletions Sub Total $648,628.00
IVIIWBE Breakdown for this Change Order
MWBE Sub Type of Service Amount for this CO
Total $0.00
Previous Change Orders
co It DATE AMOUNT
Total $0.00
Page 4 of 4
6/21/2023
Clear Fork Force Main
CPN 100996-2
Change Order 1 Notes
Staff has reviewed the requested prices and considers them to be fair and reasonable.
.Contract Comaliance Manaeer
By signing I acknowledge that I am the person responsible
for the monitoring and administration of this contract, including
ensuring all performance and reporting requirements.
Signature
Liam Conlon
Name of Employee
Project Manager
Title