HomeMy WebLinkAboutContract 58012-A1CSC No. 58012-A1 AMENDMENT No . 1 TO CITY SECRETARY CONTRACT No. 58012 WHEREAS, the City of Fort Worth (CITY) and Garver, LLC, (ENGINEER) made and entered into City Secretary Contract No. 58012, (the CONTRACT) which was administratively authorized on the 21st day of August, 2022 in the amount of $67,265.00; and WHEREAS, the CONTRACT involves engineering services for the following project: Northside III Elevated Storage Tank; WHEREAS, it has become necessary to execute Amendment No. 1 to the CONTRACT to include an increased scope of work and revised fee. NOW THEREFORE , CITY and ENGINEER, acting herein by and through their duly authorized representatives, enter into the following agreement, which amends the CONTRACT: 1. Article I of the CONTRACT is amended to include the additional engineering services specified in proposal attached hereto and incorporated herein. The cost to City for the additional design services to be performed by Engineer totals $349,055.00. 2. Article II of the CONTRACT is amended to provide for an increase in the fee to be paid to Engineer for all work and services performed under the Contract, as amended, so that the total fee paid by the City for all work and services shall be an amount of $ 416, 320. 00 . 3. All other provisions of the Contract, which are not expressly amended herein, shall remain in full force and effect. OFFICIAL RECORD CITY SECRETARY FT. WORTH, TX Prof Services Agreement Amendment Template Revision Date: November 23, 2021 Northside III EST Page 1 of 2 [CPN 1042901 EXECUTED and EFFECTIVE as of the date subscribed by the City's designated Assistant City Manager. APPROVED: City of Fort Worth Dana Burghd off (JuI Y4, 2023 10�11 CDT) Dana Burghdoff Assistant City Manager DATE: J u l 24, 2023 Laura F W ds- (Jul 10, 2023 09 41 CDT) Laura Wilson, P.E. Acting Director, Water Department Contract Compliance Manager: ENGINEER Garver, LLC Daniel N. Olson, P.E. Vice President DATE: 07/07/2023 By signing, I acknowledge that I am the person responsible for the monitoring and administration of this contract, including ensuring all performance and reporting requirements. Pra tuna Poudyal, P.E. Senior Professional Engineer APPROVED AS TO FORM AND LEGALITY: A I DBlack (Jul 24, 2023 09:31 CDT) Douglas W. Black Senior Assistant City Attorney ATTEST: oar FORT as �� Fo-�000000�LOd o % pro o- a�o oz Jannette S. Goodall 0�� 000 0 * E City Secretary �aa i,000000 ap ��naaab� Prof Services Agreement Amendment Template Revision Date: November 23, 2021 Page 2 of 2 M&C : 23-0536 Date: 6/27/2023 Form 1295: 2023-1027077 OFFICIAL RECORD CITY SECRETARY FT. WORTH, TX Northside III EST (CPN 1042901 500 West 71h Street Suite 803 Fort Worth, TX 76102 TEL 817.740.9575 www.GarverUSA.com May 23, 2023 Ms. Pratima Poudyal City of Fort Worth Water Department 311 W 10th Street Fort Worth, TX 76102 Re: Siting Study for Northside III Elevated Storage Tank- Amendment No. 1 Dear Ms. Poudyal: Enclosed with this letter is the request for Amendment No. 1 for the above referenced project. On December 21, 2023, the City provided correspondence directing the addition of final design services to develop construction plans and specifications for the Northside III Elevated Storage Tank. The proposed final design effort is detailed in Attachment A — Design Services and Attachment B - Level of Effort Supplement. Garver proposes to incorporate developer provided survey work as part of the project that overlaps the proposed elevated storage tank site. Funds from the current contract have previously been re - programed for three geotechnical bores. It has been identified that two additional geotechnical bores will be required to satisfy the foundation design for the elevated storage tank and the two additional bores are included in the proposed amendment number #1 bringing the total anticipated geotechnical bore count up to five for the project. Construction phase services shown are consistent with the City standard scope of services language and represent City led construction inspection and administration. Elevated Storage Tanks are unique construction projects and Garver has elevated tank inspectors and can provide this service upon request if the City prefers to outsource these services. Garver has identified conceptual level OPCC estimates for 2 MG to 2.5 MG elevated storage tanks and these costs range from approximately $8.7 million to $13.2 million. Ms. Poudyal 05/09/2023 Page 2 of 2 The proposed fee and increase to the Contract is detailed in the table below: Original Contract Amount $67,265.00 Additional Amount Requested (Amendment No. 1) $349,055.00 Proposed Contract Total Amount $416,320.00 Please call me if you have any questions. Sincerely, GARVER Derek T. Schwan ke, P. E. Senior Project Manager Attachments: Attachment A - Design Services Attachment B - Level of Effort Supplement Attachment C - 2.5 MG Pre -Design OPCC ATTACHMENTA DESIGN SERVICES FOR NORTHSIDE III EST FINAL DESIGN CITY PROJECT NO.:104290 ATTACHMENT A Scope for Enaineerina Design Related Services for Water Improvements DESIGN SERVICES FOR NORTHSIDE III EST FINAL DESIGN CITY PROJECT NO.: 104290 The scope set forth herein defines the work to be performed by the ENGINEER in completing the project. Both the CITY and ENGINEER have attempted to clearly define the work to be performed and address the needs of the Project. WORK TO BE PERFORMED Task 1. Design Management Tab- 2. GGnGoptual Dasrq_n Task 3. Preliminary Design Task 4. Final Design Task 5. Bid Phase Services Task 6. Construction Phase Services Task 7. ROW/Easement Services Task 8. Survey and Subsurface Utility Engineering Services Task 9. Plan Submittal Checklists TASK 1. DESIGN MANAGEMENT. ENGINEER shall ensure efficient and effective use of ENGINEER's and CITY's time and resources. ENGINEER shall manage change, ■ communicate effectively, ■ coordinate internally and externally as needed, and ■ proactively address issues with the CITY's Project Manager and others as necessary to make progress on the work. 1.1. Managing the Team • Lead, manage and direct design team activities • Ensure quality control is practiced in performance of the work • Communicate internally among team members • Task and allocate team resources 1.2. Communications and Reporting City of Fort Worth, Texas Attachment A PMO Release Date: 07.23.2012 Page 1 of 19 ATTACHMENT A DESIGN SERVICES FOR NORTHSIDE III EST FINAL DESIGN CITY PROJECT NO.: 104290 • Attend a pre -design project kickoff/chartering meeting with CITY staff to confirm and clarify scope, understand CITY objectives, and ensure economical and functional designs that meet CITY requirements • Conduct in person review meetings with the CITY at the end of each design phase • Prepare invoices and submit monthly in the format requested by the CITY. • Prepare and submit monthly progress reports in the format provided by the Water Department. • Prepare and submit baseline Project Schedule initially, and Project Schedule updates with a schedule narrative monthly, as required in Attachment D to this Standard Agreement and according to the City of Fort Worth's Schedule Guidance Document. • Complete Monthly M/WBE Report Form and Final Summary Payment Report Form at the end of the project • Coordinate with other agencies and entities as necessary for the design of the proposed infrastructure, and provide and obtain information needed to prepare the design • With respect to coordination with permitting authorities, ENGINEER shall communicate with permitting authorities such that their regulatory requirements are appropriately reflected in the designs. ENGINEER shall work with regulatory authorities to obtain approval of the designs, and make changes necessary to meet their requirements, as part of the design scope. • Personnel and Vehicle Identification: When conducting site visits to the project location, the ENGINEER or any of its sub -consultants shall carry readily visible information identifying the name of the company and the company representative. ASSUMPTIONS • 18 MANBE reports will be prepared (6 monthly invoices during design and one every other month during the 24-month construction period) • 6 meetings with city staff • 2 — Progress Check -ins (anticipated to be virtual bi-monthly meetings) • Pre -Design Kickoff (In person) • 60% Workshop (In person) • 90% Workshop (In person) • 100% Workshop (In person) • 18 monthly water department progress reports will be prepared (6 monthly invoices during design and one every other month during the 24-month construction period) • 18 monthly project schedule updates will be prepared (6 monthly invoices during design and one every other month during the 24-month construction period) City of Fort Worth, Texas Attachment A PMO Release Date: 08.1.2014 Page 2 of 19 ATTACHMENTA DESIGN SERVICES FOR NORTHSIDE III EST FINAL DESIGN CITY PROJECT NO.: 104290 DELIVERABLES A. Meeting summaries with action items B. Monthly invoices C. Monthly progress reports D. Baseline design schedule E. Monthly schedule updates with schedule narrative describing any current or anticipated schedule changes F. Monthly M/WBE Report Form and Final Summary Payment Report Form G. Plan Submittal Checklists (See Task 9) TASK 2. CONCEPTUAL DESIGN (30 PERCENT). Th,-,--�e Ge eo teal Design chiCll I►9 oAmittsd to CITY per the approved Drnion+ SGhedule. The purpese of the GenGeptual design is for the ENGINEER to * Stud the nrnion , Identify and develop alternatives that enhanGe the system, PFesent (through the defined deliverables) these alternatives to the CITY * ReGemmend the al}erno}mica th& ou oes f, illy addresses the design problem, and t Obtain the CITY' endorsement of this nonnep} €NG NEER will develop the GenGeptual design of the infraStFUGWre as felle 2.1. Data 901leGtien in addutmeR te data obtained from the CITY, ENaINEER will reseaFGh proposed . . nent6 in GOnj6lnGt'en with any etheF plaRned future,, 1 [jai w v � I i — its that may infl, ,enoe the proiec.t- • T---roc ENGINEER Will -Alsn- Eld-entify and seek to obtaiR data for existing Genditions utilities,that may impaGt the PFOjeGt inGluding but not Ii.m.0ted to; or Plano, and preperty o orohip Do a lailable from +he Tax Assessor's office_ meetiRgS with affeGted property i r d businesses as necessary tE) develop sewer re routing plans • The ENGINEER shall v4 i++he praise+ si+e onrt obtain the metor numbers and sizes 2.2. G City of Fort Worth, Texas Attachment A PMO Release Date: 08.1.2014 Page 3 of 19 ATTACHMENT A DESIGN SERVICES FOR NORTHSIDE III EST FINAL DESIGN CITY PROJECT NO.: 104290 •--ENGINEER shall advwse the CITY ef test berings and otlior oub'3urfa e investigatieRs that may be Reeded for the PFE)jeGt. if the CITY determiReS that i ir•h boringor investigations are needed then the ENGINEER shall we* -with the JTY and !MTV's oeoteohnir.ol ^onoultant t The r•o St of 1 inh testing will he paid for by the CITY +ems+regram. T,� .,.,........w.,., ..,......� ..... __ �_._ ._. _, _.._ CITY. 2.Z. Firs I ine Rer•onneotion 2.1. The CORD ptusl Design PaGka^o ohall incAude the fellaw+rig Cover Sheet Graphic-Qj(hkito and wrier vv itten s:ammary of I+ernr++i„e le iron nnnr en+o nnnc ilJere r! strengths and weaknesses of eaGh, and the Fationale for seleGting the recvormrrrmrrcndca design r• rv�+. •—Proposed pha�ng of any water an sanitary sewer worR that io insl� idle,- in +"is narrative form. .. DOG imentation of Lev design rteoisions. • Eotimat s of nrnhr+hle r•nnotF potion OOSt. ASSUMPTIONS n Geotenhnin.+l borings — evneoted for thio pr*Gt-. 0 desigR) will be delivered.. Deport @hall lle-letteG sized and r•vmh bound with s nl�+r placr—G stic n�v�r i i Drawing 411 he s4ze fold ets. bound in the report 9 DVVF f0leS Greated frorn design CAD drawings will be upleaded to the designated prejec-tf or in ✓izz-cm 0 EN INFER shall prepaFe the rneetiRg minutes of the CORGept Review meeting and revise the report if needed •--€N I6 IEEP ohall not pregeed ,^,if" R liminary Design aGtivitnes without obtaining avr4on approval by the CITY of the Gnnroptual Design PaGkarre DELIVERABLES A. Go nsoptNal Design Der•Loyv City of Fort Worth, Texas Attachment A PMO Release Date: 08.1.2014 Page 4 of 19 ATTACHMENT A DESIGN SERVICES FOR NORTHSIDE III EST FINAL DESIGN CITY PROJECT NO.: 104290 TASK 3. PRELIMINARY DESIGN (60 PERCENT). Preliminary plans and specifications shall be submitted to CITY per the approved Project Schedule. ENGINEER will develop the preliminary design of the infrastructure as follows. 3.1. Development of Preliminary Design Drawings and Specifications shall include the following: • Cover Sheet A Proiect Control Sheet, showing all Control Points, used or set while gathering data. Generally on a scale of not less than 1:400. The following information shall be indicated for each Control Point: Identified (existing City Monument #8901, PK Nail, 5/8" Iron Rod); X, Y and Z Coordinates, in an identified coordinate system, and a referred bearing base. Z coordinate on City Datum only; descriptive location (i.e. set in the centerline of the inlet in the South curb line of North Side Drive at the East end of radius at the Southeast corner of North Side Drive and North Main Street). • Overall oroiect easement lavout sheet(s) with property owner information. • Overall project water lavout sheets. The water layout sheet shall identify the proposed water main improvement/ existing water mains in the vicinity and all water appurtenances along with pressure plane boundaries, water tanks, pump stations, valves, and fire hydrants. 0 Overall r onnitsw sewer abandonment shoo+ • Coordinates on all P.C.'s, P.T.'s, P.I.'s, manholes, valves, mainline fittings, etc., in the same coordinate system as the Control Points. • Bench marks per 1,000 ft of plan/profile sheet — two or more. Bearings given on all proposed centerlines, or baselines. • Station equations relating utilities to paving, when appropriate. • Plan and profile sheets which show the following: proposed water and/or sanitary sewer plan/profile and recommended pipe size, fire hydrants, water service lines and meter boxes, gate valves, isolation valves, manholes, existing meter numbers and sizes that are to be replaced, existing sample locations, existing fire line locations, existing utilities and utility easements, and all pertinent information needed to construct the project. Legal description (Lot Nos., Block Nos., and Addition Names) along with property ownership shall be provided on the plan view. The ENGINEER will design the 24-inch waterline to the property boundary edge. • The ENGINEER shall make provisions for reconnecting all identifiable water and/or wastewater service lines which connect directly to any main being replaced, including replacement of existing service lines within City right-of-way or utility easement. When the existing alignment of a water and sanitary sewer main or lateral is changed, provisions will be made in the final plans and/or specifications City of Fort Worth, Texas Attachment A PMO Release Date: 08.1.2014 Page 5 of 19 ATTACHMENTA DESIGN SERVICES FOR NORTHSIDE III EST FINAL DESIGN CITY PROJECT NO.: 104290 by the ENGINEER to relocate all service lines which are connected to the existing main and connect said service lines to the relocated main. The following shall be applic;able at all lerations where it is --essa-ry to re!eE;ate or rereute the existing private sanitary sewer service line due to the abandonment r realignment of the existing publiG sanitary or main: The GITv c hall furnish the ENGINEER with anJample format of hew the sewer service lino design SUFvey, if a Fed Gan be inserted threugh the GleaRE)61t to the bottern of the serv;ee-4+ne, the serViGe line prier to advertising the PFGjeGt for bid. if the SeFViGe flow li Gn Gannot be obtained during design -survey, the E INEER a`lall delay The des+gR of the sewer GerViGe lino until after Level Sijbour-IaGeJJtP4 `n`Yine rririg- UJE invest4at+on hco been ern-perforrmed).The Leevel A SUE ,e •ll la p ermerl• !1\ hii�ho E",QNE P. If prior to bidding if the CITY de}ermines that it i needed { r,� � or aatiofa of the design; or (3) by the GontraGtor after the of hoo been bid, by-mz,nS Of 81 bid item to that effeGt. in all optiens, the ENGINEER shall prGpGse-approp4ate-de- infer.m.-;;tmon Gf the sewer GeNiGe line. The ENGINEER shall use this infGFMa4e� provide the design for the sanitary sewer seFvic;e line te be rerouted or relOGated. •-P-revfds map dhowing IGGation of new manhole GenstrUGtffiGn at the end of existing sewer segments, 99 degree bends, ar tee Gonnecfions. Site survey er speGificu design plano for manhole nnnStFUGtien is net 'nnluderl «� i, �G,�ia�G co part of the SGepe. The to ohcll opec-i€y that it io the Gentra esponoibility-to GOerrimarfe utility Irn te4n"on , eon. manhole GitStYtGfi 7tt- • The ENGINEER will prepare standard and special detail sheets for water line installation and sewer rehabilitation or replacement that are not already included in the D-section of the CITY's specifications. These may included connection details between various parts of the project, tunneling details, boring and jacking details, waterline relocations, details unique to the construction of the project, trenchless details, and special service lateral reconnections. • The ENGINEER will develop an access layout and details to include a gravel road to provide access to the tank while the subdivision is under construction. The access road will connect to an existing gravel road near the tank site that has access to SH 114. • The ENGINEERwill design an overflow line and discharge dechlorination point that allows the tank to be flushed during maintenance operations. • Site Plan • Yard Piping Plan • Piping Profile • Water line Details • Grading Plan (includes iSWM Construction Plan) City of Fort Worth, Texas Attachment A PMO Release Date: 08.1.2014 Page 6 of 19 ATTACHMENTA DESIGN SERVICES FOR NORTHSIDE III EST FINAL DESIGN CITY PROJECT NO.: 104290 • Erosion Control Plan • Paving Plan • Tank Plan Sheets (Upper and Lower levels) • Tank Details • Tank Elevation and Sections • Electric Site Layout • Electric Single -Line Diagram (One Sheet) • Electric Plan —Tank (Upper and Lower Levels) • Electric Schematics • Lighting Floor Plan • Electrical Details • 18 Total Estimated Plan Sheets 3.2. Geotechnical Investigation • Soil investigations, including field and laboratory tests, borings, related engineering analysis and recommendations for determining soil conditions performed as part of the siting study task will be analyzed to be incorporated into the design. In addition to the above investigations, 2 additional boring and appropriate field and laboratory analysis will be performed (total of 5 borings, 4 equally spaced along the edge of the tank support and one in the center) to support the Contractor's tank structural design. 3.3. Constructability Review • Prior to the 60 percent review meeting with the CITY, the ENGINEER shall schedule and attend a project site visit with the CITY Project Manager and Construction personnel to walk the project. The ENGINEER shall summarize the CITY's comments from the field visit and submit this information to the CITY in writing. 3.4. Utility Clearance • The ENGINEER will consult with the CITY's Transportation and Public Works Department, Water Department, and other CITY departments, public utilities, private utilities, private utilities and government agencies to determine the approximate location of above and underground utilities, and other facilities (current and future) that have an impact or influence on the project. ENGINEER will design CITY facilities to avoid or minimize conflicts with existing utilities, and where known and possible consider potential future utilities in designs. • The ENGINEER shall upload individual DWF files for each plan sheet of the approved preliminary plan set to the designated project folder in Buzzsaw for forwarding to all utility companies which have facilities within the limits of the City of Fort Worth, Texas Attachment A PMO Release Date: 08.1.2014 Page 7 of 19 ATTACHMENT DESIGN SERVICES FOR NORTHSIDE III EST FINAL DESIGN CITY PROJECT NO.: 104290 project. The DWF files should be created directly from the CAD files as opposed to PDF files. 3.5. Traff iG Control Plan •Develop a trcff+o-Gs of plan utilizing posted as "T„niGals" en }he JTY'o ✓uzzoa\vA*eb-sit&-. Tho typ+sal-s- Reed -not -be sealed inrdiii`di+lli if in�+ �� in�rr-trhre sealed oon}rno} &G iman}� • DevelopoupplameRtal traff OG Gen}rol rdravvingc as needed fer review and nnnrnrol by tho Traffi .Transportation and P blig Werks Department. These drawingo ohall be sealed by a nrefe sional engineer registered in }ho State of Texas ASSUMPTIONS • 1 public meeting(s) will be conducted or attended during the preliminary design phase. • 5 borings at a maximum depth of 70 feet or 40 feet into the unweathered bedrock, whichever is less will be evaluated (field investigations performed under another task). • Traffic Control "Typicals" will be utilized to the extent possible. It is assumed an additional 0 project specific traffic control sheets will be developed. • 3 sets of 11 x 17 size plans will be delivered for the Constructability Review. • 3 sets of 11 x 17 size plans will be delivered for the Preliminary Design (60% design). • 3 sets of technical specification index will be delivered for the Preliminary Design (60% design). • DWF files created from design CAD drawings will be uploaded to the designated project folder in Buzzsaw. • The CITY's front end and technical specifications will be used. The ENGINEER shall supplement the technical specifications if needed. • 3 sets of 11 x 17 size drawings will be delivered for Utility Clearance. • ENGINEER shall not proceed with Final Design activities without written approval by the CITY of the Preliminary Design plans. DELIVERABLES A. Preliminary Design drawings and technical specification index (Assume 14 drawing sheets plus details) B. Utility Clearance drawings C. City of Fort Worth, Texas Attachment A PMO Release Date: 08.1.2014 Page 8 of 19 ATTACHMENTA DESIGN SERVICES FOR NORTHSIDE III EST FINAL DESIGN CITY PROJECT NO.: 104290 D. Storm Water Pollution Prevention Plan E. Estimates of probable construction cost F. Data Base listing names and addresses of residents and businesses affected by the project. TASK 4. FINAL DESIGN (90 PERCENT) AND FINAL CONSTRUCTION DOCUMENTS (100 PERCENT). Upon approval of the Preliminary plans, ENGINEER will prepare construction plans as follows: For projects that disturb an area greater than one (1) acre, the Contractor will be responsible for preparing and submitting the Storm Water Pollution Prevention Plan (SWPPP) with appropriate regulatory agencies. The Engineer will prepare the iSWM Construction Plan according to the current CITY iSWM Criteria Manual for Site Development and Construction which will be incorporated into the SWPPP by the contractor. • Draft Final plans (90%) and specifications shall be submitted to CITY per the approved Project Schedule. • Following a 90% construction plan review meeting with the CITY, the ENGINEER shall submit Construction Documents (100%) to the CITY per the approved Project Schedule. Each plan sheet shall be stamped, dated, and signed by the ENGINEER registered in State of Texas. • The ENGINEER shall submit a final design estimate of probable construction cost with both the 90% and 100% design packages. This estimate shall use ONLY standard CITY bid items. ASSUMPTIONS • 3 sets of 11 x 17 size drawings and 3 specifications will be delivered for the 90% Design package. • A DWF file for the 90% Design will be created from design CAD drawings and will be uploaded to the project folder in Buzzsaw. • 3 sets of 11 x 17 size drawings and 3 specifications will be delivered for the 100% Design package. • A DWF file for the 100% Design will be created from design CAD drawings and will be uploaded to the project folder in Buzzsaw. • Final design plan set estimated to include the following sheets: o Cover Sheet o Notes 1 — Civil o Notes 2 — Process o Notes 3 — Electrical o Project Control o Project Easement Layout City of Fort Worth, Texas Attachment A PMO Release Date: 08.1.2014 Page 9 of 19 ATTACHMENTA DESIGN SERVICES FOR NORTHSIDE III EST FINAL DESIGN CITY PROJECT NO.: 104290 o Project Water Layout o Piping Plan & Profile Sheet (1 total) o Grading Plan (includes iSWM Construction Plan) o Paving Plan o Temporary Access Road Plan Sheet o Tank Plan (upper) o Tank Plan (lower) o Tank Elevation & Sections o Electric Site Plan o Electric Single Line Diagram (One Sheet) o Electric Plan (Tank - Upper) o Electric Plan (Tank - Lower) o City of Fort Worth Standard Details List DELIVERABLES A. 90% construction plans and specifications. B. 100% construction plans and specifications. C. Detailed estimates of probable construction costs including summaries of bid items and quantities using the CITY's standard bid items and format. D. Original cover mylar for the signatures of authorized CITY officials. TASK 5. BID PHASE SERVICES. ENGINEER will support the bid phase of the project as follows. 5.1. Bid Support • The ENGINEER shall upload all plans and contract documents onto Buzzsaw for access to potential bidders. • Contract documents shall be uploaded in a .xIs file. • Unit Price Proposal documents are to be created utilizing CFW Bidtools only and combined in a specified spreadsheet workbook, Bid Proposal Worksheet Template, and will be populated and configured so that all pages are complete and the Summary Worksheet(s) in the workbook detail and automatically summarize the totals from the inserted Unit Price Proposal document worksheets. • Plan Sets are to be uploaded to Buzzsaw in two formats, .pdf and .dwf files. The .pdf will consist of one file of the entire plan set. The AM will consist of individual files, one for each plan sheet, and will be numbered and named in a manner similar to that of the plan set index. • The ENGINEER shall sell contract documents and maintain a plan holders list on Buzzsaw from documents sold and from Contractor's uploaded Plan Holder Registrations in Buzzsaw. • The ENGINEER will develop and implement procedures for receiving and answering bidders' questions and requests for additional information. The City of Fort Worth, Texas Attachment A PMO Release Date: 08.1.2014 Page 10 of 19 ATTACHMENT A DESIGN SERVICES FOR NORTHSIDE III EST FINAL DESIGN CITY PROJECT NO.: 104290 procedures shall include a log of all significant bidders questions and requests and the response thereto. The log shall be housed and maintained in the project's Buzzsaw folder titled Request for Information. The ENGINEER will provide technical interpretation of the contract bid documents and will prepare proposed responses to all bidders questions and requests, in the form of addenda. The ENGINEER shall upload all approved addenda onto Buzzsaw and mail addenda to all plan holders. • Attend the prebid conference in support of the CITY. • Assist the CITY in determining the qualifications and acceptability of prospective contractors, subcontractors, and suppliers. • When substitution prior to award of contracts is allowed in the contract documents, the ENGINEER will advise the CITY as to the acceptability of alternate materials and equipment proposed by bidders. • Attend the bid opening in support of the CITY. • Tabulate and review all bids received for the construction project, assist the CITY in evaluating bids, and recommend award of the contract. A copy of the Bid Tabulation and the CFW Data Spreadsheet created utilizing CFW Bidtools only are to be uploaded into the project's Bid Results folder on Buzzsaw. • Incorporate all addenda into the contract documents and issue conformed sets. 5.2 Final Design Drawings 1) Final Design Drawings shall be submitted in both Adobe Acrobat PDF format (version 6.0 or higher) format and DWF format. There shall be one (1) PDF file and one (1) DWF file for the TPW plan set and a separate PDF and DWF file for the Water plan set. Each PDF and DWF file shall be created from the original CAD drawing files and shall contain all associated sheets of the particular plan set. Sinaular PDF and DWF files for each sheet of a clan set will not be, accented. PDF and DWF files shall conform to naming conventions as follows: TPW file name example — "W-1956—org47.pdf" where "W-1956" is the assigned file number obtained from the CITY, "_org" designating the file is of an original plan set, "47" shall be the total number of sheets in this file. Example: W-0053_org3.pdf and K-0320_org5.pdf II. Water and Sewer file name example — "X-35667_org36.pdf" where "X- 35667" is the assigned file number obtained from the CITY, "_org" designating the file is of an original plan set, "36" shall be the total number of sheets in this file. Example: X-12755_org18.pdf City of Fort Worth, Texas Attachment A PMO Release Date: 08.1.2014 Page 11 of 19 ATTACHMENT A DESIGN SERVICES FOR NORTHSIDE III EST FINAL DESIGN CITY PROJECT NO.: 104290 Both PDF and DWF files shall be uploaded to the project's Final Drawing folder in Buzzsaw. 2) In addition to the PDF and DWF files, the ENGINEER shall submit each plan sheet as an individual DWG file with all reference files integrated into the sheet. If the plans were prepared in DGN format, they shall be converted to DWG prior to uploading. The naming convention to be used for the DWG files shall be as follows: I. TPW files shall use the W number as for PDF and DWF files, but shall include the sheet number in the name — "W-1956—SHT01.dwg", "W- 1956—SHT02.dwg", etc. II. Water and Sewer file names shall use the X number as for PDF and DWF files, but shall include the sheet number in the name — "X- 12155—SHT01.dwg", "X-12755—SHT02.dwg", etc. For information on the proper manner to submit files and to obtain a file number for the project, contact the Department of Transportation and Public Works Vault at telephone number (817) 392-8426. File numbers will not be issued to a project unless the appropriate project numbers and fund codes have been assigned and are in the Department of Transportation and Public Works database. ASSUMPTIONS • The project will be bid only once and awarded to one contractor. • 10 sets of construction documents will be sold to and made available on Buzzsaw for plan holders and/or given to plan viewing rooms. • 5 sets of 11 x 17 size and 2 sets of 22 x 34 size drawings plans and 3 specifications (conformed, if applicable) will be delivered to the CITY. • PDF, DWF and DWG files will be uploaded to Buzzsaw. DELIVERABLES A. Addenda B. Bid tabulations C. CFW Data Spreadsheet D. Recommendation of award E. Construction documents (conformed, if applicable) TASK 6. CONSTRUCTION PHASE SERVICES. ENGINEER will support the construction phase of the project as follows 6.1 Construction Support City of Fort Worth, Texas Attachment A PMO Release Date: 08.1.2014 Page 12 of 19 ATTACHMENTA DESIGN SERVICES FOR NORTHSIDE III EST FINAL DESIGN CITY PROJECT NO.: 104290 • The ENGINEER shall attend the preconstruction conference. • After the pre -construction conference, the ENGINEER shall provide project exhibits and attend public meeting to help explain the proposed project to residents. The CITY shall select a suitable location and mail the invitation letters to the affected customers. • The ENGINEER shall visit the project site at requested intervals as construction proceeds to observe and report on progress. • Punch List • Tank foundation rebar check / in foundation conduit inspection • Weld check on bowl (preferably while it is still on the ground) • NACE coating inspection for blast, prime coat, and each subsequent top coat • Piping / duct bank • Electric gear installation • Startup • As requested by the CITY, the ENGINEER shall provide necessary interpretations and clarifications of contract documents, review change orders, and make recommendations as to the acceptability of the work. • As requested by the CITY, the ENGINEER shall review and respond to submittals. The ENGINEER shall attend the "Final" project walk through and assist with preparation of final punch list 6.2 Record Drawings • The ENGINEER shall prepare Record Drawings from information provided by the CITY depicting any changes made to the Final Drawings during construction. The following information shall be provided by the CITY: o As -Built Survey o Red -Line Markups from Contractor o Red -Line Markups from City Inspector o Copies of Approved Change Orders o Approved Substitutions The ENGINEER shall modify the Final Drawings electronically and shall place a stamp on the plans indicating that they represent Record Drawings of the project as constructed. The stamp shall be signed and dated by the ENGINEER and shall be placed on each plan sheet, whether there are any revisions on the sheet or not. Each sheet shall clearly indicate all changes which apply to that sheet by clouding and numbering, or other suitable means. City of Fort Worth, Texas Attachment A PMO Release Date: 08.1.2014 Page 13 of 19 ATTACHMENT A DESIGN SERVICES FOR NORTHSIDE III EST FINAL DESIGN CITY PROJECT NO.: 104290 • The following disclaimer shall be included with the Record Drawing stamp: o These Record Drawings were prepared using information provided by others and represent the as constructed conditions to the extent that documented changes were provided for recording. The ENGINEER assumes no liability for undocumented changes and certifies only that the documented changes are accurately depicted on these drawings. • The ENGINEER shall submit a set of sealed Final Drawings, modified and stamped as Record Drawings, on mylar for record storage. The ENGINEER may keep copies of the information provided by the CITY for their files, but all original red -lined drawings shall be returned to the CITY with the mylars. 2) Record Drawings shall also be submitted in both Adobe Acrobat PDF format (version 6.0 or higher) format and DWF format. There shall be one (1) PDF file and one (1) DWF file for the TPW plan set and a separate PDF and DWF file for the Water plan set. Each PDF and DWF file shall contain all associated sheets of the particular plan set. Sinaular PDF and DWF files for each sheet of a. elan set will not be accepted. PDF and DWF files shall conform to naming conventions as follows: I. TPW file name example — "W-1956—rec47.pdf" where "W-1956" is the assigned file number obtained from the CITY, "_rec" designating the file is of a record drawing plan set, "47" shall be the total number of sheets in this file. Example: W-0053_rec3.pdf and K-0320_org5.pdf II. Water and Sewer file name example — "X-35667—rec36.pdf" where "X- 35667" is the assigned file number obtained from the CITY, "—rec" designating the file is of a record drawing plan set, "36" shall be the total number of sheets in this file. Example: X-12755_rec18.pdf Both PDF and DWF files shall be uploaded to the project's Record Drawings folder in Buzzsaw. ASSUMPTIONS • Construction duration is 720 days. • 10 RFI's are assumed. • 2 Change Orders are assumed. • 5 Submittals are assumed • One copy of full size (22"x34") Record Drawing mylars will be delivered to the CITY. City of Fort Worth, Texas Attachment A PMO Release Date: 08.1.2014 Page 14 of 19 ATTACHMENTA DESIGN SERVICES FOR NORTHSIDE III EST FINAL DESIGN CITY PROJECT NO.: 104290 DELIVERABLES A. Public meeting exhibits B. Response to Contractor's Request for Information C. Review of Change Orders D. Review of shop drawings E. Final Punch List items F. Record Drawings on Mylar TASK 7. ROW/EASEMENT SERVICES. ENGINEER will support and perform activities related to ROW and land as outlined below, per scoping direction and guidance from the CITY's Project Manager. 7.1. Right -of -Way Research • The ENGINEER shall determine rights -of -way, easements needs for construction of the project. This work is focused on determining the access to the project site during construction and for maintenance and use purposes prior to the construction of developed road access assuming the use of existing gas well roads. Required temporary and permanent easements will be identified based on available information and recommendations will be made for approval by the CITY. 7.2. Right-of-Way/Easement Preparation and Submittal. The ENGINEER shall prepare documents to be used to obtain right-of-way and permanent and/or temporary easements required to construct the improvements. • The ENGINEER shall submit the right-of-way and/or easement documents to CITY PM for real property acquisition The documentation shall be provided in conformance with the checklists and templates available on the CITY's Buzzsaw site. 7.3. Temporary Right of Entry Preparation and Submittal • Prior to construction, the ENGINEER shall prepare and submit Temporary Right of Entry documents for landowners to CITY PM for real property acquisition. It is assumed that letters will only be required for land owners adjacent to temporary construction easements or who are directly affected by the project and no easement is required to enter their property. • The documentation shall be provided in conformance with the checklists and templates available on the CITY's Buzzsaw site. City of Fort Worth, Texas Attachment A PMO Release Date: 08.1.2014 Page 15 of 19 ATTACHMENT A DESIGN SERVICES FOR NORTHSIDE III EST FINAL DESIGN CITY PROJECT NO.: 104290 ASSUMPTIONS • Up to 4 Easements or right-of-way documents will be necessary for the Elevated Storage Tank construction and maintenance access. • Up to 2 Easements or right-of-way documents will be necessary for the tank overflow discharge piping construction and maintenance access (anticipated to cross through the proposed developed and discharge to the future storm system). • Up to 4 Temporary right -of -entry documents will be necessary. • Right -of -Way research and mapping includes review of property/right-of-way records based on current internet based Tarrant Appraisal District (TAD) information available at the start of the project and available on -ground property information (i.e. iron rods, fences, stakes, etc.). It does not include effort for chain of title research, parent track research, additional research for easements not included in the TAD, right-of-way takings, easement vacations and abandonments, right-of-way vacations, and street closures. DELIVERABLES A. Easement exhibits and meets and bounds provided on CITY forms. B. Temporary Right of Entry Letters TASK 8. SURVEY AND SUBSURFACE UTILITY ENGINEERING SERVICES. ENGINEER will provide survey support as follows 8.1. Design Survey • ENGINEER will perform field surveys to collect horizontal and vertical elevations and other information needed by ENGINEER in design and preparation of plans for the project. Information gathered during the survey shall include topographic data, elevations of all sanitary and adjacent storm sewers, rim/invert elevations, location of buried utilities, structures, trees (measure caliper, identify overall canopy, and have qualified arborist identify species of trees), and other features relevant to the final plan sheets. Existing drainage at intersections will be verified by field surveys. Spot elevations will be shown on intersection layouts with cross slope to fit intersecting grade lines. • The minimum survey information to be provided on the plans shall include the following: — A Project Control Sheet, showing ALL Control Points, used or set while gathering data. Generally on a scale of not less than 1:400: — The following information about each Control Point; a. Identified (Existing. CITY Monument #8901, PK Nail, 5/8" Iron Rod) b. X, Y and Z Coordinates, in an identified coordinate system, and a referred bearing base. Z coordinate on CITY Datum only. City of Fort Worth, Texas Attachment A PMO Release Date: 08.1.2014 Page 16 of 19 ATTACHMENT A DESIGN SERVICES FOR NORTHSIDE III EST FINAL DESIGN CITY PROJECT NO.: 104290 C. Descriptive Location (Ex. Set in the centerline of the inlet in the South curb line of North Side Drive at the East end of radius at the Southeast corner of North Side Drive and North Main Street). — Coordinates on all P.C.'s, P.T.'s, P.I.'s, Manholes, Valves, etc., in the same coordinate system, as the Control. — No less than two horizontal bench marks, per line or location. — Bearings given on all proposed centerlines, or baselines. — Station equations relating utilities to paving, when appropriate. 8.2. Temporary Right of Entry Preparation and Submittal • Prior to entering property, the ENGINEER shall prepare and submit Temporary Right of Entry for landowners to CITY PM. • The documentation shall be provided in conformance with the checklists and templates available on the CITY's Buzzsaw site. ASSUMPTIONS • Topographic survey at intersection will include no more than 100 ft. in each direction. DELIVERABLES A. Copies of field survey data and notes signed and sealed by a licensed surveyor. B. Drawing of the project layout with dimensions and coordinate list. City of Fort Worth, Texas Attachment A PMO Release Date: 08.1.2014 Page 17 of 19 ATTACHMENT A DESIGN SERVICES FOR NORTHSIDE III EST FINAL DESIGN CITY PROJECT NO.: 104290 TASK 9. PLAN SUBMITTAL CHECKLISTS Engineer shall complete and submit Plan Submittal Checklists in accordance with the following table: PLAN SUBP41TTAL CHECKLIST REQUIREMEN—S Traffic Traffic Traffic Street Water Control Control Control Traffic Storm Storm Lights /Sewer Traffic 30% 60% 90% Attachment "A" Signal Water Water (Submit (Submit Engineering Type (Submit All 30% 60% All @ All @ (Submit All ° @ 30 /o) 30% 60%) @ 60%) Required for all work in City ROW Street X X X X V X X X X Storm Water X X X X X Water / Sewer X X X X *If included in street project ADDITIONAL SERVICES NOT INCLUDED IN THE EXISTING SCOPE OF SERVICES Additional Services not included in the existina Scope of Services — CITY and ENGINEER agree that the following services are beyond the Scope of Services described in the tasks above. However, ENGINEER can provide these services, if needed, upon the CITY's written request. Any additional amounts paid to the ENGINEER as a result of any material change to the Scope of the Project shall be agreed upon in writing by both parties before the services are performed. These additional services include the following: • Negotiation of easements or property acquisition including temporary right -of - entries. • Services related to development of the CITY's project financing and/or budget. Services related to disputes over pre -qualification, bid protests, bid rejection and re -bidding of the contract for construction. Construction management and inspection services Periodic site visits during construction phase Performance of materials testing or specialty testing services. Services necessary due to the default of the Contractor. • Services related to damages caused by fire, flood, earthquake or other acts of God. City of Fort Worth, Texas Attachment A PMO Release Date: 08.1.2014 Page 18 of 19 ATTACHMENTA DESIGN SERVICES FOR NORTHSIDE III EST FINAL DESIGN CITY PROJECT NO.: 104290 • Services related to warranty claims, enforcement and inspection after final completion. Services related to submitting for permits (ie.TxDOT, railroad, etc...) • Services related to topographic survey (assumed to use developer provided survey for design development). Services related to Subsurface Utility Engineering Levels A, B, C or D Services related to Survey Construction Staking • Services related to acquiring real property including but not limited to easements, right-of-way, and/or temporary right -of -entries. • Services to support, prepare, document, bring, defend, or assist in litigation undertaken or defended by the CITY. cr�mpl-,.; and other submittalo oabmitted by the r,nntrar--tGr-. • Performance of miscellaneous and supplemental services related to the project as requested by the CITY. City of Fort Worth, Texas Attachment A PMO Release Date: 08.1.2014 Page 19 of 19 Task No. Task Description yY 11 Rat, 11,., k I� ITieamnt i tdl 1 oordination Meetings 1.1.1 (monthly-6 months) 1.1.2g are ly 6�f Reports vim 1,25 Schedule lt� f'fgpCre Moonily MBGWtit Reports [ MMhh mw 20 cent) 21 A aensandDraina9e+Ya.'ti 22 bap 3.0 ' 1161111,1n //yy Dggcs g 111 Percent) 3.1 rj'reumm�Nflfl��9�t¢AEBAYPa" S'I"" nica ve avemen Design (2 additional geotech bores to 32 W".�11*ew 3.3 4.0 Final Design Final Draft (90%) Construction Plans and 4.1 Specifications 18 sheets Final (100%) Plans and Specifications 18 42 sheets 4.3 Project Decision Logs (90%and 100-A) 4 Con.tr egpn"Imates(9U%and 1uu%1 10 5., "IleMgrt, e G Irac[Oocuments and Maintain 5.1.1 Plan Holdem List ` �']'3 ej19 @ @ �llence 17A ee 1 5.1.5 Tabulate Bids and RecommendAWafd 5.1.6 Issue Conformed Contract Documents City of Fort Worth, Texas Attachment B-Level of Effort Supplement PMO (gdal Release Date. 8.09.2012 Level of Effort Spreadsheet TASK/HOUR BREAKDOWN Design Services for Northside III EST Final Design City Project No. 104290 Mobley Genesis Rios- Specs- Castillo - n,....4 T io (20/801 Gala Riebe Jesus Gonzale, 4020 Project Project Projttt Director Manager Engineer S300 S2d0 $190 Site Civii Lead $195 Site Civil Production Process Lead --tior(ny ) Process Production WIDC Load WIDC Electrical production Lead Electrical Production Structural Leal Structural Protluebon Total Late Cost Expense Subconsultant Tavel MWBE Non-MWBE Reproduction Total Expense Lost Task Sub Total $120 $250 $12 $19 512 331 S15 529 $12 6 6 6 6 ( 4 4 9 p j, L4 f4 8, d I I - II:I'li lti Il 1111 II i:i ' I',� • 1i.1. �. Illil ". 0 01 01 0 .... .... �`, 40 31 102 21 6 21 E ini;l : n": 8 E � 4� 2 $13,149 $ $12,800 3 52.02� 560 $31T� S:iFil $60 $2.000 Sc $Sq so 34 S $ $0 $ .. �... _. ... .... .. .. ... $ $72,92 $9,3 S $10 $9,4 $13*140 30 312,800 $2,020 70.270 1 4 1 8 1 6 31, $3460 2 2 $2,000 $0 $0 $0 30 $82,370 i,�.. 0 01 II.. ` 0 20 8 3C, for 2K E. 2L 8i 4( 8,4 0 $7.040 S1,720 $1,240 $1 240 $9,3� I I I $100 $10 $9,35 $ 0 $16,390 2 4 4 41 $1, 20 $1.240 2 41 2 41 $1240 $0 0 2 16 4 43 .-1 —�—� 'I 43 139933 101 1 7 6 $3230. ....__ $65,20 ._.__ _: .�__... $21)520 $3,230 $65,405 4 15 25 15 Jfi, $0 is fy 2C 4 8 4 1 S52,515 $27,480 $6,460 I l 4 $16,680 sc $111 $10 S100 $10 112.611 8 20 $27.580 0 4 13 8 401 21 4 2 41 81 4 2 a 4 ! —.V $q V $6460 $16,68 H L 41� y . ,1.,.1.i,.. ,. ,_, ,,.,.,. ,. ..... 4 ... ... A :nnn i' l i�uu ,unlit ,,i i 4 I nit', u'nm l -u1 I1 • I to 1 S3,240 I I ---$T,'22077,, 1 �� r, l u.l. p,... , _._..,-_ - _�_. _. _ _ .... _ _ 3 $3,240 4 4 2,10 2 _. .,. 8 11 4 4 1 d 1 4 $4,790 Sc S4,790 11 Mobley Genesis Rios - Tina Derek Traio (20/60) Garza Rlebe Task No. I Task Description Project Projeet� Director Manager Project Engineer Sit.Civil Lead Sit.Civil Production%(II Proce� Lcatl R.n $30 S I 51 $19 sizd S.0 Phase Services 75 718 7 42 �Constrution 6.1 ConsOrucson Support 1 I 6.1.1 Attend Preconstrucaon Conference 21 21 01 Attend Public Meeting 21 41 1 6.7.3 Project Site VISIM (2) I I I 11 121 6.1.4 Submittal Review (5) I I 20 20 6.1.5 Re quest for Information/Change Order Review(6) 5 20 6.1.6 Final Walk Through an tl Punch Ust 1 1 61 el 6.1.7 NACE Coating Inspection 80 62 Record D—gs I 21 6 21 161 21 7.0 —ti OW/Easement Servien o d 16 2 6 0 1.1 Rlgmaf-Way Research 1 RI9ht-of-Way/Easement Preparation antl � 72 Submittal(6) 2 6J 1 6 7.3 Temporary Right of Entry Submittal (4) 8.0 purvey , J 8 1 2 0 a.7 Design Survey i ZJ J 1 82 Tempoary Right of Entry Submittal 1 6 it a.3 s Rcm"uor' uw 9.0 'Perm7diRg 0 0 0 0 0 0 S., 92 nVIfOnIlleRidIS4MC06 9.3 Roodpl-m-Se-oes 9.4 9.5 9. 9.7 PFarks6onversloR I J robl! 341 109 3191 1fi/1 136 City of Fort Worth, Texas Attachment B - Level of Effort Supplement PMO Official Release Date: 8.09.2012 Level of Effort Spreadsheet TASK/HOUR BREAKDOWN Design Services for Northside III EST Final Design City Project No. 104290 Specs -Castillo - Jesus Gonzalez Chonp20/80 C6uentes Grant 4020 oor Iursl e�p on - I I El I I Structupi Telacost� Subconsultant Total Expense Task Sub Total Production -DC Lwtl Production Lead PEcanStructural Production Reproduction Cost 51 519 S7 531 31 529Q 51 MINNI Non 8 Q 561,7 $62, 34( I ;m I 14 5 I 12 s �1'. 2q I 2q 1 2q I I Ste•f, I $5,00 S5,D0 t\ I q $9,32 1 $2 Q S. $9.�52 I I I I I 7> I $zdG 52 a q a 1qf"• Stz S� l 51,E $13�0 573. $$4, �. =_41 I I 7 d .. .''.I4 5 .. sc S 5 $ q q $ I I S I I I S S 1 1 $ 19q 12q 1 10� 13a 5J $302; 1 $32,00 $9,35Q 596 $30 34Z '1 ..J I Project Summary Total Hours 1, Total Labo $. 1 Total Expense $42,61 MBE/S Subcansulta .53ZDD Noh_MBE/5 Subconeulta $9,35 1,,Sub Mar f 54,13 MBE/SBE Paroapaoo 9 I Total Project Co —.05 2 of PAY ITEM 1 2 3 4 BID LIST ITEM NO Citv of Fort Worth Northside 111 EST Pre -Design ENGINEER'S OPINION OF PROBABLE CONSTUCTION COST SPEC. DESCRIPTION APPROX. UNIT TOTAL NO. OF ITEMS QTY. PRICE AMOUNT Composite Elevated Tank (2.5 MG) 1 LS $ 8,200,000.00 $ 8,200,000.00 Electrical and Controls 1 LS $ 700,000.00 $ 700,000.00 Piping & Mechanical - Tank Structure 1 LS $ 300,000.00 $ 300,000.00 Site Work - Civil, Security and Piping 1 LS $ 900,000.00 $ 900,000.00 SUBTOTAL $ 10,100,000.00 Contingency Allowance (30%) $ 3,030,000.00 TOTAL $ 13,130,000.00 5/10/2023 1 of 1 LOCATION MAP Ft City of Fort Worth, Texas Mayor and Council Communication DATE: Tuesday, June 27, 2023 REFERENCE NO.: **M&C 23-0536 LOG NAME: 60NSIIIESTA1-GARVER SUBJECT: (CD 10) Authorize Execution of Amendment No. 1, in the Amount of $349,055.00, to an Engineering Agreement with Garver, LLC. for the Northside III Elevated Storage Tank Project and Adopt Appropriation Ordinances to Effect a Portion of Water's Contribution to Fiscal Years 2023-2027 Capital Improvement Program RECOMMENDATION: It is recommended that the City Council: 1. Authorize execution of Amendment No. 1, in the amount of $349,055.00, to City Secretary Contract No. 58012 a professional services agreement with Garver, LLC. for the Northside III Elevated Storage Tank project for a revised contract amount $416,320.00; 2. Adopt the attached appropriation ordinance increasing receipts and appropriations in the Water Impact Fee Fund in the amount of $502,410.00 from avaliable funds, for the purpose of transferring funds from the Water/Wastewater Wholesale Impact Fees and Water/Wastewater Retail Impact Fee projects (City Project Nos. B20004 and B20005) to the Northside III Elevated Storage Tank project (City Project No. 104290); and 3. Adopt the attached appropriation ordinance increasing receipts and appropriations in the Water Impact Fee Fund in the amount of $502,410.00 transferred from within the Water Impact Fee Fund to the Northside III Elevated Storage Tank project (City Project No. 104290) to effect a portion of Water's Contibutions to the Fiscal Year 2023 - 2027 Capital Improvement Program. DISCUSSION: On August 21, 2022, the City Manager administratively authorized a professional services agreement in the amount of $67,265.00 (budgeted in the Water & Sewer Fund Other Contractual Services Line, as appropriated) with Garver, LLC. (City Secretary Contract No. 58012) for the Siting Study for Northside III Elevated Storage Tank. Due to increased development in the Northside III service area, it is necessary to install an elevated storage tank to provide increased capacity and delivery reliability to future customers. Amendment No. 1 will provide for the preparation of plans and specifications for the construction of Northside III Elevated Storage Tank. Garver, LLC. proposes to provide all the necessary design and construction administration services for a fee of $349,055.00. Staff considers the proposed fee to be fair and reasonable for the scope of services proposed. In addition to the contract amount, $153,355.00 is required for project management, utility coordination, and material testing. This project will have no impact on the Water Department Operating budget when complete. It is the practice of the Water Department to appropriate its CIP plan throughout the fiscal year, instead of within the annual budget ordinance, as projects commence, additional funding needs are identified, and to comply with bond covenants. The actions in the M&C will appropriate funds in support of the Water's portion of the City of Fort Worth's Fiscal Years 2023-2027 Capital Improvement Program, as follows: 60NSIIIESTA1-GARVER Capital Revised Budgetproject Fund FY2023 CIP Change Authority FY2023 Name Name Appropriations (Increase/ Budget Decrease) Water Impact 104290 — Fee - Northside $0.00 This M&C $502,410.00 $502,410.00 Fund III EST 56003 Funding is currently available in the W/WW Wholesale Impact Fees and the W/WW Retail Impact Fees projects within the Water Impact Fee Fund for the purpose of funding the Northside III Elevated Storage Tank project. Funding for the Northside III Elevated Storage Tank project is depicted below: FUND I-AppropriatExistinions Additional AppropriationsI Project Total* 'Water Impact Fee - $0.00 $502,410.00 $502,410.00 Fund 56003 Project Total $0.00 $502,410.00 $502,410.00 Numbers rounded for presentation purposes. Business Equity: Garver LLC., is in compliance with City's Business Equity Ordinance by committing to nine percent MWBE participation on this project. The City's MWBE goal on this project is nine percent. The project is located in COUNCIL DISTRICT 10. FISCAL INFORMATION / CERTIFICATION: The Director of Finance certifies that funds are currently available in the W/WW Wholesale Impact Fees and W/WW Retail Impact Fees projects within the Water Impact Fee Fund and upon approval of the above recommendations and adoption of the attached appropriation ordinance, funds will be available in the Water Impact Fee Fund for the Northside III EST project to support the above recommendations and execution of the agreement. Prior to an expenditure being incurred, the Water Department has the responsibility of verifying the availability of funds. FUND IDENTIFIERS (FIDs),: TO Fund Department ccount Project Program ctivity Budget Reference # mount ID 1 ( ID I 1 ( Year I (Chartfield 2) FROM Fund Department ccount Project Program ctivity Budget Reference # mound ID ID I ( Year I (Chartfield 2) CERTIFICATIONS: Submitted for City Manager's Office by_ Dana Burghdoff (8018) Originating Department Head: Chris Harder (5020) Additional Information Contact: Pratima Poudyal (6149) ATTACHMENTS 1. 60NSIIIESTA1-GARVER Comr)liance Memo.pdf (CFW Internal) 2. 60NSIIIESTAl-GARVER Form 1295.pdf (CFW Internal) 3. 60NSIIIESTA1-GARVER funds availabilitv.pdf (CFW Internal) 4. 60NSIIIESTAl-GARVER Map.pdf (Public) 5. 60NSIIIESTAl-GARVER Updated FID.xlsx (CFW Internal) 6. Entitvinformation-Garver.pdf (CFW Internal) 7.ORD.APP 60NSIIIESTAl-GARVER_56003 A0231(r3).docx (Public) 8.ORD.APP 60NSIIIESTAl-GARVER 56003 AO23(r2).docx (Public) 9. PBS CPN 104290.pdf (CFW Internal) 60NSIIIESTAI-GARVER FID Table 2 56003 0600430 4413023 B20004 2023 $251,205.00 2 56003 0600430 B20004 2023 $251,205.00 2 56003 0600430 4413024 B20005 2023 1 $251,205.00 2 56003 0600430 B20005 2023 I I $251,205.00I 3 56003 0600430 4956003 104290 2023 I $502,410.00 3 56003 0600430 104290 2023 $502,410.00 3 56003 3 56003 3 56003 0600430 5900016 B20004 0600430 5900016 B20005 0600430 4956003 104290 2&3) 56003 0600430 5110101 104290 1) 56003 0600430 5330500 104290 2&3) 56003 0600430 5310350 104290 2&3) 56003 0600430 5540101 104290 20) 156003 0600430 5330500 104290 1 2&3) 156003 I 1 1 1 0600430 5310350 104290 B02000 B02000 001830 9999 9999 9999 $251,205.00 $251,205.00 ($502,410.00) 001830 9999 $82,400.00 Water Staff Cost 001830 9999 $349,055.00 Contract 001870 9999 $2,005.00 Utility coordination 001830 9999 $2,000.00 Public Outreach 001884 I 9999 I I $51,500.00 Soil Lab Consultant 001884 9999 I I $15,450.00 Soil Lab TPW Staff cost