HomeMy WebLinkAboutContract 49556-A5CSC No. 49556-A5
AMENDMENT No . 5
TO CITY SECRETARY CONTRACT No. 49556
WHEREAS, the City of Fort Worth (CITY) and Burns & McDonnell
Engineering Company, Inc., (ENGINEER) made and entered into City
Secretary Contract No. 49556, (the CONTRACT) which was authorized by M&C
C-28288 on June 20, 2017 in the amount of $400,000.00; and
WHEREAS, the CONTRACT was subsequently revised by: Amendment No. 1
in the amount of $1,500,000.00 which was authorized by M&C C-28764 on
June 26, 2018; Amendment No. 2 in the amount of $790,959.41 which was
authorized by M&C 20-0361 on June 2, 2020; Amendment No. 3 in the amount
of $311,248.00 which was authorized by M&C on February 8, 2022; Amendment
No. 4 in the amount of $259,965.00 which was authorized by M&C on June
28, 2022; and
WHEREAS, the CONTRACT involves engineering services for the
following project:
Cromwell Marine Creek Road, City Project No. 101012; and
WHEREAS, it has become necessary to execute Amendment No. 5 to the
CONTRACT to include an increased scope of work and revised fee.
NOW THEREFORE, CITY and ENGINEER, acting herein by and through their
duly authorized representatives, enter into the following agreement,
which amends the CONTRACT:
Article I of the CONTRACT is amended to include the additional
engineering services specified in proposal attached hereto and
incorporated herein. The cost to City for the additional design services
to be performed by Engineer totals $23,004.60. (See Attached Funding
Breakdown Sheet, Page -4-)
2.
Article II of the CONTRACT is amended to provide for an increase in
the fee to be paid to Engineer for all work and services performed under
the Contract, as amended, so that the total fee paid by the City for all
work and services shall be an amount of $3,285,172.01.
OFFICIAL RECORD
CITY SECRETARY
3. FT. WORTH, TX
All other provisions of the Contract, which are not expressly
City of Fort Worth, Texas Cromwell Marine Creek Road Improvements
Prof Services Agreement Amendment Template 101012
Revision Date: November 23, 2021
Page 1 of 4
amended herein, shall remain in full force and effect.
EXECUTED and EFFECTIVE as of the date subscribed by the City's
designated Assistant City Manager.
APPROVED:
City of Fort Worth
Willi am Johnson() 28,202310:26 CDT)
William Johnson, P.E.
Assistant City Manager
DATE: J u [ 28, 2023
APPROVAL RECOMMENDED:
ENGINEER
Burns & McDonnell, Engineering
Company, Inc.
Digitally signed by Scott Clark
DN: C=US,
E=om,Scott CIarkO=Burns & McDonnell,
CN=Scott
Clark
Data 2023,06.22 13:58:52-05'00'
Scott Clark, P.E.
Vice President
DATE: 6/22/2023
X
Lauren Prieur (Jul 25, 202315:09 CDT)
Lauren Prieur, P.E.
Director, Transportation and Public Works Department
Contract Compliance Manager:
By signing, I acknowledge that I am the person responsible for the
monitoring and administration of this contract, including ensuring all
performance and reporting requirements.
Alejandra Ayala, P.E.
Sr. Project Manager
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
City of Fort Worth, Texas Cromwell Marine Creek Road Improvements
Prof Services Agreement Amendment Template 101012
Revision Date: November 23, 2021
Page 2 of 4
APPROVED AS TO FORM AND LEGALITY:
I
DBlatk (Jul 27, 202316:11 CDT)
Douglas W. Black
Assistant City Attorney
ATTEST: poFF.....Q0
p Wig° NO
V � .,s a°nnn�z 456p�
Jannette Goodall
City Secretary
M&C: N/A
Date: N/A
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
City of Fort Worth, Texas
Prof Services Agreement Amendment Template
Revision Date: November 23, 2021
Page 3 of 4
Cromwell Marine Creek Road Improvements
101012
FUNDING BREAKDOWN SHEET
City Secretary No. 49556
Amendment No. 5
Department Fund -Account -Center Amount
TPW 34018-0200431-5330500-101012-002330-9999- $23,004.60
18010199
Total: $23,004.60
City of Fort Worth, Texas Cromwell Marine Creek Road Improvements
Prof Services Agreement Amendment Template 101012
Revision Date: November 23, 2021
Page 4 of 4
�� BURNS
MEDONNELL.
May 19, 2023
Mrs. Alejandra (Alex) Ayala, P.E.
Senior Project Manager - City of Fort Worth
Transportation & Public Works Department
1000 Throckmorton Street
Fort Worth, Texas 76102
817-392-8883; aleiandra.avala@fortworthtexas.aov
Re: Proposal to collect additional bores and pavement cores to evaluate existing pavement structure and
evaluate retaining wall required along proposed channel along Huffines Blvd.
Mrs. Ayala:
Burns and McDonnell is pleased to submit this proposal in the amount of $23.004.60 for professional
engineering services to collect bores to determine existing pavement section on Cromwell Marine Creek
Rd, Huffines Blvd, and Bob Hanger Rd. The proposal also includes collecting bores along Huffines Blvd,
and conducting a geotechnical analysis required for the design of the proposed (slope) wall adjacent to the
proposed widened channel on the west side of Huffines Blvd.
Project Overview
Pavement Cores: Based on input from the Construction Manager at Risk firm (Sundt Construction),
following their review of the geotechnical report and as -built drawings they identified that additional
geotechnical information is required of the existing pavement structure on Cromwell Marine Creek Rd.
Therefore, pavement cores are requested to finalize the roadway design and to develop pavement removal
quantities.
Geotechnical Analysis of Channel Slope Wall: During design development, the need for geotechnical
assessment of slope wall or retaining was identified to avoid any impact to the existing pavement on
Huffines. Due to the proposed depth and possible 2:1 side slope of the proposed widened channel on the
west side of Huffines Blvd, a geotechnical evaluation is required to determine if a concrete riprap slope
(TxDOT CRR Detail) or retaining wall will be required.
Scope of Work:
Burns & McDonnell will develop the analysis based on the following scope of work items:
1. Collect 6 pavement cores on Cromwell Marine Creek Rd to provide existing pave structure
information required to finalize roadway design and removal quantities.
2. Collect •1 pavement core on Huffines to provide existing pave structure information required to
finalize roadway design and removal quantities.
3. Collect 1 pavement core on Bob Hanger Rd to provide existing pave structure information
required to finalize roadway design and removal quantities.
4. Collect 2 bores within channel area and conduct geotechnical analysis to determine required
retaining wall or channel wall.
13737Noel fd • 6ollerlo North Tower I/Sulte 700 • Dollos, U75740 Cromwell Marine Creek Road Improvements
Tel.• 977-4S.f--9100 - fox 977-986--4076 • www.hurosmrdrom 101012
� BURNS
MEDONNELL..
Proposal to collect pavement cores to evaluate existing pavement structure and bores and
geotechnical evaluation of required wall along proposed channel adjacent to Huffines Blvd.
May 19, 2023
Page 2
General Assumptions:
Burns & McDonnell shall develop the geotechnical assessment based on the following assumptions:
1. Final core locations will be finalized in coordination with the Construction Manager at Risk firm
(Sundt Construction).
2. Bore will be scheduled upon approval of this work.
We look forward to working with you towards completion of a successful analysis. Please contact me if
you have any questions and/or if you require any additional information.
Sincerely,
4.,f M � a, CLOW
Dennis R. Ingram, P.E.
Project Manager
Burns & McDonnell Engineering Company, Inc.
(214) 336-5560 / dringram@burnsmcd.com
Enclosures:
1) Fee Request for Pavement Cores and Geotechnical Assessment of Slope/Retaining Wall at
Huffines Blvd.
2) cc: BMcD Project File: T:\TRN\City of Fort Worth\102809 Cromwell Marine Creek
Rd\Management\Contracts\Task Order 5
15950Norlh Dollos Parkway • Tower 11/Sui1e700 • Dollos, TX75248 Cromwell Marine Creek Road Improvements
Tel. 972-45S3100 • fox. 97?4M-4026 • www.hurnsmrd.rom 101012
Prime: Burns McDonnell City of Fort Worth, Texas
Project: Cromwell Marine Road Method of Payment: Lump Sum Task Order #2
City Project: 101012
COUNTY: Tarrant
PROJECT NAME: Cromwell Marine Creek Road Retaining Wall/Slope at Huffines and Pavement Cores
CSJ:
LIMITS: From Boat Club Road to Marine Creek Parkway
19-May-23
PRIME PROVIDER NAME: Burns & McDonnell
SUB
TOTAL
TASKS
ETTL
TOTAL
LUMP SUM
I
I
I
Route & DesignStudies
$
10,890.00
$
10,890.00
Direct Expenses
$
11,819.60
$
11,819.60
Project Management
$
295.00
$
295.00
FC 170
$
-
$
-
SUB TOTAL (Lump Sum)
$
23,004.60
$
23,004.60
Percentaqe
100.0%
100.0%
0.0%
$
23,004.60
$
23,004.60
SPECIFIED RATE
SUB TOTAL (Specified Rate)
TOTAL THIS WORK AUTHORIZATION
I I$ -
Lump Sum $ 23,004.60
Specified Rate $ -
Total $23,004.60
Page 1 of 1
Cromwell Marine Creek Road Improvements
101012
Method of Payment: Lump Sum
COUNTY: Tarrant
PROJECT NAME: Cromwell Marine Creek Road Retaining Wall/Slope at Huffines and Pavement Cores
CSJ:
LIMITS: From Boat Club Road to Marine Creek Parkway
Method of Payment: Lump Sum
SUBPROVIDER NAME: East Texas Testing Laboratory, Inc.
TASK DESCRIPTION PROJECT PROJECT ENGINEERING CADD ADMIN/ TOTAL
MANAGER ENGINEER GEOLOGIST TECHNICIAN OPERATOR CLERICAL LABOR HRS.
f i f & COSTS
ROUT?& dlll' YU 1S_R HOUR $165.00 $145.00 $125.00 $65.00 $75.00 $65.00
A. Geotechnical Report
Prelpre Borinq Plan and Traffic Control Plan
Stake Borings and Utility Clearance
Drillirp Coordination, Loa{�mq�and Pavement Coring
g�v`ew/Prepafe Lgp�s and Testmq
etamma a l or Slope Analysis @Huffines
Draft Report
Final Report
HOURS SUB -TOTALS
the contract which includes base hourly rate, overhead
TOTAL LABOR COSTS
SUBTOTAL
PROJECT MANAGEMENT
Meetingqs
Contrail Administration
HOURS SUB -TOTALS
the contract which includes base hourly rate, overhead
SUBTOTAL
SUMMARY BY FUNCTION CODE
ROUTE & DESIGN STUDIES
PROJECT MANAGEMENT
SUBTOTAL LABOR HOURS
CONTRACT RATE PER HOUR
SUBTOTAL LABOR EXPENSES
OTHER DIRECT EXPENSES (FC 163)
Mobilization
Mile�yy�
Atterbew Limits
Deiffrmir� amount of Soil Finer than 75 micro Sieve
Moisture �ontent
Lime Series Testig
California Bearip, Ratio f CBRI
Determininy Sulfate and Chloride Contents
CU Tri- - Tests
Soil Borinq/Rock Corinq without TCP (<60 ff)
Soil Borinq/Rock Corinq with TCP (<60 ft)
Soil Bori,Rock Cori? with TCP (>60
Core/Dri71 to drill flexible pavement (6" Diameter)
Traffic Control (medium Project)
Lodjj{{inss{{/Hotel
LodginallotelTaxes and Fees
Meals
Courier Services
Photocopies B/W (8 1/2" X 111
Photocopies B/W 11" X 17")
Photocopies Color 8 1/2" 11 ")
Photoc9 jes Color 11" X 17")
Plots Bon Bon }
Plots 1\Color on Bond)
SUBi S'TAL DIRECT EXPENSES (FC 163)
COST PER NO OF I LABOR HRS
TASK DWGS PERSHEET
1
1
1
$ 365.00
N/A
N/A
1
10
$ 1415.00
N/A
N/A
30
$ 3,�0.00
N/A
N/A
$ -
N/A
N/A
2
24
$ 3/810.00
N/A
N/A
6
2
1.0020.00
N/A
N/A
1
2
1
530.00
N/A
N/A
5
32
41
4
$65.00
75.00
$65.00
1825.00
114,640.00
15,125 00
1300.00
$' 0,�890.00
$10,890.00
$
N/A
N/A
$
N/A
N/A
1
2
$ 295.00
N/A
N/A
1
2
$165.00
$145.00
$125.00
$65.00
$75.00
$65.00
$165.00
$130.00
$295.00
$295.00
5
32
41
4
82
$10,890.00
1
2
3
$ 295.00
6
32
41
4
2
85
$165.00
$145.00
$125.00
$65.00
$75.00
$65.00
$ 990.00
$ 4,640.00
$ 5,125.00
$ -
$ 300.00
$ 130.00
$11,185.00
$11,185.00
Quantity
UNIT
Rate
Total
mile
4.500
584
in
Q.650
P79.60
6
Each
45.00
'70.00
1150.00
6
Each
. 00
6
Each
0.00
$60.00
Each
000Each
00.00
t11135.00
Each
1
Each
$1,500.00
$1,500.00
50
Foot
$32.00
$1,600.00
Foot
$33.00
Foot
$34.00
80
Inch
$18.00
$1,440.00
Assuming 10"
pavement at each location
3
Day
$1,800.00
$5,400.00
6
Da/Person
$94.00
$564.00
6
DadPPerson
$35.00
$210.00
6
Dav/Person
$41.00
$246.00
SUMMARYLABy
NON -SALARY (OOT�IER DI��qT E E R COST (include II�ISJES� Ier $$113, 113,819(
TOTAL (Labor and ire xpenses $`/23,0 4.60
each $25.00
each $0.10
each $0.15
each $0.50
each $0.80
square foot $0.50
square foot $1.50
$11,819.60
Page 1 of 1
Cromwell Marine Creek Road Improvements
101012
101012-EPAM-Cromwell Marine Creek Road
Amendment No. 5
Interim Agreement Report 2023-07-20
Created: 2023-06-29
By: Andrea Munoz (Andrea. M unoz@fortworthtexas.gov)
Status: Out for Filling
Transaction ID: CBJCHBCAABAAVkbDDcHesUCr3Vpls8KOvKjhdJO4JtA6
Agreement History
Agreement history is the list of the events that have impacted the status of the agreement prior to the final signature. A final audit report will
be generated when the agreement is complete.
"101012-EPAM-Cromwell Marine Creek Road Amendment No. 5
" History
Document created by Andrea Munoz (Andrea. Munoz@fortworthtexas.gov)
2023-06-29 - 5:40:13 PM GMT- IP address: 204.10.90.100
Document emailed to wendi.hedlund@fortworthtexas.gov for filling
2023-06-29 - 5:51:37 PM GMT
Document emailed to Alejandra.Ayala@fortworthtexas.gov for filling
2023-06-29 - 5:51:37 PM GMT
Email viewed by Alejandra.Ayala@fortworthtexas.gov
2023-06-29 - 10:05:33 PM GMT- IP address: 204.10.90.100
Signer Alejandra.Ayala@fortworthtexas.gov entered name at signing as Alejandra Ayala
2023-06-29 - 10:05:57 PM GMT- IP address: 204.10.90.100
Form filled by Alejandra Ayala (Alejandra.Ayala@fortworthtexas.gov)
Form filling Date: 2023-06-29 - 10:05:59 PM GMT - Time Source: server- IP address: 204.10.90.100
Email viewed by wendi.hedlund@fortworthtexas.gov
2023-06-30 - 8:09:58 PM GMT- IP address: 204.10.90.100
-;� Signer wendi.hedlund@fortworthtexas.gov entered name at signing as Wendi Hedlund
2023-06-30 - 8:45:48 PM GMT- IP address: 204.10.90.100
FORTW❑RTHg I Pawered6v
Adobe
Acrobat Sign
-- Form filled by Wendi Hedlund(wendi.hedlund@fortworthtexas.gov)
Form filling Date: 2023-06-30 - 8:45:50 PM GMT - Time Source: server- IP address: 204.10.90.100
Document emailed to Raul.LopezRoura@fortworthtexas.gov for filling
2023-06-30 - 8:45:52 PM GMT
Email viewed by Raul.LopezRoura@fortworthtexas.gov
2023-07-05 - 3:15:45 PM GMT- IP address: 204.10.90.100
Signer Raul.LopezRoura@fortworthtexas.gov entered name at signing as Raul E Lopez
2023-07-05 - 3:20:42 PM GMT- IP address: 204.10.90.100
Form filled by Raul E Lopez (Raul.LopezRoura@fortworthtexas.gov)
Form filling Date: 2023-07-05 - 3:20:44 PM GMT - Time Source: server- IP address: 204.10.90.100
Document emailed to Lissette.Acevedo@fortworthtexas.gov for filling
2023-07-05 - 3:20:46 PM GMT
FORTW❑RTHg I Paw m"Y
Adobe
Acrobat Sign
FORTWORTH.
Routing and Transmittal Slip
Transportation & Public Works
Department
DOCUMENT TITLE: Cromwell Marine Creek Road - Professional
Services Agreement Amendment No. 5
M&C: CPN: 101012 CSO: 49556 DOC#:
Date:
To:
Name
Department
Initials
Date Out
1.
Wendi Hedlund
TPW — review
Jun 30, 2023
2.
Alejandra Ayala
TPW - review
AA
Jun 29, 2023
3.
Raul Lopez
TPW — review
Jul 5, 2023
4.
Lissette Acevedo
TPW — review
Jul 25, 2023
5.
Patricia Wadsack
TPW — review
PLw
Jul 25, 2023
7.
Lauren Prieur
TPW — Signature
Jul 25, 2023
8.
Doug Black
Legal - signature
Jul 27, 2023
9.
William Johnson
CMO - signature
Jul 28, 2023
10.
Jannette Goodall
CSO - signature
,SGTSG
Ju131, 2023
11.
TPW Contracts
TPW
DOCUMENTS FOR CITY MANAGER'S SIGNTURE: All documents received from any and all City
Departments requesting City Manager's signature for approval MUST BE ROUTED TO THE
APPROPRIATE ACM for approval first. Once the ACM has signed the routing slip, David will review and
take the next steps
NEEDS TO BE NOTARIZED: ❑ Yes X No
RUSH: ❑ Yes X No SAME DAY: ❑ Yes ❑ No NEXT DAY: ❑ Yes ❑ No
ROUTING TO CSO: X Yes ❑ No
Action Required:
❑ As Requested
❑ For Your Information
X Signature/Routing and or Recording
❑ Comment
❑ File
❑ Attach Signature, Initial and Notary Tabs
Return To: TPWContracts(o�fortworthtexas.aov at ext. 7233 for pick up when completed.
Aleiandra.Avala(c)..fortworthtexas.aov email executed document when
completed.
I
ICPN:
Project Name:
(Consultant:
I
I Contract
CSN 49556
M&C C-28288 8/17/2017
Amendment No. 1 CSN 28288-A1
M&C C-28764 8/1/2018
t
endment No. 2 CSN 28288-A2
C 20-0361 6/4/2020
Amendment No. 3 CSN 28288-A3
M&C 22-0099 2/8/2022
Amendment No. 4 CSN 28288-A4
M&C 22-0536 6/28/2022
Amendment No. 5 CSN 28288-A5
Administratively approved
JUSTIFICATION OF CONTRACT CHANGES
101012
Cromwell Marine Creek Road Widening Improvements
Burns & McDonnell
Contract Change Total to Date Justification
$400,000.00 Original contract to PS&E for 2 roundabouts
Additional funds to complete PS&E for 2 roundabouts
$ 1,500,000.00 $ 1,900,000.00
Project scope change for PS&E of approx. 2 miles of
$ 790,954.41 $ 2,690,954.41 roadway widening.
Added services for additional traffic signal
analysis/warrant, additional retaining walls, SUE and
$ 311,248.00 $ 3,002,202.41 change delivery method to CMAR.
Add right-of-way acquisition services and additional
$ 259,965.00 $ 3,262,167.41 services for CMAR contract documents development.
Add additional pavement cores of existing asphalt
pavement to determine actual quantity of removal.
$ 23,004.60 $ 3,285,172.01