HomeMy WebLinkAboutContract 59204-PM1FORT WO T H CSC No. 59204-PM 1
PROJECT MANUAL
FOR
THE CONSTRUCTION OF
Trinity Lakes Mixed Use South, Phase I
Water, Sanitary Sewer, Storm Water, Paving, and Lighting Improvements
IPRC No. — 21-0161
City Project No.—103849
FID No. — 30114-0200431-103849-EO7685
X-No. — X-27190
File No. — W-2804
Betsy Price David Cooke
Mayor City Manager
Christopher P. Harder
Director, Water Department
William Johnson.
Director, Transportation and Public Works Department
Prepared for
Trinity Lakes Partners, LLC
PO Box 185105
Fort Worth, TX 76181
DCG Engineering, Inc.
1668 Keller Parkway, Ste 100
Kelley, Texas 76248
EFRN F-21947
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
00 00 00
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Page 1 of 5
SECTION 00 0010
TABLE OF CONTENTS
DEVELOPER AWARDED PROJECTS
Division 00 - General Conditions
nno�3
Last Revised
i
00 41 00
00 42 43
0043 13
lastF ,etiors t Bidde :s
Bid Fefm
Proposal Form Unit Price
Bid Ben
03 0
nn in s
05/22/2019
nn in 4
nno n�=
Bidde :s Pf:eq, alifieatiea's
Prequalification Statement
nn in 4
09/01/2015
00 45 12
00 45 26
Contractor Compliance with Workers' Compensation Law
i
04/02/2014
nQ i
004540
00 52 43
Mine -ity Business Enterprise Ge
Agreement
a
06/16/2016
00 61 25
Certificate of Insurance
07/01/2011
00 62 13
Performance Bond
01/31/2012
00 62 14
Payment Bond
01/31/2012
00 62 19
00 7200
Maintenance Bond
Genef.,i Conditions
01/31/2012
i ii ii T
00 73 00
0073 10
c,,,.,.io,,.,eata y r,,.,difi np
Standard City Conditions of the Construction Contract for Developer
n7inm�vzi
01/10/2013
Awarded Projects
Division 01- General Requirements
Last Revised
01 1100
Summary of Work
12/20/2012
01 25 00
Substitution Procedures
08/30/2013
01 31 19
Preconstruction Meeting
08/30/2013
813129
01 32 33
Pr-eieet Meet*-
Preconstruction Video
07101/2
08/30/2013
01 33 00
Submittals
08/30/2013
01 35 13
Special Project Procedures
08/30/2013
01 45 23
Testing and Inspection Services
03/20/2020
01 50 00
Temporary Facilities and Controls
07/01/2011
01 5526
Street Use Permit and Modifications to Traffic Control
07/01/2011
0157 13
Storm Water Pollution Prevention Plan
07/01/2011
01 60 00
Product Requirements
03/20/2020
01 66 00
Product Storage and Handling Requirements
04/07/2014
01 70 00
Mobilization and Remobilization
04/07/2014
01 71 23
Construction Staking
04/07/2014
01 74 23
Cleaning
04/07/2014
0177 19
Closeout Requirements
04/07/2014
01 78 23
Operation and Maintenance Data
04/07/2014
01 78 39
Project Record Documents
04/07/2014
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS —DEVELOPER AWARDED PROJECTS City Project No. 103849
Revised March 20, 2020
00 00 00
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Page 2 of 5
Technical Specifications which have been modified by the Engineer specifically for this
Project; hard copies are included in the Project's Contract Documents
None
Technical Specifications listed below are included for this Project by reference and can be
viewed/downloaded from the City's website at:
http://fortworthtexas.2ov/tuw/contractors/
or
httDs:Happs.fortworthtexas.2ov/Proi ectResources/
Division 02 - Existing Conditions Last Revised
0241 13 Selective Site Demolition 12/20/2012
02 4414 U44it-y n o,,,ey f i n i..,,.defff,,oi 2i�tz
0241 15 Paving Removal 02 ins;,
Division 03 - Concrete
03 30 00 Cast -In -Place Concrete 12/20/2012
03 34 13 Controlled Low Strength Material (CLSM) 12/20/2012
03 34 16 Concrete Base Material for Trench Repair 12/20/2012
83-89-08 Medifiea4ie 0 Ey��angCcr\���o Ftvmotur-es
Division 26 - Electrical
26 05 00
Common Work Results for Electrical
11/22/2013
26 05 10
sv-v�v
1 c
l�:/�'�Ittl�°1 �A ,..�IJL�'7��1 Fl��t2ii�S
12 20,L2012
��
26 05 33
Raceways and Boxes for Electrical Systems
12/20/2012
26 05 43
Underground Ducts and Raceways for Electrical Systems
07/01/2011
Division 31-
Earthwork
31 1000
Site Clearing
12/20/2012
3123 16
Unclassified Excavation
01/28/2013
31 23 23
Borrow
01/28/2013
312400
Embankments
01/28/2013
312500
Erosion and Sediment Control
12/20/2012
,
3 -1 3600
31 37 00
+GabiefiS
Riprap
2rc/20a012
12/20/2012
Division 32
- Exterior Improvements
Z 7�T
�r�~�nt �scxhll,t P`v irr� LL�sai,r
1 2 20/-2014
��
3'�o
Temper-af Aophalt N- ving Repair
12 /�Q
32 01 29
Concrete Paving Repair
12/20/2012
32 1123
Flexible Base Courses
12/20/2012
32 1129
Lime Treated Base Courses
12/20/2012
32 1133
,z
�, 11 3., ,-
Cement Treated Base Ce
r ;,,,,;a Tfea4e c ,
oil f.'t�✓'.li��
12/20/-2012
0 9/21 01 c
32 1216
Asphalt Paving
12/20/2012
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS —DEVELOPER AWARDED PROJECTS City Project No. 103849
Revised March 20, 2020
00 00 00
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Page 3 of 5
32 1273
Asphalt Paving Crack Sealants
12/20/2012
32 13 13
Concrete Paving
12/20/2012
32 1320
Concrete Sidewalks, Driveways and Barrier Free Ramps
06/05/2018
32 1373
Concrete Paving Joint Sealants
12/20/2012
32 14 16
Rr4ck _kx1 t 1W,
1'f1 /' z
32 16 13
Concrete Curb and Gutters and Valley Gutters
10/05/2016
32 1723
Pavement Markings
11/22/2013
32 1725
Curb Address Painting
11/04/2013
3231 3
27�0
Crnr F��r� a Gates
W; .o Fences and G es
�>z 12/2n/2n12
12/20,L2012
27�9
3232 13
Weed Fences and Gates
C" k- P.Vae Gone.ote Retaining W.,
12/20,L2012
06/no 542
3291 19
Topsoil Placement and Finishing of Parkways
12/20/2012
32 92 13
37�3•
Hydro -Mulching, Seeding, and Sodding
Tf:ees and Sl..ubs
12/20/2012
12/'fizrzvriviz
Division 33 -
Utilities
33 01 30
Sewer and Manhole Testing
12/20/2012
33 0131
Closed Circuit Television (CCTV) Inspection
03/03/2016
Z Z�v
%-paw Du.� ing „F Existing Sewer- Systems
1 2 /'fr�-zvriviz
33 04 10
33 04 }
Joint Bonding and Electrical Isolation
r,.,...esien r nt el Tort Stafiens
r,ragnesiti r.,tt,edie Systeffl
12/20/2012
12/7 z
33 04 12
33 04 30
33 04 40
Anode Pfete tie
Tempefur- , Water- Seta,;,
Cleaning and Acceptance Testing of Water Mains
12/20,L2012
0�nQ/„ 1�n
02/06/2013
33 04 50
Cleaning of Sewer Mains
12/20/2012
3305 10
Utility Trench Excavation, Embedment, and Backfill
T
12/12/2016
3305 12
3305 13
Water- Line ,...,ofin
Frame, Cover and Grade Rings — Cast Iron
12/20,L2012
01/22/2016
33 05 13.10
Frame, Cover and Grade Rings — Composite
01/22/2016
33 05 14
Adjusting Manholes, Inlets, Valve Boxes, and Other Structures to
12/20/2012
Grade
rea Vaults
1
110
33 05 17
ef:ete Water-
Concrete Collars
2/'frz�-zvriviz
12/20/2012
33 05 20Aiiger-12/20a012
330521
Tu.—mOl Lrr emote
12 /'�tz
33-0522
330523 23
gteel-Cac �iv, Pir,a
Hand T,m eli*g
11 /�12
12/'fez
33 05 24
33 05 26
lasta hate,, - Pipe i Casing (.. Tunnel Liner- or nla4-e
f G
06/lovr19QO13
12/20/2012
E) Fie
Utility Markers/Locators
33 05 30
Location of Existing Utilities
12/20/2012
33 1105
Bolts, Nuts, and Gaskets
12/20/2012
33 11 10
33 11 11
Duet;le i-en 12ip-e
Ductile Iron Fittings
12/'fez
12/20/2012
33 11 12
Polyvinyl Chloride (PVC) Pressure Pipe
11/16/2018
?✓3 11 13
Ceneret3 Prowuro Piro, Baf IALFapped, Stool Cylindef Type
11 /�12
12/'fez
33 11 14
33 12 10
33 }
Burie Steel Pipe and Fittings
Water Services 1-inch to 2-inch
Large ge Water- r, eter-s
02/14/2017
12/20,9012
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS -DEVELOPER AWARDED PROJECTS City Project No. 103849
Revised March 20, 2020
00 00 00
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Page 4 of 5
33 1220
Resilient Seated Gate Valve
b,b Nl
12/20/2012
33 12 21
33 1225
AWW-A R ef: Seated Butte.-f1.,
Connection to Existing Water Mains
Q/20aoQ
02/06/2013
33 1230
. Potable .,tef Syst^. �
Ge 1 iaa4ie Aif V^l.,^ kaae iWkas f xx�
11 /�12
33 1240
Fire Hydrants
01/03/2014
ZZ�no
33 12 60
cI'a4 z,�,-). St^ iens
St.,ndai-7,1 Blew ,.FFValve Assembly bly
12/20/2012
06/1 3
3331 2
33 31 3
n,,.^a in Dlaee Pipe (rmn)
Fibefs1w0 P OCf r e Pipe F. r -a-y t.��'i1�7y�2Vers
12/�12
11 /12
'_'Z ?% ks
High Pefisit-y Pelyethylene (14PPE) Pipe acx��—der
12/'f�zrzvriviz
33 31 20
Polyvinyl Chloride (PVC) Gravity Sanitary Sewer Pipe
06/19/2013
33 3121
Fmit ry of
Ripe
r12r20r/2012
ZZ 21 ��
7TJTLz
Safi t^,.. Sewo c r '
nA112GATy"C7G�Pv��l/�Y �%.���g
12/2n/2n12
1�1Z
12/'fr�-zvriviz
33 31 23
33 31 50
Sa-n ta-y Sewer- Pipe E.- la-..om^
Sanitary Sewer Service Connections and Service Line
04/26/2013
333170
33 39 10
Cembinatien Air- Va4ve fer- Sa-mitafy Sewer Force Mains
Cast -in -Place Concrete Manholes
12/20a012
12/20/2012
33 39 20
Precast Concrete Manholes
12/20/2012
33 39 40
33 39 60
Write,.,^ . n eeess Chamber- (WAG) G)
Epoxy Liners for Sanitary Sewer Structures
11 / 0a
12/20/2012
3341 10
Reinforced Concrete Storm Sewer Pipe/Culverts
07/01/2011
l.. 11 11
High Defisit-y Polyethylene (14PPE) Pipe F T� ,- Storm Jrx.:4
12/'fez
,-2 11 12
Reinfer-eed Pelyetl.len ERPE) P*a
/
1 1 /1 5
11 /�12
33 4600
33 4601
��i ge
SleAed St3rm D"A�,rc.
n�/no 1�n
�4H--02
�arr�is �u�r�
n�/n1 /2n1 1
,n
3349 10
Cast -in -Place Manholes and Junction Boxes
12/20/2012
33 49 20
Curb and Drop Inlets
12/20/2012
33 49 40
Storm Drainage Headwalls and Wingwalls
07/01/2011
Division 34
2A�o
- Transportation
Tf:affie Sign lss
11 n/1015
24 41 10.011
34�02
Attraehmeat A �E+efAfeller- Cabine
At a eat Gentf.ol.V"1 E-roaifie i va
Atttaehmeat G Seft'V awe Speeifiea-tien
T^,v.pe-a-., T,-.,Ff;e Signals
12/i�t1_5
OV2012
01,L2012
11 /'fn 22,L2013
34� 41-10.03
34�-41-11
34 41 13
?/1 11 if
D o,ti.... ing Traffi . Signals
Reetalgula is/.d FkaahingBeaean
1 2 /'lzzr20a012
1111 /'� =013
34 416
Redou*�aA I-I;bfid-Sigoa4
11 /fin
34 41 20
Roadway Illumination Assemblies
12/20/2012
3 n nano l=
Artorlll. T �T�T.� Via, T �amil�vr�rs
0645,L2015 �
3n n�02
l ..noway LED n,,.,dw
06/10 c�1�5
2n n�no3
r � r �ii���o
dl >1 n ^a..,.,.,
0orfti� 6/15a01�_5
34 41 30
Aluminum Signs
TiT.,.ae !'able
11/12/2013
4 4150
3471 13
Single Fite- Opt;,,
Traffic Control
02/moo
11/22/2013
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS -DEVELOPER AWARDED PROJECTS City Project No. 103849
Revised March 20, 2020
00 00 00
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Appendix
Page 5 of 5
GG4,91
Ac�Lulity e
Fib-4.02
E,ubmr e ��r .,,a;�;
GG 4.06
Lac., .dour Eiwir-enfnental Condition . 4 S4e
GG 6..0.6.D
n d ✓winrjoo Er. -Pr rjo Cemplianee
GG 6.07
GG 6.09
D,,.mits and U444ies
1
1`Oxdisarimryatiox
GR-01 60 00 Product Requirements
City of Fort Worth Water Department Standard Products
END OF SECTION
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS —DEVELOPER AWARDED PROJECTS City Project No. 103849
Revised March 20, 2020
BIDDER'S APPLICATION
UNIT PRICE BID
SECTION 00 42 43
Developer Awarded Projects - PROPOSAL FORM
Project Item Information
poa4a
DAP -No PROPOSAL
Page l of7
Bidder's Application
fiddor, Propoaal
BidLst Item SPwlflcauon Umt of Bid
Description Umt Pace Bld Vvue
No. 81cDon ND Measure Quanary
UNIT I: WATER IPR(jME B\
4
3311.0261 8" PVC Water Pipe
F
5749
$53,25
_ 2_
3312,3003 8" Gate Valve
33 1220
EA
46
$2,100.00
3
33110001 Ductile Iron Water Fittings w/Restraint
33 11 11
Ton
8
$9,500.00
- 4
3312.2003 1"Water Service
331210
FA
187
$1,145.00
5 _
9999.0002 2" Auto Flushing Device
00 00 00
FA
6
$8,350.00
6
_
33050109 Trench Safety
330510
_
LF
_
5789
$0.25
7
3312.0001 Fire Hydrant _ _
331240
EA
4
$5,900.00
_ 8
_
3312,3002 6" G V
331220
EA
4
$1,42500
9
3312,0117 CONN. TO EX 4"-12" WATER LINE
33 12 25
EA
1
$3,925 00
10
3311 0264 8" PVC Water Pipe, CLSM BACKFILL
33 11 12
LF
40
$53,25
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
29
30
32
33
34.
35
38
37
38
39
40
41
42
TOLL. UNIT I: WAA� IMPROVEMENTS
$306,134,25
$96,600 00
$57,000 00
$214,115 00
$50,100.00
$1,447 25
$23,600,00
$5,700.00
$3,925.00
$2,130.00
$760,751.501
=m, PO0.T WORTH loo, Ld- Miui Oae So.F a-1
STANDAROfONSF0.VLT10N 5PEC61fAT10N OOCVMEMS-oEVELOPERAWARDEOPR01ER5 Llry PwlexNo - InlYA9
Fonn Vmion M1ley E3. 3019 poll43 aitl Pmpal DAPekl
on,il.
DAP. RID PROPOSPL
oe on
SECTION 00 42 43
Developer Awarded Projects - PROPOSAL FORM
UNIT PRICE BID Bidder's Application
Projca Item loformaaon
Blddeh Proposal
Description
Specda
Unit
Zf I
Unit PaceI
Bid ValueOIJLsIImm
NoNo
Section
Meaa
QBld ty
fi
JJ
UNIT II: SANITARY3:AAWER IMPROV'MENTS
1
3331
4115
6" Sewer Pipe
3311 10,33
LF
2084
$60.00
$125,040.00
2
3331
4116
8" Sewer Pipe w/CSS Ball
3311 10, 33
LF
100
$78.00
$7,800.00
3
3339.1001
4' Manhole
33 39 10, 33
_
EA
31
$6,800AO
$210,800.00
4
3339.0001
Epoxy Liner for Manhole_
333960
_
_ _
102
_
$466.00
$47.53200
5
3331.3101
4" Sewer Service
3331 50
_ _VF _
EA
187
$1,225.00
$229,075.00
6
3301.0101
Manhole Vacuum Testing
330130
EA
37
$165.00
$6,10500
7
3301,0002
Post -CCTV Inspection
330131
LF
_
5956
_
$5.50
$32,758.00
8
33050109
Trench Safety
330510
LF
5956
$2,25
$13,40100
9
3331.575315"
SEWER PIPE, CLSM BACKFILL
33 11 10,33 31
LF
830
$16717
$138,751A0
10
3331.420812"SEWER
PIPE
331110
LF
2022
$86,50
$174,903.00
17
3331
5751
12" SEWER PIPE, CLSM BACKFILL
3331 20,33
LF
920
$131 00
$120,520.00
12
3339.1101
5" CIA MH
333910
EA
8
_
$12,500,00
_
$75.000.00
t8
14-
15
16
17-
18-
19-
26
21
22
—
--- --
23
24_-
25
26
27
28
29
30
31
32
33
34
35
36
- -
3]
38
39
_..
-
40
41
42
43
44
TOTAL UNIT II: SANITARY
SEWER IMPRO"EMEN7_91
$1,181,685A0
CRYOPFORT waem To,i, r,,ka Mimi Ua Seet. flwe I
STArl A CONSTRUCTION SPECMCKaON DOCUMENTS- DEVELOPER AWARDED PROrECTS c.,no-Iratio
Fmm Vmm My2Z MI 00 42 4] ei Pmpp DAPc I
one. am BeoFosu.
POBal ar]
SECTION 00 42 43
Developer Awarded Projects - PROPOSAL FORM
UNIT PRICE BID Bidder's Application
Project Item lnformauon I Biddees Proposal
&dint Item)
Description
I Spe
unit of
I Bid
Unit Price
Bid Value
No,
SBUmecarion
ion .
No
Me asure
Q1Bnfiy
UNIT III: DRAINATN1PjjOVEM{NTS�
1
3349.5001 10' CuM Inlet
A �'1Ba
_ 6
$7,150.00
$42,900.00
__ 2
3341.0409 48" RCP, Class III
334110
LF
78
$293.00 _
_$22,854,00
3
9999.0003 42" HE STORM PIPE
000000
LF
_
508
$168 00
$85,344,00
4
9999 0004 30" HP STORM PIPE
000000
LF
273
$132.00
$38,038.00
5
9999.000530"HP STORM PIPE
000000
LF
239
$107.00
$25,57300
6
3349.0003 6'Stom Junction Box
334910
EA
1
$17,000,00
$17,000,00
7
3349.00014'Slorm Junction Box
334910
FA
2
$5,450.00
$10,900.00
8
3349,0002 5' Storm Junction Box
_
33 49 10 -
_
EA
1
$6,600.00
$6,600.00
9
3349.410730"SET, I PIPE
334940
FA
1
$3,70000
$3,700.00
10
3349.90034' Grate Inlet
334920
EA
1
$10,850.00
$10,850.00
11
3305.0109 Trench Safety
330510
LF
1098
$050
$549.00
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
-
-.
...
42
43
TOTAL UNIT III: DRAINAG-IMPRO? VEMENTSI$262.306.001
CU,, OF IORT WORT. Trims M;W us. nw0, Fri— I
STANDARD CONSTROCTON S V MCATION DOCUMENTS-Mvs n AWARDED FROIECTS City floral No -, na.9
Fo" Versmn May II,2019 00 42 43_Bid Papul_DAP ORI
UNIT PRICE BID
Bldiidl Iteml
N.
1
2
3
4
5
6
7
8
9
10
11
12
13
SECTION 00 42 43
Developer Awarded Projects - PROPOSAL FORM
Project Rem Infprmatmn
.o.
OM-0a)VRO10SAL
R 4M7
Bidder's Application
Bidders Proposal
Oescnpnon l Spec16cation Unn of I Bid l List Price III Bid Value
S tlon No. Measure Q..dW
UNIT IV:. PAVING Ih1P$QVEMIi
3213 0101 6" Conc Pvmt
3211.0502 8" Lime Treatment_
3211 0400 Hydrated Lime
3213.0006 Barrier Free Ramp, Type P-1
3305.0107 Manhole Adjustment, Minor
9999.0006 Traffic Control (Dead End Barricade)
9999 0001 Traffic Signs / Pavement Markings
3471.0001 General Traffic Control
3292.0400 Seeding, Hydromulch
3291.0100 Topsoil
3137 0104 Medium Stone Riprap, dry
3212.0401 HMAC Transition
_ 33050111 VALVE BOX ADJUSTMENT
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44 _
45
14713._
$75.88
$1,116.422.44
321129
SY
16087
_
_ $3.50
$56304.50
321129
TON
289.57
_ $264,00
$76.446.48
321320
FA
7
_ $3,17143
$22,20000
33 05 14
EA
30
$500.00
$15,000.00
000000
EA
4
$2,050 00
$8,200 00
000000
_ LS
1
$26,275.00
$26,275,00
347113
MO
7
$825,00
$5,775.00
329213
BY
12950
$0.50
$6,475.00
329119
CY
1530
$10,00
$15,300,00
31 3700
BY
4IA379
$135.02
$6,000.00
32 12 16
BY
167
$115,00
$19,205.00
330514
EA
44
$250.00
$11, 000.00
TOTAL JNIT IV: PAVIN3 IMPROVEMENTS
$1,384,603.42,
CRY OF FORT WORTH T-,. Milw. SONh, Mm 1
STANDARD CONST =ON SPECIFICATION DOCOMENTS- DEVELOPER AWARDED FRORTms Ory R%a1 0w-1ai
F.-Version M., It. .II W 4341 aid Fropmet_OM[RI
00 42 43
DAP - BID PROPOSAL
Page 5 of 7
SECTION 00 42 43
Developer Awarded Projects - PROPOSAL FORM
UNIT PRICE BID Bidder's Application
Project Item Information Bidder's Proposal
Bidlist Item
Description
Specification
Unit of
Bid
Unit Price
Bid Value
No.
Section No.
Measure
Quantity
UNIT V: STREET LIGHTING
IMPROV MENTS
1
3441.3301 Rdwy Illum Foundation TY 1.2 and 4
3441 20
EA
13
$1,500.00
$19,500.001
2
3441.3002 Rdwy Illum Assembly TY 8,11,D-25
3441 20
EA
13
$2,383.00
$30,979.001
3
3441.3104 150w MH PC Lighting Fixture
3441 20
EA
13
$692.00
$8,996.001
4
2605.3015 2" Conduit PVC SCH 80
26 05 33
LF
4096
$18.09
$74,096.641
5
3441.1409 No 8 Insulated Elec Condr
3441 10
LF
12288
$1.59
$19,537.921
6
3441.1501 Ground Box Type B
3441 10
EA
32
$668.00
$21,376.001
7
3441.3037 Furnish/Install 10'-14' Washington Standard
3441 20
EA
33
$4,868.00
$160,644.001
8
3441.3303 Rdwy Foundation TY 7
3441 20
EA
33
$1,500.00
$49,500.001
9
3441.1771 Furnish/Install 120-240 Volt Single Phase Me 34 41 20
EA
1
$10,400.00
$10,400.001
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
I 29
30
31
32
33
34
35
36
37
38
I 39
40
41
42
43
44
45
TOTAL UNIT V: STREET LIGHTING IMPROVEMENTS
$395,029.561
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS City Project No. - 103849
Form Version May 22, 2019 00 42 43_ahv Bid Proposal_DAP cta.xls
UNIT PRICE BID
Sidlist Item
No.
SECTION 00 42 43
Developer Awarded Projects - PROPOSAL FORM
Project item Information
Description
004241
OAP - BID PROPOSAL
Page y of 7
Bidder's Application
@iddce� Proposal
Specification I urk of I raid `
Section No, Measure Quantity Unit Price Bid Value II
Sid Sum nsary
UNIT 1; WATER IMPROVEMENTS
UNIT 11: SANITARY SEWER IMPROVEMENTS
UNIT III: DRAINAGE IMPROVEMENTS
UNIT IV: PAVING IMPROVEMENTS
UNIT V: STREET LIGHTING IMPROVEMENTS
UNIT VI: TRAFFIC SIGNAL IMPROVEMENTS
Total Construriion Rill
Contractor agrees to complete WORK for FINAL ACCEPTANCE within
CONTRACT cam men ces to run as provided in the Gen cral Conditions.
END OF SECTION
$760,751.50
$1,181,585.1 Q
$262,306,00
$1, 384,603.42
$395, 029.56
$3,984,375,58
1211 working days after the date when the
CrrV OF FORT WORTH
ST ANDARD CONSTRUCTION SPECMCA TION DO -CUM ENTS - DEW LOPE R ,A W ARDE D PROJEC TS
Form Version play 22, 2019
Tnmly L L" Mixed Use So, th, Phue I
City ftja l No - IWS49
0042 43_Bid Proposal_DAP era 1
UTILITIES
WALKER UTILITIES
00 45 12
DAP PREQUALIFICATION STATEMENT
Page 1 of 1
SECTION 00 4512
DAP — PREQUALIFICATION STATEMENT
Each Bidder is required to complete the information below by identifying the prequalified contractors
and/or subcontractors whom they intend to utilize for the major work type(s) listed. In the "Maior Work
Tvve" box Drovide the complete maior work tvDe and actual description as Drovided by the Water
Department for water and sewer and TPW for Davins.
Major Work Type Contractor/Subcontractor Company Name Prequalification
Expiration Date
Water New Development Open Walker Utilities 1/31/2024
Cuts (all sizes); Wastewater
New Development Open Cuts
(all sizes)
The undersigned hereby certifies that the contractors and/or subcontractors described in the table above
are currently prequalified for the work types listed.
BIDDER:
Walker Utilities, Inc. BY: Gary Walker
124 Brown Trail
Hurst, Texas 76053
(Signattilre)
TITLE: cn4'
DATE: I I / Z 3/z Z
END OF SECTION
CITY OF FORT WORTH
STANDARD CONSTRUCTION PREQUALIFICATION STATEMENT— DEVELOPER AWARDED PROJECTS
00 45 12_Prequalification Statement 2015—DAP Utilities.docx
Form Version September 1, 2015
1
SECTION 00 52 43
00 52 43 - 1
Developer Awarded Project Agreement
Pagel of4
2 AGREEMENT
3 THIS AGREEMENT, authorized on llJ231 27- is made by and between the Developer,
4 Trinity Lakes Partners, LLC, authorized to d❑ business in Texas ("Developer"), and Walker
5 Utilities, authorized to do business in Texas, acting by and through its duly authorized
6 representative, ("Contractor").
7 Developer and Contractor, in consideration of the mutual covenants hereinafter set forth, agree as
8 follows:
9 Article 1. WORK
10 Contractor shall complete all Work as specified or indicated in the Contract Documents for the
1I Project identified herein.
12 Article 2. PROJECT
13 The project for which the Work under the Contract Documents may be the whole or only a part is
14 generally described as follows:
I5 Trinhi Lakes Miyed Vse Swah, Phase 1
16 C'itt, Proiect No. - 103849; XNo.-X-27190. FID 1Vo. - 3011-1-0200431-103X49-F0
17 File .No. - l3'-2804
18 Article 3. CONTRACT TEVIE
19 3.1 Time is of the essence.
20 All time limits for Milestones, if any, and .Final Acceptance as stated in the Contract
21 Documents are of the essence to this Contract.
22 3.2 Final Acceptance.
23 The Work will be complete for Final Acceptance within ! D6 working days after the
24 date when the Contract Time commences to run as provided in Paragraph 32.04 of the
25 Standard City Conditions 4 the Construction Contract for Developer Awarded Projects,
26 3.3 Liquidated damages
?7
28
29
30
31
32
33
34
35
36
37
Contractor recognizes that time is of the essence of this Agreement and that Developer
will suffer financial loss if the Work is not completed within the times specified in
Paragraph 3.2 above, plus any extension thereof allowed in accordance with Article 10 of
the Standard City Conditions of the Construction Contract for Developer Awarded
Projects. The Contractor also recognizes the delays, expense and difficulties involved in
proving in a legal proceeding the actual loss suffered by the Developer if the Work is not
completed on time. Accordingly, instead of requiring any such proof, Contractor agrees
that as liquidated damages for delay (but not as a penalty), Contractor shall pay
Developer One thousand Dollars ($1, 000.00) for each day that expires after the time
specified in Paragraph 3.2 for Final Acceptance until the City issues the Final Letter of
Acceptance.
CRY OF FORT WORTH I i'�r1rl !. rd'.s i Itirrd ! ea .Srr1111l. Pltuar T
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS— DEVELOPER AWARDED PROJECTS r rh Po•oxcl ko. - 103 411
Revised June 16, 2016
005243-2
Developer Awarded Project Agreement
Page 2 of 4
38 Article 4. CONTRACT PRICE
39 Developer agrees to pay Contractor for performance of the Work in accordance with the Contract
40 Documents an amount in current funds of 7-wo M i «! oil +Q o h dndred aA4 Avr Dollars
41 ($ -Z zoq 7if� ' }. +- o ie^A4 Sedei AmJrcd -Fbr- -'4-oo J.11 rs -%d SIk
42 Article 5. CONTRACT DOCUMENTS
43 5.1 CONTENTS:
44
A. The Contract Documents which comprise the entire agreement between Developer and
45
Contractor concerning the Work consist of the following:
46
1.
This Agreement.
47
2.
Attachments to this Agreement:
48
a. Bid Form (As provided by Developer)
49
1) Proposal Form (DAP Version)
50
2) Prequalification Statement
51
3) State and Federal documents (project specific)
52
b. Insurance ACORD Form(s)
53
c. Payment Bond (DAP Version)
54
d. Performance Bond (DAP Version)
55
e. Maintenance Bond (DAP Version)
56
f. Power of Attorney for the Bonds
57
g. Worker's Compensation Affidavit
58
h. MBE and/or SBE Commitment Form (If required)
59
3.
Standard City General Conditions of the Construction Contract for Developer
60
Awarded Projects.
61
4.
Supplementary Conditions.
62
5.
Specifications specifically made a part of the Contract Documents by attachment
63
or, if not attached, as incorporated by reference and described in the Table of
64
Contents of the Project's Contract Documents.
65
6.
Drawings.
66
7.
Addenda.
67
8.
Documentation submitted by Contractor prior to Notice of Award.
68
9.
The following which may be delivered or .issued after the Effective Date of the
69
Agreement and, if issued, become an incorporated part of the Contract Documents:
70
a. Notice to Proceed.
71
b. Field Orders.
72
c. Change Orders.
73
d. Letter of Final Acceptance.
74
75
CITY OF FORT WORTH h• nn- blArs Mixed l+u sonlih. Ploor 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS till Proier7 No. - 10384V
Revised June 16. 2Q16
00 52 43 - 3
Devaioper Awarded Project Agreement
Page 3 of 4
76 Article 6. INDEMNIFICATION
77 6.1 Contractor covenants and agrees to indemnify, hold harmless and defend, at its own
78 expense, the city, its officers, servants and employees, from and against any and all
79 claims arising out of, or alleged to arise out of, the work and services to be performed
80 by the contractor, its officers, agents, employees, subcontractors, licenses or invitees
81 under this contract. This indemnification provision is specifically intended to overate
82 and be effective even if it is alleged or vroven that all or some of the damages being
83 sought were caused, in whole or in Dart, by anv act, omission or negligence of the city.
84 This indemnity provision is intended to include, without limitation, indemnity for
85 costs, expenses and legal fees incurred by the city in defending against such claims and
86 causes of actions.
87
88 6.2 Contractor covenants and agrees to indemnify and hold harmless, at its own expense,
89 the city, its officers, servants and employees, from and against any and all loss, damage
90 or destruction of property of the city, arising out of, or alleged to arise out of, the work
91 and services to be performed by the contractor, its officers, agents, employees,
92 subcontractors, licensees or invitees under this contract. This indemnification
93 provision is specifically intended to overate and be effective even if it is alleged or
94 proven that all or some of the damages beins sought were caused. in whole or in Dart.
95 by anv act, omission or negligence of the city.
96
97 Article 7. MISCELLANEOUS
98 7.1 Terms.
99 Terms used in this Agreement are defined in Article I of the Standard City Conditions of
100 the Construction Contract for Developer Awarded Projects.
101 7.2 Assignment of Contract.
102 This Agreement, including all of the Contract Documents may not be assigned by the
103 Contractor without the advanced express written consent of the Developer.
104 7.3 Successors and Assigns.
105 Developer and Contractor each binds itself, its partners, successors, assigns and legal
106 representatives to the other party hereto, in respect to all covenants, agreements and
107 obligations contained in the Contract Documents,
108 7.4 Severability.
109 Any provision or part of the Contract Documents held to be unconstitutional, void or
110 unenforceable by a court of competent jurisdiction shall be deemed stricken. and all
III remaining provisions small Continue to be valid and binding upon DEVELOPER and
11.2 CONTRACTOR,
113 7.5 Governing Law and Venue.
114 This Agreement, including all of the Contract Documents is performable in the State of
115 Texas. Venue shall be Tarrant County, Texas, or the United States District Court for the
116 Northern District of Texas, Fort Worth Division.
CITY OF FORT WORTH I cowi 1.uhr s A1i.sr r1 I r,, I
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS r 'ir+ MvIevr No. - 111AS4Q
Revised June 16, 2016
117
118
119
120
121
122
123
124
125
126
127
00 52 43 - 4
Developer Awarded Project Agreement
Page 4 of 4
7.6 Authority to Sign.
Contractor shall attach evidence of authority to sign Agreement, if other than duly
authorized signatory of the Contractor.
IN WITNESS WHEREOF, Developer and Contractor have executed this Ag' eement in multiple
counterparts.
This Agreement is effective as of the last date signed by the Parties ("Effective Date" ).
Contractor: Walker Utilities, Inc. Developer: Trinity Lakes Partners, LLC
rr6)�
By:
(Signature) (Signature)
Brandon Walker Kenneth B. Newell
(Printed Name) (Printed Name)
Title: Vice President
Company Name: Walker Utilities, Inc.
Address: 124 Brown Trail
City/StatelZip: Hurst, TX 76053
1112-3
Date
Title. Member
Company name: Trinity Lakes Partners, LLC
Address: PO Box 185104
City/State/Zip: Fort Worth, TX 76181
it
Date /
CITY OF FORT WORTH Trrurn L rl•r Al .srrll'u 1 rrrlh 1'!r +ar I
STANDARD CONSTRUC-LION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS { -rr, I11„j„ r V„ - lrtir rU
Revised June 16.2016
0062 13- 1
PERFORMANCE BOND
Page 1 of 2
Bond #4450877
t SECTION oo 62 13
PERFORMANCE BOND
3
4 THE STATE OF TEXAS §
5 § KNOW ALL BY THESE PRESENTS:
6 COUNTY OF TARRANT §
7
8 That we. Walker Utilities. Inc. , known as "Principal"
9 herein and SureTec Insurance Company a corporate surety(sureties, if
10 more than one) duly authorized to do business in the State of Texas, known as "Surety" herein
I I (whether one or more), are held and firmly bound unto the Developer, Trinitp Lakc� Partners.
12 LLC, authorized to do business in Texas ("Developer") and the City of Fort Worth, a Texas
13 municipal corporation ("City"), in the penal sum of,
Two Million Two Hundred Four Thousand Seven Hundred
14 Forty-two and 60/100"" Dollars ($ 2,204,742.60' i.
15 lawful money of the United States, to be paid in Fort Worth, Tarrant County, Texas for the
16 payment of which sum well and truly to be made jointly unto the Developer and the City as dual
17 obligees, we hind ourselves, our heirs, executors. administrators, successors and assigns, jointly
I8 and severally, firmly by these presents.
19 WHEREAS, Developer and City have entered into an Agreement for the construction of
20 community facilities in the City of Fort Worth by and through a Community Facilities
3) Agreement, CFA Number CFA 12-1077,and
22 WHEREAS, the Principal has entered into a certain written contract with the Developer awarded
23 the 23rd day of November , 20 22 , which Contract is hereby referred to and made a
24 part hereof for all purposes as if fully set forth herein, to furnish all materials, equipment labor
25 and other accessories defined by law, in the prosecution of the Work. including any Change
26 Orders, as provided for in said Contract designated as T) inin 1.akt,► Afi.ked [ 'i,r .5wirl& Phan , 1
27 NOW, THEREFORE, the condition of this obligation is such that if the said Principal
28 shall faithfully perform it obligations under the Contract and shall in all respects duly and
29 faithfully perform the Work, including Change Orders, under the Contract, according to the plans,
30 specifications, and contract documents therein referred to, and as well during any period of
31 extension of the Contract that may be granted on the part of the Developer and/or City, then this
32 obligation shall be and become null and void. otherwise to remain in full force and effect.
CITY OF FORT WORTH r r+0,+e, f. to +h -i,+n
STANDARD CITY CONDrr14NS - DEVELOPER AWARDED PROJECTS 1' •,+, r 1. �
Revised January 31, 2012
006213-2
PERFORMANCE BOND
Page 2 of 2
i PROVIDED FURTHER, that if any Iegal action be filed on this Bond, venue shall lie in
Tarrant County, Texas or the United States District Court for the Northern District of Texas, Fort
Werth Division.
4 This bond is made and executed in compliance with the provisions of Chapter 2253 of the
5 Texas Government Code, as amended, and all liabilities on this bond shall be determined in
6 accordance with the provisions of said statue,
7 IN WITNESS WHEREOF, the Principal and the Surety have SIGNED and SEALED
8 this instrument by duly authorized agents and officers on this the 29th day of
9 November 20 22
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
ATTEST:-
W�J�
(Principal) Secretary
'��Q�C1il�.C.t2� �C7CL
Witness as to Principal
G 0711
Witnes. as 10 Surety rystal Langhorn
PRINCIPAL:
Walker Utilities, Inc,
BY:
Signature
Brandon Walker. Vice President
Name and Title
Address: 124 Brown Trail
Hurst_ TX 76053
SURETY:
SureTec Insurance Comoanv
BY_ ?� 1k," fli
Signature
Elena Sells, Attorney -in -Fact
Nance and Title.
Address: 2103 CityWest Blvd., Suite 1300
Houston, TX 77042
Telephone Number: 713-812-0800
'Note: If signed by an officer of the Surety Company, there must be on file a certified extract
from the by-laws showing that this person has authority to sign such obligation. If
Surety's physical address is different from its mailing address, both must be provided.
The date of the bond shall not be prior to the date the Contract is awarded.
CITY OF FORT WORTH tf,„,! i „
STANDARD CITY CONDITIONS -DEVELOPER AWARDED PROJECTS rr 1 0.
Revised January 31. 2012
006214-1
PAYMENT BOND
Page I of?
Bond #4450877
1 SECTION oD 62 14
2 PAYMENT .BOND
3
4 THE STATE OF TEXAS §
i § KNOW ALL BY THESE PRESENTS:
b COUNTY OF TARRANT §
7 That we, Walker Utilities, Inc. , known as
8 "Principal- herein, and SureTec Insurance Company , a
9 corporate surety ( or sureties if more than one), duly authorized to do business in the State of
to Texas, known as "Surety" herein (whether one or more), are held and firmly hound unto the
1 1 Developer. Trinity Lakes Partners, LLC, authorized to do business in Texas "(Developer"), and
12 the City of Fort Worth. a Texas municipal corporation ("City"), in the penal sum
Two Million Two Hundred Four Thousand Seven Hundred
# 3 of Fny_two and 601100•• Dollars ($ 2,204,742.60• },
14 lawful stoney of the United States. to be paid in Fort Worth, Tarrant County. Texas, for the
15 payment of which sum well and truly be made jointly unto the Developer and the City as dual
16 obligees, we hind ourselves, our heirs, executors, administrators, successors and assigns, jointly
17 and severally, firmly by these presents,
Is WHEREAS, Developer and City have entered into an Agreement for the construction of
19 community facilities in the City of Fort Worth, by and through a Community Facilities
24 Agreement, CFA Number CFA22-1 Q77; and
21 WHEREAS, Principal has entered into a certain written Contract with Developer,
97 awarded the 23rd day of November 20 22 . which Contract is hereby
23 referred to and made a part hereof for all purposes as if fully set forth herein. to Furnish all
24 materials, equipment, labor and other accessories as defined by law_ in the prosecution of the
25 Work as provided for in said Contract and designated as Triniry Luke.s Alrxed Ure Sou►h, Phase 1.
26 NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION is such that if
27 Principal shall pay all monies owing to any (and all) payment bond beneficiary (as defined in
28 Chapter 2253 of the Texas Government Code, as amended) in the prosecution of the Work under
29 the Contract. then this obligation shall be and become null and void: otherwise to remain in full
39 force and effect.
CITY OF FORT WORTH frinulr La,1ee i ned f4v.Vemdr I'+baw 1
STANDARD CITY CONDITIONS - 1XV17-LOPFR AWARDFD PROJFC`r5 Aa - 1 B49
Revised January 31.2f112
Wfi214-2
PAYMENT BOND
Page 2 of 2
1 This bond is made and executed in compliance with the provisions of Chapter 2253 of the
2 Texas Government Code, as amended, and all liabilities on this bond shall be determined ill
3 accordance with the provisions of said statute.
4 IN WITNESS WHEREOF, the Principal and Surety have each SIGNED and SEALED
5 this instrument by duly authorized agents and officers on this the 28th day of
6 November .20 22 .
7
3
9
to
I1
12
13
14
11l If 4A 0a{t__ kQ.&^—
(Principal) Secretary
►:r���lg1rA
(Surety) Secretary
WitrlE a5 tCi� Crystal Langhorn
PRINCIPAL:
Walker Utilities, Inc.
BY:
Signature
Brandon Walker, Vice President
Name and Title
Address: 124 Brown Trail
Hurst, TX 76053
SURETY:
SureTec Insurance Company
IFJ
BY: 'l/6
Signature
Elena Sells, Attorney -in -Fact
Name and Title
Address: 2103 CityWest Blvd., Suite 1300
Houston, TX 77042
Telephone Number; 713-812-0900
Note: If signed by an officer of the Surety, there must be on file a certified extract from the
bylaws showing that this person has authority to sign such obligation. If Surety-s physical
address is different from its mailing address, both must be provided.
The date of the bond shall not be prior to the date the Contract is awarded.
f 0401IQ 2LYXO31111010
CITY OF FORT WORTH ►iWVA [IAL A .11RiYrI f '.0 yl-WA. Phtlw ►
STANDARD CITY CONDITIONS - DEVELOPER AWARDED PROJECTS Cip Prev 't'i %so. - II► N4'J
Revised January 31.2012
006219-1
MAINTENANCE BOND
Page t of 3
SECTION 44 62 19 Bond 94450877
2 MAINTENANCE BOND
3
4 THE STATE OF TEXAS §
S § KNOW ALL BY THESE PRESENTS:
6 COUNTY OF TARRANT §
7
8 That we, Walker Utilities. Inc. known as "Principal"
9 herein and SureTec Insurance Company a corporate surety (sureties, if
14 more than one) duly authorized to do business in the State of Texas, known as "Surety" herein
11 (whether one or more), are held and firmly bound unto the Developer, TrinIIN Lake'. Partncr,�.
12 H.C, authorized to do business in Texas ("Developer') and the City of Fort Worth, a Texas
Two Million Two Hundred Four Thousand Seven Hundred
13 municipaI corporation ("City"), in the sum of Forty-two and 601100••
14 DolIars ($ 2,204,742.60•° ), lawful money of the United States, to be paid in Fort
15 Worth, Tarrant County, Texas, for payment of which sum well and truly be made jointly unto the
16 Developer and the City as dual obligees and their successors, we bind ourselves, our heirs,
17 executors, administrators, successors and assigns, jointly and severally, firmly by these presents.
18
19 WHEREAS, Developer and City have entered into an Agreement for the construction of
2[1 community facilities in the City of Fort Worth by and through a Community Facilities
21 Agreement, CFA NumberCFA22-t1177: and
22 WHEREAS, the Principal has entered into a certain written contract with the Developer
23 awarded the 23rd day of November .20 22 . which Contract is
24 hereby referred to and a made part hereof for all purposes as if fully set forth herein, to furnish all
25 materials, equipment labor and other accessories as defined by law, in the prosecution of the
26 Work, including any Work resulting from a duly authorized Change Order (collectively herein.
27 the "Work") as provided for in said Contract and designated as l o mori Lakek Ifi ked I .�r Smith,
28 f'Irtr.v, 1. and
29
30 WHEREAS, Principal binds itself to use such materials and to so construct the Work in
31 accordance with the plans, specifications and Contract Documents that the Work is and will
32 remain free from defects in materials or workmanship for and during the period of two (2) years
33 after the date of Final Acceptance of the Work by the City ("Maintenance Period"); and
34
CITY OF FORT WORTH [.iA UtUd I 51407& P14di. 1
STANDARD CITY CONDITIONS —DEVELOPER AWARDED PROJECTS � '�[ti• �'r,�r, t ,V, Iri e,,tu
Revised }anumy 31, 2012
1
2
3
4
S
6
7
8
9
10
11
12
I3
14
15
16
17
18
19
20
21
22
23
006219-2
MAINTENANCE BOND
Page 2 of 3
WHEREAS, Principal binds itself to repair or reconstruct the Work in whole or in part
upon receiving notice from the Developer and/or City of the need thereof at any time within the
Maintenance Period.
NOW THEREFORE. the condition of this obligation is such that if Principal shall
remedy any defective Work, for which timely notice was provided by Developer or City, to a
completion satisfactory to the City, then this obligation shall become null and void; otherwise to
remain in full force and effect.
PROVIDED, HOWEVER, if Principal shall fail so to repair or reconstruct any timely
noticed defective Work, it is agreed that the Developer or City may cause any and all such
defective Work to be repaired and/or reconstructed with all associated costs thereof being borne
by the Principal and the Surety under this Maintenance Bond. and
PROVIDED FURTHER, that if any legal action be filed on this Bond, venue shall lie in
Tarrant County. Texas or the United States District Court for the Northern District of Texas. Fort
Worth Division; and
PROVIDED FURTHER, that this obligation shall be continuous in nature and
successive recoveries may be had hereon for successive breaches.
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised January 31.1012
I'lfrlr� f N t�l �i �I + ,, S. H1111 1'+I-Iu I
006219-3
MAINI°ENANCE BOND
Page 3 of 3
1 IN WITNESS WHEREOF, the Principal and the Surety have each SIGNED and SEALED this
2 instrument by duly authorized agents and officers on this the 29th day of
3 November 1 7()22
4
b
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
3fi
37
38
39
40
41
42
ATTEST:
�{Jccx�rL1I�—
(Principal) Secretary
Witness as to Principal
(Surety) Secretary
Cr� LAYL4
Witness as to Surety Crstal Langhorn
PRINCIPAL:
Walker Utilities. Inc.
BY:
Signature
Brandon Walker- Vice President
Name and Title
Address: 124 Brown Trail
Hurst. TX 76053
SURETY:
SureTec Insurance Company
13Y:
Sig2aie
Elena Sells, Attorney -in -Fact
Name and Title
Address: 2103 CityWest Blvd., Suite 1300
Houston, TX 77042
Telephone Number: 713-812-0800
*Note: If signed by an officer of the Surety Company, there must be an file a certified extract
from the by-laws showing that this person has authority to sign such obligation. If
Surety's physical address is different From its mailing address, both must be provided.
The date of the Mond shall not be prior to the date the Contract is awarded.
CITY OF FORT WORTH I �, �. qrrlr. Mla %. r
STANDARD CITY CONDITIONS - DEVELOPER AWARDED PROIECTS V1, 114.1 '.rr
Revised January 31, 2012
FOA a: 4221800
SureTec Insurance Company
LIMITED POWER OF ATTORNEY
Know A11 Men by These Presents, That SURETEC INSURANCE COMPANY (the "Company"), a co rporat ion d my organ ixed and
existing under the lawsofthe State ofTexas, and hav ing its principa I office in Hou ston, H arris County, Texas. d o e s by these presents
make, constitute and appoint
Lanny Land, Steven W- Lewis, Elena Sells, Paul Fredette, Crystal Langhorn, Adam Syswerda
its true and lawful Attomey-in-Fact, with full powerand authority hereby conferred in its name, place and stead, to execute, acknowledge
and deliver anyandallbonds,recognazances,undertakings or other instruments or contracts of suretyship to include waivers to the
conditions of contracts and consents of surely for, providing the bond penalty does not exceed
Ten Million and 001100 Dollars ($10,000,000,00)
and to bind the Company thereby as fully and to the same extent as if such bond were signed by the President, sealed with the corporate
seal of the Company andduly attestedby its Se c re tary, h e re byra tifyin g and con firminga 11 that the said Attorney -in -Fact in ay do in th e
premises. Said appointment is made tinder andby authority of the foilow•ingresolutions of the Board of Directors of the SureTec
Insurance Company:
Be it Resolved, that the President, any V ice -President, any Assistant Vice -President, any Secretary a any Assistant Secretary sh al I be an d is
hereby vested with Full power and authority to appoint any one or more suitable persons as Attarney(s)-in-Fact to represent and act for an d n n
behatfof the Company subject to the following provisions:
.horsey -in -Fact may be given Full power and authority for and in the name of and of behalf of the Company, to execute, acknowledge and
deliver, any and all bonds, recognizances, contracts, agreements or indemnity and other conditional or obligatory undertakings and any and al I
notices and documents canceling or terminating the Company's liability thereunder, and any such instruments so executed by any such
Attorney -in -Face shall be binding upon the Company as if signed by the President and sealed and effected by the Corporate Secretary.
Be ll Resolved, that the signature of any authorized officer and sea] of the Company heretoforeor hereafter affixed to any power of attorney ❑r
any certificate relating thereto by Facsimile, and any power of attorney ar certificate bearing facsimile signature a facsimile seal shall be valid
and binding upon the Company with respect to any bond or undertaking to which it is attached. (Adopted at meeting held on 2 0 of•April,
1999.)
In Witness Whereof, SUR -TEC INSURANCE COMPANY has caused these presents to be signed by its President, and its corporate seal
to be hereto affixed this 26th day of August , A.D. 2022 .
SURETEC INSURANCE COMPANY
y�7OF
{ x 9• ` 0 By;
CA i LU r nt Michael C. Ketmig, President
k
State of Texas ss: ._.. � -�`�•
County offtarris
On this 26th day of August , AM. 2022 before me personally came Michael C, Kcimig, tome known, who, being by me duly sworn, did depas e
and say, that he resides in Houston. Texas, that he is President of SURETEC INSURANCE COMPANY, the company described in and which executed
the above instrumenr, that he knows the seal of said Company; that the seal affixed to said instrument is such corporate seal; that it was so affixed by
order of [he Hoard of Directors afsaid Company; and that he signed his name thereto by like ord
TANYA SNEE❑
' } • � _ Notary Public, State of Texas ;
_= Comm. Expires 03-30-2023 Tanya Sneed, No ry Public
° s E o Notary ID 128571231 My commission expires March 30, 2023
I, M. Brent Beaty, Assistant Secretary of SURETEC INSURANCE COMPANY, da hereby certify that the above and foregoing is a true and earrectcopy
of a Power of Attorney, executed by said Company, which is still in full force and effect; and furthermore, the resolutions of the Board of Directors, s et
out in the Power of Attorney are in full force and effect.
Given undermy hand andtheseal of said. Company at Houston, Texas this 29th day of November 2022 �, A.D.
x
M.13)ntsiant5i-xeerctary
Any instrument issued in excess of the penalty stated above is totally void and without any. valtdity. 42218na
For verification ofthe authority of this power you may call (713)812-0800 any business day between 8;30 am and 5:00 pm CST.
SureTec Insurance Company
IMPORTANT NOTICE
Statutory Complaint NoticelFiling of Claims
To obtain information or make a complaint: You may call the Surety's toll free telephone number for information or to make
a complaint or file a claim at: 1-886-732-9999. You may also write to the Surety at:
SureTec Insurance Company
9737 Great Hills Trail, Suite 320
Austin, TX 78759
You may contact the Texas Department of Insurance to obtain information on companies, coverage, rights or complaints
at 1-899-252- 3439. You may write the Texas department of Insurance at:
PO Box 149104
Austin, TX 78714-9104
Fax#: 512-490-1007
Web: htto:Nwww.tdi.texas.00v
Email: ConsumerProtection@tdi.texas.gov
PREMIUM OR CLAIMS DISPUTES: Should you have a dispute concerning your premium or about a claim, you should
contact the Surety first. If the dispute is not resolved, you may contact the Texas Department of Insurance.
Texas Rider 8/2019
SureTec Insurance Company
THIS BON❑ RIDER CONTAINS IMPORTANT COVERAGE INFORMATION
The obligations of the Surety and Principal under the Bond or Bonds to which this Rider is
annexed are subject to the following limitations and conditions, to wit: that, it is a condition
precedent to their liability hereunder that the contractual obligation (the contract or
subcontract, as the case may be, being referred to in this Rider as the "Contract") between
the Principal and the Obligee underlying this Bond includes (or shall be considered amended
to include) a Force Mcieure exclusion holding that the Principal and its Sureties shall not be
held liable under this Bond or under the Contract for any impacts, delays, defaults, or
damages related to Principal's work arising from, or related to epidemics, pandemics,
medical emergencies, supply line interruptions, or natural disasters impacting the work
required by the Contract, regardless of where such events occur, acts of God, terrorism,
war, acts of government or administrative suspension, limitation, or shut -down, ❑r the
direct or indirect consequences or aftermath of any of the foregoing, and the Contract
further provides that the Principal shall be entitled to an extension of the Contract Time and
an equitable adjustment of the Contract Price, as a result of any of the exclusions
heretofore cited, in the event the provisions for force majeure, time extensions, or
equitable adjustment for time and money are more favorable to Principal in the Contract,
than in this Rider, the more favorable shall apply.
Revised 3-2009
PAVING
STABILE & WINN, INC.
0045 12
DAP PREQUALIFICATION STATEMENT
Page 1 of 1
SECTION 00 45 12
DAP — PREQUALIEICATION STATEMENT
Each Bidder is required to complete the information below by identifying the prequalified contractors
and/or subcontractors whom they intend to utilize for the major work type(s) listed. In the "Major Work
Tvpe" box provide the complete maior work tvne and actual descrintion as nrovided by the Water
Department for water and sewer and TPW for navine.
Major Work Type Contractor/Subcontractor Company Name Prequalification
Expiration Date
Machine Laid Concrete Paving Stabile and Wiiw, Inc. 01/31/24
Construction
The undersigned hereby certifies that the contractors and/or subcontractors described in the table above
are currently prequalified for the work types listed.
BIDDER:
Stabile and Winn, hic
PO Box 79380
Saginaw, Texas 76179
TITLE:
DATE:+--
END OF SECTION
CITY OF FORT WORTH
STANDARD CONSTRUCTION PREQUALIFICATION STATEMENT— DEVELOPER AWARDED PROJECTS
004512_Prequ a fication Statement 2015_DAP Paving.doex
Form Verslon September 1, 2015
00 5243 -1
Developer Awarded Project Agreement
Page 1 of4
SECTION 00 52 43
2 AGREEMENT
3 THIS AGREEMENT, authorized on ll-a l -&1914 is made by and between the Developer,
4 Trinity Lakes Partners, LLC, authorized to do business in Texas ("Developer"), and Stabile and
5 Winn, Inc., authorized to do business in Texas, acting by and through its duly authorized
6 representative, ("Contractor").
7 Developer and Contractor, in consideration of the mutual covenants hereinafter set forth, agree as
8 follows:
9 Article 1. WORK
10 Contractor shall complete all Work as specified or indicated in the Contract Documents for the
I Project identified herein.
12 Article 2. PROTECT
13 The project for which the Work under the Contract Documents may be the whole or only a part is
14 generally described as follows:
15 Trinity Lakes Mixed Use South. Phase I
16 CitvProieetNo.-103R49 VMo—X-27190-FIT) Nn—i0114-01)04i1-In7949-F07mi
17 File No. — W-2804
18 Article 3. CONTRACT TIME
19 3.1 Time is of the essence.
20 All time limits for Milestones, if any, and Final Acceptance as stated in the Contract
21 Documents are of the essence to this Contract.
22 3.2 Final Acceptance.
23 The Work will be complete for Final Acceptance within 110 working days after the date
24 when the Contract Time commences to run as provided in Paragraph 12.04 of the Standard
25 City Conditions of the Construction Contract for Developer Awarded Projects.
26 3.3 Liquidated damages
27 Contractor recognizes that time is of the essence of this Agreement and that Developer
28 will suffer financial loss if the Work is not completed within the times specified in
29 Paragraph 3.2 above, plus any extension thereof allowed in accordance with Article 10 of
30 the Standard City Conditions of the Construction Contract for Developer Awarded
31 Projects. The Contractor also recognizes the delays, expense and difficulties involved in
32 proving in a legal proceeding the actual loss suffered by the Developer if the Work is not
33 completed on time. Accordingly, instead of requiring any such proof , Contractor agrees
34 that as liquidated damages for delay (but not as a penalty), Contractor shall pay
35 Developer One thousand Dollars ($1 0' 00.00) for each day that expires after the time
36 specified in Paragraph 3.2 for Final Acceptance until the City issues the Final Letter of
37 Acceptance.
CITY OF FORT WORTH Trmiry Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS— DEVELOPER AWARDED PROJECTS Cary Project No. -103845
Revised June 16, 2016
GO 5243 -2
Developer Awarded Project Agreement
Page 2 oril
38 Article. 4. CONTRACT PRICE
39 Developer agrees to pay Contractor for performance of the Work in accordance with the Contract
40 Documents an amount in current funds of One million three hundred eighty four thousand
41 six hundred three dollars and fortv 42 cents. ($1.384.603.42)
42 Article 5. CONTRACT DOCUMENTS
43 5.1 CONTENTS:
44
A. The Contract Documents which comprise the entire agreement between Developer and
45
Contractor concerning the Work consist of the following:
46
1.
This Agreement.
47
2.
Attachments to this Agreement:
48
a, Bid Form (As provided by Developer)
49
1) Proposal Form (DAP Version)
50
2) Prequalification Statement
51
3) State and Federal documents (project specific)
52
b. Insurance ACORD Form(s)
53
c. Payment Bond (DAP Version)
54
d. Performance Bond (DAP Version)
55
e. Maintenance Bond (DAP Version)
56
f, Power of Attorney for the Bonds
57
g. Worker's Compensation Affidavit
58
h, MBE and/or SBE Commitment Form (If required)
59
3.
Standard City General Conditions of the Construction Contract for Developer
60
Awarded Projects.
61
4.
Supplementary Conditions.
62
5.
Specifications specifically made a part of the Contract Documents by attachment
63
or, if not attached, as incorporated by reference and described in the Table of
64
Contents of the Project's Contract Documents.
65
6.
Drawings.
66
7.
Addenda.
67
8,
Documentation submitted by Contractor prior to Notice of Award.
68
9.
The following which may be delivered or issued after the Effective Date of the
69
Agreerncrit and, if issued, become an incorporated part of the Contract Documents:
70
a. Notice to Proceed.
71
b. Field Orders.
72
c. Change Orders.
73
d. Letter of Final Acceptance,
74
75
CITY OF FORT WORTH Ti-inn)- Luker dlixed Use Sion di, Phase i
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS Cify Prgjavl IVa. - i03844)
Revised June 16.2036
005243-3
Developer Awarded Project Agreement
Page of4
76 Article 6. INDEMNIFICATION
77 6.1 Contractor covenants and agrees to indemnify, hold harmless and defend, at its own
78 expense, the city, its officers, servants and employees, from and against any and all
79 claims arising out of, or alleged to arise out of, the work and services to be performed
80 by the contractor, its officers, agents, employees, subcontractors, licenses or invitees
81 under this contract. This indemnification provision is specifically intended to operate
82 and be effective even if it is alleged or proven that all or some of the damages being
83 sought were caused. in whole or in part, by anv act. omission or negligence of the city.
84 This indemnity provision is intended to include, without limitation, indemnity for
85 costs, expenses and legal fees incurred by the city in defending against such claims and
86 causes of actions.
87
88 6.2 Contractor covenants and agrees to indemnify and hold harmless, at its own expense,
89 the city, its officers, servants and employees, from and against any and all loss, damage
90 or destruction of property of the city, arising out of, or alleged to arise out of, the work
91 and services to be performed by the contractor, its officers, agents, employees,
92 subcontractors, licensees or invitees under this contract. This indemnification
93 provision is specifically intended to operate and be effective even if it is alleged or
94 proven that all or some of the damages being sought were caused. in whole or in part.
95 by anv act. omission or negligence of the city.
96
97 Article 7. MISCELLANEOUS
98 7.1 Terms.
99 Terms used in this Agreement are defined in Article I of the Standard City Conditions of
100 the Construction Contract for Developer Awarded Projects.
101 7.2 Assignment of Contract.
102 This Agreement, including all of the Contract Documents may not be assigned by the
103 Contractor without the advanced express written consent of the Developer.
104 7.3 Successors and Assigns.
105 Developer and Contractor each binds itself, its partners, successors, assigns and legal
106 representatives to the other party hereto, in respect to all covenants, agreements and
107 obligations contained in the Contract Documents.
108 7.4 Severability.
109 Any provision or part of the Contract Documents held to be unconstitutional, void or
110 unenforceable by a court of competent jurisdiction shall be deemed stricken, and all
III remaining provisions shall continue to be valid and binding upon DEVELOPER and
112 CONTRACTOR.
113 7.5 Governing Law and Venue
114 This Agreement, including all of the Contract Documents is performable in the State of
115 Texas. Venue shall be Tarrant County, Texas, or the United States District Court for the
116 Northern District of Texas, Fort Worth Division.
CRY OF FORT WORTH hrdry Lakes Meeed U. Sourh, Ph..I
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS— DEVELOPER AWARDED PROJECTS City Praren No.-103849
Revised June, 16, 2016
00 52 43 - 4
Developer Awarded Project Agreement
Pave 4 of 4
117
118 7.6 Authority to Sign.
119 Contractor shall attach evidence of authority to sign Agreement, if other than duly
120 authorized signatory of the Contractor.
121
122 1N WITNESS WHEREOF, Developer and Contractor have executed this Agreement in multiple
123 counterparts.
124
125 This Agreement is effective as of the last date signed by the Parties ("Effective Date").
126
Contractor: Stabile & Winn, Inc.
y _ {Sig ture}
John Stabile
(Printed Name)
Title: President
Company Name: Stabile & Winn, Inc.
Address: PO Box 79380
City/State/Zip: Saginaw, TX 76179
II- 3 /- ad�07
Developer: Trinity Lakes Partners, LLC
4CBy:. V .
(Signature)
f
Kenneth B. Newell
(Printed Name)
Title: Member
Company name: Trinity Lakes Partners, LLC
Address: PO Box 185104
City/State/Zip: Fart Worth, TX 76181
Date Date
127
CITY OF FORT WORTH Tripiity Lakes Mixed Use.Soulb, Phase !
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Projeel Na. - 103849
Revised June I6, 20I6
006213- 1
PERFORMANCE BOND
Page I of 3
BOND NO.8050113
SECTION 00 62 13
THE STATE OF TEXAS §
§ KNOW ALL BY THESE PRESENTS:
COUNTY OF TARRANT §
That we, Stabile &, Winn, Inc. , known as "Principal"
herein and Amerisure Mutual Insurance Company , a corporate
surety(sureties, if more than one) duly authorized to do business in the State of Texas, known as
"Surety" herein (whether one or more), are held and firmly bound unto the Developer, Trinity
Lakes Partners, LLC, authorized to do business in Texas ("Developer"} and the City of Fort
Worth, a Texas municipal corporation ("City' }, in the penal sum of, One million three hundred
eighty four thousand six hundred three and 42/100 Dollars ($ 1,384,603.42 ), lawful
money of the United States, to be paid in Fort Worth, Tarrant County, Texas for the payment of
which sum well and truly to be made jointly unto the Developer and the City as dual obligees, we
bind ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally,
firmly by these presents.
WHEREAS, Developer and City have entered into an Agreement for the construction of
community facilities in the City of Fort Worth by and through a Community Facilities
Agreement, CFA Number CFA22-0177 and
WHEREAS, the Principal has entered into a certain written contract with the Developer awarded
the d/At
day of 17f 7716Er , 24JA, which Contract is hereby referred to and made a
part hereof for all purposes as if fully set forth herein, to furnish all materials, equipment labor
and other accessories defined by law, in the prosecution of the Work, including any Change
Orders, as provided for in said Contract designated as Trinin< Lakes Mixed Use South, Phase 1.
CITY OF FORT WORTH drrrrrn, Lakes Mixed Use Suurk. Phase I
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS i in+ Aojerr No - 103849
Revised January 31, 2012
006213-2
PERFORMANCE BOND
Page 2 o1'3
NOW, THEREFORE, the condition of this obligation is such that if the said Principal
shall faithfully perform it obligations under the Contract and shall in all respects duly and
faithfully perform the Work, including Change Orders, under the Contract, according to the plans,
specifications, and contract documents therein referred to, and as well during any period of
extension of the Contract that may be granted on the part of the Developer and/or City, then this
obligation shall be and become null and void, otherwise to remain in full force and effect,
PROVIDED FURTHER, that if any legal action be filed on this Bond, venue shall lie in
Tan -ant County, Texas or the United States District Court for the Northern District of Texas, Fort
Worth Division.
This bond is made and executed in compliance with the provisions of Chapter 2253 of the
Texas Government Code, as amended, and all liabilities on this bond shall be determined in
accordance with the provisions of said statue.
IN WITNESS WHEREOF, the Principal and the Surety have SIGNED and SEALED
twe;,�F'�rn
'ument by duly authorized agents and officers on this the day of
[nor, 2aA,)-
ATTEST:
(Principal) Secretary
Witness as to Rqrl�ipal���
CITY OF FORT WORTH
STANDARD CITY CONDITIONS - DEVELOPER AWARDED PROJECTS
Revised January 31, 2012
P P
Lgjpt)flq'a Winn. Inc.
BY:
Signature
John Stabile, President
Nanne and Title
Address: Pa Box 79380
Saeinaw, TX 76179
SURETY:
Arnerisure Mutual Insurance Companv.
BY:
Signature
Tracy Tucker, Attorney -in -Fact
Nance and Title
Address: P n Box 2285
Fort Wordy, TX 76113
T: iirin' Lakes hAxed Use Sourh, Pharr I
C in• Proiert Alo - 103849
006213-3
PERFORMANCE BOND
&42��
Witness as to Surety
Telephone Number: 8171336-8520
Page 3 of 3
*Note: If signed by an officer of the Surety Company, there must be on file a certified extract
from the by-laws showing that this person has authority to sign such obligation. If
Surety's physical address is different from its mailing address, both must be provided.
The date of the bond shall not be prior to the date the Contract is awarded.
CITY OF FORT WORTH
STANDARD CITY CONDMONS - DEVELOPER AWARDED PROJECTS
Revises! January 31, 2012
Trinity Lakes Mixer! Use South, Phase 1
Coy Project No. - 10384Y
006214- 1
PAYMENT BOND
Page i of 2
BOND NO.8050113
SECTION 00 52 14
PAYMENT BOND
THE STATE OF TEXAS §
§ KNOW ALL BY THESE PRESENTS:
COUNTY OF TARRANT §
That we, Stabile & Winn, Inc. known as
"Principal" herein, and Amerisure Mutual Insurance Company , a
corporate surety (or sureties if more than one), duty authorized to do business in the State of
Texas, known as "Surety" herein (whether one or more), are hetd and firmly hound unto the
Developer, Trinity Lakes Partners, LLC, authorized to do business in Texas "(Developer"), and
the City of Fort Worth, a Texas municipal corporation ("City"), in the penal sum of One million
three hundred eighty four thousand six hundred three and 421100 Dollars
($ 1,384,603.42 ), lawful money of the United States, to be paid in Fort Worth, Tarrant County,
Texas, for the payment of which sum well and truly be made jointly unto the Developer and the
City as dual obligees, we bind ourselves, our heirs, executors, administrators, successors and
assigns, jointly and severally, firmly by these: presents:
WHEREAS, Developer and City have entered into an Agreement for the construction of
community facilities in the City of Fort Worth, by and through a Community Facilities
Agreement, CFA Number CFA22-0177 ;and
WHEREAS, Principal has entered into a certain written Contract with Developer,
awarded the 31 'd day of �/7/,�iXkA) , 20AL, which Contract is hereby
referred to and made a part hereof for all purposes as if fully set forth herein, to furnish all
materials, equipment, labor and other accessories as defined by law, in the prosecution of the
Work as provided for in said Contract and designated as TriniD� Lakes Mired Llse Soulb, Phase 1.
NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION is such that if
Principal shall pay all monies owing to any (and all) payment hand beneficimy (as defined in
Chapter 2253 of the Texas Government Code, as amended) in the prosecution of the Work under
the Contract, then this obligation shall be and become null and void: otherwise to remain in full
force and effect.
CITY OF FORT WORTH Dlnirr lakes Mixed Use Sau+h. Phase I
STANDARD CITY CONDITIONS - DEVELOPER AWARDED PROJECTS 00- Prvjsci No: - 10384E
Revised January 33, 2012
006214-2
PAYMENT BO VD
Page 2 of 2
This bond is made and executed in compliance with the provisions of Chapter 2253 of the
Texas Government Code, as amended, and all liabilities on this bond shall be determined in
accordance with the provisions of said statute.
IN WITNESS WHEREOF, the Principal and Surety have each SIGNED anSEALED
this nstrument by duly authorized agents and officers on this the day of
I ja�&�bov . 20dA A.
►WINA-3 6
(Principal) Secretary
�"
Witness as to P ' cipaY
(Surety) Secretary
sme /-,� 4�
Witness as to Surety
PRINCIP
Winn, Inc.
John Stabile, President
Name and Title
Address: PO Box 79380
Saainaw, TX 76179
SURETY:
Amerisure Mutual Insurance Company
BY:
Signature
Tracy Tucker, Attorney -in Fact
Name and Title
Address: P O Box 2285
Fort Worth, TX 76113
Telephone Number: 8171336-8520
Note: If signed by an officer of the Surety, there must be on file a certified extract from the
bylaws showing that this person has authority to sign such obligation. If Surety's physical
address is different from its mailing address, both must be provided.
The date of the bond shall not be prior to the date the Contract is awarded.
END OF SECTION
CITY OF FORT WORTH Tjjujty Lakes Mixed Use South. Phase I
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS 00i Project hro. - 103,'49
Revised January 31, 2012
006219-I
MAINTENANCE BOND
Page I of 3
BOND NO.8050113
SECTION 00 62 19
MAINTENANCE BOND
THE STATE OF TEXAS §
§ KNOW ALL BY THESE PRESENTS:
COUNTY OF TARRANT §
That we, Stabile & Winn, Inc.
, known as "Principal"
herein and Amerisure Mutual Insurance Companv , a corporate surety (sureties, if
more than one) duly authorized to do business in the State of Texas, known as "Surety" herein
(whether one or more), are held and firmly bound unto the Developer, Trinity Lakes Partners,
LLC , authorized to do business in Texas ("Developer") and the City of Fort Worth, a Texas
municipal corporation ("City"), in the sum of One million three hundred ei-ahty four thousand six
hundred three and 421100 Dollars ($ 1,384,603.42 ), lawful money of the United States, to be
paid in Fort Worth, Tarrant County, Texas, for payment of Which sum well and truly be made
jointly unto the Developer and the City as dual obligees and their successors, we bind ourselves,
our heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these
presents,
WHEREAS, Developer and City have entered into an Agreement for the construction of
community facilities in the City of Fort Worth by and through a Community Facilities
Agreement, CFA Number CFA22-I077,and
WHEREASS the Princi al has entered into a certain written contract with the Developer
awarded the � / day of , 20- , which Contract is
hereby referred to and a made part hereof for all purposes as if fully set forth herein, to furnish all
materials, equipment labor and other accessories as defined by law, in the prosecution of the
Work, including any Work resulting from a duly authorized Change Order (collectively herein,
the "Work") as provided for in said Contract and designated as Trinity Lakes Mixed Use South,
Phase 1, and
CITY OF FORT WORTH rrimh- Lakes hfued Use South, Plume 1
STANDARD CITY CONDITIONS - DEVELOPER AWARDED PROJECTS 0n. Project NO- - 103849
Revised January 3 I , 20 E 2
006219-2
MAINTENANCE BOND
Page 2 of 3
WHEREAS, Principal binds itself to use such materials and to so construct the Work in
accordance with the plans, specifications and Contract Documents that the Work is and will
remain free from defects in materials or worlananship for and during the period of two (2) years
after the date of Final Acceptance of the Work by the City ("Maintenance Period"); and
WHEREAS, Principal binds itself to repair or reconstruct the Work in whole or in part
upon receiving notice from the Developer and/or City of the need thereof at any time within the
Maintenance Period.
NOW THEREFORE, the condition of this obligation is such that if Principal shall
remedy any defective Work, for which timely notice was provided by Developer or City, to a
completion satisfactory to the City, then this obligation shall become null and void; otherwise to
remain in full force and effect.
PROVIDED, HOWEVER, if Principal shall fail so to repair or reconstruct any timely
noticed defective Work, it is agreed that the Developer or City may cause any and all such
defective Work to be repaired and/or reconstructed with all associated costs thereof being borne
by the Principal and the Surety under this Maintenance Bond; and
PROVIDED FURTHER, that if any legal action be fled on this Bond, venue shall lie in
Tarrant County, Texas or the United States District Court for the Northern District of Texas, Fort
Worth Division; and
PROVIDED FURTHER, that this obligation shall be continuous in nature and
successive recoveries may be had hereon for successive breaches.
CITY OF FORT WORTH IYrnhr v Lakes Mixed Use .S'off k Phase
STANDARD CITY CONDITIONS - DEVELOPER AWARDED PROJECTS CrfyflenimlNo. - 103849
Revised January 31, 2012
OQ 62 19 - 3
MAINTENANCE BOND
Page 3 of 3
IN WITNESS WHEREOF, the Principal and the Surety have each SIGNED and SEALED this
instrument by duly authorized agents and officers on this the day of
ll?a 3 IVA) , 20,
ATTEST:
(Principal) Secretary
ZVI,�
Witness as to PnncipaI G
ATTEST:
(Surety) Secretary
— AWL AV�6
Witness as to Surety
PRINCIPAL:
51a$i &Winn. Inc.
BY:
ignature
Jahn Stabile, President
Name and Title
Address: PO Box 79380
Saginaw, TX 76179
SURETY:
Amerisure Mutual Insurance Company
BY: - ' r�
Signatu}e-
Tracy Tucker, Attomey-in-Fact
Name and Title
Address: P 0 .Sox 2295
Fort Worth, TX 76113.
Telephone Number: 817/336-8520
*Note: If signed by an officer of the Surety Company, there must be on file a certified extract
from the by-laws showing that this person has authority to sign such obligation. If
Surety's physical address is different from its mailing address, both must be provided.
The date of the bond shall not be prior to the date the Contract is awarded.
CITY OF FORT WORTH Trirjiry Lukas Mixed Use Smith. Please 1
STANDARD CITY CONDITIONS - DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised January 31, 2012
DUAL OBLIGEE RIDER
To be attached to and form a part of contract bond nurnber 8050113 issued by the
Amerisure Mutual Insurance Comnanv on behalf of Stabile & Winn, Inc. in the
amount of One million three hundred eiehty four thousand six hundred three and
421100---- ---- (S 1,384,603.42) and dated II . Z 5 -I; in favor of
Trinitv Lakes Partners, LLC.
In consideration of the sum of One Dollar ($1.00), and other good and valuable
consideration receipt of which is hereby acknowledged, the Undersigned herby agree as
follows:
1. City of Fort Worth, Texas is hereby added to said bond as an additional
obligees.
2. The Surety shall not be liable under this bond to the Obligees, or any of them
unless the said Obligees, or any of them, shall make payments to the Principal
strictly in accordance with the terms of the said contract as to payments, and shall
perform all other obligations to be performed under said contract at the time and
in the manner therein set forth.
3. No suit, action or proceeding by reason of any default whatever shall be brought
on this bond after two (2) years and one ( 1) month from the day on which the
final payment under said construction contract falls due.
4. Aggregate liability of Surety hereunder to Obligees is limited to the penal sum
above stated and Surety, upon making payment hereunder, shall be subrogated to,
and shall be entitled to an assignment of all rights of the payee with respect to the
particular obligation discharged by the payment, either against principal or against
any other party liable to the payee on the dischar ed obligation.
Signed, sealed and dated this day of D cQ mbe p , 20 .
& Winn, Inc.
Amerisure Mutual Insurance
Comvanv
Surety ---�
Tracy Tucker) Attorney -in -Fact
AMERISURE MUTUAL INSURANCE COMPANY AMERISURE
AMERISURE INSURANCE COMPANY �-SURETY
AMERISURE PARTNERS INSURANCE COMPANY
POWER OF ATTORNEY
KNOW ALL MEN BY THESE PRESENTS: That Amensure Mutual Insurance Company, Amerisure Insurance Company and Amerisure Parners Insurance
Company are corporations duly organized under the laws of the State of Michigan (herein collectively the "Companies"), and that the Companies do hereby
make, constitute and appoint
Tracy Tucker, Steven Tucker, Kevin J. Dunn, W. Lawrence Brown
Bennett Brown and Roberta H. Erb
its true and lawful Attorney(s)-in Fact, each in their separate capacity if more than one is named above, to sign, execute, seal and ackn(ywWge, for and on
its behalf and as its act and deed, bands or others writings obligatory in the nature of a bond on behalf of each of said Companies, as surety, on
contracts or suretyship as are or may be required or permitted by law, regulation, contract or otherwise, provided that no bond or undertaking or contract
or suretyship executed under this authority shall exceed the amount of:
ONE HUNDRED MILLION ($100,000,000.00) DOLLARS
This Power of Attorney is granted and signed by facsimile under and by the authority of the following Resolutions adopted by the Boards
of Directors of Amerisure Mutual Insurance Company, Amerisure Insurance Company and Amerisure Partners Insurance Company at meetings duly called
and held on February 17, 2022.
"RESOLVED, that any two of the President & Chief I-xeeutive Officer, the Chief Financial Officer & Treasurer, the Senior Vice President Surety, the
Vice President Surety, or the General Counsel & Corporate Secretary be, and each or any of them hereby is authorized to execute, a Power of Attorney
qualifying the attorney -in -fact named in the given Power of Attorney to execute an behalf of the Company bonds, undertakings and ail contracts
of surety, and that President & Chief Executive ❑fficer, Chief Financial Officer & Treasurer or General Counsel & Corporate Secretary each or any of
them hereby is authorized to attest to the execution of any such Power of Attorney and to attach therein the seal of the Company;
FURTHER RESOLVED, that the signature of such officers and the seal of the Company may be affixed to any such Power of Attorney or to any certificate
relating thereto riectronicaIlyldigitall Iy or by Facsimile, and any such Power of Attorney or certificate bearing such electromcldigital or facsimile signatures
or electronicldigiW or facsimile seal shall be binding upon the Company when so affixed and to the future with regard to any hand, undertaking or
contract of surety to which it is attached,
FURTHER RESOLVED. that any work carried out by the attorney -in -Fact pursuant to this resolution shall he valid and binding upon the Company."
.C�py INgUP a
f ;?Su�RR,yC By:
11 Rlll,y
`t�...........
e ��Go}t�agiy�y�tianv
R� c
Michael A. Ito, Senior Vice President
R SEAL '
_� SEAL p
'e=n_ 2000 10
=sd.7y
L,
'L�: 1968 'a= By:
!CHSGp�,''��e r
gyysy�
Aaron Green. Vice President
Q-
gde.,yseHt�.
i �4Y ���
}
.'MliNlllll lllxl�y
"Y rr4rl.i �YwPW
IN WITNESS WHEREOF,
Amerisure Mutual Insurance
Company, Amerisure Insurance Company and Amerisure Partners
Insurance Company
have caused their afI'icial seals to be hereunto affixed, and these presents to be signed by their authorized offioers this
25th day of March 20 22
Amerisure Mutual Insurance Company
Amerisure Insurance Company
Amerisure Partners Insurance Company
State of Illinois
County of Kane
On this 251h day of March 20?2 before me, allotary Public personally appeared Michael A. Ito- of Amerisure Mutual Insurance Company, Amerisure
Insurance Company and Amerisure Partners Insurance Company and Aaron Green of Amerisure Mutual Insurance Company, Amerisure Insurance Company
and Amerisure Partners Insurance Company, personally known to me, who being by me duly sworn, acknowledged that they signed the above Power of Attorney
as officers of and acknowledged said instrument to be the voluntary act and deed of their respective companies.
OFFKW $EAL
M iCENNY
[NOTARY PUBLIC, STATE OF ILLiNOISCOMMISSION UPIRE° 12104=5
hi. erpty, PWtary Pwb
L Shannon K. Anderson. the duly elected Vice President, General Counsel & Corporate Secretary of Amerisure Mutual Insurance Company, Amerisure
Insurance Company and Amerisure Partners Insurance Company, do hereby certify that the above and foregoing is a true and correct copy of a Power of
Attorney executed by said Companies, which remains in full Force and effect.
TN WITNESS WHEREOF- I have set my hand and affixed the seals of the Cornparues this day of 20
Shannon I:. Anderson. Vice President, General Counsel & Comorate Sf�cretaty
AMERISURE
%SURETY
Texas Important Notice
rnk I03 tIl I10k01 Aaull 141 Il
To obtain information or make a complaint:
You may tali Amerisure Surety's toll -free telephone
number for information or to make a complaint at:
1-800-257-I 900
You may contact the Texas Department of Insurance to
obtain information on companies, coverages, rights, or
complaints at:
1-800-252-3439
You may write the Texas Department of
Insurance:
P.D. Box 12030
Austin, TX 78711-2030
Fax: (512) 490-I007
Web: %vww.tdi.texas.gov
E-mail: ConswnerProtection@tdi.texas.gov
PREMIUM OR CLAIM DISPUTES:
Should you have a dispute concerning your premium or
about a claim, you should contact the company first. If the
dispute is not resolved, you may contact the Texas
Department of Insurance.
ATTACH THIS NOTICE TO YOUR POLICY:
This notice is for information only and does not become a
part or condition of the attached document.
Amerisure Mutual Insurance Company
Amerisure Insurance Company
Amerisure Partners Insurance Company
P.O. Box 9098
Farmington Hills, MI 48333-9098
AV1SO IMPORTANTE
Para obtener inforrnacion o para presentar Una que}a:
Usted puede llamar a] m5mero de telefono gratuito de
Amerisure Surety's para obtener information o para
presentar una queja at:
1-800-257-I 900
Listed puede comunicarse con el Departamento de Se-guros
de Texas para obtener information sobre corn-pan`ias,
coberturas, derechos, o quejas al:
1-800-252-3439
Usted puede escribir a] Departamento
de Seguros de Texas a:
P.O. Box 12030
Austin. TX 78711-2030
Fax: (512) 490-1007
Shio web: www.tdi.texas.gov
E-mail: ConsumerProtection@tdi.texas.gov
DISPUTAS FOR PRIMAS DE SEG11ROS 0
F517w TA 3 F.Tti 010 361
Si tiene una disputa relacionada con su prima do seguro
o con una reclamacion, usted debe comunicarse con la
compania primero. Si la disputa no es resuelta, usted
puede comunicarse con el Departamento de Seguros de
Texas.
ADJUNTE ESTE AVISO A SU POLIZA: Este aviso es
solamente para propbsitos informativos y no se con-vierte en
pane o en condicion del documents adjunto.
AC® CERTIFICATE CERTIFICATE OF LIABILITY INSURANCE DATE IMMIDD YV)
Il I 06/22/2023
THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE HOLDER. THIS
CERTIFICATE DOES NOT AFFIRMATIVELY OR NEGATIVELY AMEND, EXTEND OR ALTER THE COVERAGE AFFORDED BY THE POLICIES
BELOW. THIS CERTIFICATE OF INSURANCE DOES NOT CONSTITUTE A CONTRACT BETWEEN THE ISSUING INSURER($), AUTHORIZED
REPRESENTATIVE OR PRODUCER, AND THE CERTIFICATE HOLDER,
IMPORTANT: If the certificate holder is an ADDITIONAL INSURED, the policy(ies) must have ADDITIONAL INSURED provisions or be endorsed.
If SUBROGATION IS WAIVED, subject to the terms and conditions of the policy, certain policies may require an endorsement. A statement on
this certificate does not confer rights to the certificate holder in lieu of such endorsement(s).
PRODUCER CONTACT Michelle Hodges
NAME
Tucker Agency, Ltd PHONE (817) 336-8520 FAX
)AIC No Extl (AIC. NO:
P O Box 2285 E-MAIL ADDRESS. michelle@tuckeragency.com
I
INSURER(S) AFFORDING COVERAGE
NAIL# I
Ft. Worth TX 76113
INSURERA: Amensure Mutual Insurance Cc
23396
INSURED
INSURER B: Amensure Insurance Company
19488
Stabile & Winn Inc
INSURER c: Hanover Insurance Group
22292
Po Box 79380
INSURER D
INSURER E:
Saginaw TX 76179-0360
INSURER F:
I
COVERAGES CERTIFICATE NUMBER: 23-24 All Lines
REVISION NUMBER:
THIS IS TO CERTIFYTHATTHE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED
TO THE INSURED NAMEDABOVE FOR THE POLICY PERIOD
INDICATED NOTWITHSTANDING ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACTOR
OTHER DOCUMENT WITH RESPECT TO WHICH THIS
CERTIFICATE MAYBE ISSUED OR MAY PERTAIN, THE INSURANCE AFFORDED BY THE
POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS,
EXCLUSIONS AND CONDITIONS OF SUCH POLICIES LIMITS SHOWN MAY HAVE BEEN
REDUCED BY PAID CLAIMS
INSRI MUULnUHtt
LTR TYPE OFINBURANCE INBD WVD POLICY NUMBER
POLICY EFF POLICY E%P
IMMIDOIYYYYI (Mail DIYYYV)
LIMITS 1
MERCIAL GENERAL LIABILITY
EACH OCCURRENCE
1,000,000 II(
rp
CLAIMS -MADE ®OCCUR
OH
PREMISES IEa occurrence)
$
$ 1,000,000
EXP(Any ene Person)
$ 10,000
AI
CPR 2083085
06/28/2023 06/26/2024 I PERSONAL&ADV INJURY
$ 1,000,000
G ONAGGREGATE LIMITAPPLIES PER
GENERAL AGGREGATE
$ 2,000,000
® JEOT
2,000,000
POLICY
LOC
PRODUCTS-COMP/OPAGG
$
OF ER
$
AUTOMOBILE LIABILITY
COMBINED SINGLE LIMIT
$ 1,000,000
IEa accidenn
�( ANYAUTO
BODILY INJURY (Per person)
$
OVJNED
B - AUTOS ONLY
SCHEDULED CA2055209
AUTOS
06/28/2023 06/26/2024
eoolLV WJURv Par aeeldant
( )
$
HIRED
N014-OWNED
t PROPERTY DAMAGE
$
AUTOS ONLY
AUTOS ONLY
(Per accident)
X UMBRELLALIAB X OCCUR
A EXCESS LIAR ICLAIMS-MADE
DED I XI RETENTION S D
WORKERS COMPENSATION
AND EMPLOYERS' LIABILITY YIN
ANY PROPRIETORIPARTNER/EXECUTIVE
B OFFICERIMEMBER EXCLUDED? N NIA
(Mandatory in NH)
f yes, describe under
DESCRIPTION OF OPERATIONS below
C Contractors Equipment
CU2030254 06/28/2023 08/28/2024
WC2030265 06/28/2023 06/28/202x
EACH OCCURRENCE $ 5,000,000
AGGREGATE $ 5,000,000
S
X STATUTE EERH
EL EACH ACCIDENT
EL DISEASE - EA EMPLOYEE
EL DISEASE -POLICY LIMIT
Scheduled Equipment
IHD D942549 04 06/28/2023 06/28/2024 1Leased/Rented
DESCRIPTION OF OPERATIONS LOCATIONS I VEHICLES 1AC3RD 101, Additional Remarks Schedule, maybe attached if more space Is required)
Project Trinity Lakes Mixed Use South,Phase I City Project No. — 103849, X No—X-27190; FID No.—30114-0200431-103849-EO7685 File No — W-2804
BLANKET ADDTIONAL INSURED APPLIES ON THE ABOVE LISTED GENERAL LIABILITY POLICY. BLANKET WAIVER OF SUBROGATION APPLIES
ON THE ABOVE LISTED GENERAL LIABILITY POLICY PRIMARY AND NON-CONTRIBUTORY APPLIES ON THE ABOVE LISTED GENERAL
LIABILITY POLICY. BLANKET WAIVER OF SUBROGATION APPLIES TO THE ABOVE LISTED WORKERS COMPENSATION POLICY. BLANKET
ADDTIONAL INSURED AND WAIVER OF SUBROGATION APPLIES TO THE ABOVE LISTED COMMERICAL AUTO POLICY UMBRELLA IS FOLLOW
FORM
CERTIFICATE HOLDER CANCELLATION
1,000,000
1,000,000
1,000,000
3,519,930
25,000
SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE
THE EXPIRATION DATE THEREOF, NOTICE WILL BE DELIVERED IN
City of Fort Worth ACCORDANCE WITH THE POLICY PROVISIONS,
200 Texas St
AUTHORIZED REPRESENTATIVE
Fort Worth TX 76102
I
9)1988.2015 ACORD CORPORATION. All rights reserved.
ACORD 25 (2016/03) The ACORD name and logo are registered marks of ACORD
BID QUALIFICATION:
01 This proposal is submitted with the understanding that the owner's
credit and financial arrangements for making payment under the
Contract are satisfactory to Stabile & Winn, Inc.
02 Partial Payments on the Fifteenth of the next month, Final
Payment immediately upon acceptance from Owner.
03 Two Year Maintenance Bond is included.
04 All Testing, Soil Series, and Coring for Compliance to be furnished & paid for by others.
05 Construction Staking is not included.
06 Inspection Fees, if any, to be paid for by others.
07 Backfill all work is included.
08 Utility Relocations, if any, to be furnished & paid for by others.
09 Temporary Barricades with t_ites & Signage are included.
10 Imported Material {Topsoil, Select Fill, etc.) & Seeding Parkways are not included.
11 After the Utility Contractor has completed their work, the Street
Subgrade and Parkways must be restored to +/- 0.10 Ft. by others
or it will be done on a Force -Account -Basis.
12 Sales Tax is not included.
13 The Erosion Control Plan (SWPPP), and the implementation of
the plan are not included. However, the maintaining of the
existing implementation is included.
14 Unit Prices are contingent upon all the incorporated materials being installed prior to
March 31, 2023- if all the incorporated materials cannot be installed within this time frame,
then our unit prices maybe subjected to increases due to delays that are not within our cause
or scope of work, and shall be treated as a Change Order to the Contract.
This Bid Qualification is a part of this Contract
Contractor: STABILE & WINN, INC.
Signed:
�Y
John UV. Stabiie
President
STREET LIGHTS
STF DESIGN & BUILD
0045 12
DAP PREQUALIFICATION STATEMENT
Page 1 of 1
SECTION 00 45 12
DAP - PREQUALIFICATION STATEMENT
Each Bidder is required to complete the information below by identifying the prequalified contractors
and/or subcontractors whom they intend to utilize for the major work type(s) listed. In the "Major Work
Tvpe" box provide the complete major work tvpe and actual descriution as provided by the Water
Department for water and sewer and TPW for paving.
Major Work Type Contractor/Subcontractor Company Name Prequalification
Expiration Date
Street Lighting and Electric STF Design and Build. 04/22/24
The undersigned hereby certifies that the contractors and/or subcontractors described in the table above
are currently prequalified for the work types listed.
BIDDER:
STF Design and Build BY:
2820 East Belknap Street
Fort Worth, Texas 761.1.1
/(S'ignature)
TITLE:
DATE: 2 1 j 2-2-
END OF SECTION
CITY OF FORT WORTH
STANDARD CONSTRUCTION PREQUALIFICATION STATEMENT— DEVELOPER AWARDED PROJECTS
00 45 12_Prequalification Statement 2015_DAP Street Lights (002)
Form Version September 1, 2015
00 52 43 - 1
Developer Awarded Protect Agreement
Page I of 4
SECTION 00 52 43
2 AGREEMENT
3 THIS AGREEMENT, authorized on +,I /L1/&0, is made by and between the Developer.
4 Trinity Lakes Partners, LLC, authorized to d❑ business in Texas ("Developer"), and STF Design
5 & Build., authorized to do business in Texas, acting by and through its duly authorized
6 representative, ("Contractor").
7 Developer and Contractor, in consideration of the mutual covenants hereinafter set forth, agree as
8 follows.
9 Article 1. WORK
10 Contractor shall complete all Work as specified or indicated in the Contract Documents for the
11 Project identified herein.
12 Article 2. PROJECT
13 The project for which the Work under the Contract Documents may be the whole or only a part is
14 generally described as follows:
15 Trinity Lakes Mixed Use South. Phase 1
16 City Project No.—103849; _k No.—X-27190; IID No. — 30114-0200431-10.3849-E076(U
17 File No. — W-2804
18 Article 3. CONTRACT TIME
19 3.1 Time is of the essence.
20 All time limits for Milestones, if any, and Final Acceptance as stated in the Contract
21 Documents are of the essence to this Contract_
22 3.2 Final Acceptance.
23 The Work will be complete for Final Acceptance within A0 working days after the date
24 when the Contract Time commences to run as provided in Paragraph 12.04 of the Standard
25 City Conditions of the Construction Contract for Developer Awarded Projects.
26 3.3 Liquidated damages
27
28
29
30
31
32
33
34
35
36
37
Contractor recognizes that time is of the essence of this Agreement and that Developer
will suffer financial loss if the Work is not completed within the times specified in
Paragraph 3.2 above, plus any extension thereof allowed in accordance with Article 10 of
the Standard City Conditions of the Construction Contract for Developer Awarded
Projects. The Contractor also recognizes the delays, expense and difficulties involved in
proving in a legal proceeding the actual loss suffered by the Developer if the Work is not
completed on time. Accordingly, instead of requiring any such proof, Contractor agrees
that as liquidated damages for delay (but not as a penalty), Contractor shall pay
Developer One thousand Dollars ($1.000.00) for each day that expires after the time
specified in Paragraph 3.2 for Final Acceptance until the City issues the Final Letter of
Acceptance.
CITY OF FORT WORT14 Tow0n• Lakes ,4 tavd i jse South. Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS— DEVELOPER AWARDED PROJECTS Ceti Pmlect Na - 143841?
Revised June 16, 2016
005243-2
Developer Awarded Projeet Agreement
Page 2 of 4
38 Article 4. CONTRACT PRICE
39 Developer agrees to pay Contractor for perfonrnance of the Work in accordance with the Contract
40 Documents an amount in current funds of Dollars
41 ($ 3 9s ;
42 Article 5. CONTRACT DOCUMENTS
43 5.1 CONTENTS:
44
A. The Contract Documents which comprise the entire agreement between Developer and
45
Contractor
concerning the Work consist of the following:
46
1.
This Agreement.
47
2.
Attachments to this Agreement:
48
a. Bid Form (As provided by Developer)
49
1 ) Proposal Form {DAP Version}
50
2} Prequalification Statement
51
3} State and Federal documents (project specific)
52
b. Insurance ACORD Form(s)
53
c. Payment Bond (DAP Version)
54
d. Performance Bond (DAP Version)
55
e. Maintenance Bond (DAP Version)
56
f. Power of Attorney for the Bonds
57
g. Worker's Compensation Affidavit
58
h. MBE and/or SBE Commitment Form (If required)
59
3.
Standard City General Conditions of the Construction Contract for Developer
60
Awarded Projects.
61
4.
Supplementary Conditions.
62
5.
Specifications specifically made a part of the Contract Documents by attachment
63
or, if not attached, as incorporated by reference and described in the Table of
64
Contents of the Project's Contract Documents.
65
6.
Drawings.
66
7.
Addenda.
67
S.
Documentation submitted by Contractor prior to Notice of Award.
68
9.
The following which may be delivered or issued after the Effective Date of the
69
Agreement and, if issued, become an incorporated part of the Contract Documents:
70
a. Notice to Proceed.
71
b. Field Orders.
72
c. Change Orders.
73
d. Letter of Final Acceptance.
74
75
CITY OF FORT WORTH iriniti? Lakes Mixed rlsr Suiah. Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS 0h- Preyeo Nfl. - 103849
Revised June 16.2016
Ud 52 43 - 3
Developer Awarded Project Agreement
Page 3 or4
76 Article 6. INDEMNIFICATION
77 6.1 Contractor covenants and agrees to indemnify, hold harmless and defend, at its own
78 expense, the city, its officers, servants and employees, from and against any and all
79 claims arising out of, or alleged to arise out of, the work and services to be performed
80 by the contractor, its officers, agents, employees, subcontractors, licenses or invitees
81 under this contract. This indemnification Drovision is specifically intended to operate
82 and be effective even if it is alleged or proven that all or some of the damages being
83 s ught were caused, in whole or in part. by anv act. omission or ne Iigence of the city.
84 This indemnity provision is intended to include, without limitation, indemnity for
85 costs, expenses and legal fees incurred by the city in defending against such claims and
86 causes of actions.
87
88 6.2 Contractor covenants and agrees to indemnify and hold harmless, at its own expense,
89 the city, its officers, servants and employees, from and against any and all loss, damage
90 or destruction of property of the city, arising out of, or alleged to arise out of, the work
91 and services to be performed by the contractor, its officers, agents, employees,
92 subcontractors, licensees or invitees under this contract. This indemnification
93 provision is specifically intended to onerate and be effective even if it is alleged or
94 proven that all or some of the damages being sought were caused. in whole or in Dart,
95 by anv act. omission or negli of the city.
96
97 ArticIe 7. MISCELLANEOUS
98 7.1 Terms.
99 Terms used in this Agreement are defined in Article l of the Standard City Conditions of
100 the Construction Contract for Developer Awarded Projects.
101 7.2 Assignment of Contract.
102 This Agreement, including all of the Contract Documents may not be assigned by the
103 Contractor without the advanced express written consent of the Developer.
104 7.3 Successors and Assigns.
105 Developer and Contractor each binds itself, its partners, successors, assigns and legal
€fib representatives to the other party hereto, in respect to all covenants, agreements and
107 obligations contained in the Contract Documents.
108 7.4 Severability.
109 Any provision or part of the Contract Documents held to be unconstitutional, void or
110 unenforceable by a court of competent jurisdiction shall be deemed stricken, and all
Ill remaining provisions shall continue to be valid and binding upon DEVELOPER and
112 CONTRACTOR,
113 7.5 Governing Law and Venue.
114 This Agreement, including all of the Contract Documents is performable in the State of
115 Texas. Venue shall be Tarrant County, Texas, or the United States District Court for the
116 Northern District of Texas, Fort Worth Division.
CFrY OF FORT WORTH Trio ;- C ekes .khwd Ilse ,South. 11GarG I
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS C q 1 f N4v
Revised June 16, 2016
117
IN
119
120
121
122
123
124
125
126
12'7
00 52 43 - 4
Developer Awarded Project Agreemerit
Page 4 of
7.6 Authority to Sign.
Contractor shall attach evidence of authority to sign Agreement, if other than duly
authorized signatory of the Contractor.
IN WITNESS WHEREOF, Developer and Contractor have executed this Agreement in multiple
counterparts.
This Agreement is effective as of the last date signed by the Parties ("Effective Date').
Contractor: STF Design & Build Developer: Trinity Lakes Partners, LLC
By: /
(Si attire)
Larry Hussey
(Printed Name)
Title: Vice President
Company Name: STF Design & Build
Address: 2820 East Belknap St.
City/State/Zip: Ft. Worth, TX 761 1 1
11'2 I I Z C, -2 2-
Date
Si na � g re)
Kenneth B. Newell
(Printed Name)
Title: Member
Company name: Trinity Lakes Partners, LLC
Address: PO Box 185104
City/State/Zip: Ft. Worth, TX 76181
Date
CITY OF FORT WORTH TNeiin, Lahov +Ika f t* SarNh, Pjlasr, 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS— DEVELOPER AWARDED PROJECTS C'io, Prgjeci No. - 10384SO
Revised lunc 16, 2016
Bond No. 4456179
006213-1
PERFORMANCE BOND
Page 1 of 2
1 SECTION 00 62 13
2 PERFORMANCE BOND
3
4 THE STATE OF TEXAS §
5 § KNOW ALL BY THESE PRESENTS-
6 COUNTY OF TARRANT §
7 That we, STF Desiun & Build known as "Principal"
8 herein and SureTec Insurance Company , a corporate surety(sureties, if
9 more than one) duly authorized to do business in the State of Texas, known as "Surety" herein
10 (whether one or snore), are held and firmly bound unto the Developer, Trinity Lakes Partners,
l i LLC, authorized to do business in Texas ("Developer") and the City of Fort Worth, a Texas
12 municipal corporation ("City"), in the penal sum of,
13 Three Hundred Ninety Five Thausand Twenty Nine and No11 QO Dollars (S 395,029,00
14 lawful money of the United States, to be paid in Fort Worth, Tarrant County, Texas for the
15 payment of which sum well and truly to be made jointly unto the Developer and the City as dual
16 obligees, we bind ourselves, our heirs, executors, administrators, successors and assigns, jointly
17 and severally, firmly by these presents.
is WHEREAS, Developer and City have entered into an Agreement for the construction of
19 community facilities in the City of Fort Worth by and through a Community Facilities
20 Agreement, CFA Number CFA22-0177: and
21 WHEREAS, the Principal has entered into a certain written contract with the Developer awarded
22 the 21 St day of November , 20 22, which Contract is hereby referred to and made a
23 part hereof for all purposes as if fully set forth herein, to furnish all materials, equipment labor
24 and other accessories defined by law, in the prosecution of the Work, including any Change
25 Orders, as provided for in said Contract designated as Trini); Lakes ML-ve l Use Sown. Phase 1,
26 NOW, THEREFORE, the condition of this obligation is such that if the said Principal
27 shall faithfully perform it obligations under the Contract and shall in all respects duly and
28 faithfully perform the Work, including Change Orders, under the Contract, according to the plans,
29 specifications, and contract documents therein referred to, and as well during any period of
30 extension of the Contract that may be granted on the part of the Developer and/or City, then this
31 obligation shall be and become null and void, otherwise to remain in full force and effect.
CITY OF FORT WORTH Tri.ri[y f.nkes :Sliced Use soarh Phrlse
STANDARD CITY CONDIT[ON5 — DEVELOPER AWARDED PROJECTS CYn• PrnjeV1 hn.
Revised January 31, 2012
1
2
3
4
5
6
006213-2
PERFORMANCE BOND
Page 2 of 2
PROVIDED FURTHER, that if any legal action be filed on this Bond, venue shall lie in
Tarrant County, Texas or the United States District Court for the Northern District of Texas, Fort
Worth Division.
This bond is trade and executed in compliance with the provisions of Chapter 2253 of the
Texas Government Code, as amended, and all liabilities on this bond shall be determined in
accordance with the provisions of said statue.
7 IN WITNESS WHEREOF, the Principal and the Surety have SIGNED and SEALED
8 this instrument by duly authorized agents and officers on this the 23rd day of
9 November , 20 22 .
to
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
ATTEST.
(Principal) Secretary
Witness as to Principal
Witness as to Surety 1Nlliam Mitchell Jennings
PRINCIPAL:
ST)✓ Desizn & Build
BY: .` r�
Signa
VP
Name and Title
Address: 2820 East Belknav Street
Fort Worth, TX 76111
SURETY:
SureTec Insurance Company
BY: As
i Pe `
Payton Blanchard, Attornt�i--il_)_ act
Name and Title
Address: 2103 Citywest Blvd. Suite 1300
Houston, TX 77042
Telephone Number: 713-812-0800
*Note: If signed by an officer of the Surety Company, there must be on file a certified extract
from the by-laws showing that this person has authority to sign such obligation. If
Surety's physical address is different from its mailing address, both must be provided.
The date of the bond shall not be prior to the date the Contract is awarded.
CITY OF FORT WORTH Trinio- Lakes Alined Mu South, Piwse t
STANDARD CrrY C0NDrrZ0NS - DEVELOPER AWARDED PROIECTS Ci1r Proert An. - 103849
Rcvistd January 31. 2012
POA #: 4221178
SureTec Insurance Company
LIMITED POWER OF ATTORNEY
KnawA 11 Men by These Present-% That SURETEC INSURANCE COMPANY (the "Company"), a c o rpo ra I. i on duly organized and
existing under the la ws ofthe State ❑fTexas, and having its principal office in Houston, Harris County, Texas, d o es by these p re senIs
make, constitute and appoint
William Mitchell Jennings, Lindsay Senior Gingras, Jessica Turner, Payton Blanchard, William Blanchard, James R. Reid, Markham Paukune
its true a n d I wful Attorney -in -fact, with full p ower and authority hereby co nferred in its na me, place and stead, to ex ecu te, ackn owle dor ge
and deliver any and all bonds, recogpizances,undertakings or ctherinstruments or contracts of suretyship to include waivers to the
conditions of contracts and consentsafsuretyfor, providingthebond penalty does not exceed
Five Million and 001100 Dollars ($5,000,000.00)
and to bind the Company therebyas fully and to the same extentas if such bond were signed by the President, sealedwith the corporate
sea lof the Company and duly atLes tedby its Secretary, It ereby ra tifyin g a nd confirming all that the said Attomey- in -Fa cI m ay do in the
premises. Saidappointmentismadeunderandbyauthorityofthe followingresolutions of the Board of Directors of theSureTec
Insurance Company:
Be it Resohved, that the President, any Vice -President, arty Assistant Vice -President, any Secretary a any AssistantSec retary s11 al I b e and is
hereby vested with full power and authority to appoint any one or more suitable persons as Attarney(s)-in-Fact to represent and act for and ❑ n
behaifof the Company subject the following provisions:
Artor•ney-in-Fact may be given full power and authority for and in the name of and of behalf of the Company, to execute, acknowledge and
deliver, any and all bands, me a gn izan ces, contracts, agreements or indemnity and othercon ditiMat arobligatory undertakings and any and all
notices and documents canceling or terminating the Company's liability thereunder, and any such instruments so executed by any such
Attorney -in -Fact shall be bindingupon the Company as if signed by the Presidentand scaled and effected by the Corporate Secretary,
Be ii Resolved, that the signature of any autharized officer and seal of the Company heretotore or hereafter affixed to any power of attorney or
any certificate relating thereto by facsimile, and any power of attorney or certificate hearing facsimile signature or facsimile seal 5ha11 be valid
and binding upon the Company with respect to any bond or undertakingto which it is attached. (Adapted ata meeting held on 2 0 of Ap r•iI,
1999.)
In Witness Whereof, SURETEC INSURANC E COMPANY has caused these presents to be signed by its President; and its corporate sea]
to be hereto affixed this 11th day of January. A.D. 2D22
SURETEC iNSU A,NCE COMPANY
(�tW
Byt =>=_ MichaelC.Keimig,President
State ofTexas ss:
County of Harris
On this tit" day of January, A.D. 2022 before me personally came Michael C. Keimig, to me known, who, being by me duly sworn, did depose and
say, that he resides in Houston, Texas, that he is President of SURETEC INSURANCE COMPANY, the company described in and which executed the
above instrument, that he knows the seal of said Company; that the sea] affixed to said instrument is such corporate seal; that it was so affixed by order of
the Board of Directors o f s a i d Company: and that he signed his name thereto by like order.
- - - - -
- XENIA CHAVEZ
_
Notary Pubtic, Slale ofTesas t
_-
Notary 1D# 12911765-9
J;., r't hAy Comm:sstan Ettpirss t
SEPTEMBER
10, 2024 ;
t av _iota >x ex , ry Puhli
y commission expires September 10, 2 024
I, M, Brent Beaty, Assistant Secretary ofSEIR.ETEC INSURANCE COMPANY, do hereby certify that the above attd foregoing is a true and correct copy
ofa Power of Attorney, executed by said Company, which is still in Full Farce and effect; and furthermore, the resolutions ofthe Board of direct❑ rs, s et
out in the Power of Attorney are in full fore: s1'3 efTaet,
Given under my hand and thesealof said Companyat Houston, Texas this 23rd day of Dove ber 2 A.D.
M. Br'eutBeaty,AssistantS retary
Any instrumentissued in excess afthe penalty stated above is totally void and without any validity. 4221178
For verification ofthe authority of this power you may call (713) 812-0800 anybusiness day between 8:30 am and 5:00 pm CST,
Bond No. 4458179
00Q 14-1
PAYMENTBOND
Page 102
1 SECTION 00 62 14
2 PAYMENT BOND
3
4 THE STATE OF TEXAS §
5 § KNOW ALL BY THESE PRESENTS:
6 COUNTY OF TARRANT §
7 That we, SIT Desian & Build known as
8 "Principal" herein, and SureTec Insurance Company , a
9 corporate surety ( or sureties if more than one), duly authorized to do business in the State of
10 Texas, known as "Surely" herein (whether one or more), are held and finely bound unto the
11 Developer, Trinity Lakes Farmers, LLC, authorized to do business in Texas "(Developer"), and
12 the City of Fort Worth, a Texas municipal corporation ("City"), in the penal sum
13 of Three Hundred Ninety Five Thousand Twenty Nine and Noll00 Dollars S 395,029.00 )
14 lawful money of the United States, to be paid in Fort Worth, Tarrant County, Texas, for the
15 payment of which sum well and truly be made jointly unto the Developer and the City as dual
16 obligees, we bind ourselves, our heirs, executors, administrators, successors and assigns, jointly
17 and severally, firmly by these presents:
Is WHEREAS, Developer and City have entered into an Agreement for the construction of
19 community facilities in the City of Fort Worth, by and through a Community Facilities
20 Agreement, CIA Number CFA22-0177;and
21 WHEREAS, Principal has entered into a certain written Contract with Developer,
22 awarded the 21st day of November , 20 22 which Contract is hereby
23 referred to and made a part hereof for all purposes as if fully set forth herein, to furnish all
24 materials, equipment, labor and other accessories as defined by law, in the prosecution of the
25 Work as provided for in said Contract and designated as Trinity Lakes Mixed Use South. Phase 1.
26 NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION is such that if
27 Principal shall pay all monies owing to any (and all) payment bond beneficiary (as defined in
28 Chapter 2253 of the Texas Government Code, as amended) in the prosecution of the Work under
29 the Contract, then this obligation shall be and become null and void; otherwise to remain in full
30 force and effect.
CITY OF FORT WORTH horn, Laker daaed 11x-w,A Phone I
STANDARD CITY CONDITIONS— DEVELOPER AWARDED PROIECIS 04•hy.1 No-103849
Revised danusy 31, 2012
006214-2
PAYMENT BOND
Page 2 cf 2
1 This bond is made and executed in compliance with the provisions of Chapter 2253 of the
2 Texas Govermnent Code, as amended, and all liabilities on this bond shall he determined in
3 accordance with the provisions of said statute,
4 IN WITNESS WHEREOF, the Principal and Surety have each SIGNED and SEALED
5 this instrument by duly authorized agents and officers on this the 23rd day of
6 November .20 22
7
PRINCIPAL:
STF Desien & Build
ATTEST: BY. -
Sig e
//V S cs tiI
(Principal) Secretary Name and Title
Address: 2820 East Belknap Street.
Fort Worth, TX 76111
Witness as to Principal
SURETY:
SureTec insurance Company
ATTEST: BY:Af 6
Signatge
Payton Blanchard, Attorney -in -Fact
{Sure Secretary Jessica Turner Name and Title
Address: 2103 Citywest Blvd. Suite 1300
Houston, TX 77042
Witness as to Surety William Mitchell Jennings
Telephone Number: 713-812-0800
8
9 Note: If signed by an officer of the Surety, there must be on file a certified extract from the
14 bylaws showing that this person has authority to sign such obligation. If Surety's physical
1 t address is different from its mailing address, both must be provided.
12
13 The date of the bond shall not be Friar to the date the Contract is awarded.
14 END OF SECTION
CITY OF FORT WORTH Tiimnr Lakes Ahed 11se .%nih. Phase 1
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS C'fn• Project Ala - 163,349
Revised January 31, 2012
POA #: 4221178
SureTec Insurance Company
LIMITED POWER OF ATTORNEY
ItnowAItMen byThese Present,,That 5URETECINSURANCE COMPAN-Y(the "Company"), a corporation duly organized and
existing under the lawsoftheState ofTexas,andhaving its principaIoffice inHouston,Harris Ccunty,Texas, does by thesepresents
m akt , const itute a nd appo int
William Mitchell Jennings, Lindsay Senior Gingms, Jessica Turner, Payton Blanchard, William Blanchard, Jaynes R. Reid, Markham Paukune
its true and la wfulAttomey-in-fact, with full powerand authority hereby conferred in its name, place and stead, to execute, acknowledge
and deliver any and all bonds, recognizances, undertakings or other instruments or contracts of suretyship to irtc Jude waiv ers to the
conditions of contracts and conseuts ofsurety for, prov iding the bond penalty does not exceed
Five Million and 001100 Dollars ($5,000,400.00)
and to bind the Company thereby s fully and to the same extent as if such bond were signed by the President, sealed with the co rporate
seal of the Company andduly attested by its Secretary, hereby ratifying and confirming as that the said Attorney -in -Fact rn ay d o in the
premises. Said appointment is ma de under and by authority of the following resolutions of the Board of Directors of the SureTec
Insurance Company:
Be it Resolved, that the President_ any Vice -President, any Assistant Vice -President, any Secretary or any Assistant Secretary shall h e an d is
hereby vested with fullpower and authority to appointany one or more suitable persons as Attorney(s)-in-Factto represent and act for and on
behalfof the Company subject to the following provisions:
rlrtomey-in-Faer may he given full power and authority for and in the name of and of behalfof the Company, to execute, acknowledge and
deliver, any and all bonds, reco gn i zan ces, contracts, agreements or indemnity and other conditional ❑robIigatory undertakings and any and all
notices and documents canceling or terminating the Company's liability thereunder, and any such instruments so executed by any such
Attorney -in- Fact sha11 be binding upon the Company as ifsigned by the Presidentand sealed and effected by the Corporate Secretary.
Be it Resolved, that the signature afany authorized officer and seal ofthe Company heretofore or hereafter affixed to any power of attorite y o r
any certificate relating thereto by facsimile, and any power of attorney or certificate bearing facsim ile signature at Facsimile seal shall be v a] id
and bindingupan the Company with respectto any band o r u n dertakin g to wh i ch it is attached. (Adopted arameeting held ❑n 2 0 " of Apri1,
1999.)
In W ittress iYhereof, SURETEC INSURANCE COMPANY has caused these presents to be signedby its President, and its corporate seat
to be hereto affixed this inn dayof January , A.D. 2022
SURET EC INSURANCE COMPANY
Iro.:
By:
[r
Lit 15 Michael C. Keimig, Pre
sidertt
State orTexas ss: 1n
County of Harris
on this ivri day of dsnuary. , A.D. zom before me personally came Michael C. Keimig, to me known, who, being by me duly sworn, did depose and
say, that he resides in Houston, Texas, that he is President of 8LIRETEC INSURANCE COMPANY, the company described in and which execu t e d tlt e
above instrument; that he knows the seal of said Company; that the seal affixed to said instrument is such corporate seal; that it was so affixed by order of
the Board of Directors of said Company; and that he signed his name thereto by like order.
- XENIA CHAVEZ ;
L �' Nolaty Puolic. State pl Texas i
%ZI�609
= Notary Id# 12911755-9 y haven,(0t-a4ty Pubii
My Garnmismn Expires
t ,'F' '•� y commission expires Septern 10,2024
SEPTEMBER 102024
L, lot, Brent Beaty, Assistant Secretary of SURE TEC INSURANCE COMPANY, do h e reby certi fy thatthc above and foregoing is a true and correct copy
of Power of Attorney, executed by said Company, which is still in full forge and effect; and furthermore, theresolutions of the Board of Directors, s et
out in the Power orAttorney are in ful! rorce and effect.
Given under my hand and sheseal ofsaid CampanyatHouston, Texas this .23rd dayof November 22 A.D.
M. B entBeaty,Assistant5 retary
Any instrument issued in exc"s of the penalty stated above is totally void and without any validity. 4221178
For verification of the authority of this power you may call (713) 812-0800 any business day between 8:30 am and 5:00 pm CST.
Bond No. 4456179
00 62 19- 1
MAMTENANCE BOND
Pegs i of3
1 SECTION 00 6219
2 MAINTENANCE BOND
3
4 THE STATE OF TEXAS §
5 § KNOW ALL BY THESE PRESENTS:
6 COUNTY OF TARRANT §
7
8 That we, STF Desien & Build , known as "Principal"
9 herein and SureTec Insurance Company , a corporate surety (sureties, if
10 more than one) duly authorized to do business in the State of Texas, known as "Surety" herein
i l (whether one or more), are held and firmly bound unto the Developer, Trinity Lakes Partners,
12 LLC, authorized to do business in Texas ("DevelopeeD and the City of Fort Worth, a Texas
13 municipal corporation ("City"), in the sum of Three Hundred Ninety Five Thousand Twenty Nine and No/i 00
14 Dollars ($ 395,029.00 ), lawful money of the United States, to be paid in Fort
15 Worth, Tarrant County, Texas, for payment of which sum well and truly be made jointly auto the
16 Developer and the City as dual obligees and their successors, we bind ourselves, our heirs,
17 executors, administrators, successors and assigns, jointly and severally, firmly by these presents.
18
19 WHEREAS, Developer and City have entered into an Agreement for the construction of
20 community facilities in the City of Fort Worth by and through a Community Facilities
21 Agreement, CFA Number CFA22-0177; and
22 WHEREAS, the Principal has entered into a certain written contract with the Developer
23 awarded the 21 at day of November , 2022 which Contract is
24 hereby referred to and a made part hereof for all proposes as if fully set forth herein, to furnish all
25 materials, equipment labor and other accessories as defined by law, in the prosecution of the
26 Work, including any Work resulting from a duly authorized Change Order (collectively herein,
27 the "Work") as provided for in said Contract and designated as Trinity Lakes Mixed Use South.
28 Phase 1; and
29
30 WHEREAS, Principal binds itself to use such materials and to so construct the Work in
31 accordance with the plans, specifications and Contract Documents that the Work is and will
32 remain free from defects in materials or workmanship for and during the period of two (2) years
33 after the date of Final Acceptance of the Work by the City ("Maintenance Period); and
34
CJTYOF FORT WORTH T wu, Lrt4ee :lflxd U.. Somh, Phaa J
STANDARD CITY CONDITIONS -DEVELOPER AWARDED PROJECTS Ciry Pi»/ea Na -1038J9
R &dJ.o 31,2012
006219-2
MAINTENANCE BOND
Page 2 of 3
I WHEREAS, Principal binds itself to repair or reconstruct the Work in whole or in part
j upon receiving notice from the Developer and/or City of the need thereof at any time within the
3 Maintenance Period.
4
5 NOW THE, the condition of this obligation is such that if Principal shall
6 remedy any defective Work, for which timely notice was provided by Developer or City, to a
7 completion satisfactory to the City, then this obligation shall become null and void; otherwise to
S remain in full force and effect.
9
l0 PROVIDED, HOWEVER, if Principal shall fail so to repair or reconstruct any timely
1 I noticed defective Work, it is agreed that the Developer or City may cause any and all such
12 defective Work to be repaired and/or reconstructed with all associated costs thereof being borne
13 by the Principal and the Surety render this Maintenance Bond; and
14
15 PROVIDED FURTHER, that if any legal action be filed on this Bond, venue shall lie in
16 Tarrant County, Texas or the United States District Court for the Northern District of Texas, Fort
17 Worth Division; and
l8
19 PROVIDED FURTHER, that this obligation shall be continuous in nature and
20 successive recoveries may be had hereon for successive breaches.
21
22
23
CITY OF FORT WORTH Twilit, Lakes Mixer! U: ve South. Phaw i
STANDARD CITY CONDITIONS - DEVELOPER AWARDED PROJECTS cin- r'rgacr G'a. - 103,349
Revised January 31, 2012
006219-3
MAINTENANCE BOND
Page 3 of 3
1 IN WITNESS WHEREOF, the Principal and the Surety have each SIGNED and SEALED this
2 instrument by duly authorized agents and officers on this the 23rd day of
3 November 20 22 .
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
44
41
42
(Principal) Secretary
Witness as to Principal
ATTEST:
(Sur ) Secretary Jessica urner
qyl /1&._ ,
Witness as to Surety William Mitchell Jennings
PRINCIPAL:
STF Desien & Build
BY:
Si e
ame and Title
Address: 2920 East Belknap Street
Fart Worth, TX 76111
SURETY:
SureTec Insurance Company
BY 941
Si4 e
Pavton Blanchard. Attornc;Lr-Fact
Name and Title
Address. 2103 Citywest Blvd. Suite 1300
Houston. TX 77042
Telephone Number: 713-812-0800
*Note: If signed by an officer of the Surety Company, there must be on file a certified extract
from the by-laws showing that this person has authority to sign such obligation. If
Surety's physical address is different from its mailing address, both must be provided.
The date of the bond shall not be prior to the date the Contract is awarded.
CITY OF FORT WORTH r+imil. Lakds IhreJ f:,ee Split h, phase 1
STANDARD CITY CONDITIONS — Dr-VFI,OPF.R AWARDED PROJECTS ('11y Projecl ivo. - 103841
Revised January 31, 2012
POA #-. 42211 T8
SureTec Insurance Company
LIMITED POWER OF ATTORNEY
Know A 11 Men by These Present% That SURETEC INSURANCE COMPANY (the "Company'), acorporaIio❑ duly ❑rganized and
existing under the lawsnftheState ofTexas,andhavingits principaIoffice in Houston,Harris County,Texas, daes by these presents
m ake, constitute and appoint
William Mitchell Jennings, Lindsay Senior Gingras. Jessica Turner, Payton Blanchard, William Blanchard, James R. Reid, Markham Paukune
its true and lawful Attorney-in-fact,,Mth full power and authority hereby conferred in its name, place and stead, to execute, acknowledge
and deliver any andallbonds, recognizances,undertakings or other instruments or contracts of suretyship to include waivers to the
conditions of contmcts and consents of surety for, prov id ing the bond penalty does no I exceed
Five Million and 0011 ❑0 dollars ($5,000,000.00)
and to bindthe Company thereby as fully and to the same extent as if such bond were signed by the President, sealed with the corporate
s e a I o f rheCompanyandduly aItestedby its 5ecretary,hereby ratifyingand confinnin g a R that the said Atto mey- in -Fact m a y do in the
premises. Said appointment ismadeunderandbyauthorityofthe followingresolutions ❑fthe Board of Directors of the SureTec
Insurance Company;
Be it Resolved, thatthe President, any Vice -President, any Assistant Vice -President, any Secretary or any Assistan[ Secretary shall be and is
hereby vested with full power and authority to appoint any one or more suitable persons as Attorneys) -in -Fact to representand act fpr and o a
behalfof the Company subject to the following provisions:
Rrromay-in-Fact may be given full power and authority for and in the name of and of behalfof the Company, to execute, acknowledge and
deliver, any and all bands, re cognizances, contracts, agreements a indemnity and other conditional orobligatory undertakings and any and all
notices and documents canceling or terminating the Company's liability thereunder, and any such instruments so executed by any such
Attorney-in-Factsh all be binding up on the Company as if signed by the President and sealed and effected by the Corporate Secretary.
Be it Resolved, that the signature of any authorized officer and seal oftbe Company hereto fore or hereafter affixed to any power of sun mey or
an y certi ficate relating thereto by facsimile, and any power of attorney or certificate b car ing facs im i le signature or facsimile seal shall be va I id
and bin ding upon the Company with respect to any bond or undertaking to which it is attached. (Adopted arameeting held o nz 2 qrh of Ap r-it
1999,)
In Witness Whereof, SUR ETEC INSURANCE COM PANY has caused these presents to be signedby its President, and its corporate seal
to be hereto affixed this 1ith day of January. A.D. 2022 .
SURETEC LNSURANCE COMPANY
;�StyRANC�C,
C>By;
w i w ; m; Michael C. Ttieimig,Presit3ent
State afTexas ss:
County ofHarris
On this 1 uh day of January. A.U. 2022 before me personally came Michael C. Keimig, tome known, who; being by me duly sworn, did depose and
say, that he resides in Houston, Texas, that he is President of SURETEC INSURANCE COMPANY, the company described in and which executed A e
above instrument; thathe knows the seal of said Company; thatthe seal affixed to said instmirientis such corporate seal; that it was so affixed by order of
the Board of Directors of said Company; and that he signed his name thereto by like order,
rs; y'P�
� `-
XENIA CHAVEZ ;
A
Notary Public, State of Texas Y
_r '• =
Notary iD# 12911765-9 t
Aty cammisston t xplle$ t
SE'TEMBER 10, 2024,
1 - a
hav nta u li� 'ice ez, Nry "CJ P kt ti
y t commissionexpires September 10,2024
1, M. Brent Beaty, Assistant Secretary ofSURETEC INSURANCE COMPANY. do hereby certify that the above and foregoing is a true and correct copy
of a Power ofAttorney, executed by said Company, which is still in full forceand effect; and furthermore, the resolutions of the Board of Directors , s et
out in the Power of Attorney are in fLII Force and effect.
Given ttndermy hand and hesealaf said Company at Houston, Texas this 23rd day of Noce? bet 022 A.D.
M. Brent Beaty, Assistant retary
Any instrument issued In excess of the penalty stated above is totally void and without any validity. 4221178
For verification of the authority of this power you may call (713) 812-0800 anybusiness day between 8:30 am and 5:00 pm CST.
SureTec Insurance Company
IMPORTANT NOTICE
Statutory Complaint Notice/Filing of Claims
To obtain information or make a complaint: You may call the Surety's tall free telephone number for information or to make
a complaint or file a claim at: 1-866-732-0099. You may also write to the Surety at:
SureTec Insurance Company
9737 Great Hills Trail, Suite 320
Austin, TX 78759
You may contact the Texas Department of Insurance to obtain information on companies, coverage, rights or complaints
at 1-800-252- 3439. You may write the Texas Department of Insurance at:
P❑ Box 149104
Austin, TX 78714-9104
Fax#: 512-490-1007
Web: httr)://www.tdi.texas.ciov
Email: ConsumerProtectlon@tdi.texas.gov
PREMIUM OR CLAIMS DISPUTES: Should you have a dispute concerning your premium or about a claim, you should
contact the Surety first. If the dispute is not resolved, you may contact the Texas Department of Insurance.
'rexQs Rider &2019
STANDARD CITY CONDITIONS
OF THE CONSTRUCTION CONTRACT
FOR DEVELOPER AWARDED PROJECTS
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
STANDARD CITY CONDITIONS OF THE
CONSTRUCTION CONTRACT
FOR DEVELOPER AWARDED PROJECTS
TABLE OF CONTENTS
Article 1 — Definitions and Terminology..........
1.01 Defined Terms ...............................
1.02 Terminology ..................................
Article 2 —
Preliminary Matters ......................
2.01
Before Starting Construction.....
2.02
Preconstruction Conference.......
2.03
Public Meeting ...........................
Page
.............................................1
.............................................1
............................................. 5
....................................................... 6
....................................................... 6
....................................................... 6
....................................................... 6
Article 3 — Contract Documents and Amending............................................................................................... 6
3.01 Reference Standards..................................................................................................................... 6
3.02 Amending and Supplementing Contract Documents.................................................................. 6
Article 4 — Bonds and Insurance....................................................................................................................... 7
4.01 Licensed Sureties and Insurers..................................................................................................... 7
4.02 Performance, Payment, and Maintenance Bonds........................................................................ 7
4.03 Certificates of Insurance............................................................................................................... 7
4.04 Contractor's Insurance.................................................................................................................. 9
4.05 Acceptance of Bonds and Insurance; Option to Replace...........................................................12
Article 5 —
Contractor's Responsibilities........................................................................................................12
5.01
Supervision and Superintendent.................................................................................................12
5.02
Labor; Working Hours................................................................................................................13
5.03
Services, Materials, and Equipment...........................................................................................13
5.04
Project Schedule..........................................................................................................................14
5.05
Substitutes and "Or-Equals".......................................................................................................14
5.06
Pre -Qualification of Bidders (Prime Contractors and Subcontractors).....................................16
5.07
Concerning Subcontractors, Suppliers, and Others...................................................................16
5.08
Wage Rates..................................................................................................................................18
5.09
Patent Fees and Royalties...........................................................................................................19
5.10
Laws and Regulations.................................................................................................................19
5.11
Use of Site and Other Areas.......................................................................................................19
5.12
Record Documents......................................................................................................................20
5.13
Safety and Protection..................................................................................................................
21
5.14
Safety Representative.................................................................................................................21
5.15
Hazard Communication Programs.............................................................................................22
5.16
Submittals....................................................................................................................................22
5.17
Contractor's General Warranty and Guarantee..........................................................................23
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
5.18 Indemnification ............................................
5.19 Delegation of Professional Design Services
5.20 Right to Audit: .............................................
5.21 Nondiscrimination ........................................
Article 6 - Other Work at the Site.......
6.01 Related Work at Site .......
Article 7 - City's Responsibilities ............................................
7.01 Inspections, Tests, and Approvals .......................
7.02 Limitations on City's Responsibilities ................
7.03 Compliance with Safety Program ........................
Article 8 - City's Observation Status During Construction.......
8.01 City's Project Representative .................................
8.02 Authorized Variations in Work ..............................
8.03 Rejecting Defective Work ......................................
8.04 Determinations for Work Performed ......................
Article 9 - Changes in the Work ......................
9.01 Authorized Changes in the Work
9.02 Notification to Surety ...................
Article 10 - Change of Contract Price; Change of Contract Time
10.01 Change of Contract Price ...........................................
10.02 Change of Contract Time ...........................................
10.03 Delays.........................................................................
24
24
25
25
26
26
26
26
26
27
.......................... 27
.......................... 27
.......................... 27
.......................... 27
.......................... 28
Article 11 - Tests and Inspections; Correction, Removal or Acceptance of Defective Work ............
11.01 Notice of Defects..............................................................................................................
11.02 Access to Work.................................................................................................................
11.03 Tests and Inspections........................................................................................................
11.04 Uncovering Work.............................................................................................................
11.05 City May Stop the Work...................................................................................................
11.06 Correction or Removal of Defective Work......................................................................
11.07 Correction Period..............................................................................................................
11.08 City May Correct Defective Work...................................................................................
Article 12 - Completion ...........................................
12.01 Contractor's Warranty of Title ............
12.02 Partial Utilization .................................
12.03 Final Inspection ....................................
12.04 Final Acceptance ..................................
Article 13 - Suspension of Work .....................................
13.01 City May Suspend Work .............................
Article 14 - Miscellaneous ..........................................
14.01 Giving Notice ..........................................
CITY OF FORT WORTH
STANDARD CITY CONDITIONS -DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
a
a
a
a
... 29
... 29
... 29
... 29
... 30
... 30
... 30
... 30
... 31
................................. 32
................................. 32
................................. 32
................................. 32
................................. 33
............................................................. 33
............................................................. 33
34
34
14.02 Computation of Times................................................................................................................ 34
14.03 Cumulative Remedies................................................................................................................. 34
14.04 Survival of Obligations...............................................................................................................35
14.05 Headings......................................................................................................................................35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
0073 10- 1
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page I of 35
ARTICLE 1— DEFINITIONS AND TERMINOLOGY
1.01 Defined Terms
A. Wherever used in these General Conditions or in other Contract Documents, the terms listed
below have the meanings indicated which are applicable to both the singular and plural thereof,
and words denoting gender shall include the masculine, feminine and neuter. Said terms are
generally capitalized or written in italics, but not always. When used in a context consistent with
the definition of a listed -defined term, the term shall have a meaning as defined below whether
capitalized or italicized or otherwise. In addition to terms specifically defined, terms with initial
capital letters in the Contract Documents include references to identified articles and paragraphs,
and the titles of other documents or forms.
1. Agreement - The written instrument which is evidence of the agreement between Developer
and Contractor covering the Work
2. Asbestos —Any material that contains more than one percent asbestos and is friable or is
releasing asbestos fibers into the air above current action levels established by the United
States Occupational Safety and Health Administration.
3. Business Day — A business day is defined as a day that the City conducts normal business,
generally Monday through Friday, except for federal or state holidays observed by the City.
4. Buzzsaw — City's on-line, electronic document management and collaboration system.
5. Calendar Day — A day consisting of 24 hours measured from midnight to the next midnight.
6. City— The City of Fort Worth, Texas, a Texas home -rule municipal corporation, acting by,
its governing body through its City Manager, his designee, or agents authorized pursuant to
its duly authorized charter on his behalf.
7. Community Facilities Agreement (CFA) A Contract between the Developer and the City
for the Construction of one or more following public facilities within the City public right-of-
way or easement: Water, Sanitary Sewer, Street, Storm Drain, Street Light, and Street Signs.
A CFA may include private facilities within the right-of-way dedicated as private right-of-
way or easement on a recorded plat.
8. Contract —The entire and integrated written document incorporating the Contract
Documents between the Developer, Contractor, and/or City concerning the Work. The
Contract supersedes prior negotiations, representations, or agreements, whether written or
oral.
9. Contract Documents —Those items that make up the contract and which must include the
Agreement, and it's attachments such as standard construction specifications, standard City
Conditions, other general conditions of the Developer, including:
a. An Agreement
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
0073 10-2
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 2 of 35
b. Attachments to the Agreement
i. Bid Form
ii. Vendor Compliance with State Law Non -Resident Bidder
iii. Prequalification Statement
C. Current Prevailing Wage Rates Table (if required by City)
d. Insurance Accord Form
e. Payment Bond
f. Performance Bond
g. Maintenance Bond
h. Power of Attorney for Bonds
i. Workers Compensation Affidavit
j. MWBE Commitment Form( If required by City)
k. General Conditions
1. Supplementary Conditions
in. The Standard City Conditions
n. Specifications specifically made part of the Contract Documents by attachment, if
not attached, as incorporated by reference and described in the Table of Contents of
the Project's Contract Documents
o. Drawings
P. Documentation submitted by contractor prior to Notice of Award.
q. The following which may be delivered or issued after the effective date if the
Agreement and, if issued become an incorporated part of the Contract Documents
i. Notice to Proceed
ii. Field Orders
iii. Change Orders
iv. Letters of Final Acceptance
r. Approved Submittals, other Contractor submittals, and the reports and drawings of
subsurface and physical conditions are not Contract Documents.
10. Contractor —The individual or entity with whom Developer has entered into the Agreement.
11. Day or day —A day, unless otherwise defined, shall mean a Calendar Day.
12. Developer — An individual or entity that desires to make certain improvements within the
City of Fort Worth
13. Drawings —That part of the Contract Documents prepared or approved by Engineer which
graphically shows the scope, extent, and character of the Work to be performed by
Contractor. Submittals are not Drawings as so defined.
14. Engineer —The licensed professional engineer or engineering firm registered in the State of
Texas performing professional services for the Developer.
15. Final Acceptance — The written notice given by the City to the Developer and/or Contractor
that the Work specified in the Contract Documents has been completed to the satisfaction of
the City.
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
0073 10- 3
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 3 of 35
16. Final Inspection — Inspection carried out by the City to verify that the Contractor has
completed the Work, and each and every part or appurtenance thereof, fully, entirely, and in
conformance with the Contract Documents.
17. General Requirements —A part of the Contract Documents between the Developer and a
Contractor.
18. Laws and Regulations Any and all applicable laws, rules, regulations, ordinances, codes,
and orders of any and all governmental bodies, agencies, authorities, and courts having
jurisdiction.
19. Liens —Charges, security interests, or encumbrances upon Project funds, real property, or
personal property.
20. Milestone —A principal event specified in the Contract Documents relating to an
intermediate Contract Time prior to Final Acceptance of the Work.
21. Non -Participating Change Order —A document, which is prepared for and reviewed by the
City, which is signed by Contractor, and Developer, and authorizes an addition, deletion, or
revision in the Work or an adjustment in the Contract Price or the Contract Time, issued on
or after the Effective Date of the Agreement.
22. Participating Change Order —A document, which is prepared for and approved by the City,
which is signed by Contractor, Developer, and City and authorizes an addition, deletion, or
revision in the Work or an adjustment in the Contract Price or the Contract Time, issued on
or after the Effective Date of the Agreement.
23. Plans — See definition of Drawings.
24. Project Schedule —A schedule, prepared and maintained by Contractor, in accordance with
the General Requirements, describing the sequence and duration of the activities comprising
the Contractor's plan to accomplish the Work within the Contract Time.
25. Project —The Work to be performed under the Contract Documents.
26. Project Representative —The authorized representative of the City who will be assigned to
the Site.
27. Public Meeting — An announced meeting conducted by the Developer to facilitate public
participation and to assist the public in gaining an informed view of the Project.
28. Regular Working Hours — Hours beginning at 7: 00 a.m. and ending at 6:00 p.m., Monday
thru Friday (excluding legal holidays).
29. Samples Physical examples of materials, equipment, or workmanship that are
representative of some portion of the Work and which establish the standards by which such
portion of the Work will be judged.
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
0073 10- 4
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 4 of 35
30. Schedule of Submittals —A schedule, prepared and maintained by Contractor, of required
submittals and the time requirements to support scheduled performance of related
construction activities.
31. Site —Lands or areas indicated in the Contract Documents as being furnished by City or
Developer upon which the Work is to be performed, including rights -of -way, permits, and
easements for access thereto, and such other lands furnished by City or Developer which are
designated for the use of Contractor.
32. Specifications —That part of the Contract Documents consisting of written requirements for
materials, equipment, systems, standards and workmanship as applied to the Work, and
certain administrative requirements and procedural matters applicable thereto.
Specifications may be specifically made a part of the Contract Documents by attachment or,
if not attached, may be incorporated by reference as indicated in the Table of Contents
(Division 00 00 00) of each Project.
33. Standard City Conditions — That part of the Contract Documents setting forth requirements
of the City.
34. Subcontractor —An individual or entity having a direct contract with Contractor or with any
other Subcontractor for the performance of apart of the Work at the Site.
35. Submittals All drawings, diagrams, illustrations, schedules, and other data or information
which are specifically prepared or assembled by or for Contractor and submitted by
Contractor to illustrate some portion of the Work.
36. Superintendent — The representative of the Contractor who is available at all times and able
to receive instructions from the City and/or Developer and to act for the Contractor.
37. Supplementary Conditions —That part of the Contract Documents which amends or
supplements the General Conditions.
38. Supplier —A manufacturer, fabricator, supplier, distributor, materialman, or vendor having
a direct contract with Contractor or with any Subcontractor to furnish materials or
equipment to be incorporated in the Work by Contractor or Subcontractor.
39. Underground Facilities All underground pipelines, conduits, ducts, cables, wires,
manholes, vaults, tanks, tunnels, or other such facilities or attachments, and any
encasements containing such facilities, including but not limited to, those that convey
electricity, gases, steam, liquid petroleum products, telephone or other communications,
cable television, water, wastewater, storm water, other liquids or chemicals, or traffic or
other control systems.
40. Weekend Working Hours — Hours beginning at 9: 00 a. in. and ending at 5: 00 p.m., Saturday,
Sunday or legal holiday, as approved in advance by the City.
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
0073 10- 5
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 5 of 35
41. Work —The entire construction or the various separately identifiable parts thereof required
to be provided under the Contract Documents. Work includes and is the result of performing
or providing all labor, services, and documentation necessary to produce such construction
including any Participating Change Order, Non -Participating Change Order, or Field
Order, and furnishing, installing, and incorporating all materials and equipment into such
construction, all as required by the Contract Documents.
42. Working Day — A working day is defined as a day, not including Saturdays, Sundays, or
legal holidays authorized by the City for contract purposes, in which weather or other
conditions not under the control of the Contractor will permit the performance of the
principal unit of work underway for a continuous period of not less than 7 hours between 7
a.m. and 6 p. m.
1.02 Terminology
A. The words and terms discussed in Paragraph 1.02.13 through D are not defined but, when used in
the Bidding Requirements or Contract Documents, have the indicated meaning.
B. Defective:
1. The word "defective," when modifying the word "Work," refers to Work that is
unsatisfactory, faulty, or deficient in that it:
a. does not conform to the Contract Documents; or
b. does not meet the requirements of any applicable inspection, reference standard, test, or
approval referred to in the Contract Documents; or
c. has been damaged prior to City's written acceptance.
C. Furnish, Install, Perform, Provide:
1. The word "Furnish" or the word "Install" or the word "Perform" or the word "Provide" or
the word "Supply," or any combination or similar directive or usage thereof, shall mean
furnishing and incorporating in the Work including all necessary labor, materials, equipment,
and everything necessary to perform the Work indicated, unless specifically limited in the
context used.
D. Unless stated otherwise in the Contract Documents, words or phrases that have a well-known
technical or construction industry or trade meaning are used in the Contract Documents in
accordance with such recognized meaning.
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
0073 10- 6
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 6 of 35
ARTICLE 2 — PRELIMINARY MATTERS
2.01 Before Starting Construction
Baseline Schedules: Submit to City in accordance with the Contract Documents, and prior to starting
the Work. New schedules will be submitted to City when Participating Change Orders or Non -
Participating Change Orders occur.
2.02 Preconstruction Conference
Before any Work at the Site is started, the Contractor shall attend a Preconstruction Conference as
specified in the Contract Documents.
2.03 Public Meeting
Contractor may not mobilize any equipment, materials or resources to the Site prior to Contractor
attending the Public Meeting as scheduled by the City.
ARTICLE 3 — CONTRACT DOCUMENTS AND AMENDING
3.01 Reference Standards
A. Standards, Specifications, Codes, Laws, and Regulations
1. Reference to standards, specifications, manuals, or codes of any technical society,
organization, or association, or to Laws or Regulations, whether such reference be specific or
by implication, shall mean the standard, specification, manual, code, or Laws or Regulations
in effect at the time of opening of Bids (or on the Effective Date of the Agreement if there
were no Bids), except as may be otherwise specifically stated in the Contract Documents.
2. No provision or instruction shall be effective to assign to City, or any of its officers,
directors, members, partners, employees, agents, consultants, or subcontractors, any duty or
authority to supervise or direct the performance of the Work or any duty or authority to
undertake responsibility inconsistent with the provisions of the Contract Documents.
3.02 Amending and Supplementing Contract Documents
A. The Contract Documents may be amended to provide for additions, deletions, and revisions in
the Work or to modify the terms and conditions thereof by a Participating Change Order or a
Non -Participating Change Order.
B. The requirements of the Contract Documents may be supplemented, and minor variations and
deviations in the Work not involving a change in Contract Price or Contract Time, may be
authorized, by one or more of the following ways:
1. A Field Order;
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
0073 10- 7
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 7 of 35
1. City's or Engineer's review of a Submittal (subject to the provisions of Paragraph 5.16.C); or
2. City's written interpretation or clarification.
ARTICLE 4 — BONDS AND INSURANCE
4.01 Licensed Sureties and Insurers
All bonds and insurance required by the Contract Documents to be purchased and maintained by
Contractor shall be obtained from surety or insurance companies that are duly licensed or authorized
in the State of Texas to issue bonds or insurance policies for the limits and coverage so required.
Such surety and insurance companies shall also meet such additional requirements and qualifications
as may be provided Section 4.04.
4.02 Performance, Payment, and Maintenance Bonds
A. Contractor shall furnish performance and payment bonds in the name of Developer and City, in
accordance with Texas Government Code Chapter 2253 or successor statute, each in an amount
equal to the Contract Price as security for the faithful performance and payment of all of
Contractor's obligations under the Contract Documents.
B. Contractor shall furnish maintenance bonds in the name of Developer and City in an amount
equal to the Contract Price as security to protect the City against any defects in any portion of the
Work described in the Contract Documents. Maintenance bonds shall remain in effect for two
(2) years after the date of Final Acceptance by the City.
C. All bonds shall be in the form prescribed by the Contract Documents except as provided
otherwise by Laws or Regulations, and shall be executed by such sureties as are named in the list
of "Companies Holding Certificates of Authority as Acceptable Sureties on Federal Bonds and
as Acceptable Reinsuring Companies" as published in Circular 570 (amended) by the Financial
Management Service, Surety Bond Branch, U.S. Department of the Treasury. All bonds signed
by an agent or attorney -in -fact must be accompanied by a sealed and dated power of attorney
which shall show that it is effective on the date the agent or attorney -in -fact signed each bond.
D. If the surety on any bond furnished by Contractor is declared bankrupt or becomes insolvent or
its right to do business is terminated in the State of Texas or it ceases to meet the requirements of
Paragraph 4.02.C, Contractor shall promptly notify City and shall, within 30 days after the event
giving rise to such notification, provide another bond and surety, both of which shall comply
with the requirements of Paragraphs 4.01 and 4.02.C.
4.03 Certificates of Insurance
Contractor shall deliver to Developer and City, with copies to each additional insured and loss payee
identified in these Standard City Conditions certificates of insurance (and other evidence of
insurance requested by City or any other additional insured) which Contractor is required to
purchase and maintain.
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
0073 10- 8
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 8 of 35
1. The certificate of insurance shall document the City, an as "Additional Insured" on all
liability policies.
2. The Contractor's general liability insurance shall include a, "per project" or "per location",
endorsement, which shall be identified in the certificate of insurance provided to the City.
3. The certificate shall be signed by an agent authorized to bind coverage on behalf of the
insured, be complete in its entirety, and show complete insurance carrier names as listed in
the current A.M. Best Property & Casualty Guide
4. The insurers for all policies must be licensed and/or approved to do business in the State of
Texas. Except for workers' compensation, all insurers must have a minimum rating of A-:
VII in the current A. M. Best Key Rating Guide or have reasonably equivalent financial
strength and solvency to the satisfaction of Risk Management. If the rating is below that
required, written approval of City is required.
5. All applicable policies shall include a Waiver of Subrogation (Rights of Recovery) in favor
of the City. In addition, the Contractor agrees to waive all rights of subrogation against the
Engineer (if applicable), and each additional insured identified in these Standard City
Conditions. Failure of the City to demand such certificates or other evidence of full
compliance with the insurance requirements or failure of the City to identify a deficiency
from evidence that is provided shall not be construed as a waiver of Contractor's obligation
to maintain such lines of insurance coverage.
6. If insurance policies are not written for specified coverage limits, an Umbrella or Excess
Liability insurance for any differences is required. Excess Liability shall follow form of the
primary coverage.
7. Unless otherwise stated, all required insurance shall be written on the "occurrence basis". If
coverage is underwritten on a claims -made basis, the retroactive date shall be coincident with
or prior to the date of the effective date of the agreement and the certificate of insurance shall
state that the coverage is claims -made and the retroactive date. The insurance coverage shall
be maintained for the duration of the Contract and for three (3) years following Final
Acceptance provided under the Contract Documents or for the warranty period, whichever is
longer. An annual certificate of insurance submitted to the City shall evidence such
insurance coverage.
8. Policies shall have no exclusions by endorsements, which, neither nullify or amend, the
required lines of coverage, nor decrease the limits of said coverage unless such endorsements
are approved in writing by the City. In the event a Contract has been bid or executed and the
exclusions are determined to be unacceptable or the City desires additional insurance
coverage, and the City desires the contractor/engineer to obtain such coverage, the contract
price shall be adjusted by the cost of the premium for such additional coverage plus 10%.
9. Any self -insured retention (SIR), in excess of $25,000.00, affecting required insurance
coverage shall be approved by the City in regards to asset value and stockholders' equity. In
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
0073 10-9
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 9 of 35
lieu of traditional insurance, alternative coverage maintained through insurance pools or risk
retention groups, must also be approved by City.
10. Any deductible in excess of $5,000.00, for any policy that does not provide coverage on a
first -dollar basis, must be acceptable to and approved by the City.
11. City, at its sole discretion, reserves the right to review the insurance requirements and to
make reasonable adjustments to insurance coverage's and their limits when deemed
necessary and prudent by the City based upon changes in statutory law, court decision or the
claims history of the industry as well as of the contracting party to the City. The City shall
be required to provide prior notice of 90 days, and the insurance adjustments shall be
incorporated into the Work by Change Order.
12. City shall be entitled, upon written request and without expense, to receive copies of policies
and endorsements thereto and may make any reasonable requests for deletion or revision or
modifications of particular policy terms, conditions, limitations, or exclusions necessary to
conform the policy and endorsements to the requirements of the Contract. Deletions,
revisions, or modifications shall not be required where policy provisions are established by
law or regulations binding upon either parry or the underwriter on any such policies.
13. City shall not be responsible for the direct payment of insurance premium costs for
Contractor's insurance.
4.04 Contractor's Insurance
A. Workers Compensation and Employers' Liability. Contractor shall purchase and maintain such
insurance coverage with limits consistent with statutory benefits outlined in the Texas Workers'
Compensation Act (Texas Labor Code, Ch. 406, as amended), and minimum limits for
Employers' Liability as is appropriate for the Work being performed and as will provide
protection from claims set forth below which may arise out of or result from Contractor's
performance of the Work and Contractor's other obligations under the Contract Documents,
whether it is to be performed by Contractor, any Subcontractor or Supplier, or by anyone directly
or indirectly employed by any of them to perform any of the Work, or by anyone for whose acts
any of them may be liable:
1. claims under workers' compensation, disability benefits, and other similar employee benefit
acts;
2. claims for damages because of bodily injury, occupational sickness or disease, or death of
Contractor's employees.
3. The limits of liability for the insurance shall provide the following coverages for not less
than the following amounts or greater where required by Laws and Regulations
a. Statutory limits
b. Employer's liability
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
00 73 10- 10
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 10 of 35
1) $100,000 each accident/occurrence
2) $100,000 Disease - each employee
3) $500,000 Disease - policy limit
B. Commercial General Liability. Coverage shall include but not be limited to covering liability
(bodily injury or property damage) arising from: premises/operations, independent contractors,
products/completed operations, personal injury, and liability under an insured contract. Insurance
shall be provided on an occurrence basis, and as comprehensive as the current Insurance
Services Office (ISO) policy. This insurance shall apply as primary insurance with respect to
any other insurance or self-insurance programs afforded to the City. The Commercial General
Liability policy, shall have no exclusions by endorsements that would alter of nullify
premises/operations, products/completed operations, contractual, personal injury, or advertising
injury, which are normally contained with the policy, unless the City approves such exclusions
in writing.
1. For construction projects that present a substantial completed operation exposure, the City
may require the contractor to maintain completed operations coverage for a minimum of no
less than three (3) years following the completion of the project
2. Contractor's Liability Insurance under this Section which shall be on a per project basis
covering the Contractor with minimum limits o£
a. $1,000,000 each occurrence
b. $2,000,000 aggregate limit
3. The policy must have an endorsement (Amendment — Aggregate Limits of Insurance)
making the General Aggregate Limits apply separately to each job site.
4. The Commercial General Liability Insurance policies shall provide "X", "C", and "U"
coverage's. Verification of such coverage must be shown in the Remarks Article of the
Certificate of Insurance.
C. Automobile Liability. A commercial business auto policy shall provide coverage on "any auto",
defined as autos owned, hired and non -owned and provide indemnity for claims for damages
because bodily injury or death of any person and or property damage arising out of the work,
maintenance or use of any motor vehicle by the Contractor, any Subcontractor or Supplier, or by
anyone directly or indirectly employed by any of them to perform any of the Work, or by anyone
for whose acts any of them may be liable.
1. Automobile Liability, Contractor's Liability Insurance under this Section, which shall be in
an amount not less than the following amounts:
a. Automobile Liability - a commercial business policy shall provide coverage on "Any
Auto", defined as autos owned, hired and non -owned.
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
00 73 10- 11
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 11 of 35
1) $1, 000, 000 each accident on a combined single limit basis. Split limits are
acceptable if limits are at least:
2) $250,000 Bodily Injury per person
3) $500,000 Bodily Injury per accident /
4) $100,000 Property Damage
D. Railroad Protective Liability. If any of the work or any warranty work is within the limits of
railroad right-of-way, the Contractor shall comply with the following requirements:
1. The Contractor's construction activities will require its employees, agents, subcontractors,
equipment, and material deliveries to cross railroad properties and tracks owned and
operated by:
Write the name of the railroad company. (If none, then write none)
2. The Contractor shall conduct its operations on railroad properties in such a manner as not to
interfere with, hinder, or obstruct the railroad company in any manner whatsoever in the use
or operation of its/their trains or other property. Such operations on railroad properties may
require that Contractor to execute a "Right of Entry Agreement" with the particular railroad
company or companies involved, and to this end the Contractor should satisfy itself as to the
requirements of each railroad company and be prepared to execute the right -of -entry (if any)
required by a railroad company. The requirements specified herein likewise relate to the
Contractor's use of private and/or construction access roads crossing said railroad company's
properties.
3. The Contractual Liability coverage required by Paragraph 5.04D of the General Conditions
shall provide coverage for not less than the following amounts, issued by companies
satisfactory to the City and to the Railroad Company for a term that continues for so long as
the Contractor's operations and work cross, occupy, or touch railroad property:
a. General Aggregate:
b. Each Occurrence: :
Enter limits provided by Railroad Company (If none, write none)
Enter limits provided by Railroad Company (If none, write none)
4. With respect to the above outlined insurance requirements, the following shall govern:
a. Where a single railroad company is involved, the Contractor shall provide one insurance
policy in the name of the railroad company. However, if more than one grade separation
or at -grade crossing is affected by the Project at entirely separate locations on the line or
lines of the same railroad company, separate coverage may be required, each in the
amount stated above.
b. Where more than one railroad company is operating on the same right-of-way or where
several railroad companies are involved and operated on their own separate rights -of -
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
00 73 10- 12
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 12 of 35
way, the Contractor may be required to provide separate insurance policies in the name
of each railroad company.
c. If, in addition to a grade separation or an at -grade crossing, other work or activity is
proposed on a railroad company's right-of-way at a location entirely separate from the
grade separation or at -grade crossing, insurance coverage for this work must be included
in the policy covering the grade separation.
d. If no grade separation is involved but other work is proposed on a railroad company's
right-of-way, all such other work may be covered in a single policy for that railroad, even
though the work may be at two or more separate locations.
5. No work or activities on a railroad company's property to be performed by the Contractor
shall be commenced until the Contractor has furnished the City with an original policy or
policies of the insurance for each railroad company named, as required above. All such
insurance must be approved by the City and each affected Railroad Company prior to the
Contractor's beginning work.
6. The insurance specified above must be carried until all Work to be performed on the railroad
right-of-way has been completed and the grade crossing, if any, is no longer used by the
Contractor. In addition, insurance must be carried during all maintenance and/or repair work
performed in the railroad right-of-way. Such insurance must name the railroad company as
the insured, together with any tenant or lessee of the railroad company operating over tracks
involved in the Project.
E. Notification of Policy Cancellation: Contractor shall immediately notify City upon cancellation
or other loss of insurance coverage. Contractor shall stop work until replacement insurance has
been procured. There shall be no time credit for days not worked pursuant to this section.
4.05 Acceptance of Bonds and Insurance; Option to Replace
If City has any objection to the coverage afforded by or other provisions of the bonds or insurance
required to be purchased and maintained by the Contractor in accordance with Article 5 on the basis
of non-conformance with the Contract Documents, the Developer and City shall so notify the
Contractor in writing within 10 Business Days after receipt of the certificates (or other evidence
requested). Contractor shall provide to the City such additional information in respect of insurance
provided as the Developer or City may reasonably request. If Contractor does not purchase or
maintain all of the bonds and insurance required by the Contract Documents, the Developer or City
shall notify the Contractor in writing of such failure prior to the start of the Work, or of such failure
to maintain prior to any change in the required coverage.
ARTICLE 5 — CONTRACTOR'S RESPONSIBILITIES
5.01 Supervision and Superintendent
A. Contractor shall supervise, inspect, and direct the Work competently and efficiently, devoting
such attention thereto and applying such skills and expertise as may be necessary to perform the
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
00 73 10- 13
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 13 of 35
Work in accordance with the Contract Documents. Contractor shall be solely responsible for the
means, methods, techniques, sequences, and procedures of construction.
B. At all times during the progress of the Work, Contractor shall assign a competent, English-
speaking, Superintendent who shall not be replaced without written notice to City. The
Superintendent will be Contractor's representative at the Site and shall have authority to act on
behalf of Contractor. All communication given to or received from the Superintendent shall be
binding on Contractor.
C. Contractor shall notify the City 24 hours prior to moving areas during the sequence of
construction.
5.02 Labor; Working Hours
A. Contractor shall provide competent, suitably qualified personnel to perform construction as
required by the Contract Documents. Contractor shall at all times maintain good discipline and
order at the Site.
B. Except as otherwise required for the safety or protection of persons or the Work or property at
the Site or adjacent thereto, and except as otherwise stated in the Contract Documents, all Work
at the Site shall be performed during Regular Working Hours. Contractor will not permit the
performance of Work beyond Regular Working Hours or for Weekend Working Hours without
City's written consent (which will not be unreasonably withheld). Written request (by letter or
electronic communication) to perform Work:
1. for beyond Regular Working Hours request must be made by noon at least two (2) Business
Days prior
2. for Weekend Working Hours request must be made by noon of the preceding Thursday
3. for legal holidays request must be made by noon two Business Days prior to the legal
holiday.
5.03 Services, Materials, and Equipment
A. Unless otherwise specified in the Contract Documents, Contractor shall provide and assume full
responsibility for all services, materials, equipment, labor, transportation, construction
equipment and machinery, tools, appliances, fuel, power, light, heat, telephone, water, sanitary
facilities, temporary facilities, and all other facilities and incidentals necessary for the
performance, Contractor required testing, start-up, and completion of the Work.
B. All materials and equipment incorporated into the Work shall be as specified or, if not specified,
shall be of good quality and new, except as otherwise provided in the Contract Documents. All
special warranties and guarantees required by the Specifications shall expressly run to the benefit
of City. If required by City, Contractor shall furnish satisfactory evidence (including reports of
required tests) as to the source, kind, and quality of materials and equipment.
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
00 73 10- 14
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 14 of 35
C. All materials and equipment to be incorporated into the Work shall be stored, applied, installed,
connected, erected, protected, used, cleaned, and conditioned in accordance with instructions of
the applicable Supplier, except as otherwise may be provided in the Contract Documents.
5.04 Project Schedule
A. Contractor shall adhere to the Project Schedule established in accordance with Paragraph 2.01
and the General Requirements as it may be adjusted from time to time as provided below.
1. Contractor shall submit to City for acceptance (to the extent indicated in Paragraph 2.01 and
the General Requirements) proposed adjustments in the Project Schedule.
2. Proposed adjustments in the Project Schedule that will change the Contract Time shall be
submitted in accordance with the requirements of Article 9. Adjustments in Contract Time
for projects with City participation shall be made by participating change orders.
5.05 Substitutes and "Or -Equals "
A. Whenever an item of material or equipment is specified or described in the Contract Documents
by using the name of a proprietary item or the name of a particular Supplier, the specification or
description is intended to establish the type, function, appearance, and quality required. Unless
the specification or description contains or is followed by words reading that no like, equivalent,
or "or -equal" item or no substitution is permitted, other items of material or equipment of other
Suppliers may be submitted to City for review under the circumstances described below.
1. "Or -Equal" Items: If in City's sole discretion an item of material or equipment proposed by
Contractor is functionally equal to that named and sufficiently similar so that no change in
related Work will be required, it may be considered by City as an "or -equal" item, in which
case review and approval of the proposed item may, in City's sole discretion, be
accomplished without compliance with some or all of the requirements for approval of
proposed substitute items. For the purposes of this Paragraph 5.05.A.1, a proposed item of
material or equipment will be considered functionally equal to an item so named if:
a. City determines that:
1) it is at least equal in materials of construction, quality, durability, appearance,
strength, and design characteristics;
2) it will reliably perform at least equally well the function and achieve the results
imposed by the design concept of the completed Project as a functioning whole; and
3) it has a proven record of performance and availability of responsive service; and
b. Contractor certifies that, if approved and incorporated into the Work:
1) there will be no increase in cost to the City or increase in Contract Time; and
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
00 73 10- 15
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 15 of 35
2) it will conform substantially to the detailed requirements of the item named in the
Contract Documents.
2. Substitute Items:
a. If in City's sole discretion an item of material or equipment proposed by Contractor does
not qualify as an "or -equal" item under Paragraph 5.05.A.1, it may be submitted as a
proposed substitute item.
b. Contractor shall submit sufficient information as provided below to allow City to
determine if the item of material or equipment proposed is essentially equivalent to that
named and an acceptable substitute therefor. Requests for review of proposed substitute
items of material or equipment will not be accepted by City from anyone other than
Contractor.
c. Contractor shall make written application to City for review of a proposed substitute item
of material or equipment that Contractor seeks to furnish or use. The application shall
comply with Section 0125 00 and:
1) shall certify that the proposed substitute item will:
i. perform adequately the functions and achieve the results called for by the general
design;
ii. be similar in substance to that specified;
iii. be suited to the same use as that specified; and
2) will state:
i. the extent, if any, to which the use of the proposed substitute item will prejudice
Contractor's achievement of final completion on time;
ii. whether use of the proposed substitute item in the Work will require a change in
any of the Contract Documents (or in the provisions of any other direct contract
with City for other work on the Project) to adapt the design to the proposed
substitute item;
iii. whether incorporation or use of the proposed substitute item in connection with
the Work is subject to payment of any license fee or royalty; and
3) will identify:
i. all variations of the proposed substitute item from that specified;
ii. available engineering, sales, maintenance, repair, and replacement services; and
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
00 73 10- 16
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 16 of 35
4) shall contain an itemized estimate of all costs or credits that will result directly or
indirectly from use of such substitute item, including costs of redesign and Damage
Claims of other contractors affected by any resulting change.
B. Substitute Construction Methods or Procedures: If a specific means, method, technique,
sequence, or procedure of construction is expressly required by the Contract Documents,
Contractor may furnish or utilize a substitute means, method, technique, sequence, or procedure
of construction approved by City. Contractor shall submit sufficient information to allow City, in
City's sole discretion, to determine that the substitute proposed is equivalent to that expressly
called for by the Contract Documents. Contractor shall make written application to City for
review in the same manner as those provided in Paragraph 5.05.A.2.
C. City's Evaluation: City will be allowed a reasonable time within which to evaluate each
proposal or submittal made pursuant to Paragraphs 5.05.A and 5.05.13. City may require
Contractor to furnish additional data about the proposed substitute. City will be the sole judge of
acceptability. No "or -equal" or substitute will be ordered, installed or utilized until City's review
is complete, which will be evidenced by a Change Order in the case of a substitute and an
accepted Submittal for an "or -equal." City will advise Contractor in writing of its determination.
D. Special Guarantee: City may require Contractor to furnish at Contractor's expense a special
performance guarantee, warranty, or other surety with respect to any substitute. Contractor shall
indemnify and hold harmless City and anyone directly or indirectly employed by them from and
against any and all claims, damages, losses and expenses (including attorneys fees) arising out
of the use of substituted materials or equipment.
E. City's Cost Reimbursement: City will record City's costs in evaluating a substitute proposed or
submitted by Contractor pursuant to Paragraphs 5.05.A.2 and 5.05.B. Whether or not City
approves a substitute so proposed or submitted by Contractor, Contractor may be required to
reimburse City for evaluating each such proposed substitute. Contractor may also be required to
reimburse City for the charges for making changes in the Contract Documents.
F. Contractor's Expense: Contractor shall provide all data in support of any proposed substitute or
"or -equal" at Contractor's expense.
G. Substitute Reimbursement: Costs (savings or charges) attributable to acceptance of a substitute
shall be incorporated to the Contract by Participating Change Order.
5.06 Pre -Qualification of Bidders (Prime Contractors and Subcontractors)
A. The Contractor and any subcontractors are required to be prequalified for the work types
requiring pre -qualification
5.07 Concerning Subcontractors, Suppliers, and Others
A. Minority and Women Owned Business Enterprise Compliance:
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
00 73 10- 17
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 17 of 35
❑ Required for this Contract.
(Check this box if there is any City Participation)
❑ Not Required for this Contract.
It is City policy to ensure the full and equitable participation by Minority and Women Business
Enterprises (MWBE) in the procurement of goods and services on a contractual basis. If the
Contract Documents provide for a MWBE goal, Contractor is required to comply with the intent
of the City's MWBE Ordinance (as amended) by the following:
1. Contractor shall, upon request by City, provide complete and accurate information regarding
actual work performed by a MWBE on the Contract and payment therefor.
2. Contractor will not make additions, deletions, or substitutions of accepted MWBE without
written consent of the City. Any unjustified change or deletion shall be a material breach of
Contract and may result in debarment in accordance with the procedures outlined in the
Ordinance.
3. Contractor shall, upon request by City, allow an audit and/or examination of any books,
records, or files in the possession of the Contractor that will substantiate the actual work
performed by an MWBE. Material misrepresentation of any nature will be grounds for
termination of the Contract. Any such misrepresentation may be grounds for disqualification
of Contractor to bid on future contracts with the City for a period of not less than three years.
B. Contractor shall be fully responsible to City for all acts and omissions of the Subcontractors,
Suppliers, and other individuals or entities performing or furnishing any of the Work just as
Contractor is responsible for Contractor's own acts and omissions. Nothing in the Contract
Documents:
1. shall create for the benefit of any such Subcontractor, Supplier, or other individual or entity
any contractual relationship between City and any such Subcontractor, Supplier or other
individual or entity; nor
2. shall create any obligation on the part of City to pay or to see to the payment of any moneys
due any such Subcontractor, Supplier, or other individual or entity except as may otherwise
be required by Laws and Regulations.
C. Contractor shall be solely responsible for scheduling and coordinating the Work of
Subcontractors, Suppliers, and other individuals or entities performing or furnishing any of the
Work under a direct or indirect contract with Contractor.
D. All Subcontractors, Suppliers, and such other individuals or entities performing or furnishing
any of the Work shall communicate with City through Contractor.
E. All Work performed for Contractor by a Subcontractor or Supplier will be pursuant to an
appropriate agreement between Contractor and the Subcontractor or Supplier which specifically
binds the Subcontractor or Supplier to the applicable terms and conditions of these Contract
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
00 73 10- 18
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 18 of 35
Documents, Contractor shall provide City contract numbers and reference numbers to the
Subcontractors and/or Suppliers.
5.08 Wage Rates
❑ Required for this Contract.
❑ Not Required for this Contract.
A. Duty to pay Prevailing Wage Rates. The Contractor shall comply with all requirements of
Chapter 2258, Texas Government Code (as amended), including the payment of not less than the
rates determined by the City Council of the City of Fort Worth to be the prevailing wage rates in
accordance with Chapter 2258. Such prevailing wage rates are included in these Contract
Documents.
B. Penalty for Violation. A Contractor or any Subcontractor who does not pay the prevailing wage
shall, upon demand made by the City, pay to the City $60 for each worker employed for each
calendar day or part of the day that the worker is paid less than the prevailing wage rates
stipulated in these contract documents. This penalty shall be retained by the City to offset its
administrative costs, pursuant to Texas Government Code 2258.023.
C. Complaints of Violations and City Determination of Good Cause. On receipt of information,
including a complaint by a worker, concerning an alleged violation of 2258.023, Texas
Government Code, by a Contractor or Subcontractor, the City shall make an initial
determination, before the 31 st day after the date the City receives the information, as to whether
good cause exists to believe that the violation occurred. The City shall notify in writing the
Contractor or Subcontractor and any affected worker of its initial determination. Upon the
City's determination that there is good cause to believe the Contractor or Subcontractor has
violated Chapter 2258, the City shall retain the full amounts claimed by the claimant or
claimants as the difference between wages paid and wages due under the prevailing wage rates,
such amounts being subtracted from successive progress payments pending a final determination
of the violation.
D. Arbitration Required if Violation Not Resolved. An issue relating to an alleged violation of
Section 2258.023, Texas Government Code, including a penalty owed to the City or an affected
worker, shall be submitted to binding arbitration in accordance with the Texas General
Arbitration Act (Article 224 et seq., Revised Statutes) if the Contractor or Subcontractor and any
affected worker does not resolve the issue by agreement before the 15th day after the date the
City makes its initial determination pursuant to Paragraph C above. If the persons required to
arbitrate under this section do not agree on an arbitrator before the 1 Ith day after the date that
arbitration is required, a district court shall appoint an arbitrator on the petition of any of the
persons. The City is not a party in the arbitration. The decision and award of the arbitrator is
final and binding on all parties and may be enforced in any court of competent jurisdiction.
E. Records to be Maintained. The Contractor and each Subcontractor shall, for a period of three (3)
years following the date of acceptance of the work, maintain records that show (i) the name and
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
00 73 10- 19
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 19 of 35
occupation of each worker employed by the Contractor in the construction of the Work provided
for in this Contract; and (ii) the actual per diem wages paid to each worker. The records shall be
open at all reasonable hours for inspection by the City. The provisions of Paragraph 6.23, Right
to Audit, shall pertain to this inspection.
F. Progress Payments. With each progress payment or payroll period, whichever is less, the
Contractor shall submit an affidavit stating that the Contractor has complied with the
requirements of Chapter 2258, Texas Government Code.
G. Posting of Wage Rates. The Contractor shall post prevailing wage rates in a conspicuous place at
all times.
H. Subcontractor Compliance. The Contractor shall include in its subcontracts and/or shall
otherwise require all of its Subcontractors to comply with Paragraphs A through G above.
5.09 Patent Fees and Royalties
A. To the fullest extent permitted by Laws and Regulations, Contractor shall indemnify and hold
harmless City, from and against all claims, costs, losses, and damages (including but not limited
to all fees and charges of engineers, architects, attorneys, and other professionals and all court
or arbitration or other dispute resolution costs) arising out of or relating to any infringement of
patent rights or copyrights incident to the use in the performance of the Work or resulting from
the incorporation in the Work of any invention, design, process, product, or device not specified
in the Contract Documents.
5.10 Laws and Regulations
A. Contractor shall give all notices required by and shall comply with all Laws and Regulations
applicable to the performance of the Work. Except where otherwise expressly required by
applicable Laws and Regulations, the City shall not be responsible for monitoring Contractor's
compliance with any Laws or Regulations.
B. If Contractor performs any Work knowing or having reason to know that it is contrary to Laws
or Regulations, Contractor shall bear all claims, costs, losses, and damages (including but not
limited to all fees and charges of engineers, architects, attorneys, and other professionals and all
court or arbitration or other dispute resolution costs) arising out of or relating to such Work.
However, it shall not be Contractor's responsibility to make certain that the Specifications and
Drawings are in accordance with Laws and Regulations, but this shall not relieve Contractor of
Contractor's obligations under Paragraph 3.01.
5.11 Use of Site and Other Areas
A. Limitation on Use of Site and Other Areas:
1. Contractor shall confine construction equipment, the storage of materials and equipment, and
the operations of workers to the Site and other areas permitted by Laws and Regulations, and
shall not unreasonably encumber the Site and other areas with construction equipment or
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
00 73 10- 20
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 20 of 35
other materials or equipment. Contractor shall assume full responsibility for any damage to
any such land or area, or to the owner or occupant thereof, or of any adjacent land or areas
resulting from the performance of the Work.
2. At any time when, in the judgment of the City, the Contractor has obstructed or closed or is
carrying on operations in a portion of a street, right-of-way, or easement greater than is
necessary for proper execution of the Work, the City may require the Contractor to finish the
section on which operations are in progress before work is commenced on any additional
area of the Site.
3. Should any Damage Claim be made by any such owner or occupant because of the
performance of the Work, Contractor shall promptly attempt to resolve the Damage Claim.
4. Pursuant to Paragraph 5.18, Contractor shall indemnify and hold harmless City, from and
against all claims, costs, losses, and damages arising out of or relating to any claim or
action, legal or equitable, brought by any such owner or occupant against City.
B. Removal of Debris During Performance of the Work: During the progress of the Work
Contractor shall keep the Site and other areas free from accumulations of waste materials,
rubbish, and other debris. Removal and disposal of such waste materials, rubbish, and other
debris shall conform to applicable Laws and Regulations.
C. Site Maintenance Cleaning: 24 hours after written notice is given to the Contractor that the
clean-up on the job site is proceeding in a manner unsatisfactory to the City or Developer, if the
Contractor fails to correct the unsatisfactory procedure, the City may take such direct action as
the City deems appropriate to correct the clean-up deficiencies cited to the Contractor in the
written notice (by letter or electronic communication), and shall be entitled to recover its cost in
doing so. The City may withhold Final Acceptance until clean-up is complete and cost are
recovered.
D. Final Site Cleaning: Prior to Final Acceptance of the Work Contractor shall clean the Site and
the Work and make it ready for utilization by City or adjacent property owner. At the completion
of the Work Contractor shall remove from the Site all tools, appliances, construction equipment
and machinery, and surplus materials and shall restore to original condition or better all property
disturbed by the Work.
E. Loading Structures: Contractor shall not load nor permit any part of any structure to be loaded
in any manner that will endanger the structure, nor shall Contractor subject any part of the Work
or adjacent property to stresses or pressures that will endanger it.
5.12 Record Documents
A. Contractor shall maintain in a safe place at the Site or in a place designated by the Contractor
and approved by the City, one (1) record copy of all Drawings, Specifications, Addenda, Change
Orders, Field Orders, and written interpretations and clarifications in good order and annotated
to show changes made during construction. These record documents together with all approved
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
00 73 10- 21
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 21 of 35
Samples and a counterpart of all accepted Submittals will be available to City for reference.
Upon completion of the Work, these record documents, any operation and maintenance manuals,
and Submittals will be delivered to City prior to Final Inspection. Contractor shall include
accurate locations for buried and imbedded items.
5.13 Safety and Protection
A. Contractor shall be solely responsible for initiating, maintaining and supervising all safety
precautions and programs in connection with the Work. Such responsibility does not relieve
Subcontractors of their responsibility for the safety of persons or property in the performance of
their work, nor for compliance with applicable safety Laws and Regulations. Contractor shall
take all necessary precautions for the safety of, and shall provide the necessary protection to
prevent damage, injury or loss to:
1. all persons on the Site or who may be affected by the Work;
2. all the Work and materials and equipment to be incorporated therein, whether in storage on
or off the Site; and
3. other property at the Site or adjacent thereto, including trees, shrubs, lawns, walks,
pavements, roadways, structures, utilities, and Underground Facilities not designated for
removal, relocation, or replacement in the course of construction.
B. Contractor shall comply with all applicable Laws and Regulations relating to the safety of
persons or property, or to the protection of persons or property from damage, injury, or loss; and
shall erect and maintain all necessary safeguards for such safety and protection. Contractor shall
notify owners of adjacent property and of Underground Facilities and other utility owners when
prosecution of the Work may affect them, and shall cooperate with them in the protection,
removal, relocation, and replacement of their property.
C. Contractor shall comply with the applicable requirements of City's safety programs, if any.
D. Contractor shall inform City of the specific requirements of Contractor's safety program, if any,
with which City's employees and representatives must comply while at the Site.
E. All damage, injury, or loss to any property referred to in Paragraph 5.13.A.2 or 5.13.A.3 caused,
directly or indirectly, in whole or in part, by Contractor, any Subcontractor, Supplier, or any
other individual or entity directly or indirectly employed by any of them to perform any of the
Work, or anyone for whose acts any of them may be liable, shall be remedied by Contractor.
F. Contractor's duties and responsibilities for safety and for protection of the Work shall continue
until such time as all the Work is completed and City has accepted the Work.
5.14 Safety Representative
Contractor shall inform City in writing of Contractor's designated safety representative at the Site.
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
00 73 10- 22
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 22 of 35
5.15 Hazard Communication Programs
Contractor shall be responsible for coordinating any exchange of material safety data sheets or other
hazard communication information required to be made available to or exchanged between or
among employers in accordance with Laws or Regulations.
5.16 Submittals
A. Contractor shall submit required Submittals to City for review and acceptance. Each submittal
will be identified as required by City.
1. Submit number of copies specified in the General Requirements.
2. Data shown on the Submittals will be complete with respect to quantities, dimensions,
specified performance and design criteria, materials, and similar data to show City the
services, materials, and equipment Contractor proposes to provide and to enable City to
review the information for the limited purposes required by Paragraph 5.16.C.
3. Submittals submitted as herein provided by Contractor and reviewed by City for
conformance with the design concept shall be executed in conformity with the Contract
Documents unless otherwise required by City.
4. When Submittals are submitted for the purpose of showing the installation in greater detail,
their review shall not excuse Contractor from requirements shown on the Drawings and
Specifications.
5. For -Information -Only submittals upon which the City is not expected to conduct review or
take responsive action may be so identified in the Contract Documents.
6. Submit required number of Samples specified in the Specifications.
7. Clearly identify each Sample as to material, Supplier, pertinent data such as catalog numbers,
the use for which intended and other data as City may require to enable City to review the
submittal for the limited purposes required by Paragraph 5.16.C.
B. Where a Submittal is required by the Contract Documents or the Schedule of Submittals, any
related Work performed prior to City's review and acceptance of the pertinent submittal will be
at the sole expense and responsibility of Contractor.
C. City's Review:
1. City will provide timely review of required Submittals in accordance with the Schedule of
Submittals acceptable to City. City's review and acceptance will be only to determine if the
items covered by the submittals will, after installation or incorporation in the Work, conform
to the information given in the Contract Documents and be compatible with the design
concept of the completed Project as a functioning whole as indicated by the Contract
Documents.
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
00 73 10- 23
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 23 of 35
2. City's review and acceptance will not extend to means, methods, techniques, sequences, or
procedures of construction (except where a particular means, method, technique, sequence,
or procedure of construction is specifically and expressly called for by the Contract
Documents) or to safety precautions or programs incident thereto. The review and
acceptance of a separate item as such will not indicate approval of the assembly in which the
item functions.
3. City's review and acceptance shall not relieve Contractor from responsibility for any
variation from the requirements of the Contract Documents unless Contractor has complied
with the requirements of Section 01 33 00 and City has given written acceptance of each
such variation by specific written notation thereof incorporated in or accompanying the
Submittal. City's review and acceptance shall not relieve Contractor from responsibility for
complying with the requirements of the Contract Documents.
5.17 Contractor's General Warranty and Guarantee
A. Contractor warrants and guarantees to City that all Work will be in accordance with the Contract
Documents and will not be defective. City and its officers, directors, members, partners,
employees, agents, consultants, and subcontractors shall be entitled to rely on representation of
Contractor's warranty and guarantee.
B. Contractor's warranty and guarantee hereunder excludes defects or damage caused by:
1. abuse, modification, or improper maintenance or operation by persons other than Contractor,
Subcontractors, Suppliers, or any other individual or entity for whom Contractor is
responsible; or
2. normal wear and tear under normal usage.
C. Contractor's obligation to perform and complete the Work in accordance with the Contract
Documents shall be absolute. None of the following will constitute an acceptance of Work that is
not in accordance with the Contract Documents or a release of Contractor's obligation to
perform the Work in accordance with the Contract Documents:
1. observations by City;
2. recommendation or payment by City or Developer of any progress or final payment;
3. the issuance of a certificate of Final Acceptance by City or any payment related thereto by
City;
4. use or occupancy of the Work or any part thereof by City;
5. any review and acceptance of a Submittal by City;
6. any inspection, test, or approval by others; or
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
00 73 10- 24
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 24 of 35
7. any correction of defective Work by City.
D. The Contractor shall remedy any defects or damages in the Work and pay for any damage to
other work or property resulting therefrom which shall appear within a period of two (2) years
from the date of Final Acceptance of the Work unless a longer period is specified and shall
furnish a good and sufficient maintenance bond, complying with the requirements of Article
4.02.13. The City will give notice of observed defects with reasonable promptness.
5.18 Indemnification
A. Contractor covenants and agrees to indemnify, hold harmless and defend, at its own expense, the
City, its officers, servants and employees, from and against any and all claims arising out of, or
alleged to arise out of, the work and services to be performed by the Contractor, its officers,
agents, employees, subcontractors, licenses or invitees under this Contract. THIS
INDEMNIFICATION PROVISION IS SPECIFICALLY INTENDED TO OPERATE
AND BE EFFECTIVE EVEN IF IT IS ALLEGED OR PROVEN THAT ALL OR SOME
OF THE DAMAGES BEING SOUGHT WERE CAUSED, IN WHOLE OR IN PART, BY
ANY ACT, OMISSION OR NEGLIGENCE OF THE CITY. This indemnity provision is
intended to include, without limitation, indemnity for costs, expenses and legal fees incurred by
the City in defending against such claims and causes of actions.
B. Contractor covenants and agrees to indemnify and hold harmless, at its own expense, the City, its
officers, servants and employees, from and against any and all loss, damage or destruction of
property of the City, arising out of, or alleged to arise out of, the work and services to be
performed by the Contractor, its officers, agents, employees, subcontractors, licensees or invitees
under this Contract. THIS INDEMNIFICATION PROVISION IS SPECIFICALLY
INTENDED TO OPERATE AND BE EFFECTIVE EVEN IF IT IS ALLEGED OR
PROVEN THAT ALL OR SOME OF THE DAMAGES BEING SOUGHT WERE
CAUSED, IN WHOLE OR IN PART, BY ANY ACT, OMISSION OR NEGLIGENCE OF
THE CITY.
5.19 Delegation of Professional Design Services
A. Contractor will not be required to provide professional design services unless such services are
specifically required by the Contract Documents for a portion of the Work or unless such
services are required to carry out Contractor's responsibilities for construction means, methods,
techniques, sequences and procedures.
B. If professional design services or certifications by a design professional related to systems,
materials or equipment are specifically required of Contractor by the Contract Documents, City
will specify all performance and design criteria that such services must satisfy. Contractor shall
cause such services or certifications to be provided by a properly licensed professional, whose
signature and seal shall appear on all drawings, calculations, specifications, certifications, and
Submittals prepared by such professional. Submittals related to the Work designed or certified
by such professional, if prepared by others, shall bear such professional's written approval when
submitted to City.
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
00 73 10- 25
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 25 of 35
C. City shall be entitled to rely upon the adequacy, accuracy and completeness of the services,
certifications or approvals performed by such design professionals, provided City has specified
to Contractor performance and design criteria that such services must satisfy.
D. Pursuant to this Paragraph 5.19, City's review and acceptance of design calculations and design
drawings will be only for the limited purpose of checking for conformance with performance
and design criteria given and the design concept expressed in the Contract Documents. City's
review and acceptance of Submittals (except design calculations and design drawings) will be
only for the purpose stated in Paragraph 5.16.C.
5.20 Right to Audit:
A. The City reserves the right to audit all projects utilizing City funds
B. The Contractor agrees that the City shall, until the expiration of three (3) years after final
payment under this Contract, have access to and the right to examine and photocopy any directly
pertinent books, documents, papers, and records of the Contractor involving transactions relating
to this Contract. Contractor agrees that the City shall have access during Regular Working Hours
to all necessary Contractor facilities and shall be provided adequate and appropriate work space
in order to conduct audits in compliance with the provisions of this Paragraph. The City shall
give Contractor reasonable advance notice of intended audits.
C. Contractor further agrees to include in all its subcontracts hereunder a provision to the effect that
the subcontractor agrees that the City shall, until the expiration of three (3) years after final
payment under this Contract, have access to and the right to examine and photocopy any directly
pertinent books, documents, papers, and records of such Subcontractor, involving transactions to
the subcontract, and further, that City shall have access during Regular Working Hours to all
Subcontractor facilities, and shall be provided adequate and appropriate work space in order to
conduct audits in compliance with the provisions of this Paragraph. The City shall give
Subcontractor reasonable advance notice of intended audits.
D. Contractor and Subcontractor agree to photocopy such documents as may be requested by the
City. The City agrees to reimburse Contractor for the cost of the copies as follows at the rate
published in the Texas Administrative Code in effect as of the time copying is performed.
5.21 Nondiscrimination
A. The City is responsible for operating Public Transportation Programs and implementing transit -
related projects, which are funded in part with Federal financial assistance awarded by the U.S.
Department of Transportation and the Federal Transit Administration (FTA), without
discriminating against any person in the United States on the basis of race, color, or national
origin.
B. Title VI, Civil Rights Act of 1964 as amended: Contractor shall comply with the requirements of
the Act and the Regulations as further defined in the Supplementary Conditions for any project
receiving Federal assistance.
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
00 73 10- 26
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 26 of 35
ARTICLE 6 — OTHER WORK AT THE SITE
6.01 Related Work at Site
A. City may perform other work related to the Project at the Site with City's employees, or other
City contractors, or through other direct contracts therefor, or have other work performed by
utility owners. If such other work is not noted in the Contract Documents, then written notice
thereof will be given to Contractor prior to starting any such other work; and
B. Contractor shall afford each other contractor who is a party to such a direct contract, each utility
owner, and City, if City is performing other work with City's employees or other City
contractors, proper and safe access to the Site, provide a reasonable opportunity for the
introduction and storage of materials and equipment and the execution of such other work, and
properly coordinate the Work with theirs. Contractor shall do all cutting, fitting, and patching of
the Work that may be required to properly connect or otherwise make its several parts come
together and properly integrate with such other work. Contractor shall not endanger any work of
others by cutting, excavating, or otherwise altering such work; provided, however, that
Contractor may cut or alter others' work with the written consent of City and the others whose
work will be affected.
C. If the proper execution or results of any part of Contractor's Work depends upon work
performed by others under this Article 7, Contractor shall inspect such other work and promptly
report to City in writing any delays, defects, or deficiencies in such other work that render it
unavailable or unsuitable for the proper execution and results of Contractor's Work. Contractor's
failure to so report will constitute an acceptance of such other work as fit and proper for
integration with Contractor's Work except for latent defects in the work provided by others.
ARTICLE 7 — CITY'S RESPONSIBILITIES
7.01 Inspections, Tests, and Approvals
City's responsibility with respect to certain inspections, tests, and approvals is set forth in Paragraph
11.03.
7.02 Limitations on City's Responsibilities
A. The City shall not supervise, direct, or have control or authority over, nor be responsible for,
Contractor's means, methods, techniques, sequences, or procedures of construction, or the safety
precautions and programs incident thereto, or for any failure of Contractor to comply with Laws
and Regulations applicable to the performance of the Work. City will not be responsible for
Contractor's failure to perform the Work in accordance with the Contract Documents.
B. City will notify the Contractor of applicable safety plans pursuant to Paragraph 5.13.
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
00 73 10- 27
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 27 of 35
7.03 Compliance with Safety Program
While at the Site, City's employees and representatives shall comply with the specific applicable
requirements of Contractor's safety programs of which City has been informed pursuant to
Paragraph 5.13.
ARTICLE 8 — CITY'S OBSERVATION STATUS DURING CONSTRUCTION
8.01 City's Project Representative
City will provide one or more Project Representative(s) during the construction period. The duties
and responsibilities and the limitations of authority of City's representative during construction are
set forth in the Contract Documents.
A. City's Project Representative will make visits to the Site at intervals appropriate to the various
stages of construction as City deems necessary in order to observe the progress that has been
made and the quality of the various aspects of Contractor's executed Work. Based on
information obtained during such visits and observations, City's Project Representative will
determine, in general, if the Work is proceeding in accordance with the Contract Documents.
City's Project Representative will not be required to make exhaustive or continuous inspections
on the Site to check the quality or quantity of the Work. City's Project Representative's efforts
will be directed toward providing City a greater degree of confidence that the completed Work
will conform generally to the Contract Documents.
B. City's Project Representative's visits and observations are subject to all the limitations on
authority and responsibility in the Contract Documents.
8.02 Authorized Variations in Work
City's Project Representative may authorize minor variations in the Work from the requirements of
the Contract Documents which do not involve an adjustment in the Contract Price or the Contract
Time and are compatible with the design concept of the completed Project as a functioning whole as
indicated by the Contract Documents. These may be accomplished by a Field Order and will be
binding on City Developer, and also on Contractor, who shall perform the Work involved promptly.
8.03 Rejecting Defective Work
City will have authority to reject Work which City's Project Representative believes to be defective,
or will not produce a completed Project that conforms to the Contract Documents or that will
prejudice the integrity of the design concept of the completed Project as a functioning whole as
indicated by the Contract Documents. City will have authority to conduct special inspection or
testing of the Work as provided in Article 11, whether or not the Work is fabricated, installed, or
completed.
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
00 73 10- 28
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 28 of 35
8.04 Determinations for Work Performed
Contractor will determine the actual quantities and classifications of Work performed. City's Project
Representative will review with Contractor the preliminary determinations on such matters before
rendering a written recommendation. City's written decision will be final (except as modified to
reflect changed factual conditions or more accurate data).
ARTICLE 9 — CHANGES IN THE WORK
9.01 Authorized Changes in the Work
A. Without invalidating the Contract and without notice to any surety, City may, at any time or
from time to time, order Extra Work. Upon notice of such Extra Work, Contractor shall
promptly proceed with the Work involved which will be performed under the applicable
conditions of the Contract Documents (except as otherwise specifically provided). Extra Work
shall be memorialized by a Participating Change Order which may or may not precede an order
of Extra work.
B. For minor changes of Work not requiring changes to Contract Time or Contract Price on a
project with City participation, a Field Order may be issued by the City.
9.02 Notification to Surety
If the provisions of any bond require notice to be given to a surety of any change affecting the
general scope of the Work or the provisions of the Contract Documents (including, but not limited
to, Contract Price or Contract Time), the giving of any such notice will be Contractor's
responsibility. The amount of each applicable bond will be adjusted by the Contractor to reflect the
effect of any such change.
ARTICLE 10 — CHANGE OF CONTRACT PRICE; CHANGE OF CONTRACT TIME
10.01 Change of Contract Price
A. The Contract Price may only be changed by a Participating Change Order for projects with City
participation.
10.02 Change of Contract Time
A. The Contract Time may only be changed by a Participating Change Order for projects with City
participation.
10.03 Delays
A. If Contractor is delayed, City shall not be liable to Contractor for any claims, costs, losses, or
damages (including but not limited to all fees and charges of engineers, architects, attorneys, and
other professionals and all court or arbitration or other dispute resolution costs) sustained by
Contractor on or in connection with any other project or anticipated project.
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
00 73 10- 29
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 29 of 35
ARTICLE 11— TESTS AND INSPECTIONS; CORRECTION, REMOVAL OR ACCEPTANCE OF
DEFECTIVE WORK
11.01 Notice of Defects
Notice of all defective Work of which City has actual knowledge will be given to Contractor.
Defective Work may be rejected, corrected, or accepted as provided in this Article 13.
11.02 Access to Work
City, independent testing laboratories, and governmental agencies with jurisdictional interests will
have access to the Site and the Work at reasonable times for their observation, inspection, and
testing. Contractor shall provide them proper and safe conditions for such access and advise them of
Contractor's safety procedures and programs so that they may comply therewith as applicable.
11.03 Tests and Inspections
A. Contractor shall give City timely notice of readiness of the Work for all required inspections,
tests, or approvals and shall cooperate with inspection and testing personnel to facilitate required
inspections or tests.
B. If Contract Documents, Laws or Regulations of any public body having jurisdiction require any
of the Work (or part thereof) to be inspected, tested, or approved, Contractor shall assume full
responsibility for arranging and obtaining such independent inspections, tests, retests or
approvals, pay all costs in connection therewith, and furnish City the required certificates of
inspection or approval; excepting, however, those fees specifically identified in the
Supplementary Conditions or any Texas Department of Licensure and Regulation (TDLR)
inspections, which shall be paid as described in the Supplementary Conditions.
C. Contractor shall be responsible for arranging and obtaining and shall pay all costs in connection
with any inspections, tests, re -tests, or approvals required for City's acceptance of materials or
equipment to be incorporated in the Work; or acceptance of materials, mix designs, or equipment
submitted for approval prior to Contractor's purchase thereof for incorporation in the Work.
Such inspections, tests, re -tests, or approvals shall be performed by organizations approved by
City.
D. City may arrange for the services of an independent testing laboratory ("Testing Lab") to
perform any inspections or tests ("Testing") for any part of the Work, as determined solely by
City.
1. City will coordinate such Testing to the extent possible, with Contractor;
2. Should any Testing under this Section 11.03 D result in a "fail", "did not pass" or other
similar negative result, the Contractor shall be responsible for paying for any and all retests.
Contractor's cancellation without cause of City initiated Testing shall be deemed a negative
result and require a retest.
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
00 73 10- 30
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 30 of 35
3. Any amounts owed for any retest under this Section 11.03 D shall be paid directly to the
Testing Lab by Contractor.
Developer/Contractor.
City will forward all invoices for retests to
4. If Contractor fails to pay the Testing Lab, City will not issue a letter of Final Acceptance
until the Testing Lab is Paid
E. If any Work (or the work of others) that is to be inspected, tested, or approved is covered by
Contractor without written concurrence of City, Contractor shall, if requested by City, uncover
such Work for observation.
11.04 Uncovering Work
A. If any Work is covered contrary to the Contract Documents or specific instructions by the City, it
must, if requested by City, be uncovered for City's observation and replaced at Contractor's
expense.
11.05 City May Stop the Work
If the Work is defective, or Contractor fails to supply sufficient skilled workers or suitable materials
or equipment, or fails to perform the Work in such a way that the completed Work will conform to
the Contract Documents, City may order Contractor to stop the Work, or any portion thereof, until
the cause for such order has been eliminated; however, this right of City to stop the Work shall not
give rise to any duty on the part of City to exercise this right for the benefit of Contractor, any
Subcontractor, any Supplier, any other individual or entity, or any surety for, or employee or agent
of any of them.
11.06 Correction or Removal of Defective Work
A. Promptly after receipt of written notice, Contractor shall correct all defective Work pursuant to
an acceptable schedule, whether or not fabricated, installed, or completed, or, if the Work has
been rejected by City, remove it from the Project and replace it with Work that is not defective.
Contractor shall pay all claims, costs, additional testing, losses, and damages (including but not
limited to all fees and charges of engineers, architects, attorneys, and other professionals and all
court or arbitration or other dispute resolution costs) arising out of or relating to such correction
or removal (including but not limited to all costs of repair or replacement of work of others).
Failure to require the removal of any defective Work shall not constitute acceptance of such
Work.
B. When correcting defective Work under the terms of this Paragraph 11.06 or Paragraph 11.07,
Contractor shall take no action that would void or otherwise impair City's special warranty and
guarantee, if any, on said Work.
11.07 Correction Period
A. If within two (2) years after the date of Final Acceptance (or such longer period of time as may
be prescribed by the terms of any applicable special guarantee required by the Contract
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
00 73 10- 31
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 31 of 35
Documents), any Work is found to be defective, or if the repair of any damages to the land or
areas made available for Contractor's use by City or permitted by Laws and Regulations as
contemplated in Paragraph 5.10.A is found to be defective, Contractor shall promptly, without
cost to City and in accordance with City's written instructions:
1. repair such defective land or areas; or
2. correct such defective Work; or
3. if the defective Work has been rejected by City, remove it from the Project and replace it
with Work that is not defective, and
4. satisfactorily correct or repair or remove and replace any damage to other Work, to the work
of others or other land or areas resulting therefrom.
B. If Contractor does not promptly comply with the terms of City's written instructions, or in an
emergency where delay would cause serious risk of loss or damage, City may have the defective
Work corrected or repaired or may have the rejected Work removed and replaced. All claims,
costs, losses, and damages (including but not limited to all fees and charges of engineers,
architects, attorneys, and other professionals and all court or other dispute resolution costs)
arising out of or relating to such correction or repair or such removal and replacement (including
but not limited to all costs of repair or replacement of work of others) will be paid by Contractor.
C. Where defective Work (and damage to other Work resulting therefrom) has been corrected or
removed and replaced under this Paragraph 11.07, the correction period hereunder with respect
to such Work may be required to be extended for an additional period of one year after the end
of the initial correction period. City shall provide 30 days written notice to Contractor and
Developer should such additional warranty coverage be required. Contractor's obligations under
this Paragraph 11.07 are in addition to any other obligation or warranty. The provisions of this
Paragraph 11.07 shall not be construed as a substitute for, or a waiver of, the provisions of any
applicable statute of limitation or repose.
11.08 City May Correct Defective Work
A. If Contractor fails within a reasonable time after written notice from City to correct defective
Work, or to remove and replace rejected Work as required by City in accordance with Paragraph
11.06.A, or if Contractor fails to perform the Work in accordance with the Contract Documents,
or if Contractor fails to comply with any other provision of the Contract Documents, City may,
after seven (7) days written notice to Contractor and the Developer, correct, or remedy any such
deficiency.
B. In exercising the rights and remedies under this Paragraph 11.09, City shall proceed
expeditiously. In connection with such corrective or remedial action, City may exclude
Contractor from all or part of the Site, take possession of all or part of the Work and suspend
Contractor's services related thereto, and incorporate in the Work all materials and equipment
incorporated in the Work, stored at the Site or for which City has paid Contractor but which are
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
00 73 10- 32
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 32 of 35
stored elsewhere. Contractor shall allow City, City's representatives, agents, consultants,
employees, and City's other contractors, access to the Site to enable City to exercise the rights
and remedies under this Paragraph.
C. All claims, costs, losses, and damages (including but not limited to all fees and charges of
engineers, architects, attorneys, and other professionals and all court or other dispute resolution
costs) incurred or sustained by City in exercising the rights and remedies under this Paragraph
13.09 will be charged against Contractor, and a Change Order will be issued incorporating the
necessary revisions in the Contract Documents with respect to the Work; and City shall be
entitled to an appropriate decrease in the Contract Price.
D. Contractor shall not be allowed an extension of the Contract Time because of any delay in the
performance of the Work attributable to the exercise of City's rights and remedies under this
Paragraph 11.09.
ARTICLE 12 — COMPLETION
12.01 Contractor's Warranty of Title
Contractor warrants and guarantees that title to all Work, materials, and equipment covered by any
Application for Payment will pass to City no later than the time of Final Acceptance and shall be
free and clear of all Liens.
12.02 Partial Utilization
A. Prior to Final Acceptance of all the Work, City may use or occupy any substantially completed
part of the Work which has specifically been identified in the Contract Documents, or which
City, determines constitutes a separately functioning and usable part of the Work that can be
used by City for its intended purpose without significant interference with Contractor's
performance of the remainder of the Work. City at any time may notify Contractor in writing to
permit City to use or occupy any such part of the Work which City determines to be ready for its
intended use, subject to the following conditions:
1. Contractor at any time may notify City in writing that Contractor considers any such part of
the Work ready for its intended use.
2. Within a reasonable time after notification as enumerated in Paragraph 14.05.A.1, City and
Contractor shall make an inspection of that part of the Work to determine its status of
completion. If City does not consider that part of the Work to be substantially complete, City
will notify Contractor in writing giving the reasons therefor.
3. Partial Utilization will not constitute Final Acceptance by City.
12.03 Final Inspection
A. Upon written notice from Contractor that the entire Work is complete in accordance with the
Contract Documents:
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
00 73 10- 33
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 33 of 35
1. within 10 days, City will schedule a Final Inspection with Contractor.
2. City will notify Contractor in writing of all particulars in which this inspection reveals that
the Work is incomplete or defective. Contractor shall immediately take such measures as are
necessary to complete such Work or remedy such deficiencies.
12.04 Final Acceptance
A. Upon completion by Contractor to City's satisfaction, of any additional Work identified in the
Final Inspection, City will issue to Contractor a letter of Final Acceptance upon the satisfaction
of the following:
1. All documentation called for in the Contract Documents, including but not limited to the
evidence of insurance required by Paragraph 5.03;
2. consent of the surety, if any, to Final Acceptance;
3. a list of all pending or released Damage Claims against City that Contractor believes are
unsettled; and
4. affidavits of payments and complete and legally effective releases or waivers (satisfactory to
City) of all Lien rights arising out of or Liens filed in connection with the Work.
5. after all Damage Claims have been resolved:
a. directly by the Contractor or;
b. Contractor provides evidence that the Damage Claim has been reported to Contractor's
insurance provider for resolution.
6. Issuing Final Acceptance by the City shall not relieve the Contractor of any guarantees or
other requirements of the Contract Documents which specifically continue thereafter.
ARTICLE 13 — SUSPENSION OF WORK
13.01 City May Suspend Work
A. At any time and without cause, City may suspend the Work or any portion thereof by written
notice to Contractor and which may fix the date on which Work will be resumed. Contractor
shall resume the Work on the date so fixed. During temporary suspension of the Work covered
by these Contract Documents, for any reason, the City will stop contract time on City
participation projects.
B. Should the Contractor not be able to complete a portion of the Project due to causes beyond the
control of and without the fault or negligence of the Contractor, and should it be determined by
mutual consent of the Contractor and City that a solution to allow construction to proceed is not
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
00 73 10- 34
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 34 of 35
available within a reasonable period of time, Contractor may request an extension in Contract
Time, directly attributable to any such suspension.
C. If it should become necessary to suspend the Work for an indefinite period, the Contractor shall
store all materials in such a manner that they will not obstruct or impede the public unnecessarily
nor become damaged in any way, and he shall take every precaution to prevent damage or
deterioration of the work performed; he shall provide suitable drainage about the work, and erect
temporary structures where necessary.
ARTICLE 14 — MISCELLANEOUS
14.01 Giving Notice
A. Whenever any provision of the Contract Documents requires the giving of written notice, it will
be deemed to have been validly given i£
1. delivered in person to the individual or to a member of the firm or to an officer of the
corporation for whom it is intended; or
2. delivered at or sent by registered or certified mail, postage prepaid, to the last business
address known to the giver of the notice.
B. Business address changes must be promptly made in writing to the other party.
C. Whenever the Contract Documents specifies giving notice by electronic means such electronic
notice shall be deemed sufficient upon confirmation of receipt by the receiving party.
14.02 Computation of Times
When any period of time is referred to in the Contract Documents by days, it will be computed to
exclude the first and include the last day of such period. If the last day of any such period falls on a
Saturday or Sunday or on a day made a legal holiday the next Working Day shall become the last
day of the period.
14.03 Cumulative Remedies
The duties and obligations imposed by these General Conditions and the rights and remedies
available hereunder to the parties hereto are in addition to, and are not to be construed in any way as
a limitation of, any rights and remedies available to any or all of them which are otherwise imposed
or available by Laws or Regulations, by special warranty or guarantee, or by other provisions of the
Contract Documents. The provisions of this Paragraph will be as effective as if repeated specifically
in the Contract Documents in connection with each particular duty, obligation, right, and remedy to
which they apply.
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
00 73 10- 35
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 35 of 35
14.04 Survival of Obligations
All representations, indemnifications, warranties, and guarantees made in, required by, or given in
accordance with the Contract Documents, as well as all continuing obligations indicated in the
Contract Documents, will survive final payment, completion, and acceptance of the Work or
termination or completion of the Contract or termination of the services of Contractor.
14.05 Headings
Article and paragraph headings are inserted for convenience only and do not constitute parts of these
General Conditions.
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
1
2
3 PART1- GENERAL
4 1.1 SUMMARY
SECTION 01 11 00
SUMMARY OF WORK
011100-1
DAP SUMMARY OF WORK
Paget of 3
5 A. Section Includes:
6 1. Summary of Work to be performed in accordance with the Contract Documents
7 B. Deviations from this City of Fort Worth Standard Specification
8 1. None.
9 C. Related Specification Sections include, but are not necessarily limited to:
10 1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the Contract
11 2. Division 1 - General Requirements
12 1.2 PRICE AND PAYMENT PROCEDURES
13 A. Measurement and Payment
14 1. Work associated with this Item is considered subsidiary to the various items bid.
15 No separate payment will be allowed for this Item.
16 1.3 REFERENCES [NOT USED]
17 1.4 ADMINISTRATIVE REQUIREMENTS
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
A. Work Covered by Contract Documents
1. Work is to include furnishing all labor, materials, and equipment, and performing
all Work necessary for this construction project as detailed in the Drawings and
Specifications.
B. Subsidiary Work
1. Any and all Work specifically governed by documentary requirements for the
project, such as conditions imposed by the Drawings or Contract Documents in
which no specific item for bid has been provided for in the Proposal and the item is
not a typical unit bid item included on the standard bid item list, then the item shall
be considered as a subsidiary item of Work, the cost of which shall be included in
the price bid in the Proposal for various bid items.
C. Use of Premises
1. Coordinate uses of premises under direction of the City.
2. Assume full responsibility for protection and safekeeping of materials and
equipment stored on the Site.
3. Use and occupy only portions of the public streets and alleys, or other public places
or other rights -of -way as provided for in the ordinances of the City, as shown in the
Contract Documents, or as may be specifically authorized in writing by the City.
a. A reasonable amount of tools, materials, and equipment for construction
purposes may be stored in such space, but no more than is necessary to avoid
delay in the construction operations.
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — Developer Awarded Projects City Project No. - 103849
Revised December 20, 2012
011100-2
DAP SUMMARY OF WORK
Page 2 of 3
1 b. Excavated and waste materials shall be stored in such a way as not to interfere
2 with the use of spaces that may be designated to be left free and unobstructed
3 and so as not to inconvenience occupants of adjacent property.
4 c. If the street is occupied by railroad tracks, the Work shall be carried on in such
5 manner as not to interfere with the operation of the railroad.
6 1) All Work shall be in accordance with railroad requirements set forth in
7 Division 0 as well as the railroad permit.
8 D. Work within Easements
9 1. Do not enter upon private property for any purpose without having previously
10 obtained permission ftom the owner of such property.
11 2. Do not store equipment or material on private property unless and until the
12 specified approval of the property owner has been secured in writing by the
13 Contractor and a copy furnished to the City.
14 3. Unless specifically provided otherwise, clear all rights -of -way or easements of
15 obstructions which must be removed to make possible proper prosecution of the
16 Work as a part of the project construction operations.
17 4. Preserve and use every precaution to prevent damage to, all trees, shrubbery, plants,
18 lawns, fences, culverts, curbing, and all other types of structures or improvements,
19 to all water, sewer, and gas lines, to all conduits, overhead pole lines, or
20 appurtenances thereof, including the construction of temporary fences and to all
21 other public or private property adjacent to the Work.
22 5. Notify the proper representatives of the owners or occupants of the public or private
23 lands of interest in lands which might be affected by the Work.
24 a. Such notice shall be made at least 48 hours in advance of the beginning of the
25 Work.
26 b. Notices shall be applicable to both public and private utility companies and any
27 corporation, company, individual, or other, either as owners or occupants,
28 whose land or interest in land might be affected by the Work.
29 c. Be responsible for all damage or injury to property of any character resulting
30 ftom any act, omission, neglect, or misconduct in the manner or method or
31 execution of the Work, or at any time due to defective work, material, or
32 equipment.
33 6. Fence
34 a. Restore all fences encountered and removed during construction of the Project
35 to the original or a better than original condition.
36 b. Erect temporary fencing in place of the fencing removed whenever the Work is
37 not in progress and when the site is vacated overnight, and/or at all times to
38 provide site security.
39 c. The cost for all fence work within easements, including removal, temporary
40 closures and replacement, shall be subsidiary to the various items bid in the
41 project proposal, unless a bid item is specifically provided in the proposal.
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — Developer Awarded Projects City Project No. - 103849
Revised December 20, 2012
011100-3
DAP SUMMARY OF WORK
Page 3 of 3
1 1.5
SUBMITTALS [NOT USED]
2 1.6
ACTION SUBMITTALSANFORMATIONAL SUBMITTALS [NOT USED]
3 1.7
CLOSEOUT SUBMITTALS [NOT USED]
4 1.8
MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
5 1.9
QUALITY ASSURANCE [NOT USED]
6 1.10
DELIVERY, STORAGE, AND HANDLING [NOT USED]
7 1.11
FIELD [SITE] CONDITIONS [NOT USED]
8 1.12
WARRANTY [NOT USED]
9 PART 2 - PRODUCTS [NOT USED]
10 PART 3 - EXECUTION [NOT USED]
11 END OF SECTION
12
Revision Log
DATE NAME SUMMARY OF CHANGE
13
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — Developer Awarded Projects City Project No. - 103849
Revised December 20, 2012
01 25 00 - 1
DAP SUBSTITUTION PROCEDURES
Page 1 of 4
1 SECTION 0125 00
2 SUBSTITUTION PROCEDURES
3 PART1- GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. The procedure for requesting the approval of substitution of a product that is not
7 equivalent to a product which is specified by descriptive or performance criteria or
8 defined by reference to 1 or more of the following:
9 a. Name of manufacturer
10 b. Name of vendor
11 c. Trade name
12 d. Catalog number
13 2. Substitutions are not "or -equals".
14 B. Deviations from this City of Fort Worth Standard Specification
15 1. None.
16 C. Related Specification Sections include, but are not necessarily limited to:
17 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
18 2. Division 1 — General Requirements
19 1.2 PRICE AND PAYMENT PROCEDURES
20 A. Measurement and Payment
21 1. Work associated with this Item is considered subsidiary to the various items bid. No
22 separate payment will be allowed for this Item.
23 1.3 REFERENCES [NOT USED]
24 1.4 ADMINISTRATIVE REQUIREMENTS
25 A. Request for Substitution - General
26 1. Within 30 days after award of Contract (unless noted otherwise), the City will
27 consider formal requests from Contractor for substitution of products in place of
28 those specified.
29 2. Certain types of equipment and kinds of material are described in Specifications by
30 means of references to names of manufacturers and vendors, trade names, or catalog
31 numbers.
32 a. When this method of specifying is used, it is not intended to exclude from
33 consideration other products bearing other manufacturer's or vendor's names,
34 trade names, or catalog numbers, provided said products are "or -equals," as
35 determined by City.
36 3. Other types of equipment and kinds of material may be acceptable substitutions
37 under the following conditions:
38 a. Or -equals are unavailable due to strike, discontinued production of products
39 meeting specified requirements, or other factors beyond control of Contractor;
40 or,
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised August 30, 2013
012500-2
DAP SUBSTITUTION PROCEDURES
Page 2 of 4
1 b. Contractor proposes a cost and/or time reduction incentive to the City.
2 1.5 SUBMITTALS
3 A. See Request for Substitution Form (attached)
4 B. Procedure for Requesting Substitution
5 1. Substitution shall be considered only:
6 a. After award of Contract
7 b. Under the conditions stated herein
8 2. Submit 3 copies of each written request for substitution, including:
9 a. Documentation
10 1) Complete data substantiating compliance of proposed substitution with
11 Contract Documents
12 2) Data relating to changes in construction schedule, when a reduction is
13 proposed
14 3) Data relating to changes in cost
15 b. For products
16 1) Product identification
17 a) Manufacturer's name
18 b) Telephone number and representative contact name
19 c) Specification Section or Drawing reference of originally specified
20 product, including discrete name or tag number assigned to original
21 product in the Contract Documents
22 2) Manufacturer's literature clearly marked to show compliance of proposed
23 product with Contract Documents
24 3) Itemized comparison of original and proposed product addressing product
25 characteristics including, but not necessarily limited to:
26 a) Size
27 b) Composition or materials of construction
28 c) Weight
29 d) Electrical or mechanical requirements
30 4) Product experience
31 a) Location of past projects utilizing product
32 b) Name and telephone number of persons associated with referenced
33 projects knowledgeable concerning proposed product
34 c) Available field data and reports associated with proposed product
35 5) Samples
36 a) Provide at request of City.
37 b) Samples become the property of the City.
38 c. For construction methods:
39 1) Detailed description of proposed method
40 2) Illustration drawings
41 C. Approval or Rejection
42 1. Written approval or rejection of substitution given by the City
43 2. City reserves the right to require proposed product to comply with color and pattern
44 of specified product if necessary to secure design intent.
45 3. In the event the substitution is approved, if a reduction in cost or time results, it will
46 be documented by Change Order.
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised August 30, 2013
012500-3
DAP SUBSTITUTION PROCEDURES
Page 3 of 4
1 4. Substitution will be rejected if-
2 a. Submittal is not through the Contractor with his stamp of approval
3 b. Request is not made in accordance with this Specification Section
4 c. In the Developer's opinion, acceptance will require substantial revision of the
5 original design
6 d. In the City's or Developer's opinion, substitution will not perform adequately
7 the function consistent with the design intent
8 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
9 1.7 CLOSEOUT SUBMITTALS [NOT USED]
10 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
11 1.9 QUALITY ASSURANCE
12 A. In making request for substitution or in using an approved product, the Contractor
13 represents that the Contractor:
14 1. Has investigated proposed product, and has determined that it is adequate or
15 superior in all respects to that specified, and that it will perform function for which it
16 is intended
17 2. Will provide same guarantee for substitute item as for product specified
18 3. Will coordinate installation of accepted substitution into Work, to include building
19 modifications if necessary, making such changes as may be required for Work to be
20 complete in all respects
21 4. Waives all claims for additional costs related to substitution which subsequently
22 arise
23 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
24 1.11 FIELD [SITE] CONDITIONS [NOT USED]
25 1.12 WARRANTY [NOT USED]
26 PART 2 - PRODUCTS [NOT USED]
27 PART 3 - EXECUTION [NOT USED]
28 END OF SECTION
29
30
Revision Log
DATE NAME SUMMARY OF CHANGE
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised August 30, 2013
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
012500-4
DAP SUBSTITUTION PROCEDURES
Page 4 of 4
EXHIBIT A
REQUEST FOR SUBSTITUTION FORM:
TO:
PROJECT: DATE:
We hereby submit for your consideration the following product instead of the specified item for
the above project:
SECTION PARAGRAPH SPECIFIED ITEM
Proposed Substitution:
Reason for Substitution:
Include complete information on changes to Drawings and/or Specifications which proposed
substitution will require for its proper installation.
Fill in Blanks Below:
A. Will the undersigned contractor pay for changes to the building design, including engineering
and detailing costs caused by the requested substitution?
B. What effect does substitution have on other trades?
C. Differences between proposed substitution and specified item?
D. Differences in product cost or product delivery time?
E. Manufacturer's guarantees of the proposed and specified items are:
Equal Better (explain on attachment)
The undersigned states that the function, appearance and quality are equivalent or superior to the
specified item.
Submitted By: For Use by City
Signature Recommended
as noted
Firm Not recommended
Address By
Date
Date Remarks
Telephone
For Use by City:
Approved Rejected
City Date
Recommended
Received late
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised August 30, 2013
1
2
3 PART1- GENERAL
SECTION 01 31 19
PRECONSTRUCTION MEETING
01 31 19-1
DAP PRECONSTRUCTION MEETING
Page 1 of 3
4 1.1 SUMMARY
5 A. Section Includes:
6 1. Provisions for the preconstruction meeting to be held prior to the start of Work to
7 clarify construction contract administration procedures
8 B. Deviations from this City of Fort Worth Standard Specification
9 1. No construction schedule required unless requested by the City.
10 C. Related Specification Sections include, but are not necessarily limited to:
11 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
12 2. Division 1 — General Requirements
13 1.2 PRICE AND PAYMENT PROCEDURES
14 A. Measurement and Payment
15 1. Work associated with this Item is considered subsidiary to the various items bid.
16 No separate payment will be allowed for this Item.
17 1.3 REFERENCES [NOT USED]
18 1.4 ADMINISTRATIVE REQUIREMENTS
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
A. Coordination
1. Attend preconstruction meeting.
2. Representatives of Contractor, subcontractors and suppliers attending meetings
shall be qualified and authorized to act on behalf of the entity each represents.
3. Meeting administered by City may be tape recorded.
a. If recorded, tapes will be used to prepare minutes and retained by City for
future reference.
B. Preconstruction Meeting
1. A preconstruction meeting will be held within 14 days after the delivery of the
distribution package to the City.
a. The meeting will be scheduled and administered by the City.
2. The Project Representative will preside at the meeting, prepare the notes of the
meeting and distribute copies of same to all participants who so request by fully
completing the attendance form to be circulated at the beginning of the meeting.
3. Attendance shall include:
a. Developer and Consultant
b. Contractor's project manager
c. Contractor's superintendent
d. Any subcontractor or supplier representatives whom the Contractor may desire
to invite or the City may request
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised August 30, 2013
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
01 31 19 - 2
DAP PRECONSTRUCTION MEETING
Page 2 of 3
e. Other City representatives
f. Others as appropriate
4. Preliminary Agenda may include:
a. Introduction of Project Personnel
b. General Description of Project
c. Status of right-of-way, utility clearances, easements or other pertinent permits
d. Contractor's work plan and schedule
e. Contract Time
f. Notice to Proceed
g. Construction Staking
h. Progress Payments
i. Extra Work and Change Order Procedures
j. Field Orders
k. Disposal Site Letter for Waste Material
1. Insurance Renewals
m. Payroll Certification
n. Material Certifications and Quality Control Testing
o. Public Safety and Convenience
p. Documentation of Pre -Construction Conditions
q. Weekend Work Notification
r. Legal Holidays
s. Trench Safety Plans
t. Confined Space Entry Standards
u. Coordination with the City's representative for operations of existing water
systems
v. Storm Water Pollution Prevention Plan
w. Coordination with other Contractors
x. Early Warning System
y. Contractor Evaluation
z. Special Conditions applicable to the project
aa. Damages Claims
bb. Submittal Procedures
cc. Substitution Procedures
dd. Correspondence Routing
ee. Record Drawings
f£ Temporary construction facilities
gg. MBE/SBE procedures
hh. Final Acceptance
ii. Final Payment
J. Questions or Comments
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised August 30, 2013
01 31 19-3
DAP PRECONSTRUCTION MEETING
Page 3 of 3
1 1.5
SUBMITTALS [NOT USED]
2 1.6
ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
3 1.7
CLOSEOUT SUBMITTALS [NOT USED]
4 1.8
MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
5 1.9
QUALITY ASSURANCE [NOT USED]
6 1.10
DELIVERY, STORAGE, AND HANDLING [NOT USED]
7 1.11
FIELD [SITE] CONDITIONS [NOT USED]
8 1.12
WARRANTY [NOT USED]
9 PART 2 - PRODUCTS [NOT USED]
10 PART 3 - EXECUTION [NOT USED]
11 END OF SECTION
12
13
Revision Log
I DATE NAME SUMMARY OF CHANGE
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised August 30, 2013
1
2
3 PART1- GENERAL
4 1.1 SUMMARY
SECTION 0132 33
PRECONSTRUCTION VIDEO
01 3233- 1
DAP PRECONSTRUCTION VIDEO
Page 1 of 2
5 A. Section Includes:
6 1. Administrative and procedural requirements for:
7 a. Preconstruction Videos
8 B. Deviations from this City of Fort Worth Standard Specification
9 1. Though not mandatory, it is highly recommended on infill developer projects.
10 C. Related Specification Sections include, but are not necessarily limited to:
11 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
12 2. Division 1 — General Requirements
13 1.2 PRICE AND PAYMENT PROCEDURES
14 A. Measurement and Payment
15 1. Work associated with this Item is considered subsidiary to the various items bid.
16 No separate payment will be allowed for this Item.
17 1.3 REFERENCES [NOT USED]
18 1.4 ADMINISTRATIVE REQUIREMENTS
19 A. Preconstruction Video
20 1. Produce a preconstruction video of the site/alignment, including all areas in the
21 vicinity of and to be affected by construction.
22 a. Provide digital copy of video upon request by the City.
23 2. Retain a copy of the preconstruction video until the end of the maintenance surety
24 period.
25 1.5 SUBMITTALS [NOT USED]
26 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
27 1.7 CLOSEOUT SUBMITTALS [NOT USED]
28 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
29 1.9 QUALITY ASSURANCE [NOT USED]
30 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
31 1.11 FIELD [SITE] CONDITIONS [NOT USED]
32 1.12 WARRANTY [NOT USED]
33 PART 2 - PRODUCTS [NOT USED]
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised August 30, 2013
01 32 33 - 2
DAP PRECONSTRUCTION VIDEO
Page 2 of 2
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised August 30, 2013
1
2
3 PART1- GENERAL
4 1.1 SUMMARY
SECTION 0133 00
DAP SUBMITTALS
01 33 00 - 1
DAP SUBMITTALS
Page 1 of 8
5 A. Section Includes:
6 1. General methods and requirements of submissions applicable to the following
7 Work -related submittals:
8 a. Shop Drawings
9 b. Product Data (including Standard Product List submittals)
10 c. Samples
11 d. Mock Ups
12 B. Deviations from this City of Fort Worth Standard Specification
13 1. None.
14 C. Related Specification Sections include, but are not necessarily limited to:
15 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
16 2. Division 1 — General Requirements
17 1.2 PRICE AND PAYMENT PROCEDURES
18 A. Measurement and Payment
19 1. Work associated with this Item is considered subsidiary to the various items bid.
20 No separate payment will be allowed for this Item.
21 1.3 REFERENCES [NOT USED]
22 1.4 ADMINISTRATIVE REQUIREMENTS
23 A. Coordination
24 1. Notify the City in writing, at the time of submittal, of any deviations in the
25 submittals from the requirements of the Contract Documents.
26 2. Coordination of Submittal Times
27 a. Prepare, prioritize and transmit each submittal sufficiently in advance of
28 performing the related Work or other applicable activities, or within the time
29 specified in the individual Work Sections, of the Specifications.
30 b. Contractor is responsible such that the installation will not be delayed by
31 processing times including, but not limited to:
32 a) Disapproval and resubmittal (if required)
33 b) Coordination with other submittals
34 c) Testing
35 d) Purchasing
36 e) Fabrication
37 f) Delivery
38 g) Similar sequenced activities
39 c. No extension of time will be authorized because of the Contractor's failure to
40 transmit submittals sufficiently in advance of the Work.
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised August 30, 2013
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
01 33 00 - 2
DAP SUBMITTALS
Page 2 of 8
d. Make submittals promptly in accordance with approved schedule, and in such
sequence as to cause no delay in the Work or in the work of any other
contractor.
B. Submittal Numbering
1. When submitting shop drawings or samples, utilize a 9-character submittal cross-
reference identification numbering system in the following manner:
a. Use the first 6 digits of the applicable Specification Section Number.
b. For the next 2 digits number use numbers 01-99 to sequentially number each
initial separate item or drawing submitted under each specific Section number.
c. Last use a letter, A-Z, indicating the resubmission of the same drawing (i.e.
A=2nd submission, B=3rd submission, C=4th submission, etc.). A typical
submittal number would be as follows:
03 30 00-08-B
1) 03 30 00 is the Specification Section for Concrete
2) 08 is the eighth initial submittal under this Specification Section
3) B is the third submission (second resubmission) of that particular shop
drawing
C. Contractor Certification
1. Review shop drawings, product data and samples, including those by
subcontractors, prior to submission to determine and verify the following:
a. Field measurements
b. Field construction criteria
c. Catalog numbers and similar data
d. Conformance with the Contract Documents
2. Provide each shop drawing, sample and product data submitted by the Contractor
with a Certification Statement affixed including:
a. The Contractor's Company name
b. Signature of submittal reviewer
c. Certification Statement
1) `By this submittal, I hereby represent that I have determined and verified
field measurements, field construction criteria, materials, dimensions,
catalog numbers and similar data and I have checked and coordinated each
item with other applicable approved shop drawings."
D. Submittal Format
1. Fold shop drawings larger than 8 '/2 inches x 11 inches to 8 '/z inches x 11 inches.
2. Bind shop drawings and product data sheets together.
3. Order
a. Cover Sheet
1) Description of Packet
2) Contractor Certification
b. List of items / Table of Contents
c. Product Data /Shop Drawings/Samples /Calculations
E. Submittal Content
1. The date of submission and the dates of any previous submissions
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised August 30, 2013
01 33 00 - 3
DAP SUBMITTALS
Page 3 of 8
1
2.
The Project title and number
2
3.
Contractor identification
3
4.
The names of-
4
a. Contractor
5
b. Supplier
6
c. Manufacturer
7
5.
Identification of the product, with the Specification Section number, page and
8
paragraph(s)
9
6.
Field dimensions, clearly identified as such
10
7.
Relation to adjacent or critical features of the Work or materials
11
8.
Applicable standards, such as ASTM or Federal Specification numbers
12
9.
Identification by highlighting of deviations from Contract Documents
13
10.
Identification by highlighting of revisions on resubmittals
14
11.
An 8-inch x 3-inch blank space for Contractor and City stamps
15
F. Shop Drawings
16
1.
As specified in individual Work Sections includes, but is not necessarily limited to:
17
a. Custom -prepared data such as fabrication and erection/installation (working)
18
drawings
19
b. Scheduled information
20
c. Setting diagrams
21
d. Actual shopwork manufacturing instructions
22
e. Custom templates
23
f. Special wiring diagrams
24
g. Coordination drawings
25
h. Individual system or equipment inspection and test reports including:
26
1) Performance curves and certifications
27
i. As applicable to the Work
28
2.
Details
29
a. Relation of the various parts to the main members and lines of the structure
30
b. Where correct fabrication of the Work depends upon field measurements
31
1) Provide such measurements and note on the drawings prior to submitting
32
for approval.
33
G. Product Data
34
1.
For submittals of product data for products included on the City's Standard Product
35
List, clearly identify each item selected for use on the Project.
36
2.
For submittals of product data for products not included on the City's Standard
37
Product List, submittal data may include, but is not necessarily limited to:
38
a. Standard prepared data for manufactured products (sometimes referred to as
39
catalog data)
40
1) Such as the manufacturer's product specification and installation
41
instructions
42
2) Availability of colors and patterns
43
3) Manufacturer's printed statements of compliances and applicability
44
4) Roughing -in diagrams and templates
45
5) Catalog cuts
46
6) Product photographs
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised August 30, 2013
01 33 00 - 4
DAP SUBMITTALS
Page 4 of 8
1 7) Standard wiring diagrams
2 8) Printed performance curves and operational -range diagrams
3 9) Production or quality control inspection and test reports and certifications
4 10) Mill reports
5 11) Product operating and maintenance instructions and recommended
6 spare -parts listing and printed product warranties
7 12) As applicable to the Work
8 H. Samples
9 1. As specified in individual Sections, include, but are not necessarily limited to:
10 a. Physical examples of the Work such as:
11 1) Sections of manufactured or fabricated Work
12 2) Small cuts or containers of materials
13 3) Complete units of repetitively used products color/texture/pattern swatches
14 and range sets
15 4) Specimens for coordination of visual effect
16 5) Graphic symbols and units of Work to be used by the City for independent
17 inspection and testing, as applicable to the Work
18 I. Do not start Work requiring a shop drawing, sample or product data nor any material to
19 be fabricated or installed prior to the approval or qualified approval of such item.
20 1. Fabrication performed, materials purchased or on -site construction accomplished
21 which does not conform to approved shop drawings and data is at the Contractor's
22 risk.
23 2. The City will not be liable for any expense or delay due to corrections or remedies
24 required to accomplish conformity.
25 3. Complete project Work, materials, fabrication, and installations in conformance
26 with approved shop drawings, applicable samples, and product data.
27 J. Submittal Distribution
28 1. Electronic Distribution
29 a. Confirm development of Project directory for electronic submittals to be
30 uploaded to City's Buzzsaw site, or another external FTP site approved by the
31 City.
32 b. Shop Drawings
33 1) Upload submittal to designated project directory and notify appropriate
34 City representatives via email of submittal posting.
35 2) Hard Copies
36 a) 3 copies for all submittals
37 b) If Contractor requires more than 1 hard copy of Shop Drawings
38 returned, Contractor shall submit more than the number of copies listed
39 above.
40 c. Product Data
41 1) Upload submittal to designated project directory and notify appropriate
42 City representatives via email of submittal posting.
43 2) Hard Copies
44 a) 3 copies for all submittals
45 d. Samples
46 1) Distributed to the Project Representative
47 2. Hard Copy Distribution (if required in lieu of electronic distribution)
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised August 30, 2013
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
01 33 00 - 5
DAP SUBMITTALS
Page 5 of 8
a. Shop Drawings
1) Distributed to the City
2) Copies
a) 8 copies for mechanical submittals
b) 7 copies for all other submittals
c) If Contractor requires more than 3 copies of Shop Drawings returned,
Contractor shall submit more than the number of copies listed above.
b. Product Data
1) Distributed to the City
2) Copies
a) 4 copies
c. Samples
1) Distributed to the Project Representative
2) Copies
a) Submit the number stated in the respective Specification Sections.
3. Distribute reproductions of approved shop drawings and copies of approved
product data and samples, where required, to the job site file and elsewhere as
directed by the City.
a. Provide number of copies as directed by the City but not exceeding the number
previously specified.
K. Submittal Review
1. The review of shop drawings, data and samples will be for general conformance
with the design concept and Contract Documents. This is not to be construed as:
a. Permitting any departure from the Contract requirements
b. Relieving the Contractor of responsibility for any errors, including details,
dimensions, and materials
c. Approving departures from details furnished by the City, except as otherwise
provided herein
2. The review and approval of shop drawings, samples or product data by the City
does not relieve the Contractor from his/her responsibility with regard to the
fulfillment of the terms of the Contract.
a. All risks of error and omission are assumed by the Contractor, and the City will
have no responsibility therefore.
3. The Contractor remains responsible for details and accuracy, for coordinating the
Work with all other associated work and trades, for selecting fabrication processes,
for techniques of assembly and for performing Work in a safe manner.
4. If the shop drawings, data or samples as submitted describe variations and show a
departure from the Contract requirements which City finds to be in the interest of
the City and to be so minor as not to involve a change in Contract Price or time for
performance, the City may return the reviewed drawings without noting an
exception.
5. Submittals will be returned to the Contractor under 1 of the following codes:
a. Code 1
1) "NO EXCEPTIONS TAKEN' is assigned when there are no notations or
comments on the submittal.
a) When returned under this code the Contractor may release the
equipment and/or material for manufacture.
b. Code 2
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised August 30, 2013
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
01 33 00 - 6
DAP SUBMITTALS
Page 6 of 8
1) "EXCEPTIONS NOTED". This code is assigned when a confirmation of
the notations and comments IS NOT required by the Contractor.
a) The Contractor may release the equipment or material for manufacture;
however, all notations and comments must be incorporated into the
final product.
c. Code 3
1) "EXCEPTIONS NOTED/RESUBMIT". This combination of codes is
assigned when notations and comments are extensive enough to require a
resubmittal of the package.
a) The Contractor may release the equipment or material for manufacture;
however, all notations and comments must be incorporated into the
final product.
b) This resubmittal is to address all comments, omissions and
non -conforming items that were noted.
c) Resubmittal is to be received by the City within 15 Calendar Days of
the date of the City's transmittal requiring the resubmittal.
d. Code 4
1) "NOT APPROVED" is assigned when the submittal does not meet the
intent of the Contract Documents.
a) The Contractor must resubmit the entire package revised to bring the
submittal into conformance.
b) It may be necessary to resubmit using a different manufacturer/vendor
to meet the Contract Documents.
6. Resubmittals
a. Handled in the same manner as first submittals
1) Corrections other than requested by the City
2) Marked with revision triangle or other similar method
a) At Contractor's risk if not marked
b. Submittals for each item will be reviewed no more than twice at the City's
expense.
1) All subsequent reviews will be performed at times convenient to the City
and at the Contractor's expense, based on the City's or City
Representative's then prevailing rates.
2) Provide Contractor reimbursement to the City within 30 Calendar Days for
all such fees invoiced by the City.
c. The need for more than 1 resubmission or any other delay in obtaining City's
review of submittals, will not entitle the Contractor to an extension of Contract
Time.
7. Partial Submittals
a. City reserves the right to not review submittals deemed partial, at the City's
discretion.
b. Submittals deemed by the City to be not complete will be returned to the
Contractor, and will be considered "Not Approved" until resubmitted.
c. The City may at its option provide a list or mark the submittal directing the
Contractor to the areas that are incomplete.
8. If the Contractor considers any correction indicated on the shop drawings to
constitute a change to the Contract Documents, then written notice must be
provided thereof to the Developer at least 7 Calendar Days prior to release for
manufacture.
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised August 30, 2013
01 33 00 - 7
DAP SUBMITTALS
Page 7 of 8
1 9. When the shop drawings have been completed to the satisfaction of the City, the
2 Contractor may carry out the construction in accordance therewith and no further
3 changes therein except upon written instructions from the City.
4 10. Each submittal, appropriately coded, will be returned within 30 Calendar Days
5 following receipt of submittal by the City.
6 L. Mock ups
7 1. Mock Up units as specified in individual Sections, include, but are not necessarily
8 limited to, complete units of the standard of acceptance for that type of Work to be
9 used on the Project. Remove at the completion of the Work or when directed.
10 M. Qualifications
11 1. If specifically required in other Sections of these Specifications, submit a P.E.
12 Certification for each item required.
13
N. Request for Information (RFI)
14
1. Contractor Request for additional information
15
a. Clarification or interpretation of the contract documents
16
b. When the Contractor believes there is a conflict between Contract Documents
17
c. When the Contractor believes there is a conflict between the Drawings and
18
Specifications
19
1) Identify the conflict and request clarification
20
2. Sufficient information shall be attached to permit a written response without further
21
information.
22
23
24
25
26
1.5
SUBMITTALS [NOT USED]
27
1.6
ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
28
1.7
CLOSEOUT SUBMITTALS [NOT USED]
29
1.8
MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
30
1.9
QUALITY ASSURANCE [NOT USED]
31
1.10
DELIVERY, STORAGE, AND HANDLING [NOT USED]
32
1.11
FIELD [SITE] CONDITIONS [NOT USED]
33
1.12
WARRANTY [NOT USED]
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised August 30, 2013
01 33 00 - 8
DAP SUBMITTALS
Page 8 of 8
I PART 2 - PRODUCTS [NOT USED]
2 PART 3 - EXECUTION [NOT USED]
3 END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
12/20/2012 D. Johnson 1.4.K.8. Working Days modified to Calendar Days
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised August 30, 2013
01 35 13-1
DAP SPECIAL PROJECT PROCEDURES
Page 1 of 7
1 SECTION 0135 13
2 SPECIAL PROJECT PROCEDURES
3 PART1- GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. The procedures for special project circumstances that includes, but is not limited to:
7 a. Coordination with the Texas Department of Transportation
8 b. Work near High Voltage Lines
9 c. Confined Space Entry Program
10 d. Air Pollution Watch Days
11 e. Use of Explosives, Drop Weight, Etc.
12 £ Water Department Notification
13 g. Public Notification Prior to Beginning Construction
14 h. Coordination with United States Army Corps of Engineers
15 i. Coordination within Railroad permits areas
16 j. Dust Control
17 k. Employee Parking
18 B. Deviations from this City of Fort Worth Standard Specification
19 1. None.
20 C. Related Specification Sections include, but are not necessarily limited to:
21 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
22 2. Division 1 — General Requirements
23 3. Section 33 12 25 — Connection to Existing Water Mains
24
25 1.2 REFERENCES
26 A. Reference Standards
27 1. Reference standards cited in this Specification refer to the current reference
28 standard published at the time of the latest revision date logged at the end of this
29 Specification, unless a date is specifically cited.
30 2. Health and Safety Code, Title 9. Safety, Subtitle A. Public Safety, Chapter 752.
31 High Voltage Overhead Lines.
32 3. North Central Texas Council of Governments (NCTCOG) — Clean Construction
33 Specification
34 1.3 ADMINISTRATIVE REQUIREMENTS
35 A. Coordination with the Texas Department of Transportation
36 1. When work in the right-of-way which is under the jurisdiction of the Texas
37 Department of Transportation (TxDOT):
38 a. Notify the Texas Department of Transportation prior to commencing any work
39 therein in accordance with the provisions of the permit
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised August, 30, 2013
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
01 35 13-2
DAP SPECIAL PROJECT PROCEDURES
Page 2 of 7
b. All work performed in the TxDOT right-of-way shall be performed in
compliance with and subject to approval from the Texas Department of
Transportation
B. Work near High Voltage Lines
1. Regulatory Requirements
a. All Work near High Voltage Lines (more than 600 volts measured between
conductors or between a conductor and the ground) shall be in accordance with
Health and Safety Code, Title 9, Subtitle A, Chapter 752.
2. Warning sign
a. Provide sign of sufficient size meeting all OSHA requirements.
3. Equipment operating within 10 feet of high voltage lines will require the following
safety features
a. Insulating cage -type of guard about the boom or arm
b. Insulator links on the lift hook connections for back hoes or dippers
c. Equipment must meet the safety requirements as set forth by OSHA and the
safety requirements of the owner of the high voltage lines
4. Work within 6 feet of high voltage electric lines
a. Notification shall be given to:
1) The power company (example: ONCOR)
a) Maintain an accurate log of all such calls to power company and record
action taken in each case.
b. Coordination with power company
1) After notification coordinate with the power company to:
a) Erect temporary mechanical barriers, de -energize the lines, or raise or
lower the lines
c. No personnel may work within 6 feet of a high voltage line before the above
requirements have been met.
C. Confined Space Entry Program
1. Provide and follow approved Confined Space Entry Program in accordance with
OSHA requirements.
2. Confined Spaces include:
a. Manholes
b. All other confined spaces in accordance with OSHA's Permit Required for
Confined Spaces
D. Use of Explosives, Drop Weight, Etc.
1. When Contract Documents permit on the project the following will apply:
a. Public Notification
1) Submit notice to City and proof of adequate insurance coverage, 24 hours
prior to commencing.
2) Minimum 24 hour public notification in accordance with Section 0131 13
E. Water Department Coordination
1. During the construction of this project, it will be necessary to deactivate, for a
period of time, existing lines. The Contractor shall be required to coordinate with
the Water Department to determine the best times for deactivating and activating
those lines.
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised August, 30, 2013
01 35 13-3
DAP SPECIAL PROJECT PROCEDURES
Page 3 of 7
1 2. Coordinate any event that will require connecting to or the operation of an existing
2 City water line system with the City's representative.
3 a. Coordination shall be in accordance with Section 33 12 25.
4 b. If needed, obtain a hydrant water meter from the Water Department for use
5 during the life of named project.
6 c. In the event that a water valve on an existing live system be turned off and on
7 to accommodate the construction of the project is required, coordinate this
8 activity through the appropriate City representative.
9 1) Do not operate water line valves of existing water system.
10 a) Failure to comply will render the Contractor in violation of Texas Penal
11 Code Title 7, Chapter 28.03 (Criminal Mischief) and the Contractor
12 will be prosecuted to the full extent of the law.
13 b) In addition, the Contractor will assume all liabilities and
14 responsibilities as a result of these actions.
15 F. Public Notification Prior to Beginning Construction
16 1. Prior to beginning construction on any block in the project, on a block by block
17 basis, prepare and deliver a notice or flyer of the pending construction to the front
18 door of each residence or business that will be impacted by construction. The notice
19 shall be prepared as follows:
20 a. Post notice or flyer 7 days prior to beginning any construction activity on each
21 block in the project area.
22 1) Prepare flyer on the Contractor's letterhead and include the following
23 information:
24 a) Name of Project
25 b) City Project No (CPN)
26 c) Scope of Project (i.e. type of construction activity)
27 d) Actual construction duration within the block
28 e) Name of the contractor's foreman and phone number
29 f) Name of the City's inspector and phone number
30 g) City's after-hours phone number
31 2) A sample of the `pre -construction notification' flyer is attached as Exhibit
32 A.
33 3) Submit schedule showing the construction start and finish time for each
34 block of the project to the inspector.
35 4) Deliver flyer to the City Inspector for review prior to distribution.
36 b. No construction will be allowed to begin on any block until the flyer is
37 delivered to all residents of the block.
38 G. Public Notification of Temporary Water Service Interruption during Construction
39 1. In the event it becomes necessary to temporarily shut down water service to
40 residents or businesses during construction, prepare and deliver a notice or flyer of
41 the pending interruption to the front door of each affected resident.
42 2. Prepared notice as follows:
43 a. The notification or flyer shall be posted 24 hours prior to the temporary
44 interruption.
45 b. Prepare flyer on the contractor's letterhead and include the following
46 information:
47 1) Name of the project
48 2) City Project Number
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised August, 30, 2013
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
01 35 13-4
DAP SPECIAL PROJECT PROCEDURES
Page 4 of 7
3) Date of the interruption of service
4) Period the interruption will take place
5) Name of the contractor's foreman and phone number
6) Name of the City's inspector and phone number
c. A sample of the temporary water service interruption notification is attached as
Exhibit B.
d. Deliver a copy of the temporary interruption notification to the City inspector
for review prior to being distributed.
e. No interruption of water service can occur until the flyer has been delivered to
all affected residents and businesses.
f. Electronic versions of the sample flyers can be obtained from the Project
Construction Inspector.
H. Coordination with United States Army Corps of Engineers (USACE)
1. At locations in the Project where construction activities occur in areas where
USACE permits are required, meet all requirements set forth in each designated
permit.
I. Coordination within Railroad Permit Areas
1. At locations in the project where construction activities occur in areas where
railroad permits are required, meet all requirements set forth in each designated
railroad permit. This includes, but is not limited to, provisions for:
a. Flagmen
b. Inspectors
c. Safety training
d. Additional insurance
e. Insurance certificates
£ Other employees required to protect the right-of-way and property of the
Railroad Company from damage arising out of and/or from the construction of
the project. Proper utility clearance procedures shall be used in accordance
with the permit guidelines.
2. Obtain any supplemental information needed to comply with the railroad's
requirements.
J. Dust Control
1. Use acceptable measures to control dust at the Site.
a. If water is used to control dust, capture and properly dispose of waste water.
b. If wet saw cutting is performed, capture and properly dispose of slurry.
K. Employee Parking
1. Provide parking for employees at locations approved by the City.
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised August, 30, 2013
01 35 13-5
DAP SPECIAL PROJECT PROCEDURES
Page 5 of 7
1 1.4
SUBMITTALS [NOT USED]
2 1.5
ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
3 1.6
CLOSEOUT SUBMITTALS [NOT USED]
4 1.7
MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
5 1.8
QUALITY ASSURANCE [NOT USED]
6 1.9
DELIVERY, STORAGE, AND HANDLING [NOT USED]
7 1.10
FIELD [SITE] CONDITIONS [NOT USED]
8 1.11
WARRANTY [NOT USED]
9 PART 2 - PRODUCTS [NOT USED]
10 PART 3 - EXECUTION [NOT USED]
11 END OF SECTION
12
13
Revision Log
DATE NAME SUMMARY OF CHANGE
1.3.13— Added requirement of compliance with Health and Safety Code, Title 9.
8/31/2012 D. Johnson Safety, Subtitle A. Public Safety, Chapter 752. High Voltage Overhead Lines.
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised August, 30, 2013
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
01 35 13-6
DAP SPECIAL PROJECT PROCEDURES
Page 6 of 7
EXHIBIT A
(To be printed on Contractor's Letterhead)
Date:
CPN No.:
Project Name:
Mapsco Location:
Limits of Construction:
THIS IS TO INFORM YOU THAT UNDER A CONTRACT WITH THE CITY OF FORT
WORTH, OUR COMPANY WILL WORK ON UTILITY LINES ON OR AROUND YOUR
PROPERTY.
CONSTRUCTION WILL BEGIN APPROXIMATELY SEVEN DAYS FROM THE DATE
OF THIS NOTICE.
IF YOU HAVE QUESTIONS ABOUT ACCESS, SECURITY, SAFETY OR ANY OTHER
ISSUE, PLEASE CALL:
Mr. <CONTRACTOR'S SUPERINTENDENT> AT <TELEPHONE NO.>
OR
Mr. <CITY INSPECTOR> AT < TELEPHONE NO.>
AFTER 4:30 PM OR ON WEEKENDS, PLEASE CALL (817) 392 8306
PLEASE KEEP THIS FLYER HANDY WHEN YOU CALL
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised August, 30, 2013
01 35 13-7
DAP SPECIAL PROJECT PROCEDURES
Page 7 of 7
I EXHIBIT B
0a
4
FORT WORTH
Dale:
001E NO. XXXX
Project Dame:
NOTICE OF TEMPORARY WATER SERVICE
INTERRUPTION
DUE TO UTILITY IMPROVEMENTS IN YOUR NEIGHBORHOOD, YOUR
WATER SERVICE WILL BE INTERRUPTED ON
BETWEEN THE HOURS OF AND
IF YOU HAVE QUESTIONS ABOUT THIS SHUTOUT, PLEASE CALL;
MR. AT
(CONTRACTORS SUPERINTENDENT) (TELEPHONE NUMBER)
OR
MR. AT
(CITY INSPECTOR) (TELEPHONE NUMBER)
THIS INCONVENIENCE WILL BE AS SHORT AS POSSIBLE.
THANK YOU,
CONTRACTOR
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised August, 30, 2013
014523-1
DAP TESTING AND INSPECTION SERVICES
Page 1 of 2
1 SECTION 0145 23
2 TESTING AND INSPECTION SERVICES
3 PART1- GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. Testing and inspection services procedures and coordination
7 B. Deviations from this City of Fort Worth Standard Specification
8 1. None.
9 C. Related Specification Sections include, but are not necessarily limited to:
10 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
11 2. Division 1 — General Requirements
12 1.2 PRICE AND PAYMENT PROCEDURES
13 A. Measurement and Payment
14 1. Work associated with this Item is considered subsidiary to the various Items bid.
15 No separate payment will be allowed for this Item.
16 a. Contractor is responsible for performing, coordinating, and payment of all
17 Quality Control testing.
18 b. City is responsible for performing and payment for first set of Quality
19 Assurance testing.
20 1) If the first Quality Assurance test performed by the City fails, the
21 Contractor is responsible for payment of subsequent Quality Assurance
22 testing until a passing test occurs.
23 a) Final acceptance will not be issued by City until all required payments
24 for testing by Contractor have been paid in full.
25 1.3 REFERENCES [NOT USED]
26 1.4 ADMINISTRATIVE REQUIREMENTS
27 A. Testing
28 1. Complete testing in accordance with the Contract Documents.
29 2. Coordination
30 a. When testing is required to be performed by the City, notify City, sufficiently
31 in advance, when testing is needed.
32 b. When testing is required to be completed by the Contractor, notify City,
33 sufficiently in advance, that testing will be performed.
34 3. Distribution of Testing Reports
35 a. Electronic Distribution
36 1) Confirm development of Project directory for electronic submittals to be
37 uploaded to the City's document management system, or another form of
38 distribution approved by the City.
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised March 20, 2020
014523-2
DAP TESTING AND INSPECTION SERVICES
Page 2 of 2
1 2) Upload test reports to designated project directory and notify appropriate
2 City representatives via email of submittal posting.
3 3) Hard Copies
4 a) 1 copy for all submittals submitted to the Project Representative
5 b. Hard Copy Distribution (if required in lieu of electronic distribution)
6 1) Tests performed by City
7 a) Distribute 1 hard copy to the Contractor
8 2) Tests performed by the Contractor
9 a) Distribute 3 hard copies to City's Project Representative
10 4. Provide City's Project Representative with trip tickets for each delivered load of
11 Concrete or Lime material including the following information:
12 a. Name of pit
13 b. Date of delivery
14 c. Material delivered
15 B. Inspection
16 1. Inspection or lack of inspection does not relieve the Contractor from obligation to
17 perform work in accordance with the Contract Documents.
18 1.5 SUBMITTALS [NOT USED]
19 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
20
1.7
CLOSEOUT SUBMITTALS [NOT USED]
21
1.8
MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
22
1.9
QUALITY ASSURANCE [NOT USED]
23
1.10
DELIVERY, STORAGE, AND HANDLING [NOT USED]
24
1.11
FIELD [SITE] CONDITIONS [NOT USED]
25
1.12
WARRANTY [NOT USED]
26 PART 2 - PRODUCTS [NOT USED]
27 PART 3 - EXECUTION [NOT USED]
28
29
30
DATE NAME
END OF SECTION
Revision Log
SUMMARY OF CHANGE
03/20/2020 D.V. Magana Removed reference to Buzzsaw and noted that electronic submittals be uploaded
through the City's document management system.
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised March 20, 2020
01 50 00 - 1
DAP TEMPORARY FACILITIES AND CONTROLS
Page 1 of 4
1 SECTION 0150 00
2 TEMPORARY FACILITIES AND CONTROLS
3 PART1- GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. Provide temporary facilities and controls needed for the Work including, but not
7 necessarily limited to:
8 a. Temporary utilities
9 b. Sanitary facilities
10 c. Storage Sheds and Buildings
11 d. Dust control
12 e. Temporary fencing of the construction site
13 B. Deviations from this City of Fort Worth Standard Specification
14 1. None.
15 C. Related Specification Sections include, but are not necessarily limited to:
16 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
17 2. Division 1 — General Requirements
18 1.2 PRICE AND PAYMENT PROCEDURES
19 A. Measurement and Payment
20 1. Work associated with this Item is considered subsidiary to the various Items bid.
21 No separate payment will be allowed for this Item.
22 1.3 REFERENCES [NOT USED]
23 1.4 ADMINISTRATIVE REQUIREMENTS
24 A. Temporary Utilities
25 1. Obtaining Temporary Service
26 a. Make arrangements with utility service companies for temporary services.
27 b. Abide by rules and regulations of utility service companies or authorities
28 having jurisdiction.
29 c. Be responsible for utility service costs until Work is approved for Final
30 Acceptance.
31 1) Included are fuel, power, light, heat and other utility services necessary for
32 execution, completion, testing and initial operation of Work.
33 2. Water
34 a. Contractor to provide water required for and in connection with Work to be
35 performed and for specified tests of piping, equipment, devices or other use as
36 required for the completion of the Work.
37 b. Provide and maintain adequate supply of potable water for domestic
38 consumption by Contractor personnel and City's Project Representatives.
39 c. Coordination
40 1) Contact City 1 week before water for construction is desired
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised JULY 1, 2011
015000-2
DAP TEMPORARY FACILITIES AND CONTROLS
Page 2 of 4
1
d. Contractor Payment for Construction Water
2
1) Obtain construction water meter from City for payment as billed by City's
3
established rates.
4
3.
Electricity and Lighting
5
a. Provide and pay for electric powered service as required for Work, including
6
testing of Work.
7
1) Provide power for lighting, operation of equipment, or other use.
8
b. Electric power service includes temporary power service or generator to
9
maintain operations during scheduled shutdown.
10
4.
Telephone
11
a. Provide emergency telephone service at Site for use by Contractor personnel
12
and others performing work or furnishing services at Site.
13
5.
Temporary Heat and Ventilation
14
a. Provide temporary heat as necessary for protection or completion of Work.
15
b. Provide temporary heat and ventilation to assure safe working conditions.
16
B. Sanitary Facilities
17
1.
Provide and maintain sanitary facilities for persons on Site.
18
a. Comply with regulations of State and local departments of health.
19
2.
Enforce use of sanitary facilities by construction personnel at job site.
20
a. Enclose and anchor sanitary facilities.
21
b. No discharge will be allowed from these facilities.
22
c. Collect and store sewage and waste so as not to cause nuisance or health
23
problem.
24
d. Haul sewage and waste off -site at no less than weekly intervals and properly
25
dispose in accordance with applicable regulation.
26
3.
Locate facilities near Work Site and keep clean and maintained throughout Project.
27
4.
Remove facilities at completion of Project
28
C. Storage Sheds and Buildings
29
1.
Provide adequately ventilated, watertight, weatherproof storage facilities with floor
30
above ground level for materials and equipment susceptible to weather damage.
31
2.
Storage of materials not susceptible to weather damage may be on blocks off
32
ground.
33
3.
Store materials in a neat and orderly manner.
34
a. Place materials and equipment to permit easy access for identification,
35
inspection and inventory.
36
4.
Equip building with lockable doors and lighting, and provide electrical service for
37
equipment space heaters and heating or ventilation as necessary to provide storage
38
environments acceptable to specified manufacturers.
39
5.
Fill and grade site for temporary structures to provide drainage away from
40
temporary and existing buildings.
41
6.
Remove building from site prior to Final Acceptance.
42
D. Temporary Fencing
43
1.
Provide and maintain for the duration or construction when required in contract
44
documents
45
E. Dust
Control
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised JULY 1, 2011
01 50 00 - 3
DAP TEMPORARY FACILITIES AND CONTROLS
Page 3 of 4
1 1. Contractor is responsible for maintaining dust control through the duration of the
2 project.
3 a. Contractor remains on -call at all times
4 b. Must respond in a timely manner
5 F. Temporary Protection of Construction
6 1. Contractor or subcontractors are responsible for protecting Work from damage due
7 to weather.
8 1.5 SUBMITTALS [NOT USED]
9 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
10 1.7 CLOSEOUT SUBMITTALS [NOT USED]
11 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
12 1.9 QUALITY ASSURANCE [NOT USED]
13 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
14 1.11 FIELD [SITE] CONDITIONS [NOT USED]
15 1.12 WARRANTY [NOT USED]
16 PART 2 - PRODUCTS [NOT USED]
17 PART 3 - EXECUTION [NOT USED]
18 3.1 INSTALLERS [NOT USED]
19 3.2 EXAMINATION [NOT USED]
20 3.3 PREPARATION [NOT USED]
21 3.4 INSTALLATION
22 A. Temporary Facilities
23 1. Maintain all temporary facilities for duration of construction activities as needed.
24 3.5 [REPAIR] / [RESTORATION]
25 3.6 RE -INSTALLATION
26 3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED]
27 3.8 SYSTEM STARTUP [NOT USED]
28 3.9 ADJUSTING [NOT USED]
29 3.10 CLEANING [NOT USED]
30 3.11 CLOSEOUT ACTIVITIES
31 A. Temporary Facilities
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised JULY 1, 2011
015000-4
DAP TEMPORARY FACILITIES AND CONTROLS
Page 4 of 4
1 1. Remove all temporary facilities and restore area after completion of the Work, to a
2 condition equal to or better than prior to start of Work.
3 3.12 PROTECTION [NOT USED]
4 3.13 MAINTENANCE [NOT USED]
5 3.14 ATTACHMENTS [NOT USED]
6 END OF SECTION
7
8
Revision Log
I DATE NAME SUMMARY OF CHANGE
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised JULY 1, 2011
015526-1
DAP STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL
Page 1 of 3
1 SECTION 0155 26
2 STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL
3 PART1- GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. Administrative procedures for:
7 a. Street Use Permit
8 b. Modification of approved traffic control
9 c. Removal of Street Signs
10 B. Deviations from this City of Fort Worth Standard Specification
11 1. None.
12 C. Related Specification Sections include, but are not necessarily limited to:
13 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
14 2. Division 1 — General Requirements
15 3. Section 34 71 13 — Traffic Control
16 1.2 PRICE AND PAYMENT PROCEDURES
17 A. Measurement and Payment
18 1. Work associated with this Item is considered subsidiary to the various Items bid.
19 No separate payment will be allowed for this Item.
20 1.3 REFERENCES
21 A. Reference Standards
22 1. Reference standards cited in this specification refer to the current reference standard
23 published at the time of the latest revision date logged at the end of this
24 specification, unless a date is specifically cited.
25 2. Texas Manual on Uniform Traffic Control Devices (TMUTCD).
26 1.4 ADMINISTRATIVE REQUIREMENTS
27 A. Traffic Control
28 1. General
29 a. When traffic control plans are included in the Drawings, provide Traffic
30 Control in accordance with Drawings and Section 34 71 13.
31 b. When traffic control plans are not included in the Drawings, prepare traffic
32 control plans in accordance with Section 34 71 13 and submit to City for
33 review.
34 1) Allow minimum 10 working days for review of proposed Traffic Control.
35 B. Street Use Permit
36 1. Prior to installation of Traffic Control, a City Street Use Permit is required.
37 a. To obtain Street Use Permit, submit Traffic Control Plans to City
38 Transportation and Public Works Department.
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised July 1, 2011
015526-2
DAP STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL
Page 2 of 3
1 1) Allow a minimum of 5 working days for permit review.
2 2) Contractor's responsibility to coordinate review of Traffic Control plans for
3 Street Use Permit, such that construction is not delayed.
4 C. Modification to Approved Traffic Control
5 1. Prior to installation traffic control:
6 a. Submit revised traffic control plans to City Department Transportation and
7 Public Works Department.
8 1) Revise Traffic Control plans in accordance with Section 34 71 13.
9 2) Allow minimum 5 working days for review of revised Traffic Control.
10 3) It is the Contractor's responsibility to coordinate review of Traffic Control
11 plans for Street Use Permit, such that construction is not delayed.
12 D. Removal of Street Sign
13 1. If it is determined that a street sign must be removed for construction, then contact
14 City Transportation and Public Works Department, Signs and Markings Division to
15 remove the sign.
16 E. Temporary Signage
17 1. In the case of regulatory signs, replace permanent sign with temporary sign meeting
18 requirements of the latest edition of the Texas Manual on Uniform Traffic Control
19 Devices (MUTCD).
20 2. Install temporary sign before the removal of permanent sign.
21 3. When construction is complete, to the extent that the permanent sign can be
22 reinstalled, contact the City Transportation and Public Works Department, Signs
23 and Markings Division, to reinstall the permanent sign.
24 F. Traffic Control Standards
25 1. Traffic Control Standards can be found on the City's Buzzsaw website.
26 1.5 SUBMITTALS [NOT USED]
27 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
28 1.7 CLOSEOUT SUBMITTALS [NOT USED]
29 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
30 1.9 QUALITY ASSURANCE [NOT USED]
31 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
32 1.11 FIELD [SITE] CONDITIONS [NOT USED]
33 1.12 WARRANTY [NOT USED]
34 PART 2 - PRODUCTS [NOT USED]
35 PART 3 - EXECUTION [NOT USED]
36 END OF SECTION
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised July 1, 2011
015526-3
DAP STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL
Page 3 of 3
Revision Log
DATE NAME SUMMARY OF CHANGE
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised July 1, 2011
015713-1
DAP STORM WATER POLLUTION PREVENTION
Page 1 of 3
1 SECTION 01 5713
2 STORM WATER POLLUTION PREVENTION
3 PART1- GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. Procedures for Storm Water Pollution Prevention Plans
7 B. Deviations from this City of Fort Worth Standard Specification
8 1. None.
9 C. Related Specification Sections include, but are not necessarily limited to:
10 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the
11 Contract
12 2. Division 1 — General Requirements
13 3. Section 3125 00 — Erosion and Sediment Control
14 1.2 PRICE AND PAYMENT PROCEDURES
15 A. Measurement and Payment
16 1. Construction Activities resulting in less than 1 acre of disturbance
17 a. Work associated with this Item is considered subsidiary to the various Items
18 bid. No separate payment will be allowed for this Item.
19 2. Construction Activities resulting in greater than 1 acre of disturbance
20 a. Measurement and Payment shall be in accordance with Section 3125 00.
21 1.3 REFERENCES
22 A. Abbreviations and Acronyms
23 1. Notice of Intent: NOI
24 2. Notice of Termination: NOT
25 3. Storm Water Pollution Prevention Plan: SWPPP
26 4. Texas Commission on Environmental Quality: TCEQ
27 5. Notice of Change: NOC
28 A. Reference Standards
29 1. Reference standards cited in this Specification refer to the current reference
30 standard published at the time of the latest revision date logged at the end of this
31 Specification, unless a date is specifically cited.
32 2. Integrated Storm Management (iSWM) Technical Manual for Construction
33 Controls
34 1.4 ADMINISTRATIVE REQUIREMENTS
35 A. General
36 1. Contractor is responsible for resolution and payment of any fines issued associated
37 with compliance to Stormwater Pollution Prevention Plan.
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised July 1, 2011
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
015713-2
DAP STORM WATER POLLUTION PREVENTION
Page 2 of 3
B. Construction Activities resulting in:
1. Less than 1 acre of disturbance
a. Provide erosion and sediment control in accordance with Section 3125 00 and
Drawings.
2. 1 to less than 5 acres of disturbance
a. Texas Pollutant Discharge Elimination System (TPDES) General Construction
Permit is required
b. Complete SWPPP in accordance with TCEQ requirements
1) TCEQ Small Construction Site Notice Required under general permit
TXR150000
a) Sign and post at job site
b) Prior to Preconstruction Meeting, send 1 copy to City Department of
Transportation and Public Works, Environmental Division, (817) 392-
6088.
2) Provide erosion and sediment control in accordance with:
a) Section 3125 00
b) The Drawings
c) TXR150000 General Permit
d) SWPPP
e) TCEQ requirements
3. 5 acres or more of Disturbance
a. Texas Pollutant Discharge Elimination System (TPDES) General Construction
Permit is required
b. Complete SWPPP in accordance with TCEQ requirements
1) Prepare a TCEQ NOI form and submit to TCEQ along with required fee
a) Sign and post at job site
b) Send copy to City Department of Transportation and Public Works,
Environmental Division, (817) 392-6088.
2) TCEQ Notice of Change required if making changes or updates to NOI
3) Provide erosion and sediment control in accordance with:
a) Section 3125 00
b) The Drawings
c) TXR150000 General Permit
d) SWPPP
e) TCEQ requirements
4) Once the project has been completed and all the closeout requirements of
TCEQ have been met a TCEQ Notice of Termination can be submitted.
a) Send copy to City Department of Transportation and Public Works,
Environmental Division, (817) 392-6088.
40 1.5 SUBMITTALS
41
42
43
44
45
46
47
r&=Vff I ,
1. Submit in accordance with Section 0133 00, except as stated herein.
a. Prior to the Preconstruction Meeting, submit a draft copy of SWPPP to the City
as follows:
1) 1 copy to the City Project Manager
a) City Project Manager will forward to the City Department of
Transportation and Public Works, Environmental Division for review
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised July 1, 2011
01 57 13-3
DAP STORM WATER POLLUTION PREVENTION
Page 3 of 3
1
B. Modified SWPPP
2
1. If the SWPPP is revised during construction, resubmit modified SWPPP to the City
3
in accordance with Section 0133 00.
4
1.6
ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
5
1.7
CLOSEOUT SUBMITTALS [NOT USED]
6
1.8
MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
7
1.9
QUALITY ASSURANCE [NOT USED]
8
1.10
DELIVERY, STORAGE, AND HANDLING [NOT USED]
9
1.11
FIELD [SITE] CONDITIONS [NOT USED]
10
1.12
WARRANTY [NOT USED]
11 PART 2 - PRODUCTS [NOT USED]
12 PART 3 - EXECUTION [NOT USED]
13 END OF SECTION
14
15
Revision Log
I DATE NAME SUMMARY OF CHANGE
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised July 1, 2011
01 58 13-1
DAP TEMPORARY PROJECT SIGNAGE
Page 1 of 3
1 SECTION 01 5813
2 TEMPORARY PROJECT SIGNAGE
3 PART1- GENERAL
4 1.1 SUMMARY
5
A. Section Includes:
6
1. Temporary Project Signage Requirements
7
B. Deviations from this City of Fort Worth Standard Specification
8
1. None.
9
C. Related Specification Sections include, but are not necessarily limited to:
10
1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
11
2. Division 1 — General Requirements
12
1.2
PRICE AND PAYMENT PROCEDURES
13
A. Measurement and Payment
14
1. Work associated with this Item is considered subsidiary to the various Items bid.
15
No separate payment will be allowed for this Item.
16
1.3
REFERENCES [NOT USED]
17
1.4
ADMINISTRATIVE REQUIREMENTS [NOT USED]
18
1.5
SUBMITTALS [NOT USED]
19
1.6
ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
20
1.7
CLOSEOUT SUBMITTALS [NOT USED]
21
1.8
MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
22 1.9 QUALITY ASSURANCE [NOT USED]
23 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
24 1.11 FIELD [SITE] CONDITIONS [NOT USED]
25 1.12 WARRANTY [NOT USED]
26 PART 2 - PRODUCTS
27 2.1 OWNER -FURNISHED [OR] OWNER-SUPPLIEDPRODUCTS [NOT USED]
28 2.2 EQUIPMENT, PRODUCT TYPES, AND MATERIALS
29 A. Design Criteria
30 1. Provide free standing Project Designation Sign in accordance with City's Standard
31 Details for project signs.
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised April 7, 2014
01 58 13-2
DAP TEMPORARY PROJECT SIGNAGE
Page 2 of 3
1 B. Materials
2 1. Sign
3 a. Constructed of 3/4-inch fir plywood, grade A-C (exterior) or better
4 2.3 ACCESSORIES [NOT USED]
5 2.4 SOURCE QUALITY CONTROL [NOT USED]
6 PART 3 - EXECUTION
7 3.1 INSTALLERS [NOT USED]
8 3.2 EXAMINATION [NOT USED]
9 3.3 PREPARATION [NOT USED]
10 3.4 INSTALLATION
11
A. General
12
1. Provide vertical installation at extents of project.
13
2. Relocate sign as needed, upon request of the City.
14
B. Mounting options
15
a. Skids
16
b. Posts
17
c. Barricade
18
3.5
REPAIR / RESTORATION [NOT USED]
19
3.6
RE -INSTALLATION [NOT USED]
20
3.7
FIELD [OR] SITE QUALITY CONTROL [NOT USED]
21
3.8
SYSTEM STARTUP [NOT USED]
22
3.9
ADJUSTING [NOT USED]
23
3.10
CLEANING [NOT USED]
24
3.11
CLOSEOUT ACTIVITIES [NOT USED]
25
3.12
PROTECTION [NOT USED]
26
3.13
MAINTENANCE
27 A. General
28 1. Maintenance will include painting and repairs as needed or directed by the City.
29 3.14 ATTACHMENTS [NOT USED]
30 END OF SECTION
31
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised April 7, 2014
DATE
4/7/2014
01 58 13-3
DAP TEMPORARY PROJECT SIGNAGE
Page 3 of 3
Revision Log
NAME SUMMARY OF CHANGE
M. Domenech Revised for DAP application
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised April 7, 2014
1
2
3 PART1- GENERAL
SECTION 0160 00
PRODUCT REQUIREMENTS
01 60 00 - 1
DAP PRODUCT REQUIREMENTS
Page 1 of 2
4 1.1 SUMMARY
5 A. Section Includes:
6 1. References for Product Requirements and City Standard Products List
7 B. Deviations from this City of Fort Worth Standard Specification
8 1. None.
9 C. Related Specification Sections include, but are not necessarily limited to:
10 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
11 2. Division 1 — General Requirements
12 1.2 PRICE AND PAYMENT PROCEDURES [NOT USED]
13 1.3 REFERENCES [NOT USED]
14 1.4 ADMINISTRATIVE REQUIREMENTS
15 A list of City approved products for use is available through the City's website at:
16 httDs://anus.fortworthtexas.2ov/ProiectResources/ and following the directory
17 path: 02 — Construcction Documents\Standard Products List
18 A. Only products specifically included on City's Standard Product List in these Contract
19 Documents shall be allowed for use on the Project.
20 1. Any subsequently approved products will only be allowed for use upon specific
21 approval by the City.
22 B. Any specific product requirements in the Contract Documents supersede similar
23 products included on the City's Standard Product List.
24 1. The City reserves the right to not allow products to be used for certain projects even
25 though the product is listed on the City's Standard Product List.
26 C. Although a specific product is included on City's Standard Product List, not all
27 products from that manufacturer are approved for use, including but not limited to, that
28 manufacturer's standard product.
29 D. See Section 0133 00 for submittal requirements of Product Data included on City's
30 Standard Product List.
31 1.5 SUBMITTALS [NOT USED]
32 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
33 1.7 CLOSEOUT SUBMITTALS [NOT USED]
34 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
35 1.9 QUALITY ASSURANCE [NOT USED]
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. — 103849
Revised April 7, 2014
01 60 00 - 2
DAP PRODUCT REQUIREMENTS
Page 2 of 2
1 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
2 1.11 FIELD [SITE] CONDITIONS [NOT USED]
3 1.12 WARRANTY [NOT USED]
4 PART 2 - PRODUCTS [NOT USED]
5 PART 3 - EXECUTION [NOT USED]
6 END OF SECTION
7
Revision Log
DATE NAME SUMMARY OF CHANGE
10/12/12 D. Johnson Modified Location of City's Standard Product List
4/7/2014 M.Domenech Revised for DAP application
03/20/2020 D.V. Magana Removed reference to Buzzsaw and noted that the City approved products list is
accessible through the City's website.
8
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. — 103849
Revised April 7, 2014
01 66 00 - 1
DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS
Page 1 of 4
1 SECTION 0166 00
2 PRODUCT STORAGE AND HANDLING REQUIREMENTS
3 PART1- GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. Scheduling of product delivery
7 2. Packaging of products for delivery
8 3. Protection of products against damage from:
9 a. Handling
10 b. Exposure to elements or harsh environments
11 B. Deviations from this City of Fort Worth Standard Specification
12 1. None.
13 C. Related Specification Sections include, but are not necessarily limited to:
14 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
15 2. Division 1 — General Requirements
16 1.2 PRICE AND PAYMENT PROCEDURES
17 A. Measurement and Payment
18 1. Work associated with this Item is considered subsidiary to the various Items bid.
19 No separate payment will be allowed for this Item.
20 1.3 REFERENCES [NOT USED]
21 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED]
22 1.5 SUBMITTALS [NOT USED]
23 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
24 1.7 CLOSEOUT SUBMITTALS [NOT USED]
25 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
26 1.9 QUALITY ASSURANCE [NOT USED]
27 1.10 DELIVERY AND HANDLING
28 A. Delivery Requirements
29 1. Schedule delivery of products or equipment as required to allow timely installation
30 and to avoid prolonged storage.
31 2. Provide appropriate personnel and equipment to receive deliveries.
32 3. Delivery trucks will not be permitted to wait extended periods of time on the Site
33 for personnel or equipment to receive the delivery.
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised April 7, 2014
01 66 00 - 2
DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS
Page 2 of 4
1
4.
Deliver products or equipment in manufacturer's original unbroken cartons or other
2
containers designed and constructed to protect the contents from physical or
3
environmental damage.
4
5.
Clearly and fully mark and identify as to manufacturer, item and installation
5
location.
6
6.
Provide manufacturer's instructions for storage and handling.
7
B. Handling
Requirements
8
1.
Handle products or equipment in accordance with these Contract Documents and
9
manufacturer's recommendations and instructions.
10
C. Storage Requirements
11
1.
Store materials in accordance with manufacturer's recommendations and
12
requirements of these Specifications.
13
2.
Make necessary provisions for safe storage of materials and equipment.
14
a. Place loose soil materials and materials to be incorporated into Work to prevent
15
damage to any part of Work or existing facilities and to maintain free access at
16
all times to all parts of Work and to utility service company installations in
17
vicinity of Work.
18
3.
Keep materials and equipment neatly and compactly stored in locations that will
19
cause minimum inconvenience to other contractors, public travel, adjoining owners,
20
tenants and occupants.
21
a. Arrange storage to provide easy access for inspection.
22
4.
Restrict storage to areas available on construction site for storage of material and
23
equipment as shown on Drawings, or approved by City's Project Representative.
24
5.
Provide off -site storage and protection when on -site storage is not adequate.
25
a. Provide addresses of and access to off -site storage locations for inspection by
26
City's Project Representative.
27
6.
Do not use lawns, grass plots or other private property for storage purposes without
28
written permission of owner or other person in possession or control of premises.
29
7.
Store in manufacturers' unopened containers.
30
8.
Neatly, safely and compactly stack materials delivered and stored along line of
31
Work to avoid inconvenience and damage to property owners and general public
32
and maintain at least 3 feet from fire hydrant.
33
9.
Keep public and private driveways and street crossings open.
34
10. Repair or replace damaged lawns, sidewalks, streets or other improvements to
35
satisfaction of City's Project Representative.
36
a. Total length which materials may be distributed along route of construction at
37
one time is 1,000 linear feet, unless otherwise approved in writing by City's
38
Project Representative.
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised April 7, 2014
01 66 00 - 3
DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS
Page 3 of 4
1 1.11 FIELD [SITE] CONDITIONS [NOT USED]
2 1.12 WARRANTY [NOT USED]
3 PART 2 - PRODUCTS [NOT USED]
4 PART 3 - EXECUTION
5 3.1
INSTALLERS [NOT USED]
6 3.2
EXAMINATION [NOT USED]
7 3.3
PREPARATION [NOT USED]
8 3.4
ERECTION [NOT USED]
9 3.5
REPAIR / RESTORATION [NOT USED]
10 3.6
RE -INSTALLATION [NOT USED]
11 3.7
FIELD [OR] SITE QUALITY CONTROL
12 A. Tests and Inspections
13 1. Inspect all products or equipment delivered to the site prior to unloading.
14 B. Non -Conforming Work
15 1. Reject all products or equipment that are damaged, used or in any other way
16 unsatisfactory for use on the project.
17 3.8 SYSTEM STARTUP [NOT USED]
18 3.9 ADJUSTING [NOT USED]
19 3.10 CLEANING [NOT USED]
20 3.11 CLOSEOUT ACTIVITIES [NOT USED]
21 3.12 PROTECTION
22 A. Protect all products or equipment in accordance with manufacturer's written directions.
23 B. Store products or equipment in location to avoid physical damage to items while in
24 storage.
25 C. Protect equipment from exposure to elements and keep thoroughly dry if required by
26 the manufacturer.
27 3.13 MAINTENANCE [NOT USED]
28 3.14 ATTACHMENTS [NOT USED]
29 END OF SECTION
30
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised April 7, 2014
01 66 00 - 4
DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS
Page 4 of 4
Revision Log
DATE NAME SUMMARY OF CHANGE
4/7/2014 M.Domenech Revised for DAP application
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised April 7, 2014
2
3 PART1- GENERAL
4 1.1 SUMMARY
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
01 70 00 - 1
DAP MOBILIZATION AND REMOBILIZATION
Page 1 of 4
SECTION 0170 00
MOBILIZATION AND REMOBILIZATION
A. Section Includes:
1. Mobilization and Demobilization
a. Mobilization
1) Transportation of Contractor's personnel, equipment, and operating supplies
to the Site
2) Establishment of necessary general facilities for the Contractor's operation
at the Site
3) Premiums paid for performance and payment bonds
4) Transportation of Contractor's personnel, equipment, and operating supplies
to another location within the designated Site
5) Relocation of necessary general facilities for the Contractor's operation
from 1 location to another location on the Site.
b. Demobilization
1) Transportation of Contractor's personnel, equipment, and operating supplies
away from the Site including disassembly
2) Site Clean-up
3) Removal of all buildings and/or other facilities assembled at the Site for this
Contract
c. Mobilization and Demobilization do not include activities for specific items of
work that are for which payment is provided elsewhere in the contract.
2. Remobilization
a. Remobilization for Suspension of Work specifically required in the Contract
Documents or as required by City includes:
1) Demobilization
a) Transportation of Contractor's personnel, equipment, and operating
supplies from the Site including disassembly or temporarily securing
equipment, supplies, and other facilities as designated by the Contract
Documents necessary to suspend the Work.
b) Site Clean-up as designated in the Contract Documents
2) Remobilization
a) Transportation of Contractor's personnel, equipment, and operating
supplies to the Site necessary to resume the Work.
b) Establishment of necessary general facilities for the Contractor's
operation at the Site necessary to resume the Work.
3) No Payments will be made for:
a) Mobilization and Demobilization from one location to another on the
Site in the normal progress of performing the Work.
b) Stand-by or idle time
c) Lost profits
3. Mobilizations and Demobilization for Miscellaneous Projects
a. Mobilization and Demobilization
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised April 7, 2014
01 70 00 - 2
DAP MOBILIZATION AND REMOBILIZATION
Page 2 of 4
1 1) Mobilization shall consist of the activities and cost on a Work Order basis
2 necessary for:
3 a) Transportation of Contractor's personnel, equipment, and operating
4 supplies to the Site for the issued Work Order.
5 b) Establishment of necessary general facilities for the Contractor's
6 operation at the Site for the issued Work Order
7 2) Demobilization shall consist of the activities and cost necessary for:
8 a) Transportation of Contractor's personnel, equipment, and operating
9 supplies from the Site including disassembly for each issued Work
10 Order
11 b) Site Clean-up for each issued Work Order
12 c) Removal of all buildings or other facilities assembled at the Site for
13 each Work Oder
14 b. Mobilization and Demobilization do not include activities for specific items of
15 work for which payment is provided elsewhere in the contract.
16 4. Emergency Mobilizations and Demobilization for Miscellaneous Projects
17 a. A Mobilization for Miscellaneous Projects when directed by the City and the
18 mobilization occurs within 24 hours of the issuance of the Work Order.
19 B. Deviations from this City of Fort Worth Standard Specification
20 1. None.
21 C. Related Specification Sections include, but are not necessarily limited to:
22 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
23 2. Division 1 — General Requirements
24 1.2 PRICE AND PAYMENT PROCEDURES
25 A. Measurement and Payment
26 1. Mobilization and Demobilization
27 a. Measure
28 1) This Item is considered subsidiary to the various Items bid.
29 b. Payment
30 1) The work performed and materials furnished in accordance with this Item
31 are subsidiary to the various Items bid and no other compensation will be
32 allowed.
33 2. Remobilization for suspension of Work as specifically required in the Contract
34 Documents
35 a. Measurement
36 1) Measurement for this Item shall be per each remobilization performed.
37 b. Payment
38 1) The work performed and materials furnished in accordance with this Item
39 and measured as provided under "Measurement" will be paid for at the unit
40 price per each "Specified Remobilization" in accordance with Contract
41 Documents.
42 c. The price shall include:
43 1) Demobilization as described in Section 1.1.A.2.a.1)
44 2) Remobilization as described in Section 1.1.A.2.a.2)
45 d. No payments will be made for standby, idle time, or lost profits associated this
46 Item.
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised April 7, 2014
01 70 00 - 3
DAP MOBILIZATION AND REMOBILIZATION
Page 3 of 4
1 3. Remobilization for suspension of Work as required by City
2 a. Measurement and Payment
3 1) This shall be submitted as a Contract Claim in accordance with Article 10
4 of Section 00 72 00.
5 2) No payments will be made for standby, idle time, or lost profits associated
6 with this Item.
7 4. Mobilizations and Demobilizations for Miscellaneous Projects
8 a. Measurement
9 1) Measurement for this Item shall be for each Mobilization and
10 Demobilization required by the Contract Documents
11 b. Payment
12 1) The Work performed and materials furnished in accordance with this Item
13 and measured as provided under "Measurement' will be paid for at the unit
14 price per each "Work Order Mobilization" in accordance with Contract
15 Documents. Demobilization shall be considered subsidiary to mobilization
16 and shall not be paid for separately.
17 c. The price shall include:
18 1) Mobilization as described in Section 1.1.A.3.a.1)
19 2) Demobilization as described in Section 1.1.A.3.a.2)
20 d. No payments will be made for standby, idle time, or lost profits associated this
21 Item.
22 5. Emergency Mobilizations and Demobilizations for Miscellaneous Projects
23 a. Measurement
24 1) Measurement for this Item shall be for each Mobilization and
25 Demobilization required by the Contract Documents
26 b. Payment
27 1) The Work performed and materials furnished in accordance with this Item
28 and measured as provided under "Measurement' will be paid for at the unit
29 price per each "Work Order Emergency Mobilization" in accordance with
30 Contract Documents. Demobilization shall be considered subsidiary to
31 mobilization and shall not be paid for separately.
32 c. The price shall include
33 1) Mobilization as described in Section 1.1.A.4.a)
34 2) Demobilization as described in Section 1.1.A.3.a.2)
35 d. No payments will be made for standby, idle time, or lost profits associated this
36 Item.
37 1.3 REFERENCES [NOT USED]
38 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED]
39 1.5 SUBMITTALS [NOT USED]
40 1.6 INFORMATIONAL SUBMITTALS [NOT USED]
41 1.7 CLOSEOUT SUBMITTALS [NOT USED]
42 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
43 1.9 QUALITY ASSURANCE [NOT USED]
44 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised April 7, 2014
01 70 00 - 4
DAP MOBILIZATION AND REMOBILIZATION
Page 4 of 4
1 1.11 FIELD [SITE] CONDITIONS [NOT USED]
2 1.12 WARRANTY [NOT USED]
3 PART 2 - PRODUCTS [NOT USED]
4 PART 3 - EXECUTION [NOT USED]
5 END OF SECTION
6
Revision Log
DATE NAME SUMMARY OF CHANGE
4/7/2014 M.Domcncch Revised for DAP application
7
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised April 7, 2014
017123-1
CONSTRUCTION STAKING AND SURVEY
Page 1 of 7
1 SECTION 01 71 23
2 CONSTRUCTION STAKING AND SURVEY
3 PART1- GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. Requirements for construction staking and construction survey
7 B. Deviations from this City of Fort Worth Standard Specification
8 1. See Changes (Highlighted in Yellow).
9 C. Related Specification Sections include, but are not necessarily limited to:
10 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
11 2. Division 1 — General Requirements
12 1.2 PRICE AND PAYMENT PROCEDURES
13 A. Measurement and Payment
14 1. Construction Staking
15 a. Measurement
16 1) This Item is considered subsidiary to the various Items bid.
17 b. Payment
18 1) The work performed and the materials furnished in accordance with this
19 Item are subsidiary to the various Items bid and no other compensation will
20 be allowed.
21 2. Construction Survey
22 a. Measurement
23 1) This Item is considered subsidiary to the various Items bid.
24 b. Payment
25 1) The work performed and the materials furnished in accordance with this
26 Item are subsidiary to the various Items bid and no other compensation will be
27 allowed.
28 3. As -Built Survey
29 a. Measurement
30 1) This Item is considered subsidiary to the various Items bid.
31 b. Payment
32 1) The work performed and the materials furnished in accordance with this
33 Item are subsidiary to the various Items bid and no other compensation will be
34 allowed.
35 1.3 REFERENCES
36 A. Definitions
37 1. Construction Survev - The survey measurements made prior to or while
38 construction is in progress to control elevation, horizontal position, dimensions and
39 configuration of structures/improvements included in the Project Drawings.
CITY OF FORT WORTH Trinity Lakes Mixed Use South Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project Number 103849
Revised February 14, 2018
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
017123-2
CONSTRUCTION STAKING AND SURVEY
Page 2 of 7
2. As -built Survev —The measurements made after the construction of the
improvement features are complete to provide position coordinates for the features
of a project.
3. Construction Staking — The placement of stakes and markings to provide offsets
and elevations to cut and fill in order to locate on the ground the designed
structures/improvements included in the Project Drawings. Construction staking
shall include staking easements and/or right of way if indicated on the plans.
4. Survev "Field Checks" — Measurements made after construction staking is
completed and before construction work begins to ensure that structures marked on
the ground are accurately located per Project Drawings.
B. Technical References
1. City of Fort Worth — Construction Staking Standards (available on City's Buzzsaw
website) — 01 71 23.16.01— Attachment A —Survey Staking Standards
2. City of Fort Worth - Standard Survey Data Collector Library (fxl) files (available
on City's Buzzsaw website).
3. Texas Department of Transportation (TxDOT) Survey Manual, latest revision
4. Texas Society of Professional Land Surveyors (TSPS), Manual of Practice for Land
Surveying in the State of Texas, Category 5
20 1.4 ADMINISTRATIVE REQUIREMENTS
21 A. The Contractor's selection of a surveyor must comply with Texas Government
22 Code 2254 (qualifications based selection) for this project.
23 1.5 SUBMITTALS
24 A. Submittals, if required, shall be in accordance with Section 0133 00.
25 B. All submittals shall be received and reviewed by the City prior to delivery of work.
26 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS
27 A. Field Quality Control Submittals
28 1. Documentation verifying accuracy of field engineering work, including coordinate
29 conversions if plans do not indicate grid or ground coordinates.
30 2. Submit "Cut -Sheets" conforming to the standard template provided by the City
31 (refer to 01 71 23.16.01 — Attachment A — Survey Staking Standards).
32 1.7 CLOSEOUT SUBMITTALS
33 B. As -built Redline Drawing Submittal
34 1. Submit As -Built Survey Redline Drawings documenting the locations/elevations of
35 constructed improvements signed and sealed by Registered Professional Land
36 Surveyor (RPLS) responsible for the work (refer to 01 71 23.16.01 — Attachment A
37 — Survey Staking Standards) .
38 2. Contractor shall submit the proposed as -built and completed redline drawing
39 submittal one (1) week prior to scheduling the project final inspection for City
40 review and comment. Revisions, if necessary, shall be made to the as -built redline
41 drawings and resubmitted to the City prior to scheduling the construction final
42 inspection.
CITY OF FORT WORTH Trinity Lakes Mixed Use South Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project Number 103849
Revised February 14, 2018
017123-3
CONSTRUCTION STAKING AND SURVEY
Page 3 of 7
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
2 1.9 QUALITY ASSURANCE
3 A. Construction Staking
4 1. Construction staking will be performed by the Contractor.
5 2. Coordination
6 a. Contact City and Developer's Project Representative at least one week in
7 advance notifying the City of when Construction Staking is scheduled.
8 b. It is the Contractor's responsibility to coordinate staking such that
9 construction activities are not delayed or negatively impacted.
10 3. General
11 a. Contractor is responsible for preserving and maintaining stakes. If
12 Developer's Project Representative is required to re -stake for any reason, the
13 Contractor will be responsible for costs to perform staking. If in the opinion of
14 the City, a sufficient number of stakes or markings have been lost, destroyed
15 disturbed or omitted that the contracted Work cannot take place then the
16 Contractor will be required to stake or re -stake the deficient areas.
17 B. Construction Survey
18 1. Construction Survey will be performed by the Contractor.
19 2. Coordination
20 a. Contractor to verify that horizontal and vertical control data established in the
21 design survey and required for construction survey is available and in place.
22 3. General
23 a. Construction survey will be performed in order to construct the work shown
24 on the Construction Drawings and specified in the Contract Documents.
25 b. For construction methods other than open cut, the Contractor shall perform
26 construction survey and verify control data including, but not limited to, the
27 following:
28 1) Verification that established benchmarks and control are accurate.
29 2) Use of Benchmarks to furnish and maintain all reference lines and grades
30 for tunneling.
31 3) Use of line and grades to establish the location of the pipe.
32 4) Submit to the City copies of field notes used to establish all lines and
33 grades, if requested, and allow the City to check guidance system setup prior
34 to beginning each tunneling drive.
35 5) Provide access for the City, if requested, to verify the guidance system and
36 the line and grade of the carrier pipe.
37 6) The Contractor remains fully responsible for the accuracy of the work and
38 correction of it, as required.
39 7) Monitor line and grade continuously during construction.
40 8) Record deviation with respect to design line and grade once at each pipe
41 joint and submit daily records to the City.
42 9) If the installation does not meet the specified tolerances (as outlined in
43 Sections 33 05 23 and/or 33 05 24), immediately notify the City and correct
44 the installation in accordance with the Contract Documents.
45 C. As -Built Survey
46 1. Required As -Built Survey will be performed by the Contractor.
CITY OF FORT WORTH Trinity Lakes Mixed Use South Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project Number 103849
Revised February 14, 2018
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
01 71 23 - 4
CONSTRUCTION STAKING AND SURVEY
Page 4 of 7
2. Coordination
a. Contractor is to coordinate with City to confirm which features require as -
built surveying.
b. It is the Contractor's responsibility to coordinate the as -built survey and
required measurements for items that are to be buried such that construction
activities are not delayed or negatively impacted.
c. For sewer mains and water mains 12" and under in diameter, it is acceptable
to physically measure depth and mark the location during the progress of
construction and take as -built survey after the facility has been buried. The
Contractor is responsible for the quality control needed to ensure accuracy.
3. General
a. The Contractor shall provide as -built survey including the elevation and
location (and provide written documentation to the City) of construction
features during the progress of the construction including the following:
1) Water Lines
a) Top of pipe elevations and coordinates for waterlines at the following
locations:
(1) Minimum every 25O linear feet, including
(2) Horizontal and vertical points of inflection, curvature,
etc.
(3) Fire line tee
(4) Plugs, stub -outs, dead-end lines
(5) Casing pipe (each end) and all buried fittings
2) Sanitary Sewer
a) Top of pipe elevations and coordinates for force mains and siphon
sanitary sewer lines (non -gravity facilities) at the following locations:
(1) Minimum every 25O linear feet and any buried fittings
(2) Horizontal and vertical points of inflection, curvature,
etc.
3) Stormwater — Not Applicable
b. The Contractor shall provide as -built survey including the elevation and
location (and provide written documentation to the City) of construction
features after the construction is completed including the following:
1) Manholes
a) Rim and flowline elevations and coordinates for each manhole
2) Water Lines
a) Cathodic protection test stations
b) Sampling stations
c) Meter boxes/vaults (All sizes)
d) Fire hydrants
e) Valves (gate, butterfly, etc.)
f) Air Release valves (Manhole rim and vent pipe)
g) Blow off valves (Manhole rim and valve lid)
h) Pressure plane valves
i) Underground Vaults
(1) Rim and flowline elevations and coordinates for each
Underground Vault.
3) Sanitary Sewer
a) Cleanouts
(1) Rim and flowline elevations and coordinates for each
CITY OF FORT WORTH Trinity Lakes Mixed Use South Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project Number 103849
Revised February 14, 2018
017123-5
CONSTRUCTION STAKING AND SURVEY
Page 5 of 7
1 b) Manholes and Junction Structures
2 (1) Rim and flowline elevations and coordinates for each
3 manhole and junction structure.
4 4) Stormwater — Not Applicable
5 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
6 1.11 FIELD [SITE] CONDITIONS [NOT USED]
7 1.12 WARRANTY
8 PART2- PRODUCTS
9
A. A construction survey will produce, but will not be limited to:
10
1.
Recovery of relevant control points, points of curvature and points of intersection.
11
2.
Establish temporary horizontal and vertical control elevations (benchmarks)
12
sufficiently permanent and located in a manner to be used throughout construction.
13
3.
The location of planned facilities, easements and improvements.
14
a. Establishing final line and grade stakes for piers, floors, grade beams, parking
15
areas, utilities, streets, highways, tunnels, and other construction.
16
b. A record of revisions or corrections noted in an orderly manner for reference.
17
c. A drawing, when required by the client, indicating the horizontal and vertical
18
location of facilities, easements and improvements, as built.
19
4.
Cut sheets shall be provided to the City inspector and Survey Superintendent for all
20
construction staking projects. These cut sheets shall be on the standard city template
21
which can be obtained from the Survey Superintendent (817-392-7925).
22
5.
Digital survey files in the following formats shall be acceptable:
23
a. AutoCAD (.dwg)
24
b. ESRI Shapefile (.shp)
25
c. CSV file (.csv), formatted with X and Y coordinates in separate columns (use
26
standard templates, if available)
27
6.
Survey files shall include vertical and horizontal data tied to original project
28
control and benchmarks, and shall include feature descriptions
29 PART 3 - EXECUTION
30 3.1 INSTALLERS
31 A. Tolerances:
32 1. The staked location of any improvement or facility should be as accurate as
33 practical and necessary. The degree of precision required is dependent on many
34 factors all of which must remain judgmental. The tolerances listed hereafter are
35 based on generalities and, under certain circumstances, shall yield to specific
36 requirements. The surveyor shall assess any situation by review of the overall plans
37 and through consultation with responsible parties as to the need for specific
38 tolerances.
39 a. Earthwork: Grades for earthwork or rough cut should not exceed 0.1 ft. vertical
40 tolerance. Horizontal alignment for earthwork and rough cut should not exceed
41 1.0 ft. tolerance.
CITY OF FORT WORTH Trinity Lakes Mixed Use South Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project Number 103849
Revised February 14, 2018
017123-6
CONSTRUCTION STAKING AND SURVEY
Page 6 of 7
1
b. Horizontal alignment on a structure shall be within .0.lft tolerance.
2
c. Paving or concrete for streets, curbs, gutters, parking areas, drives, alleys and
3
walkways shall be located within the confines of the site boundaries and,
4
occasionally, along a boundary or any other restrictive line. Away from any
5
restrictive line, these facilities should be staked with an accuracy producing no
6
more than 0.05ft. tolerance from their specified locations.
7
d. Underground and overhead utilities, such as sewers, gas, water, telephone and
8
electric lines, shall be located horizontally within their prescribed areas or
9
easements. Within assigned areas, these utilities should be staked with an
10
accuracy producing no more than 0.1 ft tolerance from a specified location.
11
e. The accuracy required for the vertical location of utilities varies widely. Many
12
underground utilities require only a minimum cover and a tolerance of 0.1 ft.
13
should be maintained. Underground and overhead utilities on planned profile,
14
but not depending on gravity flow for performance, should not exceed 0.1 ft.
15
tolerance.
16 B. Surveying instruments shall be kept in close adjustment according to manufacturer's
17 specifications or in compliance to standards. The City reserves the right to request a
18 calibration report at any time and recommends regular maintenance schedule be
19 performed by a certified technician every 6 months.
20 1. Field measurements of angles and distances shall be done in such fashion as to
21 satisfy the closures and tolerances expressed in Part 3.1.A.
22 2. Vertical locations shall be established from a pre -established benchmark and
23 checked by closing to a different bench mark on the same datum.
24 3. Construction survey field work shall correspond to the client's plans. Irregularities
25 or conflicts found shall be reported promptly to the City.
26 4. Revisions, corrections and other pertinent data shall be logged for future reference.
27
28 3.2 EXAMINATION [NOT USED]
29 3.3 PREPARATION [NOT USED]
30 3.4 APPLICATION
31 3.5 REPAIR / RESTORATION
32 A. If the Contractor's work damages or destroys one or more of the control
33 monuments/points set by the Developer's Project Representative, the monuments shall be
34 adequately referenced for expedient restoration.
35 1. Notify City or Developer's Project Representative if any control data needs to be
36 restored or replaced due to damage caused during construction operations.
37 a. Contractor shall perform replacements and/or restorations.
38 b. The City or Developer's Project Representative may require at any time a
39 survey "Field Check" of any monument or benchmarks that are set be verified
40 by the Developer's Project Representative before further associated work can
41 move forward.
CITY OF FORT WORTH Trinity Lakes Mixed Use South Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project Number 103849
Revised February 14, 2018
017123-7
CONSTRUCTION STAKING AND SURVEY
Page 7 of 7
1 3.6 RE -INSTALLATION [NOT USED]
2 3.7 FIELD [OR] SITE QUALITY CONTROL
3 A. It is the Contractor's responsibility to maintain all stakes and control data placed by the
4 Developer's Project Representative in accordance with this Specification. This includes
5 easements and right of way, if noted on the plans.
6 B. Do not change or relocate stakes or control data without approval from the City.
7 3.8 SYSTEM STARTUP
8 A. Survey Checks
9 1. The City reserves the right to perform a Survey Check at any time deemed
10 necessary.
11 2. Checks by City personnel or 3rd party contracted surveyor are not intended to
12 relieve the contractor of his/her responsibility for accuracy.
13
14 3.9 ADJUSTING [NOT USED]
15 3.10 CLEANING [NOT USED]
16 3.11 CLOSEOUT ACTIVITIES [NOT USED]
17 3.12 PROTECTION [NOT USED]
18 3.13 MAINTENANCE [NOT USED]
19 3.14 ATTACHMENTS [NOT USED]
20
21
Pip)
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
8/31/2012 D.Johnson
Added instruction and modified measurement & payment under 1.2; added
8/31/2017 M. Owen definitions and references under 1.3; modified 1.6; added 1.7 closeout submittal
requirements; modified 1.9 Quality Assurance; added PART 2 — PRODUCTS ;
Added 3.1 Installers; added 3.5 Repair/Restoration; and added 3.8 System Startup.
Removed "blue text"; revised measurement and payment sections for Construction
Staking and As -Built Survey; added reference to selection compliance with TGC
2/14/2018 M Owen 2254; revised action and Closeout submittal requirements; added acceptable depth
measurement criteria; revised list of items requiring as -built survey "during" and
"after" construction; and revised acceptable digital survey file format
CITY OF FORT WORTH Trinity Lakes Mixed Use South Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project Number 103849
Revised February 14, 2018
01 74 23 - 1
DAP CLEANING
Page 1 of 4
1 SECTION 0174 23
2 CLEANING
3 PART1- GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. Intermediate and final cleaning for Work not including special cleaning of closed
7 systems specified elsewhere
8 B. Deviations from this City of Fort Worth Standard Specification
9 1. None.
10 C. Related Specification Sections include, but are not necessarily limited to:
11 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
12 2. Division 1 — General Requirements
13 3. Section 32 92 13 — Hydro -Mulching, Seeding and Sodding
14 1.2 PRICE AND PAYMENT PROCEDURES
15 A. Measurement and Payment
16 1. Work associated with this Item is considered subsidiary to the various Items bid.
17 No separate payment will be allowed for this Item.
18 1.3 REFERENCES [NOT USED]
19 1.4 ADMINISTRATIVE REQUIREMENTS
20 A. Scheduling
21 1. Schedule cleaning operations so that dust and other contaminants disturbed by
22 cleaning process will not fall on newly painted surfaces.
23 2. Schedule final cleaning upon completion of Work and immediately prior to final
24 inspection.
25 1.5 SUBMITTALS [NOT USED]
26 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
27 1.7 CLOSEOUT SUBMITTALS [NOT USED]
28 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
29 1.9 QUALITY ASSURANCE [NOT USED]
30 1.10 STORAGE, AND HANDLING
31 A. Storage and Handling Requirements
32 1. Store cleaning products and cleaning wastes in containers specifically designed for
33 those materials.
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised April 7, 2014
01 74 23 - 2
DAP CLEANING
Page 2 of 4
1 1.11 FIELD [SITE] CONDITIONS [NOT USED]
2 1.12 WARRANTY [NOT USED]
3 PART 2- PRODUCTS
4 2.1 OWNER -FURNISHED [OR] OWNER-SUPPLIEDPRODUCTS [NOT USED]
5 2.2 MATERIALS
6 A. Cleaning Agents
7 1. Compatible with surface being cleaned
8 2. New and uncontaminated
9 3. For manufactured surfaces
10 a. Material recommended by manufacturer
11 2.3 ACCESSORIES [NOT USED]
12 2.4 SOURCE QUALITY CONTROL [NOT USED]
13 PART 3 - EXECUTION
14
3.1
INSTALLERS [NOT USED]
15
3.2
EXAMINATION [NOT USED]
16
3.3
PREPARATION [NOT USED]
17
3.4
APPLICATION [NOT USED]
18
3.5
REPAIR / RESTORATION [NOT USED]
19
3.6
RE -INSTALLATION [NOT USED]
20
3.7
FIELD [OR] SITE QUALITY CONTROL [NOT USED]
21
3.8
SYSTEM STARTUP [NOT USED]
22
3.9
ADJUSTING [NOT USED]
23
3.10
CLEANING
24 A. General
25 1. Prevent accumulation of wastes that create hazardous conditions.
26 2. Conduct cleaning and disposal operations to comply with laws and safety orders of
27 governing authorities.
28 3. Do not dispose of volatile wastes such as mineral spirits, oil or paint thinner in
29 storm or sanitary drains or sewers.
30 4. Dispose of degradable debris at an approved solid waste disposal site.
31 5. Dispose of nondegradable debris at an approved solid waste disposal site or in an
32 alternate manner approved by City and regulatory agencies.
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised April 7, 2014
01 74 23 - 3
DAP CLEANING
Page 3 of 4
1 6. Handle materials in a controlled manner with as few handlings as possible.
2 7. Thoroughly clean, sweep, wash and polish all Work and equipment associated with
3 this project.
4 8. Remove all signs of temporary construction and activities incidental to construction
5 of required permanent Work.
6 9. If project is not cleaned to the satisfaction of the City, the City reserves the right to
7 have the cleaning completed at the expense of the Contractor.
8 10. Do not burn on -site.
9 B. Intermediate Cleaning during Construction
10 1. Keep Work areas clean so as not to hinder health, safety or convenience of
11 personnel in existing facility operations.
12 2. At maximum weekly intervals, dispose of waste materials, debris and rubbish.
13 3. Confine construction debris daily in strategically located container(s):
14 a. Cover to prevent blowing by wind
15 b. Store debris away from construction or operational activities
16 c. Haul from site at a minimum of once per week
17 4. Vacuum clean interior areas when ready to receive finish painting.
18 a. Continue vacuum cleaning on an as -needed basis, until Final Acceptance.
19 5. Prior to storm events, thoroughly clean site of all loose or unsecured items, which
20 may become airborne or transported by flowing water during the storm.
21 C. Exterior (Site or Right of Way) Final Cleaning
22 1. Remove trash and debris containers from site.
23 a. Re -seed areas disturbed by location of trash and debris containers in accordance
24 with Section 32 92 13.
25 2. Sweep roadway to remove all rocks, pieces of asphalt, concrete or any other object
26 that may hinder or disrupt the flow of traffic along the roadway.
27 3. Clean any interior areas including, but not limited to, vaults, manholes, structures,
28 junction boxes and inlets.
29 4. If no longer required for maintenance of erosion facilities, and upon approval by
30 City, remove erosion control from site.
31 5. Clean signs, lights, signals, etc.
32 3.11 CLOSEOUT ACTIVITIES [NOT USED]
33 3.12 PROTECTION [NOT USED]
34 3.13 MAINTENANCE [NOT USED]
35 3.14 ATTACHMENTS [NOT USED]
36
37
38
39
40
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised April 7, 2014
01 74 23 - 4
DAP CLEANING
Page 4 of 4
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
4/7/2014 M.Domenech Revised for DAP application
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised April 7, 2014
1
2
3 PART1- GENERAL
4 1.1 SUMMARY
SECTION 01 7719
CLOSEOUT REQUIREMENTS
017719-1
DAP CLOSEOUT REQUIREMENTS
Page 1 of 3
5 A. Section Includes:
6 1. The procedure for closing out a contract
7 B. Deviations from this City of Fort Worth Standard Specification
8 1. None.
9 C. Related Specification Sections include, but are not necessarily limited to:
10 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
11 2. Division 1 — General Requirements
12 1.2 PRICE AND PAYMENT PROCEDURES
13 A. Measurement and Payment
14 1. Work associated with this Item is considered subsidiary to the various Items bid.
15 No separate payment will be allowed for this Item.
16 1.3 REFERENCES [NOT USED]
17 1.4 ADMINISTRATIVE REQUIREMENTS
18 A. Guarantees, Bonds and Affidavits
19 1. No application for final payment will be accepted until all guarantees, bonds,
20 certificates, licenses and affidavits required for Work or equipment as specified are
21 satisfactorily filed with the City.
22 B. Release of Liens or Claims
23 1. No application for final payment will be accepted until satisfactory evidence of
24 release of liens has been submitted to the City.
25 1.5 SUBMITTALS
26 A. Submit all required documentation to City's Project Representative.
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised April 7, 2014
017719-2
DAP CLOSEOUT REQUIREMENTS
Page 2 of 3
1.6 INFORMATIONAL SUBMITTALS [NOT USED]
2 1.7 CLOSEOUT SUBMITTALS [NOT USED]
3 PART 2 - PRODUCTS [NOT USED]
4 PART 3 - EXECUTION
5 3.1 INSTALLERS [NOT USED]
6 3.2 EXAMINATION [NOT USED]
7 3.3 PREPARATION [NOT USED]
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
3.4 CLOSEOUT PROCEDURE
A. Prior to requesting Final Inspection, submit:
1. Project Record Documents in accordance with Section 0178 39
2. Operation and Maintenance Data, if required, in accordance with Section 0178 23
B. Prior to requesting Final Inspection, perform final cleaning in accordance with Section
01 74 23.
C. Final Inspection
1. After final cleaning, provide notice to the City Project Representative that the Work
is completed.
a. The City will make an initial Final Inspection with the Contractor present.
b. Upon completion of this inspection, the City will notify the Contractor, in
writing within 10 business days, of any particulars in which this inspection
reveals that the Work is defective or incomplete.
2. Upon receiving written notice from the City, immediately undertake the Work
required to remedy deficiencies and complete the Work to the satisfaction of the
City.
3. Upon completion of Work associated with the items listed in the City's written
notice, inform the City, that the required Work has been completed. Upon receipt
of this notice, the City, in the presence of the Contractor, will make a subsequent
Final Inspection of the project.
4. Provide all special accessories required to place each item of equipment in full
operation. These special accessory items include, but are not limited to:
a. Specified spare parts
b. Adequate oil and grease as required for the first lubrication of the equipment
c. Initial fill up of all chemical tanks and fuel tanks
d. Light bulbs
e. Fuses
f. Vault keys
g. Handwheels
h. Other expendable items as required for initial start-up and operation of all
equipment
D. Notice of Project Completion
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised April 7, 2014
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
017719-3
DAP CLOSEOUT REQUIREMENTS
Page 3 of 3
1. Once the City Project Representative finds the Work subsequent to Final Inspection
to be satisfactory, the City will issue a Notice of Project Completion (Green Sheet).
E. Supporting Documentation
1. Coordinate with the City Project Representative to complete the following
additional forms:
a. Final Payment Request
b. Statement of Contract Time
c. Affidavit of Payment and Release of Liens
d. Consent of Surety to Final Payment
e. Pipe Report (if required)
£ Contractor's Evaluation of City
g. Performance Evaluation of Contractor
F. Letter of Final Acceptance
1. Upon review and acceptance of Notice of Project Completion and Supporting
Documentation, in accordance with General Conditions, City will issue Letter of
Final Acceptance and release the Final Payment Request for payment.
3.5 REPAIR / RESTORATION [NOT USED]
3.6 RE -INSTALLATION [NOT USED]
3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED]
3.8 SYSTEM STARTUP [NOT USED]
3.9 ADJUSTING [NOT USED]
3.10 CLEANING [NOT USED]
3.11 CLOSEOUT ACTIVITIES [NOT USED]
3.12 PROTECTION [NOT USED]
3.13 MAINTENANCE [NOT USED]
3.14 ATTACHMENTS [NOT USED]
DATE NAME
4/7/2014 M.Domenech
END OF SECTION
Revision Log
SUMMARY OF CHANGE
Revised for DAP application
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised April 7, 2014
017823-1
DAP OPERATION AND MAINTENANCE DATA
Page 1 of 5
1 SECTION 0178 23
2 OPERATION AND MAINTENANCE DATA
3 PART1- GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. Product data and related information appropriate for City's maintenance and
7 operation of products furnished under Contract
8 2. Such products may include, but are not limited to:
9 a. Traffic Controllers
10 b. Irrigation Controllers (to be operated by the City)
11 c. Butterfly Valves
12 B. Deviations from this City of Fort Worth Standard Specification
13 1. None.
14 C. Related Specification Sections include, but are not necessarily limited to:
15 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
16 2. Division 1 — General Requirements
17 1.2 PRICE AND PAYMENT PROCEDURES
18 A. Measurement and Payment
19 1. Work associated with this Item is considered subsidiary to the various Items bid.
20 No separate payment will be allowed for this Item.
21 1.3 REFERENCES [NOT USED]
22 1.4 ADMINISTRATIVE REQUIREMENTS
23 A. Schedule
24 1. Submit manuals in final form to the City within 30 calendar days of product
25 shipment to the project site.
26 1.5 SUBMITTALS
27 A. Submittals shall be in accordance with Section 0133 00. All submittals shall be
28 approved by the City prior to delivery.
29 1.6 INFORMATIONAL SUBMITTALS
30 A. Submittal Form
31 1. Prepare data in form of an instructional manual for use by City personnel.
32 2. Format
33 a. Size: 8 '/2 inches x 11 inches
34 b. Paper
35 1) 40 pound minimum, white, for typed pages
36 2) Holes reinforced with plastic, cloth or metal
37 c. Text: Manufacturer's printed data, or neatly typewritten
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised April 7, 2014
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
01 78 23 - 2
DAP OPERATION AND MAINTENANCE DATA
Page 2 of 5
d. Drawings
1) Provide reinforced punched binder tab, bind in with text
2) Reduce larger drawings and fold to size of text pages.
e. Provide fly -leaf for each separate product, or each piece of operating
equipment.
1) Provide typed description of product, and major component parts of
equipment.
2) Provide indexed tabs.
f. Cover
1) Identify each volume with typed or printed title "OPERATING AND
MAINTENANCE INSTRUCTIONS".
2) List:
a) Title of Project
b) Identity of separate structure as applicable
c) Identity of general subject matter covered in the manual
3. Binders
a. Commercial quality 3-ring binders with durable and cleanable plastic covers
b. When multiple binders are used, correlate the data into related consistent
groupings.
4. If available, provide an electronic form of the O&M Manual.
B. Manual Content
1. Neatly typewritten table of contents for each volume, arranged in systematic order
a. Contractor, name of responsible principal, address and telephone number
b. A list of each product required to be included, indexed to content of the volume
c. List, with each product:
1) The name, address and telephone number of the subcontractor or installer
2) A list of each product required to be included, indexed to content of the
volume
3) Identify area of responsibility of each
4) Local source of supply for parts and replacement
d. Identify each product by product name and other identifying symbols as set
forth in Contract Documents.
2. Product Data
a. Include only those sheets which are pertinent to the specific product.
b. Annotate each sheet to:
1) Clearly identify specific product or part installed
2) Clearly identify data applicable to installation
3) Delete references to inapplicable information
3. Drawings
a. Supplement product data with drawings as necessary to clearly illustrate:
1) Relations of component parts of equipment and systems
2) Control and flow diagrams
b. Coordinate drawings with information in Project Record Documents to assure
correct illustration of completed installation.
c. Do not use Project Record Drawings as maintenance drawings.
4. Written text, as required to supplement product data for the particular installation:
a. Organize in consistent format under separate headings for different procedures.
b. Provide logical sequence of instructions of each procedure.
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised April 7, 2014
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
017823-3
DAP OPERATION AND MAINTENANCE DATA
Page 3 of 5
5. Copy of each warranty, bond and service contract issued
a. Provide information sheet for City personnel giving:
1) Proper procedures in event of failure
2) Instances which might affect validity of warranties or bonds
C. Manual for Materials and Finishes
1. Submit 5 copies of complete manual in final form.
2. Content, for architectural products, applied materials and finishes:
a. Manufacturer's data, giving full information on products
1) Catalog number, size, composition
2) Color and texture designations
3) Information required for reordering special manufactured products
b. Instructions for care and maintenance
1) Manufacturer's recommendation for types of cleaning agents and methods
2) Cautions against cleaning agents and methods which are detrimental to
product
3) Recommended schedule for cleaning and maintenance
3. Content, for moisture protection and weather exposure products:
a. Manufacturer's data, giving full information on products
1) Applicable standards
2) Chemical composition
3) Details of installation
b. Instructions for inspection, maintenance and repair
D. Manual for Equipment and Systems
1. Submit 5 copies of complete manual in final form.
2. Content, for each unit of equipment and system, as appropriate:
a. Description of unit and component parts
1) Function, normal operating characteristics and limiting conditions
2) Performance curves, engineering data and tests
3) Complete nomenclature and commercial number of replaceable parts
b. Operating procedures
1) Start-up, break-in, routine and normal operating instructions
2) Regulation, control, stopping, shut -down and emergency instructions
3) Summer and winter operating instructions
4) Special operating instructions
c. Maintenance procedures
1) Routine operations
2) Guide to "trouble shooting"
3) Disassembly, repair and reassembly
4) Alignment, adjusting and checking
d. Servicing and lubrication schedule
1) List of lubricants required
e. Manufacturer's printed operating and maintenance instructions
£ Description of sequence of operation by control manufacturer
1) Predicted life of parts subject to wear
2) Items recommended to be stocked as spare parts
g. As installed control diagrams by controls manufacturer
h. Each contractor's coordination drawings
1) As installed color coded piping diagrams
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised April 7, 2014
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
01 78 23 - 4
DAP OPERATION AND MAINTENANCE DATA
Page 4 of 5
i. Charts of valve tag numbers, with location and function of each valve
j. List of original manufacturer's spare parts, manufacturer's current prices, and
recommended quantities to be maintained in storage
k. Other data as required under pertinent Sections of Specifications
3. Content, for each electric and electronic system, as appropriate:
a. Description of system and component parts
1) Function, normal operating characteristics, and limiting conditions
2) Performance curves, engineering data and tests
3) Complete nomenclature and commercial number of replaceable parts
b. Circuit directories of panelboards
1) Electrical service
2) Controls
3) Communications
c. As installed color coded wiring diagrams
d. Operating procedures
1) Routine and normal operating instructions
2) Sequences required
3) Special operating instructions
e. Maintenance procedures
1) Routine operations
2) Guide to "trouble shooting"
3) Disassembly, repair and reassembly
4) Adjustment and checking
f. Manufacturer's printed operating and maintenance instructions
g. List of original manufacturer's spare parts, manufacturer's current prices, and
recommended quantities to be maintained in storage
h. Other data as required under pertinent Sections of Specifications
4. Prepare and include additional data when the need for such data becomes apparent
during instruction of City's personnel.
30 1.7 CLOSEOUT SUBMITTALS [NOT USED]
31 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
32 1.9 QUALITY ASSURANCE
33 A. Provide operation and maintenance data by personnel with the following criteria:
34 1. Trained and experienced in maintenance and operation of described products
35 2. Skilled as technical writer to the extent required to communicate essential data
36 3. Skilled as draftsman competent to prepare required drawings
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised April 7, 2014
017823-5
DAP OPERATION AND MAINTENANCE DATA
Page 5 of 5
1 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
2 1.11 FIELD [SITE] CONDITIONS [NOT USED]
3 1.12 WARRANTY [NOT USED]
4 PART 2 - PRODUCTS [NOT USED]
5 PART 3 - EXECUTION [NOT USED]
6 END OF SECTION
7
Revision Log
DATE NAME SUMMARY OF CHANGE
8/31/2012 D. Johnson 1.5.A.1 — title of section removed
4/7/2014 M.Domenech Revised for DAP Application
8
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised April 7, 2014
017839-1
DAP PROJECT RECORD DOCUMENTS
Page 1 of 4
1 SECTION 0178 39
2 PROJECT RECORD DOCUMENTS
3 PART1- GENERAL
4 1.1 SUMMARY
5 A. Section Includes:
6 1. Work associated with the documenting the project and recording changes to project
7 documents, including:
8 a. Record Drawings
9 b. Water Meter Service Reports
10 c. Sanitary Sewer Service Reports
11 d. Large Water Meter Reports
12 B. Deviations from this City of Fort Worth Standard Specification
13 1. None.
14 C. Related Specification Sections include, but are not necessarily limited to:
15 1. Division 0 — Bidding Requirements, Contract Forms and Conditions of the Contract
16 2. Division 1 — General Requirements
17 1.2 PRICE AND PAYMENT PROCEDURES
18 A. Measurement and Payment
19 1. Work associated with this Item is considered subsidiary to the various Items bid.
20 No separate payment will be allowed for this Item.
21 1.3 REFERENCES [NOT USED]
22 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED]
23 1.5 SUBMITTALS
24 A. Prior to submitting a request for Final Inspection, deliver Project Record Documents to
25 City's Project Representative.
26 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
27 1.7 CLOSEOUT SUBMITTALS [NOT USED]
28 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
29 1.9 QUALITY ASSURANCE
30 A. Accuracy of Records
31 1. Thoroughly coordinate changes within the Record Documents, making adequate
32 and proper entries on each page of Specifications and each sheet of Drawings and
33 other Documents where such entry is required to show the change properly.
34 2. Accuracy of records shall be such that future search for items shown in the Contract
35 Documents may rely reasonably on information obtained from the approved Project
36 Record Documents.
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised April 7, 2014
017839-2
DAP PROJECT RECORD DOCUMENTS
Page 2 of 4
1 3. To facilitate accuracy of records, make entries within 24 hours after receipt of
2 information that the change has occurred.
3 4. Provide factual information regarding all aspects of the Work, both concealed and
4 visible, to enable future modification of the Work to proceed without lengthy and
5 expensive site measurement, investigation and examination.
6 1.10 STORAGE AND HANDLING
7 A. Storage and Handling Requirements
8 1. Maintain the job set of Record Documents completely protected from deterioration
9 and from loss and damage until completion of the Work and transfer of all recorded
10 data to the final Project Record Documents.
11 2. In the event of loss of recorded data, use means necessary to again secure the data
12 to the City's approval.
13 a. In such case, provide replacements to the standards originally required by the
14 Contract Documents.
15 1.11 FIELD [SITE] CONDITIONS [NOT USED]
16 1.12 WARRANTY [NOT USED]
17 PART 2 - PRODUCTS
18 2.1 OWNER -FURNISHED [OR] OWNER -SUPPLIED PRODUCTS [NOT USED]
19 2.2 RECORD DOCUMENTS
20 A. Job set
21 1. Promptly following receipt of the Notice to Proceed, secure from the City, at no
22 charge to the Contractor, 1 complete set of all Documents comprising the Contract.
23 B. Final Record Documents
24 1. At a time nearing the completion of the Work and prior to Final Inspection, provide
25 the City 1 complete set of all Final Record Drawings in the Contract.
26 2.3 ACCESSORIES [NOT USED]
27 2.4 SOURCE QUALITY CONTROL [NOT USED]
28 PART 3 - EXECUTION
29 3.1 INSTALLERS [NOT USED]
30 3.2 EXAMINATION [NOT USED]
31 3.3 PREPARATION [NOT USED]
32 3.4 MAINTENANCE DOCUMENTS
33 A. Maintenance of Job Set
34 1. Immediately upon receipt of the job set, identify each of the Documents with the
35 title, "RECORD DOCUMENTS - JOB SET".
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised April 7, 2014
017839-3
DAP PROJECT RECORD DOCUMENTS
Page 3 of 4
1 2. Preservation
2 a. Considering the Contract completion time, the probable number of occasions
3 upon which the job set must be taken out for new entries and for examination,
4 and the conditions under which these activities will be performed, devise a
5 suitable method for protecting the job set.
6 b. Do not use the job set for any purpose except entry of new data and for review
7 by the City, until start of transfer of data to final Project Record Documents.
8 c. Maintain the job set at the site of work.
9 3. Coordination with Construction Survey
10 a. At a minimum clearly mark any deviations from Contract Documents
11 associated with installation of the infrastructure.
12 4. Making entries on Drawings
13 a. Record any deviations from Contract Documents.
14 b. Use an erasable colored pencil (not ink or indelible pencil), clearly describe the
15 change by graphic line and note as required.
16 c. Date all entries.
17 d. Call attention to the entry by a "cloud" drawn around the area or areas affected.
18 e. In the event of overlapping changes, use different colors for the overlapping
19 changes.
20 5. Conversion of schematic layouts
21 a. In some cases on the Drawings, arrangements of conduits, circuits, piping,
22 ducts, and similar items, are shown schematically and are not intended to
23 portray precise physical layout.
24 1) Final physical arrangement is determined by the Contractor, subject to the
25 City's approval.
26 2) However, design of future modifications of the facility may require
27 accurate information as to the final physical layout of items which are
28 shown only schematically on the Drawings.
29 b. Show on the job set of Record Drawings, by dimension accurate to within 1
30 inch, the centerline of each run of items.
31 1) Final physical arrangement is determined by the Contractor, subject to the
32 City's approval.
33 2) Show, by symbol or note, the vertical location of the Item ("under slab", "in
34 ceiling plenum", "exposed", and the like).
35 3) Make all identification sufficiently descriptive that it may be related
36 reliably to the Specifications.
37 c. The City may waive the requirements for conversion of schematic layouts
38 where, in the City's judgment, conversion serves no useful purpose. However,
39 do not rely upon waivers being issued except as specifically issued in writing
40 by the City.
41 B. Final Project Record Documents
42 1. Transfer of data to Drawings
43 a. Carefully transfer change data shown on the job set of Record Drawings to the
44 corresponding final documents, coordinating the changes as required.
45 b. Clearly indicate at each affected detail and other Drawing a full description of
46 changes made during construction, and the actual location of items.
47 c. Call attention to each entry by drawing a "cloud" around the area or areas
48 affected.
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised April 7, 2014
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
017839-4
DAP PROJECT RECORD DOCUMENTS
Page 4 of 4
d. Make changes neatly, consistently and with the proper media to assure
longevity and clear reproduction.
2. Transfer of data to other Documents
a. If the Documents, other than Drawings, have been kept clean during progress of
the Work, and if entries thereon have been orderly to the approval of the City,
the job set of those Documents, other than Drawings, will be accepted as final
Record Documents.
b. If any such Document is not so approved by the City, secure a new copy of that
Document from the City at the City's usual charge for reproduction and
handling, and carefully transfer the change data to the new copy to the approval
of the City.
3.5 REPAIR / RESTORATION [NOT USED]
3.6 RE -INSTALLATION [NOT USED]
3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED]
3.8 SYSTEM STARTUP [NOT USED]
3.9 ADJUSTING [NOT USED]
3.10 CLEANING [NOT USED]
3.11 CLOSEOUT ACTIVITIES [NOT USED]
3.12 PROTECTION [NOT USED]
3.13 MAINTENANCE [NOT USED]
3.14 ATTACHMENTS [NOT USED]
DATE NAME
4/7/2014 M.Domenech
END OF SECTION
Revision Log
SUMMARY OF CHANGE
Revised for DAP Application
CITY OF FORT WORTH Trinity Lakes Mixed Use South, Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS City Project No. - 103849
Revised April 7, 2014
FORTWORTH.
CITY OF FORT WORTH
WATER DEPARTMENT
STANDARD PRODUCT LIST
Updated: April 09, 2021
The Fort Worth Water Department's Standard Products List has been developed to
minimize the submittal review of products which meet the Fort Worth Water
Department's Standard Specifications during utility construction projects. When
Technical Specifications for specific products, are included as part of the
Construction Contract Documents, the requirements of the Technical Specification
will override the Fort Worth Water Department's Standard Specifications and the
Fort Worth Water Department's Standard Products List and approval of the
specific products will be based on the requirements of the Technical Specification
whether or not the specific product meets the Fort Worth Water Department's
Standard Specifications or is on the Fort Worth Water Department's Standard
Products List.
Table of Content
(Click on items to go directly to the page)
Items
Page
A. Water & Sewer
1.
Manholes & Bases/Components...........................................................
1
2.
Manholes & Bases/Fiberglass...............................................................
2
3.
Manholes & Bases/Frames & Covers/Rectangular ...............................
3
4.
Manholes & Bases/Frames & Covers/Round.......................................
4
5.
Manholes & Bases/Frames & Covers/Water Tight & Pressure Tight ..
5
6.
Manholes & Bases/Precast Concrete ....................................................
6
7.
Manholes & Bases/Rehab Systems/Cementitious................................
7
8.
Manholes & Bases/Rehab Systems/NonCementitious .........................
8
9.
Manhole Insert (Field Operations Use Only) ........................................
9
10.
Pipe Casing Spacer...............................................................................
10
11.
Pipes/Ductile Iron.................................................................................
11
12.
Utility Line Marker...............................................................................
12
B. Sewer
13. Coatings/Epoxy..................................................................................... 13
14. Coatings/Polyurethane.......................................................................... 14
15. Combination Air Valves....................................................................... 15
16. Pipes/Concrete...................................................................................... 16
17. Pipe Enlargement System (Method) ..................................................... 17
18. Pipes/Fiberglass Reinforced Pipe ......................................................... 18
19. Pipes/HDPE.......................................................................................... 19
20. Pipes/PVC (Pressure Sewer)................................................................. 20
21. Pipes/PVC*........................................................................................... 21
22. Pipes/Rehab/CIPP................................................................................. 22
23. Pipes/Rehab/Fold & Form.................................................................... 23
24. Pipes/Open Profile Large Diameter...................................................... 24
C. Water
25. Appurtenances.......................................................................................
25
26. Bolts, Nuts, and Gaskets.......................................................................
26
27. Combination Air Release Valve...........................................................
27
28. Dry Barrel Fire Hydrants......................................................................
28
29. Meters...................................................................................................
29
30. Pipes/PVC (Pressure Water).................................................................
30
31. Pipes/Valves & Fittings/Ductile Iron Fittings .......................................
31
32. Pipes/Valves & Fittings/Resilient Seated Gate Valve ..........................
32
33. Pipes/Valves & Fittings/Rubber Seated Butterfly Valve ......................
33
34. Polyethylene Encasement.....................................................................
34
35. Sampling Stations.................................................................................
35
36. Automatic Flusher.................................................................................
36
CITY OF FORT WORTH
FORT WORTH. WATER DEPARTMENT
STANDARD PRODUCT LIST
Note: All water or sewer nine lartrer than 15 inch diameter shall be approved for use by the Water Department on a nroiect specific basis.
i l Water & Sewer - Manholes & Bases/Comuonents 33-39-10 (Rev 2/3/16)
Updated:04/09/2021
be required for some
07/23/97
33 05 13
Urethane Hydrophilic Waterstop
Asahi Kogyo K.K.
Adeka Ultra -Seal P-201 ASTM D2240/D412/D792
04/26/00
3305 13
Offset Joint for 4' Diam. MH
Hanson Concrete Products
Drawing No. 35-0048-001
04/26/00
3305 13
Profile Gasket for 4' Diam. MH.
Press -Seal Gasket Corp.
250-4G Gasket ASTM C-443/C-361
1/26/99
3305 13
HDPE Manhole Adjustment Rings
Ladtech, Inc
HDPE Adjustment Ring
5/13/05
3305 13
Manhole External Wrap
Canusa - CPS
WrapidSeal Manhole Encapsulation System
SS MH
Non -traffic area
* From Original Standard Products List Click to Return to the Table of Content 1
CITY OF FORT WORTH
FORT WORTH. WATER DEPARTMENT Updated:04/09/2021
STANDARD PRODUCT LIST
Note: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.
Approval 1. Classsification Mamufactimer Model
Water & Sewer - Manholes & Bases/FiberElass 33-39-13 (1/8/13)
1/26/99 3339 13 Fiberglass Manhole Fluid Containment, Inc. Flowtite ASTM 3753 Non -traffic area
08/30/06 3339 13 Fiberglass Manhole L.F. Manufacturing Non -traffic area
* From Original Standard Products List Click to Return to the Table of Content 2
CITY OF FORT WORTH
FORT WORTH. WATER DEPARTMENT Updated:04/09/2021
STANDARD PRODUCT LIST
Note: All water or sewer
than 15 inch diameter shall be approved for use by the Water Department on a
Water & Sewer - Manholes & Bases/Frames & Covers/Rectaneular 33-05-13 (Rev 2/3/16)
33 05 13 (Manhole Frames and Covers I Western Iron Works, Bass & Hays Foundry
basis.
• 1001 MEIN
be required for some
24"x40" WD
* From Original Standard Products List Click to Return to the Table of Content
FORTWORTH,,
Note: All water or sewer
CITY OF FORT WORTH
WATER DEPARTMENT
STANDARD PRODUCT LIST
than 15 inch diameter shall be approved for use by the Water Department on a
basis.
Updated:04/09/2021
be required for some
JL
Water & Sewer - Manholes & Bases/Frames & Covers/Standard (Round) 33-05-13 (Rev 2/3/16)--
*
3305 13
Manhole Frames and Covers
Western Iron Works, Bass & Hays Foundry
30024
24" Dia.
*
3305 13
Manhole Frames and Covers
McKinley Iron Works Inc.
A 24 AM
24" Dia.
08/24/18
3305 13
Manhole Frames and Covers
Neenah Foundry
R-1272
ASTM A48 & AASHTO M306
24" Dia.
08/24/18
3305 13
Manhole Frames and Covers
Neenah Foundry
R- 165-LM (Hinged)
ASTM A48 & AASHTO M306
24" Dia.
08/24/18
3305 13
Manhole Frames and Covers
Neenah Foundry
NF 1274
ASTM A48 & AASHTO M306
30" Dia.
08/24/18
3305 13
Manhole Frames and Covers
Neenah Foundry
R-1743-LM (Hinged)
ASTM A48 & AASHTO M306
30" dia.
3305 13
Manhole Frames and Covers
Sigma Corporation
MH-144N
3305 13
Manhole Frames and Covers
Sigma Corporation
MH-143N
3305 13
Manhole Frames and Covers
Pont-A-Mousson
GTS-STD
24" dia.
3305 13
Manhole Frames and Covers
Neenah Casting
24" dia.
10/31/06
3305 13
Manhole Frames and Covers (Hinged)
Powerseal
Hinged Ductile Iron Manhole
ASTM A536
24" Dia.
7/25/03
3305 13
Manhole Frames and Covers
Saint-Gobain Pipelines (Pamrex/rexus)
RE32-R8FS
30" Dia.
01/31/06
3305 13
30" Dia. MH Ring and Cover
East Jordan Iron Works
V 1432-2 and V 1483 Designs
AASHTO M306-04
30" Dia.
11/02/10
3305 13
30" Dia. MH Ring and Cover
Sigma Corporation
MH165IFWN & MH16502
30" Dia
07/19/11
3305 13
30" Dia. MH Ring and Cover
Star Pipe Products
MH32FTWSS-DC
30" Dia
08/10/11
3305 13
30" Dia. MH Ring and Cover
Accucast
220700 Heavy Duty with Gasket Ring
30" Dia
30" ERGO XL Assembly
10/14/13
3305 13
30" Dia. MH Ring and Cover (Hinged & Lockable)
East Jordan Iron Works
with Cam Lock/MPIC/T-Gasket
ASSHTO M105 & ASTM A536
30" Dia
06/01/17
3405 13
30" Dia. MH Ring and Cover (Hinged & Lockable) Cl
SIP Industries
2280 (32")
ASTM A 48
30" Dia.
CAP-ONE-30-FTW, Composite, w/ Lock
09/16/19
3305 13.10
30" Dia. MH Ring and Cover
Composite Access Products, L.P.
w/o Hing
30" Dia.
* From Original Standard Products List Click to Return to the Table of Content 4
CITY OF FORT WORTH
FORT WORTH. WATER DEPARTMENT
STANDARD PRODUCT LIST
Note: All water or sewer nine lartrer than 15 inch diameter shall be approved for use by the Water Department on a nroiect specific basis.
Water & Sewer - Manholes & Bases/Frames & Covers/Water Tight & Pressure Tight 33-05-13 (Rev 2/3/16)
*
3305 13
Manhole Frames and Covers
Pont-A-Mousson
Pamtight
*
3305 13
Manhole Frames and Covers
Neenah Casting
*
3305 13
Manhole Frames and Covers
Western Iron Works,Bass & Hays Foundry
300-24P
*
3305 13
Manhole Frames and Covers
McKinley Iron Works Inc.
WPA24AM
03/08/00
3305 13
Manhole Frames and Covers
Accucast
RC-2100
04/20/01
3305 13
Manhole Frames and Covers
(SIP)Serampore Industries Private Ltd.
300-24-23.75 Ring and Cover
Updated:04/09/2021
be required for some
24" Dia.
24" Dia.
24" Dia.
24" Dia.
ASTM A 48 24" Dia.
ASTM A 48 24" Dia.
* From Original Standard Products List Click to Return to the Table of Content 5
FORTWORTH,,
Note: All water or sewer nine h
CITY OF FORT WORTH
WATER DEPARTMENT
STANDARD PRODUCT LIST
than 15 inch diameter shall be annroved for use by the Water Department on a
basis.
Updated:04/09/2021
be required for some
Water & Sewer - Manholes & Bases/Precast Concrete (Rev 1/8'
*
3339 10
Manhole, Precast Concrete
Hydro Conduit Corp
SPL Item #49
ASTM C 478
*
3339 10
Manhole, Precast Concrete
Wall Concrete Pipe Co. Inc.
ASTM C-443
09/23/96
3339 10
Manhole, Precast Concrete
Concrete Product Inc.
48" I.D. Manhole w/ 32" Cone
ASTM C 478
05/08/18
3339 10
Manhole, Precast Concrete
The Turner Company
48", 60" I.D. Manhole w/ 32" Cone
ASTM C 478
10/27/06
3339 10
Manhole, Precast Concrete
Oldcastle Precast Inc.
48" I.D. Manhole w/ 24" Cone
ASTM C 478
06/09/10
3339 10
Manhole, Precast (Reinforce Polymer)Concrete
US Composite Pipe
Reinforced Polymer Concrete
ASTM C-76
09/06/19
33 39 20
Manhole, Precast Concrete
Forterra Pipe and Precast
60" & 72" I.D. Manhole w/32" Cone
ASTM C-76
48"
48"
48" w/32" cone
48", 60"
48" Diam w 24" Ring
48" to 72"
60" & 72"
* From Original Standard Products List Click to Return to the Table of Content 6
FORTWORTH,,
Note: All water or sewer nine h
CITY OF FORT WORTH
WATER DEPARTMENT
STANDARD PRODUCT LIST
than 15 inch diameter shall be approved for use by the Water Department on a Droiect specific basis.
WAS & Sewer - Manholes & Bases/Rehab Svstems/Ce nentitious E
*
E1-14
Manhole Rehab Systems
Quadex
04/23/01
E1-14
Manhole Rehab Systems
Standard Cement Materials, Inc.
Reliner MSP
E1-14
Manhole Rehab Systems
AP/M Permaform
4/20/01
E1-14
Manhole Rehab System
Strong Company
Strong Seal MS2A Rehab System
5/12/03
E1-14
Manhole Rehab System (Liner)
Poly -triplex Technologies
MH repair product to stop infiltration
08/30/06
General Concrete Repair
F1exKrete Technologies
Vinyl Polyester Repair Product
Updated:04/09/2021
be required for some pipes.
ASTM D5813
Misc. Use
* From Original Standard Products List Click to Return to the Table of Content 7
CITY OF FORT WORTH
FORT WORTH. WATER DEPARTMENT
STANDARD PRODUCT LIST
Note: All water or sewer nine lartrer than 15 inch diameter shall be approved for use by the Water Department on a nroiect specific basis.
Updated:04/09/2021
be required for some
VV ULCl OL 3VWC1 - iflLU 111UMN Oi D-AJCJ/ilCllil11 JVJLC111J/i4U111.C111C11LltlUUJ
I I
I
05/20/96
E1-14
Manhole Rehab Systems
Sprayroq,
Spray Wall Polyurethane Coating
ASTM D639/D790
*
E1-14
Manhole Rehab Systems
Sun Coast
For Exterior Coating of Concrete
12/14/01
Coating for Corrosion protection(Exterior)
ERTECH
Series 20230 and 2100 (Asphatic Emulsion)
Structures Only
01/31/06
Coatings for Corrosion Protection
Chesterton
Arc 791, SlBB, Sl, S2
Acid Resistance Test Sewer Applications
8/28/2006
Coatings for Corrosion Protection
Warren Environmental
S-301 and M-301
Sewer Applications
08/30/06
Coatings for Corrosion Protection
Citadel
SLS-30 Solids Epoxy
Sewer Applications
33 05 16, 33 39 10, 33
RR&C Dampproofmg Non-Fibered Spray
For Exterior Coating of Concrete
03/19/18
3920
Coating for Corrosion protection(Exterior)
Sherwin Williams
Grade (Asphatic Emulsion)
Structures Only
* From Original Standard Products List Click to Return to the Table of Content 8
CITY OF FORT WORTH
FORT WORTH. WATER DEPARTMENT
STANDARD PRODUCT LIST
Note: All water or sewer nine lartrer than 15 inch diameter shall be approved for use by the Water Department on a nroiect specific basis.
Updated:04/09/2021
be required for some
y•.—
— v v—
- mauuvm ■11-1 w - rmiu vuciaumm
vx vwy t— --gA + 1
I
*
3305 13
Manhole Insert
Knutson Enterprises
Made to Order - Plastic ASTM D 1248
For 24" dia.
*
3305 13
Manhole Insert
South Western Packaging
Made to Order - Plastic ASTM D 1248
For 24" dia.
*
3305 13
Manhole Insert
Noflow-Inflow
Made to Order - Plastic ASTM D 1248
For 24" dia.
09/23/96
3305 13
Manhole Insert
Southwestern Packing & Seals, Inc.
Lifesaver - Stainless Steel
For 24" dia.
09/23/96
3305 13
Manhole Insert
Southwestern Packing & Seals, Inc.
TetherLok - Stainless Steel
For 24" dia
* From Original Standard Products List Click to Return to the Table of Content 9
CITY OF FORT WORTH
FORT WORTH. WATER DEPARTMENT
STANDARD PRODUCT LIST
Note: All water or sewer nine lartrer than 15 inch diameter shall be approved for use by the Water Department on a nroiect specific basis.
Updated:04/09/2021
be required for some
VV attul QC auwul - riyu l,ilSlll$'3"ilkxi b JJ-yo-LN 1V //Vl/1.3
l
11/04/02
Steel Band Casing Spacers
Advanced Products and Systems, Inc.
Carbon Steel Spacers, Model SI
02/02/93
Stainless Steel Casing Spacer
Advanced Products and Systems, Inc.
Stainless Steel Spacer, Model SSI
04/22/87
Casing Spacers
Cascade Waterworks Manufacturing
Casing Spacers
09/14/10
Stainless Steel Casing Spacer
Pipeline Seal and Insulator
Stainless Steel Casing Spacer Up to 48"
09/14/10
Coated Steel Casin Spacers
Pipeline Seal and Insulator
Coated Steel Casin Spacers Up to 48"
05/10/11
Stainless Steel Casing Spacer
Powerseal
4810 Powerchock Up to 48"
03/19/18
Casing Spacers
BWM
SS-12 Casing Spacer(Stainless Steel)
03/19/18
Casing Spacers
BWM
FB-12 Casing Spacer (Coated Carbon Steel) for
Non pressure Pipe and Grouted Casing
* From Original Standard Products List Click to Return to the Table of Content 10
CITY OF FORT WORTH
FORT WORTH. WATER DEPARTMENT
STANDARD PRODUCT LIST
Note: All water or sewer nine lartrer than 15 inch diameter shall be approved for use by the Water Department on a nroiect specific basis.
*
V♦0.1G1 UIL UGVV
33 11 10
GI � 11r1GJ/LUl
Ductile Iron Pipe
08/24/18
33 11 10
Ductile Iron Pipe
08/24/18
33 11 10
Ductile Iron Pipe
*
33 11 10
Ductile Iron Pipe
*
33 11 10
Ductile Iron Pipe
Griffin Pipe Products, Co.
American Ductile Iron Pipe Co.
American Ductile Iron Pipe Co.
U.S. Pipe and Foundry Co.
McWane Cast Iron Pipe Co.
Updated:04/09/2021
be required for some
Super Bell-Tite Ductile Iron Pressure Pipe, AWWA C150, C151
American Fastite Pipe (Bell Spigot) AW WA C150, C151
American Flex Ring (Restrained Joint) AWWA C150, C151
AW WA C150, C151
AWWA C150, C151
3" thru 24"
4" thru 30"
4" thru 30"
* From Original Standard Products List Click to Return to the Table of Content 11
FORTWORTH,,
Note: All water or sewer
than 15 inch diameter shall be
Water & Sewer - Utility Line Marker (08/24/2018)
CITY OF FORT WORTH
WATER DEPARTMENT
STANDARD PRODUCT LIST
for use by the Water Department on a
basis.
Updated:04/09/2021
be required for some
* From Original Standard Products List Click to Return to the Table of Content 12
CITY OF FORT WORTH
FORT WORTH. WATER DEPARTMENT Updated:04/09/2021
STANDARD PRODUCT LIST
Note: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.
Approval 1. Classsification Mamufactimer Model
Cnwpr _ r"afinac/Fna— 22_20_6n full MR/1,11
02/25/02
Epoxy Lining System
Sauereisen, Inc
SewerGard 210RS LA County #210-1.33
12/14/01
Epoxy Lining System
Ertech Technical Coatings
Ertech 2030 and 2100 Series
04/14/05
Interior Ductile Iron Pipe Coating
Induron
Protecto 401 ASTM B-117
01/31/06
Coatings for Corrosion Protection
Chesterton
Arc 791, SIBB, Sl, S2 Acid Resistance Test
8/28/2006
Coatings for Corrosion Protection
Warren Environmental
S-301 and M-301
Ductile Iron Pipe Only
Sewer Applications
Sewer Applications
* From Original Standard Products List Click to Return to the Table of Content 13
FORTWORTH,,
Note: All water or sewer
CITY OF FORT WORTH
WATER DEPARTMENT
STANDARD PRODUCT LIST
than 15 inch diameter shall be approved for use by the Water Department on a
basis.
Updated:04/09/2021
be required for some
* From Original Standard Products List Click to Return to the Table of Content 14
FORTWORTH,,
Note: All water or sewer pipe larger than 15 inch diameter shall be
Approval i
Sewer - Combigation Air Valves
05/25/18 33-31-70 Air Release Valve
CITY OF FORT WORTH
WATER DEPARTMENT
STANDARD PRODUCT LIST
for use by the Water Department on a proiect specific basis.
A.R.I. USA, Inc. I D025LTP02(Composite Body)
Updated:04/09/2021
be required for some
* From Original Standard Products List Click to Return to the Table of Content is
FORTWORTH,,
Note: All water or sewer
CITY OF FORT WORTH
WATER DEPARTMENT
STANDARD PRODUCT LIST
than 15 inch diameter shall be approved for use by the Water Department on a
basis.
Updated:04/09/2021
be required for some
Pives/Coricret-
* E1-04 Conc. Pipe, Reinforced
Wall Concrete Pipe Co. Inc.
ASTM C 76
* E1-04 Conc. Pipe, Reinforced
Hydro Conduit Corporation Class III T&G, SPL Item #77
ASTM C 76
* E1-04 Conc. Pipe, Reinforced
Hanson Concrete Products SPi It_: MY 2M=4=le, *°.� 9 Pipe
ASTM C 76
* E1-04 Conc. Pipe, Reinforced
Concrete Pipe & Products Co. Inc.
ASTM C 76
* From Original Standard Products List Click to Return to the Table of Content 16
FORTWORTH,,
Note: All water or sewer
CITY OF FORT WORTH
WATER DEPARTMENT
STANDARD PRODUCT LIST
than 15 inch diameter shall be approved for use by the Water Department on a
basis.
Updated:04/09/2021
be required for some
Sewer - Pine Entarement Svstem (Method)33-31-23 /13
PIM System PIM Corporation Polyethylene PIM Corp., Piscata Way, N.J. Approved Previously
McConnell Systems McLat Construction Polyethylene Houston, Texas Approved Previously
TRS Systems Trenchless Replacement System Polyethylene Calgary, Canada Approved Previously
* From Original Standard Products List Click to Return to the Table of Content 17
FORTWORTH,,
Note: All water or sewer
CITY OF FORT WORTH
WATER DEPARTMENT
STANDARD PRODUCT LIST
than 15 inch diameter shall be approved for use by the Water Department on a
basis.
Updated:04/09/2021
be required for some
Sewer - Pipe/Fiberglass
Reinforced Pipe 33-31-13(1/8/13)
7/21/97
03/22/10
33 31 13
33 31 13
Cent. Cast Fiberglass (FRP)
Fiberglass Pipe FRP
Flobas Pipe USA, Inc.
Ameron
Flobas Pipe (Non -Pressure)
Bondstrand RPMP Pie
ASTM D3262/D3754
ASTM D3262/D3754
04/09/21
Glass -Fiber Reinforced Polymer Pipe (FRP)
Thompson Pie Group
Thom son Pipe (Flowtite)
ASTM D3262/D3754
4/14/05
06/09/10
El-9
Polymer Modified Concrete Pipe
Reinforced Polymer Concrete Pipe
Amitech USA
US Composite Pipe
Meyer Polycrete Pipe
Reinforced Polymer Concrete Pipe
ASTM C33, A276, F477
ASTM C-76
8" to 102", Class V
* From Original Standard Products List Click to Return to the Table of Content 18
CITY OF FORT WORTH
FORT WORTH. WATER DEPARTMENT
STANDARD PRODUCT LIST
Note: All water or sewer nine lartrer than 15 inch diameter shall be approved for use by the Water Department on a nroiect specific basis.
Updated:04/09/2021
be required for some
High -density polyethylene pipe
Phillips Driscopipe, Inc. Opticore Ductile Polyethylene Pipe
ASTM D 1248 8"
* High -density polyethylene pipe
Plexco Inc.
ASTM D 1248 8"
High -density polyethylene pipe
Polly Pipe, Inc.
ASTM D 1248 8"
High -density polyethylene pipe
CSR Hydro Conduit/Pipeline Systems McConnell Pipe Enlargement
ASTM D 1248
* From Original Standard Products List Click to Return to the Table of Content 19
CITY OF FORT WORTH
FORT WORTH. WATER DEPARTMENT Updated:04/09/2021
STANDARD PRODUCT LIST
Note: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.
Approval 1 1Model No. National Spec Size
Sewer - Pipes/PVC (Pressure Sewer) 33-11-12 (4/1/13)
12/02/11 33-11-12 DR-14 PVC Pressure Pipe Pipelife Jetstream PVC Pressure Pipe AWWA C900 4" thru 12"
10/22/14 33-11-12 DR-14 PVC Pressure Pipe Royal Building Products Royal Seal PVC Pressure Pipe AWWA C900 4" thm 12"
* From Original Standard Products List Click to Return to the Table of Content 20
FORTWORTH,,
Note: All water or sewer
CITY OF FORT WORTH
WATER DEPARTMENT
STANDARD PRODUCT LIST
than 15 inch diameter shall be approved for use by the Water Department on a
basis.
Updated:04/09/2021
be required for some
Sewer - Pines/PVC* 33-31-20 (7/1/13)
NEEL
*
33-31-20
PVC Sewer Pipe
J-M Manufacturing Co., Inc. (JM Eagle)
SDR-26
ASTM D 3034
4" - 15"
12/23/97*
33-31-20
PVC Sewer Pipe
Diamond Plastics Corporation
SDR-26
ASTM D 3034
4" thru 15"
*
33-31-20
PVC Sewer Pipe
Lamson Vylon Pipe
ASTM F 789
4" thru 15"
01/18/18
33-31-20
PVC Sewer Pipe
Vinyltech PVC Pipe
Gravity Sewer
ASTM D3034
4" thru 15"
11/11/98
33-31-20
PVC Sewer Pipe
Diamond Plastics Corporation
"S" Gravity Sewer Pipe
ASTM F 679
18" to 27"
*
33-31-20
PVC Sewer Pipe
J-M Manufacturing Co, Inc. QM Eagle)
SDR 26/35 PS 115/46
ASTM F 679
18" - 28"
09/11/12
33-31-20
PVC Sewer Pipe
Pipelife Jet Stream
SDR-26 and SDR-35
ASTM F-679
18"
05/06/05
33-31-20
PVC Solid Wall Pipe
Diamond Plastics Corporation
SDR 26/35 PS 115/46
ASTM F-679
18" to 48"
04/27/06
33-31-20
PVC Sewer Fittings
Harco
SDR-26 and SDR-35 Gasket Fittings
ASTM D-3034, D-1784, etc
4" - 15"
*
33-31-20
PVC Sewer Fittings
Plastic Trends, In.c
Gasketed PVC Sewer Main Fittings
ASTM D 3034
3/19/2018
33 31 20
PVC Sewer Pipe
Pipelife Jet Stream
SDR 35
ASTM F679
18"- 24"
3/19/2018
33 31 20
PVC Sewer Pipe
Pipelife Jet Stream
SDR 26
ASTM D3034
4% 15"
3/29/2019
33 31 20
Gasketed Fittings (PVC)
GPK Products, Inc.
SDR 26
ASTM D3034/F-679
4"- 15"
10/21/2020
33 31 20
PVC Sewer Pipe
NAPCO
SDR 26
ASTM D3034
4" - 15"
10/22/2020
33 31 20
PVC Sewer Pipe
Sanderson Pipe Corp.
SDR 26
ASTM D3034
4"- 15"
10/21/2020
33 31 20
PVC Sewer Pipe
NAPCO
SDR 26/35 PS 115/46
ASTM F-679
18% 36"
* From Original Standard Products List Click to Return to the Table of Content 21
CITY OF FORT WORTH
FORT WORTH. WATER DEPARTMENT
STANDARD PRODUCT LIST
Note: All water or sewer nine lareer than 15 inch diameter shall be approved for use by the Water Department on a nroiect specific basis.
*
05/03/99
05/29/96
n%,irr 00-01-
in Place Pipe
in Place Pipe
in Place Pipe
Insituform Texark, Inc
National Envirotech Group National Liner, (SPL) Item #27
Reynolds Inc/Inliner Technolgy (Inliner USA) Inliner Technology
Updated:04/09/2021
be required for some
ASTM F 1216
ASTM F-1216/D-5813
ASTM F 1216
* From Original Standard Products List Click to Return to the Table of Content 22
FORTWORTH,,
Note: All water or sewer
CITY OF FORT WORTH
WATER DEPARTMENT
STANDARD PRODUCT LIST
than 15 inch diameter shall be approved for use by the Water Department on a
basis.
Updated:04/09/2021
be required for some
Sewer - Pipes/Rehab/Fold & Form
* Fold and Form Pipe Cullum Pipe Systems, Inc.
11/03/98 Fold and Form Pipe Insituform Technologies, Inc. Insituform "NuPIpe" ASTM F-1504
Fold and Form Pipe American Pipe & Plastics, Inc. Demo. Purpose Only
12/04/00 Fold and Form Pipe Ultraliner Ultraliner PVC Alloy Pipeliner ASTM F-1504, 1871, 1867
06/09/03 Fold and Form Pipe Miller Pipeline Corp. EX Method ASTM F-1504, F-1947 Up to 18" diameter
* From Original Standard Products List Click to Return to the Table of Content 23
FORTWORTH,,
Note: All water or sewer
CITY OF FORT WORTH
WATER DEPARTMENT
STANDARD PRODUCT LIST
than 15 inch diameter shall be approved for use by the Water Department on a
basis.
Updated:04/09/2021
be required for some
Sewer - Pipes/Open Profile Large Diameter
Im
09/26/91
E100-2
PVC Sewer Pipe, Ribbed
Lamson Vylon Pipe
Carlon Vylon H.C. Closed Profile Pipe,
ASTM F 679
18" to 48"
09/26/91
E100-2
PVC Sewer Pipe, Ribbed
Extrusion Technologies, Inc.
Ultra -Rib Open Profile Sewer Pipe
ASTM F 679
18" to 48"
E100-2
PVC Sewer Pipe, Ribbed
Uponor ETI Company
11/10/10
(E100-2)
Polypropylene (PP) Sewer Pipe, Double Wall
Advanced Drainage Systems (ADS)
SaniTite HP Double Wall (Corrugated)
ASTM F 2736
24"-30"
11/10/10
(E100-2)
Polypropylene (PP) Sewer Pipe, Triple Wall
Advanced Drainage Systems (ADS)
SaniTite HP Triple Wall Pipe
ASTM F 2764
30" to 60"
05/16/11
Steel Reinforced Polyethylene Pipe
ConTech Construction Products
Durmaxx
ASTM F 2562
24" to 72"
* From Original Standard Products List Click to Return to the Table of Content 24
FORTWORTH,,
Note: All water or sewer
CITY OF FORT WORTH
WATER DEPARTMENT
STANDARD PRODUCT LIST
than 15 inch diameter shall be approved for use by the Water Department on a
basis.
Updated:04/09/2021
be required for some
Water - Aunurtenances 33-12-10 (07/01/13)
01/18/18
33-12-10
Double Strap Saddle
Romac
202NS Nylon Coated
AWWA C800
1"-2" SVC, up to 24" Pipe
08/28/02
Double Strap Saddle
Smith Blair
#317 Nylon Coated Double Strap Saddle
07/23/12
33-12-10
Double Strap Service Saddle
Mueller Company
DR2S Double (SS) Strap DI Saddle
AWWA C800
1"-2" SVC, up to 24" Pipe
10/27/87
Curb Stops -Ball Meter Valves
McDonald
6100M,6100MT & 61OMT
3/4" and 1"
10/27/87
Curb Stops -Ball Meter Valves
McDonald
4603B, 4604B, 6100M, 610OTM and 6101M
1%" and 2"
FB600-7NL, FB1600-7-NL, FV23-777-W-NL,
5/25/2018
33-12-10
Curb Stops -Ball Meter Valves
Ford Meter Box Co., Inc.
L22-77NL
AWWA C800
2"
FB600-6-NL, FB 1600-6-NL, FV23-666-W-NL,
5/25/2018
33-12-10
Curb Stops -Ball Meter Valves
Ford Meter Box Co., Inc.
L22-66NL
AWWA C800
1-1/2"
FB600-4-NL, FB 1600-4-NL, B 11-444-WR-NL,
5/25/2018
33-12-10
Curb Stops -Ball Meter Valves
Ford Meter Box Co., Inc.
B22444-WR-NL, L28-44NL
AWWA C800
V
B-25000N, B-24277N-3, B-20200N-3, H-
AWWA C800, ANSF 61,
5/25/2018
33-12-10
Curb Stops -Ball Meter Valves
Mueller Co., Ltd.
15000N, , H-1552N, H142276N
ANSI/NSF 372
2"
B-25000N, B-20200N-3, B-24277N-3,H-
AWWA C800, ANSF 61,
5/25/2018
33-12-10
Curb Stops -Ball Meter Valves
Mueller Co., Ltd.
15000N, H-14276N, H-15525N
ANSI/NSF 372
1-1/2"
B-25000N, B-20200N-3,H-15000N, H-
AWWA C800, ANSF 61,
5/25/2018
33-12-10
Curb Stops -Ball Meter Valves
Mueller Co., Ltd.
15530N
ANSI/NSF 372
1"
01/26/00
Coated Tapping Saddle with Double SS Straps
JCM Industries, Inc.
#406 Double Band SS Saddle
1"-2" Taps on up to 12"
0/5/21/12
33-12-25
Tapping Sleeve (Coated Steel)
JCM Industries, Inc.
412 Tapping Sleeve ESS
AWWA C-223
Up to 30" w/12" Out
05/10/11
Tapping Sleeve (Stainless Steel)
Powerseal
3490AS (Flange) & 3490MJ
4"-8" and 16"
02/29/12
33-12-25
Tapping Sleeve (Coated Steel)
Romac
FTS 420
AWWA C-223
U p to 42" w/24" Out
02/29/12
33-12-25
Tapping Sleeve (Stainless Steel)
Romac
SST Stainless Steel
AWWA C-223
Up to 24" w/12" Out
02/29/12
33-12-25
Tapping Sleeve (Stainless Steel)
Romac
SST III Stainless Steel
AWWA C-223
Up to 30" w/12" Out
05/10/11
Joint Repair Clamp
Powerseal
3232 Bell Joint Repair Clamp
4" to 30"
Plastic Meter Box w/Composite Lid
DFW Plastics Inc.
DFW37C-12-IEPAF FTW
Plastic Meter Box w/Composite Lid
DFW Plastics Inc.
DFW39C-12-IEPAF FTW
08/30/06
Plastic Meter Box w/Composite Lid
DFW Plastics Inc.
DFW65C-14-lEPAF FTW
Class "A"
Concrete Meter Box
Bass & Hays
CMB37-B 12 1118 LID-9
Concrete Meter Box
Bass & Hays
CMB-18-Dual 1416 LID-9
Concrete Meter Box
Bass & Hays
CMB65-1365 1527 LID-9
* From Original Standard Products List Click to Return to the Table of Content 25
FORTWORTH,,
[Vote: All water or sewer
CITY OF FORT WORTH
WATER DEPARTMENT
STANDARD PRODUCT LIST
than 15 inch diameter shall be approved for use by the Water Department on a
basis.
Updated:04/09/2021
be required for some
* From Original Standard Products List Click to Return to the Table of Content 26
FORTWORTH,,
Note: All water or sewer nine h
CITY OF FORT WORTH
WATER DEPARTMENT
STANDARD PRODUCT LIST
than 15 inch diameter shall be approved for use by the Water Department on a
Updated:04/09/2021
basis. Special beddine may be required for some
Water - Combination Air Release 33-31-70 (Ol/08/13)
* E1-11 Combination Air Release Valve GA Industries, Inc. Empire Air and Vacuum Valve, Model 935 ASTM A 126 Class B, ASTM A 1" & 2"
240 - float, ASTM A 307 - Cover
Bolts
* E1-11 Combination Air Release Valve Multiplex Manufacturing Co. Crispin Air and Vacuum Valves, Model No. 1/2", 1" & 2"
* E1-11 Combination Air Release Valve Valve and Primer Corp. APCO #143C, #145C and #147C 1", 2" & 3"
* From Original Standard Products List Click to Return to the Table of Content 27
CITY OF FORT WORTH
FORT WORTH. WATER DEPARTMENT
STANDARD PRODUCT LIST
Note: All water or sewer nine lareer than 15 inch diameter shall be approved for use by the Water Department on a nroiect specific basis.
JWater - Dry Barrel Fire Hvdrants 33-12-40 (01/15/14)
10/01/87
E-1-12
Dry Barrel Fire Hydrant
03/31/88
E-1-12
Dry Barrel Fire Hydrant
09/30/87
E-1-12
Dry Barrel Fire Hydrant
01/12/93
E-1-12
Dry Barrel Fire Hydrant
08/24/88
E-1-12
Dry Barrel Fire Hydrant
E-1-12
Dry Barrel Fire Hydrant
09/24/87
E-1-12
Dry Barrel Fire Hydrant
10/14/87
E-1-12
Dry Barrel Fire Hydrant
01/15/88
E1-12
Dry Barrel Fire Hydrant
10/09/87
E-1-12
Dry Barrel Fire Hydrant
09/16/87
E-1-12
Dry Barrel Fire Hydrant
08/12/16
33-1240
Dry Barrel Fire Hydrant
American -Darling Valve
Drawing Nos. 90-18608, 94-18560
American Darling Valve
Shop Drawing No. 94-18791
Clow Corporation
Shop Drawing No. D-19895
American AVK Company
Model 2700
Clow Corporation
Drawings D20435, D20436, B20506
ITT Kennedy Valve
Shop Drawing No. D-80783FW
M&H Valve Company
Shop Drawing No. 13476
Shop Drawings No. 6461
Mueller Company
A-423 Centurion
Shop Drawing FH-12
Mueller Company
A-423 Super Centurion 200
U.S. Pipe & Foundry
Shop Drawing No.960250
Waterous Company
Shop Drawing No. SK740803
EJ (East Jordan Iron Works)
WaterMaster 5CD250
Updated:04/09/2021
be required for some
AWWA C-502
AWWA C-502
AWWA C-502
AWWA C-502
AWWA C-502
AWWA C-502
AWWA C-502
AWWA C-502
AWWA C-502
AWWA C-502
AWWA C-502
* From Original Standard Products List Click to Return to the Table of Content 28
FORTWORTH,,
Note: All water or sewer pipe h
Approval Spec 1
Water - Nift
02/OS/93 E101-5
08/05/04
CITY OF FORT WORTH
WATER DEPARTMENT
STANDARD PRODUCT LIST
than 15 inch diameter shall be approved for use by the Water Department on a Droiect specific basis.
Check Meter
Drive Vertical Turbine
Ames Company I Model 1000 Detector Check Valve
Hersey Magnetic Drive Vertical
Updated:04/09/2021
be required for some pipes.
\ . 1 I . 1
AW WA C550 4" - 10"
AW WA C701, Class 1 3/4" - 6"
* From Original Standard Products List Click to Return to the Table of Content 29
CITY OF FORT WORTH
FORT WORTH. WATER DEPARTMENT
STANDARD PRODUCT LIST
Note: All water or sewer nine larlrer than 15 inch diameter shall be approved for use by the Water Department on a nroiect specific basis.
l VV 2LLUI - rlpub/ r V 1. IrI CSSul1
01/18/18
33-11-12
PVC Pressure Pipe
3/19/2018
33 11 12
PVC Pressure Pipe
3/19/2018
33 11 12
PVC Pressure Pipe
5/25/2018
33 11 12
PVC Pressure Pipe
5/25/2018
33 11 12
PVC Pressure Pipe
12/6/2018
33 11 12
PVC Pressure Pipe
12/6/2018
33 11 12
PVC Pressure Pipe
9/6/2019
33 11 12
PVC Pressure Pipe
9/6/2019
33 11 12
PVC Pressure Pipe
9/6/2019
33 11 12
PVC Pressure Pipe
9/6/2019
33 11 12
PVC Pressure Pipe
Updated:04/09/2021
be required for some
AWWA C900, AWWA C605,
Vinyltech PVC Pipe
JL DR14
ASTM D1784
4"-12"
Pipelife Jet Stream
DR14
AWWA C900
4"-12"
Pipelife Jet Stream
DR18
AWWA C900
16"-24"
Diamond Plastics Corporation
DR 14
AWWA C900
4"-12"
Diamond Plastics Corporation
DR 18
I AWWA C900
16"-24"
AWWA C900-16
UL 1285
J-M Manufacturing Co., Inc d/b/a JM Eagle
DR 14
ff:�28-
ANSI/NSF 61
FM 1612
AWWA C900-16
UL 1285
J-M Manufacturing Co., Inc d/b/a JM Eagle
DR 18
16"-24"
ANSI/NSF 61
FM 1612
Underground Solutions Inc.
DR14 Fusible PVC
AWWA C900
4" - 8"
NAPCO
DR18
AWWA C900
16" - 24"
NAPCO
DR14
AWWA C900
4"- 12"
Sanderson Pipe Corp.
DR14
AWWA C900
4"- 12"
* From Original Standard Products List Click to Return to the Table of Content 30
FORTWORTH,,
Note: All water or sewer
CITY OF FORT WORTH
WATER DEPARTMENT
STANDARD PRODUCT LIST
than 15 inch diameter shall be approved for use by the Water Department on a
Updated:04/09/2021
basis. SDecial beddine may be required for some
lWater - PinesNalves & Fittings/Ductile Iron Fittings 33-11-11 (01/08/131
07/23/92
E1-07
Ductile Iron Fittings
Star Pipe Products, Inc.
Mechanical Joint Fittings
AWWA C153 & C110
*
E1-07
Ductile Iron Fittings
Griffin Pipe Products, Co.
Mechanical Joint Fittings
AWWA C 110
*
E1-07
Ductile Iron Fittings
McWane/Tyler Pipe/ Union Utilities Division
Mechanical Joint Fittings, SSB Class 350
AWWA C 153, C 110, C III
08/11/98
E1-07
Ductile Iron Fittings
Sigma, Co.
Mechanical Joint Fittings, SSB Class 351
AWWA C 153, C 110, C 112
02/26/14
E1-07
MJ Fittings
Accucast
Class 350 C-153 MJ Fittings
AWWA C153
4"-12"
05/14/98
E1-07
Ductile Iron Joint Restraints
Ford Meter Box Co./Uni-Flange
Uni-Flange Series 1400
AWWA C111/C153
4" to 36"
05/14/98
E1-24
PVC Joint Restraints
Ford Meter Box Co./Uni-Flange
Uni-Flange Series 1500 Circle -Lock
AWWA C111/C153
4" to 24"
11/09/04
E1-07
Ductile Iron Joint Restraints
One Bolt, Inc.
One Bolt Restrained Joint Fitting
AWWA C111/C116/C153
4" to 12"
02/29/12
33-11-11
Ductile Iron Pipe Mechanical Joint Restraint
EBAA Iron, Inc.
Megalug Series 1100 (for DI Pipe)
AWWA C111/C116/C153
4" to 42"
02/29/12
33-11-11
PVC Pipe Mechanical Joint Restraint
EBAA Iron, Inc.
Megalug Series 2000 (for PVC Pipe)
AW WA C111/C116/C153
4" to 24"
08/05/04
E1-07
Mechanical Joint Retainer Glands(PVC)
Sigma, Co.
Sigma One-Lok SLC4 - SLC10
AWWA C111/C153
4" to 10"
03/06/19
33-11-11
Mechanical Joint Retainer Glands(PVC)
Sigma, Co.
Sigma One-Lok SLCS4 - SLCS12
AWWA C111/C153
4" to 12"
08/05/04
E1-07
Mechanical Joint Retainer Glands(PVC)
Sigma, Co.
Sigma One-Lok SLCE
AWWA C111/C153
12" to 24"
08/10/98
E1-07
MJ Fittings(DIP)
Sigma, Co.
Sigma One-Lok SLDE
AWWA C153
4" - 24"
10/12/10
E1-24
Interior Restrained Joint System
S & B Techncial Products
Bulldog System ( Diamond Lok 21 & JM Eagle
ASTM F-1624
4" to 12"
08/16/06
E1-07
Mechanical Joint Fittings
SIP Industries(Serampore)
Mechanical Joint Fittings
AW WA C153
4" to 24"
11/07/16
33-11-11
Mechanical Joint Retainer Glands
Star Pipe Products, Inc.
PVC Stargrip Series 4000
ASTM A536 AWWA CI I I
11/07/16
33-11-11
Mechanical Joint Retainer Glands
Star Pipe Products, Inc.
DIP Stargrip Series 3000
ASTM A536 AWWA CI I I
03/19/18
33-11-11
Mechanical Joint Retainer Glands
SIP Industries(Serampore)
EZ Grip Joint Restraint (EZD) Black For DIP
ASTM A536 AWWA CI I I
3"48"
EZ Grip Joint Restraint (EZD) Red for C900
03/19/18
33-11-11
Mechanical Joint Retainer Glands
SIP Industries(Serampore)
ASTM A536 AWWA CI I I
4"-12"
DR14 PVC Pipe
EZ Grip Joint Restraint (EZD) Red for C900
03/19/18
33-11-11
Mechanical Joint Retainer Glands
SIP Industries(Serampore)
ASTM A536 AWWA CI I I
16"-24"
DR18 PVC Pipe
* From Original Standard Products List Click to Return to the Table of Content 31
FORTWORTH,,
Note: All water or sewer
CITY OF FORT WORTH
WATER DEPARTMENT
STANDARD PRODUCT LIST
than 15 inch diameter shall be auproved for use by the Water
Water - Pines/Valves & Fittings/Resilient Seated Gate Valve* 33-12-20 (05/13/15).
Resilient Wedged Gate Valve w/no Gears
American Flow Control
12/13/02
Resilient Wedge Gate Valve
American Flow Control
08/31/99
Resilient Wedge Gate Valve
American Flow Control
05/18/99
Resilient Wedge Gate Valve
American Flow Control
10/24/00
E1-26
Resilient Wedge Gate Valve
American Flow Control
08/05/04
Resilient Wedge Gate Valve
American Flow Control
05/23/91
E1-26
Resilient Wedge Gate Valve
American AVK Company
01/24/02
E1-26
Resilient Wedge Gate Valve
American AVK Company
*
E1-26
Resilient Seated Gate Valve
Kennedy
*
E1-26
Resilient Seated Gate Valve
M&H
*
E1-26
Resilient Seated Gate Valve
Mueller Co.
11/08/99
Resilient Wedge Gate Valve
Mueller Co.
01/23/03
Resilient Wedge Gate Valve
Mueller Co.
05/13/05
Resilient Wedge Gate Valve
Mueller Co.
01/31/06
Resilient Wedge Gate Valve
Mueller Co.
01/28/88
E1-26
Resilient Wedge Gate Valve
Clow Valve Co.
10/04/94
Resilient Wedge Gate Valve
Clow Valve Co.
11/08/99
E1-26
Resilient Wedge Gate Valve
Clow Valve Co.
11/29/04
Resilient Wedge Gate Valve
Clow Valve Co.
11/30/12
Resilient Wedge Gate Valve
Clow Valve Co.
05/08/91
E1-26
Resilient Seated Gate Valve
Stockham Valves & Fittings
*
E1-26
Resilient Seated Gate Valve
U.S. Pipe and Foundry Co.
10/26/16
33-12-20
Resilient Seated Gate Valve
EJ (East Jordan Iron Works)
08/24/18
Mateo Gate Valve
Mateo-Norca
on a
basis.
Updated:04/09/2021
be required for some
Series 2500 Drawing # 94-20247
Series 2530 and Series 2536
AW WA C515
Series2520 & 2524(SD 94-20255)
AWWA C515
Series 2516 (SD 94-20247)
AW WA C515
Series 2500 (Ductile Iron)
AW WA C515
42" and 48" AFC 2500
AW WA C515
American AVK Resilient Seaded GV
AW WA C509
Series A2361 (SD 6647)
Series A2360 for 18"-24" (SD 6709)
Mueller 30" & 36", C-515
Mueller 42" & 48", C-515
16" RS GV (SD D-20995)
Clow RW Valve (SD D-21652)
Clow 30" & 36" C-515
Clow Valve Model 2638
Metroseal 250, requirements SPL #74
EJ F1owMaster Gate Valve & Boxes
225 MR
AW WA C515
AW WA C515
AW WA C515
AW WA C515
AW WA C509
AW WA C515
AW WA C515
AW WA C515
AW WA C515
AW WA C 509, ANSI 420 - stem,
ASTM A 276 Type 304 - Bolts &
nuts
AW WA/ANSI C 115/An21.15
16"
30" and 36"
20" and 24"
16"
4" to 12"
42" and 48"
4" to 12"
20" and smaller
4" - 12"
4" - 12"
4" - 12"
16"
24" and smaller
30" and 36"
42" and 48"
4" - 12"
16"
24" and smaller
30" and 36" (Note 3)
24" to 48" (Note 3)
4" - 12"
3" to 16"
4" to 16"
* From Original Standard Products List Click to Return to the Table of Content 32
CITY OF FORT WORTH
FORT WORTH. WATER DEPARTMENT
STANDARD PRODUCT LIST
Note: All water or sewer nine larirer than 15 inch diameter shall be approved for use by the Water Department on a nroiect specific basis.
JL Water&nes/Valves & Fittings/Rubber Seated Butterflv Valve 33-12-21 (07/10/14) .ENEL.-
Updated:04/09/2021
be required for some
*
E1-30
Rubber Seated Butterfly Valve
Henry Pratt Co.
AWWA C-504
*
E1-30
Rubber Seated Butterfly Valve
Mueller Co.
AWWA C-504
1/11/99
E1-30
Rubber Seated Butterfly Valve
Dezurik Valves Co.
AWWA C-504
06/12/03
E1-30
Valmatic American Butterfly Valve
Valmatic Valve and Manufacturing Corp.
Valmatic American Butterfly Valve.
AWWA C-504
04/06/07
E1-30
Rubber Seated Butterfly Valve
M&H Valve
M&H Style 4500 & 1450
AWWA C-504
03/19/18
33 1221
Rubber Seated Butterfly Valve
G. A. Industries (Golden Anderson)
AWWA C504 Butterfly Valve
AWWA C-504
24"
24"and smaller
24" and larger
Up to 84" diameter
24" to 48"
30"-54"
* From Original Standard Products List Click to Return to the Table of Content 33
FORTWORTH,,
Note: All water or sewer nine h
CITY OF FORT WORTH
WATER DEPARTMENT
STANDARD PRODUCT LIST
than 15 inch diameter shall be annroved for use by the Water Department on a
basis.
Updated:04/09/2021
be required for some
Water - Polvethvlene Encasement 33-11-10 (01/08/13)
05/12/05
E1-13 Polyethylene Encasment
Flexsol Packaging
Fulton Enterprises
AWWA C105
05/12/05
EI-13 Polyethylene Encasment
Mountain States Plastics (MSP) and AEP Ind.
Standard Hardware
AW WA C105
05/12/05
E 1-13 Polyethylene Encasment
AEP Industries
Bullstrong by Cowtown Bolt & Gasket
AW WA C105
09/06/19
33-11-11 Polyethylene Encasment
Northtown Products Inc.
PE Encasement for DIP
AW WA C105
8 mil LLD
8 mil LLD
8 mil LLD
8 mil LLD
* From Original Standard Products List Click to Return to the Table of Content 34
CITY OF FORT WORTH
FORT WORTH. WATER DEPARTMENT
STANDARD PRODUCT LIST
Note: All water or sewer nine lareer than 15 inch diameter shall be approved for use by the Water Department on a nroiect specific basis.
3/12/96 1 1 Water Sampling Station I Water Plus I B20 Water Sampling Station
Updated:04/09/2021
be required for some
* From Original Standard Products List Click to Return to the Table of Content 35
FORTWORTH,,
CITY OF FORT WORTH
WATER DEPARTMENT
STANDARD PRODUCT LIST
Updated:04/09/2021
Note: All water or sewer nine lartrer than 15 inch diameter shall be approved for use by the Water Department on a nroiect specific basis. Snecial beddine may be required for some nines.
Approvalin Model
Water - Automatic
Flusher
10/21/20
Automated Flushing System
Mueller H dro and
HG6-A-IN-2-BRN-LPRR(Portable)
HG2-A-IN--2-PVC-018-LPLG Permanent
04/09/21
Automated Flushing System
Kupferle Foundry Company
Eclipse #9800we
04/09/21
Automated Flushing System
Kupferle Foundry Company
Eclipse #9700 (Portable)
* From Original Standard Products List Click to Return to the Table of Content 36