HomeMy WebLinkAboutOrdinance 26327-08-2023ORDINANCE NO. 26327-08-2023
AN ORDINANCE INCREASING ESTIMATED RECEIPTS AND
APPROPRIATIONS IN THE GRANTS CAPITAL PROJECTS FEDERAL FUND, IN
AN AMOUNT UP TO (1) $2,800,000.00, SUBJECT TO RECEIPT OF THE GRANT,
AND (2) $700,000.00 AS A TRANSFER FROM PARR CENTREPORT TXDOT
GRANT PROJECT (CITY PROJECT NO. 104858) WITHIN THE GENERAL
CAPITAL PROJECTS FUND TO SATISFY THE CITY'S MATCH
REQUIREMENT, TOTALLING $3,500,000.00, FOR THE PURPOSE OF FUNDING
THE PURPOSE OF FUNDING THE CENTREPORT TRAIL PHASE I PROJECT
(CITY PROJECT NO. 100082); PROVIDING FOR A SEVERABILITY CLAUSE;
MAKING THIS ORDINANCE CUMULATIVE OF PRIOR ORDINANCES;
REPEALING ALL ORDINANCES IN CONFLICT HEREWITH; AND PROVIDING
AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH,
TEXAS:
SECTION 1.
That in addition to those amounts allocated to the various City departments for Fiscal Year 2022-2023 in the
Budget of the City Manager, there shall also be increased estimated receipts and appropriations in the Grants
Capital Projects Federal Fund, in an amount up to (1) $2,800,000.00, subject to the receipt of the grant, and
(2) $700,000.00 transferred from the PARD Centreport TXDOT Grant project (City Project No. 104858)
within the General Capital Projects Fund to satisfy the City's match requirement, totaling $3,500,000.00, for
the purpose of funding the Centreport Trail Phase I project (City Project No. 100082).
SECTION 2.
That should any portion, section or part of a section of this ordinance be declared invalid, inoperative or void
for any reason by a court of competent jurisdiction, such decision, opinion or judgment shall in no way impair
the remaining portions, sections, or parts of sections of this ordinance, which said remaining provisions shall
be and remain in full force and effect.
SECTION 3.
That this ordinance shall be cumulative of Ordinance 25773-09-2022 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance are in
direct conflict with such other ordinances and appropriations, in which instance said conflicting provisions of
said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
APPROVED AS TO FORM AND LEGALITY:
Assistant City Attorney
ADOPTED AND EFFECTIVE: August 8, 2023
CITY SECRETARY
F oqaO!°
r
a=�o
Jannette S. Goodall ,°°o�0�0o
00 o�000OXaFASR
f A • a TRE Tarrant County
1 i _--trePortj�
1 c ^Station�
Alm -1011
dZ7 ttiiil
I
,. A
f 1 • 1
�. ,� 1111111/ .a �„ f � F P � � t,. i 1 � 5 ^� •p
II IYI 1dl- � 1 1 `•+Rk7� l
.........1
amaluwwut mum Il�r' � � - � '-
IIf1111 flll 11 R. �a
11111111111111 rj} �
moo �ul•inlnnnn41anu1nin ,.J1�, ,_..�
�fl r
las County =, j
F.�.Afviti k �L"4,` • may' ` + l`._ �1
=+ '
• . s,:aa.
F
}
City of Fort Worth, Texas
Mayor and Council Communication
DATE: 08/08/23 M&C FILE NUMBER: M&C 23-0666
LOG NAME: 80CENTREPORT TRAIL PHASE I AFA AMEND 3 & PHASE II ENGR AGRMT
SUBJECT
(CD 5 ) Adopt a Resolution Authorizing Execution of Amendment No. 3 to the Advance Funding Agreement with the Texas Department of
Transportation for the CentrePort Trail Phase I Project to Increase the Project Cost from $6,110,470.00 to $9,610,470.00 with City Participation
Increasing to the Total Amount of $1,922,096.00, Authorize Execution of an Engineering Services Agreement with Halff Associates, Inc., in the
Amount of $228,000.00 for Final Engineering Design and Construction Administration Services for CentrePort Trail Phase II, Adopt Appropriation
Ordinances and Amend the Fiscal Years 2023-2027 Capital Improvement Program
RECOMMENDATION:
It is recommended that the City Council:
1. Adopt the attached Resolution authorizing execution of Amendment No, 3 to the Advance Funding Agreement with the Texas Department of
Transportation (City Secretary Contract No, 49494; CSJ# 0902-90-050) for the CentrePort Trail Phase I (City Project No.100082) to
increase the total project cost estimate from $6,110,470.00 to $9,610,470.00 with city participation increasing to the amount of
$1,922,096.00;
2. Authorize the acceptance of additional $2,800,000.00 in federal funds contributing to CentrePort Trail Phase I (City Project No. 100082)
through the Texas Department of Transportation;
3. Authorize the acceptance of a restricted donation from Streams & Valleys, Inc. in the amount of $35,000.00 designated for CentrePort Trail
Phase I (City Project No. 100082);
4. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the Special Donations Capital Projects
Fund in the amount of $35,000.00, from donation accepted, in the PARD Centreport TXDOT Grant project (City Project No. 104858) for the
purpose of funding a grant match for the CentrePort Trail Phase I project (City Project No. 100082);
5. Adopt the attached appropriation ordinance adjusting estimated receipts and appropriations in the General Capital Projects Fund by
increasing estimated receipts and appropriations in the PARD Centreport TXDOT Grant project (City Project No. 104858) in the amount of
$665,000.00 and decreasing estimated receipts and appropriations in the Future Community Partnerships programmable project (City
Project No. P00047) by the same amount for the purpose of funding a grant match for the CentrePort Trail Phase I project (City Project No.
100082);
6. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the Grants Capital Projects Federal Fund,
in the amount up to (1) $2,800,000.00, subject to the receipt of the grant, and (2) $700,000.00 transferred from the PARD Centreport TXDOT
Grant project (City Project No. 104858) within the General Capital Projects Fund and the Special Donations Capital Project Fund, to satisfy
the City's match requirement, totaling $3,500,000.00 for the purpose of funding the Centrepoint Trail Phase I (City Project No. 100082);
7. Amend the Fiscal Years 2023-2027 Capital Improvement Program; and
8. Authorize execution of an engineering services agreement with Halff Associates, Inc., in the amount of $228,000.00 for final engineering
design and construction administration services for CentrePort Trail Phase II (City Project No. 102130).
DISCUSSION:
The purpose of this Mayor and Council Communication (M&C) is to adopt the attached Resolution authorizing execution of Amendment No. 3 to
the Advance Funding Agreement (AFA) with the Texas Department of Transportation (TxDOT) (City Secretary Contract No. 49494; CSJ# 0902-90-
050) for the CentrePort Trail Phase I (City Project No.100082) for an increase of project construction cost, and the corresponding increase of
Federal, State and City cost participation, and authorize the execution of an engineering services agreement with Halff Associates, Inc., in the
amount of $228,000.00 for final 90% to 100% engineering design and construction administration services for CentrePort Trail Phase II (City
Project No. 102130).
The CentrePort project includes two phases. Phase I will start at the new American Airlines Campus in the east Fort Worth CentrePort area,
connect to Arlington River Legacy Trails and terminate at the Trinity Railway Express (TRE) CentrePort Station (approximately 1.6 miles total).
Phase II will start at the THE CentrePort Station and extend east along the THE railroad until meeting Trinity Boulevard, and then continue heading
south to Mike Lewis Park in Grand Prairie (approximately 3.5 miles total), Anticipated improvements include a 12-foot wide concrete paved trail,
3-foot wide shoulders, trail structures (bridges, retaining walls, drainage headwalls, tunnel, etc.), traffic control and 911 location signs.
The City Council approved an AFA with TxDOT in the amount of $2,757,588.00 on June 20, 2017 (M&C G-18975 and M&C G-19040) for the
engineering and construction of the CentrePort Trail Phase I.
The City Council approved Amendment No. 1 to increase the total agreement amount from $2,757,588.00 to $3,684,450.00 on September 25,
2018 (M&C G-19383) for up to 90% engineering design of the CentrePort Trail Phase II.
The City Council approved Amendment No. 2 to increase total project amount from $3,684,450.00 to $6,396,749.00 on June 14, 2022 (M&C 22-
0405) based on an increase of 60% construction cost estimate of CentrePort Phase I. The increase is due to the realignment of the trail around
unanticipated large areas of unstable slopes and additional reinforcement structures. Upon execution of the AFA, the amounts were reduced by
TxDOT to reflect a less increased amount of $6,384,302.00 which includes project budget in the amount of $6,110,470.00 and Indirect State Costs
in the amount of $273,832.00. City participation was reduced to the amount of $1,222,096.00.
Amendment No.3 is based on an increase of 100% construction cost estimate of CentrePort Trail Phase I. The increase is due to construction cost
escalation and the trail's close vicinity to exiting highway and the Trinity Railway Express (TRE) infrastructure. As a result, additional drainage
structures, security fencing, retaining walls and construction labor training requirements are added into the construction scope.
Funding for this amendment was not included in the Fiscal Years 2023-2027 Capital Improvement Program (CIP) due to unanticipated construction
challenges being incurred after the CIP was adopted. The action in this M&C will amend the Fiscal Year 2023-2027 Capital Improvement Program
as approved in connection with Ordinance 25773-09-2022, Section 7. Capital Improvements, as listed on page(s) 24:
Capital Fund Name V
Project Name
202 CIP
Authority
Bud, B
Revi Budget IFY2023
Ap
A U—Stent
301 eneral Capital
047F re Community
$750,000.00
($665,000.00)
$85,000.00
e00-s
Partnerships —... --
M&C
30100-General Capital
Projects _
100082 Centreport Trail
$0.00
This
M&C
$665,000.00
$665,000.00
30100-General Capital
Projects
Total
$750,000.00�
$0.00
$750,000.00
The total AFA increase of $3,500,000.00 is summarized below. The City does not budget Indirect State Costs in grants/projects.
Participation
Fund
Authority
Original
Budget Change
Revised
Budget
(Increase/Decrease)I
Budget
M&C G-18975; G-
Federal
Grants Cap Projects Federal
Fund
19383; 22-0405; This
F$4888,3741.00
$2,800,000.00
$7,688,374.00
M&C
Local
PARD Improvements Fund (2013
M 975-18637; G-
$350,000.00
$0.00
$350,000.00
CO's)
Local
2014 Bond Fund
IM&C G-18975
$170,002.00
$0.00
$170,002.00
M&C G-19305; G-
Local
General Capital Projects Fund
(PAYG)
19383; 22-0405; This
$355,169.00
$665,000.00
$1,020,169.00
M&C
Capital Projects Fund
[General
Donation from Streams &
This M&C
$0.00
$35,000.00
$35,000.00
alleys, Inc.)
Local
PARD Gas Lease Capital
Projects Fund
M&C 20-0256
$197,513.00
$0.00
$197,513.00
Local
City of Grand Prairie
G-19383; 22-0405
$149,412.00
$0.00
$149,412.00
Total Federal and Local
Participation
$6,110,470.00
$3,500,000.00
$9,610,470.00
Halff has been under contract (M&C C-29147 and City Secretary Contract No. 52483) since June 11, 2019, providing engineering design services
for CentrePort Phase I full engineering services and Phase II up to 90% engineering design services.
Business Equity: TxDOT set a goal of 0%, therefore the City will not override a federal or state goal except where the City is mandated to set
goals by state or federal requirements.
This project is located in COUNCIL DISTRICT 5.
FISCAL INFORMATION / CERTIFICATION:
The Director of Finance certifies that funds are currently available in the Future Community Partnerships programmable project within the General
Capital Projects Fund and the Centreport Trail Phase 2 project within the Grants Cap Projects Federal Fund and upon approval of the above
recommendations and adoption of the attached appropriation ordinances, funds will be available in the Grants Cap Projects Federal Fund for the
CentrePort Trail and Centreport Trail Phase 2 projects to support the above recommendations and execution of an engineering service agreement
and amendment to the advance funding agreement. The Park & Recreation Department (and Financial Management Services) will be responsible
for the collection and deposit of funds due to the City. Prior to an expenditure being incurred, the Park & Recreation Department has the
responsibility to validate the availability of funds. This is a reimbursement grant.
Submitted for City Manager's Office by: Jesica L. McEachem 5804
Originating Business Unit Head: Dave Lewis 5717
Additional Information Contact: Joel McElhany 5745