HomeMy WebLinkAboutContract 52153-A1AMENDMENT No.l CSC No. 52153-A1
TO CITY SECRETARY CONTRACT No. 52153
WHEREAS, the City of Fort Worth (CITY) and Southwestern Bell
Telephone Company d/b/a AT&T Texas, (UTILITY OWNER) made and entered into
City Secretary Contract No. 52153, (the CONTRACT) which was authorized by
M&C C-29047 on the 5th day of March, 2019 in the amount of $ 139,836.45;
and
WHEREAS, the CONTRACT involves utility relocation services for the
following project:
Six Points Urban Villages Central Cluster Project, CPN C00705; and
WHEREAS, it has become necessary to execute Amendment No. 1 to the
CONTRACT to include an increased scope of work and revised fee.
NOW THEREFORE, CITY and UTILITY OWNER, acting herein by and through
their duly authorized representatives, enter into the following
agreement, which amends the CONTRACT:
1.
Article I of the CONTRACT is amended to include the additional
utility relocation services specified in proposal attached hereto and
incorporated herein. The cost to City for the additional utility
relocation services to be performed by UTILITY OWNER totals $54,902.85.
(See Attached Funding Breakdown Sheet, Page -4-)
2.
Article II of the CONTRACT is amended to provide for an increase in
the fee to be paid to UTILITY OWNER for all work and services performed
under the Contract, as amended, so that the total fee paid by the City
for all work and services shall be an amount of $194,739.30.
3.
All other provisions of the Contract, which are not expressly
amended herein, shall remain in full force and effect.
EXECUTED and EFFECTIVE as of the date subscribed by the City's
designated Assistant City Manager.
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
City of Fort Worth, Texas Six Points Urban Villages Central Cluster
Prof Services Agreement Amendment Template C00705
Revision Date: November 23, 2021
Page 1 of 4
APPROVED:
City of Fort Worth
William Johnson (ALk 15, 2023 18:53 CDT)
William Johnson
Assistant City Manager
DATE: Aug 15, 2023
APPROVAL RECOMMENDED:
UTILITY OWNER
AT&T
Patrick McDermott (Jul27, 2023 16:53 CDT)
Patrick McDermott
AT&T Engineer
DATE: Jul 27, 2023
Lauren Prieur (Aug 11, 202315:16 CDT)
Lauren Prieur
Director, Transportation and Public Works Department
Contract Compliance Manager:
By signing, I acknowledge that I am the person responsible for the
monitoring and administration of this contract, including ensuring all
performance and reporting requirements.
Chad Allen
Engineering Manager
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
City of Fort Worth, Texas Six Points Urban Villages Central Cluster
Prof Services Agreement Amendment Template C00705
Revision Date: November 23, 2021
Page 2 of 4
APPROVED AS TO FORM AND LEGALITY: M&C: N/A
wo�� 1
DBlack (Aug 15, 202317:30 CDT)
Douglas W. Black
Sr. Assistant City Attorney
�p4UUL4�
FORr �aa
A�F 000000..
ATTEST:
a� �°
�v° o _°
�o
o
aa��u j(p 900
d
oa
Jannette Goodall
City Secretary
Date:
N/A
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
City of Fort Worth, Texas
Prof Services Agreement Amendment Template
Revision Date: November 23, 2021
Page 3 of 4
Six Points Urban Villages Central Cluster
C00705
FUNDING BREAKDOWN SHEET
City Secretary No. 52153
Amendment No. 1
Department Fund -Account -Center Amount
TPW 34014-0060419-5330500-000705-006573-9999- $54,902.85
14010205
Total: $54,902.85
City of Fort Worth, Texas Six Points Urban Villages Central Cluster
Prof Services Agreement Amendment Template C00705
Revision Date: November 23, 2021
Page 4 of 4
*** PROPRIETARY - NOT TO BE DISCLOSED OUTSIDE AT&T AND/OR AFFILIATE
COMPANY EXCEPT FOR 3RD PARTIES REQUESTING DETAIL OF CHARGES BILLED
TO THEM FOR CUSTOM WORK ***
AT&T AND/OR AFFILIATE COMPANY
CWO Bill Support Report - PA006010
Project No.: AOIDGGV
FREESE AND NICHOLS C/O CITY OF FORT WORTH
Summary of Charges
New Material 19,456.85
Labor - Contract 38,108.58
Labor - AT&T 50,421.98
Engineering - Contract 0.00
Engineering - AT&T 5,773.35
AT&T Payroll Taxes/Benefits 22,703.69
Miscellaneous Expense 16,891.71
Corporate Overhead Loadings 41,383.14
Gross Construction Cost $194,739.30
Plant Betterment Credit 0.00
Salvage Credit 0.00
Depreciation Credit 0.00
------------------
Net Construction Cost $194,739.30
Net Construction Cost
x Ratio of 100.00000% 194,739.30
CIAC 0.00
TAXES 0.00
COST OF MONEY 0.00
Total $194,739.30
Project Start Date MAY , 2019 Project End Date APRIL , 2021
------------------------------
Records available for audit at:
AT&T
1010 N. St. Mary's Street, Finance Department
San Antonio, Texas 78215
210.351.4643
Six Points Urban Villages Central Cluster
C00705
ADDITIONAL COST CITY OF FORT WORTH PROJECT RACE ST A0IDGGV
Print 1
Additional 6,995' of footage added to labor and costs associated with pulling cable through
underground conduit 7,072
Additional 8,407' of footage added to labor and costs associated with removing AT&T aerial facilities
9,053
Print 2
1 Pole removal added labor and associated costs 2,056
Additional labor and costs associated with splicing, testing engineering AT&T facilities 3,285
Print 3
Additional 950' of footage added to labor and additional costs associated with with the removal and
placement of aerial facilities 1,460
Additional labor cost for fastening AT&T facilities to utility poles 1,040
Additional material cost 150' of 50PR COPPER CABLE added 215.85
Additional 100' of footage added to labor and costs associated with pulling cable through underground
conduit 101
Additional labor and costs associated with splicing, testing, engineering AT&T facilities 474
Print 4
Labor added for raising/lowering aerial fiber splice case 172
2 pole removals added labor and associated costs 4,112
Additional time added to labor associated with splicing, testing, engineering AT&T facilities 349
Print 5
Additional material cost 200' 100PR COPPER CABLE 299
Additional 275' of footage added to labor and costs associated with for rodding and placing pull string in
conduit 311
Additional labor and associated cost for removal of AT&T facilities 688
Additional labor and costs associated the placement of aerial facilities 275
Additional labor and costs associated with splicing, testing, engineering AT&T facilities 6,874
Print 6
Additional 1,215' of footage added to labor and costs associated with and Boring underground
CABLE/INNERDUCT 10,448
Six Points Urban Villages Central Cluster
C00705
ADDITIONAL COST CITY OF FORT WORTH PROJECT RACE ST A0IDGGV
Additional labor and associated costs for placing COPPER GROUNDING BED for UNDERGROUND
structure 359
Additional labor and costs associated with splicing, testing, engineering AT&T facilities
611
Print 7
Additional labor and costs associated with splicing, testing, engineering AT&T facilities
138
Print 8
Additional labor and costs associated with splicing, testing, engineering AT&T facilities
155
Print 10
Additional labor and costs associated with splicing, testing, engineering AT&T facilities
5,355
Six Points Urban Villages Central Cluster
C00705
FORT WORTH
Routing and Transmittal Slip
Transportation & Public Works
Department
DOCUMENT TITLE: Six Points Urban Villages Central Cluster:
AT&T Utility Relocation Contract Amendment #1
M&C N/A
DATE: 7-05-2023
TO:
1.
Alexiz Ramirez
2.
Utility Owner -AT&T
3.
Chad Allen
4.
Lissette Acevedo
5.
Patricia Wadsack
6.
Lauren Prieur
7.
Doug Black
8.
William Johnson
9.
Jannette Goodall
10.
TPW Contracts
CPN C00705 CSO #
INITIALS
- review
- signature pmlol
- signature
- review
- review PLW
PAW
- signature
WLLP-
- signature d
wb
- signature -
- signature ��
52153 DOC#
DATE OUT
Jul 11, 2023
Jul 27, 2023
Aug 6, 2023
Aug 6, 2023
Aug 11, 2023
Aug 11, 2023
Aug 15, 2023
Aug 15, 2023
Aug 16, 2023
1
DOCUMENTS FOR CITY MANAGER'S SIGNATURE: All documents received from any and all City
Departments requesting City Manager's signature for approval MUST BE ROUTED TO THE
APPROPRIATE ACM for approval first. Once the ACM has signed the routing slip, David will review
and take the next steps.
NEEDS TO BE NOTARIZED: ❑ Yes ❑ No
RUSH: ❑ Yes ❑ No SAME DAY: ❑ Yes ❑ No NEXT DAY: ❑ Yes ❑ No
ROUTING TO CSO: ❑ Yes ❑ No
Action Required: ❑ Attach Signature, Initial and Notary Tabs
❑ As Requested
❑ For Your Information
® Signature/Routing and or Recording
❑ Comment
❑ File
Return To: Please calITPW Contracts at ext. 7233 for pick up when completed. Thank you.
Amendment Purpose Statement:
The purpose of this amendment is to pay AT&T for additional utility relocation services performed as
part of the Six Points Urban Village Streetscapes project. The original Letter of Agreement for
Construction Services with AT&T for this project was executed in March of 2019. In January of 2022
when the project was entirely complete, AT&T submitted an invoice to the City for additional utility
relocation work not included in the original contract. After receiving and reviewing back-up information
and costs for the additional services performed, we are now processing this amendment to allow
payment for this work.
Six Points Urban Village Central Cluster
C00705