HomeMy WebLinkAboutContract 58871-CO1CSC No. 58871-COI
FORT WORTH City of Fort Worth
`—' Change Order Request
Project Namel 2022 Bond Year 1 - Contract 4
City Sec # 1 58871
Client Project #(s)l 102930
Project Description
I Reconstruction of existing pavement with proposed water & sanitary sewer on Burton Avenue, Chickasaw Avenue,
Crouch Avenue and Quails Lane.
Contractorl Stabile & Winn, Inc
Change Order#1
1 1
Datel 7/6/2023
City Project Mgr.l Gregory Robbins
City Inspectorl
Cody Horton
Dept. Unit 1: Water
Unit 2: Sewer
Unit 3: Paving
Contract Time
Totals (CD)
Original Contract Amount $2,018,239.50
$1,626,486.50
$3,867,989.00
$7,512,715.00 390
Extras to Date
Credits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Date $2,018,239.50
$1,626,486.50
$3,867,989.00
$7,512,715.00 390
Amount of Proposed Change Order $0.00
$0.00
$0.00
Revised Contract Amount $2,018,239.50
$1,626,486.50
$3,867,989.00
$7,512,715.00 390
Original Funds Available for Change Orders $100,912.00
$81,324.00
$193,399.00
$375,635.00
Remaining Funds Available for this CO $100,912.00
$81,324.00
$193,399.00
$375,635.00
Additional Funding (if necessary)
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT
0.00%
MAX ALLOWABLE CONTRACT
AMOUNT (ORIGINAL CONTRACT COST + 25%)
$9,390,893.75
IN ACCORDANCE WITH THIS CHANGE ORDER REQUEST, THE CONTRACTOR SHALL: Furnish all labor and material as per the attached proposed Change Order #1.
This change order provides the necessary pay item quantities to allow for the installation of 6" concrete pavement to match the existing pavement thickness on Crouch
street subsequent to water main connection on the street Cost -
Contractor will use unit prices as bid in Unit 3: Paving
Time - There will be no addtional time for the work.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in
full (both time and money) for all costs arising out of, or incidental to, the above Change Order. The Project/Program Manager signing below
acknowledges that he/she is the person responsible for the monitoring and administration of this contract, including ensuring all performance and
reporting requirements.
Contractor's Company Namem Contractor (Names 11111111PrContract Signature
Stabile & Winn, Inc Jerry Henderson ,/a Ir Aug 4, 2023
Inspector/Inspection Supervisor
Date
Project and Contract Compliance Manager
Date
Aug 3, 2023
C—
Aug 3, 2023
Program Manager
Date
Senior Capital Project Officer
Date
�v
Aug 412023
Aug 7, 2023
Assistant Director (Dept)
Date
Director, Contracting Department (Dept)
Date
' aP�ic
P . is L. Wadfack
Aug 16, 2023
�.�-
Aug 16, 2023
sistant City Attomey
Date
Assistant City Manager
Date
(
Aug 17, 2023
i�
Aug 17, 2023
Council Action (if required)
4ovvopbn M&C Number I I M&C Date Approved
ATTEST: �r oo
*—o
�pCo o
oJannette Goodall, City Secretary poo=d
p$0 44 000l'o aO"v
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
City of Fort Worth
Change Order Additions
Project Name 1 2022 Bond Year 1 - Contract 4
Client Project # 1 102930
Contractorl Stabile & Winn, Inc
I I tM UtS(:HIF' I ION
415 3213.0101 6" Conc Pavement
47 3211.0502 8" Lime Treatment
48 3211.0400 Hydrated Lime
I City Sec # 1 58871
1
PMl Gregory Robbins l Inspectorl Cody Horton l
Change Order Submittal # Date 1 7/6/2023
ADDITIONS
ULP I Oty Unit Unit Cost I otal 1
Unit 1: Water 99.000000ou SY $87.15 $8,827.851
Unit 1: Water 105.00000000 SY $4.80 $504.001
Unit 1: Water 2.00000000 TN $323.50 $647.001
1
1
1
1
1
1
1
1
1
1
I
1
1
1
I
I
I
I
I
I
I
I
I
I
I
I
I
I
1
I
1
I
1
1
1
1
1
1
I
I
I
I
I
I
I
I
I
I
I
I
I
I
1
I
1
1
1
1
I
1
1
1
I
I
I
I
I
Unit 1: Water $9,778.851
Unit 2: Sewer $0.001
Unit 3: Paving $0.001
I I
Change Order Additions Page 2 of 7
I Sub Total Additions 1 $9,778.851
Change Order Additions Page 3 of 7
FORT WORTH
1,
Project Name 1 2022 Bond Year 1 - Contract 4
ClientProject# 1 102930
Contractorl Stabile & Winn, Inc
HEM tM UEbUKIP I IUN
45 9999.0001 Water Construction Allowance
City of Fort Worth
Change Order Deletions
City Sec # 1 58871 1
1
l PMl Gregory Robbins l Inspector] Cody Horton l
Change Order Submittal # 0 Date 1 71612023 1
DELETIONS
Uf=P I Uty Unit Unit Uost I otal
Unit 1: Water 0.0977885U LS $100,000,0U $9,778.85
Unit 1:Water $9,778.85
Unit 2:Sewer $0.00
Unit 3: Paving $0.00
Change Order Deletions Page 4 of 7
I Sub Total Deletions 1 $9,778.851
Change Order Deletions Page 5 of 7
MISBE for this Change Order
M/SBE Sub Type of Service Amount for this CO
Total $0.00
Previous Change Orders
CO# DATE AMOUNT
Total 1 $0.00 1
FORTWORTH,
Routing and Transmittal Slip
Transportation & Public Works Department
DOCUMENT TITLE: Change order #1— 2022 Bond Year 1 — Contract 4
M&C: CPN: 102930 CSO: 58871 DOC#:
Date:
To:
Name
Department
Initials
Date Out
1,
Filogonio Munoz
TPW - signature
Aug 3, 2023
2.
Jerry Henderson
Stabile & Winn, Inc -
T
Aug 2023
g
signature
JH
3.
Cody Horton
TPW - signature
cfll
Aug 3, 2023
4.
Christian Cardona
TPW - signature
el.—
Aug 3, 2023
5.
Gregory Robbins
TPW - signature
Aug 4, 2023
6.
Mary Hanna
TPW - signature
Aug 7, 2023
7.
Patricia Wadsack
TPW - signature
PL TLW
Aug 16, 2023
8.
Lauren Prieur
TPW - signature
�
Aug 16, 2023
9.
Doug Black
Legal - signature
dWdwb
Aug 17, 2023
10.
William Johnson
CMO - signature
W
Aug 17, 2023
11.
Jannette Goodall
CSO - signature
,SG
Aug 17, 2023
12.
TPW Contracts
DOCUMENTS FOR CITY MANAGER'S
SIGNATURE:
All documents received from any
and all City Departments requesting
City Manager's signature for approval MUST
BE ROUTED
TO THE
APPROPRIATE ACM for approval first. Once the ACM has signed
the routing slip,
David
will review and take the next steps.
NEEDS TO BE NOTARIZED: []YES ®No
RUSH: ®YES ❑No SAME DAY: ❑YES ❑No NEXT DAY: ❑YES ®No
ROUTING TO CSO: ®YES ❑No
Action Reauired:
❑ As Requested
❑ For Your Information
® Signature/Routing and or Recording
❑ Comment
❑ File
❑ Attach Signature, Initial and Notary Tabs
Return To: TPWContractsaFortWorthTexas.Lyov at ext. 7233 for pick up when completed.
Thank you!