HomeMy WebLinkAboutIR 0730INFORMAL REPORT TO CITY COUNCIL MEMBERS
No. 23-0730
To the Mayor and Members of the City Council
August 15, 2023
Page 1 of 8
SUBJECT: MONTHLY DEVELOPMENT ACTIVITY REPORT
This Informal Report is in response to the City Council's request to receive a monthly update on
development activity within the City and the measures staff are using to improve the
development process. Staff also generates a monthly report to keep the Council informed of the
volume of development activity, process improvements and staff's performance in implementing
changes and improving the delivery of plan review and permits. This activity report consists of
metrics associated with building permits, infrastructure, stormwater development, and water
development plan review. It provides updates on continuous development process improvement
efforts. The monthly Development Activity Report is attached for your use and information. The
following highlights are for the months of June and July 2023:
June 2023 Highlights
Building Permits
The City's updated Transportation Impact Fees went into effect on June 1, 2023. Projects with
approved final plats and with building permits accepted on or before May 31, 2023, are able to
utilize the previous fee schedule. As a result, there was an increase in permit activity in May.
Permits
Jun
2023*
May
2023
Mo - Mo
Change
Jun
2022
Yr - Yr
Change
New Commercial Permits Issued
96
82
17%
52
85%
New Multifamily Permits Issued (1)
11
35
-69%
64
-83%
New Detached Multifamily Permits Issued (2)
0
67
-100%
4
-100%
New Residential Dwelling Permits Issued (3)
730
847
-14%
570
28%
Total New Permits Issued (4)
837
1,031
-19%
690
21%
Total Commercial Valuation ($ Millions)
(incl. new, remodels & additions)
$253M
$264M
-5%
$211M
20%
New Commercial Permit Apps Received (5)
33
58
-43%
33
0%
New Multi -family & Detached Multi -family
Apps Received(5)
8
124
-94%
24
-67%
New Residential Dwelling Apps Received (5)
658
825
-20%
837
-21%
Data as of July 3, 2023
(1) Includes apartments and Commercial Townhouse apartments
(2) Includes detached multifamily (i.e. single family for rent) properties- Data tracked as of Jan 2022
(3) Includes duplexes, townhomes on a single lot, single family and single family model homes (excludes Pool/Spa and Non -
Dwelling Strucures)
(4) Excludes New Non -Dwelling Structures and Pool/Spa
(5) New Commercial, New Multi -family & Detached Multi -family and New Residential Dwelling applications received only includes
new building permit applications
ISSUED BY THE CITY MANAGER FORT WORTH, TEXAS
INFORMAL REPORT TO CITY COUNCIL MEMBERS
No. 23-0730
To the Mayor and Members of the City Council
August 15, 2023
Page 2 of 8
SUBJECT: MONTHLY DEVELOPMENT ACTIVITY REPORT
Development Support Services
• The Overall Customer Service Satisfaction was 90% for either Very Positive or Somewhat
Positive for June 2023, based on 66 out of 73 responses. This is up from 85% for either Very
Positive or Somewhat Positive for May 2023, based on 51 out of 60 responses. Out of 73
respondents only 12 people provided feedback. Majority of the feedback was centered around
frustration on the layout of the website and website being too complex. Refer to Chart A and
Chart B, below.
• In June 2023, no customers responded to the Inspection team customer service survey.
• Chart A shows survey responses for June 2023.
_..-. . A: How wo I you rate the quality of your customer service experience?
100.00% 90.41% 90.00%
80.00%
60.00%
40.00%
20.00% No
1.37% 0.00% 5.48/° 0.00% 2.74% 0.00%
0.00%
Very Positive + Somewhat Somewhat Negative Very Negative
Positive ■ City of Fort Worth Customers ■ CFW Goal
Jun23
• Chart B shows commercial vs residential survey responses for June 2023.
Chart B: Overall, how would you rate the quality of your customer service experience?
100.00% 95.00% 90.00%
� 84.85%
80.00%
60.00%
40.00%
20.00%
0.00%
Jun23
0.00% 3.03% 0.00%
Very Positive + Somewhat Neutral
Positive E City of Fort Worth Customers (Com.)
2.50% 9.09%0.00% 2.50% 3.03% 0.00%
Somewhat Negative Very Negative
City of Fort Worth Customers (Res) ■ CFW Goal
ISSUED BY THE CITY MANAGER
FORT WORTH, TEXAS
INFORMAL REPORT TO CITY COUNCIL MEMBERS
No. 23-0730
To the Mayor and Members of the City Council
August 15, 2023
Page 3 of 8
SUBJECT: MONTHLY DEVELOPMENT ACTIVITY REPORT
X-Team Building Plan Review
X-Team Activity
Jun-23*
May-23
Difference Moe
Jun-22
Difference
X-Team Applications
14
18
-22%
16
-13%
Conferences Held
16
12
33%
19
-16%
Building Permits Issued
13
28
-54%
20
-35%
Data as of July 1, 2023
X-Team Activity Totals
YTD 2023*
CY 2022
CY 2021
Total
X-Team Applications
87
183
139
409
Conferences Held
68
136
68
272
Building Permits Issued
123
573
228
924
Data as of July 1, 2023
• As of July 1, 2023, there were 165 pending X-Team building permits. Pending status includes
permits in plan review, awaiting client reply, or permits that have been approved and are
waiting on the customer to pay fees.
Buildina Plan Review
• On July 1, 2023, the review times to first comment were as follows:
Days to first review Commercial Plans Actual 10 Days Goal 7 Days
Days to first review Residential Plans Actual 6 Days Goal 7 Days
Department -wide Building Permit Review
• For June 2023, the average departmental review times to first comment were as follows:
Days to first review Commercial Plans
Days to first review Residential Plans
Average 4 Days Goal 7 Days
Average 4 Days Goal 7 Days
ISSUED BY THE CITY MANAGER
FORT WORTH, TEXAS
INFORMAL REPORT TO CITY COUNCIL MEMBERS
No. 23-0730
To the Mayor and Members of the City Council
August 15, 2023
Page 4 of 8
SUBJECT: MONTHLY DEVELOPMENT ACTIVITY REPORT
Development Activity Applications
Type
Jun-23*
May-23
Mo - Mo
Change
Building Permits**
1,623
1,887
-14%
Infrastructure Plans
63
50
26%
Community Facility Agreement
13
15
-13%
Platted Lots (Residential & Non -Residential)
538
271
99%
Plats
42
39
8%
Zoning /Site Plans
23
12
92%
Data as of July 3, 2023
** Incl: New Commercial & Residential, Comm/Res Remodel, Comm/Res Accessory, Comm/Res Addition, Occupancy Change of
Use. etc.
ISSUED BY THE CITY MANAGER
FORT WORTH, TEXAS
INFORMAL REPORT TO CITY COUNCIL MEMBERS
No. 23-0730
To the Mayor and Members of the City Council
August 15, 2023
Page 5 of 8
SUBJECT: MONTHLY DEVELOPMENT ACTIVITY REPORT
July 2023 Highlights
Building Permits
Permits
July
2023
Jun
2023
Mo - Mo
Change
July
2022
Yr - Yr
Change
New Commercial Permits Issued
120
96
173%
67
291%
New Multifamily Permits Issued (1)
22
11
100%
105
-79%
New Detached Multifamily Permits Issued (2)
142
0
-
0
-
New Residential Dwelling Permits Issued (3)
679
730
-7%
636
7%
Total New Permits Issued (4)
963
837
32%
808
37%
Total Commercial Valuation ($ Millions)
(incl. new, remodels & additions)
$284M
$253M
-5%
$441M
20%
New Commercial Permit Apps Received (5)
18
33
-45%
27
-63%
New Multi -family & Detached Multi -family
Apps Received(5)
43
8
438%
18
-
New Residential Dwelling Apps Received (5)
554
658
-17%
510
11%
Data as of Aug 2, 2023
(1) Includes apartments and Commercial Townhouse apartments
(2) Includes detached multifamily (i.e. single family for rent) properties- Data tracked as of Jan 2022
(3) Includes duplexes, townhomes on a single lot, single family and single family model homes (excludes Pool/Spa and Non -
Dwelling Strucures)
(4) Excludes New Non -Dwelling Structures and Pool/Spa
(5) New Commercial, New Multi -family & Detached Multi -family and New Residential Dwelling applications received only includes
new building permit applications
Development Support Services
The Overall Customer Service Satisfaction was 88% for either Very Positive or Somewhat
Positive for June 2023, based on 66 out of 75 responses. This is down from 90% for either
Very Positive or Somewhat Positive for June 2023, based on 66 out of 73 responses. Out of
29 respondents only 20 people provided feedback. Majority of the feedback was positive.
However, there were a few that suggested improving communication and processes. Refer to
Chart A and Chart B, below.
• In July 2023, 1 customer responded very positive under extremely helpful to the Inspection
team customer service survey.
ISSUED BY THE CITY MANAGER
FORT WORTH, TEXAS
INFORMAL REPORT TO CITY COUNCIL MEMBERS No. 23-0730
To the Mayor and Members of the City Council August 15, 2023
�aT�• Page 6 of 8
x�
SUBJECT: MONTHLY DEVELOPMENT ACTIVITY REPORT
1875
• Chart A shows survey responses for July 2023.
Chart A How would you rate the quality of your customer service
experience?
100.00% 88.00% 90.00%
80.00%
60.00%
40.00%
20.00%
5.33% 0.00%
0.00%
Very Positive + Somewhat Neutral
Positive
5.33% 0.00% 1.33% 0.00%
Somewhat Negative Very Negative
■ City of Fort Worth Customers ■ CFW Goal
• Chart B shows commercial vs residential survey responses for July 2023.
Chart B Overall, how would you rate the quality of your customer
service experience?
100.00% 88.38% 87.51 % 90.00%
80.00%
60.00%
40.00%
20.00% 6.98% ° 9.38%
3.13 /00.00% 2.33% 0.00% 2.33% 0.00% 0.00%
0.00%
Very Positive + Somewhat Neutral Somewhat Negative Very Negative
Positive
Jul 23 ■ City of Fort Worth Customers (Com.) i City of Fort Worth Customers (Res) ■ CFW Goal
X-Team Building Plan Review
X-Team Activity
Jul-23*
Jun-23
Difference Moe
Jul-22
Difference
X-Team Applications
14
14
0%
14
0%
Conferences Held
11
16
-31 %
10
10%
Building Permits Issued
12
13
-8%
32
-63%
Data as of Aug 1, 2023
ISSUED BY THE CITY MANAGER
FORT WORTH, TEXAS
INFORMAL REPORT TO CITY COUNCIL MEMBERS
No. 23-0730
To the Mayor and Members of the City Council
August 15, 2023
Page 7 of 8
SUBJECT: MONTHLY DEVELOPMENT ACTIVITY REPORT
X-Team Activity Totals
YTD 2023*
CY 2022
CY 2021
Total
X-Team Applications
101
183
139
423
Conferences Held
79
136
68
283
Building Permits Issued
135
573
228
936
Data as of Aug 1, 2023
• As of Aug 1, 2023, there are 177 pending X-Team building permits. Of the 177 Pending X-
Team permits 10 are in Initial Plan Review, 159 are Awaiting Client Reply, and 8 permits have
been Approved with payment pending.
Building Plan Review
• On July 1, 2023, the review times to first comment were as follows:
Days to first review Commercial Plans Actual 9 Days Goal 7 Days
Days to first review Residential Plans Actual 5 Days Goal 7 Days
Department -wide Building Permit Review
• For June 2023, the average departmental review times to first comment were as follows:
Days to first review Commercial Plans
Days to first review Residential Plans
Development Activity Applications
Average 4 Days Goal 7 Days
Average 2 Days Goal 7 Days
Type
Jul-23*
Jun-23
Mo - Mo
Change
Building Permits**
1,435
1,623
-12%
Infrastructure Plans
54
63
-14%
Community Facility Agreement
9
13
-31 %
Platted Lots (Residential & Non -Residential)
163
538
-70%
Plats
23
42
-45%
Zoning /Site Plans
12
23
-48%
Data as of Aug 1, 2023
** Incl: New Commercial & Residential, Comm/Res Remodel, Comm/Res Accessory, Comm/Res Addition, Occupancy Change of
Use, etc.
ISSUED BY THE CITY MANAGER
FORT WORTH, TEXAS
INFORMAL REPORT TO CITY COUNCIL MEMBERS
No. 23-0730
To the Mayor and Members of the City Council
August 15, 2023
Page 8 of 8
SUBJECT: MONTHLY DEVELOPMENT ACTIVITY REPORT
Business Process Improvement — Certificate of Occupancy Process
DSD has completed 21 out of the 31 total CO BPI recommendations. Seventeen (17)
recommendations were due by September 30, 2022. Of these 17, 14 have been completed and
3 are 98% complete. There are 14 recommendations due by April 30, 2023. Of these 14, 7 are
complete, 1 is 98%, 1 is 95% complete and 5 are 80% complete.
Business Process Improvement — Pre-Platting/Platting Process
DSD has completed 10 out of the 13 total Pre -Plat/ Platting BPI recommendations. Eleven (11)
recommendations were due by March 31, 2023. Of these 11, 8 are complete, 1 is 95%
complete, 1 is 80%, 1 is 70% complete. There are 2 recommendations due by September 30,
2023. Both of these are complete.
Please contact D.J. Harrell, Development Services Director, at 817-392-8032 or
Dalton. Harrel l(a-)fortworthtexas.gov if you have any questions, concerns or comments.
David Cooke
City Manager
ISSUED BY THE CITY MANAGER
FORT WORTH, TEXAS
FORT WORTH.
Development
Activity Report
INSIDE THIS EDITION
June 2023
Building Permits .........................................
CFA and Platting ........................................
Infrastructure ..............................................
Traffic & Stormwater...................................
Stormwater.................................................
Water..........................................................
Development Process Improvement ..........
Building Permit Comparison
25,000
20,000
4 15,000
E
�5
10,576
11,131
11,320
0 10,000
5,000
0
2013
2014
2015
■ Multi -Family
349
376
349
■ Residential
8,115
8,471
8,792
■ Commercial
2,112
2,284
2,179
All data is in calendar year
New Single -Family Permits
1000
900
800
700
600
500
400
300
200
100
0
-
-
Jan
Feb
Mar
■ 2021
601
480
510
■ 2022
537
606
835
■ 2023
193
278
478
All data is in calendar year
19,537
18,455
16,349
14,717 14,573
12,853 13,467
7,945
2016 2017 2018 2019 2020 2021 2022 YTD
2023
803 487 421 451 552 624 788 323
9,522 10,562 11,687 11,523 13,920 15,552 15,998 6,639
2,528 2,418 2,609 2,599 1,877 2,279 2,751 983
Apr
May
Jun
655
849
906
535
550
570
523
838
718
Jul
Aug
Sep
Oct
Nov
499
331
415
752
656
636
725
720
405
480
Dec
475
250
Development Activity Report
2
New Multi -Family (MF) and Detached Multi -Family (DMF) Permits
400
350
300
250
U)
200
150
0
100
50
i
�IL
Ili
L
_
_�
ra
Jan
Feb Mar
Apr
May
Jun
Jul
2021 MF
1
7 39
13
20
7
18
■2021 DMF
2
7 72
0
232
2
8
■2022 MF
8
44 80
372
9
64
11
■2022 DMF
35
38 70
33
1
4
0
■2023 MF
8
3 14
3
35
11
■2023 DMF
11
34 1
50
67
0
All data is in calendar year
_a_
_
' _
i
Aug
Sep
Oct
Nov
Dec
4
12
5
13
19
2
0
4
0
0
11
1
7
3
14
4
78
221
1
212
New Multi -Family (MF) and Detached Multi -Family (DMF) Valuation
$250.0
$200.0
fA
o $150.0
$100.0
$50.0
Jan
Feb
Mar
2021 MF
$0.4
$62.8
$50.5
■2021 DMF
$0.7
$0.7
$7.5
■2022 MF
$16.1
$31.5
$59.4
■2022 DMF
$2.9
$1.9
$4.6
■2023 MF
$68.0
$1.5
$45.1
■2023 DMF
$5.5
$12.5
$0.7
All data is in calendar year
d
Apr
May
Jun
Jul
$28.1
$160.1
$91.7
$17.6
$_
$26.7
$0.2
$2.3
$127.4
$37.3
$86.1
$212.3
$3.5
$_
$2.0
$_
$1.5
$19.6
$46.9
$14.0
$23.8
$_
1
11-1
L IL -79
Aug
Sep
Oct Nov Dec
$2.7
$27.4
$2.3 $45.6 $55.1
$0.8
$_
$0.4 $_ $_
$81.3
$4.5
$39.6 $32.0 $41.2
$0.2
$9.2
$22.1 $7.0 $46.3
Development Activity Report
3
New Private Development, Non -Residential Commercial Permits*
140
120
100
U) 80
E
0- 60
0
0
40
20
0
Jan
■ 2021
86
■ 2022
98
■ 2023
58
Feb Mar
54 131
101 73
79 95
Apr May Jun
50 83 96
59 45 50
62 79 91
Jul
Aug
Sep
Oct
Nov
Dec
61
126
53
76
113
73
65
101
97
71
50
92
* Excludes all New Multi -family (MF) and Detached Multi -family (DMF), Education, Institutional and Townhouse Apartments. Only
new permits are included in this data set. Excludes additions and remodels.
New Private Development, Non -Residential Commercial Permit Valuation*
200
180
160
140
U) 120
c
0
100
80
60
40
20 'J
0 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
■ 2021 $137 $84 $108 $118 $57 $160 $74 $113 $56 $170 $133 $77
■ 2022 $188 $107 $113 $170 $103 $28 $69 $111 $18 $165 $52 $77
■ 2023 $67 $180 $127 $101 $124 $129
* Excludes all New Multi -family (MF) and Detached Multi -family (DMF), Education, Institutional and Townhouse Apartments.
Only new permits are included in this data set. Excludes additions and remodels.
Development Activity Report
4
New Non -Residential Commercial Permits*
160
140
120
100
E
80
r
O
4t 60
40
20
0
_..
—.
Jan
Feb
Mar
Apr
May
Jun Jul
■ 2021
86
50
134
52
86
98 61
■ 2022
98
102
76
83
60
54 67
■ 2023
60
80
95
65
82
96
1
j
6011 —.
A =I
Aug Sep
Oct Nov Dec
131 53
80 113 74
104 100
73 60 92
* Excludes Multi -family (MF) and Detached Multi -family (DMF), New Townhouse Apartments, addition, and remodel permits.
Does include Education and Institutional new permits.
New Non -Residential Commercial Permit Valuations*
$450
$400
$350
$300
o $250
$200
$150
$100
$50
$0 Jan Feb Mar
■ 2021 $137 $96 $134
■ 2022 $188 $107 $114
■ 2023 $71 $182 $84
Apr May Jun Jul Aug Sep Oct Nov Dec
$169 $73 $160 $74 $195 $56 $188 $133 $81
$170 $387 $32 $100 $181 $72 $244 $52 $77
$101 $127 $163
* Excludes New Multi -family (MF), Detached Multi -family (DMF), and Townhouse Apartments, additions and remodels.
All data is in calendar year.
Development Activity Report
5
Total Commercial Valuation*
$600
$500
$400
c
$300
$200
$100
$0 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
■ 2021 $187 $223 $276 $270 $299 $462 $192 $285 $119 $259 $273 $151
■ 2022 $304 $173 $198 $377 $496 $208 $441 $337 $162 $340 $312 $334
■ 2023 $200 $240 $190 $196 $264 $253
* Data includes new, additions, and remodel permits for all commercial types including MF, DMF, Education and Institutional. All
data is in calendar year.
Permit Valuation Comparison
Current
Prev.
Difference
Prev.
Diff. Y-Y
Year to Date CY22 vs CY23
Month
Month
Category
M-M
Year
%
New SF
-117
+150
-606
Permits
718
835
568
3,025 3,631
-14%
+26%
-17%
-$20.8M
+$34.M
-$100.4M
New SF
$134.9M
$155.6M
$100.8M
$582.6M
$683.OM
Value
-13%
+34%
-15%
New
-77
-13
-218
Comm
107
184
120
997
1,215
Permits
-42%
-11 %
-18%
New
+$39.27M
+$89.3M
-$430.2M
Comm
$209.5M
$170.3M
$120.2M
$965.2M
$1,395AM
Value
+23%
+74%
-31 %
Development Activity Report
0
Large Commercial Projects*
LargeJune
Commercial Projects
Address
Council
District
Project Name
Work Description
Valuation
3153 Sandy Ln &
Various
5
Mid -Cities
New Commercial Construction of
$36,930,418
Addresses
Logistics
Warehouse Bldgs A, B,C, D & E
13853 & 13860
New Commercial Construction of Apt.
Stonehawk Way
5
The Crawford
Complex with 280 Units Total. Ph 1A, 1 B,
$30,897,332
1 C, 1 D, 2A, 2B & Parking Garage
1633 Mistletoe
9
BSW 5 Story
New Commercial Construction of Parking
$30,000,000
Blvd
Parking Garage
Garage
1310 Crawford St
8
Magnolia Lofts
New Commercial Construction of
$17,000,000
Apartment Complex with 67 Units Total
3863 SW Loop
6
UTEX Ft Worth
New Commercial Construction of Storage
$8,000,000
820 Fwy
Self Storage
Facility
2120 Cantrell
2
W.R. Meadows
New Commercial Construction of
$6,501,000
Sansom Rd
Warehouse
3250 Tracewood
4
Parkside East
New Commercial Construction of Retail
$3,097,000
Way
Shell Bldg E
1200 Intermodal
7
Cargill Inc
Commercial Remodel of Bldg
$2,576,567
Pkw
8400 Calmont
3
Double Eagle
New Commercial Construction of an
$1,800,000
Ave
Office
3781 Thompson
4
Foursquare
New Commercial Construction of a
$1,780,000
Rd
Community Center
Community Center
15301 N Beach St
7
Alliance Center
Commercial Remodel of Warehouse
$1,780,000
North
4729 Saint
3
Montserrat
Commercial
New Commercial Construction of Shell
$1,750,000
Amand Cir
Development
Bldg
2755 Ellis Ave
2
Suvida Healthcare
Commercial Remodel & Change of Use of
$1,672,440
Retail Clinic Space
4001 Mark IV
2
M & M
Commercial Remodel of Industrial
$1,575,515
Pkwy
Manufacturing
Manufacturing Bldg
2908 Chapel
3
McDonald's
New Commercial Construction of a
$1,500,000
Creek Blvd
Restaurant
2513 Rodeo
Plaza
2
Lone Spur Cafe
Commercial Remodel of Restaurant
$1,500,000
9120 North Fwy
4
Planet Fitness
Commercial Remodel of Gym
$1,450,000
9937 Blue Mound
7
Knox Street
New Commercial Construction of Shell
$1,400,000
Rd
Partners
Bldg
300 Throckmorton
9
Varghese
Commercial Remodel of Office Bldg
$1,396,848
St
Summersett
6301 N Beach St
4
Chipotle
New Commercial Construction of a
$1,250,000
Restaurant
100 Throckmorton
9
Cross First Bank
Commercial Remodel of Office Bldg
$1,216,237
St
5601 Bryant Irvin
6
MB Fort Worth
Commercial Remodel of Auto Repair
$1,098,557
Rd
Lockers
Shop
4150 International
3
Creative Solutions
Commercial Remodel of Office
$1,041,000
Plaza
* Excludes Institutional and Educational Uses
Development Activity Report
Development Activity Report
New Residential Permit Heat Map
.f
N
'i']
vie ` o "'rd. �
i ~
F 1 J. ,rp
P# 4
ti I
k x .GCS
o C1
8
CO
04
4 �
.-h
a +199 O O p .
Pwhif t �i8rcari. 4 $ p DallEe
.. . 4 O O
%a# a 61 o a o f
sp
49
Oy0 p p
�gb aL— '
F i $a o4 # I ¢
OYY Q
O Reedientkd Eulld.tg PefirAq June 20M3 Exiew CIIy Lffr '
L� O Re-atliemttel Bulld tg Pmftia JurtB 2025- Interibf City Lrttah
)Aunibpal UtIIty al5trCI& (lAUN)
Am In ETJ Under DeWopmemtAgreenerl
clo-5
�10.15
�15.211
JGM94o W20 • 25
—Trudy RMer
0 25 25 5 dry 10 0CFWClyLimit
Miles
Development Activity Report
9
CFA Project Overview
$40.0
$35.0
$30.0
$25.0
U)
C:
=0 $20.0
$15.0
$10.0
$5.0
Jan Feb Mar Apr May June July Aug Sept Oct Nov Dec
m2021 $7.3 $21.4 $21.1 $6.3 $16.9 $23.6 $14.7 $22.3 $20.4 $14.7 $13.0 $14.2
m2022 $16.5 $30.5 $29.3 $27.5 $1.7 $24.5 $28.4 $13.8 $34.8 $7.7 $16.9 $14.1
m2023 $16.4 $12.4 $21.7 $32.9 $19.1 $12.9
All data is in calendar year
Platted Lots Overview
1800
1600
1400
1200
1000
800
0 600
400
200
0
Jan Feb Mar Apr May June July Aug Sept
p■
1 '221 Res 549 148 711 460 08 1078 1210 !918 W
. .. ...... ............... ...... ..... ...... .... .......... ..... .............. ......
I N 0fl-R 29 20 15 24 18 : 19 0 14 6
....... ....... ............. ................... ................ ....... ...... ............................
* '22 Res 1551.........947 99 841) 925 511 Big 20.......................
4 1493
....... ............. ... ....... ......
* '22 Noii-R: 27 121 9 19 27 112 33 12 53
.... ...................... ....... .......
.01 23 Res :....390.......243 165 905 216 516
.... . . ........... .......... . . . ...... ............
m '23 Non-R: 5 21 19 - 13 55 22
... .............. ....... ....... ........ ....... ........ ...... .... .........
All data is in calendar year
Development Activity Report
Oct Nov Dec
Dec
370 6 049
...... : ................
7 6 11
...........
959 5W 945
............ . .............
18 21 44
........... ................ . ..............
................ .. .............
...............
10
IPRC Overview*
IPRC Overview Report
Cycles Complete
52
54
52
52
26
Total Projects
181
153
173
240
77
Avg. Project Total Per Cycle
3.5
2.8
3.3
4.6
2.96
Total Accepted Projects
143
136
132
166
72
Plan Rev. & Ret w/n 14 days
94%
99%
98%
84%
83%
All data is in calendar year
IPRC Quarterly Details*
Cycles Complete
13
13
13
13
13
Total Projects
57
54
60
46
31
Avg. Projects Per Cycle
4.4
4.2
4.6
3.5
2.4
Avg. Accepted Projects Per Cycle
3.1
3.0
2.0
2.7
2.8
Plan Rev. & Ret w/n 14 days
72%
80%
83%
85%
83%
*All data is in calendar year
Public Infrastructure Residential Projects
$30.0
$25.0
$20.0
c
$15.0
$10.0
$5.0
$
Jan
Feb
Mar
Apr
May
Jun Jul
■2021
$2.6
$19.5
$16.3
$0.4
$18.3
$22.9 $12.0
■2022
$16.5
$24.3
$25.3
$27.2
$0.3
$13.0 $18.2
■2023
$14.1
$9.6
$16.3
$21.6
$7.8
$4.3
All data is in calendar year
11 1_
Aug Sep Oct
$13.4 $19.3 $4.3
$12.1 $27.60 $2.3
Nov
$13.0
$14.7
11
Dec
$4.5
$12.4
Development Activity Report
Public Infrastructure Commercial Projects
$4.5
$4.0
$3.5
$3.0
o $2.5
$2.0
$1.5
$1.0
$0.5 - L L - 16
$ Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
■2021 $- $0.2 $1.7 $0.8 $0.8 $0.2 $0.1 $1.5 $0.7 $0.1 $0.1 $0.4
■2022 $- $3.9 $1.5 $0.1 $1.2 $0.5 $- $0.5 $0.1 $1.4 $0.9 $0.2
■2023 $1.3 $0.2 $3.8 $3.6 $1.1 $1.9
Jan - Jun 122 $7.21VI Jan - Jun 2023 $11.91VI.. 1' Increase
All data is in calendar year
Public Infrastructure Industrial Projects
$10.0
$9.0
$8.0
$7.0
$6.0
0
$5.0
$4.0
$3.0
$2.0
$1.0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
■2021 $4.3 $1.2 $2.2 $3.3 $- $- $0.6 $4.0 $- $5.4 $- $1.0
■ 2022 $- $- $0.1 $- $0.1 $8.6 $3.7 $0.3 $5.7 $2.4 $0.2 $0.1
■2023 $1.0 $0.1 $0.9 $1.7 $0.1 $0.4
All data is in calendar year
Development Activity Report 12
Public Infrastructure Multi -Family Projects
$12.0
$10.0
$8.0
o $6.0
$4.0
$2.0
$ Jan Feb Mar Apr May Jun Jul Aug Sep
■ 2021 $0.4 $0.4 $0.3 $0.8 $0.2 $- $2.0 $2.9 $-
■2022 $- $2.4 $0.2 $- $0.2 $1.8 $4.3 $0.9 $1.4
■2023 $0.1 $1.8 $- $1.0 $10.1 $0.6
All data is in calendar year
Public Infrastructure Institutional Projects
$2.5
$2.0
$1.5
N
c
0
$1.0
$0.5
$
Jan
Feb
Mar
Apr
May
Jun
Jul Aug
Sep
■ 2021
$-
$-
$-
$-
$-
$-
$- $0.4
$0.3
■ 2022
$-
$-
$-
$0.2
$0.1
$0.6
$2.3 $0.0
$-
■ 2023
$-
$0.6
$0.8
$-
$-
$0.1
All data is in calendar year
1
.
Oct Nov
Dec
$5.0 $-
$7.7
$- $0.5
$1.5
Oct
Nov Dec
$-
$- $0.6
$0.1
$0.6 $-
Development Activity Report
13
Traffic Review Performance
Traffic (TIA) Study Review Performance*
Newly Submitted Traffic Studies
CY'22 YTD '23 Jun '23
46 31 2
Traffic Submittal Review Cycles Completed
41 27 1
Avg. Review Time in Days for Completed Traffic Submittals (City)
17.9 11.5 6
Avg. Traffic Study Iterations (City)**
1.3 1.4 1
*TIA Study data supplied only for CY'22 & CY'23
**A study can be submitted multiple times prior to the reported month before being approved
Stormwater Review Performance
Stormwater Submittal Review Cycles Completed
1,246
1,643
731
103
Avg. Review Time (days)
7.4
7.2
7.2
6.3
% completed in 10 business days or less
93.9%
97.5%
93.2%
95.2%
Avg. IPRC Review Iterations (City)
2.7
2.4
3
3.1
Avg. Drainage Studies Iterations (City)*
3.1
3.2
3.8
3.8
Overall Customer Satisfaction Rating (1-5 scale)
3.6
4.6
4
2
Num. of Surveys Taken
18
24
10
1
*Item tracked as a result of HB 3161
New Stormwater Submissions
U
rn
70
60
50
40
30
20
10
0
—
io
Jan
Feb
Mar
Apr
May
Jun Jul
■ 2021
26
26
39
26
35
39 47
■ 2022
39
50
67
49
40
55 48
■ 2023
30
35
47
33
23
33
All data is in calendar year
Aug Sep Oct Nov Dec
36 38 37 49 42
46 40 34 43 38
Development Activity Report
14
Stormwater Pipeline Number of Reviews
250
Ibu
0 Ishii libbLLUNIII
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
'22 '22 '22 '22 '22 '22 '23 '23 '23 '23 '23 '23
■ Reviews in process 196 196 192 186 200 209 193 168 199 179 172 176
■ Reviews with City 67 52 67 44 34 42 37 38 66 63 45 40
Stormwater Pipeline Average Days for Review
.el
50
3: 40
A)
a�
30
0
W
p 20
10
0
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Feb Mar
Apr
May
Jun
'22
'22
'22
'22
'22
'22
'23
'23 '23
'23
'23
'23
■Avg. age of Reviews
4
5
3
5
5
9
6
7 5
7
3
7
with City (Days)
■ Avg. age of Reviews
27
29
29
29
24
30
34
38 31
27
28
29
with Developer (Days)
Development Activity Report
15
Water/Sewer Study Review Performance
Water Study Review Performance
Newly Submitted Water Studies
CY'22
139
YTD '23
56
Jun '23
5
Water Submittal Review Cycles Completed
258
80
20
Avg. Review Time in Days for Completed Water Submittals (City)
14.4
9.7
10.1
Avg. Water Study Iterations (City)*
2.0
1.9
2.5
StudySewer •
Newly Submitted Sewer Studies
138
54
4
Sewer Study Review Cycles Completed
266
82
20
Avg. Review Time in Days for Completed Sewer Submittals (City)
14.3
8.2
9.5
Avg. Sewer Study Iterations (City)*
1.9
1.7
2
* A study can be submitted multiple times prior to the reported month before being approved
Water/Sewer Studies in Process
Water Study Reviews in Process
FebWater
34
Mar
30
Apr
32
May
40
Jun
37
Water Study Reviews in Process with City
9
5
6
12
10
Water Study Reviews in Process with Owner
25
25
26
28
27
Avg. Water Study Review Completed — time with City (Days)
6.7
13.4
4.1
10.1
10.1
Avg. Water Study Review Completed — time with Owner (Days)
Sewer Study Reviews in Process
5.7
FebSewer
35
9.7
Mar
28
8.2
Apr
34
7.3
May
39
1 21.9
Jun
33
Sewer Study Reviews in Process with City
8
4
7
12
6
Sewer Study Reviews in Process with Owner
27
24
27
27
27
Avg. Sewer Study Review Completed — time with City (Days)
17.7
10.3
2.6
10.6
9.5
Avg. Sewer Study Review Completed — time with Owner (Days)
23.4
12.8
14.7
0*
9.3
*Studies either only had one submittal or when comments were provided the customers responded on the same day
Development Activity Report
16
Department/
Staff Assigned
Accela Improvements Development
Services, ITS
Development •
Development
Update and republish process trees Services, Water,
and TPW
Status
The new PDC record and the improved Plan Check
Deficiency Report went live on 7/2/2023 along with platting
Accela workflow notifications.
• ••
Project Facilitation team has completed and published to
the website 16 of the 18 process trees. The remaining
trees are Water Miscellaneous Projects and IPRC. Both
trees are nearing completion and will be finished and
published on the website in July 2023.
DSD has completed 21 out of the 31 total CO BPI
Lean process evaluation of the
recommendations. Seventeen (17) recommendations
Certificate of Occupancy Process
Development
were due by September 30, 2022. Of these 17, 14 have
Report Completed: May 2022; Rev.
Services
been completed and 3 are 98 /o complete. There are 14
recommendations due by April 30, 2023. Of these 14, 7
Aug 2022.
are complete, 1 is 98%, 1 is 95% complete and 5 are 50%
complete.
DSD has completed 10 out of the 13 total Pre -Plat/
Lean process evaluation of the
Platting BPI recommendations. Eleven (11)
Pre -Plat/ Platting process
Development
recommendations were due by March 31, 20230. Of these
Services
11, 8 are complete, 1 is 95% complete, 1 is 80 /o, 1 is 70%
Report Completed: Sept 2022
complete. There are 2 recommendations due by
September 30, 2023. Both of these are complete.
City staff has initiated preliminary discussions with Denton
Update Interlocal Agreements with 2 Development and Tarrant County. Denton to read through the
of the 5 adjoining counties covering agreement and provide feedback. Tarrant County
plat regulations in the City of Fort Services, TPW, contacts have left and looking to make connections with
Worth ETJ and Legal new staff to discuss the process moving forward. Next
meeting dates TBD.
Consultant team is working to complete the initial draft of
the Infill Development SO Chapter by August 2023. The
City has assembled a Technical Committee made up of
Infill Development Subdivision Project Platting senior level decision makers representing various
development review teams who will review and comment
on the proposed chapter contacts. Technical Committee
Meetings are scheduled to begin in August 2023.
Comments from stakeholders have been received on the
Urban Forestry Master Plan Urban Forestry first draft of the Master Plan. The second version has
been received, the revised version will be in a revised
format making it easier to read.
Development Activity Report
17
Development Services
D.J. Harrell, Director
Development Services Department
817-392-8032
Dalton.Harrell@fortworthtexas.gov
Building Permits
Evan Roberts, Assistant Director
Development Services Department
Development Building Division
817-392-7843
Evan. Roberts@fortworthtexas.gov
Infrastructure
Victor Tornero, Engineering Manager
Development Services Department
Infrastructure Development Division
817-392-7830
Victor.Tornero@fortworthtexas.gov
Stormwater
Tyson Thompson, Assistant Director
Development Services Department
Infrastructure Development Division
817-392-2120
Tyson.Thompson@fortworthtexas.gov
Water
Chris Harder, Director
Water Department
817-392-5020
Christopher.Harder@fortworthtexas.gov
Development Activity Report 18
FORT WORTH.
Development
Activity Report
V H 1 y AMEvAME I.
INSIDE THIS EDITION Building Permits.......................................................................2
CFAand Platting.....................................................................9
Infrastructure.........................................................................11
Traffic & Stormwater..............................................................14
Stormwater............................................................................15
Water.....................................................................................16
Development Process Improvement......................................17
Building Permit Comparison
25,000
19,537
20,000
18,455
16,349
4 15, 000
13,467
14,717
14 573
E
12,853
a)
10,576
11,131
11,320
9,672
0 10,000
5,000
0
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
YTD
2023
■ Multi -Family
349
376
349
803
487
421
451
552
624
788
510
■Residential
8,115
8,471
8,792
9,522
10,562
11,687
11,523
13,920
15,552
15,998
7,971
■Commercial
2,112
2,284
2,179
2,528
2,418
2,609
2,599
1,877
2,279
2,751
1,191
All data is in calendar year
New Single -Family Permits
1000
900
800
700
600
500
400
300
200
100
0
L
J
Jan
Feb
Mar
Apr
May
Jun
Jul Aug Sep Oct Nov Dec
■ 2021
601
480
510
655
849
906
499 331 415 752 656 475
■ 2022
537
606
835
535
550
570
636 725 720 405 480 250
■ 2023
193
278
478
523
838
718
672
All data is in calendar year
Development Activity Report 2
New Multi -Family (MF) and Detached Multi -Family (DMF) Permits
400
350
300
250
z
E 200
150
0
100
50
0
Jan
Feb Mar
2021 MF
1
7 39
■2021 DMF
2
7 72
■2022 MF
8
44 80
■2022 DMF
35
38 70
■2023 MF
8
3 14
■2023 DMF
11
34 1
All data is in calendar year
Apr
May
Jun
Jul
Aug
13
20
7
18
4
0
232
2
8
2
372
9
64
11
11
33
1
4
0
4
3
35
11
22
50
67
0
142
1 _
I i
Sep
Oct
Nov
Dec
12
5
13
19
0
4
0
0
1
7
3
14
78
221
1
212
New Multi -Family (MF) and Detached Multi -Family (DMF) Valuation
$250.0
$200.0
o $150.0
$100.0
64
$50.0
A L
I �__a
Ad
k
$-
-I
-C -__A
- - -
L-
Jan
Feb
Mar
Apr
May
Jun
Jul
2021 MF
$0.4
$62.8
$50.5
$28.1
$160.1
$91.7
$17.6
■2021 DMF
$0.7
$0.7
$7.5
$-
$26.7
$0.2
$2.3
■2022 MF
$16.1
$31.5
$59.4
$127.4
$37.3
$86.1
$212.3
■2022 DMF
$2.9
$1.9
$4.6
$3.5
$-
$2.0
$-
■2023 MF
$68.0
$1.5
$45.1
$1.5
$19.6
$46.9
$44.0
■2023 DMF
$5.5
$12.5
$0.7
$14.0
$23.8
$-
$25.1
All data is in calendar yea.
Aug
Sep
Oct
Nov
Dec
$2.7
$27.4
$2.3
$45.6
$55.1
$0.8
$-
$0.4
$-
$-
$81.3
$4.5
$39.6
$32.0
$41.2
$0.2
$9.2
$22.1
$7.0
$46.3
Development Activity Report
3
New Private Development, Non -Residential Commercial Permits*
140
120
100
80
E
0- 60
0
40
l
I
20
0
Jan
Feb
Mar
Apr
May
Jun
Jul
■ 2021
86
54
131
50
83
96
61
■ 2022
98
101
73
59
45
50
65
■ 2023
58
79
95
62
79
91
119
Aug Sep Oct Nov Dec
126 53 76 113 73
101 97 71 50 92
* Excludes all New Multi -family (MF) and Detached Multi -family (DMF), Education, Institutional and Townhouse Apartments. Only
new permits are included in this data set. Excludes additions and remodels.
New Private Development, Non -Residential Commercial Permit Valuation*
200
180
160
140
U) 120
c
100
80
60
40
20
'
0
Jan
Feb
Mar
Apr
May
Jun
■ 2021
$137
$84
$108
$118
$57
$160
■ 2022
$188
$107
$113
$170
$103
$28
■ 2023
$67
$180
$127
$101
$124
$129
all 1 j I
Jul Aug Sep Oct Nov Dec
$74 $113 $56 $170 $133 $77
$69 $111 $18 $165 $52 $77
$87
* Excludes all New Multi -family (MF) and Detached Multi -family (DMF), Education, Institutional, and Townhouse Apartments.
Only new permits are included in this data set. Excludes additions and remodels.
Development Activity Report
4
New Non -Residential Commercial Permits*
160
140
120
100
E
L
80
0
4t 60
40
20
0
Jan
■ 2021 86
■ 2022 98
■ 2023 60
jimi I I j I
Feb
Mar
Apr
May
Jun
Jul Aug Sep Oct Nov Dec
50
134
52
86
98
61 131 53 80 113 74
102
76
83
60
54
67 104 100 73 60 92
80
95
65
82
96
120
* Excludes Multi -family (MF) and Detached Multi -family (DMF), New Townhouse Apartments, addition, and remodel permits.
Does include Education and Institutional new permits.
New Non -Residential Commercial Permit Valuations*
$450
$400
$350
$300
o $250
$200
$150
V
$100
$50
$0 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
■ 2021 $137 $96 $134 $169 $73 $160 $74 $195 $56 $188 $133 $81
■ 2022 $188 $107 $114 $170 $387 $32 $100 $181 $72 $244 $52 $77
■ 2023 $71 $182 $84 $101 $127 $163 $88
* Excludes New Multi -family (MF), Detached Multi -family (DMF), and Townhouse Apartments, additions and remodels.
All data is in calendar year.
Development Activity Report
5
Total Commercial Valuation*
$600
$500
$400
c
$300
$200
$100
$0 Jan ' Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
■ 2021 $187 $223 $276 $270 $299 $462 $192 $285 $119 $259 $273 $151
■ 2022 $304 $173 $198 $377 $496 $208 $441 $337 $162 $340 $312 $334
■ 2023 $200 $240 $190 $196 $264 $253 $284
* Data includes new, additions, and remodel permits for all commercial types including MF, DMF, Education and Institutional. All
data is in calendar year.
Permit Valuation Comparison
Difference
Prev.
Diff. Y-Y
Current
Prev. Month
Year Date CY22 vs CY23
CategoryMonth
-46
+36
-572
New SF
672
718
636
3,697 4,269
Permits
-6%
+6%
-13%
-$17.3M
+$7.8M
-$93.6M
New SF
$117.5M
$134.9M
$109.7M
$700.1 M
$793.7M
Value
-13%
+7%
-12%
New
177
+112
-108
Comm
284
107
172
1,281
1,389
Permits
165%
+65%
-8%
New
-$52.5M
-$155.7M
-$577.8M
Comm
$157.OM
$209.5M
$312.7M
$1.1 B
$1.7B
Value
-25%
-50%
-34%
Development Activity Report
0
Large Commercial Projects*
LargeJuly Commercial
Projects
Address
Council
District
Project Name
Work Description
Valuation
10073 Evelyn Blvd,
10052 Ian Ln, 9964
3
Royalton at Sienna
New Commercial Construction of 1 B, 2E,
$29 200,000
Ian Ln, & Various
Hills
3D, 4A, 5C, 6C, 7C & 8B Bldgs 293 Units
Addresses
4851 E Loop 820 S
5
Oak Creek
New Commercial Construction of
$15,400,000
Fwy
Warehouse
3701 Litsey Rd
10
Henry Shein Inc
Commercial Remodel of Warehouse
$6,329,118
2700 N Tarrant Pkwy
7
North City
New Commercial Construction of Shell
$4,700,000
Bldg B1 & B2
2849 Heritage Trace
4
Whiskey Cake
New Commercial Construction of
$4,000,000
Pkwy
Restaurant
119, 123, 115, & 111
7
Merritt
Condominiums /
New Commercial Construction of Bldg
$3,000,000
Merritt St
KinoD
1,2,3,& 4 Apartment Bldgs 36 Units
3051 Northern Cross
4
Novartis CSM
Commercial Remodel of Office Bldg
$2,134,889
Blvd
1124 Bold Ruler Rd
7
Spearpoint
Logistics
Commercial Remodel of Warehouse
$2,000,000
2441 NE Pkwy
2
TTI Inc.
Commercial Remodel of Office Bldg
$2,000,000
11229 Timberland
10
Timberland 7-11 C-
New Commercial Construction of New
$1,500,000
Blvd
Store
Gas Sation
5253 Golden Triangle
7
McDonalds
New Commercial Construction of
$1,500,000
Blvd
McDonalds
549 W Loop 820 N
3
Holt Cat Fort Worth
Commercial Remodel of Auto Repair
$1,500,000
Fwy
Remodel
13901 Aviator Way
10
Alliance Airport —
Hillwood Office
Commercial Remodel of Office Bldg
$1,445,950
16101 Three Wide Dr
7
SAMS DFW3
Commercial Remodel of Warehouse
$1,300,000
2900 Western Center
2
Chick-Fil-A
Commercial Remodel of Restaurant
$1,000,000
Blvd
2900 Western Center
2
Chick-Fil-A
New Commercial Construction of Shade
$1,000,000
Blvd
Structure
15300 Northlink Dr
7
Spec Tenant
Commercial Remodel of Warehouse
$1,000,000
* Excludes Institutional and Educational Uses
Development Activity Report
New Commercial Permit Heat Map
Vase Denton
i EIS
d d �
8
�o
Parker ►_ Tarran "--i
f
r r
0
IS
0 1.25 2.5 5 7.5 10
Miles
Logpnd
• Commercial Building Permits July 2023
0 a-5
0 s-io
10-15
15-20
M 20 - 25
— Trinity River
1= CFW City Limit
I
Development Activity Report
E
Nt:W FWbIUVnI.iai rVrIIIIniI. nt:aL ivi
Wise Denton
• J , � o
O
ti
P
00
OOQ
a o a
Parker Tarrar
a� o $ `D'8
S6 O Q I $
1] 0-k D p C U
83
aQ O s 4
a 0
v
� I r
0
4 #
� Lag�ne
D Residential Suiling Permits July 2023 - Exlerior City Limits
Q 1.25 2.5 5 7.5 14
Miles
O Residential Buildrrg Permlls July 2023 - Interior City Limits
i� Municipal UGldy Districts (MU Ds)
57 Area in ETJ Under DevelopmentAgreement
=0-5
05- 1Q
M10-15
W15-20
M20-25
— Trinity River
0 CFW City Limit
Development Activity Report
I
CFA Project Overview
$40.0
$35.0
$30.0
$25.0
U)
c
g $20.0
$15.0
$10.0
$5.0
$
Jan
Feb
Mar
■ 2021
$7.3
$21.4
$21.1
■2022
$16.5
$30.5
$29.3
■2023
$16.4
$12.4
$21.7
All data is in calendar year
Platted Lots Overview
lil
May
July
i
Aug
Apr
June
$6.3
$16.9
$23.6
$14.7 $22.3
$27.5
$1.7
$24.5
$28.4 $13.8
$32.9
$19.1
$12.9
$12.4
I
Sept
i
Oct
i
Nov
I
Dec
$20.4
$14.7
$13.0
$14.2
$34.8
$7.7
$16.9
$14.1
1800
1600
1400
1200
1000
a 800
0 600
400
2000
Jan
Feb
Mar
Apr
May
June
July
Aug
Sept
Oct
Nov
Dec
'21 Res
549
148
711
460
33
1073
1218
918
16T
370
6
349
'21 Non-R
29
20
15
24
18
19
.........................................................................
6
14
6
7
6
.....
11
■ '22 Res
1551
947
99
840 .....
...
925
511
319......
204
:....
1433
: 358
566
...
945
■ '22 No�R
27
121
..........
9
19 ..:......27
112
33
.................
12
.................
58
:.......
13
....
21
.....
44
■ '23 Res
380
248
.............
165
905
216
516 ........153
..................
.........
..............
.. ........................
■ '23 No i-R
5
21
.................
19
...........
Is
55
:..........
22
:.....................................................
10
............
All data is in calendar year
Development Activity Report
10
IPRC Overview*
IPRC Overview Report
Cycles Complete
52
54
52
52
30
Total Projects
181
153
173
240
93
Avg. Project Total Per Cycle
3.5
2.8
3.3
4.6
3.1
Total Accepted Projects
143
136
132
166
83
Plan Rev. & Ret w/n 14 days
94%
99%
98%
84%
57%
'All data is in calendar year
IPRC Quarterly Details*
Cycles Complete
13
13
13
13
4
Total Projects
54
60
46
31
14
Avg. Projects Per Cycle
4.2
4.6
3.5
2.4
3.5
Avg. Accepted Projects Per Cycle
3
2
2.7
2.8
2.7
Plan Rev. & Ret w/n 14 days
80%
83%
85%
83%
57%
*All data is in calendar year
Public Infrastructure Residential Projects
$30.0
$25.0
$20.0
c
$15.0
$10.0
$5.0
$
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug Sep Oct Nov Dec
■2021
$2.6
$19.5
$16.3
$0.4
$18.3
$22.9
$12.0
$13.4 $19.3 $4.3 $13.0 $4.5
■2022
$16.5
$24.3
$25.3
$27.2
$0.3
$13.0
$18.2
$12.1 $27.60 $2.3 $14.7 $12.4
■2023
$14.1
$9.6
$16.3
$21.6
$7.8
$4.3
$6.2
All data is in calendar year
Development Activity Report 11
Public Infrastructure Commercial Projects
$4.5
$4.0
$3.5
$3.0
o $2.5
$2.0
$1.5
$1.0
$0.5 L -
_ bum_ _ _ _ _
$ Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
■2021 $- $0.2 $1.7 $0.8 $0.8 $0.2 $0.1 $1.5 $0.7 $0.1 $0.1 $0.4
■2022 $- $3.9 $1.5 $0.1 $1.2 $0.5 $- $0.5 $0.1 $1.4 $0.9 $0.2
■2023 $1.3 $0.2 $3.8 $3.6 $1.1 $1.9 $0.1
Jan - July 122 = $7.21VI Jan - July 2023 $12.01VI.. :' Increase
All data is in calendar year
Public Infrastructure Industrial Projects
$10.0
$9.0
$8.0
$7.0
$6.0
0
$5.0
$4.0
$3.0
$2.0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
■2021 $4.3 $1.2 $2.2 $3.3 $- $- $0.6 $4.0 $- $5.4 $- $1.0
■ 2022 $- $- $0.1 $- $0.1 $8.6 $3.7 $0.3 $5.7 $2.4 $0.2 $0.1
■2023 $1.0 $0.1 $0.9 $1.7 $0.1 $0.4 $0.5
All data is in calendar year
Development Activity Report 12
Public Infrastructure Multi -Family Projects
$12.0
$10.0
$8.0
o $6.0
$4.0
$2.0
$
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep Oct
■ 2021
$0.4
$0.4
$0.3
$0.8
$0.2
$-
$2.0
$2.9
$- $5.0
■ 2022
$-
$2.4
$0.2
$-
$0.2
$1.8
$4.3
$0.9
$1.4 $-
■ 2023
$0.1
$1.8
$-
$1.0
$10.1
$0.6
$1.4
All data is in calendar year
Public Infrastructure Institutional Projects
$2.5
$2.0
$1.0
$0.5
1
10
Im1
1_
I
$ _
.
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
■ 2021
$-
$-
$-
$-
$-
$-
$-
$0.4
$0.3
■ 2022
$-
$-
$-
$0.2
$0.1
$0.6
$2.3
$0.0
$-
■ 2023
$-
$0.6
$0.8
$-
$-
$0.1
$-
All data is in calendar year
M mi
Nov Dec
$- $7.7
$0.5 $1.5
Oct Nov Dec
$- $- $0.6
$0.1 $0.6 $-
Development Activity Report
13
Traffic Review Performance
Traffic (TIA) Study Review Performance*
Newly Submitted Traffic Studies
CY'22 YTD '23 July'23
46 33 2
Traffic Submittal Review Cycles Completed
41 27 0
Avg. Review Time in Days for Completed Traffic Submittals (City)
17.9 11.5 N/A
Avg. Traffic Study Iterations (City)**
1.3 1.4 N/A
*TIA Study data supplied only for CY'22 & CY'23
**A study can be submitted multiple times prior to the reported month before being approved
Stormwater Review Performance
Stormwater Submittal Review Cycles Completed
1,246
1,643
835
104
Avg. City Review Time (days)
7.4
7.2
7.3
7.9
% completed in 10 business days or less
93.9%
97.5%
92.4%
87.5%
Avg. IPRC Review Iterations (City)
2.7
2.4
3.1
4.2
Avg. Drainage Studies Iterations (City)*
3.1
3.2
2.7
3.3
Overall Customer Satisfaction Rating (1-5 scale)
3.6
4.6
4
N/A
Num. of Surveys Taken
18
24
10
0
*Item tracked as a result of HB 3161
New Stormwater Submissions
80
70
60
50
W
0
40
N
E
30
U)
0
20
10
0
Jan
Feb
Mar
Apr
■ 2021
26
26
39
26
■ 2022
39
50
67
49
■ 2023
30
35
47
33
All data is in calendar year
1111111
May
Jun
Ili]
Jul Aug Sep Oct Nov Dec
35
39
47 36 38 37 49 42
40
55
48 46 40 34 43 38
23
33
38
Development Activity Report
14
Stormwater Pipeline Number of Reviews
250
200
150
100
50
0
■
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun July
'22 '22 '22 '22 '22 '23 '23 '23 '23 '23 '23 '23
■ Reviews in process 196 192 186 200 209 193 168 199 179 172 176 190
■ Reviews with City 52 67 44 34 42 37 38 66 63 45 40 41
Stormwater Pipeline Average Days for Review
.el
50
3: 40
A)
a�
30
0
p 20
10
■
■
■
■
■
■
■
■
■
■
0
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar Apr
May
Jun
July
'22
'22
'22
'22
'22
'23
'23
'23 '23
'23
'23
'23
■Avg. age of Reviews
4
5
3
5
5
9
6
7 5
7
3
7
with City (Days)
■ Avg. age of Reviews
29
29
29
24
30
34
38
31 27
28
29
25
with Developer (Days)
Development Activity Report
15
Water/Sewer Study Review Performance
Water Study Review Performance
Newly Submitted Water Studies
CY'22
139
YTD'23
69
July'23
13
Water Submittal Review Cycles Completed
258
114
34
Avg. Review Time in Days for Completed Water Submittals (City)
14.4
9.7
10
Avg. Water Study Iterations (City)*
2
1.9
2.8
Sewer Study Review Performance
Newly Submitted Sewer Studies
138
67
13
Sewer Study Review Cycles Completed
266
98
16
Avg. Review Time in Days for Completed Sewer Submittals (City)
14.3
8.2
15.7
Avg. Sewer Study Iterations (City)*
1.9
1.7
2.3
* A study can be submitted multiple times prior to the reported month before being approved
Water/Sewer Studies in Process
Water
Water Study Reviews in Process
Mar
30
Apr
32
May
40
Jun
37
July
39
Water Study Reviews in Process with City
5
6
12
10
11
Water Study Reviews in Process with Owner
25
26
28
27
28
Avg. Water Study Review Completed — time with City (Days)
13.4
4.1
10.1
10.1
10
Avg. Water Study Review Completed — time with Owner (Days)
Sewer
Sewer Study Reviews in Process
9.7
Mar
28
8.2
Apr
34
7.3
May
39
21.9
Jun
33
15.9
July
41
Sewer Study Reviews in Process with City
4
7
12
6
10
Sewer Study Reviews in Process with Owner
24
27
27
27
31
Avg. Sewer Study Review Completed — time with City (Days)
10.3
2.6
10.6
9.5
15.7
Avg. Sewer Study Review Completed — time with Owner (Days)
12.8
14.7
0
9.3
19.1
*Studies either only had one submittal or when comments were provided the customers responded on the same day
Development Activity Report
16
Department/
Staff Assigned
Status
Development The new PDC record and the improved Plan Check
Accela Improvements Services, ITS Deficiency Report went live on 7/2/2023 along with
Platting Accela workflow notifications.
Development All 18 trees have been published to the City's website as
Update and republish process trees Services, Water, of July 2023.
and TPW
DSD has completed 21 out of the 31 total CO BPI
Lean process evaluation of the
recommendations. Seventeen (17) recommendations
Certificate of Occupancy Process
Development
were due by September 30, 2022. Of these 17, 14 have
Report Completed: May 2022; Rev.
Services
been completed and 3 are 98 /o complete. There are 14
recommendations due by April 30, 2023. Of these 14, 7
Aug 2022.
are complete, 1 is 98%, 1 is 95% complete and 5 are 80%
complete.
DSD has completed 10 out of the 13 total Pre -Plat/
Lean process evaluation of the
Platting BPI recommendations. Eleven (11)
Pre -Plat/ Platting process
Development
recommendations were due by March 31, 20230. Of these
Services
11, 8 are complete, 1 is 95% complete, 1 is 80 /o, 1 is 70%
Report Completed: Sept 2022
complete. There are 2 recommendations due by
September 30, 2023. Both of these are complete.
City staff has initiated preliminary discussions with Denton
Update Interlocal Agreements with 2 Development and Tarrant County. Denton to read through the
of the 5 adjoining counties covering agreement and provide feedback. Tarrant County
plat regulations in the City of Fort Services, TPW, contacts have left and looking to make connections with
Worth ETJ and Legal new staff to discuss the process moving forward. Next
meeting dates TBD.
Consultant team is working to complete the initial draft of
the Infill Development SO Chapter by August 2023. The
City has assembled a Technical Committee made up of
Infill Development Subdivision Project Platting senior level decision makers representing various
development review teams who will review and comment
on the proposed chapter contacts. Technical Committee
Meetings are scheduled to begin in August 2023.
A final draft has been distributed for review. Documents
Urban Forestry Master Plan Urban Forestry included are UFMP, Technical Report, redline version of
the Urban Forestry Ordinance, and a draft for proposed
Cross Timbers Overlay District.
Development Activity Report
17
Development Services
D.J. Harrell, Director
Development Services Department
817-392-8032
Dalton.Harrell@fortworthtexas.gov
Building Permits
Evan Roberts, Assistant Director
Development Services Department
Development Building Division
817-392-7843
Evan. Roberts@fortworthtexas.gov
Infrastructure
Victor Tornero, Engineering Manager
Development Services Department
Infrastructure Development Division
817-392-7830
Victor.Tornero@fortworthtexas.gov
Stormwater
Tyson Thompson, Assistant Director
Development Services Department
Infrastructure Development Division
817-392-2120
Tyson.Thompson@fortworthtexas.gov
Water
Chris Harder, Director
Water Department
817-392-5020
Christopher.Harder@fortworthtexas.gov
Development Activity Report 18