FORT WORTH City of Fort Worth
Change Order Request
Project Name:1 Water and Sanitary Sewer replacement Contract 2011 WSM-D Part 2 City Sec No., 1 56582
Project No.(s):l 1929-2 1 DOE No. I N/A City Proj. No.:l 1929 N
Project Description:) Replacing water line, Sanitary Sewer lines, Flat works and Paving on various streets,
Contractor: Woody Contractors Inc.
City Project Mgr.1 Preeli KC
Phone Number: (817) 392-5467
Dept.
Original Contract Amount
Extras to Date
Credits to Dale
Pending Change Orders (in M&C Process)
Contract Cost to Date
Amount of Proposed Change Order
Revised Contract Amount
Original Funds Available for Change Orders
Remaining Funds Available for this CO
Additional Funding (if necessary)
Change Order# Date: 8/8/2023
City Inspector: Ariel Duarte
Phone Number (817) 392-8306
Water Sewer TPW Totals Contract Time
(Calender days)
$2,031,329.25 $914,697.25 $0.00 $2,946,026.50 %365
$40,572.70 $45,685.00 $236,072.00 $322,329.70 195
$2,071,901.95
'
$960,382.25
1
$236,072.00
$0.00
$0.00
$0.00
$2,071,901.95
$960,382.25
$236,072.00
$101,566.75
$45,733.75
$0.00
$60,994.05
$48.75
$0.00
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT
MAXALLOWABLECONTRACTAMOUNT (ORIGINAL CONTRACT COST+ 25%)
JUSTIFICATION (REASONS) FOR CHANGE ORDER
I
$3,268,356.20 560
$0.00 30
$3,268,356.20 590
I$147,300.50
$61,042.80
10,94%
$3,682,533.13
Transportation and Public Works(TPW) Field Operations were scheduled to pulverize and overlay Prospect
Avenue (Cliff Street to 300 feet South) subsequent to water main installation. However, TPW crews were not
able to conduct pulverization and stabilization due to the grade of the street. Change Order No. 8 will allow
Woody Contractors to pulverize and stabilize the street and TPW will install the HMAC overlay. The change
order will compensate the contractor for remobilizing to the job site and also providing additional pay item for
the retaining wall installation.
Staff concurs with the contractr's request for 30 additional calendar days on the project for the change order.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents
payment in full (both time and money) for all costs arising out of, or incidental to, the above Change Order.
Contractor's Company Name
I
Contractor Name
Contractor Signature
Date' 1
Woody Conlraclors Inc.
Troy Woody
I �-
I q � - a 3 I
Inspector
Date
Project Manager v
Date
,(Sll2GQi� !/LG15Z'A&
8/8/23
`4,e,, X(i
8/8/2023
Director (Water Dept) , . _ , . _,do&
Date
Construction Supervisor (TPW)
Date
T S,
Auiz 9, 2023
41za Z2aaA&
8/8/23
Senior Assistant City Attorney
Date
Assistant City Manager
Date
�++
(
Aug41
15, 2023
, ba�uz S ��
Aug 15, 2023
I
Council Action (If Required)
M&C Number N/A M&C Date Approved N/A OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
FORT WORTH
City of Fort Worth
s
Change Order Additions
Project Name I Water and Sanitary Sewer replacement Contract 2011 WSM-D Part 2
City Sec No.:
56582
Project No.(s): 1 1929-2
DOE No.1 N/A
CityProj. No.:
1929
Project I Description Replacing water line, Sanitary Sewer lines, Flat works and Paving on various streets.
Contractor Woody Contractors Inc,
I Change Order:®
Date:1 8/8/2023
City Project Mgr. Preeti KC
City Inspector I Ariel Duarte
ADDITIONS
I I rM UESCHIP I IUN
DEPT Qty 'Unit
"Unit Cost
Total
13 Install Retaining Wall
Sewer 145.00 SF
$110.00
$15,950.00
55 Mobilization
Sewer 1.00 LS
$5,500.00
$5,500.00
56 Major Manhole Adjustment
Sewer 1.00 EA
$4,700.00
$4,700.00
58 10" Pulverization & Cement Stabilization
Sewer 828.00 SY
$30.00
$24,840.00
59 Cement (26lb/SY)
Sewer 11.00 TN
$445.00
$4,895.00
57 Chain Link Fence
Water 30.00 LF
$80.00
$2,400.00
58 Concrete Steps
Water 38.00 SF
$40.00
$1,520.00
,Water $3,920.00
Sewer $55,885.00
JPW
Page 1 of 1 lAdditions Sub Total $59,805.00
FO RT WO RT H
City of Fort Worth
Change Order Deletions
Project Name Water and Sanitary Sewer replacement Contract 2011 WSM-D Part 2
City Sec No.: 56582
Project No,(s): I 1929-2
1 DOE No. I N/A
City Proj. No.: I 1929
Project Description
I Replacing water line, Sanitary Sewer lines, Flat works and Paving on various streets.
Contractor Woody Contractors Inc.
Change Order: ®
Date 8/8/2023
City Project Mgr. Preeti KC
City Inspector: I Ariel Duarte
DELETIONS
ITEM DESCRIPTION
DEPT Qty Unit
'Unit Cost Total
39 10-inch Pavement Pulverization
Water 420,00 SY
$6.15 $2,583.00
42 4-inch Concrete Sidewalk With Retaining Wall
Water 167.125 SF
$8.00 $1,337.00
26 7-inch Concrete Curb and 18-inch Gutter (match
existing) Sewer 496.00 LF
$38.00 $18,848.00
27 7-inch Concrete Valley Gutter
Sewer 59.821 SY
$162.00 $9,691.00
28 2-inch Asphalt Pavement Type "Y
Sewer 2,486.00 SY
$11.00 $27,346.00
lWater $3,920.00
Sewer $55,885,00
ITPW
Pag-� 1 cf 1 (Deletions Sub Total
MMBE Breakdown for this Change Order
:;,s.•�.��!-F7i`.'-?�t � -. _ _ .: i;,, }��• t .xn:a: � N �er ram_ :r. dime,.,.: ;a:,.::�;.L,.._-�_ ,J ,VI
asr:Lt � ru.
:tf :;.1`,=:.:i,!; .... x, lce7,:.. ,,lei
Total
Previous Change Orders
t..:. =;�+: � fi �' �, r,5_� — ✓-'i �, . �.'.-. ; _ ;._.. «y :—•z: �s- - ,..1 , � - - v5-:fi�ar:o
L" :�I�:_.f,i��l��:. •Ii���.�:�N�P. Q�N,?�Y�i1����;;;};.:.
Total
Page 1 of 1
W-109
ripy and hemphill
Oleander & st. Louis.
I Pearl
HOUSTON
BIRD AND CLECKLER
lisbon and ashland
W-115
Evans St.
IW-130 RENEWAL 1 WELLBAUM'S
ICRABTREE & Berner -RR job
bellaire Park Deck.
keller haslet
barkdale dam
I
(PRICING OR WAITING PO
Ilund'er construction
PRICED PO WO INVOICED PM COMPLETE PAID KLUTZ START
x X JANE
x Miguel
Jane
x miguel
X Miguel
x >C jane
x half I x WELLBAUM
x x x half well
x well
x miguel
wellbaum
trevino
august I
July
aug. 8th
8/8/2022
Water and Sanitary Sewer Replacement Contract 2011, WSM-D, Part 2
CPN 1929
CSC No.: 56582
Change Order 8 Notes
Staff has reviewed the requested days and considers them to be fair and reasonable.
Contract Compliance Manager
By signing I acknowledge that I am the person responsible
for the monitoring and administration of this contract, including
ensuring all performance and reporting requirements.
Signature
Preeti KC
Name of Employee
Sr. Professional Engineer
Title