HomeMy WebLinkAboutContract 49054-FP1NN Coded 07.31.23
Vendor: ARK Contracting
VendorlD:0000024628
Invoice No.Date:
: 0 .25.23 FORTWORTH CSC No.49054-FP1
Invoice Date: 07.25.23
Retainage release total: $136,746.72
FID 30100-2060000-CO0558-CRETAN $7,306.29 —IF
FID 59607-2060000-CO0558-CRETAN $129,440.41
WATER DEPARTMENT
ENGINEERING AND FISCAL SERVICES
NOTICE OF PROJECT COMPLETION
59607-000558
CS 49054
Regarding contract 49054 for M-219 Sanitary Sewer Rehabilitation Contract LXI (61) as required by the Water
Department as approved by City Council on 3/28/2017 through M&C C-28164 the Director of the Water Department,
upon the recommendation of the Sr. Capital Projects Officer, Capital Projects Delivery, Water Department, has accepted
the project as complete.
Original Contract Prices:
Amount of Approved Change Orders:
Revised Contract Amount:
Total Cost Work Completed:
Less Deductions:
Liquidated Damages:
Other Deductions(see comments):
Total Deduction Amount:
Total Cost Work Completed:
Less Previous Payments:
Final Payment Due
07,19 J v J /C)
Recommended for Acceptance
Assistant Director, Water Department
Christopher Haffder (Aug 29, 2023 15:55 CDT)
Accepted
Director, Water Department
'Dwia &Uh off
Dana Burg, 202� CDT)
City Manager
$3,750,858.00
$0.00 Ns 1
$3,750,858.00
$2,734,935.35
0 Days @ $630.00/ Day
$0.00
$2,734,935.35
$2,598,188.65
$136,746.70
Date
Date
Date
� /,z �- /2-S
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
Project Name: M-219 Sanitary Sewer Rehabilitation Contract LXI (61) DOE. Ns:
Comments:
59607-CO0558
CS 49054
City Project Numbers 00558
Contract Name M-219 Sanitary Sewer Rehabilitation Contract LXI (61)
Contract Limits Council District 2
Project Type Paveing
Project Funding
DOE Number
6538
Estimate Number
33
Payment Number
33
For Period Ending
7/15/2023
Project Manager Chaubey City Secretary Contract Number 49054
Inspectors Johnson / Gieger Contract Date 3/28/2017
Contractor ARK CONTRACTING SERVICES, LLC Contract Time 795 CD
420 SOUTH DICK PRICE ROAD Days Charged to Date 795 CD
KENNEDALE, TX 76060 Contract is .000000 Complete
CITY OF FORT WORTH
SUMMARY OF CHARGES
Line Fund Account Center Amount Gross Retainage Net
Funded
--------------------------------------
Total Cost of Work Completed $2,734,935.35
Less 0 % Retained
$0.00
Net Earned
$2,734,935.35
Earned This Period $136,746.77
Retainage This Period $0.00
Less Liquidated Damages
0 Days @ $0.00 / Day
$0.00
LessPavement Deficiency
$0.00
Less Penalty.
$0.00
Less Previous Payment
$2,598,188.58
Plus Material on Hand Less 15%
$0.00
Balance Due This Payment
$136,746.77
Monday, July 24, 2023 Page 6 of 6
FORT WORTH
CITY OF FORT WORTH
FINAL PAYMENT REQUEST
Contract Name
M-219 Sanitary Sewer Rehabilitation Contract LXI (61)
Contract Limits
Council District 2
Project Type
Sewer
City Project Numbers 00558
DOE Number
6538
Estimate Number 33 Payment Number 33 For Period Ending 7/15/2023
CD
City Secretary Contract Number 49054 Contract Time 799D
Contract Date 3/28/2017 Days Charged to Date 795
Project Manager Chaubey Contract is 73.000 Complete
Contractor ARK CONTRACTING SERVICES, LLC
420 SOUTH DICK PRICE ROAD
KENNEDALE, TX 76060
Inspectors Johnson / Gieger
Monday, July 24, 2023 Page 1 of 6
City Project Numbers 00558 DOE Number 6538
Contract Name M-219 Sanitary Sewer Rehabilitation Contract LXI (61) Estimate Number 33
Contract Limits Council District 2 Payment Number 33
Project Type Sewer For Period Ending 7/15/2023
Project Funding
Unit I Sewer
Item
Description of Items
Estimated Unit
Unit Cost
Estimated
Completed
Completed
No.
Quanity
Total
Quanity
Total
---------------------------------------
1
8" Sewer Pipe (CO#1)
9995 LF
$125.00
.,249,375.00
9994.19 ,1,249,273.75
2
6" CIPP
176 LF
$120.00
$21,120.00
481.9
$57,828.00
3
8" Sewer Pipe, CSS Backfill
165 LF
$160.00
$26,400.00
85
$13,600.00
4
8" Pipe Enlargement
728 LF
$150.00
$109,200.00
420.6
$63,090.00
5
4" Sewer Service (CO#1)
229 EA
$1,000.00
$229,000.00
229
$229,000.00
6
Trench Safety
10567 LF
$5.00
$52,835.00
9964.19
$49,820.95
7
Remove 4' Sewer Manhole
32 EA
$500.00
$16,000.00
30
$15,000.00
8
4' Manhole (CO#1)
46 EA
$7,000.00
$322,000.00
46
$322,000.00
9
4' Drop Manhole (CO#1)
3 EA
$9,000.00
$27,000.00
3
$27,000.00
10
4' Extra Depth Manhole (CO#1)
64 VF
$200.00
$12,800.00
64.28
$12,856.00
11
Sanitary Line Grouting (CO#1)
0 CY
$300.00
$0.00
12
Epoxy Manhole Liner
68 VF
$200.00
$13,600.00
74.53
$14,906.00
13
Concrete Collar
57 EA
$600.00
$34,200.00
45
$27,000.00
14
Manhole Vacuum Testing
57 EA
$200.00
$11,400.00
38
$7,600.00
15
Imported EmbedmentBackfill, Crushed
5 CY
$100.00
$500.00
16
Pre -CCTV Inspection
904 LF
$3.00
$2,712.00
828.1
$2,484.30
17
Post -CCTV Inspection (CO#1)
11403 LF
$1.00
$11,403.00
10896.69
$10,896.69
18
Exploratory Excavation of Existing U
4 EA
$1,200.00
$4,800.00
4
$4,800.00
19
Service reinstatement for pipe enlar
11 EA
$900.00
$9,900.00
7
$6,300.00
20
Service reconnection for CIPP
3 EA
$600.00
$1,800.00
1
$600.00
21
Sag adjustment
100 LF
$90.00
$9,000.00
22
Construction Survey
1 LS
$6,000.00
$6,000.00
1
$6,000.00
23
Construction Staking
1 LS
$5,000.00
$5,000.00
1
$5,000.00
24
4-Feet Wide Asphalt Pvmt Repair, Res
1200 LF
$45.00
$54,000.00
1059.5
$47,677.50
25
Asphalt Pvmt Repair, Sewer Service
1005 LF
$25.00
$25,125.00
46
$1,150.00
26
Temporary Asphalt Paving Repair (2 i
3100 LF
$30.00
$93,000.00
2587
$77,610.00
27
7-Inch Cone. Pvmt Repair
1300 SY
$100.00
$130,000.00
297.89
$29,789.00
28
Trench Cut Repair for gravel surface
1500 LF
$12.00
$18,000.00
836
$10,032.00
29
Seeding, Hydromulch
2000 SY
$2.00
$4,000.00
30
Additional Pavement Repair Beyond Tr
500 SY
$70.00
$35,000.00
163.52
$11,446.40
31
Remove and Replace 6-Inch Concrete C
1800 LF
$30.00
$54,000.00
1172.21
$35,166.30
Monday, July 24, 2023 Page 2 of 6
City Project Numbers 00558
DOE Number
6538
Contract Name M-219 Sanitary Sewer Rehabilitation Contract LXI (6 1)
Estimate Number
33
Contract Limits Council District 2
Payment Number
33
Project Type Sewer
For Period Ending
7/15/2023
Project Funding
32
Install New 6" Concrete Curb and Gut
1700 LF
$25.00
$42,500.00
33
8-Inch Pavement Pulverization
9400 SY
$5.00
$47,000.00
4823.96
$24,119.80
34
2-Inch HMAC Surface Course Type "D"
9400 SY
$10.00
$94,000.00
3851.99
$38,519.90
35
Water Valve Box Adjustment with Cone
11 EA
$200.00
$2,200.00
36
Water Meter Box Adjustment
3 EA
$100.00
$300.00
37
Manhole Adjustment with Concrete Col
8 EA
$800.00
$6,400.00
1
$800.00
38
Block Sod Placement
675 SY
$8.00
$5,400.00
39
Traffic Control
5 MO
$3,000.00
$15,000.00
3
$9,000.00
40
Concrete -Class 'B" (2500 psi) -Mince
5 CY
$120.00
$600.00
41
Concrete -Class "E" (1500 psi)-Miscel
5 CY
$160.00
$800.00
42
SWPPP > 1 acre
I LS
$10,000.00
$10,000.00
1
$10,000.00
43
Construction Allowance
1 LS
$70,000.00
$70,000.00
45
8-inch Concrete Drives in Alley (CO#1)
9350 SF
$12.00
$112,200.00
9350
$112,200.00
46
10 Foot Curb Inlet (CO#1)
1 EA
$8,000.00
$8,000.00
1
$8,000.00
47
Reinforced Concrete with Asphalt Overlay (CO#1)
533 SY
$76.00
$40,508.00
533
$40,508.00
48
Excavate & Repair Existing 24 inch Storni Drain
I EA
$7,735.00
$7,735.00
1
$7,735.00
(CO# 1)
Sub -Total of Previous Unit $3,051,813.00 $2,588,809.59
Unit H Pavement
Item Description of Items
No.
----------------
I Remove and Replace 6-Inch Concrete C
2 Install New 6" Concrete Curb and Gut
3 8-Inch Pavement Pulverization
4 2-Inch HMAC Surface Course Type "D"
5 Water Valve Box Adjustment with Conc
6 Water Meter Box Adjustment
7 Manhole Adjustment with Concrete Col
8 Block Sod Placement
9 Traffic Control
10 Concrete -Class "B" (2500 psi)-Miscel
11 Concrete -Class "E" (1500 psi)-Miscel
12 Construction Survey
13 Construction Staking
Estimated Unit Unit Cost Estimated Completed Completed
Quanity Total Quanity Total
----------------------
1800 LF $30.00 $54,000.00 538.88 $16,166.40
1700 LF $25.00 $42,500.00
9400 SY $5.00 $47,000.00 4823.96 $24,119.80
9400 SY $10.00 $94,000.00 3851.99 $38,519.90
11 EA $200.00 $2,200.00 3 $600.00
3 EA $100.00 $300.00
8 EA $600.00 $4,800.00 2 $1,200.00
675 SY $10.00 $6,750.00
5 MO $3,000.00 $15,000.00
5 CY $120.00 $600.00
5 CY $160.00 $800.00
1 LS $4,000.00 $4,000.00
1 LS $4,000.00 $4,000.00
Monday, July 24, 2023 Page 3 of 6
City Project Numbers 00558 DOE Number 6538
Contract Name M-219 Sanitary Sewer Rehabilitation Contract LXI (61) Estimate Number 33
Contract Limits Council District 2 Payment Number 33
Project Type Paveing For Period Ending 7/15/2023
Project Funding
14
Remove and Replace 6-Inch Cone. Driv
11400
SF
$12.00
$136,800.00
3316.03 $39,792.36
15
Remove and Replace 44nch Concrete S
600
SF
$10.00
$6,000.00
349.68 $3,496.80
16
Remove and Replace 4-Inch Cone. Side
2600
SF
$12.00
$31,200.00
17
Install New 4-Inch Concrete Sidewalk
17100
SF
$7.00
$119,700.00
18
Install New 4" ADA Wheelchair Ramp
11
EA
$1,500.00
$16,500.00
19
Curb Address Painting
53
EA
$75.00
$3,975.00
20
13 Ib/sy Cement Modification
121
TN
$170.00
$20,570.00
56.65 $9,630.50
21
Roadbond EN 1
146
GA
$200.00
$29,200.00
63 $12,600.00
22
Stop Bars Pavement Markings
105
LF
$30.00
$3,150.00
23
Remove and Replace Existing Wheelcha
3
EA
$2,000.00
$6,000.00
24
--------------------------------------
Construction Allowance
1
LS
$50,000.00
$50,000.00
--------------------------------------
Sub-Total
of Previous Unit
$699,045.00
$146,125.76
Monday, July 24, 2023 Page 4 of 6
City Project Numbus 00558
Contract Name M-219 Similary Sewer Rehabilitation Contract LXI (61)
Contract Limits Council District 2
Project Type Pawing
Project Funding
Contract Information Summary
Original Contract Amount
Chann Orders
Change Order Number I
DOE Number
6538
Estimate Number
33
Payment Number
33
For Period Ending
7/15/2023
$3,750,958.00
$0.00
TWO Contract Price $3,750,858.00
Conlntcl r v
��. Date G7-2S- Z(5L3 Total Cost of Work Completed
1)ate 7
'—inspection Supervisor
c j
C��—�2 •� ' '1 n,r tl— Date ? Ja �l _✓23
�! Ej,Prolcct Mann cr
Datc7l2 C 12-
Asst. DirectorP+'%r
Chnstopher Ha der (Aug 29, 202315:55 CDT) Date,
Director / Contracting Department
Less 0 % Retained
Net Earned
Earner) This Period $136,746.77
Retainage This Period $0.00
Less Liquidated Damages
Days rr / Day
LessPaventent Deficiency
Less Penalty,
Less Previous Payment
Plus Material on Hand Less 15%
Balance Due This Payment
$2,734,935.35
$0.00
$2,73,1,935.35
$0.00
$0.00
$0.00
$2,598,188.58
$0.00
$136,746.77
Monday, .luly 24, 2023 Page 5 or
D'O RT WO R`1� H rev a3,�,,�t,
WATER ENGINEERING & FISCAL SERVICES
FINAL STATEMENT OF CONTRACT TIME
FINAL STATEMENT NO.:33
NAME OF PROJECT: M-219 Sanitary Sewer Rehabilitation Contract LXI (61)
PROJECT NO.: 558 CONTRACTOR: Ark Contracting Services
CITY PROJECT 558
PERIOD FROM 07/01/23 TO: 07/15/23 FINAL INSPECTION DATE: 3/8/2022
WORK ORDER EFFECTIVE:9/2/2017 CONTRACTTIME: 345 + 450 =795 0 WD (§) CD
DAYS DAYS
DAY OF REASON FOR DAYS DAY OF REASON FOR DAYS
MONTH CHARGED CREDITED MONTH CHARGED CREDITED
DURING DURING
I. 16.
2. 17.
3. 18.
4• 19,
5. 20,
6. 21.
7. 22.
8. 23.
`. 24.
l0• 25.
I. 26.
12. 27.
13. 28.
14. 29.
15. 30.
31.
SAT, SUN,
RAIN, TOO WET,
UTILITIES
DAYS
TOTAL
& HOLIDAYS
& TOO COLD
RELOCATIONS
OI HERS "
CHARGED
DAYS
THIS
PERIOD
245
PREVIOUS
PERIOD
550
TOTALS
TO DATE
795
V. 1:1 V A tv [% I%a:
t
CTO DATE INSPECTOR DATE
Capital Projects Delivery, Water Department
The Cily of Dort V"orth • 200 T exas Strect • Dort Worlli, T\ 76012-6311
(817) 392 - 4477 • Pas: (817) 392 - 8460
CONSENT OF
SURETY COMPANY
TO FINAL PAYMENT
Bond Number: 1847644
OWNER
❑
ARCHITECT
❑
CONTRACTOR
❑
SURETY
❑
OTHER
❑
PROJECT: M-219 Sanitary Sewer Rehabilitation Contract LXI (61)
(name, address)
TO (Owner)
City of Fort Worth CONTRACT FOR: Sewer
200 Texas St.
Fort Worth, TX 76102 PROJECT NO.:
CONTRACTOR: CONTRACT DATE:
Ark Contracting Services, LLC
420 South Dick Price Road FINAL CONTRACT PRICE: 2, 734, 935.35
Kennedale, TX 76060
In accordance with the provisions of the Contract between the Owner and the Contractor as indicated
above, the (here insert name and address of Surety Co.)
Great American Insurance Company
P.O. Box 5425
Cincinnati, OH 45201-5425
, SURETY COMPANY,
on bond of (here insert name and a(Ich•ess of Contractor)
Ark Contracting Services, LLC
420 South Dick Price Road
Kennedale, TX 76060
,CONTRACTOR
hereby approves of the final payment to the Contractor and agrees that final payment to the
Contractor sliall not relieve the Surety Company of any of its obligations to (here insert name and
address of Owner)
City of Fort Worth
200 Texas St.
Fort Worth, TX 76102
OWNER,
as set forth in the said Surety Company's Bond.
IN WITNESS WHEREOF,
the Surety Company has hereunto set its hand this 22nd day of February 2023
Great American Insurance Company
Surety C pany
(SEAL) By
Signatu •e of Authorized Representative
Lloyd Ray Pitts Jr - Attorney -In -Fact
Title
GREAT AMERICAN INSURANCE COMPANY@
Administrative Office: 301 E 4TH STREET • CINCINNATI, OHIO 45202 • 513-369-5000 • FAX 513-723-2740
The number of persons authorized by
this power of attorney is not more than TWO
No.o 20935
POWER OF ATTORNEY
KNOW ALL MEN BYTHESE PRESENTS: That the GREATAMERICAN INSURANCE COMPANY, a corporation organized and existing under
and by virtue of the laws of the State of Ohio, does hereby nominate, constitute and appoint the person or persons named below, each individually if more than
one is named, its true and lawful attorney -in -fact, for it and in its name, place and stead to execute on behalf of the said Company, as surety, any and all bonds,
undertakings and contracts of suretyship, or other written obligations in the nature thereof; provided that the liability of the said Company on any such bond,
undertaking or contract of suretyship executed under this authority shall not exceed the limit staled below.
Name Address Limit of Power
LLOYD RAY PITTS, JR. BOTH OF BOTH
WILLIAM D. BIRDSONG DALLAS, TEXAS $100,000,000
This Power of Attorney revokes all previous powers issued on behalf of the attorneys) -in -fact named above.
IN WITNESS WHEREOF the GREAT AMERICAN INSURANCE COMPANY has caused these presents to be signed and attested by its appropriate
officer, and its corporate seal hereunto affixed this 10TH day of DECEMBER 1 2020
Attest GREATAMERICANINSU ANCE COMPANY
'Assi.9lEntl Seerewn, Divisional Senior I we President
STATE OF OHIO, COUNTY OF HAMILTON - ss: MARK VaCARro (877-377-2405)
On this 10TH clay of DECEMBER , 2020 , before me personally appeared MARK VICARIO, to me known,
being duly sworn, deposes and says that he resides in Cincinnati, Ohio, that he is a Divisional Senior Vice President of the Bond Division of Great American
Insurance Company, the Company described iu and which executed the above instrument that he knows the seal ofthe said Company; that the seal affixed to the
said instrument is such corporate seal; that it was so affixed by authority of his office under the By -Laws of said Company, and that he signed his name thereto
by like authority.
w=o
SUSAN A KOHORST
Notary Public
State o
�
My Comm, Expires
May 18, 2025
This Power of Attorney is granted by authority of the following resolutions adopted by the Board of Directors of GreatAnlerican Insurance Company
by unanimous written consent dated June 9, 2008.
RESOLVED: That the Divisional President, the several Divisional Senior Vice Presidents, Divisional here Presidents card Divisonal Assistanl Vice
Presiclenis, or an), one ol'thent, be and hereby is authorized, •Iron lithe to lime, to appoint one or nio•e Allorneys-in-Foal to execute on behall'of the Company,
as sure(ts any and all bonds, undertakings and contracts gl'suretvship, or other written obligations in the nature thereof; to prescribe their respeclive duties and
the respective lintils ol'Iheir authority; and to awoke any such alymbiluent at any lime.
RF,SOLPED FUR7 HER: That the Coinpann, seal and the signature of amp of the g%resaid officers and arp, Secretary or Assistant Secre/art, of the
Company may be ef[rved by facsimile to any power of attorney or cerltficale of eilher given for the execution of aqj, bond, undertaking, contract ofsitrelyship,
or otter written obligation in the nalu re lhereaf; such signature and seal when so used being hereby adopted by the Company as the original signature gl'such
officer and the original seal of the Canpany, to he valid and binding upon llte Company with the ,ante force and effect as though maintalli,afxed.
CERTIFICATION
i, STEM iEN C. BERAI IA, Assistant Secretary of Great American Insurance Company, do hereby certify that the foregoing Power of Attorney and
the Resolutions of the Board of Directors of June 9, 2008 hnve not been revoked and are now in full force and effect.
Signed and scaled this 22nd day of February 2023
y.
A.s.sislant Seererw•y
S1029AH (03/20)
AFFIDAVIT
STATE OF TEXAS
COUNTY OF TARRANT
Before me, the undersigned authority, a notary public in the state
and county aforesaid, on this day personally appeared Karen Hatton,
Controller Of Ark Contracting Services, LLC, known to me to be a
credible person, who being by me duly sworn, upon his oath deposed and
said;
That all persons, firms, associations, corporations, or other
organizations furnishing labor and/or materials have been paid in full;
That the wage scale established by the City Council in the City of
Fort Worth has been paid in full;
That there are no claims pending for personal injury and/or
property damages;
On Contract described as;
M-219 Sanitary Sewer Rehabilitation Contr 61
BY
Karen"IIatton, ControlTer
Subscribed and sworn before me on this date 13th of January, 2023.
-lu.v,.,-�cv► V�an1 o UYI o.,���, .1.P
Notary Public
Tarrant, Texas
SHANNON MARIE MERRELL
�g
:rr Notary Public, State of Texas
Comm. Expires 03-30-2026
VNotary ID 133676609
FoRTWORTH
Capital Projects Delivery, Water Department
CONTRACTOR'S EVALUATION OF CITY
I) PROJECT INFORMATION
Nante oj'Canractor
Ark Contracting Services
Water Engineering Inspector
Paul L. Gieger
DOE Neunber Project D cull),
558 O Simple (j) Routine Q Complex
btitial Contract Amount
$3,750,858.00
II) PERFORMANCE EVALUATION
REV: 02/22/07
Date: 12 1 -Jul-23 _
Project Name
M-219 Sanitary Sewer Rehabilitation Contract LXI (61)
Project Alanager
Scott Taylor
Type of Contract
❑ Water Q Waste Water ❑ Storm Drainage ❑ Pavement
final Contract Anuontt
$2,734,935.35
0 - Inadequate l - Deficient 2 - Standard 3 - Good 4 - Excellent
ELEMENT'
RATING
ELEMENT
RATING
INSPECTION EVALUATION
PLANS & SPECIFICATIONS
I Availability of Inspector
I Accuracy of Plans to Existing Conditions
2 Knowledge of Inspector
3
2 Clarity & Sufficiency of Details
3 Accuracy of Measured Quantities _
_�_
3 Applicability of Specifications
4 Display Of Professionalism
4 Accuracy of Plan Quantities
5 Citizen Complaint Resolution—
-
PROJECT MANAGER EVALUATION
—
6 Performance - Setting up Valve Crews, Labs -
3
I Knowledge And/Or Problem Resolution
ADMINISTRATION
2 Availability of Project Manager
l Change Order Processing Time
3 Communication-
2 Timliness of Contractor Payments
3
4 Resolution of Utility Conflicts
3 Bid Opening to Pre -Con Meeting Timeframe
I11) COMMENTS & SIGNATURES
COMMENTS
Signature Contractor
Signature Inspector
Signature Inspector's Supervisor
INSPECTOR'S COMMENTS
Capital Projects Delivery, Water Department
The City of fort \Vorth • 1000 Throckfnorton Street • Fort \Vortli,'rx 76012-6311
(817) 392 - 4477 • Fax: (817) 392 - 8460
FoRTWORTHREV:02/20/07
Capital Projects Delivery, Water Department
PERFORMANCE EVALUATION OF CONTRACTOR
I) CONTRACTOR & PROJECT DATA
of Contractor
Project Name
IName
Ark Contracting Services
M-219 Sanitary Sewer Rehabilitation
Contract LX1 (61)
Water Engineering Inspector
DOE Number
Paul L. Gieg_er
558
Water Engineering Inspector
Project Manager
❑ Water 121 Waste Water ❑ Storm Drainage ❑ Pavement
Scott Taylor
Contract Antotunl
Project D(Uculq,
IInilial
$3,750,858.00
0 simple
0 Routine
0 Complex
rinal Contract Amount
Date
1 $2,734,935.35
7/21/2023
II) PERFORMANCE EVALUATION
10 - Inadequale I - Deficient 2-Standard 3-Good
4-Excellent
IELENIEN-r WEIGHT
( x)
APPLICABLE
(Y / N)
IRATING (0 - 4)
MAX SCORE SCORE
1 Submission of Documents
2
Y
3
8
6
Public Notifications
5
Y
2
20
10
12
3 Plans on Site
5
Y
3
20
15
14 Field Supervision
t5
Y
3
60 1
45
15 Work Performed
15
Y
3
60
45
16 Finished Product
IS
Y
3
60
45
17 Job Site Safety
15
Y
3
60
45
18 Traffic Control Maintenance
15
Y
3
60
45
19 Daily Clean Up
5
Y
2
20
10
110 Citizen's Complaint Resolution
5
Y
3
20
15
I Property Restoration
5
Y
2
20
10
12 After Hours Response
1t
5
Y
3
20
15
13 Project Completion
5
Y
I 3
20
15
TOTAL EI.EMENf SCORE (A)
321
BONUS POINTS
(25 Maximum) (B)
TOTAL SCORE (I'S)
321
111) CONTRACTOR'S RATING
Maximum Score (MS) = 448 or sum of applicable element score maximums which = 448
Rating( ITS/ NIS1 * 100%) 321 / 448 = 72%
Performance Category Good
<20% = /nadequate 20% to <40% = Deficient 40% to --60% = Standard 60% to <80% = Good >80% = Rwellent
Inspeetor's Comments (INCLUDING EXPLANATION OF BONUS POINTS AWARDED)
Signature Inspector Signature Contractor
Signature Inspector's Supervisor—�
CONTRACTOR'S COMMENTS
Capital Projects Delivery, Water Department
flee City of Fort \North • 1000 Throckmorton Street • Fort \Xforth, TX 76012-6311
(817) 392 - 4477 • Fax: (817) 392 - 8460
FORT WORTH.
WATER ENGINEERING & FISCAL SERVICES
PIPE REPORT FOR:
PROJECT NAME: M-219 Sanitary Sewer Rehabilitation Contract LXI (61)
PROJECT NUMBER: 558
DOE NUMBER: 558
WATER
PIPE LAID SIZE TYPE OF PIPE LF
0 0
FUZE HYDRANTS: 0 VALVES (16" OR LARGER) 0
PIPE ABANDONED SIZE TYPE OF PIPE LF
DENSITIES: 0
NEW SERVICES: 0
SEWER
PIPE LAID SIZE TYPE OF PIPE LF
PVC SDR-26 811 PVC SDR-26 10,079 '
HDPE 8 " HDPE 8 " 421 '
PIPE ABANDONED SIZE TYPE OF PIPE LF
Concrete Pipe 811 Concrete Pipe 525 '
Concrete Pipe 6 " Concrete Pipe 285 '
DENSITIES: YES
NEW SERVICES:
WATER ENGINEERING & FISCAL SERVICES
The City of Fort Worth • 1000 Throckmorton Street • Fort Worth, TX 76012-6311
(817) 392 - 4477 • Fax: (817) 392 - 8460
City of Fort Worth
Inspector's Estimate Worksheet
City Project Numbers 00558
Contract Name M-219 Sanitary Sewer Rehabilitation Contract LXI (61
DOE Number 6538
Contract Limits: Council District 2
Estimate Number 33
Project Type Sewer
Payment Number 33
o/ 1
Control Number
653801
For Period Ending ✓C / —9L(V3
Contract: 49054
Contract Date: 3/28/2017
Contract Time 795 CD
Days Charged to Date CD
Inspectors Johnson /
Gieger
023
Contract is % Complete
Date Prepared by Inspector 09
/ � /�
Construction ID: 11536
Item Description of Items
Estimated Uni
Unit Cost
Previous Quanity Completed Total Cost
No.
Quanity
Quanity for Month Quanity
Unit I Sewer
1 8" Sewer Pipe (CO#1)
9995 LF
$125.00
9994.19
2 6" CIPP
176 LF
$120.00
481.9
3 8" Sewer Pipe, CSS Backfill
165 LF
$160.00
85
4 8" Pipe Enlargement
728 LF
$150.00
420.6
5 4" Sewer Service (CO#1)
229 EA
$1,000.00
229
6 Trench Safety
10567 LF
$5.00
9964.19
7 Remove 4' Sewer Manhole
32 EA
$500.00
30
8 4' Manhole (CO#1)
46 EA
$7,000.00
46
9 4' Drop Manhole (CO#1)
3 EA
$9,000.00
3
10 4' Extra Depth Manhole (CO#1)
64 VF
$200.00
64.28
11 Sanitary Line Grouting (CO#1)
0 CY
$300.00
12 Epoxy Manhole Liner
68 VF
$200.00
74.53
13 Concrete Collar
57 EA
$600.00
45
14 Manhole Vacuum Testing
57 EA
$200.00
38
15 Imported Embedment/Backfill,
5 CY
$100.00
Crushed
16 Pre -CCTV Inspection
904 LF
$3.00
828.1
17 Post -CCTV Inspection (CO#1)
11403 LF
$1.00
10896.69
18 Exploratory Excavation of Existing
4 EA
$1,200.00
4
U
Monday, July 17, 2023 Page 1
City of Fort Worth
Inspector's Estimate Worksheet
City Project Numbers 00558
Contract Name M-219 Sanitary Sewer Rehabilitation Contract LXI (61
Contract Limits: Council District 2
Project Type Sewer
19 Service reinstatement for pipe enlar
20 Service reconnection for CIPP
21 Sag adjustment
22 Construction Survey
23 Construction Staking
24 4-Feet Wide Asphalt Pvmt Repair,
Res
25 Asphalt Pvmt Repair, Sewer
Service
26 Temporary Asphalt Paving Repair
(2 i
27 7-Inch Conc. Pvmt Repair
28 Trench Cut Repair for gravel
surface
29 Seeding, Hydromulch
30 Additional Pavement Repair
Beyond Tr
31 Remove and Replace 6-Inch
Concrete C
32 Install New 6" Concrete Curb and
Gut
33 8-Inch Pavement Pulverization
34 2-Inch HMAC Surface Course
Type "D"
35 Water Valve Box Adjustment with
Conc
36 Water Meter Box Adjustment
37 Manhole Adjustment with Concrete
Col
38 Block Sod Placement
39 Traffic Control
40 Concrete -Class "B" (2500 psi)-
Misce
DOE Number 6538
Estimate Number 33
Payment Number 33
11 EA $900.00 7
3 EA $600.00 1
100 LF $90.00
1 LS $6,000.00 1
1 LS $5,000.00 1
1200 LF $45.00 1059.5
1005 LF $25.00 46
3100 LF $30.00 2587
1300 SY $100.00 297.89
1500 LF $12.00 836
2000 SY $2.00
500 SY $70.00 163.52
1800 LF $30.00 1172.21
1700 LF $25.00
9400 SY $5.00 4823.96
9400 SY $10.00 3851.99
11 EA $200.00
3 EA $100.00
8 EA $800.00 1
675 SY $8.00
5 MO $3,000.00 3
5 CY $120.00
Monday, July 17, 2023 Page 2
City of Fort Worth
Inspector's Estimate Worksheet
City Project Numbers 00558
Contract Name M-219 Sanitary Sewer Rehabilitation Contract LXI (61
DOE Number 6538
Contract Limits: Council District 2
Estimate Number 33
Project Type Sewer
Payment Number 33
41
Concrete -Class "E" (1500 psi)-
5 CY
$160.00
Miscel
42
SWPPP >_ 1 acre
1 LS
$10,000.00
1
43
Construction Allowance
1 LS
$70,000.00
45
8-inch Concrete Drives in Alley
9350 SF
$12.00
9350
(CO#1)
46
10 Foot Curb Inlet (CO#1)
1 EA
$8,000.00
1
47
Reinforced Concrete with Asphalt
533 SY
$76.00
533
Overlay (CO#1)
48
Excavate & Repair Existing 24
1 EA
$7,735.00
1
inch Storm Drain (CO#1)
,stimated Total This Unit
$3,051,813.00
Completed Total This Unit $2,588,809.59
Construction ID: 11537
-------------------------
Item
Description of Items
Estimated Uni
Unit Cost
Previous Quanity Completed Total Cost
No.
Quanity
Quanity for Month Quanity
Unit
II Pavement
1
Remove and Replace 6-Inch
1800 LF
$30.00
538.88
Concrete C
2
Install New 6" Concrete Curb and
1700 LF
$25.00
Gut
3
8-Inch Pavement Pulverization
9400 SY
$5.00
4823.96
4
2-Inch HMAC Surface Course
9400 SY
$10.00
3851.99
Type "D"
5
Water Valve Box Adjustment with
11 EA
$200.00
3
Conc
6
Water Meter Box Adjustment
3 EA
$100.00
7
Manhole Adjustment with Concrete
8 EA
$600.00
2
Col
8
Block Sod Placement
675 SY
$10.00
9
Traffic Control
5 MO
$3,000.00
Monday, July 17, 2023 Page 3
City of Fort Worth
Inspector's Estimate Worksheet
City Project Numbers 00558
Contract Name M-219 Sanitary Sewer Rehabilitation Contract LXI (61
Contract Limits: Council District 2
Project Type Paveing
10
Concrete -Class "B" (2500 psi)-
Miscel
11
Concrete -Class "E" (1500 psi)-
Miscel
12
Construction Survey
13
Construction Staking
14
Remove and Replace 6-Inch
Conc. Driv
15
Remove and Replace 4-Inch
Concrete S
16
Remove and Replace 4-Inch
Conc. Side
17
Install New 4-Inch Concrete
Sidewalk
18
Install New 4" ADA Wheelchair
Ramp
19
Curb Address Painting
20
13 Ib/sy Cement Modification
21
Roadbond EN 1
22
Stop Bars Pavement Markings
23
Remove and Replace Existing
Wheelcha
24
Construction Allowance
DOE Number 6538
Estimate Number
Payment Number
5 CY $120.00
5 CY $160.00
1 LS $4,000.00
1 LS $4,000.00
11400 SF $12.00 3316.03
600 SF $10.00 349.68
2600 SF $12.00
17100 SF $7.00
11 EA $1,500.00
53 EA $75.00
121 TN $170.00 56.65
146 GA $200.00 63
105 LF $30.00
3 EA $2,000.00
1 LS $50,000.00
33
33
;stimated Total This Unit $699,045.00 Completed Total This Unit $146,125.76
Monday, July 17, 2023 Page 4
City of Fort Worth
Inspector's Estimate Worksheet
City Project Numbers 00558
Contract Name M-219 Sanitary Sewer Rehabilitation Contract LXI (61 DOE Number 6538
Contract Limits: Council District 2 Estimate Number 33
Project Type Paveing Payment Number 33
Total Itemized Amount (Including Change Order $3,750,858.00
V LDQ -0'\) DATE ON I 9 Total Cost of Work Completed �' U.5 3�
Inspector Less V % Retained -- Q �2
Net Earned q IV5Qd2
6
Previous Payment $2,598,188.58
Material on Hand 15%IL
L
Balance Due This Payment / 7
p
t
Monday, July 17, 2023 Page 5
PreE stimate Print Construction ID
BidTab Item Description
ID
11536
Estimated Desc. Unit Cost Completed Item Total
Quanity Quanity
223545
1
8" Sewer Pipe (CO#1)
9995
LF
$125.00
223546
2
6" CIPP
176
LF
$120.00
223547
3
8" Sewer Pipe, CSS Backfill
165
LF
$160.00
223548
4
8" Pipe Enlargement
728
LF
$150.00
223549
5
4" Sewer Service (CO#1)
229
EA
$1,000.00
223550
6
Trench Safety
10567
LF
$5.00
223551
7
Remove 4' Sewer Manhole
32
EA
$500.00
223552
8
4' Manhole (CO#1)
46
EA
$7,000.00
223553
9
4' Drop Manhole (CO#1)
3
EA
$9,000.00
223554
10
4' Extra Depth Manhole (CO# 1)
64
VF
$200.00
223555
11
Sanitary Line Grouting (CO#1)
0
CY
$300.00
223556
12
Epoxy Manhole Liner
68
VF
$200.00
223557
13
Concrete Collar
57
EA
$600.00
223558
14
Manhole Vacuum Testing
57
EA
$200.00
223559
15
Imported Embedment/Backfill, Crushed
5
CY
$100.00
223560
16
Pre -CCTV Inspection
904
LF
$3.00
223561
17
Post -CCTV Inspection (CO#I)
11403
LF
$1.00
223562
18
Exploratory Excavation of Existing U
4
EA
$1,200.00
223563
19
Service reinstatement for pipe enlar
11
EA
$900.00
223564
20
Service reconnection for CIPP
3
EA
$600.00
223565
21
Sag adjustment
100
LF
$90.00
9994.19 ,249,273.75
481.9 $57,828.00
85 $13,600.00
420.6 $63,090.00
229 3229,000.00
9964.19 $49,820.95
30 $15,000.00
46 3322,000.00
3 $27,000.00
64.28 $12,856.00
74.53 $14,906.00
45 $27,000.00
38 $7,600.00
828.1 $2,484.30
10896.69 $10,896.69
4 $4,800.00
7 $6,300.00
1 $600.00
Page 1 of 3
Monday, July 24, 2023
BidTab Item Description
ID
Estimated Desc. Unit Cost Completed Item Total
Quanity Quanity
223566
22
Construction Survey
1
LS
$6,000.00
223567
23
Construction Staking
1
LS
$5,000.00
223568
24
4-Feet Wide Asphalt Pvmt Repair, Res
1200
LF
$45.00
223569
25
Asphalt Pvmt Repair, Sewer Service
1005
LF
$25.00
223570
26
Temporary Asphalt Paving Repair (2 i
3100
LF
$30.00
223571
27
7-Inch Conc. Pvmt Repair
1300
SY
$100.00
223572
28
Trench Cut Repair for gravel surface
1500
LF
$12.00
223573
29
Seeding, Hydromulch
2000
SY
$2.00
223574
30
Additional Pavement Repair Beyond Tr
500
SY
$70.00
223575
31
Remove and Replace 6-Inch Concrete C
1800
LF
$30.00
223576
32
Install New 6" Concrete Curb and Gut
1700
LF
$25.00
223577
33
8-Inch Pavement Pulverization
9400
SY
$5.00
223578
34
2-Inch HMAC Surface Course Type "D"
9400
SY
$10.00
223579
35
Water Valve Box Adjustment with Conc
11
EA
$200.00
223580
36
Water Meter Box Adjustment
3
EA
$100.00
223581
37
Manhole Adjustment with Concrete Col
8
EA
$800.00
223582
38
Block Sod Placement
675
SY
$8.00
223583
39
Traffic Control
5
MO
$3,000.00
223584
40
Concrete -Class "B" (2500 psi)-Misce
5
CY
$120.00
223585
41
Concrete -Class "E" (1500 psi)-Miscel
5
CY
$160.00
223586
42
SWPPP >_ 1 acre
1
LS
$10,000.00
223587
43
Construction Allowance
1
LS
$70,000.00
270810
45
8-inch Concrete Drives in Alley (CO#1)
9350
SF
$12.00
270811
46
10 Foot Curb Inlet (CO#1)
1
EA
$8,000.00
1 $6,000.00
1 $5,000.00
1059.5 $47,677.50
46 $1,150.00
2587 $77,610.00
297.89 $29,789.00
836 $10,032.00
163.52 $11,446.40
1172.21 $35,166.30
4823.96 $24,119.80
3851.99 $38,519.90
1 $800.00
3 $9,000.00
1 $10,000.00
9350 3112,200.00
1 $8,000.00
Monday, July 24, 2023 Page 2 of 3
BidTab Item Description
ID
270812 47 Reinforced Concrete with Asphalt Overlay (CO#1)
270813 48 Excavate & Repair Existing 24 inch Storm Drain (CO#1)
Estimated Desc. Unit Cost Completed Item Total
Quanity Quanity
533 SY $76.00
533 $40,508.00
1 EA $7,735.00
1 $7,735.00
Total Cost
$2,588,809.59
Previous Payment -
$2,459,369.11
Unpaid Balance -
$129,440.48
Retainage -
$0.00
This Payment (Amt paid to Contractor)
$129,440.48
Percent Complete
4.000000
Monday, July 24, 2023 Page 3 of 3
PreEstimate Print Construction ID
BidTab Item Description
ID
11537
Estimated Desc. Unit Cost Completed Item Total
Quanity Quanity
223588
1
Remove and Replace 6-Inch Concrete C
1800
LF
$30.00
223589
2
Install New 6" Concrete Curb and Gut
1700
LF
$25.00
223590
3
8-Inch Pavement Pulverization
9400
SY
$5.00
223591
4
2-Inch HMAC Surface Course Type "D"
9400
SY
$10.00
223592
5
Water Valve Box Adjustment with Cone
11
EA
$200.00
223593
6
Water Meter Box Adjustment
3
EA
$100.00
223594
7
Manhole Adjustment with Concrete Col
8
EA
$600.00
223595
8
Block Sod Placement
675
SY
$10.00
223596
9
Traffic Control
5
MO
$3,000.00
223597
10
Concrete -Class "B" (2500 psi)-Miscel
5
CY
$120.00
223598
11
Concrete -Class "E" (1500 psi)-Miscel
5
CY
$160.00
223599
12
Construction Survey
1
LS
$4,000.00
223600
13
Construction Staking
1
LS
$4,000.00
223601
14
Remove and Replace 6-Inch Cone. Driv
11400
SF
$12.00
223602
15
Remove and Replace 4-Inch Concrete S
600
SF
$10.00
223603
16
Remove and Replace 4-Inch Cone. Side
2600
SF
$12.00
223604
17
Install New 4-Inch Concrete Sidewalk
17100
SF
$7.00
223605
18
Install New 4" ADA Wheelchair Ramp
11
EA
$1,500.00
223606
19
Curb Address Painting
53
EA
$75.00
223607
20
13 lb/sy Cement Modification
121
TN
$170.00
223608
21
Roadbond EN 1
146
GA
$200.00
538.88 $16,166.40
4823.96 $24,119.80
3851.99 $38,519.90
3 $600.00
2 $1,200.00
3316.03 $39,792.36
349.68 $3,496.80
56.65 $9,630.50
63 $12,600.00
Monday, July 24, 2023 Page 1 of 2
BidTab Item Description
ID
Estimated Desc. Unit Cost Completed Item Total
Quanity Quanity
223609 22 Stop Bars Pavement Markings 105 LF $30.00
223610 23 Remove and Replace Existing Wheelcha 3 EA $2,000.00
223611 24 Construction Allowance 1 LS $50,000.00
Total Cost $146,125.76
Previous Payment - $138,819.47
Unpaid Balance - $7,306.29
Retainage - $0.00
This Payment (Amt paid to Contractor) $7,306.29
Percent Complete 69.000000
Monday, July 24, 2023 Page 2 of 2
CSC No. 49054-0O2
Po, P'x'I(c) I(;'x' x 1[ City of Fort Worth
Change Order Request
Project Name: M-219 Sanitary Sewer Rehabilitation Contract LXI (61) Part 2 City Sec No.: I 49054 I
Projecl No.(s)] 59607 0700,130 574010 1 DOE No. I N/A City Proj. No.: C00550 1
Project Description:)
Rehabllitalion of sanitary sewer in the North Beverly Hills/Rosen Heights Area
Contractor. Ark Construction Services, LLC I Change Order II 2 Dale:
6/2912023 1
City Project Mgr.1 Scott Taylor Cily Inspeclor: 1 Paul Geiger
1
Phone Number] 817.392.72,10 I Phona Number] 817.223-2250
Dept. Water Sewer Totals
Contract Time
(Cnlondor days)
Original Contract Amount $3,750,858.00 $3,750,858.00
300
Exlms to Data $0.00 $0.00
045
Credits to Data
Pending Change Orders (in M&C Process)
Contract Cost to Date $3,760i06000 $3,750,858.00
3,16
)Amount of Proposed Change Order $0,00 $0.00
450
Revised Contract Amount $3,750,058,00 3,750,050,00
795
Original Funds Available for Change Orders $120,000.00 120,000.00
Remaining Funds Available for this CO $120,000.00 $120,000.00
Additional Funding (if necessary)
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT
$0.00
MAXALLOWABLE CONTRACTAMOUNT (ORIGINAL CONTRACT COST+ 25%)
$000,572.50
JUST,IFICATION�,(REAS.ONS) FOR'CWANCE'ORDER
The change order will provide an additional 460 calendar days on Ilia project for the time period it took AT&T to relocate two
conflicting cables
that were encountered during sewer main installation In Ilse alley between Menefee Street and Lorg Avenue and also on Menfee Street,
Staff recommends Ilse approval of 450 calendar days for Ilse change order.
II is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment
In full (both time and money) for all costs arising out of, or Incidenlal to, Ilia above Change Order.
Contraetorscompany Name
I
•ConlrtfclorNpmQ
INS
I
Dale
Ark Construction Services, LLC
gaig-lis.— lla±—f Vt
v 6/0 o
hiap'ctar,
`hole �,
IMP monagtir
06-1�0
N1.
Dlroclor,(Walor Dept) /%
Data
Oo 1Inrollon Supo `VIOUP
yr W.,r, V
'� S Jut 3, 2023
f
Sonior Assislmlt City Attorney
Data
As lalollt Clty Mann41er '
Data
1
Jul 3,2023
b^n^Ru
Jul 5,2023
Cotmcil,Aollon (If Required)
M&C Number I NIA
M&C Date Approved NIA
Flo, iz'r Woiz- ult City of Fort Worth
Chango Order Additions
Project Name I Sanitary Sewer Rehabililalon Contract LXI (61) Part 2 City Sec No.: 149054
Project No.(s): 1 69607 0700430 6740010 DOE No.1 N/A City Pro}. No.: 00556
Project I Rehabilitation of sanitary sewer in the North Beverly Hills/Rosen Heights Area
Description
Contractor I Ark Construction Services, LLC 1 Change Order: 0 Date:1 6/2912023 I
City Project Mgr, I Scott Taylor I City Inspector I Paul Geiger
ADDITIONS
u �m UbbUNIP I IUra DEPT Aty 'Unit 'Unit Coat Total
lWaler
Sewer
I
Page 1 of 1 !Additions Sub Total
lF•-o City of Fort Worth
Change Order Deletions
Project Name M•219 Sanitary Sewer Rehabililalion Contract LXI (61) Part 2 City Sec No.: 49054
Project No.(s): 59607 0700,130 574010 1 DOE No. N/A City Proj. No.: C00556
Project Description I Rehabilitation of sanilary sewer in the North Beverly HillslRosen Heights Area I
Contractor I Ark Construction Services, LLC I Change Order: [_ 2 Dale 6129/2023
City Project Mgr. Scott Taylor City Inspector: I Paul Geiger
DELETIONS
ITEM 'DESCRIPTION DEPT City ','Unit Unit Cost Total
- Water
Sewer
Pag? 1 of 1 Deletions Sub Total
MIWBE Breakdown for this Change Order
MWBE Sub Type of Service Amount for this CO
co It
Previous Change Orders
DATE
Total
Page 1 of '1
Total
AMOUNT
$0.00
$0.00
6/29/2023
M-219 Sanitary Sewer Rehabilitation Contract LXI (61), Part 2
CPN C00558
Change Order 2 Notes
Staff has reviewed the requested prices and considers them to be fair and reasonable.
.Contract Compliance Manager
By signing I acknowledge that I am the person responsible
for the monitoring and administration of this contract, including
ensuring all performance and reporting requirements.
Signature
Scott Taylor, P.E.
Name of Employee
Project Manager
Title
ATTEST:
A .
Jannette Goodall
City Secretary
FORTWORTH.
July 24, 2023
Ark Contracting Services
420 S. Dick Price Rd.
Kennedale, TX 76060
Re: Acceptance Letter
Project Name: M-219 Sanitary Sewer Rehabilitation Contract LXI (61)
Project Type: Sewer
Project Ns: 00558
DOE. Ne: 6538
Contract No: 49054
Gentleman:
Dated: 7 / 24/ 2023
On March 08, 2022 a final inspection was made on the subject project. There were punch list items identified at
the time. The punch list items were completed on March 15, 2022. The final inspection and the corrected
punch list items indicate that the work meets the City of Fort Worth specifications and is therefore accepted by
the City. The warranty period will start on March 15, 2022, which is the date of punch list completion and will
extend for (2) years in accordance with the Contract Documents.
If you have any questions concerning this letter of acceptance, please feel free to contact me at (817) 392-6054
Yours Truly,
Tony Sholola, P.E., Assistant Director, Water Department
TS /
cc: Chris Harder, P.E., Director, Water Department
Laura Wilson, P.E., Deputy Director, Water Department
Captain Michael Skains, Fire Department
Luke Coffman, Sanitary Sewer Systems Superintendent, Water Department
Cesar Zavala, Water Systems Superintendent, Water Department
John Kasavich PE, Project Manager, Water Department Capital Projects Delivery
David R Johnson, Inspection Supervisor, Water Department Capital Projects Delivery
Paul Gieger, Inspector, Water Department Capital Projects Delivery
Consultant
Contractor
File
Fort Worth
wl-nmeI� � WATER DEPARTMENT
1 I I I V
THE CITY OF FORT WORTH * 200 TEXAS STREET * FORT WORTH, TEXAS 76102 I
817-392-8240 * FAX 817-392-8195
1964 • 1993 •2011 '.i. Printed on recycled paper