AMENDMENT No . 1
TO CITY SECRETARY CONTRACT No. 57029
WHEREAS, the City of Fort Worth (CITY) and Neel -Schaffer, Inc.,
(ENGINEER) made and entered into City Secretary Contract No. 57029, (the
CONTRACT) which was authorized by M&C 22-0049 on the 11th day of January,
2022 in the amount of $543,512.00; and
WHEREAS, the CONTRACT involves engineering services for the
following project:
Water and Sanitary Sewer Replacement Contract 2020, WSM-J; and
WHEREAS, it has become necessary to execute Amendment No. 1 to the
CONTRACT to include an increased scope of work and revised fee.
NOW THEREFORE, CITY and ENGINEER, acting herein by and through
their duly authorized representatives, enter into the following
agreement, which amends the CONTRACT:
1.
Article I of the CONTRACT is amended to include the additional
engineering services specified in proposal attached hereto and
incorporated herein. The cost to City for the additional design services
to be performed by Engineer totals $53,760.00 (Water: $37,632; Sewer:
$16,128. 00) .
2.
Article II of the CONTRACT is amended to provide for an increase in
the fee to be paid to Engineer for all work and services performed under
the Contract, as amended, so that the total fee paid by the City for all
work and services shall be an amount of $597,272.00.
3.
All other provisions of the Contract, which are not expressly
amended herein, shall remain in full force and effect.
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
City of Fort Worth, Texas [WSSS Repl. Contract 2020 WSM-J]
Prof Services Agreement 7wendment Template [1034201
Revision Cate: November 23, 2021
Page 1 of 2
EXECUTED and EFFECTIVE as of the date subscribed by the City's
designated Assistant City Manager.
APPROVED:
City of Fort Worth
pana Burandoff (Sep 2, 202 .. 8 CDT)
Dana Burghdoff
Assistant City Manager
DATE: Sep 22, 2023
APPROVAL RECOMMENDED:
Chri,+r,,,hPr HACI(Ir (Sen W -)m'� 14 i3 CDT1
Christopher Harder, P. E.
Director, Water Department
Contract Compliance Manager:
ENGINEER
Neel -Schaffer, Inc.
J�Ies P. Amick, P.E.
.Engineering Manager
DATE: 9 r,� z� r2
By signing, I acknowledge that I am the person responsible for the
monitoring and administration of this contract, including ensuring all
performance and reporting requirements.
L am Conlon
Project Manager
APPROVED AS TO FORM AND LEGALITY
wj�� 1
nplarl* ISan 71 7n7-� 14-05 CDT)
Douglas W. Black
Sr. Assistant City Attorney
d4�oponu
aAF FORt add
ATTEST:
pC90 0 4
°6o b�
Jannette Goodall
City Secretary
City of Fort Worth, Texas
Prof services Agreement Amendment Template
Revision Date: November 23, 2021
Page 2 of 2
M&C'. N/A
Date: N/A
Form 1295: N/A
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
(P7c98 Repl. Contract 2020 i13H-J)
(1034201
RL NEEL-SCH,AEEER
Solutions you can build upon
September 7, 2023
Mr. Liam Conlon
City of Fort Worth - Water Department
311 West 10th Street
Fort Worth, Texas 76102
Reference: Design Services for Water and Sanitary Sewer Replacement Contract 2020, WSM-J, City
Project Number 103420; Amendment 1 for Additional Services to Extend the Project by
adding Malvern Trail waterline to the project, and other adjustments to water and sewer
alignments within the existing project scope. Revision 6.
Dear Liam:
Neel -Schaffer, Inc. offers additional Professional Engineering and Surveying Services for this project. These
additional services were requested by the City of Fort Worth, since there has not been a water rehabilitation
project on Malvern Trails from Canberra Court to Mitchell Boulevard. The sanitary sewer in Malvern Trail was
replaced in two projects in 1998 (X-17829) and 1999 (X-17891) respectively and will not be addressed in this
amendment. This amendment will also cover the City's request to re-route the sewer lateral L-2513 off of the
Catholic Diocese of Fort Worth property on Burchill Road to relocate this lateral in Burchill Road to tie to existing
sewer lateral L-2660 at McKenzie Street then proceed northerly along McKenzie Street approximately 155 feet to
the original ending manhole east of the Catholic Diocese of Fort Worth property.
The survey limits of the work are approximately 900 feet of Malvern Trail from Canberra Court to Mitchell
Boulevard for the Malvern Trail portion of the addition and approximately 155 feet of survey will be required on
McKenzie Street to complete the mapping. An additional 600 feet of Burchill Road from the west side of Binkley
Street to its junction with Vaughn Boulevard is included.
The water and sanitary sewer work and associated paving replacement are described below:
TASK DESCRIPTION
Task 1.0 Project Management & Prepare Monthly MBE/SBE Reports. ($2,645.00)
Task 2.1 Additional 150' of 12" waterline (design) in Mitchell Blvd. ($3,460.00)
Task 2.2 Additional 50' of 24" waterline (design) in Mitchell Blvd. at Moresby Street. ($2,235,00)
Task 2.3 Additional 80' of 8" waterline (design) across Mitchell Blvd. at Malvern Trail. ($535.00).
Task 2.4 Realignment of 900' of 12" waterline (design) in Berry Street to middle of road to shorten long
services ($5,010.00).
Task 2.5 Second revision to tle-in for 24" waterline (design) in Mitchell Blvd. at E. Berry Street due to timing
of project with other projects consultant. ($2,235.00)
ARLINGTON • DALLAS • FORT WORTH • HOUSTON • SAN ANTONIO
engineers • planners • surveyors • environmental scientists • landscape architects
515 Houston St., Ste, 651 • Fort Worth, TX 76102 • ph: 817-870-2422 • fax: 817-870-2489 • www,neeI-schaffer.com
Mr. Liam Conlon
September 7, 2023
Page 2
Task 2.6 Second revision to tie-in for 12" waterline (design) in Mitchell Blvd. at E. Berry Street due to timing
of projects with other projects consultant. ($2,235.00)
Task 2.7 Additional 335' of 8" sanitary sewer in Burchill Road (survey & design) to eliminate line through
Catholic Diocese Property. ($3,215.00)
Task 2.8 Additional 154' of 12" sanitary sewer (survey & design) in McKenzie to tie-in to original location.
($2,205.00)
Task 2.9 Revision of waterline in Shropshire Street from an 8" waterline to a 12" waterline from Canberra
Court to the 12" waterline and junction with Sandgate Street with the 12" profile added.
($3,730.00)
Task 2.10 The addition, then removal of the 8" waterline on Burchill's south end (survey & design) from
junction with Binkley Street to junction with Vaugh Boulevard being approximately 600 feet of
additional survey and two plan sheets for the 8" waterline, plus the additional paving area
modifications. ($5,965.00)
Task 3.1 Malvern Trail addition of 870' of 6" waterline replacement (survey & design) with 8" waterline
from Mitchell Blvd. to Canberra Court. ($6,307,00)
Task 3.2 Addition of 860 feet of POL for Malvern Trail from Mitchell Blvd. to Canberra Court. ($855.00)
Task 3.3 Adjustments to Layout and Paving Sheets ($320.00)
Task 8.0 Additional Design Surveys. ($12,810)
This work will require approximately two new double plan sheets for the Malvern Trail 8" water line replacement.
One new plan/profile sheet may be needed for the re-route of the 8" lateral, L-2660, in Burchill Road.
No additional SUE or Geotechnical work is included,
Neel -Schaffer, Inc. proposes to increase the contract amount by $53,760.00 for these additional services. See
attached Level of Effort for backup. All additional services will be performed in accordance with the original
contract dated January 22, 2022.
Summary of Contract Fee
Original Contract Amount
Proposed Amendment No. 1
Revised Contract Amount
$543,512.00
$ 53, 760.00
$597,272.00
O:Mobs\16921 -2020 WSM-AAdm4AContmc1\Am 1\2020 WSM ] Amendment 01_ReO.doox
Mr. Liam Conlon
September 7, 2023
Page 3
If you have any questions or we may be of further service, please call me at 817/870-2422.
Sincerely,
NE L-SCHAFFER, INC.
Richar E. "Rick" Sh pson, RPLS, PS
Senior Project Manager
TBPElS PE Firm Reg. No. F-2697
TOPEtS LS Firm Reg. No.10027200
HL
O:Vobs\16921 - 2020 WSM-AAdmin\Contract\Am 1\2020 WSM-J Amendment IIl_RoO.dom
1
�A
EXHIBIT B-2
Level of Effort Spreadsheet Rev. 2
TASK/HOUR BREAKDOWN
Design Services for
Water and Sanitary Sewer Replacement Contract 2020, WSM-J Amendment 1
City Project No. 103420
Labor (hours)
E(pense
Task No.
Task Description
Principal Project
Project
EIT I CADD Administrative Total Labor
Subconsultant I
Total Expense Task Sub Total Percent
ManaR@@r,
Engineer
Cost
Travel Reproduction
Cost
Complete
Rate
$270 $215
$185
$1401 $160 $95
MWBE Non-MWBE
1.0
Project Management
0 71
01
01 0 12
$2,64$
$0 $0 $0 $0
$0
$2,645
1.1
Managing the Team
I
I
I
Sty
$0
SO
1.2
aq d Reporting
2I
S430
$0
$430
.Com�icto
PrU12.1 esian Zoordination Meeting
1
$215
$0
$215
1.2.2
Design Submittal Review Meetings
21
1
1
$430
$0
$430
1.2.3
Prepare Baseline Schedule
1 11
I
I
$215
$0
$215
Prepare Monthly Progress Reports with
1.2.4
Schedule
I 11
I
I I 6
$785
SO
$785
1.2.5
Prepare Monthly MBE/SSE Reports
I I
I 6
$570
1
$0
$570
2.0
Design
01 221
481
01 1521 0
$37,930
$01 $01 $0 $375
$375
$38,305
2" waerline in M itchell
I J
1
2.1
Blvd. at MoresbylStr ett(sheet 14)
4
8
$2,235
$0
$2,235
Additional 50' of 24" waterline in Mitchell
I
2.2
Blvd. at Moresby Street (sheet 8)
1
4
8
$2,235
$0
$2,235
Additional 0' of 8" waterline across
2.3
Michell BlvBd. at Malvern Trail (sheet 11)
I 1
21
$535
I
I I
$0
$535
Add 'of 12" waterline across
OE.
I
I
I
2.4
By d,atBerry Street (sheet 12Mitchell
11
2
4
$1,225
$01
$1,2251
Realign 900' of 12" waterline in Berry to
middle of road to shorten long services
2.5
(three sheets) (sheets 19,20, & 21)
2
4
24
$5.010
SO
$5,010
Second revision to tie-in for24" waterline
in Mitchell Blvd at E. Berry Street due to
J
time of projects with other projects
J
2.6
consultant
8
$2,235
$0
$2,235
Second revision to tie-in for 12" waterline
in Streetdueto
atth
timethererry
time of projects with other projects
2.7
arrojectBlv
1
4
8
$2,235
$0
$2,235
Additional 335' of 8" sewer in Burchill
Road to eliminate line through Catholic
1
1
2.8
Diocese Property (sheet 32)
2
4
12
$3,090
$125
$125
$3,215
Addit154' of 12" in
I
1
1
I
2.9
tobe� nnal to original locatine(new sh et)1e
2
21
8
S2,080
$1251
$1251
$2,2051
Malvern - 870' of 8" waterline (two
I
2.10
new sheets) I
4
11
I 241
$6,180
I I $1251
$1251
$6,3051
Revision of waterline in Shropshire Street
from an 8" waterline to a 12" waterline
from Canberra Court to the 12" waterline
and junction with Sandgate Street with the
;. 2.1�we�eVLv�inchprolle added.
2
4
16
$3,730
$0
$3.730
Attachment B - Level of Effort Supplement
Typical Water and Sewer Replacement
FWWTR Official Release Date: 8.09.2012
Remaining
Budget
The addition, then removal, of the 8"
waterline on Burchill's south end from
junction with Binkley Street to junction
with Vaughn Boulevard, being
approximately 600 feet of additional
survey and two plan sheets for the 8"
2.12
waterline
3
8
2.13
Malvern Trail - 860' Paving
1 I
1
2.14
Adjustment to Layout & Paving Sheets
I I
I
I
8.0
Survey
I I
01 21
I
0l
I
0
8.1
Design Survey
1 21
1
10.0
Additional Services
of 01
01
01
Additional Uesign Services (as uirected oy
10.1
City)
Totals
0 311
481
01
1
Water Line Footage
1,1501
70%
I
Sewer Line Footage
4891
30%
1,639
100%
(A)
Total Fee
$53.760
(B)
Survey Fee
$10,500
(C)
Total Fee ((- survey Fee
$43,260
1
Water Fee (�0% of C)
Sewer Fee (30% of C)
I
$30.282.00 I
$12,978.00
1 Description
WP Water
Sewer
I Conceptual Design (30%)
30 $9,085.00
$3,893.00
I Preliminary Design (60%)
30 $18,169.00
$7,787.00
1 Final Design (10%)
30 $3,028.00
$1,298.00
I Survey
30 $7,350.00
$3,150.00
I
I Subtotal
I $37.632.00 1
$16,128.00
I Total I
$53,760.00
City of Fort Worth, Texas
Attachment B - Level of Effort Supplement
Typical Water and Sewer Replacement
FWWTR Official Release Date: 8.09.2012
24
$5,965
41
$855
21
$320
41
2
$1,260
$10,5001 $0 $0
41
2
$1,260
$10,5001 1
01
0
$0
1 1 1
$01 Sol $ol
1561
14
$41,835
$10,5001 $01 $01
$0 $5,965
$0 $855
so 5320
$0 $10,500
$11,760
$10,500
511,760
$0 $0
$0
$0
$0
$375 $10,875
$52,710
Project Summary
Total Hours
249
Total Labor
$41,835
Total Expense
$375
MBE/SBE Subconsultant
$10.500
Non-MBE/SBE Subconsultant
$0
10% Sub Markup
$1,050
MBE/SBE Participation
19.5%
Total Project Cost
$53,760.00