HomeMy WebLinkAboutContract 57476-CO2CSC No. 57476-0O2
City of Fort Worth
Change Order Request
Project Name:1
Eagle Mountain Westside Water Treatment Plants Weatherproof Enclosures
City Sec No.: 1 57476
Project No.(s):1
5602010600430i 103335 1 DOE No. I N/A
CityPro). No.: 1 103335
Project Description:I
J�
Weatherproof Enclosures at Eagle Mountain and Westridge Water Treatment Plants
Conlraclod
Crescent Constructors, Inc. Change Order#
2 Date: 9/18/2023
City Project Mgr.1
Dena Johnson, PE cityInspector:
Nathan Gray
Phone Number.
(817) 392-7866 Phone Number:)
(817) 392-4961
Dept. Water
Totals
Contract Time
(Calender days)
Original Contract Amount $7,897,000.00
$7,697,000.00
400
Extras to Dale $72,504.00
$72,504.00
0£0
Credits to Dale
Pending Change Orders (in M&C Process)
Contract Cost to Date $7ff%9r604.00
$7,969,604.00
490
Amount of Proposed Change Order-560,204.00
-$60,284.00
025
Revised ConlractAmount $7,909,220.00
,909,220.00
�197,425,00
515
Original Funds Available for Change Orders $197,425.00
Remaining Funds Available for this CO $124,921.00
$124,921.00
Additional Funding (if necessary)
,
CHANGE ORDERS to DATE (INCLUDING THiS ONE) AS % OF ORIGINAL CONTRACT
0.15%
MAXALLOWABLE CONTRACTAMOUNT(ORiGINAL CONTRACT COST+ 23l)
$9,871,250.00
9 JUSTIFICATION') (REASONS) FOR CHANGE ORDER
Change Order No. 2 provides for the following that were at the Eagle Mountain WaterTreatment Plant
High
Service Pump Station No. 2 and Westside Water Treatment Plant High Service Pump Station No. 1:
• The installation of a duct bank to electrical station ff 113
• Credit for not painting the galvanized structural steel.
Staff concurs with the contractors request for 25 calendar days for the change order.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment
in full (both time and money) for all costs arising out of, or incidental to, the above Change Order.
`Contractor's Companv Name Contractor Name ntr or S lu ,/ date _
Crescent Constructors, Inc. I Todd Hoff I
Inspector
Director Water D t)
a ✓ Har, B✓
hnstpph,, Harder(SIP 2,3
Senior Assistant City Attorney
�e���� W dIra .I
M&C Number I N/A I
Dato
h,lanagef
M.I.
,
Dalem
/N�
9722f239/21/2023
Date
_Project
Ctruotion ervisor Maler Deot)
Dale
Sep 28, 2023
v! / �J 2
& Date
Assistant City Manager
Date
Oct 2, 2023
aha $
Oct 2.2023
Council Action (It Required)
_.
M&C Date Approved NIA
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
FORT WORTH City of Fort Worth
Change Order Additions
Project Name Eagle Mountain Weslside Water Treatment Plants Weatherproof Enclosures
(;fly Sec No.:
57476
Project No.(a): 56020 / 0600430 / 103335 1 DOE No.1 N/A (
City Proj. No.:
10j3335
Project
( Weatherproof Enclosures at Eagle Mountain and Westridge Water Treatment Plants
I
Description
7
Conlraclor Crescent Constructors, Inc. Change Order [ �2
Date:1 9118/2023
City Project Mgr, Dena Johnson, PE City Inspector I Nathan Gray
ADDITIONS
ITEM - ULbUKIPTIUN DEPT Qty Unit
'Unit Cost
- Total
11 Duct bank to electrical manhole #13 Water 1.00 LS
$34,821.00
$34,821.00
Credit for not painting the galvanized structural steel at Westside HSPS #1 Water 1.00 LS
-$95,105.00
495,105.00
12 and Eagle Mountain HSPS 42
Water ($60,284.00)
Page 2 of 4 Additions Sub Total ($60,284.00)
FORT WORTH City of Fort Worth
Change Order Deletions
Project Name Eagle Mountain Westside Water Treatment Plants Weatherproof Enclosures ( City Sec No.: 57476
Project No.(s): 56020106004301103335 DOE No. N/A City Proj. No.: 103335
Project Description Weatherproof Enclosures at Eagle Mountain and Westridge Water Treatment Plants 1
Conlractor I Crescent Constructors, Inc. I Change Order. F-2-1 Date 9/18/2023
City Project Mgr. Dena Johnson, PE City Inspector. I Nathan Gray
DELETIONS
ITEM DESCRIPTION DEPT I City !Unit Unit Cost Total
Water
Deletions Sub Total
Page 3 of 4
MWBE Sub
CO#
MMIBE Breakdown for this Change Order
Type of Service
Previous Change Orders
DATE
Total
Page 4 of 4
Total
AMOUNT
Amount for this CO
$0.00
0
$0.00
CONTRACT MODIFICATION REQUEST: 5
PROJECT: Eagle Mountain & Westside Water Treatment Plant DATE: 1 9/7/2023 I
Pump Station Weatherproof Enclosures
CS##57476
ATTENTION: Dena Johnson, PE
City of Fort Worth
Attention:
The following change in contract on this project is proposed:
A breakdown of cost SIULL be attached
H'a•k stroll not commence until awhorized by die 011WER.
Description of the Proposed Change & Clarifications
Install missing duct bank from viestside existing electreical building to EMI-13. The existing conduit does not run
to the manhole, it's ben investigated but no one knows where the conduit runs to but it does not run to the
manhole. The conduit has even had a camera run in it but no luck to find it's final destination.
TOTAL AMOUNT 1 $ 34,8211
Todd C. Hoff
All work shall be In accordance with the terms, stipulations, and conditions of the
original Contract Documents. If the work herein provided for is Approved by
Change Order, the time of completion will be:
j Increased I By 26 Calendar Days
Decreased
Unchanged
El ACCEPTED I
City of Fort Worth date
❑ REJECTED
CHANGE ORDER SUMMARY
Front Sheet
Eagle Mountain & Westside Water Treatment Plant Pump Station Weatherproof Enclosures
CHANGE DESCRIPTION: Westside Electrical Building Missing duct bank from electrical building to EIVIH-13,
CONTRACTORS MODIFICATION REQUEST 1f005 Job #: 2022-03
Description Labor Material Equipment Subcontract Other
Total
DIRECT COSTS _- 7,620 4,340 - 12,626
241568
LABOR BURDEN 8 FRINGES 55°% 4.191
4,191_
SMALL TOOLS 8% OF LABOR _ 818 _ _
8114
SAFETY SUPPLIES 3% OF LABOR 220
229
Il> Yu dawih— ak=101
SUBTOTALS 11,811 4.340 _ - 12,826 036
28.615
CONTRACTOR MARKUP 1.772 6511 - - 1.894
4.317
BONDS & INSURANCE 3%
aes
TOTAL -
CLARIFICATIONS:
1 Native material for backfill of duct bank excavoGon
2 Flexbase backfill under paving
3
4
Todd Hoff
From: Keith Moyer <kamrac68@gmail.com>
Sent: Monday, August 21, 2023 2:12 PM
To: Todd Hoff
Subject: Credit/Structural
Todd, Credit back for structural on Westside & Eagle Mountain
Project will be $95,105.00
Kam -Rae Coatinas. LLC.
201 W. Mulberry St. Kaufman, Tx
76142
Keith Moyer
Cell: 214-243-0451 1
Contract Compliance Manazer
By signing I acknowledge that I am the person responsible
for the monitoring and administration of this contract, including
ensuring all performance and reporting requirements.
Signature
Dena Johnson
Name of Employee
Project Manager
Title
gaooanU
cF F°°Rr�ad
ATTEST: ~°
pro o=°
/� a�4 lEXAS.00a
�� �bU4ua4
Jannette Goodall
City Secretary
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX