HomeMy WebLinkAboutContract 58704-CO2CSC No. 58704-CO2
FoR'I-VVou-I I I, City of Fort Worth
Change Order Request
Project Name 2023 Concrete Restoration Contract 2 I City Sec # l 58704
Client Project #(s)l 104179
Project Description Repair and replacement of select concrete pavement panels on Meadowbrook Dr.
Contractorl Makou Inc. I Change Order#1 2 I Date 9/25/2023
City Project Mgr.l Iretomiwa Otuyelu l City Inspectorl Travis Strang
Dept.
Original Contract Amount
Extras to Date
Credits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Date
Amount of Proposed Change Order
Revised Contract Amount
Original Funds Available for Change Orders
Remaining Funds Available for this CO
Additional Funding (if necessary)
TPW
$1,449,450.00
$184,750.00
$1,634,200.00
$0.00
$1,634,200.00
$0.
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT I
MAX ALLOWABLE CONTRA CT AMOUNT (ORIGINAL CONTRACT COST+ 25%)
Contract Time
Totals (CD)�
$1,449,450.00 80
$184,750.00
$1,634,200.00 180
35
$1,634,200.00 215
$0.00
12.75%
$1,811,812.50
This change order is to add new bid items identified by staff, which require an additional scope after substantial completion of work. The new items are: (1) Crosswalk pavement
markings to include the black contrast markings. (2) ADA ramp type M-3 at the intersection of Meadowbrook & Stark due to the location of the bus shelter directly across the
ADA Ramp. (3) Replacement of underground enclosure of the traffic signal assembly.
This change order will also add 35 calendar days to contract days due to these delays: (1) Delays due to scheduling conflict (15 days): The Contractor sent the notice of
substantial completion on 08/25/2023, but due to scheduling conflicts, the pre -final inspection was not scheduled until 09/07/2023. (2) Additional scope (21 days): the additional
scope that was added after substantial completion, which included the installation of two R-1 Ramps, one M-3 Ramp, the revised crosswalk pavement markings, and a driveway
removal and replacement at 5160 Meadowbrook Dr. This delay includes the time it took to make the decisions (which was ongoing till 09/13/2023) and the time to execute this
change order.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full
(both time and money) for all costs arising out of, or incidental to, the above Change Order. The Project/Program Manager signing below acknowledges that
he/she is the person responsible for the monitoring and administration of this contract, including ensuring all performance and reporting requirements.
ontractor's C...a—,v ontractor Na
Makou Inc Magsood Khan�,��,„s,°„
-1119
Date
Oct 5, 2023
Inspector/Inspection Supervisor
Date
Project and Contract Compliance Manager
Date
Oct 9, 2023
Oct 5, 2023
Program Manager
Date
Senior Capital Project Officer
Date
r—«;
Oct 9, 2023
Oct 9, 2023
Assistant Director (Dept)
Date
Director, Contracting Department (Dept)
Date
P'g'-, L. v✓ad
Oct 10, 2023
A- 9
Oct 10, 2023
ssistant Cit Attorney
Date
Assistant City Manager
Date
(
Oct 11, 2023
�+��
Oct 15, 2023
Council Action if re wired
Number M&C e,� n - M&C Date Approved
ATTEST:
Jannette Goodall, City Secretary
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
T: N �wide r�i City of Fort Worth
Change Order Additions
Project Name 1 2023 Concrete Restoration Contract 2 City Sec # 1 58704
Client Project # 1 104179 1
Contractorl Makou Inc. I PMI Iretomiwa Otuyelu Inspectorl Travis Strang I
Change Order Submittal # O2 Date 1 9/25/2023
ADDITIONS
IIEM UESCKIPIIUN UEPI Uty Unit Unit Cost total 1
31 3217.0501 Furnish/Install 24" Preformed I hermoplashc Contrast PW 180.00000000 LF $22.OU $3,960.001
32 3213.0501 Remove and Replace barrier Free Ramp, Type M-3 TPW 1.00000000 EA $3,000.OU $3,000.001
33 Replacement of Underground Enclosure of Traffic Signal Assembly TPW 1.00000000 LS $1,770.00 $1,770.00�
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
1
I
TFW $8,730.001
1
1
1
Sub Total Additions $8,730.001
Change Order Additions Page 2 of 4
T t� V'�r;'r City of Fort Worth
T Change Order Deletions
Project Name 1 2023 Concrete Restoration Contract 2 I City Sec # 1 58704
Client Project# 1 104179 1
Contractorl Makou Inc. I PMI Iretomiwa Otuyelu I Inspectorl Travis Strang I
Change Order Submittal # O2 Date 1 9/25/2023 1
DELETIONS
I I tM UtSURIP I IUN ULH I
18 321 t.0001 4" Uouble solid I hennoplastic (HAS) center Lane Line I PVV
20 321 t.UbU1 24' JLU Pvmt marKing HAt I PVV
24 3213.0501 Remove and Replace Barrier Free Ramp, Type R-1 TPW
Luy unit unncost Iotai 1
213.000UUUUU LF $1U.UU $2,13umul
200.000000UU LF $18.UU $3,bUUAUI
1.000OOOOU Fes, $3,000.OU $3,000.001
TOW $8,730.001
1
1
1
Sub Total Deletions $8,730.001
Change Order Deletions Page 3 of 4
MISBE for this Change Order
M/SBE Sub Type of Service Amount for this CO
Total $0.00
Previous Change Orders
Co # DATE I AMOUNT
6/29/2023 $184,750.00
Total I $184,750.00 1
FORT WORTH
Routing and Transmittal Slip
Transportation and Public Works
Department
DOCUMENT TITLE: 2023 CONCRETE RESTORATION CONTRACT 2
M&C; 23-0588 CPN, 104179 CSO # 58704 DOC# 2
Date:
To: Name Department Initials Date Out
1
Ann Estes
BSP
AELL
Oct 6, 2023
2
Magsood Khan
Vendor
" k
Oct 5, 2023
3
Travis Strang
TPW
Oct 9, 2023
4
Iretomiwa Otuyelu
TPW
Oct 5, 2023
5
Omar Elbagalati
TPW-
Oct 9, 2023
6
Mary Hannah
TPW
Oct 9, 2023
6
Patricia Wadsack
TPW
P-PLW
Oct 10, 2023
7
Lauren Prieur
TPW
d�
Oct 10, 2023
7
Doug Black
Legal
d�
Oct 11, 2023
8
William Johnson
CMO
4-
Oct 15, 2023
9
Jannette Goodall
CSO
jsG L4
Oct 16, 2023
10
TPW Contracts
TPW
CC: Program
Manager, Sr. CPO, TPW BSAP Recon Team, TPW Records Room,
TPW Contracts
-Bus Sppt: -Prg Mgr:
-Sr. CPO:
DOCUMENTS FOR CITY MANAGER'S SIGNTURE: All documents received from any and all City
Departments requesting City Manager's signature for approval MUST BE ROUTED TO THE
APPROPRIATE ACM for approval first. Once the ACM has signed the routing slip, David will review
and take the next steps.
NEEDS TO BE NOTARIZED: ❑ Yes X No
RUSH: ❑ Yes X No SAME DAY: ❑ Yes X No NEXT DAY: ❑ Yes X No
ROUTING TO CSO: ❑ Yes ❑ No
Action Rea it :
❑ As Requested
❑ For Your Information
X Signature/Routing and or Recording
❑ Comment
❑ File
❑ Attach Signature, Initial and Notary Tabs
Return to: Please notify TPWContracts(dfortworthtexas.gov for pickup when complete. Call ext. 7233 or
ext. 8363. Thank you!