Loading...
HomeMy WebLinkAboutContract 31696-A7 AMENDMENT NO. 7 STATE OF TEXAS S CITY SECRETARY CONTRACT NO.3�k,1t -A�l (M&C Not Required) COUNTY OF TARRANT S WHEREAS, the City of Fort Worth (City) and TranSystems Corporation dba TranSystems Corporation Consultants, (Engineer) made and entered into City Secretary Contract No. 31696, (the Contract) which was authorized by the City Council by M&C C-20631 on the 5t' day of April, 2005 and subsequently revised by six previous amendments; and WHEREAS, the Contract involves engineering services for the following project: Water and Sanitary Sewer Replacement for SH-121T (Southwest Parkway) , Part 1 from Hulen Street to Summit Avenue. WHEREAS, it has become necessary to execute Amendment No. 7 to said Contract to include an increased scope of work and revised maximum fee; NOW THEREFORE, City and Engineer, acting herein by and through their duly authorized representatives, enter into the following agreement which amends the Contract: 1. Article I of the Contract is amended to include the additional engineering services specified in a proposal letter dated April 5, 2011, a copy of which is attached hereto and incorporated herein. The cost to City for the additional design services to be performed by Engineer total $49, 444 .00. 2. Article II of the Contract is amended to provide for an increase in the maximum fee to be paid to Engineer for all work and services performed under the Contract, as amended, so that the total fee paid by the City for all work and services shall not exceed the sum of $1,485, 677.00. OF ;�::,_�. r, I A x%Y `. ' . .. TY 3 . All other provisions of the Contract which are not expressly amended herein shall remain in full force and effect. EXECUTED on this the �� day of 2011, in Fort Worth, Tarrant County, Texas. ATTEST: �'00000ro�po p o o d Marty Hendrix o o°xd City Secretary ��A co 000�c dd 0000000000 a ann�QaQ�aper APP REC ED: APPROVED: S. Frank Crumb, P.E. Fernando Costa Director, Water Department Assistant City Manager TranSystems Corporation d/b/a TranSystems Corporation Consultants [NO M&c REUIRI:I) Engineer By: C Name: ul Pena III, P.E. , Principal 500 W. 7 Street, Suite 600 Fort Worth, TX 76102 APPRO AS TO FORM AND LEGALITY: Assis Y--Attorney -2- OF ` '; rY Liam Conlon,Project Manager IEW—Y97 Water City of Fort Department II 1000 Throckmorton Street — Fort Worth,TX 76102-6311 RE Amendment 7 of SH 121T,Part 1 Water and Sanitary Sewer Systems Improvements City Project No.00203,D.O.E.4855 Date:4/5111 Dear Mr.Conlon, TranSystems(TSC)appreciates the opportunity to provide additional services with respect to the above referenced project We have prepared this amendment request for services regarding engineering and surveying. These services are specifically for the relocation of a 42'water line related to SH121T and UPRR Improvements,additional final design issues and conslniction services. Below is an itemized breakout of these services: I. Stoneciate Blvd 42"Water Line Design Subtotal$35,618 This design replaces 150 linear feet of shallow 42'water line across Slonegate Blvd.The improvements will finalize the rerouting of the 42'water One that Is In oonflict with the Hulen St Bridge and UPRR improvements. The design eliminates future maintenance concerns with the existing concrete encasing pipe and provides favorable clearance from an adjacent 48'sanitary sewer and TPW facififies. Services include the following: A. Survey lump Sum $ 8,062 1. Design survey across Stonegate Blvd.right-of-way. 2. Exploratory excavations to identify existing water line elevations. TSC will coordinate with the contractor to survey points along the existing 42'water fine within Hulen St, 16'water One within Stonegate Blvd., and existing joints on the southeast comer of Stonegate Blvd.and Hulen St. These points will define the limits of the project 3. Research utilities,and coordinate with public utility locators. B. Conceptual Design Lump Sum $ 4,333 1. Attend meetings with the City to review alternative designs. 2. Develop an evaluation matrix and exhibits for 3 design alternatives. 3. Develop an opinion of probable construction cost for the alternatives. C. Preliminary Design Lump Sum $ 4,891 1. Attend meetings wilh the City. 2. Develop plan profile sheets. 3. Incorporate City review comments. 4. Develop aerial exhibits to Identify impacts to traffic and local businesses. D. Final Design Lump Sum $18,182 1. Attend design meetings with the City. 2. Finalize plan and profile sheets. 3. Design 16'water fine connection to proposed 42'water One. Design anchor thrust ring. 4. Design phase 1 traffic control plan for the bore pit on the northeast corner of Hulen St(2 sheets). 5. Design phase 2 traffic control plans for lane closures on Stonegate Blvd.(13 sheets). 6. Design phase 3 traffic oDnW plan for closure of Stonegate Blvd(1 sheet) 7. Attend Water Dept and TPW traffic control review meetings(5 total). 8. Coordinate final desijn with contractor and pipe manufacturer. 9. Develop an opinion of probable cost. 10. Provide change order assistance. SH121amndment 7 040411.doc 1 E. Reproduction Lump Sum $ 150 1. Distribute plans to City(mylar and paper sets). 2. Distribute cumulative sets of SH121T Part 18 plans and change order plans to City and Contractor. II. Miscellaneous Services Subtotal$13,826 The following items are additional services: A. Construction Services Lump Sum $6,850 The City requires TranSystems to remain active with the SH121T construction phases. TranSystems will provide backup information and interpret documents when there are questions or changes in the field conditions. Tasks include: 1. SH121T Part 16 construction meetings(3)and general services. This includes assisting in the placement of the UPRR meter vault and backflow preventer. 2. SH121T Part 18 constriction meetings and general services. 3. SH121 T Part 18 shutdown site visits. d SH121T Part 18 Additional Services Lump Sum $6,976 The following items require additional assistance beyond the design scope: 1. Meetings with the City for the Southwest Transmission Main Shutdown on the north side of the Trinity River(4). 2. Revise sequence of Construction for Southwest Transmission Main Shutdown for Stonegate Blvd. Improvements. 3. Construction services for placement of a water line within the Kinderplate school property. 4. Redesign of the Hartwood Dr.water line. Includes site visits(3)and redesign. TOTAL Lump Sum Fee of $49,444 Breakout of Amendment 7 by Work Phase Water Sewer Total Survey 51-Design Survey $ 8,062.00 $ 0 $ 8,062.00 Engineering 31-Concept Design $ 0 $ 0 $ 0 32-Preliminary Design $ 0 $ 0 $ 0 33-Final Design 41 382.00 $0 41 382.00 Engineering Totals $41,382.00 $ 0 $ 41,382.00 Total(Survey and Engineering) $49,444.00 $ 0 $ 49,444.00 H 1 z: cne t.,ime n t. I C4t'41_- 1ec Summary of the Contract and Amendments Original Contract $ 658,405.00 Amendment 1. $ 49,050.00 M-133 added to project.(engineering and surveys for project) Amendment 2. $ 91,089.00 Parkview Dr.water line(engineering and surveys for project) added to project,additional meetings,misc.soil boring for 4 projects. Amendment 3. $130,476.00 Beckham water design,M-133 design between Landers and Montgomery, USACE specification and shop drawings for Hulen St.42°water line,and reproduction. Amendment 4. $ 24,867.00 W.Vickery water line design and subsurface evaluation. Amendment 5. $179,441.00 Review and coordinate UPRR related Fort Worth utility improvements,develop bid documents for Part 18 Trinity River Bridge utility protection report,and M- 272-D protection review. Amendment 6. $302,905.00 Design services for Stonegate Blvd.and Hulen St area. Amendment 7 $ 49,444.00 See this amendment Contract Total $1,485,677.00 This proposal does not include: 1. Construction management If you have any questions or require additional information please give me a call. Sincerely, TranSystems Corporation Consultants Kent Lunskl,P.E. Project Manager Copy: Craig Schellbach,P.E.,Team Leader Al2iamer.Wnent / U40411.dou j City of Fort Worth SH121T Part 1 (Southwest Parkway) Amendment 7 415!2011 RPLS ec rew E4 E3 T4 Total 135.00 78.00 900.00 1 .00 F12 I.Stone ate Blvd.Water Line Desi n S 3 618.00 A.Surve a oez.00 Stone ate Blvd Des' n 2 16 12 S 2,71800 St ate Blvd.E oral excavations(4) 4 16 16 $ 5,032.00 OUACoordination 1 1 1 7 312.00 one Design 333. Meetings w/City(2 4 8 S 1.856.00 Mafrot and Exhibit 2 8 8 S 2,340.00 0 on of Probable Cost 1 3 137.00 relimhna ry Desion Meetl w/C (1) 4 8 1 $ 1,856.00 Plan 8 Profile 16 3 2,192.00 City Review/Comments 2 2 $ 490.00 Exhibits 1 2 S 353.00 D. Rnal Design 18 182.00 Meetirw W CRY 2 2 3 654.00 Plan 8 Profile 1 4 8 3 1,412.00 MISC.Details anchor ring.16-waten 16 4 S 2.624.00 TCP-Hulen Cross' 2 ants 16 8 S 3,904.00 TCP-Stonegate Blvd.(dosed hall street-13 shin) 8 18 12 3 5,008.00 TCP-St ate full street closure-1 sht) 4 4 4 $ 1,740.00 City Review/Comments 2 water Dept.3 TP 7 4 $ 1,391.00 Coordination with Contractor/Pipe Manufacturer 4 $ 548.00 Opinion of Probable Cost 1 $ 137.00 Ch a Order Assistance 4 2 $ 764.00 .Re roducUon 140,00 War and Copies for Improvements $ 10000 Reproduction of Cum.Part 18 Sets(2 full and hall sizes) $ 50.00 11.Miscellaneous 13 826.00 A Construction Services Is 4860.W Part 16 Construction Meetings Construction Meech s 20 $ 2.740.00 Construction Meetings/Services Part 18 15 S 2.05500 Part 18 Shutdown Site Vlsfta 00 d s) 15 $ 2,055 FO- Part t AMona Services 6.976.00 Meeting with City for Shutdown#1 Meetings 4) 12 $ 1.64400 Revise Sequence of Construction for Shutdown#2 6 $ 1,096.00 Kin late Construction Services 16 2 S 3,256.00 Hartwood Water Line Site Visila(3)/Redesign 4 4 S 980.00 Total S 49,444.00 Water Sewer Total Surveying S 8.06200 $ 3 8,062.00 Engineering Concept 3 $ $ Prelim $ $ $ Final 541,38200 S S 41,38200 Engineer Total $41.38200 $ $ 41,382.00 Total S49,44400 S S 49 444.00 Original Contract $ 658,405 00 Amendment 1.M-133 added to project.(enginewing and surveys for project) $ 49,050 00 Amerdment 2 Parkview Dr.water line(engineering and surveys for project) $ 91,08900 Amendment 3 Beckham water cesign,M-133 design between Landers and Montgomery, USACE specs.and shop drawings for Huien St 42' rva:er line $ 130,475 00 Arrendment 4.W_Vickery water line design and subsurface evaluation $ 24,86700 ArrerKiment 5.Review and coordinate UPRR related Fort Worth utility improvements,develop led documents for Part 18 Trinity River Bridge utility protection report,and M-272-0 protection review $ 179,44100 Amendment 6 Part 18 related improvements and sewer M-2 12D relocation by Htten St Bridge $ 302,905.00 Amendment 7 See this amendmeM $ 49,444 00 Contract Total $1,485,677 00