HomeMy WebLinkAboutContract 56846-A1AMENDMENT No . 1 CSC No. 56846-Al TO CITY SECRETARY CONTRACT No. 56846 WHEREAS, the City of Fort Worth (CITY) and Teague Nall & Perkins, Inc., (ENGINEER) made and entered into City Secretary Contract No. 56846, (the CONTRACT) which was authorized by M&C 21-0875 on the 9th day of November, 2021 in the amount of $188,066.00; and WHEREAS, the CONTRACT involves engineering services for the following project: Water and Sanitary Sewer Replacement Contract 2019, WSM-K; and WHEREAS, it has become necessary to execute Amendment No. 1 to the CONTRACT to include an increased scope of work and revised fee. NOW THEREFORE, CITY and ENGINEER, acting herein by and through their duly authorized representatives, enter into the following agreement, which amends the CONTRACT: 1. Article I of the CONTRACT is amended to include the additional engineering services specified in proposal attached hereto and incorporated herein. The cost to City for the additional design services to be performed by Engineer totals $329,198.00. 2. Article II of the CONTRACT is amended to provide for an increase in the fee to be paid to Engineer for all work and services performed under the Contract, as amended, so that the total fee paid by the City for all work and services shall be an amount of $517,264.00. 3. All other provisions of the Contract, which are not expressly amended herein, shall remain in full force and effect. OFFICIAL RECORD CITY SECRETARY FT. WORTH, TX Prof Services Agreement Amendment Template Revision Date: November 23, 2021 W&SS Contract, 2019 WSM-K Page 1 of 2 CPN 103416 EXECUTED and EFFECTIVE as of the date subscribed by the City's designated Assistant City Manager. APPROVED: City of Fort Worth 7�allz� 3�r�i�l� Dana Burghdoff (Nov 4, 2023 '�'3 CST) Dana Burghdoff Assistant City Manager DATE: Nov 14, 2023 APPROVAL RECOMMENDED: Chris-1-0ohBY Rar- e Christopher Harder (Nov 14, 2023 14:47 CST) Chris Harder, P.E. Director, Water Department Contract Compliance Manager: ENGINEER Teague Nall & Perkins_J2C. J6nathan Bengfort, 'PE. Director of Engineering Services, Associate Principal DATE: By signing, I acknowledge that I am the person responsible for the monitoring and administration of this contract, including ensuring all performance and reporting requirements. Dena Jo nson, P.E. Project Manager APPROVED AS TO FORM AND LEGALITY: DBlack (Nov 14, 2023 16:44 CST) Douglas W. Black Senior Assistant City Attorney 9M �aA oFa °9d ATTEST: ova o=p J�Uan"n�et`to S. Goodall City Secretary Prof Services Agreement Amendment Template Revision Date: November 23, 2021 Page 2 of 2 M&C . 23-0912 Date: 10/31/2023 Form 1295: 2023-1077953 OFFICIAL RECORD CITY SECRETARY FT. WORTH, TX W&SS Contract, 2019 WSM-K CPN 103416 tnp Contract Amendment No. 1 To: Dena Johnson, PE — City of Fort Worth CC Tony Sholola, PE — City of Fort Worth From: Andrew Luce, PE REV Date: September 25, 2023 RE: Additional Professional Services Water and Sewer Replacements Contract 2019, WSM-K (Project No. 103416) www.tnpinccom engineers surveyors landscape architects TEXAS FORT WORTH DENTON ALLEN HEATH KATY Per the City's request, we offer this contract amendment for additional water and sanitary sewer design services associated with the WSM-K Water and Sewer Replacement contract. The City has requested that TNP expand the scope of the project to include additional water line and sewer line replacements as shown in the tables below: WATER IMPROVEMENTS Street Name Notes Size Length (in) (LF) 24" Proposed Water Line 24 3,263 2,359 LF of 24" Cast Iron Water Line to be Abandoned - - 1 2" Cast Iron Water Line to be Replaced 12 355 Biddison Street, Ryan Avenue, Dickson 8" Cast Iron Water Line to be Replaced 8 632 Street, James Avenue, and Ripy Street 6" Cast Iron Water Line to be Replaced 8 2,564 4" Cast Iron Water Line to be Replaced 8 310 2" Cast Iron Water Line to be Replaced 8 103 Total 7,227 SEWER IMPROVEMENTS Size Length Street Name Notes (in) (LF) Ripy St (Ryan Avenue tol 80 LF east of Willing 6" Concrete Sewer Line to be Replaced 8 543 Avenue) Total 543 The addition of the water and sanitary sewer lines shown above will include the following additional services: • Design of 7,227 LF of Water Line • Design of 543 LF of Sanitary Sewer Line • Design Surveys • Two (2) BNSF Railroad Permits • Geotechnical Borings at both RR crossings • SUE investigation at both RR crossings • Encroachment Agreement for Pipeline Crossing (16" Williams MLP) TNP Firm < Registrations Texas Board of Professional Engineers and Land Surveyors I Engineering Firm No. F-230 I Surveying Firm No. 1001 1600 1 101 94381 1 1001 1 601 Texas Board of Architectural Examiners Firm No. BR 2673 Summary of Contract Fee: Original Contract Amount: $ 188,066.00 Amendment No. 1 $ 329.198.00 Revised Contract Amount $ 517,264.00 Please find attached the following contract documents: • Attachment B • Exhibit B-1 • Exhibit B-2 • Exhibit B-3 • Attachment C • Attachment D • Attachment E Sincerely, tnp teague nall & perkins Andrew Luce, P.E. Compensation Engineer Invoice Level of Effort Spreadsheet Conceptual Opinion of Probable Construction Cost Changes and Amendments to Standard Agreement Project Schedule Project Map ATTACHMENT B COMPENSATION Design Services for Water and Sewer Replacements Contract 2019, WSM-K Contract Amendment No. 1 City Project No. 103416 Lump Sum Project Compensation A. The ENGINEER shall be compensated a total lump sum fee of $329,198 as summarized in Exhibit B-1 — Engineer Invoice and Section IV — Summary of Total Project Fees. The total lump sum fee shall be considered full compensation for the services described in Attachment A, including all labor materials, supplies, and equipment necessary to deliver the services. B. The ENGINEER shall be paid monthly payments as described in Section II - Method of Payment. Method of Payment A. Partial payment shall be made to the ENGINEER monthly upon City's approval of an invoice prepared and submitted by the ENGINEER in the format and including content as presented in Exhibit B-1, Progress Reports as required in item 111. of this Attachment B, and Schedule as required in Attachment D to this Agreement. B. The estimated current physical percent complete as required on the invoice shall be calculated from the progress schedule as required in Attachment D to this Standard Agreement and according to the current version of the City of Fort Worth's Schedule Guidance Document. C. The cumulative sum of such monthly partial fee payments shall not exceed the total current project budget including all approved Amendments. D. Each invoice shall be verified as to its accuracy and compliance with the terms of this Agreement by an officer of the ENGINEER. III. Progress Reports A. The ENGINEER shall prepare and submit to the designated representative of the Water Department monthly progress reports and schedules in the format required by the City. City of Fort Worth, Texas Attachment B Revised Date: 12/9/2022 Page 1 of 3 AM ATTACHMENT B COMPENSATION IV. Summary of Total Project Fees Firm Primary Responsibility Prime Consultant Teague Nall & Perkins, Engineering Design, SUE Inc. Proposed MWBE Sub -Consultants Gorrondona & Surveying Associates, Inc. HVJ Associates Geotechnical Investigation Non-MWBE Consultants Corrpro Companies, Cathodic Protection Design Inc. Project Number & Name City MWBE Goal = 10% City of Fort Worth, Texas Attachment B Revised Date: 12/9/2022 Page 2 of 3 TOTAL Fee Amount $248,324 75.4 $40,874 12.4 $20,000 6.1 $20,000 6.1 $329,198 100% Total Fee MWBE Fee MWBE % $329,198 $60,874 18.5% Consultant Comm tted Goal = 18.5% AM EXHIBIT "13-1" ENGINEER INVOICE (Supplement to Attachment B) Insert required invoice format following this page, including negotiated total budget and allocations of budgets across work types and work phases. City of Fort Worth, Texas Attachment B Revised Date: 12/9/2022 Page 3 of 3 AM Professional Services Invoice Project: iWater and Sanitary Sewer City Project #: 1103416 City Sec Number: Company Name: (Teague Nall & Perkins, Inc. Consultant's PM: Andrew Luce, P.E. Supplier Invoice M Payment Request M Service Date:From Service Date:To Invoice Date: ,oject Manager:) Dena Johnson Summa Contract 2019, WSM-K - Amendment 1 Supplier Instructions: Fill in green cells including Invoice Number, From and To Dates and the included worksheets. When your Invoice is complete, save and close, start Buzzsaw and Add your invoice to the Consultant folder within Project's folder. email. r5237 e to inc.com Office Address: N. Riverside Dr., Suite 100, Fort Worth, TX 76102 Telephone: -665-8217 Fax: -336-2813 Remit Address: 5237 N. Riverside Dr., Suite 100, Fort Worth, TX 76102 Agreement LTD Agreement Amendment Amount to Completed Percent ($) Invoiced Current Remaining Sheet FID and Work Type Description Amount Amount Date Amount Spent Previously Invoice Balance Work Type 1 Water $306,192.00 $306,192.00 $306,192.00 Work Type 2 Sewer $23,006.00 $23,006.00 $23,006.00 Work Type 3 Work Type 4 Work Type 5 Work Type 6 Totals This Invoice $329,198.00 $329,198.00 $329,198.00 Overall Percentage Complete: Professional Services Invoice Project Manager: Dena Johnson Project: Water and Sanitary Sewer Replacements Contract 2019, WSM-K - Amendment 1 City Pro)ect #: 103416 Work Type Desc: Supplier Instructions: FID: City Sec Number: Fill in green cells including Percent Complete and Invoiced Previously Quanities Purchase Order: When your Invoice is complete, save and close, start Buzzsaw and Add your invoice to the Consultant folder within Project's folder. Company Name: Teague Nall & Perkins, Inc. Supplier's PM: Andrew Luce, P.E. email: aluce@tnpinc.com Supplier Invoice #: Office Address: 5237 N. Riverside Dr., Suite 100, Fort Worth, TX 76102 Payment Request #: Telephone: 817-665-8217 Service Date:From Fax: 817-336-2813 Service Date:To Invoice Date: Remit 5237 N. Riverside Dr., Suite 100, Fort Worth, TX 76102 Pay Items Agreement LTD Agreement Amendment Amendment Amount to Completed Description Amount Number Amount Date Amount 31 -Conceptual Design Water $306,192.00 $306,192.00 32 - Preliminary Desiqn Water 33 - Final Desiqn Water 65 - Construction Services Water 51 - Preliminary Survey Water 32 - Geotech Report Water 33 - Printinq Water Totals This Unit: $306192.00 $306192.00 Overall Percentage Complete: Percent ($) Invoiced Current Remaining Spent Previously Invoice Balance $306,192.00 Professional Services Invoice Project Manager: Dena Johnson Project: Water and Sanitary Sewer Replacements Contract 2019, WSM-K - Amendment 1 City Project #: 103416 Work Type Desc: Supplier Instructions: FID: City Sec Number: Fill in green cells including Percent Complete and Invoiced Previously Quanities Purchase Order: When your Invoice is complete, save and close, start Buzzsaw and Add your invoice to the Consultant folder within Project's folder. CompanyName: Teague Nall & Perkins, Inc Supplier's PM: Andrew Luce, P.E. Supplier Invoice #: Payment Request #: Service Date:From Service Date:To Invoice Date: Pay Items Description 31 - Conceptual Design 32 - Preliminary Design 33 - Final Design 85 - Construction Services 51 - Preliminary Survey 32 - Geotech Report 33 - Printing email: aluce@tnpinc.com Office Address: 5237 N. Riverside Dr., Suite 100, Fort Worth, TX 76102 Telephone: 817-665-8217 Fax: 817-336-2813 Remit Sewer 5237 N. Riverside Dr., Suite 100, Fort Worth, TX 76102 Agreement LTD Agreement Amendment Amendment Amount to Completed Amount Number Amount Date Amount $23,006.00 $23,006.00 Percent ($) Invoiced Current Remaining Spent Previously Invoice Balance $23,006.00 Totals This Unit: $23,006,00 $23,006.00 $23006.00 Overall Percentage Complete: Attachment B - Level of Effort Spreadsheet (REV 9-18-23) TASK/HOUR BREAKDOWN Design Services for WATER AND SANITARY SEWER REPLACEMENTS CONTRACT 2019, WSM-K Contract Amendment No. 1 City Project No. 103416 08.04.2023 Task Description Project Task No. Director Rate $290 Project Manager $270 Project Engineer $180 EIT/ Designer $160 Labor CADD 5/I SUE Manager $11 $190 hours) -Man Designating Crew $200 2-Man Vac. Truck Crew $320 RPLS $250 Survey Tech $150 2-Man Surv. Crew $200 Admin./ Clerical $85 Total Labor Cost Expense Subconsultant MWBE I Non-MWBE Travel Reproduction Total Expense Cost Task Sub Total 1.0 Design Management 30 30 14 0 0 0 0 0 0 0 0 0 1.1 Managing the Team 1.1 Proiect Management 1.1. CA/QC 30 1.2 Corwrn.S a7o nr{Reoorting 1.2. Pre -Design oo motion Meeting 2 2 1.2 Proiect Update Meetings 4 4 1.2. Design Submittal Review Meetings 8 8 1.2 Prepare Baseline Schedule 2 Prepare Monthly Progress Reports with 1.2. Schedule 6 1.2 Prepare Monthlv MNVBE Reports 1.2. Coordination with Other Agencies 8 2.0 Conceptual Design (30 Percent) 0 36 72 96 80 0 0 0 0 0 0 0 $19.320 $0 $0 $0 $0 $0 $19,320 $0 $0 $0 $0 $0 $0 $8,700 $0 $0 $8,700 $0 $0 $900 $1,800 $0 $900 $0 $1,800 $3,600 $540 $0 $3,600 $0 $540 $1,620 $0 $1,620 $0 $2,160 $0 $0 $0 $2,160 $48,040 $20,000 $0 $0 $200 $20,200 $68,240 2.1 2.2 2.3 2.4 Data Collection Geotechnical Investigations Conceptual Design Package Construction Estimates (30%) 32 16 48 8 24 6 8 8 $6,720 $0 $20.000 $200 $0 $6,720 $20,000 $20,000 $37,520 $3,800 $0 $37,520 $200 $4,000 3.0 Preliminary Design (60 Percent) 0 48 84 136 128 0 0 0 0 0 0 0 $65,840 $0 $0 $0 $200 $200 $66,040 3.1 Preliminary Design Drawings 3.2 Constructability Review 3.3 Utility Clearance 3.4 Traffic Control Plan 3.5 Attend Public Meeting / Prepare Disolays 3.6 Construction Estimates (60%) 40 J 41 60 8 4 8 120 8 8 120 8 $55,800 $0 $200 $200 $56,000 $0 $0 $1,440 $3,000 $0 $1.440 $0 $3,000 $1,800 $3,800 $0 $1.800 $0 $3,800 4.0 Final Design 0 38 58 96 128 0 0 0 0 0 0 0 $52,060 $0 $20,000 $0 $500 $20,500 $72,560 4.1 4.2 4.3 4.4 Final Draft (90%) Construction Plans and Specifications Cathodic Protection Design Final (100%Plans and Specifications Construction Estimates (90%and 100%) 24 12 2 36 18 4 60 32 4 96 3 $34 560 $20,000 $250 $250 $250 $34 810 $0 $15.600 $1,900 $20,000 $20,000 $250 $15,850 $0 $1,900 5.0 Bid Phase 0 10 18 8 4 0 0 0 0 0 0 0 $7,720 $0 $0 $0 $1,000 $1,000 $8,7 20 5.1 Bid Support Upload and Sell Contract Documents and 5.1. Maintain Plan Holders List 4 5.1 Issue Addenda (assumes 3) 6 4 5.1. Attend Pre -bid Conference 2 2 5.1 Tabulate Bids and Recommend Award 2 4 5.1. Issue Conformed Contract Documents 4 4 $0 $640 $1.000 $1,000 $1,000 $0 $640 $3,780 $900 $0 $3,780 $0 $900 $1,260 $0 $1,260 $1,- to $0 $1,140 I I 6.0 Construction Phase Services 0 26 42 18 12 0 0 0 0 0 0 0 $18,960 $0 $0 $0 $0 $0 $18,960 6.1 Con��ucti( Support 6.1. QNend Preconskruction Conference 2 6.1 Attend Public Meetino 4 6.1. Proiect Site Visits 12 12 6.1 Request for Information Review 16 2 6.1. Change Order Review 6.1 Final Walk Through and Punch List 4 6.2 Record Drawings 6 12 $0 $540 $0 $0 $0 $540 $1,440 $4,080 $0 $1,440 $0 $4,080 $8.640 $0 $0 $8.640 $0 $0 $1.800 $2,460 $1.800 $021 $2,460 City of Fort Worth, Texas Attachment B - Level of Effort Supplement PMO Official Release Date: 5.19.2010 1 of2 Attachment B - Level of Effort Spreadsheet (REV 9-18-23) TASK/HOUR BREAKDOWN Design Services for WATER AND SANITARY SEWER REPLACEMENTS CONTRACT 2019, WSM-K Contract Amendment No. 1 City Project No. 103416 08.04.2023 Task Description Project Task No. p Director Project Manaqer Project Engineer EIT/ Designer CADD Labor(hours) SUE Manager 2-Man Desi natin Crew 9 2-Man Vac. Truck Crew RPLS Surve Tech 2-Man Sum. Crew Admin./ Clerical Total Labor Cost $0 Expense Subconsultant MWBE I Non-MWBE $0 $0 Travel $0 Reproduction $0 Total Expense Cost $0 Task Sub Total $0 Rate $290 7.0 ROW/Easement Services 0 $270 $180 $160 $125 $190 $200 $320 $250 $150 $200 $85 01 0 01 0 01 0 0 01 01 0 0 Right -of -Way Research and Boundary (Office 7.1 and Field Work) Right-of-Way/Easement Preparation and 7.2 Submittal 7.3 Temporary Right of Entry $0 $0 $0 $0 $0 $0 $0 8.0 Survev and Subsuface Util. Eno. Sam. 0 0 0 0 0 0 0 0 0 0 0 0 $10.000 $40,874 $0 $0 $0 $40,874 $50,874 8.1 8.2 Design Survev SUE (for RR and Gas Permittinq) 1 $0 $10.000 $40.874 $40,874 $40,874 $0 $10.000 9.0 Permittinq 0 52 0 40 0 0 0 0 0 0 0 0 $20.440 $0 $0 $0 $0 $0 $20,440 9.1 9.2 Railroad Crossinq Permits (2) Gas Crossinq Permit (1) 36 16 24 16 $13,560 $6,880 $0 $13,565 $0 $6.880 Additional Services (as requested and 10.0 authorized by City) Totals $0 $0 $0 $0 $0 $0 30 240 288 394 352 0 0 0 0 0 0 0 $242,380 $60,874 $20,000 $0 $1,900 $82,774 $325,154 Footage % 77Foota9DesW Flee $6.Water! 7227 92 23.005 Sewer 7"jTotal! 7100%1 329.1197 City of Fort Worth, Texas Attachment B - Level of Effort Supplement PMO Official Release Date: 5.19.2010 Water and Sewer Design Breakdown I Water Sanitary Sewer Total Cost % Complete Remaining Budget I Footaoe % $ LF % $ I TOTAL 7227 93% I $ 306.192 543I 7%1 $ 23.006 $ 329.198 01.1 $ 329.198 Pro Summa V tal Hours 1.304 Total Labor $242.380 Total ExoQpse $82,774 MWBE SubconsuNan{ �L�L Q.874 Non-MWBE Subconsu0anf $�000 5% Sub Markup ,1't�044 MWBE Partic'p lion Total Proieclf CosE. 1 .5% $329,198 2 of FORT WORTH PROJECT: CLIENT: CITY JOB # TNP JOB # ITEM ***+ t n p EXHIBIT B-3 CONCEPTUAL OPINION OF PROBABLE CONSTRUCTION COST Water and Sanitary Sewer Contract 2019, WSM-K - Amendment No. 1 City of Fort Worth 103416 FTW 21324 DESCRIPTION DATE. 8/4/2023 QTY. UNIT UNIT COST TOTAL 1 0135.0102 Railroad Flagmen 20 WD $1,000.00 $20,000.00 2 0170.0100 Mobilization 1 LS $10,000.00 $10,000.00 3 0171.0101 Construction Staking 1 LS $5,000.00 $5,000.00 4 0171.0102 As -Built Survey 1 LS $2,500.00 $2,500.00 5 0241.0100 Remove Sidewalk 180 SF $15.00 $2,700.00 6 0241.0401 Remove Concrete Drive 220 SF $20.00 $4,400.00 7 0241.1001 Water Line Grouting 260 CY $210.00 $54,600.00 8 0241.1209 24" Water Abandonment Plug 4 EA $5,000.00 $20,000.00 9 0241.1218 4%12" Water Abandonment Plug 18 EA $3,500.00 $63,000.00 10 0241.1 300 Remove Conc Curb&Gutter 370 LF $8.00 $2,960.00 11 0241.1302 Remove 6" Water Valve 8 EA $230.00 $1,840.00 12 0241.1303 Remove 8" Water Valve 4 EA $375.00 $1,500.00 13 0241.1305 Remove 12" Water Valve 3 EA $500.00 $1,500.00 14 0241.1354 Salvage 24" Water Valve 4 EA $1,500.00 $6,000.00 15 0241.1510 Salvage Fire Hydrant 4 EA $650.00 $2,600.00 16 0241.2001 Sanitary Line Grouting 4 CY $190.00 $760.00 17 0241.2102 6" Sewer Abandonment Plug 2 EA $1,000.00 $2,000.00 18 0241.2201 Remove 4' Sewer Manhole 3 EA $1,1 00.00 $3,300.00 19 0330.0001 Concrete Encase Sewer Pipe 15 CY $200.00 $3,000.00 20 3110.0101 Site Clearing 1 LS $5,000.00 $5,000.00 21 3201.0113 6' Wide Asphalt Pvmt Repair, Residential 6803 LF $80.00 $544,240.00 22 3201.0150 Asphalt Pvmt Repair, Sewer Service 20 LF $80.00 $1,600.00 23 3201.0151 Asphalt Pvmt Repair, Water Service 1000 LF $60.00 $60,000.00 24 3213.0301 4" Conc Sidewalk 180 SF $65.00 $1 1,700.00 25 3213.0401 6" Concrete Driveway 220 SF $1 10.00 $24,200.00 26 3216.0101 6" Conc Curb and Gutter 370 LF $50.00 $1 8,500.00 27 3292.0400 Seeding, Hydromulch 2405 SY $5.00 $12,025.00 28 3301.0001 Pre -CCTV Inspection 543 LF $5.00 $2,715.00 29 3301.0002 Post -CCTV Inspection 543 LF $4.00 $2,172.00 30 3301.0101 Manhole Vacuum Testing 2 EA $250.00 $500.00 31 3305.0103 Exploratory Excavation of Existing Utilities 10 EA $2,500.00 $25,000.00 32 3305.0109 Trench Safety 7757 LF $3.00 $23,271 .00 33 3305.01 10 Utility Markers(Buried) 1 LS $2,500.00 $2,500.00 34 3305.0110 Utility Markers 1 EA $500.00 $500.00 35 3305.0203 Imported Embedment/Backfill, CLSM 10 CY $110.00 $1,100.00 36 3305.1 107 42" Casing By Other Than Open Cut 240 LF $600.00 $144,000.00 37 3305.2007 24" Water Carrier Pipe 240 LF $500.00 $120,000.00 38 3311.0001 Ductile Iron Water Fittings w/ Restraint 12.6 TON $10,000.00 $1 26,000.00 39 331 1.0161 6" PVC Water Pipe 112 LF $75.00 $8,400.00 40 3311.0261 8" PVC Water Pipe 3964 LF $1 10.00 $436,040.00 41 3311.0441 12" Water Pipe 355 LF $180.00 $63,900.00 42 331 1.0641 24" Water Pipe 2783 LF $300.00 $834,900.00 43 3312.0001 Fire Hydrant 4 EA $7,500.00 $30,000.00 44 331 2.0108 Connection to Existing 24" Water Main 2 EA $10,000.00 $20,000.00 45 331 2.01 17 Connection to Existing 4"-12" Water Main 10 EA $3,500.00 $35,000.00 46 331 2.2001 1" Water Service, Meter Reconnection 71 EA $400.00 $28,400.00 47 3312.2003 1" Water Service 71 EA $2,000.00 $142,000.00 FORT WORTH #***tnp EXHIBIT B-3 CONCEPTUAL OPINION OF PROBABLE CONSTRUCTION COST PROJECT: Water and Sanitary Sewer Contract 2019, WSM-K - Amendment No. 1 CLIENT: City of Fort Worth CITY JOB # 103416 TNP JOB # FTW 21324 ITEM DESCRIPTION 48 331 2.3002 6" Gate Valve 49 331 2.3003 8" Gate Valve 50 331 2.3005 1 2" Gate Valve 51 331 2.3008 24" Gate Valve w/ Vault 52 331 2.6003 8" Blow Off Valve 53 3331.3101 4" Sewer Service 54 3331.3102 4" 2-Way Cleanout 55 3331.41 15 8" Sewer Pipe 56 3331.6101 2" Air Release Valve 57 3339.0001 Epoxy Manhole Liner 58 3339.1001 4' Manhole 59 3339.1003 4' Extra Depth Manhole 60 3339.1004 4' Shallow Manhole 61 3471.0001 Traffic Control SUBTOTAL CONTINGENCY (30%) TOTAL CONSTRUCTION COST Basis for Cost Projection: ❑✓ Conceptual Design ❑ Preliminary Design ❑ Final Design DATE. 8/4/2023 QTY. UNIT UNIT COST TOTAL 4 EA $2,500.00 $10,000.00 6 EA $3,000.00 $18,000.00 1 $8,000.00 $8,000.00 3 EA $35,000.00 $105,000.00 1 EA $28,000.00 $28,000.00 1 EA $1,000.00 $1,000.00 1 EA $500.00 $500.00 543 LF $100.00 $54,300.00 1 EA $8,000.00 $8,000.00 18 VF $18.00 $324.00 2 EA $5,500.00 $1 1,000.00 2 VF $350.00 $700.00 1 EA $6,000.00 $6,000.00 12 MO $2,000.00 $24,000.00 NOTE: OPCs reflect construction cost only (July 2023 dollars) and do not include estimates or costs for professional services & fees, environmental mitigation, nor property & easement acquisition (as well as all related costs such as appraisals, closings, building demolition &/or removal, etc.). Does not include any costs that the City may incur for the relocation of any franchise utilities that may be in conflict. $3,206,200.00 $961,900.00 $4,168,100.00 ATTACHMENT "C" CHANGES AND AMENDMENTS TO STANDARD AGREEMENT Design Services for Water and Sewer Replacements Contract 2019, WSM-K Amendment No. 1 City Project No. 103416 None. City of Fort Worth, Texas Attachment C PMO Release Date: 05.19.2010 Page I of I CITY OF FORT WORTH Water and Sanitary Sewer Replacements Contract 2019, WSM-K PROJECT NO. 103416 ID Task Name Duration Project Schedule (Working Days) CONTRACT AMENDMENT NO. 1 Start I Finish l tNl INr-r- aNU su4 aays 2 Design Engineering Agreement 35 days 3 Execute Contract Documents 50 days i ue i imiz7 rn imiz3 Mon 8/7/23 Fri 9/22/23 Fri 10/13/23 Mon 8/7/23 4 Notice to Proceed 5 Conceptual Design Phase 6 Design Kick-off Meeting 7 Design/Topographic Surveys 0 days Fri 10/13/23 Fri 10/13/23 Wed 3/6/24 98 days Fri 10/20/23 0 days Fri 10/20/23 Fri 10/20/23 35 days Thu 10/26/23 Wed 12/13/23 8 Conceptual Design (30%) Plans 9 Conceptual Design (30%) Submital 40 days Thu 12/14/23 Wed 2/7/24 Wed 2/7/24 Wed 2/7/24 0 days 10 City Review 11 Preliminary Design Phase 20 days Thu 2/8124 Wed 3/6/24 Wed 10/2/24 Wed 5/1/24 150 days 40 days Thu 317124 Thu 3/7124 12 Preliminary Design (60%) Plans 13 Preliminary Design (60%) Submittal 0 days 20 days Wed 5/1/24 Thu 5/2/24 Wed 5/29/24 Wed 5/1/24 Wed 5/29/24 Wed 5/29/24 14 City Review 15 Neighborhood Meetings 0 days 16 Utility Clearance Phase 17 RR Permit Acquisition 90 days Thu 5/30/24 Wed 10/2/24 90 days Thu 5/30/24 Wed 10/2/24 18 Final Design Phase 19 Final Design (90%) Plans 135 days Thu 5/30124 Wed 12/4/24 40 days Thu 5/30/24 Wed 7/24/24 20 Final Design (90%) Submittal 21 City Review 0 days Wed 7/24/24 Wed 7/24/24 Wed 8/21/24 20 days Thu 7/25/24 22 Final PS&E (100%) 23 City Review/Sign Cover Sheet 25 days Thu 10/17/24 Wed 11/20/24 10 days Thu 11/21/24 Wed 12/4/24 24 CONSTRUCTION 25 Bid Phase 26 Project Advertisement 1st 27 Project Advertisement 2nd 352 days Tue 12/10/24 Thu 4116/26 70 days Tue 12/10/24 Tue 12/10/24 Tue 12/17/24 Tue 3118/25 Tue 12/10/24 Tue 12/17/24 0 days 0 days 28 Pre -bid Conference 29 Open Bids 0 days Fri 12/20/24 Fri 12/20/24 0 days Tue 1/7/25 Tue 1/7/25 30 M & C Circulation Process 30 days Wed 1/8/25 0 days Tue 2/18/25 20 days Wed 2/19/25 282 days Wed 3/19125 Tue 2/18/25 31 Council Award of Contract 32 Contract Execution 33 Construction Phase Tue 2/18/25 Tue 3/18/25 Thu 4/16/26 34 Pre -Construction Meeting 35 Neighborhood Meetings 10 days Wed 3/19/25 Tue 4/1/25 10 days Wed 4/2/25 Tue 4/15/25 36 Construction 262 days Wed 4/16/25 Thu 4/16/26 2 Teague Nall and Perkins, Inc. 2023 2024 2025 20: Qtr 2 1 Qtr 3 1 Qtr 4 Qtr 1 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 r 7 S 8/7 10/13 10113 10/20 3/6 10/20 10/26 ME 12/13 12/14 2/7 2/7 2/8 3/6 3/7 10/2 3/7 5/1 511 512 5129 5/29 5130 10/2 5/30 10/2 5/30 1214 5/30 7/24 7/24 7/25 8/21 10/17 IM 11/20 11/21 ® 12/4 12/10 4/16 12/10 3/18 12/10 12/17 12/20 1/7 1/82/18 2/18 2119 3/18 3119 4/16 3/19 ® 411 4/2 (0) 4/15 4/16 4/16 ATTACHMENT E City of Fort Worth, Texas Mayor and Council Communication DATE: Tuesday, October 31, 2023 LOG NAME: 60WSSC19WSMKAl-TNP REFERENCE NO.: **M&C 23-0912 SUBJECT: (CD 9) Authorize Execution of Amendment No. 1 in the Amount of $329,198.00 to an Engineering Agreement with Teague Nall and Perkins Inc, for the Water and Sanitary Sewer Replacement Contract 2019, WSM-K, and Adopt Appropriation Ordinance to Effect a Portion of Water's Contribution to the Fiscal Years 2024-2028 Capital Improvement Program RECOMMENDATION: It is recommended that the City Council: Authorize execution of Amendment No. 1 in the amount of $329,198.00, to City Secretary Contract No. 56846, an engineering agreement with Teague Nall and Perkins Inc, for the Water and Sanitary Sewer Replacement Contract 2019, WSM-K project for a revised contract amount of $517,264.00; and Adopt the attached Appropriation Ordinance increasing estimated receipts and appropriations in the Water and Sewer Capital Projects Fund in the amount of $329,198.00, transferred from available funds within the Water and Sewer Fund, for the purpose of funding the Water and Sanitary Sewer Replacement Contract 2019, WSM-K project (City Project No. 103416) and to effect a portion of Water's contribution to the Fiscal Years 2024-2028 Capital Improvement Program. DISCUSSION: On November 9, 2021, Mayor and Council Communication (M&C) (21-0875), the City Council authorized an engineering agreement in the amount of $188,066.00 with Teague Nall and Perkins Inc, (City Secretary Contract No. 56846) for the Water and Sanitary Sewer Replacement Contract 2019, WSM-K project. Amendment No. 1 will provide for additional survey and design for the replacement or relocation of the cast iron water mains water along with deteriorated sanitary sewer mains on the following streets located in close proximity to the original project: Street 11 To Ryan Avenue IDickson Street West right of way Dickson Street line of BNSF Railroad Biddison Ryan Avenue Street Ripy Street IRyan Avenue James Avenue Dickson Street Easement east Biddison Street of BNSF From 11 Scope Biddison Street IlWater Ryan Avenue Water 130 feet west Water IlEast 550 feet IlWater/Sewer North 210 feet then Water northeast 250 feet North 190 feet then Water east 210 feet As part of this project, the existing 24-inch cast iron water main located along the west right -of -way line of Burlington Northern and Santa Fe Railroad (BNSF) is to be abandoned and a new 24-inch main will be constructed in Dickson Street, Ryan Avenue and Biddison Street as shown on the attached Mayor and Council location map. It is the practice of the Water Department to appropriate its CIP plan throughout the Fiscal Year, instead of within the annual budget ordinance, as projects commence, additional funding needs are identified, and to comply with bond covenants. The actions in the M&C will appropriate funds in support of the Water's portion of the City of Fort Worth's Fiscal Years 2024-2028 Capital Improvement Program, as follows: 60WSSC19WSMKAl -TNP Capital project FY2024 CIP Budget Change Revised Fund Name Appropriations Authority (Increase/Decrease) FY2024 Name Budget Fund W/SS 56002- REPL W&S Contract $0.00 This M&C $329,198.00 $329,198.00 Capital 2019 Projects WSM-K Funding is budgeted in the Transfer to Water/Sewer account of the Water and Sewer operating budget for the purpose of funding the Water and Sanitary Sewer Replacement Contract 2019, WSM-K project. Appropriations for Water/Sanitary Sewer Replacement project are as depicted below: Fund Existing Additional Project Appropriations Appropriations Total* W&S Capital Projects - Fund $333,054.00 $329,198.00 $662,252.00 56002 Project Total $333,054.00 $329,198.00 $662,252.00 *Numbers rounded for presentation purposes. Business Equity: Teague Nall and Perkins, Inc. agrees to maintain its initial M/WBE commitment of 10 percent that it made on the original agreement and extend and maintain that same M/WBE commitment of 10 percent to this first amendment. Therefore, Teague Nall and Perkins, Inc. remains in compliance with the City's M/WBE Ordinance and attests to its commitment by its signature on the Acceptance of Previous M/WBE Commitment form executed by an authorized representative of its company. This project is located in COUNCIL DISTRICT 9. FISCAL INFORMATION / CERTIFICATION: The Director of Finance certifies that funds are currently available in the Water & Sewer Fund and upon approval of the above recommendations and adoption of the attached appropriation ordinance, funds will be available in the W&S Capital Projects Fund, for the W/SS REPL Contract 2019 WSM- K project. Prior to any expenditure being incurred, the Water Department has the responsibility to validate the availability of funds. FUND IDENTIFIERS (FIDs): TO Fund Department Account Project ProgramActivity Budget Reference # Amount ID ID Year (Chartfield 2) FROM Fund Department Account Project ProgramActivity Budget Reference # Amount ID ID Year (Chartfield 2) CERTIFICATIONS: Submitted for Citv Manager's Office bv: Dana Burghdoff (8018) Originating Department Head: Chris Harder (5020) Additional Information Contact: Dena Johnson (7866) ATTACHMENTS 1. 60WSSC19WSMKA1-TNP APC Form.pdf (CFW Internal) 2. 60WSSC19WSMKA1-TNP FID Table (WCF 09.26.23).xlsx (CFW Internal) 3. 60WSSC19WSMKA1-TNP Form 1295.pdf (CFW Internal) 4. 60WSSC19WSMKA1-TNP.docx (CFW Internal) 5. Entitvinformation Teaaue Nall & Perkins. pdf (CFW Internal) 6. M&C Map.pdf (Public) 7.ORD.APP 60WSSC19WSMKA1-TNP 56002 A024(r2).docx (Public) 8. PBS CPN 103416.pdf (CFW Internal) 60WSSC19WSMKAl-TNP FID Table 2 56002 0600430 103416 2024 $306,192.00 2 56002 0700430 4956001 103416 2024 $23,006.00 2 56002 0700430 103416 2024 $23,006.00 2 56002 0600430 4956001 103416 001730 9999 ($306,192.00) 2 56001 0709020 5956001 $23,006.00 2 56002 0700430 4956001 103416 001730 9999 ($23,006.00) 56002 56002 0600430 5330500 103416 0700430 5330500 103416 001730 001730 9999 9999 $306,192.00 To pay contract $23,006.00 To pay contract