HomeMy WebLinkAboutContract 57694-CO3PROJECT NAME:
CONTRACT:
CFA #
CITY PROJECT #
FID #
FILE #
INSPECTOR:
PROJECT MANAGER:
ORIGINAL CONTRACT
EXTRAS TO DATE
CREDITS TO DATE
CONTRACT TO DATE
AMOUNT OF PROP. CHANGE ORDER
REVISED CONTRACT AMOUNT
TOTAL REVISED CONTRACT
AMOUNT PER UNIT
REVISED COST SHARE
TOTAL REVISED CONTRACT
DEVELOPER -AWARDED -PROJECT CHANGE ORDER
Water Drainage, Paving, & Street Light Improvements to Serve Chisolm Trail Ranch NORTH BOUND CHANGE
CS 57694 ORDER No:
CFA21-0119 CITY PARTICIPATION:1 Yes
103435
3
30114-0200431-103435-EO7685
X-26971, K-2845
Jesse Davis
Debbie Willhelm
Phone No:
Phone No:
WATER
STORM
Developer Cost
$ 87,070.00
$ 3,600.00
$ -
$ 90,670.00
$ 90,670.00
City Cost
Developer Cost
$ 1,444,041.00
$ 49,413.00
$ -
$ 1,493,454.00
$ 1,493,454.00
$ 56,640.00
$
$ -
$
6 (3,600.00)
$
$ 53,040.00
$
$ 53,040.00
$
$ 143,710.00 $
Dev. Cost:
817-863-3705
817-392-2481
CSC No. 57694-CO3
CONTRACT UNIT
PAVING STREET LIGHTS SEWER
:ity Cost
Developer Cost
$ 1,446,223.64
$ -
$ -
$ 1,446,223.64
$ -
$ 1,446,223.64
$
City Cost Developer Cost
$ 218,143.85 $ 77,160.40
$ 212,450.15 1 $ -
$ - I $ -
$ 430,594.001 $ 77,160.40
$ - I $ (18,314.40)
1 $ 430,594.00 $ 58,846.00
1,876,817.64 $
City Cost Developer Cost
$ 2,440.001 $ -
$ 25,925.601 $ -
$ - I$ -
$ 28,365.60I $ -
$ 18,314.401 $
$ 46,680.001 $
105,526.001 $
68,223.00
$
-
-
68,223.00
$
-
$
68,223.00
$
1,561,677.00
$3,089,193.64
City Cost:
$3,687,730.64
$598,537.00
CONTRACT
DAYS
Cost
180
30
- 210
0
210
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
You are directed to make the following changes in the contract documents:
CITY BID ITEM
PAY ITEM #
#
QUANTITY
UNIT
ITEM DESCRIPTION
UNIT PRICE I
Developer Cost
City Cost
Unit IV: STREET LIGHTING IMPROVEMENTS
3
3441.1645
-2016
LF
No. 2 Insulated Elec Condr
$ 8.00
$
(16,128.00)
$
-
10
9999.0008
-3644
LF
Salvage and Reinstall Existing Conductor
$ 0.60
$
(2,186.40)
$
-
3
3441.1645
2016
LF
No. 2 Insulated Elec Condr
$ 8.00
$
-
$
16,128.00
10
9999.0008
3644
LF
Salvage and Reinstall Exisitng Conductor
$ 0.60
$
-
$
2,186.40
Unit IV TOTAL
Subtotal Unit IV - Street Lighting Improvements
$
(18,314.40)
$
18,314.40
GRAND TOTAL
1
$
(18,314.40)1
$
18,314.40
Asterisk (*) indicates New Pay Item
REASONS FOR CHANGE ORDER: 1. Reconcile Error on Change Order 2. Two of the street lighting quantities should've been deducted from Developer's cost instead of City's cost.
CITY FUNDS ARE INVOLVED ON THS CONTRACT. DEVELOPER WILL BE RESPONSIBLE FOR-$18,314.40 AND CITY WILL BE RESPONSIBLE FOR $18,314.40 FOR THIS CHANGE
ORDER. NET AMOUNT FOR CHANGE ORDER 2 IS ZERO.
[SIGNATURES APPEAR ON THE FOLLOWING PAGE]
RECOMMENDED:
Dunaway Associates, LLC
_,70Sh WY At
Josh Wright, PE (Oct 5, 202311:21 CDT)
By:
Name: Josh Wright, PE
Title: Project Engineer
APPROVAL RECOMMENDED:
CFW - Development Services Department
By:
Name: Tyson W. Thompson
Title: Assistant Development Services Director
RECOMMENDED:
CFW - *Contract Compliance Manager
7Ja66ri � G!%u�,ht
By:
Name: Debbie J. Willhelm, PE
Title: Senior Professional Engineer
M&C Number: M&C 22-0256
M&C Date Approved: 4/12/2022
APPROVED:
Legacy CTW, LP
By:
Name: Steve Saxon
Title: Manager
APPROVED:
CFW - Assistant City Manager
bwt.v B�u^g�cr%
By:
Dana Burghdoff (No�i4, 2023`2 :04 CST)
Name: Dana Burghdoff
Title: Assistant City Manager
ATTEST:
<� on°r°o9yP
Of8 .1P
By:
Name: Jannette S. Goodall
Title: City Secretary
APPROVED:
McClendon Construction, Inc
ate,
By:
Name: Justin Blair
Title: VP of Project Management
APPROVED AS TO FORM AND LEGALITY:
CFW - Assistant City Attorney
By: Richard A. McCracken (Nov 14, 202318:15 CST)
Name: Richard McCracken
Title: Senior Assistant City Attorney
* Contract Compliance Manager (Project Manager):
By signing I acknowledge that I am the person responsible
for the monitoring and administration of this contract, include
ensuring all performance and reporting requirements.
[ ] There are NO City Funds associated with this Contract
[ X ] There are City Funds associated with this Contract