Change Order Request
Project Name:I Village Creek WRF Digester Mixing, Flare, Dome Improvements Phase 1
City Sec No.: 1 58683
Project No.(s):
I M&C: 1 22-1046
CityProj. No.: l 102652
Project Description:) Digester mixing, flare, and
dome improvements, new digeseter gas dryers, and new hydrogen sulfide scrubbers.
Contractor: Eagle Contracting, LLC
Change Order#
1 1 Date: 11/21/2023
City Project Mgr. l Suzy Abbe
City Inspector:
Nathan Gray
Phone Number: 817-392-8209
Phone Number:
817-991-0629
Dept.
Sewer
Totals Contract Time
(Calender days)
Original Contract Amount
$39,773,000.00
$39,773,000,00 1,095
Extras to Date
Credits to Date
Pending Change Orders (in M&C Process)
Contract Cost to Date
$39,773,000.00
$39,773,000.00 1,095
Amount of Proposed Change Order
$13,120.00
$13,120.00 0
Revised Contract Amount
$39,786,120.00
$39,786,120.00 1,095
Original Funds Available for Change Orders
$318,184.00
$318,184.00
Remaining Funds Available for this CO
$318,184.00
$318,184.00
Additional Funding (if necessary)
CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT
0.03%
MAXALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST+ 259o) $49,716,250.00
JUSTIFICATION (REASONS) FOR CHANGE ORDER
Change Order No. 1 provides for the following:
Rerouting an 8" digested sludge line that was in conflict with the foundation of the 1-12S scrubbers (CMR-02).
Additional excavation and concrete encasement of an existing, shallow 24" drain line under digester mixing pad no. 5 (CMR-03).
Relocation of mixing pad no. 3 following excavation and utility locates at the original location. The cost of the relocation includes excavating
at the new location (CMR-04) and backfilling and paving restoration at the original location (CMR-07).
Replace door hardware with panic hardware (CMR-06).
Additional length of stainless steel pressure sensing tubing to reduce pressure swings when gas begins flaring (CMR-08). The change will
reduce the duration of sludge surging when the flares turn on.
Replace 5700 SF of asphalt with concrete paving and eliminate concrete cap over 30" HDPE low pressure gas line (CMR-11). Installation
of the 30" HDPE pipe required a wider trench than anticipated with certain areas requiring excavation of the full width of the street. The plans
called for permanent trench repair with a concrete cap, which did not work based on the level of excavation needed to install the pipe.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment
in full (both time and money) for all costs arising out of, or incidental to, the above Change Order.
Contractor's Company Name I Contractor NameI Contractor Signature I Date
Eagle Contracting, LLC Victor Dorantes
Inspector
Director (Water Dept)
Ch!a�-ooher Harder
Senior Assistant City Attorney
M&C Number I N/A
Date
Project Manager
Date
11 /21 /23ti
3
'wL"Date
CoLstr,ction Supervisor (Water Dept)
Date Iq
Nov 29, 2023
Date
Assistant City Manager
Date
Nov 29, 2023
�I
Nov 29, 2023
Council Action
(If Required) "
OFFICIAL RECORD
M&C Date Approved I N/4—
CITY SECRETARY
FT. WORTH, TX
FORT WORTH City of Fort Worth
'
Change Order Additions
Project Name
Village Creek WRF Digester Mixing, Flare, Dome Improvements Phase 1
City Sec No.:
58683
Project No.(s):
I
DOE No.1 22-104q
City Proj. No.:
102652
Project
Description
Digester mixing, flare, and dome improvements, new digeseter gas dryers,
and new hydrogen sulfide
scrubbers.
Contractor
Eagle Contracting, LLC Change Order: 0
Date: 1 11/21/2023
City Project Mgr,
Suzy Abbe City Inspector I Nathan Gray
ADDITIONS
I I tM
DESURIP I IUN DEPT
Qty Unit
Unit Cost
Total
24 CMR-02 reroute 8" digester sludge pipe Sewer
1.00 LS
$14,730.00
$14,730.00
25 CMR-03 -
concrete encase 24" storm drain at mixing pad no. 5 Sewer
1.00 LS
$46,888.00
$46,888.00
26 CMR-04 -
excavation for mixing pad no. 3 at new location Sewer
1.00 LS
$15,894.00
$15,894.00
27 CMR-06 -
furnish door panic hardware Sewer
1.00 LS
$631.00
$631.00
28 CMR-07 -
backfill and pavement restoration at original mizing pad no. 3 locati Sewer
1.00 LS
$9,353.00
$9,353.00
29 CMR-08 -
additional length of pressure sensor tubing at flares Sewer
1.00 LS
$546.00
$546.00
31 CMR-11 -
replace 5700 SF of asphalt paving with concrete paving Sewer
1.00 LS
$20,078.00
$20,078.00
Sewer $108,120.00
Page 1 of 1 lAdditions Sub Total $108,120.00
FORT WORTH
City of Fort Worth
Change Order Deletions
Project Name Village Creek WRF Digester Mixing, Flare, Dome Improvements Phase 1
City Sec No.: 58683
Project No.(s):
I DOE No. I 22-104
City Proj. No.: I 102652
Project Description
I Digester mixing, flare, and dome improvements, new digeseter gas dryers, and new hydrogen
sulfide scrubbers.
Contractor I Eagle Contracting, LLC
Change Order: F1 I
Date I 11/21/2023
City Project Mgr. I Suzy Abbe
City Inspector: I Nathan Gray
DELETIONS
ITEM DESCRIPTION
DEPT Qty Unit
Unit Cost Total
22 Utility Relocation Allowance
Sewer 1.00 LS
$50,000.00 $50,000.00
23 Construction Allowance
Sewer 0.30 LS
$150,000.00 $45,000.00
Sewer $95,000.00
Page 1 of 1 Deletions Sub Total $95,000.00
MIWBE Breakdown for this Change Order
MWBE Sub Type of Service Amount for this CO
Total $0.00
Previous Change Orders
CO# DATE AMOUNT
Total $0.00
Page 1 of 1
Contract Compliance Manager
By signing I acknowledge that I am the person responsible
for the monitoring and administration of this contract, including
ensuring all performance and reporting requirements.
Signature
Suzanne Abbe
Name of Employee
Senior Engineer, Capital Project Delivery
Title
4,d-p94�n�
as P
a> F°°°�Rtoo
o o
ATTEST: c°~° ° 9�dd
o o=d
pPa °o�
a
rEXoti
�baa�44
Jannette Goodall
City Secretary
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
11/17/2023
CPN 102652
Digester Mixing, Flare, Dome Improvements Phase 1
Change Order 1 Notes
Change Order No. 1 provides for the following:
• Rerouting an 8" digested sludge line that was in conflict with the foundation of the H2S
scrubbers (CMR-02). The line was not shown on the plans. The cost includes repairing the
ruptured line prior to rerouting.
• Additional excavation, bracing, and concrete encasement of an existing, shallow 24" drain line
under digester mixing pad no. 5 (CMR-03).
• Relocation of mixing pad no. 3 due to utility conflicts at the original location. The cost of the
relocation includes excavating at a new location (CMR-04) and backfilling and paving restoration
at the original location (CMR-07).
• Replace door hardware with panic hardware (CMR-06).
• Additional length of stainless steel pressure sensing tubing to reduce pressure swings when gas
begins flaring (CMR-08). The change will reduce the duration of sludge surging when the flares
turn on.
• Change 5700 SF of asphalt paving to concrete paving and eliminate concrete cap over 30" HDPE
low pressure gas line (CMR-11). Installation of the 30" HDPE pipe required a wider trench than
anticipated with certain areas requiring excavation of the full width of the street. The plans
called for permanent trench repair with a concrete cap, which did not work based on the level of
excavation needed to install the pipe.
Labor hours, material costs, and quantities in the contractors' proposal were reviewed. Approved
CMR's are saved in BIM 360. A summary of the negotiation is provided in Table 1. Contract time was
not added because the additional work was not on the critical path.
Table 1: Change Order 1 Negotiated Price
CMR
Days
Original Proposal
COF Counter
Approved Price
CMR-02
0
$
21,892.00
$
12,080.00
$
14,730.00
CMR-03
0
$
57,192.00
$
43,610.00
$
46,888.00
CMR-04
0
$
19,009.00
$
11,280.00
$
15,894.00
CM R-06
0
$
631.00
$
631.00
$
631.00
CMR-07
0
$
11,222.00 I
$
8,588.00
$
9,353.00
CMR-08
( 0
$
546.00 I
$
546.00
$
546.00
CMR-09*
I 0
( $
28,212.00 I
$
-
$
-
CMR-11
I 0
I $
20,078.00
$
20,078.00
$
20,078.00
Total
I 0
I $
158,752.00
$
96,813.00
$
108,120.00
*CMR 9 was developed to capture
the cost
of the redesign of Mixing Pump
Pad No. 3 and concrete
encasement of 10" line under the pad. It
was determined upon
review that
the cost of the redesign would
involve
a credit based on a
reduced
concrete quantity. The credit will be
captured in a later
change order once
adjustments
for all of the mixing
pads are captured. The
contractor waived the cost of the concrete
encasement due to issues with installation.